3 1223 06446 4663
Sjs
San Francisco Public Library
Qr /srnment Information Center
San Francisco Public Library
1C0 Larkin Street, 5th Floor
San Francisco, CA 94102
REFERENCE BOOK
Not to be taken from the Library
Digitized by the Internet Archive
in 2013
http://archive.org/details/3annualreportsanf
>
U1
^
JfcL
\ ix ~- —
jfflBiw
—
i
"**-
3tK
1
S^f
3,
.1974 AN»iUA4\REP0RT 1975
HETCH HETCHY WtTER AND POWER
PUBLIC UTILITIESC0MMIS5 ON
CITY AND COUNTY OF SAN FRANC SCC
3 1223 06446 4663
CITY AND COUNTY OFJ5AN FRANCISCO
JOSEPH L. ALIOTO - MAYOR
PUBLIC UTILITIES COMMISSION
H. WELTON FLYNN
JOSEPH P. BYRNE
OLIVER M. ROUSSEAU
JOSEPH J. DIVINY
HENRY E. BERMAN
JOHN D. CROWLEY
President
Vice President
Commissioner
Commissioner
Commissioner
General Manager
ANNUAL REPORT
FISCAL YEAR 1974-75
HETCH HETCHY WATER AND POWER DEPARTMENT
ORAL L. MOORE - General Manager
This report is respectfully dedicated to
Hetch Hetchy employees, past and present,
whose devoted and conscientious efforts have
made possible these accomplishments for
San Francisco.
2 50354 SFPL= ECONO JRS
58 SFPL 05/07/04
LAKE ELEANOR AND LAKE
LLOYD/CHERRY DAM (foreground)
HIGHLIGHTS - 1974-75
For Hetch Hetchy, fiscal year 1974-75 has been a record year in
many ways. The heavy rainfall and snow on the Tuolumne River
Watershed during the past two years have brought higher-than-
normal inflows. With all project reservoirs assured of filling
and spilling, our efforts were bent on channeling the maximum
available water for electric power production and on minimizing
spill after the reservoirs have been filled. The success of
these efforts is shown by department's electric system output
of 2,057,609,000 kilowatthours for 1974-75, a new record for
total project hydroelectric generation for one fiscal year.
1 -
During the year, Hetch Hetchy furnished 588,989,569 kilowatthours
to seven industrial customers located in Alameda, Santa Clara
and Stanislaus Counties, for a revenue of $7.9 million. Both
sales and revenue represent records unmatched in Hetch Hetchy' s
history. The impact of the revenue becomes even more dramatic
when it is shown that the same number of kilowatthours sold to
these customers in fiscal year 1969-70 would have returned little
more than half as much revenue.
The record generation and the high industrial power rates combined
have boosted the department's total revenue from sale of electric
energy to a new high of $18.5 million in 1974-75, an increase of
$4.5 million over the last fiscal year. Compared with the previous
high of $15.0 million for fiscal year 1970-71, the increase is
still a sizable $3.5 million.
Surplus earnings enabled the department to make available $1.0
million to the City's general fund in 1974-75, hopefully marking
the beginning of many such contributions.
Negotiations to extend the March 14, 1945 "Main Contract" between
PGandE and City beyond the expiration date of July 31, 1975 were
concluded with the execution of an amendment agreement dated
June 24, 1975. This contract covers, among other things, the
services which the Company performs in wheeling Hetch Hetchy
energy to City's municipal consumers in and out of San Francisco.
Through bargaining based on the cost-of-service principle and on
the changes in conditions incident to wheeling of Hetch Hetchy
power by Company over the last three decades, City negotiators
were able to obtain for the City prospective annual net savings
in the amount of $290,000.
2 -
HETCH HETCHY ORGANIZATION AND FUNCTIONS
Under policies established by the San Francisco Public Utilities
Commission, the HETCH HETCHY WATER AND POWER DEPARTMENT and the
BUREAU OF LIGHT, HEAT AND POWER serve the City and County of
San Francisco in the dual function of operating department and
service bureau.
Hetch Hetchy* is a municipally-owned system of storage reservoirs
and aqueducts which collects water from the Tuolumne River water-
shed and delivers it to the San Francisco Water Department. As
a by-product of falling water, Hetch Hetchy operates and maintains
hydroelectric generating stations and high voltage transmission
lines for the production and distribution of electric energy.
Through its Transit Power Division, Hetch Hetchy has funded,
operated, maintained and provided improvements for the electric
facilities of the San Francisco Municipal Railway since July 1,
1969.
All of Hetch Hetchy' s expenses, including those of the Transit
Power Division, are supported by water and power revenues.
NEW MOCCASIN POWERHOUSE AND PENSTOCK
* Hetch Hetchy is an Indian name for the valley in the
Sierra where the Department's first dam was built.
The Bureau of Light, Heat and Power administers contracts for
furnishing electric, gas and steam services to municipal depart-
ments and handles monthly billings. It also administers contracts
for furnishing street lighting services and for operation and
maintenance of City-owned street lighting. Financing, design
and construction of City-owned street lighting improvements are
under the jurisdiction of the Department of Public Works, and
plans for these improvements must be approved by the Public
Utilities Commission through this Bureau. The Bureau is financed
by appropriations from municipal departments and gas tax funds.
For fiscal year 1974-75, the Department administered budgeted
funds for all purposes as follows:
Budget
Hetch Hetchy Water and Power
Number of
Employees
199
Total Amount
Appropriated
$ 18,695,408
Hetch Hetchy Water and Power
(Transit Power Division)
Bureau of Light, Heat and Power
52 2,968,471
11 7,747,732
262 $ 29,411,611
4 -
HETCH HETCHY WATER AND POWER SYSTEM
REVENUES AND EXPENDITURES
Revenue from Hetch Hetchy Water and Power operations is derived
principally from two sources:
1. Sale of electric power and energy to San Francisco Municipal
departments, Modesto and Turlock Irrigation Districts in the
San Joaquin Valley, and seven industrial customers:
Kaiser Cement and Gypsum Corporation
Kaiser Aluminum § Chemical Corporation
Lockheed Missiles and Space Company, Inc.
General Motors Corporation
IBM Corporation
Liquid Air, Inc.
Norris Industries, Riverbank
Santa Clara County
Santa Clara County
Santa Clara County
Alameda County
Santa Clara County
Alameda County
Stanislaus County
2. Sale of water to the San Francisco Water Department.
This past year, revenue from sale of water and standby service
to the San Francisco Water Department was $6,500,000.
Gross sale of electric energy amounted to $18,484,718 compared to
$14,104,677 during the year 1973-74. This increase in electric
revenue in part reflected the increase in actual sales during the
year; 2,025,074,464 kilowatthours as compared to 1,823,491,146
kilowatthours for 1973-74.
MOCCASIN AUTOMOTIVE SHOP
WITH SNO-CAT
(L TO R) DICK WHITE, Gen.
Util. Mech.; WARREN WOOLEY,
Gen Util. Mech; KEN BLAU,
Auto Serviceman
WATER REVENUE $ 6,500,000
MISCELLANEOUS REVENUE
$ 14 4, 126
PO
WER REVENUE $18,484,718
TOTAL $25,128,844
HETCH HETCHY REVENUES
FISCAL YEAR I 974 -75
PURCHASED POWER
$ 135 , 38 9
TAXES
$4 98, 0 15
CAPITAL
I M PROVEMENT
HETCH HETCHY
PROJECT
$ 1,640 , 500
CAPITAL
IMPROVEMENT
TRANSIT POWER
DIVISION
$ 1,2-19, 700
BOND INTEREST AND
REDEMPTION $9,077,334
ADMINISTRATION
OPERATION 8
MAINTENANCE
TRANSIT POWER
DIVISION
$1,518,786
SERVICE CHARGE
FOR POWER
TRANSMISSION
AND DISTRIBUTION
$ 2, 309, 68 7
ADMINISTRATION
OPERATION AND
MAINTENANCE
HETCH HETCHY
PROJECT $ 4,129 , 922
EXCESS OF REVENUE
OVER EXPENDITURES
$4,599,511
TOTAL $ 25,128,844
HETCH HETCHY EXPENDITURES
FISCAL YEAR I 974 -75
POWER SALES
Power and energy delivered to all City Departments decreased 0.31
over the previous year, totally the result of reduced consumption
at the San Francisco International Airport. The Airport, usually
the single biggest energy consumer of the City departments,
contributed significantly to the overall result with a 4.4%
reduction, while all other City Department showed increases varying
from 0.71 for street lighting to as much as 8.9% for the San
Francisco Water Department, principally for pumping load.
Hetch Hetchy power is sold to City Departments at cost, representing
a saving to taxpayers for 1974-75 of approximately $4 million
compared to the cost if supplied by the local investor-owned
utility at current rates which are more than 50% higher than those
if effect some four years ago because of continued escalation in
fuel prices.
Power and energy delivered to
Modesto Irrigation District,
Hetch Hetchy 's largest power
customer, and to Turlock
Irrigation District, the third
largest, decreased by 7.71 and
27.61 respectively this year.
The reason for the Districts'
decrease is due largely to the
fact that more than normal gen-
eration was available from their
own generating plants because
of the increased water storage
behind Don Pedro Dam resulting
from three successive above-
normal-precipitation years. The
effect of Don Pedro storage on
each of the two Districts is
different. It has less effect
on Modesto's purchase, since
Modesto normally generates less
than 20% of its total load require
ments. Turlock's own generation
in 1974-75 accounted for nearly
70% of its total requirements,
MOCCASIN SWITCHYARD which is about two-thirds of
AND PENSTOCK Modesto's.
Gross sale of electric energy amounted to $18,484,718 compared to
$14,104,677 during 1973-74. This record increase in revenue can
be attributed to three reasons: (1) As a result of higher-than-
normal precipitation on the Tuolumne River watershed the past two
years, total electrical generation of the Hetch Hetchy powerhouses
increased from 1,992,850,000 kilowatthours in fiscal year 1973-74
to 2,057,609,000 kilowatthours in fiscal year 1974-75, an increase
of 3.25 percent. This establishes a new record for total project
electrical generation for one fiscal year. (2) The withdrawal
of 123,458,969 kilowatthours of electrical energy which was deposited
the previous year under City's "banking" arrangement with the Pacific
Gas and Electric Company and (3) The sale to industrial customers
at the high PGandE rates of 567,294,414 kilowatthours of energy,
an increase of 2 1/2 times as compared to 227,596,800 kilowatthours
for 1973-74.
Another favorable effect of the record generation is the decrease
in expenditure for supplementary power and energy from $447,270
to $99,734.
In order to guarantee a market for the large quantity of excess
energy which was deposited with the Company in 1973-74 and which
would be withdrawn this year, the Pacific Gas and Electric Company
assigned to the City, as a temporary accommodation, four additional
industrial customer loads during the year, namely: Liquid Air, Inc.
in Union City under an agreement dated August 12, 1974, Lockheed
No. 2 in Sunnyvale, General Motors Corporation in Fremont and IBM
Corporation in San Jose, all under individual agreements dated
September 10, 1974.
October 29, 1974 marked the beginning of negotiations with the
Pacific Gas and Electric Company for extension of the March 14,
1975 "Main Contract" between the Company and the City and County
of San Francisco. This contract, which expires July 31, 1975,
covers such items as the wheeling of Hetch Hetchy power to the
City's municipal customers, and the furnishing of supplementary
energy and standby service to the City. These negotiations
entail extensive review and analysis of the cost of service to
various municipal loads. In order to assist and advise the Hetch
Hetchy staff in these negotiations, the Public Utilities Commission
authorized the employment of an expert consultant, Mr. Roy A. Wehe.
After seven months of fruitful exchanges, negotiations were sat-
isfactorily concluded with the execution of an amendment agreement
on June 24, 1975. These negotiations have resulted in prospective
annual net savings to the City for wheeling charges in the amount
of at least $290,000.
9 -
On May 27, 1975, the San Francisco Public Utilities Commission
adopted a new set of rate schedules for the sale of Hetch Hetchy
power to private consumers and the Municipal Departments of the
City, replacing a similar set which had been in effect since
July 1, 1958. At about the same time, a staff study to determine
the cost to serve the City departments was also made. It was
found that based on test year 1973-74, a zero discount applied to
billings for energy supplied to the San Francisco International
Airport for resale to its tenants and a 45.5% discount to billings
for energy supplied to City Departments for Municipal purposes
would permit the recovery of cost. It is estimated that beginning
July 1, 1975, the change in rates together with the change in
discounts for the City dppartments will increase Hetch Hetchy' s
annual power revenue by one million dollars.
- 10
? o
1 s
0 -
n _
I I I I I I I I I I I
1965 1966 1967 1968 1969 1970 1971 1972 1973 1974 1975
( Year Ending June 30)
REVENUE FROM SALE OF ELECTRIC ENERGY
I I I I I I I I I I
1965 1966 1967 1968 1969 1970 1971 1972 1973 1974
( Year Ending June 30)
HETCH HETCHY POWER SYSTEM OUTPUT
WATER PRODUCTION AND TRANSMISSION
Precipitation recorded for the year at our measuring stations was
1071 of the long term average.
During the year, 80,321,370,000 gallons of water were diverted
from the Tuolumne River watershed through the Hetch Hetchy Aqueduct
to the San Francisco Water Department, representing 86% of the
City's total customer consumption. In addition, 236,999,312
gallons were delivered to the United States Atomic Energy Commission
at Mocho Shaft of the City's Coast Range Tunnel for use at the
Lawrence Radiation Laboratory at Livermore; 49,229,620 gallons
were delivered to Groveland Community Service District in Tuolumne
County from the Mountain Tunnel.
Appendix Table 6 shows comparative data on precipitation, runoff,
storage and delivery of the Hetch Hetchy Water Supply System.
- 13
300 ,000 "4
200, 000
w l 00,000— [
LlI
DELIVERIES OF WATER TO
SAN FRANCISCO WATER DEPARTMENT
OPERATION AND MAINTENANCE - MOCCASIN DIVISION
Holm Powerhouse Unit No. 2 Generator
The No. 2 generator at Dion P. Holm Powerhouse was shut down by
protective relays at 6:26 p.m. on Sunday, January 5, 1975, indi-
cating a failure to ground in the stator winding. Immediate
preliminary investigation established that the fault was confined
to Phase C of the 3-phase winding. The following day it was
determined that the fault was limited to a single coil in a slot
location that was readily accessible. It was also determined
that bypassing the defective coil and then restoring the circuit
continuity would be a simple solution, one that would not affect
the operation of the generator adversely. An Allis-Chalmers
Corporation factory engineer was contacted and repair efforts
were begun. The repairs were made by departmental forces under
the supervision of the Allis-Chalmers representative and the
unit was restored to service on the following Sunday, January
12, 1975. The total outage of the unit was therefore limited to
only one week by the fortunate location of the fault and swift,
concentrated efforts by departmental personnel.
MOCCASIN ELECTRIC SHOP
CL TO R) HAROLD SCOTT
DON ANDERSON - Elect. ;
HERB SWANSON - Lineman
Elect
- 15 -
Kirkwood Powerhouse Unit No. 1 Power Transformer
The Kirkwood Powerhouse Phase B transformer for Unit No. 1 that
failed on January 3, 1974, was repaired, tested and returned
to service on September 4, 1974. The substitute transformer
which was rented from PGandE for the duration of the repair
work was shipped back to PGandE. The use of the substitute
transformer, which enabled the powerhouse to operate at full
capacity from February, saved the City more than $150,000 per
month during the period of repair, about six months.
MOCCASIN PAINT SHOP
JOE WADELL, Painter
MOCCASIN CORP. YARD
Pipe Threading
ERVIN JOHNSON (L) , Plumber
BILL STEELY, Plumber
16 -
OPERATION AND MAINTENANCE - TRANSIT POWER DIVISION
The Transit Power Division is responsible for supplying the 600
volt direct current power that is necessary to operate the street-
cars and trolley coaches of the San Francisco Municipal Railway.
The Division is composed of two sections: Motive Power and
Overhead Lines.
MOTIVE POWER SECTION
This Section operates and maintains seven substations which con-
vert electric power from 12,000 volts alternating current to 600
volts direct current by means of motor-generators, synchronous
converters, and mercury arc rectifiers. (See Appendix Table 3
for statistical data.) Motive Power is also responsible for
maintaining the electric motors and associated control equipment
for operating the cable-winding machinery located in the Cable
Car Powerhouse at Washington and Mason Streets. In addition,
Motive Power is also responsible for periodic inspection, clean-
ing, adjusting and repairing the streetcar and trolley coach
recorders at Central Control of the Municipal Railway. The
substations operate 24 hours per day, 7 days per week, 365 days
per year.
On December 30, 1974 the 700 horsepower motor which drives the
Cable Car System, failed due to an internal electrical fault.
Our powerhouse electricians disassembled the motor and found the
fault in the wound rotor. A local motor repair shop (Reyna
Electric) was able to repair the damaged winding without the
delay and expense of rewinding the rotor. Our powerhouse elec-
tricians reassembled the motor, tested it and returned it to
service on January 15, 1975.
The following day (January 16, 1975) the other motor (750 hp)
which drives the Cable Car System failed to start. Our power-
house electricians disassembled it and found it had a fault
similar to that found in the 700 hp motor. Again, Reyna Electric
was able to repair the fault without rewinding the rotor. Our
powerhouse electricians reassembled the motor, tested it and
made it available for service on February 19, 1975.
While the rotors were being repaired, the stator coils and
housing of both motors were cleaned, inspected, painted with
insulating enamel and dried using heat lamps.
- 17
Because the Cable Car System frequently overloaded its driving
motor and caused the protective overload sensor to disconnect
the motor by tripping its circuit breaker, a recording ammeter
was installed in the switchgear panel to monitor the load. The
recorder subsquently showed that the cable system load was far
exceeding the rating of the driving motors.
OVERHEAD LINES SECTION
The primary function of the Overhead Lines Section is to maintain
the trolley wire overhead facilities and the electric distribution
system (both overhead lines and underground cables) which conveys
power to it. Secondary functions include the maintenance of the
Municipal Railway Signal Systems and the electric light and power
systems of all Municipal Railway buildings.
During the fiscal year 1974-75, the Overhead Lines Section responded
to 4,184 emergency calls. In addition to emergency calls, this
section has a regular and extensive maintenance program for over-
hauling all overhead and underground facilities. This section
operates with three shifts per day, seven days a week. Monday
through Friday, the normal workday shift is from 8:00 a.m. to
3:00 p.m. with a two-man emergency crew on the "swing" or evening
shift (3:30 p.m. - 10:30 p.m.) and the graveyard shift (1:00 a.m.
- 8:00 a.m.). On Saturdays, Sundays and holidays there is a two-
man emergency crew on each of three eight-hour shifts; midnight
to 8:00 a.m., 8:00 a.m. to 4:00 p.m., and 4:00 p.m. to midnight.
Overhead and underground facilities are systematically inspected,
and worn or damaged parts are replaced before they can cause
accidents or malfunction of equipment.
A considerable amount of damage to overhead facilities was caused
by trolley coaches dewiring and snagging their poles in the over-
head facilities and tearing them down, or by breaking the spans
with the flaying poles. Such damage is repaired at no cost to
the Municipal Railway. Other parties who damage our facilites
are billed for the cost of repairs. This includes damage to
overhead facilities caused by high loads on trucks or careless
operation of crane equipment and damage to underground feeder
cables by contractors digging into our duct lines. During 1974-75,
responsible parties were billed for 14 damage cases totalling
$16,702.95. The overhead Lines Section also performed work for
building owners and contractors under work orders amounting to
19 jobs totalling $24,545.24. This work included moving trolley
poles to accommodate driveways; relocating trolley poles and
feeders to permit construction of new buildings; temporarily
removing trolley wires and feeders to permit passage of high
loads; and shifting of trolley wires and feeders for various
excavations .
The Overhead Lines Section engaged in many other activities of
a related nature which it is especially equipped to perform.
These additional duties include repairs, maintenance and construc-
tion of electrical systems in Muni's car barns, offices and shops;
welding and rebuilding of worn overhead lines special work;
making and rebuilding parts for switches, warning block signals,
car recorders, and strand alarms for the cable car system;
installing mobile radio equipment; installing streetcar and bus
stop signs and public information signs.
19
ENGINEERING DIVISION
The Engineering Division of Hetch
engineering services for the Hetc
Power Division and the Power Impr
include the preparation of studie
plans and specifications for new
of structures and for items of ma
inspection of construction, contr
recommendations are provided for
Hetch Hetchy Water and Power. Wo
requires special knowledge and ex
engineering consulting firms and
Division. The Division is organi
Structural and Civil, Electrical,
and Construction.
Hetchy Water and Power provides
h Hetchy Project, the Transit
ovement Program. These services
s, reports, cost estimates, and
construction, for replacement
jor maintenance. Surveying,
act administration and payment
all construction work under
rk of unusual magnitude which
pertise is done by qualified
reviewed by the Engineering
zed into five main sections:
Mechanical, Architectural,
PHOTO TAKEN DURING CONSTRUCTION OF HETCH
HETCHY AQUEDUCT, 9" 6" PIPE, MARCH 192 5
20
HETCH HETCHY PROJECT
During the year, plans and specifications were prepared for the
following work to facilitate and maintain Hetch Hetchy Project
operations (for construction work in progress during 1974-75
please refer to Table 18 in the Appendix) :
HH-443 - Moccasin Dam Spillway, Construct Weir and Energy
Dissipator and Red Mountain Bar Waste Way Training Walls
A contract was let to raise the weir at Moccasin Dam so that
increased water flow can be delivered through the San Joaquin
Pipelines and Coast Range Tunnel. In addition to the weir, an
energy dissipator is to be constructed at the end of the spill-
way and training walls are to be erected at the Red Mountain Bar
Waste Way. The energy dissipator is provided to protect the
lower Moccasin Dam area from erosion during high volume spills.
The training walls are required to contain and direct water spilled
at Red Mountain Bar where high volume spills now overflow the
existing structure and cause erosion.
HH-477 - Moccasin Penstock
Valve House
Plans and specifications have been
prepared for the construction of a
steel frame structure to enclose
the butterfly valves at the head
of Moccasin Penstock. The struc-
ture will provide protection and
security for the valves.
HH-454 - Reconstruct Moccasin
Sewage Disposal System
A package sewage treatment plant
producing an odorless effluent
and sludge has been planned to
replace the existing septic tank
system. A reapplication is in
process for a Federal "Clean
Water Grant" that should cover a
substantial portion of the cost
of construction of the project.
Negotiations to acquire land for
an effluent sprinkler field, as
required by the State Water Qual-
ity Control Board, have been
FINN HAASKJOLD
Mechanical Engineer
- 21
completed and the land will be purchased. Work is in progress
to satisfy the requirements of the State Water Resources Control
Board and the Regional Water Quality Control Board (Central
Valley Region) .
HH-499R - Moccasin and Early Intake - Reroof Cottages
Reroofing of six cottages at Moccasin.
HH-507 - Cherry Road, Resurface Mile Post 16.1 to Mile Post 23.4
A contract was let to resurface a portion of Cherry Road. An
asphalt wearing surface is to be applied to a length that had
been damaged by logging operations (Mile Post 16.1 to 17.1).
The reminder of the road (Mile Post 17.1 to 23.4) will receive
an asphalt seal coat and rock screenings to prolong the life
of the road surface.
HH-515 - Moccasin Shop and Warehouses - Replace Windows
The contract was for the replacement of existing deteriorated
wood windows with new aluminum fixed windows and shop building,
line warehouse building and Warehouse No. 2 building at
Moccasin.
HH-516 - Storage Shed - Repair Roof
Repairing the roof on the storage shed which is part of the
storeroom building at Bryant.
HH-518 - Tesla Portal Overflow Shaft Extension
A contract was let to extend the Tesla Portal Overflow Shaft.
The extended shaft along with other improvements will allow
a greater volume of water to be pushed through the Coast Range
Tunnel.
TRANSIT POWER DIVISION
During the year, plans and specifications were prepared for the
following work to facilitate and maintain Transit Power Division
operations (for construction work in progress during 1974-75
please refer to Table 18 in the Appendix):
HH-494 - Replace, Repair and Paint Steel Trolley Poles
(Fulton Street)
Contract plans and specifications have been completed to Teplace,
- 22 -
repair and paint steel trolley poles on Fulton Street, La Playa
Street and Mission Street. The contract is scheduled to be let
in August 1975. This work is part of a program to rehabilitate
all steel trolley poles in the City.
HH-520 - Haight Street, Stanyan Street to Central Avenue -
Painting Steel Trolley Poles
A contract was let to paint steel trolley poles on a section of
Haight Street. The poles were in a deteriorated state and were
painted to arrest further corrosion and to improve their appear-
ance ,
HH-538 - Paint Trolley and Street Lighting Poles - Sutter
Street, from Taylor Street to Presidio Avenue
In response to a request from a neighborhood association to
paint poles along Sutter Street to improve the street's appear-
ance, contract plans and specifications for painting have been
completed. The contract is scheduled to be let in September
1975. Both City and PGandE facilities will be painted under
this contract and an agreement has been negotiated with PGandE
for payment of its share of the work.
POWER IMPROVEMENT PROGRAM
Work during fiscal year 1974-75 under the Federal Grant of $19.8
million (total Project Cost of $29.65 million) approved by UMTA
for the Power Improvement Program was as follows (for construc-
tion work in progress during 1974-75 please refer to Table 18
in the Appendix) :
1. Grant Amendment
An amendment increasing the total Project Cost to $57.7
million and the Federal Grant to $42.1 million was submitted
to UMTA for approval on February 24, 1975. Since the prep-
aration of the original budget, certain operating criteria
and power requirements of the new subway-surface light rail
vehicles have changed or have become better defined. The
effect on the power supply and distribution system was
evaluated by an updating of the conceptual design approved
by UMTA. The final report was received after approval of
the Project grant and budget. Subsequent detailed engineer-
ing design has developed more realistic cost estimates.
Unprecedented inflationary trends in materials and construc-
tion costs have resulted in greatly increased costs.
- 23 -
2. Electrification Project
A) Design Services
Preliminary design reports, covering the modifications
to the existing streetcar trolley overhead wiring to
permit pantograph operation and the installation of
feeder cables, gap breaker stations and trolley wire
systems in the Market Street Subway and the Twin Peaks
and Sunset Tunnels, were reviewed with the consultant,
PBQ5D, Inc. and Gibbs § Hill, Inc., and were accepted,
with revisions to be incorporated into the final design.
The consultant began work on final design contract plans
and specifications.
Contract plans and specifications for Contract HH-521,
Market Street Subway Electrification, Embarcadero Station
to Duboce Portal, were completed and transmitted to UMTA
for approval. Bids were received on May 15, 1975. The
contract was awarded on May 27, 1975 to Amelco Electric,
San Francisco, California, who submitted the low bid of
$1,077,000. The contract was certified by the City
Controller on June 30, 1975. Work is scheduled to
commence early in July 1975.
A decision was made to combine the Twin Peaks Tunnel
Electrification with the TIP project for repairs to the
tunnel. Plans and specifications for the electrification
v/ork were completed and sent to TIP for inclusion in
Contract MR-622, Twin Peaks Tunnel Electrification,
Structural Repairs and Improvements. TIP transmitted
to UMTA for approval on June 3, 1975. Bids are scheduled
to be received by TIP on July 9, 1975.
Amendment No. 1 to the professional services agreement
was negotiated with the consultant. The amendment,
which provides for additional professional services not
covered under the agreement, was approved by the Public
Utilities Commission on June 24, 1975, and was trans-
mitted to UMTA for approval on June 27, 19 75.
B) Cable Purchase
Technical specifications and bid documents for the pur-
chase of insulated copper feeder cable were completed
and submitted to UMTA for approval. Bids were received
by the City Purchaser on March 24, 19 75. The contract
was awarded by the City Purchaser to Cyprus Wire and
Cable Co., South San Francisco, California, who submitted
the low bid of $3,151,452. The contract was certified
by the City Controller on May 1, 1975.
- 24 -
3. Substation Project
A) Design Services
Our consultant, Bechtel, Inc., continued design work on
the substation buildings and equipment installation.
Plans and specifications for Contract HH-522, Civic
Center, Church and Downtown Substation, Installation of
Electrical Equipment, were completed and submitted to
the Public Utilities Commission for approval. Plans
and specifications are scheduled to be transmitted to
UMTA for approval early in July 1975.
Plans and specifications at the 85$ completion level for
Carl Substation were submitted by the consultant and
were reviewed by Hetch Hetchy and returned with comments,
Plans and specifications at the 851 completion level
for Judah and Laguna Honda are scheduled to be sub-
mitted by the consultant in July 1975.
Amendment No. 1 to the
existing professional
services agreement was
negotiated with the
consultant. The amend-
ment, which includes
consultant's review of
substation equipment
submittals, changes in
the design of Laguna
Honda Substation, and
addition of sanitary
facilities in certain
substation, was sub-
mitted to UMTA for
approval on December
5, 19 74. The amend-
ment which was approved
by UMTA on January 22,
1975.
HAMILTON MARS
Assoc. Civil Engineer
- 25
Amendment No. 2 to the existing professional services
agreement was negotiated with the consultant. The
amendment, which provides for additional professional
services not covered under the agreement or Amendment
No. 1 to the Agreement, was approved by the Public
Utilities Commission on May 27, 1975, and was forwarded
to UMTA for approval on May 30, 19 75.
Review of final plans and specifications for BARTD
Contract 1S0041, West Portal Station, for compliance
with our requirements for the West Portal Substation
and electrification conduits and feeder details in-
cluded in the contract, was completed and comments were
transmitted to Transit Task Force.
Review of contract drawings and specifications for
Contract MR- 609, Muni Metro Center, for compliance with
our requirements for the San Jose Substation and for
feeder conduits and yard overhead construction included
in the contract, was made and comments were transmitted
to TIP.
Building designs for the six new substations, except for
Taraval, received Phase II approval by the San Francisco
Art Commission. Final (Phase III) apparoval for three
of these substations, Laguna Honda, Judah and Carl,
also received from the San Francisco Art Commission.
B) Substation Sites
All substation sites have received approval of the City
Planning Commision for conformance to the City Master
Plan, with the exception of Taraval as noted hereinafter
due to necessity of alternate sites.
Independent appraisals by two outside real estate appraisal
firms were completed for all new substation sites.
Jurisdiction of the Laguna Honda Substation site was
transferred from the City Health Department to Hetch
Hetchy by the Board of Supervisors on December 12, 1974.
Following concurrence by UMTA on the purchase price for
Judah Substation site, the Public Utilities Commission
adopted a resolution which approved the acquisition and
recommended to the Board of Supervisors that they approve
the acquisition. The Board of Supervisors approved the
acquisition. The site was vacated as of June 13, 1975;
keys to the existing building were delivered to Hetch
Hetchy by the Real Estate Department.
- 26 -
Negotiations for the Taraval Substation site, a privately
owned vacant lot, brought out the possibility of Eminent
Domain action to acquire the property. UMTA has concurred
with the price offered and the use of Eminent Domain
action. Authority to proceed with Eminent Domain pro-
cedure for acquisition of this approved Taraval Substation
site near 32nd and Taraval was withheld by the San
Francisco Board of Supervisors' Finance Committee at
their meetings on January 15 and January 29, 1975. At
their direction, alternative sites have been found on
Taraval Street near 40th Avenue and 42nd Avenue.
Environmental Impact Data on the alternative sites, to
supplement that on file, was forwarded to UMTA, as
requested, prior to approval by UMTA of proceeding with
real estate appriaisals as the first step in acquisition
of one of the sites.
A supplementary Environmental Impact Statement on the
alternative Taraval sites was filed with and evaluated
by the San Francisco City Planning Department, in
accordance with the California Environmental Quality
Act of 1970, with the finding that the project could
have no significant effect on the environment. A
negative declaration was prepared, posted, and advertised,
and it received no notice of appeals within the required
time limits. An EIR will not be required.
City Planning Department was requested to review the two
alternative Taraval Substation sites for conformance with
the City Master Plan.
Acquisition of either of the two alternative Taraval
Substation sites was approved by UMTA on March 16, 1975.
Community approval of both sites was received from the
Taraval - Parkside Merchants Association and the Parkside
District Improvement Club. The two sites are being
reviewed by City Planning for Master Plan Conformance.
Real Estate Department is proceeding with the ordering
of independent appraisals of the sites.
Negotiations with Pacific Gas and Electric Company for
an easement for the Randolph Substation site, and for
the relocation of PGandE energized underground electric
distribution facilities within the easement, was completed.
A rear yard variance to provide space for the Randolph
Substation Building was granted by San Francisco Planning
Department. A work order to PGandE for relocating their
electric distribution facilities from the proposed
- 27 -
Randolph Substation site was transmitted to UMTA for
approval on April 9, 1975. The work order was approved
by UMTA on June 2, 1975, and was certified by the City
Controller on June 17, 1975. The work order will become
effective after PGandE grants the easement for the sub-
station to the City. Legislation necessary for the
acquisition of the easement is underway.
Meetings were held with San Francisco Redevelopment
Agency, City Real Estate Department and Hetch Hetchy to
develop the terms for use of the Fillmore Substation
site to be obtained from the Redevelopment Agency.
C) Equipment Purchase
Work commenced on fabrication of substation equipment.
Meetings were held with ITE Imperial Corporation to
review technical specifications and to coordiante
delivery of equipment with future contracts for con-
struction of substation buildings and installation of
equipment. Shop drawings, wiring diagrams and other
equipment data are continuing to be submitted for
approval and are reviewed by Hetch Hetchy and our con-
sultant, Bechtel. Equipment modifications, required
by detailed design criteria and increased Project
requirements, are being processed.
4. Control and Communication Project
The negotiated agreement between Systems Control, Inc. and
the City was approved by UMTA on September 6, 19 74. The
agreement was certified by the City Controller on December
30, 1974 and work began on January 15, 19 75. Following a
meeting held on January 22, 1975 with Hetch Hetchy to
establish project schedule, identify key design criteria
and to cover interfaces of this project with other portions
of the Power Improvement Program, the consultant began
gathering data to establish design criteria for the preli-
minary report required under the contract. The preliminary
report was submitted by the consultant in June 1975 and was
being reviewed by Hetch Hetchy staff.
28
5. Feeder Undergrounding
A) United Nations Plaza (D.P.W. Contract 23,476
Bids for the United Nations Plaza, which include con-
struction of underground duct lines for PIP were re-
ceived on January 8, 1975. The contract, including PIP
work in the amount of $31,130 was awarded to the low
bidder, Homer J. Olsen, Inc., on January 29, 1975.
Construction began in March 1975.
B) Judah Street (D.P.W. Contract 23,506)
Construction work commenced on the relocation of trolley
poles and the undergrounding of feeder cables included
in the Department of Public Works contract for Judah
Street, 4th to 20th Avenues - Street Improvements and
Track Reconstruction.
C) 2nd and Mission Streets (Contract HH-489)
All work on this contract was completed in accordance
with contract plans and specifications on August 26, 1974
D) Market Street - 7th to
8th Streets
(Contract HH-492)
All work on this contract
was completed in accordance
with contract plans and
specifications on September
9, 1974.
E) 19th Avenue and Municipal
Railway Right-of-Way -
St. Francis Circle to
Junipero Serra Boulevard
(Contract HH-493)
All work on this contract
was completed in accordance
with contract plans and
specifications on July
17, 1974.
29
JOHN KELLOGG
Civil Engineer
F) Ecker and Stevenson Streets - Underground Duct System
(Contract HH-496)
Plans and specifications for constructing underground
manholes and duct banks in Ecker and Stevenson Streets
were approved by UMTA. Bids were received on August 19,
1974. The contract was awarded to Underground Construction
Company, Inc., San Leandro, California, who submitted the
low bid of $98,810. Construction commenced on October 7,
1974. All work on the contract was completed in accordance
with contract plans and specifications on February 11, 1975
G) Market and Ecker Street - Construct Manhole (Work Order)
Construction work commenced in July 1974 on this contract.
All work covered by the Work Order was satisfactorily
completed on October 21, 1974 by Cahill Construction
Company.
II) Fillmore Street - Hayes to Pine Street (Contract HH-491)
Plans and specifications for the installation of under-
ground power facilities on Fillmore Street between Hayes
and Pine Streets were approved by UMTA on September 4,
1974. Bids were received on October 10, 1974. The
contract was awarded to Abbett Electric Corporation,
San Francisco, California, who submitted the low bid of
$737,618. Construction commenced in December 1974.
I) Junipero Serra Boulevard Track Reconstruction and
Landscaping (Contract MR-595R)
Following approval by UMTA, bids for Contract 595, a
joint TIP/PIP project, which includes the construction
of underground duct lines and installation of feeder
cables for the Power Improvement Program, were received
on July 29, 1974. After careful evaluation of the sole
bid received, which was considerably above the Engineering
estimate, and extensive discussion with the UMTA rep-
resentative, it was agreed that TIP Control Group re-
design and readvertise the project. Bids were received
on September 20, 1974. The contract was awarded to Homer
J. Olsen, Inc. who submitted the low bid which included
$62,400 for the PIP ortion of the contract. Work on the
duct lines and manholes (feeder cables eliminated in
revised contract) commenced in November 1974 and was
completed in June 19 75.
- 30 -
J) Ocean and Phelan Avenues Rechannelization
(D.P.W. Contract 23,727)
Plans, specifications and cost estimate for the relocation
of trolley poles and the overhead trolley wire system and
the undergrounding of feeder cables which will be included,
along with Muni Railway streetcar track relocation and
rerailing in a Department of Public Works contract for
Ocean and Phelan Avenues Rechannelization, were trans-
mitted to the Department of Public Works in November 1974.
