■.I'.V'T!/:
^ir
iii^^^^
1 > '
rb
HP
.Ko *S357.56
dn
lo7^-
> o
[Document 53 — 1883.]
CITY OF ^^ BOSTON.
ANNUAL REPORT
CITY ENG-INEEK
FOR THE YEAR 1882.
Office of the City Engineer, City Hall,
Boston, February 23, 1883.
To the Honorable City Council: —
In compliance with the sixth section of the ordinance
relating to the Engineer's Department, the following report
of the expenses and operations of the department for the
year 1882 is respectfully submitted.
The duties of the City Engineer may be classified under
the following heads : —
A. — Those pertaining to the City Engineer's Department
proper, which consist in the superintendence of the filling of
new streets and of districts, in the care and maintenance
of bridges, in designing and superintending the construction
of new bridges, retaining- walls, city wharves, etc., and in
miscellaneous work called for by committees of the City
Council. (City Engineer's Department.)
B. — Superintendence of the Sudbury River, Cochituate,
and Mystic Water Works, including charge of new con-
structions for these works. (Water Works.)
2 City Document No. 53.
C. — Charge of the construction of a system of intercept-
ing and outlet sewers. (Improved Sewerage.)
D. — Charge of the engineering work in connection with
the Back Bay and other })roposed parks. (Parks.)
The expenses incurred mider the liead C, are paid wholly
from a special appropriation, under the charge of the Joint
Special Committee on Improved Sewerage.
(A.) — City Engineer's Department.
The following is a statement of engineering expenses from
January 1, 1882, to January 1, 1883 : —
Amount expended from department appropria-
tion for 1881-82 $8,112 76
Amount expended from department appropria-
tion for 1882-83 22,996 84
Total expended from department appropria-
tions $31,109 60
Condition of department appropriation : —
Amount of appropriation for iinancial year
1882-83 $32,000 00
Amount expended to January 1,1883 . . 22,996 84
Unexpended balance, January 1, 1883 . . $9,003 16
CLASSIFICATION OF EXPENSES.
Salaries of City Engineer, assistants, draughts-
men, transitmen, levellers, rodmen, etc. . $28,505 S8
Engineering instruments and repairs of same . 228 65
Drawing-paper and materials . . . 323 12
Stationery and printing-stock . . . 335 97
Reference-books, maps, photographs andframes, 142 00
Printing and binding . . . . . 131 73
Travelling expenses, including horse-keeping,
etc 725 89
Incidental expenses, furniture and small sup-
plies ....... 363 38
" Blue Process " printing .... 173 03
Committee expenses . . . . . 179 95
Total $31,109 60
Report of the City Engineer. 3
The number of persons employed and paid from the de-
partment appropriation was, on the first of January, 1882
(inckiding the City Engineer), 23. The present number is
20. Tiie operations of the department for the year, together
with sucli oeneral information relating to tiie various works
and structures, finished and in progress, as is thought to be
of interest, are given in the following statements : —
BRIDGES.
"With the exception of Granite bridge, a comparatively
small structure, none of the tide-water bridges have required
very extensive repairs during the year.
Several inland bridges in process of construction at the
date of the last annual report, have been completed. These
comprise the bridge on the Broadway extension over the
Boston & Albany railroad, the Commonwealth avenue and
Boston & Albany railroad bridges over the Park water-way,
and the Beacon-entrance bridge over the Boston & All^any
railroad.
Work upon the Boylston-street arch bridge is now being
prosecuted; the arch proper is . completely turned, and the
spandrel walls are rapidly apju'oaching completion.
The system of making the repairs upon the tide-water and
inland bridges by day's labor has been continued as for
several past 3xars.
The services of Mr. S. S. Lewis as superintendent of re-
pairs of the tide-water bridges were retained by the Com-
mittee on Bridges. His compensation was fixed at $150 per
month, to include the furnishing of a team and all ordinary
tools.
Carpenters have been paid $2.50 per day and laborers
$2.00.
The spruce lumber required for repairs has been furnished
by Mr. John W. Leatherbee, the lowest bidder and con-
tractor for the past six years. Under his contract for 1881,
he has furnished 14,497 feet B. M. at $16.40 per M., and
under his contract for 1882, 256,751 feet B. M. at $15.90
per M. Other material used in making repairs has been
purchased of various dealers at the lowest market rates.
The painting of the tide-water bridges has been done by
day's labor, under the supervision of Mr. A. H. Townsend, as
foreman, from June 21st to Jul}^ 21st, and Mr. E. B. Perry
from the latter date until Oct. 14th.
The foreman was paid $3.50, painters $2.25 and $2.50,
and laborers employed for cleaning $2.00 per day. The
4 City Document No. 53.
paint-stock was furnished by Dexter Brothers, the lowest
bidders. Total cost of hibor, $3,017.13; materials, tools,
etc., $940.55.
The total cost of ordinary repairs on tide-water bridges
made under the direction of this department was $31,959.33.
All rei)airs made upon the inland bridges, in charge of
the Superintendent of Streets, have been made by day's
labor, under the direction of this department. Advantage
has been taken of favorable contracts made for the supply of
materials for the repair of the tide-water bridges to procure
supplies for inland-l)ridge repairs at same prices. The total
cost of repairs on inland bridges was $3,124.87.
The records of the number of vessels passing through
the draw-ways, time of passage, name, etc., have been kept
by the superintendents of the several bridges in the same
manner as last year. These monthly returns have been
tabulated, and a summary will l)e found in Appendix A.
The usual annual examination (required by Section 4 of
Chapter 17 of the Revised Ordinances) of all bridges within
the city limits, open to team and foot travel, has been made,
and the resvilts of this examination respecting the condition
of the bridges as to safety and need of renewal or repairs,
are given in the succeeding pages.
The following is a list of the bridges inspected. The
total number is two more than last year. Three have been
added to the list and one removed. The three added are
the Commonwealth avenue. Beacon entrance, and Broadway ;
the one removed was the Beacon street, for which the new
bridge over the outlet of the Park pond has been substi-
tuted. The old bridge has been torn up and its site filled
with gravel.
In the list those marked with an asterisk are over naviga-
ble waters, and are each provided with a draw : —
I. — Bridges wholly supported by Boston.
Ashland street. Ward 23, over Boston & Providence
Railroad.
Athens street, over N.Y. & N.E. Railroad.
Back-Bay park, over Boston & All)any Railroad.
Beacon street, over outlet to Back-Bay ]:)ark pond.
Berkeley street, over ])Oston & Albany Railroad.
Berkeley street, over Boston & Providence Railroad.
Blakemore street, over Boston & Providence Railroad,
Ward 23.
*Broadway, over Fort Point Channel.
Broadway, over Boston & Albany Railroad.
Report of the City Engineer. 5
Bi'ookliiie avenue, over Muddy river, Ward 22.
*Charles River, from Boston to Charlestown.
*Chelsea (South), over South Channel, Mystic river.
*Chelsea street, from East Boston to Chelsea.
Columbus avenue, over Boston & Albany Railroad.
*Commercial Point, or Tenean, Ward 24.
Commonwealth avenue, over outlet to Back-Bay park pond.
*Con2fress street, over Fort Point Channel.
Dartmouth street, over Boston & Albany and Boston &
Providence Railroad.
*Dover street, over Fort Point Channel.
*Federal street, over Fort Point Channel.
Ferdinand street, over Boston & Albany Railroad.
Huntington avenue, over Boston & Albany Railroad.
*Malden, from Charlestown to Everett.
*Meridian street, from East Boston to Chelsea.
*Mt. Washington avenue, over Fort Point Channel.
Newton street, over Boston & Providence Railroad.
Public Garden, foot-bridge.
Shawmut avenue, over Boston & Al])any Railroad.
Swett street, east of N.Y. & N.E. Railroad.
Swett street, west of N.Y. & N.E. Railroad.
*Warren, from Boston to Charlestown.
West Chester park, over Boston & Albany Railroad.
West Chester park, over Boston & Providence Railroad.
Wiuthrop, from Breed's Island to Winthrop.
II. — Bridges of which Boston supports the Part
WITHIN its Limits.
*Cambridge street, from Brighton (Ward 25) to Cambridge.
Central avenue, from Ward 24 to Milton.
*Chelsea (North), from Charlestown to Chelsea.
*Essex street, from Ward 25 (Brookline) to Cambridge.
*Granite, from Dorchester (Ward 24) to Milton.
Longwood avenue, from Ward 22 to Brookline.
Mattapan, from Ward 24 to Milton.
Milton, from Ward 24 to Milton.
*Neponset, from Ward 24 to Quincy.
*North Beacon street, from Ward 25 to Watertown.
*North Harvard street, from Ward 25 to Cambridge.
Spring street, from West Roxbury (Ward 23) to Ded-
ham.
*Western avenue, from Ward 25 to Cambridge.
* Western avenue, from Ward 25 to Watertown.
City Document No. 53.
III. — Bridges of which Boston pays a Part of the
Cost of Maintenance.
Albany street, over Boston & Albany Eailroad.
*Canal, from Boston to Cambridge.
Dorchester street, over Old Colony Railroad.
*Prison Point, from Charlestown to Cambridge.
*West Boston, from Boston to Cambridge.
IV. — Bridges supported by Railroad Corporations.
Ist. — Boston (& Albariy Railroad.
Brighton avenue. Ward 25.
Harrison avenue.
Market street. Ward 25.
Tremont street.
Washington street.
2d. — Boston & Maine Railroad.
Mystic avenue.
Main street.
3d. — Boston S Providence Railroad.
Beech street. Ward 23.
Bellevue street. Ward 23.
Canterbury street. Ward 23.
Centre street, or Hog Bridge, Ward 23.
Centre and Mt. Vernon streets, Ward 23.
Dudley avenue, Ward 23.
Park street. Ward 23.
4th. — Boston f Revere Beach ^ & Lynn Railroad.
Everett street.
5t]i. — Eastern Railroad.
Mystic avenue.
Main street.
6th. — New York & New England Railroad,
Broadway.
Dorchester avenue.
Fifth street.
Forest Hill avenue, Ward 24.
Report of the City Engineer. 7
Fourth street.
Harvard street, Ward 24.
Norfolk " " "
Norfolk " " "
Second street.
Silver street.
Sixth street.
Third street.
Washington street, Ward 24.
7th. — Old Colony Railroad.
Adams street.
Ashmont street and Dorchester avenue.
Cedar Grove cemetery.
Commercial street.
Savin Hill avenue.
Eecapitulation.
I. Number wholly supported by Boston . . 35
H. Number of which Boston supports the part with-
in its limits ...... 14
in. Number of which Boston pays a part of the cost
of maintenance . . . . . .5
IV. Number supported by Railroad Corporations : —
1. Boston & Albany ...... 5
2. Boston & Maine .2
3. Boston & Providence ..... 7
4. Boston, Revere Beach, & Lynn .... 1
5. Eastern ....... 2
6. New York & New England .... 13
7. Old Colony 5
Total number ...... 89
1.— BRIDGES WHOLLY SUPPORTED BY BOSTON.
Ashland-steeet Bridge (over Boston & Providence
Railroad, Ward 23).
This bridge has been painted and the roadway has been
sheathed. The almtments have needed repointing for the
past two years ; otherwise the bridge and abutments are in
excellent condition.
Total cost of repairs, $442.74.
City Document No. 53.
Athens-street Bridge (over New York & New Eng-
land Railroad)
Has not required any repairs, and is in good order.
Beacon-entrance Bridge (over Boston & Albany Rail-
road).
This is a new iron bridge of the deck pattern, and was
completed September 30th, although not yet opened for
public travel. The abutments were built of stones from
the Beacon-Hill reservoir. The entire structure is of the
most substantial cliaracter. A more detailed description of
it is given in my report to the Park Commissioners.
Beacon-street bridge (over Outlet of Back Bay Park
Pond).
No repairs have been made upon this bridge during the
past year. It will require painting, and probably sheathing,
the coming season.
Berkeley-street Bridge (over Boston & Albany
Railroad) .
Although this is a bridge of insufficient strength for the
travel of the thoroughfare upon which it is h>cated, no
change for the worse has been observed in it, and it is appa-
rently in good order. The only repairs required were upon
the roadway sheathing.
Total cost of repairs, $101.75.
Berkeley-street Bridge (over Boston & Providence
Railroad.)
The wearing surface of the roadway has been renewed and
the hard-pine under-floor recalked.
The under-floor showed signs of decay, confined princi-
pally to a small amount of rot on the edges of some of the
planks. All rotten wood was removed, and the floor left in
good condition.
The iron-work and other portions of the bridge are in
good order.
Total cost of repairs, $1,029.16.
Report of the City Engineer.
Blakemore-street Bridge (oyer Boston & Providence
Eailroad, Ward 23).
This is a new iron bridge with granite masonry, abutments
and wing-walls. The bridge was completed at the date of
the last annual report, but had not been opened for travel,
as the tilling of the approaches had not been done. The fill-
ing was completed early in the year, and the Ijridge has been
open to travel since.
It will probably require painting this year ; otherwise it is
in excellent condition.
* Broadway Bridge (over Fort Point Channel).
The principal repairs made during the year consisted in
renewing the roadway sheathing, recalking the under-floor
of the draAv, and painting.
The tim1)er floor built last year to replace the iron plate
and wood-pavement flooring of the column section on the
Boston side of the channel has given good satisfaction, and
has not required any expenditure for repairs.
The iron plate and wood-pavement floor on the column
section on the South Boston side of the channel has, as here-
tofore, given considerable trouble, on account of the expan-
sion of the wood blocks, caused by frost.
To remedy this difficulty rows of the blocks have been
taken out at intervals of about one hundred feet, and their
places filled by planks fitted in such a way as to permit the
expansion of the pavement without its being raised in waves,
as has usually been the case.
The remedy has proved successful so far as to prevent the
former stoppages of travel from this expansion of the pave-
ment in frosty weather ; but the wooden blocks are neverthe-
less a source of annoyance, expense, and possible danger,
and have proved extremely undesiraljle as a road surface for
a bridge structure, either of iron or wood.
The timber curbing in the gutters of the wood pavement
section is rotten, and must be renewed soon. The under-
floor of the concrete sidewalks is in bad condition, and will
require more or less repairs the present year. The floor of
the draw-pier will also require renewal to a considerable ex-
tent.
