Full text of "An investigation of production scheduling problems motivated by semiconductor manufacturing"

AN INVESTIGATION OF PRODUCTION SCHEDULING PROBLEMS MOTIVATED BY 

SEMICONDUCTOR MANUFACTURING 



By 
JEFFREY WILLIAM HERRMANN 



A DISSERTATION PRESENTED TO THE GRADUATE SCHOOL 

OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT 

OF THE REQUIREMENTS FOR THE DEGREE OF DOCTOR OF PHILOSOPHY 

UNIVERSITY OF FLORIDA 

1993 



ACKNOWLEDGMENTS 

Years of learning are not sufficient for one who wishes to prepare a dissertation; also 
necessary is an environment which encourages one to develop the talents which God has given 
and to become an intelligent person, a responsible person, a kind person, a successful person. For 
providing such a setting I thank my family. 

To many others am I indebted: to the chairman of my supervisory committee, Dr. Chung- 
Yee Lee, who has been an exceptional influence on my development as a researcher, teacher, and 
scholar, to department chairman Dr. Jack Elzinga, Dr. Boghos Sivazlian, and the members of my 
committee; to all who were involved in the Harris project and whose effort was critical to this 
work; and to the quality friends, classmates, and teachers whom I have known and who have all 
added something valuable to my life. 

DISCLAIMER 

This material is based upon work supported under a National Science Foundation Graduate 
Research Fellowship. Any opinions, findings, conclusions or recommendations expressed in this 
dissertation are those of the author and do not necessarily reflect the views of the National 
Science Foundation. 



u 



TABLE OF CONTENTS 



ACKNOWLEDGMENTS 



page 



ABSTRACT . 
CHAPTERS 



vn 



L 



2. 



INIRODUCTION .... 








1 


LI Semiconductor Manufacturing 








2 


L2 Job Shop Scheduling 








4 


L3 Look-ahead and Loolc-bchind Scheduling 








4 


1.4 Setups. .... 








5 


1 .5 Sman-and-lucky Searches . 








6 


1 .6 Problem Space and Heuristic Space 








8 


1.7 Objective Functions. 








8 


1.8 Overview of Research 








9 


1 .9 Plan of Dissertation . 








10 


BACKGROUND .... 








13 


2.1 Semiconductor Test Operations . 








13 


2.2 Semiconductor Scheduling. 








16 


2.2.1 Production Planning 








17 


2.2.2 Shop Floor Control . 








19 


2.2.3 Performance Evaluation 








32 


2.2.4 Summary 








35 


2.3 Job Shop Scheduling 








36 


2.3.1 Scheduling Notation 








36 


2.3.2 Shifting Bottleneck . 








37 


2.3.3 Dispatching Rules . 








39 


2.3.4 Summary 








45 


2.4 Flow Shop Scheduling 








45 


2.4.1 Makespan 








46 


2.4.2 Total Flowtime 








46 


2.4.3 Maximum Lateness (Lmax) 








50 


2.4.4 Number of Tardy Jobs 








51 



m 



i 



2.5 
2.6 

2.7 



2.8 



2.9 

2.10 

2.11 



2.4.5 General Topics 

2.4.6 Summary 
Look-ahead and Look-behind SchcduUng 
Class Scheduling 
Some One-machine Problems 

2.7.1 Constrained Rowtime 

2.7.2 Release and Due Dales 

2.7.3 Flowtime and Release Dates 
Smart-and-iucky Searches . 

2.8.1 Introduction . 

2.8.2 Simulated Annealing . 

2.8.3 Tabu Search . 

2.8.4 Genetic Algorithms . 

2.8.5 Summary 
Problem and Heuristic Space 
NP-Complcteness . 
Chapter Summary . 



52 
55 
55 
57 
60 
61 
61 
62 
64 
64 
64 
67 
70 
75 
75 
77 
78 



3. ONE-MACHINE CLASS SCHEDULING PROBLEMS 

3.1 Introduction .... 

3.2 Constrained Flowtime with Setups 

3.2.1 Introduction . 

3.2.2 Literature Review 

3.2.3 Notation and an Optimal Property. 

3.2.4 The Heuristic 

3.2.5 The Genetic Algorithm 

3.2.6 Empirical Testing . 

3.2.7 Conclusions . 

3.3 Cla.ss Scheduling with Release and Due Dales 

3.3.1 Introduction . 

3.3.2 Literature Review 

3.3.3 Notation and Problem Formulation 

3.3.4 Heuristics 

3.3.5 Analysis of the Heuristic 

3.3.6 The Genetic Algorithm 

3.3.7 Empirical Tests and Results 

3.3.8 Extension to Minimizing Tardiness 

3.3.9 Conclusions . 

3.4 Flowtime with Setups and Release Dates 

3.4.1 Introduction . 

3.4.2 Notation and Problem Formulation 

3.4.3 Background . 

3.4.4 Solution Techniques 



80 
80 
81 
81 

84 
85 
87 
91 

100 
104 
104 
105 
105 
106 
106 
109 
113 
115 
120 
123 
124 
124 
125 
125 
126 



IV 



3.4.5 Empirical Testing . 

3.4.6 Special Case . 

3.4.7 Conclusions . 
3.5 Chapter Summary . 

LOOK-AHEAD SCHEDULING PROBLEMS 

4.1 Introduction . 

4.2 Minimizing the Makespan . 

4.2.1 Notation 

4.2.2 Johnson's Algorillim 

4.2.3 Permutation Schedules 

4.2.4 NP-Complctencss . 

4.2.5 Makespan Optimality Conditions and 

Polynomially-Solvable Cases 

4.2.6 Branch-and-Bound Algorithm 

4.2.7 Heuristics .... 

4.2.8 Empirical Results . 

4.2.9 Heuristic Error Bounds 

4.3 Minimizing the Total Flowtime . 

4.3.1 Total Enumeration . 

4.3.2 Lower Bounds 

4.3.3 SpeciiU Case .... 

4.3.4 Empirical Testing . 

4.4 Minimizing the Number of Tardy Jobs . 

4.4.1 Problem Introduction 

4.4.2 Lower Bound and Special Case . 

4.4.3 Heuristics .... 

4.4.4 Results .... 

4.5 Application to Job Shop Scheduling 

4.6 Chapter Summary .... 



GLOBAL JOB SHOP SCHEDULING . 

5.1 Introduction ..... 

Job Shop Scheduling ... 

A Genetic Algorithm for Job Shop Scheduling 

5.3.1 The Heuristic Space. 

5.3.2 A Genetic Algorithm for Global Scheduhng 
Global Job Shop Scheduling 

5.4.1 The Semiconductor Test Process . 

5.4.2 The Previous Scheduling System . 

5.4.3 Scheduling Needs 

5.4.4 Scheduling System Design. 

5.4.5 Information Requirements . 



5.2 
5.3 



5.4 



134 
136 
140 
141 

142 
142 
145 
145 
146 
147 
149 

150 

158 
160 
160 
162 
164 
165 
167 
168 
169 
170 
170 
171 
172 
173 
174 
175 

177 
177 
179 
181 
182 
185 
187 
187 
190 
191 
192 
193 



I 

I 



5.4.6 Implcmcniation of Global Scheduling . . . 195 

5.4.7 Implementation I.s.sucs ..... 197 

5.4.8 Conlribution.s of Global Scheduling ... 199 
5.5 Chapter Summary ....... 200 

6. SUMMARY AND CONCLUSIONS 201 

6.1 One-machine Class Scheduling Problems .... 201 

6.2 Look-ahead Scheduling ...... 202 

6.3 Searching for Job Shop Schedules ..... 202 

6.4 Conclusions 203 

REFERENCES 206 

BIOGRAPHICAL SKETCH 219 



VI 



Abstract of Dissertation Presented to the Graduate School of the University of Florida in Partial 
Fulfillmcni of the Requirements for the Degree of Doctor of Philosophy 

AN INVESTIGATION OF PRODUCTION SCHEDULING PROBLEMS MOTIVATED BY 

SEMICONDUCTOR MANUFACTURING 

By 

Jeffrey William Herrmann 

December. 1993 

Chairman: Dr. Chung- Yee Lee 

Major Department: Industrial and Systems Engineering 

Manufacturing and service organizations frequently face the challenges of making high- 
quality products quickly and of delivering those products to their customers on-time. 
Improvements in the scheduling of their operations can often contribute to their success in 
meeting these goals. However, as manufacturing processes become more complex, the difficulty 
of finding good production schedules increases. 

This dissertation addresses dynamic deterministic job shop scheduling, a problem that 
occurs in many manufacturing environments. The problem is among the most difficult 
scheduling problems, and few solution procedures have been implemented. The approach in this 
research is to consider specific subproblems that are motivated by semiconductor test operations 
and to develop genetic algorithms that exploit alternative search spaces. 

The research includes new analytical and empirical results for previously unstudied one- 
machine class scheduling problems and three-machine look-ahead problems. The one-machine 
problems include sequence-dependent setup times. In the three-machine problems, two groups of 
jobs are processed on separate second-stage machines. Testing shows that a new type of genetic 
algorithm can find good schedules for the one-machine problems by adjusting the problem data 
while using an appropriate heuristic. An approximation algorithm for the three-machine problem 
is able to find near-optimal schedules. 



vu 



Moreover, this dissertation describes the development and application of a global job shop 
scheduling system for the semiconductor test area. This system uses a detailed deterministic 
simulation model of the shop iloor, data about the current status of the shop, and a genetic 
algorithm to search over combinations of dispatching rules in order to create a good shift 
schedule. These rules include those motivated by this research into the one-machine and three- 
machine problems. The scheduling system is able to adapt to changing conditions each shift. 

The benefits of this work consist of the identification of dominance properties for the one- 
machine class scheduling and three-machine look-ahead problems, the development of a problem 
space genetic algorithm, the definition of new look-ahead heuristics, the creation of a new genetic 
algorithm for global scheduling, and the implementation of these results to the actual 
semiconductor test floor that is the motivation for this work. 



viu 



CHAPTER 1 
INTRODUCTION 



Why investigate production scheduling problems motivated by semiconductor 
manufacturing? Because scheduling works. Scheduling, the term, refers to the process of 
assigning tasks to resources and determining when each task will be done. Scheduling is not, 
however, limited to manufacturing, since this type of problem occurs in other activities. 
Scheduling, the science, embodies knowledge about models, techniques, and insights related to 
actual systems (Baker, 1992). This field is an important part of operations research. In order to 
compete effectively in the marketplace, firms have used operations research as a tool for 
understanding and improving their manufacturing systems. 

This is especially true in the manufacturing of high-technology products, where the new, 
complicated processes lead to production scheduling problems that are not well-solved. The 
post-assembly testing of semiconductors, for instance, is a complicated job shop scheduling 
problem; among the difficulties is the presence of sequence-dependent setups at certain 
operations. Moreover, scheduling, which has been studied from the eariiest days of operations 
research, has received new attention due to the successful implementation of just-in-time systems 
that emphasize the close coordination of resources and the maintenance of low woric-in-process 
inventory levels. 

Although the research in production scheduling has yielded a large body of knowledge 
which has been successfully applied to a number of areas, there still remain problems to be 
solved. The problems previously studied have always simplified reality in some way. Adding 
realism creates problems that resist simple solution techniques. Further research into these types 
of problems is necessary in order to increase our ability to control manufacturing processes 
effectively. 

1 



The research described in ihis dissertation falls into this category. It includes factors that 
model reality more closely and studies a number of different problems in an effort to gain iasighl 
into how improved job shop scheduling may be achieved. This insight will be applied to the 
semiconductor test area being studied. 

The problems that this research investigates are motivated by a high-technology field where 
much time has been spent investigating manufacturing systems, namely the semiconductor 
industry. The research is particularly motivated by the operations of semiconductor testing, 
although the problems can also be found in the processes of other manufacturing industries. 

This introduction includes a number of sections about topics that will arise in the 
scheduling of semiconductor test operations. These topics are introduced here in order to 
describe how they are related to this research. The first of these is an overview of semiconductor 
manufacturing. 

1.1 Semiconductor Manufacturing 

In order to give some context to the problems being studied, this section describes the 
general flow of semiconductor manufacturing. 

The manufacturing of semiconductors consists of many complex steps. The first process is 
that of wafer fabrication, done in a super-clean environment in order to protect the delicate 
structures on the wafers from contaminants. The wafers of silicon undergo repeated applications 
of the cycle of photolithography, etching, and diffusion in order to build, layer by layer, the 
different electronic devices. A wafer will contain a number of identical circuits laid out in a grid 
pattern on the wafer. In the next process, probe, these individual circuits are inspected with a 
wafer probe and marked if defective. In the assembly process, another clean area, the wafers are 
cut into the separate circuits. Good circuits are placed into the packages that protect them from 
the environment and that provide electrical connections to allow them to interact with the world. 
The identical devices from a lot of identical wafers become a lot that then moves into the test 



facility, an area where cnvironmenial safeguards protect the devices from static electricity that 
could still damage the circuits. 

The lest process consists of initial testing, bum-in, and Tmal testing. The testing includes 
electrical testing of each device and other testing of the device packages. Bum-in consists of 
subjecting the semiconductor chips to extreme thermal stresses. Other non-test operations, such 
as serialization and brand, take place during the process. 

Not all of the lots follow the same route through the lest floor. Different products are tested 
on different machines and undergo a different set of tests. Thus, the test area is a job shop, and 
the scheduling problem is a job shop scheduling problem. This job shop of semiconductor test 
operations has sequence-dependent setup times, re-entrant flows, batch processing, routes that 
temporarily leave the test area, and other complications that lead to many interesting scheduling 
questions. 

The primary management objectives for this area are customer satisfaction and making 
profit. Because testing is the last process in the manufacturing flow, the output of this area 
affects how well the company can get orders to its customers on time and how much product the 
company can ship to generate revenue. 

The particular semiconductor test area being studied has implemented a decision support 
system to assist in the scheduling of lots through the area. The programs in the system can order 
the lots waiting for an woricstation with priority rules that include information about lateness, 
priority, and setups. As part of the facility-wide computer-integrated manufacturing system, it is 
able to access real-time information about the lots. The system is used to create schedules for a 
short time period (two to four hours), since dispatching more often would require excessive 
computer resources. Lots that are tardy and lots that have some extcmally-imposed priority are 
expedited whenever possible. 



\ 



1.2 Job Shop Scheduling 

The semiconductor lest area is a job shop, and optimizing the scheduling of the area is a job 
shop scheduling problem. This section discusses job shop scheduling. 

Job shop scheduling consists of those scheduling problems in which different jobs may 
follow different routes tlirough the shop. A job consists of a number of operations or tasks, which 
must be processed in the given order. There exists a specified machine (or workstation) that can 
perform each operation. These problems are generally the hardest to solve optimally, since few 
properties of optimal schedules are known and the number of possible solutions explodes as the 
problems increase in size. However, in many cases, the job shop is a better model of reality than 
one-machine, parallel-machine, or flow shop problems. 

Because of the complexity of job shop scheduling, algorithms to find the optimal solution 
(in a reasonable amount of time) for any arbitrary objective function do not exist. Recent 
research has shown that the shifting bottleneck heuristic is successful at finding good solutions for 
a simple job shop scheduling problem. Traditionally, however, researchers have studied and 
schedulers have used dispatching rules to order the jobs waiting for processing at a machine. 
When a machine becomes available, it chooses from among the jobs in its queue by using a 
dispatching rule. Common dispatching rules employ processing times and due dates in both 
simple rules and complex combinations. These dispatching rules are often extensions of the 
algorithms used to solve one-machine problems. 

In any shop, there may exist a bottleneck machine whose throughput is a limiting factor on 
the capacity of the shop. If so, the improved scheduling of this one machine becomes an 
important objective. 

1.3 Look-ahead and Look-behind Scheduling 

This section addresses a weakness of the traditional dispatching rule approach to 
scheduling job shops and defines two types of rules that overcome this weakness. 



Traditional dispatching rules arc myopic; they arc concerned only with the machine to be 
scheduled and the jobs waiting for that machine. Improved scheduling may be realized by using 
rules that can consider morc information, in order to see that critical lots arc arriving soon or that 
a certain machine has an excessive queue. Look-ahead and look-behind scheduling includes 
procedures that look around the shop for more information to use in making a scheduling 
decision. With this additional information, they can hopefully produce better decisions. Look- 
ahead models consider the machines where the jobs will be headed after this stage. Look-behind 
models consider the jobs that will be arriving at this machine soon. 

The terms look-ahead and look-behind are used to designate scheduling procedures that do 
more than consider just the state of one machine. Both types of models look into the future 
(where jobs will go and what jobs will be arriving). The difference is what part of the future they 
consider. 

1.4 Setups 

One of the complications of scheduling the operations in semiconductor testing is the 
presence of different product types that require different configurations on the same machine. 
The task of configuring a machine in order to process a job is a setup. 

If the setup for a job is independent of the job that was scheduled before it on the same 
machine, the setup time can be included in the processing requirements of that job. If the setup 
for a job is sequence-dependent, that is, the time of the setup depends upon the immediate 
predecessor job, the scheduling problem becomes quite difficult. 

Because the problems with sequence-dependent setups are quite difficult, researchers have 
examined special ca.scs of the general problem. The most common problem is the class 
scheduling problem, where the jobs to be processed are grouped into a number of job classes. 
There exists no sequence-dependent setup between jobs from the same class, although there does 
exist a special setup, the class setup, when a job from one class is processed after one from 
another class. There may also exist a class setup for the first job processed. These class setups 



may be sequence-dependent in iliai tiiey depend upon the class that was last processed. Class 
scheduling is still dirficult. though: the class scheduling extensions of one-machine problems that 
are easy to solve are usually NP-complete problems. 

An example of class setups occurs in the electrical testing of assembled semiconductor 
devices on a machine which can test a number of different types of semiconductors. If a machine 
is scheduled to test a lot consisting of devices that arc different from the devices tested in the 
previous lot, various setup tasks are required. These tasks may include changing a handler and 
load board that can process only certain types of semiconductor packages or loading a new test 
program on the tester. However, if the new lot consists of devices that are the same as the 
previous type, none of this setup is required. This is a class scheduling problem. 

1.5 Smart-and-luckv Searches 

As mentioned before, algorithms to solve the job shop scheduling problem optimally in 
reasonable time do not exist. In addition to the shifting bottleneck heuristic and the use of 
dispatching rules, one way to find good solutions is to search for them. This section will discuss 
standard local searches and new, more sophisticated heuristic searches. 

One method of finding good solutions to hard optimization problems has been local search. 
A local search begins with some initial solution and moves from an incumbent solution to a better 
neighboring solution, ending when no improvement can be found. At this point, the search has 
reached a local optimum. Two common local searches are hillclimbing and steepest descent. In a 
hillclimbing search, the neighbors are chosen at random, and the first better neighbor found is 
chosen as the new solution. In a steepest descent search, the entire neighborhood of the 
incumbent solution is searched and the neighbor that has the best performance improvement is 
selected. In order to overcome the fact that these searches converge only to local optima, new 
heuristic searches have been developed. These include simulated annealing, tabu search, and 
genetic algorithms. 



These heuristic searches arc complex searches that are smart enough to escape from most 
local optima and are lucky enough to generally find good solutions. 

Simulated annealing (SA) is a variant of the hillclimbing algorithm. Simulated annealing is 
so called because the algorithm views optimization as a process analogous to physical annealing, 
the cooling of a system until it reaches a low-energy slate. In the same way that a system may 
pass through higher-energy states during the cooling process, the simulated annealing search 
occasionally moves to worse neighbors before settling into a good solution. 

Tabu search (TS) is a variant of steepest descent. Given an incumbent solution, a TS 
canvasses the neighborhood of this solution in order to find the best allowable move. If the 
search is at a local optimum, it is forced to move away, and the move that would return to the 
previous solution is temporarily prohibited (tabu) by adding it to the tabu list for a number of 
moves. In this way, TS may continue to move away from a local optimum and find an area of the 
space that leads to another local optimum. An aspiration level insures that the search will make a 
move that leads to a solution better than any yet found, even if tabu. Thus, a tabu search works 
because the tabu list forces the search to explore new areas of the solution space. The short-term 
aspect of the memory and the aspiration level allow, however, the search to get to a global 
optimum. 

A genetic algorithm (GA) is a procedure that mimics the adaptation that nature uses to find 
an optimal state. In genetic algorithms, solutions are represented as strings (chromosomes) of 
alleles. An allele is a bit of information about the solution. The search performs operations on 
the population of solutions. TTiese operations are 1) the evaluation of individual fitness, 2) the 
formation of a gene pool, and 3) the recombination and mutaUon of genes to form a new 
population. After a period of time, good strings dominate the population, providing a good 
solution. 

When applied to scheduling problems, simulated annealing and tabu search easily search 
the complex solution spaces with simple types of moves, generally find good solutions fast, and 
are smart and lucky variations of standard searches such as hillclimbing and steepest descent. 



g 

Gcnclic algorithms arc something completely diffcrcnt, work well by using good strings and 
implicit parallelism, and arc harder to implement. 

1.6 Problem Space and Heuristic Space 

Typical problem-solving searches like those described in the above section have examined 
the solution space. A solution can be a vector of values or a sequence of objects. Applying a 
heuristic to a problem yields a point in the solution space. This implies that a search over all of 
the possible heuristics would fmd a solution that gives the optimal objective function value. 

Moreover, applying a heuristic to another, similar problem also generates a point in the 
solution space which can be evaluated for the original problem using the objective function. 
Thus, a search over the new problem space provides a way to solve the problem. 

An example of a heuristic space is the space of vectors of m dispatching rules for a w-job 
and m-machine job shop scheduling problem, where each dispatching rule is applied to a different 
machine. Searching over the vectors of dispatching rules is similar to machine learning. For a 
complicated one-machine problem, a sample problem space would be the space of ^-element 
vectors, where each element corresponds to an alternative due date for a job. Sorting the jobs by 
these alternative due dates creates a new solution. 

1.7 Objective Functions 

The management of a manufacturing system is concerned with many different performance 
measures, including customer service, inventory holding costs, throughput, and machine 
utilization. This section describe how the objectives used in scheduling mirror these concerns. 

Scheduling problems include many different objective functions that attempt to model the 
concerns of those who are running the system. Most objectives are functions of the completion 
times of the jobs to be scheduled. The makespan is the maximum completion time, which is 
when all of the jobs are finished, and is some measure of the throughput of the system. The total 
flowtime is the total time that the jobs spend in the system and is a measure of the work-in- 



process inventory held while processing ihe jobs. Other objective functions include due dales for 
each job. where a job is lardy if il compleies after iis due dale. These objective functions are 
concerned with customer satisfaction, and include maximum lateness, which is the maximum 
difference between a completion time and a due date, the number of lardy jobs, and the total 
tardiness. Another interesting objective function is earliness, which is a measure of the holding 
cost incurred by storing finished product until it is delivered at its due date. 

While all of these objective functions (and many more) have been studied for one-machine 
problems, most analysis of flow shop and job shop scheduling has focused on the minimization of 
makespan. Since this objective is not appropriate in semiconductor manufacturing, this research 
is especially interested in solving job shop scheduling problems with other objectives. 

1.8 Overview of Research 

There exist different approaches to attacking the job shop scheduling problem. One can use 
the shifting bottleneck algorithm to minimize the makespan, use good dispatching rules in a 
dynamic environment, or search for good global schedules. This research is concerned with the 
last two methods (see Figure 1.1). This research investigates the use of smart-and-lucky searches 
over the new search spaces to find good solutions to the job shop scheduling problem. Also 
investigated are a number of interesting one-machine class scheduling problems and look-ahead 
models in order to devise techniques that can be used as good dispatching rules. Finally, this 
research studies how these techniques may be applied to the actual semiconductor test floor that 
is the motivation for this work. 

The benefits of this work include three areas: 1 . The addition of results to the body of 
knowledge about specific scheduling problems, including the difficult class scheduling problems 
and little -studied look-ahead models. 2. The construction of a robust genetic algorithm for one- 
machine class scheduling problems. 3. The development and implementation of a genetic 
algorithm for global job shop scheduling. Moreover, this work continues the investigation of 
scheduling semiconductor test operations that has only recently begun. 



10 



SCHEDULING 



Semiconductor 
Manufacturing 



Job Shop Scheduling 



Shifting 
Bottleneck 



Dispatching 
Rules 



x 



T 



One-machine 
Problems 



1 



Searches 



Look-Ahead 
Problems 



Class 
Scheduling 



Flow Shop 



Smart &c Lucky 
Searches 



Problem and 
Heuristic Space 



Figure 1.1. Relationship of dissertation topics. 



1.9 Plan of Dissertation 



This research investigates both one-machine and multi-machine problems. The one- 
machine problems studied are class scheduling problems that model the complicating factor of 
machine setups in the manufacturing process. This work also considers some three-machine 
general flow shop problems that are attempts to model how scheduling can be improved by 
considering the states of other machines. The research also investigates a general job shop 
scheduling problem in an attempt to see how new search spaces may be used for global job shop 
scheduling. 

For these problems, the research has focused on finding good lower bounds, developing 
heuristics to find good solutions for the problems, and using genetic algorithms to find better 
solutions. Empirical testing of these bounds and heuristics serves as a way of evaluating the 



I 



i 



11 

heuristics and the searches. Also, good heuristics for the subproblems can be implemented as 
advanced dispatching rules for solving the job shop scheduling problem. 

In addition, analytical results such as NP-completeness, lower bounds, error bounds, and 
oplimality conditions arc presented for the problems being studied. 

The machine scheduling problems under investigation arc as follows: 

1. Constrained Flowtime with Setups (CFTS) 

2. Class Scheduling with Release and Due Dates (CSRDD) 

3. Flowtime with Setups and Release Dates (FTSRD) 

4. Three-Machine Look-Ahead Scheduling: Makespan (3MLA-MS) 

5. Three-Machine Look-Ahead Scheduling: Flowtime (3MLA-FT) 

6. Three-Machine Look- Ahead Scheduling: Number of Tardy Jobs (3MNT) 

7. Job shop scheduling 

The first problem is the class scheduling extension of the one-machine problem of 
minimizing the total flowtime of a set of jobs that have deadlines. The second problem is the 
class scheduling problem where each job has a release date and a due date. The objective is to 
minimize the number of tardy jobs. The objective in the third problem is to minimize the total 
flowtime where each job has a release date. 

The research next considers the three-machine look-ahead problems with the objectives of 
makespan, total flowtime, and number of tardy jobs. 

Finally, this research investigates the general job shop scheduling problem and a heuristic 
space approach to finding good solutions with a genetic algorithm. 

The dissertation consists of the following five chapters: the background; the research on 
one-machine class scheduling problems, on three-machine look-ahead problems, and on job shop 
scheduling; and the conclusions. 

The background material contains detailed information about the problems and methods 
under investigation and summaries of a number of papers that are related to this work. The topics 
include semiconductor test operations and semiconductor scheduling, job shop scheduling 



12 

techniques, class scheduling, some one-machine problems, smart-and-lucky searches, problem 
and heuristic space, look-ahead and flow shop scheduling, bum-in scheduling, and NP- 
completeness. 

The discussion of the research contains reports on the problems that have been investigated: 
three one-machine class scheduling problems, three three-machine general flow shop problems, 
and a heuristic search for use on the general job shop scheduling problem. In the conclusions we 
summarize this research and identify some directions for future research. 



I 



CHAPTER 2 
BACKGROUND 



This chapter of the dissertation perfonns two functions: it elaborates on the topics in the 
introduction and provides a review of the relevant literature. The discussion in this chapter is 
both wide-ranging and descriptive. In Chapters 3, 4, and 5, discussions of previous research will 
be problem-specific and less explicit. 

The first section will describe in more detail the particular operations associated with the 
testing of semiconductor devices. Remaining sections will discuss papers on semiconductor 
manufacturing, job shop scheduling techniques, and flow shop scheduling problems. Also 
included in this chapter are sections on look-ahead and look-behind scheduling, the scheduling of 
the bum-in operation, class scheduling, some one-machine problems, smart-and-lucky searches, 
problem and heuristic space, and NP-completeness. 

2. 1 Semiconductor Test Operations 

The manufacturing of semiconductors consists of many complex steps. As described in the 
introduction, this includes wafer fabrication, probe, assembly, and test. This research is 
concerned with this last facility. Although the routes of lots through the test process vary 
significantly over the many different types of products, general trends can be described. Figure 
2. 1 shows what these routes look like for seventeen representative products of a test area. The 
numbers on each arc are the number of products that follow that path. 

Presented here is a description of the operations in a typical product route. The terms 
semiconductor and device describe the same thing. 



13 



14 



LOT 
FORM 



INSPEC- 
TION 



SERIAL- 
IZATION 



X-RAY 



INITIAL 
TEST 



BURN 
IN-1 



INTERIM 
TEST 



BURN 
IN-2 










INTERIM 
TEST 


— 



FINAL 
TEST 



ASSEMBLY 






BURN 


IN-3 






INTERIM 


TEST 



BRAND 



TEST 





ASSEMBLY 



VISUAL, DOC REV.QCI, 
PACK, INSPECT, SHIP 



Figure 2.1. Product Routes in the Test Area. 



15 

The loi arrives at the lolform area with an assembly traveler that describes the history of the 
lot up to that point. A lot is started through the test floor when it is needed to meet back-ordered 
demand or when the area planner includes it on the weekly release plan. The test traveler for this 
product is printed, and engineering information is extracted from the database and attached to the 
traveler. The tubes of devices arc placed into a box, and the box is moved to a waiting area. 

The lot is then serialized. Done in the brand area, serialization is the process of giving each 
device a unique serial number. This process is labor-intensive as someone must stamp each 
device with a branding machine. 

The lot then undergoes X-ray testing. This operation includes six tasks; loading the devices 
into racks, shooting the X-rays, unloading the devices, developing the X-rays, reading the X-rays 
for internal defects in the package assembly, and culling the rejects. The lot may experience 
significant waiting before and after the reading of the X-rays. Three people handle the lot: one 
who loads and shoots, one who reads, and one who culls. 

Electrical testing, the next step, is an important, machine-intensive operation. During an 
electrical test, the lot is processed by a handler machine that positions each device over a contact 
with the tester, a computer that performs a number of tests by subjecting the device to a number 
of different electrical inputs. After the test of that semiconductor is done, the device is fed to an 
output bin. The test floor contains a number of different types of testers and different handlers. 
Since each product requires a different combination of handler and tester, significant setup time 
can be incurred if the operator must find and install a handler to process the lot. 

After the initial test, the lot must be bumed-in. The devices in the lot are loaded onto 
boards that hold from 10 to 100 devices each. These boards are placed into ovens, where the 
devices are subjected to thermal stresses and electrical inputs in order to cause infant mortality. 
The bum-in period lasts a minimum of 24 hours, although no penalty is associated with keeping 
the devices in the oven for longer than this time. After the boards are removed from the oven, the 
devices are unloaded from the boards. 



I 



16 

After the bum-in period, Uie lol returns to a tester and undergoes interim test. Interim lest 
consists of testing at room, low, and high temperatures. For the low temperature test, a botUc of 
liquid nitrogen must be attached to the handler and the handler must chill the testing environment 
to the desired temperature. In a test at high temperature, the handler warms the test chamber to 
the desired temperature. 

After the last bum-in and interim test, a final test is conducted. The lot then goes to the 
assembly facility, where fine and gross leak testing of the package seal is performed. During this 
time, the lot is out of the test facility's area of control. 

The lot retums and moves to brand, where each device is stamped with the company logo. 
The devices are placed into pans and then sit through a three-hour bake in a kiln. After this step, 
testing is performed to verify that no damage was done to the devices during brand. 

After another trip to assembly, the lot undergoes a visual test, where each device is 
inspected under magnification for obvious defects in the packaging. The lot enters document 
review next. At this time, all of the paperwork associated with the lot must be reviewed for 
completeness. 

The lot then undergoes customer source inspection, where a representative of the customer 
personally supervises the testing of a sample of the lot. In the shipping operation, the devices are 
placed in boxes and the boxes are addressed, ready for delivery to the customer. 

2.2 Semiconductor Scheduling 

The manufacturing of semiconductors has received much attention form production 
planning and scheduling researchers. This section reviews a number of papers that address the 
issue of semiconductor production planning and scheduling directly or indirectly. As in Uzsoy, 
Lee, and Martin- Vega (1992a, 1993), the papers are classified into the following topics: 
production planning; shop fioor scheduling: dispatching rules and work release, deterministic 
scheduling, batch processing, control-theoretic approaches, knowledge-based approaches, and 
simulation; and performance evaluation: queueing models, and simulation. This review is 



1 



17 

intended to display the numerous methods that have been used in the research of production and 
scheduling issues of semiconductor manufacturing. 

2.2.1 Production Planning 

A number of authors have addressed the large-scale problem of production planning for the 
semiconductor industry. The most common approach has been a hierarchical decomposition of 
the problem. 

Leachman (1986) describes a corprarate-level production planning system. This system 
divides the manufacturing process into the stages of wafer fab, probe, assembly and test, linked 
by inventories. Its model may include multiple facilities. The production processes in a plant are 
treated as a single entity, and problem complexity is reduced by the aggregation of products that 
are in the same process at each stage. 

Information from corpxjrate databases is used in a linear program with dynamic production 
functions that capture the relationships between the processes. This yields a production plan. 
Through a set of linear programs, the aggregate plan is then decomposed into a capacity-feasible 
weekly start schedule for various facilities. In a later work, this system was implemented by 
Harris Semiconductor. 

Hadavi and Voigt (1987) describe the planning system for a Siemens development wafer 
wafer fab. In their approach, they create different levels of abstraction for different levels of 
planning and localize rescheduling while making minimal resource constraints. 

The system architecture is a hierarchy of constraint sets that represent different time 
windows. Quarterly requirements are divided into months, weeks, and days. Arriving orders 
start feasibility analysis (can it be done?) and then a scheduling heuristic (when will it be done?) 
that tries to satisfies the constraint sets (based on the hierarchy). Scheduled orders are sequenced 
by an algorithm that maximizes throughput. A rule-based expert system recovers from 
disturbances by local rescheduling. 



I. 



18 

Harrison, Holloway, and Palcll (1989) discuss the production planning question and present 
a case study of National Semiconductor Corporation. They list the following programs that can 
improve customer service: management information systems; logic and algorithms used to 
generate delivery quotations and to schedule production; and performance evaluations and 
incentive systems based on measures of delivery performance. They place the emphasis on 
operational decision-making, from booking orders to scheduling lots on machines. 

The authors also consider performance measurement, which should give the upper 
management information about the different groups, all of whom are acting to improve their 
performance on these scales. These measures should encourage mangers to act optimally for the 
company. 

The authors make the following comments about scheduling. Marketing wants 
commitments to be inviolate; production planners thus want control over factory loading. 
Managers view scheduling as a MIS problem that provides reliable routine execution. The 
company must get the right information to the right people and then coerce them to do the right 
thing. 

Golovin (1986) describes various attempts to solve the problem of production planning and 
factory scheduling. Mathematically, an integer programming problem of the factory scheduling 
problem considers all costs. The solution philosophies are diverse and involve certain tradeoffs. 
Mathematical optimization gives the best solution but is computationally costly in data and time 
and ignores local conditions. Dispatching rules are concerned only with the present. They may 
make poor scheduling decisions by ignoring global conditions, but they work quickly and 
cheaply. Just-In-Time maintains a balance of work in the factory and attempts to maintain a high 
level of quality. 

The authors find most promising hierarchical systems that decompose the problem into sets 
of decisions made at different times: capacity planning, release planning, and lot dispatching. 
This approach may yield suboptimal policies but it gives control of decisions to the users who are 
responsible for the results. Scheduling is done under the assumption that sufficient capacity 



19 

exists. Dealing with uncertainly in yields and equipment calls for keeping safety slock of 
standard product and buffers in front of each machine to prevent starvation. 

2.2.2 Shop Floor Control 

Methods used to control the shop floor vary widely in their approaches to solving the 
problems encountered there. The basic areas include lot release policies, dispatching rules, 
deterministic scheduling, control-theoretic approaches, knowledge-based approaches, and 
simulation. 

The production of detailed shop schedules for planning and shop floor control has also been 
considered by researchers looking for some way to go beyond materials requirements planning, 
which docs not consider capacity constraints, and to search for schedules better than those found 
by dispatching rules. 

Vollmann, Berry, and Whybark (Chapter 5, 1988) discuss three simple ways in which shop 
floor control can be done: Gantt charts (often created backwards from the job due dates), priority 
sequencing (dispatching) rules, and finite loading schemes, which create a schedule for the time 
horizon by simulating the operation of the shop. 

Bai and Gershwin (1989) initiate a discussion of all important phenomena in semiconductor 
fabrication and characterization of all events and scheduling objectives and factory types. They 
start with the observation that two types of events exist: controllable and uncontrollable. 
Controllable events are those that the person in charge of scheduling the shop can start. The state 
of the system is a complete description of the production variables, such as the status of each 
machine and each worker. The variables in the state are chosen by the scheduler for his purposes, 
and he may ignore certain inconsequential quantities. Events change the state of the system, and 
the current state limits the options of the scheduler, who must make a decision based upon the 
state. 

The authors note that schedules in the real worid are subject to disruption by uncontrollable 
events and that schedulers have three weapons to reduce the effects of disruption: real-time 



20 

scheduling systems, prediction, and inherently- robust schedules. The first is the most powerful, 
but the computational effort makes combinatorial optimization impractical; thus, scheduling 
heuristics are necessary. 

The paper includes a summary of the semiconductor manufacturing processes and a 
detailed description of wafer fabrication. This description includes an explanation of the different 
machines, workers, and events in the fabrication process. The uncontrollable events are classified 
into those that are predictable and unpredictable. The latter include machine failure and defective 
wafers and are the ones that make life difficult for schedulers. The authors also include the 
constraints on scheduling and the objectives of scheduling, which are the minimization of WIP, 
throughput, variability in throughput, and costs and the meeting of demand. 

Lot release policies and dispatching rules . A number of researchers have realized that the 
release of work into the shop has large ramifications on the performance of that shop. 
Dispatching rules are in use in many shops, and some work has been devoted to developing better 
rules. 

Wein (1988) considers the problem of minimizing cycle time in a semiconductor wafer 
fabrication. His approach is to study the input regulation policy. He studies four alternatives: no 
control (Poisson arrivals); uniform start policy (constant release rate); constant WIP (closed 
loop); and workload regulating. This last rule focuses on the heavily-utilized workstations and 
uses a Brownian network model to approximate a multiclass queueing model with dynamic 
control capability. A lot is released when the work in the system for a bottleneck machine falls 
below a certain level. Bottleneck machines use various dispatching rules while other machines 
use FIFO. The workload regulation rule was found through simulation studies to reduce the 
mean and variance of cycle time, and the effects of dispatching rules were less significant and 
varied by system and input type. The study uses data gathered at Hewlett-Packard Technology 
Research Center in Palo Alto. 

Glassey and Resende (1988 a,b) examine a wafer wafer fab with a single bottleneck 
workstation, single product, and constant demand. Their approach is to control input regulation 



\ 



21 

by considering global informalion. The measure of performance is the cycle-lime versus 
throughput curve. Their answer is to release jobs so that they arrive at the bottleneck just in time 
to avoid starving that machine (starvation avoidance). This requires the determination of the 
virtual inventory, the amount of work for the bottleneck machine that is there now or will be soon 
(within the lead time it takes a released job to reach the machine). If this inventory is less than 
the lead time, release a job. This is similar to a safety-stock inventory policy. 

Simulation studies reveal that starvation avoidance results in lower cycle-time vs. 
throughput curves than other release rules: uniform, fixed- WIP, and workload regulation. 
Solorzano (1989) describes the implementation at Harris Semiconductor. 

Glassey and Pctrakian (1989) consider the problem of minimizing the queue of a bottleneck 
machine in a shop using starvation avoidance input regulation. They do so by using queue 
predictions and dispatching rules that give higher priority to lots that should encounter a shorter 
queue on their next visit to the bottleneck. This extra queue prediction computation is intensive, 
although certain simplifying assumptions are made. Object-oriented simulation studies show 
good behavior (better than dispatching rules such as SPT and FIFO) in both a one-product wafer 
fab and a two-product wafer fab. 

Wein and Chevalier (1992) take a broader view of the job-shop scheduling problem by 
considering three dynamic decisions: assigning due-dates to arriving jobs, releasing jobs from 
backlog to shop floor, sequencing jobs at each workstation. Their objective is to minimize WIP 
and due-date lead time, subject to an upper bound constraint on fraction tardy. They take a two- 
step approach: (1) release and sequence jobs to minimize WIP subject to throughput rate; and (2) 
set due dates that minimize due-date lead time. 

The authors propose three principles: (1) while maintaining fraction tardy, average due date 
lead times can be reduced by dynamically basing due-dates on the status of the backlog and shop 
floor, the type of arriving job, and the job release and sequencing policies used; (2) without 
affecting the throughput, WIP can be reduced by regulating the amount of work on the shop floor 



22 

for bottleneck stations; and (3) belter due-date performance can be achieved by focusing on 
efficient system performance and ignoring due dates when sequencing. 

The proposed job release policy is to inject a customer into the shop whenever the 
workload at the bottlenecks is at a certain level, determining the customer by a workload 
balancing input heuristic. Priority .sequencing uses dynamic reduced costs from an LP. In step 
two, due dates are set using rough approximations that follow the spirit of principle 1 . Simulation 
experiments considered a two-machine, two-product shop. The proposed policies beat standard 
policies. 

Lee et al. (1993) describe a decision support system for shop- floor control in a test facility. 
The system uses the Short-Interval Scheduler (SIS) module of COMETS to perform dispatching. 
The main contribution of the work is the development and implementation of a mechanism that 
considers sequence-dependent setups while making despatching decisions. This is done by 
classifying the setups and assigning each operation a setup code representing the setup 
configuration (determined by handler, temperature, and package type). This allows the operator 
to select operations with desirable setup characteristics in addition to the due date or operation 
type allowed by COMETS. This system has been implemented in a test facility and has been 
running successfully for over two years. 

Detenninistic scheduling . Under certain conditions, or using simplifying assumptions, 
controlling the shop floor can be represented by a scheduling problem that can be solved 
deterministicaUy. The solution to this problem gives a schedule that can be used on the shop 
floor. 

The papers by Uzsoy, Lee, and Martin-Vega (1992b) and Uzsoy etal. (1991a, 1991b) 
consider the scheduling of a semiconductor test facility and the associated single-machine 
problems. This work addresses back-end and due-date issues. Their first approach is the use of 
the shifting bottleneck algorithm, which iteratively schedules workcenters based on some 
measure of criticality. 



1 



23 

In another result, they use dynamic programming algorithms and heuristics to minimize 
maximum lateness and number tardy on a single-machine problem with sequence-dependent 
setup times. Finally. Ihcy minimize maximum lateness on a single tester with a branch and bound 
algorithm and local search improvements to heuristics. They also describe the prototype 
implementation of an approximation scheme for an entire test facility (Harris Semiconductor), 
which may be a practical alternative to dispatching rules. 

Graves et al. (1983) study the problem of scheduling a production facility with re-entrant 
product flows for identical products. Their objective is to minimize average cycle time while 
meeting a target production rate. They develop cyclic schedules that process each operation of a 
job once every cycle, where the length of the cycle is the reciprocal of the production rate. Thus, 
in each cycle, one job is started and one job is finished. The scheduling of tasks on machines in 
the cycle is done with a greedy heuristic that maintains feasibility. The machines in the problem 
may be multi-channel or batch facilities. The authors compare their rule to the simple FIFO 
dispatching rule. 

Kubiak, Lou, and Wang (1990) consider a re-entrant job shop with a hub machine, the 
machine to which jobs return repeatedly. They wish to minimize total completion time under the 
following assumptions: (1) the shortest operation on the bottleneck is longer than any other 
operation (allowing the single-machine simplification); and (2) the jobs possess a hereditary 
order, where a smaller total processing time implies a shorter processing time for any operation 
on hub machine. An optimal well-ordered schedule sequences jobs at the same operation for the 
hub machine by SPT. They develop a dynamic program and present a heuristic that develops 
clustered schedules, where groups of jobs scheduled together, finishing one cluster before moving 
to the next. 

Lee, Uzsoy, and Martin- Vega (1992) study bum-in as a single-machine problem. They 
assume that each lot of devices has been loaded onto a number of boards, and each of these 
boards forms a job for a bum-in oven. If a batch of jobs is placed into the oven, the entire batch 
must remain in the oven until all of the jobs have been processed long enough. Thus, the 



24 

processing time of the batch equals the maximum processing time of the jobs in the batch. The 
authors examine the performance measures of maximum tardiness, number of tardy jobs, 
maximum lateness, and makespan. In this mathematical paper, the authors present dynamic 
programming algorithms to solve batch scheduling problems with release dates and parallel batch 
scheduling problems. 

Bitran and Tirupali (1988 a,b) consider the problem of epitaxial wafer manufacturing. 
They identify the bottleneck as the epitaxial growth operation, which takes place in a number of 
different reactors. Their model is a single-stage parallel unrelated machine problem, with the 
objectives of makespan and total tardiness. They develop static scheduling heuristics that create 
schedules in two phases: product group priorities (by workload and due date measures) and then 
job priorities (by due date) within each group. 

They also address the planning problem of assigning reactors to product groups in order to 
decomfX)se the problem into independent shops. This approach reduces the complexity of the 
problem and results in the following observation: the choice of heuristic to solve the problem 
should be guided by the homogeneity of product set and the objective function. An implemented 
scheduling system provides shop floor schedule for each reactor, job status, lead-time estimates, 
and reactor load profile. Periodic resolving of model after planning preprocessing creates 
uniform reactor loads and homogeneous product mixes. 

Control -theoretic approaches . In an attempt to find policies that perform better than 
standard rules, some researchers have created control-theoretic models. The solutions to these 
models are then used to manage the shop floor. 

Bai, Srivatsan, and Gershwin (1990) consider a hierarchical production planning and 
scheduling system for a semiconductor wafer fabrication facility. They attempt to meet 
throughput goals while treating random disruptions explicitly. They integrate the scheduler with 
the system data base. Events in the wafer wafer fab are classified by their frequency and whether 
they are controllable (starling a lot vs. machine breakdown). Planning hierarchy is organized by 
these frequencies. Each level has events with the same magnitude of frequency, capacity 



25 

constraints, and objectives passed to lower levels. When something with a low frequency 
happens, the target frequencies of higher-frequency events arc rccalculalcd. The real-time 
scheduling is derived from control theory and trcats random events as part of the system. This 
decomposition allows small but very detailed models. The approach is implemented at the MIT 
Integrated Circuit Lab. Recent results on this work are covered in Bai and Gershwin (1992). 

Bai and Gershwin (1990) cover previous work on scheduling single-part, multiple-part, and 
re-entrant flow systems using a real-time feedback control algorithm. For single-part systems, the 
linear programming problem for the feedback control law divides the surplus space into regions 
where the optimal production rate is constant. There also exists a spot called the hedging point 
where the surplus is enough to compensate for any disruptions. The feedback controller attempts 
to drive the system to this point. 

The authors measure the system's performance in keeping the amount of surplus close to 
zero with low buffer inventories. They also attempt to improve behavior by separating the 
machines from each other to reduce effect of machine failure. Solving a nonlinear program 
yields an optimal hedging point (minimizes buffer inventory and buffer sizes). The current buffer 
inventories and the hedging point are then used to calculate the desired production rate for the 
system. Loading times for machines are calculated heuristically to be close to the optimal 
production rate. 

For multiple-part systems, machines are divided into single-part sub-systems with the same 
failure and repair rates and capacities proportional to the demand for that part. In re-entrant 
systems, machines are again divided by part and also by operation, with appropriate capacities 
calculated. 

In Lou and Kager (1989), the authors consider VLSI wafer fabrication with the goal of 
reducing WIP while following target production and observing machine capacity. Their approach 
is to use lot release and lot dispatching control rules based on flow rate control, a stochastic 
optimal control problem. Assuming a continuous flow, the authors divide the shop into 
workstations and determine a production rate for each according to control rules that consider the 



i 



26 

inventories across the floor and predetermined hedging points. The advantages of this model 
include reducing tlie dimension (by ignoring machines) and providing dynamic feedback control 
(by responding to surpluses, down machines). The authors compare their policy to an event- 
driven simulation using uniform-loading by cosus of inventory at all stages, and claim that the 
flow-rate control reduces costs by 50%. 

Gong and Matsuo (1990a) examine a multiperiod production system with random yield, 
with the objective of minimizing fluctuation of WIP inventory, leading to more predictable 
system performance. Their approach is to consider control rules for starting product into each 
stage and raw material. They report that intuitive control rules can be destabilizing. Their new 
control rule - Minimum Weighted Variance - is the optimal control policy for a stochastic 
dynamic program with a quadratic objective function that penalizes WIP deviation from targets 
and inrinite time horizon. Rule performs well in systems close to capacity. 

Gong and Matsuo (1990b) also consider a problem with multiple products, Umited 
workccnter capacity, rework, and re-entry. Again, they wish to minimize weighted WIP 
variance, where the weights in the objective are determined by a nonlinear program that 
minimizes total expected WIP. With sufficient conditions on the variance of yield and rework 
fractions, the authors find an optimal control policy for the associated dynamic program. An 
important conclusion is that the development of stable control policies in uncertain environments 
is challenging and depends upon the yield and rework distributions. 

