<.■■';•;
^
■XT
cJV? . )
\3SiiJ..2i.
■Bi
a^
^
[Document 18 — 1958.]
M bost(d:st[.a. ^Ij
\^>, KB 30. K$^
ANNUAL REPORT
OF THE
PUBLIC WOEKS DEPARTMENT
FOR THE YEAR ENDING DECEMBER 31, 1957.
Boston, January 2, 1958.
Hon. John B. Hynes,
Mayor of Boston.
Dear Mr. Mayor:
In compliance with the provisions of section 24 of
chapter 3 of the Revised Ordinances of 1947, I respect-
fully submit the annual report of the Public Works
Department and the Public Improvement Commission
for the year ending December 31, 1957.
Fiscal
The total expenditures of the department for the
year were $25,357,692.66, of which $3,328,696.68 rep-
resents water assessments levied by the Metropolitan
District Commission and $874,165.17 represents Metro-
politan District Commission sewer assessments. The
water assessments are $37,901.24 greater than those
levied in 1956, and the sewer assessments show an
increase of $179,709.03 in excess of those levied in 1956.
The sewer assessments will continue to rise due to the
large expenditures being made by the Metropolitan
District Commission in providing for sewage treatment
plants and deep rock tunnels to convey sewage to Deer
Island and Nut Island, and also because of the policy
(now curtailed to some extent) of admitting relatively
2 City Document No. 18
remote communities to the Metropolitan District Com-
mission sewer system with Boston paying an unreason-
ably large share of the cost of the connection. The full
impact of the Metropolitan District Commission pro-
gram will not be felt for four or five years, but even
beyond that period the sewer assessments unquestion-
ably will continue to increase. The present rate of $80
per million gallons charged by the Metropolitan Dis-
trict Commission for water will also probably have to
be increased to $100 or $120 within the next five years.
Under the circumstances, Boston can look for no finan-
cial relief in the foreseeable future, insofar as Metropoli-
tan District Commission assessments are concerned.
The receipts of the Water Division totaled $6,274,-
964.54, and the revenue derived from the Sumner
Tunnel reached a record high to $2,581,503. The
operation of the Sumner Tunnel resulted in a record-
breaking surplus of $1,194,586.30 and the surplus
resulting from the sale of water amounted to $97,607.45.
Loan Orders
On July 26, 1957, a City Council order was approved
by your Honor which provided, under the provisions of
section 7 of chapter 44 of the General Laws, that the
sum of $3,000,000 be appropriated for the construction
of public ways. Ordinarily loan orders for street con-
struction and reconstruction work provide for an
amount of $2,000,000, but we requested the above-
referenced larger sum in order that it would be un-
necessary to request an additional loan order this year,
which would automatically have added 10 cents to the
1958 tax rate.
Legislation
Under the provisions of chapter 718 of the Acts of
1956, the City of Boston was allocated the sum of
$2,530,208.82 for the reconstruction of highways. This
allocation — which was paid from the proceeds of the
Highway Fund — was expended under the direction
and in accordance with regulations estabhshed by the
State Department of Public Works. It was of tre-
mendous benefit in carrying out the department's
highway program in 1957 and it was a factor in making
it unnecessary to issue a loan order in 1958 for the con-
struction and reconstruction of highways.
(/'^^r<^3/]}j-S'
Public Works Department 3
Of the above-referenced amount, the sum of $250,000
was earmarked for the installation of traffic signals
under the direction of the Traffic Commission.
Street Construction Work
State- Aid Program
The Chapter 90 Highway Program was continued
at the same tempo that has characterized this program
since 1951. In my opinion, our Chapter 90 Program
for the improvement of main highways is second to
none in the state. Since 1951, the cost of Chapter 90
projects has averaged approximately $800,000 each
year; of which from fifty to sixty per cent has been paid
out of the State Highway Fund. I don't believe that a
comparable program for highway improvements has
ever been carried out in the history of the department.
Incidentally, it would never have been possible to carry
out such a program without the enthusiastic and whole-
hearted support of the officials and engineers of the
State Department of Public Works, both past and
present. Their cooperation has been outstanding.
Our Chapter 90 Program provides for the complete
modernization of main highways with emphasis on
safety features to protect pedestrians and motorists.
Our Chapter 90 highways are well-hghted by means
of mercury vapor luminaries and, where possible, a
center divisional island of a minimum width of five feet
is provided. The latter acts as a haven for pedestrians,
separates vehicular traffic going in opposite directions,
and unquestionably tends to reduce vehicular speed and
prevents motorists from driving on the wrong side of
the traveled way. A good example of modern urban
highway reconstruction may be observed on Common-
wealth avenue, from Brighton avenue to Warren street,
and on Blue Hill avenue, from Columbia road to Matta-
pan square. Both of these highways were reconstructed
in 1957 as Chapter 90 projects, and they are concrete
examples of the type of improvement that we have
been able to effect under the Chapter 90 Program
with the cooperation of the State Department of Public
Works.
I submit herewith a schedule of the Chapter 90
activities in 1957 and those proposed in 1958:
4 City Document No. 18
Projects started in 1956 and completed in 1957
Final Contract
Project Contractor Bid Price Payment
Blue Hill avenue, Dorchester:
Reconstructed from (and includ-
ing) Mattapan square to southerly
S-^IS' °"^ '': '': ''■"■ * Z°n'SSL^Z;'""- 139,502 75 »ioo.i22 03
and
River street, Dorchester:
Reconstructed from Mattapan
square to approximately 500 feet
northerly.
Bunker Hill street, Charlestown :
Reconstructed from Chelsea street
to Main street and including side
9 treets and approaches . . . Dooley Brothers, Inc. 123,401 00 140,793 12
New bridge over Belle Island Inlet
between East Boston and Win- Eastern Roads Com-
throp pany 132,987 00 150,000 00
Total $345,890 75 $390,915 15
Projects started and completed in 1957
Final Contract
Project Contractor Bid Price Payment
Centre street. West Roxbury:
Reconstructed from Spring street
to Grove street J. A. Susi & Sons, Inc. $158,881 80 $161,277 15
and
Baker street. West Roxbury:
Reconstructed from Veterans of
Foreign Wars Parkway to Newton
line.
Summer street. South Boston:
Reconstructed from viaduct to
East Second street (excluding draw-
bridge and approaches of bridge
over Reserved Channel) . . . Dooley Brothers, Inc. 118,206 00 125,321 73
and
L street. South Boston:
Reconstructed from East Second
street to East Fourth street.
Washington street, Roxbury:
Reconstructed from Northampton
street to Eustis street . . . Dooley Brothers, Inc. 54,391 75 70,154 60
Total $331,479 55 $356,753 48
Public Works Department
Projects started in
Project
Blue Hill avenue, Dorchester:
Reconstruction from Columbine
street to Columbia road
Blue Hill avenue, Dorchester:
Reconstruction from Woodhaven
s treet to Columbine street
Commonwealth avenue, Brighton:
Reconstruction from Brighton
avenue to Warren street
East Broadway, South Boston:
Reconstruction from Dorchester
street to L street ....
Tremont street, Brighton:
Reconstruction from Oak square
to Newton line ....
Summer Street Drawbridge over
Reserved Channel:
Repairing and strengthening of
approaches and drawspan
1957 — to be completed in 1958.
Per Cent
Contractor Bid Price Complete
1957
A. Singarella & Sons,
Inc. $294,597 00 99%
Manning Construction
Company, Inc. 248,102 00 36%
Rufo Construction
Company 238,663 72 73%
Baker & Co., Inc.
Chesterbrook Con-
struction Company
Ralph Richard Con-
struction Company
Total
100,721 50 8%
45,100 00 0%
234,326 00 0%
[,161,510 22
Additional Chapter 90 Projects Scheduled for
Project
Seaver street, Roxbury:
Reconstruction from Blue Hill avenue to Walnut avenue
Columbus avenue, Roxbury:
Reconstruction from Walnut avenue to Egleston square
Baker street. West Roxbury:
Reconstruction from Centre street to Veterans of Foreign W
way
Dorchester avenue, South Boston:
Reconstruction from West Fourth street to Andrew square
River street, Dorchester and Hyde Park:
Reconstruction from Edgewater Drive to Wood avenue .
Main street, Charlestown :
Reconstruction from City square to Sullivan square
Commonwealth avenue, Brighton:
Reconstruction from Warren street to Lake street .
Columbus avenue, Roxbury:
Reconstruction from Roxbury street to Centre street
West Broadway, South Boston:
Reconstruction from Dorchester avenue to Dorchester street
American Legion Highway, West Roxbury:
Reconstruction from Blue Hill avenue to Cummins Highway
Total
1958
Park
Length
4,130 feet
1,240 feet
6,700 feet
4,350 feet
4,000 feet
5,100 feet
9,450 feet
2,600 feet
4,120 feet
11,030 feet
52,720 feet
or 10.0 miles.
6 City Document No. 18
Street Construction Work
Exclusive of Chapter 90 Projects
We also completed a major street reconstruction
program comprising extensive construction and recon-
struction in every section of the city. Several important
traffic arteries resurfaced by the department during
the year are listed as follows :
Arlington street, City Proper, from Boylston street to
Beacon street.
Beech street, West Roxbury, from Kittredge street to
Poplar street.
Berkeley street. City Proper, from Boylston street to
Beacon street.
Boylston street, City Proper, from Tremont street to
Charles street and from Arlington street to Berkeley street.
Centre street, West Roxbury, from Eliot street to Prince
street.
Clarendon street. City Proper, from Boylston street to
Beacon street.
Day Square, East Boston.
Jackson square and vicinity, Roxbury, including parts of
Centre street, Columbus avenue and Ritchie street.
Massachusetts avenue, City Proper and Roxbury, from
Huntington avenue to Columbus avenue.
Metropolitan avenue, Hyde Park, from Beacon street to
Milton Hne.
North Harvard street, Brighton, from Hooker street to
Western avenue.
Parker Hill avenue, Roxbury, from Parker street to Sunset
street.
Perkins street, West Roxbury, from Prince street to
Francis Parkman Drive.
Ruggles street, Roxbury, from Columbus avenue to
Leon street.
Roxbury Crossing, Roxbury, from Tremont street to
Roxbury street.
In continuation of our policy of replacing brick
sidewalks with cement concrete in the older sections
of the city, contracts during the year, totaling approxi-
mately $153,500, were awarded for this work.
The following is a summarized financial state-
ment of the expenditures made in 1957 for highway
improvements :
Public Works Department 7
Public Ways, Construction of (Loan Account) . . . $1,785,406 98
Public Ways, Construction of (Revenue Account) . . 84,147 12
Reconstruction of Streets (including sidewalks) . . . 19,069 46
Sidewalks, Construction and Reconstruction of . . . 165,711 01
Expended under provisions of chapter 718, Acts of 1956 1,484,467 59
Total $3,538,802 16
The following is a summarized record of the highway
improvement work done by the department in 1957:
Number of Streets Constructed or Reconstructed, 220.
Includes 50 new streets ordered laid out and con-
structed as public ways under the provisions of chapter
393, Acts of 1906.
Streets Improved, 37.66 miles.
Includes 6.8 miles reconstructed as chapter 90
projects.
Sidewalks Improved, 6.35 miles.
This item does not include sidewalks improved in the
above-noted street improvements.
Street Lights
During the year, we removed 1,704 gas lamps which
were replaced with electric lights of a 2,500 lumen
intensity. It is our intention to continue this program
in 1958 and, if possible, remove all of the remaining
gas street lights located in Boston. As of December 31,
there were only 710 gas lamps remaining. In the past
eight years, we have removed 6,263 gas lamps and
replaced them with modern street lights. Incidentally,
for the past forty or fifty years, the city has had a
contract for the servicing and maintaining of all gas
lamps throughout the city. This contract service was
terminated at midnight on December 31, as the con-
tractor, the American Service Company, did not wish
to continue the contract, in view of the small number
of gas lamps remaining. Therefore, as of January 1,
1958, we took over the maintenance and servicing of
the remaining gas lamps, and we are employing — for a
temporary period — three former employees of the
American Service Company. Up to date, the servicing
work being done by the department has proved very
satisfactory.
City Document No. 18
Snow Removal
While we did not encounter any major snow storms
during the year; that is, those in excess of eight inches,
we did encounter a series of small storms which neces-
sitated extensive plowing, sanding, and salting opera-
tions. Our sanding and salting program has been
greatly accelerated over the past six years due to the
necessity of eliminating hazardous driving conditions
during the winter months. The number of vehicles now
on the road makes it absolutely necessary to continue
with an extensive sanding and salting program even
when only light snowfalls are encountered.
The plowing, sanding and salting operations are
expensive as they involve the rental of contractors'
equipment, overtime payment to department em-
ployees, and the purchase of large volumes of sand and
salt. The salt item alone is a major item as we now use
from six to eight thousand tons a year, and it costs
approximately $15.60 a ton. It is not unusual to use
400 tons of salt in a single night to eliminate hazardous
driving conditions caused by sleet or light snowfalls.
The cost of snow removalworkin 1957 was $449. 797. 64.*
* Not available.
Bridges
During the year, work continued on the major con-
tract for rebuilding and repairing the Charlestown
Bridge, which probably is the most important draw-
bridge in the city as it is used by approximately 20,000
motorists and M. T. A. passengers daily. The drawspan
was closed to the passage of all marine traffic from
May 1 to December 31, due to the necessity of effecting
major repairs. We have had some difficulty in making
the necessary adjustments for operating the draw,
but we hope that we will be able to re-open the draw for
marine traffic some time early in 1958.
South Bay Incinerator
During the year, the contract for the driving of
foundation piles was completed by the J. F. White Con-
tracting Company. This contract was awarded in 1956,
and the final payment to the contractor totaled
$419,000.
■*%^
o
Cl
CO
Q.
CO
7r
o- o
• o
o
oi
Public Works Department 9
A contract was awarded to Coleman Brothers Corp.
in June for the construction of the refuse storage bin.
The bid price was $423,000 and the work was sub-
stantially completed by the end of the year.
Under date of November 25, a contract for the con-
struction of the building was awarded in the amount of
$2,693,793 to the Bowen Company. This contract has
not started as yet, but it is expected to start verv early
in 1958.
Personnel
There were 1,948 employees in the Department as of
December 31, as compared with 1,990 employees on the
rolls on January 1, 1957.
Our Plans for 1958
1. First — and of utmost importance — we will
make every reasonable effort to reduce expenditures to a
minimum consistent with the rendering of proper service
to the public. We fully realize the necessity of observing
an austerity program, and will be guided accordingly in
connection with our expenditures.
2. Every effort will be made to reduce personnel
another 5 per cent, although we are scraping bottom in
certain areas insofar as a future reduction in personnel is
concerned. This is due, in part, to the fact that we have
been carrying out a ''no hire — no fire" program for the
past eight years as evidenced by the fact that the De-
partment now has 582 employees less than we had on
January 1, 1950. This reduction takes into consideration
the transfer of 65 employees from the Street Laying-Out
Department to this department on May 1, 1954.
3. W^e intend to continue our accelerated Chapter 90
Program for the improvement of main highways.
4. We intend to place Boston's first incinerator in
operation some time in 1958.
5. We intend to complete our gas lamp elimination
program.
6. We are going to make an effort to close the
Charlestown Drawbridge to marine traffic, thereby
effecting a minimum saving of $70,000 a year to Boston's
taxpayers. We are now required to maintain a three-
man crew around the clock, seven days a week, to
operate this drawspan for the benefit of scows and
barges hauHng sand and oil upstream to plants located
10 City Document No. 18
in Cambridge. The maintaining of a drawspan at the
Charlestown Bridge places an unreasonable burden on
Boston's taxpayers, particularly in view of the fact
that we receive no benefit as the vessels are hauling
material to and from plants located in Cambridge.
In addition to the excessive cost of operating this
span, the motorists and M. T. A. passengers are sub-
jected to an unreasonable inconvenience every time that
the draw is opened for the passage of a boat. An aver-
age of 20,000 motorists a day use this structure, as well
as 80,000 M. T. A. passengers. Since May 1, 1957, the
drawspan has been closed to all marine traffic in order
to permit the repairing of the draw at a cost of approxi-
mately $600,000.00. It seems reasonable to assume
that if marine traffic got along without the opening of
the draw for eight months, it might be able to get along
permanently without a drawspan, thereby resulting in a
substantial reduction in cost to the city and eliminating
the inconvenience now caused to approximately 120,000
people. Therefore, it is our intention to petition the
U. S. Army Engineers to permit the closing of the draw-
span and maintain the bridge structure as a fixed span.
Incidentally, there is a vertical clearance of 23 feet
under the drawspan at high water, thereby permitting
scows, small tugs, small barges and pleasure-craft to
pass through the channel without opening the draw.
The only vessels requiring the operation of the draw-
span are the large oil barges and large towboats. In
view of the expense assumed by the city in maintaining
and operating the draw, it does not appear unreasonable
to require the owners of oil barges to use only the small-
sized barges when making deliveries of oil upstream
of the bridge to plants located in Cambridge. In any
event, I feel that the entire matter should be thrashed
out at a pubhc hearing before the Army Engineers, and
I intend to petition for the closing of the drawspan as
soon as we have prepared sufficient material to substan-
tiate our opinion that the city should not be required
to maintain the Charlestown High Bridge as a draw-
bridge.
7. We are going to make every reasonable effort to
eliminate the contract which provides for the hauling
of refuse material from the Fort Hill Wharf to Spectacle
Island. This service, which costs the Department
approximately $400,000.00 per year, will be eliminated
when the incinerator is placed in operation. The present
Public Works Department 11
contract expires on March 31, and we can effect a
substantial saving for the remaining nine months of
1958 or until the incinerator is placed in service, if we
can find other suitable areas in which to dump the refuse
now hauled by scows to Spectacle Island.
I was unsuccessful in my efforts in 1957 to eliminate
this operation, but am hopeful that I will be more suc-
cessful this year, particularly in view of the fact that
the construction of the incinerator is well under way.
It appears reasonable to assume that it should be in
operation before the end of the current year. We must
make a determined effort to eliminate the costly scow
operation for the last nine months of 1958 to offset an
anticipated increase in the cost of the refuse collection
contracts. These contracts are bound to increase in
cost in 1958 as the agreement with the Union provides
for a 15-cent-an-hour wage increase to all employees
engaged in refuse collection work, effective next April 1.
We estimate that a 10-cent-an-hour increase to such
employees will increase the cost of the contracts approxi-
mately $75,000, and this cost normally is passed along
to the city by the contractors. Therefore, we are faced*
with an increased cost of refuse collection of approxi-
mately $110,000, but this can be offset to some extent
if we are successful in our efforts to terminate the
Spectacle Island operation.
Incidentally, the total cost of the refuse collection
and disposal contracts in 1957 was $2,608,681. This
compares favorably with the 1956 cost of $2,571,813
when you consider that the hourly rate for the contrac-
tors' employees in 1956 was $2 and in 1957 $2.15. The
cost of these services in 1950 was $2,730,019 or $129,338
in excess of our 1957 cost despite the fact that the hourly
wage rate in 1950 was only $1.38. However, I am at
my wits' end as to how to reduce the cost of refuse col-
lection and disposal any further unless we are successful
in eliminating the scow operation on April 1, 1958. We
are working on a plan to accomplish such an objective,
but I am not confident that we will be successful.
8. We intend to continue with our program of en-
closing hazardous open brooks with concrete conduits
similar to the work done in Stony Brook in the past
three years. The open Stony Brook has been entirely
replaced with a concrete conduit, and a conduit has
also replaced a section of the open Canterbury Branch
of Stony Brook in Roslindale adjacent to American
12 City Document No. 18
Legion Highway. We intend to further enclose the
Canterbury Branch between the terminus of the present
conduit, which was installed in 1957, and Walk Hill
street. This type of project is worth-while as open
brooks are a hazard to children and act as a deterrent
to the development of adjacent areas. They generally
overflow during spring freshets or following heavy rains,
causing flooding of cellars.
Recommendations
1. We should press for the passage of a law to per-
mit the Massachusetts Port Authority to function.
With said Authorit}^ in business, we will get a minimum
of $7,619,380 for the Sumner Tunnel, and we might
never obtain anything for it if we permit this oppor-
tunity to pass. We can, of course, recover the $2,619,380
paid out of real estate taxes to make up tunnel deficits
for the period from 1935 to 1944. However, under the
provisions of Chapter 297 of the Acts of 1929, the City
can never derive a profit from the operation of the
'tunnel. Section 12 of the Acts provides, in substance,
that after the tunnel is debt free, a schedule of tolls
shall be established sufficient to meet operating costs
only. The tunnel revenue cannot be transferred to the
General Fund of the city, nor can it be used to finance
another tunnel or a bridge to span the harbor. If
Boston retains ownership of the tunnel, it is faced with
the prospect of operating the present inadequate tube
for the foreseeable future without being able to apply a
single penny of tunnel revenue to reduce the tax rate.
The advantages that will accrue to Boston for the sale
of the tunnel to the Port Authority are obvious.
2. Transfer of vehicular roads from the jurisdiction
of the Parks and Recreation Department to the Public
Works Department. We are responsible for the con-
struction, reconstruction, and maintenance of 750 miles
of public highways, and I believe that there are approxi-
mately 25 miles of public roads under the Park Depart-
ment's jurisdiction. It makes sense to me to have all the
highway work under the jurisdiction of one department
from a point of view of efficiency and also economy.
However, if the park roads are transferred to us, all
personnel, plant, and equipment related to the mainte-
nance and construction of the roads should also be
transferred.
Public Works Department 13
3. As pointed out by Chief Engineer Haley in his
report on the activities of the Survey Division, our in-
abihty to attract engineers has reached the acute stage.
This problem not only affects the Survey Division, but
all divisions of the department, and all departments of
the city. Many years ago, the city abandoned all hope
of attracting college men to enter the municipal engineer-
ing field, but we are now in the position of not being able
to attract high school graduates. In 1957, conditions
reached such a state that we reached into the labor ranks
of the department and temporarily promoted four motor
equipment operators to the position of senior engineering
aids. We have been instructing them in the duties of
transitmen.
This is a problem that should be met head on in order
to solve it. I think that a sitdown with the school
officials might be of some help. As a springboard to
further discussion, I suggest the following:
Hire no rodmen during the summer months unless they
are at least 16 years old, enrolled in a technical high school
in Boston, and intend to follow the civil engineering field
upon graduation from high school.
This policy will give young men, who do not intend
to go to college, an opportunity to become interested in
the municipal engineering field and practically assure
them of passing the civil service examination for
rodmen on their graduation. We still have a wage
differential to overcome to compete with the State
Department of Public Works, but that matter can be
adjusted if we find enough high school students interested
enough in the program. The municipal engineering
field has many attractions, and I am reasonably certain
that we can get enough young men interested in such a
career if we give them the opportunity to try it out.
4. All proposed legislation concerning the M. D. C.
should be carefully scrutinized and examined to make
certain that its passage would have no detrimental
effect on Boston. I know of several instances of laws
being passed concerning the M. D. C. and which ap-
peared to be innocuous, but which actually will cost the
City of Boston many hundreds of thousands of dollars;
and this statement is no exaggeration. The laws were
passed before I got interested in studying such matters
14 City Document Xo. 18
folloT^ing a study that I made of the effect that the
admitting of Randolph and Westwood into the ]\1. D. C.
sewer system would have on Boston.
I also view ^ith alarm the many strictly local improve-
ments that the AI. D. C. has been undertaking over the
past three or four years. These improvements not only
have been effected in the other cities and towns of the
metropoHtan area, but also in Boston. Regardless of
where they are constructed, improvements strictly for
the benefit of individual communities are contrary to
the concept of metropolitan government and should be
undertaken and paid for by the communities benefiting
by them. The cost should not be spread over the entire
!M. D. C. area unless the benefits or improvements are
metropolitan in character. The trend (probably pro-
moted by political pressure) to have the M. D. C.
construct improvements of a local nature, should be
stopped, and any legislation pertaining to them should
be vigorously opposed by Boston and all other com-
munities interested in restricting the ]\1. D. C. to
projects or improvements that are metropolitan in
character. In any event, I wish to emphasize the
necessity of carefully studjdng any proposed law
affecting the yi. D. C, in order to make certain that
Boston is being fairly treated.
5. As you well know, chapter 407 of the Acts of
1957 provided for the alternate parking of vehicles on
public wa\'s on alternate sides of the streets on alternate
nights. In accordance with the provisions of this act,
the Traffic Commission passed a vote under date of
November 27 of 1957, implementing the law. A con-
certed effort should be made to inform the public of the
provisions of this law because if motorists are properly
informed, I am certain that they will comply with it.
The law was passed in the public interest and to increase
safety and proxide for clean streets throughout the year
and properly plowed streets during the winter months.
Up to now, the law has been followed in the breach
rather than in the observance, and I feel that the prin-
cipal reason is due to the fact that people do not under-
stand the precise provisions of the regulation. I feel
that a card informing the motorists of the law should
be placed under the windshield wiper of every vehicle
parked in the public streets during the nighttime. It
would be more effective if the Police Department
placed these cards, but apparently said department is
Public Works Department 15
not desirous of undertaking such an assignment. There-
fore, it is my intention to have some cards printed and
have them so placed by P. W. D. employees. There
probably are from 30,000 to 50,000 cars illegally parked
ever}' night, so that we have a tremendous problem,
but I think that we should make a start on it. Con-
ditions have reached the point where we cannot properly
plow residential streets, and we cannot keep them
clean, due to the continuous occupation of curb space
by parked cars during the nighttime.
Appended are reports submitted by the di^-ision heads
relative to the acti\'ities of their divisions in 1957, and
also report of the Pubhc Improvement Commission for
the same year.
Respectfully submitted,
George G. Hylaxd,
Co77i?7iissioner of Public Works.
16 City Document No. 18
MAINTENANCE APPROPRIATIONS AND EXPENDITURES.
Total Appropriations,
Division or Service.
Including
Transfers and Amounts
Carried Over from 1956.
Expenditures.
Unexpended
Balance.