The sheet-piling of the draw-pier, to which attention has
been called in previous reports, on account of its worm-eaten
condition, has not shown any change for the worse.
The substructure of the bridge has been painted for about
10 City Document No. 53.
three-fourths of its length with red lead. The remainder of
it and the superstructure should be painted in the spring.
Total cost of repairs, $4,841.94.
Broadway Bridge (over the Boston & Albany Rail-
road).
The abutments and retaining- walls were ready to receive
this iron bridge early in the year. There still remained some
grading of the approaches to be done by the contractors,
Messrs. John Cavanagh & Co., and this work was tinally
completed by the city in connection with its own filling out-
side the lines embraced by the contract. A final settlement
was made with the contractors Sept. 16, 1882; the total
amount paid was $64,228.50.
The iron bridge was completed by Mr. D. H. Andrews,
the contractor, in April, about three and one-half months
behind the contract time.
The cost of the iron bridge was $29,366.80, exclusive of
the fences. The fences were furnished and erected by the
Manly & Cooper Company, of Philadelphia, at a cost of $1,860.
Brookline-avenue Bridge (over Muddy River).
This small timber bridge will be destroyed on the com-
pletion of the Muddy-river covered channel, a work now in
progress and probably to be completed the present year.
It is in safe condition and has cost nothing for repairs.
* Charles-river Bridge (from Boston to Charles-
town).
The condition of the draw of this bridge is not such as
could be wished in view of the much larger amount of travel
which will probal)ly go over it on account of the reconstruc-
tion and widening of Warren bridge. The draw foundation
is in very poor condition, and although all the work Avhich
could ])e done to any advantage while the draw was in use
has been done, much more is required to make the founda-
tion what it ought to be for a structure of this kind.
As soon as the recoirstructed Warren bridge is opened for
travel, so that this bridge can be out of use for a time with-
out great inconvenience, an entirely new draw foundation
above the piles should be built.
The draw has received two severe blows in nearly the
same place from passing vessels, and one girder is bent con-
siderably. If it should be struck again with so much force'
as in cither of the other cases it would probably be disabled.
Eepoet of the City Engineer. 11
If the draw is to be retained, — a measure of somewhat
doubtful expediency if the foundation is renewed, — steam-
power should be applied for moving it oft' and on, and also
as an aid to vessels passing through the draAv-way.
The bridge, as a whole, may be said to be in fair condition.
Total cos't of repairs, $2,438.05.
* Chelsea Bridge (South) (over South Channel,
Mystic River).
Only the usual small repairs have been made upon this
bridge, and it is now in good condition.
Total cost of repairs, $314.76.
* Chelsea-street Bridge (from East Boston to
Chelsea).
The draw to this bridge was replanked early in the year,
but no other repairs have been made upon it. The fixed
portion of the bridge is in good condition and the draw is in
good enough condition for street travel. If the draw had to
be opened frequently for the passage of vessels it would soon
require extensive repairs or entire renewal ; but as it is
seldom or never opened, although always kept in condition
for use, it is probable that it will answer its purpose for some
time to come.
Total cost of repairs, $149.90.
Columbus- AVENUE Bridge (over Boston & Albany
Railroad).
The roadways have been replanked. The bridge needs
painting, but is otherwise in excellent condition.
Total cost of repairs, $81.40.
*COMMERCIAL PoiNT, OR TeNEAN BrIDGE (WaRD 24).
The plank flooring of this bridge has been entirely renewed
the past season, and the structure is now in good order.
COMMONWEALTH-A VENUE BrIDGE (OVER AVATEE-WAY, BaCK
Bay Park.)
This new iron bridge was completed by the contractors,
Messrs. Cook, Rymes, & Co., in May.
It is an iron-plate girder bridge of the deck pattern, and
cost, exclusive of the fence, $9,803.59.
It has not been opened for public travel, as the Common-
12 City Document No. 53.
wealth-avenue extension is not completed. The bridge has,
however, been in use for the passage of gravel trains during the
filling of the avenue and adjacent lands.
No fences have yet been placed ui)on the bridge, as it was
thought desiral)le to aAvait the ado})tion of some style of fence
by the Park Commissioners for the portions of the Beacon
entrance, which require fencing, and then make the bridge
fences of a similar pattern.
The bridge is a thoroughly substantial structure, and has
shown no signs of weakness under the unusual strains caused
by the passage over it of the gravel trains and heavy engines
which draw them.
* Congress-street Bridge (over Fort Point Channel).
A new centre-pivot bearing, by which the weight of the
draw is carried upon flat steel-plates 12| inches in diameter,
has replaced the steel friction-roll centre-bearing, which was
not only considerably worn, but was unsatisfactory in its
action. The new centre-bearing woi-ks well ; the old one will
be retained for use in case of accident.
The planking on the sides of the water-ways, which was
badly worn by the passage of such large numbers of vessels,
has been partially renewed with planks of greater thickness ;
this work should be continued and completed the coming
season.
Under the direction of the Harbor and Land Commis-
sioners the channel has been dredged to a depth of sixteen feet
below low-water as far as the In'idge. As there are but twelve
feet in depth at low water in the draw-wa^'s and above the
bridge, vessels drawing more than this amount may acci-
dentally get caught in the draw-way. The sixteen-foot depth
should be continued to such distance above the bridge as to
render such an occurrence impossible, as the stoppage of
travel over this bridge causes the greatest inconvenience to
the large traffic over it to and from the railroad freight-yards
and steamship-docks on the South Boston side of the channel.
The machinery for turning the draw has been kept in good
repair, and the bridge, as a whole, is in good condition.
Total cost of repairs, $3,554.45.
Dartmouth-street Bridge (over Boston & Albany and
Boston & Providence Railroads).
The iron-work above the floor has been painted, and the
roadways sheathed. The In-idge is in good order.
Total cost of repairs, $761.10.
Report of the City Engineer. 13
* Dover-street Bridge (over Fort Point Channel).
The draw-way of this bridge was narrower than the law
required by more than a foot. It has been made the full
legal width of thirty-six feet at the level of high water.
Two of the main trucks under the draws have been re-
moved on accoi'.ut of wear, and two spare trucks substituted
for them. The old trucks have been put in order, and are
ready for use when required.
The roadways of both draws have been sheathed, and the
entire bridge painted. It is now in good condition.
Total cost of repairs, §3,248.08.
* Federal-street Bridge (over Fort Point Channel).
The sides of the draw-ways of this bridge have been
trimmed off so as to make the opening the full legal width
of thirty-six feet.
The bulkheads at the ends of the draws have been rebuilt
with new timber, a considerable amount of repaving has
been done in the bridge roadway, and the machinery for
working the draws has been thoroughly repaired.
For a wooden bridge that is growing old its condition is
fair, — the floor is known to he badly decayed in places, and
the draws will not last many more years.
Total cost of repairs, $3,040.07. .
Ferdinand-street Bridge (over Boston & Albany
Railroad).
The roadway has been sheathed, and the bridge proper is
in good condition. The bulkhead referred to in last year's
report is still in an unsafe condition, nothing having been
done to improve it.
Total cost of repairs, $51.26.
Huntington-a venue Bridge (over Boston & Albany
Railroad)
Is in good order, no repairs have been made upon it the
past year.
*Malden Bridge (from Charlestown to Everett).
A small section of this bridge rests upon an old timber
crib, which it was found impracticable to drive piles through
when the bridge was lebuilt in 1875. This section has settled
somewhat, but not enough to require any work to be done
14 City Document No. 53.
upon it yet. The cross-ti miners, which transfer tlie weight of
the draw to the centre pivot, are badly bent. With the ex-
ception of these defects the bridge is in good order, although
only slight repairs have been made.
Totafcost of repairs, $80.32.
* Meridian-street Bridge (from East Boston to
Chelsea).
The turning-gear, tracks, and wheels of the draw have
been put in good order, and a small amount of paving has
been done on the bridge.
The plank floor, bulkheads, and railing of the fixed por-
tion of the l)ridge are in poor condition.
Total cost of "repairs, $451.32.
*Mt. Washington-avenue Bridge (over Fort Point
Channel) .
The draw-pier has been strengthened at one end, and will
require similar work at the other end in the spring. The
draw has been sheathed twice, and the entire bridge has been
painted. It is now in good condition.
Total cost of repairs $2,164.52.
Newton-street Bridge (over Boston & Providence
Railroad).
The abutments have been repointed. No other repairs
have been made. The bridge is in good order.
Public Garden Foot-Bridge.
The stone masonry of this ]>ridge has needed repointing
for several years ; otherwise the bridge is in good condition.
Siiawmut-avknue Bridge (over Boston & Albany
Railroad).
The roadway has been newly sheathed, and the concrete
sidewalk has been repaired to a slight extent. The bridge
is in excellent order.
Total cost of repairs, $283.97.
Swett-street Bridges (over South-Bay sluices).
The northerly bridge has been sheathed and the sidewalks
on both put in order. The al)utmcnt Avings, Avhich are of a
temporary character, show some signs of weakness ; other-
wise the bridges are in fair condition.
Total cost of repairs, $185.85.
Eeport of the City Engineer. 15
* Warr"en Bridge (from Boston to Charlestown) .
Only the most necessary repairs have been made on this
bridge, owing to the uncertainty of its future as an avenue
of travel. The action of the City Government in granting
the appropriation for widening and reconstructing the bridge
will render any further large expenditure in the way of
repairs unnecessary.
There are two particulaly w'eak piles in the bridge, which
may do service until the new structure is completed, but
they will require careful watching in the meantime.
During the year the pavement has been extensively
patched, the concrete sidewalk resurfaced, and the usual
minor repairs made.
The general condition of the brids^e is very poor.
Total cost of repairs, $1,870.25. "
"^ West Chester Park Bridge (over Boston & Albany
r Railroad)
^ Is in good order ; no repairs have been made upon it during
the year.
West Chester Park Bridge (over Boston & Provi-
dence Railroad).
The roadway sheathing has been patched and the trusses
cleaned. The bridge is in good order.
Total cost of repairs, $51.68.
Winthrop Bridge (from Breed's Island to Winthrop) .
The under floor has been recalked, the roadway sheathed,
and railing painted. One of the main piles, near the centre
of the bridge, has mysteriously disappeared. The bridge
has been strengthened at this weak point and is now in good
condition.
Total cost of repairs, $987.45.
II. — BRIDGES OF WHICH BOSTON SUPPORTS
THE PART WITHIN ITS LIMITS.
* Cajubridge-street Bridge (from Ward 25 to
Cambridge).
The buoy has been reset, the draw newly sheathed, and
the Superintendent's house repaired. The bridge is now in
fair condition.
Total cost of repairs, $253.46.
16 City Document No. 53.
Central-avenue Bridge (over Neponset River, Dor-
chester Lower Mills).
With the exception of new roadway sheathing, no repairs
have been made on this bridge. It will require painting the
comino- season ; but is in other respects in excellent condition.
Total cost of repairs, $128.69.
* Chelsea Bridge (North) (from the Mystic River
Corporation's Wharf to Chelsea)
Is in excellent condition, and only ordinary repairs have
been made upon it during the 3^ear.
Total cost of repairs, $420.16.
* Essex-street Bridge (from Ward 25 to Cambridge).
The portion of this bridge maintained by Cambridge has
been rebuilt during the past year. The draw is of the leaf
or lifting pattern, and the half on the Boston side was old
and in poor condition. Advantage was taken of the stoppage
of travel over the bridge by Cambridge to substitute a new
leaf for the old one on the Boston side of the channel. The
roadway of the bridge was also newly sheathed. The under-
floor of the roadway was found in much poorer condition
than was anticipated, considering that it has been down but
four years and consists of hard-pine plank, calked and paid.
It was rotten in many places, and although repaired to some
extent was in such condition that entire renewal would be
cheaper in the end than thorough repair. The floor will
probably be safe for a few years, but will require careful
watching. No reason is known for the early decay of this
floor ; an examination of other bridge-floors, similarly con-
structed and much older, shows them to ])e in good condition.
That the timber of which it is composed might not have been
sufficiently seasoned ; that it was made from trees from which
the sap had been drawn, or that it was overheated in trans-
portation, furnish the only reasons which have been suggested
for its failure.
Total cost of repairs, $2,860.62.
* Granite Bridge (from Ward 24 -To Milton).
This bridge has been rebuilt above the pile-"\vork with new
materials. The draw has l^een repaired, and the entire bridge
is now in good condition.
The repairs consisted of splicing three defective piles,
Report of the City Engineer. 17
putting on new girder-caps at a lower grade than the old
ones in all the bents of piles ; a new hard-pine floor, 4 inches
thick, calked and paid, and covered with 2-inch spruce ; and
a new sidewalk, 5 feet wnde, on one side of the bridge. The
draw was also replanked, and the approach to the bridge
newly fenced. All of the work was done by the repair-gang,
under the immediate supervision of Mr. Lewis, the foreman.
The portion of the bridge in Milton was rebuilt, on sub-
stantially the same plan, mider the direction of the Road
Commissioners.
Total cost of repairing Boston's portion, $2,350.93.
LoxGwooD-AVExuE Beidge (feom Ward 22 TO Brook-
line)
Is in fair condition ; no repairs have been made upon it the
past year.
Mattapan Bridge (from Ward 24 to Milton).
A w^eak structure, in fair condition ; no repairs have been
made during the past season.
Milton Bridge (from Ward 24 to Milton)'.
Slight repairs have been made on the sidewalks. It is
probable that the floor is somewhat rotten, as it is old, but
no signs of weakness have been noticed. A careful exami-
nation of it will be made early in the season to determine its
condition. The iron-work needs painting ; otherwise the
bridge is apparently in good condition.
Total cost of repairs, $7.27.
*Neponset Bridge (from Ward 24 to Quincy).
Only small repairs have been required. The bridge is in
good order.
Total cost of repairs, $93.86.
* North Beacon-street Bridge (from Ward 25 to
Watertown).
A new railing is needed on this bridge ; otherwise it is in
fair condition. No repairs have been made upon it the past
year.
18 City Document No. 53.
* North Harvard-street Bridge (from Ward 25 to
Cajibridge.)