In Ou and Wein (1991), the wafer fabrication system has a single bottleneck, multiple 
processes with re-entry, and by-products. The authors use for their model a single-server queue 
with job classes that correspond to different operations. The model's objective is to minimize 
total cost: the sum of holding costs for WIP (jobs waiting for re-entry) and finished goods and 
backorder costs. Their approach is to develop a control problem approximation involving 
Brownian motion. The optimal control policy can be interpreted as the optimal schedule. The 
authors compare their policy to two state-dependent heuristic policies with a simulation and find 
that their policy reduces costs. 



27 

Knowlcdgc-bascd approaches . Many researchers have attempted to give managers better 
control of the shop floor with decision support and expert systems, which incorporate knowledge 
that can be used to set control policies or schedule machines. Some expert systems can even 
perform scheduling events themselves. 

Adachi, Moodie, and Talavage (1988) consider a production system with re-entrant product 
flows. They use a simulation model to examine the effect of management decision variables on 
system performance. The variables are lot size, dispatching rules, start rate, frequency of urgent 
jobs, and frequency of machine breakdowns. The measures are product mix, throughput, cycle 
time, and WIP. 

The authors report that the start rate was a more important factor than the dispatching rules. 
The lot sizes also had significant effects. The dispatching rules were important policies only in 
over-capacity shops. The authors then develop a pattern recognition DSS that, through an 
iterative procedure, helps the user find a system that matches the user-defined goals. A prototype 
is implemented on the printed circuit board fabrication line at NEC Corporation. 

In Adachi, Moodie, and Talavage (1989), the authors extend their work on production 
systems with re-entrant product flows. This time, the decision support system includes a rule- 
based component and simulation model. The simulation model comes from the previous work 
and evaluates the effect of control variables on measures of inventory, product mix, cycle time, 
throughput. The results are used to obtain regression coefficients, which are stored in a database 
for the rule-based component, which organizes the control variables into the hierarchy of start 
rate, lot size, and priority rule. This DSS was implemented for a printed circuit board fabrication 
line, resulting in superior control policies to the previous pattern recognition DSS. 

Adelsbergcr and Kanet (1991) report on a new tool in computer-aided manufacturing 
scheduling: the leitstand, a decision support system with a computer-aided graphical interface. 
Leitstands include the following components: the graphics component is a electronic Gantt chart; 
a schedule editor allows a user to easily change an existing production schedule; the data base 
manager incorporates data from production planning system, engineering, and shop floor and 



28 

uses specific knowledge; an evaluation component measures the schedules on objective functions 
and creates reports; and an advanced automatic schedule generator produces feasible schedules. 

Savell, Perez, and Koh (1989) describe scheduling semiconductor wafer production with an 
expert system that takes advantage of the modularity of workcenters and sophisticated data 
analysis. The wafer fab is divided into into thirty cells. The expert system, which is an off-the- 
shelf PC package with some external routines for data manipulation, creates daily schedules. It 
includes two modules: (1) the priority assignment module uses information from CAM about the 
operational slack of each lot and knowledge about special lots; and (2) the equipment scheduling 
module for each cell uses specific knowledge about the cell and the lot priorities to create a 
schedule for the lots in the cell and those arriving at the cell within a certain time frame. The 
expert system is implemented in two cells (P-Diffusion and Aluminum Deposition) at Harris 
Semiconductor. 

Sullivan and Fordyce (1990) report on IBM Burlington's Logistics Management System for 
wafer fabrication. The main function is the shop fioor dispatching of lots. It replaces slack lead 
times with information to handle the coupling of strategic and operational decisions. 

The LMS includes real-lime lot and machine status and proactive intervention, with an 
expert system that has knowledge about generating alerts in certain conditions and responding to 
some of these by making dispatch decisions that consider five conflicting objectives: lot priority, 
on-time delivery, fiow requirements, increasing throughput, meeting engineering specifications. 
The LMS is implemented in various areas and realizes the importance of accurate data and 
continual updating to reflect changing environment. 

Fordyce et al. (1992) discuss the current version of the Logistics Management System 
(LMS) in place at the IBM Buriington Semiconductor manufacturing site. The emphasis of this 
paper is on the last of the four tiers of the scheduling decision hierarchy. This is dispatch or 
short-interval scheduling for periods from one hour lo two weeks. This tier contains the decisions 
concerning the actual manufacturing flow, including the scheduling of an operation. The LMS 
contains a dispatcher/short-intcrval-schedulcr, that creates zones of control around the botUcneck 



29 

points, which may a sequence of operations that lots must visit repeatedly. Kanbans within these 
zones monitor the WIP level for the different passes through the zone. The dispatching is done 
by something called a Judge. The Judge receives information from goal advocates in order to 
make its decision, and the different advocates have different goals, including meeting due dates, 
meeting the daily plan, maintaining low WIP (this is the goal of the kanbans), and increasing 
machine utilization (this includes minimizing setups). 

Hadavi etal. (1991) present a distributed architecture for real-time scheduling and describe 
its implementation in a wafer fabrication factory. The system (ReDS) works to meet 
management objectives of meeting due dates, reducing WIP and finished goods inventory, 
reducing cycle times, and maximizing machine utilization. The system abstracts constraints and 
time into a tree with nodes that correspond to an interval of time; it also abstracts an order into an 
"essence function" that describes its critical resources. The release policy uses "continuity 
indices" to reduce cycle times. The modules in the system include a preprocessor to abstract the 
constraints and orders and a feasibility analysis to release orders. Also in the system are a 
detailed scheduling module that uses least commitment planning in determining a daily or shift 
schedule. A sequencer then dispatches the operations scheduled for a time period by using a 
dynamic sequencing rule that responds in real time to a changing floor. 

Rao and Lingaraj (1988) review a number of expert systems for production and operations 
management decision making. They classify the systems along two dimensions: strategic 
decisions versus tactical decisions and operations orientation versus resources orientation. 
Scheduling systems are classified as tactical, operations-oriented applicaUons. They review a 
number of systems in scheduling, capacity planning, facility layout, process & product design, 
quality control, aggregate planning, inventory control, and maintenance & reliability. They 
conclude that expert systems should combine technological knowledge and logistical data in 
order to be effective. 



30 

ISIS (Fox and Smith. 1984) is an expert system for scheduling that uses a hierarchical 
approach to scheduling: job selection, capacity analysis, resource analysis, and reservation 
selection. It uses decisions made at each level as constraints for the lower levels. 

Opportunistic scheduling is a knowledge -based approach introduced in the OPIS system 
(Smith, Fox, and Ow, 1986, and Ow and Smith, 1988). In this system, the authors extend the job- 
oriented scheduler of ISIS with a machine-oriented scheduling procedure. After identifying an 
initial bottleneck, the search for a good schedule proceeds by directing activity towards the 
bottleneck subproblems of the job shop scheduling problem. The characteristics of this system 
include alternative problem decompositions, multiple scheduling heuristics, and multiple problem 
abstraction. 

Sadeh (1991) discusses a system called MICRO-BOSS, another opportunistic scheduler 
that identifies an initial bottleneck and revises its strategy as new bottlenecks emerge during the 
construction of the schedule. This system is a more flexible procedure, however, for it can revise 
its scheduling strategy after each operation. Thus, it avoids having to scheduling large 
subproblems for a machine or a job. 

Bensana, Bel, and Dubois (1988) describe a system called OPAL, a job shop scheduling 
software that combines three types of knowledge: theoretical knowledge about scheduling 
problems, empirical knowledge about scheduling heuristics, and practical knowledge of the 
scheduling environment. They claim that combining artificial intelligence techniques with 
operations research should be an effective approach to scheduling problems. 

OPT and other approaches . OPT (Optimized Production Technology) is a proprietary 
scheduling system that focuses on the scheduling of the bottleneck resource. The system has 
been reviewed by a number of authors, including Jacobs (1984), Meleton (1986), Lundrigan 
(1986), and Vollman (1986). OPT uses a forward finite-loading scheduling procedure to 
schedule the identified bottleneck. The remaining, non-critical operations are scheduled using an 
backward infinite-loading procedure. According to Morton (1992), the advantages of OPT are its 
good solutions to large scheduling problems and its focus on the bottlenecks. Disadvantages 



31 

include the inability to do reactive scheduling without resolving the whole problem. Details 
about OFT can be found in the above articles and in VoUmann, Berry and Whybark (Chapter 20, 
1988). 

Faaland and Schmitt (1993) use a cost-based system to enhance the planning function of 
MRP in an assembly shop. They developed a system that can create a detailed schedule of jobs, 
workers, and work centers for a maker of aircraft audio, power, and light systems. They include 
inventory holding costs associated with finishing early, opportunity costs associated with late 
delivery, and payroll costs, since the model includes the cross-training of workers. 

Morton (Chapter 16, 1992) describes an early version of bottleneck dynamics called 
SCHED-STAR (initially reported in Morton et al., 1988). This system iterated lead times and 
prices over the bottleneck and considered an objective function that included revenue, tardiness, 
direct completion costs, and holding costs. A number of release and dispatch heuristics were 
studied on a variety of shop situations, and the authors conclude that bottleneck dynamics (and 
iterated pricing and lead times) leads to better schedules. 

Simulation scheduling . Primarily, simulation models are used to predict the performance of 
certain policies. However, once the policies are set, the simulation model can be used to create a 
feasible schedule for the shop floor. 

Atherton (1988) states that simulation can be used on all levels of planning. For short-term 
scheduling, models may perform short-interval and shopnAoor scheduling. This form of 
scheduling considers factory capacity (dispatching rules don't). A validated simulation model, 
provided with current information on the system status, can use rules to determine what will 
happen in the short term, providing a shop floor schedule. If the projected lot completions do not 
meet production requirements, further simulations may be necessary to find a schedule that is 
close to the goal. 

Leachman and Sohoni attack the problem of semiconductor manufacturing using an 
automated scheduling system and teamwork-fostering management. For every shift, a target is 
set that considers the real Ooor. The entire staff meets to identify problems and propose 



32 

solutions. The targets arc generated by the scheduling system: a simulation model of the wafer 
fab in BLOCS that is linked to the WIP tracking system, providing it with real-time data. The 
simulation considers availability but assumes perfect execution. Thus, it is fair and accurate. To 
make the schedule, it uses logic accepted by the staff, including least slack, FIFO, and starvation 
avoidance rules and furnace waiting cost analysis. 

The authors discuss how a shift proceeds: meetings before and after the shift with explicit 
incentives for meeting the target. They also review the organizational effectiveness of their 
approach in terms of motivation, satisfaction, communication and coordination, problem solving 
capability, acceptance of change. 

Najmi and Lozinski (1989) discuss the implementation of the system in two wafer fabs at 
NCR, Inc. The simulation model is written in BLOCS, an object-oriented language where each 
physical object or collection of data is a object (composed of data and procedures), and the 
objects communicate to each other with messages that represent the interaction of objects. 

2.2.3 Performance Evaluation 

The complexity of semiconductor fabrication facilities makes direct analytical evaluation of 
them difficult at best. In many cases, researchers use queueing models or simulation models in 
order to gain some insight on how the system performs in the current or some proposed 
environment. 

Burman et al. (1986) discuss the ways that OR tools and techniques are used to analyze IC 
manufacturing hnes: simulation, queueing analysis, and deterministic capacity models. The 
authors describe a simulation study for direct step on wafer printers in photolithography. The 
study determined the effect of lot size, number of products, and setup time on capacity and WIP. 
It also used large-scale simulations to obtain arrival distributions to this area. A deterministic 
capacity model of a clean room uses the mean number of steps and the mean process time. The 
analysis took much less computing time than a simulation. The model was useful for estimating a 
room's capacity and determining the minimal number of machines required for a proposed 



33 

program. They conclude that simulation models have the greatest flexibility and best success but 
take considerable time to develop and run. The other techniques arc quicker and, if not quite 
accurate, do provide estimates that may be verified in simulation. 

Oucucinp models . Queueing models attempt to model the shop floor as a set of servers 
with service time distributions and possible stochastic routings. The system yields a set of 
equations that describe its behavior. Because the success of solving these equations is usually 
undermined by the complexity of the shop being modelled, researchers are forced to make 
simplifying assumptions. 

Chen et al. (1988) develop a simple queueing network model to predict performance 
measures in an research and development wafer fab. The Hewlett-Packard Technology Research 
Center Silicon Wafer fab serves as the model. The model is a classic job shop, and the 
performance measures are throughput and cycle time. Machine breakdown rates added to actual 
service time to create an effective service time. The naive queueing network model includes 
different types of customers that have different routing distributions. Straightforward formulas 
from previous researchers yield performance measures. The authors report that the model yielded 
performance measures that were within 10% of the actual numbers. 

Wein (1991) investigates a wafer wafer fab with time-dependent stochastic defects, using a 
simple queueing theoretic model to determine the relationship of yield and cycle time to 
throughput. The model is a single-server queueing system with exponential arrival and service 
times. The author derives a closed form relationship between the mean cycle time and the 
throughput of good die. In standard models, as the start rate is increased, the throughput 
increases and asymptotically approaches some upper bound as cycle times increase to infinity. In 
this model, the cycle times increase without bound but throughput reaches some maximum and 
then decreases as the increased cycle time leads to a higher defect rate (and thus less yield). 

Simulation . Simulation models remain as a popular approach to measuring the 
performance of manufacturing system, and many packages have been developed. The state of the 



34 

art is probably the BLOCS package developed at California-Berkeley and partially described in 
Najmi and Lozinski (1989). The following papers report on some uses of simulation. 

In two papers, Dayhoff and Atherion (1986 a.b) develop simulation models of wafer fabs. 
They model wafer fab as a qucucing network with components for each lot and process flow. 
Models are used to analyze system performance, measured by its signature: the plots of cycle 
time, inventory level, and throughput versus start rate. The signature provides a way to gain 
information from the large quantity of data provided by a simulation by displaying the 
relationships among different variables. As a specific example, they model a bipolar wafer fab. 

They compare the signatures for a number of dispatch schemes for a bipolar wafer fab 
where products visit the masking station seven times. In the wafer fab, there exist three levels of 
dispatching: (1) among lots of one product waiting for one process, (2) among process steps of 
the same product, (3) among products. This paper works at level two; the first level is done by 
FIFO, third by product priority. The study compares the following dispatch schemes for 
masking: earlier steps first (a form of longest remaining processing time), later steps first (a form 
of shortest remaining processing fime), round-robin (changing priority). Qualitative analysis 
shows that earlier steps first failed at higher start rates by building inventory and that the later 
steps first was better by getting higher throughput with no increase in inventory. 

Dayhoff and Atherton (1987) provide definitions of the elements of wafer fabrication and 
their interactions. They idenfify the important parameters that govern wafer wafer fab and result 
from wafer fab operations. The elements defined include work station, process flow, products, 
wafer lot, process step, batch, batching down, service, dispatch system, rework, and wafer fab 
graph. They discuss the following types of simulation results: average wait times, queue lengths, 
inventory, cycle time, equipment utilization, yield, throughput. 

Atherton and Pool (1989) discuss the ACHILLES simulation model in a wafer wafer fab of 
Silicon Systems, Inc. The describe the model and its initialization, calibration, and validation by 
comparison to actual measures of factory performance. The discuss the use of the model to 
predict the effect of reducing inventory levels on cycle-umes. 



L_ 



35 

Spcncc and Welter (1987) discuss a project by Stanford University and Motorola Inc. that 
allempLs to improve the performance of a semiconductor wafer fabrication line. The goal is to 
increase the tha>ughpul of the line without sacrificing cycle lime. The analysis was done with a 
Monte Carlo simulation to determine capacity, defined as throughput rate, cycle time, and WIP. 
The performance was measured on the steady-state cycle-time vs throughput trade-off curve, 
instead of using transient signatures (c.f. Dayhoff and Atherton). The photolithography cell was 
studied for its analytical difficulty, the build up of WIP in this cell, and the proposal of system 
changes. The authors report that adding resources (operators, aligner equipment) reduced cycle 
lime at higher throughput. Reducing reworks, setup times, and the time to wait for repair reduced 
cycle times at all levels. Larger lot sizes were preferable at higher throughputs. 

2.2.4 Summary 

From this review, it can be seen that many different approaches have been applied to the 
problems of production planning and scheduling. However, most of this work addresses the 
questions raised in wafer fabrication. The primary exceptions are Uzsoy, Lee, and Martin-Vega 
(1992b), Uzsoy et al. (1991a, 1991b), Lee, Uzsoy, and Martin- Vega (1992), and Lee etal. (1993) 
which do explicitly consider the problems of semiconductor test. However, this work does not 
make use of the new, sophisticated heuristic searches and is not concerned with the ideas of class 
scheduling and look-ahead and look-behind scheduling. 

Although Savell, Perez, and Koh (1989) do develop a system that is look-behind, it is 
implemented in an off-line system in a wafer fabrication cell. The research in this dissertation, 
however, investigates the application of both look-behind and look-ahead rules into the current 
real-time dispatching system of a semiconductor test area. 



36 



2.3 Job Shop Scheduling 

Before beginning the analysis of scheduling problems, it is useful to review the notation to 
be used and the basics of scheduling problems. Because even the simplest job shop scheduling 
problems arc NP-complclc, the literature consists of different heuristics. 

Job shop scheduling, as one of the most difficult scheduling problems, has attracted a lot of 
attention from researchers. Techniques such as the shifting bottleneck algorithm (Adams, Balas, 
and Zawack, 1988) or bottleneck dynamics (described in Morton, 1992) concentrate on solving 
the problem at one machine at a time. Other researchers have studied how well different 
dispatching rules perform in minimizing makespan and other objective functions. Panwalkar and 
Iskander (1977) present a list of over 1(X) rules. Recent studies include Fry, Philipoom, and 
Blackstone (1988) and Vepsalainen and Morton (1988). Various scheduling systems for shop 
floor control are reviewed in Section 2.2. More sophisticated look-ahead and look-behind rules 
have also been introduced; see Section 2.5 for a discussion of these ideas. In this section we 
review scheduling notation, the shifting bottleneck algorithm, and dispatching rules. 

2.3.1 Scheduling Notation 

In the general job shop scheduling problem, there exists a set of jobs Jj,j = 1 , ..., n, and set 
of machine Mj, / = 1, ..., m. Eachjob/.-has /i; operations (or tasks) Oy, i = 1, ..., nj, where 0,-.= 
k if the ith operation of 7.- is to be processed on machine Mj^. In a flow shop, all nj = m and 
Oij = / for aU /. In general, each operation has a processing time /?,■.- > 0. A job can have release 
dates r: and due dates d: and deadlines D .-. 

A feasible schedule o is a plan that determines when each operation is processed on each 
machine subject to the following constraints: the operations of each job must be performed in 
order, and no machine can process more than one operation at at time. 

For a schedule, certain performance measures can be associated with a job/.-: the 
completion time C.-, the lateness L: = C: - d-., the tardiness T: = max {L.-, 0), and whether or not 



37 

the job is lardy, U; = 1 if T.- > and otherwise. Objective functions that measure the 
performance of the schedule include the makcspan, Cf^^^j^^ = max [Cj], the total flowtime X C., 
and the number of lardy jobs X U:. 

The scheduling problem is to find a feasible schedule that minimizes the objective function. 
For the regular performance measures mentioned above, the set of schedules that need lo be 
considered is the set of active schedules, where no operation can be started earlier without 
causing another operation to be delayed. In this set, there exists a one-to-one correspondence 
between a schedule and its representation by a sequence of operations for each machine. Thus, a 
sequence that orders ihe jobs on each machine can be considered a solution to the problem. 

Standard scheduling problems can be classified in a concise way by using the following 
three-element description: x/y / z. The field x describes the machine environment as one- 
machine, parallel-machine, or shop. The second field (y) describes any constraints or special 
characteristics of the problem. The third field (z) describes the objective function. Consider the 
following examples: 

1 / '■/ / S Uj is a one-machine problem where the jobs have release dates and the objective is to 
minimize the maximum lateness. 

I / Dj/'Z Cj is the one-machine problem where the jobs have deadlines and the objective is to 

minimize the total nowtimc. 

F2 / / Cf^i^jj^ is the two-machine flowshop problem of minimizing the makespan. 
J / / C^^j^j^ is the general job shop scheduling problem of minimizing makespan. 

2.3.2 Shifting Bottleneck 

Adams, Balas, and Zawack (1988) introduce the Shifting Bottleneck procedure to minimize 
the makespan of job shop scheduling. This algorithm sequences the machines in a job shop 
successively by identifying the machine that is a bottleneck among the machines not yet 
sequenced. After the scheduling of the new bottleneck, all of the previously-considered machines 



38 

have their schedules readjusted. The individual steps involve finding the solution to one-machine 
problems. 

The authors lean heavily on the disjunctive graph associated with the job shop scheduling 
problem. In this graph, there exists a node for each operation to be performed as well as dummy 
start and termination nodes. For each job there exist directed arcs from each operation to its 
successor and an arc from the start to the first operation and an arc from the last operation to the 
termination. For each machine, there exist a pair of disjunctive arcs between each pair of 
operations on this machine. All of the arcs have a length equal to the processing time of the head 
operation. 

If a selection is made for the disjunctive arcs of each machine and the corresponding graph 
is non-cyclic, a schedule for the entire shop is made by scheduling each job as soon as possible 
under the constraints imposed by the selections and the job operation sequence. The makespan of 
the schedule is equal to the longest path from the start node to the termination node. 

The Shifting Bottleneck procedure iteratively selects a bottleneck machine, schedules this 
machine, and readjusts all previously-scheduled machines. Given that a set of machines has been 
scheduled, procedure determines the bottleneck by considering each unscheduled machine 
individually. This yields a one-machine problem where the minimization of the makespan for the 
shop is equivalent to minimizing the maximum lateness of the operations on this machine. The 
minimization problem is NP-complete, but the authors use the algorithm of Carlier, a branch-and- 
bound procedure that gives excellent results. The machine that has the largest such maximum 
lateness is the bottleneck, and that machine is added to the set of scheduled machines. 

The local reoptimization procedure considers the set of scheduled machines and performs a 
number of cycles. Each cycle consists of solving the one machine problem for each machine in 
turn, using the selections found for all of the other machines. 

The authors report that the Shifting Bottleneck procedure performs exceptionally well, 
including finding the optimal makespan for the notorious 10-job and 10-machine problem of 
Giffier and Thompson. 



39 



2.3.3 Dispatching Rules 

Because of the complexity of job shop scheduhng, algorithms to find the optimal solution 
for any arbitrary objective function do not exist. Thus, researchers have studied and schedulers 
have used dispatching rules to order the jobs wailing for processing at a machine. Most of the 
research in this area has examined the performance of various despatching rules, which sequence 
the jobs that arc waiting for a machine according to some statistic that is a function of the jobs' 
characteri.stics. 

When a machine becomes available, it chooses from among the jobs in its queue by using a 
rule that sorts the jobs by some criteria. Common dispatching rules employ processing times and 
due dates in simple rules and complex combinations. 

These dispatching rules are sometimes extensions from simple one-machine problems. For 
instance, the Shortest Processing Time (SPT) algorithm is known to minimize the total flowtime 
of jobs processed on one machine. The SPT dispatching rule sorts jobs waiting for a machine by 
the amount of processing time they require on the machine. Also, the Earliest Due Date (EDD) 
algorithm is known to minimize the maximum lateness of a set of jobs being processed on one 
machine. The EDD dispatching rule is used in job shop scheduling in an attempt to reduce 
maximum lateness. While the list of known dispatching rules includes over 100 items, only a 
handful are commonly used. And most of the rest are combinations of the most common rules. 

Day and Hottenstein (1970) present a review of sequencing research, in which they discuss 
Jackson's Decomposition Principle (1967), which assumes that the arrival times for each job 
arriving from outside the system are exponentially distributed, the processing times at each 
machine are exponentially distributed, the jobs are routed to a machine by a fixed probability 
transition matrix, and the priority rule at each machine is First-Come-First-Served (FCFS). 

They also discuss several due dale assignment schemes presented by Conway (1965). 
These are CON (constant from the order to the due date), RAN (random: due date chosen by 
customer and accepted by salesman), TWK (Total Work Content: the allowable shop time is 



40 

proportional to the sum of the processing times of the operations of the job), and NOP (Number 
of Operations: the allowable shop time is proportional to the number of operations). 

The authors also review the previous research on dispatching rules by Conway (1965), who 
compared SI to 3 1 other rules and found that it dominated the set of rules tested. It is simpler and 
easier to implement. However, the biggest objection to SI is the following fact: if the mean time 
which jobs spend in the system is small, individual jobs (those with long operations) may be 
intolerably delayed. Thus the variance of the lateness distribution is the basic disadvantage of the 
SI mle. Conway tried three methods to reduce the variance: (i) Alternating the SI rule with a low 
variance rule (with respect to flowtime) to periodically clean out the shop, (ii) forcibly truncating 
the SI rule by imposing a limit on the delay that individual jobs will tolerate; and (iii) dividing 
jobs into two classes, preferred and regular, as the primary criteria, leaving SI as a secondary 
criteria. 

The authors then move to the COVERT dispatching rule. Buffa (1968) retained the 
performance of the SI rule and tended to minimize the extreme completion delays of a few orders. 
Trilling (1966) used a ratio of delay cost rate of a job to the processing time of that job on the 
machine in question. The job with the highest ratio is dispatched first. 

The authors also report on the priority rules employed in industry, where job lateness is a 
primary concern. Hence, EDD and least slack rules are most used. However, LPT becomes a 
popular rule because schedulers rank jobs by the index of importance and it is reasonable to 
expect some positive correlation between importance and processing time. 

HoUoway and Nelson (1974) study the problem of job shop scheduling with stochastic 
processing times. Their performance measures are the mean, variance, and maximum of 
tardiness. For dispatching, the authors use HSP, a multi-pass heuristic that produces delay 
schedules, HSP-NDT (a non-delay version), DDATE, SPT, SLACK, and a SPT-SLACK 
combination. 

The authors study three problems of different size, tightness, and utilization, where the 
processing times were constant or from one of three distributions. They report that HSP did well 



41 

on low-variance problems and on maximum tardiness. HSP-NDT beat HSP in some situations. 
Of the non-delay ailcs, the deterministic problems were a good predictor of relative performance 
on problems with variability. DDATE improved its relative performance as variability of 
processing times increased. 

Panwalkar and Iskander (1977) list 100 dispatching rules. They categorize these rules into 
five classes: simple dispatching rules, combinations of simple rules, weighted priority indexes, 
heuristic scheduling rules, and other rules. The simple dispatching rules are organized into 
processing time, due date, number of operations, cost, setup time, arrival time, and machine rules. 
Combination rules sequence jobs by considering first one characteristic and then another. 
Weighted priority indexes .sequence jobs by combining values from different job characteristics 
(by adding or dividing). 

Blackstone, Phillips, and Hogg (1982) state that the best measure of performance is cost 
effectiveness. Their work covers this objective function and others: tardiness, lateness, flowtime, 
inventory. They note that analytic measures depend upon Jackson's decomposition, which 
assumes a FIFO dispatching rule. Other rules lead to interrelated queues and thus researchers use 
simulation. 

For the single-server model, it is known that SI (shortest imminent processing time) 
minimizes mean flowtime and mean lateness and EDD (earliest due date) minimizes maximum 
lateness and maximum tardiness. Mean tardiness cannot be optimized by any dispatching rule; 
thus, the authors conclude that "no single dispatching rule yet developed will optimize delay costs 
in the job shop environment." 

The authors consider a number of dispatching rules. Their first is SI. They report that SI is 
not affected much by imperfect data, it performed best on mean flowtime, and it minimized the 
number of tardy jobs and mean lateness for exogenous (constant and random) due date 
assignment. It also perfonned better when internal due dates are less than seven times processing 
time and utilization is high. Modifications to SI to clear jobs that have been waiting include 



42 

alternating rules and truncation. Truncation versions seem useful for shops having control over 
due dales and concerned about very late jobs. 

The authors also consider a number of due date rules: EDD, Slack, and Slack-pcr-opcralion. 
Slack-per-opcrdtion is the best and, compared to SI or FIFO, produces a smaller variance of job 
lateness independent of due date assignment. Compared to EDD and slack, it performs best on 
lateness variance, cost-per-order, job tardiness, number of lardy jobs. Slack may be defined in 
static or dynamic terms, although rules ihal use ihe latter are better. The authors also report that 
critical ratio rules are also in use. 

Among rules that used neither processing time nor due date information are FIFO and NOP 
(number of operations). The authors report that both perform worse than other good rules. They 
also conclude that the look ahead-rules NINQ (number in next queue) and WINQ (work in next 
queue) are not as good as SI in flowtime and inventory criteria and that a value-based rule usually 
becomes longest processing time, which generally behaves poorly. 

The authors report that weighted combinatorial rules are not belter than any single rule, 
although COVERT (delay cost over time remaining) may be useful in shops willing to estimate 
delay costs. The authors also discuss dispatching heuristics. The look-ahead heuristic LAH 
allows insertion of idle time in order to process a critical job. Heuristics improve the 
performance of dispatching rules but their implementation may not be cost effective; a complete 
study has not been done. 

Green and Appel (1981) examine the problem of job shop scheduling by asking the 
following questions: What traditional dispatching rules do experienced schedulers select? Would 
dispatch rule selection be influenced by urgency? Would schedulers select a dispatch order based 
on organizational influence and/or peer pressure? The authors asked schedulers in a number of 
plants to denote which of the following rules they used: Due Date, Slack, Operations Due Date, 
Slack per Operations, SPT, FCFS, COVERT, Program in Greatest Trouble (PGT), or Friend 
Needs a Favor (FNF). The authors report that influence systems affect scheduling. PGT (a 



43 

coalition rule) was highly valued, but FNF (an individual nilc) was rejected. Traditional and 
theoretical rules were not highly valued. 

Kanet and Hayya (1982) also consider the problem of job shop scheduling. Their paper 
tries to determine if operation due dates are better. Their comparison is done by running 
controlled simulation experiments using the following dispatching rules: Earliest Due Date: 
DDATE and OPNDD; Smallest Job Slack: SLACK and OPSLK; Critical ratio: CR and OPCR. 
The slack is static; the critical ratio is dynamic: time until due-date over remaining allowance or 
operation allowance. For critical ratio, each operation must be assigned an allowance. This 
allowance is proportional to the processing time. The allowance multiple controls the difficulty 
of meeting due dates. 

The authors consider the performance measures of lateness (mean and standard deviation), 
fraction tardy, conditional mean tardiness, flowtime (mean and standard deviation), and 
maximum tardiness. The authors report that all rules were outperformed by their operation 
counterparts on all measures. Introducing operation due dates shifts distribution of job lateness to 
the left (less) and compresses it. One unexpected result was that OPNDD (due date) 
outperformed OPSLK (slack) and always minimized maximum tardiness. The CR rule gives 
lower lateness variances, but the OPCR rule was even better. The authors note that, as the 
allowance multiple is increased, due dates become larger and DDATE and SLACK rules act more 
like SPT, minimizing flowtime. For the critical ratio rules, a larger allowance means longer jobs 
get lower ratios, causing CR to act like LPT. 

Baker and Bertrand (1982) take up the problem of single-machine dynamic scheduling and 
study different due date assignment methods and dispatching rules. They are concerned with 
average tardiness. The authors introduce a new dispatching rule: the modified due date rule 
(MDD), where the modified due date is defined as the maximum of the due date and earliest 
finish date. This rule is a combination of EDD and SPT that implicitly responds to changes in the 
amount of slack. The authors report that MDD dominates both SPT and EDD on average 
tardiness. 



44 

Baker and Kanct (1983) extend the MDD rule to attack the problem of job shop scheduling. 
They consider the performance measures of mean job tardiness and proportion of tardy jobs. 
They introduce the modified operation due dale rule (MOD), where the modified operation due 
date is the maximum of operation due date and earliest operation finish time. The authors also 
consider other dynamic rules: Slack per operation, Critical ratio, and COVERT under different 
allowances and utilization levels. 

The authors report the following results: MOD performs better than MDD and SPT and is 
sometimes better than operation due date, critical ratio, and slack per operation rules. The 
authors thus conclude that MOD is an important dispatching mechanism. 

Baker (1984) considers the job shop scheduling problem and attempts to clarify some 
conflicting results between different rules of dispatching and due-date assignments. He points 
out that two factors are of primary interest: flowtime and due-date performance. He reports that 
SPT is the best tactic for reducing mean flowtime. However, no single priority rule dominates 
performance comparisons. He reports that the critical ratio is best for minimizing conditional 
mean tardiness (that is, the average tardiness of tardy jobs); SPT is best for number of tardy jobs; 
however, for mean tardiness, the results are mixed. 

Fry, Philipoom, and Blackstone (1988) consider the problem of job shop scheduling with 
90% utilization. For the due date assignment, they use the total work method with two different 
allowances. They consider the following performance measures: mean flowtime, mean tardiness, 
and root mean square tardiness (designed to punish large tardiness). 

They study truncated and alternating versions of the SPT dispatching rule. The authors 
define the critical percentage (%C) as the percentage of jobs that enter a higher priority queue 
because they have been waiting a long time. They report that the best rule depends upon the this 
critical value. 

Vepsalaincn and Morton (1987, 1988) consider the problem of minimizing weighted 
tardiness in job shop scheduling. They use the following dispatching rules: FCFS, EDD, Slack 
per remaining processing time (S/RPT), WSPT, weighted COVERT, and Apparent Tardiness 



45 

Cost (ATC). A lead lime eslimalion is necessary for last two rules. Lead time estimates arc 
computed as a fixed multiple of processing times, derived from rough waiting-line analysis and 
job priority indices, or found from iterating simulations. 

The authors first studied the flow shop problem, where ATC and COVERT dominated 
using any lead-time estimate. Using the iteration estimate resulted in better weighted tardiness. 
ATC did better on fraction of jobs tardy and inventory measures. In the job shop, under different 
loads and due date tightnesses, the authors report that the ATC rule did better, followed closely 
by COVERT. The use of the priority estimates yielded a smaller fraction of jobs tardy. 

2.3.4 Summary 

In addition to introducing some notation, this section covered two important methods of job 
shop scheduling: the shifting bottleneck procedure and dispatching rules. Both methods have 
limitations, however. The shifting bottleneck procedure searches for a schedule and continuously 
improves upon it. Thus, it is only a local search technique. The dispatching rules that have been 
studied are mainly short-sighted techniques that do not consider other machines. The research in 
this dissertation extends this work by considering smart-and-lucky searches and investigating 
look-ahead and look-behind dispatching rules. 

2.4 Flow Shop Scheduling 

This dissertation considers a three-machine problem where all jobs are processed on a 
certain machine and then go to one of two second-stage machines. This problem is similar to a 
flow shop, and it was useful to review the flow shop scheduling problems that have been 
previously studied. 

The flow shop problem is actually a collection of problems that deal with the minimization 
of some regular objective function for a set of jobs in a flow shop, where each job consists of a 
number of different operations that must be processed on a set of machines. The primary feature 



46 

of a flow shop is thai the sequence of operations is the same for each job. That is, each follows 
the same path through the shop. 

All now shop analysis starts with Johnson (1954) who studied the minimization of 
makespan for two-machine flow shop problems and for some special three-machine flow shop 
problems. His algorithm starts jobs with the smallest tasks on machine 1 as soon as possible and 
jobs with the smallest tasks on machine 2 as late as possible. For the two- and three- machine 
cases, it can be shown that only permutation schedules need be considered. Permutation 
schedules are schedules for the machines in which the sequence of jobs is the same for each 
machine. Johnson showed that for four machines, passing may be necessary for optimality. 

Although most analytical research in shop scheduling has dealt with the makespan 
objective function, this research is interested in the minimization of total flowtime, also known as 
the mean completion time, the sum of completion times, the mean time in system, or the total 
time in system. Therefore, this section concentrates on a number of papers on the minimization 
of total flowtime, a less-commonly studied objective, and then moves on to other objectives, 
including maximum lateness, and the number of tardy jobs. Also included in this section are 
reports on some NP-completeness results and problems with separated setup times. 

2.4.1 Makespan 

Special cases of the flow shop makespan problem have been studied by a number of 
researchers, including Mitten (1958), Conway, Maxwell, and Miller (1967), Bums and Rooker 
(1975), and Szwarc (1977). Carey, Johnson, and Sethi (1976) proved that the general three- 
machine problem was NfP-complete. Problems with release dates, preemption, precedence 
constraints, or more than three machines have also been studied. 

2.4.2 Total Flowtime 

Ignall and Schrage (1965) describe a branch-and-bound algorithm for F2 // X C: and for 
F3 // C^ax- ^^^ ^^'^ '"^'^' nowiimc problem, the authors consider two values: the sum of 



47 

completion times if the first machine is the only capacity constraint and the sum if the second 
machine is the capacity constraint. The larger of these two values is the bound at each node. 

Krone and Slciglitz (1974) consider the static flow shop scheduling problem with the 
objective of minimizing the mean flowtime of n jobs that must visit m machines. They present a 
heuristic method. The authors note that two previous researchers performed separate sampling 
experiments of the flow shop scheduling problem. Heller concluded that permutation schedules 
should be investigated while Nugent found that good schedules tended to be permutation 
schedules that had allowed some jobs to pass others (a local reversal). 

For the flow shop problem, the authors consider semiactive schedules (where no operation 
can be shifted forward in time) and define a schedule as an array S that gives a sequence for each 
machine. S,-. is the job that is 7th on the /th machine. The authors define a two-phase heuristic. 
In the first phase, the search considers only permutation schedules. In the second phase, the 
search takes an initial permutation schedule and allows deviations from the uniform ordering. 
Each phase is a local search, although the neighborhood structures are different for each phase. 

Kohler and Steiglitz (1975) study the two-machine flow shop problem with the objective of 
minimizing the mean fiowtime. They present algorithms that they combine with lower bounds 
that guarantee the accuracy of the heuristics. The authors use the lower bound of Ignall and 
Schragc. They compute an initial solution by moving down a branch-and-bound tree without 
backtracking, selecting the node with the lowest lower bound at each stage. They consider 
different local searches, with either a random start or the above initialization, hillclimbing (first 
improvement), and one of four neighborhood structures: backward insertion, forward insertion, a 
double adjacent pair interchange (switches two pairs), and finally the union of the first and third. 

The authors report that the good iniualization helped the local search perform better than 
the random starting search. 

The authors then present three different branch-and-bound algorithms that differ in the way 
the nodes are eliminated. Since some of the algorithms exceed computational limits, they 
determine a bracket that is the relative difference between the final upper bound and the greatest 



48 

lower bound. If the goal is to find a solution that is within a certain amount of the optimal, this 
bracketing idea allows great speedup since a good (sometimes optimal) initial upper bound was 
used and the lower bound is very close. For a given r< 1 , the algorithm stops when the lower 
bound L is greater than or equal to r times the best upper bound i/, i.e., ril <L< optimal < U. 

Miyazaki, Nishiyama, and Hashimoto (1978) present a heuristic algorithm for F // X C,-. 
Given a sequence, the authors interchange two adjacent jobs and determine the change in 
flowtime. They then derive a number of conditions that are sufficient to say that the second job 
should never directly precede the first. Using these different conditions they create temporary 
sequences and assign each job an ordinal number corresponding to its place in these sequences. 
The jobs are then sorted by the sum of these values, (more here) 

Miyazaki and Nishiyama (1980) extend this work by creating permutation schedules for the 
weighted mean flowtime flow shop problem. The authors derive some precedence conditions and 
create an algorithm to generate good solutions. The first analysis considers the effect of 
interchanging two jobs in the permutation sequence to create. If this switch causes no decrease in 
the weighted flowtime, then the second job cannot directly precede the first in an optimal 
sequence. The authors then embark on finding a number of relations for two jobs that are 
independent of all other jobs and that will detenmine if a job should precede another. 

For their algorithm, the authors evaluate these various relations for each job. If each of the 
relations yields the same sequence, this sequence is optimal. If not, each job is given a value for 
each relation that is its perfonmance on the relation (l=best, . . .). These values are added over the 
relations and the jobs are ordered by these sums. 

Szwarc (1983) discusses the mean flowtime flow shop problem and a number of special 
cases. The author develops two properties that create a precedence relation between two jobs, the 
first for a fixed presequcnce, and the second for an arbitrary presequences. Using these 
properties, the author presents a special case of a 2-job problem, and a case where the final 
completion limes depend only on the completion times on some eariier machine. This last case 



49 

holds for the iwo-machinc case where the r/^ > t2r for all jobs J^ and the case where the columns 
and rows form a perfect order under dominance. 

Ahmadi et al. (1989) study the two-machine flow shop subproblcm with one or two batch 
processors as a segment of a larger job shop. They study the objective functions of makespan and 
total flowiimc. They consider two types of processors. The first is a batch processor that has a 
fixed capacity and the time necessary to process the jobs in a batch is a constant. The other type 
of processor is called a discrete processor, which refers to a standard single-machine processor. 
The authors consider the six types two-machine problems that can be formed. 

To minimize the makespan of a batch-discrete shop, full batches are optimal, permutation 
schedules dominate non-pcrmutalion schedules, and the optimal solution is to sequence jobs by 
LPT and fill each batch. For the discrete-batch shop, the analysis is similar, but in this case the 
jobs should be ordered by SPT. For two-batch-machine-shop, all of the jobs are equivalent. The 
optimal policy is to completely fill the batches on machine one and to use a dynamic program to 
fill the batches on machine 2, using the completion times on machine 1 as release dates. 

To minimize the total flowtime of a discrete-batch shop, SPT should sequence the jobs on 
the discrete machine 1. A dynamic program can be used to perform the batch dispatching on 
machine 2. For the two-batch-machine-shop, the batches on machine 1 should be completely 
filled and the completion times from this can be used as release dates to batch machine 2, which 
is dispatched using the same dynamic program. For the problem where a discrete processor is fed 
by a batch machine, the batches should be completely filled, but the authors prove that this case is 
strongly NP-complete. They do consider special cases relating the processing times on one 
machine to another and derive two optimal algorithms. 

For the NP-complete problem, the authors propose a heurisUc determines the number of 
shortest batches that are shorter than the batch processing time. To these batches the shortest jobs 
are dealt. The remaining jobs are sequenced by SPT to form batches. The authors show that the 
error tends to 1/2 as the number of batches tends to infinity. 



50 



Ahmadi and Bagchi (1990) present a lower bound on the total nowiimc. Given a partial 
schedule J^. of r jobs and fixing a machine 7, the authors bound the final completion times based 
on the completion times on machine;. Then, they search over sequences on machine 7, 
considering the sequence constraints and the machine) release dates for each job. This is the NP- 
hard problem of solving l/rVX C.. The authors solve the problem by allowing preemption. The 
lower bound is the greatest found by performing this procedure over each of the machines. 

Van de Velde (1990) studies the two-machine flow shop problem and minimizes the sum of 
completion times by using a Lagrangcan relaxation. The author decides to relax the precedence 
constraints between the two operations of a job (instead of the capacity constraints on each 

machine). Let the vector of multipliers be X = (^i, X2 A.„). The relaxed problem is one of 

minimizing the weighted sum of operation completion times, solved by SWPT on each machine 
separately. The author, however, wants to restrict the solution to permutation schedules. 

Thus, the author reformulates the problem into a linear ordering problem, which is 
polynomially solvable in certain cases. The author lets all X,j = c, where < c < 1, and if c = or 
c = 1 , the problem yields the bounds of Ignall and Schrage. Thus, for c, the relaxation can be 
solved optimally with a permutation schedule. The author claims that the lower bound as a 
function of c is continuous, concave, piecewise-Iinear function, and the maximum can be found in 
polynomial time. 

One partial sequence dominates another if the sum of completion times is smaller and the 
makespan is also smaller. The author develops a number of sufficient conditions for dominance. 
Also, if P2/ - P2i ^^^ Pli - Plh '^'^" ^^ author proves that there exists an optimal sequence 
where job i precedes job j. 

2.4.3 Maximum Lateness (Lmax) 

Masuda, Ishii, and Nishida (1983) find a solvable case oiVll I L^^^^ and present an 
algorithm for the general problem with a worst case bound. The authors first prove that the HDD 
sequence is an optimal schedule if for i and j : rf^ <d.if andonly if min {fl/.fc,} <min {a;,ft,}. 



51 

This says ihat the EDD and Johnson sequence arc the same. However, this property docs not 
provide any precedence for the general case, but the authors schedule the jobs according to EDD 
and give an error bound that is tight asymptotically. 

Grabowski, Skubalska, and Smutnicki (1983) the flow shop problem of minimizing 
maximum lateness with release dates. They analyze two lower bounds, one with one bottleneck 
machine and a non-bottleneck preceding it and the other with two bottleneck machines and a non- 
botdcneck between them. 

2.4.4 Numbcrof Tardv Jobs 

Hariri and Potts (1989) consider a permutation flow shop and develop a lower bound and a 
branch-and-bound procedure to minimize the number of tardy jobs. This problem is NP-hard. 
For a given partial sequence and a machine j, we can consider the time this machine is available, 
disregard the processing before machine j and suppose that the machines after machine j have 
infinite capacity. The additional processing can be subtracted from the due date and The Moore- 
Hodgson algorithm applied to find a minimum number of late jobs. Applying this procedure to 
each of the machines yields a lower bound. 

The authors derive another bound using the consistent early set, a set of jobs that is feasibly 
early for each of the machine subproblems. The size of the smallest consistent late set (a set 
whose complement is a consistent early set) is the lower bound. The authors extend this to the 
idea of a consistent feasible early sequence for single-machine and r-machine problems. 

In generating problems to test their bounds, the authors set due dates that were uniformly 
distributed in a range proportional to an estimate of the total processing time. The fractions 
ranged from 0.2 to 1.0. The branch-and-bound algorithm with the simple bound was good 
enough for the small problems, but the use of consistent sequences yielded the most efficient 
procedure on the larger problems. The due date range of 0.4 to 0.6 yielded the hardest problems 
since the range was not great enough to guide sequencing and the due dates were tight. 



52 



2.4.5 General Tonics 

Garcy, Johnson, and Sethi (1976) prove a number of NP-complclcness proofs for 
scheduling problems. They do allow zero processing times. The authors begin by discussing 
some of the terms of NP-thcory. All of the proofs will be by transformation from 3-panition, 
which is NP-complete in the strong sense. 

The first proof is that of the ^^ 1 1 Cmax problem, where dummy jobs are created to give 
slots on the second machine that jobs corresponding the elements of A must fit. The next proof is 
for the F2 // E C: problem. Dummy jobs create slots on the second machine that dummy jobs of 
intermediate length and the jobs corresponding to the partition problem must fill. Long tasks are 
added to the end to insure that the spacers are completed as soon as possible. Lastly, they prove 
that ill I C^^ is NP-complete, although this depends upon a job that is re-entrant n times to 
machines 1 and 2. 

Gonzalez and Sahni (1978) consider a number of flow shop and job shop problems, with 
and without preemption, minimizing makespan and flowtime. The authors extend the makespan 
results to the preemptive problems. 

F3/pmtn/C^^j^ is NP-complete even if no job has more than 2 operations. They have jobs 
with 1-2, 1-3, and 2-3 flows. They transform Partition into this, and the result and proof are the 
same for non-preemptive jobs. F3/pmtn/C,„^jj^ is strongly NP-complete, including jobs with 
operations on all three machines. 

J2/pmtn/C^^ is NP-complete if all but two jobs have only two operations. The two other 
jobs go 1-2-1 and 2-1-2. The result also holds for non-preemptive jobs. J2/pmtn/C,^^j;j is 
strongly NP-complete with one job that visits each of the two machines n times. 

The authors move to some approximation algorithms and bounds. For the total flowtime 
job shop problem, the bound on the ratio of the flowtimes for any busy schedule to the optimal is 
m. And this holds if the busy schedule is SPT. The ratio for makespan is also bounded by m. A 
variation of Johnson's algorithm that considers pairs of machines has an error bound of mil. 



53 

Lagcweg. Lcnslra, and Rinnooy Kan (1978) report on a number of differcnl lower bounds 
and a classification of them as well as showing that a new lower bound for the makespan problem 
is better than the rest. 

They present two dominance criteria and then move to the lower bounds, which relax the 
problem by allowing some machines to have infinite capacity. The unit-capacity machines are 
called bottlenecks and the infinite-capacity one are non-bottlenecks. The authors limit 
consideration to at most two bottleneck machines M^ and My and combine consecutive non- 
bottlenecks into one by summing the processing times for each job. Additionally, a non- 
bottleneck can be eliminated by adding the minimum processing requirement on this machine to 
the lower bound. This leads to nine different schemes (excluding symmetric ones). The authors 
describe each of the nine and analyze the effort required for each. They describe some upper 
bound calculations. 

They test all of the lower bounds on problems with six jobs and three, five, or eight 
machines. The better ones were tested on larger problems with 10 to 50 jobs and 3 to 5 machines. 
The best results were obtained using elimination criteria and the two bottleneck machine bound 
with a non-botileneck between them and the head and tail non-bottleneck machines removed. 

Some researchers have looked at the flexible flowshop problem, where there may exist two 
or more parallel machines at a stage of the flow. Wittrock (1988) attempts to minimize the 
makespan and the queueing time. He creates three subproblems: machine allocation, sequencing, 
and timing. In order to simultaneously minimize makespan and queueing, he develops a heuristic 
procedure to greedily sequence the jobs given an allocation of the jobs to machines. He applies 
the LPT heuristic to do this allocation at each stage. Timing consists of loading the parts into the 
system as late as possible while not delaying any subsequent operation. He also considers buffer 
limits. 

