Skip to main content

Full text of "Annual report of the City Engineer"

See other formats


Wit 


[Document  25  — 1881.] 


CITY  OF  ^^m  BOSTON. 


ANNUAL   REPORT 


CITY   ENQINEEK 


FOR  THE  YEAR  1880. 


Office  of  the  City  Engineer,  City  Hall, 
Boston,  February  1,  1881. 

To  the  Honorable  City  Council ;  — 

In  compliance  with  the  sixth  section  of  the  ordinance 
relating  to  the  Engineer's  Department,  the  following  report 
of  the  expenses  and  operations  of  the  department  for  the 
year  1880  is  respectfully  submitted. 

The  duties  of  the  City  Engineer  may  be  classified  under 
the  following  heads  :  — 

A.  — Those  pertaining  to  the  City  Engineer's  Department 
proper,  which  consist  in  the  superintendence  of  the  filling  of 
new  streets  and  of  districts,  in  the  care  and  maintenance 
of  bridges,  in  designing  and  superintending  the  construction 
of  new  bridges,  retaining-walls,  city  wharves,  etc.,  and  in 
miscellaneous  work  called  for  by  committees  of  the  City 
Council.      (City  Engineer's  Department.) 

B.  —  Superintendence  of  the  Sudbury  River,  Cochituate, 
and  Mystic  Water  Works,  including  charge  of  new  con- 
structions for  these  works.      (Water  Works.) 

C.  —  Charge  of  the  building  of  a  new  system  of  works 
for  bringing  an  additional  supply  of  water  from  Sudbury 
River.     (Additional  Supply.) 


2  City  Document  No.  25. 

D.  — Charge  of  the  construction  of  a  system  of  intercept- 
ing and  ontlet  sewers.     (Improved  Sewerage.) 

E.  —  Charge  of  the  engineering  work  in  connection  with 
the  Back  Bay  and  other  proposed  parks.     (Parks.) 

The  expenses  incurred  under  the  lieads  C.  and  D.  are  paid 
wholly  from  special  api3ropriations ;  one  under  the  charge  of 
the  Water  Board,  the  other  under  the  charge  of  the  Joint 
Special  Committee  on  Improved  Sewerage. 


(A.) — City  Engineer's  Department. 

The  following  is  a  statement  of  engineering  expenses  from 
January  1,  1880,  to  January  1,  1881 :  — 

Amount  expended  from  department  appro- 
priation for  1879-80    ....  $6,765  54 

Amount  exijended  from  department  appro- 
priation for  1880-81    ....  19,276  23 


Total   expended    from    department   appro- 
priations      $26,041  77 

Amount  expended    from  special  and  other 

appropriations    .         .         .         .         .  2,074  60 


Total $28,116  37 


Condition  of  department  appropriation  ;  — 

Amount  of  appropriation   for  financial  year 

1880-81  $26,000  00 

Amount  expended  to  January  1,1881  .  19,276  23 

Unexpended  balance,  January  1,  1881         .  $6,723  77 


From  special  and  other  appropriations  :  — 

New  main  Cochituate  Water  Works. 
Pay-rolls $807  50 

Chelsea  Bridge. 
Pay-rolls  and  incidentals         ....  575  50 

Broadway  extension. 
Pay-rolls  and  incidentals         .         .         .         .  691  60 

Total $2,074  60 


53,411 

74 

144 

35 

245 

30 

187 

32 

218 

36 

74 

46 

645 

18 

592 

50 

303 

41 

132 

65 

86 

50 

26,041 

77 

Report  of  City  Engineer. 


CLASSIFICATION  OF  EXPENSES. 

Salaries  of  City  Engineer,  assistants,  drauglits- 

meu,  transitmen,  levellers,  rodmen,  etc. 
Engineering  instruments  and  repairs  of  same   . 
Drawing  paper  and  materials 
Stationery  and  printing  stock 
Reference  books,  maps,  photographs,  and  frames, 
Printing  and  binding       ..... 
Travelling  expenses,  including  horse-keeping, 

etc.  .         .         .         .         .         .         . 

Horse  and  new  caariage  .         !         .         . 

Incidental  expenses  and  small  supplies     . 
"  Blue  Process  "  printing  and  materials 
Committee  expenses        ..... 

Total 

The  number  of  persons  employed  and  paid  from  the  de- 
partment appropriation  was,  on  the  first  of  January,  1880 
(including  the  City  Engineer),  18.  The  present  number  is 
22.  The  operations  of  the  department  for  the  year,  together 
with  such  general  information  relating  to  the  various  works 
and  structures,  finished  and  in  progress,  as  is  thought  to  be 
of  interest,  are  given  in  the  following  statements  :  — 

BRIDGES. 

The  largest  portion  of  the  work  done  on  the  tide-water 
and  inland  bridges,  during  the  year,  has  been  in  the  way  of 
repairs. 

The  city's  portion,  with  the  exception  of  the  draw  and  its 
foundations,  of  the  Chelsea  bridge  over  the  main  channel  of 
the  Mystic  river,  has  been  entirely  rebuilt. 

Two  new  street  bridges  are  in  process  of  construction, — 
the  bridge  over  the  Boston  and  Albany  Railroad  on  the  ex- 
tension of  Broadway,  and  the  Beacon-street  bridge  over  the 
Park  water-way.  In  the  Back-Bay  park  the  foundations 
are  being  put  in  for  an  arched  bridge  on  Boylston  street, 
over  the  Park  pond. 

The  ordinary  repairs  of  the  bridges  in  charge  of  the 
Committee  on  Bridges  have  been  made  by  day's  labor, 
under  the  same  system  adopted  by  the  committee  of  last 
year.  Mr.  S.  S.  Lewis  has  been  the  superintendent  of  the 
work,  receiving  for  this  service,  and  for  furnishing  a  team 
and  transportation  for  his  men,  $100  per  month,  and  $2.00 


4  City  Document  No.  25. 

per  day  for  labor  furnished.  His  work  has  comprised  all 
the  carpentering,  painting,  and  odd  jobbing  required  on  the 
bridges.  Machinists'  and  blacksmiths'  work,  pile-driving, 
stone-work,  paving,  calking,  and  concrete-laying  have  been 
done  by  day's  labor,  but  by  agreement  after  competition. 

The  spruce  lumber  required  for  repairs  has  been  furnished 
by  Mr.  John  W.  Leatherbee,  the  lowest  bidder,  and  the  cou- 
ti'actor  for  several  past  years.  He  has  furnished  245,880 
feet  B.M.,  for  $13.90  perM.,  under  his  contract  of  1880, 
and  3,279  feet  B.M.,  for  $11.90  per  M.,  under  his  contract 
of  1879.  The  other  kinds  of  lumber  required  have  been 
bought  of  the  lowest  bidders  under  competition,  and  in  the 
open  market. 

The  total  cost  of  repairs  made  under  the  direction  of  this 
department  on  the  tide-water  bridges  has  been  $25,565.02. 

Repairs  have  been  made  under  the  supervision  of  this 
department  upon  many  of  the  inland  bridges,  at  the  request 
of  the  Superintendent  of  Streets.  This  work  has  been  done 
by  day's  labor,  and  with  materials  purchased  in  the  open 
market.     The  total  cost  of  these  repairs  has  been  $2,501.66. 

The  usual  annual  examination  (required  by  Section  5  of 
the  ordinance  relating  to  the  Engineer's  Department)  of  all 
bridges  within  the  city  limits  open  to  team  and  foot  travel 
has  been  made ;  and  the  results  of  this  examination,  in 
regard  to  the  condition  of  the  bridges  as  to  safety  and  need 
of  renewal  or  repairs,  are  given  in  the  following  pages. 

The  following  is  a  list  of  the  bridges  inspected.  The 
number  is  one  greater  than  last  year,  owing  to  the  two  por- 
tions of  Chelsea  bridge,  which  now  have  about  a  quarter  of  a 
mile  of  solid  street  between  them,  being  considered  as  sepa- 
rate bridges. 

Those  marked  with  an  asterisk  are  over  navigable 
waters,  and  are  each  furnished  with  a  draw  ;  — 

I.  —  Bridges  wholly  supported  by  Boston. 

Ashland    street,    "Ward    23,    over   Boston   &,   Providence 
Railroad. 

Athens  street,  over  N.Y.  &  N.E.  Raih-oad. 

Berkeley  street,  over  the  Boston  &  Albany  Railroad. 

Berkeley  street,  over  Boston  &  Providence  Railroad. 
*Broadway,  over  Fort  Point  Channel. 

Brookline  avenue,  over  Muddy  river,  Ward  22. 
*Cbarles  river,  from  Boston  to  Charlestown. 
*Chelsea  (South),  over  South  Channel  Mystic  river. 
*Chelsea  street,  from  East  Boston  to  Chelsea. 

Columbus  avenue,  over  Boston  &  Albany  Railroad. 


Report  of  Citt  Engineer.  5 

*Commercial  Point,  or  Tenean,  Ward  24. 
*Congress  street,  over  Fort  Point  Channel. 

Dartmoutli   street,  over  Boston   &  Albany  and  Boston  & 
Providence  Railroad. 
*  Dover  street,  over  Fort  Point  Channel. 
♦Federal  street,  "        "       "  " 

Ferdinand  street,  over  Boston  &  Albany  Railroad. 

Huntington  avenue,  over  "       "       "  " 

*Maldcn,  from  Charlestown  to  Everett. 
*Meridian  street,  from  East  Boston  to  Chelsea. 

Mill-dam,  over  Back-Bay  sluices. 
*Mt.  Washington  avenue,  over  Fort  Point  Channel. 

Newton  street,  over  Boston  &  Providence  Railroad. 

Public  Garden,  foot-bridge. 

Shawmut  avenue,  over  Boston  &  Albany  Railroad. 

Swett  street,  east  of  N.Y.  &  N.E.  Railroad. 

Swett  street,  west  of  N.Y.  &  N.E.  Railroad. 
*Warren,  from  Boston  to  Charlestown. 

West  Chester  park,  over  Boston  &  Albany  Railroad. 

West  Chester  park,  over  Boston  &  Providence  Railroad. 

Winthrop,  from  Breed's  Island  to  Winthrop. 

II.  —  Bridges   of    which   Boston    supports   the    Part 
WITHIN   its   Limits. 

♦Cambridge  street,  from  Brighton  (Ward  25)  to  Cambridge. 

Central  avenue,  from  Ward  24  to  Milton. 
*Chelsea  (North) ,  from  Charlestown  to  Chelsea. 
*Essex  street,  from  Ward  25  (Brookline)  to  Cambridge. 
*Granite,  from  Dorchester  (AVard  24)  to  Milton. 

Long  wood  avenue,  from  Ward  22  to  Brookline. 

Mattapan,  from  Ward  24  to  Milton. 

Milton,  "         "     "    "        " 

*Neponset,      "         "     "    "Quincy. ' 
*North  Beacon  street,  from  Ward  25  to  Watertown. 
*North  Harvard  street,  from  Ward  25  to  Cambridge. 

Spring  street,  from  West  Roxbury  (Ward  23)  to  Dedham. 
♦Western  avenue,  from  Ward  25  to  Cambridge. 
♦Western  avenue,  from  Ward  25  to  Watertown. 

Ill  — Bridges  of  which  Boston  pays   a  Part  of  the 
Cost  of  Maintenance. 

Albany  street,  over  Boston  &  Albany  Railroad. 
♦Canal,  from  Boston  to  Cambridge. 

Dorchester  street,  over  Old  Colony  Railroad. 
♦Prison  Point,  from  Charlestown  to  Cambridge. 
♦West  Boston,  from  Boston  to  Cambridge. 


6  City  Document  No.  25. 


IV. — Bridges  supported  by  Railroad  Corporations. 

1st.  —  Boston  (&  Albany  Railroad. 

Brighton  Avenue,  Ward  25. 
Harrison  avenue. 
Market  street,  Ward  25. 
Tremont  street. 
Washington  street. 

2d.  —  Boston  di  Maine  Mailroad. 

Mystic  avenue. 
Main  street. 

3d.  —  Boston  &  Providence  Railroad. 

Beach  street,  Ward  23. 

Belle vue  street.  Ward  23. 

Centre  street,  or  Hog  Bridge,  Ward  23, 

Centre  and  Mt.  Vernon  streets.  Ward  23. 

Dudley  avenue.  Ward  23. 

Park  street.  Ward  23. 

Sharon  street.  Ward  23. 

4th.  —  Boston,  Revere  Beach,  &  Lynn  Railroad. 
Everett  street. 


5th.  —  Eastern  Raihoad. 


Mystic  avenue. 
Main  street. 


6th.  —  N'ew  York  &  New  England  Railroad. 

Broadway. 

Dorchester  avenue. 

Fifth  street. 

Forest  Hill  avenue.  Ward  24. 

Fourth  street. 

Harvard  street.  Ward  24. 

Norfolk       "  a       ii     , 

Norfolk        .<  u       «t 

Second  street. 

Silver  street. 

Sixth  street. 

Third  street. 

Washington  street,  Ward  24. 


Report  of  City  Engineer.  7 

7ih.  —  Old  Colony  Railroad. 
Adcims  street. 

Ashmout  street  and  Dorchester  avenue. 
Cedar  Grove  cemetery. 
Commercial  street. 
Savin  Hill  avenue. 

Recapitulation. 

I.  Number  wholly  supported  by  Boston       .         .  30 

II.  Number   of  which   Boston  supports   the   part 

within  its  limits        .         .         .         .         .  14 

Iir.  Number   of  which  Boston  pays  a  part  of  the 

cost  of  maintenance  .....  5 

IV.  Number  supported  by  Railroad  Corporations  :  — 

1.  Boston  &  Albany    ......  5 

2.  Boston  &  Maine     ......  2 

3.  Boston  &  Providence       .....  7 

4.  Boston,  Revere  Beach,  &  Lynn        ...  1 

5.  Eastern          .......  2 

6.  New  York  &  New  England     .         .         .         .  13 

7.  Old  Colony 5 

Total  number     ......         84 

1.  — BRIDGES  WHOLLY  SUPPORTED  BY  BOSTON. 

Ashland-street  Bridge    (over  Boston   &  Providence 
Railroad,  Ward  23). 

This  bridge  is  in  good  condition.  The  abutments  need 
repointing,  and  the  girders  should  be  painted  during  the 
coming  year. 

No  repairs  have  been  made  the  past  year. 

Athens-street  Bridge  (over  New  York   &  New  Eng- 
land Railroad). 

No  repairs  have  been  made,  but  the  bridge  is  in  good 
order.     It  will  probably  require  painting  this  season. 

Berkeley-street    Bridge     (over    Boston    &    Albany 

Railroad). 

This  bridge  is  not  equal  in  strength  to  the  bridges  of  more 
recent  construction.  It  was  built  by  the  Moseley  Iron 
Bridge  Works  for  the  Boston  Water  Power  Co.,  and  came 
into  the  possession  of  the  city  when  the  street  was  accepted. 


8  City  Document  No.  25. 

Since  then  it  has  been  strengthened  and  is  now  in  good  con- 
dition, but  its  position  on  a  wide  thoroughfare  brings  it  in 
the  route  of  many  large  processions,  and  while  no  special 
signs  of  weakness  have  been  discovered,  it  requires  careful 
watching,  and  should  be  replaced  before  many  years  by  a 
stronger  structure. 

The  abutments  are  built  of  Roxbury  stone,  laid  dry,  and 
fire  very  poorly  constructed. 

The  roadway  has  been  sheathed. 

Total  cost  of  repairs,  $116.18, 


Berkeley-street  Bridge  (over  Boston  &   Providence 

Railroad). 

The  roadway  of  this  bridge  has  been  sheathed  during  the 
year. 

On  Dec.  5  a  derailed  engine  struck  three  of  the  cast- 
iron  supporting  columns,  knockin'g  them  out  of  position,  but 
fortunately  doing  no  other  damage  to  the  bridge.  The 
repairs  were  made  by  the  railroad  company. 

The  iron-work  will  probably  require  repainting  in  the 
spring ;  otherwise  the  bridge  is  in  good  condition. 

Total  cost  of  repairs,  $536.66. 

*  Broadway  Bridge  (over  Fort  Point  Channel). 

The  main  item  of  repairs  during  the  year  has  been  a  new 
under  floor  for  the  draw.  This  consists  %f  3|-inch  white 
pine,  calked  and  paid ;  the  draw  is  now  in  excellent 
condition. 

The  sheathing  of  all  the  truss  spans  has  been  renewed 
during  the  year. 

The  wood  pavement  between  the  draw  and  the  Lehigh- 
street  span  is  in  bad  order,  and  must  be  renewed  in  the 
spring.  The  draw-pier,  as  mentioned  in  previous  reports,  is 
in  a  somewhat  insecure  condition,  due  to  the  gradual  de- 
struction by  worms  of  the  spruce  sheet-piling  which  supports 
the  structure.  No  especial  change  for  the  worse  has,  how- 
ever, been  noticed  during  the  year. 

The  iron-work  will  require  cleaning  and  painting  in  the 
spring. 

Total  cost  of  repairs,  $3,621.45. 