The dolphin on the down-stream side of the bridge was
damaged by vessels, and has been repaired, so that it is now
in fair condition. The contemplated dredging operations
in the vicinity of this bridge by the United States Govern-
ment will render the dolphin useless as soon as they are
done, and it should then be replaced by a buoy. It will
probably be a constant source of expense until that time,
owing to its exposed position and careless use by vessels.
The sheathing on the bridge roadway has been patched,
and the counterbalance of the draw increased in weight.
The bridge is now in good order.
Total cost of repairs, $284.25.
Spring-street Bridge (from Ward 23 to Dedham)
Is a stone arch bridge in good order ; no repairs have been
required.
* Western-avenue Bridge (from Ward 25 to Cam-
bridge).
The roadway of this bridge has been newly sheathed, a new
buoy put in place, and the superintendent's building repaired.
The bridge is now in good condition.
Total cost of repairs, $274.07.
* Western- avenue Bridge (from Ward 25 to Water-
town) .
Attention has been called in last year's and several former
reports to the obstruction to navigation caused by the bad
position of this draw in reference to the channel. It re-
mains in the same condition as last year, and will probably
continue to do so until the Watertown authorities are im-
pressed with the necessity for a change in its location.
The draw is often twisted and racked by passing vessels,
and the shafting has l)cen removed and straightened twice
during the year from this cause.
The sheathing and part of th eunder-floor have been renewed,
but the abutment remains in the unstable condition reported
last year. The bridge proper and the draw are in fair con-
dition.
The total cost of repairs, $304.70.
Report of the City Engineer. 19
III. —BRIDGES FOR MAINTENANCE OF WfflCH
BOSTON PAYS A PART OF THE COST.
Albany-street Bridge (over Boston & Albany
Railroad).
The bad condition of this bridge and its abutments was
fully described in last year's report. No special change for
the worse in the condition of this structure has been noted.
The retaining-wall between the westerly abutment and the
Broadway extension will have to be rebuilt in connection with
the raising of the grade of Albany street at its junction with
the extension. The abutments of the bridg-e ought to be re-
built at the same time to avoid closing the street to travel
more than once. If this work is done a new bridge will
probably become necessary, as the old one is not worth
putting back again if removed.
* Canal Bridge (from Boston to Cambridge) .
* Prison-Point Bridge (from Charlestown to
Cambridge).
* West-Boston Bridge (from Boston to Cambridge) .
The Canal and Prison-Point bridges are in fair condition.
The West Boston bridge will require somewhat extensive re-
pairs the coming season. (For further details, see report of
the Commissioner for Boston, City Doc. No. 15, 1883.)
Dorchester-street Bridge (over Old Colony
Railroad)
Has required no repairs, and is in good condition.
IV. — BRIDGES SUPPORTED BY RAILROAD
CORPORATIONS.
The main truss of the Ashland-street bridge, over the
Shawmut branch of the Old Colony Railroad, is out of line
and grade, and looks overloaded. Beech-street bridge, on
the Dedham branch of the Boston & Providence Railroad, is
old and poor, and is supported by temporary props from the
road-bed. A new iron bridge has replaced the old wooden
bridge on Canterbury-street, Ward 23, over the Boston &
Providence Railroad .
The remaining bridges, supported by railroad corporations
given in the list, are in good order or fair condition, and
require no special mention.
20 City Document No. 53.
MISCELLANEOUS WOEK AND CONSTRUCTIONS
IN 1882.
Atlantic-avenue Sidewalk.
When this avenue was built, wherever it crossed the head
of a dock a retaining or sea-wall was constructed on a line
24 feet from the line of the avenue ; the sidewalk was built
on pile-work which extended to within 4 feet of the line.
On the line of the avenue across all of the docks an oak-pile
and hard-pine timber fender-guard was built.
The sidewalk and fender-guard thus constructed aggre-
gates 1,450 feet in length, and have been thoroughly recon-
structed and repaired during the past season.
The work consisted principally in building new fences,
outside bulkheads, and renewal of plank flooring where it
was rotten. The floor was found in good condition except in
a few places, a result undou])tedly to be attributed to the fact
that it was creosoted or treated with "dead oil" vapor at the
time it was laid. Although the treatment was very imper-
fect, as the creosoting process had at that date (1869-70)
been but a short time in use in this city, yet, without it, 6
inch spruce-plank, covered with 18 inches of gravel as this
was, could not have lasted probably for more than one-half of
the number of years which have since elapsed.
The total cost of the stock and carpenters' work for the
repairs was $2,143.62.
D-STREET Extension.
Under this head is included all the work done by the Old
Colony Railroad Comixuiy, to fulfil its contract with the city,
dated Dec. 28, 1881, and also the building of a culvert or
passage-way under and across the raih'oad from E street to
Ames street.
The railroad company's contract required the building of
granite-masonry abutments on the lines of D street Avhere it
crossed the railroad, the building of an iron bridge upon them
to carry the railroad over the street, the building of retaining-
walls wherever it was necessary to prevent the flliing of the
road-bed from encroaching upon land not owned b}'^ the com-
pany, and in general all the work necessary to give the city
a clear headway of 13 feet above grade 10, city base, under
the railroad on the lines of D street extended. The work
was to be completed Nov. 15, 1882, and the city was to pay
for its proportion of the cost, $45,000.
Report of the City Engineer. 21
The work has been very actively prosecuted by the railroad
company during the past year, and it was practically com-
pleted on Nov. 22d. A final estimate and payment Avas made
Feb. 12th of this year.
The masonry of the abutments and retaining-walls is of the
most sul:»stantial character, fully up in most respects to the
standard of such work as done by the city, and the entire
improvement has been carried on by the compauy's officials
apparently with the desire to do the best possible work of
the class required without reference to the fact that the terms
of the contract might permit them to make it less expensive.
The grading of D street and its extension, to conform to
the bridge built ijy the railroad company, is the only work
now remaining to be done to render this much-needed avenue
available for public travel.
While the work under the railroad company's contract was
in progress, a petition was presented to the City Council for
the construction of a passage-way under and across the rail-
road between E street and Ames street. The petition was
favorably considered, and an appropriation of $600 was made
to construct a timber passage-way. It was afterwards deemed
desirable l^y the Committee on Streets to have a more per-
manent structure built, and a further appropriation of $600
was obtained.
The structure, as built, consists of an arched passage-way or
culvert 4 feet 6 inches wide, and 7 feet high, constructed
entirely of hydraulic cement concrete. The foundations ex-
teud through several feet of mud to hard clay, and for them
American cement concrete was used. Above the foundations
the structure consists principally of English Portland cement
concrete. Two or three hundred dollars could be advanta-
geously spent in improving the approaches to this passageway,
and in making provision for lighting it with gas at night.
East Boston Ferries.
By request of the Board of Directors of these ferries, sur-
veys, plans, estimates, and specifications were made for
building new slips on the Boston side of the North ferry.
Plans were also made for a new foundation and spring for
the shore end of the southerly drop.
The city's lot at this ferry is very narrow, rendering a
radical change in the form of the slips and piers a necessity
if provision was made for the dockage of two boats at the
same time. The form of pier desired for the sides of the
slips was decided upon by the Board of Directors ; and
in the plans and specifications for the work furnished by
22 City Document No. 53.
this department every provision that could be made for in-
creasing their strength and durability was adopted. The
outside pier of eacli slip consists of two rows of oak-piles,
the inner one sheathed Avith maple-planks four inches in
thickness, placed vertically and securely treenailed to oak
girders bolted to the piles. The piles of the outer row Avere
strongly connected together by lines of oak-girders bolted to
them.
The centre pier consists of two rows of piles, the piles of
each row being connected together by oak-girders. Both
faces of the centre pier were sheathed with maple planks in
the same manner as the faces of the piers opposite to them.
The piles of every row were chained together at their tops
with heavy iron chains.
Base-lines and grades for the work were given by this de-
partment ; but the construction was in charge of a competent
inspector, appointed by and under the direction of the
Board of Directors.
St. Charles-street Eetaining-Wall.
In June, plans and specifications were prepared for build-
ing a retaining-wall on the line of the Boston & Albany Rail-
road across the end of St. Charles street.
Proposals for doing the work were received July 13th,
but, being greatly in excess of the estimated cost, they were
rejected, and the work readvertised, proposals being received
the second time July 27th ; again the price was considered
too high, and it was decided to do the work by day's labor.
Work was begun at once, and completed on November 24th.
The wall has a foundation of spruce piles, driven 3 feet
apart lengthwise of the wall, by 2 feet 6 inches and 3 feet
apart in the other direction. They were driven at an incli-
nation to the vertical of 1 inch in 12 ; the tops were cut ofi' at
grade 3 feet 6 inches above city base. A foundation course
of concrete masonry 3 feet 6 inches in depth, 11 feet wide on
the l)ottom, and 8 feet on top was built on the piles surround-
ing them to a depth of (> inches below their tops. The con-
crete was mixed in the proportion of one part cement to two
parts of sand and five of gravel, Portland cement being
used for a shell of one foot in thickness on the outside of the
mass, and llosendale cement for the interior. The top of the
concrete is six inches below the surfiicc of the earth in front.
On this is a wall of granite masonry, laid in cement, 0 feet 6
inches wide on the bottom, 3 feet (J inches wide on top, and
11 feet 1 inch high, surmounted by a cut-granite coping 1
foot 8 inches hiffh. The wall is ballasted with broken con-
Eeport of the City Engineer. 23
Crete. The granite and broken concrete were brought from
Beacon-hill reservoir. On top of the wall is a close board-
fence 5 feet high.
The lowest bid received for doing the work Avas $4,790.
Its cost by day's labor was $3,074.01.
West Rutland square and Durham-street Retaining-
Walls, and Foot-Bridge over Boston & Providence
Railroad.
These walls are located, one on each side of the Boston &
Providence Railroad, at the ends of West Rutland square
and Durham street, these streets being in line with each
other.
,The work was advertised at the same time as the St.
Charles-street wall, with the same results ; no satisfactory
bids being received, it was therefore decided to do it
by day's labor. It was begun immediately, and is now com-
pleted. The foundation of each wall consists of spruce piles,
spaced 3 feet by 2 feet 6 inches apart, driven at an inclination
to the vertical of 1 in 12, and cut off at grade 4 feet above
city base. On the piles is a mass of concrete 7 feet wide and
4 feet 6 inches high, mixed and deposited in the same manner
as at St. Charles street. On the concrete is a wall of e:ranite
masonry laid in cement, 5 feet 6 inches wide on the bottom,
3 feet 6 inches wide on top, and 9 feet 5 inches high, with a
coping on top 1 foot 5 inches high ; the whole is surmounted
by a close board-fence 5 feet high. Buttresses were built on
the backs of the walls so as to give sufficient foundation for
the iron foot-bridge which has been erected. The wall was
ballasted with broken concrete. The granite and broken
concrete were brought from Beacon-hill reservoir.
The iron foot-bridge over the Boston & Providence Rail-
road at this point is a through bridge, and rests upon iron
piers built upon the retaiiiing-walls. The piers are made of
wrought-iron posts, thoroughly braced together, and are 10
feet 10| inches high. The tops of the piers, which are on a
level with the floor of the bridge, are reached by stair-
ways'from each side of each street-. These stairways are of
wrought-iron, excepting the stair treads, which are of hard-
pine.
The trusses of the bridge, two in number, are of the
riveted bowstring type, have eight panels each, and are 69
feet 7 inches long over all, and 10 feet deep at centre.
Cross floor-beams of 8-inch channel-iron are riveted to
the trusses at their panel-points, and on these rest hard-
24 City Document No. 53.
pine stringers 3 inches by 8 inches, whicli support a flooring
of 1 J-inch hard-pine phmk, phmed and rabbetted.
The lower hiteral system is of angle iron, and the top
chords are braced together for four panels at centre of bridge.
The strain from the top bracing is transferred to the lower
lateral system by special vertical bracings placed one panel
each side of centre of bridge.
The stairways, piers, and bridge are provided with gas-
pipe railings, connected to cast-iron posts and to the bridge
trusses.
The bridge was furnished and erected by the Boston
Bridge Works, D. H. Andrews, Engineer, and cost $2,370.
The cost of the retaining-walls was $7,227.21. The lowest
bid received when advertised was $9,497.73.
Falmouth-street Filling.
Work was begun on September 1st, by the Boston & Al-
bany Railroad Co., on the tilling of Falmouth street, between
Newton street and West Chester park. The material was
brouo^ht from Newton where the Railroad Co. were makinof
some changes in the location of their tracks. Work was
stopped on November 16th, on account of the exhaustion of
the source of supply of earth, but was resumed on January
25th, with gravel from Riverside. The work is not yet com-
pleted. There were deposited to January 1, 1,539 squares of
filling, at a cost of $3.20 per square.
Paving-Yaed Wharf at Charlestown.
The bulkhead forming one side of this wharf has been for
some time in a dilapidated condition. It became necessary
the past season either to rebuild the old bulkhead or build a
new one outside of it. The latter alternative was adopted,
and a new bulkhead was constructed, partly with old oak
piles from the Mt. Washington-avenue bridge and partly
with new spruce piles. The space between the old and new
bulkheads was then filled with ashes.
Tyler-street Retaining-Walls.
The raising of the grade of Tyler street, in connection with
the extension of Broadway, involved the building of retain-
ing walls on both sides of the street, on the rising grade.
These walls were built by day's labor, and the stone used
was furnished from the Beacon-hill reservoir. The wall on
the northerly side of the street is about 100 feet in length,
and that on the southerly side about 40 feet.
The cost of the work was $2,987.36.
Keport of the City Engineer. 25
In General.
A considerable amount of Avork of a miscellaneous char-
acter has been clone during the year. Under this head may
be classed surveys and estimates of quantities of materials
required for filling the Prison-Point flats for the Board of
Health ; plans for extending and relocating one pier on the
easterly side of the South ferry, East Boston side ; plans and
specifications for a new tank for East Boston ferries ; estimates
of cost of raisino- o-vades of Beacon street and Brookline
avenues, to avoid grade crossings of the Boston & Albany Rail-
road ; plans, estimates of cost, and models of various methods
of providing increased bridge facilities between Boston and
Charlestown ; repairs of pile-work and capping of South
Paving-yard wharf, etc.
In the draughting-room the usual large amount of work of
a general character, such as copying, tracing, blue-prinlirsg,
and revising plans, has been done. Plans and specifications
for the following work have also been made : —
Beacon Entrance bridge over Boston & Albany Railroad,
Back Bay park.
