Skip to main content

Full text of "Concrete, its manufacture and use"

See other formats


TA 


ONCRETE 


ITS 

MANUFACTURE 
AND  USE 


KOEBRINC 


GIFT  OF 


CONCRETE 

ITS 

MANUFACTURE 
AND   USE 


Copyright  1921 

by 
Koehring  Company 


-f  f^ 


11 


Published  by 

KOEHRING  COMPANY 

Milwaukee,  Wisconsin 


TABLE  OF 

Chapter  1. 

Field  Operations  in  Concrete  Construction. ...     9 

Chapter  2. 

Materials  Entering  Concrete 23 

Chapter  3. 

Concrete  in  Highway  Construction 34 

Chapter  4. 

Miscellaneous  Notes  for  Superintendent  and 
Foreman 85 

Chapter  5. 

Forms  for  Concrete  Construction 95 

Chapter  6. 

Use  of  Reinforcing  Steel  in  Concrete. 105 

Chapter  7. 

Notes  on  Specifications 113 

Chapter  8. 

Estimating  Cost  of  Concrete  Construction. ...  121 

Chapter  9. 

Notes  on  Culvert  and  Bridge  Construction .  .  .127 

Chapter  10. 

Convenient  Estimating  Tables  and  Exam- 
ples of  Use 135 

Chapter  11. 

Foundations  and  Footings 141 

Chapter  12. 

Waterproofing  of  Concrete 143 

Chapter  13. 

Placing  Concrete  under  Water 147 

Chapter  14. 

Notes  on  Silos,  Coal  and  Material  Bins,  and 
Grain  Tanks 149 

Chapter  15. 

Mechanical  Equipment — Its  Starting,  Care 

and  Operation 157 

6 


H 

u 


INTRODUCTION 

The  opportunities  of  a  manufacturer  of  construc- 
tion equipment  to  be  of  assistance  to  the  inspector, 
superintendent,  foreman  and  engineer  are  not  nu- 
merous. Yet  we  have  felt  that  there  was  a  distinct 
need  for  a  handbook  that  could  be  carried  in  the 
pocket  and  which  would  contain  information  con- 
cerning the  best  practice  in  the  manufacture  and 
use  of  concrete. 

The  word  "manufacture"  is  here  employed  in  its 
true  sense — "To  make  from  raw  materials  by  any 
means  into  a  form  suitable  for  use."  The  construc- 
tion engineer,  whether  he  represents  a  contractor, 
or  a  private  or  government  owner,  who  combines 
cement,  sand,  stone  and  water,  by  mixing  them  in  a 
concrete  mixer  is  as  truly  a  manufacturer  as  he  who 
combines  steel,  cast  iron  and  bronze  in  the  con- 
struction of  equipment.  In  the  same  degree  that 
the  mixer  manufacturer  must  fit  all  of  the  consti- 
tuent parts  to  make  the  finished  machine,  so  must 
the  concrete  manufacturer  control  the  materials 
entering  his  product  and  the  methods  employed  in 
their  combination  and  use. 

In  presenting  this  little  book  no  attempt  is  made 
to  have  it  serve  as  a  text  book,  nor  to  prescribe 
formulas  or  rules.  It  was  compiled  as  a  book  of 
reference,  of  sound  engineering  practice,  in  concise 
and  easily  readable  form.  It  is  not  a  finished  expo- 
sition of  methods  employed  in  all  types  of  con- 
struction work  in  which  concrete  is  used,  and  could 
not  be  made  complete  due  largely  to  the  ever 
changing  conditions  encountered. 

Accept  the  book,  therefore,  in  the  spirit  in  which 
it  has  been  prepared — a  guide  to  the  construction 
man  who  manufactures  and  places  concrete  in 
America's  permanent  structures,  and  a  suggestion 
for  the  better  care  of  equipment. 

KOEHRING  COMPANY. 


OJ 

\r 

OJ 

a* 

o 

o 
o 

01 

I 

0 

£ 
01 


CHAPTER  1 


FIELD  OPERATIONS  IN  CONCRETE 
CONSTRUCTION 

Careful  Planning  Means  Economical 
Completion  of  Project 

The  owner  for  whom  the  work  is  being  done,  be 
he  an  individual,  a  corporation,  or  a  government 
agency,  is  interested  in  quality,  speed  and  cost.  The 
contractor  and  the  construction  superintendent  are 
interested  in  cost,  speed  and  quality.  The  sequence 
of  these  items  is  in  accordance  with  their  relative 
importance  to  the  two  parties  to  the  contract. 

Both  are  interested  in  each  but  to  a  different 
degree.  The  owner,  whose  money  pays  for  the  work, 
desires  a  structure  on  which  depreciation  will  be 
negligible,  completed  in  as  short  a  time  as  possible 
after  the  decision  has  been  made  to  go  ahead,  and  at 
as  low  cost  as  is  consistent  with  quality.  Having  de- 
cided to  make  the  expenditure,  his  whole  thought  is 
of  quality  and  the  time  at  which  he  can  put  the 
building  to  use.  On  the  other  hand,  the  contractor 
having  given  an  estimate  of  the  cost  of  construction, 
is  vitally  interested  in  keeping  the  cost  below  that 
figure.  To  him  speed  means  the  ability  to  obtain  his 
reward  or  profit  at  an  earlier  date,  provided  it  can 
be  done  at  equal  cost  with  that  obtained  by  a  little 
slower  progress.  The  element  of  interest  on  bor- 
rowed money  must  be  offset  against  larger  payrolls 
or  a  greater  expenditure  for  plant.  But  even  though 
the  viewpoints  of  the  two  contracting  parties  are  not 
exactly  alike  they  are  closely  allied.  Both  are  inter- 
ested in  the  relation  between  cost,  speed,  quality 
and  mechanical  equipment. 

It  is  not  possible  to  give  any  fixed  rule  for  field 
organization  or  for  the  plant  required  for  a  project. 
The  character  of  the  enterprise,  its  location,  relation 
to  railroad  facilities  and  to  other  structures,  and 
local  traffic  conditions  over  which  the  contractor  has 
no  control  affect  the  decision  as  to  the  most  economi- 


pal  method  of  consumption.    It  is  evident,  however, 

-irhas/sh^lsucsess  ot'.tlxe  '-enterprise  depends  entirely 

'upon "the  care'ful* planning  of  the  method  by  which 

the  work  is  prosecuted,  and  the  proper  coordination 

of  all  items  entering  into  it.     These  items  will  be 

taken  up  in  accordance  with  their  relation  to  the 

placing  of  the  concrete.' 

Receipt  of  Materials  and  Plant  for 
Handling 

In  the  construction  of  every  project,  whether  it 
be  a  highway,  building,  dam,  or  bridge,  a  consider- 
able amount  of  time  must  be  given  to  the  prepara- 
tions of  the  site.  During  this  time  receipt  of  ma- 
terials for  the  concrete  should  be  arranged  for  and 
delivery  commenced.  These  materials  include  ce- 
ment, sand,  stone,  reinforcing  steel,  and  lumber  and 
steel  for  forms.  Finally  the  construction  plant  should 
come  on  the  ground.  The  construction  plant  has 
been  given  last  place,  not  because  it  is  least  impor- 
tant, but  to  emphasize  the  fact  that  without  the  ma- 
terials of  construction  available  the  plant  can  do 
nothing.  Many  contractors  have  found  themselves 
fully  equipped  with  expensive  plants  but  with  no 
materials  to  keep  them  busy. 

This  condition  can  be  overcome  only  by  storing 
a  considerable  quantity  of  materials  before  the  plant 
is  erected  or  provided.  Aggregates  and  cement  must 
be  on  hand  in  such  quantities  as  to  insure  continuous 
operation  of  the  concrete  plant.  The  cost  of  storage 
and  rehandling  is  more  than  offset  by  the  wages  paid 
to  skilled  mechanics  and  superintendents  if  the  work 
is  delayed  after  the  organization  is  in  the  field. 

Storage  of  aggregates  and  cement  may  be  at  the 
point  of  deposit  or  at  the  point  of  delivery  from  boat 
or  car.  It  is  probable  that  the  contractor  can  pro- 
tect himself  against  delays  due  to  truck  breakdowns 
while  hauling  material  from  the  point  of  delivery  to 
the  point  of  deposit,  yet  it  is  impossible  with  the 
present  condition  of  railroad  transportation  to  insure 
regular  delivery  from  the  source  of  supply  to  the 
railroad  siding.  Such  storage  means  increased  handl- 
ing. Practically  all  materials  must  be  rehandled  at 


10 


least  once.  Such  factors  as  interest  on  money  and 
the  tying  up  of  working  capital  must  be  taken  into 
consideration.  This  entails  more  expense  to  the 
contractor  unless  he  can  reduce  cost  at  some  other 
point  to  justify  it. 

The  first  essential  for  economical  handling  of 
aggregates  is  the  substitution  of  mechanical  equip- 
ment for  man  power.  Three  types  of  equipment  are 
available:  first,  bucket  or  skip  elevators  carrying 
material  from  bin  under  the  track  to  the  stock  pile; 
second,  locomotive  cranes  operating  on  a  track,  or  on 
wheels  or  multiple  traction,  handling  materials  from 
cars  into  piles;  and  third,  a  derrick  equipped  with 
clam-shell  bucket.  The  quantity  of  materials  to  be 
handled  per  day,  ability  to  reload  materials  into 
transportation  units  and  the  quantity  of  storage  re- 
quired will  determine  the  style  of  equipment  best 
suited.  In  selecting  this  equipment  the  quantity  of 
materials  to  be  handled  must  be  kept  constantly  in 
mind.  It  will  be  remembered  that  the  aggregates 
are  received  in  a  loose  state  and  as  a  result  the  clam- 
shell must  handle  1%  yards  of  aggregate  for  each 
yard  of  concrete.  Aggregate  must  be  handled  at 
least  twice,  making  necessary  the  use  of  equipment 
with  a  capacity,  measured  in  loose  materials,  of  at 
least  three  times  that  of  the  maximum  quantity  of 
concrete  placed  each  day.  The  unloading  plant  is 
the  first  of  those  items  which  go  to  make  up  a  per- 
fectly balanced  construction  plant. 

Amount  of  Concrete  to  be  Placed 

In  laying  out  the  remainder  of  the  plant  the  one 
item  of  importance  is  the  quantity  of  concrete  to  be 
placed.  When  this  is  determined  it  becomes  a  simple 
matter  to  determine  the  relation  between  plant 
charge  and  labor  charge.  The  decision  will  depend 
upon  the  cost  of  plant,  the  cost  of  freight  from  the 
contractor's  headquarters  or  from  the  point  of  man- 
ufacture to  the  point  of  installation,  additional  costs 
of  removal,  maintenance  and  repairs.  If  25,000  cubic 
yards  of  concrete  are  to  be  placed,  the  allowable 
plant  charge  against  the  job  can  and  should  be  much 

11 


greater  than  if  only  500  cubic  yards  were  to  be 
handled.  Not  only  should  the  total  cost  be  more  but 
the  plant  expenditure  chargeable  to  the  undertaking 
can  be  more  per  cubic  yard  of  concrete,  in  order  that 
the  number  of  men  may  be  reduced,  thereby  allow- 
ing more  rapid  completion  of  the  contract  even  with 
a  scarcity  of  men. 

Character  of  Plant 

It  has  been  found  advisable  in  many  instances 
to  divide  the  work  into  two  distinct  parts,  that 
handled  by  small  portable  mixers  and  that  placed  by 
the  large  central  mixing  plant.  For  the  preliminary 
work  such  as  footings  or  foundation  walls  where  the 
quantity  of  concrete  required  does  not  justify  the 
operation  of  a  large  plant  a  7-foot  portable  mixer, 
taking  a  one-sack  batch  of  a  1 :2 :4  or  a  1 :3 :6  mix, 
will  prove  most  satisfactory.  This  type  of  machine 
can  be  set  up  at  any  convenient  point,  the  aggregates 
delivered  to  the  point  of  deposit  and  the  concrete 
put  in  at  lower  cost  than  by  any  other  method.  Upon 
the  completion  of  the  job  there  will  always  be  a  lot  of 
odds  and  ends  that  are  in  need  of  similar  treatment. 

Mixer   Most  Important  Piece  of  Plant 

The  concrete  mixer,  because  of  its  ability  to  turn 
out  the  element  for  which  payment  is  received, 
namely,  concrete,  is  the  most  important  unit  of  the 
construction  plant.  With  the  increased  use  of  con- 
crete construction  and  the  development  of  large  and 
expensive  placing  plants,  the  ability  of  the  concrete 
mixed  to  stand  up  under  hard  usage  is  a  big  item. in 
making  the  decision  for  the  adoption  of  a  given 
machine.  Delays  due  to  breakdowns  mean  excessive 
cost.  Continuity  of  operation  spells  profits.  This 
demands  heavy  duty  construction — a  machine  built 
of  the  best  materials  available — by  competent  work- 
men, with  careful  supervision. 

Organization  of  Remainder  of  Plant  Around 
Mixer 

The  remainder  of  the  construction  organization 
must  be  built  around  the  mixer.  Its  capacity  in 

12 


cubic  yards  per  day  will  depend  largely  on  the  equip- 
ment with  which  it  is  surrounded.  This  not  only 
requires  that  the  hoisting  and  placing  equipment  be 
able  to  take  care  of  the  output  but  that  every  link  in 
the  chain  from  the  receipt  of  the  cement  and  aggre- 
gates through  the  transportation,  the  bending  of  the 
steel,  and  the  erection  of  the  forms  be  planned  en- 
tirely on  the  maximum  mixer  capacity.  A  little 
item,  such  as  the  size  of  the  water  line  feeding  the 
mixer  may  result  in  slowing  down  the  operation 
from  five  to  ten  per  cent.  With  a  large  plant 
charge  constantly  going  on,  these  items  must  be 
given  consideration.  It  must  always  be  remem- 
bered that  no  pay  is  received  except  for  concrete 
in  place,  and  that  unless  the  mixer  is  doing  its  work, 
that  pay  stops. 

Character  of  Placing  Equipment 

The  type  of  placing  equipment  and  the  justifiable 
expenditure  will  depend  entirely  on  the  size  and 
character  of  the  work.  Naturally,  the  same  type  of 
equipment  cannot  be  used  on  a  highway  where  the 
concrete  is  placed  in  a  thin,  comparatively  narrow 
ribbon  as  would  be  used  on  a  building  or  on  heavy 
dam  construction. 

For  building  work  three  general  types  of  placing 
plants  have  been  used.  The  first  consists  of  a  tower 
up  which  is  hoisted  a  concrete  bucket.  From  this 
tower  the  concrete  is  distributed  by  gravity  through 
chutes  to  the  point  of  deposit.  The  same  type  of 
tower  is  used  in  the  second  plan,  together  with  a 
floor  hopper  from  which  the  materials  are  discharged 
into  concrete  buggies  or  barrows.  The  third  method 
consists  in  the  use  of  material  elevators,  the  concrete 
being  elevated  in  carts  or  barrows  to  the  point  of 
distribution  and  then  wheeled  to  place.  Three  items 
are  essential  regardless  of  the  system  used;  first, 
the  concrete  must  be  placed  without  segregation  of 
the  particles;  second,  there  must  be  control  of  the 
amount  of  water  consistent  with  maintaining  the 
flowability  of  concrete ;  and  third,  the  concrete  must 
be  of  such  quality  that  it  will  flow  around  the  rein- 
is 


forcing  steel.  Where  spouts  are  used  it  is  essential 
that  the  material  be  fed  to  the  spouts  slowly  from 
hoppers,  so  that  there  is  a  constant  stream  of  con- 
crete. By  doing  this  it  will  be  found  possible  to  use 
a  mix  which  is  easily  handled  in  the  forms  and  with 
which  there  will  be  no  segregation. 

On  construction  work,  such  as  retaining  walls 
where  there  is  comparatively  little  concrete  per 
linear  foot  it  is  sometimes  desirable  to  set  up  a  cen- 
tral mixing  plant  and  haul  the  concrete  for  distances 
not  to  exceed  1,000  feet  in  each  direction.  If  this  is 
done,  care  must  be  taken  to  see  that  the  aggregate 
is  thoroughly  wet  before  going  into  the  mixer  or 
that  the  concrete  is  mixed  for  a  considerable  length 
of  time  and  that  the  amount  of  water  used  is  kept  to 
a  minimum.  Otherwise,  there  will  be  segregation 
causing  difficulty  in  placing  the  concrete  and  irregu- 
lar distribution  of  cement  and  aggregate  in  the 
forms. 

The  distribution  of  concrete  in  highway  con- 
struction has  been  practically  standardized  by  the 
adoption  of  the  end  charging  paving  mixer  equipped 
with  distributing  boom  and  bucket.  After  being 
mixed  the  concrete  is  discharged  from  the  drum  into 
the  bucket,  a  full  batch  at  one  time,  run  out  on  the 
boom  and  dumped  on  the  grade.  The  adoption  of 
the  bottom  dump  bucket  has  made  possible  the  de- 
positing of  concrete  in  place  without  segregation. 

Quality  of  Concrete  Desired 

The  character  of  the  work  to  be  done  will  deter- 
mine the  quality  of  concrete  desired.  It  may  be  for 
a  highway,  for  mass  work  or  for  heavily  reinforced 
sections.  Reference  to  table  No.  1  on  pages  28  and  29 
shows  the  recommended  proportions  for  each  char- 
acter of  work.  Peculiar  grading  of  aggregates  or  the 
availability  of  certain  sizes  of  materials  may  take  it 
desirable  to  vary  from  these  arbitary  proportions. 
Before  definitely  determining  the  mix  to  be  used  on 
a  large  project,  it  will  be  found  desirable  to  have 
the  aggregates  examined  to  determine  their  phys- 
ical properties  and  to  make  compressive  tests  to  de- 

14 


termine  the  strength  of  concrete  obtained  by  use  of 
the  various  proportions. 

Uniform  Strength  Demands  Uniform 
Consistency  of  Concrete 

The  quality  of  concrete  is  dependent  largely  on 
the  uniform  control  of  the  quantity  of  water.  It  is 
evident  that  the  same  consistency  cannot  be  used  for 
thin,  reinforced  sections  as  would  be  the  case  in 
highway  construction.  Yet,  having  adopted  a  con- 
sistency it  is  essential  that  this  be  strictly  adhered 
to.  This  is  easily  done  by  measuring  the  water  with 
an  automatic  water  measuring  tank  with  which  the 
mixer  can  be  equipped.  The  quantity  of  water  in  the 
aggregate  will  affect  the  amount  necessary  to  be 
put  into  a  batch,  and  although  this  water  content  of 
the  aggregate  will  vary  from  day  to  day,  depending 
on  weather  conditions,  it  will  not  be  found  neces- 
sary often  to  change  the  water  control.  It  is  readily 
appreciated  that  if  one  batch  of  concrete  is  flooded 
with  water  and  the  next  comes  out  dry  that  the 
strength  of  the  two  will  not  be  the  same,  as  the  dis- 
tribution of  cement  will  not  be  alike  throughout  the 
two  batches. 

Placing  Concretelin  Forms 

The  concrete  having  been  brought  to  the  point  of 
deposit,  it  is  essential  that  it  be  placed  with  care, 
first,  in  order  that  there  may  be  no  voids  between  the 
reinforcing  steel  and  the  concrete,  thereby  insuring 
proper  bond,  and  second,  that  no  honeycombed  spots 
appear  when  the  forms  are  removed.  This  is  possible 
by  careful  spading  at  the  sides  of  the  form  and  spad- 
ing or  rodding  the  concrete  sufficiently  to  make  sure 
that  there  are  no  porous  places  left  in  the  concrete. 
Satisfactory  surfaces  are  much  more  readily  ob- 
tained by  proper  spading  of  a  plastic  concrete  than 
by  trying  to  place  the  concrete  when  so  wet  that 
segregation  results.  Attention  should  be  given  to 
the  forcing  of  the  concrete  around  the  reinforcing 
steel  particularly  in  long,  narrow  or  deep  girders 
which  are  heavily  reinforced.  Reference  to  table  1 
on  pages  28  and  29  shows  that  in  this  type  of  con- 

15 


struction  it  is  desirable  to  use  a  comparative! 
small  aggregate,  so  that  the  concrete  can  be  place 
around  the  reinforcing  steel.  Even  with  this  aj 
gregate,  however,  there  is  a  tendency  for  the  stone 
to  bunch,  thus  forming  porous  spots. 

Too  much  water,  improper  mixing,  and  impropc 
methods  of  handling  concrete  result  in  laitanc 
Laitance  consists  of  the  finely  divided  dirt,  silt  an 
a  certain  amount  of  the  cement,  which  being  con 
paratively  light  and  having  no  adhesive  qualit; 
flow  to  the  surface.  This  may  be  generally  obviate 
by  reducing  the  quantity  of  water  to  the  point  whei 
there  is  no  large  excess  on  the  surface.  Laitance  hz 
no  strength  and  if  allowed  to  accumulate  will  mal 
a  weak,  porous  layer  in  the  structure.  Special  cai 
should  be  taken  in  the  concreting  of  wing  walls  fc 
bridges  and  culverts  when  the  wall  is  sloped  to  tf 
outer  end,  thereby  making  it  difficult  to  force  tf 
concrete  into  place  at  the  end  of  the  form.  Often  coi 
crete  will  be  allowed  to  fill  the  center  of  the  abu 
ment  with  the  idea  that,  like  water,  it  will  seek  I 
own  level  and  fill  up  the  end  of  the  wing  wall  forr 
What  happens  actually  is  that  the  lighter  particle 
including  the  excess  water,  flow  into  this  portion  < 
the  form  and  remain  there  until  the  forms  are  r< 
moved.  If  the  laitance  is  not  immediately  remove 
and  the  wall  repaired  there  will  be  insufficiei 
strength  in  this  portion  of  the  structure  to  wit] 
stand  frost  action,  to  say  nothing  of  withstandin 
pressure.  Where  laitance  occurs  it  should  be  in 
mediately  cleaned  from  the  surface  before  a  ne 
layer  of  concrete  is  put  into  place. 

Curing 

Reference  has  been  made  elsewhere  to  the  ne 
essity  of  proper  curing  of  concrete,  yet  it  may  n< 
be  out  of  place  at  this  point  to  refer  to  the  respon 
ibilities  which  this  particular  work  puts  upon  tf 
contractor.  In  country  road  construction  where  tit 
concrete  can  be  readily  cured  either  by  ponding  < 
by  wetting  of  an  earth  covering,  the  expense  can  t 
very  readily  calculated,  the  only  additional  equi] 

16 


ment  being  a  little  larger  pipe  line  than  will  other- 
wise be  required  and  possibly  a  little  larger  pump. 
On  concrete  floors  in  buildings  the  question  of  prop- 
er curing  is  a  much  more  difficult  matter.  Two 
methods  have  been  largely  employed,  the  first  one 
using  sawdust  which  is  kept  wet  and  the  second 
method  covering  the  floor  with  sand.  Both  of  these 
have  their  drawbacks  due  to  the  expense  of  getting 
the  material  in  place  and  removing  it.  However, 
the  results  obtained  by  curing  more  than  justify  the 
expense.  It  is  suggested  that  every  contractor  put 
into  his  bid  an  item  to  cover  curing  of  concrete  in 
floors  and  roof  slabs,  as  well  as  all  pavements. 

Strength 

All  of  the  foregoing  items  have  an  ettect  upon 
strength,  and  it  is  probable  that  in  the  future  we 
will  be  able  to  increase  materially  our  present 
standard  for  highway  construction  because  of  high 
strength  concrete  made  available  by  more  careful 
control  of  the  materials  entering  the  mixer.  How- 
ever, at  the  present  time  this  art  has  not  been  car- 
ried far  enough  so  that  we  can  do  no  more  than  pay 
very  strict  attention  to  all  these  details.  The  item 
of  strength  is  one  that  is  of  more  than  passing  in- 
terest. True,  a  building  may  be  designed  for  con- 
crete having  a  strength  of  only  2,000  pounds  per 
square  inch  but  may  inadverdently  be  so  loaded  in 
spots  as  to  throw  a  higher  stress  upon  it.  Floors 
which  are  subject  to  heavy  trucking,  industrial 
driveways,  and  concrete  pavements  all  must  nec- 
essarily withstand  great  impact  as  well  as  compres- 
sion. It  is  evident  that  there  is  a  relation  between 
strength  and  resistance  to  wear,  although  other  fac- 
tors, such  as  quality  of  aggregates  materially  affect 
this  relation. 

Effect  of  Design  of  Mixer  on  Quality  of  Concrete 

The  development  of  the  concrete  mixer  has  been 
the  result  of  a  demand  on  the  part  of  contractors 
for  a  more  economical  way  of  mixing  concrete,  on 
the  one  hand,  and  a  demand  on  the  part  of  en- 
gineers and  owners  for  a  more  uniform  and  stronger 

17 


concrete,  on  the  other.  It  is  interesting  to  note  that 
by  far  the  largest  part  of  experimental  work  on  con- 
crete done  in  laboratories  has  been  done  with  con- 
crete mixed  by  hand,  but  tests  in  the  field  show  that 
uniformity  of  product  is  available  only  when  prop- 
erly mixed  in  a  mixer  of  proper  design. 

Batch  concrete  mixers  can  roughly  be  divided 
into  two  general  types.  First,  those  that  mix  by  a 
churning  action  only,  and  second,  those  having  an 
action  wherein  the  materials  are  alternately 
scattered  and  brought  together.  In  the  mixing  of 
any  material  it  is  evident  to  obtain  maximum  mix- 
ing in  the  minimum  time  it  is  necessary  to  dislodge 
each  particle  of  material  from  the  particle  with 
which  it  was  in  contact  and  then  recombine  it  with 
another  particle.  In  this  way  only  can  there  be  a 
true  mixing  action. 

In  the  mixing  of  concrete  there  are  four  materi- 
als which  are  placed  in  the  drum  in  their  natural 
state  and  which  must  be  discharged  from  the  drum  in 
a  homogeneous,  uniform  mass.  These  materials  are 
cement,  sand,  stone  and  water.  The  sand  and  stone 
are  more  or  less  of  the  same  general  character  and 
would  take  their  own  positions  with  comparatively 
little  mixing.  However,  it  is  essential  that  the  cement 
and  water  be  formed  into  a  cement  paste  which 
thoroughly  covers  all  of  the  particles  of  stone  and 
sand  making  a  matrix  to  hold  the  entire  mass  in 
place.  In  order  that  this  may  be  done  in  a  short  time 
(from  1  minute  to  iy2  minutes)  there  must  be  a 
large  number  of  actions,  scattering  and  bringing  ihe 
materials  together.  If,  on  the  other  hand,  the  ma- 
terials are  simply  carried  to  the  top  of  the  drum  and 
dropped  into  the  mass  as  a  whole  there  can  be  very 
little  mixing.  If  a  swing  chute,  pivoted  on  the  in- 
side of  the  drum,  so  as  to  allow  it  to  stand  at  a 
steep  angle  and  to  throw  the  materials  which  are 
carried  up  in  the  pickup  buckets  over  to  the  charg- 
ing side,  is  inserted  into  the  mixer,  an  entirely  dif- 
ferent mixing  action  takes  place.  The  materials 
having  been  placed  in  the  charging  side  of  the 
drum,  the  throw-over  blades,  which  are  attached  to 

18 


the  shell  diagonally  to  the  axis  of  the  drum,  cut 
through  the  material,  moving  a  portion  of  it  for- 
ward and  over  the  top  of  the  vane.  This  has  a 
scattering  effect  on  those  particles  and  a  mixing  ac- 
tion as  those  particles  strike  other  particles.  As  the 
drum  continues  to  revolve  the  concrete  is  carried  by 
these  blades  into  the  pick-up  bucket,  there  to  be 
carried  up  to  the  top  of  the  drum  and  thrown  onto 
the  inverted  swing  chute.  While  dropping  through 
space  the  particles  have  a  tendency  to  separate.  The 
direction  is  then  quickly  changed  as  the  material 
strikes  the  swing  chute,  so  that  the  concrete  is 
spread  over  the  width  of  the  chute  in  a  thin  sheet 
prior  to  being  returned  to  the  charging  side  of  the 
mixer  to  go  through  the  remixing  action  again. 

The  water  should  be  put  into  the  mixer  at  the 
same  time  as  the  other  materials.  This  is  desirable 
in  order  that  the  mixing  of  the  cement,  water  and 
aggregate  may  go  on  simultaneously.  Incidentally, 
the  placing  of  water  at  the  same  time  as  other  ma- 
terials keeps  the  blades  of  the  mixer  clean  thereby 
protecting  against  clogging.  If,  on  the  other  hand, 
water  is  put  into  the  drum  ahead  of  other  materials 
the  wet  buckets  and  throw-over  blades  are  struck 
by  the  dry  materials,  resulting  in  a  tendency  for  the 
cement  to  stick  to  these  parts. 

It  is  reasonable  to  believe  that  the  quality  of  the 
concrete  will  be  materially  affected  by  the  amount 
of  mixing  that  it  receives.  It  is  not  surprising,  there- 
fore, that  concrete  of  greater  strength  can  be  ob- 
tained in  the  same  time  in  a  machine  with  a  com- 
plex mixing  action  than  in  a  machine  in  which  ma- 
terial is  simply  churned  around.  Sufficient  tests 
are  not  available  to  make  a  definite  statement  as  to 
the  desirability  of  adopting  a  given  time  of  mixing  as 
standard  for  all  machines.  In  order  to  obtain  gen- 
erally satisfactory  results,  however,  engineers  have 
adopted  a  one  minute  mix  as  a  standard  minimum. 

Aggregate  Control 

The  workability  of  concrete  can  be  materially 
affected  not  only  by  the  size,  but  also  by  the  charac- 

19 


ter,  of  aggregate.  For  instance,  if  a  very  porous  ag- 
gregate is  used  it  will  be  found  difficult  to  handle 
the  mixed  concrete  unless  the  aggregate  is  either 
soaked  before  entering  the  mixer  or  the  materials 
are  allowed  to  remain  in  the  mixer  for  a  consider- 
able length  of  time.  If  this  is  not  done,  the  water 
in  the  concrete  will  be  quickly  absorbed  with  the 
result  that  there  will  not  be  a  sufficient  amount  to 
lubricate  the  mixture.  A  slight  variation  in  the  re- 
lation between  the  quantity  of  sand  and  stone  may 
materially  help  the  workability  of  certain  materials. 
This  is  desirable  where  a  coarse  aggregate  of  one 
size  is  being  used  to  add  to  a  second  coarse  aggre- 
gate to  make  the  mixer  more  workable. 

Water   Control 

The  grading  and  character  of  the  aggregates, 
and  the  proportions  affect  the  amount  of  water  re- 
quired to  make  a  plastic,  workable  mix.  As  the 
quality  of  concrete  is  dependent  upon  a  uniform 
quantity  of  water  for  each  batch  it  is  essential  that 
the  quantity  of  water  be  mechanically  controlled. 

Control  of  Amount  of  Mixing 

The  amount  of  mixing  required  to  obtain  a  de- 
sired strength  using  the  same  amount  of  cement, 
aggregate  and  water  will  always  be  the  same  for  a 
given  design  of  machine.  It  may  not  be  the  same 
for  another  concrete  mixer.  This,  as  explained  above, 
will  depend  entirely  upon  the  mixing  action.  In 
order  that  the  amount  of  mixing  may  be  absolutely 
uniform  in  all  instances  a  batchmeter  has  been  de- 
veloped which  mechanically  controls  the  number  of 
revolutions  or  time  of  mixing  for  each  batch.  This 
instrument  is  of  two  types.  The  first  is  driven  from 
the  mixer  drum  and,  knowing  the  speed  of  the 
drum,  the  time  is  mechanically  interpolated  to  a 
dial.  The  second  is  operated  by  an  escapement  so 
that  it  measures  elapsed  time.  The  control  which 
can  be  set  at  any  point  between  three  seconds  and 
three  minutes  releases  the  locking  mechanism  allow- 
ing the  discharge  of  the  mixer  and  announcing  the 
fact  by  the  ringing  of  a  bell. 

20 


Prior  to  the  adoption  of  this  mechanism  on  pav- 
ing mixers  many  had  not  appreciated  the  economy 
of  building  an  organization  around  time  control. 
Experience  has  shown,  however,  that,  knowing  the 
time  of  mix,  the  speed  with  which  the  concrete  is 
discharged,  and  the  speed  of  charging  the  mixer,  it 
is  possible  to  develop  the  organization  necessary  to 
get  maximum  output  from  the  machine.  The  whole 
basis  of  efficiency  engineering  is  the  coordinating 
of  time  with  production.  The  batch  meter  is  prov- 
ing a  pacemaker  for  the  crew,  measuring  the  same 
amount  of  time  for  each  batch. 

Capacity  of  Mixing  Plant 

The  capacity  of  the  mixing  plant  is  dependent 
upon,  first,  the  speed  of  charging  the  mixer,  second, 
time  of  mixing,  third,  time  for  discharging,  fourth, 
delays  incident  to  preparation  of  forms  and  receipt 
of  materials,  fifth,  organization  of  crew,  sixth,  size  of 
batch,  and  seventh,  ability  to  dispose  of  the  concrete. 
The  successful  contractor  is  the  one  who  can  place 
the  greatest  quantity  per  machine  at  the  least  cost  in 
a  season,  and  not  the  contractor  who  can  turn  out 
the  most  concrete  in  an  hour  or  even  in  a  day. 

Speed  of  charging  is  controlled  largely  by  the 
method  of  charging  the  mixer.  A  skillful  operator 
will  hoist  the  charging  skip  and  have  the  new  batch 
in  the  drum  within  five  seconds  after  the  last  of  the 
concrete  has  been  discharged  from  the  drum,  even 
though  it  may  take  ten  or  twelve  seconds  to  raise 
the  skip. 

The  time  required  for  discharging  the  batch  is 
comparatively  short,  so  that  even  if  the  concrete  is 
held  in  the  drum  of  the  mixer  for  a  full  minute  it 
will  be  possible  to  obtain  thirty  to  forty  batches  of 
concrete  per  hour.  Time  of  mixing  is  not  such  a 
large  factor  as  would  at  first  appear  because  there  are 
on  every  project  a  large  number  of  conditions  which 
cause  delay.  Investigation  of  construction  plants 
show  that  the  greatest  delays  are  due  to  inability  to 
obtain  materials  at  the  proper  time,  inability  to  get 
the  forms  in  shape  to  receive  the  concrete,  or  ina- 
bility to  place  the  concrete  after  it  is  mixed. 

21 


Concrete  mixers  are  built  having  capacities  of 
from  four  to  thirty-four  cubic  feet  of  concrete. 
Each  size  has  its  special  place.  It  may  be  more 
economical  in  certain  instances  to  use  the  equip- 
ment on  hand  for  a  certain  time  each  day  rather 
than  to  purchase  new  equipment  that  is  exactly  the 
right  size  for  the  job.  However,  as  a  general  rule 
there  is  a  tendency  on  the  part  of  construction  or- 
ganizations to  give  too  little  thought  to  the  size  of 
mixer  which  they  use  on  a  given  piece  of  work. 

The  richness  of  mix  and  the  quantity  of  water 
used  do  not  effect  the  capacity  of  the  mixer  plant, 
with  the  possible  exception  of  the  ability  to  place 
concrete  in  forms  by  use  of  towers  and  spouts. 

Conclusion 

This  chapter  is  intended  as  a  resume  of  experi- 
ence based  on  a  study  of  construction  operations 
and  construction  plants.  It  has  not  been  prepared 
with  the  idea  that  it  is  the  place  of  a  manufacturer 
of  machinery  to  make  definite  recommendations  as 
to  the  exact  size  of  plant.  There  are  many  items 
which  enter  into  such  a  decision  and  it  is  hoped  that 
these  have  been  set  forth  in  this  chapter  in  a  way  to 
be  helpful  suggestions. 


22 


CHAPTER  2 
MATERIALS  ENTERING  CONCRETE 

Concrete  Aggregates 

Aggregates  are  the  inert  materials,  such  as  sand, 
stone  screenings,  pebbles,  broken  stone  and  slag,  used 
with  portland  cement  and  water  to  make  concrete. 

Aggregates  are  usually  classified  as  coarse  or 
fine.  Fine  aggregate  is  any  suitable  material  that 
will  pass  a  No.  4  sieve  or  a  screen  having  four 
meshes  to  the  linear  inch.  Therefore,  when  stone 
screenings  or  other  rock  material  is  crushed  so  that 
it  conforms  to  the  above,  it  is  regarded  as  sand 
when  used  in  proportioning  a  concrete  mixture. 

Coarse  aggregate  is  any  suitable  material  such 
as  pebbles  or  crushed  rock  of  various  kinds  that  will 
not  pass  a  No.  4  sieve.  Coarse  aggregate  may  range 
from  ^4-inch  to  as  much  as  3  inches  in  greatest 
dimension,  depending  upon  the  nature  of  the  work 
for  which  the  concrete  is  to  be  used.  As  a  rule, 
however,  the  average  maximum  for  most  building 
construction  is  1*4  or  !/4  inches. 

Concrete  cannot  be  stronger  than  the  materials 
of  which  it  is  composed.  Nothing  is  more  certain  to 
produce  unsatisfactory  concrete  than  poor  aggre- 
gates. The  quality  of  the  cement,  methods  of  pro- 
portioning and  mixing  the  ingredients,  the  amount  of 
water  used,  the  time  of  mixing  and  the  manner  of  de- 
positing concrete,  all  have  their  effect  upon  its  den- 
sity, strength  and  general  quality,  but  good  results 
cannot  be  expected  when  poor  aggregates  are  used. 

Sand,  or  Fine  Aggregate 

In  the  selection  of  sand,  even  greater  precau- 
tions are  necessary  than  when  selecting  coarse  ag- 
gregates, because  sand  varies  in  physical  character- 
istics and  in  general  properties  more  widely  than  do 
the  materials  commonly  used  as  coarse  aggregate. 

A  small  quantity  of  organic  matter  in  sand  may 
make  it  entirely  unfit  for  use.  Many  impurities  found 
in  sand  affect  the  setting  of  the  cement,  hence,  the 

23 


strength  of  the  concrete.  Clay  in  the  form  of  a 
coating  on  the  particles  is  injurious  since  it  prevents 
the  cement  from  contact  with  the  surface  of  par- 
ticles and  thereby  performing  its  bonding  or  bind- 
ing function. 

Clean  Sand 

If  the  sand  is  clean  it  should  not  discolor  the 
hands.  A  coating  of  vegetable  matter  on  sand  grains 
appears  not  only  to  prevent  the  cement  from  hard- 
ening, but  may  affect  it  chemically.  Frequently 
the  quantity  present  is  so  small  that  it  cannot  be 
detected  by  the  eye,  yet  may  prevent  the  mortar  in 
which  it  is  used  from  ever  reaching  any  appreciable 
strength. 

A  simple  test  for  the  presence  of  organic  matter 
is  known  as  the  Colorimetric  Test,  developed  by 
the  Structural  Materials  Research  Laboratory,  Chi- 
cago. This  is  made  as  follows: 

Colorimetric  Test 

Obtain  a  12-ounce  graduated  prescription  bottle 
from  any  drug  store  and  fill  to  the  4J/2 -ounce  mark 
with  the  sand  to  be  tested.  Add  to  this  a  3  per  cent 
solution  of  caustic  soda,  also  obtainable  at  any  drug 
store,  until  the  volume  of  sand  and  solution  after 
shaking  amounts  to  7  ounces.  Let  this  stand  for 
twenty-four  hours.  At  the  end  of  this  time  observe 
the  color  of  the  liquid  above  the  sand.  If  the  solu- 
tion is  colorless  or  nearly  so — that  is,  has  but  a  pale 
yellowish  color,  the  sand  may  be  considered  suffi- 
ciently free  from  organic  impurities  for  any  use.  On 
the  other  hand,  if  the  solution  is  brownish  yellow  in 
color,  or  darker  than  a  pale  straw  color,  the  sand 
should  not  be  used  in  important  concrete  work  such 
as  that  required  in  roads  and  pavements  or  rein- 
forced concrete  building  construction.  If,  in  general, 
the  color  is  brownish,  the  sand  should  not  be  used  in 
anything  but  unimportant  work  such  as  footings  or 
foundations  that  are  not  to  carry  heavy  loads  nor  be 
subjected  to  frost.  If  the  solution  is  dark  brown  in 
color  the  sand  should  be  rejected. 

24 


This  test  furnishes  a  simple  and  inexpensive 
method  of  detecting  the  presence  of  such  organic 
impurities  as  decayed  vegetable  matter.  The  test  is 
being  used  by  a  large  number  of  testing  labora- 
tories, engineers  and  contractors  in  passing  on  the 
suitability  of  sand  for  use  in  concrete. 

Harmful  Materials 

The  term  "silt"  is  used  to  designate  all  foreign 
material  which  may  be  present  in  an  aggregate  in 
the  form  of  a  coating  on  the  grains  or  in  a  finely 
divided  state,  or  in  the  form  of  soft  or  soluble  mat- 
ter. Other  impurities  such  as  acids,  alkalies  or  oils 
in  the  sand  or  mixing  water,  usually  injuriously 
affect  the  quality  of  the  concrete. 

Effect  of  Physical  Properties  of  Aggregate 
on  Quality  of  Concrete 

The  hardness  of  aggregates  grows  in  importance 
with  the  age  of  the  concrete.  Due  to  the  rounded 
surface  of  the  aggregate,  pebble  concrete  one  month 
old  may  be  weaker  than  concrete  made  with  com- 
paratively soft  broken  stone,  but  when  one  year  old, 
it  may  surpass  in  strength  the  broken  stone  con- 
crete, because  as  the  cement  becomes  harder  and 
the  bond  firmer,  the  resistance  of  the  aggregate  to 
stress  becomes  a  more  important  factor.  The  aggre- 
gate particles  should  offer  at  least  as  high  a  resist- 
ance to  crushing  as  does  the  cement  after  attaining 
maximum  strength.  In  comparing  sands  of  the 
same  kind,  those  having  the  highest  specific  gravity 
are  likely,  as  a  rule,  to  be  the  strongest.  This  ap- 
plies in  a  general  way  to  the  comparison  of  different 
kinds  of  coarse  aggregate  also. 

Grading  of  aggregates — that  is,  the  relative  size 
and  quantity  of  the  particles  in  the  mass  determines 
in  a  large  degree  the  density  of  the  mass.  This  has 
its  effect  on  the  strength  of  the  concrete.  However, 
quantity  of  water  used,  time  of  mixing,  protection  of 
concrete  while  hardening,  also  exert  their  influence, 
so  that  grading  is  not  all-important  for  strength. 

A  sufficient  quantity  of  fine  grains  is  necessary 
in  grading  the  material  to  reduce  the  voids,  if  for  no 

25 


other  reason  than  to  assist  with  the  cement  in  in- 
creasing watertightness.  An  excess  of  fine  sand  has 
a  tendency  to  diminish  the  strength  of  the  concrete. 
Within  reasonable  limits,  the  strength  of  concrete 
increases  with  the  size  of  the  aggregates.  For  mass 
concrete,  the  practical  maximum  size  is  2y2  or  3 
inches.  In  thin  reinforced  sections,  such  as  floors 
and  walls,  the  maximum  size  must  be  confined  to 
particles  that  will  enable  the  placing  of  the  concrete 
around  reinforcing  steel.  Generally  1  or  1J4  inches 
is  then  the  preferred  maximum. 

The  shape  of  aggregate  particles,  especially  that 
of  large  aggregates,  influences  the  strength  of  the 
mortar  or  concrete.  Flat,  elongated  particles  pack 
loosely  and  generally  are  inferior  to  those  of  more 
nearly  cubical  fracture. 

Voids 

Voids  are  air  spaces  between  the  particles  and 
are  usually  referred  to  as  a  percentage  of  the  whole. 
An  aggregate  consisting  of  particles  all  uniform  in 
size  will  present  the  maximum  of  voids.  This  can 
be  illustrated  as  follows: 

Perfect  spheres  of  equal  size  piled  in  the  most 
compact  manner,  leave  theoretically  about  26  per 
cent  of  voids.  The  only  requirement  is  that  the 
spheres  be  of  equal  size.  If,  however,  the  spaces 
between  the  spheres  in  such  a  pile  of  equal  size  are 
filled  with  other  perfect  spheres  of  a  diameter  just 
sufficient  to  touch  the  larger  spheres,  the  voids  in 
the  total  included  mass  would  be  reduced  theoretic- 
ally to  20  per  cent.  Should  this  be  followed  up 
with  smaller  spheres,  the  air  spaces  or  voids  could 
theoretically  be  reduced  to  make  the  mass  water- 
tight. In  practice,  however,  a  mass  of  equal  sized 
spheres  will  be  found  to  contain  about  44  per  cent  of 
voids. 

Sampling  Sand 

In  selecting  a  sample  of  sand  for  test,  one  should 
make  certain  that  representative  samples  have  been 
obtained  from  different  parts  of  the  pit  from  which 
material  is  to  be  used.  The  most  representative 
sample  is  a  blend  of  several  samples  taken  from 

26 


different  parts  of  the  pit.  Whenever  possible,  the 
samples  should  be  taken  from  the  hoppers  or  from 
the  aggregate  pile  after  delivery  upon  the  work. 

Method  of  Making  Void  Determinations 

The  usual  method  of  making  void  determination 
is  by  means  of  a  graduated  vessel  partly  filled  with 
the  sand  to  be  tested.  The  amount  of  sand  should  be 
read  and  poured  out.  The  vessel  is  next  partly  re- 
filled with  water  and  the  graduations  read.  The 
known  amount  of  sand  is  then  added  to  the  water. 
The  difference  between  the  sum  of  the  two  gradua- 
tions and  the  reading  after  the  sand  is  poured  into 
the  water,  divided  by  the  amount  of  the  sand,  gives 
the  percentage  of  voids. 

Tests  on  Aggregates 

Accurate  tests  on  fine  and  coarse  aggregate  such 
as  tensile  or  compressive  tests  can  be  made  only  in 
physical  laboratories  properly  equipped  for  that 
purpose.  There  are  certain  to  be  apparent  discrep- 
ancies between  laboratory  tests  and  field  practice 
unless  the  laboratory  tests  are  made  under  field  con- 
ditions of  proportioning  and  mixing.  This  difference 
is  largely  due  to  the  exact  control  of  quantity  of 
materials  entering  the  batch  when  made  up  in  a 
laboratory,  which  is  not  entirely  possible  when  the 
work  is  done  in  the  field. 

There  is  concrete  work  which  has  proven  un- 
satisfactory because  of  the  use  of  fine  porous  lime- 
stone dust  or  screenings.  These  screenings  possibly 
were  accepted  after  a  laboratory  test  in  which  they 
were  made  up  into  briquettes  and  tested  in  tension, 
showing  a  strength  considerably  greater  than  the 
standard  sand.  In  making  the  briquettes,  the  ma- 
terial was  thoroughly  kneaded  so  that  there  was  a 
separation  of  every  small  particle  of  stone  dust  and 
a  thorough  coating  of  all  grains  with  cement.  In  the 
field,  however,  this  material  has  a  tendency  to  ball 
up,  with  the  result  that  the  cement  does  not  have  an 
opportunity  to  surround  each  small  particle.  The 
concrete,  therefore,  never  reaches  full  strength,  is 
porous,  and  is  affected  by  frost. 

27 


Table  No.  1 


TABLE  OF  RECOMMENDED  MIXTURES 
AND  MAXIMUM  AGGREGATE  SIZES 


MIXTURE  AND  CHARACTER 
OF  WORK 


1:1:1  Mixture  for 

The  wearing  course  of  two-course  floors  subject  to 
heavy  trucking,  such  as  occurs  in  factories,  ware- 
houses, on  loading  platforms,  etc. 

1 :2 :3  Mixture  for 

Reinforced  concrete  roof  slabs 

One-course  concrete  road,  street,  and  alley  pave- 
ments   

One-course  walks  and  barnyard  pavements  . . 

One-course  concrete  floors 

Fence  posts 

Sills  and  lintels  without  mortar  surface 

Watering  troughs  and  tanks 

Reinforced  concrete  columns 

Mine  Timbers 

Constructions  subjected  to  water  pressure,  such  as 
reservoirs,  swimming  pools,  storage  tanks,  cis- 
terns, elevator  pits,  vats,  etc 


1:2:4  Mixture  for: 

Reinforced  concrete  walls,  flloors,  beams,  columns, 
and  other  concrete  members  designed  in  combi- 
nation with  steel  reinforcing 

Concrete  for  the  arch  ring  of  arch  bridges"  «nd 
culverts 

Foundations  for  engines  causing  heavy  loading,  im- 
pact and  vibration 

Concrete  work  in  general  subject  to  vibration  .  .  .  , 

Reinforced  concrete  sewer  pipe 


1:2  %:4  Mixture  for 

Silo  walls,  grain  bins,  coal  bins,  elevators  and  simi- 
lar structures 

Building  walls  above  foundation,  when  stucco  finish 
will  not  be  applied 

Walls  of  pits  or  basements,  exposed  to  moisture. . . 

Manure  pits 

Dipping  vats,  hog  wallows 

Backing  of  concrete  block 

Base  of  two-course  road,  street  and  alley  pave- 
ments   


Recommended 
Maximum  Size 
of  Aggregate 
in  Inches 


28 


Table  No.  1 

TABLE  OF  RECOMMENDED  MIXTURES 
AND  MAXIMUM  AGGREGATE  SIZES 


MIXTURE  AND  CHARACTER 
OF  WORK 


Recommended 

Maximum  Size 

of  Aggregate 

in  inches 


1:2  1/2 :5  Mixture  for 

Walls  above  ground  which  are  to  have  stucco  finish  1  Vi 

Base  of  two-course  walks,  feeding  floors 1 

Bridge  abutments  and  wing  walls,  culverts,  dams 

small  retaining  walls,  when  not  reinforced 2 

Basement  walls  and  foundations  where  water  tight- 
ness is  not  essential 2 

Foundation  for  small  engines 2 

1:3:6  Mixture  for 

Mass  concrete — large  retaining  walls,  heavy  foun- 
dations and  footings 

1:1%  Mixture  for 

Inside  finish  of  water  tanks,  silos,  and  bin  walls, 
where  required,  and  for  facing  walls  belo'w  ground 
when  necessary  to  afford  additional  protection 

against  the  entrance  of  moisture To  pass  through 

No.  8  Screen) 

Back  plastering  of  gravity  retaining  walls To  pass  through 

.,_.; No.  8  Srceeen) 

1 :2  Mixture  for 

Facing  block  and  similar  concrete  products V4 

Wearing  course  of  two-course  walks,  floors  sub- 
jected only  to  light  loads,  barnyard  pavements, 
etc 1/4 

1:2%  Mixture  for 

Scratch  coat  of  exterior  plaster  (cement  and  stucco)    To  pass  through 

No.  8  Screen) 
Fence  posts  when  coarse  aggregate  is  not  used Vi 

1 :3  Mixture  for 

Intermediate  and  finish  stucco  coats To  pass  through 

No.  8  Screen) 

Concrete  block  when  coarse  aggregate  is  not  used .  Vi 

Concrete  brick Vi 

Concrete. drain  tile  and  pipe  when  coarse  aggregate 

is  not  used V4 

Ornamental  concrete  products Vi 


29 


During  the  past  few  years  a  number  of  state 
highway  departments  have  undertaken  field  tests 
with  a  view  of  ascertaining  the  quality  of  concrete 
obtained  in  the  field.  It  has  been  found  that  a  6  by 
12  cylinder  is  the  best  size  specimen  to  use.  The 
cylinders  are  made  in  the  field,  the  concrete  being 
taken  from  the  mixer  during  its  operation.  After 
hardening  they  are  shipped  to  the  laboratory  to  be 
tested  in  compression  and  by  impact. 

Washing  Aggregates 

If  the  only  aggregates  available  for  use,  contain 
some  of  the  objectionable  foreign  materials  already 
mentioned,  they  should  be  washed  before  using. 
Appreciating  the  importance  of  clean  aggregates, 
there  are  many  aggregate  plants  which  now  make  it 
a  practice  to  supply  only  washed  aggregates  for 
concrete  construction. 

Small  quantities  of  an  aggregate  may  be  washed 
in  trough-like  devices,  set  at  sufficient  angle  so  that 
when  the  materials  are  shoveled  into  the  upper  end 
and  a  strong  stream  of  water  allowed  to  play  down 
the  trough,  silt  and  clay  will  be  removed  by  the 
tumbling,  rolling,  washing  action  as  the  aggregates 
travel  toward  the  lower  or  outlet  end  of  the  trough. 
Where  any  considerable  quantity  of  aggregates 
must  be  washed,  special  washing  plants,  usually 
equipped  with  rotary  screens  to  size  the  particles  are 
necessary. 

Effect  of  Aggregate  on  Fire  Resistive  Quali- 
ties of  Concrete 

Concrete  has  assumed  its  place  in  building  con- 
struction because  of  its  ability  to  resist  fire.  To 
attain  this  in  the  greatest  degree,  it  is  necessary  that 
the  aggregates  be  selected  for  their  fire  resistive 
properties.  Some  aggregates  that  might  be  suited 
to  construction  where  the  concrete  is  to  be  exposed 
principally  to  impact  or  wear,  would  not  be  suitable 
where  fire  resistance  is  desirable.  The  best  aggre- 
gates are  siliceous  sands,  traprock  and  slag,  but 
some  grades  of  hard  limestone  have  also  proven 
particularly  suitable  to  fire  resistive  construction. 

30 


Steam  coal  cinders  also  may  be  used,  but  great 
care  should  be  taken  to  see  that  they  are  free  from 
particles  of  unburned  coal  and  contain  no  ash  or 
other  refuse.  Steam  coal  cinders  that  are  burned 
to  a  clinker  are  best.  Both  slag  and  trap  rock  have 
high  resistance  to  fire  and  probably  make  the  best 
coarse  aggregate  for  the  highest  type  of  fire  resist- 
ing construction. 

Effect  of  Mineral  Properties  of  Aggregate  on 
Strength  of  Concrete 

Sometimes  the  mineral  properties  of  certain  ag- 
gregates are  such  as  to  render  them  unfit  for  use  in 
a  concrete  mixture.  Iron  ore  and  rocks  containing 
some  other  mineral  substances  are  not  suitable: 
neither  are  slags  from  some  smelting  processes.  The 
slag  preferred  is  that  from  blast  furnaces  used  in 
iron  ore  reduction.  Where  sand  and  gravel  obtained 
in  iron  producing  regions  have  not  given  satisfac- 
tory result  in  concrete,  it  has  generally  been  due  to 
the  mineral  content.  The  oxidation  of  the  iron  pres- 
ent has  been  known  to  form  sulphite,  so  that  the 
chemical  action  was  powerful  enough  to  break  up 
the  concrete  through  disintegration. 

AcceptabilityJ^of  Aggregates 

Cinders  are  used  principally  for  concrete  where 
very  light  loads  are  involved  or  to  protect  steel 
structural  members.  They  are  frequently  used  as 
aggregate  for  concrete  in  floor  construction  or  in 
blocks. 

Stone  screenings,  if  from  hard,  durable  rock,  such 
as  granite  or  traprock,  and  if  well  graded,  clean  and 
free  from  an  excess  of  dust,  may  be  used  in  place  of 
sand  with  satisfactory  results.  As  a  wearing  sur- 
face for  floors,  clean  washed  screenings  from  granite 
are  very  desirable.  Owing  to  the  difficulty  of  ob- 
taining screenings  that  are  sufficiently  free  from 
dust  they  should  not  be  used  unless  they  are  first 
washed. 

Broken  concrete  should  never  be  used  as  aggre- 
gate. The  fact  that  there  are  but  few  of  the  original 
sand  and  stone  or  pebble  surfaces  exposed,  makes  it 

31 


almost  impossible  for  the  cement  to  bond  broken 
particles  of  concrete  together. 

Chats,  a  product  of  zinc  smelting,  are  frequently 
used  as  a  concrete  aggregate,  particularly  in  the  zinc 
mining  region  of  Missouri  where  it  is  the  principal 
aggregate  material  available.  When  properly  com- 
bined with  the  necessary  amount  of  hard  sand  and 
cement,  the  result  is  a  good  concrete. 

Quality  of  Concrete  not  Dependent  on  Ce- 
ment Alone 

A  popular  supposition  among  many  users  of 
cement  is  that  failures  in  concrete  construction  are 
caused  by  poor  cement.  Portland  cement  is  a  manu- 
factured product,  the  qualities  of  which  can  be  ex- 
actly controlled,  and  as  cement  manufacturers  must 
make  a  product  which  will  meet  standard  specifica- 
tion requirements,  it  can  be  realized  that  any  of  the 
well  known  brands  of  cement,  of  which  there  are 
many,  must  be  dependable  products  or  the  manufac- 
turers could  not  long  stay  in  business. 