Central Office
.$74,055 00
$71,488 84
.S2,.566 16
Automotive Division .
832.609 00
812,185 00
20,424 00
Bridge Division .
980,682 02
906,420 26
74,261 76
Highway Division
1,840,286 63
1,600,040 04
240,246 59
Highway Program, Chapter
718, Acts of 1956 .
2,280,208 82
1,484,467 59
795,741 23
Lighting Service .
1,609,191 06
1,609,191 06
— ■
Sanitary Division
4,993,418 75
4,959,038 85
34,379 90
Sewer Division .
799,552 08
786,871 90
12,680 18
Sumner Tunnel .
650,260 81
629,284 79
20,976 02
Survey Division .
113,900 00
113,727 57
172 43
Water Division .
2,711,529 46
2,472,526 21
239,003 25
Totals ....
$16,885,693 63
$15,445,242 11
$1,440,451 52
LOANS AND SPECIAL APPROPRIATIONS.
Title.
Total Amount
Available.
Expenditures.
Unexpended
Balance.
Bridges, Construction of (Non-Revenue)
Construction of Buildings and Original Equipment and
Furnishings Thereof (Non-Revenue)
Incinerator Building, Construction and Equipping
(Non-Revenue)
Public Ways, Construction of (Non-Revenue)
Public Ways, Construction of (Revenue)
Sewerage Works (Non-Revenue)
Snow Removal (Revenue)
Reconstruction of Streets (Revenue) ,
Sidewalks, Construction and Reconstruction of (Reve-
nue)
Street Signs (Revenue)
Totals
$4,114,577 79
8,661 09
2,391,867 95
5,160,141 16
158,338 04
1,176,989 81
475,000 00
45,572 34
291,215 72
14,035 53
$1,403,879 06
973,175 39
1,785,406 98
84,147 12
815,389 44
449,797 64
19,069 46
165,711 01
13,012 60
$2,710,698 73
8,661 09
1,418,692 56
3,374,734 18
74,190 92
361,600 37
25,202 36
26,502 88
125,504 71
1,022 93
$13,836,399 43
55,709,588 70
$8,126,810 73
Public Works Department
17
REVENUE
On Account of Public Works Department
Central Office:
Charges for plans and specifications $1,360 00
Automotive Division :
Sale of junk 411 63
Bridge Division:
Rents $1,170 00
Miscellaneous 13,858 03
15,028 03
Sumner Tunnel:
Tolls 2,589,725 00
Lighting Service:
Sale of junk 1,247 02
Highway Division:
From assessments (added to taxes) on
abutters for cost of laying sidewalks
in front of their premises $8,743 22
Permits and Driveways 73,261 46
Sale of materials, etc 375 19
Rents 10,054 50
Licenses 21,855 00
Signs 87,620 78
Contributions from Commonwealth of
Massachusetts under Chapter 90 of
General Laws for construction of
public wavs, including one bridge
amounting' to $47,192.07 629,934 07
831,844 22
Sanitary Division:
Sale of garbage and miscellaneous 5,566 68
Sewer Division:
Disposal of sewage $19,233,00
Entrance fees 14,457 70
Rents 849 00
Refunds, etc 438 00
34,977 70
Water Division:
Water rates $5,648,388 11
Water rates added to taxes 510,722 08
Service Pipes for new takers, extending,
repairing, etc 1,925 59
Fees on overdue rates 16 40
Damage to property 2,789 59
Labor and materials 2,757 74
Deposit account 78,337 67
Elevator and fire pipe connections 123 59
Miscellaneous income 1,369 32
6,246,430 09
Grand Total $9,726,590 37
18
City Document No. 18
The records of the department show that there are
now 1,985 persons ehgible for employment in the
several divisions, and of that number 1,945 were upon
the January 2, 1958 payrolls.
Grade and Number of Employees.
Services.
TlTLB.
•as
urn
go
o
6
>
1
<
•a
•c
m
■r
5
•a
CQ
1
3
1
to
•3
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
3
1
1
2
14
1
1
2
10
14
1
1
2
1
9
4
2
15
5
8
2
2
11
5
7
9
Principal senior and assistant civil
21
61
19
21
2
Senior public relations representative
1
1
Automotive and senior electrical
1
1
2
3
Assistant electrical engineers
1
4
1
Pumping station engineers and sta-
4
1
District foremen
11
1
63
7
3
08
2
16
2
5
3
28
Other foremen
11
1
''1
3
3
20
171
Legal assistant
1
Chief electrician
1
11
1
2
2
15
4
17
19
117
98
62
17
41 24 1
399
1
Public Works Department 19
Grade and Number of Employees. — Continued.
Services.
Title.
-38
am
so
o
>
o
i
<:
•c
n
ja.SP
5
■a
09
SO
1
•33
5
>
a
"3
o
4
1
17
19
117
98
62
17
41
24
.S99
Executive secretary, P. W. D
1
2
?.
Senior personnel officer and assistant . .
2
2
1
1
1
1
?,
1
1
3
1
S
Principal clerk and secretary
Principal clerks, stenographers, ac-
1
1
1
2
4
11
4
5
1
8
1
32
9
2
1
3
1
37
1
Senior clerks, typists, stenographers.
2
6
1
1
5
2
1
1
54
Clerk-stenographers, clerks, typists. . .
1?:
2
1
3
1
2
1
6
Principal storekeepers
1
2
o
Senior storekeeper and storekeepers . .
1
1
5
31
3
Chief water meter reader
1
Supervisor and special water meter
5
Water meter readers and clerks
31
Sergeant tollmen guards
5
48
5
Tollmen guards
48
1
3
9
1
Sergeants, mobile guard
3
Mobile guards
g
Drawtenders and assistants
111
111
Analytical chemist
0
Chief and senior investigators
2
7
2
Estimators and investigators
7
Dispatcher
1
Plumbers
19
1
33
19
Head photostat operator
71
76
154
Carried forward
11
44
136
145
107
777
20 City Document No. 18
Grade and Number of Employees. — Concluded.
Services.
Title,
O
o
1
<
•e
Highway-
Lighting.
Sanitary.
a
a
3
H
a
>
3
1
11
44
136
145
107
71
1
76
154
33
1
1
777
2
Principal duplicating machine oper-
7
5
2
5
1
3
2
1
3
7
13
4
1
3
9
1
10
1
20
38
1
10
1
3
1
Repairmen and maintenancemen ....
30
2
1
8
3
77
1
20
124
1
Maintenance mechanics and helpers,
1
12
2
39
1
4
7
2
7
?5
1
22
3
2
5
1
14
1
40
18
1
19
4
13
9
1
25
1
6
13
9
Heavy motor equipment operators. . .
3
2
5
18
40
61
109
12
18
24
113
205
0
19
5
1
8
20
4
96
1
303
6
15
36
3
467
10
Totals
11
110
165
352
631
175
102
364
35
1945
Public Works Department
21
Number of Employees Actually Employed January 1, 1957, and
January I, 1958.
>,
t
3
CO
3
H
on
-d
03 .a
CQ
>
>>^
O
2 'a
•as
3
mO
OQ
<
January 1, 1957
January 1, 1958
January 1, 1957
January 1, 1958
34
35
98
102
12
11
168
165
383
364
361
352
614
631
184
175
131
110
1,985
1,945
Total Eligible Force.
44
112
13
183
422
394
658
210
145
43
109
13
181
423
396
663
205
128
2,181
2,161
Appointments, Transfers, Resignations, Retirements, Deaths,
etc., of Employees.
i
s
o «
lO
00
i§
i
o>
tl
T3
Si
^
Sbbvicbs.
» _ oS
•a
•a
T3
t
a
1957-1958.
a
§5
5
'o
(S
Q
(2
go
.a
Q
s
a
4
a
a
•-1
5"
H
(2
a
<
2
3
19
1
6
12
131
170
361
Central Office . . .
Automotive
11
110
165
352
3
1
3
7
1
1
1
3
6
2
5
1
9
3
7
13
3
5
1
Highway
5
3
7
9
20
3
3
4
9
615
Sanitary
632
18
9
2
36
3
6
1
2
2
1
4
185
36
175
35
1
1
1
5
2
2
2
1
1
11
2
12
99
384
Tunnel
Water
102
365
1
5
1
1
1
1
7
1
17
18
18
65
11
39
20
40
1,993
Totals
1,947
40
18
9
80
22 City Document No. 18
APPENDIX A
REPORT OF THE AUTOMOTIVE DIVISION
FOR THE YEAR 1957
Boston, January 2, 1958.
To the Commissioner of Public Works.
Dear Sir:
I am submitting herewith the annual report of the
Automotive Division of the PubHc Works Department
for the year ending December 31, 1957. This report
covers the activities of the five garages, the Mobile
Guard Section and the Motor Pool.
The quota of employees assigned to the Automotive
Division for 1957 was 143, but due to transfers and
vacancies the number of employees dropped to an
average of 115. These employees were assigned to the
following duties: One chief automotive engineer in
charge of the division, 9 employees assigned to office
work, one dispatcher in charge of Motor Pool, four
employees assigned to stockroom, three employees
assigned to wreckers, 40 employees assigned to repair
work, 38 employees assigned to maintenance of build-
ings, gasoline and oil dispensing, cleaning, watchmen's
duties, and motor vehicle operation, and 19 employees
assigned to the Mobile Guard Section which maintains
a watch over Public Works Department property and
equipment between the hours of 4:00 p.m. and 8:00 a.m.
weekdays, and all day Saturday, Sunday, and holidays.
The office maintained by the division at City Hall
processed 1,758 requisitions in 1957, of which 1,077
were service orders, and 687 were purchase orders.
A petty cash fund of $300 was used to make about 100
purchases a month, usually under $3 each. The City
Hall office reports the following expenditures from the
1957 appropriation.
Personal services .
Contractual services
Materials and supplies
Rents and registration fees .
Purchase of new equipment
$452,301 00
64,601 00
181,070 00
11,281 00
102,932 00
$812,185 00
Public Works Department 23
The following equipment was purchased in 1957 from
budget appropriations and equipment loan:
For Sanitary Division :
Two street sweepers
Two front bucket loaders
Three 3-ton dump trucks
Three Tarco salt spreaders
For Highway Division:
Two tractor shovels
One core drill
For Sewer Division :
One sedan
For Water Division:
One derrick truck
Four 2-ton dump trucks
One 2-ton platform truck
Six express trucks
Four sedans
For Automotive Division (Mobile Guard Section) :
Three l§-ton pick-up trucks
The department's fleet of 493 units of automotive
equipment, under the supervision of this division,
consists of 82 sedans and other vehicles used for trans-
portation purposes, and 278 trucks of various sizes,
including 36 snowfighters, ten compressors, four catch-
basin cleaners, 35 pick-up trucks, 131 dump trucks,
six wreckers, six flushers, three derrick trucks, two lumber
trucks, one rack truck with crane, three platform
trucks, 32 emergency trucks and nine miscellaneous
trucks. There are 28 street sweepers, 11 gasoline road
rollers, seven snow and bucket loaders, 19 front bucket
loaders, two tractor shovels, four crawler tractors,
one grader, and three trailer compressors, and 58 pieces
of miscellaneous equipment ; 440 of these units are regis-
tered under the motor vehicle law of the Commonwealth.
The repair shop at the Highland street garage per-
formed approximately 12,000 repair jobs, including tire
repairs and lubrication check-ups. Six thousand repair
work orders were made out by the motor equipment
repairmen. Contracts in the amount of $10,000, and
$6,000 were issued for the respective repair of Walter
Snowfighters and F.W.D. trucks.
24 City Document No. 18
The Mobile Guard and the Motor Pool operated in a
satisfactory manner during 1957. The laborer-watch-
men in the Mobile Guard were transferred from the
Automotive Division to the Sanitary and Highway
Divisions. The Motor Pool consists of one dispatcher
and seven drivers (one from the Automotive Division).
The dispatcher makes all assignments to the drivers,
and also has charge of the short-wave radio. Within
the Public Works Department are 44 cars equipped with
two-way radios. The Motor Pool assignments outside
the Public Works Department consist of the following:
Institutions Department — Conveying patients to Tewks-
bury, Long Island, and Nazareth.
Purchasing Department — Conveying inspectors to sources
of supplies.
Public Library — Checking district libraries.
Election Department — Conveying voting machine in-
spectors, and work on election days.
Assessing Department, Printing Department, Public Cele-
brations, and Mayor's Office — Various assignments.
Real Estate Division — Conveying city auctioneer to loca-
tions where city-owned property is to be auctioned.
The Mobile Guard Section, with 19 men and three
vehicles, patrolled the city, protecting Public Works
property. The guards inspect all yards and at each
location punch a Detex time clock. Watchmen are
permanently stationed on locations where experience
has shown that it is advisable to have a man present at
all times to protect city property.
Several improvements to the buildings and equip-
ment were made in 1957. A new hoist with lubrication
equipment was installed at the Forest Hills garage to
take care of snow fighting equipment. New overhead
doors were installed at the Albany street, and Hyde
Park garages. The lubrication lift at the Highland
street garage was remodeled to handle the latest models
of passenger cars. A complete new Alemite system was
installed at Highland street to replace the worn out
system.
If sufficient funds are available from Equipment
Loans in 1958, considerable new equipment to replace
worn out and outmoded automotive equipment will be
purchased.
Public Works Department
25
NUMBER OF EACH TYPE OF AUTOMOTIVE EQUIPMENT
IN PUBLIC WORKS DEPARTMENT
Passenger cars
82
Trucks, half-ton .
35
Trucks, 1 to 1^ ton
47
Trucks, 2 to 3 ton
133
Trucks, 5 to 8 ton
5
Wreckers
6
Compressors .
10
Trailer compressors
3
Crawler tractors .
4
Tractor shovels
2
Front bucket loaders
19
Grader .
1
Street flushers
6
Street sweepers
28
Road and sidewalk rollers
11
Snow fighters
36
Snow and bucket loaders
7
Miscellaneous equipment
58
Total ....
493
Registered
440
Respectfully submitted,
James H. Stewart,
Chief Automotive Engineer.
26 City Document No. 18
APPENDIX B
REPORT OF THE DIVISION ENGINEER OF
THE BRIDGE DIVISION
Boston, January 2, 1958.
To the Commissioner of Public Works.
Dear Sir:
Submitted herewith is the annual report of the Bridge
Division, covering the income, expenditures and opera-
tion of the Bridge Service and the Sumner Tunnel for
the year ending December 31, 1957.
Respectfully,
John J. McCall,
Division Engineer,
Bridge Division.
Public Works Department
27
I. BRIDGE SERVICE.
Summary of Budget Appropriations and Expenditures
Regular
Appropria-
tion
Bridges,
Repairs, etc.
Bridges, Construction op
Revenue
Non -Revenue
Balance from 1956
1957 Appropriation ....
$699,786 00
$61,570 37
70,000 00
$149,325 65
$4,067,385 72
47,192 07
Total Credits
$699,786 00
9,639 00
$131,570 37
$149,325 65
$4,114,577 79
Transfers from
Encumbrances
Total Debits
$676,659 51
686,298 51
$71,368 36
71,368 36
$148,753 39
148,753 39
$549,938 71
853,940 35
Unencumbered
Balances
$13,487 49
$60,202 01
$572 26
$2,710,698 73
Details of Expenditures on Tidewater Bridges
TIDEWATER BRIDGES— 1957
Bridge
Draw-
tenders'
Salaries
Mechanics'
Wages
Material
T, . Supplies,
Repair utUities,
Bi^ Etc.
Total
*Broadway
$15,290 15
50,789 36
58,194 42
43,704 76
41,893 99
57,870 36
56,701 30
60,535 18
46,812 74
$1,092 10
1,924 81
3,736 64
2,404 58
3,465 34
6,152 56
2,295 76
2,650 71
8,179 56
18,957 53
$28 58
16 40
201 97
87 68
565 03
472 77
68 63
73 80
770 75
13.551 85
$192 20
1,943 61
328 16
785 08
176 40
940 33
1,022 69
2,420 64
4,443 18
2,852 06
$339 28
1,271 55
682 94
658 24
601 26
870 46
2,223 42
2,485 27
691 67
$16,942 31
55,945 73
63,144 13
47,640 34
4,206 77
50,060 91
62,127 90
64,069 87
76,413 94
82,865 85
Charlestown
Chelsea Street
Congress Street
♦Dover Street
L Street
Maiden
Andrew P. McArdle.. . .
Northern Avenue
Summer Street
Totals
$431,792 26
$50,859 59
$15,837 46
$15,104 35
$9,824 09
$523,417 75
* Not operating as drawbridge but kept in operable condition
Fitzgerald Expressway in Fort Point Channel area.
for possible use during construction of
28
City Document No. 18
u
O
Q
OQ
<
Q
E
O
O
C^
E
O
<
U
z
o
CO
o^
u
H
rrl
a
o
H
a
G,
O
r/j
<1>
=?
O
H^
1=1 -£3
on 03
Ph
«
3
o
CO »o C5 1:0
•# o
^ fO (M
r^ t^ rt O
Tj^ Tt< ^
O CO 10
00 10 10
c
<B
•5
-tJ
0
TA)
00
OJ
Qi
c«
<D
Xi
-C3
u
u
fa «
-^ s
3 <:
o
a a
a a I
3 3 I
Public Works Department 29
At the beginning of 1957, the Bridge Division main-
tained eleven (11) drawbridges, three of which were not
operated as such; Broadway, Dover Street, and Warren
Bridge.
The status and conditions of the various drawbridges
are summarized as follows:
Fort Point Channel
Dover Street and Broadway Bridges
These bridges were not operated during the year but
were maintained in operable condition in the event that
the construction of the Fitzgerald Expressway would
require the use of waterborne equipment using the
channelway. To date, this has not been necessary.
In connection with the Dover Street Bridge, it has
been decided to replace this structure with a solid fill
causeway having culvert facilities to accommodate the
tidal flow of the channel; and the Massachusetts Depart-
ment of Public Works has agreed to execute the project
under the provisions of Section 34, Chapter 90, of the
General Laws, on condition that the City will contribute
$350,000 which represents 50 per cent of the estimated
cost of the project.
This decision was based on an engineering study and
report made for this department by William A. Fisher
Company, Inc., consulting engineers.
At the present time, the Massachusetts Department
of Public Works are having plans and specifications
drawn for the project; and it is expected that these will
be completed and the work commenced within the next
few months; more or less in conjunction with the con-
struction of the Fitzgerald Expressway facilities at
Dover and Albany streets.
It is hoped that the replacement of Dover Street
Bridge with a solid fill causeway will accelerate the
filling-in of the channel at least to its upper end at
Massachusetts avenue.
Summer Street, Congress Street, and Northern Avenue
Bridges
These bridges are still fully operating.
The rebuilding of the Summer Street Bridge is being
deferred until the American Sugar Refinery has re-
located in the Charlestown area; at which time it is
30 City Document No. 18
fully expected that the Fort Point Channel will be en-
tirely closed to navigation, thereby permitting the
replacement of the Summer Street Bridge with a fixed
span.
The Congress Street Bridge is in good condition.
The Northern Avenue Bridge is operating satis-
factorily but requires constant maintenance. Struc-
turally, the bridge is of an age, type and condition that
warrants replacement; and this project should be
scheduled as soon as feasible, consistent with the ex-
pected closing of the channel to navigation.
Reserved Channel
Summer Street Bridge (Formerly L Street Bridge)
This bridge is scheduled for major repairs to the ap-
proaches in the coming year. Under a Chapter 90
project, with the City assuming 40 per cent of the cost
and the Commonwealth 60 per cent, the South Boston
approach is to be entirely rebuilt and the Boston ap-
proach pilework repaired throughout. On the basis of
bids received on December 10, 1957, the estimated cost
is $234,326.
The work to be done under this project is based on the
findings of a professional inspection of the pilework
and timberwork made by the Carnes Company, Inc.,
who were engaged by this department for the purpose.
The inspection was made early in the year and com-
pleted with a report on March 28, 1957.
The drawspan of this bridge is not included in the
work to be done. The draw is in good operating con-
dition; and although the deck and superstructure will
probably need repairs in the near future, it is hoped
that the channelway can possibly be closed to navi-
gation in the reasonably near future, thereby making it
possible to build a fixed span to replace the draw span.
Charles River
Warren Bridge
This bridge has been deactivated since November of
1954; with the movable draw spans pulled back to leave
the waterway unobstructed. Although the bridge was
closed to highway traffic and the drawbridge out of
operation, it was maintained in operable condition for
Public Works Department 31
emergency use until such time as the Charlestown
Bridge reconstruction had progressed sufficiently to rule
out the further need of Warren Bridge.
In September, 1957, Warren Bridge was officially dis-
continued as a public way from the pierhead line on the
Charlestown end to the line of the Fitzgerald Express-
way at the Boston end.
Accordingly, the drawspan structures were dismantled
and removed under contract late in 1957, at a cost of
$1,497.
It is hoped that the remaining pile trestle approaches
can be removed in the reasonably near future under the
provisions of Chapter 91, of the General Laws, with the
Commonwealth and the City each paying 50 percent
of the cost.
Charlestown Bridge
The drawspan of this bridge has been closed to navi-
gation since May 1, 1957, in order to permit the removal
of the old mechanical and electrical operating equipment
and installation of the new system.
This work is now near completion; and the drawspan
will be restored to operation early in 1958.
Otherwise, the reconstruction of this bridge is in its
final stage. At the present time, the bridge is still
carrying 2- way vehicular traffic on one roadway; and
sometime in February, 1958, should be fully opened to
traffic with all work completed.
Chelsea River
Chelsea Street and Andrew P. McArdle Bridges
The two drawbridges spanning the Chelsea River at
Meridian street and Chelsea street are in good condition
and fully operating.
At the Chelsea Street Bridge, it is intended to alter
the fender pier construction to comply with an order of
the Corps of Engineers, United States Army, to widen
the navigable waterway under the bridge to 96 feet. It
now varies from 70 feet at the upstream side to about
98 feet at the downstream side. The alteration is made
necessary because of the proposed permanent removal of
the New York Central Railroad bridge immediately
upstream of the City bridge.
32 City Document No. 18
Mystic River
Maiden Bridge {Alford Street)
This bridge is fully operating but is in very poor con-
dition structurally, requiring constant maintenance.
This bridge should be replaced by a new structure as
soon as possible; and it is expected that this project will
be undertaken by the Massachusetts Department of
Public Works as soon as Federal Aid funds are available,
around July 1, 1958.
Inland Bridges
This department is involved in the maintenance of
80 inland bridges as follows:
Maintained entirely by this department
Maintained jointly with New Haven RR
Maintained jointly with Boston & Albany RR
Maintained jointly with Boston & Maine RR
Maintained jointly with M.TA. .
Maintained jointly with Town of Winthrop
Maintained jointly with Town of Milton
Maintained jointly with Town of Watertown
49
15
10
1
1
1
2
1
Total 80
During 1957, two major improvements were completed
in the rebuilding of the Massachusetts Avenue Bridge
over the New York, New Haven and Hartford Railroad,
and the Winthrop Bridge over Belle Isle Inlet. These
projects are described in detail hereinafter.
The Boylston Street Bridge over the Boston and
Albany Railroad is in serious need of a new steel floor
system and deck. It was intended to prosecute such
work in 1957, but because of the uncertainty of final
plans involving the use of the railroad right of way for
an extension of the Massachusetts Turnpike as far as
the proposed new Prudential Center, and the possibility
that the present bridge may have to be rebuilt, the re-
decking work has been deferred.
The Broadway Bridge over the Boston & Albany
Railroad is in poor condition, and the city has peti-
tioned the Massachusetts Department of Public Utilities
on the matter of rebuilding. A hearing on the matter
was held before the Department of Public Utilities on
October 7, 1957, and was postponed to permit of further
inspections and reports on the existing structure.
Public Works Department 33
The city engaged the services of the Charles A.
Magiiire and Associates to furnish such inspection and
report.
Any action relating to this bridge may possibly be
deferred until such time as it is decided whether the
Massachusetts Turnpike will be extended to the South
Station.
The same is true of the Massachusetts Avenue Bridge
over the Boston and Albany Railroad, which should be
scheduled for major repairs or rebuilding within the next
few years.
In general, otherwise, the fixed bridges throughout the
city are in good condition, although several should be
rebuilt to provide modern structures to accommodate
present day traffic conditions.
Among these are the bridges located over the railroads
at Tremont street (Arlington square), Southampton
street, Boston street, Dorchester avenue, and Ben-
nington street. East Boston.
Major Construction Work and Repairs
Reconstruction of Charlestown Bridge
At the close of 1957, this project was nearing comple-
tion under separate contracts covering the drawspan
and the approach spans. The work has been fully
described in previous reports, having started late in
1955.
The work should be entirely completed early in 1958,
at an estimated cost of $615,000 for the drawspan; and
1925,000 for the approach spans. The original esti-
mated cost based on the bid of the contractor. Builders
Iron Works, was $606,204 for the drawspan and
$931,965.50 for the approach spans.
Reconstruction of the Massachusetts Avenue Bridge
Over the New York, New Haven & Hartford Rail-
road
A contract for this work was awarded to the low
bidder. Builders Iron Works, in the amount of
$143,854.75.
Work was commenced on April 8, 1957, and com-
pleted on November 15, 1957, at a final cost of
$144,978.36.
This work was carried on without interfering with
traffic by rebuilding the bridge one third at a ti
34 City Document No. 18
This work has resulted in a major improvement by
replacing the old through girders with a deck type beam
span thereby eliminating a dangerous traffic hazard
and restriction.
Rebuilding the Winthrop Bridge over Belle Isle Inlet
Under the provision of Chapter 90, Section 34 of the
General Laws, this bridge was rebuilt at a final cost of
$148,942.05; which cost was apportioned as follows:
Commonwealth (60%) .... $89,365 23
City of Boston (24%) .... 35,746 09
Town of Winthrop (16%) . . . 23,830 73
The new bridge was built one half at a time in order
to maintain traffic; and consists of a pile trestle founda-
tion carrying a reinforced concrete deck and sidewalks.