Brookline-avenue  Bridge  (over  Muddy  River) 
Is  in  fair  condition. 


Report  of  City  Engineer. 


*  Charles-river    Bridge     (from    Boston    to  Charles- 

town). 

The  usucal  repairs  have  been  made,  and  the  bridge  is  in 
good  condition. 

A  small  addition  to  the  horse-honse  has  been  built  for 
the  better  accommodation  of  the  horses.  The  bridge  and 
buildings  have  been  painted,  and  a  new  buoy  has  been  placed 
below  the  bridge. 

Total  cost  of  repairs,  $2,347.40. 

*  Chelsea-street  Bridge  (from  East  Boston  to 
Chelsea)  . 

The  draw  to  this  bridge  is  in  poor  condition.  It  is  not 
used  for  the  passage  of  vessels  to  any  extent ;  otherwise  it 
would  require  rebuilding.  The  fixed  part  of  the  bridge  is 
in  good  condition. 

Total  cost  of  repairs,  $186.93. 

Columbus-avenue   Bridge    (over  Boston  &  Albany 
Railroad)  . 

None  but  ordinary  repairs  have  been  made.  The  bridge 
is  in  good  order. 

Total  cost  of  repairs,  $198.93. 

*  Commercial  Point,  or  Tenean  Bridge  (Ward  24), 

Has  received   the   usual  repairs,   and   the  bridge  is  in  fair 
condition. 

Total  cost  of  repairs,  $388.06. 

*  Congress-street  Bridge  (over  Fort  Point  Channel)  . 

The  opening  of  A  street  for  public  travel,  and  the  occu- 
pation of  the  South  Boston  Flats  by  the  New  York  &  New 
England  Railroad  Company,  have  caused  a  large  increase  in 
the  traffic  over  this  bridge. 

In  October  the  draw  was  run  into  by  a  coal  steamer, 
which  cut  through  the  sidewalk,  and  nearly  through  the 
lower  chord  of  one  of  the  main  trusses.  It  was  thoroughly 
repaired,  and  has  apparently  sustained  no  permanent  injury. 

The  centre  pivot  bearing  of  the  draw  was  examined  in 
October,  and  found  so  badly  worn  that  steps  have  been  taken 
to  provide  a  new  one. 

The  bridge,  as  a  whole,  is  in  good  condition. 

Total  cost  of  repairs,  $2,569.59. 


10  City  Document  No.  25. 

Dartmouth-street  Bridge  (over  Boston  &  Albany  and 
Boston  &  Providence  Eailroads). 

The  roadway  has  been  sheathed,  and  all  the  iron-work 
underneath  the  floor  has  been  painted.  It  is  now  in  good 
order. 

Total  cost  of  repairs,  $593.49. 

*  Dover-street    BrIdge    (over   Fort   Point   Channel) 

Has  required  only  ordinary  repairs,  and  is  in  good  order. 
Total  cost  of  repairs,  $858.14. 

*  Federal-street  Bridge  (over  Fort  Point  Channel). 

The  trusses  of  the  southerl}^  draw  have  been  repaired,  and 
the  floors  of  the  sidewalks  have  been  renewed  and  strength- 
ened. The  draw-piers  need  replankiug,  and  the  roadway 
floor  will  soon  require  renewal. 

Total  cost  of  repairs,  $3,028.32. 

Ferdinand-street  Bridge    (over   Boston   &   Albany 
Eailroad)  . 

But  few  repairs  have  been  made,  and  it  is  in  fair  condition. 
The  bulkhead  adjoining  the  bridge  remains  in  the  unsafe 
condition  reportc^cl  last  year. 

Total  cost  of  repairs,  $63.46. 

Huntington- a  venue  Bridge  (over  Boston  &  Albany 
Railroad)  . 

The  iron-work  has  been  thoroughly  cleaned  and  painted, 
and  the  bridge  is  in  good  condition. 
Total  cost  of  repairs,  $400.57. 

*  Malden  Bridge  (from  Charlestown  to  Everett)  . 

Very  few  repairs  have  been  required,  but  the  bridge  is  in 
good  condition.     It  should  be  painted  the  coming  season. 
Total  cost  of  repairs,  $184.20. 

*Meridian-street     Bridge      (from     East     Boston     to 

Chelsea). 

The  bulkheads  and  fences  on  the  main  bridge  are  decayed 
and  need  renewal ;  otherwise  the  bridge  is  in  t\iir  condition. 

The  stone  bulkheads  across  the  bridge,  at  the  ends  of  the 
draw,  which  have  proved  a  constant  source  of  annoyance  and 
expense,  have  been  removed,  and  wooden  bulkheads  sub- 
stituted. 

Total  cost  of  repairs,  $1,939.63. 


■J 


Keport  of  City  Engineer.  11 

Mill-Dam  Bridge  (over  Back-Bay  Sluices). 

The  Roxbuiy  stone  piers  of  this  bridge  are  not  in  good 
condition,  bnt  will  probably  continue  to  do  their  work  until 
the  completion  of  the  new  Beacon-street  bridge  and  the 
filling  of  the  Back  Bay  render  the  sluices  unnecessary. 

No  repairs  have  been  made. 

*Mt.    Washington-avenue   Bridge    (over   Fort    Point 

Channel). 

This  bridge  has  been  painted,  its  fender  guards  rebuilt, 
the  roadway  floor  patched,  and  other  smaller  repairs  made. 
The  floor  of  the  roadway  is  in  bad  condition,  and  should  be 
entirely  renewed.  The  floor  of  the  draw  is  also  weak,  and 
will  require  strengthening  the  coming  year. 

Total  cost  of  repairs,  $4,687.25. 

Newton-street   Bridge    (over  Boston  and  Providence 

Railroad)  . 

I  renew  the  recommendation  of  last  year  that  the  abut- 
ments be  extended  and  pointed. 

The  bridge  is  otherwise  in  good  condition. 
No  repairs  have  been  made. 

Public  Garden  Foot-Bridge. 

The  stone  work  of  this  bridge  should  be  pointed,  and  the 
wood  and  iron  work  painted. 

Shawmut-avenue     Bridge    (over    Boston    &     Albany 
Eailroad)  . 

This  bridge  is  in  fair  condition  ;  but  it  should  be  painted 
this  year.  • 

Total  cost  of  repairs,  $6.19. 

Swett-street  Bridges  (over  South-Bay  Sluices) 
Are  in  fair  condition. 

*Warren  Bridge  (from  Boston  to  Charlestown). 

The  roadway  near  the  Fitchburg  Eailroad  station  has  been 
strengthened  by  additional  stringers  put  in  place  from  below  ; 
the  sidewalks  on  the  draw  have  been  relaid,  and  the  usual 
repairs  made. 

The  bridge,  as  a  whole,  is  in  bad  condition  ;  the  larger  part 
of  the  supporting  piles  were  driven  w^hen  the  bridge  was 
built,  in  1828  ;  they  were  not  so  large  as  piles  used  in  later 


12  City  Document  No.  25. 

years,  and  have  been  reduced  in  size  by  the  action  of  water 
and  ice.  The  portion  of  the  bridge  near  the  Fitchburg  Rail- 
road station  was  built  in  1847,  to  facilitate  the  placing  of  the 
station  in  its  present  position,  and  the  piling  and  super- 
structure of  this  part  of  the  bridge  have  not  been  renewed 
since  that  time.  The  superstructure  of  the  remaining  por- 
tion was  renewed  in  1855. 

As  this  bridge  shows  no  exception  to  the  general  rule, 
that  the  older  any  portion  of  a  bridge  is  the  poorer  its  con- 
dition, it  follows  that  the  piles  are  in  the  worst  condition  on 
that  part  of  the  bridge  between  the  draw  and  Charlestown, 
and  the  flooring  and  timbers  are  the  poorest  portions  of  the 
section  between  the  draw  and  Boston. 

The  subject  of  increased  bridge  accommodations  between 
the  city  proper  and  Charlestown  has  been  carefully  con- 
sidered by  a  special  committee  of  the  City  Council  during 
the  past  year,  and  a  report  has  been  made  (City  Doc.  No. 
143,  1880)  which  gives  the  results  of  their  investigations. 

It  will  be  evident,  from  the  preceding  statements  of  the  age 
and  present  condition  of  this  bridge,  that  it  is  not  a  proper 
structure,  as  a  whole,  to  be  the  main  avenue  of  communica- 
tion between  the  city  proper  and  Charlestown.  It  will  last, 
with  careful  watching  and  repairing,  for  several  years  more ; 
but  its  width  at  the  present  time  is  inadequate  for  the  travel 
over  it,  and  it  would  probably  be  better  economy  to  rebuild 
and  widen  it  than  to  let  it  stand  much  longer  in  the  condition 
it  is  now. 

The  total  cost  of  repairs  was  $1,586.89. 

West  Chester   Park   Bridge   (over  Boston  &  Albany 

Railroad)  . 

This  bridge  is  in  good  order.       , 
No  repairs  have  been  made. 

West   Chester   Park   Bridge  (over   Boston   &  Provi- 
dence Railroad). 

The  roadways  have  been  replanked. 

The  bridge  is  in  fair  condition ;  both  this  and  the  pre- 
ceding bridge  should  be  painted  next  season. 
Total  cost  of  repairs,  $45.70. 

WiNTHROP  Bridge  (from  Breed's  Island  to  Winthrop) 

Is  in  good  condition. 

No  repairs  have  been  made. 


Report  of  City  Engineer.  13 


II.  — BRIDGES    OF    WHICH    BOSTON     SUPPORTS 
THE   PART   WITHIN   ITS   LIMITS. 

*  Cambridge-street    Bridge    (from   Ward   25   to 
Cambridge). 

Only  ordinary  repairs  have  been  made  ;  the  bridge  needs 
replanking,  and  the  work  will  be  done  this  winter,  if  the 
weather  permits. 

Total  cost  of  repairs,  $163.58. 

Central-avenue   Bridge   (over  Neponset  River,  Dor- 
chester Lower  Mills). 

This  bridge  is  in  excellent  condition. 
No  repairs  have  been  niudo. 

*  Chelsea  Bridge,  South  (from  Charlestown  to  the 

Boston  &  Lowell  Railroad  Wharf), 

and 

*  Chelsea  Bridge,  North  (from  the  Mystic  River 

Corporation's  Wharf  to  Chelsea). 

The  reconstruction  of  the  old  Chelsea  bridge,  partially 
made  in  1866-7,  has  been  completed  during  the  past  year, 
and  the  last  portion  of  the  old  bridge  of  the  Salem  turnpike 
and  Chelsea  Bridge  Corporation,  built  in  1802-3,  has  been 
removed.  When  the  work  of  reconstruction  was  commenced, 
in  1876,  the  bridge  was  3,300  feet  long  between  abutments  ; 
since  then  182  feet  in  length  at  the  Charlestown  end,  250 
feet  at  the  Chelsea  end,  and  1,263  feet  in  the  central  part  of 
the  bridge,  have  been  filled  solid,  making  two  bridges  in  lieu 
of  one.  These  bridges  are  separated  by  nearly  a  quarter  of 
a  mile  of  solid  street,  and  each  is  provided  with  a  draw  for 
the  passage  of  vessels.  The  bridge  over  the  south  channel, 
on  the  Charlestown  shore,  which  was  built  in  1877,  and  is 
371  feet  in  length,  is  in  good  condition  ;  only  ordinary  repairs 
have  been  made  upon  it.  A  full  description  of  this  structure 
may  be  found  in  the  Report  of  1878  (City  Doc.  20). 

The  bridge  over  the  main  channel  of  the  Mystic  river,  or 
"Chelsea  bridge.  North,"  with  the  exception  of  the  draw 
and  its  foundations,  has  been  rebuilt  during  the  year,  from 
19  feet  north  of  the  draw  to  the  Boston  abutment,  by  Boston, 
and  the  remainder  by  Chelsea.  The  portion  now  maintained 
,by  Boston  is  922  feet  in  length,  including  the  draw. 


14  City  Document  No.  25. 

An  Act  of  the  Legislature  of  1878  (Chapter  41)  pro- 
vided that  Boston  should  maintain  all  that  portion  of  the  bridge 
lying  southerly  of  the  draw,  and  that  the  draw  should  be 
maintained  jointly  by  Boston  and  Chelsea.  The  agreement 
made  last  year  with  Chelsea,  by  which  that  city  was  to  pay 
$25,000,  and  Boston  was  to  assume  the  future  mainten- 
ance of  the  draw,  draw-piers,  and  the  portion  of  the  bridge 
between  the  draw-piers  when  rebuilt,  has  been  consummated, 
the  assent  of  the  Legislature  having  been  previously  ob- 
tained. The  care  of  the  draw  was  assumed  by  Boston,  June 
1,  1880. 

The  work  of  rebuilding  the  portion  of  the  bridge  belong- 
ing to  Boston  was  done,  under  contract,  by  Messrs.  Young 
&  Ryan,  the  contract  price  being  $44,937. 

The  bridge  was  closed  to  travel  on  June  8.  The  rebuild- 
ing was  sufficiently  advanced  by  September  22  to  admit  of 
the  resumption  of  travel,  but  owing  to  the  non-completion  of 
the  portion  rebuilt  by_Qhelseajtha--travel  was  not  resumed 
jintil  December  \.J  The  new  bridge  is  49  feet  in  width, 
with  one  sidewaTIi  8  feet  wide.  It  is  built  in  a  substantial 
manner,  with  oak  piles  and  hard-pine  caps,  bolsters,  stringers, 
and  floor.  The  road-way  floor  is  6  inches  thick,  laid  with 
close  joints,  calked  and  covered  with  a  layer  of  Trinidad 
asphalt,  and  paved  with  granite  blocks.  The  sidewalk  is 
coal-tar  concrete  on  a  floor  of  creosoted  North  Carolina  pine. 
The  fences  are  white  pine,  neatly  painted. 

The  draw-piers  are  19  feet  in  width,  and  are  respectively 
170  and  180  feet  in  length.  They  have  oak  pile  foundations, 
with  hard-pine  timber  superstructures,  and  creosoted  North 
Carolina  pine  floors.  The  bents  of  piles  are  cross-braced 
with  oak,  and  the  ends  of  the  piers  protected  with  iron 
straps.  The  sides  of  the  water-ways  are  planked  to  a  line 
one  foot  above  low-water  mark.  The  pier  on  the  westerly 
side  of  the  bridge  occupies  the  place  of  the  old  one ;  on  the 
easterly  side  the  pier  is  built  on  the  side  of  the  channel 
opposite  to  the  old  pier.  Both  piers  are  now  on  the  Chelsea 
side  of  the  channel. 

■  Two  buoys  have  been  placed,  one  above  and  one  below 
the  bridge,  to  facilitate  the  passage  of  vessels  through  the 
draw-way. 

A  work-shop  has  been  built  on  the  draw-pier,  and  a  build- 
ing containing  the  Superintendent's  ofiice,  two  sleeping- 
rooms,  and  a  convenient  stable,  has  been  built  on  a  small 
wharf  adjoining  the  bridge  near  the  draw. 

The  draw  has  been  repaired  and  painted,  an  entirely  new 
floor  laid,  and  a  sidewalk  built  upon  it. 
*  The    cost   of  the    entire    work   of  rebuilding,    including 


Report  of  City  Engineer.  15 

engineering,  superintendence,  building  and  furnishing  Super- 
intendent's office,  etc.,  and  all  expenses  incurred  up  to  Jan. 
1,  1881,  was  $50,477,08. 
Total  cost  of  ordinary  repairs  on  both  bridges,  $1,693.G6. 

*ESSEX-STREET    BrIDGE    (fROM   WaRD    25    TO    CAMBRIDGE). 

A  short  piece  of  this  bridge  from  the  railroad  crossing  to 
the  abutment  has  been  newly  covered  with  a  hard-pine  floor, 
calked  and  paid,  and  the  whole  bridge  surface  has  been 
replanked.     The  bridge  is  now  in  good  condition. 

Total  cost  of  repairs,  $1,368.05. 

*Granite  Bridge   (from  Ward  24  to  Milton). 

Only  ordinary  repairs  have  been  made,  and  it  is  in  fair 
condition. 

Total  cost  of  repairs,  $116.03. 

LONGWOOD-A VENUE    BrIDGE     (FROM    WaRD    22    TO     BrOOK- 

line). 

A  new  floor  has  been  laid  on  the  part  supported  by  Bos- 
ton.    The  bridge  is  in  good  condition. 
Total  cost  ot^repairs,  $282.04. 

Mattapan  Bridge  (from  Ward  24  to  Milton). 

This  bridge  is  a  weak  structure,  but  in  fair  condition. 
No  repairs  have  been  made. 

Milton  Bridge  (from  Ward   24  to  Milton). 

This  bridge  is  in  fair  condition. 

No  repairs  have  been  made  during  the  year. 

*Neponset  Bridge   (from  Ward  24  to  Quincy). 

This  bridge  has  been  painted,  and    a  few  minor  repairs 
have  been  made  ;  it  is  in  good  condition. 
Total  cost  of  repairs,  $123.85. 