Careful  investigation  of  concrete  failures  has 
generally  shown  that  aggregates,  workmanship,  or 
some  factor  other  than  the  cement  has  been  respon- 
sible for  failure  when  such  has  occurred.  There  are, 
no  doubt,  concrete  structures  standing  which  are 
not  what  they  should  be  because  of  faults  of  work- 
manship or  the  introduction  of  some  bad  practice. 

A  word  of  caution  should  be  given  concerning 
the  use  of  so-called  pit-run  gravel.  Almost  invari- 
ably such  material  contains  a  volume  of  sand  prac- 
tically twice  that  of  the  volume  of  pebbles,  while  for 
good  concrete,  the  bulk  of  pebbles  or  other  coarse 
aggregate  should  be  practically  twice  the  bulk  of 
sand.  Also  gravel  pits  frequently  are  not  stripped 
of  overlying  soil  before  they  are  worked  and  this 
soil,  which  is  usually  humus,  or  rotted  vegetable 
matter,  drifts  down  the  face  of  the  pit  and  becomes 
mixed  with  the  materials.  In  such  a  case  they 
should  not  be  used  until  washed.  They  should  also 
be  passed  over  suitable  screens  so  that  the  sand  and 
pebbles  may  be  separated  and  remixed  in  proper 
proportions. 


Careful  tests  will  show  that  no  two  wagon-loads 
of  gravel  taken  from  the  same  pit  are  alike  in  con- 
tained volumes  of  sand  and  pebbles,  nor  have 
throughout  the  same  grading  of  particles.  Even 
where  the  natural  run  of  bank  material  is  fairly  well 
graded,  this  grading  will  be  considerably  out  of  bal- 
ance when  the  material  is  dug  from  the  pit  because 
the  coarser  particles  drift  down  the  face,  so  one  load 
will  consist  largely  of  pebbles,  while  the  next  load 
will  be  largely  of  sand.  Bank-run  material,  therefore, 
should  be  prepared  for  use  by  screening  into  two 
volumes — sand  and  pebbles.  Even  were  it  possible 
to  make  good  concrete  by  disregarding  the  desira- 
bility of  screening  and  reproportioning  the  materials, 
economy  would  dictate  it  because  of  the  reduced 
quantity  of  cement  required  to  produce  a  concrete 
of  given  strength. 


Table  No.  2 


TABLE  SHOWING  CUBIC  YARD  WEIGHTS  IN  POUNDS, 

EQUIVALENT  WEIGHT  IN  TONS  AND  FRACTIONAL 

NUMBER   OF  CUBIC  YARDS  PER  TON 


Weight  of  Aggregates 
in  Pounds  per  Cubic 
yard 

Equivalent  Weight 
in  Tons 

Fractional  Number  of 
Cubic  Yards  per  Ton 

2,100 

1.050 

0.952 

2,150 

.075 

0.930 

2,200 

.100 

0.909 

2,250 

.125 

0.888 

2,300 

.150 

0.869 

2,350 

.175 

0.851 

2,400 

.200 

0.833 

2,450 

.225 

0.816 

2,500 

.250 

0.800 

2,550  A 
2,600  f 

.275 
.300 

0.784 
0.769 

2,650-- 

.325 

0.754 

2,700 

.350 

0.740 

2,750 

.375 

0.727 

2,800 

.400 

0.714 

2,850 

.425 

0.701 

2,900 

.450 

0.689 

2,950 

.475 

0.677 

3,000 

.500 

0.666 

3,050 

.525 

0.655 

3,100 

.550 

0.645 

3,150 

.575 

0.635 

3,200 

.600 

0.625 

3,250 

.625 

0.615 

3,300 

.650 

0.606 

33 


CHAPTER  3. 
CONCRETE  IN  HIGHWAY  CONSTRUCTION 

In  this  chapter  the  discussion  of  the  use  of  con- 
crete in  highway  construction  will  be  limited  to  the 
improvement  of  streets,  roads,  and  alleys  by  paving. 

Concrete  has  become  an  important  factor  in  the 
construction  of  highways  whether  it  is  used  as  a 
material  forming  the  entire  pavement  slab,  as  in  the 
case  of  concrete  pavements,  or  forms  the  founda- 
tions to  support  various  types  of  surface  such  as 
brick,  sheet  asphalt  and  asphaltic  concrete.  When 
used  for  the  entire  pavement,  it  must  be  designed 
and  built  to  give  the  type  of  surface  required  of  a 
first  class  heavy  duty  highway.  When  concrete 
serves  as  a  base  or  a  foundation  its  principal  func- 
tion becomes  one  of  carrying  the  load  and  distrib- 
uting it  over  the  subgrade. 

Probably  in  no  other  field  of  use  is  concrete  sub- 
jected to  such  severe  abuse  as  when  used  for  the 
construction  of  the  all-concrete  highway,  whether 
this  be  road,  street  or  alley.  The  concrete  not  only 
must  be  relied  upon  to  furnish  the  desired  surface 
for  traffic  but  must  resist  the  impact  and  abrasion 
resulting  from  the  weight  and  volume  of  such  traf- 
fic. It  is  evident  that  more  exacting  requirements 
must  be  made  for  concrete  in  the  all-concrete  pave- 
ment than  in  concrete  used  as  the  base  or  founda- 
tion for  another  type  of  wearing  surface.  This  does 
not  mean,  however,  that  the  concrete  foundation 
work  for  any  type  of  wearing  surface  can  be  mixed 
or  placed  in  a  slipshod  manner. 

One  and  Two  Course  Construction 

As  a  rule  concrete  pavements  are  of  one  course 
construction.  So-called  two  course  construction  is 
used  in  case  the  supply  of  local  materials  is  of  such 
quality  that  the  required  resistance  to  wear  and 
surface  impact  cannot  be  met  by  a  concrete  wearing 
course  in  which  the  local  aggregates  are  used.  In 
other  words,  in  two  course  concrete  highway  con- 

34 


struction  the  top  or  wearing  course  contains  aggre- 
gates especially  selected  for  toughness  and  wear 
resistance. 

Design  of  Pavements 

The  design  of  concrete  pavements  is  still  in  the 
process  of  evolution.  Many  practices  have  come  to 
be  regarded  as  standard  because  this  type  of  pave- 
ment has  now  had  sufficient  years  of  test  to  have 
proven  the  desirability  of  making  certain  require- 
ments fundamental.  Among  these  are  drainage  of 
foundation  or  subgrade,  proper  crown  of  the  pave- 
ment surface,  so  that  the  water  may  be  quickly  re- 
moved, slope  of  shoulders  to  the  gutters,  suitable 
outlets  for  delivering  water  to  culverts  and  natural 
channels,  and  associated  details  which  render  and 
maintain  the  foundation  or  subgrade  in  a  suitable 
condition.  Naturally  soil  conditions  as  well  as  cli- 
matic conditions  may  require  that  some  one  or  more 
of  these  features  be  given  particular  attention. 

Width  is  determined  principally  by  traffic  de- 
mands. With  motor  traffic  now  predominating  on 
most  highways  it  is  evident  that  the  minimum 
width  should  be  established  with  particular  refer- 
ence to  the  safety  of  motor  traffic  when  passing  at 
prevailing  speeds. 

The  thickness  required  to  meet  traffic  conditions 
has  not  been  standardized.  Traffic  has  changed 
both  in  amount  and  volume  with  greater  rapidity 
than  has  the  knowledge  of  the  requirements  of  high- 
way construction.  The  same  lack  of  standardiza- 
tion is  apparent  in  the  reinforcement  of  concrete 
pavements,  although  it  is  pretty  well  established 
that  reinforcement  under  many  conditions  of  sub- 
soil is  not  only  desirable  but  extremely  advisable. 
The  duty  of  the  reinforcement  is  to  prevent  ap- 
preciable opening  of  cracks  which  may  form. 

Concrete  Base 

When  concrete  is  used  as  a  base  for  other  types 
of  surfacing,  it  may  be  plain  or  reinforced,  but  since 
the  base  is  designed  almost  entirely  from  the  stand- 
point of  load  carrying  capacity  the  mixtures  used 

35 


usually  are   different  from  the  standard  mixtures 
used  in  the  all-concrete  pavement. 

Curves 

The  need  for  utmost  safety  of  traffic  on  modern 
highways  because  of  the  predominance  of  motor 
traffic  has  caused  more  attention  to  be  given  in  the 
past  two  or  three  years  to  certain  requirements 
of  design  and  construction  which  a  few  years  ago 
were  not  recognized  as  necessary.  Among  these 
are  easy  curves,  super-elevated  and  widened,  so  that 
motor  vehicles  can  take  them  in  safety  without  un- 
necessary reduction  in  speed. 

Shoulders 

Shoulders  for  a  concrete  road  are  provided  to 
allow  additional  room  for  passing,  to  give  the  en- 
tire roadway  a  finished  appearance  and  to  assist  in 
carrying  away  the  water  from  the  pavement.  In 
the  case  of  narrow  roads,  shoulders  are  usually  con- 
structed and  maintained  to  receive  a  portion  of  the 
traffic.  They  are  made  of  macadam,  either  water 
bound  or  tar  bound,  or  of  gravel  or  of  natural  earth, 
properly  graded  toward  the  side.  If  of  ordinary 
earth  the  usual  practice  is  to  endeavor,  as  soon  as 
possible  to  cover  them  with  a  growth  of  grass,  ex- 
cept for  that  portion  used  for  passing  vehicles,  thus 
preventing  wash  and  making  maintenance  easier 
and  less  costly. 

Curbs 

In  certain  cases  roads  as  well  as  streets  are 
bordered  by  curbs.  This  is  particularly  true  of 
curves  on  grades,  and  on  stretches  through  cuts. 
Usually  such  curbs  are  made  integral  with  the 
pavement  and  together  with  the  surface  of  the 
pavement  form  a  gutter  to  carry  surface  water  to  a 
permanently  located  outlet.  The  integral  curb  is 
suitable  for  boulevard,  avenue,  business  thorough- 
fare, alley,  driveway  or  road. 

Materials  of  Construction 

The  materials  entering  into  concrete  used  in 
highway  construction  are  the  same  as  when  used 

36 


for  other  structural  purposes.  They  are  cement, 
aggregates  and  water.  Elsewhere  the  required 
physical  properties  of  materials  have  been  consid- 
ered. These  apply  to  concrete  used  in  highway 
construction,  whether  for  base  or  for  the  all-con- 
crete pavement,  except  that  in  the  base  the  aggre- 
gates are  not  exposed  to  the  immediate  contact  of 
traffic.  Table  No.  10  on  page  58  gives  the  cubic 
yards  of  concrete  per  linear  foot  and  per  mile  of 
pavement  for  various  widths  and  thicknesses.  Ta- 
ble No.  11  shows  the  quantity  of  cement,  sand  and 
stone  required  per  linear  foot  and  per  mile  of  road 
for  different  mixtures  of  concrete.  The  following 
table  gives  recommended  thickness  for  concrete 
roads  and  streets. 

Table  No.  3 

THICKNESS  FOR  LIGHT  TRAFFIC  ROADS  AND  STREETS 


Width  Feet 

Sides  Inches 

Center  Inches 

10 

6 

8  (inside) 

18 

6 

8 

27 

6 

9 

36 

6 

9V2 

Table  No.  4 

THICKNESS  FOR  HEAVY  TRAFFIC  ROADS  AND  STREETS 


Width  Feet 

Sides  Inches 

Center  Inches 

20 
30 
40 

8 
8 
8 

10 
11 
12 

Just  as  it  has  been  the  practice  to  increase  the 
thickness  of  the  all-concrete  highway  pavement,  so 
has  the  tendency  within  the  past  year  or  two  been 
to  increase  the  thickness  of  concrete  base  used  for 
the  other  types  of  wearing  surface.  Also  the  mix- 
ture for  concrete  bases  has  been  made  richer.  In 
Illinois  the  standard  mix  for  concrete  foundation 
for  other  types  of  surface  is  1 :2 :3J£,  and  the  thick- 
ness from  four  to  six  inches.  The  tendency  in  oth- 
er parts  of  the  country  is  also  toward  wider  and 

37 


thicker  concrete  pavements  and  concrete  bases  in 
keeping  with  the  great  increase  of  heavy  motor  traf- 
fic on  all  classes  of  highways. 

Drainage 

As  already  mentioned,  much  of  the  stability  of 
any  type  of  road  surface  depends  upon  the  care 
given  to  draining  the  foundation  or  subgrade.  The 
purpose  of  drainage  is  to  secure  and  maintain  uni- 
formity of  subgrade  condition.  It  may  be  neces- 
sary to  lay  tile  drains  not  only  paralleling  the 
pavement  but  beneath  it.  In  flat  country,  for  ex- 
ample, shoulder  drains  are  generally  necessary  if 
the  pavement  is  placed  on  clay  soil.  In  case  the 
construction  of  a  highway  necessitates  the  cutting 
of  a  clay  or  shale  hill  where  sub-surface  water  is 
troublesome  it  is  advisable  to  construct  herring- 
bone cross  drains  of  broken  stone  or  tile  at  least 
eighteen  inches  deep  and  one  foot  wide.  These 
drains  have  their  beginnings  at  the  center  of  the 
road  and  extend  to  the  gutter,  at  an  angle  of  from 
thirty-five  to  forty-five  degrees  to  the  center  line 
of  the  pavement.  This  construction  is  particularly 
applicable  where  the  slope  of  the  rock  strata  is 
such  that  the  roadway  cuts  natural  water-bearing 
seams. 

Mechanical  Equipment 

As  the  increasing  highway  programs  of  the 
state  and  federal  governments  developed,  improved 
methods  of  handling  materials  and  organizing  the 
projects  made  their  appearance.  Those  interested 
in  the  construction  industry,  including  contractors, 
engineers  and  manufacturers  of  equipment,  have 
developed  new  machines  to  meet  the  new  require- 
ments, or  have  adapted  to  highway  work  the  ma- 
chines used  successfully  in  other  lines. 

The  paving  mixer  has  gone  through  an  interest- 
ing development.  As  originally  designed,  the  ma- 
terial was  placed  in  a  narrow  skip  barely  wide 
enough  to  allow  one  wheelbarrow  to  dump  into  it. 
Concrete  was  distributed  by  spout  or  by  horse 
drawn  cart.  The  next  prominent  step  was  the  de- 

38 


velopment  of  the  boom  and  distributing  bucket, 
which  was  made  automatic  the  next  year.  Then 
came  the  widening  of  the  skip  which  allowed  two 
men  to  discharge  their  wheelbarrows  into  it  at  the 
same  time.  Next  came  multiplane  traction  to  take 
the  place  of  road  wheels  on  the  traction  end  of  the 
mixer.  Finally,  with  the  development  of  the  use  of 
industrial  railroads,  a  derrick  was  added  to  pick 
the  batch  boxes  from  the  cars.  Today  the  paving 
mixer  stands,  an  example  of  the  highest  type  of 
construction  equipment. 

The  capacity  of  the  mixer  to  be  used  on  a  spe- 
cific contract  or  to  be  adopted  as  standard  by  a 
contractor  should  be  based  upon  the  following: 

(1)  the  quantity  of  highway  to  be  placed  per  year; 

(2)  availability  of  sufficient  materials  to  keep  the 
equipment  busy;    (3)  railroad  facilities,  car  supply, 
etc.;  (4)  storage  space  for  materials  and  availabil- 
ity  of    railroad   sidings    along    line    of   the   work; 

(5)  type    of    hauling     equipment     to     be     used; 

(6)  character  of  work  to  be  undertaken. 

Having  determined  the  size  of  the  machine  to 
be  adopted,  all  other  equipment  should  be  pur- 
chased with  one  idea,  to  keep  the  machine  going  to 
full  capacity  with  a  minimum  expense.  This  does 
not  mean  a  minimum  first  cost  for  equipment,  but 
does  mean  a  balanced  plant  that  will  reduce  labor 
costs  to  a  minimum  consistent  with  capacity  pro- 
duction. 

Equipment  is  naturally  divided  according  to  its 
use  into  handling  and  storage,  hauling,  pumping, 
mixing  and  placing,  and  finishing.  The  relation  of 
equipment  to  the  economical  completion  of  a  pro- 
ject will  be  considered  in  the  order  named. 

Handling  Materials 

Methods  of  handling  materials  from  cars  vary. 
The  size  of  the  project  and  the  method  of  handling 
other  parts  of  the  job  will  affect  the  choice.  The 
methods  of  unloading  include,  first,  unloading  by 
hand  either  into  wagons  or  trucks,  or  into  movable 
bodies  hung  against  the  side  of  the  car  from  which 

39 


The  Koehring  Crane  Excavator 

with  gasoline  engine 
and  multiplane  traction. 


•in 


the  material  is  dumped  into  trucks  or  wagons; 
second,  mechanical  unloading,  using  bucket  eleva- 
tors or  skip  hoists  from  pits  below  the  track;  and 
third,  the  use  of  a  clam  shell  bucket  on  a  derrick  or 
a  traction  crane.  The  first  and  second  of  these 
methods  have  proved  very  successful  where  com- 
paratively small  amounts  of  materials  were  handled 
or  where  the  material  could  be  obtained  in  bottom 
dump  gondola  cars,  but  they  do  not  give  the  re- 
quired capacity  in  case  the  storage  must  be  at  the 
railroad  station  and  not  on  the  subgrade. 

The  crane  fits  the  requirements  so  much  better 
than  the  others  that  even  at  a  larger  initial  invest- 
ment it  has  been  found  an  economical  addition  to 
a  plant.  The  speed  of  its  swing,  its  ability  to  travel 
alongside  the  piles,  and  thus  to  increase  the  storage 
capacity,  are  large  factors  in  its  favor. 

Opinion  is  divided  as  to  the  effectiveness  of  two 
types  of  material  storage  units — the  bin  and  the 
tunnel.  Bins  are  less  expensive  in  first  cost,  but 
the  tunnel  system  has  the  advantage  of  reducing 
the  amount  of  rehandling.  The  nature  of  the  re- 
mainder of  the  plant  used  will  have  an  effect  upon 
the  decision. 

No  very  satisfactory  mechanical  equipment  has 
been  developed  for  handling  cement  from  cars  to 
storage  and  into  the  haulage  units.  For  sacked 
cement  manually  operated  two-wheel  trucks  have 
proved  the  most  satisfactory.  Some  progress  has 
been  made  in  the  use  of  mechanical  appliances  but 
at  best  the  handling  of  the  cement  is  expensive. 
Bulk  cement  has  been  found  practicable  when 
shipped  either  in  box  cars  or  in  open  top  gondolas 
protected  by  tarpaulins.  When  shipped  in  box  cars, 
handling  is  accomplished  with  a  power  scoop  draw- 
ing the  material  through  the  door  of  the  car  into 
the  boot  of  a  conveyor.  When  received  in  gon- 
dolas the  material  is  handled  by  locomotive  crane 
or  derrick  equipped  with  clamshell  bucket. 

In  case  materials  of  construction  are  not  stored 
on  the  sub-grade  concentrated  storage  at  one  point 
or  at  several  points  along  the  line  of  the  road  must 
be  adopted.  Not  only  does  this  change  the  system 

41 


of  operation  but  it  increases  the  amount  of  railroad 
track  facilities  required  to  complete  a  project.  If 
the  mixer  is  charged  by  wheelbarrows  or  with  the 
mixer  loader,  it  is  not  uncommon  to  see  materials 
distributed  for  from  one-half  to  two  miles,  ready  to 
be  placed  in  the  mixer.  This  equals  1500  to  8000 
cubic  yards  of  aggregate  or  sufficient  materials  to 
carry  on  the  operation  from  one  week  to  one 
month.  Cement  storage  may  be  available  in  barns 
along  the  line  of  the  work.  The  storage  space  re- 
quired at  the  railroad  siding  under  this  method  of 
construction  therefore  is  small. 

If  the  materials  are  to  be  kept  off  the  sub-grade, 
all  this  is  changed.  Facilities  must  be  provided 
at  the  railroad  for  a  large  amount  of  material.  It  is 
probable  that  the  economy  resulting  justifies  the 
added  expenditure  for  plant,  yet  the  new  condition 
must  be  studied  closely  to  determine  whether 
available  facilities  are  sufficient  to  operate  economi- 
cally or  whether  it  is  necessary  to  increase  the  ex- 
isting trackage  or  build  sidings  at  another  point. 

In  order  to  bring  out  more  clearly  the  method  of 
designing  such  a  plant  an  assumed  job  will  be  dis- 
cussed. On  this  project  there  is  sixteen  miles  of 
sixteen  foot  road,  six  inches  thick  at  the  sides  and 
eight  inches  thick  at  the  center.  Proportions  speci- 
fied are  one  part  cement,  one  and  one-half  part  sand 
and  three  parts  stone.  Further,  because  of  the 
peculiar  railroad  situation  it  is  necessary  to  haul 
materials  for  the  whole  sixteen  miles  from  one  point 
near  the  center  of  the  section.  Based  on  experi- 
ence in  highway  work,  it  is  reasonable  to  believe 
that  there  will  be  an  average  of  twenty  working 
days  per  month,  this  taking  into  consideration  Sun- 
days and  rainy  days  but  not  considering  any  delays 
due  to  lack  of  materials.  The  experience  gained  in 
1920  shows  that  there  should  be  at  least  one 
month's  supply  of  materials  on  hand  at  all  times  if 
this  progress  is  to  be  maintained  and  that  there 
will  be  times  after  the  start  of  the  shipping  season 
for  aggregate  when  two  month's  supply  may  have 
to  be  stored. 

42 


Table  No.  5  shows  the  quantity  of  materials 
required  per  hour,  day,  week  and  month. 

Table  No.  6  gives  the  number  of  cars  required 
per  day  and  per  month  for  the  three  sizes  of  pav- 
ing mixers. 

The  basis  on  which  these  tables  have  been  pre- 
pared is  an  average  production  of  thirty  batches 
per  hour  for  eight  working  hours,  six  days  per 
week.  It  is  appreciated  that  with  proper  organiza- 
tion this  can  be  pushed  up  to  four  hundred  batches 
in  a  ten  hour  day  without  great  difficulty  or  at  the 
rate  of  forty  batches  per  hour;  yet  considering  the 
delays  to  which  such  a  project  is  subjected  it  seems 
reasonable  to  adopt  thirty  batches  per  hour  over  an 
eight  hour  day  as  a  basis  on  which  to  calculate  the 
quantity  of  storage  space  required. 

The  railroad  facilities  will  be  controlled  by  the 
maximum  number  of  cars  to  be  received  per  day. 
As  there  is  a  tendency  toward  bunching  it  is  evi- 
dent that  trackage  must  be  provided  for  at  least 
twice    the    daily    requirement.      The    quantity    of 
trackage  required  for  each  individual  job  will  de- 
pend upon  the  switching  service  rendered  by  the 
railroad  and  the  distance  to  yards  of  sufficient  ca- 
pacity to  absorb  the  bunching  of  materials.     With 
the  average  project  located  at  a  considerable  dis- 
tance from  a  large  city  or  division  point  it  is  not 
probable  that  there  will  be  made  available  more 
than  two  car  deliveries  per  day,  and  materials  will 
be  placed  in  considerable  quantity  only  once  a  day. 
One  of  these  switches  will  come  in  in  the  morning 
and  the  other  either  later  in  the  day  or  at  night. 
This  requires  that  space  be  made  available  for  at 
least  twelve  cars  if  a  14E  paver  is  used,  eighteen 
cars  if  a  21E  paver  is  used,  and  twenty-nine  cars  if 
a  32E  paver  is  used.    Some  leeway  must  be  given, 
so  that  the  empty  cars  can  be  pushed  out  of  the 
way.    Assuming  40  feet  per  car,  and  that  it  is  neces- 
sary to  have  a  tail  track  capacity  for  at  least  fifty 
per  cent  of  the  cars,  720  feet  of  track  is  required 
for  a  14E  paver,  1080  feet  of  track  for  21E  paver 
and  1740  feet  of  track  for  a  32E  paver.    If  switch- 

43 


ing  facilities  are  better  than  here  given  this  quan- 
tity of  track  may  be  cut  in  half. 

Table  No.  5 

Minimum  Quantity  of  Storage  Required  for  Eco- 
nomical Operation  of  Highway  Project 

Mix  1-11/2-3. 


Machine 

Quantity 
pef  Hour 

Quantity 
per  day 

Quantity 
per  6  Days 

Quantity 
per  20  Days 

cement 
14E  sand 
stone 

30  bbls. 
6.66cu.yd. 
13.33  cu.  yd. 

240  bbls. 
53.3  cu  yd. 
106.6  cu.  yd. 

1440  bbls. 
320  cu.  yd. 
640  cu.  yd. 

4800  bbls. 
1066  cu.  yd. 
2132  cu.  yd. 

cement 
21  E  sand 
stone 

45  bbls. 
10  cu.  yd. 
20  cu.  yd. 

360  bbls. 
80  cu.  yd. 
160  cu.  yd. 

2160  bbls. 
480  cu.  yd. 
960  cu.  yd. 

7200  bbls. 
1600  cu.  yd. 
3200  cu.  yd. 

Tcement 
32E  sand 
stone 

67.5  bbls. 
15  cu.  yd. 
30  cu.  yd. 

540  bbls. 
120  cu.  yd. 
240  cu.  yd. 

2890  bbls. 
720  cu.  yd. 
1440  cu.  yd. 

11800  bbls. 
2400  cu.  yd. 
4800  cu.  yd 

Table  No.  6 

Cars  of  Materials  Required  per  Day  and  per  Month 
for  Three  Sizes  of  Pavers 

Mix  1-11/2-3. 
14-E  PAVER 


Cars  per  Day: 

Cars  per  Month: 

1  car 

cement 

19  cars 

sand  .... 

2  cars 

sand  

.  .  36  cars 

stone 

4  cars 

stone 

72  cars 

21-E  PAVER 


cement 

1  1/2  cars 

cement 

30  cars 

sand  

21/2  cars 

sand  »,  

50  cars 

stone 

5  cars 

stone    . 

100  cars 

32-E  PAVER 


cement 2-1/6  cars 

sand 4  cars 

stone 8  cars 


cement . 
sand. .  . 
stone. . 


43  cars 

80  cj-rs 

.  .  160  cars 


Table  No.  7 

Minimum  Trackage  Required  for 
Economical  Operation 


14E 

21E 

32E 

Minimum    side    track    space 
„    required      for      daily     car 
i    storage  

280  ft. 
720  ft. 

400  ft. 
1080  ft. 

600  ft. 
1740  ft. 

Recommended    track    space 
for    economical    operation 
One    switch    per    day  —  by 
railroad 

44 


As  very  few  individual  sidings  exist  with  this 
capacity  which  are  not  in  constant  use,  the  con- 
tractor may  be  forced  to  build  one  for  himself. 
If  so,  the  expense  of  this  must  be  taken  into  con- 
sideration at  the  time  of  submitting  his  bid  and  the 
total  expense  charged  against  the  job. 

From  the  above  figures  the  necessity  for  a  large 
storage  area  and  sufficient  trackage  is  evident. 

Rehandling  Materials 

The  handling  of  this  material  from  cars  to  stor- 
age piles  is  easily  accomplished  with  the  crane,  but 
the  next  step  is  of  equal  importance  if  the  opera- 
tion is  to  prove  financially  successful.  How  best  to 
re-handle  the  materials  into  haulage  units  for  trans- 
portation to  the  mixer  is  the  problem.  Three 
types  of  equipment  are  in  general  use, — first,  fixed 
bins;  second,  portable  bins  on  wheels;  third,  tun- 
nels. The  last  of  these  has  not  been  used  extens- 
ively except  for  projects  equipped  with  industrial 
railroad.  The  relative  cost  of  the  three  methods 
is  in  accordance  with  the  order  in  which  they  are 
given  above.  The  economy  of  each  is  so  depend- 
ent upon  the  amount  of  work  to  be  completed  that 
it  is  not  practicable  to  discuss  their  relative  effi- 
ciency at  this  time.  When  bins  are  adopted  they 
should  have  a  capacity  of  at  least  two  hours  run, 
so  that  no  delays  will  result  in  case  the  crane  is  em- 
ployed handling  cars  at  the  other  end  of  the  pile, 
and  that  short  stoppages  due  to  unforseen  condi- 
tions can  be  bridged. 

Below  is  given  the  recommended  capacity  for 
bins  of  each  size  of  mixer. 

Table  No.  8 

Minimum  Capacity  of  Material  Bins 
Based  on  2  hours  supply  for  mixer 


14E 

21E 

32E 

Sand 
Stone 

13  y2  cu.  yd. 
27       cu.  yd. 

20  cu.  yd. 
40  cu.  yd. 

30  cu.  yd. 
60  cu.  yd. 

Bins  of  the  portable  type  can  be  mounted  either 
on  railroad  or  road  wheels,  so  that  they  may  move 

45 


as  required  by  the  condition  of  the  storage  piles. 
This  moving  will  actually  be  done  seldom,  as  under 
normal  conditions  material  will  be  handled  from 
cars  to  bins  without  rehandling  and  storing.  If  the 
material  is  used  from  storage  there  will  be  suffi- 
cient of  it  within  the  reach  of  the  crane  to  keep  the 
operation  going  for  at  least  one-half  day  without 
changing  the  location  of  the  bins. 

Drag  scrapers  operated  by  a  light  hoist  have 
proved  economical  for  cleaning  up  the  piles  when 
materials  are  deposited  beyond  the  reach  of  the 
crane. 

Ha  u  lage^  Un  its 

Haulage  units  may  naturally  be  divided  into 
two  distinct  classes;  first,  trucks  and  second,  indus- 
trial railroad.  Ten  years  ago  teams  had  a  large 
place  in  hauling  on  highway  construction  work. 
This,  however,  has  changed  until  their  use  is  so 
limited  that  there  seems  to  be  no  necessity  for  dis- 
cussing them  here. 

Trucks  again  may  be  divided  into  heavy  trucks 
— three  tons  and  over, — and  light  trucks,  of  one  and 
one-half  ton  capacity.  In  the  past  the  tendency  has 
been  to  use  the  five-ton  truck  for  hauling  materials. 
The  only  objection  to  this  unit  has  been  the  tend- 
ency to  cut  up  the  grade  and  the  difficulty  of  its 
use  under  anything  but  the  best  of  road  conditions. 
During  the  last  two  years,  therefore,  a  number  of 
contractors  have  adopted  lighter  trucks  equipped 
with  pneumatic  tires.  These  are  easily  handled, 
can  go  over  the  road  rapidly  and  do  not  cut  up  the 
grade  as  much  as  do  the  larger  trucks.  They  have 
a  big  disadvantage,  however,  in  the  labor  involved 
per  ton  of  material  hauled.  About  all  that  can  be 
said  concerning  the  size  of  truck  to  adopt  is  that 
it  will  depend  entirely  on  the  condition  of  the  roads 
on  which  the  hauling  is  to  be  done,  the  method  of 
handling  the  work,  and  length  of  haul. 

The  use  of  industrial  railroad  is  comparatively 
new  to  the  highway  construction  industry.  True, 
it  was  used  some  years  ago  but  not  extensively  and 
it  was  only  in  1919  that  the  present  system  of  use 

46 


was  developed.  The  use  of  batch  boxes,  two  boxes 
to  a  car,  two-foot  gauge  equipment,  and  either  gaso- 
line or  steam  locomotives  has  become  practically 
standard  practice.  At  the  loading  station,  the  batch 
is  prepared,  the  proper  amount  of  cement,  sand  and 
stone  being  put  into  the  batch  box  and  hauled  in 
its  dry  state  to  the  paving  mixer  to  be  mixed  and 
placed  on  the  road. 

The  only  criticism  of  this  system  is  the  fact  that 
any  delay  in  the  transportation  results  in  a  direct  de- 
lay to  the  mixer.  In  highway  work  the  contractor  re- 
ceives no  remuneration  until  the  concrete  has  passed 
through  the  mixer  and  is  in  place  on  the  road. 

There  are  three  other  methods  of  handling  ma- 
terials: first  by  trucks  direct  from  the  railroad  sid- 
ing to  the  sub- grade,  from  which  the  material  is  re- 
handled  into  the  mixer;  second,  the  handling  of  it 
in  the  same  manner  from  stock  piles  at  distances  of 
from  five  hundred  feet  to  one  mile;  and  third,  the 
use  of  batch  boxes  on  flat  bed  trucks,  hauling  over 
the  completed  concrete  and  transferring  the  batch  to 
industrial  cars  for  hauling  along  the  concrete  already 
placed  but  not  yet  sufficiently  hardened  to  be  used. 

This  system  appears  to  combine  the  advantages 
of  both  types  of  haulage  equipment.  In  the  first 
place  the  truck  has  the  opportunity  to  travel  on  a 
hard  surfaced  road.  In  the  second  place,  the  length 
of  the  industrial  railroad  (and  the  delays  incident 
to  an  industrial  railroad  vary  at  least  directly  as  its 
length)  is  reduced  to  not  to  exceed  two  miles  and 
probably  not  to  exceed  one  and  one-half  miles. 

Mixer  Plant 

The  type  and  size  of  paving  mixer  to  adopt  will 
depend  almost  entirely  on  the  amount  of  road  to  be 
placed  in  one  season,  but  will  be  affected  by  the 
method  of  charging  the  mixer. 

The  central  mixing  plant  has  been  used  on  a 
number  of  highway  projects.  Yet  the  cost  of 
hauling  the  concrete  as  opposed  to  hauling  the  dry 
batch,  in  addition  to  the  other  costs  of  this  method 
seems  to  be  such  as  to  make  this  method  less  effi- 
cient than  the  use  of  a  paving  mixer  on  the  sub- 

47 


grade.  Undoubtedly  the  boom  and  automatic  dis- 
tributing bucket  is  the  only  method  which  has  been 
evolved  for  distributing  concrete  in  place  in  the 
proper  condition  to  obtain  the  maximum  strength. 
It  is  very  desirable  that  after  the  concrete  leaves 
the  drum  of  the  mixer  it  be  put  into  its  final  place 
rapidly.  By  so  doing  less  water  can  be  used  than 
would  be  necessary  if  the  concrete  were  hauled  and 
the  resulting  concrete  will  be  denser  and  more 
homogeneous. 

Of  the  four  sizes  of  paving  mixers  it  is  probable 
that  the  No.  14E  will  remain  the  popular  machine 
for  any  but  the  small  or  large  contracts.  On  the 
small  contracts  the  10E  will  be  popular  while  on 
the  large  contracts  the  support  will  be  divided  be- 
tween the  21E  and  the  32E.  The  decision  as  to 
which  of  these  sizes  should  be  used  rests  entirely 
upon  the  remaining  equipment  and  organization  of 
the  contractor. 

Pump  and  Water  Line 

Rapid  highway  construction  necessitates  suffi- 
cient water  at  all  times  to  insure  water  for  the 
mixer,  and  for  sprinkling  and  curing,  as  well  as 
water  for  steam  purposes  for  the  other  pieces  of 
equipment  on  the  project.  Necessarily  this  requires 
a  pump  which  automatically  regulates  the  quantity 
forced  into  the  pipe  depending  upon  the  amount 
used.  The  mistake  has  very  often  been  made  of 
using  too  small  a  pipe  line  on  construction  work. 
It  is  recommended  that  no  pipe  line  less  than  two 
inches  be  adopted  and  that  for  distances  of  over 
one  mile  that  two  and  one-half  inches  be  adopted. 
The  quantity  of  water  required  to  carry  on  a  pro- 
ject is  as  follows: 

For  mixer 10  gallons  per  sq.  yd. 

For  sprinkling  and  curing . .  25  gallons  per  sq.  yd. 

Additional  for  miscellaneous 

equipment 10  gallons  per  sq.  yd. 

It  is  recommended  that  a  pump  of  a  capacity 
sufficient  to  give  thirty  pounds  pressure  at  the 
mixer  be  furnished.  The  graph  and  table  may  be 
used  in  determining  the  size  of  pipe  to  use. 

49 


Table  No.  9 

Size  of  Pipe  Required  for  Varying  Length  and  Head 


50 


Use  of  Tables 

An  example  of  the  use  of  Table  No.  9  is  as 
follows : 

Required  the  size  of  pipe  for  delivery  of  40  gal- 
lons of  water  per  minute  through  9800  feet  of  pipe 
to  an  elevation  of  320  feet  above  the  water  supply. 
Solution — Under  the  heading  of  40  gallons  locate 
9800  feet.  On  this  line  and  in  column  marked  Ele- 
vation find  200  feet.  2-inch  pipes  should  therefore 
be  used. 

Table  may  also  be  used  as  follows: 

Problem — How  much  water  will  the  Koehring 
steam  pump  deliver  through  4200  feet  of  1%-mch 
pipe  against  a  total  head  of  110  feet.  To  obtain 
this  note  column  marked  1%-inch  pipe.  In  this 
column  locate  4400  and  on  this  line  in  column 
marked  Elevation  read  100.  Therefore  the  delivery 
under  stated  length  will  be  35  gallons  per  minute. 

The  same  data  can  be  obtained  by  use  of  Figure 
No.  1.  Examples  of  the  use  of  these  figures  are 
given  as  follows:  Example  1 — What  size  of  pipe 
is  required  to  deliver  50  gallons  per  minute  320  feet 
above  and  75100  feet  from  the  pump,  suction  lift 
being  22  feet? 

Solution: — Total  head  equals  320  plus  22  or 
342  feet.  Locate  7500  on  upper  pipe  scale  and  342 
on  vertical  scale  on  the  right.  The  intersection  of 
these  two  lines  is  near  the  2% -inch  pipe  50  gallon 
curve.  Hence  2y2-inch  pipe  is  required. 

EXAMPLE  2 — How  much  will  a  2-inch  pipe 
deliver  at  342  feet  head  and  7500  feet  length? 

Solution: — Locate  7500  on  lower  pipe  scale  and 
342  on  vertical  scale  on  the  left.  The  intersection 
of  the  two  lines  is  near  the  2-inch  pipe  40-gallon 
curve.  Hence  nearly  40  gallons. 

EXAMPLE  3— Describe  the  length  of  2-inch 
pipe  that  can  be  used  to  deliver  40  gallons  per  min- 
ute against  a  420-foot  head. 

Solution: — Note  where  curve  marked  2  inches 
40  gallons  intersects  with  the  line  denoting  420- 

61 


52 


foot  head.    From  that  point  drop  down  to  the  pipe 
scale  and  read  the  answer,  5000  feet. 

Reference  to  Figure  No.  1  shows  the  method  of 
obtaining  length  of  pipe,  total  head,  and  discharge 
head,  which  information  is  used  in  determining 
size  of  pipe,  or  the  quantity  of  water  which  will 
flow  through  a  pipe  of  a  given  size. 

Forms  and  Finishing 

There  is  little  to  be  said  concerning  the  type  of 
forms  to  adopt.  Steel  forms  have  proven  so  much 
better  than  wood  forms  that  they  are  recommend- 
ed. With  the  general  adoption  of  machine  finish- 
ing it  is  desirable  that  these  forms  be  sufficiently 
stiff  to  withstand  the  strains  set  up  by  the  vibra- 
tion as  well  as  the  weight  of  the  machine.  The 
finishing  of  concrete  is  one  of  those  items  which, 
although,  it  is  not  a  major  item  of  cost  is  import- 
ant, as  it  materially  affects  the  riding  qualities  of 
the  road.  In  case  a  machine  is  used  it  is  essental 
that  the  forms  be  kept  clean,  so  that  the  wheels 
carrying  the  machine  will  always  be  at  the  same 
relative  elevation  and  will  not  be  forced  to  rise 
over  the  concrete,  therefore  giving  a  wavy  surface. 
Where  roller  and  belt  is  used  care  should  be  taken 
to  make  sure  that  the  finishing  is  not  completed  too 
quickly  after  depositing  the  concrete. 

Organization  of  Crew 

The  mixer  capacity  controls  the  size  of  the 
crew  on  all  other  parts  of  the  work  if  the  plant  is 
properly  balanced.  Otherwise,  the  output  of  the 
mixer  is  controlled  by  the  capacity  of  the  slowest 
unit.  The  whole  idea  in  organization  of  a  highway 
construction  crew  is  that  of  efficiency,  time  against 
production.  Without  efficiency,  and  efficiency 
means  the  balancing  of  all  labor  going  into  the 
production  of  a  road,  costs  are  going  to  go  very 
high.  It  must  be  appreciated  that  a  highway  pave- 
ment is  a  long,  thin,  narrow  strip  for  which  the 
contractor  receives  a  small  remuneration  per  run- 
ning foot.  When  it  is  made  clear  that  a  14E  paver 
has  a  capacity  of  about  one  and  one-half  to  two 

53 


feet  of  road  per  batch,  the  necessity  is  apparent  for 
organizing  the  crew  throughout  in  a  way  that  each 
action  is  the  most  effective  and  can  be  repeated 
economically  3000  times  in  the  completion  of  a 
mile  of  road. 

The  batch  meter,  with  which  all  concrete  mixers 
may  be  equipped,  assists  in  this  standardization  of 
operation.  This  is  an  instrument  attached  to  the 
mixer  which  controls  the  time  the  material  remains 
in  the  drum,  automatically  locking  the  discharge 
chute  as  the  charging  skip  reaches  the  top  of  its 
travel  and  releasing  the  discharge  upon  the  expira- 
tion of  the  controlled  time.  Economy  of  organiza- 
tion can  best  be  effected  by  basing  the  crew  on  the 
output  of  the  mixer  controlled  by  the  meter. 

Balancing  of  Plant 

Not  only  is  it  necessary  that  the  crew  be  bal- 
anced, but  it  must  be  balanced  in  relation  to  the 
plant,  otherwise  there  cannot  be  true  coordination 
which  results  in  profits  at  the  end  of  the  project. 
From  the  receipt  of  materials  through  the  hand- 
ling, storage,  hauling,  mixing  and  placing,  it  is 
essential  that  the  capacity  of  one  machine  fit  the 
capacity  of  the  other. 

If  this  is  done  and  there  is  proper  organization 
of  the  labor,  the  advantage  in  cost  is  going  to  ac- 
crue to  that  contractor  who  has '  equipped  himself 
with  large,  efficient  machinery. 

Cold  Weather   Work 

The  construction  of  concrete  pavements  is  not 
recommended  during  freezing  weather.  It  is  some- 
times necessary  or  desirable,  however,  to  complete 
a  small  section  under  unfavorable  weather  condi- 
tions in  order  that  an  entire  stretch  of  pavement 
may  be  thrown  open  to  use.  The  fundamental  pre- 
cautions to  be  observed  when  concreting  is  done 
under  such  conditions  is  to  maintain  a  certain  de- 
gree of  warmth  in  and  in  the  presence  of  the  con- 
crete until  it  has  completed  early  hardening  and 
will  be  proof  against  injury  from  freezing. 

54 


Concrete  should  not  be  placed  on  a  frozen  sub- 
grade.  All  materials  excepting  the  cement  should 
be  heated  so  that  when  the  concrete  is  mixed  it  will 
have  a  sufficiently  high  temperature  that  the  hard- 
ening process  may  proceed  sufficiently  not  to  be 
damaged  by  frost.  It  should  be  placed  quickly  and 
at  once  protected  to  prevent  loss  of  the  heat.  Com- 
pleted work  can  be  housed  in  by  using  light 
frames  covered  with  canvas,  or  by  covering  the 
pavement  with  a  layer  of  hay  or  straw,  a  foot  or 
more  thick,  after  the  concrete  has  hardened  suffi- 
ciently to  prevent  damage  to  the  surface  from  con- 
tact with  this  covering.  A  one-inch  layer  of  saw- 
dust with  canvas  over  the  top  has  been  found  very 
satisfactory  when  this  means  of  protection  is  ob- 
tainable and  the  degree  of  cold  to  be  protected 
against  will  not  exceed  three  or  four  degrees  be- 
low freezing. 

Curing 

One  of  the  most  important  features  of  concrete 
pavement  construction  is  proper  protection  of  the 
concrete  while  hardening.  As  soon  as  it  has  been 
finished,  the  work  should  be  covered  with  canvas 
stretched  on  light  frames  to  prevent  rapid  evapora- 
tion of  water.  After  hardening  has  advanced  suffi- 
ciently to  permit  an  earth  covering  being  thrown 
on  without  damage  to  the  surface,  at  least  two 
inches  of  such  covering  should  be  applied  and  be 
kept  wet  by  frequent  sprinkling  for  a  period  of  ten 
days  or  more,  depending  upon  weather  and  tem- 
perature conditions.  Hardening  should  be  allowed 
to  progress  slowly  and  uniformly. 

Where  possible  to  arrange  for  it,  the  most  satis- 
factory method  of  curing  concrete  pavements  is  to 
pond  them.  This  consists  of  keeping  them  covered 
with  about  two  inches  of  water  retained  by  earth 
dams  built  across  the  pavement  at  suitable  inter- 
vals. Flooding  is  generally  done  in  the  evening 
when  the  water  is  not  needed  for  the  mixer  and  is 
kept  at  a  minimum  depth  of  two  inches  over  the 
crown  of  the  pavement  for  at  least  ten  days. 

55 


Maintenance  of  Concrete  Pavements 

With  passage  of  time  it  becomes  necessary  to 
give  attention  to  maintenance,  although  well  built 
concrete  pavements  require  less  maintenance  than 
any  other  type  of  pavement.  Nevertheless,  such 
maintenance  as  is  required  must  be  regularly  and 
systematically  given.  This  in  general  includes  fill- 
ing joints  and  cracks  with  tar  or  asphalt  and  repair 
of  spots  which  result  from  local  disintegration  due 
to  clay  balls  or  other  foreign  materials  in  the  con- 
crete, or  to  pitting  from  freezing  where  the  con- 
crete was  not  properly  protected  while  undergoing 
early  hardening. 

The  materials  required  for  maintaining  concrete 
pavements  are  portland  cement,  sand,  stone  and 
bitumen.  The  last  may  be  some  one  of  the  coal  tar 
or  asphaltic  products.  Demand  for  these  for  the 
purpose  mentioned  has  resulted  in  the  preparation 
of  several  standard  commercial  products  now  on 
the  market.  Care  should  be  taken  that  the  prep- 
arations are  used  in  accordance  with  the  manufac- 
turer's recommendations,  since  some  are  intended 
to  be  applied  hot  and  others  cold.  Overheating  the 
hot  preparations  in  general  destroys  their  ef- 
fectiveness. 

But  little  equipment  and  few  tools  are  needed 
for  the  simple  maintenance  work  concrete  pave- 
ments require.  A  kettle  to  heat  tar,  a  can  to  pour 
it  in  the  cracks  or  holes,  a  stiff  broom  for  sweeping 
out  cracks  and  some  kind  of  a  hooked  tool,  similar 
to  a  stove  poker  but  with  sharp  point,  may  be  used 
to  scrape  out  compacted  foreign  matter  from  joints 
or  cracks.  For  convenience  in  removing  the  tar 
heater,  it  is  generally  mounted  on  wheels,  and 
where  there  is  considerable  mileage  to  maintain, 
the  outfit  is  usually  moved  by  means  of  a  small 
motor  truck. 

Examples  of  Use  of  Tables  lO^and  11 

Tables  10  and  11  have  been  prepared  with  the 
belief  that  there  is  a  need  for  a  table  giving  the 
quantity  of  concrete  per  foot  and  per  mile  of  con- 

66 


crete  pavement  and  base.  These  tables  are  given 
for  each  inch  of  thickness,  from  4  inches  uniform  to 
8  inches  at  the  sides  and  10  inches  at  the  center. 

In  table  No.  11  the  quantity  of  cement,  sand  and 
stone  for  each  thickness,  width  and  mixture  is 
given.  All  calculations  are  based  on  quantities 
taken  from  Taylor  and  Thompson. 

It  will  be  noticed  that  in  the  first  column  three 
figures  are  given — the  first  is  the  thickness  at  the 
edge — the  next  the  thickness  at  the  center  and  the 
third  the  thickness  of  a  uniform  slab  with  equal 
cross  section  area. 

As  all  pavements  are  built  with  curved  crowns, 
the  difference  between  the  thickness  given  and  the 
average  of  the  two  thicknesses  is  due  to  the  greater 
cross  sction  resulting  from  the  use  of  a  curve.  For 
example,  a  pavement  6  inches  thick  at  the  side  and 
8  inches  thick  at  the  center  has  a  cross  section  area 
equal  to  a  pavement  7%  inches  thick  and  not  one 
7  inches  thick. 

Example — To  obtain  the  quantity  of  concrete 
per  linear  foot  and  per  mile  of  a  pavement  18  feet 
wide  7  inches  thick  at  the  edge  and  8  inches  thick 
at  the  center,  follow  along  the  width  until  18  feet  is 
reached.  Then  follow  down  the  column  until  the 
line  headed  7-8-7%  is  reached  and  read  .426  cubic 
yards  per  linear  foot  or  2249.28  cubic  yards  per 
mile.  If,  on  the  other  hand,  one  is  desirous  to  as- 
certain the  quantity  of  cement,  sand  and  stone  re- 
quired for  this  pavement,  using  a  1-2-3  mixture,  re- 
fer to  table  No.  11 — under  1-2-3  mixture — Follow 
down  18  foot  column  to  point  opposite  7-8-7%  and 
read  .741  bbls.  of  cement  per  foot,  .23  cubic  yards 
of  sand  per  foot  and  .33  cubic  yards  of  stone  per 
foot.  In  like  manner  the  quantities  of  material  re- 
quired per  mile  are  3913  barrels  of  cement, — 1192 
cubic  yards  of  sand  and  1732  cubic  yards  of  stone. 


67 


Table  No.  10 


CUBIC  YARDS  OF  CONCRETE  PER  LINEAR  FOOT 
AND  PER  MILE  OF  PAVEMENT 


Thickness 

Pavement 

Width  Pavement  Feet 

Inches 

| 

Per 
Lin. 

So    "S      § 

Foot 

9' 

10' 

12' 

14' 

16' 

18' 

3   QJ    < 

Per 

Mile 

444 

Foot 

.111 

.123 

.148 

.173 

197 

.222 

Mile 

586.08 

649.44 

781.44 

913-44 

040  16 

1172.16 

4       5     4* 

Foot 

.130 

.144 

.173 

.201 

.230 

.259 

Mile 

686. 

760.32 

913.44 

1061.28 

1214.40 

1367.52 

4       6     5H 

Foot 

.148 

.164 

.197 

.230 

263 

.296 

Mile 

781.44 

865.92 

1040.16 

1214.40 

1388.64 

1562.88 

5       5     5 

Foot 

.139 

.154 

.185 

.216 

.247 

.278 

Mile 

733.92 

813.12 

976.80 

114048 

1304.16 

1467.84 

5      6     5% 

Foot 

.157 

.175 

.210 

.245 

.280 

.314 

Mile 

828.% 

924.. 

1108.80 

1293.60 

1478.40 

1657.92 

5       7     6^ 

Foot 

.176 

.195 

.234 

.274 

.313 

.352 

Mile 

929.28 

1029.60 

1235.52 

1446.72 

1652.64 

1858.56 

5      8     7 

Foot 

.194 

.216 

.259 

.302 

.346 

.389 

Mile 

1024.32 

1140.48 

1367.52 

1594.56 

1826.88 

2053.92 

666 

Foot 

.167 

.185 

.222 

.259 

.296 

.333 

Mile 

881.76 

976.80 

1172.16 

1367.52 

1563.28 

1758.24 

6      7     6% 

Foot 

.185 

.205 

.247 

288 

.329 

.370 

Mile 

976.80 

1082.40 

1304.16. 

1520.64 

1737  12 

1953.60 

6      8     7>i 

Foot 

.204 

.227 

.271 

.317 

.362 

.407 

Mile 

1077.12 

1198.56 

1430.88 

1673.76 

1911.36 

2148.96 

698 

Foot 

.222 

.247 

.296 

.346 

.395 

.444 

Mile 

1172.16 

1304.16 

1562.88 

1826.88 

2085.60 

2344.32 

777 

Foot 

.194 

.216 

.259 

.302 

.346 

.389 

Mile 

1024.32 

1140.48 

1367.52 

1594.56 

1826.88 

2053.92 

7       8     7% 

Foot 

.213 

.236 

.284 

.331 

.378 

.426 

Mile 

1124.64 

1246.08 

1499.52 

1747.68 

1995.84 

2249.28 

7     9   JK 

Foot 

.231 

.257 

.309 

.360 

.411 

.463 

Mile 

1219.68 

1356.96 

1631.52 

1900.80 

2170.08 

2444.64 

7     K)     9 

Foot 

.250 

.278 

.333 

.389 

.444 

.500 

Mile 

1320. 

1467.84 

1758.24 

2053.92 

2344.32 

2640. 

888 

Foot 

.222 

.247 

.296 

.346 

.395 

.444 

Mile 

1172.16 

1304  16 

1562.88 

1826.88 

2085.60 

2344.32 

8      9     8% 

Foot 

.241 

.267 

.321 

.374 

.428 

.481 

Mile 

1272.48 

1409.76 

1694.88 

1974.72 

2259.84 

2539.68 

8     10     9x 

Foot 

.259 

.288 

346 

403 

.461 

.518 

Mile 

1367.52 

1520.64 

1826.88 

2127.84 

2434.08 

2735.04 

Table  No.  10 


CUBIC  YARDS  OF  CONCRETE  PER  LINEAR  FOOT 
AND  PER  MILE  OF  PAVEMENT 


Thickness 

Pavement 

Width  Pavement  Feet 

Inches 

».       & 

Per 
Lin. 

a   | 

Foot 

20' 

22' 

24' 

26' 

28' 

30' 

2    cj    < 

Per 

Mile 

444 

Foot 

.247 

.271 

.296 

.321 

.346 

.370 

Mile 

1304.16 

1430.88 

1563.28 

1694.88 

1826.88 

1953.60 

4       5     4« 

Foot 

.288 

.316 

.345 

.374 

.403 

.431 

Mile 

1520.64 

1668.48 

1821  60 

1974.72 

2127.84 

2275.68 

4       6     5^ 

Foot 

.329 

.362 

.395 

.428 

.461 

.494 

Mile 

1737.12 

1911.36 

2085.60 

2259.84 

2434.08 

2608.32 

5       5     5 

Foot 

.309 

.339 

370 

.401 

.432 

.463 

Mile 

1631.52 

1789.92 

1953.60 

2117.28 

2280.96 

2444.64 

5       6     5% 

Foot 

.349 

.384 

.419 

.454 

.489 

.524 

Mile 

1842.72 

2027.52 

2212  32 

2397.12 

2581  .92 

2766.72 

5       7     6M 

Foot 

.391 

.430 

.469 

.508 

.547 

.586 

Mile 

2064.48 

2270.40 

2476.32 

2682.24 

2888.16 

3094.08 

5       8     7 

Foot 

.432 

.475 

518 

.562 

.605 

.648 

Mile 

2280.96 

2508. 

2735  04 

2967.36 

3194.40 

3421.44 

666 

Foot 

.370 

.407 

.444 

.481 

.519 

.556 

Mile 

1953.60 

2148.% 

2344  32 

2539.68 

2740.32 

2935.68 

6       7     6^ 

Foot 

.411 

.452 

.493 

.534 

.576 

.617 

Mile 

2170.08 

2386.56 

2603.04 

2819.52 

3041.28 

3257.76 

6       8     7* 

Foot 

.452 

.498 

.543 

.588 

.633 

.679 

Mile 

2386.50 

2629.44 

2867  04 

3104.64 

3342.24 

3585.12 

6       9     8 

Foot 

.494 

.543 

.593 

.642 

.691 

.741 

Mile 

2608.32 

2867.04 

3131.04 

3389.76 

3648.48 

3912.48 

777 

Foot 

.432 

.475 

.518 

.562 

.605 

.648 

Mile 

2280.96 

2508. 

2735.04 

2967.36 

3194.40 

3421.44 

7       8     7^ 

Foot 

.473 

.520 

.567 

.615 

.662 

.709 

Mile 

2497.44 

2745.60 

2993.76 

3247.20 

3495.36 

3743.52 

7       9     8* 

Foot 

.514 

.566 

.617 

.668 

.720 

.      .771 

Mile 

2713.92 

2988.48 

3257.76 

3527.04 

3801.60 

4070.88 

7      10     9 

Foot 

.555 

.611 

667 

.722 

.778 

.833 

Mile 

2930.40 

3226.08 

3521.66 

3812.16 

4107.84 

4398.24 

8       8     8 

Foot 

.494 

.543 

.593 

.642 

.691 

.741 

Mile 

2608.32 

2867.04 

3131.04 

3389.76 

3648.48 

3912.48 

8       9     Sy3 

Foot 

.535 

.588 

.641 

.695 

.748 

.802 

Mile 

2824.80 

3104.64 

3384.48 

3669.60 

3949.44 

4234.56 

8      10     9n 

Foot 

.575 

.634 

.691 

.748 

.806 

.864 

Mile 

3036. 