The new bridge is 10 feet wider than the old bridge
which was of pile trestle construction with an all- wooden
deck and sidewalks. The approaches were widened
and improved to meet the new conditions.
Under a contract awarded to the low bidder. Eastern
Roads Company, Inc., work commenced on March 27,
1957 and was completed on December 31, 1957.
Reconstructing Span No. 3 of the Northern Avenue
Bridge over Fort Point Channel
Because of the badly deteriorated condition of some
of the main steelwork in this span it was necessary to
make a major improvement. Inasmuch as the defective
condition of the steelwork was brought about mainly
by the Union Freight Railroad traffic, the railroad
company was asked to participate in the cost of repairs,
to which they agreed.
Accordingly, it was arranged for the city to remove
the old decking, allowing the railroad to repair the steel-
work, after which the city would construct a new deck.
This work was commenced under a contract awarded
to Frederick W. Byron for the city's portion of the
work, on June 24, 1957.
The railroad engaged the Groisser & Shlager Iron
Works to make the necessary steel repairs and renewals.
Public Works Department 35
At this writing the work is two thirds completed and
the final third is expected to be completed early in 1958.
The final portion of work was of necessity postponed
because of winter conditions.
The total estimated cost to the city for this work is
approximately $27,000,
The railroad's cost is estimated to be approximately
$20,000.
Emergency Repairs to the Operating Machinery of the
Congress Street Bridge over Fort Point Channel
On April 10, 1957, a very serious defect was dis-
covered in the gears of the operating machinery of the
drawspan of this bridge, which made it extremely
dangerous to attempt further openings of the draw.
Accordingly, an emergency contract was awarded to
the General Ship & Engine Works of East Boston for
making the necessary repairs. This was necessary in
order to make all possible speed in restoring the bridge
to operation so that the important sugar cargo boats
could be allowed to pass.
Repair work was commenced on April 11, 1957, and
finished on May 1, 1957, at a final cost to the city of
$12,000.
On the thirteenth of April, temporary repairs were
made to permit one opening for a sugar cargo vessel
which otherwise would have been held up for more than
two weeks.
Demolition and Removal of the Warren Bridge Draw-
span
Warren Bridge was closed permanently to highway
traffic on November 26, 1954, and the two drawspan
units drawn back to permit an unobstructed waterway.
The bridge was kept operable until such time as the
Charlestown Bridge reconstruction project was sub-
stantially completed.
In September, 1957, Warren Bridge was officially dis-
continued as a highway under a contract awarded
to James G. Grant Co., low bidder, for the removal and
disposal of the two movable drawspan superstructures.
The work was commenced on November 12, 1957,
and completed on December 29, 1957, at a cost of
$1,497.
36
City Document No. 18
other Work Accomplished Under Contract By the Bridge Division
During 1957
Work Cost Contractor
Resurfacing, etc.
Arlington street over Boston and Al- „„, ,„ .1. ^ /^ r-. r
bany Railroad $4,224 48 Albert C. Graglia
Furnishing field inspection, services, etc. ^ , ^^ ^^ „ ^^
Charlestown Bridge .... 3,150 00 Carnes Co.
Repairing the Fender System.
^Thr„fr" ''"''' °"' ""' ' 8.081 28 W. H. Ellis & Son Co.
Demolition and removal of buildings,
SouSVerT" '"'"'""*' • • • 3.730 00 Lawrence Buildmg Wrecking Co.
n'JriSfsSdgS'' ''■'''"''"'■. . . 5.173 00 J. J. Finn Electrical Service
Inspection of Piling — Boston Approach
and Dravirspan Foundation.
Summer Street Bridge over Reserve
Channel 1>700 00 Carnes Co.
Yard Forces
The maintenance force of the Bridge Service is utihzed
in the various repair operations of both emergency and
routine nature in repairs to bridge roadway deckmg,
sidewalks, fender piers, retractile bridge tracks, stair-
ways, raihng and pertinent facilities.
Other work included placing barricades and trattic
control signs necessary during the periods of pouring
concrete deck slabs and the testing of mechanical and
electrical facihties of bridges being repaired; and clean-
ing bridge sidewalks and stairways of ice and snow.
II. SUMNER TUNNEL
1957 Budget Summary
Credits:
Appropriation Credits, 1957
Pensions ....
Total Credits
Debits:
Expenditures, 1957
Unliquidated Encumbrances
Pensions ....
Total Debits .
Unencumbered Balance
$650,260 81
45,639 63
$695,900 44
$629,284 79
374 00
45,639 63
$675,298 42
$20,602 02
Public Works Department
SUMMARY OF 1957 TRAFFIC BY CLASSIFICATIONS
37
Class Toll Description
1. $0 20 Truck not in excess of 2 tons capacit3\
Tractor without trailer
2. 0 20 Passenger car
3. 0 20 Motorcycle .
4. 0 25 Truck over 2 tons and up to 5 tons capacity.
Tractor with trailer over 2 tons and up to 5 tons
capacity
5. 0 20 Passenger car with trailer
6. 0 35 Truck over 5 tons and up to 10 tons capacity.
Tractor with trailer over 5 tons and up to 10 tons
capacity
7. 0 20 Tractor with trailer not in excess of 2 tons capacity
8. 1 00 Truck over 10 tons capacity
9. 0 35 Bus with or without passengers ....
* Reserved Lane
No. of
Vehicles
400,893
12,199,300
3,807
61,668
19,740
19,460
2,810
1,837
4,755
182,454
Total Traffic 12,896,724
* M. T. A. and Eastern Massachusetts Railway buses included in this classification.
7,156 M. T. A. and 75,962 Eastern Massachusetts Railway buses at $0.35 included in
this total.
COMPARATIVE 5=YEAR SUMMARY OF OPERATION, FROM
1953 TO 1957, INCLUSIVE
1953
1954
1955
1956
1957
hicular Traffic:
Total number vehicles
10,835,674
902,973
208,378
29,686
11,080,966
923,414
212,513
30,359
12,094,107
1,007,842
231,945
33,135
12,736,726
1,061,394
244,552
34,800
12,896,724
1,074,727
248,014
35 333
Weekly average
Daily average
wer Consumption:
4,966,604
4,527,315
5,236,214
5,614,061
6,079,026
tiancial Results:
Dperating expenditure
Balance to next year
nterest requirements
$591,327 09
16,591 87
687,494 39
440 60
$595,127 07
3,925 18
740,213 05
122 85
$585,650 61
6,188 73
760,100 00
98 60
$649,869 99
28,924 02
743,991 37
$674,924 42
374 00
748,762 50
1 80
Total Expenses
$1,295,853 95
$1,339,388 15
$1,395,093 63
$1,422,785 38
$1,424,062 72
$2,172,410 00
24,679 45
$2,224,195 00
16,591 87
$2,413,231 59
3,925 18
$2,550,125 00
6,188 73
$2,589,725 00
28,924 02
Jalance from previous year
Total Receipts
$2,197,089 45
$2,240,786 87
$2,417,156 77
$2,556,313 73
$2,618,649 02
Net Result
$901,235 50
(Excess)
$901,398 72
(Excess)
$1,022,063 14
(Excess)
$1 133 528 35
$1,194,586 30
(Excess)
(Excess)
38 City Document No. 18.
SUMNER TUNNEL
The Sumner Tunnel is a vehicular crossing between
Boston proper and East Boston, and was opened for
public use on June 30, 1934, and has been in continuous
operation up to the present time.
The total traffic for the past year of 1957, which has
been the highest in its history; amounted to 12,896,724
vehicles, an increase of 159,998 cars over the previous
year of 1956.
All of the electrical and mechanical machinery and
equipment used in connection with the ventilating and
operation of the tunnel is in good condition and operat-
ing satisfactorily.
The Toll Collecting equipment including all treadles,
key boxes and toll registers are under constant supervi-
sion and are recording and totalizing properly as per
traffic requirements. All adjustments and repairs are
made as may be required.
On December 20, 1957 a hearing was held by the
Massachusetts Department of Public Utilities relative
to toll rates for the coming year, 1958. It was agreed
that the present rates be continued without change.
To date, the Massachusetts Port Authority which was
created to consolidate several facilities, including the
Sumner Tunnel, under one agency has not begun to
function. Consequently, the operation, care and con-
trol of the Sumner Tunnel remains with the City of
Boston.
Contracts Awarded in 1957
1. Drainage System
A contract was aw^arded to the Mercer Marine Com-
pany after being properly advertised, for the sum of
$1,910 to clean and remove all mud and dirt from all
catch basins, 72 drop inlets, all sand traps, sumps, etc.,
of the tunnel drainage system. All of the work had to
be performed between the hours of 12.30 a.m. and
5.30 A.M.
2. Oil Burner
Invitation bids were sent to eight (8) of the larger
oil companies for furnishing and installing a new oil
burner in the Boston Ventilation Building, to replace
the original burner that had been in continuous service
since 1934. This contract was awarded to the Esso Oil
Burner Company for the amount of $456.
Public Works Department 39
3. Boston and East Boston Ventilation Buildings
Specifications were written and a contract awarded
after advertising, to the Bond Painting Company for
the sum of §14,321 to paint all of the steel and structures
of these two buildings, including all glazing, and the
removal of all existing glass louvers, and replacing them
with Transite panels, all in accordance with the contract.
4- Cleaning Exhaust Air Duct and Fan Rooms
Bids were received after public advertisement for the
''cleaning of exhaust air duct and fan rooms" and a
contract awarded to the Mercer Marine Company for
the cleaning and removal of all dust and dirt from the
exhaust air duct and from 14 exhaust fan rooms. The
total bid for this work amounted to $1,195.
6. Cleaning and Painting Ventilation Equipment at
Ventilation Buildings
Specifications were WTitten and advertised, and a
contract awarded to Joseph and Nicholas Bello, in the
amount of $7,941 for the cleaning and painting of ventila-
tion equipment at the Sumner Tunnel Ventilation
Buildings. This work called for the cleaning and paint-
ing of 28 ventilating fans, fan motors, dampers, damper
operating mechanisms, fan housings, inside and outside,
controllers, etc.
6. Control Cable
During the past year a contract was advertised and
awarded to the Minot Construction Company for the
sum of $5,691 to install 4,292 feet of new 259 conductor
No. 19 A.W.G. control cable furnished by the City of
Boston. All work performed as per contract and
specifications.
7. Splicing Chamber Cover Plates
Bids were received after public advertisement and a
contract awarded to the Albany Contracting Company
for the sum of $1,830 to clean and paint all south wall
chamber frames and cover plates. All work was per-
formed as per specification and with no interference to
vehicular traffic, all work between the hours of 12.30
A.M. and 5.30 a.m.
40 City Document No. 18
APPENDIX C
REPORT OF THE DIVISION ENGINEER OF
THE HIGHWAY DIVISION
BcsTON, January 2, 1958.
To the Commissioner of Public Works.
Dear Sir:
The following report of the income, expenditures, and
operation of the Highway Division of the Public Works
Department is hereby submitted for the year ending
December 31, 1957.
Respectfully submitted,
RUTHFORD J. KeLLEY,
Division Engineer, Highway Division.
Public Works Department
41
HIGHWAY DIVISION
Paving Service
Summary of Budget Appropriations
Appropriation.
Total Credits. Expenditures
Balance
Unexpended.
Paving Service .
Reconstruction of
Streets
Public Ways, Construc-
tion of (Revenue). . . .
Public Ways, Construc-
tion of (Non-Revenue)
Sidewalks, Construction
and Reconstruction of
Street Signs
Snow Reomoval
Chapter 718 — Acts of
1956
$1,840,286 63
45,572 34
158,338 04
5,160,141 16
291,215 72
14,035 53
475,000 00
2,280,208 82
$1,600,040 04
19,069 46
84,147 12
1,785,406 98
166,711 01
13,012 60
449,797 64
1,484,467 59
$240,246 59
26,502 88
74,190 92
3,374,734 18
125,504 71
1,022 93
25,202 36
795,741 23
In the Permit Office, the permits issued and monies
received for 1957 are as follows:
Permits Issued
Signs
Occupation permits .
Sidewalk licenses
Driveway applications
Special permits .
Department permits (free)
Street opening permits
7,361
7,444
330
316
392
1,253
505
Total permits 17,601
42 City Document No. 18
Cash Received
Occupation permits $72,631 46
Signs 87,620 78
Sidewalk license 21,855 00
Plans and miscellaneous 16 75
Driveway applications 630 00
Notifications 110 00
Rents 10,054 50
Total income less street openings . . . $192,918 49
Street openings 73,354 72
Total income $266,273 21
The regular forces of the Paving Service were em-
ployed as usual in the maintenance of public streets,
resurfacing and patching macadam pavements, patching
permanent pavements, such as asphalt and granite
block, and maintaining gravel, brick, and artificial stone
sidewalks.
In the snow removal season, division forces were em-
ployed in spreading rock salt and sand on icy streets
and also supervised plowing work throughout the City
by 250 contractors' hired plows after snowstorms. All
snow removal bills for plowing, hauling, force account
work, cubic yard removal, etc., were processed through
the Paving Service office.
The following work was done in placing new street
signs and replacing and repairing existing street signs :
Erected 217 4-inch street signposts.
Erected 8 new hero signs for dedication.
Replaced 186 hereo square signs.
Installed 752 new street signs.
Removed 384 old hand-painted signs, damaged baked
enameled signs and obliterated signs.
Repaired and straightened 168 bent or broken street sign
posts (4-inch type).
Repaired 276 broken street sign frames and welded 59
4-inch street sign posts in blacksmith shop.
Repaired 598 street sign frames, collars, and brackets on
4-inch street sign posts and light poles on location.
Removed 132 pieces of rope, wire, old tires, etc. from 4-inch
street sign posts and light poles.
Installed 588 street sign frames.
Installed 367 street sign collars on 4-inch street sign posts
and light poles.
Installed 57 adapters on wooden poles.
Installed 201 4-inch acorns on 4-inch street sign posts.
Public Works Department 43
Installed 110 "Private Way" signs on 4-inch street sign
posts and light poles.
Removed 53 "Private Way" signs from 4-inch posts and
light poles because of the making of public ways.
Painted 602 4-inch street sign posts.
Painted 898 street sign frames.
Painted 397 4-inch acorns on 4-inch street sign posts.
Painted 649 street sign collars on street sign posts and light
poles.
Installed 12 directional signs on 4-inch posts.
Washed and cleaned 376 street sign name plates.
Painted 293 blanks for temporary name platea.
There were 220 streets constructed or reconstructed
during the year. There were approximately 6| miles of
sidewalks improved during the year 1957.
Some of the more important thoroughfares on which
reconstruction work was completed in 1957 are as
follows :
Commonwealth avenue, from Brighton avenue to Warren
street (Chapter 90).
Blue Hill avenue, from Columbia road to Mattapan square
(Chapter 90).
Centre street, West Poxbury, from Spring street to Grove
street (Chapter 90).
Baker street, West Roxbury, from Veterans of Foreign
Wars Parkway to Newton line (Chapter 90).
Summer street, South Boston, from viaduct to East
Second street, excluding drawbridge and approaches of bridge
over reserved channel (Chapter 90).
L street, South Boston, from East Second street to East
Fourth street (Chapter 90).
Washington street, Roxbury, from Northampton street
to Eustis street (Chapter 90) .
Arlington street. City Proper, from Boylston street to
Beacon street.
Beech street. West Roxbury, from Kittredge street to
Poplar street.
Berkeley street. City Proper, from Boylston street to
Beacon street.
Boylston street, City Proper, from Tremont street to
Charles street, and from Arlington street to Berkeley street.
Centre street. West Roxbury, from Eliot street to Prince
street.
Clarendon street, City Proper, from Boylston street to
Beacon street.
Day square. East Boston.
Jackson square and vicinity, Roxbury, including parts of
Centre street, Columbus avenue, and Ritchie street.
44 City Document No. 18
Massachusetts avenue, City Proper and Roxbury, from
Huntington avenue to Columbus avenue.
Metropolitan avenue, Hyde Park, from Beacon street to
Milton line.
North Harvard street, Brighton, from Hooker street to
Western avenue.
Parker Hill avenue, Roxbury, from Parker street to
Sunset street.
Perkins street, West Roxbury, from Prince street to Francis
Parkman Drive.
Ruggles street, Roxbury, from Columbus avenue to Leon
street.
Roxbury Crossing, Roxbury, from Tremont street to
Roxbury street.
The following is a list of streets constructed and
reconstructed and sidewalk work done by contract in
the various wards of the City in 1957.
Ward 1 — Chelsea street, Orleans street, Shelby street,
Eagle square. East Eagle street, Boardman street, Prescott
street, Sea View avenue, Trenton street, Walley street.
Day square, Ashley street, Leyden street.
Ward 2 — Bunker Hill street (Chapter 90), Chelsea street
(Chapter 90), Hunter street (Chapter 90), Moulton street
(Chapter 90), Vine street (Chapter 90).
Ward 3 — Bulfinch street (sidewalks), Tileston street
(sidewalks), Bulfinch place (sidewalks), Wiggin street (side-
walks). Commercial street (sidewalks), Bowker street,
Chardon street, Devonshire street, Foster street, Hawkins
street, Henchman street, Pitts street. Court street, Merrimac
street, Tremont street. Green street, Hayward place, Har-
rison avenue. Arch street, Franklin street, Tremont street,
Washington street, High street, Matthews street. Leather
square. North Bennett street.
Ward 4 — Huntington avenue (sidewalks). Saint Cecilia
street (sidewalks), Saint Stephen street (sidewalks), Stuart
street (sidewalks), Gainsborough street (sidewalks), Hemen-
way street (sidewalks). Saint Botolph street (sidewalks,
Forsyth street, Dalton street (sidewalks), Falmouth street
(sidewalks), Carleton street, Forsyth street (roadway
widening), Ruggles street, Clarendon street, Massachusetts
avenue (H — C), Saint James avenue, Massachusetts
avenue (W — B).
Ward 5 — Brookline avenue. Beacon street (sidewalks),
Marlborough street (sidewalks), Hereford street (sidewalks),
Newbury street (sidewalks), Berkeley street, Boylston
street, Clarendon street. Public Alley No. 439, Arlington
street. Beacon street, Dartmouth street, Exeter street,
Hereford street, Boylston street, Eliot street, Stuart street,
Public Works Department 45
Tremont street, Beacon street (MA — CE), Pinckney
street, Peterborough street (sidewalks), Dartmouth street
(sidewalks).
Ward 6 — East Fifth street, Northern avenue, Columbia
road, East Fourth street, M street. West Fourth street. East
Sixth street, L street and Summer street (Chapter 90),
B street, Fargo street.
Ward 7 — Dr. Michael Gavin Way (sidewalks), General
Lawrence J. Logan Way (sidewalks). General William H.
Devine Way (sidewalks), Kemp street (sidewalks), Major
Michael J. O'Connor Way (sidewalks), Monsignor Dennis F.
O'Callaghan Way (sidewalks), Mayhew street (sidewalks,
Columbia road, Dudley terrace.
Ward 8 — Washington street (Chapter 90), Eustis street
(Chapter 90).
Ward 9 — Greenwich court, Columbus avenue, Simmons
street, Massachusetts avenue, Tremont street, Washington
street (Chapter 90).
Ward 10 — Alleghany street, Calumet street, Fisher
avenue, Iroquois street, Parker street, Parker Hill avenue,
Pontiac street. Saint Alphonsus street. Darling street,
Walden street.
Ward 11 — Fort avenue (safety barrier), Glen road.
Forest Hills street, Cemetery road, McBride street (side-
walks), Jamaica street, Columbus avenue.
Ward 12 — Forest Hills street, Cemetery road, Crest-
wood park, Lorimer place, Park View street. Blue Hill
avenue (Chapter 90).
Ward 13 — Mount Vernon street (sidewalks), Dalin
place, Howard place.
Ward 14 — Brunswick street. Blue Hill avenue (Chap-
ter 90).
Ward 15 — Homes avenue (sidewalks).
Ward 16 — King street (sidewalks), Whitten street,
Daytona terrace, Hutchinson street, Glide street (sidewalks).
Ward 17 — Barna road. Range road.
Ward 18 — Chapel road, Meadowview road. Millstone
road. Beech street, Canterbury street. Deforest street,
Rosa street, Harmon street, Richmere road, Loring street
(sidewalks), Tyler street (sidewalks), Blue Hill avenue
(Chapter 90), River street (Chapter 90), Brainard street,
Cliftondale street, Harvard avenue. Metropolitan avenue,
Prospect street, Radcliffe road, Rosemont street, Ruskin-
dale road, Taunton avenue, Tileston street, Gordon avenue
(sidewalks). Hale street (sidewalks), Daniel court, Dietz
court, Dietz road. Dodge road, Eastmont road, Kardon
road, Kristin court, Leighton road, Senders court, Susanna
court, Wharton court, Belnap road. Greenwood avenue.
Metropolitan avenue, Gordon avenue, Derry road, Green-
46
City Document No. 18
wood Circle, Huntington avenue, Melba Way, Safford street,
Barry street, Chestnut street, Byrd avenue, DeStefano
road, Rosecliff terrace.
Ward 19 — Louder's Lane, Wachusett street, Alveston
street. Centre street, Dunster road, Granfield avenue. Moss
Hill road, Patten street, Roanoke avenue, Elm street,
Cummins Highway (sidewalks), Agassiz park, Cheshire
Street Extension, Driftwood road, Mossdale road, Meyer
street, Pershing road, Perkins street.
Ward 20 — Eastbourne street, Edgemere road, Glen-
burnie road, Keith street, Landseer street, Mendum street,
Pelton street, Redgate road, Rockland street, Schiller road,
Anawan terrace, Albright street, Libbey street. Maple
Street Extension, Maple Street Footway, Carey street
(sidewalks), Woodard Road (sidewalks), Alaric street (side-
walks), Gretter road (sidewalks). Centre street and Baker
street (Chapter 90), Gardner street, Rivermoor street,
Charles Park road. Autumn street, Cohasset street, Dunwell
street, Francesca street, Heldun street, Joyce Kilmer road,
Lasell street, Manthorne road, Montview street, Peak Hill
road, Perham street, Powell street. Saint Theresa avenue,
Gretter road, Schirmer road, Grayfield avenue, Crockers
Lane, Hackensack road, Marlin road, Sherbrook street,
Spinney street, Welton road, Corey street. Church street,
Jacqueline road, Willowdean avenue, Courtney road, Willow
terrace.
Ward 21 — Brookline avenue. Overland street, Englewood
avenue. Beacon street (sidewalks), Commonwealth avenue
(sidewalks), Colborne road, Hinsdale street, Keswick street,
Medfield street, Blenford road.
Ward 22 — Kenrick street (sidewalks), Athol street,
Everett street, Holton street. North Harvard street. Lake
Shore road, Eatonia street, West Sorrento street.
Work Done by Contract in 1957
Item
Quantity
Earth excavation ....
60,799 cubic yards
Rock excavation ....
3,251 cubic yards
Bank gravel
57,527 tons
Crushed stone for edgestone
2,816 tons
Base removed ....
9,773 square yards
Pavement removed
51,712 square yards
Straight edgestone
32,388 lineal feet
Circular edgestone
7,825 lineal feet
Corners
1,154 each
Edgestone reset or relocated
62,823 lineal feet
Edgestone hauled to City yard .
7,300 lineal feet
Macadam base ....
41,013 tons
OA asphalt
229,558 gallons
Table
Showing Length and j
Length in Miles.
Sheet
Aepbalt.
tAsphalt
Concrete.
tOranite
Block.
Wood
Block.
Plank
Bridges.
Brick.
S." "
Year 1956 Report
227 . 57
30.46
337.44
45 17
26.36
3.53
0.15
0.02
0.35
0,05
0,50
0,07
19.77
2.64
Januahv 1, 1958.
49.02
4,31
2.80
11.61
40.14
34.48
.53.85
20.52
7.87
32.12
7.59
23.52
20.57
37,49
95.91
82.01
33.49
28 90
8 39
4.72
2.96
4,91
2,32
0.02
0.48
0.29
O.OII
0,06
0,06
0,00
0,09
0,02
0.02
0,03
0,17
0,02
0,02
0 01
2,87
0,74
1,39
0.32
4.13
2.27
5.17
0,78
0,64
South Boston
West Roxhury
0.03
0.04
0.04
0 08
0 03
Total
Percent
224.66
30-05
301.66
48.37
24,09
3.22
0.15
0.02
0.35
0.05
0.22
0.03
18.31
2.45
-In the above table the
bdivided substantially c
tOf this amount 0.02 iiiilea or 185 square yards is eobbli
square yards is granite block paving on concrete base.
§0f this amount 0.00 miles or 435 square yards if Blorn
II Of this amount 99.01 miles or 1,603.711 square yards i
Area tn Square Yards.
idam.
Gravel.
Not
Graded.
Totals.
Sheet
Aspljalt.
t.^aphalt
Concrete.
tGranite
Block.
Wood
Block.
Plank
Bridges.
Brick.
§Concrete.
II Macadam.
Gravel.
Not
Graded.
Totals.