*NoRTH    Beacon-street    Bridge     (from    Ward    25    to 
Watertown)  . 
No  repairs  have  been  made  on  this  bridge.     The  lower 
course  of  floor-plank  is  in  bad  condition,  and  will  have  to  be 
renewed  this  year. 

*North    Harvard-street   Bridge    (from    Ward   25   to 
•  Cambridge). 

Only  trifling  repairs  have  been  made ;  it  is  in  excellent 
condition. 

Total  cost  of  repairs,  $30.80. 


16  City  Document  No.  25. 

Spring-street   Bridge    (from    Ward    23   to   Dedham). 

With  the  exception  of  the  railing,  which  is  poor,  and  to 
which  attention  has  been  called  for  several  years,  this  bridge 
is  in  good  order. 

*  Western-avenue    Bridge    (from    Ward    25    to    Cam- 

bridge) . 

This  bridge,  completed  during  the  early  part  of  the  year, 
was  described  in  the  last  annual  report.  Very  few  repairs 
have  been  needed,  and  it  is  now  in  excellent  condition. 

Total  cost  of  ordinary  repairs,  $404.31. 

*  Western-avenue  Bridge  (from  Ward  25  to  Water- 

town)  . 

Estimates  and  plans  for  rebuilding  this  bridge, and  a  model 
of  a  leaf  draw  applicable  to  the  very  sharp  angle  which  the 
bridge  makes  with  the  river,  were  made  early  in  the  year ; 
but  the  town  of  Watertown  did  not  wish  to  cooperate  with 
the  city  in  rebuilding  the  bridge,  so  nothing  further  was 
done.  The  reconstruction  of  the  bridge  was  recommended 
by  the  Committee  on  Bridges  of  last  year,  and  is  a  very 
much  needed  improvement.  Great  inconvenience  is  experi- 
enced on  account  of  the  difficulty  of  passing  vessels  through 
the  draw,  and  the  long  time  consumed  in  doing  it. 

The  bridge  is  in  safe  condition  ;  but  the  abutment  over- 
hangs its. base,  and  is  liable  to  fall. 

Total  cost  of  repairs,  $266.88. 

III.  — BRIDGES    FOR  MAINTENANCE   OF    WHICH 
BOSTON  PAYS    A   PART   OF    THE  COST. 

Albany-street   Bridge  (over  Boston  &  Albany  Rail- 
road). 

The  abutments  are  in  very  bad  condition,  and  the  bridge 
is  rapidly  deteriorating  from  the  effects  of  rust. 

The  abutments  ought  to  be  rebuilt,  and  if  the  bridge  was 
removed  for  this  purpose  it  would  not  probably  be  worth 
putting  back  again. 

Total  cost  of  repairs,  $98.11. 

*  Canal  Bridge  (from  Boston  to  Cambridge). 

*  Prison-Point    Bridge    (from   Charlestown  to   Cam- 

bridge) . 

*  West  Boston   Bridge    (from  Boston  to  Cambridge). 
These  three  bridges  are  in  good  order. 

[See  Report  of  the  Commissioner  for  Boston,  City  Doc. 
No.  8,  1881.] 


Report  of  City  Engineer.  17 

Dorchester-street    Bridge    (over   Old   Colony   Rail- 
road). 

Nothing  hfis  been  clone  to  arrest  the  rusthig  out  of  this 
bridge,  and  its  condition  cannot  be  better  expressed  than  by 
the  use  of  the  Language  in  tlie  last  report :  "  The  bridge  is 
badly  damaged  for  want  of  proper  care  ;  just  how  badly  can- 
not be  known  until  it  is  stripped  and  cleaned.  Enough  is 
known  of  its  condition  to  warrant  the  statement  that  unless 
it  is  cleaned  and  painted  soon  it  will  last  but  a  few  years 
more." 


IV.  — BRIDGES   SUPPORTED  BY  RAILROAD   COR- 
PORATIONS. 

The  bridge  on  Commercial  street,  Dorchester,  over  the 
Old  Colony  Railroad, is  in  bad  condition.  The  main  trusses 
are  old  and  rotten,  and  the  floor  timbers  should  be  supported 
on  a  wall  plate  instead  of  the  insecure  blocking  now  in  use. 

The  surface  of  the  bridge  on  Centre  and  Mt.  Vernon 
streets,  over  the  Dedham  branch  of  the  Boston  &  Providence 
Railroad,  is  inclined  in  the  wrong  direction,  and  water  stands 
upon  it  after  a  rain. 

The  bridge  on  Broadwa3^  over  the  New  York  and  New 
England  Railroad,  is  in  bad  condition,  the  under  floor  being 
especially  poor  and  rotten. 

The  remaining  bridges  in  this  class  are  apparently  in  good 
order,  and  require  no  special  mention.  Most  of  them  are 
simple  platforms  of  wood,  and  when  under  repair  their  con- 
dition can  be  ascertained  with  ease.  To  obtain  the  informa- 
tion which  would  enable  this  department  to  report  with  cer- 
tainty as  to  their  safety  it  would  be  necessary  to  remove  the 
flooring,  —  usually  in  two  thicknesses,  crossing  each  other  at 
right  angles,  • —  and  as  there  seems  to  be  no  special  necessity 
for  incurring  so  large  an  expense,  this  has  never  been  done. 
The  most,  therefore,  that  can  be  said  of  these  bridges  is  that 
they  are  apparently,  and  probably,  in  safe  condition,  with 
the  exceptions  mentioned. 

MISCELLANEOUS    WORK    AND    CONSTRUCTIONS 

IN  1880. 

Alford-street  Sea-Wall. 

Plans  and  specifications  for  increasing  the  height  of  the 
sea-wall  on  Alford  street,  Charlestowu  (near  Maiden  Bridge) , 
and  for  a  fence  and  sidewalk  on  the  same,  have  been  made. 


18  City  Document  No.  25. 

A  contract,  dated  Nov.  8,  1880,  was  made  with  Charles  T. 
Derry,  for  domg  the  work,  for  the  sum  of  $3,494,  and  it  is 
now  partially  completed. 

The  top  of  this  wall  was  considerably  below  the  street 
filling,  and  the  work  now  in  progress  to  remedy  this  defect 
consists  in  rebuilding  a  small  portion  of  the  wall,  and  setting 
a  course  of  cap-stones  on  it  at  the  established  grade  for  its 
entire  length.  A  new  fence  and  a  creosoted  jilank  sidewalk 
are  also  included  in  the  contract.  The  wall  is  1,100  feet  in 
length.  No  payment  on  account  of  this  work  has  yet  been 
made. 

Beacon-street  Bridge. 

Early  in  the  year  plans  and  specifications  were  prepared 
for  the  foundations  of  a  new  bridge,  and  a  temporary  datn 
in  connection  therewith,  at  the  outlet  of  the  Back -Bay  park 
pond.  The  contract  for  this  work  was  aAvarded  to  Ross  & 
Lord,  who  conmienced  operations  August  12,  but  have  not 
yet  completed  it. 

The  bridge  is  to  consist  of  two  spans,  of  20  feet  each,  over 
the  sluice-wa}'  from  the  park  pond.  Five  and  one-half  feet 
north  of  the  northerly  line  of  Beacon  street  there  is  to  be  a 
dam,  with  self-operating  swinging- gates,  across  the  sluice- 
way. .  ' 

The  top  of  this  dam  is  to  be  at  grade  6.5  above  city  base, 
with  flash-boards  of  sufficient  height  to  prevent  the  surface 
of  the  park  pond  from  falling  below  grade  8,  unless  the 
flash-boards  are  removed.  The  gates  are  to  be  over  the 
dam,  forming  a  part  of  it,  and  are  to  open  outwards. 

When  the  surface  of  the  pond  rises  above  grade  8,  the 
water  will  discharge  over  the  dam,  unless  the  tide  outside 
should  be  higher  than  this  grade  ;  in  which  case  the  gates  shut 
out  the  tide,  and  no  water  will  then  run  over  the  dam  until 
the  tide  level  is  lower  than  the  pond. 

This  dam  in  its  present  form  and  location  is  a  temporary 
structure,  which  is  only  intended  to  remain  until  it  is  deter- 
mined what  is  to  be  done  with  the  flats  on  the  Charles-river 
side  of  Beacon  street.  When  this  question  is  settled,  and 
the  lines  of  improvement  are  defined,  it  will  be  necessary  to 
build  a  permanent  dam  and  gate-chamber  in  some  other  loca- 
tion on  the  extension  of  the  sluice-way.  Its  construction  at 
the  present  time  is  for  the  purpose,  in  connection  with  the 
covered  channel  of  Stony  Brook,  of  controlling  the  height 
of  the  water  in  the  pond,  so  that  the  necessary  work  can  be 
done  within  the  Park  limits. 

Provision  has  been  made  in  the  contract  for  building 
across  Beacon  street  a   portion   of  the  covered   channel  of 


Keport  of  City  Engineer.  19 

Stony  Brook,  so  that  it  will  not  be  necessary  to  again  inter- 
rupt travel  over  it  for  this  work. 

The  travel  over  Beacon  street  is  now  maintained  by  means 
of  a  road-way  filled  around  the  site  of  the  bridge  on  the 
southerly  side  of  the  street ;  a  water-pipe  is  laid  temporarily 
in  this  road-way,  to  prevent  any  interruption  of  the  flow 
throuajh  the  40~incli  main.  . 

The  amount  of  the  contract  for  the  bridge  fonndations  and 
dam  is  $36,898,  and  there  has  been  paid  for  work  done,  and 
materials  furnished,  the  sum  of  $12,490.15. 

On  Dec.  30,  1880,  a  contract  was  made  with  David  H. 
Andrews,  of  the  Boston  Bridge  Works,  to  build  an  iron 
deck  bridge,  and  a  wrought-iron  water  pipe  to  connect  with 
the  40-inch  main,  for  the  sum  of  $4,693.  The  bridge  and 
pipe  are  to  be  completed  and  erected  within  thirty  days  from 
the  date  of  the  completion  of  the  abutments  and  central 
pier. 


Beacon-street  Widening. 

The  contract  with  Martin  Lennon,  of  Boston,  for  widening 
the  section  of  Beacon  street  between  West  Chester  Park 
and  the  intersection  of  the  former  street  with  Brighton  and 
Brookline  avenues,  was  finished  Aug.  18,  1880.  The 
character  of  the  work  is  fully  described  in  the  last  annual 
report. 

The  total  amount  expended  for  work  under  the  contract 
was  $19,143.99. 

Broadway   Extension   (over   the   Boston   and   Albany 

Railroad). 

Plans  and  specifications  for  abutments  for  a  bridge  over 
the  Boston  and  Albany  Railroad,  and  for  retaiuing-walls 
from  the  abutments  to  the  streets  nearest  to  the  bridsfe,  have 
been  prepared.  A  contract,  dated  Sept.  3,  1880,  was  made 
with  John  Cavanagh  &  Co.  for  building  the  same,  for  the 
sum  of  $64,900.  The  sharp  angle  which  the  bridge  makes 
with  the  railroad  necessitates  abutments,  each  119  feet  in 
length,  on  the  foundation  line.  The  width  of  the  roadways 
on  each  side  of  the  railroad,  from  the  abutments  to  the 
streets,  is  62  feet,  the  top  of  the  retaining- walls  being  set 
one  foot  over  the  line  of  the  abutting  premises  by  agreement 
with  the  Boston  &  Albany  Railroad  Co. 

The  work  is  being  actively  prosecuted,  and  the  founda- 
tions for  the  abutments  and  the  larger  part  of  the  foundations 
for  the  retaining  walls  ai-e  completed.  The  abutments  above 
the  foundations  have  been  commenced,  and  most  of  the  cut 


20  City  Document  No.  25. 

stone  required  for  completing  them  has  been  delivered.  It 
is  expected  that  the  work  will  be  so  fiir  advanced  early  in 
the  season  as  to  be  in  readiness  for  the  superstructure. 

The  total  amount  paid  to  the  contractor,  including  the 
January  estimate,  was  $22,569.37. 

The  plans  for  the  iron  bridge  superstructure  are  in  prog- 
ress.    The  span  will  be  144  feet. 

Commonwealth-avenue   Extension. 

In  February  negotiations  were  begun  between  the  city 
and  owners  of  the  land  bounded  by  Beacon  street.  West 
Chester  park,  Brookline  avenue,  and  the  Boston  &  Albany 
Kailroad,  having  for  their  object  a  mutual  agreement  for  the 
filling  of  that  territory.  Surveys  and  soundings  were  made 
by  this  department  in  conjunction  with  Messrs.  Fuller  and 
Whitney,  engineers  for  the  land-owners,  to  complete  and 
verify  a  survey  commenced  previously  by  Messrs.  Fuller  and 
Whitney.  March  20,  1880,  an  agreement  was  entered 
into  between  the  City  of  Boston,  the  Boston  Water  Power 
Co.,  the  Trustees  of  the  Beacon-street  lands,  and  Alfred  A. 
Marcus,  for  the  filling  jointly  of  this  territory. 

Proposals  were  advertised  for,  and  April  29,  1880, 
separate  contracts  were  made  with  the  Boston  &  Albany 
Railroad  Company,  by  the  Committee  on  Streets  and  Park 
Commissioners  for  the  City  of  Boston,  and  the  Boston  Water 
Power  Co.,  and  the  Trustees  of  the  Beacon-street  lands,  for 
filling  the  area  between  Beacon  street,  Brookline  avenue,  the 
Boston  &  Albany  Railroad,  and  the  easterly  line  of  50- 
feet  street  bordering  on  the  easterly  side  of  the  Beacon 
entrance  of  the  Back-Bay  park. 

Work  was  begun  on  this  filling  April  26,  1880,  and  the 
quantity  of  gravel  deposited  upon  the  territory,  to  and 
including  December  31,  1880,  was  94,106  car-loads, 
amounting  to  37,350  squares.  Of  this  amount  the  approxi- 
mate estimates  show  that  there  have  been  deposited,  — 

Upon  land  of  the  B.  &  A.  R.R.  Co.     .         .         795  squares 
"        "     "    "   Boston  Water  Power  Co.  .      6,856       " 
"        "     "    "    Trustees  Beacon-st.  lands  .      7,737      " 
"     Back- Bay  park  ....      6,847       "- 

"     Commonwealth    avenue  and   adjacent  " 

streets 15,115       " 


Total 37,350 

By  the  terms  of  the  several  contracts  the  entire  work  is 
to  be  completed  August  1,  1881. 


Report  of  City  Engineer.  21 

Until  December  9  the  gravel  was  brought  from  the 
bank  at  AVeston  which  was  used  for  the  park  filling  under 
the  contract  of  1879.  Since  December  9  it  has  been 
brought  from  a  bank  recently  opened  by  the  company  in 
Newton,  near  Riverside  Station. 

Roxbury-Canal  Improvement. 

The  work  of  filling  that  portion  of  Roxbury  canal  west  of 
West  Chester  park  was  commenced  October  11,  1878, 
and  was  finished  March  26,  1880;  during  this  time 
6,352  squares  of  filling  were  deposited  in  the  canal,  at  a 
cost,  including  dumping,  measurement  of  carts  and  superin- 
tendence, of  $17,445.79. 

The  total  amount  expended  for  work  done  under  the  super- 
vision of  this  depaitment  was  $31,261.35. 

The  Joint  Special  Committee  on  Improved  Sewerage,  in 
charge  of  this  improvement,  settled  with  Joseph  Ham,  De- 
cember 31,  1880,  for  damages  caused  by  taking  his  land. 
The  amount  paid  was  $79,000.  This  was  the  only  claim 
remaining  unsettled  except  that  of  George  Curtis. 

South-Bay  Dam. 

This  dam  was  built  for  the  Board  of  Health.  The  Board 
was  directed,  by  an  order  passed  by  the  City  Council,  July 
26,  1880,  to  abate  a  nuisance  on  that  portion  of  the  .South- 
Bay  flats  between  the  New  York  &  New  England  Railroad 
and  Dorchester  avenue  north  of  Swett  street,  and  the  sum  of 
$4,600  was  appropriated  for  the  purpose. 

A  license  was  obtained  from  the  Harbor  and  Land  Com- 
missioners for  the  construction  of  a  temporary  dam  from 
"Wales  Island"  to  the  embankment  of  the  N.Y.  &  N.E. 
R.R.  Plans  and  specifications  were  made  for  it,  and  the  con- 
tract for  the  wood-work  was  awarded  to  F.  G.  Whitcomb, 
Oct.  1,  1880;  the  ballasting  was  awarded  to  C.  H.  Ed- 
wards. 

The  dam  is  522  feet  in  length,  with  sluices  24  feet  in 
length,  and  consists  of  a  line  of  sheet-piling  driven  between 
two  rows  of  spruce  piles.  The  piles  are  driven  in  pairs  15 
feet  apart,  except  at  the  sluices,  where  they  are  6  feet  apart 
measuring  on  the  line  of  the  dam.  The  sheet-piling  is  securely 
spiked  near  the  top  to  a  double  line  of  spruce  stringers, 
which  are  bolted  to  the  piles  with  1-inch  diameter  wrought- 
irun  bolts. 


22  City  Document  No.  25. 

The  dam  is  ballasted  on  both  sides. 

