Skip to main content

Full text of "Proceedings of the annual convention"

See other formats


PROCEEDINGS  OF  THE 

AMERICAN  RAILWAY  ENGINEERING 

ASSOCIATION 

CONTENTS,  VOLUME  77 

(For  detailed  index,  see  Bulletin  658,  page  713) 


Bulletin  654,  September-October  1975  Page 

Principles  and  Criteria  for  the  Design  of  a  Railroad  Test  Track  Facility       1 
Work    Equipment    Repair    Organizations    of    North    American    Railroads 
(Advance    Report    of    Connnittee    27 — Maintenance    of    Way    Work 

Equipment)    9 

Tie  Renewals  and  Costs  (Advance  Report  of  Committee  3 — ^Ties  and  Wood 

Preservation )     13 

Statistical   Data  for   Coupled-in-Motion   Weighing   and  Testing    (Advance 

Report  of  the  Special  Committee  on  Scales )    25 

Summary  of  Performance  of  Standard-Carbon  and  Various  Wear-Resistant 
Rails  in  Test  Curves  on  the  Chessie  System — Second  Report  (Advance 
Report  of  Committee  4 — Rail )    55 

Bulletin  655,  November-December  1975  (Part  1) 

Manual  Recommendations    87-249 

Bulletin  655,  November-December  1975  (Part  2 — Reports  of  Committees) 

Highways  (9)    255 

Engineering  Records  and  Property  Accounting  ( 11 )    273 

Yards  and  Terminals   ( 14 )    279 

Bulletin   656,   January-February    1976   (Reports   of   Committees) 

Scales   ( Special  Committee )    287 

Economics  of  Railway  Construction  and  Maintenance  ( 22 )    299 

Environmental   Engineering    (13)     323 

Maintenance  of  Way  Work  Equipment  (27 )    333 

Clearances    ( 28 )    337 

Buildings    (6)    341 

Timber   Structures    ( 7 )    , 351 

Concrete   Structures   and  Foundations    ( 8 )    353 

Steel  Structures  (15)    359 

Roadway  and   Ballast    ( 1 )    363 

Ties  and  Wood  Preservation  ( 3 )    367 

Rail  (4)    373 

Economics  of  Plant,  Equipment  and  Operations  (16)    383 

Engineering  Education  ( 24 )    401 

Electrical  Energy  Utihzation   (33)    403 

Addresses  Presented  at  Vancouver  Regional  Meeting 415-449 


Bulletin  658,  June-July    1976  (Technical  Conference   Report)  Page 

President's    Address     487 

Special  Features    '^91 

Installation  of  Officers    667 

AAR  Engineering  Division  Session 673 

Report  of  Executive  Director   681 

Report  of  Treasurer    691 

AREA  Constitution  697 


^.  c.   \^rQ/ttne.yef 


/J 


American  Railway 

Engineering  Association— Bulletin 


RECEIVED 
NOV  0  6  197S 

t.  STALLMEYER 


Bullefin  654 
Proceedings  Volume  77* 


September-October   1975 


CONTENTS 

Principles  and  Criteria  for  the  Design  of  a  Railroad  Test 

Track  Facility 1 

Work  Equipment  Repair  Organizations  of  North  Ameri- 
can Railroads  (Advance  Report  of  Committee  27 — 
Maintenance  of  Way  Work  Equipment) 9 

Tie   Renewals  and   Costs  (Advance  Report  of  Committee 

3 — Ties  and  Wood  Preservation) 13 

Statistical  Data  for  Coupled- in -Motion  Weighing  and 
Testing  (Advance  Report  of  the  Special  Committee 
on    Scales)    25 

Summary  of  Performance  of  Standard-Carbon  and  Various 
Wear-Resistant  Rails  in  Test  Curves  on  the  Chessie 
System — Second  Report  (Advance  Report  of  Com- 
mittee  4 — Rail)   55 

Directory — Consulting    Engineers    84—1 


•Proceedings   Volume   77    (1976)    wiU   consist  of   AREA   BuUetins    654,   September- 


BOARD  OF  DIRECTION 

1975-1976 

President 
J.  T.  Ward,  Senior  Assistant  Chief  Engineer,  Seaboard  Coast  Line  Railroad,  500  Water 
St.,  Jacksonville,  FL  32202 

Vice  Presidents 
John  Fox,  Assistant  Chief  Engineer,  Canadian  Pacific  Rail,  Windsor  Station,  Montreal, 

PQ  H3C  3E4 
B.  J.  WoRLEY,  Vice  President — Chief  Engineer,  Chicago,  Milwaukee,  St.  Paul  &  Pacific 

Railroad,  Union  Station,  Room  898,  Chicago,  IL  60606 

Past  Presidents 

D.  V.  Sartore,  Chief  Engineer — Design,  Burlington  Northern,  Inc.,  176  E.  5th  St.,  St. 

Paul,  MN  55101 
R.  F.  Bush,  Chief  Engineer,  Erie  Lackawanna  Railway,  Midland  Bldg.,  Cleveland,  OH 

44115 

Directors 
R.  W.  Pember,  Chief  Engineer — Design  and  Construction,  Louisville  &  Nashville  Rail- 
road, P.  O.  Box  1198,  Louisville,  KY  40201 

E.  Q.   Johnson,   Senior  Assistant   Chief   Engineer,   Chessie  Systena,  P.  O.   Box   1800, 

Huntington,  WV  2S718 

W.  E.  FuHR,  Assistant  Chief  Engineer — Staff,  Chicago,  Milwaukee,  St.  Paul  &  Pacific 
Railroad,  Union  Station,  Room  898,  Chicago,  IL  60606 

B.  E.  Pearson,  Chief  Engineer,  Soo  Line  Railroad,  Soo  Line  Bldg.,  Room  1520,  Minne- 
apolis, MN  55440 

P.  L.  Montgomery,  Manager  Engineering  Systems,  Norfolk  &  Western  Railway,  8  N. 
Jefferson  St.,  Roanoke,  VA  24042 

E.  C.  HoNATH,  Assistant  General  Manager  Engineering,  Atchison,  Topeka  &  Santa  Fe 
Railway,  900  Polk  St.,  Amarillo,  TX  79171 

Mike  Roucas,  Chief  Engineer,  Bessemer  &  Lake  Erie  Railroad,  P.  O.  Box  471,  Green- 
ville, PA  16125 

J.  W.  DeValle,  Chief  Engineer  Bridges,  Southern  Railway  System,  99  Spring  St.,  S.  W., 
Atlanta,  GA  30303 

R.  L.  Gray,  Chief  Engineer,  Canadian  National  Railways,  P.  O.  Box  8100,  Montreal, 
PQ  H3C  3N4 

E.  H.  Waring,  Chief  Engineer,  Denver  &  Rio  Grande  Western  Railroad,  P.  O.  Box 
5482,  Denver,  CO  80217 

Wm.   Glavin,   General  Manager,   Grand  Trunk  Western   Railroad,   131   W.  Lafayette 
Blvd.,  Detroit,  MI  48226 

G.  H.  Maxwell,  System  Engineer  of  Track,  Union  Pacific  Railroad,  1416  Dodge  St., 
Omaha,  NE  68179 

Treasurer 

A.  B.  HiLLMAN,  Jr.,  Chief  Engineer,  Belt  Railway  of  Chicago,  6900  S.  Central  Ave., 
Chicago,  IL  60638 

Executive  Director 

Earl  W.  Hodgkins,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 
Assistant  to  Executive  Director 

N.  V.  Engman,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Administrative  Assistant 

D.  F.  Fredley,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Published   by    the    American    Railway    Engineering   Association,    Bi-Montbly,    January-February,    April- 
May,   June-July,   September-October  and   November-December,   at 
59  East  Van  Buren  Sueet,  Chicago,  Dl.  6060S 
Second  class  postage  at  Chicago,   III.,  and  at  additional  mailing  offices. 
Subscription   $15   per  annum 

Copyright  ©   1975 

American  Railway  Engineering  Association 

All  rights  reserved. 

No    part    of    this    publication    may    be    reproduced,    stored    in    an    information    or    data    retrieval 

system,     or    transmitted,    in    any    form,    or    by    any    means — electronic,     mechanical,    photocopying, 

recording,   or   otherwise — without   the  prior  written  permission  of  the  publisher. 


Principles  and  Criteria  for  the  Design  of  a   Railroad 
Track  Test  Facility* 

By  Arnold   D.    Kerr^ 

SUMMARY 

The  paper  contains  a  discussion  of  principles  and  criteria  for  the  design  of  a 
railroad  track  test  facility.  One  such  facility  is  to  be  built  and  operated  by  tlie 
Federal  Railroad  Administration  ( FRA ) .  The  puipose  of  the  tests  to  be  conducted 
is  to  support  the  various  track  research  programs  which  aim  to  improve  the  design 
as  well  as  the  maintenance  procedures  and  safety  of  railroad  tracks. 

INTRODUCTION 

As  part  of  its  effort  to  pro\ide  the  technology  necessary  for  improving  the  per- 
formance and  safety  of  the  railroad  tracks  in  the  United  States,  the  Federal  Rail- 
road Administration  ( FRA )  is  planning  to  build  and  operate  a  track  research  labo- 
ratory in  Pueblo,  Colorado.  The  purpose  of  the  tests  to  be  conducted  at  this 
lalx)ratory  is  to  gain  information  for  impro\ing  the  design,  as  well  as  the  main- 
tenance procedures,  for  railroad  tracks.  The  planned  program  may  include  tests  for: 
( 1 )  the  determination  of  stresses  in  the  rails,  ties  and  fasteners  due  to  static  and 
dynamic  loads  and  various  conditions  of  the  ballast;  (2)  the  determination  of  safe 
temperature  increases  to  prevent  buckling  of  an  unloaded  track;  and  (3)  a  study 
of  the  effect  of  a  moving  train  on  the  stability  of  a  thermally  compressed  track.  In 
these  tests  special  attention  should  be  given  to  the  effect  of  tamping  and  traffic 
compaction  of  the  ballast  on  the  stability  of  the  welded  track,  a  problem  of  great 
importance  for  stipulating  efficient   track  maintenance  procedures. 

The  purpose  of  the  following  presentation  is  to  establish  a  number  of  general 
principles  and  criteria  for  the  design  of  such  a  track  test  facility. 

DISCUSSION    OF   DESIGN    PRINCIPLES   AND    CRITERIA 

When  planning  a  test  stand  for  the  study  of  the  track  response  caused  by  a 
variety  of  forces,  it  is  essential  to  know  the  approximate  displacement  and  force 
distributions  anticipated  during  the  \arious  tests.  This  is  necessary  for  the  stipula- 
tion of  the  minimum  length  of  the  test  track  and  for  estimating  the  largest  antici- 
pated forces.  This  in  turn  affects  the  choice  of  the  loading  mechanisms  and  the 
accuracy  of  the  measuring  devices. 

The  first  task  in  the  planning  of  such  a  test  stand  is  the  determination  of  the 
minimum  length  of  the  test  track,  L,„,„.  From  the  literature  on  railroad  track  tests, 
it  appears  that  from  the  multitude  of  tests  to  be  conducted,  the  buckling  and 
dynamic  experiments  require  the  longest  track  section. 

Consider  the  straight  track  shown  in  Fig.  1-(I).  A  uniform  temperature 
increase  induces  in  the  welded  rails,  due  to  constrained  thermal  expansions,  an 
axial  compression  force  Ni  which  does  not  \ar\-  along  the  track,  as  shown  in  Fig. 


"  Research  sponsored   bv   the   Department  of  Transportation,   Federal  Railroad   Administration, 
under  contract  DOT-FR-400i7. 

1  Visiting  Professor,   Department  of  Civil  Engineering,  Princeton  University,  Princeton,  N.J. 

1 
Bui.  654 


Bulletin  654 — American  Railway  Engineering  Association 


z 


undeformed    state 


-buckled    state 
I  a 


(I)   Top  view  of  track 


K 


K 


(I)  Axial  compression    force    before    buckling 


m 


n; 


N. 


-N, 


— •-=— — I 1  — 

(H)  Axial   compression   force    after    buckling 

Fig.  1 


N 


l-(II).  For  a  large  value  of  Ni,  say  N,,  the  track  may  buckle  out.  The  resulting 
force  distribution  is  shown,  schematically,  in  Fig.  l-(III).  In  the  buckled  region 
of  length  I,  because  of  the  associated  deformations,  part  of  the  thermal  expansions 

is  released.  This  results  in  a  reduction  of  the  axial  force  Nt  to  Nt.  In  the  adjoining 
regions,   each   of   length  a,   due   to   ballast   resistance   to   axial  displacement  of  the 

track,  the  constrained  thermal  expansions  vary;  so  does  the  axial  force  A^(  <  N  < 
Ni,  as  shown  in  Fig.  l-(III).  According  to  the  above  description,  track  buckling  is 
a  local  phenomenon  and  except  for  the  length  (/  +  2c)  the  track  is  not  affected  by 
it.  Thus 

L„,An  =  l+2a (1) 

To  realize  the  possible  effect  of  the  adjoining  regions  of  length  2a,  the  reader 
is  referred  to  Ref .  ( 1 )  and  to  Ref .  ( 2 ) .  The  case  n  =  o  in  Ref .  ( 1 )  corresponds 
to  the  elimination  of  the  elfect  of  the  adjoining  regions.** 

The  test  tract  at  the  Technical  University  of  Karlsruhe,  used  for  the  DB  track 
research  program,  consisted  of  a  46.50-m  (153-ft)  track  confined  between  two 
reinforced  concrete  piers  weighing  624  tons  each.  For  details  the  reader  is  referred 
to  Ref.   (3)    (4) 

The  test  track  of  the  Civil  Engineering  Laboratory  of  the  Western  Region  of 
British  Railways  consisted  of  a  36.6-m  (120-ft)  track  anchored  at  both  ends  to 
concrete  blocks  sunk  to  ground  level.  For  details  the  reader  is  referred  to  Ref.  (5). 

The  test  track  of  the  Central  Railroad  Research  Institute  of  the  Soviet  Union 
(CNII  MPS)  consists  of  a  100-m  (328-ft)  long  straight  track,  mounted  between 
two  concrete  piers.  The  length  of  a  curved  test  track  was  fixed  to  200  m  (656  ft). 
For  details  the  reader  is  referred  to  Ref.   (6). 


"For  buckling   in   the   horizontal   jilane,   the   load   q   in    (1)    and    (2)    is  to  be   interpreted  as 
a  resistance  against  lateral  deformations. 


Designing  a  Railroad  Test  Track  Facility 


According  to  the  results  of  many  buckling  tests  conducted  on  the  100-m  test 
track  by  CNII  (6),  the  track  buckled  in  the  horizontal  plane  and  the  buckled 
length  (which  usually  consisted  of  more  than  one  wave)  varied  for  different  tracks. 
The  largest  observed  I  for  a  straight  track  was  42  m.  For  many  tests,  I  was  about 
30  m.  The  values  for  cui-ved  tracks  were  about  the  same.  These  results  suggest  that 
the  test  tracks  of  the  DB  and  BR  may  have  been  too  short.  This  conjecture  is  also 
confirmed  by  the  buckling  mode  shown  in  Fig.  31  of  Ref.   (5). 

If  a  test  track  is  too  short,  it  will  usually  yield  higher  buckling  temperatures 
than  a  corresponding  track  encountered  in  the  field.  In  view  of  the  larger  rigidities 
of  the  rails  currently  in  use  in  the  U.S.A.  (and  to  be  tested  in  the  future),  it  is 
proposed  that  for  the  planned  test  track  Imtn  should  be  about  60  m.  Taking  into 
consideration  the  additional  lengths  2a,  it  appears  that  a  reasonable  minimum  total 
length  of  the  new  test  track  should  be  (for  an  analysis  see  footnote  below): 

L,„,„  ■=  490  m  (about  1,600  ft)*    (2) 

The  next  task  is  to  decide  on  tJie  type  of  end  restraints.  This  may  be  achieved 
in  several  ways: 

( 1 )  The  track  may  continue  on  boUi  ends  as  in  an  actual  railroad  track. 
The  minimum  length,  h,  of  these  adjoining  regions  to  L  is  determined 
from  the  largest  anticipated  track  compression  force,  say  NT'"'  =  500 
tons'"*,  and  the  resistance  of  the  imloaded  track  to  axial  displacements 
r(x)  per  unit  length  of  track.  Considering  the  equilibrium  of  forces 
in  the  horizontal  plane  on  the  free  body  diagram  shown  in  Fig.  2,  it 
follows  that: 


b 

1 

moxM 

r                          /q 

N|  y^ 

y 

L 

"" — 

■•" 

"" — 

rW 

y. 

■*— 

■'— 

V 

1 — 5 — 

'q 

Fig.  2 


NT 


J    r{x)  dx (3] 


*  The  value  of  Lmin  =  490  m  in  equation  (2)  was  determined  by  assuming 
that  Nt  —  N,  =  150  tons,  hence  a  =  {N!  ~  Nt)  /r„  =  215  m  and  L,„,„  =  Lm  + 
2a  =:  490  m.  The  r„  value  has  to  be  determined  experimentally,  after  the  track  to 
be  tested  is  chosen. 

"'At  the  Karlsruhe  test  stand  ([4],  p.  332)  a  buckling  load  of  as  high  as  375 
tons  was  observed.  At  the  BR  tests  ([5],  Table  5)  the  highest  load  encountered 
was  about  275  tons.  At  the  CNII  ([6],  p.  23)  in  one  test  no  buckling  was  observed 
even  at  425  tons. 


Bulletin  654 — American  Railway  Engineering  Association 

When  r(x)  is  known,  the  above  integral  can  be  evaluated  and  then 
equation  (3)  solved  for  h,  its  only  unknown.  In  the  railroad  literature 
it  is  often  assumed  that  /•  docs  not  vary  with  .r.  Hence  r(x)  =z  r„  =: 
constant.  In  this  case  e(|uation   (3)   reduces  to  N',""''  =  r„   •   /?  and  hence 


b- 


^,„„. 


(4) 


For  example,  accordinj^  to  equation  (4),  if  N'""'  =  500  tons  and  the 
resistance  r„  ^  7  kg/cm  (467  lb/ft),  then  the  required  b  equals  715  m 
(2,350  ft). 

In  order  to  simulate  the  actual  conditions  in  the  field,  the  desired 
distribution  of  axial  forces  in  the  buckled  track  has  to  be  as  shown 
schematically  in  Fig.  3. 


b 

1 

L 

=  500 

m 

1 

b 

r                                 '1' 

"-M, 

^^ 

'~-~ 

k 

JiJJ- 

L>^ 

Distribution    of  axial  forces   at  the  onset  of  buckling 


Desired    distribution  of   forces    after   buckling 

Fig.  3 


(2)  The  necessary  length  b  may  be  shortened  considerably  by  placing 
loaded  railroad  cars  or  locomotives  outside  the  L  region.  Once  the 
weight  and  geometry  of  the  available  loaded  cars  or  locomotives  are 
known,  their  position  on  the  track  should  be  determined  to  insure  the 
desired  conditions  in  the  L  region. 

(3)  The  b  regions  may  be  eliminated  (almost)  entirely  by  using  heavy 
piers  on  both  track  ends.  However,  because  the  anticipated  axial  track 
loads  may  be  as  high  as  500  tons,  small  displacements  of  the  piers  at 
the  ends  of  the  test  track  are  usually  unavoidable.  The  magnitude  of 
these  displacements  will  depend,  for  a  fixed  temperature  increase,  upon 
the  weight  and/or  foundation  of  the  piers.  The  desired  distribution  of 
axial  forces  in  the  track  after  buckling,  is  shown  schematically  in  Fig.  4. 
The  drop  of  the  axial  forces  in  the  outer  track  regions  of  length  b',  is 
due  to  the  anticipated  yielding  of  the  piers. 


Designing  a  Railroad  Test  Track  Facility 


VZA 


Pier 


Top  view  of  test  stand 


YTA 

Pier 


ti 

L  = 

50C 

nr 

1 

- 

.  i  . 

■ 

^J-^ 

Distribution   of  axial  forces   at  the  onset  of  buckling 


Nt 

i 

€>0 

\\    1    II    II    11^ 
LSSOOm 

77 
€^0  i 

1 

r 

Desired    distribution  of  forces    after   buckling 

Fig.  4 

The  test  tracks  in  Karlsruhe,  at  the  BR  Western  Region  Laboratory,  and  at 
the  CNII  MPS  used  end  piers,  as  described  above  in  option  (3).  The  SNCF  (7) 
and  JNR  (8)  used  locomotives,  as  described  in  option  (2).  The  choice  of  either 
of  the  three  alternatives  described  above  should  depend  upon  the  availability  of 
space,  locomotives  or  cars,  and  other  economic  factors.  Also  the  versatility  of  a 
particular  arrangement  with  regard  to  various  test  programs  to  be  conducted, 
should  be  taken  into  consideration. 

For  example,  one  possible  aim  to  ])c  achieved  using  the  planned  facility  is  to 
determine  the  effect  of  traffic  compaction  of  the  ballast  on  the  stability  of  tlie  track. 
Namely,  how  many  passes  (say,  in  tons)  are  needed  after  tamping  to  reach  the 
desired  stability  of  a  planned  track.  This  proljlem  is  related  to  the  removal  of 
imposed  speed  restrictions  after  track  renovation.  Such  a  compaction  could  be 
achieved  in  a  test  stand  by  moving  locomotives  and  loaded  cars  back  and  forth  on 
the  test  track  (or  in  one  direction  if  both  ends  of  the  test  track  are  connected  to  a 
track  loop)  before  it  is  subjected  to  axial  compression  forces.  For  such  tests,  option 
(1)  or  (2)  is  preferable.  In  option  (2),  after  completing  the  compaction  runs,  the 
locomotives  and  cars  can  be  used  to  achieve  the  desired  end  conditions.  Another 
advantage  of  options  (1)  and  (2)  is  that  the  length  of  the  test  track,  L,  can  be 
easily  increased,  if  this  should  become  necessary.  If  buckling  tests  of  a  heated  track 
subjected  to  a  moving  train  are  contemplated,  or  a  study  of  axial  rail  forces  in- 
duced by  a  moving  train  are  planned,  then  option  ( 1 )  is  necessary.  The  length 
hmin  —  500  m  should  be  sufficient  also  for  these  purposes. 

Tests  involving  compaction  due  to  traffic  also  require  that  proper  clearance 
should  be  secured  over  the  test  track  in  order  not  to  hinder  the  planned  movement 
of  the  locomotive  or  cars. 


6 


Bulletin  654 — American  Railway  Engineering  Association 


The  use  of  locomotives  or  loaded  railroad  cars  for  compaction  purposes  re- 
quires that  the  test  facility  be  connected  to  an  existing  railroad  track  in  order  to 
facilitate  their  delivery  and  movement.  This  point  should  be  considered  when  de- 
ciding on  the  location  of  the  track  test  facility.  In  order  to  enable  a  study  of 
buckling  phenomena  caused  by  a  temperature  increase  and  a  moving  train,  or  a 
study  of  axial  rail  forces  induced  by  a  moving  train,  the  possibiUty  of  tying  the 
test  tract  to  an  existing  track  loop  should  be  considered  when  deciding  on  the  loca- 
tion of  the  test  track. 

For  various  track  studies,  there  is  a  need  to  exeii>  on  the  track  a  lateral  load 
of  several  torus.  The  lateral  load  may  be  produced  by  means  of  hydraulic  or  screw 
jacks  that  press  against  a  structure  located  near  the  track,  as  shown  in  Fig.  5.  Such 


test  track 


Fig.  5 

a  structure  may  l^e  a  concrete  pier  built  along  the  test  track.  A  more  versatile 
alternative  is  to  use  a  heavy  tractor  instead  of  the  pier.  The  advantages  of  using 
a  tractor  are  that  it  can  be  placed  in  any  desired  location  along  the  500-m-long 
track,  and  that  it  can  be  used  directly  for  push  or  pull  purposes.  In  order  to  in- 
crease its  resistance  against  displacements,  when  necessary,  the  tractor  may  be  par- 
tially dug  in. 

For  some  tests  it  may  be  necessary  to  exert  a  lateral  force  on  the  moving 
train  (7).  This  may  be  achieved,  economically,  by  placing  the  test  track  near  and 
parallel  to  an  existing  track. 

The  axial  compression  force  in  an  actual  welded  track  is  often  induced  by 
raising  the  rail  temperatures.  To  simulate  such  a  situation  the  test  track  has  to  be 
heated.  The  use  of  mechanical  jacks  built  into  the  rails  to  induce  axial  compression 
forces,  as  described  in  Ref.  (9),  is  not  admissible,  as  shown  in  Ref.  (1)  (10).  In 
the  test  stands  in  Karlsruhe  (3)  (4)  and  at  the  CNII  (6)  the  rails  were  heated 
utilizing  electric  currents.  In  the  tests  at  the  BR  Western  Region  Laboratory  (5) 
heating  of  the  rails  was  achieved  by  placing,  along  each  rail,  parabolic  reflectors 
fitted  with  electric  heating  elements.  For  the  JNR  tests  (8)  the  rails  were  heated 
using  steam. 

The  heating  method  which  uses  electric  currents  is  to  be  preferred.  In  order 
to  be  able  to  heat  each  rail  to  a  different  temperature  level,  each  of  the  two  rails 
should  have  its  own  electric  circuit.  This  arrangement  is  necessary  for  those  tests 
whose  purpose  will  be  the  determination  of  the  effect  of  different  rail  temperatures 
(i.e.  eccentricity  of  the  axial  force  in  the  track)   on  track  stabiHty. 


SUMMARY   OF   RECOMMENDATIONS 

The  guiding  principle  in  designing  the  track  test  facility  should  be  that  the 
test  track  and  its  mechanical  environment  should  simulate  as  closely  as  possible,  for 
each  test,  the  situation  the  actual  track  will  encounter  in  the  field. 


Designing  a  Railroad  Test  Track  Facility 


It  is  proposed  that  for  the  planned  test  track,  the  lent^th  of  the  test  section, 
L,  be  about  1,600  ft.  To  secure  versatility,  the  end  constraints  should  he  achieved 
as  discussed  in  option  (1);  namely,  the  test  track  should  be  sufficiently  lon^.  Both 
ends  of  the  test  track  should  be  connected  to  a  track  loop,  as  shown  in  Fig.  6. 


Fig.  6 

This  arrangement  is  needed  for  tests  which  require  moving  trains  over  the  test 
section.  Proper  clearance  over  the  test  track  should  be  secured  to  allow  unhindered 
movement  of  the  locomotives  and  cars  over  the  entire  test  track.  The  planned  test 
track  should  be  connected  to  an  existing  track,  to  facilitate  the  delivery  of  rolling 
stock.  If  possible,  the  test  track  should  be  located  near  and  parallel  to  an  existing 
track.  To  exert  vertical  forces  on  the  track,  use  can  be  made  of  available  locomo- 
tives or  cars  and  in  special  situations  by  utilizing  cranes.  Lateral  forces  on  the 
track  can  be  exerted  by  mechanical  jacks.  The  necessary  supporting  structure  should 
be  mobile.  To  simulate  thermal  stresses  in  the  field,  the  axial  compression  forces  in 
the  track  should  be  induced  using  electric  currents.  Each  rail  should  have  its  own 
circuit. 

In  conclusion  it  should  be  noted  that  because  of  the  large  variety  of  tests  to 
be  conducted,  which  will  include  the  determination  of  stresses  in  the  rails  due  to 
vertical  and  horizontal  loads,  the  study  of  axial  rail  forces  induced  by  moving 
trains,  and  track  buckling  caused  by  temperature  stresses  and  the  moving  train, 
it  is  suggested  that  the  track  test  facility  be  as  versatile  as  possible.  Thus,  the  con- 
struction of  permanent  structures,  such  as  heavy  concrete  piers,  should  be  avoided 
whenever  mechanically  possible  and  economically  feasible. 

REFERENCES 

1.  Kerr,  A.  D.  "A  Model  Study  for  Vertical  Track.  Buckling",  High  Speed  Ground 
Transportation   Journal,   Vol.   7,   No.   3,   1973,    (DOT  Report,    1971). 

2.  Kerr,  A.  D.,  "On  the  stability  of  the  railroad  track  in  the  vertical  plane".  Rail 
International,  Nr.  2,  1974,  (DOT  Report,  1972). 

3.  Raab,  F.  "Tests  on  the  jointless  track"  ("Versuche  am  liickenlosen  Gleis",  in 
German),  Eisenbahntechnische  Rundschau,  H.  10,  1956. 

4.  Birmann,  F.  and  F.  Raab,  "To  the  development  of  the  continuously  welded 
track — Test  results  of  the  Karlsruhe  test  facility;  Their  analysis  and  interpreta- 
tion" ("Zur  Entwicklung  durchgehend  verschweisster  Gleise — Ergebnisse  bei 
Versuchen  auf  dem  Karlsruher  Priifstand;  Ihre  Auswertung  und  Deutung",  in 
German)    Eisenbahntechnische   Rundschau,   H.  8,   1960. 


8  Bulletin  654  —  American  Railway  Engineering  Association 

5.  Bartlett,  D.  L.,  J-  Tuora,  and  G.  R.  Smith,  "Experiments  on  the  Stability  of  the 
Long-welded  Rails",  British  Transport  Commission,  London,  1961. 

6.  Bromberg,  E.  M.  "The  Stability  of  the  Jointless  Track"  ( "Ustoichivost  Bessty- 
kogo  Puti",  in  Russian),  Transport,  Moscow,  1966. 

7.  Private  communication  to  author  by  M.  Janin  of  the  SNCF,   (Dec,  1973). 

8.  "The  test  on  buckling  of  curved  track",  The  Permanent  Way  Society  of  Japan, 
Nr.   1,  1958. 

9.  Ammann,  O.  and  C.  V.  Gruenewaldt,  "Tests  on  the  effect  of  axial  forces  in  the 
track"  ("Versuche  liber  die  Wirkung  von  Langskraften  im  Gleis,"  in  German), 
Organ  fiir  die  Fortschritte  des  Eisenbahnwesens,  1932. 

10.  Kerr,  A.  D.,  "The  lateral  buckling  of  railroad  tracks  due  to  constrained  thermal 
expansions",  Proc.  Symposium  on  Railroad  Track  Mechanics,  Princeton  Univer- 
sity, 1975. 


Advance  Report  of  Committee  17 — Maintenance  of  Way  Work  Equipment 

F.  H.  Smith,  Chairman 

Work  Equipment  Repair  Organizations  of 
North  American  Railroads 

Your  committee  presents,  as  information,  the  results  of  a  survey  of  equipment 
repair  organizations.  The  response  to  our  questionnaire  was  excellent  and  we  wish 
to  thank  all  those  who  contributed  data. 

ROADS   WITH    5,000   TO    24,000   MILES    OF   LINE 

Sixteen  roads  in  this  category  responded.  Of  these,  only  one  repairs  both  auto- 
motive and  maintenance-of-way  (M/W)  equipment.  This  probaljly  reflects  the 
travel  and  shipping  time  losses  attributable  to  central  vehicle  repair  as  opposed  to 
outside  local  shop  repair.  One  road  has  90  percent  of  both  automotive  and  M/W 
equipment  repair  done  in  outside  shops  and  another  has  all  automotive  and  75  per- 
cent of  M/W  overhauls  farmed  out.  As  might  be  expected,  tlie  one  road  that  re- 
pairs both  automotive  and  M/W  equipment  in  company  shops  also  has  one  of 
the  closest  shop  spacings. 

Of  the  14  roads  which  repair  all  M/W  equipment  in  company  shops,  tliree 
have  only  a  single  central  shop.  The  others  have  from  five  to  20  shops  of  various 
sizes.  The  following  table  equates  repair  facilities  and  manpower  with  length  of 
line: 

Number  of  Miles  of  Road  per: 


Central 
Shop 

All 
Shops 

Field 
Supervisor 

Field 
Mechanic 

Total 
Field 

Maximum 
Minimum 
Average 

19,459 
3,789 
8,509 

12,521 

446 

3,909 

5,118 

600 

1,689 

736 

78 

296 

736 

72 

255 

ROADS   WITH    1000   TO    5000   MILES    OF   LINE 

Six  roads  responded.  All  except  one  repair  M/W  equipment  only  and  ha\e 
only  one  central  shop.  One  repairs  both  automotive  and  M/W  equipment  and 
operates  a  central  shop  and  eight  smaller  shops.  The  entire  length  of  these  roads 
is  less  than  tlie  average  miles  per  shop  for  the  longer  roads.  Thus,  one  shop  pro- 
vides better  coverage. 

Number  of  Miles  of  Road  per: 

All  Field  Field  Total 

Shops  Supervisor        Mechanic  Field 

2278  Infinite  759  759 

564  928  87  83 

1247  —  237  223 

ROADS    WITH   500   TO    1000   MILES    OF   LINE 

Six  roads  responded.  Two  of  these  roads  repair  both  automotive  and  M/W 
equipment  in  company  shops  and  three  do  only  M/W  equipment.  One  has  all 
major  work  done  on  the  outside. 

9 


Central 
Shop 

Maximum 

2932 

Minimum 

1128 

Average 

1826 

Central 
Shop 

Maximum 

988 

Minimum 

542 

Average 

821 

10  Bulletin  654  —  American  Railway  Engineering  Association 

Nunil)cr  of  Miles  of  Road  per: 

All  Field  Field  Total 

Shops  Supervisor        Meehunic  Field 

946  Infinite  692  692 

144  247  60  54 

541  —  284  258 

ROADS    WITH    200   TO    500   MILES    OF   LINE 

Twelve  roads  responded.  As  line  miles  become  shorter,  more  roads  repair  both 
automotive  and  M/W  equipment  in  company  shops.  Five  roads  repair  both  auto- 
motive and  M/W  equipment,  the  remaining  seven  repair  M/W  only.  All  have  a 
single  central  shop  except  one  road  which  has  four  shops. 

Number  of  Miles  of  Road  per: 

Field  Field  Total 

Supervisor  Mechanic  Field 

Maximum  Infinite  393  393 

Minimum  67  16  16 

Average  292  161  148 

ROADS    WITH    LESS   THAN    200   MILES    OF   LINE 

Twenty-three  roads  responded.  Thirteen  repair  both  automotive  and  M/W 
equipment,  eight  repair  only  M/W  equipment  and  two  have  all  work  done  in  out- 
side shops.  Twenty-one  roads  maintaining  a  field  repair  force  employ  a  total  of  69 
repairmen  for  1843  miles  of  road,  an  average  of  27  miles  per  man.  Obviously,  urban 
miles  are  more  difficult  than  rural  miles,  and  miles  of  track  may  be  several  times 
the  miles  of  line  for  these  roads. 

CONCLUSIONS 

In  looking  at  the  statistics  provided  by  the  responding  roads,  certain  points  of 
agreement,  near  agreement  and  disagreement  are  obvious: 

1.  Few  of  the  longer  roads  repair  both  automotive  and  M/W  equipment  in 
company  shops;  many  of  the  roads  under  500  miles  in  length  repair  both.  This  is 
probably  a  matter  of  geography  and  logistics.  In  some  cases,  the  extra  automotive 
work  probably  helps  to  justify  the  existence  of  shops  and  shop  equipment. 

2.  Few  of  the  longer  roads  rely  exclusively  on  one  central  shop,  again  prob- 
ably a  matter  of  logistics.  Almost  all  of  the  roads  under  500  miles  in  length  have 
only  a  single  central  shop.  However,  in  both  classes  of  road,  there  are  outstanding 
exceptions  to  the  rule 

3.  One  might  think  that  the  various  roads  had  made  a  decision  to  balance 
their  repair  forces  by  choosing  between  frequent  shop  facilities  and  frequent  field 
people  to  insure  prompt  and  adequate  handling  of  machine  problems.  Such  does 
not  appear  to  be  the  case.  Roads  with  most  closely  spaced  shops  also  tend  to  have 
most  closely  spaced  field  repairmen.  Obviously,  the  enormity  of  some  central  shops 
makes  up  for  some  lack  of  closely  spaced  facilities  while  increasing  logistic  prob- 
lems. The  accompanying  table  illustrates  the  wide  variation  in  repair  organization 
spacings: 


Road 

Miles  per  Shop 

Low  frequency 

of  s 

hops 

and  field  men: 

A 

4,077 

B 

2,187 

C 

7,361 

D 

12,521 

Balanced  frequency 

E 

931 

F 

10,200 

G 

676 

Frequent 

shops 

and 

field 

men: 

H 

517 

I 

868 

J 

446 

K 

1,145 

L 

1,450 

Work  Equipment  Repair  Organizations  11 

Miles  per  Field  Man 

453 
437 
736 
224 

320 
176 

287 

73 
111 
76 
72 
89 

The  most  capable  facility  is  the  large,  completely  equipped  shop.  In  its 
ultimate  state  of  perfection,  it  would  be  able  to  build  an  entire  fleet  of  maintenance 
machinery  from  scratch.  Where  complete  machine  rebuilding  or  major  component 
rebuilding  on  the  property  is  required,  a  major  shop  is  a  necessity.  Contracting  with 
outside  shops  or  scrap-early-and-buy-new  would  be  reasonable  alternatives. 

The  key  factor  in  any  M/W  repair  organization  is  the  field  repairman,  his 
equipment  and  the  size  of  his  territory.  If  his  territory  is  too  large,  he  will  spend 
more  time  travelling  than  in  doing  repair  work.  If  his  territory  is  small  and  if  he  is 
well  equipped,  he  will  be  able  to  do  work  that  would  otherwise  go  to  a  shop.  In 
the  foregoing  mileage  tabulations,  average  miles  of  road  per  field  mechanic  are 
296,  237,  284,  161  and  28,  in  order  from  the  longest  roads  to  the  shortest.  Similarly, 
average  miles  of  road  jjer  field  person  (supervisors  and  mechanics)  are  255,  223, 
258,  148  and  27.  If  heavy  reliance  is  to  be  placed  on  field  repair,  it  seems  certain 
that  the  average  mileage  figures  should  not  be  exceeded.  Indeed,  they  should  be 
reduced,  perhaps  nearing  minimum  figures  shown. 

It  is  true  that  good,  properly  trained  operators  can  sulistitute  for  or  minimize 
the  need  for  repairmen.  Similarly,  well  equipped  and  competent  field  repairmen 
can  substitute  for  and  minimize  the  need  for  shop  facilities.  With  some  limitations, 
the  reverse  is  also  true.  Thus,  a  repair  organization  can  be  flexible  . 

Our  survey  of  field  repair  vehicles  shows  a  preference  for  /i-ton  utility  trucks. 
In  view  of  the  rough  terrain  and  substantial  payloads  these  trucks  must  handle,  this 
is  the  minimum  rating  that  can  be  recommended  and  in  many  cases  may  be  too 
light  for  tire  and  suspension  economy  and  safety;  particularly  when  equipped  at 
the  low  end  of  the  6000  to  9000  gross-vehicle- weight  (GVW)  range.  Sample 
trucks  in  the  repair  fleet  should  be  check  weighed.  A  few  roads  use  very  sizcabk' 
vans:  12,000  to  30,000  CVW  with  miniature  shops  built  in.  Choice  between  the 
utility  truck  and  the  shop-van  is  one  of  money  and  organization.  Where  major 
work  is  done  in  the  field  and  a  heavy  premium  is  placed  on  field  ability  to  return 
machines  to  service  (juickly,  extra  cost  of  the  van  can  be  easy  to  justify.  A  tabula- 
tion of  trucks  and  equipment  is  shown  on  page  12. 

In  developing  or  altering  a  repair  organization,  certain  genera]  considerations 
apply.  Both  shop  and  field  work  have  some  unique  advantages  to  which  the  final 
scheme  should  adapt. 


12 


Bulletin  654 — American  Railway  Engineering  Association 


Shop: 

Shelter  and  workinjf  environmental  control. 

Parts    inventory   and   procurement   potential. 

Specialized  personnel. 

Specialized  and  expensive  tools  and  eqtn'pment. 

Stenographic,  commvmications  and  other  office  facilities. 

Central  control  of  fleet. 

FrELD: 

Elimination  of  shipping  effort  and  time. 

Knowledge  of  recent  machine  history. 

Access  to  operator  diagnosis  and  assistance. 

Communication  with  local  users  for  best  time  and  effort  management. 

Since  repair  facilities  always  seem  to  lag  behind  the  growth  of  the  M/W 
fleet,  roads  with  better  than  average  organizations  are  certainly  nearer  an  optimum 
condition.  Also,  the  fact  that  few  or  none  of  the  roads  may  follow  some  certain 
course,  does  not  mean  that  the  course  is  wrong.  That  course  may  have  been  un- 
explored or  its  time  may  have  only  just  arrived. 


VEHICLES  FURNISHED  TO  MAIMTENAMCE  OF  WAY  EQUIPHeWT  REPAIR  PERSONNEL 


ROAD     SIZE 

MILES       OF 

LINE 

U     T 

OVER 

ONE  TON 

2i 

I     L     I 
ONE 
TON 

5 

T     Y 

i 
TON 

6 

V      A 

N 

PICK 

TOM 

UPS 

i- 

TOM 

OTHER 

TWO  TON 
UP 

1^ 

TOM 

ONE 
TON 

i 
TOM 

TOTAL 

OVER  $000 

16 

1000  -  5000 

1 

1 

2i 

i 

1 

6 

SOO  -   1000 

1 

2 

i 

2i 

i_ 

6 

200  -  500 

7 

1 

2 

10 

UNDER  200 

6 

2 

2 

I4 

5 

19 

3i 


23i 


hi 


hk 


EQUIPMENT  FURNISHED  ON  MAINTENANCE  OF  WAY  REPAIR  VEHICLES 


ROAD     SIZE 

MILES       OF 

LINE 

HOIST  OR 
CRANE 

6i 

ELECTRIC 
WELDER 

16 

GAS 
WELD 

16 

AIR 

COMPRESSOR 

3 

HYDRAULIC 

SYSTEM 
ANALYZER 

Si 

NO 
REPLY 

0 

TOTAL 
ROADS 

OVER  5000 

16 

1000  -  5000 

2 

5 

5 

1 

3 

1 

6 

500  -    1000 

0 

3 

5 

0 

3 

0 

6 

200  -  500 

0 

5 

7 

2 

2 

1 

10* 

UNDER  200 

1 

_9_ 

11 

6 

Ji_ 

0 

W» 

TOTALS 

9i 

38 

hh 

n, 

m 

2 

57 

«  Additional  roads  do  not  furnish  a  vehicle. 

NOTE:  Fractions  denote  equipment  furnished  to  only  part  of  fleet. 


Advance   Report  of   Committee  3 — Ties  and   Wood   Preservation 
Report   on   Assignment   5 

Service  Records 

K.  C.   Edscorn  (chairman,  subcommittee),  L.  C.  Collister,  M.  J.  Crespo,  E.  M. 
CuMMiNGS,  J.  K.  Gloster,  H.  E.  Richardson,  R.  H.  Savage,  G.  D.  Summers. 

TIE  RENEWALS  AND   COSTS 

Statistics  providintr  information  on  cross  tie  renewals  and  average  tie  costs  for 
the  year  1974,  as  compiled  by  the  Economics  and  Finance  Department,  Associa- 
tion of  American  Railroads,  are  presented  on  following  pages  in  Tables  A  and  B. 

The  1974  statistics  on  new  tie  renewals  by  Class  I  U.S.  Railroads  compared 
with   1973  are  as  follows: 

Total  New  Renewals 

Year  Tie  Renewals  Per  Mile 

1973   17,856,780"  61 

1974   IS.SlO.aSS""  65 


"  Includes   28,63.5   concrete  ties,   excludes   819,324   secondhand   ties. 
*"  Includes   28,690   concrete  ties,   excludes   669,787   secondhand  ties. 

By  geographical  districts,  the  Eastern  Roads  inserted  in  replacement  53  ties 
per  mile,  the  Southern  Roads  97  ties  per  mile  and  the  Western  Roads  65  ties  per 
mile. 

"Indicated"  wooden  tie  life  determined  by  dividing  the  total  number  of  ties 
in  track  (1967  figures)  by  the  number  of  new  ties  inserted  in  1974  is  as  follows: 
Eastern  Roads  57  years.  Southern  Roads  32  years.  Western  Roads  50  years,  all  U.  S. 
Class  I  Roads  47  years. 

The  most  significant  change  to  be  noted  in  the  1974  tables  is  the  average  cost 
of  cross  ties  in  comparison  to  last  year.  The  inflationary  spiral  contributed  to  in- 
creases in  stumpage  prices  for  timber,  labor  and  fuel.  The  shortage  of  fuel  oil 
resulted  in  substantial  increases  in  the  cost  of  preservatives.  The  combination  of 
all  factors  provided  a  dramatic  increase  in  the  average  cost  of  43%  over  1973. 

Obviously,  maintenance  budgets  were  strained  under  this  cost  burden  which 
perhaps  accounts  for  the  rather  meager  57o  increase  in  tie  renewals.  Considering 
the  indicated  service  life  abo\'e,  it  is  apparent  that  more  ties  should  be  replaced 
and  likely  would  be  if  costs  were  more  in  line  with  revenues. 

The  Western  District  replacements  increased  by  17%  while  the  Eastern  Dis- 
trict and  Southern   District  showed  decreases  of  67c  and  2%,  respectively. 

The  number  of  concrete  ties  inserted  was  almost  exactly  tlie  same  as  in  1973, 
but  the  average  cost  of  these  ties  was  up  alnujst  44'i. 


13 


14  Bulletin  654 — American  Railway  Engineering  Association 


H     ^ 


^ 

^    0)  o 

<U     0.0    S 

ov  .-(  ^D  in  (^ 

O   O   00    so   00 

in     rH     in     OS     rH 

3         OH 

CM 

rH    O    ^    ^    rg 

r^  so  (js  00  en 

OS  <f  cjs  en  in 

en  en  -1  CM  O 



C    w  w 

(--1  vD  in  <I  <^ 

CO    O    OO   sr    CM 

r-i  in  o  r^  00 

>J  C?s  CM   m  ^ 

(U    o 

05    u 

QJ 

^ 

00 

^  <N  <f   OS  o 

<f  OS  r-l  in  <r 

CM  en  oo  in  o 

rH    O    O    rH    <f 

Qi     ctj 

3    u          (1> 

<r  en  rt  CM  ^ 

CM  <7s  o   r^  00 

en  OO  OS  en  rH 

-H     u 

lU     (0     U  -J 

.-H 

J5cjs-d-<r  CM 

(N  en  oo  -cr  CO 

en  <  <r  CM  OS 

C     O     11    -rf 

> 

(u   u   a  g 

O     4J 

B! 

n    c 

0)    -O            QJ 

g 

J3    -r^     M    ^ 

o 

--I  <Ji  O  O  l^ 

rH   r-  <r  CM  -;f 

OS  CM  en  CM  in 

3    1> 

B   (0   (U  -r^ 

^  r^  in  (O  ^ 

r-  r^  CM  so  CM 

r-l  en  in  -3-  OS 

en  in  in  CM  oo 

(U     u 

3  -^   a  e 

z   m 

z 

o. 

4J    .-H 

C    tU   --H 

00  CT^  Csl   O   CO 

c^  CM  r-  in  O 

r-l    <!■    r-l    r-    CM 

en  CM  en  in  CM 

s  s-^  s 

o\ 

m  in  r^  r-l  m 

en    so    00    rH    00 

so    O    oo    -a-    rH 

rH    00    00    so    OS 

•     >     •     •     • 

M     C           -^ 

rH    rH    rH             CM 

tli    Q)     O    u 

(U    U     t-1 

Ji 

ral 

a>         o 

rH    SO    OS    OO    O 

(» 

CO  00  CM  r-  .-H 

CO  en  in  r-i  so 
OS  so  en  e^  OS 

en  <r  OS  r^  r^ 

CM    in  Csl    sO  CM 

c  .-^ 

0)    -H     O     1-1 

in  in  o  r~  in 

so  in  00  r~  OS 

sO  rH  o  en  in 

O    m 

a,   B        JJ 

JJ  -o 

CM    CM    CO    r-l    <J1 

en  in  en  CM  r^ 

r^  in  <■  -d-  so 

C 
o    3 

"* 

a\  CO  r^  f-H  v3- 

so    rJ   so    so    CO 

en  o  <f  CN  rH 

in  00  in  eji  o 

l-i    0 

00  in  ^  ^  en 

O     OS    CM     rH     rH 

so  en  so  <r  so 

rH   CO   O    en  CM 

M  J= 

o  O  p~  in  w 

C7S  r^  r^  <j-  so 

en  1^  ^f  <f  in 

4J 

•o  ^-' 

O   en  OO  l^  so 

■u 

t^ 

\D  CM  en  >d"  (£) 

so  r-l  o  r^  c^ 

OS  r^  en  1-^  CO 

O  en  so  rH  <r 

o 

in  O  in  en  r^ 

in  so  r-4  o  so 

en  so  in  -3-  en 

.^    in    rH    (O    rH 

(U   at 

H 

3  -1 

rH  m  ^  m 

00  so        en  CM 

(JS    CJS    rH    r^    >J 

CT*  -H 

u  e 

«) 

O    CN  O   <f  O 

o  m  00  CM  o 

en  O  so  O   00 

o  CN  -a-  OO  OS 

m    dj    B  vo 

in  <r  o  r-  o 

in  en  OS  00  o 

<f  o  cjs  00  in 

so  m  CJS  m  CM 

O    -H          C3\ 

OS  O  CJi  00  o 

CT\  (Js  r^  00  o 

O    rH    00    00   o 

OS   rH    O    rH   00 

M    4J     VJ    .-1 

U           (U  ~-^ 

en  en  CM  CM  en 

CM  en  en  m  CM 

o. 

CTi  00  o  o  o 

00  o  <f  in  o 

CM    sD  C3S   00   en 

O    CM    CO    CM    CM 

P3 

,-1  en  00  .-1  OS 

sD  so  in  IN  <r 

i^  in  en  CTi  so 

00    r^   -H   (N    O 

•O     O 

<f    <r    f^    OS    r-l 

VO    so    r-l    o    CJS 

rH    sO    r^    OS    ^ 

00  00  o  <r  m 

C    ^ 

^      Oj 

o  .-1  en  en  r~. 

CO  .-1  in  in  en 

00  r^  so  <!■  en 

r^  00  CO  so  o 

•H     -r-t 

(U     (0     (0 

^  o  CO  r^  00 

o  <f  m  en  o 

OS  in  OS  en  m 

rH    Cs)    CJS    O    O 

a   to 

i-l     O     lU 

so  (N  in  .-1  --I 

so  00  r^  en  so 

rH  .-1  en  .^  <f 

-a  00  00  in  00 

4J      M 

0     H   -H 

c 

H    o   -u 

CM  en          rH  CM 

■H     00 

(11    c 

g     -H 

1   >. 

s.  in  p^  so  sD 

rH  r^  r^  en  CO 

CM    CJS  r^  CM  Csl 

OS   CJS   O    ^   so 

o   o 

O          tn       ' 

,-H  OS  so  in  c^ 

O   00  CsJ  sO  so 

CM  rH  en  o  o 

o  <r  OS  ^  en 

a   o. 

■a    CO    (0 

<M  en  ,-1  1^  en 

cjs  (M  so  <r  00 

1^    O     rH     (O    00 

CM    00   CM    r^  (O 

U     0) 

M     OJ     0     ID 

-;f 

H    1-1 

CJ    -H    H    -H 

.-H  a  o  4J 

■r^       3 

S   u 

OS 

r-i                     r^ 

•o 

....    en 

in    ...     . 

.    rsi  CN  <!-     1 

00      ...       1 

C  -O    CO 

o 

O     C     01 

tn 

r^ 

00 

O      (U    -r-l 

(1)    J=     4-1 

so 

CM 

vt    c 

•H     g 

QJ 

O  en  00  O   r-l 

i^  O  O  so  r~- 

CM   OS  o   en   rH 

>d"  00  in  CO  so 

o 

«    (13 

0pj3| 
CO 
U    iJ 

<r    CO     CM     r-l    CNI 

CM    00  <f   CM   so 

CJS  OS  m  O  OS 

CJS   m   so    rH    o 

0(3  r-j  CO  r-!  en 

O  .^  CM   OS  r^ 

.-H  o  in  o  00 

OS    00    00    rH    rH 

0)     (0 

0    & 

>  o 

U     Q) 

<:  o 

O     U 

c  c 

•H 

(U    -H 

O   T> 

O    -H 

3 

01 

r^  CN  in  00  so 

00   C3S   en   O  <M 

<r  CJS  so  <r  CJS 

00     00    vj-     OS    rH 

3    nJ 

z 

J3 

so   .-H    .-1    ^    CO 

CM   so  en  en  <f 

CM  <f  OS  en  -a- 

.J-    1^    rH    O    vf 

z 

--H 

00  .-1  <r  so  .-H 

O   O  CM    r^   CN 

<!"  1^  rH  in  m 

in  CJS  <r  o  in 

CO  r-l  00  in  so 

<j-  CM  in  00  OS 

en  CN  r^  in  so 

en  in  so  so  CM 

en  in  o-  so 

en    CM     rH     (N     CO 

1^^  o  rH  en  m 

<■ 

1 1 ^ 1 

f-t 

01 

S 

QJ 

c 

c 

10         C 

3 

•rl               -H       C 

o 

>s 

O           iJ     O 

Id 

(0     QJ 

C                 4J    C 

(H 

■H       0)   t:  iH 

o 

00 

C     U 

r~t                 IH       O      OJ 

05 

C                          Q) 

•H     QJ 

rH                 O       n      4-1 

3                  -n 

►J    >-} 

M            X    M     CO 

c 

T3 

o            .an 

^^ 

cn             (0 

c 

>!                 o  w 

3         0 

C    C         1.3  U 

01    rH 

(1) 

O    O 

O     QJ           -H 

IH       O      O 

H 

^          -H    4J     <U 

•rl     Z      4J     J= 

QJ      CO    -o      O     (3 

(0      CO      C 

X    M  A! 

01  1-1        CO 

4-1   T3     OJ    13 

C      OJ    -H 

o 

M 

C         O    O    « 

C     -rl     (4-1       O 

C    S     B     >. 

•H 

o5 

O                 O  i-J 

■rl       O      O       B     .^) 

(0     X      O    rH      OJ 

Vj 

H 

4J      ..a  V4  " 

CO   (0        n 

W         H    O  'H 

3    .M      OJ    rH    T3 

4J 

c:          <:  la 

SA4g      .      . 

i3             H    rH 

(0      C     H    rH      C 

M 

(0  ^1   a; 

..a        ^         O 

M    3          (0    (0 

Q 

u   o   n  lO  K 

la  c           (0 

01           - .-) 

O      IH      CO    >    rH 

a 

JD    0           (U 

(0     rH     r-l      4) 

O      V4     4J     4J 

(0    H     -rl               M 

-t.   B   n   B 

C   -H    CO    (0    O. 

00    (0    -H    -rt       " 

r-l            O   4=    H 

C    <    -H     O     Q) 

O   -O     W     1-1     (0 

CO    3    o    o    c 

•O     C     00 

U 

O              4-1      00    (fl 

4J      CO     4J     4J      CO 

01     C    -H    -H     00 

H 

K      d    r-l      C      CO 

(0    C    C    C    01 

•H    rH     4J     4J      00 

■rl      CO    rH    X      C 

cn 

Jd     C     (U     (0     Q) 

<  <  pq  pa  m 

O     CO     01     0)    £ 

X      11      11       OJ     rH 

n      14    rH      QJ      O 

< 

pq  o  u  u  o 

U   Q   f=3   Q  W 

pa  (J  M  hJ  e-J 

M 

Tie  Renewals  and  Costs 


15 


ri  r^  o  ^  ov 

CJ^  r^  >a-  r^  o 

vO 

00  O  r--  O  CO 

en  -1  o  o 

rv 

r^^  CN  ~I  O  rl 

CTi  vO  O  vC  00 

r^ 

r~.  ^  <f  >f>  CM 
vT  <f  r~.  en  CM 

rJ    <f    NO    O 

m  r^  r^  en 

"2 

-3-  <!■  CT\  »  r~ 

fn  ijD  CO  <r  en 

r^  ^        ^^ 

CM   ^  ,-^ 

"" 

" 

O  r-  -a-  xO  -1 

r^  ON  00  CJN  lO 

-4-  CM  in  in  oo 

CM    O   C^J    <N 

o 

<N   o  O    <-l   tn 

ps.  so  ^J-  >J  sD 

00  in  <r  ^ 

vo  vo  »  00  m 

r^  00  en  rf  CM 

in 

^  CN-  <)■  vo  r^ 

>^     in    4n     CTS 

00 

-^ 

-' 

•— 1 

tn  >i)  o  CO  00 

sD  CO  r^  ^  CO 

-J  CM  en  lO  en 

fH    CM    O    ^ 

^  ^  en  n  CM 

vo  (jN  ON  r^  00 

vO    O    sO    m 

" 

" 

^^ 

OOONONCS-I 

lO   vD 

in 

^   en  CN   oo  ^ 

CM  o  in  in 

<r 

r^  r^  a\  00  ^o 

3  CN  !n  o  ON 

r^ 

-a-  00  <r  <r  NO 

^  O  -1   in 
CN  rj  in  <!■ 

en 

C^j   c~J    ^    CN    n-C 

IN     CN     rH     <r 

O  ^  U-,  --^  un 

O   <■    r^   CM   C7^ 

00 

in  <r  00  cjN  <3N 

O  CM  in  O 

ON 

u^  -<  en  cn  cjN 

o 

t^   ON  O    -1  <f 

O   CM    NO   CM 

00 

in  CM  f^  f^  ^ 

O  CN   en  CO  C3N 

00  in  <r  m  M 

<r  sr  r^  O 

r^ 

CM   ^   IN    O    1^ 

^  in  -J  l-~  vD 

r^ 

OO  r-  in  <r  in 

CTv  r-  oo  r- 

r-- 

^ 

^    OO    1^   03    -O 

00  <r  o  CN  o 

CM 

CJN  en  sO  en  CM 

<r  in  in  ^ 

_( 

in  o  -■  00  in 

00  en  00  r^  in 

cjN  CM  NO  <r 

NO 

ts  00  r-  ^  ^ 

^  CN  r^  o  ,-1 

<r 

en  in  c^  NO  O 

vO  r^  O  <1- 

en 

O  f^  c^  00  o 

CO  -1  in  o  cjx 

en 

ON  o  nT  ^   oo 

r-(  r^  r-  o 

,_( 

IT.  0>  00  O   00 

<r  in  <f  vo  en 

O   O  en  -(   i^ 

^  ^  en  o 

o 

^  J5   vO   n  O 

en  ov  CM  en  00 

ON 

^     vO    O    ON    00 

in  00  C7N  CM 

o 

CM               vO  in 

CN  (js  en  1^ 

r^ 

-1  r-~  in  ,-1  <r 

cjN  <r  ,-1  ^ 

00 

Cvl    <J 

M3 

-' 

en 

Cs]   CS    1^   --<    O 

tJN  ON  -J-   en  CN 

lO  o  in  NO  en 

<f  en  CM   00 

CM 

o  in  m  csi  o 

O 

in  o-  -1  <r  r~. 