3347.52 

3648.48 

3949.44 

4255.68 

4561.92 

59 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

l—llA—3  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.94  Barrels  Per  Cubic  Yard. 
Sand  Required: — .42  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required:— .84  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

£ 

«      £ 

•9     S     Z 
2    o    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.215 

1137 

.238 

1259 

.287 

1515 

.335 

1771 

.382 

2018 

.431 

2274 

SAND 

.05 

246 

.05 

273 

.06 

328 

.07 

383 

.08 

437 

.09 

492 

STONE 

.09 

492 

.10 

545 

.12 

656 

.15 

767 

.17 

874 

.19 

984 

4       5     4^ 

CEMENT 

.252 

1331 

.279 

1474 

.336 

1771 

.390 

2058 

.446 

2356 

.502 

2654 

SAND 

.05 

288 

.06 

319 

07 

383 

.08 

446 

.10 

510 

.11 

576 

STONE 

.11 

576 

.12 

638 

.14 

767 

.17 

891 

.19 

1020 

.22 

1149 

4       6     5^ 

CEMENT 

.287 

1515 

.318 

1680 

.382 

2018 

.446 

2355 

.510 

2695 

.574 

3032 

SAND 

.06 

328 

.07 

364 

08 

437 

.10 

510 

.11 

583 

.12 

656 

STONE 

.12 

656 

.15 

727 

.17 

874 

.19 

1020 

.22 

1167 

.25 

1313 

5       5     5 

CEMENT 

.270 

1424 

.299 

1577 

.359 

1895 

.419 

2213 

.479 

2530 

.539 

2848 

SAND 

.06 

308 

.06 

341 

.08 

410 

.09 

479 

.10 

548 

.12 

617 

STONE 

.12 

617 

.13 

683 

.16 

821 

.18 

958 

.21 

1095 

.23 

1233 

5       6     5^ 

CEMENT 

.305 

1608 

.340 

1793 

.407 

2151 

.475 

2510 

.543 

2868 

.609 

3218 

SAND 

.07 

348 

.07 

388 

.09 

466 

.10 

543 

.12 

621 

.13 

696 

STONE 

.13 

6% 

.15 

776 

.18 

932 

.21 

1087 

.24 

1242 

.26 

1393 

5       7     6H 

CEMENT 

.341 

1802 

.378 

1998 

.454 

2399 

.532 

2808 

.607 

3207 

.683 

3606 

SAND 

.07 

390 

.08 

433 

.10 

519 

.12 

608 

.13 

694 

.15 

781 

STONE 

.15 

780 

.16 

865 

.20 

1038 

.23 

1215 

.26 

1389 

.30 

1562 

5       8     7 

CEMENT 

.378 

1987 

.419 

2212 

.502 

2654 

.586 

3094 

.671 

3544 

.755 

3985 

SAND 

.08 

430 

.09 

479 

.11 

575 

.13 

670 

.15 

767 

.16 

863 

STONE 

.16 

860 

.18 

958 

.22 

149 

.25 

1340 

.29 

1535 

.33 

1725 

666 

CEMENT 

.324 

1711 

.359 

1895 

.431 

2275 

.502 

2654 

.574 

3032 

.646 

3411 

SAND 

.07 

370 

.08 

410 

.09 

492 

.11 

575 

.12 

656 

.14 

738 

STONE 

.14 

741 

.16 

821 

.19 

984 

.22 

149 

.25 

313 

.28 

M77 

6       7     6H 

CEMENT 

.359 

1895 

.398 

2099 

.479 

2530 

.559 

2951 

.638 

3370 

.718 

3791 

SAND 

.08 

410 

.09 

454 

.10 

548 

.12 

639 

.14 

730 

.16 

821 

STONE 

.16 

821 

.17 

909 

.21 

095 

.24 

278 

.28 

459 

.31 

641 

(10 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—1^2—3  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.94  Barrels  Per  Cubic  Yard. 
Sand  Required: — .42  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .84  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

o 

fc.           00 

&  %  g 

3   3   -5 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.479 

2530 

.526 

2776 

.574 

3032 

.622 

3288 

.671 

3544 

.716 

3791 

SAND 

.10 

548 

.11 

601 

.12 

656 

.13 

712 

.15 

767 

.16 

821 

STONE 

.21 

1095 

.23 

1202 

.25 

1313 

-.27 

1424 

.29 

1534 

.31 

1641 

4       5     4% 

CEMENT 

.559 

2951 

.613 

3236 

.669 

3535 

.726 

3832 

.782 

4128 

.836 

4415 

SAND 

.12 

639 

.13 

701 

.14 

765 

.16 

830 

.17 

894 

.18 

956 

STONE 

.24 

1278 

.27 

1401 

.29 

1530 

.31 

1659 

.34 

1788 

.36 

1912 

4       6     5H 

CEMENT 

.638 

3371 

.702 

3707 

.766 

4047 

.830 

4384 

.894 

4722 

.958 

5060 

SAND 

.14 

730 

.15 

803 

.17 

876 

.18 

949 

.19 

1022 

.21 

1095 

STONE 

.28 

1459 

.30 

1605 

.33 

1752 

.36 

1898 

.39 

2045 

.41 

2191 

5       5     5 

CEMENT 

.599 

3166 

.658 

3473 

.718 

3791 

.778 

4108 

.838 

4425 

.898 

4743 

SAND 

.13 

685 

.14 

752 

.16 

821 

.17 

889 

.18 

958 

.19 

1027 

STONE 

.26 

1371 

.28 

1504 

.31 

1641 

.34 

1778 

.36 

1916 

.39 

2054 

5       6     5fc 

CEMENT 

.677 

3576 

.745 

3935 

.813 

4291 

.881 

4650 

.949 

5009 

1.017 

5368 

SAND 

.15 

774 

.16 

852 

.18 

929 

.19 

1007 

.21 

1084 

.22 

1162 

STONE 

.29 

1548 

.32 

1704 

.35 

1858 

.38 

2013 

.41 

2169 

.44 

2324 

5       7     6n 

CEMENT 

.759 

4004 

.834 

4404 

.910 

4804 

.986 

5203 

1.060 

5603 

1.137 

6002 

SAND 

.16 

867 

.18 

953 

.20 

1040 

.21 

1126 

.23 

1213 

25 

1299 

STONE 

.33 

1734 

.36 

1915 

.39 

2080 

.43 

2253 

.46 

2426 

.49 

2599 

5       8     7 

CEMENT 

.838 

4426 

.922 

4867 

1.005 

5306 

1.090 

5756 

1.174 

6196 

1.257 

6636 

SAND 

.18 

958 

.20 

1053 

.22 

1149 

.24 

1246 

.25 

1341 

.27 

1437 

STONE 

.36 

1916 

.40 

2107 

.44 

2297 

.47 

2492 

.51 

2683 

.54 

2874 

666 

CEMENT 

.718 

3791 

.790 

4169 

.861 

4547 

.933 

4928 

1.007 

5316 

1.079 

5696 

SAND 

.16 

821 

.17 

903 

.19 

984 

.20 

1067 

.22 

1151 

.23 

1233 

STONE 

.31 

1641 

.34 

1805 

.37 

1969 

.40 

2134 

.44 

2302 

.47 

2466 

6       7     6*A 
CEMENT 

.797 

4210 

.877 

4631 

.956 

5048 

1.036 

5470 

1.117 

5900 

1.197 

6321 

SAND 

.17 

911 

.19 

1003 

.21 

1093 

.22 

1184 

.24 

1277 

.26 

1368 

STONE 

.35 

1823 

.38 

2005 

.41 

2186 

.45 

2369 

.48 

2554 

.52 

2737 

61 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 

ROADS,  STREETS  AND  ALLEYS 

1— 1H— 3  MIX. 

Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.94  Barrels  Per  Cubic  Yard. 
Sand  Required:— .42  Cubic  Yard  Per  Cubic  Yard. 
Stone  Required: — .84  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

&  i 

B    o    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7x 

CEMENT 

.396 

2089 

.438 

2314 

.525 

2776 

.615 

3248 

.702 

3707 

.790 

4169 

SAND 

.09 

452 

.09 

501 

.11 

601 

.13 

703 

.15 

803 

.17 

903 

STONE 

.17 

905 

.18 

1002 

.23 

1202 

.27 

1406 

.30 

1605 

.34 

1805 

698 

CEMENT 

.431 

2274 

.480 

2530 

.574 

3032 

.671 

3544 

.766 

4047 

.861 

4547 

SAND 

.09 

492 

.10 

548 

.12 

656 

.15 

767 

.17 

876 

.19 

984 

STONE 

.19 

984 

.21 

1095 

.25 

1313 

.29 

1535 

.33 

1752 

.37 

1969 

7       7     7 

CEMENT 

.388 

1986 

.419 

2212 

.502 

2654 

.586 

3094 

.671 

3544 

.755 

3985 

SAND 

.08 

444 

.09 

479 

.11 

575 

.13 

670 

.15 

767 

.16 

863 

STONE 

.17 

887 

.18 

958 

.22 

1149 

.25 

1340 

.29 

1535 

.33 

1725 

787% 

CEMENT 

.413 

2183 

.458 

2417 

.551 

2910 

.642 

3391 

.733 

3872 

.826 

4363 

SAND 

.09 

473 

.10 

523 

.12 

630 

.14 

734 

.16 

838 

.18 

944 

STONE 

.18 

945 

.20 

1047 

.24 

1260 

.28 

1468 

.32 

1677 

.36 

1889 

CEMENT 

.448 

2367 

.499 

2633 

.599 

3166 

.698 

3688 

.797 

4210 

.898 

4743 

SAND 

.10 

512 

.11 

570 

.13 

685 

.15 

798 

.17 

911 

.19 

1027 

STONE 

.19 

1025 

.22 

1140 

.26 

1371 

.30 

1597 

.35 

1823 

.39 

2054 

7     10     9 

CEMENT 

.485 

2561 

.539 

2848 

.646 

3411 

.755 

3985 

.861 

4547 

.970 

5122 

SAND 

.11 

554 

.12 

617 

.14 

738 

.16 

863 

.19 

984 

.21* 

1109 

STONE 

.21 

1109 

.23 

1233 

.28 

1477 

.33 

1725 

.37 

1969 

.42 

2218 

888 

CEMENT 

.431 

2274 

.480 

2530 

.574 

3032 

.671 

3544 

.766 

4047 

.861 

4547 

SAND 

.09 

492 

.10 

548 

.12 

656 

.15 

767 

.17 

876 

.19 

984 

STONE 

.19 

984 

.21 

1095 

.25 

1313 

.29 

1535 

.33 

1752 

.37 

1969 

898% 

CEMENT 

.468 

2468 

.518 

2735 

.623 

3288 

.726 

3832 

.830 

4384 

.933 

4928 

SAND 

.10 

534 

.11 

592 

.13 

712 

.16 

830 

.18 

949 

.20 

1067 

STONE 

.20 

1068 

.22 

1184 

.27 

1424 

.31 

1659 

.36 

1898 

.40 

2134 

8      10     9x 

CEMENT 

.502 

2654 

.559 

2951 

.671 

3544 

.782 

4128 

.894 

4722 

1.005 

5306 

SAND 

.11 

575 

.12 

639 

.15 

767 

.17 

894 

.19 

1022 

.22 

1149 

STONE 

.22 

1149 

.24 

1278 

.29 

1535 

.34 

1788 

.39 

2045 

.44 

2297 

62 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—1  ^—3  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.94  Barrels  Per  Cubic  Yard. 
Sand  Required: — .42  Cubic  Yard  Per  Cubic  Yard. 
Stone  Required; — .84  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

,    .       & 
o      S      2 

a  J  4 

Foot 

Mil 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8      ?H 

CEMENT 

.877 

463 

.966 

5100 

1.053 

5562 

1.141 

6024 

1.228 

6483 

1.317 

6955 

SAND 

.19 

1003 

.21 

1104 

.23 

1204 

.25 

1304 

.27 

1404 

.29 

1506 

STONE 

.38 

2005 

.42 

2208 

.46 

2408 

.49 

2608 

.53 

2807 

.57 

3011 

698 

CEMENT 

.958 

5060 

1.053 

5562 

1.150 

6074 

1.246 

6577 

1.341 

7077 

1.438 

7589 

SAND 

.21 

1095 

.23 

1204 

.25 

1315 

.27 

1424 

.29 

1532 

.31 

1643 

STONE 

.41 

219 

.46 

2408 

.50 

2630 

.54 

2848 

.58 

3064 

.62 

3286 

7       7     7 

CEMENT 

.838 

4426 

.922 

4867 

1.005 

5306 

1.090 

2756 

1.174 

6196 

1.257 

6636 

SAND 

.18 

958 

.20 

1053 

M 

1149 

.24 

1246 

.25 

1341 

.27 

1437 

STONE 

.36 

1916 

.40 

2107 

.44 

2297 

.47 

2492 

.51 

2683 

.54 

2874 

787% 

CEMENT 

.918 

4844 

1.009 

5327 

1.100 

5808 

1.193 

6299 

1.284 

6780 

1.375 

7263 

SAND 

.20 

1049 

.22 

1153 

.24 

1257 

.26 

1364 

.28 

1468 

.30 

1572 

STONE 

.-40 

2097 

.44 

2307 

.48 

2515 

.52 

2727 

.56 

2936 

.60 

3145 

7       9     8n 

CEMENT 

.997 

5265 

.098 

5797 

.197 

6321 

.296 

6842 

1.397 

7376 

1.496 

7898 

SAND 

.22 

140 

.24 

255 

.26 

1368 

.28 

481 

.30 

1597 

.32 

1710 

STONE 

.43 

2280 

.48 

2510 

.52 

2737 

.56 

2963 

.60 

3194 

.65 

3420 

7     10     9 

CEMENT 

.077 

czox 

.185 

6258 

.294 

6833 

.401 

7395 

1.509 

7970 

.616 

8532 

XXrt 

SAND 

.23 

231 

.26 

355 

.28 

479 

.30 

601 

.33 

725 

.35 

847 

STONE 

.47 

2461 

.51 

2710 

.56 

2958 

.61 

3202 

.65 

3451 

.70 

3694 

888 

CEMENT 

.958 

5060 

.053 

5562 

.150 

6074 

.246 

6577 

.341 

7077 

.438 

7589 

SAND 

.21 

095 

.23 

204 

.25 

1315 

.27 

424 

.29 

532 

.31 

643 

STONE 

.41 

2191 

.46 

2408 

.50 

2630 

.54 

2848 

.58 

3064 

.62 

3286 

«       9     8* 

CEMENT 

.038 

5481 

.141 

5024 

.244 

6565 

.348 

7120 

.451 

7661 

.556 

8216 

SAND 

.22 

187 

.25 

304 

.27 

1421 

.29 

541 

.31 

659 

.34 

779 

STONE 

.45 

2373 

.49 

2608 

.54 

2843 

.58 

3083 

.63 

317 

.67 

3557 

8      10     9M 
CEMENT 

.116 

5890 

.230 

S495 

.341 

.451 

7661 

.564 

8257 

.676 

8850 

7077 

SAND 

.24 

275 

.27 

406 

.29 

1532 

.31 

659 

.34 

788 

.36 

916 

STONE 

.48 

550 

.53 

2812 

.58 

3064 

.63 

3317 

.68 

3575 

.73 

3832 

Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—3  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required:— 1.74  Barrels  Per  Cubic  Yard. 
Sand  Required: — .53  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .77  Cubic  Yards  Per  Cubic  Yard. 


Thickness 

Width  in  Feet 

in 
Inches 

9 

10 

12 

14 

16 

18 

4J 

3QJ                           > 
CJ      < 

Foo 

Mi 

Foo 

Mil 

Foo 

Mil 

Foot 

Mil 

Foo 

Mil 

Foo 

Mile 

444 

CEMENT 

.19 

102 

.21 

112 

.25 

135 

.30 

158 

.34 

181 

.38 

2039 

SAND 

.06 

31 

.07 

34 

.08 

41 

.09 

48 

.10 

55 

.12 

621 

STONE 

.09 

45 

.09 

49 

.11 

60 

.13 

70 

.15 

80 

.17 

902 

4       5     4% 

CEMENT 

.22 

119 

.25 

132 

.30 

158 

.35 

184 

.4(X 

211 

.45 

2380 

SAND 

.07 

36 

.08 

40 

.09 

48 

.11 

56 

.12 

64 

.14 

725 

STONE 

.10 

52 

.11 

58 

.13 

70 

.15 

81 

.18 

93 

.20 

1053 

4       6     5y 

CEMENT 

.25 

135 

.28 

150 

.34 

181 

.40C 

2112 

.45 

241 

.51 

2720 

SAND 

.08 

41 

.09 

45 

.10 

55 

.12 

64 

.14 

73 

.16 

828 

STONE 

.11 

60 

.13 

667 

.15 

80 

.18 

935 

.20 

107 

.23 

1204 

5       5     5 

CEMENT 

.242 

27 

.268 

1415 

.322 

1700 

.376 

1984 

.43 

226 

.48 

2554 

SAND 

.07 

38 

.08 

431 

.10 

517 

.11 

604 

.13 

69 

.15 

778 

STONE 

.11 

565 

.12 

626 

.14 

752 

.17 

878 

.19 

1004 

.21 

1130 

5       6     $% 

CEMENT 

.273 

442 

.305 

608 

.365 

931 

.426 

2252 

.487 

2572 

.546 

2885 

SAND 

.08 

439 

.09 

490 

.11 

588 

.13 

686 

.15 

783 

.17 

879 

STONE 

.12 

638 

.13 

711 

.16 

854 

.19 

996 

.22 

1138 

.24 

1277 

5       7     6^ 

CEMENT 

.306 

616 

.339 

792 

.407 

152 

.477 

2518 

.545 

876 

.612 

3235 

SAND 

.09 

492 

.10 

546 

.12 

655 

.15 

767 

.17 

876 

.19' 

985 

STONE 

.14 

715 

.15 

793 

.18 

952 

.21 

1114 

.24 

273 

.27 

431 

5       8     7 

CEMENT 

.338 

782 

.376 

984 

.451 

380 

.525 

2776 

.602 

179 

.677 

574 

SAND 

.10 

543 

.11 

604 

.14 

725 

.16 

845 

.18 

968 

.21 

087 

STONE 

.15 

788 

.17 

878 

.20 

053 

.23 

228 

.27 

407 

.30 

582 

666 

CEMENT 

291 

535 

.322 

700 

.386 

039 

.451 

380 

.515 

720 

.579 

059 

SAND 

09 

467 

.10 

517 

.12 

621 

.14 

725 

.16 

828 

.18 

932 

STONE 

13 

679 

.14 

752 

.17 

902 

.20 

053 

.23 

204 

.26 

354 

676% 

CEMENT 

322 

700 

.357 

883 

.430 

269 

.501 

646 

.572 

022 

.644 

J400 

SAND 

10 

517 

11 

73 

.13 

691 

.15 

806 

.17 

921 

.20 

036 

STONE 

14 

752 

16 

833 

.19 

004 

.22 

171 

.25 

337 

28 

505 

64 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—3  MIX. 
Quantity  in  Barrels  of  Cement— Cubic  Yards  of  Sand— 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.74  Barrels  Per  Cubic  Yard. 
Sand  Required:— .53  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required:— .77  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

|             *»                   Width  in  Feet 

20 

22 

24 

26 

28 

30 

«      £ 

a  &  4 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.430 

2269 

.472 

2490 

.515 

2720 

.559 

2949 

.602 

3179 

.644 

3400 

SAND 

.13 

691 

.14 

758 

.16 

828 

.17 

898 

.18 

968 

.20 

1036 

STONE 

.19 

1004 

.21 

1102 

.23 

1204 

.25 

1305 

.27 

1407 

.28 

1505 

454^ 

CEMENT 

.501 

2647 

.550 

2902 

.600 

3170 

.651 

3437 

.701 

3704 

.750 

3960 

SAND 

.15 

806 

.17 

884 

.18 

966 

.20 

1047 

.21 

1128 

.23 

1206 

STONE 

.22 

1171 

.24 

1284 

.27 

1403 

.29 

1521 

.31 

1638 

.33 

1753 

4       6     5n 

CEMENT 

.572 

3022 

.630 

3325 

.687 

3630 

.745 

3932 

.802 

4235 

.860 

4538 

SAND 

.17 

921 

.19 

1013 

.21 

1106 

.23 

1198 

.24 

1290 

.26 

1382 

STONE 

.25 

1337 

.28 

1471 

.30 

1606 

.33 

1740 

.35 

1874 

.38 

2008 

5       5     5 

CEMENT 

.538 

2840 

.590 

3115 

.644 

3400 

.698 

3684 

.752 

3969 

.806 

4254 

SAND 

.16 

865 

.18 

949 

.20 

1036 

.21 

1122 

.23 

1209 

.25 

12% 

STONE 

.24 

1257 

.26 

1378 

.28 

1505 

.31 

1630 

.33 

1756 

.36 

1883 

CEMENT 

.607 

3207 

.668 

3529 

.726 

3849 

.790 

4171 

.851 

4493 

.912 

4815 

SAND 

.18 

977 

.20 

1075 

.22 

1172 

.24 

1270 

.26 

1368 

.28 

1467 

STONE 

.27 

1419 

.30 

1562 

.32 

1703 

.35 

1846 

.38 

1888 

.40 

2131 

5       7     6H 

CEMENT 

.680 

3591 

.748 

3950 

.816 

4308 

.884 

4667 

.952 

5025 

1.020 

5384 

SAND 

.21 

1094 

.23 

1203 

.25 

1312 

.27 

1421 

.29 

1531 

.31 

1640 

STONE 

.30 

J589 

.33 

1748 

.36 

1907 

.39 

2065 

.42 

2224 

.45 

2382 

587 

CEMENT 

J52 

3969 

.827 

4364 

.901 

4759 

.978 

5163 

1,053 

5556 

1.128 

5953 

SAND 

.23 

209 

.25 

329 

.27 

1450 

.30 

1573 

.32 

1693 

.34 

1813 

STONE 

.33 

756 

.37 

931 

.40 

2106 

.43 

2285 

.47 

2459 

.50 

2634 

666 

CEMENT 

.644 

3400 

.708 

3739 

.773 

4079 

.836 

4420 

.903 

4768 

.967 

5109 

SAND 

.20 

036 

.22 

139 

.24 

1242 

.25 

1346 

.28 

1452 

.29 

1556 

STONE 

.28 

505 

.31 

655 

.34 

1805 

.37 

1956 

.40 

2110 

.43 

2261 

CEMENT 

.715 

3776 

.786 

4153 

.858 

4529 

.929 

4907 

1.002 

5291 

1.074 

5669 

SAND 

.22 

150 

.24 

265 

.26 

1380 

.28 

1495 

.31 

1612 

.33 

1727 

STONE 

.32 

671 

.35 

838 

.38 

2004 

.41 

2171 

.44 

2342 

.48 

2509 

65 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—3  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.74  Barrels  Per  Cubic  Yard. 
Sand  Required:— .53  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required:— .77  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

ft  1  ! 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7H 

CEMENT 

.355 

1874 

.393 

2076 

.472 

2490 

.552 

2913 

.630 

3325 

.708 

3739 

SAND 

.11 

571 

.12 

632 

.14 

758 

.17 

887 

.19 

1013 

.22 

1139 

STONE 

.16 

829 

.17 

919 

.21 

1102 

.24 

1289 

.28 

1471 

.31 

1655 

698 

CEMENT 

.386 

2039 

.430 

2269 

.515 

2720 

.602 

3179 

.687 

3630 

.773 

4079 

SAND 

.12 

621 

.13 

691 

.16 

828 

.18 

968 

.21 

1106 

.24 

1242 

STONE 

.17 

902 

.19 

1004 

.23 

1204 

.27 

1407 

.30 

1606 

.34 

1805 

7       7     7 

CEMENT 

.338 

1782 

.376 

1984 

.451 

2380 

.525 

2776 

.602 

3179 

.677 

3574 

SAND 

.10 

543 

.11 

604 

.14 

725 

.16 

845 

.18 

968 

.21 

1087 

STONE 

.15 

788 

.17 

878 

.20 

1053 

.23 

1228 

.27 

1407 

.30 

1582 

7       8     7% 

CEMENT 

.371 

1958 

.411 

2169 

.494 

2610 

.576 

3043 

.658 

3473 

.741 

3913 

SAND 

.11 

596 

.13 

660 

.15 

795 

.18 

926 

.20 

1058 

.23 

1192 

STONE 

.16 

866 

.18 

959 

.22 

1155 

.25 

1346 

.29 

1537 

.33 

1732 

7       9     8M 

CEMENT 

.402 

2126 

.447 

2364 

.538 

2839 

.626 

3310 

.715 

3778 

.805 

4256 

SAND 

.12 

646 

.14 

721 

.16 

866 

.19 

1009 

.22 

1151 

.25 

1296 

STONE 

.18 

939 

.20 

1045 

.24 

1256 

.28 

1464 

.32 

1671 

.36 

1882 

7     10     9 

CEMENT 

.435 

2299 

.484 

2554 

.580 

3058 

.677 

3575 

.773 

4080 

.870 

4594 

SAND 

.13 

700 

.15 

779 

.18 

932 

.20 

1090 

.23 

1240 

.27* 

1399 

STONE 

.19 

1016 

.21 

1130 

.26 

1355 

.30 

1581 

.34 

1805 

.39 

2033 

888 

CEMENT 

.386 

2039 

.430 

2269 

.515 

2720 

.602 

3179 

.687 

3630 

.773 

4079 

SAND 

.12 

621 

.13 

691 

.16 

828 

.18 

968 

.21 

1106 

.24 

1242 

STONE 

.17 

902 

.19 

1004 

.23 

1204 

.27 

1407 

.30 

1606 

.34 

1805 

898* 

CEMENT 

.419 

2213 

.465 

2454 

.559 

2949 

.651 

3437 

.745 

3932 

.837 

4420 

SAND 

.13 

674 

.14 

747 

.17 

898 

.20 

1047 

.23 

1198 

.25 

1346 

STONE 

.19 

979 

.21 

1086 

.25 

1305 

.29 

1521 

.33 

1740 

.37 

1956 

8     10     9* 

CEMENT 

.451 

2383 

.501 

2648 

.602 

3181 

.701 

3705 

.802 

4239 

.901 

4760 

SAND 

.13 

726 

.15 

806 

.18 

970 

.21 

1129 

.24 

1295 

.27 

1451 

STONE 

.20 

1053 

.22 

1171 

.27 

1406 

.31 

1639 

.35 

1874 

.40 

2106 

Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—3  MIX. 
Quantity  in  Barrels  of  Cement— Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.74  Barrels  Per  Cubic  Yard. 
Sand  Required: — .53  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .77  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

ill 

Foot 

Mile 

Foot 

MUe 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

687^ 

CEMENT 

.786 

4153 

.867 

4574 

.945 

4989 

.023 

403 

.101 

5815 

.181 

6238 

SAND 

.24 

1265 

.26 

1393 

.29 

520 

.31 

646 

.34 

771 

.36 

900 

STONE 

.35 

1838 

.38 

2024 

.42 

2208 

.45 

2391 

.49 

2573 

.52 

2760 

698 

CEMENT 

.860 

4538 

.945 

4989 

1.032 

5448 

1.117 

5899 

.202 

6348 

.289 

6808 

SAND 

.26 

1382 

.29 

1520 

.31 

1659 

.34 

797 

.37 

933 

.39 

2073 

STONE 

.38 

2008 

.42 

2208 

.46 

2411 

.49 

2610 

.53 

2809 

.57 

3012 

7       7     7 

CEMENT 

.752 

3969 

.827 

4364 

.901 

4759 

.978 

5163 

.053 

5556 

.128 

5953 

SAND 

.23 

1209 

.25 

1329 

.27 

1450 

.30 

573 

.32 

693 

.34 

813 

STONE 

.33 

1756 

.37 

1931 

.40 

2106 

.43 

2285 

.47 

2459 

.50 

2634 

7      8     1% 

CEMENT 

.823 

4345 

.905 

4778 

.987 

5210 

1.070 

5650 

1.152 

6081 

1.234 

6515 

SAND 

.25 

1323 

.28 

1455 

.30 

1587 

.33 

721 

.35 

1852 

.38 

1984 

STONE 

.36 

1923 

.40 

2114 

.44 

2305 

.47 

2500 

.51 

2691 

.55 

2883 

7       9     8H 

CEMENT 

.895 

4725 

.985 

5203 

1.074 

5673 

1.162 

6138 

1.253 

6618 

1.342 

7087 

SAND 

.27 

1439 

.30 

1585 

.33 

1727 

.35 

1873 

.38 

2017 

.41 

2162 

STONE 

.40 

2090 

.44 

2292 

.48 

2508 

.51 

2716 

.55 

2927 

.59 

3135 

7     10     9 

CEMENT 

.966 

5098 

1.063 

5613 

1.161 

6127 

1.256 

6633 

1.354 

7148 

1.449 

7653 

SAND 

.29 

1553 

.32 

1710 

.35 

1867 

.38 

2020 

.41 

2177 

.44 

2331 

STONE 

.43 

2256 

.47 

2484 

.51 

2712 

.56 

2935 

.60 

3163 

.64 

3386 

888 

CEMENT 

.860 

4538 

.945 

4989 

1.032 

544£ 

1.117 

5899 

1.202 

6348 

1.289 

6808 

SAND 

.26 

1382 

.29 

1520 

.31 

1659 

.34 

1797 

.37 

1933 

.39 

2073 

STONE 

.38 

2008 

.42 

7708 

.46 

241 

.49 

2610 

.53 

2809 

.57 

3012 

8      9     8fc 

CEMENT 

.930 

4916 

1.023 

5403 

1.115 

5896 

1.209 

6390 

1.300 

6873 

1.395 

7371 

SAND 

.28 

1497 

.31 

1646 

.34 

1798 

.37 

1949 

.40 

2094 

.43 

2245 

STONE 

.41 

2175 

.45 

2391 

.49 

im 

.54 

2826 

.58 

304 

.62 

3260 

8     10     9tt 

CEMENT 

1.000 

5284 

1.103 

5826 

1.202 

635C 

1.30 

6872 

1.402 

741C 

1.503 

7939 

SAND 

.30 

1609 

.34 

1765 

.37 

1934 

.40 

2094 

.43 

22St 

.46 

2417 

STONE 

.44 

2333 

.49 

2562 

.53 

2309 

.58 

304 

.62 

yir 

.67 

3512 

67 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 

ROADS,  STREETS  AND  ALLEYS 

1— 2— 3^  MIX. 

Cubic  Yards  of  Concrete  per  Linear  Foot  and  per  Mile  of  Pavement 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand- 
Cubic  Yards  of  Stone. 

Cement  Required: — 1.61  Barrels  Per  Cubic  Yard. 
Sand  Required: — .49  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required; — .85  Cubic  Yards  Per  Cubic  Yard. 


Thickness 

Width  in  Feet 

in 
Inches 

9 

10 

12 

14 

16 

18 

-     2      1 

S  3  4 

Foot 

Mil 

Foo 

Mil 

Foot 

Mil 

Foot 

Mil 

Foot 

Mil 

Foot 

Mile 

444 

CEMENT 

.179 

944 

.196 

1044 

.238 

1257 

.279 

1470 

.313 

1674 

.357 

1886 

SAND 

.05 

28 

.06 

31 

.07 

383 

.08 

447 

.10 

510 

.11 

374 

STONE 

.09 

49 

.10 

55 

.13 

664 

.15 

776 

.17 

884 

.19 

996 

4       5     4% 

CEMENT 

.209 

1104 

.23 

122 

.279 

1470 

.324 

1708 

.37C 

1955 

.417 

2202 

SAND 

.06 

336 

.07 

37 

.08 

447 

.10 

520 

.11 

595 

.13 

670 

STONE 

.11 

583 

.12 

646 

.15 

776 

.17 

902 

.20 

1032 

.22 

1163 

4       6     5M 

CEMENT 

.238 

1257 

.264 

1394 

.317 

1674 

.370 

1955 

.423 

2236 

.477 

2516 

SAND 

.07 

383 

.08 

424 

.10 

510 

.11 

595 

.13 

681 

.15 

765 

STONE 

.13 

664 

.14 

736 

.17 

884 

.20 

1034 

.22 

1181 

.25 

1328 

5       5     5 

CEMENT 

.224 

1182 

.248 

1309 

.298 

1573 

.348 

1835 

.398 

2099 

.448 

2363 

SAND 

.07 

360 

.08 

398 

.09 

479 

.11 

559 

.12 

639 

.14 

r719 

STONE 

.12 

624 

.13 

691 

.16 

830 

.18 

969 

.21 

1108 

.24 

1249 

5       6     5% 

CEMENT 

.253 

335 

.282 

488 

.338 

785 

.394 

2083 

.451 

2380 

.506 

2669 

SAND 

.08 

406 

.09 

453 

.10 

543 

.12 

634 

.14 

724 

.15 

812 

STONE 

.13 

705 

.15 

785 

.18 

943 

.21 

100 

.24 

1256 

.27 

409 

5       7     6* 

CEMENT 

.283 

496 

.314 

658 

.377 

990 

.441 

2330 

.503 

2661 

.567 

2993 

SAND 

.09 

455 

.10 

505 

.11 

606 

.13 

709 

.15 

810 

.17 

911 

STONE 

.15 

790 

.17 

876 

.20 

051 

.23 

230 

.27 

1405 

.30 

580 

587 

CEMENT 

.312 

1649 

.348 

837 

.417 

2202 

.486 

568 

.557 

2941 

.626 

3307 

SAND 

.10 

502 

.11 

559 

.13 

670 

.15 

782 

.17 

895 

.19 

006 

STONE 

.16 

870 

.18 

969 

.22 

163 

.26 

356 

.29 

1553 

.33 

746 

666 

CEMENT 

.269 

1420 

.298 

573 

.357 

887 

.417 

2202 

.477 

2516 

.536 

2830 

SAND 

.08 

432 

.09 

479 

.11 

574 

.13 

670 

.15 

766 

.16 

861 

STONE 

.14 

750 

.16 

830 

.19 

996 

.22 

163 

.25 

1329 

.28 

494 

676% 

CEMENT 

.298 

573 

.330 

742 

.3% 

2099 

.464 

449 

.530 

2797 

.596 

146 

SAND 

.09 

479 

.10 

530 

.12 

639 

.14 

745 

.16 

851 

.18 

958 

STONE 

.16 

830 

.17 

920 

.21 

108 

.24 

293 

.28 

1476 

.31 

662 

68 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

l—2—3lA  MIX. 
Quantity  in  Barrels  of  Cement— Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required:— 1.61  Barrels  Per  Cubic  Yard. 
Sand  Required: — .49  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .85  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 

Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

u      8. 

1  *   * 

w    u    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.3982099 

.436 

2304 

.476 

2516 

.517 

2729 

.557 

2941 

.596 

3146 

SAND 

.12 

639 

.13 

701 

.15 

766 

.16 

831 

.17 

895 

.18 

957 

STONE 

.21 

1108 

.23 

1216 

.25 

1329 

.27 

1441 

.29 

1553 

.31 

1661 

4       5     4% 

CEMENT 

.464 

2449 

.509 

2685 

.555 

2933 

.602 

3180 

.649 

3426 

.694 

3664 

SAND 

.14 

745 

.15 

817 

.17 

893 

.18 

968 

.20 

1043 

.21 

1115 

STONE 

.24 

1293 

.27 

1418 

.29 

1549 

.32 

1679 

.34 

1809 

.37 

1935 

4       6     5ys 

CEMENT 

.530 

2797 

.583 

3077 

.636 

3358 

.689 

3639 

.742 

3919 

.795 

4199 

SAND 

.16 

851 

.18 

936 

.19 

1022 

.21 

1107 

.23 

1193 

.24 

1278 

STONE 
5       5     5 

.28 

1476 

.31 

1624 

.34 

1773 

.36 

1921 

.39 

2069 

.4, 

2217 

CEMENT 

.498 

2628 

.546 

2882 

.596 

3146 

.6463408 

.696 

3672 

.745 

3936 

SAND 

.15 

800 

.17 

877 

.18 

957 

.20 

1037 

.21 

1118 

.23 

1198 

STONE 

.26 

1387 

.29 

1522 

.31 

1661 

.34 

1799 

.37 

1939 

.39 

2078 

5       6     5% 

CEMENT 

.562 

2967 

.618 

3265 

.675 

3561 

.731 

3859 

.787 

4157 

.844 

4455 

SAND 

.17 

903 

.19 

994 

.21 

1084 

.22 

1175 

.24 

1265 

.26 

1356 

STONE 

.30 

1567 

.33 

1724 

.36 

1880 

.39 

2037 

.42 

2195 

.45 

2352 

5       7     6n 

CEMENT 

.630 

3323 

.692 

3655 

.755 

3986 

.818 

4318 

.881 

4650 

.943 

4981 

SAND 

.19 

1011   .21 

1112 

.23 

1213 

.25 

1314 

.27 

1415 

.29 

1516 

STONE 

.33 

1754 

.37 

1930 

.40 

2105 

.43 

2280 

.46 

2455 

.50 

2630 

587 

CEMENT 

.695 

3672 

.765 

4038 

.834 

4403 

.905 

4777 

.975 

5142 

1.043 

5508 

SAND 

.21 

1118 

.23 

1229 

.25 

1340 

.28 

1454 

.30 

1565 

.32 

1676 

STONE 

.37 

1939 

.40 

2132 

.44 

2325 

.48 

2522 

.51 

2715 

.55 

2908 

666 

CEMENT 

.596 

3146 

.655 

3460 

.715 

3774 

.774 

4089 

.836 

4411 

.895 

4727 

SAND 

.18 

958!  .20 

1053 

.22 

1149 

.24 

1245 

.25 

1343 

.27 

1439 

STONE 

.31 

1662 

.35 

1827 

.38 

1992 

.41 

2159 

.44 

2329 

.47 

2496 

6       7     6K 

CEMENT 

.662 

3494 

.728 

3843 

.794 

4191 

.860 

4540 

.927 

48% 

.993 

5245 

SAND 

.20 

1063 

.22 

1170 

.24 

1275 

.26 

1382 

.28 

1490 

.30 

1596 

STONE 

.35 

1845 

.38 

2029 

.41 

2213 

.45 

2397 

.49 

2585 

.52 

2769 

Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—3%  MIX. 

Quantity  in  Barrels  of  Cement— Cubic  Yards  of  Sand- 
Cubic  Yards  of  Stone. 

Cement  Required:— J. 61  Barrels  Per  Cubic  Yard. 
Sand  Required: — .49  Cubic  Yards,  Per  Cubic  Yard. 
Stone  Required:— .85  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

all 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7M 

CEMENT 

.371 

734 

.365 

1930 

.436 

2304 

.510 

2695 

.583 

3077 

.655 

3460 

SAND 

.10 

527 

.11 

585 

.13 

701 

.15 

820 

.18 

936 

.20 

053 

STONE 

.17 

915 

.19 

1019 

.23 

1216 

.27 

1423 

.31 

1624 

.35 

827 

698 

CEMENT 

.357 

887 

.398 

2099 

.477 

2516 

.557 

2941 

.636 

3358 

.715 

3774 

SAND 

.11 

574 

.12 

639 

.15 

766 

.17 

895 

.19 

1022 

.22 

149 

STONE 

.19 

996 

.21 

1108 

.25 

1329 

.29 

1553 

.34 

1773 

.38 

1992 

7       7     7 

CEMENT 

.312 

1649 

.3481837 

.417 

2202 

.486 

2568 

.557 

2941 

.626 

3307 

SAND 

.10 

502 

.11    559 

.13 

670 

.15 

782 

.17 

895 

.19 

1006 

STONE 

.16 

870 

.18    970 

.22 

1163 

.26 

1356 

.29 

1553 

.33 

1746 

787% 

CEMENT 

.343 

1811 

.3802006 

.457 

2415 

.533 

2814 

.609 

3214 

.686 

3621 

SAND 

10 

551 

.12 

611 

.14 

735 

.16 

857 

.19 

978 

.21 

1102 

STONE 

.18 

956 

.20 

1059 

.24 

1275 

.28 

1486 

.32 

1697 

.36 

1912 

CEMENT 

.372 

1964 

.414 

2185 

.497 

2628 

.580 

3061 

.662 

3494 

.745 

3936 

SAND 

.11 

598 

.13 

665 

.15 

800 

.18 

931 

.20 

1063 

.23 

1198 

STONE 

.20 

1037 

.22- 

1153 

.26 

1387 

.31 

1616 

.35 

1845 

.39 

2078 

7     10     9 

CEMENT 

.403 

2125 

.447 

2380 

.536 

2830 

.626 

3307 

.715 

3774 

.805 

4250 

SAND 

.12 

647 

.14 

719 

.16 

861 

.19 

1006 

.22 

1149 

.25 

1294 

STONE 

.21 

1122 

.24 

1248 

.28 

1494 

.33 

1746 

.38 

1992 

.43 

2244 

888 

CEMENT 

.357 

1887 

.398 

2099 

.477 

2516 

.557 

2941 

.636 

3358 

.715 

3774 

SAND 

.11 

574 

.12 

639 

.15 

766 

.17 

895 

.19 

1022 

.22 

1149 

STONE 

.19 

996 

.21 

1108 

.25 

1329 

.29 

1553 

.34 

1773 

.38 

1992 

898% 

CEMENT 

.388 

2048 

.430 

2270 

.517 

2729 

.602 

3180 

.689 

3639 

.774 

4089 

SAND 

.12 

623 

.13 

691 

.16 

830 

.18 

968 

.21 

1107 

.24 

1245 

STONE 

.20 

108 

.23 

1199 

.27 

1441 

.32 

1679 

.36 

1921 

.41 

2159 

8     10     9^ 

CEMENT 

.417 

??0? 

.464 

2449 

.557 

2941 

.649 

3426 

.742 

3919 

.834 

4403 

SAND 

.13 

670 

.14 

745 

.17 

895 

.20 

1043 

.23 

1193 

.25 

1340 

STONE 

.22 

1163 

.24 

1293 

.29 

1553 

.34 

1809 

.39 

2069 

.44 

2325 

Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  "FOR 
ROADS,  STREETS  AND  ALLEYS 

1-^-2— 3  Y2  MIX. 

Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand- 
Cubic  Yards  of  Stone. 

Cement  Required: — 1.61  Barrels  Per  Cubic  Yard. 
Sand  Required:— .49  Cubic  Yards,  Per  Cubic  Yard. 
Stone  Required:— .85  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

2    ? 

s  J  4 

Poo, 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8      ?H 

CEMENT 

.728 

3843 

.802 

4233 

.874 

4616 

.947 

4997 

1.019 

5381 

1.093 

5772 

SAND 

.22 

1170 

.24 

1288 

.27 

1405 

.29 

1521 

.31 

1638 

.33 

1757 

STONE 

.38 

2029 

.42 

2235 

.46 

2437 

.50 

2638 

.54 

2841 

.58 

3047 

698 

CEMENT 

.795 

4199 

.874 

4616 

.955 

5041 

1.034 

5458 

1.113 

5873 

1.193 

6298 

SAND 

.24 

1278 

.27 

1405 

.29 

1534 

.31 

1661 

.34 

1788 

.36 

1917 

STONE 

.42 

2217 

.46 

2437 

.50 

2661 

.55 

2882 

.59 

3101 

.63 

3325 

7       7     7 

CEMENT 

.695 

3672 

,765 

4038 

.834 

4403 

.905 

4777 

.975 

5142 

1.043 

5508 

SAND 

.21 

1118 

.23 

1229 

.25 

1340 

.28 

1454 

.30 

1565 

.32 

1676 

STONE 

.37 

1939 

.40 

2132 

.44 

2325 

.48 

2522 

.51 

2715 

.55 

2908 

7       8     7% 

CEMENT 

.762 

4020 

.837 

4421 

.913 

4820 

.990 

5228 

1.066 

5627 

1.141 

6028 

SAND 

.23 

1224 

.25 

1346 

.28 

1467 

.30 

1591 

.32 

1713 

.35 

1835 

STONE 

.40 

2122 

.44 

2334 

.48 

2545 

.52 

2760 

.56 

2971 

.60 

3182 

7       9     8^ 

CEMENT 

.828 

4370 

.911 

4811 

.993 

5245 

1.075 

5678 

1.159 

6121 

1.241 

6554 

SAND 

.25 

1330 

.28 

1464 

.30 

1596 

.33 

1728 

.35 

1862 

.38 

1995 

STONE 

.44 

2307 

.48 

2540 

.52 

2769 

.58 

2998 

.61 

3232 

.66 

3460 

7     10     9 

CEMENT 

.838 

4717 

.984 

5194 

1.074 

5670 

1.162 

6137 

1.253 

6614 

1.341 

7081 

SAND 

.27 

1436 

.30 

1581 

.33 

1726 

.35 

1868 

.33 

2013 

.41 

2155 

STONE 

.47 

2491 

.52 

2742 

57 

2994 

.61 

3240 

.66 

3491 

.71 

3738 

8       8     8 

CEMENT 

.795 

4199 

.874 

4616 

.955 

5041 

1.034 

5458 

1.113 

5873 

1.193 

6298 

SAND 

.24 

1278 

.27 

1405 

.29 

1534 

.31 

1661 

.34 

1788 

.36 

1917 

STONE 

.42 

2217 

.46 

2437 

.50 

2661 

.55 

2882 

.59 

3101 

.63 

3325 

898^ 

CEMENT 

.861 

4548 

.947 

4999 

1.032 

5448 

1.119 

5909 

1.204 

6358 

1.291 

6818 

SAND 

.26 

1384 

.29 

1521 

.31 

1658 

.34 

1798 

.37 

1935 

.39 

2075 

STONE 

.45 

2401 

.50 

2639 

.54 

2876 

.59 

3120 

.64 

3357 

.68 

3600 

8      10     9H 

CEMENT 

.925 

4988 

1.021 

5390 

1.113 

5873 

1.204 

6358 

1.298 

6852 

1.391 

*344 

SAND 

.28 

1488 

.31 

1641 

.34 

1788 

.37 

1935 

.39 

2081 

.42 

2235 

STONE 

.49 

2581 

.54 

2846 

.59 

3101 

.64 

3357 

.69 

3618 

.73 

3878 

71 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—4  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone, 

Cement  Required: — 1.48  Barrels  Per  Cubic  Yard. 
Sand  -Required: — .45  Cubic  Yards  Per  Cubic  Yard, 
Stone  Required: — .90  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

.  I   f 

aw         > 
0     < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

MHe 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.164 

867 

.182 

96! 

.219 

1156 

.256 

1351 

.292 

1539 

.329 

1735 

SAND 

.05 

264 

.06 

292 

.07 

351 

.08 

411 

.09 

468 

.10 

527 

STONE 

.10 

527 

11 

584 

.13 

703 

.16 

822 

.18 

936 

.20 

1055 

4       5     4% 

CEMENT 

.192 

1015 

.213 

1125 

.256 

1351 

.297 

1570 

.340 

1797 

.383 

2025 

SAND 

.06 

309 

.06 

342 

.08 

411 

.09 

477 

.10 

546 

.12 

616 

STONE 

.12 

617 

.13 

684 

.16 

822J  .18 

955 

.21 

1093 

.23 

1231 

4       6     5* 

CEMENT 

.219 

1156 

.243 

1282 

.292 

153$  .340 

1797 

.389 

2071 

.438 

£313 

SAND 

.07 

351 

.07 

390 

.09 

468  .10 

546 

.12 

625 

.13 

703 

STONE 

.13 

703 

.15 

780 

.18 

936^  .21 

1093  .24 

1250 

.27 

1407 

555 

CEMENT 

.206 

1086 

.227 

1203 

.274 

144fl  .320 

1687 

.366 

1930 

.411 

2173 

SAND 

.06 

330 

.07 

366 

.08 

440 

.10 

513 

.11 

587 

.13 

661 

STONE 

.13 

661 

.14 

732 

.17 

879 

.19 

1026 

.22 

1174 

.25 

1321 

5       6     5% 

CEMENT 

.232 

1227 

.259 

1368 

.311 

1641 

.363 

1915 

.414 

2187 

.465 

2454 

SAND 

.07 

373 

.08 

416 

t09 

499 

.11 

582 

.13 

665 

.14 

746 

STONE 

.14 

746 

.16 

832 

.19 

998 

.22 

1165 

.25 

1330 

.28 

1492 

5       7     6K 

CEMENT 

.260 

1375 

.289 

1524 

.346 

1829 

.406 

2142 

.463 

2446 

.521 

7751 

SAND 

.08 

418 

.09 

464 

.11 

556 

.12 

651 

.14 

744 

.16 

837 

STONE 

.16 

836 

.18 

927 

.21 

1112 

.25 

1302 

.28 

1488 

.32 

1673 

5       8     7 

CEMENT 

.287 

1516 

.3201687 

.383 

2025 

.447 

2361 

.512 

2704 

.576 

3040 

SAND 

.09 

461 

.10 

513 

.12 

616 

.14 

718 

.16 

822 

.18 

924 

STONE 

.17 

922 

.19 

1026 

.23 

1231 

.27 

1436 

.31 

644 

.35 

1849 

666 

CEMENT 

.247 

1305 

.274 

1446 

.329 

1735 

.383 

2025 

.438 

2313 

.493 

2602 

SAND 

.08 

397 

.08 

440 

.10 

527 

.12 

616 

.13 

703 

.15 

791 

STONE 

.15 

794 

.17 

879 

.20 

1055 

.23 

1231 

.27 

407 

.30 

1582 

676% 

CEMENT 

.274 

1446 

.303 

1601 

.366 

1930 

.426,2251 

.487 

2571 

.548 

2892 

SAND 

.08 

440 

.09 

487 

.11 

587 

.13 

684 

.15 

782 

.17 

879 

STONE 

.17 

879 

.18 

974 

.22 

1174 

.26 

1369 

.30 

563 

.33 

759 

72 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—4  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.48  Barrels  Per  Cubic  Yard. 
Sand  Required: — .45  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .90  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

bC        "is          fe 

•o      5      > 
u    o    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.366 

1930 

.401 

2118 

438 

2313 

.475 

2509 

.512 

2704 

.548 

2892 

SAND 

.11 

587 

.12 

644 

.13 

703 

.14 

763 

.16 

822 

.17 

879 

STONE 

.22 

1174 

.24 

1288 

.27 

1407 

.29 

1526 

.31 

1644 

.33 

1759 

4       5     4% 

CEMENT 

.426 

2251 

.468 

2469 

.511 

2697 

.554 

2923 

.596 

3149 

.638 

3368 

SAND 

.13 

684 

.14 

751 

.16 

820 

.17 

889 

.18 

958 

.19 

1024 

STONE 

.26 

1369 

.28 

1501 

.31 

1640 

.34 

1778 

.36 

1915 

.39 

2048 

4       6     5n 

CEMENT 

.487 

2571 

.536 

2828 

.585 

3087 

.633 

3345 

.682 

3602 

.731 

3860 

SAND 

.15 

782 

.16 

860 

.18 

939 

.19 

1017 

.21 

1095 

.22 

1174 

STONE 

.30 

1563 

.33 

1720 

.36 

1877 

.39 

2034 

.41 

2191 

.44 

2347 

5       5     5 

CEMENT 

.457 

2415 

.502 

2649 

.548 

2892 

.593 

3133 

.639 

3376 

.685 

3619 

SAND 

.14 

734 

15 

806 

.17 

879 

.18 

953 

.19 

1026 

.21 

1100 

STONE 

.28 

1469 

.31 

1611 

.33 

1759 

.36 

1905 

.39 

2053 

.42 

2200 

5       6     5% 

CEMENT 

.517 

2728 

.568 

3001 

.620 

3274 

.672 

3548 

.724 

3821 

.776 

4095 

SAND 

.16 

829 

.17 

913 

.19 

995 

.20 

1079 

.22 

1162 

.24 

1245 

STONE 

.31 

1659 

.35 

1825 

.38 

1991 

.41 

2157 

.44 

2324 

.47 

2490 

5       7     6* 

CEMENT 

.579 

3055 

.636 

3360 

.694 

3664 

.752 

3969 

.810 

4274 

.867 

4579 

SAND 

,18 

929 

.19 

1022 

.21 

1114 

.23 

1207 

.25 

1300 

.26 

1392 

STONE 

35 

1858 

.39 

2043 

.42 

2228 

.46 

2414 

:49 

2599 

.53 

2785 

5       8     7 

CEMENT 

.639 

3376 

.703 

3712 

.767 

4048 

.832 

4391 

.895 

4727 

.959 

5063 

SAND 

19 

1026 

.21 

1129 

.23 

1231 

.25 

1335 

.27 

1437 

.29 

1539 

STONE 

.39 

2053 

.43 

2257 

.47 

2462 

.51 

2670 

.54 

2875 

.58 

3079 

666 

CEMENT 

.548 

2892 

.602 

3181 

.657 

3469 

.712 

3759 

.768 

4055 

.823 

4345 

SAND 

.17 

879 

.18 

967 

.20 

1055 

.22 

1143 

,23 

1233 

.25 

1321 

STONE 

.33 

1759 

.37 

1934 

.40 

2HO 

.43 

2286 

.47 

2466 

.50 

2642 

676% 

CEMENT 

608 

3212 

.669 

3533 

.730 

3852 

.790 

4174 

.852 

4501 

.913 

4822 

SAND 

.18 

977 

.20 

1074 

.22 

1171 

.24 

1269 

.26 

1368 

.28 

1466 

STONE 

.37 

1953 

.41 

2148 

.44 

2343 

.48 

2538 

.52 

2737 

.55 

2932 

73 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—4  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.48  Barrels  Per  Cubic  Yard. 
Sand  Required: — .45  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .90  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width 

in  Feet 

9 

10 

12 

14 

16 

18 

ill 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7n 

CEMENT 

.302 

1594 

.332 

1766 

.401 

2118 

.469 

2478 

.536 

2828 

.602 

3181 

SAND 

.09 

485 

.10 

537 

.12 

644 

.14 

753 

.16 

860 

.18 

967 

STONE 

.18 

969 

.20 

1074 

.24 

1288 

.29 

1507 

.33 

1720 

.37 

1934 

698 

CEMENT 

.329 

1735 

.366 

1930 

.438 

2313 

.512 

2704 

.585 

3087 

.657 

3469 

SAND 

.10 

527 

.11 

587 

.13 

703 

.16 

822 

.18 

939 

.20 

1055 

STONE 

.20 

1055 

.22 

1174 

.27 

1407 

.31 

1643 

.36 

1877 

.40 

2110 

777 

CEMENT 

.287 

1516 

.320 

1687 

.383 

2025 

.447 

2361 

.512 

2704 

.576 

3040 

SAND 

.09 

461 

.10 

513 

.12 

616 

.14 

718 

.16 

822 

.18 

924 

STONE 

.17 

922 

.19 

1026 

.23 

1231 

.27 

1436 

.31 

1644 

.35 

1849 

787% 

CEMENT 

.315 

1665 

.349 

1844 

.420 

2220 

.490 

2587 

.559 

2954 

.630 

3329 

SAND 

.10 

506 

.11 

561 

.13 

675 

.15 

787 

.17 

898 

..19 

1012 

STONE 

.19 

1012 

.21 

1121 

.26 

1350 

.30 

1573 

.34 

1796 

.38 

2024 

7       9     8n 

V 

CEMENT 

.342 

1806 

.381 

2008 

.457 

2415 

.533 

2813 

.608 

3212 

.685 

3619 

SAND 

.10 

549 

.12 

611 

.14 

734 

i  >16 

855 

.18 

977  .21 

1100 

STONE 

.21 

1098 

.23 

1221 

.28 

1469 

.32 

1711 

.37 

1953  .42 

2201 

7     10     9 

CEMENT 

.370 

1954 

.411 

2173 

.493 

2602 

.576 

3040 

.657 

3469 

.740 

3907 

SAND 

.11 

594 

.13 

661 

.15 

791 

.18 

924 

.20 

1055 

.23 

1188 

STONE 

.23 

1188 

.25 

1321 

.30 

1582 

.35 

1849 

.40 

2110 

.45 

2376 

888 

CEMENT 

.329 

1735 

.366 

1930 

.438 

2313 

.512 

2704 

.585 

3087 

.657 

3469 

SAND 

.10 

527 

.11 

587 

.13 

703 

.16 

822 

.18 

939 

.20 

1055 

STONE 

.20 

1055 

.22 

1174 

.27 

1407 

.31 

1643 

.36 

1877 

.40 

2110 

898% 

CEMENT 

.357 

1883 

.395 

2087 

.475 

2509 

.554 

2923 

.633 

3353 

.712 

3759 

SAND 

.11 

572!  .12 

635 

.14 

763 

.17 

889 

.19 

1017 

.22 

1143 

STONE 

.22 

1145  .24 

1269 

.29 

1526 

.34 

1778 

.39 

2034 

.43 

2286 

8     10     9n 

CEMENT 

.383 

2025 

.426 

2251 

.512 

2704 

.596 

3149 

.682 

3602 

.767 

4048 

SAND 

.12 

616 

.13 

684 

.16 

822 

.18 

958 

.21 

1095 

.23 

1231 

STONE 

.23 

1231 

.26 

1369 

.31 

1644 

.36 

1915 

.41 

2191 

.47 

2462 

74 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2—4  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.48  Barrels  Per  Cubic  Yard. 
Sand  Required:— .45  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .90  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

ill 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7K 

CEMENT 

669 

3533 

737 

3891 

.804 

4243 

.870 

4594 

.937 

4946 

1.005 

5306 

SAND 

.20 

074 

.22 

183 

24 

290 

.26 

1397 

.28 

1504 

.31 

1613 

STONE 

41 

2148 

.45 

2366 

.49 

2580 

.53 

2794 

.57 

3008 

.61 

3227 

698 

CEMENT 

.731 

3860 

.804 

4243 

.878 

4634 

.950 

5017 

1.023 

5399 

1.097 

5790 

SAND 

.22 

174 

.24 

1290 

.27 

1409 

.29 

1526 

.31 

1642 

.33 

1760 

STONE 

.44 

2347 

.49 

2580 

.53 

2818 

.58 

3051 

.62 

3283 

.67 

3521 

7       7     7 

CEMENT 

.639 

3376 

.703 

3712 

.767 

4048 

.832 

4391 

.895 

4727 

.959 

5063 

SAND 

19 

1026 

.21 

1129 

.23 

1231 

.25 

1335 

.27 

1437 

.29 

1539 

STONE 

.39 

2053 

.43 

2257 

.47 

2462 

.51 

2670 

.54 

2875 

.58 

3079 

787% 

CEMENT 

.700 

36% 

.770 

4064 

.839 

4431 

.910 

4806 

.980 

5173 

1.049 

5541 

SAND 

.21 

1124 

.23 

1236 

,26 

1347 

.28 

1461 

.30 

1573 

.32 

1685 

STONE 

.43 

2247 

.47 

2471 

.51 

2695 

.55 

2922 

.60 

3146 

.64 

3370 

7       9     8H 

CEMENT 

.761 

4017 

.838 

4422 

.913 

4822 

9)89 

5220 

1.066 

5627 

1.133 

6025 

SAND 

.23 

1221 

.25 

1345 

.28 

1466 

.30 

1587 

.32 

1711 

.35 

1831 

STONE 

.46 

2443 

.51 

2689 

.56 

2932 

60 

3174 

.65 

3422 

.69 

3664 

7     10     9 

CEMENT 

.821 

4336 

.904 

4774 

.987 

5213 

1.069 

5642 

1.151 

6080 

1.233 

6509 

SAND 

.25 

1319 

.27 

1452 

.30 

1585 

.32 

1715 

.35 

1849 

.37 

1979 

STONE 

.50 

2637 

.55 

2903 

.60 

3170 

.65 

3431 

.70 

3697 

.75 

3958 

888 

CEMENT 

.731 

3860 

.804 

4243 

.878 

4634 

.950 

5017 

1.023 

5399 

1.097 

5790 

SAND 

.22 

1174 

.24 

1290 

.27 

1409 

.29 

1526 

.31 

1642 

.33 

1760 

STONE 

44 

2347 

.49 

2580 

.53 

2818 

.58 

3051 

.62 

3283 

.67 

3521 

8       9     8M 

CEMENT 

.792 

418 

.870 

4594 

.949 

5008 

1.029 

5432 

1.107 

5845 

1.187 

6268 

SAND 

.24 

127 

.26 

1397 

.29 

1523 

.31 

1652 

.34 

1777 

.36 

1906 

STONE 

.48 

2543 

.53 

2794 

.58 

3046 

.63 

3303 

67 

3554 

.72 

3812 

8     10     9* 

CEMENT 

.851 

4493 

.938 

4955 

1.023 

5399 

1.107 

5845 

1.193 

6299 

1.279 

6752 

SAND 

.26 

136* 

.29 

1507 

.31 

164 

.34 

1777 

.36 

1915 

.39 

2053 

STONE 

.52 

2732 

.57 

301 

.62 

328 

.67 

3554 

.73 

383C 

.78 

4106 

75 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2^—5  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required:— 1.21  Barrels  Per  Cubic  Yard 
Sand  Required:— .46  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: —.92  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

ill 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

134 

709 

149 

785 

.179 

945 

209 

1105 

.238 

1258 

.269 

1418 

SAND 

.05 

270 

.06 

299 

.07 

359 

.08 

420 

.09 

478 

.10 

539 

STONE 

.10 

539 

.11 

597 

.14 

719 

16 

840 

.18 

957 

.20 

1078 

4       5     4% 

CEMENT 

.157 

830 

.174 

920 

.209 

1105 

.243 

1284 

.278 

1469 

.313 

1655 

SAND 

.06 

316 

.07 

350 

.08 

420 

.09 

488 

.11 

558 

.12 

629 

STONE 

12 

631 

.13 

699 

16 

840 

18 

976 

.21 

1117 

.24 

1259 

4       6     5M 

CEMENT 

.179 

945 

.198 

1048 

.238 

1258 

.278 

1469 

.318 

1681 

.358 

1891 

SAND 

.07 

359 

.08 

398 

.09 

478 

.11 

558 

.12 

639 

.14 

719 

STONE 

.14 

719 

.15 

797 

.18 

957 

.21 

1117 

.24 

1278 

.27 

1438 

555 

CEMENT 

.168 

888 

.186 

984 

.224 

1182 

.261 

1379 

.299 

1578 

.336 

1776 

SAND 

06 

338 

.07 

374 

.09 

449 

.10 

524 

.11 

600 

.13 

675 

STONE 

.13 

675 

.14 

748 

.17 

899 

.20 

1049 

.23 

1200 

.26 

1351 

CEMENT 

.190 

1003 

.212 

1118 

.254 

1342 

.296 

1566 

.339 

1788 

.380 

2006 

SAND 

.07 

381 

.08 

425 

.10 

510 

.11 

595 

.13 

680 

.14 

763 

STONE 

.14 

763 

.16 

850 

.19 

1020 

.23 

1190 

.26 

1360 

.29 

1525 

5       7     6^ 
CEMENT 

.212 

1124 

.236 

1246 

.283 

1496 

.332 

1751 

.379 

2000 

.426 

2249 

SAND 

.08 

427 

.09 

474 

.11 

569 

.13 

666 

.14 

760 

.16 

855 

STONE 

.16 

855 

.18 

948 

.22 

1137 

.25 

1331 

.29 

1521 

.32 

1710 

5       8     7 

CEMENT 

.235 

1239 

.261 

1379 

.313 

1655 

.365 

1930 

.419 

2211 

.471 

2485 

SAND 

.09 

471 

.10 

524 

.12 

629 

.14 

734 

.16 

840 

.18 

945 

STONE 

.18 

942 

.20 

1049 

.24 

1259 

.28 

1467 

.32 

1681 

.36 

1890 

666 

CEMENT 

.202 

1067 

.224 

1182 

.269 

1418 

.313 

1655 

.358 

1891 

.403 

2127 

SAND 

.08 

406 

.09 

449 

.10 

539 

.12 

629 

.14 

719 

.15 

809 

STONE 

.15 

811 

.17 

899 

.20 

1078 

.24 

1259 

.27 

1438 

.31 

1617 

6       7     6% 

CEMENT 

.224 

1182 

.248 

1309 

.299 

1578 

.348 

1840 

.398 

2102 

.448 

2364 

SAND 

.09 

449 

.09 

498 

.11 

600 

.13 

700 

.15 

799 

.17 

899 

STONE 

.17 

899 

.19 

995 

.23 

1200 

.26 

1400 

.30 

1598 

.34 

1798 

76 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—2^—5  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.21  Barrels  Per  Cubic  Yard. 
Sand  Required: — .46  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required:— .92  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