The  top  of  it  is  at  grade  5,  with  the  sluices  at  grade  0. 

Its  construction  was  commenced  Oct.  4,  and  work  upon 
it  was  stopped  Nov.  2(3. 

Owing  to  the  neglect  of  the  contractor  for  the  ballast  to 
furnish  it  as  rapidly  as  it  was  required  a  portion  of  the 
sluice-way,  35  feet  in  length,  was  carried  away.  The  gap 
has  been  tilled  up  to  low  water  with  heav}'^  riprap,  and,  as 
soon  as  the  weather  permits,  the  work  of  closing  it  will  be 
finished. 

The  amount  expended  for  the  wood-work  was  $2,680.42  ; 
for  the  ballast,  to  Jan.  1,  was  $1,260.50. 

Total  amount  expended  to  Jan.  1,  1881,  including  con- 
struction, measurement  of  scows,  etc.,  $4,048.92. 


IN   GENERAL. 

A  considerable  amount  of  work  of  a  miscellaneous  char- 
acter has  been  done  during  the  year.  Under  this  head  may 
be  classed  plans  and  estimates  for  a  bridge,  abutments,  and 
retaining-walls  at  Mt.  Hope  Station,  on  the  Boston  and  Provi- 
dence Eailroad ;  plans  for  the  improvement  of  Stony  Brook 
in  Brookside  avenue,  Ward  23  ;  estimates  for  the  extension 
of  D  street  across  the  Old  Colony  Railroad  ;  measurement  of 
stone  for  temi)orary  dam  at  the  ]\lill  Dam  sluices  ;  supervi- 
sion of  repairs  on  bridges  in  charge  of  Paving  Department ; 
estimates  and  plans,  involving  a  large  amount  of  office- work, 
for  a  new  bridge  to  Charlestown,  etc.,  etc. 

In  the  draughting-room  an  unusually  large  amount  of  work 
of  a  miscellaneous  character,  consisting  of  copying,  blue- 
printing, tracing,  and  revising  plans,  has  been  done,  and  esti- 
mates of  cost  have  been  made  for  bridges  in  the  Back-Bay 
park,  for  a  draw  for  the  proposed  Northern-avenue  bridge, 
and  designs  for  a  new  bridge  to  Charlestown.  A  large  num- 
l)er  of  plans  for  work  at  the  Improved  Sewerage  Pumi)ing- 
Station ;  also  plans  and  specifications  for  an  iron  bridge  on 
Beacon  street,  and  for  an  office  and  stable  on  Chelsea  bridge, 
have  been  made. 

Detail  pldns  for  the  iron  bridge  for  the  Broadway  exten- 
'sion  are  now  in  progress. 


Eeport  of  City  Engineer. 


23 


B.— WATER  WORKS. 

Sudbury  River  Hesewoirs.  —  During  the  first  five  months 
of  the  year  1880  the  water  in  all  the  reservoirs  remained  at 
or  near  the  crests  of  the  dams,  and  for  the  greater  portion  of 
the  time  the  water  was  wasting-  at  tlio  overflow^  of  dam  No. 
1.  After  August  1  the  water-level  of  reservoir  No.  1  slowly 
fell,  until  on  the  first  of  January,  1881,  it  stood  2.48  feet 
below  the  top  of  the  flash-boards. 

During  the  summer,  owing  to  the  presence  of  alg;e  in 
reservoirs  Nos.  1  and  3,  the  supply  for  the  city  was  drawn 
mainly  from  reservoir  No.  2,  until  August  18,  when  the 
surface  of  that  reservoir  was  8.93  feet  below  the  crest  of  the 
dam.  From  that  time  until  the  2d  of  November  the  supply 
was  drawn  from  reservoir  No.  3,  and  on  October  30  the 
water-level  of  this  reservoir  w\as  15.65  feet  below  the  crest 
of  the  dam.  Reservoir  No.  2  meanwhile  had  filled  to  within 
2h  feet  of  the  top  of  the  dam,  and  during  the  last  two  months 
of  the  year  the  supply  was  drawn  from  that  reservoir.  On 
the  first  of  January,  1881,  the  surface  of  reservoir  No.  2 
was  5.70  feet  below  the  crest  of  the  dam,  and  reservoir 
No.  3  was  11.47  feet  below  the  corresponding  point. 

During  the  year  6,230,200,000  gallons  have  been  drawn 
from  the  Sudbury-river  works  for  the  supply  of  the  city  as 
follows  :  — 


Amount  sent  to 
Chestnut  Hill  Reservoir 

Amount  sent  to 
Lake  Cochituate. 

Total. 

January 

673,600,000 

228,400,000 

902,000,000 

February 

604,100,000 

11,300,000 

615,400,000 

jNlarch     . 

268,400,000 

8,200,000 

276,600,000 

April 

348,000,000 

161,300,000 

509,300,000 

May        . 

460,000,000 

280,800,000 

740,800,000 

June 

398,600,000 

136,700,000 

535,300,000 

July 

378,400,000 

378,400,000 

August  . 

592,000,000 

592,000,000 

September 

445,500,000 

445,500,000 

October . 

434,600,000 

434,600,000 

November 

398,200,000 

398,200,000 

December 

402,100,000 

402,100,000 

Totals     . 

5,403,500,000 

826,700,000  6,230,200,000 

Daily  averages 

14,763,660 

2,258,740 

17,022,400 

The  daily  average  amount  supplied  to  the  city  from  the 
Sudbury  river  during  the  year  was  17,022,400,  or  64  per 
cent,  of  the  total  consumption. 

The  average  daily  yield  of  the  river  for  the  past  six  years 
has  been  as  follows  :  — 


24  City  Document  No.  25. 


Total  yield. 

Daily  average. 

Rainfall.    Percentage. 

1875 

27,593,700,000 

75,599,200 

45.49 

44.88 

1876 

32,309,900,000 

88,278,400 

49.563 

48.24 

1877 

34,444,750,000 

94,369,200 

44.018 

57.90 

1878 

41,202,000,000 

112,882,200 

57.931 

52.63 

1879 

25,528,900,000 

69,942,200 

41,419 

45.33 

1880 

16,561,(300,000 

45,250,300 

38,177 

32.71 

Lalie  Cochituate.  —  On  the  first  of  January,  1880,  the  sur- 
face of  Lake  Cochituate  was  7.86  ft.  below  high-water  mark  ; 
from  Jan.  1  to  May  1,  the  water  was  rising,  standing  Feb. 
1,  129.28;  March  1,  ]32.00;  April  1,  132.88,  and  May  1, 
134.10  above  tide  marsh  level.  During  the  month  of  May  it 
remained  near  this  grade,  and  after  July  1  it  steadily  fell, 
until,  on  Jan.  1,  1881,  it  was  125.62  above  tide-marsh 
level,  or  8.74  feet  below  high-water  mark. 

Mystic  Lake.  —  At  the  beginning  of  the  year  1880,  the 
water  in  Mystic  Lake  was  1.71  ft.  above  tide-marsh  level, 
or  5.88  ft.  above  the  conduit  invert.  Jan.  25  it  had  risen 
to  6.65  ft.,  and  was  allowed  to  waste  at  the  outlet  dam. 
The  waste  continued  until  April  28,  and  from  May  1  to  12, 
since  which  time  no  water  has  passed  over  the  dam.  From 
the  middle  of  May  the  surface  of  the  lake  fell,  standing ' 
July  1,  3.26;  Aug.  27,  1.50,  or  at  the  top  of  the  conduit; 
September  1,  1.34,  and  on  October  1,  0.92.  On  the  3d 
of  September  the  Water  Board  authorized  the  erection  of 
pumping  machinery  at  the  lake,  to  raise  the  water  into  the 
conduit. 

The  engines  and  pumps  which  were  used  at  Lake  Cochitu- 
ate in  1871  and  1874,  for  a  similar  purpose,  were  transported 
to  Mystic  Lake,  and  placed  in  position  upon  temporary  plat- 
forms which  had  been  built  to  receive  them.  October  2, 
as  the  conduit  by  gravitation  would  no  longer  furnish  the 
supply,  the  pumps  were  started  and  were  continued  in  oper- 
ation until  the  17th  of  January,  1881. 

On  the  25th  of  October  the  lake  surface  was  3.18  feet 
below  tide-marsh  level,  or  only  one  foot  above  the  conduit 
invert;  the  lowest  point  ever  reached.  Jan.  1st  it  was  1.66 
feet  below  tide-marsh  level.  At  the  present  time  (Feb.  1) 
it  is  0.41  ft.  above  tide-marsh  level,  or  6.59  ft.  below  high- 
water  mark. 

Consumption.  —  The  average  daily  consumption  for  each 
month  of  the  year  has  been  as  follows  :  — 


Report  of  City  Engineer. 


25 


From  the  Sudbury 
and  Cochituate  Work 

From  the 
s.    Mystic  Works. 

Total. 

January . 

.     25,817,600 

10,511,280 

36,328,880 

February 

.     27,625,800 

11,616,250 

39,242,050 

March     . 

.     23,095,700 

10,324,320 

33,420,020 

April 

.     22,670,700 

9,400,930 

32,071,630 

May 

.     25,238,200 

9,962,210 

35,200,410 

June 

.     27,795,400 

10,891,060 

38,686,460 

July 

.     26,951,800 

10,051,540 

37,003,340 

August  . 

.     28,175,100 

9,754,150 

37,929,250 

September 

.     28,734,400 

9,591,890 

38,326,290 

October . 

.     27,487,900 

7,634,890 

35,082,790 

November 

.     26,458,400 

6,245,890 

32,704,290 

December 

.     28,010,500 

6,778,050 

34,788,550 

Averages 

.     26,500,000 

9,387,880 

35,887,880 

From  the  above  it  appears  that  the  daily  average  consump- 
tion from  the  Sudbury  and  Cochituate  works  has  been 
26,500,000  gallons,  an  increase  of  3.1  per  cent,  over  that  of 
1879  ;  from  the  Mystic  works  9,387,880  gallons,  an  increase 
of  5.7  per  cent.,  and  from  the  combined  supplies  35,887,880 
gallons,  an  increase  of  3.8  per  cent. 

The  total  population  of  the  territory  supplied,  which  in- 
cludes, in  addition  to  the  city  of  Boston,  the  cities  of  Chel- 
sea and  Somerville  and  the  town  of  Everett,  is  about  412,000. 
The  daily  average  consumption  per  head  has,  therefore,  been 
about  87  gallons. 

Since  October  12  East  Boston  has  been  supplied  from  the 
Sudbury  and  Cochituate  works. 


Highland  High-Service  Works. 

The  average  daily  quantities  of  water  pumped  by  the  high- 
service  engines  at  the  Highland  station,  for  each  month,  have 
been  as  follows  :  — 


January, 

February, 

March, 

April, 

May, 

June, 


2,249,000 
2,340,500 
2,166,500 
2,174,133 
2,468,000 
2,799,300 


July, 

August, 

September, 

October, 

November, 

December, 


2,444,500 
2,432,500 
2,481,033 
2,342,500 

1,998,983 
2,199,000 


Making  a  daily  average  of  2,341,093  gallons  for  the 
year,  —  an  increase  of  4.1  per  cent  over  the  quantity 
pumped  in  1879. 


26  City  Document  No.  25. 

East  Boston  High-Service  Works. 

On  May  15,  1880,  the  Water  Board  was  authorized  to 
construct  high-service  works  for  the  supply  of  a  portion  of 
East  Boston.  Contracts  were  immediately  made  for  the 
pipes,  and  pumping-machinery  required.  Plans  having  been 
made  for  the  pumping-station  the  work  was  contracted  for, 
and,  on  the  arrfval  of  the  pipes,  the  whole  work  was  rapidly 
pushed.  On  the  12th  of  October  it  was  so  near  completion 
that  the  works  were  put  in  operation,  the  supply  being 
changed  from  Mystic  to  Sudbury  and  Cochituate. 

The  works  comprise  2  Worthingion  compound  high- 
pressure  pumps,  together  capable  of  raising  1,500,000 
gallons  in  24  hours ;  2  upright  tubular  boilers  for  supplying 
steam  for  the  pumps,  a  check-valve  with  a  by-pass  and 
safety-valve  for  regulating  the  pressure  upon  the  pipes,  and 
about  7,500  feet  of  main  pipe  connecting  with  the  former 
supply  mains. 

The  pumping-machinery  is  located  in  a  neat  wooden 
building,  on  Brooks  street,  in  the  reservoir  lot,  the  supply  for 
the  pumps  being  taken  from  the  20-inch  low-service  main 
which  supplies  the  district. 

The  territory  supplied  is  comprised  in  two  districts,  the 
"Eagle  Hill"  and  "Belmont  Square,"  containing  together 
about  850  buildings.  The  pumping-machinery  was  furnished 
by  H.  R.  Woi-thington,  of  New  York,  for  $8,400;  the 
engine-house  foundations  and  chimney  were  built  by  Fes- 
senden  &  Libby,  of  Charlestown,  for  $1,989.66  ;  and  the 
engine-house,  by  Herman  Drake,  of  East  Boston,  at  a  cost  of 
$2,205.  The  entire  work  has  been  completed  at  a  cost  of 
$23,000. 

Forty-eight-Inch  Main. 

During  the  last  session  of  the  Legislature  an  act  was 
passed,  granting  to  the  City  of  Boston  the  right  to  lay  a  new 
main  from  the  Chestnut-Hill  reservoir  to  the  city,  through 
the  town  of  Brookline,  and  on  March  20  an  order  was 
approved  by  the  Mayor,  authorizing  the  Water  Board  to 
expend  $280,000  for  the  pipes  and  special  castings  required. 
In  April  contracts  were  made  with  the  Warren  Foundry  & 
Machine  Co.,  of  Phillipsburg,  N.J.,  and  R.  D.  Wood  & 
Co.,  of  Philadelphia,  for  the  pipes  and  special  castings.  In 
"consequence  of  a  ftdl  in  the  price  of  iron  the  pipes  were 
purchased  for  $40.95  per  ton,  or  about  $70,000.  less  than  the 
amount  appropriated.  This  amount  has  since  been  applied 
to  defray  the  cost  of  laying  the  main,  and  the  entire  work 
will  be  completed  within  the  first  appropriation. 

The  work  of  laying  the  pipes  was  commenced  on  June 
23,  and  at  12  M.  of  Nov.  29  water  was    supplied  to  the 


Report  of  City  Engineer.        *  27 

city  through  the  new  main,  direct  from  Chestnut-Hill  reser- 
voir. The  pressure  throughout  the  city  was  immediately 
increased  about  10  feet. 

A  30-inch  main,  to  be  charged  to  this  appropriation,  still 
remains  to  be  laid  in  Francis  street,  to  connect  the  40-inch 
with  the  30-inch  and  36-inch  mains,  originally  laid  to  supply 
the  city,  and  it  is  expected  that  this  connection  will  still 
further  increase  the  head. 

The  new  main  starts  from  the  effluent  gate-house,  at 
Chestnut-Hill  reservoir,  and  after  connecting  with  a  48-inch 
pipe,  which  is  laid  around  the  reservoir  from  the  terminal 
chamber  of  the  Sudbury-rivcr  conduit,  it  passes  through  Bea- 
con street  to  the  junction  of  Brookllue  avenue,  —  a  distance  of 
16,300  feet,  — where  it  connects  with  the  40-inch  main  from 
Brookline  reservoir.  At  the  junction  of  Haiward  street,  in 
Brookline,  a  branch  has  been  put  in  for  a  contemplated  con- 
nection with  the  Mystic  works,  and  a  gate  is  located  in  the 
main  at  this  point.  Gates  to  control  the  flow  of  the  water 
have  also  been  placed  on  the  connection,  at  Chestnut-Hill 
reseiwoir  and  at  Brookline  avenue.  Near  St.  Paul  street,  in 
Brookline,  a  section  of  the  pipe  line,  780  feet  in  length,  is 
supported  by  a  pile  foundation,  consisting  of  spruce  piles 
driven  in  pairs,  at  distances  apart  of  5  feet  crosswise, 
and  6  feet  lengthwise  of  the  trench,  and  capped  crosswise 
with  10-inch  by  10-inch  spruce  caps,  8  feet  long. 

The  cost  of  the  main  was  largely  increased  by  the  necessity 
of  removing  and  relaying  many  of  the  water  and  gas  pipes 
in  the  town  of  Brookline. 

All  of  the  work  has  been  done  by  day's  labor,  under  the 
direction  of  E.  li.  Jones,  Superintendent  of  the  Eastern 
Division  of  the  Sudbury  and  Cochituate  Department. 

Miscellaneous  . 

Exclusive  of  the  new  48-inch  main,  about  9  miles  of 
main  pipe  have  been  laid  during  the  year,  and  59  hydrants 
established  by  the  Sudbury  and  Cochituate  Department,  and 
about  2  miles  of  the  wrought-iron  and  cement  pipe  in  the 
Charlestown  District  have  been  replaced  by  coated  cast-u*on 
pipe. 

The  plans  of  the  pipe  system  have  been  corrected  as  usual, 
and  a  skeleton  plan  of  the  high-service  system  has  been 
completed. 

C.  —  ADDITIONAL     SUPPLY. 

SUDBURY-RlVER    WORKS. 