00   ^   ^    00 

00 

(Js  O  O  -1   o 

r^  O  r^  CN  ON 

O 

NO  CM   o   O   ^ 

00    ^    i-H    C3N 

o 

^  <->  en  rocn 

<N  en^  encM 

en 

rg   en  en   en  en 

CM  en  en  CM 

en 

CT\  CM  -»  in  r^ 

o  CO  ^  en  CO 

00 

oo  m  o  r~.  ^ 

ON   CJN   00    PN- 

CM 

r^  r^  m  .— t  ^o 

NO 

r^   u-1  00   en  <r 

ON  NO  NO   en 

lO 

<r  lo  vo  vo  en 

en  oo  en  <f 

m 

00  tn  en  00  <r 

CJN  O   i-l   CM  o 

00 

,-1   CJN  vO   OO    -I 

in  CN  -a-  o 

CJN 

CJN  o  in  00  csi 

ON  en  r^  00  in 

en  ON  O   oo  CM 

NO   r^  On  ^ 

oo 

oo  r^  00  en  CM 

o 

en  en  00  CM  NO 

sf  r-  CN  m 

<r 

CM               r^  CM 

,— t  in  •-(  en 

CM 

^  CM    -1   O 

p^  C3N  en 

r^ 

en  o 

»o 

<r 

CM  en  -3- 

,-e 

ON   m  o    CT^    r-i 

CN   vD  CM   ON  o 

00 

in  CM  --I  en  CM 

en  NO  CN   -i 

in 

^  vO  in  r^  ^ 

CO 

CM   en  en  CN  O 

Ov  -1   c-l    ^   O 

en  in  -J  <r  -1 

n^    ^    CJN    <J    00 

in  r^  c^  ^ 

o 

CM  <f 

CN           ,-1 

r^ 

CM 

CTN  CM  en 

p-< 

,      ■    r.     ,    r, 

ON  <r    1   Lo    1 

1     O      1     O      1 

^    lO     1       1 

^ 

O          '■O 

CJN    vl-             00 

en 

o       o 

CNJ 

NO  r^ 

CO 

r^ 

^ 

O 

00   (^ 

NO 

'^ 

^ij  m  eg  CM   r- 

(N  en  r^  CO  <t 

-^ 

en  NO  en  CN  NO 

n^   en  CM    CM 

00 

^  o  <r  in  o^ 

00  00  en  r^  in 

i> 

NO     00     O      ^     NO 

.o  r^  00  oo  00 

CT>   00   NO    C^ 

r^  00  CTN  NO 

oo" 

r^  r^  en  o^  o 

^   CN    e3N    CC3   <3N 

^-1  f~t 

r-  lO  <N   a\  00 

<f 

vT  00  O  en  ON 

CJN   -1   o    1^ 

o 

-^  r^  00  00  en 

ON  lO  ^  CJ.  en 

r^ 

ON  in  00  ^  en 

00  en  ^  CM 

un  o  CT^  r-  O 

r^  en  en  o  CM 

-o 

ON   NO   O    O    i-i 

O   O  <f   CM 

NO 

o  <r  <r  CJ^  o 

^      oo     CJN     lO     F-H 

in 

r^  cji  o  CN  »-i 

^   NO  ON  en 

o 

oo  .-1  .-1  ■.o  in 

O   vO 

in 

^       o 

in  r--  CN 

o 

^  ^ 

<r 

^ 

CM 

<J- 

m                s 

0)                6 

C                o 

►J                0 

'^ 

■y 

<u 

.^ 

1-,     -rJ               ^ 

-1     CUl           CO 

^         <u\       ^ 

^                E 

OJl 

£   W            00 

C                          3 

•HO)            CO 

10                   M 

.    -H              U             O 

>   c  -oljs 

•H 

ea    <u           3 

•H 

o         m 

X   -H           CO 

Q 

•H               H 

oj  J!       XI  -a 

O 

H 

&.            CO          -, 

CO    J            ,-i 

O            4) 

CO    eO         -      C 

u 

O            CO 

CO         B  < 

C 

C           iJ 

►J       -a   CO 

c 

M 

u         tj          I-, 

Z    u    di 

M 

00                 0)  ^ 

Qi 

0) 

0!  r-1           <u  .-1 

C  -JS          u    >-. 

H 

01          u           C 

1^1     CO     CO      0 

X 

n  .-1    oj  3    « 

^r^                             [i,       H 

3  -o    en          a 

o    >, 

■o  j=             n 

M 

-<     CO           CJ 

a;  o  to    >, 

3 

c    1    oj  la  u 

CO   00         -Z 

Q 

lS    01   w 

-1             U 

O 

0)     -H    J=               C 

a>   vj        -o 

'H  -a    c 

o   ij   n  Ji  <u 

Oi:     3     00    C     C 

CO    U-,     CO     CO    -H 

•H    t.    t,    c 

3     00^    U 

1    J3     C     O     L. 

4J    ^    -O     -H      O 

>    CO    0)    u 

<u   o   c   o 

CO     CO    -J     S     OJ 

e 

c:  o  -H   00  c 

CO    o  j:    01 

CO 

C    w    o  ■«    c 

p:  u  -a  j:  4J 

CO     C     1-,     1-.    -H 

iJ 

•Ai    m    C    u    C 

C    u    CO    CJ    en 

H 

^  -J    o    o  ^ 

3    CO    3    CO 

o 

to  -H  _Q   o   a; 
E  S  S  Z  PL, 

H 

3 

u    ^    ^      <U    ^ 

o    <u    o    <u 

E-. 

1  Pm  PL,  a:  ti  3 

O 

<    U    fe    O    M 

►J  «  CO   3 

en 

16 


Bulletin  654 — American  Railway  Engineering  Association 


£. 

CO 

o  S 

(vj   r-  00  -^  m 

<r 

P^    00    CO 

O 

in  <t 

00 

00 

ON 

o 

m 

00 

CO 

NO 

o 

o 

3 

O  H 

o  o 

CM 

r*  ^  O  r^  CM 

"0 

tn  oo  r^  CM 

'^. 

-J  in  CM 

o 

in  in 

r^ 

■^ 

oo 

'1 

o 

"^ 

'" 

oo  r^ 

in  in 

c 

C 

in  vo  CN  r^  r^ 

sO  in  m  %o 

o- 

CM    .H    00 

On 

f^  ON 

oo 

r^ 

<r 

o 

-3  en 

nO 

NO 

r^ 

Ol  \0 

a> 

CN   r^ 

-J 

<f 

cd 

■^ 

00 

~ 

CO 

^     OJ 

cr>  o^  r^  m  r^ 

ON  nD  r-^ 

CM  r^ 

ON 

[^ 

NO 

<r  r~, 

00 

o 

p^ 

rj  o  r  - 

OJ    u 

3 

u-lO  ON   -1 

NO  00  in 

o  in 

-J- 

<f 

<r 

o 

in  tTN  r- 

<l> 

c 

(X  -r-l 

,—1 

u-i  <j-  in  m  vf 

r-( 

in<r  in  vD 

r-l 

nO      CNJ       .-I 

in 

p-  r^ 

tn 

lO 

en 

,-1 

en 

IN 

CN  <r 

NO 

in 

in 

t^j  in  r  ] 

-tJ   > 

c 

E 

<n- 

CM 

^ 

^ 

NO 

^ 

o   c 

ni 

01 

u 

T 

Xi 

i^     r^ 

o 

-J-  m  CN4  in  <t 

ON 

c>  t^  r^  nC 

o 

00  00  in 

00 

ON    00 

00 

en 

r^ 

CM 

o 

en 

nO 

00 

00  o 

,_^ 

T~* 

in 

3    y 

e 

<1>    -H 

^o  v£)  u-^  ^  in 

CM 

in-j-  o  r- 

00   CN    CN 

-3- 

00    00 

in 

vf 

<r 

en 

<!■ 

O 

in 

NO 

NO 

m  no  rn 

a>    nj 

3 

a  E 

2  ^ 

Z 

a. 

0) 

4J 

r-t 

C 

n)  -1    m 

^  vD  in  i^  O 

o  in  a.  in 

r^  <r  in 

o 

ON  r^ 

o 

o 

-3- 

O 

o 

ON    oo 

o 

o 

en 

P^  en  ^ 

3 

'-'     01 

O  O  r-*  <r  00 

0^ 

ON-j  <r  in 

CN-l 

00   ON  O 

"^ 

00  o 

c^ 

NO 

oo 

^ 

r^ 

r-i 

in 

-3- 

CO  r- 

Pn. 

o 

■"-l 

O    rH    O 

" 

c   '"  Li 

On 

CM*    CN     r-^     rH    w 

.-1  ^  O    CM 

in     '  ,-H 

r^ 

cm'  tn 

r^ 

-3- 

.-h' 

^ 

oo 

r^ 

tn 

'   rJ 

r^ 

cm' 

cm' 

f-H   fNl    r-H 

(U    o 

fa 

>- 

4J 

~ 

~ 

j^ 

CN    in    r-l    CN    00 

oo" 

<f  NO  ^  in 

CM 

in  C7N  en 

o 

O    OnI 

"no" 

"in" 

en 

"nO^ 

"oT 

^ 

cn  en 

"in~ 

NO 

00 

1    '^l 

01 

o 

00  P-)  vo  cr-  <r> 

o 

r^  00  ON  00 

O- 

CM    ON   o 

o 

O  r^ 

ON 

00 

O 

en  ON 

cn 

Vj 

in  n 

r--  o>  00  o  00 

O-   en  ON 

r^ 

en  CO 

r^ 

NO 

00 

<f  o 

r^ 

C    -^N 

0) 

o    U 

O    w 

E 

±j 

o^  ^wD  vT  ^  in 

r^ 

00  vO  O    c^ 

r-~         .-( 

On  en 

nD 

CO 

<r 

<r 

<r  en 

00 

r^ 

NO    '^ 

4J     -O 

c 

O     3 

^ 

^ 

^ 

•"^ 

o  ^  O  tN  -^l- 

~ 

^o  o  n 

to 

00   00  .-1 

NO 

r~  ON 

■<r 

7 

^ 

NO 

~ 

NO 

r^ 

NO 

en   r-l 

<o 

^ 

)-«    o 

ON 

ONO\  <t  o 

00  m  <r 

<f 

NO     C-J 

00 

<f 

NO 

CM 

<r  r- 

CM 

nJ 

W)  X 

CM  O   in  00  o^ 

CM 

oo  in  --< 

m 

00  O   00 

<f 

ON    CM 

o 

r^ 

NO 

NO 

r* 

f-* 

r~  <r 

00 

<f 

CN 

rj  tz> 

J_l 

t3    '-^ 

^    O    ^     (^    rH 

r^ 

ndnd  <r  <r 

tn  r-  00 

00    ON 

NO 

<f 

r^  00 

O 

r-- 

O   O   ^  CO  ^ 

o  in  <r  nH 

O  NO  w 

r^  r^ 

o 

<r 

r^ 

r^ 

NO 

o 

O  <f 

<f 

00 

jj    m 

0 

E- 

r^  CO  m  Ol  o 

<T 

cno-  rM  ro 

00 

00          CM 

en 

o  <r 

in 

'-* 

NO 

00 

NO 

NO 

<r 

NO 

en  CN 

en 

CM 

•-' 

r-  o 

CO      Q) 
3     r-H 

tN    (T.   -3-   O   CM 

in 

en  in  CM  in 

NO 

<r 

CM   ^ 

c^ 

r-l 

,_i 

NO 

f^ 

rH    CM 

r^ 

NO 

CM 

C71  to 

cr  -H 

00  o  ^  in  in 

<t 

o 

<f 

00 

w   e 

W 

!^ 

*"* 

a 

ro  CT%  .-H   ro  O 

o 

r^ON  o  «-! 

o 

ON  o   r^ 

<f 

00  o 

m 

a\ 

00 

o 

in 

in 

OO 

00  r^ 

in 

CM 

CN 

-H  r^ 

CO  r^  ON  o 

ON  o  .-1 

o 

CO   CO 

o 

tn  -3- 

NO    CM 

tn  NO  tz) 

c 

rH  o  cy*  o  o> 

o 

O  ON  00  o 

.-1  O  <f 

O   00 

o 

o 

o 

CJN 

ON 

o 

r-l    00 

ON 

o 

o 

CJ^  tTi  O 

o 

■H             ON 

*- 

m  en  CM  po  (N 

m  CM  CM    f^ 

CN 

CO 

u 

CO 

Q- 

~ 

~ 

o  o^  r^  r^  o 

in 

<1-  O  NO   CN 

r^ 

IN    O    ■-< 

en  o 

"^ 

NO 

<r 

NO 

o 

o 

77" 

00  r~. 

^ 

NO 

NO 

O  Kl  O 

-o    o 

O  --t  r-H  rn  r-- 

vj-   CN 

<f 

o 

ON    <f 

00  <r 

o 

CD  I— I  O 

Q)     U 

O  r^  ^  in  cr. 

■<J- 

OOO   NO    ,-1 

CM 

m  r^  in 

00 

O   1^ 

CO 

<f 

.— 1 

CM 

r^ 

o 

00 

tn  ON 

CnJ 

ON 

r-l 

C3  rn  i» 

C  --1 

r-l      W       W 

ca    dJ 

O   ^O    1^  00  oo 

o  ^r  r~~ 

o 

<]■    00 

o 

en 

en  o 

00 

r^ 

NO 

o  in  in 

CO     to 

O    -H 

<j-  P-)  in  vo  r^ 

r^ 

ONCN    ON    ,-1 

<r  O  r- 

ON 

o 

<f 

NO 

c 

■H     00 

H    o 

vo  a\  <r  CM  cN 

<N 

(>j  en  in  <M 

00 

CM    in  CM 

o 

in  o 

in 

in 

CM 

f^ 

cn 

-3- 

IN 

r^ 

ON    .-1 

en 

CNJ 

1^ 

r-t  rH   r-l 

ON  .-1  CT\  r-  vo 

CM 

00  <M            -J- 

r^ 

00 

O  w 

o 

in 

in 

00 

r^ 

p^ 

in 

en 

CN 

0>  rt  Pi 

(0    c 

in  c^  m  CO  CM 

<r 

00 

CX9  NO 

E    -H 

<J- 

OO 

^  tJ 

1 

>N 

o   o 

J2              Ol 

CO     O. 

o 

00   CM    ^   00   00 

r-.-i  NO  -^r 

en  CO  in 

r^ 

00 

o 

NO 

in  NO 

-3 

O  CTN  ^ 

T3     W     W 

r^  in  CO  00  ^ 

-^ 

00  oo  O  O 

O 

NO     NO    ,-1 

O  00 

-3- 

en 

ON  in 

00 

o 

CO 

H      ^4 

s 

0)     O     (U 

3 

<f 

CO  O    rn  CM  00 

NOr-~  IN  <f 

^''" 

!C 

On  en 

ON 

" 

NO 

in 

en 

en 

""^ 

r^ 

CO 

ON 

tn  NO  p^ 
o  o 

ia 

^ 

CM 

C  TJ    to 

in  cr>  CO  r^  m 

rn 

NO  in    1    <f 

NO 

(    tn  .-J 

00 

,         , 

7 

7 

1 

r^ 

1 

1 

7 

7" 

1    en 

1 

00 

P^ 

0   c  (u 

r-^  en  o  ^  r^ 

3 

<r  r^ 

<r 

ON    00 

ON 

o 

00 

O     to    -H 

ro 

rn  tn  m  00  ON 

<f  o 

•-' 

NO   IN 

in 

en 

'-' 

00 

r^ 

r^ 

^ 

ri-       ^ 

csi  in  <n  r^  <j- 

CM  i-t 

in 

o 

._( 

<f 

CN 

CM 

ON 

to    C 

o 

NO 

•H    E 

4J     (U 

Csl          <-> 

NO 

NO 

J3l 

<-> 

60  4.) 
to    m 

w   ^ 

fo  r^  in  r-  <J 

CO 

O  O  in  in 

o 

cTN  ^  <r 

NO 

NO     ON 

^ 

NO 

00 

-3 

._! 

CM 

o 

in 

r^  r^ 

nD 

en 

ON 

nO  n  00 

O     J-" 

!-■     O 

CN 

r-  .-H  CM  o  ON 

^ 

<1--J-  in  o 

r^ 

00    .-H    o 

NO 

CO  in 

NO 

<r 

CN 

CO 

ON 

in 

r^ 

O 

in  r^ 

O^ 

r^ 

o 

CTN  fO  oo 

P> 

00  r--  t-i  r^  r^ 

^ 

ON  ON  00    00 

r^ 

CO   O   NO 

o 

r^  00 

NO 

r^ 

r^ 

r^ 

o 

r^ 

r^ 

cm' 

r^  ON 

^ 

00 

ON 

p^  tjl  t» 

c   c 

0)    -H 

S 

-5 

•-' 

^ 

^ 

-' 

^ 

•-• 

r-4 

'-' 

ON  CO  <r  in  O 

OS 

ON  r^  <f  in 

IN 

CNJ     f^    NO 

00 

O   NO 

"in" 

"on" 

NO 

CO 

00 

NO 

"ltT 

-3- 

O  w 

CO 

,_( 

in 

p^  m  tn 

"O 

o  o  CO  <r  in 

c» 

r^  cNj  00  o 

NO   <1-    O 

00    ON 

-3 

00 

<r  CO 

1— 1  oo  n£) 

o  -o 

O      -rH 

3    c« 

4-J 

^^ 

en  00  f^  o  in 

t^ 

NO  00  <r  to 

■-I 

<r 

in  NO 

-3- 

CM 

<r 

r^ 

NO 

o 

00 

r^ 

en  NO 

t^ 

o 

en 

in  nf  in 

3 

CJ 

\0   CM    O    CO   fO 

•-^ 

r--  t*i  CM  r^ 

cn 

<f   -Cf   IN 

,^ 

<t  en 

,_( 

NO 

CJN 

r^ 

ON 

,_! 

00 

in 

CO  c^ 

o 

«n 

CTN 

CjN  v£>  nj 

3 

z 

ON  ON  ON  ^  r^ 

m  CO  NO  o 

00  en 

<f 

<f 

o 

NO 

f^ 

in  o  na 

Z 

^  00  v^  in  -^ 

1-1            ft 

<■ 

•~* 

00 

rn 

CM 

CM 

00 

1— ' 

NO 

CM 

00 

ON  rn 

'"' 

^  ^ 

ON 

00 

^ 

lUl 

3 

oil                   Jo    -H 

C     00 

fe               ^    o 

>4     C     o 

*"!     hn  ^ 

-§ 

(0 
CO                 ^   PU 

QJ     to    -H 
u   OS  >u 

C     C  N« 

B 

o 

ij        d   3 

U            -H 

•H     ■r^     T3 

0 

fti 

C            M     CO    t^ 

CO            <U    Ph 

<U     B     U 

3   o   10 

M 

w 

c 

^ 

a 

O 

TJ 

W           4J          TJ 

M    Hi 

C    O.  -H 

10 

<u 

10 

■H 

C 

C     W      •    C 

c 

tU    H            U 

C 

ti  j:  N„ 

X 

c 

V 

CO 

Lfl      }^      di     4J      CO 

(U 

-a       os  01 

n 

£   M   u 

s 

^ 

c 

s 

0 

'r1 

3 

in 

2 

i-J         73 

4J 

j: 

10         oo  c 

■u 

Vj 

3 

■^ 

to    O    B 

^     4J    JS        "  h-l 

4J 

U     V     V     01 

3   n3    o 

•H     to 

fc. 

X 

10 

O 

JJ 

B  'rJ    10 

H 

di     U    iJ      ■ 

3 

0,0    0.0 

(U 

o       z 

to 

M-l    CM 

c 

to 

tn 

0  MJ  -^ 

CJ 

O.  O    U    3  ^ 

o 

to    ■r^ 

3 

M     U 

U 

c 

3 

•^ 

M 

B 

•H     O 

B 

■H   .H   J= 

H 

O   2    0  --I    O 

w 

0    M    C   i« 

o     - 

c 

O     C 

o 

10 

U     'r^ 

•o 

to 

1 

H          Z   '<-*    0 

•H    m    C 

•Ji 

>nt4    tn 

to 

o 

to 

4J 

o 

0  MJ 

0) 

§ 

to     10     M 

c      X  pi 

^ 

0*  :!  :d  -c 

JJ         l-l       'F-( 

lA 

CM    01 

fa 

B 

to 

a)  -rt 

■u 

JJ 

Z   fa     0 

n 

c   S  ^      «    ^ 

S  3   -u 

>, 

l-l 

fa 

X 

fa    o 

fa 

z 

M 

o 

.a             u 

to 

0    0.0 

w 

•f4 

OJ 

c 

« 

B 

oi 

B    B 

Q 

0    00  o    o    o 

•o 

-    -  o 

m 

3    0. 

3 

3 

C 

OJ 

Na  s 

-fa 

B 

3 

p 

to    10    0 

n   C   oo  00  00 

to 

n  £  j:  3 

to    t/3     10 

3 

3    3 

c 

o 

O 

B 

o 

u 

5 

•H    'H    .H 

M 

a;  4J  -u 

c 

10            &J 

O 

O  X 

o 

hJ 

iJ 

•J 

j: 

10 

•o   c 

a 

< 

■O  TJ     K 

J3    r-t     O     O     O 

o 

>    3    3    4J 

<u 

m   0)   C 

to    JJ 

oo 

J.! 

c;   o 

to 

to 

M 

Ex] 

O     1-1    -H    -H    -H 

C  ^  ^    ti 

c  J^    c 

to     U 

o 

3 

O 

X 

X 

JJ 

§ 

B     C    JJ 

H 

*J     3    J=    X   X 

0 

0)     3    3    O 

to     to    v^ 

:d  o 

u 

o 

0 

a 

4) 

v 

0   C 

(U 

o 

0 

to    to    B 
O  O  t5 

<  Pft  o  o  o 

CJ 

Q   Q   O   fe 

o 

^  hJ  S 

Z 

s  z 

o 

Cfl 

» 

w 

H 

H 

E-<   » 

3 

H 

H 

p 

Tie  Renewals  and  Costs 


17 


O     <U    00   <lt   ,i^ 


.    -^   00   00   00 


CT^    0%    r^   O 
C7\    CO    00    CT\ 


<t   <t    O^    OD 


01     U  r-i 


00    1-1    CNJ    <t    r-* 


c 

o; 

01 

■H 

T3 

E   « 

il 

■o 

U     CO 

w 

a.  o 

O 

£ 

M    g 

T3 

i*<    M    3    u 


U 


u  U   iJ   J    o 


<u   o   c   o 


O     O     3    iJ 
O     O 

oj  -o  c/3  .n 


<1>  -^ 


4j  bO  oo 


•H     OJ 


WW  U  tj  (U  ^*  "D 

X      W  VJ  u  iJ  U  4J 

y  <5  w  n  o  01  c 

<  S<S  'H  w  M  3  3 


.2  5 


18 


Bulletin  654 — American  Railway  Engineering  Association 


b 

rf 

^ 

a 

a 

t/i 

u 

rri 

H 

VJ 

^ 

O 
OS. 

3 

u 

3 

a> 

C    J.! 
lU     o 
n    « 

0)    u 

u     C 
•H 

O     D 

s  -^ 

C     CO 
C    iJ 

> 

in    CO 

vT  r^  CM   .-i  (» 
nJ  en  cx>  in  r-l 

CNJ    ON   00   00   CM 
Oi    P^   NO   (Ng   ^ 

r^  <3N  lO  <r  -^ 

r-l    eg    13    <f    00 

in  1^  o  en  < 

CN|,-<  ^cMcn 

,-(,-)    _|     (VJ     ^ 

■J-    .-(    rt    r-<    CN 

r-lrnrj            eg 

-J 

ON 

CO  CJN  es  o  cx) 

ON  c-j  i~.  in  o 
en  NO  00  o-i  00 

r-l  -J-  ^   r~  CNJ 

NO    O    00    -J     r-4 

.-<   00   00    *0   ON 

^  eN<  ^  ^  in 

CSJCM           <N 

^  ^  -^   en 

r-l_.r-4              CM 

£ 

O    O    -I    ON   ON 

00  NO  CO  NO  cNg 
NO  eN  in  ON  cNi 

<r  <r  en  in  <f 

ON  O   -^   CO  ^ 

in  oo  in  en  ON 
r-i  00  in  en  r-l 

-^-ir^en 

rN,-,         CN,^ 

^csi        ^.n 

eNrHcn        CN 

P^ 

<f  ON  ,-<  in  -< 
r^  O  00  in  00 

ts  f^  CNj  r-  NO 

in  o  O  O  >3- 
in  CN  00  ^o  ^ 

rJ  r-<  ON  Sf  ON 
O   r^  en  rJ  r^ 

-,    ^-.CNlen 

C-^CNrN,^ 

r»-          ^   r~t   cr\ 

rHrHCM            CN 

s 

S  ?;;;;SS 

<f  CO  e-M  ON  o 
en  rg  00  NO  n-1 

sssss 

in  ON  en  en  o 

in^rgoj^ 

^   en-H         ^ 

CM-^-^-H^ 

r^^cN          en 

o 

<f      NO     00     1^     NO 

-3-  in  r~  in  Kt 

in  <r  o  CNj  o 
CJN  CN  00  00  t^ 

CO  CM      1    00  CM 

O   O   r-l    ON   in 

ON  in  CNi  o  r- 

CNj        ^  en^ 

CNCN,^ 

oOr-4             en 

r-lr-l 

01     4-J 

u  -a 
01    C 

W    'H 
O    (U 

u  c 

It 

c 

i^    o 

°^ 

o  E 

"  ti 

0)  a 
u  a 

60  m 

BO  S 

M)  0) 

<   c 

U     60 
CO     CO 

a   u 

>,    01 

> 

in   CO 

<N  <r  o  ON  ON 

.-1     <r    fO    r-l    CNJ 

<f  n  en  <r  ON 

in  CO  00  (N  .-4 
en  en  en  ctn  in 
<t  en  en  en  cnI 

ejN  CN  in  en  On 

00    r-l    ON    ON    00 

CnI    00   C5N    00    NO 

W    (TnI    <t    ON    O 

vl-  n  ^  CM  -J 
CI  ON  o-  <r  <N 

-CT  ON  --I  in  -3- 
1>J   CTn  O   1^  00 

CM  en  CO  in  o 
CN  en  CO  <r  00 

r-l     O     O     r-l    <r 

cn  vj-  <^   CM  C3N 

ON 

o  c-1  o  in  [^ 
CO  m  NO  ON  cN 

in  <f  00  CM  NO 
m  m  o  en  -< 
in  IN  nH  in  CM 

CO  en  ON  in  r-l 
en  <r        en  r- 

<f  in  un  en  (JN 

NO     rH     00    O    CJN 

<f  <f  in   r-l  <f 

r^ 

tn  in  r~  o  in 
w  O  O  o  en 
m  cN  c-i  <r  00 

ON  -1  ON  in  ON 
<f  IN  <r  en  es 

CO  NO  ON  r~  -1 

CM   <f   NO  O  r-l 

en        CM  en  NO 

o  -3-  in  en  o 
CM  en  en         m 

ON 

rNi  in  <r  <f  00 
o  in  ON  r-  NO 
(»  CM  m  rn  en 

1^  «■  <r  NO  tjN 
ON  in  <f  00  NO 

en  NO  ON  NO  in 
NO  <f  in  -1  ^f 
en  en  en  CN  CM 

o  p^  oo  r^  NO 
00  00  m  <r  in 
CM  en  en       NO 

o 

in  <f  1^  NO  nd 
CM  c?N  r^  ON  o 
<^       cs  <f  en 

00  O  O  .-1   ON 

in  en  -J  00  NO 
r-l        in  en  CM 

NO    O       1     r-4    NO 
O     -Cf               NO    r-l 

in  r^  NO  en  o 

en    CM    r-l            CM 

C    M 
0)    H 

aj  -0 

4J      C 
M     « 
O     C 
U     0! 

ll 

a  o 

O   .-1 
•H 

u    B 
<u 

i     ^ 

z 

cu 
U     60 
CO     CO 
0)     l-i 
>N    OJ 

> 

m   CO 

r^  nJ  in  r^  e^ 

r^  en  <f  NO  en 
in  in  r^  NO  <j- 

r^  O  -1  r-l  r^ 
CN  <r  en  vl"  CO 

NO  nO  O  O  00 
vj-    in    r^    r-l    NO 

,-1  ON  o  o  e-. 
<f  r^  m  nd  NO 

-4   1^  <f  CM  <t 

ON  IN  m  CM  in 
rH  en  in  <f  ON 

en  in  in  CNi  00 

i 

VD  NO  -vf  ■-!  tM 

cN  en  <r  in  o 

On  r^  o  in  FN- 
r^  en  m  00  en 

o-  en  <f  en  in 
m  NO        in  o 

-a-    CTn   O    -1   CM 

NO     in    r-l     r-l    NO 

ON 

w  en  CNj  en  O- 

NO  NO  in  o  CO 
NO  -*  NO  00  en 

O  NO  CN   nD   NO 

en        in  <f  ON 

O  <f  <f  -3  CM 

r^ 

ON  cN  lo  <r  o 

NO  <f  NO  r^  in 

r-l 

ON  NO  -1  o  en 

en  CTN  m  CM  NO 

r^  -*  ■<f  en  ■<}■ 

NO  ITNl  en  rH  NO 
vf     NO    r^    rH    00 

O 

esi  r^  CNl  en  <f 
r^  ^  in  O  <r 

CO  r~.  00  r-l  ,-j 
CN        rs  00  in 

In  °    '   S  § 

vo  r^  rN*  en  c^ 
m  ^r  en       -3- 

1 

ID 

c 

<0 

■u 
l-l 

•H 
» 

H 
O 
M 

M 

a 
z 

i 

< 

60 
C 

3                       O 
O                           -rl 
>^                   ^     U 

o  u 

oS           O     O 

•H    4J     0) 

-  X     CO   J^ 

c       o  o  CO 

O                  O   iJ 

C               <   .Ji 
CO    V4    0) 
O     O     U    i3     t. 
^     O           (U 

-  n    E    n    B 

O             4J      00    CO 

u   C  .-1   d   CO 

^     C     CO     CO     01 

<;  <j  cQ  w  PQ 

i 

c 
c  u 

•H     0) 

S         o 

•H  Z   JJ  X 
O  >H           CO 
Ci   -H  IM    o 
•H     O     O     S    >^ 
CO    CO           u 

S  P4  P^   0)   OJ 

2  >  .M 

CO    rH    t-l      0) 

C   ■r^    CO    CO    o. 

O   rO     ^1     M     CO 
iJ     CO    iJ    4J     m 
<o    C    C    C    0) 
O     CO     <U  ,0)  J= 

«  u  u  u  o 

O          JO 

C                  4J     c 

■H        a   c   u 

r-l                 >J      O      0) 

-1            O     ti    u 
M          X    H     CO 

1-1    o    o 

OJ     CO   TD     O    ta 

4J  -a   0)  XI 

CD      3    rH      0)     U 
CO     K      O    r-l      0) 
W       ,    H      0    -rl 
1^             H    r-l 
l«             ^              O 
OJ              -<-, 
O      ^1     4J     4J 
60     CO     -rl     -r^         rN 

CO    3    o    o    c 

O      CO      M      M     •r< 

u  n  Q  «  w 

c 

4-1     CO 

CO    CO    C 

C      01     -rl 

C      3       g       >N 

3  .a  01  r-l  -a 

CO  C  H  r-(  C 
^    S          CO    CO 

CO  H  -H          CO 

rJ           O  ,C  H 

■O     C     00 

<U  C  'H  'H  60 
•H     CO    rH    J=     C 

W   O  H  iJ  iJ 

Tie  Renewals  and  Costs 


19 


ul  <f 

-T 

vt 

NO  in 

•<r 

in  in 

O  c^ 

ON 

NO     NO 

r^ 

<t  <f 

CM 

O  ON 

<f 

o  in 

in 

(N   <N 

'^ 

CM    r-l 

CM   ^ 

'-' 

<r  .-• 

-^ 

CM  CM 

in 

CM    CM 

CM 

en 

in  <f 

en 

00  a\ 

nv 

CM    ^ 

CM   CM 

m 

NO  vo 

in 

r-,  <n 

00    rH 

CM 

in  m 

<r 

r^  r^ 

UN 

00   NO 

^   CM 

t'l 

O   CTN 

r^ 

<f  CO 

<r 

<f    NO 

,-1 

o 

i-H  in 

^ 

CM   CM 

- 

CM   ^ 

CM    CM 

-^ 

<f 

-1 

CM   CM 

NO 

CM    CM 

CM 

CM 

in  o- 

en 

a-,  n 

r^ 

NO  <r 

ON    NO 

ON 

^  ^ 

-Olen 

ND 

^  in 

^ 

ON  -oi 

en 

i/i 

■^  r^ 

CO    t-H 

,-1 

o  in 

o 

r-l     00 

^-* 

o 

vt 

CM 

rg  CM 

CM 

CM    ^ 

CM    CM 

IN 

m  ,-1 

-^ 

CM 

in 

^    CM 

CM 

en 

-3- 

^ 

^£i    ^ 

00 

o  in 

O   ON 

rNv 

O   CM 

en 

•alen 

m 

m 

o  -oi 

<f 

r^ 

^  r^ 

l^ 

r^ 

r^ 

r-- 

CM    f-H 

CM^ 

CNl     ,-t 

CM 

m^ 

-^ 

^ 

cMcn 

^ 

en 

in 

en 

kO  w 

r> 

.-1   tn 

tn 

en  <r 

in 

■a|in 

o 

r^  00 

eTN 

rM 

00  -Ol 

o 

<f  <r 

--I    NO 

cn  r^ 

^ 

<f  rt 

00 

i^ 

r^ 

CM  eg 

^ 

CM^ 

^^ 

CM 

in  CM 

'-' 

CM 

o 

CM    CM 

en 

en 

in 

<f 

m  en 

m 

NO  O- 

NO  CM 

ON 

en  00 

ON 

-01  NO 

00 

00  m 

^ 

en 

ON   TJI 

<f 

.-(  .-1 

t'l 

O   r-- 

<r 

O  00 

NO 

<J- 

CO 

CM 

CM  n 

^  - 

^  ^ 

-^ 

r^    r-t 

^ 

'-' 

en 

1-4  CM 

CM 

en 

-4- 

en 

C3>    r-l 

vO 

m  CO 

vl- 

<t  t-k 

lO 

<r  CM 

r-H    NO 

•a-  -J- 

"' 

<f  m 

"' 

-" 

c, 

<T  in 

^ 

<r  in 

,H    ON 

NO 

O  r- 

-t 

NO    ,-1 

rN.  ON 

on 

ON    NO 

en 

in 

<f    ^ 

CO  m 

r^  00 

in 

<r  r^ 

<r 

NO  r^ 

vl- 

in 

unON 

00 

<f   CM 

CM 

^  in 

^  ^ 

^ 

CM  r^ 

CM 

•Ol-H 

r~- 

en  in 

ON 

o 

<t    00 

CT 

<f  <f 

O  <f 

CO 

N.t 

CM  <r 

vt 

00 

■J-   c-1 

in  en 

'■' 

r^  en 

NO 

en 

NO 

ON    - 

on 

lO  r~ 

in 

•OICM 

in 

in 

in 

<t  <t 

00  o 

-3^ 

r-l 

00 

NO   o 

o 

r^ 

<t  CM 

'^ 

^  o 

-cr  <»■ 

'"' 

en 

NO 

Vf     NO 

CNl 

-o 

M3 

<r  C3N 

<r 

00  <f 

00  n 

m 

<f    ON 

ON 

•olON 

en 

CM  en 

in 

^ 

00   -Ol 

NO 

on 

r-l 

^ 

<r  en 

'"' 

en  CM 

CM  in 

I'l 

CM  en 

en 

in 

en 

-J-  in 

-J 

NO 

^ 

r^ 

00   vO 

o 

CM   CM 

ON  tn 

in 

00  r^ 

^ 

•OlON 

^ 

00 

-t 

eg  -Ol 

in 

<f 

00  en 

ON 

tn  <f 

in  CM 

""' 

CM 

r^ 

tn  ^ 

in 

in 

"^ 

o  ty. 

„ 

ONOO 

in  o 

<t 

■*  o 

m 

ON 

r^  r^ 

<t 

r~  <f 

U-l     NO 

in  <r 

o 

n  vo 

o 

00    00 

NO    00 

r^ 

r-l    00 

en 

-3-  CM 

en 

NO  en 

^ 

eN| 

"" 

00  <r 

NO     NO 

'■' 

en  CM 

in 

NO    ON 

2 

r^  CO 

NO 

ND 

a> 

^  ^ 

00 

r^  CM 

CO  NO 

o 

00  in 

lO 

•OICM 

(^1 

^ 

en 

vX3  r^ 

r^  in 

r^  NO 

in 

i-H 

en  ON 

" 

ON 

-T 

o 

<f  ^ 

n 

in  en 

in  CO 

en 

NO  r^ 

in 

■o|oo 

^ 

iTi 

CM 

r^  in 

in 

m 

r~ 

- 

-*  in 

in 

vO   CJN 

[N-    ■* 

CJN 

in  CM 

in 

■OlCTN 

^ 

ON  in 

en 

NO 

-H  -Ol 

vD 

r^  r^ 

m 

r^  NO 

in 

r^ 

en 

NO   CTN 

<JN 

f-l 

2 

<t  i^ 

o 

ON  r^ 

ON  CM 

^ 

NO  in 

^ 

CM 

o  o 

m 

^ 

S^"=" 

^ 

CJ 

e-5 

IM 

" 

01 

e» 

c 

e 

l-I 

o 

.y 

n| 

s> 

•H 

O     0) 

cu 

o  u 

n3 

X  w 

C 

3 

u 

ra 

Q 

CJ) 

n 

3  T3 

H 

pi. 

0) 

fH 

^J 

(  ) 

() 

OJ 

B  <: 

-     a 

<u 

t) 

(J 

■p: 

•V  <-t 

« 

0)       >N 

H 

'>\ 

u  u 

HI 

3  -O 

fr,  <2 

M 

S 

O 

Ji     0) 

^    C 

c  c 

T. 

1  XI 

Of. 

e  <u 

o 

u 

C    u 

■H 

c:  u 

H 

OJ     C 

c  u 

ffl 

fc; 

X  S 

i; 

fc    PL, 

Cm 

oi  3 

o 

<  o 

fe 

O    M 

•J 

m 

M  3 

20  Bulletin  654 — American  Railway  Engineering  Association 


Ui     OC 

o,  in  O  vo  o 

en  <f  OS  lO  00 

00  00  OS  in  o 

r^  r^ 

CM    O  00 

CM  r^ 

^  en  OS 

m  so  en 

■a- 

w 

a   u 

n  in  oi  in  o 

CM   CM   en  so  00 

•a  CM  CM  o  S 

tN  r^ 

■a  -a  csj 

en  o 

m  -a  r- 

oo 

CSI  <7i  tn 

"io 

> 

cs  r-i     '  w  cm' 

^    rH    .-I    <!■    rH 

■^           r-l   CM 

en  r^' 

csi  <f 

r-4    cm" 

00  cm"  en 

esj    r-4    rJ 

r-l 

cm" 

rH   r-4'  rH 

3 

C   M 

in    (TJ 

'-' 

-^ 

^  v^  in  r^  o 

SO    O    in   C7S   in 

SO  r^  -^  in  o 

OS  r^ 

m  cn  o 

00  o 

<r  o  o 

OS  00  o 

o 

en 

r-  to  •«■ 

u   n 
u 

r^ 

o  o  r^  <r  oo 

OS  OS  <f  <f  in 

en  00  OS  o  in 

00  o 

CM    lO    CO 

CO  r-  r- 

o 

rH 

0    rl   0 

cnJ  csj  ^  ^  ^ 

-1    -1   O    CM 

*    ITS        "    rJ    r-4 

c-4  en 

r-l  <r 

rJ    rH 

CO  -4  en 

'  f-^  ^ 

esj 

CS4 

r-4    rj   rH 

4J      C 

n 

ic  in  so  OS  OS 

in  -H  c^  o  vo 

c^  <f  -D  xilcjs 

lO  CM 

in  en  00 

r^     P^ 

tjIcsj  00 



en  cTi  -^ 

^ 

Csi 

00  r^  CJS 

O     4) 

1-.     -rJ 

r- 

CM  so  <r  -cr  -J 

f-i  CM  t>^  OS  en 

"1  ~*.  ^.      ~^. 

in  CM 

CM  so  so 

f~t     vO 

r-  o  m 

1^ 

r-l 

o 

Z'^Z 

^*'^"    '-^-^ 

CM*   ^  ^  cA  cm" 

<f                 CM 

fH  en 

ts^r^'rn" 

CM 

CJs    _l    <f    -4    1^ 

o  en  o  <f  o 

rf  i^  in  T3|^ 

CM  in 

in  r-  -1 

-a  o 

TJl-^   -Ol 

in  in  in 

<f 

_4 

.-H    U^    (-.J 

3  ^ 

r^ 

in  in  <f  00   c-1 

OS  en  o         in 

OS    r-l 

rsi  o  r~ 

O-  r~  in 

OS 

CM 

0  Ol  O^ 

c  n 

4-1     o 

S 

cj  ^'     '  w  cn" 

"  ^'  rn"  1/^  ^" 

'^     '        -^ 

'^  e^ 

en  <f 

r^CM* 

C^ 

"  '-**-^' 

'^ 

cm' 

^r^,-; 

CTs   ^   v£>  O   CM 

^  sf   OS  O  OS 

r^  in  in  T3|en 

en  o 

O  o  c^ 

r~.  -a 

•Olos  -Ol 

CO   so  CM 

o 

r- 

TT  Ol 

a. 

r^ 

so  en  OS  lO  <f 

en  o  OS  00  in 

t~.  r^  O         en 

00   Csl 

lO  ^  o 

in  CM 

en 

en  so  <js 

n 

2 

rv)  a>  rH 

cm"  ^'     ■  w*  cm" 

^"  ^"     ■    "  ^" 

'  cA     '        cm" 

en"  en" 

CM  -a- 

r-l"    e^ 

o 

O   O   O   in   CM 

en  ^  ,-1  CO  o 

00  CO  so  -oi  in 

in  en 

r-  o  -a 

OS    CI 

•al<f  -o\ 

O-    <f   CM 

CM 

OS 

^  CNJ 

r^ 

<)■    CM    CTi   <f   CM 

O  r^  <f  i^  en 

r-l    CM 

CM  in 

OS 

IN  o  en 

- 

T-I 

U->  CT.   Q 
^  r^  r^ 

cJ^"  "^'c; 

Ji  "^"cm"-: 

"cm"     ■        cm" 

en  CM     '  CM  <r 

J    rJ 

j: 

V^     00 

c^  en  00  r^  CM 

en  -a-  o  en  oo 

so  o  -a-  1^  so 

r^  CM 

so    r-l    00 

-a  r~ 

in  o  OS 

so  -a  r- 

vj- 

00 

^^  °s 

0)     Vi 

CM    OS  -1   OO  CM 

c^  op  o  00  oo 

00  -*  r^  m  so 

r-  00  r^ 

rH     OS 

-a  ^  o 

Ol   00    LTl 

n 

>.  0) 

-d-  CM  CM  CM  cn 

M  S  en  OS  en 

ejs       rH  -a 

m  -a 

tn  <7s 

r-l    <f    r-l 

en  est  -a 

■a 

r-(    to    f-J 

4)    4J 

> 

so            r-l 

in   rt 

.u  -0 
m  c 

-^ 

OS  OS  r^  m  r^ 

m  CM  r-  CM  in 

CM  cjs  so  r^  en 

CM  r>. 

OS  in  r~ 

SO  so 

in  r-l  r- 

<f  en  00 

o 

f— 

r-l  0  1^ 

U    'H 

m  -a-  CO  -<  CM 

CO  in  o  C7S  n-i 

CM  so  00  in  .-< 

o  in 

<r  OS  in 

CM  ~a 

<r  in  OS 

r-l    OS    o 

00 

u->  a>  r- 

o   nJ 

CT^ 

in  o-  in  en  o- 

.-H  m  -a  in  so 

r-l  so  CM  .-1  m 

r^  r^ 

en  so 

en  in 

Csl  <}■  so 

u   c 
3    ™ 

<n- 

CM 

'"' 

^ 

so            rJ 

m 

O   t3s  c^   00  ^ 

OS   r^  CM  .-4  so 

en  00  -a-  -also 

<f  1^ 

CTs  r^  in 

O   OS 

■ol^  o 

so   OS   OS 

en 

o 

0^  -<3-  -^ 

S    g 

(Js  O   CTs   r^  OS 

lO  r^  00  -J-  ^ 

en  en  en       00 

O  c^ 

<f     rJ    CM 

<r  OS  <f 

c 

>w   o 
o 

0) 

OS 

en  CM  en  r^  in 

-a  CM 

-a  CO 

r-l  en 

CM   OS 

r-l     r-l     <J- 

en 

en 

rsi  to  ro 

CM 

>^  in  <n  >J  o 

CO  o  .-1  00  r^ 

rH  in  r^  T3|io 

O  r~ 

in  -a  en 

O   00 

-Ol  en  131 

en  en  r- 

so 

OS 

^  to  00 

r^ 

en   00   00   CN    <f 

,-1  r^  so  ^  CM 

<f  o          '-a- 

00  lO 

<r  m  r-l 

CO  in 

r-    OS    r-l 

-^  ro  00 

^  CM       en  en 

-4  CM  CM  13  en 

i-H  o            -a- 

m  -a 

-a  cjs 

so  IM  < 

en 

en 

I— ^  ro  cj 

o   6 
u 

V    01 

'^ 

^ 

OS    r^    rH    -^    W 

in  in  so  en  tn 

OS  en  r~  -ol-a- 

r-l    CM 

m  r-l  tn 

o  en 

■air-  -Ol 

tn  m  CM 

OS 

in 

.-(  r^  rsi 

4J  a 

.-<  CM  r^  r^  -J 

CO  00  00  en  so 

O    00                 'r-l 

in  OS 

o  in  r~ 

-a 

o 

\o  t-D  en 

ID 

ON 

•<f  CM  .-H  CM   en 

-4    .-1    W    rH    CM 

rH  m           -a- 

rj  en  r^ 

-a 

^  CM  -a 

<r 

.-1  to  »-( 

00  » 

01    ,-1 

fe'3 

o 

<!■  m  c^  in  00 

r^  00  in  en  r^ 

-a  so  r^  -alcTs 

so  OS 

<r  00  in 

<r  r- 

■oi<f  -ol 

m  en  o 

St 

o 

^D  0  00 

DO  a) 

r- 

<f  OS  in  ^  o 

en  en  so  en  n-l 

CM  o  tn     'so 

■a-  ^ 

en    00    r-l 

sO  CM 

r-      ' 

CJS  00   p~ 

so 

<:  c 

en  iH  f-4  CM  en 

W  .-4  CM  <r  CM 

in            en 

Mf  tn 

r-l  CM  r- 

^CM 

m 

en  r-l  -a- 

CM 

en 

rH   to   i-H 

U     60 
CO    CO 

^£)  r^  r^  r>-  o 

00  00  w  in  so 

-a  r^  en  in  o 

r-l  o 

en  in  r-l 

O     r-l 

en  o  r- 

CM^^ 

00 

^ 

Ln  0  CTt 

r-4 

(U     U 

1^  <f  CM  <f  ic 

en  en  <r  en  in 

r-l  en       CM  r^ 

O  00 

rH  r^  en 

<f  so 

en  00  rJ 

so  -a-  in 

to  u^  ro 

to  J,! 

>^  1) 

r-l 

in          r-l 

3    O 

> 

OJ    in 

in   CO 

c  u 

-d- 

-^  en  CM  in  ^ 

tjs  OS  en  en  so 

o  CO  CO  in  00 

OS  00 

00  en  r-. 

CM   O 

en  so  00 

»   O    r-l 

^ 

in 

ri  to  rH 

•o 

r^ 

ic  lO  in  <r  in 

CM  in  -J-  o  r~ 

rH  CO  CM  CM  'a' 

00  00 

in  -a 

<!■  m 

en  -a-  o 

c-1  in  in 

so 

so 

to  *o  to 

0)     (U 

■H     C 

CO 

CM  o  <f  in  in 

lO  1^  tn  tn  ^ 

in  CM  in  T)|o 

cjs  Na 

CO  en  en 

-a  OS 

•o|in  so 

in   r^    lO 

CM 

^ 

00  r--  LO 

u   C 

r^  in  .-<  <f  en 

lO  en  in  .-1  r~. 

-a            00 

r^  so 

00    r^ 

en  <r 

CM  en  <r 

to  'd"   ^3- 

O    -H 

tl     CO 

o   E 

3   >M 

-• 

CM 

en  so  en  o  i-i 

rH    ^    OS    in   00 

lO    Csl    r-l    TllO 

r^    r-4 

r^  so  -a 

r^  in 

•0|CM  -Ol 

OS  OS  so 

OS 

r^ 

Ol  00  to 

S     0 

r^ 

00  -a-  rH  m  r~ 

CM  -a-  en  m  <f 

csi  r-            00 

r-4  OS 

<js  o- 

o  -a  <f 

c 

o> 

t-i 

o 

1-4 

1 

°9 

^ 

ID  O  OS  00  CM 

o  cs4  OS  en  oo 

CM    rH    ,-4    -Ol  in 

CO  Csl 

OS  in  in 

r^  so 

131  r-  -cJl 

in  r-  r- 

^ 

CM 

m  r~-  to 
to  u^  to 

r^ 

00  <f  CM  <f  r~ 

-*  en  CM  CM  -a 

csi  o              r-~ 

-a  c^ 

OS 

r~.  vj  in 

r— 

(U    V4 

.G     <U 

1  ^ 

s 

o 

r^  r^  r^  ^  so 

CM  CM  CM  o  en 

in  CM   CO   T3|OS 

r^  -a 

<r  OS  i-~ 

OS  in 

•OIO   -Ol 

rH    OS     r^ 

CM 

o 

^  LO  to 

r^  en  CM  ^  lO 

en  CM  <f  CO  en 

00                 so 

c^  vo 

tn  <f 

t--  CM  Ln 

so 

a\ 

T~t 

c 

Pm 

J= 

^   o 

3 

en 

o 

0)             a  -H 

C     60 

w 

pi4                   10     CJ 

Ph    CO 

11)     to    -H 

00  i3 

CO                       Ph 

4J    «    14-1 

c 

c 

o 

u        c     • 

•H   -O 

0 

u 

*H 

C         ,  H     4J    i« 

01     C     O 

E  M 

u  c 

01 

I-I 

CO    o   «;  w 

3   o   CO 

4)     4)     M 

•o 

m        jj        -a 

1-1      P4 

C     0.-H     CO 

o 

CO 

CO 

c   CO     -  c: 

C     0)    H            U 

c  V4  x;  u-i  X 

U     4J 

C 

•r4 

CO 

o 

1^    M    O    Q)    to 

H   13           li!    41 

t,     4)     CO   X     4) 

C    to 

o 

3 

Q 

PS 

Q>    S     tU   1-4 

4)   c:  la        > 

4)   J=    M    4-1    H 

CO     Hi 

•H     4,1 

W           T) 

10   £          J<!     CO 

J=     CO            60   C 

u    3 

o 

•JS 

c 

nJ    u   c 

■o 

H 

^    4J  j:    3   (H 

4J     ^     Oi     41     4J 

m     3   vfl     O     01 

•H      10 

o  pi4  j: 

CO     U 

u 

t3 

d  -H   nJ 

c 

<j 

m   ^1  u   CO 

3    U   ^     &  Q 

4)     O          Z     CO 

14-1    Ph 

C    -H 

to            -H 

0) 

..      0    M-l    i-H 

CO 

M 

O.  0    f    3  -^ 

O            CO    -rt 

3  tn   M        to 

'n   C    3 

n  >"  c 

4J 

o: 

o  z  o  .3   o 

to    o    tn    E  I* 

0     -  c 

o  c 

4J    to    o 

41    -H     CO 

9 

4J 

H 

H           Z    'H     o 

•r4      to      C 

•a    >,  -rt    w    CO 

CO  ^4 

O  («  w 

CO 

U     O     O 

0) 

C 

to     (fl     t-t 

en 

C         S  OS 

1^!    OiS    vH    ■'^   -C 

U     t4    -H    tui 

P4      4) 

01     1 

P4 

C     CO   -rl 

4)    -H     to 

3 

u 

0 

2:  c^  0 

M 

-   0   i« 

s  rs  4J 

>^  -H      4J    rH       1 

4J 

H   P4     X 

P4     U   Ph 

nS 

2 

K 

n 

C   *J           -     - 

O   i«                 u 

CO   O     O.   O    -H 

M    .H    -H 

4)     C 

Si 

to 

c  c 

O     60   O     O     O 

-o           -    -  0 

ca       3  o.  i-i 

U     01 

3    3 

C      14 

a  'Ji  X 

-P4     C 

CO 

to 

5 

cU    fO    0 

§ 

to   c::   60  60  60 

!0   1-.  j:  j:  3 

w  m   CO   3 

3    3 

coo 

c 

O            U 

4J 

■H    -H    -H 

•--1    .H     CO     CO     10 

C     CO            01     O 

O  X 

O   rJ   rJ 

Ij  X 

CO    M    en 

■a   c  oj 

o 

0 

M 

TJ    -O     H 

n 

M 

x:  .-1   CI   o   o 

(D    >    3    3    4J 

4>    en    4)    C    M 

60 

J!     to     to 

4)     O    4J 

H 

,H 

9 

«    nJ    nj 

H 

^     C    rH   ^     k4 

41    B  .^    C    <o 

4)      .      . 

0    3 

0    X    X 

ecu 

4-1   3  X  X  j= 

O     0)     3     3     O 

V4      CO      to     -H     'rt 

ii 

U    U    U 

O     O 

0.  4)     01 

o  a  £) 

U 

n)    C13    d 
u  u  0 

i 

<  (0  o  u  o 

U  Q  Q  Q  fe 

O  jKi  ►J   S  S 

O  tn  to 

CO  w 

tn  i^  H 

H  p  3 

Tie  Renewals  and  Costs 


21 


p^   u  w   ot 


u         n  u 


.H       g:   3   c   c 


m 

<1) 

3 

•H 

K 

Ctl 

3 

p: 

< 

xj 

•n 

r^ 

O 

a 

t) 

o 

60  Ov 

•H 

f 

a 

01 

c 

■U 

tin 

n 

c 

o 

u 

£ 

•^ 

>, 

Id 

>^ 

B 

0 

o. 