Plans and specifications for the combined contract were
completed by the Department of Public Works and are
scheduled to be transmitted to UMTA and the Federal
Assisted Urbanization (FAU) for approval in August 1975.
K) Ocean Avenue - Junipero Serra Boulevard to Harold Avenue -
Underground Duct System (Contract HH-502)
Plans and specifications for constructing manholes and
underground duct banks in Ocean Avenue between Junipero
Serra Boulevard and Harold Avenue were completed and were
received on January 2, 1975. The contract was awarded
to Amelco Electric, San Francisco, California, who sub-
mitted the low bid in the amount of $196,148. Construction
work commenced in March 1975.
L) West Portal Avenue and Taraval Street - St. Francis Circle to
20th Avenue - Underground Duct System (Contract HH-498)
Plans and specifications for constructing manholes and
underground duct banks in West Portal Avenue, Ulloa
Street, 14th Avenue and Taraval Street between St. Francis
Circle and 20th Avenue were completed and were transmitted
to UMTA for apparoval. Bids were received on January 30,
1975. The contract was awarded to Underground Construction
Company, Inc., San Leandro, California, who submitted the
low bid in the amount of $229,585. Construction commenced
in March 1975. All work on the contract was completed in
accordance with the contract plans and specifications on
June 20, 1975.
M) 19th Avenue, Randolph and Broad Streets - Underground
Duct System (Contract HH-519
Plans and specifications for constructing manholes and
underground duct banks in 19th Avenue, Randolph Street,
Orizaba Avenue and Broad Street between Junipero Serra
Boulevard and Plymouth Street were completed and were
- 31 -
transmitted to UMTA for approval. Bids were received
on March 17, 19 75. The contract was awarded to Venturini
Corporation, San Mateo, California, who submitted the low
bid in the amount of $179,780. Construction work commenced
in May 1975.
N) Church Street - 22nd
Street to 30th Street -
Underground Duct System
(Contract HH-497)
0) Taraval Street and 46th
Avenue - 20th Avenue to
Vicente Street - Under-
ground Duct System
(Contract HH-503)
P) Sutter Street - Presidio
to Leavenworth -Under-
ground Duct System
(Contract HH-525)
Q) McAllister Street -
Divisadero to
Leavenworth -
Underground Duct
System (Contract HH-526)
R) Haight, Fillmore, Church and
Other Streets - Underground
Duct System
(Contract HH-527)
S) Ocean Avenue, Persia
Avenue and Mission Street -
Metro Center to Russia
Street - Underground Duct
System (Contract HH-537)
,V
\
DON BURDICK
Assoc. Electrical Engineer
Work commenced on the preparation of plans and specifications
for constructing manholes and underground duct banks
(Contracts HH-497, HH-503, HH-525, HH-526, HH-527, and
HH-537). Feeder cables will be installed in these duct
banks under a later contract.
32
T) Judah Street - 20th to 48th Avenues - Underground Duct
System (Contract HH-523)
Work was temporarily suspended on the preparation of
plans and specifications for constructing manholes and
underground duct banks in Judah Street between 20th
and 48th Avenues. Feeder cables will be installed in
these duct banks under a later contract. The delay is
due to DPW determination of the extent of the Street
Improvement and Track Reconstruction work.
U) Other Work
Preliminary engineering and plans and specifications
are proceeding for duct lines and feeder undergrounding
in accordance with the requirements of the Program.
V) Manhole Frames and Covers (First Contract)
Delivery of all manhole frames and covers, totalling
100 sets, was completed on September 25, 1974.
W) Manhole Frames and Covers (Second Contract)
Contract documents for purchasing an additional 100
sets of manhole frames and covers for use on future
Power Improvement Program contracts were prepared and
transmitted to UMTA for approval. Bids were received
by the City Purchaser on January 17, 1975. The contract
was awarded to Phoenix Iron Works, Oakland, California,
who submitted the low bid of $32,100. The contract
was certified by the City Controller and the Contractor
began fabrication of the manhole frames and covers.
Overhead Line Work
A) Junipero Serra Boulevard - St. Francis Circle to Ocean
Avenue (Contract HH-517)
Work continued on preparation of plans and specifications
for trolley pole replacement and overhead trolley wire
installation on Junipero Serra Boulevard from St. Francis
Circle to Ocean Avenue.
Under this contract, which will follow the track re-
construction and landscaping contract, MR-595R, under-
- 33
ground feeder cables will
be installed in the ducts
constructed under MR-595R
and the existing overhead
feeders will be removed.
The scope of this contract
has been expanded to in-
clude underground cable
installation on Ocean
Avenue and West Portal
Avenue in underground
duct banks installed under
Contract HH-498 and HH-502.
B) Trolley Coach Overhead
Facilities for "Transit
First" Program
Work commenced on the
preparation of plans and
specifications for the
relocation of overhead
facilities on Mision
Street, Beale to South
Van Ness, and 4th Street
Market to Townsend, in
implementation of the
"Transit First" program
of the City and County of
San Francisco. Plans and
specifications for the
relocation of overhead
facilities are scheduled
to be transmitted to the
Department of Public Works in July for inclusion into
a Department of Public Works contract.
7. Miscellaneous
A) Coordination meetings of the joint staffs of Transit
Improvement Program and the Power Improvement Program
were held.
B) Coordination meetings were held between Hetch Hetchy
staff and the consultants on the electrification,
substation and control and communication projects.
KARL ALMGREN
Civil Engineering Assoc
- 34
BUREAU OF LIGHT, HEAT AND POWER
STREET LIGHTING
General
The lighting of public streets within the City of San Francisco
is provided by facilities which are, on a City-wide basis, 42.5%
owned by the City; 55.6% owned by the Pacific Gas and Electric
Company; and a small percentage, 1.91, jointly owned. In the
underground areas, where the economic advantage of City owner-
ship is greatest, 81.1% of the lights are City-owned. Five
years ago, the corresponding figure was 70.6%.
In fiscal 1933-34, the cost for street lighting was $1.25 per
capita; last year, with approximately thirty times as much light
on the streets and public thoroughfares, the cost per capita was
approximately $1.83.
LINCOLN WAY LOOKING WEST
FROM 2ND AVENUE
- 35 -
AD VALOREM TAX $ 1,240,817
TRANSFERS FROM OTHER
DEPARTMENTS $ 6,100,815
TOTAL $ 7,341 ,632
BUREAU OF LIGHT, HEAT
AND POWER REVENUES
FISCAL YEAR 1974-75
LIGHTING OF PUBLIC STREETS $ 1,058,929
ADMINISTRATION
$193, 13
STREET LIGHTING
MAINTENANCE
$ 2 17, 8 2 1
LIGHTING AND HEATING
OF PUBLIC BUILDINGS
$ 5, 87 I , 75 I
TOTAL $ 7,341,632
BUREAU OF LIGHT, HEAT
AND POWER EXPENDITURES
FISCAL YEAR 1974-75
Maintenance and repair of City-owned installations was performed
under two contracts. One provided for group replacement of lamps
in accordance with schedules developed by the Bureau. A second
contract covered work required for repair of damaged and defective
equipment, painting and miscellaneous maintenance.
Under contract, the Pacific Gas and Electric Company furnished
street lighting service as directed, including the furnishing,
maintenance and operation of Company-owned facilities. Certain
services were provided also for City-owned facilities, including
switching and control, replacement of individual lamps and globes,
and emergency work required during other than normal working
hours. Electric energy for all City and Company-owned street
light operation was supplied by the Hetch Hetchy power system.
Engineering
The Bureau review, recommends changes, approvals or rejections
of, and correlates all street lighting installations, including
that dome by the Department of Public Works, the Pacific Gas and
Electric Company, the Bay Area Rapid Transit District, the
State of California, subdividers, etc.
During the fiscal year 1974-75, 13 street lighting contract,
involving a total of 641 new street lights, were approved by
the Public Utilities Commission. Plans were submitted for
approval only after careful checking to determine that illu-
mination will exceed the minimum requirements established by
the American National Standards Institute; and that all materials
used, and manner of installation, meet with the applicable local,
State and Federal rules, regulations and statutes governing the
installation of electrical works.
Operation and Maintenance
As of June 30, 1975, a total of 37,061 City-owned and Company-
owned street lights were in service in public streets, parks,
viaducts, overcrossings , tunnels and underpasses. A summary
of the number and type of units in service at the end of the
fiscal year is shown in Appendix Table.
A total of $1,281,316 was expended for operation, maintenance,
and repair of the street lighting system. Of the total cost,
$12,614 was paid by the State for its share of the operation and
maintenance of street lighting at inersections on City streets,
which are part of the State Highway system. During the fiscal
38 -
year, there were 119 accidents involving damage to City-owned
street lighting property. Investigation was made, as soon as
possible, to remove hazards to the public and obstructions to
traffic. Total cost of repairs to damaged City-owned street
lighting property was $60,732. Every effort was made to secure
reimbursement for damages incurred from responsible parties.
Previous experience indicates that approximately three-fourths
of the repair costs will be recovered.
Complaints
During the year, 50 complaints requiring field investigation
were received and acted upon. These complaints concerned
inadequate illumination, objectionable glare in windows, and
requests for temporary and permanent relocation of street
lighting poles.
Improvements
During the fiscal year 1974-75, a total of 304 new City-owned
street lights were placed in service at a cost of $420,433.
Improvements were financed by State Gasoline Tax and the 1972
Street Lighting Bond Issue as indicated in Appendix Tables 16
and 17.
UTILITY SERVICES TO MUNICIPAL DEPARTMENTS
General
Electric energy supplied to municipal departments is generated
on the Hetch Hetchy power system and delivered to various service
points by transmission and distribution facilities of Pacific
Gas and Electric Company under a wheeling contract. Natural
gas and steam supplied to municipal departments are furnished
by the Pacific Gas and Electric Company under a service contract.
Municipal Consumption of Electricity, Gas and Steam
During the fiscal year, 478,595,675 kilowatthours of electrical
energy were consumed through 1,003 municipal accounts at an
expenditure of $4,905,273. Of the above, 147,431,772 kilowatt-
hours of energy were supplied to the San Francisco International
Airport for resale to tenants. Natural gas consumption was
17,984,305 therms through 556 accounts at a cost of $1,855,530.
One account consumed 610,200 pounds of steam at a cost of $1,475.
There were six increases in gas rates last year which increased
the cost to municipal accounts by approximately $474,246.
A summary of consumption and expenditures for these commodities
is shown in Tables 12 and 13.
- 39 -
APPENDIX
MOCCASIN DAM
TABLE 1
HETCH HETCHY WATER AND POWER
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES (INCLUDING ENCUMBRANCES)
FISCAL YEAR 1974-75
OE
110
111
112
113
120
130
139
200
216
231-1
232-2
251
300
640
641
801
804
812
813
814
815
853
854
855
856
860
862
865
870
880
900
400
500
700
800
DESCRIPTION BUDGET
Permanent Salaries $ 723,076
Overtime 16,500
Holiday Pay 4,000
Extended Work Week 2,400
Temporary Salaries 53,100
Wages 1,375,862
Wages - Gardeners 44,180
Contractual Service 120,685
Maint. and Repair of Auto Equipment 9,000
Purchase of Power for Resale 600,000
Service Charge for Transm. and Dist. 2,557,000
Subsistence of Employees 10,000
Materials and Supplies 155,400
Water Rights and Damage Claims 12,000
Hydrography 37,000
Accident Compensation 22,275
Claims 500
Fidelity Insurance 72
Automobile Insurance 8,043
Fire Insurance 6,989
Miscellaneous Insurance 12,178
Assessments Paid to Other Districts 56,000
Membership Dues 5,312
Fees to U.S. Gov't. -Raker Act 30,000
Maint. Roads and Trials-Raker Act 15,000
Retirement Allowance 473,782
Social Security 101,375
Health Service System 42,497
Taxes 498,017
Rental-Transmission Lines and Offices 114,000
Services of Other Departments . ,,, .838,621
TOTAL OPERATION AND MAINTENANCE $7,944,864
Equipment 48,975
Additions and Betterments 453,500
Reconstruction and Replacement 1,187,000
Bond Interest and Redemption 9,061,069
ACTUAL
$ 669,264
15,688
3,704
1,434
49,665
1,327,204
42,201
116,352
8,559
135,389
2,309,687
1,984
212,483
495
41,600
17,615
-0-
72
10,599
8,297
12,178
12,664
5,334
30,000
12,745
396,367
101,127
30,878
498,015
114,000
838.62.1
$7,024,221
48,792
453,500
1,187,000
9,077,334
■UNDER, OVER
$ -53,812
-812
-296
-966
-3,435
-48,658
-1,979
-4,333
-441
-464,611
-247,313
-8,016
57,083
-11,505
4,600
-4,660
-500
-0-
2,556
1,308
-0-
-43,336
22
-0-
-2,255
-77,415
-248
-11,619
-2
-0-
-0-
$-920,643
-183
-0-
-0-
16,265
TOTALS
$18,695,408
$17,790,847
$-904,561
TABLE 2
SUMMARY OF TAXES
Fiscal Year 1974-75
HETCH UETCHY PROJECT
Tax Levying Bodies
Alameda County
San Joaquin County
San Mateo County
Stanislaus County
Tuolumne County
Banta-Carbona Irrigation Dist.
Oakdale Irrigation Dist.
West Stanislaus Irrigation Dist,
Assessed Values
$ 2,050.00
39,050.00
3,345.00
107,330.00
5,269,488.00
3,233.80
25,897.00
1,700.00
Total Amount:
of Taxes
$ 224,54
4,255.58
338.84
10,324.60
482,112.72
139.05
517.94
102.00
$5,452,093.80
$498,015.27
0
LI
u
I-.
11
■1)
>
>
c
o
O
u
o
kfi
gf
0
ul
L>
.i:
M
o>
•t-)
.r:
jn
u
0)
OJ
j:
u
j-i
id
«d
>
O TJ
o
0) 0)
e
XI C
o
M
H
<
ri
H
o
CO
M
CQ
in
:=>
h-l
V)
B
i
en
o
z
OS
o
tu
O
M
cq
6
<
a.
w
H
CO
X)
CL'
OJ
u
nj
d
u
a
ui
c
M
o o
o o
o o
o o
cm m
o o
o o
m in
.-I r-l •*
(SI CM CM
(T» C\ CT»
53 53 XX
01
C
3
o
C
1-1
<u
id
(0
>
(j
(/I
s
<C
M
•H
o
X
o
jr
PL,
RJ
4J
4J
u
>
e
X,
u
0)
OJ
?
60
o>
u
c
0) •>
tt) o •
jd w a)
.-i Vj
u < 3
O 4J
C 3
(U <U 0)
jq w ai
■rJ U U JJ
U 4J Vl
c
>,
■^
fl
I)
S
n
u
■u
0)
c
u
a)
0)
Ri
10
E
u
3
a.
•rJ
id
•H
T3
o
3
C
<u
cr
l-l
XI
a;
TABLE 4
HETCII HETCHY WATER AND POWER
TRANSIT POWER DIVISION
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES
FISCAL YEAR 1974-75
OE DESCTIPTION
110-1 Permanent Salaries
130-1 Wages
300-1 Materials and Supplies
801-1 Accident Compensation
860-1 Retirement Allowances
862-1 Socinl Security
865-1 Health Service System
900-1 Services of other Departments
TOTAL OPERATION AND MAINT.
400 Equipment
500-1 Additions and Betterments
700-1 Reconstruction and
Replacements
TOTAL
BUDGET
AC
nil
*L
$
iDER, OVER
$ 69,985
$
38,285
- 31,700
1,098,907
984,110
-114,797
49,600
20,289
- 29,311
31,725
25,089
- 6,636
251,619
210,534
41,085
53,822
53,692
- 130
22,563
16,394
- 6,169
169,525
169,525
O-
$ 1,747,746
$
1
,517,918
$
-229,828
1,025
868
157
e
a
e-
1,219,700
l
,219,700
d
$ .2,968,471
$
2
,738,486
$
-229,935
TABLE 5
HETCH HETCHY WATER AND POWER
SUMMARY OF RECEIPTS AND EXPENDITURES
FISCAL YEAR 1974-75
RECEIPTS
Revenue from Sale of
Electrical Energy
Revenue from Sale of
Wat.er and Standby
Charge, SFWD
Other Revenue
BUDGET
$ 15,632,400
6,500,000
100,000
$ 22,232,400
ACTUAL -UNDER, OVER
$ 18,484,718 $ 2,852,318
6,500,000 Q-
144,126
44,126
$ 25,128,844 $ 2,896,444
EXPENDITURES
Total Expenditures
$ 21,663,879
$ 20,529,333 $ -1,134,546
LO VO o\°
HOON
• • o
cn t^ iH
to ■*
Cn O
VO LO
h- LO
K) o
ro cn to
\DON
Cn Cn OO
r~- Cn vO
CNl tO CNl
tO CNl
LO LO
vo cn
OONH
tO LO
O to
•*3- (Nl
(ni cn
r>. to
oo LO
ro <*°
o i—l
to ^a- VO
VO OO CNl
O00\0
VO VO CNl
tO CNl
CNl o
tO LO
LO oo
><
Di
U4
>
l—l
►J
w
Q
X
Q
<
—1
2
LU
CP
<
>H
(X
3
w
— 1
l/)
cj
<
Oi
2
LU
o
y— i
vO
H
H
Uh
<
CO
w
S
>~
l-J
~
CQ
cq
>-•
P-,
<
X
Uh
O
H
t_>
o
ro
H
2
W
x
W
X
c£
2
X
X
~
^
u
2
H
O
dl
w
i— i
o
X
H
<
CO
E-*
<
i— i
(X
l—l
u
pq
cn
Oh
cn oo
f"« oY3
VO (Nl VO
r^ to <sf>
cn i-o
LO VO
tOINH
en o (ni
t-~ ro
M O
NOOO
• • o
•n n
"I— I
•V .. «
WvOH
o ^r
LO
(ni r~» r-~
to ^J-
OO "3"
[N]
vO rH CNl
r-» <*
(Nl
tO CNl
cd
6
h
o
2
m
o
p
P!
<D
X
u
rp
u
CJ XI
0)
p
XOh
(D
o
X
1—1
•
1-1
X
.p
o
o
<D
P
P Ph
Ph
0)
cd
Ph
X i-J <
CO O
O <iP
t3- t-» o\»
O O
o cn
OONH
*3" OO
CNi r~-
. . t^-
* •*
*
■Cfr CNl
*3- i-H
o
(Nl tO
oo to
rH
LO tO
cn
r-- (ni o\o
CNl CNl
cni cn o
•> n
• • o
CNl 00
"*\OH
to CNl
to »-J-
r- -^t-
o o
O o\°
lo »a- a=
o o
O LO
cn cn cn
VO rH
r-» cn
•> • 00
•> n
•*
cn rH
i— i cn
o
CNl ^J-
oo o
cn
VO -^
CO
cd
e
y
o
:z
m
o
X rH
cj
X O
P
OX) p
CD
p x rt
Pu
cd o cd
X iH rH
•>
PI PJ
X
,P
tH O
O 0) 0)
cd p
PPh Ah
P Ph
cd cd cd
O Ph
X -3 pi
P"<
rH
>.
rH
•M
•H
•H
Ph O
CO
cd
Ph
o
03
z u
o to co
tO LO rH
LO VO I— I
^J- I— t CNl
CNl LO
r^ to to
iH oo o
(OOtN
Lo cn cni
o o co
vo co co
tO OO rH
OWN
VO VO CNl
tO CNl
LO VO
O0 LO
LO 00
CNl VO
O LO
r~. oo
oo oo
lo r^
>N P
X o
UT) C
P X cd
<D O <D
X rH rH
pi m
rC
iH
O (D Q)
cd
P Ph Ph
p
0) (d cd
o
X PI PI
H
cd •
bo ej
o
O ui
6 o
CJ
to
\ X
rH bO
p
>N O
r-\ bo
CD P
P w
cd
•
£ u
1^-
•H -H
to
x e
cn
o o
rH
p p
Ph<
p
Ph
•H
cd •
LO
P
p •
cd
O X
bO
<D
If) "
x>
P CD
O P
p
rH -H
u
rH (/)
p
cd
X)
bO CD
<u
P
p
O O
cr
O £
«<
Ot P
^ <D
X
LO >
.p
CNl -H
rP
P X
O
a- P
P
CD CD
CD
>
X
P -H
O rH
<P
O CD
P
o
IP TJ
cd
1
CD
p
CD CO
X
o
P CD
•H
O H3t
rH
P
cd P
XX
cd
cd
rH
cd cd
O
P
0 o
rprp
(/)
CD
p p
•H
&
O H
P P
cp
O
CD CD
PhPh
p
CD
1 >/ V
O
O
cd X)
cd e
tp
P
v « '
bO P
•H
cd e
rH
(/)
U -P
cd
CD X
P
rH
in
> cd
o
cd
m
<S
H
P
H
104
000
59
3
150
000
66
7
85
000
86
1
TAi LE 7
HETCH HETCTTi TOWER SYSTEM
ELECTRIC ENERGY GENERATED, PURCHASED, AND DISTRIBUTED
FISCAL YEAR 1974-75
Nameplate Rating Capability Annual Plant
PLANT DATA (Kilowatts) (Kilowatts) Factor - %
Moccasin Powerhouse 90,000
Dion R. Holm Powerhouse 135,000
Robert C. Kirkwood Powerhouse 67,500
Total 292,500 339,000
ENERGY GENERATED AND PURCHASED (KILOWATT-HOURS)
Gross Generation
Moccasin Powerhouse 539,990,000
Dion R. Holm Powerhouse 876,536,000
Robert C. Kirkwood Powerhouse 641,083,000 2,057,609,000
Station Service
Moccasin Powerhouse 868,000
Dion R. Holm Powerhouse 1,488,440
Robert C. Kirkwood Powerhouse 985,370 3,341,810
Net Generation 2,054,267,190
Supplementary Energy
"Bank" Withdrawal* 123,458,969
Purchase (PGandE) 0 123,458,969
Total 2,177,726,159
ENERGY DISTRIBUTED (KILOWATT-HOURS)
Sales
Municipal Accounts 481,275,895
Modesto Irrigation District 734,880,000
Turlock Irrigation District 219,120,000
Kaiser Cement and Gypsum Corporation 143,688,000
Kaiser Aluminum and Chemical Corporation 28,137,600
Norris Industries, Inc. 21,695,155
Lockheed Missiles and Space Company, Inc. 209, 304,000
General Motors Corporation 75,978,000
IBM Corporation 82,047,387
Liquid Air, Inc. 28,139,425
Miscellaneous Customers 809,002 2,025,074,464
Non-Revenue
Project Use 3,264,541
"Bank" Deposit* 55,771,707 37,036,248
Losses
Hetch Hetchy System 41,538,492
PGandE System (Municipal Accounts) 74,076,955 115,615,447
Total 2,177,726,159
' In accordance with letter-agreement between City and PGandE dated 6/24/7
TABLE 8
HETCH HETCHY POWER SYSTEM
COMPARATIVE ELECTRIC ENERGY SALES TO CUSTOMERS
FISCAL YEARS 1973-74 AND 1974-75
(Nearest 100,000 Kilowatthours)
CUSTOMER 1973-74 1974-75
Municipal Accounts
International Airport 198,700,000 189,900,000
Municipal Railway 63,600,000 64,800,000
Public Works 26,000,000 26,600,000
Street Lighting 45,500,000 45,800,000
Unified School District 37,800,000 38,300,000
Water Department 40,400,000 44,000,000
Other City Departments 70,500,000 71,900,000
Modesto Irrigation District 787,400,000 734,900,000
Turlock Irrigation District 302,800,000 219,100,000
Kaiser Cement and Gypsum Corp. 156,700,000 143,700,000
Kaiser Aluminum and Chemical Corp. 31,300,000 28,100,000
Norris Industries, Inc. 22,500,000 21,700,000
Lockheed Missiles 5 Space Co., Inc. 39,600,000 209,300,000
General Motors Corporation 0 76,000,000
IBM Corporation 0 82,100,000
Liquid Air, Inc. 0 28,100,000
Miscellaneous Customers 700,000 800,000
TOTAL 1,823,500,000 2,025,100,000
TABLE 9
HETCH HETCHY POWER SYSTEM
COMPARATIVE GROSS REVENUE RECEIVED FROM SALE OF ELECTRIC ENERGY
FISCAL YEARS 1973-74 AND 1974-75
(Nearest $1,000)
CUSTOMER 1973-74 1974-75
Municipal Accounts
International Airport $ 1,666,000 $ 1,588,000
Municipal Railway 640,000 649,000
Public Works 321,000 333,000
Street Lighting 481,000 485,000
Unified School District 560,000 567,000
Water Department 376,000 395,000
Other City Departments 902,000 912,000
Modesto Irrigation District 4,510,000 4,289,000
Turlock Irrigation District 1,696,000 1,483,000
Kaiser Cement and Gypsum Corp. 1,773,000 1,927,QQQ
Kaiser Aluminum and Chemical Corp. 377,000 418,000
Norris Industries, Inc. 225,000 227,000
Lockheed Missiles $ Space Co., Inc. 483,000 2,772,000
General Motors Corporation 0 1,054,000
IBM Corporation 0 1,122,000
Liquid Air, Inc. 0 373,000
Miscellaneous Customers 9,000 9,000
TOTAL $ 14,019,000 $ 18,603,000
o o o
O vo co
inoinio
rs, • • •
i cm t>.rv
^1" CM ^ Cn
r-^ r— o O
en »> •> •>
■ — |cr> in o
in 00 VO
inooooin
en o o o o in
00 O O O VO i—
mOOCONin
h-OOCJOO CO o>
CM 00 i — VD i — VO
i— «3- cr> co oo >—
00 CO i — <=J" CM CM
OONUlN
O CD 00 CM O
o o co «3- o
«^- 00 r^ CTl CTi
CO CTl O i — 00
r— r~~
•* o
m r~-
vo r-x
cm r->
o o o
O
■— CO
cr>
oo r--
*!•
vo cm «=j-
CM
CM r-»
I**
1
oo r«. oo
^r
in i —
r*i
r— VO CO
r~»
CO o
r*.
«d" 00 r*.
o
•* «3-
m
r—
*3" CO VO
o
VO ^
CTi
co <*
in CO VO
CTl
rx. o O O O VO
cn o o o o ■—
VO o o o o o
MCVJ^OON I
CO CT> 00 CM CM O I
<t ni — i — co in i
CM r^ CM VO i — CM
00 00 O LD CO CM
«a- r^. co i—
f— CM
en in
10 in
VO 00
VO o
CM CTl
co o
o o o
orxcn
co cm in co
VO I l"N
oo <3- «*
CO 1— r—
i — |CM CO i —
«tf- in o
in id vo
OlOOOOO
O O O O O ID
CTi O O O VO r^
en vo <3- co ■— in
in i — co vo CM CM
cm oo **■ co in co
oo co i — in t— cm
o in CM ^1" co CM
lo oo «a- i—
i i i i
ID oo
CTl CTl
r-x ID
co m
O CO
o en
«a- co
o o o
o
VO ^3-
O CO CO
ID
VO CO
cmIcm «d- en
in
«d" «d"
r~. «. •• -
i co in —
m
o «a-
■ — ►«• i — in
«*
VO CO
r*. CTi in i —
ID
CO P~-
CTl •> • -
•— |co CO <3-
ID
VO CO
CO O r—
m
•=r o
in co id
cr>
1 —
CTiooinocooo
COOOOOVOOVO
rx-OCMCMOrx-Orx.
inocTii — vo ■* vo vo
0"^"i — CMCTivDOrx.
r-MOi — CTlVOCTlCO
covooMfirNtso
r-x en vo in co ■ — 10 co
<a- rx. co i —
CM 00
i— CM
in en
r~> in
CO in
CM r*.
oo
o
oo
VO
CM
<d-
r—
o
C )
«3-
o>
r-.
oo
i — ■
C"J
i— t— "O
o o o
o
in co
o o o
o
*d- in
CO «=J- r—
CO
r-. en
o o >=*•
LO
<3- r»
NOON
1 —
VO CTi
O CM 00
1 —
CTl o
r— CM O
•3-
CO VO
CO CTi CO
m
CO «*
LOCO VO
o
< —
inoooomoovoo
inooooooocoinvo
i— oooo-xTO^oin
r*.i — vOVOCTlCOCMOCOr—
CMr-.mco«d-covocoinco
i — f) * N LO O VO CVHO ID
COCOi— M CTl >* 5t <i- OJ CO
incMCMLncocMcnocoo
vtPxCOr- f— I—
i i i i in
I I I I «*
VO CM
co in
i— VO
r— VO
O CM
(— 00
o o
O CM I
CTi CO i
CM r-. i
O CO
P-. o
CO P-.
CTi 00
^ CO
CnOOOOVOOO«*0
cnooooo.— ooooco
«^-O00OOCMOOCTi^l-
cocMvoinOi — >^t- o f-^ <d-
LOfxLOO'JMvt'Ni — CO
r-CTlr-ISMNCOOVOCO
r^r~«i — cocnincMco>3-^f
CMCOr-»VDCOCOCTlOCOCM
<tlOOJi- i— i—
«3- o
O r—
o o
•=t
«=*■
r^
O
VO
CO
CD
r*.
LO
«d-
r~-
VD
c\i
r^
i —
CO
CM
3 CU O ■—
O 2 O rtJ
.c o s +->
i~ Q- -*: O
O i — i£ 3
2
• • O CO
s_
+J +J .1- • 1—
CD
to
to to E E o ' <0
O
i.
•r- •!- 3 CD E O O
3
CU
Q Q lO -C <— 1 O -r-
■o
E
au E
o
o
CO C C >> •> (T3 CL>
s-
4->
+->OOCJ3o3tO ••- JZ
Q_ tO
to
C -r- -r- 0) CO
CU
• 3
3 4J +J o3 E .r- O
c: i—
E
O O
O « lO 3 S- • E o3
0) •■-
to
o
c
O CD CTl-l-> C +-> O E
CT> to
S-
»—l to
O -i- ■!- C -r- tO C< tO
O to
o
+->
3
=a:s-S-cuE3i-i ■♦->
i- •■-
+J
ro
« O
S- i. E 3 -o lOU
+j s:
o
5-
S- CU
r— 1— II— 1 CD 1— C "T-3
s:
O
•i- c
ro U<h w CD
z: -o
Q-cC fO
Q- O -^ CO S- o
CU
S-
i-+JOS-S-tOf— os-
>, CU
03
o
"O i—
UtoOCUCDT-SM-Q-
CU -E
S_
o
•i- CU
r-Oli — tOtoS-tJ-r-
r— ^i
aj
3 O
CT3 S-T--r- 5- S-i— i.
i— o
c:
s
O" to
303ffll00ll)l8'r
<a o
Cl>
02
SSh ^^2:dc:c_)cc>— i
<L3
>—>
_i s:
5-
+->
OE
TABLE 11
BUREAU OF LIGHT, HEAT AND POWER
COMPARISON OF BUDGETED AND ACTUAL EXPENSITURES AND RECEIPTS
(INCLUDING ENCUMBRANCES)
FISCAL YEAR 1974-75
DESCRIPTION
EXPENDITURES
BUDGET
ACTUAL
-UNDER
+ OVER
110 Permanent Salaries
111 Allowance for Overtime
112 Holiday Pay
200 Contractual Services
231 Lighting and Heating of
Public Buildings - General
231-1 Lighting and Heating of
Public Buildings - Special Fund
231-2 Lighting of Public Streets -
Pacific Gas and Electric Co.
231-3 Lighting of Public Streets -
Hetch Hetchy
231-4 Lighting of Public Streets -
Calif. Division of Highways
300 Materials and Supplies
400 Equipment
813 Auto Insurance
860 Retirement Allowance
862 Social Security
865 Health Service System
954 EDP - PUC Data Processing
TOTAL
152,659 $ 141,444 $ -11,215
500 488 -12
400 400 -9
1,165 1,268 103
1,450,000
5,025,781
580,000
483,000
1,200
460
1,129
257
27,017
6,675
5,489
12,000
1,513,579
4,358,172
585,670
472,059
1,200
460
1,006
212
27,017
4,993
3,843
12,000
63
-667
5
-10
-1
-1
,579
,609
,670
,941
-0
-123
-45
-0
,682
,646
$7,747,732 $7,123,811 $ -623.921
RECEIPTS
Interfund Receipts*
Ad Valorem Taxes
$6,151,586 $5,882,994 $ -268,592
1,596.146 1,240,817 -355,329
$7,747,732 $7,123,811 $ -623,921
WORK ORDER APPROPRIATIONS FROM ROAD FUND
DESCRIPTION
Maintenance and Repair of
Street Lighting Installations
TOTAL FUNDS EXPENDITURE
$ 218,550 $ 217,821 $
-UNDER
+ OVER
729
"Transfers from other Departments
TABLE 12
BUREAU OF LIGHT, HEAT AND POWER
EXPENDITURE FOR ELECTRICITY FOR MUNICIPAL PURPOSES
FISCAL YEAR 1974-75
(b)
DEPARTMENT
Adult Probation (a)
Art Museum
Auditorium and Brooks Hall
Child Care Centers
City Planning
De Young Museum
Disaster Corp.
Electricity
Farmer's Market
Fire
Hassler Health Home
Health
Hetch Hetchy
Hidden Valley Ranch
International Airport
Junior College District
Juvenile Hall
Legion of Honor
Library
Log Cabin Ranch
Municipal Railway
Parking Authority
Police
Public Building
Public Works
Purchasing
Real Estate
Recreation and Park
Recreation and Park
Recreation and Park
Sheriff
Social Services
Street Lighting Operations (.003)
Unified School District
War Memorial
Water
TOTAL MUNICIPAL DEPARTMENTS
Academy of Sciences
State of California: Street Lighting
Traffic Devices
GRAND TOTAL FROM HETCH HETCHY
Candlestick Park
Yacht Harbor
NO. OF
CONSUMPTION
ACCOUNTS
KILOWATTHOURS
EXPENDITURES
1
853
24
1
1,046,400
11,748
1
4,509,600
48,707
11
264,860
6,162
1
74,220
1,531
1
3,019,200
29,613
1
78
1,802
6
422,433
7,453
1
23,052
548
58
2,880,800
59,829
1
214,800
3,204
36
16,366,466
157,324
6
128,410
3,477
1
882,720
10,385
6
189,915,674
1,588,328
24
7,566,120
81,910
3
1,426,619
14,791
1
512,400
6,730
31
2,753,996
45,543
13
367,668
10,293
38
64,798,906
648,589
18
170,489
4,133
15
897,072
18,173
9
15,038,816
133,734
103
26,311,259
326,288
5
486,490
7,385
2
390,160
7,211
207
10,194,511
177,366
2
2,182,440
49,102
32
1,309,606
28,239
3
1,323,940
13,918
5
996,526
13,575
1
45,824,647
472,059
228
30,681,335
484,912
1
1,336,000
16,611
126
43,961,713
395,726
999
478,280,279
4,886,423
2
2,680,220
24,822
1
(c)
12,614
1
315,396
6,236
1,003
481,275,895
4,930,095
Notes: (a) Account Closed
(b) Includes 147,431,772 KWH resold at Commercial rates for 1,288,848 to
Airport tenants
(c) Included under Street Lighting Operations.
TABLE 13
BUREAU OF LIGHT, HEAT AND POWER
EXPENDITURE FOR GAS AND STEAM FOR MUNICIPAL PURPOSES
FISCAL YEAR 1974-1975
NATURAL GAS
DEPARTMENT
Adult Probation (a)
Auditorium and Brooks Hall
Child Care Centers
City Planning
DeYoung Museum
Electricity
Farmer's Market
Fire
Hassler Health Home
Health
Hetch Hetchy
International Airport
Junior College District
Juvenile Hall
Legion of Honor
Library
Municipal Railway
Police
Public Buildings
Public Works
Purchasing
Real Estate
Recreation and Park
Recreation and Park - Candlestick Park
Registrar of Voters
Sheriff
Single Men's Rehabilition Center
Social Services
Unified School District
War Memorial
Water
TOTAL MUNICIPAL DEPARTMENTS
NO. OF
CONSUMPTION
ACCOUNTS
THERMS
EXPENDITURES
1
88
13
2
886
128
10
31,060
3,578
1
5,700
637
1
271,425
28,970
2
62,970
6,662
1
688
91
55
671,952
72,391
3
30,746
3,320
31
4
,906,557
465,447
2
1,202
182
5
1
,687,870
161,397
15
852,291
91,251
4
430,218
45,750
1
63,532
6,823
28
107,438
12,283
11
308,095
32,898
11
42,351
4,836
5
1
,291,707
129,595
15
287,570
36,365
3
61,918
6,892
1
19,025
1,917
106
1
,310,688
141,471
1
116,797
12,383
1
6,133
700
3
384,937
41,675
1
36,523
3,894
4
67,076
8,804
218
4
,523,886
491,249
3
247,697
26,800
11
155,270
17,128
556
17
,984,305
1,855,530
STEAM
(Does not include steam generated by City)
DEPARTMENT
NO. OF
ACCOUNTS
CONSUMPTION
POUNDS
EXPENDITURE
Social Services (a)
610,200
1,475
Notes: (a) Accounts closed.