Sriskandarajah and Sethi (1989) consider a number of simple heuristics for the flexible 
flowshop problem. They derive worst-case error bounds for list scheduling and a Johnson-like 
sequence on the two-stage case where the first stage has only one machine. Their best relative 



54 

error bound is 2. They also examine the problem where each of the iwo stages has m machines. 
Their heuristic creates m two-machine flowshops and uses list scheduling and LPT to allocate the 
jobs to the different shops. Each shop is sequenced by Johnson's algorithm. 

Gupta (1988) and Gupta and Tunc (1991) study the special two-stage cases where one of 
the stages has only one machine. Both papers propose heuristics that sequence the jobs (by 
Johnson's or some algorithm rule) and then assign the jobs to the parallel machines. Lower 
bounds on the makespan and the results of empirical testing are also discussed. 

Lcc, Cheng, and Lin (1993) study a three-machine problem where each job consists of two 
tasks that are assembled in a third operation. Each of the two first-stage tasks is processed on a 
different machine and the tasks can be processed in parallel. The assembly task is performed on 
the third machine and cannot begin until both first-stage tasks are finished. They show that the 
problem is NP-complete. The authors provide some restricted versions that are polynomially 
complete. These include cases where one of the tasks dominates the other, where the assembly 
tasks is dominated by both first-stage tasks, and where the assembly tasks dominates the first- 
stage tasks. The authors present a branch-and-bound approach that uses the cases presented to 
trim the search tree. The authors present heuristics (with error bounds) that create new first-stage 
tasks from the job data and scheduling according to Johnson's algorithm to minimize the 
makespan of a two-machine flowshop. The best relative error bound is 1/3. 

This three-machine problem is therefore closely related to problems previously studied, but 
the special structure of the problem (the different flows) leads to interesting twists on these 
results. 

Lee and Herrmann (1993) look at the three-machine look-behind problem with the 
objective of minimizing the makespan. They derive results similar to the ones we derive for the 
three-machine look-ahead case. 



55 



2.4.6 Summary 

The papers covered in this section provide a number of ideas that may be useful in the 
thrcc-machinc problems to be .studied. The three-machine problem docs not fit into the flow shop 
model, and thus work must be done on how to modify the above approaches. Also, the NP- 
complcteness proofs do not apply, and the NfP-completeness of the three-machine problem must 
be proved. The flexible flowshop models and the a.ssembly flowshop model of Lee, Cheng, and 
Lin (1993) may be provide some results on minimizing makespan that can be applied, although 
the problem is fundamentally different for the flowtimc objective. 

2.5 Look-ahead and Look-behind Scheduling 

This research includes in its investigation of the complicated job shop scheduling problem 
the use of more sophisticated dispatching techniques that consider more information in their 
decision-making. This research tries to be precise in its use of the terms look-ahead and look- 
behind. The idea of looking at the other machines in the shop when dispatching is not well- 
researched, although the work-in-next-qucue and number-in-next-queue dispatching rules 
mentioned by Panwalker and Iskandcr (1977) are simple look-ahead rules. 

Look-behind rules consider the jobs that will be arriving soon (called x-dispatch by Morton 
and Ramnath, 1992). Look-ahead rules consider information about the machines downstream in 
the flow. This includes the work-in-next-queue and the number-in-next-queue rules of Panwalkar 
and Iskander (1977), bottleneck starvation avoidance (Glassey and Pctrakian, 1989), bottleneck 
dynamics (described in Morton, 1992), and lot release policies that look-ahead to the bottleneck 
(Wein, 1988; Glassey and Resende, 1988a; and Leachman, Solorzano, and Glassey, 1988). A 
three-machine look-behind scheduling problems similar to problems studied in this dissertation is 
considered in Lee and Herrmann (1993). 



56 

Also, Blacksionc, Phillips, and Hogg (1982) report on a heuristic that is called look-ahead 
but would be classified here as look-behind, and Savell, Perez, and Koh (1989) did develop a 
look-behind system. 

More specifically, look-ahead models consider the states of the machines where the jobs 
will be processed after being processed on the machine being scheduled. Information about the 
workload of other machines may be useful in balancing the flow of product through the shop. 
Look-behind models consider the machines the precede the machine being scheduled in the flow 
and the jobs being processed on these machines. Some of these machines will be processing jobs 
that will next need processing at the machine being scheduled. If the times that these jobs will 
complete is known, these times form release dates to the machine being scheduled, and the 
scheduling decision can explicitly consider these imminent arrivals. 

Other researchers have studied procedures that they called look-ahead scheduling, but the 
problem setting or interpretation is slightly different. 

Vepsalainen and Morton (1987) called their weighted COVERT and apparent tardiness cost 
rules "look-ahead" since they are concerned with the remaining waiting time of a job. They use, 
however, average waiting times without looking at the current queues. 

Koulamas and Smith (1988) are concerned with the scheduling of jobs on machines that are 
attended by a server that must unload a job from a machine and load another job onto the 
machine. Interference results from one machine finishing while the server is busy at another 
machine. This interference degrades the system performance by preventing the machine from 
being maximally utilized. 

The authors study a two-machine system where each machine has a distinct set of job types 
arriving to it. The authors propose a look-ahead rule for scheduling a machine that considers the 
state of the other machine when deciding what job to sequence next. The rule attempts to 
schedule a job whose completion will not interfere with the completion of the job on the other 
machine. 



57 

This work is similar lo the definition of look-ahead in this paper, although its objective (to 
minimize interference) is not related to the completion-time objectives being studied. 

Zeestratcn (1990) is concerned with minimizing makespan in a job shop with routing 
flexibility. Thai is, some operations may be able lo choose from more than one machine for their 
processing. The author defines a look-ahead rule as one that considers the entire state of the 
system and all of the unscheduled operations and creates a partial schedule that specifies a few 
operations for each machine. This schedule is followed until another scheduling decision is 
made. At this point, the procedure is repeated, using the new information about state of the 
system. 

The look-ahead rule is so called because it searches through the states that the system could 
reach in a period that is approximately twice the average cycle time. That is, it looks ahead in 
time without attempting to schedule all of the remaining operations. Thus, it falls somewhere 
between fixed schedules and real-time dispatching. 

This type of scheduling is actually more global in nature, since it considers the entire shop 
when scheduling. It is not looking at specific machines. 

In summary, although scattered look-ahead and look-behind techniques have been 
considered, this research attempts to categorize these ideas, conduct analysis of look-ahead and 
look-behind scheduling problems in order to derive good rules, and integrate the results into a job 
shop scheduling environment. 

2.6 Class Scheduling 

Manufacturing often involves machines that process different product types, and this 
phenomenon can be modelled as a class scheduling problem, a topic mentioned in the 
introduction (Section 1 .4). A number of researchers have studied the class scheduling case of 
sequence-dependent setup times. Examples reported by Monma and Potts (1989) include paint 
production machines that are cleaned between the production of different colors, a computer 



58 

system that must load the appropriate compiler for a type of task, and a limited labor force with 
workers switching between two or more machines. 

Bruno and IDowncy (1978) study class scheduling problems with deadlines. Their problem 
is the single-machine scheduling of classes of tasks with deadlines and a setup time or 
changeover cost between classes. They prove that, with setup times, the question of fmding a 
feasible schedule is NP-complelc. With changeover costs, the problem of finding a minimal cost 
feasible schedule is also NP-complcte. 

Monma and Potts (1989) present complexity results for class scheduling problems without 
deadlines. The assume that the class setups satisfy the triangle property. They show that 
minimizing makespan, maximum lateness, the number of tardy jobs, and the unweighted and 
weighted flowtime is NP-complete, although they discuss a number of optimal properties and 
dynamic programming algorithms that are polynomial in number of jobs but exponential in the 
number of batches. They also show that the corresponding parallel machine problems are NP- 
complete. The authors conclude that the design and analysis of heuristics for these problems is 
important 

Ahn and Hyun (1990) study the problem of minimizing flowtime and present a dynamic 
programming algorithm that is similar to those of Monma and Potts. This algorithm is 
exponential in the number of classes, and the authors develop an iterative improvement heuristic 
that finds near-optimal schedules. 

Sahney (1972) considers the problem of scheduling one worker to operate two machines in 
order to minimize the flowtime of jobs that need processing on one of the two machines. Sahney 
derives a number of optimal properties and uses these to derive an intuitive branch-and-bound 
algorithm for the problem. 

Gupta (1984) also studies the two-class scheduling problem and derives an 0(rt log n) 
algorithm to minimize flowtime. Potts (1991) presents an example that Gupta's algorithm does 
not solve and goes on to describe an O(n^) dynamic program to minimize flowtime and an Oiii^) 
algorithm to minimize weighted flowtime. 



59 



Coffman, Nozari, and Yannakakis (1989) consider a class scheduling problem wilh two 
subassembly part types. A product consists of two parts, one of each type, both made on the 
same machine, and the product cannot be delivered until both parts are finished. Their objective 
is to minimize the flowtime of delivered products, and using properties of an optimal schedules, 
they authors create an O(Vrt) algorithm. The authors describe extensions to multiple copies, 
limits on the number of changeovers, and limits on batch size as solvable cases without details. 

Mason and Anderson (1991) study the one-machine class scheduling problem with the 
objective of minimizing weighted completion times under sequence-independent setups that 
fulfill the triangle inequality. By using properties of an optimal sequence and aggregating jobs 
into composite jobs, the authors develop a brand-and-bound algorithm using their dominance 
criteria and lower bound. 

Dobson, Karmarkar, and Rummel (1987) consider a class scheduling problem with the 
objective of minimizing flowtime under both the item-How and batch-flow delivery schedules. 
The batch (or class) setups are sequence-independent and the processing times are equal for all 
parts (jobs) in one part type (class). They formulate integer programs for both problems, solving 
the item-flow problem and single-product batch-How problems optimally. For the multiple- 
product batch flow, the authors can only provide some heuristics based on their other results. 

Dobson, Karmarkar, and Rummel (1989) consider the above single-item problems on 
uniform parallel machines. They assume that the work is continuously divisible and determine 
the amount of work to allocate to each machine by solving a convex programming problem. The 
authors also apply their results to solve the item-flow problem. 

Woodruff and Spearman (1992) consider an interesting class scheduling problem where the 
objective is to maximize the profit of feasible schedules. That is, jobs must be completed by their 
deadlines. The profit calculation includes the value of jobs that are not required to be processed 
but add some revenue and two different costs: holding and setup. The authors search for good 
solutions with a tabu search. Discussion of this search can be found in Section 2.8.3. 



60 

A more typical problem is studied by Ho (1992), who examines the problem of minimizing 
the number of tardy jobs where the jobs fall into exactly two classes. He develops and efficient 
branch-and-bound algorithm. 

Gupta (1988) studies the class scheduling problem of minimizing the total flowtimc. He 
develops a heuristic that is based upon the standard shortest processing time rule. Empirical 
testing shows that the heuristic produces good results on small problems. 

A more sophisticated class scheduling problem is the minimization of the maximum 
lateness of a set of jobs with non-zero release dates. This problem is considered by Schutten and 
Zijm (1993), who develop a branch-and-bound algorithm and a tabu search over the sequences of 
jobs. They report good results on problems with up to 50 jobs. 

In summary, this body of research does not yet include much work on problems with 
additional criteria, such as deadlines or release dates, or on shop problems. Moreover, this 
research has concentrated on branch-and-bound techniques and optimal algorithms for problems 
with just two classes. Little work has been done on heuristics for problems with an arbitrary 
number of job classes or on the use of smart-and-lucky searches to solve class scheduling 
problems. 

2.7 Some One-machine Problems 

In order to gain insight into new dispatching rules that may be useful in the job shop 
scheduling question, some one-machine problems will be investigated. The three one-machine 
problems reviewed in this section are the problem of minimizing total flowtime with deadline 
constraints, the problem of minimizing the number of tardy jobs subject to matching release 
dates, and the problem of minimizing the total flowtime of jobs with release dates. These 
questions will be the first to be studied as class-scheduling problems. 



61 



2.7.1 Constrained Flowtimc 

The first one machine problem studied in the preliminary work is a class scheduling 
extension of 1 / D . / X C., the constrained flowtime problem first studied by Smith (1956). 

Smith, in this paper, proves the oplimality of ordering the jobs by Shortest Processing Time 
to minimize the total fiowtime problem 1 / / X Cj. He extends this to the problem where the jobs 
all have deadlines that must be met. 

The makespan of the jobs is known, and following the SPT property of minimizing total 
fiowtime, the algorithm tries to schedule the longest job to end at this time. However, the longest 
job's deadline may be less than the makespan, in which case the job is not available to end at this 
time. So. the algorithm searches for the longest job that can end at this time and schedules it. 
The algorithm then moves to the start time of this scheduled job. This time is now the completion 
time of the remaining unscheduled jobs, and the algorithm again searches for the longest 
available job. This algorithm is hereafter referred to as Smith's algorithm. 

The weighted problem is strongly NP-complete (Lenstra, Rinnooy Kan, and Brucker, 
1977), and different elimination criteria and branch-and-bound techniques have appeared. Potts 
and van Wassenhove (1983) study the Lagrangean relaxation of the deadline constraints, leading 
to the discovery of optimal solutions. Work by Posner (1985) and Bagchi and Ahmadi (1987) 
present improved varieties of this bound. Many other problems have been studied; see 
Herrmann, Lee, and Snowdon (1993) for a survey of dual criteria problems. 

2.7.2 Release and Due Dates 

The other one-machine problem in the preliminary results is the look-behind problem 
1 / r.- / S Uj, which is a strongly NP-complete problem in general (Lawler, 1982). The problem 
has been solved optimally if all release dates are zero by the Moore-Hodgson algorithm (Moore, 
1968). The problem has been solved optimally by Kise, Ibaraki, and Mine (1978) if the release 



62 

and due dates match (r. < r^ implies d: ^ d0. They present an 0(/i2) algorithm (Kise's algorithm, 
described below) in this case. 

Kise's algorithm orders the jobs by their release and due dates (a non-ambiguous ordering 
since the dates must match). The algorithm is an extension of Moore-Hodgson algorithm for 
minimizing the number of late jobs. Each job is scheduled after the partial schedule of on-time 
jobs while maintaining release availability. If the new job is tardy, the algorithm searches the on- 
time jobs for the job whose removal leaves the shortest schedule of on-time jobs. The removed 
job is made tardy and will be processed with the other tardy jobs after the on-time jobs. In this 
manner, the algorithm finds the largest subset of the jobs that can be delivered on-time. These 
jobs are scheduled in order of their release and due dates. 

Unlike the Moore-Hodgson algorithm, the subalgorithm that removes a job cannot just 
choose the longest job, since the presence of release dates limits how the removal a single job 
affects the completion times of later tasks. They present an efficient way to determine which job 
should be removed. 

2.7.3 Flowtimc and Release Dates 

A last one-machine problem that may yield some good results when studied as a class 
scheduling problem is closely related to the constrained fiowtime problem. This is the problem 
of minimizing total fiowtime subject to job release dates. Written as 1 / r.- / X C:, this problem is 
a strongly NP-completc question, as shown by Lenstra, Rinnooy Kan, and Brucker (1977). 

Dessouky and Deogun (1981) present a branch- and-bound algorithm with a lower bound 
and dominance properties used to prune the search tree. They list a number of dominance 
properties that hold for a given partial sequence of the jobs. Their lower bound is derived from 
the EFT schedule but starts the selected job at the first release time. They can solve problems 
with up to 50 jobs. They also report that the EFT sequence generally finds good solutions (within 
3% of optimal). 



63 

Bianco and Ricciardelli (1982) consider the weighted version of ihc problem. Let the 
weighted processing time be the processing time divided by the weight of the job. They present 
an improved branch-and-bound algorithm with further dominance properties for nodes with a 
partial schedule. They compute a lower bound by allowing preemption. The hardest 10-job 
problems to solve were those with a larger range of weights and a maximum release date near the 
expected sum of processing times (that is, the average intcrarrival and processing times were 
nearly equal). 

Hariri and Potts (1983) also attack the problem of minimizing weighted flowtime with 
release dates. They use a Lagrangean relaxation of the constraints Cj > r.- + pj to find a lower 
bound. They make use of previous dominance properties and add another that measures the 
effect of interchanging two consecutive jobs. They solve problems with 10 to 50 jobs, and the 
hardest problems (some of which remain unsolved) were those with a range of release dates 
approximately the same as the expected sum of processing times. 

Gazmuri (1985) studies the question probabilistically. He develops two cases. In the 
undersaturated case, where the expected processing time is stricUy less than the expected time 
between release dates, the author develops an algorithm that partitions the jobs into smaller sets 
and schedules each of the sets optimally. The algorithm for the oversaturated case starts with the 
optimal preemptive schedule and patches preempted jobs by shifting the delayed segments to the 
left until the job is whole. For both cases, the heuristic is asymptotically optimal as the number 
of jobs goes to infinity. 

Liu and MacCarthy (1991) use both mixed-integer linear programming and branch-and- 
bound techniques to solve the problem. They present a number of heuristics that are different 
priority rules and report that the heuristics generally find near-optimal solutions (within 1%) with 
little computational effort until the problem sizes exceed 100 jobs. The MILP can solve problems 
with only 10 jobs, the branch-and-bound procedure problems with 25 jobs. 

Finally, Rinaldi and Sassano (1977) also report on a branch-and-bound technique for the 
weighted problem. 



64 



2.8 Smart-and-luckv Searches 

In this section we will discuss a class of searches that have been receiving much attention 
from researchers recently. This class include tabu search, simulated annealing, and genetic 
algorithms. We will use the last of these in the research into different scheduling problems. 

2.8.1 Introduction 

One approach to difficult scheduling problems such as job shop scheduling is local search, 
an iterative procedure that moves from solution to solution until it finds a local optimum. Two 
examples are hillclimbing and steepest descent. The hillclimbing algorithm chooses a nearby 
point at random and moves there if the point improves the value of the objective function. The 
steepest descent procedure examines the entire neighborhood of an incumbent point and selects 
the point (if any exist) that is most improving. 

Heuristic searches (or probabilistic search heuristics) attempt to improve upon the primary 
problem of these simple searches: convergence to local optima. We can use the term smart-and- 
lucky to describe these more complex searches: they are smart enough to escape from most local 
optima; they still must be lucky, however, in order to find the global optimum. Simulated 
annealing, the most popular of the methods described in this work, was developed independently 
by Kirkpatrick, Gelatt, and Vecchi (1983) and Cemy (1985). Glover claims that tabu search, 
which is also widely used, goes back to a paper of his from 1977. Holland developed the ideas of 
genetic algorithms, which have had the least success so far, in his 1975 book. This section 
reviews the basic concepts of these searches and a number of scheduling applications. 

2.8.2 Simulated Annealing 

Simulated annealing (SA) is a variant of the hill climbing algorithm. As mentioned before, 
both Kirkpatrick, Gelatt, and Vecchi (1983) and Cemy (1985) produced the initial papers on the 



65 

simulated annealing algorithm, so called ixicausc the algorithm views opUmizalion as a process 
analogous to physical annealing, the cooling of a system until it reaches a low-energy stale. 

In annealing, as a system cools, configurations occur with weight dependent upon their 
energy and the system's temperature. In 1953 Metropolis et al. developed a statistical simulation 
of an annealing system. This algorithm randomly shifted the system from one configuration to 
another, using the physical laws that governed behavior to guide the procedure. Kirkpatrick, 
Gelatt, and Vecchi (and Cemy) modified his procedure to solve optimization problems. The 
crucial element was the acceptance of a non-improving move with a probability that was a 
function of the difference D in objective function and some cooling constant T. The standard 
formula was e-^'^'. This acceptance of a non-improving move is what differentiates a simulated 
annealing from hillclimbing. 

Kiricpatrick, Gelatt, and Vecchi (1983) list four ingredients for a simulated annealing 
algorithm: a precise description of system (that is, a solution space), the random generation of 
moves, a quantitative objective function, and an annealing schedule. Simulated annealing makes 
a move by picking from a set of possible operations that can be applied to the incumbent solution. 
Usually, the choice is made randomly, although the set may be ordered somehow. At a given 
temperature, the algorithm may stop when some equilibrium or maximum number of moves is 
reached. Then the algorithm reduces the temperature geometrically or linearly. The initialization 
of the algorithm with a starting point may be random or may use a heuristic. 

It can be proved that simulated annealing will converge to a global optimum. Aarts and van 
Laarhoven (1985) use a homogeneous Markov chain that reaches equilibrium at each temperature 
to prove this. They use a general form of acceptance probabilities, of which the standard 
exponential is a special case. However, reaching equilibrium at a temperature may require an 
exponential number of moves. They avoid the exponential chain length by defining quasicquilib- 
rium conditions and conclude with a polynomial algorithm. 

Kirkpatrick, Gelatt, and Vecchi (1983) studies a number of chip design problems and the 
traveling salesman problem. In his example, he places the cities in nine clumps and examines the 



66 

effect of temperature on the solutions found. At high temperature, the algorithm minimizes the 
number of long jumps; at a medium temperature, the coarse structure changes but stays minimal; 
and at low temperatures, the procedure improves the solutions at the small scale. Cemy also 
studies the traveling salesman problem. 

Van Laarhoven, Aarts, and Lenstra (1988) study the job shop scheduling problem by 
making use of the disjunctive graph, where the makespan of a solution is the length of the longest 
path. The disjunctive graph has an arc for each precedence among operations for a job and an 
(imdirected) edge connecting those operations on different jobs that use the same machine. A 
schedule can be found by directing the edges to form an acyclic graph. Given a feasible solution, 
any swap of a critical disjunctive edge will form another feasible solution. This becomes their 
move, and they claim that their simulated annealing is as good as shifting bottleneck and simpler. 

A different type of simulated annealing is included in the Matsuo, Suh, and Sullivan papers 
(1988, 1989) on controlled search simulated annealing (CSSA). In this approach, the algorithm 
uses a good initialization, independent acceptance probabilities, a low initial acceptance 
probability, and a sequential search of smaller neighborhoods. The motivation for acceptance 
probabilities independent of the change in objective is its use in empirical testing of different 
cooling schedules. Their first paper addresses the single-machine weighted tardiness problem. 
The CSSA uses a fixed number of iterations and its move swaps an adjacent pair. The authors 
compare different cooling schedules and claim that the CSSA is a better procedure than standard 
SA. 

In the paper on job shop scheduling, the authors use the shifting bottleneck algorithm for 
iniualization. The CSSA identifies the critical path and then switches two operations on the 
critical path with !ook-back and look-ahead options that swap other operations to improve 
makespan. If a non-improving move is not accepted, they perform a local search to find a 
possible improving solution. They claim better makespans with the same effort as shifting 
bottleneck. 



67 

For now shops. Ogbu and Smith (1990) present a simulated annealing that they call 
"probabilistic-exhaustive" because it uses independent acceptance probabilities with a random 
search of the entire neighborhood, moving to the last point accepted. They minimize makespan, 
and their moves are pair swaps and insertions. They get better processing lime than the standard 
SA and belter results than repetitive local searches. Vakharia and Chang (1990) look at a flow 
shop with jobs in families and family setup limes. They also use independent acceptance 
probabilities. Their moves swap jobs within a family or swap families. They use different 
initializations and compare their search to other heuristics. 

2.8.3 Tabu Search 

Tabu search (TS) is a variant of steepest descent. Glover (1989, 1990) presents a good 
discussion of tabu searches. Given an incumbent solution, a TS searches the neighborhood of this 
solution, finding the best allowable move. A TS allows bad move away from local optima, 
prohibits moves which lead backwards through short-term memory (the tabu list) and has an 
aspiration level to override the tabu list under certain conditions (usually best found). A tabu 
search works because the tabu list forces the search to explore new areas of the solution space. 
The short-term aspect of the memory and the aspiration level allow the search to get to a global 
optimum however. 

Table 2.1. Outline of a Simple Tabu Search. 

1. Pick initial x. let x'= x. T, the tabu list, is empty. 

2. Let S(x) be the neighborhood of x. Take s' as best member of S(x) \ T. 

3. Letx = 5Y^)- Uc(x)<c(x'),x'=x. 

4. Check slopping criteria. Update T. Go to 2. 

The best member is usually that which gives the best value of the objective function c(x). 
The stopping criteria may be a total number of moves or a number of moves since the last best. 



68 

Updating the tabu list T is the crucial pari of a tabu search. Usually this means adding moves that 
would reverse the step just taken and removing old tabu moves. 

Laguna, Barnes, and Glover (1989) investigate a tabu search for a single-machine 
scheduling problem with linear delay penalties and setup cost dependencies. They use a heuristic 
initialization and iascriion and swap moves. They claim results much belter than a branch-and- 
bound. 

Barnes and Chambers (1991) investigate the use of a tabu search to solve the job shop 
scheduling problem of minimizing makespan. The authors describe an improved approach that 
uses an actual makespan change when evaluating new schedules instead of a projected change. 

The authors compare their job shop scheduling approach to Applegate and Cook's shuffle 
algorithm and the Shifting Bottleneck algorithm of Adams, Balas, and Zawack. They observe 
that their tabu search achieves better makespans in most cases over a range of problem sizes. 

Barnes and Laguna (1992) examine the multiple-machine weighted flowtime problem with 
a similar tabu search. This problem reduces to a partition problem, and their search does prevent 
non-improving swaps: they claim that swaps are too small to move through the solution space 
effectively. Again, they claim results that beat a branch and boimd approach. 

Widmer and Hertz (1989) take up the flow shop and use permutation schedules. They 
define a distance between two jobs as the approximate increase in makespan and perform a TS 
upon the open TSP. A move in the solution space is the swap of a pair. They get slightly better 
makespans than six heuristics at the cost of terrible processing times. 

An ambitious paper by Malek et al. (1989) examines parallel and serial tabu searches and 
simulated annealing on the traveling salesman problem. For each search, a move was a 2-opt 
(subsequence reversal). The parallel runs communicate periodically, sharing good solutions. 
Parallel SA performed a quick annealing on each processor and achieved superlinear speedup. 
According to the authors, parallel TS performed best, but the simulated annealing was more 
robust (less sensitive to parameter changes). 



69 

In an inlcresling article, Woodoilf and Spearman (1992) study the problem of maximizing 
the profit gained from scheduling a set of jobs on one machine. The authors claim that the one- 
machine problem has significance for shops with a bottleneck operation, where the sequencing of 
the bottleneck determines how the shop performs. These jobs include jobs that arc required in 
some sense, say to meet specific orders, and jobs that are filler, in that they arc not required now, 
but some profit is realized by producing them. The jobs have due dates, and the schedule should 
be feasible with respect to these. The costs include the holding costs of finishing jobs too early 
and setup costs incurred when the machine must be switched from processing jobs of one family 
to those of another. Thus, this problem is a class scheduling problem, and it is an NP-complete 
question just to ask if there exists a feasible schedule. 

The authors show that if the holding costs are zero, it is optimal to order the jobs in each 
family by EDD. If the holding costs are positive, this EDD within a family is still used as a 
heuristic in order to simplify the problem of finding a good schedule. 

The authors use a tabu search to search the solution space for good sequences. The moves 
of the tabu search are insertions of jobs while maintaining EDD within a family. Complications 
are added by the presence of filler jobs that are not required to be in the schedule. The authors 
use a diversification parameter for two reasons: first, the parameter diversifies the search by being 
included in a modified cost function that provides a penalty for infeasible solutions while 
allowing the search to use these as passes into new areas. Secondly, this parameter allows the 
search to optimize its performance. This is done by initially performing tabu searches over a 
number of different values of the diversification parameter and then continuing the search with 
the best values. 

Empirical testing of the algorithm on data motivated by an actual manufacturing 
environment showed that the search is a useful method of finding good solutions for this problem. 

Glover, Taillard, and de Werra (1991) describe the main aspects of tabu search and discuss 
various refinements that may lead to a new generation of search. These refinements occur on the 
tactical, technical, and computational levels. Tactical improvements are concerned with 



70 

improving the neighborhood structure and defined moves. This may include the use of learning 
approaches, shifting penally tactics, and strategic oscillation. 

Technical improvements focus on the issues of neighborhood size, tabu list structures, and 
aspiration conditions. Computational improvements include reducing the time required to 
compute the objective function over the neighborhood and the parallclization of the search. 

Laguna and Glover (1991) use target analysis to promote diversification in a tabu search 
used to find good solutions to a single machine problem with linear delay and setup costs. The 
tabu search uses both swap and insert moves. 

The goal of using target analysis is to teach the tabu search to use good rules. The authors 
describe five phases of target analysis. The first phase is to take some specific problems and find 
very good solutions to those problems. In the second phase, with these very good solutions as 
targets, the problems are solved again and information is gathered on how well the current 
decision rules lead to the target. In the third phase, this information is integrated into a master 
decision rule. The fourth phase finds good parameter values for this master. Finally, the master 
is applied to the original problems to verify its merit. 

Reeves (1993) examines how the definition of the neighborhood in a tabu search affects the 
balance between exploration and exploitation (or diversification and intensification). Given the 
proper balance, he finds that tabu search is a more efficient procedure than simulated annealing 
for the permutation fiowshop problem. 

2.8.4 Genetic Algorithms 

A genetic algorithm is a smart-and-lucky search that manipulates a population of points in 
the effort to find the optimal solution. Each individual in the population is a string of genes, 
where each gene describes some feature of the solution. Genetic algorithms mimic the processes 
of natural evolution, including reproduction and mutation. The most powerful operator of a 
genetic algorithm is the crossover operator: the recombination of the genes of two parents to 



71 

create two offspring. This crossover allows the offspring to acquire the good characteristics of 
different points in the search space. 

Most genetic algorithms perform the following steps, stopping when a Fixed number of 
offspring has been created: 

Step 0: Form an initial population. 

Step 1; Evaluate the individuals in the population. 

Step 2: Select individuals to become parents with probability based on their fitness. 

Step 3: For each pair of parents, perform a crossover to form two offspring. Mutate each 

offspring with some small probability. 

Step 4: Place the offspring into the population. Return to Step 1. 

Holland (1975), Davis (1987, 1991), and Goldberg (1989) pix)vide good descriptions of 
genetic algorithms. Holland's 1975 book introduced the genetic algorithm (GA), a procedure that 
mimics the adaptation that nature uses to find an optimal state. In genetic algorithms, solutions 
are represented as strings (chromosomes) of alleles, and the search performs operations on the 
population of solutions. Liepins and Hilliard (1989) identify these operations as 1) the evaluation 
of individual fitness, 2) the formation of a gene pool, and 3) the recombination and mutation of 
genes to form a new population. After a period of time, good strings dominate the population, 
providing an optimal (or near-optimal) solution. 

The solution strings may be a sequence of binary bits or a permutation. The fitness of a 
solution is its objective function evaluation or ranking. In forming the gene pool, the algorithm 
takes, through some random process, those solutions that are more fit. The recombination is 
some type of crossover, one-point or multipoint. It is this powerful crossover mechanism that 
makes GAs special. The mutation operation, so important in SA, is a secondary operation here 
and serves only to maintain diversity. 

Why do GAs work? A schemata is a pattern possessed by individuals in population. The 
fitness of a schema is the average fitness of those solutions that possess it. Genetic algorithms 
work because good (short) schema survive exponentially, and the population of solutions 
provides implicit parallelism. 



72 

When do ihcy fail? A gcnclic algorilhm may fail if ihc strings arc inappropriate 
representations of solutions, the strings exclude important problem information (such as 
constraints), or the algorithm converges to a local optimum. The first issue is the largest for 
scheduling problems: representation is difficult for combinatorial problems because standard 
crossovers may lead to infeasibility. 

In an effort to address this problem for the traveling salesman problem, where a solution is 
a permutation of cities, Oliver, Smith, and Holland (1987) propose a number of unusual 
crossovers. The first is the Order crossover, which substitutes a subsequence from the first parent 
into the second and then visits the remaining cities in the same relative order as before. The 
crossover maintains short schema. Their PMX crossover compares subsequences from both 
parents and then performs a swapping in the second parent. The Cycle crossover matches cities 
to form independent tours. Then, for each tour, the crossover picks a parent to supply the cities. 
After comparing the tree crossovers, they claim that the Order is better on TSP by preserving the 
short schema, which are important for this problem. 

The job shop scheduling problem is much more complicated problem. Davis (1985) solves 
a simple job shop problem with a GA. Another method is an idea by Storer, Wu, and Vaccari 
(1990, 1992): searching problem spaces and heuristic spaces, which are discussed in detail in 
Section 2.9. 

Storer, Wu, and Vaccari (1990) note that a solution is simply the application of a heuristic 
to a problem. Changing the problem or the heuristic generates a new schedule and thus a new 
solution. A problem is a vector of processing times, and a heuristic is a vector of dispatching 
rules that can be used to create a non-delay or active schedule. These data structures create 
simple strings and perform well under standard crossover as well as simulated annealing and tabu 
search. The authors perform all three searches on both types of spaces. For the tabu search, the 
tabu list was a set of tabu makespans. Otherwise, the SA and TS were standard. The authors also 
tried shifting bottleneck, probabilistic dispatching, and random search over their new spaces. 
They test their heuristics on a number of problems ranging in size from 10 to 50 jobs. The 



73 

problems were also classified as easy or hard. The easy problems had completely random 
routings, and the hard problems tended have greater competition for the machine resources at any 
point in time. The genetic algorithms on problem space generally found higher-quality solutions. 

Fox and McMahon (1990) are interested in the job shop scheduling problem but study the 
traveling salesman problem in order to gain insight into using genetic algorithms for sequencing 
problems. 

The authors consider the binary precedence matrix M where m,.- = 1 if city / precedes cityy. 
m^i = for all cities /. This matrix incorporates micro- and macro-information. The authors 
consider row and column swap operators that exchange the successors or predecessors of two 
cities. 

The first new operator is the intersection operator, in which an offspring inherits the 
precedences that exist in both parents. That is c^ = a^ and ft^-,' o^^r all ij. This will yield a 
matrix that is consistent (no cycles) but incomplete; in other words, a partial ordering. The 
matrix is completed through an analysis of the row and column sums. 

The second new operator is the union operator. First, the cities are partitioned into two 
sets. This forms for each parent two precedence submatrices corresponding to the two subsets. 
The operator then takes one submatrix from one parent and the submatrix for the other subset 
from the other parent. Again, this leads to a partial ordering that must be completed. The authors 
claim that this operator contains little micro-information from the parents, unless a Markov 
process is used to partition the cities. 

The authors compare different operators for the TSP, including a random operator used as a 
benchmark. If the proposed operators are no better than this, they should not be pursued. Their 
city topologies included random distances, clustering, concentric circles, and a 30-city problem 
from Oliver, Smith, and Holland (1987). The population size was 900 with no mutation. The 
also tried searches with and without elitism (the keeping of the best solution). 

Among non-elite searches, the two new operators were great, even when considering 
processing time. Their advantage disappeared when the searches got to use elitism. 



74 

The authors claim thai this work will be useful in scheduling problems, although execution 
time remains a big problem. 

Biegcl and Davem (1990) begin with a general discussion of genetic algorithms. They then 
describe how a genetic algorithm could play a part in the scheduling of a shop. They discuss 
what data are essential and how the GA could form a schedule for a known group of jobs that 
follow the same route. 

The authors move to the single-machine problem and consider how the analogous GA 
would work. Moving to the 2- and //i-machine flow shop, the authors present a simple discussion 
of what the GA would do. 

For the dynamic problem, the authors consider performing a rescheduling in real-time to 
deal with arrivals and use a FIFO dispatching rules on all other machines. The authors then list a 
number of areas for future research. 

Cleveland and Smith (1989) use a genetic algorithm to schedule the release of jobs into a 
manufacturing cell to minimize weighted tardiness. They consider both the sequencing problem 
and the problem of determining the release times. 

Nakano and Yamada (1991) introduce a binary representation to solve the job shop 
scheduling problem. This representation denotes the relative ordering of each pair of jobs on 
each machine. If an illegal chromosome is formed by a genetic operator, a nearby legal one 
replaces it. The authors report that their algorithm finds good solutions on some standard 
problems. 

Whitley, Starkweather, and Shancr (1991) develop an edge recombination operator for the 
traveling salesman problem and report that a genetic algorithm with this operator is able to find 
very good schedules. 

Starkweather et al. (1991) compare six sequencing operators for the traveling salesman 
problem. They discover that the different operators stress different types of information; since 
the TSP depends upon adjacency, the edge recombination operator is the best. 



75 

In Syswercla(1991), the author discusses the scheduling of a lighter simulation lab. 
Finding a feasible scheduling is made difficult by a number of constraints. A genetic algorithm 
that manipulates sequences of jobs and employs a schedule builder to translate the sequence into 
a legal schedule was able to find good schedules. 

2.8.5 Summary 

Simulated annealing and tabu search easily search complex spaces by lending themselves 
to usually simple types of moves, generally find good solutions fast, and are smart variations of 
standard searches such as hillclimbing and steepest descent. Genetic algorithms work in a 
different manner. They work well due to the survival of good schema and their implicit 
parallelism. They have been harder to implement on scheduling problems, however. 

This research in this dissertation builds upon this work into smart-and-lucky searches by 
looking into some alternative search spaces. 

2.9 Problem and Heuristic Space 

This dissertation includes the development of global job shop scheduling models, whose 
solution will yield a schedule that can be followed for time period like an eight-hour shift. As 
mentioned in the last section, one way to find good schedules is to use a search. One recently- 
profX)sed idea is to search problem and heuristic spaces. This section will define mathematically 
how these spaces can be used and will review the ideas of a few papers in this area. 

Define a problem p as a set of data about which an optimization question can be asked. A 
solution 5 is a point that is consistent with the problem structure, where the solution has some 
performance z measured by applying the objective function/to the solution with the problem 
data, z =f(p,s). If the problem is fixed, there is a performance function C„ over the solution 
space such that z = Cp(s) =f(p,s). Solving a problem translates as finding the solution that gives 
the minimum function value. 



76 

Traditionally, problem-solving searches have occurred in the solution space. In the solution 
space live points (for standard optimization) or sequences (for combinatorial optimization). 
Heuristics arc also applied to problems. A heuristic h, applied to a problem p, yields a solution s, 
s = G(hjj) or .V = h(p). Thus, for a given problem p, there exists a performance function Dp(h) 
over the heuristic space such that z = Dp(h) = Cp(h(p)). This implies that a search over different 
heuristics could fmd a solution that gives the optimal objective function value. 

Moreover, a solution can be generated in ways besides applying a heuristic to the original 
problem. Applying a heuristic /z to a problem y in another space can generate a solution s = h(y), 
which can be evaluated using the objective function. Thus, given a problem p and the heuristic h, 
there exists a performance function £„ ^fy) over the other problem space, where z = Ep ^(y) = 
Cp(h(y)). And as before, a search over this new problem space provides a way to solve the 
problem. 

The idea of searching heuristic and problems spaces was investigated by Storer, Wu, and 
Vaccari (1990, 1992). In these papers, the authors are investigating the general job shop 
scheduling problem. They define a heuristic space composed of vectors of dispatching rules. 
The heuristic uses each rule in turn for a fixed number of dispatching decisions. For example, if 
the problem is a ten-job by ten-machine problem, the vector might have five elements, where the 
dispatching rule in the first element is used for the first window of twenty decisions, the next rule 
for the next window, and so on, until all one hundred operations have been processed. 

For a problem space, they use a space of vectors of processing Umes, where each position 
corresponds to a different operation. At each scheduling decision in the formation of the 
schedule, the dispatching rule selects a job by considering these alternative processing times. The 
operation of that job is scheduled using the actual job data in order to calculate the finish time of 
the operation, thus ensuring that the schedule produced will be feasible. Thus, a vector of 
processing times yields a sequence of operations for each machine. 



77 

The authors include a number of concepts related to searching these new spaces, including 
the definitions of neighborhoods, the use of these spaces in genetic algorithms, the fact that the 
spaces contain optimal solutions, and details of local search implementations. 

The application to genetic algorithms merits special comment. Traditional genetic 
algorithms have difficulty with scheduling problems since the components of the strings (the jobs 
in the sequence) are not independent of each other. The problem space and heuristic space 
described above, however, consist of vectors that have independent elements. That is, the 
dispatching rule (or processing time) in the first element does not affect what values the other 
elements can have. Thus, a crossover operation that breaks two strings (vectors) and joins the 
separate pieces yields offspring that are valid points in the search space. 

The authors extend this work in Wu, Storer, and Chang (1993) to the one-machine 
rescheduling problem. They use heuristics that adjust "artificial tails" to find schedules that are 
efficient and deviate little from the original schedule. 

Bean (1992) uses the idea of random keys to provide an alternative search space for a 
number of problems: multiple-machine scheduling, resource allocation, and quadratic 
assignment: the keys are used to sequence the jobs (or other variables). Then some simple rule is 
used to generate a solution from this sequence. Good empirical results are reported. 

Our research extends these ideas to one-machine class scheduling problems and 
investigates a similar heuristic space for the job shop scheduling problem. 

2.10 NP-Complctcncss 

Job shop scheduling problems are usually quite difficult to solve, and they are among the 
hardest optimization problems known. Combinatorial problems, as well as other types of 
problems, can be classified by their complexity, or how difficult they are to solve. The hardest 
problems are called NP-complete. The primary guide to the theory and use of NP-completeness 
is the book by Garcy and Johnson (1979). 



78 

Most ot the problems studied in operations research have been classiTicd by their 
complexity, and as researchers study new problems, their complexity is idcntiried also. There are 
three primary classifications: polynomial, NP-complelc, and strongly NP-complete. Problems in 
the first set can be solved with algorithms that have a running time proportional to some 
polynomial function of the problem size. Algorithms to solve problems in the second set require 
effort that is a polynomial function of the problem size and the problem data. Such an algorithm 
is called a pseudo-polynomial algorithm. Algorithms to solve problems that are strongly NP- 
complete require an exponential amount of effort. 

The complexity of a problem can be determined by identifying the problem as a more 
difficult case of a hard problem, by developing a polynomial algorithm to solve the problem, or 
by transforming a previously classified problem into the new problem. By being able to 
determine the complexity of a problem, researchers are able to know what types of approaches 
may be possible in finding optimal solutions to the problem. A problem that is known to be NP- 
complete will not be solved optimally by any polynomial-time algorithm. Pseudo-polynomial 
dynamic programs will not solve strongly NP-complete problems. This does leave the 
possibility, however, that certain special cases may be more easily solved, that algorithms that 
search for an optimal solution may have good average performance (e.g. the simplex method of 
solving linear programs), and that polynomial-time heuristic algorithms may be able to find 
generally high-quality solutions. 

This research is concerned with a number of different scheduling problems, which will 
classified by their complexity as necessary. We will directly prove NP-completeness for one of 
the problems that we study. Each of the other problems is a more difficult case of a previously 
considered NP-complete problem. 

2.11 Chapter Summary 

This chapter has attempted to cover a broad spectrum of topics and literature. Obviously, 
much research has been done in the fields of job and fiow shop scheduling and the field of 



79 

managing semiconductor manufacturing. However, no system to optimize the scheduling of such 
a process has emerged, despite the use of many different and sophisticated procedures. 

Still, new tools are needed that may have good performance when applied to specific 
settings. There do exist new ideas, such as class scheduling, look-ahead and look-behind 
approaches, smart-and-lucky searches, and problem and heuristic spaces. The literature in these 
areas reports on some initial research. 

However, the full capabilities of the these methods, especially when joined to solve a 
scheduling problem, have not been fully explored. 



I 



I 



CHAPTER 3 
ONE-MACHINE CLASS SCHEDULING PROBLEMS 



In Chapters 3, 4, and 5. we discuss the results of our research into a number of different 
scheduling problems and the general job shop scheduling problem. The primary motivation is to 
examine subproblems of the job shop scheduling problems in order to gain insight into the larger 
problem. The subproblems that we will examine are interesting scheduling problems that have 
not been previously considered. 

We will start with the one-machine class scheduling problems. Our approach in this 
chapter is to develop analytical results, to test extended heuristics, and to show that a problem 
space genetic algorithm can be a good procedure for a variety of scheduling problems. 

3.1 Introduction 

The three one-machine problems studied in this work are class scheduling problems that 
model the complicating factor of machine setups in the manufacturing process. Most problems 
with sequence-dependent setup times are NP-complcte. Class scheduling problems have a 
special structure that makes them good candidates for further research: the jobs to be scheduled 
form a number of disjoint job classes and setups occur whenever the machine processes 
consecutive jobs from different classes. And although we will study a number of different 
problems, we will sec that a problem space genetic algorithm will be a useful procedure for all of 
them. 

The one-machine class scheduling problems under investigation are as follows: 

1. Constrained Flowtime with Setups (CFTS) 

2. Class Scheduling with Release and Due Dates (CSRDD) 

3. Flowtime with Setups and Release Dates (FTSRD) 

80 



81 

The first problem studied is the class scheduling extension of the one-machine problem of 
minimizing the total flowtime of a set of jobs that have deadlines. The research includes an 
optimalily property for the jobs in the same class, a good heuristic, and the development of a 
problem space genetic algorithm that can find better solutions. 

The second problem is the class scheduling problem where each job has a release dale and 
a due date. The objective is to minimize the number of tardy jobs. We investigate a number of 
heuristics and the use of a problem space genetic algorithm. We also look at a secondary criteria, 
minimizing the total tardiness. 

The objective in the third problem is to minimize the total Howtime where each job has a 
release date. Wc consider a number of approaches to finding good solutions, including a problem 
space genetic algorithm, and present a special case that can be solved with a pseudo-polynomial 
dynamic programming algorithm. 

This chapter considers the research on each of these problems in turn. Research relevant to 
these problems is also discussed in Chapter 2. See especially Sections 2.6 and 2.7. 

3.2 Constrained Flowtime with Setups 

We will first consider the one-machine class scheduling problem of minimizing the total 
flowtime subject to the constraint that each job must finish before its deadline. A new heuristic is 
proposed for the problem. We investigate the use of a genetic algorithm to improve solution 
quality by adjusting the inputs of the heuristic. We present experimental results that show that 
the use of such a search can be a successful technique. 

3.2.1 Introduction 

This research is motivated by the scheduling of semiconductor test operations. Assembled 
semiconductor devices must undergo electrical testing on machines that can test a number of 
different types of semiconductors. If a machine is scheduled to test a lot consisUng of devices 
that are different from the devices tested in the previous lot, various setup tasks are required. 



82 

These tasks may include changing a handler and load board thai can process only certain types of 
semiconductor packages or loading a new test program for the new part. However, if the new lot 
consists of circuits that are the same as the previous type, none of this setup is required. This type 
of change is a sequence-dependent setup that can be modelled by class scheduling. 

Since post-assembly testing is the last stage in semiconductor manufacturing, meeting a 
job's due date is a very important objective for the manager of a test facility. A secondary 
criterion is the minimization of total flowtime (the sum of the job completion times), which 
reflects the manager's desire to increase throughput and decrease inventory holding costs. 

This is a dual criteria problem, in which the primary criterion is used as a constraint and the 
secondary criterion is optimized under this restriction. The problem of minimizing the total 
flowtime subject to deadlines is an old problem. Smith (1956) provides an optimal solution 
technique that repeatedly schedules the longest eligible job last. The class scheduling version of 
the problem, however, is more difficult. 

For our problem, finding a feasible schedule is an NP-complete problem. (A schedule is 
feasible if every job finishes before or at its deadline.) Thus, there exist no exact algorithms to 
minimize in polynomial time the total flowtime subject to the deadline constraints. (For a 
discussion of the theory of NP-completeness, see Section 2. 10 and Garey and Johnson, 1979.) 
Thus, we are motivated to try different heuristics. In this work we develop a multiple-pass 
heuristic that finds good solutions quickly. The first contribution of our investigafion of this 
problem is the extension of Smith's algorithm into a heuristic which considers the setup times 
while sequencing the jobs by their deadlines and processing times. 

We are also interested in using a genetic algorithm to improve the quality of our solutions. 
A genetic algorithm is a heuristic search that has been used to find good solufions to a number of 
different optimization problems, but genetic algorithms searching for good schedules must 
overcome the difficulty of manipulating the sequences of jobs. We investigate the use of a 
genetic algorithm to search a new type of space, the problem space. This type of approach was 
introduced in Slorer, Wu, and Vaccari (1992), who consider alternative search spaces for the 



83 

general job shop scheduling problem. In this worii, wc extend the idea to the problem of one- 
machine class scheduling. 

Our search attempts to adjust the deadlines of the given problem so that our heuristic will 
find even better solutions. The space of adjusted deadlines that we search forms n problem space 
(we will return to this pwinl in Section 3.2.5). The second contribution of this work is our use of 
this method to improve the scheduling of a single-machine problem. 

If we use the principles of Davis (1991), then we can classify our genetic algorithm as a 
type of hybrid genetic algorithm. However, the only unusual characteristic of our algorithm is the 
decoding (the bit string does not describe a point in the solution space; instead it must be mapped 
to a solution via the heuristic). Moreover, the range of hybrid genetic algorithms is so large (for 
instance, Goldberg, 1989, describes hybrids differently) that our use of the term problem space 
genetic algorithm is a more precise description of the search. Finally, this problem space exists 
independently of the genetic algorithm, and the use of this new search space is not limited to our 
search. Other searches (including steepest descent, simulated annealing, and tabu search) could 
be used to explore the space. Therefore, we will continue to refer to our search space as a 
problem space and to our search as a problem space genetic algorithm. 

