Skip to main content

Full text of "The evolution of vertical lift bridges"

See other formats


B^^H^^^K 

nr>_iiBi  c 

TG 


THE   EVOLUTION  OF 

VERTICAL 
LIFT  BRIDGES 


By 

HENRY  GRATTAN  TYRRELL,  C.E. 

Bridge  and  Structural  Engineer, 

EVANSTON,  ILL. 

Author  of  Mill  Building,  Construction,  1900  ;  Concrete 
Bridges   and    Culverts.     History   of  Bridge   En- 
gineering.    Mill    Buildings.    Artistic 
Bridge  Design,  etc.  etc. 


Published  by 

The  University  of  Toronto  Engineering  Society, 
Toronto,   1912 


Reprint  from  "  Applied  Science,"  1912. 


Copyrighted    !'/i:  By  H.  G.  Tyrrell 


THE   EVOLUTION  OF 

VERTICAL 
LIFT  BRIDGES 


By 
HENRY  GRATTAN  TYRRELL,  €.E. 

*  / 
Bridge  and  Structural  Engineer, 

EVANSTON,  ILL. 

Author  of  Mill  Building  Construction,  IQOO  ;  Concrete 
Bridges   and    Culverts.     History   of  Bridge   En- 
gineering.    Mill   Buildings.    Artistic 
Bridge  Design,  etc.  etc. 


Published  by 

The  University  of  Toronto  Engineering  Society, 
Toronto,  1912 


Reprint  from  "  Applied  Science,"  1912. 


Copyrighted    1V12  By  H.  G.  Tyrrell. 


.<* 
A  X 


rt 

a 

aS 

O 


THE  EVOLUTION  OF 

VERTICAL  LIFT  BRIDGES 


Hew  down  the  bridge,  Sir  Consul, 

With  all  the  speed  ye  may, 
I,  with  two  more  to  help  me, 

Will  hold  the  foe  in  play. 

And  Fathers  mixed  with  Commons, 

Seized  hatchet,  bar  and  crow, 
And  smote  upon  the  planks  above, 

And  loosed  the  props  below. 

But  meanwhile  axe  and  lever 

Had  manfully  been  plied, 
And  now  the  bridge  hangs  tottering 

Above  the  boiling  tide. 

And  with  a  crash  like  thunder 

Fell  every  loosened  beam, 
And  like  a  dam,  the  mighty  wreck 

Lay  right  athwart  the  stream. 

The  development  of  constructive  types  forms  an  interesting 
study  and  usually  shows  that  the  designs  for  many  recent  works 
are  based  upon  earlier  and  often  very  unpretentious  ones,  modified 
to  suit  local  requirements.  It  is  only  by  following  these  developments 
that  it  is  possible  to  appreciate  the  degree  of  merit  or  originality 
which  any  new  creation  may  contain.  Movable  bridges  have  been 
used  for  many  centuries,  some  writers  contending  that  the  bridge 
over  the  Euphrates  River  at  Babylon  (B.C.  783),  built  under  the 
direction  of  Queen  Nitocris,  was  arranged  with  movable  platforms, 
which  could  be  withdrawn  at  night  to  prevent  thieves  from  entering 
the  city.  Pons  Sublicius  (B.C.  621)  over  the  Tiber  at  Rome,  is 
described  by  some  historians  as  having  been  of  the  same  type,  but 
the  description  of  its  removal,  as  given  by  Lord  Macaulay,  does  not 
indicate  that  it  contained  any  parts  that  are  easily  moved,  some  of 
his  references  being  quoted  above. 


292418 


\  iqmcAL,  LIFT  BRIDGES 


Though  the  accuracy  of  these  early  traditions  will  probably 
remain  shrouded  in  mystery,  it  is  well  known  that  movable  bridges 
of  the  bascule  type  were  very  common  during  the  Middle  Ages, 
especially  at  the  approaches  to  castles  and  walled  cities,  and  quite 
elaborate  drawings  of  such  bridges  are  still  extant,  exhibiting  a 
degree  of  inventive  skill  that  has  not  been  surpassed  even  in  our 
own  time.  Indeed,  most  of  the  patented  inventions  of  the  last 
twenty  years  are  merely  revivals  of  earlier  ones  which  were  studied 
out  or  built  during  previous  centuries,  and  many  features  of  modern 
bridges,  originality  for  which  is  claimed  by  recent  proprietors,  are 
found  to  have  been  in  use  long  before  the  advent  of  the  present 
generation.  There  is,  therefore,  no  branch  of  engineering  in  which 
a  knowledge  of  history  is  more  essential. 

Movable  bridges  of  the  direct  lift  form  are,  however,  of  more 
recent  origin,  one  of  the  first  appearing  previous  to  1840,  in  the 
wooden  trestle  of  twenty-three  spans,  over  the  Danube  River  at 
Vienna,  the  floor  over  one  30  foot  opening  being  arranged  to  lift 
6^  feet.  There  was  also,  in  1846,  on  the  Amsterdam  and  Rotter- 
dam Railway,  over  the  Poldervaart — a  canal  on  the  Polders — a 
bridge  with  two  side  openings  of  21  feet  and  a  center  one  of  13  feet, 
the  last  capable  of  being  lifted  about  5  feet  vertically,  by  means  of  a 
crab  and  screw  worked  by  hand  power.  It  was  a  small  structure, 
only  55  feet  long  and  10>^  feet  wide,  with  floor  less  than  10  feet 
above  water.  Piers  were  on  a  slight  skew  and  were  founded  on 
piles.  The  next  vertical  lift  bridges  appeared  in  England,  two 
being  placed  over  the  Grand  Surrey  Canal  at  London  (1848),  under 
the  direction  of  Robert  J.  Hood,  to  carry  the  Thames  Junction 
branch  of  the  London,  Brighton  and  South  Coast  Railway.  These 
bridges  crossed  the  canal  and  tow  path  and  the  larger  one  had  a 
span  of  35  feet  between  tower  faces,  though  the  channel  opening 
was  only  21  feet.  It  was  83  feet  wide  with  a  rail-track  on  one  side. 
The  moving  platform,  weighing  12^  tons,  was  suspended  by  wire 
ropes  over  sheaves  on  top  of  four  disconnected  cast  iron  towers,  and 
the  Yl]4  tons  of  counterweight  descended  into  underground  cast  iron 
cylinders.  It  could  be  lifted  by  two  men  on  a  hand  winch,  the 
greatest  rise  being  only  5  feet.  The  other  bridge  over  the  same 
canal  was  12^  feet  wide  and  31^  feet  long,  the  upper  end  of  towers 
being  connected  by  braces  with  curved  bottom  cords.  Chains  were 
used  for  the  suspenders  instead  of  ropes,  and  the  rear  tower  faces 
were  curved,  giving  them  a  graceful  appearance.  The  total  cost  of 
the  latter  was  $6,500.  These  two  bridges  over  the  Grand  Surrey 
Canal,  were  probably  the  first  properly  constructed  ones  of  the 
vertical  lift  type,  and  for  more  than  sixty  years  have  served  as  pro- 
totypes for  many  later  and  larger  ones. 