Foot-bridge over Boston & Providence Railroad at West
Rutland square.
New centre for Congress-street brido-e draw.
New centre for West Boston bridge draw.
Iron-work, etc., connected with the engines and boilers,
and their foundations, at Improved Sewerage pumping-sta-
tion.
All inspection of the above work, both in the shops and
during erection, has been done by Mr. John E. Cheney,
designer and principal draughtsman, and his assistants. The
erection of the Blakemore-street, Common wealth- avenue,
and Broadway-extension iron bridges was under the same
supervision.
B. —WATER-WORKS.
Sudhury-River Reservoirs, Farm Pond, and Lalce Co-
chituate. — On January 1, 1882, Reservoirs Nos. 2 and 3
were full ; Reservoir No. 1 was empty, the water having
been drawn off for the purpose of repairing the 48-inch pipe
leading from Dam 2 to the gate-chamber at Dam 1. On
January .3, Reservoir No. 1 commenced to fill, and on Janu-
ary 11 water was flowing over the crest of the dam. All of
the reservoirs remained full until July 1. During July and
August Reservoir No. 2 was lowered very rapidly, and on
September 3 it was practically empty. Reservoir No. 3, which
26 City Document No. 53.
had also been falling during the month of August, continued to
fall until September 22, when its surface was 7.48 feet below
the crest of the dam. Reservoir No. 1 was drawn upon for
the city's supply from July 26 to August 5, about 160,000,-
000 gallons being taken for that purpose, lowering its surfsice
about four feet. Since the latter date no water has been
drawn from this reservoir, except the 1,500,000 gallons per
day which are allowed to run mto the river.
During the month of September rain-fall amounting to
8.74 inches raised the surface of Reservoir No. 2 about
11.5 feet.
During the month of October, and until November 24,
w^ater for the city's supply was drawn from Reservoir No. 2,
and Reservoir No. 3 was allowed to fill. At the latter date
Reservoir No. 2 was 11.41 feet, and Reservoir No. 3 was
2.20 feet below the crests of their dams. From November
24 to December 27 water was drawn from Reservoir No. 3,
and its surface lowered 5.97 feet. Reservoir No. 2 during
the same time had risen 12.12 feet. At the present time,
January 1, 1883, Reservoir No. 1 is 154.66 feet; Reservoir
No. 2, 165.65 feet; and Reservoir No. 3, 167.96 feet above
tide-marsh level.
From January until the middle of April the water in Farm
pond was kept at about grade, 146.00, in order that the
water from the reservoirs might be run through the tempo-
rary channel. Since April 20 the pond has been kept at or
near 149.25.
Lake Cochituate, on January 1, 1882, was 128.27 feet above
tide-marsh level, or 6.09 feet below high water ; on Febru-
ary 21 the lake was so full that waste was begun at the out-
let-dam.
The lake remained at or near high-water mark until June 8,
after which time it gradually fell, and on December 22 it
reached the lowest point during the year (126.25), 5.22 feet
above the conduit invert.
Mystic Lake. — At the beginning of the year 1882 the
lake was full, and it remained at or near high-water mark
until the hrst of July. During July and August the surface
fell, and on Septeml)er 11 it was 2.4 feet above tide-marsh
level, or 11 inches above the top of the conduit; October 1
it had risen to grade, 4.15 ; November 1, 5.42 ; December 1,
5.43 ; and January 1, 1883, 6.02 feet above tide-marsh
level .
Consumption. — The average daily consumption from the
combined works, for each month, has been as follows : —
Report of the City Engineer. 27
Sudbury nnd
Cochituatc Works.
Mystic Works.
Total.
January
. 32,151,100
7,816,200
39,967,300
February
. 34,662,300
7,937,300
42,599,600
March .
. 32,256,300
6,573,700
38,830,000
April .
. 30,827,000
5,946,100
36,773,100
May . .
. 28,738,000
5,793,600
34,531,600
June
. 33,178,400
6,664,400
39,842,800
July .
. 30,992,600
6,881,400
37,874,000
August .
. 34,149,300
6,912,200
41,061,500
September .
. 31,691,600
5,964,100
37,655,700
October
. 31,563,800
6,011,300
37,575,100
November .
. 31.318,700
5,577,400
36,896,100
December
. 32,352,800
6,877,600
39,230,400
Average .
. 31,970,800
6,574,400
38,545,200
The consumption from the Sudbury and Cochituate works
shows an increase of about 3 per cent, over that of the year
1881, while that of the Mystic works shows a decrease of
about 8.5 per cent. About one-half of this decrease was due
to a reduction in the amount furnished from those works for
the supply of East Boston. The total consumption shows
an increase of 330,300 gallons per day, or about one per
cent, over that of 1881.
The daily average consumption per head of population has
been 91 gallons from the Sudbury and Cochituate works, 77
gallons from the Mystic works, and 88 gallons from the
combined supplies.
Of the 11,669,300,000 gallons consumed on the Sudbury
and Cochituate works, the Sudbury-river works have fur-
nished 7,735,200,000 gallons, as follows : —
January, 595,000,000 July, 646,900,000
February, 975,700,000 August, 655,800,000
March, 1,002,300,000 September, 308,900,000
April, 781,200,000 October, 570,300,000
May, 502,800,000 November, 572,300,000
June, 491,800,000 December, 632,200,000
Average daily amount furnished, 21,192,300 gallons, or
66.3 per cent, of the total consumption.
All of the above quantity has been sent from Farm pond
to Chestnut-Hill reservoir, none having been sent to Lake
Cochituate during the year.
28 City Docujient No. 53.
High-Service Works.
The average daily quantities pumped at the Highland
station duriuff each month are as follows : —
January,
2,711,800
July,
3,023,000
February,
2,733,000
August,
3,014,000
March,
2,552,000
September,
2,779,670
April,
2,575,100
October,
2,673,500
May,
2,792,000
November,
2,698,030
June,
3,040,580
December,
2,839,000
The daily average for the year has been 2,786,545 gallons,
an increase of 15.7 per cent, over that of 1881.
At the East Boston pumping-station the daily average
amount pumped has been 422,540 gallons.
Waste of Water.
Mention is made in my last annual report of the trial in
the Charlestown District of the Deacon system of preventing
waste of water. A full statement of the results of this trial
is given in my last report to the Water Board. These results
show that a very large percentage of the water supplied to
the city is wasted, and that the prevention of this waste is
possible at a reasonable cost. The subject is so fully con-
sidered in the report above referred to, that I only allude to
it here for the purpose of calling especial attention to facts
and figures in relation to a matter which I consider one of the
most important for the consideration of the City Council.
Mystic-valley Sewer.
The treatment of the sewage from the Mystic valley, in the
manner described in my last report, has been continued during
the year with as nuich success as could be expected.
On July 15, at my request, the work, which no longer re-
quired the direct supervision of this department, was placed
in charge of the superintendent of the iMystic AVorks.
The clianofc of le2:islation asked for last winter, in order to
reduce the cost of maintenance of the present expensive sj's-
tem of pumping, and to accomplish other improvements for
the purification of the loAver IVIystic pond, was not obtained.
An attempt should be made to procure it at the earliest op-
portunity.
Sudbury-river Basin, No. 4.
The M ork on the dam for this basin was continued, although
to a small extent, during the winter months, but was resumed
more actively in the spring. 31,000 cubic yards of loam and
Report of the City Engineer. 29
perishable materials have been removed from the site of the
embankment. 19,300 cubic yards of trench excavation, ex-
tending to the underlying bed-rock which forms the foundation
of the masonry, were removed during the year. This excava-
tion was made to a greater depth than was indicated by the bor-
ings, and was somewhat dela^^ed by the blasting of a large
number of heavy boulders, wdiieh could not be removed by
other methods ; the shaping of the upper surface of the ledge
required also considerable time and labor. 1,727 linear feet
of trench were thus excavated, leaving 326 feet undone. The
concrete structure forming the centre wall of the dam and
the support for the discharge-pipes is completed for 1,383
linear feet of trench, and partially so for 100 feet, leaving
244 feet of open trench in which the masonry work remains to
be done. 7,218 cubic yards of concrete have been laid, and
the upper face of the wall has been plastered with double
layers of" Portland cement mortar.
The roll-way and a portion of the overflow are built, and
the foundation of the gate-house is completed to the surface
of the ground. In all, 2,286 cubic yards of stone and brick
masonry (exclusive of concrete) have been laid.
18,500 cubic yards of the dam embankment are in place,
and about 20,000 cubic yards of loam have been piled up ready
for removal. In accordance with an arrangement between
the Boston Water Board and the Park Commissioners,
the road-bed for a spur track connecting the Hopkinton
Branch railroad with the valley of the Cold Spring brook
has been graded, and will be used for removing the loam ex-
cavated from the basin to the Back Bay park. This track
will be extended from time to time to cover the whole area
to be cleaned.
The cost of construction of Basin 4, to Jan. 1, 1883, in-
cluding the cost of plant on hand, is $162,469.35. The cost
of removal of loam, including cost of steam-excavator, and of
grading 2,900 feet of track, is $10,963.92.
There were, on an average, during the summer and fall,
225 men and 30 horses employed on the work. At present
there is a small force at work finishing the excavation of the
trenches and quarrying stone for rubble masonry.
For reasons given in my last report to the Water Board , I
am of the opinion that it would be advantageous to the city
to finish this work as it has heretofore been conducted, — by
day's labor.
Miscellaneous.
Plans have been made showing the results of survej^s and
borings during the month of March, in the vicinity of the
30 City Document No. 53.
present dams at the outlet of Lake Coehituate, for the pur-
pose of determining the most suitable location for a new dam.
About 120 feet of 48-inch pipe have ])een laid near Com-
monwealth avenue, under the channel of the pond in the Back
Bay park. The pipe is supported by a pile foundation con-
sisting of spruce piles driven in pairs at distances apart of 5^
feet crosswise and about 6 feet lengthwise of the trench, and
capped crosswise with 10 X 10-inch spruce caps 8 feet 6 inches
long. The sides of the trench in which the pipe is laid, are
composed of 4-inch tongued and grooved sheeting.
All of the gates and hydrants connected with the distribu-
tion system of the City proper have l)een located, and new
and more accurate plans, on a scale of 100 feet to an inch,
have been made, showing the actual location of all the water-
pipes, gates, hydrants, etc.
The distributing mains of the Sudbury and Coehituate
works have been extended about seven miles during the
year.
C — IMPROVED SEWERAGE.
In last year's report I stated that the appropriation then
available for this work was insufficient to complete it in
accordance with the original plan, as modified by subsequent
additions and alterations. A little later I submitted to the
Committee on Improved Sewerage an estimate of the further
sum needed, and the reasons why it was required.
This statement was incorporated by the committee in their
request made to the City Council April 17, 1882, for an
additional appropriation of $1,500,000. This amount hav-
ing been voted by orders dated May 12, 1882, is now avail-
able for the prosecution of the work. I am happy to say
that the cost of construction during the past year, and the
present condition of the work, give every assurance that the
appropriation is now ample to cover all reasonable expense of
completing the system in a substantial manner in accordance
with the plans. Satisfactory progress towards completion
has been made during the past year. A detailed account of
it will be found in Mr. Clarke's report. I shall therefore
merely present a brief summary of the present state of the
work, and of what is required to complete it.
A natural division of the whole system is into four prin-
cipal parts, viz. : —
1. The main and intercepting sewers which convey the
sewage of the city to the pumping-station.
2. The pumping-station at which the sewage is raised.
3. The outfall sewer by which the sewage is conveyed
from the pumping-station to Moon Island.
Report of the City Engineer. 31
4. The reservoir at Moon Island in which the sewage is to
be stored, and from which it is to be emptied into the sea
during the early ebb-tide.
1. About three-quarters of all the intercepting sewers,
which it is proposed to build within the city, are practically
tinished and in condition for service. By the simple raising
of valves, already built into the city sewers, near their out-
lets, the sewage from the greater part of the city could now
be diverted and made to flow to the pumping-station. Ex-
tensions of these sewers are now in progress, and can be
continued as required, without interfering with the use of
portions already luiilt. These extensions will, in the future,
almost without exce})tion, be built in crowded thoroughfares
and in filled land, where very many unforeseen obstacles will
be encountered, requiring constant variations in location and
in methods of construction.
It would not be wise, and is not necessary, to hurry this
work ; and, to accomplish it successfully, without serious in-
convenience to abutters and the public, will require that it
shall be entirely within the control of the city, and be man-
aged by city superintendents.
2. The pumping-station, also, is practically in condition
for service. The sewage could now be raised at this point
without interfering with the erection of permanent buildings
and other minor details of work which are yet to be done.
It was supposed that the interests of the city would be best
served by the use of the sewers and pumps now completed,
to divert the sewage of the city from those points where it
is most troublesome into Dorchester bay, where, in the
opinion of those most competent to judge of the matter, its
temporary discharge would create no nuisance. Appre-
hension of danger to certain districts, however, arose, and
the following act was obtained from the Legislature, May
26, 1882; —
Be it enacted by the Senate and Honse of Ee2Jresentatives in General
Court assenMed, and by authority of the same, as folloivs : —
Section 1. No part of the contents of the main sewer now or here-
after to be constructed, running south-easterly from the direction of
Charles river, in the city of Boston, shall be discharged at or near the
shore of the Calf Pasture, so called, in Dorchester bay, or at any place
in Boston harbor, or vicinity, except at Moon island. The supreme
judicial court, or any justice thereof, upon the jietition of not less than
ten taxable inhabitants of the city of Boston, may restrain, by injunction
or otherwise, any violation of the provisions of this act.
It will be seen that the act is prohibitory, and that the
sewage can be discharged nowhere except at Moon island.
32 . City Document No. 53.
The Leavitt pumping-engines were first started July 26,
1882, and have each been run for short periods at intervals
since. AVhilc it has, of course, been impossilde to fully test
them with sewage, it may be said that, in the opinion of ex-
perts, from observation of their appearance and performance,
they will amply fulfil all requirements as to capacity, duty,
and durability, and will prove to be admirably adapted to
their work.