!4 22
16,63
9.96
1.33
0.77
0.10
747.09 1
100,00
4..573.537
31.62
6,647.373
45.96
611.832
4.23
2.474
0.02
9,244
0 06
8,795
0.06
407,513
2.82
2.003.957
13 85
171.205
1.18
28.317
0,20
14.404.247
100.00
2,46
5.22
7.59
6.21
0.30
0 03
0.22
0.11
0 40
0,55
1.27
0,23
2,54
0 01
0,04
0,50
0,00
0.00
0.03
0.20
95.48
22.70
38.62
44.62
95.31
156.74
176.18
65.76
52.61
1,095.722
84,404
61,764
245,327
823,683
608,002
1,018,646
4,54,207
134,825
733.055
206.362
536,648
431,284
704,089
1,759,809
1,547,329
648,420
553,799
164.747
105,674
60,572
134,984
30.334
3,098
10,157
22,881
45
278
1,503
21
3,258
1,098
355
892
3.069
321
1,055
1,188
145
93.001
13.395
47,177
18,780
63,041
32.729
83,059
22,131
10.086
37,302
71.866
167.283
102,874
154.959
381.727
511,313
100.928
200.134
6.087
407
3.785
1.230
7.312
8.326
21.257
3,544
40,611
41
812
15.754
4.000
1.737
50
4.500
2.137.179
484.810
878.717
952,207
23.47
33.29
10, .37
12,37
338
983
985
1,231
442
2,798,674
3,194,966
1,319,392
944,443
11.79
14.95
5.65
0.76
0.78
0.10
747.66
100.00
4,526,640
31,23
7,120.795
49.13
532,492
3,68
2,140
0.01
9,244
0.06
5,778
0.04
383.999
2.65
1.794.440
12,37
92,565
0,04
26,927
0.19
14,495,023
100.00
Total Public Streets 747.66 Miles.
indarj* lines between the districts as they existed when
i miles or 356,848
lexed to Boston. Territory
nnexed from Brooklir
53.311 square yards
icluded in City Proper.
tOf this amount 60.63 miles or 1,153.311 square yards is bituUthic; and 2.26
or 36,998 square yards is Topeka; and 0.06 miles or 920 square yards is Filbertine
0.03 miles or 595 square yards is Carey Elasute Asphalt Plank; and 0.06 miles c
square vards is Johns-Manville Asphalt Plank; and 0.09 miles or 2.224 square yards i
Asphalt Block; and 1.61 miles or 50,590 square yards is Tar Concrete.
} or 61,291 square yards public streets in charge of Park Department included in this table; 15.90 miles or 533,120 square yards
eluded in tliis table. In addition to this table there are 2.41 miles or 11,740 squa
; yards of accepted footwn
Public Works Department
47
Concrete base
2,526 cubic yards
Concrete backing up sidewalks .
18 cubic yards
Bituminous concrete base (roadway)
54,770 tons
Bituminous concrete top (roadway) .
38,179 tons
Bituminous concrete base (sidewalk)
4,032 tons
Bituminous concrete top (sidewalk) .
3,797 tons
Sheet asphalt
6,559 tons
Artificial stone sidewalks
1,027,529 square feet
Artificial stone driveways .
95,337 square feet
Loam spaces
4,515 square yards
Loam back of sidewalks
1,462 cubic yards
Covers reset
4,331 each
Catch basins or manholes rebuilt
133 each
Catch basins or drop inlets built
70 each
Sign posts set or reset ....
450 each
Parking meters reset ....
524 each
Stone bounds
154 each
Bituminous concrete pavement .
501,196 square yards
Sheet asphalt pavement
81,698 square yards
Yearly Report of Work Done by Department
Forces for 1957
Brick sidewalks, laid and relaid .
Gravel sidewalks, relaid
Artificial stone sidewalks, laid (new)
Artificial stone sidewalks, relaid (old)
Bituminous concrete sidewalks .
Artificial stone sidewalks, patched
with black top
Edgestone reset (old) ....
Macadam roadway patched
Macadam roadway resurfaced .
Asphalt or bituminous concrete road-
way patched
Asphalt or bituminous concrete road-
way resurfaced
Street cleaning
Snow removal
9,789 square yards
1,631 square yards
18,295 square feet
143,377 square feet
20,147 square yards
9,580 square feet
2,331 hnealfeet
96,228 square yards
5,330 square yards
96,339 square yards
3,267 square yards
10,559 cubic yards
45,952 cubic yards
Paving Service — 1957
Street cleaning
General highway expenditures
Sidewalk and curbing .
Snow and ice removal .
Street signs ....
$35,120 36
615,326 79
252,125 95
67,748 42
29,012 59
$999,334 11
48 City Document No. 18
HIGHWAY DIVISION
Lighting Service
Financial Statement
Total Credits for 1957 $1,609,191 06
Total Expenditures for 1957 .... 1 609 191 75
Deficit
Individual Expenditures
Street and Park Lighting (Electric) :
Boston Edison Company $1,392,808 07
Boston Gas Company, Charles-
town District . . . 64,643 43
Boston Edison (footways) . 3,160 31
Boston Gas Company, Charles-
town (footways) . . . 502 19
Boston Edison Company (sub-
stations) 17,656 10
Boston Gas Company, Charles-
town (substation) . . . 4,958 37
Street Lighting (Gas) :
Boston Gas Company . . $21,687 82
American Service Company . 40,667 44
Police Spotlights :
Boston Edison Company . $1,900 63
Boston Gas Company, Charles-
town 59 01
Construction :
Installation, removal, relocation
and modernization :
Boston Edison Company
Boston Gas Company .
James Scimone, gas post re-
moval
Emergency maintenance
Salaries :
Administrative and engineering
personnel ....
Office supplies ....
Electrical maintenance and re-
placement parts
Advertising
Travel expenses ....
Office equipment ....
Spotlight poles ....
0 69
[,483,728 47
2,355 26
$5,556 55
8,725 97
ripi,yoy D^
11,187 50
2 50
$25,472 52
$25,817 95
$353 24
$25,817 95
$353 24
$5,181 40
$24 50
$3 40
$295 37
$4,000 00
$5,181 40
$24 50
$3 40
$295 37
$4,000 00
Public Works Department
49
Following is an account of orders issued by the Light-
ing Service of the Highway Division of the Public Works
Department during the year 1957:
Mercury Vapor Lighting Projects
In 1957 orders were issued on the following listed
streets, main thoroughfares and business areas for re-
lighting with modern mercury vapor lighting:
Atlantic Avenue, Boston
Bunker Hill Street, Charlestown
Blue Hill Avenue, Dorchester
Berkeley Street, Boston
Beacon Street, Brighton
Centre Street, Roxbury
Chelsea Street, Charlestown
Centre Street, West Roxbury
Commonwealth Avenue, Brighton
Commonwealth Avenue, Brighton
Commonwealth Avenue, Boston
Canterbury Street, West Roxbury
Columbus Avenue, Roxbury
Dudley Street, Roxbury
East Broadway, South Boston
Freeport Street, Dorchester
Hunter Street, Charlestown
Hyde Park Avenue, Hyde Park
Eustis Street, Roxbury
Harrison Avenue, Roxbury
Keany Square, Boston
Maverick Square, East Boston
Maverick Square, East Boston
Massachusetts Avenue, Roxbury
Massachusetts Avenue, Boston
Massachusetts Avenue, Boston
Purchase Street, Boston
Purchase Street, Boston
Ritchie Street, Roxbury
Ruggles Street, Roxbury
Roxbury Street, Roxbury
Roxbury Street, Roxbury
Summer and L Streets, South Boston
Summer and L Streets, South Boston
Sumner Street, East Boston
Theodore Glynn Way, Roxbury
Tremont Street, Brighton .
Tremont Street, Roxbury .
Units
15 single
42 single
1 single
4 single
4 single
4 single
1 single
8 single
32 twin
55 single
2 single
8 single
7 single
17 single
20 single
7 single
1 single
39 single
2 single
2 single
1 single
6 single
5 twin
8 single
12 single
7 twin
10 single
2 twin
1 single
5 single
10 single
1 twin
15 twin
45 single
1 twin
5 single
16 single
21 single
Lumens
Each
15,000
15.000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
10,000
15,000
10,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
15,000
10,000
15,000
15,000
15,000
15,000
15,000
50
City Document No. 18
Vine Street, Charlestown
Washington Street, Boston .
Washington Street, West Roxbury
Washington Street, Roxbury
Whittier Street, Roxbury .
West Broadway, South Boston .
Warren Street, Boston
Warren Street, Roxbury
4 single
15,000
3 single
20,000
84 single
15,000
23 single
15,000
1 single
15,000
1 single
15,000
1 single
15,000
4 single
15,000
Gas Replacement Program
During the year 1957 approximately 1,700 obsolete
gas lamps were replaced with approximately 1,755 new
modern luminaries with 2,500 lumen lamps. These new
lamps, in most instances, are installed on long arms to
diminish interference with trees and to eliminate glare
from homes on residential streets.
Maintenance of Police Spotlights
The maintenance of police spotlights continued during
the year 1957. Program initiated for the installation of
additional spotlights at the locations chosen by the
Police Department.
Incandescent Lighting Projects
In 1957 orders were issued for the installation of new
and the replacement of old lighting units.
Academy Hill Road, Brighton
Brookford Street, Roxbury
Copeland Street, Roxbury
Calumet Street, Roxbury
Fisher Avenue, Roxbury
Iroquois Street, Roxbury
King Street, Dorchester
Liverpool Street, East Boston .
Leighton Road, Hyde Park
Magazine Street, Roxbury .
Newland Street, Boston
Parker Hill Avenue, Roxbury
Poplar Street, West Roxbury
Ronan Park, Dorchester
St. Theresa Avenue, West Roxbury
St. Alphonsus Street, Roxbury .
Wellesley Park, Dorchester
Binney Street, Roxbury
Units
Lumens
Each
5 single
2,500
5 single
2,500
6 single
2,500
17 single
2,500
13 single
2,500
5 single
2,500
5 single
2,500
5 single
2,500
7 single
2,500
11 single
2,500
8 single
2,500
11 single
2,500
18 single
2,500
9 single
2,500
10 single
2,500
6 single
2,500
9 single
2,500
6 single
4,000
Public Works Department
51
Harvard Street, Dorchester
Parker Hill Avenue, Roxbury
Pembroke Street, Boston
Townsend Street, Roxbury
Waltham Street, Boston
White Street, East Boston
Camden Street, Roxbury
Dwight Street, Boston
Harvard Street, Dorchester
Harrison Avenue, Roxbury
Motte Street, Boston .
Pleasant Street, Dorchester
Perkins Street, West Roxbury
Townsend Street, Roxbury .
Troy Street, Boston
Calumet Street, Roxbury
Canterbury Street, West Roxbury
Franklin Park, Dorchester .
Highland Street, Dorchester
Neptune Road, East Boston
Parker Hill Avenue, Roxbury
Savin Hill Avenue, Dorchester
Terrace Street, Roxbury
13 single
4,000
21 single
4,000
10 single
4,000
6 single
4,000
6 single
4,000
7 single
4,000
16 single
6,000
5 single
6,000
13 single
6,000
8 single
6,000
5 single
6,000
19 single
6,000
5 single
6,000
10 single
6,000
6 single
6,000
1 single
10,000
2 single
10,000
1 single
10,000
1 single
10,000
1 single
10,000
1 single
10,000
1 single
10,000
1 single
10,000
Incandescent Lamps
During 1957 incandescent lamps of 6,000 lumens each
were installed on the following streets:
Asylum street, Boston (2); Circuit street, Roxbury (1);
Claremont Park, Boston (2); Devine Way, South Boston
(1); Forest Hills street, West Roxbury (1); Garrison street,
Boston (1); Hanson street, Boston (4); Lingard street, Rox-
bury (2); Museum road, Roxbury (1); Playstead road,
Roxbury (1); Regent street, Roxbury (1); Ringgold street,
Boston (1) ; To^vn Field, Dorchester (3) ; Union Park, Boston
(2); Way street, Boston (3).
Incandescent lamps of 4,000 lumens each were installed
on the following streets:
Academy Hill road, Brighton (1); Bosworth street, Boston
(1); Brooks street. West Roxbury (4); Crossman street,
Dorchester (1); Calumet street, Roxbury (1); Circuit street,
Roxbury (3); Crown Path, Dorchester (3); Douglas street.
South Boston (1); Frawley street, Roxbury (1); Lamartine
street, Roxbury (1); Magazine street, Roxbury (1); Sachem
street, Roxbury (1); Seymour street. West Roxbury (1);
Union Park street, Boston (2); Vining street, Roxbury (1).
52 City Document No. 18
Orders were issued by the Lighting Service for the
installation of lighting units of 2,500 lumens as follows:
Alleghany street, Roxbury (4); Allston street, Dorchester
(1); Autumn street, Roxbury (3); Bartlett street, Charles-
town (1); Burton street, Roxbury (1); Belnap road, Hyde
Park (2); Barnes avenue. East Boston (1); Bragdon street,
Roxbury (1); Bayside street, Dorchester (1); B street, South
Boston (3); Cross street, Charlestown (3); Clancy road,
Dorchester (3); Chellman street, West Roxbury (2); Cordis
street, Charlestown (3); Chadwick street, Roxbury (3);
Claymount terrace, Dorchester (1); Cumston street, West
Roxbury (1); Cornwall street, West Roxbury (2); Creighton
street, West Roxbury (4); Carolina avenue. West Roxbury
(3); Dodge road, Hyde Park (2); Delle avenue, Roxbury (1);
Daly street, Dorchester (2); Draper's Lane, Boston (2);
Dunmore street, Roxbury (2) ; Everett street. West Roxbury
(2); Emmonsdale street, West Roxbury (1); Fourth street,
South Boston (3); Field street, Roxbury (1); Fremont street,
Dorchester (2); Fallon street. West Roxbury (3); Forest
Hills street. West Roxbury (1); Fabin street, Boston (2);
Frawley street, Roxbury (2) ; Green street, Charlestown (3) ;
Gore street, Roxbury (1); Glen street, Dorchester (2); Gray
street, Boston (4); Goodenough street, Brighton (2); Hazel-
mere road, West Roxbury (1); Henry street. East Boston (1);
Harleston street, Roxbury (2); Horace street. East Boston
(2); Ivanhoe street, Boston (3); Lawn street, Roxbury (1);
Maverick street. East Boston (4); Maryknoll street, Dor-
chester (2) ; Minton street, Jamaica Plain (2) ; Mystic street,
Charleston (4); Messinger street, Dorchester (1); Merola
park, Dorchester (2); M street, South Boston (3); Mission
street, Roxbury (2) ; Nevada street, Dorchester (2) ; Norfolk
avenue, Dorchester (1); Oswald street, Roxbury (1); 0 street,
South Boston (2); Page street, Dorchester (2); Paris street,
East Boston (1); Pleasant street, Charlestown (4); Rowe
street. West Roxbury (3); Renfrew street, Roxbury (1);
Rogers street. South Boston (1) ; Ringgold street, Boston (1) ;
Ruggles street, Roxbury (2); Rawson street, Dorchester (1);
South Hobart street, Brighton (1); Spaulding street, Dor-
chester (3); Standish street, Dorchester (1); Sachem street,
Roxbury (3); St. Charles street, Boston (1); Stockwell
street, Roxbury (2); Savin Hill avenue, Dorchester (1);
Soley street, Charlestown (2); Seymour street. West Rox-
bury (1); Safford street, Hyde Park (4); Tupelo road, Rox-
bury (1); Tuttle street, Dorchester (1); Taylor street,
Boston (1); Trumbull street, Boston (3); Union park, Bos-
ton (4); Wait street, Roxbury (3); Weymouth avenue.
West Roxbury (2); Windsor street, Roxbury (4); Wilming-
ton avenue, Dorchester (1); Wales street, Dorchester (2);
Warner street, Dorchester (1).
Public Works Department 53
Orders were issued by the Lighting Service during
1957 for the installation of 1,000 lumen lamps as follows:
Appian Place, East Boston (1) ; At will road, West Roxbury
(1); Armstrong street, West Roxbury (1); Arborfield road,
West Roxbury (4); Bickford street, Roxbury (1); Boswell
Lane, Charlestown (2); Bayswater street, East Boston (1);
Concord avenue, Charlestown (4); Calumet street, Roxbury
(1); Canterbury street, West Roxbury; (1) Damrell street,
South Boston (5) ; Desmond road, Dorchester (2) ; Filomena
road, West Roxbury (1); Gordon avenue, Hyde Park (1);
Gardenside street, West Roxbury (1) ; Garth road, Boston (2) ;
Heron street. West Roxbury (1); Lexington avenue, Charles-
toAvn (2); Maryknoll terrace, Dorchester (1); Meadowview
road, Hyde Park (3); Maple Street Extension, West Rox-
bury (1); Prospect park, Hyde Park (1); Stanwood street,
Dorchester (2) ; Wilmot street, West Roxbury (2) ; Wedmore
street, Dorchester (1); Willow terrace. West Roxbury (1);
Whitby terrace, Dorchester (1).
54 City Document No. 18
APPENDIX D
REPORT OF THE DIVISION ENGINEER OF
THE SANITARY DIVISION
Boston, January 2, 1958.
To the Commissioner of Public Works:
Dear Sir:
I submit herewith a statement of the activities of the
Sanitary Division of the PubUc Works Department
for the year ending December 31, 1957:
Refuse Collection and Disposal
Contracts for the collection of refuse, awarded in
March, require that all the districts of the City now be
provided with totally enclosed steel bodies on the col-
lection trucks, which is an improvement in sanitation
that has been a goal of the division for many years.
Disposal contracts for the so-called contract area,
for the first time, split the work between two con-
tractors, the DeMatteo Construction Company to
continue the scow-towing and Spectacle Island dump
operation, and the Coleman Disposal Company to
operate the Calf Pasture dump for a one-year period
from April 1, 1957 to March 31, 1958.
The total cost of refuse collection and disposal for
1957 was approximately $2,600,000, which is more
than $200,000 under the cost of the same service in
1949.
This holding the line in costs is remarkable in view
of the increase in the wage rate for collectors from $1.30
an hour in 1949 to $2.15 an hour in 1957, and the fact
that fully enclosed packer-type truck bodies are now
used in place of the open body trucks furnished pre-
viously. The resultant savings to the City were made
possible by acquiring control of the refuse dumping
sites and the institution of authentic competitive bidding
on the refuse collection and disposal contracts over the
past seven years.
\-
A.
D
c
3
■a
<K -
O »^
55
3 ^
§ B-.
\
i''
&^
„ i
r.
7Z
r.
Lt*
J
(t
Public Works Department 55
Other disposal facilities have been maintained during
the year by —
(a) Renewal of the Daggett contract for disposal of the
East Boston refuse at the Saugus dump.
(6) Continuing the sale of garbage delivered at the
Victory Road Receiving Station to a hog farmer in Sterling,
providing an income of $4,615 per year.
(c) Repairs to the roof of the Victory Road Station were
done by J. F. Shea Company at a cost of Sl,475, and the
interior steel work cleaned and painted by the C. A. Foley
Company, at a cost of $2,549.
(d) At the Gardner street dump, improvement was made
by demolition of the old Brookline Water Works structures
by Dooley Brothers, Inc., at a cost of $4,300. The excellent
dumping operation conducted at this site demonstrates the
sound judgment exercised in acquiring the ninety-seven
acres purchased by the department during the past few
years, commencing in 1951.
Street Cleaning and Snow Removal
Mechanization of the street cleaning function pro-
ceeded with the acquiring of two new mechanical pick-up
sweepers complete with cabs for the operators, and two
new front-end bucket loaders.
An appropriation of $200,000 was made for a new
sweeper garage and office building at 650 Albany street.
Borings were taken by the Carr Construction Corp.,
and preliminary architectural studies are in progress.
Construction of this building may be commenced in
1958.
The division's street cleaning force removed snow from
the streets in the down-town retail stores district follow-
ing storms in excess of two inches, which occurred during
the months of January, February and March. No snow
fell during the fall months.
The entire division was mobilized for the Spring
Clean-Up Campaign, conducted from March 25 to
April 20. At the end of this period, every section of the
city was in a clean condition, and the winter's accumula-
tion of sand in the gutters had been removed.
Incinerator Construction
Construction of the South Bay Incinerator proceeded
without delay this year. The J. F. White Contracting
Company completed driving 62,000 feet, or almost
twelve miles, of concrete-filled twelve-inch steel pipe
56 City Document No. 18
piles, averaging a depth of 160 feet below the ground sur-
face, at a cost of $419,000. A revision of the contract
with George Allen Company was made on April 24,
providing for furnishing six instead of four incinerator
furnaces and appurtenances, thereby increasing the
plant capacity from 600 tons to 900 tons per twenty-four
hours. The cost was $462,264, the same price bid by
the Allen Company sixteen months earlier, which
brought the total amount of this equipment contract to
$1,426,131. This contract was later assigned to the
Tynan Incinerator Company.
A contract for construction of the Refuse Storage Bin
was awarded on June 3 to the low bidder, Coleman
Brothers Corp., at a bid price of $423,000. Due to diffi-
cult sub-soil and high ground water conditions, the bin
was constructed in a cofferdam of steel sheeting. Work
was approximately 95 per cent completed on this con-
tract on December 31st.
The plans and specifications for the incinerator build-
ing were completed by the consulting engineers, Metcalf
& Eddy, in September, and a contract was awarded on
November 25 to the low bidder, the John Bowen Co.,
Inc., in the amount of $2,693,793. The Bowen Company
plans to commence work early in 1958, as soon as the
Coleman Brothers Corporation leaves the site, and is
expected to complete the building within twelve months.
The only remaining incinerator work not contracted
for is the steam main for transmitting steam, to be
generated by burning refuse at the incenerator, to the
Boston City Hospital. Plans and specifications for this
work will be completed early in 1958. Utilization of
the waste heat of incineration will provide a saving of
over $150,000 annually in fuel oil costs at the hospital.
Additional revenue may be derived from the sale of
surplus steam to the Boston Edison Company which
has expressed an interest in this commodity.
The undersigned was promoted to the position of Di-
vision Engineer of the Sanitary Division on August 6,
1957, to fill the vacancy caused by the death of Division
Engineer, Adolph J. Post, in February, 1956. The
Acting Division Engineer in the interim was General
Superintendent Timothy J. O'Leary.
Respectfully submitted,
John F. Flaherty, Division Engineer,
Sanitary Division, P. W. D.
CQ
Public Works Department
57
SANITARY DIVISION — 1957
Payments to Refuse Collection Contractors
District
Contractor
Monthly
Contract
Price
Total
Payments
1 South Boston.
2 East Boston.
3 Charlestown.
4 Brighton .
5 A West Roxbury.
5B Jamaica Plain .
6 A Dorchester — North.
6B Dorchester — South.
7A Elm Hill.
7B Dudley.
7C Mission Hill.
7D Roxbury.
9 South End.
9 A Back Bay.
9B Stuart.
10 North and West Ends.
11 Hyde Park.
Anthony J. Ryan, Jr.
(First 3 months) . .
(Last 9 months). . .
Milano Brothers, Inc.
Milano Brothers, Inc
(First 3 months)
Jeffries Disposal Corporation.
(Last 9 months)
Anthony J. Ryan, Inc
(First 3 months)
Frank J. Cavaliere Company, Inc.
(Last 9 months)
Frank J. Cavaliere Company, Inc.
J. J. Moore Company, Inc.
(First 3 months)
(Last 9 months)
Coleman Brothers Corporation.
(First 3 months)
(Last 9 months)
Coleman Brothers Corporation.
(First 3 months)
(Last 9 months)
William J. Banfield.
(First 3 months) .
(Last 9 months). .
United Contracting Company.
(First 3 months)
(Last 9 months)
Marinucci Brothers, Inc
(First 3 months)
Frank J. Cavaliere Company, Inc.
(Last 9 months)
L^nited Contracting Company.
(First 3 months)
James A. Freaney, Inc
(Last 9 months)
James A. Freaney, Inc.
(First 3 months) . . . .
(Last 9 months)
Dooley Brothers, Inc.
(First 3 months) . . .
(Last 9 months). . .
James A. Freaney, Inc.
(First 3 months) . . . .
(Last 9 months)
Ward General Contracting Company .
(First 3 months)
(Last 9 months)
Dooley Brothers, Inc.
(P'irst 3 montlis) . .
(Last 9 months). . .
$10,400
12,607
7,328 +
3,953
4,832
13,400
14,420
10,350 +
9,615
11,100
25,900
27,370
29,100
30,570
5,310
5,420
6,729
6,929
8,140
7,960
9,980
9,480
7,170
6,940
3,690
2,990
3,560
2,910
14,300
13,650
6,390
6,390+
Total .
$144,663
90,856
55,347
169,980
127,550
128,745
324,030
362,430
64,710
82,548
96,060
115,260
83,970
37,980
36,870
165,750
77,542
S2,164,29I
58
City Document No. 18
Payments to Refuse Disposal Contractors
Districts
Contractor
Monthly
Contract
Price
Total
Payments
3 9 9A 9B and 10
M. DeMatteo Construction Company
$39,090
30,980
2,100
$396,090
1,7A, 7B, 7C, andTD
18,900
(Last 9 months)
Total
$414,990
Payments for Rental of Dumps
Dump
Location
Contractor
Monthly
Contract
Price
Total
Payments
Dewey E. Daggett
$900
200
2,000
$10,800
Boston Gas Company
18,600
$29,400
Total Payments to Contractors for Refuse Collection and Disposal $2,608,681
Expenditures in 1957
Payments to Refuse Collection Contractors .
Payments to Refuse Disposal Contractors . .
Payroll totals were as follows:
Administrative and General
Services S55,062 88
Shops and Storehouse 201,270 40
Collection and Disposal 292,767 95
$2,164,291 00
.444,390 00
$2,608,681 00
Total Sanitary
Street Cleaning . .
Total Sanitary and Street Cleaning
$549,101 23
1,632,314 15
12,181,415 38
Overtime Payrolls were as follows:
Shops and Storehouse $4,246 46
Collection and Disposal 5,691 05
Street Cleaning 47,355 69
Total Overtime .
57,293 20
Total Payroll $2,238,708 58
Public Works Department 59
Payments on other Contracts $59,861 93
Supplies and Materials 47,652 72
Miscellaneous 4, 134 62
Grand Total $4,959,038 85
Equipment Acquired During 1957
1 Wayne Sweeper $11,650 00
1 Elgin Sweeper 12,000 00
2 Trojan Front-End Loaders 15,800 00
3 G. M. C. 3-Ton (4-yard) Dump Trucks. . . 13,500 00
Total $52,950 00
Personnel Changes in Permanent Force During the
Year 1957
Total Personnel, January 1, 1957 *616
Transfers In (from other Departments and T)'w\-
sions) 24
Reinstatements 3
Appointments 35 62
678
Deaths 9
Resignations 9
Retirements 21
Transfers Out (to other Departments and Divi-
sions) 6
Discharges 3 48
Total Personnel, January 1, 1958 .... t630
* Including 1 Military Leave of Absence,
t Total net gain of 14 employees.