Following  these,  there  appeared  at  least  four  fine  designs  which 
have  hardly  been  excelled,  and  certainly  not  in  artistic  merit.  The 
first  was  in  the  international  competition  of  1850  for  a  bridge  across 
the  Rhine  at  Cologne,  which  brought  forth  no  less  than  sixty-two 
competitive  plans,  one  of  which  by  Captain  W.  Moorsom,  of  Lon- 
don, contained  a  centre  lifting  span  100  feet  long,  between  600  feet 


VERTICAL  LIFT  BRIDGES  5 

through  side  lattice  girders.  Provision  was  made  for  a  25  foot  street 
and  two  railroad  tracks,  with  footwalks  on  an  upper  floor.  The 
under  clearance  of  the  bridge  when  down,  was  50  feet,  and  104  feet 
when  at  its  highest  position.  The  first  prize  in  the  competition  was 
awarded  to  J.  W.  Schwedler,  of  Berlin,  for  a  three  span  bridge  with 
a  central  double  bascule,  somewhat  similar  to  that  afterwards  used 
for  the  Tower  Bridge  at  London.  But  Captain  Moorsom's  design 
was  notable  for  being  the  first  important  one  of  its  kind,  being  used 
even  now  as  a  model  for  succeeding  ones.  Its  estimated  cost  was 
SI  ,184,000.  In  1867  a  design  was  made  by  Oscar  Roper  of  Hamburg, 
for  a  bridge  over  a  wide  river,  containing  a  300  foot  lift  span,  which 
could  be  raised  to  allow  ocean  sailing  ships  to  pass  under  it.  Another 
large  bridge  was  proposed  in  1872  by  T.  E.  Laing,  for  carrying  a 
railroad  over  the  River  Tees  at  Newport  near  Middlesbrough, 
England.  The  centre  lifting  span  had  a  width  of  200  feet,  and 
under  clearance  of  50  feet  when  down,  and  90  feet  when  raised. 
The  principals  were  heavy  plate  girders  200  feet  long — very  bold 
indeed  for  the  time — rising  between  stone  towers  which  had  recesses 
for  the  counterweights.  Provision  was  made  for  a  variation  in  the 
counterweight  by  adding  or  withdrawing  water,  supply  tanks  for 
the  purpose  being  placed  high  up  in  the  towers.  To  lift  the  bridge, 
water  would  be  run  into  the  tanks  on  the  counterweight,  when  it 
would  automatically  rise,  and  to  lower  it  again,  the  water  was 
withdrawn  until  the  balance  weights  were  lighter  than  the  span, 
causing  it  to  descend.  Sand  glasses  were  proposed  for  gauging  the 
amount  of  water  needed.  Another  elaborate  design  for  a  lift  bridge 
appeared  in  1878,  in  a  bridge  of  five  spans  to  cross  the  Scheldt  at 
Antwerp,  the  work  of  M.  H.  Matthyssens.  It  had  two  shore 
openings  of  178  feet  (59  meters),  two  over  the  main  channel  of  472 
feet  (150  meters),  and  a  central  lift  with  clear  width  and  height  of 
131  feet  (40  meters).  All  trusses  had  curved  upper  chords,  and 
multiple  web  members,  there  being  provision  for  a  19  foot  road, 
two  rail- tracks  and  double  sidewalks.  The  towers  were  carried  out 
in  stone  the  tops  being  connected  in  both  directions  by  struts  with 
curved  lower  members.  The  fixed  spans  and  the  centre  one  when 
down,  had  an  under  clearance  of  43  feet,  sufficient  to  pass  all  ordin- 
ary craft.  These  four  designs  for  lift  bridges  at  Cologne,  Hamburg, 
Newport  and  Antwerp  made  with  masonry  towers  and  before  the 
days  of  structural  steel,  are  the  prototypes  for  many  important 
and  later  ones,  and  contain  much  of  artistic  merit. 

Going  back  a  few  years  to  France,  it  is  found  that  a  lift  bridge 
of  unusual  design  over  the  Ourcq  Canal  at  Paris,  on  a  slight  skew, 
was  completed  in  1868  to  carry  a  line  of  railway,  the  height  of  which 
was  only  14  inches  above  the  surface  of  a  28  foot  channel.  A  lifting 
platform  was  suspended  between  two  brick  arches  28  feet  apart, 
having  a  clear  span  of  66  feet  and  21  feet  rise,  and  when  raised,  the 
under  clearance  beneath  the  platform  was  16>2  feet.  The  brick 
arches  were  6>2  feet  wide  and  3>^  feet  thick  at  the  crown,  and  brick 
pillars  at  each  end  with  guide  grooves  for  the  counterweight  sup 
ported  the  4  foot  sheaves  and  the  shore  ends  of  lattice  girders  The 


6  VERTICAL  LIFT  BRIDGES 

weight  of  moving  platform  was  22  tons,  which  was  balanced  by 
an  equal  amount  of  counterweight,  suspended  by  chains  over  sheaves, 
on  the  face  of  which  were  depressions  to  prevent  the  chains  from 
slipping.  Stairs  at  each  end  led  up  to  an  elevated  foot  walk  which 
was  always  accessible.  The  platform  remained  up  at  all  times 
excepting  when  wanted  down  for  the  passage  of  a  train,  after  which  it 
was  raised  again.  It  was  operated  by  hand  power.  Another  lift 
bridge  somewhat  similar  to  the  last,  was  placed  over  the  Rhine- 
Marne  Canal  in  1872,  overhead  girder  supports  being  used  instead 
of  brick  arches.  The  canal  had  a  width  of  only  12  meters,  but  the 
distance  between  the  approaches,  including  the  two  tow  paths, 
wa~>  24  meters,  and  the  over-all  length  29  meters.  Suspenders 
attached  to  the  ends  of  brackets  on  the  main  girders,  passed  over 
sheaves  on  the  upper  framing,  and  were  attached  to  counterweights 
at  the  ends.  The  framing  lacked  rigidity,  as  it  was  braced  trans- 
versely only  by  the  stairs  leading  up  to  the  upper  level. 

One  of  quite  different  design  was  erected  in  1873  at  Dublin  to 
carry  a  line  of  railway  over  the  Royal  Canal  entrance  at  Spencer 
Dock,  on  a  skew  of  25  degrees.  It  is  described  as  weighing  14  tons, 
the  bridge  being  balanced  with  counterweight  consisting  of  tanks 
filled  with  water,  the  tanks  when  empty  being  one  ton  lighter  than 
the  bridge,  and  when  loaded  with  two  tons  of  water,  one  ton  heavier. 
It  could  be  raised  by  hand  power  to  a  height  of  1%  feet,  which  left 
room  enough  beneath  for  barges.  The  width  was  12  feet  and  the 
lattice  girders  were  40  feet  long,  though  the  water  opening  was  only 
14^  feet.  It  was  the  first  bridge  on  the  site,  and  has  sinc^  been 
replaced. 