At  the  beginning  of  1880  the  whole  system  of  the  Sud- 
bury-river  Works,  although  not  entirely  completed  in  all  its 
details,  was  in  practical  working  order.     The  last  contracts, 


28  City  Document  No.  25. 

four  in  number,  were  finally  completed  in  the  early  part  of  the 
year  :  three  of  them  were  for  the  gate-houses  connected  with 
each  of  the  dams ;  the  other  for  the  erection  of  a  foot-bridge 
with  flash-boards  on  the  crest  of  dam  No.  2.  A  consider- 
able amount  of  minor  work  was  also  done  by  day's  labor,  under 
the  direction  of  this  department,  to  complete  the  dams  and 
reservoirs,  and  to  improve  their  borders.  At  dam  No.  2  the 
impervious  hearting  of  the  embankment  was  extended  several 
hundred  feet  on  the  high  gi-ounds,  near  the  farm  buildings  of 
Jos.  A.  Merriam,  by  means  of  sheet  piling  and  by  puddling. 
The  local  engineering  force,  reduced  to  three  assistants  after 
the  month  of  March,  and  subsequently  to  one,  was  entirely 
dispensed  with  in  October.  It  had  charge  of  the  work  of 
construction,  of  the  maintenance  of  the  portion  of  the  works 
above  the  main  gate-house  in  Farm  Pond,  and  also  com- 
pleted the    final   records    of  the  entire  work. 

On  the  24th  of  September  the  following  letter,  which  ex- 
plains itself,  was  sent  to  the  Water  Board  :  — 

Leonard  R.  Cutter,  Esq.,  Chairman  of  Boston  Water  Board:  — 

Dear  Sir,  —  The  work  of  building  the  Sudbury-river  conduit,  and  the 
three  basins  authorized  by  the  City  Council,  is,  so  far  as  this  department 
is  concerned,  com^oleted,  and  any  further  expenses  on  this  work,  excejit 
settlement  of  outstanding  claims,  should  be,  in  my  oijiniou,  charged  to 
maintejiance,  and  not  to  construction. 
Respectfully, 

iiEXRY   M.  WIGHTMAN, 

City  Engineer. 

And  on  October  15th,  in  accordance  with  a  vote  of  the 
Water  Board,  the  portion  of  the  work  left  in  charge  of  this 
department  was  transferred  to  the  Superintendent  of  the 
Western  Division  of  the  Sudbury  and  Cochituate  Works. 

As  this  transfer  closes  the  construction  period  of  the  Sud- 
bury-river  works,  as  they  were  contemplated  in  the  original 
estimates,  it  may  not  be  out  of  place  to  recall  the  principal 
data  of  this  important  scheme. 

In  1871  and  1872  Sudbury  river  was  selected  as  the  new 
source  of  water-supply  for  Boston.  The  reservoirs  for  the 
storage  of  its  waters,  and  the  conduit  through  which  they 
were  to  be  conveyed  from  Farm  j)ond  to  Chestnut-Hill 
reservoir,  were  located,  and  plans  were  made  for  the  build- 
ing of  these  structures. 

In  1872,  also,  temporary  works  were  built  to  connect  at 
once  Sudbury  river  with  Lake  Cochituate. 

In  1873  the  first  contract  was  let  for  a  portion  of  the  con- 
duit (the  tunnel  in  Ne\yton)  ;  but,  owing  to  new  investiga- 
tions ordered  by  the  City  Council  in  the  latter  part  of  1873 
and  in   1874, 'to  ascertain  whether  Sudbury  river  was  the 


Report  of  City  Engineer.  29 

best  source  of  supply,  no  other  work  was  undertaken  until 
the  beginning  of  1875, 

The  main  portion  of  the  conduit,  commenced  in  1875,  was 
finished  in  1877,  and  put  in  practical  use  early  in  1878. 

The  three  dams  and  reservoirs  were  commenced  in  1876. 
Reservoir  No.  3  was  filled  for  the  first  time  in  December, 
1878  ;  Reservoir  No.  1,  and  also  No.  2,  in  1879. 

During  the  progress  of  construction  the  original  design 
was  followed  with  but  few  changes  ;  some  important  addi- 
tions were  made,  but  the  cost  of  the  whole  work  has  been 
kept  inside  of  the  first  estimates. 

On  October  1,  1880,  the  total  cost  of  the  works  of  "addi- 
tional supply"  was  $5,23-4,678.02. 

The  water  damages,  not  included  in  the  original  estimates, 
amounted  to  $543,190.64. 

Although  the  final  completion  of  the  "  additional  supply  " 
is  so  recent,  it  will  be  remembered  that,  as  early  as  1872, 
the  water  from  Sudbury  river  was  used  for  replenishing 
Lake  Cochituate,  and  that,  from  the  beginning  of  1875,  a 
large  proportion  of  the  general  supply  has  been  taken  from 
the  new  source.  This  proportion  has  increased  every  year 
at  such  a  rate  that  the  present  supply  taken  from  the  river 
has  reached  the  limit  of  capacity  for  which  the  present  reser- 
voirs were  intended. 

When  Sudl)ury  river  was  reported  upon  for  the  first  time 
(City  Document  No.  29,  1873)  it  was  shown  that  no  less 
than  eight  storage  basins  would  be  necessary  to  develop  its 
full  resources.  The  conduits,  and  all  their  appertaining 
structures,  are  built  in  proportion  with  the  ultimate  capacity 
of  the  supply  ;  but  it  was  not  advisable  to  build  at  once  all 
the  contemplated  reservoirs.  The  consumption  of  the  city 
1)eing  then  about  19,000,000  gallons  per  day,  it  was  decided 
to  build  three  storage  reservoirs  only,  and  to  postpone  the 
construction  of  others  until  the  increasing  wants  of  the 
city  should  require  them. 

Now,  with  an  average  daily  consumption  for  1880  of 
26,500,000  gallons,  which  during  the  severe  weather  of  this 
winter  has  occasionally  reached  a  maximum  of  moi'e  than 
40,000,000  gallons  per  day,  the  time  has  already  come  to 
provide  additional  storage.  This  necessity  has  been  forcibly 
illustrated  by  the  condition  of  the  supply  for  the  last  year, 
during  which  the  rainfall  has  been  exceptionally  small,  and 
the  drought  unusually  severe. 

Thus  it  happens  that  almost  at  the  same  time  that  the 
original  works  are  reported  as  finally  completed,  a  new  ap- 
propriation of  $55,000  has  been  made  for  the  purchase  of 
land  and  for  the  investigations  necessary  for  an  additional 
storao:e  reservoir. 


30  City  Document  No.  25. 

Owing  to  the  severity  of  the  season  surveys  cannot  be 
prosecuted  to  any  advantage  at  present ;  but  borings  are 
being  made  to  ascertain  as  soon  as  possible  the  best  location 
for  a  new  dam,  and  the  nature  of  the  ground  in  which  its 
foundations  are  to  be  established.  When  the  necessary  in- 
formation is  obtained  the  work  of  construction  should  be 
commenced  and  prosecuted  without  delay. 

The  extension  of  the  storage  system  is  not  likely  to  be 
limited  to  this  structure  for  any  length  of  time.  Unless 
some  method  is  adopted  for  reducing  the  waste  of  water, 
still  larger  storage  facilities  must  be  provided  in  the  near 
future  to  accommodate,  in  a  dry  year,  the  constantly  increas- 
ing consumption. 

D.— IMPROVED  SEWERAGE. 

A  general  description  of  this  system,  accompanied  by  a 
map  and  plates,  showing  sections  of  the  sewers,  and  elevation 
and  plan  of  the  Leavitt  pumping- engines,  was  given  in  the 
last  annual  report. 

The  Leavitt  engines,  wliich  are  being  built  under  a  con- 
tract by  the  Quintard  Iron  Works,  of  Xew  York,  are  in  a 
forward  state  of  completion ;  but  will  not  be  finished  in  the 
contract  time.  Payments  on  account  of  these  engines  to 
the  amount  of  $100,569.62  have  been  made,  and  material  of 
the  value  of  $65,005.45  has  been  delivered  at  Old  Harbor 
Point,  where  the  contractor  has  erected  a  storehouse  and 
machine-shop  for  temporary  use. 

Negotiations  with  Mr.  Corliss  for  the  building  of  two 
pumping-engines,  from  liis  own  designs,  after  having  been 
carried  on  by  the  committee  at  intervals  during  the  year 
without  attaining  a  satisfactory  result,  were  finally  closed  on 
December  23,  1880.  A  contract  was  made  with  the  success- 
ors of  Mr.  Henry  R.  Worthington,  of  New  York,  on  Decem- 
ber 30,  1880,  for  two  pumping-engines  of  the  Worthington 
Duplex  type,  to  take  the  place  of  the  Corliss  engines.  Each 
of  the  engines  is  to  be  of  sufiicient  capacity  to  raise  25,000,- 
000  U.S.  gallons  of  sewage  in  twenty-four  hours  to  a 
maximum  height  of  43  feet.  The  contract  price  for  the  two 
engines  is  $90,000 ;  but  no  payment  is  to  be  made  until  they 
are  in  running  order  at  the  pumping-station,  and  have  passed 
a  satisfactory  test  by  the  city. 

A  contract  was  made  October  11,  1880,  with  Messrs.  Ken- 
dall &  Roberts,  of  Cambridgeport,  for  building,  and  erecting 
at  the  pumping-station,  two  steel  boilers  to  furnish  steam  for 
the  Leavitt  engines. 

These  boilers  are  of  the  horizontal  fire-box  tubular  form,  31 
feet,  9|  inches  long  over  all,  and  of  a  mean  diameter  of  6  feet  8 


Eeport  of  City  Engineer.  31 

inches  in  the  cylindrical  portions.  Each  boiler  has  two  fire- 
boxes, 3  feet  6  inches  wide  at  the  bottom,  5  feet  2  inches  high, 
and  11  feet  long,  connecting  with  a  combustion  chamber  4  feet 
long.  The  steel  in  the  outer  shell  is  -^^  inch,  and  in  the  fire- 
boxes and  combustion  chamber,  r^^  inch  thick.  Each  boiler 
contains  132  lap-welded  wfought-iron  tubes,  3-iiich  external 
diameter  and  15  feet  1  inch  long.  The  internal  bracing  of 
the  boilers  consists  of  knee-braces,  screw-stays,  and  rods,  all 
of  Ulster  iron.  The  boilers  are  connected  to  a  steam  drum, 
2  feet  in  diameter  by  14  feet  6  inches  long,  made  of  steel 
ySg  inch  thick. 

The  fire-box  ends  of  the  boilers  rest  upon  cast-iron  ash- 
pits, and  the  cylindrical  portions  are  supported  by  cast-iron 
cradles,  three  to  each  boiler.  The  boilers  are  provided  with 
the  necessary  hand  and  man  holes,  safety-valves,  blow-ofif 
pipes,  etc. 

The  feed-pumps  for  the  boilers  are  two  in  numljer,  of  the 
Worthingion  Duplex  pattern,  6  inches  X  3^  inches  X  6  inches, 
their  suction-pipes  being  connected  with  a  small  water-heater, 
into  which  their  exhaust  steam,  and  that  of  the  cold-water 
.pumps  for  the  Leavitt  engines,  is  led. 

The  feed  water  is  to  be  led  through  brass  pipes,  either 
direct  to  each  boiler,  or  through  a  heater  composed  of  80 
seamless  brass  tubes,  2|  inches  inside  diameter,  and  14  feet 
10  inches  long  between  connecting  beams,  which  is  placed 
inside  of  the  smoke-flue  leading  from  the  boilers  to  the 
chimney. 

After  erection  the  boilers  are  to  be  covered  with  a  lag- 
ging of  non-conducting  material. 

Samples  of  the  steel  and  iron  used  in  the  boilers  were 
tested  at  the  U.  S.  Arsenal  at  Watertown,  Mass.,  and  satis- 
factory results  obtained. 

The  boilers  are  completed,  but  not  yet  delivered  at  the 
pumping-station.  The  contract  price,  including  feed-pumps, 
heater,  and  all  other  appurtenances,  was  $19,950. 

The  sum  expended  to  January  1,  1881,  chargeable  to  the 
appropriation  for  "Improved  Sewerage,"  is  $866,374.47. 

Extracts  from  the  report  of  Mr.  E.  C.  Clarke,  principal 
assistant  engineer  on  the  improved  sewerage  system,  showing 
the  progress  of  the  work,  and  other  information  in  relation 
to  it,  are  appended. 

EXTRACTS  FROM  MR.   CLARKE'S  REPORT. 

Herewith  is  submitted  a  report  of  work  done  and  progress  made  in 
consti"ucting,  the  new  system  of  sewerage,  fi'om  Jan.  1,  1880,  to  Jan.  1, 
1881.  The  following  tabular  statement  shows  the  sizes  and  lengths  of 
main,  intei'cepting  and  outfall  sewers  built,  with  the  jwrtions  of  them 
completed  during  the  past  year,  and  is  followed  by  a  more  detailed  ac- 
count of  the  work  upon  each  section :  — 


32 


City  Document  No.  25. 


TABXir,AR    STATEMEIVT    OF    PROGRESS - 


Section. 


1.  Main  . 

2.  Main  . 

3.  Main  . 

4.  Main  . 
4^.  Main  . 

6.  Main  . 

6.  Main  . 

1.  West  Bide 

2.  West  Side 

3.  West  Side 
1.  East  Side  . 

1.  Stony  Brooli  . 

2.  Stony  Brook   . 

1.  South  Boston  . 

8.  South  Boston  . 

4.  South  Boston  . 
Pumping-station 

2.  Outfall  Sewer     . 

3.  Outfall  Sewer    . 


Locality. 


In  Camden  st.,  from  Huntington  ave.  to  Tremont  st 

In  Camden  St.,  from  Tremont  st.  to  Washington  st 

In  Washington  st.  and  E.  Chester  park,  from  Camden  st.  to  Albany  st 

In  E.  Chester  park  extension,  from  Albany  st.  to  Magazine  st 

In  E.  Chester  park  extension,  from  Magazine  st.  to  Clapp  st 

In  Clapp  and  Mt.  Vernon  sts.,  from  E.  Chester  park  extension  to  O.  C.  Railroad 

In  Mt.  Vernon-st.  extension,  from  O.  C.  Railroad  to  Old  Harbor  Point  .... 

In  Camden,  Falmouth,  Dalton,  and  Hereford  sts.,  from   Huntington  ave.  to 
Beacon  st 

In  Beaconst.,  from  Hereford  st.  to  Charles  st 

In  Charles  st.,  from  Beacon  st.  to  Cambridge  st 

In  Albany  St.,  from  E.  Chester  park  to  Dover  st 

In  Tremont  and  Cabot  sts.,  from  Camden  st.  to  Ruggles  st 

In  Cabot,  Hampshire,  Elmwood,  Ruggles  and  Tremont  sts.,  about  Stony  Brook 

In  Ninth  St.,  from  H  St.  to  N  st 

In  Von  Hillern  st..  Locust  St.,  Washington  ave.,  and  Hyde  St.,  from  Mt.  Vernon 
St.  to  Dorchester  ave 

In  Dorchester  ave.,  from  Hyde  st.  to  B  st 

Connecting  Main  Sewer  with  Filth-Hoist  and  Engine  Wells 

Tunnel  under  Dorehester  Bay,  from  O.  H.  Pier  to  Squantum  Neck  (excavation) 
Squantum  Neck  to  Moon  Island 

Totals • 


Report  of  City  Engineer. 


33 


IMPROVED    SEVTERAGE    COIVSTRTJCTIOIV. 


Size  in  feet  and  inches. 


7  ft.  Sin 

8  ft.  5  in 

8  ft.  5  in 

9  ft .   .   . 

9  ft 

(9  ft 

1 10  ft.  6  in 

10  ft.  6  in 

4  ft.  9  in.  X  5  ft.  6  in. 

1  4  ft.  9  in.  X  5  ft.  6  in 
(  4  ft.  X  4  ft.  6  in.  .   . 

4  ft.  X  4  ft-  6  in.    .   . 

5  ft.  S  in 

4  ft.  8  in 

J  4  ft.  6  in 

j  2  ft.  X  3  ft 

3  ft.  2  in 

(6  ft 

J  4  ft.  9  in.  X  5  ft.  6  in. 
(4ft.6in.  X3ft.    .   . 

4  ft.  9  in.  X  0  ft.  6  in. 

( 10  ft.  6  in 

f    9  ft 

7  ft.  6  in 

11  ft.  X  12  ft 


Length 
in  feet. 


1675.5 
1390.5 
1795. 
2504.5 

1894. 

3381. 
4088. 

4282. 

5043. 

1832. 

4524.5 

2135. 

3770. 

2717.5 

3739. 

3350. 


Built  prior  to 
Jan.  1,  18S0. 


1675.5 
1390.5 

1795. 
1200. 
489. 

2720. 

4088. 

4282. 

4923. 

1832. 

4524.5 

2135. 

2717.5 


2400. 


Built 
Jan.  1,  1881. 


1675.5 

1390.5 

1795. 

2321. 

1894. 