60 City Document No. 18
APPENDIX E
REPORT OF THE DIVISION ENGINEER OF
THE SEWER DIVISION
Boston, January 2, 1958.
To the Commissioner of Public Works.
Dear Sir:
I submit herewith statement of the activities and ex-
penditures of the Sewer Division for the year ending
December 31, 1957.
Expenditures During 1957 — The activities of the
Sewer Division during the year consisted of advertising
for sewer construction at a contract bid price of $141,-
520.80, and the maintenance and operation of the sewer
system at a cost of $786,871.90.
Contract Work — Contract work consisted of the ex-
tension of the sewer system to provide drainage for new
buildings and street construction and to ehminate cess-
pools, the locations and cost of which are attached.
Maintenance Work — Maintenance work consisted of
the cleaning of 10,882 catch basins by contract and
1,894 by yard forces, the freeing of stopped sewers and
catch basins, and the repair of sewers, manholes, and
catch basins by the yard forces and the operation of the
pumping station and disposal works, the cost of which is
attached.
Major Accomplishments — Completion of enclosing
Section 18 of Stony Brook, Hyde Park, in a conduit from
Willow Street to Bald Knob Road, a distance of 4,678.45
linear feet. The contract was awarded to Pacella
Brothers, it was started October 3, 1955, and completed
September 28, 1957. The total and final amount paid
under the contract was $490,263.02.
Completion of the enclosing of the Canterbury
Branch of Stony Brook, West Roxbury, in a conduit
from the main line of Stony Brook Conduit to beyond
Canterbury Street, a distance of 1,321 linear feet. The
contract was awarded to Civitarese-Piatelli Corporation,
the work started November 5, 1956, and was completed
June 28, 1957. The total final payment under the con-
tract was $207,184.45.
Public Works Department 61
A contract was awarded to P. J. Riley & Co. at an
estimated cost of $20,318, to furnish and install one main
sluice gate at Calf Pasture Pumping Station. The work
will start in 1958.
The emergencj^ repair of sewers by advertised con-
tract at a total cost of $25,453.52.
The maintenance of about 1,200 miles of sewers and
surface drains, the emergency cleaning of catch basins,
the repair of broken sewers and catch basins, the answer-
ing of house drain complaints, the operation of pumping
stations and storage basins for the disposal of sewage by
division forces.
The keeping of records, the issuance of permits for and
the inspection of the construction of house drains.
Engineering, clerical and inspectional work in con-
nection with the construction of sewerage works done
by advertised contract.
Proposed Work to he Done hy Advertised Contract Dur-
ing 1958 is as Follows —
Emergency repairs of sewers, estimated cost, $30,000.
Cleaning of catch basins, estimated cost, $60,000.
Extension of sewer system to provide drainage for
new buildings and new street construction. Estimated
cost, $300,000.
The covering in of that part of open Bussej' Brook for a
distance of about 1,400 linear feet, from the Dedham
branch railroad to South street. Estimated cost,
$110,000.
The covering in that part of open Canterbury Branch
of Stony Brook from Canterbury street to Walk Hill
street, estimated cost, $130,000.
The Sewer Division Labor Force consists of the following
— 15 laborers, 1 carpenter, 30 motor equipment oper-
ators and laborers, 9 catch basin machine operators,
3 tide gate repairmen and 1 working foreman tide gate
repairman, 8 working foremen sewer cleaners, 14 sewer
cleaners, 4 bricklayers, 2 yardmen, 1 heavy motor
equipment operator, 5 sewer district foremen, and 1
main drainage foreman. This makes a total of 94 men
assigned to answering complaints, cleaning catch basins,
cleaning sewers, repairs to manholes and catch basins,
repairing broken sewers, and other related work.
Length of Sewers Built — During the fiscal 3^ear 1957
there were built by contractors and day labor 4.06 miles
of common sewers and surface drains throughout the
62 City Document No. 18
city. After deducting 0.05 miles of sewers and surface
drains, rebuilt or abandoned, the net increase for 1957
is 4.01 miles, which added to the existing 1,291.30 miles
of common sewers and surface drains and 30.93 miles of
intercepting sewers, makes a grand total of 1,326.24
miles of all sewers belonging to the City of Boston, and
under the care of the Sewer Division on January 1, 1958.
There were 218 catch basins built or rebuilt and 42
abandoned or removed during the year, making a net
gain of 176 catch basins and a grand total of 24,698
catch basins under the care of the Sewer Division on
January 1, 1958.
Permit Office Report — Entrance fees to the amount
of $14,457.70 have been deposited with the City Col-
lector for collection from estates upon which no sewer
assessments were ever paid, in accordance with Ordi-
nances of 1945, Chapter 27, Section 10.
Seven hundred and seventy-five permits have been
issued, viz.: 112 to district foremen and contractors and
663 to drain layers for repairing or laying new house
drains. Inspectors from this office have personally
inspected the work done under these drain-layers'
permits.
Two thousand and one complaints have been in-
vestigated and inspectors are instructed to report in
writing in each case.
Two thousand and sixty -four catch basin complaints
were received.
Reported in writing on 2,761 municipal liens to the
City Collector, in accordance with Chapter 60, Section
25, of the General Laws. Reported orally on about
2,200 requests for information on municipal liens.
Notices have been mailed to abutters in conformity
with the- Ordinances of 1925, Chapter 27, Section 8,
apprising them of the construction of new sewers or
repairs to old sewers.
Respectfully,
Robert P. Shea,
Division Engineer, Sewer Division.
Public Works Department
63
Summary of Sewer Construction for Twelve Months Ending
December 31, 1957.
Districts.
Built by the
City Either by
Contract or
Day Labor.
Built by
Private
Parties.
Total Lengths Built.
Linear Feel.
216.70
463.70
Linear Feet.
2,195.00
Linear Feet.
2,411.70
463.70
Jl/i7es.
0.4567
0.0878
382.00
9,019.00
1,553.87
5,497.97
308.00
964.00
438.60
372.80
690.00
9,983.00
1,992,47
5,870.77
0.1307
West Roxbury
1.8907
0.3773
Hyde Park
1.1U9
Totals
17,133.24
4,278.40
21,411.64
4.0551
Summary of Sewer Construction for Five Years Previous to
January 1, 1958.
1953
1954
1955
1956
1957
Built by city by con-
tract or day labor . . .
Built by private parties
or other city depart-
Linear Feet.
27,469.81
11,482.00
Linear Feet.
33,316.89
10,459.00
Linear Feet.
33,237.48
1,695.15
Linear Feet.
25,559.88
3,487.39
Linear Feet.
17,133.24
4.278.40
Totals
38,951.81
43,775.89
34,932.63
29,047.27
21,411.64
64
City Document No. 18
Total Length of Sewers.
Districts.
Total
Lengths
Built
During
Twelve
Months
Ending
December
31, 1957.
Lengths
Removed or
Abandoned
During
Twelve
Months
Ending
December
31, 1957.
Additional Lengths
for the
Twelve Months Ending
December 31, 1957.
Linear Feet.
2,411.70
463.70
Linear Feet.
216.70
33.60
Linear Feet.
2,195.00
430.10
Miles.
0.4157
Roxbury
0.0814
G90.00
9,983.00
1,992,47
5,870.77
690.00
9,983.00
1,992.47
5,870.77
0.1307
West Roxbury
1.8907
0.3773
Hyde Park
1.1119
Totals
21,411.64
250.30
21,161.34
4.0077
Common sewers and surface drains built previous
to January 1, 1957
Common sewers and surface drains built between
January 1 and December 31, 1957
Common sewers and surface drains built ending
December 31, 1957
City of Boston intercepting sewers connecting
with Metropolitan sewers to December 31, 1957
City of Boston main drainage intercepting sewers
to December 31, 1957
Miles.
1,291.30
4.01
1,295.31
6.81*
24.12*
Grand total of common and intercepting sewers to
December 31, 1957 ... . . . 1,326.24
Total mileage of streets containing sewerage works
to January 1, 1958 714.94
* No additional lengths built during 1957.
Public Works Department.
65
Catch Basins in Charge of Sewer Division.
Districts.
Catch Basins for Twelv
Ending December 31
E Months
, 1957.
Total for Whole City
IN Charge of Seweb
Division.
Number
Built or
Rebuilt.
Number
Abandoned
or Removed.
Net
Increase.
Previous
Report to
January 1,
1957.
Grand Total
to
January 1,
1958.
1
13
0
0
0
41
78
42
43
0
0
0
0
0
5
5
32
0
1
13
0
0
0
36
73
10
43
3,800
3,481
1,477
1,223
870
2,106
4,518
5,699
1,348
3,801
3,494
1,477
1,223
870
hton
2,142
4,591
Chester
5.709
ie Park. . . .
1,391
Totals
218
42
176
24,522
24,698
66 City Document No. 18
Calf Pasture Pumping Station, 1957
Total millions of gallons pumped (annually) . . . 39,996,699,000
Average cost per million gallons (annually) ... $5 08
Costs
Annual Total Operating Costs, 1957
Labor $106,777 69
Edison Power 83,894 29
Fuel Oil No. 5 5,348 92
Fuel Oil No. 2 107 92
Bottled Gas Ill 10
Supplies 3,101 28
Miscellaneous Oil 219 02
Service Orders 3,575 04
2. Contractual Services
21. Communications $3,139 64
22. Light, heat and power . ... 90,073 80
26. Repairs and maintenance of buildings
and structures 104,102 63
27. Repairs and servicing of equipment . 3,979 45
28. Transportation of persons . . . 1,189 39
29. Miscellaneous contractual services . 808 25
3. Supplies and Materials
32. Food supplies $14 85
33. Heating supplies and materials . . 7,798 95
34. Household supplies and materials . . 408 88
35. Medical, dental and hospital supplies
and materials 29 15
36. Office supplies and materials . . 2,281 30
39. Miscellaneous supplies and materials . 7,697 27
Total $203,135 26
SEWER DIVISION
Budget Expenditures, 1957
1. Personal Services
10. Permanent employees .... $550,019 61
11. Temporary employees .... 1,153 75
12. Overtime 12,671 31
$563,844 67
203,293 16
18,230 40
4. Current Charges and Obligations
49. Miscellaneous current charges and obli-
gations $1,155 22 1,155 22
5. Equipment
5 9. Miscellaneous equipment . . . $348 45 348 45
Grand total $786,871 90
C»C<3
p-
■c
a
©>
o
' — '
Cei
I.
O
z
:^
O
aj
H
bi)
o
u
0)
(1>
H
t/3
t/3
z
o
o
•-1 C5 CO
(N 00 (M
M 00 O
Ol 0> N 00
^; z
a o
o o
p4 [>H
QJ U U
►3 tf § S
(67)
l-H t^
■^ e a
(n c3 ^ 50 5^ 5 ^
2.S
OOON "
^■5
aj o flj o "^ .2
a a &J3^'
aaa Jj ii o
■= * » e S-S
OiOO ^ " "
,-1 .-H ,-. TJH lO N
tr.
O ID O
.&.£■•*
"a'a § a a
oo " oo '^ •=!
^rtco rtrH-( [in
a'a 6 --
Lh
d o
a
f^-g
o
CJ
[^
si a
<«J
■>o
o
O
Ml
u
o
6 IB
p a
5-^
^o
c a
c3 o
S O g
o >-.
WS
(68)
o u
.2 o
■"pa
•S^ :5
te (3 a to
S 2S S 6
a aa3
» * S B £3
O O :- t-
rt rt CO fe Mh
■a d
a a a'O
£2 S
8J cj 3 B
S'W
■a-o-og
,13 a)
^ ca 2
rt 3 m m
3 3 3 oJ K 5
4) 0) O-^
na^j3
c. a a ax j3
•a-agi^
aaaa g S
» * Eg
* ' « » S g
— -Ht,05
Ol .-H rl -H CC t^
oo
oooo
oo
oooo
ooo
OOiOCO
-lO
OOt-Oi ^
C-lt^
^COr-^-H
^ 'Z
•§ >
tf w
►H o
o
~
p^
>
^a
m
o
Z
a o
T3
O
3
^
PQ CO
o
O
U
&
S
S^
tH
U
»f;
si
T3
f,C)
S
^
o
T)
T3
a
03
o; <D
OJ
L.
M i3
o
^ •
o
^
C3
is ii
H-*
""S
2 o
.tJ
U, (U
'/I
0)
Eh
.SoP
SE
& s
O w
S S »
t-t c ^
3 O C
01 611
JU « c3
^ "g >-.
^ >- CD
■> c o
O
(69)
t^
>.
>.T3
S C
s^
m
m »S
o^
tH
c!t3
o
03
03
O
X
•r, >>
C
03 O
^ o
-oW
- o
P3
O
5^
•^ 2
03 ^
■a
c
03
Q
.k^ S3
£^
^^
P> w>
c3 a>S
t. J) o
>1
o
■^"^
a:
c
C
O
C
» .-<
a
C^l
<o
es»
O) a>
CO r»
CO
lO
CO
«o
en o
CD CO
CO
in
o>
■^
CM O
CO !>.
b-
■*
eo
o in
«»
o»
co"
00
o>
fl
a
s
a
d
.g
.s.g
.a
_>
■, >,
e
1
2
H
'S
ci
S2
>,
s
03
o3
"c
"H
-o
TfTSTS-OTS
T3T)
"c
T3
c
o
v
0)
0)
o
V
a)
O O
c
a>
J3
C3
C
1
fl
c
M
«
^
c
■J
03
.2
£
M
1
1
£
a
> >>
•5 b
3
s
C3
C3 GO
3
3
CO
3
3
g
05
C3
£ 3 3
(n (0 (n
03
Oi
o3
e
oj 3'S n CO
^ ^ ce a> 03
>
•«S
U
o
^
!&
"o
■c
V
a>
a>
a>
a)
O
XI
O 0) d>
0
ja
ft ftft'-'jS^
j:
1, Q,
aj3^
A
0,^0.0. a o.j5ja
ag.&
ja
o
O ftS
"
o S.
a
c3
c
■p.'a'S.'3."a
c3
o
■ft"3.'p. o
c6
03
-1 aaoSi^
ri
e
s*
(
S o
c^
a
_c
%
t
*
«
»
s
05
'S
& % K
a
E
CM
o
of
c
<= » .s a o
£
S
§2
§
(N 00 CO-* 00
t^-*coc^i —1
CO
r-lr-lCM
§
CM
£
_^
OON
oin
ooooooin
OOOO
*i OOO
j3
OTfCO
OOO
o —
CO
00
CM 00^
o
m -^ino
c
cs
c- ...
i.sl
c
o
c-i ■*•<}<
ino
iOCDt»00OC^
i-T-i cor~
O COCOOS
t
o
c^
o
OJC^
CO CM
05'>*CMeo
asoo-*
« Pn
c
o
rtcoco
<N
rt TJI
CO CM
1— 1 r- 1
CM
o '''"
>-^
^
■z.
•z
d
6 °
c.
r
13
d
o
1
c
O
u
c
c
c
c
a:
o
m
c
c
c
.
§ 1
CO 03
5
§
H
c
c
c
C
c
c
3
Ci
o
a
03
O
o
•-5
O
a
oi
(§
•-5
"3
03
I
a
1
V-
"a
c
(1
■4^
g
1
o
C5
"a
1
•1
1
5C
> to
t^
t^
t>
t^
cc
t^
u-
lO
in
in
in
ir
in
O
5 05
en
Oi
o
CJS
o
en
•B
'
0)
•<j
•^
lO
oT
<x
U5
in
CO
c-
*-<
CM
CM
'3
S
>
■^ a
M
>
c
.
^
>. ^
<
Z
I
s
►^
<
t£
■> CO
t~
t-
CD
CC
t^
ir
lO
m
in
IT
>o
in
in
o
C5
o
OS
o-
o
O:
o>
T3
tt)
c
di
■*
^
cc
tC
■*
-tJ
(^
r)
(N
»H
CO
J
W
0.
>,
0)
6
c
§■
03 Id
3
^
3
Q
§
S
A)
O
§1
■« (I.
111
03 y-s
OT «3 t^
3
C
1
o
•a
-go
-si
o3 S
M
o o
1
is
o
•<
O
o
►-5
O
i
o 0)
n
So
■5 m
Ph
Q
(3
P3
T3
c
K«jo
o
o
Q
O
T3
C
03 u tH
O O 03
> (U
o o
«g
K
> S.
— o
0)
eg
^'
o
o
III
"3 CD 03 CJ
M _
fl CI
oi— '
03 -ana
-3
>
3
1
§
H
O
O
m
03
CQ
O
(70)
5 « S e
S t; S C g-S
(O DO QD rt o W
" - '^ ° C, ,
,-■ rt rt ,2; ■-< «
o. Q. a ^ CrS
■a'3.'S. o ''
,s.g
tH " "
(D 4) (U-a Or]
a ao- |;,-a o
'a'a'ft o § s
» 5 » .S s "
.s
■3 c
»iz 0
n
3 03
» (U
^
aaja
aa
a
too
a
0
%^t .s
O ^ c3 «i w
« tn o lU oj
<y OJ 0) O -^
a a & § §
3 S
o s:>^
.a
S 3 03 O 3 «( ~
Qo 00 u oo 00 V ^
QJ <U 4) O) (U O "^
_a D,_a a a-flja
'a'a a a ft
a
a u
ot^t^o
^" O lO o o
0100
OOCiOiO
o a
oj
PQ
C^l r-l --I
« 03 S
a:S
Q) O
^T3
ft •
.a I
3 X
oH
III "^i
S OQ
gin'-'
•^ oj O
e3-<
_. a
p! iS
tf w
.a ft
0 C3 QJ
> 2^
(71)
'E aj S
0.-S 0
n,^"
>>
*^ a
3
-0 .—
XI
oU 2
0
n
sQ^
Fl^
I 00 M^
§ gc^s •
aw 3 « * «
■^ ^% >.>>
^ '1 O i-hH
C -S T-^ 3 1^
> m i? 3 « i-
g ca t« O 3 03
S £?° S a «>
£ 3-g =3 £
^M ^> <"g
"5 S C ..T3 is
5 " "^ P ^ 03
"Pi
IP t. O (i. >.s «>
2 a,
a
o
O
o"© 2
egg
* B^
Oi 0) 0)
S fe s
lu a> «
_D. a c.
"a'a'a
h ,^rH-„
</3
•a E
03O
■5 «
03 3
fflO
fl-^.J. ® A
,
00
,
3 £t3J=-2
.So .5°
coo
0
■g^'i>.ci^
M
0 -4^ 0 .^
^-> >^
bO
a^ a c
C 3
-d
rmerly Bur
thampton
and such
which ma
issioner of
am a
stree
om a
a poi
0 0
aa
03 C3
3
0)
<u
^ >' i 0
'■"'S >> r^ 5<
SB
0 ^
ti 03
^■°
OS'S
Si a)
ynn Way, fo
8, from Sou
setts avenue
ons, if any,
y the Coram
<u
rop
Ber
ster
xbu
pla
W
a
T3
03
t, City P
hwest of
southwe
enue, Ro
of Opera
>
v
dore A. 01
eet, Ward
Massachu
nal locati
ignated b
Works.
a
B
ppleton stree
100 feet sout
point .50 feet
untington av
80 feet east
feet northeas
JJ
0
3
Oi 3
03 t-
0 —
8-^0.2 £.2
03
5
J3
H
H
< ffi
w
'Z.
(72)
Public Works Department 73
APPENDIX F.
REPORT OF THE
SURVEY DIVISION
Boston, January 2, 1958.
To the Commissioner of Public Works:
Dear Sir:
I respectfully submit the following report of the
activities of the Survey Division for the year ending
December 31, 1957.
This Division performs engineering services for other
divisions of the Public Works Department and other
city departments, boards and commissions. It also
performs administrative and engineering duties required
by the Public Improvement Commission for its operation.
The principal engineering duties include:
(a) the making of plans, surveys, estimates and reports
relating to the laying out, widening, construction and design
of public highways:
(b) the taking of easements for sewerage works;
(c) staking out lines and grades for the construction of
highways, sewerage, etc. ;
(d) the making of property surveys of land to be acquired
by the City of Boston by eminent domain ;
(e) the making of plans and surveys of city-owned land
for purposes of sale, interdepartmental transfer or new
development ;
(/) the making of various engineering surveys and plans
required by other city departments.
For the Public Improvement Commission, the ad-
ministrative functions include the processing of petitions,
arranging public hearings, preparing estimates and
orders relating to land damages and street and sewer
betterments, preparing orders for the laying out of
streets and the construction of streets and sewers,
preparing orders for eminent domain land takings,
preparing orders for the granting of permits for use
of public highways, erection of poles, etc., and the
maintenance of all records in the charge of the Public
Improvement Commission.
74 City Document No. 18
Personnel — On December 31, 1957, there were
thirty-five permanent and five temporary employees as
listed below in this Division.
Name Title
Kenneth L. Benkart Sr. Engineering Aide
Charles E. Brewer Assistant Civil Engineer
Arthur J. Brickley Assistant Civil Engineer
Oliver C. Brown Sr. Engineering Aide
George F. Buckley Jr. Civil Engineer
John A. Bulliner Sr. Engineering Aide
Carmine D. Buono Sr. Engineering Aide (Prov.)
Joyce E. Campbell Sr. Clerk & Stenographer
Michael J. Corrao Assistant Executive Secretary
George J. Creney. Photostat Operator
John J. Curley, Jr Jr. Civil Engineer
Saverio A. DeFronzo Sr. Clerk and Typist
Salvatore C. Diliberto Assistant Civil Engineer
William F. Duggan Principal Clerk and Stenog-
rapher
Harry M. Fletcher Assistant Civil Engineer
Thomas 0. Flood Senior Clerk
George H. Gilboy Sr. Engineering Aide
John F. Gilmore, Jr Assistant Civil Engineer
James W. Haley Chief Engineer
Bernard Harrington Jr. Engineering Aide (Prov.)
Leo B. Hughes Sr. Engineering Aide
Roland A. Hull Assistant Civil Engineer
Angelo J. laluna Assistant Civil Engineer
James J. Kelly Sr. Engineering Aide (Prov.)
Frank S. Lane Jr. Civil Engineer
Walter R. Luby Principal Civil Engineer
Thomas McCusker Executive Secretary
Francis McHugh Jr. Civil Engineer
Robert P. Mehegan Head Clerk
Frederick J. Milliken, Jr Sr. Engineering Aide
A. Albert Minichiello Assistant Civil Engineer
Philip A. Moynahan Sr. Engineering Aide
John Murphy Sr. Engineering Aide (Prov.)
William P. Norris Principal Duplicating Ma-
chine Operator
Thomas E. Rafferty Assistant Civil Engineer
Rose K. Reynolds Clerk-Stenographer
Albert J. Rodriguez Jr. Civil Engineer
John J. Ryan Principal Civil Engineer
Robert J. Sheehan Sr. Engineering Aide (Prov.)
Redmond L. Walsh Head Photostat Operator
The personnel allowance of this division has been
dropping steadily from 73 in 1935 to 57 in 1945 to 45
Public Works Department
75
this year. Of the 45 positions, 10 are now permanent
vacancies because of our inability to secure quaUfied
personnel through Civil Service in competition with
higher salaries offered by the State and other pubHc and
private agencies. Obviously, this situation which has
continued now for over 10 years, is a serious handicap
to the division.
Division Expenditures, January 1, 1957 to December 31, 1957,
Inclusive.
Survey
Budget
Highway
Loan
Sewer
Loan
Personnel
Pensions
Contractual Services
Supplies and Materials
Current Charges and Obligations .
Equipment
$103,300.00
$65,924.95
21,281.28
—
2,300.00
9,025.31
7,000.00
31.50
—
76,872.21
500.00
—
$134,381.28
$151,853.97
$907.95
Totals.
$907.95
Total Expenditures $287,143.20
During the period covered by this report, the Survey
Division completed one hundred eighteen (118) surveys
and plans for the improving of existing highways, laying
out of new ones and discontinuances, totaling 11.95
miles. Eleven (11) surveys and plans for .57 miles of
sewerage easements were also made. Sixteen (16)
surveys and plans of city-owned land or land to be
taken for municipal purposes were also made.
Field engineering work included the staking out of
eighty (80) streets for the Paving Service of the Highway
Division, twenty-seven (27) for the Sewer Division,
and miscellaneous services for other City departments.
Regular routine work included the resurveying of street
lines for private engineers wherever existing records
were inadequate or obsolete, marking Hues and grades
for private construction abutting public streets, exam-
ining land court plans for the Law Department, prepar-
ing land damage reports for the PubHc Improvement
Commission.
Listed below are the major engineering surveys and
plans completed during the period of this report.
76 City Document No. 18
For the Public Improvement Commission:
Fifty-four (54) surveys and plans were made for the
laying out of 4.73 miles of public highways, as follows:
District Length
in Feet
Boston Proper
Kilby place 68
Brighton
Argus place 240
Baldwin place 210
Nottingham Path 210
Dorchester
Belvoir road 215
Blair road 200
Brandon avenue 746
Cassnet street 160
Constitution road 231
Crossman street 553
Dania street 755
Hallet street 1,075
Hebron street 395
Jamestown terrace 134
Messinger street 250
Monticello avenue 3,145
Montpelier road 870
Orlando street 800
Savannah avenue 247
Viking street 185
Willow court 740
Hyde Park
Belnap road 365
Daniel court 180
Dietz court 170
Dodge road 480
Farwell avenue 225
Joan road 750
Kristin court 155
Leighton road 1,350
Radcliffe road 77
Rosemont street 278
Susanna court 200
Westminster street 1,193
Wharton court 180
Woodland road 840
Public Works Department
77
Roxbury
Alleghany street .
Darling street
Parker Hill terrace
Alley No. 822
South Bay avenue
Topeka street
Waymount street .
West Roxbury
Celia road
Claron street .
Glencliff road
Grandview street
Hackensack court
Hautevale street
June street
Leland road .