^ 

|^ 

c 

fl 

o 

Ml 

3 

rr 

U 

Bfl 

.a 

i4!  o 

n 

t: 

Tl 

<D 

o 

3 

a 

c 

ij 

o 

pji 

r. 

c 

m 

C 

o 

ri 

o 

Z 

■^^ 

J= 

^ 

CD 

t^ 

3 

O 

0 

o 

S 

c 

^ 

u 

n 

- 

•o 

J3 

C     C     O     (U    -H 
O     O     OO    >   -O    -H 


u   u  jz  a 

J,  a)  o  ■" 

a  a.  "^^ 

o   o  "^^  OJ 
o 


_    (Tj   at   RJ 

R]      (TI      ^*      tJ 


at   (3 
CL  a 

OJ    u    E 
«   «         to 

n   IS  zi 
at   0) 
■o  -a 

3     3     0)    u 

u  o  C  tg 
B  C  O  u 
M  M  («.  to 

I      I      I 


^t 


on  e 

o  o 
E    3 


tj  "O  13   ^  ^  ^^  iJ 


u     CI 

o 


22  Bulletin  654 — American  Railway  Engineering  Association 


Table  C 


OTHER  THAN  WOODEN  CROSS  TIES  LAID  IN  1974  AND  NUMBER  OF  OTHER  THAN  WOODEN 
CROSS  TIES  IN  MAINTAINED  TRACK  OCCUPIED  BY  CROSS  TIES  AS  OF  DECEMBER  31,  1974 


District  and  Road 

- 

Other  than 
wooden  cross 
ties  laid  in 
replacement 

Other  than 
wooden  cross 
ties  laid  in 

additional 
tracks ,  new 
lines  and  ex- 
tensions 

Number  of 
other  than 
wooden  cross 
ties  in  main- 
tained track 
occupied  by 
cross  ties 
(12/31/74) 

Number 

Average 
Cost 

Number 

Average 
Cost 

EASTERN  DISTRICT: 

Central  R.  R.  of  N.  J. 
Delaware  &  Hudson 
Norfolk  &  Western 

800 

$36.25 

- 

- 

840 

57  809 

800 

Total  Eastern  District 

800 

36.25 

- 

- 

59  449 

SOUTHERN  DISTRICT: 
Florida  East  Coast 
Louisville  &  Nashville 
Seaboard  Coast  Line 
Southern  System 

15  117 
205 

25.47 
14.63 

24  365 
26  095 

16.96 
25.01 

353  232 

808 

292  136 

68  579 

Total  Southern  District 

15  322 

25.32 

•50  460 

17.08 

714  755 

WESTERN  DISTRICT: 

Atchison,  Topeka  &  Santa  Fe 
Burlington  Northern 
Duluth,  Missabe  &  Iron  Range 
Kansas  City  Southern  (I  ncl .  L&A) 
St.  Louis-San  Francisco 
Western  Pacific 

400 
12  168 

27.50 

14.71 

5  254 

12.46 

6  000 

303 

530 

191  379 

74  480 

735 

Total  Western  District 

12  568 

15.12 

5  254 

12.46 

273  427 

Total  United  States 

28  690 

21.16 

•55  714 

16.64 

1  047  631 

Association  of  American  Railroads 
Economics  and  Finance  Department 
Washington,  D.  C.  20036 


July  7,  1975 


Tie  Renewals  and  Costs 


23 


TYPICAL  CROSS  TIE  PRICES 
As  of  January  1 


10  Selected  Class  I  Railroads 


District /description 
of  cross  tie 

1959 

1970 

1971 

1972 

1973 

1974 

1975 

EAST: 

7'x9"it8'6"  oak  treated 

$5.33 

$5.83 

$5.83 

$6.41 

$6.67 

$9.02 

$12.94 

Grades  («.5  Latest  A.R.E.A. 
Spec.)  60/40  Cr/Coal 

6.50 

6.90 

7.45 

7.45 

7.68 

8.23 

10.72 

Grades  4&5  treated 

(latest  A.R.E.A.  spec. 

60/40  Creosoted 

6.35 

6.90 

7.45 

7.45 

7.68 

8.23 

10.72 

SCUlll: 

6"x7',  7"x8"  and  T'k9"   by 
8"6"  treated  oak  &  mixed 
hardwood 

3.62 

4.63 

5.22 

5.09 

5.67 

6.08 

9.09 

7"x9"x8'6  treated 
7"x9"x8'5  oak,  creosoted 

5.09 
5.60 

5.13 

6.50 

5.29 

6.00 

5.64 
6.71 

5.71 
6.89 

6.48 
8.63 

10.77 
11.20 

WEST: 

7"9"x8'6"  red  oak,  Gr.  5 

4.77 

5.07 

5.24 

5.24 

5.59 

6.53 

8.95 

7"x9"x9' 

5.0  J 

5.63 

5.63 

5.63 

6.40 

8.95 

13.55 

7"9"x8'  Doug,  fir  rough  - 
No.  1  &  better 

5.00 

6.01 

6.99 

5.77 

6.06 

7,50 

10.90 

7"x8"x9'  Hardwood  treated 

4.57 



5.09 

5.12 

5.33 

5.05 

8.10 

10.37 

Association  of  American  Railroads 
Economics  and  Finance  OepartmenC 
Washington,  D,  C.  20030 


February  20,  1975 


Advance  Report  of  the  Special   Committee  on  Scales 
Report  on  Assignment  3 

Statistical  Data  for  Coupled-in-Motion 
Weighing  and  Testing 

N.  A.  Wilson  (chairman,  subcommittee),  O.  T.  Almarode,  B.  F.  Banks,  R.  O. 
Bradley,  Robert  Brumbaugh,  E.  W.  Buckles,  J.  L.  Dahlrot,  R.  H.  Damon, 
Jr.,  T.  a.  DeAlba,  O.  C.  Denz,  G.  F.  Graham,  I.  M.  Hawver,  S.  Levinson, 
L.  L.  Lowery,  B.  H.  Price,  Jr.,  W.  H.  Rankin,  S.  H.  Raskins,  R.  D.  Roberts, 
A.  E.  Robinson,  K.  D.  Tidwell,  J.  L.  Finnell. 

Your  committee  submits  as  information  the  following  interim  report  on  the  per- 
formance of  track  scales  designed  for  coupled-in-motion  weighing  of  freight  cars.  The 
committee  reviewed  tests  for  tolerance  on  18  scales  and  27  modes  over  the  scales, 
utiUzing  2707  weights.  Many  railroads  participated  in  the  testing  program,  along 
with  representatives  of  tlie  AREA,  weighing  bureaus,  cities,  states  and  the  National 
Bureau  of  Standards. 

Test  equipment  has  now  been  assembled  at  Martinsburg,  West  Virginia,  to  be 
calibrated  by  the  National  Bureau  of  Standards  to  gather  further  information  for 
the  study  of  weighing  over  coupled-in-motion  track  scales. 

There  are  presented  below  and  on  the  next  page  summaries  of  the  test  results, 
followed  by  tlie  complete   computer  printout  for  each  weight. 

Summary  of  Coupled-in-Motion  Track  Scale  Tests 

Number  of  tests   18  Scales  ( 27  Modes ) 

Number  of  cars  weighed   2,707 

Average  Percent  Deviation  of  Individual  Cars 

0.00%  to  0.20%  0.21%  to  0.50%  0.51%  to  1.00% 

81.42  17.58  1.00 

Total   weight   test    trains    .^^.*^!;^"':^. 416,770,950  lb 

r^      1        ■  ^       7     .    .                         Trains   (Gross)  i.ttooc  n 

Total   weight  deviation    iz/,oJo  lb 

Weight  deviation  per  car    8  lb 

Cars   (Gross)  _„  .  _  ._  ,, 

Total   weight  deviation 504,745  lb 

Weight  deviation  per  car 186  lb 


25 


26 


Bulletin  654  —  American  Railway  Engineering  Association 


COUPLED-IN-MOTION  TRACK  SCALE  TEST  RESULTS 

Percent  Deviation 
Inrtividc.Tl  Csrn 

UNIT  TRAIN  DATA 

0.007. 

To 
0.207, 

0.217. 

To 
0.507. 

0.517. 

To 
1 .  007. 

TEST  # 

MODE  II 

CASS 

Test  Train 

V.'ciiht 

Test  Train  Weight 
Devi-ition 

Percent  Deviation 
Test  Train 

1 

1 

100 

84 

11 

5 

13,703,000 

-4,300 

.031 

2 

100 

80 

15 

5 

13,703,000 

+7,600 

.055 

2 

100     88 

12 

15,445,400 

-  1,360 

.003 

3 

100 

76 

24  1 

10,952,800 

-5,590 

.051 

100 

71 

29 

10,952,000 

-6,000 

.054 

4 

100 

92 

8 

19,617.000 

+13,200 

.067 

5 

100 

94 

6 

19.511,800 

+1,110 

.005 

6 

100 

77 

20 

3 

11,797,400 

-1,260 

.010 

7 

100 

90 

10 

20.252.000 

-5,200 

.025 

8 

100     81 

18 

1 

12,785,800 

+  3.190 

.024 

100     73 

24 

3 

12,735.800 

+3,590 

.028 

100 

82 

18 

12,710,900 

+3,050 

.023 

9 

100 

79 

21 

18,944,100 

+  580 

.003 

10* 

99 

80    IS 

4 

12.852,000 

+  1,800 

-014 

*rii 
11 

ssed  1 

:ar 

100 

77 

22 

1 

12,923.000 

-1.100 

.008 

100 

71 

28 

1 

12, 923, SCO 

+400 

.003 

100 

65 

35 

12,923,300 

+  20,900 

.161 

100 

82 

18 

12, 923, £00 

+1,200 

.009 

12 

100 

85 

15 

15,084,400 

+2,030 

.013 

100 

83 

15 

2 

15,034,400 

-1,095 

.007 

13 

100 

80 

20 

13,557,300 

-11.130 

.  059 

14 

100 

95 

5 

15,172,400 

+4,020 

.026 

100 

86 

14 

15,172,400 

-190 

.001 

15 

100 

80 

19 

1 

20.645.520 

-9,700 

.  046 

16 

108 

75 

24 

1 

22,209.750 

-W,150 

.  018 

17 

100 

80 

20 

18.557,300 

-5.760 

.  032 

18 

100 

93 

7 

1 

1   13,557,800 

+8,130 

.  043 

Test  *1 

'618  ue 

:e  IT 

ade  on  s 

cales  a 

:  differs 

:it  locations. 

i 

1  GROSS  TOTAL 

127,835 

1 1 

Tests  of  Coupled-in-Motion  Weighing 27 


I  oorvj     oocr     oor-     ocao     ooo     ooin     oo-j-     ooo     ooo     oo^ 
loo'*^    oo-r     oo-"*    ooo    o     o    oo>r     ooo     ooo     o     o    oo^o 


.  M  ^O*— '      'niAU^      — <— 'O       o<-*o 

iicoio     foio     ^     O     r*-     O 
II  -^      1      o      I      */>  -< 


(\JCOO 

r^O-— 1 

-^a>o 

CO 

o 

i/\r-o 

O  1     • 

ror\j    . 

cr  1    • 

o 

• 

r-       • 

iiootTi  oo— '  iDC/c  ooco  ooiA  oo^  oor-  ooo  oo— '  ooo  oo-< 
2*1100^  OOCX5  o  O  OtxiO  Of^J•'^J  OOu^  0<3't  OOO  CfNJ^  OPsl^  oom 
3  II  o— 'O  u-.u-ir^  —I  o  o  I  o  r-(M— I  o— lO  r»i(Nj— ■  o-— i— <  r^  o  cc-h-<  ~or-o 
a:ticot»f*^l«»cD       -f^       •tr\i*sOl»vO       •oi*Ln       •oo       •cri« 

ii'-to.ooi/NO— <or^or--or-oa-or--ooo^o 

II  '-• 

II 

)i  oor-     oo--*     ooo     ooco     ooco     oom     oor-     ooo     c^G^     ooco     ootn 

;T  II  OOf^      ooco      O      O      OCOJD       OrsJ-O       oo— <      OO^      O       O      0<NJ— *      O.NJ—t      oo^ 

i:3ii>rr<i— *    inu^r-     — '     o     oio     co— lo     o^inj— •    ropg^    o     o    r^     o    r^     o     -t  (y^o 
a:iicoi.roi"*a3       •(—       •     u^  i    •     \r\  i    •     <i       -o       'in       -co       "O-i' 


II  -• 


—      I      -•      I 


II OO'^    ooin     coo     oor"     <Do\rf     oo-o    ooo     ooo    coo<     oom    oo-o    o— i 
:?  II  ooco    oopsj     o     o     ooo'r*     o^njini     oG^r^    o-oo     ooo    ocom     occr-     oo—t     < 
^iit^j-— I     ■c^'C     '-'     o     a-—'—'     i^fNj— ■     o— 'O     tM— lo     c— >— I     ^rsi— <     -o  I  o     r^o— ' 
cr'iicoi"     roi«fl-aj       •     >oi«     mi*     oi»     ^       •     oi«     int*     co       •     co— <• 
ii'JO-ccvno— ict^o^-or^oa-or^ooo~oio:i 
iitNji  I  ^,^1^1^  l_^i_-,l^i      ooirvuj 

II  ^  -1"^     ■z 

II  _i         O 

r-  I <         Z 

iicof"-     ooco     ooo     com     OOO)     oom     oor-     ooo     ooirv    ooco    ooir> 
^  II  oom    oo^o    o    o    ocoiTv    o.-vj-c    oo^    c-o^    o    o    cco-1-    o'v—'    oo-o       coo 
3  II  >j-mr-i     r^m^     — «     o     cr--<— *     co—^o     0*^%!— <     mpsi— *     o     o     -OIO     r-     O     ^[>o         QOt^ 
:it:iicoi«mi.»cc       •a3i«i-i|"tni'>0       "O       "in       -co       "a-l'         f\jir\o 


I  -c     o 


•Oil"'           ••           ••  ••  ••  ••  ••           ••  ••  ••           •• 

Moo-l-    ooco    ooo  ooi^  ootM  oo-o  oo-j-     ooo  ooirv  ooo  oo>o 

ziioof^    oo-o     o     o  ot\j— I  ocoo  oom  o-oo     ooo  ox>r  o-'M-"  oom 

3  11— t-ocNj     r-m>T     —4     o  — *     o  — ^— t— *  o— *o  stmtNj     cr— <— <  voio  co^^^  oomo 

aiicoi«»mi«-»-oo       •  r-       •  •o       •  -oi«  -o       •■a-cri*  m       •  as       •  ct>i« 


a-     o     "- 


II  (NJ        I  I 


m  11    •  •          .  •         •  • 

II  ooco     ooin    ooo 

oor~ 

ooin 

coo 

oor-- 

ooo 

OO-i 

coo 

oom 

2IIOO(M      OOtM      C      O 

Of\J-i 

oco^r 

o     o 

o-o^i- 

ooo 

CtM-" 

OtNJ— 1 

oo-r 

3ll(MiniNJ       -O^-O       -"       o 

-1      o 

o     o 

-1     o 

m(Nj-i 

X>C\1(\J 

r^     o 

CO— 1— ' 

r--oo 

^iioDi    .«-mi    •*co      • 

f*-      • 

■o      • 

-o 

o 

O-  1     • 

IX\          ' 

CO          • 

a-  1    . 

<r 

II  oci~- 

OOQD 

00(VJ 

ooc- 

OOin 

OO-O 

ooo- 

ooo 

oom 

com 

OOO 

1 

^ 

II  oom 

CO-C 

oor- 

org-i 

ocoo 

oom 

o-oo 

ooo 

ocoo- 

CINJ 

—4 

oom 

z 

3  II  J-ro-. 

r^m^ 

o- 

-•— 1 

—4 

o 

o 

o 

o— 4 

o 

O-mcNj 

a-. 

-4—4 

~o  1  o 

'-^ 

c 

OTif 

^0 

.-4 

lY 

II  CX)    1      • 

m  1     •■«• 

-i: 

1    • 

l^ 

-n 

• 

O   1 

• 

~o       ••; 

t    T- 

1         • 

m       • 

CO 

• 

a-  1 

• 

11-1      o 

o    c 

m 

o 

>~t 

n 

r^ 

o 

r^ 

o 

r~-     o 

0- 

o 

1^      o 

o 

o 

-o 

o 

."^ 

QJ 

II  (N         1 
II 

1 

1 

1 

1 

-4         1 

- 

1 

o 

1- 
< 

UJ 
1/1 

II  OOI^ 

OOO 

OOINJ 

OOlNi 

oom 

OC 

o 

OO-i 

ooo 

oooo 

coco 

ooo 

>— • 

l/l 

7' 

II  oom 

oo-o 

oor- 

o< 

MO 

Ocoo- 

oom 

o-oo 

ooo 

OC\JO 

o.^ 

1—4 

o 

c 

> 

(_' 

> 

II  Nj-m^-H 

r-m^ 

INJ— 1 

.-NJ-i— 1 

o 

o 

O-i 

o 

mo(Ni 

COCMINJ 

cC-iO 

r- 

o 

m 

o 

UJ 

a 

rr 

11  oc  1     . 

m  1    •■» 

•CO 

• 

f^ 

• 

•D 

• 

•O  1 

• 

•c      •■sc 

1    • 

m      • 

CO 

• 

o 

c 

o 

II  -1     o 

.0     o 

m 

O 

r^ 

o 

t- 

o 

r* 

o 

1^      o 

CT- 

o 

I--      o 

o 

o 

r- 

o 

II  PsI        1 

1 

'^ 

'^ 

•^ 

1 

•^ 

1 

"^ 

^ 

m 

rv, 

II  OOf- 

-^^ 

ooo 

COIN; 

OOrvl 

OOO 

OOr~ 

ooo 

oo-a 

ooa 

oco 

y 

II  ocm 

OOfNJ 

o 

C3 

Ot\jO 

oooo 

n 

C3 

o-oo- 

ooo 

OiN-O 

CN 

1—4 

o 

C5 

-) 

11  -j-m-i 

oo-  JD 

,-1 

o 

tSJ-i-l 

^-< , 

—4—4 

^^ 

o 

m(Ni-4 

0-- 

-4—4 

0C-4O 

co- 

1—4 

m 

o 

ct 

II  00   1      . 

mi    •■«•  CO 

r- 

• 

■a 

• 

-o 

• 

-O 

a- 

1        • 

m       • 

co 

• 

o 

• 

II  -<     o 

~D       O 

in 

o 

— * 

o 

r~ 

o 

r^ 

o 

r-     c 

o~ 

c 

r-     o 

o 

o 

r- 

o 

II  (\j      1 

1 

^ 

'~* 

'^ 

'~* 

1 

^ 

'^ 

'^ 

ooo 

-40 

mo 

^M 

II    •   • 

•    • 

• 

• 

• 

• 

•  « 

*  • 

• 

• 

•  • 

•       4 

• 

• 

0000(M 

II  OO  — 

O-C-0 

C^i 

CJt\J 

oom 

oom 

coo 

oor^ 

ooo 

oom 

OC 

KM 

OC.-M 

or--m 

•  • 

^ 

II  oca- 

oom 

Ol 

OI^ 

oiNjr- 

ocoo- 

com 

o  oo- 

o 

o 

OrvJtNJ 

o^o 

ooo 

m,a)o-oo 

_) 

II  J'rsiO 

C  '~*^-< 

rvj. 

— t-^ 

srm,.Nj 

o 

o 

iSJ  — 

lO 

mCNJ— ^ 

c:> 

o 

C~<M-' 

cr."NiPsj 

r-o--4 

OCT    1 

1 

T 

II  cc        • 

ro   1      • 

<r. 

• 

r- 

.«•  .o 

• 

-n 

• 

-O          • 

o 

m       • 

CO 

•  ^  •-*- 

-4      ■ 

r-  o 

II  -•     o 

-0       O 

m 

o 

r-* 

o 

r- 

o 

r- 

o 

r-     o 

o 

o 

r-     o 

o 

O 

r-- 

o 

mm 

II  (\4 

1 

'^ 

'^ 

"" 

'^ 

^ 

^ 

'-' 

2 

-4-4 

^_ 

11    . 

, 

, 

. 

, 

, 

, 

^—  ^~- 

O 

II  o 

o 

C5 

o 

o 

c 

o 

o 

o 

o 

o 

OiSi 

.i 

II  o 

o 

O 

CO 

rsi 

o 

o- 

o 

XI 

CO 

o 

■crs 

£ 

II  f- 

o 

— * 

o 

'^ 

—4 

o 

C3 

-o 

-O 

m 

u 

u_ 

II  CO 

~r 

CO 

r- 

m 

-0 

-o 

O 

m 

CO 

o 

U-l-CC 

_J 

LU 

II  — * 

.o 

IT. 

—1 

r^ 

r- 

r~ 

o 

p— 

o 

r~- 

ujCof 

_J 

T 

II  -^J 

— ^ 

— ( 

^-t 

~-4 

^^ 

^^ 

—4 

m 

QC^-U 

< 

II         1— 

t— 

V— 

^— 

H- 

»— 

t— 

1- 

1- 

1— 

—4 

1- 

II         P" 

'Z 

;' 

7 

;^ 

7' 

Z 

7 

2Z 

^ 

l-K-f- 

ZX 

tj 

II  00       'JJ 

en     uj 

-O 

UJ 

cr 

UJ 

o 

LU 

m 

t~       UJ 

o; 

-C       UJ 

cr 

CCCO< 

y 

II  -lao 

~con_) 

J-QiO 

CO  cr:o 

^-1 

:ri.j 

onto 

-•QCO 

—41 

K-l   ) 

vcao 

r~-a:o 

K-l-l-Q.  J. 

11  ^o 

vf  o 

OO 

m 

c 

f<M 

n 

mc 

o-c 

a:Q 

o-o 

o-o 

c. 

II  -ctinr 

Oa  ix 

f'^ 

rt  ct 

tj 

ona 

o. 

ae 

ccio: 

OCCO^ 

^-i^ 

occc 

ocictr 

Ca:oi: 

i-oirt- 

II  m  cr"  .1^ 

•Oir  lU 

c; 

cr  UJ 

^^ 

ir  UJ 

-H 

'YUI 

— 4  0- 

■  U_' 

-4QruJ 

f^^ijj 

— -Ci  -u 

-4q:uj 

Ocr  z 

o 

II   O'JC 

m'ij,i 

w 

u.i:^ 

(„ 

■JJC- 

o 

J-O- 

LJU. 

.0. 

0..1.T. 

r- 

un 

O-jjS. 

OU- 

la 

3l 

uo 

28  Bulletin  654 — American  Railway  Engineering  Association 


tl    •  • 

t-  II  O  O  IN 

OO-i 

ooin 

oo-o 

oo-< 

oocr 

00<3 

OOCT- 

00(\J 

00-* 

O  II  OOOO 

oom 

oo~j- 

OO-" 

OOifl 

oom 

OOO- 

OOOO 

OOfM 

oo-o 

(SJINO 

oom 

i^o>^r 

mao 

r-t^o 

-Hr-o 

0><ro 

>J--tO 

ir\r-o 

II  oo-<    • 

o       • 

0><M    • 

\r\-t  • 

CO  1     • 

»-#      • 

Csif-t    • 

o      • 

•0  1     • 

r-      • 

II  CQ       O 

•J-     o 

1-  1  o 

r-    o 

in     o 

•o    o 

<o    o 

o    o 

m    o 

00     o 

>0 

ir>      1 

f-4 

r-      1 

r- 

r- 

o 

r«-     1 

o 

(/» 

M  <M 

^ 

i-^ 

1-4 

•-I 

c^ 

*-i 

•-I 

^ 

Oil 

,   , 

,  , 

,     , 

,  , 

,     , 

,  , 

,  , 

,  , 

,  , 

. 

. 

ooo 

oo-o 

oor- 

OOOO 

oo-o 

oo>l- 

ooo 

OO-I 

ooo 

oo«i 

Z  ItOO-T 

ooin 

00-- 

ooooo 

OINO 

oom 

OnOO 

o    o 

OOvJ-J 

Org-1 

OO^ 

►- 

:3  II  oo-<o 

r-lt-tt-4 

oof«>if< 

mcvj-J 

OOr^O 

(M.-<0 

-J-rOlN 

o    o 

r-     o 

oo-^^ 

cr-oo 

OOOO 

a:  n  00      • 

■*              • 

r»-  1    •»  r~      • 

U\  1      • 

•0        • 

•O        ••O         • 

vn      • 

00        • 

o 

• 

t-  •  •  • 

II  -^     o 

o    o 

m    o 

^    o 

f-     o 

r-    o 

r-     o 

o    o 

i>-    o 

O     O 

r- 

o 

oino 

II  INJ 

1 

,-i 

w~t 

rH 

•-« 

m 

U.(M 

II 
II 

0^  11     •    • 

.. 

.. 

.. 

^  ^ 

.. 

,     ^ 

^   ^ 

■^ 

^ 

o 

»- 

iioo— '    ooo    ciO't    ooi^    oo-^    ooo    oo>r    ooo    ooif>    ooo    OOIM 

ziioocr     o    o    oo-r    o.mi^    oin^    oor-    o-oo    o     o    ooo-r    ofM— 4    oof~ 

3iia"MO    o    o     c>(\jn>     -rroiN    c>  1  o    -i-fo-^    -j-cmnj    o    o    -c  \  o    oo-^i-i    moo 

Kiioo      '-r      •r-i««r-      •»ir\      '-o       "-o      •»o      •    ix^      too      .-4,^« 

ii-jo-ooiriOi-<or—    or-of»-ooot»-ooor^o 

II  (M  i-<  -^l-"  -•  •-'  ^1^  fn 


n 
00  II 


looin    00-0    oo-o    0000    oo-^    000    oo-i-    000    oo<nj    ooo    oo-*'  oiv 

ziioo-i'    ooiri    oo-<    ofMin    oinjco    o    o    o-om    000    0000    otvi-j    00^  < 
Z3iicor-to     ^-*^^     oomin     in-^-m     -om'-^     ^     o     ^-^     o     fMCMrg     ir>^«-t     a>^^     ir»fVO 
ex  II  CO      •>!■      •r-i'-M-r-      •»mi»o      '-o      'O      •if\i«oo      "O      • 
ii-^o-ooir\oi-'0(>-or^or^ooor-ooor—    03 

II  (vj  |r-"  ^i-i  ^  -J  ^1^  ,n  ooinuj 

II  -i  _iro     z 

f--l <  Z 

llOOm      CO-O      OOnJ-      00^      OO-^      00-0      000      000      00'J^      OOOO      0003 

ziioo-1'     ooio     oo-t     ofM-t     0'>)— •    ooin     o-oa>     000     ooo-r     o<n— <    ooin  000 

z}  II  CO— <o    -H.-H-4    o-osiro    -oif\-r    o-  I  o    <Nj— 40    (sj^o    ^-4'^    .010    r^    o    ^000  000 

<i  II 00       •     -r       •     1^1    •«r-       •«iA       '-o       '-o       "O       'i/v       "CO       .-H       •  o-jino 

ii^o-ooiTio-^or—of-or-ooor-ooor-o  ••• 

II  rg                                      |r-i             _,|^             ^             -J             ^(^             ro  00-^ 


-0  II    •  • 

II  OOlfl 

000 

OO-*- 

oo-J- 

OOCD 

oo-o 

OOtvJ 

000 

CO-i 

OOOO 

00.0 

Z  II  oo>i- 

0    0 

OO-t 

o<N-r 

OtM-0 

ooin 

O-J-IN 

000 

0.-NJ-< 

O.M-" 

oom 

3  II  00 -<o 

0    0 

O-OJf" 

-Oin-i- 

00 -<o 

r\j-io 

0  1  0 

^^— *^H 

r-    0 

(^     0 

coino 

-3-        • 

r-  1    •«i~- 

inn  1    • 

-0 

•0        • 

0      • 

in 

00      • 

II  -<    0 

-0      0 

in     0 

-.     0 

I--     0 

r^     0 

P-      0 

0     0 

r-    0 

0    0 

1^    0 

1 

,-1 

'-     1 

r~t 

-"       1 

#-i 

•-4 

r-t 

II 

^ 

in  II   •  • 

II  OO-i 

000 

oo-j- 

OOCD 

OO-i 

oo~o 

000 

000 

OO"-" 

000 

OOCD 

Z  11  OOO- 

0      0 

oo-r 

oogin 

o^--< 

00  LI 

0-0  a- 

0    0 

O.-M-* 

0<NJ'-l 

ooin 

0  II  O-tMO 

0      0 

a-<\Jro 

.n-i-m 

0^  1  0 

fM-40 

r-i-<o 

0    0 

r-     0 

CO -1-1 

-•CPO 

.t;  11 00      • 

-f 

1^  1    •■ 

!H-       •■ 

«•  in      • 

0 

•0 

0 

in      • 

CO          • 

— '      • 

►-a:  oca: 

ZUJUDUJ 

o>>> 
aooo 


-1-  II   •  • 

11  00— ' 

00-0 

00-t 

cc-t 

OOCD 

000 

000 

000 

oo-< 

com 

coin 

1 

Z  11  0  0  CT- 

ooin 

OOvJ 

OfM'-" 

O<NJ-0 

c     0 

0-0  CT- 

000 

OtM-" 

OCOI~- 

00-0 

Z 

:d  11  o-iM  0 

o-rsjrn 

COI^-O 

C0-"0 

-4         0 

(\J-iO 

^^.-4—1 

1^ 

0 

-0  1  0 

tMO-O 

•~« 

0£  II  00        • 

-r      • 

1^  1    '*  r~       •■M-in  1    • 

-0             • 

-0         • 

0             • 

in 

• 

CO        • 

t-4            • 

11  ^    0 

.0     0 

in     0 

^    0 

1^      0 

r--     0 

^-      0 

0         0 

f- 

0 

0     0 

^-         0 

z 

q: 

II  nj 

1 

,^ 

r^           1 

.-4 

t-4 

v^ 

-H 

^      1 

m 

c 

a. 

II 
II 

UJ 

h- 

ro  II    •    • 

,  , 

a  « 

,    , 

a     « 

»  « 

«      « 

•      • 

•      . 

•  • 

•      • 

<I 

i/i 

II  oor- 

000 

00-r 

000- 

OO-H 

oo-o 

000 

000 

ooin 

OOCO 

OOtM 

•— « 

I/O 

Z  11  Oarr\ 

0    0 

oo-i- 

O^MiM 

CtNJ'H 

oom 

0-0  cr 

000 

C33-r 

Or-jr^ 

oor- 

> 

0 

0  II  C  f^  ^ 

0    0 

(MNro 

r^-om 

0-    1  0 

r-j^o 

<M-IO 

•>Hr-lr-4 

-0  1 

0 

1^      0 

moo 

UJ 

a. 

a:  II  c-       • 

-t      • 

r-  1    •«•  r-       ••M-in       • 

-0 

-0      • 

0              • 

in 

• 

03          • 

•— tr-4     • 

0 

0 

II  ^     0 

-0    0 

u>     0 

,-.     0 

P-       0 

r-     0 

t-     0 

0          0 

r- 

0 

0       0 

1^         0 

II  (NJ 

1 

•^         1 

,H 

,-< 

.— t 

.—4 

1 

r-4 

f<^ 

II 

"* 

t--;  II    .   • 
II  oor-- 

00-0 

00<\J 

OOO^ 

ocin 

CO-O 

000 

000 

oom 

OOOO 

OCu-l 

Z  11  OOro 

oOin 

OOI^ 

Of^JIM 

OINJfVI 

ootn 

0-0  O' 

000 

ooo-r 

onj^ 

00-0 

3  11  OCl-H 

0-^^ 

0-1 -< 

i^-oin 

f^OO-l 

(\J-40 

rg^O 

0-1  (M(M 

-0  1 

0 

r-     0 

ojo-o 

OC  11  0-        • 

n  1    • 

CO  1     • 

r-      •«in  1    • 

-0            • 

-0       • 

0 

in 

• 

00      • 

f-4            • 

11  ^    0 

•0     0 

in     0 

^    0 

t^     0 

r-    0 

r-    0 

0      0 

r- 

0 

0     0 

r^    0 

It  (NJ 

1 

1 

r-4           1 

»-» 

m 

II 

#-t 

•      •     •! 

ino 

II 

ocoino 

r^  II    •   • 

,  , 

,  , 

,  , 

«    • 

•  • 

•  • 

•    • 

• 

• 

•  • 

•  • 

coocnj 

II  00-" 

oo-o 

OOt--J 

COvJ- 

com 

corn 

oco 

000 

CO-i 

OOfM 

ooin 

C.O-0 

•  • 

Z  II  0  0  0- 

ooin 

oor- 

OrM-T 

OCO-T 

00^ 

0-00- 

000 

00 

-1.-1 

OlMO 

00-0 

mop-00 

3  11  O-.-NiO 

O--'-' 

O'-i'-' 

-o-n-j- 

0     0 

O-t-sl-' 

nj-HO 

— 4.^r-4 

1^ 

0 

crtMtvj 

(MtJ-O 

0^ 

a:  II  X       • 

m  1    • 

CO  1     • 

r-       •«  -O       • 

in  1     • 

-0      • 

0                • 

in 

• 

CO       •  *  -^       • 

r-r- 

II  --•     0 

-0     0 

in     0 

->    0 

r--     0 

1^     0 

r^     0 

0            0 

r~- 

0 

0     0 

r-     0 

roro 

11  PsI 

II 

1 

1 

-^ 

-^ 

-<      1 

—' 

'^ 

"* 

'"' 

ro 

■""■^ 

II 
1-  11   • 

. 

. 

a 

a 

, 

, 

, 

, 

>-i- 

0  II  0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

3  II  0 

0 

0 

00 

<NI 

0 

-f 

0 

CO 

00 

0 

as 

3 

II  r- 

0 

0 

CT> 

^H 

0 

0 

-0 

-D 

ro 

0 

u.  11  00 

-r 

00 

i~- 

m 

•0 

0 

0 

in 

CO 

0 

U-t-Ot 

— 1 

LU  II  r-l 

-0 

in 

r- 

1^ 

r^ 

0 

r- 

0 

r- 

UJCOi 

-1 

OC  ll(M 

c-l 

-^ 

f-i 

.^ 

p^ 

•-4 

m 

aJLiu 

•a 

II             h- 

1— 

1- 

*- 

y- 

►- 

1— 

»- 

•  II             Z 

z 

z 

z 

z 

z 

z 

z 

Z 

Z 

l-t->-ZX 

C  II  00       UJ 

cc     ai 

-0       LU 

0-       UJ 

0     m 

in     UJ 

I-.       UJ 

00     UJ 

-0 

UJ 

0-      UJ 

aaoo< 

z  II  -<o:o 

-ooto 

-l-QCO 

COQCO 

—  JiO 

oao 

->CLk^ 

-4  01:0 

-00:0 

t~a.<^ 

i-1-i-a.x 

11  -oc 

-j-o 

OC 

rno 

ron 

mc 

-i-o 

000 

-tc 

-4-0 

nf  II  -oor  a: 

•occc^ 

mor-Q!: 

O0[;cif 

OQca* 

on-oi- 

oaa 

r^oro: 

00c  OC 

OCCCf 

1— QiH- 

<T   II  fnoiUJ 

-oc^oj 

ooriu 

rH^'LU 

— loruj 

*-*  W.  UJ 

--<  O'  U  J 

p-aui 

r-lQCUJ 

-tOIfUJ 

enrz 

0  11  OIUQ. 

r-iua 

0  UQ. 

OlUQ. 

coja 

O'.UX 

oua 

I^UJQ. 

dJ 

j<i. 

CLja 

3'il(_> 

II 

i-co; 

II  -^ 
II 

IN] 

n 

-t 

■-'^ 

■  r 

■^ 

5- 

0 

c  -ItU 

Tests  of  Coupled-in-Motion  Weighing 


29 


t-  II  ooo 

ooo 

OOJ- 

oo-« 

ooco 

oo-< 

OOU1 

OOU-. 

ooo- 

OOO 

fAroio- 

(Tcra) 

^•J- J- 

CCtNJiA 

OO.NJO 

OOO 

mr-o 

r^r-r- 

(^1^00 

(\JOO 

o^o 

vroo 

cxjiniN 

■O  1  O 

IMOO 

o,r-< 

-"OO 

.-«-^— J 

ro— 1    . 

J--I  • 

r — 1  • 

030     t 

03          . 

O  1     • 

J--.  • 

<tf'  • 

~o     o 

—    o 

-c   1   O 

O      O 

03       O 

cr  1  o 

«!•      O 

r~     o 

II  .r     1 

O 

r- 

ir\ 

l/^      1 

t^     1 

f1         1 

m      1 

f^ 

o 

^4 

f\j 

CNJ 

ft 

-^ 

F-H 

f* 

»-* 

►— 

oil 

^    ^ 

,      , 

,   , 

,  , 

.     , 

,  . 

,    , 

.  , 

,    . 

OOfNI 

ooo 

ooc- 

oor- 

OOCT 

cor- 

OOOO 

OOO 

oo(~- 

OOO 

r^f-o- 

OfNJ-J- 

O-iO-i 

m  J-(VJ 

o-ooirv 

r-^(Nj 

^i»io- 

f<^i^CT- 

0<NJIM 

>— 

J- -JO 

r~-io 

cririiNj 

03  1  O 

_.     o 

in  1  o 

J-^O 

a3rri-i 

ojmo 

OOOO 

a:  II  -1       • 

O 

~0         • 

—1      . 

-•1     •»  o       • 

03          • 

o<      • 

~r       • 

r-       • 

>!•         • 

1-  •  •  • 

OOO 

0003 

OO-J 

ooin 

oo>j- 

ooo 

OOO 

OOf»> 

oor- 

OOIN     oo^- 

(M-J-O 

rsioi) 

— i^~T 

ino--" 

r-r~-r 

(Njx\ro 

^r-in 

xm,-> 

r\j^O 

(T-O-rn      iNlMtNj 

in     o 

^rg-j 

infNj^ 

rO(\j-J 

003ro 

cr      o 

O  1  o 

■J'-'O 

rrs     o 

cDrotM      -J>)-0 

o       • 

o 

-1  1    • 

-■  1    'ii 

o       • 

33          • 

a-  1    • 

-r 

r-       •»  ,!■  1    • 

CD  II     •    • 

II  ooo 

OOO 

OOfNJ 

OOin 

OOO 

00(7- 

OOfM 

oor- 

oocr 

oo>J- 

OOrO 

l-tMOO 

Z  II  03 

o 

inr^— * 

~ra30 

incrm 

<ys\m 

r^>J-rg 

—  or- 

cj-fNjin 

r>-l(\jCO 

— -l-T 

a^OI^J 

< 

3  II  J- 

o 

-I.-XJINJ 

vT-H-l 

.n  1  o 

oojm 

m  1  O 

o  —  o 

mc\/-i 

J-  — o 

0-  J-tSI 

— imo 

O         ••5-  O         • 

— <       • 

-1  1     •«•  o 

03    1      • 

o-  1    • 

^      • 

r-      •»<t  t    • 

o 

o    o 

r-     o 

.n     o 

in     O 

rr\       O 

(^     o 

m     o 

m     O 

o     o 

J-     o 

^ 

(M         1 

INJ         1 

--<     1 

—       1 

-■ 

— 

tn      1 

OOiniLi 
_lro      2 

_l           O 

r-  II    • 

• 

«    • 

•  « 

•    • 

•   • 

«    « 

■    • 

•   • 

•   • 

•  • 

•  • 

<           Z 

II  OOIM 

oor^ 

0003 

oom 

oo- J 

OOINI 

ooo 

oo-j- 

OOO 

OOO 

oo^ 

2  II  'n  I' 

nf^ 

i-invT 

03!\)0 

r"->o 

^-lO 

—  -TO 

->    o 

O3roo 

•Tr\o^ 

(\J(-MLO 

r\ja3^ 

OOO 

3  II  -J 

1  o 

>\J     o 

ro— lO 

O  1  o 

-.J-^ 

0  —  -1 

—    o 

mc\lf> 

<T'-'=> 

c>-rM 

l-'-'O 

OOO 

a  II  -I 

o       • 

o 

(M  1      • 

r-       • 

03          • 

a-  1    • 

-T         • 

r-      •• 

» <r 

(Njino 

—     I      -I 


on    •  • 

ooin 

OOO 

ooo 

ooo 

oom 

OOO- 

OOOO 

ooo- 

ooi-- 

oom 

Z.JJlUUJ 

o>>> 

Z  II  INI-l-<> 

oo3r* 

oo;n 

tr-nin 

r^-iO 

-lO,!- 

o—r- 

o—i-- 

(-OtSJJO 

a  ooo 

13  II  in     o 

ro     o 

m— o 

l^-^O 

OO-r^ 

CO  1  o 

o  — o 

in— lo 

J-— lO 

o       • 

o      • 

f*      • 

—1  1     •»  o        • 

CO  1     . 

0-  1     • 

-r 

r-       • 

>r  1    • 

II  si-      o 

o     o 

r-     o 

in     o 

in     o 

r^     o 

,■•-1      o 

ro      o 

m     o 

o     o 

-3-      o 

rH 

INJ 

INI         1 

'-I      1 

—      1 

—      1 

-J 

—J 

in      1 

o 

m  II   •  • 

•  • 

«      « 

•     • 

•   • 

•  • 

■  • 

•  • 

•   • 

•  • 

•   • 

3 

110  003 

oot>- 

ooo» 

oofo 

004- 

OO-H 

ooo 

oo-< 

OOIN 

ooin 

z  ii^r-o 

r-in-j- 

ror^ro 

in-i-r 

IMIMO 

.j-r^m 

03^0 

r-~rr~ 

a-r-in 

■j--j->r 

C^^\f\ 

3  II  -«•  1  -^ 

.!M       O 

ro     O 

r--JO 

OO-rO 

o-     o 

COINJ— 1 

rO(M-i 

rn     o 

r^cM-J 

0030 

O 

a  II  -1 

o      • 

o       • 

^-4            • 

—  1     .1 

i-  o 

r~  1    • 

O-  1     • 

-J- 

r~-       • 

m  1     . 

O                 1 

II  «!•      O 

o    o 

r~-     o 

in     o 

in     o 

ro      o 

m     o 

ro      O 

f<1       o 

o     o 

<r     o 

•~* 

U            1 

,-H 

(M 

IN        1 

I— I 

-"      1 

—      1 

— * 

f4 

in      1 

11 

'^ 

1 
1 

.«•  11    •   • 
11  OOO 

coo 

ooo- 

ooin 

OOO 

oo>f 

OCro 

ooo 

00<-sl 

OOO- 

OOin 

1 

TT  11  .T-i-cr 

cooin 

o-j-i~- 

fCO-^ 

--iror- 

iniNi  — 

J-r-fM 

■j-r-in 

-Jroisj 

oor- 

n-o-o 

311  .!■  1  O 

oo     o 

-T— O 

0-(Nj-l 

-i,t-i 

X  1  o 

C^  -H— 4 

un  1  o 

rri       c 

00 1^  — 

o     o 

■-• 

a:  II  -1      • 

o       • 

o 

•-4           • 

rvj  1     • 

O 

r-  1    • 

o- 

J- 

p-       • 

-f 

11-1-      o 

o    o 

1-      o 

■J^     c 

in     O 

m     c 

c*>      O 

rn      o 

m     o 

o     o 

vT       O 

2 

II          1 

II 
II 

r-l  II     •    • 

fV 

rg      1 

—       1 

—        1 

'J     1 

in 

< 

II  COt-g  OOt-0 

■  II  int-^i—  •4-fM— ' 

'  II  vf  I  o  r^— ■— I 

II  —       •  o       • 

II  >j-    o  o    o 


OCIN 

r^-HO 


OOO- 
J-O-o 
l~--iO 


OOO- 

—  mo 
Oinnj 
IN   I      'i 


OOtT- 
rolNX 

<r  — o 


IN  II     •     • 

11  co-1- 

ooin 

ooo 

oom 

ooo 

oom 

oor- 

oom 

OOO 

OCrO 

COvT 

Z  II  0-— IN 

O-f-O 

rnr-o 

CO  J- 

oa;cr 

i--or- 

INJ  — o 

s!-r~:^ 

cor^iN 

CTCM-- 

p-i^  — 

3  II  nT 

o 

O 

sj-— O 

Orri  — 

0-J-  — 

r--  — o 

•-< 

o 

ror 

Mr-* 

sf  — 

— J 

l--I\ 

l'^ 

r-iNO 

Ci   II  — 

• 

o 

• 

o 

IN        • 

(N  1     . 

o 

1    • 

OS 

• 

o- 

1        • 

■4- 

• 

r-- 

• 

•J- 

II  J- 

o 

o 

o 

r^     o 

in     o 

lA      o 

«\ 

o 

ro 

o 

r^ 

c 

ro 

o 

o 

o 

■4-      O 

II 

'"' 

IN 

IN         1 

'^ 

I 

'~* 

'^ 

1 

'~* 

^ 

— 

.  .  .roo 
aoooo 

•  • 

•  • 

•    • 

• 

•    . 

• 

• 

•   • 

•  « 

•  • 

O-TOOIN 

II  COC 

oot- 

OOIN 

ceo- 

com 

OCI-- 

ooo- 

COO 

oc 

0 

cc 

.—1 

OCP- 

vTCm    .    . 

Z  II  OINX 

o<rm 

-J- coo 

>ro  — 

r--r— IN 

CD  — O 

0-l> 

Jin 

-3-r^in 

xr^ 

IN 

r-r-o 

m  — o 

in  J-— OO 

:j  11  r"^ 

-•rj 

Osl 

o 

<r  — — 

o-i*-.— 

o-mcN 

CO 

o 

ODr^r-* 

^n 

1  O 

J-  — 

ft 

o- 

1^^ 

^r— o 

-j-<r  1   1 

K  II  —  1 

.«  O 

o 

—-1       • 

—  1    •»  o 

• 

t~-  1 

• 

o- 

• 

-r 

• 

p- 

• 

<T   1     • 

VI     -T 

n 

o 

o 

r-     o 

m     o 

■s\     o 

r> 

o 

m 

o 

rA 

o 

CO 

o 

o 

O 

>]■      o 

u-1^ 

11 

1 

-' 

'- 

IN 

IN         1 

'^ 

'^ 

1 

•-' 

1 

"^ 

'^ 

in      1 

— — 

1-  II    • 

, 

, 

, 

, 

. 

, 

, 

. 

. 

l-l- 

O  II  o 

o 

o 

o 

o 

O 

o 

o 

o 

o 

o 

OO 

3  11  03 

PsJ 

o 

~3- 

-r 

r- 

-^ 

r^ 

ft 

o 

vT 

SS.         3: 

II  ~r 

r-g 

r\l 

O 

O) 

^^ 

O 

rO 

in 

in 

LL  11  — 

O 

O 

.-* 

IN 

o 

03 

o- 

•J- 

r- 

-T 

LUI-Ii       _l 

o)  II  >r 

C 

r~ 

in 

in 

(O 

ro 

m 

r*> 

o 

%?■ 

LUOOC       _J 

a:  11 

,M 

p-i 

IN 

r^ 

-4 

-^ 

,-4 

ft 

-H 

in 

1- 

1- 

1- 

h- 

y— 

}— 

1- 

y— 

1- 

^— 

ft 

1— 

•  11 

z 

z 

z 

z 

z 

z 

z 

Z 

z 

z 

l-l-l-ZX 

O  II  — 

UJ 

IN 

lU 

m     UJ 

-^       LL* 

-H       LU 

CT 

LU 

in 

UJ 

nj 

Ul 

O 

UJ 

X 

UJ 

CjOCO< 

z  II  ooco 

ooco 

ooco 

CDOtO 

-J-cZO 

OOCO 

•j-oco 

l~-0CO 

IN  CJCO 

or^o 

I-I-I-Q.5. 

II  — c. 

— c 

— o 

ino 

inCj 

>rc 

oc 

f-O 

roc 

(NO 

a  II  o  ac  0- 

Ori-ci: 

Ca-C3C 

OQ  ctr 

ca  cir 

xccac 

mu 

:  Qc 

Oococ 

joc.i: 

INCiCOC 

t-cty- 

<r  II  O  2f  al 

Oo-uj 

CC-CLU 

rr'UU: 

i»-r!riL' 

CI 

y  -u 

INCI 

;  lu 

c.  < 

nruj 

\s\a 

UJ 

•fri 

LU 

c:ci  z 

O  II  C^J 

u:\. 

o  jj.-L 

O-UQ. 

O  J-Ci. 

Clu'^ 

O. 

Li 

O.JCl. 

O- 

u.1. 

O  J- 

lO. 

—  i. 

lU. 

3IUO 

II 

y-iSi-i. 

II 

<N 

n 

-J- 

■n 

o 

1- 

-o 

C- 

;x 

(-•3CL 

30  Bulletin  654 — American  Railway  Engineering  Association 


►-iioo-<    oo-^    ooCT>    oor-    oOnJ-  qoo    oor-    oof^    oooo    oo-*- 

O II  ^nJ-^m     ooo     (?»'-*>*■     oom     ininr^  rof^^J-     sO^^vT     miriin     >fOsj-     mmin 

h- K  OfNJO     ^^m,^    oo--^    oo*j-o    ^^a>o  ^-«vO.-^    ^-^co^-*    cot^o    mo^^    inino 

no      •     '^— <  •    o-^  •    cr  I    •    rg      •  c\t,~>  •     oo-<  •roi«crrg«o      • 

ll>»-     O     00     o     ooio     -o     o     -J-     o  o-io     -i-io     o     o     ooio     o     o 

11-^  <Nj  (Mioir-  ^ifvjioiroio 

ii-<^^-<  _<^  ^^ 

O  II 

^11  ••    ••    ••    ••    ••  ••    ••    ••    ••    ••    •• 

iioox     oo^J-     oo-^    ooo-     ooiM  oom     oo<Nj     ooiA    ooir\    ooo    ootr\ 

^iir-o^r*-     c— 'O     mroo     co-c^T     ^^ir\o  r\j«tPo     sj-^m     rgO'O     a*ir*fO     ^^^—^     sooorg 

3 II  o     o     — "iM^     ro-j-H     — 1^-^     m^(\i  sT     o     o     o     in-^rH     -h     o     -tv}--*     .Of<><-' 
ociisT      tco      "oj      'i^      •-!•      •■Iter       »    ir\      »     o      •     c      'O      •«sO'^  • 

ll-<0'NO'MOOOr~0'^OINO-OOrOOOOOO 


o>ii»»            ••  ••  ♦•  ••            ••  ••            ••  ••  ••            •• 

iiooiNj  OOOO  oocr  oor-  oor^  oofvj  oooo  oot\i  ooir>  ooo  oo(m 

Zii>j-nO^  ooor*  ininro  co^j-ro  --^^^o  O-^o  ^^rro  oooro  o^i/^m  coooco  >oco-o 

Olio     o  o— 'O  -H  I  o  a- I  o  t\j     o  •r-'O  o     o  ir>     --  o  i  o  f<^(»^^o  t>-oo 


oiNo<MOoor-o-^o(\JO-o 


•  *ir\ 


II  3 

CO  I K~J-00 

II  oo--"    oo-o    ooo^    ooo    ooir\    ootn    oo~j-    ooa>    oor^    ooo    oo-o    ofM 
zii-^r^-o    ryi<j-l-    r^mr-     so-ou^     o>r<ir-    inrriro    p-roo     a>fO-l'    o>mo    cjcmim    r--^-f     < 
3 II  o<  I  o     c<  I  o    o^fM-i    o  I  o     1SJ--I— I    ro  i  o     CO— '--i     m  I  o    o>^^    ^^^    ^^u^o 
QCiifO      "p-      -r-i^o      •>!■      'O^       •~i-l»o      •coi.o      •-J-I* 

II— <0<NJOCvJOOOI^O-JO(MO>OOrOOOOO>03 
il-4|-i|^l^l  ^1^1  1^1^  oi      ooir\uj 

II  -H  _JfO        Z 

II  _J         o 

r^i <        z 

iiooiTi     ooi^     oooo     oo-o     oor-     ooo     oo-o     oo.n    oor^     ooo    oo-l- 

zh>i-nJ-,-o     roin— <     — ^cr^     ^c•OLn     — ^mo     sOcnjo     ror-^^     (jro^     ^r^^f^^     — tcrcj*     mmo  ooo 

3 "  c>  I  o     —1—1— I    o-^-^     £3^  I  o     o^j     o    (Nj^— 1    r^.Mrvi     (>j^(M    oomtNj     O"  I  o    fvjoo  ooo 

aiiiro       'CO       •col'O       •^l•       •(7>l»-l-l»-M-OI»«co|.<i-o>       .^— i.  rjino 

ll-H0fM0(M000r~0— '0<NJO.OOrOOCT-00»IO  ••• 

II -"I-"               -11-11                          -,|^|                   1^1                  lOI  OO^ 

II  ^ 

II  i-QSoro: 

OII««  ••  ••  ••  ••  ••  ••  ••  ••  ••  ••  ZOIUJLU 

II  OO-i      oor-      OOO-      ooo      OOm      OO-i      OOiM      OO-O      oo-o      OOO      OOnT      o>>> 
z  II  minro     r<Mrt— *     aof\j^     cooin     r-j-riA     -^-j-o     o-J'O     aD>to     cooco     0'd->*'     orvjr^     a.OOa 

3  II  -^^-^      ^-<^      COrOINJ       O       O       -^   I  O       ^(SJt-vl      f^(\l-H       m  I   o      0O(M-^       C7>   I  o      ^j-coo 

ocii-1-      "CO      •p-i««-r^      'J-      •CT-i««~ri«o      •ooi.o>      •     'T  l    ' 

ll-<0<N0tsJ000^-0— iO(NJO-OOrriOCJ>00>0 

II  r^  ^  Wl-4  l^l^l  1^1  lOlOO 

II  -1  ►- 

II  o 

iTiii 3: 

II  OOIM      oooo      00<0      00~J-      OOrO      000>      OOOO      OOOO      OOJ>      OOO      OOINJ 

2'ii-r-OJ>     r-o-t     mr-00     ^cor-     r--H^     roino     »t-ooo     O(nj0>     r-r--o     >i--oo     roirvro 

3  II  O      O      ^— if-1      cX)f<^(NJ      C>  I  O      ^^      O      — irgcNJ      -OrnOsi      rO^^— *      p-mf\J      co-^— i      00>i-^^      O 
ctii-l-       "oo       •r-i.ito       '     <f       'O-l'ltvj-i.^oi'Ooi.ito^l'fn-t.o  c 

ll-iOfviOlMOOOr-O— iO<NiO-OOrOOO>OO^IO-^ 
II  r^  -1  ^|-<|  _<|^|  1^1  lOI  s 


>!•  II    • 

.  . 

.     . 

. 

.  , 

.  . 

.  . 

.    . 

.  . 

. 

. 

.    . 

1 

II  OOOO 

coin 

OOro 

ooo 

oo<t 

ooo- 

OCOO 

OOC7- 

ooo- 

000 

oom 

z  II  r--C7-p- 

roinc- 

oo(\jcr 

-1-.0 

mr-CT- 

roino 

-l-or-j 

Lnro-j- 

r-it\jn-4 

rOfT^fO 

0^a^rr\ 

z 

3  HO 

o 

rvjrs 

1^^ 

O-iO 

o  1 

o 

(M 

o 

-ll\IC\l 

CO -1-1 

■J-     0 

coroiM 

0 

0 

OOrrtO 

■-^ 

Oi  II  .I- 

• 

00 

• 

00  1     • 

r^ 

• 

-1- 

a-  1    ••!;•  vT  1    • 

0       • 

00  1     • it  0 

• 

-t  1      • 

II  —1 

o 

(\J 

o 

(M      o 

o 

o 

r- 

o 

-1     o 

r-j     O 

-o     0 

r<-i     0 

0 

0 

cr.     0 

z 

a. 

II  —1 

—I 

-^       1 

^H 

1 

r-l          1 

^      1 

-1       1 

—1 

0      1 

0 

a: 

II 

—1 

LU 

II 

1- 

m  II    • 

•   i 

•    • 

• 

• 

•  < 

•     • 

•   • 

•  • 

•    • 

• 

• 

•  « 

< 

lyO 

II  OOOO 

oo<r 

co-o 

oocr 

OO-i 

OOlTl 

OOO 

oocr 

OOM 

000 

oo-o 

(—1 

1/1 

21  II  r-o-i^ 

inr-r\ 

tMCOO- 

vO~0~}- 

ootN-0 

ooor^ 

oo^^• 

-000- 

r*^— irsj 

■ninm 

OCO-1 

> 

a 

3  II  O 

o 

o 

c 

00  (^.  INI 

CO- 

-1—1 

IM- 

1-^ 

o-sf  ro 

r-rot-g 

m  1  0 

oom.cvi 

0 

0 

or-i-H 

Ui 

Oi 

q:  II  -3- 

• 

CO 

r-  1     •■!!■  O   1 

1     • 

~r 

• 

CO    1      'it  ^    \      .  -K-  O 

CO   1      .-ifO 

• 

-3-— 1    • 

0 

0 

II  -1 

o 

(M 

o 

M       O 

o 

o 

r- 

o 

->     o 

rg     O 

0     0 

r<1     0 

0 

0 

o>  1  0 

II  —1 
II 

'~* 

-1         1 

■"* 

1 

-1     1 

-1      1 

1 

-1      1 

""* 

0     1 

(\i  II    •  . 
11  oor-- 

OOnI- 

oo~l- 

oo-o 

ooro 

OO-i 

oooo 

oor-i 

oooo 

000 

oor- 

Z  II  OOOCO 

cr-i-0 

fnr--^ 

r-in-j- 

f---i-i 

>r-j-o 

CT--1C0 

r--Lnoo 

0-4-PJ 

vl--J-~J' 

ooor-j 

O  II  00 -lO 

— it\i-< 

-1  1  o 

a-  1 

1  o 

—1 

o 

-lt--J(M 

X— lO 

-3-     0 

-1  1  0 

0 

0 

O^roo 

QC  II  fO    1 

• 

00 

■ 

00          • 

-o 

• 

~J- 

• 

a-  1    ••><■  ~j-  1    • 

0       • 

0- 

0 

« 

<r  1    • 

II  ^ 

o 

tM 

o 

CM       O 

o 

o 

r- 

o 

^     o 

r-j     o 

•0     0 

rr,     0 

0 

0 

CT-      0 

II -< 

1 

—1 

-J         1 

—1 

1 

-1      1 

-1      1 

-1        1 

0        1 

II 

•       •       •! 