The next subsection summarizes some of the relevant literature on class scheduling 
problems and the dual criteria objective under consideration. In Section 3.2.3, we discuss our 
notation, an example instance of the problem, and a number of basic results. We discuss in 
Section 3.2.4 the heuristic developed for the problem. Our genetic algorithm will employ this 
heuristic. In Section 3.2.5, we present a problem space, introduce genetic algorithms, and 
discuss the details of the genetic algorithm we developed to search the problem space. Section 
3.2.6 describes the generation of the sample problems, the computational experiments, and the 
results. Finally, in Section 3.2.7, we present our conclusions. 



I 



84 



3.2.2 Literature Review 

In this section we will briefly mention some of the relevant research on class scheduling 
and on the dual criteria problem of minimizing total flowtime subject to job deadlines. This owrk 
and the literature on genetic algorithms are discussed in more detail in Chapter 2. 

One of the first papers on problems with class scheduling characteristics is Sahney (1972), 
who considers the problem of scheduling one worker to operate two machines in order to 
minimize the flowtime of jobs that need processing on one of the two machines. Sahney derives 
a number of optimal properties and uses these to derive an branch-and-bound algorithm for the 
problem. Gupta (1984) defines the class scheduling problem, and Potts (1991), Coffman, Nozari, 
and Yannakakis (1989), and Ho (1992) also study two-class scheduling problems. 

Bruno and Downey (1978) prove that, for more general class scheduling problems, the 
question of finding a schedule with no tardy jobs is NP-complete. Monma and Potts (1989) prove 
that many class scheduling problems are NP-compleie, including minimizing makespan, 
maximum lateness, the number of tardy jobs, total flowtime, and weighted flowtime. 

Dobson, Karmarkar, and Rummel (1987, 1989), Gupta (1988), Ahn and Hyun (1990), and 
Mason and Anderson (1991) all study the class scheduling problem under different objective 
functions. We will modify the procedure of Ahn and Hyun in order to use it as a comparative 
heuristic. The only other dual criteria problem in this area is studied by Woodruff and Spearman 
(1992); they consider a class scheduling problem with profit maximization and deadlines. 

In the dual criteria literature, the problem of minimizing total flowtime subject to job 
deadlines (a deadline is a constraint on the completion time) is among the oldest questions, being 
first studied by Smith (1956). The problem of minimizing the weighted flowtime subject to job 
deadlines is a strongly NP-complete problem (Lenstra, Rinnooy Kan, and Brucker, 1977), and a 
number of researchers have examined branch-and-bound techniques. 



85 

3.2.3 Notation and an Opiimal Proocnv 

In this section we introduce our problem and notation, give an example instance of the class 
scheduling paiblem under consideration, and present some basic results. 

Our class scheduling problem is the minimization of the total flowtime of a set of jobs 

where the jobs have deadlines on their completion. The problem can be formulated with the 

following notation: 

Jj }ohjJ=l,. . . ,n 

Pj processing time of /.- 

Dj deadline of 7. 

G,- job class i,i= I, . . . ,m 

rtj- number of jobs in Gj 

Sq^ time of initial setup if first job is in G,- 

Sf^ time of setup between jobs in G^ and G,- 

Cj completion lime of 7,- 

5J C; total flowtime. 

The problem is to find a sequence that minimizes the total flowtime (Z Cj) subject to the 
deadline constraints (C; < D . for all Jj). We name this problem the Constrained Flowtime with 
Setups problem (CFTS). Since job preemption or inserted idle time leads to a non-optimal 
solution, we will assume that schedules being considered have neither. Any schedule that is a 
solution for CFTS will have a number of batches or runs that are sets of jobs from one class 
processed consecutively. Before each batch will be a class setup. The problem involves 
determining the composition and order of batches from different classes. 

CFTS is an extension of a one-machine problem studied by Smith (1956). In his problem, 
which we name the Constrained Flowtime problem (CFT), there exist no sequence-dependent 
setup umes. 

An instance that we will use to illustrate our work is described in Example 3. 1 . 
Example 3.1. The data in Table 3.1 form an instance of a class scheduling problem with five 
jobs in two job classes. The first three jobs form one class, with the remaining two jobs in the 



86 

second class. Recall thai no setup is required between jobs in the same class. However, a class 
setup is necessary between jobs of different classes. 

Table 3.1. Job and Class Data for Example 3.1. 



j 


12 3 4 5 


Pj 


12 2 3 2 


Dj 


3 16 14 10 18 


Gi = {1.2,3} 


n, = 3 


Soi - ^21 - 2 


G2={4,5) 


n2 = 2 


So2 = Si2= 1 



CFTS is an NP-complete problem since finding a feasible schedule is NP-complete (Bruno 
and Downey, 1978). Hence, it is unlikely that any polynomial algorithm to solve the problem 
exists. We will study the use of heuristics to find good solutions. 

We now describe Smith's rule for CFT and an optimal properly for CFTS. Our new 
heuristic extends Smith's rule by taking advantage of the optimal property, which we call Smith's 
property. 

In this and later sections, we will refer to each job that can complete at a given time without 
violating the job's deadline as being eligible. In this problem, we are concerned with deadlines 
that are constraints on the completion times, and we will create schedules backwards, starting 
with the last position in the sequence. Thus, we say that a job J: is eligible at a time r if f < D .-. 
The job can feasibly complete at this time without violating the deadline constraint. 

Smith's property for CFT states that if a job is assigned the last position of an optimal 
schedule, then it must be the longest eligible job. Smith's rule is derived from this property. 
Algorithm 3.1 (Smith's rule for CFT). Let f = p, + . . . + p„. Among the jobs that are eligible 
at time t, that is, t < D.-, choose the job J: with the longest processing time p.. Schedule Jj to 
complete at r, and solve the remaining problem in a similar manner. 



87 



The following property extends Smith's mle to each class in CFTS. This property will then 
be extended to consider all classes in order to generate approximate solutions to CFTS. 
Lemma 3.1 (Smith's property for CFTS). For each class in an optimal schedule for CFTS. the 
only job that could be scheduled to complete at a time t is the longest eligible one. 
Proof. It suffices to show that if two jobs 7, and J: in the same class are both eligible at time / 
and J I is longer than J: (p,- > p.), then scheduling 7. to complete at time / leads to a non-optimal 
solution. Suppose we do. Then C: = t, and 7,- precedes J: in the schedule formed. Create a new 
schedule by interchanging the two jobs. Since J: is moved to the left, it is still feasible, and the 
new completion time is less than Cj, the old completion time of 7, (p,- >p/). The completion 
times of any jobs between 7.- and 7,- are decreased. Meanwhile, 7/ completes when Jj did, but this 
is feasible since t < D,-. We have therefore created a feasible schedule with less total flowtime, 
and the original schedule cannot be optimal. QED. 

3.2.4 The Heuristic 

Quick methods of finding good solutions are sometimes effective ways to attack difficult 
problems. In this section we describe a multiple-pass heuristic that extends the idea of Smith's 
rule. We illustrate how this heuristic works using Example 3.1. 

Our heuristic finds solutions for CFTS by scheduling jobs in the spirit of Smith's rule, 
working backwards from the end of the schedule. Since the makespan (the maximum completion 
time) of the optimal solution is not known, the heuristic starts with a trial makespan. After 
scheduling all of the jobs, we compute the actual makespan (by removing any idle time) and use 
this makespan as the starting point for another iteration. We continue this process until some 
limiting makespan is reached. At this point, another pass of the heuristic yields a schedule with 
the same makespan or a schedule that is infeasible (because some job or setup starts before time 
zero). 

This heuristic consirucLs schedules that satisfy Smith's property for CFTS (Lemma 3.1). 
While that lemma applies only to jobs in one class, our algorithm extends the idea of longest 



88 

eligible job by coasidering all of ihe job classes. Wc schedule the longest job with the minimum 
wasted time. Wasted time is time spent in a setup and idle time. 

This (single-pass) Minimum Waste algorithm schedules an eligible job from the same class 
as the previously scheduled job if one exists. Else, it selects a job from the class with the smallest 
setup or selects the job with the latest deadline. It does this by measuring each job's gap: the 
wasted time incurred by selecting that job. Note that if no class setups exist, this algorithm is the 
same as Smith's rule for CFT (Algorithm 3. 1). 
Algorithm 3.2 (Single-pass) Minimum Waste. 

Step 0: Given a completion lime t, select for the last job the longest job eligible at this time Jj, 
i.e. r < Dj. Schedule this job to end at t, and reduce t by pj. 

Step 1 (a modification to Smith's rule): Suppose that at time t, a job from class G,- starts. Then, 
for each unscheduled job J:, define q: as the gap between the last possible completion time of Ty 
and t. liJj is in class G^, q: = max {/ - Dj, 5^,} (see Remarks below for an explanation of this 
definition). Let ^ = min {q: over unscheduled 7, } . Select the longest job Jj with qj = ^ and 
schedule this job to end alt- q. Any necessary setup sj^i can begin alt-q. Reduce f by <? and pj. 
Step 2: If there remain unscheduled jobs, return to Step 1 . 

Step 3: Thert are no more unscheduled jobs. If the first job in the schedule is in class G,-, a setup 
of length SQi must end at f. Reduce t by this amount. 

Step 4: If r < 0, the schedule created is infeasible. Else, compute the actual makespan of the jobs 
and setups scheduled. 

Remarks. In order to motivate the definition of qj, the gap, let us note that the setup after Jj is 
Sj^, so the job may not complete after t - sj^. However, if the deadline Dj<t- s^-, the gap will be 
qj^t- Dj, which is greater than 5^^. This gap thus includes the setup and a period of inserted idle 
time of length f - D - 5^,. Note that iUj is also in class G,-, ^y = if and only if f < Dj. The 
algorithm is a type of greedy heuristic, in that it attempts to minimize the setup time or idle time 
in selecting jobs to be scheduled. 



89 

Multiple-Pass Minimum Waste Heuristic. To find a good solution for CFTS. we can use the 

following procedure that makes use of the single-pass Minimum Waste algorithm. 

Step A: Lclt'=mdi\ [Dj-.j = \, . . . ,n]. 

StepB: Letr = t'. 

Step C: Perform one pass of the Minimum Waste algorithm (Algorithm 3.2) with completion 

lime t. This creates a trial schedule. 

Step D: Let t' be the sum of processing times and setup times of this schedule. \f t' < t and the 

trial schedule is feasible, go to Step B. (The smaller makespan may yield another schedule.) 

Step E: If the trial schedule was infeasible or t' = t, take the last feasible schedule created and 

remove the inserted idle time, starling all jobs as soon as possible. This schedule is the result of 

the heuristic. If an infeasible schedule was created on the first pass, then lake the sequence of 

jobs from the schedule and process the jobs in this order, starting at time zero. This will yield a 

schedule with some violated deadline constraints. 

Because the problem of finding a feasible schedule is NP-complele, a single pass of the 
Minimum Waste algorithm is not guaranteed to find one. Still, as we shall see, it is usually able 
to find a feasible schedule if one exists. If a feasible schedule exists, it must finish by the 
maximum deadline, which is the first trial makespan. Initially, the heuristic is concemed with 
reducing the makespan. Eventually, as the makespan reaches a lower limit, the algorithm 
concentrates on the flowtime objective through its use of Smith's property to select a job. 
Example 3.2. Let us apply the Multiple-Pass Minimum Waste heuristic to Example 3. 1 . In the 
first iteration, f = 1 8, the maximum deadline. The first pass of the Minimum Waste algorithm 
performs the following calculations (see Table 3.2 for complete algorithm): at time 18, no jobs 
have been scheduled, and the only eligible job is J^. After choosing 75, t is reduced by pj = 2 to 
16. Foryy,yj, and y^, the waste is the gap until the deadline. Thus.t^y = 16-Dy = 13, and 
similariy for the other two jobs. For 72- however, D2 = 16. and the deadline gap is zero, but 
because J2 is in a different class than J^,q2 = sj2=\. Thus, J 2 has the smallest waste and is 
scheduled to end at lime 15. After five steps, all of the jobs arc scheduled (see Figure 3.1). There 



90 

are two units of inserted idle time, however, so the actual makcspan of the schedule can be 
reduced to 16. 



Table 3.2. Calculations of the first pass of the Minimum Waste algorithm. Initial makespan ; 
18. 



Time: 


Waste: 
Jl h 


J3 


J4 


h 


Schedule: 


18 
16 
13 
11 
6 


15 2 

13 1 

10 

8 

3 


4 
2 



8 
6 
3 
2 





J5 18 
h 15 
J3 13 
J4 9 
Jl 3 


Scheduled flowiimc: 58. 
Reduced makcspan: 16. 



SQl 


Jl 




Sl2 


J4 


S2I 


J3 


J2 


H2 


J5 



2 3 5 6 9 11 13 

Figure 3.1. Schedule created on first pass of heuristic. 



15 16 



18 



When the heuristic repeats the algorithm with the new makespan of 16 (see Table 3.3 for 
calculations), jobs J 2 and J^ are eligible at time 16. These jobs also have the same processing 
time, but suppose J2 is chosen. Then, at time 14, Jj is eligible and has no gap, as it is in the same 
class as J2. However, /j has a gap ^5 = S]2 = 2- The algorithm continues in this manner, 
creating the schedule shown in Figure 3.2. 

The Multiple-Pass Minimum Waste Heuristic again repeats the algorithm, which now 
begins at the reduced makespan of 15, and a similar schedule can be found if ^2 'S chosen at time 
15. This schedule has no idle time (see Figure 3.3), the reduced makespan is also 15, and so the 
heuristic stops. 



91 

Table 3.3. The second pass of the Minimum Waste algorithm. Initial makcspan - 16. 





Waste; 








Schedule: 


Time: 


h h 


^3 


h 


h 


^J Cj 


16 


13 


2 


6 





J2 16 


14 


11 





4 


2 


J3 14 


12 


9 




2 


2 


J4 10 


7 


6 









J5 7 


5 


2 








Jl 3 


Scheduled flowtimc: 50. 










Reduced makespan: 15. 











SQl 


h 




Hi 


h 


J4 


S21 


J3 


h 



2 3 4 5 7 10 12 

Figure 3.2. Second schedule. 



14 



16 



SQl 


Jl 


H2 


h 


J4 


S21 


J3 


J2 



6 9 11 13 

Figure 33. Third and final schedule. 



15 



3.2.5 The Genetic Algorithm 

In this section we present an alternative search space, the problem space, provide a brief 
introduction to genetic algorithms and some references to selected works, and discuss the details 
of the problem space genetic algorithm we used to find good solutions for CFTS. 

Problem space . The original work on problem and heuristic spaces is by Storer, Wu, and 
Vaccari (1990, 1992), who define some alternative search spaces for the job shop scheduling 
problem: the problem space and the heuristic space. They note that a solution to a problem is the 
result of applying a heuristic to the problem. Given a problem p, a heuristic /z is a function that 
creates a sequence corresponding to a solution s, i.e. h(p) = s. Thus, if one adjusts the heuristic, 
one creates a different solution. The set of adjusted heuristics is the heuristic space. Likewise, if 



92 

one adjusts the problem data that are used by the heuristic, one generates a different solution. 
This set of adjusted problem data is tlic problem space. The idea is applied to the job shop 
scheduling problem, and different heuristic searches over the spaces are pcrfomied, including hill 
climbing, genetic algorithms, simulated annealing, and tabu search. 

Our research extends this idea by defining a problem space for the one-machine class 
scheduling problem. If we adjust the deadlines that are inputs (along with the other problem data) 
to a pass of the Minimum Waste algorithm, we will create a possibly different schedule. We will 
use as a problem space for CFTS these adjusted deadlines, and we will use one pass of the 
Minimum Waste algorithm to create a sequence of jobs using the adjusted deadlines. The 
feasibility (against the actual deadlines) and total flowtime of the sequence can be evaluated by 
scheduling the jobs to start at time zero with no inserted idle time. The idea is to force jobs to be 
done earlier or later by decreasing or increasing the deadlines. We will prove that every solution 
for CFTS (including the optimal one) is in the range of /i. 

Theorem 3.1. For each solution to an instance of CFTS, there exists a vector of adjusted 
deadlines that can be mapped to that solution using one pass of the Minimum Waste algorithm. 

Proof. Suppose that o is a solution (a feasible schedule with no preemption or inserted idle 
time) for an instance of CFTS. For each job, consider adjusting the deadline so that it equals the 
job completion time. Then, if we use one pass of the Minimum Waste algorithm with the 
adjusted deadlines, the job selected for the last position will be the job with the maximum 
adjusted deadline. This job is the one with the maximum completion time C,- and thus was the 
last job in a. It will be scheduled to complete at its adjusted deadline, which is C,-. 

Now we are at the start time t of a job J^ and the job with the smallest gap is the 
unscheduled job J: that immediately precedes 7,- in o, since the adjusted deadline is Cj, and Cj < t. 
Any setup necessary between 7 . and J^ is already included in the difference between Cj and t. 
Thus the gap cannot be larger for this job, and the gap for any other job 7^ is larger since Q < Cj. 
This job will be scheduled to complete at its adjusted deadline, which is Cj. If we continue in this 



93 

manner, all of the jobs will be sequenced in ihc same order as Ihey were in a, and we create the 
same schedule. QED. 

The more we adjust the deadlines, the more change we create in the schedule. For instance, 
consider the following examples of applying one pass of the Minimum Waste algorithm to 
vectors of adjusted deadlines where we have changed only the second and fifth deadlines: (Note 
that the fourth schedule created is infeasible since J 2 completes at time 18, which is greater than 
the actual deadline: D2 = 16. The adjusted deadline of 19 was used only to sequence the jobs.) 

Heuristic(problem) = solution: 

Minimum Waste (3, 6, 14, 10, 20) = [ 1 2 4 3 5 ], flowtime 46. 

Minimum Waste (3, 16, 14, 10, 18) = [ 1 4 3 2 5 ], flowtime 50 (original deadlines). 

Minimum Waste (3, 17, 14, 10, 16) = ( 1 5 4 3 2 ], Howiimc 46. 

Minimum Waste (3, 19, 14, 10, 17) = [ 1 4 3 5 2 ], infeasible (C2 = 18). 

In Figure 3.4 we show a graph that illustrates how adjusting just two of the five deadlines 
of Example 3.1 can create a number of different schedules. The first, third, and fourth deadlines 
were not adjusted. Each point in the plane (only non-negative deadlines were considered) 
corresponds to a pair of values for the second and fifth adjusted deadlines. The points in each 
region of the plane are mapped by a pass of the Minimum Waste algorithm to the job sequence 
denoted by the five-digit sequence shown in that region. The dot marks the point that 
corresponds to the unadjusted deadlines {D2 = 16, D^ = 18). The best sequences achievable by 
adjusting these deadlines are 12435 and 15432 (total fiowtimc = 46), and the only other feasible 
sequences are 14235 and 14325 (total fiowUme = 50). The optimal solution (which cannot be 
found by adjusting only the second and fifth deadlines) is 13452, with total flowtime = 43. 

Since the actual problem space consists of all of the problem data and there are numerous 
heuristics that can be used, we can investigate other spaces and heuristics that might be usefiil. 
Our first search was to adjust the job processing times and to use the Shortest Processing Time 
(SPT) rule. However, it is difficult to find feasible solutions since SFT ignores the deadline 
constraints entirely. We also tried the using the Earliest Due Date (EDD) rule while adjusting the 



94 

deadlines, but EDD docs not give enough allenlion to the flowtime objective. Sequencing by 
either SPT or EDD is a fairly naive heuristic, since neither makes use ol the other available 
information. The Minimum Waste algorithm, however, considers due dates, processing times, 
and setups, and using it improves our searches. In addition, while it would be possible to use the 
Minimum Waste algorithm while adjusting the processing or setup times, the effect of these 
variables on the sequencing of jobs is more indirect than that of the deadlines. 

The use of a heuristic space seems to be hard for this problem. Feasibility is a large 
concern, and there are very few heuristics we can use to find feasible schedules. Also, the 
Minimum Waste algorithm has no parameters to adjust. 

Job 5 Deadline 



18 



14 













/ 


/ 


21435 


12435 


14235 


14325 

/ 


/ 






/ 


/ 


A 


/ 


14352 




21543 

/ 


12543 

/ 


15423 


15432 


r 

52143 


51243 


51423 




51432 





3 6 10 14 18 

Job 2 Deadline 



Figure 3.4. Graph of adjusted deadlines and schedules created. 



9S 

A genetic al^oriihm lor CHTS . In this section we discuss ihc details of the genetic 
algorithm we developed lo find better solutions for CFTS. As mentioned before, genetic 
algorithms arc heuristic searches that use a population of points in the effort to find the optimal 
solution. The stronger members of the population survive, mate and produce offspring that may 
undergo a mutation. These offspring form a new generation. Genetic algorithms have been used 
on sequencing problems before, although they cannot use natural crossover techniques in 
searching the solution space. The advantage of the problem space is that the genetic algorithm 
can use standard techniques to create offspring. 

Our genetic algorithm searches the space of adjusted deadlines. We use a binary coding for 
the adjusted deadlines and a single pass of the Minimum Waste algorithm as the heuristic. For 
this genetic algorithm, we use many of the ideas presented in Davis (1991), to which we refer 
readers who wish to learn more about the issues discussed here. 

In the problem space, each point is a vector of integers that are deadlines used as input for 
one pass of the Minimum Waste algorithm. We will use a binary representation of the points in 
problem space. In the population of the genetic algorithm, each individual is a string of bits. 
Each successive six-bit substring represents a deadline for a specific job. The integer decoded 
from tills binary number ranges from zero to 63 and linearly maps to a real number in the range 
from zero to the maximum deadline in the given problem data. This discretization reduces the 
problem space but still allows the deadlines to vary significantly with respect to each other. 

The adjusted deadlines are used as input to a single pass of tiie Minimum Waste algorithm, 
which outputs a sequence of jobs. The algorithm uses the largest of the adjusted deadlines as the 
initial makespan and schedules Uie jobs accordingly, using tiie actual job processing and class 
setup times where necessary but using the adjusted deadlines to determine when a job is eligible. 
If necessary, the algorithm can start jobs before time zero. 

Using the actual problem data and the sequence of jobs output from one application of tiie 
Minimum Waste Algoritiim, we can create a schedule of jobs Uiat starts at time zero and has no 



96 



inserted idle time. Wc evaluate the original string of bits by computing the feasibility and the 
total flowtimc of this schedule. 

Since we cannot guarantee that the algorithm will produce a schedule with no tardy jobs, 
we use a penalty function to make undesirable those individuals in the population that yielded 
infeasible schedules (with respect to the actual deadlines). This penally function is C> = X 7".-^, 
where T: = max (0, C. - D.} . Our objective function/is defined as/= 'LCj + r <I>. 

In order to encourage solutions with good total flowtime (regardless of feasibility) at the 
beginning of the search and to encourage feasibility near the end of the search, we start the search 
with the constant r small and increase it periodically. 

The initial population includes one individual (the dummy, or seed) that we create by 
dividing each actual deadline by the maximum deadline, multiplying by 63, rounding down to the 
nearest integer, and converting this integer (which is in the range to 63) to its binary 
representation. The remaining individuals in the initial population arc constructed by mutating 
the bits in the initial (dummy) chromosome. The mutation rate is set at fifty percent (0.5). Note 
that using an initial mutation rate of 0.5 is equivalent to choosing a random chromosome from the 
entire search space. 

Let us illustrate this procedure using Example 3.1, the problem we introduced earlier (see 
Table 3.1 for problem data). Also, let us define LxJ as the greatest integer less than or equal to x. 

Mapping the deadlines to the bit strings yields the dummy, shown in Table 3.4. Let us 
create another member on the initial population. If two bits, the fourth of the fourth substring and 
the first of the last substring, are flipped in the mutation, we have the point in problem space 
shown in Table 3.5. Performing one pass of the Minimum Waste algorithm on the new deadlines 
(see Table 3.6) yields the sequence [15 4 3 2], from which we create the feasible schedule 
shown in Figure 3.5, with a makespan of 15 and a total flowtimc of 46. 



97 



Table 3.4. Bit representation of the dummy. 



L63Dj/18j 


10 56 49 35 63 


Bits 


(XJioio iiicxx) ii(KX)i Kxxni mill 


Table 3.5. A point in the problem space. 


Bits 


(X)IOIO 111000 110001 100111 011111 


Integer 


10 56 49 39 31 


Dj 


2.85 16 14 11.14 8.85 



Table 3.6. Application of the Minimum Waste algorithm. 





Waste: 








Schedule: 


Time: 


Jl J2 


J3 


h 


J5 


Jj S 


16 


13.15 


2 


4.86 


7.15 


h 16 


14 


11.15 





2.86 


5.15 


J3 14 


12 


9.15 




2 


3.15 


J4 10 


7 


4.15 









J5 7 


5 


2.15 








Jj 2.85 







SOl 



'12 



J5 



L 



S21 



h 



2 3 4 6 9 11 13 15 

Figure 3S. Schedule corresponding to new bit string. 

After some experimentation we decided to use a steady-state genetic algorithm that created 

offspring by repeatedly (and randomly) selecting from a set of four genetic operators: one-point 

crossover, uniform crossover, and two types of mutation. Small mutation used a low probability 

(two percent per bit) of flipping a bit in the string; large mutation used a higher probability (fifty 

percent). The search used tournament selection for selecting the parents necessary for the 

crossover or mutation, and duplicate bit strings were not allowed in the population. Tuning was 

performed in order to dctenminc some good settings for various algorithm parameters. (See Table 

3.7. The problem sets used for tuning arc described in Section 3.2.6.) 



98 

Table 3.7. Flowlimc performance while tuning 2(XX)-individual genetic algorithm on 30-job 
problems (Ncwprot>4). 



Population 
Size 



Operator 
Probabilities 
(in percent) 



Increase 

in r 



Frequency 
of Increase 



Mutation Average 
Rate Ratio 



Tuning Increase in r and Frequency of Increase, Population Size = 10 



10 
10 
10 
10 
10 
10 
10 
10 
10 



25. 25. 
25. 25. 
25. 25. 
25, 25. 
25. 25. 
25. 25. 
25. 25. 
25.25. 
25.25. 



25.25 
25.25 
25.25 
25.25 
25.25 
25.25 
25.25 
25.25 
25.25 



+2 

+ 10 

+50 

+2 

+ 10 

+50 

+2 

+10 

+50 



10 

10 

10 

50 

50 

50 

100 

100 

100 



Tuning Increase in r and Frequency of Increase. Population Size 50 



50 
50 
50 
50 
50 
50 
50 
50 
50 



25. 25. 
25. 25. 
25. 25. 
25, 25, 
25, 25. 
25, 25. 
25.25. 
25, 25. 
25, 25, 



25.25 
25.25 
25.25 
25,25 
25,25 
25,25 
25.25 
25.25 
25,25 



+2 

+ 10 

+50 

+2 

+10 

+50 

+2 

+10 

+50 



10 

10 

10 

50 

50 

50 

100 

100 

100 



Tuning Increase in r and Frequency of Increase, Population Size 100 



100 
100 
100 
100 
100 
100 

Tuning Mutation Rale 

10 
10 
10 
10 
10 
10 
50 
50 
50 



25.25.25.25 
25.25.25.25 
25.25.25.25 
25. 25. 25. 25 
25, 25, 25, 25 
25.25.25.25 



25. 25. 
25. 25, 
25, 25. 
25. 25. 
25. 25. 
25. 25. 
25. 25. 
25.25. 
25.25. 



25.25 
25,25 
25,25 
25.25 
25.25 
25.25 
25,25 
25,25 
25,25 



+2 

+50 

+2 

+50 

+2 

+50 



+50 

+50 
+50 
+50 
+50 
+50 
+50 
+50 
+50 



10 

10 

50 

50 

100 

100 



10 
10 
10 
50 
50 
50 
10 
10 
10 



2% 


0.8575 


2% 


0.8666 


2% 


0.8562 


2% 


0.8646 


2% 


0.8700 


2% 


0.8624 


2% 


0.8676 


2% 


0.8755 


2% 


0.8625 


2% 


0.8597 


2% 


0.8660 


2% 


0.8623 


2% 


0.8669 


2% 


0.8687 


2% 


0.8654 


2% 


0.8619 


2% 


0.8626 


2% 


0.8669 


2% 


0.8800 


2% 


0.8794 


2% 


0.8738 


2% 


0.8792 


2% 


0.8751 


2% 


0.8716 


2% 


0.8562 


10% 


0.8990 


50% 


0.9962 


2% 


0.8624 


10% 


0.8953 


50% 


0.9629 


2% 


0.8623 


10% 


0.8994 


50% 


0.9236 



99 



Table 3.7. (Continued) 



Population Operator 


Increase 


Frequency 


Mutation 


Average 


Size 


Fitnesses 


in r 


of Increase 


Rate 


Ratio 




(in percent) 












Open 


alor Fitness 












10 


75, 0, 0, 25 


+50 


10 




2% 


0.8664 


10 


50. 15, 10, 25 


+50 


10 




2% 


0.8764 


10 


25,25.25,25 


+50 


10 




2% 


0.8562 


10 


15. 50, 10. 25 


+50 


10 




2% 


0.8758 


10 


0. 75, 0, 25 


+50 


10 




2% 


0.8592 


10 


75, 0, 0, 25 


+50 


50 




2% 


0.8730 


10 


50. 15. 10. 25 


+50 


50 




2% 


0.8628 


10 


25.25.25,25 


+50 


50 




2% 


0.8624 


10 


15,50,10,25 


+50 


50 




2% 


0.8649 


10 


0, 75, 0, 25 


+50 


50 




2% 


0.8688 


50 


75, 0, 0, 25 


+50 


10 




2% 


0.8574 


50 


50.15.10.25 


+50 


10 




2% 


0.8732 


50 


25,25,25,25 


+50 


10 




2% 


0.8623 


50 


15,50,10,25 


+50 


10 




2% 


0.8689 


50 


0, 75, 0, 25 


+50 


10 




2% 


0.8720 


3000 


-individual genetic algorithm 


on 50-job problems 


(ProbSOz). 




10 


25, 25, 25, 25 


+50 


50 




2% 


0.8880 


50 


25. 25. 25. 25 


+50 


50 




2% 


0.8931 


50 


25. 25. 0. 50 


+50 


50 




2% 


0.8739 



Notes: Performance is average ratio to solution found by the Multiple-Pass Minimum Waste 
Heuristic. Operators are one-point crossover, uniform crossover, large mutation, and small 
mutation. Mutation rate is probability per bit. 

These parameters included the population size, the mutation rate, the operator selection 

probabilities, and the rate of change of the penalty coefficient r. The rate of increase in the 

penalty coefficient affected the solution quality slightly. The mutation rate, population sizx, and 

relative probabilities of operator selection affected solution quality more significantly, with a 

smaller mutation rate (two percent, as mentioned earlier), smaller population sizxs, and a higher 

probability for selecting the small mutation yielding better solutions. These factors imply that the 

search can easily find good neighborhoods (especially since a point corresponding to the original 

problem data is included in the initial population) but needs to spend time hunting for a better 



100 

solution. Thus, a search that incorporates some kind of local search at the end of the genetic 
algorithm may be useful. 
3.2,0 Empirical Tv\stins 

In this section we describe a set of experiments performed in order to test the genetic 
algorithm and the heuristics. Wc discuss the generation of sample problems and the 
computational results. 

Problem generation . In order to test the heuristics and the genetic algorithm described 
above, it is necessary to create a set of test problems. We describe in this section how we can 
create problems that have at least one feasible solution and problems where finding a feasible 
solution is more difficult. 

The problems in the first problem set have 30 jobs in four classes, with random processing 
times in the range [1, 20] and sequence-dependent setup times in the range [0, 5]. For this set, we 
want to determine random deadlines in order to insure that some feasible schedule did exist. 

We use the following procedure: after computing the random class setup limes, each job is 
given a random processing time, and an initial completion time is computed by scheduling it after 
all previously constructed jobs. This first-generated, first-served schedule yields a makespan that 
becomes an upper bound for the deadlines, and each job is given a deadline determined by 
sampling a random variable uniformly distributed between the job completion time (in this 
schedule) and the makespan, i.e. the interval [ C.-, C^^ ]. Thus, the initial sequence is a feasible 
solution. 

In order to determine the performance of the genetic algorithm on minimizing the flowiime 
when feasible solutions are harder to locate, a number of additional problem sets are created. In 
addition to the problem set described eariicr, which includes problems that were known to have a 
feasible solution, we generate 30-job and 50-job problems with tighter deadlines. The 30-job 
problems have four job classes and the 50-job problems ten job classes. Tighter deadlines are 
achieved by extending the range of values that a random deadline could lake. Let us define a 
value k thai can range from zero to one. The deadline for 7. is taken from the interval 



101 

[k Cj, Cf^^, where the C.- and C^^^. arc from the original generated schedule. U k= 1 , this plan 
is the same as the original one, and the generated problem is guaranteed to have a feasible 
schedule. U k. = 0, all of the deadlines vary equally, and there may exist no feasible schedule. As 
k decreases from one to zero, the problems we generate have a higher probability of having fewer 
feasible schedules. We generated problems with k = 0, 0.2, and 1. Since the Multiple-Pass 
Minimum Waste Heuristic cannot find feasible solutions for some of these problems, we will see 
if the genetic algorithm can find solutions that are feasible. 

Results . In this section we discuss the results of our experiments with the solution 
procedures on the generated problem sets. We summarize the findings and present tables of the 
collected data. Since the optimal solutions are not known (a branch-and-bound algorithm to find 
optima requires excessive computational time) and no good lower bound can be determined, we 
measure the performance of the solution procedures relative to each other. 

Each procedure was run once on each of the problems in the problem sets. The procedures 
include the Multiple-Pass Minimum Waste Heuristic and the problem space genetic algorithm. 

For comparison purposes, we also implemented a version of the heuristic that Ahn and 
Hyun (1990) use to reduce the total fiowtime in class scheduling problems. They proposed an 
iterative heuristic that starts with an initial feasible sequence where the jobs in each class are in 
SPT order (since they are not concerned with deadlines) and applies both a forward and backward 
procedure to it, repealing the steps until no strict improvement is found. Each of the forward and 
backward procedures interchanges different subschedules where the second subschedule consists 
of jobs from one class and the first subschedule has no jobs from this class. If the interchange 
reduces the total fiowtime, the subschedules are switched; this maintains the class SPT propeny. 

Our version of this algorithm, called the Modified Ahn & Hyun heuristic, uses one pass of 
the Minimum Waste algorithm to form the initial schedule. In addition, a potential swap of two 
subschedules is performed only if the swap reduces the total fiowtime and maintains deadline 
feasibility. 



102 

The results (see Table 3.8) show that the genetic algorithm can find solutions that arc much 
better than those found by the Multiple-Pass Minimum Waste Heuristic and arc slightly better 
than those that Modified Ahn & Hyun heuristic produces. The genetic algorithm needs more 
time to find good solutions on the larger problems, although additional tuning may help improve 
the performance of the search. 

The searches for the 30-job problems were for 2000 iterations using the following 

parameter settings: population size of 10, all operator fitnesses equal, increase of 50 in r every 10 

individuals. The searches for the 50-job problems were for 3000 iterations using the same 

population size, no large mutations, and an increase of 50 in r every 50 individuals. 

Table 3.8. Total flowtime performance of heuristics on problems where a feasible was 
found. 



Problem Problems 


Jobs 


k 


Performance^ of Heuristics 


Set 






Genetic Algorithm 


Modified Ahn & Hyun 


Ncwprob4 10 


30 


1 


0.8562 


0.9130 


Prob2a 4 


30 


0.2 


0.9099 


0.9346 


Prob50z 10 


50 


1 


0.8739 


0.8755 


Prob2c 8 


50 


0.2 


0.8796 


0.8914 


Note: a: Performance 


IS average 


ratio to solution found by the Multiple-Pass 


Minimum Waste Heuristic. 









We observed that if the Multiple-Pass Minimum Waste Heuristic is unable to generate a 
feasible solution, the Modified Ahn & Hyun heuristic and the problem space genetic algorithm 
cannot locate a feasible solution. Thus our results are reported only for those problems where 
feasible schedules were created. 

The genetic algorithm is able to outperform the Multiple-Pass Minimum Waste heuristic on 
total flowtime at the cost of increased computational time, as a full 2000-individual run lasts 256 
seconds on average. (All computations performed on a 386 personal computer.) This is due to 
the effort of decoding the long bit strings into deadlines and the complexity of using one pass of 
the Minimum Waste algorithm to evaluate the individual. This computational effort is substantial 



103 

compared to that of running the Mulliplc-Pass Minimum Waste and Modified Ahn & Hyun 

heuristics. The heuristics need less than one second to find a good solution to a problem. A 

faster computer, however, would be able to reduce the computation time necessary for the genetic 

algorithm. Still, these results show that genetic algorithms that search the problem space can find 

very good solutions to scheduling problems. 

The improvement in total flowtime of the solutions that the genetic algorithm can find is a 

result of two things: the multiple sampling of the search space and the evolutionary process. This 

leads to the following question: Arc the genetic characteristics of the search a significant factor? 

We answer this question by changing the genetic algorithm so that each individual is a 

completely new one. Instead of choosing parents and creating offspring, we create new 

individuals by again mutating the dummy individual. This is a random sampling approach. (See 

Table 3.9.) These results imply that even though the same number of individuals are evaluated, 

the random sampling performs well but does not generate the same quality of solutions that the 

genetic algorithm does. Thus, we feel that the evolutionary process does contribute significantly 

to the improvement in total flowtime. 

Table 3.9. Total flowtime performance of random sampling on problems where a feasible 
was found. 



Problem Problems 


Jobs 


k 


Performance^ of Random Sampling 




Set 










Newprob4 10 


30 


1 


0.9435 




Prob2a 4 


30 


0.2 


0.9545 




ProbSOz 10 


50 


1 


0.9728 




Prob2c 8 


50 


0.2 


1.0165 




Note: a: Performance is average 


ratio to solution found by the Multiple-Pass 




Minimum Waste Heuristic. 









In conclusion, the genetic algorithm can find solutions with low total flowtimcs. This good 
performance is due to the multiple sampling of the problem space (since more than one 
neighborhood can be searched at once); the use of the Minimum Waste algorithm to create 



104 

solutions from adjusted deadlines; and the ability of the genetic algorithm to combine the best 
characteristics of the points in the initial population. 

3.2.7 Conclusions 

This portion of the work has two contributioas: it introduces an extended heuristic for the 
dual criteria class scheduling problem that we call CFTS, and it describes a problem space 
genetic algorithm used to find good solutions. The problem is to minimize the total fiowtime 
subject to deadline constraints. In this section we present a multiple-pass heuristic for finding 
good solutions and discuss problem space and the genetic algorithm. Finally, we describe our 
experimental results, in which we compared the genetic algorithm to some heuristic approaches. 
From these results we make the following conclusions: 

The Multiple-Pass Minimum Waste heuristic performs well at minimizing the total 
flowtime of CFTS. Though not an exact procedure, it is usually able to find feasible, high-quality 
solutions. 

A genetic algorithm that searches a problem space of the Minimum Waste algorithm for 
CFTS can find solutions with lower total flowtime. This genetic algorithm includes a penalty 
function for infeasible points that increases the cost of tardiness as the search progresses. In 
addition, it produces slightly better solutions than another procedure modified for this problem. 

3.3 Class Scheduling with Release and Due Dates 

In this section, we study the one-machine class scheduling problem of minimizing the 
number of tardy jobs. Moreover, some of the jobs have non-zero release dates. We describe an 
extended heuristic developed for this problem and a genetic algorithm used to find good 
solutions. We also discuss an extension of this problem to the question of minimizing tardiness 
with minimum number of tardy jobs. 



lOS 



3.3.1 Iniroduction 

The class scheduling problem studied in this section is to schedule a set of jobs, where 
some jobs have non-zero release dates, in order to minimize the number of lardy jobs. This 
problem is motivated by the semiconductor lest area. Since post-assembly testing is the last stage 
in semiconductor manufacturing, meeting a job's due date is a very important objective for the 
manager of a lest facility. The consideration of release dates is an attempt to model the look- 
behind situation thai exists in the job shop, where the scheduling of a machine (the bottleneck, for 
instance) may be improved by including infonmation about the jobs that are arriving soon. 

This problem, like most class scheduling problems, is a difficult case. Since even finding a 
schedule with no tardy jobs is an NP-complete problem, exact algorithms to solve our problem in 
polynomial time do not exist. Thus, wc are motivated to try different heuristics and searches. 

Our approach was to modify an existing algorithm to include class setups and see how such 
an algorithm performs on this problem. Since the heuristic was not guaranteed to find good 
solutions, we also investigated a genetic algorithm. Thus, this research presents contributions in 
the extension of class scheduling problems to include a problem that has not been previously 
investigated and the use of both genetic algorithms and problem spaces to include the search for 
good solutions to class scheduling problems. 

3.3.2 Literature Review 

In this section we will mention some of the most relevant research on class scheduling and 
on the problem of minimizing the number of tardy jobs in the presence of release dales. A full 
discussion can be found in Chapter 2. 

Bruno and Downey (1978) prove that, for general class scheduling problems, the problem 
of finding a schedule with no tardy jobs is NP-complete. Monma and Potts (1989) prove that 
class scheduling to minimize the number of tardy jobs is an NP-complete problem. 



106 

As discussed in Chapter 2, the one-machine problem of minimizing ihe number of lardy 
jobs when some have non-zero release dales (1 / r.7 Z Uj) is a slrongly NP-compleie problem 
(Lawler, 1982). A rcsiricied version of the problem has been considered by Kise, Ibaraki, and 
Mine (1978), who solve the problem optimally if the release and due dales match (r.< r^ implies 
dj < df.). They present an 0(n~) algorithm (Kise's algorithm, described in Section 3.3.4) for this 
case. 

3.3.3 Notation and Problem Formulation 

We will use the basic notation introduced in Section 3.2.3. For CSRDD, each job Jj has a 
release date r: and a due date d:. For a given schedule, (J: = 1 if C.- > d: and otherwise. The 
problem is to find a sequence that minimizes X (J; subject to the constraint that C: > n + pj. 

An NP-complcie problem, CSRDD is unstudied in the literature on class scheduling. In 
order to simplify the problem, it is assumed that the release and due dates match; that is, there 
exists an ordering where the jobs are simultaneously in Earliest Release Dale (ERD) order and in 
Earliest Due Date (EDD) order. Our primary heuristic for CSRDD extends Kise's algorithm for 
the problem without setups to form a heuristic for finding good solutions. 

3.3.4 Heuristics 

In this section we will describe a number of heuristics: Kise's algorithm for the problem 
without class setups, our extension of this algorithm, and other heuristics used for testing 
purposes. 

Kise's algorithm. Kise's algorithm orders the jobs by their release and due dates (a non- 
ambiguous ordering since the dates must match). The algorithm is an extension of the Moore- 
Hodgson algorithm (Moore, 1968) for minimizing the number of late jobs. Eachjob is scheduled 
after the partial schedule of on-time jobs while maintaining release date availability. If the new 
job is tardy, the algorithm searches the on-time jobs for the job whose removal leaves the shortest 
schedule of on-time jobs. The removed job is made tardy and will be processed with the other 



107 

tardy jobs after the feasible jobs. In this manner, the algoritlmi finds the largest subset of the jobs 
that can be delivered on-time. These jobs arc scheduled in order of their release and due dates. 
The search subalgorithm has effort that is linear in the number of jobs in the partial schedule. 
Since the subalgoriihm may be performed up to n times, the total effort of Kise's algorithm is 

0(«2). 

Rise's heuristic is not optimal for CSRDD, although it can be modified to include setup 
times. Take the following example: 



Example 3 J. 



J rj pj dj i 

10 5 6 1 

2 4 13 2 

3 5 5 14 2 

4 6 2 15 1 

■^01 =■^02 = 1- •^la^ 1- •^21 ='*• 



The optimal sequence is [7, 74/2 ^ ], with Cj = 6, C4 = 8, C2 = 13, and C^^ 18, which has 
one tardy job. Kise's algorithm adds J^, which is tardy after 7] and 72. and the subalgorithm 
makes 7) a tardy job. When 74 is added to the schedule after 72 and 73, it also is tardy, for a total 
of two tardy jobs. 

Kise extension. Our algorithm for CSRDD extends Kise's algorithm by considering two 
options when adding a new job to a partial schedule: we can place the job in a position after all of 
the on-time jobs or in a position after the last on-time job from the same class (if there is one). In 
either case, if an on-time job becomes tardy, we make tardy the job whose removal creates the 
shortest partial schedule of on-time jobs. We then choose between the two partial schedules 
created, selecting the new partial schedule with the smaller number of late jobs (or smaller 
makespan if they tie) as the incumbent before trying to schedule the next job. 

Intuitively, it appears that the extended algorithm should outperform the Kise algorithm, 
since it includes an additional scheduling choice. Due to the complexity of the problem, 
however, this is not guaranteed. The following problem is one counter-example: 



108 



Example 3.4. 



j rj pj dj i 

10 3 5 2 

2 3 13 1 

3 6 3 14 2 

4 14 3 17 2 

■^01 =•^21 = '• ■^02 = •^la^ 2. 

The optimal sequence is 1 J^ J2J3 J4 ], with C, = 5, C2 = 9, C3 = 14, and C4 = 17, with none 
tardy. Kise's algorithm will construct this schedule. In the proposed algorithm, the addition of 73 
to [JiJj] creates a partial schedule with no tardy jobs and a makespan of 14. The scheduling of 
Jj after/, and before ^2 ^^reates a makespan of 13 (C, = 5, Cj = 9, €2= 13), so the sequence [ J^J^ 
J2 ] replaces [ 7, J2J3 ]. When we add J^ after 72 . J4 is tardy (C4 = 18), and the on-time jobs 
complete at time 13; when J^ is scheduled before 72, 72 is tardy (C4 = 17, €2= 21). The algorithm 
thus yields [ 7, 73 72/4 ), which is not an optimal schedule. 

Tardiness rules. We also tested two heuristics based upon the R & M procedure of 
Rachamadugu and Morton (1982) and used for reducing weighted tardiness in Morton and 
Ramnath (1992). These are primarily class scheduling extensions. 

RM: A dispatching rule where the priority of a job at time t is based upon the weight, the 
processing time, and the slack of the job: 

RM = Wj/pj * exp( - Sj'^ I k * p^^g), 
where RM is the job priority, w.- the job weight, pj the processing time, Sj^ the slack max (0, dj - 
r - p.} , ^ a predefined constant, and p^^^ the average processing time of the jobs in the queue. In 
this formulation, jobs with higher weights, shorter processing times, and less slack will be 
scheduled first. According to Ramnath and Morton, the constant k is normally set to 2. 

X-RM: The x-dispatch (look-behind) version of the RM rule includes jobs that will be 
arriving soon in an extended queue. That is, they arrive before the completion time of the 
shortest job already waiting. The RM priority is discounted by an amount that depends upon the 
arrival time: 



109 

X-RM = RM * (1 - (1.3 + p)*(rj - t)^IPmin>' 
where X-RM is the job priority, p the utilization factor, r: the arrival time of the job, and /7^,„ the 
smallest processing time among jobs currently available. Morton and Ramnath (1992) claim that 
this procedure reduces weighted tardiness by 40% over the standard RM rule. 

These two priorities are used as dynamic dispatching rules. At a time r, the job with the 
highest priority is scheduled next. For our class scheduling problem, we redefine the components 
to include the setup times, but otherwise we use the same formulas. This works well for the 
objective of weighted tardiness, but for our objective (minimizing the number of tardy jobs), we 
would like to postpone the processing of the tardy jobs in order to concentrate on the on-time 
jobs. Thus, when we schedule a job that will be tardy, we look for the job whose removal will 
result in a shorter schedule with no tardy job and we remove that. 

For our class scheduling problem, we include in the processing time the class setup 
necessary to process a job and modify the release date by the same amount. That is, if the job 
completing at time t is in G^ and J : is in G^, we add s^j^ to p.- and subtract s^j^ from r.- (for the X- 
RM calculation). We use p = 1 and k = 2 and w. = 1 for all J:. 

3.3.5 Analysis of the Heuristic 

In this section we discuss the computational effort necessary to perform the extended Kise 
heuristic and the worst case error of this heuristic. A pseudo-code presentation of the heuristic 
and its subalgorilhm can be found in the Appendix. 

It is obvious that the extended version of Kise's heuristic takes more effort than Kise's 
algorithm. However, the effort of the algorithm is still 0{rfi). When adding the next job to a 
partial schedule, there arc two positions for the new job. The algorithm would take at most 0(n) 
effort to find the last job from the same class as the new job, to insert the new job, and to 
determine which (if any) jobs arc now tardy. If there is a tardy job, a pass of Kise's subalgorithm 
must be performed to determine which job to remove. This is also 0(/i). For the other position, 
there is 0(«) effort in adding the new job to the end of the partial schedule and pcrfomiing a pass 



110 

of the subalgoriihm. Thus, the total effort of adding the new job is 0(n). and since n jobs must be 
scheduled, the total effort of the extended Kise heuristic is 0(/|2). 