TABll. 14
BUREAU OF LIGH1', 1IEAT AND POWER
S IZE AND TYPE OF LAMP
High Voltage Series Circuit
STREET LIGHTS IN SERVICE
JUNE 30, 1975
COMPANY- JOINTLY-
CITY-
OWNED OWNED
OWNED
TOTAL
UNDERGROUND CONNECTION
1,000
2,500
4,000
6,000
10,000
23,000
400
1,000
175
250
-Lume
-Lume
-Lume
-Lume
-Lume
-Lume
-Watt
-Watt
-Watt
Watt
n Incandescent
n Incandescent
n Incandescent
n Incandescent
n Incandescent
n Fluorescent
Mercury Vapor
Mercury Vapor
Mercury Vapor
Mercury Vapor
Low Voltage Multiple Circuit
1,000-Lumen Incandescent
2,500-Lumen Incandescent
4,000-Lumen Incandescent
6,000-Lumen Incandescent
10,000-Lumen Incandescent
5,500-Lumen Fluorescent
23,000-Lumen Fluorescent
100-Watt Mercury Vapor
175-Watt Mercury Vapor
250-Watt Mercury Vapor
400-Watt Mercury Vapor
700-Watt Mercury Vapor
1,000-Watt Mercury Vapor
400-Watt Lucalox
248
1,028
569
443
12
178
36
10
38
44
37
304
22
22
24
73
345
127
1
,537
2
,692
453
3
,033
4
,055
18
545
1
,006
45
170
218
3
3
---
10
10
2
107
107
4
58
74
2
104
284
5
85
126
14
24
38
38
4
42
112
112
3
,430
3
,474
1
,002
1
,039
4
,565
4
,869
364
364
135
135
321
321
High Voltage Series Circuit
2,500-Lumen Incandescent
4,000-Lumen Incandescent
6,000-Lumen Incandescent
Low Voltage Multiple Circuit
2,500-Lumen Incandescent
4,000-Lumen Incandescent
6,000-Lumen Incandescent
175-Watt Mercury Vapor
250-Watt Mercury Vapor
400-Watt Mercury Vapor
TOTAL, JUNE 30, 1975
TOTAL, JUNE 30, 1974
NET CHANGE DURING THE YEAR
OVERHEAD CONNECTION
1
28
42
1
70
9
9
52
7
59
8
1
9
14,705
2
14,707
1,954
1,954
890
890
20,599
700
15
,762
37,061
55.67„
1.97.
42.57.
1007.
20,725
707
15
,559
36,991
-126
-7
+203
+70
TABLE 15
BUREAU OF LIGHT, HEAT AND POWER
EXPENDITURES FOR OPERATION AMD MAINTENANCE OF STREET LIGHTING
FISCAL YEAR 1974-1975
CONTRACTUAL SERVICE
PGandE Company
Company-owned facilities (a) 829,962
Jointly-owned facilities (a) 34,898
City-owned facilities (b) 131,852
Less deduction for energy component
Emergency service to City-owned facilities
Lease-Lite Corporation
Group lamp replacement - City-owned facilities
Mahoney Electric
Maintenance and repair - City-owned facilities
Routine maintenance
Repair of damage caused by accidents (c)
Repair of damage caused by equipment failure
Repair of damage caused by vandals
MATERIAL AND SUPPLIES (FURNISHED BY CITY)
Damage caused by accidents (c)
Damage caused by equipment failure
Damage caused by vandals
ELECTRIC ENERGY (HETCH HETCHY)
45,823,986 kwh @ $0.01345 less 21% discount
TOTAL EXPENDITURE
LESS AMOUNT PAID TO HETCH HETCHY FROM:
Gas Tax Funds for State Highway routes
Recreation and Park Dept. for off-street lighting
TOTAL NET EXPENDITURE
AVERAGE OPERATING COST
Based on number of lights in service June 30, 1975, average total
cost of operation, maintenance and repair per light per year:
996,712
411,041
585,671
4,902
58,545
47
,176
34
,860
38
002
1
977
122
015
25
,872
11
418
845
38
134
486
903
1,296
170
12
614
2
240
14
854
1,281
316
34.57
NOTES: (a) Includes maintenance, repair, fixed charges and
electric energy for Company-owned facilities.
(b) Includes replacement of individual lamps and broken
glassware, service and switching charges, and electric energy.
(c) When responsible party is known, claim is filed for recovery
of cost.
TABLE 16
BUREAU OF LIGHT, HEAT AND POWER
NEW CITY-OWNED STREET LIGHTING INSTALLATIONS
COMPLETED DURING FISCAL YEAR 1974-1975
Locations
Financed by Bond Issues:
Powell and Stockton Streets
Mission Area
TOTALS
Number of
Lights
35
56
91
Type of
Lights*
Value
M $ 50,905
M 72,210
$ 123,115
Financed by State Gasoline Tax:
Geary Blvd. Underpass at Masonic Ave. 58
Webster Street--Bush Street to Geary Blvd. 22
Various Location, Cable Car Route 6
Army Street Circle Channelization - Contract 3 53
San Jose Avenue, Highland Avenue Bridge 7
Various Saftey Problem Location, Traf. Sigs. Cont. 2 5
Washington Street-Montgomery to Sansome Streets 7
Keith Street-Fairfax to Evans Avenues 2
Griffith Street and Oakdale Avenue 2
Midtown Terrace 45
Rivera Street-14th Avenue to Funston Avenue 2
Redevelopment Area D-l, Y.B., New Street No. 4 3
Minesota Street-So. 22nd Street 2
TOTAL 213
GRAND TOTAL 304
M
$
47,275
M
66,314
M
10,143
M
53,000
M
6,600
M
8,393
M
9,820
M
7,005
M
8,098
M
62,580
M
6,811
M
5,000
M
6,279
$
297,318
$
420,433
* M-Mercury Vapor
iriOfnoNco<fMminNa!<foO(N
-d'co^coors.rs.cOr-ioONOvcm
O-iinroirisjoori
ONO<ors.,^r-irs.ro
OOCMvOvtmvOOvf
ojr-i-d-r«»r-ia\cMOfnONvooof^r^«j'r^^-ioO'-|'-<mO
-tfONOOOinaoooino<fOrs.inoNOOcocM~*ininocM
•Jhn r-t r-i,-ir-icor-icor-io\coinONOoco<i-m<t
CO r-l CM CM
CM
CM
•->
00
o
on
cm
m
vO
o
1-1
co
o->
</>
.0
a
0
0)
*
C
■y>
nj
a
^-<
u
^
m
■1)
3
u
0
■
Cfl
•rJ
:■:
— i o>
in CO
no cm
co O co
00 co in ro
co oo no on
in o oo eh
^ H N
I I I I
co on
>.
QJ
a
•
u
*
jj
ca
j=
a
*j
61'
0.)
ca
n
SB
4-1 (0
a. c
o 3
0.
in r> is «3
\0 CM u-l i-l
(N CM vO ON
CM vO CM
st CM v*
I I I I
•j-moo<t»coNt-i«3-vovOCvom o
OON-d-oomONCirseir-somrs. O
nO CO CMrs.00OmON\£)r-ICM00 to
rs.CM r-< r-l CO —I r-l CM CO
m <-t
60
u
C in
a)
•^ -a
a)
*-> c
^
x o
4J
so ca
w
•H
►J
ON
ON
00
Cn)
CO
ON
CM
CM
o
o
o
CM r-l
<}• r-l
>* o
i— 1
CO
CM
CM
CO
00
CO
CO
nD
r-l
NO
I-l
NO
CM
o o
UO r-l
u-i CO
I-( r-l
1 njO
CO
CM
ro
CM
.— i
</>
ON
si-
f—1
rs
ON
u
.-I
ca
0)
u
>-.
ca
o cd
cfl
O
E
0)
S-i
W
o
<D
r-l
X
«
d
>
<
H
in
r-l
rs
o
I— 1
CM
r~-
NO
si-
CO
CO
GO
NO
CO
st
cr-
ON
in
i-i
<t
<t
«*
CO
— i
a.)
CM
«*
s+
vO
CM
rs
•->
CM
o
<r
r-s
NO
^t
CM
co
CO
CO
r-l
NO
I— 1
t— i
r-l
oc
NO
NO
ON
CO
i-l
O
-J
co
r-l
CO
NO
r-l
a-
CM
\D
o
in
NO
rs
CO
rs
Csl
O
CO
kO
«tf
I— I
O
CM
O
<t
O
r»
sf
,_|
m
<t
ON
o
r-l
--<
^3
|S
i— i
CM
CO
s-t
CM
NO
r~-
o
CO
O
00
«tf
ON
rs
. — 1
is
is
m
ON
<t
lO
NO
ON
NO
i-i
r-l
CM
CO
st
•— 1
i— i
CO
co
<f
LO
<f
CM
CM
H N <f 00 H
m cm o no o
r-< rs rs i— i m
•>•>•> i i i i i i i
oo cm in m vf cm
>d" s* in •— i
fS. r-l r-l
coco-J-mNOrs-ooONOi-iCMcOsl-invors.ooONOr-icMrOsj-
mininmmmmmNOvONON0^3vovONONOvor>.rs.r»r>.rs.
ON QN ON ON ON ON ON ON ON CTN ON ON ON ON ON ON ON ON ON ON ON ON ON
CO
ON
(J
60
CO
ca ca
CO
u
C
a)
• 13
o
•r-l
m
•r-l
u
u
3
•.-I
<o-
D, -o
^
ON c
•n
T)
u
r-l O
ai
«
ca
nO
>
o
>
o
U-I
co rt
CM
ON
E
(1)
u
e
u
•a
0)
c
on a>
r-l U
00
03
V)
5
O
< pi
■— 1
C
o
c
o
■
>N
CM
•r-l
4J
•H
cd <-<
•r-l
■CO-
M
0
o
o
a
D.
14-1
< 5
■H
U-I
a, o3
O
O
4-1
S __,
4J
4-1
O
co 5
U)
(0
u
o
O
*9 M
u
u
r-l
ca
r3 "H
OT
c
y §
c s
3
CO
•1-1
60
H
CO
•r-l
o
•
u
H
r-l
o
■X
00
h
r.
a-
1-4
V
U
:-•
3
a
*0
a>
u
c
■
o
■r-
a
h
I-H
u
CO
u
C
4
CJ
■r-l
h
o
M
i-i
—
iH
c
u
U
o
£
c
u
v.
|
c
CO
£
6
m
e
2
i
<
g
«4?
ri
(>j
o
G°*
UJ
o
r— 1
H
<
2
o
^
£
M
H
CJ
£
OS
53
s
H
CO
CO
2
M
ps
O
fa
u
CJ
H
g
x; c
o o
•-} en
a
n
o
o
o •
o •
O •
o •
u o
cj o
O CJ
o o
a
c
c
c
•a m
T> M
XI M
■a m
c
c
c
c
3 «
3 •>
3 «
3 «
O •
O •
O •
O •
t-i O
u o
I-i O
Im o
t>0 CJ
60 CJ
60 CJ
60 CJ
l-i
h
l-l
U
0) c
0) c
CU C
<U C
•a o
T3 O
•o o
X> O
C l-l
C i-<
C i-l
C 1-1
» JJ
& 4J
!=> -U
D 4J
>-,
E
e
B
B
4-1
CU
e
0)
cu
CU
CU
0)
t-l
cu
4-1
OJ
>»
4J
4-1
tu
t— 1
4-1
co
0)
CO
CO
CO
)M
CJ
o
10
>>
r^ Ct
>•>
>. 4J
>
u
T3
r^
A
co
CO
I
CO
CO
CO
<
H
C
CO
CO
(M
4-1
I4M
«m
cB
4-1
cu
0)
4-1
x.
4-1
O
4-)
4-1
4-1
r-l
XI
u
o
60
u
>
01
O
J-I
a
1
CJ
0)
CJ
m
4J
c
o
C
c
3
O
u
3
co
3
4J
3
OJ
3
>
o
i-l 4J
PS
•r-1
1-1
O
CO
Cm
4J
O
O
J=
O
IM
a
CO
CN|
CO CU
cn
CO
u
4->
CO
o
60
4J
)M
Oh CU
•a
a)
60
X.
>a
0)
•a
•o
4-1
"O
i-l
T)
CO
•v
CO
o
>H
E
c
u
c
60
e
c
CU
B
01
B
c
PS
C
c
H
4J
•a *j
O
cfl
u
•H
•H
CO
CO
l-l
3
u
3
x;
3
3
c
3
C CO
o
0
"3
►J
Q
i-J
O
0
O
4->
o
H-l
O
o
o
^
4J
co
PS
CO
60
s
CU
co
M
B
u
r^
l-l
u
CO
l-l
c
fa
C
•r-l
>M
>•>
r-4
60 r-l
60
60
60
c
60
O
M O
4J
O
•H
u
3
o
CO
O
c
l-l
l-l
u
i
U
^
}M
0)
u
01
U
•r-1 t-4
c
JZ
4J
co
«
1-1
CO
jC
o
CU
1-1
cu
CU
<U
>
CU
>
•i-l
co to
•l-l
co
c
u
cu
C
1-1
-3
fa
CO
T3
4-1
T3
T3
TJ
0)
•3
<
u
O- co
tfl
1-1
0J
r-l
0)
c
CO
CO
C
CU
c
cu
C
C
C
4J
c
cu i-i
fa
c
CO
>
(4
4J
JC
rS
CO
r=
>-.
»
CU
-3
cO
&
CO
tr>
r-4
CO
OS S
•H
fa
4J
c
60
1-1
cn
CO
l-l
nj
■r4
u
(0
i-J
U
M
3
4-1
X
4J
a>
tc
u
u
4-1
4J
-o
4-1
4-J
O
- c
o
co
l-l
CO
O
n)
u
a
•h
CJ
co
CJ
CU
CJ
c
o
u
c
cu o
3
o
O
>
Cm
CU
x:
3
•a
4J
O
3
3
>
3
CO
3
o
CO
u
l-l
o
•!-(
(-1
o
CO
U
c
u
•r-l
4J
M
4-1
l-l
<
l-l
u
Cm
u
co w
4J
o
u
CJ
«0
«0
u
CO
4J
r-4
j-i
<u
JJJ
4->
u
4-1
fa
r-4 cu
(0
S
01
CO
i-M
r-4
o
CO
CO
■rl
0)
CO
r^
CO
X.
CO
0)
CO
4J
a r-i
c
4-1
<u
CO
ex
C
•o
C
O
c
C
u
C
4J
c
^
c
CO
cu o
o
4->
X
u
01
CU
4-1
O
c
o
CO
i-i
o
CO
O
O
o
CJ
o
0)
4-1
OS cu,
u
<d
w
fa
H
OS
c«
CJ
CN
CJ
fa
fa
CJ
X
o
r-l
CJ
w
CJ
3
CO
l-l O
r^
CO
CO
4-> 2
-*
<j-
■*
c
I
i
o
xc
tc
tr
CJ
re
S
0-.
_*:
i-.
o
ac
i.
r-c
C
X
u
lm
t-.
:■■
O
3
Q
■
cti
9
01
U
^<
B
LI
<T3
0
•-<
>
Q
EK
i-l
60
u
JZ
C
3
B
1-1
M
3
u
4-1
l-l
a
(0
a,
i-i
c
cd
o
h
Cm
CJ
01
u
4-1
CQ
S
01
>
£
->
« s
04 S
CD '
c
o>
4-1
4-1
JJ T3
•1-4
4J
CO
CO
CO >
hJ
^
CO
>m-<
i-i
0)
CJ
>.-a
c
co m
c
1-4
CO
o
CO
cd
c
cd
o
(0
3
4J
o
o
>N
4-i rt
1-1
O.
O
CO
•a
4J
u
c
u ^
CO
01
33
C
0)
u
ta
CO
cd
3 W
co
OS
eg
x:
3
0)
4-1
Q 0)
•r4
01
0-.
CO
o
■a
r-4
CO
co
e
T3
>
c
o
TJ
m
C
Ol
01
4J
-o
cd
0-.
c
c o
c
a)
cd
co
60
0)
c
a>
3 )-!
cd
>
3
cd
OJ
3
j-.
>N
CU
O 01
M
co
00
O
u
i-l
O
a.
cu
»
i-i a.
H
I-i
c
M
.c
o
4-1
u
I-I
4J
60 i-l
0)
•r-l
a)
u
4U
CO
60
td
1—1
01 •
M C
.*:
5
a
>
to
CO
kl
T3
o
-Q 01
0) 3
)->
o
i-i
i-i
s
4->
cu
c
1-1
>
•o »-j
0)
(0
H
PL.
04
o
1
c
X)
to
H
4J <J
C
>
S
Ol.
cd
c
04
o>
so -
<
0)
i-(
»
c
U-l
s^
3
1—1
0) i-l
•
2!
0)
01
i-i
B
o
M
*i
01
i-i cd
4-1 a)
T3
1
0)
z
3
1—1
o
a
4-1
o>
4-1 U
o >
i—i
C
4-1
cr
o
04
O
CU
4-1
CO 4J
3 <
o
•H
co
r-4
cd
X
t-4
3
>
co
c
U
u
0]
1-1
o
u
o
U
•<
4-> 01
4J C
<d
cd
4J
cd
^
4-1
•■-4
»*
4J
4J
JB CJ
co cd
db
u
c
4J
c
cd
1—1
CO
JS
c
60
C 01
cj
•1-4
10
c
1-1
a
e
4-1
•r-l
•i-4 T3
o o
o
o
ca
C
cd
cd
0)
4-1
o
ON
cd
<d c
u o
4-1
X
0^
M
CO
a*
04
cd
CJ
■-I
O-i
SB cd
c
0!
o
CJ
4J
1-1
3
4-1
4->
o
cd
CJ
Sj
z
3
1
I-l
0)
-o
4-1
04
a)
M
u
o
M
>-.
!B
c
cfl
•H
L)
U-l
V-i
:••
0
:>
a
. <
<u
cd
:J
U
o
H
a
gg
«
0
•r(
>
Q
to
«
u
v
a
m
u
•H
>-i
•H
CUj
u
u
r)
a
Cm
ft!
§
o
co
CL,
H
m
U
r~-
§
3
1
<
B
Pi
o
H
w
u
H
«<
z
S
o
UJ
M
6m
u
H
U
3
H
3
O
w
H
cc
K
to
H
!S
tn
EC
O
U
O
H
W
w
c
Q,
n)
o
o
u
r-l
ti
Pi
<4-4
CO
to
o
o
M
•
a)
u
u
u3
a»
CM
5
1
Ph
r~
jr
c
o
XI
CN
4-1
iH
>
r-t
*;
</>
Vj •
3
rfl
•H
u
O O
u
(-4
■s
o
CSJ
2 O
lu
G
CE
to
4J
u
O
a>
to
>
u
o
4-1
o
c
o
ua
C_>
to
>.
a)
x:
§
3
3
3
Q
Q
3
O
O
•H
TJ
X)
•H
4J
3
3
•
4J
CO
3
3
X)
CO
4-)
O
O
>
4J
CO
U
u
iH
W
J3
00
60 m
XI
3
u
M
3
co
CD
<u
tfl
CO
XI
X)
n
4->
3 4J
3
n
(-1
CU
D QJ
o
CD
01
0)
0)
en
4J
n
4J VJ
4-1
3
4J
CJ 4-1
o
O
01
CO
3 CO
3
M
u
M
M
0)
.3
4J J2
4J
D.
CJ
o
to to
CO
•H
•H
1-1
3 xi
3
3
>
3
O 3
O
3
•H
£!
U i-)
c_>
^
U
U
4-1
X!
0)
3
K
to
S
O
X)
0)
4J
J=
3
to
3
•H
O
Ej
B
■9
3
En
Pi CO Pi
<i co <!
1975 ANNUAL REPORT 1976
O'SHAUGHNESSY DAM FEB 28 1978
DOCUMENTS DEPT.
S.F. PUBLIC LIBRARY
*
HETCH HETCHY
WATER AND POWER
^
PUBLIC UTILITIES COMMISSION
CITY AND COUNTY OF SAN FRANCISCO
CITY AND COUNTY OF SAN FRANCISCO
PUBLIC UTILITIES COMMISSION
ANNUAL REPORT
FISCAL YEAR 1975-76
HETCH HETCIIY WATER AND POWER SYSTEM
AND
BUREAU OF LIGHT, HEAT AND POWER
0. L. MOORE
GENERAL MANAGER
CITY AND COUNTY OF SAN FRANCISCO
GEORCE R. MOSCONE - MAYOR
PUBLIC UTILITIES COMMISSION
JOHN F. HENNING,
DENNIS V. CAREY
H. WELTON FLYNN
JOSEPH F. BYRNE
LYDTA LARSEN
JOHN D. CROWLEY
Jr
President
Vice President
Commissioner
Commissi oner
Commissioner
General Manager
ANNUAL REPORT
FISCAL YEAR 1975-76
HETCH HETCHY WATER AND POWER DEPARTMENT
ORAL L. MOORE - General Manager
This report is respectfully dedicated to
Hetch Hetchy employees, past and present,
whose devoted nnd conscientious efforts have
made possible these accomplishments for
San Francisco.
The picture on the front cover of 0' Shaughnessy Dam
was taken on June 7, 1923, before the dam was raised
an additional 85.5 feet.
In the 75th year since the first lands were acquired for the
Hetch Iletchy Water and Power system, and in the midst of a very
dry year, it is fitting to recognize the foresight, industry
and dedication of the people who conceived, huilt and operate
that system. One and three-quarter million San Francisco Bay
Area residents receive a supply of first quality water from
Hetch Iletchy. How did it all come about?
The Metropolitan Bay Area of 1(J01 consisted of a San Francisco
of 350,000 population, and a collection of small, quiet towns
around the Bay. Booming growth, a high level of civic pride,
and the belief of every citizen that San Francisco was to be
the leading metropolis of the Pacific Coast were the keynotes
of the times.
Some dissatisfaction with the commercial supplier, the Spring
Valley Water Company, prevailed, occasioned by high rates,
periodic shortages and recurring water quality problems. That
dissatisfaction had prompted language in the Charter enacted
in 1900, setting as a goal the acquisition and construction of
a municipally owned water supply system. What was needed was
a plentiful, high-quality water source that would meet the
area's need for at least 100 years. Looking east to the Sierra
Nevada, the planners found such a source in Yosemite National
Park. But the water was 150 miles away!
The "City that knows how" was determined that the water system
would be built, and the first land was purchased, and water
rights established, in 1901. The ensuing struggle for permis-
sion to build a dam in Hetch Iletchy valley went on for years.
When the United States Congress confirmed the City's right to
proceed in 1913, construction commenced on the largest such
project on the Pacific Coast up to that time. After 21 years,
and the expenditure of some $100 million, the first water
arrived at Crystal Springs Reservoir via the Hetch Iletchy
aqueduct in 1934. The drama surrounding the leadership, poli-
tics, and the engineering and construction effort involved in
the project would be worthy of an epic novel, as expansion of
the system to meet water and power demand continues down to the
present .
The large and complex system was designed to be built in incre-
ments as demand increased. The master plan concept of a full
gravity aqueduct system to Crystal Springs, established in 1912,
has been followed as the system has grown through the years to
the present capacity of 300 million gallons daily. As a by-
product of the falling water, hydroelectric generating capa-
bility of 340 megawatts has been constructed; a major economic
asset for San Francisco. Additional elements of the system are
planned for construction as the demand increases.
1 -
Today, the benefits of the Hetch Iletchy project are so matter-
of-factly accepted that the public has granted the system its
highest accolade: cheap, pure and plentiful water is taken for
granted!
- 2
The last concrete in the original 0' Shaughnessy Dam
construction was poured in April, 1923, bringing the
total to 398,000 cubic yards. The height of the dam
was 226.5 feet above the original streambed and 344.5
feet from the bottom of the foundation. It was 298
feet thick at the base and 15 feet at the top. At the
time it was constructed, it was the second highest dam
in the United States, Arrowrock in Idaho winning by
ten feet. Between 1934 and 1938 it was raised an
additional 85.5 feet.
HIGHLIGHTS
Financially, the outcome of Hctch Hctchy's Water and Power
system operation for 1975-70 was influenced by two major events
which occurred during the year - one man-made and the other
the result of a natural occurrence.
Breakdown of wage negotiations for the upcoming fiscal year
between City's crafts workers and the Board of Supervisors
resulted in a 38-day strike by City employees including electri-
cians, plumbers, carpenters, laborers, street cleaners, etc.
who are members of the crafts union. The strike began March
31, 1976 and ended on May 8, 1976. The public transit system
was quickly brought to a halt when the Municipal Railway drivers
joined the strike at the very outset. The importance of the
Hetch Hetchy Water and Tower system operation to the success or
failure of the strike was not to be overlooked. It, too, was
forced to shut down with all hydroelectric generators stopping
production at 1400 hours on April 2, followed by complete
cessation of water delivery to the San Francisco Water Depart-
ment for domestic purposes.
The drought brought on by the lack of precipitation in the
winter of 1975-76, resulting in the smallest snow melt runoff
from the Hetch Hetchy, Cherry and Eleanor Watersheds in the 59
years of record, has left the three reservoirs at less than
60% full at the end of the report year. In order to conserve
as much water as possible for domestic use in the Bay Area, the
average daily power draft at Kirkwood and Moccasin Powerhouses
beginning June 1, 1976, was reduced to 300 million gallons per
day to coincide with the Hetch Hetchy Aqueduct capacity and the
anticipated San Francisco Water Department demand for the next
several months. In addition, the power draft at Holm Powerhouse
was reduced to 200 cubic feet per second in order to conserve
water at Lake Lloyd so that, if later conditions require, such
water can be directed into the Hetch Hetchy Aqueduct.
HETCH HETCHY ORGANIZATION AND FUNCTIONS
Under policies established by the San Francisco Public Utilities
Commission, the HETCI1 HETCHY WATER AND POWER DEPARTMENT and the
BUREAU OP LIGHT, HEAT AND POWER serve the City and County of
San Francisco in the dual function of operating department and
service bureau.
Iletch lletchy is a municipally-owned system of storage reservoirs
and aqueducts which collects water from the Tuolumne River
watershed and delivers it to the San Prancisco Water Department.
As a by-product of falling water, Hetch Hetchy operates and
maintains hydroelectric generating stations and high voltage
transmission lines for the production and distribution of elec-
tric energy.
Through its Transit Power Division, Hetch Hetchy has funded,
operated, maintained and provided improvements for the electric
facilities of the San Prancisco Municipal Railway since July 1,
1969.
In order to handle this additional responsibility, Hetch Hetchy
assumed control of the equipment and personnel of the Overhead
Lines and Motive Power Sections of the Municipal Railway.
All of Hetch Hetchy' s expenses, including those of the Transit
Power Division, are supported by water and power revenues.
The Bureau of Light, Heat and Power administers contracts for
furnishing electric, gas and steam services to municipal depart-
ments and handles monthly billings. It also administers con-
tracts for furnishing street lighting services and for operation
and maintenance of City-owned street lighting. Financing,
design and construction of City-owned street lighting improve-
ments are under the jurisdiction of the Department of Public
W7orks, and plans for these improvements must be approved by the
Public Utilities Commission through this Bureau. The Bureau is
financed by appropriations from municipal departments and gas
tax funds.
For fiscal year 1975-76, the Department administered budgeted
funds for all purposes as follows:
Budget
Hetch Hetchy Water and Power
Hetch Hetchy Water and Power
(Transit Power Division)
Bureau of Light, Heat and Power
Number
of
Total Amount
Employees
Appropriated
219
$ 21,350,716
52
4,505,194
11
9,493,990
282
$ 35,349,900
- 5
O1 Shaughnessy Dam as it looks now.
PLANS FOR THE NEAR FUTURE
Plans for future Hotel) lletehy construction are included in the
City's current Capital Improvement Plan.
Projects which will be added next year will include the
following :
Cherry Eleanor Pumping Station
We have studied the possibility of installing pumps at the
Cherry end of the Cherry Eleanor Tunnel. This study determined
that it was economically feasible to capture, for electrical
generation, water which presently spills at Lake Eleanor during
the runoff season. Preliminary design work will commence this
year, while the necessary permits and approvals are being
obtained.
Moccasin Powerhouse Bypass
Studies are planned to make improvements on Rattlesnake Creek
and Rig Jackass Creek to permit the discharge of water from
Priest Reservoir into the Hetch Hetchy Aqueduct for use in
times of emergency when Moccasin Powerhouse is not operative.
HETCH HETCHY WATER AND POWER SYSTEM
REVENUE AND EXPENDITURES
Revenue from Hetch Hetchy Water and Power operations is derived
principally from two sources:
1. Sale of electric power and energy to San Francisco Municipal
departments, Modesto and Turlock Irrigation Districts in
the San Joaquin Valley, and seven industrial customers.
Kaiser Cement {j Gypsum Corporation Santa Clara County
Kaiser Aluminum § Chemical Corporation Santa Clara County
Lockheed Missiles and Space Company, Santa Clara County
Inc.
General Motors Corporation Alameda County
IBM Corporation Santa Clara County
Liquid Air, Inc. Alameda County
Norris Industries, Riverbank Stanislaus County
2. Sale of water to the San Francisco Water Department.
POWER SALES
Gross sale of electric energy amounted to $20,224,183, up from
$18,484,718 during 1974-75. Although this revenue appears to
be a new record, it does not have the same significance as the
record revenue of last year. The reasons are not so obvious
without knowing the following:
(1) Much of the increase is due to the very large amount
of supplementary power and energy which City had to
purchase for resale and which was resold to the
customers at substantially the same high price at
which it was purchased.
(2) The offset to last year's record revenue in terms of
expenditure for supplementary power and energy was
only $99,734, whereas this year the offset is
$4,389,319. Therefore, from the standpoint of net
earnings, the department finds itself in a much less
profitable financial position than that of last year.
Power and energy delivered to all City Departments increased
1.91 over the previous year, mainly the result of increased
consumption at the San Francisco General Hospital where addi-
tional power for construction of the new facilities nearly
doubled the total requirements of 11,091,942 kilowatthours for
1974-75. Consumption at the Airport, usually the single largest
energy consumer among the City departments, has remained sub-
stantially the same as 1974-75. The requirements for the San
Francisco Water Department have again increased 9.3%, reflecting
more [lumping required by the drought condition. The Municipal
Railway showed a decrease of 12.2% in annual consumption over
the previous year, largely as a result of the Muni shutdown
during the City employees' strike.
Power and energy delivered to Modesto Irrigation District,
Hetcli Metchy's largest power customer, and to Turlock Irrigation
District, the third largest, increased by 17.71 and 13.6%
respectively this year. These increases in purchases clearly
reflect the dry year operation of the Districts' own plant where
power is derived from water stored behind Don Pedro Dam.
The hope of exceeding the record generation of 1974-75 was
effectively shattered by the drought and the strike. Instead,
the opposite was achieved with the lowest production recorded
in seven years of operation of the present project. By
comparison, the 1975-76 total output of 1,640,671,000 kilowatt-
hours is 201 less than the record output of 2,057,609,000
kilowatthours for 1974-75.
Hetch Hetchy power is sold to City Departments at cost, repre-
senting a saving to taxpayers for 1975-76 of approximately $3.2
million compared to the cost if supplied by the local investor-
owned utility.
One of the benefits resulting from the June 24, 1975 Amendment
Agreement witli the Pacific Cas and Electric Company for wheeling
Hetch Hetchy power to City's municipal customers was the reduc-
tion in energy which City has to supply to compensate the
Company for losses incurred in transmission and distribution.
The data for 1975-76 indicates that 33,248,681 kilowatthours
was delivered to the Company for this purpose, almost 41,000,000
kilowatthours less than that required under the old agreements.
This reduction in losses when sold to industrial customers at
prices effective during the year returned to the City additional
revenue in excess of $650,000.
In last year's annual report, it was estimated that the new
electric power rates which were scheduled to go into effect
July, 1975 would increase Hetch Hetchy' s power revenue for 1975-
76 from sales to the municipal customers (including resale to
Airport tenants) by one million dollars. Comparison of results
for 1974-75 and 1975-76 has confirmed the accuracy of this
prognostication. Another revision of the rates is scheduled
for action by the Public Utilities Commission in July 1976.
Adoption of the proposed rates will boost revenue from sales to
private consumers and municipal users another $900,000 in the
upcoming fiscal year.
August 1975 marked the first month of higher rates for Hetch
Hetchy power sold to the Modesto and Turlock Irrigation Districts
under signed agreements with them dated May 22, 1973 and
November 6, 1972 respectively.
9 -
WA'IT.R SALliS
This past year, revenue from sale of water and standby service
to the San Francisco Water Department was $6,550,000, $428,000
less than cost to Hetch Hetchy.
10 -
The Supervisors' inspection party on Red Mountain
Bar Cableway - July 14, 1927.
Miscellaneous
Revenue
HETCH HETCHY REVENUES
AND EXPENDITURES
FISCAL YEAR 1975-76
LI
CO
or
o
?b
20-
15-
10-
SUPPLEMENTAL
1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976
( Yea r Ending June 30 )
HETCH HETCHY POWER SYSTEM OUTPUT
20-
CO
or
o
o
o
CO
o
10-
5—
1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976
( Year Ending June 30 )
REVENUE FROM SALE OF ELECTRIC ENERGY
12
WAT1-R PRODUCTION AND TRANSMISSION
Precipitation recorded for the year at our measuring stations
was 58* of the long term average.
During the year, 70,086,900,000
from the Tuolumne River watershc
Aqueduct to the San Francisco Wa
71° of the City's total customer
2 37,69 3,4 56 gallons were deliver
Atomic U.nergy Commission at Moch
Range Tunnel for use at the I.awr
Livermore; 49,306,396 gallons we
Community Service District in Tu
Tunnel .
gallons of water were diverted
d through the Hetch Hetchy
ter Department, representing
consumption. In addition,
ed to the United States
o Shaft of the City's Coast
ence Radiation Laboratory at
re delivered to Groveland
olumne County from the Mountain
Appendix Table 6 shows comparative data on precipitation,
runoff, storage and delivery of the Hetch Hetchy Water Supply
System.
300,000
CO
o
I—
o
LU
or
200,000-
100,000-
0 —
1 1971-72 ' 1972-73 ' 1973-74 ' 1974-75 ' 1975-76 '
DELIVERIES OF WATER TO
SAN FRANCISCO WATER DEPARTMENT
13
Woodrow Wilson, President of the United States,
presented this plaque to the Honorable James Rolph,
Jr. , Mayor of San Francisco, expressing his support
and enthusiasm for the Hetch Hetchy Act.
OPERATING AND MAINTENANCE - MOCCASIN DIVISION
HOLM POWERHOUSE UNIT NO. 2 GENERATOR
At approximately 0842 hours on Sunday, January 25, 1976, the
13,800 volt stator winding of Generator No. 2 at Dion R. Holm
Powerhouse failed. Preliminary investigation indicated that
approximately 8 of the 216 coils had been damaged. However,
detailed examination following removal of the rotor assembly
disclosed that a total of 16 coils would have to be replaced.
Several of these coils were still functional, but dc high
voltage testing showed that they would probably fail in a short
time and were therefore deemed unacceptable for continued use.
Portions of insulation on 4 field poles were also damaged by
hot metal splatters from the stator windings when the failure
occurred, requiring re- insulat ion of the affected area. All
repair work was performed by departmental personnel, with
supervision provided by the field engineers from All is-Chalmers ,
the generator manufacturer. The repairs were completed and the
generating unit returned to service by the middle of March.
A board of inquiry consisting of the senior electrical engi-
neer inc. staff members was formed to investigate the failure for
cause and to recommend corrective measures. A final report is
expected to include analyses and possible solutions to this
maintenance problem whereby the reliability of the equipment
can be improved.
CHERRY DAM HOLLOW JET VALVE REPAIRS
The Machine Shop repaired one of the two 60 -inch valves used to
release water from Lake Lloyd. The valve was leaking badly and
water had gotten into the operating mechanism. If allowed to
remain in place, it would have been necessary to replace the
valve in a short period of time. It was necessary to build up
and machine the body and plug seats, replace a brass bushing,
a leather packing and two thrust bearings. Other miscellaneous
repairs were made to broken or defective parts. The Mechanical
Engineering Section provided engineering and procurement assis-
tance to the Machine Shop, including inspection of work done to
the plug seat by a local shop. At the end of the fiscal year,
repairs were nearing completion and the valve will be available
for use during the next runoff season.
EARNER JOHNSON RE LI EF VALVE NO. 2 AT SAN JOAQUIN VALVE HOUSE
The relief valve on Pipeline No. 2 at the San Joaquin Valve
House was removed from service during pipe cleaning and painting
(HH-511R). The machine shop used this time to completely
rebuild the valve including braising and remachining the seats.
15
The old Moccasin Powerhouse completed June, 1925.
The new Moccasin Powerhouse completed May 20, 1969,
OPERATION AND MAINTENANCE - TRANSIT POWER DIVISION
The Transit Tower Division is responsible for supplying the 600
volt direct current power that is necessary to operate the
streetcars and trolley coaches of the San Francisco Municipal
Ra i Lway .
The Transit Power Division is composed of two sections - the
Motive Power Section and the Overhead Lines Section.
Motive Power Section
The Motive Power Section operates and maintains seven sub-
stations which convert electric power from 12,000 volts
alternating current to 600 volts direct current by means of
motor-generators, synchronous converters, and mercury arc
rectifiers. (See Appendix Table 3 for statistical data.)
Motive Power is also responsible for maintaining the electric
motors and associated control equipment for operating the
cable-winding machinery located in the Cable Car Powerhouse at
Washington and Mason Streets. In addition, Motive Power does
periodic inspection, cleaning, adjusting and repairing the
streetcar and trolley coach recorders at Central Control of the
Municipal Railway. The substations operate 24 hours per day,
36 5 days per year.