-10 

II 

oooino 

^  II    • 

• 

•  1 

•    • 

• 

• 

•  < 

•  • 

•   • 

•   t 

•    • 

• 

• 

•    • 

0-1  CT-Or-i 

II  oooo 

OOfO 

00-* 

ooo^ 

ooc 

OOO-I 

OOO 

000 

00-1 

000 

000 

cor-jin 

9  • 

z  II  <>o>r- 

•-tmcNj 

CT'-i-t 

-oo~i- 

-0 

o 

o-cr<r 

inirvx 

C7-(^C0 

-OOOO 

— ia~o< 

— ir-r- 

(Nj(--inoo 

3  II  CO  1 

o 

o 

o 

oomtNj 

00- 

-1-^ 

-^ 

o 

Oo-j(\j 

Oro.--Lj 

-KNro 

cor-ir-1 

ao-1-1 

j-co-i 

in.^j-  1 

1 

Qt  II  m 

• 

tx> 

• 

I--   1      •■il-~C   i 

1    • 

^ 

• 

0-1    '^^rl    '-trOl    ••K-coi    '#  (y 

1    • 

r*^— 1  • 

O-CT- 

II  -< 

o 

(M 

o 

tsi     o 

o 

o 

r- 

o 

-1      o 

c\l     O 

-0    0 

t<\     0 

V 

0 

c-  1  0 

00 

II  -^ 

1 

pH 

-1      1 

,-1 

1 

-1      1 

—1      1 

1 

-<      1 

1 

0      1 

-H-^ 

II 

II 

t-  II   • 

, 

. 

, 

, 

. 

. 

. 

. 

, 

, 

t-l- 

OHO 

o 

o 

o 

o 

o 

o 

0 

0 

0 

0 

00 

X  II  00 

CO 

o 

f>J 

o 

CD 

o 

rg 

~r 

0 

CO 

33 

3 

II  o 

o^ 

(NJ 

o 

-^ 

m 

o 

«J- 

0 

fM 

0 

J.  II  ro 

r- 

00 

r-- 

>r 

C7- 

in 

0 

CT- 

0 

in 

U-I-Qf 

_i 

UJ  II  — 1 

<NI 

(N. 

o 

r- 

—1 

r-J 

-0 

ro 

0 

c- 

LUOOC 

_i 

a  II  -1 

—1 

r-M 

—4 

-^ 

—4 

—4 

—1 

0 

CCX.ijJ 

< 

II 

t- 

1- 

1— 

t- 

1- 

^ 

1- 

1— 

h- 

H- 

--1 

1 

h- 

•  II 

z 

z 

z 

z 

z 

z 

z 

z 

Z 

Z 

t-Kt-ZX 

O  llf- 

UJ 

o- 

m 

-<       UJ 

o 

LU 

00 

LLI 

0-        LJJ 

C-       LU 

■O       LU 

-0       LU 

CD 

LU 

occo< 

Z  H  POao 

(MQCO 

r-ao 

OOIO 

r^crro 

moiO 

-'Ctl^ 

OQiU 

—euro 

-10:0 

1-i-i-Q.s: 

H  OO 

-iC 

■OO 

-lO 

mo 

OO 

o-o 

00 

0^0 

COO 

or  II  ociroc 

tNJQ^Qi: 

ooro: 

— iQf  q: 

ir.Qr  a: 

OCX  a 

-00:0: 

(Vara: 

-ooca. 

-larcr 

t-Oth* 

<  II  o-araj 

rrc: 

LU 

oaroj 

T-C 

t  LU 

onruj 

ro.r  LJJ 

COCUJ 

-OarTLU 

OQCLU 

r-  c/ '  u 

ooirz 

O  11  Ou 

JO. 

■MJJQ. 

oiua. 

O'JJQ. 

on 

J  3. 

-iiua 

OOJQ. 

OLUi. 

OJJQ. 

r- . 

UQ. 

SLUO 

Tests  of  CoupIed-in-Motion  Weighing 


31 


t-  II  ooin 

000 

OOCT- 

OO-- 

000 

OOr<> 

OOCO 

OOCM 

OO-i 

oor- 

c  II  -r-oo 

OO-" 

fMXO 

-•a~o 

C\J  XI  — 

,-\J  £.%! 

r-rrir~ 

OOX 

C-iO 

ror^co 

>-  II  r~-  1  o 

ir.^-.-xJ 

r"OiM 

-lO-i 

l/>  1  0 

irv.-^JO 

l~-(M-i 

l~-vAO 

O-vJ--" 

■oroo 

II  o-        . 

(MtM    • 

C3-.-M    . 

o~—  . 

.-<        • 

m  1    • 

l~-IM     • 

CO    1       . 

0-1  • 

0-  1     • 

II  ro      o 

cu     0 

f--  1  0 

~0  1  0 

>J-    0 

0-     0 

J-  1  0 

0    0 

X  1  0 

CT-       0 

n  -•      1 

0     1 

r-      1 

-<      1 

CNJ          1 

•0     1 

ro       1 

0-        1 

i/> 

,^ 

.^ 

— « 

-4 

<-* 

►- 

O  II 

0 

•     * 

•    • 

•    • 

•  • 

•  • 

•    • 

•    • 

•    • 

•    • 

•     • 

3 

11  ocr- 

0033 

oox 

ooj- 

OOCT 

000 

OOoO 

00—1 

000 

000 

000 

7^  II  orxj-. 

ooor- 

00-0 

0-ro_l 

o-r^tNj 

00     0 

•J- -00 

co>rcci 

^ryrr^ 

CM  CM  CM 

(T-O-co 

1- 

3  M  O-  1  O 

o->o 

•a-o-t 

r-<MfM 

C--ifS| 

ra      0 

r~r\jrM 

CM-^CM 

O— !-• 

0       0 

l^>J--" 

aooo 

nc  II  ro        • 

CO          • 

r-  1     •»  .0  1     •»  m  1    .»<r       • 

>J-   1      .IfO   1      .#00   1      • 

0          • 

CO—    • 

1-  •  •  • 

M  ->      O 

(SJ       0 

(Nj     0 

0    0 

r~     0 

-1      0 

CM       0 

0       0 

CO      0 

0       0 

0   1  0 

croo 

•->      I 

1 

— t 

^^       1 

1 

-1       1 

—* 

0        1 

LLCM 

II 

-" 

a 

a-  II    •  • 

,  . 

.   . 

.  . 

,  . 

.    . 

.  . 

.     . 

.   . 

.    . 

.    . 

1— 

II  oo>n 

oom 

00-0 

OOCO 

ocr~- 

CQ'O 

00~D 

00.1- 

OOCM 

000 

oo-r 

z 

2  II  i^  -r  rn 

r^  i>a- 

00^ 

.T--00 

oouo 

u-vr-in 

r^*' 1 

vOOsO 

p,-r-cM 

coco.-o 

.ocMr~ 

0 

3  II  O      O 

(M<\J— 1 

CM-" 

Or<-.ro 

0  1  -1 

«f     0 

r-PMCM 

CM-iCM 

cr-i-< 

0    0 

,3-XO 

a. 

a  II  -r       • 

GO             • 

CO   1      • 

01    •»  vr       • 

0- 

vT    1      •»  0    1      •»  CO   1      • 

0 

vr  1    • 

11  —     o 

tM       0 

(M       0 

0    0 

f~-     0 

-.     0 

CM       0 

-a     0 

CO     0 

0    0 

cr     0 

_4 

-•         1 

1 

^^ 

-1         1 

1 

-■      1 

—4 

0      1 

_i 

II 

-" 

< 

3 

aj  II    •  • 

•    • 

•     • 

•    • 

•  • 

•   • 

•     • 

•    • 

•   • 

•     • 

•  • 

l-(J>00 

II  OOr^ 

CO.-xi 

ooo- 

OOtM 

oa^ 

OO'O 

oox 

00-0 

000- 

000 

OOro 

(_)<M 

Z  II  tM,00 

•oaD.0 

OrvJO- 

a-r-c\j 

OJOCD 

cr-i-c 

00 -J- -o 

^rorvj 

CMXX 

r-  — X 

< 

3  HUT  J-  ^ 

0    0 

O-.-N.-" 

o-rm 

Cr-irM 

rv  — 0 

r^-cM— 1 

CO  1  0 

cr— '— • 

r-CMCM 

AJO-l 

a:  II  ro  1     .•»  CO       • 

r-  1    • 

,0  1     •»'<>  1     .VCT-   1     • 

vl-      1          • 

0      • 

X  1    • 

cr  1    .-B-coiM   . 

II  -•     o 

(\J    0 

(\j     0 

0    0 

f~    0 

-1      0 

CM       0 

-0    0 

ro      0 

0-    0 

(7-  1  0 

S. 

II  -■     1 

-«      1 

-•      1 

1 

■— 1       1 

-•         1 

1 

-1       1 

' 

0       1 

coinuj 

-ICO      z 

_i        0 

r-  11    •   • 

•    • 

•  • 

•    • 

•    • 

•    • 

•     • 

•    • 

•    • 

•    • 

•    • 

<        z 

II  0003 

00-c 

000 

00-0 

OOro 

OO-i 

oox 

oo<r 

000 

000 

oo<j> 

2  11  cj-crr- 

r-o-Ni 

l^lTi  J- 

ONj-n 

r">.-\  J- 

.0--il\j 

COC7-— 1 

CO  —  '^ 

X:mcm 

.-NJ^-O 

000 

3  II  OD  1  o 

.-M.-NJ.-Nj 

cr.Ni.-M 

0    0 

(s-     0 

>r     0 

in  J- CO 

,-M— ICO 

Tcsj-1 

a<  1  0 

■s\t~o 

000 

q:  11  m       . 

CD       • «-  r-  1    •  -K-  r-       . 

^»■ 

o- 

•4-1    •■; 

J  0   1      •*  X  1      • 

c^ 

J-  1    • 

cMino 

II  '-     o 

(\j     0 

(M       0 

0    0 

r~-     0 

-1    0 

CM       0 

-0     0 

CO       0 

a-     0 

o-     0 

•  •  • 

-•      1 

-• 

-«         1 

1 

—1      1 

1 

0     1 

00  — 

II 

'>-a:a.(± 

-O  II    •   • 

•  « 

•    • 

•    • 

•   • 

•    • 

•     • 

•    • 

•    • 

•  • 

•    • 

ZlUUJUJ 

11  ooo 

000 

OO-H 

OOCO 

Oom 

OCX 

oop 

00-0 

ooa> 

coo 

oox 

o>>> 

■Z  II  ^/^^-^r^ 

lAr--^ 

cofsir- 

mp-io 

r — 1-1 

—  roio 

00-0 

oj->o 

co-<r- 

i--r-r- 

t^J^O 

O-OOO 

3  II  (NJtMOj 

tSJ.-V.-M 

a^oj^^ 

00—1—1 

-.     0 

J1-.-1 

XCM— 1 

~r     0 

0-10 

0     0 

CO       0 

a  11^         .«33        •■itr-l     • 

0  1    • 

-J- 

c^ 

«r  1    • 

0 

0-  1    • 

0      • 

m       • 

II  -"       o 

tM       0 

rvj     0 

0    0 

r-     0 

-1    0 

iNI      0 

0    0 

CO       0 

0     0 

a>     0 

II  -• 
II 

-1      1 

'-' 

-1      1 

-1     1 

-^ 

0 

i>i 

0 

J-.  11      .    . 

•    • 

•   • 

•    • 

•  • 

•    • 

•  • 

•  • 

•    • 

•  » 

•  • 

3 

11  ooc^ 

00-3- 

oo~r 

OOC 

oo>i- 

oor^ 

OOCM 

OOCM 

OO'^ 

000 

OO  — 

2  11  (*>-rv^^ 

,-tr<^.-» 

-TJCN; 

,o~rro 

-OOro 

xo-0 

-IC'-r 

>rx(0 

r-^CO.-M 

CMCMCM 

ooor^ 

3  II  tMtMt\J 

■-r>iO  J- 

0— 1-1 

— l.-^'^ 

iM-4-1 

ITHNJ-l 

X  — 

^  t  -< 

-•  1   0 

0       0 

or-o 

0 

nC  II  -J-       • » 50       . »  n  1     . 

r-       . 

<■ 

(7- 

<r  1    • 

0 

(7- 

0          • 

•0 

0 

CM      O      O      O 


o     o~     o     — 


~r  II  •  • 
II  occ 

OO^r       C'O-' 

OOCM 

OCri 

000 

00,0 

000 

OC<!- 

000 

OOvf 

?  w  -r-c-^ 

xoco     xf\.r^ 

^CM  — 

CM-C  — 

X     0 

XCMCT- 

CM       0 

LOO--C 

-Osl-^J- 

inr-cM 

—  II  — 1— «_< 

CMCorM       CJ'.•^^  — 

—---I—) 

rc\_i  ^J 

fO      0 

X  — 0 

-r     c 

0  1  0 

C-  1  0 

IPIMO 

a:  II  ,r      • 

X       .*r-  1    • 

1^          . 

<■          •■> 

«■  3^         • 

-r  1    • 

0 

C7>         • 

O- 

.n       • 

II  ocr- 

OCO 

ceo 

oox 

OOro 

OOCM 

000 

OOC 

000 

coo 

oox 

< 

VO 

^  II  CCM 

— « 

7-  — .Nl 

— 'T- 

CM 

j^  f^  n 

o-i-.o 

—  •,- J- 

Lrvj^Nj- 

x-c 

0 

c-^.r- 

1^-^, 

rr> 

'j^'O^r 

> 

c 

3  II  C 

0 

CO<-CC^ 

C-CNJCM 

x—*— * 

CM 

0 

CM— «— » 

cr  1  0 

•^ 

0 

racM- 

X— 1 

— 1 

i^ino 

UJ 

QC 

CL-    II    J- 

• 

X       .«-r-  1 

•  « 

vC     1        • 

>r 

• 

C7-   1      • 

>t       • 

0 

• 

X  1    • 

0-  1 

• 

«!•  1     • 

c 

0 

ir  — 

0 

(N      0 

CM 

0 

0    0 

r- 

0 

—       0 

CM      0 

-0 

0 

CO       0 

<7> 

0 

Q-      0 

II 
.>j  II    •  . 

II  oc 

'~* 

■"* 

1 

—     1 

—        1 

—        1 

—     1 

1 

0       1 

CO 

OCO- 

(z:^ 

,J" 

CCI^ 

o- 

jr- 

OO.-M 

OCCM 

oc 

CO 

OCO 

c^ 

0 

oox 

;•  ii<;^ 

iC^ 

-^coi^ 

CO 

ro 

r^i/>c\j 

.-^1 

.0,0 

o-o- J- 

—  crco 

<r."Mco 

oj-o 

r^co 

ro 

,0  cm  CO 

3  II  r- CM 

1^^ 

CMCM  — 

ceo  CM 

-ceo  CO 

—1 

1  0 

OCMCM 

l~-c\j,-s, 

,j- 

C3 

0— — 

X  — 

1^^ 

t^ir\— 

n;  II  (O  1 

• 

X          • 

I--   1 

•  ic  .0  1    • »  >r 

CT  1     •■; 

!■  J-    1      •■*  0 

C   1      • 

c  1 

• 

ro—   • 

11  — 

0 

CM       0 

CM 

c 

0     0 

h- 

0 

—    c 

CM        0 

•0 

0 

CO      0 

0- 

0 

CT>  1  0 

1 

1 

1 

—     1 

—          1 

—     1 

1 

0      1 

II 

•  •  • 

•4-0 

II 

OOCinO 

—  11    •   < 

•     • 

•     • 

•  • 

• 

• 

•    • 

•     • 

*  4 

•    • 

•  ■ 

•  • 

CCOOCM 

II  r:>Q: 

'X 

ocr- 

CO 

X 

OOCM 

C  : 

ceo 

OCCM 

0  c>r 

n-. 

;-o 

cc^ 

OOC 

OCC 

COXO 

•    • 

Z  II  1^—0 

CMJ-X 

—  a< 

^ 

or,-in 

O^TlT* 

—  r,- J- 

r^coo 

.-^  — 

1—1 

0  J-CM 

tr  T-cj- 

r-— 0 

CMOOOO 

3  II  c-   1 

0 

CMCM  — 

c  — 

^-4 

■■MCMCM 

CM 

0 

CM  — — 

r-cM— 

>r  1 

0 

—  1  0 

0 

0 

CM  1  0 

s^-t  1 

1 

X          • 

X    1 

• 

^-       •'. 

*  J- 

C-   1      . 

J-  1    • 

0 

o>       • 

0 

• 

■r\       • 

(7-0- 

11  — « 

0 

CM       0 

CM 

0 

0    0 

r- 

0 

—    0 

CM       C 

0 

0 

CO      0 

0 

0 

0     0 

00 

II  — 

1 

'-' 

— 

1 

— ' 

—      1 

—         1 

1 

—        1 

-" 

0      1 

— — 

1-  11    • 

, 

. 

, 

, 

. 

. 

. 

. 

. 

,_^. 

0  II  0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

3  II  X 

X 

0 

CM 

■a 

X 

0 

CM 

,r 

0 

X 

^3 

3 

II  c> 

c- 

C^4 

0 

—1 

CO 

0 

-T 

— « 

0 

CM 

0 

U-  11  (^ 

r- 

X 

.■^ 

•J- 

Q- 

ir\ 

0 

(3- 

f) 

in 

U.I-2C 

_) 

llJ  11  — 

(Ni 

CNJ 

0 

r- 

— I 

CM 

0 

CO 

0 

c^ 

U.Gt^ 

_l 

oc  11  — 

^^ 

,-* 

-^ 

—1 

— « 

^-* 

—4 

0 

Cti-OJ 

< 

II 

1- 

^- 

»- 

h- 

>— 

1- 

1- 

1— 

\~ 

1— 

—4 

1— 

•  II 

7 

•^ 

■y 

2 

X 

Z 

z 

y 

y 

;' 

l-l-l- 

.,'X 

c  II  r- 

MS 

0       lU 

— « 

UJ 

C       UJ 

X 

UJ 

C3-       'J- 

0-      UJ 

^ 

■Q       UJ 

X 

UJ 

CCOO<I 

2-  II  CMCCO 

CM  ceo 

r-QCO 

OOCO 

CO 

OCO 

inaco 

—  Q-O 

ccto 

— nco 

—  OCO 

1-t-f-Q.i: 

11  CO 

— c 

vCC 

— c: 

CO 

r. 

OO 

crc 

00 

c^c 

xo 

□r  11  ca:ct: 

CMcXCt 

^aor: 

—  Q-  tic 

l/^OCQC 

CCLOC 

vOocnc 

coc^ 

■Ci 

-OQCOC 

—  UL 

Cl 

l-CCl- 

<*  11  cr  '5f  -jj 

r"D-uj 

c:3C 

lU 

CJ-iruj 

vO^rul 

coc<U.i 

coruj 

-C,-tuJ 

0=caj 

r-cr 

i:J 

ojrz 

0  II  OOJQ- 

CMi-JCL 

C:iJ 

la. 

C-l-i 

0 

.U3. 

—  ja 

Cl-lO. 

Ou. 

.'2. 

Oi-jn. 

I^U, 

la. 

.«UJ0 

11 

i-'ioc 

II  "* 

CM 

fO 

,!■ 

iT 

0 

"^ 

■0 

CT> 

0 

P<ia. 

32  Bulletin  654 — American  Railway  Engineering  Association 


II    •  • 

t-  II  OOi/> 

ooo^ 

OO-O 

OOf^ 

oo-o 

OOCO 

OOfSj 

OOO 

oor- 

ooo 

O  II  O  O  -J- 

00-" 

OOOO 

OOCT- 

ooo 

ooo 

OOO 

OOINJ 

OOvT 

oorg 

t-  II  r~r-o 

o-cr-" 

-r-oo 

inmo 

a--iO 

OOO 

inin-H 

a-O'-i 

coco-« 

-O-J-O 

II  CO 

• 

OIM    • 

O-i   • 

^-H    . 

CD   1      • 

,t(M    • 

OOINJ    • 

OIM    • 

-.(N    • 

in  1 

1    • 

Wf> 

o 

rg      O 

<o  1  o 

•*■     o 

—    o 

(M      O 

(\J      O 

^    o 

o    o 

r- 

o 

II  in 

* 

00     1 

in 

in      1 

o 

-r 

^^■ 

o- 

a> 

1 

CO 

II  -^ 

O  II 

<VJ 

-^ 

■^ 

'-' 

rvj 

ni 

IN) 

-" 

-• 

►- 

, 

,  . 

,  , 

,  , 

,  , 

,    , 

,    . 

,     , 

,  , 

, 

, 

,  , 

-I 

II  ooi;> 

oofo 

OO-J 

ooo> 

ooin 

OOtT- 

OOINJ 

oo-r 

oor- 

ooo 

ooin 

^  II  oo-o 

<DO<SI 

oo-o 

oorj 

ooo 

oo~j- 

0003 

OOINI 

OOin 

o 

o 

oom 

t- 

13  1IO>--0 

r-m^ 

crm^ 

-HfM-l 

00 -<o 

r0-"0 

COINO 

-•m-" 

(Njr«1w 

•o 

C3 

<ri^o 

O' 

a  II  fn 

• 

r\i        • 

in  1    • 

<J-  1    • 

-.  1    . 

fvj        • 

(NJ         • 

.-«      • 

O        • 

r^ 

• 

(\j      • 

1- 

II  in 

o 

.J-      O 

00      o 

in     o 

in     o 

O      O 

■J-       O 

~r     o 

o-    o 

o- 

o 

~o     o 

II  -> 

fVJ 

-^      1 

'->      1 

-1      1 

(M 

(M 

<M 

f-* 

1-* 

o> 

u. 

II 
II 

a-  II   • 

. 

.. 

.. 

.. 

.. 

.. 

^    ^ 

.. 

.. 

^ 

^ 

.. 

»- 

iiooin     ooM     oor-     ooo     ooin     oooo     oo(m    oo-j-     ooin     oo-h    oo-<     z 
iioocr     ooao     ooo     o     o     oo-o     c 
iii-<m— I     oruo     o<Nj-j     fTi     o     oo-<o     ir 
II -r       •(->!      'Oi'^r       .^|.(\ 


iiooiri     oo<^     ooo     oo<t     ooin     ooco     oot^J     oo— •     oor~-     ooo     ooo    o 


ooo- 

oo-o 

oo~r 

oooo 

oo~>- 

ooin 

0<»^— ■ 

CO -JO 

mro«— 1 

crt-go 

CT'-'O 

(\ji^-i 

^  1     • 

'-'  1    • 

(Xj        • 

C-M         • 

O 

o 

II 


II  ooo     ooin     oo— '     oo-^     c:D:r\    oooo     ooro     oo-r     ooin     ooo  oo-o 

^»o     o     oo-o     OO-O     oo-o     oo-o     ooc-     oor-j     oofM     cDoo    o     o  ooin  ooo 

3  1100      O      cO,r— •      CT-m— 1      <N^o      O— 'O      -J-.-vJO      O-ro— <      ^ro— I      — ir-j^      o      o  cD-<0  OOO 

QtiirTi       •r-j       •inI»-j-l«fNi       -fM       •r-j       •— <       "O       •!--        •  rvj-j   •  njino 

iiino^ooooinoinooON}"0^ocT-oa-o-oo  ••• 

11^                  (N                  ^         \         ^         i         ^                  <M                  (NJ                  <M                   ^                  ^  O-  00-< 

II  i-xocae. 

.Oii»»     ••     ••     ••     ••     ••     ••     ••     ••     ••     ••  :?'uu,'Lu 

3     oocT-     ooiNi     oo^l-     oor-     ooo  or.—-  o>>"> 

D     oo-j-     ooco     oocM     ooin     ooo  oao  aC'jO 

D     r<^— <0     a;rgo     ^ro^     cNjrc^     u^— *o  f^o^^ 

•         PSJ  •         fM^^     •         ^  •         O  •         1--     I        •  fOf\J     • 


II  oO'n 

OOO      OOrO 

oo-j- 

Z  II  ooo- 

ooo     oom 

oorg 

zj  11  ^ro-i 

CMntM     — i-io 

ccinf<^ 

of  II  nT          • 

rg       •*  -o  1     • 

>»■       •• 

in  II    •  • 
II  oOin 

00<~g 

OOro 

oo-j- 

oom 

O  0  3- 

oorg 

oo* 

oom 

ooo 

OO-O 

i 

z  II  ooo 

OOOO 

ooin 

ooo- 

ooga 

OO* 

ooco 

oorg 

ooo 

oom 

oor- 

O  llC^  — 

o 

0(M0 

— i^O 

■^m'-* 

O-iO 

rOr-io 

corjo 

— .rri-i 

-irg-i 

r-r-io 

.■simo 

O 

• 

Q:  II  r^ 

t-g        • 

-O  1     • 

~T         • 

(M          • 

rg        . 

Aj       . 

f~-*       * 

o 

r--       • 

ro-4   • 

O 

o 

II  in 

o 

-I-      O 

00      o 

in      o 

m     o 

o     O 

*     o 

*      O 

cr-     o 

(7-      O 

o     o 

—I 

o 

II  -* 

rg 

-<     1 

-J 

,— t 

rg 

.Nl 

rg 

—4 

<— 4 

cr 

CO 

II 
II 

'^ 

1 

1 

rg 

-J-  11    •  • 
II  ooo 

OOINJ 

ooo 

oo* 

oom 

oooo 

oorg 

oom 

OOO 

OO-i 

oo-o 

1 

Z  II  oo 

r^ 

OOCO 

o    o 

oorg 

oo-o 

oocr 

ooco 

oox 

OO-i 

oom 

oooo 

z 

ID  II  -CtNl 

,-t 

-OtMO 

(M       O 

Xini-o 

co^O 

-i-rvio 

x.-sio 

o.%io 

rr  <rro 

a  (^—1 

*r-o 

•-' 

oi  iim  1 

• 

CM        • 

o 

~I-        •■«•-<  1     • 

.-NJ 

■^ 

.-J        • 

o       •■«•  r-       • 

rri-i    • 

II  in 

O 

~r     o 

CO     o 

in     o 

m     o 

O      O 

-r     o 

*       O 

c-     o 

CT-      o 

-O      O 

z 

T 

II  --I 

1 

(NJ 

,-^ 

,-4 

^      1 

rg 

rg 

rg 

r-H 

^~t 

cr 

o 

orr 

II 

-^ 

>-• 

Lb 

II 

>— 

ro  II    •    • 

*    • 

•    • 

•    • 

•  • 

•   • 

•    • 

•   • 

•    • 

•   • 

•    • 

-^ 

U3 

II  ooin 

00<N 

OOO 

oo  J- 

com 

oooo 

OOr^ 

COrr' 

ooi^ 

ooo 

OOO 

»-• 

l>0 

^  II  co-o 

OOCO 

o     o 

ooo 

co^ 

oo* 

CO.-xj 

oc  :: 

com 

oo  m 

oom 

> 

o 

=>  II  r-^ 

lO 

OIMO 

(M       O 

f\Jr-io 

.-0--O 

mro^ 

Crl  — 

orgc 

.-gm--* 

r^  — o 

00-40 

LU 

cc 

a  II  m  1 

eg 

-o        • 

-J  1    • 

—  1    • 

(M          • 

f-g         • 

r— 1                • 

o       • 

r-       • 

rj-j   « 

D 

O 

II  ^ 

o 

-r     o 

00     o 

m     o 

m     o 

o    o 

*      O 

*            O 

ON      o 

0^      o 

o    o 

II  -H 

II 

tNJ 

"" 

-•      1 

-"      1 

rg 

CM 

rg 

"^ 

" 

cr 

rg  II    •  • 

II  ooo 

OO.-M 

OOrO 

ooc^ 

oom 

oooo 

oo-j- 

OOI^ 

OOP- 

oo* 

ooo 

Z  11  C  O  r'> 

oocn 

oo-n 

oorg 

oo-o 

ooc< 

ooo 

OOO 

oom 

oom 

ooo 

3  11  onj 

!•— ' 

-O.-MO 

^-■o 

inrgr-i 

OrHO 

*rgo 

o-t-> 

rrimrg 

rgro  — 

o-r-m 

0(^0 

Dt  11  -J- 

• 

rg       • 

-C  1     • 

~r 

tsj        • 

rg       • 

ro       • 

■-<      '^a 

-O  1     ••»  C.-J    • 

11  in 

o 

■J-     O 

00       O 

in     o 

m     o 

o    o 

*     o 

*      O 

o-     o 

o-     o 

o    o 

11  '-> 

rg 

-J     1 

r~t 

pj 

rg 

(N 

rg 

—4 

'-•      1 

0- 

II 

.-1 

«  .  .r-o 

II 

OOOOO 

•  • 

•    • 

•      • 

•  • 

•   • 

•    • 

•   • 

•    • 

•  • 

•    • 

OCOOrg 

II  oom 

ooin 

oox 

OOrr. 

oom 

oocc 

oom 

co-o 

oor- 

oo-- 

CO-i 

Org.-M 

•    • 

z  II  oo-o 

oo-o 

oo-o 

oom 

oo-o 

ooo- 

00(\J 

oo-o 

oom 

ooo 

oocr 

r--omoo 

3  11  c- 

'O 

00  ^T-- 

r^m  rg 

Ol~->J- 

o-^c 

*rgo 

O-l^-H 

rg*-. 

rgro-^ 

*rg,-j 

mco(D 

-4m-4 

y.  wrr, 

• 

r\j       • 

in  1    ". 

;l-m       .-; 

f  og       • 

(N.        • 

rg       • 

—4            • 

O       • 

r-  1    • 

m^  • 

OO 

11  in 

o 

-r     o 

00      o 

m     o 

m     o 

O      O 

*     o 

*     o 

o<    o 

c>     o 

o    o 

O-rT 

II  —1 
II 

rg 

'-'      ' 

"' 

"^ 

rg 

iNI 

rg 

'^ 

-H           1 

0> 

-H— 4 

t-  II    • 

, 

, 

, 

, 

, 

, 

, 

, 

l-l- 

O  II  o 

o 

o 

o 

o 

O 

o 

o 

o 

o 

o 

oo 

3  II  O 

o 

o 

o 

o 

o 

o 

o 

o 

o 

o 

33 

3 

II  CO 

-r 

rg 

m 

a- 

r-j 

-o 

X 

(y 

-0 

r- 

O 

U.  II  (^ 

-O 

•r 

,-t 

rg 

rg 

o 

o- 

r- 

—4 

u->-q: 

_l 

Lu  11  m 

~i- 

00 

m 

m 

O 

* 

* 

CO 

a- 

o 

LUCOC 

_l 

OC  ll-J 

(M 

.-H 

—4 

rg 

rg 

rg 

—4 

—4 

0~ 

C^SL-U 

< 

II 

1- 

1- 

^— 

1- 

1- 

1— 

1- 

1- 

►— 

1— 

—4 

h- 

•  II 

z 

z 

z 

Z 

z 

Z 

Z 

z 

z 

z 

i-i-i-zx 

O  llro 

OI 

t-4         tU 

(SI       LU 

r~     uj 

^        LU 

<t        LU 

O-        LU 

rg     UJ 

m     LU 

^^       LU 

oooo<t 

Z  11  O^Qto 

moco 

o-a:o 

njoi^o 

—  OfTU 

COOCO 

oci:o 

r-QJO 

moco 

OOCO 

i-i-i-Q-s: 

iir-o 

aa 

->c 

ceo 

ono 

*o 

ooo 

*o 

-oo 

c^c 

OC  11  -J  act 

cccia 

-iQ;a- 

r-  a-a. 

moiQ^ 

rxQrrorr 

-<ac^ 

X£i:ci. 

->ci:of 

*o;cx 

l-Ctl- 

<  »  ma 

LU 

r-rir  LLi 

r-5!"jj 

J-Q-UJ 

OOflU 

m  :£:lu 

-ooruj 

OCT  OJ 

mo-'jj 

*r»"xi 

J>a:z 

O  II  r\j  '-u  Q. 

Oujci. 

oil.  a. 

r<-,._ijCi. 

O-UQ. 

—  LUC. 

OLUO. 

Cidjn. 

—  UJO. 

— i^a. 

3dJl_) 

Tests  of  Coupled-in-Motion  Weighing 33 


I— M  OOO^     OOO     OO-O     OOi^     OO^     OOrg     OO^  OOro     OOrsj     OOir» 

Qiir«>r^*o     cr— *o     crj^— <     -o-x*-*     r-f*-fn     inj^o     sDvO-/^  ror^r*     --40^^^     ogrsjrg 

t— Htv^o     c^  I  o     r-fMO     ^mo     -O-oo     f*>     o     ^-*ro— 1  oD'r^o     V'O^^^     — *— «^h 

iifs^^^v     p-       •     ft^       •     rsii»     o       •     fM       •     -^ro*  m^-<»     m^H»     -tpo« 

ti^^lo<MOf^oo     o^orsior^o  nJ-io^oioojo 

ii_>ir~-ir-  _j|_4  CO  -<  -^ir-l-o  ui 

lirg— ■— 'rgfM-JC\J(M-J-<  I— 

on  'J 

-HM»'  ••  ••  ••  ••  ••  "♦  ••  ••  ••  ••  3 

iicoo     com     oco     oox     ooi^     ooct-     000     co-H    00— •    00m     oorg 

^"  H  rv  i^f^     'TsffNi     >r<7*i/^     OGf^     r^iA-o     ^a^>r     '>J>1 — '     i/^o>i"     — tcoo     'r>r20     f^rvo  t— 

3ll,^_0      CO      O      -T      O      01^— '      rorn-<      —  lO      f"><M— <      .0  10      »3--<— •      r"_jo      <M      O  OOOO 
Q-ii,^l.>>j       .r-       .-oi'^J-       'cvj       .r-       "J-       •J3l»oo       •-<       •►-••• 

M^or^o^-o^o^^o<t)0'^0'.^or*o.oo»AO        vooo 

iirvji-^  — ■  (Mirg  — '|(M  rMi-ni-J  CT>  li. 

II  -•  O 

o-  II •- 

II  00— «  OO^r^  OOC3  CO>r  00m  0003  OOtr\  OOC7*  OOO^  dO^^  oor^  z 
^ii.TfOO  r.-..<>r.-  — <.r'^  ^^^.o  i^j^r^j  Lr>oo>  ^-*mo  r-f^r-  croo  cofxi— <  roinm  o 
^  K  r — to  vC'-'O  tv^o  >r— 'O  o  o  o^^o  roosj^  tn.-'O  rvjro— <  ^-«  I  o  ir»oo  Q. 
.Yii'-«i*^i*r.-i*.o       '^r       •:Nj|»r^       •sri^.oi'co       •oi« 

,i^or~-or-o— <o— 'OOO'-'o— 'Oi~-oooir\o 

lltMl— 'I— 'IfSI  (N  -J|(M  (NJI— <l--^IC7-l— I 

II  ^  < 

II  3 

CO  It..  ..  ..  ..  ..  ••  ..  ••  ••  ••  ••  1-000 

II  0  0>3-      00^      OOfNi      000      00>J-      OOCO      00.3"      C^tD^      COro      OOU>      OC^O  O 

2ii>J"f^— '     O^fco     (\jr~ir»     r\iccr»^     m--*o     -Of^m     cnj^^o     incr^r     r'^Of^     OvOm     o^^^^o  < 
3 II  cc  I  o     o— <c     ofvj— '     t\;  I  o     o     o     -^  I  c     f\j-HO     010     >.->io     ^     O     '-<     o 
Qiii— •       .pvji.r-       .>o       "^       ..^       .r-       "^r       'O       *ao       .^-i       • 

,i^of~-or-c-JO— •oojO'-'O-'Or-oooioos 

lirvil— '1^  (NICM  ^^|(N  (Nil— *!'-«  O  aOUMXl 

I,                                                                                                                                              -<  -im     z 

II  _1          c 

r- <         z 

II  OOC      OOvT      OOf*^      OO-'N      OOf*^      OOX      OC^O^      OOfNj      00-4-      0000      OOf*> 

Ziio— 'Cr     ^.Cf**     cDf^r^     r^r-m     >-org     or^r^     r-G^r^     r^f^r-     sr^rtcc     inin»f     u^>-0  OOO 

OHOrvjo    r^io     .J-— »o    c<\    o     o^io    '"H    c     >rm— I    f^ro— <     >r^o     >rfM— *    (nj     o  000 

a:ii_i.,-\;       .r--       •<>       .m       ..-nj       •(—       .j-i.-ci.x       .— <       •  ojr\o 

ii^or-cf^o^o— '0030— <o--<or-o>ooir\o  ... 

iirvji^i— ■            t\j             ^1—"            t\j             t^g|— ii— <            c^  00— • 

II  — ' 

II  ^cccx:a^ 


rioorsj     CO^^     OOr-     OO'^o     OOco  oom     OOnO     OOi/*     ooro     00^     oox 

311— <vOn^     Nr>i"X     m.-Nio    .-Njpsjn    r^-^^cr*  — *XN^     fNi>j'.rt     o>J"nO     ct^o— •     xxrvj    ror^f^J 

I^  II  o."Nj^     o— *0     rM— 10     >J"— <o     fNjf\,o  ro     o     -J-r^— I     >o— 'O     rof^4— ^     ir*r<>pg     r^ino 
an— 1|.;^       .r^i.o       .-r       ..m       .r-       .~rl«oi.a)       •*-<       • 

II— <0."^0r—       O— 'O— 'O  X       O— 10— '0-~       0-00i/>0 

lltNJI— .                  — "ItM                  (SJ  rJ                  (Nl                  (Ml— 'I—"                  J- 

;/^||.•             ••             ••             ••             ••  ••             ••             ••             ••             ••             •• 

II  oo-r    00-3-     ooT-     oo(^     000  000     ooj>     oof—     oor-    ooirv    000 

2  II  C^XX      sr.i3f*^      Xf^r*^      fOr'^--*      r-'X^t^  rn      O      P^CM^      X-OCNJ      OC*0      — «— <0      CrMO 
O II  -o— <o     r-  1  o     tM  I  o     "^     o     — <— 10  ."M     o     <rrr,—>     o  1  c     ~r— '— •     ^— 40     m— lO 

i-^ll— 'I'fNi         .1^         •       -O         •      ^         •  r^         .r-         .J-         .-CI.X         .—I         • 

II— <or-or-0— 'O— <oao— 'O— 'Or-OOOi^O 

llpgl— ■!— -IIM                  <\l  -^                  <M                  .-NJl— 'l-^                  J- 

II  — ' 

^11..          ..          ..          ..          ••  ..          ..          ..          ••          ..          .. 

IIOO^      QC-T      corn      COO      00>r  OCr\J      OO^v;      OOi-"v      OO.^      OOO      OOO 

^  II  r-OC"      r\j "  C      0>Cr^     ;7'-^^/^     ir»r*>^^  <T.C>r      .'Ni.fC      C  ^  <3      .c^x      xxo     t^— *o 

3  II  -CMO       C— '— •      CV  I  C       — •— "O      C       O  ^r-NI-^      ^^tvj       O— 'O      r^^y—i      vTr^j— <      —lie 

'j;ii— 'I'fN.i"''-       -oi'^r       •  (\i       •     r~       .v-j-i.ji.x       .— .       . 
ii^cr^-or-o^o^oxo— *o^or^oooir«o 

IICMI— ■!— 'ICM|(^J  -^                  i>4                  (NJI— il— '                   Tl 

II  -* 


rn  11    .   . 
11  OC 

/-^ 

oc-c 

ceo- 

COO 

CO  J- 

OOL.•^ 

oc<t 

CCfM 

CC(M 

OCC^ 

COX 

< 

oi 

3r  II  o  — 

,^ 

~r -rc' 

^r^-*^. 

r<r 

— ' 

—*— 'O 

r%— « 

•-* 

—  rTN^ 

.■MtM 

c 

.t^^TiM 

inofi 

nT  ■ 

<,<o 

> 

^_- 

3  II  0.>.0 

— <r^  — 

.J-        c 

C  rv. 

-^ 

C  1  o 

OCSI 

,-A 

oirtM 

'^(M 

^H 

J^   1 

o 

.-^-^c 

l"**. 

-•o 

UJ 

c< 

"'  1)  -•  1 

• 

f^        • 

r^        • 

-T    1 

. 

-T           . 

tM    1 

• 

1^      •* 

<■    1 

. 

O 

. 

X        ♦ 

—J 

. 

o 

O 

II  -• 

o 

r-     o 

r~     O 

—* 

o 

-•       O 

X 

o 

-"     o 

•~K 

o 

(*-- 

o 

~o    o 

^ 

o 

II  f\J 

II 
tM  II    •  • 

11  oo 

1 

""• 

"^ 

r\j 

1 

tN         1 

■^ 

1 

tM 

i-vj 

1 

'"* 

1 

^^ 

o 

'^ 

oo-c 

oc-c 

o-; 

NJ 

ccr- 

OC 

^ 

OCiTi 

CC 

■s- 

CC 

.^ 

CO  — 

c'( 

o  o 

z  11  cr- 

r^ 

.•N4X.J- 

C>.-irM 

CO 

,7* 

sJ-CC*^ 

xinro 

r-c-tM 

tMtMO^ 

.x-r-o 

^^fM 

a-' 

-4m 

Z)  11  X  1 

O 

•^  1  c 

r'S  1  C 

--\<MO 

c-  1  O 

^»•t^ 

l*-l 

U->>I-(M 

0-- 

'Cj 

(Mro 

tM 

i^ioro 

xr-o 

a:  11  — 

t\. 

r^       • 

■C 

. 

rn        . 

tsi 

. 

r~      .ii 

.I-   1 

. 

O   1 

•-» 

■  X         .« 

■  —t 

. 

II  -■ 

O 

f^      o 

r-     o 

-^ 

o 

-"      O 

m 

o 

^    o 

f-A 

o 

r- 

O 

o    o 

tn 

o 

11  rvj 

1 

— '      1 

—       1 

<M 

(M        1 

'^ 

(M 

(M 

1 

'^ 

' 

'* 

1^ 

.  .  . 

ir>o 

II 

ooooo 

— <  II    .  . 

*  • 

•   • 

.     • 

•    . 

.   I 

.     ■ 

•     ■ 

•  • 

.    • 

* 

• 

O-i-i 

0(M 

11  oo-r 

O  C-J* 

CC:.-^ 

acra 

oc-r 

COIM 

CC  c 

occ- 

c  c 

-c 

OOO 

o 

^'T' 

OC— 4 

.    • 

7"  11  -rm 

—4 

f\j<NJ  J3 

ovir-c- 

ro-... 

r^ 

m-.o 

i^om 

inr-r^ 

r-r-r- 

(M^- 

c- 

nnirn 

XGO 

-4r>j  — 

oo 

13  II  X  1 

O 

a--iO 

r-'C 

— i^H 

lO 

c     o 

-»  1 

o 

(M  — o 

in-io 

^-c 

lO 

Nj-tM— 1 

fM 

-"O 

—*.^ 

.%j 

f*-       • 

sO     1 

* 

sr       • 

.%, 

r-       • 

>r  1 

. 

•O  1 

. 

OC 

^^ 

• 

ir-in 

II  — « 

-3 

>-     o 

r^     o 

•~* 

(.3 

-"      o 

X 

C) 

— <     o 

o 

r^ 

o 

O       O 

li". 

o 

crtj^ 

II 

1 

-* 

'"' 

rsi 

1 

.-M 

-" 

1 

(M 

<M 

1 

■-' 

1 

•" 

X, 

-4-4 

>-  II     • 

. 

, 

. 

, 

. 

. 

, 

. 

^^_ 

O  II  o 

c 

o 

O 

O 

o 

C 

O 

o 

o 

O 

oo 

:s  iir- 

c 

v.-^ 

O 

rsi 

n 

X 

.r 

t^ 

o 

X 

:i3 

:v 

II  X 

X 

-*N 

r^ 

O 

fM 

o 

i~- 

u". 

f\l 

—4 

c 

a.  II  -■ 

:Ni 

r- 

<; 

^r 

tM 

p^ 

vT 

O 

a; 

•-* 

li-i-a: 

_i 

UJ  II  — 1 

r^ 

r- 

— • 

— « 

X 

—4 

— i 

'^ 

o 

in 

luCq: 

_i 

-jr  II  <M 

-^ 

-^ 

iM 

i-vj 

—4 

tM 

IM 

— ^ 

—4 

7- 

,-lCi-Xl 

< 

II 

1- 

h~ 

\-~ 

^— 

^ 

^ 

h— 

\-~ 

1- 

^ 

—4 

1- 

•  II 

^* 

~y 

7 

."^ 

7* 

7 

•^ 

2r 

7- 

z 

1— ^— h— 

j:x 

C  II  o- 

lit 

f~        JU 

i^     -jj 

o 

UJ 

O-       LU 

— < 

O       UJ 

-0 

LU 

O 

LU 

—4         UJ 

caco< 

Z  II  <Oa:i_) 

u-iaro 

ci)f<:o 

flQ^U 

^CL^ 

vOuCO 

orzo 

J>a:o 

-■ao 

r-oco 

t-1-i-Q.s: 

II  xc 

si-c: 

I^O 

~rc 

— *o 

cc 

■i-CI 

ino 

inc 

-<o 

a  II  oa 

J. 

CC^I/  Cl. 

CaCci 

crcif 

OC 

oao: 

(Mo'tr 

O-LiCt 

ootai: 

octroi: 

Otitrt: 

i-eri- 

<  11  t^a 

Li. 

(MCl'UJ 

mrs'-:- 

r^cT 

'U 

C  -J.  IJ 

(*>r^ 

'  XI 

iriuroj 

cc>;iu 

oty 

UJ 

OQ"-U 

<.■; 

a.^ 

O  11  (M- 

.0. 

X^=. 

X  -.^ 

rs.-1-T. 

3-ixi:. 

Xa-il. 

.j-tja. 

(T-OjO. 

OJ^X 

O-LtO. 

j: 

UJO 

„ 

^. 

tj'a 

II  — * 

r.j 

.■^. 

.^ 

•r^ 

-0 

r- 

'-^ 

o> 

O 

.'.^■ 

_ii.i. 

II 

^■4 

1- 

<a. 

Bttl.  654 


34  Bulletin  654 — American  Railway  Engineering  Association 


II  ••       ••       ••       ••       ••       ••       ••       ••       ••       «• 

»- II 00-*  oo^  oor-  oofo  oof^  ooo"  oom  ooo-  00.0  00<X3 

O II  rg(\jr**  *r»OfO  *^vJ">*-  >J'nO'-^  oocoin  rgoo^H  rvjrsjr-  >tf-sO>r  coco>j-  o>j-m 

►-iir^r-O  t-*'0'^  *t«0-^  s*"^^0  tAcno  nO^O  ^corsj  ro>j-.-i  fsjoo  •-••^rg 

no       •  >otM  •  o-<  •  in  I    •  .-<       •  CT>  I    •  ^-^  •  rr,^  •  —i-^  .  rorg  • 

no    o  •-•lo  -*    o  •*    o  ^o    o  m    o  gj    o  ^-lo  *    o  -f  \  o 

vfl            11  o  oi-^  — •i«o  CIO  o>     \  m  o>l  i/> 

II  -<  fM  -H  -4  ru  (- 

O  II  o 

O           .-4||«»             ••             ••  ••  ••  ••  ••  ••             ••  ••  ..           2 

z            II 000  ooco  000    000  ooiNj    000  oo-^    0000    oorg  oor-    ooin 

^  II 000  oooro  cooir*     o     o  o-^o     cooo  o>ri-»     ocsjrvj     ocoo  cooao     c\jao^^  »— 

J-         :d  11  r-4^,^  >0(M'4  roif\sr     ir>     o  (»ic>jm     cd-^w  ^— <rg     -jroro     ,i-ro-<  o>tiri     o-^O  OOOO 

VI        or  11  o      •  -J  I    •  ->      •«>r      •  .0      •■iK»i  I    •  -o      •»h- I    •■tt^i-      •  -r  1    •«ct>      .  i-  •  •  t 

l"  IIOOOO'-"0-^0<OOCT>0>000>OrOOO>OI~-0  rOrOO 

►-ii-H(M|-H-<  I  leg  I'-iu.rg 

II  ^  o 

11 
c  n   '  '  ••         ••         ••         ••         ••         ••  ••         ••         ••         .•        I- 

II 000     OOCO     000     00^     000     ootn     oo(M     oo»^     oor-     00^^     oo<m     z 
2  (I  >o^*r     oooco     oooa^     >j-f\io     o^a*     ococo     o^>o     >ococo     oosr— *     f\jvj-r^     o^r-o     o 
Z)  It  c^  10     inrrt^H     cT'-^o     nj--h^     o  io     o  I  o     inrvjm     sO^^r-*     a»  I  o    oir.in     or^o     a. 
in         ociia>       •— "l»o       •■4-|«'0       'tn       •<)       •»r-       ^ro       •~Ti»«a>i» 
r^  HO^ooO'-^O'^O'OooO'OOO^OfOocT^or-o 

o<  i|.|rg|-i  -"I  I  I  (Ml  l-Hi./ 

^11  ^  < 

II  3 

••         a>ll»»  ••  ••  ••  ••  ••  ••  ••  .♦  •»  ••         i-rorflo 

o  n  000     0000     oo-o     000     oorg     ooro     ooiM     ooin     oo-j-     oo>o     oo-o     org 

rg         2il«4"^^     OXQO     ^^ro     ooco>o     vj-cor-     (M'OsO     -ootn     odoo     >r(NJCT*     og^j-r^     ogrgco     < 

O II  o     o     inrO'^     00  I  o     ~t  \  o     CP'-'fs)     ty  1  o     mm  j-     ivjrgcM     (\j(\io     o-o-o     r-oo 
>-         ctiio       ••-'i«o       •-!■       •ini««m       "gj       .*r^|.<t-sj-       .roi«»cO'-'« 

<  Il000o^o^^og^oo0'00c^orooc^o^-I03 

3;            lit-"  rgi— "i-^i              I              I                            log  |'-4|  ooifMLi 

n  ^  _im     z 

II  _i         O 

uj   r^ii»«    ••    ••  ••  ••    ••    ••    ••    ••  ••  ••  <    z 

t-             II 000  oor-  00-0  oorg  000     oofo     oorg     oo>o     oorg  oom     ooir\ 

<  ;t  » pgrgrg  coo^  rg^rg  o>om  co>3->0     rgvOsC     -J-oorg     s3-nJ->3-      g5>ro  O^^-O     occ— <  OOO 
C         3  tl  ^^^-^,-t  roinrg  o^^^^  i/>  I  o  o  I  o     O  I  O     mrg^l-     pgogfsj     rgrg-4  m  |  o     m<-"0  OOO 

oc  II  o  •  —"I  •■»•-•  •  >r  •  -o  .  ro  •  ~o  •■»f-i  •if-i-  .  ,}•  .  cf  t  •  rgioo 
iioooo-<o-*o-ooo>o-ooa>Ofnooot-o  «•• 
111-'  rg|^  -<l  I  I  |rg  i_ji  OO"-" 

II  ^ 

II  y-cerf.ee 

sO< p- -.;;■).'. !j 

H  000     ooa>     OON    oorg     000     000     otD--     oo.-m     tio-r     oo7~     c:)Ocr::     i_:>:.-:' 
Z  It  rgrgrg     sOrg:n      o^x>^     rg^j-rg     ocorg     ccoo     .xr\j.'o     o  wJO     sj-rMC^     o-oo     o-x-^     CCt^w 
n  n -'•-"•-I     r-rHO     o-*'-'     •J-^'-'     rg     .-1     .x-j— >     m.-4-.     ,j-  10     rgrgo     •3--1— •     TjVho 
aciio      .^|.-^      •>)-i»g3       '     m  \    t     ^      •!--      •»!■       •-4-i«(7<      • 
lloooo^o-<o•ooJ■o•ooc^o^^loc^o^-o 
lI'Hrgi.-tr-ii  1  irg  i-^ui 

II  ^  I- 

II  O 

ir\ii»«  ••  ••  ••  ••  ••  ••  «•  •«■         ••  .•        3 

II  000     0000     oo-o    oorg    000     00-^    00— '    oor-     0000    00-0    000 

Z  II  <0-00     ^J•-3■'-^     rg-j-fi     rgotn     -j-corg     orgrg     oorgco     cooo     rgorg     o-ooo     ~ooo-r 

Olio     o     org^^     c^o^oool»-«oo     m^^— *     ,-jrom     mm^     •-*>i-«d-     rg^o     o  • 

aciio      --^I'O      'nJ-      "O      '^r      •>c      •    r~i    »^<r      •>ri«»a'i»o  o 

M  0000-^0— 'Ogjoo<o-ooo>omooor-Or-i  rg 

llr-irgi^^  I  irg  1^1  rsi 

n  ^1-0 

II  I  -< 

■* ♦ 1 

II 000     ooo>     0000     ooo<     oOr-i     000     00— <     oorg     ooa>     00m     ooir> 
Z  II  ^o^oo     Offico     Orgo^     rgvOfO     ^rgoo     *4*'Or-     ^oo^-     cooo     co>tin     0»0^     orgro     2 
3110     O     i^.-io     ■-irg-H     i^i-t—i     rg-H^     ^,-1^     <-rfrg     m-J-<     00^0     ir\  I  O     —•-TO     •-< 
a:  no      .-<|.— 1      .sj-      •    ~o      •>!•      ••o      •*r-i«mi«.r      »    o      • 

II  0000^0— "O-OOO^OsOOO^OrOOO^OCOOZ  £t 

3n-<rg|.-(r-i  |rg|  i^Ool' 

•■II  — I  "-•  UJ 

KTI  u  .  h- 

»         roil..  ••  ••  ••  ••  ••  •!  ••  ••  ••  ••  <  1/) 

lu  M  000    oco>     000    oo-i-    oorg    oo-j    oorg    corg    ooco    oo--"    00^  •-•  «/i 

-        rriigagjo     ocob     cooi^     rj-rm    cro^-     gjrgrg     o«Tg2     xoc     orgc     -co-'     •otsi-o  >  o 

Z         Z>  u  —"^^     h-^o     i-irorg     in  |  o     d-^rg     c  I  o     ifirgm     rr>— 1^     o  I  O     l--rgrg     str-c  uj  aL 

I  ocno        .-i|.-i        .».*■        .>o        •«rri        •>0        •*r-l«-3-        •-!•        '^O        'Q  O 

—  IIOOOO— •0-HO-000»0>000>OrOOO<OCOO 
lull— irgi— I— 1|  I  |rg|  — i 

>  II  r-l 

o  n 

X        rgii 

t/i  nooo     OOX     OC03     oorg     000     co-i     oorg     ooro     oosT     oorg     oom 

—  Z  n  rgrgrg     sr>r-^     orgc     o-J-rg     vO^gj     .orgrg     ^corg     .1--J--1-     .l-coci     rgj-.*-     rgcorg 
i/i         13  H  -^-^-H     -org-^     ^rg— <     r^— <^     — •     o     a>  I  o     iTirg-i-     m— i-h     o<  I  o     m  i  o     orgo 

ctno      .— 1|.— I      .*       •-o       .n^      •.o       •*r-l»m      '-^       "O      • 

—  noooo^o-<o<30o>o-oco<omocroooo 
_in-<rg|-<-H  1  irgj  l-< 

_i     11  ^      ,  ,  .00 

3     n  ooOr-»o 

Q.    -HH«»    ••    ••    ••    ••    ••    ••    ••    ••    ••    ••   o-j--oorg 

—  nooo    oocr    ooco    oocr    000    oom    coo    oo-r     000    co— •    oor-     ■j--<rg  •  • 
Q-         Z  » corgrg     rg<or^     *org-^     cocoo     ocorg     g^ojco     ooosrg     rg-o-0     rg     o     «00'^     00*0^     f-^O—iOO 

r>  n  c>  I  o     r--io     coio     -J-IO     rg     —1     o     o     — il— 1     ro-^^     o     O     rorgrj     -tmo     CO  I.  I 
cine      •-'l»o      •■!•       •     -a       •     <■       '     -o       •i--l«-f       •-ri»')KJ>i«     f-r- 
n  ncooO'-O'^ogjoco-oocoroocor-o     — •-• 

UJ  nirg|-^i-<l  1  Irg  I'^l      -<-• 

on  -< 

o  H 

oi-ii*  •  •  •  •  •  •  •  •  •  •►-»- 

owo  o  o  o  o  o  o  o  o  o  o  00 

3110             CO             OQ             -O             rg             CO             .0             co             <M             <0             <r  3E^3C 

iiococoir\-<a>rg.^oir»h-  O 

U.110            — '            o            •*"            -o            m            o            r-            ^r            >r            c  u.y-ce     -j 

i/)ujiio           o           — I           — <           >o           a>           -o           c           m           o>           r-  ujooc    _i 

i/)Q^II-<rg-j-<                                                                              rg                             -<  oCSiMJ     < 

•  nz           z           z           z           z  z           z           z           z           z                  t-t-i-zx 

I  onr-oi-i-ujmujr-ujrgujstiurgujrouj— <uJOUJ  oaOO< 

Z  Z  n --oco  — 'cto  Ooco  rgoco  -<c»:o  rjoco  rgci:o  r-oco  '^ocu  -^oco                    t-t-t-a.S 

c            ncoc  >oo  gjo  gjc  oa  — 'O  -oo  rgc  r-o  mo  ' 

•->  oc  n  — loca:  mococ  ^ococ  -hococ  moto:  rooco:  inocc^:  rgcsroc  •tac^  roococ     >-qc>- 

H-  <inr-o:uj  rgpru  oorm  ooroi  rgauj  mofuj  rgo^uj  moruj  •rocoi  inojuj     ootz 

o  OHr-ujCL  olucl  ojjo.  oujo.  mcjo.  oujcl  imuoi.  oi.ua.  cljo.  oujcl     scujo 

VU  II 

a.  n  »-Ce£ 

•-1  ii-jrgm-t  u^-o^-  00  COC  -juj 

O  II  -4  »-<&. 