0,          $          fi 

a  3  1 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.299 

1578 

.328 

1732 

.358 

1891 

.388 

2051 

.419 

2211 

.448 

2364 

SAND 

.11 

600 

.12 

658 

.14 

719 

.15 

780 

.16 

840 

.17 

899 

STONE 

.23 

1200 

.25 

1317 

.27 

1438 

.30 

1559 

.32 

1681 

.34 

1798 

4       5     4% 

CEMENT 

.348 

1840 

.382 

2018 

.417 

2205 

.453 

2390 

.488 

2575 

.512 

2754 

SAND 

.13 

700 

.15 

767 

.16 

838 

.17 

909 

.19 

979 

.20 

1047 

STONE 

.26 

1400 

.29 

1535 

.32 

1676 

.34 

1817 

.37 

1958 

.40 

2094 

4       6     5H 

CEMENT 

.398 

2102 

.438 

2312 

.478 

2524 

.518 

2735 

.558 

2945 

.598 

3156 

SAND 

.15 

799 

.17 

879 

.18 

960 

.20 

1040 

.21 

1120 

.23 

1200 

STONE 

.30 

1598 

.33 

1758 

.36 

1919 

.39 

2079 

.42 

2239 

.45 

2399 

555 

CEMENT 

.374 

1975 

.410 

2166 

.448 

2364 

.485 

2562 

.523 

2760 

.560 

2958 

SAND 

.14 

751 

.16 

823 

.17 

899 

.18 

974 

.20 

1049 

.21 

1125 

STONE 

.28 

1501 

.31 

1647 

.34 

1798 

.37 

1948 

.40 

2099 

.43 

2249 

565% 

CEMENT 

.422 

2230 

.465 

2454 

.507 

2677 

.549 

2900 

.592 

3124 

.634 

3348 

SAND 

.16 

848 

.18 

933 

.19 

1018 

.21 

1103 

.22 

1188 

.24 

1273 

STONE 

.32 

1696 

.35 

1866 

.39 

2035 

.42 

2205 

.45 

2375 

.48 

2546 

5      7     6H 

CEMENT 

.473 

2497 

.520 

2747 

.567 

29% 

.615 

3245 

.662 

3494 

.709 

3744 

SAND 

.18 

949 

.20 

1044 

.22 

1139 

.23 

1234 

.25 

1328 

.27 

1423 

STONE 

.36 

1899 

.40 

2088 

.43 

2278 

.47 

2467 

.50 

2657 

.54 

2846 

587 

CEMENT 

.523 

2760 

.575 

3035 

.627 

3309 

.680 

3590 

.732 

3865 

.784 

4139 

SAND 

.20 

1049 

.22 

1154 

.24 

1258 

.26 

1365 

.28 

1469 

.30 

1574 

STONE 

.40 

2099 

.44 

2307 

.48 

2516 

.52 

2730 

.56 

2938 

.60 

3147 

666 

CEMENT 

448 

2364 

.492 

7600 

.537 

2836 

.582 

3073 

.628 

3315 

.673 

3553 

SAND 

.17 

899 

.19 

989 

.20 

1078 

.22 

1168 

.24 

1260 

.26 

1351 

STONE 

.34 

1798 

.37 

1977 

.41 

2156 

.44 

2337 

.48 

2521 

.51 

2701 

CEMENT 

.497 

2626 

.547 

2888 

.597 

3150 

.646 

3412 

.697 

3680 

.747 

3942 

SAND 

.19 

r998 

.21 

1098 

.23 

1197 

.25 

1297 

.26 

1399 

.28 

1499 

STONE 

.38 

19% 

.42 

21% 

.45 

2395 

.49 

2594 

.53 

2798 

.57 

2997 

77 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 

ROADS,  STREETS  AND  ALLEYS 

1—2  H— 5  MIX. 

Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand- 
Cubic  Yards  of  Stone. 

Cement  Required.—- 1.21  Barrels  Per  Cubic  Yard. 
Sand  Required:- .46  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required:  -.92  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

SJ      §> 

3   o    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7M 

CEMENT 

.247 

1303 

.273 

1444 

.328 

1732 

.384 

2026 

.438 

2312 

.492 

2600 

SAND 

.09 

495 

.10 

549 

.12 

658 

.15 

770 

.17 

879 

.19 

989 

STONE 

.19 

991 

.21 

1098 

.25 

1317 

.29 

1540 

.33 

1758 

.37 

1977 

698 

CEMENT 

.269 

1418 

.299 

1578 

.358 

1891 

.419 

2211 

.478 

2524 

.537 

2836 

SAND 

.10 

539 

.11 

600 

.14 

719 

.16 

840 

.18 

960 

.20 

1078 

STONE 

.20 

1078 

.23 

1200 

.27 

1438 

.32 

1681 

.36 

1919 

.41 

2156 

777 

CEMENT 

.235 

1239 

.261 

1379 

.313 

1655 

.365 

1930 

.419 

2211 

.471 

2485 

SAND 

.09 

471 

.10 

524 

.12 

629 

.14 

734 

.16 

840 

.18 

945 

STONE 

.18 

942 

.20 

1049 

.24 

1259 

.28 

1467 

.32 

1681 

.36 

1890 

CEMENT 

.258 

1361 

.286 

1508 

.344 

1815 

.401 

2115 

.457 

2415 

.515 

2721 

SAND 

.10 

518 

.11 

573 

.13 

690 

.15 

804 

.17 

918 

.20 

1035 

STONE 

.20 

1035 

.22 

1146 

.26 

1380 

.30 

1608 

.35 

1836 

.39 

2069 

7      9     8M 

CEMENT 

.280 

1476 

.311 

1642 

.374 

1975 

.436 

2300 

.497 

2626 

.560 

2958 

SAND 

.11 

561 

.12 

624 

.14 

751 

.17 

874 

.19 

998 

.21 

1125 

STONE 

.21 

1122 

.24 

1248 

.28 

1501 

.33 

1749 

.38 

1996 

.43 

2349 

7     10     9 

CEMENT 

.303 

1597 

.336 

1776 

.403 

2127 

.471 

2485 

.537 

2836 

.605 

3194 

SAND 

.12 

607 

.13 

675 

.15 

809 

.18 

945 

.20 

1078 

.23 

1214 

STONE 

.23 

1214 

.26 

1351 

.31 

1617 

.36 

1890 

.41 

2156 

.46 

2429 

888 

CEMENT 

.269 

1418 

.299 

1578 

.358 

1891 

.419 

2211 

.478 

2524 

.537 

2836 

SAND 

.10 

539 

.11 

600 

.14 

719 

.16 

840 

.18 

960 

.20 

1078 

STONE 

.20 

1078 

.23 

1200 

.27 

1438 

.32 

1681 

.36 

1919 

.41 

2156 

898% 

CEMENT 

.292 

1539 

.323 

1706 

.388 

2051 

.453 

2390 

.518 

2735 

.582 

3073 

SAND 

.11 

585 

.12 

649 

.15 

780 

.17 

909 

.20 

1040 

.22 

1168 

STONE 

.22 

1170 

.25 

1297 

.30 

1559 

.34 

1817 

.39 

2079 

.44 

2337 

8     10     9M 

CEMENT 

.313 

1655 

.348 

1840 

.419 

2211 

.488 

2575 

.558 

2945 

.627 

3309 

SAND 

.12 

629 

.13 

700 

.16 

840 

.19 

979 

.21 

1120 

.24 

1258 

STONE 

.24 

1259 

.26 

1400 

.32 

1681 

.37 

1958 

.42 

2239 

.48 

2516 

78 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS.  STREETS  AND  ALLEYS 

1— 2K— • 5  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required:— 1.21  Barrels  Per  Cubic  Yard. 
Sand  Required:— .46  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .92  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

-cf       u        > 

u    u    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

687* 

CEMENT 

.547 

2888 

.603 

3181 

.657 

3469 

.711 

3757 

.766 

4044 

822 

4338 

SAND 

.21 

1098 

.23 

1209 

.25 

1319 

.27 

1428 

.29 

1537 

.31 

1649 

STONE 

.42 

2196 

.46 

2419 

.50 

2638 

.54 

2857 

.58 

3075 

.62 

3298 

698 

CEMENT 

.598 

3156 

.657 

3469 

.718 

3789 

.777 

4102 

.836 

4414 

.897 

4734 

SAND 

.23 

1200 

.25 

1319 

.27 

1440 

.30 

1559 

.32 

1678 

.34 

1800 

STONE 

.45 

2399 

.50 

2638 

.55 

2881 

.59 

3119 

.64 

3356 

.68 

3599 

7       7     7 

CEMENT 

.523 

2760 

.575 

3035 

.627 

3309 

.680 

3590 

.732 

3865 

.784 

4139 

SAND 

.20 

1049 

.22 

1154 

.24 

1258 

.26 

1365 

.28 

1469 

.30 

1574 

STONE 

.40 

2099 

.44 

2307 

.48 

2516 

.52 

2730 

.56 

2938 

.60 

3147 

7       8     7% 
CEMENT 

.572 

3021 

.629 

*323 

.686 

3623 

.744 

3929 

.801 

4229 

.858 

4530 

SAND 

.22 

1149 

.24 

1263 

.26 

1377 

.28 

1494 

.30 

1608 

.33 

1722 

STONE 

.44 

2297 

.48 

2526 

.52 

2754 

.57 

2987 

.61 

3215 

.65 

3444 

798* 

CEMENT 

.622 

3284 

.685 

3615 

.747 

3942 

.808 

4268 

.871 

4600 

.933 

4926 

SAND 

.24 

1248 

.26 

1374 

.28 

1499 

.30 

1622 

.33 

1749 

.35 

1873 

STONE 

.47 

2497 

.52 

2749 

.57 

2997 

.61 

3245 

.66 

3498 

.71 

3745 

7     10     9 

CEMENT 

.672 

3545 

.739 

3903 

.807 

4262 

.874 

4613 

.941 

4971 

1.008 

5322 

SAND 

.26 

1348 

.28 

1484 

.31 

1620 

.33 

1754 

.36 

1890 

.38 

2023 

STONE 

.51 

2696 

.56 

2978 

.61 

3240 

.66 

3507 

.72 

3779 

.77 

4046 

388 

CEMENT 

.598 

3156 

.657 

3469 

.718 

3789 

.777 

4102 

.836 

4414 

.897 

4734 

SAND 

.23 

1200 

.25 

1319 

.27 

1440 

.30 

1559 

.32 

1678 

.34 

1800 

STONE 

.45 

2399 

.50 

2638 

.55 

2881 

.59 

3119 

.64 

3356 

.68 

3599 

898% 

CEMENT 

.647 

3418 

.711 

3757 

.776 

4095 

.841 

4441 

.905 

4778 

.970 

5124 

SAND 

.25 

1300 

.27 

1428 

.29 

1557 

.32 

1688 

.34 

1817 

.37 

1943 

STONE 

.49 

2599 

.54 

2857 

.59 

3113 

.64 

3376 

.69 

3633 

.74 

3896 

8     10     9* 

CEMENT 

.696 

3674 

767 

4051 

.836 

4414 

.905 

4778 

.975 

5150 

1.045 

5520 

SAND 

.26 

1397 

.29 

1540 

.32 

1678 

.34 

1817 

.37 

1958 

.40 

2099 

STONE 

.53 

2793 

.58 

3080 

.64 

3356 

.69 

3633 

.74 

3916 

.79 

4197 

Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—3—6  MIX. 

Quantity  in  Barrels  of  Cement— Cubic  Yards  of  Sand- 
Cubic  Yards  of  Stone. 

Cement  Required: — 1.02  Barrels  Per  Cubic  Yard. 
Sand  Required:— .47  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .93  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

u    a 
a   |    | 

Foo 

Mile 

Foot 

Mil 

Foot 

Mile 

Foot 

Mile 

Foot 

Mil 

Foot 

Mile 

687^ 
CEMENT 

.20* 

109S 

.231121 

.27t 

146C 

.32 

1707 

.369 

194 

.41! 

2192 

SAND 

.10 

5M 

.11 

56 

.13 

673 

.15 

78 

.17 

89 

.19 

1010 

STONE 

.19 

1002 

.21 

1105 

.25 

1331 

.29 

155 

.34 

177 

.38 

1999 

698 

CEMENT 

.22 

1195 

.25: 

!133 

.302 

1594 

.35 

1864 

.403 

212 

.452 

2391 

SAND 

.10 

551 

.12 

61 

.14 

73 

.16 

85 

.19 

980 

.21 

1102 

STONE 

.21 

1090 

.23 

121 

.28 

145 

.32 

1699 

.37 

1940 

.41 

2180 

111 

CEMENT 

.19 

1044 

.220116 

.264 

139 

.30* 

162 

.353 

1864 

.397 

2095 

SAND 

.09 

481 

.10 

53 

.12 

62 

.14 

750 

.16 

859 

.18 

965 

STONE 

.18 

952 

.20 

1060 

.24 

1272 

.28 

148 

.32 

1699 

.36 

1910 

787% 

CEMENT 

.21 

1146 

.241 

127 

.290 

1530 

.336 

1783 

.386 

2036 

.435 

2294 

SAND 

.10 

528 

.11 

586 

.13 

705 

.16 

822 

.18 

938 

.20 

1057 

STONE 

.20 

1045 

.22 

1159 

.26 

1395 

.31 

1626 

.35 

1856 

.40 

2092 

7       9     8n 

CEMENT 

.23 

1244 

.262 

1384 

.315 

1665 

.367 

1939 

.419 

2213 

.472 

2494 

SAND 

.11 

573  .12 

638 

.15 

767 

.17 

893 

.19 

1020 

.22 

1149 

STONE 

.21 

1135 

.24 

1262 

.29 

1518 

.33 

1768 

.38 

2018 

.43 

2274 

7      10     9 

CEMENT 

.255 

1346 

.284 

1497 

.340 

1793 

.397 

2095 

.453 

2391 

.5!0 

2693 

SAND 

.12 

620 

.13 

690 

.16 

826 

.18 

965 

.21 

1102 

.24 

1241 

STONE 

.23 

1228 

.26 

1365 

.31 

1635 

.36 

1910 

.42 

2180 

.47 

2455 

888 

CEMENT 

.226 

195 

.252 

1330 

.302 

1594 

.353 

864 

.403 

2128 

.452 

2391 

SAND 

.10 

551 

.12 

613 

.14 

735 

.16 

859 

.19 

980 

.21 

1102 

STONE 

.21 

090 

.23 

1213 

.28 

1454 

.32 

699 

.37 

1940 

.41 

2180 

898% 

CEMENT 

.246 

297 

.272 

1438 

.327 

1729 

.381 

015 

.437 

2305 

.491 

2591 

SAND 

.11 

598 

.13 

663 

.15 

797 

.18 

928 

.20 

1062 

.23 

1194 

STONE 

.22 

183 

.25 

1311 

.30 

1576 

.35 

837 

.40 

2102 

.45 

2362 

8     10     9y3 

CEMENT 

.264 

395 

.294 

551 

.353 

1864 

.411 

171 

.470 

2483 

.528 

2790 

SAND 

.12 

643 

.14 

715 

.16 

859 

.19 

000 

.22 

144 

.24 

1285 

STONE 

.24 

272 

.27 

1415 

.32 

699 

.37 

979 

.43 

2264 

.48 

2544 

fin 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—3—6  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.02  Barrels  Per  Cubic  Yard. 
Sand  Required: — .47  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required:— .93  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

!«  * 

2    o    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

6       8     7M 

CEMENT 

.461 

2435 

.508 

2682 

.554 

2924 

.600 

3167 

.646 

3409 

.693 

3657 

SAND 

.21 

1122 

.23 

1236 

.26 

1349 

.28 

1459 

.30 

1571 

.32 

1685 

STONE 

.42 

2220 

.46 

2445 

.50 

2666 

.55 

2888 

.59 

3108 

.63 

3334 

698 

CEMENT 
SAND 

.504 
.23 

2660 
1226 

.554 
.26 

2924 
1347 

.605 
.28 

3194 
1472 

.655 
.30 

3458 
1593 

.705 
.32 

3721 
1715 

.756 
.35 

3990 
1839 

STONE 

.46 

2425 

.50 

2666 

.55 

2912 

.60 

3153 

.64 

3393 

,69 

3638 

111 

CEMENT 

.441 

2327 

.485 

2558 

.528 

2790 

.573 

3026 

.617 

3259 

.661 

3489 

SAND 

CTYMVIC 

.20 

Af\ 

1072 

1  1  *>l 

.22 

A  A 

1179 

IITl 

.24 

1285 

.26 

1394 

.28 

1501 

.30 

1608 

STONE 

.40 

2121 

.44 

2332 

.48 

2544 

.52 

2759 

.56 

2970 

.60 

3182 

7       8     I* 

CEMENT 

.482 

2547 

.530 

2801 

.578 

3054 

.627 

3312 

.675 

3565 

.723 

3819 

SAND 

.22 

1174 

.24 

129) 

.27 

1407 

.29 

1526 

.31 

1643 

.33 

1760 

STONE 

.44 

2322 

.48 

2554 

.53 

2784 

.57 

3020 

.62 

3250 

.66 

3482 

7      9     8M 

CEMENT 

.524 

2768 

.577 

3048 

.629 

3323 

.681 

3598 

.734 

.786 

4152 

3878 

SAND 

.24 

1276 

.27 

1404 

.29 

1531 

.31 

1658 

.34 

1787 

.362 

1913 

STONE 

.48 

2524 

.53 

2779 

.57 

3030 

.62 

3280 

.67 

3536 

.72 

3786 

7     10     9 

CEMENT 

.566 

2989 

.623 

3291 

.680 

3592 

.736 

3888 

.794 

4190 

.850 

4486 

SAND 

.26 

1377 

.29 

1516 

.31 

1655 

.34 

1792 

.37 

1931 

.39 

2067 

STONE 

.52 

2725 

,57 

3000 

.62 

3275 

.67 

3545 

.72 

3820 

.77 

4090 

888 

CEMENT 

.504 

2660 

.554 

2924 

.605 

3194 

.655 

3458 

.785 

3721 

.756 

3990 

SAND 

.23 

1226 

,26 

1347 

.28 

1472 

.30 

1593 

.32 

1715 

.35 

1839 

STONE 

.46 

2425 

.50 

2666 

.55 

2912 

.60 

3153 

.64 

3393 

.69 

3638 

8      9     By, 

CEMENT 

.546 

2882 

.6003167 

,654 

3452 

.709 

3743 

.763 

4028 

,818 

4320 

SAND 

,25 

1328 

.28 

1459 

.30 

1590 

.33! 

1725 

.35 

1856 

.38 

1990 

STONE 

.50 

2627 

.55 

2888 

.60 

3147 

.65 

3413 

.70 

3673 

.75  i 

3939 

8     10     9^ 

CEMENT 

.587 

3097 

.647 

3415 

.705 

3721 

.763 

4028 

.822 

4341 

.881 

4653 

SAND 

.27 

1427 

.30 

1574 

.32 

1715 

.35 

1856 

.38 

2000 

.41 

2144 

STONE 

.53 

7873 

.59 

3114 

.64 

3393 

.70 

3673 

.75 

3958 

.80 

4243 

81 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—3—6  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.02  Barrels  Per  Cubic  Yard. 
Sand  Required:— .47  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .03  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

9 

10 

12 

14 

16 

18 

,1   1 

3    3    X 

Foot 

Vtile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.113 

598 

.125 

662 

.151 

797 

.176 

931 

.200 

1061 

.226 

1195 

SAND 

.05 

275 

.06 

305  .07 

367 

.08 

429 

.09 

489 

.10 

551 

STONE 

.10 

545 

.11 

604 

.14 

726 

.15 

849 

.18 

967 

.21 

1090 

4       5     4n 

CEMENT 

.133 

700 

.147 

775 

.176 

931 

.205 

1082 

.235  238 

.264 

1395 

SAND 

.06 

322 

07 

357 

.08 

429 

.09 

499 

.10 

571 

.12 

643 

STONE 

.12 

638 

.13 

707 

.16 

849 

.19 

987 

.21 

129 

.24 

1272 

4      6    SH 

CEMENT 

.151 

797 

.167 

883 

.201 

061 

.235 

1238 

.268 

417 

.302 

1594 

SAND 

.07 

367 

08 

407 

.09 

489 

.11 

571 

.12 

653 

.14 

735 

STONE 

.14 

726 

J5 

805 

.18 

967 

.21 

1129 

.24 

292 

.28 

1454 

555 

CEMENT 

.142 

749 

.157 

829 

.189 

997 

u220 

163 

.252 

330 

.284 

1497 

SAND 

.07 

345 

07 

382 

.09 

459 

.10 

536 

.12 

613 

.13 

690 

STONE 

.13 

683 

.14 

756 

.17 

909 

.20 

060 

.23 

213 

.26 

1365 

5       6     5% 

CEMENT 

.160 

846 

179 

942 

.214 

1131 

.250 

1320 

.286 

508 

.320 

1691 

SAND 

.07 

390 

.08 

434 

.TO 

521 

.12 

608 

.13 

695 

.15 

779 

STONE 

.15 

771 

.16 

859 

.20 

1031 

.23 

1203 

.26 

375 

.29 

1542 

5       7     6n 

CEMENT 

.180 

948 

.199 

1051 

.239 

1261 

.279 

1476 

.319 

1686 

.359 

18% 

SAND 

.08 

437 

09 

484 

.11 

581 

.13 

68 

.15 

777 

.17 

871 

STONE 

.16 

864 

.18 

958 

.22 

1149 

.25 

1346 

.29 

1537 

.32 

1729 

587 

CEMENT 

.198 

1044 

220 

1163 

.264 

1395 

.308 

162 

.353 

1864 

.397 

2095 

SAND 

.09 

4811  '10 

536!  .12 

643 

.14 

750 

.16 

859 

.18 

965 

STONE 

.18 

952 

.20 

1060 

.24 

1272 

.28 

148 

.32 

1699 

.36 

1910 

666 

CEMENT 

.170 

900 

.189 

993 

.226 

1195 

.264 

139 

.302 

1594 

.34C 

1793 

SAND 

.08 

415 

09 

459 

.10 

55 

.12 

64 

.14 

735 

.16 

1826 

STONE 

.16 

82C 

.17 

90S 

.21 

1090 

.24 

127 

.28 

1454 

.31 

1635 

676^ 

CEMENT 

.189 

993 

.209 

lift 

.252 

133C 

.294 

155 

.336 

1772 

.377 

1993 

SAND 

.09 

45S 

.10 

5TC 

.12 

61 

.14 

71 

.15 

8U 

.17 

918 

STONE 

.17 

90S 

.19 

10(X 

.23 

121 

.27 

141 

.31 

1615 

.34 

1817 

82 


Table  No.  11 

QUANTITY  OF  MATERIAL  REQUIRED  FOR 
ROADS,  STREETS  AND  ALLEYS 

1—3—6  MIX. 
Quantity  in  Barrels  of  Cement — Cubic  Yards  of  Sand — 

Cubic  Yards  of  Stone. 

Cement  Required: — 1.02  Barrels  Per  Cubic  Yard. 
Sand  Required: — .47  Cubic  Yards  Per  Cubic  Yard. 
Stone  Required: — .93  Cubic  Yards  Per  Cubic  Yard. 


Thickness 
in 
Inches 

Width  in  Feet 

20 

22 

24 

26 

28 

30 

*     1      1 

u    o    < 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

Foot 

Mile 

444 

CEMENT 

.252 

1330 

.276 

1460 

.302 

1594 

.327 

1729 

.353 

1864 

.377 

993 

SAND 

.12 

613 

.13 

673 

.14 

735 

.15 

797 

.16 

859 

.17 

918 

STONE 

.23 

1213 

.25 

1331 

.28 

1454 

.30 

1576 

.32 

1699 

.34 

1817 

4       5     4% 

CEMENT 

.294 

1551 

.322 

1701 

.352 

1858 

.381 

2015 

.411 

2171 

.440 

2322 

SAND 

.14 

715 

.15 

784 

.16 

856 

.18 

928 

.19 

1000 

.20 

1070 

STONE 

.27 

1415 

.29 

1551 

.32 

1694 

.35 

1837 

.37 

1979 

.40 

2117 

CEMENT 

.336 

1772 

.369 

1949 

.403 

2128 

.437 

2305 

.470 

2483 

.504 

2660 

SAND 

.15 

816 

.17 

898 

.19 

980 

.20 

1062 

.22 

1144 

.23 

1226 

STONE 

.31 

1615 

.34 

1777 

.37 

1940 

.40 

2102 

43 

7764 

.46 

2425 

5      5     5 

CEMENT 

.315 

1665 

.346 

1826 

.377 

1993 

.409 

2159 

.441 

2327 

.472 

2494 

SAND 

.15 

767 

.16 

841 

.17 

918 

.19 

995 

.20 

1072 

.22 

1149 

STONE 

.29 

1518 

.32 

1665 

.34 

1817 

.37 

1968 

.40 

2121 

.43 

2274 

5      6     5« 

CEMENT 

.360 

1880 

.392 

2069 

.427 

2256 

.463 

2445 

.499 

2644 

.534 

2822 

SAND 

.16 

866 

.18 

953 

.20 

1040 

.21 

1127 

.23 

1214 

.25 

1300 

STONE 

.32 

1714 

.36 

1886 

.39 

2057 

.42 

2229 

.45 

2401 

.49 

2573 

5       7     6H 
CEMENT 

.399 

2105 

.439 

2315 

.478 

2526 

.518 

2736 

.558 

2946 

.598 

3156 

SAND 

.18 

970 

.20 

1067 

.22 

1164 

.24 

1261 

.26 

1357 

.28 

1454 

STONE 

.36 

1920 

.40 

2111 

.44 

2303 

.47 

2494 

.51 

2686 

.54 

2877 

5      8     7 

CEMENT 

.441 

2327 

.485 

2558 

.528 

2790 

.573 

3026 

.617 

3259 

.661 

3489 

SAND 

.20 

1072 

.22 

1179 

.24 

1285 

.26 

1394 

.28 

1501 

.30 

1608 

STONE 

.40 

2121 

.44 

2332 

.48 

2544 

.52 

2759 

.56 

2970 

.60 

3182 

666 

CEMENT 

.377 

1993 

.415 

2)92 

.453 

2391 

.491 

2591 

.529 

2795 

.567 

2995 

SAND 

.17 

918 

.19 

1010 

.21 

1102 

.23 

1194 

.24 

1288 

.26 

1380 

STONE 

.34 

1817 

.37 

1999 

.41 

2180 

.45 

2362 

.48 

2548 

.52 

2730 

6      7     6H 

CEMENT 

.419 

2213 

.461 

2435 

.503 

2655 

.545 

2876 

.588 

3102 

.629 

3323 

SAND 

.19 

1020 

.21 

1122 

.23 

1223 

.25 

1325 

.27 

1429 

.29 

1533 

STONE 

.38 

2018 

.42 

2220 

..46 

2421 

.50 

767? 

.54 

2828 

.57 

3030 

S4 


CHAPTER  4. 

MISCELLANEOUS  NOTES  FOR  SUPERIN- 
TENDENT AND  FOREMAN 

Forms 

Various  methods  of  building  and  erecting 
forms,  and  other  important  essentials  related  to 
their  use,  have  been  more  fully  discussed  elsewhere. 
There  are,  however,  a  number  of  precautions  which 
should  always  be  observed  which  are  of  such  im- 
portance that  repetition  of  mention  can  be  excused. 

Forms  should  be  built  exactly  as  called  for  by 
the  drawings  unless  proved  impractical.  The  su- 
perintendent should  be  able  to  determine  whether 
forms  are  sufficiently  strong  to  support  the  load  of 
concrete  that  will  be  placed  upon  them  and  should 
see  that  they  are  sufficiently  braced  so  that  they  will 
neither  collapse  nor  sag  when  filled.  They  should  be 
cleaned  of  all  refuse  or  rubbish  before  any  concrete 
is  placed.  This  is  particularly  true  of  column  forms, 
but  special  reference  to  column  form  does  not  mean 
that  any  part  of  the  inspection  is  to  be  slighted. 

Reinforcing  steel  must  be  properly  placed  and 
when  in  place  should  be  carefully  checked  against 
the  drawings  to  make  certain  that  the  required 
amount  has  been  used  and  is  in  proper  position. 

Many  failures  have  been  caused  by  weakness  of 
supports  for  concrete  forms  and  centering.  If  the 
forms  shake  or  vibrate  considerably  when  work  is  in 
progress,  it  is  almost  certain  that  such  disturbance 
will  affect  the  concrete  while  hardening.  An  interfer- 
ence of  this  kind  during  the  hardening  of  the  concrete 
impairs  the  effectiveness  of  the  cement  as  a  binder. 

Forms  should  be  so  placed  and  so  supported, 
particularly  when  the  uprights  rest  upon  the  earth, 
as  to  prevent  warping,  twisting  or  sagging.  The 
maximum  safe  loads  for  wood  posts  of  various 
lengths  and  sections  are  given  below.  Knowing  the 
length  of  post,  total  weight  of  concrete  and  form  to 
be  supported  and  the  economical  number  of  posts, 
the  load  per  post  and  size  can  readily  be  determined. 

85 


A  corner  post  carries  only  one-half  of  the  load  car- 
ried by  the  side  post,  while  a  side  post  carries  one- 
half  the  load  that  must  be  borne  by  the  inside  one. 

Table  No.  12 

MAXIMUM  SAFE  LOAD  FOR  WOOD  COLUMNS 


Length  in  Feet 

Minimum   Dimensions 

4  in. 

6  in. 

8   in. 

5 

9,400 

6 

8,800 

7 

8,200 

8 

7,500 

20,700 

9 

6,900 

19,800 

10 

6,300 

18,900 

37,700 

11 

17,900 

36,400 

12 

17,000 

35,200 

14 

15,100 

32,700 

16 

30,200 

18 

27,600 

20 

25,100 

Example :— Flat  slab  14  feet  by  17  feet  8  inches, 
weighing  approximately  60,000  pounds,  16  posts 
can  be  spaced  economically  in  four  rows  of  4  each. 
There  will  be  4  corner  posts,  8  side  posts  and  4  in- 
side posts — 16  posts. 

4  corner  posts  carry  load  of  1  inside  postal 

8  side  posts  carry  load  of  4  inside  post&=4 

4  inside  posts  carry  load  of  4  inside  posts— 4 

Number  of  posts  of  equal  load     9 

Maximum   load   per   post—  -—• — ==6,666  Ibs. 

Length  of  post  6  feet  0  inches. 
From  the  table  we  find  one  4  by  4  post  6  feet 
long  will  carry  safely  a  load  of  8,800  pounds, 
since  posts  should  never  be  less  than  4  by  4 
inches  and  this  size  will  answer  in  this  case. 
In  filling  forms,  care  should  be  taken  to  place 
the  proper  quantities  of  concrete  at  one  time.     It 
should  be   placed   in  layers   no   thicker  or  deeper 
than  can  be  properly  consolidated  and  caused  to 
unite  with  concrete  previously  placed.     The  forms 
for  a  slab  and  beam  should  be  filled  at  the  same 
time.    If  necessary  to  discontinue  work,  good  judg- 
ment should  be  exercised  as  to  the  best  place  to 
make  such  a  stop  so  as  not  to  leave  a  permanent 

86 


line  of  cleavage  that  will  affect  the  final  strength 
of  the  structure. 

Careful  Supervision  over  Proportioning 
and  Mixing  Necessary 

At  all  times  while  concreting  is  in  progress,  the 
contractor's  superintendent  or  foreman  should  keep 
careful  watch  over  the  manner  in  which  the  concrete 
is  being  proportioned  and  mixed,  so  that  there  will  be 
no  question  but  that  specification  requirements  are 
being  complied  with.  Cement  is  sold  by  the  barrel 
but  is  usually  received  on  the  job  in  bags  or  sacks, 
four  of  such  containers  corresponding  to  a  so-called 
barrel.  At  all  times  careful  watch  should  be  kept  of 
the  aggregates  being  used  to  make  certain  that  definite 
proportions  called  for  are  not  changed,  due  to  careless- 
ness of  some  of  the  workmen,  by  being  carelessly  mea- 
sured, nor  that  unscreened  aggregates  are  being  substi- 
tuted for  the  separate  volumes  of  fine  and  course 
aggregates  specified. 

In  no  instance  should  forms  or  centering  be  re- 
moved until  it  is  positively  known  that  the  concrete 
has  hardened  sufficiently  to  have  the  required  strength, 
not  only  to  carry  its  own  weight  but  any  weight  that 
may  be  placed  on  it  during  subsequent  processes  of 
construction.  Concrete  hardens  much  more  rapidly 
during  warm  than  in  cold,  damp  weather.  Retaining 
walls  that  are  to  withstand  earth  pressure  should  not 
be  subjected  to  such  pressure  until  all  possibility  of 
injury  from  load  has  passed.  There  is  no  good  guide 
for  form  removal  other  than  that  acquired  by  long  ex- 
perience, which  enables  the  superintendent  or  foreman 
to  place  proper  value  upon  the  conditions  under  which 
the  concrete  has  been  hardening.  Extraordinary  pre- 
cautions should  be  taken  when  it  comes  to  removing 
supports  from  floor  slabs,  roofs,  arches  and  similar 
classes  of  work.  The  length  of  time  that  forms  are 
left  in  place  should  be  much  longer  in  cold  than  in 
warm  weather.  Somewhat  of  a  guide  can  be  obtained 
by  making  cubes  or  cylinders  of  concrete  at  the  same 
time  as  the  concrete  in  the  job  is  placed.  These  should 
be  examined  later  and  tested,  if  necessary,  to  deter- 
mine whether  the  concrete  is  of  proper  strength.  Yet 
such  tests  must  not  be  relied  upon  as  an  invariable 
guide. 

87 


Concreting  in  Cold  Weather 

Experience  has  proved  the  possibility  of  carrying 
on  many  classes  of  concrete  work  under  conditions 
which  a  few  years  ago  would  have  been  thought  un- 
favorable. There  are  contracting  firms  who  specialize 
on  concrete  work  in  cold  weather.  Such  lengthening 
of  the  ordinary  concreting  season  has  been  made  pos- 
sible by  the  application  of  such  precautions  as  heating 
the  sand,  pebbles  or  broken  stone  and  water  so  that 
sufficient  warmth  is  added  to  the  concrete  mixture  to 
carry  it  through  the  period  necessary  for  early  hard- 
ening. All  materials  except  the  cement  are  heated  so 
that  the  concrete  when  placed  has  a  temperature  of 
from  seventy  to  eighty  degrees  Fahrenheit.  After 
being  placed,  it  is  protected  so  that  the  mass  will  re- 
tain this  heat  and  the  possibility  of  freezing  be  pre- 
vented for  at  least  forty-eight  hours.  Work  so  done 
will  be  as  successful  as  that  carried  on  under  the  usual 
favorable  conditions.  This  is  true  of  practically  all 
classes  of  concrete  work  except  concrete  road  or  street 
construction,  which  it  is  not  advisable  to  continue 
when  temperatures  fall  so  low  that  continued  freez- 
ing may  be  expected. 

No  concrete  should  be  laid  when  temperatures 
may  go  to  freezing  or  lower,  unless  precautions  are  ta- 
ken to  heat  materials  as  described.  It  is  better  to 
suspend  work  than  to  run  the  chance  of  a  severe  drop 
in  temperature  which  may  injure  the  concrete  if  it  is 
frozen  more  than  once  before  thoroughly  hardened. 
Concrete  floors  are  laid  in  buildings  during  freezing 
weather  by  enclosing  the  frame  of  the  structure  with 
with  tarpaulins  and  maintaining  heat  within  the  en 
closure  by  means  of  stoves,  or  "salamanders". 

In  heating  materials,  a  number  of  methods  may  be 
employed.  Mixing  water  can  readily  be  heated  by 
leading  the  water  through  a  pipe  coil  around  which  a 
coke  or  wood  fire  is  kept.  Or  it  can  be  heated  in 
barrels  by  discharging  steam  from  the  boiler  plant  on 
the  job  into  the  barrels  filled  with  water;  or  if  there 
is  no  such  plant,  then  the  required  quantities  can 
usually  be  heated  in  large  kettles.  The  sand  and  peb- 
bles or  broken  stone  can  be  heated  by  improvising  pipe 
stoves  made  out  of  sections  of  metal  smoke  stack* 


and  piling  the  materials  over  and  about  a  piece  of 
such  stack  with  fire  built  inside.  Materials  should  be 
turned  or  raked  over  frequently  so  those  next  to  the 
stove  will  not  be  damaged  by  over-heating,  and  those 
farther  away  will  be  sure  to  have  the  frost  drawn 
from  them.  Another  method  frequently  employed  to 
heat  the  stone  or  sand  is  to  insert  a  small  perforated 
pipe  through  which  live  steam  is  passed.  It  is  abso- 
lutely necessary  to  get  all  frost  out  of  the  aggregate 
before  putting  it  in  a  concrete  mixture. 

Very  often  on  account  of  the  limited  space  in  the 
street  or  at  the  site  of  the  work,  or  because  of  unusual 
conditions,  it  is  not  easy  to  improvise  the  desired 
method  of  heating  material.  A  heating  attachment 
which  was  originally  designed  for  use  in  mixing  asphal- 
tic  concrete,  has  been  very  sucessfully  used  to  mix 
concrete  in  winter  where  it  is  desirable  to  have  all 
materials  thoroughly  heated.  The  heating  unit  con- 
sists of  an  oil  tank  for  supplying  fuel  to  the  double 
burner  oil  furnace  and  a  blower  which  forces  the 
heated  air  and  flame  into  the  inside  of  the  drum,  thus 
insuring  the  necessary  degree  of  warmth  to  the  con- 
crete which,  with  other  measures  of  protection,  prevent 
it  from  freezing  in  the  forms  until  after  early  harden- 
ing has  been  completed. 

Various  methods  are  used  to  protect  the  concrete 
after  it  has  been  placed,  from  possible  damage  due  to 
freezing.  Coverings  of  canvas,  straw  or  similar  mate- 
rial can  be  used  on  flat  surfaces,  while  vertical  faces 
also  may  be  covered  with  canvas  hung  away  from 
the  forms;  or  the  forms  can  be  battened  and  building 
paper  tacked  on  the  battens,  thus  introducing  a  dead 
space  that  does  much  to  insulate  against  extreme  cold. 
For  mass  work  sometimes  the  forms  themselves  afford 
sufficient  protection  when  cold  is  not  extreme.  Pad- 
ing  the  forms  with  hay  or  straw  in  extreme  cold 
weather  provides  excellent  protection. 

Manure  should  never  be  placed  directly  on  con- 
crete as  a  means  of  protection  against  freezing.  Exper- 
iments have  proved  that  in  the  process  of  decomposi- 
tion the  chemical  changes  which  may  take  place  in  the 
manure  are  likely  to  produce  nitric  acid.  Although 
this  does  not  always  happen,  it  may,  and  if  it  does 


che  result  will  be  a  scaling  or  pitting  of  the  surface. 
Besides,  manure  placed  directly  in  contact  with  a  con- 
crete walk  or  floor  is  certain  to  cause  considerable 
staining  of  the  surface,  which  in  most  cases  would  be 
objectionable. 

Curing  of  Concrete 

Many  persons  have  the  impression  that  the  hard- 
ening process  which  takes  place  in  concrete  is  due  to 
drying.  Nothing  will  do  more  to  "weaken  concrete 
than  to  allow  it  to  dry  out  rapidly  after  placed.  For 
this  reason  concrete  work  requires  certain  protection 
in  warm  weather  to  safeguard  it,  just  as  it  requires 
protection  in  cold  weather.  When  sun  or  hot  dry 
winds  strike  fresh  concrete  much  of  the  water  intro- 
duced in  mixing  rapidly  evaporates.  Water  is  neces- 
sary to  the  hardening  of  concrete.  Generally  speak- 
ing, the  protection  that  should  be  given  to  concrete 
during  hot  weather  is  essentially  the  same  for  all 
classes  of  concrete  work.  Ways  and  means  of  apply- 
ing the  protection  may  differ  slightly,  but  all  aim 
toward  the  same  end. 

Pavements  in  general,  which  properly  include 
floors,  sidewalks,  driveways,  etc.,  have  a  relatively 
larger  area  exposed  to  the  atmosphere  than  has  mass 
concrete.  Wall  sections  have  a  still  greater  area 
exposed,  usually  two  sides.  Either  canvas  or  earth 
covering  should  be  applied  to  concrete  surfaces  to 
protect  against  rapid  drying.  In  hot  weather  it  is 
very  desirable  to  stretch  canvas  on  frames  over  con- 
crete street  and  highway  pavement  immediately  after 
the  surface  has  been  struck  off  and  floated,  and  to  keep 
such  a  covering  in  place  until  the  surface  has  hard- 
ened enough  to  permit  applying  a  protective  layer  of 
earth.  Walls  of  structures  should  be  protected  either 
by  frequent  sprinkling  or  by  hanging  wet  canvas  over 
them.  When  temperatures  are  not  extremely  high, 
sprinkling  of  the  concrete  alone,  if  done  at  sufficiently 
frequent  intervals,  will  often  give  the  desired  protec- 
tion. 

Mass  work,  such  as  foundation  walls  entirely  be- 
low ground,  heavy  abutments,  and  retaining  walls, 
do  not  require  the  same  extreme  measures  of  protec- 
tion as  does  work  of  thinner  section.  Leaving  forms 


in  place  and  occasionally  sprinkling  or  wetting  down 
the  work  for  several  successive  days  will  often  be  all 
that  is  necessary. 

Roof  slabs  require  essentially  the  same  protection 
as  thin  concrete  walls,  since  two  surfaces  are  essen- 
tially exposed.  Roofs  should  be  covered  with  moist 
earth  or  sand,  sprinkled  freely,  and  otherwise  be  pro- 
tected like  pavements.  Stucco  work  may  be  ruined 
by  lack  of  proper  protection  while  hardening.  Much 
of  the  cracking  and  crazing  of  stucco  has  been  due  to 
neglect  in  protecting  the  work. 

Joining  New  Concrete  to  Old 

New  and  old  concrete  can  be  joined  only  with 
great  difficulty  and  the  strength  of  such  a  connection 
is  always  uncertain.  It  is  only  by  using  the  greatest 
care  that  a  cement  finish  coat  can  be  made  to  adhere 
to  a  concrete  base  that  has  completely  hardened. 
The  joining  of  old  and  new  concrete  work  is  best  done 
by  thoroughly  cleansing  it  from  all  dust  and  loose 
particles,  sometimes  chipping  the  surface,  saturating 
it  with  water,  painting  it  with  a  cement  grout  paint 
mixed  to  the  consistency  of  thick  cream,  and  while  this 
coating  is  fresh,  immediately  placing  the  new  concrete 
or  applying  the  plaster  coat  as  the  case  may  be.  As 
cement  begins  to  harden  within  a  very  short  time 
after  being  combined  with  water,  the  grout  paint 
should  be  applied  only  a  short  distance  in  advance  of 
the  work  going  on.  The  more  nearly  clean  aggregate 
faces  are  exposed  to  the  new  concrete  or  plaster  to  be 
applied,  the  better  will  be  the  bond  secured  between 
old  and  new  work. 

Concrete  Surface  Finish 

Concrete  surfaces  are  susceptible  of  a  great  variety 
of  pleasing  finishes  that  have  practically  no  limit 
other  than  that  imposed  by  individual  ingenuity  of 
the  workers  on  the  job.  The  types  of  surface  finish 
may  be  obtained  as  follows: 

(1)  Leaving  the  concrete  as  it  is  when  forms  are  removed; 

(2)  Using  a  mortar  facing  or  plaster; 

(3)  Hammer  dressing  or  tooling; 

(4)  Using   special   concrete   mixtures; 

(5)  Coloring    the    surface; 

(6)  Washing  the  surface  to  expose  aggregates  selected  with  that  en  d 
in  view. 

91 


The^kind  of  surface  finish  that  will  result  from 
leaving  the  concrete  as  it  is  when  forms  are  removed 
depends  upon  two  factors.  Such  a  surface  will  be 
truly  characteristic  of  concrete  if  the  forms  have 
been  well  made  of  planed  lumber  and  the  concrete 
was  carefully  and  thoroughly  spaded  next  to  form 
faces  while  being  placed.  If  these  essentials  have  been 
observed  there  is  rarely  or  never  any  need  of  subse- 
quent work  on  the  surface  for  ordinary  concrete 
structures.  A  few  pebble  pockets  may  be  in  the  sur- 
face, and  these  can  readily  be  pointed  up  immediately 
after  forms  are  removed  by  using  a  mortar  of  cement 
mixed  with  the  same  number  of  parts  of  sand  as  were 
used  in  the  concrete  mixture.  For  example:  If  the 
concrete  was  a  1 :2 :4  mixture,  then  a  1 :2  sand-cement 
mortar  should  be  used  for  pointing.  If  a  1 :3 :6 :  mix- 
ture, then  a  1 :3  mortar  should  be  used  for  pointing. 
This  is  necessary  in  order  that  the  spots  where  the 
work  is  pointed  up  will  not  have  a  color  different  from 
the  remainder  of  the  surface. 

A  mortar  facing  or  plaster  may  be  considerably 
varied.  Usually  when  such  finish  is  intended  for 
monolithic  construction  or  for  concrete  block  con- 
struction the  concrete  when  placed  in  the  forms  is 
not  thoroughly  spaded  next  to  form  faces,  thus  in- 
tentionally leaving  exposed  pebble  pockets  on  the 
surface  which  will  insure  a  better  key  for  the  plasterer. 
In  block  construction  where  stucco  is  to  follow  the 
block  are  rough  cast  for  the  purpose  of  providing  a 
better  bond  for  the  mortar  coat.  But  the  mortar  coat 
itself  is  susceptible  to  considerable  variation.  It  can 
be  given  different  floated  finishes  by  using  a  steel 
trowel,  a  wood  float,  or  a  wood  float  covered  with  a 
piece  of  carpet  or  burlap.  Each  of  these  methods  of 
smoothing  the  finished  surface  produces  a  different 
texture. 

The  plaster  coat  may  also  be  varied  by  tinting, 
but  for  such  work  only  mineral  pigments  should  be 
used  because  other  colors  lack  permanence.  In  a  plas- 
ter coat  finish  another  variation  consists  of  pebble - 
dash  finish  which  is  secured  by  throwing  pebbles  of 
uniform  size,  thoroughly  washed  and  wet,  against 
the  soft  mortar  coat.  To  make  these  pebbles  adhere 
better  it  is  advisable  to  wet  them  with  a  thin  cement 

92 


grout  immediately  before  throwing  against  the  surface 
being  treated. 

Concrete  surfaces  can  be  tool  or  hammer  dressed 
in  just  the  same  manner  as  stone  surfaces  are  so  treat- 
ed. For  successful  hammer  dressing  or  tooling,  it  is 
very  necessary  that  the  aggregates  used  shall  be  of 
uniform  hardness  throughout  and  have  been  selected 
in  anticipation  of  such  surface  finish.  If  pebbles  are 
used  for  aggregate  and  have  considerable  variation 
in  hardness,  the  hammer  dressing  will  cause  some  of 
the  pebbles  to  break  out  of  the  surface  and  the  finish 
will  not  be  so  pleasing  as  where  aggregates  of  uniform 
hardness  throughout  are  used.  Also,  the  appearance 
of  the  work  will  be  considerably  influenced  by  the 
time  which  the  concrete  is  allowed  to  stand  before 
being  hammered.  If  too  soft,  particles  of  concrete 
will  be  loosened.  If  the  surface  is  too  hard,  the  work 
will  take  more  time  and  hence  be  more  expensive 

Surface  finish  of  great  attractiveness  can  be  se- 
cured by  using  special  concrete  mixtures.  These  are 
usually  facing  mixtures  in  which  the  aggregates  are 
selected  sands  and  stone  chips,  the  facing  being  placed 
at  the  same  time  as  the  mass  of  concrete  by  using  a 
metal  septum  in  the  forms.  After  forms  have  been 
removed  and  the  concrete  has  hardened,  the  aggre- 
gates may  be  exposed  in  a  number  of  ways.  The  sur- 
face may  be  tooled  if  so  desired,  or  it  may  be  scrubbed 
down  with  water  if  forms  can  be  removed  within 
the  first  twelve  hours  or  so  before  the  cement  is  thor- 
oughly hardened.  If  the  work  must  be  delayed  until 
later,  then  an  acid  wash  and  scrubbing  will  remove 
the  surface  film  of  cement  and  expose  the  colored 
aggregate.  The  possible  variations  of  colored  texture 
to  a  surface,  possible  by  using  special  concrete  mix- 
tures containing  selected  aggregates,  is  limited  only 
by  the  variety  of  aggregates  that  may  be  obtained; 
also  by  the  various  mixtures  that  may  be  made  by 
combining  two  or  more  of  these  aggregates. 

White  cement,  white  sand,  marble  dust,  quartz 
screenings,  mica  spar,  granite,  marble  chips  of  var- 
ious colors,  crushed,  screened,  graded  selected  chips 
singly  or  in  combination  are  used  in  special  concrete 
mixtures  for  various  colored  surfaces.  In  fact  where 

93 


colors  are  desired,  this  method  of  securing  them  is 
certain  to  result  in  permanence. 

Aggregates  are  sometimes  exposed  by  using  a  sand 
blast  which  removes  the  plastic  or  pasty  effect  given 
to  the  concrete  by  the  forms,  and  produces  a  granu- 
lated finish  somewhat  similar  to  sandstone  but  not  so 
uniform  because  the  aggregates  are  likely  to  be  irregu- 
larly exposed.  For  the  hammering  or  tooling,  pneu- 
matic hammers  are  often  used,  especially  where  large 
areas  must  be  treated  in  this  way.  Finishing  with 
pneumatic  hammers  produces  a  very  attractive  sur- 
face for  buildings  in  which  concrete  has  appropriate 
architectural  features.  The  bush  hammer  is  used  for 
intricate  portions  of  the  work  and  other  plane  portions 
are  dressed  with  the  pneumatic  hammer.  Owing  to 
the  cost  of  equipment  necessary  to  produce  sand  blast 
finish,  this  method  is  not  used  except  on  expensive 
structures  where  the  one  item  of  finish  does  not  bear  a 
great  relation  to  the  total  cost  of  the  work. 