Since CSRDD is strongly NP-complcte, there is no optimal polynomial or pseudo- 
polynomial algorithm. Since our extended Kise heuristic is not guaranteed to find an optimal 
solution, we need to look into the worst-case error bound. In the following we describe two 
families of instances for CSRDD where the extended Kise heuristic cannot find good solutions. 
While the first of these examples prove that the heuristic can perform arbitrarily badly, the 
examples will also provide problem instances that we can use for testing the performance of the 
genetic algorithm. They are especially good for this since we know the optimal solution in 
advance. 

Example 3S. In this case, the extended Kise heuristic finds n - 1 out of n jobs tardy when the 
optimal has only two tardy jobs. There are n jobs where 7) is in G, and J2, . . ■ ,Jn are in Gj, and 
the jobs have the following characteristics: 

Jj Jj h' ■ ■■ < ^n 

Fj 1 

Pj 1 1 

dj 1 n 



The class setups are as follows: 



Gi 


Gi 


G2 


SQi 





2 


Hi 


- 


n 


S2i 





-. 



The optimal sequence (for n>2) begins with the /i - 1 jobs in G2. The last job ends at 1 -t- 
(/i - 1) = n, so they are all on-time. Since /j is scheduled after this, it is tardy. The Kise and Kise- 
extension algorithms start by scheduling 7, first. This job completes at time 1. When the first job 
from G2 is scheduled to fomi [ 7, 72 1. the job completes at 1 + /z + 1 = n + 2 and is therefore 
tardy. Removing 7i yields a partial schedule that ends at time 2 and is thus longer than the partial 



Ill 

schedule consisting of jusl 7|. Thus J 2 is made lardy. This continues for all of the jobs from Gi, 
and they are all forced to be tardy, for n - 1 tardy jobs. 

Example 3.6. In this case the optimal solution has no tardy jobs and the extended Kise heuristic 
finds n/3 tardy jobs. We construct the problem instance in the following way: choose a non- 
negative integer it. Letrt = 3(/k+ 1). Letm = 3. For / = 0, ..., /t, construct three jobs, 73,^.1 in 
Gi,J2i+2 •" ^2' 2nd J2i+3 in G3, with the following job characteristics, where < e < 1 and 
0<6<1: 



'J 
Pj 



Jsi+l 
3i 

1-e 

3i+2 



•'31+2 h\+3 

3i 3i 

1+e 1 

3i+2+6 3i+3. 



Let the class setups be as follows, where s>5: 



Gi 


Gi 


G2 


G3 


SQi 











Sli 


- 


s 





S2i 





- 


s 


S3i 


1 





-. 



The optimal sequence of jobs is [ JiJi J^J^J^Jf, . . . ■f'ik+l-^Sk+l •^3k+3 ]• ^'^ schedule 
has no inserted idle time and no setup time (see Figure 3.6). 



h 


h 


h 


h 


h 


h 




•'3k+2 


J3k+1 


J3k+3 



1+e 



4+e 5 6 

Figure 3.6. Optimal Schedule. 



3k+l+e 3k+2 3k+3 



Taking the jobs in ERD order, we schedule 7, first (C, = 1 - e). J2 is scheduled next, but C2 
= Ci + S12 + P2 = 2 + i > ^2 = 2 + 5. Thus, J2 is tardy, and since P2>P\< J\ remains while J2 is 
now tardy. J^ is added next, with C3 = C] + ^13 +^3 = 2 - e. J^ is added next, starting at time 3 > 
C3 + 531 = 3 - e and completing at time C4 = 4 - e. (Starting 74 after 7, makes 73 tardy.) By 
repeating the above argument, it can be shown that 75 will be made tardy and 7^ will follow 74. 



112 



This process conlinucs for all of the jobs (see Figure 3.7). Thus, the heuristic creates a schedule 
where the )t + 1 = /i/3 jobs in G2 are tardy, while the optimal schedule has no tardy jobs. Note 
that we never insert a job into the middle of a partial schedule; thus, Kise's algorithm and the 
extended Kisc heuristic create the same schedule. 



Jl 


J3 


S3I 




J4 




Jsk+l 


Jsk+S 


h 


Jsk+Z 



1-e 2-e 3-e 3 4-e 3k 3k+l-e 3k+2-e 3k+3 

Figure 3.7. Heuristic Schedule. 



4k+3+ke 



The first of the two above cases will be useful in the proof of the following error bound 
theorem. For the purposes of Theorem 3.2, we assume that the triangle equality holds for the 
class setups: s^ + Sfj^ > s^, for all a = 0, . . . , m, b = \ , . . . , m, c = I , . . . , m. 

Theorem 3.2. For an instance of CSRDD, if there exists a schedule in which at least one job 
completes on-time, the extended Kise heuristic will create a schedule with at least one on-time 
job. Moreover, there exist problem instances where the heuristic will schedule exactly one on- 
time job, although there exist schedules with more than one on-time job. 

Proof. First, we note that the number of scheduled on-ume jobs never decreases as the extended 
Kise heuristic schedules new jobs. Now, consider a job J: in class Gj that completes on-time in 
some feasible schedule. Thus, for 7.-, C: < dj. Now, C; > n + p.- and C: > sqi + pj, since by the 
triangle inequality stated above, if there exist any jobs before Jj, the sum of the setups before 7. is 
at least sq^. Thus, d: > r .• + pj, and d: > sq^ + pj. 

Suppose that the schedule created by the extended Kise heuristic has no on-time jobs. 
Then, when Uie extended Kise heuristic considered J:, no oUier on-time jobs were scheduled. The 
heuristic started J; as soon as possible (the maximum of r: and sq^), but J; was tardy. Thus, 
Cj = max (r.-, sqi) + p, > dj, but this contradicts the result above. Thus, the heuristic creates a 
schedule with at least one on-time job. 



113 

Thus, wc have shown ihat Uic extended Kise hcurislic will schedule at least one on-time 
job. This bound is tight, as our discussion of Example 3.5 shows that there exist problems for 
which the heuristic will schedule exactly one on-time job although the optimal schedule has more 
than one on-time job. 

3.3.6 The Genetic Algorithm 

In this section we present the problem space and discuss the details of the genetic algorithm 
we used to fmd good solutions for CSRDD. 

Problem space. In Chapter 2 we described the ideas of alternative search spaces. In this 
section we present the problem space that we searched in order to find good solutions for 
CSRDD. 

We defined a problem space for CSRDD in the following manner: Given a problem p in 
problem space, a heuristic /i is a function that creates a sequence corresponding to a solution s for 
CSRDD, i.e. h(p) = s. We defined a problem as a vector of job release dates, using a pass of 
Rise's algorithm to create a sequence of jobs by considering the jobs in order of their new release 
dates instead of the order imposed by the matching release and due dates. The actual release 
dates are used in determining the schedule, however. Note that all solutions for CSRDD 
(including the optimal ones) that schedule all tardy jobs last are in the range of h. Following are 
two examples of applying this heuristic to different vectors of deadlines for the problem in 
Example 3.3: 

Heuristic(problcm) = solution: 

Kise (0, 1 , 5, 6) = [ 72 -^s -^i -^4 ]• two jobs tardy. 
Kise (0, 8, 5, 4) = [ 7] J^ Jj Jj ], one job urdy. 

A genetic algorithm for CSRDD. In this work we developed a genetic algorithm based on 
the ideas presented in Davis, 1991, namely, steady-state reproduction without duplicates. 



114 

fitnesses measured by linear normali/ation, a unilomi crossover operation, operation selection, 
and interpolated parameters. 

Steady-state reproduction adds new individuals a few at a time, whereas the traditional 
method replaces the entire population with a new generation. Steady-sute reproduction 
(attributed to Whitley, 1988, and Syswerda, 1989) is used to ensure that good individuals (and 
their good characteristics) survive. Steady-state reproduction without duplicates prevents 
children that are identical (in chromosome values) to a current member from joining the 
population. 

Linear normalization is a fitness technique that creates fitness values by ordering the 
individuals in a population by their objective function evaluation. The assignment of fimesses 
begins with a constant value and decreases the fitness linearly as it considers each individual in 
order. This technique prevents a super individual from dominating the population at the 
beginning of a run and yet differentiates between the various very good individuals that exist near 
the end of a run. Of course the values of the original constant and the decrement parameter 
influence the extent of these two phenomena. 

Uniform crossover, an operator first described by Syswerda (1989), is a way to combine 
characteristics in ways that standard one- or two-point crossovers cannot. In a uniform crossover, 
two parents are selected and two children produced. Each bit position is considered 
independently and the parent that contributes the bit value for that position in the first child is 
determined randomly. The second child receives the value for that position from the other parent. 
While uniform crossover can destroy a good characteristic by mixing it with a bad string, it can 
also combine features that are widely dispersed across the string. 

Since one-point crossover remains a good operator, however, we used both types of 
crossover in our genetic algorithm. Before creating a child, we randomly decide on which 
operator we wish to perform: uniform crossover, one-point crossover, or mutation. Each operator 
has an operator fitness and the probability of that operator being selected is proportional to that 
fitness. If one of the crossovers is selected, two parents are selected and two children are created. 



115 

If the mutation operator is selected, one parent is selected and a child created by forcing each bit 
to undergo a mutation with some small probability. The child or children created are checked 
against the current population for duplication, evaluated, and iascricd into the population, 
replacing the worst members of the population. The new population is then reordered and new 
fitnesses created using the linear normalization teclmique. 

As we did with the CFTS genetic algorithm, the initial population included one individual 
(the dummy, or seed) that was created form the actual problem data. The remaining individuals 
in the initial population were constructed by mutating the bits in the initial (dummy) 
chromosome. This initial mutation rate was set at 0.05 per bit. 

We interpolate the following parameters over the course of the run: the decrement for linear 
normalization is increased, and the operator fitnesses are changed to favor crossovers and 
discourage mutations. 

Table 3.10. Parameter values for genetic algorithm. 



Population size: 100 




Linear normalization decrement: 0.2 to 1.2 




Probability of selecting mutation operator: 35% to 25% 




Probability of selecting uniform crossover operator: 40% to 30% 




Probability of selecting one-point crossover operator: 25% to 45% 




Mutation rate: 0.02 per bit 





3.3.7 Empirical Tests and Results 

In this section we describe the empirical tests conducted to test how well the heuristics and 
genetic algorithm perform. 

Problem generation. We created problem sets using the due date assignment method of 
Hariri and Potts (1989). The release dates can also be created using a similar method. In this 
method, setup times and processing times of the jobs are determined first from random variables. 
Then, an estimate of the maximum completion time is made by simply summing the job 



116 

processing times. This makcspan is used to define a specific ranges for the due dales and a range 
for the release dales. The due dales and release dates arc sorted and the matching pairs are given 
to the jobs. By changing the paramclcrs governing the definition of the ranges, problem sets with 
different characteristics can be created. 

Different sets of 10 problems were created. The number of jobs fxr problem ranged from 
15 to 100. The processing times ranged from 1 to 20 and the class setup times from to 9. The 
jobs were randomly placed into a number of job classes, depending on problem size. The release 
dales and due dates were taken from a uniform distribution. The upper and lower bounds of this 
distribution were proportional to the sum of the job processing limes. The proportions changed 
for each problem set. (See Table 3.11.) 

Table 3.11. Data on problem sets. 

Set Problems Jobs Classes Release date Due date 

range range 

KH301 10 30 4 0-0.4 0.4-0.6 

KH302 10 30 4 0-0.4 0.6-1.0 

KH151 10 15 4 0-0.4 0.4-0.6 

KH501 10 50 5 0-0.4 0.4-0.6 

KH303 10 30 4 0-0.4 0.2-1.0 

KH304 10 30 4 0-0.6 0.2-1.0 

KHM1XED2 10 30 4 - 0.4 0.4 - 0.6 

KHM1XED3 10 30 4 0-1.0 0.4-1.2 

KHMIXED4 10 30 8 0-1.0 0.4-1.2 

Results. After numerical testing on these forty problems, it appears that the Kise and Kise 
extension heuristics and the R & M heuristics arc fairiy equal. A number of other heuristics werc 
unable to find as many on-time jobs. Note thai the lower bound was derived by using Rise's 
algorithm while ignoring all setup limes. 



117 
Table 3.12. Average jjerformance of heuristics. 



Set 


Jobs 


Lower 

Bound 


Kisc 


Extended 
Kisc 


RM 


X-RM 


KH301 


30 


8.3 


12.0 


10.7 


11.6 


11.6 


KH302 


30 


1.1 


4.9 


2.7 


4.2 


4.3 


KH151 


15 


4.8 


6.8 


6.4 


6.6 


6.7 


KH501 


50 


12.6 


19.5 


16.0 


17.9 


17.9 



Note: Performance is the average number of lardy jobs found by that heuristic on the ten 
problems in each problem set. 

In addition to the problems where the release and due dates matched, we created a set of 
30-job problems where no such correspondence existed. These ten problems had the same 
characteristics as the problems in the set KH301. On these problems the R & M heuristic 
performed slightly better than the extended Kise heuristic. 

Table 3.13. Average performance of heuristics, non-matching release and due dates. 

Set Jobs Kise Extended RM X-RM 

Kise 

KHMIXED2 30 7.7 5.3 4.5 4.7 

KHMIXED3 30 11.1 10.2 8.9 8.7 

KHMIXED4 30 10.0 9.2 7.2 7.0 

Notes: Performance is the average numberof tardy jobs found by that heuristic on the ten 
problems in each problem set. 

Since the heuristics were finding good solutions, we decided to test the problem space 
genetic algorithm on 18- and 30-job problems that could not be solved well by the heuristics. 
These problems were instances of the problem described above in Example 3.6, where the 
extended Kisc heuristic creates a schedule where a third of the jobs are tardy, although an optimal 
schedule has no tardy jobs. These results show that the problem space genetic algorithm is able 
to find good solutions. (In some of the following graphs we present our results with the number 
of on-time jobs, since the objective of the genetic algorithm was to maximize the numberof on- 
time jobs.) 



118 



Set 



Table 3.14. Average performance of heurislics, hard problems. 

Jobs Kise Extended Genetic Algorithm" 

Kise 1 ()()() 3(XX) 



Hard A 


18 


6.0 


6.0 


0.6 


HardB 


30 


10.0 


10.0 


4.5 



1.5 



Notes; Performance is the average number of TARDY jobs found by that heuristic on the five 

problems in each problem set. 

a: Results reported at 1000 and 3000 individuals. 



18 



17- 



s 




o 


16 


<—> 




4> 




E 








*-* 




c 




O 


ib 


<*- 




o 




u« 




Ji 




E 

3 


14 


z 





13- 




12 



100 200 300 400 500 600 700 800 96o 1000 

Number Created 



Figure 3.8. 1 8-job problems, Average number of ON-TIME jobs. 



119 



Table 3.15. 18-job problems, number of ON-TIME jobs. lOrunsoflOOO: 



Number of 


Problem 










Avei 


Individuals 














Created 


1 


2 


3 


4 


5 







13.7 


13.9 


13.5 


13.6 


13.4 


13.6 


100 


13.9 


14.1 


14.1 


14.0 


13.9 


14.0 


200 


14.7 


14.5 


14.7 


14.8 


14.9 


14.7 


300 


15.4 


15.3 


15.5 


15.5 


15.3 


15.4 


400 


16.2 


16.1 


16.1 


16.5 


15.8 


16.1 


500 


16.5 


16.5 


16.9 


16.6 


16.5 


16.6 


600 


16.8 


16.8 


17.1 


17.0 


16.8 


16.9 


700 


16.9 


17.3 


17.3 


17.3 


17.0 


17.2 


800 


17.0 


17.5 


17.3 


17.3 


17.5 


17.3 


900 


17.0 


17.5 


17.4 


17.3 


17.5 


17.3 


1000 


17.1 


17.5 


17.5 


17.3 


17.5 


17.4 




1000 1500 2000 

Number Created 



2500 



3000 



Figure 3.9. 30-job problems, average number of ON-TIME jobs. 



120 

Table 3.16. 30-job problems, number of ON-TIME jobs; 3 runs of 3000 

Number of Problem Average 

Individuals 

Created 12 3 4 5 






20.3 


20.3 


20.7 


21.3 


20.7 


20.67 


100 


21.3 


21.0 


21.0 


21.7 


21.3 


21.27 


200 


21.7 


21.7 


21.0 


22.0 


21.7 


21.60 


300 


22.0 


22.0 


21.7 


22.0 


22.0 


21.93 


400 


22.7 


22.3 


22.3 


22.7 


22.3 


22.47 


500 


23.3 


23.0 


22.7 


23.0 


23.3 


23.07 


600 


24.0 


24.0 


23.0 


23.3 


23.7 


23.60 


700 


24.0 


24.0 


24.0 


23.7 


23.7 


23.87 


800 


25.0 


24.3 


24.7 


24.7 


24.7 


24.67 


900 


25.0 


24.7 


25.0 


24.7 


25.0 


24.87 


1000 


25.7 


25.0 


26.3 


25.3 


25.3 


25.53 


1100 


26.0 


26.0 


26.7 


26.3 


25.7 


26.13 


1200 


26.3 


26.0 


27.0 


26.7 


26.0 


26.40 


1300 


26.7 


26.7 


27.7 


26.7 


26.3 


26.80 


1400 


27.0 


26.7 


28.0 


26.7 


26.7 


27.00 


1500 


27.3 


27.0 


28.0 


27.0 


26.7 


27.20 


1600 


27.3 


27.3 


28.0 


27.3 


27.0 


27.40 


1700 


27.7 


27.3 


28.3 


27.3 


27.0 


27.53 


1800 


28.0 


27.7 


28.3 


27.3 


27.3 


27.73 


1900 


28.0 


27.7 


28.3 


28.0 


27.3 


27.87 


2000 


28.0 


27.7 


28.3 


28.3 


27.7 


28.00 


2100 


28.3 


27.7 


28.3 


28.3 


27.7 


28.07 


2200 


28.3 


27.7 


28.3 


28.3 


28.0 


28.13 


2300 


28.3 


27.7 


28.3 


28.3 


28.3 


28.20 


2400 


28.3 


28.3 


28.3 


28.3 


28.3 


28.33 


2500 


28.3 


28.3 


28.3 


28.7 


28.3 


28.40 


2600 


28.3 


28.3 


28.3 


28.7 


28.3 


28.40 


2700 


28.3 


28.3 


28.7 


28.7 


28.3 


28.47 


2800 


28.3 


28.3 


28.7 


28.7 


28.3 


28.47 


2900 


28.3 


28.3 


28.7 


28.7 


28.3 


28.47 


3000 


28.3 


28.7 


28.7 


28.7 


28.3 


28.53 



3.3.8 Extension to Minimizing Tardiness 

In addition to simply minimzing the numberof tardy jobs, it is often an objective of 
schedulers to minimize the total tardiness of the tardy jobs. To this end, we study the problem of 



121 

minimizing the total tardiness subject to a constraint on the number of tardy jobs, since the 
minimization of total tardiness usually leads to schedules where many jobs are tardy and arc tardy 
by a small amount. Since finding the minimum number of lardy jobs is an NP-completc problem, 
we use our heuristic to set the value of the constraint. Then, within that limitation, we minimize 
the total tardiness. 

We develop some further extensions of Kise's algorithm that create a set of tardy jobs and 
then insert the tardy jobs into the schedule of on-time jobs in order to reduce the total tardiness. 
We also use our genetic algorithm to search for schedules with low number of tardy jobs and low 
total tardiness. 

The problem of minimizing tardiness subject to a minimal number of tardy jobs has been 
considered for the problem without class setups (or release dates) by Vairaktarakis and Lee 
(1993), who develop an algorithm to optimally schedule a given set of tardy jobs and an efficient 
branch-and-bound technique to find the optimal tardy set. Other researchers have studied dual 
criteria problems with the same primary objective. Emmons (1975) considered the problem of 
minimizing total fiowtime subject to minimum number of tardy jobs, using a branch-and-boimd 
algorithm to find optimal solutions. Shanthikumar (1983) examined the problem of minimizing 
the maximum lateness subject to minimum number of tardy jobs, also using a branch-and-bound 
algorithm. 

Our problem, which includes both class scheduling and non-zero release dates, is an NP- 
complete problem. The tardiness heuristics that we use to find good solutions use the extended 
Kise heuristic to determine a set of tardy jobs. The heuristics also use the sequence of on-time 
jobs created by the extended Kisc heuristic, pushing the jobs to the right, staning them as late as 
possible, and attempting to insert the tardy jobs into the gaps in this schedule. 

The first heuristic (7,) orders the tardy jobs by their release dates and attempts to 
interieave the two sequences of jobs, scheduling tardy jobs to start as soon as possible while 
maintaining the feasibility of each on-time job (whose completion time is constrained by the due 
date). 



122 

The second heuristic (T2) considers every tardy job as a candidate for a gap between the 
partial schedule and the next on-time job, selecting the tardy job that yields te earliest start time 
for the next on-time job. Any remaining tardy jobs arc scheduled by their release dates. 

The third heuristic (Tj) was a modification of the second that scheduled the remaining 
tardy jobs using a version of the Minimum Waste heuristic (see Section 3.2) that didn't consider 
deadlines (since all jobs arc tardy). This heuristic has been shown to perform well on fiowtime 
criteria. We use this because minimizing the total tardiness of the set of tardy jobs is identical lo 
minimizing the total fiowtime of those jobs. 

Due to the non-optimal nature of the extended Kise heuristic, it is possible that the 
tardiness heuristics will often be able to schedule a tardy job so that it finishes on-time (reducing 
its tardiness to zero). However, the primary objective of these heuristics is to reduce tardiness, 
not reduce the number of tardy jobs. 

Results . We tested the heuristics on three problem sets, selected because the variance of 
the due dates meant that the schedules were more likely to have gaps in which to insert tardy jobs. 
Each solution technique was measured by the average total tardiness found by that heuristic on 
the ten problems in each problem set and the percent deviation of this average from the average 
tardiness found by the extended Kise heuristic. The performance of the genetic algorithm on 
each problem is the average of ten trials of one thousand new individuals. 

Table 3.17. Data on new problem sets. 



Problems 


Jobs 


Qasses Release date 


Due date 






range 


range 


10 


30 


4 0-0.4 


0.2- 1.0 


10 


30 


4 0-0.6 


0.2-1.0 



Set 



KH302 
KH303 
KH304 



Extended 
Kise 

236.4 
758.3 
920.0 



123 
Table 3.18. Average performance of heuristics. 
T, % T2 % 



237.3 
756.6 
869.0 



-0.38 
0.22 
5.54 



234.7 
718.4 
859.4 



0.72 
5.26 
6.59 



231.5 
704.1 
844.0 



Note: Performance is the average total tardiness and the percent improvement. 

Table 3.19. Average performance of heuristics. 

% 



8.30 



Note: Performance is the average total tardiness and the percent deviation. 



Set 


Extended 


G.A. 


% 


G.A. 




Kise 






3000 


KH302 


236.4 


229.0 


3.13 




KH303 


758.3 


884.3 


-16.62 


695.3 


KH304 


920.0 


771.9 


16.10 





% 



2.07 
7.15 
8.26 



3.3.9 Conclusions 

In this section we have introduced a class scheduling problem that we call CSRDD. The 
problem is to minimize the number of tardy jobs where some jobs have non-zero release dates, 
and we assume that the release and due dates match. We have described a heuristic developed to 
find good solutions. We have discussed a problem space and a genetic algorithm to search this 
space. We have described our experimental results, from which we make the following 
conclusions: 

Our extended Kise heuristic can find good solutions for instances of CSRDD. It can do this 
by considering the class setups in both the subalgorithm that decides on which job to make tardy 
when a new job is added and the option to insert the new job into the middle of the partial 
schedule in order to reduce the number of setups. 



124 

When the extended Kise heuristic cannot find good solutions, our problem space genetic 
algorithm can. By searching tlic problem space near the original problem, it can discover 
solutions that arc improvements on the schedule constructed by Kisc's algorithm. 

Also in this section wc discussed an extension of this problem to the problem of 
minimizing total tardiness in the presence of a constraint on the number of tardy jobs. 

3.4 Flowtime with Setups and Release Dates 

The third of the class scheduling problems that we consider has jobs with non-zero release 
dates, and the objective is to minimize the total flowtime. We develop some lower bounds and 
dominance properties and examine some heuristics for finding good solutions to the problem. 
We discuss a problem space genetic algorithm that can improve the performance of a look-behind 
dispatching rule. For this problem we also developed a search technique for comparison 
purposes. 

3.4.1 Introduction 

This problem, like the others we have examined, is motivated by considering the 
scheduling of a semiconductor test area. We have class setups, arriving jobs, and an objective 
that mirrors the goal of management to minimize work-in-process inventory. 

We will examine the problem of minimizing total fiowtime when the jobs have non-zero 
release dates. This strongly NP-complcte problem is a look-behind scheduling model, where we 
are interested in scheduling a machine by considering the jobs that will be arriving at the machine 
soon. 

In addition to a look-behind scheduling rule, we will consider the use of a problem space 
genetic algorithm (similar to those developed for CFTS and CSRDD) that can improve the 
performance of this rule by adjusting the parameters of the rule. Due to the structure of the 
FTSRD problem, we will also use a decomposition heuristic as a means of comparing solution 



125 

quality. The decomposition heuristic is a search technique that considers a sequence of 
subproblcms at each move. 

In the next section we will introduce the notation and problem formulation. After that we 
will mention some of the previous research on the scheduling problem under consideration (a 
review of the literature on class scheduling and genetic algorithms can be found in Chapter 2), 
examine some lower bounds and dominance properties that can be used in a branch-and-bound 
technique, discuss our heuristics (including sequencing rules and the genetic algorithm), and 
report on the experimental results. 

3.4.2 Notation and Problem Formulation 

We use the same notation as that for the CFTS and CSRDD problems (Sections 3.2.3 and 
3.3.3), except that the jobs do not have due dates. The FTSRD problem is to find a sequence that 
minimizes X C.- subject to the constraint that C.- > r.- + p .. We will see that FTSRD is NP- 
complete and has not been previously considered in the literature on class scheduling. 

We make two assumptions in the analysis of the problem. One, a class setup for a job can 
begin before the job is available. Two, although all of the release dates are known, the processing 
for a job cannot begin until the release date. These conditions are motivated by our consideration 
of the one-machine problem as part of the job shop scheduling problem. 

3.4.3 Background 

The one-machine problem of minimizing total flowtime when the jobs have non-zero 
release dates has been previously studied in the case where no sequence-dependent setups are 
present The problem is simple if the jobs are preemptive, that is, if a job that has begun 
processing can be interrupted by another job and then resumed later. In this case, the optimal 
policy at the next decision point is to schedule the job with the shortest remaining time. The set 
of decision points includes all job release times and completion times. If the jobs are non- 



126 

preemptive and have no sequence -dependent setup times, the problem (denoted by 1 / r./ Z Cp is 
a strongly NP-complete question, as shown by Lenstra et al. (1977). 

Among class scheduling problems, minimizing the total flowtime is a strongly NP- 
complete problem (Monma and Potts. 1989). Thus, it can be seen that our problem, which is to 
minimize total flowtime with class setups and release dates, is also a strongly NP-complete task. 

Many researchers (see Chapter 2) have considered the problem of minimizing the total 
flowtime subject to job release dates, 1 / r.- / X C:. Branch-and-bound algorithms have been the 
most popular approaches. None of these researchers included sequence-dependent setup times in 
their analysis. 

3.4.4 Solution Techniques 

In this section we will discuss a number of different approaches to solving the FTSRD 
problem. These include branch-and-bound searches, dispatching rules, a decomposition heuristic, 
and a genetic algorithm. A job arrives at r .- and is available at time r if f > r.-. Recall that we 
assume that a class setup can be performed before the associated job becomes available. 

Branch-and-bound . A straightforward branch-and-bound algorithm can be developed for 
this scheduling problem. The branch-and-bound procedure finds the optimal solution by 
searching a tree that consists of every possible permutation. Each node of the tree consists of a 
partial schedule of jobs processed in that order and as soon as possible. (The root node consists 
of an empty schedule.) Unscheduled jobs will be appended to the schedule for a node. 
Branching occurs by adding a child node for each unscheduled job. A lower bound can be 
calculated for each node, and the search moves to the child with the lowest lower bound. 

Local dominance properties . The number of nodes to be examined can be reduced by 
applying dominance properties that identify nodes that cannot lead to optimal solutions. Local 
dominance properties claim that a node a is dominated by another node (3 under certain 
conditions. Thus, we do not need to branch on node a because we can find a better solution by 
branching on p and searching its dcsccndcnts. 



127 



We note here that matching processing limes and release dates do not imply a dominance 
property. Even if p.- < pi implies r.- < r,- (or even if the release dales are identical) within each 
class, we do not have an optimal order for the jobs in each class. Consider the following 
instance: 



A 


3 





h 


4 





h 


4 





h 


1 


6 


Js 


1 


6 


h 


1 


6 



•^01 -•^21 -•^02- •^12- ^• 

The optimal solution is [J2, J4, J5, ^, ^i- ^3]. with a total flowtime of 59. The best solution 
in which G^ is in SPT order are [y,, J4, J5, J(,, Ji, ^]. with a total flowtime of 60 (see Figure 
3.10). 



X 


h 


X 


J4 


J5 


J6 


X 


Jl 


h 



7 8 9 



13 



17 



X 


Jl 


X 




J4 


J5 


J6 


X 


h 


h 



4 7 8 9 14 

Figure 3.10. Optimal schedule and best SPT schedule. 

A number of dominance properties have been suggested for the 1 / r^ / S Cy. We have 
modified the properties of Dessouky and Dcogun (1981) for use in our search. We make the 
assumption here that the class setups satisfy the triangle inequality: s^^. ^s^ + Sfj^ for all G^, 
G[j, Gf.. 



18 



128 

Suppose Uial we are al a node in ihc search tree wiih a partial schedule o that ends al lime t 
with a job in class G^ and a set K of unscheduled jobs. If 7. is in K and in Gfj, define the 
following earliest start time: 

f. = max {t + s^-ij.rj}. 

Note that if r + j^.^ < r.-, the necessary class setup can be completed before the job arrives. 
At this node we can use any of the following dominance properties: 

Property 3.1. Let J,- be the shortest job in K. UJj is in G^ and 7,- is in G^, the node (a, Jj) 
is dominated by (a, J^) iff,-*- s^ < t:. 

Property 3.2. The node (o, 7.) is dominated by (o, J^) if /,• + p,- + s^ < rj. 

Property 3.3. If 7.- is in G^ and 7, is in G^, the node (o, JJ) is dominated by (a, 7,) if all of 
the following statements arc true: 

(a) ti + Pi < tj + pj, 

(b) f J + Pi + s^g < tj + Pj + Sfjg for all job classes Gg-.G^nK^ [}, 

(c) s^Ij + Pj < SgQ + pi for all Gg : G^ n /c: ?i { ) , and 

(d) Sgij + pj + Sfyfi < Sgg + p^- + 5^ for all Gg : Gg n ^ ?t ( } , and G^ : G^ n a: ?t { } . 
Proofs: Property 3.1. Take any schedule (o, 7.-, ai,7j, 02), where there are m jobs in Oj. 

If we move Jj before 7.-, the new completion time of 7^- is no greater than the old completion time 
of 7;; thus the flowiime of 7,- is decreased by at least {m + l)p,- (since Jj is the shortest job). 
Meanwhile, we delay only the start of 7; and the m jobs in Oj by at most/?,- (since ?/ + p, + s^ - 
tj < Pi). The jobs in aj are not delayed at all (the triangle inequality of the setups insures this). 

Property 3.2. Take any schedule (a, Jj, O] , 7,-, 02). We can move 7,- before Jj without 
delaying 7,-, decreasing the flowtime of 7^ and possibly that of the jobs in 02- 

Property 3.3. Take any schedule (o, Jj, O] , 7,, 02). Note that the earliest start times of 7, 
and Jj are before Oj . Interchange 7,- and Jj. The new completion time for 7,- is not greater the old 
completion time of 7.- (by condition a). By condition b (if the first job of O] is in Gg), the jobs in 
0| are not delayed. Then, by condition c (if the last job of O] is in G^), the new completion time 



129 

fori, is not greater than the old completion time ofy^-. Finally, tlic last condition (if the first job 
of 02 is in Gj) implies that no jobs in 02 are delayed. 

In any of these cases, we can take a schedule that starts with (o, 7.) and find a schedule 
which starts with (.a, 7,) and which has less total fiowtime. Thus, it is clear that the first node is 
dominated and that we do not need to search that part of the tree. 

Lower bound . A branch-and-bound procedure needs a lower bound. A good lower bound 
is important to efficiently finding solutions. We develop two bounds: the first concentrates on the 
release dates, the second on the setup times. 

The first lower bound for a node completely ignores the class setups. Instead, it solves the 
associated 1 / r.-, preemption / X C. problem with the SRPT rule and adds the optimal fiowtime to 
that of the partial schedule in the node. 

The second lower bound separates the setup times from the job processing times. We 
assume that each class will have exactly one remaining setup. If we further assume that this setup 
wiU the shortest possible, then we can easily sequence the job classes to minimize the 
contribution of the setup times to the total fiowtime. The unscheduled jobs are scheduled by SPT 
without regard to their release dates. The two sums are added to the fiowtime of the partial 
schedule in the node. 

The first lower bound should work well when the interarrival times are large, and the 
second bound should be useful at nodes where all of the unscheduled jobs are available. 

Testing . For 30-job problems, the branch-and-bound procedure required excessive 
computation time to find an optimal. Still, improved lower bounds could be found by truncating 
the branch-and-bound search in the following way: We prevent the search from moving below a 
certain depth in the tree and take the lower bound at this depth as the objective function value. If 
we continue to do this, the truncated search returns the lowest lower bound at this depth. This 
will be a lower bound on the optimal solution and will be better than the lower bound computed 
at the root node. 



130 

Dispatching rules . The SPT rule is known lo minimize the total flowiime for 1 / / Z C: 
(Smith. 1956). Since we are studying a total llowtime problem, we are most interested in SPT- 
like heuristics. We will develop a rule that considers the waste associated with a job (the waste is 
the sum of the idle time and setup time incurred if the job is scheduled next). We propose the 
look-behind dispatching rule Shortest Waste. "Among the jobs with the minimum waste, schedule 
the shortest one." (This rule is similar to the Minimum Waste algorithm for CFTS.) 

Let us define a few relevant variables: t is the current time, the completion of the last 
scheduled job; G^, is the class of the last scheduled job, and the waste of an unscheduled job J: in 
G^is 

Wj = max {r.- t,s^fy]. 

Our dispatching rule can be now stated: 

Shortest Waste: 

Among all unscheduled J;, select the job with the minimum wj. Break any ties 
by selecting the one with the minimum pj. 

Decomposition . For the FTSRD problem, we decided lo implement a search heuristic for 
comparison purposes. A decomposition heuristic for finding good solutions to sequencing 
problems was introduced by Chambers et al. (1992). The heuristic is a type of local search. It 
begins with an initial sequence, and forms new sequences until it finds a local minimum. The 
critical step is the decomposition of the problem into subproblems that depend upon the current 
solution. A new solution is generated by combining the optimal or near-optimal solutions to each 
subproblem. The heuristic thus makes very good moves through the search space; only a few 
moves are needed before convergence is reached. 

Consider, for example, a 12-job problem. Start with some initial solution to the problem. 
Select the first six jobs of this solution and find a good solution to the 6-job subproblem. Take 
the first three jobs (in order) of this subproblem solution as the first three jobs of the new 
solution. Then combine the remaining three jobs from the subproblem and with the next three 



131 

jobs from the initial solution. This forms a new 6-job subproblem. Continue solving 
subproblems and building the new solution until all of the jobs have been considered. 

We use this technique in order to fmd good solutions against which we could measure the 
performance of our other heuristics. (We did not feel that this type of search would be as 
effective on deadline-oriented CFTS and CSRDD problems.) We use a branch-and-bound 
technique with an approximate dominance property to generate near-optimal solutions to the 
subproblems. The algorithm has two parameters. We need to select m as the size of the 
subproblems which we will solve; the larger the value, the better our subproblem solutions will 
be (at the expense of computation time). We also select/as the number of jobs from the 
subproblem solution that will be fixed into the new solution. A smaller/ requires that more 
subproblems be solved per step. The following steps outline the procedure. 

Stepl. Set m and/. (We want/ to divide «- m.) Let o be the ERD schedule. 

Step 2. Take the first m jobs of a. Let rt be an empty schedule. 

Step 3. Solve the m-job subproblem by branch-and-bound. 

Step 4. Append the first /jobs of the solution to k. 

Step 5. If there are any unconsidered jobs in o, take the next /jobs from o, add to the 

m -/remaining from the subproblem, and go to Step 3; else go to Step 6. 

Step 6. Append the m -/remaining jobs of the solution to n. If n is a better schedule 

than o, let o = 7C and return to Step 2; else go to Step 7. 

Step 7. The solution found by the heuristic is o. 

We experimented with different values of (m.f). The best results (in terms of computation 
time and solution quality) were achieved with (9, 3) and (15, 5). We used our branch-and-bound 
algorithm with only the second lower bound and only the following approximate dominance 
property: 

Property 3.4. Given a partial schedule o, (o, J[) dominates (o. Jj) if 7/ and Jj are in the same 
class, /j is the shortest unscheduled job in that class, and w,- < Wj. 

This property is a simple extension of a previously considered dominance rule (see, for 
instance, Dessouky and Deogun, 1981). Unlike the dominance rules that we use in the full 



132 

branch-and-bound procedure, it has the advantage of being quick to check, since there arc fewer 
unscheduled jobs from the same class. 

In the section on computational results, we will discuss how well the decomposition 
heuristic performs. 

A problem space genetic algorithm . In this problem, we consider the problem space 
defined over the problem release dates. A point in this space is an n-element vector of non- 
negative real numbers. When a heuristic is applied to an instance of FTSRD, it uses the actual 
release dates to generate a solution. If, however, we adjust the release dates of the problem, we 
can change the sequence created by the heuristic. This sequence can be evaluated as a schedule 
by using the actual problem data. We can associate, therefore, with the vector of adjusted release 
dates a performance value: the total fiowtime of the schedule that was created. Moreover, we can 
search the space of adjusted release dates to find good schedules. This exploration is the 
objective of the problem space genetic algorithm. Our purpose is to show that the performance of 
a simple heuristic can be improved with a smart-and-lucky search like a genetic algorithm. 

We will use the Shortest Waste heuristic to convert a vector of adjusted release dates into a 
sequence of jobs. The optimal solution is within the range of this heuristic: if each adjusted 
release date equals the actual start time of the job in an optimal solution, the Shortest Waste 
heuristic will schedule the jobs in the optimal order, since at any time, the job with the shortest 
waste will be the one with the next adjusted release date, which is the job with the next optimal 
start time. 

As we did for CFTS and CSRDD, we will use a steady-state genetic algorithm. The initial 
population is formed by mutating a source individual that is the digital representation of the 
actual release dates. After empirical testing on a number of problem instances, we decided on the 
following parameters: The population size is 100 individuals. The four operators arc uniform 
crossover, one-point crossover, small mutation, and large mutation; all have the same probability 
of being selected. In the small mutation, a bit is Hipped with 2% probability; in the large, the 
probability increases to 50%. The algorithm uses tournament selection to identify parents. See 



133 

Davis (1991) or Goldberg (1989) for more infomialion aboul these aspects of the genetic 
algorithm. 

Example 3.7. The following problem is used to illustrate some of the issues we have 
discussed so far. 



■'y 



1 





5 


1 


2 





4 


2 


3 


5 


5 


2 


4 


6 


2 


1 



501='y02= 1- •«12= 1- •^21= 4. 

The ERD sequence is [7] J 2 ^ ^4], with a total flowtime of 55. The EFT sequence is 
[72 73 74 7,], with a total flowtime of 52. The Shortest Waste sequence is identical in this case. If 
we adjust the release dates to (1,2, 5, 6), the Shortest Waste sequence is [7, J4J2J3]' with a 
flowtime of 45. 

In the branch-and-bound algorithm, we compute lower bounds at the root node. The first 
lower bound for the entire problem is the SRPT schedule, total flowtime of 39, shown below (7, 
is preempted at time 6 by 74): 



h 


h 


J4 


h 


h 



4 6 8 11 16 

Figure 3.11. The SRPT schedule. 

The second lower bound (Longest Weighted Batch Size plus SPT) is computed as follows: 

Batch sizes: 6) = 2. ^2 = 2. 

Shortest setups: Si = 5oi = 1. ^2 = ^02= 1- 

I.9,B,= 1(4)+1(2) = 6. 

Processing times in SPT order: 2, 4, 5, 5. 

Completion times: 2, 6, 1 1, 16. X C'. = 35. 

Lower bound = 35 + 6 = 41. 



134 



3.4.5 Empirical Testing 

Problem generation . In order to test the heuri.slics, four sets of ten problems were created. 
The characteristics of the sets arc shown below (processing, interarrival, and setup times 
randomly selected from uniform distributions with the given ranges): 

Table 3.20. Data on problem sets 

Set Problems Jobs Qasscs Processing Interarrival Setup 

Times Times Times 

FTISI 10 15 5 1,20 1,10 0,9 

FT301 10 30 5 1,20 1,15 0,9 

FT302 10 30 10 1,20 1,15 5,9 

FT304 10 30 10 1,15 1,20 5,9 

Results . In this section we will discuss how well our solution techniques performed. (See 
Table 3.21 .) The branch-and-bound could find optimal solutions on only the 15-job problems. 
On the 30-job problems, we used the decomposition heuristic with parameters (9, 3) to quickly 
generate solutions and measured the performance of other heuristics against these solutions. The 
(15, 5) decomposition was much slower than the (9, 3) decomposition, since the time necessary to 
solve each subproblem grew exponentially. Still, it found slightly better solutions, and the 
processing time was reasonable (although it varied from problem to problem) if the heuristic 
dominance property and second lower bound were used. 

Table 3.21. Performance of heuristics. 

Problem Shortest (9,3) (15,5) Genetic 

Set Waste Algorithm 

FT151 1.095 1.005 - 1.010 

FT301 1.067 1.000 0.992 1.006 

Fr302 1.066 1.000 0.995 1.005 

FT3(M 1.031 1.000 0.994 1.005 

Notes: Performance measured against optimal solution for FT151. Against decomposition 
(9,3) for 30-job problems. All performances are average ratios over 10 problems. 
Performance of genetic algorithms averaged over three runs of 30(X) individuals. 



135 

Although the initial lower bounds for the 30-job problems were not good, we were able lo 
improve them using the branch-and-bound tree lo show that the decomposition (9, 3) heuristic 
was within ten percent of the optimal flowtimc. 

The Shortest Waste heuristic found good solutions very quickly and generally performed 
better than other dispatching rules. On the 15-job problems, the genetic algorithm was not an 
effective heuristic, since it required more compulation time than the branch-and-bound and could 
not always find optimal solutions. 

On the 30-job problems, the problem space genetic algorithm found solutions better than 
Shortest Waste and as good as the decomposition heuristic. The computation time was slightly 
longer for a 3000-individual search than for a (15, 5) decomposition, but a 1000-individual search 
was much shorter and found solutions with little increase in total flowtime. The exponential 
nature of genetic search is exhibited in Figure 3. 12. (In other testing, we found that the genetic 
algorithm was not as effective when using a simple Earliest Release Date rule to create 
sequences). 

All programs were run on a 386 PC. Decreases in times were achieved when the programs 
were run on a 486 PC, and further decreases could be achieved on a more powerful machine. 
Except for the 30-job branch-and-bound (which we could not solve), we do not consider 
processing times to be a significant obstacle. The numbers in Table 3.22 are offered only for 
comparison puiposes. 



Table 3.22. Typical computation times 

FT302.1 

Decomposition (9,3): 17.8 seconds 
Decomposition (15.5): 338.67 seconds 
1000-individual G A: 134.62 seconds 
3000-individual GA: 350.37 seconds 
Shortest Waste: < 0.1 seconds 

FT151.1 

Branch-and-bound: 10.71 seconds 
Decomposition (9,3): 0.8 seconds 
3000-individual GA: 149.24 seconds 
Shortest Waste: < 0.1 seconds 



136 



1.07 




500 



1000 1500 2000 

Number of New Individuals 



3000 



Figure 3.12. Performance of Shortest Waste Genetic Algoritlim 
Performance measured against decomposition (9,3). 



3.4.6 Special Case 



In this section we consider a particular special case of the problem which may be useful in 
certain manufacturing situations. We will assume that there exist exactly two job classes and that 
the job processing times are equal within each class. 

Specifically, we study the following instance: p.- = p for all J: in Gj, p: = q for all J: in Gi- 
Since all of the jobs in a class have identical processing times, we may order them by ERD. We 
note here that all of the release times are integer. 

We will describe a pseudo-polynomial dynamic program to solve the problem, a spjccial 
case of the strongly NfP-complete FTSRD problem. 



137 

Dynamic programming . Wc can use a dynamic program for iwo reasons: there arc only 
two classes, and we have an ordering for the jobs in each class. According to Monma and Potts 
(1989), this ordered batch scheduling problem can be solved in pseudo-polynomial time. The 
following dynamic program interleaves the classes. The state variable in the dynamic program 
corresponds to a partial schedule that consists of the first j'l jobs from G] and the first iiSoh?, from 
Gi and that ends before or at a specific time with a job from a specific class (if it is cheaper to end 
sooner, that schedule should take precedence). At each point in the state space, we will measure 
the total fiowtime of the scheduled jobs. The recursion determines the best partial schedule to 
which we should add the specified job. 

Algorithm 3.3. Lety(f, a, /], i^) be the minimum fiowtime of a partial schedule where the 
last jobs ends at or before time r, there are tj jobs from G) and J2 jobs from G2, and the last 

scheduled job is from G^. f = R. a = 1, 2. /, = «,, /j = 0, . . . , ^2- Renumber the 

jobs so that y<«, ify.isinGi, r, < . . . < r^,, andy'>/ii if/.- is in G2, rn,+, < . . . < r^. /? is some 
upper bound on the makespan of a schedule. We can find one such R by scheduling all jobs in 
ERD order, performing a class setup in front of every job. We also have an upper bound: R < 
max [rj] + 'Lpj + «! S21 + «2 ■^12- 

Initialization: 

/(r,a,/„/2) = °°iff<0. 

fit, 1, 0, 12) = °° for all t and for ij > 0. 

jit, 2, /j, 0) = °° for all t and for /j > 0. 

y(r, 1, 1,0) = °° for f< max {sq^, rA + p, if/.isthe first job in Gj (j=l). 

fit, 1, 1,0) = max {5oi,r } +pforf >max {%, ry} -i-p, ifjy is the first job inG, 0= !)• 

fit, 2, 0, 1) = °° for t < max {502. ''/} + (}< >f •{/ is the first job in G2 (/ = "i + !)• 

fit, 2, 0, 1) = max {^02. rj) + <? for r > max { jqj' '}} + ?• ^^Jj 's the first job in G2 0' = «i + !)■ 

Iteration: (j, + /2> 

fit, l.i,,j2) = min Uit-p, I, iyl, 12) + t,At-p-S2i,2, ir\, k) + t,Ai-^, 1. J,, J2)) iff>')+p, 

where) = /i. 

fit, 1, /,, ^2) = °°\i t<rj + p, where) = /,. 



138 



fit. 2. J,, /j) = min [/{i-q. 2. <,. /j-l) + t,At-q-S\i, 1. /i. /2-0 + './('-L 2. ii. h)) iit^rj + q, 

where 7 - n^ + 12. 

fit, 2, /,, 12) = °° if r < r. + </, where 7 = /i] + /2- 

Ans>ver: the optimal total flowtime is min [/(/?, \, n^, n^,/iR, 2, /i], n2)]. 





Jk 


Jj 




t-p 






h 


S21 


Jj 




1-P-S21 


t 




^j 







t-l I 

Figure 3.13. Schedules for iteration (J.- and /^ in G] and /,• in G2). 

In the iteration, the first term being considered for f{t, 1, Jj, /2) is the total flowtime of the 
partial schedule formed by adding the J: (J = /]) to a schedule ending at or before t-p with a job in 
Gj. The second term is the flowtime if 7. is added to a schedule ending at or before t-p-S2\ with a 
job in G2. The third term corresponds to a schedule that ends at or before t- 1 with /:. If r < r .- + /?, 
there is no feasible schedule that ends with /.•; thus,y(r, 1, Jj, 12) is set to infinity. The iteration is 
similar for \hej{t, 2, /], j^)- 

The effort for each point in the state space is constant. The effort for the entire program is 
thus proportional to the number of points in the state space. This is O(Rn^). Since R is bounded 
by a polynomial function of the problem data, the algorithm is pseudo-polynomial. The dynamic 
program can be implemented to find the optimal objective function value with memory 
requirements that are 0(Rn): If we are determining the values for points with /, + /2 = *- any 
points in the space where jj + i2<k- 1 are ignored. If we define /^(r, a, /[) =J{t, a, i^, k - ii), we 
need to keep only/^ and/^.] at any time. 



139 

Test problems . Wc generated 70 test problems in order to test the dynamic program on a 
range of problem sizes. The data for the problem sets are summarized in Table 3.23 (10 problems 
in each set). 



Table 3.23. Data about problem sets for special case. 