3381. 

4088. 

4282. 

4923. 

1832. 

4524.5 

2135. 

2200. 

2717.5 

3739. 


332. 


49178. 


Built  by 


P.  J.  Condon. 
P.  J.  Condon. 
John  Cavanagh. 
Charles  Linehan. 
City. 


Hoblitzell,  Condon,  and 
Hohlitzell,  and  City. 

Clinton  Beckwith,  and  J.  V. 
Quackenbush. 


City. 
City. 

Thos.  McCann. 

A.  H.  Delamater  &  Co.  and 
R.  A.  Malone. 

Myles  Tierney. 
City. 


Stephen  Connelly  &  Co.  and 
City. 


Charles  Linehan. 


Hoblitzell,  Condon,  and 
Hoblitzell,  and  City. 


City. 

R.  A.  Malone. 

W.  C.  Poland  &  Son. 


34  City  Document  No.  25. 


Section  4,  Main  Sewer. 

1,121  feet  of  this  sewer,  9  feet  in  diameter,  were  built  during  the 
year.  For  nearlj"  the  whole  distance  a  simple  12-inch  ring  of  brick- 
work, founded  on  the  clay,  proved  to  be  sufficiently  stable.  In  passing 
the  large  gas-holder  of  the  Boston  Gas-Light  Company  a  leak  into  the 
trench,  from  the  well  of  the  holder,  caused  some  apj^rehension,  but  was 
stopped  before  causing  damage.  As  a  precaution,  in  passing  within  35  feet 
of  the  holder  of  the  Roxbury  Gas  Company,  4-inch,  tongued  and  grooved, 
sheet  planks  were  driven,  and  the  trench  back-filled,  to  the  crown  of  the 
sewer  arch,  with  concrete.  No  esijecial  obstacles  were  encountered 
until  the  site  of  the  old  Roxbmy  canal,  recently  filled  by  the  city,  was 
reached.  Here  an  influx  of  tide-water,  along  the  loose  walls  of  the 
canal,  occasioned  much  trouble  and  delay.  The  sheet  planks  were 
backed  with  clay  without  success,  and  the  walls  had  finally  to  be  cut  off 
by  several  dams,  made  of  double  rows  of  planking,  filled  with  puddled 
clay.  The  contractor  spent  five  months  in  contending  with  these  diffi- 
culties, and,  just  as  they  seemed  to  be  surmounted,  the  inclemency  of  the 
season  obliged  him  to  suspend  operations  for  the  winter.  About  180 
feet  remain  to  be  built,  and  it  is  tioi:)ed  that  this  work  can  be  accom- 
plished early  in  the  spring ;  thus  completing  the  last  gap  in  the  main 
sewer,  from  its  begimiing  at  Huntington  avenue  to  its  end  at  old  Harbor 
Point.  A  side-enti"ance  and  boat-chamber  have  been  built  on  this  section, 
at  the  corner  of  East  Chester  Park  and  Swett  street,  to  aftbrd  convenient 
facilities  for  visiting-  the  sewer. 


Section  4i,  Main  Sewer. 

This  section,  woi'k  on  which  began  August  1,  1879,  was  completed  in 
October,  1880.  It  was  built  by  the  city,  mider  the  superintendence  of  Mr. 
H.  A.  Carson,  and  the  method  of  its  construction  was  described  in  last 
year's  report.  It  was  designed  to  withstand  slight  movements,  and,  as 
none  of  moment  have  been  noticed  in  the  filling  which  surrounds  it,  is 
believed  to  maintain  its  shape  and  grade. 

Section  5,  Main  Sewer. 

On  this  section  work  progressed  slowly  during  the  year.  No  diffi- 
culties were  encountei*ed  in  building  the  sewer  at  either  end  of  the  sec- 
tion, where  it  was  in  open  cut,  although  expensive  precautions  were 
required  in  j^assing  luider  the  Old  Colony  Railroad  ti'acks.  About  1,900 
feet  of  the  middle  of  the  section  were  built  by  tunnelling  through  con- 
glomerate rock  and  coarse  sand.  The  rock,  where  it  suiTounded  the 
trmnel,  presented  no  serious  obstacle  ;  but  the  sand  tended  to  run  into  the 
excavation,  and  required  close  sheeting  and  heavy  bracing  to  support  it. 
For  several  hundred  feet  the  sewer  grade  was  near  the  surface  of  the 
ledge,  and  the  latter,  being  very  irregular  and  Covered  with  boulders, 
tunnelling  operations  at  this  point  were  attended  with  considerable  diffi- 
culty ;  several  caves  occurred,  and  the  rate  of  j^rogress  was  veiy  slow. 
For  a  length  of  160  feet  the  ground  was  oj)ened  from  the  top,  and  the 
sewer  built  in  a  trench  about  45  feet  deep. 

Finally,  on  October  25,  1880,  the  contractors,  having  become  finan- 
cially embarrassed,  notified  the  committee  of  their  inability  to  comj^lete 
the  work,  and  definitely  abandoned  it.  The  city  at  once  took  possession, 
and  completed  the  short  distance  that  remained.  Although  the  tunnel 
had  been  well  built,  for  that  class  of  masonry,  it  was  found  to  leak  con- 
siderably in  places,  after  the  pumps  had  been  removed  from  their  wells, 
and  the  water-table  rose  above  the  sewer.  These  leaks,  however, 
could  be  successfully  calked.     The  process  consisted  in  i-aking  out  a  joint. 


Keport  of  City  Engineer.  35 

where  a  leak  occurred,  to  the  full  depth  of  the  brick,  and  driving  in 
sheet  lead  for  half  the  depth,  the  remainder  being  filled  with  cement. 

The  whole  section  is  now  complete,  except  a  little  more  calking,  and 
the  building  of  the  upper  portion  of  one  manhole. 

Section  6,  Main  Sewer. 

Although  the  whole  of  this  sewer  was  built  prior  to  1880,  it  was  foimd, 
as  stated  in  the  last  report,  that  for  about  1.50  feet  of  it  the  side-walls 
had  spread  somewhat,  and  the  crown  flattened,  necessitating  repairs. 
Although  even  this  portion  was  probably  stable,  it  was  not  considered 
wise  to  establish  a  precedent  of  accepting  any  impei'feet  work.  The 
contractor  was  accordingly  directed,  January  30,  1880,  to  reconstruct 
the  sewer  arch  at  this  point,  and,  on  his  declining  to  do  so,  the  work 
was  relet,  under  provisions  of  the  conti-act,  to  J.  V.  Quackenbush.  The 
trench  was  reopened,  the  sewer  uncovered,  and  its  arch  broken  down 
with  sledges.  It  was  fomid  that  the  12-inch  Akron  pipe,  extending 
under  the  sewer,  to  facilitate  drainage  during  construction,  was  broken  at 
this  i)oint,  and  the  water  from  it,  accumvilated  from  4,000  feet  of  trench, 
found  an  outlet^md  poured  over  the  side  of  the  invert.  This  water  was 
conti'olled  by  pumps,  but  was  found  to  have  washed  out  a  quantity  of 
sand,  causing  a  considerable  cavity  under  the  sewer  platform.  Five 
holes,  10  feet  apart  on  centres,  were  made  through  tlie  bottom  of  the 
sewer,  and  3-inch  wrought-iron  gas-pipes  inserted  in  them.  Two  of 
these  jjipes  were  about  30  feet  long,  and  three  othei\s,  for  vents,  were  6 
feet  long.  Constant  streams  of  grout,  made  fi'om  47  casks  of  neat, 
quick-setting,  Portland  cement,  were  forced  imder  a  25-feet  head, 
through  the  long  pipes  into  the  cavity,  till  it  was  filled,  as  shown  by 
the  cement  rising  in  the  short  pipes.  The  gi'out  hai'dened  satisfactorily, 
and  fm'nished  a  secure  foundation.  Special  ribs  were  cut  to  fit  the 
invert,  which  was  again  covered.  The  section,  thus  completed,  is  in 
good  conditiofi. 

Section  3,  South  Boston  Intercepting  Sewer. 

This  section  was  completed  in  December,  1880.  No  especial  difiicul- 
ties  were  encountered  in  building  it,  and  the  work  is,  on  the  Mdiole,  sat- 
isfactory. A  I'egulating  chamber,  similar  to  that  shown  on  the  plan,  is 
placed  in  the  line  of  the  sewer,  near  Kemp  sti'cet,  to  control  the  amount  of 
rain  from  the  whole  of  South  Boston  to  be  admitted  to  the  main  sewer. 
An  iron  fiushing-gate  is  also  provided  for  this  section,  and  where  the 
north  and  south  branches  of  the  South  Boston  sewer  come  together  they 
unite  in  a  bell-mouth  connection-chamber. 

Section  4,  South  Boston  Intercepting  Sewer. 

Xothing  worthy  of  note  occuri'ed  in  building  this  section  mitil  October 
25,  1880,  when  the  contractors,  the  same  as  for  Section  5,  main  sewer, 
abandoned  the  work.  The  city  at  once  assumed  control,  and  appointed 
ISIr.  C.  F.  Gilman  superintendent,  under  whom  the  sewer  was  com- 
pleted. The  amount  of  water  met  Avith  occasioned  some  difficulty,  but 
sound  work  was  obtained.  An  iron  flushing-gate  is  included  among  the 
appurtenances  to  this  section. 

Section  2,  Stony  Brook  Intercepting  Sewer. 

Work  on  this  section  was  begun  early  in  June,  1880.  It  is  built  by 
the  city,  with  Mr.  H.  A.  Carson  as  superintendent.  The  section  consists 
of  sevei'al  branches,  radiating  from  the  upper  end  of  Section  1,  at  the 
corner  of  Cabot  and  Ruggles  sti'eets,  and  is  intended  to  intercept  the 


36  City  Document  No.  25. 

whole  of  the  sewage  now  dischai'ging  through  various  outlets  into 
Stony  Brook.  The  main  branch,  4^  feet  in  diameter,  mainly  in  Hamp- 
shire street,  is  about  1,700  feet  long,  and  takes  the  sewage  entering 
the  brook  through  the  Elmwood  and  Hampshire  sti'eet  outlets.  It 
passes  twice  imder  the  brook,  low  enough  to  preserve  its  regular  grade 
and  shape.  The  other  branches  are  built  just  large  enough  to  enter 
conveniently,  being  2  by  3  feet,  egg-shaped,  with  the  smaller  end 
down.  Two  of  these  also  ci'oss  vmder  the  brook,  at  Tremont  street  and 
at  Ruggles  street. 

All  the  branches  unite  in  a  three-way  bell-mouth  chamber,  whence 
the  sewage  will  pass  through  the  regulating  chamber  shown  in  the  plan. 
As  will  be  seen,  the  a^jparatus  is  very  simple,  and  consists  of  stop- 
planks,  closing  the  sewer  fi'om  its  top  down  to  about  the  orilinary  flow 
line,  the  sewer  below  the  planks  being  lined  with  a  cast-iron  gate-frame 
or  seat,  curved  to  fit  the  invert,  and  also  vertically  to  coiTcspond  with 
the  plane  of  motion  of  the  cast-iron  gate  which  plays  ujj  and  down  in 
front  of  it.  The  gate  is  held  by  2  cast-iron  arms,  pivoted  by  a  3- 
inch  wrought-iron  shaft  in  2  bearings,  and  connected  by  vertical  arms 
at  their  ends  to  a  3-inch  square  bar.  To  the  ends  of  this  bar  are 
comiected  two  boiler-plate  floats,  jjlaced  in  wells  on  either  side  of  the 
sewer.  To  avoid  disturbance  to  the  motion  of  the  floats  by  waves, 
caused  by  the  rush  of  sewage  under  the  gate,  water  is  brought  to  tlie 
wells  thi'ough  a  5-inch  pi^Je,  as  shown,  from  a  jjoint  50  feet  below  the 
gate. 

The  city  sewers  are  connected  with  the  intercepting  sewers  by  short 
branches,  from  12  to  24  inches  in  diameter,  starting  from  sump-holes 
in  the  former.  Into  these  sump-holes  the  amount  of  sewage  to  be  taken 
will  fall,  and  over  them  will  flow  the  excess  of  rain  to  be  wasted.  The 
immediate  inlet,  at  the  l)ottom  of  the  sump,  consists  of  a  short  section 
of  iron  pipe,  with  an  iron  flap  valve  hinged  over  it,  the  latter  being 
closed  if  there  is  need  of  emptying  the  collector. 

As  the  city  sewers,  intercepted  by  this  section,  although  below  the 
level  of  high-water,  are  not  provided  with  tide-gates,  it  will  be  neces- 
sary to  provide  a  double  set  for  each. 

Pdmping-Station  Sewers. 

These  comprise  97  feet  of  10^-feet  sewer,  extending  fi'om  the  end  of 
Section  6,  main  sewer,  to  the  filth-hoist,  and  a  pair  of  9-feet  sewers, 
235  feet  long  in  all,  leading  from  the  same  sti'ucture  to  the  galleries 
connected  with  the  pump-wells  on  either  side  of  the  engine-house.  They 
were  built  by  Mr.  S.  H.  Tarbell,  supei'intendent  for  the  city.  A  salt- 
water well,  and  the  beginning  of  a  o^-feet  sewer  from  it,  have  also  been 
constructed  at  this  jioint,  for  the  purpose  of  bringing  sea-water  to  the 
pumps,  should  a  sufficient  quantity  of  sewage  not  be  supjjlied  by  the 
main  sewer. 

Pumpestg-Station  and  Filth-Hoist. 

The  filth-hoist  has  been  completed  to  grade  16,  except  setting  the 
cages,  machineiy,  and  some  other  iron-work.  The  sewers,  where  they 
connect  with  it,  have  granite  voussoirs  cut  to  form  bell-shaijed  groins. 
The  4  gate-openings  ai-e  formed  of  large  granite  blocks,  faced  with 
6-cut  work.  The  outside  walls  are  of  granite,  and  the  division  walls 
of  brick.  The  depth  of  the  sti-uctin-e  below  the  surface  of  the  gromid 
is  about  30  feet. 

The  foundation  walls  of  the  engine-house  are  also  completed  to  grade 
16.5.  These  walls,  aggregating  about  340  feet  in  length,  are  37.5  feet 
high,  and  9  feet  thick  at  the  bottom,  where  they  rest  on  24  inches  of 
timber  platform.     They  are  built  of  granite,  and  although  called  rubble 


CITY  or  BOSTOy^ 
JMPR  O  VED      SE  WERA  OE. 

or 
REGULATING   APPARATUS 

Sfojit/  JBrook  Jhtej'xieptin^  Sewei" . 

Jan.  i88 I 


V/y,.,.../../A//v...  v//,/.y//'////  ,//  ,  'A.//,.//,////.//'.///y//.\ 


Sectional  Elevation 


Sectional     Plan 


TntHilk'MicPnrMKfCiMlTwxmtXBtstsn 


Eeport  of  City  Engineer.  37 

masomy,  yet,  owing  to  the  sizes  and  shapes  of  the  stones  used,  and  the 
care  taken  in  selecting  and  laying  them,  resemble  more  nearly  a  fair 
quality  of  roughly  coursed  Ijloek-stone  work.  Two  of  the  engine  piers 
are  wholly,  and  2  others  jjartially,  completed,  including  the  setting  of 
cut-stones  and  iron-work  imbedded  in  the  masonry.  213  cut-stones, 
besides  those  dressed  on  the  ground,  were  furnished  by  the  Cape  Ami 
Granite  Co.,  under  a  contract  dated  ]\Iarch,  1880.  The  same  company 
also  furnished  70  stones  for  the  filth-hoist. 

Considerable  delay  in  building  the  engine  piers  was  occasioned  by  an 
uncei'taiuty  as  to  the  character  of  2  of  the  engines  which  were  to  rest 
on  tliem.  This  doubt  having  been  removed,  the  work  will  be  pushed 
rapidlv  to  completion.  A  poition  of  the  site  of  the  engine-house  has 
been  I'oofed  in  to  permit  the  laying  of  masomy  during  the  winter. 

In  iSlay,  1880,  a  conti-act  for  4,000,000  bricks,  to  be  used  in  con- 
structing the  engine  foundations  and  Dorchester  Bay  Tunnel,  was  con- 
cluded with  Messrs.  Stoddard  &  Hellier,  of  Bangor,  Me.,  and  over 
2,000,000  of  them  have  been  already  delivered,  and  are  housed  under  a 
temporary  wooden  structure.  Various  offices,  store-houses,  cement  and 
tool-sheds  and  workshops  have  been  built  in  the  vicinity  of  the  engine- 
house.     The  foundations  for  the  boiler-house  are  also  completed. 

A  large  portion  of  the  2  pumping-engines,  ordered  from  the  Quin- 
tard  h'on  Works,  of  Xew  York,  lias  already  been  delivered,  and  is  on 
the  gromid.  It  is  cared  for  by  the  contractors,  by  whom  the  engines 
are  also  to  be  erected. 

Section  1,  Outfall  Sewer. 