Tests  of  Coupled-in-Motion  Weighing 35 


II   •  • 

ooo 

OOf^J 

OOCO 

ooirv 

OOO 

oom 

OOfCi 

ooin 

oom 

inirvo 

fMCO^-< 

o-a--i 

inj>-< 

0>-"(N 

f^  1  o 

rOfvj— 1 

^--rf 

■OINIO 

inrgO 

cr-t'^ 

cr^O 

<MM    • 

00          • 

CO   1      • 

r~(vj  • 

0^   1  O 

fO   1  O 

-r    o 

O     o 

in  1  o 

irv     o 

-1       1 

00         1 

CO 

m      1 

cr      1 

O        1 

•-♦ 

O  II 

<M 

rj 

'^ 

(M 

■"* 

(M 

(M 

o 

OOCO 

OOCO 

oo-< 

oo-o 

OOOO 

OOro 

00(M 

OOfM 

mo- J- 

OfNjir\ 

r-r-oo 

•j-o-1- 

(M<ro 

co^^^ 

o<     o 

O-'O 

CO'-'O 

l^-HO 

cr-l-tM 

OfNJ^^ 

ro  1     • 

-1-      • 

f-4            • 

ir\  1    • 

in  1    . 

o      •■»o      • 

-1     O 

CO      O 

CO      o 

m     o 

CT-       O 

O      O 

-•    o 

CT-      O 

II -<     1 

<M 

^      1 

(VJ       1 

(M 

cvj 

H 
0-  II     •    • 

OOO 

OOnT 

OOIM 

oor- 

OOO 

OOCNJ 

OOin 

OOO 

OOO 

vOOir> 

CO^f*^ 

(j'-i-i- 

-iro  j3 

m-io 

OC0I-- 

O-iO 

r-  1  o 

CT--IO 

0---IO 

^0(^J-^ 

•o      • 

(7-  1     « 

>r  1    • 

>r       • 

o 

^  1     • 

o 

o    o 

-<    o 

CO      o 

03       O 

ro     o 

o>     O 

o    o 

^    o 

ll'-i       1 

(>j 

r-J       1 

-1      1 

^         1 

(M 

— '       1 

<M         1 

<vj 

'^ 

II 

CO  II     •    • 

3 

^ 

^  , 

,    , 

,    , 

,    » 

*     c 

«    • 

•    • 

•    • 

t-OOO 

OOO 

00(J> 

OO^ 

OOfO 

oorsi 

OOCO 

ooin 

OO-t 

o^ 

ooro 

oooo 

■OINJ-I 

rnu-v>0 

ocoo- 

inoo 

-"r'>o< 

Of<-l-. 

O-iO 

OOM-^ 

O-IO 

OrO'-^ 

-Or-IO 

o>>l---i 

nI-      o 

~o  1     • 

a>  1    • 

J-  1    • 

irv       • 

r-4              • 

irv  1     • 

in  1    . 

•o       • 

-H       o 

X>       O 

03       O 

ro     o 

cr     O 

o     o 

^    o 

eg 

^      1 

rvj      1 

CM 

i-H 

II 

_jm     z 

_)         o 

^   , 

,  . 

,   , 

«   » 

,   . 

•  • 

•   • 

•    • 

•     • 

•   • 

<           2 

OOfNJ 

002D 

OOO 

OOCO 

oo-r 

OO-O 

OOOO 

OOCvJ 

OOfVJ 

OO-i 

O-J-rO 

sJ-OO 

a-^o 

o-inr- 

-j-o-3- 

CT'-'O 

<}-.\l-> 

OCM-" 

CO      o 

CO-'O 

r-wo 

in     o 

O.NI'-' 

in  1    . 

O^  1     • 

^         • 

irv       • 

o 

^  1    . 

in  1     . 

o 

00       O 

CO      o 

CO      o 

o     o 

o     O 

->    o 

•    •    • 

II  —•      1 

rsj      1 

fM         1 

>~^ 

CM 

-H         1 

CM        1 

(NJ 

vO    11       •      • 

l-0£:QiOt 

oo-j- 

00li^ 

OOI^ 

OOfVJ 

oom 

OOO 

ooo 

OOM 

jraiujiu 

rric-o- 

-JiTvlA 

-OOlTi 

in->o 

om^ 

O^rrNj 

in -"in 

r-o-co 

O^CM 

3  11  CPvOro 

-J-IN-i 

Oro^ 

O'-'O 

CO      o 

O-iO 

COfNJ^ 

0--1O 

00  (<\-" 

a  II  m  1    • 

«  -O 

a<  1    . 

^  1    • 

«i-       • 

'-'      • 

.A   1      • 

in       • 

->     I     'H 


in  11    •  • 
II  OOfM 

oor-- 

OO.M 

cco- 

ooin 

oo-< 

oo  J- 

OOi>J 

ooo» 

ooo 

OOIM 

3. 

:z  11  fNjoo 

OOsJ-O 

-iinfM 

^»^^o^- 

0-4-f~ 

oiMin 

COOf^ 

(Mnr- 

cr— IOC 

CO  Of^ 

^Of»> 

3  II  fNJf*!^^ 

CM -HO 

o     O 

O0rr,-H 

r--.o 

r — lo 

in-TfM 

CT--IO 

00  J--" 

fM  1   O 

inoo 

o 

• 

Oi   II  >t    1       • 

o       • 

o 

(^   1     • 

-r  1    • 

o  1    • 

•J-.  1    •  ■«•  in       • 

O 

o       • 

^  1    • 

O 

o 

II  CO     o 

o    o 

fM       O 

03        O 

00      o 

ro     o 

a-     o 

o    o 

-J     o 

CT-      O 

fM      O 

'^ 

CO 

II -1     1 

II 

II 

IM 

(M 

-•         1 

->      1 

fM         1 

--1      1 

fM 

fM 

^       1 

O       1 
fM 

! 

fM 

.*  II  •  • 

11  OOnj 

OOOO 

ooc 

OOfM 

ooa- 

coc^ 

ooo- 

OO-I 

ooin 

OO-H 

OOl^ 

' 

Z  II  f\)00 

ofMin 

<l-fMO 

^fMOO 

o>r<M 

fMO0< 

c-inrcj 

^-r-ro 

OfMin 

OfMO 

OOO 

z 

3  M  .■^J^f^— 1 

fM-HO 

r-fM^ 

O'nfM 

OfM-- 

^<r '-' 

in~3-fM 

intM-H 

o-<o 

-r-iO 

—»—«--« 

*~' 

a.  11  ^  1     • 

o       • 

o  1    • 

ro  1     •■)) 

•  -r  1    • 

O  I     • 

S\\      •  •»■  vA   1      • 

o      • 

o       • 

roIM    • 

II  00      o 

o     o 

-■     o 

CO       O 

CO      o 

rr,      o 

o>     o 

O     o 

-1      O 

(7-      o 

fM  1  O 

z 

DC 

II  -<      1 

<M 

<M         1 

-■      1 

■^      1 

fM         1 

-1     1 

fM         1 

CM 

<— t 

O        1 

o 

a. 

II 

rj 

UJ 

1- 

r<1  II    •    • 

.  . 

.     . 

.   . 

.  . 

.     . 

•  • 

•     • 

•     • 

•    • 

♦    • 

< 

1/1 

II  oca* 

oocr 

COrO 

OOC- 

ooo 

ooin 

COPfl 

oo<j- 

oocr 

ooo 

oom 

*-• 

Irt 

2"  11  -■— iin 

CC-CfM 

COO 

c  o>r 

-■■Of- 

iTC-fM 

(NJfMO 

rt^-HO 

OCCfM 

r-rno 

r-roo 

> 

o 

:;  11  vr-jo 

O  1  o 

or^-i 

r->j-fM 

r--io 

innj-^ 

r-rOr-l 

03    1  O 

r^r>j--* 

nT-iO 

coroo 

UJ 

a: 

a  11  ^  1    • 

o       • 

O   1     • 

f^,  1    •«<  \    • 

O  1     • 

in  1    • 

in       • 

o       • 

o 

f~,-'  • 

c 

o 

11  =0      o 

o    o 

-J      o 

00      o 

CO      o 

m     o 

(T      o 

o    o 

-H         O 

(T-      O 

fM  1  O 

n  '-*      1 

nj      1 

M       1 

--H     1 

-1      1 

fM        1 

-1      1 

Aj      1 

fM 

-A 

O        1 

II 
II 

fM 

(SJ  II     •    • 

11  ooo 

OOfM 

OC^ 

oco 

ooo 

OO-H 

ocr- 

OOOO 

oo<r 

00-* 

oocr 

2-  II  '^  r-  o 

r-r-aj 

CT-i^r^ 

fMNj-m 

-ir--^ 

rOincM 

—.(^—1 

OfMin 

-j-oo 

fMCO  J- 

oo-< 

-_3  II  — im(M 

0--HO 

(~--<0 

crfM--« 

-H(M-< 

o>     o 

COfMi-H 

0,^0 

-^Off^ 

OO^ffM 

o-ro 

Qi  11  sT  1    •Si-  m  1    • 

cr  1    • 

ro  1     . 

in        • 

o       • 

in  1    • 

ir\   ■  . 

r^      '*o      '-ttin      • 

II  cc     c 

o     o 

-.      o 

00      O 

CO      o 

fO     o 

cr     o 

o     o 

-*    o 

cr     o 

fM      o 

II  —4          1 

<M       1 

fM         1 

•-*       1 

•-4 

IM 

>~-4           1 

fM 

<M 

f-* 

o 

II 

fM 

•  •  "ino 

It 

OOOfMO 

-4 II    •  • 

»    * 

•     • 

•   « 

•   • 

•    « 

•     • 

•  • 

«     • 

•  • 

•    • 

COOOfM 

IIOCO 

oorf^ 

OOr" 

OOOO 

COI^ 

coc 

co-« 

OOf> 

oc-1- 

coo- 

COtM 

0=5fM 

•  • 

Z  II  o  o  -J- 

— 1C10 

o-ro 

OOO 

— ■r-.-<i 

CO     a 

OfMO 

OfMO 

cocc; 

f>c--*- 

inin(*\ 

cMoinoo 

3   11  (N,  t\J  -1 

O-'O 

-.--o 

O-IM-l 

o>     o 

00      o 

-H-IO 

00      O 

CC-4--" 

OOsTIM 

OOOO 

in^  1 

1 

or  11  -}■  1    • 

O  1      • 

o       • 

fO    1      • 

~j-       • 

o      • 

o       • 

m       • 

o      • 

o      • » in      • 

fMtM 

11  00      o 

O     o 

CM     o 

CO      O 

CO      o 

ro    o 

o    o 

o     o 

-■    o 

o    o 

fM      O 

Cjo 

II  -^      1 

IM         1 

fM 

-1     1 

-' 

rg 

^ 

fM 

IM 

-* 

o 

IM 

IM(N 

II 
t-  II   • 

^ 

. 

^ 

, 

, 

, 

, 

, 

, 

. 

^-^- 

OHO 

o 

o 

o 

o 

o 

o 

o 

o 

o 

o 

ou 

3  II  fM 

»f 

o 

o 

<r 

CO 

^ 

>>• 

CO 

-J- 

o 

33 

3 

H  in 

t> 

00 

<D 

o 

CD 

fo 

fM 

O 

u.  II  >r 

o 

o> 

~r 

-r 

o 

o 

in 

•o 

o 

in 

u-i-oc 

-J 

UJ  II  oo 

o 

00 

00 

fo 

o 

o 

«-4 

cr 

CM 

ujOoc 

-J 

cc  II  '^ 

<M 

fM 

,^ 

m^ 

(M 

»H 

fM 

(M 

»-4 

O 

ocxai 

<. 

II            H- 

H- 

k- 

t- 

V- 

t- 

V- 

t- 

t- 

t- 

fSl 

1 

h- 

•  II         ^ 

^ 

z 

T- 

TT. 

■z 

■z 

z 

z 

l-t-l-ZX 

C  II  >i-      iU 

00       UJ 

•-<       UJ 

o     oi 

O       UJ 

(M      ID 

*-*       UJ 

^      UJ 

CO    UJ 

O      UJ 

ocoo< 

Z  »  <tC^^J 

O-DCO 

OQiO 

f~e£0 

OC^^J 

r-OCO 

^f5:o 

fMato 

o-oro 

.roto 

1-i-i-Q.z: 

Hino 

fMC 

^o 

r-C 

o-c 

crc 

CMC 

oc 

-"O 

^o 

a:  11  r- oca 

t~cr-a. 

ooocct 

o-oroc 

r~-c:oc 

•-•occc 

r-aoc 

r-cKc^ 

IMOflX 

njotoc 

l-Of  ►- 

<?  n  ocai 

COCLU 

OOtlf  UJ 

XOCUJ 

oauj 

(Mfi:uj 

onruj 

OSOCUJ 

riofuj 

fOO<UJ 

oa.T. 

O  IICUJQ. 

11 

OUJO. 

OJJQ. 

ouja 

OUJCL 

^OJO. 

ouJOk 

oxjo. 

CLua 

OliJ3. 

^UJO 
►-l50f 

II 

'>■ 

r^ 

^ 

n 

•^ 

r- 

Oi 

0- 

O 

~_IJJ 

36  Bulletin  654 — American  Railway  Engineering  Association 


w    •   • 

OOfsJ 

OOrr\ 

00(VI 

ooin 

oom 

oo-o 

OOfl 

OOfvJ 

oo-r 

O  II  oo* 

0>-^(»l 

eritf\r- 

00  (Mr- 

f-r-fo 

OOr" 

uMr\o 

t-r — 1 

,o>ro 

•j--l-ir\ 

t-  II  ^mo 

->C\lO 

•oivjo 

C>00^ 

oo- 

tvJOO 

!*<-•-• 

-i-iO 

0-  1  o 

roo--H 

II «  1    • 

CO  1     . 

1—1^4     • 

KMM    • 

oo-"  • 

O-  1     • 

mcM  • 

lf\       • 

m      , 

c-«  • 

M  m    o 

o    o 

r-    o 

m  1  o 

<M      o 

-0      O 

o-     o 

-O      O 

0-      o 

in     o 

II  <o      1 
II 

Oil 

-0       1 

<o 

-o      1 

r>j 

r-      1 

C--I 

r-i 

ro       1 

ru 

m 

"^ 

^ 

"^ 

"" 

'^ 

O 

-^  II   •  • 

•    • 

•  • 

•  • 

•  • 

•  • 

•    • 

»   • 

•    • 

•   • 

•      • 

3 

II  OOfM 

ooo 

oom 

OOro 

oor- 

oom 

oo-r 

OOO 

oo-< 

00-" 

OOOO 

z  no -TO 

o-oir\ 

00-1-03 

oooa) 

•or-JO' 

r-iom 

rsioir* 

o    o 

oor- 

oo-r(*> 

■T-or-j 

1— 

:3  II  <o  1  o 

o-trj 

-J -HO 

rr,(<\t~t 

r-— O 

O-  1  o 

ror-j-H 

in     o 

ir>-40 

r^     o 

O-roo 

OOOO 

oc  II  m      • 

•t       '«t~       • 

m  1    . 

p-i       • 

•o      • 

0-       . 

-o       . 

0-       • 

m      • 

oc 

1-  •  •  • 

II  <o     o 

-o    o 

•o    o 

•o    o 

<M       O 

r^     o 

rj     o 

r-i     o 

m    o 

r>j     o 

r-     o 

0-— o 

II         1 

t-i 

-H       1 

r-< 

•~*      1 

•-I 

(-1 

f-i 

-H 

O-l 

U--1 

II 
II 

O  II     •    • 

-' 

o 

.  . 

.  , 

.    . 

.  . 

,  , 

.   « 

,   . 

,  , 

,  , 

,  , 

»- 

II  OO— " 

OO-i 

ooo- 

oooo 

OOf- 

oo-o 

oor- 

ooro 

OOf- 

oo— 

00(M 

z 

Z  II  .orgrri 

-0(Mm 

o-tnoo 

O^O^r*> 

00-J-|«- 

oooiri 

-riNj-T 

<M00O 

rgooin 

.-M-r-r 

Z)  II  -o     o 

00      o 

^^o 

rgmr-1 

O-miM 

O-HO 

-rmrsi 

•J-  1  o 

m  I  O 

OO-I— 

— ino 

a. 

oc  II  ro       • 

m       • 

r-      • 

m  1    •»(vi       •»r-       • 

o-      •«o 

0-         . 

in      • 

o-       • 

11-0      o 

o     o 

-o    o 

o     o 

(M       O 

r-     o 

rg     o 

<>J      o 

m     o 

C\J     o 

1-      o 

tl 

»-< 

*-*      1 

-H 

r-4 

-H 

-H          1 

'^      1 

-H 

rg 

-J 

II 

>-H 

< 

II 

3 

CO  II    •    • 

•  • 

•  • 

•  • 

•    • 

•      • 

•   • 

•    • 

•  • 

•  • 

•    • 

i-o>— o 

II  00-' 

OCX 

oo'.n 

oo-o 

OOin 

OO-O 

oo-i- 

oor- 

oo  — 

OOr-J 

ooin 

o— 

Z  \\<\l(Strn 

O-i/M- 

ir\-HO 

.*■ -!•-»• 

00 -TO- 

OOOl^ 

r-jom 

0.0-*- 

oor~- 

(NOOIM 

-ooo-r 

< 

3  II  -O   1  O 

r-  1  o 

_i_io 

nJ-(M^ 

CO  (M—1 

o-<o 

m(Nj-< 

in     o 

fO-HO 

0<NJf--J 

—ino 

□cum 

i-o       • 

r—       • 

m  1    . 

C--J          . 

r--       • 

o- 

•c 

O-  1     . 

-0       ••»  o>      • 

l\  -o     o 

■o     O 

-o     o 

-o     o 

(NJ       O 

r-     o 

<M      o 

f\l      o 

m     o 

r\j     o 

I--     o 

2 

II         1 

1 

«-* 

-H      1 

i-i 

.—1 

*-* 

t-* 

'->      1 

r-4 

(M 

OOUMU 

II 

f— 1 

_)m     z 

II 
f^  II   •  . 

.  . 

.  . 

.  . 

.     , 

.  . 

,  , 

,  . 

,  , 

,      , 

.     , 

_1          o 

<       z 

II  oocM    oot~-     OOO-    oor-j    cio-c    oo-t     ooro    ooo    oo-j-    oo-j-    ooo 

Z  II  m'-«r--     r-jrgoo     -TO—     ocor*^      -oou— <      ^r-jr-j     a;-0(\j     o      O     -^■O'-i     -or-i^-      0-O-(*^  OOO 

3  II  in  — —      f-^H—      r-ir\j—      rnrOlNJ      -O      O      f^CNJ*-*      p-j  — -H      Ln      O      r-J  — — *      O-o-J—      — rOO  OOO 

oCiiroi«(<\i«r—       •ml«iKN       ••oi'O-       --o       "O-l'in       •ooi»  (Mino 

ll-00-00-00-00<MOI~-OlMO'MOf<10'NJOI~-0  ••• 

II           I               I—            -HI—            --.i-i            —            -H|-H            r-ji  oo— 


-O  II    •    • 

II  oo  — 

oo  — 

ooo- 

OOINJ 

oor-- 

oo-)- 

oo— 

ooin 

OOO- 

oo-o 

oo— 

ZJJ'JJ 

'J 

Z  II  -Ofvir'^ 

-oo-im 

-i-o- 

OCOINJ 

co-j-r- 

OCMCM 

l^.^t~- 

rrii^^ 

XXIM 

oo.v 

O  II  -o 

o 

CO      o 

CNjr-J- 

-J-(VJ  — 

O-ro  f-j 

CMCM  — 

-J-C^CM 

-J-  1  O 

.n  —  — 

— '  ■*-  r-j 

C-J-< 

ot  II  ro 

• 

f*^       • 

r-       • 

m  1    . 

CM          •*  1^ 

,-7-          -V-O 

:*-       • 

o       •»  o—  • 

11  -o 

o 

-0      o 

-0      o 

-o     o 

f\J      o 

r-     o 

CM     :^ 

■NJ         O 

r^       C 

^     o 

■X>       O 

II 

f-t 

—      1 

•— 

--4 

-H 

—           1 

,-t 

-H 

CM 

1/1 

II 

1- 

II 

o 

in  11    • 

•  • 

■  • 

•  • 

•    • 

•    • 

•    • 

•      • 

f     • 

•    • 

»     • 

3 

11  oo-r 

OOI-- 

ooin 

ooco 

oox 

oo<*^ 

oo— 

OO-O 

OOO 

oor- 

OOO 

Z  H  -l-O- 

t--J(VJ00 

cD-oro 

r-i-oin 

ooj- 

Nj-orri 

m-co 

—  —  X 

■o-ro 

O-OCM 

inrci— 

3  11  -J-<NJf<^ 

r-- — 

0-  1  o 

-1-r-i  — 

1^     o 

o    o 

crir-jfM 

o  — o 

CNJ-H^H 

0-  — — 

-r— o 

o 

ft 

a  11  m  1 

•  #  m  1    . 

•c       • 

m  1     • 

tM         • 

r-       • 

o-       •*o 

O-    1        • 

in       • 

X  1     • 

o 

o 

!l  -o 

o 

-o     o 

-o    o 

-o     o 

CM       O 

r-     o 

IM     o 

CM       O 

CO       o 

CM       O 

r-     o 

-H 

cf\ 

II 

1 

1 

—     1 

—     1 

,-i 

r~4 

r-4 

-H 

—          1 

,-t 

CM         1 

X 

II 

-4 

1 

tn 

II 

1 

-H 

-J- 11   • 

•  • 

•    • 

•    • 

•    • 

u      • 

•      • 

■    • 

•     • 

•    • 

•    • 

1 

11  ooin 

00(M 

OOI- 

oo— 

ooin 

ooo 

OOrO 

oor- 

OO-J- 

OO-O 

ooo- 

Z  11  -ocor-i 

0-1--0 

r-fTi— 

ooor- 

CM  ceo 

CM -OO- 

xonj 

— CT-ro 

CMCM- 

C-OC 

xocv 

z 

Z)  iiin  1 

-H 

CD  1  O 

O      O 

-TfM- 

p-      o 

OO— O 

.-M- — 

o-rc"^ 

-3-       O 

OCMCM 

e-nc 

-^ 

a:  11  m 

• 

rri 

r- 

m  1    • 

CM          • 

-C   1     • 

c-       . 

-0  1    •■a-o- 

-O         .^X  1     . 

11  -0 

o 

-O      O 

o     O 

-0     o 

CM       O 

r-     o 

INJ       O 

CM      o 

pri      o 

CM      O 

1-     o 

■'i: 

II 

1 

1 

--4 

—      1 

— H 

—      1 

—4 

—      1 

— -1 

r-* 

(M        1 

o 

tY. 

II 

'Xi 

11 

1- 

r<>  II    • 

«    • 

•      • 

ft  • 

•      • 

•  • 

•      • 

•  • 

•    • 

.•    • 

•     m 

■i 

CO 

II  OC  — 

oor-j 

OCfO 

oo-i- 

OOO 

OOfO 

oc-c 

ooo- 

OO-O 

ooin 

OO-O 

1—4 

1/1 

Z  II  -o<Nm 

f^— *h- 

CO-l-X 

roinr-- 

o-in-l- 

CM.OO 

-o-o-j- 

oor^ 

rocNjx 

(MINI- 

r^  — X 

> 

o 

13  II  -O 

o 

1-— — 

—  — o 

r\j-j-<\i 

in  1  o 

-omcM 

O  1  o 

si-- c 

CM— O 

r--  1  o 

>r— o 

UJ 

ac 

ot  II  rri 

« 

ro  1     . 

h-        • 

m  1     .»(\, 

-C  1     •#0- 

-O  1     . 

a<  1    • 

in      • 

i~-—  • 

c 

O 

11  -0 

o 

.0     o 

-0     o 

-0     o 

INI      o 

r-    o 

CM      O 

C--I      O 

(V)     o 

<M     o 

>  1  o 

11 

1 

•— < 

—      1 

—      1 

—      1 

—       1 

—     1 

—      1 

•-<      1 

(M        1 

II 

11 

INJ  11      • 

.  . 

,  , 

.   . 

.   . 

,  . 

,    . 

.  , 

,  , 

,  , 

.    . 

11  oo-t 

oo— 

OOf^ 

oo-o 

ooco 

ooo 

ooc- 

coo- 

oct<^ 

OOINI 

oo-»- 

z  11  o.oc^ 

-OtNim 

CO -J- CO 

-i--r-r 

CMCorsj 

X      O 

cxro 

OOI^ 

-o-o-r 

^-mx 

— m-o 

OIII-- 

o 

CD       O 

—  — O 

-l-rg— 

O^CMCM 

O-     o 

en  — — 

-0  — o 

-1-      o 

O-CM  — 

-rroo 

a;  ii(«^ 

• 

m 

1^      • 

ro  1    . 

CM          •»  -0          • 

o- 

-0 

o- 

in       • 

o-      • 

II  -o 

o 

-o     O 

•o    o 

-0     O 

CM       O 

r-    o 

fM      O 

CM       O 

m     o 

(M      o 

r-    o 

11 

t-4 

-H           1 

-H 

•H 

f-H 

-H 

,~-i 

f-H 

(M 

II 

t— 

•    •    ft 

-TO 

II 

OOOCMO 

-H    II       • 

•  • 

•    • 

•      • 

•      • 

•     • 

•    • 

•  • 

■    • 

•    • 

ocT-o^or-i 

11  ocr- 

ooin 

o&r~- 

ooco 

OOiT, 

COX 

cc>r 

coin 

coco 

oo-l- 

CO-f 

XC-  — 

ft    ft 

z  11  r-m-r 

in— — 

rsicoo 

OXsT 

ct>-ro- 

oxin 

OXO- 

-r-ro 

oo>»- 

l—CT-CM 

inxci^oo 

z>no 

o 

jc     o 

M  — — 

•O  1  O 

00  (M  — 

I-C--1  — 

inmcM 

—  OJ> 

-orsi  — 

OCMCM 

-H  J>— ( 

xco 

oc  11  r^ 

• 

m       • 

h-       • 

rf-       . 

r-w       • 

-O   1      . 

0-       •«  r-       •■»  o- 

-c 

>o—  • 

i--h- 

II  -0 

o 

o     o 

-O     o 

c     o 

CM       O 

r-     o 

tM      o 

(M      o 

m     o 

CM       O 

X     o 

CMCM 

II 

-H 

-H           1 

,-* 

—      1 

-H 

-H 

-H 

-H 

CM 

-H-H 

II 

— 

11 
1-  II    • 

, 

. 

. 

, 

, 

. 

. 

. 

. 

l-l- 

OHO 

o 

o 

o 

O 

o 

o 

o 

o 

o 

o 

OtD 

X  11  -r 

-»■ 

~3- 

00 

-J- 

X 

CM 

o 

o 

-1- 

X 

s:s 

:i 

II  -0 

CD 

O 

-0 

-o 

O- 

-H 

in 

-1- 

r- 

in 

o 

u.  II  m 

m 

r- 

t<\ 

M 

•c 

o- 

-0 

o- 

j\ 

X 

a.>-r£ 

_l 

uj  II  -0 

•O 

-0 

-0 

CM 

t- 

CM 

CM 

m 

CM 

r^ 

UJOOC 

_l 

a:  II 

-H 

-H 

r-* 

— * 

-H 

-H 

-H 

-H 

.M 

OCi^UJ 

< 

II 

^- 

1- 

^ 

1- 

h- 

1- 

1- 

y- 

>- 

1- 

--4 

h- 

•  II 

z 

z 

z 

z 

Z 

z 

z 

z 

Z 

z 

l-l-l-ZX 

o  iiin 

ai 

in     UJ 

00       LU 

-1-       UJ 

-0     oi 

-0       UJ 

•—       UJ 

—       UJ 

O       UJ 

CT-       UJ 

oooo< 

z  n  oiicj 

O-dCO 

-i-oro 

inoco 

■oa.i_> 

>COCt^ 

l~-cZO 

r-ct:o 

XOCO 

-j-c»:o 

i-i-i-as: 

II  ma 

COO 

OO 

fMO 

coo 

XC 

ino 

xo 

c«10 

-oo 

3C  11  — cio; 

fNjQCo; 

nI-ocq: 

(Moco: 

root  a: 

rocto: 

-TOiQC 

r-cco: 

r^oca: 

tPQCOC 

I-QCI- 

<   11  CQCliJ 

—  aiu 

oorui 

ocy  LU 

r-oCiu 

f-cr  UJ 

-3-C3CUJ 

OCCUJ 

-l-OJUJ 

l-ClTUJ 

oorz 

o  11  o  uu  i 

OLua. 

OUJQ. 

c  jja 

OOJOl 

Cujn. 

—  UJQ. 

—  UJO- 

c-uja 

ouja. 

^UJO 

II 

i-oor: 

11  — 

(M 

rr, 

>» 

in 

■C 

f- 

-D 

tr 

c 

c;_jjj 

II 

— 

I-<Ql 

Tests  of  Coupled-in-Motion  Weighing 37 


II  •  • 
t-  II  ooo- 

OOO 

00<T- 

oo(^ 

OOO- 

OOOO 

oorvi 

oor- 

OOO 

OOC7> 

o  II  trwi^-t 

sO~0~J- 

rsirsi-f 

oocDtf^ 

-r-ro 

tninfo 

inin-i 

(7--<(N) 

-•Oxvj 

J-N1--0 

1—  II  roc*— < 

•OfMO 

(NJOOO 

f^a>o 

!>-(»>-» 

mj--i 

-O^J--" 

rO-O-" 

r-(Nio 

UN -J -4 

CO          • 

r-      • 

r--«  • 

r^rg   • 

INJ-i     • 

r<l-i    • 

m  1    • 

<J<(NJ     • 

tl  f<>      o 

ro     o 

r-     O 

m    o 

INI      o 

-O  1  o 

0^     o 

-0  1  o 

o-     o 

in     o 

II  o 

-O 

■o 

o 

(\j 

r^      1 

(NJ 

(NJ          1 

m      1 

(Nl 

II 
O  II 

"]  . 

"^  . 

a     a 

a     a 

a    a 

a     a 

a     a 

o 

3 

II  OOOO 

00(M 

oom 

oo-o 

OO-" 

ooo- 

OOro 

ooj- 

00(»> 

00(7- 

00(»1 

z  II  o^inr- 

co^j-o 

00 -J- as 

CT--'0 

j-coo 

-r~rr- 

0-J-.0 

r^r^ro 

sf -0-r 

^or- 

mit\-f 

^ 

3  II  >0      O 

00      o 

-<_iO 

o    o 

lO-iO 

co-^o 

-l-miNJ 

-0-^-' 

m  1  o 

00 -"O 

-lUNO 

OOOO 

Qt  II  m       • 

r-       • 

fO        • 

(SJ  1      • 

-O  1     • 

o-      •»  -o      • 

o-       • 

u>       • 

o-       • 

1-   •  •  • 

u  -o     o 

.0      o 

o     O 

<5      o 

<M      O 

f-      o 

(Nl       O 

(Nl        O 

ro     o 

(\J      o 

r^     o 

r~rr\o 

II 

•— ■       1 

'-•      1 

^^ 

•-4 

^^      1 

^H 

(--J 

U.(NJ 

II 

'"' 

o 

cr  II    •   • 
II  OOrj 

ooc^ 

oo-< 

ooro 

OOO 

oo-o 

OOINI 

OO-O 

OOin 

ooo- 

OOINJ 

z 

Z  »  o<r-o 

ODOO^ 

— ir~^ 

of\jr^ 

O-Oro 

mrr\!a 

-J-'NIO- 

a--j-o 

inirvro 

0-J--T 

CDO-O 

1_) 

3  II  ~0  1  O 

r-  1  o 

-1      o 

m--o 

OO-l-i 

-cro— 1 

(NI-IO 

(NJINJ-. 

-r     o 

ro-rrd 

r-ooo 

Q. 

ac  II  ro       • 

m       • 

r^      • 

m  1    • 

<N)         . 

-O   1      • 

CT-          • 

-O   1     • 

(7-         • 

■n  1    .-in^  1    • 

II  >o     o 

■o    o 

.0     o 

■o     o 

(NJ       O 

r-     o 

r\j      O 

(NJ         O 

ro      O 

(Nl       O 

r-     o 

II           1 

1 

-<      1 

^ 

--'      1 

" 

-■     1 

" 

-1         1 

(M         1 

_l 
< 

3 

00  II     •    • 

,    ^ 

,  a 

,  , 

«     a 

a     a 

a     a 

a     a 

a     a 

a     a 

a     a 

i-r-(»^o 

II  OOi/> 

OOINJ 

OO-J 

oo-o 

OOO 

OO-O 

oo-r 

OOO- 

OOO 

OOO 

oor- 

0(N| 

Z   II  <NJ  00  (VJ 

OnTvO 

«0:^J^- 

pg^m 

roa-m 

lyo'r- 

f-gOtn 

oor~- 

-o^o 

o  j-r-- 

oooro 

< 

3  II  r-     -■ 

00  1  o 

-j-iO 

~o  1  o 

crtMtM 

<T~TI\I 

fO.NJ^ 

-J--'0 

(NJ--1-" 

>j-m(Nj 

---to 

a:  II  m      • 

1^       • 

r<^       • 

t\J       .*  >0  1    ••«•  o       • 

■C   1      • 

a-  1    • 

in  1    • »  CO  1    .. 

II  >o     o 

-0     o 

■C      O 

-0     o 

r\j     o 

r-     o 

(Nl       O 

(Nl        O 

ro      o 

(NJ       o 

r-      o 

3 

i 

^^      1 

--<      1 

-"      1 

--•      1 

->      1 

(NJ          1 

ooinai 

|. 

>~-4 

-IfO      z 

,1 

_1          O 

r-  11    •  • 

«    , 

a     « 

•    • 

•  • 

a     a 

a     a 

«    • 

•     a 

•  • 

•      • 

<        z 

II  oo>i- 

oo-< 

OOO 

oo-o 

oo-o 

OOO- 

OO-" 

OOO- 

OO--" 

OO-i 

OOOO 

z  »  ooty- 

.OfMr<1 

-J-      o 

Nj-Or'> 

-OfM  — 

0)0-0 

CD-OO 

-((XNl 

oor- 

r-(-o>r 

>J-Org 

OOO 

3  II  r^     o 

CO       o 

o     o 

r-     o 

-o    o 

-Dro^ 

m.-Njrg 

Njr-gi--j 

un— lo 

-><trn 

CJ-roO 

OOO 

:^  n  m 

ro        • 

r~       • 

rr,        • 

f\J       • 

-C  1      • 

O-         •»  -O   1      •■! 

1-  o-       • 

-O        '^OO 

(Niino 

II  o     o 

-0     o 

vO     o 

.0     o 

(SJ       O 

r-     o 

(Nl       O 

(Nl       O 

r'\     o 

(NJ       o 

r^     O 

a     •     • 

^^ 

'-'      1 

-^ 

'->        1 

<~* 

—* 

OJ 

oo-« 

II 
<0  II     •    • 

^ 

1- a:  of  of 

,    , 

,    a 

,    , 

a     a 

a     a 

a     • 

a     a 

a     a 

a     a 

a     • 

ZVULUlil 

II  oor- 

OOO 

ooirv 

oo-< 

OOJ- 

oo-i- 

OOtNl 

ooc 

oom 

oo-t 

oo-r 

o>>> 

z  II  ^Oin 

mij'-f 

o^om 

r<1inC 

rotT'.n 

O.-0-" 

iNjom 

ir\uN(<\ 

i^(^a- 

r--r--a- 

^J30 

o-oao 

3  II  r — 1-« 

CT'      —1 

-"     o 

CO-IO 

ao.-1-i 

-Cr^iNJ 

-J-rotNj 

irv     o 

rNl-.0 

rorri(NI 

•o     o 

o:  II  m       • 

ro        • 

r-      • 

m       • 

<N         • 

-O  1     •»  CT-        •«■  -O 

o-  1    • 

ir\  1     'ttoo       • 

II  -o      o 

^      O 

-0      o 

-o     o 

tsi     o 

r-     o 

<N       O 

(NJ       o 

-n     o 

(NJ       o 

I--      o 

-^      1 

^^ 

—4 

-<      1 

-<      1 

(NJ 

y/i 

II 
II 

^^ 

^ 

O 

in  II    •  • 

a     « 

,  a 

•  • 

a    a 

a    a 

a     a 

a     a 

a     a 

•   • 

•      • 

3 

II  OCM 

OOin 

ooo 

ooo> 

OOifl 

OOO 

oo>r 

OOUN 

oor~ 

OOO 

ooo 

Z   II  tNJOOOO 

f\JCO<M 

~j-ox\ 

-l-O-J 

PJ00.O 

(NJOO- 

OOOO- 

0O(NJ-l 

(Njooir\ 

O-OOO 

-OOOO 

3  II  OO-TJ 

O-      -J 

^-JO 

OfOM 

r-     O 

00 -HO 

mrocM 

-r  1  o 

ro  1  o 

-irotNl 

COfNJ-l 

O 

3i  II  ro        •»  ro        . 

I--       • 

-J- 

<t  .-NJ 

-O  1     • 

o>       . 

*  o 

c-       • 

-O        • 

iiO'-i    • 

O 

II  -0      O 

O      O 

■o     o 

-0     o 

-■NJ        O 

r-     o 

(Nl       o 

(Nl       O 

m     o 

(NJ         O 

r-     o 

■-(               1 

II 

_4 

^H 

-H      1 

^H 

'->     1 

-"      1 

^^ 

(NJ 

II 

'^ 

1 
1 

II  OOCO 

OOlTl 

ooiri 

ooiri 

OOO- 

OOO 

oo~i- 

OOirv 

oo  J- 

OO-O 

oor^ 

1 

Z   II  ^tNJOO 

rjoorvj 

o-ocr 

eg -TOO 

-OINJI- 

■Ot-JOO 

(NJOir\ 

-t-OO 

O-O-.0 

O-OO 

l-O-m 

z 

3  II  l^-i-i 

a-     -1 

r-j— .o 

co->o 

corNj— ■ 

-cro-1 

rOfM-f 

(NjrO.-NJ 

si-     o 

C.-N1(NJ 

(Nl-OO 

<— 

at  Hm 

i~-       • 

en       . 

,NJ 

-O   1      • 

O- 

-o  1    • 

»o> 

o 

»cr      • 

</)        3  II  r-^-H 


ro  II    •   • 

a 

a     , 

a      4 

•   I 

a 

•     a 

•   • 

•   • 

•  • 

<               1/1 

II  OC 

,-t 

ooc 

00«^ 

ooin 

oo-i- 

oo-c 

OOO 

oor- 

OOJ- 

00-.1- 

-,'N 

-ocy-j- 

1^0- in 

rg-rx 

x-1- 

'^H 

JNO 

N-^ 

3-'^ 

-4 

oor^ 

OO 

-4 

ooo 

OOOO 

>           o 

,-i 

—4 

o 

co- 

'O 

r--i^ 

c-  1 

o 

inin-r 

oD.-^rg 

in^ 

1—4 

or-o 

LU                    QC 

q:  II  CN 

.»(»N 

a 

1- 

rn 

(NJ 

a 

o 

CO   1 

•« 

O         •«•  O- 

• 

o      •«  cr-4  • 

c           o 

II  -0 

o 

-0 

o 

-0 

o 

-o 

o 

(NJ 

o 

r- 

o 

(Nl 

o 

.NJ      o 

.-«> 

o 

rg      o 

,-t 

—1 

p-4 

1 

—4 

1 

-^ 

-^ 

F-4 

rg 

II 

'-' 

(Nl  11     •    • 
II  OOtNl 

ooo 

oo'.n 

OC(Nj 

OOro 

oom 

OC 

O 

oo-< 

co-j- 

oox 

00<T 

Z   II  '/N-- 

II- 

■J- 

o 

o-om 

ini--j- 

o-oo- 

r-- 

-r- 

o-J-m 

CL-(N,— 4 

00  (N 

1-^ 

-to-< 

r-0--4 

3  II  r-^ 

en 

o 

o 

1- 

o 

or^fNj 

om— • 

r-4 

o 

<7-in-r 

CO  1 

o 

-4sJ-rr, 

r-^o 

a 

m 

r~ 

m 

• 

(<N 

•  i>  O   1 

1    • 

o- 

• 

JN  1     •»  o- 

• 

O          •«00          • 

II  o 

o 

-o 

o 

-o 

o 

-0 

o 

pg 

O 

1- 

o 

rg 

o 

rg     o 

m 

o 

rg     o 

r-     o 

1 

'-•      1 

1 

—4 

.    •    .CCO 

OOOrgO 

a 

a 

a 

a 

a 

a 

a     1 

a     a 

a      1 

•   • 

•       • 

OC-c-cnj 

11  cc-r 

OO.Nl 

CO-" 

oco 

ooo 

ocn 

C- 

;a; 

oor- 

OOO 

OOO- 

CCJN 

ccrim   •   • 

o-ro 

-0(^ 

g^^ 

-^ro-J- 

rgcN 

J-> 

rr- 

-O 

O-J-O 

r-c^r- 

>f  0=0 

(Njcor- 

sT  -cm 

.no-cNOO 

3  II  r-- 

T. 

1  o 

o 

ri 

O^^-i 

O  1 

o 

(?> 

o 

(-g^^-H 

r-r-'n 

— .rg-4 

r-crr- 

OsJ-O 

OOOO 

•  »  m 

r- 

a 

m 

a 

(-g 

a 

-o 

a 

0- 

a 

in  1    .«  o  1 

• 

o       •»  cr       • 

II  -0 

,-1 

-T. 

o 

-n 

o 

-c 

o 

(NJ 

o 

r- 

o 

(NJ 

o 

(NJ       o 

m 

o 

rg     o 

r-     o 

pg.-g 

II 

1 

-^ 

-" 

-^ 

'- 

->      1 

•" 

' 

■"" 

rg 

—4-4 

II 

. 

a 

a 

a 

a 

a 

a 

a 

i-l- 

OHO 

O 

o 

o 

o 

o 

o 

o 

O 

o 

o 

3  II  -r 

^ 

-J- 

CO 

^ 

00 

rg 

o 

o 

-J- 

CO 

3S           i 

II  -o 

(D 

o 

-n 

-I) 

fT- 

—4 

in 

-J- 

r- 

in 

fl 

m 

O 

IT- 

o 

o- 

in 

CO 

u-t-o:     _i 

-.1 

-o 

INI 

r- 

rg 

rg 

m 

rg 

i~- 

UJOCC        _l 

aC  II 

-^ 

,-* 

,-t 

—4 

—4 

-4 

(-g 

(ii-LU        < 

^ 

H. 

t- 

V- 

1— 

1- 

l- 

t- 

1- 

-4 

?■ 

7 

7- 

z 

z 

Z 

z 

^ 

O  II  UN 

LU 

U~. 

OD 

-r 

o 

OJ 

in 

,-* 

LU 

p-4       LU 

o 

UJ 

Q-       LJ 

oooo< 

z  11  oao 

O-ClCO 

-roco 

in  oco 

oa:o 

-OoiO 

r-a:o 

r-ocu 

itjaco 

-foco 

OOO 

OO 

(NJO 

ceo 

-i-c 

u-iC 

coo 

mo 

OO 

r-jof  (^ 

-ra'(x' 

(NJQ 

t  rf 

rriixc^ 

oqcq: 

-j-oro: 

t-aet 

ONocac 

iaqcq: 

t-tl-l- 

1  II  cocuu 

-HC^UJ 

Ctx-'JJ 

0«UJ 

l-CCUJ 

inriruj 

<ta:^ 

CCtOJ 

-raai 

r-Qcuj 

ISOCZ 

<_;  11  ou 

JO. 

Cl 

UQ. 

OOlQ. 

o-ua. 

OU 

Ji 

ini 

U(3. 

-411 

J  a. 

_UJi 

r-u 

JOl 

■SLUO 

>-(.n3: 

II 

Nl 

i-O 

~»- 

■n 

o 

1- 

uc 

c- 

^ 

■- 3-1X1 
l-<li 

38  Bulletin  654 — American  Railway  Engineering  Association 


II  ••  ••       ••       ••       ••       ••       ••       ••       ••       •• 

t-iiooo  oo-*-    oor>-  ooo>    oo<vj    00.0    oo>o    oorj    000    oo^^ 

O  II  ^— '•O  -1->1--J     l/^u^M  ror-o     (M.'vj-l-     >1--0(\J     l^roo     •t'Om     •T■^'^     -h^p-4 

I—  II  -000  -o<MO     r^in-j  «r-^o     -taj^     -t.roo     ■I'ooo     r~.o-<     r-r--*    r-r-— « 

II 00^  «  ^       •     00^  •  in  I    •     o-<  •     ro  I    •     ro  I    •     o>-<  •     ,»■       •     r-       • 
H-ooroo-<o^oooocoo>ro>fiOfnoroo 

II  ^  .0  IN  r-      I      f\j  ro      I      ivj      I      rg      I      o  ^ 

11^  ^  ^  ^  ^  .^  r-<  ^ 

O  II 

^11  ••  ••    ••    ••    ••    ••    ••    ••    ••    •• 

iioo-J  oo-<    00-J  oor- 

^'limr-.j-  ^o-o     r-in»l-  o-o-^ 

U  II  CO     o  0-10     (~-     o  rooj— I 

H-oo-ooojo^-o<MO.foo<MO<NJo>oo>oof^o       00c 

H-H  ^1^  ^l^l^l^l^l  (Ml         U-r-* 


oor- 

00(\J 

oo-*- 

OO-H 

001--    000 

oor- 

in -HO 

rool^ 

Oroo 

incrr*- 

<m(\jnI-    0     0 

sj-innj 

K- 

00  1  0 

f\j-<0 

f«1-4-H 

0  1  0 

onjfo     r-     0 

r-foo 

0000 

r^      • 

CO  1    • 

-*■  1   • 

in      • 

m       •ftfo       . 

0  1    • 

t-    •    •   • 

0>  II     .    . 

•  • 

•  • 

•  • 

t  • 

•  • 

•  • 

•  • 

•    « 

»  » 

•  • 

t- 

II  OOO' 

OO0> 

ooin 

00-^ 

00.1- 

ooin 

000 

00-4 

000 

ooin 

OO'^ 

z 

H  II  ooin 

(Vino-r 

o*-^ 

•J-CM-l 

OOrO 

-r  o-H 

.nrNJI*- 

O^rro 

•j--r.Ni 

CO  CO  CM 

inocr 

0 

:>  iico-<o 

(M      0 

oo-<-i 

m  1  0 

->tnc\t 

in -4 -4 

OINJ-4 

-■  1  0 

in-4(Ni 

r-     -H 

CM-40 

1^ 

q:  II  0      • 

fO          • 

»-4            • 

•0      • 

CD        •»  =o        • 

•T        • 

in      . 

fo      •«rn      • 

CM-4    • 

II  >o     0 

0       0 

ni     0 

r-    0 

«M      0 

m     0 

CM       0 

(Nl     0 

0    0 

0     0 

r-    0 

II  -< 

^H 

1-4 

r^     1 

«-• 

•-H 

f-l 

^     1 

CM 

_l 

II 

f-4 

< 

H 

3 

00  II   •  • 

•    • 

•     • 

•  • 

•    * 

•     • 

*    • 

•  • 

•  • 

•  • 

•    • 

(-0000 

II  OOrO 

COX 

000 

OOr<i 

000 

OOI«- 

oor- 

00-4 

oo-r 

OO-l 

000 

0-4 

Z  II  (^J^roO 

o>i-o 

^^(JK 

0000 

lNJO~J- 

CMOOO 

or-cr 

O-J- ro- 

«ro<^ 

CMCMrO 

in>ro 

< 

3  II  -o  —  o 

COl^.NI 

0-"0 

oincM 

0^       0 

— IIN^ 

Of^CM 

coco  cNi 

ro  1  0 

r^     0 

00-4 

CC  II  -0  1     • 

INJ   1      •«-*  1      • 

0  1    •»r-      • 

CO   1      • 

-T  1     •*n1-  1     -^rri        . 

ro       • 

0>(M.» 

II  -0     0 

0       0 

<\J     0 

r^     0 

CM      0 

ro     0 

CM      0 

CM       0 

0    0 

0     0 

0  1  0 

3 

11 -H     1 

-^         1 

-^     1 

-^      1 

«-4 

-4       1 

f-4          1 

-4           1 

1 

CM         1 

oomuj 

II 

-im    z 

11 

_i        0 

r^  II  •  • 

•     ♦ 

•    • 

•  • 

•     • 

•    • 

•     • 

•    • 

•    • 

•   • 

•    • 

<        z 

IIOOI^ 

000 

000 

oOin 

oom 

OOr<i 

000 

oon 

OOro 

00(M 

000 

Z  II  >rcorM 

o.N,cr 

tMO~r 

>TCO>3- 

corMCT> 

•ro-f 

w;:N(Ni 

--.'  '.7  0 

^-J-O 

or-i- 

000 

3  II  -<rri(M 

'fm'-' 

Of*>fM 

0       0 

0-^0 

sT     0 

:^.■  — *  -^ 

^^iNjr-4 

-r     0 

r-     0 

oc^o 

000 

c^lll--        ♦■it-m        . 

(M          •«  0          • 

r^       • 

■*o       • 

ST   1      • 

-J-      1          • 

fr,        • 

c«^       • 

(M        • 

cNjmo 

MO     0 

0     0 

CM       0 

I--       0 

CM      0 

r^>      0 

(NJ       0 

CM      0 

0    0 

0     0 

r-     0 

•  •  • 

II-' 

«-* 

^H 

r-t 

•—4 

*-4 

-4          1 

-<       1 

CM 

00-4 

II 

II 

i-otococ 

Oil    •  • 

•  • 

•    • 

•      • 

•     • 

•     • 

•     • 

•    • 

•    • 

•   • 

•  • 

ZUJUUUJ 

H  oor- 

0000 

000 

000 

ooin 

oo-r 

oo-r 

000 

OO-M 

OOrri 

OOCM 

o>>> 

Z  II  -J- coo 

000 

o~fr~- 

ooin 

o-J-o 

OCM -4 

OfOCO 

-»•      0 

oom 

00-4 

cDO-ro 

Q.OOO 

3,|(J-r^^ 

ro-<0 

Or^rM 

o-^o 

fMC<>CM 

m  1  0 

0(N1— 1 

-1      0 

in -4  CM 

0>(Njro 

r-o-4 

OC  II  0        • 

m       • 

(\j       ••M-o       • 

CO         •«00         • 

-r      • 

in      • 

rO        •»c<l        •»  (Nl-4   • 

II  o    0 

0     0 

INJ      0 

(^     0 

CM       0 

ro     0 

CNJ        0 

CM      0 

0      0 

0      0 

r-    0 

II  i-H 

■-H 

fM 

r~4 

•—1 

--      1 

■-4 

-4 

(Nl 

l/l 

u 

—4 

►- 

N 

0 

in  II   •  • 

•     • 

•     • 

•      • 

•    • 

•   • 

•      • 

•  • 

•    • 

•   • 

•  • 

3 

II  00 -< 

ooin 

000 

oor- 

000 

000 

000 

OO-" 

OOrri 

ooin 

00-4 

Z  II  ~J-INJ^ 

rocrin 

ooo-r 

CDCMO 

ooin 

minco 

ooino 

O-TI^ 

~r-4-o 

0OX(NJ 

CMr-(NJ 

o  H  r-  1  0 

<M    0 

r-     0 

O-HO 

OCM— 1 

-4  CM -4 

-4  CM  CM 

00  CO  CM 

•r    0 

1^         -4 

OOCMO 

0                  • 

Oi  II  -o       • 

ro       • 

-4       • 

0      • 

CO         • 

CD   1      . 

>r  1     •■»  nT   1     ••«■  cri        . 

rri        • 

0  1   • 

0               0 

II  >o     0 

0     0 

(NJ       0 

r-    0 

CM       0 

CO      0 

(N      0 

CM       0 

0    0 

0      0 

r-     0 

-H                       fC, 

II -<      1 

--I 

i-t 

)-4 

-4 

-4           1 

—4           1 

-"        1 

(M         1 

00 

II 

r~4 

1               ro 

II 

1                         -4 

-r  II   .  • 

•  • 

•     • 

•      • 

•     • 

•    • 

•      • 

•    • 

•  • 

•   • 

•      • 

iioor- 

OOOJ 

ooni 

000 

ooin 

000 

oo-r 

ooin 

00-4 

oot^ 

00-4 

Z   II  ^}■0O>l• 

OfM-J 

(NIOOO 

ooin 

COlNJ— " 

c^inro 

0(^CM 

CMCMCJ> 

(Mcoro 

rc^rrisj- 

Of-(^j 

j'* 

0 IICO      c 

->       0 

00 -"O 

0-"0 

00     0 

<r     0 

>f   1    0 

O-'O 

vl-        0 

r--     0 

(^■N.    -. 

.--* 

0:  II  0 

ro        . 

--4            ■ 

0      • 

^-       • 

CO          • 

>1-          • 

.n  1    • 

m       • 

m 

,~i            • 

HO       0 

0      0 

(NJ        0 

r-     0 

(M      0 

rr:       0 

CM       0 

CM      0 

0     0 

■£     0 

r-     0 

Z               (J£ 

II -« 

>-i 

•-« 

>-4 

r-4 

•-4 

-4         1 

-4         1 

(NJ 

0           a: 

II 

-H 

1— •                 UJ 

II 

1- 

m  11     •    • 

•   • 

•    • 

•     « 

•     • 

•    • 

•     • 

•  • 

•  • 

•  ■ 

•    • 

<                  U1 

1100-^ 

OO-H 

000 

OCfM 

ooin 

OC-4 

oOnJ- 

C;0(7> 

oo-r 

0000 

00-4 

•-i            t/> 

TT  II  ror-o 

>i-oo 

.I- CM  CO 

1^^  0 

inc>c 

<)--i-o 

in :';  nT 

-l-O^" 

0  0  ■> 

CM(N10O 

-3- mm 

>          a 

:;  II  a->-H 

<\i^Cl 

0-(NJ-^ 

O-iO 

CMmrc^ 

CM -4 -4 

CM  — -4 

O-CM— ■ 

vf           0 

00-4—4 

r-00 

UJ            a 

or  II  0      • 

ro       • 

^H            • 

0      • 

00       ••)!•  CD  1    • 

nT    I      • 

sr  1    • 

c<^        • 

m       • 

r-4              • 

CJ              0 

II 0    0 

0    0 

(\J         0 

r-    0 

CM      0 

m     0 

(M       0 

CM       0 

0     0 

0     0 

r-     0 

II  -> 

1— 1 

— H 

—4 

r-4 

f-i        1 

-4           1 

-4         1 

«NJ 

II 

II 

INJ  II    •    • 

-4 

,  , 

,     , 

,  , 

.  , 

,  , 

,  , 

,    , 

,   , 

,  , 

,     , 

II  ooo> 

000 

OOINI 

000 

0000 

oo>j- 

oc-r 

ooo- 

oo-r 

OOfM 

com 

z  II  ooin 

in^o 

"l-INJO 

0    0 

oor- 

OCM— 1 

oroo 

o^in-4 

OOiT 

-r-io 

(NjrriCNI 

;d  II  00.^0 

^    0 

OdtNl 

in    0 

0^-40 

fn  1  0 

(Tl-4^ 

a>.-4^ 

-r    0 

1-    0 

<trr,o 

0:  II  0 

rr,       • 

nj        •«•  0        • 

r- 

CO         • 

-1-  1    • 

~»-  r   • 

cri        • 

m      • 

t~t        • 

no    0 

0     0 

nj     0 

r-    0 

nj     0 

m     0 

CM       0 

(Nl      0 

0    0 

•0    0 

l~-     0 

II  —• 

d 

(-1 

1— 1 

r-i 

^      1 

-4           1 

-4      1 

CM 

II 

-4 

•  •  •mo 

II 

OOOfMO 

•-H   II      •     • 

•     • 

•  • 

•  • 

•  • 

•  • 

•    • 

•  • 

•    • 

•  • 

•     • 

ommo(Nj 

II  OOff^ 

OC-1 

000 

oco 

OOsJ- 

ccn 

OOCNJ 

ocr- 

oo-i- 

000 

000 

0-(7<0   •   • 

2  II  jMj>in 

-TOO 

inmo 

ooin 

00m 

-ro-4 

cr>)-fo 

COOCNJ 

ooo> 

com 

ro-rm 

0r<1(*^00 

:3  MOO    0 

O-iO 

00-<-" 

0— 'O 

— ir<^rg 

IT -4-4 

CO  1  0 

C-.-4-4 

.T       0 

00  ^H— 4 

r — 30 

-4-4 

q:  11  0      • 

r»^  1     • 

w-4              • 

0      • 

00         •<  CO         « 

>r 

-*■  1    • 

Cl         • 

r<\       • 

•-4      • 

r-i^ 

II 0    0 

0      0 

t\J          0 

r-     0 

CM     0 

f"       0 

CM      0 

(Nl       0 

0    0 

0     0 

r-     0 

(M(M 

11-^ 

•~*       1 

t— 1 

—4 

.-4 

,—1 

-4     1 

^         1 

(Nl 

-4 1-4 

II 

-4 

II 
t-  II   • 

, 

, 

. 

. 

, 

, 

, 

, 

. 