After  completing  the  Erie  Canal  in  1825,  elevated  fixed  bridges 
similar  to  those  in  England  and  France,  had  been  used,  with  ap- 
proach grades  of  7  to  8  per  cent.,  the  grades  being  afterwards  reduced 
and  lengthened,  with  slopes  not  exceeding  4  to  5  per  cent.  A  few 
swing  bridges  with  center  piers  were  then  tried  but  none  of  them 
were  satisfactory.  The  need  of  more  efficient  ones  became  evident, 
and  in  1872  Squire  Whipple  began  his  investigations  for  commodious 
ones.  He  found  that  a  center  pier  was  too  great  a  hindrance  to  navi- 
gation in  a  canal  only  60  feet  wide,  and  to  place  a  turn  table  on  one 
side,  would  obstruct  valuable  wharfage  and  business  property. 
He  therefore  designed  a  vertical  lift  bridge  on  which  a  patent  was 
granted  to  him  in  1872.  The  first  bridge  at  Hotel  Street,  Syracuse, 
was  completed  in  1874,  and  in  1907  was  still  in  service.  The  plat- 
form, 60  feet  long  and  18  feet  wide,  was  the  only  lifting  part.  It  was 
suspended  by  rods  10  feet  apart,  from  the  fixed  overhead  trusses 
supported  on  end  towers,  the  rods  moving  up  inside  the  hollow 
columns  of  the  trusses.  The  bridge  crossed  the  canal  and  tow  path, 
the  total  length  of  trusses  being  72  feet.  The  counterweight  con- 
sisted of  twelve  long  cast  iron  boxes  nine  inches  square,  filled  with 
pig  iron,  six  of  them  hanging  on  each  side,  and  weighing  when  empty 
800  pounds.  The  whole  moving  weight,  including  counterweight, 
was  20  tons.  A  tread  wheel  9  feet  in  diameter  was  used  for  raising 
two  weights,  one  of  which  was  for  lifting  and  the  other  for  lowering 


VERTICAL  LIFT  BRIDGES  7 

the  bridge,  both  of  which  merely  to  overcome  friction,  were  twice 
as  large  as  actually  needed.  Their  movement  was  regulated  by  a 
ratchet  wheel  like  that  on  a  clock.  The  rope  sheaves  were  3  feet 
in  diameter  for  ^4 -inch  rope,  turning  on  2v4  inch  axles.  In  the 
same  year  (1874)  a  patent  was  granted  to  A.  J.  Post  of  Jersey  City 
for  a  "vertical  sliding  bridge  guided  by  columns  at  the  four  corners, 
operated  by  flexible  connecting  belts  between  the  towers,  driven  by 
a  windlass  and  crank."  It  was  counterweighted  by  heavy  blocks 
hanging  in  the  towers. 

Many  other  lift  bridges  began  to  appear  in  the  principal  towns 
along  the  Erie  Canal,  among  them  being  the  Allen  Street  lift  at 
Rochester  (1878),  which  was  somewhat  similar  to  that  at  Utica, 
having  overhead  girders  on  corner  towers  with  a  suspended  counter- 
weighted  platform.  Instead  of  hand  power,  it  was  operated  by 
hydraulic  motors,  which  transmitted  power  to  an  overhead  shaft 
with  pulleys.  Other  similar  ones  were  soon  afterwards  built  in  the 
same  city. 

Benefiting  by  the  experience  of  American  engineers,  a  lift 
quite  similar  in  principle  to  those  at  Utica  and  Rochester  was  erected 
in  1878  at  Calcutta,  India,  with  a  span  of  116  feet  over  a  tow  path 
and  110  feet  waterway.  The  principal  difference  in  the  designs  was 
in  the  corner  towers,  which  at  Calcutta  were  of  stone,  giving  a  much 
finer  and  more  substantial  appearance  than  the  lighter  ones  of  metal 
used  in  America.  The  two  lines  of  trusses  were  18  feet  deep,  and  from 
them,  a  platform  was  suspended  which  could  be  raised  about  13 
feet,  providing  a  head  room  of  20  feet  at  high  water.  The  counter- 
weight was  two  tons  heavier  than  the  suspended  platform  causing 
the  bridge  to  rise  and  remain  open,  but  the  addition  of  about  4 
tons  of  water  to  the  platform  tanks  reversed  the  overbalance  and 
caused  the  platform  to  descend,  the  required  overbalance  being  just 
enough  to  overcome  the  friction.  In  this  respect  it  was  similar 
to  the  one  of  1873  over  the  Royal  Canal  at  Dublin.  It  carried  a 
single  line  of  railway  and  cost  $51,500.,  the  maintenance  cost  being 
$450.  per  year.  W.  D.  Bruce  was  engineer.  Another  very  fine 
European  design  appeared  in  1883,  the  work  of  J.  Pitt  Bayley,  for 
crossing  the  Thames  near  the  Tower  of  London.  The  plans  showed 
four  deck  arches  of  175  feet  span,  and  a  centre  lift  between  a  pair 
of  great  metal  ribs,  the  clear  width  and  height  of  the  open  passage 
being  70  and  90  feet  respectively.  Its  width  was  54  feet,  and  length 
880  feet,  the  estimated  cost  with  machinery  and  approaches  being 
500,000  pounds  sterling. 

In  the  same  year  (1883)  the  city  of  Rochester  erected  another 
hydraulic  lifting  bridge  over  the  Erie  Canal,  at  Lyell  Ave.  quite 
similar  to  the  one  of  1878.  The  platform  was  78  feet  long,  18  feet 
wide  with  a  projecting  5  feet  walk  at  each  side,  and  the  overhead 
bridge  spanning  the  canal  and  tow  path  at  one  side  on  a  slight  skew, 
was  94  feet  long.  Another  of  1884  over  the  canal  at  Syracuse, 
carries  two  tracks  of  the  West  Shore  Railway,  and  it  is  on  a  skew, 
having  a  length  of  104  feet,  but  it  is  different  to  the  last,  in  that  the 
whole  bridge  rises  and  not  simply  the  floor.  The  trusses  are  23  feet 


8  VERTICAL  LIFT  BRIDGES 

with  double  web  systems,  and  are  suspended  by  wire  rope  passing 
over  sheaves  7>£  feet  in  diameter.  The  counterweight  boxes  are 
6  feet  by  6  feet  by  9  feet,  filled  with  pig  iron,  the  weight  of  the  bridge 
being  146  tons  and  counterweight  140  tons  more.  Previous  to  this 
time,  the  floors  were  the  only  lifting  parts  of  railroad  lift  bridges  on 
the  Erie  Canal.  The  towers  of  the  last  bridge  were  36  feet  high, 
and  the  span  can  be  raised  13  feet  between  them.  Albert  Lucius 
was  engineer.  The  Salina  Street  hydraulic  lift  bridge  near-by  is  similar 
to  the  one  in  Utica,  with  a  crossing  angle  of  56  degrees,  and  a  span 
length  of  83  feet.  It  is  25  feet  wide,  with  two  6  foot  walks,  the 
floor  weight  of  60  tons  being  counter-balanced  by  semi-cylinder 
troughs  filled  with  pig  iron,  suspended  by  eighteen  wire  ropes  three- 
quarters  of  an  inch  in  diameter,  over  24  inch  pulleys,  the  floor  being 
capable  of  rising  9  feet. 