In  finishing  concrete  surfaces  with  carborundum 
stone,  only  the  form  marks  can  be  removed  by  hand 
methods  without  excessive  labor.  Many  irregulari- 
ties cannot  be  entirely  obliterated.  A  machine  recent- 
ly placed  on  the  market  is  designed  to  remove  all 
marks,  giving  a  perfectly  straight  surface.  The  pro- 
cess is  a  dry  one.  The  machine  is  essentially  a  revolv- 
ing disc  in  which  are  mounted  a  number  of  hardened 
steel  cutter  wheels,  which  roll  on  the  surface  to  be 
dressed,  and  remove  the  material  by  a  chipping 
action.  The  disc  is  driven  through  a  flexible  shaft 
by  an  electric  motor,  carried  by  the  operator.  The 
cutting  action  can  be  made  to  give  a  surface 
resembling  that  obtained  by  a  bush  hammer,  which 
offers  a  good  bond  for  float  or  other  finish. 

There  are  also  on  the  market  several  floor  sur- 
facing machines  intended  for  use  in  finishing  terrazzo 
floors,  or  in  grinding  down  the  usual  cement  floor 
surfaces  where  it  is  desired  to  obtain  a  finish  similar 
to  terrazzo. 


94 


CHAPTER  5. 
^FORMS  FOR  CONCRETE  CONSTRUCTION 

Care  in  Manufacture  of  Forms 

No  part  of  concrete  construction  requires  more 
care  than  the  making  and  use  of  the  forms  in  which 
the  concrete  is  placed  to  harden.  The  appearance 
as  well  as  the  safety  of  the  finished  work  is  gov- 
erned in  a  large  degree  by  the  care  used  in  making 
and  erecting  the  forms.  Frequently  such  work  is 
so  carelessly  done  that  ends  of  upright  supports 
or  props  rest  on  soft  earth  in  such  a  manner  that 
beams,  girders  or  other  portions  of  a  structure  sag 
out  of  true  intended  line.  Often,  sides  of  beam  and 
girder  forms,  when  these  members  are  to  be  deep, 
are  sometimes  so  poorly  built  and  braced  as  to 
bulge  or  warp. 

Forms  supporting  the  concrete  for  floors  fre- 
quently are  not  propped  up  with  sufficiently  strong 
timbers  and  so  bulge  under  the  weight  of  concrete, 
usually  resulting  in  a  continual  sagging  of  the  form 
while  the  concrete  is  hardening,  thus  resulting  in 
permanent  cracks  on  the  under  side  of  the  slab. 
This  naturally  prevents  the  floor  from  having  the 
strength  for  which  it  was  designed. 

Contractor  responsible  for  forms 

In  all  cases,  care  in  the  construction  of  the  form 
work  is  very  evident  in  the  appearance  of  the  fin- 
ished work.  Usually  it  will  be  found  that  the  care 
and  judgment  displayed  in  building  and  erecting 
forms  will  be  proof  of  similar  care  exercised 
throughout  the  construction  and  the  results  of  this, 
other  things  being  equal,  will  insure  a  safe  build- 
ing of  fine  appearance. 

Construction  of  forms  should  be  left  to  the  con- 
tractor since  he  has  the  responsibility  for  the  work 
until  it  is  completed.  Naturally,  however,  there 
should  be  necessary  cooperation  between  represen- 
tative of  the  engineer  and  architect,  so  that  no  mis- 

95 


interpretation  of  specifications  will  be  responsible 
for  forms  not  in  strict  keeping  with  the  work's  re- 
quirements. "The  contractor's  drafting  forces  should 
be  impressed  with  the  responsibility  of  careful  de- 
sign of  forms,  so  that  in  every  respect  the  finished 
structure  may  conform  to  the  architect's  and  engi- 
neer's plans.  In  all  instances  the  engineer  should 
control  the  time  for  form  removal  on  any  engineer- 
ing construction  and  his  inspectors  should  be  quali- 
fied to  insure  the  safety  of  the  structure  by  intelli- 
gent inspection  of  falsework  and  supports. 

Many  types  of  forms  are  used  in  concrete  con- 
struction. Wood  and  steel  are  the  materials  most 
commonly  used.  Forms  may  vary  from  the  most 
simple  to  the  most  elaborate,  depending  upon  the 
nature  of  the  work  and  its  engineering  or  architec- 
tural details.  Some  forms  are  intentionally  built  for 
use  once  only.  Others  are  and  may  properly  be 
planned  for  repeated  use,  thus  insuring  considerable 
economy  of  form  cost  with  respect  to  any  one  job. 

Perhaps  the  most  extensive  use  of  steel  forms 
is  in  connection  with  the  manufacture  of  various 
classes  of  concrete  products  such  as  block,  brick, 
tile,  sewer  pipe,  concrete  trim-stone,  etc.  Most  of 
such  forms  or  molds  are  in  reality  a  part  of  the  ma- 
chine used  to  make  or  form  the  product.  However, 
steel  forms  are  used  extensively  in  various  other 
classes  of  concrete  construction.  Some  of  these 
forms  are  patented,  perhaps  with  particular  refer- 
ence to  a  patent  also  covering  a  so-called  system 
of  construction.  Many  of  them  are,  however, 
adaptable  to  any  type  of  monolithic  concrete  work. 
Among  the  examples  of  use  of  steel  forms  are  those 
used  in  connection  with  monolithic  sewer  construc- 
tion, bridge  arches,  culverts  and  such  circular  struc- 
tures as  silos,  tanks,  chimneys,  etc. 

Some  ornamental  concrete  products,  such  as 
garden  furniture,  trimstone  and  statuary,  are  cast  in 
plaster,  glue  or  sand  molds.  Such  work,  however, 
is  generally  confined  to  a  central  plant,  therefore 
hardly  comes  in  for  description  in  what  is  intended 
to  cover  principles  of  field  work  of  concrete  form 
construction. 


Form  Economy 

A  great  amount  of  material  and  labor  is  required 
in  the  construction  of  some  forms  on  engineering 
structures.  It  is  evident,  therefore,  that  the  cost  of 
this  work  is  not  a  small  part  of  the  cost  of  the  fin- 
ished building,  and  by  exercising  care  in  design 
much  material  and  labor  can  be  saved.  It  may  be 
best  in  some  cases  to  draw  up  sketches  from  which 
the  carpenters  who  are  to  build  forms  can  work 
and  thus  insure  least  waste  of  material. 

The  greatest  economy  is  gained  by  building 
forms  so  that  they  can  be  repeatedly  used.  It  is 
not  uncommon  to  construct  a  ten-story  building  by 
using  throughout  the  form  work  employed  for  the 
first  three  stories.  This  fact  should  be  borne  in 
mind  in  the  design  of  reinforced  concrete  structures 
because  it  is  frequently  cheaper  to  keep  the  columns 
of  the  same  dimension  throughout  in  order  to  save 
the  cost  of  changing  forms.  That  is  more  true  now 
than  ever  in  view  of  the  great  increase  in  cost  of 
labor  and  the  scarcity  of  materials.  Where  beam 
and  girder  construction  is  used,  consideration  of 
form  cost  as  against  the  use  of  a  slight  increased 
quantity  of  concrete  will  often  determine  whether 
it  would  be  more  desirable  to  reduce  the  size  of 
section  or  leave  it  the  same  size  as  other  corre- 
sponding sections  of  the  building. 

Economy  in  form  construction  results  from  de- 
vising ways  and  means  to  fasten  sections  together 
and  in  position  on  the  work  so  that  the  least 
amount  of  nailing  will  be  required.  Every  nail  that 
is  driven  home  gives  trouble  when  the  forms  are 
taken  down,  and,  because  of  careless  handling,  may 
result  in  much  injury  to  forms,  not  to  mention  in- 
jury to  concrete  which  has  not  thoroughly  hard- 
ened, from  the  hammering  and  knocking  necessary 
to  dismantle  forms.  In  many  cases  wedges, 
clamps,  ties,  brackets  and  a  variety  bf  fastening  de- 
vices other  than  nails  can  be  used,  thus  consider- 
ably reducing  the  labor  to  set  and  take  down  forms 
and  also  resulting  in  prolonging  their  life  for  use 
a  greater  number  of  times. 

97 


Safety  Dependent  on  Form  Construction 

The  safety  of  a  reinforced  concrete  floor,  as  well 
as  that  of  the  entire  structure,  may  be  jeopardized 
by  faulty  form  construction.  Many  of  the  failures 
of  reinforced  concrete,  if  not  most  of  them,  can  be 
traced  directly  to  weakness  in  the  forms  used,  due 
to  faulty  construction  of  their  supports  or  the  false 
work.  For  example,  if  forms  for  beams  and  girders 
are  supported  by  struts  of  insufficient  strength, 
causing  a  collapse  of  the  form  in  one  part,  the 
probability  is  that  the  forms  of  the  whole  floor  will 
collapse  with  it  and  deposit  its  contents  on  the  floor 
below.  A  load  suddenly  applied  in  this  manner  to 
the  floor  below  might  cause  collapse  of  the  whole 
building,  since  the  accident  would  probably  take 
place  at  a  time  when  none  of  the  concrete  had  at- 
tained the  strength  ultimately  to  be  realized. 

In  order  that  there  may  be  no  doubt  regarding 
the  safety  of  forms,  they  should  be  carefully  in- 
spected before  any  of  the  concrete  is  placed.  Up- 
right supports  and  braces  must  be  examined  to.  de- 
termine that  they  are  sufficiently  strong  to  carry 
the  weight  of  the  wet  concrete.  Frequently,  false 
work  and  braces  are  improperly  placed  and  do  not 
have  sufficient  support.  It  is  also  not  uncommon 
to  find  forms  braced  against  green  masonry  and 
brick  work  and  struts  secured  with  a  few  wire  nails 
where  they  should  have  been  notched  into  support- 
ing timbers  and  well  spiked  in  position. 

Standardization  of  Panels 

In  the  construction  of  forms,  it  is  often  possible 
to  standardize  a  set  of  panels  that  will  permit  of 
considerable  latitude  in  setting  up,  thus  making 
re-use  of  the  same  set  of  forms  possible  a  large 
number  of  times.  Sometimes  such  panels  are  metal 
lined  with  galvanized  sheeting  in  order  to  prolong 
their  life  and  at  the  same  time  insure  a  better  ap- 
pearing finished  surface  to  the  work. 

Wood  Forms 

Where  wood  forms  are  used  most  of  the  work 
of  cutting  and  erecting  forms  is  done  on  the  build- 

98 


ing  site.  However,  for  some  classes  of  work  such 
as  foundations  for  relatively  small  structures  like 
dwellings,  standard  panels  are  used  and  if  carefully 
handled  may  be  re-used  a  number  of  times,  On 
account  of  the  cost  of  form  construction,  any  suc- 
cessful attempt  to  standardize  sections  so  that  wood 
forms  can  be  used  repeatedly  is  likely  to  prove 
profitable.  Some  of  the  various  so-called  form  sys- 
tems which  have  already  been  mentioned  are 
adaptable  to  a  variety  of  construction  uses  other 
than  the  particular  system  of  construction  for  which 
originally  devised. 

The  kind  of  lumber  to  use  for  form  construc- 
tion depends  to  a  considerable  extent  on  the  kind 
available  and  whether  the  material  after  first  use  is 
to  be  again  used  in  similar  work;  also,  whether  the 
building  is  to  have  many  floors  of  the  same  design 
and  construction  or  whether  only  two  or  three 
stories.  Ordinarily,  good  material  should  be  used 
in  form  work,  for  it  permits  good  carpenter  work 
and  also  smooth,  true  concrete  work.  To  support 
forms  it  is  the  custom  to  use  as  cheap  a  grade  of 
rough,  sound  lumber  as  can  be  purchased.  For  the 
sheathing,  or  that  portion  of  the  form  in  contact 
with  the  concrete,  it  is  best  to  use  a  good  grade  of 
well  seasoned  hard  pine  because  such  material  pos- 
sesses both  strength  and  grain  of  sufficient  close- 
ness to  prevent  the  form  boards  from  splintering 
badly.  Norway  pine,  when  obtainable,  is  one  of 
the  best  materials.  The  hardwoods  are  too  costly 
and  too  expensive  to  work.  The  softer  woods  do 
not  permit  of  repeated  use,  although  for  exception- 
ally fine  surface  finish  and  detail,  it  is  sometimes 
necessary  to  use  soft  grades  of  pine  because  of  the 
ease  with  which  carpentry  can  be  done  on  the 
forms  to  reproduce  the  surface  wanted. 

If  the  forms  are  to  be  used  once  only,  sheathing 
is  generally  made  up  of  1-inch  dressed  material.  If 
they  are  to  be  used  several  times,  the  side  and  bot- 
tom form  boards  of  beams  and  girders  are  made  of 
either  \y2  or  2-inch  dressed  planks.  Shores  and 
supports  for  the  centering  generally  consist  of 
rough  3  by  4-inch  studding.  Timbers  as  large  as 

99 


4  by  6,  6  by  8,  and  8  by  10  may  be  used  to  brace 
and  secure  form  work  where  the  masses  of  concrete 
to  be  supported  are  exceptionally  heavy. 

Sliding  Forms 

In  some  instances  sliding  forms  are  used  in  cer- 
tain classes  of  construction,  notably  in  the  erection 
of  circular  grain  tanks  or  other  buildings  which  it 
is  intended  shall  be  truly  monolithic  throughout. 
Such  forms,  as  the  name  implies,  are  kept  moving 
continually  upward  as  concrete  is  placed.  In  gen- 
eral, sliding  forms  consist  of  wide  outer  and  inner 
panels,  operated  by  means  of  jacks  which  derive 
their  support  from  vertical  rods  or  pipes  embedded 
in  the  concrete.  The  use  of  sliding  forms  requires 
continuous  placing  of  concrete  for  twenty-four 
hours  daily  so  that  the  forms  may  be  moved  up- 
ward slowly  at  a  steady  and  uniform  rate,  thus  pre- 
venting concrete  from  adhering  to  them.  In  the 
use  of  silding  forms  it  is  essential  that  at  all  points 
the  forms  be  kept  in  exact  horizontal  and  vertical 
relation  to  each  other.  These  requirements  indi- 
cate that  although  the  system  is  quite  simple,  ex- 
perience and  constant  watchfulness  must  be  on  the 
job  to  obtain  the  best  results.  Also  the  system  of 
jacking  up  the  forms  must  permit  of  positive  con- 
trol and  there  must  be  no  slipping  of  the  jack  on 
its  support. 

Sliding  forms  are  usually  made  fast  to  an  upper 
and  lower  wale,  consisting  of  2-inch  planks  with 
overlapping  joints.  In  circular  concrete  construc- 
tion, one  edge  of  these  planks  is  cut  to  a  radius  of 
the  wall  surface  plus  or  minus  the  thickness  of  the 
sheathing.  Therefore,  there  is  an  inside  and  out- 
side pair  of  wales  cut  to  segments  corresponding 
to  the  curve  of  the  outside  and  the  inside  of  the 
wall  respectively.  To  these  built  up  wales,  1-inch 
sheathing)  about  four  feet  long  is  nailed  usually 
with  triangular  bracing  between  the  wales  to  give 
the  forms  required  rigidity.  The  yokes  are  at- 
tached at  intervals  to  these  forms  and  may  be  en- 
tirely of  wood,  although  the  head  piece  is  often 
made  of  steel  plates  so  as  to  insure  little  variation 

100 


in  the  separation  of  forms  and  .to  give  a  rigid 
member  to  take  the  lifting  action  of  the  jacks. 

Jacks  used  are  of  several  different  types,  some 
of  which  are  patented.  Two  types  are  common. 
Both  of  these  work  on  the  jack  screw  principle.  A 
common  type  of  jack  consists  of  a  hollow  screw 
fitted  at  its  top  with  a  turning  head  and  at  its  bot- 
tom with  a  device  commonly  known  as  a  ratchet, 
or  "dog,"  for  gripping  a  vertical  jack  rod  which  is 
embedded  in  the  concrete.  The  jack  rod  passes  up 
through  the  center  of  the  jack,  which  in  turn  passes 
through  the  threaded  head  piece  of  the  yoke.  By 
turning  the  turning  head  with  a  bar,  the  yoke  is 
caused  to  move  up,  taking  the  forms  with  it.  Suc- 
cessive turnings  of  the  jacks  through  the  same 
angle  will  thus  cause  every  portion  of  the  forms 
to  move  the  same  distance.  A  strict  regulation  of 
the  amount  of  turning  which  each  turning  head  is 
given  is  absolutely  necessary  to  correct  operation 
of  the  forms. 

Another  type  of  jack  consists  of  a  threaded  rod 
fitted  with  a  collar  which  bears  on  a  ly^-inch  pipe 
embedded  in  the  concrete.  The  threaded  rod 
passes  through  the  head  piece  of  the  yoke  and  is 
fitted  with  a  turning  head.  The  pipe  is  made  in 
3-foot  lengths,  cut  square  at  the  ends  and  without 
threads.  The  lower  end  of  the  threaded  jack  rod 
extends  down  through  the  3-foot  length  of  pipe  and 
6  inches  into  the  pipe  below.  This  keeps  all  of 
the  3-foot  lengths  of  pipe  in  line,  while  the  col- 
lar bearing  on  the  top  of  the  uppermost  pipe  fur- 
nishes a  positive  support  to  the  jack.  When  the 
forms  have  been  raised  the  full  distance  of  their 
travel  for  one  position  of  the  jacks,  the  clutch  is 
released,  the  jack  moved  up  and  a  short  length  of 
rod  or  pipe,  as  the  case  may  be,  placed  on  top  of 
and  in  line  with  those  already  embedded  in  the 
wall.  The  ratchet  then  engages  the  rod  and  the 
work  proceeds.  When  rods  are  used,  the  successive 
short  lengths  are  connected  by  sleeves. 

Sliding  forms  have  been  used  for  a  considerable 
variety  of  structures.  These  include  standpipes, 
water  tanks,  grain  tanks,  grain  elevators,  mill 


101 


'ar-d.  chimneys.  The  system  is  also  adapted 
to  the  construction  of  hollow  concrete  piers  and 
warehouses  or  walls,  although  it  has  so  far  been 
but  little  used  in  such  construction.  When  such 
forms  are  used  by  experienced  contractors  in  the 
construction  of  mill  and  elevator  buildings,  window 
openings  can  easily  be  provided  for  and  cross 
beams  from  one  wall  to  another  also  can  be  con- 
structed without  special  difficulty. 

Dry  Form  Lumber  Desirable 

Form  lumber  should  be  free  from  shakes,  rot 
and  knots.  Knots  and  similar  imperfections  leave 
their  imprint  on  the  finished  surface  of  the  concrete 
and  in  addition  weaken  the  lumber,  hence  the 
forms.  Air  seasoned  lumber  is  better  than  kiln 
dried.  The  latter  will  swell  and  bulge  at  the  joints, 
while  green  lumber  will  shrink  if  not  kept  wet,  re- 
sulting in  the  opening  of  cracks  through  which 
water  carrying  cement  will  leak  when  the  concrete 
is  placed.  Even  for  rough  work,  lumber  that  is 
dressed  at  least  on  one  side  and  two  edges  is  best 
for  form  sheathing  so  as  to  make  the  boards  fit 
closely  together.  The  planed  surface  will  also  re- 
duce the  labor  of  removing  and  cleaning  forms. 
Tongued  and  grooved  stock,  as  well  as  ship-lap  is 
often  used  for  sheathing.  Beveled  edge  stock  is 
preferred  by  some  because  if  the  lumber  swells,  the 
edges  will  slip  past  each  other  without  causing  a 
warping  or  bulging  of  the  boards.  Form  sheathing 
should  be  of  uniform  thickness  to  prevent  uneven- 
ness  in  the  concrete  surface. 

Cost  of  Forms 

The  cost  of  forms  varies  within  a  wide  range. 
One  of  the  most  accurate  methods  of  estimating  the 
cost  of  wood  forms  is  to  figure  the  board  measure 
of  lumber  and  the  hardware  required,  the  carpenter 
labor  per  thousand  board  measure  to  erect,  the 
labor  of  taking  down  and  cleaning  forms,  and  the 
cost  of  transporting  lumber  to  and  from  the  job.  A 
certain  percentage  of  the  cost  of  form  lumber 
should  be  charged  to  the  job.  What  this  shall  be 

102 


can  be  learned  only  from  carefully  compiled  data 
covering  a  number  and  variety  of  jobs  that  will  dis- 
close how  long  forms  may  be  used  repeatedly.  The 
amount  of  skilled  and  common  labor  required  to 
make,  erect  and  dismantle  forms,  depends  upon  how 
complicated  they  are  and  the  conditions  under 
which  the  men  work.  The  amount  of  carpenter 
labor  per  thousand  board  measure  of  lumber  for 
form  work  is  often  difficult  to  estimate.  A  carpen- 
ter experienced  on  concrete  form  work  can  accom- 
plish more  than  one  whose  experience  has  been 
confined  to  general  building  construction.  Experi- 
enced form  carpenters  bear  in  mind  that  forms 
must,  if  possible,  be  designed  and  built  to  permit 
salvage  and  further  use,  therefore,  do  no  more  cut- 
ting of  lumber  than  necessary.  They  also  plan  the 
forms  so  that  they  may  easily  be  taken  down  with 
least  damage. 

Along  with  all  other  commodities  lumber  has 
increased  in  cost.  Consequently,  it  costs  more  to 
make  wood  forms  than  it  used  to.  For  that  very 
reason  greater  care  in  making  forms  with  respect 
to  cutting  and  fitting  the  various  pieces  as  well  as 
greater  care  in  erecting  and  dismantling  forms  is 
likely  to  pay  better  than  ever.  It  should  be  pos- 
sible to  use  forms  several  times  and  the  greater  the 
number  of  times  they  can  be  used,  the  lower  the 
percentage  of  original  cost  to  be  charged  against 
any  one  job.  For  certain  classes  of  construction, 
form  lumber  can  be  used  ten  times.  Seldom  should 
more  than  twenty-five  per  cent  of  the  first  cost  be 
charged  to  one  use  unless  there  is  an  unusual 
amount  of  cutting  of  stock  lengths. 

Wetting  Forms 

In  dry,  hot  weather  it  is  common  to  wet  down 
forms  immediately  before  placing  concrete  in  them. 
This  assists  to  prevent  concrete  from  sticking  to 
the  forms  and  also  keeps  the  forms  from  absorbing 
water  from  the  concrete,  necessary  to  its  harden- 
ing. Each  time  after  taking  down  and  before  using 
again,  forms  should  be  thoroughly  cleaned  of  all  ad- 
hering concrete. 

103 


Centering  and  Falsework 

The  construction  of  centering  and  false  work 
for  reinforced  concrete  bridges  must  be  sufficiently 
strong  to  carry  the  weight  of  the  wet  concrete  of 
the  completed  structure  without  deflection  or  move- 
ment. All  such  form  work  must  be  securely 
braced  against  failure  from  the  pressure  of  con- 
crete. The  principal  requirement,  however,  is  that 
the  centering  be  so  arranged  that  it  may  be  readily 
dropped  away  when  the  concrete  has  hardened  suf- 
ficiently to  be  self-sustaining  and  it  is  desired  to 
remove  the  forms.  Probably  the  best  method  is  to 
use  wedges  of  hardwood  under  main  uprights  or 
under  the  false  work  supporting  the  lagging,  then 
these  can  be  backed  out,  thus  allowing  the  center- 
ing to  settle  under  them.  Another  method  is  to 
use  what  is  known  as  a  sand  box,  which  consists 
of  a  tight  metal  box  fitted  with  a  plunger  upon 
which  the  uprights  stand.  The  box  is  filled  with 
sand  and  in  it  is  a  small  aperture  which  can  be 
closed  with  a  screw  plug  or  some  other  way.  When 
desired  to  drop  the  centering,  the  aperture  is 
opened,  allowing  the  dry  sand  to  flow  out,  thus 
permitting  the  plunger  and  centering  to  settle. 
Sometimes  centering  is  built  on  screw  jacks  and 
where  several  arch  rings  are  to  be  built  parallel 
with  each  other,  the  entire  centering  is  built  on 
trucks  or  rollers  carried  on  a  track.  In  this  way 
when  one  arch  ring  has  been  completed,  the  false 
work  may  readily  be  shifted  to  the  new  position. 

. 


104 


CHAPTER  6. 
USE  OF  REINFORCING  STEEL  IN  CONCRETE 

Need  for  Reinforcement 

Reinforced  concrete  is  defined  as  a  combination 
of  concrete  and  metal,  preferably  steel  of  certain 
determined  quality,  the  metal  being  so  placed  as 
regards  position  and  quantity  that  the  concrete  and 
the  metal  both  take  and  resist  the  strains  which 
they  can  best  withstand. 

Concrete  is  about  ten  times  as  strong  in  com- 
pression as  in  tension.  Plain  concrete — that  is, 
concrete  without  any  reinforcement  in  it — would 
have  to  be  unnecessarily  massive  to  possess  the 
required  strength  as  subjected  to  tension  in  con- 
struction. As  a  matter  of  fact,  it  would  be  found 
impossible  to  design  most  structures  of  concrete 
were  it  not  that  steel  is  embedded  in  it  to  provide 
the  tensile  strength  which  concrete  lacks  and  at  the 
same  time  fully  utilize  its  compressive  strength.  In 
mass  work  where  the  load  is  placed  immediately 
upon  concrete — that  is,  where  the  load  is  one  of 
compression  entirely — reinforcement  is  seldom  if 
ever  used,  but  great  economy  of  design  as  well  as 
the  great  utility  of  concrete  has  resulted  from 
proper  disposition  of  reinforcement  in  it. 

Quality  of  Reinforcing  Steel 

Any  quality  of  steel  will  not  do  for  reinforce- 
ment. Usually  a  certain  quality  is  specified,  that  is 
steel  having  a  certain  chemical  composition  and 
given  physical  properties.  Such  steel,  if  properly 
embedded  in  concrete  of  correct  proportions  and 
consistency  so  that  everywhere  the  concrete  will 
bond  or  adhere  perfectly  to  the  metal,  takes  the 
pulling  and  bending  strains  because  the  adhesion 
between  the  concrete  and  the  steel  prevents  the  lat- 
ter from  slipping  in  the  mass.  These  facts  make 
it  possible  to  use  concrete  in  many  ways  that 
would  be  impracticable  were  it  not  reinforced. 

105 


Position  of  Steel 

In  the  design  of  concrete  structures,  the  quan- 
tity and  position  of  steel  are  indicated  on  the  plans. 
It  is  important  that  no  less  a  quantity  be  used  than 
called  for  and  still  more  important  that  the  position 
of  the  steel  as  shown  be  strictly  secured  in  the  pro- 
cess of  construction. 

The  position  of  steel  is  determined  by  the  na- 
ture of  the  loads  to  which  the  structural  member 
or  portion  of  the  building  is  to  be  subjected  and 
also  to  insure  that  it  is  covered  with  sufficient  con- 
crete to  protect  it  from  prolonged  exposure  to  fire 
and  from  corrosion  due  to  possible  penetration 
of  moisture. 

Piers 

In  piers,  posts  and  columns  the  concrete  takes 
compression  assisted  by  the  steel,  and  the  vertical 
steel  takes  tension  if  any  bending  occurs. 

Beams 

In  beams  there  are  stresses  of  compression, 
tension  and  shear.  The  concrete  takes  all  the  com- 
pression and  a  limited  amount  of  shear.  The  steel 
is  computed  as  taking  all  the  direct  tension  and 
assists  the  concrete  to  carry  shear  stresses. 

Columns 

It  is  customary  to  reinforce  all  columns  whether 
reinforcement  is  theoretically  required  or  not.  The 
practice  is  to  use  at  least  four  rods  so  disposed  in 
the  column  that  their  location  corresponds  to  the 
four  corners  of  a  square.  In  no  case  should  the 
steel  be  nearer  the  surface  than  one  and  one-half 
to  two  inches,  since  it  is  desirable  to  prevent  any 
tendency  of  the  vertical  rods  to  buckle  under  ec- 
centric stresses  or  working  loads.  It  is  also  cus- 
tomary to  place  occasional  horizontal  hoops  or  ties 
around  the  vertical  steel.  Such  hoops  in  the  form 
of  wire  ties  are  helpful  in  holding  the  rods  in  cor- 
rect position  while  concrete  is  being  placed.  In 
some  systems  of  reinforcing  columns,  reinforcement 

106 


is  shipped  to  the  job  practically  assembled.  The 
same  is  true  in  part  of  reinforcement  for  certain 
types  of  beams  or  girders. 

Types  of  Reinforcements 

In  addition  to  plain  round,  plain  square  and 
twisted  square  bars,  there  are  various  types  of 
deformed  bars  used  for  concrete  reinforcement.  In 
general,  the  deformation  consists  of  lugs  or  other 
projections  formed  on  their  surface  during  the  pro- 
cess of  rolling.  The  principal  object  of  such  de- 
formation is  to  increase  mechanical  bond  and  to 
safeguard  against  the  effect  of  absence  of  mechan- 
ical bond  in  places  where  concrete  may  not  every- 
where surround  or  be  in  contact  with  the  steel. 

In  addition  to  steel  bars  of  various  forms,  there 
are  many  so-called  metal  fabrics  or  meshes  used  as 
concrete  reinforcement.  The  material  commonly 
known  as  "expanded  metal"  for  example,  is  formed 
by  slotting  sheets  of  steel  having  required  thick- 
ness and  physical  properties,  then  stretching  or  ex- 
panding the  sheet,  thus  opening  the  slots  and  con- 
siderably increasing  the  area  of  the  sheet.  Some 
types  of  expanded  metal  are  particularly  adapted 
to  exterior  and  interior  plaster  work  such  as  stucco. 
Some  others  are  intended  to  be  used  so  that  they 
will  make  actual  forms  unnecessary,  even  to  secure 
monolithic  construction.  For  example,  a  steel 
frame  is  set  up,  expanded  metal  or  so-called  metal 
lath  attached  to  each  side  of  this  frame,  the  space 
between  lath  filled  with  concrete  and  finally  both 
outside  surfaces  plastered,  thus  giving  a  monolithic 
reinforced  wall. 

Other  types  of  mesh  reinforcement  may  be 
likened  to  woven  wire  fencing  or  to  square  mesh 
fabric  similar  to  that  used  for  common  screens. 
These  vary  in  weight  per  certain  area  due  to  the 
weight  of  strands  of  wire  used  in  forming  the  fab- 
ric. Some  such  fabrics  are  woven,  others  are  weld- 
ed where  the  strands  intersect  or  cross. 

It  makes  little  difference  which  one  of  these 
forms  of  reinforcement  is  used  in  certain  classes 
of  work,  other  than  that  perhaps  in  specific  cases 

107 


some  one  type  will  be  more  economical  or  may  be 
otherwise  used  more  advantageously.  The  principal 
thing  to  observe  is  that  the  physical  properties  of 
the  steel  and  the  net  cross-sectional  area  of  steel  are 
satisfactory  and  the  material  is  in  the  proper  place 
to  take  all  the  tension  to  which  it  will  be  subjected. 

Handling  Reinforcement  on  the  Work 

Often  on  the  job,  reinforcing  metal  is  carelessly 
thrown  about  and  allowed  to  become  rusty  and  per- 
haps covered  with  oil  or  other  filth.  Care  should  be 
taken  when  placing  it  to  make  certain  that  it  is  free 
from  mill  scale  or  scale  in  the  form  of  rust.  Either 
of  these  can  be  removed  by  pickling  in  weak  acid 
or  perhaps  by  brushing  with  stiff  wire  brushes. 

Frequently  some  steel  must  be  shaped  on  the  job 
to  conform  to  the  details  of  design  shown  on  the 
building  plans.  Various  devices  are  used  for  bend- 
ing steel,  typical  among  which  are  Koehring  bar 
benders.  These  are  made  in  two  sizes.  The  smaller 
will  bend  bars  cold  up  to  one  inch  square.  The 
bending  die  is  two  inches  in  diameter,  giving  a  one- 
inch  radius  to  the  inside  curve  of  the  bar  at  the 
bend,  and  has  roller-bearing  journal.  The  guide 
block  is  provided  with  a  large  roller,  allowing  the 
bar  to  follow  freely,  in  order  to  avoid  fracturing 
by  too  great  tension.  This  roller  reduces  friction 
to  a  minimum. 

The  large  type  will  bend  up  to  134-inch  round  or 
lJ4'mch  square.  The  bending  die  is  3  inches  in  di- 
ameter, which  gives  a  IJ^-inch  radius  to  the  inside 
curve  of  the  bar  at  the  bend,  and  likewise  has  roller- 
bearing  journal.  This  bender  is  provided  with  an 
adjustable  clamp,  which  automatically  adjusts  itself 
to  the  thickness  of  the  bar,  and  securely  holds  the 
bar  at  one  end.  It  is  so  constructed  that  the  small 
bars  can  be  bent  with  direct  leverage,  and  bars  one 
inch  and  larger  can  be  bent  with  two  men  by  using 
the  back  gear  attachment.  The  pinion  is  provided 
with  a  ratchet  lever,  and  this  pinion  engages  the 
gear  segment  on  the  main  frame. 

108 


The  bending  point  is  central  with  the  journal, 
which  gives  it  greatest  leverage,  and  this  combined 
with  the  roller  bearing  journal  and  roller  guide 
makes  it  possible  to  bend  the  bars  with  least  force. 
Any  size  bar  up  to  1%-inch  round  can  be  bent 
without  making  any  adjustments.  The  bender  also 
affords  advantages  of  counterbending,  without  re- 
moving the  bar  or  without  making  adjustments  in 
case  a  bar  has  been  bent  too  much. 

It  is  also  necessary  to  have  a  device  capable  of 
cutting  bars  as  may  be  required.  One  of  the  most 
efficient  tools  for  this  purpose  is  the  Koehring  bar 
cutter,  also  made  in  two  sizes. 

In  designing  this  bar  cutter  the  primary  object 
was  to  provide  a  machine  light  in  weight,  conven- 
ient to  handle,  effective  in  operation,  and  simple 
in  construction,  so  it  will  not  get  out  of  order. 

The  cutting  jaws  are  so  arranged  that  it  be- 
comes more  powerful  as  the  resistance  increases  in 
advancing  the  cut,  and  so  that  the  bar  to  be  cut  will 
not  be  pushed  away  by  the  two  knives  in  the  cut- 
ting action.  When  cutting,  the  two  knives  advance, 
which  makes  a  clean,  square  cut,  and  does  not  leave 
fractured  ends. 

The  cutters  are  built  entirely  of  steel,  and  in- 
clude handle  for  operating.  With  the  No.  1  size  one 
man  can  easily  cut  a  ^-in.  square  twisted  or  round, 
and  with  the  No.  2-A  size  two  men  can  easily  cut 
a  1%-inch  round  or  a  1 54-inch  square  twisted  bar. 

Stops  are  provided  to  prevent  the  bar  from 
twisting,  and  in  cutting  the  various  thicknesses, 
care  must  be  taken  that  the  bar  is  placed  at  right 
angle  with  the  knives  and  that  a  spacing  block  is 
placed  between  the  bar  and  the  stop  post.  If  the 
space  between  the  bar  and  the  post  is  not  filled  in, 
it  will  allow  the  bar  to  twist  while  the  knives  are  in 
cutting  action,  and  this  will  cause  them  to  break 
out.  See  that  the  bar  is  placed  straight  through 
the  opening  at  right  angle  with  the  blades,  and 
that  a  piece  of  wood  or  iron  is  placed  between  the 
stop  post  and  the  bar. 

In    shaping    steel    by    bending,  care  should  be 

109 


taken  not  to  exert  the  bending  strain  suddenly  or 
violently,  but  rather  gradually  and  uniformly  to 
prevent  any  fracture  at  the  point  of  bend. 

Makeshift  Reinforcement  Dangerous 

No  doubt  concrete  failures  have  resulted  be- 
cause of  makeshift  practices  in  reinforcing.  Old 
chain,  wire  cable  and  similar  scrap  material,  which 
seldom  can  be  handled  to  advantage  in  the  forms, 
is  quite  likely  to  be  ineffective  even  though  the  sum 
total  of  metal  used  is  greatly  in  excess  of  actual 
requirements  determined  by  design.  Generally  this 
is  due  to  the  fact  that  once  a  strain  of  tension  comes 
on  the  concrete  greater  than  it  can  bear  the  immedi- 
ate help  of  reinforcement  is  lacking  because  the 
steel  or  other  metal  was  so  placed  as  not  to  take 
tension  immediately. 

It  is  necessary  that  the  action  of  reinforcement 
be  continuous,  and  as  in  some  classes  of  work  bars 
cannot  be  secured  of  sufficient  length  to  extend  be- 
tween two  desired  points,  it  is  necessary  to  splice 
them.  Splicing  is  usually  done  by  lapping  the  bars 
a  certain  number  of  times  their  diameter,  roughly 
50  to  60  times  this  diameter,  at  a  point  of  least 
stress.  It  is  common  where  laps  are  necessary  in 
rectangular  structures,  to  make  them  at  or  near  the 
center  of  one  side  rather  than  at  or  near  a  corner. 

Examples 

Two  simple  examples  will  serve  to  illustrate  the 
results  obtained  by  hoop  reinforcing  of  a  column. 
Make  a  cylinder  of  thin  paper  and  fill  it  with  sand. 
The  paper  may  be  strong  enough  to  hold  the  sand 
if  not  disturbed,  but  if  a  load  is  put  on  top  the  paper 
will  burst  and  the  sand  will  flow.  If  the  shell  of  a 
tin  can,  when  top  and  bottom  is  removed,  is  used  in 
place  of  the  paper  cylinder,  it  will  take  considerable 
load  to  burst  the  tin  confining  the  sand.  If,  instead 
of  sand,  the  cylinder  is  filled  with  cement  mortar  or 
concrete,  it  can  be  seen  that  the  concrete  will  take 
its  full  measure  of  load  in  compression  and  will 
have  the  benefit  of  the  encircling  tin  to  prevent 

no 


crushing  or  failure  when  the  safe  compressive  load 
of  the  concrete  has  been  approached  or  exceeded. 

The  principle  of  reinforcement  in  a  beam  can  be 
illustrated  in  a  very  simple  manner.  If  a  column  of 
concrete  is  made  6  by  12  inches  in  square  dimension 
and  10  feet  long,  then  laid  in  such  position  that  its 
two  ends  only  are  supported,  it  corresponds  to  a 
beam.  Realizing  that  concrete  is  relatively  weak 
in  tension,  it  can  readily  be  seen  that  it  would 
easily  be  possible  to  make  this  concrete  beam  break 
of  its  own  weight  by  increasing  its  length  suffi- 
ciently between  supports.  The  neutral  axis  in  a 
beam  is  the  point  where  the  character  of  stress 
changes  from  tension  to  compression  or  from  com- 
pression to  tension.  In  a  beam  of  homogeneous 
material,  that  is,  one  in  which  the  tensile  and  com- 
pressive strengths  are  equal,  with  symmetrical 
cross  section,  the  neutral  axis  will  be  midway  be- 
tween the  top  and  bottom  surface,  or  skin.  At  this 
point  stress  is  zero.  At  other  points  throughout 
the  section  it  will  vary  in  amount  and  nature  (ten- 
sion or  compression)  with  reference  to  the  location 
of  the  neutral  axis. 

It  is  not  the  purpose  of  this  discussion  to  elab- 
orate on  the  subject  of  reinforcing  concrete  since  it 
is  a  very  technical  one  and  requires  a  thorough 
knowledge  of  engineering  for  a  full  understanding. 

Frequently  reinforcement  is  used  in  some  parts 
of  structures  not  because  an  increase  of  structural 
strength  is  necessary,  but  to  prevent  unsightly 
cracks  due  to  volume  changes  in  the  concrete  from 
changes  in  temperature,  in  other  words,  from  ex- 
pansion and  contraction.  Such  reinforcement  is 
known  as  "temperature  reinforcement." 


111 


112 


CHAPTER  7. 
NOTES  ON  SPECIFICATIONS 

Specifications  Should  be  Clear 

Specifications  for  any  construction  work  of  im- 
portance are  necessary  so  that  there  may  be  a  clear 
understanding  on  the  part  of  the  contractor  as  to 
the  methods  by  which  the  work  is  to  be  carried  on 
to  conform  with  the  engineer's  plan. 

The  first  requirement  of  any  set  of  specifica- 
tions is  that  it  shall  be  in  such  form  as  to  present 
only  legal  demands  and  afford  legal  protection  to 
all  persons  interested.  This  means  that  a  specifi- 
cation should  be  so  worded  as  to  be  easy  of  inter- 
pretation. It  should  not  contain  phrases  or  expres- 
sions that  by  any  chance  might  be  given  more  than 
one  interpretation. 

Technical  terms  and  phrases  must  necessarily  be 
a  large  part  of  the  text  of  specifications.  Such 
terms  are  well  understood  by  the  engineering  and 
contracting  professions,  yet  it  is  possible  to  so  refer 
to  technical  subjects  that  a  clear  understanding  of 
them  may  be  had  by  anyone  who  can  read.  It  is 
well  in  the  case  of  some  unusual  terms  or  expres- 
sions to  append  to  the  specifications,  if  necessary, 
a  glossary  of  terms  that  will  define  such  words  or 
phrases  in  the  light  in  which  they  are  to  be  inter- 
preted in  reading  the  specifications. 

Responsibility  should  be  Clearly  Defined 

Specifications  should  not  be  drawn  in  such  a  way 
as  to  release  the  engineer  from  responsibility  justly 
his.  If  for  any  reason  there  is  wisdom  in  dividing 
responsibility,  the  specifications  should  be  so  clear- 
ly worded  as  to  indicate  what  responsibilities  rest 
solely  on  the  engineer  or  on  the  contractor,  and 
what  responsibility  is  to  be  shared  between  them. 

Another  important  requirement  of  specifications 
is  that  they  shall  demand  only  methods  that  are 

113 


generally  recognized  as  practicable — that  is,  no 
unreasonable  demands  or  requirements  should  be 
made.  Also,  it  is  poor  practice  to  write  rigid  speci- 
fications if  there  is  no  intention  of  carrying  them 
out  literally  as  written. 

There  probably  never  will  be  a  piece  of  work 
where  minor  adjustments  will  not  be  necessary 
from  time  to  time  as  the  work  progresses,  but  this 
does  not  mean  that  the  specifications  applying  are 
not  practical.  Specifications  should  be  so  defined 
that  the  contractor  may  know  as  nearly  as  possible 
the  grade  or  grades  of  materials  he  will  be  expected 
to  furnish,  the  quantity  of  work  he  will  have  to  do 
and  as  much  other  accurate,  necessary  information 
as  possible.  They  should  be  so  drawn  that  neither 
a  superficial  analysis  of  them,  nor  an  attempt  to 
carry  them  out,  will  prove  that  they  are  at  variance 
with  the  plans  on  which  they  are  based. 

Features  for  Consideration 

Among  the  various  features  of  work  that  must 
be  given  consideration  in  drawing  specifications  for 
plain  and  reinforced  concrete  construction,  are  the 
following : 

Cement 

Aggregates 

Mixing  water 

Reinforcing  steel 

Proportioning,  mixing,  and  placing  concrete 

Type  of  mixer  to  be  used 

Requirements  for  placing  reinforcing  steel 

Methods  of  bending  steel 

Work  done  in  cold  weather 

Form  construction 

Protection  of  concrete,  both  in  cold  and  warm 

weather 

Removal  of  forms 

Patching  or  repairing  imperfect  concrete 
Provision  for  expansion  joints 

114 


Inspection 

Status  of  various  men  on  the  work  as  between 

representatives    of    the    engineer,    contractor, 

owner,  etc. 

It  should  be  remembered  that  many  large  pieces 
of  work  often  involve  changes  of  one  kind  or  anoth- 
er in  the  original  plans.  There  should  be  a  clause  in 
the  specifications  that  will  state  how  such  changes 
are  to  be  handled  by  the  contractor,  particularly 
with  regard  to  additional  or  decreased  compensa- 
tion. 

Often  it  has  been  the  practice  to  arrange  for  the 
arbitration  of  disputes  in  a  way  that  was  not  always 
equitable  to  either  or  any  of  the  parties  interested — 
that  is,  the  arbitration  board  provided  for  in  the 
specifications  frequently  included  at  least  one  mem- 
ber likely  to  be  partial  to  one  or  the  other  of  the 
parties  most  concerned. 

From  the  very  nature  of  concrete  construction, 
whether  plain  or  reinforced,  it  is  difficult  to  make 
alterations  in  the  work  after  it  has  progressed  be- 
yond a  certain  point.  Therefore  it  is  important 
that  provisions  be  made  for  continuous  inspection 
as  the  work  advances,  so  that  before  any  consider- 
able amount  of  it  at  variance  with  specifications 
can  be  finished  it  will  be  possible  to  correct  faults. 

Basic  Principles  in  all  Specifications 

As  nearly  every  piece  of  work  has  some  features 
peculiar  to  itself,  specifications  vary  in  accordance 
with  the  particular  job  for  which  written.  How- 
ever, certain  basic  principles  of  concrete  work  are  a 
feature  of  every  job.  Therefore  certain  portions  of 
every  specification  are  alike  for  all  jobs.  The  ex- 
tensions of,  or  additions  to,  a  specification  may  be 
almost  without  limit,  yet  should  not  be  made  with- 
out some  definite  purpose  in  view. 

Nearly  all  specifications  that  form  the  basis  of 
bids  for  certain  pieces  of  work  are  accompanied  by 
explanatory  notes,  consisting  of  instructions  and  in- 
formation for  bidders.  These  items  usually  pre- 


scribe  the  method  of  making  a  bid  and  how  it 
should  be  forwarded  when  ready  for  delivery  to  the 
person  or  persons  interested.  If  the  bid  is  accepted, 
the  next  step  is  the  signing  of  a  proper  contract 
which  in  its  essentials  states  when  the  contractor 
will  commence  the  work  and  the  time  he  will  be  al- 
lowed for  its  completion.  All  specifications  for 
work  likely  to  be  subject  to  various  delays  beyond 
reasonable  control,  should  contain  a  clause  outli- 
ning the  procedure  necessary  to  obtain  extension  of 
time  on  a  contract. 

On  any  job  the  first  work  usually  involves  more 
or  less  excavation  or  other  preparatory  work.  On 
large  jobs,  contracts  are  usually  let  for  various 
parts  of  the  work  so  the  concrete  contractor  may 
have  nothing  to  do  with  excavation  or  other  pre- 
liminaries. If  so,  the  contract  should  so  state. 

The  first  paragraph  of  a  specification  for  con- 
crete work  involves  the  cement  to  be  used.  As  a 
rule,  most  specifications  are  too  wordy  in  laying 
down  the  requirements  for  the  Portland  cement  to 
be  used  on  the  job — that  is,  they  go  into  such  de- 
tails as  stating  the  specific  gravity,  fineness,  time  of 
setting,  tensile  strength,  chemical  content,  etc. 
These  requirements  can  be  met  by  briefly  stating 
that  the  Portland  cement  used  shall  meet  the  re- 
quirements of  the  latest  Specifications  and  Tests 
for  Portland  Cement  of  the  American  Society  for 
Testing  Materials.  If  this  is  done,  any  of  the  well- 
known  brands  of  Portland  cement,  the  manufac- 
turers of  which  have  subscribed  to  these  specifica- 
tions, may  be  relied  upon  to  meet  the  demands  of 
any  concrete  construction. 

Another  objection  to  specifying  in  detail  the 
qualities  that  the  cement  shall  possess,  is  that  very 
few  persons,  other  than  those  whose  experience  in 
sampling  and  testing  cement  has  been  acquired  by 
thorough  laboratory  work,  are  competent  to  under- 
take cement  testing.  This  fact  has  often  been  re- 
sponsible for  high  grade  cement  being  rejected  on 
the  job.  If  for  any  reason  it  is  desirable  to  test 
cement,  the  work  should  be  intrusted  to  a  well- 

11G 


known,  well  equipped  testing  laboratory  which  spe- 
cializes in  such  work. 

Aggregates 

The  second  item  of  the  specification  usually  cov- 
ers the  subject  of  aggregates.  These  will  consist  of 
sand  and  pebbles  or  of  sand  and  some  kind  of 
crushed  stone,  among  which  may  be  slag  or  other 
materials  of  rock  origin.  If  fine  aggregate  such  as 
stone  screenings  is  to  be  used  in  place  of  sand,  or  if 
cinders  are  to  be  used  in  place  of  other  coarse  ag- 
gregate, the  specifications  should  detail  very  care- 
fully the  quality  of  such  materials  and  should  give 
field  methods  of  determining  their  quality.  Actual 
tests  on  aggregates,  like  tests  for  cement,  should 
be  made  in  some  laboratory  properly  equipped  for 
such  work. 

The  specifications  for  sand,  usually  referred  to  as 
fine  aggregate,  are  becoming  more  and  more  rigid, 
and  rightly  so,  since  it  has  been  proved  that  the  qual- 
ity of  the  sand  affects  the  quality  of  the  resulting  con- 
crete in  a  far  greater  degree  than  was  once  realized. 

Proportioning  Mixtures 

The  next  item  of  specification  should  take  up 
the  subject  of  proportioning  mixtures.  It  should 
go  explicitly  into  the  manner  in  which  the  several 
ingredients  are  to  be  measured  and  mixed,  so  that 
by  no  chance  can  the  specification  be  interpreted  to 
mean  that  a  1:2 'A  mixture  and  a  1 :6  mixture  are 
identical.  Methods  of  measuring  materials  should 
be  definitely  stated,  as  should  the  methods  of  mix- 
ing them. 

Type  of  Mixer 

Engineers  are  in  accord  on  the  point  that  only 
a  batch  mixer  should  be  used.  Specifications  should 
be  specific  in  stating  how  and  in  what  type  of  ma- 
chine materials  are  to  be  mixed.  The  time  of  mix- 
ing, or  its  equivalent  in  number  of  revolutions  for 
particular  make  of  machine,  should  be  carefully 
specified  and  rigidly  enforced. 

117 


Miscellaneous  Paragraphs 

Definite  amount  of  water  should  be  used  for 
each  successive  batch  so  long  as  materials  are  con- 
stant in  physical  properties  and  moisture  content. 

The  importance  of  the  correct  amount  of  mixing 
water  is  another  thing  which  has  but  recently  been 
thoroughly  appreciated.  A  clause  should  describe 
the  consistency  so  clearly  that  any  excess  of  water 
will  be  avoided. 

In  reinforced  concrete  work,  methods  of  placing 
reinforcing  steel  and  all  practice  involved  in  han- 
dling and  bending  it  where  necessary  to  form  it  to 
shapes  shown  on  the  plans,  should  be  clearly  stated 
in  the  specifications. 

On  many  jobs  it  is  necessary  to  devote  consider- 
able space  in  the  specifications  to  detailing  methods 
of  making  and  erecting  forms.  A  great  deal  of  con- 
crete work  has  failed  to  attain  the  strength  that 
might  have  been  expected  had  proper  attention 
been  given  to  form  construction  and  all  details  con- 
cerning erection,  use  and  removal  of  forms. 

Concrete  work  is  often  carried  on  during  low  tem- 
peratures. In  fact,  during  recent  years,  many  large 
contracting  firms  have  practically  specialized  on 
winter  work.  They  have  proved  conclusively  that 
good  concrete  work  can  be  done  in  cold  weather. 
But  in  anticipation  of  a  certain  contract  extending 
through  a  season  when  temperatures  will  be  near  or 
below  freezing,  specifications  should  clearly  define 
how  work  should  be  handled  under  such  conditions. 

Much  of  the  success  of  finished  concrete  work 
depends  upon  carefully  protecting  the  concrete  for  a 
certain  time  after  placed.  This  is  true  not  only  in 
cold  weather  but  also  in  extremely  warm  weather, 
especially  when  hot,  dry  winds  prevail.  This  latter 
fact  is  seldom  appreciated  and  the  practice  of  protect- 
ing concrete  in  warm  weather  is  almost  universally 
neglected  except  in  highway  pavement  construction. 

There  should  be  a  clause  in  every  specification 
covering  such  protection  as  it  is  desired  shall  be 
given  the  work  for  a  stipulated  period  under  cer- 

118 


tain  conditions.  For  certain  classes  of  work,  the 
time  when  forms  may  be  removed  should  be  defi- 
nitely specified. 

If  surface  finish  other  than  that  secured  by  plac- 
ing the  concrete  in  the  forms  is  desired  and  the 
same  contractor  is  to  attend  to  this  part  of  the 
work,  the  specifications  should  state  the  kind  of 
surface  finish  and  how  it  shall  be  secured. 

Sometimes  concrete  work  is  carried  on  under 
specifications  which  require  that  proprietary  prepa- 
rations such  as  waterproofing  mediums  or  floor 
hardeners  be  used  in  some  parts  of  the  work.  It 
is  not  right  to  place  entire  responsibility  on  the 
contractor  for  the  success  or  failure  of  the  work 
as  a  whole,  where  the  use  of  such  mediums  is  made 
a  part  of  the  specification.  In  these  cases  responsi- 
bility should  rest  upon  the  manufacturer  of  the  par- 
ticular preparation  and  he  should  supply  and  en- 
force the  specifications  governing,  thus  fixing  re- 
sponsibility for  success  or  failure. 

No  specification  should  be  longer  than  neces- 
sary to  cover  all  details  of  the  work,  yet  far  too 
many  specifications  fall  back  on  such  expressions 
as  "Shall  be  done  in  a  thoroughly  workmanlike 
manner"  or  "Shall  be  done  to  the  satisfaction  of  the 
engineer."  These  expressions  are  vague  in  defining 
quality  of  workmanship  and  are  sure  to  lead  to  al- 
most interminable  disputes  on  some  occasions. 

Considerable  trouble  on  every  concrete  job  of 
any  magnitude,  where  the  job  naturally  comes  un- 
der the  jurisdiction  of  local  building  ordinances,  is 
due  to  the  fact  that  plans  as  well  as  specifications 
frequently  are  at  variance  with  building  code  re- 
quirements. Such  trouble  can  always  be  avoided 
if  specifications  and  code  requirements  are  harmo- 
nized before  work  is  started. 


119 


120 


CHAPTER  8. 

ESTIMATING  COST  OF  CONCRETE 
CONSTRUCTION 

Cost  of  concrete  construction  depends  upon 
many  conditions.  Cost  of  labor  and  materials 
varies  widely  with  locality. 

In  making  estimates  upon  reinforced  concrete 
structures,  cost  may  be  closely  approximated  by 
taking  a  unit  price  per  cubic  yard  or  per  square  foot 
of  floor  surface  from  similar  work  recently  complet- 
ed under  nearly  or  practically  identical  conditions. 
Such  unit  price  may  be  used  for  approximating  the 
cost  of  a  proposed  structure  or  piece  of  work.  In 
order,  however,  that  such  an  estimate  will  approxi- 
mate probable  cost,  the  plans  and  specifications  as 
well  as  prevailing  prices  of  labor  and  material  must 
be  carefully  compared  with  those  of  the  structure  or 
job  from  which  the  unit  prices  are  derived.  Even 
then  it  must  be  realized  that  such  an  estimate  can 
only  be  an  approximation.  It  may,  however,  be  a 
very  close  one  if  the  contractor  has  had  consider- 
able experience  and  throughout  his  experience  has 
made  it  a  practice  to  carefully  compile  and  analyze 
cost  data  for  the  purpose  of  enabling  close  compari- 
sons. Cost  figures,  based  on  one's  own  experience, 
are  much  more  valuable  than  those  derived  from 
the  experiences  of  others,  as  the  latter  relate  to  un- 
known conditions  of  working,  while  the  figures 
which  the  individual  compiles  from  his  own  experi- 
ence relate  to  his  way  of  working  and  the  condi- 
tions which  he  has  met  and  with  which  he  is  there- 
fore most  familiar. 

Estimating  the  cost  of  concrete  construction 
is  in  many  respects  different  from  estimating  cost 
of  other  classes  of  work.  Naturally,  experience  in 
handling  a  particular  kind  of  job  qualifies  one  to 
estimate  more  closely  on  that  kind  of  work  than  on 
another  kind  with  which  one  has  had  little  or  no 
experience.  Frequently  the  inexperienced  contractor 

121 


has  found  out  that  the  knowledge  which  he  thought 
he  had  acquired  under  the  direction  or  guidance  of 
someone  else,  has  not  been  so  substantial  as  he 
believed,  in  that  he  lacked  the  inside  viewpoint  and, 
therefore,  was  unable  to  make  careful  analysis  of 
all  factors  affecting  cost. 