. 

l-l- 

0  no 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

3  II  0 

-I- 

CM 

0 

0 

CO 

Cl 

>r 

0 

0 

a- 

33           3 

iir- 

-4 

r- 

in 

CO 

m 

-I- 

-r 

r^ 

0 

0 

U.  II  0 

m 

•-4 

0 

r- 

CO 

>r 

in 

CI 

m 

^^ 

U.I-QC       _J 

uj  II 0 

0 

CM 

t- 

CNJ 

fO 

CM 

CM 

0 

0 

r-- 

UJOOC       _l 

oc  II  -^ 

(-^ 

■-4 

r-t 

•-4 

f-4 

-4 

•-4 

INJ 

atxuj     t 

II        1- 

1- 

(- 

1- 

1- 

t- 

1- 

h- 

i— 

t— 

•-4 

t- 

•M           Z 

Z 

Z 

z 

Z 

z 

z 

Z 

z 

z 

t-t-i-srx 

C  IKS      UJ 

•T      Ul 

0       LU 

in    lu 

00     lij 

a>    UJ 

-4         UJ 

in    UJ 

in     UJ 

coco< 

z  n  >j-a:o 

inoco 

ooto 

ooco 

t~CC<^ 

C»^QCO 

-j-oco 

l^ciO 

ooco 

(3-o:o 

t-i-t-cj.3: 

HOO 

MO 

000 

^0 

ino 

mo 

oa 

000 

r-o 

mo 

0:  n-T  a  cc 

(Mao: 

roctoc 

OO^CL 

■fa.cc 

■fc^a: 

imceac 

r-oCQC 

r^mai 

CMOCOf 

H-OCI- 

<  II  OtfUJ 

oa:LU 

P-(iUJ 

inuCLu 

•tctm 

r^auj 

r--a:uLi 

occm 

-<o:ijl; 

-4  0CUJ 

OC£Z 

U  H  OUICl 

oaiQ. 

oaio. 

inujx 

--41UO. 

o-ucx 

C'^Q. 

— lUJCL 

oiua 

O-UQ. 

iUJU 

Tests  of  Coupled-in-Motion  Weighing 


39 


t-HOOoj  ooo  00-'  oooo  oo-o  oof>J  OO'^  oo—  oor-  OOPJ 
OHf^m.!-  oo-  u>uM>  (ort^in  o-l-r-  oo<NJ>»-  fvjoo-^  J-.<-cM  (sjfsi-o  inino 
t-Hvrcj^o     como     -ia>^    i-mo     oooo    r--"©     cr-io     ~»-o-<    irvtMO     oo-m 

II  CT>        •      J-        •     r 1   •     .-M-i   .     rorg   •      rri-"   .(Ml.     fOtvj   •     -0-<   .     om   • 

IO>Or-OOOOOa3IO>J-|00'000      00<OOIO 
X^  (^  rr.  J3  JDI.OIUII'O  r^  ml 


OOJ-      oooo      OOm      OOrj      ooo      OOO      OO-J"      OOlTi      OOin      OOO-      OOl£\ 

z  I  mcoo     oxirvj    j--.-^    -cpsr     o(-iv    o     o    >J-msr    r-mm    -lojin    f-'^!)!    i^::^^ 

5    o      .    r-      •    o      .    -■      .«oo      .    >r      .    o>      'CO      .^^c^      •    o>  i    .fto^. 
io>oi^oo<ooo-ooooirio-ooh-o<\joo;o 


0>  II    .    • 

oooo 

ooo 

oo-^ 

OOfO 

ooo 

OOO 

ooo 

oo-r 

oom 

ooo- 

z 

cooo 

ror-o 

o-«.-o 

c^oo■J^ 

0(S1^ 

ro-io 

>i--<o 

^orvi 

m     o 

insTtsi 

I--IO 

o 

03   1      . 

in      .« o>      • 

00      .«a> 

II  o>     o 
11^ 

r~     o 

o>    o 

-o     o 
rg 

-O      O 

INJ          1 

o     o 

in     o 

o    o 

00 

-1 
< 

3 

00  II   •  • 

^  ^ 

,  , 

^  , 

,  . 

«  • 

•  » 

t-^OO 

oo-j- 

OOOJ 

oo-« 

OO-D 

oor- 

ooo 

oor- 

oocr 

oom 

OfM 

OrOfO 

cvjoro 

roor- 

mom 

L-som 

0(MO> 

rjCT>'-' 

,0-^-^ 

c\j-.o 

-j,l--i 

-4m-« 

<M  1   O 

j-m-i 

O 

00  1     . 

>!•  1     . 

o< 

00        . 

II  GO       O 

II -"     1 

r-     o 

o    o 

-0      O 

o     o 

O      O 
rsl       1 

in     o 

o     o 

^      1 

ooinuj 

_1         o 

r~-  II    .  • 

^ 

^    ^ 

,   , 

,    , 

»  , 

a     a 

a     • 

•  . 

.  . 

<        z 

ooo 

OOOO 

oom 

oom 

oooo 

OOIM 

oorvi 

oom 

OO  J- 

.-^JOm 

OCTrn 

-JCNJOO 

>f  .-o— . 

CO  j-o 

r-^.-Nj 

O-""© 

'ri  1  o 

r-(\jo 

m     o 

>r  miNj 

n     o 

O  1     . 

00         • 

•J- 

o-      . 

00       .» o- 

II  cr     o 
II  -• 

r-     o 

-H           1 

cr    o 

O      O 
rsi       1 

o     o 
(\J      1 

o     o 

(Nl 

in     o 

o     o 

-■      1 

OO 

OO-i 

II 

i-ccixoc 

ooo 

ooo 

00-" 

ooin 

OO'-" 

oor- 

OOO 

o>>> 

-.  CM- 

tN'r-.-xj 

sT  .n.n 

vOinm 

rxjooco 

tMCT-O 

>!•  1  o 

cofom 

CO -iC 

in  1  o 

m-io 

rsj  1  o 

ONr<Nj 

OC  II  o        . 

r-      . 

o 

It  O 

CO        . 

■4-   1      . 

<y 

CO         . 

r-l  I  '-< 


II  OO— *  oojo 
zii-.-J-(Ni  o<-j-r-- 
13  II  30  I  o    in-io 


II  -"     I     '^ 


oo-n 

ooo 

ooo 

oom 

OO-" 

oom    ooi— 

oma3 

mom 

on  in 

oo^roo 

mo—* 

mi-vjo 

^4m<-< 

OlM-" 

(SI— lO 

l-tSl-< 

i-o-T     omo 

O        '■»€> 

00    1      • 

vf    1        • 

a-  1    • 

00 

Z!     ^ 

cr     o     -» 


^      1      -. 


,1-  II   .  • 

oo-t 

ooo 

oo-« 

ooo 

OOO 

ooo 

oom 

OOCO 

no  in  in 

003  CO 

rvjr-o 

0(yr- 

CT^xin 

~»- 

O 

in(\jo 

-O-'O 

in      o 

o-j--« 

r^C^r-< 

m-io 

m     o 

'-* 

o 

o       • 

o      . 

00  1     . 

>!■  1     • 

o- 

00 

• 

■y       . 

r~     o 

CT     o 

o    o 

o    o 

o    o 

in     o 

o 

o 

(N        1 

(M       1 

,-4 

.—1 

i-* 

II 

"^ 

m  II    .  . 

oor- 

ooin 

oor- 

ooin 

oo-i- 

oo-> 

com 

oo^ 

OOrg 

OO0~ 

r-in_r 

<min 

m^O 

^mco 

co-T-X} 

vn.-Nj-' 

C--10 

-r-'C 

(Tin  IN 

■J--IO 

(\Jr-<0 

in     o 

O   II  o- 

r-  1    . 

o         .»•  0~   1     . 

00  1      . 

m  1    .■ 

» o>      . 

oc 

■ 

I         !M         I         IM         I         -< 


oo-J- 

COO- 

or: 

o 

OC^l■ 

OO -T 

oom 

CDO-f 

CXDr^ 

oom 

(VJO^O 

>rooo 

om 

lO 

om.-sj 

O-i 

o- 

m.-rm 

r~-o>i- 

oom 

m  1 

1  o 

crm>r 

cr-io 

-"-l- 

^^ 

^^(^ 

*>— 4 

Ofl 

M-< 

o 

1  o 

(M^ 

J—* 

(~- 

o 

.»  0-  1     • 

CO    1 

• 

■I-  1 

1        . 

O-   1 

. 

oc 

* 

0-  1 

. 

o 

r- 

o 

a> 

o 

m     o 

o 

o 

o 

o 

m 

o 

o 

o 

I-- 

<M         1 

rvj 

1 

1 

1 

II 
II 

oocoo 

^ 

^ 

a     , 

,  , 

, 

« 

,  , 

, 

, 

« 

• 

•  . 

.   • 

ocoooorM 

oor— 

ooo 

oo-J- 

ooo- 

oor- 

OO 

If— 

oom 

ooo 

OO-i 

ooc^ 

— lom 

.   • 

r-jom 

r-.aoa3 

r-mm 

m^T'O 

l-tMO 

mom 

o-foo 

om-i 

njcOO 

r-<--r 

r— '^f-i 

r-m-" 

mt\;o 

J- 

1  o 

fsj  1 

o 

O-"© 

m  1 

1  o 

. 

C-  1     • 

O)    1 

• 

-r 

. 

0- 

. 

CO 

1    . 

a- 

. 

O 

r- 

o 

0- 

O 

m     o 

O 

o 

o 

o 

in 

o 

o 

o 

f-- 

o 

'^ 

1 

r>i       1 

(M 

' 

CSl 

1 

'^ 

1 

'^ 

1 

^ 

1 

S      ' 

^-. 

II 
1-  11    . 

o 

o 

O 

O 

O 

o 

O 

o 

O 

o 

i-i- 

mm 

m 

m 

~ 

CT- 

o- 

m 

~r 

m 
m 

O 

>r 

a 

■n 

O 

CX3 

-J- 

c 

00 

a> 

o 

>r 

0- 

o 

O 

o 

m 

o 

(- 

m 

(Nl 

<M 

(NJ 

.-^ 

-^ 

^H 

— * 

oo 

^ 

^ 

^. 

f_ 

1- 

1- 

1— 

1— 

►— 

— * 

-z 

^ 

? 

?• 

7 

y 

z 

MI 

r- 

CT- 

IIJ 

O      UJ 

J- 

LU 

m 

UJ 

m 

UJ 

-r 

UJ 

CO 

LU 

r-     uj 

moco 

ooto 

rsiQCO 

t\iao 

mo:o 

00  CKTO 

OOCO 

OOCO 

croco 

1— ^— h- 

II  o-c 

-•C 

l-O 

r-C 

mc 

OO 

OO 

mo 

e\iaa- 

-"CtOt 

oao: 

ooLor 

cocLo: 

— »i 

~ccc 

OTrof" 

mo^uj 

oaaj 

oociu 

onriL) 

njoiruj 

f-CiUJ 

Oduj 

oaiui 

O  II  o. 

XlO, 

O' 

ua. 

OL 

UOl 

^'OJi 

-•UJQ. 

-"■ 

XJQ. 

OKI  a 

m  jx 

■JQ- 

OUJQ. 

I] 

i-'j:a.' 

H- 

(\j 

m 

^ 

j^ 

c 

'^ 

X 

C" 

'X, 

V. P      J 

40  Bulletin  654 — American  Railway  Engineering  Association 


II   •   : 
»-  II  oo-< 

ooin 

OOO 

oo-i- 

ooo- 

00.0 

OOfNJ 

00-" 

OOro 

oo— 

o  iioo-r 

oo-o 

ooo 

OO-" 

OOO 

OOI^ 

ooin 

oocr 

ooco 

ooo 

1-  11  r-«io 

•t^o 

0>-<0 

r-roo 

ooroo 

-o~oo 

-1— o 

inino 

oo— 

—c— 

11  o  1    • 

r~      • 

1^  1    • 

CD  1     • 

in  1    . 

<\J—  • 

CM-.    . 

r-  i    • 

in-<  • 

1-  1    . 

II—     o 

o    o 

-o    o 

-1     o 

0-     o 

o>    o 

o    o 

-t     o 

^r    o 

in    o 

111^     1 

-o 

in     1 

O       1 

O        1 

o 

I-* 

in      1 

in 

in      1 

UO 

II 

t-i 

(M 

rg 

fM 

ra 

1- 

oil 

13 

-<  II   •  • 

•    • 

•  • 

•    • 

•  • 

•    • 

•  • 

•  • 

«  • 

t  • 

«  • 

3 

11  oo~r 

oocr 

oo-^ 

ooco 

oor^ 

oo-o 

ooo 

OOfM 

OOro 

OOCT- 

OOsf 

Z  II  oorvj 

OOfM 

ooo^ 

oo-i- 

oo^ 

oooo 

ooa> 

oooo 

OOCO 

oor^ 

ooin 

>- 

3  II  o^-"-^ 

O-rjrO 

irvm  — 

-OrO-J 

in-<o 

t^O(\J 

in~i-  — 

CT-  — 

inr-i— 

o-  — 

o>r-o 

OCMOO 

a  II  a>  1    • 

O        .^-O  1     • 

—  1     • 

O-  1     • 

O!          •«0          • 

-1-        • 

•*■      • 

in      • 

ro      • 

1-    •   •    • 

II  t^    o 

o    o 

in    o 

o    o 

o    o 

o    o 

•->    o 

in    o 

in    o 

in    o 

o»    o 

o«ro 

II         1 

-<      1 

r>j      1 

<M        1 

nj 

(M 

CM 

U.CM 

II 
II 

0>  II    •  • 

>-< 

O 

.  , 

.  . 

.   . 

,  . 

,  . 

■     ,    , 

,  , 

,  , 

,  . 

,  , 

(- 

M  ooo 

oo-t 

oor- 

ooa> 

OOP- 

ooo 

ooin 

oocg 

oor- 

oooo 

ooo 

z 

2  II           O 

OOC7> 

00<M 

OO-f 

oo-r 

o    o 

oocr 

OOCO 

oo-o- 

ooin 

oom 

o 

r3  II        o 

OrOsJ- 

-OC\J-< 

OrHO 

in— o 

—    o 

CTfSjO 

cr-<-< 

•cror" 

OlSiro 

-o-^o 

a. 

OC  11              • 

'-*        •♦^  1     • 

IVJ        • 

o>  1    • 

o>       • 

0>  1     • 

>r      • 

-r      •»  -o      •»<»>      • 

-ooinoooooo 


CO  II    • 

.  • 

•    . 

.   < 

•     > 

•  • 

.    . 

.  • 

,  t 

•    a 

.    • 

l-O^O 
OCM 

II  ooo 

oo~i- 

OOO 

ooo 

oom 

oo-*- 

oor- 

OOCM 

ooo 

OOO 

OOO 

z  II  oo-r 

oo-o 

o    o 

o    o 

ooo 

OOro 

oo-r 

OOOO 

o    o 

OOI~- 

OO-O 

< 

O  II  coogcM 

CO  — — 

CO      o 

o    o 

COCMO 

oor-co 

CM— o 

o— — 

-r    o 

r--  — 

— oo 

ccua- 

•  »o      • 

-o       • 

p-H            • 

o 

O         '^O 

-J-      • 

>»• 

in  1    • 

-1-      • 

II  r- 

o 

-o    o 

m    o 

o    o 

o    o 

O      O 

—    o 

in     o 

in     o 

in     o 

o    o 

3 

II 

1 

f-H 

IM 

CM 

CM 

CM 

1 

CM 

oo-ruj 

II 

f-l 

-ICM      Z 

II 

_l        o 

r-  II   • 

• 

•    • 

•     • 

•    • 

•    • 

•    • 

•  • 

•  • 

•  • 

*  • 

•    • 

<       z 

II  oo>r 

OO^f 

oo— 

OOO 

OOrO 

OO  — 

coo 

coo 

OO.-o 

ooo 

ooo 

2  II  00(Vi 

ooj;. 

ooo 

coo 

00^1• 

coy- 

O.J  o 

r_:  n  .Nj 

C  O  :o 

CO  — 

oo-c 

OOO 

Z3  II  -"- 

■I^H 

o  — 

— ,-o— 

r-.-MO 

Oro  — 

in^- 

oco.-o 

^  vj-r- 

.Ar-t-H 

•-r  -Ti~- 

— oo 

ooo 

a  iio 

• 

O  1     • 

(^       • 

—  1    • 

O         • 

o      • 

o      •^^^l■  1    •»  -r 

in  1    .«.!■ 

CM  ino 

II  CO 

o 

■o    o 

in    o 

O     o 

O      O 

o     O 

—    o 

m     o 

in     o 

in    o 

o    o 

•    •    • 

II 

1 

r~t 

(M       1 

CM 

CM 

CM 

t 

1 

CM 

oo— 

II 

i-c^cjroc 

on   • 

• 

•    • 

»     • 

•    • 

•    • 

«  • 

•  « 

•  • 

•  • 

•      9 

«    • 

ZUJUJUJ 

nooo 

oo<»- 

ooo 

ooo 

oor^ 

oom 

ooo 

OOCM 

OOro 

OOI^ 

ooo 

o>» 

z  no 

o 

oo-o 

o    o 

o     o 

oo^j- 

oo«i- 

o    o 

OOOO 

OOOO 

OOro 

o     o 

ca-ocq 

Z)  II  o 

o 

-o— — 

CO      o 

o     o 

in— o 

^ro  — 

—    o 

O  — — 

in— 

inroj> 

CM      O 

QC  no 

t 

o  1    . 

-o       • 

—1        • 

o  1    • 

o       • 

o       • 

<•         • 

-a-      • 

in  1    .^m      • 

II  00 

o 

o     o 

in     o 

o     o 

o     o 

o    o 

—    o 

in    o 

in     o 

in     o 

o    o 

II 

1 

■-H 

CM 

CM       1 

CM 

CM 

1 

CM 

Ui 

» 

f-t 

1— 

II 

o 

in  II   • 

• 

«    • 

•     • 

•    • 

«  • 

•    • 

•    • 

•  • 

•  • 

•  • 

•    • 

2 

II  oo-j- 

oo>i- 

oor- 

ooo 

OOI^ 

OOI^ 

OO.-M 

oo-r 

oom 

OO-O 

coin 

Z  II  OOINJ 

oo-o 

oor-j 

o    o 

oo-j- 

OOxf 

OO-T 

oo-o 

OOCO 

oo— 

oo  — 

Z)  II  CT-  — 

-o- — 

0(-sl  — 

o    o 

in— o 

(M  — O 

~rro  — 

OCMCO 

iri  — 

~r-iT^ 

-l-CMO 

O                  • 

I3i  IICT^ 

• 

O  1     • 

r-      • 

f4            • 

o  1    • 

o       • 

o       • 

in      •«■-»■      • 

in  1    •«ro       • 

o                ■-? 

II  r- 

o 

-o     o 

in    o 

o    o 

o     o 

O      O 

—    o 

in     o 

JA      O 

-n     o 

o    o 

o 

II 

1 

1 

t~i 

CM 

CM        1 

CM 

CM 

1 

CM 

CM 

II 

f-< 

1                   -O 

N 

1                  — 

•4-11   • 

• 

•    • 

•  « 

•    • 

•    • 

•    • 

•    • 

•  • 

•  • 

•   • 

•    • 

1 

II  ooo 

oo-t 

ooo 

ooo 

ooin 

OOO 

ooc~ 

OOCM 

OOO 

ooo 

ooin 

Z  II  oo-j- 

oo-o 

o    o 

oo~i- 

coo 

o    o 

OO-J 

OOCO 

o    o 

o    o 

oo  — 

z 

3  II  noo 

0(\J 

CO  — — 

CO     o 

oo-o 

a-.r^O 

—     o 

O'^c:- 

r-*  — — 4 

-1-     o 

CO     o 

OCMO 

»-« 

Of  II  O 

•  *  o 

-0        • 

•-'  1     * 

o        • 

o 

O  1     • 

vT   1      • 

-r 

in       • 

CO   1      • 

II  r- 

o 

-0     o 

in     o 

o    o 

o     o 

o    o. 

—    o 

ir.     o 

in    o 

in     o 

O      O 

Z              C£ 

II 

1 

•—1 

CM        1 

(M 

CM 

CM        1 

1 

CM         1 

O              OC 

II 

r-4 

^                UJ 

II 

t- 

rri  II    . 

• 

•    • 

•  • 

•    • 

•    • 

•    • 

•    • 

•   • 

•  • 

•  • 

•     • 

«*           m 

II  oo<i- 

ooo 

OOr^ 

ooo 

ocin 

ooo 

COCM 

co-i- 

oor- 

OOO 

OOCO 

—           I/) 

Z  II  OOCVJ 

o     o 

CO-O 

OOs)- 

ooo 

o    o 

oc>>- 

OO-D 

oo-o 

oor- 

OOCM 

>          o 

3  II  — — 

f-     o 

I-— O 

oo— o 

00  (MO 

—    o 

COCO  — 

■Cc-y;ro 

-OCVJCO 

1^— — 

ocoo 

UJ              cc 

DC  II  O 

• 

c 

-f/  1     • 

—  1   • 

O         • 

o 

O  1     • 

~J-  1     •*  -3-        •^in  1    . 

CVj  1      • 

O             O 

II  00 

o 

-o     o 

in     o 

o    o 

O      O 

o    o 

o     o 

m     o 

n    o 

in     o 

O      O 

II 

—      1 

CM         1 

CM 

CM 

CM         1- 

1 

1 

CM         1 

II 

II 

(M  II    • 

— 

, 

,  , 

,  . 

,  , 

.    , 

,    , 

,     , 

,  , 

,  . 

,  , 

,  , 

II  OOO 

ooo 

oo— 

ooo 

oOin 

oor" 

cor- 

oo-r 

OOCO 

OOCO 

OOO^ 

Z  II  O 

o 

o    o 

ooo 

ooo 

OOO 

oo-r 

oo>r 

oo-o 

OOCO 

ooin 

oo  — 

3  II  O 

o 

P-     o 

— en- 

— CslO 

^CMO 

CO  co- 

CM—o 

-orsico 

in  — 

OPMCO 

>rcMO 

a  II  o 

• 

o       • 

1-      • 

CM         • 

O  1     • 

co  1    • 

o      • 

-»■  1    •»-J-      • 

o      .«co      • 

II  00 

o 

o    o 

in    o 

O     O 

o    o 

o    o 

—    o 

in    o 

in    o 

in     o 

o    o 

11 

«-4 

CM 

CM       1 

CM        1 

CM 

1 

CM 

II 

i  .  .>ro 

II 

ooo— o 

—  11   . 

« 

«    • 

•     • 

«    • 

•    • 

•    • 

•    • 

•  • 

•  • 

•  • 

•    • 

OOOCCM 

II  oo~i- 

ooo 

OO  — 

OOO 

OOOO 

oom 

oco 

oo-r 

OOro 

ooo 

oor- 

OCDX    .    • 

Z  II  00<M 

o    o 

coo 

oo-r 

OOC<1 

ooo 

o    o 

oo-o 

oota 

oor- 

oor- 

CMrO- OO 

=>  II  — 

r-     o 

inci- 

o— o 

—  in  CM 

OCMO 

—    o 

-OCMCO 

m  — 

f--— 

CMOO 

mm 

a  II  o 

• 

o       • 

-O  1     • 

(M        • 

o  1    'Hm  1    . 

o       • 

~t  1     •*>!■        • 

in  1    • 

CM-    • 

OOCO 

II  CO 

o 

■o    o 

in     o 

o    o 

o     o 

o    o 

—    o 

in     o 

in    o 

in    o 

O  1  o 

CM  CM 

II 

f-4          1 

C--J 

(M        1 

CM         1 

CM 

1 

1 

CM       1 

— — 

II 

1-  II    • 

. 

, 

, 

, 

, 

. 

, 

, 

, 

, 

l-l- 

OHO 

o 

o 

o 

o 

o 

o 

o 

o 

o 

o 

oo 

:2  II  o 

o 

o 

o 

o 

o 

o 

o 

o 

o 

o 

33          3 

II  o 

r- 

00 

o 

-o 

•-* 

•— 1 

CO 

-1- 

CO 

CM 

o 

u-  n  o 

o 

-o 

•— 

o 

o 

o 

-r 

-1- 

m 

(O 

U.I-OC      _J 

UJ  1100 

•o 

in 

o 

o 

o 

#~l 

in 

in 

in 

o 

UJCQC      _i 

oi:  II 

—4 

CM 

(M 

CM 

CM 

CM 

OCSIUJ      < 

II 

h- 

t- 

»- 

t- 

1- 

h- 

1- 

1- 

>~ 

1- 

tH 

1- 

•  II 

z 

■z 

Z 

2 

z 

Z 

z 

z 

z 

Z 

•-►-h-ZX 

Cll  — 

UJ 

r-     UJ 

o     UJ 

in     UJ 

>r    UJ 

in     UJ 

)-4         UJ 

in     UJ 

in    UJ 

rri     UJ 

oaoo< 

Z  II  —oco 

(J-oCO 

~tocu 

ooco 

fOQCO 

mao 

in  OCO 

OOCO 

CM  oco 

OOCO 

H-f— h-^^ 

II  ino 

CIO 

oo 

oo 

coo 

coo 

OO 

CDC 

ino 

OO 

cc  II  c^aa: 

tnc^oc 

mac  a; 

■J-Q'OC 

inococ 

inotoc 

o-aa: 

(\jq:oc 

COCCQC 

>roCQC 

>-cey- 

1  11  O-QCIU 

co-iu 

OOfUJ 

o^iu 

oofuj 

OQCOI 

r-ecuj 

r-ciruj 

r-nCLu 

CdTUJ 

130CZ 

o  11  CMjja. 

CLUQ. 

OUQ. 

COLLI  Q. 

OUJCL 

OiJCL 

cmujol 

OUJO. 

OLLIQ- 

rOiiQ. 

3UJO 

II 

t-cb:^ 

11  — 

(N 

n1 

^r 

in 

-O 

r- 

•x. 

o 

O 

n^^i 

Tests  of  Coupled-in-Motion  Weighing 41 


II    .  • 

»-  II  OOI^ 

oo— 

OOl*> 

ooco 

OOrsj 

oor~ 

0005 

OOO- 

oor- 

000- 

O  II  00(M 

OOl^ 

oo-o 

oocc 

ooo 

OOfSJ 

CiC3-> 

ooo 

ooo 

00-" 

>-  II  'VJCD— 1 

-CO'-- 

J\^(\l 

f\j(Njr\j 

~0O'-' 

ooco-' 

^-<o 

a"-o 

<M<3-< 

rgtvo 

II  a-—  • 

sOrO    • 

-rm  • 

mir\   • 

•OINI     . 

30-1    • 

m        • 

-O  1     • 

03    1      . 

O         • 

II  O  1  o 

03       O 

r-     o 

O  1  o 

J-     o 

O  1  o 

irv     o 

03      o 

u^      o 

O      O 

II  -r      1 

O- 

— * 

m       1 

<y 

-T        1 

lA 

O        1 

U-v         1 

O 

II  -• 

^^ 

^-4 

_^ 

^^ 

'-t 

^^ 

^^ 

O  II 

,     . 

.       . 

.   . 

.  . 

.    , 

.     . 

.  , 

.    •             .    • 

IIOOO      OO— •      00<NJ      OOrO      OO-l-      OOr^      0003      OO-^      OOm      OOO      OOf\l 
'HO      O      O^f^      OnOCT       O^^f       O-JT^      O-O— '      OOO      OOC7*      oa3^J-       O      O      OfVirO      t— 

Ml—*     o     r^m— •     %o^m     >j-srfNi     Gor<>— «     ct»— •— i     >t     — <     vO— *o     03  i  — -     o     o     f*^>to     oooo 


IIOOIM  ooo 
Z  II  oo— '  0-Tr~ 
3  II  cor^fM  in—'O 
Ct  II  O  I     •  ■»  u        • 


lOOr*!      ooo      OO''-      ooo-      OOr"      OO-T      0003      OO— •      OOrn      OOO      OOO      Of 

10003    o-j-r-     0.00     o-ro     o-frvj    0.003     OOO     ooo-     ooJ-r     o     o     0030     < 
ir-vj-pg     a-»— *o     inrom     — ir-->4-     i-^rg— *     o^^Nj— «     ^     ^     o— 'O     03  I  ^     o     o     — ir-o 


-"     o 

33       O 

0-      o 

~i-     o 

in     o 

o     o 

m     o 

o 

o 

0> 

o 

m-.o 

-1         1 

-•     1 

OJ 

a 

oor- 

oo-r 

OO-T 

oo^ 

OC03 

OO-i 

OOtxj 

ooo 

ooo 

z 

o  oo 

ovro 

o-rr- 

O  OOD 

ooo 

ooo- 

zjao<\i 

o 

o 

0030 

o 

lOr^r^ 

oo3>r 

a3r^-> 

03(\J— 1 

-r     — ■ 

O-iO 

1- ir^ 

o 

o 

— ir-o 

a. 

r-       '< 

O  1     •» 

■r 

O   1      • 

in       • 

CO   1      . 

in  1     • 

•»  o 

• 

t\j 

1    • 

-•     o 

oo     o 

o-     o 

■J-      o 

in     o 

o     o 

in     o 

o 

o 

0- 

o 

— * 

-•      1 

—1 

^      1 

-■      1 

1 

— « 

(M 

1 

_i 

M  O    I      •*  Oj 

ii-foc>o^oooocr 
„  ^      I      ^  -<  ^      I      ^ 


II  ooo     oo-^    OG'O    oo-f     oo-^    oof*^     oorsj    ooo    oof*^     ooo     oo-j- 

;?iicor^     o<rr-     o-o.-^     o^r-o     ostJ^     oo^     o^f^     o     o     oocj-     o     o     003^  000 

3  II  o— *o    h-f^^    fc^-^    oco^     ^o— *o    o*^^    i-oio     h-     o     oji-^     o     o     miAo  000 

C£.   »  ^   t       '        CO           •r-           •OI*»nJ-           'Ol^iJ^           •(!)           •Lf>           -O           -rNJl*  fNilTNO 

iiNrocro^ocoocrO'J"Oir»oooir\ooocro  ••• 

11  -^t—*                -<                ^i^                -»!                   I-*                           (^                fNJi  OO-^ 


" 

t-QiriXQC 

ZlU'-UlU 

HOO-T       000 

0003      oot^      OOro 

oo<r 

OO.-M 

000 

ooiM     000 

000 

ziiootn     o>r(M 

oof^     o^^-in     o>rrsj 

0003 

o>j-i^ 

0     0 

oo3r>j     0     0 

0030 

Q-oao 

3110mm      >3-       0 

r-inNj-     tsiom     r-rvj-i 

aD(\j-i 

ro   1   0 

r-     0 

(--•r"      0      0 

-.f-O 

QC    11  0    1       •«  CO           • 

r-       .«  0  1    •»  J- 

0  1    • 

in       • 

05       • 

in  1     •»  0       • 

t\j  1     • 

—I      I      -1 


a.         — • 


in  It    •   • 

•    • 

•   • 

•    • 

•   • 

•   • 

•   • 

•  < 

•  • 

• 

•  t 

3 

II  OO-" 

OO-" 

oo-r 

COrO 

OOro 

oom 

00=0 

000 

ooin 

000 

OOsl- 

z  II  oo~r 

0-T<M 

OsjTO 

o.i->r 

o>ri\j 

00-" 

000 

0 

C 

OfMro 

0 

0 

CM  CM 

3  llrorg-i 

=)>J-nj 

-•  1  0 

-1-~J-<M 

r-(\j-. 

o----. 

sr     -< 

0 

0-     0 

0 

0 

njroo 

0 

• 

c:  II  -■ 

CO       ••»  r^ 

0  1    •»  sr      • 

0  1    • 

s\       • 

a; 

• 

Ul              • 

0 

fO 

• 

0 

0 

II -l-      0 

0-     0 

— •    0 

03    0 

0-     0 

-I-     0 

in     0 

0 

0 

in     0 

0 

0 

0- 

0 

sT 

II -< 

-H 

— <      1 

-<     1 

-H 

-■      1 

—4 

— « 

S\ 

II 

—4 

1 

0 

II 

1 

(M 

j^  II    .    . 

«   • 

•  • 

•     • 

•   • 

• 

•   • 

• 

•     4 

1 

II  OOd 

OO-i 

oor- 

ooco 

OOIM 

com 

COIM 

000 

oom 

COO 

OOIM 

z  II  0003 

o^r- 

000 

o-i-o- 

oooc 

oo-> 

OsTr- 

0 

0 

000  sT 

0 

0 

OX 

iin 

z 

3  II  '--J-IM 

r-f^— J 

inrof 

miniM 

m-.o 

O-i-i 

m  1  0 

p^ 

0 

X    1  —1 

0 

0 

IMOO 

o-  II  0   1     '«  CO         • 

r-       •itoi    '«  -t  1    • 

0  1    • 

in 

CO 

• 

in       • 

0 

nj  1 

• 

II  ~r     0 

c    0 

-.     0 

CO      0 

o>     0 

sr    0 

in     0 

c 

0 

in     0 

0 

0 

0- 

0 

z 

CH 

n—      1 

>-* 

•~* 

-•     1 

— •      1 

-1     1 

1 

-« 

1 

^^ 

(M 

1 

d 

OC 

II 

^_ 

m  II    •  ■ 

•    • 

•   • 

•   • 

•  • 

•  • 

•   • 

• 

•   . 

• 

«     , 

<t 

SO 

II  CC— 1 

OOr'l 

000 

0000 

00  J 

co>r 

OOfM 

OO-i 

ocin 

coo 

00|s- 

— . 

I/) 

Z  II  0  0  nT 

o>rr- 

o~j-o- 

o-rco 

o-j-^- 

oo.^ 

O-T"^ 

000- 

orsjO 

0 

0 

OlM-< 

> 

0 

:;  II  CT-i-vj— 

f^C^^ 

CDflMNJ 

inr<-i-« 

Xro-. 

XIM— • 

m  1   0 

0- 

■•0 

0-     0 

0 

c 

-4<MO 

UJ 

oc 

0  II  c  1    ■ 

C        •«  -C  1     .«■  0  1     • 

-r      • 

C  1     . 

m       . 

CJ 

• 

in 

c 

rrs 

• 

c 

0 

II  .J-     0 

0-    0 

-.       0 

00     0 

OS     0 

-r     0 

in     0 

0 

0 

XI    0 

0 

0 

0- 

0 

II  -■      1 

-«         1 

-1      1 

nj 

rv,  11    .   . 

II  000 

00c 

OOIM 

OCX 

OOro 

OOfM 

OOIM 

000 

ooin 

cod- 

com 

-  iioor- 

O^TiM 

aoo- 

O-TOO 

Osrnj 

oosr 

OsT"^ 

0 

0 

Onjm 

000 

oiMin 

r)  11  (\j-.o 

Ofvj-i 

O^Tr^ 

ini»-  — 

r^fM— 4 

0  1  0 

m  1  0 

r- 

0 

o-    c 

•1^^ 

0|s-0 

a;  II  ^^       • 

03         • 

r-      -tto  1    • 

•J-       • 

^^      • 

in       • 

co 

• 

in      • 

0 

• 

rf\ 

« 

11  sr     0 

cr     0 

-.    0 

CO      0 

(f     0 

sT      C 

in     0 

0 

0 

in     0 

c 

c 

0- 

0 

II  ^^ 

'-t 

— * 

-1     1 

^H 

— '        1 

1 

— • 

—4 

nj 

II 

•  •  • 

XO 

II 

00000 

^^11    •  • 

*  * 

•  • 

•    • 

•     • 

•    ■ 

• 

•  • 

• 

•  < 

OOOOru 

1100  — 

000 

0003 

OOlNJ 

000 

OCtSs' 

ooou 

OO-i 

com 

000 

CO" 

xr*— 4 

•    • 

z  II  oo^r 

0~»nj 

00-^ 

o,j-i\j 

OsTtM 

OOJ- 

000 

ooo- 

O.Mm 

000 

OIMO 

xrs-— ' 

00 

3  II  cog-i 

~T       0 

CT-I^O 

03   1  0 

•n     0 

0  1  0 

-r     -< 

CO- 

'C 

0-     0 

4—4 

r-  CO 

rgiM  1 

1 

:i  11  0  1    • 

CO          • 

r-      ••!;  c      • 

si- 

'-t        • 

OT 

XI         • 

c 

• 

rr\ 

0-0- 

II  ^     0 

0-    0 

—    0 

CO      0 

0-     0 

sr     0 

in     0 

0 

0 

m     0 

0 

0 

0- 

o 

II  -1      1 

^^ 

'" 

— ■         1 

"^ 

-■      1 

-"- 

II 

, 

, 

. 

, 

, 

, 

, 

, 

^^ 

0  II  0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

3t  no 

0 

-1- 

-J- 

0 

0 

sT 

0 

X 

0 

X 

jcs 

X 

II  — * 

m 

'-* 

cc 

sr 

0 

ro 

r- 

OJ 

0 

X 

0 

U.  II  -1 

00 

r- 

0 

>r 

^^ 

in 

X 

J-s 

0 

tM 

u-t-ae 

-J 

lu  II  sl- 

c- 

—* 

CO 

0- 

~T 

in 

0 

in 

0 

c- 

UJOOC 

-I 

oe  II -< 

^^ 

-^ 

'^ 

-^ 

'-* 

— * 

"4 

nj 

ors-aj 

< 

II        1- 

h— 

y- 

1— 

1— 

>— 

1- 

1- 

1- 

>— 

^H 

^ 

•  II          z 

Z 

z 

z 

z 

Z 

Z 

^• 

^ 

z 

V— Wl— 

r-x 

0  iim     Lu 

r-     LU 

0-      UJ 

0      UJ 

0-      UJ 

0       UJ 

sO             UJ 

0- 

UJ 

0      UJ 

X 

COOl-X 

z  II  -■  at  0 

-TOCO 

cocio 

ooco 

(MatO 

—  OfO 

J-OCO 

I-3f  0 

XoCO 

—  QCO 

i-i-t-ci-s: 

II  nTO 

00 

f^C 

oc 

r-o 

-ro 

src 

sTO 

rrso 

roc 

ir  II  0  r<  rr 

Orro^ 

0:^2- 

Ccrof 

oo:.-: 

coi-c^ 

occ 

;  1' 

Co-:y 

-a: 

i-a 

'^ 

<    II  —  -^    U-' 

r-j'nu.- 

-■cu; 

—  cir  lu 

sjcr  lu 

-TI-LU 

-<irj. 

—  Jt'O.' 

— .-.-  u 

r-ci-iu 

T  -If 

.■• 

ijiiouja     nci-'O.     Ojja 


42 


Bulletin  654 — American  Railway  Engineering  Association 


ooa> 

OO.0 

ooo 

OOr-< 

OOIM 

OOir> 

oooo 

oooo 

oor- 

OOO 

ooo> 

ooo 

o    o 

OO--" 

oo>i- 

OOf^ 

OOI>- 

OO-H 

ooo^ 

ooin 

^~i-o 

O-ro-" 

>r    o 

oroo 

CM^rg 

^if\0 

in-JO 

(SJfNJO 

t~^^ 

inino 

<\j^  • 

Oro    • 

(—1      • 

00        • 

a>>i-  • 

O  1     • 

intM  • 

r~      • 

r~^  • 

o>  1    . 

-•    o 

00      o 

r-    o 

o    o 

m  1  o 

•^      O 

ir>    o 

00      O 

lA  1  O 

o>    o 

>»■ 

a> 

I-* 

00 

0^       1 

^     1 

in 

o 

irt     1 

(J-     1 

i/> 

'^ 

f-4 

•^ 

'" 

"* 

"" 

'" 

OOCJ 

ooo 

oo^i- 

oooo 

OOvO 

OOCO 

ooo> 

OO-l 

oom 

ooo 

00-* 

3 

OO-H 

0<J-fvJ 

o>rro 

0>000 

oom 

O-tr-j 

o-ooo 

ooo< 

O00>}- 

O      O 

ooo-r 

t- 

oifncNj 

>r    o 

-<  1  o 

O-"© 

O-l-rg 

-1      O 

m-<c\j 

O-iO 

CO  1  -- 

O     o 

fOino 

oooo 

o  1    •»aj      . 

r-      • 

w-t           • 

-»■  1    •«-<      • 

in      •♦00  1    . 

in 

o       • 

IM  1     • 

t-  •  •  • 

>!•      O 

ON     o 

->    o 

CO      o 

o>     o 

•4-      O 

m    o 

o    o 

in     o 

o    o 

o-    o 

o>-<o 

-•       1 

^     1 

'^     I 

^     1 

' 

rg     1 

u.nj 

o 

ooo 

oo-« 

OO-i 

OOC\l 

oocr 

OOrj 

ooo 

OO-H 

oom 

ooo 

OO'^ 

2 

oor~ 

o>rf>- 

o-Oin 

O-rrvj 

O-Of^ 

oo^r 

oo-o 

ooo^ 

OOOnJ- 

o    o 

0(\J0 

o 

<M-'0 

r-m^ 

r>j     o 

00  1  o 

oo^orn 

O  1  O 

>0(\J-J- 

00 -HO 

CO  1  —• 

o    o 

a>    o 

a. 

^      • 

CO       • 

1^       • 

o       • 

fO    1       ««--H           . 

iTk        •»00        • 

in       • 

o       • 

nj       • 

H>i-oo>0'HOcn 


o    in    o    o    o    in 


•  • 

•  • 

•  • 

•  • 

«    • 

•  • 

•   • 

•  • 

•  • 

•  • 

•  • 

t-ON-lO 

OOnj 

oo-< 

00-4 

OCM 

oor-- 

oooo 

OOO- 

00-4 

oom 

ooo 

OOI- 

OIM 

oo-< 

o.j-r- 

o.oin 

O.TIN 

o-ooo 

O-f  (\J 

O.0C0 

ooo- 

ooo-r 

o    o 

Oooro 

< 

COfOCNJ 

^-^o-< 

C\J      o 

00  (  O 

O^incNj 

'-'     o 

J\r-4<\l 

,0-"O 

00    1    -4 

o    o 

-J-'J-O 

O  1     ••»  .0 

r-      • 

O        • 

f<1    1       .It-H           • 

in       •■ 

tt-00  1     • 

in      • 

o       • 

<\J  1    • 

■J-     o 

a~    o 

^    o 

X>      O 

o.    O 

•r    o 

in     o 

O     o 

in    o 

o    o 

ON      O 

X 

'^    1 

-H       1 

'^     1 

-t     1 

1 

rsj      1 

ooinai 
-IfO     z 

<       z 

OOfvJ 

oo-« 

OO-i 

OOf<^ 

OOf-- 

oom 

OOON 

coo 

OOnj 

ooo 

oo-o 

oo-< 

o<j-^- 

O-Oin 

OvOro 

O-ooo 

o-c^ 

O-CX 

o    o 

003  <S) 

ooo 

ocoo 

ooo 

^j-cicg 

r-fo-i 

CM      O 

cy     o 

o^incsj 

0<-i-< 

in— i>j 

1^     o 

t~^rr, 

0--H^ 

a3  1  o 

ooo 

-H         •■tt-OO         • 

t»-      • 

o 

CO  1     •»o  1     • 

in      •■ 

»CD         • 

in  1    •*  ON  1    • 

rvi       • 

niino 

-J-    o 

o    o 

-H        O 

CO     o 

o>     O 

•4-      O 

in    o 

o    o 

in    o 

o>    c 

0-     o 

•  •  • 

-<     1 

-H          1 

1 

1 

-^ 

oo-^ 
zoiujai 

OOO 

ooo 

oo— 

oom 

oo-o 

OOOO 

OOCT- 

oo-< 

oom 

ooo 

oor- 

o>>> 

oor>- 

0-J-(NJ 

O-Oin 

O-Orrt 

O-Of" 

O-TCSt 

O-OO 

OOON 

OCDnT 

ooo 

0(NJ-< 

CLOOO 

(M— "O 

nOCNJ'H 

<M      O 

ON      o 

O-TtVJ 

^      O 

-oiNj-r 

co^O 

00  1  -J 

C'-'-i 

-<(Nn10 

^      • 

00         • 

r-      • 

o       • 

>r  1    ••»-< 

.n      •  «•  00      • 

in      • 

Cf  1     • 

m      . 

O      -H      O     CO      O      ON      o 


in    o    o    o    in    o    o^ 


lOO'-'      00'-<  ooo> 

100-3-      OnJ-C-  0»1--< 

irorvi^     t— m-j  o-^-^ 

l-H       .00       .  r-  I    • 

!<■      O      O-      O  -H      o 

l*H  -^  -H     I 


oo^- 

OnTI^ 
r--iO 
O  I     • 


oo-o  OOfO 
O-Of*^  o-c»-< 
0-*-M      ON>H^ 

-*•  I    ♦■»o  I    • 


^     I     ^     I     -I 


in    o    o    o    in 


oo<nni    ooo 
ocoonJ     ooo 

n  I    •*o>  I    • 


OOnI- 

ooo-r 

t«iino 


loom  oo-H  oooN 
I  oooo  o-j-ni  o.*-< 
nn-4-nj  oo-j-fM  o>-<-< 
I  r-<  •»oo  •j.'r^  I  • 
InT      o     O-      O     -H      o 

1^  ^  ^1 


oo-o     CO-*- 

OCON 

oo-< 

oom 

ooo 

OOI^ 

ON0r<>     O-Coo 

c-cc 

coo- 

oeD-r 

coo 

C(Sl-H 

Ontim     ao(M-i. 

OPsi-.r 

00 -HO 

00    1    -H 

0-^-< 

-H(NJO 

-J-  1    •*o  1     • 

in      • 

*  X         • 

m      • 

ON     1          • 

m      , 

o    in    o    o>    o 


looni  oonj  OO-t 
lOO-H  o-J-|~-  O-i-rr, 
I  Nj-rorNj  ONinnj  -«  I  c 
I  -<      •*oo      •■»r^       • 


OCfM 

oom 

oorj 

OOON      OOfO 

oor^ 

OOO 

Ooni 

ONl-ro 

OnO--<^ 

O-OnI- 

o-ooo    oooo 

OD-t 

OOO 

Onj(»^ 

-Orvj-H 

(Nirg-H 

o  1  o 

in*Hr-j     O-INI-H 

00   1   rH 

CN-<^ 

O^-tC 

O  1    . 

•J-  i     • 

^H             • 

in      •«•  cc      • 

in      • 

C-  1     . 

rrv       • 

<-•     I     ^     I 


inoootnooNOON 


a        -H  H 


—  OC  II 


cow 

OO-H 

OO-H 

00=0 

coin 

OCX 

ooo 

oo^ 

oo^'^ 

ooo 

coin 

OO-H 

o-i-r~ 

o-oin 

0-003 

OnOX 

OnJ-oj 

com 

ooo- 

ox-4- 

o 

o 

ocNjin 

-j-rotN 

1— fO-H 

fSI 

O 

O-HO 

-<ro^ 

-H 

o 

r-rri-O 

nO- 

<o 

X    1    -H 

o 

o 

-OIN-O 

—      •»oo 

• 

f- 

• 

-H 

• 

-3-  1 

• 

f-H 

in 

•  «  X   1 

• 

in       » 

o 

m      • 

•4-     O 

o- 

o 

r-4 

o 

to 

o 

o> 

o 

-r 

o 

in 

o 

o 

o 

in     o 

o 

o 

ON     o 

1 

1 

1 

CnJ 

•  •  •mo 
coooo 
oooorg 

OOfM 

00'-» 

OO-H 

COX 

OOnO 

oox 

ooo- 

oco 

com 

ooo 

ooo 

COt-Nj-f-      •      • 

OO-- 

O-rr- 

o-oin 

O-OX 

o-om 

O-l-og 

o-o-o 

o 

o 

OXr>l 

o 

o 

0(N|n1- 

XON     oo 

NTrt-irNl 

h-f 

^>-* 

<\J 

o 

O-HO 

OnJ-(NJ 

-H 

o 

-OOnInJ- 

t- 

o 

r-*-Hrrt 

o 

o 

■J- no 

.■MINi 

-H        •«  00 

• 

r- 

• 

-H 

• 

nT     I 

•#  -H 

• 

in 

•  »  ra 

• 

in  1    •  <■  o 

• 

i-O        . 

ONO- 

Nl-            O 

ON 

c 

-H 

o 

CO 

o 

ON 

o 

>J- 

o 

in 

o 

o 

o 

in     o 

o 

o 

ON      o 

r-jPNi 

' 

' 

(Vl 

t-i- 

O 

o 

o 

o 

o 

o 

o 

o 

o 

o 

o 

oo 

O 

nO 

nI- 

nI- 

nO 

>o 

nI- 

o 

X 

o 

X 

S3        je 

-H 

ro 

-H 

X 

nT 

o 

(O 

1- 

X 

it 

ra 

o 

-H 

00 

|N- 

o 

nI- 

-H 

in 

ro 

in 

o 

nj 

u-l— of      _J 

< 

o« 

i-H 

00 

0- 

■»• 

in 

o 

in 

o 

o- 

LUCOf       _) 

-H 

-H 

--« 

-H 

-H 

-H 

_4 

_4 

r-i 

OfZOJ      < 

»- 

►- 

►- 

1- 

1- 

►- 

>- 

t- 

(- 

(- 

-H 

H- 

z 

z 

z 

?■ 

?■ 

z 

z 

z 

z 

t-l-l-ZX 

in    lu 

r- 

liJ 

O 

LU 

o 

LLI 

ON 

lU 

nO 

LU 

-o 

Ol 

ON 

lli 

o     lu 

X 

LU 

COOO<.' 

-HCiU 

nTOCO 

oooco 

O-QCO 

njQCO 

-HQCO 

Nj-QfO 

r-ofo 

xofo 

-HOfO 

i-t-i-Q.2; 

•4-0 

oo 

mo 

oo 

r-o 

nI-O 

sTO 

nJ-O 

coo 

xc 

Oct  of 

'Ccccc 

cacoc 

C~L 

to: 

oof  of 

oof  « 

OO-Ct. 

oaa 

oorro- 

-'CCCC 

t-Of  H- 

-HOC  JJ 

rNinf'jj 

-HOT 

'OJ 

-'QtlJ 

-j-oi: 

ij 

— IQf  .JJ 

-HOfUJ 

-HfYUJ 

-HOf  UJ 

f-oruj 

OrrtZ 

OiUQ. 

inoio. 

OUJQ. 

O-JCX 

oiua. 

OL 

L/O. 

OJJQ. 

Ou. 

J1. 

O'JJO. 

f^L 

uc^ 

31U(J 

Tests  of  Coupled-in-Motion  Weighing 43 


1—  II  OOCT" 

oo^ 

oo>o 

OOlfv 

ooo 

oooo 

OorvJ 

ooo- 

oor- 

ooo< 

O  II  OO  J> 

OOO 

OOrO 

OO-i 

oo-r 

OO.XJ 

OOO 

QOO 

OO— ' 

ooo 

►_  II  043— t 

.OOr<i 

oo~* 

rOCT-tM 

inc-o 

OJ-O 

mo--" 

O'-^O 

r — lO 

00  .n*}- 

o>-o  • 

(Njm    • 

in      • 

—4            • 

•r      • 

O  1     • 

CO  1     * 

oin  • 

HO      O 

CO      o 

(~      O 

^      O 

-1-     o 

-<    o 

in     o 

00      o 

in    o 

'->     o 

II  O 

cr 

CO 

o- 

>!• 

in 

O       1 

in      1 

-f 

1/1 

II  ^ 

-H 

-• 

'-< 

-* 

'-' 

-* 

o 

3 

Oil 

^ 

^  ^ 

,  , 

,  , 

,  , 

,  , 

H  ooo 

OOrsl 

OOJ- 

ooo- 

ooo 

OOCT 

oooo 

OOO 

COfI 

ooin 

ooin 

?  M  ooo 

O-JT^ 

O-J-ro 

O-OCT- 

o-om 

o^-o- 

ooo 

O      O 

OCOsJ- 

ooiv 

oiNjnJ 

I— 

3  II  ^^^^ 

CMTVIN 

^  1  O 

iMrO-i 

•J-  1  o 

(\J-<0 

>f    -^ 

r-     o 

CO  1  -> 

f-oj- 

ino*^ 

OOOO 

q:  II  o 
HO     o 

00      •er-      • 
0-     o     -<     o 

00       O 

&•     o 
-"     1 

J-     o 

in      • 
in    o 

00        • 

o    o 

in      • 

in     o 

1 

~i-     o    o-     o 

inoo 
LLm 

II 

■^ 

o 

n 
O^  II    •   • 
II  ooo 

oorvj 

OO^ 

OOCT- 

OO^I■ 

OOtO 

ooo- 

oo-< 

OOro 

OOsT 

ooo- 

z 

2  H  ooo 

o-r.-M 

0.0.^ 

o«ocj> 

o-rr- 

00-" 

ooo 

ooo- 

OCOvT 

oo'n 

OiMf^ 

o 

SlirsirvjfM 
c^  II  O         • 

O-Oro      ^3•l^J<^J      r\Jrn— i 
C7^         •»l^         •■tt-^         • 

00  ro-" 

O  1      • 

m^f--j     oo^o 
in       •*oo       • 

00   1  ^ 

in       • 

Oinro     tMm^ 
^       .-innrM  • 

o. 

HO       O 
II  -• 

CT>      O 

^    o 

OO      O 

o>    o 

>!■       O 

'-'     1 

in     o 

o    o 

in     o 

~r     o            ~ 

o-     o 

INI 

< 

II 

3 

SO  II     •    • 
II  OOO 

^ 

^    ^ 

^  ^ 

,    , 

,  , 

«    , 

•  • 

«  • 

•    • 

(-•noo 

OOro 

oo-* 

OOO- 

oom 

OOrO 

ooo- 

oo-« 

ooro 

oom 

oom 

om 

z  II  ooo 

O-J-r- 

O-OiTi 

O-OO 

o-r(M 

OO-* 

oooo 

ooo- 

oco-r 

oooo 

C(MO 

< 

3  II  ^^,-<^* 

-ip-ro 

t\J      o 

•r  ^nm 

r-(M-> 

0--.^ 

in-oNi 

OD^O 

.O   1  --I 

in^rg 

0^4^* 

ex  II  O        • 

o>       •»  r-       • 

-H            •«  -J-            • 

O  1     • 

in       ••«■  CO       • 

in       • 

.-4       ••u  innj  • 

HO      O 

II  •^ 

o-    o 

_.      o 

00      o 

<T-     O 

J-      O 

-<     1 

in     o 

o    o 

in     o 
1 

>r    o           ~ 

o-     o 
rg 

3 

ooiniu 
_im    z 

'* 

_J          o 

II 

II  ooo 

^   ^ 

,  , 

^   , 

,   , 

,   , 

»  « 

•   • 

•  • 

•  • 

<        z 

oo^ 

oo-o 

com 

OOO 

OOOO 

ooco 

ooo 

ooco 

ooo 

ooin 

2  II  ooo 

OsTlNi 

o-om 

o-om 

0^(NJ 

0^<M 

ooo 

o    o 

OCOnC 

OOC' 

OiNjrsJ 

ooo 

3  II  (MCMiNJ 
ct  II  O        • 

oo         •»l-         • 

0-     o 
o 

ir\     o 
-1-      • 

r-4          O 

in      • 

r-    o 

CO        • 

CO  1  .-< 

in       • 

00  r-  J-     T^^--) 

OOO 
rgino 

HO       O 

CT-      O 

'-'      o 

00       O 

0-     o 

J-      o 

in     o 

o     o 

in     o 

1 

J-     o 

o-      <-> 

OO-* 

II 

i-c^oca: 

" 

^ 

^    ^ 

,  , 

,  , 

,  , 

«    » 

«  • 

ZUJLULU 

*0  II    •    • 
II  OOO 

oom 

OO-i 

ooa< 

ooo 

oooo 

ooo- 

oo--" 

oom 

oo-r 

ooco 

o>>> 

Z  II  OOO 

o-j-r^ 

o-o>r> 

ooo 

OnTINI 

o-j-.^ 

OOCO 

ooo- 

Oi~-Jro 

ooin 

ONI— 1 

a.ooo 

l;  II  ngpsjog 

-ii~-m 

t\i     o 

sJ-lA(^ 

0--rrM 

-"     o 

in^^iNj 

CO-iO 

o-    o 

Oinro 

h-00(NJ 

QC  II  O        • 

cr      •■ 

»r-       . 

-■          ••fr-J-          •*-' 

in       •• 

»■  CO         • 

>n       • 

^~*       •' 

tt  inr-j  • 

HO      O 

kT-      o 

-"     o 

CO      o 

c^     o 

J-     o 

in     o 

O     o 

in     o 

vT       O 

0^     o 

II  ^ 

II 

II 

inii    •  • 

II  OOO 

-^ 

'-' 

^ 

'^ 

f-g 

1- 

o 

OOtM 

OO"^ 

oo~r 

OO-i 

ooo- 

OOr-j 

OO'^ 

oom 

COO 

ooo- 

3 

Z'  H  OOO 

OsTiNI 

o-oo 

o-cirv 

o>rt~- 

o-ro- 

o-i-r^ 

ooo> 

ooo>r 

ooo- 

oiNir- 

O  II  ^-i-i 

o-om 

inrorr, 

fn^(M 

o-^o 

(NI-hO 

1^  1  o 

O— 'O 

X)   1   --< 

00  r--!- 

(Njm— * 

o 

«:  H  o      • 

o       • 

«-r- 

tt  -1 

» J-      • 

>-^        • 

n       • 

D   1      • 

n       • 

—4        • 

^  inrg   • 

o 

HO      O 

a-    o 

-<     o 

00       O 

a>    o 

■3-      O 

in     o 

o    o 

in     o 

-3-      O 

a-     o 

— * 

II  -^ 

II 

II 

.J-  II  •  . 