The  most  elaborate  system  of  navigable  inland  canals  anywhere 
in  the  world  is  in  France,  where  not  less  than  3,000  miles  of  such  water- 
ways are  operated  under  government  direction.  But,  as  previously 
described,  France  and  England  generally  used  fixed  overhead  bridges 
with  graded  approaches,  instead  of  movable  ones.  Departures  from 
the  usual  custom  were,  however,  introduced  in  France  at  the  cities 
of  Paris  and  Dijon,  a  very  attractive  little  bridge  being  completed 
in  1886  in  the  reconstruction  of  Bassin  Villette-Canal  St.  Denis — 
in  Rue  de  la  Crimee,  Paris.  A  lift  bridge  was  preferred  to  a  rotating 
one,  as  the  tail  end  of  the  swing  span  wotild  have  interfered  with 
existing  approaches.  The  canal  is  30  meters  wide,  but  the  opening 
at  the  site  is  narrowed  to  half  that  width,  making  the  bridge  20  meters 
long,  and  leaving  space  at  each  side  of  the  canal  for  boats  at  the  docks. 
The  bridge  is  ly£  meters  wide  and  the  maximum  lift  4>^  meters,  but 
at  one  side  is  an  elevated  fixed  foot  bridge  with  a  79  foot  span, 
approached  at  the  end  by  steps.  The  main  supports  are  lattice 
girders  and  the  platform  is  suspended  by  means  of  chains  with  1% 
inch  links  passing  over  8  foot  sheaves  at  the  top  of  independent 
corner  towers  which  are  25  feet  high  and  27  to  33  inches  in  diameter. 
The  counterweights  descend  into  pits,  the  motion  ceases  when  they 
reach  the  bottom.  It  is  operated  by  hydraulic  pistons  under  the 
center  of  the  end  floor  beams,  and  is  provided  also  with  hand  power 
machinery,  with  pinions  working  on  vertical  racks  placed  against 
the  towers.  At  each  corner  are  safety  ratchets  which  would  engage 
teeth  on  the  towers  if  the  suspenders  should  fail.  Its  total  weight 
is  241  tons,  and  cost  5,000  pounds  sterling.  It  replaced  the  one 
of  1868  in  which  a  platform  was  suspended  between  brick  arches. 

Another  bridge  at  Larrey  in  the  city  of  Dijon,  erected  1890 
over  the  Burgundy  Canal,  replaced  an  old  stone  arch  of  1800.  The 
span  is  32  feet,  crossing  a  20  foot  canal  and  two  tow  paths,  and  it  is 
lifted  4  feet  by  hydraulic  cylinders,  the  under  clearance  when  raised 
being  slightly  less  than  8  feet.  The  pavement  is  one,  peculiar  to 
the  canal  bridges  of  France,  and  consists  of  old  discarded  collier 
ropes  of  1>^  by  7  inch  flat  manilla,  laid  crosswise  over  the  plank 
flooring.  It  is  said  to  wear  well,  but  absorbs  a  lot  of  water  and 
causes  the  weight  to  vary,  seriously  affecting  the  counterbalance. 


VERTICAL  LIFT  BRIDGES  9 

At  each  end  are  steps  leading  up  to  platforms  from  which  the  bridge 
is  accessible  when  raised,  so  that  predestrians  may  cross  at  all  times. 
A  highway  bridge  184  feet  long  in  three  spans,  crossing  an  arm  of 
the  Danube  at  the  Alt-Ofen  Dockyard,  has  a  centre  lifting  span  of 
68  feet.  The  road  is  17  feet  wide  and  the  lattice  side  girders  are  7 
feet  deep,  moving  between  braced  metal  towers  at  each  corner, 
which  extend  28  feet  above  the  floor.  The  counterweight  of  44  tons 
is  hung  by  chains  over  pulleys,  and  the  whole  can  be  raised  13  feet 
by  a  windlass  and  hand  power  near  the  span  centre,  giving  a  clear 
headroom  of  42  feet  above  low  water.  It  was  erected  under  the 
direction  of  Peter  Remel,  and  cost  5,648  pounds  sterling. 

During  the  year  1890  a  design  appeared  in  Europe  for  a  long 
bridge  with  a  succession  of  cantilevers,  in  one  span  of  which  a  lift 
bridge  replaced  the  usual  suspended  part.  Towers  were  supported 
above  the  deck  on  the  ends  of  the  adjoining  cantilever  arms,  and  the 
counter  weights  hung  inside  of  the  two  near-by  river  piers  which  were 
60  meters  apart,  similar  designs  with  bascules  instead  of  lifts,  being 
patented  in  America,  some  years  later.  In  the  same  year  a  patent 
was  granted  in  the  United  States  to  J.  F.  Alden,  for  a  vertical  lift 
bridge  with  counter- weighted  platform  hung  by  rods,  the  whole 
being  worked  by  electric  motors. 

The  greatest  impetus  to  the  design  of  movable  bridge  in  America 
began  in  1892  with  the  competition  for  a  bridge  over  the  channel 
at  Duluth,  one  of  the  twelve  designs  submitted  being  a  patented 
one  by  Dr.  J.  A.  L.  Waddell  for  a  lift  bridge  of  250  feet  span,  rising 
to  a  clear  height  of  140  feet  above  water,  the  total  estimated  cost 
being  $125,000.  The  trusses  were  shown  25  feet  apart  for  a  line  of 
steam  railway  and  two  walks,  and  outside  the  trusses  were  13  feet 
roads  on  cantilever  brackets  for  carriage  and  trolley  travel.  The  sus- 
pended weight  was  about  500  tons,  which  was  counterbalanced, 
making  the  moving  mass  1,000  tons.  Provision  was  made  for  raising 
and  lowering  it  again  by  electric  power,  all  in  the  space  of  five 
minutes.  Sheaves  were  15  feet  diameter  for  forty-eight  1^  inch 
ropes  loaded  to  only  one  tenth  of  their  capacity.  Towers  were  not 
connected  at  their  tops  as  were  those  of  Cologne,  Newport  and  Ant- 
werp, but  stood  independent  of  each  other.  The  prize  in  this 
competition  was  awarded  on  a  double  retractile  design,  but  as  its 
cost  was  excessive,  the  lift  bridge  was  recommended  and  accepted, 
though  a  bridge  of  another  form  was  finally  built. 