In anticipation of the need to assume responsibility for eigh-
teen new substations, this section perused and commented on the
wiring and control schemes proposed for these stations.
A new mimic board showing the new stations in schematic form
was constructed and installed at the Bryant Substation. As new
automatic stations are completed and become operational, they
will be monitored and controlled from this remote location.
Since Outer Mission and West Portal Stations are presently
unmanned, controls for these stations were designed and
installed on this new mimic board. This new status display
and control board will continually be augmented with new
automatic station controls until such time as it shall be super-
seded by a more sophisticated and flexible Supervisory Control
System.
Overhead Lines Section
The primary function of the Overhead Lines Section is to main-
tain in satisfactory operating condition the trolley wire over-
head facilities and the electric distribution system which
conveys power to it. This electric distribution system consists
of both overhead lines and underground cables.
17
Secondary functions include the maintenance of the Municipal
Railway Signal Systems and the electric light and power systems
of all Municipal Railway buildings.
During the fiscal year 1975-76, the Overhead Lines Section
responded to 3606 emergency calls. In addition to emergency
calls, this section had a regular and extensive maintenance
program for overhauling all overhead and underground facilities.
This section operated with three shifts per day, seven days a
week. Monday through Friday, the normal workday shift was from
8:00 a.m. to 3:30 p.m. with a two-man emergency crew on the
"swing" or evening shift (3:30 p.m. -10:30 p.m.) and the grave-
yard shift (1:00 a.m. -8:00 a.m.).
On Saturdays, Sundays and holidays a two-man emergency crew was
available on each of the three eight-hour shifts; midnight to
8:00 a.m., 8:00 a.m. to 4:00 p.m., and 4:00 p.m. to midnight.
Overhead and underground facilities were systematically
inspected, and worn or damaged parts were replaced before they
could cause accidents or malfunction of equipment.
A considerable amount of damage to overhead facilities was
caused by trolley coaches de-wiring and snagging their poles in
the overhead facilities and tearing them down, or by breaking
the spans with the flaying poles. Such damage was repaired at
no cost to the Municipal Railway. Other parties who damaged
our facilities were billed for the cost of repairs. This
included damage to overhead facilities caused by high loads on
trucks or careless operation of crane equipment and damage to
underground feeder cables by contractors digging into our duct
lines. During 1975-76, responsible parties were billed for 7
damage cases totalling $3,728.53. The Overhead Lines Section
also performed work for building owners and contractors under
work orders amounting to IS jobs totalling $44,183.13. This
work included moving trolley poles to accommodate driveways;
relocating trolley poles and feeders to permit construction of
new buildings; temporarily removing trolley wires and feeders
to permit passage of high loads: and shifting of trolley wires
and feeders for various excavations.
The Overhead Lines Section engaged in many other activities of
a related nature which it is especially equipped to perform.
These additional duties included repairs, maintenance and
construction of electrical systems in Muni's car barns, offices
and shops; welding and rebuilding of worn overhead lines special
work; making and rebuilding parts for switches, warning block
signals, car recorders, and strand alarms for the cable car
system; installing mobile radio equipment; installing streetcar
and bus stop signs and public information signs.
In March 1976 the section curtailed operations for a six week
period during a labor dispute involving city Craft workers.
18
:
Mr. 0' Shaughnessy, City Engineer, inspecting
project on August 11, 1918.
ENGINEERING DIVISION
The Engineering Division of Hetch Hetchy Water and Power provides
engineering services for the Hetch Hetchy Project and the Transit
Power Division. These services include the preparation of
studies, reports, cost estimates, and plans and specifications
for new construction, for replacement of structures and for items
of major maintenance. Surveying, inspection of construction,
contract administration and payment recommendations are provided
for all construction work under Hetch Hetchy Water and Power.
Work of unusual magnitude or which requires special knowledge
and expertise is done by engineering consulting firms which have
the necessary manpower and qualifications. The Engineering
Division is organized into five main sections: Structural and
Civil, Electrical, Mechanical, Architectural, and Construction.
During the year, plans and specifications were prepared for the
following work to facilitate and maintain Hetch Hetchy operations
[IH-454 - Reconstruct Moccasin Sewage Disposal System.
A package sewage treatment plant producing an odorless effluent
and sludge has been planned to replace the existing septic tank
system. This project is a carryover from last year due to the
slowness to acquire approval for the Federal "Clean Water Grant"
which we reapplied for last year. Conceptual approval has been
received. The EIR and the Project Report received approval from
the State Water Resources Control Board, and we are now awaiting
Federal EPA approval. The Hughes site for the effluent sprinkler
field was purchased during the year.
HH-477 - Moccasin Penstock Valve House.
A contract was let for the construction of a steel frame struc-
ture to enclose the butterfly valves at the head of Moccasin
Penstock. This structure will provide protection and security
for the valves.
HH- 511R - San Joaquin Pipeline No. 2, Repair Lining.
A contract was let for cleaning the interior of the pipe and
applying a coal-tar lining. This work was necessary because
the existing cement mortar lining, which protects the steel pipe
from corrosion, has been softened by action of the soft water
and the invert is being eroded away.
HH-512 - San Joaquin River Valve House, Repairs and Piping.
Under this contract, which was completed during the year, new
sump pumps and related piping were installed at the San Joaquin
River Valve House. Also, under this contract, a leaking manifold
at the valve house was repaired.
2n
HH-51 4 - Moccasin Administration Building, Replace Heating
System.
The plans and specifications to replace the existing oil burning
steam heating system and bring ihe electrical service at the
building up to code were completed and bids opened this year.
The existing heating system had become expensive to maintain
and operate because of its age and its use of fuel oil. The
replacement of the oil by electric heating necessitated increas-
ing the capacity of the building electrical system, and improv-
ing it to meet code requirements.
IIH-539 - Repair and Taint Concrete Trolley Poles (Van Ness
Avenue) .
A contract has been let to repair and paint concrete trolley
poles on Van Ness Avenue. This work is part of a program to
rehabilitate all trolley poles in the City.
Mil- 54 5 - Repair, Reroof Hetch Hetchy Buildings, Moccasin and
Early Intake.
A contract was let for the reroofing of the Machine Shop and
five (5) cottages at Moccasin; reroofing Kirkwood Powerhouse at
Parly Intake, and replacement of parapet flashing and construc-
tion of joint flashing at Holm Powerhouse near Early Intake.
HH-553 - Replace, Repair and Paint Steel Trolley Poles (Mission
Street) .
Contract plans and specifications have been completed to
replace, repair and paint steel trolley poles on Mission Street.
The contract is scheduled to start in September 1976. This
work is part of a continuing program to rehabilitate all trolley
poles in the City.
HH - 5 5 4 - Construction of #47 Trolley Coach Loop at Army Street.
At the request of the Municipal Railway, a contract was let to
restore the terminal loop of the #47 trolley coach line to Army
Street. Several years ago the route was shorted to turn back
at 25th Street in order to facilitate the construction of the
freeway interchange at Army Street and Potrero Avenue. The
Department of Public Works funded the project.
HH- 5 56 - Claribel Lateral Timber Bridge.
A contract was let for the construction of a timber bridge to
replace an existing wood plank bridge across the Oakdale
Irrigation District's lateral that has collapsed. The bridge
provides access for maintenance and inspection along our right-
of-way.
22 -
The Honorable James Rolph, Jr., Mayor, and City Engineer
M. M. 0' Shaughnessy and party at holing through of the
Foot Hill Tunnel on January 5, 1934.
j
!
HH-564 - Moccasin and Tesla Portal Buildings - Exterior Repair,
Painting and Roof Preservative
A contract was let for exterior repair and painting of fourteen
(14) cottages at Moccasin and caretaker's cottage at Tesla
Portal including painting of Chlorinator , Pumphouse and Generator
Buildings. This work also includes roof repair and painting of
the vehicle storage shed at Moccasin.
Market Street Reconstruction
Plans and specifications for relocation of trolley wires on
Market Street were prepared for inclusion in various DPW
contracts for reconstruction of Market Street.
24
View looking downstream, showing the flume intake
in the temporary cofferdam across Moccasin Creek,
above the location of the downstream dam of the
Moccasin Reservoir, July 14, 1927.
The completed Moccasin Spillway at the approximate
site of the Diversion Flume Reconstruction completed
March 18, 1976.
rOVVr.R IMPROVEMENT PROGRAM
Work during Fiscal Year 1975-70 under the UMTA -approved Federal
Grant for the Tower Improvement Program was as follows:
1 . Grant Amendments
Based on our application suhmitted in February 1975, and
updated in November 1975, Amendment No. 1, increasing the
total Project Cost from $29.6 to $38.4 million and the
Federal Grant from $19.8 to $26.8 million, was approved by
UMTA on May 20, 1976. The additional funds were approved
to cover increased costs due to inflation and revised Project
requirements for the current fiscal year. An additional
amendment to provide sufficient funds for the balance of the
Project, increasing the total Project cost to $50.5 million
and the Federal Grant to $36.5 million, is currently in the
final stages of approval by UMTA and is expected in July
1976.
2 . Electrification Project
A) Contracts
Construction commenced on Contract HH-521, Market Street
Subway Electrification, Embarcadero Station to Duboce
Portal on July 14, 1975. Bids were received on July 9,
1975 on Contract MR-622, Twin Peaks Tunnel Electrifica-
tion, Structural Repairs and Improvements. Due to
irregularities in the low bid and claim of the low bidder
of ambiguity on the application of the San Francisco
Plan, the Public Utilities Commission on July 29, 1975
voted to reject all bids and readvertise. The contract
was readvertised as Contract MR-622R and bids were
received on August 27, 1975. The contract was awarded
on September 10, 1975 to Abbett Electric Corporation,
San Francisco, California, who submitted the low bid of
$3,022,910, which includes an amount of $1,416,422 for
the Power Improvement Program portion of the contract.
The contract was certified by the City Controller on
October 10, 1975. Construction commenced on October 27,
1975.
Plans and specifications for Contract HH-531, Market
Street Subway Electrification, Duboce Junction to Eureka
Station, were approved by UMTA. Bids were received on
February 26, 1976. The contract was awarded on March 9,
1976 to Amelco Electric, San Francisco, California, who
submitted the low bid of $195,428. The contract was
certified by the City Controller on April 12, 1976.
Construction commenced on April 26, 1976.
26
\\ ) Design Services
The consultant, PBQfiD, Inc. and Gibbs P, Hill, Inc.
(PBGII) continued work on final design contract plans
and specifications.
Contract plans and specifications for the PIP and TIP
portions of Contract HII-536, Streetcar Overhead System,
West Portal Avenue, Conversion for Pantograph Operation,
and Related Street Lighting Work were completed and will
be transmitted to UMTA for approval in July. This con-
tract is scheduled for advertising in July 1976.
Plans and specifications at the 9 5% completion level to
be incorporated into purchase orders for special Trolley
Coach Streetcar Crossing Hardware were submitted by the
consultant. Review was completed and comments were
transmitted to the consultant for incorporation into
final documents. The special hardware will be purchased
by the City, due to the 6-month manufacturing lead time,
and will be furnished to several installation contractors.
Plans and specifications at the 95% completion level for
the streetcar overhead system conversion for pantograph
operation for Contracts HH-524 ("K" Line), HH-532
("N" Line), HH-533 ("J" Line), HH-534 ("L" Line), and
HH-535 ("M" Line) were submitted by the consultant, and
are being reviewed for final completion.
Plans and specifications at the 60% completion level for
streetcar overhead system conversion for pantograph
operation for Contract HH-530 ("J" eT "N" Lines, Duboce
Portal) were submitted by the consultant. Review was
completed and comments were transmitted to the consultant
for incorporation into the 951 completion level submittal
due in July 1976.
Amendment No. ] to the existing professional services
agreement, approved by the rUC on June 24, 1975, was
approved by UMTA on Septmeber 5, 1975. This amendment
was executed by the consultant, PBGH, on September 19,
1975 and certified by the City Controller on October 27,
1975.
C) Cable Purchase
Orders were placed with Cyprus Wire and Cable Co., South
San Franicsco, California for insulated copper feeder
cable to be furnished as required under the $3,151,452
purchase contract. A total of 325,000 feet of the five
types of cable, having a value of $800,000, was received
2 7
during the fiscal year and delivered to the installation
contractors for the Market Street Subway and Twin Peaks
Tunnel electrification contracts, and for the Downtown,
Civic Center and Church Substations equipment installa-
tion contract. An additional 85,000 feet of cable was
ordered but not received as yet, for other substation
and feeder undergrounding contracts.
Substation Project
A) Contracts
Plans and specifications for Contract HH-522, Civic
Center, Church and Downtown Substations, Installation of
electrical Equipment, were approved by UMTA on July 21,
1975. Bids were received on August 14, 1975. The
contract was awarded on August 28, 1975 to De Narde
Construction Company, who submitted the low bid of
$652,990. The contract was certified by the Controller
on September 17, 1975. Construction commenced on
October 6, 1975.
Plans and specifications for Contract HH-528, Laguna
Honda and Judah Substations, Construct Buildings and
Install Equipment, were completed and transmitted to
UMTA for approval on October 28, 1975. The plans and
specifications were approved by UMTA on November 11,
1975 and bids were received on December 11, 1975. The
contract was awarded on January 8, 1976 to Herrero
Brothers, Inc. who submitted the low bid of $567,913.
The contract was certified by the City Controller on
February 5, 1976. Construction commenced on March 1,
1976. Plans and specifications for Contract HH-529,
Carl Substation, Construct Building and Install Equip-
ment, were completed and transmitted to UMTA for approval
on February 25, 1976. The plans and specifications were
approved by UMT/V on March 9, 1976. Bids were received
on April 1, 1976. The contract was awarded on April 27,
1976 to S.J. Amoroso Construction Co., Inc., Foster City,
California, who submitted the low bid of $597,800.
The contract was certified by the City Controller on
June 9, 1976. Construction is scheduled to start early
in July, following issuance of a building permit by the
Department of Public Works.
Plans and specifications for Contract HH-544, Fillmore
Substation, Construct Building and Install Equipment,
were completed and transmitted to UMTA for approval on
May 26, 1976. The plans and specifications were approved
by UMTA on June 4, 1976. The contract was advertised
with bids scheduled to be received on July 15, 1976.
28
B) Design Services
The Consultant Bechtel , Inc. continued design work on
the substation buildings and equipment installation.
Final plans and specifications for Contract MM- 545,
Outer Mission Substation, Install Equipment, were com-
pleted by the consultant.
Final plans and specif icat ions for Contract HII-547, San
Jose Substation, Install Equipment, were completed by
the consultant.
Tlans and specifications at the 85*6 completion level for
Contract HH-546, Randolph Substation, Construct Building
and Install Equipment, were submitted by the consultant.
Review was completed and comments were transmitted to the
consultant for incorporation into the final documents.
Flans and specifications at the 85% completion level for
Contract IIH-548, Taraval Substation, Construct Building
and Install Equipment, were submitted by the consultant
and are being reviewed for final completion.
Flans and specifications at the 85* completion level for
Contract [IH-550, West Fortal Substation, Install Equip-
ment, were submitted by the consultant and are being
reviewed for final completion.
Amendment No. 2 to the existing Professional Services
Agreements, approved by the Public Utilities Commission
on May 27, 1975, was approved by UMTA on July 17, 1975.
This amendment was certified by the City Controller on
September 10, 1975.
Amendment" No. 3 to the Existing Professional Services
Agreement was negotiated with the consultant. The amend-
ment, which provides for additional services in the
review of drawing submittals from the substation equip-
ment manufacturer, I-T-F Imperial Corporation, was
approved by the Public Utilities Commission on November
25, 1975, and was transmitted to UMTA for approval on
November 18, 19 75.
Amendment No. 4 to the existing Professional Services
Agreement was negotiated with the consultant. The
amendment, which provides for additional design services
for Fillmore, Taraval and Bryant Substations, was
approved by the Public Utilities Commission on December 9,
1975, and was transmitted to UMTA for approval on
December 11, 1975.
29 -
Amendments No. 3 and 4 were approved by UMTA on February
4, 1976 and January 21, 1976, respectively, and were
certified by the City Controller on February 9, 1976.
The consultant continued design work on Bryant and
Richmond Substations (Contracts HH-549 and HH-551).
Building design for the relocated Taraval Substation
received Phase I and Phase II approval from the San
Francisco Art Commission. Final approval (Phase III)
was received for three substations: Fillmore, Randolph
and Taraval. This completes Art Commission approval on
all six substation buildings.
C) Substation Sites
The use of either of two alternative sites for Taraval
Substation was approved by City Planning on July 10,
1975 as conforming to the Master Plan. Appraisals on
both sites were completed. An Offer to Sell the pre-
ferred alternate site was received from the owner. A
resolution authorizing the acquisition of the property
from Northern Counties Title Company was adopted by the
PUC on September 10, 1975. A resolution approving
acquisition of the property was adopted by the Board of
Supervisors on October 6, 1975. The deed granting the
property to the City and County of San Francisco was
recorded on October 29, 1975.
A resolution authorizing the acquisition of an easement
from the Pacific Gas and Electric Company for the
Randolph Substation was adopted by the PUC on July 29,
1975. On September 2, 1975, the Board of Supervisors
adopted a resolution approving the acquisition of the
easement. The deed granting the easement to the City
and County of San Francisco was recorded on October 3,
1975.
A resolution authorizing acquisition of property from
the San Francisco Redevelopment Agency for the Fillmore
Substation site was adopted by the Public Utilities
Commission on April 27, 1976. On June 7, 1976, the Board
of Supervisors adopted a resolution approving the acqui-
sition of the property. The deed conveying the property
to the City and County of San Francisco was executed by
the San Francisco Redevelopment Agency on June 8, 1976
and was deposited in escrow on June 28, 1976. The deed
will be recorded in July 1976.
30 -
With the recording of the deed for the Fillmore Substation
site, all property acquisition for the six new substation
buildings will be completed.
D) Equipment Purchase
The substation equipment manufacturer, I-T-E Imperial
Corporation, continued production on the $5,896,000
purchase contract.
Review of shop drawings submitted by ITE continued.
Modification of Contract No. 1, covering changes to
Laguna Honda Substation equipment was processed. Modifi-
cation of Contract No. 2, covering changes to the gap
breakers and providing for local warehousing of sub-
station equipment was processed.
Deliveries of equipment commenced. Equipment for the Gap
Breaker Stations at Eureka and Forest Hill was delivered
to the Contractor, Abbett Electric, at the jobsite
(Contract MR-622R) on January 27, 1976, and for the Gap
Breaker Stations at Powell and Van Ness was delivered to
the Contractor, Amelco Electric, at the jobsite (Contract
HH-521) on February 5, 1976. Equipment for the first
stage of construction at Downtown Substation was received
for installation by the Contractor, De Narde Construction
Co., on February 19 and 20, 1976, and equipment for Church
Substation was received for installation by the Contractor,
De Narde Construction Co., on March 16, 1976 and lowered
through the street hatch into the substation (Contract
HH-522). The equipment for Civic Center Substation was
received and lowered into the station through the roof
hatch opening at the U.N. Plaza on June 8, 1976. Addi-
tional equipment is being received at the local warehouse
for later deliveries to installation contractors.
Approximately 60% of the contract equipment is now on
hand.
A Service Engineer, assigned by ITE to assist during
installation and testing of the new equipment, provided
assistance at the four Gap Breaker Stations and at
Downtown, Civic Center and Church Substations.
Work commenced on the preparation of plans and specifica-
tions for the purchase of additional substation equipment
for Stations E, F, J, and N. The recently approved
amendment to the Power Improvement Program provides for
the acquisition and rehabilitation of these substations,
now owned by the Pacific Gas and Electric Company.
31 -
4 . Control and Communication Project
The Consultant, Systems Control, Inc., had submitted the
preliminary report in June 1975. Review was completed on
the alternate systems designs presented in the preliminary
report. The choice of design was made by Hetch Hetchy. The
consultant was directed to proceed with detailed design.
The consultant delivered the Supervisory Control System
specifications, at the 30% completion level, for review. In
addition, the consultant submitted the design criteria for
the subway maintenance telephone system for approval. Review
of the submittals and design criteria was completed by Hetch
Hetchy. The consultant was notified to proceed with prepara-
tion of final plans and specifications.
The 90% completion level submittal is scheduled for August
1976.
5 . Feeder Underground ing
A) United Nations Plaza (DPW Contract 23,476)
All PIP work on this contract was completed in accordance
with the contract plans and specifications on September
25, 1975.
B) Judah Street (DPW Contract 23,506)
All PIP work on this contract was completed in accordance
with the contract plans and specifications.
C) Ocean Avenue and Phelan Avenue Rechannelization and
Track Reconstruction (DPW Contract 23,727)
Plans and specifications for the TIP and PIP portions of
DPW Contract 23,727 for Ocean and Phelan Avenues
Rechannelization, which will include relocation of
trolley poles and the overhead trolley wire system and
the undergrounding of feeder cables, along with Muni
streetcar track relocation and rerailing, were approved
by UMTA on April 7, 1976. The plans and specifications
were approved by the State (FAU) on June 4, 1976. The
contract was advertised on June 29, 1976 with bids
scheduled to be received on August 4, 1976.
D) Fillmore Street, Hayes to Pine Streets, Underground Power
Facilities (Contract HH-491)
All work on this contract was completed in accordance
with contract plans and specifications.
32 -
E ) Ocean Avenue, Junipcro Serra Boulevard to Harold Avenue
Underground Duct System (Contract HH-SOTJ"
All work on this contract was completed in accordance
with contract plans and specifications.
F) 19th Avenue, Randolph and Broad Street - Underground
Duct System (Contract 1111-519]
All work on this contract was completed in accordance
with contract plans and specifications on October 24,
1975.
G) Church Street - 22nd Street to 30th Street - Underground
Duct System (Contract HiFTDTJ
Plans and specifications for constructing manholes and
underground duct banks in Church Street between 22nd
Street and 30th Street were completed and transmitted to
UMTA for approval on November 13, 1975. The plans and
specifications were approved by UMTA on December 9, 1975
The contract was awarded on January 13, 1976 to Abbett
Electric Corporation, San Francisco, California who
submitted the low bid of $109,590. The contract was
certified by the City Controller on February 4, 1976.
Construction commenced on February 16, 1976.
H) Taraval Street and 46th Avenue - 20th Avenue to Vicente
Street - Underground Duct System (Contract HH-503)
Plans and specifications for constructing manholes and
underground duct banks in Taraval Street and 46th Avenue
between 20th Avenue and Vicente Street, were completed
and transmitted to UMTA for approval on October 28, 1975
The plans and specifications were approved by UMTA on
November 5, 1975. Bids were received on January 15,
1976. The contract was awarded on January 27, 1976 to
Peter Kiewit Sons' Company who submitted the low bid of
$246,200. The contract was certified by the City
Controller on March 9, 1976. Construction commenced on
March 29, 1976.
I ) Sutter Street - Presidio Avenue to Leavenworth
Underground Duct System (Contract HH-525)
Plans and specifications for constructing manholes and
underground duct banks in Sutter Street between Presidio
Avenue and Leavenworth were completed and transmitted to
UMTA for approval on September 4, 1975. The plans and
specifications were approved by UMTA on September 16,
1975. Bids were received on November 13, 1975. The
33
contract was awarded on November 25, 1975 to R. Flatland '
Company, San Mateo, California, who submitted the low
bid of $372,835. The contract was certified by the City
Controller on January 8, 1976. Construction commenced
on January 26, 1976.
J ) McAllister Street - Divisadero to Leavenworth
Underground Duct System (Contract HH-526)
Plans and specifications for constructing manholes and
underground duct banks in McAllister Street between
Divisadero and Leavenworth were completed and transmitted
to UMTA on December 22, 1975. The plans and specifica-
tions were approved by UMTA on January 14, 1976. Bids
were received on February 2, 1976. The contract was
awarded on March 9, 1976 to R. Flatland Company, San
Mateo, California who submitted the low bid of $248,430.
The contract was certified by the City Controller on
May 27, 1976. Construction commenced on June 1, 1976.
K) Ashbury, Fillmore, Church, 18th and Other Streets
Underground Duct System (Contract HH-527)
Plans and specifications for constructing manholes and
underground duct banks in Ashbury, Fillmore, Church,
18th and Other Streets were completed and transmitted to
UMTA for approval on March 3, 1976. The plans and
specifications were approved by UMTA on March 9, 1976.
Bids were received on April 15, 1976. The contract was
awarded on April 27, 1976 to The Lowrie Paving Company,
South San Francisco, California, who submitted the low
bid of $367,998.50. The contract was certified by the
City Controller on June 4, 1976. Construction commenced
on June 28, 1976.
L) Ocean Avenue, Persia Avenue and Mission Street - Metro
Center to Russia Street - Underground Duct System
(Contract HH-537J
Plans and specifications for constructing manholes and
underground duct banks in Ocean Avenue, Persia Avenue
and Mission Street from the new Muni Metro Center to
Russia Street were completed and transmitted to UMTA for
approval on July 25, 1975. The plans and specifications
were approved by UMTA on August 8, 1975. Bids were
received on October 2, 1975. The contract was awarded
on October 14, 1975 to Venturini Corporation, San Mateo,
California, who submitted the low bid of $127,267.
Construction commenced on December 22, 1975. All work
on this contract was completed in accordance with
contract plans and specifications on June 3, 1976.
34
M) Judah Street - 20th to 48th Avenues - Underground Duct
System (Contract HH-523J
Work remained suspended on the preparation of plans
and specifications for constructing manholes and under-
ground duct banks in Judah Street between 20th and 48th
Avenues. Feeder cables will be installed in these duct
banks under a later contract. The delay is due to DPW
determination of the extent of the Street Improvement
and Track Reconstruction work.
N) Feeder Underground - Folsom and Howard Streets
CContract~TlH-448y
0) Feeder Undergrounding - Sutter and McAllister Streets
(Contract HH^54Fj
P) Feeder Undergrounding - Irving, Carl, Duboce
Fillmore and Church Streets (Contract HH-552)
Work commenced on the preparation of plans and specifi-
cations for installation of feeder cables in duct banks
constructed under other contracts.
Q) San Jose Avenue and Broad Street - Metro Center to
Plymouth Street - Underground Duct System
"[Contract HH^ITSF)
R) Folsom and Howard Streets, Main to 11th Streets
Underground Duct System (Contract HH-559)
S) Haight Street - Stanyan to Gough Streets - Underground
Duct System (Contract HH-560)
T) Fillmore, Jackson, Presidio and Other Streets
Underground Duct System (Contract HH-561)
U) Fulton and McAllister Streets - Stanyan to Divisadero
Underground Duct System (Contract HH-562)
V) Folsom Street - 11th to 16th Streets and 11th Street
Market to Bryant - Underground Duct System
(Contract HH-563J
W) Hayes Street - Van Ness Avenue to Stanyan Street
Underground Duct System (Contract HH-567)
Work commenced on the preparation of plans and specifi-
cations for constructing manholes and underground duct
banks. Feeder cables will be installed in these duct
banks under later contracts.
35 -
X) Other Work
Preliminary engineering and plans and specifications are
proceeding for duct lines and feeder undergrounding in
accordance with the requirements of the Program.
Y) Manhole Frames and Covers (Second Contract)
Delivery of all manhole frames and covers, totalling 100
sets, was completed on September 15, 1975.
Z) Manhole Frames and Covers (Third Contract)
Contract documents for purchasing an additional 200
sets of manhole frames and covers for use on future Power
Improvement Program contracts were prepared and trans-
mitted to UMTA for approval on April 15, 1976, and were
approved by UMTA on May 4, 1976. Bids are scheduled to
be received by the City Purchaser on July 16, 1976.
Overhead Line Work
A) K-Line, Transit Power Facilities, Street Lighting and
Related Work (Contract HH-517J
Plans and specifications for trolley pole replacement,
overhead trolley wire reconstruction, feeder under-
grounding and street lighting on Junipero Serra Boulevard
from St. Francis Circle to Ocean Avenue, and for feeder
cable installation in duct banks previously constructed
under Contracts HH-498 and IIH-502 on West Portal Avenue
and on Ocean Avenue, were completed and transmitted to
UMTA for approval on December 9, 1975. The plans and
specifications were approved by UMTA on December 15, 1975,
Bids were received on January 29, 1975. The contract
was certified by the City Controller on April 17, 1976.
Construction commenced on May 24, 1976.
B) K-Line, Ocean Avenue at Route 280 Overpass, Track
Reconstruction and Power Facilities (Contract MR-620)
Plans and specifications for trolley overhead work and
underground duct lines to be included in Contract MR-620,
"K" Line, Ocean Avenue at Route 280 Overpass, Track
Reconstruction and Power Facilities, were completed and
transmitted to TIP on November 20, 1975. The plans and
specifications were completed by TIP and transmitted to
UMTA for approval on January 23, 1976. The plans and
specifications were approved by UMTA on February 18,
1976. Bids were received on March 12, 1976. The low
bid in the amount of $328,820 includes an amount of
- 36
$64,526 for the Power Improvement Program (PIP) portion
of the work. The contract was awarded to Homer J. Olsen,
Inc., Union City, California on April 9, 1976. The
contract was certified by the City Controller on June 16,
1976. Construction work commenced on June 28, 1976.
C ) Transit Preferential Street Program: Mission Street and
Fourth Street, Muni Passenger Platforms and Muni Power
FacilitiesTT)PW Contract 23,834)
Plans and specifications for the PIP portion of Depart-
ment of Public Works (DPW) Contract No. 23,834, Transit
Preferential Street Program: Mission Street, Beale to
South Van Ness Avenue; and Fourth Street, Market to
Townsend; which include the relocation of trolley coach
overhead facilities, were transmitted to UMTA for
approval on October 14, 1975. The Department of Public
Works transmitted the final contract plans and specifica-
tions were approved by UMTA on April 7, 1976 and the
State (FAU) on April 29, 1976. Advertising of the
contract is awaiting scheduling by the Department of
Public Works.
7 . Miscellaneous
A) Coordination meetings of the joint staffs of Transit
Improvement Program and the Power Improvement Program
were held.
B) Coordination meetings were held between Hetch Hetchy
staff and the consultants on the electrification,
substation and control and communication projects.
- 37
BUREAU OF LIGHT, HEAT AND POWER
STREET LIGHTING
General
The lighting of public streets within the City of San Francisco
is provided by facilities which are, on a City-wide basis, 43.5%
owned by the City; 54. 7 o owned by the Pacific Gas and Electric
Company; and a small percentage, 1.81, jointly owned. In the
underground areas, where the economic advantage of City ownership
is greatest, 81.31 of the lights are City-owned. Five years ago,
the corresponding figure was 7 4.4%.
In fiscal year 1933-34, the cost for street lighting was $1.25
per capita; last year, with approximately thirty times as much
light on the streets and public thoroughfares, the cost per
capita was approximately $1.85. ~
Maintenance and repair of City-owned installations was performed
under two contracts. One provided for group replacement of
lamps in accordance with schedules developed by the Bureau. A
second contract covered work required for repair of damaged and
defective equipment, painting and miscellaneous maintenance.
Under contract, the Pacific Gas and Electric Company furnished
street lighting service as directed, including the furnishing,
maintenance and operation of Company-owned facilities. Certain
services were provided also for City-owned facilities, including
switching and control, replacement of individual lamps and
globes, and emergency work required during other than normal
working hours.
Electric energy for all City and Company-owned streetlight opera-
tion was supplied by the Hetch Hetchy power system.
Engineering
The Bureau reviews, recommends changes, approvals or rejections
of, and correlates all street lighting installations, including
that done by the Department of Public Works, the Pacific Gas and
Electric Company, the State of California, subdividers, etc.
During the fiscal year 1975-76, 19 street lighting contracts,
involving a total of 819 new streetlights, were approved by the
Public Utilities Commission. Plans were submitted only after
careful checking to determine that illumination will exceed the
minimum requirements established by the American National
Standards Institute; and that all materials used, and manner of
installation, meet with the applicable local, state and federal
rules, regulations and statutes governing the installation of
electrical works.
- 38 -
BUREAU OF LIGHT, HEAT & POWER
REVENUES AND EXPENDITURES
FISCAL YEAR 1975-1976
Operation and Maintenance
As of June 30, 1976, a total of 37,378 City-owned and Company-
owned streetlights were in service to the public streets, parks,
viaducts, overcrossings , tunnels and underpasses. A summary of
the number and type of units in service at the end of the fiscal
year is shown in Appendix Table.
A total of $1,326,226 was expended for operation, maintenance,
and repair of the street lighting system. Of the total cost,
$12,649 was paid by the State for its share of the operation and
maintenance of street lighting at intersections on City streets,
which are part of the State Highway system.
During the fiscal year, there were 114 accidents involving damage
to City-owned street lighting property. Investigation was made,
as soon as possible, to remove hazards to the public and obstruc-
tions to traffic. Total cost of repairs to damaged City-owned
street lighting property was $73,125. Every effort was made to
secure reimbursement for damages incurred from responsible
parties. Previous experience indicates that approximately three-
fourths of the repair costs will be recovered.
Complaints
During the year, 48 complaints requiring field investigation
were received and acted upon. These complaints concerned
inadequate illumination, objectionable glare in windows, and
requests for temporary and permanent relocation of street
lighting poles.
Improvements
During the fiscal year 1975-76, a total of 868 new City-owned
streetlights were placed in service at a cost of $724,798.
Improvements were financed by State Gasoline Tax and the 1964
and 1972 Street Lighting Bond Issues as indicated in Appendix
Tables 16 and 17.
40
UTILITY SERVICES TO MUNICIPAL DEPARTMENTS
General
Electric energy supplied to municiapl departments is generated
on the Hetch Hetchy power system and delivered to various service
points by transmission and distribution facilities of Pacific
Gas and Electric Company under a wheeling contract. Natural gas
supplied to municipal departments is furnished by the Pacific
Gas and Electric Company under a service contract.
Municipal Consumption of Electricity and Gas
During the fiscal year, 486,936,786 kilowatthours of electrical
energy were consumed through 1,054 municipal accounts at an
expenditure of $6,077,738. Of the above, 147,463,469 kilowatt-
hours of energy were supplied to the San Francisco International
Airport for resale to tenants. Natural gas consumption was
17,787,179 therms through 556 accounts at a cost of $2,691,890.
There were several increases in gas rates last year which
increased the cost to municipal accounts by approximately
$805,652. The average cost per therm increased by approximately
421.
A summary of consumption and expenditures for these commodities
is shewn in Tables 12 and 13.
41
APPENDIX
TABLE 1
HETCH HETCHY WATER AND POWER*
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES (INCLUDING ENCUMBRANCES)
FISCAL YEAR 19 75-76
OE DESCRIPTION
110 Permanent Salaries
111 Overtime
112 Holiday Pay
120 Temporary Salaries
130 Wages
139 Permanent Salaries - Gardeners
200 Contractual Services
216 Maint. and Repair of Auto Equipment
231-1 Purchase of Power for Resale
231-2 Service Charge for Transm. and Dist
251 Subsistence of Employees
300 Materials and Supplies
640 Water Rights and Damage Claims
641 Hydrography
801 Accident Compensation
804 Claims
812 Fidelity Insurance
813 Automobile Insurance
814 Fire Insurance
815 Miscellaneous Insurance
853 Assessments
854 Membership Dues
855 Fee to U.S. Gov't. - Raker Act
856 Maint. of Roads - Raker Act
860 Retirement Allowances
8^2 Social Security
865 Health Service System
870 Taxes
880 Rental - Transm. Lines and Offices
900 Services of Other Departments
TOTAL OPERATION AND MAINTENANCE
400 Equipment
4 76 Library and Reference Books
500 Additions and Betterments
700 Reconstruction and Replacement
830 Bond Interest and Redemption
TOTALS
BUDGET
ACTUAL
$
779,469
$
649,653
15,750
15,400
4,070
2,662
53,180
49,102
1
,789,623
1
,427,802
58,107
53,393
79,090
97,226
12,000
6,118
4
,284,000
3
,903,720
2
,500,000
2
,436,435
10,000
3,464
140,875
157,519
12,000
- 8 -
45,800
45,713
24,750
42,438
500
163
72
82
11,130
11,130
23,064
23,064
39,498
39,498
45,000
17,077
5,312
5,744
30,000
30,000
15,000
15,000
550,401
367,277
114,902
119,989
58,916
33,410
525,396
525,312
136,400
111,900
864,121
864,121
$12
,228,426
$11,054,412
59,634
59,628
800
- 9 -
24,000
24,000
197,000
197,000
8
,840,856
8
,840,856
$21
,350,716
$20
,175^896
-UNDER, OVER
$ -129,816
-300
-1,408
-4,078
-361,821
-4,714
18,136
-5,882
-380,280
-63,565
-6,536
16,644
-12,000
-87
17,688
-337
10
- 9 -
- e -
- 9 -
-27,923
432
- 9 -
- 9 -
-183,124
5,087
-25,506
-84
-24,500
- 9 -
$ -1,174,014
-6
-800
- 9 -
- 9 -
$ -1,174,820
* Does not include Transit Power Division - Table 4 or Bureau of Light,
Heat and Power - Table 11.
TABLE 2
SUMMARY OF TAXES
FISCAL YEAR 1975-76
HETCH HETCHY PROJECT
Tax Levying Bodies
Alameda County
San Joaquin County
San Mateo County
Stanislaus County
Tuolumne County
Banta-Carbona Irrigation Dist.
Oakdale Irrigation Dist.
West Stanislaus Irrigation Dist.