Problem 
Set 

FT201 
FT307 
FT308 
FT309 
FT401 
FT507 
FT601 



Number 
of jobs 

20 
30 
30 
30 
40 
50 
60 



1 
1 
2 
4 
1 
1 
1 



Class 
setup 

1 
1 
1 
3 
1 
1 
1 



Interarrival 
times 

1-3 
1-3 

2-5 
4-8 
1-3 
1-3 
1-3 



Results of special case dynamic program . The dynamic program finds optimal solutions in 
time that is nearly proportional to Rrfi (see Table 3.24). 

One drawback of the dynamic program is the amount of memory required to perform the 
algorithm; we were able to solve only 60-job problems. In addition, it requires significant 
processing time on a 386 personal computer. These problems can be overcome, however, since a 
larger computer could handle more memory (the amount required is 0(y?n)), and would run more 
quickly. 



Table 3.24. Results of dynamic program 



Problem 


Number 


Average 


Average 


Set 


of jobs 


R 


computation time 


FT201 


20 


41.1 


0.808 


FT307 


30 


61.4 


2.270 


FT308 


30 


108.1 


3.487 


1-1309 


30 


185.5 


5.899 


F1401 


40 


81.8 


4.698 


FT507 


50 


101.6 


9.079 


K1601 


60 


121.4 


14.836 



140 

Extensions of special case . The dynamic program can be modi Tied lo solve any FTSRD 
problem where there exists* a natural order for the jobs within each class. This includes problems 
where the jobs in each class have the same processing time (as we have discussed) or problems 
where all of the jobs have the same release date (order the jobs in each class by SPT). In any of 
these cases we have an ordered batch scheduling problem. If each class has a natural order, the 
dynamic program can be used to interleave these sequences since we have an ordered batch 
scheduling problem. 

Recall from the example presented in Section 3.4.4 that matching processing times and 
release dates do not give us a natural order for a class. 

3.4.7 Conclusions 

In this research we have studied a computationally difficult class scheduling problem. The 
objective is to minimize the total flowtime of a set of jobs that have non-zero release dates. We 
examined a number of techniques to solve the problem, including a branch-and-bound search, 
look-behind dispatching rules, a decomposition heuristic, and a problem space genetic algorithm. 
We were interested in determining how this type of genetic algorithm can be used to find good 
solutions for another class scheduling problem. 

Our results are as follows: While we did develop lower bounds and a number of 
dominance properties, our branch-and-bound approach was unable to solve any 30-job problems. 
The decomposition heuristic was a successful technique, locating solutions of high quality. The 
Shorest Waste heuristic could sometimes generate good solutions. However, by incorporating 
these rules in a genetic algorithm that searched the space of adjusted release dates, we could find 
much better solutions. 

From these results we can conclude two things: For the one-machine class scheduling 
problem we call FTSRD both the problem space genetic algorithm and the decomposition 
heuristic can find good solutions in reasonable time. Additionally, look-behind rules may be 



141 

useful for job shop scheduling, especially on a bottleneck machine which undergoes class setups 
and where jobs continue to arrive while the machine is processing. 

3.5 Chapter Summary 

In this chapter we have presented the results of research into three one-machine class 
scheduling problems. We can make a number of observations about this research. 1. None of 
these three problems have been previously considered in the literature. 2. We have presented 
analytical results and developed extended heuristics for each of these problems. 3. All three 
problems are motivated by the semiconductor test area job shop environment, and the extended 
heuristics developed for these problems may be useful as dispatching rules in the general job shop 
scheduling problem. 4. Our problem space genetic algorithm is a robust approach, able to find 
good solutions over a variety of one-machine class scheduling problems, and should be 
applicable to other difficult combinatorial and scheduling problems. 



CHAPTER 4 
LOOK-AHEAD SCHEDULING PROBLEMS 



In this chapter we discuss the second major area of this research. We study the problem of 
scheduling a machine that processes jobs headed for two different second-stage machines. We 
analyze this three-machine problem with three different objective functions: makespan, total 
flowtime, and number of tardy jobs. We first examine the complexity of the problem and then 
identify some lower bounds as well as some special cases that can be solved in polynomial time. 
We develop a number of heuristics that find good solutions to the problem. We also use a 
branch-and-bound technique to find optimal solutions. 

4.1 Introduction 

Job shop scheduling includes those scheduling problems in which different jobs may follow 
different routes through the shop. These problems are generally the hardest to solve optimally, 
since few properties of optimal schedules are known and the number of possible solutions 
explodes as the problems increase in size. 

Because of the complexity of job shop scheduling, algorithms to find the optimal solution 
(in a reasonable amount of lime) for even the simplest objective functions, e.g. makespan, do not 
exist. Recent research has shown that bottleneck-based techniques such as the shifting bottleneck 
algorithm (Adams, Balas, and Zawack, 1988) or bottleneck dynamics (see Morton, 1992, for 
example) can be successful at finding good schedules. Traditionally, however, researchers have 
studied (and schedulers have used) dispatching rules to order the jobs waiting for processing at a 
machine. 

Normal dispatching rules consider only the jobs currently in the queue for the machine 
being scheduled. Wc define look-ahead scheduling as the ability of a sequencing procedure to 

142 



143 

include information about the status of machines downstream in the flow, enabling it to make a 
better solution. Previous techniques that use this look-ahead idea include the work-in-next-qucue 
and numbcr-in-next-queue dispatching rules (Panwalker and Iskandcr, 1977) and the use of 
bottleneck starvation avoidance in shop floor control by Glasscy and Pctrakian (1989). Robinson 
et al. (1993) consider upstream and downstream information in scheduling semiconductor batch 
operations. Researchers have also studied lot release policies that look ahead to the status of the 
inventory in front of or arriving at a bottleneck; see for example, Wein (1988), Glasscy and 
Resende (1988), and Leachman, Solorzano, and Glassey (1988). Other researchers have studied 
procedures that they called look-ahead scheduling (Koulamas and Smith, 1988; Zeestraten, 1990) 
but the problem setting or interpretation is different. 

Consider two examples from the semiconductor test area. In the first, lots of two different 
products are processed through the same brand workstation. After brand, the lots require 
electrical testing, but the differences between the products indicate that the lots must be tested on 
different machines. Or consider the effect of re-entrant flows. The various lots waiting for 
processing at an electrical test workstation may be at one of two points in their route. At one 
point, a lots moves to brand after being tested (and it will return to test at some point in the 
future). At another, it moves to visual/mechanical inspection. In the first case, the brand 
workstation is sending lots to two different testers; in the second, the tester is sending lots to two 
dissimilar workstations. If one of the second-stage machines is a bottleneck, it seems clear that 
the sequencing of lots on the first-stage machine should try to maximize the efficient use of that 
bottleneck. 

We can model this scenario with the following three-machine problem: There are three 
machines Mq, M,, and Mj. Each job follows one of two different flows: Mq - Mj, or Mq - M2. 
Thus, Mq is feeding the other two machines. If one of these second-stage machines is a 
bottleneck because the total work required on that machine is the larger than that on the other 
machine, the sequencing of jobs on Mq should have as a priority the proper feeding of that 



144 

machine. This idea of a txMlleneck will nol affect our analysis of the problem. Wc will, however, 
return to it for the heuristics and the empirical testing. 

This problem, which could occur in any number of manufacturing environments, forms an 
interesting general tlow shop problem and a subproblem of the job shop scheduling problem. As 
a flow shop problem, it is a simple model unlike the multi-machine problems previously 
discussed in the literature, although work has been done on flexible flow shops with multiple 
parallel machines at any given stage. 

Moreover, the research into our three-machine problem may impix)ve job shop scheduling 
in two ways: one, the solution procedures can be applied directly to the subproblem of scheduling 
machines near the bottleneck machine, and two, these techniques may be translated into good 
look-ahead dispatching rules for scheduling throughout the shop. 

In this chapter we investigate three objective functions for this problem: the minimization 
of makespan, of total flowtime, and of the number of tardy jobs. We are concerned with the 
analysis of solutions to the problem and the development of heuristics which can be used to find 
good solutions. 

The major contributions of this work include the proof that minimizing makespan is a 
strongly NP-complete problem, the identification of optimality properties and special cases that 
can be solved in polynomial time, and the development of an approximation algorithm. 

The look-ahead scheduling problems under investigation are as follows (using the 
numbering given earlier): 

4. Three-Machine Look-Ahead Scheduling: Makespan (3MLA-MS) 

5. Three-Machine Look-Ahead Scheduling: Flowtime (3MLA-FT) 

6. Three-Machine Look-Ahead Scheduling: Number of Tardy Jobs (3MNT) 

In this chapter we will look at each of these objective functions. In Chapter 2 we discussed 
the research relevant to these problems. In the next section we start with the makespan objective. 
In Section 4.3 we look at minimizing the total flowtime, and Section 4.4 discusses work on 
minimizing the number of tardy jobs. 



145 

4.2 Minimi/in^ ihc Makcspan 

As mcniioncd in ihc iniroduclion, wc arc studying a problem that is a subproblcm of the 
general job shop scheduling problem and is also a special case of the general flow shop problem. 
All analysis of the flow shop starts with Johnson (1954), who studied the minimization of 
makespan for two-machine flow shop problems and for some special three-machine flow shop 
problems. His famous algorithm starts jobs with the smallest first-stage tasks as soon as possible 
and jobs with the smallest second-stage tasks as late as possible. 

Special cases of the flow shop makespan problem have been studied by a number of 
researchers, including Mitten (1958), Conway, Maxwell, and Miller (1967), Bums and Rooker 
(1975), and Szwarc (1977). Garey, Johnson, and Sethi (1976) proved that the general three- 
machine problem was NP-complcte. Problems with release dates, preemption, precedence 
constraints, or more than three machines have also been studied. 

In the flexible flow shop, more than one machine may be present at a particular stage. 
Heuristics for this type of problem are discussed by Wittrock (1988), Sriskandarajah and Sethi 
(1989), Gupta (1988), and Gupta and Tunc (1991). Lee, Cheng, and Lin (1992) study an 
assembly flow shop problem where each job consists of two subas.sembly tasks that are 
assembled in a third operation. 

This three-machine problem is therefore closely related to problems previously studied, but 
the pre-assignment of the jobs to different second-stage machines gives this problem a special 
structure and leads to interesting results. 

4.2.1 Notation 

The following list describes the components of the problem and the notation used. 



146 

/; iobj,j= 1, .... /I. 

Mo The first-stage machine. 

M], M2 The second-stage machines. 

W] The set of jobs tliat visit Mq and then Mp 

H2 The set of jobs that visit Mq and then M2. 

Pqj The first-stage processing time of 7. on Mq. 

Plj The second-stage processing time of 7. on Mj, / = 1 or 2. 

For a given schedule o, we can calculate the following variables: 

Cqj The completion time of 7. on Mq. 

Cy The completion time of 7.- on Mj, / = 1 or 2. 

Cj = Cy, the second-stage completion time of 7.-. 

Cmax = "13" {Cj}' the makespan of the schedule. 

Z Cj the total flowtimc of the schedule. 

Note that we will call a set of jobs that visit the same second-stage machine a group; thus. 
Hi and H2 are each a group of jobs. Each group has a flow. The flow for the jobs in Hy is Mq - 
M]. The flow for the jobs in H2 is Mq - M2. This section is concerned with the problem of 
minimizing, over all feasible schedules, the makespan of the jobs. We call this problem the 
Three-Machine Look-Ahead problem - Makespan (3MLA-MS). 

4.2.2 Johnson's Algorithm 

If we consider just one group and its corresponding flow, the problem of minimizing the 
makespan of the set of jobs that visit these two machines is the same as Johnson's two-machine 
flow shop problem. Johnson (1954) provided an oplimality rule and an algorithm to solve the 
problem. If each job to be scheduled has task processing times a . and b: on machines one and 
two respectively, then his rule is as follows: 

Johnson's Rule: 7, precedes 7; in an optimal sequence if min {a,, b:] < min {a.-, ft,}. 

This rule is implemented in the following algorithm: 

Johnson's Algorithm: 

Step 1. Find the smallest unscheduled task processing time. (Break ties arbitrarily.) 



147 

Step 2. If this minimum is on the llrsl machine, place ihe job in the first open position in 
the schedule. Else, place the job in the last open position in the schedule. Return to Step 1 . 

4.2.3 Permutation Schedules 

In flow shop scheduling, a feasible schedule is called a permutation schedule if the 
sequence of jobs on each machine is the same. Thus, the sequence of jobs on the first machine 
uniquely identifies a schedule (assuming all tasks arc started as soon as possible). In the three- 
machine look-ahead problem that we are studying, the two sequences on the second-stage 
machines consist form two disjoint sets of jobs. Thus, for our problem, we extend the idea of 
permutation schedules to include schedules where the relative order of two jobs in the same flow 
is the same at both stages. 

It is known that considering permutation schedules is sufficient for finding optimal 
solutions for regular two-machine flow shop problems. Thus, for our three-machine look-ahead 
problems, it seems likely that permutation schedules will also be sufficient, since the problem 
contains two two-machine flows. We will show that this is indeed true. 

Definition: A schedule is a permutation schedule if, for all J: and 7,- in //, (H-^), Ji precedes 
Jj on Mq if and only if 7,- precedes J: on M] (M^). 

Theorem 4.1. For any regular performance measure, there exists a permutation schedule 
that is an optimal schedule. 

Proof. First we will show that we can interchange two jobs that are not in the same order at 
both stages. Given a schedule a where job J: directly follows 7,- on machine M, (or M2) but Jj 
precedes 7,- on machine Mq, move the Mq task of 7y after the Mq task of 7,. 

If we look at Figure 4. 1 , we can observe that moving ./.- causes all of the tasks (except Jj) on 
Mq to start earlier, which docs not delay any (and may expedite some) second-stage tasks. Now, 
since 7,- will complete on Mq when 7, did {C'qj = Cqi), the processing of 7y on M, will not be 
delayed. Our interchange, therefore, does not increase the completion time of any job. 



148 

Thus, for any given schedule, wc can create a corresponding pcrmulalion schedule by 
interchanging the first-stage tasks. None of the job completion times are increased by this 
construction. Indeed, some of the completion times may be decreased. Therefore, this 
permutation schedule has a better or equal performance on all regular measures (e.g. makespan, 
flowiime, number of tardy jobs, maximum lateness). Thus, it is sufficient to consider 
permutation schedules when trying to minimize these objective functions. QED. 







coj 






Coi 








^J 


Jb 


Jm 




h 












Jb 


Jm 




h 


Jj 





Cli Cij 







c 


Ob 






C 


Oi 


C 


Oj 








Jb 


Jm 




J. 


Jj 










Jb 


Jm 




h 


Jj 





lb 



C'li C'lj 



Figure 4,1. The exchange into a permutation schedule for Mq and M,. 
(Machine M2 not shown.) 



We would note here that a permutation schedule preserves the relative order of the 
sequence for each group. We will use the term interleaving for the process of combining two 
sequences to form a pennutation schedule. We will show in Section 4.2.5 that if we are given 
sequences for each group, then there is a polynomial-lime algorithm to find the interleaving that 
minimizes the makespan of the schedule created. However, the optimal second-stage sequences 
cannot be dctenmincd in polynomial time. In fact, the 3MLA-MS problem is strongly NP- 
complete, as will see in the next section. 



149 



4.2.4 NP-Complctcncss 

In this section, wc consider the complexity of the 3MLA-MS problem. Although other 
researchers (including Gonzalez and Sahni, 1978) have shown the NP-complclcness of a number 
of small shop problems, we cannot determine the complexity of our problem from any of this 
previous work. 

We will therefore prove that 3MLA-MS is strongly NP-completc, which will be done by 
transforming 3-Parlition to 3MLA-MS. (Recall that it is sufficient to consider permutation 
schedules.) The 3-Parlition problem can be stated as follows: Given a set of a,, j = 1, . . . , 3«, 
and B, partition these elements into n sets y4,, . . . , -4„, where each set contains three elements and 
the sum of the three elements equals B. We will make the assumption that for all /, 
1/4 B<ai< 1/2 B. (We can transform any problem without this property into one where it is 
true.) With this property, there will never be a set of two a,- or a set of four a,- where the sum of 
the elements equals B. 
Theorem 4.2. 3MLA-MS is a strongly NP-complete problem. 

Proof. Given an instance of 3-Partition, with a set of a,-, / = 1 3/j, and B (note all a^ > 1), 

create 4« jobs, 3n of which go from Mq to Mj and have processing times pQi = a,- and P2j = 
(S+l)a,-, J = 1 , . . . , 3rt; let these jobs form a set W. The n remaining jobs that go from Mq to M,, 
•^3/1+1' •^3n+2' • • ■ ' Un-POk = ^^ fo"" ^^ * ^nd pj/, - {B+\)B, ^ = 3ai, .... 4n-l, and p; 4„ = B; 
let these jobs form a set X. The desired makespan is M = n(B^ + B) + B. 

Part 1. If there exists a partition (/I, A„) such that for all a,- in A/^, I a,- = B, then the 

sequence on Mq of [-4 iJjn+X ^2 ^Sn+l ■■'^n Un^ ^''^ y'^^'^^ ^ schedule where the completion 
time on M, will be M and the time on Mj will be no greater than M. (See Figure 4.2.) 

Part 2. Now, suppose there exists no partition. Consider any arbitrary permutation 
schedule a. The sequence is composed of consecutive subsets of jobs from W and of jobs from 

X. LetAy.y = 1. n+1 be these subsets of W, where Aj directly precedes theylh job from X, 

except for/\„+i, which is the set of jobs following the last job from X. Note that any of these Aj 



150 



may be cmply. Let S: equal the sum of the firsl-slagc task processing times for the jobs in A:. Let 
Aj^ be the first A: such that 5^ is not equal to B. Because there is no partition, there must exist one 
such i4^ among y4i /\„. 

If S^ > B, then the makespan on machine M] is delayed by the delay in the /ih job inX: 
MS(M,) > S, + B- + . . . + S^ + fi"2 + (n - k){B^ + B) + B > kB + kB^ + (n - k.){B^ + B) + B = M. 
(This assumes that all of the first k-\ jobs have long tasks on M,, leaving n-\-(k-\) long tasks and 
one shon task on M , . if one of the first k- 1 has the short task, then the makespan is even longer.) 

If S^ < B, let S = Si + . . . + S^ < A:B (and < kB - 1) and suppose 7^ is the first job from W 
after the /tth job from X. Then, the makespan on Mj is postponed by 7^: MS(M2) ^ 5 + kB'^ + a^^ 
+ (B + \){nB - S)>S + kB^ + a^ + nB^ + nB - BS - S. Including -BS > -kS^ + B implies MS(M2) 
> a^ + nB^ + nB + B>M. Thus, there exists no schedule with makespan less than or equal to A/. 

Part 1 and Part 2 of the proof show that there exists a partition if and only if there exists a 
schedule with the desired makespan. This implies that 3MLA-MS is a strongly NP-complete 
problem. QED. 



Mr 



Ml 



M^ 



Al 




A2 










^n-l 




^n 






B 


b2 


B 


b2 




B 


b2 


B 


b2 








B^+B 


B^+B 




b2 + B 


B 




b2 + B 


B^+B 




b2+B 


b2 + B 



Figure 4.2. A schedule for the 3MLA-MS problem. 



4.2.5 Makespan Optimalitv Conditions and Polynomiallv-So lvablc Ca.ses 

This section discusses the optimal combination of two given sequences, lists a few 
properties of opfimal schedules, and presents two special ca.ses that have easily-found optimal 
solutions. We will see that we can easily form a permutation schedule by optimally interleaving 



151 



sequences for each group (Algorithm 4.1). Properties 4.1, 4.2. and 4.3 arc dominance properties 
between jobs in the same group. Theorems 4.3 and 4.4 describe the special cases. 

Because we need to consider only permutation schedules, we can create a single schedule 
for all three machines from a sequence of the jobs. That is, given a sequence on the first-stage 
machine we can create a sequence for each second-stage machine. This is done by considering 
the jobs in the order they appear on the first machine. However, there is no comprehensive rule 
for determining this sequence. Thus, we will spend some time on how this sequence should be 
constructed in certain situations. 

Interleaving two sequences . Since the problem is NP-complete in the strong sense, 
heuristic methods for finding good solutions are justified. A very natural heuristic is to schedule 
the jobs in each group separately. For instance, each group can be scheduled by Johnson's rule. 
Then we can interleave these two sequences to form a solution to the original problem. The 
process of combining two sequences to achieve the minimal makespan is called optimally 
interleaving. This is the best combination of these two sequences. Note, however, that the best 
combination of the two Johnson sequences may not be an optimal solution; the optimal solution 
may be some combination of sub-optimal solutions to each subproblem. In Section 4.2.9 we 
present an example where optimally interleaving the Johnson sequences for each group is not 
optimal. 

So, while interleaving the Johnson sequences is a natural heuristic that worics well (see 
Section 4.2.8), we may wish to try other heuristics to the subproblcms before interieaving. These 
are discussed in Section 4.2.7. In this subsection we will describe how two sequences should be 
interleaved. 

Now, suppose we are given two sequences c j and 02- one sequence for each group (we 
have found solutions for each of the subproblcms), and we want to find the minimal makespan 
that can be achieved by combining these two sequences. The following observations will lead us 
to an algorithm for doing so. 



1S2 

DcTinc C as a makcspan that wc wish lo achieve. To minimi/.c the makespan given the Iwo 
sequences we need to find the minimal C for which we can find a feasible schedule. Wc can 
schedule the tasks on the second-stage machines in the order given by O] and aj and as late as 
possible, so thai the last task on each machine ends at C. In a feasible schedule, the first-stage 
task for each job has to complete on Mq before the second-stage task can begin. We need to 
delcrmine if there is some ordering of the tasks on Mq so that each task finishes on-time (with 
respect the second-stage task). 

For each job J: the start time of the second-stage task can be used as the due date d.- for the 
corresponding first-stage task. We can find a sequence where each first-stage task finishes on- 
time (Cq: < dj) if and only if we can find a sequence where the maximum lateness is less than or 
equal to zero. If we wish to minimize the maximum lateness of the first-stage tasks, we should 
order them by HDD (Earliest Due Date), according to Jackson (1955). The schedule created is an 
interleaving of the two given schedules: if /^ precedes J: in a^, then d^ < dj, and /,■ will precede Jj 
on Mq. 

Each due date dj = C - r.-, where t: is the sum of the second-stage processing times of iy and 
the jobs Jfr that follow Jj on the second-stage machine. See Figure 4.3. 





JJ 



Jj 





Coj dj ^ tj -^ C 

Figure 4.3. The variables associated with Jj (second-stage started late). 
Note: Other second-stage machine not shown. 

Since the HDD sequence corresponds to sequencing the tasks in decreasing order of tj, the 

sequence of jobs is the same for all values of C, including the optimal one. Therefore, we can 

find the optimal makcspan from the feasible schedule with the jobs in this order and all tasks 

starting as soon as possible. This is the optimal interleaving of two given sequences, described in 

Algorithm 4.1. 



153 



Algorithm 4.1 (Optimal Interleaving): Given a sequence Oj for the jobs in //, and a 
sequence 02 for the jobs in H2, pcrfomi the following steps to yield a schedule with the minimal 
makespan: 

Step 1 . For each 7. in //,, define A: as the set of jobs (not including J J) that follow Jj in Oj. 
Then tj = pjj+'L^jPjl^. 

Step 2. For each 7. in Wj. define A: as the set of jobs (not including Jj) that follow Jj in 02- 

Thenry=/72y+lAyP2)t- 

Step 3. Schedule the jobs on Mq in decreasing order of the tj, starting at time zero, and start 

all second-stage tasks as soon as possible. 

Note that this algorithm takes 0(«) effort, since each group is already in decreasing order of 
the tj, and forming the schedule is only combining the two sequences without changing the 
relative orderings. 

In Example 4.1 we perform Algorithm 4.1 on a problem with five jobs and given sequences 
for each group. We are given sequences [JjJ^J2]2ind[ J 4 J^ ] for each group. After 
computing the f .-, we form the interleaved sequence [ Jj Jj J 4 J$J2^- ^*^ corresponding 
schedule has a makespan of 1 1 (see Figure 4.4). 

Example 4.1. Given the following five jobs and the two sequences [ 7/ JjJ2 1 and 



Jj Hi POj Pij \ 



'} 



Jl Hj 2 4 9 

h Hi 1 * ' 

J3 Hi 2 4 5 

J4 H2 2 1 4 

J5 H2 1 3 3 



154 



h 


h 


h 


h 


1 

J2 








h 


h 


h 








U 


h 









2 4 6 7 8 10 11 

Figure 4.4. Oplimal schedule for Example 4.1. 

Properties of optimal solutions . In general, we still do not know how to construct the 
sequences on M, and M2. These subproblems are what is difficult about this problem. Johnson's 
rule, which is optimal for the two-mchine flow shop, is not always applicable for the 3MLA-MS 
problem. Of some help, however, are a number of dominance properties for jobs in the same 
group that limit the number of sequences that need to be considered in searching for the optimal. 
The first property establishes a precedence relationship between two jobs that is a restrictive form 
of Johnson's rule. The other two relate two jobs that are processed consecutively on some 
machine. 

Property 4.1. (Absolute Dominance) If both J^ and Jj are in H^ and pq,- < pqj and 
Pkx - Pkr ^^" ^i s*io"ld precede /.■. (If both equalities hold, then the jobs are obviously 
interchangeable.) 

Proof. Suppose we have a schedule o such that the inequalities above hold and Jj precedes 
/,-. Without loss of generality, suppose both jobs are in //, and that all of the second-stage tasks 
are started as late as possible. Then it is easy to see that exchanging 7,- and Jj on both machines 
(see Figure 4.5) does not increase the makespan. Thus, it is sufficient to consider schedules 
where 7,- precedes J:. QED. 



s 


Oj ^ 


Oj 




s 


Ji ^Oi 








Jj 




Ji 








Jj 




Ji 





Ij 



»li 



-li 



Figure 4.5a. 7,- and 7.- on Mq and M, . (Machine M2 not shown.) 



155 





c 


Oi 




«^ 


Oj 










Ji 




H 










Ji 




^J 





li 



C'li 



S'lj ^'ij 



Figure 4.5b. The exchange of 7^- and 7, on Mq and M,. 
(Machine M2 not shown.) 



Property 4.2. (Consecutive Dominance) If both 7, and 7. are in //^ and are processed 
consecutively on Mq, they should be sequenced by Johnson's rule (i.e., if min (p^,, p^.) < min 
[pf^, Pqi], then 7, should immediately precede 7.). 

Proof. The fact that both jobs are processed consecutively on both machines implies that 
Johnson's Rule applies to them. If the jobs are not sequenced according to Johnson's Rule, they 
can easily be exchanged, and the makespan of the schedule is not increased by the switch. QED. 

This property is stated for two jobs from the same group processed consecutively. It can be 
extended to a set of three of more consecutive jobs on Mq from the same group: 

Corollary 4.1. (Batch Dominance) The jobs in each batch of a schedule should be 
ordered by Johnson's Rule, where a batch is defined as a set of consecutive jobs on Mo from the 
same group. 

Property 4.3. (Small Second-stage Dominance) Suppose 7j and Jj are in //^ and are 
processed consecutively on Mj^. If p^,- > p^,-. pqj > p/^j, and p^,- > p^y, then 7,- should precede Jj. 

Proof. Without loss of generality, suppose 7, and Jj are in //,. Consider a schedule where 
the two groups have been optimally interleaved and the second-stage ta.sks are started as late as 
possible. Then, if there arc any jobs between 7/ and Jj on Mq, they must be from Hj, and the start 
times of these jobs on Mj are between the start times of 7,- and Jj on M ,. (See Figures 4.6a and 
4.6b.) Suppose 7.- precedes 7,-. Let us interchange these jobs on both Mq and M, and check that 
we still have a feasible schedule without increasing the makespan. Let y be the old start time of 
Jj on Mj. Let z be the old completion time of 7,- on Mq. FotJj, the new completion time on Mq 



156 



equals z. Since 7, can be on only one machine at a time, z<y + p]j, the old start time of 7, on 
M]. Thus, z<y +p//, the new start time ofy.on M], and the schedule is still feasible for 7.-. 



POj 


Je 


POi 








Plj 


Pli 








h 



y z 

Figure 4.6a. (second-stage tasks started late). 



POi 


Je 


POj 










Pli 


Plj 








Jc 



X y z 

Figure 4.6b. (second-stage tasks started late). 

Now, let X be the new start time of 7, on Mq. Thus y>z-pjj>z-pQj = x. Now, for 7, and 
for all jobs 7g between 7 .■ and 7,-, the new completion time is less than x and thus y and thus the 
start time of their second-stage tasks. We can therefore switch Jj and 7, without increasing the 
makespan of the schedule. QED. 

Corollary 4.2. If for some //^, pg; > pi^j for all Jj, then the jobs in Hj^ should be ordered by 
LPT on the Mj^^ tasks. 

We note that if Corollary 4.2 is trtie for both //, and Hj, we have the first special case 
mentioned below (Theorem 4.3). 

Polvnomially-solvable special cases . Like other three-machine flow shop problems, the 
3MLA-MS problem has special cases that can be solved in polynomial time. Theorems 4.3 and 
4.4 present such special cases. 



157 

Theorem 4.3. If p/^ ^ Po^t ^^^ ^'* -^k '" ^i ^'^ P2j ^ POj f"*" ^^* •'/ '" ''z- ^^^ l^c optimal 
solution can be found by ordering the jobs in each group by their second-stage processing times, 
longest processing time first, and optimally interleaving the two sequences. 

Proof. This is true because Corollary 4.2 holds for both groups. QED. 

Theorem 4.4. If, for some H^, min [pg: .Jje Hi^jHi) ^ max (/?,■. : J: e //,), then the 
optimal schedule can be found by sequencing the jobs in each group by Johnson's Rule and 
optimally interleaving these sequences. 

Proof. By the given, we know that the conditions of Corollary 4.2 hold for the jobs in //,-. 
Thus, the jobs in this group should be ordered by longest second-stage task processing time first. 
For these jobs, this sequence is the same as the sequence given by Johnson's rule. Now, if we can 
determine the optimal ordering of the jobs in //^, the other group, we can interieave the groups to 
derive an optimal schedule. We will show that these jobs should be ordered by Johnson's rule. 

Consider an optimally-interleaved schedule where J^ is processed immediately before Jj on 
Mj^, and where the jobs are not ordered by Johnson's rule. That is, min {pQj, pj^f^} < min {p^;,, 

Pkj^ 

If there are no jobs from //, between Jf^ and 7. on Mq, then Property 4.2 implies that the 

jobs should be interchanged. 

Else, let y^ be the job from //, processed just before Jj. \Uj is not the last job on Mq, then 
we can move Jj to immediately after Jf^. Because the jobs that were between 7^ and Jj have short 
second-stage tasks, delaying these jobs does not delay the processing of any successive jobs. 
Now Jf^ and Jj are consecutively processed on Mq. and Property 4.2 implies that the jobs should 
be interchanged. 

Finally, if 7.- is the last job on Mq (and M^, then the fact that the schedule is optimally 
interieaved implies that p^y < Pi^, since 7^ is the last job on Mj. By the given, Py„ is less than or 
equal to pQf^ and pqj. Thus, min [pQj, pu^ ] < min [pgh^ Pkj) implies that p^/, < min {pQf^, pj^j) 
(since p^y < pqj) and consequently p^ < pq^ and p^/j < p^y. Property 4.3 implies that Jj should 
precede 7^. 



158 

Wc have thus shown that the jobs in //^ should be ordered by Johason's rule. This gives us 
an optimal ordering for //^ which can be interleaved with //,• to solve the problem. QED. 

4.2.6 Branch-anj-Bound Alj^oriihm 

In this section we will identify three lower bounds on the makcspan; we will take the 
maximum of these to form our overall lower bound. We will also discuss the use of a branch- 
and-bound technique for finding optimal solutions for the 3MLA-MS problem. We will use the 
overall lower bound in the analysis of the worst-case performance of an approximation algorithm 
(Section 4.2.9). We will begin by discussing the three component lower bounds. 

For the first component bound, consider only the jobs in //]. Order these jobs using 
Johnson's rule and determine for each 7.- a complefion time Cj: on M,. Then, LBj = max {Cjj]. 
Similarly, LB2 = max {€21]- 

The third component bound takes into account that all of the jobs use Mq. We relax the 
problem by dropping the second-stage assignments of the jobs and allowing an infinite number of 
second-stage machines. In fact, however, we only need n second-stage machines, one for each 
job. If each job has a separate second-stage machine, then the minimal makespan, which will be 
a lower bound on the optimal makcspan for the original problem, is the maximum sum of first- 
stage completion time plus second-stage task processing lime. By an argument similar to that of 
Section 1.4, we can find the minimal makespan by sequencing the jobs by their second-stage task 
processing times, longest first. We schedule the jobs in this order on Mq. The second-stage 
completion time of any job Jj in //, is Cqj + pij. Therefore, LB3 = max {Cqj + Pij] . Note that 
LS3 will be greater than S pqj^, since there exists some job Jj that has Cqj = Z pgic 

Our lower bound for a given problem (hereafter referred to by the variable LB) will be the 
maximum of these three lower bounds for the makespan: (i) LBj, the minimum possible 
makespan of the jobs in set //,, (ii) LB2, the makespan of the jobs in set Hj, and (iii) LB^, the 
minimal makespan if there exist an infinite number of sccond-slagc machines. That is, LB = 
max [LBi,LB2,LB2]. 



159 



In a standard branch-and-bound algorithm, each node will consist of a partial schedule of 
jobs. From a node, wc exclude certain branches using the above dominance properties and create 
a lower bound using straight-forward extensions of the above lower bounds. 

In order to help prune branches from the search tree, we will use the optimal properties that 
we developed in Section 4.2.5. We will also use a dominance property (Properly 4.4) that is more 
dependent upon the current makespan of each machine (where f, is the makespan of Mj). 

Property 4.4. For a given partial schedule, if 7. is unscheduled and in //^ (where H^ is the 
other group), ';t - ^ POi ^^^ ^^^ °^^'' ^' Jot's), and f^ < S Poi< ihen J: should not precede any 
job from Z/^. 

It is easy to show that if, in any schedule constructed from this partial schedule, 7. does 
precede any of the jobs from //^, we can move Jj to the last position without increasing the 
makespan. 

We used the branch-and-bound algorithm to solve a number of problems. On the set of 15- 
job problems, the running time was usually less than one second (on a 386 PC), although it was 
much greater for two problems, one of which had a lower bound that was not tight. See 
Table 4.1. 



Table 4.1. Statistics on branch-and-bound procedure for LA154. 



Problem Lower Bound Optimal 



Note: Time measured in seconds. 



Time 



Nodes 



1 


2942 


2942 


0.11 


38 


2 


2080 


2080 


0.11 


39 


3 


3138 


3138 


0.16 


47 


4 


3122 


3122 


0.11 


37 


5 


1956 


1956 


0.16 


56 


6 


2034 


2034 


0.22 


51 


7 


2187 


2187 


0.17 


57 


8 


1919 


1919 


0.17 


71 


9 


1911 


1911 


73.92 


61916 


10 


1945 


1956 


637.30 


546654 



160 

4.3.7 Heuristics 

Since 3MLA-MS is a strongly NP-complctc problem and the branch-and-bound procedure 
may occasionally take loo long to find the optimal solution, the use of approximation algorithms 
is a preferable alternative. Our discussion so far has led us one very natural heuristic, the 
interieaving of the Johnson sequences. We will also introduce another combination that will be 
of use later. 

Johnson Interleaved. Order the jobs in each group using Johnson's rule. Optimally 
interleave them using Algorithm 4. 1. 

Merged Johnson. Order the jobs in each group using Johnson's rule. Select the group 
with the smallest total task processing time on Mq (if the totals are equal, pick one arbitrarily). 
Start the schedule with all of the jobs from this group. Follow them with the jobs from the other 
group. 

4.2.8 Empirical Results 

In this section we report on the empirical testing of our heuristics. We discuss the problem 
sets generated, our methodology, and our results. 

In order to study the scheduling of a bottleneck machine, consider one of the second-stage 
machines, say Mj, as a bottleneck operation. As a bottleneck, the workload of M, should be 
greater than that of Mo or M2. Therefore, we will construct problems where the total processing 
time on M, is likely to be the largest. 

Three problem sets (LA 154, LA304, LA504) were created using uniform distributions to 
generate processing times. The mean fraction of jobs in each group and the mean processing 
times were set such that M, would have more work to do than M2. These problems had 15, 30, 
and 50 jobs. There were ten problems in each set. 



20-60 


40-120 


30-90 


80-160 


240^80 


120-200 


30-60 


40-80 


60-120 



161 

Table 4.2. Characteristics of 3MLA-MS problem instances. 

Set Jobs Average number Mq limes Mj times M2 times 

of jobs in H, (range) 

LA304 30 15 

LA154 15 5 

LA504 50 37 

Another problem set (LA201) was created based upon the problem structure used in the 
NP-complcteness proof. Ten sets of 15 random integers ranging from 1 to 10 was created (with 
an adjustment to insure that the total processing time was divisible by 5), and a 20-job problem 
was created from each set of these a: using the construction in Theorem 4.2. For this problem we 
knew a good lower bound, although we determined later that two of the embedded 3-Partition 
problems had no solution and thus the lower bound could not be achieved. 

For each problem, our lower bound on the makespan was the maximum of the three 
component bounds (see Section 4.2.6). The best component bound depended upon which 
machine had the largest workload for any problem. Since M, generally had the most processing 
time, the Mq - M] bound was usually greatest. 

For the 15-job problems, we were able to calculate the value of the optimal solution. For 
the other uniform problems we were able to find heuristic solutions that achieved the lower 
bound, implying that our lower bounds were tight and that we had found optimal solutions. 

On the 20-job hard problems, we could solve the imbedded 3-Partition problem. For 8 of 
the 10 problems, there does exist a partition and thus we know the optimal makespan. For the 
other two, we do not know the optimal, although we came very close with the heuristics. 

The results of the Johnson Interleaved and Johnson Merged heuristics on minimizing the 
makespan are shown in Table 4.3. Performance is the relative deviation from the optimal (if 
known) or the lower bound. We observed that the Johnson Interieaved algorithm found near- 
optimal or optimal solutions for all of these problems. The performance of the Johnson Merged 
algorithm varied from good on the 30- and 50-job problems to poor on the 20-job problems. The 
Johnson Interieaved heuristic outperformed a number of other sequencing rules, and these results 
were consistent with testing on a number of other problem sets with different problem structures. 



162 

Table 4.3. Makcspan summary tabic for 3MLA-MS problem. 
Pcformancc is relative deviation from optimal or lower bound. 

Set Johnson Johason 

Interleaved Merged 



LA 154 


0.50 


2.44 


LA 304 


0.00 


0.35 


LA 504 


0.00 


0.40 



LA 201 0.42 23.14 

4.2.9 Heuristic Error Bounds 

It is often possible to evaluate a heuristic by analyzing its worst-case behavior. Heuristics 
that minimize the makespan of scheduling problems arc especially open for this kind of analysis 
due to the simplicity of the objective function. Since the Johnson Intcrieavcd heuristic performed 
the best in our empirical study, we are most interested in determining the worst-case performance 
of this procedure. 

We will begin our analysis with the Merged Johnson procedure. For this bound we will 
make use of the lower bounds derived in Section 4.2.6. Recall that our lower bound LB = max 
[LB^,LB2,LBj]. 

Theorem 4 J. For a given instance of 3MLA-MS, the schedule created by the Merged 
Johnson heuristic has a makespan less than 3/2 LB. 

Proof. Without loss of generality suppose that Thi POj - ^in POj- Now, LB3 > S Pop ^^ 
sum over all of the jobs, implying "Zm pg; < 1/2 LB^ < 1/2 LB. LBj^ be the minimal makespan 
achievable by the jobs in //^, found by scheduling the jobs using Johnson's rule. The makespan 
of the scheduled created using the Merged Johason heuristic is max {Lfii, 'LhiPoj+ ^2)- T^is 
is less than max [LB, \/2LB + LB] ^ 3/2 LB. QED. 

Now, let us consider the John.son Intcrieaved heuristic. Since this algorithm combines the 
two Johnson sequences optimally, its performance cannot be worse than that of the Merged 
Johnson heuristic. Thus we can make the following statement. 



163 

Corollary 4.3. For a given instance of 3MLA-MS, the schedule created by the Johnson 
Interleaved heuristic has a makespan less than 3/2 LB. 

Theorem 4.6. The maximum error of the Johnson Interleaved algorithm relative to the 
optimal makespan is one-half. 

Proof. If C is the value of the optimal makespan and Cj/ the makespan of the schedule 
created by the Johnson Interieaved algorithm, LB < C* < Cjj < 3/2 LB < 3/2 C*. Thus, 
(Cjj-C*)/C*< 1/2. QED. 

Let us make a few observations about our algorithm. First, the error bound can be extended 
to the case where there arc m > 2 groups (each group with a different flow to a different second- 
stage machine). The maximum relative error of the Johnson Interieaved algorithm is 1 - 1/m in 
this case. 

Second, the Johnson Interleaved algorithm interleaves the groups by looking ahead to the 
future workload of the second-stage machines (the sum of the remaining second-stage task 
processing times). 

Finally, our error bound of one-half is tight. In the following problem instance, the bound 
is achieved in the limit. 

Example 4.2. Given n, let C be 2« -i- 1 . For A/] , construct jobs /j , . . . , 7„ with the 
following characteristics: 

J =!,...,«- 1: Poi=^ P]i='^ 

Construct in Hj jobs J^^ ],..., J2n with similar characteristics; 

i = n+ \, . . . ,2n- \: pgi = 1 pji = I 

' = 2i: P02n='^ Pl2n = '^- 

Now, since ties can be broken arbitrarily, each group is already ordered by Johnson's rule 
(we could force this ordering by subtracting a small amount from the appropriate first-stage 
tasks). An optimal schedule can be achieved by interleaving the sequences [ JfiJ\ ■ ■ ■ J n-l 1 ^^^ 



164 

^•^2n-^n+\ ■ ■ -^In-} 1- The makespan of such a schedule is C =2n+ 1. The interleaving of the 
Johnson sequences yields a schedule with malccspan 3n, as docs merging the Johnson sequences. 
As n goes to infinity, the ratio of each of these maicespans to C goes to 1 .5. See Figures 4.7, 4.8, 
4.9 (J^ = y,o) for the optimal, interleaved, and merged schedules with « = 5. 



h 


Jx 


h 


J6 


J2 


h 


h 


h 


U 


h 






h 


h 


h 


h 


h 




Jx 


J6 


h 


h 


}g 



1 8 9 10 11 
Figure 4.7. Optimal schedule (second-stage tasks started late). 



Jl 


J6 


h 


h 


h 


J8 


J4 


h 


J5 


Jx 












h 


h 


h 


J4 


J5 




J6 


h 


h 


J9 


Jx 



2 6 10 15 

Figure 4.8. Interleaved Johnson schedule (second-stage tasks started late). 



Jl 


h 


h 


J4 


h 


J6 


h 


h 


J9 


K 






h 


h 


J3 


h 


h 
















h 


h 


h 


J9 


Jx 



1 



15 



Figure 4.9. Merged Johnson schedule. 



4.3 Minimizing the Total Flowtimc 



In this section we discuss the Three-Machine Look-Ahead problem with the objective of 
minimizing the total flowiime (3MLA-FT). We know that minimizing total flowtime in a two- 
machine flow shop is an strongly NP-complete problem (Garey, Johnson, and Sethi, 1976). Since 



165 

that problem is a special case of 3MLA-FT, 3MLA-FT must also be a strongly NP-complcte 
problem. Hence, we will investigate opiimality conditions, lower bounds, and heuristics. Since 
total flowtime is a regular objective function, only permutation schedules need be considered for 
optimality (see Section 4.2.3); thus, a sequence of jobs for Mq corresponds to a unique schedule 
on all three machines. The problem notation is the same as that for the 3MLA-MS problem. 

A number of researchers have studied the problem of minimizing the total flowlime in a 
flow shop. This work includes lower bounds, branch-and-bound algorithms, and heuristic 
approaches. See Ignall and Schrage (1965) for a branch-and-bound and Ahmadi and Bagchi 
(1990) for improved lower bounds. Szwarc (1983) studies special cases, and Van de Velde 
(1990) presents a Lagrangian relaxation. Krone and Steiglitz (1974), Kohlcr and Steiglitz (1975), 
Miyazaki, Nishiyama, and Hashimoto (1978), and Miyazaki and Nishiyama (1980) all present 
heuristic approaches. Ahmadi et al. (1989) includes batch processing. 

4.3.1 Total Enumeration 

Initially, we wanted the compare Lhe difficulty of finding near-optimal solutions for 3MLA- 
FT to the difficulty of finding near-optimal solutions for 3MLA-MS, where we had very good 
results. One way in which we could compare the two problems was to compare the range of the 
objective functions over the domain of all permutation schedules. 

For a nine -job problem, a total enumeration of the permutation schedules includes over 
300,000 sequences. We picked an arbitrary instance, created each schedule, and measured the 
makespan and total Howtime of each schedule. This procedure yielded a distribuUon of 
makespans and total tlowtimcs over the set of sequences. 

The primary result is that 18.5% of all sequences have makespans within 6.7% of the 
optimal makespan, but less than one quarter of one percent of all sequences have flowtimes 
within 6.7% of the optimal fiowlimc. (See Table 4.4 and Figure 4.10.) Because there are much 
fewer schedules that are near-optimal, we can infer that the problem of minimizing the total 
flowtime is a much harder problem than the problem of finding the minimum makespan. Similar 



166 

results hold for another nine-job problem and a fifteen-job problem where a random sample of the 
sequences were examined. 

Table 4.4. Distribution of schedule makespans and flowiimes. 



Deviation from 


Percent of 


Deviation from 


Percent of 


optimal makcspan 


schedules 


optimal flowtime 


schedules 


3.3 % 


5.65 % 


3.7 % 


0.05 % 


6.7 


18.47 


6.7 


0.23 


10.0 


30.13 


14.2 


2.05 


13.3 


49.07 


21.6 


6.85 


16.7 


62.17 


29.1 


15.83 


20.0 


75.41 


36.6 


29.18 


23.3 


86.24 


44.0 


45.37 


26.7 


92.31 


51.5 


62.31 


30.0 


96.43 


59.0 


77.28 


33.3 


98.10 


66.4 


88.65 


40.0 


100.00 


73.9 


95.49 




30 40 50 60 

Percent Deviation from Optimal 



80 



Makcspan --Q- Flowiimc 



Figure 4.10. Deviation from optimal makcspan and flowtime. 



167 



4.3.2 Lower Bounds 

In this section we discuss lower bounds on the total flowtimc. These lower bounds provide 
us with a way of determining the quality of the solutions produced by our heuristics and can be 
extended into lower bounds for a branch-and-bound algorithm. 

The lower bounds are similar to those proposed in Ignall and Schrage (1965). The initial 
lower bound on the total flowtime is calculated by ordering the jobs by their processing times on 
Mq, shortest processing time first (SPT), and assuming that the second-stage machines have 
infinite capacity. That is, LB^ - X Cq: + Z Pjj + S P2j- 

We compute the second bound by considering each of the second-stage machines. Let a = 
min [pQj -.Jje //, ) and ft = min {pg: :Jje Hj}. Now, a (b) is the earliest lime that the second- 
stage tasks on Mj (Mi) could start. Then, form two sequences Oj and O2of the jobs in//, and H2 
respectively by ordering the jobs in each group by the second-stage task processing times, 
shortest processing time first. Schedule on M, the second-stage tasks of the jobs in //, in the 
order given by O]. The first task should begin at a, and each successive task should immediately 
follow (we do not schedule the first-stage tasks). This forms completion times Cjj for the jobs. 
Repeat for the second-stage tasks of the jobs in H2 in order to calculate C2/. 

However, only one machine can start at its cariiest time. The other must start at a time no 
less than a + b. Let r be the cardinality of//; and s the cardinality oi Hj. Either the r tasks on M, 
will be delayed by b, or the s tasks on M2 will be delayed by a. After calculating rb and sa, we 
can increase our lower bound by adding the smaller quantity. Thus, the second lower bound is 
LBj = X C]j + Z C2j + min {rb, sa}. 

In Example 4.3, we calculate the lower bounds for the problem instance that we introduced 
in Example 4.1. 



168 
Example 4 J. Given the following five jobs in iwo groups: 



Jj 


"i 


POj 


Pij 


'j 


h 


Hx 


2 


4 


9 


h 


W, 


1 


1 


1 


h 


^1 


2 


4 


5 


J4 


Hi 


2 


1 


4 


h 


»2 


1 


3 


3 



Lower Bound 1: Order first-stage by SPT and add second-stage: 
POj \ 1 2 2 2 

Cqj \ 2 A b % 

Y.Coj = 2\. lpjj = 9. 1P2J = 4. LB, = 34. 

Lower Bound 2: Order each second-stage machine by SPT: 
a= 1. r=3. b= 1. 5 = 2. 

Plj 14 4 P2j \ 3 

Cjj 2 6 10 C2j 2 5 

I Cjj = 18. I C2j = 7. min [rb, sa) = 2. LB2 = 27. 

4.3.3 Special Case 

This section discusses a special case that leads to easily-found optimal solutions. 

Theorem 4.7. If p/^ < pq^ for all Jj^ in H, and P2j ^ Pqj for aU Jj in Wj. then any sequence 
a in which the first-stage tasks are in SPT order forms an optimal schedule. 