As  a  joreliminary  to  building  this  section,  which  consists  of  an  elevated 
double  sewer,  extending  about  1,200  feet,  from  near  the  engine-house, 
out  to  the  west  tunnel-shaft,  it  was  necessary  to  construct  a  pier  to  sup- 
port the  sewers.  The  work  of  building  this  pier,  called  Old  Harbor 
l^ier,  was  awarded  by  conti'act,  JNIarch  8,  1880,  to  Messrs.  Edwards, 
Deny,  G.  H.  Cavahagh,  J.  Cavanagh,  and  Sylvester.  The  work  cov- 
ered hj  tlie  contract  consists  of  a  gravel  pier  about  1,200  feet  long,  pro- 
tected on  its  sea  side  by  a  riprap  emljankment,  ballasted  with  broken 
stones  and  oj'Ster-shells,  and  on  its  landward  slope  by  layers  of  ballast 
and  riprap  ,and  terminated  at  its  easterly  end  beyond  the  shaft  by  a 
sea-wall  of  cut-stone  masonry,  resting  on  a  pile  foundation. 

In  the  rijirap  embankment  there  has  been  placed  27,096  tons  of  large 
stones,  and  6,579  yards  of  ballast,  and  it  is  nearly  finished ;  80,219  yards 
of  gravel  filling  are  in  place.  The  gravel  has  been  obtained  by  dredg- 
ing, and  is  dumped  from  scows  near  the  end  of  the  pier,  whence  it  is 
raised  and  placed  in  cars  by  a  dippei'-dredge,  a  small  engine  hauling 
the  cars  to  the  proper  places  for  dumping.  A  portion  of  the  piles  for 
the  sea-wall  foundation  are  driven,  and  the  stones  for  the  wall  itself  are 
cut  and  on  the  ground. 

This  work  was  stopped,  on  account  of  ice  in  the  bay,  Jan.  7,  1881,  but 
will  be  renewed  as  soon  as  the  season  permits. 

Section  2,  Outfall  Sewer. 

On  this  section,  commonh^  called  Doi'chester  Bay  Tunnel,  some  diffi- 
culties incidental  to  such  work  have  been  encountered,  l)ut  none  of  a 
serious  nature,  nor  am*  that  might  not  have  been  anticipated.  On  the 
whole  it  may  be  said  that  the  developments  are  quite  as  favorable  as 
were  expected  when  the  work  was  decided  on.  At  the  Ijeginning  of 
last  year  the  contractor,  ]\Ir.  ]\Ialone,  was  engaged  in  sinking  two  of  the 
three  shafts,  and  the  thii'd  was  begun  soon  after.  At  the  east  and  middle 
shafts  the  iron  cylinders,  which  fomi  their  upjoer  portions,  were  forced 
down  to  the  rock  at  depths  below  the  sm-face  of  the  ground,  of  21  and 


38  City  Document  No.  25. 

38  feet  i-espeetively.  These  shafts  were  continued  in  the  rock,  to  and 
below  the  gi"ade  line  of  the  tunnel,  which  is  established  abovit  142  feet 
below  the  elevation  of  city  base  or  mean  low  water.  Excavating  for 
the  tunnel,  from  these  shafts,  has  progressed  steadily,  with  two  short 
interruptions,  and,  at  these  points,  nearly  2,000  linear  feet  are  now  ready 
to  receive  the  brick  lining. 

From  the  end  of  the  inclined  portion  of  tunnel,  situated  midway 
across  Squantmii  neck,  a  heading  was  driven  downwards  for  about  400 
feet  and  then  stopped,  owing  to  the  difficulty  and  expense  of  removing 
the  water  which  accmuulated  at  its  face.  The  remainder  of  the  incline 
will  be  completed  from  the  east  shaft,  and  less  than  100  feet  of  it  remain 
to  be  excavated.  The  rock  met,  thus  far,  has  consisted  almost  entirely 
of  slate,  of  'different  degrees  of  hardness,  i^enetrated  with  planes  of 
bedding  and  cleavage,  which  renders  it  easy  to  work.  Contrary  to  ex- 
jDectation,  veiy  few  layers  of  conglomerate  have  been  fomid,  which 
fact  is  favorable  to  the  rapid  prosecution  of  the  work.  The  rock  yields 
no  more  water  than  was  to  be  expected,  the  maximum  quantity  to  be  dis- 
posed of  at  present,  at  any  shaft,  being  about  12,000  gallons  an  hour. 
Pumping  machineiy  of  insufficient  capacity,  provided  at  the  outset, 
caused  some  delay.  At  the  east  shaft  a  failure  of  the  pumps,  Aug.  20, 
1880,  allowed  the  drifts  and  shaft  to  fill  with  water,  which,  after  severial 
trials,  was  pmnped  out  again  and  controlled  October  21.  Work  at  the 
middle  shaft  was  stopped  about  Aug.  20,  until  a  new  and  larger  pump 
could  be  obtained ;  but  the  water  was  kept  down  in  the  interval. 

At  the  west  shaft  it  was  not  expected  that  the  cylinder  could  be  driven 
to  the  rock.  By  weighting  it  with  about  180  tons  of  iron  dross,  it  was 
finally  forced  down  into  the  clay  to  a  depth  of  about  60  feet  below  the 
surface  of  the  ground.  Below  this  point  a  square  shaft  was  excavated, 
with  great  ease,  in  plastic  clay,  jjeneti-ated  with  occasional  veins  of  fine 
sand,  but  yielding  little  water,  and  was  rather  hastily  timbered.  Just 
above  the  rock  was  encountered  a  bed  of  gravel  and  hard-pan,  bringing 
water  at  the  rate  of  aliout  10,000  gallons  an  hour.  At  tliis  time  move- 
ments were  observed  in  the  lining  of  the  shaft,  and  the  timbers,  on  one 
side,  near  its  l)ottom,  bulged  in.  It  was  not  considered  safe  to  allow  the 
shaft  to  remain  in  this  condition,  and  about  40  feet  of  it  were  retimbered, 
the  old  sticks  being  cut  oiit  with  chisels.  This  work  was  accomplished, 
but  not  Mdthout  great  difficult^'.  Althoiigh  the  quantity  of  water  was 
not  great,  the  cramped  dimensions  of  the  shaft  aftbrded  little  room  for 
the  jjumps,  or  opportunity'  for  supjjorting  them.  To  counteract  a  down- 
ward pressure  exerted  by  the  clay  upon  the  lower  part  of  the  shaft-lining, 
a  25ortion  of  it  was  suspended  from  the  cylinder  above  by  iron  bars,  and, 
on  these  breaking,  by  heavy  wire  cables.  After  the  shaft  had  been  re- 
timbered,  it  was  smik  to  grade  through  the  rock,  and  14  feet  of  tunnel 
excavated.  At  this  time,  August  3,  1880,  a  failure  of  thepum])S  allowed 
the  shaft  to  fill  before  they  could  be  removed.  It  was  jjumpedout  again 
on  Nov.  9  and  22,  by  means  of  a  special,  upriglit,  sinking-pump,  sus- 
pended from  above,  and,  although  maintained  on  each  occasion  for  a 
short  time,  was  finally  lost  through  some  failure  of  the  pump.  Nothing 
further  was  done  at  this  point  till  Januaiy  17,  1881,  when  the  shaft  was 
again  cleared  of  water,  a  new  pump  set  in  position,  and  the  work  of 
excavation  resumed. 

In  giving  lines  for  the  tunnel,  instiaiments  designed  by  the  engineers 
are  used,  by  means  of  which  a  beam  of  light  from  the  heading  is  reflected 
from  the  bottom  of  the  shaft  to  a  transit  at  its  top. 

Three  casualties,  resu^lting  in  death,  have  occurred  in  connection  with 
the  work ;  but  in  no  case,  as  is  believed,  through  negligence  on  the  part 
of  the  conti-actor.  One  man  fell  down  the  middle  shaft ;  another  was 
crushed  by  a  car  falling  on  him  ;  and  a  third,  not  employed  by  the  con- 
tractor, was  killed  while  unloading  coal. 

Li  detail,  the  tunnel  excavation,  completed  Jan.  1,  1881,  is  as  follows  : 


Keport  of  City  Engineer.  39 

From  west  shaft  eashvai'd 14  feet 

"     middle  shaft  westward 533   " 

"         "  "       eastward 546    " 

"     east  "     westward  ......  494    " 

"       "  "       eastward 417    " 

"       "        portal  westward 394   " 

Total 2,398  feet 

Section  3,  Outfall  Sewek  and  Moon  Island  Reservoir. 

The  contr-act  for  constructing  this  section  was  awarded,  April  20,  1880, 
to  William  C.  Poland  &  Son,  of  Boston.  The  contractors  began  about 
INIaj'  1  the  preliminaiy  work  of  constructing  offices,  sheds,  barns,  and  a 
wharf,  and  on  ^laj  17th  the  building  of  the  embankment  for  the  sewer 
was  commenced.  A  portion  of  this  embankment,  which  extends  oppo- 
site the  reservoir  and  ft'om  Aloon  Island  to  Squantum,  has  been  raised  to 
grade  16,  and  the  whole  of  it  is  as  high  as  grade  6.  Parts  of  it  are  also 
ballasted  and  riprapped. 

The  lower  portion  of  the  embankment  is  formed  of  dredged  material ; 
the  up2)er  of  gravel  dug  from  or  near  the  reservoir  site.  The  gravel 
has  been  moved  by  carts  ;  but  the  haul  being  now  too  long  to  make  this 
economical,  the  contractor  has  built  a  pile  trestle  the  whole  length  of  the 
embankment,  and  intends  to  use  steam  power  in  the  future.  In  all, 
nearly  150,000  cubic  yai'ds  of  material  have  been  put  into  the  embank- 
ment, of  which  54,000  were  excavated  from  the  site  of  the  reservoir. 

Two  hundred  linear  feet  of  the  sewer  have  been  constructed  at  its 
westerly  end,  on  Squantiuii  neck. 

For  a  short  time  during  the  last  summer  some  annoyance  was  experi- 
enced in  prosecuting  the  work  on  this  section  through  an  attemj^t  by  outside 
parties  to  prevent  access  to  the  work  by  closing  all  approaches  to  it.  The  city 
employes  were  obliged  to  remove  barriers  erected  against  them,  and,  an 
injunction  restraining  them  from  maintaining  a  ft-ee  passage  having  been 
refused  l^y  the  Suj^reme  Court,  no  further  trouble  was  experienced.  As 
a  precaution,  however,  a  right  of  way  ft'om  a  pulilic  road  to  the  sewer 
line  was  taken  by  the  city,  mider  the  act  authorizing  the  construction  of 
the  works. 

Work  on  this  section  ceased  Dec.  28,  on  account  of  the  inclemency  of 
the  season,  but,  it  is  hoped,  will  be  soon  resumed. 

Office  and  Other  Work. 

In  addition  to  the  above,  in  compliance  with  the  terms  under  which 
the  city  obtained  the  right  of  way  for  building  Section  3,  South  Boston 
Litercepting  Sewer,  a  road-way  has  been  graded  over  Hyde  sti'eet,  Wash- 
ington avenue,  and  Von  Hillern  street.  A  contract  for  doing  this  was 
awarded,  Feb.  28,  1880,  to  Charles  Linehan.  The  gravel  filling  is  brought 
by  the  Old  Colony  Railroad  Company  ft'om  a  bank  at  Quincy,  whei'e  it  is 
measui'ed  by  the  citj\  About  22,000  cubic  yards  have  been  already  de- 
livered, and  the  work  is  nearly  completed. 

To  i^rovide  an  ajjproach  for  colliers  and  other  vessels,  ft'om  the  ship 
channel  in  Dorchester  Bay  to  the  cit}'"s  wharf  at  Old  Harbor  Point,  a 
conti'act  was  concluded,  April  20,  1880,  with  the  Old  Harbor  Pier  Com- 
pany, for  dredging  a  navigable  channel,  about  2,200  feet  long,  12  feet 
deep  at  low  water,  and  aljout  100  feet  wide  on  top.  69,000  yards  of 
material  have  been  already  removed,  which  comprises  the  bulk  of  the 
work  contemplated. 

Early  in  January,  1880,  Mr.  Malone,  the  contractor  for  Dorchester 
Baj^  Tunnel,  desired,  in  order  to  facilitate  his  work  on  the  tmmel,  to  ex- 


40  City  Document  No  25. 

cavate  the  oi3en  cut  for  Section  3,  Outfall  Sewer,  on  Squantum  neck, 
adjoining  the  east  portal  of  the  tunnel. 

As  his  ternis  offered  were  favorable,  being  one  dollar  a  yard  for  rock 
excavation,  and  twenty-five  cents  a  yard  for  earth,  a  contract  with  him 
was  signed  Jan.  18,  1880,  and  the  trench,  for  its  length  of  600  feet,  is 
now  excavated  to  its  proper  size  and  grade. 

The  engineering  force  has  been  employed,  as  in  previous  years,  in 
making  surveys,  giving  lines  and  grades,  making  calculations,  measure- 
ments, and  estimates,  and  in  superintending  construction.  All  contract 
work  has  been  constantly  watched  by  comjjetent  inspectors,  and  force 
accomits  have  been  kept  of  all  labor  employed. 

The  difficult^'  of  reaching  portions  of  the  work  from  the  city  led,  in 
May,  1880,  to  the  establishment  of  an  engineering  party,  under  Mr.  F. 
P.  Stearns,  at  Squantum,  where  an  office  was  hired  for  them.  This 
paitj^  takes  charge  of  Dorchester  Bay  Tunnel  and  Section  3,  Outfall 
Sewer  and  Moon  Island  Eeservoir. 

Several  hundred  light  rod  borings  have  been  made  during  the  j^ear, 
principally  in  the  vicinity  of  Moon  Island. 

A  supplementary  series  of  float  experiments  were  made,  at  diff'erent 
stages  of  the  tide,  from  INIoon  Island,  and  their  result  confirmed  the 
previous  decision  as  to  the  j^roper  place  for  the  sewer  outlet. 

The  testing  of  cement  bought  by  the  city  or  by  contractors  has  con- 
stituted, as  heretofore,  an  imj^oftant,  if  minor  department  of  office-work. 
During  the  year  8,575  tests  in  all  have  been  made,  including  2,700  for 
experimental  jmrposes.  The  best  result  of  this  rigid  testing  of  cement  is 
that  little  of  inferior  quality  is  now  ofiered.  Of  17,906  casks  examined 
last  year,  but  516  were  rejected. 

From  one  to  three  draughtsmen  have  been  constantly  employed  in  the 
office,  making  record  and  working  plans,  and  a  clerk  is  employed  to 
keep  a  set  of  accomit-books,  and  to  perform  other  incidental  office  duties. 


E.— PARKS. 

The  report  of  the  Park  Commissioners  (City  Doc.  No. 
12,  1881)  gives  a  general  statement  of  work  now  in  progress 
on  the  Back-Bay  park ;  but  as  a  more  particular  statement 
and  description  of  tlie  portions  of  it  under  the  supervision 
of  this  department  may  be  of  value  for  future  reference, 
the  following  synopsis  is  given  :  — 

General  Work,  Filling,  etc. 

In  January  a  new  channel  for  Muddy  river  was  exca- 
vated through  the  marsh  near  the  easterly  side  of  the  park. 
This  channel,  together  with  the  culvert  previously  built 
through  the  road- way  across  Muddy  river,  near  the  Hun- 
tington entrance,  provided  for  the  flow  of  water  in  ])oth 
Muddy  river  and  the  old  channel  of  Stony  Brook,  so  that  it 
was  possible  to  continue  the  construction  of  the  boundary 
road  between  Huntino;ton  and  Parker  Hill  entrances  with- 
out  injury  to  private  parties.  The  filling  by  carts  was  con- 
tinued on  this  road  during  the  winter  and  early  spring,  under 
direction  of  the  superintendent  appointed  l)y  the  Park  Com- 
missioners.    The  Health  Department  was  allowed  to  dump 


Report  or  City  Engineer.  41 

ashes,  etc.,  witliin  the  park  limits,  until  about  the  first  of 
July. 

The  contract  for  filling  the  roadway  on  the  westerly  side 
of  the  park,  made  with  the  Boston  and  Albany  Railroad  Com- 
pany June  20,  1879,  was  continued  in  force  by  a  supple- 
mentary contract,  dated  January  28,  1880,  which  provided 
for  the  filling  of  the  site  for  the  Boylston-street  bridge  over 
the  park  water-way.  The  price  paid  for  the  additional  filling 
was  $3.25  per  square. 

The  extended  contract  was  completed  March  29,  1880, 
the  total  amount  deposited  being  24,176  squares,  at  $3.45, 
and  5,800  squares,  at  $3.25.  The  total  number  of  car-loads 
was  70,425.  The  gravel  was  brought  from  the  company's 
l)ank  at  Weston,  about  10  miles  from  the  park. 

June  1,  1880,  a  contract  was  made  with  the  Boston  and 
Albany  Railroad  Company,  for  the  filling  of  the  boundary 
road  from  the  point  near  Longwood  entrance,  to  which  it 
was  filled  under  the  previous  contract,  to  the  Huntington 
entrance.  This  work  was  begun  July  1,  and  is  now  nearly 
completed ;  30,981  car-loads  of  gravel  have  been  delivered 
underthis  contract,  amounting  to  12,197  squares.  The 
contract  price  is  $3.45   per  square. 