Paulman Circle
Pleasantdale road
Rivermoor street
Willow terrace
692
65
180
100
930
567
110
206
290
580
450
340
209
430
630
270
800
565
232
Twenty-two (22) surveys and plans were made for the
widening and relocation of 1.68 miles of public highways
as follows:
District
Boston Proper
Clinton street
Troy street
Charlestown
Lowney Way
Park street
Dorchester
Hill Top street
Rosselerin road
Willow court .
Hyde Park
Brainard street
Radcliffe road
River street .
Roxbury
Darling street
Sachem street
St. Botolph street
Seaver street .
Norfolk avenue
Length
in Feet
220
94
157
38
32
415
800
20
48
43
72
128
20
3,665
143
78
City Document No. 18
South Boston
D street
30
West Roxhury
Anawan avenue 24
Baker street 2,641
Firth road 21
Joyce Kilmer road 24
South street 319
Woodard road 36
Eighteen (18) surveys and plans were made for the
discontinuance of .54 miles of public highways as
follows :
District
Boston Proper
Blackstone street
Cambridge street
Central street
Fulton street .
Genesee street
John street
Lovering street
Public Alley No.
Pubhc Alley No.
Oneida street .
Oswego street
Warren Bridge
Brighton
Ryder Hill road
Hyde Park
Chapel road .
Saiford street
702
703
Length
in Feet
122
43
214
65
80
146
291
205
192
60
60
783
14
87
238
48
Roxhury
Public Alley No. 821
West Roxhury
Brook Farm road 30
Maple street 190
Twenty-four (24) surveys and plans were made for the
alteration (specific repair) of 5.00 miles of pubHc high-
ways as follows:
District Length
in Feet
Boston Proper
Berkeley street 265
Clarendon street 245
Public Works Department 79
Columbus avenue at Stuart street .... 55
Commonwealth avenue at St. Mary's street . . 37
Massachusetts avenue between Columbus and
Huntington 990
Washington street at Hayward place ... 35
Brighton
Beacon street at Ayr road 75
Beacon street at Cleveland Circle .... 747
Commonwealth avenue 5,090
Dorchester and Roxhury
Blue Hill avenue 2,349
Roxhury
Columbus avenue — Washington street to Walnut
avenue
Columbus avenue at Ruggles street
Elm Hill avenue at Cra^vford street
Ruggles street at Columbus avenue
Seaver street
1,205
35
98
12
4,065
South Boston
East Broadway 2,714
Dorchester avenue — West Fourth street to Andrew
Square 4,250
West Roxhury
Baker street — Spring street to Veterans of Foreign
Wars Parkway 4,402
Brewer street at Thomas street 13
Brewer street at Eliot street 15
Centre street at South Huntington avenue . . 14
Hagar street at Thomas street 10
Hager street at Eliot street 15
Walworth street 27
Washington street at South 10
Four (4) survej^s and plans were made for the revision
of grade of .33 miles of public highways as follows :
District Length
in Feet
Bost&n Proper
Castle street 530
Hyde Park
Safford street 350
West Roxhury
Burley street 280
Brook Farm road 731
80 City Document No. 18
Two (2) surveys and plans were made for the taking
of eminent domain of 26,129 square feet of land for
municipal purposes, as follows:
Location Area Department
700 Tremont street, Boston Proper . . . 2,881 Fire
42-56 Worcester street, Boston Proper . 23,248 School
Eleven (11) surveys and plans were made for the tak-
ing of .57 miles of easements for sewerage purposes as
follows :
District Length
in Feet
Hyde Park
Arborfield road 925
Beech street 318
Mansur street 960
Millstone road (private land) 30
West street (private land) 100
Roxbury
Kenway terrace 12
West Roxbury
Centre street (private land at Dedham Line)
Dow road
Grandview street
Hackensack court
Maria Lane
70
36
455
89
15
For the Public Works Department (Central Office),
a plan was prepared for exchange of land at Gardner
street, West Roxbury. Study plans were made of the
following: Parker Hill avenue. Sachem street, Way-
mount street, Roxbury; land bounded by Southampton,
Bradston streets and Southeast Expressway; Metro-
politan avenue and railroad location in Hyde Park.
For the Public Works Department (Highway Divi-
sion), eighty (80) highways were staked out for con-
struction.
For the PubHc Works Department (Sewer Division),
eighty-three (83) catch basins were staked out. Also,
thirty-four (34) drainage surveys and reports were made.
For the Pubhc Works Department (Sanitary Divi-
sion), locations of test piles at incinerator site, South
Bay avenue, Roxbury, were checked periodically. Top-
ographical plan of land adjacent to incinerator site was
made.
Public Works Department 81
For the Real Property Department, surveys and plans
were made of city lands on Battery street, Boston
Proper; Sumner street, East Boston; Lewis street. East
Boston; Eastern avenue, Boston Proper; Medford street,
Charlestown, and Ritchie street, Roxbury. A plan was
prepared showing the relocation of Fitzgerald Express-
way at Fort Hill square.
For the Law Department, a survey was made for
encroachment on Harrison avenue at East Newton
street. Accident plans were made for the following loca-
tions: Arhngton street, Boston Proper at Chandler
street; Boylston street, Boston Proper at Hemenway
street; 1245 Columbus avenue, Roxbury and North Ben-
net street, Boston Proper at North Bennet Street place.
Lines were marked at 58 L street, South Boston, Ballard
street and Custer street. West Roxbury. A survey and
plan was made of boundary line between Boston and
Winthrop. A plan of sewer easement in Wave avenue,
Dorchester, was prepared.
For the Building Department, property Unes were
checked at 10 Grove street. West Roxbury, 38 Prospect
street and 1 Mt. Vernon street, Charlestown; 41-51
Hanover street, Boston Proper. A topographical plan
of area adjacent to Lodgehill road and Beech street,
Hyde Park, was made.
For the Hospital Department, a plan was made
showing the location of inflammables at City Hospital.
For the Fire Department, a survey and taking plan
and topographical and utihties plan was made of Tre-
mont street and West Concord street, Boston Proper.
For the School Buildings Department, a survey and
plan of land on Worcester street, Boston Proper, for
addition to Dwight School. Plans were prepared of
Dorchester High School lot and EngHsh High School lot.
A sketch plan was prepared of Greenwood School on
Metropolitan avenue, Hyde Park. Line and grade
was furnished for new school on Warren avenue, Boston
Proper.
Stone Bounds — In accordance with a policy estab-
hshed in 1950, stone bounds were set and drilled on the
following newly constructed streets:
Number of
Street District Bounds
Ackley place West Roxbury 3
Ayles road Hyde Park 3
Barna road Dorchester 1
82 City Document No. 18
Number of
Street District Bounds
Brockton street Dorchester 3
Brush Hill terrace Hyde Park 4
Edwardson street Hyde Park 3
Ellard road Hyde Park 2
Farwell avenue Hyde Park 1
Frazer street Hyde Park 2
Granada park West Iloxbury 2
Harrow street Dorchester 4
Howard place Dorchester 4
Lewiston street Hyde Park 3
Maple street West Roxbury 3
Meadowview road Hyde Park 6
Millstone road Hyde Park 2
New Bedford street Hyde Park 1
Range road Dorchester 3
Rocky Nook terrace Dorchester 3
Tanglewood road Dorchester 1
Alvarado avenue Hyde Park 1
Ansonia road West Roxbury 7
Hillis road Hyde Park , 1
Reynold road Hyde Park 1
Solaris road Hyde Park 1
Vallaro road Hyde Park 2
Engineering Information Services
The preservation of street line locations is one of the
most important responsibilities of this division. As
brought out in recent annual reports, we have been
losing ground steadily in maintaining adequate records
of these street line locations, due primarily to lack of
personnel. To establish an adequate program for this
work, it will be necessary to increase the engineering
force by employing twelve additional competent engi-
neering aides at a cost of S45,000 per year. With these
additional men, we could establish four new survey
parties to work exclusively on street line surveys.
Atlases
Second only to the street line problem is our need
for new up-to-date atlases or maps of the city. The
ages of our best atlases are as follows:
Hyde Park 46 years
South Boston 39 years
East Boston-Charlestown . . . .36 years
West Roxbury 34 years
Brighton 33 years
Public Works Department 83
Roxbury 27 years
Dorchester 25 years
Boston Proper 20 years
The need for new atlases is obvious, not only for our
needs, but all city departments and many other public
and private agencies.
"Boston's Streets" (Street Book)
On April 30, 1957, this division issued for the first
time a Street Book "Supplement" showing all changes
in street records occurring since the 1955 edition of the
Street Book. The supplement was well received and it
is proposed that each year a new supplement be issued
with a new street book edition being published only once
every five or six years.
Preparation of the following private ways for public
travel, as provided for in Chapter 393, Acts of 1906, as
amended, was approved by the PubHc Improvement
Commission to be done under the general supervision
of engineers of this division.
Altacrest road, West Roxbury
Arborfield road. West Roxbury and Hyde Park
Beech street, Hyde Park, between Sherrin street and
Asheville road
Corcoran road, Dorchester
Desmond road, Dorchester
Dow road. West Roxbury
Gould street. West Roxbury, from Belle avenue to North-
dale road
Itasca street, Dorchester, northeast and southwest of
Messinger street
Kiernan road, West Roxbury
Lodgehill road, Hyde Park, from Beech street to Goff
street
Manchester street, Dorchester, extension to Temple
street
Mansur street, West Roxbury and Hyde Park
Merola park, JDorchester
Messinger street, Dorchester, from Colorado street to
Savannah avenue
Northdale road, West Roxbury
Surreyhill road, West Roxbury
Reproduction Work
On January 1, 1957, a new poHcy requiring signed
requisitions for all reproduction work was put into
84 City Document No. 18
effect. Also, a charge to the pubHc of $1 per copy was
begun in accordance with a revised schedule of fees
established by the City Council, December 1, 1957.
As expected, the total amount of work fell off con-
siderably. One exception was ozalid printing which
increased slightly. This increase was caused by one
particular job, the South Bay Avenue Incinerator, of
which over 8,000 prints were made.
The new fee schedule brought an income of $623 to
this division from the sale of copies of its plans and
records. Other departments and divisions likewise
received substantial new revenues from the sale of
copies produced by our reproduction service.
Following is the report of reproduction work of the
division for the year 1957.
Department PHSTS BPS OZS APS
Administrative Services 1,288 226
Assessing 770 2,094
Auditing 546
Building Department 906 20 934
City Clerk 708 98
City Council 2,104 352
Civil Defense 574 116
Compensation Review Board 286
Finance Commission 142
Fire Department 466 107
Health Department 598 39
Registry Division 920
Boston Housing Authority 16 16
Law Department 616 186
Mayor's Office 3,244 212
Park Department 62
Penal Institutions 16 12
Planning Board 966 633
Public Works:
Central Office 662 28
Bridge Division 286 559
Highway Division 624 97 1,969 126
Sanitary Division 148 8,054
Sewer Division 926 116 455
Survey Division 3,130 1,926 6,929 22
Water Division 338 7 453
Public Works (Commonwealth of
Massachusetts) 237
Real Property 1,432 26 1,050
Registry (Court House) 114
Retirement Board 72
School Buildings 230 87
School Committee 52
Traffic Commission 234 95 752
Treasurer's Office 126
Collecting Division 22
Veterans Services 418 12
White Fund 508 35
Election Department 16
Public Buildings 52 66
Public Works Lighting Service 64 384
Public Works Department 85
Totals:
Photostats '. 23,668
Ozalids 26,179
Blueprinting 2,287
Autopositives 148
52,282
Photographic Service — In carrying out a policy intro-
duced in 1956, we have established a Photographic
Service for the Public Works Department and other
city departments. As a part of this program we now
take photographs of the location of all new highway
layouts and proposed improvements, and lands taken
for municipal purposes. The following is a summary
of this work during the year 1957:
Photo- 4x5 8 X 10
Public Works Department graphs Prints Prints
Sanitary Division 342 342 32
Survey Division 380 380 20
Sewer Division 150 150
Bridge Division 178 176 56
Highway Division 140 140
Water Division 40 40
Automotive Division 18 18
Central Office 52 56
Public Improvement Commission 160 160
Totals 1,460 1,108 462
Land Damages — -During 1957, 67 land damage reports
recommending awards totaling $24,500 were submitted
to the Public Improvement Commission.
Assessments — During the period reported on, esti-
mates of benefit for assessment purposes were prepared
amounting to $241,503.01. These estimates are in-
cluded in orders for street and sewer improvements.
Also, final assessments were prepared amounting to
$286,936.04.
Respectfully submitted,
James W. Haley,
Chief Engineer.
86
City Document No. 18
APPENDIX G.
REPORT OF DIVISION ENGINEER OF THE
WATER DIVISION
Boston, January 2, 1958.
To the Commissioner of Public Works:
Dear Sir:
I respectfully submit the following report of the
activities of the Water Division, operations and expen-
ditures for the fiscal year ending December 31, 1957.
During the year a total of 22,282.6 hnear feet, or
4.22 miles, of main pipe was laid or relaid, varjdng in
size from 4 inches to 24 inches and 720 appHcations
were received for installation of new service pipes,
enlarged service pipes and fire pipes, etc., into new or
remodeled buildings.
There were 13 petitions received for the extension of
water mains. The particular streets in which the above
work was performed are shown on the accompanying
tables.
The districts in which the main pipe was laid and
relaid are as follows:
District
Laid
Linear Feet
Relaid
Linear Feet
City Proper .
East Boston .
South Boston
Dorchester
Hyde Park .
West Roxbury
7,271.0
80.0
323.0
3,809.0
6,604.7
2,326.0
1,656.4
0
0
0
0
212.0
Under the provisions of Chapter 4 of the Ordinances
of 1952, which deals with capital improvements, the
W^ater Division submitted a capital improvement pro-
gram, which program was not followed to any great
extent due to the fact that all available funds were
needed to extend water mains to provide water into
residential areas.
Public Works Department 87
Engineering Office
The office force assisted the pubUc in ascertaining
official information in relation to water mains and
service pipe locations, making studies and estimates
on new mains and services and other assistance relating
to water matters. The record plans, pressure charts
and other official records were brought up to date.
The office drew up plans and contracts for laying new
and relaying old mains, supervised construction, and
had supervision of snow removal in contract areas 4
and 10.
The engineering office assisted in design and super-
vision of construction of water mains and appurtenances
for the following major projects; their status being
as follows:
Central Artery.
Fort Hill Square to South street, completed.
South street to Dover street, one third complete.
Southeast Expressway
Dover street to Boston street, plans completed.
Boston street to Columbia road, 90 per cent complete.
Savin Hill Section, 90 per cent complete.
William T. Morrissey Boulevard to beyond Neponset
avenue, complete.
Soldiers Field Road
Eliot Bridge to Cambridge street, completed.
Reinforced Faulkner Hospital Area, completed by connec-
tion to new 36-inch M.D.C.H.H.S. Mam at Weld
street and West Roxbury Parkway.
Reinforced Hyde Park with 16-inch main on Providence
street, completed.
New York Street Area, completed.
Temporary pump installation during summer months to
raise pressure in Stony Brook Village, Hyde Park.
Codman Hill Section of Dorchester reinforced by M.D.C.
installation of 12-inch Det. Meter Gallivan Boulevard
at Morton street.
Projects Under Study
(o) Reinforce southern section of West Roxbury.
(6) Reinforce Stony Brook section of Hyde Park with
H.H.S.
88 City Document No. 18
(c) Reinforce Low Service, Roxbury and South Boston, by
cleaning and lining 30-inch-24-inch main Roxbury Crossing
to Andrew Square.
(d) Storage building for water works supplies in Albany
Street Yard.
Hydrants
There were 24 new hydrants established, 136 hy-
drants changed and 35 hydrants abandoned, a decrease
of 11 hydrants.
Summation
System relaid .35 miles, extended 3.87 miles, aban-
doned 2.95 miles, 24 new hydrants estabhshed and 35
hydrants abandoned; an increase of .92 miles and a
decrease of 11 hydrants.
The Distribution Branch
The Distribution Branch consisting of the main
yard at 710 Albany street (with a small subyard in
Charlestown) and three district yards are responsible
for the repair and maintenance of main pipes, service
and fire pipes, hydrants, gates, and providing emergency
and general service to the public. The main yard main-
tains emergency crews around the clock for any
water service that might be required in any section of
the city.
The main yard and three district yards were assisted
by three contracting firms, one in each yard with one
contractor having two districts. The contractual
work consisted of excavation and backfilling to allow
the water division employees to repair leaks, lay or
relay water services, change hydrants and repair or
replace defective water appurtenances. This contrac-
tual work was performed in a satisfactory manner and
proved its value by giving service to the public.
During the year the main yard was cleaned up on the
northern side by removing the old sheds, placing an
asphalt pavement over the area and erecting a mod-
ern chain link fence from Albany street to the channel.
District Yards
The three district yard forces (West Roxbury, Dor-
chester and Brighton) were utilized in general assistance
to the public repairing leaks, installing new services,
meter changes, hydrant changes, off and on calls, etc.
A new combination garage and shelter of prefab steel
Public Works Department 89
was constructed in the Dorchester District Yard, re-
placing the old wooden stable and garage, and chain
link fence was installed on Gibson street, replacing
the old wooden fence.
The Machine Shop
The machine shop and plumbing shop handled all
drilling of services in the main yard and assisted in case
of emergency in the district yards. The machine shop
continues to machine and assemble all new gates up to
and including 12 inches, tapping gates up to 6 inches.
Gates 16 inches and larger are now purchased under
contract made under Specifications of New York Pat-
tern, M. D. C. Type. They machine and assemble all
hydrants, repair defective hydrants, repair in the ground
if possible defective gates and rebuild gates both cor-
poration, tapping and high pressure. Along with this
work they, both the plumbing and machine shop, are
called on to assist other branches of the Public Works
Department in many special jobs.
The Meter Branch
The meter shop handled a total of 17,981 meters,
divided as follows:
Meters applied on new services .... 626
Meters discontinued 1,683
Meters Changed Out 5,562
Meters Changed In 5,440
Meters tested in shop 6,809
Meters repaired in service 570
Meters repaired in shop 753
Meters reset 733
Meters junked 1,367
Total 23,543
Business Office
This office performs all the work related to the
processing of bills to property owners for water used
and the maintenance of water meters.
These operations include receiving applications for new
services and fire pipes; reading 95,000 meters quar-
terly; computing and preparing 382,000 bills amounting
to $6,223,229.77; keeping account of paid and unpaid
bills; testing, repairing, installing, and removing water
meters and receiving complaints from the water-
consuming public.
90
City Document No. 18
It is unfortunate that for many years the surplus of
the Water Division was not allowed to accumulate a
reserve fund which would have been available when
water receipts failed to meet expenditures.
1957
Main pipe petitions received 13
Domestic service applications 659
Fire pipe applications 61
Special meter tests 34
Hydrant permits issued 13
Repair deposits received 84
Miscellaneous deposits 30
APPROPRIATIONS, EXPENDITURES, AND REVENUE
Budget appropriation, 1957
Amount expended
52,465,718 00
2,472,526 00
Amount of money collected from all sources during the
year 1957
Amount expended from all sources
Surplus
R6,274,964 54
6,177,357 09
$97,607 46
The Metropohtan assessment for 1957 amounted to
$3,328,696.68 at the rate of $80 per milUon gallons, an
increase of $37,901.24 over the assessment of 1956,
based on the $80 per milhon gallon rate.
Total amount billed for 1957 .... $6,232,598 76
Total amount collected for 1957 bills, as of
December 31, 1957 $4,825,825 43
Total amount abated for 1957 bills, as of
December 31, 1957 $21,124 18
Total amount collected in 1957 on bills ren-
dered prior to 1957 $822,762 68
By chapter 487, Acts of 1954, entitled "An Act Rela-
tive to Liens for Water Rates and Charges" effective
January 1, 1955, the law was changed so that hens for
water rates take effect by operation of law without
the necessity of recording a hen statement at the Regis-
try of Deeds.
The issuance of statements of outstanding water bills
to the consumers at the end of the year has been con-
tinued as a courtesy to the customer.
Respectfully submitted,
D. M. Sullivan,
Division Engineer.
Public Works Department
91
Balances from 1956
Water Service Receipts
Water Service .
Receipts
Water Rates and Services
Tax Titles, Water .
Expenditures
Pensions and Annuities .
Water Division
Refunds
Metropolitan Water Assessment
Collecting — • Water .
Automotive — Water
Water Service 1957
$271,990 01
245,811 46
5,223,229 77
51,734 77
$225,333 58
2,472,526 21
2,275 90
3,328,696 68
137,282 00
125,191 00
Transfer of 1956 Surplus
Carried forward to 1958 Water Division .
Surplus
1957
Summary of Water Division
Collections and Expenditures
Total Amount Collected
Expenditures
Pensions and Annuities . . . $225,333 58
Water Division (Budget) . . 2,472,526 21
Refunds 2,275 90
Collecting — Water . . . 137,282 00
Automotive — Water . . . 125,191 00
M.D.C. Water Assessment
Less cash forwarded 1956 to 1957
Plus cash forwarded 1957 to 1958
$2,962,608 69
3,328,696 68
$6,291,305 37
245,811 46
$6,045,493 91
131,863 18
$517,801 47
6,274,964 54
56,792,766 01
6,291,305 37
$501,460 64
271,990 01
$229,470 63
131,863 18
$97,607 45
j,274,964 54
6,177,357 09
Surplus
$97,607 45
92 City Document No. 18
Water Division 1957
Construction Account
Extension of mains (from revenue)
Cost of construction Dec. 31, 1957 $25,439,829 36
Cost of construction Dec. 31, 1956 25,357,313 14
Increase in plant cost during 1957 .... $82,516 22
Cost of existing worlcs Dec. 31, 1957
Pipe yards and buildings . . $84,332 16
Distribution system .... 25,439,829 36
Hyde Park water works . . . 175,000 00
$25,699,161 52
High pressure 2,448,340 64
$28,147,502 16
Water Statistics for the Fiscal Year Ending
December 31, 1957
Mains
Kind of pipe : cast iron, wrought iron, steel.
Size, 2-inch to 48-inch.
Extended miles — 3.87.
Size enlarged miles, 0.35.
Total miles now in use, 1,030.8.
Public hydrants added, 24.
Public hydrants now in use, 12,543.
Stop gates added, 45.
Stop gates now in use, 16,553.
Number of blowoffs, 857.
Range of pressure on mains, 30 to 90 pounds.
Services
Kind of pipe and size :
5/8 inch to 2 inches in diameter of lead or copper.
4 inches and 6 inches in diameter of cast iron.
Shutting Off and Turning On Water in 1957
Number of shut-offs for repairs 5,089
Number of premises turned on after repairs 4,475
Number of shut-offs for vacancy 768
Number of premises turned on for occupancy .... 187
Number of premises shut off for nonpayment of water rates . 13
Number of premises turned on again after being shut off for non-
payment 2
Number of premises shut off on account of waste .... 37
Number of premises turned on again after being shut off for
waste 0
Number of new service pipes turned on for the first time . . 360
Total number of times water was shut off or turned on . . 10,931
Public Works Department
93
Table No. 1. Statement of Work Done During the Year 1957.
Make.
<
a
o
u .
Q§
— a
Meters
Changed.
a
il
.2
b >
a
So.
5
a
•3
1
Out.
In.
600
14
1,353
281
20
25
1
2
4,584
837
46
74
1
7.
1
5,300
135
5,738
925
46
74
7
1
461
104
653
90
731
2
367
797
72
121
1
9
19,787
3,185
184
294
5
25
1
3
Nash
o
10
1
5
13
2
3
1
8
41
Trident
6
1
1
1
3
Pitt
10
10
Totals
626
1,683
5,562
5,440
6,809
570
753
733
1,367
23,543
94 City Document No. 18
Table No. 2. Meters in Service, December 31, 1957.
Diameter in Inches.
Make.
%
V4.
1
IVi
2
3
4
6
8
10
Total.
Hersey
Watch Dog
71,069
7,878
474
1,196
48
47
5,044
261
7
6
2,464
393
4
1,421
757
8
6
1,012
410
3
4
349
228
425
66
123
37
18
81,962
9,993
King
496
2
1,214
48
47
1
1
4
1
....
2
8
Nash
8
3
10
1
16
23
1
1
7
9
5
1
14
16
2
56
Trident
1
2
1
33
3
1
3
1
4
Total
80,727
5,321
2,861
2,206
1,450
620
510
129
38
18
93,880
Diameter in Inches
Total
Make
%
M
1
IV2
2
3
4
6
8
10
No
Size
2,377
42
177
3
60
25
20
82
29
165
17
66
4
26
4
7
4
1
2,692
City of Boston, Connec-
1
10
428
Total
2,419
180
85
102
194
83
30
11
5
1
10
3,120
Public Works Department 95
Table No. 3. Meters in Shop, December 31, 1957.
Diameter in Inches.
Totall
Make.
Vs
%
1 1>^
2
3
4
6
8
10
New
390
390
Hersey H. C. T
1
1
Hersey Detector
Watch Dog
Total
390
1
391
Old
Hersey Disc
170
10
5
20
18
10
8
7
1
4
5
6
1
252
Hersey Detector
12
Hersey H. C. T
1
2
Total
170
10
5
20
18
11
16
9
6
1
266
Table No. 4. Meters Repaired in Shop in 1957.
Make.
Diameter in Inches.
Total.
Vs
H
1
IH
2
3
4
6
Hersey Disc
321
129
57
78
54
1
7
1
4
1
642
Hersey H.C.T
11
Hersey Detector
Watch Dog
52
32
4
2
90
Hersey F. M
Arctic
5
2
1
8
Pitt
Trident
1
1
2
Total
321
129
57
135
88
13
9
1
753
Note: Approximately 1,400 meters are awaiting examination to determine whether they are repairable
or not.
96 City Document Xo. 18
Table No. 5. Meters Repaired and Rebuilt at Factory in 1957.
Make.
Diameter in Inches.
ToUl.