By the terms of the contract under which they were fur-
nished it was stipulated that the contractors should maintain
the engines and repair any defects which might be developed
in running them during a probationary period of twelve
months after their completion. Also, that the city might re-
tain, during that time, five per cent, of the contract price,
to guarantee the performance of said requirements. As the
efiect of the act, just cited, was to postpone indefinitely the
beginning of said period of probation, it was thought for the
interest of the city to release the retained percentage and
obtain in its place a bond by which the contractors, in con-
sideration of said present release, agreed to extend the
period of probation to January 1, 1885, and to return said
percentage, on demand from the city, at any time within said
period, should any contingency arise to require it. This
arrangement was concluded October 12, 1882, and is thought
to innure to the advantage of both parties.
3. Fair progress has been made during the past year in
constructing the outfall sewer from the pumping-station to
Moon island. From the pumps to the tank-sewers the force-
mains are already in place. The tank-sewers which connect
these with the tunnel under Dorchester bay are partly con-
structed, and can be finished during the coming season.
The tunnel will be completed early in the summer. It is
entirely excavated, and nearly the whole of it is now
lined with brick-work. It is a matter for congratulation that
this piece of work has been successfully accomplished.
While it would not have been attempted had there l)een
doul)ts of its feasibility or that difliculties Avould be en-
countered which could not be surmounted, yet such work,
from its nature, is always somewhat uncertain, and, until the
last foot is penetrated, there are possibilities of meeting
demoralized rock, open seams, excessive amounts of water,
etc., which may cause serious delay and expense. These
contingencies ))eing now impossible, the tunnel may be said
to be an assured success, and to aflbrd the best and most
economical route for reaching the point of discharge. From
the end of the tunnel the outfall sewer has been constructed
towards Moon island, as far as is considered at present ex-
Report of the City Engineer. 33
pedient ; should it be thought wise to permit further time for
settlement of the embankment from Squantum to the island
before building the permanent masonry structure on it, a
temporary conduit can be built during the coming year, so
as not to delay the use of the system.
4. The new contractors have prosecuted the construction
of the reservoir on Moon island with great energy durino- the
past year, and there is every assurance that the structure will
be put in condition for service during the coming season,
although the completion of muior portions of the work may
extend into next year. The outlet sewer section, through
which the sewage accumulated in the reservoir, will be dis-
charged at high-tide into the current setting out of the har-
bor between Moon and Long islands, is yet to be built.
Plans and specifications for it are prepared, and it is expected
that it will be contracted for in March or early April of this '
year. It is not certain that it can be wholly built during the
present season ; but the use of the rest of the system need
not be delayed until its completion.
From the foregoing statements it will be seen that the in-
tercepting system of sewerage is at present in condition for use
up to and including the point w^here the sewage is raised
high enough to be discharged into the outer harbor, and that
beyond this point it can probably be put iij condition for use
w ithin a year. Extension and perfection of the system may
continue for a year or two longer. The work, as a whole,
and in its parts, is known to be durable and efficient, and no
doubts are entertained that it will accomplish the good results
which have been claimed for it.
The total appropriation for improved sewerage is $5,253,000.
The gross expenditure to Jan. 1, 1883, including that for pre-
liminary surveys, has been $3,389,104.07, leaving a balance
of $1,863,895.93.
Below are given extracts from the report of Mr. E. C.
Clarke, principal assistant-engineer of this work, wdiich relate
in detail the operations of the past year, and items of interest
connected with them.
Extracts from Mr. Clarke's Report.
The following is the customary annual statement, showing,
in tabulated form, the different sections of sewers already
built or in process of construction, with the size and extent
of each, the lengths built prior to and during the past year,
whether done by contract or otherwise, and the builder's
name.
34
City Document No. 53.
TABUliAR STATEMENT OF PROCJRESS —
Section.
1. Main
2. Main
3. Main
4. Main
4^. Main
5. Main
6. Main
1. West Side
2. West Side
3. West Side
1. East Side
2. East Side
3. East Side
4. East Side
1. Stony Brooli
2. Stony Brook
1. South Boston
3. South Boston
4. South Boston
6. South Boston
Roxbury Canal .
Chester Park . ,
Pumping-Station .
1. Outfall Sewer . ,
2. Outfall Sewer . ,
3. Outfall Sewer . ,
Locality.
In Camden St., from Huntington ave. to Tremont st
In Camden St., from Tremont St. to Washington st
In Washington St., and E. Chester park, from Camden st. to Albany st.
In E. Chester-park extension, from Albany st. to Magazine st. ...
In E. Chester-park extension, from Magazine st. to Clapp st
In Clapp and Mt. Vernon sts., from E. Chester park, to O.C. R.R. .
In Mt. Vernon-st. extension, from O.C. R.R. to Old Harbor Point . .
In Camden, Falmouth, Dalton, and Hereford sts., from Huntington
ave. to Beacon st
In Beacon St., from Hereford st. to Charles st
In Charles st., from Beacon st. to Cambridge st
In Albany St., from E. Chester park, to Dover 8t
In Albany st., Lehigh St., and O.C. R.R. freight-yards, to Federal st. .
In Federal St., from O.C. R.R. freight-yards, to Summer st
In Atlantic ave., from Summer st. to Belcher lane
In Tremont and Cabot sts., from Camden st. to Ruggles st
In Cabot, Hampshire, Elm wood, Ruggles, and Tremont sts., about
Stony Brook
In Ninth st., from H. st. to N. st
In Von Ilillern st.. Locust st., Washigton ave., and Hyde St., from
Mt. Vernon st. to Dorchester ave
In Dorchester ave., from Hyde st. to B. st
In Dorchester ave. and Foundry st., from B. st. to First st
In Albany st. and E. Chester park, from Northampton st. to Roxbury
Canal
In E. Chester park, from Albany st. to Harrison ave
Connecting M.nin Sewer and Filth-Hoist and Engine- Wella and Salt-
Watcr Conduit
From Pumping-Station to Dor. B.ay Tunnel
( Excavation
Tunnel imder Dorchester Bay <
( Brick lining
Squantum Neck to Moon Island
Totals
Eepoet of City Engineer.
35
OIPROVED SEWERAGE COWSTRHCTIOIS.
Size in feet and inches.
Length
in feet.
Built prior
to Jan. 1,
1882.
Built Jan.
1, 1883.
Built by
7 ft. 8 in
1675.5
1675.5
1675.5
P. J. Condon.
8 ft. 5 in
1390.5
1390.5
1390.5
P. J. Condon.
8 ft. 5 in
1795.
1795.
1795.
John Cavanagh.
9 ft
2506.5
2506.5
2506.5
Charles Linehan and City.
City.
9ft
1894.
3381.
1894.
3381.
1894.
3381.
(9ft )
no ft. 6 in \
Hoblitzell, Condon, and
Hoblitzell and City.
10 ft. 6 in
40S8.
4088.
4088.
Clinton Beckwith, and J. V.
Quackenbush.
4 ft. 9 in. X 0 ft. 6 m. .
4282.
4282.
4282.
City.
<4ft. 9in. X5ft.6in. )
H ft- X 4 ft. 6 in. . . )
5043.
5013.
5013.
City.
4 ft. X 4 ft. 6 in . . . .
1832.
1832.
1832.
Thomas McCann.
5 ft. S in
4524.5
4524.5
4524.5
A. H. Delameter & Co., and
R. A. Malone.
( 5 ft. X 4 ft )
> 5 ft. X 3 ft )
2331.5
650.
2331.5
City.
2 ft. 8 in. X 4 ft. 6 in. .
2108.
2108.
City.
2 ft. 8 in. X 4 ft. 6 in. .
2032.
250.
City.
4 ft. 8 in
2135.
2135.
2135.
Myles Tierney.
( 5 ft. X 4 ft. 6 in. . . )
, 2 ft. X 3 ft [
15 in. pipe )
4500.
4500.
4500.
City.
3 ft. 2 in
(6 ft )
2717.5
3739.
2717.5
3739.
2717.5
3739.
Stephen Connolly & Co.,
and City.
( 4 ft. 6 in. X 3 ft. . . )
Charles Linehan.
4 ft. 9 m. X 5 ft. 6 in. .
33.50.
33.50.
3350.
Hoblitzell, Condon, and
HobUtzell and City.
3 ft. X 5 ft
2820.
600.
City.
4 4 ft. 6 m )
left i
620.
725.
620.
620.
725.
City.
4 ft. 6 in
City.
(10 ft. 6 in )
J 9ft \
602.
1250.
507.
602.
Partial.
818.
City.
City.
( 5 ft. 6 Ln )
Double 8 ft. X 16 ft. . .
Abt. 10 ft. 6 Ln
(7004.)
(5913.)
(7004.)
7 ft. 6 in
7004.
844.
5012.
R. A. Malone.
11 ft. X 12 ft.
5989.
600.
1322.
W. C. Poland & Son and
C. W. Parker & Co.
74335.
52044.5
63212.
36 City Document No. 53.
An examination of the foregoing table shows that a con-
siderable amount of sewer construction has been completed
during the past year, and that extensions of the intercepting
sewers located in the streets of the city proper have been
chiefly constructed by the city under its own superintendents.
This is due to the fact that such construction is now
confined to crowded thoroughfares, in which peculiar man-
agement is required to prevent serious obstruction to travel
and the business of abutters, and also because these opera-
tions being principally carried on in filled land, beds of
dock-mud, old walls, wharves, and other obstacles are con-
tinually encountered, which require a frequent variation in
the methods of construction, which could not be foreseen and
provided for in the specifications of a contract. This will be
understood from the following account in detail of the opera-
tions during the year upon difierent sections of the work.
Section Two, East Side.
This section extends from Dover street through Albany to
Lehigh street, at which point it enters private land, and
crosses the freight and switch yards of the Boston and Albany
and Old Colony Railroad Companies to Federal street near the
bridge. In Albany and Lehigh streets are the tracks of the
Albany street Freight Railway Co., which are used by the
stone and lumber yards on Albany street, but especially by
the Hinckley Locomotive Works, to convey locomotives to
and from their shops. Itwas considered questionable whether
these tracks could be maintained for service during building
operations. In the railroad yards are about forty lines of rails
in constant use, which it was very important should not be
disturbed. The whole section traverses filled land, underlaid
by beds of mud from 5 to 20 feet deep below the liottom of
the sewer, Avhich is itself several feet lielow the level of low
tide. The sewer is oval, 5 feet high, and required piling
for its support. It was built partly of wood, lined with two
inches of concrete, and partly of brick-work resting on a solid
cradle of wood six inches thick. At difierent points ob-
structions in the shape of old walls and wharves were en-
countered, which admitted sea-water freely to the trench, so
that, as a rule, work could only progress during low stages
of the tide.
As stated in last year's report, work began on this section
in Septeml)er, 1881. Travel upon the streets was not inter-
rupted, and with considerable difiiculty the freight railway
tracks were supported and maintained. As it would have been
impossible to have had an open trench through the Albany
Eeport of the City Engineer. 37
and Old Colony yards without interfering with their traffic,
operations at this point were carried on entirely below the
surface. The tracks were supported by stringers, and the
spaces between them floored over. By the use of special
machinery all the earth excavated and refilled, as well as all
materials for construction, were conveyed by tracks suspended
below the floor. The trench was well braced, and its sides
protected by lag sheeting, which, together with the piles
driven to support the sewer, were all put in place without
encroaching upon the surflice. It is believed that not a
single train was delayed, nor any inconvenience caused by
these operations.
A large regulating apparatus, similar to the one of which
a plan was given in the report for 1880, was put in this
section. The chamber containing it is located on Albany
street, just north of Dover street. The apparatus will con-
trol the flow of the entire east-side intercepter above this
point, thus doing away with the necessity of separate small
regulators for each city sewer. By this means, during heavy
rain-storms, the amount of water coming from the higher dis-
tricts of the central and northerly portions of the city can be
reduced to any extent, and the sewer left free to receive rain
from the districts south of Dover street, where the cellars
are apt to be inundated at such times. At this section con-
nections are made with the Osw^es^o-street and Harvard-street
main city sewers, and also with the Dover-street sewer. The
former two outlets have been supplied with chambers con-
taining new tide-gates, similar to those shown in last year's
report.
Dover-street Connection.
According to the usual practice in such cases, the Dover-
street sewer would have been connected with the intercepter
at or near the point in Albany street where their two loca-
tions intersect. But it was found, in examining the city
sewers with reference to our connections with them, that the
main in Dover street was not in condition to be intercepted
at an}' point west of Harrison avenue. Between that street
and its outlet it is a rectangular wooden structure, 5X6 feet,
located on the north side of the street, close to a stone retain-
ing-wall, and surrounded by loose stone ballast. It is con-
siderably broken, so that the tide-water, which follows the
wall and ballast, has free access to the sewer at high tide, and
would flow into the intercepting sewer and so reach the
pumps. From Harrison avenue westwardly the sewer is of
brick, and is believed to be tight. A set of tide-gates are
already built at this point. Accordingly, the connection was
38 City Document No. 53.
made with the brick-sewer west of the tide-gates, and a three-
feet oval brick branch sewer built from this point to convey
the sewage to the intercepting sewer at x\lbnny street. The
distance is about 575 feet, and some difficulty was ex-
perienced in tinding a practicable line free from old walls
and wharves and the ivater which follows them. The sewer
was finally located on the line of the southerly sidewalk, on
which side are no permanent buildings, so that the minimum
of inconvenience was caused, and travel on the street was
not impeded. The w^ork was done during June, July, and
August, and is now complete in condition for service.
Section Three, East Side.
This section extends in Federal street, from near the bridge,
to the beginning of Atlantic avenue at Summer street, a dis-
tance of 2,108 feet. The street is occupied by double horse-
railroad and single freight-railway tracks, and beneath its
surface are one sewer, two water, and two gas pipes. Beds
of mud extend from 5 to 20 feet below the bottom of the new
sew^er and dock-walls, and timber structures were frequently
encountered. A location on the east side of the street was
found to be most practicable, and the sewer was built by
methods which left the roadway open for travel. By flooring
over the trench at intervals, passages were maintained
through the excavating machine to the yards and wharves
bordering Fort-Point channel. The freight-railway tracks
were shifted towards the centre of the street, and were used
during the day for the passage of horse-cars in one direction.