H  ooo 

'^ 

"^ 

"^ 

" 

1 

— '     1 

1 

- 

1 
1 

OOro 

OOf- 

ooo< 

OCPn 

COrvj 

OOtM 

ooro 

OOf-l 

ooin 

OOINJ 

1 

■Z  II  o  o  o 

o>ri~- 

OJ3C 

OsOO 

o-*t\j 

oo-i- 

o>rr- 

oooo 

Cl<^(T 

COfvi 

CP-JO 

*- 

r>  H  i\;(NirNJ 

-4f^f<1 

inrofo 

^inm 

r~(\j^ 

O  1  o 

ro  1  o 

in(M-< 

— <c\jm 

I^Ovt- 

inofNj 

•"* 

V  II  o        • 

(T        • 

»r--      • 

«-< 

tr-t 

^H            • 

in       • 

2)  1      • 

o       • 

•«•  ->      ' 

-il-inrg   • 

HO       O 

a>    o 

-.     o 

CO      o 

o>     o 

-T      O 

in     o 

o     O 

in     o 

•f     o 

o-     O 

z 

-^ 

-■ 

-' 

->       1 

' 

-"        1 

■"* 

I^ 

o 

II 

^  , 

,  , 

,  , 

,  , 

.    . 

.   , 

.    . 

.  . 

.  . 

.   . 

< 

.looo  oo-<  co-^  coo-  COIN  occ  ooco  oo— <  oom  co-r 
ZHOOO  o-rt^  ooin  ooo  ooco  o-ri--  ooo  ooo-  Oix.-3-  oOin  ocm— ' 
3ii^_,^  r~rri^  (Ni  c  j-inm  m-<o  miNi-^  vj-  -^  o-ho  co  i  — <  oinm  j-in— ' 
i^iio       'oc       "f"-       •--       •«^i»-<       .in       'ooi'in       •^       •it-r— <• 


H  o     o     o-     o     -^     o 

II  • 

II 


rg  H     .    • 

oom 

ooo 

oom 

ooo 

ooc> 

oco- 

Od'^ 

coin 

ooo 

cor 

;•  II  ooo 

o  j-r- 

oom 

CO-T 

oom 

o^a- 

ooco 

OOO- 

O  NIC'-l 

-ir-m 

ro^^ 

vT    1  C 

INI— <o 

in-i(Ni 

co— *o 

o-     o 

a-      •«  r- 

,~-t      • 

vl- 

—1      • 

in       •■ 

It  00 

in       • 

^^        • 

u  o 

o 

o-     o 

-"     C 

00      o 

(7-       O 

>>•    o 

in     o 

o    o 

-■        1 

II 

II 

—  II   • 

II  Oi 

^ 

oo 

co^ 

oco 

ococ- 

com 

coco 

ooo- 

OO-i 

ClC-T 

com 

col 

o>r  (NI 

oom 

oooo 

oom 

O-JTNJ 

OOD 

ooo- 

0(NJ^ 

«  J-<NI 

O-iO 

INIt-vi-l 

—1     o 

in— 4  0g 

O— lO 

o— t\l 

• 

00          • 

«•  ^-       • 

^~t      • 

J-  1    • 

^-1        • 

in       • 

«•  -O  1     • 

o      •< 

f  — *      • 

II  o 

o 

o-    o 

—     o 

CO      o 

0-     o 

-1-      o 

■n     o 

O      O 

-•     1 

II 

. 

. 

, 

, 

. 

oocoo 

OOO-'l-u 
ccr-<j-  •  • 
COO-OOO 

(Njsrog 

O-CT- 
INIINJ 


LU  H  O 

O- 

Cf  ll-< 

-4 

II 

h- 

^- 

•  II 

^ 

Z 

C  II  CO 

UJ 

r~     lu 

z  11  -• 

ao 

>roco 

II  00  r-, 

cc 

n'  II  -^ 

a  cf 

oact 

<  II  r- 

O-ll.' 

■Nio-ai 

in  '.u  :i-     o  I J  2- 


z 

_, 

-, 

y: 

7 

z 

z 

1- 1- 1-  i:'  X 

c^    UJ 

O       UJ 

O       UJ 

C>      UJ 

O     UJ 

in     UJ 

OCXO 

(-jc<:o 

-•oco 

■io-KJ 

r-a;o 

CO  oco 

-■cico 

OO 

f-C 

~ra 

-ro 

.3-C 

mo 

•J-O 

C-ntct 

oca- 

oactr 

c^irir 

OO  QC 

coca: 

ctcoi: 

-•rfuj 

nJ-Oi'U, 

-■oruj 

-•C-JJ 

-•rtTUJ 

^:i-  LU 

-in-uj 

O-lJC 

oaja 

OlUC-. 

o-i-a- 

ciijc:. 

CLUi 

ecu-:. 

44  Bulletin  654 — American  Railway  Engineering  Association 


II  ••  ••  ••        •• 

l-tlOOO-  OOO  00-*      OOlfi 

OllOOr-  OO-J  OOro     OOm 

)- II  CO  CO -4  cDogo  O^o     -^-OO 

11^^*  m       •  •-•I    •     r^^a 

HO     o  00     o  r-     o     oio 

II  O  O-  -H        1       03        I 

II  ^  -<  -4                       -< 

O  II 

,^11    ••  ••  ••           •• 

IIOOO  OOO  OO.0 

SrilOOO  O-OCD  O-Or^ 

ZJlimrOr*^  fsj— lO  f^^-^ 

a;  HO       "ttxi    •  r^       • 

iiooao— io<ooc>o^oirioooir\o-TOO-o        as.; 

11^  ^          I  ^                    ^|_.                    -II                                 -^1                        l-4|f\J|ll.-. 

II  -"  O 


OO'J- 

oom 

OOfNi 

oo~r 

ooin 

oo-< 

ooirv 

OO-i 

OOI^ 

oo%o 

oom 

00<VJ 

.oo-< 

OO-t 

oo^^o 

r"r-o 

•OtvJO 

r~<rio 

r-m   • 

a-— 1  • 

m       • 

•O  1     • 

CO  1     « 

O  1     • 

~r     o 

O  1  o 

vr\     o 

CD      o 

lf\      o 

^      O 

00(M 

OOO 

oo^ 

OOO-    oom 

com 

oo-< 

OOI- 

o-tm 

OJTM 

o-ooo 

o-ooo    ooco 

O00.J- 

oo-t 

Ooom 

►- 

■Orsl-i 

in     o 

CDfSj-1 

in^rg     mrg^^ 

CO  1  ^ 

CMM-H 

-J- -to 

OOOO 

O  1     • 

-r 

O  1     . 

in       •»  cc  1    • 

irv       • 

O  1     • 

CM  1     • 

t-   .  •  • 

cr  11    • 

•    • 

•    • 

•  • 

•  • 

•    • 

•   • 

•   • 

•  • 

•   • 

•  1 

t- 

IIOOO 

OOO 

OO-" 

com 

oo-j- 

OOCNJ 

ooc^ 

OO  — 

ooin 

OOO 

ooo 

z 

Z  IIOOO 

o-om 

o-o-n 

oom 

o-J-r- 

00-3- 

ooco 

oocr 

ocNjm 

OOI^ 

OCM-J- 

o 

3  II  tSJCMCM 

C  1  o 

r\j     o 

CT-     o 

com-i 

O  1  O 

iri—iNj 

o— o 

cr     o 

O— O 

«rmo 

a. 

a:  II  O 

• 

33          • 

(^       • 

o 

J- 

>-*        • 

in       •»«>  1    • 

in       • 

—  1    • 

m 

• 

II  O 

o 

a>     o 

-^    o 

CO      o 

a>     o 

-T        O 

in     o 

o    o 

in     o 

>r    o 

cr 

o 

II  •-* 

-^      1 

—t 

_4 

,-4 

-<         1 

—     1 

—     1 

C\J 

_i 

II 

—4 

< 

II 

3 

(C  II     • 

• 

•  • 

•    • 

•    « 

•     • 

•     • 

•   • 

•  • 

•   • 

•  f 

h-COOO 

II  OOO 

OOO 

OO-H 

oor- 

00-3- 

oom 

OOCVJ 

oom 

oom 

ooo 

oo-J- 

o  — 

Z  IIOOO 

O  J-INJ 

OOfNJ 

0>}T~ 

o-j-r- 

O-O-H 

o^r- 

OOOO 

OCD-l- 

o    o 

oo-jrsi 

< 

3  llroo 

-lr<-> 

-3-       O 

~l-(\JfM 

I---IO 

ocm  — 

CT-— — 

m  1  o 

incM  — 

CO  1  — 

—    o 

(\jmo 

a:  II  O 

•  *co 

r-      .»o  1    • 

~r 

O  1     • 

in       • 

CD  1     • 

in       • 

—»        • 

m 

• 

II  O 

O 

O-      O 

-.     o 

CO       O 

ON         o 

>}•      o 

in     o 

o     o 

in     o 

-J-     o 

CT> 

o 

s 

M  —* 

i— ' 

•-* 

—      1 

—4 

—*       1 

1 

—      1 

1 

l-l 

<NJ 

ooiniu 

II 

—4 

_im     z 

II 

_l         O 

r-  M    • 

• 

•    • 

*  • 

•    • 

•      • 

•    • 

•   • 

•   • 

•  • 

•    • 

•     1 

<        z 

II  OOO 

OOO 

OO  — 

oom 

oom 

oom 

OOO- 

OOO 

oom 

ooo 

ooco 

?■  IIOOO 

0>ri- 

O-OfNj 

Ojm 

O-J-IM 

oo  — 

0-0  03 

o    o 

oiNjm 

o    o 

OCMP- 

ooo 

Slim,. 

tl.-O 

in  -o 

-l-.-NJINJ 

cr     O 

r-<Nj— 

a--i  — 

'n  — •  M 

r-     O 

o-     o 

—    o 

CT-OO 

ooo 

of  II  O 

•  i 

:-  -'.       • 

I--         •  «  O 

<■       • 

O  1     • 

in       --iKi)       • 

in      • 

•-4            • 

m—  • 

(\jmo 

M  O 

o 

.?-     o 

—    o 

00      o 

o-     o 

-r     o 

in     o 

O      O 

in     o 

-J-      o 

o> 

o 

•   •    • 

II -^ 

II 

II 

•-' 

'-' 

-I 

-■ 

"•      1 

— 

— 

(M 

OO  — 

i-aCC!Co£ 

•O  II     • 

• 

•   • 

•    • 

•  • 

•  * 

•  • 

•   • 

•    • 

•  • 

•    • 

•  ' 

zojiu-si 

II  OOO 

OOO 

OOO 

OO'-- 

004- 

oom 

oo.^ 

OOO 

oom 

ooo 

oom 

o>>> 

z:  II  OOO 

o-om 

o^t-- 

o-rf^ 

o^r- 

O-O-" 

o^r^ 

O     o 

ocoj- 

oor^ 

OCO  — 

Q.OOO 

3  II  (VfVJINJ 

m  1  o 

0-H-« 

r-  — o 

com— 

CJ-  —  — 

m  1  o 

I--      o 

CO  1   — 

o— o 

r-— o 

QC  HO 

• 

CD         • 

r-  1    • 

O  1     • 

-3-         • 

O  1     • 

tn 

OO          • 

in       . 

—  1    • 

rst  1 

• 

HO 

o 

O      O 

—    o 

00       O 

c>    o 

vr     o 

in     o 

o     o 

■n     o 

•J-      o 

o> 

o 

U^ 

'-'       1 

-1     1 

—      1 

^H 

"-■     1 

1 

—1 

1 

—t       1 

(\J 

1 

c/l 

II 

—4 

H- 

II 

O 

•J-1  H     • 

• 

•    • 

•    • 

•  • 

•    • 

•  • 

•  • 

•    • 

•  • 

•    • 

• 

',< 

H  OOO 

OOO 

ooa- 

0  0>>J 

OOO 

oom 

OOO-I 

ooo 

oom 

coo 

0-; 

;-»■ 

Z  IIOOO 

o~rr- 

o^r  — 

O-rCNI 

o-rtNj 

OO-H 

o-i-r- 

o    o 

OCO^ 

o     o 

OI--J  Vi 

3  II  fSJfSJCSJ 

in— lO 

O-"-" 

00   1    O 

0>•r(^J 

Cr-"— 1 

m  1  o 

I--      o 

00  1  — 

—    o 

rsjc 

■\o 

O 

QC  II  O 

• 

<o      • 

r-  1     . 

o 

-r      --iJo  1    • 

■n 

00           • 

■Tl          • 

—t        • 

m 

c 

H  O 

o 

a>    o 

—      O 

00       o 

o     o 

-T      o 

in     o 

o    o 

in     o 

-J-      o 

cr 

o 

^^               1 

H  --< 

.—1 

—        1 

—1      1 

—1 

-"      1 

1 

—4 

1 

— « 

nj 

H 

II 

J-  II     • 

•^ 

1 

1 

H  COO 

OOO 

OOO 

oom 

OOO 

OOIM 

ooc> 

ooo 

co-t 

ooo 

ooco 

Z  II  O 

o 

c-om 

O-fO- 

oj-in 

o-om 

oo-i- 

ooco 

o    o 

0(M  — 

o    o 

OOOO 

2* 

=)  HO 

o 

ro  1  o 

comtvj 

rgom 

■J-  1  o 

O  1  o 

in  — cvj 

r-     o 

O— (\J 

—    o 

OCOO 

»-« 

a:  H  o 

• 

CO          • 

-O  I     .-it-O  1     •■< 

t  nT            • 

—1      . 

•n       •  -K-  CO       • 

o        •«■  — 

CM  1 

• 

2'  3  H  —  —  — 


m  H    ■   . 
II  c  O  C 

OO  — 

OOCT 

com 

oor^ 

oom 

OCCM 

OO  — 

oc-r 

ooc 

OOCT 

<i            1/1 

^  II  o  o  o 

oom 

0<T-> 

oom 

o^rr- 

oo 

1—4 

c-rr- 

ooo- 

org  — 

o 

0 

OM 

0 

>          0 

3  II  ■— ' 

-1-^ 

—  r-j— 

o  — — 

CT- 

O 

oincNj 

a-  — 

1—4 

m 

1  o 

o- 

4C1 

O  — (VJ 

^J 

C5 

0  — 

0 

LU                    «• 

'-'HO 

• 

CO  1     . 

1^  1    • 

o 

• 

in       ••«■  o  1 

m 

or.  1 

• 

o 

•«  — 

• 

m 

• 

c           0 

HO 

o 

O-     O 

—    o 

iO 

o 

o-     o 

-r 

O 

in 

o 

O 

o 

m 

o 

>!• 

0 

cr 

0 

H  "4 

—      1 

—     1 

—4 

—t 

^-4 

1 

1 

—4 

1 

—4 

nj 

II 

"^ 

C-J  H     •    • 
II  OOO 

OOO 

oo-r 

oor-j 

(DOO 

OOCM 

OOCM 

OO  — 

com 

ooo 

oc 

!(- 

Z  II  OOO 

0-3-c\j 

o>i-o 

O-J-'N 

o-riNi 

OOJ- 

o^rr-- 

CCtJ- 

ooo  J- 

o 

0 

OIN 

I—* 

Z5  II  —  — — 

OtM— 

0-c\j(\J 

CO   1 

o 

(T-rcM 

O   1 

O 

m 

1  o 

o— o 

CO   1 

^^ 

—4 

0 

—  (NJO 

or  II  c 

• 

CD         • 

o  1    •■»o 

• 

>«-      •*  — 

• 

m 

• 

CD   1 

• 

m 

• 

'^ 

• 

m 

• 

II  O 

O 

O      O 

—    o 

00 

o 

cr     o 

•4- 

o 

m 

o 

O 

o 

m 

o 

~r 

0 

cr 

0 

H 

'^ 

—      1 

'-' 

1 

'-' 

"" 

1 

1 

-' 

1 

1 

'^ 

(\j 

•  •  -o-c 

II 

cocco 

• 

•    • 

•  • 

• 

•  • 

«       4 

• 

■ 

•    1 

•  t 

• 

• 

•  4 

OOOOIM 

HCOO 

COO 

OOT- 

oom 

CO-T 

OCin 

OOINJ 

COO 

oom 

ooo 

oor- 

ccot^J   •   • 

Z  IIOOO 

OvI-fM 

0-3-  — 

oom 

O-.*!^ 

oom 

o~rr- 

O 

o 

OCOsT 

OOI^ 

0(\ 

1^^ 

coo— 00 

3  H— . 

-^—4 

OIM  — 

O— — 

c 

c 

com  — 

f-  m^ 

r4^ 

1  :3 

r— 

o 

X  1 

•~* 

.»- O 

— ir-40 

(Mm 

cr-  HO 

CD         • 

r-  1    • 

o 

<■       • 

O   1 

•  «  m 

CO 

• 

m 

• 

^^ 

• 

m 

• 

0-0- 

II  O 

O 

C       C 

—      O 

CD 

o 

C-      O 

-r 

c> 

m 

o 

o 

o 

m 

o 

->■ 

0 

o- 

0 

(M(M 

II  — 

.-4 

—      1 

.^ 

^^ 

—4 

1 

1 

—4 

1 

—4 

f--l 

—4^^ 

II 

— 

1-  II     • 

. 

. 

. 

. 

, 

. 

. 

. 

. 

. 

!-►- 

OHO 

o 

o 

o 

o 

o 

o 

o 

O 

o 

0 

OCJ 

3  HO 

o 

^ 

^ 

o 

o 

-}• 

o 

00 

o 

CO 

S3           3 

HO 

CO 

-I- 

o 

m 

1^ 

00 

^H 

CO 

U.  II  O 

00 

r-- 

o 

^ 

r~4 

m 

CO 

m 

—4 

CM 

O-I-Ot        _l 

lU  II  C 

0- 

^-4 

OO 

o- 

■f 

m 

o 

m 

>>• 

0- 

luCoc     -> 

a;  n  — 

•— 1 

.-4 

—4 

—4 

—4 

—4 

—4 

CM 

cxrs'u     < 

II 

h- 

»- 

^ 

*- 

1— 

>- 

1— 

t- 

1- 

►— 

—4 

»— 

•  II 

^ 

z 

z 

z 

z 

z 

z 

z 

i' 

;■ 

h-  h-l—  ^  X 

C  HOO 

UJ 

r-     LU 

a     LU 

o 

lU 

c     UJ 

o 

LU 

o 

UJ 

o- 

LU 

O 

LU 

in 

UJ 

OOOJO 

Z  II— C£0 

vfcio 

cooro 

a^a.Kj 

(SJC^O 

—  (iO 

>)-qco 

i-aco 

cooco 

—01:0 

3 

oo 

ma 

CO 

r-c 

■j-o 

-j-o 

-4-0 

mo 

-j-o 

ry  II— era 

•ccr.r^ 

ccxa: 

c-cf.o^ 

ce:cf 

Oct 

-  Ct 

Ooirni: 

Oa-c- 

cocci 

cciof 

l-OC 

'.h- 

^  iii~-i 

YlJI 

(xjiyiji 

—  O'UI 

—  CTLU 

^n-iL.' 

'-4rt 

■  ILI 

— oC'jj 

—  ■XUJ 

—  QCLU 

—  rtiij 

LScr^r 

O  lll~-l 

xia 

inujQ. 

OLJC^ 

O'l 

JO. 

ou-a 

OLL 

J  a. 

c 

uo. 

OUJO. 

O'J 

la. 

0 

L'Q. 

JLUO 

Tests  of  CoupIed-in-Motion  Weighing 45 


^ 

II  OOJ- 

OOCT> 

OOOO 

oo-o 

mtnr*^ 

inmo 

tnino* 

ooo 

ooo 

mm  — 

n 

II  (TOO 

fOrO^^ 

j-~j-.o 

tr*ir*rg 

■o>om 

~rm>j- 

OOCNJ 

00  (Mm 

rsjiMCO 

oo-m 

^— 

HO       O 

(NJO-i 

cooo 

-nrvo 

r--iO 

OlAO 

C-CT--< 

in  J-  — 

OOOO 

-ri^o 

II  o 

r-c\j  • 

^^^^    • 

ir»       • 

o 

O  1     • 

o       • 

OfM    • 

03—    . 

v»-     1        • 

II  (M       O 

O-     o 

fM       O 

in     o 

cs     o 

•a     o 

o    o 

—  1  o 

rsl      O 

o    o 

II  o 

•o 

ir\ 

o 

J- 

fO         1 

r^ 

■O        1 

(\J 

m      1 

i/> 

II  -■ 

.-* 

—4 

(NJ 

^^ 

*4 

•~A 

(\i 

H- 

o 

II 

3C 

II  inirvf^ 

iTvinco 

iTvin-o 

oom 

inin^ 

oo— 

M\\C\~t 

oo>i- 

ooin 

mm<> 

oo-t- 

.^ 

II  r--rg^^ 

Kf^-Orrs 

o<vj-> 

i^O>,j- 

rop^in 

crr-in 

-•00-0 

i~-mo 

—  rriO 

O-IMOO 

f\jr 

vjm 

1— 

_3 

II  r^og-i 

■3  1  O 

-4      o 

c^  1  O 

r-     — ' 

-"     o 

00— <N) 

Cr^rsj 

a— — 

(SJIXJO 

OOOO 

OOOO 

or 

II  ^  1     . 

(^ 

(\j      • 

in       . 

oo       • 

-o 

a<  1    •«  o  1    • 

It  M 

o  1    • 

r--  1 

1    • 

1—    •   •    « 

HO-     O 

-O      O 

in     o 

o    o 

-<•     o 

ro     o 

o    o 

-o    o 

c\j      O 

m     o 

o 

o 

moo 

II  -H          1 

-•       1 

^^ 

(M         1 

f-i 

1 

—     1 

•-4 

IM        1 

in 

1 

U-  — 

" 

'^ 

o 

0- 

II    •  • 

.    . 

,  . 

.  , 

,   . 

.   . 

,  . 

,  . 

.     , 

.   . 

, 

, 

1- 

II  oor- 

ocoo 

ITMrvfM 

oo-^ 

intn^ 

ootsi 

u-vinoj 

oor- 

oor- 

OOI^ 

mu 

-im 

z. 

7 

II  ,r^T'^ 

tSIO'A 

OCMH 

r-a>vr 

rrif-irv 

cD^ro 

irvinr- 

oo-r 

OtNJT- 

inr-vO 

.nojrvj 

o 

) 

II  r^m— 1 

j-->o 

tsi-io 

^jf\j^^ 

r-     —* 

0-—-. 

o    o 

a- j-(M 

cr— o 

m  — o 

omo 

a. 

a 

II  (^J       • 

O   1      • 

rg       . 

lA    1      . 

oo       • 

L-\    1      • 

o 

O  1     • 

» i%i       • 

O  1     • 

00 

1    • 

w       I       ^  rg       I  '-'I  ^       I       ^ 


II OO^     ooa>     inmo*     ir\ino     oOf*^     ooc>     oor^     mi/>f*^     inm'j-v     u^in--<     LOir>o     o— • 

it  It  ooo      r-'-TvoD      rg^fM 


-X  II  (M 


OOrri 

ooa- 

oor- 

m  in  (^     m  m  m 

mm  — 

or--i- 

-0>J-!M 

>r-i-m 

m.4-—     cooco 

—  0-3- 

m  1  — 

—    o 

o     o 

0-r"(xj  .    CD— C 

-1-  — O 

CO 

.  -o 

o 

O  1     •  It  .Ni        • 

O  1     • 

—.      I      ^ 


iiCOiA     oOin     inin— «     in^no     ooo     oOoo     ia»/>'j^     ooo     Lnrn^     mm—*  mmo 

2"  II  f\iC0>3-     mmrr*     mmo     >3-cocr     o     o     oaoin     >£»<;<<*     corgro     ocoo     ^lO  morM  OOO 

3  H  r-pg— «     r^tNj^^     rsir-^— *     o— <o     o     o     fN»     c     — *— <.%!     o»Ni— «     J3     o     m     o  *X)mo  ooo 

3111— <l•c^       -^       -in       '00       -o       -O       •■»— 'i-rsj       -o       •  X)       •  rvjmo 


O  II     •    • 

•   • 

•  • 

•  • 

•   •           •    • 

•    • 

•  • 

»  • 

Z-UJUJIU 

II  mmo 

oo  — 

mmc> 

xvmr- 

mmr—     mmco 

m.m^j-     mm^ 

mmo 

003- 

ooo 

o>>> 

^  rl  35  00O 

or- J- 

00OJ3 

(Mor- 

rvjror^      .t:^J  — 

f\JfNJ%0       or<\oo 

COO.O 

r~-n  — 

o-ot^ 

0.000 

13  II  —  —  o 

m     o 

— — o 

(X)r>i  — 

m— (M     —     o 

rf^rnj-      — — o 

0>(M  — 

m     o 

moo 

a:  II  (M       . 

o 

<N        • 

m       • 

CO  1      •»  ») 

O        .»  —  1     . 

tM        . 

o      • 

CP—    . 

—     I     — 


11  com 

mm.o 

ooo- 

m  nr- 

OO-O 

0<D^ 

OCI-- 

mnm 

ooo 

mm  n 

oor- 

^  II  f^  ( 

■n  — 

(*>— ifNJ 

r-o-m 

-r— o 

rgoog 

mr^m 

— — m 

CO  —^fO 

^oro 

f*^— sf 

orgrg 

3  II  a- 

1  o 

•~-INJ„ 

—     o 

vT 

1  o 

r-     — ^ 

O  1  O 

,-^,~t,-4 

Orv.i  — 

0-  — — 

■O'^O 

oo<^o 

J-  II  — 

■ 

o       • 

rg 

m 

• 

X3          • 

o 

o 

—  1     • 

-M 

o 

CO 

11  cr> 

o 

o     o 

m      o 

o 

o 

<T        O 

rO      O 

r-     o 

o     o 

rg      o 

m     o 

o     o 

11  — 

1 

^H 

^^ 

rg 

1 

—       1 

•-*        1 

^^ 

II 

-' 

II  mmm 

mm-0 

mmc 

rni 

nrsi 

mmm 

mmm 

co- 

mmc 

mm  — 

mmo- 

mm  00 

^  II  rnoi" 

(viom 

m^-co 

m 

o 

rgoro 

ar^m 

mmit 

rgr-r^ 

ergo 

-TP-O 

rgit)r-i 

3  It  C* 

1  c 

—  ct^ 

mtsi  — 

-r 

o 

r-      — 

—       O 

o     o 

C.-Nj- 

CT-  — 

rgrg- 

omo 

:i  II  — 

• 

c       •»(%; 

m 

• 

XI 

■c 

o 

—  1     • 

.-N,        • 

O  1     . 

0- 

II  C- 

o 

i^     o 

m     o 

o 

o 

-r     o 

c\      O 

r~     o 

o     o 

rg      o 

m     o 

o     o 

II  -H 

1 

*"* 

"* 

rg 

^ 

—     1 

^ 

rg       1 

m 

II  ooo 

OOfV 

mmcr 

OOvT 

ocrg 

mmm 

OOCD 

mmco 

OOOO 

mm  — 

OOCT- 

~  II  c-r--  > 

-o>r.-o 

-0  — o 

^  1 

-r-^ 

—  mo 

mcDl-<^ 

OC-J 

oo-m 

I-  — o 

omrM 

'^(yrr, 

:;  11  mm.^ 

o— o 

O  1  o 

<r 

C 

r-      — * 

:?.— — 

— *-^rg 

rg  1  o 

r^  1  o 

-1-  1  o 

cmo 

u.   »  tSl 

•  ■B 

r  tj-       • 

IM 

m 

T.          • 

m  1     ■ 

O       .*  — 

rg        • 

o 

0- 

II  <7> 

o 

■o     o 

m     o 

o 

O 

-J-      O 

m     o 

r-     O 

o    o 

rsl      O 

m     o 

o    o 

II   *-4 

^^ 

—      1 

rg 

—      1 

—     1 

—        1 

rg       1 

m 

og  II     • 

11  mi 

nr^ 

00-3- 

ooo 

OOr- 

OOO 

mmm 

oor- 

oo- 

OOO 

mmrri 

mmo 

,"^  II  C7^  1 

o  o 

O  corsi 

r^-^o 

<r  XCO 

r- — irg 

-rf-i-- 

-j--J-m 

rg-0  — 

r^  m-r 

''laDm 

-1-Cf-r 

_;  II  fNjh-  f^ 

(Mn(\j 

O  1  o 

~o. 

—  O 

■C      O 

r-mrj 

c     o 

— <.-l— I 

CO       o 

<r  1  o 

f^-OO 

a.  11  — 

1    •<: 

:(?       •-; 

;-  rg 

m 

00         • 

m  1     .It  c 

—  1    • 

rg       . 

o 

1^  1    • 

_i              II—      I—  —      irg  —       I  —      I—  rgimi 

_l                  II  —  .    .    .rrio 

Z3                  II  COO  — O 

Q.          —t  n    •    *  ••  ••  ••  ••            ••  ••            ••  ••  ••  ••  O'^'^crg 

—              II  COM  mmoc  mm— t  mmrg  mm.^^     mmm  m-nr-     mmcT'  OOO  cjom  nm^  -r  >J  O   •   • 

a.        ^  II  ooin  fMOro  rg>fo  mio  j*mr-     -rr-m  >r-ro     r--.-gro  rnm-r  x^r-  '--(♦^-r  -r  orgoo 

_)  II  —  —  O  C~>rrg  r«lrg—  -J-      o  O      O      C  I  O  — — rg      org—  co     O  -T  >  O  OOO  or  3 

r'  II  rg       •  T-       •«■  rg       •  m       •  oo       •     o       «  o       •<-  —  I     •  rg       •  o       •  c-       •  OO 


m  n 


ij.  II  rM 

a> 

Nl 

m 

yy 

o 

O 

^ 

rg 

0 

ijc  11  o- 

■o 

m 

O 

-1- 

m 

r- 

sO 

rvj 

m 

ri  II  — 

—I 

'-4 

rg 

-^ 

— t 

—* 

•Nl 

1) 

h- 

h— 

k- 

^— 

^ 

^ 

^ 

^ 

^ 

^ 

•  II 

y 

^' 

^" 

r' 

^' 

T' 

^ 

7- 

7* 

-r 

C  II  o 

LU 

r- 

LU 

on 

ULI 

O 

LU 

m 

LU 

-^ 

■Lj 

— « 

o 

111 

.~t 

III 

0       lU 

ir  II  oc< 

O 

I--0CO 

•1-=: 

l-J 

ainro 

mao 

o^o 

oci:o 

—  (^O 

r^ci\j 

mnco 

11  •-^_- 

-rc 

rgo 

-c 

ri; 

ac 

o 

rgO 

<-*( 

c 

rgc 

t-a 

ouo 

:/■  11  C  o- 

-L 

rgi^QC 

CCY- 

iTt. 

o 

nror 

CO 

ti 

If. 

Ce- 

n- 

carci; 

C^ri: 

rr- 

a:  y: 

u 

mrcoc 

'*  II  Oo' 

lU 

r^.  rr 

■JJ 

,ny: 

'U 

sl-t^u 

c 

c 

1    J 

rr  -f 

L'.l 

C' 

■^ILI 

■J-cr- 

':  I 

c--r 

r-rrTL-l 

L/   M   'JIUO. 

fML  J 

1. 

.■N.1. 

i:L 

c 

^a. 

o 

■L-a. 

:v  L. 

■L 

O' 

11^ 

'.Z   .1 

a. 

OJi 

iL 

-;  ijO. 

46  Bulletin  654 — American  Railway  Engineering  Association 


II. •       ••       ••       ••       ••       ••       ••       ••       ••       •• 

K- iiuMno     inino     mir»fO     iniTim     oom     lAino^     OOC     irtinp*     inirtst-     oor^ 
o  II  oors(     fMi — I    CO— 4(^     a^o^st     — 4CT*sO     oj^fNi    ^>r^j    00**0     O'Ofvj    mmr^ 
1— iiuMoo    o— <o    fMino     sj-oso     r«i(M<\j    ir\roo    — "-^o    mo^     >rr>io    -ho-o 
110       •oi.oi'ir*       •     in-<  •     ^       •     o       •     oiNj  .     r-  I    •     r^-<  • 
iiMOcrofMOir\ocoio<oooo— iiorgooo 
II  a>  >oiirtio  -t     I     m  r-  oi<Miir>  i/> 

ii^-i-<pg  -1  ^-4iM  »_ 

O II  O 

-< ••         X 

iiooj-     ooro    ooin    ifMn— •    ocr^     ma^r-    000    inirvo'    ir\vr\ro    ifimo>    irvin-^ 
5'ii>}--r<N/     -JO-in     ooo-O     -oou>     (^J^Tco     ro-Jin     r-i^o     \r\-Tco     o^^c     ^r<^JO     -^r-m     1— 
3 II  <Nj(M-^     o     o    o— 'O     in-^o    iri-^(M     fOcMr-i    o     -<    --—10     oo-^o    iri    o    o>-to    ocoo 
cents;      '    (}•      •— i|«in      •ool•^^^o      "O      .-^i.tsi      #0      "Co      «»-.«« 
iit>o<oou>ooo«tor'ior~ooo'Moinooo        r-.NO 
11^  -^  .-<loj  1-^  ^l_H  rg  in  u.-^ 

II  -4  O 

II 

a>i • I- 

mrnnro  ininaj  000  irvi^j-  ooin  00—4  i/Mnt^  ooog  0000  ooif\  ooiri  h 
zno-oro  o— <o  00  o  inoo^  -ooo  inr-A  -^.j-o  ct-^ct'  f~--^o  *o-*t"  co-r— •  o 
3110  O  in  I  O  o  o  ^--O  ir\— '(M  010  -H— losj  crro-^  r- I  o  oom_i  ^i\jo  a. 
c£ii(M      'Cr      '(M      •ir>      •coix-o      'O      •»oi»<m      "O      •<»      • 


II  cr     0 

<o    0 

in    0 

0      0 

>r    0 

m     0 

r-     0 

■£)      0 

rg     0 

m     0 

0     0 

II  -< 

-^     1 

•—4 

rj 

1 

*-<      1 

-H       t 

-^      1 

rg 

m 

_i 

II 

,-^ 

«x 

II 

3 

CO  II    •    • 

•    • 

•  • 

•   • 

•  • 

•  • 

•  • 

•    • 

•   • 

•   • 

«    • 

l-r-.NO 

iiooin 

inu'^— 1 

in.nfsj 

OOCO 

OOrsJ 

00m 

ininr- 

oo-i- 

oo>j- 

oo-j> 

mmrg 

0  — 

^  II  r^m-4 

-.0.0 

iniMco 

cotNjin 

rg^oo 

rOCTi-i 

r~-r-o 

inj^in 

nJ- J-— ' 

-D-J-in 

o-~J->r 

< 

r>  II  (T  1  0 

-r-io 

0>-"0 

in -10 

0  1  0 

oorgrg 

0     '-I 

OiM-l 

sO-«— ■ 

-O-iO 

r-,00 

a  II  -"      • 

o>  1    • 

-<  1    • 

in       • 

CC         • 

in  1     •»  0       • 

f— )  1    • 

rg  1     . 

0      • 

i~-  1     • 

II  <>    0 

0    0 

in     0 

0     0 

-J-    0 

m     0 

r~    0 

~o     0 

rj     0 

in     0 

0     0 

3 

II  ^     1 

— '     1 

-J      1 

rsj 

1 

--      1 

—4      1 

-H        1 

rg 

m      1 

oomoi 

II 

—4 

_jro     z 

II 
r-  II   •  • 

,  . 

,  , 

,  , 

,  , 

,   . 

,  . 

,  . 

,   , 

,  , 

.  , 

-1        0 
<       z 

II 00-0 

inin  J- 

oo:n 

inin-i 

inino 

inino 

inmr- 

ininrg 

COI^ 

mm— 1 

mm—" 

z  II  r--  r^  m 

-J-.-\j-< 

inr»ia) 

~Ta)~l- 

t>.oro 

r-ino 

-JCOO 

ro^O 

'-'r-tn 

p-rno 

-<i-SIO 

000 

3  110      0 

in     0 

cr— 10 

in     0 

-t'-im 

^fOrg 

r-iMj- 

— Ir-H^H 

r-  1  0 

r-rg-i 

>!■   1  0 

000 

a.  Hi\i 

0<       • 

-^  1    . 

in       • 

CO  1    '-iKi       •»  J-  1    •*-!  1     • 

rg       • 

0       • 

CO         • 

rgmo 

II  o>     0 

vO     0 

in    0 

0     0 

-t     0 

r^l      0 

~o    0 

-0     0 

<M     0 

m     0 

0    0 

•  •  • 

II  -J 

II 

II 

•-I 

-^      1 

(M 

1 

'-' 

1 

-1     1 

-"      1 

rg 

m      1 

OO--^ 

>-cir<riC 

>0  II    •  • 

•  • 

•  • 

•    • 

t  • 

•    • 

•  • 

«    • 

•   • 

•  • 

•  • 

rr  i.". ' - / 

II  tnirv^ 

■-nino 

OOfSJ 

ooo> 

oo~r 

inino 

ininr-- 

inTico 

ininr- 

mmi^ 

m  .-N  '1 

'.-'  _■•  ->  '■* 

Z  II  ooin 

cor^tsj 

000  in 

COrgo 

r-cras 

(MCT-CT- 

nT^O 

njf^o 

iOO>r- 

-<3>c> 

">  .:■  •> 

•V  '..  VCJ  w 

3  II  -•—10 

»r  1  0 

0  1  0 

«r     0 

in  1  ■-< 

p^forg 

^-irg 

-^—1^^ 

.0  1  0 

-0     ') 

."^ii'iO 

a  II  fNj      • 

0      . 

(\i      • 

in       • 

00        • 

in  1    •■M-o       •♦—•1    • 

rg 

0 

!^-      1          • 

II  o>     0 

~o    0 

in     0 

0     0 

-r     0 

fo     0 

r-     0 

•c     0 

.>j     0 

m     0 

0            0 

M^ 

^     1 

^      1 

<M 

1 

f*^      1 

-^      1 

-•      1 

rg 

m      1 

^ 

II 

—4 

t- 

II 

0 

in  II   •  • 

•  • 

•  • 

•  • 

•  • 

•   • 

•  • 

•  • 

•  • 

•   • 

•  • 

3 

II  oor- 

oo-o 

inino 

oo-r 

coco 

ooin 

oo~}- 

in.no> 

ininxj- 

oom 

mmvf 

iT  II  —".-HA 

c^mf^ 

oc\i— 1 

r^-ic 

->ino 

^(NJfO 

mLn-— 1 

o>oco 

r-.  1  0 

•Ji-trr, 

ogjo 

3  II  -<-io 

.m-40 

-<    0 

J-    0 

in-im 

^roiM 

00— irg 

o>«>— 1 

r^     0 

oom-i 

m     0 

0            • 

a:  It  rsi      . 

a-  1    • 

nj       • 

in      • 

ro  >     'iK)        •* 

i-C>  1     '^O  1     • 

i\j      • 

0 

CO 

0           m 

II  o>     0 

0    0 

in     0 

0     0 

sr    0 

m    0 

-0     0 

lO      0 

rg     0 

m     0 

0     0 

r1                   -t 

11^ 

-^      1 

•-* 

IN 

•r-t 

1 

-H      1 

*-*      1 

rg 

m 

rg 

II 

—4 

1              ro 

n 

^  11   .  . 

.  , 

.  • 

.    , 

,  , 

,     , 

,  , 

,  , 

,  , 

,  . 

.  , 

1              -• 

1 

II  000 

ininiM 

ooo> 

oocr 

OOnT 

000 

ininrg 

in  in  in 

inin^j- 

mm— • 

mmm 

Z  II  ^  .J-  fSJ 

r^inm 

sf-Of^ 

(NOCVJ 

o-r-in 

r-in--i 

^^cr 

-om-l- 

(<Mn>r 

r^mo 

r-«\-i 

z 

0  II  0    0 

in     0 

^      0 

in    0 

rrit\jin 

(Mr-<--l 

0     0 

onj-^ 

CO      0 

f^rg— 1 

-orgo 

—• 

0:  II  <NJ          • 

0       • 

<\J        • 

in      • 

00  1     •*  0       • 

0 

^-*  1    * 

rg        • 

0 

CO        • 

II  o>     0 

-0     0 

in     0 

0     0 

-J-     0 

ro     0 

r-    0 

•0     0 

rg     0 

m     0 

0     0 

^               a 

11^ 

f.^ 

,-t 

nj 

1 

r-t 

t~*      1 

r-A 

rg 

m 

c          a 

II 

—1 

►-                  UJ 

II 

t— 

m  n   .  . 

•  « 

«  • 

•  • 

•  • 

•     • 

•  • 

•  • 

•      • 

•  • 

•  • 

<             l/l 

II  i/Mnf<\ 

inin-o 

ooo> 

oc^ 

oo-< 

00-4- 

00<M 

oo-< 

ooog 

mm^ 

mm-l- 

«-.           Irt 

!•  n^t'T-M 

.C>l-(Ni 

J^^"-« 

t~'^T\ 

■J-nj^ 

(M^rg 

00^ 

->3^^ 

000-c 

i~-mo 

rg-<-< 

>         0 

0  no     0 

m     0 

0  1  c 

in-<r.? 

.O  1  0 

rg-i--i 

C^^^^^ 

ornrsj 

inrg^ 

<5-iO 

rjrgo 

UJ            a: 

of  II  CO         • 

c       • 

PJ      • 

in       • 

m      • 

»i^       • 

C-   1      • 

0  1     •»(M  1     • 

0      • 

CO  1     . 

0           0 

lie     0 

0     0 

in    0 

0     0 

-T      O- 

ro      0 

lO     0 

0      0 

rg     0 

m     0 

0     0 

II  -H 

—4 

'-'      1 

(VJ 

1 

f-* 

t 

r-l           1 

•*-*      1 

CM 

m      1 

n 

'-' 

II 

(Vj  II     •    • 

.  . 

.  . 

.   , 

.  . 

.    , 

.  . 

.     . 

.  . 

.  . 

.  . 

II  OOr^ 

inin.-\j 

--  lO  X) 

imn— ' 

m,Ti^ 

OOrg 

inin^j 

mino- 

in  in  CO 

m;nm 

corg 

^  II  ^-OX 

(M      0 

^00 

-OOXl 

omrg 

O^mrsl 

r-i>-a> 

om-o 

-<r>rg 

mmm 

miy,-n 

3  II  00 -lO 

in    c 

a>-^rH 

m-io 

>rrgm 

0  1  0 

njrgm 

co^cg 

CO      0 

•c-^o 

o>-j-o 

a:  II  ^  1    • 

o>      • 

•— I    1       • 

in       • 

CD  1     •«<)        • 

0       'li-o  1    •»(M       • 

0 

t-  1    • 

II  a-     0 

vO    0 

in     0 

0     0 

•r    0 

m     0 

f-     0 

sO     0 

pg     0 

m     0 

0    0 

II  -J      1 

t^ 

'^      1 

(M 

1 

-H        1 

-•      1 

i-H 

,rj 

m      1 

II 

II 

om,;^oo 

-J  II    •  • 

•    • 

•  • 

•  • 

•    • 

•  * 

•  • 

■  • 

•     • 

•  • 

•   • 

co;-o.-M 

IIOCC 

COsJ- 

00^ 

inn-- 

OOPi^ 

corg 

ocnj 

inn-c 

COO 

OOfO 

ccn 

<TOO    •    • 

3  II  rvjovl-" 

-<-4,0 

— iro— 1 

>i-ao^ 

oorg 

C7-rorg 

oo>i- 

--rO(^ 

a>-«c 

m->co 

--*fri^ 

j-ro— 'OO 

z;  II  0    0 

-T-"0 

-"      0 

n     0 

gj  1  — 

0  1  0 

CJN— 1-1 

CtN  — 

r-     0 

r-rgo 

rgrgo 

C300   1     1 

K  II  fM 

C-  I     • 

nj 

in      • 

CO        • 

0       • 

C-   1      • 

-•  1    • 

ru 

0 

CO  1      • 

00 

IICT>      0 

•0    0 

in     0 

0     0 

sj-         0 

nl      0 

•0    0 

■a    0 

rg      0 

m     0 

0    0 

mm 

II  -< 

-^     1 

«-4 

nj 

1 

-■       1 

1 

'-•     1 

-^ 

."g 

m      1 

'^f-* 

11 

— ' 

II 
1-  H    • 

. 

. 

, 

. 

. 

. 

. 

. 

. 

. 

i-i- 

OHO 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

3  110 

(N 

00 

0 

■0 

rg 

0 

0 

00 

rg 

~J- 

33           3 

II  0 

in 

0 

~J- 

0 

—4 

0 

i^ 

I-- 

m 

-J- 

0 

U.  II  fM 

3> 

rg 

in 

CO 

-0 

0 

,~-t 

rg 

0 

CO 

U-I-Ct       _J 

LU  II  0> 

•0 

in 

0 

-r 

m 

r~ 

0 

rg 

m 

0 

U.O0d      J 

a  II  -< 

—4 

*-4 

nj 

f-t 

r-« 

■-4 

eg 

m 

iXi.UJ      < 

II        1- 

1- 

>- 

1- 

►- 

h- 

►- 

>- 

h- 

i- 

rH 

t- 

•  II           2" 

z 

z 

Z 

^, 

z 

2f 

z. 

7- 

2" 

^-^-^-zx 

0  II  0     UJ 

r-    UJ 

ay     m 

0      UJ 

in    UJ 

^      UJ 

-•       UJ 

0      UJ 

'-•       UJ 

0     UJ 

coao< 

rr  II  o«o 

r-cf<_> 

•tcci^ 

CO  (TO 

in«o 

'ooiro 

OlXO 

-^cio 

rgaco 

rO«o 

t-t-t-a-X. 

II -10 

-f  c 

t\j(D 

-cc; 

000 

rsio 

'-•Cl 

ruO 

r~o 

COO 

«■  II  ooror 

rsiccct 

c  ceo: 

Ocr-OC 

ooc/rc2 

00.  af 

axcr-. 

c-orci 

corni 

mo;  ex: 

t-ai- 

<  HO(YUJ 

r^iXiij 

r<^erjj 

•trftu 

On-Lu 

r^cyiu 

OQ'UJ 

<tKIL! 

O-KUl 

rr,ri:u: 

ifo-z- 

0  II  OJJO. 

rvjLLia. 

-■vj'JJO. 

O'UC- 

0  JJCL 

CNjiua 

OUIQ. 

ouja 

-oajx 

c.ua 

Xujo 

Tests  of  Coupled-in-Motion  Weighing      47 


II    •  • 
►-  II  ooo> 

OOOT 

OO-" 

oo-i- 

00<<1 

oo~t 

ooo> 

oom 

ooo 

oo-« 

O  II  -J-  J-  ro 

~o-J-<r 

—  O'-' 

inir\-< 

^^*-4.-4 

(*^r^^|^ 

ro  J5-0 

ooir\ 

OO  J- 

a-<o 

t-  iiiTv r- o 

— las-" 

irv>j-rg 

O^fvjO 

o.>j-< 

r-f\j  — 

■t—o 

-ro^ 

ino-o 

mo-« 

II  in 

9 

CTTVJ    . 

Or->   . 

1^  1    • 

tNJ<\J     • 

O.M    • 

-I-l  • 

cm  • 

1^       • 

fO(M   • 

II  o> 

o 

O  1  o 

ir>  1  o 

CO       o 

in     o 

00  1  o 

O-  1  o 

ir>  1  o 

r-     o 

CO  1  o 

II  CO 

o>      1 

-0       1 

1^     1 

a- 

.0      1 

■O        1 

O-      1 

o 

0-        1 

II  f^ 

^^ 

t-« 

^4 

-^ 

.— • 

l-« 

f-< 

(\j 

-^ 

oil 

^^  II    • 

t 

•  • 

•   • 

•     • 

•  • 

•   • 

•    • 

•   • 

•  • 

•    •             •    • 

II  oofNj  oor*  oouA  ooo  oo^  00*0  000  ooco  oocr*  00m  oo^< 
^  Hu^r^^r  'O^r-  ^O'j-o  'O^oo  csj-rr^  oocuo  r-<mf\(  .-<'<^>o  r-<-<-4-  ro^^o  CT-OfSi 
13  iir*(M^H  cofo^^  OfOfNj  o-^o  — *r-*o  r--^^^  -.n  1  o  crro^^  o^ro^^  tr\  1  o  r^^mo 
0:110^       •0(»iAi«*ro       •ir>       •aoi»o       •mi«r-       •co       •mi" 


C-  II    •   . 
II  oor-- 

ooro 

ooin     ooin 

000 

OO-"     oor- 

OOC      OOCD 

OO-i 

OOrO 

Z  II  j-~o.-^ 

mr-CT- 

-Hom     .Njo-> 

M^rM 

-o-j-o     ~oo-i 

rvc-J-     tNj.O'M 

t\JM.O 

roinco 

3  II  r^(M-< 

ccm^ 

Or^iNi     ocNj^ 

0      0 

mf*>fNj     r^rsj^ 

f-sriM     r-     0 

f\J(^-< 

rvjino 

ct  II  c^       • 

0  1    • 

irv  1    •«  ro  1    • 

a\ 

CO  1    •■)<•  a> 

in  1    ••&(--       . 

OJ   1      • 

~r-"  • 

_l     I     ^      I     ^  _J     I     ^ 


00  II     •    < 

.    , 

.    . 

.  . 

.  . 

.    . 

.  . 

.    . 

.   . 

.  > 

.  • 

1-000 

IIOO-" 

ooin 

OO.M 

OOtNJ 

ooco 

ooc 

coo 

OO-" 

Ooru 

ooin 

ooin 

UC\I 

Z  II  .3-Oro 

-OvJ-tM 

inmo- 

O-roro 

h-C-J- 

mf-in 

ino-o-v 

(\JtMO 

r-^in 

^—10 

minm 

< 

:3  II  j-\ 

0 

crtM-^ 

r-  -oi-" 

.niM-. 

r\j(\j— 1 

-OlM— 1 

om<M 

-.^O 

r-^-o 

in     0 

-IJDO 

JC  M  C 

0  1    • 

sj-  1     •*  ro  1     . 

in 

00  1    • 

C7>         .« 

01     • 

1^       . 

00       • 

in  1    . 

II  03 

0 

a>     0 

0      0 

r^     0 

<y     0 

-0     0 

■0      0 

a-     0 

0     0 

e-     0 

in     0 

3 

M  — « 

-■      1 

— >       1 

^      1 

^-i 

'-'      1 

.—t 

'-I      1 

tsi 

w4 

00      1 

ooinui 

II 

—< 

_jm     z 

II 

-I        0 

r-  II    •   < 

•  • 

•    • 

•  • 

•  • 

•    • 

•    • 

•  • 

•   • 

•     • 

•  • 

<       z 

II  00-" 

CCOO 

OOt^ 

oo-o 

000 

00m 

COM 

00^ 

000 

000 

OOI~- 

i:  II  r\j.r<Ni 

-TO  XI 

>!■  -O'^T 

r~-ir.oc 

(--0-0 

-iC"J-i 

oo-< 

r-r-co 

000- 

(NI(\J.O 

oco-i- 

000 

J  II  .n 

0 

.oro^ 

^(NJ-l 

'O-'O 

mmrsj 

CO  1  0 

.^mrM 

o-<o 

corgo 

,i-_.o 

cxo 

000 

a  II  o- 

0  1    • 

irv  1    • 

r^  1    • 

in       • 

CO 

CI     -li  vO  1      • 

1^ 

00  1     . 

-J- 1  • 

^ino 

II  CO 

0 

0-     0 

•0     0 

r-     0 

c     0 

.0    0 

-0     0 

0     0 

0     0 

0    0 

in     0 

•  •  • 

II  -• 

-^      1 

— '      1 

'-'      1 

-• 

'-I      1 

-1     1 

-■      1 

INl 

-1     1 

X      1 

oo-< 

II 
II 

"^ 

l-QCQfQi: 

0  II    •  ' 

•   • 

•  • 

•  • 

•   • 

•    • 

t    • 

•  • 

«     • 

•    • 

•  • 

ZUIlULU 

II  oo-< 

OOltv 

oor- 

OO-M 

oom 

oor- 

oor-- 

oor- 

oon 

000 

ooco 

o>>> 

Z  \l<t~TC\l 

•o-roj 

C-HCO 

0-0  0> 

OCOvJ- 

001^ 

ooD-r 

oinrsj 

IMO'^ 

OJ-M 

000  in 

0.000 

3  II -J-  1 

0 

O-CM-l 

om-< 

-O-iO 

rMiN-" 

om-i 

-4-  1  0 

O-fM-l 

cr(N)-' 

m(\i-i 

r-00 

a;  iiO< 

• 

0  1    . 

rv  1    • 

ro  1     . 

m       • 

CO   1      . 

<y      • 

in  1    • 

r*-       • 

CO   1      • 

,j--<  • 

II  <t) 

0 

c    0 

0     0 

r-     0 

<y     0 

<}     0 

0    0 

o>     0 

0     0 

0-    0 

.n  1  0 

11 -H 

1 

-•      1 

r~*      1 

-^      1 

—4 

'->     1 

^     1 

'-i      1 

r\j 

-<     1 

00      1 

10 

II 
II 

"* 

0 

\r\  »    •  ■ 

•  • 

•   • 

•   • 

•  • 

•    • 

•  • 

•  • 

•   • 

•    • 

•  • 

:s 

M  00-" 

000 

oom 

ooco 

00-' 

00m 

00.0 

octsi 

00m 

oo'n 

00m 

Z  II  0  .-^  -0 

'/Mnro 

-o-j-o 

-J-T- 

-ooo-r 

<r.o-H 

-r.'Moc 

O-J-CVJ 

r-cr<r 

m-40 

onJO 

311  O-'O 

CM\J— • 

OrOfM 

inm^^ 

0     0 

inmtvj 

(vjro— 1 

Onj^ 

in  1  0 

m.-vj-i 

XO>-< 

0 

af  11  a- 

• 

0  1    • 

lo  1    .  ft  m  1     . 

in 

la  1    •«  cr  1    • 

-0  1     • 

r*-       • 

00  1    • 

m^^  • 

0           1 

II  CO 

0 

c-    0 

.0     0 

i~-     0 

a-     0 

-0     0 

~o    0 

O-      0 

0     0 

IT       0 

n  1  0 

r~*                        1 

II  -• 

-'     1 

->      1 

'-•      1 

•-4 

>-*     1 

>-*       1 

•-*       1 

rxj      1 

-"        1 

00      1 

II 

'" 

[                            1 

.J-  11    •  • 
II  coo 

ocr- 

OOrr, 

coin 

000 

com 

OOJ- 

coin 

OOsI- 

000 

ooco 

1 

Z  II  CO 

0 

■c<\so 

crtNJO- 

,-4^^rr. 

— iro-O 

■J- JJ-" 

^in<M 

-OCOCP 

oc-t 

O^fVJ 

minin 

2- 

3  II  -J- 

0 

:o«^— 1 

Or"-^ 

■J-~J-(NJ 

-<— iO 

■nrotxi 

Cinm 

0  JI.-NJ 

mm-H 

rniNi^-* 

OOO-l 

*-« 

OC   11  O' 

0  1     . 

in  1    . 

ml    •  If  L-N       • 

coi    ••:>cri    .ii-inl    •af~-i    • 

00  1    . 

Mrj  • 

II  oc 

0 

o-    0 

-c    0 

1^     0 

o-     0 

sO     0 

.0     0 

a>     0 

0     0 

<y    0 

in  1  0 

Z               ( 

II  —4 

-^       1 

-•     1 

•-*      1 

rH 

-^      1 

-^      1 

•-I      1 

IM        1 

'->     1 

00      1 

0               1 

II 

—i 

*—               1 

II 

H- 

r^  II    • 

«    • 

•   • 

•   • 

•     • 

•  • 

•   • 

•    • 

•  • 

«  • 

<               ' 

II  OO'" 

OO-i 

OOsO 

coin 

OC^ 

ooin 

oor- 

0000 

oooc 

oo-o 

ocr- 

^~t              1 

2  11  vfvj-r- 

-la-.n 

-<0-.7- 

CM-.n 

-occ~r 

CT^^^O 

^j-i<- 

rr\-iO 

•COJ- 

•n  T  -T 

inmcD 

>               ( 

Z;  II  r"-<0 

cr<^:— ■ 

G-  -3-(M 

OfM-" 

0    c 

X  1  0 

m.-v-i 

CC-TI-^ 

l^-'C 

C-^.-Si 

^00 

UJ 

□;  II  cr  1 

0  1    . 

vr  1    ••!>  J- 

00          . 

o-  1    • 

in  1    ••»  1^ 

00  1    •iKr->  ' 

c 

II  CO 

0 

a-    0 

-0    0 

t^     0 

<j<    0 

0    0 

0    0 

c     0 

0     0 

c    0 

x>  1  0 

II  -1 

1 

-■     1 

-•     1 

"* 

""* 

-<     1 

-"     1 

-•      1 

(M 

-1     1 

00      1 

,%i  II    .   • 

11  OOCO 

OOCO 

OOJ- 

0  o*-* 

ooco 

oc?- 

oco 

OOINJ 

co-r 

oco 

00 '.n 

;:'  II  ^r"0 

rOC--X 

-CfX 

<r  ■■Ni<r 

r-o-vj- 

ocn 

0    0 

^oin 

mm -J 

-TOO 

xoo 

3  II  -O-HO 

O'-'O 

(\J-hO 

(M^(M 

r\jrv)-i 

0  —  0 

in     0 

c-m-H 

-o  I  0 

m(N-4 

co^o 

i.£  II  O- 

• 

'-   1      • 

in  1    . 