On  June  30,  1892,  the  South  Halsted  Street  swing  over  the  East 
Fork  of  the  South  branch  of  Chicago  River  in  Chicago,  completed 
twenty  years  before,  was  demolished  by  collision  with  a  steamer, 
and  as  it  was  a  principal  thoroughfare,  immediate  action  was  taken 
for  its  restoration.  Encouraged  by  the  favor  shown  for  a  lifting 
bridge  at  Duluth,  the  engineers  of  that  project  submitted  to  the 
city  of  Chicago  a  modification  of  their  former  plans,  which  were 
accepted,  and  a  contract  was  awarded  to  the  Pittsburg  Bridge  Co. 
on  a  tonnage  basis  and  estimated  quantities,  revised  plans  being 
prepared  by  the  engineers  in  less  than  thirty  days.  The  length  of 
lifting  span  is  130  feet,  crossing  a  channel  of  118  feet  on  a  slight 


10  VERTICAL  LIFT  BRIDGES 

skew  of  10  degrees.  Trusses  are  40  feet  apart  on  centres,  leaving 
a  clear  roadway  of  36  feet,  outside  of  which  are  10  foot  walks  at 
each  side,  making  a  total  width  of  60  feet.  It  was  proportioned  for 
a  live  load  of  4,500,  and  a  dead  load  of  4,000  pounds  per  lineal  foot. 
The  towers  at  each  side  are  40  feet  square  at  the  base  and  200  feet 
high,  the  top  of  pole  being  217  feet  above  water.  Rear  tower  legs 
have  adjustment  to  provide  against  any  possible  settlement  of 
foundations,  each  leg  having  a  ball  and  socket  bearing  with  10  inch 
screws.  Comparison  made  at  Duluth  showed  that  no  saving  would 
result  from  using  an  elevated  fixed  span,  with  suspended  floor, 
and  the  whole  span  is  therefore  lifted  140  feet,  leaving  a  clear  under 
height  of  155  feet  above  water.  It  rises  at  a  maximum  velocity  of 
4  feet  per  second,  the  whole  weight  of  bridge  and  platform  weighing 
290  tons,  being  suspended  by  thirty-two  wire  cables,  1>£  inch  diam- 
eter, eight  at  each  corner,  the  power  for  moving  being  applied  by 
a  seven-eighth  inch  wire  rope.  The  suspension  cables  pass  over 
12-foot  sheaves  turning  on  12-inch  axles  at  the  top  of  towers,  and  are 
balanced  by  cast  iron  counterweight  blocks  10  by  12  inches  by  9 
feet,  moving  between  vertical  angle  guides,  the  whole  weight  of 
moving  parts  being  600  tons,  the  cables  and  counterweight  chains 
weighing  20  tons.  Beneath  the  floor  are  four  water  ballast  tanks 
having  a  capacity  of  19,000  pounds,  for  the  purpose  of  regulating 
an  exact  balance,  and  in  case  of  failure  of  the  machinery,  the  bridge 
can  be  operated  by  water-weight  supplied  from  a  reservoir  on  the 
top  of  one  tower,  filled  by  pumps  in  the  engine  room,  all  water 
tanks  having  steam  coils  to  prevent  their  freezing.  The  original 
design  called  for  the  use  of  two  65  h. p.  electric  motors,  but  the  city  of 
Chicago  required  a  steam  engine  plant  of  115  h.p.  instead.  As  a 
steam  plant  in  the  towers  would  have  caused  too  great  vibration, 
the  engine  room  was  placed  under  ground.  The  cost  of  the  steam 
power  operation  and  maintenance,  however,  was  found  to  be  excessive, 
and  in  1907  electric  motors  were  substituted  for  steam.  Operation 
by  steam  had  required  the  services  of  three  engine  men,  two  signal 
men,  four  police  and  one  coal  shoveller,  or  ten  men  all  together, 
their  combined  wages  being  $1,000  per  month.  In  addition  to  this 
there  was  $170.  per  month  expended  for  coal,  the  boilers  being  kept 
going  at  all  times,  whereas  the  cost  of  electric  power  for  intermittent 
service  proved  to  be  only  $50.  per  month,  with  the  services  of  only 
one  tender  while  two  had  formerly  been  needed  with  steam.  Alto- 
gether the  change  to  electric  power  resulted  in  a  saving  of  $3,240. 
per  year  in  the  operating  expenses.  The  bending  of  the  cables 
consumed  in  itself  no  less  than  6  h.p.  The  comparison  just  given, 
is,  however,  hardly  fair,  for  it  was  found  that  26  tons  of  sand  that 
was  placed  under  the  pavement  to  crown  the  road,  had  not  been 
counterweight ed,  and  this  had  to  be  lifted  at  each  operation,  in 
addition  to  overcoming  inertia  and  friction.  Buffer  cylinders  12 
inches  in  diameter  and  4  feet  stroke  are  provided,  glycerine  being 
used  to  avoid  freezing,  but  the  upper  bumpers  are  ineffective  as 
the  over  head  girders  where  they  strike  the  tower  framing  have  for 
several  years  been  bent  and  battered,  greatly  injuring  the  appearance. 


VERTICAL  LIFT  BRIDGES  11 

The  itemized  cost  of  the  bridge  is  as  follows:— 

Substructure $84,600 

Superstructure 81,400 

Machinery  and  engines 50,000 

$216,000 

It  is  claimed  by  the  designer  that  the  bridge  could  be  repro- 
duced at  a  cost  of  $50,000  less  than  that  of  the  above  figures,  while 
Mr.  W.  W.  Curtis,  the  resident  engineer  in  charge,  reported  that  it 
need  not  cost  again  more  than  $175,000.  The  use  of  steam  power 
with  engines  greatly  increased  both  first  cost  and  maintenance,  though 
in  any  case  the  lifting  of  a  whole  span  to  so  great  a  height  would 
consume  a  large  amount  of  energy.  The  weight  of  metal  in  the  span 
is  250  tons,  and  the  whole  weight  with  counterweight  is  675  tons. 
When  inspected  recently  by  the  writer,  it  had  no  street  gates  or 
guards  of  any  kind. 

Soon  afterwards  (1894)  the  same  engineers  made  plans  for  a 
somewhat  similar  bridge  over  the  Missouri  River  at  Kansas  City, 
using  the  piers  of  the  proposed  Winner  Bridge  which  had  been 
abandoned.  Piers  were  to  be  cut  off  52  feet,  making  it  a  low  level 
bridge,  and  provision  was  made  for  two  railroad  tracks  on  each  deck 
with  trusses  32  feet  apart,  and  double  wagon-ways  and  walks  on  the 
upper  deck,  the  total  width  being  65  feet.  Metal  towers  are  pierced 
above  piers  No.  4  and  5  near  the  south  side,  with  an  elevated  fixed 
span,  and  suspended  lifting  floor  weighing  925  tons,  all  of  which 
is  counterweighted  at  every  panel  with  cast  iron  blocks  supported 
by  one  hundred  and  twelve  1^-inch  steel  wire  cables,  over  fifty-six 
cast  iron  sheaves  5  feet  diameter.  The  deck  can  be  lifted  45  feet 
and  can  be  worked  by  eight  men.  The  hangers  which  support  the 
lower  deck  will  rise  through  the  main  posts  of  the  fixed  overhead 
span  when  the  deck  is  lifted,  as  was  done  on  those  over  the  Erie 
Canal  in  1874. 