Bricks, cement, and other materials were piled on the outer
edges of both sidewalks where they would cause least incon-
venience, and always so as to leave a clear passage-way four
feet wide. Endeavors were made to cause the least possible
annoyance to corporations and individuals ; and, in general,
these etforts seemed to be appreciated and reciprocated by
the public, so that complaints were rare. The work was
chiefly built during the autumn, and consists of an oval
sewer 4 feet 6 inches by 2 feet 8 inches in diameter, with an
8-inch brick arch and 2-inch brick invert, resting on a solid
plank cradle 4 inches thick, supported for a part of its length
on piles. Connections have been made with the Federal-
street and Summer-street city sewers, and chambers with
new tide-gates built to protect these connections.
Section Four, East Side.
This is a continuation of the preceding section. Construc-
tion of it began in November, and, unless the season should
Eeport of the City Engineer. 39
prove unusually severe, may be continued throughout the
M^hiter. It extends in Atlantic avenue from Summer street
to Belcher lane. The sewer is oval, 4 feet 6 inches by 2 feet
8 inches in diameter. It is located on the westerly side of the
street, near to the centre line of old Broad street before the
widening. It was hoped that, hy adopting this location, the
head and side walls of many of the docks which formerly
extended to Broad street would be avoided, and also the tide-
water which would be sure to follow such structures. Al-
though this hope has not been fully realized, it is probable
that less serious obstacles have been met with than would
have been found on the easterly side of the avenue, and the
filling being less recent is more compact and more impervious
to water. The location adopted may interfere somewhat
with the traflfic of the large warehouses on the same side of
the avenue ; but, by using special precautions, a clear passage-
way for teams has thus far been maintained, and no reason-
able causes for complaint have been given. This section will
intercept the Congress-street, Pearl-street, and Central-wharf
sewers, and by its subsequent extension furnish the outlet for
the sewage from the east side of the north end of the city to
Hanover street.
Chester-park Sewer.
As stated in last year's report, a section of sewer, called
Roxbury-caiial sewer, was built to intercept all the sewage
which formerly flowed into Roxbury canal above East Chester
park. The city sewer in Chester park that was thus inter-
cepted was a three feet square wooden box, somewhat out of
shape, and had settled, probably on account of the building
of the main sewer near to and below it, so that it was a little
lower at Albany street than the new sewer with which it con-
nected. In the interest of good sewerage for the district it
was thought best to at once extend a brick sewer to replace
the present wooden one between Albany street and Harrison
avenue. This has l)een done T)y an arrangement with the
Sewer Department. Work began in September, and was
completed by the end of the year. The sewer is circular,
4 feet 6 inches in diameter, about 730 feet long, and is sup-
ported on piling for three-quarters of its length. It connects
at its east end with a bell-mouth connection chamber, and at
its west end with brick sewers in Harrison avenue and in
Chester park west of the avenue.
Section Five, South Boston.
This is an extension from Section 4, which ended on Dor-
chester avenue, just south of the Old Colony Railroad. Two
40 City Document No. 53.
routes from this point, by which to reach Foundry street,
were considered. By one, the sewer, turning to the left
through private land, passed under the road-beds of the Old
Colony and N.Y. & N.E. Railroad Companies, and then under
the freight yard of the former company. The other, keeping in
Dorchester avenue, passed under both railroads, and turned
into Foundry street at its junction with the avenue. The
latter route, though somewhat longer, was tinally adopted,
as avoiding land damages and possible injury to buildings.
Considerable ditficulty was encountered in passing under the
abutments of the bridge on Dorchester avenue, over the
N.Y. & N.E. Railroad. These were underlaid by running
sand, and the northerly abutment, Avhich had been built with-
out mortar, had to be taken down over the sewer. The
bridge, however, was not endangered, nor was travel over
it interrupted. The sewer is of brick, oval, 5 feet high.
Where it passes under the N.Y. & N.E. tracks its shape
has been somewhat altered, keeping the top arch lower, so
that if it ever should be desirable to lower the road-bed for
a few feet under the bridge, this can be done without inter-
fering with the sewer. AVork on this section began in Sep-
tember, and will probably continue during the winter. The
city sewers intercepted by it are those in B street, Fourth
street, and First street.
Salt-water Conduit.
This structure at the pumping-station, 5^ feet in diam-
eter, designed to bring salt water to the condensers and
pumps, has been completed during the 3'ear, and is ready
for service, except for a little dredgiiig, which must be done
in the dock in front of its jnlet.
Main and Intercepting Sewers.
To this account is charged the expense of maintaining, at
intervals, a small force, consisting of a foreman, one car-
penter, and four laborers, who take care of the sewers
already built, maintain the tide-gates in a state of maximum
efficiency, clean and slush penstocks, flushing-gates, and
other iron-work, remove gravel which gets into the sewers
around man-hole covers, and construct any minor details of
Avork omitted for any cause when the sewers were built. It
was found necessary, for the convenient and safe working
of the penstocks and flushing-gates already 1)nilt into the
sewers, to provide them with counterbalancing apparatus.
Eight sets of these were furnished by Cook, Rymes, & Co.,
Keport or THE City Engineer. 41
of Boston, under a contract dated Jan. 12, 1882, and they
Avere put in place by the party aboA^e referred to. In all,
this party has been employed about eight months during the
past year.
Filth-hoist.
This necessary part of the system, situated at the end of
the main sewer, and through which the sewage flows before
reaching the pumps, has been completed, and put in condi-
tion for service during the past year. The foundations and
chambers, extending from 17 feet below low tide to 18 feet
above that elevation, were chiefly built during 1881. Last
summer the superstructure, consisting of a granite-stone
building, 30 by 37 feet, was erected, under the supervision
of the City Architect. Two iron penstock gates, 7 feet by 6
feet 6 inches each, have been built in place. These serve to
divert the flow^ of sewao-e through the screens on either side
of the structure, leaving the other free for examination or
repairs. They can be protected in front by stojj-planks, for
which grooves are provided. The gates are counterbalanced,
and are Avorked up and down by hydraulic pressure from the
city water main, acting through cylinders and pistons. This
pressure is sufficient to move them freely ; but to start them,
when down with a head of water against them, an hydraulic-
force pump has been added, by which the initial pressure can
be increased to any extent. Behind each gate are a pair of
screens, or fllth-cages, formed of vertical bars of iron, with
one-inch spaces, through which the sewage Avill flow, and by
which dead animals, pieces of cloth, wood, and other solid
matters likely to clog the pump-valves, will be intercepted.
The cages are counterbalanced, and are raised for the re-
moval of their contents, and again lowered by steam-power.
Steam has been brought under ground from the boiler-house
for this purpose. A pair of steam radiators will keep the
building Avarm in Avinter. The cages, with their engines and
gearing, Avere furnished and put in place by the Coffin Valve
Co., under a contract dated Feb. 20, 1882.
Pumping— station.
A considerable part of the work for the year has been per-
formed at this locality, Avhich properly includes the tilth-
hoist just referred to. Under the direction of the City
Architect work has begun on constructing the permanent
buildings, including engine, boiler, and coal-houses. These
are built chiefly of granite block stone obtained from the old
Beacon-Hill reservoir. This department paj's the city from
42 City Document No. 53.
$5.00 to $7.00 a yard for the stoiie, and also pays for its con-
veyance to Old-Harlior Point. The coal-house is already
built and roofed in, needing only its windows and internal
fittings to make it complete. The walls of the boiler-house
are about finished, and those of the engine-house will be soon
started. For re-dressing the stones, a yard and sheds, con-
necting with a spur-track of the Old Colony Railroad, are in
operation. Two additional steel boilers, making four in all,
have been furnished and set in place by Kendall & Roberts
of Caml)ridgeport. The four boilers have been connected to
form one battery, and, with their pipes, have been suitably
covered. Two i3air of double-acting feed-pumps are in
place and connected, also two double-acting salt-water pumps
for pumping salt-water for the condensers from the salt-water
conduit into a tank. The boiler-house, with all its apparatus,
may be said to be in running order.
In the engine-house the two Leavitt engines have been put
in complete condition for service, and each of them has been
run sufficiently, with pure water, to demonstrate their effi-
ciency. They have been protected from the danger of rust
and are waiting the time for actual work. The foundations
for the Worthington engines and pumps have been completed,
and these machines will be put in position during the coming
year. A large bilge-pump, for clearing the galleries and
pump-wells of the engine-house, is in place, and has been
utilized during the year to keep the main and intercepting
sewers free from water by pumping all which leaks into
them.
Nine cast-iron gates, with their hoisting-engines and gear-
ing, have been set in place here during the past year. They
were furnished by the Coffin Valve Co., under a contract
dated December 3, 1881. Eight of them, 6 feet 3|^ inches by
4 feet 9^ inches, control the flow of sewage to the pump-wells
and one, 3 feet 9^ inches square, admits salt-water from the
salt-water conduit. To warm the engine-house and machinery
and prevent water of condensation forming on the engines, a
s^^stem of steam-pipes and radiators has been put in by the
Walworth Manufacturing Co., at a cost of about $1,300. The
48-inch cast-iron force-mains, which arrived last winter, and
which connect the Leavitt pumps with the tank-sewers at the
pipe-chamber, have been laid in place and jointed during the
past season, xlbout 180 hard i)ine stoi)-})lanks, of diflerent
sizes, for use in the pipe-chamber and about the various gates
and wells, have been fitted, ironed, and painted or oiled, ready
for use. The salt-water conduit has been completed, and the
portiou of sea-wall at its end is built. Further extcMisions of
this wall and the wharf outside of it remain to be constructed.
Ji
Report of the City Engineer. 43
The channel connecting the city dock at this point with the
main ship channel of Dorchester bay became somewhat
shoaled with mud during the year, and was dredged, without
cost to the city, down to twelve feet below low water, by the
Old Harbor Pier Co., under the provision of their contract,
b}^ which the channel is to be maintained without charge
until the completion of the pier now ])uilding by them for the
city. About 12,000 yards of gravel tilling has been received
from the Old Colony Railroad, and used in grading about the
pumping-station grounds. A telephone-wire now connects
the pumping-station with City Hall and several department
yards in the city.
Section One, Outfall Sewer.
On this section, commonly called Old-Harbor Pier, ex-
tending from the pumping-station to the tunnel, work has not
progressed as rapidly as could have been desired. The con-
tractors have completed the sea-wall at the outer end of the
pier by building 226 yards of cut-stone masonry and 324
yards of concrete. They have also put in place during the
season 4,060 yards of filling, 1,915 yards of ballast, 4,367
tons of rip-rap, and 180 piles. Except immediately about
the tunnel-shaft, the pier is filled to about grade 18, and
about 36,000 yards of filling are needed to complete it. The
stone pipe-chamber at the westerly end of the pier was fin-
ished by the city early in the year, and a temporary wooden
sluice-way from it constructed, which was used to discharge
water while testing the Leavitt engines.
In July the city l)egan l)uilding the tank-sewers, to extend
about 1,250 feet, from the pipe-chamber to the tunnel shaft,
and about 800 feet of the lower half of this structure was
completed and protected by the end of the season. Two
machine concrete mixers have been procured, and will be used
next season. The general character of the tank-sewers will
be understood from the accompanying plate. As will be seen,
they consist of a monolithic structure of concrete, forming two
conduits, each 16 feet high by 8 wide. The bottom portion,
up to the straight walls, is formed of Rosendale cement, sand,
and pebbles, in the proportion of each, respectively, of 1, 2
and 5. Above this elevation, for the outer side- walls, the
same proportion is maintained ; but the cement used is a mix-
ture of 1 part Portland and 2 parts Rosendale. For the con-
crete forming the centre wall and arches only Portland cement
is used. The best Rosendale, and very fine ground, sloAv-set-
ting Portland cements were procured for the work. The con-
crete is rammed thoroughly in courses which are bonded to-
44 City Document No. 53.
gether. Man-holes of brick, and low dams to intercept street
detritus, will be built at intervals of about 300 feet. The
arches are tied, as shown, by l|-inch Avrought-iron rods,
spaced five feet apart.
These sewers are to have gates at their ends, so that the
sewasre can be turned through either or both of them.
o
Section Two, Outfall Sewer.
This section includes Dorchester-bay Tunnel, and extends
under Dorchester bay from Old-Harbor Pier to about the
middle of Squantum Neck, a distance of 7,004 lineal feet.
Fair progress has been made during the year ; and, as none
of the uncertain contingencies always affecting this class of
work are now to be feared, there is no doubt of the success-
ful completion of the tunnel during the coming summer. At
the beginning of last year 87 feet remained to be excavated
between the east and middle shafts, and 1,004 feet between
the middle and west shafts. At the former point the head-
ings met January 24, and at the latter June 22. No appre-
ciable error in alignment or elevation was found to exist, which
was very satisfactory, considering the difficulties experienced
in transferring lines 160 feet down shafts filled with steam-
pipes, causing heated currents of air and incidental errors of
refraction. Lining the excavation with brick- work began
March 10, and has continued with little delay since. Pro-
jecting portions of rock have been trimmed off, so that a
solid brick lining, twelve inches thick, laid in courses, is
always obtained. The shape and size of the excavation is quite
irregular. In places considerable rock has to be trimmed
ofi', so that the lining may be built to its proper line and
thickness ; at other points there are cavities outside of the
lining large enough to hold a cart. All spaces between the
linins: and the sides of the rock excavation are solidlv filled
with masonry, principally brick-work. The amount of back-
ing thus required to make solid work averages about three-
quarters of a yard per lineal foot. Jan. 1, 1883, 1,994 lineal
feet remained to be lined, or about 28 per cent, of the whole
tumiel, besides portions of two shafts. At the average rate
of progress, this will be completed by June of the present
year.
The maximum amount of water noted flowing into the
tunnel was about ()4,000 gallons per iiour. This, however,
has now decreased to about 52,000 gallons, owing, perhaps,
to some silting of the crevices in the rock through which it
comes. In putting in the lining, iron pipes are built into the
brick-work wherever necessary, to furnish outlets for the
Report of the City Engineer. 45
water, Avhich would otherwise wash out the mortar. These
pipes can eventually be plug-ged or capped. It is not ex-
pected that in this manner the water will be prevented from
entering the tunnel when empty, since the head at such
times, as shown by a pressure gauge, is about 60 pounds per
inch, or sufficient to force it through a brick wall, however
carefully laid. But when in use the head of the sewage
inside the tunnel will be in excess of that of the water out-
side, and, the pressure being outwards, no leakage inwards
will occur.