Assessed Values
2,350.00
42,250.00
3,610.00
116,170.00
5,706,865.00
3,642.28
25,897.00
4,250.00
Total Amount
of Taxes
284.62
4,533.68
322.10
11,442.62
507,957.24
156.62
544.94
153.00
$ 5,905,034.28
$ 525,394.82
C H
to u)
c
Vj
1-1
4-J <D
(0 >
0)
O C
3
o o
C
o
0)
J3
>
t>0 in
<
•h .c
.c 4J
XI
u
0) 0)
43
J= <->
60
u
T)
01
<U
.n
H
d
-n
n
ci)
f-i
^
p-
•H
CO
U)
0. i-l
o c
is :=>
X)
o
1)
r-l
1-1
tr,
ct;
o
-U
t/i
C
H
o o o
o o o
m in o
H H N
n n n n cn
i-h i-i m
<-* <f r-l 1-1 <f
£ S E 2
iJ
•J!
3
(>
u
c
.
3
U-l
0)
■n
>
CD
M
CD
0
CO
.c
i-J
01
VI
4J
■u
c
OJ
•H
0)
.c
C
en
■u
P
CI)
Vj
c
D-
•H
01
0)
en
■—I
.e
n
&:
B
CO
O
O
to
0J
u
•a
to
O
4-1
c
0)
1-4
4-1
■u
0
r-l
c
m
h
o
T3
0
to
a)
0)
ai
c
<D
•i-4
4J
e
4-1
•rt
TJ
!-(
to
a
»j
'■M
0)
0)
1-1
c
•H
CD
•H
u
0)
CO
1-1
3
>
4J
CO
c
cr u
c
CJ
e
t^
w o
o
01
4J
4-1
(J
u
pi
CO
O
oj
r-4
C co
4:
c
T>
10
O U
en
o
4J
O
c
•H (U
3
u
a)
B
1-1
vi C
0
<c
w
1-1
60
u ai
c
4-1
CO
.C
•H
<u o
o
&
1-4
4J
n
> i
l-l
c
►»
•r4
0
c u
j:
3
3
01
3
o o
o
u
x:
0)
o w
C
h
01
4-1
4-1
u
o
>!
0)
a)
C
01
>u s
W3
£
4J
0)
a)
3
o
ra
en
e
II
li
li
0
3
0.
in
at
•H
CO
1-1
4J
ex o
Pi
T3
O
3
•H
£*
O
c/5
gj
c
M
0>
c
&
TABLE 4
HETCH HETCHY WATER AND POWER
TRANSIT POWER DIVISION
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES
(INCLUDING ENCUMBRANCES)
FISCAL YEAR 1975-76
OE DESCRIPTION
110-1 Permanent Salaries
130-1 Wages
200-1 Contractual Services
300-1 Materials and Supplies
801-1 Accident Compensation
860-1 Retirement Allowance
862-1 Social Security
£65-1 Health Service System
900-1 Services of Other Departments
BUDGET
75,529
1,230,128
30,000
56,000
35,250
247,147
50,723
10,159
175,258
ACTUAL
36,532
973,844
2,055
14,973
18,571
160,723
52,508
14,620
175,258
$
-UNDER, OVER
-38,997
-256,284
-27,945
-41,027
-16,679
-86,424
1,785
4,461
- 9 -
TOTAL OPERATION AND MAINT.
700 Reconstruction and
Replacement
$ 1,910,194 $1,449,084
2,595,000 2,595,000
$ -461,110
- 9 -
TOTAL
$ 4,505,194 $4,044,084 $ -461,110
TABLE 5
HETCH HETCHY WATER AND POWER
SUMMARY OF RECEIPTS AND EXPENDITURES
FISCAL YEAR 1975-76
RECEIPTS
Revenue from Sale of
Electrical Energy
Revenue from Sale of
Water and Standby
Charge, SFWD
Other Revenue
BUDGET
$ 15,883,000
6,500,000
100,000
$ 22,483,000
ACTUAL
-UNDER, OVER
$ 19,693,525 $ 3,810,525
6,500,000
187,307
- 0 -
87,307
$ 26,380,832 $ 3,897,832
EXPENDITURES
Total Expenditures
$ 25,855,910
$ 24,219,980 $-1,635,930
f^ r-l
CO
O r-l &-S
CO CJv 00
St St
CO 6^
CO o
m cm
• • m
»m
•-> <t
vo o>
m
CM CM
r-» cm
o
m cm
vO
Ct> O
vo in
r«. st
r^ ov \0
CM d CM
en cm
rn
st
tO
UP
DO
OJ
■— (
CM
rs
o
00
vO
o
^D
CM
<n
r-j
ON 00
r» e-5
o\ in
m ^o
r-~ m
«-< o
st cm r-
st ■-<
cm en
oo m
m m
m vo
oo m
in oo
IS
as
RJ
•
u
e
H
z
M
fe
H
o
z
erf
-
U-t
CJ
o
o
<
M
H
u
<
e
fx.
H
OJ
tn
H
>,
o
o
Ph
.£
u
z
M
o
TJ
<u
S3
CJ
u
>^a.
erf
z
u
01
>J
C/l
c
4J
^
a.
erf
00
0)
TO
a.
S
<
w
►J
<q
H
w
<
00
S
CO
CT>
ON
m
o
r~>
kO
<J
N
CM
r-^
St
r-i
;•
f— (
u
■ J
1-4
a.
(J
to
a
D
o
n
H.
u
<
erf
>>
Vj
o
x:
o
H
o
XI
c
r^
4J
^
TO
0)
o
ai
erf
K
.— <
^-i
H
.J
M
O
x:
>
CJ
<1J
a>
Pi
4J
J£
^
w
01
TO
CO
C/1
W
J
kJ
^.
>.
TO
TO
•a
TD
>j
(J
QJ
01
ex
CL
Nameplate Rati
nfi
Capability
Annual Plant
(Kilowatts)
(Kilowatts)
Factor - "U
90,000
104,000
50.6
135,000
150,000
50.0
6 7^500
85,000
70.2
taiu.i; 7
retch ui:tchy power system
electric energy generated, purchased, and distributed
fiscal year 1975-76
PLANT DATA
Moccasin Powerhouse
Dion R. Holm Powerhouse
Robert C. Kirkwood Powerhouse
Total 292,500
ENERGY GENERATED AND PURCHASED (KILOWATT-HOURS)
Cross Generation
Moccasin Powerhouse
Dion R. Holm Powerhouse
Robert C. Kirkwood Powerhouse
Station Service
tloccasin Powerhouse
Dion R. Holm Powerhouse
Robert C. Kirkwood Powerhouse
Net Generation
Supplementary Energy
"Hank" Withdrawal*
Purchase (PGandE)
Total
ENERGY DISTRIBUTED (KILOWATT-HOURS)
Sales
Municipal Accounts
Modesto Irrigation District
Turlock Irrigation District
Kaiser Cement and Gypsum Corp.
Kaiser Aluminum and Chemical Corp.
Morris Industries, Inc.
Lockheed Missiles and Space Co. Inc.
General Motors Corporation
J B M Corporation
Liquid Air, Inc.
Miscellaneous Customers
Hon -Re venue
Froject Use
"Bank" Deposit*
losses
Hetch Hetchy System
PGandE System (Municipal Accounts)
Total
339,000
460,560,000
657,219,000
522,892,000
841,700
1,238,750
772,150
36,545,220
247,922,311
490,203
865,104
248,817
78,351
11,280
7,167
80,177
28,837
25,761
12,547
?20
,242
,000
,883
,659
,000
,744
,458
,778
,600
,200
fc85,L.
3,277,963
2,773,513
33,816,359
33,248,681
1,640,671,000
2,852,600
1,637,818,400
284,467,531
1,922,285,931
1,849,169,415
6,051,476
67,065,040
1,922,285,931
n accordance with letter-agreement between City and PGandE dated 6/24/75
TABLE 8
1IETCII HETCHY POWER SYSTEM
COMPARATIVE ELECTRIC ENERGY SALES TO CUSTOMERS
FISCAL YEARS 1974-75 AND 1975-76
(Nearest 100,000 Kilowatthours)
CUSTOMER
1974-75
1975-76
Municipal Accounts
International Airport
Municipal Railway
Public Works
Street Lighting
Unified School District
Water Department
Other City Departments
Modesto Irrigation District
Turlock Irrigation District
Kaiser Cement and Gypsum Corp.
Kaiser Aluminum and Chemical Corp.
Norris Industries, Inc.
Lockheed Missiles & Space Co., Inc.
General Motors Corporation
IBM Corporation
Liquid Air, Inc.
Miscellaneous Customers
189,900,000
64,800,000
26,600,000
45,800,000
38,300,000
44,000,000
71,900,000
734,900,000
219,100,000
143,700,000
28,100,000
21,700,000
209,300,000
76,000,000
82,100,000
28,100,000
800,000
189,200,000
56,900,000
26,800,000
46,400,000
39,700,000
48,400,000
82,800,000
865,100,000
248,800,000
78,400,000
11,300,000
7,200,000
80,200,000
28,800,000
25,800,000
12,500,000
900,000
TOTAL
2,025,100,000
1,849,200,000
TABLE 9
HETCH HETCHY POWER SYSTEM
COMPARATIVE GROSS REVENUE RECEIVED FROM SALE OF ELECTRIC ENERGY
FISCAL YEARS 1974-75 AND 1975-76
(Nearest $1,000)
CUSTOMER 1974-75 1975-76
Municipal Accounts
International Airport $ 1,588,000 $ 2,542,000
Municipal Railway 64-9,000 649,000
Public Works 333,000 330,000
Street Lighting 485,000 517,000
Unified School District 567,000 553,000
Water Department 395,000 476,000
Other City Departments 912,000 1,011,000
Modesto Irrigation District 4,289,000 7,457,000
Turlock Irrigation District 1,483,000 2,283,000
Kaiser Cement and Gypsum Corp. 1,927,000 1,318,000
Kaiser Aluminum and Chemical Corp. 418,000 220,000
Norris Industries, Inc. 227,000 164,000
Lockheed Missiles & Space Co., Inc. 2,772,000 1,454,000
General Motors Corporation 1,054,000 572,000
IBM Corporation 1,122,000 478,000
Liquid Air, Inc. 373,000 190,000
Miscellaneous Customers 9,000 10,000
TOTAL $ 18,603,000 $ 20,224,000
o
<^
o
..-!
i.-
m
CM
oo
CO
O
ON
r-4
"
rs
•T,
. 1
o\
m
CM
1-1
m
■-J
<f
uD
u ,
o
O
O
I >
IC
- i
o
un
iC
CM
is
r-
r.i
-t
,-i.
r-l
CI
1 S
0>
U-i
n
tn
rs
«rt
in
CO
iO
a
CM
CM
en
i.-l
CM
st-
-1
un
I :<
-P
i^
m
-t
CM
CM O C"> ON O
st O oo m o
CM O CO NO O
1 vt
rs i-i
O
rs
■> O
•—i in
to
\D
-1 f-I
ao en
CM
i— 1
O in oo co
<t 00 cm
in O O
moo
00 o o
m
O
o
00
rs
in
is
00
CM
OO
en
a.
CM
oo
f— l
vO
i— i
NO
H vt OM»1 CO H
CO CO i-t st CM CM
st rs es i-i
00 00 O O r-l
in rs o O in
<t rs vo cm oo
O O rs in cm
O O oo cm o
O O en <t O
i i i i no\o no
is
ON
st
in
st
r-l
m
\0
r-l
CM
<o
is
in
r»
is
i-4
i— i
CM
O
O
O
O
CJN
( i
•o
CM
«d
00
rs
33
VQ
CO
st
DO
is
st
CO
lO
in
r-l
in
CO
vP
_i
co
30
rs
CM
r>.
m
r-l
en
• 1
st
<»
iC
st
en
st
rs o o O O
CT« o o o o
no o o o o
oo ai co cm n o i i
•.+ ro is N ri in I I
i i in
i i m
CM rs CM vO <— 1 CM
co oo O m m cm
-J is <n — i
CJN
CO
m
<t
in
<t
0>
en
st
1— 1
<r
r-H
r-l
OS
en
o
r-4
IS
r-l
o
CM
o
O
O
( )
is
o>
CM
un
00
nP
j;
r^"
oo
<t
st
00
?-*
i — 1
rsj
en
r-l
<t
in
! )
in
no
nD
on o o o o o
o o o o o no
CJN O O O nO rs
cr> vo <j- oo r-i m
in H CO O N N
cm co <t cn m en
00 00 r-l in r-l CM
O m cm <)■ en cm
in CO <f rl
I I I I I
o
o
O
o
en
m
r-i
st
a>
oo
m
r-H
rs
m
on
m
-h
en
CO
st
en
O
r-l
m
CO
iO
o
O
o
o
O
O
OJ
st
•— 1
o
O
st
1^
m
is
o
CJ
00
r-4
CM
o
en
ON
r^i
in
CO
'O
•O
st
nO
en
<t
st
o
st
■X)
en
en
rs
X)
00
st
o
— 1
in
m
st
in
rs
O
st
rs.
NO
ON
CXl
o
en
nP
en
st
r-4
CJN O
00 o
is O CM CM O r
in O oo O O
in
o
ON
rs
vO
-t
NO
NO
o
st
CM
ON
^>
C J
is
i-i
rs
NO
— i
ON
NO
en
CO
-d- rs en -"-I
o o m o o no o
o o oo o co m no
o o <r o <r o m
s r-l NO NO
a.
en
CXI
o
cn
_i
•g rs in en
st
m
NO
co
in
en
-i en <t is
in
a
NO
CM
NO
>o
C0COHNON<t<fsfN00
incMCMineneMejNOeno
St IS m r-l r-l r-l
I I I <t
DJ
Ql
en
:?
3
0
n
Ph
t.
u
X)
CD
o
:?
0
o
3
Cu
.M
Ifl^J
m
LJ
CO
3
T)
1J
en
c
o
H-)
U
m
u
•n
;'j
.a
H
c
D-.
3
O
4-1
s^
CO
H
a
n
p. U
1-4
u
•r-4
B
T3
o
e
o
CO
c
c
P>S
CO
0)
r-l
■U
4-1
o
o
O >£
CO
•rJ
X
Ph
cn
CO
C
•r-4
•r-l
OJ
C
u
OJ
3
D
■U
4-1
13 §
•r-l
O
c
r-4
c
O
U
j<
O
CO
C3
i-i
.is
OJ
•r-4
CO
o
C
U
00
bO
4-1 C
4->
o
CO
cn
1-1
•rJ
1-4
CO
4-J
1-J
u
•r-l
•r-l
C -H
CO
c
in
0
cn
o
4_l
3
•1-1
<
<
u
u
cu g
3
M
4-1
r-l
•r-4
4-J
CO
O
OJ
CO
H
u
u
E 3
-a
CO
u
4-1
S
o
J-4
S-1
OJ
CO
o
O
t— <
M
r-4
CD r-l
a
•r-l
3
•r-l
?J
o
■r-4
d
r3
a.
H
(0
O <C
r-4
CO
C
X)
13
X)
rX
<
eej
<u
01
a.
o
r^
CU
u
O
04
t-4
1-1
r-l
3
4U
Q
■r-l
4-J
CJ
>J rJ
CO
f—l
o
n
>N
0)
eo
0
T3
i—l
C
o
C)
w
o
0) QJ
■r-l
3
14-1
04
0)
X.
!-4
U
•r-l
0J
OJ
01
^s
m
■U
0)
CO CO
u
o
•r-l
r-4
^
0J
3
CJ
>
■1—1
c
01
c
•o
VJ
•r-l t4
rJ
n
M
r-l
o
c
~7-\
ct<
CO
CJ
o
eo
10
r— 1
3
o
5
ea ccj
O
OJ
CO
■r-l
CO
K3
OJ
03
•r4
■1-1
or.
u
M
OJ
Ifl
^J
?:
H
^ V!
^
:x;
U
•X
>
rJ
rj
M
r-T
>*.
1
p-t
-
cn
in
c
o
cn
o
TABLE 11
BUREAU OF LIGHT, HEAT AND POWER
COMPARISON OF BUDGETED AND ACTUAL EXPENS1TURES AND RECEIPTS
(INCLUDING ENVUMBRANCES)
FISCAL YEAR 1975-76
OK
DESCRIPTION
BUDGET
ACTUAL
-UNDER
+OVER
110
111
112
200
231
231-1
231-2
231-3
231-4
300
813
860
862
865
954
EXPENDITURES
Permanent Salaries
Overtime
Holiday Pay
Contractual Services
Lighting and Heating of Public
Buildings - General
Lighting and Heating of Public
Buildings - Special Fund
Lighting of Public Streets -
Pacific Gas and Electric Co.
Lighting of Public Streets -
He tcli Hetchy
Lighting of Public Streets -
Calif. Division of Highways
Materials and Supplies
Auto Insurance
Retirement Allowance
Social Security
Health Service System
EDP - PUC Data Processing
$ 175,980
550
400
1,250
2,113,223
6,086,322
577,000
493,000
1,200
460
257
28,732
8,190
5,793
1,633
$ 158,116
261
261
1,259
2,076,281
6,140,693
581,186
504,549
1,200
490
222
25,761
5,792
3,884
1,633
$ -17,864
-289
-139
+9
-36,942
+54,371
+4,186
+11,549
-9-
+30
-35
-2,971
-2,398
-1,909
-9-
T0TAL
RECEIPTS
Interfund Receipts*
Ad Valorem Taxes
TOTAL
$9,493,990 $9,501,588 $ +7,59?
$7,641,616
1,852,374
$9,493,990
$7,928,551
1,573,037
$ +286,935
-279,337
$9,501,588 $ -7,598
WORK ORDER APPROPRIATIONS FROM ROAD FUND
DESCRIPTION
TOTAL FUNDS EXPENDITURE
-UNDER
+OVER
Maintenance and Repair of
Street Lighting Installation $ 205,000 $ 205,007 $
+7
* Transfers from other Departments.
TABLE 12
BIIHKA.il OF LlOHf," ~HKAT AND POWER
EXPENDITURE FOR ELECTRICITY FOR MUNICIPAL PURPOSES
FISCAL YEAR 197$ -
1976
NO. OF
CONSUMPTION
DEPARTMENT
ACCOUNTS
KILOWATT-HOUR
EXPENDITURES
ktt Museum
1
1,095,360
12,696
Auditorium and Brooks Hall
1
U, 539, 200
5U,U15
Child Care Centers
12
239, 69h
h,908
City Demonstration Agency (a)
1
77,680
1,202
City Planning
1
8l,U60
l,38li
Pe Young Museum
1
3,206,hOO
33,6hl
Di saster Corn.
1
78
l,2hli
Electricity
5
1146,070
7,106
Farmer's Market
l
19,696
U21
Fire
59
3,036,107
53,699
Hassler Health Home
1
201,000
3,000
Health
37
26,7)j2,105
257,322
Hetch Hetbhy
6
lhh,12U
2,926
Hidden Valley Ranch
1
938,880
11,139
International Airport (b)
18
189,260,331
2,5h2,05h
Junior College District
26
7,69h,5l8
88,100
Juvenile Hall
3
l,ltlU,li63
15,601
Lepion of Honor
1
55o,8oo
7,019
Library
31
2,727,UU3
U0,796
Log Cabin Ranch
13
358,219
7,111
Municipal Railway
73
56,369,769
6h8,92li
Parking Authority
18
193,116
U,03?
Police
15
871,030
lb, 877
Public Buildings
11
1U, 829, 365
lh9,091
Public Works
106
26,h68,126
32U,721
Purchasing
5
1*31,068
6,9h2
Heal Estate
h
253,960
h,033
Recreation and Park
202
10,305,3h8
163, h73
Recreation and Park - Candlestick Park
3
1,993,676
53,160
Recreation and Park - Yatch Harbor
32
l,31h,h76
2U,276
Sheriff
3
1,636,280
16,706
Social Services
5
815, 2h8
10,92h
Street Lighting Operations (.003)
1
h6,383,311
50h,5la?
Unified School District
222
31,985,522
h6h,706
v,-ir Memorial
1
1,377,81x0
17,200
Vnter
128
ii8,38h,523
h76,269
TOTAL MUNICIPAL DEPARTMENTS
1,050
U86,936,786
6,029,667
Academy of Sciences
2
2,951,060
30,171
State of California: Stredt Lifrhtine
1
(c)
12,6h9
Traffic Devices
1
315,396
5,2h8
r-RAND TOTAL FROM HETCH HETCHY
i,o5U
U90,203,2t2
6,077,738
Motes: (a) New Account, previously charged in Real Estate Department
(b) Including Ib7,!i63,h69 KYffl resold at commercial rates for $2,197,598
to Airport tenants
(c) Included under Street Lighting Operations.
TABLE 13
PURFAU OF LIGHT, HEAT AND POWER
EXPENDITURE FOR GAS ^OR MUNICIPAL PURPOSES
FISCAL YEAR 197$ - 1976
NATURAL GAS
DEPARTMENT
Auditorium and Rrooks Hall
'"hi Id Care Centers
City Demonstration Agency (a)
City Planning
be Young Museum
Electricity
'•"armer's Market
Fl re
Hassler Health Home
Health
Hetch Hetchy
International Airport
Junior College District
Juvenile Hall
Legion of Honor
I ibrary
Municipal Railway
Police
Public Buildings
Public Works
J'urehasing
Real Estate
Recreation and Park
Recreation and Park - Candlestick Park
i'"gistrar of Voters
Sheriff
'•ingle Men's Rehabilition Center
Social Services
"nified School District
'Xnr Memorial
Water
TOTAL MUNICIPAL DEPARTMENTS
NO. OF
ACCOUNTS
2
11
1
1
1
2
1
5b
3
31
2
5
17
h
1
28
13
11
6
15
3
2
106
1
1
3
1
b
213
3
10
556
CONSUMPTION
THERMS
EXPENDITURES
661
lib
30,763
b,702
li,58li
727
5,265
806
282,182
U2,911
h8,090
7,275
b86
81
582,633
87,56b
32,998
h,965
5,bll,853
79b, 270
1.9U7
328
1,500,388
217, b20
899,10ii
135,658
bbb,b56
66,9bl
56,329
8,5b5
113, b8o
17,b32
261,921
37,718
b5,807
7,017
1,175,537
169,329
26b,32U
bb,62b
52,565
7,827
8,Ob8
1,192
1,300,528
196,975
109, 6U3
I6,b85
5,837
898
b73,7b5
68,002
37,233
5,571
55,171
8,361
MU3,213
677,28b
2bb,2h0
37,171
155,b72
23,697
17,787,179
2,691,890
"ote: (a) N°w Account, previously charged in Real Estate Department,
TAPLE lb
BUREAU OP LIGHT, HEAT AND POWER
street lights i n_ service
JWWF. 30, 1976
517! '• TYPE OP LAMP
Hich Voltage Scries Circuit
1,000-Lumen Incandescent
2,500 " »
h,PO0
tl
II
6,000
II
II
1^,000
II
II
IjOO-Watt
Mercury Vapor
175
II
n
250
II
11
COMPANY
JOINTLY-
OWNED
OWNED
UNDERGROUND
CONNECTION
22
245
2b
997
127
577
UU1
bb3
2b
6
b3
CITY-
OWNED
73
l,ll|2
3,03b
5b7
236
10
79
TOTAL
. 22
342
2,266
1,05?
l,01)i
205
10
81
\nv> Voltage Multiple Circuit
1,000-Lumen Incandescent
?,500 " "
,'i,000 " "
A,oqo " "
]( i,000 " "
5,500 " Fluorescent
23,000 »' »'
100-Watt Mercury Vapor
175 " "
250 " "
bOO " "
700 " "
1,000 " "
?50-V<'att Sodium Vaoor
liOO " "
10
177
38
10
38
bb
37
30b
70
58
10b
85
lb
38
b
112
3,521
1,338
b,60b
368
101
10
658
70
72
283
128
2b
38
b2
112
3,565
1,375
b,908
368
101
10
658
Hirh Voltage Series Circuit
2,500-Lumen Incandescent
!i,000 " "
Lov.' Voltage Multiple Circuit
2,500-I.umon Incandescent
Ji,000 " "
6,000 » "
175-Watt Mercury Vapor
250 " "
bOO " "
TOTAL, JUNE 30, 1976
TOTAL, JUNE 30, 1975
NET CHANGE DURING THE YEAR
OVERHEAD CONNECTION
1
28
2
52
8
Hi, 705
1,907
798
20,429
54.7%
20,599
-170
b2
7
2
692
1.85?
16,257
b3.52
700
15,762
-8
+b95
1
70
2
59
8
lb, 707
1,907
798
37,378
10C$
37,061
+317
TABLE 15
FURF.AU OF LIGHT, H^AT AMP PCWER
FXP> FUTURES FOR OPERATION AMD MAINTENANCE OF STREET LIGHTING
FISCAL YEAR 1975 - 76
CONTRACTUAL SERVICE
P. G. fr E. Company
Connany-ownod facilities (a) 82h,3hO
Jointly-own«d facilities (a) 3b, 623
City-owned facilities (b) 126,819
Lor^s deduction for energy component
Emergency service to City-owned facilities
I>ase-Lite Corporation
Group lamp replacement - City-owned facilities
Lease-Lite Corporation
Maintenance and repair - City-owned facilities
Routine maintenance
Repair of damage caused by accidents (c)
Repair of damage caused by equipment failure
Repair of damage caused by vandals
MATERIAL AMD S I U'PLIES (FURNISHED BY CITY)
Damage caused by accidents (c)
Damage caused by equipment failure
Damage caused by vandals
EIKCTRIC ENERGY (HETCH HETCHY)
Ii6,383,311 KWH at $0.02055/KWH less 45.5% discount
TOTAL EXPENDITURE
If'S AMOUNT PAID TO HETCH HETCHY FROM:
Gas Tax Funds for State Highway Routes
Recreation and Park Department for off-street lighting
TOTAL NET EXPENDITURE
AVERAGE OFERATI NO COST
Eased on number of lights in service June 30, 1976, average total
cost of operation, maintenance and repair per light per year:
MOTES: (a) Includes maintenance, repaor, fixed charges and
electric energy for Company-owned facilities.
(b) Includes replacement of individual lamp and broken
glassware, service and switching charges, and electric
energy.
(c) When resoonsible party is known, claim is filed for
recovery of cost.
985,582
hob, 395
581,187
6,600
57,033
h7,308
b2,6o5
hi, 810
2,679
13h,h02
30,520
10,811.
1,159
h2,h93
5l9,h8l
l,3hl,196
12,6h9
2,281
lh,930
1,326,266
35.39
TABLE 16
PHKK-AU OF LIGHT, HF.AT AND POWER
NEW CITY-OWNED STREET LIGHTING INSTALLATIONS
COMPLETED DURING EISCAL YEAR 1975-76
Locations
Financed by Pond Issues:
Castle Manor Area
Laurel Heights Area * California St,
Market St. Reconstruction Cont. 1
Market St. Reconstruction Cont.. 2
fiarket St. Reconstruction Cont. 2B
Market St. Reconstruction Cont. h
Number of
Type
of
Value
Lights
Light
s*
Value
17
MV
$ hO, 690
llU
MV
113, 2h5
111
SV
82,907
165
sv
109, 7"1
12
sv
9,125
30
sv
21,180
Total
liUi
$ 376,928
Financed by State Gasoline Tax:
Buchanan St .-Grove to Hayes Stj>.
Kvans St. - Third to Jennings Sts.
P'lirfax Ave. - Newhall to Mendel 1 Sts.
Oalvez Ave., Newhall & Mendell Sts.
North Water Front Area
forth Water Front Various Location
Park Merced Area
Turk St. - Divisadero St. to Masonic Ave.
2
MV
$
6,160
h3
MV
6h,P70
Hi
MV
37, h85
16
MV
30,510
21
MV
39,235
2
MV
5,990
306
MV
120, h 65
J?0
MV
h3,055
Total
h2l,
$ 3U7,870
Grand Total
868
$
Z2LI21
-»■ TW — Mercury Vapor
SV - Sodium Vapor (High Pressure)
in O ci omju •< rMinifi(Moo-}a)NioOrHuinin>fainoo
W-jH-JvDOOiOMNnNvCNNN^OCIN-JHM'lOv
cMrH<ri^rHcricJOcocr\vocor^r^-<rr^rHoOrHrHcoo
-jovocomooooino-tOMnaiooi'iN^ininONN
<t H N i-l r-HrHrHcOrHrOi-Ho\rOinO*r>Oco-<Tin<T
m
')
a
gi
*
s
Ul
U
rH
(J
i-l
U
u
3
u
0
DO
■H
S3
v.
ovno n oo n m tn
n •* vo o n oo * w
n m no i m o oo cr>
I I I I i I I i
CM CM
CM O
r-l co
tn
H
7--.
w
fc!
o
Pd
Pi
M
Pi
(T
ItJ
2S
H
o
H
fa
sa
w
§
i-i
J
<3
t <
H
w
a
EC
H
ai
H
O
PC
w
o
H
§
-1
u
fa
r~
o
H
n
p
-J
<
w
fa
3
O
P
PQ
H
to
o
u
3
c_>
1-1
oS
o
H
c/1
M
«
r^
01
TO
O -* 00 i-l
i-i
'-:
U
in r- r^ oo
«
.CJ
a.
\£> cm m <-\
u
W)
CD
OQ
•H
n
CM CM vD ON
u
q
01
•H
BO
(l)
4-1
T1
M
.C
c
u
M
CJ
t/i
•H
w
-1
(U
c
rl
!/)
iH
0)
O
a
TO
C3
H
0
3
u
0
01
r-l
a)
TO
X
>
TO
H
<C
- I I I I I I I
<fin«)<JvDmrl'<fvOiOO'0|0
ocr><room<Tirnr^cor-«omr-~
-KN-j(NHrieONCiMno\
I « I I I I I
I I I I I I I I I I I I I
<X> CM i-H CM O CM rH
OiH -J N O •* H
00 CO CT\ r^ O ST o
CM 00 rH v£> rH O O
CM 00 CO rH vD m H
in rH co vo cm m oo
LO
CO
rH
rj
rH
a-.
ro
vO
oi
r-
r-l
ro
inr-tr~-or-icMr^vD<Tcooooov£ico<-cr>ONinr-isT<rsTooo
rH00iHCMvT<TvOCMr^rHCMOsTr-^\O<|-CMC0C0C0rH\0i-lr-~
HHOOvOvDOirirlOHtnHCOiOHmNiOOinvOMnoO
r-^cMOoO\o-»r-iocMO<Tor^<rr-iinvTO\Ot-ii-ivor^r^
rHcMcosrcMvor-~oooooo<j-cr>r~.i-ir~~r^incrvsTinvocr<sf
VO rl H CM CO <TrHr-lCOCO<rm<TCMCMCO
m rH r-. <t oo x-i
oo cm m m «* cm
r-. rH H rH
I I I I I I
I I I I I I I I I I
<-invar^oocriOrHcMcosTmvCir-»ooc»Of-icMco<Tin>jD
ininmininin\Ovo\oiovovovo\ovDvoi — r^r^r^r^i — r--
I I I I I I I I I I I I I I I I I I I i i I i
coco<Tin^or--ooo,iOrHcMco-d-invor^ooCT>Or- 1 n n <f m
minininmininm,>ovDv£>,-0'iDvovovo\D,>oi~-r~r^-r^r~-r^
o> <j\ g\ <y\ <y\ o\ o\ o\ ex* <j\ o> cr* o\ oS cj\ cr» o\ o** cr» cr» d cr* cx» cr*
1
y
CM
-i:
t'l
cr>
hO
rH
r:
1 vO
•H
W
sr r-~
OJ
4-i
r-~ l
C
U
TI
<T> m
3
3
2
rH r^
^
Jn
(TJ
u e
rl C
01
O -H
•H
-i!
•H rl
4J
fi
M 3
•H
CM
rt
O.TJ
rH
<f
•H
CT>
d
T> 13
O
rH
0
CD OJ
CO
|
•H
> >
UH
in
4-1
o o
CO
TO
6 0
•a
CTn
<1J
CD 01
CD
rH
n
rl rl
g
^^
u
0)
00 CO
O
<
cr.
C C
1
o o
>.
PM
•H -H
4-1
>^
4J 4->
•H
Xf
TO
rl U
CJ
C
15
O O
<D
rH
a. a.
14H
•H
<; oj
01
cd
a)
p.
Tl
•H
TO
CJ
rH
•H
u
C
c
3
M
;:
a:
u
0
u
M
a
q
id
•rl
<u
■t-i
M
:■■
o
3
Q
- t
CU
d
3
01
i
H
d
in
DO
0
•r(
>
Q
fe
r-l
4J
d
CJ
u
Bl
SJ
•rl
W
u
nn
4J
T-I
T-I
C
M
n
0
d,
o
c_>
ptj
i
o
111
to
H
vo
1
u
r-
i
1
H
r—
r.^
Z
CT>
1 1
O
r-l
H
U
0
:s
^
o
w
><
M
t«
&J
H
u
U
f-J
H
!=>
<
CU
Di
o
g
H
c/>
co
M
st
2
Pl,
u
O
H
o
UJ
X
Q
CJ
!0
CX
C
H
0
01
•H
-C
4-1
p4
O
1
rH
M
0)
4-1
»)
•1)
e
c
co o
XI
U -H
0)
O CO
CU
CM CM
CO Cfl
O 3
Pi O"
-a
rH
0J
CO
•u
c2
^
u
3
-a
60
w
r-l
c
C
0)
•U
n)
•H
>%
0)
w
C
CO
QJ
c
u
•H
ffi
•H
o
o
CO
4-1
u
•u
U
o
•H
CO
H
4J
rH
a*
•r-l
>. -H
>.
a)
O
CO
U)
CO
C
cd
is
in
&
•H
Cu
rH
•H
CD
CM
r-H
Q
4J
(-1
•H
01
a)
D.
r^
CO
4-1
;>
CO
60
CU
o
u
QJ
cm
a)
U
)-i
a
cfl
4-1
'O
n
w
pa
CO
c
3
c
-o
C
cu
O
■H
C
•H
U
r-l
W
cj
CO
o
00
rt
4-i
s
M
o
V-i
C3
I-l
0)
a
•r-l
3
rH
x>
o
QJ
O
•H
c
^
t3
S
U.
r3
4-1
B
xi C
CO
3
c x:
CD
o
M
cfl 60
3
PU
O
3
C
4-1
en co
cO
0)
QJ
CU
>^
m x:
XI
r-l
>
0)
rH
cfl
CU CO
C
M
<D
<t;
M
•H
S
X) -
C-J
0)
3
4-1
S
rH
C o
CXI
CO
C
x;
CO
rH
•H
B
QJ
B
4-1
s
«
•H
rH «
o
CU
O
>
0)
VD
QJ
cu
CU
o-
P.
>s CO
4-1
4-1
M
<
4-1
<r
4-1
4-1
CJ
CO
CJ CU
CO
a>
CO
C
CO
cO
ro
4J
x:
>>
CUTJ
>»
XI
QJ
>%
H-l
CM
4J
00 cfl
4-1
CO
•I-l
rH
CO
C
O
CO
r-l
C
C O
o
c
O
cfl
•H
3
4-1
•H
•H
en
4-1
3
r-l
4-1
>
4-1
CO
CO
cd
4-1 CU
O
^
CO
CJ
CJ
cu
O
CM
CO x)
a
3
re
3
4-1
O
3
OS
CM
M -H
4-1
a
Q
CU
4-1
a
X)
CU rH
01
CU
o
cu
cu
C
Pu CO
01
X)
3
4-1
13
u
QJ
TJ
XI
rH
cfl
o
r-l
c
c
a
4-1
3
c
cfl
•H
u
4-1
3
a)
-d
3
CO
C
3
o
s
4-1
XI o
CO
O
>
M
o
QJ
o
Pi
CO
S1"
u
<
CO
M
rH
>
r-l
o
CO
.c
00
>
oo
cd
<
00
&
4J
rH
60
o
M
§
0)
>-i
>
u
J3
co C
V4
<u
rH
cu
cO
-C
<u
M
rH
X)
CU -H
3
X>
a)
3
XI
u
4J
XI
CU
S
4J pu
rG
C
u
O
C
cd
o
c
6
VO
CO -H
CJ
t3
O
ffl
ti
H
CJ
&
rH
co
O CM
' '•
i:
■. i
oi
■n
M
;-'
0
3
i i
rH
.11
cd
-1
.11
U
rH
V.
HI
m
0
■H
>
1 1
u,
r-l
u
-i)
'J
c
id
h
c
a
o
•H
O
O
4-1
U
c
u
M
3
00
M
s
co
4J
-H
00
01
M
CO
X>
e
cd
O
C
■H
l-l
4-1
o
p
4-1
o
O
o
■H
c
Cd
Ph
1-1
rH 01
h
cd
d
W 4-1
4-1
u
)-i
PM
3 O
s
•1-1
01
O 3
o
s .
4J
CO T3
c_>
■u
o
03
cd O
M O
CD
c
•
0) V4
o O
>
M
S
CO p-i
on
c
•H
4J
c
•H
en
cd
(U
P-i
tn
3
M
O
CJ
XI
O
CD
4-1
M
0)
cd
W
C
>
s
•H
oi
rH
rJ 00
Cu
0)
0) c
a.
> -H
a)
•H
•H O.
en
P-. 00
Pi -H
3
c
PM
O
3 -H
C
X!
•H 3
•H TJ
^
3 -H
3 3
a)
a* hJ
cr cd
s
cd
cd
o
o u
o u
P-I
<-> -H
*-) "H
cd
cd
s
3 a.