404
404
Total
404
404
Table No. 5A. Meters Purchased New in 1957.
Diameter in Inches.
Make.
1
1
1
U
2
3
4
6
Total.
2.440
100
50
60
4.5
2,695
23
Hereey H. C. T
10
10
3
Total
2,440
100
50
60
45
10
10
3
2,718
Table No. 6. Meters Reset in 1957.
Make.
Diameter in Inches.
ToUl.
1
J
1
li
2
3
4
Hersey Disc
663
2
42
17
25
3
1
751
Watch Dog
2
Total
665
42
17
25
3
1
753
Public Works Department 97
Table No. 7A. Meters Changed in 1957. Meters Taken Out.
Make
Diameter in Inches
H
H
1
IH
2
3
4
6
8
10
Total
ersey
3,829
637
45
73
1
7
393
38
160
54
93
57
. . 1
65
36
15
11
16
4
8
2
3
4,584
837
'atch Dog
ing
46
''orthington
1
74
merican
J
sderal
7
rctic
4
3
1
1
2
10
rident
1
rown
1
1
marling
1
1
Total
4,592
431
214
155
105
28
23
9
2
3
5,562
Table No. 7B. Meters Changed in 1957. Meters Put In.
Make
Diameter in Inches
Total
H
?4
1
IH
2
3
4
6
8
10
Jrsey
4,506
3
291
1
190
5
142
85
2
103
33
3
29
5
32
3
5
1
1
5,300
135
atch Dog
ctic
5
Total
4,509
292
195
229
139
34
35
5
1
1
5,440
98 City Document No. 18
Table No. 8. Meters Repaired in Service in 1957.
.M
Make.
•3
3
1
a
'3
s
ai
O
1
01
a
a
'3
_2
.s
a
■ft
a
a
"a
c3
t
3
Q
M
O
^
P3
W
Pi
H
171
226
28
12
2
22
461
Watch Dog
36
62
4
2
104
2
1
3
1
1
1
1
Total
209
290
32
12
5
22
570
Table No. 9. Meters Applied in 1957.
Diameter in Inches.
Total
Make.
f
i
1
li
2
3
4
6
Hersey
486
10
22
30
6
26
6
2
3
8
1
8
1
1
591
Watch Dog
14
2
1
1
2
3
10
Total
486
11
23
36
37
11
12
1
617
Meters applied on old service 9
Meters applied on new service 607
Connection pieces applied on new services 10
Total 626
Public Works Department
99
Table No. 10. Meters Discontinued in 1957.
Make.
Diameter in Inches.
"* m 3
a
p
O
a
o
Vs
H
1
iy2
2
3
4
6
8
10
c3
Hersey
Watch Dog
1,211
166
26
30
1
65
6
80
27
17
8
1
12
6
3
10
3
1
2
1
1
232
35
1
1,017
170
29
136
20
3
2,780
449
57
Worthington
1
34
1
1
2
1
4
7
7
1
1
Trident
1
1
1
1
2
Total
1,441
71
107
26
19
15
5
3
1
1
268
1,218
161
3,336
100 City Document Xo. IS
Table No. 11. Reason for Meter Change in Year 1957.
Makj:.
J
1
1
o
Q
tc
e
"E
9
O
u
i
'E
c
c
J
a
c.
Q
is
S
2
S
s
1
a
o
s
ca
u
O
O
o
1
1
£
Hersey
1.961
42S
22
45
1
3
3
1
1
1
96
22
1
924
159
12
15
S3
11
27
6
62
1
37
1
35
3
77
10
1
1
41
1
215
34
2
3 55S
Watch Dog
676
King-
40
Wortldngton
1
1
65
1
Federal
4
7
Arctic
2
5
Trident
1
Crown
1
Neptune . . .
1
Total
2,466
119
1,114
93
33
64
39
3S
89
44
253
4,355
Table No. 12. Meters Junked in 1957.
Make
Diameter in Inches
H
H
1
m
2
3
4
6
Total
Hersey
352
712
71
121
1
9
4
43
3
40
1
2
2
3
I
1
1
367
VTatcIi Dog
797
Kintr
72
121
ATnerip.<iTi
1
Federal
9
0
Trident
0
Crown
0
Nash
0
Arctic
0
Total
1,266
47
44
4
3
1
1
1
1,367
Note — The number of meters lost in sennce in 1957 amounts to 308.
CS
ei
r«
u
i«
Q
©^
•/I
Ji
«.
u
<^
O
^
4>
_0
g
£i
it
3
I1»
a
Q
>>
^
Xi
i>
•a
s
o
es
f/1
«s
u
r
O
a.
O
0)
>
■a
«
n
>
■a
>*>
o
u
~
o
^
X)
O
B
!«
3
o
z:
■^
■o
'■J
jU
o
es
c
j;
</)
O
it
CJ
u
>
■a
u
o
CS
c/)
2.
u
1>
u
o
-w
C3
^
be
c
-J
M
C
o
o
-r <ffl r» ■?
I XI ;■» -
< -f c. c c
OS
CO o«
3 t~ 0> 1
00
■V n >n cc ■--
CO f
0 CO •■-
- T
^
•*
lO LO 00 c
1
'O
»
0 •-
; X X 1
03
»>."
<o
^
1
t-
CI*
*
5S
o
M
i^
c
~r
'
-•
C5
H
-^'
,_
cc
^-
~~Vj
r»
■6
co_
-r
CO ^ Ci
rr
~ao -
< 0-.
o
0
»<»
oi_
01
-^
9
r^ c
fl
-r
^«
t-
o
(O —
•r
CO
0
t>*
t-
o
^
o
CO
^
I^
,_t
w c
2B
"-)■
CO
f -r
c
c
CO
-r
o
o
• 0
c
x_
0
o
«)
co'
t-'
co'
o
^4
t^
t^ iT
CO <r
-r
tri
t»
<o
~~^ ir
S5
GO
o>
O oi —
t~
S
>
Ci
C5
o
=•» CO
<j
x_
OC
^"
•^"
X
CO
^
If
CO
■)-
CO
-
""
^
o —
O ?I
•-0
"T
—
f—
■^
!>•
•r c
'i
«
t~
^
o
o
1.0
5--
L^
S5
^
T
cs
^-
•r
-r
1<
t*
CO ■.'
c
■c
CO
0 *-•■
0 II
X
T
X
0 0 0 0 11
'^
S)
^ X
c-
"?
co_
l>.
N
-r
lO
f
«3
-1"
ni
CO
-
'^
■M
•^ n
«o r'
,«
0
CO
c;
—
I.*"
t- -5> II
t^
w c
t- r-
uO
C-. c
t' UO II
«
-t
t^ -
X
X
-J"
t^ —
^
1^'
•.0
c
0"
X
'^
«
CO
,^
4 '^
r-
t-
uO
CO
c
c
C
0
r» ir
LO X
c
r- L-
ir
-r
e
O
co
CI
'^l
r«
t
X
0
0"
CI
O
:c ^
r~ O
c
r~.
*-o
~x ■.-
t-
o
t^ OC
CO X
t^
t- X
CO
-r
M
c-
ec
M
X
X
'O
O CO
CO
0
lO
c
CO
CO
o ^
CO
0
0
CO
©
ft
^-
CI
•-^
f^
h^
00
tC
X
—
»-0
CO
CO CO
SS
CO CO
-e
CI
CI
"i
o"
CO
0
£2.
Ci
•n o
to
Cl
"T?
c
'O
o
o
>-o
•V
C5
^'
^
-T O
u-
^
•^
uO
t-0
o>
M
""
•V
o
0"
uO
o o
i-O
~5 0
o
^
o
0
-0
as
o
0
■T
LO
co"
0
u
0
•^ .■
^ 0
a u
0 T
J3
0 ?
•3 ;
t>.
I^
>-o
0
t 1
g
1
o .
10
10
a
? 2
0
0;
0;
•■*
^
II
c
c
X
s
s
e
:2 :
2, ■
£ :
T3 •
1
m
e
§
s
•0
a
0
C
i
a
0
a
1
a
d
■3
•0
1
c
s
■i
IS
s=
0
1 1
a ^
c
c
_c
c
a
0
i
1
5g
"3
>
"5
fc
00 C
>
d
Cf
"«
is
o
a
OS
GO
■3
a M
jst^ a
d
>
te
£
a.
c
C
(^
_0
m5
2
=5
u
s
t
«,
>
0
"SI'S
1
u
1
!s
c
^
^
|q
O
<
2;
^
■<
£
^ re *^
^
<■
^
Ci
c;
.J
-I
"^
"^
II
•3-0
;^x
o o
$■51
a a
a"M
(101)
102
City Document No. 18
TABLE NO. 11.
Total Number of Hydrants in System, December 31, 1957.
^
S
1
0
1
o
1
1
Hydrants
►^
fi;
>,
•Sn
Ph
a
Oh
2
w
e
c
ej
•S2
^
p
to
&
c
o
o
o
1
PQ
O
T3
1-5
O
0
J3
o
1
3
Public, December 31. 1956
451
241
2,109
2,074
6,677
2
5
91
7
11,657
Private, December 31. 1956
33
5
29
126
17
13
56
4
111
394
1
123
124
14
29
80
12
135
Total Public, December 31, 1957.
438
241
1,980
1,994
6,787
2
5
91
7
11,646
Total Private, December 31, 1957
33
5
29
126
17
13
56
4
111
394
Total hydrants in service, December 31, 1956
Total hydrants added during 1957
Total hydrants abandoned during 1957
Total hydrants in service, December 31, 1957
High pressure fire hydrants in service, 1957
Total hydrants (all kinds) in service, December 31, 1957
12,051
124
135
12,040
503
12,543
^
CS
""
^
d
o
z
-u
c
u
a>
J
h
CO
a>
<
1-
a
(U
0^
H^
o<^
5 -5 g o ->,
5 s i fe -^
5 fQ (§ O
« m o o 03
-H to <N
00 00 CO
05 00 —1 IN
O O 00 M
C-) CO ;o 00
m ffi
00 00 -< 00 00 00 00
^ ^ ^ ^ ^ ^ ^
1:0 CO fM C^ O Tjf 00
a
t
!. *3
(103)
.
c
>
'e3
%
o
<4-i
T.
O
c
*35
CO
c
<
aj
h-
X
w
o
O
S
U
-«^
(3
o
M
M
o
ft
a
_C
t-,
" &
§ t
^
^
^
^
c
&
&
^
^
^
&
c
&
^
-n
0-
P-
a
ft.
ft.
a
ft.
ft.
ft.
ft.
o
a
ft.
c
C
c
P
P
P
P
P
P
P
P
^
p
P
^^
c
<■
fa
^
J3
S
OS
t*
OS
rt
cc
oi
OS
rt
tf
=y
C!
0!
^
p:
S
S
%
%
§
%
%
§
%
§
§
O
§
S
00
50
t^
m^
CO
r_,
<^ M
>o
CO
g^
li
CO
00
o
M
S^
?>
CI
.&o
Tf
f^M
o
o
c
'5
o
>
^
^
^
^
^
^
&:
^
^
^
p:
§
&:
^
11
o
PLi
eu
(^
Ah
ftn
ftn
Ph
Pt,
P^
Oh
ftn
ftn
Ph
CO
P
P
P
P
P
3
o
P
P
P
U
P
P
o
P
P
«&
C3
OS
d
i
i
c
1
03
i
1
a
iM"
1*
s
§
S
§
%
§
§
S
§
<5
§
%
s
§
o
o
O
o
O
o
o
o
o
o
O
O
O
O
o
O
o
J3^
o
o
lo
o
o
o
o
o
N
o
00
o
O
CO
r~
C)
00
c
t~-
or
IN
c
T(
C
c
•<J
c:
«^l
or
o
O!
o
Oi
c<
M
C>)
•*
O)
a
»-<
M
CO
c^
■t"
CO)
,_,
,_«
<Utl-l
kJ--
^^
00
M
to
IN
Tf
to
M
N
to
M
o
00
o
(M
00
o
CO
(n a>
—I
'^
'-'
'^
-<
— 1
"
—■
"<
CI
N^
^"^
h
H
Cd
K
H
CO
a
^
f
to
,^
.^
c:
.^
.(j
.^
^
a
is
a;
a;
s
^
>
ca
>
0!
■£
>,
o
z
^
i
1
a
'a
a
a
1
03
a/
a
03
j2
J3
01
s
s
£
I
B
O
2;
3
3
3
W
<;
<
<
u
U
U
ftn
ftn
Hh
ft<
M
CG
w
pa
pa
0
«!
^
—
1^
r^
(^
W)
"^
f^
(~5
1^
i~5
i~)
1^
fO
"5
«
r»
t>
(104)
^
^
^
pj
oj
Ph
ft,
ft.
ft.
^
0
Q
Q
Q
o
>
d
Ol
a)
S
§
S
S
W
m m VI
oa "8 -a
- S c Ji;
=a o o
> pa tf >
p4 Is d w
u o o
.^ o
tf o P^
o
rm
_
r^
1^
^
oq
^
o
rt
■*
■M
r^
^
r^
r-.
o
N
O
00
02
t^
c^
O
CO
o
CD
05
Tfl
CJ
o
CO
•V
«3
'-'
o
t^
1^
Of)
CD
o
CO
Oi
or
(^
■*
^
no
t^
N-
CO
CO
■*
^
CO
05
CO
-T<
CO
t^
or
Of)
lO
t^
r^
CO
M
CO
•— *
o
Oi
CO
00
C^I
03
"»<
5D
C^l
t~
00
rj
o
c<
CO
CO
in
IN
IM
C-l
CO
CO
O
CO
Ol
C-l
o
N
to
CO
^
CO
<M
„
lO
CO
•91
o
<M
^^
o
(-1
o
Ol
lO
(M
o
-^
•^
•*
Ol
o
05
t^
Ol
o
CO
05
•o
^
■*
Of)
CO
O
•*
lO
CO
05
r^
•o
lO
IN
lO
CO
a
CO
o
t^
•o
S
t^
o
CO
CO
o
LO
Of)
t-
o
o
o
«
■*
*-•
o
00
Ol
■<)<
OS
r-l
CI
<N
CO
CO
en
^ ^ ^
ft, Ph ft,
O Q Q
Ol CO M
— c to CM
-, ,-. f, 00 lO 1-1
C-. CO — o
ioo!iN'00)Cicocri
00 O O CI 00
CO CO CO 00 lO 00
o CI 00
CO 00 -H
rt CM rt .-I
§ s
O CI C) CD '-< -< lO
00 C5 t^ i-^ t- "^ "^
CO CO lO CO lO 00 CO
•>*< — I 00 o
lO h- O -*
CO ^ rt «
CD -H -H
CO -H CI
CI CO CO
xsoxoooooooooooooooocooooo
o s 5
i^ -S -e
(S s
CO w E-1 !>
r>> 00 00 90 90 00 00
000090000000009000
(105)
a.
6 '^
Z c
w ^
-J <
CO <*.
< o
H c
_o
*!«
1^
2
1
o
O
J. Capone & Son, Inc.
Z & S Construction Co.
J. Freaney Co
J. Capone & Son, Inc.
J. Capone & Son, Inc.
"S -g
go
IN M O X5 -H CO
>0 O 0> O <N 05
Tt< 03 "O 00 --I --I
lO C) OS M 00 0>
os_ •* -fl*^ iq o n
(N (N r^ (N -H
IN
IN
2
(N
00
N O O O ^ O
00 O O O IN >o
«0 ■<}< lO C<3 O C3
T»< 00 "O to -^ -H
O ■* 00 -^ IN (N
IN -<■ -<"
to
00
00
§
oo"
O CO O 1(5 O CO
t^ O O o o ■*
t>. lO o >o >0 00
O ■* 'i' t^ CO t^
OS OS to O 00 --I
CO
CO
00
co"
CO
J5 ^
o o o o o o
Tt< CO to CO o t^
OS O ■* — 1 Tf to
M CO <N ■* CO
o
0, S
IN 00 to 00 00 00
Ed
H
to
o
c
a;
u
a
3
C
n
C
u
o
a
i2
i
.0
B
_C
c
a
X
g
.2
"s
■d
J3
•e
o
2:
OS
CI
<
e
O
S
©
(106)
Public Works Department 107
APPENDIX H.
REPORT OF THE
PUBLIC IMPROVEMENT COMMISSION
Boston, January 2, 1958.
Hon. John B. Hynes,
Mayor of Boston.
Through the Commissioner of Public Works.
Dear Mr. Mayor:
In accordance with the provisions of section 24,
chapter 3 of the Revised City Ordinances of 1947, the
following report of the Public Improvement Commis-
sion for the year ending December 31, 1957, is respect-
fully submitted.
The Public Improvement Commission was established
May 1, 1954, by the provisions of section 57, chapter 2
of the 1954 Ordinances. This Commission, consisting
of the Commissioner of Public Works, the Commissioner
of Real Property, and the Chairman of the Boston
Traffic Commission, was assigned all of the powers
and duties of the former Board of Street Commissioners,
except :
(a) Those relating to the storage and sale of inflammables,
filling stations, and parking lots which were transferred
to the Committee on Licenses in the Public Safety
Commission ;
(6) Those relating to the planting and removal of trees in
public ways, the use of public ways for any temporary
obstruction in, under, or over the same, the use of
public ways for the storage and sale of merchandise,
and the designating of coasting streets, which were
transferred to the Commissioner of Public Works; and
(c) Those relating to the abatement of taxes which were
transferred to the Real Property Department.
Functions of the Board of Street Commissioners
transferred to this Commission include the authority
to lay out, widen, relocate, alter, discontinue, or rename
public highways, and to order the making of specific
repairs therein; to order the construction of sanitary
sewers and storm drains; to take land by eminent
108 City Document No. 18
domain for municipal purposes (except housing and
off-street parking) ; to permit the opening of private
ways for public travel; to levy assessments for street,
sidewalk, and sewer betterments; and to issue permits
for the location of wire-carrying poles, conduits, pipes,
tracks, and similar uses of the public ways.
STREET PROGRAM
During the period covered by this report, eighty-three
(83) highway improvements, including the laying out of
thirty-nine (39) new highways, the widening and reloca-
tion of seventeen (17) public ways, and the making of
specific repairs in twenty-seven (27) existing streets,
were ordered by the Public Improvement Commission.
Of particular interest in these groups are the following
projects:
The improvement of Commonwealth avenue, Brighton, from
Brighton avenue to Warren avenue, at an estimated cost of
$270,000. With the volume of traffic on this main artery into
Boston from the west greatly increased since the opening of the
Massachusetts Turnpike, this Board has ordered the recon-
struction of a particularly dangerous section between Brighton
avenue and Warren avenue with the new construction to
include a four-lane divided highway for through traffic and the
service roads on either side altered to allow much additional
parking area at the local business districts.
The improvement of Blue Hill avenue, Seaver street, Colum-
bus avenue, from Columbia road to Egleston square, at an
estimated cost of $250,000. In 1956 we began at Mattapan
square on the Milton boundary line ordering major improve-
ments, most of which are now constructed, of Blue Hill avenue
to Columbia road. In our current year, we have continued the
improvement of this major route into the heart of the city
from the south by ordering the construction of a wide divided
highway throughout the length of Seaver street, using the
abandoned street car reservation for a new road.
The improvement of East Broadway, South Boston, from
West Broadway to L street, at an estimated cost of $105,000.
This improvement, consisting of the reduction in width of
existing sidewalks, will widen the newly reconstructed road so
as to allow ten feet additional for highway travel.
The improvement of Massachusetts avenue, Boston Proper,
from Columbus avenue to Huntington avenue, by installing a
highway divisional island at an estimated cost of $13,000.
The improvement of Cleveland Circle, Brighton, at an esti-
mated cost of $50,000, by removing the existing circular
traffic island and installing channelizing islands which will
eliminate the rotary traffic movement and permit a well-
controlled traffic intersection.
Public Works Department 109
The improvement of Baker street, West Roxbury, at an
estimated cost of $100,000, will include the widening of the
existing roadway to thirty feet throughout most of the length
with an additional widening being made at the proposed site
of the Central Catholic High School at the corner of Gardner
street. Baker street is one of the principal thoroughfares
across West Roxbury from the Newton boundary line to
Dedham.
The following streets were ordered laid out as Public
Ways during 1957:
Alleghany street, Roxbury, from Parker street approxi-
mately 692 feet northwesterly. Length, 690 feet; estimated
cost, $18,431; estimated benefit, $5,261.75.
Asheville road, Hyde Park, from Deforest street approxi-
mately 477 feet easterly. Length, 477 feet; estimated cost,
$12,105; estimated benefit, $5,111.26.
Belnap road, Hyde Park, from Eastmont road to Leighton
road. Length, 341 feet; estimated cost, $11,375; estimated
benefit, $3,784.
Celia road. West Roxbury, from Bellevue street approxi-
mately 210 feet northeasterly. Length, 210 feet; estimated
cost, $6,323; estimated benefit, $3,252.
Claron street. West Roxbury, between Beech street and
Hautevale street. Length, 291 feet; estimated cost, $9,311;
estimated benefit, $4,330.
Coffey street, Dorchester, from Newhall street approxi-
mately 375 feet easterly. Length, 279 feet; estimated cost,
$9,249; estimated benefit, $5,239.
Daniel court, Hyde Park, from Dietz road approximately
180 feet easterly. Length, 180 feet; estimated cost, $5,924;
estimated benefit, $2,516.
Dietz court, Hyde Park (formerly Perry court), from Dietz
road approximately 170 feet easterly. Length, 170 feet; esti-
mated cost, $6,012; estimated benefit, $2,090.
Dodge road, Hyde Park, from Leighton road approximately
480 feet northwesterly. Length, 480 feet; estimated cost,
$16,000; estimated benefit, $6,444.50.
Farwell avenue, Hyde Park, extended from a point ap-
proximately 450 feet southeast of Summit street to Milton
avenue. Length, 385 feet; estimated cost, $13,475; estimated
benefit, $4,329.
Furbush road. West Roxbury, from La Grange street ap-
proximately 402 feet northeasterly. Length, 402 feet; esti-
mated cost, $10,386; estimated benefit, $5,387.50.
Graham terrace. West Roxbury, from Maple street ap-
proximately 200 feet southwesterly. Length, 200 feet; esti-
mated cost, $6,060; estimated benefit, $1,492.
110 City Document No. 18
Grandview street, West Roxbury, from Beech street ap-
proximately 450 feet southwesterly. Length, 450 feet; esti-
mated cost, $10,260; estimated benefit, $5,405.75.
Greenwood Circle, Hyde Park, from Greenwood avenue
approximately 270 feet southwesterly and westerly. Length,
270 feet; estimated cost, $5,878; estimated benefit, $2,650.
Hautevale street. West Roxbury, from Claron street ap-
proximately 209 feet northwesterly. Length, 209 feet; esti-
mated cost, $7,654; estimated benefit, $3,101.
Joan road, Hyde Park, from Leighton road to Dodge road.
Length, 782 feet; estimated cost, $26,075; estimated benefit,
$8,943.
June street. West Roxbury (formerly Granville street),
from Beech street approximately 430 feet southwesterly.
Length, 430 feet; estimated cost, $10,505; estimated benefit,
$5,401.25.
Kilby place, Boston Proper, from Kilby street approximately
63 feet northeasterly. Length, 63 feet; estimated cost, $1,600;
estimated benefit, none.
Kristin court, Hyde Park, from Dodge road approximately
155 feet southwesterly. Length, 155 feet; estimated cost,
$5,175; estimated benefit, $2,020.
Larch place. West Roxbury, from Hyde Park avenue ap-
proximately 185 feet westerly. Length, 185 feet; estimated
cost, $4,804; estimated benefit, $2,405.
Leighton road, Hyde Park, from the northerly end of East-
mont road to the southerly end of Eastmont road. Length,
1,300 feet; estimated cost, $43,350; estimated benefit, $16,809.
Liberty place. South Boston, from Preble street approxi-
mately 130 feet southerly. Length, 130 feet; estimated cost,
$2,449; estimated benefit, $1,150.
Melba Way, Hyde Park, between Tacoma street and Safford
street. Length, 354 feet; estimated cost, $12,668; estimated
benefit, $5,395.
Messinger street, Dorchester, between Orlando street and
Savannah avenue. Length, 270 feet; estimated cost, $6,060;
estimated benefit, $1,492.
Meyer street, West Roxbury, from Catherine street ap-
proximately 220 feet northerly. Length, 220 feet; estimated
cost, $5,043; estimated benefit, $2,600.
Newfield street. West Roxbury, between Veterans of Foreign
Wars Parkway and Fur bush road. Length, 433 feet; estimated
cost, $15,406; estimated benefit, $6,262.50.
Orlando street, Dorchester, from Messinger street approxi-
mately 130 feet southwesterly and 134 feet northeasterly.
Length, 264 feet; estimated cost, $9,290; estimated benefit,
$3,951.
Parker Hill terrace, Roxbury, from Parker Hill avenue
approximately 175 feet westerly. Length, 175 feet; estimated
cost, $4,375; estimated benefit, $1,170.
Public Woeks Department 111
Paulman Circle, West Roxbury, from Church street ap-
proximately 270 feet northeasterly. Length, 270 feet; esti-
mated cost, $9,643; estimated benefit, $4,731.
Radcliffe road, Dorchester, extended from former boundary
line between Hyde Park and Dorchester to Greenfield road.
Length, 77 feet; estimated cost, $2,200; estimated benefit, none.
Rosemont street, Dorchester, extended from approximately
430 feet northeast of Tileston street to Taunton avenue.
Length, 277 feet; estimated cost, $7,500; estimated benefit,
$2,200.
Rushmore street, Brighton, from Academy Hill road ap-
proximately 420 feet northwesterly. Length, 420 feet; esti-
mated cost, $8,704; estimated benefit, $4,108.25.
Savannah avenue, Dorchester, from a point approximately
166 feet northeast of Newcastle street to Messinger street, and
from Messinger street approximately 124 feet northeasterly.
Length, 290 feet; estimated cost, $9,564; estimated benefit,
$5,139.