In  1894-95  several  new  lift  bridges  were  placed  over  the  Erie 
Canal  at  Rochester  and  Syracuse.  Two  adjoining  overhead  fixed 
bridges  at  Rochester  were  removed  in  1875,  and  a  single  swing 
substituted,  but  in  1889  it  was  replaced  by  two  lifting  spans.  Bridge 
service  on  the  canal  was  still  unsatisfactory,  and  in  1894,  before 
rebuilding  the  West  Main  St.  bridge  at  Rochester,  the  state  of  New 
York  sent  a  representative  to  Europe  to  investigate  similar  con- 
ditions there,  special  attention  being  given  to  the  bridges  in  Holland 
where  canals  are  abundant.  The  old  Dutch  Portal  bridge  with  over- 
head balance  beams  was  found  to  be  the  prevailing  type,  though 
some  of  the  newer  bridges  were  being  built  as  double  bascules. 
Returning  to  America,  this  representative  reported  quite  fully  on 
European  bridges  as  he  found  them,  and  improvements  that  were 
appropriate  for  American  canals  were  adopted.  The  Emerson 
St.  lift  at  Rochester,  finished  1895,  was  then  the  longest  span  over  the 
canal,  the  distance  between  end  columns  being  112  feet,  and  the  floor 
only  is  raised,  like  Whipple's  first  one  of  1874  at  Utica.  A  very 
serious  accident  happened  to  another  one  at  Rochester  in  November 


12  VERTICAL  LIFT  BRIDGES 

1896  when  the  whole  movable  structure  of  the  Caledonia  Avenue 
bridge  fell  from  its  highest  position  upon  a  passing  canal  boat, 
fortunately  without  loss  of  life.  It  was  to  prevent  such  an  accident 
as  this,  that  safety  appliances  were  added  to  the  Ourcq  Canal  lift 
at  Rue  de  Crimee,  which  was  previously  described.  On  March 
7,  1898,  another  bridge  over  a  dry  bed  of  the  Erie  Canal  at  Whites- 
boro  St.,  Utica,  failed,  killing  one  person.  It  weighed  about  50  tons 
and  is  said  to  have  been  built  forty  years  before,  but  had  been  con- 
demned and  closed  for  a  year.  It  is  interesting  here  to  note  the 
heroic  measures  used  at  Watervliet,  N.Y.,  to  meet  operating  expenses. 
The  draw  was  raised  and  left  up  until  the  two  adjoining  towns  paid 
the  bridge  tenders'  wages  which  were  a  year  in  arrears. 

The  second  important  event  in  America  to  cause  progress  in 
the  design  of  movable  bridges  was  the  competition  for  one  over 
Newton  Creek  at  Vernon  Avenue  in  1896,  when  among  many  others, 
a  lifting  design  was  submitted  by  F.  S.  Williamson,  similar  to  that 
at  Halsted  Street,  Chicago,  with  an  estimated  cost  of  $200,000.  A 
contract  was  awarded  to  the  King  Bridge  Company  for  its  con- 
struction at  a  price  of  $418,000,  which  agreement  was  afterwards 
cancelled. 

No  lift  bridges  worthy  of  notice  had  been  erected  or  proposed 
in  other  countries  since  the  completion  of  those  in  France  in  1886 
and  1890,  until  1896,  when  a  small  one  was  placed  over  Murray 
River  at  Swan  Hill,  Australia,  between  New  South  Wales  and 
Victoria,  with  a  14  foot  highway  and  a  58  foot  span.  The  whole 
bridge  weighed  34  tons  and  cost  only  $44,500,  and  is  operated  by 
one  man  hand  power.  There  are  no  masted  ships  on  the  river  and 
the  maximum  lift  is,  therefore,  only  30  feet.  The  design  was  the 
work  of  Mr.  Percy  Allen. 

In  the  four  years  following  1899,  five  other  lifts  were  placed 
over  the  Erie  Canal  at  Utica,  Lockport,  Rochester,  and  Canajoharie. 
On  the  Schuyler  St.  lift  at  Utica  (1899)  with  a  span  of  84  feet,  the 
floor  only  is  raised.  The  Lockport  lift,  111  feet  long  and  32  feet 
wide,  is  worked  by  hydraulic  power  from  the  city  mains  under 
pressure  of  90  pounds  per  square  inch,  the  piston  rod  being  attached 
to  a  cast  steel  rack  gearing  with  an  8  inch  pinion,  all  machinery 
being  below  the  floor,  but  it  is  equipped  also  for  hand  power.  The 
towers  are  24  feet  high,  supporting  cables  of  cast  steel  rope,  support- 
ing the  cast  iron  counterweight.  One  at  West  Avenue,  Rochester 
(1902)  with  a  span  of  139^  feet,  is  the  longest  over  the  canal,  and  air- 
tight pontoons  are  used  instead  of  counterweight,  similar  to  that 
used  the  same  year  for  a  direct  lift  over  the  Elbe-Trave  Canal  at 
Launenburg,  Germany,  and  at  Wattrelos,  two  years  later.  Other 
similar  bridges  are  at  Plymouth  Avenue,  Rochester,  1903,  and  Church 
St.,  Canajoharie,  1904.  The  lift  bridge  over  a  street  subway  at 
Friedrichstrafse,  Dresden,  is  quite  different  from  the  usual  forms, 
the  upper  road  being  lifted  about  5  feet  by  means  of  levers  to  which 
segments  are  attached,  on  which  hand-operating  pinions  are  worked 
by  winches. 