Some experiments were made to determine to what extent
the porosity of the brick lining could be destroyed by silting
from without. An iron pipe, extending up one shaft, was
connected at its lower end with the pipes built through the
brick-work, and water containing clay, cement, and fine saw-
dust, was forced outside of the lining. The finer portions of
these materials came through the lining, and in places the
leakage was materially reduced. Holes of apparent size were
calked with lead. By this means the leakage into the in-
clined portion of the tunnel, about 800 feet long, was reduced
from about 2,200 gallons an hour to about 500. It was not
considered practicable, however, except at considerable ex-
pense, to thus materially reduce the quantity of water coming
in ; and, in view of its slight importance in respect to the use
of the tunnel, the attempt was given up. A large mining
pump is to be provided at the east shaft, by which the
tunnel can be cleared of water at any time in the future,
should it prove necessary. At present, to economize in
pumping, the completed portion of the tunnel, east of the
middle shaft, has been isolated by means of a thick masonry
bulkhead, and allowed to fill with water.
To ensure the good quality of all bricks and cement used
in building the tunnel the contract provides that these ma-
terials shall be purchased from the city at fixed prices. The
delivery of the two million bricks, furnished the city by Stod-
dard & Hellier, under. their contract of May 21, 1881, was
completed during last year. Another million was obtained
from the Brewer Brick Co., of Bangor, under a contract
dated August 1, 1882, and three million more have been con-
tracted for, and in part delivered, by the Bay State Brick
Co. Cement has been purchased from F. O. Norton, of New
York, and VYaldo Brothers, of Boston, In all, to January 1,
1883, there has been used in building the tmmel, 5,310,000
bricks, and 15,573 casks of cement.
But one serious accident has occurred on this section dur-
ing the past year, which was the falling of a cage with a man
on it, at one of the shafts. The man recovered sufficiently
46 City Document No. 53.
to return to work, but soon after died, whether as a result of
his previous injuries Avas not ascertained.
Section Three, Outfall and Moon-island Reservoir.
The contractfor this section of work was relet Dec. 28, 1881,
to C. W. Parker & Co., and has been prosecuted with energy
since. Active operations began January 25, and have
continued throughout the year. Inckided in the contractor's
plant were one steam-shovel, two steam-dredges, and three
locomotives. On Squantum Neck 844 feet of 11X12 feet of
outfall sewer are now built ; also, a chamber connecting this
sewer with the end of Dorchester-bay Tunnel. At the same
point a connection has been built for the future high-level
sewer, should one ever be needed. The walls of this chamber
form foundations for a house, and it will furnish an opportunity
for putting in and taking out boats and the ball to be used in
flushing the tunnel. From Squantum to Moon island, a dis-
tance of nearly a mile, the embankment for carrying the out-
fall sewer has been partly constructed, and protected on its
sides with ballast and riprap. In places this embankment
is thirty feet high, and has been filled nearly to grade. The
mud under a portion of it has been displaced at points, but
not so generally as was anticipated. As an experiment,
an attempt was made to hasten this action by exploding
dynamite cartridges under the embankment. No results of
magnitude were obtained ; but the experiment demonstrated
the resistance of the mud to displacement and the probable
stability of the embankment.
At Moon island two low discharge sewers, 8X8|^ feet and
8X12 feet, respectively, and the outfall server, 11X12 feet,
have been nearly completed ; also, an outfiill chamber, turbine
well and engine, boiler, and coal-house foundations. The
easterly wall of the sewage reservoir is finished and the
northerly wall nearly so ; portions of the other retaining and
division walls have been built.
Beginning with last year, the practice has been followed of
constantly taking photographs, by the cheap dry-plate i)ro-
cess, of all points of interest in connection with this con-
tract. These not onl}^ furnish an interesting record of the
l)rogress of construction, and the methods and machinery
used, l)ut may prove of great value as aftbrding indisputable
evidence to be used in any })ossible future disagreement with
the contractors concerning the character or condition of the
work at any time. Heliotype reproductions of tAvo of these
photographs are given, merely as affording a good general
idea of the character and magnitude of the work.
Eeport of the City Engineer. 47
The work done at this point during the past year includes
the furnishing and putting in place of about 117,000 yards of
earth, 7,000 yards of Imtlast, 22,000 tons of riprap, 2,200
yards of brick masonry, 8,600 yards of rubble masonry, and
3,000 3'ards of concrete. The value of this, in round num-
bers, is $250,000, of which nearly $50,000 is retained by the
city as security (in addition to the bond) for the satisfactory
completion of the whole contract. The stones for the cut-
stone masonry used on this section arc furnished by the
city, and are obtained from the Cape Ann Granite Co., under
a contract dated Dec. 14, 1881.
One fatal casualty has occurred at this point during the
year. ,
Office and Miscellaneous.
The cement-room has been kept busy testing all cement
purchased by the city, or procured by contractors for use on
the work. Dealers, being now acquainted with the rigorous
character of these tests, rarely offer any but superior articles,
and in some instances manufacturers select and grind especial
qualities for this department. 20,365 barrels of Rosendale
cement purchased hj the city have been tested and accepted,
and 3,183 barrels of Portland cement. For contractors,
13,375 barrels of Rosendale cement have been accepted.
1,000 barrels of Rosendale, and 849 of Portland cement have
been tested for the Park Department, and 50 of Portland for
the covered channel. Tests have also been made for the
water-works, and a few for private parties who wished to
avail themselves of the city's facilities in this respect. Two
lots of Portland cement, and four of Rosendale, submitted
during the year, have failed to come up to our standard.
Experiments on the transverse strength of concrete were
made to determine the proper proportions to be used in
building the tank-sewers. Various other experimental tests
have also been made.
The branch office at Squantum has been maintained during
the year, and will be necessary until the completion of the
reservoir and tunnel. Office work at this point and at the
main office in the city has included the preparation of plans
and contracts for future work, makino- calculations, working
up estimates and force accounts, keeping books, etc. Drafts-
men are at present employed upon a full set of record plans,
in detail, to furnish a complete record of all work built in
connection with the system.
48 City Document No. 53.
D.— PARKS.
For the purpose of makino: this report a complete record of
the Avork of this department, the followins; statement, which,
with tlie exception of some slight omissions and additions,
was made to the Park Commissioners, and printed in their
report to the City Council, is given : —
''Filling.
"The filling of the territory between Beacon street and the
Boston & Albany Railroad, under the contracts of April 29,
1880, and May 26, 1881, which was in progress at the be-
ginning of the year, was completed November 24, with the
exception of a small amount, wdiich cannot be done until other
work on the park is farther advanced. The several owners
of the land tilled have accepted the work, with the under-
standing that the railroad company shall furnish any tilling
that may be hereafter needed to complete the work, at the
same price as heretofore.
" There have been no payments during the year for filling
on the park under the contract of April 29, 1880 ; the amount
done has been small, and cannot be accurately stated until the
completion of the final estimate and apportionment, work on
which is now in progress.
"Under an arrangement with the Boston & Albany Railroad
Company, 3,107 squares of filling have been deposited on
the westerly boundary road, between the Beacon-entrance
Bridge and Boylston street, of which amount 222 squares
were brought from a point on the line of the railroad just
west of the Newton station; the balance, 2,885 squares, has
been brought from the company's bank at Riverside, since
the completion of the filling north of the railroad.
"In May 341 squares of filling were de})osited by the same
company, for the purpose of closing the opening in the
easterly boundary road left for the flow of water into and out
of the i)ark.
" The price paid per square for the filling is $3.20, the same
as last year.
''Beacon-entrance Bridge over B. & A. R.R.
"The foundations of the abutments and wing-walls of this
bridge were completed in 1881. The masonry above the
foundations was commenced on Jan. 5, 1882, and completed
June 12. The abutments and wing-walls were constructed
entirely from stone from the Beacon-Hill reservoir.
Report of the City Engineer. 49
"A contract was made, May 5, 1882, with David H.
Andrews for building and erecting the iron bridge. He
completed his contract September 30.
" The grading of the approaches has been so far completed
that the bridge is in use for teaming purposes, and it is
proposed to run the gravel trains over it, for completing the
unfilled portions of the approaches on the north side of the
railroad.
^^ Boston & Albany Railroad Bridge over Parh Water-way.
"The work of building the piers, abutments, and wing-
walls of this bridge, which was under contract to I. A.
Sylvester, was finished March 20.
"The iron bridge, a portion of which had been temporarily
placed on timber trestle-work, was put in its proper position
on the masonry, and the work upon it completed March
26.
"Since the completion of the city's portion of the bridge
the railroad company has widened it, making a five instead
of three-track bridge. The entire bridge-seat is now occu-
pied, and the structure has a more finished appearance.
^^ Boylston-street Arch Bridge, over Park Water-way.
" Considering the complicated nature of the structure, satis-
factory progress has been made upon it. The erection of the
centring was commenced April 10 and completed June 16.
" Owing to delay in the delivery of the stones for the faces
of the arch, the setting of them was not commenced until
July 20. The work has been actively prosecuted since that
date, and the arch proper has been completed. The spandrel-
walls and backing for the wing- walls and "tourelles," on the
easterly side of the bridge, have been completed, and when
the weather is suitable similar work on the westerly side of
the bridge is now being done.
"The brick portion of the arch is four feet in thickness at
the springing line and two and one-half feet at the crown, and
in its construction 700,000 bricks were used.
"The extrados of the arch has been coated with asphalt, to
prevent percolation of water through the brick-work.
^^Commonwealth-avenue Bridge.
"This bridge was built under the direction of the Com-
mittee on Streets, as it is the street-bridge carrying Common-
wealth avenue over the park water-way.
" The abutments and wing-walls were completed at the date
50 City Document No. 53.
of the last report, and the iron superstructure was under con-
tract to be finished on or before February 1. Owing to de-
lay on the part of the contractors the bridge was not finally
completed until May 27.
^^ Excavation of Water-ivay.
"The work of excavating and forming the shores of the
water-way through the Beacon Entrance of the park, which
was in progress at the beginning of last year, was continued
during the spring, and completed as far as the Boylston-street
arch bridge. May 19 the old channel crossing the boun-
dary road between the railroad and the Boylston entrance was
closed by filling it with gravel, and the flow of water since
that date has been through the new water-way.
"The steam-dredge was launched March 17, and four
scows soon afterwards. The dredge began work April 15,
and was kept constantly employed until December 2, when
work was stopped by ice forming in the l^asiu and preventing
the movement of scows. Since that date the dredge and
scows have had such repairs made upon them as were ren-
dered necessary by the season's service, and are ready for
work as soon as the ice breaks up in the spring.
"The work of the past season has consisted in excavating
and forming the shores of the new channel southerly from
Boylston street. When the material excavated was gravel,
it was used for building an eml)ankment on the shore line of
the channel, while the mud excavated was deposited in the
rear of this embankment. In this manner about 4,000
linear feet of shore line has been formed, and the channel
between the banks excavated to grade 0.
"The dredging plant has proved itself to be both efficient
and economical. The cost per cubic yard, dredged and put
in place, averages less than 20 cents. The efficiency of the
dredging plant could be increased by the use of a small tug-
boat for moving the scows. Plans for a boat of this kind are
in progress, and will soon be submitted to your Board for
approval.
'^Embankment Wall.
"Under this head is included the retaining- walls between
the Commonw^ealth-avenue and Bcnicon-entrance bridges,
and between the Beacon-entrance and Boylston-street arch
bridges, also the retaining-walls adjoining the Boylston-
street arch.
"The wall between Commonwealth-avenue and Beacon-
Keport of the City Engineer. 51
entrance bridges is completed, with the exception of the
parapet.
"The foundation of the wall between the Beacon-entrance
and Boylston-street arch bridges has been built to grade lines,
3 feet below the proposed surface of the ground in front of
the wall.
"The foundations for portions of the walls adjoining the
Boylston-street arch bridge were built in connection with
the arch foundations.
"The wall is built upon one general plan, the foundations
consisting of pile-work to grade 7, and hydraulic cement
concrete to grade lines, 3 feet below the ground surface, in front
of the wall. The wall proper is built of seam-faced granite,
irregularly coursed, and backed with rubble- work. It has a
curved batter on the face, and the parapet is to have a cop-
ing of red granite.
^^ Granite Curb and Fence.
"The granite curb to carry an iron fence, which is to form
the street boundary around the section of the Beacon-entrance
between Commonwealth avenue and Beacon street, and
between Commonwealth avenue and the railroad, has all been
delivered by the contractor.
"The foundations for the posts which support the curb are
completed.
"The posts are about 11 feet apart, and each has a hydraulic
cement concrete foundation resting upon four piles.
"The total length of curb is 1,476 feet, and of this 1,220
feet have been set. The setting of the remainder will be com-
pleted within a few weeks, and the whole will then be in
readiness for the iron fence.
^^ Grading and Loam.
"In August work was begun on grading the slopes between
the drive-ways and the shores of the water-way. The portion
of the Beacon-entrance between Beacon street and Common-
wealth avenue has been graded to the sub-grade, so that the
slopes are ready for putting on the loam. Between Com-
monwealth avenue and the railroad the slope on the easterly
side of the water-way is ready for loaming, while on the other
slopes considerable work has been done. As soon as spring
opens the whole of the Beacon-entrance will be ready for the
loam, the grading of the slopes being now in progress when
the weather permits.
"In order to obtain the large quantity of loam needed for
the park, the construction of a spur-track, leading from the
52 City Document No. 53.
Hopkinton Branch Railroad into the ncAV water-works basin
No. 4, in Ashland, was decided upon.
" The length of the spur-track from the railroad to the valley
of the basin is 7,139 feet, and the length of track required in
the valley is 4,626 feet. The grading of the road-bed was
commenced October 9, and completed November 18. The
location required 600 feet of trestle-work, which was com-
menced October 26, and as portions of it were 30 feet in
height, and the work was several times interrupted for want
of tim])er, it was not completed until December 28, too
late for track-laying, as the ground was frozen to quite a
depth.
" Arrangements have been made with the Boston & Albany
Railroad Company for transporting the loam from Ashland
to the park, and 20,000 cubic yards are now piled beside
the track road-bed in the valley.
" A contract has been made for the rails to be delivered on
or before February 15, and the ties have been secured. As
soon, therefore, as spring opens, the track can be completed,
and the transportation of the loam commenced.