Proof. Suppose we have such a o. Consider//,. If/,- is the first job on M,, then Cy, = Cq, 
+ Pll. Ify^ is the next job from//, onU,,\hQnpii<pQi<pQi^. Thus, the second-stage task of 7,- 
completes before (or at the same time as) the first-stage task of 7^ and does not delay the second- 
stage task of ./^. Thus, Cy^ = Cqj^ + pjj^. Similarly, this equality is true for all 7^ in //,, and C2J 
- ^Oj "•■ P2j fo"" ^'^ -^i '" ^2- 'Phe total fiowtime is therefore I Cy = I Cqj + 'Lpij + 'L P2j- Since 
the first-stage tasks are in SPT order, this achieves the first lower bound, and this sequence is an 
optimal schedule. QED. 



169 

4.3.4 Empirical Testing 

Empirical testing was performed using a number of different heuristics. The three 
heuristics that performed the best (and very similarly) are described below. The 3MLA-MS 
problem sets were used as a testbcd. For each problem, the four lower bounds on the flowtime 
were calculated. The best of these was taken as the lower bound. For the fifteen-job problems, 
we were able to find the optimal solutions from the branch-and-bound algorithm. The 
performance of a heuristic on a problem was taken as the relative deviation from the optimal 
solution (if known) or the best lower bound. 

SPT-look-ahead. Each group //, and H2 is ordered by the first-stage task processing times 
(shortest first), forming two sequences. These sequences are interieavcd by choosing at each step 
the first unscheduled job from one sequence or the other. Define at each step the following 
variables: fg is the completion lime of the partial schedule on Mq and f 1 is the completion time of 
the partial schedule on Mj. Letpi (P2) be the processing time on Mq of the next job from H^ 
(H2). Note that these are the shortest such task processing times from each set of jobs. If f 1 - ^o - 
Px, the work-in-process inventory (WIP) waiting at Mj is low; schedule the job from //j. If ^i - 1^ 
>Pi+ P2, then the WIP at Mj is high; schedule the job from H2. Else, Pi < ^1 - fo < Pi + ^2' ^d 
the WIP is intermediate; schedule the job with shortest first-stage processing time (pi or/72)- 

WIP-look-ahead. Again, order the jobs in each group by the first-stage task processing 
times (shortest first). Combine the groups as in SPT-Look-ahcad, except for one case: If /?i < t^ - 
h<P\ ^Pi' schedule the job from //j. Thus the work on M, is always used to determine which 
job to schedule. 

Johnson-look-ahead. Sequence each group by Johnson's rule. Combine the groups as in 
SPT-Look-ahead, except for one case: If pi < '1 - '0 < Pi + P2> schedule the job from //j. Thus the 
work on M] is always used to determine which job to schedule. 

We tested the heuristics on the problem sets described in Section 1.7. For the fifteen-job 
problems, we were able to find the optimal solutions from a branch-and-bound algorithm. We 



170 

could not find optimal solutions for the larger problems. Therefore, in order to measure the 
heuristics, we computed a lower bound on the flowtime for each problem. We calculated the 
lower bounds described in Section 2. 1 and took the largest as the lower bound. The performance 
of a heuristic on a problem was taken as the relative deviation from the optimal solution (if 
known) or the best lower bound. Due to the special structure of the problem, we could find 
improve the second lower bound for the instances in Set 4 by determining the optimal total 
flowtime for the five jobs in H^. 

Minimizing the total flowtime is harder than minimizing the makespan, and in Table 4.5 we 
report the results of the three heuristics described above. These heuristics were selected because 
they performed much better than a number of other procedures that combined the groups 
differently. The look-ahead heuristics found solutions with average total flowtime within eight 
percent of the optimal value. Because of the special structure of the 3MLA instances in Problem 
Set LA201, very good solutions were easier to find. The WIP-Look-ahead heuristic was slightly 
better on all of the other problem sets. However, the heuristics were very close to each other. 



Table 4.5. Heuristic performance for the 3MLA-FT Problem. 
Performance relative to optimal or lower bound. 



Set SPT WIP Johnson 

Look-ahead Look-ahead Look-ahead 



LA154 


7.23 7.13 


7.32 


LA 304 


5.41 5.16 


6.15 


LA 504 


4.95 4.85 


6.58 


LA 201 


1.37 1.37 


1.37 




4.4 Minimizing the Number of Tardv Jobs 


4.4. 1 Problem Iniroductior 


I 





The other objective function under consideration in look-ahead scheduling is the number of 
tardy jobs. This problem models a subproblcm of the shop scheduling problem related to the 



171 

feeding of a bottleneck machine. The objective mirrors the management concern of customer 
satisfaction. 

Let us call our problem the Three-Machine Number Tardy (3MNT) problem. Recall that 
only permutation schedules need be considered. Thus a sequence for all of the jobs defines a 
unique schedule. The problem notation is the same as that for 3MLA-MS, except that we have 
for each job J: a due date d:. Since 3MLA-MS is strongly NP-complctc, 3MNT is also strongly 
NP-complete. Consider an instance where all of the jobs have the same due date: finding a 
schedule with no tardy jobs is equivalent to finding a schedule with makespan less than or equal 
to the common due date. 

Since the problem is computationally difficult, we will examine a simple lower bound, a 
special case, and some heuristic approaches to finding solutions. 

4.4.2 Lower Bound and Special Case 

Good lower bounds are hard to find for the problem of minimizing the number of tardy jobs 
in a flow shop (Hariri and Potts, 1989). We will make use of a fairly simple one. 

The lower bound makes use of the fact that the Moore-Hodgson algorithm will find the 
optimal number of tardy jobs for a one-machine problem. Given an instance of 3MNT, the due 
date of each job is adjusted by subtracting the processing time of the second-stage task. These 
adjusted due dates and the first-stage processing times form a one-machine problem for machine 
zero. The lower bound is calculated by using the Moore-Hodgson algorithm to optimally 
sequence these tasks. The number of tardy first-stage tasks is a lower bound on the minimum 
number of tardy jobs for the 3MNT instance. 

This lower bound is achievable in the following special case: 

Theorem 4.8. If min [pq: :Jje //, } > max [pj: : J.- € //, } and min {pQj :Jje H2} ^ max 
(P2j '.Jie H2], then an optimal sequence can be found be minimizing the number of first-stage 
tasks that are tardy to the adjusted due dates. 



172 

Proof. Because of ihe condilions above, the completion time of a job J: in //, is 
C: = Cq; + Pij. Thus. Jj is tardy if and only if Cq: > d; - Piy QED. 

We also tried lower bounds on each of the second-stage machines, but these were not as 
good. This seems reasonable if the interaction of the two flows is significantly contributing to 
tardiness. 

4.4.3 Heuristics 

Simple rules that can be extended for this problem include the Moore-Hodgson algorithm 
and Eariiest Due Date (EDD). These can be expanded by including look-ahead ideas. We also 
developed a simple problem space genetic algorithm to find good solutions. 

Look-ahead rules . The look-ahead extension of the Moore-Hodgson algorithm includes 
both machines. The jobs are ordered by their due dates and added to the schedule until a tardy 
job is found. The procedure then determines the critical path of tasks that determines the 
completion time of the tardy job. Then, each job in the path is evaluated to determine how much 
the completion time would decrease if that job were removed from the partial schedule. This 
calculation depends upon whether the job precedes, is, or follows the crossover job (the job 
whose first and second tasks are in the critical path). 

We developed two look-ahead versions of the EDD rule. The first is similar to the Moore- 
Hodgson rule. The jobs are sequenced by their due dates. They are scheduled one at a time. 
When a job is tardy, however, we simply remove it to the end of the schedule. (In the Moore- 
Hodgson rule, we look for the job whose removal helps the most.) This form of the EDD is 
called EDD-No Tardy. 

The other look-ahead version (EDD-Look-ahead) tries to schedule machine one (the 
bottleneck) carefully. The jobs in each group arc ordered by their due dates. The primary idea is 
to get the jobs from group one to be on-time; group two jobs can be inserted if they don't 
interfere. At any point in constructing the schedule, we consider the next job from each group. If 
either would be lardy if scheduled next, we place it at the end of the schedule. Eventually, we get 



173 

a job from each group that would be on-time if scheduled next. We then determine if scheduling 
the group two job next would cause the group one job to be tardy. If not, we schedule this group 
two job and consider the next job from that group. Else we schedule the group one job next. 

Genetic algorithm . After initial testing, we determined that the look-ahead Moore-Hodgson 
rule found consistently good solutions. Thus, we used a problem space genetic algorithm to 
adjust the problem data used by this rule so that we could find belter solutions. The procedure is 
similar to those described in Chapter 3. We adjust the due dates using a steady-slate genetic 
algorithm. The population size was 50, and the algorithm generated 1000 new individuals. 

4.4.4 Results 

In order to compare the heuristics we created a number of problem sets. Each set had 10 
similar instances. Problems were created with 15, 30, and 50 jobs. The processing times were 
chosen randomly, and the due dales were chosen from a range that depended upon the sum of the 
processing times. 

The look-ahead Moore-Hodgson heuristic performs better than any of the other rules (See 
Table 4.6). A number of rules that used the first-stage due date of a lot were also tested but did 
not perform as well. The genetic algorithm was able to find slightly better solutions than those 
found by the Moore-Hodgson rule. 

Table 4.6. Summary table of results for 3MNT. 

Set Jobs Lower EDD EDD Moore Genetic 

Bound No Tardy Look-ahead Algorithm 



NT 151 


15 


5.8 


7.8 


7.3 


7.0 


6.5 


NT 152 


15 


5.3 


7.6 


7.1 


7.1 


6.3 


NT 301 


30 


9.0 


12.7 


12.5 


12.0 


10.6 


NT 501 


50 


17.0 


21.6 


21.4 


20.7 


20.4 



174 
4.5 Application lo Job Stiop Scheduling 

One of the primary motivations for studying these problems was to see if we could develop 
useful dispatching rules. After considering our results, it seemed clear that look-ahead and look- 
behind policies similar to those we used on the one-machine and three-machine problems would 
be intuitively good ways to dispatch jobs. However, we wanted to determine the tradeoffs of 
using such rules on a number of objectives. To this end, we created a job shop scheduling 
problem that modeled the semiconductor test area we were studying. This problem had 82 jobs 
and 23 machines and included various test operations. Processing time data were gathered from 
some historical lots. We scheduled the jobs under a number of dispatching rule combinations, 
using standard dispatching rules, look-ahead rules, and look-behind rules. We measured the 
schedules on four scales: total flowiime, makespan, number of tardy jobs, and total tardiness. 

The bottleneck in this problem was a set of bum-in boards. Thus, we developed a look- 
ahead rule that orders the jobs wailing by their task processing times and uses information about 
the downstream bottleneck resource (the bum-in board availability) to determine which lot should 
be scheduled next. We also developed a look-behind rule that sequences lots by EDD and 
reserves bum-in boards for the next late lot that will be arriving soon. The effort of using these 
rules is slight for our problem; in a manufacturing environment, the dispatching effort might be 
more significant. 

We used the following scheme in order to see how look-ahead and look-behind rules would 
influence schedule performance. We allocated the rules by dividing the machines into three 
areas: electrical test, bum-in, and other. In any given policy, all of the machines in the same area 
used the same dispatching mle. Our model included one bum-in workstation and 15 testers. We 
used seven standard rules: SPT, EDD, Slack per Remaining Operation, LPT, Modified Due Date, 
Earliest Finish Time, and First-In-First-Out in all areas. 

For each of the standard rules, we created four policies. In the first, all of the areas used 
that rule. In the second, the testers used the look-ahead rule (since these were the machines 



175 

feeding the bum-in area). In the third, the bum-in area used the look-behind rule. In the fourth, 
the testers used the look-ahead rule while the bum-in area used the look-behind rule. This 
yielded 28 policies. 

The average results over the seven standard rules arc summarized in Table 4.7. We observe 
that the use of a look-behind rule, which is concemed with expediting late jobs, has a drastic 
effect on due date-related measures. It is able to reduce total tardiness while increasing the 
number of tardy jobs. This is a common tradeoff in scheduling problems. The look-ahead rule, 
which is concemed with avoiding unnecessary delays, reduces the total flowtime and makespan 
objectives. Our results are the consequence of the specific definitions of these look-ahead and 
look-behind rules. For other problems, altemative definitions may yield different results. While 
our results are not proof that look-ahead and look-behind rules are the answer to solving the job 
shop scheduling problem, the decreases in total flowtime (when the look-ahead rule was used) 
and total tardiness (with the look-behind rule) did encourage us to use them in our procedures to 
find good solutions (discussed in Chapter 5). 

Table 4.7, Performance of 28 dispatching rule combinations. 

Flowtime Makespan Tardy Tardiness 

All policies^ 2,179,344 88,677 17.1 192,394 

Single mles^ 2,168,014 

With Look-ahead'' 2,135,800 

With Look-behind* 2,222,639 

With both* 2,190,921 

Notes: a: Average over all 28 policies. 

b: Average over seven policies, one for each standard rule. 

4.6 Chapter Summarv 

In this chapter we have examined a special case of the general three-machine flow shop. In 
this problem, the jobs to be scheduled form two classes with different groups, and we wish to 
minimize the makespan, the total fiowiime, or the number of tardy jobs. 



89,324 


16.6 


249,968 


88.850 


16.6 


243,253 


88.534 


17.6 


138,130 


88.001 


17.6 


138,226 



176 

We proved that minimizing the makcspan is a strongly NP-complctc problem, and we also 
identified some properties of optimal solutions and some special cases that can be solved in 
polynomial time. We developed an approximation algorithm, Johnson Interleaved, that can find 
near-optimal solutions by looking ahead to the future workload of the second-stage machines. 
We showed that the worst-case error bound for this procedure is one-half and that this bound is 
tight in the limit. We also developed a branch-and-bound algorithm that can find exact solutions 
to the problem. 

Then we described the problem of minimizing the total flowtime. We presented lower 
bounds, optimality conditions, and the results of testing on selected problem instances a number 
of heuristics that look ahead to current workload at the second-stage machines. 

Finally we examined the problem of minimizing the number of tardy jobs. We discussed a 
simple lower bound, a special case that achieves this bound, and a number of simple and look- 
ahead heuristics. We also showed that a problem space genetic algorithm can find better 
solutions. 

These results have two contributions. First is the analysis of these three-machine problems, 
problems previously unstudied in the literature. We conclude from the results of our empirical 
testing that look-ahead heuristics can find good solutions for the problems of minimizing total 
flowtime and minimizing the number of tardy jobs, and the interieaving procedure minimizes 
makespan. 

Second, while these problems are important questions in their own right, they are also 
significant as subproblems in a job shop. It is possible to apply our results to the problem of job 
shop scheduling, either as part of a general scheduling procedure or as an attempt to schedule the 
bottleneck of a job shop more efficiently. 



CHAPTER 5 
GLOBAL JOB SHOP SCHEDULING 



In this chapter wc describe a global job shop scheduling procedure that uses a genetic 
algorithm to find a good schedule. We have implemented the scheduling system in a 
semiconductor test area. The test area is a job shop and has sequence-dependent setup times at 
some operations. The concern of management is to meet their customer due dates and to increase 
throughput. This requires the coordination of many resources, a task beyond the ability of simple 
dispatching rules. We discuss a centralized procedure that can find a good schedule through the 
use of a detailed scheduling model and a genetic algorithm that searches over combinations of 
dispatching rules. We discuss our effort in developing a system that models the shop, creates 
schedules for the test area personnel, and contributes to test area management. 

5.1 Introduction 

In many areas of manufacturing, the ability of a facility to meet its objectives depends 
upon the close coordination of resources. This coordination must occur on different levels: 
capacity planning, release planning, and lot dispatching. Effective approaches exist (and new 
techniques are being developed) for the first two levels. The third level, meanwhile, continues to 
pose very difficult scheduling problems. These are the problems that we address. Like other 
researchers, we are interested in creating systems to better schedule resources in a manufacturing 
process, since effective scheduling can lead to improvements in throughput, customer satisfaction 
(measured by meeting due dates), and other pxjrformance measures. 

We are concerned with the effective scheduling of a semiconductor test area, a job shop 
environment. In this facility, a lot is a number of identical semiconductor devices. Each lot must 
undergo a number of tests (electrical and physical) and other operations before the product can be 

177 



178 

shipped to the customer. Associated with the lot is the due date of the customer order it will be 
used to fill. Because each product has a unique route, different lots take different paths through 
the test area. 

A number of characteristics make the semiconductor test area difficult to control. These 
include the conflicting goals of management (balancing increased throughput against meeting due 
dates), work centers with sequence -de pendent setup limes, operations where multiple lots can be 
processed simultaneously, and the relationships between operations. 

The purpose of this chapter is to describe the global job shop scheduling system developed 
for semiconductor testing. We will examine the needs of the semiconductor test area, their 
requiremenLs for a scheduling system, and our approach to this problem. 

The primary goal of the global job shop scheduling system is to use information about the 
current status of the shop, the jobs to be manufactured, and the production process in order to 
create a schedule of activities for each work center in the shop over a fixed time period. By using 
a centralized procedure with global information, the system can search for a schedule better than 
that computed by making nearsighted, local decisions. 

The system finds good solutions with a genetic algorithm, a type of heuristic search. One 
interesting characteristic of this search is that it looks for a good combination of dispatching rules 
to find an efficient schedule. The use of dispatching rules is an effective local procedure to create 
a job shop schedule; such techniques do not, however, use any global information. Our 
procedure addresses this shortcoming. It goes beyond simply finding good local schedules; it 
executes a search that looks for a bener global schedule. While global scheduling techniques 
have been proposed before, the important contributions of our work are the development of a 
genetic algorithm for job shop scheduling and the implementation of a scheduling system that 
uses such an advanced solution procedure. 

The next section of this chapter will review some background and related research on job 
shop scheduling. The genetic algorithm for global scheduling is introduced in Section 5.3, where 
we also discuss a small example of our search space. In Section 5.4 we describe the scheduling 



179 

problem in the semiconductor test area under consideration and the global job shop scheduling 
system that we developed. We summarize our report in Section 5.5 and describe how a similar 
system may be useful in other manufacturing environments. 

5.2 Job Shop Schcduiint! 

As mentioned in the introduction, the problem of coordinating resources to ensure efficient 
manufacturing is a difficult problem. When the production process is fairly straightforward, 
techniques such as Just-In-Time (JIT) manufacturing result in efficient scheduling. In many 
situations, however, the process is much more complicated, and finding an optimal or near- 
optimal schedule is an impossible task. In this section we will review some of the approaches to 
job shop scheduling. More details on these papers can be found in Chapter 2. 

The traditional method of controlling job shops is the use of dispatching rules. A 
dispatching rule is a sequencing policy that orders the jobs waiting for processing at a machine; 
the ordering depends upon the particular dispatching rule used. Common rules include the 
Shortest Processing Time (SPT) and Eariiest Due Date (EDD) rules. 

While such rules have been the subject of much research, standard dispatching rules have a 
narrow perspective on the scheduling problem, since they ignore information about other jobs and 
other resources in the shop. More advanced look-ahead and look-behind rules attempt to include 
more information, but their reach is still limited. Effective job shop scheduling depends upon the 
interaction of a number of factors. The complexity of these interactions makes the development 
of a global scheduling system a difficult task. 

A number of researchers have looked at semiconductor manufacturing at all levels, from 
production planning to scheduling. Approaches to shop floor control include lot release policies, 
dispatching rules, deterministic scheduling, control-theoretic approaches, knowledge-based 
approaches, and simulation. Uzsoy et al. (1992a, 1993) review a substantial number of papers 
that consider these approaches to semiconductor scheduling. 



180 

This work in semiconductor manufacturing includes corporate-wide production planning 
that uses a rale-based model of production and linear programming (Leachman, 1993, and 
Hackman and Leachman, 1989). Such a global planning system has been developed under the 
name IMPReSS at Harris Semiconductor. Hung and Leachman (1992) have developed an 
iterative method that uses a linear program and a discrete-event simulation to develop long-term 
production plans for a wafer fab. 

While most of the research in semiconductor scheduling has concentrated on the fabrication 
of semiconductor wafers, a number of other papers have addressed the problems of 
semiconductor test. These include Lee, Uzsoy, and Martin- Vega (1992), and Uzsoy etal. (1991a, 
1991b, and 1992b). Lee et al. (1993) report on the implementation of a decision support system 
for the dispatching of lots in a semiconductor test area. Our work is the natural extension of this 
system. 

Previous approaches to the production of detailed shop schedules for planning and shop 
floor control include expert systems like ISIS (Fox and Smith, 1984), OPIS (Smith, Fox, and Ow, 
1986, and Ow and Smith, 1988), MICRO-BOSS (Sadeh, 1991), and OPAL (Bensana, Bel, and 
Dubois, 1988); cost-based procedures such as OPT (Optimized Production Technology, reviewed 
by a number of authors, including Jacobs, 1984), Faaland and Schmitt (1993), and the bottleneck 
dynamics of SCHED-STAR (Morton et ai, 1988); simulation (Leachman and Sohoni, Najmi and 
Lozinski); and leitstands (Adelsberger and Kanet, 1991). Adlcr et al. (1993) describe the 
implementation of a bottleneck-based scheduling support system for a paper bag production 
flexible flow shop. While these approaches have been developed for a number of different 
manufacturing processes, the complications of the semiconductor test area forced us to consider a 
new design. 

Job shop scheduling, as one of the most difficult scheduling problems, has attracted a lot of 
attention from researchers. Techniques such as the shifting bottleneck algorithm (Adams, Balas, 
and Zawack, 1988) or bottleneck dynamics (see Morton, 1992, for example) concentrate on 
solving the problem at one machine al a time. More work has gone into the development and 



181 

evaluation of various dispatching nilcs. Panwalkar and Iskandcr (1977) present a list of over 100 
rules. Recent studies include Fry, Philipoom, and Blackslone (1988), Vcpsalainen and Morton 
(1988), and Bhasakaran and Pinedo (1991). 

More sophisticated look-ahead and look-behind rules have also been discussed. Look- 
behind rules (called x-dispatch by Morton, 1992) consider the jobs that will be arriving soon from 
upstream machines. Look-ahead rules consider information about the downstream machines. 
This includes the work-in-ncxt-qucuc and the numbcr-in-next-qucue rules of Panwalkar and 
Iskander (1977), bottleneck starvation avoidance (Glassey and Petrakian, 1989), and lot release 
policies that look-ahead to the bottleneck (Wein, 1988; Glassey and Resende, 1988; and 
Leachman, Solor/ano, and Glassey, 1988). Look-ahead and look-behind scheduling problems 
have been studied in this dissertation and by Lee and Herrmann (1993). 

Finally, heuristic searches have also been developed for job shop scheduling, and a number 
of these are discussed in Section 2.8 of this dissertation. 

5.3 A Genetic Algorithm for Job Shop Scheduling 

In this section we will describe how a genetic algorithm can be used to find good schedules 
for the job shop scheduling problem. 

One approach to difficult scheduling problems such as job shop scheduling is local search, 
an iterative procedure that moves from solution to solution until it finds a local optimum. Smart- 
and-lucky searches (or heuristic searches, or probabilistic search heuristics) attempt to overcome 
the primary problem of these simple searches: convergence to local optima. These more complex 
searches are smart enough to escape from most local optima; they still must be lucky, however, in 
order to find the global optimum. 

In previous sections we reviewed the basic concepts of genetic algorithms and mention 
some application of smart-and-lucky techniques for job shop scheduling. In this section we 
describe our application of these ideas. 



182 
5.3.1 The Heuristic Space 

Many heuristic searches for the job shop scheduling problem have been considered. One 
reccnily-iniroduced idea is to search the problem and heuristic spaces, since a solution is the 
result of applying a heuristic to a problem. A change to the parameters of a heuristic or a 
problem yields a slightly dilTcrcnt solution. This section will describe how a heuristic space can 
be used for job shop scheduling. We will show why a genetic algorithm is especially suited for 
searching this space. 

The idea of searching heuri.stic and problem spaces was reported by Storer, Wu, and 
Vaccari (1992). In their paper, the authors examine the general job shop scheduling problem. 
They define a heuristic space composed of vectors of dispatching rules. Each vector in the space 
can be used to determine a schedule. Each rule in the vector is used for a fixed number of 
dispatching decisions, regardless of the machine being scheduled. That is, all of the machines use 
the same dispatching rule at the same time until the next rule replaces it. 

Our approach uses a different perspective. Since we will be working in a dynamic job shop 
scheduling environment, we may not know how many operations will be scheduled. Thus, it is 
impossible to divide the scheduling horizon by allocating each rules to a fixed number of 
operations. Instead, it seems more fair to assign a dispatching rule to each machine. The system 
can evaluate this combination of dispatching rules (which we call a policy) by measuring the 
performance of the schedule that is created by using this policy. Changing the policy by 
modifying the dispatching rule on one or more machines changes the schedule created. 

In order to demonstrate this idea, consider the following four-job, three-machine problem 
and two policies used to dispatch the jobs wailing for processing (see Figure 5.1 for the task 
processing times). 



183 



Job 


Due Dale 


h 


8 


h 


12 


h 


17 


u 


15 



Sequence of Machines to Visit: 

Machine 1 . Machine 2, Machine 3 
Machine 1, Machine 2 
Machine 2, Machine 1 . Machine 3 
Machine 2, Machine 3 



Machine 1 Machine 2 Machine 3 



Job 1 



Job 2 



Job 3 



Job 4 



4 . 3 • 3 



Figure 5.1. Task processing times for each job. 
Tasks grouped by a doited line are on the same machine. 



Policy 1 = [EDD, EDD, EDD]. Under this policy, the tasks waiting for processing at M, 
are sequenced by earliest due date first. Thus, when both 7, and J2 are at Mj, 7] is sequenced first 
since its due date is 8. 

The dispatching rule for Mj is EDD, so the tasks are sequenced by the job due date. When 
73 and 74 are at Mj, J4 is selected. After this task is completed, 7, has arrived and its due date is 
also smaller than Jy The same thing occurs when 7] finishes and J2 simultaneously arrives. 



184 



Policy 1 : lEDD, EDD, EDD] 
Schedule: Makcspan = 21. 



Ji 



J^ 



9 10 11 12 



17 



21 



In Policy 2, the altered dispatching rules, [SPT, SPT. SPT], change the selection of jobs. 
On M, the job Ji has the shortest task processing time and is thus preferred. On M2 the job J^ has 
the shorter task processing time and is scheduled first. 

Policy 2 : [SPT. SPT, SPT] 
Schedule: Makespan = 18. 



h 


Jl 


h 




h 


h 


h 


Jl 












h 




Jl 


J3 



1 3 5 7 8 10 11 



14 



Obviously, the application of a different policy creates a different schedule with a different 
evaluation on any objective we could wish to measure (makespan, defined as the maximum job 
completion time, was chosen here only as an example). 

These policies can be easily manipulated by a genetic algorithm. Traditional genetic 
algorithms must be modified for machine scheduling problems since the components of the 
strings (the jobs in the sequence) are not independent of each other. The heuristic space 
described above, however, consists of vectors that have independent elements. That is, the 
dispatching rule for the first machine does not affect what values the other elements can have. 
Thus, a crossover operation that breaks two strings (vectors) and joins the separate pieces yields 
offspring that arc valid points in the search space. 



185 
5.3.2 A Genetic Algorithm for Global Scheduling 

Wc will describe in Ihi.s section the Genetic Algorithm for Global Scheduling (GAGS). 
This search procedure is the engine that finds a good schedule. After discussing it in this section, 
we will turn away and address the scheduling system that it drives. 

GAGS consists of two primary components: the genetic search and the model of the shop 
floor. The interaction between these two functions is outlined in Figure 5.2. The genetic 
algorithm starts with a number of policies. (Each policy is a combination of dispatching rules, 
one rule for each machine. See Table 5. 1 for a list of the dispatching rules that were used in the 
global scheduling procedure.) Each policy is evaluated by the schedule that is created if the jobs 
in the shop are dispatched according to this piolicy. The model of the shop floor is employed to 
build this schedule from the set of shop, job, and process information. 



GAGS 



Genetic 
Operator 



Parents 



Population of Policies 



Best Policy 



Schedule 



Offspring 



Policy 



Offspring 



Fitness 



Input Data 



Scheduling Model 



Performance 



Schedule 



Figure 5.2. GAGS - Scheduling Model Interface 



186 
Table 5.1. List of dispatching rules considered. 

SPT 

Minimum Setup 

EDD 

Shop: Late-Setup Match-EDD 

Slack per remaining operation 

Modified Due Date 

Longest Processing Time 

Shortest Remaining Processing Time 

Earliest Finish Time 

First In First Out 

Least work in next queue 

EDD Look-ahead to bum-in 

SPT Look-ahead to bum-in 

Look-behind from bum-in 



The genetic algorithm creates new offspring policies by combining two policies in the 
population (crossover) or changing a solitary parent (mutation). For instance, consider again the 
above three-machine problem and the two policies [EDD, EDD, EDD] and [SPT, SPT, SPT). 
These policies were evaluated by creating schedules for all three machines. Their evaluations (on 
the makespan objective function) were 21 and 18. If we split each policy after the first rule and 
link the beginning of the first policy with the end of the second policy, we create the offspring 
policy [EDD, SPT, SPT], which the reader can confirm creates a schedule with a makespan of 17. 

Policy 3 : [EDD, SPT, SPT] 
Schedule: Makespan = 17. 



Jl 


h 


J3 




J3 


J4 


Jl 


J2 












J4 


Jl 


J3 



1 



4 5 7 8 10 11 13 



17 



These offspring policies are evaluated using the scheduling model. The genetic algorithm 
converges to a number of good policies, and the best is u.scd to create a final schedule. 

The model of the shop Hoor is the problem to be solved, and the genetic algorithm provides 
different heuristics. The system depends upon this model, therefore: only with a valid model can 



187 

a scheduling system create plans that match reality. For our project, the model was a 
deterministic simulation of the shop. It uses as input a set of resources that correspond to the 
equipment and staffing of the test area, a set of jobs that correspond to the lots that need 
processing in the test area, and expert knowledge about the production processes. The policy 
provided by the genetic algorithm sequences the jobs at each resource. Events in the simulation 
correspond to resources beginning work on a task and resources finishing tasks. Other events are 
added as necessary to control the simulation of the producUon process. 

Note that the search is not affected by the complexity of the scheduling problem being 
solved. The genetic algorithm can find solutions to classical problems and to problems with 
prcviously-unconsidered characteristics. The genetic algorithm can take advantage of complexity 
by including dispatching rules designed for use in that environment. 

5.4 Global Job Shop Scheduling 

In this section we will discuss the manufacturing process and scheduling needs of the 
semiconductor test area for which we are trying to create good schedules. As we will see, the 
problem is quite difficult. This will lead us into the description of the design, implementation, 
and contributions of our global job shop scheduling system. 

5.4. 1 The Semiconductor Test Process 

The manufacturing of semiconductors consists of many complex steps. This includes four 
primary activities: wafer fabrication, probe, assembly, and test. This research is concerned with 
the last facility. Although the routes of lots through the test process vary significantly over the 
many different types of products, general trends can be described (see Section 2.1 of this 
dissertation). 

The area under study tests commercial-use semiconductor devices and consists of two 
domains: one dedicated to Digital products and another to Analog products. We directed our 
work toward the Digital side, where there are over 1400 product lines. The test area has three 



188 

shifts per day. five days a week. The resources in the Digital side include nearly sixteen electrical 
test heads and a dozen brandcrs. The staffing on a normal shift consisted of nearly fifteen 
personnel in eight areas. The product mix changes continuously, and staffing and machine 
resources often change to rcfiect this. 

Although a typical product may have a route that consists of over 30 numbered operations, 
only a fraction of those are steps where significant time and resources are required. In our job 
shop model of the lest area, we concentrated on the following operations: electrical test (room, 
low, and high temperature), brand, bum-in, bum-in load and unload, visual-mechanical test, and 
document review. Due to the re-entrant nature of the process, an average lot will have twelve 
steps that need processing. 

Most of the operations in the semiconductor test area are electrical or physical tests, 
performed in an automated fashion or by hand. During these tests, each device in a lot must be 
examined. Thus, the processing times depend directly upon the size of the lot. Also, the products 
in the lest area have different package types. A package is the shell in which the semiconductor 
chip resides. These packages can be plastic or ceramic and come in many different sizes and 
styles. The package of a product also influences how the devices are tested. 

In the job shop model, a work center for each of the resources in the shop (except the bum- 
in ovens) is a tester, machine, or operator that needs to be scheduled. Each type of work center 
has a list of the operations that can be performed at the station. Distinct resources that perform 
the same operations are modelled as separate stations, each with a queue of jobs that next need 
processing at that station. These queues are sequenced by the dispatching rule for that station. 

Two unique operations in semiconductor testing are electrical test and bum-in. Electrical 
test operations have sequence-dependent setups, and bum-in is a bulk-service process. 

The sequence-dependent setups at electrical test are a result of the test requirements. First, 
a handler must be attached to the test head to automatically feed the devices in the lot. However, 
due to the physical attributes of the packages, different handlers arc required for different 
packages. Testing also occurs at various temperatures, which requires additional equipment. The 



189 

amount of setup is thus affected by the setup of the previous test, since It will be necessary to put 
into place new equipment only when the previous setup was different. 

The other unique operation is bum-in. At this operation, the devices in the lot are placed 
into one of a number of ovens for a fixed period of time. These times range from 24 hours to 
over 4 days. Many lots can be bumed-in at once, and the capacity constraint is more often on the 
availability of bum-in boards than on the space in the ovens. Additionally, after the boards are 
removed from the oven, the devices are unloaded from the boards, and the lot must undergo an 
electrical test within 96 hours to locate any faulty devices. The combination of bulk service, 
secondary capacity constraints, and operation deadlines requires special modeling. 

Access to bum-in is controlled by the bum-in load work center, since each lot must be 
loaded onto bum-in boards before being placed in the oven. If sufficient boards are not available, 
the lot cannot be processed. After bum-in load, the lot moves directly to the bum-in oven and 
begins the bum-in period. The factory control system provides information on which day the lot 
should be removed from bum-in. On that date, the lot is scheduled for unload, and the bum-in 
boards become available for another lot. 

As Lee et al. (1993) mention, the test area has five features that distinguish it from classical 
job shop scheduling: 

1. Sequence-dependent setup times and re-entrant product flows, 

2. Machines with different scheduling characteristics, 

3. Complex interactions between machines, 

4. Dynamic production environment, and 

5. Multiple, conflicting objectives. 

These characteristics make effective scheduling of the semiconductor test area a difficixlt 
task. They also encourage us to design a global scheduling system that can search for good 
solutions without being obstructed by complexity. 



190 

5.4.2 The Pn?viou.s Sclicdulint; System 

In this subsection we briefly discuss how scheduling was done previously in the test area 
using dispatching rules and some drawbacks to this system. (The development of this system is 
described in Lee ci al. 1993.) 

The test area was using a set of dispatching stations to sequence the lots awaiting 
processing at each work center at the beginning of the .shift. During the shift, this ordered list of 
lots was updated by using the dispatch station to resequence the loLs in the queue, since more lots 
may have arrived. The dispatching stations and rules are part of a software module called Short- 
Interval Scheduling (SIS). 

SIS is a component of WORKSTREAM, a product of Consilium, Inc. (Consilium, 1988). 
WORKSTREAM is the test area's computer-integrated manufacturing (CIM) system and is 
implemented on the corporate VAX mainframe. Transactions such as processing a lot or 
beginning a setup are logged into WORKSTREAM, which maintains information about the 
current status of each lot and each machine. This information is used by SIS to sequence the lots 
waiting for processing. 

In addition to WORKSTREAM, the company uses higher-level systems such as Activities 
Planning & Dispatching (AP/D) to match the production lots to customer orders and IMPReSS to 
determine the amount of product that each area of the company (including the test area) should be 
produced each week. All of these systems provide critical data about the lots to be processed and 
the characteristics of the test area. We will need this information to model the test area. 

While SIS has led to better scheduling in the test area, it has a number of disadvantages 
related to the structure and capabilities of the CIM system. The primary obstacle is that 
dispatching rules are making local decisions (even when they attempt to look-ahead or look- 
behind). Thus they are unable to know how their decisions affect the work at other areas in the 
test area. And they are unable to advantage of information that may lead to better dispatching 



191 

decisions. In addition, the dispatching rules arc unable to use information about processing and 
setup times. 

Since the implemented dispatching rules cannot use global information, we began to 
consider job shop scheduling procedures. While a number of optimization procedures have been 
suggested (see Section 2), these have concentrated on the classical job shop problem of 
minimizing makespan. In particular, the more well-known procedures use the disjunctive graph 
to represent the problem. Unfortunately, manufacturing environments like semiconductor lest 
area often have more complicated problems that require more complicated scheduling models. 

We wanted to make use of global information in a complex production process and to 
search for a better schedule. Therefore, we decided to implement the genetic algorithm for global 
scheduling. We described the primary characteristics of this procedure in Section 3. In the 
remainder of Section 4 we will describe the development of our global job shop scheduling 
system. 

5.4.3 Scheduling Needs 

Over the course of a number of years, the scheduling system in the semiconductor test area 
progressed from manual dispatching to an integrated rule-based decision support system. As we 
mentioned above, this system had significant limitations, since it was based on dispatching rules. 
However, the planners in the area need to know in what order the lots waiting at a station should 
be processed, and this system gave them this information. They would also like to know when 
these lots will be completed. 

In addition to these tactical decisions, the planners need to have some idea of how their 
limited resources (in both personnel and equipment) on the shop floor affect the performance of 
the shop in relation to meeting the shop goals. Finally, they need to measure the performance of 
the personnel on the floor. 

The managers of this test area have two objectives. The first is to meet customer due dates. 
The company stresses customer satisfaction, and the responsibility of the test area is to ship the 



192 

required number of parts to the customer by the requested time. The test area is measured on the 
number of delinquent line items, the number of customer orders that are not shipped on-time. 
Thus, the most important of the two primary objectives is to minimi/.c the numberof tardy jobs. 

The second objective is to test as much product as possible. This goal is both positively 
and negatively correlated with the first goal. If the area can test product more quickly, it is more 
likely to meet customer due dates. However, the push to increase the quantity tested can interfere 
with the need to process lots on-time (since the lots with the earliest due dates may be those with 
the largest processing times). At the time we were working on this project, the test area had extra 
capacity, so we considered the objective of minimizing llowtime to be a subordinate one. 

5.4.4 Scheduling System Design 

We have looked at some of the complexity that occurs in scheduling a semiconductor test 
area. These characteristics make the problem in the semiconductor test area much more difficult 
than the job shop problems previously considered. At the same time, however, the CIM systems 
in place are able to provide the type of area-wide information needed to create a schedule. 
Therefore, we are motivated to try a new approach: a global scheduling system that uses a genetic 
algorithm to find good schedules in the presence of shop floor complexity. In this section we will 
describe the basic design features. 

This system includes a simulation model of the test floor and an optimization procedure 
that can search for schedules using a genetic algorithm. The search finds a schedule that is better 
than any schedule that a predefined set of dispatching rules could create. This schedule specifies 
the order in which the lots should be processed and the times at which the operations should be 
done. 

The system can be used to react to unforeseen events that might occur during the course of 
a shift by including new information and producing a new schedule; for example, a machine may 
fail, or an important lot may arrive. The system also serves in a decision support manner, 
allowing the planners to determine the effects that changing resources has upon the schedule. 



193 

Through the use of fair processing limes in an accurate model, the schedule can be used as a 
target for the shift; the work completed by the shift personnel can be compared to the work on the 
schedule. 

The foundation for the system is the test area's extensive CIM system, which will provide 
the information necessary to model the test area. Finally, the global scheduling system is under 
the control of production planners, who use the computing power of the system to evaluate 
alternative plans and to create a detailed schedule for the shop floor. 

The most important component of a global job shop scheduling system is the model of the 
shop floor. Only with a valid model can a scheduling system create plans that match reality. For 
our project, the model was a deterministic simulation of the test area. It uses as input a set of 
resources that correspond to the equipment and staffrng of the test area, a set of jobs that 
correspond to the lots that need processing in the test area, and a set of dispatching rules that 
sequence the jobs at the resources. Thus, the model creates a schedule for the current scenario. 

This is the central relationship in the system. Because the schedule depends upon the 
dispatching rules, the optimization procedure in this global scheduling system is a search of the 
combinations of dispatching rules in order to find a good schedule (one that meets management 
goals efficiently). A genetic algorithm is employed to search over the rules, evaluating each set 
by running the simulation with those rules and measuring how well the schedule performed at 
keeping jobs on-time. This part of the system is called the Genetic Algorithm for Global 
Scheduling, and it is discussed in Section 5.3 of this chapter. 

5.4.5 Information Requirements 

The scheduling system makes use of data from a number sources inside and outside the test 
area's CIM system. In this subsection we will mention the types of information that are used in 
the system. See Figure 4 for a diagram of how the primary data structures interact. 



194 







LOT STATUS 










^ ' \ " 












NEW PRODUCTS 




DIGITAL 1 
LOTS 








J 




/ 


PROP 
FILE 












/ 




SHOP 
RESOURCES 








y 


/^ 


PROCESSING 
TIMES 




















\ 


JOBS ,/'^ 












CURRENT \ 


^ 




' BURN-IN 






SETTINGS 


\\ 




N 


V BOARDS 












^\ 


1 






\ \ 












\ \ 


1 




















RULES \ 


SHOP FLOOR 
SCHEDULE 




^ HOT LOTS 








^ 




DOWN MACHINES 












OOT-— 1 


^^ 






BRE 


AKS 











Figure 4. Data Structures 



Three general types of files can be described: data extracted from the CIM, data collected 
by the project team, and data entered by the user. The first category includes data that is fairly 
stable and data that constantly changes. Stable data includes information about the product 
routes. This Product-Operation (PROP) file matches each product to the operations that need to 
be performed. This file is updated weekly as new products are added to the product mix. Other 
files of extracted information list package types, bum-in board requirements, and tester 
requirements. 

The dynamic data is primarily the lot status information. The status of a lot changes as it 
undergoes different operations. Before each shift the CIM system takes a snapshot of the status 
for each lot in the test area. Our system extracts lot status information for each digital lot from 
this report. Although the status of a lot continues to change during the day, our system cannot sec 
the changes until the next report. 



195 

The project leum also collcclcd data on processing times and lest area resources. The 
collection of processing times will be discussed in Section 4.7. The resources files matches each 
type of resource (tester, brandcr) to the operations that it can process. 

Finally, the user controls other information needed for the scheduling system, including the 
current test area resources (how many of each type), the dispatching rules to use, the breaks 
schedule, the status of any down machines, and the arrival of any new hot lots. 

5.4.6 Implementation of Global Scheduling 

The implementation of the global scheduling system followed the design of the system and 
the collection of data sources. In this subsection we will describe how we implemented the 
system and how the test area creates schedules. 

After creating the scheduling model and the genetic algorithm off-line, we installed the 
basic programs on the corporate mainframe. We began testing the system and developing the 
utilities that collect the necessary job, shop, and process information. Working closely with the 
test area personnel, we began to run schedules each day. Feedback from these initial schedules 
led to improvements in all parts of the system. A technology transfer session formally introduced 
the system capabilities to the test area personnel, and soon they began to run the system 
themselves. The project team created user interface programs and documentation so that the test 
area would be able to use, understand, and maintain the system. 

The scheduler perfomis shift scheduling for the Digital side of the test area. Output from 
the system includes the shift schedule, which lists each work center, the lots to be scheduled, and 
the approximate start and finish times for each operation. Also available are post-shift 
performance reports that compare the production of the test area to the schedule. 

User interface programs make it easy for the users to collect and modify data, create a 
schedule, view the output, and create performance reports. 



196 

Creating a schedule consists of a number of steps. First, the current status of all of the lots 
in the lest area is determined from the prc-shift lot status report. Non-digital lots and lots in a 
stores operation arc ignored. 

Second, the lot status information is combined with the PROP file, which converts lots into 
jobs. The job consists of relevant lot information and a number of operations. The lot 
information includes product class, due date, and lot quantity. For each operation a processing 
time is computed along with a remaining cycle lime. 

Third, the user must check the current shop settings on resources, dispatching rules, and 
breaks. The user is shown the default settings and has the opportunity to make any changes. 

Fourth, the schedule is created using the job, shop, and process information collected to this 
point. This schedule can be created using the genetic algorithm, which searches over 
combinations of dispatching rules, or the dispatching rules which the user chose. In the latter 
case, no search is performed; the scheduling model uses the user's rules and outputs the schedule 
that these rules yield. 

The genetic algorithm begins with a population of randomly-created policies. The genetic 
operators shift the population towards more successful policies (measured on their ability to 
create a schedule with more on-time jobs). The algorithm stops after a fixed period of time; this 
time was selected after experimentation into the trade-off between schedule quality and search 
effort. 

In addition to creating a shift schedule, the system creates a number of other files that are 
used to drive pcrfonmance reports. There are three performance reports: shift summary, daily 
summary, and daily detailed. The summary reports compare what was done with what was 
scheduled. The scheduled operations for each machine are compared to the operations that have 
been those lots. The detailed report compares processing times. The scheduled processing times 
are compared to the actual times that are derived from daily lot history files. 

If the user makes no changes to the default shop settings, the entire process can take as little 
as ten minutes. This compares to the 15 minutes necessary in SIS to sequence just the lots 



197 

waiting at one work center. Therefore, the process can be done as part of the prc-shift planning, 
and the user has ample opportunity to update any data and to experiment with different shop 
settings. 

The system is currently being used by the test area personnel, who will soon be expanding 
the system to include the Analog side of the floor. After discussing some of the issues that our 
implementation raised, we will describe the contributions of our system. 

5.4.7 Implementation Issues 

Researchers engaged in projects like this one often encounter difficulties that are 
considered in no classroom and occasionally learn things that are in no textbook. 

Processing times . One primary problem was a result of our attempt to model an uncertain 
process with a deterministic procedure. We wanted to use processing times that were realistic but 
that also set fair targets for the test floor. Thus, we needed good estimates of what the processing 
times should be. The collection of these estimates was an important concern. We had historical 
data from the factory control system, which monitors when each lot begins and ends each 
operation. We began with an average for each operation, but this average ignored the variability 
in processing time due to lot quantity. We then took the historical data for the subset of products 
and fitted a linear regression to the data in an effort to predict processing time from lot size. The 
regression was run for different package types in order to remove another source of variability. 

Perfection . We learned that perfection is an unattainable goal in a setting as complex as 
semiconductor test. However, we also learned that falling short of perfection is sufficient if our 
system improves the ability of the facility to satisfy customer demand efficiently. From the 
beginning, management knew (better than the project team did) that we could not hope to capture 
all of the activities that occur. This attitude allowed us to build a significant model instead of 
being overwhelmed by the complexity of finding an optimal solution. With modeling and 
controlling the test area perfectly beyond our reach, we concentrated on developing a system 



198 

which meets ihc needs of the test area planners and provides them with a tool which they can use 
to intelligently manage their facility. 

Simplicity . A significant feature of the implemented system is the ability of production 
planners to modify data related to resources and other factors. This called for a number of 
modules that could manipulate the data without requiring undue effort from the planners. These 
modules were user-friendly (easy to understand and fail-safe), flexible routines that the planners 
felt comfortable using. We feel that this has contributed to the success of the implementation. 

Timeliness . Next to the estimates of processing times, accurate information about lot status 
was the hardest data to gather. Since there are hundreds of lots in the facility's inventory, 
determining which lots are wailing at which stations is not a trivial task. The system depends 
upon WIP extracts that were run from the factory control system before each shift. Although the 
planners have the ability through the factory control system to check on the status of individual 
lots, it was not possible to develop procedures to gather the status of the lots during the middle of 
the shift. 

Because the system could not gather the current lot status during the shift, it could only 
react to unforeseen events by rebuilding the original schedule from the beginning of the shift and 
incorporating the new information about machine breakdowns and lot arrival. Searches to find 
good schedules were not possible. 

Optimiy.ation procedure . A number of other researchers continue to work on ways to solve 
the job shop scheduling problem. Although we cannot guarantee that our heuristic space genetic 
algorithm is the best procedure for finding a good shop schedule, a search over dispatching rules 
seemed to be an ideal approach for the needs and requirements that we faced, however. 

The system makes use of the scheduling model and a separate genetic algorithm program. 
The two procedures are distinct modules developed and modified independently. This gave us a 
great deal of ficxibility as we began to test and implement the scheduling system. We chose the 
genetic algorithm to gain the power of its parallelism and its simplicity and to avoid the problems 



199 

of local searches. The test area personnel could understand how policies combined to form new 
policies and how these policies could be used to create schedules. 

Due to the impossibility of fmding an optimal .schedule to the dynamic job shop scheduling 
problem, it is sufficient for our heuristic space search (an approximation algorithm) to determine 
a quality schedule quickly. 

5.4.8 Contributions of Global Scheduling 

In this section we will discuss the benefits of our implementation of the global scheduling 
system. While primarily unquantifiable, the gains are real. 

The test area now has a tool that can substantially improve scheduling with a combination 
of global information, detailed scheduling model, genetic search for good schedules, reaction to 
unforeseen events, and short-term performance reports. 

The global system has a number of strengths compared to SIS, the previous scheduling 
system. As a centralized procedure, it can make use of information from around the test area 
including processing times, queue lengths, current setups, resource availability, and job arrivals. 
The genetic algorithm searches for a schedule that has more on-time lots than a schedule created 
by any fixed set of dispatching rules. 