Another  important  American  waterway,  the  Miami  and  Erie 


VERTICAL  LIFT  BRIDGES  13 

Canal,  which  is  used  for  barges  only,  had  for  many  years  been 
equipped  with  automatic  closing  swing  bridges,  mostly  of  the 
"Smith  Bridge  Co."  type,  but  in  1900  a  new  form  was  erected  at 
Middletown,  Ohio,  34  feet  long  and  66  feet  wide,  crossing  the  canal 
and  tow  path,  the  floor  being  raised  about  9  feet  for  the  passage  of 
boats.  The  moving  part  weighing  46  tons,  is  balanced  by  two 
counterweights  of  23  tons  each,  lifted  by  an  electric  motor  beneath 
the  floor,  the  maximum  armature  speed  being  1,100  revolutions  per 
minute.  Another,  and  very  economical  design  of  lift  bridge  for 
small  waterways,  was  prepared  by  the  writer  in  1904  in  the  compe- 
tition for  one  to  cross  the  same  canal  at  New  Bremen,  Ohio.  The 
bridge  has  a  28  foot  roadway  and  two  6  foot  walks,  with  plank 
floor  and  steel  joist.  It  consists  of  an  ordinary  deck  plate-girder 
highway  bridge  suspended  and  counterweighted  by  means  of  wire 
ropes  passing  over  sheaves  at  the  four  corners,  the  counterweights 
moving  up  and  down  inside  the  towers.  The  fixed  end  of  the  rope 
is  attached  to  the  overhead  lattice  girder,  and  produces  bending 
therein.  The  bridge  is  raised  and  lowered  by  means  of  four  pinions 
working  on  racks  attached  to  the  corner  towers.  These  pinions 
are  connected  through  a  series  of  shafts  and  gears  to  a  10  h. p.  electric 
motor  placed  beneath  the  floor,  the  motors  and  machinery  being 
enclosed  and  protected  from  the  weather.  For  oiling  or  inspection, 
it  can  be  reached  through  a  movable  panel  in  the  floor.  The  con- 
troller is  placed  against  the  railing  and  is  likewise  enclosed,  electric 
current  being  taken  from  the  street  wires.  The  quantities  of  material 
in  the  superstructure  are  as  follows : — 

Riveted  steel  work  37  tons 

Machinery .     5 

Counterweight  iron 20 

Steel  joist 6     " 

Electric  motor  and  equipment. 

Lumber,  6,000  feet  b.m. 

Estimated  cost,  $5,300. 

Generally,  all  forms  of  lift  bridges  require  expensive  counter- 
weights. In  this  case,  the  cost  of  counterweights  alone  is  about 
20  per  cent,  of  the  entire  cost  of  the  superstructure.  In  nearly  all 
other  forms  of  lift  bridges,  the  cost  of  counterweight  greatly  exceeds 
this  amount.  In  South  Halsted  Street  lift  bridge  at  Chicago,  the 
total  weight  of  metal  in  the  structure  is  675  tons,  and  of  this  amount, 
290  tons,  or  43  per  cent,  is  counterweight.  This  expensive  feature 
applies  not  only  to  direct  lift  bridges,  but  also  to  all  forms  of  bascule 
bridges,  which  are  counterweighted  to  a  greater  or  less  extent. 
Swing  bridges  over  canals  with  only  one  waterway,  have  either  one 
half  of  the  bridge  over  the  land  where  it  is  not  required  excepting 
for  a  counterbalance,  or  have  one  short  arm  loaded  with  cast  iron 
or  concrete,  either  of  which  arrangements  are  expensive.  The 
retractile  draw  similar  to  that  at  Summer  St.,  Boston,  which  rolls 
back  on  a  track  at  an  angle  of  45  degrees  to  the  canal,  is  likewise 
expensive,  inasmuch  as  a  large  part  of  the  bridge  must  be  built  over 


14  VERTICAL  LIFT  BRIDGES 

the  land,  in  order  to  give  room  for  mounting  it  on  trucks.  The 
trucks  and  track,  and  the  excavated  recess  for  the  bridge  when  it  is 
rolled  back  into  its  open  position,  all  add  to  its  cost.  Swing  bridges 
with  small  roadways,  such  as  commonly  used  over  waterways,  are 
not  suitable  for  wide  roadways  with  sidewalks.  The  ordinary 
drawbridge  over  the  Miami  and  Erie  Canal  through  the  rural  dis- 
tricts, has  a  roadway  12  to  16  feet  in  width,  and  is  a  bob-tail  swing. 
It  is  opened  by  the  pressure  of  the  boat  against  it,  and  after  the  boat 
or  barge  has  passed,  the  bridge  swings  back  again  automatically 
into  its  closed  position.  A  bumping  timber  backed  with  springs 
is  bolted  to  the  side  of  the  bridge  to  receive  the  blow  of  the  barge 
as  it  strikes  the  bridge  and  opens  it.  These  bridges  are  very  common 
along  the  canal,  and  are  satisfactory  for  rural  districts  and  light 
travel.  But  where  wide  roadways  and  walks  are  needed  to  accom- 
modate city  travel,  they  are  then  no  longer  practicable. 

The  normal  width  of  the  Miami  and  Erie  Canal  is  50  feet, 
allowing  three  boats  each  15  feet  wide,  to  pass  each  other.  But  at 
crossings,  the  canal  is  frequently  narrowed  to  about  32  feet,  and  the 
cost  of  the  draw  bridge  reduced  accordingly.  The  estimated  costs 
of  other  forms  of  opening  bridges  for  the  same  location,  are  as  fol- 
lows, and  in  each  case  the  estimate  is  based  on  providing  a  fifty  foot 
clear  waterway.  A  double  leaf  bascule  with  leaves  meeting  at  the 
centre,  and  towers  at  each  side,  with  a  platform  60  feet  long,  would 
cost  $5,700.  A  single  retractile  draw,  similar  to  that  at  Summer 
Street,  Boston,  would  cost  $7,300.  In  this  case  the  length  of  plat- 
forms required  is  75  feet  on  one  side  and  115  feet  on  the  other.  A 
bob-tail  plate  girder  swing,  with  sand  counterweight,  would  cost 
$5,400.  The  length  of  platform  in  this  case  would  be  90  feet.  A 
revolving  truss  swing  with  equal  arms,  and  a  platform  140  feet  long, 
would  cost  $6,700.  Comparative  estimates  are  therefore  as  fol- 
lows : — 

Tower  direct  lift  bridge $5,200 

Double  leaf  bascule 5,700 

Single  retractile  draw 7,300 

Bob-tail  plate  girder  swing 5,400 

Revolving  truss  swing,  equal  arms 6,700 

The  bridge  was  designed  to  open  by  electric  power  in  one 
minute,  and  it  appears  to  fulfil  all  the  requirements  for  the  given 
location.  Gates  should  be  used  at  each  end  of  the  bridge,  to  be 
lowered  or  closed  before  the  bridge  is  opened.* 

The  forty-one  movable  railroad  bridges  in  New  York  State 
were  examined  in  1907  by  engineers,  under  the  direction  of  the 
State  Board  of  Railroad  Commissioners,  with  a  view  to  making 
such  changes  as  might  be  necessary  to  insure  public  safety,  and  the 
conclusions  and  report  of  this  board  contain  many  valuable  pro- 
visions. (Engineering  Record,  July  10th,  1907). 

Several  comparatively  small  lifts  in  other  countries  are  those  at 
Haslar,  Nyasaland,  and  Edinburgh,  all  other  ones  of  any  importance 

*Lift  Bridges  for  Small  Waterways.      H.  G.  Tyrrell  in  Electrical  Review,  Dec.  31st,  1904. 