" Covered Cha7inel of Stony hrook.
" The wooden conduit connecting the gate-chamber with
Charles river was so far completed on July 2 that the water
of Stony brook was allowed to run through it instead of
into the park.
" The large automatic-acting wooden gates, to control the
height of water in the park, and permit the flow of Stony
brook into it in time of freshets, were hung and adjusted by
September 5. The iron sluice-gate, to control the tlow of
salt-water into the park, through the wooden conduit, has
also been completed, and the setting of it was finished
December 9.
" Work upon the gate-house superstructure was prose-
cuted during the late fall and early winter, and the walls
are completed and ready for the roof.
''With the exception of the roof, doors, and windows, and
other small details in connection with the gate-chamber
superstructure, the work of liuilding the "Covered Channel
of Stony brook" is now completed.
" Covered Channel of Muddy river,
" The length of this channel, if built on the line originally
proposed, Avill be about 3,300 feet. The work was begun
October 2, and 1,369 feet in length are now completed.
" It is built mainly of wood in a similar manner to the
Eeport of the City Engineer. 53
covered channel of Stony brook, but is much larger, and
has a cement concrete key at the crown of the arch. The
concrete key was adopted, as the crown of the arch was above
the line of mean high water, and would be liable to decay ii
made of wood. The form of the conduit is elliptical. It is
11 feet in height and 9 feet in width.
" Under the Boston & Albany Railroad location, for a
length of 129 feet, the conduit is built entirely of hydraulic
cement concrete ; the section of the mass of concrete through
which it runs measures 13 feet wide and 15 feet high.
" As far as built the conduit rests every^^here on sand or
gravel ; but, w4th the exception of the bottom and top, it is
surrounded by peat. There has been less change of form
than was expected to occur, considering the size of the con-
duit and character of material iu which it is built.
^^ In General.
" The building of a wharf on the river side of Beacon street,
and the dredging of a channel to it from the river, have largely
reduced the cost of delivery of stone required for the various
structures in the park by substituting delivery by water for
that by rail.
" A storage-yard has been established at the Westland
entrance. An area 100 ft. X 116 ft. has been enclosed by
a high board-fence ; one side of the area is occupied by sheds
for the storage of tools and machinery which would be in-
jured by exposure to the weather ; an office for a time-
keeper, who acts as store-keeper, has been located in one
corner, and the remainder of the area is used for general
storage purposes.
"In addition to the supervision of the above work, surveys
and complete plans showing the area of land taken from each
owner by the proposed Improvement of Muddy river, and
surveys and plans of East Wood island and land for parkway,
purchased for East Boston park ; also, surveys and plans of
estates adjoining the Bussey Farm and Arnold Arboretum,
and record plans of the land taken for park purposes in this
locality, have been made for the Commissioners."
The table giving the number of vessels passing through
the draw-bridges controlled by the City of Boston, during the
year 1882, will be found in Appendix A.
The table showing the width of draw-opening in the
bridges over tide-water in this city is given in Appendix B.
The openings have all been re-measured for this report.
HENRY M. WIGHTMAN,
City Engineer.
54
City Document No. 53.
0 t^
tH
0 CO
. 10
0 <M
•sSnTnado
CO 0
10 C£)
l-H
<y> 0
0 io_
00 0
05^ i-H^
oq
AlBJQ JO "0^
W<"
co"
c4~ c<r
(>f -.J^
00
00
T-H
-* (M
05
■^ CO
• 0
t^ l^
I^
f-1
(?q 00
0
^ 10
t^ CO
S
2
l-H Oi
t^
0 0
00 C<J
s«
M
0
e
H
H
0
00
CO CO
!>• 0
<»
Oi
T-H
>i
H
>
0 ^
Oi
00 (M
CO 1-1
<»
%
^
10 (N
0
CO !>•
l-H r*<
i<
^%
CO rH
l-H
-5j< CO
"^ I-H
Gj
6
^
i-H
(^^"
CO i-T
00 00
0
CO l-H
• «o
-^ CO
s
^
0 10
CjD
t^ 00
CO (M
-i
0
«
t-^ 00
0^
kO <N
■>*l l-H
«5
>.
-^
«D^
(>r co^
•^ rjT
n
l-H
t>. CO
(M
>o 0
• 0
t^ l-H
o
13
t>. CO
«>^
00 'ti
00 C<l
Kl
is
0
(M
t-
CO -*
l-H (M
"^
in
K
H
C^
o
g
H
0
00 CO
CO
CO s<>
00 05
,
m.Sf
<o
l-H
0 CO
T-t
0 CO
10
«2
O
^
<1
^
Ci 0
OS
(M 00
• 0
0 (><
'^ >.
.-' CO
00
00 0
t- 00
«
'^
«5
IM
»o
<M '^
CO^ I-H
•
O
^
T-(
<H
i-H t>.
t^
10 00
cs t-
^
Ph
's
^
■rtH t>.
GO
05 l-H
CO 0
<u
5
o_ 0
>o^
0 0^
l> 05
W
o
^
C^
<>r
T-T (>r
00 I-T
kj
P^
^
KN
s
■ -^ l-H
l-H
(M -*
t^ 1—1
r 1
p
m
«i
0 t>
'^
T-H 0
CO 03
M
.^
«
0
(»
CO
(M (N
G^ (M
cc
CO
Eh
^
T-H
ft
«
>.
^ 0
CO '^
00 l-H
t^^ CO
0 -H
h^
H
^^
«
0 10
(M
CO 00
10 CO
V/^i
»o
ft
i
^~'
(M
T-l T-H ,
t^ I-H
12;
<5
<M <M
<X>
05 00
t^ CO
^
t^ t^
00
0 00
CO 0
^
Q)
2
0
t>-^ CO
CO^
05 r-<^
CO I-H
H
w
Eh
CO
10
T-H .
CO CO
1
»^
.-H 0
05
l-H CO
t- 00
<
^
5>
>
mI
05 IQ
C5
0
l-H CO
l-H T-H .
"* 05
0^ t^
0
K
tzi
»-H
l-H
T-H fN
t^
00 (M
0 10
&1
CQ
^
00 i>J
!>•
05 10
<M 0
Q
S
s
«
l-^ CO
t^
|> 0
l-H CO
w
C^
CO
T-H
Iff (>r
^
-<*
lO !>• •
-<*• CO
r2
3
0
CO
00
T-H •
0 CO
09
H
^
CO
CO
(M
T-t CO
^
^l>
T-H
CO
i-H • •
OS l-H
'^
^
•
.
T-H <
00
CO !>• •
CO CO
^a
t>\
-<*<
1—1 •
CO (M
««
l-H .
tH
fO
• I
^
-u
III
-1-3
a
9*
CD
-^'^v ^"N •
<»
•<
t4
^
-t-' +f +J
2 S CD
i
■«-3 <
51
R
OS
■i be
<^ c» ^
^-^ CO
'a
■3
s-str
treet
'5
6
1
§ a
ei
elsea
elsea
elsea'
a
a
ngres
ver-s
^ e«
,a
xi ja ja
0
0 5
pq
0
0
000
0
0 P
Report of City Engineer.
55
O 05
OS CO '-'
1-1
tH
> as CD
»0 CO
CC
OS
i>
•^
CD CD
CO o o
o
-^
. eo o
CD 1-1
oo
OS
CD
rH
CD y-t
1-1 00 00
c^
1—1
> (M »fl
iC
tH
1>
■<*
lO
t^
lO
<>j
00
^
GO
T^
cq
1 ^
»0 Oi
CO CO CS
l>.
t^
Ei c
<M CD
oc
-<*■
CO
C^ (M
Oi t- (N
t^
»o
t>- (N
1—1
CC
I--
""t
00
O kO
I— 1 o.
CO
CO
(M
CO iCi
o-
tH
CO
»o
^H
lO
rH CD
■<*
T-(
CD
CC
GO
"*
1— 1
1 "^
^^O
"ff^l" oc
t^
l—{
~co
lO QC
OC
CO
~cc
o
^
l^
CO T-<
r-. -<*
"^
o
(M
»0 CD
CO
CO
CO
CC
o
-<*<
I— 1
a>
CO^
T— •
CO
00^
rH
rH
(tT
^H
^H
1—1
■^
cT"
~Th lO (M
CD
"^
. S<l (N
-^ CO
~oc
oc
OS
lO
CD rH
00 (M 00
C>1
CO
. <N i«
OS OS
CC
OS
c
t^
o-
1-H
T— 1 I—
1—1
-^
(N
. CO r-
t>.
CC
OS
t>-^
>o
-<*<
oT
-<t
CO
co"
CD
«
o
- c
»o
CO
~G<I
. CD C
G^ t»
~c5
l>i
CC
O
CO Oi
• (M ^
• c<j >f:
CO CO
t>
c
»c:
CO
">*
00
CO
1—1
iC
CC
CO
CO
l>
•*
-*
CO c
lO
~oc
>c
iC
^
T— 1
<N
1—1
•
t>
-^
OS
tH
<M
1— 1
•
•
''^
1—1
g5
-*
cr.
T— 1
OS
~SJ
CO o
t^ t-
~^
CO
oc
CD
cc
t^
C
(>1
as
(M ''t
C<]
CO
OS
OS
c
CO
CO
00
rH
■^
CO
^H
00^
CD~
c
o
If;
o
t^
~«
CD CO
c-
■r-t
~co
1-H
c
1—1
t'
t^
o-
5
CO
as
r—
(N OS
CO (M
CC
t-
CC
O
>c
(M
t^
CO
1—1
^
<M -<*
te:
CC
CJS
^
(M
(M
lO
r"
CO
c
l^
Ti
l>
^
o
"^
^ lO
CC
rH
c
oc
^
ec
(M
OC
CD
lO
CO CD
CC
t^
CO
tC
CD
CO
CD
OJ
>c
OO
c
CO
~oc
'Jt
CD
t^
"^
G<1 OC
CO o
~~^
GO
t-
"^
■*
oc
c-
CO
■TtH
r—
as (M
t^ CO
CD
^
C
CO
»o
as
C£
(M
o
r-
1-1 fN
'^
CO
"*
CD
^
(M
'^
iH
Oi
GO
lO
"oc
CD
00
CD
~t^
>o ^^
r-
-*
"~»c
L-
t>
CO
G^
CO
c-
ir:
CO
i-H
cr.
(M OS
-<*
CD
<T.
L^
t^
t^
-^
t^
cc
o
CO
V—
rH CC
CO
■^
CC
OC
CD
CO
1— 1
■*
-^
GO
O
C
o
~s
^
OS
(>»
~c-
00 '^
I>
CO
~iC
OS
a:
CO
cc
iC
(>.
•^
"*
t^
^
<
r-
«^
■^
CO
If:
<*
OS
00
05
o
as
a;
f-H
Tjl
o
1—1
^H
1-t
1— (
o
~c
i?5
cs
^
~QC
!>. r-
'^t
CO
~c
X
oc
OS
cr
QC
l>
00
'^l
T—
o ■*
o-
Ttl
-^
CO
t>
00
CO t-^
cr.
05
l^
T—
rH ■»»>
CJ
^
CO
CC
lO^
(M
CO
<N
oT
GO
^
C£
CD
rH
(?Q
<
^
~oc
CC
't
OS
CO
1—1
1—1
lO
GC
>fl
CO
lO
OS
(N
o
»o
OS
.
~a:
GO
CC
lO
r-^
T— 1
1—1
CC
•
CC
OS
•
CO
•
(M
cc
CD
CD
CC
-*
~05
^^
'^
c^
O
1—1
CO
't
1
CC
^
GO
00
CD
<V
;
>
-t-
^
3 a
ai
' a
^ 1
> e.
£
3 ^
<4^
-1^
1
: 1
5
c
-4-
■on
1 {
p
3 1
c
: ^
e
c
c
CO
oc
• a
3
CO
i
• c
5 !2
3 ^
1
\ i
) 0-
i c
'^
Q
►J
a
(/
a
'c
c
;■
> c
' a
5 ^
03
0
c
c
C
a
5 <:
H 52
i 1
>
i 1
i 03
5 m
c
a;
! PC
! 1
)
i
56
City Document No. 53.
M
I— I
ft
<1
8
o
"as
?>
^
CO
a^
»
oo
<D
H
H
-S^
h^
>^
cq
PQ
«
'«
s
•^
<5j
-2
*»1
«0
b
CO
;^
s*
'S.
eo
Co
s
"iS>
a,
O
'S^
»«
s
CQ
h
•SGKiJsLaao
^o
H
1^ ^
<J
-a .«5
O
C^
o >
CPO
Q
o
t-GOTjHTHClOit^tDCiOOOICOOOO
O ;-!
— ' fee
a; r— '
53?^3«^|
IPh*^ G c S
j_i "p c o -—
) o ^ r -"
MO
Q
, ^^
3^
. O
o
. 4^
CO
^ o
O
c3
^6
o
OP
o
pq
03 a; .-:
O O
<o
2S ^
«^ fl 2 53
o c c 2 ^
pqOOOO
1;^
4d rt -a o CQ cc
t: W O Ph ->^
C3 rr.
O)
ID
OS
CO
o
Ol
bJO
a
o o
u
>
o
p
Eeport of City Engineer.
57
00»OOOO»OO-^0iCOOOT-lOOl-^i— I'Ttft^OO-^OiTHt^Oit^OOiO
eocococococccocococ<t)cO"^»oo-Tt<-<^co-^'^cococococcicococococo<i<i
r-li— <i— li— li— It— frHt— li— It— It— i»— l(N (?;» t— *(>< ,— I,— |,-^,_(,-_(tHt— l<M t— It— (
• ® S rt
'?.-,??-
fli .1- s ""^ '^
o ^
si
O ;^
« a;
0 >
be O)
go
63
o a
bo
- =j -t^
^ o
o
w
c3
P o
^ o
s §
c3
6
o
Ph
o
o
a
c
a
o "
I"!
©
be
.So
3 0*-
^ o
^ s
G<» CO
53 2
^6
n
9
b£)
-4^
T!
:/>
<iJ
;-i
ri^
03
a
^
03
UCJ
o o
o o
CO 03
O O
be ^
•73 O
a 03
O Q
rp 'p
S 03
BOSTON PUBLIC LIBRARY
3 9999 06315 933 7