November  4,  1880,  a  supplementary  contract  was  made 
to  provide  for  the  filhng  of  the  portion  of  the  park  roadway 
between  the  Huntington  entrance  and  Boylston  street.  The 
price  to  be  paid  is  $3.20  per  square. 

Huntington  entrance  has  been  partially  filled  with  surplus 
earth  from  the  Sewer-Department  excavations  on  the  im- 
provement of  the  channel  of  Stony  Brook,  and  also  with 
surplus  earth  from  the  excavations  on  the  Improved  Sewer- 
age system,  on  Hampshire  and  Ruggles  streets.  The  number 
of  cart-loads  deposited  by  the  Server  Department,  to  De- 
cember 31,  was  21,702,  and  by  the  Improved  Sewerage 
Department,  2,370.  These  quantities  are  the  net  amounts 
left  after  the  deduction  of  the  loads  which  were  exchanged 
for  sand.  For  an  account  of  the  filling  of  the  Beacon  en- 
trance see  "  Commonwealth- Avenue  Extension." 

Tallymen  are  employed,  who  keep  an  account  of  the  num- 
ber of  cars  removed  from  the  different  gravel-banks  for  the 
contract  work,  and  also  the  number  delivered  on  the  work. 

Boylston-Street  Arch  Bridge. 

At  a  distance  of  about  300  feet  southwardly  from  the 
Boston  and  Albany  Railroad  the  park  pond  is  to  be  crossed 
by  an  elliptical  arch  bridge,  which  is  on  the  extension  of 
Boylston  street,  through  the  park.      The  water-way  is  nar- 


42  City  Docttment  No.  25. 

rowed  at  this  point  to  a  width  of  60  feet,  and  the  arch  which 
spans  it  is  intended  by  Mr.  Ohnsted,  the  landscape,  and 
Mr.  Richardson,  the  consulting,  architect  of  the  Park  Com- 
missioners, to  be  the  most  prominent  feature  of  the  park. 

The  bridge  is  to  have  a  width  at  the  westerly  end  of  about 
141  feet,  and  at  the  easterly  end  of  about  111  feet.  The 
arch  which  forms  the  bridge  will  be  straight  at  the  southerly 
end  and  askew  at  the  northerly  end.  The  span  is  to  be  60 
feet  at  right  angles  to  the  water-way,  but  at  the  skew  end 
the  span  at  the  face  of  the  arch  is  67  feet ;  the  rise  is  to  be  18 
feet,  measured  from  the  water  line  or  grade  8.  The  abut- 
ments, spandrel  walls,  and  faces  of  the  arch  will  be  granite ; 
the  intermediate  portions  will  be  brick. 

A  contract  for  building  the  foundations  and  abutments  for 
the  arch  was  made,  Sept.  28,  1880,  with  Mr.  Isaac  A.  Syl- 
vester, of  Newton,  the  contract  price  being  $38,647.  Before 
the  plans  and  specifications  for  the  work  were  completed  a 
careful  examination,  by  means  of  soundings  and  borings, 
was  made  of  the  materials  composing  the  substrata  at  the 
point  of  location. 

The  result  of  this  examination,  which  was  supplemented  by 
driving  trial  piles,  while  it  indicated  unmistakably  the  practi- 
cability of  and  necessity  for  a  pile  and  platform  foundation 
for  the  westerly  al>utment,  was  not  so  positive  with  regard 
to  the  foundation  for  the  easterly  abutment.  The  substratum 
into  which  the  piles  will  have  to  be  driven  for  the  easterly 
abutment  is  a  very  compact  sand,  and,  as  the  number  of  piles 
required  is  very  large,  it  was  thought  somewhat  doubtful  if 
they  could  be  driven  into  the  material ;  provision  has  there- 
fore been  made  in  the  contract  for  substituting  a  foundation 
of  hydraulic  cement  concrete. 

The  foundation  for  the  east  abutment  is  to  consist  of  rows 
of  spruce  piles,  2^  feet  apart,  each  row  capped  with  10  x  12 
inches  hard-pine  timber,  with  the  spaces  between  the  caps 
and  around  the  heads  of  the  piles  filled  to  a  depth  of  2  feet 
with  hydraulic  cement  concrete.  A  flooring  of  spruce  tim- 
bers, 6  inches  in  thickness,  is  to  cover  the  caps,  and  form  the 
platform  from  which  the  masonry  is  to  start.  The  masonry 
for  each  abutment  will  be  16  feet  in  width  at  the  bottom, 
and  6  feet  6  inches  in  width  at  the  top,  and  will  consist  of 
5  courses  of  cut  stones,  with  inclined  beds  and  builds, 
except  the  beds  of  the  lowest  course,  which  will  be  horizontal,. 
The  arch  practically  commences  at  the  platform ;  but  the 
masonry  now  under  contract  will  not  be  seen  above  the  usual 
water-hne,  and  has  therefore  been  considered,  for  convenience 
of  description,  as  forming  abutments. 

The   season  was  so  far  advanced  at  the  time  the  contract 


Eeport  or  City  Engineer.  43 

was  closed,  that  not  much  progress  has  been  made  in  con- 
struction. The  cofter-dam  to  enclose  the  foundations  is, 
however,  nearly  completed;  7,000  cubic  yards  of  excavation 
have  been  made,  and  236  cubic  yards  of  cut  stone  delivered. 
The  work  will  be  actively  prosecuted  as  soon  as  the  season 
opens,  and  it  is  hoped  will  be  completed  in  time  to  commence 
the  arch  by  the  middle  of  the  year. 

Covered  Channel  of  Stony  Brook. 

Under  this  head  is  included  a  covered  conduit  extending 
from  Charles  river  across  Beacon  street,  and  through  the 
50-feet  street  on  the  easterly  side  of  the  Beacon  entrance,  to 
the  roadway  on  the  southerly  side  of  the  railroad,  thence 
following  the  roadway  to  a  gate-chamber  situated  on  the 
border  of  the  Park  pond,  nearly  opposite  to  the  Huntington 
entrance.  The  gate-chamber  is  to  form  the  connection 
between  the  conduit,  the  Park  pond,  and  the  extension  of 
the  present  Stony-Brook  channel,  now  terminating  at  Parker 
street. 

The  extension  of  the  Stony-Brook  channel  to  the  gate- 
chamber  will  consist  of  two  arched  water-ways  of  practically 
the  same  section  as  the  ones  with  which  they  are  to  connect. 

The  conduit  from  Charles  river  to  the  gate-chamber  is 
3,520  feet  long,  and  7  feet  2  inches  internal  diameter.  It  is 
built  of  spruce  planks,  2  inches  in  thickness  and  8  inches  in 
width,  thoroughly  trenailed  together,  and  every  fourth  plank 
is  wedge-shaped,  to  give  the  conduit  its  circular  form. 
About  1,700  feet  of  it  are  now  completed.  If  deemed 
advisable,  after  completion  it  can  be  lined  with  an  inch  of 
concrete,  as  it  is  2  inches  larger  in  diameter  than  at  tirst 
contemplated. 

The  gate-chamber  substructure  will  be  built  of  rubble 
granite,  with  brick  inverts,  and  of  cut-stone  for  all  gate- 
openings  and  for  a  portion  of  the  flooring. 

Plans  and  sections  of  this  structure  are  shown  on  the 
accompanying  plates,  which  also  show  the  dimensions  of  the 
water-ways  forming  the  extension  to  Parker  street. 

These  water-ways  are  324  feet  long,  and  will  have  stone 
side  walls  with  brick  arches  and  linings  laid  in  cement,  the 
whole  structure  having  a  pile  platform  foundation. 

All  of  the  work  upon  these  structures  is  being  done  by 
day's  labor,  under  the  immediate  supervision  of  Mr.  Howard 
A.  Carson.  The  machinery  invented  by  him  is  used  for 
making  the  excavations,  and  proves  both  efficient  and  eco- 
nomical. The  right  to  use  this  machinery  in  all  the  city 
departments  was  purchased  July  28,  1880. 


44  City  Document  No.  25. 

In  addition  to  the  part  of  the  conduit  which  has  been  con- 
structed, the  excavation  for  the  gate-chamber  and  a  large 
portion  of  that  for  the  water-ways  between  the  gate-cham- 
ber and  Parker  street,  has  been  done.  The  pile  foundation 
and  timber  platform  for  the  g|ite-chamber  is  also  completed, 
and  a  contract  has  been  made  with  the  Cape  Ann  Granite 
Co.  for  the  stone  for  the  substructure.  The  appropriation 
for  the  entire  work  is  $110,000,  and  the  amount  expended 
to  January  1,  1881,  was  $33,199.43. 

The  flow  of  water  into  the  pond  and  the  regulation  of  its 
height  are  controlled  by  the  gates  in  the  chamber,  in  connec- 
tion with  the  dam  to  be  built  in  the  Beacon-street  bridge 
water-way.      (See  description  of  this  dam,  page  18.) 

The  gate-chamber,  the  conduit,  the  pond,  and  the  dam  at 
Beacon  street,  must  be  considered  together  to  understand  the 
manner  in  which  the  waters  of  Stony  Brook  are  to  be  con- 
trolled and  disposed  of.  The  gate-chamber  is  furnished,  as 
shown  on  the  plan,  with  double  w^ater-ways*,  corresponding 
to  the  w^ater-w^ays  of  Stony  Brook  as  they  now  exist.  These 
water-ways  are  each  provided  with  a  double  set  of  self-acting 
gates,  which  prevent  the  w^ater  from  the  pond  from  running 
into  the  conduit,  and  thus  finding  its  way  to  Charles  river. 
These  gates  serve,  also,  to  admit  into  the  pond  whatever 
portion  of  the  water  fi'om  Stony  Brook  the  conduit  is  not 
capable  of  discharging  into  Charles    river  in  time  of  freshets. 

The  conduit  will  convey  the  ordinary  flow  of  the  brook  to 
the  river,  and  will  also  at  every  high  tide  be  full  of  salt 
water  from  Charles-river  basin  as  far  as  the  tide-gates  in 
the  chamber  near  its  connection.  This  salt  water  can  be  let 
into  the  pond,  if  it  is  desired,  through  a  gate  in  the  chamber 
provided  for  the  purpose. 

If  the  Waaler  in  the  pond,  which  it  is  proposed  to  maintain 
generally  at  grade  8,  reaches  a  higher  grade,  by  reason  of 
the  discharge  into  it  of  the  waters  of  Stony  Brook  in  time 
of  freshets,  the  surplus  water  (unless  the  tide  should  be  at 
a  still  higher  level  at  the  same  time)  will  be  discharged  over 
the  dam  at  the  Beacon-street  water-ways,  and  this  discharge 
will  continue  as  long  as  the  level  of  the  pond  is  above  the 
dam  and  the  height  of  the  tide  below  grade  8. 


The  table,  showing  the  width  of  draw-openings  in  the 
bridges  over  tide-water  in  this  city,  is  given  in  the  Ap- 
pendix. The  openings  have  all  been  remeasured  for  this 
report. 


Eeport  of  City  Engineer.  45 

In  closing  this  my  first  annual  report  to  the  City  Council, 
I  should  state,  for  the  information  of  such  of  its  members  as 
were  not  in  office  last  year,  that  I  succeeded  Mr.  Joseph  P. 
Davis,  upon  his  resignation  of  the  office  of  City  Engineer, 
March  20,  1880,  and  appointed  to  fill  the  vacancy  caused  by 
my  promotion  from  Chief  Assistant,  Mr.  Alphonse  Fteley, 
formerly  the  resident  engineer  in  the  building  of  the  Sudbury- 
river  works. 

Nearly  all  of  the  works  described  in  the  foregoing  report, 
especially  under  the  heads  of  "  Additional  Supply,"  "  Im- 
proved Sewerage,"  and  "  Parks,"  had  already  been  studied, 
designed,  or  nearly  completed,  under  the  direction  of  my 
predecessor ;  and  if  those  which  are  now  incomplete,  prove, 
as  I  have  perfect  confidence  they  will,  as  successful  engineer- 
ing works  as  those  already  completed,  they  will  be  monu- 
ments which  will  attest  his  skill  and  eminence  in  his  profes- 
sion. 

HENRY  M.  WIGHTMAN, 

City  Engineer. 


46 


City  Document  No.  25. 


M 

"A 

Ph 
Ph 

<1 


o 


5~ 


<5 


o 


< 


^ 

d 

00 

CO 

00 

-^  Ci 

t- 

00   C5   T-l    CO 

TiH  CO  CO  0 

CO 

w 

t— I 

H 

Q 

f 

0 

»OkOCOOiOiOOO'^<M'*^COCO-<*iO 

CO 

CO 

^COCOCOCO^COCO 

(3<»   --^  -<*  CO  CO 

•sf)KiNa<io 

^0 

1-H 

rH 

T-H   rH   rH   1— 1   i-H   ,-1   (N 

T— 1   (5<l 

rH  T-\ 

aaawn]sl 

(-H         .      (T)         •         •         •         •         • 

.  1— 1 

^ 

r^ 

::    c 

f?       hfiTH       «       0                  (T) 

0 

H 
0 

3 

0 

-^ 

1 

0 

0 

^  j^  -^-'  ^     p     0 

?^|o   0   0   0        ^ 

24      ... 
Fort  Point  Cha 

i,                  a 

0 

0 

0 

.  'o  c  c  T^      "^  :: 

•73    ._    - 

-     0 

-^ 

^-< 

"H    ;_,  +-*  +^    ■rS          -t-3   ^ 

u   S 

-t-> 

t» 

0 

0      _i      £/3      03      C3               02 

s  ? 

CO 

pqOO^ttPQO      W 

^0 

0 

pq 

» 

.        .        .        . 

'     *   a> 

0 

rs 

Q 

•        •     ©        • 

•  "m 

« 

3 

0 

PQ 

^ ^^ ^  r^      iX> 

Ph 

m              0   '^ 

.  .;=;  0 

0 

0        ■+-<  •::< 

j;pq 

H 
g 

p^ 

:^ 

S  -    0   - 

•|6 

< 

0      -t^-;:^ 

COO 

;z; 

0) 

_C3    _a    _^    r^ 

'oCQco 

^ 

m 

C3  r-i-; 

s  river 
a  (Sout' 

(Nort 

a  St.  (E 

(C 

ercial  P 

3SS  st.    ( 
( 

P^ 

0 

^  ^   '—3  T"     02             ^ 

'H      S 

02 

-^ 

gags'®-!; 

^^ 

0 

"^ 

^    03    c3  ,a  -=)         -J3 

0  0 

0    o3 

w 

PC 

C 

)C 

)C 

)0     0 

QQ 

C  " 

w 

Report  of  City  Engineer. 


47 


oco^OOO-^O^ai^crsOioOT-icoT-if^ir-iiociOcooot^T-irHir:) 

T— I    r— I  T-H  I— I  1—1  _^ 


LOOiOCD>0'-i'^OiOiOcV5'COGO'X>t^rHOOOOT-iioco»o»oi/^ir:),-iCTi 
CO  CO  CO  CO  CO  CO  CO  coco  C0^»O»OC0C0C0'*^C0C0C0C0C0C0C0C0C0C0«^ 


« s  ^ 

fcrj  3  r 


1^    o 

c  +^ 

<»  S  o  to 
CP^Opq 


©    c3 


o 


W 


•^  ^  r:!   o 

ri    M    ^    cc 
O 


C3  K, 


OW 


o 


o 

o 


o  "^ 


!3  o 

<3<J  - 


^   . 


be  3 


be 


in     G 


O 


^  ^,  >.^   o   bp      -g 


-  pq 


-:::    O 


rt  .5    3 


0*5 


c2  a 


-u  -<-' 


C 
CO 


C<1  c^ 


a   c3 


o 

o 


o  ^OO 

_xi    O    o    o 
"H^  ^  +J  ,^J 

"^  ^   -   - 
,  o)  a  fl 

'^  T^    o    o 
2  ■*-'  -'-^ 

C3      CC      CO 

-a  o  o 
Upqpq 


^'    o 

a  c3 
o  o 

rp  i-p 


S 

o 


-a 

,be 
'S 

bo 

a 
S 

S3 
0) 


-  .2 

o 


:^.      »-5 


05 


o  -d 


S^  o  o 

3  •-  M  o) 

pq  9  a, 


CO     O 

w6 


o  ^ 
bfj 

m 

53 


?3  :: 


3-^. 


53      © 


o 

6 


a; 


a 
o 


•^  o 


o 


CO    173 

O  rQ 

t^  g 

O    53 

pqo 


fl  cq 


fi;^^  ^ 


M  CHiliEi. 


3BO)^TCiF  1.^.  mm. 


SCALE  OF  METRES. 


CUT  STONE.     BRICK. 


RUBBLE.      PAVING. 
VV7 


^^ 


Section  on  Line  AB. 


qrade  IS.Ody^^z, 


1^- 


Section  on  Line  OD. 


Section  on  Line  EF. 


BOSTON  PUBLIC  LIBRARY 

mill  nil  III  III  III!  I 


3  9999  06315  933  7