Senders Court, Hyde Park, from Dietz road approximately
170 feet easterly. Length, 170 feet; estimated cost, $11,745;
estimated benefit, $6,332.50.
South Bay avenue, Roxbury, between Atkinson street and
Moore street. Length, 907 feet; estimated cost, $45,000;
estimated benefit, $6,561.
Susanna court, Hyde Park, from Dietz road approximately
200 feet northwesterly. Length, 200 feet; estimated cost,
$6,650; estimated benefit, $3,197.
Topeka street, Roxbury, between Southampton street and
South Bay avenue. (Formerly Burnham street). Length,
832 feet; estimated cost, $27,644; estimated benefit, $12,837.
Wharton court, Hyde Park, from Dietz road approximately
450 feet southeasterly and southwesterly. Length, 450 feet;
estimated cost, $6,425; estimated benefit, $2,132.
Willow terrace, West Roxbury, from Willow street ap-
proximately 240 feet southwesterly. Length, 240 feet; esti-
mated cost, $5,135; estimated benefit, $1,350.
Widened Or Relocated
Anawan avenue. West Roxbury, at the northeasterly corner
of Park street.
Baker street, West Roxbury, between Centre street and
Johnson street.
Baker street. West Roxbury, between Spring street and
Cutter road, and between Park Lane Drive and Veterans of
Foreign Wars Parkway.
Brainard street, Hyde Park, at Cleveland street.
Darling street, Roxbury, at the southeasterly corner of Calu-
met street.
Joyce Kilmer road, West Roxbury, at Glenhaven road.
112 City Document No. 18
Lowney Way, Charlestown, on the northwesterly side be-
tween Bunker Hill street and Tremont street.
Park street, Charlestown, at the northwesterly corner of
Warren street.
Radcliffe road, Hyde Park, at Tileston street.
Rosselerin road, Dorchester, on the southerly side between
Train street and Daly street.
Saratoga street, East Boston, from a point approximately 133
feet east of Shawsheen road approximately 1,172 feet easterly.
Saratoga street. East Boston, from a point approximately 195
feet east of Annavoy street to the Boston- Winthrop boundary
line.
Seaver street, Roxbury, on the southwesterly side adjacent to
Franklin park between Walnut avenue and Blue Hill avenue.
South street, West Roxbury, at the northeasterly corner of
Edgemont street.
Troy street, Boston Proper, at the northerly and southerly
corners of Albany street.
Wachusett street, Hyde Park, at the easterly corner of River
street.
Woodard road. West Roxbury, at the northwesterly corner of
Park street.
Specific Repairs
Baker street. West Roxbury, between Spring street and
Veterans of Foreign Wars Parkway, consisting of the reduction
in width of existing sidewalks.
Baker street. West Roxbury, from Spring street to the north-
easterly portion of Johnson street, consisting of the reduction
in width of the existing sidewalks.
Beacon street, Brighton, at Ayr road, consisting of the widen-
ing of the existing street car reservation crossover.
Beacon street, Brighton, at Cleveland Circle, consisting of
the removal of the existing traffic circle, the installation of new
traffic divisional islands, and the reduction in width of sidewalks
on the southerly side from Chestnut Hill avenue to the Brook-
line boundary line.
Berkeley street, Boston Proper, from Beacon street to Marl-
borough street, consisting of the reduction in width of the
existing sidewalks.
Blue Hill avenue, Roxbury, between Franklin Park road and
Seaver street, consisting of the reduction in width of the
westerly sidewalk.
Blue Hill avenue, Dorchester, on the easterly side between
Landor road and Stratton street, consisting of the reduction in
width of the existing sidewalks.
Brewer street. West Roxbury, at the southwesterly corner of
Thomas street and the southeasterly corner of Eliot street, con-
sisting of increasing the curb radii.
Public Works Department 113
Centre street, West Roxbury, at the intersection of South
Huntington avenue, consisting of the installation of a traffic
island.
Columbia road, Dorchester, at the northwesterly and south-
westerly corners of Hamlet street, consisting of increasing the
curb radii.
Columbus avenue, Roxbury, consisting of the reduction in
length of the existing traffic divisional island north of Ruggles
street.
Columbus avenue, Boston Proper, at the northwesterly corner
of Stuart street, consisting of the installation of a traffic island
and the extension of the existing traffic island at the intersection
of Arlington street.
Columbus avenue, Roxbury, between Washington street and
Walnut avenue, consisting of the reduction in width of existing
sidewalks and the installation of traffic divisional islands.
Commonwealth avenue, Brighton, between Brighton avenue
and Warren street, consisting of the reduction in width of
existing sidewalks at various locations, reduction in width of
existing planting reservation, and the installation of a traffic
divisional island in the main roadway.
Commonwealth avenue, Brighton, on the southerly side be-
tween Fordham road and Reedsdale street, consisting of the
reduction in width of the existing sidewalk and the reduction
in width of the existing planting reservation.
Commonwealth avenue, Boston Proper, consisting of in-
creasing the curb radii at the southeasterly and southwesterly
corners of St. Mary's street.
East Broadway, South Boston District, from Dorchester
street at the intersection of West Broadway to L street, con-
sisting of the reduction in width of existing sidewalks.
Elm Hill avenue, Roxbury, at the northeast corner of
Crawford street, consisting of the reduction in width of the
existing sidewalk.
Hagar street. West Roxbury, consisting of increasing the
curb radii at the southwesterly corner of Thomas street and
the southeasterly corner of Eliot street.
Massachusetts avenue, Boston Proper, between Columbus
avenue and Huntington avenue, consisting of the reduction in
width of the existing sidewalks and the installation of a traffic
divisional island.
River street, Hyde Park, consisting of the installation of a
traffic divisional island at the intersection of Wachusett street.
Ruggles street, Roxbury, at the intersection of Columbus
avenue, consisting of the installation of a traffic divisional
island.
Seaver street, Roxbury, between Walnut avenue and Blue
Hill avenue, consisting of the removal of the existing street
car reservation, the reduction in width of the existing sidewalk,
and the installation of traffic divisional islands.
114 City Document No. 18
Walworth street, West Roxbury, at the northeasterly
corner of Belgrade avenue, consisting of increasing the curb
radius.
Washington street, Boston Proper, at the southeasterly
corner of Hayward place, consisting of increasing the curb
radius.
Washington street. West Roxbury, at the intersection of
South street, opposite Firth road, consisting of the installation
of a traffic island.
Woodard road. West Roxbury, at Wren street, consisting of
the reduction in size of the existing island.
Grades Revised
Brook Farm road, West Roxbury, between Lyall street and
Banks street.
Burley street, West Roxbury, from Metropolitan avenue
approximately 150 feet southerly.
Castle street, Boston Proper, between Harrison avenue and
Albany street.
Safford street, Hyde Park, between Huntington avenue and
Manion road.
Discontinuances
Brook Farm road, West Roxbury, at the northeasterly
corner of Banks street.
Cambridge street, Boston Proper, between Lindall place and
West Cedar street.
Central street, Boston Proper, from Kilby street approxi-
mately 215 feet northeasterly.
Chapel road, Hyde Park, on the easterly side between
Tacoma street and Farrar avenue.
Genesee street, Boston Proper, from a point approximately
412 feet southeast of Harrison avenue to Albany street.
Lovering street, Boston Proper, between Washington street
and Harrison avenue.
Maple street, West Roxbury, on the southeasterly side
between Corey street and Chilton road.
Motte street, Boston Proper, between Harrison avenue and
Washington street.
Oneida street, Boston Proper, from a point approximately
431 feet southeast of Harrison avenue to Albany street.
Oswego street, Boston Proper, from a point approximately
432 feet southeast of Harrison avenue to Albany street.
Public Alley No. 702, Boston Proper, between Worcester
street and West Springfield street.
Public Alley No. 703, Boston Proper, between Newland
street and Public Alley No. 702.
Public Works Department 115
Ryder Hill road, Brighton, from a point approximately 176
feet south of Bray ton road approximately 15 feet southerly.
Warren Bridge, Boston Proper and Charlestown.
Slope Easement
Hunneman street, Roxbury, discontinuance of slope ease-
ments between Washington street and Albany street.
Eminent Domain Land Takings
During the period of this report, land takings were
made for municipal purposes as follows:
Fire Department
1, The taking of approximately eleven thousand
seven hundred sixty-three (11,763) square feet of land
on Tremont street, Boston Proper District, under an
order of this Commission and Mayor dated January 4,
1957, and recorded in the Suffolk Registry of Deeds on
February 4, 1957.
2. The taking of approximately two thousand three
hundred eighty-six (2,386) square feet of land on
Tremont street, Boston Proper District, under an
order of this Commission and Mayor dated November
20, 1957, and recorded in the Suffolk Registry of Deeds
on November 26, 1957.
School Department
1. The taking of approximately twenty-three thou-
sand two hundred forty-nine (23,249) square feet of
land on Worcester street, Boston Proper District,
under an order of this Commission and Mayor dated
August 28, 1957, and recorded in the Suffolk Registry
of Deeds on September 18, 1957.
Sewer Program
During the year 1957, the construction of .65 miles of
sanitary sewer; .85 miles of storm sewer; 216 catch
basins; and 94 drop inlets was ordered at a total
estimated cost of $178,858.
Estimated benefit to private property for the con-
struction of the .58 miles of sanitary sewer amounted to
$24,923.75.
Sewerage works ordered were as follows:
116
City Document No. 18
Street
<g a
OS
03-t
3
CO
n
m
OJ
"a
a
o
Q
1
o
a
.sg
Boston Proper
78
$1,950 00
1,000 00
1,700 00
1,250 GO
5,500 ,00
800 00
4,550 00
350 00
2,500 00
900 00
1,600 00
5,000 00
600 00
400 00
2,000 00
2,000 00
4,800 00
1,200 00
2,600 00
3,400 00
2,000 00
3,200 00
1,700 00
300 00
150 00
600 00
3,800 00
1.200 00
None
3
3
3
1
None
None
50
None
11
4
4
None
None
181
None
1
5
5
5
3
1
14
3
5
9
2
1
14
None
None
Brighton
None
None
400
None
Charlestown
None
None
Dorchester
Blue Hill avenue . . .
None
None
340
319
$2,040 00
2
None
265
$1,950 00
6
8
3
8
None
East Boston
None
Hyde Park
Asheville road
100
102.5
370
$600 00
None
2
1
4
2
2
8
1
None
None
None
205
205
$1,600 00
None
590
10.000 00
None
* Easements taken
Public Works Department
117
Street
4> ■£
a a
id
.9g
gfc,
3
si
m
a
a
a
o
Q
1
O
-a
"S
w
Is
Sg
Hyde Park (Continued)
Huntington avenue
135
135
8
1
81,900 00
1,200 00
2,000 00
1,700 00
1,200 00
750 00
$1,425 00
None
40
115
♦Millstone road
Melba Way
1
2
1
None
Taunton avenue
40
20
•S562 50
(Relocation of existing
brook)
Roxbury
3
3
10
1
3
10
1
3,000 00
550 00
3,000 00
350 00
1,250 00
500 00
500 00
6,408 00
1,150 00
2,500 00
14,850 00
2,300 00
600 00
350 00
900 00
300 00
400 00
3,000 00
1,200 00
1.200 00
Blue Hill avenue . .
None
None
50
1
1
3
1
8
None
7
3
8
Forsyth street
South Bay avenue
321
$3,600 00
3
1
1
1
1
South Boston
Hill place
East Third street
1
West Roxbury
Ana wan avenue
6
2
2
Arborfield road and
Metropolitan avenue at
* Easements taken
118
City Document No. 18
Stbeet
^•^
Q ^
^2
a
■a
J
a
ci
o
Q
West Roxbury (Continued)
♦Centre street
Charles Park road
Claron street
Dow road
Furbush road
Furbush road
Graham terrace
♦Grandview street
*Hackensack court
Hautevale street
Joyce Kilmer road
June street
Mansur street
Maria Lane
Marlin road
Myer street
Moreland street
Newfield street
Partridge street
Pleasantdale road
Perkins street
Shandon road
Williams street
Woodard road
Woodard road
660
80
440
400
35
52
100
120
325
80
450
405
35
670
$1,500 00
3,000 00
300 00
1,800 00
1,000 00
500 00
800 00
11,800 00
1,300 00
100 00
300 00
1,200 00
11,400 00
1,000 00
1,250 00
500 00
4,800 00
1,000 00
900 00
1,800 00
8,000 00
1,000 00
700 00
350 00
300 00
* Easements taken
Public Works Department
119
Assessments
During the year 1957, the Highway Division of the
Pubhc Works Department sent notice of completion of
forty-nine (49) streets at a total cost of $679,705.24.
On this work the Public Improvement Commission
levied assessments in the amount of $241,402.54.
During the same period, the Sewer Division of the
Public Works Department reported the completion of
construction of sanitary sewerage in twenty-five (25)
streets at a cost of $101,331.71, on which the Pubhc
Improvement Commission levied assessments in the
amount of $41,459.
The completion of new sidewalks in two (2) streets at
a cost of $8,840.08, authorized by the Boston City
Council, was also reported by the Highway Division.
On these, the Pubhc Improvement Commission levied
assessments totahng $4,074.50.
Street Assessments
Street
District
Cost
Assessment
Ackley place
Agassiz park
Alleghany street. .
Ayles road
Barna road
Brockton street . . .
Brownson terrace. .
Brush Hill terrace .
Caltha road
Chapel road
Cheshire street. . . .
Driftwood road. . . .
Drumlin road
Edwardson street. .
Ellard road
Farwell avenue. . . .
Frazer street
Granada park
Guest street
Hampstead Lane. .
West Ro.xbury
West Roxbury
Roxbury
Hyde Park
Dorchester
Dorchester
West Roxbury
Hyde Park
Brighton
Hyde Park
West Roxbury
West Roxbury
East Boston
Hyde Park
Hyde Park
Hyde Park
Hyde Park
West Roxbury
Brighton
West Roxbury
S5,598 69
5,583 76
17.867 57
32.868 95
9,902 50
6,473 36
15,894 98
14,381 40
12,169 85
7,309 73
3,021 01
15,006 75
17,340 56
5,983 77
13,246 92
15,201 59
25,474 74
9,993 96
31,313 43
6,056 61
S2,599 30
2,328 94
5,261 75
12,470 36
5,426 27
2,619 18
6,894 06
5,721 38
2,269 24
2,274 60
1,498 91
6,140 80
1,893 52
2,181 47
2,021 16
4,831 91
9,492 67
4,741 6&
10.152 51
3,871 99i
Carried forward..
$41,427 21
120
City Document No. 18
Street Assessments. — Concluded.
Street
District
Cost
Assessment
Brought forward.
Harmony street
Harrow street
Howard place
Itasca street
Joslin road
Langford park
Laurie avenue
Lewiston street
Lorimer place
Maple street
Marion place
Marlin road
Mary knoll street
Maryknoll terrace
Meadowview road
Messinger street
Mildred avenue
Millstone road
Mossdale road
New Bedford street
New England avenue. . .
O'Donnell terrace
Range road
Rocky Nook terrace. . . .
Savannah avenue
Tanglewood road
Welton road
West Howell street
Wichita terrace
East Boston
Dorchester
Dorchester
Dorchester
Roxbury
Roxbury
West Roxbury
Hyde Park
Roxbury
West Roxbury
East Boston
West Roxbury
Dorchester
Dorchester
Hyde Park
Dorchester
Dorchester
Hyde Park
West Roxbury
Hyde Park
Dorchester
Dorchester
Dorchester
West Roxbury
Dorchester
Dorchester
West Roxbury
Dorchester
Dorchester
8,323 20
10,418 25
4,945 75
17,779 86
11,398 39
6,379 15
35,106 85
9,014 75
5,769 91
19,723 51
5,095 12
11,572 13
57,055 59
7,039 56
24,095 18
3,595 00
9,954 04
6,797 55
42,138 06
16,883 22
9,672 90
8,544 54
16,147 70
8,625 82
16,552 34
3,467 79
7,383 37
23,482 60
6,052 98
J41,427 21
712 50
3,075 76
1,869 00
6,586 40
2,031 80
2,793 30
14,793 37
3,982 25
2,092 17
3,410 88
1,694 10
4,253 50
14,039 59
3,146 85
11,368 30
1,500 00
4,000 00
2,203 56
22,299 06
6,487 64
4,326 24
3,850 50
6,914 30
3,249 01
5,612 68
1,540 72
3,280 79
3,082 50
2,514 06
Totals.
$679,705 24
$241,402 54
Public Works Department
Sewer Assessments
121
Street
Arborfield road.
Brook Farm road. . .
Coleman street
Davison street
Furbush road
Gladstone street. . . .
Hackensack terrace.
Keenan road
La Grange street . . .
Merola park
Moreland street . . . ,
Partridge street . . . ,
Partridge street . . . ,
Prairie street
Ransom road
Riley road
Rivermoor street . . .
Ryan road
RufBng street
Safford street
Sherrin street
West Howell street .
Wilmot street
Winchester terrace.
Woodland road
District
Cost
Assessment
West Roxbury
and Hyde Park
West Roxbury
Hyde Park
Hyde Park
West Roxbury
East Boston
West Roxbury
Brighton
West Roxbury
Dorchester
West Roxbury
West Roxbury
West Roxbury
Dorchester
Dorchester and
Hyde Park
Hyde Park
West Roxbury
Brighton
Hyde Park
Hyde Park
Hyde Park
Dorchester
West Roxbury
West Roxbury
Hyde Park
$12,017 00
4,932 00
2,256 00
2,500 00
2,450 00
1,196 00
3,191 00
2,358 70
8,992 00
2,708 00
2,830 00
1,777 00
350 00
1,160 00
820 00
4,487 44
19,000 00
2,660 10
5,100 00
800 00
2,900 00
6,916 00
2,274 00
2,602 47
5,054 GO
$6,364 80
3,360 00
1,350 00
870 00
480 00
650 00
2,150 00
1,400 00
2,721 40
2,200 00
911 25
990 00
210 00
360 00
360 00
1,860 00
4,440 00
1,600 00
2,639 91
600 00
1,306 64
1,095 00
792 00
1,518 00
1,230 00
Totals.
$101,331 71
$41,459 00
Sidewalk Assessrnents
Street
District
Cost
Assessment
West Roxbury
Brighton
$2,076 01
6,764 07
$1,007 50
3,067 00
Totals
$8,840 08
$4,074 50
122
City Document No. 18
Street Name Changes
The names of the following public streets were
changed :
Daytona Terrace, Dorchester District, from Centre Street
approximately 230 feet northeasterly; new name: O'Donnell
Terrace.
Harrison Avenue, Boston Proper District, between Essex
Street and Bedford Street; new name: Harrison Avenue Ex-
tension.
Main Street, Charlestown District, between Gardner Street
and the SomerVille boundary line (southerly roadway only);
new name: Maffa Way. (To be effective March 1, 1958).
The names of the following private streets were
changed :
Chelsea Place, East Boston District, from Chelsea Street
approximately 166 feet northwesterly; new name: Anthony J.
Grieco Terrace.
Hackensack Square, West Roxbury District, from Hacken-
sack Road approximately 310 feet southerly; new name:
Hackensack Terrace.
Land Damages
On new street construction, 95 claims were filed for
damage to property resulting from land takings or
changes in grade. On these claims, this Commission
awarded damages in the amount of $22,310.18.
During the period of this report, 374 petitions from
public utilities were approved for the placing and main-
taining of poles for the support of wires.
Also, 66 petitions were approved for miscellaneous
installations or uses of the public highways of the City
of Boston as follows:
Street
Petitioner
Nature of Petition
Ansonia road, West Roxbury
Boston Gas Company
Underground gas main
Beacon street, Boston Proper
Boston Edison Company
Underground conduit
Bennington street. East Boston
Boston Gas Company
Underground gas main
Blue Hill avenue, Dorchester
Boston Gas Company
Underground gas main
Bosworth street, Boston Proper
Old Colony Trust Company, et al
Underground steam main
Brainard street, Hyde Park
Worcester Gas Light Company
Underground gas main
Brook Farm road. West Roxbury
Boston Gas Company
Underground gas main
Bunker Hill street, Charlestown
Boston Gas Company
Underground gas main
Cedar Grove street, Dorchester
Boston Gas Company
Underground gas main
Public Works Department
123
Street
Petitioner
Nature of Petition
Clare avenue, Hyde Park
Worcester Gas Light Company
Underground gas main
Clarendon street, Boston Proper
Boston Edison Company
Underground conduit
Cleveland street, Hyde Park, Child
street and Beaver street
Worcester Gas Light Company
Underground gas main
Columbia road, Dorchester
Jenney Manufacturing Company
Underground fill pipe
Crown street, Hyde Park
Worcester Gas Light Company
Underground gas main
Curtis street. East Boston
Boston Gas Company
Underground gas main
Dale street, West Roxbury, at Burley
street
Boston Gas Company
Underground gas main
Dale street. West Roxbury, at May-
nard street
Boston Gas Company
Underground gas main
Duxbury road, Dorchester
Boston Gas Company
Underground gas main
E street, South Boston
Boston Gas Company
Underground gas main
East First street. South Boston
Boston Gas Company
Underground gas main
Edgemere road. West Roxbury
Boston Gas Company
Underground gas main
Farragut street. West Roxbury
Boston Gas Company
Underground gas main
Hackensack road, West Roxbury
Boston Gas Company
Underground gas main
Hallowell street, Dorchester
Boston Gas Company
Underground gas main
Harrison avenue, Boston Proper,
northeast of Hayward pi
Boston Edison Company
Underground conduit
Harrison avenue, Boston Proper,
southwest of Norfolk pi
Boston Edison Company
Underground conduit
Huntington avenue, Hyde Park, op-
posite No. 339
Worcester Gas Light Company
Underground gas main
Huntington avenue, Hyde Park, near
No. 260
Worcester Gas Light Company
Underground gas main
Jackson street, Charlestown
Boston Gas Company
Underground gas main
Kelton street, Brighton
Governor Apartments
Underground conduits
Kneeland street, Boston Proper
Boston Edison Company
Underground conduits
Lyall street. West Roxbury
Boston Gas Company
Underground gas main
Lynn street, Boston Proper
Boston Gas Company
Underground gas main
MaryknoU street, Dorchester
Boston Gas Company
Underground gas main
Massasoit street, Hyde Park
Worcester Gas Light Company
Underground gas main
Massachusetts Avenue Bridge, Bos-
ton Proper
Boston Gas Company
Relocate steel pipe
Massachusetts avenue and Clearway
street, Boston Proper
Boston Edison Company
Underground conduit
Massasoit street, Hyde Park, from
River street
Worcester Gas Light Company
Underground gas main
Mattakeeset street, Hyde Park
Worcester Gas Light Company
Underground gas main
Milk street, Boston Proper
Boston Edison Company
Underground conduit
Metropohtan avenue. West Roxbury
Boston Gas Company
Underground gas main
Monponset street, Hyde Park
Worcester Gas Light Company
Underground gas main
Mossdale road. West Roxbury
Boston Gas Company
Underground gas main
124
City Document No. 18
Street
Petitioner
Nature of Petition
Norton street, Hyde Park
Worcester Gas Light Company
Underground gas main
Norway street, Boston Proper
First Church of Christ
Pipe tunnels
Pierce street, Hyde Park
Worcester Gas Light Company
Underground gas main
Porter street, East Boston
Boston Gas Company
Underground gas main
Province street, Boston Proper
Brook Realty Company, Inc.
Projection
Providence street, Boston Proper
Boston Edison Company
Underground conduit
Readville street, Hyde Park
Worcester Gas Light Company
Underground gas main
River street, Hyde Park
Worcester Gas Light Company
Underground governor pit
River street, Dorchester
Boston Gas Company
Underground gas main
Saratoga street. East Boston, 4,019
feet of 12-inch
Boston Gas Company
Underground steel pipe
Saratoga street, East Boston, 3,825
feet of 12-inch
Boston Gas Company
Underground steel pipe
South Waverly street, Brighton
Boston Gas Company
Underground gas main
Southampton street. South Boston
Boston Gas Company
Underground gas main
Stuart street, Boston Proper
Boston Edison Company
Underground conduit
Summer street. South Boston
Boston Gas Company
Underground gas main
Summer street, Boston Proper
Boston Edison Company
Underground conduit
Tileston street, Hyde Park
Worcester Gas Light Company
Underground gas main
Vine street, Charlestown
Boston Gas Company
Underground gas main
Wachusett street, Hyde Park
Worcester Gas Light Company
Underground gas main
West Broadway, South Boston
Boston Gas Company
Underground gas main
West Cedar street, Boston Proper
Potter-Horn, Inc.
Wood cornice
Western avenue, Brighton
Boston Gas Company
Underground gas main
Wyola place Dorchester
Boston Gas Company
Underground gas main
During the year 1957, permission was given to prepare
for public travel the following private ways:
Gorman road, Dorchester, from 350 feet north of Cummins
Highway approximately 680 feet northeasterly.
Desmond road, Dorchester.
Gould street. West Roxbury, from Belle avenue to Northdale
road.
Itasca street, Dorchester, from Messinger street approxi-
mately 120 feet northeasterly.
Kiernan road, West Roxbury.
Mansur street, West Roxbury and Hyde Park, from Metro-
politan avenue to Grew avenue.
Messinger street, Dorchester, from Savannah avenue to
Colorado street.
Public Works Department 125
Northdale road, West Roxbury, from Gould street approxi-
mately 295 feet southerly.
Surreyhill road, West Roxbury, between Moss Hill Road and
Slocum road.
During the year 1957, permission was given to open
for public travel the following private ways:
Arborfield road, Hyde Park.
Emelia road, West Roxbury.
Garth road. West Roxbury.
Keenan road, Brighton.
Ryan road, Brighton.
Wilmot street. West Roxbury.
Respectfully submitted,
George C. Hyland, Chairman.
Herman Carp, Vice-Chair man.
Timothy J. O'Connor, Member.
Crry op Boston
Administrative Services Department
Printing o^^^ Section
m^rl.?,m''^^'-'C LIBRARY
Mm
■m