Items  Entering  into  Cost 

The  following  items  enter  into  most  work  and 
are  therefore  subject  to  detailed  consideration  be- 
fore the  preliminary  cost  of  a  piece  of  work  can  be 
considered  as  complete: 

Interest 

Overhead  expense 

Bonds 

Insurance 

Employer's  liability 

Public  liability 

Fire  insurance 

Special  risks 

Freight  on  outfit  to  and  from  work 

Moving  in  and  out 

Land  damages 

Camp  and  other  buildings 

Preliminary  work 

Cost  of  materials  plus  freight 

Hauling  materials 

Supervision 

Labor 

Loss  due  to  camp  operation 

Transportation  of  labor 

Tools 

Plant  rental 

Running  repairs 

General  repairs 

Specials 

Machinery 

Fuel  and  power 

Weather 

The  subject  of  interest  includes  proper  return  on 
the  actual  investment  in  equipment,  as  well  as 
money  that  must  be  paid  to  any  source  from  which 

122 


financing  for  a  job  must  be  drawn.  Certain  jobs 
can  be  financed  with  a  sum  not  exceeding  10  per 
cent  of  their  total  cost,  providing  the  contractor 
succeeds  in  making  suitable  arrangements  for  pay- 
ment on  account,  as  the  work  progresses.  Finan- 
cial standing  and  credit  rating  of  a  contractor  regu- 
late his  activities,  and  limitation  of  these  frequently 
causes  failure. 

Overhead 

Overhead  expense  is  made  up  of  a  number  of 
items  and  should  include  salary  allowance  for  mem- 
bers of  the  organization,  traveling  expenses  and 
similar  incidentals.  Under  overhead  would  also  come 
the  maintenance  of  an  equipment  storage  yard. 

Bonds  are  necessary  to  safeguard  the  commun- 
ity or  individual  owner  with  respect  to  faithful  per- 
formance of  the  work  in  accordance  with  the  speci- 
fication and  contract. 

Insurance 

Insurance  that  must  be  provided  is  of  various 
kinds  and  includes  protection  from  fire  loss  on  any 
combustible  materials,  safeguards  against  damage 
to  nearby  buildings  or  structures,  protection 
against  damage  claims  due  to  bodily  injuries  of  em- 
ployes and  any  other  special  risks  against  which 
the  contractor  may  be  protected  by  underwriting. 

Many  contractors  underestimate  the  amount  of 
freight  or  other  transportation  charges  involved  in 
moving  their  outfits  from  one  job  to  another. 

Cost  and  Quantity  of  Materials  Very  Important 

In  making  up  an  exact  estimate,  the  cost  of  the 
quantity  of  materials  required  can  be  accurately 
determined  by  using  the  figures  corresponding  to 
current  market  prices.  The  materials  used  in  con- 
crete construction  may  represent  anywhere  from  20 
to  70  per  cent  of  the  total  cost  of  the  work.  It 
can  readily  be  seen  that  in  so  large  an  item,  errors 
in  estimating  may  affect  profit  considerably.  The 
contractor  must  also  know  that  the  materials  de- 
livered to  him  are  up  to  quality  and  quantity  re- 

123 


quired  so  that  he  will  not  be  called  upon  to  remove 
or  demolish  a  portion  of  completed  work  or  secure 
additional  materials  beyond  those  delivered  in  in- 
sufficient supply. 

In  the  case  of  practically  all  other  building  ma- 
terials, finished  products  of  known  quality  are  sup- 
plied to  the  contractor  and  he  is  simply  a  builder; 
but  in  concrete  work  he  is  a  manufacturer  also,  and 
must  be  competent  to  correctly  judge  the  quality 
and  suitability  of  materials  entering  into  his  work. 

Labor  costs  can  be  estimated  accurately  only 
when  experience  has  proved  the  volume  of  work 
which  certain  kinds  of  workmen  or  laborers  may  be 
depended  upon  to  perform  in  a  given  time  or  under 
given  conditions.  Labor  costs  in  erecting  forms  are 
particularly  difficult  to  determine,  especially  where 
reinforced  concrete  construction  is  new  to  a  locality 
and  the  only  carpenters  obtainable  have  had  little 
or  no  experience  with  such  class  of  work. 

Speed  of  construction  influences  cost  and  in  turn 
is  influenced  largely  by  the  availability  of  space  and 
labor.  Frequently  throughout  a  job  a  contractor 
is  confronted  by  a  shortage  of  labor  or  unsatisfac- 
tory labor.  Competition  of  nearby  work  may  make 
it  difficult  for  a  contractor  to  maintain  or  retain  an 
efficient  organization. 

The  uncertainties  of  transportation  and  its  cost 
affect  the  cost  of  work  within  a  wide  range.  It 
must,  if  possible,  be  arranged  that  there  shall  be  an 
uninterrupted  supply  of  materials  in  order  that  the 
work  may  progress  without  costly  stoppages. 

Weather  Conditions 

Weather  conditions  play  an  important  part  on 
the  cost  of  work.  It  is  not  possible  to  foretell  when 
storms  or  unfavorable  weather  may  interrupt  the 
work,  except  that  experience  shows  that  more  de- 
pendable weather  prevails  at  certain  seasons  of  the 
year  than  during  other  times.  Late  fall  and  early 
spring  are  marked  by  unsettled  weather,  and  if  the 
work  must  begin  in  or  extend  into  either  of  these 
seasons,  calculations  must  be  made  on  the  inter- 

124 


ruptions  that  will  result  and  the  probable  influence 
in  cost  that  they  will  have  on  the  work. 

A  comparison  of  different  classes  of  work  will 
show  which  factors  most  influence  cost  as  among 
various  classes.  In  reinforced  concrete  construc- 
tion, for  example,  cost  of  materials  is  secondary  to 
that  of  labor,  while  in  plain  mass  concrete  construc- 
tion there  is  a  larger  cost  for  materials  than  for 
labor.  Some  classes  of  work  call  for  complicated 
and  therefore  expensive  form  construction.  On 
other  jobs  forms  represent  but  a  relatively  small 
portion  of  the  total  cost. 

Relation  of  Speed  to  Cost 

Speed  of  the  work  is  a  factor  in  estimating  cost. 
The  work  may  be  carried  on  too  rapidly  at  certain 
points,  thus  causing  congestion  of  labor  and  ma- 
terials. For  the  same  reason  cost  will  be  affected 
favorably  or  unfavorably  by  a  well  or  poorly  bal- 
anced construction  gang.  The  mixer  and  associ- 
ated equipment  may  be  too  small  or  too  large  for 
the  number  of  men  working  or  there  may  be  too 
few  or  too  many  men  for  the  equipment. 

Often  contractors  must  accept  notes,  bonds  or 
other  commercial  paper  instead  of  cash  in  payment 
for  their  work.  The  market  value  of  such  paper 
should  be  definitely  determined.  When  possible  to 
do  so,  arrangement  should  be  made  to  dispose  of  se- 
curities of  this  kind  at  a  definite  price  before  closing 
the  contract.  Only  by  knowing  what  such  securi- 
ties will  bring  in  cash  can  the  contractor  safeguard 
himself  in  estimating.  For  example,  if  he  is  given 
negotiable  securities  having  a  face  value  of  $10,000, 
which  will  bring  only  $9,000  cash,  his  estimate 
must  include  an  amount  sufficient  to  cover  such  dif- 
ference between  face  and  market  value  of  securi- 
ties accepted  as  cash. 

Cement  requirements  can  be  estimated  accurate- 
ly. It  is,  therefore,  not  necessary  to  increase  the 
quantity  estimated  other  than  to  add  a  small  sum  to 
actual  cost  per  barrel  to  cover  sack  losses.  The 
percentage  of  sacks  lost  is  largely  dependent  upon 

125 


the  care  received  while  in  the  hands  of  the  user. 
On  many  large  jobs  it  is  possible  to  adapt  bulk  ce- 
ment to  the  work  and  avoid  the  temporary  invest- 
ment and  the  certain  loss  of  some  of  this  investment 
when  cement  is  used  in  sacks.  It  is  always  best  to 
have  one  or  more  men,  as  necessary,  made  respon- 
sible for  the  careful  handling  and  bundling  of  sacks. 
Aggregates  are  sometimes  sold  by  weight  and 
sometimes  by  the  cubic  yard,  or  a  unit  weight  is 
adopted  and  deliveries  in  cubic  yards  are  converted 
into  equivalent  weights.  If  aggregates  or  cement 
must  be  transported  and  rehandled  from  trucks  to 
cars  and  cars  to  trucks,  where  there  is  likely  to  be 
loss,  there  is  also  the  cost  of  this  transportation  and 
rehandling.  There  is  also  some  wastage  of  materials, 
particularly  aggregates  at  the  site  of  the  work.  It  is, 
therefore,  safe  to  estimate  10  per  cent  over  actual 
figured  aggregate  requirements  to  cover  such  loss. 

Cost  of  Water  Should  Not  Be  Overlooked 

The  probable  cost  of  water  is  often  overlooked. 
Frequently  there  is  no  difficulty  in  arranging  for  a 
sufficient  supply.  Within  city  limits,  for  example, 
the  necessary  arrangements  can  be  made  with  the 
city  water  department  for  hydrant  or  similar  con- 
nection. The  quantity  of  water  required  may  safely 
be  figured  at  from  40  to  50  gallons  per  cubic  yard 
for  concrete  only.  In  addition  to  that  there  is  the 
water  required  for  operating  mixers,  engines  and 
other  equipment,  for  wetting  down  forms  and 
sprinkling  concrete  while  hardening  and  for  inci- 
dental waste  that  may  bring  the  estimated  require- 
ments up  to  100  gallons  per  cubic  yard  of  concrete 
in  place.  The  problem  of  water  supply  is  often  a 
troublesome  one  on  highway  construction.  Fre- 
quently the  supply  must  be  hauled  in  tank  wagons 
or  piped  for  long  distances,  and  before  estimating 
cost  of  water,  the  situation  to  be  met  must  be  care- 
fully analyzed.  Hauling  charges  involve  loading 
and  unloading  of  materials,  including  working  as 
well  as  waiting  time  of  team  and  driver  or  motor 
truck  and  actual  time  of  truck  in  travel. 

126 


CHAPTER  9. 

NOTES  ON  CONCRETE  CULVERT 
AND  BRIDGE  CONSTRUCTION 

Culverts 

The  simplest  form  of  concrete  culvert  is  that 
made  of  precast  pipe.  It  is  adapted  to  all  sizes  of 
opening  from  12  inches  upward  to  the  largest  size 
of  pipe  made,  providing  the  largest  size  will  other- 
wise suit  the  situation.  Good  practice  limits  the  mini- 
mum size  of  waterway  openings  to  12  inches  because 
smaller  sizes  easily  become  choked  with  rubbish. 

The  box  culvert  is  the  most  generally  used  of  all 
concrete  culverts  because  for  the  head-room  the 
greatest  area  of  waterway  can  be  secured,  and  very 
simple  forms  are  required.  As  the  name  implies,  it 
is  merely  a  long  box  with  concrete  top,  sides  and 
bottom.  It  is  in  effect  a  small  concrete  bridge  with 
top  slab  acting  as  a  floor  to  support  the  loads  of 
traffic.  The  slab  must  be  reinforced  with  steel  rods 
or  heavy  mesh  fabric.  In  building  box  culverts,  a 
concrete  floor  should  be  laid  in  the  bottom  of  the 
culvert.  This  is  sometimes  omitted  and  the  sides 
extended  down  a  short  distance  into  the  stream 
bed.  It  is  always  best  to  put  the  floor  in  to  prevent 
damage  from  undermining. 

The  arch  culvert  is  different  from  the  box  cul- 
vert in  that  the  top  is  in  the  form  of  an  arch  in- 
stead of  a  flat  slab.  There  is  no  advantage  in  the 
arch  culvert  for  small  spans.  It  requires  little  or 
no  reinforcing  because  the  concrete  takes  all  of  the 
load  in  compression.  Form  work  for  arch  culverts 
is  more  costly  than  for  box  culverts. 

The  area  of  waterway  for  culverts  is  shown  in 
the  following  table.  These  figures  are  given  merely 
as  a  guide  from  which  an  estimate  can  be  made  of 
the  approximate  size  of  opening  required.  The  area 
of  the  waterway  opening  depends  upon  the  water- 
shed to  be  drained  and  the  amount  of  rainfall  which 
must  be  taken  care  of  from  this  area. 

127 


Table  No.  13 

SIZE  OF  WATERWAY  REQUIRED  FOR 

VARIOUS  AREAS  TO  BE  DRAINED 

(From  Bureau  of  Public  Roads) 


Area  Drained 

Area  of  Waterway  Needed  (in 

Sq.  Ft.) 

Steep  Slopes 

Rolling  Country 

Flat  Country 

Acres 

10 

5.6 

1.9 

1.1 

20 

9.4 

3.1 

1.9 

30 

12.8 

4.3 

2  6 

40 

15.9 

5.3 

3.2 

50 

18.8 

6.3 

3  8 

60 

21.6 

7.2 

4.3 

80 

27 

8.9 

5.4 

100 

32 

10.6 

6.3 

125 

37 

12.5 

7.5 

150 

43 

14 

8  6 

200 

53 

18 

10.6 

300 

72 

24 

15 

400 

89 

30 

20 

Square  Miles 

1 

127 

42 

25 

2 

214 

71 

43 

3 

290 

97 

58 

4 

359 

120 

72 

5 

425 

141 

85 

7 

548 

183 

109 

10 

716 

239 

143 

15 

970 

323 

194 

20 

1204 

401 

241 

30 

1630 

543 

326 

50 

2390 

797 

478 

75 

3240 

1080 

648 

100 

4020 

1340 

805 

In  the  installation  of  concrete  pipe  culverts,  the 
pipe  is  laid  in  a  carefully  prepared  trench,  curved 
at  the  bottom  to  fully  support  the  pipe.  Back-fill 
and  road  cushions  must  be  carefully  placed  and 
compacted  in  layers  so  that  the  concentrated  loads 
of  vehicles  will  be  distributed  over  a  large  area  and 
not  come  directly  over  a  small  portion  of  the  pipe. 

For  small  box  and  arch  culverts  in  stable  soil, 
the  side  walls  usually  constitute  sufficient  founda- 
tion bearing.  In  soft  or  doubtful  soil  and  for  large 
sized  culverts,  spread  footings  should  be  placed  un- 
der side  walls.  Often  the  culvert  floor  is  considered 
as  the  foundation  footing.  In  such  a  case  the  floor, 
which  acts  as  a  beam,  should  be  reinforced  in  the 
same  manner  as  the  culvert  top,  except  that  the 
steel  is  placed  in  the  upper  part  of  the  slab. 

All  flat  slab  or  box  culverts,  regardless  of  size, 
should  be  reinforced.  As  a  rule,  such  reinforcing  is 

128 


placed  with  its  center  point  1%  inches  from  the  bot- 
tom of  the  slab,  except  in  the  case  of  the  floor  slab, 
when  it  would  be  1%  inches  from  the  top.  Rein-; 
forcing  should  be  bent  down  and  up  into  side  walls 
a  suitable  distance.  Care  should  be  taken  to  see 
that  it  is  held  the  required  distance  from  the  forms 
by  metal  spacers  or  other  devices  so  that  it  will  be 
in  correct  position  in  the  concrete  when  the  work  is 
finished. 

Wing  Walls 

Wing  walls  are  provided  on  bridges  and  culverts 
to  retain  the  road  fill  and  prevent  stream  erosion. 
Such  walls,  used  in  connection  with  concrete  pipe 
culverts,  are  generally  built  straight  and  parallel 
with  the  road.  The  top  thickness  of  unreinforced 
end  walls  for  pipe  culverts  should  be  not  less  than 
12  inches  and  as  a  general  rule  the  thickness  at  the 
bottom  should  be  0.4  the  height  of  the  wall.  The 
foundation  footing  under  the  wall  is  usually  made 
6  to  12  inches  wider  than  the  wall. 

End  and  wing  walls  for  box  or  arch  culverts  are 
either  straight  and  parallel  with  the  road  or  flared 
at  an  angle  to  it.  The  flare  type  is  more  effective 
in  confining  the  road  fill.  Especially  should  it  be 
used  on  the  upstream  end  of  the  culvert.  End  and 
wing  walls  are  frequently  reinforced  in  the  interest 
of  economy  of  concrete. 

The  concrete  floor  built  in  the  bottom  of  con- 
crete culverts  assists  in  preventing  choking  of  the 
waterway  and  undermining  of  the  foundation.  A 
vertical  cut-off  wall  at  each  end  of  the  floor,  extend- 
ing down  2  feet,  is  added  protection  against  under- 
mining. For  very  small  culverts,  the  floor  is  made 
continuous  with  the  walls  and  thus  acts  practically 
as  a  foundation.  In  larger  culverts  the  floor  is  laid 
usually  as  a  6-inch  pavement  between  the  walls  in 
order  to  properly  distribute  concentrated  loads. 

Road  covering  over  all  culverts  should  be  2  feet 
for  dirt  or  macadam.  Owing  to  the  better  distribu- 
tion of  loads  by  concrete  pavement,  it  will  be  suffi- 
cient if  the  road  slab  proper  is  laid  directly  on  the 

129 


top  of  the  culvert.  This  allows  a  greater  clear 
height  to  the  waterway,  without  altering  the  grade 
of  the  road,  than  when  the  dirt  or  macadam  road 
cushion  must  be  provided. 

Since  the  upper  part  of  the  culvert  top  slab  is 
acting  in  compression,  it  should  not  be  made  part  of 
the  concrete  road.  The  additional  thickness  of  the 
road  slab  should  be  laid  upon  the  culvert  top.  In 
doing  this,  it  is  best  to  paint  the  top  of  the  culvert 
slab  with  something  that  will  prevent  bond  between 
it  and  the  road  slab.  The  road  section  over  the 
culvert  should  extend  some  distance  on  each  side  of 
the  culvert  and  be  reinforced.  In  this  way  no  joint 
is  formed  at  the  side  of  the  culvert  and  danger  of 
settling  of  the  road  slab  at  sides  is  avoided. 

Concrete  culverts  are  made  the  full  width  of  the 
road,  including  the  shoulders.  This  is  done  by  widen- 
ing the  road  slab  to  the  full  length  of  the  culvert. 

Bridges 

Most  of  the  foregoing  notes  on  concrete  culverts 
apply  to  concrete  bridges.  A  bridge  implies  a  larger 
structure,  although  there  is  no  line  drawn  to  defi- 
nitely state  where  the  structure  changes  from  the 
classification  of  culvert  to  that  of  bridge. 

The  type  of  highway  bridge  to  be  selected  for 
any  given  location  depends  uppn  length  of  span, 
waterway  opening  required,  foundation  conditions, 
etc.  The  flat  slab  bridge  is  probably  the  simplest 
form  and  is  specially  adapted  to  short  spans  and  to 
the  loads  of  ordinary  highway  traffic.  It  is  merely 
a  concrete  slab  of  proper  thickness,  suitably  rein- 
forced and  resting  on  abutments.  Reinforcement 
usually  consists  of  steel  rods  and  requires  little  or 
no  fabrication  before  placing.  Form  work  also  is 
simple.  Essentially  all  that  is  required  is  a  tem- 
porary wooden  floor  upon  which  the  concrete  may 
be  supported  until  it  has  hardened  sufficiently  to 
carry  its  own  weight  and  that  of  traffic. 

Where  loads  and  length  of  span  are  such  as  to 
require  a  heavier  floor  slab  than  common  in  the 
ordinary  type  of  flat  slab  bridge,  the  design  changes 

130 


to  a  combination  of  girder  and  slab  or  girder,  beam 
and  slab.  Girders  extend  parallel  to  the  road  be- 
tween abutments  and  support  the  floor  slab  which 
can  then  be  made  relatively  thinner.  As  the  entire 
structure  is  a  monolith,  concrete  beams  act  as  "L" 
or  "T"  beams  of  which  the  floor  slab  is  the  upper 
flange.  This  results  in  economy  by  reducing  the 
required  size  of  beams.  The  beams,  of  course,  are 
suitably  reinforced.  Sometimes  on  long  spans,  large 
concrete  girders  are  used  at  each  side  with  cross 
beams  between,  supporting  the  floor  slab.  Rein- 
forcement in  this  type  of  structure  is  more  compli- 
cated than  in  the  types  previously  described. 

In  order  to  simplify  the  problem  of  reinforcing 
and  of  form  construction,  steel  "I"  beams  are  some- 
times substituted  for  concrete  beams.  The  "I" 
beam  should  be  encased  in  concrete  to  prevent  cor- 
rosion. The  concrete  floor  slab  rests  on  the  "I" 
beams.  In  this  type  of  construction  it  is  conven- 
ient to  hang  the  forms  to  the  lower  flange  and  thus 
eliminate  the  necessity  of  post  supports  for  forms. 

Concrete  arches  are  suitable  for  locations  where 
good  foundation  and  sufficient  head-room  exist. 
Under  such  conditions  the  arch  is  economical. 
Form  work  is  more  difficult  and  extreme  care  is 
necessary  to  secure  an  unyielding  foundation  for 
the  abutments.  Both  plain  and  reinforced  concrete 
is  used  for  highway  arch  bridges.  In  many  cases 
the  arch  can  be  designed  so  that  it  will  not  need 
reinforcing.  In  other  cases  designing  it  for  rein- 
forcing will  result  in  desirable  economy  of  concrete. 

Functions  of  Bridge  Abutments 

Bridge  abutments  have  two  functions.  They 
help  to  support  the  bridge  superstructure  and  to 
retain  the  fill  of  the  approach.  They  may  be  either 
of  plain  or  reinforced  concrete.  If  reinforced,  they 
allow  considerable  reduction  in  the  abutment  thick- 
ness and  a  consequent  saving  in  concrete. 

Wing  walls  are  needed  for  all  highway  bridges, 
regardless  of  size.  They  prevent  undermining  and 
erosion  of  the  abutment  and  also  add  to  the  stabil- 

131 


ity  of  the  abutment,  as  well  as  help  to  retain  the  fill 
of  the  road  and  bridge  approaches. 

In  the  building  of  abutments,  retaining  walls  and 
wing  walls,  drainage  should  be  taken  care  of  by  de- 
positing against  the  back  of  the  wall,  a  layer  of 
broken  stone  for  the  full  height,  connecting  this  with 
weep  holes  or  pipe  extending  through  the  wall. 

Concrete  for  the  ring  of  arch  bridges  may  be 
placed  in  two  ways  unless  the  structure  is  so  small 
that  concreting  can  be  finished  in  one  day.  The  first 
method  is  to  concrete  a  section  of  sufficient  width 
so  that  the  ring  can  be  completed  from  abutment  to 
abutment  in  one  continuous  operation.  One  section 
is  completed  each  day  or  during  a  given  period,  un- 
til the  full  width  of  the  bridge  is  reached.  The  sec- 
ond method  is  to  deposit  the  concrete  in  transverse 
sections,  extending  the  full  width  of  the  bridge  in  a 
manner  similar  to  that  after  which  masonry  arches 
are  built.  In  this  method,  the  surface  of  the  con- 
crete at  the  end  of  each  day's  work  must  be  left  in 
a  plane  perpendicular  to  the  form  centering  at  that 
point.  In  the  larger  arches  built  by  the  latter 
method,  there  is  some  danger  that  the  placing  of 
concrete  at  the  haunches  will  cause  the  centering  to 
rise  at  the  crown,  thus  distorting  the  true  curve  of 
the  arch.  This  danger  is  slight  in  small  arches,  but 
can  be  guarded  against  by  placing  the  keystone  sec- 
tion and  the  haunch  at  the  same  time,  the  weight 
of  the  first  tending  to  hold  down  the  centering.  In 
placing  concrete  after  either  method,  it  should  be 
deposited  first  at  both  haunches  and  in  equal 
amounts  on  each  side  so  as  to  load  the  forms  equally. 

Foundation  Material  of  Utmost  Importance 

The  stability  of  arch  bridges  depends  in  a  great 
measure  on  unyielding  abutments  and  foundations. 
The  character  of  the  foundation  material  is  there- 
fore of  utmost  importance.  Rock,  hardpan,  and 
hard  and  compact  gravel,  are  suitable  arch  abut- 
ment foundations.  Piles  are  required  when  the  soil 
is  yielding.  Foundation  footings  must  be  carried 
down  sufficiently  to  prevent  underscouring  or  un- 

132 


dermining  by  the  current.  Where  necessary,  they 
should  be  protected  by  rip-rap.  For  very  large  mass 
work  it  is  permissible  to  use  field  stones  in  the  con- 
crete to  effect  a  saving  of  materials.  These  should 
not  be  thrown  in  the  forms  indiscriminately,  but  be 
distributed  carefully  by  hand  during  the  placing  of 
the  regular  concrete  mixture,  so  that  they  will  be 
evenly  scattered  throughout  the  mass. 

In  order  to  prevent  seepage  of  water  through 
the  joints  in  the  arch  ring,  the  ring  must  be  thor- 
oughly waterproofed.  While  well  made  concrete  in 
itself  is  sufficiently  waterproof  for  this  purpose,  nev- 
ertheless there  are  joints  at  the  end  of  each  day's 
work  which  might  allow  seepage  that  would  de- 
tract from  the  appearance  of  the  arch.  To  prevent 
this  the  back  of  the  arch  and  inner  faces  of  the  span- 
drel walls  are  given  a  Ys-mch  coating  of  coal  tar 
pitch.  To  dispose  of  surface  water,  broken  stone 
drains  are  provided  to  lead  it  away  from  the  abut- 
ment or  to  drain  pipes  extending  through  the 
haunch  of  the  arch  near  the  springing  line.  The 
road  fill  may  be  of  broken  stone,  cinders  or  earth. 
A  minimum  thickness  of  2-feet  of  fill,  well  com- 
pacted, should  be  provided  at  the  crown. 

If  a  permanent  hard  surfaced  road  is  to  be  in- 
stalled over  the  bridge,  it  is  good  policy  to  wait  for 
at  least  a  year  so  that  all  settlement  of  the  fill  may 
have  subsided. 

Carpenter   Work  on  Bridge 

Carpenter  work  required  on  average  bridge 
forms  can  easily  be  done  by  an  ordinary  carpenter. 
It  should  be  borne  in  mind  that  various  members  of 
bridges  are  of  considerable  size  and  weight,  there- 
fore, forms  should  be  strong  and  rigid  to  sustain  the 
heavy  loads  imposed  by  the  fresh  concrete.  In  or- 
der that  dimensions  and  shape  of  all  members, 
when  finished,  will  conform  exactly  with  the  design, 
every  precaution  should  be  taken  to  prevent  distor- 
tion of  forms.  Extra  care  expended  on  making  and 
erecting  them  will  be  repaid  by  the  better  appear- 
ance of  the  finished  work.  Where  necessary,  plenty 

133 


of  posts,  well  braced,  should  be  used  to  support 
forms  and  prevent  them  from  sagging  with  the 
green  concrete. 

The  centering  for  an  arch  bridge  is  necessarily 
more  elaborate  than  for  a  simple  flat  bridge,  yet  the 
carpenter  work  is  well  within  the  abilities  of  the 
carpenter  of  average  skill.  Special  attention  must 
be  given  to  the  wedges  which  provide  for  easy  and 
gradual  lowering  of  the  centering.  Only  good 
quality  lumber  should  be  used  for  arch  centering, 
particularly  for  main  supporting  timbers  and  brac- 
ing. Unless  under  exceptional  circumstances, 
forms  should  never  be  lowered  from  beneath  arch 
rings  or  floor  systems  in  less  than  one  month  from 
the  placing  of  the  last  concrete.  If  the  work  has 
been  done  under  unfavorable  conditions  of  temper- 
ature, a  longer  time  even  may  be  necessary. 

Table  No.  14 

TABLE  SHOWING  QUANTITIES  OF   MATERIALS  REQUIRED   IN 
CONCRETE  BRIDGES  OF  SPANS  8  FEET  TO  24  FEET,  ROAD- 
WAY 20  FEET,  AS  SHOWN  BY  THE  STANDARD  PLANS  OF 
THE  WISCONSIN  HIGHWAY  COMMISSION 


Size 

Excavation 

Concrete 

Reinf. 
Steel 
Pounds 

8-foot  span,  20-foot  roadway 
10  -foot  span,  20  -foot  roadway 
12-foot  span,  20-foot  roadway 
14-foot  span,  20-foot  roadway 
16-foot  span,  20-foot  roadway 
18-foot  span,  20-foot  roadway 
20-foot  span,  20-foot  roadway 
2  2  -foot  span,  20  -foot  roadway 
24-foot  span,  20-foot  roadway 

25  cu.  yd. 
30  cu.  yd.    "  - 
35  cu.  yd. 
35  cu.  yd. 
40  cu.  yd. 
40  cu.  yd. 
45  cu.  yd. 
50  cu.  yd. 
50  cu.  yd. 

42.3  cu.  yd. 
49.8  cu.  yd. 
56.5  cu.  yd. 
60.3  cu.  yd. 
68.6  cu.  yd. 
72.8  cu.  yd. 
81.4  cu.  yd. 
91.9  cu.  yd. 
98.2  cu.  yd. 

1910 
2210 
2720 
3100 
3540 
3950 
4540 
5320 
6360 

134 


CHAPTER  10. 

CONVENIENT  ESTIMATING  TABLES  AND 
EXAMPLES  OF  USE 

For  convenience,  concrete  is  usually  mixed  in 
batches,  each  requiring  one  or  more  sacks  of  ce- 
ment. The  following  table  shows  the  cubic  feet  of 
sand  and  pebbles  (or  crushed  stone)  to  be  mixed 
with  one  sack  of  cement  to  secure  mixtures  of  the 
different  proportions  indicated  in  the  first  column. 
The  last  column  gives  the  resulting  volume  in  cubic 
feet  of  compacted  mortar  or  concrete. 


Table  No.  15 


Mixtures 

Materials 

Concrete  cu.  Ft 

Cement 

Sand 

Pebbles 
or 
Stone 

cement 
in 
Sacks 

Sand 
Cu.Ft. 

Pebbles 
or  Stone 
Cu.  Ft. 

Mortar 

Con- 
crete 

1 

1.5 
2 
3 
1.5 
2 
2 
2.5 
2.5 
3 

3 
3 

4 
4 
5 
5 

1.5 

2 
3 
1.5 
2 
2 
2.5 
2.5 
3 

3 
3 

4 
4 
5 
5 

1.75 
2.1 
2.8 

3.5 
3.9 
4.5 
4.8 
5.4 
5.8 

The  following  table  gives  the  number  of  sacks 
of  cement  and  cubic  feet  of  sand  and  pebbles  (or 
stone)  required  to  make  one  cubic  yard  (twenty- 
seven  cubic  feet)  of  compacted  concrete  propor- 
tioned as  indicated  in  first  column. 


135 


Table  No.  16 


Mixtures 

Quantities  of  Materials 

Pebbles 

Cement 

Sand 

Stone  or 

Cement 

Sand 

or  Stone 

in  Sacks 

Cu.  Ft. 

Pebbles 

Cu.Ft. 

1.5 

15.5 

23.2 

2 

12.8 

25.6 

3 

9.6 

28.8 

1.5 

3 

7.6 

11.4 

22.8 

2 

3 

7 

14 

21 

2 

4 

6 

12 

24 

2.5 

4 

5.6 

14 

22.4 

2.5 

5 

5 

12.5 

25 

3 

5 

4.6 

13.8 

23 

3 

6 

4.2 

12.6 

25.2 

Example  No.  I 

How  much  cement,  sand,  and  pebbles  will  be 
required  to  build  a  feeding  floor  30  feet  by  24  feet, 
5  inches  thick? 

Multiplying  the  area  (30  by  24)  by  the  thickness 
in  feet  gives  300  cubic  feet,  and  dividing  this  by  27 
gives  11-1/9  cubic  yards  as  the  required  volume  of 
concrete.  A  one-course  floor  should  be  of  1 :2 :3 
mixture,  see  Table  No.  1  page  28.  Table  No.  16 
shows  that  each  cubic  yard  of  this  mixture  required 
7  sacks  of  cement,  14  cubic  feet  of  sand,  and  21  cubic 
feet  of  gravel  or  stone.  Multiplying  these  quantities 
by  the  number  of  cubic  yards  required  (11-1/9  gives 
the  quantities  of  material  required,  eliminating 
fractions)  as  78  sacks  of  cement,  156  cubic  feet  of 
sand,  and  233  cubic  feet  of  pebbles  or  stone.  As 
there  are  4  sacks  of  cement  in  a  barrel,  and  27  cubic 
feet  of  sand  or  pebbles  in  a  cubic  yard,  we  shall 
need  a  little  less  than  20  barrels  of  cement,  6  cubic 
yards  of  sand,  and  9  cubic  yards  of  pebbles  or  stone. 

Example  No.  II 

How  many  fence  posts  3  by  3  inches  at  the  top, 
5  by  5  inches  at  the  bottom,  and  7  feet  long  can  be 
made  from  one  sack  of  cement?  How  much  sand 
and  pebbles  will  be  needed? 

136 


Fence  posts  should  be  of  a  1:2:3  mixture. 
Table  No.  15  page  135  shows  the  volume  of  a  one- 
sack  batch  of  this  mixture  to  be  3-9/10  cubic  feet. 
The  volume  of  one  concrete  post,  found  by  multi- 
plying the  length  by  the  average  width  and  breadth 
in  feet  (7  by  %  by  %)  is  7/9  cubic  feet.  By  divid- 
ing 3-9/10  by  7/9  we  find  that  five  posts  can  be 
made  from  1  sack  of  cement  when  mixed  with  2 
cubic  feet  of  sand  and  3  cubic  feet  of  pebbles. 

Example  III 

What  quantities  of  cement,  sand  and  pebbles  are 
necessary  to  make  100  unfaced  concrete  blocks, 
each  8  by  8  by  16  inches? 

The  product  of  height,  width  and  thickness,  all 
in  feet  (%  by  %  by  4/3)  gives  16/27  cubic  feet  as 
the  contents  of  a  solid  block.  As  the  air  space  is 
usually  estimated  as  33%  per  cent,  the  volume  of 
concrete  in  one  hollow  block  will  be  %  of  16/27  or 
32/81  cubic  foot;  in  100  blocks  the  volume  of  con- 
crete will  bej5200==39.5— 1. 46  cubic  yards,  or  66% 

81 

cubic  feet  which  being  divided  by  27  gives  a  little 
less  than  \y2  cubic  yards.  Unfaced  concrete  block 
should  be  1 :2y2  :4  mixture,  see  Table  No.  1,  page  28. 
Table  No.  16  shows  that  each  cubic  yard  of  this 
mixture  requires  5-6/10  sacks  of  cement,  14  cubic 
feet  of  sand,  and  22-4/10  cubic  feet  of  pebbles. 
Multiplying  these  quantities  by  the  number  of  cubic 
yards  required  (1J4)  gives  the  quantities  of  mater- 
ial required  as  8-2/5  sacks  of  cement,  21  cubic  feet 
of  sand,  and  33-3/5  cubic  feet  of  gravel. 

Example  IV 

How  many  6-foot  hog  troughs  12  inches  wide  and 
10  inches  high  can  be  made  from  1  barrel  of  cement? 

Use  a  1 :2 :3  mixture,  see  Table  No.  1  page  28. 
Table  No.  15  shows  the  volume  of  a  1-sack  batch  of 
this  mixture  to  be  3-9/10  cubic  feet.  As  there  are 
4  sacks  in  1  barrel,  a  barrel  of  cement  would  be 
sufficient  for  four  times  3-9/10,  or  15-6/10  cubic 
feet  of  concrete.  The  product  of  the  three  dimen- 
sions, all  in  feet,  gives  the  volume  of  one  trough  as 

137 


5  cubic  feet.  However,  approximately  30  per  cent 
of  this  volume  is  in  the  open  water  basin  or  inside 
of  the  tank,  leaving  3-5/10  cubic  feet  as  the  solid 
contents  of  concrete  in  one  trough.  Dividing 
15-6/10  by  3-5/10,  we  find  that  4  troughs  (and  a 
fraction  over)  can  be  made  from  1  barrel  of  cement 
when  mixed  with  8  cubic  feet  of  sand  and  12  cubic 
feet  of  pebbles. 

Table  No.  17 

NUMBER  OF  SQUARE  FEET  OF  WALL  SURFACE  COVERED 

PER   SACK   OF   CEMENT,   FOR   DIFFERENT   PROPORTIONS 

AND  VARYING  THICKNESS  OF  PLASTERING 


Materials 

Tc 

tal  Thickness  of  Plaster 

Pro- 

Vz-in. 

X  -in. 

1-in. 

1  i/4-in. 

iVz-in. 

portions 

of  Mix- 

Sacks 

Bush- 

ture 

Ce- 
ment 

Cu.  Ft. 

Sand 

els 
Hair* 

Sq.  Ft. 
Cover- 

Sq. Ft. 
Cover- 

Sq. Ft. 
Cover- 

Sq. Ft. 
Cover- 

Sq. Ft. 

Cover- 

ed 

ed 

ed 

ed 

ed 

1:1 

1 

1 

M 

33.0 

22.0 

16.5 

13.2 

11.0 

1:1% 

1 

1% 

% 

42.0 

28.0 

21.0 

16.0 

14.0 

1:2 

1 

2 

% 

50.4 

33.6 

25.2 

20.1 

16.8 

1:2% 

1 

2% 

v& 

59.4 

39.6 

29.7 

23.7 

19.8 

1:3 

1 

3 

y* 

67.8 

45.2 

33.9 

27.1 

21.6 

*Used  in  scratch  coat  only. 

Note: — These  figures  are  based  on  average  conditions  and  may  vary 
10  per  cent  either  way,  according  to  the  quality  of  the  sand  used.  No  al- 
lowance is  made  for  waste. 

Table  No.  18 

MATERIALS  REQUIRED  FOR  100  SQ,  FT.  OF  SURFACE 
FOR  VARYING  THICKNESS  OF  PLASTER 


Propor- 
tions 

Thick- 
ness 
(in.) 

1: 

1 

1: 

2 

1:2  % 

1:3 

C. 

(sacks) 

Sd. 
(cu.yd.) 

C. 

(sacks) 

Sd. 
(cu.yd.) 

C. 

(sacks) 

Sd. 
(cu.yd.) 

C. 

(sacks) 

Sd.(cu. 
yd.) 

1 

1V4 
1% 
IK 

2 

2.2 
3.0 
4.5 
6.0 
7.5 
9.0 
10.5 
12.0 

0.08 
0.11 
0.16 
0.22 
0.27 
0.33 
0.39 
0.45 

1.5 
2.0 
2.9 
3.9 
4.9 
5.9 
6.9 
7.9 

0.11 
0.15 
0.22 
0.29 
0.36 
0.43 
0.50 
0.58 

1.3 
1.7 
2.5 
3.3 
4.2 
5.1 
6.0 
6.9 

0.12 
0.16 
0.23 
0.31 
0.39 
0.47 
0.56 
0.64 

1.1 
1.5 
2.2 
3.0 
3.7 
4.5 
5.4 
6.2 

0.13 
0.17 
0.25 
0.33 
0.41 
0.50 
0.60 
0.69 

If  hydrated  lime  is  used  it  should  be  added  in  amounts  of  from  5  to 
10%  by  weight  of  the  cement. 

Hair  is  used  in  the  scratch  coat  only  in  amounts  of  %  bushel  to  1  sack 
of  cement. 

These  figures  may  vary  10%  in  either  direction  due  to  the  character  of 
the  sand. 

No  allowance  is  made  for  waste. 

138 


Table  No.  19 


QUANTITY  OF  CEMENT   REQUIRED  PER    CUBIC    FOOT    AND 
PER  CUBIC  YARD  OF  CONCRETE  FOR  VARIOUS 
MIXTURES  IN  TERMS  OF  SACKS  AND  BARRELS 


1  Cu.  Ft. 

Sacks  of 

1  Cu.  Yd. 

Bbl.  of 

Concrete 

Cement 

Concrete 

Cement 

1:1:1 

.5404 

:1:1 

3.375 

l:li/2:3 

.2808 

:1V2:3 

1.895 

1:2:4 

.2220 

:2:4 

1.498 

1:2  y2  :5 
1:3:6 

.1848 
.1570 

:2V2:5 
:3:6 

1.247 
1.060 

Table  No.  20 


MATERIALS  REQUIRED  FOR  100  SQ.  FT.  OF  SURFACE 
FOR  VARYING  THICKNESS  OF  COURSE 


Thickness 
Mix 

C. 

1  in. 

St. 

2  in. 
Sd. 

4  in. 

Sin. 

St. 

Sd. 

C. 

St. 

C. 

Sd. 

St. 

C. 

Sd. 

1:2 
1:1:1 

:2:32 
:2:4 
:2V2:4 
:2V2:5 
:3:6 

3.9 

4.2 
3.7 
2.6 

0.29 
0.15 
0.14 
0.14 

6.  is 

0.20 
0.24 

7.9 
8.3 
7.3 
5.1 

0.58 
0.31 
0.27 
0.28 

0.31 
0.41 
0.47 

9^4 
8.6 
7.4 
6.9 
6.2 
5.2 

0.'64 
0.55 
0.64 
0.57 
0.58 

i'.04 
0.95 
1.10 
1.02 
1.14 
1.16 

ii'.7 

10.8 
9.3 
8.6 

7.7 
6.5 

Q'.SO 

0.69 
0.80 
0.72 
0.73 

i!so 

1.19 
1.37 
1.27 
1.43 
1.45 

Table  No.  20 

MATERIALS  REQUIRED  FOR  100  SQ.  FT.  OF  SURFACE 
FOR     VARYING     THICKNESS     OF     COURSE 


6  in. 

7  in. 

8  in. 

9  in. 

Thickness 
Mix 

C. 

Sd. 

St. 

C. 

Sd. 

St. 

C. 

Sd. 

St. 

C. 

Sd. 

St. 

:1V2:3 

14.0 

0.78 

1.56 

16.4 

0.91 

1.82 

18.7 

1.04 

2.08 

21.1 

1.17 

2.34 

:2:3 

12.9 

0.95 

1.43 

15.0 

1.11 

1.67 

17.2 

1.27 

1.90 

19.3 

1.43 

2.14 

:2:4 

11.1 

0.82 

1    64 

12  9 

0,Qfi 

1    92 

14  8 

1    10 

2   19 

16  7 

1    23 

2  47 

:2V2:4 

10.3 

0.95 

1.53 

12.0 

1.11 

1.78 

13.8 

1.27 

2.03 

15.5 

1.43 

2.29 

:2V2:5 

9.2 

0.86 

1.72 

10.8 

1.00 

2.00 

12  3 

1    14 

2   2Q 

13.9 

1.29 

2.57 

:3:6 

7.9 

0.87 

1.74 

9.2 

1.02 

2.03 

10.5 

1.16 

2.32 

11.8 

1.31 

2.61 

Note: — Quantities  expressed  in  the  following  units: 

Cement sacks  Sand cubic    yard 

Pebbles  or  Broken  Stone cubic  yards 

139 


Table  No.  21 


MATERIALS  REQUIRED  FOR  100  SQ.  FT.  OF  SIDEWALKS  AND 
FLOORS  FOR  VARYING  THICKNESS  OF  COURSE 


Concrete  Base 


1:2:3 

1:2:4 

1:2  l/2  :4 

1:2V2:5 

Proportions 

Thickness 

C. 

Sd. 

St. 

C. 

Sd. 

St. 

C. 

Sd. 

St. 

C. 

Sd. 

St. 

2  i/2  in. 

5.4 

0.40 

0.60 

4.6 

0.34 

0.68 

4.3 

0.40 

0.63 

3.9 

0.36 

0.72 

3 

6.5 

0.48 

0.72 

5.6 

0.41 

0.82 

5.2 

0.48 

0.77 

4.6 

0.43 

0.86 

3% 

7.5 

0.56 

0.84 

6.5 

0.48 

0.96 

6.0 

0.56 

0.89 

5.4 

0.50 

1.00 

4 

8.6 

0.64 

0.95 

7.4 

0.55 

1.10 

6.9 

0.64 

1.02 

6.2 

0.57 

1.14 

4'/2 

9.7 

0.72 

1.07 

8.3 

0.62 

1.23 

7.7 

0.72 

1.14 

6.9 

0.64 

1.28 

5 

10.8 

0.80|1.19 

9.3 

0.69 

1.37 

8.6 

0.80 

1.27 

7.7 

0.71 

1.43 

5V2 

11.8 

0.88 

1.31 

10.2 

0.76 

1.50 

9.5 

0.87 

1.40 

8.5 

0.78 

1.57 

6 

12.9 

0.95 

1.43 

11.1 

0.82 

1.64 

10.3 

0.95 

1.53 

9.2 

0.86 

1.72 

Wearing  Course 


Thickness 
Inches 

I4 
2 

1:1 

1:1  Vz 

1:2 

C. 

Sd. 

C. 

Sd. 

C. 

Sd. 

3.0 
4.5 
6.0 
7.5 
9.0 
10.5 
12.0 

0.11 
0.16 
0.22 
0.27 
0.33 
0.39 
0.45 

2.4 
3.6 
4.8 
6.0 
7.2 
8.4 
9.6 

0.13 

0:19 

0.26 
0.33 
0.40 
0.46 
0.53 

2.0 
2.9 
3.9 
4.9 
5.9 
6.9 
7.9 

0.15 
0.22 
0.29 
0.36 
0.43 
0.50 
0.58 

Note: — Quantities  expressed  in  the  following  units: 

Cement sacks  Sand cubic  yards 

Pebbles  or  Broken  Stone cubic  yards 


140 


CHAPTER  11. 
FOUNDATIONS  AND  FOOTINGS 

Before  foundations  and  their  footings  are  built, 
it  is  presupposed  that  suitable  tests  by  borings  and 
test  loads  have  been  made  on  the  soil  at  the  build- 
ing site  to  determine  its  bearing  value.  In  order  to 
sustain  the  weight  of  the  structure  to  be  placed 
upon  it,  the  foundations  must  be  started  on  soil  of 
sufficient  bearing  capacity  to  sustain  the  proposed 
superimposed  load.  Frequently  to  avoid  excava- 
tion to  unnecessary  depth  the  proposed  load  is  dis- 
tributed over  a  greater  area  of  soil  by  starting  the 
foundation  proper  on  a  suitable  footing. 

When  the  excavation  required  for  the  building 
having  basement  extending  40  or  50  feet  below 
grade  passes  through  a  firm  stratum  into  softer  ma- 
terial or  where  any  settlement  at  all  would  be  con- 
siderable, the  foundations  usually  consist  of  wood 
or  concrete  piles  driven  close  together  or  of  con- 
crete piers  extending  to  a  lower  stratum  of  hard 
clay  or  to  bed-rock.  Where  piles  are  driven  close 
together  and  do  not  bear  on  bed-rock,  the  soil  is 
compacted  and  skin  friction  together  with  slight 
bearing  at  the  foot  of  the  piles  sustains  the  super- 
imposed load  without  any  material  settlement. 
Concrete  piers,  on  the  other  hand,  do  not  depend 
on  friction  except  when  it  is  impossible  to  carry 
them  down  to  bed-rock,  in  which  case  their  sustain- 
ing power  is  usually  increased  by  increasing  the 
diameter  of  the  lower  section  to  form  a  bell-shaped 
footing  which  gives  additional  bearing  area. 

Building  codes  in  various  cities  specify  the  max- 
imum load  allowed  on  clay  or  other  soils.  For 
clay,  the  allowable  unit  pressures  go  as  high  as 
7,000  pounds  per  square  foot  for  spread  founda- 
tions. Concrete  piers  are  usually  proportioned  to 
carry  a  load  of  40,000  to  50,000  pounds  per  square 
foot  at  the  top.  The  load  generally  used  for  wood 
or  concrete  piles  seldom  exceeds  20  tons  per  pile 

141 


but  it  will  be  found  that  in  most  cases  long  piles, 
driven  to  refusal  will  carry  safely  50  tons.  Foun- 
dations and  footings  are  rarely  or  never  reinforced, 
dependence  being  placed  on  their  mass  for  the  re- 
quired strength.  There  are,  however,  exceptions. 

For  small  structures,  it  is  frequently  possible  to 
place  the  concrete  for  the  foundation  in  the  exca- 
vated earth  trench  without  using  forms  until 
ground  level  is  reached.  This  is  true  when  the 
earth  is  sufficiently  firm  to  prevent  caving  of  the 
sides  of  the  trench.  However,  when  concrete  is 
placed  under  such  conditions,  workmen  should  be 
cautioned  against  running  wheel-barrows  too  near 
the  edge  of  the  trench,  thus  resulting  in  earth 
dropping  into  freshly  placed  concrete  and  causing 
porous  pockets  in  the  mass.  The  best  way  is  to 
lay  planks  alongside  of  the  trench.  Also,  in  spad- 
ing or  tamping  concrete  for  foundations  where  it  is 
being  deposited  in  a  trench  without  forms,  care 
should  be  taken  not  to  knock  down  fresh  earth  into 
the  concrete  for  the  reason  above  mentioned. 
Sometimes,  as  in  the  case  of  excavations  for  a  base- 
ment or  cellar,  the  concrete  will  need  a  form  only 
on  the  inside,  the  earth  wall  of  the  excavation  serv- 
ing in  this  case  as  the  outer  form. 

Table  No.  22 

BEARING  POWER  OF  SOILS 


Supporting 
Power  in 
Tons  per  Sq. 

Ft. 

Rock  —  in  thick  layers,  in  natural  bed.                               

200 

Clay  —  in  thick  beds,  always  dry  

4 

Clay  —  inthick  beds,  moderately  dry  

2 

Clay  —  soft 

1 

Gravel  and  coarse  sand,  well  cemented  

8 

Sand  —  compact  and  well  cemented                             .          

4 

2 

Loam  soils    .           .                 .                 .                     

0.5 

142 


CHAPTER  12. 
WATERPROOFING  OF  CONCRETE 

Poor  Concrete  Responsible   for    Popular  Belief 
that  Concrete  is  not   Watertight 

Much  concrete  construction  that  has  been  done 
would  give  many  the  impression  that  concrete 
could  not  resist  the  passage  of  water.  This  has 
given  rise  to  discussion  as  to  the  waterproofness 
or  watertightness  of  concrete. 

Good  Concrete  Properly  Mixed  is  Water  Tight 

Probably  no  concrete  ever  has  been,  nor  ever 
will  be  made  that  does  not  contain  a  considerable 
percentage  of  voids.  But  for  all  practical  purposes 
concrete  can  be  made  watertight.  The  simplest 
way  of  doing  this  is  to  so  proportion  well  graded 
materials  that  voids  will  be  reduced  to  the  lowest 
possible  minimum,  and  as  existing,  will  not  be  con- 
nected with  one  another  so  as  to  result  in  continu- 
ous open  channels  through  the  mass. 

The  fact  that  concrete  well  made  and  properly 
placed  is  essentially  a  watertight  material,  is  proved 
in  many  structures  long  used  successfully  as  con- 
tainers for  water,  oil  or  other  liquids. 

Thin  sections  of  concrete  are  likely  to  contain 
small  fissures  that  will  permit  seepage.  Also  such 
sections  are  almost  invariably  porous  because  of  the 
difficulty  in  placing  thin  sections  of  concrete  in 
forms  to  insure  uniform  density  of  the  structure 
throughout.  However,  countless  structures  such  as 
tanks,  standpipes  and  other  concrete  receptacles  for 
fluids  stand  today  as  evidence  that  concrete  can  be 
made  watertight  for  all  practical  purposes. 

Fundamentals  for   Watertightness 

Primarily,  several  fundamentals  govern  the  suc- 
cess or  failure  to  attain  watertight  concrete.  These 
fundamentals  when  observed  or  disregarded,  as  the 

143 


case  may  be,  contribute  to  the  success  or  failure  of 
the  desired  end.  If  mixtures  are  not  properly  pro- 
portioned, if  the  materials  of  which  they  are  pro- 
portioned are  not  graded  so  as  to  reduce  voids  to 
the  lowest  possible  limit,  if  mixtures  are  too  dry  or 
too  wet,  if,  after  placing,  the  concrete  is  not  pro- 
tected against  too  rapid  drying  out,  the  work  will 
not  be  watertight.  It  is  necessary,  of  course,  that 
most  uses  of  concrete  in  building  construction  shall 
result  in  work  that  is  watertight  or  waterproof  be- 
cause basement  walls,  floors  and  roofs  fail  in  part 
of  their  intended  usefulness  unless  such  an  end  is 
attained. 

Reinforcing  steel  must  also  be  prevented  from 
rusting  and  this  can  only  be  done  when  the  concrete 
covering  it  is  essentially  impermeable  to  water. 

Systems  for  Increasing   Watertightness 

There  are  three  principal  methods  or  systems 
employed  to  increase  the  watertightness  of  con- 
crete. They  may  be  termed  the  "integral,"  "super- 
ficial" and  "membrane"  methods.  The  first  consists 
in  adding  a  material  to  the  concrete  when  it  is 
mixed.  The  superficial  method  consists  of  coating 
the  concrete  surface  with .  a  preparation  that  will 
adhere  to  it  and  remain  attached.  The  membrane 
method  consists  of  putting  on  the  concrete  a  coat- 
ing distinct  from  it.  While  this  coating  may  ad- 
here to  the  concrete,  it  will  not  crack  if  the  concrete 
does,  because  of  being  a  distinct  and  somewhat 
elastic  membrane,  usually  strengthened  by  felt  or 
other  fiber  cloth  and  impregnated  with  a  mastic 
asphaltic  or  bituminous  material. 

The  three  methods  just  summarized  have  ad- 
vantages as  well  as  disadvantages.  For  example,  it 
is  impossible  to  use  the  integral  method  to  prevent 
water  from  seeping  through  concrete  after  the  work 
has  been  finished.  In  integral  as  well  as  in  superfi- 
cial methods  o'f  treatment,  cracks  developing  in  the 
concrete  would  make  the  possible  waterproofing 
medium  or  method  in  these  classes  of  no  avail.  In 
the  membrane  as  well  as  the  superficial  method, 

144 


care  must  be  taken  not  to  puncture  the  waterproof- 
ing coat. 

The  three  methods  of  waterproofing  mentioned 
are  closely  allied  and  there  are  various  processes  of 
waterproofing  on  the  market  that  are  about  halfway 
between  two  of  the  methods.  For  example,  when 
melted  paraffin  is  applied  to  a  concrete  surface  with 
a  brush,  as  is  sometimes  done  to  increase  water- 
tightness,  the  treatment  belongs  to  the  superficial 
method,  though  the  paraffin  may  penetrate  the  con- 
crete so  far  as  to  be  classed  as  an  example  of  the 
integral  method.  Some  paints  may  be  classed  as 
belonging  to  the  superficial  methods  though  they 
are  elastic  enough  to  bridge  over  very  small  cracks 
that  may  develop  in  the  concrete  and  thus  come 
within  the  membrane  class. 

There  are  a  number  of  proprietary  preparations 
on  the  market,  the  use  of  which  is  urged  by  the 
manufacturers  in  the  interest  of  increasing  the  wa- 
tertightness  of  concrete.  Without  approving  or 
condemning  the  claimed  merits  of  any  of  these 
preparations,  it  may  be  said  that  in  no  case  will 
their  use  be  successful  unless  in  proportioning,  mix- 
ing and  placing  the  concrete  and  protecting  it  after 
placed,  all  of  the  fundamentals  of  good  concreting 
practice  are  recognized. 

One  of  the  oldest  processes  of  waterproofing 
concrete  is  known  as  the  Sylvester  process.  It 
consists  of  applying  powdered  alum  and  soft  soap 
to  the  concrete.  These  materials  combine  chemi- 
cally to  form  compounds  that  are  insoluble  in  water 
and  fill  the  surface  voids  in  the  concrete  with  an  in- 
soluble, gelatinous  mass.  As  a  rule  the  Sylvester 
process  is  applied  by  painting  on  the  concrete  two 
separate  solutions  of  alum  and  soap. 

Asphalt  and  coal  tar  are  used  for  waterproofing, 
particularly  the  outside  of  foundation  or  basement 
walls.  They  are  applied  hot  with  a  mop.  Several 
coatings  are  usually  applied. 


145 


146 


CHAPTER  13. 
PLACING  CONCRETE  UNDER  WATER 

When  concrete  must  be  placed  under  water,  the 
work  should  be  done  in  such  a  manner  that  the 
ingredients  of  the  mix  will  not  separate.  Either  a 
tremie  must  be  used — that  is,  a  large  pipe  through 
which  the  concrete  is  carried  to  a  point  near  the 
bottom  of  the  water;  or  large  buckets  with  hinged 
bottoms,  that  can  be  lowered  and  from  which  the 
concrete  can  be  dumped  with  least  disturbance. 

When  a  tremie  is  used,  the  pipe  is  gradually 
withdrawn  and  thus  elevated  upward  as  the  mass 
of  concrete  deposited  is  increased.  The  best  results 
are  obtained  by  mixing  the  concrete  moderately 
dry,  although  when  depositing  by  means  of  a  pipe 
or  chute,  the  concrete  is  often  mixed  very  dry.  The 
difficulty  often  encountered  in  placing  concrete  un- 
der water  usually  results  from  lack  of  care  to  pre- 
vent separation  of  materials.  If  the  concrete  is 
thrown  into  the  water  or  even  allowed  to  settle 
through  it,  separation  of  materials  is  unavoidable. 