3 a,
rH
rd CD
cd oj
O
co pi
CO CEi
S
rC 3
o
cd
0)
o
•H
4-1
01
3
4J
u
o
M
o
g
cd
o
3
4-1
4-1
TJ
o
c^
o
CO
•ca
cd
4-1
•H
4-1
CD
3
o
CO
U-l
CD
3
o
3
u
•H
CJ
3
u
O
m
CO
U
o
o
14-1
CD
CD
U
4-1
XI
o
O
>
•3
oo
-a
4J
CJ
rH
<
Cd
i-i
§
CJ
CD
•3
3
co
CD
3
rH
3
O
o
0
•H
X)
O
W
o
cd
•H
•H
CD
>
3
x:
4J
4J
-a
4J
•H
3
pu TJ
>»
x:
01
4-1
•H
CO
Q
H
3
cd
3
CJ
rH
3
CO
>.
O
3
&
O
U
rH
CD
01
4-1
CO
4-1
tj
O
xi
•H
3
3
S
u
CD
4-1
01
s
M
3
4-1
x:
4-1
a.
CU
0)
4-1
a>
CD
00
CO
cd
o
CO
■H
u
CJ
CD
>-4
pi
1-1
4->
3
3
r>
4J
3
r4
4-1
OJ
4J
CO
M
a*
4-1
GO
Q
4J
CO
T3
CD
V4
w
<D
CO
<d
3
a)
o
0)
*
CD
x:
T3
x:
3
S3
u
u
4-1
3
rH
M
4J
3
r-l
4-1
3
3
4-1
o>
3
O
cd
4-1
u
3
0)
U
o
ttl
CO
t>
CD
vH
CJ
CO
o
O
4-1
0
•H
>
CO
cd
U
4-1
•H
■3-
r4
CO
t«
tn
<!
4-1
4->
u
CO
r-l
U
c
oo
•r-l
3
a
3
CD
CD
u
o
4-1
4-1
CD
<D
u
rH
CD
01
ai
x;
CD
^
cd
•H
U3
o
4-1
>
CD
rH
>
4J
4J
4-1
U
U
XI
>
Xl
CD
4-1
ct)
T3
-6
cd
CO
X
ON
4-1
cd
e
•r)
3
rH
3
0)
3
CD
>^
w
rH
CO
s e
U
CO
w
CO
rJ
&
s
,-J
CO
u o
VI
u
0
u
M
; :
t:
trj
■, i
1
'M
u
;••
o
a
n
, <
01
al
3
0J
u
H
a
»i
id
0
1 1
>
a
u.
H
4J
Sj
(J
d
rtj
•H
u
I
DO
u
CJ
•-i
3
-.1
u
a
M
o
u
CV
W
o
u
o
<u
o
u •
rH
u u
CO
CJ 3
y
ffi M
<d
!>.
U
1
cO
rH
cu
-M
SH
4D
13
o
10
•H
fn
n
o
00
4J
a
o
•H
CO
M
M
4-)
S
s
3 o
3 u
XI
CU
cO co
<4H
cd
cd
3
CJ
4-1 4-1
tH
4->
M
Q
4-1
rH
3
CO CO
In
CO
CU
CJ
CU
H
•H
Xi 3
4-t
3
4-1
"3
CU
a
CO
3 M
o
c<J
3
c
5
u
U
CO
CO
cu
*i
<u
u
3
4J
H
O CU
T3
rH
<1)
>
u
C
Crt
O 3
-s §
w
3
<
o
ttO
1-1
4-1
3
w
O -H
2i rJ
■a
>> w
CO
u
M
O
■rH
(U
3 CO
co
•H
u
<u
i-H
cd
rH
• 3
—> fcO
3
o
CO
0)
•3
>. &4
o
CO O
a
Xi
4-1
U
JgJ
3
CO
Oh
U -H
Tj -H
3
<u
D
H
CU CO
g -a
3 rH
CO
3
PM
cu
to
3 <n
O
IJ
3
3
O -H
•H
4-1
•H
CJ
4J
4-1
C
•H
h a
n) 3
cu
4-1
(U
CJ
CJ
CU
CJ
4-1
CO
T3 PQ
cu
O
3
H
CJ
cu
>
x:
a) 3
3
u
3
3
4J
H
M
<
00
O 4-1
4->
4-)
3
Oi
en
■U
4-1
•rH
cu i-i
P3 O
3
CO
•-)
>
00
to
o
►J
4-1 H
3
cu
-3
3
•H
CO
n) in
a
u
0)
O
cO
a
t-l
TJ
4-1
£t
3 4J
D-
cu
o
§
■H
■H
CJ
<U
•H
CU
4J iH
3 CO
•H
.V
o
w
CO
u
4-1
in
CU
3 CO
U) e
3
M
XI
cu
n
CO
CO
4J
CJ
M
TJ >
cO o
o*
.2
3
o
■H
3
>■.
3
u
4-1
cfl CU
•J o
w
A
Q
o
E
(*S
CO
CO
Ph
to
Pi Z!
1976 ANNUAL REPORT 1977
HETCH HETCHY
WATER AND POWER
DOCUMENTS DEPT.
CIVIC CENTER SUBSTATION
PUBLIC UTILITIES COMMISSION
CITY AND COUNTY OF SAN FRANCISCO
CITY AND COUNTY OF SAN FRANCISCO
PUBLIC UTILITIES COMMISSION
ANNUAL REPORT
FISCAL YEAR 1976-77
HETCH HETCHY WATER AND POWER SYSTEM
AND
BUREAU OF LIGHT, HEAT AND POWER
0. L. MOORE
GENERAL MANAGER
CITY AND COUNTY OF SAN FRANCISCO
GEORGE R. MOSCONE - MAYOR
PUBLIC UTILITIES COMMISSION
JOHN F. HENNING, Jr
LYDIA LARSEN
H. WELT ON FLYNN
JOSEPH P. BYRNE
PETER McCREA
JOHN B. WENTZ
President
Vice President
Commissioner
Commissioner
Commissioner
General Manager
ANNUAL REPORT
FISCAL YEAR 1976-77
HETCH HETCHY WATER AND POWER DEPARTMENT
ORAL L. MOORE - General Manager
This report is respectfully dedicated to
Hetch Hetchy employees, past and present,
whose devoted and conscientious efforts
have made possible these accomplishments
for San Francisco.
O'SHAUGHNESSY DAM AND HETCH HETCHY RESERVOIR
showing the effects of the drought in February, 1977
HIGHLIGHTS
From the parched Redwood forests of the north state to the blazing
deserts of the south, the one single aspect that dominated all of
the water and power systems in California during the fiscal year
is an unprecedented drought and its devastating impact. For the
Hetch Hetchy Water and Power System, whose hydroelectric genera-
tion is totally dependent on water, and whose viability as a going
concern is principally dependent on power revenue, the year has
been a particularly difficult one financially.
The drought had its beginning in the winter of 1975-76 when lack
of precipitation and meager snowmelt resulted in only 605,388
acre-feet of runoff into Hetch Hetchy Reservoirs during the spring
of 1976, or 53 percent of normal. The second dry year, 1976-77,
resulted in even less runoff during the past spring, totaling only
333,504 acre-feet, or 29 percent of normal. These record low
inflows in successive years have left the three reservoirs in our
mountain watersheds at less than 45 percent of capacity at the
end of the report year.
- 1
Anticipating that the drought might continue into a second year,
the Lower Cherry Aqueduct was reconditioned in the fall of 1976
in the event that water supply to the Hetch Hetchy Aqueduct would
need to be supplemented with water from Cherry Reservoir. This
turned out to be a farsighted move when drought conditions dic-
tated shutting down Dion R. Holm Powerhouse and diverting this
water into the aqueduct to the Bay Area in October 1976.
To further conserve water in our reservoirs against future public
need, a request was submitted to the Secretary of the Interior,
in March 1977, for permission to reduce fish releases from
O'Shaughnessy Dam. So far, the Secretary has not advised us of
any decision in the matter.
Based on the precipitation record for the water year commencing
October 1, 1976, and the result of snow surveys conducted on our
mountain watersheds, the San Francisco Public Utilities Commission
instituted a mandatory 25 percent reduction in system water
consumption. The reduction was put into effect May 1, 1977, in
order to insure the ability of the Hetch Hetchy systems to meet
the needs of the San Francisco Water Department and its service
area during the continuing drought.
Comparing the amount of electric energy generated this year against
that of previous years, the adverse impact of the drought is
apparent. As generation was reduced to about 35 percent of normal,
the resulting revenue available for supplying the cash flow for
operating and maintaining the department was also reduced in
roughly the same proportion. This necessitated rescinding many of
the capital improvement projects scheduled for the year.
In spite of the above, work progressed on the federally assisted
Power Improvement Program for the rehabilitation of the Municipal
Railway transit power system. As of the end of the fiscal year,
approximately $26.5 million has been expended or encumbered. The
professional services contracts for engineering design are 90 per-
cent completed. Twenty-seven contracts for construction work and
material purchases have been completed and twenty-two are currently
in progress. Electrification of the Market Street Subway and Twin
Peaks Tunnel is nearly completed. Ten of the eighteen substations
are under construction, with three completed and in service.
Thirty miles of the eventual fifty miles of underground duct lines
are completed or under construction. Approximately 35 percent of
the underground feeder cable has been installed, and an additional
20 percent is on order for delivery to current installation
contractors. The conversion of the streetcar overhead trolley
system for pantograph operation is progressing with all work on
the "K" Line under construction; the "NM Line ready for bid; and
the "J", "L" and "M" Lines in the final design stages.
- 2
HETCH HETCHY ORGANIZATION AND FUNCTIONS
Under policies established by the San Francisco Public Utilities
Commission, the HETCH HETCHY WATER AND POWER DEPARTMENT and the
BUREAU OF LIGHT, HEAT AND POWER serve the City and County of
San Francisco in the dual function of operating department and
service bureau.
Hetch Hetchy is a municipally-owned system of storage reservoirs
and aqueducts which collects water from the Tuolumne River water-
shed and delivers it to the San Francisco Water Department. As
a by-product of falling water, Hetch Hetchy operates and maintains
hydroelectric generating stations and high voltage transmission
lines for the production and distribution of electric energy.
Through its Transit Power Division, Hetch Hetchy has funded,
operated, maintained and provided improvements for the electric
facilities of the San Francisco Municipal Railway since July 1,
1969.
In order to handle this additional responsibility, Hetch Hetchy
assumed control of the equipment and personnel of the Overhead
Lines and Motive Power Sections of the Municipal Railway.
All of Hetch Hetchy' s expenses, including those of the Transit
Power Division, are supported by water and power revenues.
The Bureau of Light, Heat and Power administers contracts for
furnishing electric, gas and steam services to municipal depart-
ments and handles monthly billings. It also administers contracts
for furnishing street lighting services and for operation and
maintenance of City-owned street lighting. Financing, design and
construction of City-owned street lighting improvements are under
the jurisdiction of the Department of Public Works, and plans for
these improvements must be approved by the Public Utilities
Commission through this Bureau. The Bureau is financed by appro-
priations from municipal departments and gas tax funds.
For fiscal year 1976-77, the Department administered budgeted
funds for all purposes as follows:
Number of Total Amount
Budget Employees Appropriated
Hetch Hetchy Water and Power 216 $ 52,999,096
Hetch Hetchy Water and Power
(Transit Power Division) 52 3,671,863
Bureau of Light, Heat and Power 11 11,262 ,850
279 $ 67,933,809
3 -
MOCCASIN POWERHOUSE AND RESERVOIR
- 4
HETCH HETCHY WATER AND POWER SYSTEM
REVENUE AND EXPENDITURES
Revenue from Hetch Hetchy Water and Power operations is derived
principally from two sources:
1. Sale of water to the San Francisco Water Department
2. Sale of electric power and energy to San Francisco Municipal
departments, Modesto and Turlock Irrigation Districts in the
San Joaquin Valley, and seven industrial customers:
Kaiser Cement § Gypsum Corporation Santa Clara County
Kaiser Aluminum § Chemical Corporation Santa Clara County
Lockheed Missiles and Space Company, Inc. Santa Clara County
General Motors Corporation Alameda County
IBM Corporation Santa Clara County
Liquid Air, Inc. Alameda County
Norris Industries, Riverbank Stanislaus County
WATER SALES
This past year, revenue from the sale of water and standby service
to the San Francisco Water Department was $8 million.
POWER SALES
Gross sale of electric energy was $43,341,973, up from $19,693,525
during 1975-76. This doubling of revenue is deceiving, since the
increase does not represent extra return on project investments
for the following reasons:
1. The increase is principally due to the record-breaking amount
of supplementary power and energy which City had to purchase
for resale, on account of the drought, and which was resold
to the customers at substantially the same high price at which
it was purchased.
2. The offset to this year's so-called record revenue, in terms of
expenditure for supplementary power and energy, is $33,921,500
instead of the $2,100,000 budgeted, leaving only $9,420,473 in
net revenue from gross, a far cry from the record net of over
$18 million for 1974-75.
Power and energy delivered to City Departments increased 2.0 per-
cent over the previous year, about the same rate as in 1975-76.
The City department mainly responsible for this increase is the
San Francisco International Airport. Consumption at the Airport,
the single largest energy consumer among the City Departments,
- 5 -
Miscelloneous Revenue
$ 124,451
Administrotion Operation &
Maintenance Tronsit
Power Division
$ 1,426,705
Capitol Improvement
Helch Hetchy
Project
$ 221,00
HETCH HETCHY REVENUES
AND EXPENDITURES
FISCAL YEAR 1976-77
- 6
has increased by 3.2 percent, indicative of a resurgence of
construction and expansion activities. Requirements for the
Municipal Railway appear to have increased by 9.5 percent over
the previous year. This is not a valid comparison, of course,
because of last year's low consumption due to shutdown of the
public transportation system during the 38-day employees' strike.
Power and energy delivered to Modesto Irrigation District, Hetch
Hetchy's largest power customer, and to Turlock Irrigation District,
the third largest, increased by 17.2 percent and 37.9 percent
respectively this year. These increases are directly related to
the drought. The storage in Don Pedro Reservoir, upon which the
two Districts are dependent for generation and irrigation needs,
has been going down steadily and the Districts have been extremely
careful in using this precious and meager resource. Since Hetch
Hetchy is in the same predicament, 86 percent of the power deliv-
ered to the Districts by Hetch Hetchy had to be supplied from
supplementary power and energy purchased from the Pacific Gas and
Electric Company.
Total generation of 710,002,000 kilowatthours for the report year
from the project's three plants (the lowest production since 1969)
amounts to 43 percent of the output of 1,640,471,000 kilowatthours
in 1975-76. The financial strength of the Department resulting
from this decline in electric energy generation has been severely
impaired. If current conditions continue, additional shortfall
in operating revenue in the upcoming fiscal year can be anticipated.
Hetch Hetchy power is sold at cost to City Departments for munici-
pal purposes, representing a saving to taxpayers for 1976-77 of
approximately $4 million, compared to the cost if supplied by the
local investor-owned utility at rates which include a "fuel cost
adjustment" to account for the additional costs brought on by the
unending price increases in oil, gas and coal fuel used for
electric generation. Beginning September 1976, revised rates for
Hetch Hetchy power, approved by the Commission on July 13, 1976,
became effective for private consumers and municipal users. The
higher rates boosted power revenue from these sources by nearly
$1 million in the fiscal year. This is just another step in our
continuing effort to base our power rates on the value of power
in the market place, in order to maximize the return of the power
that is produced from the Hetch Hetchy system. In a fiscal year
where generation is at a record low, this increase helped to
somewhat ease the economic dislocation brought on by the reduced
generation.
SYSTEM PLANNING
As part of our efforts to increase rainfall in our mountain water-
sheds, in light of the lessons learned from the drought, the
7 -
CO
en
o
IE
o
_)
25-
20—
15-
10-
CD
HETCH HETCHY
GENERATION
1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 1977
( Year Ending June 30)
HETCH HETCHY ELECTRIC ENERGY SOURCES
40 —
35-
30 —
CO
QC
<
J
25—
_J
o
Q
u_
20 —
O
co
z:
o
15—
10-
5 —
REVENUE DEDUCTI0
FOR SUPPLEMENTA
-<
REVENUE
FOR
AF1
SUPF
'ER [
>LEMI
)EDU
:nta
:nor
L
i
1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 1977
( Yea r Ending June 30 )
REVENUE FROM SALE OF ELECTRIC ENERGY
Department has been investigating the feasibility of a weather
modification program. The goal is to increase precipitation by
cloud seeding of appropriate storms in the area. Preliminary
data indicate that our effort should be directed to the Cherry
Watershed. As an initial step to bring this program to fruition,
plans are under way to hire expert consultants for the preparation
of an Environmental Impact Report.
On October 22, 1976, the City and County of San Francisco, through
the Public Utilities Commission, together with the Modesto and
Turlock Irrigation Districts, submitted an "Amended Application
for Preliminary Permit, Clavey-Wards Ferry Project" to the Federal
Power Commission. The application was made in order that the City
and the Irrigation Districts might secure and maintain priority
for a license under the Federal Power Act. The proposed project
consists of three small dams and related facilities designed to
harness the unused power potential of the Tuolumne. They would be
situated on the upper reaches of the river below the City's Dion R.
Holm and Robert C. Kirkwood Powerhouses and upstream from Don
Pedro Dam. It is estimated that the project has a capability of
generating 400 megawatts of power as well as a new water supply of
11,900 acre-feet. However, actual development will depend on the
outcome of a study by federal agencies for possible inclusion of
this portion of the river in the federal wild and scenic river
system.
OPERATION AND MAINTENANCE
On Sunday, November 7, 1976, at approximately 0822 hours, the
13,800 volt metal-clad switchgear unit through which power is
supplied to the 2,500 kVA Ridge Line transformer from Generator
No. 2 at Dion R. Holm Powerhouse failed during routine testing
of a protective device. The failure resulted in destruction of
the circuit breaker element and related appurtenances. However,
service to the Ridge Line was promptly restored by connecting it
to the Mather Line, which is supplied from Robert C. Kirkwood
Powerhouse. Necessary replacements were purchased from General
Electric and installed by Department personnel with final adjust-
ment and testing performed by field engineers from General
Electric. All work was completed and service to the Ridge Line
reverted to Dion R. Holm Powerhouse on June 3, 1977.
- 9
WATER PRODUCTION AND TRANSMISSION
Precipitation recorded for the year at our measuring stations was
52 percent of the long term average. Much of this amount fell
during the normally dry summer months and did not run off.
During the year, 89,103,588,000 ga
from the Tuolumne River watershed
Aqueduct to the San Francisco Wate
105 percent of the City's total cu
deliveries represent a decision by
its local storage reserve. In add
6 percent from last year, were del
Atomic Energy Commission at Mocho
Tunnel for use at the Lawrence Rad
58,864,608 gallons, up 19 percent
Groveland Community Service Distri
Mountain Tunnel.
lions of water were diverted
through the Hetch Hetchy
r Department, representing
stomer consumption. The water
the Water Department to increase
ition, 223,307,920 gallons, down
ivered to the United States
Shaft of the City's Coast Range
iation Laboratory at Livermore;
over 1975-76, were delivered to
ct in Tuolumne County from the
Appendix Table 6 shows comparative data on precipitation, runoff,
storage and delivery of the Hetch Hetchy Water Supply System.
300,000
to
O
UJ
or
200,000
100,000-
or
0-
' 1972-73 ' 1973-74 ' 1974-75 ' 1975-76 ' 1976-77
DELIVERIES OF WATER TO
SAN FRANCISCO WATER DEPARTMENT
10
OPERATION AND MAINTENANCE - TRANSIT POWER DIVISION
The Transit Power Division is responsible for supplying the 600
volt direct current power that is necessary to operate the street-
cars and trolley coaches of the San Francisco Municipal Railway.
The Transit Power Division is composed of two sections - the
Motive Power Section and the Overhead Lines Section.
Motive Power Section
The Motive Power Section operates and maintains ten substations
which convert electric power from 12,000 volts alternating current
to 600 volts direct current by means of motor-generators, synchro-
nous converters, mercury arc rectifiers and silicon rectifiers.
(See Appendix Table 3 for statistical data.) Motive Power is
also responsible for maintaining the electric motors and associated
control equipment for operating the cable-winding machinery located
in the Cable Car Powerhouse at Washington and Mason Streets. In
addition, Motive Power periodically inspects, cleans, adjusts and
repairs the streetcar and trolley coach headway recorders at
Central Control of the Municipal Railway. The substations operate
24 hours per day, 365 days per year.
In anticipation of the need to assume responsibility for eighteen
new substations being built by the Power Improvement Program
(reported elsewhere in this report) , this section perused and
commented on the wiring and control schemes proposed for these
stations. The first of the new electrical substations, Civic
Center Station, was placed in revenue service in December of 1976.
A commissioning ceremony was held by Mayor George Moscone who
dedicated this first station to the service of the citizens of
San Francisco.
A new mimic board showing the new stations in schematic form was
constructed and installed at the Bryant Substation. As each new
automatic station is completed and becomes operational, it will
be monitored and controlled from this remote location via telephone
lines. Since Civic Center, Church, Judah, Outer Mission and West
Portal Stations are presently unmanned, controls for these stations
were designed and installed on this new mimic board. This new
status display and control board will continually be augmented
with additional automatic station controls until such time as it
shall be superseded by a more sophisticated and flexible Supervisory
Control System.
Overhead Lines Section
The primary function of the Overhead Lines Section is to maintain
in satisfactory operating condition the trolley wire overhead
facilities and the electric distribution system which conveys
power to it. This electric distribution system consists of both
overhead lines and underground cables.
-11-
Secondary functions include the maintenance of the Municipal
Railway Signal Systems and the electric light and power installa-
tions at all Municipal Railway buildings.
During fiscal year 1976-77, the Overhead Lines Section responded
to 3,943 emergency calls, an increase of 8 percent over the prior
year. In addition to emergency calls, this section performed a
regular and extensive ongoing maintenance program. All overhead
and underground facilities were systematically inspected and all
worn or damaged parts that could cause accidents or equipment
malfunctions were replaced. This section also operates an
emergency crew 24 hours a day year round, including all holidays.
The main work crew normally worked on the day shift but occasion-
ally was assigned to night work to overhaul facilities during the
hours Muni trolleys and streetcars do not run.
A considerable amount of damage to overhead facilities was caused
by trolley coaches de-wiring and snagging their poles in the
overhead facilities and tearing them down, or by breaking the spans
with the flaying poles. Such damage was repaired at no cost to
the Municipal Railway. Other parties who damaged our facilities
were billed for the cost of repairs. This included damage to
overhead facilities caused by high loads on trucks or careless
operation of crane equipment and damage to underground feeder
cables by contractors digging into our duct lines. During 1976-77,
responsible parties were billed for 9 damage cases totaling
$17,246.41. The Overhead Lines Section also performed work for
4 building owners and contractors under work orders amounting to
$2,994.82. This work included moving trolley poles to accommodate
driveways; relocating trolley poles and feeders to permit construc-
tion of new buildings; temporarily removing trolley wires and
feeders to permit passage of high loads; and shifting of trolley
wires and feeders for various excavations.
The Overhead Lines Section engaged in many other activities of a
related nature which it is especially equipped to perform. These
additional duties included repairs, maintenance and construction
of electrical systems in Muni's car barns, offices and shops;
welding and rebuilding of worn overhead lines special work; making
and rebuilding parts for switches, warning block signals, car
recorders, and strand alarms for the cable car system; installing
mobile radio equipment; installing streetcar and bus stop signs
and public information signs.
- 12
ENGINEERING DIVISION
The Engineering Di
engineering servic
Division and the P
the preparation of
specifications for
and for items of m
construction, cont
are provided for a
and Power. Work o
knowledge and expe
which have the nee
Engineering Divisi
and Construction,
Administration, an
vision of Hetch Het
es for the Hetch He
ower Improvement Pr
studies, reports,
new construction,
ajor maintenance,
ract administration
11 construction wor
f unusual magnitude
rtise is done by en
essary manpower and
on is organized int
Electrical, Mechani
d Special Projects
chy Water and Power provides
tchy Project, Transit Power
ogram. These services include
cost estimates, and plans and
for replacement of structures
Surveying, inspection of
and payment recommendations
k under Hetch Hetchy Water
or which requires special
gineering consulting firms
qualifications. The
o six main sections: Civil
cal, Architectural, Engineerinj
(Power Improvement Program) .
During the year, plans and specifications were prepared for the
following work to facilitate and maintain Hetch Hetchy operations
HH-454
Moccasin Sewage Treatment
Plant
A package sewage treatment plant
has been planned to replace the
existing septic tank system. This
process is a carryover from last
year due to the lengthy process
required to obtain approval for a
federal "Clean Water Grant". State
and federal permission to begin
preparation of final plans and
specifications was given in Septem-
ber, 1976. Approval of the final
plans and specifications was ob-
tained in March, 1977. The con-
struction contract has subsequently
been awarded with work to begin in
August, 19 77.
DAVID SHAW, STATIONARY ENGINEER,
PERFORMING A TEST AT THE MOCCASIN
SEWAGE TREATMENT PLANT
13
HH-514 - Moccasin Administration Building, Replace Heating System
Under this contract, completed during the year, the old heating
system, using costly fuel oil, was replaced by a new electrical
heating/ventilating system. In addition, extensive electrical
improvements were made to bring the existing electrical system up
to code requirements, and extensive plumbing and architectural
improvements were also made.
HH-549 - Bryant Substation and Power Control Center
The Power Control Center (part of the Power Improvement Program
described elsewhere in this report) was originally to be installed
in the existing Bryant Substation building. When engineering
investigations of this 1904 building revealed that it did not meet
seismic standards, it was determined to construct a new building
to house both the Control Center and the new substation. The
Control Center portion of the building will accommodate the facili-
ties for remote supervisory control of the eighteen new automatic
substations that will provide electric power for the Municipal
Railway. The design of the substation portion of the building
was performed by our consultants under the Power Improvement
Program. The design of the Power Control Center portion of the
building has nearly been completed by Hetch Hetchy personnel.
The design of the facility has received approval of the Art
Commission and a City Planning Commission Environmental Impact
Report determination of no significant effect on the environment.
HH - 5 5 5 - Red Mountain Bar Surge Shaft Cover
A construction contract was let to cover the surge shaft with a
steel frame and steel sheets to provide a barrier against debris
entering the water supply.
HH-557 - Paint Steel Trolley Poles, Various Locations
A construction contract was let to prepare and paint trolley poles
in numerous locations throughout the City. This work is part of
a continuing program to rehabilitate all of the trolley poles in
the City that are not to be replaced under the Power Improvement
Program or other federal grant.
HH - 5 6 5 - Lower Cherry Aqueduct Rehabilitation
In anticipation of a continued drought, an emergency construction
contract was let to rehabilitate the Lower Cherry Aqueduct in
order to supplement the water supply to Hetch Hetchy Aqueduct with
water from Lake Lloyd and Lake Eleanor. This three mile long
aqueduct was originally constructed in 1917, had not been used
since 1960, and was in poor condition. The contract has been
completed and diversion of water began in November 1976 with a
capability of supplying approximately 130 mgd into the Hetch
Hetchy Aqueduct at Early Intake.
14
HH-5 66 - San Joaquin Valve House - Backflow Prevention and
Replacement of Miscellaneous Pipeline Appurtenances
Design of this facility has been directed toward a determination
of the actual water level in Elliott Cut and how it is controlled.
HH - 5 6 8 - Moccasin New Vehicle Refueling Station
Plans and specifications have been completed to replace and
relocate the existing vehicle refueling station that does not meet
present operating and safety requirements. The new location will
also provide for the new air pollution control regulations.
HH - 5 7 3 - Replace, Repair and Paint Trolley Poles, Various Locations
A contract was let to replace, repair and paint trolley poles at
various locations. This work is part of a continuing program to
rehabilitate all of the trolley poles in the City that are not to
be replaced under the Power Improvement Program or other federal
grant.
HH-576 - Hughes Leithold and Foothill Waterlines
Replace and Repair
Design work on this project involved research into the actual loss
of water from natural springs that resulted from the construction
of the Foothill Tunnel in the 1930's, and included field surveys
to the existing temporary supply system.
15
POWER IMPROVEMENT PROGRAM
Work during fiscal year 1976-77 under the UMTA-approved Federal
Grant for the Power Improvement Program was as follows:
1. Grant Amendment
Amendment No. 2 to the Project Grant was approved by UMTA on
July 21, 1976. This final amendment provides sufficient funds
for the balance of the Project and increases the total Project
Cost to $50.5 million and the Federal Grant to $36.5 million.
2 . Project Status
As of the end of the fiscal year, approximately $26.5 million
has been expended or encumbered. The professional services
contracts for engineering design are 90 percent completed.
Twenty-seven contracts for construction work and material
purchases have been completed and twenty-two are currently in
progress. Electrification of the Market Street Subway and
Twin Peaks Tunnel is nearly completed. Ten of the eighteen
substations are under construction, with three completed and
in service. Thirty miles of the eventual fifty miles of
underground duct lines are completed or under construction.
Approximately 35 percent of the underground feeder cable has
been installed and an additional 20 percent is on order for
delivery to current installation contractors. The conversion
of the streetcar overhead trolley system for pantograph
operation is progressing with all work on the "K" Line under
construction, the "N" Line ready for bid and the "J", "L" and
"M" Lines in the final design stages. Details of the various
projects and contracts are in the following sections.
3 . Electrification and Overhead Conversion
A) Contracts
Construction was essentially completed on Contract HH-521,
Market Street Subway Electrification, Embarcadero Station
to Duboce Portal. Modification of Contract No. 5, in the
amount of $122,690, for corrective work required for final
alignment of the catenary system to suit field conditions,
was approved by UMTA on June 9, 1977. The Contractor
commenced work on the modification.
Construction neared completion on Contract HH-531, Market
Street Subway Electrification, Duboce Junction to Eureka
Station.
All PIP work included in Contract MR-622R, Twin Peaks
Tunnel Electrification, Structural Repairs and Improvements
was completed on June 17, 1977.
16 -
JUNIPERO SERRA BLVD. LOOKING NORTH FROM OCEAN AVE
BEFORE-Overhead feeder cables and streetcar trolley overhead
AFTER-New trolley/streetlight poles and pantograph type overhead
17
Plans and specifications for Contract HH-524, K Line
Streetcar Overhead System, Conversion for Pantograph
Operation, were completed and transmitted to UMTA for
approval on November 2, 1976. Following approval of
plans and specifications by UMTA, bids were received on
December 2, 1976. The contract was awarded on December 14,
1976 to Amelco Electric, San Francisco, California, who
submitted the low bid of $239,000. The contract was
certified by the City Controller on January 24, 1977.
Construction commenced on February 21, 1977.
Plans and specifications for Contract HH-536, Streetcar
Overhead System, West Portal Avenue, Conversion for
Pantograph Operation, were completed and transmitted to
UMTA for approval on July 28, 1976. Following approval
of plans and specifications by UMTA, bids were received
on August 26, 1976. The contract was awarded on
September 14, 1976 to Mahoney Electric Co. Inc., San
Francisco, California, who submitted the low bid of
$295,671. The contract was certified by the City
Controller on October 21, 1976. Construction commenced
on November 8, 1976.
Construction was completed on Contract HH-517, K-Line
Transit Power Facilities, Street Lighting and Related
Work. Included was the installation of new trolley poles
and overhead trolley wire reconstruction for pantograph
operation on Junipero Serra Boulevard.
Construction on Contract MR-620, "K" Line, Ocean Avenue
at Route 280 Overpass, Track Reconstruction and power
Facilities, was completed. Included was overhead trolley
wire reconstruction for pantograph operation.
Final contract documents for Purchase Contract No. 1 for
Special Trolley Coach/Streetcar Crossing Hardware were
completed and transmitted to the City Purchaser. The
special hardware will be purchased by the City, due to
the six-month manufacturing lead time, and will be
furnished to several installation contractors. The
contract was advertised by the City Purchaser on October 4,
1976. Bids were received on October 29, 1976. The
contract was awarded to Ohio Brass Co., who submitted the
sole bid in the amount of $20,049. The manufacturer, Ohio
Brass Co., completed fabrication of the special trolley
coach/streetcar crossing hardware and delivery was made on
June 8, 1977.
Final contract documents for Purchase Contract No. 2 for
Special Trolley Coach/Streetcar Crossing Hardware were
18
completed and transmitted to the City Purchaser. Bids
were received on May 20, 1977. On June 27, 1977, the
City Purchaser awarded the contract to Ohio Brass Co.,
who submitted the low bid of $24,275.
During this year, the Municipal Railway outfitted an
existing PCC streetcar with an LRV pantograph, floodlights,
and an observation window in the roof. The location of
the pantograph on this PCC is essentially identical to
its location on the new LRV streetcars now being manufac-
tured for the City of San Francisco. This car was and
will be used by Hetch Hetchy as an overhead trolley system
test car, testing the catenary systems installed in the
Market Street Subway and Twin Peaks Tunnel and testing
the surface overhead trolley systems being converted for
pantograph operation under various contracts. The car
will remain in regular passenger service except when
required for testing.
B) Design
The Consultant, PBQ^D, Inc. and Gibbs § Hill, Inc. (PBGH)
continued work on final design contract plans and
specifications .
Hetch Hetchy review continued on plans and specifications
at the 95 percent completion level as submitted by the
Consultant for streetcar overhead system conversion for
pantograph operation for Contracts HH-530 ("J" Line -
Duboce to 17th Street), HH-532 ("N" Line), HH-533 ("J"
Line), HH-534 ("L" Line), and HH-535 ("M" Line), with
emphasis on Contract HH-532 ("N" Line) .
Review was completed on the 95 percent completion level
plans and specifications for Contract HH-532, "N" Line
Streetcar Overhead System, Church Street to Nineteenth
Avenue, Conversion for Pantograph Operation, and Sunset
Tunnel Electrification. Comments were transmitted to
the Consultant, PBGH, for incorporation into the final
contract documents. Following return of plans and
specifications from the Consultant, with corrections,
preparation of final contract documents commenced.
Contract is scheduled to be advertised in August 1977.
Plans and specifications to be included in DPW Contracts
23,919 and 23,920 - Judah Street, 19th to 32nd Avenue and
32nd Avenue to La Playa, Street Improvement and Track
Reconstruction, were completed and transmitted to the
Department of Public Works. The work to be included
consists of replacement of trolley poles and conversion
of the streetcar overhead system for pantograph operation,
19 -
This work was formerly part of Contract HH-532, and the
plans and specifications were prepared by the Consultant,
PBGH. The plans and specifications were approved by UMTA
on May 13, 1977, and June 27, 1977 respectively. Plans
and specifications for DPW Contract 23,919 were approved
by the State (FAU) on June 23, 1977. The contract is
scheduled to be advertised by DPW in July 1977. Adver-
tising of DPW Contract 23,920 is awaiting approval by
the State (FAU) .
Plans and specifications for new trolley pole foundations
on the "M" Line from St. Francis Circle to Junipero Serra
Boulevard were completed and delivered to Muni (TIP) on
May 27, 1977 for inclusion in Contract MR-643, "M" Line
Rerailing. The new trolley poles and overhead conversion
work will be done later under Contract HH-535.
Plans and specifications were completed and transmitted to
Muni (TIP) on March 31, 1977 for Contract MR-642, West
Portal Avenue, Track Reconstruction. The work to be
included consists of the relocation of the streetcar
overhead to suit the new track alignment.
The Consultant completed work of determining the nature,
degree, cause and correction of deviations in catenary
construction from contract designs in the Market Street
Subway. Drawings for the corrective work were completed
and issued to the Contractors.
20 -
1
4 . Substations
A) Contracts
Construction neared completion on Contract HH-522, Civic
Center, Church, and Downtown Substations, Installation of
Electrical Equipment. The Contractor completed installa-
tion of substation equipment and performed pre-energization
tests at Church and Civic Center Substations. On
November 23, 1976, the Civic Center Substation was dedi-
cated and Unit No. 2 (12 kV ac switchgear, transformer,
4000 kw silicon diode rectifier and 600 V dc switchgear)
was placed in operation. On December 23, 1976, Unit No. 1
(12 kV ac switchgear, transformer, 4000 kw silicon diode
rectifier and 600 V dc switchgear) was placed in operation.
On March 21, 1977, the second major unit of the Power
Improvement Program, Church Substation, consisting of two
4000 kw transformer-rectifier units and associated 12 kV
ac and 600 V dc switchgear, was placed in operation. Unit
No. 1, Phase I at Downtown Substation (12 kV ac switchgear,
transformer, 4000 kw silicon diode rectifier and 600 V
switchgear) was inspected, tested and on July 22, 1976
The Honorable George Moscone, Mayor, and Oral L. Moore, General
Manager, Hetch Hetchy Water and Power, at the dedication ceremony
of the Civic Center Substation, November 23, 1976.
21 -
placed in operation and began supplying 600-volt dc power
to Muni vehicles on lower Market Street and adjacent areas.
Installation of Unit 1, Phase I equipment completed the
first of four phases required to replace the obsolete
rotating machines with modern equipment while keeping the
substation in operation. The Contractor completed the
removal of the old equipment and prepared for installation
of the remainder of the new equipment in the final Phase IV
of the conversion.
Construction neared completion on Contract HH-528, Laguna
Honda and Judah Substations, Construct Buildings and
Install Equipment. On April 29, 1977 Judah Substation
was energized and load tested. This single-unit 4000 kw
rectifier substation began providing power for the "N"
Line streetcars on Judah Street from 20th Avenue to
La Playa on May 3, 1977.