As a shift scheduler, the system gives the test area a plan that shows how work at one area 
depends upon work at another and that can be used to measure the performance of that shift. In 
fact, the ability to accurately model the test area and compute a shift schedule was just as 
important to the test area as the ability to find better schedules. The simulation component of the 
system allows the test area plaimers to forecast how modifying the level of available resources 
will affect the output of the test area. The system can also react to certain unforeseen events that 
may necessitate a change in the schedule. 

As mentioned earlier, the product mix in the semiconductor test area is constantly 
changing. This variety is a significant factor on the lest area performance. Thus, we are unable 
to measure any long-tcnm quantitative benefits. The test area managers have expressed their 



200 

confidence that the system will lead to improvements in the performance of the test area through 
improved schedules and planning tools. 

5.5 Chapter Summary 

In this chapter we have described the development of a global scheduling system that uses 
a genetic algorithm to find good schedules. This system has been successfully implemented in a 
semiconductor test area. Controlling the test area is a complex, dynamic job shop scheduling 
problem where it is difficult to meet the management objectives of satisfying customer demand 
on-time and increasing throughput. Our scheduling system uses the extensive data available in 
the CIM databases in order to simulate the operation of the test area. This system uses a genetic 
algorithm to search for combinations of dispatching rules that yield schedules that are better than 
the sequencing that could be done with fixed dispatching rules. The primary practical 
accomplishment of this research is the implementation of an advanced job shop scheduling 
system in a manufacturing environment. Moreover, this implementation makes use of a new 
heuristic procedure that searches the combinations of dispatching rules to find a good schedule. 
Thus it is able to adapt each shift to changing conditions in the jobs to be scheduled and the shop 
resources. 

This approach could be extended to any manufacturing area that has a complicated shop 
scheduling problem and a computer-integrated factory control system that can supply the 
necessary data for such a global scheduling system. In fact, the semiconductor manufacturing 
firm where we have implemented the system is considering exporting this system to other areas. 
Additionally, other optimization techniques may be u.scful in finding good schedules. 



CHAPTER 6 
SUMMARY AND CONCLUSIONS 



This dissertation has reported on a number of production scheduling problems that were 
motivated by considering the testing of semiconductors. The research into these topics, 
summarized below, adds to the body of knowledge about scheduling. This work is especially 
relevant to the study of the harder and broader problem of job shop scheduling. Benefits of the 
work include results on specific one-machine class scheduling problems, results on three-machine 
look-ahead problems, and the use of genetic algorithms and new search spaces on different types 
of scheduling problems. 

6.1 One-machine Class Scheduling Problems 

The research on the three one-machine class scheduling problems has yielded a number of 
results. Most notably, the problem space genetic algorithm is a robust tool for finding high- 
quality solutions to difficult scheduling problems. 

For the problem of minimizing total flowtime subject to deadline constraints (CFTS), we 
developed an multiple-pass heuristic that makes use of an optimal property for jobs in the same 
class. By considering the effect of wasted setup time, it is able to find reasonable solutions. We 
can improve upon these solutions with a problem space genetic algorithm that adjusts the job 
deadlines in order to create better schedules. 

For the problem of minimizing the number of tardy jobs where the jobs have non-zero 
rclca.se dates (CSRDD), we extend a non-setup procedure to create a heuristic for the class 
scheduling problem. The average performance of the heuristic is good compared to a number of 
other dispatching rules. A problem space genetic algorithm is able to find better solutions on 
some especially difficult problems where the heuristic performs poorly. 

201 



202 

Our extended heuristics for the problem of minimizing the total flowtime of jobs with non- 
zero release dales (FTSRD), were outclassed by a decomposition procedure and a problem space 

genetic algoriilim. \Vc developed a number of dominance properties for use in a branch-and- 
bound technique. 

6.2 Look-ahead Scheduling 

The three-machine problems that have been studied show that look-ahead rules can perform 
better than standard dispatching rules. 

For the problem of minimizing makespan, the interleaving of the Johnson sequences is able 
to provide near-optimal solutions. The worst case relative error of this heuristic is fifty percent. 
There are, however, special cases of the problem that can be solved in polynomial time. 

The problem of minimizing the total flowtime is more difficult. There do exist special 
cases where the lower bounds can be achieved. Look-ahead rules that consider the queue at the 
second-stage machines are able to find good solutions. 

The last problem was that of minimizing the number of tardy jobs. Again, special cases 
exist where optimal solutions can be easily found. Look-ahead rules were able to find better 
schedules than other sequencing rules. A problem space genetic algorithm found improved 
solutions. 

6.3 Searching for Job Shop Schedules 

This research has investigated the development of a procedure for the job shop scheduling 
problem. The genetic algorithm makes u.se of known heuristics (dispatching rules) but increases 
their effectiveness by searching over combinations of rules to find a good schedule. This 
procedure provides a way to find good schedules under any objective function and in any 
scheduling environment, since it makes use of a detailed shop floor scheduler. These 
characteristics make this procedure unique. 



203 

In addition, this procedure has been implemented as part of a global scheduling system for 
a semiconductor test area. In this environment, it creates real-time schedules for the next shift 
using information about the current status of the lots, the current resources in the shop, and the 
manufacturing process. The system includes not only the simulation model and the genetic 
algorithm but also utility functions for the collection of data from multiple sources and the 
generation of performance reports. In addition, the system can respond to unforeseen events, and 
the test area planners can use the system to determine the effect of changing the shop resources. 

6.4 Conclusions 

The scheduling of a manufacturing process is a complicated problem. The static job shop 
scheduling problem is incredibly difficult to solve, and no system has been able to optimize the 
scheduling of an entire dynamic job shop, which is the environment present in many 
manufacturing facilities. Thus, continued research into procedures that can find good schedules 
is necessary. 

Many researchers have studied thiis problem, introducing systems which range in scope 
from company-wide planning to machine scheduling. This research is concerned with efforts at 
the level of the shop floor and machine. 

This research investigated production scheduling problems that are motivated by 
semiconductor test operations and are expected to hold widely in other production environments. 
Of particular concern are those problems that occur in the testing of semiconductor devices. Let 
us now take a moment to provide some pcrsj^cctive. 

This dissertation is concerned with two types of operations research: management science 
and management engineering (the terms of Corbett and Van Wassenhove, 1993). Management 
science is the discovery of new results that add to the body of knowledge about a subject. 
Management engineering (a less active area of the field) is the solution of a practical problem by 
modifying existing tools or by using existing tools in original ways. 



204 

The scicntinc coniribulions arc clear. While much research in the areas of scheduling and 
semiconductor manufacluring has been pcrlormed. this research investigated a number of 
previously unstudied problems and methods. Our research into these problems has yielded a 
number of useful properties and effective heuristics. 

This research has shown that smarl-and-lucky searches and the new problem and heuristic 
spaces can be used for the problems under consideration. Problem space genetic algorithms can 
find good solutions to machine scheduling problems. For the job shop scheduling problem, a 
genetic algorithm can search combinations of dispatching rules and u.se a shop floor simulation to 
determine a good schedule. 

Additionally, this research lies together separate problems in an effort to improve the 
scheduling of the manufacturing process being studied. This is an engineering question. The 
cooperation of the semiconductor test facility motivated research into the problems of an actual 
system and provided an opportunity to implement our solution procedures. (This docs not 
preclude the potential of our approach to solve problems in other manufacturing environments.) 

Our global job shop scheduling system (with its detailed simulation model and heuristic 
space genetic algorithm) is a new technique for the problem of creating good shift schedules for a 
semiconductor test area in real-time. Since look-ahead dispatching rules can be more effective 
than standard rules, the results of the work into the three-machine subproblems have been used as 
dispatching procedures for the shop floor and as pan of the job shop scheduling procedure. 

This research opens some chapters of scheduling that need to further pursued. While the 
problem space genetic algorithm is a robust procedure that finds good solutions, better solutions 
to particular problems may be achievable through the use of solution-specific heuristics that can 
improve the schedules that the genetic algorithm constructs. Also, it may be possible to create 
searches that combine different spaces for other types of combinatorial problems. 

The set of class scheduling problems includes a number of other interesting problems; so 
does the set of look-ahead problems. Even more interesting is the combination of these problems. 



205 

Look-ahead class scheduling problems may yield more insights into the job shop scheduling 
problem. 

There also exist issues in global job shop scheduling that still need to be addressed: job 
release, resource planning, and uncertainty in the manufacturing process. It is difficult to obtain 
satisfactory solutions in these circumstances using current scheduling techniques. 

The general approach of this research (problem and heuristic space searches) can be applied 
to almost any difficult problem. It may be profitable to consider this approach for problems 
where good solutions are hard to find. 

Why investigate production scheduling problems motivated by semiconductor 
manufacturing? Because organizations and individuals often have difficulty meeting their goals 
efficiently, and this dissertation, which has applications beyond the problems contained herein, 
offers some ways to solve people's problems. 



REFERENCES 



Aarts, E.H.L., and P.J.M. van Laarhovcn, "Slalislical cooling: a general approach lo 

combinatorial optimization problems," Philips Journal of Research, Vol. 40, p. 193, 1985. 

Adachi, T., C.L. Moodie, and J.J. Talavagc, "A paltcm-recognition-bascd method for controlling 
a multi-loop production system," InternationalJournal of Production Research, Vol. 26, 

pp. 1943-1957, 1988. 

Adachi, T., C.L. Moodie, and J.J. Talavagc, "A rule-based control method for a multi-loop 
production system," Artificial Intelligence in Engineering, Vol. 4, pp. 1 15-125, 1989. 

Adams, J., E. Balas, and D. Zawack, "The shifting bottleneck procedure for job shop scheduling," 
Management Science, Vol. 34, pp. 391-401, 1988. 

Adelsbcrger, H.H., and J.J. Kanet, "The leitstand - a new tool in computer-integrated 

manufacturing," Production and Inventory Management, Vol. 32, No. 1, pp. 43-48, 1991. 

Adler, L., N. Fraiman, E. Kobacker, M. Pinedo, J.C. Plotnicoff, and T.-P. Wu, "BPSS: a 

scheduling support system for the packagin industry," Operations Research, Vol. 41, 
No. 4, pp. 641-648, 1993. 

Ahmadi, J.H., R.H. Ahmadi, S. Dasu, and C.S. Tang, "Batching and scheduling jobs on batch and 
discrete processors," Anderson Graduate School of Management, UCLA, 1989. 

Ahmadi, R. H., and U. Bagchi, "Improved lower bounds for minimizing the sum of completion 
limes of n jobs over m machines in a flow shop," European Journal of Operational 
Research, Vol. 44, pp. 331-336, 1990. 

Ahn, B.-H., and J.-H. Hyun, "Single facility multi-class job scheduling," Computers and 
Operations Research, Vol. 17, No. 3, pp. 265-272, 1990. 

Atherton, R.W., "Factory scheduling using simulation models," Proceedings of the Third 

Symposium on Automated Integrated Circuit Manufacturing, Electrochemical Society, 
Princeton, New Jersey, 1988. 

Atherton, R.W., and M.A. Pool, "Validated simulation models for factory control," International 
Semiconductor Manufacturing Science Symposium, Scmicon West, Burlingame, 
California, May 22-24, 1989. 

Bagchi, U., and R.H. Ahmadi. "An improved lower bound for minimizing weighted completion 
times with deadlines." Operations Research, Vol. 35. pp. 311-313, 1987. 

Bai, X., and S.B. Gershwin "A manufacturing scheduler's perspective on semiconductor 
fabrication," VLSI Memo No. 89-518, Massachusetts Institute of Technology, 1989. 



206 



207 



Bai, S.X., and S.B. Gershwin, "Scheduling manufacturing systems with work-in-process 
inventory, " Proceedings, Twenty-ninth IEEE Conference on Decision and Control, 
Honolulu, Hawaii, December, 1990. 

Bai, S.X., and S.B. Gershwin, "Real-time production scheduling for a wafer fabrication facility," 
Research Report 92-19, Department of Industrial and Systems Engineering, University of 
Florida, Gainesville, Rorida, 1992. 

Bai, X., N. Srivatsan, and S.B. Gershwin, "Hierarchical real-lime scheduling of a semiconductor 
fabrication facility," Proceedings, Ninth IEEE International Electronics Manufacturing 
Technology Symposium, Washington, D.C., October 1-3, 1990. 

Baker, K.R., "Sequencing rules and due-date assignments in a job shop," Management Science, 
Vol. 30, pp. 1093-1104, 1984. 

Baker, K.R., Elements of Sequencing and Scheduling, Amos Tuck School of Business 
Administration, Dartmouth College, Hanover, New Hampshire, 1992. 

Baker, K.R., and J.W.M. Bcrtrand, "A dynamic priority rule for sequencing against due-dales," 
Journal of Operations Management, Vol. 3, pp. 37-42, 1982. 

Baker, K.R., and J.J. Kanet, "Job shop scheduling with modified due dales," Journal of 
Operations Management, Vol. 4, pp. 1 1-22, 1983. 

Barnes, J.W., and J.B. Chambers, "Solving the job shop scheduling problem using labu search," 
Technical Report OPR91-06, Graduate Program in Operations Research, University of 
Texas at Austin, 1991. 

Barnes, J.W., and M. Laguna, "Solving the multiple-machine weighted flow lime problem using 
tabu search," Technical Report Scries, Graduate Program in Operations Research, 
University of Texas, Auslin, 1992. 

Bean, J.C., "Genetics and random keys for sequencing and optimization," Technical Report 92- 
43, Department of Industrial and Operations Engineering, University of Michigan, Ann 
Arbor, Michigan, 1992. 

Bensana, E., G. Bel, and D. Dubois, "OPAL: a multi-knowledgc-based system for industrial job- 
shop scheduling," International Journal of Production Research, Vol. 26, No. 5, pp. 795- 
819, 1988. 

Bhaskaran, K., and M. Pincdo, "Dispatching," Chapter 83, Handbook of Industrial Engineering, 
G. Salvendy, cd., J. Wiley, New York, 1991. 

Bianco, L., and S. Ricciardelli, "Scheduling of a single machine to minimize total weighted 

completion lime subject to release dates," Naval Research Logistics Quarterly, Vol. 29, 
No. l.pp. 151-161, 1982. 

Biegel, J.E., and J.J. Davem, "Genetic algorithms and job shop scheduling," Computers and 
Industrial Engineering, 19, pp. 81-91. 1990. 

Bitran, G.R., and D. Tirupati, "Planning and scheduling for epitaxial wafer production facilities," 
Operations Research, Vol. 36, pp. 34-49, 1988a. 



208 

Bitran, G.R., and D. Tirupati, "Dcvclopmcnl and implementation of a scheduling system for a 
wafer fabrication facility," Operations Research, Vol. 36, pp. 377-395, 1988b. 

Blackstonc, J.H., Jr., D.T. Phillips, and G.L. Hogg, "A state-of-the-art survey of dispatching rules 
for manufacturing job shop operations," International Journal of Productions Research, 
Vol. 20, pp. 27-45, 1982. 

Bruno, J., and P. Downey, "Complexity of task sequencing with deadlines, set-up times and 
changeover costs," SI AM Journal of Computing, Vol. 7, No. 4, pp. 393-404, 1978. 

Buffa, E. S., Production Inventory Systems: Planning and Control, Richard D. Irwin. Inc., 
Homewood, Illinois, 1968. 

Barman, D.Y., F.J. Gurrola-Gal, A. Nozari. S. Sathaye, and J.P. Silarik. "Performance analysis 
techniques for IC manufacturing lines," AT&T Technical Journal, Vol. 65, pp. 46-57, 
1986. 

Bums, F., and J. Rooker, "Extensions and comments regarding special cases of the three machine 
flow-shop problem," Naval Research Logistics Quarterly, Vol. 22, pp. 811-817, 1975. 

Cemy, V., "Thermodynamical approach to the traveling salesman problem: an efficient 

simulation algorithm," Journal of Optimization Theory and Applications, Vol. 45, p. 41 , 
1985. 

Chambers, R.J., R.L. Carraway, T.J. Lowe, and T.L. Morris, "Dominance and decomposition 
heuristics for single machine scheduling," Operations Research, Vol. 39, No. 4, pp. 639- 
647, 1991. 

Chen, H., J.M. Harrison, A. Mandclbaum, A. Van Ackere, and L.M. Wein, "Empirical evaluation 
of a queueing network model for semiconductor wafer fabrication," Operations Research, 
Vol. 36, pp. 202-215, 1988. 

Cleveland, G., and S. Smith, "Using genetic algorithms to schedule flow shop releases," in 

Proceedings of the Third International Conference on Genetic Algorithms, J.D. Schaffer, 
ed., Morgan Kaufmann, San Mateo, California, 1989. 

Coffman, E.G., A. Nozari, and M. Yannakakis, "Optimal scheduling of products with two 

subassemblies on a single machine," Operations Research, Vol. 37, No. 3, pp. 426-436, 
May- June, 1989. 

Conway, R.W., "Priority dispatching and job lateness in a job shop," Journal of Industrial 
Engineering, Vol. 16, pp. 228-237, 1965. 

Conway, R.W., W.L. Maxwell, and L.W. MiUer. Theory of Scheduling, Addison- Wesley, 
Reading, Massachusetts, 1967. 

Corbett, C.J., and L.N. Van Wassenhove, "The natural drift: what happened to operations 
research?" Operations Research, Vol. 41, No. 4, pp. 625-640, 1993. 

Davis, L., "Job shop scheduling with genetic algorithms," in Proceedings of an International 
Conference on Genetic Algorithms and their Applications, J. Grefenstelte, ed., Lawrence 
Eribaum A.s.socialcs, Hillsdale, New Jersey, 1985. 

Davis, L., ed.. Genetic Algorithms and Simulated Annealing, Pitman Publishing, London, 1987. 



209 

Davis. L., cd.. Handbook of Genetic Algorithms, Van Nosirand Rcinhold. New York, 1991 . 

Day, J. E. and M. P. Hoitcnslcin, "Review of sequencing research," Naval Research Logistic 
Quarterly, Vol. 17, pp. 1 1-39, 1970. 

Dayhoff, J.E., and R.W. Allicrton, "Signature analysis: simulation of inventory, cycle time, and 
throughput trade-olTs in wafer fabrication," IEEE Transactions on Components. Hybrids, 
and Manufacturing Technology, Vol. 9, pp. 498-507, 1986a. 

Dayhoff, J.E., and R.W. Alherion, "Signature analysis of dispatch schemes in wafer fabrication," 
IEEE Transactions on Components, Hybrids, and Manufacturing Technology, Vol. 9, pp. 
518-525, 1986b. 

Dayhoff, J.E., and R.W. Atherton, "A model for wafer fabrication dynamics in integrated circuit 
manufacturing," IEEE Transactions on Systems, Man. and Cybernetics, Vol. 17, pp. 91- 
100, 1987. 

Dessouky, M.I., and J.S. Deogun, "Sequencing jobs with unequal ready times to minimize mean 

now time," SIAM Journal on Computing, Vol. 10, No. 1, pp. 192-202, 1981. 

Dobson, G., U.S. Karmarkar, and J.L. Rummel, "Batching to minimize flow times on one 
machine," Management Science, Vol. 33, No. 6, pp. 784-799, June, 1987. 

Dobson, G., U.S. Karmarkar, and J.L. Rummel, "Batching to minimize flow times on parallel 
heterogeneous machines," Management Science, Vol. 35, No. 5, pp. 607-613, May, 1989. 

Emmons, H., "One machine sequencing to minimize mean flow time with minimum number 
tardy," Naval Research Logistics Quarterly, Vol. 22, pp. 585-592, 1975. 

Faaland, B., and T. Schmitt, "Cost-based scheduling of workers and equipment in a fabrication 
and assembly shop," Operations Research, Vol. 41, No. 2, pp. 253-268, 1993. 

Fisher, H., and G.L. Thompson, "Probabilistic learning combinations of local job-shop scheduling 
rules," in Industrial Scheduling, J.F. Muth and G.L. Thompson, eds., Prentice-Hall, Inc., 
Englewood Cliffs, New Jersey, 1963. 

Fordyce, K., R. Dunki-Jacobs, B. Gerard, R. Sell, and G. Sullivan, "Logistics Management 

System: an advanced decision suport system for the fourth decision tier dispatch or short- 
interval scheduling," Production and Operations Management, Vol. 1 , pp. 70-85, 1992. 

Fox, B. R., and M. B. McMahon, "Genetic operators for sequencing problems," Plaitning and 
Scheduling Group, McDonnell Douglas Space Systems, Houston, Texas, 1990. 

Fox, M.S., and S.F. Smith, "ISIS - a knowledge-based system for factory scheduling," Expert 
Systems, Vol. 1, No. 1, pp. 25-49, 1984. 

Fry, T.D., P.R. Philipoom, and J.H. Blackstone, "A simulation study of processing time 
dispatching rules," Journal of Operations Mcmagement, Vol. 7, pp. 77-92, 1988. 

Garey, M.R., and D.S. Johnson, Computers and Intractability: a Guide to the Theory ofNP- 
Completeness, Freeman, San Francisco, 1979. 

Garey, M. R., D. S. Johnson, and R. Sethi, "The complexity of flowshop and jobshop 
scheduling," Mathematics of Operations Research, Vol. 1. pp. 1 17-129, 1976. 



210 

Gazmuri, P.G., "Probabilistic analysis of a machine scheduling problem," Mathematics of 
Operations Research. Vol. 10, No. 2. pp. 328-339, 1985. 

Glassey, C.R., and R.G. Pctrakian, "The use of bottleneck starvation avoidance with queue 

predictions in shop floor control," Research Report ESRC 89-23, University of California, 
Berkeley, 1989. 

Glassey, C.R., and M.G.C. Resende, "Closed-loop job release control forvlsi circuit 

manufacturing," /£££ Transactions on Semiconductor Manufacturing, Vol. 1, pp. 36-46, 
1988a. 

Glassey, C.R., and M.G.C. Resende, "A scheduling rule for job release in semiconductor 
fabrication," Operations Research Letters, Vol. 7, pp. 213-217, 1988b. 

Glover, F., "Heuristics for integer programming using surrogate constraints," Decision Sciences, 
Vol. 8, No. l,pp. 156-166, 1977. 

Glover, F., "Tabu Search - Part I," ORSA Journal on Computing, Vol. 1, pp. 190-206, 1989. 

Glover, F., "Tabu Search - Part II," ORSA Journal on Computing, Vol. 2, pp. 4-32, 1990. 

Glover, F., E. Taillard, and D. de Werra, "A user's guide to tabu search," Graduate School of 
Business, University of Colorado, Boulder, Colorado, 1991. 

Goldberg, D.E., Genetic Algorithms in Search. Optimization, and Machine Learning, Addison- 
Wesley, Reading, Massachusetts, 1989. 

Golovin, J.J., "A total framework for semiconductor production planning and scheduling," Solid 
State Technology, pp. 167-170, May, 1986. 

Gong, L., and H. Matsuo, "Stabilizing work-in-process and smoothing production in a production 
system with random yield," Graduate School of Business, University of Texas. Austin, 
May, 1990a. 

Gong, L., and H. Matsuo, "A control policy for a manufacturing system with random yield and 
rework," Graduate School of Business, University of Texas, Austin, September, 1990b. 

Gonzalez, T., and S. Sahni, "Flow.shop and jobshop schedules: complexity and approximation," 
Operations Research, Vol. 26. pp. 36-52, 1978. 

Grabowski, J., E. Skubalska, and C. Smutnicki, "On flow shop scheduling with release and due 
dates to minimize maximum lateness," Journal of the Operational Research Society, 
Vol. 34, pp. 615-620, 1983. 

Graves. S.C. H.C. Meal, D. Stefek, and A.H. Zcghmi, "Scheduling of re-entrant flow shops," 
Journal of Operations Management, Vol. 3, pp. 197-207, 1983. 

Green, G.I.. and L.B. Appcl, "An empirical analysis of job shop dispatch mle selection," Journal 
of Operations Management, Vol. l,pp. 197-203, 1981. 

Gupta. J.N.D., "Optimal schedules for single facility with classes," Computers and Operations 
Research, Vol. 1 1, pp. 409-413, 1984. 



211 

Gupla. J.N.D., "Single facility scheduling with multiple job classes," European Journal of 
Operational Research, Vol. 8. pp. 42-45, 1988a. 

Gupla. J.N.D., "Two-stage, hybrid llowshop scheduling problem," Journal of the Operational 
Research Society, Vol. 39, No. 4. pp. 359-364, 1988b. 

Gupta, J.N.D., and E.A. Tunc, "Schedule for a two-stage hybrid llowshop with parallel machines 
at the second stage," International Journal of Production Research, Vol. 29, No. 7, 
pp. 1489-1502, 1991. 

Hadavi, K., and K. Voigt, "An integrated planning and scheduling environment," Proceedings 
Simulation and Artificial Intelligence in Manufacturing, Society of Manufacturing 
Engineers, Long Beach, California, October 14-16, 1987. 

Hadavi, K., W.L. Hsu, T. Chen, and C.N. Lee, "An architecture for real time distributed 
scheduling," working paper, Siemens Corporate Research, 1991. 

Hariri, A. M. A., and C. N. Potts, "An algorithm for single machine sequencing with release dates 
to minimize total weighted completion time," Discrete Applied Mathematics, Vol. 5, 
pp. 99-109, 1983. 

Hariri, A. M. A., and C. N. Potts, "A branch and bound algorithm to minimize the number of late 
jobs in a permutation llow-shop," European Journal of Operational Research, 38, pp. 228- 
237, 1989. 

Harrison, J.M., C.A. HoUoway, and J.M. Patell, "Measuring delivery performance: a case study 
from the semiconductor industry," presented at the "Measuring Manufacturing 
Performance" colloquium, Harvard Business School, Cambridge, Massachu.setts, January 
25-26, 1989. 

Herrmann, J.W., C.-Y. Lee, and J.L. Snowdon, "A classification of static scheduling problems," 
in Complexity in Numerical Optimization, P.M. Pardalos, ed., pp. 203-253, World 
Scientific, River Edge, New Jersey, 1993. 

Ho, J.C, "Minimizing the number of tardy jobs with two job classes," Division of Business, 
Northeast Missouri State University, 1992. 

Holland, J.H., Adaptation in Natural and Artificial Systems, University of Michigan Press, Ann 
Arbor, Michigan, 1975. 

Holloway, C.A., and R.T. Nelson, "Job shop scheduling with due dates and variable processing 
times," Management Science, Vol. 20, pp. 1264-1275, 1974. 

Ignall, E., and L. Schrage, "Application of the branch and bound technique to some flow-shop 
scheduling problems," Operations Research, Vol. 15, pp. 4(X)-412, 1965. 

Jackson, J.R., "Scheduling a production line to minimize maximum tardiness," Research Report 
43, Management Science Research Project, University of California, Los Angeles, 1955. 

Jackson, J.R., "Networks on waiting lines," Operations Research, Vol. 5, 1967. 

Jacobs, F.R., "OPT uncovered: concepts behind the system," Industrial Engineering, Vol. 16, 

No. 10, pp. 32-41, 1984 



212 

Johnson, S.M., "Optimal two- and thrcc-siagc production schedules with setup times included," 
Naval Research Logistics Quarterly, Vol. 1, pp. 61-68, 1954. 

Kanct, J.J., and J.C. Hayya, "Priority dispatching with operation due-dates in a job shop," Journal 
of Operations Management, Vol. 2, pp. 155-163, 1982. 

Kirkpatrick, S., CD. Gelatt, and M.P. Vecchi, "Optimization by simulated annealing." Science, 
Vol. 220, p. 671, 1983. 

Kisc, H., T. Ibaraki, and H. Mine, "A solvable case of the one-machine scheduling problem with 
ready and due times", Operations Research, Vol. 26, pp. 121-126, 1978. 

Kohler, W.H., and K. Steiglitz, "Exact, approximate, and guaranteed accuracy algorithms for the 
flow-shop problem n/2/F/Favg," Journal of the Association for Computing Machinery, 
Vol. 22, pp. 106-114, 1975. 

Koulamas, C.P., and M.L. Smith, "Look-ahead scheduling for minimizing machine interference," 
International Journal of Productions Research, Vol. 26, pp. 1523-1533, 1988. 

Krone, M. J., and K. Steiglitz, "Heuristic-programming .solution of a flowshop-scheduling 
problem," Operations Research, Vol. 22, pp. 629-638, 1974. 

Kubiak, W., S.X.C. Lou, and Y.M. Wang, "Mean flow time minimization in re -entrant job shops 
with hub," Faculty of Management, University of Toronto, July 17, 1990. 

van Laarhoven, P.J.M., E.H.L. Aarls, and J.K. Lenstra, "Job shop scheduling by simulated 
annealing," Report OS-R8809, Centre for Mathematics and Computer Science, 1988. 

Lageweg, B. J., J. K. Lenstra, and A. H. G. Rinnooy Kan, "A general bounding scheme for the 
permutation flow-shop problem," Operations Research, Vol. 26, No. 1, pp. 53-67, 1978. 

Laguna, M., J.W. Barnes, and F. Glover, "Tabu search methods for a single machine scheduling 
problem," Technical Report Series, Graduate Program in Operations Research, University 
of Texas, Austin, 1989. 

Laguna M., and F. Glover, "Integrating target analysis and tabu search for improved scheduling 
systems," Graduate School of Business, University of Colorado, Boulder, Colorado, 1991. 

Lawler, E.L., "Scheduling a single machine to minimize the number of late jobs," Preprint, 
Computer Science Division, University of California, Berkeley, 1982. 

Leachman, R.C., "Preliminary design and development of a corporate-level production planning 
system for the semiconductor industry," Operations Research Center, University of 
California, Berkeley, Febmary, 1986. 

Leachman, R.C., M. Solorzano, and C.R. Glassey, "A queue management policy for the release 
of factory work orders," Research Report 88-19, Engineering Systems Research Center, 
University of California at Berkeley, 1988. 

Leachman, R.C., and V.S. Sohoni, "Automated shift scheduling as a tool for problem 
identification and people management in semiconductor factories," University of 
California, Berkeley, California. 



213 

Lee, C.-Y., T.C.E. Cheng, and B.M.T. Lin, "Exact and approximate solutions to the 3-machine 
assembly -type llowshop scheduling problem to minimize the makcspan," Management 
Science, Vol. 39, No. 5, pp. 616-625, 1993. 

Lee, C.-Y., and J.W. Herrmann, "A three-machine scheduling problem with look-behind 
characteristics," Research Report 93- 1 1, Department of Industrial and Sy.stems 
Engineering, University of Rorida, Gainesville, Rorida, 1993. 

Lee, C.-Y., L.A. Martin- Vega, R. Uzsoy, and J. Hinchman, "Implementation of a decision 

support system for .scheduling semiconductor testing operations," to appear in Journal of 
Electronic Manufacturing, 1993. 

Lee, C.-Y., R. Uzsoy, and L.A. Martin- Vega, "Efficient algorithms for scheduling semiconductor 
bum-in operations," Operations Research, Vol. 40, No. 4, pp. 764-775, 1992. 

Lenstra, J.K., A.H.G. Rinnooy Kan, and P. Brucker, "Complexity of machine scheduling 
problems," Annals of Discrete Mathematics, Vol. 1, pp. 343-362, 1977. 

Liepins, G.E., and M.R. Milliard, "Genetic algorithms: foundations and applications," Annals of 
Operations Research, Vol. 21, p. 31-58, 1989. 

Liu, J., and B.L. MacCarlhy, "Effective heuristics for the single machine sequencing problem 

with ready times," InternationalJournal of Production Research, Vol. 29, No. 8, pp. 1521- 
1533, 1991. 

Lou, S.X.C, and P.W. Kager, "A robust control policy for vlsi wafer fabrication," IEEE 
Transactions on Semiconductor Manufacturing, Vol. 2, pp. 159-164, 1989. 

Lundrigan, R., "What is this thing they call OFT?" Production and Inventory Management, Vol. 
27, pp. 2-12, 1986. 

Malek, M., M. Guruswamy, M. Pandya, H. Owens, "Serial and parallel simulated annealing and 
tabu search algoritlims for the traveling salesman problem," Annals of Operations 
Research, Vol. 21, p. 59-84, 1989. 

Mason, A. J., and E. J. Anderson, "Minimizing flow time on a single machine with job classes 
and setup times," Naval Research Logistics, Vol. 38, pp. 333-350, 1991. 

Masuda, T., H. Ishii, and T. Nishida, "Some bounds on approximation algorithms for n/m/I/Lmax 
and n/2/F/Lmax scheduling problems," Journal of the Operations Research Society of 
Japan, Vol. 26, pp. 212-224, 1983. 

Matsuo, H., C.J. Suh, and R.S. Sullivan, "Controlled search simulated annealing for general job 
shop scheduling problem," Working Paper #03-04-88, 1988. 

Matsuo, H., C.J. Suh, and R.S. Sullivan, "A controlled search simulated annealing method for the 
single-machine weighted tardiness problem," Annals of Operations Research, Vol. 21, p. 
85-108, 1989. 

Meleton, M.P., "OPT - fantasy or breakthrough," Production and Inventory Management, 
Vol. 27, pp. 13-21, 1986. 



214 

Metropolis. N.. A. Roscnblulh. M. Roscnbluth, A. Teller, and E. Teller. "Equaiion of state 
calcuialions by fast compuling machines," Journal of Chemical Physics. Vol. 21 . pp 
1087-1092. 1953. 

Mitten. L.G.. "Sequencing « jobs on two machines with arbitrary time lags." Management 
Science. Vol. 5, pp. 293-298, 1958. 

Miyazaki, S., and N. Ni.shiyama, "Analysis of minimizing weighted mean flow-time in flow-shop 
scheduling," Journal of the Operations Research Society of Japan. Vol. 23, pp. 118-1 32. 
1980. 

Miyazaki, S., N. Nishiyama, and F. Hashimoto, "An adjacent pairwise approach to the mean 
flow-lime scheduling problem." Journal of the Operations Research Society of Japan. 
Vol. 21. pp. 287-299, 1978. 

Monma, C. L., and C. N. Potus, "On the complexity of scheduling with batch setup times," 
Operations Research, Vol. 37, No. 5, pp. 798-804, Sepiembcr-Octobcr, 1989. 

Moore. J.M., "An njob. one machine sequencing algorithm for minimizing the number of late 
jobs," Management Science. Vol. 15, pp. 102-109, 1968. 

Morton, T.E., Heuristic Scheduling Systems, Graduate School of Industrial Administration, 
Carnegie Mellon University, John Wiley, in press. 1992. 

Morton. T.E., S.R. Lawrence, S. Rajagopolan, and S. Kekre. "SCHED-STAR: a price-based shop 
scheduling module," Journal of Manufacturing and Operations Management. Vol. 1. 
pp. 131-181. 1988. 

Morton, T.E., and P. Ramnath, "Guided forward tabu/beam search for scheduling very large 

dynamic job shops. 1: one machine weighted tardiness," Working paper 1992^7. Graduate 
School of Industrial Administration. Carnegie Mellon University. Pittsburgh. 
Pennsylvania. 1992. 

Najmi. A., and C. Lozinski, "Managing factory productivity using object-oriented simulation for 
setting shift production targets in VLSI manufacturing," Proceedings of the Autofacl 
Conference, Society of Manufacturing Engineers, Detroit, Michigan, pp. 3.1-3.14, 
November, 1989. 

Nakano. R.. and T. Yamada, "Conventional genetic algorithms for job shop problems," in 

Proceedings of the Fourth International Conference on Genetic Algorithms, R.K. Below 
and L.B. Booker, eds., Morgan Kaufmann Publishers, Inc., San Mateo, California, 1991. 

Ogbu, F.A., and D.K. Smith, "The application of the simulated annealing algorithm to the 
solution of the n/m/Cmax flowshop problem," Computers and Operations Research, 
Vol. 17, p. 243, 1990. 

Oliver, I.M., D.J. Smith, and J.R.C. Holland, "A study of permutation cro.ssover operators on the 
traveling salesman problem," Genetic Algorithms and their Applications: Proceedings of 
the Second International Conference on Genetic Algorithms, J. Grefenstelte. ed., Lawrence 
Erlbaum Associates, Hillsdale, New Jersey, 1987. 

Ou, J., and L.M. Wcin, "Dynamic .scheduling of a production/inventory system with by-products 
and random yield," Sloan School of Management, Massachu.setts Institute of Technology. 
May. 1991. 



215 

Ow, P.S., and S.F. Smiih, "Viewing scheduling as an opportunistic problem-solving process." 
AnnaLs of Operations Research, Vol. 12, pp. 85-108. 1988. 

Panwalker, S.S., and W. Iskander. "A survey of scheduling rules." Operations Research, Vol. 25. 
pp. 45-61. 1977. 

Posner. M.E.. "Minimizing weighted completion limes with deadlines." Operations Research, 
Vol. 33, pp. 562-274. 1985. 

Potts. C. N.. "Scheduling two job classes on a single machine." Computers and Operations 
Research,Vol. 18. pp. 411-415. 1991. 

Potts. C.N.. and L.N. van Wasscnhove. "An algorithm for single machine sequencing with 

deadlines to minimize total weighted completion time," European Journal of Operational 
Research. Vol. 12. pp. 379-387. 1983. 

Rachamadugu. R.M., and T.E. Morton, "Myopic hcuri.stics for the single machine weighted 
tardiness problem," Working Paper 30-82-83, Graduate School of Indu.strial 
Administration, Carnegie Mellon University, PilLsburgh, Pennsylvania, 1982. 

Rao, H.R., and B.P. Lingaraj, "Expert systems in production and operations management: 
classification and prospects," Interfaces, Vol. 18, No. 6, pp. 80-91, 1988. 

Reeves, C.R., "Improving the efficiency of tabu search for machine sequencing problems," 
Journal of the Operational Research Society, Vol. 44, No. 4, pp. 375-382, 1993. 

Rinaldi, G., and A. Sassano, "On a job .scheduling problem with different ready times: some 

properties and a new algorithm to determine the optimal .solution," Report R.77-24, Isututo 
di Automatica, Univcrsita di Roma, 1977. 

Robinson, J.K., J. W. Fowler, and J.F. Bard. "The use of upstream and downstream information in 
scheduling scmiconducotr batch operations," Technical Report 93-06, Graduate Program 
in Operations Research, University of Texas, Austin, 1993. 

Sadeh, N., "MICRO-BOSS: a micro-opportunistic factory scheduler," Center for Integrated 
Manufacturing Decision Systems, The Robotics Institute. Carnegie Mellon University, 
Pittsburgh, Pennsylvania, 1991. 

Sahney, V. K., "Single-server, two-machine sequencing with switching time." Operations 
Research, Vol. 20. pp. 24-36. 1972. 

Savell, D.V., R.A. Perez, and S.W. Koh, "Scheduling semiconductor wafer production: an expert 
system implementation," IEEE Expert, Vol. 4, pp. 9-15, 1989. 

Schutten, J.M.J., and W.H.M. Zijm, "Scheduling a single machine with release dates, due dates, 
and family setup times," Department of Mechanical Engineering, University of Twente. 
The Netherlands, 1993. 

Shanthikumar, J.G., "Scheduling jobs on one machine to minimize the maximum tardiness with 
minimum number tardy," Journal of Computers and Operations Research, Vol. 10, 
pp. 255-266, 1983. 



216 

Smith, S.F., M.S. Fox, and P.S. Ow, "Consirucling and mainlaining detailed production plans: 
investigations into the development of knowledge-based factory scheduling sy.stcms," Al 
Magazine, Vol. 7. No. 4. pp. 45-61, 1986. 

Smith, W.E., "Various optimizers for single-stage production," Naval Research Logistics 
Quarterly, Vol. 3, pp. 59-66, 1956. 

Solor/.ano, M., "Workload Regulation of Semiconductor Fabrication Facilities," ESRC 89-1, 
University of California, Berkeley, January, 1989. 

Spence, A.M., and D.J. Welter, "Capacity Planning of a Photolithography Work Cell in a Wafer 
Manufacturing Line," Proceedings of tlie IEEE Conference on Robotics and Automation, 
pp. 702-708, 1987. 

Sriskandarajah, C, and S.P. Sethi, "Scheduling algorithms for flexible flowshops: worst and 

average case perfonmance," European Journal of Operational Research, Vol. 43, pp. 143- 
160, 1989. 

Starkweather, T., S. McDanicls, K. Mathias, C. Whitley, and D. Whitley, "A comparison of 

genetic sequencing operators," in Proceedings of the Fourth International Conference on 
Genetic Algorithms, R.K. Below and L.B. Booker, eds., Morgan Kaufmann Publishers, 
Inc., San Mateo, California, 1991. 

Storer, R.H., S.Y.D. Wu, and R. Vaccari, "Local Search in Problem and Heuristic Space For Job 
Shop Scheduling," Working Paper, Department of Industrial Engineering, Lehigh 
University, 1990. 

Storer, R.H., S.Y.D. Wu, and R. Vaccari, "New search spaces for sequencing problems with 

application to job shop scheduling," Management Science, Vol. 38, No. 10, pp. 1495-1509. 
1992. 

Sullivan, G., and K. Fordyce, "IBM Buriington's Logistics Management System," Interfaces, 
Vol. 20, pp. 43-64, 1990. 

Syswerda, G., "Uniform crossover in genetic algorithms," in Proceedings of the Third 

International Conference on Genetic Algorithms, J.D. Schaffer, ed., Morgan Kaufmann 
Publishers, Inc., San Mateo, California, 1989. 

Syswerda, G., "Schedule optimization using genetic algorithms," in Handbook of Genetic 
Algorithms, L. Davis, ed.. Van Nostrand Rcinhold, 1991. 

Szwarc, W., "Optimal two-machine orderings in the 3 x n flow-shop problem," Operations 
Research, Vol. 25, pp. 70-77, 1977. 

Szwarc, W., "The flow-shop problem with mean completion time criterion," //£ Transactions, 
Vol. 15, pp. 172-176, 1983. 

Trilling, D. R., "Job shop simulation of orders that are nclwoiks," Journal of Industrial 
Engineering, Vol. 17, 1966. 

Uzsoy, R., C.-Y. Lee, and L.A. Martin- Vega, "A review of production planning and schcduUng 
models in the semiconductor industry, part I: system characteristics, performance 
evaluation and production planning," //£ Transactions, Vol. 24, pp. 47-61, 1992a. 



217 

Uzsoy. R., C.-Y. Lcc, and L.A. Martin- Vega, "Scheduling semiconductor test operations: 

minimizing maximum lateness and number of lardy jobs on a single machine," Naval 
Research Logistics. Vol. 39, pp. 369-388, 1992b. 

Uzsoy, R., C.-Y. Lcc, and L.A. Martin- Vega, "A review of production planning and scheduling 
models in the semiconductor industry, part II: shop floor control," to appear in /IE 

Transactiuns, 1993. 

Uzsoy, R., C.-Y. Lcc, L.A. Martin- Vega, and J. Hinchman, "Scheduling Semiconductor Testing 
Operations: Optimization and Approximation," Proceedings, Joint U.S. -German 
Conference on New Directions for Operations Research in Manufacturing, Gaithersburg, 
Mar)'land. July 30-31. 1991a. 

Uzsoy, R., L.A. Manin-Vcga, C.-Y. Lee, and P.A. Leonard, "Production Scheduling Algorithms 
for a Semiconductor Test Facility," IEEE Transactions on Semiconductor Manufacturing, 
1991b. 

Vairaktarakis, G.L., and C.-Y. Lee, "The single machine problem to minimize total tardiness 
subject to minimum numberof tardy jobs," to appear in HE Transactions, 1993. 

Vakharia, A.J., and Y.L. Chang, "A simulated annealing approach to scheduling a manufacturing 
ceU," Naval Research Logistics, Vol. 37, p. 559, 1990. 

Van de Veldc, S.L., "Minimizing the sum of the job completion times in the two-mchine flow 
shop by Lagrangian relaxation," Annals of Operations Research, Vol. 26, pp. 257-268, 
1990. 

Vepsalainen, A.P.J. , and T.E. Morton, "Priority rules for job shops with weighted tardiness 
costs," Management Science, Vol. 33, No. 8, pp. 1035-1047, 1987. 

Vepsalainen, A.P.J., and T.E. Morton, "Improving local priority rules with global lead-time 

estimates," Journal of Manufacturing and Operations Management, Vol. 1 , pp. 102-1 18, 
1988. 

Vollmann, T.E., "OPT as an enhancement to MRP II," Production and Inventory Management, 

Vol. 27, pp. 38-47, 1986. 

Vollmann, T.E., W.L. Berry, and D.C. Whybark, Manufacturing Planning and Control Systems, 
Second edition, Dow Jones-Irwin, Homcwood, Illinois, 1988. 

Wein, L.M., "Scheduling semiconductor wafer fabrication" IEEE Transactions on Semiconductor 
Manufacturing, Vol. l,pp. 115-130, 1988. 

Wein, L.M., "On the relatioaship between yield and cycle time in semiconductor wafer 
fabrication," Sloan School of Management, Massachusetts Institute of Technology. 
January. 1991. 

Wein, L.M.,and P.B. Chevalier, "A broader view of the job-shop scheduling problem," 
Management Science, Vol. 38, No. 7, pp. 1018-1029, 1992. 

Whitley, D., "GENITOR: a different genetic algorithm," in Proceedings of the Rocky Mountain 
Conference on Artificial Intelligence, Denver, Colorado, 1988. 



218 

Whitley. D., T. Slarkwcatlicr, aiid D. Shancr, "The traveling salesman and sequence scheduling: 
quality solutions using genetic edge optimization," in Handbook of Genetic Algorithms, 
L. Davis, cd.. Van Noslrand Rcinhold, 1991. 

Widmcr, M., and A. Hcitz, "A new heuristic method for the How shop sequencing problem," 
European Journal of Operational Research, Vol.41, p. 1H6-19.3, 1989. 

Wittrock. R.J., "An adaptable scheduling algorithm for flexible flow lines," Operations Research, 
Vol. 36, No. 3, pp. 445-453, 1988. 

Woodruff. D. L., and M. L. Spearman, "Sequencing and batching for two classes of jobs with 
deadlines and setup times," Production and Operations Management, Vol. 1, pp. 87-102. 
1992. 

Wu, S.D., R.H. Slorer, and P.-C. Chang, "One-machine rescheduling hcruistics with efficiency 
and stability as criteria," Computers and Operations Research, Vol. 20, No. 1, pp. 1-14, 
1993. 

Zeesiratcn, M. J., "The look ahead dispatching procedure." InternationalJournal of Production 
Research, Vol. 28, pp. 369-384, 1990. 



BIOGRAPHICAL SKETCH 

Jeffrey W. Herrmann has a degree in applied malhcmalics from Georgia Tech and is a 
Ph.D. candidate in the Dcparimeni of Industrial and Systems Engineering at the University of 
Florida. He held an NSF Graduate Research Fellowship from 1990 until 1993 and has been 
working on an applied research project with Harris Semiconductor. His research interests include 
operations research, production scheduling, and heuristic search. 



219 



I certify thai I have read this study and that in my opinion it conforms to acceptable 
standards of scholarly presentation and is fully adequate, in scope and quality, as a dissertation 
for the degree of Doctor of Philosophy. 




pY~^^^ L 



<2J^ 



Chung- Yee Lee, Chairman 
Associate Professor of Industrial and Systems 
Engineering 



I certify that I have ixrad this study and that in my opinion it conforms to acceptable 
standards of scholarly presentation and is fully adequate, in scope and quality, as a dissertation 
for the degree of Doctor of Philosophy. 




izmga ^y ^ 

fessor of Industriaf;arid Systems Engineering 

I certify that I have read this study and that in my opinion it conforms to acceptable 
standards of scholarly presentation and is fully adequatp-.jin sppe and quality, ^as a dissertation 
for the degree of Doctor of Philosophy. 




Sherman Bai 

Assistant Professor of Industrial and Systems 
Engineering 



I certify that I have read this study and that in my opinion it conforms to acceptable 
standards of scholarly presentation and is fully adequate, in scope and quality, as a dissertation 
for the degree of Doctor of Philosophy. 




Gary K 
Profcssi 



of Decision and Information Sciences 



I certify that I have read this study and that in my opinion it conforms to acceptable 
standards of scholarly presentation and is fully adequate, in scope and quality, as a dissertation 
for the degree of Doctor of Philosophy. 




/^elclik Ercn 
Professor of 




cision and Information Sciences 



This dissertation was submitted to the Graduate Faculty of the College of Engineering and 
to the Graduate School and was accepted as partial fulfillment of the requirements for the degree 
of Doctor of Philosophy. 



December, 1993 



fn Winfrcd M. Phillips 

Dean, College of Engineering 



Karen Holbrook 
Dean, Graduate School 



\ 



•^ >JIK^S^0^ 



sc\t^^^ 



u^^ 



MARSTON SCIENCE UBRARY 





Date 


Due 




Due 


Returned 


Due 


Returned 


M^^cs^KM 








MAY 2 9 1W5 








^'^ 15 1996 








,JAN 6 1997 


u.13^^'*^ 






lilin 1 7 10Q 


<5" 

7 






(MAH 1 7 r^ 


AH 'Z 4 1997 







































































































































J 1262 05234 5005 



MARSTON SCIENCE LIBRARY 



LD 
17S0 

SCIENCE 
LIBRARY 



Ir,/ 



HECKMAN 

BINDERY INC. 

JULY 94