One  common  and  inexpensive  method  is  to 
provide  a  closed  rectangular  wood  chute  or  a  circu- 
lar metal  one.  This  is  placed  with  one  end  extend- 
ing into  the  water  and  to  the  foundation  in  such 
a  manner  as  to  prevent  the  concrete  from  flowing 
out  while  the  chute  is  being  filled.  When  entirely 
filled,  it  is  raised  slightly,  thereby  permitting  the 
concrete  to  gradually  distribute  itself  and  at  the 
same  time  permit  additional  concrete  to  be  placed 
in  the  chute,  so  that  at  no  time  can  water  enter. 

In  extensive  work,  a  closed  bucket  with  hinged 
bottom  is  often  used.  In  some  cases  concrete  has 
been  placed  under  water  in  coarse  jute  sacks  which 
were  lowered  to  the  bottom  of  the  foundation.  This 
method,  however,  is  not  dependable  since  frequent- 
ly there  is  poor  bond  between  different  parts  of  the 
foundation.  When  the  concrete  is  to  be  deposited 

147 


from  an  airtight  receptacle  lowered  into  the  water, 
it  should  be  mixed  dry  enough  so  that  when  the 
gate  or  trap  door  of  the  bucket  is  opened,  the  ma- 
terial will  be  discharged  in  a  mass. 

Cofferdams  should  be  sufficiently  tight  to  pre- 
vent current  of  water  through  the  pit  and  in  other 
respects  the  water  should  be  quiet.  The  surface  of 
the  concrete  deposited  must  be  kept  as  nearly  level 
as  possible  to  avoid  the  formation  of  pockets  which 
will  retain  laitance  and  sediment.  Where  concrete 
is  not  deposited  continuously,  all  sediment  should 
be  removed  from  the  surface  of  the  concrete  by 
pumping  or  some  other  means  before  concreting  is 
resumed.  No  mixture  leaner  than  1 :2 :4  should  be 
used  when  concrete  is  deposited  under  water. 


148 


CHAPTER  14. 

NOTES  ON  SILOS,  COAL  AND  MATERIAL 
BINS  AND  GRAIN  TANKS 

As  a  rule  all  structures  coming  under  the  above 
heading  are  circular  in  shape,  the  exception  being 
that  sometimes  coal  pockets  and  other  material  bins 
may  be  of  rectangular  form.  However,  because  of 
the  development  of  circular  forms  for  such  con- 

tstruction,  the  occasions  where  rectangular  bins  are 
used  are  those  largely  governed  by  the  location. 
The  circular  type  of  structure  is  in  general  more 
popular  and  becoming  more  common. 

Certain  essentials  of  construction  are  alike  in 
all  of  the  structures  mentioned.  Because  of  the 
pressure  of  contained  contents  all  must  be  the  sub- 
ject of  engineering  design,  principally  to  insure  that 
the  concrete  will  be  sufficiently  reinforced  to  with- 
stand internal  pressure. 

Reinforcement  for  any  of  the  structures  men- 
tioned may  be  either  rods  or  some  one  of  the  sev- 
eral types  of  mesh  fabric  used  as  concrete  reinforce- 
ment. To  illustrate  the  method  of  determining  the 
kind  of  reinforcement  required  for  a  monolithic 
concrete  silo  for  example,  reference  is  made  to  an 
accompanying  table  which  shows  the  spacing  of 
horizontal  reinforcing  bars  for  silos  of  various  in- 
side diameters.  Assume  a  silo  14  feet  inside  diam- 
eter and  40  feet  high  as  an  example.  For  an  inside 
diameter  of  14  feet,  the  table  specifies  */2 -inch  round 
rods.  The  column  at  the  extreme  left  of  the  table 
gives  the  distance  from  the  top  of  the  silo  for  in- 
tervals of  5  feet.  As  the  silo  is  40  feet  high,  run 
down  the  column  to  the  line  "35  to  40  feet,"  then 
across  to  the  column  under  "14  feet  diameter." 
This  shows  the  spacing  as  12  inches  which  means 
that  there  must  be  a  horizontal  ring  of  %-inch  steel 
every  12  inches.  This  spacing  applies  to  the  first 
5  feet  above  the  floor.  For  the  next  5  feet  the  spac- 
ing changes  to  14  inches.  Spacing  becomes  great- 

149 


er  as  the  top  of  the  silo  is  approached  and  can  be 
found  by  simply  following  the  14- foot  column  to  the 
top.  This  method  of  determining  the  horizontal  re- 
inforcement applies  to  all  sizes  and  heights  of  silos. 

Table  No.  23 

SPACING  OF  HORIZONTAL  REINFORCING  RODS  FOR 
SILOS  OF  VARIOUS   INSIDE    DIAMETERS 


Distance 

10-foot 

12  -foot 

14-foot 

16-foot 

18  -foot 

20  -foot 

in  Feet 

Diameter 

Diameter 

Diameter 

Diameter 

Diameter 

Diameter 

Down 
from  Top 

%-inch 
Round 

jHi-inch 
Round 

Vz-inch 
Round 

Vz-inch 
Round 

V2-inch 
Round 

Vz-inch 
Round 

of  Silo 

Rods 

Rods* 

Rods* 

Rods* 

Rods* 

Rods* 

Inch 

Inch 

Inch 

Inch 

Inch 

Inch 

Top  5  ft. 

24 

24 

24 

24 

24 

24 

5  to  10 

24 

24 

24 

24 

24 

24 

10  to  15 

24 

18 

24 

24 

24 

24 

15  to  20 

18 

16 

24 

18 

18 

16 

20  to  25 

16 

12 

18 

16 

14 

14 

25  to  30 

14 

10 

16 

14 

12 

12 

30  to  35 

12 

9 

14 

12 

10 

10 

35  to  40 

10 

8 

12 

10 

9 

8 

40  to  45 

9 

7 

11 

9 

8 

7% 

45  to  50 

8 

6'/2 

10 

81/2 

7V2 

7 

*If  square  rods  are  used  increase  spacing  30  per  cent,  but  in  no  case 
should  spacing  be  greater  than  24  incnes. 

Vertical  reinforcement  is  needed  in  all  monolithic 
concrete  silos.  Usually  this  consists  of  %  or  %• 
inch  steel  rods  spaced  30  inches  apart  around  the 
circumference  of  the  silo  regardless  of  its  size.  In 
this  connection  it  should  be  mentioned  that  while 
theoretically  the  center  of  the  wall  is  not  the  exact 
place  where  reinforcement  should  be  placed  in  a  cir- 
cular structure,  in  designing  for  the  reinforcement 
a  factor  of  safety  is  considered  which  permits  plac- 
ing reinforcement  at  the  center  of  the  concrete  sec- 
tion principally  to  facilitate  placing  of  concrete.  At- 
tention also  should  be  called  to  the  necessity  of  se- 
curely wiring  horizontal  to  vertical  rods,  correctly 
spaced  at  their  intended  location  so  that  they  may 
not  be  misplaced  while  depositing  concrete. 

Usually  concrete  of  three  different  proportions  is 
used  in  building  monolithic  silos.  Requirements  for 
materials  are  given  elsewhere  under  "Aggregates." 
Table  No.  1  page  28.  A  1 :2%  :5  mixture  is  generally 

150 


used  for  foundation  and  floor.    For  the  walls  a  1 :2 :4 
mixture  is  used  and  for  the  roof  a  1:2:3  mixture. 

An  accompanying  table  gives  quantity  of  concrete 
materials  for  monolithic  silos  of  various  diameters. 

Table  No.  24 

QUANTITY  OF  CONCRETE  MATERIALS  FOR  MONOLITHIC 
SILOS   OF   VARIOUS    DIAMETERS 

These  figures  include  footings  and  floor,  but  not  roof.  Walls  6  inches 
thick.  Continuous  doors  2  feet  wide.  Figures  are  for  sacks  of  cement 
and  cubic  yards  of  sand  and  pebbles: 


For  Silo  30  Feet  High 

For  Each  Additional  5  Feet 

Inside 

in  Height 

Diameter 

Feet 

Cement 

Sand 

Pebbles 

Cement 

Sand 

Pebbles 

or  Stone 

or  Stone 

Sacks 

Cu.  Yd. 

Cu.  Yd 

Sacks 

Cu.  Yd. 

Cu.  Yd. 

10 

116 

11 

18 

16.0 

1.5 

2.4 

12 

140 

13 

21.5 

19.2 

1.8 

2.9 

14 

164 

15 

25 

22.5 

2.1 

3.4 

16 

188 

17.3 

28.7 

25.7 

2.4 

3.8 

18 

212 

19.6 

32.6 

29.0 

2.7 

4.3 

20 

236 

22 

36.5 

32.3 

3.0 

4.8 

In  order  to  assist  contractors  in  giving  informa- 
tion as  to  size  of  silo  required,  a  table  showing  di- 
ameter of  silo  necessary  to  feed  various  numbers 
of  animals  and  another  showing  the  approximate 
capacity  of  round  silos  are  given. 

Table  No.  25 

DIAMETER    OF    SILOS    REQUIRED    TO    FEED 
VARIOUS    NUMBERS    OF    ANIMALS 


Minimum  number  of  each  kind  of  stock  to 

Approxi- 

be fed  from  each  size  silo 

Diameter 

mate 

in  Feet 

Pounds  to  be 

Fed  Daily 

Dairy 
Cows 

Beef 
Cattle 

Stock 
Cattle 

500-lb. 
Calves 

Horses 

Sheep 

10 

525 

13 

21 

26 

44 

48 

75 

12 

755 

19 

30 

38 

63 

69 

252 

14 

1030 

26 

41 

52 

86 

94 

344 

16 

1340 

34 

54 

67 

112 

122 

446 

18 

1700 

42 

68 

85 

142 

155 

567 

20 

2100 

53 

84 

105 

175 

191 

700 

151 


Table  No.  26 

APPROXIMATE  CAPACITY  OF  ROUND  SILOS 


Inside  Diameter  of  Silo  in  Feet  and  Capacity  in  Tons 

Height 

OI 

Silo 

Feet 

10  feet 

12  feet 

14  feet 

16  feet 

18  feet 

20  feet 

Tons 

Tons 

Tons 

Tons 

Tons 

Tons 

28 

42 

61 

83 

30 

47 

67 

91 

32 

51 

74 

100 

131 

34 

56 

80 

109 

143 

36 

61 

87 

118 

155 

196 

38 

66 

94 

128 

167 

212 

40 

70 

101 

138 

180 

229 

280 

42 

109 

148 

193 

244 

299 

44 

117 

159 

207 

261 

320 

46 

170 

222 

277 

340 

48 

236 

293 

361 

50 

310 

382 

Bins  for  holding  materials  other  than  grain  such 
as  coal,  sand,  etc.,  are  sometimes  built  under  trestles 
and  are  filled  by  dumping  into  an  opening  in  the 
top,  or  by  bucket,  belt  or  screw  conveyors.  They  are 
emptied  through  gates  at  or  near  the  bottom  or  by 
dippers  and  grab  buckets.  Others  are  filled  and 
emptied  in  much  the  same  manner  as  grain  bins. 

The  average  grain  elevator  provides  for  the  fol- 
lowing parts  and  operation: 

1.  A  receiving  shed  where  the  grain  is  dumped 
from  wagons  into  chute  ending  in  a  boot  at 
the  foot  of  the  elevator.     Usually  a  scale  is 
provided  to  weigh  the  grain  as  received. 

2.  The  elevator  is  an  endless  chain  or  belt  with 
buckets    which    carry    the    grain  to  a  head- 
house  where  it  is  delivered  by  spout  to  the 
bins.    A  belt  conveyor  is  generally  necessary 
where  there  is  a  group  of  several  bins. 

3.  When  removing  grain  from  the  bin  for  ship- 
ping, it  is  usually  spouted  from  the  bottom  of 
the  bins  into  the  boot  at  the  foot  of  the  ele- 
vator and  from  there  elevated  to  the  work- 
ing floor. 

4.  Elevators  may  or  may  not  contain  drying  and 
cleaning  machines  and  other  special  machinery. 

152 


Lengths  of  rods  used  as  reinforcement  are  gen- 
erally such  that  splices  must  be  made.  The  only  re- 
liable splice  is  to  lap  the  ends  enough  to  develop 
bond.  If  the  pieces  are  in  contact  there  will  be  loss 
of  bonding  area,  amounting  in  the  case  of  s.quare 
bars  to  25  per  cent.  For  efficient  bond  the  concrete 
must  everywhere  completely  surround  the  steel. 
Lapped  ends  should  have  a  clear  space  between 
them  of  not  less  than  twice  the  thickness  of  the 
steel,  the  minimum  distance  being  1  inch  regardless 
of  the  thickness  of  the  steel.  This  may  be  obtained 
by  placing  a  piece  of  steel  or  concrete  between  the 
ends  of  the  rods  and  wrapping  around  them  some 
soft  wire  to  keep  the  ends  separated  while  concrete 
is  being  placed.  Horizontal  reinforcement  is  gener- 
ally placed  on  the  outside  of  vertical  reinforcement, 
merely  because  this  is  the  easiest  way  to  place  it. 

Accompanying  tables  show  quantity  of  rein- 
forcement required  for  bins  of  various  diameter  and 
height,  and  capacity  of  circular  bins  and  tanks  in 
bushels. 

This  table  and  the  two  following  are  based  on 
data  contained  in  the  text  book  known  as  "Walls, 
Bins  and  Grain  Elevators"  by  Milo  S.Ketchum, pub- 
lished by  the  McGraw-Hill  Book  Co.,  New  York. 

Figures  given  for  quantities  of  reinforcement 
required  are  theoretically  correct  but  each  bin  or 
tank  should  be  the  subject  of  special  engineering 
design  so  that  the  particular  requirements  in  ques- 
tion to  be  met  will  be  accurately  determined. 


Circular  Grain   Tanks 

Area  of  horizontal  reinforcing  steel  in  square 
inches  per  foot  of  depth,  and  thickness  of  wall  in 
inches.  Steel  to  be  in  center  of  wall. 

Set  ^4-inch  rods  vertically  at  approximately  6- 
foot  centers  and  %-inch  rods  between  them  at  ap- 
proximately 2-foot  centers. 

153 


Table  No.  27 

CIRCULAR  GRAIN  TANKS— DIAMETER  IN  FEET 


Depth 

in 

8 

10 

12 

14 

16 

18 

20 

22 

Feet 

f 

5 

0.026 

0.033 

0.040 

0.046 

0.053 

0.059 

0.066 

0.072 

10 

0.041 

0.066 

0.079 

0.092 

0.105 

0.118 

0.131 

0.145 

15 

0.050 

0.073 

0.096 

0.120 

0.157 

0.194 

0.197 

0.217 

20 

0.056 

0.082 

0.109 

0.140 

0.171 

0.207 

0.234 

0  289 

25 

0.058 

0.087 

0.119 

0.153 

0.190 

0.228 

0.268 

0.309 

30 

0.059 

0.090 

0.125 

0.163 

0.204 

0.246 

0.294 

0.336 

35 

0.060 

0.091 

0.128 

0.170 

0.213 

0.260 

0.309 

0.360 

40 

0.062 

0.092 

0.131 

0.174 

0.219 

0.270 

0.324 

0.381 

45 

0.064 

0.094 

0.134 

0.179 

0.225 

0.288 

0.335 

0.398 

50 

0.066 

0.095 

0.135 

0.183 

0.235 

0.290 

0.347 

0.410 

Thick- 
ness 

6" 

6" 

6" 

6" 

7" 

7" 

7" 

8" 

of  wall 

Square  Grain  Tanks 

Upper  figures  give  thickness  of  wall  in  inches. 
Lower  figures  give  area  of  reinforcement  in  square 
inch  per  foot  of  depth.  Center  of  horizontal  steel 
to  be  IJ^-inch  from  face  of  wall.  Vertical  bars 
54-inch  round  or  y2-mch  square  to  be  spaced  24-inch 
centers  (approx.) 

Table  No.  28 

SQUARE  GRAIN  TANKS— DIMENSIONS  IN  FEET 


Depth 
in 
Feet 

8'x8' 

10'xlO' 

12'xl2' 

14'xl4' 

16'xl6' 

18'xl8' 

20'x20' 

22'x22' 

5 

4" 

4" 

4.5" 

6.0" 

6.0" 

6.5" 

8.0" 

85" 

0.23 

0.28 

0.34 

0.43 

0.50 

0.55 

0.60 

0.65 

10 

4" 

5.5" 

6.5" 

8.0" 

9.0" 

10.0" 

10.5" 

10.5" 

0.28 

0.39 

0  47 

0.60 

0.68 

0.77 

0.83 

0.91 

15 

4.5" 

5.5" 

7.0" 

9.5" 

10.5" 

11.5" 

12.5" 

14.0" 

0.31 

0.42 

0.52 

0.74 

0.86 

0.94 

1.02 

1.15 

20 

4.5" 

6.0" 

7.0" 

9.5" 

11.0" 

13.0" 

14.0" 

15.5" 

0.32 

0.44 

0.55 

0.74 

0.90 

1.06 

1.18 

1.28 

25 

5" 

6" 

7.5" 

10.0" 

11.5" 

13.0" 

14.5" 

16.0" 

0.34 

0.46 

0.58 

0.80 

0.93 

1.06 

1.22 

1.34 

30 

5" 

6.5" 

8.0" 

10.0" 

11.5" 

13.5' 

15.0" 

16.5" 

0.34 

0.46 

0.63 

0.80 

0.96 

1.11 

1.27 

1.38 

35 

5" 

6.5" 

8.5' 

10.5" 

12.0" 

14.0" 

15.5" 

17.0" 

0.35 

0.48 

0.66 

0.82 

0.97 

1.14 

1.27 

1.44 

40 

5" 

6.5" 

8.5" 

10.5" 

12.0" 

14.0" 

15.5" 

17.5" 

0.35 

0.48 

0.67 

0.83 

0.99 

1.16 

1.30 

1.48 

45 

5" 

6.5" 

8.5" 

11.0" 

12.5" 

14.0" 

16.0" 

18.0" 

0.35 

0.48 

0.68 

0.84 

1.00 

1.18 

1.33 

1.51 

50 

5' 

6.5" 

8.5" 

11.0" 

12.5" 

14.5" 

16.0" 

18.0" 

0.35 

0.<?8 

0.68 

0.85 

1.03 

1.20 

1.35 

1.54 

154 


Table  No.  29 


CAPACITY   OF   CIRCULAR   GRAIN   BINS   AND   TANKS— IN 
BUSHELS 


Height 

Diameter  in  Feet 

10 

12 

14 

16 

18 

20 

22 

24 

10 
15 

631 

946 

910 
1364 

1238 
1855 

1616 
2420 

2042 
3060 

2525 
3785 

3060 
4590 

3550 
5320 

20 

1212 

1820 

2475 

3230 

4090 

5050 

6125 

7100 

25 

1578 

2275 

3095 

4040 

5100 

6310 

7650 

8880 

30 

1892 

2730 

3715 

4840 

6125 

7575 

9180 

10630 

35 

2208 

3185 

4340 

5650 

7145 

8840 

10700 

12400 

40 

2525 

3640 

4950 

6460 

8170 

10018 

12240 

14560 

45 

2840 

4095 

5570 

7270 

9190 

11350 

13780 

16380 

50 

3158 

4550 

6195 

8030 

10210 

12620 

15300 

18200 

55 

5005 

6814 

8888 

11231 

13882 

16830 

20020 

60 

5460 

7433 

9696 

12252 

15144 

18360 

21840 

65 

8053 

10504 

13273 

16406 

19890 

23660 

70 

8672 

11312 

14294 

17668 

21420 

25480 

75 

.... 

9293 

12120 

15315 

18930 

22950 

27300 

80 

.... 

.... 

12928 

16336 

20192 

24480 

29120 

85 

.... 

13736 

17357 

21454 

26010 

30940 

90 

14544 

18373 

22716 

27510 

32760 

95 

19399 

23978 

29070 

34580 

100 

20420 

25240 

30600 

36400 

lbushel=2150cu.  inches=1.245  cu.ft.  or  I  cu.  ft.  =  1728  cu.  inches= 
1 . 245  cu.  ft.  per  bu. 

Note: — Special  bins  should  always  be  the  subject  of  special  en 
gineering  design. 


155 


g 

8 

S 

5 

§ 

S 

g 

§ 

3 

§ 

S 

S 

§ 

g 

g 

g 

-.• 

~ 

cvi 

o 

04 

CO 

S 

g 

s 

9 

$ 
2 

:£ 
5 

in 

S 
S 

« 

M 

^! 
» 

M 

3 

w 

X 

3 

«t 

« 
^t 

^ 

r* 
m 

IO 

r^ 
in 

S 

8 
t>> 

§ 

8 

in 

!*• 
S 

s 

5 

8 

3 

S 

2 

S 

S 

ie 

s 

s 

3 

S 

S 

§ 

S 

§ 

S 

g 

S 

•• 

"• 

M 

M 

« 

« 

« 

*» 

in 

— 

00 

SJ 

& 

3 

8 

S 

:£ 
S 

8 

X 

!n 

0 

^ 
3 

in 

^ 

£ 

S 

^ 

s 

3 

s 

s 

S 

s 

s 

S 

— 

— 

N 

M 

w 

m 

•* 

»* 

m 

0 

in 

?3 

8 

P5 

3 

S 

§ 

S 

§ 

S 

§ 

S 

§ 

s 

S 

§ 

§ 

S 

g 

g 

g 

— 

— 

04 

<M 

m 

« 

Tt 

* 

in 

O 

in 

s 

S 

s 

$ 

S 
t 

S 

in 

s 

s 

S 

^ 

S 

in 

X 
g 

S 

f 

12 

S 

cQ 

s 

12 

s 

8 

* 

— 

— 

(VI 

M 

m 

(O 

rt 

t 

Oft 

«» 

Oft 

S 

8 

S 

m 

5 

g 

8 

s 

g 

S 

in 

s 

S 

S 

s 

S 

s 

S 

g 

S 

* 

— 

— 

N 

M 

« 

« 

^ 

«» 

Oft 

CO 

CO 

S 

S 

CO 

Ml 

S 

5 

S 
3 

« 

X 
^ 

g 

^ 
CM 

3 

S 

3 

^ 

« 

« 

s 

m 

r* 

g 

« 

S 

S2 

P  W 

£! 

il 

M 

s 

8 

t»! 

SSJ 

3 

5 

s 

s 

§ 

§ 
CJ 

3 

N 

§ 

N 

8 

eo 

§ 

CO 

g 
«* 

8 

00 

§ 

N 

g 

g 

8 

g 

3 

g 
8 

B|- 

S 

X 
5 

£ 

s 

M 

s 

X 

5 

S 

^ 
3 

§ 

X 

P; 

!5 

s 

8 

g 

S 

s 

8 

co 

— 

— 

— 

CM 

N 

« 

co 

CO 

r«. 

3 

in 

00 

Si 

8 

to 

$ 

g 

8 

3 

IS 

O 

in 

§ 

in 

s 

S 

S 

g 

s 

g 

S 

CO 

— 

— 

— 

M 

M 

CM 

co 

co 

r* 

0 

2 

£ 

M 

8 

S 

SJ 

S 
3 

8 

s 

8 

^ 
3 

in 

Oft 

2 
«4 

S 

S 

3 

a 

S 

12 

g 

s 

S 

12 

— 

— 

- 

N 

N 

« 

8 

o 

8 

S 

§ 

S 

S 

S 

0 

3 

S 

s 

s 

S 

g 

g 

g 

g 

"• 

"• 

•• 

M 

M 

M 

- 

M 

S 

£ 

S 
S 

£ 

s 

3 

e 

« 
^ 

s 

£ 

S 

S 

X 

5 

s 

^ 
s 

in 
01 

S 

s 

s 

8 

— 

— 

— 

— 

N 

M 

M 

!2 

8 

S 

£ 

§ 

S 

s 

5S 

S 

S 

S 

s 

S 

g 

s 

g 

S 

™" 

^ 

mm 

^ 

- 

- 

- 

£ 

1 

- 

N 

0 

8 

8 

3 

s 

s 

S 

156 


CHAPTER  15. 

MECHANICAL  EQUIPMENT— ITS   STARTING 
CARE  AND  OPERATION 

The  best  equipment  that  it  is  possible  to  make 
can  be  quickly  ruined  and  its  usefulness  destroyed 
by  improper  care  and  operation.  Every  contractor 
desires  to  get  the  best  possible  results  from  his 
equipment,  and  he  hires  the  best  obtainable  opera- 
tors to  take  care  of  his  machines.  At  times,  how- 
ever, new  men  have  to  be  broken  in,  and  in  order 
that  these  men  may  have  the  benefit  of  the  experi- 
ence of  others,  we  have  compiled  in  this  chapter 
useful  data  as  to  the  starting,  care  and  operation 
of  Koehring  Mixers. 

Embodied  in  this  will  be  found  data  that  will 
also  be  of  interest  and  value  to  experienced  oper- 
ators. In  addition,  our  Research  and  Engineering 
Departments  will  be  glad  to  answer  any  questions 
submitted  to  them  by  operators,  with  a  view  to  en- 
abling them  to  secure  the  greatest  possible  output 
from  their  machines  under  existing  conditions. 

Method  of  Unloading  Mixer 

Assuming  that  the  car  containing  a  Koehring 
Mixer  has  arrived  at  the  nearest  siding  to  the  work 
and  that  the  blocking  has  been  removed,  jack  up  the 
mixer  and  put  wheels,  or  multiplane  tractors  in 
place.  A  runway  of  at  least  20  feet  long  should  be 
built  to  make  an  easy  grade.  If  an  abundance  of 
railroad  ties  is  available,  one  may  build  a  close  crib- 
bing of  them,  and  use  3"  x  12"  planks  for  runways. 
If  the  ties  are  not  to  be  had,  heavier  stringers  may 
be  hauled  to  the  siding,  as  they  do  not  require  as 
much  blocking  as  the  above  mentioned  method. 
After  the  runway  is  built,  block  the  wheels  of  the 
flat  car  securely,  fasten  block  and  tackle  to  the  frame 
of  the  mixer  and  to  the  draw  bar  of  the  car  on  the 
opposite  end  from  the  cribbing.  Use  pinch  bars  un- 
der the  truck  wheels  and  work  the  mixer  gradually 
onto  the  incline,  lowering  slowly  by  means  of  the 

157 


blocks  and  tackle.  A  Paving  Mixer  may  also  be 
run  off  of  car,  and  down  runway  under  its  own 
power,  if  desired. 

Assembling  of  Paving  Mixers 

The  first  step  in  assembling  a  Koehring  Paver, 
after  unloading,  is  the  placing  of  the  overhead  steel 
frame,  which  should  be  put  together  as  indicated 
by  the  marks  on  the  different  parts.  The  tighten- 
ing of  bolts  should  be  left  until  the  framework  is 
completely  assembled  as  it  may  be  necessary  to  ad- 
just some  parts  of  it  by  means  of  drift  pins.  By 
leaving  bolts  loose,  the  operation  is  made  easier. 
After  all  bolts  are  in  place,  see  that  lock  washers 
are  on  each,  and  then  draw  nuts  up  tight. 

Next,  load  the  charging  skip  of  the  paver  on  a 
truck,  back  the  truck  to  the  mixer  and  fasten  skip 
in  proper  place.  This  method  of  attaching  skip 
eliminates  much  lifting  and  blocking,  and  saves 
much  time.  The  two  skip  cables  are  then  led  from 
the  grooved  winding  sheaves,  over  the  small  sheaves 
near  the  top  of  the  frame,  to  the  cable  brackets  on 
the  skip.  Care  should  be  taken  to  have  the  same 
tension  on  each  cable  to  prevent  twisting  of  the 
skip.  It  is  also  important  that  the  cable  ends  are 
fastened  securely. 

Before  the  large  sheave  is  &eyed  on,  all  cable 
should  be  run  off  and  rewound  to  be  sure  that  there 
is  no  twist  in  it.  This  is  extremely  important  as 
the  cable  will  continue  to  jump  off  the  winding  drum 
if  twisted.  Next,  be  sure  that  the  sheave  fits  within 
1/32"  of  the  bearing;  then  drive  the  key  home. 
When  skip  is  on  the  ground  the  hoisting  cable 
should  practically  fill  the  large  sheave  and  there 
should  be  \y2  wraps  on  the  winding  drum.  On  the 
14E  Paver,  in  order  that  the  cable  may  lead  prop- 
erly, the  grooved  winding  sheave  should  be  keyed 
on  at  the  end  of  the  shaft  and  not  close  up  against 
the  large  sheave. 

Next,  load  boom  on  truck,  back  truck  to  paver 
and  secure  boom  in  place.  As  the  boom  support 
cable  is  attached  to  boom,  when  shipped,  it  is  a  sim- 

158 


pie  matter  to  hang  it.  Take  cable  off  of  sheave  on 
boom  where  it  is  attached,  and  get  the  slack  needed 
by  turning  the  boom  elevating  hand  wheel  and  then 
slip  over  sheave  which  is  attached  near  top  of  frame. 

On  the  10E,  21E  and  32E,  the  delivery  bucket 
cable  is  reaved  onto  the  grooved  winding  drum 
when  shipped  from  the  plant,  so  all  that  is  neces- 
sary is  to  put  it  in  the  proper  sheaves  on  the  boom 
and  attach  to  cable  clamps  on  bucket  as  shown  by 
blue  print  accompanying  mixer. 

On  the  14E  the  cable  must  be  re-reaved  when 
assembled  on  the  job,  as  the  idler  sheave  is  removed 
before  mixer  leaves  the  plant.  To  reave  cable 
properly,  stretch  it  on  the  ground  in  line  with 
boom;  take  end  nearest  to  mixer,  lead  it  over  top 
of  idler  or  tension  sheave  on  operator's  side,  bring 
it  down  in  back  of  main  winding  grooved  sheave 
and  then  up  again  to  idler  sheave.  Repeat  this  op- 
eration until  only  two  empty  grooves  remain  on 
idler  sheave,  then  skip  a  groove  and  bring  it  down 
in  front  of  main  winding  sheave,  then  in  front  of 
rear  upper  sheave  on  boom,  and  over  top  of  lower 
sheave.  Then,  take  cable  under  boom  and  stop  at 
bucket,  which  should  be  placed  in  center  of  boom. 
The  other  end  of  the  cable  is  taken  under  the  front 
sheave  on  top  of  boom,  through  the  boom  hoist 
bracket,  over  sheave  on  front  end  of  boom,  thence 
back  to  bucket.  The  ends  are  then  taken  around 
the  shuttle  and  clamped  in  place.  Be  sure  that  cable 
is  started  in  top  center  groove  of  shuttle  and  carried 
under  the  full  length  of  shuttle  before  clamping. 

Slack  in  bucket  cable  on  the  10E  and  14E  is  dis- 
posed of  by  taking  up  nuts  on  the  idler  or  tension 
sheave  hangers,  and  on  the  21E  and  32E  by  adjust- 
ing sheave  on  the  end  boom. 

Boom  Erection  and  Adjusting  Instructions 

Erect  boom  and  place  pin  (1)  in  position.  Then 
fasten  support  cable  to  support  (2)  and  thread  as 
per  diagram  and  fasten  other  end  at  (3).  Next  slip 
assembled  bucket  and  carriage  on  boom  and  bolt 
stop  blocks  (4)  in  position. 

119 


Boom  Details 


SHUTTUE., 


Figure  1 


Boom  Details 


Figure 


161 


Thread  boom  cable  as  follows: 

Place  end  of  long  cable  in  winding  drum  (5)  at 
hole  (A).  Bend  cable  and  clamp  securely.  Turn 
winding  drum  (5)  until  half  the  grooves  are  filled. 
Place  end  of  short  cable  in  hole  (8)  and  lace  other 
half  of  drum.  Thread  as  shown  in  diagram,  BEING 
SURE  ENDS  MEET  IN  CENTER  OF  BOOM 
on  under  side  of  channels.  Place  ends  in  shuttle, 
as  shown  in  detail,  and  clamp.  Slip  shuttle  into 
carriage  and  bolt  stop  blocks  (19)  in  position.  To 
tighten  cable  adjust  bolt  (6). 

Adjust  boom  as  follows : 

See  that  both  clutches  (7)  and  (8)  are  in  neutral 
position.  When  in  this  position  links  (17)  should 
be  in  line.  Adjustment  may  be  made  at  (9)  and 
operating  lever  should  be  in  neutral  position  in 
plate  (10).  Brake  should  then  be  set  by  adjusting 
bolt  (18).  Run  bucket  in,  and  if  carriage  hits 
bumper  (11)  adjust  nuts  (12).  Run  bucket  out  and 
if  carriage  hits  stop  blocks  (4)  adjust  turnbuckle 
(14).  Carriage  should  never  be  allowed  to  strike 
blocks  (4)  but  to  come  as  close  as  possible. 

The  door  of  bucket  can  be  adjusted  to  suit  con- 
sistency of  concrete  and  thickness  of  pavement  to  be 
laid.  To  obtain  proper  opening,  adjust  angle  (15). 
If  door  does  not  close  properly  draw  up  on  bolts  (16). 

Assembling  of  Construction  Mixers 

The  same  methods  used  in  unloading  the  Paving 
Mixer  should  be  used  for  a  Construction  Mixer,  and 
the  same  principles  apply  to  the  hoisting  cables  for 
the  skip;  but,  instead  of  loading  the  charging  skip 
on  a  truck,  the  skip  should  be  taken  down  off  the 
car  and  rolled  into  place  at  the  side  of  the  Mixer 
where,  raised  on  planks,  it  could  be  readily  slid  up 
to  place  by  means  of  bars. 

Preparing  to  Start  Mixer 

After  mixer  is  assembled,  see  that  all  grease  and 
oil  cups  are  full,  using  a  good  grade  of  oil  and  No.  3 
cup  grease.  Grease  cups  should  be  screwed  down  at 
least  twice  a  day,  to  keep  all  the  bearings  well  lu- 

162 


bricated.  Be  sure  to  keep  all  cables  lubricated  with 
good  cable  compound,  and  all  gear  teeth  well  lubri- 
cated with  a  good  graphite  grease,  but  DO  NOT 
put  grease  on  rollers  or  drum  runway.  The  cable 
clamps  should  all  be  gone  over  to  make  sure  all  nuts 
are  tight,  as  a  loose  clamp  may  cause  trouble. 

Before  starting  the  engine,  be  sure  that  all 
clutches  are  disengaged ;  by  so  doing  a  bad  accident 
may  be  avoided. 

Starting  and  Care  of  Boiler 

After  mixer  is  assembled,  a  slow  fire  should  be 
started  in  the  boiler.  Do  not  crowd  the  fire  until 
steam  pressure  shows  on  the  gauge,  indicating  that 
sufficient  steam  has  been  generated  to  protect  the 
top  ends  of  the  tubes;  which,  in  full  length  tube 
boilers  are  exposed  to  the  hot  gases.  Hard  firing 
in  getting  up  steam  is  almost  certain  to  damage  the 
top  ends  of  the  tubes.  This  not  only  applies  to  fir- 
ing the  boiler  the  first  time,  but  holds  good  for 
every  time  a  new  fire  is  made. 

During  the  first  day's  operation,  do  not  keep  the 
water  level  in  the  boiler  above  the  middle  of  the 
gauge  glass,  as  the  water  will,  undoubtedly,  foam  on 
account  of  the  oil  and  grease  on  the  plates.  Blow 
down  the  water  glass  several  times  a  day  but  never 
depend  on  it,  as  the  opening  may  become  choked, 
keeping  the  water  level  apparently  constant,  while 
the  water  in  the  boiler  may  actually  be  getting  very 
low.  The  water  cocks  are  put  in  the  boiler  to  use,  and 
are  the  only  sure  way  of  ascertaining  the  water  level. 

The  boiler  should  be  blown  off  well  at  the  end  of 
the  day  to  remove  all  grease.  After  this,  sufficient 
water  should  be  carried  in  the  boiler  to  show  %  °f 
the  way  up  on  the  gauge  glass. 

Keep  a  thin  clean  fire.  This  will  give  you  100% 
more  heat  than  a  thick  dirty  fire,  as  the  smoke  from 
a  thick  fire  chokes  up  the  tubes,  and  combustion 
takes  place  not  in  the  tubes  but  in  the  hood  and 
stack.  Clinkers  should  be  removed  from  the  fire 
box  frequently  and  the  ash  box  should  be  kept 
clean.  Doing  so  prolongs  the  life  of  the  grates  and 
gives  a  better  draft. 

163 


If  at  any  time  the  boiler  is  to  remain  out  of  use 
for  a  few  days,  place  a  cover  over  the  smoke  stack 
to  prevent  water  rusting  out  the  tubes. 

There  will  probably  be  injector  trouble  the  first 
day,  due  to  clogging  from  scales  from  new  pipes 
and  boiler.  In  such  an  event,  take  injector  apart 
and  clean  thoroughly. 

The  boiler  tubes  should  be  kept  clean,  as  the  soot 
collected  on  them  is  a  nonconductor  of  heat  and 
more  fuel  is  required  in  order  to  keep  up  steam.  As 
often  as  is  necessary,  the  tubes  should  be  cleaned 
with  a  scraper — the  frequency  will  depend  entirely 
upon  the  fuel  used  and  the  carefulness  exercised  in 
firing ;  but  they  should  be  cleaned  in  the  morning,  at 
least,  before  firing  up,  and  during  the  day  they  should 
be  blown  out  every  once  in  a  while  with  steam. 

Practically  all  feed  waters  contain  more  or  less 
scale  forming  substances  which  precipitate  and  form 
incrustations  in  the  water  leg,  on  the  flue  sheet  and 
around  the  lower  end  of  the  tubes. 

Frequently  the  contractor  has  to  make  use  of 
muddy  water,  and  this  also  collects  in  the  water  leg 
and  on  the  lower  flue  sheet.  This  scale  and  mud,  if 
not  removed  by  frequent  cleansing,  will  become 
firmly  baked  on  the  heating  surfaces,  retarding  the 
flow  of  the  heat  to  the  water  and  weakening  the  iron 
from  stresses  due  to  unequal  expansion.  An  accum- 
ulation of  scale  1/32"  thick  requires  10%  more  fuel; 
1/16"  of  scale  requires  20%  more;  y&"  of  scale  re- 
quires 30%  more;  and  %"  requires  60%  more.  By 
keeping  boilers  clean,  considerable  fuel  is  saved. 

Under  usual  conditions  the  boiler  should  be 
blown  off  a  little  every  day.  It  is  a  good  plan,  be- 
fore stopping  after  a  day's  run,  to  pump  in  more 
water  than  required  while  running.  The  next  morn- 
ing after  firing  is  started  and  some  ten  to  thirty 
pounds  pressure  has  been  raised,  open  the  blow-off 
valve  and  blow  the  water  down  to  the  proper  level. 
If  the  water  is  very  muddy,  it  is  a  good  plan  to  re- 
peat this  at  the  noon  hour.  After  the  boiler  has  been 
run  for  some  length  of  time  the  boiler  should  be 
blown  down  entirely  and  thoroughly  washed.  This 

134 


should  be  done  at  least  once  a  week,  and  in  case 
of  muddy  water,  it  could  be  done  to  advantage 
twice  a  week. 

The  boiler  should  not  be  blown  down  for  wash- 
ing while  under  steam  pressure.  The  best  time  to 
do  it  is  when  the  steam  pressure  has  just  gone  down, 
but  the  water  is  still  hot.  Open  the  blow-off  valve, 
let  all  the  water  run  out,  remove  the  handhole 
plates  and  wash  out  the  boiler  with  a  hose.  To 
properly  do  this,  it  is  necessary  that  the  water  be 
under  pressure  and  that  a  properly  shaped  nozzle  is 
used.  A  good  nozzle  can  be  made  of  %"  or  %"  pipe 
having  a  short  bend  at  the  end  so  as  to  throw  the 
stream  of  water  at  right  angles  to  its  length  and  at 
high  velocity.  If  y2"  pipe  is  used,  the  opening  at 
the  end  of  the  pipe  should  be  drawn  down  a  little 
on  a  taper  so  as  to  give  about  a  %"  opening. 

The  boiler  should  also  be  scraped  with  a  scraper 
consisting  of  an  elliptically  shaped  piece  of  iron, 
which  would  fit  the  side  of  the  boiler,  and  fastened 
to  a  rod  for  handle.  A  very  good  cleaner  can  also 
be  improvised  from  a  heavy  wire  with  a  piece  of 
chain  secured  to  the  end  of  it. 

If  the  feed  water  contains  ingredients  such  as  to 
form  a  hard  scale,  impossible  to  remove  by  wash- 
ing, a  boiler  compound  may  be  used  to  advantage 
so  as  to  reduce  the  scale  to  a  muddy  consistency 
that  can  be  washed  out. 

The  best  water  obtainable  should  always  be  used 
for  the  boiler.  Where  necessary  to  take  it  from  a 
road  side  sump,  it  is  well  to  make  two  sumps  and 
use  one  as  a  settling  basin;  or  barrels  may  be  filled 
and  water  drawn  from  them  after  the  sediment  has* 
settled  to  the  bottom. 

Starting  and  Care  of  Steam  Engine 

After  all  grease  and  oil  cups  and  lubricator  are 
filled,  see  that  they  are  feeding  properly.  The  oil 
cup  on  the  connecting  rod  when  full  should  last  five 
hours;  the  lubricator  should  be  adjusted  to  feed  six 
drops  per  minute.  The  engine  being  oiled  and 
enough  steam  in  the  boiler,  see  that  throttle  valve  is 

165 


closed  and  drain  cocks  in  cylinder  and  steam  chest 
are  open.  Open  valve  in  steam  line  near  boiler, 
and  the  throttle  valve  just  enough  to  blow  out  the 
water  in  steam  line,  steam  chest  and  cylinder.  After 
allowing  the  steam  to  pass  through  a  few  minutes, 
turn  fly  wheel  off  dead  center,  open  throttle  slowly 
until  the  engine  starts  running;  then  close  drain 
cocks  and  open  throttle  valve  wide.  To  avoid 
blowing  out  of  gaskets,  the  nuts  on  the  studs,  hold- 
ing cylinder  head  and  steam  chest  cover  in  place, 
should  be  tested  and  tightened  up,  if  necessary. 

When  starting  an  engine  in  cold  weather,  lim- 
ber it  up  by  letting  it  run  idle  a  little  while  before 
placing  any  load  upon  it.  When  engine  is  started 
run  it  slowly,  having  all  cocks  open.  Many  cylin- 
ders are  cracked  by  a  sudden  change  in  temperature. 

In  cold  freezing  weather,  drain  all  water  and  oil 
from  the  cylinder  and  lubricator  when  engine  is 
shut  down  for  the  night. 

Gasoline  Engine 

For  adjusting  Fuller  &  Johnson  Engine  see  their 
instruction  book. 
To  Start  and  Run  Fuller  &  Johnson  Engine 

1.  Tighten  the  grease  cups  on  main  bearings 
and  connecting  rod  and  set  feed  on  cylinder  oil 
cup.    Oil  small  parts  with  squirt  can. 

2.  Fill  jacket  and  water  cooling  tank  with  clean 
water.     In  the  winter  time  the    water    should    be 
warm  to  assist  the  engine  in  starting  readily. 

3.  Fill  the  starting  reservoir  with  gasoline  and 
open  the  gasoline  throttle  to  the  starting  mark  (S). 

4.  Close  the  starting  damper.  (Handles  in  hori- 
zontal position  as  shown  in  Fig.  2). 

5.  Close  switch  on  battery.  (If  battery  ignition). 

6.  Prime  the  cylinder  through  the  priming  cup. 
Put  in  one-half  to  one  priming  cup  full  if  the  engine 
is  cold.     The  hotter  the  engine  the  less  gasoline 
required. 

7.  Attach  the  starting  crank  on  the  governor 
side  and  give  the  engine  a  few  quick  turns.  As  soon 
as  the  engine  starts,  open  the  starting  damper  and 
adjust  the  gasoline  throttle  to  the  running  mark  (R). 

166 


167 


Care  of  and  Starting  Waukesha  Motor 

See  that  fuel  tank  is  full. 

Inspect  the  spark  plugs  to  see  that  none  is 
cracked  or  loose. 

Test  them  for  sparking.  If  you  aren't  getting 
a  good  spark  at  every  plug,  look  for  carbon  on  the 
plugs,  or  trouble  with  the  ignition. 

Look  at  your  oil  glass  to  see  that  your  motor 
won't  run  dry. 

Be  sure  that  the  cooling  system  is  not  short  of 
water.  An  overheated  motor  will  never  give  the 
good  results  that  a  perfectly  cooled  one  will.  Be- 
sides, if  you  are  going  where  water  is  not  right  at 
hand,  it  may  take  you  half  an  hour  or  so  to  get  the 
water  you  need. 

In  other  words,  look  your  motor  over  from  stem 
to  stern  before  you  start,  so  that  you  can  correct 
any  troubles  in  the  easiest  and  quickest  manner. 

A  motor  that  has  good  ignition,  is  well-oiled  and 
well-fueled  seldom  gives  any  trouble — but  neglect 
any  one  of  these  features,  and  troubles  arise. 

You  can  save  yourself  a  lot  of  time,  trouble,  and 
expense-^to  say  nothing  of  adding  years  to  the  life 
of  your  motor — by  careful  inspection  of  all  parts 
before  you  start. 

Owing  to  the  presence  of  kerosene  in  some  fuel, 
which  is  destructive  to  the  motors  if  not  properly 
vaporized,  we  advise  that  the  following  should  be 
given  every  attention. 

1.  At  all  times  be  sure  of  a  good  adjustment  on 
the  carburetor.     In  ninety  cases  out  of  a  hundred 
the  carburetors  feed  too  much  fuel. 

2.  See  that  the  air  intake  of  the  carburetor  re- 
ceives hot  air  from  the  exhaust,  as  it  is  most  im- 
portant that  the  carburetor  bowls  remain  heated  to 
assist  in  vaporizing  the  kerosene. 

3.  Although  spark  plugs    cause    little    trouble 
these  days,  they  should  be  removed  at  least  once  a 
week  and  have  all  the  points  uniformly  adjusted  no 
further  apart  than  1/32"  of  an  inch.    Guard  the  ig- 
nition wires;  nothing  tends  to  reduce  the  efficiency 

168 


of  the  motor  more  than  poor  ignition  and  carbure- 
tion.     Make  every  spark  do  its  work. 

4.  Do  not  overload  the  crank  case  with  oil.  Add 
oil  several  times  a  day  and  in  this  way  retain  a  cer- 
tain level  at  all  times.     Oil  magneto  once  a  week, 
putting  about  two  drops  of  sperm  oil  in  each  oil  hole 
with  a  match.    Too  much  oil  is  as  bad  as  not  enough. 

5.  Drain  the  oil  from  the  crank  case  at  least 
once  a  week  if  using  high  test  gasoline,  or  every 
third  day  when  using  the  ordinary  grade  of  gaso- 
line.   In  doing  this  be  sure  to  remove  the  four  plugs 
under  each  connecting  rod  oil  pocket  as  well  as  the 
large  plug  to  the  oil  reservoir. 

6.  Keep  the  motor  at  its  proper  speed.     Insist 
on  having  a  seal  placed  on  your  governor,  and  never 
attempt    to    break    it:    it  is  one  protection  against 
motor  troubles. 

7.  Watch  the  adjustment  of  push  rods.     Keep 
the  valve  seats  in  good  condition.    Any  one  cylin- 
der working  improperly  will  cause  no  end  of  trou- 
ble in  a  short  time. 

8.  Cut  down  the  idling  of  the  motor,  as  doing 
this  will  reduce  the  dilution  of  the  oil  in  the  crank 
case,  and  the  carbonizing  of  combustion  chambers 
by  at  least  40%. 

After  the  motor  has  been  examined  to  see  that 
the  plugs  are  clean  and  that  it  has  plenty  of  gaso- 
line and  oil,  retard  spark  on  magneto;  throw  out 
grounding  switch;  prime  engine  through  the  four 
priming  cups,  putting  about  two  priming  cups  full 
of  gasoline  in  each  cylinder.  Then  the  engine  is 
ready  to  crank.  When  engine  is  running,  advance 
spark.  Before  beginning  to  mix,  see  that  there  is 
proper  water  circulation  by  raising  the  return  pipe 
in  cooling  tank. 

To  Get  Out  of  Trouble 

No  matter  whether  you  have  a  Fuller  &  Johnson 
engine,  a  Waukesha  engine,  or  some  other  make, 
when  trouble  arises,  consult  the  following  TROU- 
BLE CHART  (reprinted  by  the  courtesy  of  Stan- 
ton  &  Van  Vliet  Company,  Chicago,  Illinois,  pub- 

169 


lishers  of  'Gas  Engine  Troubles  and  How  To  Rem- 
edy Them'  by  J.  B.  Rathbun).  Follow  down  the 
column  under  the  head  of  SYMPTOMS  until  the 
description  tallies  with  the  actions  of  your  engine. 

Engine  Will  not  Turn  Over — Engine  Stuck 

1.  Hot  bearing  or  bearings  seized. 

2.  Stuck  piston  due  to  overheated  cylinder. 

3.  Water  frozen  to  piston  and  cylinder  (leaks). 

4.  Bolts  rubbing  on  base  or  oil  shields. 

5.  Friction  clutch  holding  load  on  engine. 

6.  Broken  gears  wedging. 

7.  Water  in  cylinder  due  to  leak  in  jacket. 

8.  Obstacle  blocking  wheels  or  gears. 

9.  Broken  crank-shaft. 

10.    Dry  bearings  or  rusted  piston. 

Starting  Troubles 

1.  Fuel    valve    closed    at    tank  (see  that  fuel 
reaches  engine). 

2.  No  gasoline  in  tank. 

3.  Battery  or  magneto  switch  open. 

4.  Broken  or  disconnected  battery  or  magneto 
wire. 

5.  Dirty  electrodes  on  make  and  break  ignition 
system. 

6.  Broken  igniter  spring  on  make  and  break  ig- 
nition system. 

7.  Weak  batteries  on  either  low  or  high  tension 
system. 

8.  Magneto  not  generating    on    either    low    or 
high  tension  system. 

9.  Foul  spark  plug,  high  tension  system. 

10.  Short  circuit  in  wires  or  connection. 

11.  Defective  spark  coil  on  high  tension  system. 

12.  Defective  timer. 

13.  Storage  batteries. 

14.  No  compression,  indicated  by  engine  turning 
easily  over  center. 

15.  Carburetor  trouble  due  to  poor  mixture. 

16.  Cold  weather  carburetor  troubles. 

17.  High  altitude. 

170 


18.  Air  leaks  in  cylinder  between  carburetor  and 
cylinder. 

19.  Vibrator  on  high  tension  spark  coil  may  be 
out  of  action. 

No  Power — Loss  of  Power 

1.  Fuel  valve  partly  closed,  may  jar  shut. 

2.  Air  damper  closed  in  air  intake  pipe;  always 
open  the  damper  immediately  after  starting. 

3.  Compression    relief    cam    may    be    left    in 
"starting"  position.    It  should  always  be  turned  to 
"run"  as  soon  as  engine  is  up  to  speed. 

4.  Throttle  left  in  "starting"  position. 

5.  Retarded   spark  will   reduce   power   output; 
always  advance  it  to  the  proper  point  as  soon  as 
engine  is  up  to  speed. 

6.  Advanced  spark,  when  excessive,  will  cause 
a  loss  of  power,  which   will  be   accompanied  by 
heavy  pounding. 

7.  Weak  batteries  reduce  the  spark  and  power. 

8.  Vibrator  adjustment  may  be  poor  on  high 
tension  spark  coil. 

9.  Foul  igniters  on  make  and  break  system. 

10.  Foul   spark   plugs   are   a  frequent   cause   of 
power  loss,  especially  with  high  compression. 

11.  Defective  timer  will  cause  power  loss. 

12.  Misfiring  is  always  accompanied  by  a  loss 
of  power. 

13.  Clogged  muffler  filled  with  soot,  or  a  clogged 
exhaust  pipe  will  cause  power  loss. 

14.  Long  exhaust  pipes   or   exhaust   pipes   with 
many  short  bends  will  reduce  power. 

15.  Magneto  trouble  will  reduce  the  spark. 

16.  Lack  of  oil,  especially  in  the  cylinder  will 
cause  compression  leakage  and  power  loss. 

17.  Hot    bearings    will    cause  the  effects  of  an 
overload  and  reduce  the  output. 

18.  Carburetor    troubles    are    a    very    frequent 
cause  of  power  loss.     "See  Loss  of  Power." 

19.  Compression  leakage  is  a  very  common  and 
persistent  cause  of  power  loss.    Test  for  compres- 
sion by  turning  engine  over  "center"  on  compres- 

171 


sion  stroke:  if  it  passes  over  easily  leakage  exists, 
and  must  be  stopped  to  prevent  power  loss  and 
waste  of  fuel. 

20.  Cold  jacket  water  will  reduce  power;  have  it 
leave  jacket  at  160  degrees  F.  on  gasoline  engines, 
and  200  degrees  F.  with  kerosene  engines. 

21.  Valve  out  of  time  will  cause  power  loss. 

22.  Warm  intake  air  will  reduce  mixture  in  cyl- 
inder. 

23.  High  altitudes  will  reduce  output  of  engine. 

24.  Worm  cams,  rollers  and  timing  gears  change 
timing. 

25.  Valve  opening  too  small  causes  back  pressure. 

26.  Spring  too  stiff  on  automatic  intake  valve. 

27.  Magneto  out  of  time. 

28.  Valves  stuck  in  guides. 

29.  Valve  gear  worn. 

Misfiring 

1.  Loose  wires  or  dirty  connections. 

2.  Swinging  ground  caused  by  poor  insulation. 

3.  Broken  wire. 

4.  Weak  or  exhausted  batteries. 

5.  Poorly  adjusted  vibrator    on    high    tension 
system. 

6.  Foul  spark  plugs  on  high  tension  system. 

7.  Dirty  electrodes  on  make  and  break  system. 

8.  Moisture  may  cause  short  circuits. 

9.  Magnetos  may  cause  misfiring. 

10.  Power  loss  is  generally  accompanied  by  mis- 
firing. 

11.  Defective  or  short  circuited  spark  coil. 

12.  Defective  timer  on  high  tension  system. 

13.  Batteries  may  be  weak. 

14.  Water  in  gasoline. 

15.  Valve  gear  worn. 

16.  Leaking  exhaust  valves  are  a  common  cause. 

17.  Poor  mixture  or  poor  carburetor  adjustment. 

18.  Air  leaks  between  carburetor  and  cylinder. 

19.  Valves  out  of  time. 

20.  Leaking  automatic  intake  valves. 

21.  Compression  leaks. 

172 


22.  Empty  fuel  tank. 

23.  Spark  gap  too  large  in  spark  plug. 

Misfiring  in  One  Cylinder 

1.  One  cylinder  may  have  a  heavier  carbon  de- 
posit. 

2.  One  cylinder  may  have  an  air  leak. 

3.  One  cylinder  out  of  time. 

4.  By  timer  having  poor  contact. 

5.  Loose  wire  leading  to  misfiring  cylinder. 

6.  Sooted  plug. 

7.  Magneto  distributor  foul  with  dust. 
18.  One  vibrator  stuck. 

Sudden  Stop 

1.  Ignition  switch  jarred  open. 

2.  Fuel  exhausted  in  tank. 

3.  Broken  wire. 

4.  Loose  connections  or  wires. 

5.  Carburetor  nozzle  clogged  with  dirt. 

6.  Fuel  pipe  clogged  leading  to  carburetor. 

7.  Timer  broken. 

8.  Defective  magneto. 

9.  Hot  bearings  seize  the  shaft. 

10.  Defective  igniter. 

11.  Water  in  gasoline. 

12.  Hot  cylinder — Piston  seized. 

13.  No  oil. 

14.  Poor  mixture. 

Back-Firing 

1.  Poor  mixture  due  to  carburetor  adjustment. 

2.  Retarded  spark  will  cause  back-fire. 

3.  Clogged  carburetor  nozzle  or  fuel  pipe. 

4.  Leaky  inlet  valve  on  engine. 

5.  Air  leaks  in  cylinder,  or  intake  pipe. 

6.  Wide  open  throttle  at  full  load. 

7  On  low  speed  may  be  caused  by  opening  of 
the  auxiliary  air  valve  on  the  carburetor. 

8.  Valves  out  of  time. 

9.  Defective  timer  on  high  tension  system. 
10.  Weak  batteries. 

173 


Irregular  Running 

1.  Broken  wire. 

2.  Dirty  timer. 

3.  Sticking  coil  vibrator,  high  tension  system. 

4.  Worn    make    and    break    mechanism    (loose 
joints). 

5.  Loose  timer  control  rods. 

6.  Water  in  gasoline. 

7.  Clogged  carburetor  nozzle. 

8.  Weak  exhaust  valve  spring  (broken  springs). 

9.  Air  leaks  between  carburetor  and  jcylinder. 
10.    Worn  cams  or  cam  shaft  on  multi- cylinder 

engine  as  well  as  a  twisted  shaft  or  loose  gears. 

