Case details

Court: nynd
Docket #: 1:10-cv-00581-GLS -ATB
Case Name: Cellco Partnership v. Town of Colonie, New York et al
PACER case #: 80878
Case Cause: 47:332 Telecommunications Act of 1996.
Nature of Suit: Other Statutory Actions

Documents

Date Filed Document # Attachment # Short Description Long Description Upload date SHA1 hash
2011-11-29 27 0 MEMORANDUM-DECISION and ORDER - That Verizons motion for summary judgment (Dkt. No. 18) is GRANTED. That the Planning Boards July 29, 2010 decision is Vacated. That the Town shall, within thirty (30) days of this order, approve Verizons Minor SPR a pplication, and grant all permits, licences and/or approvals necessary to effectuate the construction of the bell tower. That Verizon will update the court via letter filing when the Town has complied with the courts order. That if the Town fails to comply with the courts order within thirty (30) days, Verizon may seek to either reopen the case, and/or sanctions against the Town. Signed by Judge Gary L. Sharpe on 11/28/2011. (jel, ) 2011-11-29 09:49:46 641ee4e4de96bcb2b47b153dcbbd89a895266fcf