Construction commenced on Contract HH-529, Carl Substation,
Construct Building and Install Equipment, on July 19, 1976.
Bids were received on July 15, 1976 for Contract HH-544,
Fillmore Substation, Construct Building and Install
Equipment. The contract was awarded on July 27, 1976 to
Herrero Brothers, Inc., San Francisco, California, who
submitted the low bid of $641,840. The contract was
certified by the City Controller on August 25, 1976.
Construction commenced on September 13, 1976.
Plans and specifications for Contract HH-546, Randolph
Substation, Construct Building and Install Equipment,
were completed and transmitted to UMTA for approval on
November 8, 1976. The plans and specifications were
approved by UMTA on November 24, 1976. Bids were received
on January 13, 1977. The contract was awarded on
January 25, 1977 to Kaplan-Jones, Joint Venture, who
submitted the low bid of $226,900. The contract was
certified by the City Controller on February 14, 1977.
Construction commenced on March 7, 1977.
Plans and specifications for Contract HH-547, San Jose
Substation, Install Equipment, were completed and trans-
mitted to UMTA for approval on September 14, 1976. The
plans and specifications were approved by UMTA on
September 28, 1976. Bids were received on October 14,
1976. The contract was awarded on October 26, 1976 to
L. K. Comstock $ Co., Inc., who submitted the low bid of
$84,790. The contract was certified by the City Controller
on February 3, 1977. Construction commenced on February 28,
1977.
22
Plans and specifications for Contract HH-548, Taraval
Substation, Construct Building and Install Equipment,
were completed and transmitted to UMTA for approval on
January 11, 1977. The plans and specifications were
approved by UMTA on February 3, 1977. Bids were received
on February 24, 1977. The contract was awarded on March 8,
1977 to J. DiGiorgio $ Sons, who submitted the low bid of
$253,950. The contract was certified by the City
Controller on March 23, 1977. Construction commenced on
April 18, 1977.
B) Design
The Consultant, Bechtel, Inc., completed design work on
the substation buildings and equipment installation.
Final plans and specifications for Contract HH-549, Bryant
Substation, Construct Building and Install Equipment, were
received from the Consultant in May 1977. The plans and
specifications will be included in one contract for the
construction of the Bryant Substation and Power Control
Center Building. The design for the Power Control Center
portion of the building is nearing completion by Hetch
Hetchy Engineering personnel.
Final plans and specifications for Contract HH-550, West
Portal Substation, Install Equipment, were received from
the Consultant in October 1976. Advertising of the con-
tract must be deferred until the structure, which is a
part of the new West Portal Station being constructed by
BART, is completed sufficiently in early 1978.
Final plans and specifications for Contract HH-551,
Richmond Substation, Install Equipment, were received
from the Consultant in April 1977. Advertising of the
contract must be deferred until the new West Portal
Substation is completed in 1978, and the equipment from
the existing West Portal Substation will be available for
relocation to Richmond Substation.
Advertising of Contract HH-545, Outer Mission Substation,
Install Equipment, is being deferred until the completion
of the new San Jose Substation under Contract HH-547. The
plans and specifications for HH-545 were previously com-
pleted by the Consultant. This is necessary so that the
Outer Mission Substation can be shut down during recon-
struction and its load temporarily assumed by the San Jose
Substation.
The building design for the new combined Bryant Substation
and Power Control Center received approval from the San
Francisco Art Commission.
- 23 -
The City Planning Commission issued a negative declaration
of environmental impact and approved the project as con-
forming to the Master Plan.
C) Equipment Purchase
The substation equipment manufacturer, ITE-Gould, completed
production on the $5,896,000 purchase contract.
Review of shop drawings submitted by ITE-Gould was
completed.
Negotiations were conducted with ITE-Gould for a contract
modification to provide additional equipment for Laguna
Honda Substation. The second rectifier, transformer and
related switchgear to be purchased will provide power
reliability in the Twin Peaks Tunnel. This addition to
the Project was approved by UMTA in the Grant Amendment.
Deliveries of equipment under the purchase contract were
virtually completed. Equipment for Laguna Honda, Judah
and Downtown Substations were received by the Contractors,
Herrero Brothers, Inc. (Laguna Honda and Judah) and DeNarde
Construction Co. (Downtown) and is being installed. This
completed delivery to the site for five substations. For
the remaining substations, all items of the equipment,
except for minor shortages, are on hand at the local ware-
house for later pickup by the installation contractors.
Meetings were held with factory representatives from ITE-
Gould to resolve outstanding minor problems that have
developed during installation and initial operation of
the new substation equipment.
The Service Engineer, assigned by ITE-Gould to assist
during installation and testing of the new equipment,
continued to provide assistance at Downtown, Civic Center,
Church, Laguna Honda and Judah Substations.
Work continued on the preparation of plans and specifica-
tions for the purchase of additional substation equipment
for Stations E, F, J and N.
Control and Communications
Plans and specifications at the 90 percent completion level
for Contract HH-569, Supervisory Control System, Equipment
Purchase and Installation, were resubmitted by the Consultant,
Systems Control, Inc., in January 1977. Review was completed,
and the plans and specifications were returned to the Consultant
with comments and corrections to be incorporated into the final
plans and specifications.
24
Plans and specifications at the 90 percent completion level
for Contract HH-574, Communication Cable and Subway Maintenance
Telephone System, Installation Contract No. 1, were submitted
by the Consultant. Review was completed and the plans and
specifications were returned to the Consultant with comments
to be incorporated into the final plans and specifications.
Amendment No. 1 to the existing professional services agreement
was negotiated with the Consultant. The amendment provides
for additional design services necessary to extend the super-
visory control system to the four additional substations - E,
F, J and N, recently added to the PIP, and to increase the
flexibility of the maintenance telephone system. The amendment
which increases the total cost of the agreement from $85,895
to $93,607, was approved by the PUC on August 24, 1976, and
was certified by the City Controller on September 28, 1976.
Cable Purchase
Orders totaling 370,000 feet of insulated power cable were
placed during the fiscal year for contracts in progress that
require City-furnished cable. A total of approximately 780,000
feet of cable has been purchased under the contract with
Cyprus Wire § Cable Company, which expired on June 30, 1977.
Efforts to extend the contract were unsuccessful.
Contract documents were prepared and transmitted to UMTA on
June 13, 1977 for a new contract to provide the estimated
650,000 feet of cable required to complete the planned work
under the Power Improvement Program. The contract documents
were approved by UMTA on June 21, 1977. Bids are scheduled
to be received by the City Purchaser on July 8, 1977.
Feeder Undergrounding
A) Church Street - 22nd Street to 30th Street - Underground
Duct System (Contract HH-497)
All work on this contract was completed in accordance with
contract plans and specifications on July 14, 1976.
B) Taraval Street and 46th Avenue - 20th Avenue to Vicente
Street - Underground Duct System (Contract HH-505)
All work on this contract was completed in accordance with
contract plans and specifications on October 8, 1976.
C) K-Line, Transit Power Facilities, Street Lighting and
Related Work (Contract HH-517)
All work on this contract was completed in accordance with
contract plans and specifications. Included was underground
- 25
feeder cable installation in previously constructed duct
banks on West Portal and Ocean Avenues and Junipero Serra
Boulevard.
D) Sutter - Presidio Avenue to Leavenworth - Underground Duct
System (Contract HH-525T
All work on this contract was completed in accordance with
contract plans and specifications on September 14, 1976.
E) McAllister Street - Divisadero to Leavenworth - Underground
Duct System (Contract HH-526)
All work on this contract was completed in accordance with
contract plans and specifications on November 24, 1976.
F) Ashbury, Fillmore, Church, 18th and Other Streets
Underground Duct System (Contract HH-526)
All work on this contract was completed in accordance with
contract plans and specifications on January 13, 1977.
G) K-Line, Ocean Avenue at Route 280 Overpass, Track
Reconstruction and Power Facilities (Contract MR-620)
All work on this contract was completed in accordance with
contract plans and specifications. Included was the
construction of underground duct lines.
H) Ocean Avenue and Phelan Avenue Rechannelization and Track
Reconstruction (DPW Contract 23,727)
Bids were received on August 4, 1976 for DPW Contract 23,727
for Ocean and Phelan Avenues Rechannelization, which
includes relocation of trolley poles and the overhead trol-
ley wire system and the undergrounding of feeder cables,
along with Muni streetcar track relocation and rerailing.
The contract was awarded on September 3, 1976 to Homer J.
Olsen, Inc., Union City, California, who submitted the low
bid of $1,415,831. The amount bid for the PIP work included
in the contract was $63,962. The contract was certified
by the City Controller on November 8, 1976. Construction
commenced on November 10, 1976.
I) Judah Street - 20th to 48th Avenues - Underground Power
Facilities (Contract HH-523)
Plans and specifications for construction of manholes and
underground duct banks and the installation of feeder
cables and related work were completed and transmitted to
UMTA for approval on November 22, 1976. Included in the
26 -
contract to be funded under the Transit Improvement
Program is the furnishing and installing of new trolley/
streetlight poles and the furnishing and installing of
new feed spans and related work. The plans and specifica-
tions were approved by UMTA on December 1, 1976. Bids
were received on December 16, 1976. The contract was
awarded on January 11, 1977 to L. K. Comstock § Company,
Inc., San Francisco, California, who submitted the low
bid of $355,462. The contract was certified by the
City Controller on February 8, 1977. Construction
commenced on February 28, 1977.
J) Sutter, McAllister and Fillmore Streets - Underground
Power Facilities and Related Work (Contract HH-540)
Plans and specifications for the installation of feeder
cables in duct banks constructed under Contracts HH-525
and HH-526 were completed and transmitted to UMTA for
approval on August 23, 1976. The plans and specifications
were approved by UMTA on September 8, 1976. Bids were
received on September 16, 1976. The contract was awarded
on September 28, 1976 to Abbett Electric Corporation,
San Francisco, California, who submitted the low bid of
$238,495. The contract was certified by the City
Controller on October 14, 1976. Construction commenced
on November 8, 1976.
K) J, N, No. 22 and 33 Lines, Underground Power Facilities
(Contract HH-552)"
Plans and specifications for installation of feeder cables
in duct banks constructed under Contracts HH-497 and
HH-527, and in existing duct banks in Carl and Irving
Streets, were transmitted to UMTA for approval on March 2,
1977. Following approval by UMTA, bids were received on
March 31, 1977. The contract was awarded on April 12,
1977 to Amelco Electric, San Francisco, California, who
submitted the low bid of $238,950. The contract was
certified by the City Controller on May 5, 1977. Construc-
tion commenced on May 23, 1977.
L) Folsom and Howard Streets, Eleventh Street to Main Street
Underground Duct System (Contract HH-559)
Plans and specifications for constructing manholes and
underground duct banks in Folsom and Howard Streets
between Eleventh and Main Streets were completed and
transmitted to UMTA for approval on August 23, 1976.
The plans and specifications were approved by UMTA on
- 27 -
I
September 8, 1976. Bids were received on September 16,
1976. The contract was awarded on September 28, 1976
to McGuire § Hester, Oakland, California, who submitted
the low bid of $629,735. The contract was certified by
the City Controller on October 25, 1976. Construction
commenced on November 15, 1976.
M) Haight Street - Stanyan to Gough - Underground Duct
System (Contract HH-560)"
Plans and specifications for constructing manholes and
underground duct banks in Haight Street, between Stanyan
and Gough, were completed and transmitted to UMTA for
approval on February 4, 1977. The plans and specifica-
tions were approved by UMTA on February 25, 1977. Bids
were received on March 10, 1977. The contract was
awarded on March 22, 1977 to Underground Construction
Co., Inc., San Leandro, California, who submitted the
low bid of $329,847. The contract was certified by the
City Controller on April 7, 1977. Construction work
commenced on May 2, 1977.
N) Fillmore, Jackson, Presidio and Other Streets
Underground Duct System (Contract HH-561)
Plans and specifications for constructing manholes and
underground duct banks in Fillmore, Jackson, Presidio and
other streets were completed and transmitted to UMTA for
approval on October 29, 1976. The plans and specifica-
tions were approved by UMTA on November 10, 1976. Bids
were received on December 2, 1976. The contract was
awarded on December 14, 1976 to W. R. Thomason, Inc.,
Martinez, California, who submitted the low bid of
$614,000. The contract was certified by the City
Controller on January 11, 1977. Construction work
commenced on January 31, 1977.
0) Fulton and McAllister Streets - 8th Avenue to Diyisadero
BTreet - Underground Duct System (Contract HH-562)
Plans and specifications for constructing manholes and
underground duct banks in Fulton and McAllister Streets
between 8th Avenue and Divisadero Street were transmitted
to UMTA for approval on April 5, 1977. The plans and
specifications were approved by UMTA on April 19, 1977.
Bids were received on May 12, 1977. The contract was
awarded on May 24, 1977 to Amalgamated Superior
Engineering, Inc., Oakland, California, who submitted
the low bid of $312,275. The contract was certified
by the City Controller on June 10, 1977, and the
Contractor was notified of the starting date of July 5,
1977.
28
P ) Folsom Street - 11th to 16th Streets and 11th St reet
Market to Bryant - Underground Duct System
(Contract HH-T53J
Plans and specifications for constructing manholes and
underground duct banks in Folsom Street between 11th and
16th Streets and in 11th Street between Market and Bryant
were completed and transmitted to UMTA for approval on
September 10, 1976. The plans and specifications were
approved by UMTA on September 28, 1976. Bids were received
on October 14, 1976. The contract was awarded on
October 26, 1976 to Underground Construction Co., Inc.,
San Leandro, California, who submitted the low bid of
$169,075. The contract was certified by the City
Controller on November 17, 1976. Construction work
commenced on December 13, 1976. All work on this contract
was completed in accordance with contract plans and
specifications on April 14, 1977.
Q) Hayes Street - Van Ness to Stanyan - Underground Duct
System (Contract HH-567T
Plans and specifications for constructing manholes and
underground duct banks in Hayes Street between Van Ness
Avenue and Stanyan Street were completed and transmitted
to UMTA for approval on June 2, 1977. The plans and
specifications were approved by UMTA on June 21, 1977.
Bids are scheduled to be received on July 21, 1977.
R) Broad Street and San Jose Avenue, M-Line Track Extension
(Contract~MR-644)
Plans and specifications for the PIP portion of work to
be included in Municipal Railway Contract MR-644, Broad
Street and San Jose Avenue, M-Line Track Extension, were
completed and transmitted to TIP on April 8, 1977. The
work to be included consists of construction of manholes
and underground duct banks in San Jose Avenue and Broad
Street, from Plymouth Avenue to Mt . Vernon Avenue. This
work was formerly part of Contract HH-558. Advertising
by TIP for receipt of bids for this contract is awaiting
approval by UMTA of amendment to System Improvement Program
(SIP).
S) Feeder Undergrounding - Folsom and Howard Streets
(Contract HH-448)"
Work continued on the preparation of plans and specifica-
tions for the installation of feeder cables in underground
duct banks constructed under other contracts.
- 29 -
T) Ocean Avenue - Phelan Avenue to Outer Mission Substation
Underground Power Facilities and" Related Work
"[Contract HH-STSJ
Work commenced on the preparation of plans and specifica-
tions for the installation of feeder cables in duct banks
constructed under DPW Contract 23,727 and Contracts MR-620
and HH-537. Also to be included in this contract will be
the removal of overhead feeders on Ocean Avenue from
Junipero Serra Boulevard to Mission Street and on San Jose
Avenue between Ocean Avenue and Geneva Substation.
U) Union, Parnassus and Clayton Streets - Underground Duct
System (Contract HH-579)
V) Bryant, 16th, Mission, South Van Ness and Other Streets
Underground Duct System (Contract HH-580)
W) California Street - Parker to 32nd Avenue and 8th Avenue
California to Fulton - Underground Duct Systeln
(Contract HH-581J"
X) San Jose Avenue - Mt . Vernon Avenue to Metro Center
FFLine Track Extension (Future Municipal Railway Contract)
Work commenced on the preparation of plans and specifica-
tions for constructing manholes and underground duct banks.
Feeder cables will be installed in these duct banks under
later contracts.
Y) Other Work
Preliminary engineering and plans and specifications are
proceeding for duct lines and feeder undergrounding in
accordance with the requirements of the Program.
Z) Manhole Frames and Covers (Third Contract)
Bids were received on July 16, 1976 for purchasing an
additional 200 sets of manhole frames and covers for use
on future Power Improvement Program contracts. The contract
was awarded to Neenah Foundry Company, Neenah, Wisconsin,
who submitted the low bid of $68,000. Delivery of the
frames and covers was completed on February 28, 1977.
Transit Preferential Street Program: Mission Street and
Fourth Street, Muni Passenger Platforms and Muni Power
Facilities (DPW Contract 23,834)
Advertising of Department of Public Works (DPW) Contract
No. 23,834, Transit Preferential Street Program: Mission
30
Street, Beale to South Van Ness Avenue; and Fourth Street,
Market to Townsend, which includes the relocation of trolley
coach overhead facilities, is awaiting scheduling by the
Department of Public Works.
Miscellaneous
A) Coordination meetings of the joint staffs of Transit
Improvement Program and the Power Improvement Program
were held.
B) Coordination meetings were held between Hetch Hetchy staff
and the Consultants on the electrification, substation and
control and communication projects.
31
BUREAU OF LIGHT, HEAT AND POWER
STREET LIGHTING
General
The lighting of public streets within the City of San Francisco
is provided by facilities which are, on a City-wide basis, 44.0
percent owned by the City; 54.2 percent owned by the Pacific Gas
and Electric Company; and a small percentage, 1.8 percent, jointly
owned. In the underground areas, where the economic advantage of
City ownership is greatest, 82.4 percent of the lights are City-
owned. Five years ago, the corresponding figure was 78.3 percent.
In fiscal year 1933-34, the cost for street lighting was $1.25 per
capita; last year, with approximately thirty times as much light
on the streets and public thoroughfares , the cost per capita was
approximately $2.18.
Maintenance and repair of City-owned installations was performed
under two contracts. One provided for group replacement of lamps
in accordance with schedules developed by the Bureau. A second
contract covered work required for repair of damages and defective
equipment, painting and miscellaneous maintenance.
Under contract, the
and Electric Company
street lighting serv
rected, including th
ing , maintenance and
of Company-owned fac
Certain services wer
also for City-owned
including switching
replacement of indiv
and globes, and emer
required during othe
mal working hours.
Pacific Gas
furnished
ice as di-
e furnish-
operation
ilities .
e provided
facilities ,
and control,
idual lamps
gency work
r than nor-
Electric energy for all City
and Company-owned streetlight
operation was supplied by the
Hetch Hetchy power system.
NEW STREETLIGHTS ON
BOSWORTH STREET
32 -
BUREAU OF LIGHT, HEAT 8. POWER
REVENUES AND EXPENDITURES
FISCAL YEAR 1976-1977
33 -
Engineering
The Bureau reviews, recommends changes, approvals or rejections
of, and correlates all street lighting installations, including
that done by the Department of Public Works, the Pacific Gas and
Electric Company, the State of California, subdividers, etc.
During the fiscal year 1976-77, 14 street lighting contracts,
involving a total of 664 new streetlights, were approved by the
Public Utilities Commission. Plans were submitted for approval
. only after careful checking to determine that illumination will
exceed the minimum requirements established by the American
National Standards Institute; and that all materials used, and
manner of installation, meet with the applicable local, state and
federal rules, regulations and statutes governing the installation
of electrical works.
Operation and Maintenance
As of June 30, 1977, a total of 37,446 City-owned and Company-
owned streetlights were in service to the public streets, parks,
viaducts, overcrossings , tunnels and underpasses. A summary of
the number and type of units in service, at the end of the fiscal
year, is shown in Appendix Table 14.
A total of $1,524,286 was expended for operation, maintenance,
and repair of the street lighting system. Of the total cost,
$18,773 was paid by the State for its share of the operation and
maintenance of street lighting at intersections on City streets,
which are part of the State Highway system.
During the fiscal year, there were 127 accidents involving damage
to City-owned street lighting property. Investigation was made,
as soon as possible, to remove hazards to the public and obstruc-
tions to traffic. Total cost of repairs to damaged City-owned
street lighting property was $104,000. Every effort was made to
secure reimbursement for damages incurred from responsible parties.
Previous experience indicates that more than half of the repair
costs will be recovered.
Complaints
During the year, 40 complaints requiring field investigation were
received and acted upon. These complaints concerned inadequate
illumination, objectionable glare in windows, and requests for
temporary and permanent relocation of street lighting poles.
Improvements
During the fiscal year 1976-77, a total of 691 new City-owned
streetlights were placed in service at a cost of $1,184,878.
Improvements were financed by State Gasoline Tax and the 1964
and 1972 Street Lighting Bond Issue as indicated in Appendix
Tables 16 and 17.
34 -
Engineering
The Bureau reviews, recommends changes, approvals or rejections
of, and correlates all street lighting installations, including
that done by the Department of Public Works, the Pacific Gas and
Electric Company, the State of California, subdividers, etc.
During the fiscal year 1976-77, 14 street lighting contracts,
involving a total of 664 new streetlights, were approved by the
Public Utilities Commission. Plans were submitted for approval
, only after careful checking to determine that illumination will
exceed the minimum requirements established by the American
National Standards Institute; and that all materials used, and
manner of installation, meet with the applicable local, state and
federal rules, regulations and statutes governing the installation
of electrical works.
Operation and Maintenance
As of June 30, 1977, a total of 37,446 City-owned and Company-
owned streetlights were in service to the public streets, parks,
viaducts, overcrossings , tunnels and underpasses. A summary of
the number and type of units in service, at the end of the fiscal
year, is shown in Appendix Table 14.
A total of $1,524,286 was expended for operation, maintenance,
and repair of the street lighting system. Of the total cost,
$18,773 was paid by the State for its share of the operation and
maintenance of street lighting at intersections on City streets,
which are part of the State Highway system.
During the fiscal year, there were 127 accidents involving damage
to City-owned street lighting property. Investigation was made,
as soon as possible, to remove hazards to the public and obstruc-
tions to traffic. Total cost of repairs to damaged City-owned
street lighting property was $104,000. Every effort was made to
secure reimbursement for damages incurred from responsible parties.
Previous experience indicates that more than half of the repair
costs will be recovered.
Complaints
During the year, 40 complaints requiring field investigation were
received and acted upon. These complaints concerned inadequate
illumination, objectionable glare in windows, and requests for
temporary and permanent relocation of street lighting poles.
Improvements
During the fiscal year 1976-77, a total of 691 new City-owned
streetlights were placed in service at a cost of $1,184,878.
Improvements were financed by State Gasoline Tax and the 1964
and 1972 Street Lighting Bond Issue as indicated in Appendix
Tables 16 and 17.
- 34
UTILITY SERVICES TO MUNICIPAL DEPARTMENTS
General
Electric energy supplied to municipal departments is generated on
the Hetch Hetchy power system and delivered to various service
points by transmission and distribution facilities of Pacific Gas
and Electric Company under a wheeling contract. Natural gas
supplied to municipal departments is furnished by the Pacific Gas
and Electric Company under a service contract.
Municipal Consumption of Electricity and Gas
During the fiscal year, 496,305,458 kilowatthours of electrical
energy were consumed through 1,072 municipal accounts at an
expenditure of $6,966,586. Of the above, 152,161,432 kilowatt-
hours of energy were supplied to the San Francisco International
Airport for resale to tenants. Natural gas consumption was
17,174,388 therms through 560 accounts at a cost of $3,321,758.
There were several increases in gas rates last year which
increased the cost to municipal accounts by approximately
$629,868. The average cost per therm increased by approximately
28 percent.
A summary of consumption and expenditures for these commodities
is shown in Tables 12 and 13.
- 35 -
HOWARD P. GRANT
J~L
fin
fUl
UU UU
VJOS
JACK O'ROURKE
JOE F. DE GRACA
EVERETT M. HINTZE $ KEVIN R. WALSH
36 -
APPENDIX
HETCH HETCHY RESERVOIR
Hetch Hetchy Reservoir, which provides a water supply for almost
2,000,000 people in the Bay Area, is shown here at its lowest
point during the drought... at 6.8 percent of capacity.
- 37 -
CONTENTS OF APPENDIX
Table 1 Summary of Receipts, Expenditures and Taxes
Table 2 Comparison of Budgeted and Actual Expenditures
Table 3 Motive Power Section - Substations
Table 4 TRANSIT POWER DIVISION - Comparison of Budgeted and
Actual Expenditures
Table 5 Construction Contracts
Table 6 Precipitation, Runoff, Storage and Delivery
Table 7 Electric Energy Generated, Purchased, and Distributed
Table 8 Comparative Electric Energy Sales to Customers
Table 9 Comparative Gross Revenue Received From Sale of
Electric Energy
Table 10 Electric Energy Generated, Purchased, and Distributed
By Fiscal Years
Table 11 Comparison of Budgeted and Actual Expenditures and
Receipts
Table 12 Expenditure for Electricity for Municipal Purposes
Table 13 Expenditure for Gas for Municipal Purposes
Table 14 Streetlights in Service
Table 15 Expenditures for Operation and Maintenance of
Street Lighting
Table 16 New City-Owned Street Lighting Installations
Table 17 Historical Cost of City-Owned Street Lighting
Improvements
- 38
TABLE 1
HETCH HETCHY WATER AND POWER
SUMMARY OF RECEIPTS, EXPENDITURES AND TAXES
FISCAL YEAR 1976-77
RECEIPTS
Revenue from Sale of Electrical
Energy
Revenue from Sale of Water
and Standby Charge, SFWD
Other Revenue
Total Revenue
EXPENDITURES
Total Expenditures
TAXES
Tax Levying Entity
Alameda County
San Joaquin County
San Mateo County
Stanislaus County
Tuolumne County
Banta-Carbona Irrigation Dist.
Oakdale Irrigation Dist.
West Stanislaus Irrigation Dist.
Total
Budget
Actual
$ 40,933,000 $ 43,341,973
-Under, Over
$ 2,408,973
8,000
000
8,000,000
100
000
124,451
$ 24,451
$ 49,033
000
$
51,466^424
$ 2,433,424
$ 56,670
,959
$
55,970,922
$ -700,037
Total Amount
No. of B
Llls
Assessed Values
$ 2,450.00
of Taxes
10
$ 292.76
12
45,375.00
4,481.18
16
3,900.00
361.36
79
124,310.00
12,602.74
42
6,105,311.00
559,936.46
1
3,642.28
156.62
4
25,897.00
535.94
1
4,250.00
153.00
165
•
$
6,315,135.28
$ 578,520.06
- 39
OE
TABLE 2
HETCH HETCHY WATER AND POWER*
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES (INCLUDING ENCUMBRANCES)
FISCAL YEAR 1976-77
DESCRIPTION
110 Permanent Salaries
110-1 Permanent Salaries - Crafts
111 Overtime
11-1 Overtime - Crafts
112 Holiday Pay
112-1 Holiday Pay - Crafts
113 Extended Workweek
113-1 Extended Workweek - Crafts
120 Temporary Salaries
120-1 Temporary Salaries - Crafts
139 Permanent Salaries - Gardeners
200 Contractual Services
216 Maint. and Repair of Auto Equipment
231-1 Purchase of Power for Resale
231-2 Service Charge for Transm. and Dist.
251 Subsistence of Employees
300 Materials and Supplies
640 Water Rights and Damage Claims
641 Hydrography
801 Accident Compensation
804 Claims
812 Fidelity Insurance
813 Automobile Insurance
814 Fire Insurance
815 Miscellaneous Insurance
853 Assessments
854 Membership Dues
855 Watershed Protection
855 Fee to U.S. Gov't - Raker Act
856 Maint. of Roads - Raker Act
860 Retirement Allowances
862 Social Security
865 Health Service System
870 Taxes
880 Rental - Transm. Lines and Offices
900 Services of Other Departments
TOTAL OPERATION AND MAINTENANCE
400 Equipment
500 Additions and Betterments
700 Reconstruction and Replacement
830 Bond Interest and Redemption
TOTAL
* Does not include Transit Power Division - Table 4 or Bureau of Light,
Heat and Power - Table 11.
BUDGET
ACTUAL
-UNDER, OVER
$ 823,518
$ 785,429
$ -38,089
1,219,893
1,087,895
-131,998
15,000
10,804
-4,196
121,539
73,888
-47,651
2,200
2,181
-19
2,282
2,282
-
3,869
3,439
-430
10,460
13,603
3,143
55,000
30,441
-24,559
192,000
143,217
-48,783
54,653
54,653
-
101,745
94,218
-7,527
10,209
8,422
-1,787
34,007,000
33,921,500
-85,500
2,515,000
2,568,255
53,255
4,000
1,944
-2,056
192,202
232,597
40,395
5,000
944
-4,056
49,800
47,909
-1,891
45,335
45,335
-
500
4,420
3,920
82
82
-
10,599
10,599
-
8,297
26,439
18,142
39,007
39,007
-
51,091
51,091
-
300
366
66
20,000
20,000
-
30,000
30,000
-
15,000
15,000
-
589,119
437,612
-151,507
140,037
135,831
-4,206
77,872
71,665
-6,207
578,520
578,520
-
116,400
114,733
-1,667
982,047
969,176
-12,871
$42,089,576
$41,633,497
-456,079
106,825
104,850
-1,975
221,000
221,000
-
1,978,035
1,978,035
-
8,603,660
8,603,660
$52,541,042
-
$52,999,096
-458,054
- 40
x
to <u
•H X
X 4J
0) >
>
c o
o o
>.
s
O X)
u
o
0) CU
3
o
Xi 3
0
•H
s
M
rH
xi m
<u
•H
Q) rH
£
CO
•H
ii
II
CO CO
a. -h
Z
o
M
(1)
<
5 N
5 -H
z
H
c/>
o
to
M
PQ
to
3>
M
C/>
>
M
1
ro
a
<4-l
!S
O CO
W
ei
O
4J
►J
M
• -H
P2
H
o c
<
o
O
S3 33
H
H
W
to
M
0*
co
g
o
■a
PL|
CD
H
rH
w
CU rH
>
4-1 CO
M
CO 4J
H
O CO
Q
C
£
rH
o o
o o
m in
o
O
O
o
rH <T
rH i-H
**
H
rH
rH
rH
CM CM
CN CN
CN
on
ON
ON
ON
ON ON
ON ON
ON
XX XX
>
CU
T3
CO
H
C
>
CO
u
cfl
o
O
O
O
CO
C
CO
X
o
o
4-1
u
X
rH
CU
o
o
cfl
c
X)
sf
-3-
r4
CO
CO
4-1
3
ai
3
4J
c
CU
cfl
3
O
•H
0)
X
a)
c
c
CO
4-1
3
O
o
&
OJ
o
I
)-l
M
s
4J
n
xi
Cu -H
60
o
a
3
*->
d
<u
0)
CO
•H
o
>,
rH
X
1-4
X
CN
rH
£
CO
XI
CO
4-1
(U
•H
CO
cfl
ii
II
01
>.»*H
13
a
u
•H
o
•H
u
4J
4J
1
u
>
CO
O
Cfl
£
C/j
M
CU
CO
o
o
CU
U
a
XI
CU
rH
4J
4-1
o
rH
s
O
T3
o
Cfl
r^
r-~-
ai
c
Hi
•H
4-1
r~^
r-.
e
■o
rH
CO
ON
ON
Cu
CU
0)
•H
C
rH
rH
■H
3
U
CO
a)
3
CO
C
•H
>>
w
4J
4-)
M
rH
cfl
o
0)
rH
c
X
a
XI
Cfl
o
■U
o
3
■H
CU
e
•H
CO
CO
r4
00
u
4-»
cd
X
•H
CU
■H
4J
M
>
3
r>*
•H
O
C
3
<u
&
Pi
Pi
O
X
(U
en
C/D
o
CO
CU
4-1
4-1
U
CU
11H
4J
cu
CU
s
o
cO
co
e
o
3
O.
CO •
a)
•H
CO
•H
4J rH
c_
XI
O
3
•H CN
>N
3
OJ
cr
3 ON
H
M
X
cu
!=> rH
41 -
TABLE 4
HETCH HETCHY WATER AND POWER
TRANSIT POWER DIVISION
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES
(INCLUDING ENCUMBRANCES)
FISCAL YEAR 1976-77
-UNDER
OE DESCRIPTION
110 Permanent Salaries
110-1 Permanent Salaries - Crafts
111-1 Overtime - Crafts
112-1 Holiday Pay - Crafts
113-1 Extended Work Week - Crafts
120-1 Temporary Salaries - Crafts
200 Contractual Services
300 Materials and Supplies
800 Accident Compensation
860 Retirement Allowances
862 Social Security
865 Health Service System
900 Services of Other Departments
TOTAL OPERATION AND MAINTENANCE
400 Equipment
700 Reconstruction and Replacements
TOTAL
BUDGET
ACTUAL
OVER
$
68,425
840,522
91,398
8,851
43,080
8,000
10,626
57,798
20,665
266,830
48,672
28,708
175,113
$
34,548
750,385
99,651
8,718
25,943
9,071
4,092
27,118
20,665
199,471
47,205
26,425
173,413
$
-33,877
-90,137
8,253
-133
-17,137
1,071
-6,534
-30,680
-67,359
-1,467
-2,283
-1,700
$
1,668,688
3,175
2,000,000
$
1
2
,426,705
3,175
,000,000
$
-241,983
$
3,671,863
$
3
,429^880
$
-241,983
- 42 -
60 4-1 i-t
•H 3
l-l O P-,
o o
*
8
a
to
P*
H
r^
O
r>
B
g
i
SO
H
r-^
fa
Oi
<X.
O
H
H
CJ
<
S3
S)
s
o
W
M
>-
>J
H
5c
O
►J
u
3>
<
H
Pi
u
w
H
co
3=
CO
H
S3
ft.
X
O
U
CJ
H
M
s
C
w
CO
O
•H
u
>>
fed
CO
a
k
o •
ai
J3 a
u •
« s
CO o
S M
Ph u
o -a
c
4J
s-i C
CO
CO
H to
>
CJ
<
M
•u co
4-1
C >.
X.
CO
•H co
4J
-, e
t0 .-I
vO
CO ci)
P-. P-.
-3"
4-1 4-1
5 CO
x> n)
XI
a; >.
3 pJ
3
CJ CO
n)
CO
•H
•*
> 4J
M 3
CO
o
-H O
4J
4-i
O 3
CO 4J
CJ
CO
W P
D. y-\
01
<u
CO 3
M
M
CO XI
Pi fc
4J
4-1
3 C
to
CO
C 3
co o s
o o
CO CO -H
i-H CO CO
an si
«) o n
PS Pu S
co o
i-H > l-l
CO < 60
> M
CO J2 CO
H4J-D
CO O C
HN5
•H S
■H X)
O CO
CO 4-1
En CO
i-H
l-l CO
a) pi
0 X)
PL4 3
CO
4->
•H 60
CO 3
C -H
CO 4J
l-i XI
H 60
•H
1 .J
4-1
S4 CO
4-1 M
CO O
O Pi
l-i O
4-> X
O 3
0) P
CO 3
S O
O iH 3
l-i CO CO
3 4-10
,3 co a.
C_> 3 i-t
M 3
CO CO
4-> 3
3 O
X) XI
3 3
B 4-1
CO CO
4J U
CO CO
>. p.
CO o
3 CO
•H >
iJ 3
co o
s
H 3
co co
4J S3
1
i
i
1
1
1
1
1
3
BC
S3
EC
ffi
S3
PC
S3
EC
O
rs
S
tc
S3
s
33
BC
EC
43
M 60 M
o 3 co
a -H <U
M >m
<4-i 3
O O rH
co
0) 01 o
3 3 CO
rH O -H
rH
4-1
cfl
o
c
03
11
■H
r.
o
00
4-1
•H
•H
c
M
M
o
Pm
O
u
OJ 3
Ed M
a
o «
x •
w o
£ o
4-1
3
OJ
T3
o
at
-o
c
CO
•H
u
c
CO
c
•u
4-1
3
o
60
4-1
3
o
CJ
cO
o
4-1
3
w
o
X
4-1
•H
rH
3
U
•H
4J
•H
<V
J-i
4J
U
4->
rH
U
4J
•H
4-1
CO
4-1
T3
4-1
u
o
ao
00
3
cd
CO
4J
3
IH
CO
a)
in
CD
3
X
o
n
n
rH
Q
4J
4-1
CO
0)
•H
4-1
S
o
^
CO
cfl
60
s
0)
0)
CO
CO
3
E
rl
00
U-l
rl
u
•H
i-H
Jm
•3
-o
T3
X
c
O
O-
4-1
O
4-1
rl
hJ
rH
rl rl
(0
q
X
C
3
M
o
•H
CJ
CO
s
3
rs
CO
•H
•H
CD O
c
CO
S
O
3
co
3
CD
,*
CD
O
TJ
Cfl
4-1
Pm
& S
o
•H
rl
O
T3
cr
i-H
OJ
4-1
•H
3
60
4-1
P.