VERTICAL  LIFT..R££'  *.•'  ' '%  :'•:  *  15 

being  in  America.  That  over  the  entrance  to  Portsmouth  Harbor, 
at  Haslar,  England,  is  a  small  affair  of  less  than  28  feet  span,  with 
towers  framed  in  reinforced  concrete,  though  the  floor,  which  is 
only  7  feet  wide,  has  steel  frame.  It  forms  an  opening  through  the 
harbor  jetty  and  is  probably  the  only  one  of  its  kind.  A  lift  over 
Shire  River — a  branch  of  the  Zambesi — at  Nyasaland,  designed  by 
Sir  Douglas  Fox,  has  a  100  foot  opening,  and  a  clear  height  above 
water  of  30  feet.  The  lifting  span  rises  between  disconnected 
towers,  supporting  the  sheaves,  and  when  open,  the  counterweight 
descends  and  lies  across  the  track,  forming  a  substantial  barricade. 
Openings  are  of  rare  occurrence,  and  hand  power  only  is  supplied, 
so  it  can  be  opened  in  25  minutes  by  eight  men.  The  weight  of  steel 
in  the  lift  span  is  55  tons,  in  tower  31  tons,  and  in  counterweight 
shells  8  tons.  The  towers  stand  on  30-inch  cast  iron  cylinders. 
The  small  lift  bridge  over  Union  Canal,  at  Fount ainbridge,  Edin- 
burgh, has  a  25-foot  road  and  steel  trough  floor.  The  canal  is  only 
13  feet  wide,  and  the  maximum  lift  is  8^2  feet.  It  has  an  elevated 
foot  walk  at  one  end,  reached  by  steps,  similar  to  the  bridge  at 
Dijon. 

A  patent  was  issued  in  1908  to  Eric  Swenson  of  Minneapolis, 
for  his  "gyratory  lift  bridge"  designed  for  crossing  the  Narrows 
at  Lake  Minnetonka,  the  counterweight  being  so  placed  as  to  keep 
the  centre  of  gravity  in  the  centre  of  rotation,  and  the  towers  were  to 
be  covered  with  ornamental  iron. 

Other  important  designs  for  direct  lift  bridges  during  the  last 
three  or  four  years  are  the  work  of  Waddell  and  Harrington,  civil 
engineers,  several  patents  having  been  granted  to  them  during  the 
summer  of  1908  for  bridges  at  Keithsburg,  Chicago,  and  Portland. 
One  for  the  Iowa  Central  Railroad  over  the  Mississippi  River  at 
Keithsburg,  will  not  contain  a  draw  of  the  usual  form,  but  a  novel 
lifting  arrangement  instead.  Several  spans  are  so  arranged  that 
towers  can  be  placed  at  their  ends,  with  their  rear  legs  on  the  adjac- 
ent fixed  spans.  The  230  feet  intermediate  span  between  the  towers 
can  then  be  lifted  45  feet,  thus  providing  for  a  shifting  channel. 
Comparative  tenders  received,  showed  the  arrangement  to  cost  about 
$39,000  less  than  an  ordinary  swing.  Three  other  lifting  spans  over 
Calumet  River,  Chicago,  were  begun  in  January,  1910,  one  being 
a  four  track  bridge  for  the  Lake  Shore  and  Michigan  Southern 
Railway,  the  other  two,  double  track  bridges  for  the  Pennsylvania 
Railroad,  all  having  skew  spans  of  210  feet,  crossing  a  waterway  of 
140  feet.  The  concrete  piers  will  go  down  to  rock  and  the  moving 
span  will  rise  to  give  a  clear  height  of  120  feet  above  high  water. 

The  lift  bridge  at  Hawthorn  Avenue,  Portland,  Oregon,  contains 
a  span  245  feet  long,  which  is  capable  of  rising  110  feet,  leaving  an 
under  clearance  above  high  water  of  165  feet.  The  trusses  are  23 
feet  apart  with  curved  upper  chords,  and  floor  beam  overhanging 
19  feet  for  car  tracks,  making  a  total  width  of  63  feet.  The  total 
weight  of  lifting  span  with  floor  and  machinery  is  885  tons,  which  is 
counterweighted  with  concrete  blocks  21  feet  by  37  feet  by 
6  feet  10  inches.  Towers  are  170  feet  high,  each  ©ne  weighing 


i6 


.VERTICAL  LIFT  BRIDGES 


128  tons.  The  cost  of  substructure  is  $100,000,  and  superstructure 
$350,000.  The  other  lift  at  Portland,  for  the  Oregon  Railway  and 
Navigation  Company  is  the  largest  of  the  kind  ever  attempted 
and  adjoins  a  swing  bridge  built  from  plans  by  George  S.  Morison 
in  1889.  It  contains  two  decks,  the  lower  one  only,  being  lifted 
52  feet  for  ordinary  craft,  which  includes  about  90  per  cent,  of  all 
the  river  travel,  although  the  whole  span  and  both  decks  can  be 
lifted  between  the  towers  for  masted  ships,  leaving  a  clearance  of 
135  feet.  The  approach  trusses  are  through  spans  with  a  railroad 
on  the  upper  deck,  and  highway  70  feet  wide  on  the  lower  one, 
which  is  locked  down  when  in  service.  The  highway  is  paved  with 
blocks  on  plank  supported  on  cross  ties,  all  wood  being  creosoted. 
Its  total  cost  is  reported  to  be  $1,650,000.  The  method  of  providing 
two  decks,  both  of  which  are  movable,  is  somewhat  similar  to  that 
used  in  1891  for  the  elevated  railroad  at  Liverpool,  England,  where 
the  double  bacsules  of  the  lower  deck  are  lifted  for  small  boats, 
while  for  larger  ships,  the  whole  bridge  with  lower  platform  suspended 
from  the  upper  one,  can  be  revolved  open  on  turntables  at  each  side. 
Other  direct  lift  bridges  are  in  Idaho,  Washington,  and  Arkansas, 
and  another  over  the  Miami  and  Erie  Canal  at  Mohawk  Place, 
Cincinnati. 

It  appears  therefore,  that  the  chief  progress  during  seventy 
years,  in  the  design  and  construction  of  direct  lifting  bridges,  has 
been  in  the  use  of  steel  towers  instead  of  cast  iron  and  stone,  and  in 
the  substitution  in  some  cases,  of  floating  buoys  instead  of  counter- 
weight, a  method  which  was  successfully  used  by  M.  Vescovali  in 
1893,  in  the  Tiber  River  bascule  near  Rome.  Compensating  chain 
weights  have  also  been  used  in  some  recent  works,  modifications 
of  those  invented  by  Poncelet,  and  used  on  bascules  in  France,  prior 
to  1847.  In  only  one  case — at  Kansas  City — has  the  length  of 
lifting  span  exceeded  300  feet,  as  proposed  by  Oscar  Roper,  of 
Hamburg,  in  1867. 


Proposed  Lift  Bridge  over  the  Tees  at  Newport,  the  design 
by  T.  E.  Laing  in  1872 


LD21— 32m— i 
(S3845L)4970 


(iaylord  Bros. 
Makers 

Syracuse',  \.  y 
W.  J*N.  2),  we 


2.  14 


UNIVERvSITY  OF  CALIFORNIA  LIBRARY