Overheating  in  Cylinder 

1.  Retarded  spark. 

2.  Mixture  too  rich. 

3.  Lack  of  oil  in  the  cylinder. 

4.  Poor  water  circulation  due  to  the  jacket. 

5.  Poor  compression. 

6.  Insufficient  valve  lift. 
7  Clogged  exhaust  pipe. 

8.  Clogged  muffler. 

9.  Clogged  radiator. 

10.  Defective  circulating  pump. 

11.  Tight  piston. 

12.  Lime  deposits  in  cylinder. 

13.  Overload  on  engine. 

14.  Closed  water  supply  valve. 

Pre-Ignition  or  Deep  Pounding  in  Cylinder 

1.  Too  much  lubricating  oil  forms  deposit. 

2.  Rich  mixture  forms  a  deposit  in  combustion 
chamber. 

3.  Overheated  cylinder,  especially  in  air  cooled 
engines. 

4.  Sharp  edges  in  combustion  chamber. 

5.  Deposit  in  cylinder. 

6.  Deposits    in    kerosene    engines    are    usually 
formed  by  running  with  a  cold  cylinder  or  by  hav- 
ing the  intake  air  too  cold. 

174 


Smoke 

1.  Black  smoke  is  caused  by  too  much  gasoline, 
or  too  rich  a  mixture. 

2.  Light  colored  smoke  is  caused  by  an  excess 
of  oil  fed  to  the  cylinder. 

Engine  Gradually  Slows  Down  and  Stops 

1.  Weak  or  exhausted  batteries. 

2.  Poor  mixture  due  to  carburetor  adjustment. 

3.  Overload  on  engine. 

4.  Magneto  slipping  or  governor  out  of  order. 

5.  Overheated  bearings. 

Excessive  Vibration 

1.  Engine    crankshaft    may    not    be    perfectly 
balanced. 

2.  Twisted  cam  shaft  may  change  valve  timing 
and  cause  an  uneven  application  of  power. 

3.  Uneven  wear  on  cams  or  push  rods  may  give 
an  uneven  application  of  power. 

4.  Defective  timer  may  fire  the  cylinders  at  un- 
equal periods. 

5.  Carburetor  not  situated  at  equal   distances 
from  the  cylinders  may  be  the  cause  of  vibration. 

Cam  Shaft  Rattle 

1.  Caused  by  retarded  spark. 

2.  Loose  cam  shaft  bearings  or  gears. 

3.  Loose  cam  rollers  or  pins. 

Wheezing  Scraping  Sound 

1.  Broken  piston  rings. 

2.  Dry  piston  due  to  lack  of  oil. 

3.  Vibration  of  auxiliary  air  valve  on  carburetor. 

4.  Tight  piston. 

5.  Overheated  cylinder. 

6.  Fly  wheel  scraping  on  metal  shields. 

Knocking  and  Pounding — Regular 

1.  Ignition  too  far  advanced. 

2.  Pre-ignition. 

3.  Overheated  cylinders. 

4.  Loose  bearings. 

175 


5.  Loose  connecting  rod  bearings. 

6.  Loose  fly  wheel. 

7.  Loose  counterweights. 

8.  End  play  in  crank  shaft. 

9.  Broken  valve  stem. 

10.  Broken  circulating  pump. 

11.  Wear  on  cam  shaft  and  cams. 

Irregular  Knock 

1.  Loose  electrical  connections. 

2.  Loose  piping  or  rod  on  engine. 

3.  Pre-ignition. 

4.  Defective  commutator  or  timer. 

Speed  Variation 

1.  Due  to  misfiring. 

2.  Water  in  fuel. 

3.  Irregular  supply  of  gas. 

4.  Magneto  slipping. 

5.  Defective  fuel  pump. 

6.  Defective  governor. 

7.  Wear  on  valve  gear. 

8.  Defective  timer. 

9.  Loose  electrical  connections. 
10.  Poor  mixture. 

Adjustment  of  Friction  Clutches 


Unnecessary  slipping  of  the  friction  clutch,  caus- 
ing undue  wear  on  the  friction  blocks  E  should  be 
remedied  at  once  by  making  adjustments  in  the 
following  manner: 

1.  Loosen  lock-nut  A  on  set  screw  B. 

2.  Loosen  set  screw  B. 

3.  Strike  set  screw  B  lightly  with  a  hammer  to 
loosen  copper  disc  C  which  has  been  forced  into 
threads  of  master  disc  65. 

4.  Turn  adjusting  ring   63   to  the  right  about 
one-quarter  of  a  turn  to  adjust  for  ordinary  wear 
on  blocks  E.     Try  the  clutch  by  pushing  in  spool 
70  with  lever  or  hand  wheel.    If  the  clutch  should 
be  too  tight,  i.  e.  does  not  lock,  turn  adjusting  ring 
63  to  the  left  slightly. 

5.  When    proper    adjustment    has    been    made 
TIGHTEN    SET    SCREW    B,  making   sure    that 
copper  disc  C  is  in  place  first,   and  then  tighten 
lock-nut  A. 

CAUTION:  Be  sure  that  the  fifth  instruction 
has  been  complied  with  before  operating  the  ma- 
chine. 


*ste 

TO 

rj  '   !/Q 

r 

H 

P« 

"h 

^ozj- 

jjfS 

/7^^7\ 

rr^-.-J.tr{_^>, 
A       ^^ 

V-~;-^i  

"-1" 

^^T^A\ 
LOCATING, 
gWftf  HEK*E  Ji 

j 

J  H  r^j 

— 

•3TRIKE.  MHf?£ 

t—  "  !;  i  r- 

a 

Figure  4 

Removing  Clutches 

When  for  any  reason  it  becomes  necessary  to 
remove  a  clutch,  where  it  is  impractical  to  remove 
the  housing  H  first,  proceed  as  follows : 

1.  Loosen  lock-nut  A  on  set  screw  B. 

2.  Loosen  set  screw  B. 

177 


Figure  5 
Main  Shaft  and  Clutch  Assembly  14E  Paver 


178 


Figure  5 
Main  Shaft  and  Clutch  Assembly  14E  Paver. 


179 


3.  Strike  set  screw  B  lightly  with  a  hammer  to 
loosen  copper  disc  C,  which  has  been  forced  into 
threads  of  master  disc  65. 

4.  Unscrew  adjusting  ring  63  and  remove  same, 
together  with  toggle  links  71,  toggle  yokes  72  and 
spool  70. 

5.  Remove  from  plate  60  and  friction  plate  74. 

6.  Remove    pins    F    from    adjusting    ring    and 
toggle  links  and  replace  adjusting  ring  63  on  master 
disc  65,  as  shown  in  Fig.  4. 

7.  Scratch  a  locating  mark  on  shaft  at  edge  of 
master  disc  65  to  insure  proper  replacement  of  disc. 

8.  Insert  two  or  three  bolts  (three  if  you  have 
a  three-link  adjusting  ring)  in  the  slots  of  the  ad- 
justing ring  63  and  through  a  plate  placed  over  the 
end  of  the  shaft  as  shown  in  Fig.  4. 

9.  Be  sure  that  pins  D  in  housing  H  are  in  line 
with  slots  S  in  master  disc  65. 

10.  Draw  up  nuts  on  bolts  and  strike  occasional- 
ly with  a  hammer  on  plate  as  indicated  in  Fig.  4  in 
order  to  start  the  disc  65. 

11.  In  cases  where  the  housing  can  be  removed 
first,  the  master  disc  65  can  be  driven  off. 

12.  When  replacing  clutch  parts,  locate  master 
disc  65  by  mark  previously  scratched  on  shaft,  see 
that  it  is  keyed  tight  and  be  sure  that  set-screw  B 
is  tightened  before  operating  the  machine. 

Toggle  links  71,  toggle  yokes  72  and  pins  F, 
and  J  should  be  replaced  by  new  ones  when  they 
become  worn  to  such  extent  as  to  cause  improper 
operation  of  the  clutch. 

Adjustment  of  Hoist  Brake 

On  all  Koehring  Mixers,  the  basic  principle  of 
adjustment  is  to  first  adjust  the  clutch,  and  then 
adjust  the  brake  to  suit.  While  the  design  of  levers 
is  somewhat  different  on  the  various  mixers,  the 
following  general  method  of  adjustment  of  the 
brake  on  the  14E  and  21 E  Pavers  applies  to  all  the 
machines.  For  reference  see  Figure  5. 

In  case  set  screws  (7)  and  (8)  have  been  dis- 
turbed, after  mixer  has  left  the  factory,  to  adjust 

180 


properly — Pull  lever  (6)  down  and  loosen  nuts  (14) 
and  (15). 

Adjust  set  screws  (7)  and  (8)  so  that  centers  of 
(9),  (10)  and  (11)  are  approximately  in  line  when 
clutch  (18)  is  engaged.  Release  clutch  (18)  with 
lever  (1)  and  move  back  to  extreme  limit.  Tighten 
nut  (14)  until  tension  pulls  clutch  (18)  forward 
*4 ",  then  tighten  nut  (15). 

Readjust  lever  (6)  by  adjusting  nut  (13)  until 
lever  (6)  locks  brake  band,  then  tighten  nut  (12). 

After  the  brake  is  adjusted,  adjust  the  knockout 
at  (16)  or  (17). 

Lever  ^Operation 
General : — 

While  the  lever  arrangement  is  somewhat  differ- 
ent on  the  various  mixers,  the  same  operating  prin- 
ciples apply  to  all  machines,  whether  they  be 
Pavers,  Heavy  Duty  Mixers  or  Dandie  Mixers. 

As,  on  account  of  the  propelling  features,  the 
lever  arrangement  is  somewhat  more  complex  on 
the  pavers,  it  is  described  in  detail: 

10E  Paver 

Refer  to  Figure  6  page  182  for  reference. 

When  starting  mixer  disengage  gasoline  engine 
clutch  (not  shown)  or  stop  steam  engine.  Then 
disengage  traction  clutch  with  lever  (1) ;  shifting 
lever  (2)  must  be  in  neutral  position.  Next,  engage 
drum  drive  gear  with  lever  (4)  and  engage  gasoline 
engine  clutch  (not  shown)  or  start  steam  engine. 

To  hoist  charging  skip,  engage  hoisting  clutch 
with  lever  (6). 

To  stop  hoisting  of  skip,  disengage  clutch  with 
lever  (6)  and  apply  brake  lever  (7). 

If,  however,  the  skip  is  raised  to  charging 
height,  it  will  be  stopped  automatically  providing 
the  adjusting  screw  is  set  properly  in  the  knockout. 

To  lower  bucket,  release  brake  lever  slightly. 

To  move  mixer,  hoist  and  lock  charging  skip 
clear  of  the  ground,  then : 

(a)  For  low  Speed  Ahead — Lever  (2)  must  be 

in  neutral  position. 

181 


® 


11 


Disengage     traction     clutch     with     lever     (1). 
Next,  shift  lever  (3)  to  left  hand  notch.     Then, 
engage  clutch  with  lever  (1). 
To  brake,  throw  out  traction  clutch  with  lever 
(1)  and  apply  brake  lever  (5)) 

(b)  For   reverse    traction — Disengage    traction 
clutch  with  lever  (1),  having  lever  (2)  in  neu- 
tral   position.     Then,    shift    lever   (3)   to.  right 
hand  notch  and  engage  clutch  with  lever  (1). 
To  brake,  throw  out  traction  clutch  with  lever 
(1)  and  apply  brake  lever  (5). 

(c)  For  high  speed  ahead — With  gasoline  en- 
gine clutch  disengaged  or  steam  engine  stopped 
and  lever  (3)  in  neutral  position,  engage  trac- 
tion clutch  lever  (1)  and  throw  out  drum  drive 
gear  with  lever  (4).    Then  shift  lever  (2)  from 
left  hand  hole  to  right  hand  hole  and  engage 
gasoline  engine  clutch  or  start  steam  engine. 
To  brake,  make  sure  that  traction  clutch  lever 
(1)  is  engaged.     Then,  throw  out  gasoline  en- 
gine clutch  or  shut  off  steam  and  apply  brake 
lever  (5). 

14E  and  21E  Pavers 

For  reference  see  Figure  7  pages  184  and  185. 

To  hoist  skip,  engage  drum  drive  clutch  with 
lever  (2)  then  engage  hoist  clutch  with  lever  (1). 

To  lower  skip,  disengage  clutch  lever  (1)  half- 
way and  when  skip  nears  ground, apply  brake  with 
lever  (1). 

To  hold  mixer  when  operating  on  a  grade,  ap- 
ply and  lock  brake  lever  (4). 

To,1  hoist  batch  box  with  derrick — Engage 
clutch  (7)  with  lever  (6) ;  raise  batch  box  higji 
enough  to  clear  skip,  next  apply  brake  with  level 
(6)  swing  batch  box  over  skip  and  dump  material. 
After  batch  box  is  empty,  to  lower  box  on  car 
reverse  operation. 

To  operate  power  discharge — Engage  clutch 
(B)  with  lever  (18)  to  discharge.  To  reverse 
swinging  chute,  engage  clutch  (A)  with  lever  (8). 

To  move  mixer,  hoist  skip  to  clear  ground, 
then  lock  with  lever  (13). 

183 


NOT  PUT  pRE*§£  CN  p^v.  R'JN.'.^S 


Figure  7 
Main  Shaft  and  Clutch  Assembly  21E  Paver. 


184 


flj 


TEERiNG  WHEEL 


u 


Figure  7 
Main  Shaft  and  Clutch  Assembly  21E  Paver. 


185 


(a)  For  slow  speed  forward,  be  sure  brake  lever 
(4)  is  disengaged;  disengage  clutch  lever  (3); 
turn  shifting  wheel  (5)  until  L  is  at  arrow,  then 
engage  clutch  with  lever  (3). 

(b)  For  reverse  traction— Be  sure  brake  lever 
(4)  is  disengaged;  disengage  clutch  with  lever 
(3) ;  turn  shifting  wheel  (5)  to  the  left  until  R 
is  at  arrow,  then  engage  clutch  with  lever  (3). 

(c)  For  high  speed  ahead— Be  sure  that  brake 
lever  (4)  is  disengaged;  disengage  clutch  with 
lever  (3) ;  next  disengage    drum    drive    clutch 
with  lever  (2) ;  turn  shifting  wheel'  (5)  to  right 
until  H  is  at  arrow,  then  engage  clutch  with 
lever  (3). 

(d)  To  work  brake  for  all  traction  speeds — dis- 
engage clutch  with  lever  (3)  then  apply  brake 
lever  (4). 

When  mixer  is  to  be  removed  with  teams  or 
tractor  instead  of  its  own  power,  remove  driving 
chains  from  rear  wheels,  disconnect  steering  rod, 
by  removing  cap  from  front  ball  socket,  and  be 
sure  to  wire  the  rod  up  well. 

To  apply  brake  under  the  above  conditions,  pull 
on  brake  lever  near  rear  wheels. 

Instructions  for  Operating  Steering  Mechanism 

on  21E  Paver— With  Full  Length 

Multiplane 

Straight  Ahead 

When  traveling  straight  ahead  leave  steering 
wheel  (A)  in  neutral. 

Slight  Turn 

Turn  wheel  (A)  quickly  in;  desired  direction 
until  you  feel  a  sudden  stop.  After  proper  course 
is  obtained,  quickly  turn  wheel  (A)  back  to  neu- 
tral. 

Sharp  Turn 

Turn  wheel  (A)  quickly  in  desired  direction  un- 
til you  feel  a  sudden  stop.  Continue  to  turn  wheel 
until  no  more  movement  can  be  obtained  and  hold 

186 


firmly  until   proper   course   is   obtained;   then   re- 
verse wheel  back  to  neutral. 

Adjustments  and  Greasing 

If  brake  drum  sticks  apply  a  few  drops  of  oil 
on  lining. 

Grease  cups  (H)  and  (K)  should  be  turned 
down  freely  twice  a  day;  on  a  long  travel  4  to  6 
times  daily. 

If  lever  (B)  goes  over  center  without  setting 
brake  hard  enough,  loosen  nut  (D),  remove  pin 
(L),  adjust  clevis  (E)  until  you  obtain  1/16"  clear- 
ance ibetween  brake  shoe  (G)  and  brake  drum  (F) 
on  both  drums. 

Replace  pin  (L)  and  tighten  nut  (D). 

Loosen  nut  (C),  remove  pins  (M)  and  (N),  ad- 
just! rod  (P).  When  rod  (P)  is  properly  adjusted, 
lever  (B)  must  be  in  neutral  and  1/16  clearance 
maintained  between  each  brake  shoe  and  brake 
drum.  Insert  pins  (M)  and  (N)  and  tighten 
nut  (C). 


187 


VIEW'     SHOWING,    ONE 
A  ITS    BRAKE    APPLIED 


Steering  Mechanism  with  Full  Length  Multiplane  on  21E  Paver. 


188 


Water  Control  Essential  to  Dominant 
Strength  Concrete 

Successful  concrete  construction  is  only  possible 
when  the  quantity  of  mixing  water  is  systemati- 
cally controlled.  Uniformity  of  water  content  in 
each  batch  means  uniform  strength  of  concrete. 
Without  knowledge  of  the  aggregates  to  be  used, 
the  weather  conditions  under  which  the  work  is  to 
be  carried  on,  and  the  amount  of  water  in  the  sand, 
it  is  impossible  to  set  a  definite  figure  as  the  quan- 
tity of  mixing  water  required  per  cubic  foot  or 
cubic  yard  of  concrete.  If  a  porous  aggregate,  such 
as  crushed  blast  furnace  slag,  is  employed,  sufficient 
water  must  be  added  not  only  to  hydrate  the  ce- 
ment and  wet  the  surface  of  the  sand  but  to  be  ab- 
sorbed by  the  coarse  aggregate ;  while  with  a  hard 
dense  gravel  less  water  is  required. 

With  a  given  aggregate,  known  weather  condi- 
tions and  a  particular  type  of  work,  there  is  one 
quantity  of  water  which  satisfies  the  requirements. 
This  amount  may  change  from  day  to  day  but  will 
not  change  from  one  mix  to  the  next. 

Adjustment  of  Water  Tank 


In  the  design  of  the  water  measuring  tank  two 
requirements  have  been  kept  constantly  in  mind. 
First,  that  the  measuring  device  be  easily  adjust- 


189 


ed,  and  second,  that  the  tank  when  set  deliver  the 
same  quantity  of  water  to  each  batch  of  concrete, 
measuring  it  automatically  even  though  the  oper- 
ator be  giving  his  attention  to  some  other  part  of 
the  mixing  operation.  Further,  the  foreman  or  in- 
spector should  be  able  at  a  glance  to  determine  the 
quantity  of  water  passing  into  the  mixer. 

The  Koehring  Water  Measuring  Tank  fulfills 
these  requirements.  It  is  constructed  without  floats 
or  intricate  parts  and  can  be  quickly  regulated  and 
adjusted  without  the  use  of  a  wrench  or  special 
tools.  Simple  in  design,  staunch  in  construction, 
it  is  a  dominant  factor  in  the  manufacture  of  Stand- 
ardized Concrete. 

The  tank  is  filled  by  attaching  a  supply  hose  at 
nipple  D,  Fig.  8,  and  turning  handle  of  three-way 
valve,  into  position  C,  Fig.  8.  With  the  handle  in 
this  position,  water  will  flow  into  the  tank,  the  air 
escaping  through  check  valve  E,  which  automati- 
cally closes,  when  the  tank  is  filled. 

Discharge  of  water  from  the  tank  into  the 
drum  is  accomplished  by  turning  three-way  valve 
handle  into  position  C2,  Fig.  8. 

The  following  table  gives  the  amount  of  water 
discharged  from  the  tank  for  each  setting  of  the 
regulating  handle: 


Set- 

Discharge 

Discharge 

Discharge 

Discharge 

Discharge 

ings  of 

fron  12x24 

from  12x33 

from  16x34 

from  18x40 

from  18x50 

Valve 
Han- 

Tank 

Tank 

Tank 

Tank 

Tank 

die 

Gal. 

Lbs. 

Gal. 

Lbs. 

Gal. 

Lbs. 

Gal. 

Lbs. 

Gal. 

Lbs. 

1 

1.2 

3.5 

1.3 

10.75 

2.1 

17.5 

6.4 

53.0 

5.7 

47.5 

2 

1.4 

11.5 

1.7 

14.5 

3.0 

24.75 

7.5 

62.75 

7.1 

59.5 

3 

1.8 

15.25 

2.7 

22.5 

4.3 

35.5 

9.7 

81.5 

9.7 

81.0 

4 

2.4 

20.0 

3.5 

29.0 

6.2 

51.25 

12.6 

105.75 

13.6 

113.0 

5 

3.3 

27.25 

4.7 

39.0 

8.3 

69.0 

16.5 

137.5 

18.0 

150.0 

6 

4.2 

35.25 

5  9 

49.25 

11.2 

94.0 

20.0 

167.0 

22.2 

185.5 

7 

5.2 

43.5 

7.6 

63.25 

14.0 

117.0 

24.3 

203.0 

29.2 

243.5 

8 

6.2 

52.0 

9.0 

75.25 

17.5 

145.5 

29.0 

240.75 

35.3 

294.5 

9 

7.8 

64.75 

10.8 

90.0 

21.0 

175.25 

34.0 

284.5 

42.2 

352.0 

10 

9.2 

76.5 

12.7 

106.0 

24.1 

201.0 

38.0 

317.0 

48.5 

404.25 

11 

10.0 

84.0 

14   1 

117.5 

27.1 

226.0 

41.5 

345.75 

53.5 

446.5 

12 

10.9 

91.0 

15.1 

126.25 

28.5 

235.7 

43.5 

362.75 

57.3 

478.0 

In  starting  up  mixer,  the  segment  on  the  handle 
B  should  be  set  with  latch  A  in  notches  (4)  or  (5) 
and  then  moved  backward  or  forward  to  regulate 
to  the  proper  amount  of  water  required. 


190 


If  tank  does  not  fill  fast  enough,  do  not  blame 
the  water  measuring  system  but  rather  look  for  the 
trouble  in  the  supply  line.  See  if  there  is  sufficient 
water  pressure  and  be  sure  that  the  supply  line  or 
any  part  of;  it  is  not  smaller  than  the  supply  open- 
ing at  D. 

The  tank  should  be  occasionally  drained  during 
the  working  season  in  order  to  remove  sediment, 
which,  if  allowed  to  accumulate,  will  cut  the  bronze 
plug  and  cause  trouble.  IT  MUST  ALWAYS  BE 
DRAINED  AT  NIGHT  AND  WHEN  NOT  IN 
USE  IN  COLD  WEATHER,  in  order  to  prevent 
damage  to  parts  by  freezing. 

Mixer  on  Work 

After  mixer  has  been  taken  to  the  work,  we 
suggest  putting  one  or  more  wheelbarrows  full  of 
stone  in  the  drum  and  running  the  mixer  for  half 
an  hour  or  more,  thus  scouring  it  thoroughly  and 
removing  all  roughness.  The  revolutions  of  the 
drum  should  be  tried  out.  The  best  results  are  ob- 
tained at  the  following  revolutions  per  minute: 
No.  of  Mixer  R.P.M. 

104S    17 

10S,  14S,  214E,  10E  and  14E 16 

107S,  21S  and  21E 15 

28S  and  32E 14 

The  pickup  buckets,  discharging  directly  upon 
the  swing  chute,  also  give  the  quickest  discharge  at 
the  above  stated  revolutions.  At  a  lower  speed  a 
certain  amount  falls  off  the  buckets  before  reach- 
ing the  proper  height  and  at  a  greater  speed  some 
of  the  concrete  is  carried  over  the  swinging  chute. 
It  is  advisable,  upon  starting  a  new  mixer,  to 
use  one-half  the  normal  crew  the  first  day,  in  order 
to  allow  the  operator  to  become  acquainted  with 
his  machine  and  to  make  minor  adjustments  of  the 
clutches. 

After  running  the  machine  a  couple  of  days, 
remove  all  slack  from  cables,  as  new  cables  stretch 
with  use.  This  eliminates  the  jerks  by  which  they 
are  sometimes  broken. 

191 


After  running  a  week  or  so,  all  nuts  should  be 
drawn  up,  as  the  new  bolts  may  stretch,  leaving 
the  nuts  loose. 

Operating  MIXER  TO  INSURE  MAXIMUM 
Yardage 

The  operator  should  throw  in  the  hoisting 
clutch,  then  when  the  skip  has  reached  the  elevation 
where  it  is  ready  to  charge  drum,  start  the  water 
flowing  from  the  measuring  tank.  As  automatic 
knockouts  are  on  all  Koehring  Machines  the  skip 
will  stop  when  reaching  the  proper  height.  After 
skip  has  been  lowered  the  operator  should  close  the 
three-way  valve  when  the  water  stops  flowing.  'He 
can  tell  this  by  watching  the  gauge  glass  on  the 
water  tank.  When  concrete  has  been  mixed  the  re- 
quired length  of 'time,  has  been  dumped,  and  three- 
fourths  of  the  concrete  is  out  of  the  drum,  the  skip 
should  be  started  up  again.  By  the  time  it  has 
reached  the  charging  position  the  drum  is  empty. 
Then  reverse  the  tilting  discharge  chute  so  that  it 
can  aid  in  mixing  the  next  batch.  The  operator 
will  have  time  to  run  bucket  out  on  the  boom  and 
dump  it  while  the  batch  is  being  mixed  and  the 
skip  is  being  loaded. 

Keep  Mixer  Clean 

When  contractors  finish  concreting  at  noon  and 
in  the  afternoon,  it  is  advisable  to  put  a  few  wheel- 
barrows of  stone  in  the  drum  and  scour  it  for  a  few 
minutes.  By  doing  this  a  clean  drum  is  assured  at 
all  times. 

To  help  instill  in  the  minds  of  the  crew  pride  in 
their  work  and  to  secure  a  maximum  of  output,  the 
machine  should  be  kept  as  clean  as  possible,  both 
on  the  inside  and  on  the  outside.  The  outside  may 
be  kept  clean  by  brushing  off  the  machine  each 
night  before  shutting  down  and  coating  the  drum 
and  other  parts  with  oil,  which  will  prevent  the  ce- 
ment from  sticking.  The  oil  drained  from  the 
crank  case  can  be  saved  and  used  for  this  purpose. 

192 


In  coating  the  drum  and  other  parts  of  mixer 
with  oil,  care  must  be  taken  that  no  oil  gets  on  the 
runways  of  either  the  drum  or  the  boom. 

The  Proper  Method   of  Putting   Aggregate   in 

Skip  to  PREVENT  CONCRETE  CLOGGING 

on  Blades 

Cement  should  never  be  put  in  skip  first,  as  it 
retards  the  flow  of  material  when  skip  is  elevated, 
thereby  making  it  necessary  to  hold  it  in  that  posi- 
tion for  a  longer  time  to  clean  itself.  As  the  ce- 
ment is  last  to  leave  the  skip,  some  of  it  will  stay  in 
the  sub-chute  until  pushed  into  the  drum  by  the 
next  batch,  and  some  will  pack  on  the  inside  of  the 
drum  head  on  the  charging  side,  building  up  a  ring 
around  the  drum  opening.  There  should  always  be 
at  least  J4  °f  *he  stone  or  gravel  in  skip  before  ce- 
ment is  dumped,  as  this  will  aid  the  flow  of  material 
and  also  prevent  the  cement  hanging  in  the  sub- 
chute. 

It  is  very  important  that  the  water  be  admitted 
at  the  proper  time ;  that  is,  when  the  material  starts 
to  roll  into  the  drum,  so  the  material  and  water  will 
enter  the  drum  at  the  same  time  to  avoid  clogging. 
This  also  increases  the  mixing  efficiency. 

Shutting  Down  Mixer  for  Winter  or  Prolonged 
Period,  When  Machine  Will  not  Be  in  Use 

Drain  all  water  from  the  boiler  and  steam  en- 
gine or  gasoline  engine,  and  also  from  piping  and 
water  tanks.  Pour  about  one  gallon  of  .cylinder  oil 
into  the  boiler  and  a  quart  of  oil  into  the  tanks. 
Fill  again  with  water,  then  drain.  It  would  be  well 
to  add  a  little  whitelead  to  the  cylinder  oil, — just 
enough  to  give  it  a  little  body. 

If  mixer  is  equipped  with  steam  power,  remove 
hood  from  boiler  and  clean  the  tubes  out  thorough- 
ly 1  with  a  wire  brush  and  swab  carefully  with  oiled 
waste  or  rags.  Cover  the  top  of  the  boiler  with 
canvas  and  tie  it  down  securely,  then  coat  inside 
of  fire  box  with  heavy  oil,  and  paint  oryoil  the  out- 
side of  the  boiler. 

Whether  gasoline  or  steam  engine  is  used,  take 

193 


off  cylinder  head  and  coat  inside  of  cylinder  with 
whitelead  and  oil. 

All  hard  working  machinery,  especially  concrete 
machinery,  must  wear ;  therefore  examine  the  entire 
machine  carefully  and  try  out  all  working  parts  and 
replace  with  new  parts  those  parts,  if  any,  which 
are  worn  enough  so  as  not  to  work  properly. 

By  overhauling  the  mixer  and  replacing  all 
worn  parts,  when  mixer  is  shut  down,  no  delay  will 
be  occasioned  by  having  to  make  repairs  when 
ready  to  re-start  the  mixer  in  the  spring.  This 
should  not  be  neglected,  for  worn  machinery  de- 
creases results  and  increases  delays  and  conse- 
quently labor,  and  possibly  will  necessitate  extra 
hours  at  night  for  the  operator  "when  the  mosqui- 
toes are  biting  at  their  best." 

After  machine  has  been  thoroughly,  inspected 
and  overhauled/ coat  all  bright  parts  on  mixer  with 
heavy  machine  oil  or,  preferably,  cylinder  oil  con- 
taining a  good  heavy  body  of  whitelead.  Give  bal- 
ance of  mixer*  a  good  coat  of  paint. 

Grease  all  bearings  carefully  and  turn  machin- 
ery over  a  few  times  to  insure  that  the  insides  of 
bearings  are  thoroughly  coated.  Take  off  cables 
and  clean  thoroughly  with  kerosene,  then  pass 
through  a  bath  of  warm  lubricant.  The  following 
makes  a  good  mixture: 

One  part  freshly  slacked  lime. 

Four  parts  fine  or  coal  tar. 

One-half  part  powdered  graphite. 

Heat  up  and  thoroughly  mix  together. 

Clean  traction  chain  thoroughly  with  kerosene, 
then  give  it  a  good  coat  of  heavy  oil. 

If  possible,  house  the  mixer  or  cover  it  with 
tarpaulin  in  order  to  protect  it  from  the  weather. 

When  starting  up  again  after  a  prolonged  shut 
down,  it  will,  of  course,  be  necessary  to  clean  off  all 
surplus  grease  and  then  follow  the  same  procedure 
as  used  in  starting  of  a  new  machine. 

Ordering  Parts 

When  ordering  new  parts  for  a  mixer,  the  con- 
tractor should  be  sure  to  give  the  size  and  number 


194 


of  his  machine.  This  he  will  find  on  the  nameplate 
attached  to  the  frame.  The  part  and  pattern  num- 
ber he  will  find  in  the  repair  part  book  which  ac- 
companies each  mixer. 

Ordering  Clutch  Parts 

When   ordering   new   parts   for   clutches,  state 
specifically  whether  parts  are  wanted  for — 
Drum  or  main  drive  clutch. 
Charging  skip  hoist  clutch. 
Traction  clutch. 

Boom  clutch  or  auxiliary  hoist  clutch. 
AND  ALWAYS  GIVE  THE  NUMBER  OF 
YOUR  MIXER. 

(Illustration) 

Part  No.  65,  master  disc  for  charging  skip  hoist 
clutch  on  mixer. 

Size   No 

Get  these  numbers  from  nameplate  on  your  mixer 

Or 

. Mixer  No 

code  word  of  part      code  word  of  HP  clutch 

This  will  eliminate  mistakes  and  will  enable  us 
to  give  our  customers  prompt  service. 


195 


INDEX 

Page 
Aggregates 

Chapter  7 — Notes  on  Specifications 117 

Aggregates — Acceptability  of 

Chapter  2 — Materials  Entering  Concrete 31 

Aggregates — Concrete  Aggregates 

Chapter  2 — Materials  Entering  Concrete 23 

Aggregate  Control 

Chapter  1 — Field  Operation  in  Concrete  Construction.  .  .    19 

Aggregate — Effect  of  Aggregate  on  Fire  Resistive  Qualities 
of  Concrete 

Chapter  2 — Materials  Entering  Concrete 30 

Aggregate — Effect  of  Mineral  Properties  of  Aggregate 
on  Strength  of  Concrete 

Chapter  2 — Materials  Entering  Concrete 31 

Aggregate — Effect  of  Physical  Properties  on  Quality  of 
Concrete 

Chapter  2 — Materials  Entering  Concrete 25 

Aggregates.  Tests  on 

Chapter  2 — Materials  Entering  Concrete 27 

Aggregates,  Washing 

Chapter  2 — Materials  Entering  Concrete 30 

Amount  of   Concrete  to  be  Placed 

Chapter  1 — Field  Operation  in  Concf  etc  Construction ...    11 
Assembling  of  Construction  Mixers 

Chapter  15 — Mechanical  Equipment — its  Starting,  Care 

and  Operation 162 

Assembling  of  Paving  Mixers 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 158 

Balancing  of  Plant 

Chapter  3 — Concrete  in  Highway  Construction 54 

Basic  Principles  in  all  Specifications 

Chapter-7 — Notes  on  Specifications 115 

Beams 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 106 

Boiler,  Starting  and  Care  of 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 163 

196 


INDEX— Continued 

Page 

Boom  Erection  and  Adjusting  Instructions 

Chapter  15 — Mechanical  Equipment — Its   Starting, 

Care  and  Operation 159 

Bridges 

Chapter  9 — Notes  on  Concrete  Culvert  and  Bridge  Con- 
struction   130 

Bridge  Abutments — Functions  of  Bridge  Abutments 

Chapter  9 — Notes  on  Concrete  Culvert  and  Bridge  Con- 
struction   131 

Capacity  of  Mixing  Plant 

Chapter  1 — Field  Operation  in  Concrete  Construction.  . .   21 

Careful  Planning  Means  Economical  Completion  of 
Project 

Chapter  1 — Field  Operation  in  Concrete  Construction ...      9 

Careful  Supervision  over  Proportioning  and  Mixing 
Necessary 

Chapter  4 — Miscellaneous  Notes  for  Superintendent  or 

Foreman 87 

Carpenter  Work  on  Bridge 

Chapter  9 — Notes  on  Culvert  and  Bridge  Construction .  .  133 

Centering  and  Falsework 

Chapter  5 — Forms  for  Concrete  Construction 104 

Clean  Sand 

Chapter  2 — Materials  Entering  Concrete 24 

Clutches — Adjustment  of  Friction  Clutches 

Chapter  15 — Mechanical  Equipment —  Its  Starting,  Care 

and  Operation 176 

Clutches — Removing  Clutches 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 177 

Coal  and  Material  Bins 

Chapter  14 — Notes  on  Silos,  Coal  and  Material  Bins  and 

Grain  Tanks 149 

Cold  Weather  Work 

Chapter  3 — Concrete  in  Highway  Construction 54 

Chapter  4 — Miscellaneous  Notes 88 

Colorimetric  Test 

Chapter  2 — Materials  Entering  Concrete 24 

Columns 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 160 

197 


INDEX— Continued 

Page 
Concrete  Base  in  Highway  Construction 

Chapter  3 — Concrete  in  Highway  Construction 35 

Control  of  Amount  of  Mixing 

Chapter  1 — Field  Operation  in  Concrete  Construction ....   20 

Cos  tof  Forms 

Chapter  5 — Forms  for  Concrete  Construction 102 

Cost — Items  Entering  into  Cost 

Chapter  8 — Estimating  Cost  of  Concrete  Construction ....  122 

Cost — Cost  and  Quantity  of  Materials  very  Important 

Chapter  8 — Estimating  Cost  of  Concrete  Construction 123 

Cost — Relation  of  Speed  to  Cost 

Chapter  8 — Estimating  Cost  of  Concrete  Construction 125 

Cost  of  Water  Should  not  be  Overlooked 

Chapter  8 — Estimating  Cost  of  Concrete  Construction 126 

Culverts 

Chapter  9 — Notes  on  Concrete  Culvert  and  Bridge  Con- 
struction   127 

Curbs  in  Highway  Construction 

Chapter  3 — Concrete  in  Highway  Construction 36 

Cost — Cost  and  Quantity  of  Materials  very  Important 
Chapter  8 — Estimating  Cost  of  Concrete  Construction. .  .  123 

Curing 

Chapter  1— Field  Operation  in  Concrete  Construction ...   16 

Curing  in  Highway  Construction 

Chapter  3 — Concrete  in  Highway  Construction 55 

Curing 

Chapter  4 — Miscellaneous  Notes  for  Superintendent  or 

Foreman 90 

Curves  in  Highway  Construction 

Chapter  3 — Concrete  in  Highway  Construction 36 

Design — Effect  of  Design  of  Mixer  on  Quality  of  Concrete 

Chapter  1 — Field  Operation  in  Concrete  Construction ...   17 

Design  of  Pavements 

Chapter  3 — Concrete  in  Highway  Construction 35 

Drainage 

Chapter  3 — Concrete  in  Highway  Construction 38 

198 


INDEX — Continued 

Page 

Effect  of  Aggregate  on  Fire  Resistive  Qualities  of 
Concrete 

Chapter  2 — Materials  Entering  Concrete 30 

Effect  of  Design  of  Mixer  on  Quality  of  Concrete 

Chapter  1 — Field  Operation  in  Concrete  Construction.  . .   17 

Effect  of  Physical  Properties  of  Aggregate  on  Quality  of 
Concrete 

Chapter  2 — Materials  Entering  Concrete 25 

Engines 

Gasoline  Engine 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 166 

Steam  Engine,  Starting  and  Care  of 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation . 165 

Engine — To  Start  and  Run  Fuller  &  Johnson  Engine 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 166 

Engine  Trouble 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 
and  Operation 

Engine  will  not  Turn  Over — Engine  Stuck.  .170 

Starting  Troubles 170 

No  Power — Loss  of  Power 171 

Misfiring 172 

Misfiring  in  one  Cylinder 173 

Sudden  Stop 173 

Back 'Firing 173 

Irregular  Running 174 

Overheating  in  Cylinder 174 

Pre-Ignition  or  deep  pounding  in  cylinder.  .174 

Smoke 175 

Engine  gradually  slows  down  and  stops ....  175 

Excessive  vibration 175 

Cam  shaft  rattle 175 

Wheezing  scraping  sound 1 75 

Knocking  and  pounding — regular 175 

Irregular  Knock 176 

Speed  variation 176 

Falsework — Centering  and  Falsework 

Chapter  5 — Forms  for  Concrete  Construction 104 

199 


INDEX— Continued 

Page 
Features  for  Consideration 

Chapter  7 — Notes  on  Specifications 114 

Finishing — Forms  and  Finishing 

Chapter  3— Concrete  in  Highway  Construction 53 

Forms 

Chapter  4 — Miscellaneous  Notes  for  Superintendent  or 

Foreman 85 

Forms — Care  in  Manufacture  of  Forms 

Chapter  5 — Forms  for  Concrete  Construction 95 

Forms — Contractor  Responsible  for  Forms 

Chapter  5 — Forms  for  Concrete  Construction 95 

Forms — Cost  of 

Chapter  5— Forms  for  Concrete  Construction 102 

Forms — Dry  Form  Lumber  Desirable 

Chapter  5 — Forms  for  Concrete  Construction 102 

Forms — Form  Economy 

Chapter  5 — Forms  for  Concrete  Construction 97 

Forms — Forms  and  Finishing 

Chapter  3 — Concrete  in  Highway  Construction 53 

Forms — Sliding  Forms 

Chapter  5 — Forms  for  Concrete  Construction 100 

Forms — Wetting  Forms 

Chapter  5 — Forms  for  Concrete  Construction 103 

Forms — Wood  Forms 

Chapter  5— Forms  for  Concrete  Construction 98 

Foundation  Material  of  Utmost  Importance 

Chapter  9 — Notes  on  Culvert  and  Bridge  Construction.  .  132 

Foundation  and  Footings 

Chapter  11 141 

Gasoline  Engine 

Chapter  15 — Mechanical  Equipment — Its  Starting, 

Care  and  Operation 166 

Grain  Tanks 

Chapter  14 — Notes  on  Silos,  Coal  and  Material  Bins  and 

Grain  Tanks 153 

Handling  Materials 

Chapter  3 — Concrete  in  Highway  Construction 39 

200 


INDEX— Continued 

Page 
Harmful  Materials 

Chapter  2 — Materials  Entering  Concrete 25 

Haulage  Units 

Chapter  3 — Concrete  in  Highway  Construction 64 

Hoist  Brake— Adjustment  of  Hoist  Brake 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

Construction 180 

Instructions  for  Operating  Steering  Mechanism  on  21 E 

Chapter  15— Mechanical  Equipment  etc 186 

Insurance 

Chapter  8 — Estimating  Cost  of  Concrete  Construction. .  .  123 

Joining  New  Concrete  to  Old 

Chapter  4 — Miscellaneous  Notes  for  Superintendent  or 

Foreman 91 

Keep  Mixer  Clean 

Chapter  15 — Mechanical  Equipment  etc 192 

Lever  Operation 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 181 

Maintenance  of  Concrete  Pavements 

Chapter  3 — Concrete  in  Highway  Construction 56 

Materials  of  Construction  in  Highway  Construction 

Chapter  3 — Concrete  in  Highway  Construction 36 

Materials — Cost  and  Quantity  of  Materials  Very  Impor- 
tant 

Chapter  8 — Estimating  Cost  of  Concrete  Construction. .  .  1 23 

Mechanical  Equipment 

Chapter  3 — Concrete  in  Highway  Construction 38 

Method  of  Making  Void  Determination 

Chapter  2 — Materials  Entering  Concrete 27 

Mineral  Properties  of  Aggregate — Effect  on  Strength  of 
Concrete 

Chapter  2 — Materials  Entering  Concrete 31 

Mixer — Effect  of  design  of  Mixer  on  Quality  Concrete 

Chapter  1 — Field  operation  in  Concrete  Construction.  .  .    17 

Mixer 

Keep  Mixer  Clean 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 192 

Mixer  Most  Important  Piece  of  Plant 

Chapter  1 — Field  Operation  in  Concrete  Construction.  . .    12 

201 


INDEX— Continued 

Page 
Mixer  on  work 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 191 

Mixer  Plant 

Chapter  3 — Concrete  in  Highway  Construction 47 

Mixer — Type  of  Mixer 

Chapter  7 — Notes  on  Specifications 117 

Motor — Care  and  Starting  Waukesha  Motor 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 168 

Notes  on  Silos,  Coal  and  Material  Bins  and  Grain  Tanks 

Chapter  14 149 

One  and  Two  Course  Construction 

Chapter  3 — Concrete  in  Highway  Construction 34 

Ordering  Clutch  Parts 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 195 

Ordering  Parts 

Chapter  1 5 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 194 

Organization  of  Crew 

Chapter  3 — Concrete  in  Highway  Construction 53 

Operating  Mixer  to  Insure  Maximum  Yardage 

Chapter  15 — Mechanical  Equipment-^Its  Starting,  Care 

and  Operation 192 

Overhead 

Chapter  8 — Estimating  Cost  of  Concrete  Construction. .  .  123 

Panels — Standardization  of  Panels 

Chapter  5 — Forms  for  Concrete  Construction 98 

Pavers 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 
and  Operation 

No.  10E  Paver 181 

No.  14E  and  21E  Paver 183 

Piers 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 106 

Placing  Concrete  in  Forms 

Chapter  1 — Field  Operation  in  Concrete  Construction ...    15 

202 


INDEX — Continued 

Page 
Placing  Equipment,  Character  of 

Chapter  1 — Field  Operation  in  Concrete  Construction.  .  .    13 

Placing  Concrete  Under  Water 

Chapter  13 147 

Planning — Careful  Planning  Means  Economical  Com- 
pletion of  Project 

Chapter  1 — Field  Operation  in  Concrete 9 

Plant,  Balancing  of 

Chapter  3 — Concrete  in  Highway  Construction 54 

Plant,  Character  of 

Chapter  1 — Field  Operation  in  Concrete  Construction  ...    12 

Plant — Remainder  of  Plant  Around  Mixer 

Chapter  1 — Field  Operation  in  Concrete  Construction  ...    12 

Preparing  to  Start  Mixer 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 162 

Proper  Method  of  Putting  Aggregate  in  Skip  to  Prevent 
Concrete  Clogging  on  Blades 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 193 

Proportioning  Mixtures 

Chapter  7 — Notes  on  Specifications 117 

Pump  and  Water  Line 

Chapter  3 — Concrete  in  Highway  Construction 49 

Quality  of  Concrete  Desired 

Chapter  1 — Field  Operation  in  Concrete  Construction ...   14 

Quality  of  Concrete  not  Dependent  on  Cement  Atone 

Chapter  2 — Materials  Entering  Concrete 32 

Receipt  of  Materials  and  Plant  for  Handling 

Chapter  1 — Field  Operation  in  Concrete  Construction  ...   10 

Rehandling  Materials 

Chapter  3 — Concrete  in  Highway  Construction 45 

Reinforcement — Handling  Reinforcement  on  the  Work 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 108 

Reinforcement — MakeshiftReinforcement  Dangerous 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 110 

203 


INDEX — Continued 

Page 
Reinforcement — Need  for  Reinforcement 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 105 

Reinforcements — Types  of  Reinforcements 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 107 

Reinforcing  Steel — Examples,  of  Reinforcing  Steel  in 
Concrete 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 110 

Reinforcing  Steel — Position  of  Steel 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 106 

Reinforcing  Steel — Quality  of  Reinforcing  Steel 

Chapter  6 — Use  of  Reinforcing  Steel  in  Concrete 105 

Remainder  of  Plant  Around  Mixer 

Chapter  1 — Field  Operation  in  Concrete  Construction.  .  .   12 

Responsibility  Should  be  Clearly  Defined 

Chapter  7 — Notes  on  Specifications 113 

Sampling  Sand 

Chapter  2 — Materials  Entering  Concrete 26 

Safety  Dependent  on  Form  Construction 

Chapter  5 — Forms  for  Concrete  Construction 98 

San  J  or  Fine  Aggregate 

Chapter  2 — Materials  Entering  Concrete 23 

Shoulders  in  Highway  Construction 

Chapter  3 — Concrete  in  Highway  Construction 36 

Shutting  Down  Mixer  for  Winter  or  Prolonged  Period 
When  Machine  Will  Not  be  in  use 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 193 

Silot 

Chapter  14 — Notes  on  Silos,  Coal  and  Material  Bins  and 

Grain  Tanks 149 

Sliding  Forms 

Chapter  5 — Forms  for  Concrete  Construction 100 

Specifications  Should  be  Clear 

Chapter  7 — Notes  on  Specifications 113 

Starting  and  Care  of  Boiler 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 163 

204 


INDEX — Continued 

Page 
Steam  Engine— Starting  and  Care  of 

Chapter  15 — Mechanical  Equipment,  Its  Starting, 

Care  and  Operation 166 

Steering  Mechanism — Instructions  for  Operating 
Steering  Mechanism  on  21 E  Paver — With 
Full  Length  Multiplane 

Chapter  15 — Mechanical  Equipment — Its  Starting, 

Care  and  Operation 186 

Strength 

Chapter  1 — Field  Operation  in  Concrete  Construction  ...   17 

Surface  Finish — Concrete  Surface  Finish 

Chapter  A — Miscellaneous  Notes  for  Superintendent  or 

Foreman .   91 

Tables—Use  of 

Chapter  3 — Concrete  in  Highway  Construction 51 

Tests  on  Aggregates 

Chapter  2 — Materials  Entering  Concrete 27 

Two  Course  Construction 

Chapter  3 — Concrete  in  Highway  Construction 34 

Type  of  Mixer 

Chapter  7 — Notes  on  Specifications 117 

Uniform  Strength  Demands  Uniform  Consistency  of 
Concrete 

Chapter  1 — Field  Operation  in  Concrete  Construction    .  .    15 

Unloading — Method  of  Unloading  Mixer 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 157 

Voids 

Chapter  2 — Material  Entering  Concrete 26 

Voids — Method  of  Making  Void  Determination 

Chapter  2 — Materials  Entering  Concrete 27 

Washing  Aggregates 

Chapter  2 — Materials  Entering  Concrete 30 

Water  Control 

Chapter  1 — Field  Operation  in  Concrete  Construction  ...   20 

Water  Control  Essential  to  Dominant  Strength  Concrete 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 189 

205 


INDEX— Continued 

Page 
Water  Line — Pump  and  Water  Line 

Chapter  3 — Concrete  in  Highway  Construction 49 

Water  Tank — Adjustment  of  Water  Tank 

Chapter  15 — Mechanical  Equipment — Its  Starting,  Care 

and  Operation 189 

Watertightness — Fundamentals  for  Watertightness 

Chapter  12 — Waterproofing  Concrete 143 

Watertightness — Good  Concrete  Properly  Mixed  is 
Watertight 

Chapter  12 — Waterproofing  Concrete 143 

Watertightness — Poor  Concrete  Responsible  for  Popular 
Belief  That  Concrete  is  Not  Watertight 

Chapter  12 — Waterproofing  of  Concrete 143 

Watertightness — System  for  Increasing 

Chapter  12 — Waterproofing  Concrete 144 

Weather  Conditions 

Chapter  8 — Estimating  Cost  of  Concrete  Construction..  .124 

Wetting  Forms 

Chapter  5 — Forms  for  Concrete  Construction 103 

Wing  Walls 

Chapter  9 — Notes  on  Culvert  and  Bridge  Construction .  .  129 

Wood  Forms 

Chapter  5 — Forms  for  Concrete  Construction 98 


206 


INDEX  TO  TABLES 

Page 
Table  No.  1 

Table  of  Recommended  Mixtures  and  Maximum  Aggre- 
gate Sizes 28 

Table  No.  2 

Table  Showing  Cubic  Yard  Weights  in  Pounds,  Equiva- 
lent Weight  in  Tons,  and  Fractional  Number  of  Cubic 
Yards  Per  Ton 33 

Table  No.  3 

Thickness  for  Light  Traffic  Roads  and  Streets 37 

Table  No.  4 

Thickness  for  Heavy  Traffic  Roads  and  Streets 37 

Table  No.  S 

Minimum  Quantity  of  Storage  Required  for  Economic 
Operation  of  Highway  Project 44 

Table  No.  6 

Cars  of  Materials  Required  Per  Day  and  Per  Month  for 
Three  Sizes  of  Paver. 44 

Table  No.  7 

Trackage  for  Economiral  Operation 44 

Table  No.  8 

Capacity  of  Material  Bins 45 

Table  No.  9 

Size  of  Pipe  Required  for  Varying  Length  Head 50 

Table  No.  10 

Cubic  Yards  of  Concrete  Per  Linear  Foot  and  Per  Mile 

of  Pavement 58 

Table  No.  11 

Quantity  of  Material  Required  for  Roads,  Streets  and 
Alleys 60 

Table  No.  12 

Maximum  Safe  Load  for  Wood  Columns 86 

Tmble  No.  13 

Size  of  Waterway  Required  for  Various  Areas  to  be 
Drained 128 

207 


INDEX  TO  TABLES— Continued 

Page 
Table  No.  14 

Table  Showing  Quantities  of  Material  Required  in  Con- 
crete Bridges  of  Spans  8  Feet  to  24  Feet,  Roadway  20 
Feet,  as  Shown  by  the  S.tandard  Plans  of  the  Wisconsin 
Highway  Commission 134 

Table  No.  15 

Table  Giving  the  Cubic  Feet  of  Sand  and  Pebbles  (or 
crushed  stone)  to  be  Mixed  With  One  Sack  of  Cement  to 
Secure  Mixtures  of  the  Different  Proportions,  and  the 
resulting  Volume  in  Cubic  Feet  of  Compacted  Mortar  or 
Concrete. 135 

Table  No.  16 

Table  Giving  the  Number  of  Sacks  of  Cement  and  Cubic 
Feet  of  Sand  and  Pebbles  or  Stone  Required  to  Make  One 
Cubic  Yard  ftwenty-?even  cubic  feet)  of  Compacted  Con- 
crete   136 

Table  No.  17 

Number  of  Square  Feet  of  Wall  Surface  Covered  Per  Sack 
of  Cement,  for  Different  Proportions  and  Varying  Thick- 
ness of  Plastering 138 

Table  No.  18 

Materials  Required  for  100  Sq.  Ft.  of  Surface  for  Varying 
Thickness  of  Plaster 138 

Table  No.  19 

Quantity  of  Cement  Required  Per  Cubic  Foot  and  Per 
Cubic  Yard  of  Concrete  for  Various  Mixtures  in  Terms  of 
Sacks  and  Barrels 139 

Table  No.  20 

Materials  Required  for  100  Sq.  Ft.  of  Surface  for  Varying 
Thicknes  of  Course 139 

Table  No.  21 

Materials  Required  for  100  Sq,  Ft.  of  Sidewalks  and  Floors 
for  Varying  Thickness?  of  Course 140 

Table  No.  22 

Bearing  Power  of  Soils 142 

Table  No.  23 

Spacing  of  Horizontal  Reinforcing  Rods  for  Silos  of  Vari- 
ous Inside  Diameters 150 

Table  No.  24 

Quantity  cf  Concrete  Materials  for  Monolithic  Silos  of 
Various  Inside  Diameters ..  151 


INDEX  TO  TABLES— Continued 

Page 
Table  No.  25 

Diameter  of  Silos  Required  to  Feed  Various  Numbers  of 
Animals 151 

Table  No.  26 

Approximate  Capacity  of  Round  Silos 152 

Table  No.  27 

Circular  Grain  Tanks — Area  of  Horizontal  Reinforcing 
Steel  in  Square  Inches  Per  Foot  of  Depth,  and  Thickness 
of  Wall  in  Inches.  Steel  to  be  in  Center  Wall 154 

Table  No.  2S 

Square  Grain  Tanks — Thickness  of  Wall  in  Inches  and 
Area  of  Reinforcement  in  Square  Inch  Per  Foot  of  Depth . .  154 

Table  No.  29 

Capacity  of  Circular  Grain  Bins  and  Tanks  in  Bushels ....  155 

Table  No.  30 

Table  of  Wages .  .  156 


209 


LIST  OF  ILLUSTRATIONS 

Page 
Koehring  Paver  with  distributing  spout 2 

Koehring    Construction    Mixer    with    steam    engine, 

boiler  and  power  charging  skip 4 

Koehring  Paver  with  full  length  multiplane  traction 

and  distributing  boom  and  bucket 6 

Spread  Your   Concrete  This  Way  with  a   Koehring 

Paver 8 

Koehring  Crane  Excavator 40 

Installation  Plan — Koehring  Steam  Pump 48 

Koehring  Dandie  Mixer  equipped  with  power  charg- 
ing skip  and  solid  rubber  tires 84 

Koehring  28S  Heavy  Duty  Construction  Mixer 112 

An  interesting  picture,  showing  complete  plan  of  road 
building    operations,    from    material    bins    to    the 

finished  concrete  road , 120 

View  of  bridge  under  construction 146 

Boom  details 160 

Boom  details 161 

Line    drawing   showing   Fuller   &   Johnson   Gasoline 

Engine  167 

Adjustment  of  friction  clutches,  Fig.  4 176 

Main  shaft  and  clutch  assembly  14E  Paver,  Fig.  5 178 

Main  shaft  and  clutch  assembly  14E  Paver,  Fig.  5 179 

Gear  assembly  and  control,  10E  Paver,  Fig.  6 182 

Main  shaft  and  clutch  assembly,  21E  Paver,  Fig.  7. ..   184 

Main  shaft  and  clutch  assembly,  21E  Paver,  Fig.  7 185 

Diagram  showing  steering  mechanism  full  length 
multiplane  on  21E  Paver 188 


210 


INITIAL  FINE~OF  25  OEKTS 


LD  21-100m-7/33 


49293 


UNIVERSITY  OF  CALIFORNIA  LIBRARY 


Q 

3D 

-g» 

0 

^> 

33 

-n 

C 

^ 

m 
o 

m 

00 

0 
D 

m 

en 

co- 
co 

en 

m 

< 
m 
a 

to 

CD 
CO 

g 

D 

C 

m 

CO 


•o 
m 
a 

CD 
m 

I 


Om 


§0 

oa> 


m 

o 


o 
2 


O 
cn 


O 

O 

C 


o 


U.C.BERKELEY  LIBRARIES