CD
o
•H
>
3
U
XI
C
c
w
W
u
CO
CO
cfl
3
CD
QJ
CD
"3
Pm "3
4-1
•H
4J
XI
00
CO
CO
o
3
>>
rl
•H
#,
cd
U
3
01
a
O
QJ
U
J-l
"3
•H
<-{
>, W
co
QJ
3
4-1
U
4J
cfl
73 4-1
H
QJ
0)
3
CO
4-)
rH
CO
>
O
X
cfl
CO
3 cfl
(-4
■
H
•»
T3
•-)
oo
CO
CO
5
o
T3
3
•H
00
s
4-1
rl
3 rH
O
4J
4-1
ai
a
c
4-1
4J
X
4J
CO
O
4-1
•H
QJ
•a
CD
O OJ
W
OJ
00
rl
o
T)
•H
CO
CO
3
CD
CJ
cfl
rJ
QJ
3
4-1
U Pm
QJ
01
O
s
-a
X
3
CO
3
X
U
OJ
rl
cfl
co
60
Q
H
X
B
CO
i-H
3
rH
O
rl
QJ
4-1
3
4J
•H
rl X)
4-1
4-1
rH
co
•H
CO
4J
•rl
CD
CD
O,
CD
3
en
>>
rH
CD 3
CO
)-l
rH
4-1
cfl
3
•3
01
4J
>
3
o
CD
CD
CD
rH
X) CO
o
e
•H
0)
-a
m
4-1
3
CD
CJ
O
C
U
>
4-1
<-\
<c
3
rl
3
QJ
fn
0)
3
CD
CO
rl
3
QJ
X
4-1
<
c
rH
o
I3> CO
a)
C
4-1
)-!
o
4-1
4-1
CD
4-1
3
rl
>
o. co
•H
o
s
OJ
4J
OJ
CO
4-1
ec
o
3
rl
00
CO
•"3
CO
<
cO
CO
o
rl
« iH
(0
>
^
>S CO
3
OJ
4-)
3
CJ
>H
•3
CO
Pm
H
CO 4-1
•H
cfl
CO
M
e
CO
P
a
CO
•H
4-1
0)
4-1
rH
60
OJ
CD
n
4J -H
■-H
0)
3
W
QJ
c
4-1
ex
T3
01
CJ
CD
cfl
o
4-1
S3
X
4-1 CO
CD
QJ rH
i-t
►J
4-1
X
CD
4-1
3
CO
iH
i-H
rH
^
O
CD
4-1
4-1
CO
4-1
3 QJ
4-1
QJ iH
<
CJ
X
X
CO
00
C
3
M
•H
rl
X
U
rl
s
rH
3
rl
•H r-i
4-J
rl CJ
a
o
3
CO
4-1
>,
cO
o
cr
CO
3
CO
3
4J
O
Cfl
CD
CO
o
CO O
3
4-1 CO
s
4-1
Q
<
O
00
hJ
u
w
CJ
M
s
P
co
PL,
P4
Pi
>
2
Pm Pm
CO
CO Ph
4-1 53
1
1
1
1
1
i
3
»
EC
g
s
tc
cc
O
Sm
S3
5C
s
s
su
44
M
U
Ml
M
0
c
id
:*
•H
(i
1-1
►«
4-1
3
O
a
en
01
0)
u
3
c
Ul
H
Q
•H
cfl
CJ
u.
>
i-H
ij
to
CJ
C
m
81
•H
u
U
Oil
i~>
-rH
•H
c
u
H
o
(X
o
U
•H 0
<J
■n
c
Hi
0
u
u
u
d
4-1
to
? u
o
o
OS
ri 00
PQ 3
c
01
iH
M
u
.* 4->
01
•H
c c
4J
>
co -h
co
1-1
Vj CO
0)
CJ
fe Ph
S
CO
co u
o
•H •
Ol 3
4-1
O O
3 w
co
C
o c
0
•H M
1-3 a)
o
Q
1 >
u
s
j3 co
ca 4->
(X C
rH C
US
oj o
O, tH
o
to co
cd o
s
o
W ^
r-3
M
i-) «e
>1
CU I
c
o
3
2 I
*3
3
rH 4-1
>%
4-1 4-1
4-1 4J
4-1
to
CJ 01
J3
>,
O C
O 3
4->
8
CO
Ol 01
c
a
iH
3 CU
3 ,u
rH
CJ
CU
0)
CO
4J U
•H
4J
M
U 0
H 0
i-H
3
0
3
0)
tn 4J
CO
a)
tO
4J O.
4J O.
CO
&
P.
iH
•H
co
D
PC
w
CO -H
CO iH
4-1
4-1
•H
rJ
4-1
4J
u cu
C 3
3 3
co
CO
3
•H
3 3
CJ 3
x;
T3
o c
o cr
C
3
cr
ro
rH
•H O
O -H
rj
c
u w
u w
M
O
w
p">
•H
CO iH
S hJ
4J
CO
o
CJ
Cm co
CU
•>rH
-rH
rH
ca
CO
« c
S3
c
C -H
C rH
3
I-H
O
Fn
TJ iH
co o
•H
O CO
O cfl
o
3
CO
53
3 S
U -H
>4-4
CO
•H 4J
•H 4-1
iH
o
4-1
H
3
cu co
o
to
4J CO
4J CO
4-1
•H
CO
"3
cj
3
Se co
o
CJ
CO C
CO 3
CO
4-J
3
3
s
H O
O >H
M
CJ
4J M
4J M
4-1
CO
M
cO
o
•H
H 0
01
o
CO
(0
co
4->
Cm
3 CO
co
OS
S
XI "3
J3 13
x»
CO
•3
CN
^J
a. 3
rH 3
3 C
3 3
3
X3
3
CM
TJ
VJ
CU rH
Ol CO
TJ
co co
CO CO
CA
3
CO
C
0
os o
0) t-i
s
to
4->
CO
3
2
CM
4J H
CO
60
01 00
j3 00
<U
3
00
O
O
CO
c
r< B
CU c
CO
a)
rH
3
53
M
-a
3 >>
^
H
■H
<u
O -H
rH iH
o
0
CO
•H
oo
01
O 3
4-> H
•H
T3
^
0 T3
o *o
•->
Cu
>
*3
m
u
CO rH
3 CO
CO
rH
CO
r-l rH
*3 rH
•H
CO
rH
s
CJ
to
rH rH
•H &
CXt-I
4-1
rH -H
3 -H
3
3
U
•H
T3
rH
D. O
CO Q)
0)
3
a
•H 3
CO 3
CO
a*
cfl
3
C
CJ
(U 1-4
Ph z
OS
pa
M
tn PQ
OS «
CO
W
H
CQ
*-}
3
OS
OS H
4J O
3 S3
O
1
IB
i
SB
1
S3
1
33
1
33
1
33
33
re
S3
S3
S3
33
33
33
45 -
U
60
M
o
q
«
t*
fl
0)
^
>h
u-i
a
o
n
0)
0)
u
3
c
w
H
o
•H
od
UJ
1*1
>
H
4J
nj
U
P
CO
V
•H
>-i
u
60
■u
•^
■H
C
U
M
o
Pw
O
u
u
c
T3 O
C -H
3 W
O O
H 3
00 U
U 4-1
0) (0
•O C
C O
•o o
C -H
3 4J
0 O
H 3
60 )-i
M 4->
01 CO
"O C
C O
J=
■H
60
n
5
3
M
•H
O
QJ
c
4J
E
T)
u
3
0)
o
u
a
to
M
4J T3
c c
qj 3
> O
<u u
60
3
>> to
c >»
n) CO
4-1
C/3 4-1
T3 4J
C O
rt 3
O
c c
C
(0
•o >,
c u
<d pq
to CO
J= Jj >,
4-» S W
•H T3
3 C
pa ca
o pq
3
'H VI
4-1 0)
CO x>
C B
O -H
U H
oi co
*-> c
to o
4-1 U 0)
cd c
PC P
H X 10
•H 4J ^
fa-. O CO
x) a. oi
c <u >
CO pci -H
CO
)-i
4-> O
C 55
46
a
H
<
w
fa
►I
&!
w
P3
o
J
CO
1
<
u
\D
«
o
oo
a
H
H
^
H
W
fa
J
<
3
3
fa*
PQ
H
>-
fa
5
C
O
§
co
W
fa
M
X
„
§
5
o
n
H
l-l
fa
W
H
c
pa
<
H
M
53
fa
M
U
S
fa
co ^
cm <y>
CM CN
co u->
O B^
r-» m
co o
o\ co
r*. s^
r-» co
^
0> u-i
m vo
C\ O
CM
r-» en
rH O
o
«> rH
in vo
H
o «a-
m
co .*
oo sr
CM
r-» •*
CM
rH
00 <3\
r^
r» cm
8-5
en m
m
CM CT\
o
O r»»
co
o
<r vo
iH
vO -*
o
CO «*
CM CM
m
r-» <■
iH
O I
U-I O
tu
>. o
.C H
OT) tl
« >* fa
01 o
PC iH •
►J x
J= o
U 01 h
4-1 ^ fa
0) (0 fa
K J <
wo c
4J >-. tj
0) m
CO CO
-1 rJ
\o c^ c^
r-» co o
m ^ m
CO
a
1
o
z
§
o
U-I
<
o
s-'
«j
w
c
y
cu
u
pi
u
o
01
H
fa
00
.
as
X
M
o
o
Vj
>
fa
fa
CO
o>
CO
vO
o
CM
0>
cr.
00
r--
cr\
vO
«N
ro
CM
co
CM
O 00 vO
VO vO N
CO CM
vO CM vO
CO r-» rH
Is* oo o
cm r» r»
VO rH CM
CO CM
rH
>
rH
■u
O O o
■H
•H
vO O O
fa
CI
f 00 H
00
CO
fa
OCOh
0
CO
O vO CM
2:
U
CO CM
CM O
co m
m oo
in \o
oo m
m co
ShJ
CO
>*
Ml
• r»
C O
C
o «
0
•h m
•H
00
rH
w
rH
•H ••
•H
g «*
6
6 co
O en
CO
U rH
rH
>> c
00 -H
s»
u
<-i
0) c
<D
c «
4J
w to
CO
0)
i
U .O
•H
•H
X
e *j
0
o o
H
4J 3
fa< -o
fa
0)
CO
• 3
r4
W.$
o
P3
>>
co
- JS
C
01 u
0
4J 4J
rH
•H 0)
rH
W PP
CO
DO
0) J2
u u
o
O 4J
o
S 01
<J\
U PP
01
m
> <«
CO 4-1
3 >> CO
C H rJ
01 OJ 0>
> fa
4-1 -H O
O rH
O 01 o>
M
IH "O O
cfl
1 c
01
oi en -h
J^
rJ oi co
O -a
rH
CO 3 rH
>< >.
CO
rH CO
CO (0
O
01 CJ 4J
TJ T3
CO
CCO
O M H
•H
rW IH
■H
0) 0>
fa fa
H
O
CO .a cj
<U E
UH
00 3
CO e
rH
U -H
CO
01 X
u
co
> CO
o
W
< a
H
H
47 -
TABLE 7
HETCH HETCHY POWER SYSTEM
ELECTRIC ENERGY GENERATED, PURCHASED, AND DISTRIBUTED
PLANT DATA
FI!
SCAL YEAR 1976-77
Nameplate Rating
(Kilowatts)
Capability
(Kilowatts)
104,000
150,000
85,000
339,000
Annual Plant
Factor - %
Moccasin Powerhouse
Dion R. Holm Powerhouse
Robert C. Kirkwood Powerhouse
Total
90,000
135,000
67,500
292,500
41.9
11.5
41.3
ENERGY GENERATED AND PURCHASED (KILOWATT-HOURS)
Gross Generation
Moccasin Powerhouse
Dion R. Holm Powerhouse
Robert C. Kirkwood Powerhouse
Station Service
Moccasin Powerhouse
Dion R. Holm Powerhouse
Robert C. Kirkwood Powerhouse
Net Generation
Supplementary Energy
"Bank" Withdrawal*
Purchase (PGandE)
Total
ENERGY DISTRIBUTED (KILOWATT-HOURS)
Sales
Municipal Accounts
Modesto Irrigation District
Turlock Irrigation District
Kaiser Cement and Gypsum Corp.
Kaiser Aluminum and Chemical Corp.
Norris Industries, Inc.
Lockheed Missiles and Space Co. Inc.
General Motors Corporation
IBM Corporation
Liquid Air, Inc.
Miscellaneous Customers
Non-Revenue
Project Use
"Bank" Deposit*
Losses
Hetch Hetchy System
PGandE System (Municipal Accounts)
Total
330,510,000
135,416,000
244,076,000
853,800
499,290
451,590
0
1,468,919,029
499,833,145
1,013,509,726
591,956,719
0
0
2,058,278
0
0
0
0
824,292
2,965,669
0
36,002,634
29,965,886
710,002,000
1,804,680
708,197,320
1,468,919,029
2,177,116,349
2,108,182,160
2,965,669
65,968,520
2,177,116,349
* In accordance with letter-agreement between City and PGandE dated 6/24/75
- 48 -
TABLE 8
HETCH HETCHY POWER SYSTEM
COMPARATIVE ELECTRIC ENERGY SALES TO CUSTOMERS
FISCAL YEARS 1975-76 AND 1976-77
(Nearest 100,000 Kilowatthours)
CUSTOMER
1975-76
1976-77
Municipal Accounts
International Airport
Municipal Railway
Public Works
Street Lighting
Unified School District
Water Department
Other City Departments
Modesto Irrigation District
Turlock Irrigation District
Kaiser Cement and Gypsum Corp.
Kaiser Aluminum and Chemical Corp.
Norris Industries, Inc.
Lockheed Missiles & Space Co., Inc ,
General Motors Corporation
IBM Corporation
Liquid Air, Inc.
Miscellaneous Customers
189,200,000
56,900,000
26,800,000
46,400,000
39,700,000
48,400,000
82,800,000
865,100,000
248,800,000
78,400,000
11,300,000
7,200,000
80,200,000
28,800,000
25,800,000
12,500,000
900.000
195,200,000
62,300,000
26,000,000
46,000,000
39,100,000
44,900,000
86,300,000
1,013,500,000
592,000,000
0
0
2,100,000
0
0
0
0
800,000
TOTAL
1,849,200,000
2,108,200,000
49 -
TABLE 9
HETCH HETCHY POWER SYSTEM
COMPARATIVE GROSS REVENUE RECEIVED FROM SALE OF ELECTRIC ENERGY
FISCAL YEARS 1975-76 AND 1976-77
(Nearest $1,000)
CUSTOMER
1975-76
1976-77
Municipal Accounts
International Airport
Municipal Railway
Public Works
Street Lighting
Unified School District
Water Department
Other City Departments
Modesto Irrigation District
Turlock Irrigation District
Kaiser Cement and Gypsum Corp.
Kaiser Aluminum and Chemical Corp.
Norris Industries, Inc.
Lockheed Missiles & Space Co., Inc.
General Motors Corporation
IBM Corporation
Liquid Air, Inc.
Miscellaneous Customers
2,542,000
649,000
330,000
517,000
553,000
476,000
1,011,000
7,457,000
2,283,000
1,318,000
220,000
164,000
1,454,000
572,000
478,000
190,000
10,000
$ 3,081,000
781,000
359,000
559,000
612,000
509,000
1,126,000
20,982,000*
12,484,000*
124,000
35,000
32,000*
134,000
37,000
60,000
17,000
10,000
TOTAL
$ 20,224,000
$ 40,942,000
* Indicates amount as paid by customer
- 50 -
1 1
CJ
>J
r^
<*
o
10
S
m
CM
0
0>
^L
cn
•»
cn
CM
CO
«3
m
~-t
CM
U U tN
o
o
o
o
m
m
cn
OnI
00
00
O
0>
00
l-<
r~
c-n
rM
0*
in
CM
m
m
CM
<r
to
in
O
i-4
C-J
CM
rn
in
CM
>*
CM
m
on
ic
r^-
en
<r
CM
CO ON O <J-
como-J
co vd O r-~
ro <t
f-~
r-4
o
l»»
O O
r-i
u-i
00
10
CM r-l
CO
cn
CM
1-1
o m co co
C^ vD <f N
-J CO N
CO 00 o o ^
CO CO
in r^ o o m
NO r-M
O- r»« vo cm co
on m
r-» r^ i— i r-~ o
r-» co
n n vO -Cf N
r-. i^
H CO MA 0\
cm r-»
o co m cm
CO CM
00 CM CM .-4
O
o
i0
cn
m
o
r^
I"*
<t
o>
O
o
LO
o
C-.
<st
03
0
moo
on o o
oo o o
o o r-» m o
m
O
O
oo
r~-
LO
r-~
30
rsi
CO
ro
ON
CM
CO
i— i
vO
"*
nO
r-M O- ON CO 00 —I
CO CO r-l <t CM CM
<T r>» cm .-<
o
O
CO
rsi
O
o
o
ro
<t
*»
cn
<!■
CO
r^
CTN
o
t >
r^
<t
CO
a>
ro
ON
O
r- 1
CN
m
CM
CO
O
r~.
CO
CM
lO S l~4
O
O
O
O
on
O
nO
CM
<r
CO
r^
30
— i
nC
00
<r
CO
r"»
<t
CO
10
m
—,
rM
m
co
O
-m
ro
00
r>
CM
r>»
m
H
cn
O
<r
<t
^r>
-c-
CO
<*
r^ O O O O vO
On O O O O r-l
no o o o o o
cm cm <t- O O CM
CO ON 00 CM CM O
<f n cn r> n m
C\l t^ N lO H N
co co o in co cm
<f r-~ co •-!
i i i vo i i i cn
i i i in i i i cn
i t i in i i i r»
MD CO
vO O
CM ON
o
O
o
CN
r««
CN
CM
LO
00
10
—J
r^
CO
<r
<t
00
i— i
ft
CM
CO
r-l
<-
m
O
m
nO
10
ON o o o o o
O O O O O M3
on O O O vO r^
on io vf oo i-i in
in r-l CO MS cm CM
cm oo <}■ co m co
CO CO H m H N
O in CM <}• CO CM
in oo <!• <-t
I I I I I i I I r«.
I I I I I I I I Mf
I I I I I I I I CO
vO CO
ON ON
!•»» nO
co m
O CO
o ON
rv
CO
00
o
<f
I— 1
H
<f
m
CO
NO
Mt
vo
00
CM
<f
i-(
CM
o o
o
O co
CO
cm <r
CN
oo in
1 — I
f* r-l
LO
on in
r-l
CO CO
St
CO o
m co
\D
nO
<t
10
CO
«*
<*
O
<T
10
CO
CO
r^
10
CO
<t
a
ON
90
O
c
o
o
o
CM
m
O
CM
o
o
o
CO
NO
O
o
o
O
NO
in
o
i— i
o
r-l
10
CM
10
ON
ON
o
NO
o
ON
i0
CO
CO
<t
i0
r^
a
o
cn
CM
m
i-H
co
cn
r-l
in.
in
o
CO
i i i i i ■ in
r~ vo
oo m
cm r~
ii
a
CO
gg
p
E
0
•
re
O
Sm
CO
3
•H
1-1
OJ
c
O
0
3
CJ
r
O
n
Q
CO
J3
h-l
a
•r-l
-a
e
o
Pm
O. CJ
6
O
0
<u
—
cn
c
C
Po
CO
CD
H
4-1
03
ki
"3
*
4-1
0
0
CJ
<4>
CO
•r-l
rC
D-,
CO
CO
a
cu
O
■— i
fM
1 — 1
x-v i—l
C
•1-1
•r-4
a>
d
u
aj
3
o
3
O
CO
CJ
CO
t: co
3
4-1
4J
■Sj
£
—1
O
d
r-4
e
U
CJ
■);
r;
0
3
4-1
c-
?
■a 4-i
O
ra
ro
)M
.a
a
1-1
CO
0
d
U
Cm
^
O
w
CO
c o
►J
o
CO
DO
4-1
C
4-1
to
CO
rJ
•rJ
H
CO
u
<u
P
•u
S
Sm
CO 4J
<
u
•rM
T-4
d
■r4
CO
0
<
cn
0
CO
0
4J
3
1-1
z
3
£
i-<
JO
u
■a
O J3
H
<
h
n
0
3
d
■u
M
•r-l
4-1
re
O
CD CO
□
G
-H
W
3
X
Cm 3
O
n
iM
£
TJ
H
CO
O
4-1
s
O
)-i
P
QJ
CO O
—
Cm
o
CO
J
4J
n-X CO
H
•z
r-f
M
Cu
r-M
B
•r-l
3
—4
s
O
—4
c
r-l a.
H
<
•^
o
to
CJ
<
r-l
CO
d
•3
Z
•a
a. <
co
CJ
OJ
<C
CI
CJ
H
s
0)
l-l
CU
0
_Ni
0)
u
0
OJ
r-l
u
r-l
3
4J Q
•rJ
2
CO
H
•iM
4-J
O
u
>M
01
r-l
0
Sm
>-.
CU
re
0
-a
r-l
C
CJ
W
CO
nci
u
W
a
3
y
BO
0
OJ
0)
1-1
3
CM
Cm
CJ
rC
u
u
•r-l
0)
OJ
OJ ^
a
re
M
§
^
X.
m
co
■r-l
a
I—l
CO
to
U
O
1-1
^
CJ
3
0
>
■rn d
CJ
c:
cu
c
o
M
a
c
■3
u
•^4
•H
U
)M
-M
M
O
d
g
cr
co
OJ
O CO
e>
U
0
0
>J
-j
)M
Cm
^
3
0
3
ro
re
0
CJ
ro
—4
re
0
OJ
CO
•r-l
T-4
Cm
|M CQ
q
— i
o
Cm
M
3
H
re
ISl
"r;
H
bM
^
z
X
O
<
>
r-I
CJ
M
rJ
Z
1
Pi =
H
S
Q
a!
fe
-
Cm
CO
M
W
c
0
Z
CO
o
z
- 51 -
OE
110
111
112
200
231
231-1
231-2
231-3
231-4
300
400
813
860
862
865
954
TABLE
11
BUREAU OF LIGHT,
HEAT AND POWER
COMPARISON OF BUDGETED AND ACTUAL EXPENDITURES
AND
RECEIPTS
(INCLUDING ENCUMBRANCES)
FISCAL YEAR 1976-77
-UNDER
DESCRIPTION
BUDGET
ACTUAL
+0VER
EXPENDITURES
Permanent Salaries
$ 181,225
$
153,913
$ -27,312
Overtime
538
538
9
Holiday Pay
537
e
-537
Contractual Services
1,284
1,338
+54
Lighting and Heating of Public
Buildings - General
2,372,380
2
,617,266
+244,886
Lighting and Heating of Public
Buildings - Special Fund
7,440,009
7
,130,728
-309,281
Lighting of Public Streets -
Pacific Gas and Electric Co.
695,380
706,554
+11,174
Lighting of Public Streets -
Hetch Hetchy
507,620
540,350
+32,730
Lighting of Public Streets -
Calif. Division of Highways
1,400
1,400
e
Materials and Supplies
500
499
-1
Equipment
1,700
1,507
-193
Auto Insurance
257
257
9
Retirement Allowance
33,408
28,459
-4,949
Social Security
8,205
5,757
-2,448
Health Service System
6,407
4,911
-1,496
EDP - PUC Data Processing
12,000
12,000
9
TOTAL
$11,262,850
$11
,205,477
$ -57,373
RECEIPTS
Interfund Receipts*
$ 8,718,076
$ 8
,389,311
$-328,765
Ad Valorem Taxes
2,544,774
2
,816,166
+271,392
TOTAL
$11,262,850
$11
,205,477
$ -57,373
WORK ORDER APPROPRIATIONS FROM ROAD FUND
-UNDER
DESCRIPTION
TOTAL FUNDS
EXPENDITURE
+OVER
Maintenance and Repair of
Street Lighting Installations
$ 238,372
$
239,667
$ +1,295
* Transfers from other Departments.
52
TABLE 12
BUREAU OF LIGHT, HEAT AND POWER
EXPENDITURE FOR ELECTRICITY FOR MUNICIPAL PURPOSES
FISCAL YEAR 1976-77
DEPARTMENT
Art Commission (a)
Art Museum
Auditorium and Brooks Hall
Child Care Centers
City Demonstration Agency
City Planning
De Young Museum
Disaster Corp.
Electricity
Farmer's Market
Fire
Hassler Health Home
Health
Hetch Hetchy
Hidden Valley Ranch
International Airport (b)
Junior College District
Juvenile Hall
Legion of Honor
Library
Log Cabin Ranch
Municipal Railway
Parking Authority
Police
Public Buildings
Public Works
Purchasing
Real Estate
Recreation and Park
Recreation and Park - Candlestick Park
Recreation and Park - Yacht Harbor
Sheriff
Social Services
Street Lighting Operations (.003)
Unified School District
War Memorial
Water
TOTAL MUNICIPAL DEPARTMENTS
Academy of Sciences
State of California:
Street Lighting
Traffic Devices
GRAND TOTAL FROM HETCH HETCHY
NO. OF
CONSUMPTION
ACCOUNTS
KILOWATT-HOUR
EXPENDITURES
3
38,320
792
2
1,248,640
15,938
1
4,917,000
66,933
12
268,067
5,391
1
170,720
2,925
1
80,660
1,440
1
3,059,200
36,573
1
117
1,711
5
844,218
11,051
1
25,706
520
59
2,993,742
54,644
1
133,000
2,375
A3
29,520,323
299,786
6
128,975
2,728
1
827,040
11,485
18
195,244,022
3,081,124
26
7,746,837
100,695
3
1,397,914
16,825
1
533,600
7,839
31
2,444,828
39,228
13
307,759
6,427
75
62,282,949
780,500
18
179,171
3,672
15
828,646
14,904
14
15,301,621
168,256
111
25,712,986
353,696
5
533,334
7,697
5
245,248
5,341
208
9,997,703
167,708
3
2,078,538
66,212
32
1,153,833
21,859
3
1,429,560
16,374
5
854,272
11,812
1
45,976,235
540,350
219
31,373,067
510,535
2
1,525,360
22,057
126
44,882,247
509,183
1,072
496,305,458
6,966,586
2
3,212,291
36,343
1
(c)
18,773
1
315,396
5,596
1,076
499,833,145
7,027,298
Notes: (a) New Account.
(b) Including 152,161,432 KWH resold at commercial rates for $2,682,816
to Airport tenants.
(c) Included under Street Lighting Operations.
53 -
TABLE 13
BUREAU OF LIGHT, HEAT AND POWER
EXPENDITURE FOR GAS FOR MUNICIPAL PURPOSES
FISCAL YEAR 1976-1977
NATURAL GAS
NO. OF
CONSUMPTION
DEPARTMENT
ACCOUNTS
2
THERMS
EXPENDITURES
Art Commission (a)
3,398
680
Auditorium and Brooks Hall
2
1,007
197
Child Care Centers
11
30,156
5,723
City Demonstration Agency
1
9,539
1,878
City Planning
1
4,551
883
De Young Museum
1
238,287
46,149
Electricity
2
38,560
7,566
Farmer ' s Market
1
335
70
Fire
54
441,321
85,108
Hassler Health Home
3
1,443
293
Health
34
6,011,678
1,141,123
Hetch Hetchy
2
1,730
341
International Airport
5
1,444,270
273,861
Junior College District
17
606,221
116,916
Juvenile Hall
4
404,798
78,562
Legion of Honor
1
49,483
9,685
Library
28
93,808
18,256
Municipal Railway
14
264,005
54,733
Police
11
40,994
7,925
Public Buildings
5
1,233,393
239,823
Public Works
15
284,860
59,913
Purchasing
3
' 42,173
8,242
Real Estate
3
4,203
762
Recreation and Park
105
1,118,168
216,320
Recreation and Park - Candlestick Park
1
94,716
18,366
Registrar of Voters
1
2,934
557
Sheriff
3
438,175
84,274
Single Men's Rehabilitation
1
15,179
2,758
Social Services
4
48,849
9,532
Unified School District
211
3,832,147
752,904
War Memorial
3
235,392
46,277
Water
11
138,615
27,081
TOTAL MUNICIPAL DEPARTMENTS
560
17,174,388
3,321,758
Note: (a) New Account
54 -
TABLE 14
BUREAU OF LIGHT, HEAT AND POWER
STREETLIGHTS IN SERVICE
JUNE 30, 1977
SIZE & TYPE OF LAMP
High Voltage Series Circuit
1,000-Lumen Incandescent
2,500-Lumen Incandescent
4,000-Lumen Incandescent
6,000-Lumen Incandescent
10,000-Lumen Incandescent
400-Watt Mercury Vapor
175-Watt Mercury Vapor
250-Watt Mercury Vapor
Low Voltage Multiple Circuit
1,000-Lumen Incandescent
2,500~Lumen Incandescent
4,000-Lumen Incandescent
6,000-Lumen Incandescent
10,000-Lumen Incandescent
5,500-Lumen Fluorescent
23,000-Lumen Fluorescent
100-Watt Mercury Vapor
175-Watt Mercury Vapor
250-Watt Mercury Vapor
400-Watt Mercury Vapor
700-Watt Mercury Vapor
1,000-Watt Mercury Vapor
250-Watt Sodium Vapor
400-Watt Sodium Vapor
COMPANY-
JOINTLY-
CITY-
OWNED
OWNED
OWNED
TOTAL
UNDERGROUND CONNECTION
___
22
___
22
245
24
62
331
937
122
1,065
2,124
571
449
2,455
3,475
430
17
515
962
6
43
232
4
79
281
4
81
2
___
___
60
60
10
4
54
68
142
5
109
256
34
5
84
123
10
14
24
38
38
38
4
42
111
111
45
3,783
3,828
34
1,641
1,675
304
4,660
4,964
369
369
100
100
309
309
658
658
OVERHEAD CONNECTION
High Voltage Series Circuit
2,500-Lumen Incandescent
4,000-Lumen Incandescent
Low Voltage Multiple Circuit
2,500-Lumen Incandescent
4,000-Lumen Incandescent
6,000-Lumen Incandescent
175-Watt Mercury Vapor
250-Watt Mercury Vapor
400-Watt Mercury Vapor
TOTAL, JUNE 30, 1977
TOTAL, JUNE 30, 1976
NET CHANGE DURING THE YEAR
1
14
2
58
8
14,697
1,908
802
20,298
54.2%
20,429
131
691
1.8%
692
1
49
2
16,457
44.0%
16,257
200
1
14
2
107
8
14,699
1,908
802
37,446
100%
37,378
68
- 55
TABLE 15
BUREAU OF LIGHT, HEAT AND POWER
EXPENDITURES FOR OPERATION AND MAINTENANCE OF STREET LIGHTING
FISCAL YEAR 1976 - 77
883,566
30,875
105,038
1,019,479
312,925
CONTRACTUAL SERVICE
P. G. & E. Company
Company-owned facilities (a)
Jointly-owned facilities (a)
City-owned facilities (b)
Less deduction for energy component
Emergency service to City-owned facilities
Lease-Lite Corporation
Group lamp replacement - City-owned facilities
Lease-Lite Corporation
Maintenance and repair - City-owned facilities
Routine maintenance
Repair of damage caused by accidents (c)
Repair of damage caused by equipment failure
Repair of damage caused by vandals
MATERIAL AND SUPPLIES (FURNISHED BY CITY)
Damage caused by accidents (c)
Damage caused by equipment failure
Damage caused by vandals
ELECTRIC ENERGY (HETCH HETCHY)
45,976,235/KWH at $0.02408/KWH less 48.6% discount
TOTAL EXPENDITURE
LESS AMOUNT PAID TO HETCH HETCHY FROM;
Gas Tax Funds for State Highway Routes
Recreation and Park Department for off-street lighting
TOTAL NET EXPENDITURE
AVERAGE OPERATING COST
Based on number of lights in service June 30, 1977, average total
cost of operation, maintenance and repair per light per year:
NOTES: (a) Includes maintenance, repair, fixed charges and
electric energy for Company-owned facilities.
(b) Includes replacement of individual lamp and broken
glassware, service and switching charges, and electric
energy.
(c) When responsible party is known, claim is filed for
recovery of cost.
706,554
5,946
58,485
50,
,130
53,
,392
44,
,857
2,
,615
150,
,994
37,
,713
14,
,495
2,
,160
54,
569,
,368
,053
1
,545,
,400
18,
,773
2,
,341
21,
,114
1
.524,
,286
40.71
- 56 -
TABLE 16
BUREAU OF LIGHT, HEAT AND POWER
NEW CITY-OWNED STREET LIGHTING INSTALLATIONS
COMPLETED DURING FISCAL YEAR 1976-77
Number of Type of
Lights Lights*
Locations
Financed by Bond Issues:
Trumbull St. - Mission to Alemany St.
Fillmore - Chestnut
Bayshore Blvd. - Costa St. to County Line
Fillmore - Sutter
Maiden Lane - Grant Ave. to Kearny St.
Outer Richmond and Sunset Area
Potrero Ave. - Division to Army
Valencia St. - Market to Mission
Eugenia Ave. Stairway, Prospect Ave. to
Winfield St.
Value
Total
11
MV
$
22,001
58
MV
77,968
27
MV
140
SV
286,520
54
MV
65,401
4
MV
6,132
125
MV
284,133
119
MV
118,881
142
MV
293,066
2
MV
6,944
682
$1
,161,045
Financed by State Gasoline Tax:
John Muir Drive
Newhall and Mendall Sts.
Total
Grand Total
5
4
9
691
MV
MV
$ 17,310
6,523
$ 23,833
$1,184,878
*MV - Mercury Vapor
SV - Sodium Vapor (High Pressure)
- 57
m o
<r rn
m
. 4
ax
o->
00
VO
o
iX3
l£>
in
c 1
in
r^
rH
CM
m
o
co
oj
O
\0
LI.)
in
O
00
i-l
O
CM
m
m
VO
rn
in <r
LO
o
en
rn
~3-
CO
o-.
r-»
0 i
r-
00
O
l--
CM iH
-a- i-H
-T
o
CM
BO
H
m
H
00
rH
o
rH
rn
o
i-i
m
vO
O
i-4
00
rn
i/i
rH
On
a-.
O
CO
r -
O
un
rH
m
a
o
IN
VO
o
o
i-4 i-H
m in
m <■
rn
o
o
CM
C J
c -
oo
^h
vo
0>
m
H
cs
CN|
i-4
VO
rH
</>
CO-
9
0
->-•
ai
co
i-H a\
m o rn
oo m in
<r
a
01
in m
<r vo o
m oo vo
c^
eg
o
vO CM
m rn o
in o oo
av
<t m
cn r-~
<t CM
S 4J
j= a
oo <u
•H Q
o <r oo i-i
m r-~ r— oo
io m m H
. « » - l
CM CS vO 0>
« I I I I
>*
IJ
J
M
U
01
o
a.
a
0
3
u
a
Cu
>j in oo ^ \o o> r- i <r vo vo o vo m
ocrv^d-ooinc/vrnr^onr-^Oinr^
vf^N-CTNHNOOtSflM'lW
I I I I I I
I I I I I I I
OJV
CM
rH
oj
o
CM ,H
<f
m
CO
m
o>
Ov
rH
<r
CM
o
<r i-4
H
rH
CM
<r
CM
oo
m
on
r>
c
-* o
m
rH
av
O
l».
CM
oo
rH
vo
rH
o o
vO
rn
vO
rH
co
04
a>
m
rH
vO
m iH
ro
CM
P-.
vO
o~
m
</>
H
on
vc
CM
m oo
T-\ 1-1
CM
rH
rn
rH
rH
rH
1 r-«.
o
0
m r-»
0)
•H
a
r- 1
a
U
on VO
3
O
■a
iH r-»
•"}
7)
c
a\
U
m
U r-4
C
4-)
cO
O
to
JH
a> u
c
c
?n CO
0)
o
D
01
c
B
■H
01
rH
:■:
O
cfl
cn
H
id
in iH
rH CO
■H iH
rH
CO
o
CM
VO
rH
Csl
o^
vO
m
OJ
rH
o
m
rH
rH
co
CM
on
CO
o
rH
CO
m
rH
O^
O-J
OJ
m
m
rH
O
en
in
rH
vO
co
i-4
rn
O
o~
CO
m
co
Ol
OA
CO
r-~ cm
rH CM
o
cn
O
OJ
rH
rH
o
o
rH
CN
CO
O
O
CM
co
o
m
o^
rH
rH
rH
rH
cn
crv
m
cn
o
on
rH
m
<-<
m
<r
vO
og
CM
cn
cn
Ol
vO
o~
</>
m
c/l
co
0)
n) ft
•H
o
(0
> cu
l+H
CO
cu O
in rH r~ -* oo i-H
r-^ in cm o vo o
vo i-4 r-^ r-» i— i in
oo cm m m -* cm I I
<r <r m r-i r-i
I I I I I I I I I I I I
I I I I I I I I I I I I
I I I I I I
onm-*invor~cocTvO'-ioMcn<rmvor^ooavOi— icMcn-crinvo
inininuninininmvovovovovovovovovovor^r^r^r^r^r — ^r^-
C^C^^C^O>C^C^CACA^<7iO>CAC^C^C^OVO>C^^OVO^CAOVOV
T)
TJ
o
o\
C
01
a)
CO
rH
o
>
>
m
|
•H
u
o
in
4-1
F.
Fi
T3
on
CO
(1)
(1)
<u
cr>
QJ
u
U
c
rH
CJ
Dl
CO
o
Q<
C
C
1
<1
P4
o
o
^
[2
•H
•H
4-1
py
■u
4-J
•H
rn
u
u
u
T3
ro
<)
o
C
s
a.
Cu
in
o
CO
•H
LIH
U-<
<!
TO
o
o
4-1
CO
§
Pi
4-1
4-1
o
rH
m
CO
o
CO
d
0
o
01
D.
C )
C )
rH
X)
•H
CO
D
o
c
rH
■H
•H
O
C
n
oo
c
3
CO
•H
M
g
- 58
z_