-T      •*  in      • 

0- 

CT- 

in  1    . 

r-      • 

00  1     . 

in      • 

'-     I     '-'     I 


II 

^^ 

.  .  .0-0 

II 

ocoino 

^^  II    •    • 

«  * 

•  • 

•  • 

•    • 

•    • 

•  • 

0  r-  -<"  0  (SI 

II  CO--" 

oon 

co- 

00 = 

00—      COiNi      OOJ- 

oco 

com 

ocn 

ooc;- 

xo--"  •  • 

;»  II  r\j -J  i-u 

<-om 

in  in  in 

ox  — 

r~a":n     ^thJ^-    o-oo^ 

m  — in 

o-t~o 

inc-c- 

o-co 

r-o—oo 

Z;  11  in     0 

(MNJ-' 

— *fM^H 

rgm.-Nj 

-T-r^     >j--J-^    -T— *o 

— —  C 

om  — 

m—o 

0—0 

in^)--'  1 

c-  11  CT- 

0  1    • 

n  1    • 

-T         •* 

t  r\      •ecci    •itr'i    • 

0  1    • 

tx,        t 

X  1    • 

in  1    • 

mm  1 

11  no       0 

a>     0 

-0     0 

r-     0 

c>     0     0     0     0     0 

0-     0 

0     0 

c     0 

in     0 

xco 

—     I     —     t     _• 


t-  II   • 

• 

• 

• 

• 

• 

• 

• 

• 

• 

1^^ 

0  110 

0 

0 

0 

0 

c 

0 

0 

0 

0 

0 

00 

3  II  <o 

0 

0 

(SI 

X 

0 

•0 

-1- 

0 

>«■ 

X 

SjC             I 

II    Nf 

INI 

-T 

X 

a- 

cr 

in 

tsi 

0 

n 

r- 

0 

u-  II  o- 

^•^ 

in 

m 

>j- 

X 

0- 

0 

r~ 

X 

in 

u.>-ci     _i 

Ol  II  CO 

cr 

.0 

r- 

0- 

0 

0 

cr 

0 

CT- 

in 

LJCa:     -1 

;y.  II  -< 

—* 

—4 

-^ 

0-* 

--4 

^^ 

.% 

^4 

X 

OCIillU      < 

II 

^— 

►- 

t~ 

1- 

1- 

H- 

1- 

^ 

1- 

1- 

r^ 

1- 

•  II 

z 

■^ 

z 

z 

T' 

z 

z 

v. 

z 

i-i-t-Z-x 

a  110 

lU 

m 

LU 

0 

LLI 

ou 

LJJ 

•<• 

LU 

-t 

LU 

in 

LU 

CD       LU 

•0 

LU 

•T 

HI 

ccao«i 

Z  II  r-  ix  0 

—oco 

mnto 

maco 

incKo 

^~l 

iO 

mti^ij 

O'oro 

-euro 

oc^o 

1-i-H-Q.r; 

II  ^H'~ 

mc 

UMl 

—0 

crc 

ino 

ma 

— c 

-C 

inc 

c^  lieu,  cr 

in  lice 

mc^ct 

ma 

C. 

no.  a 

r-i 

toe 

001:0- 

moco!; 

«ra:a. 

inoriY 

y-a.*- 

•3  II  ro  n 

\u 

r-rfuj 

m-ir 

■X 

f^cr. 

UJ 

■not  UJ 

mi 

:y  'J-i 

mcr-lu 

■nncLU 

xrjr 

■.u 

xrr 

lU 

ISC^Z 

0  II  —  -1 

Oo-v 

—  li- 

lO. 

—  u. 

IC 

— u 

JT. 

— '. 

■i-'rt. 

—  1 

ua 

—  UJO. 

— 'ij 

lO. 

—  li- 

;i 

jilUO 

48  Bulletin  654 — American  Railway  Engineering  Association 


»-       »- II  ooa>    ooeo    oo<M    oofvj    ooo^    oom    00.0    oor-    oo— i    oo<>i 
oii-o-oo    >>'-o-o    •*»ro    (Ttmo     -o-o-j-     •o-tto    r^r~-t-    — <-^t>*    •^•fo    -^o>«r 
uj         >-iif^r--j     oor-o     00     O     o     O     roin-^     oir\o     -rcoo     mo^-^     -^oo     ■O'-'O 
o  iir*rg  t     -o-^  •     ro       •     ^^       •     fNj^-#  •     rn^^  •     oo       •     rn^n  •     r*       •     r\j  i    • 

o  iicgot^loi/>oooo>rooioooooomo>l-0 


II  u> 
II  rg 
O  II 


II  oor^     oor-     ooo     oofo     oo-o     ooiri     ooo     ooo~     ooo     oor-     oo-o 

^iih-r^»o     ^fMO     t/>rO(\»     >o>o^     osi^rg     oou^     mr^CT*     C7^ir*a^     oo     o     mn^«o     in<-*4'  i— 

3  II  O^^O     00  I  O     1*^  I  O      ^^     O      str'^^0     ro^o      O^^O      rgr-io      -O      O      fM  I  O      0*1^0  OOOO 
ociirg       •r^       •m       "Oo       •■!■       •»oi«tD       'O       'irx       --r       ^r-       .i-... 

timoir»o^omoooooooooiAoiAO>j'0— <o        moo 

II  rg  tMi-^l-H  -<  ^1^  -^  lin  u. 

II  -I  O 

II 

ON    II..  ..  ..  ..  ..  ..  ..  ••  .•  ..  ..  I- 

II  OOO     ooro     oocr     ooso     oo<\j     oo-J-     oooo     oofo     oo-«     oo<m     oo-<  z 

z  11  fMfvirM     (Ni«ra^     ^-if*>co     m^nm     ocor^     or^cT^     o^r^^-o     ^r~^^     >r>rr*-     miA— *     ogcom  o 

zjiicor"-^    -otvo    ir\^o    --    o     (M-^-<    <M-^o    (D'^o    ro^^    -o  I  o    (\j  I  r-"    r-^ro  o. 
GCilfNJ       .f^i.in       .00       .^r       .oi^oo       .o       .m       •     ^       .r^       • 
iimomo-J'Orooooajooooirioioo-ro-^o 

II  (M  <\j|-i  -^  -<  ^(^  ^  I  |ir\  _i 

11  ^  < 

II  3 

ooii*.  ••  *.  *•  •*  ••  ••  ••  •*  ••  ••  1— moo 

II  ooo     OO"^     ooro     ooo     ooa>     oo~}-     coro     ooo     oo— <     oom     ooo  o 

2^  II  CO  com     *ooj*     sOcoog     o     o     r--^o     c>r-c>     oofMO     cmo     fsj>rr--     oog^     m— «(m  < 
Oilco.-^i-'     mm— <     m— <-<     -J     O     Olo     r\j— 'O     co-^O     rotM— ■     r-     o     r"     O     mf^o 
aiiiNi       .i^i.m       .00       •-!■       •     o  I    '     :o       •     o       .m       •>!•       -i^       • 


II  (M            (NJi— <  -^            ^1— <|-<  — <  m  oomuj 

II  -■  _im     7 

II  _i         O 

r^u>«           ••           ••  ••           ••           ••           ••  ••  ••           ••           ••  <         Z 

II  o org     0003     oooo  oOfM     OC-"     oom     oo-"  ooo-  oo-^     oor-     oom 

2:»-t<iC)     oofO     coo>o  ooi^     r^--C-     — *mCT'     rgor^  >oog>-  — ^.-'^m     mroo     o>*to  ooo 

rj  II  <\iAj^     r— -^o     ^-^o  o-^c     cj  i  ^.>     — iro— <     m     o  ^m— "O  i—     o    <m  i  o     i^mo  ooo 

c£iirsii*r-|.m       .ool'^r       'Ol^co       .o       .m       .^j-       *oi»  rgmo 

iimomo-i^omooocDOcoomomo-rO'-'O  ••• 

iipg|(-gi-«  -11-11— i(-i  — ■  iml  ' 

M  -■ 

II  H-a:.- 

^ii..         ..         ..  ..         ..         ..         ..  ..  ..         ..         ••  :r'jjujjj 

II  OOO      oooo      OOO      ooo      OOr--      OO-l-      OO^      OOO      OO^      oom      00(7-      o>>> 
Z  II 0OCOC7-     -oom     ^Hrorg     o     o     o— <f7^     a-f^o*     o>tfNj     o-mo     rg-JT--     o.'\i>r     ^om     o-OOO 
3  II  ctnJ--^     r*^^o     ^     o     — <     o     f«ir^(M     rg— *o     oo     o     roog— <    f-     o    ro     o     — *a-o 
oiiirg       .r^i.m       .oo       .^r       .li-oi.oo       'O       .m       .-r       .co       • 
iimomo-TomoooooofDomomo^ro— 'O 
lirgrgi'H— •— I'^l'^— •  mi/) 

II  -.  I- 

II  O 

mil..  •«  ••  ••  ••  ••  ••  ••  ••  ••  ••         i 

iioorg     oo<7<     oorn     oofo     OO-O     ootM     oom     oo-o     oom     OOI^     OO-J- 
zit>j->l-r*-     oor*^     org^^     oo-^     f^Otic     f>js3-(-g     OOO     OOO     OiNim     mi-*-iO     rgcoo 
ID  H-rcyr^     mro-^     r^lO     — •     O     — <     O     ^lO     0>rg— •     r<^— «— i     o  I  O     rg  |  o     rgo-o     O 
c^iirri      .-tfr-i.m      .113       .-r       .o       .33      .o       .m       •-<-       .i;       •     o  ; 

iimomo>J-Of'>OOOoooa3omoir40-4-0'-^0'-^ 
II  rg  rg|— 'l-H  — <  — <i— 1  ^  1  im 

II  ^  I  r 

II  I 

^11..  ..  ..  ..  ..  ..  ■•  ■•  ••  ••  ••  I 

II 000     oof^     00-0     ooco     ooco     000     com     OC'O     oom     cr:o     ooco 
^  II  oooo— "     oorg     ^t^.^     o-*Tg     ococo      OOO     o-rri^     c- s- c     — 'mir     -^  ,-r-      .-■-rr— •     ^ 
I3iir^rg— I     XIO     rg— *— '     olO     mrorg     — *rn-4     f^     o     rrrvj^     f--     o     (\,|''"-     '■■-■--:      — • 
ariirg       .f^       .mi*     00       .>3-       .iJOI.aj       .0       .m       •-*-       •^-        • 
11  m     o     m     o     -I"     o     rn     o     o     o     00     o'    00     o     m     o     m     o     ^     o     —     o     ;"' 
II  rg  rg      I      -<      I       -^      1      -"  -.       |      ^  -t  I      m 


Q-  — ' 


m  II    .  • 

.   • 

.   • 

•   • 

•      • 

•  • 

•   • 

•   • 

•  • 

•   * 

< 

uy 

II  c  0  o- 

00-4 

oo^r 

00-" 

oo~r 

oooo 

OO-i 

000- 

oom 

000 

ocr^ 

— ' 

7  II  OO^- 

f-r-m 

rt-imm 

r-mrg 

rom-4- 

ooco 

rgom 

orgl~- 

org-i 

X 

0 

OtNJO 

> 

0 

"^  11  f-rgo 

^tro-i 

•4-     0 

0  1  0 

rg-i-H 

m-'O 

03      0 

rg^O 

co-'rg 

rg 

0 

m-io 

UJ 

c:  II  rg       . 

f^  1    ♦ 

m      • 

CO         • 

sT         • 

0  1    • 

oc       • 

0       • 

m        •«•  -T 

* 

1^       • 

II  m     0 

m     0 

-J-     0 

fo     0 

0      0 

00     0 

00     0 

m     0 

m     0 

4- 

0 

—1     0 

II  .-M 

rg      1 

-t     1 

—1 

-"      1 

-^ 

—t 

m 

II 
II 

"   , 

II  oo-- 

oo-" 

ocxi 

oo-< 

oom 

COI^ 

oorg 

oom 

ocr- 

COO 

oorg 

2  II  mmm 

t7-r"-i 

mrom 

mrorg 

>rom 

mmrg 

oom 

co<r  J- 

-f  00 

CO 

0 

mc--< 

3  11  o-<o 

cc     0 

^rg-4 

-4     0 

rg-i— 1 

rgrg-" 

00 -<o 

rg-io 

1—     -> 

rg 

0 

oc:  II  rg 

1- 

m  1    • 

00       • 

-I- 

0  1     • 

00 

0 

m 

-T 

• 

r-       • 

II  m     0 

m     0 

-J-     0 

m     0 

0     0 

00     0 

00     0 

m     0 

m     0 

J- 

0 

^H 

,-t 

-<       1 

—4 

—4 

m 

^^ 

•    .    • 

00 

OOOi 

r-gc 

.  . 

.   • 

•      . 

.   . 

•   • 

«    . 

•   • 

•  • 

• 

•   ■ 

Org(\JOrg 

II  oor- 

OOI~- 

000 

000 

ooco 

com 

oo-" 

ccc- 

ocm 

C- 

org 

ooco 

-r  j-o 

«    • 

Z  II  rgrg-r 

-rrgo 

00     0 

0         0 

f*-im>r 

-iirvoo 

rg,l-rg 

nTOCT 

O0D,J- 

mm-i 

mo-m 

3  11  o-<o 

CO  1  0 

m     0 

-■         0 

-■     0 

O-tO 

r~-  1  0 

,rm— 

f-     -1 

rg 

1  -< 

oc  mo 

o     -•     o     min 


1-  II    • 

. 

• 

• 

• 

. 

« 

• 

1—1— 

0  II  0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

3  11  0 

0 

00 

0 

00 

0 

0 

-J- 

CO 

X 

>1- 

3  j:         j: 

CD 

m 

,-1 

n 

~1- 

1- 

>-< 

0 

fM 

m 

00 

•r 

0 

CO 

0 

m 

nT 

1^ 

u-i-Qi:     -1 

-t 

ro 

0 

00 

00 

m 

m 

~}- 

—t 

ujoa:     -1 

Qi  II  rg 

iN 

^H 

—4 

—4 

,-t 

—4 

m 

oi:s:aj     < 

t- 

1- 

i_ 

^ 

1- 

1- 

1- 

i~- 

—4 

•  II 

T 

y 

T' 

z 

z 

p- 

.r- 

Z 

2" 

^ 

1- 1- 1~  ^  x: 

C  II  iri 

Ul 

m 

iij 

-4- 

O-       UJ 

—4 

UJ 

rg 

UJ 

m 

m     UJ 

m     UJ 

m 

UJ 

^  II  (Mci:o 

moro 

-.ao 

mtico 

oonco 

moro 

o-a:o 

moco 

-4  0:0 

OC^O 

II  -"C 

—  0 

00a 

mo 

mc 

-iC 

rgo 

ma 

oo 

OO 

a  II  r^ao: 

to  oca: 

i^orrci: 

cq:oc 

OCtK 

ccctoc 

r-Qt 

lil 

r-QCCL 

octcr: 

r-or.or 

l-CCI- 

<  11  (7- or 

UJ 

O-rtroj 

rr^rL 

Ul 

rg3L  UJ 

OCT  lU 

0  Y 

u: 

c-x 

UJ 

r-cioj 

mciruj 

ma: 

Ul 

iDOf  Z' 

(_'  M  0  UJ  a 

O'-L 

la. 

Ciu 

IQ. 

muJC. 

mu 

Jfl. 

OU. 

IQ. 

OUJQ. 

OlUQ. 

OUJ3. 

OU 

IC^ 

>-(j:c/. 

II 

.-M 

m 

-f 

m 

0 

r- 

a 

c- 

;:, 

C  _1M.- 
1-1-3. 

Tests  of  Coupled-in-Motion  Weighing 49 


-3-  — • 


^ 

OO-" 

ooo- 

coco 

OO'^ 

OO.0 

ooco 

ooo 

ooo- 

ooo 

^_i 

s\r\C} 

iNJ  .-NJ  .-«** 

OO'-' 

ivj  a;  .-Nj 

DtSIO 

ajtNir- 

-^— <— * 

,^ 

a-i-iO 

rrir^O 

J-tMO 

intMO 

ao-iO 

, 

CO           • 

-J-   1      • 

O   I      • 

O  1     • 

(yrrt    • 

o     o 

CO      O 

o    o 

J-       O 

00      o 

J-  1  O 

r--     o 

(\J      o 

tr> 

00 

<D         1 

O        1 

f"      1 

>r     1 

in 

\r\ 

a  II 

"' 

"^ 

'^ 

•^ 

^^ 

r>j 

(M 

^-  II    •  • 

•    • 

•  • 

*   * 

•    * 

•    • 

•  • 

•  • 

•   • 

"            --,  ^^ 

ootM     ooo-     oof"     ooo     oo(M     ooc-     ooj-     oox     ooco     oor~     ooj- 

.    „  irwn-i     miTia;     cr^m     ■4-r\i-'     o-J-t\,     0(m— ■     roncT-     sOtMoo     -•■^a>     r^^--o     (nj.-\j-i     h- 

3  ,t  f^     _i     r-     o     oio     r--io     ir>     o     oio     rvj-^o     crj-.-vj     r-^-^o     ■o-'O    o<\JO     oooo 


Of  II  -J- 


-i      I      —       I 


CT-  11 

OO-n 

oor- 

oo-o 

OOf- 

OOt>J 

OOro 

OOOO 

oo-- 

OOO 

oo^j- 

ooin 

V  II 

ina>j- 

rri.-or-- 

J^^~->o 

-0  >r>j 

O-iJ-O 

o-oo 

-•    o 

00      o 

f*-i— 'O 

r\i—i'~> 

C  1  o 

Of*^*N 

>Cf\J'-' 

(Xim— • 

o:  11 

~r       • 

» in       • 

o       • 

.X        • 

O  1      • 

vT          • 

XI 

^    1      •il- 

l~-  1    • 

.-NJ          • 

^       ' 

-1      1      -■      I 


=:> 

oom 

OZir^ 

ooin 

oo>r 

OO.-NJ 

OOO 

oom 

ooo 

oo>r 

ooo- 

l-^OO 

JDOO 

f^l~-0- 

r-o-co 

iNCOfO 

■s\r^:y 

,o     o 

-1 

f-     '-' 

O   1  O 

O-.N.-" 

-o-'O 

rU"^— ' 

(?-'-' 

(r<rfM 

IX,     c 

o 

JO         • 

o 

^        • 

r-  1     • 

-J-  1    •« 

r—       • 

r-       • 

3C        O 

o     o 

r"      O 

-J-      o 

in     o 

in     o 

—1      1 

-'        1 

-1      1 

tNJ 

rg 

■m 

_im    -z 
_l         o 

^ 

II    •   • 

.   , 

,  . 

.  . 

.  . 

.    . 

.  . 

•  • 

•   • 

•  • 

<        z 

oo-i- 

ooco 

OOtM 

ooo- 

00-' 

oor- 

oo>»- 

-^ 

r — i-o 

j,r-T- 

C-C^'- 

0--'-'> 

i»Mno 

r rcO 

r-r--c 

-^ 

om^ 

w-'O 

r— .NjfM 

D.M-' 

0--J-r" 

O.'NJO 

o-'O 

OlMO 

o 

0- 

O  1     • 

rfW     .it  r-   1     • 

-J-    1      •»  CO 

rsl 

=0      o 

o     o 

rA      o 

>r     o 

•    •    • 

M                1 

-•      1 

-'      1 

—       1 

-'      1 

CNJ 

tNJ 

" 

i-a:a:(^ 

o 

OOP- 

oox 

OO'O 

OOtNJ 

OOP- 

oOin 

oooo 

ooo 

ZUJUJ'JJ 

-^ 

j-i— ro 

— 'inr'i 

-TOru 

r-.-in 

vOfNJ-'^ 

rOf^sO 

T\'r>fn 

C<m-i 

-^ 

1-     o 

O   1  O 

■a  1  o 

r--rv;— ' 

-'      O 

m.'N-' 

oomf" 

O-'O 

S\         ' 

o       • 

03          • 

o 

^         • 

00          • 

-T  1     •*  aD       • 

CNi    1        • 

11  J-       o 

■SS      o 

^     o 

n     o 

^    o 

O      O 

.-o     o 

-r     o 

m     o 

in     o 

.n  11    •  • 

^, 

OOrv 

ooo 

OOtM 

CO-" 

oo'n 

OOi^ 

COO- 

ocm 

_« 

o-co 

sr  COO- 

•J-fvJO 

ccoc- 

rnro.'Nj 

(MOX 

.■\jOl-vJ 

Z)  II  t«1 

^^ 

CT'-'O 

fO-iO 

OOPii-' 

-.      o 

coini'i 

a-     o 

r--cN 

• 

o 

c        • 

O  1     • 

-■^  1     • 

CL-           • 

<  1    • 

» J-- 

rvj 

r-        • 

m     o 

in     o 

CO       O 

X     c 

o    o 

m     o 

-1-     o 

-'^      w- 

■n 

-1     1 

—      1 

H 

^  II    •  ■ 
II  OO 

^ 

no 

OOr- 

oca- 

c  or^ 

OOCC 

OCl^ 

ooo 

oor- 

oc  — 

CCINJ 

CO—" 

C.J-(Vi 

ooco 

-T-O 

XINJX 

C-0-r<- 

XXr»^ 

■a     o 

r^^.i^— • 

O.-vl-i 

:»--'0 

C  1  o 

C--'0 

a^<Trr\ 

l~-  1  O 

o-«r 

— ' 

o 

c-       • 

O   1      • 

nT 

r-  I    • 

<T  1     • 

«(■- 

• 

r^       • 

II  -J- 

O 

in     o 

UT       O 

OO      o 

.o     o 

o     o 

CI     o 

•J-     o 

J>      C 

in 

^  I  ^  I  r-l  I  ^ 


;;  II  .\-     o     r^     — <     '-*     o 


cor- 

COX 

00-' 

OOi^. 

00(^. 

occ 

OOI^ 

f^f-,*^ 

-^j-\o 

inr-:^ 

-nrom 

'^r^  -«^ 

o  1  O 

-.      o 

ri— •-' 

O-'O 

xm— . 

X  .n  o 

O  1     • 

X          • 

in       • 

X        • 

M          • 

f-       • 

-I     I      -I 


'"N* 

11   -*o 

ooc- 

CU.n 

coo 

OC(^ 

.4,*,, 

ooin 

COr^ 

ooo- 

OOO 

o-4-in 

ooo 

C-rr-^ 

^oin 

^-J-.%l 

■m'-io 

o 

O  1  O 

0-rsi-< 

inrg— ' 

<    o 

C--'-' 

->    o 

O- J-tM 

X  1  o 

r-njo 

o-  1    • 

03  1     • 

o       • 

(<\  1    . 

X          • 

.f  1    •* 

J-      O 

00      O 

X     o 

o    o 

C-1      o 

>}•      o 

in     o 

in     O 

1 

'~* 

-'      1 

"^ 

-'      1 

tSI         1 

'^ 

.    .    .-lO 
OOOOO 

1 

11    •   • 

^    ^ 

,    , 

,   , 

,  , 

,    , 

•   , 

.    « 

•  • 

•   • 

•    • 

O-'C-O^ 

^ 

oo-< 

ooc^ 
— 'f*^^ 

?iS^ 

o  o  o 

X1--JO 

O  Dir 
o--<c 

oo*- 
:r-<o 

oox 
c-oo 

oor- 

(-vinj^r 

C1--0 

^,Ni—     •    • 

-:^ 

(■ufNJ  1   OO 

— ' 

—  1  o 

J~-  1  o 

n— 'C 

^^—4^^ 

O  1  o 

Or^nj 

'-j.-n—* 

O-'O 

-^ 

e  n  1    ■»o 

X 

c       • 

•t 

-.o      • 

-J-    1      '-S 

■  X 

(\J      • 

r-'       • 

'~*'T* 

IT.       O 

in     o 

X       O 

X      o 

o     o 

-o      o 

J-      o 

u-1         O 

-'      1 

-• 

-■ 

-•       1 

-'      1 

(-g 

rvj 

'■'"' 

^-'-~* 

n 

O 

c 

o 

o 

o 

o 

o 

CDO 

n  11  X 

X 

<r 

o 

O 

X 

o 

X 

o 

c 

>J- 

o 

r- 

-r 

o 

^^ 

-n 

ru 

o 

X 

O 

vT 

X 

in 

r~ 

<M 

r-- 

in 

in 

X 

X 

o 

m 

-r 

m 

in 

•-* 

,^ 

^4 

'^ 

rM 

<M 

^ 

^_ 

^ 

h— 

1- 

h- 

H- 

,-* 

^~ 

-^ 

-- 

i^ 

Z 

^^ 

y 

'>' 

^ 

UJ 

ro 

in 

III 

i-O 

<VJ       UJ 

o- 

vT 

UJ 

in     UJ 

in 

UJ 

.r.  II  0(i:o 

'-'fi'O 

mtiio 

ly 

,-£0 

in  oio 

xnfo 

inrto 

-'CtlO 

injio 

njnr.o 

II  o.: 

-^ 

•czz 

mo 

n 

— ^C 

mo 

LT-) 

xc 

— 'ri 

r  f 

■cere 

i^aic:: 

i~-i^a:r 

x  nr  ly. 

c:  txo' 

Ol^CX 

r--cici 

■X IX  a 

—  oc 

1— 

•.n  T 

'1  ■ 

CT-n: 

'ij 

r^ 

ri-UJ 

c-criu 

O  lY  'Xl 

tvji 

Y'LU 

m.-ir 

!U 

c  «.••■' 

iSOt 

.^ 

(..'  11  iii 

ilCl. 

I'X 

Oi^ 

;.T. 

O 

■UCL 

C^LIO. 

.n:il=. 

in 

l-'-i 

C-J.. 

i;\. 

OJjn. 

J.  11. 

Bill.   654 


50         Bulletin  654 — American  Railway  Engineering  Association 


t-  IIOO-< 

oor- 

OOCO 

OOOO 

oooo 

O  II  ooo 

octNJ 

oooo 

ooo 

oooo 

t-   II  OtNJfVJ 

OO'-' 

r-cro 

-0.O-I 

-T-O 

II  m-c  • 

-oo  • 

co-<  • 

0(\J    • 

l\l~-l  . 

II  r-  1  o 

J-  1  o 

ic\     o 

O  1  o 

—      O 

fi  m      1 

ro        1 

—« 

-r      1 

cr 

II  og 

INJ 

(N 

tM 

f-4 

O  II 

OOO      OOO 


OOO 

00-" 

OOO 

ooin 

oor- 

oocg 

tSJO-' 

if\r-o 

tOIMO 

p-fTi  • 

1 — •  • 

CT-  1     • 

iioo-o     oor^ 

Z  II  OfM0>      OOtNJ 

Oiiin-j-in     NOf"-" 

<X  II  -O— '    •■»  J-  I     • 

Iiml0mo-'0r0      00>000-'0<0      0ro00>0-0l0 
iKsirrjicN  (Ml-<|f\j|rvj  -J|pj  lOI 


COrvi 

OO--       OOO 

oocr 

ooo 

OOf^      00<M 

OOO 

OO-' 

0<M0 

Oi-gj-      o-l-t\J 

OsOrvj 

o    o 

OfNJCNi     orsjc^ 

OOO 

orjfO 

K- 

0>(M-i 

incoro     O  1  O 

tr\  1  o 

in     o 

vOsTfM       00<MO 

0<^-i 

COI^W 

oooo 

in       • 

(7>  1     •«-■ 

•o      • 

fO         • 

r-  1    ••»  o 

a-  1    • 

-irM    • 

1-  •  •  • 

II 


O  M      •     • 
II  OOCM 

OOiTv 

OOro 

OOvT 

OOO 

ooo- 

OOO 

oor- 

ooin 

OOO 

OOO) 

t- 
z 

^  II  orMa> 

OOCO 

orMro 

otNir- 

OOro 

OO-M 

o      O 

OtM— 1 

OiMro 

o     o 

ocoo 

o 

ZJ II  r-(NJO 

r-<NO 

•J-r-ro 

O-J--' 

rO(M-i 

in  1  o 

in     o 

00(M-< 

o-ro— I 

o     o 

1^— o 

a. 

ct  II  r-  1    • 

■J-  1    • 

O         •»  (T-   1      • 

^^       • 

o 

ro       • 

r-  1    • 

o       • 

o       • 

~r       • 

II  ro     o 

ro     o 

-"       O 

ro      o 

(7"      O 

o     o 

-1     o 

00        O 

ro      o 

o    o 

o     o 

II  <\)      1 

rg       1 

rvj 

<M         1 

^A 

<M        1 

(M 

-*      1 

tM 

o 

-I 

II 
II 

tM 

< 
3 

CO  II     •    • 

•   • 

•   • 

•     • 

•    • 

•    • 

•  • 

•  • 

•    • 

•    • 

•    • 

l-O  — o 

II  O  O  <D 

oc  o 

OOI~- 

OOro 

OOO 

ooo 

OOO 

OOO 

ooo 

ooo 

ooin 

OIM 

Z  II  orvj— 1 

OOi~- 

orsjoo 

Orsiro 

OOro 

o-r-" 

o     o 

OtMf^ 

otMin 

o    o 

OtM-< 

< 

Z)  II  ~i-  in  ,-M 

ir^_i 

ro^tNj 

Oro^ 

rO(M-i 

COtM-H 

in     o 

r-ro-4 

r-— lO 

o    o 

tMtOO 

a:  II  f--  1    -it  vT  1    • 

■O        •«■  O  1     • 

r-l              • 

O          • 

ro       • 

r-  1    • 

o       • 

o 

-r  1    • 

II  m     o 

ro      o 

->     O 

vT      O 

o-     o 

o     o 

-J      o 

00       O 

ro     o 

o    o 

o     o 

3 

II  ."SI         1 

fM       1 

rvl 

rM        1 

f~t 

IM 

.-M 

— '      1 

tM 

-^ 

O        1 

OO'JMU 

II 

tM 

_lro      Z 
-t          O 

r-  II    •  • 

•   • 

•      • 

•     • 

•  • 

•  • 

•    • 

•    • 

<        z 

II  OOnI- 

OOI- 

OOJ- 

OOO 

ooo 

oor- 

OOO 

OOO 

OOtM 

OOO 

oo-i- 

2"  II  CNJJ- 

OOrvj 

0(MC< 

OtNJ— ■ 

OOro 

o-io 

OO  J- 

otMr- 

OtMtT- 

ooo 

OtMin 

ooo 

3  II  —•ODro 

-Oro-. 

^.J--. 

coinrvj 

rorvj— 1 

r^-iO 

nT-iO 

f-ro-J 

tOtMO 

0--4-1 

>J--iO 

OOO 

Qi  II I--  1    ■  -a-  nJ-  1    • 

-0         • 

o  1      •*  — 1        . 

o       • 

ro  1     . 

r-  1    • 

O          • 

cr  1    . 

ro-i   • 

rsiino 

II  ro      o 

ro     o 

->    o 

ro     o 

o>     o 

o     o 

-1      o 

00       o 

ro      O 

0-     o 

-O  1  o 

•   •   • 

II  INi         1 

rvl       1 

rg 

IM        1 

•~* 

rM        1 

'-*       \ 

(M 

1 

O        1 

oo-< 

II 

tM 

h-ora^a 

-O  II    •    • 

•    • 

•    • 

•    • 

•    • 

•  • 

■    • 

•   • 

•    • 

•    • 

«    • 

ZLUUJUJ 

II  oo-j- 

oor-- 

OOM 

ooo 

OOro 

ooo- 

ooo 

OOO 

OOCO 

ooo 

oo>i- 

o>>> 

Z  II  OfN)f> 

ooc> 

or\jo 

OOO-l 

OOCO 

OOrsj 

o     o 

OtMI- 

OiNIO 

o    o 

OtMfO 

aooo 

Z3  ii.cm-< 

(Mr- CM 

at\j— 1 

Otsj'-* 

(M-iO 

in  1  o 

in      o 

r~-ro-j 

O       O 

o    o 

COI--0 

q:  II 1^  1    • 

-T  1    '«  ir\       • 

o       • 

-A        • 

o      • 

ro         • 

1^  1     • 

o 

o 

to  1     • 

II  ro       o 

ro     o 

-c       O 

sT      O 

a-     o 

o     o 

-1      o 

CO      O 

ro      O 

o     o 

o     o 

II  (NJ        1 
II 

tsi       1 

CM 

(NJ 

'^ 

(M         1 

rM 

--I       1 

tM 

'-' 

o       1 

nj 

h! 

II 

o 

u-\  II     .    • 

•    • 

•     • 

•   • 

<  • 

•    • 

•    • 

•    • 

«    • 

•   • 

3 

II  OOOO 

OO.'M 

cor- 

OO-i 

OOro 

oc:<x- 

OOO 

OOro 

COO 

ooo 

OO^ 

Z  11  0(N— 1 

OOsf 

oooro 

OtMCT- 

OOCO 

oo.-M 

oo<r 

OCMtM 

oojin 

ooo 

otMin 

Z)  H  -ruMNJ 

OD-IO 

-O  1  o 

-IINJO 

(M— lO 

in  1  o 

J--IO 

o^rtsj 

r--iO 

^-<— 1— * 

«r-"0 

o              • 

or  II  (^  1     • «  -J-  1     • 

KS\             ' 

O  1     • 

—4            • 

o 

ro  1     . 

r^  1    •«  o 

o 

ro-i    • 

o           o 

II  rO      o 

ro      o 

->    o 

-J-      o 

CT-       O 

o     o 

-1     o 

x>     o 

.■o     o 

o    o 

O  1  o 

-■                       sf 

II  'Nl        1 

CNJ         1 

(\J     1 

fM         1 

^H 

rM       1 

(M         1 

'->      1 

tM 

,--\ 

O        1 

1— 

II 

tM 

t             in 

II 

1                   tM 

•r  II  •  . 

•    • 

•    • 

•    • 

•    • 

•   • 

•  • 

«  • 

•   • 

•    • 

•    • 

1 

IICOC 

OOCM 

oooo 

OOO- 

OOO 

oc^- 

OOro 

OOO 

OCtM 

ooo 

OOro 

Z  II  CtNJ.O 

oo<r 

OCD.O 

OfVJ-4- 

0«tr\j 

oor- 

OOC 

0(Mr- 

orMO- 

ooo 

or\JO 

z 

ID  II  ro  vO  iSJ 

co^O 

— iir^.iNj 

rM— 'O 

O  1  o 

J--HO 

r-.MO 

h-ro— ( 

COtMO 

rMfMlM 

(Mroo 

—* 

cc  II  r-  1    •«  -J-  1    • 

u>  1    •*  o  1    ■ 

^^        • 

O  1     • 

ro        . 

r-  1    • 

o       • 

o       • 

i-o-<   . 

II  ro     o 

ro      O 

—     o 

-J-      O 

Cf      o 

o     o 

-H         O 

CO      o 

ro      O 

o     o 

O  1  o 

Z                   C£. 

II  rsi       1 

II 

II 

<N         1 

INJ         1 

rsj        1 

'-'     1 

r-o       1 

<NJ 

-■      1 

tM 

'^ 

O       1 

c            cc 

—                  UJ 

•     ■ 

•    • 

•    • 

•    • 

•   • 

•     • 

•  ■ 

•    • 

•    • 

•    • 

<                  1/5 

II  coo 

oor- 

ootsj 

OOO- 

OO-J 

OOCT- 

OOO 

OOO 

OOO 

ooo 

OOtM 

—          I/) 

r-  II  orsi^ 

OCOJ 

OCOCM 

Ooi-t 

OOro 

OOINJ 

oo<r 

OtMl— 

OtMJ-1 

ooo 

OtMtJ- 

>            cr 

3  11  r*^  ~0  .-SJ 

~om-' 

rvi^M 

rsl-<0 

-I     o 

in  1  o 

-1--.0 

r-ro-i 

r--iO 

cr-i-i 

OO-O 

uj            oc 

ct  II  1^   1     •<?  n3-  1     • 

tn  1    •ito  1    • 

f— 1         • 

o      • 

ro  1     • 

r^  1    • 

o 

c^  1    • 

IM— 1     • 

a           o 

II  ro     o 

ro      o 

r-<      O 

^l-         O 

^^     o 

O      O 

-i     o 

=0      o 

i-o     o 

0-     o 

O  1  o 

II  CNJ           1 

II 

(NJ       1 

(NJ         1 

tM         1 

~* 

rM       1 

rsl       1 

-1      1 

(M 

1 

O        1 

tM 

M  OOCO 

OOlA 

OC-i 

ooc- 

oo-o 

ooo- 

ooo 

OOro 

ooo 

coo 

coo 

r:  II  o  .-M  — ■ 

OOl/^ 

O'Si-t 

OfM^f 

OOro 

OOM 

o     o 

orvJO 

otMin 

ooo 

OfSltM 

3  II  .j-iniM 

ro  ^c\l 

rMinoj 

<M-IO 

rOf\j-i 

in  1  o 

in     o 

cr-<o 

r-r-io 

P-4  0-IP-.4 

-J-4-0 

aiir-l     "^t-j-l    '%  •o       'itoi    • 

•— *       » 

-o 

fO        • 

r-  1    • 

o 

o 

-r  1    • 

II  fO      o 

ro      O 

-1      O 

■i-      O 

o>    o 

o     o 

r-l         O 

03      o 

ro      o 

o    o 

o    o 

II  t\j      1 

IM        1 

(\j 

<M         1 

r-< 

CM         1 

fM 

'->      1 

tM 

— * 

O       1 

M 

tM 

.    •    .OO 
OOOvJ-O 

^4   II       •      • 

•    t 

•  • 

•      • 

•  • 

•    • 

•  • 

•    • 

•    • 

•    • 

OOOOO^. 

II  coo 

OOO 

GOTO 

C1C1-' 

OOCO 

ooi^ 

OOO 

oor-- 

OOfM 

coo 

ooo 

iMiT.r--  .  • 

^  II  O  AJ  -c 

O      O 

OtSI-T 

0<M0 

oooo 

O-J-O 

oo~r 

O.-M-J 

OtMO- 

ooo 

OIM— 1 

>nina-oo 

D  II  ro  sO  rv 

0-      O 

OrO-< 

-■tMO 

>J-ro^ 

r — lo 

O-iO 

oo.-M -< 

CCtMO 

r~roro 

rotMO 

-J-ro  1    1 

ri:  II  ^-  1     •«.}•        . 

-C         • 

C   1      • 

*-i        • 

o 

ro        • 

r-  1    • 

O 

0-1     ''it-t   \     ' 

OO 

II  ro     o 

ro      O 

-1      O 

-1-      O 

O-      o 

O      O 

-"     o 

CO       O 

ro      O 

o-     o 

o     o 

CO 

II  rvj       1 
II 

r\J 

rvi 

IM         1 

-" 

(M 

tM 

-■     1 

CM 

1 

O        1 
CM 

tMtM 

II 
K  II     • 

, 

, 

. 

, 

, 

, 

, 

, 

. 

. 

l-h- 

O  II  o 

O 

o 

o 

o 

o 

o 

o 

o 

o 

o 

oo 

3  11  IN) 

o 

00 

CM 

->■ 

o 

o 

tM 

00 

o 

r\j 

i3           jE 

II  (T- 

C7- 

■o 

ro 

o 

in 

in 

O 

in 

o 

in 

o 

u-  II  r^ 

>r 

in 

o 

r-* 

o 

to 

CO 

o 

o 

>r 

u-t-o:     -1 

LU  II  ro 

ro 

,~* 

-1- 

0- 

o 

--t 

to 

ro 

o 

o 

UiCOC       _l 

oc  11  tvj 

tsi 

rvi 

•■M 

-^ 

(M 

rM 

-H 

tM 

,-t 

o 

oriiJJ      < 

II          ►- 

^ 

t- 

1— 

^ 

H- 

1- 

1- 

^ 

y- 

tM 

t- 

•  II          Z 

^ 

Z 

z 

^ 

z 

z 

Z. 

z 

z 

i-i-t-ZX 

o  II  cr     LU 

vf     aj 

o     uj 

ro     m 

,-J       lU 

l~-     ai 

vf       UJ 

O       UJ 

^       UJ 

in     UJ 

ocao< 

^  II  roo:o 

OuCO 

an:o 

'-•n^o 

croco 

O^o 

OOCO 

-1DC(_) 

'-■QtO 

-<ii:u 

1-i-i-a.i; 

II  .J-Cj 

inc 

-OO 

-OO 

-OQ 

rOO 

r-O 

ina 

ooo 

a  II  croro: 

•Jro-O. 

ccoro: 

ojct  q: 

OccQl 

ccac^ 

xaa. 

t~a.cc 

--CJ^Qi 

—  oca: 

>-cc\- 

<r  II  u:a;uj 

NT^rm 

vrrf  lu 

Nfrt  jj 

rOfy'LU 

oaruj 

■•caruj 

QCnLlu 

fMOU] 

f--Q:uj 

OQ^r 

O  II  oua 

■■'■.  aj  3. 

oiiin. 

O'jja 

ouja. 

o  ;.'c. 

oiua 

ou-a. 

r-lJJQ. 

^-UJO. 

-lUJO 

Tests  of  Coupled-in-Motion  Weighing  51 


t-  II  oo 

_, 

ooo- 

ooo 

oa-t 

OO-i 

ooo< 

OOI- 

ooo- 

ooo- 

ooo> 

oo-i- 

oo-j- 

O  II  oco 

oin^ 

o 

o 

O  ri^ 

OO-- 

oi/^o 

oiotn 

oo-r 

oor~ 

OJ>-' 

ooo- 

ooo 

»-  11  cr- 

—4 

oino 

<> 

o 

C0(\JO 

■o.-cm 

no  .-no 

-<0<M 

inin-< 

^<^-|(^l 

-or--< 

ccin-> 

O^-JCsJ 

M  rsi--^ 

• 

o---  . 

o 

• 

,0-i    • 

^-i^fy    • 

r<>— *    • 

OO     • 

mf^  . 

r-in   • 

o--  • 

fsim  . 

CO-"    • 

II  aj 

o 

ro  1  o 

uo 

o 

O  1  o 

.0      O 

-H          O 

in     o 

J-     o 

rsl  1  O 

■O  1  o 

O  1  o 

c^   1  O 

II  .0 

<NJ       1 

■M 

ro        1 

00 

li^ 

rO 

ro 

O)        1 

>r      1 

00         1 

ITV         1 

O  II 

f\j 

<SJ 

. 

rg 

.. 

". 

". 

.. 

.. 

.. 

.. 

icoo  ooo  ooo  ooo  ooo  ooo  ooo  ooo  ooo  ooo  ooc  ooo  ooo 


II  oom 

ooo 

ooc 

ooi~- 

Z  11  00'-.-\ 

ono 

oon 

or\y- 

:3 11  a--"o 

(^.■vj-< 

^»^-lO 

<M(NJO 

ac  11  o       • 

JO   1      • 

■O   1      • 

•O  1      • 

oor-     ooco    oo>r 
Occm     ■^r'>c\j     oDrOi-* 


o 

o 

O 

o 

O 

O 

aoty-o 

o 

o 

O 

o 

O 

o 

inoo 

LLfNJ 

o 

z 

OOro 

oo-j- 

OOO 

ooa 

OO-O 

coo 

oon 

OOT 

0--^'^ 

ooo 

oo-o 

OJ-V-" 

o 

^r^J■-" 

O-OfNj 

—  1  o 

ro,)--! 

0^-<-i 

0<N 

JO 

□l 

o 

m  1     .&  ro        . 

O  1     • 

a-  1    • 

no 

• 

llCOrO      ooo      ooo      OO^-      OOJ^      OOOO      OO-O      OO-V      OC^I      00«J-      ooo-      00'<1      00:n      i^c 

ziiooir\    oin(\j    o     o     oino-     oo-j-    oxl^I■     ointsj     ooc     oo-r    oinw    ootr     ooro    omo     < 
12  H  '^^o     C^  I  O     ^     O     Psj-^NJO     lAro^     fOAi— «     rnoom     ir»'r»^^     or-ro     :^c<^rsi     f*^^^     cOAjro     00     O 


llOOO  OO-J      OOf~-  OOr~  OOO      OOO-  OOO-      OOiNJ  Oor-  OOf^  OOO-  ooo  OOO 

.Til  ooo  o-no     OOC-  Ou-vo-  o     o     oint-vi  omr—     OOO-  oo-r  o-oin  ooj-  ooo  o..•^^/^  OOO 

^  tl  — 'm— *  rooAj      0--^^  r-rsio  rg      o      — *      O  (--i-si*J-      tnj>.-*  rOro^  C7- N**-*  ^.--^^  (7*^^h  O.MO  OOO 

of  II  r-        •  CD  I     •♦rri        •  O        •  O        '00        •  -J— •   "itO        •  rri|«  fsjl.  OI»  0-l«  O- — '    •  t--Jir>0 


OOO-  ooo  oo-c  oo-i  ooc-  ooo 
o-'^r-  OO!^  ooo-  OJ^o-  oo-j-  ooo 
r-(vj^  OOf-vl  r-o^J■^  o— -O  -j--^— <  0--J— • 
-•-'  "-IJO  '^mi  •  mi  .  oi  •  o-l  • 
OOOOOOOOOOiTvo 
(--J  rg  rg       I       -1       I       r-j       I  | 


II  ooo 

OOO 

oox 

00:0 

000- 

0000 

2  11  ooo 

OJ^r^J 

oor^ 

0  n.n 

00m 

0  J^>r 

r)  II  -.m-. 

o-  1  o 

OIMO 

m—o 

(T-r-m 

rTM-Nj-i 

Of  II  r^ 

00          • 

m      • 

0  1    • 

0       •-; 

1-  CO 

u-MI     .    . 

II  oom 

000 

oo'y 

ooo- 

OOAJ 

000- 

oo-r 

oom 

ocin     oo-i 

ooo- 

000 

oo-r 

Z  II  CO :r> 

Ou->0 

OOro 

OJ>  — 

oo^r 

Cincc 

otom 

00-n 

oo-r     0  in  0- 

00-r 

000 

oin-i 

Z3  II  0--<0 

_._iO 

m— 10 

in    0 

r-uM-g 

(M-IO 

CDm-i 

^-r— ' 

'-iini-g     0—0 

r\iiniM 

O--"— ' 

-■mo 

1:  II  0 

:^      • 

m  1    • 

0 

0       ••; 

!•  TO         • 

0      • 

0 

m  1     •  V-  m  1     • 

0  1     •< 

J  0-  1    • 

00      • 

o     o     -■ 


II   •  . 
II  cot^ 

000 

OOOO 

COI- 

COI-- 

000- 

oco- 

coin 

ocf-g     oom 

000-     000 

COO 

II  oco 

Oinrg 

oor- 

Oinc 

COOO 

Oinrg 

oin-< 

OO-i 

000-     Cinin 

oo-r     000 

Ou-v.-g 

II  o,-v-« 

0      0 

.>jrgo 

^rgc 

oorm 

-<     0 

jy     0 

-^m^ 

.— crm,     c-^— ' 

•M  u^  og     o-  — 1  — 1 

-•00 

11 1--      . 

c- 

m  1     • 

0  1     . 

^       .i 

r  T)          • 

C 

C 

(xj  1    .  ii-  r-j  1    . 

01     .  -f  0-  1     • 

r-  1    • 

Q.  — ' 


m  II    •  • 
11  oco 

co-< 

occc 

ocin 

OOi-g 

coo- 

000- 

ooin 

OCO 

oc-^ 

00c- 

000 

cc-r 

<            I/: 

•-■            i/~ 

.-r  II  oc 

:0 

c 

nvT 

ocr- 

cmi-- 

oo^r 

C-nco 

r- 

OO-H 

OO'-.'- 

n.T- 

oco 

Oin-< 

> 

3  II  _4m-< 

*^  ■ 

xim 

OIN'O 

o-r  — 

r-innj 

rv-io 

l--rv 

;-r 

mm-< 

rgsr^ 

o-«o 

m.r-1 

0  '-l  — 

^mo 

ct  11  r- 

• 

X 

1    ••'. 

!•  m        . 

0  1    • 

0       *^  ro       • 

— i  — 

■  •■rf  0 

• 

m  1    . 

r<^ 

1    • 

0  1    • 

c-  1     • 

00       • 

0                          w 

II  CO 

0 

•r 

0 

in     0 

■r\     0 

0     0 

0      0 

0 

0 

-0 

0 

0     0 

0 

0 

0     0 

m     0 

0     0 

11  "-* 

(M 

1 

(M 

IM         1 

f-g 

^^ 

IN/ 

rg 

rg       1 

.~* 

1 

fM         1 

II 
.--g  II    •  . 

rg 

. 

. 

,   , 

.    , 

,   , 

,   , 

,    . 

.    , 

,    . 

, 

, 

,    , 

,  , 

.    . 

H  OC 

;0 

000 

ocr- 

oom 

co-r 

000 

oom 

CO.-M 

oom 

oo-r 

000- 

oom 

000 

.^  II  000 

O' 

nsT 

oom 

oint^ 

ocoo 

Cnf\j 

cm 

:"> 

OOC- 

oo-r 

n-^ 

oor- 

oom 

Oinm 

3  II  _m-4 

-Ci 

'■^^^ 

o-r-i 

o-r-< 

njc-r 

-.     0 

r^r-jO 

inin-< 

o-i--m 

xr 

'irg 

m<-.-i 

lorgm 

cr-o 

a:  II  I'- 

• 

OJ 

1    • 

m  1    . 

.0  1    • 

r--^  •■&  CO      • 

c 

• 

0 

• 

rg  1     .i 

■  Og 

1     »'iO  \     • 

o-l    •tr~  x    ' 

c 

>r 

0 

in     0 

m     0 

0     0 

0     0 

0 

0 

0 

0 

0     0 

-c 

0 

0    0 

in     0 

0     0 

ll  — » 

rsi 

1 

iM      1 

<M      1 

eg 

—4 

rg 

rg 

rg       1 

»-« 

1 

rg      1 

1 

-r      1 

II 

II 

OOC-JC 

-^11    •   < 

• 

• 

•  • 

•  • 

•   • 

•   • 

•   i 

•    1 

•    • 

• 

• 

•   • 

•  • 

•  • 

'-nomor.J 

11  cc 

:0 

0; 

00 

coa- 

OOr- 

oo--« 

ooc- 

C  ''■ 

(-g 

000 

oo-r 

Oi 

-0 

oo-r 

r)0  0 

c  .1;  0 

r-o--i  •  ■ 

^-  11  0 

0 

O^co 

oom 

cmcT- 

ooco 

Oin.-g 

oinr-- 

0 

0 

co-r 

omm 

oc-r 

000 

OJ^  J 

c-  m  >r  0  c 

^  tt  ^ 

0 

sT  ■ 

j--> 

m-.o 

i-'fsjO 

^rcgj^ 

—     0 

C^t 

'#-1 

0 

0 

c-r^m 

.-4 

1  0 

>Tm-i 

O--!-! 

iT— 0 

O-i 

:.'  11  0 

• 

r- 

• 

m  I     . 

0 

f-_.    ..if  TO 

0 

• 

0 

rg  1    .-ii-  m 

0  1    • 

7-  1    • 

rjrg 

II  CO 

0 

-r 

0 

m     0 

n     0 

0    0 

0     0 

0 

0 

0 

0 

0     0 

-0 

0 

0     0 

in     0 

0       0 

rgrg 

II  '~' 

rg 

i-g      1 

t-j 

rg 

r-* 

r^ 

(N 

rg      1 

—4 

1 

.■Nj      1 

-r 

rgrg 

II 
II 

>-  11    • 

rg 

. 

. 

. 

. 

. 

. 

. 

, 

. 

. 

, 

i-l- 

<J  II  0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

0 

00 

ic  II  0 

in 

0 

•s\ 

0 

J-\ 

in 

0 

0 

in 

0 

0 

in 

i:i        -~ 

II  ^0 

'7- 

-r 

-r 

M 

0 

-r 

0 

0 

r- 

0 

f^ 

■A.  II    0 

OJ 

0 

0 

33 

0 

0 

m 

m 

0 

0 

r- 

U-I-Ci       _ 

-r 

in 

in 

0 

0 

0 

0 

0 

0 

0 

0 

0 

ujOn:     _. 

OC  II  -• 

i\i 

.-g 

r-g 

1%J 

.-< 

.-g 

.g 

rg 

rg 

-r 

n-i.oj     '• 

It 

h- 

1- 

V— 

1— 

^— 

^- 

1- 

t- 

f_ 

1- 

^ 

1- 

•  II 

z 

^ 

t'' 

^- 

z 

j" 

z 

-^ 

^ 

Z 

z 

H-l-l-^.--- 

OHO 

UJ 

■0 

HI 

m     oj 

— •     ill 

cc     u/ 

0       UJ 

r- 

UJ 

CT- 

LU 

m     LU 

r<\ 

UJ 

0       LU 

C        LU 

C'CCU-- 

Z  n  rgnco 

•— *i 

YO 

00  ecu 

o-oco 

f-cco 

r-::iro 

on. 

0 

^Q£|_) 

COlCO 

-rCYTO 

00:0 

fvjnro 

>-t-t-a.-^. 

II  -oo 

l/^• 

_v 

iTU 

<NlC 

.no 

rOO 

•or. 

OC 

00 

-ro 

-■0 

00 

It  a  o-oco: 

ini^ix 

core: 

OC-  c: 

■Ocitr 

^-xo: 

30  .V 

nr 

On'rt- 

■tctcy. 

rutlOC 

cocro; 

oarar 

*-ccy- 

•1  M  r-  "<  c-' 

rg, 

fL' 

T"^  til 

-*-,-/ '11 

r-oriu 

c\)r/"ii 

rg,-f 

lij 

Sf 

•ui 

r-Triu 

m'TU) 

r-c^-xi 

iC  or-  IJ 1 

OCJ-J* 

l_;  II  C; 

.'.. 

IS;; 

UO. 

->U.  JS. 

^  J.Tl 

rvi  j,CL 

xiun- 

rsi'j. 

-V 

O'i 

ir. 

■CUQ. 

01 

i.n. 

.-g  ■  IJ  .1 

OU'i 

J.'xJO 

52 


Bulletin  654 — American  Railway  Engineering  Association 


oom 

oo-j- 

ooo> 

OO-i 

OOro 

oor- 

ooin 

ooo 

ooin 

vO-O-'l 

r-f--o 

coo^r- 

^>— ICM 

mr*^a^ 

JOfNJtM 

mr — ■ 

c\j<\jro 

-^(T-O 

in^i^  -< 

o     o 

inr<io 

fl-J-O 

.MCtlO 

cor-(Nj 

-<tNjrg 

u>irio 

oor--i 

a--<  • 

o>  1    • 

J- -J    . 

^sr   • 

— i^J-   • 

0- 

m-<  • 

-•    o 

lA      o 

fO      o 

J-     o 

^       O 

r-  1  o 

CO  1  o 

00       o 

cr  1  o 

OOO       ooo       OOtNi       OOCO       OO^       OOf^       OOOO       OOf^ 


II  oom 

OOfxJ 

00(NJ 

Z  II  rvj-j-r^ 

ooin 

[NJIM-" 

3  II  -O— lO 

m— lO 

-1-     o 

OC  IIO> 

^       • 

lA          . 

r\i     o     o^^-* 


r-  I    •»  cc  I 


a-  I    . 


a- 

IIOOtM       00(NI 

OOCO 

OOIN/ 

ooo 

ooo 

ooo     ooo 

OOCO 

ooa- 

OO'- 

ZllcoOfM      oo^ 

(MCOO 

ooo- 

•O'M-' 

~r     o 

(Njvr^     -\jcNi-" 

oo-" 

<r(Njrg 

3l|.Oco^      ro— 'O 

tNJ^^ 

O-— lO 

O-  1  o 

cNj     a 

^tnrg     roiN— 1 

.— <(NJ'-* 

f<irsi-i 

ac  II  CO  1    •  ■»  — 1      • 

\r\  1    • 

ro        • 

sr       • 

-a 

r-  1    •  -t  .XI  1    • 

cr       . 

c^  1    • 

<r--4  . 

I  -I      I     -• 


00  II     •    • 

II  oon; 

z  H  o~xi<- 

3  II  nT  I  o 

a:  M  (7>       • 

II  ra     o 

II  -I      I 


I  ooo 

I  OfM— » 

I  ~r  I  o 


^      I      ^ 


oooo 

<NJ0O-3- 
c-n   I  O 


-1-1       -I-IO 


ooo 

tNj    I    O 


OO—i     oo— I  OC 

o>OfM     ao>oco  coa 

Psj  sj-  pg     ^^(^^^  o^ 

r-  I     •  ■«■  CO  I     •  CO 

O     o     O      o  sO 

(M        I        -I        I  -< 


OOCO 

v0ou> 

nT-'O 
G-   1      • 


OOvO 
COiA 


OOIN 

cooo 
c^-<o 


oom 
sr  oo 


00-"     oo-" 

O-J-fM  CO.M-H 
— i<f(\J  -O  I  o 
•  --0   I      •  »  30 


OO'A 

ro  <ro 
j^  I    • 


I      ooir»u 


3o-"'       ooo 


1—1      I      —I 


II 


-o  II    •   •  • 

iioom  OC 

ziir--io  >!■< 

3  II  -J-  I  o  inn 

a  II  o-       .  -1 

II  CO      o  o^ 

II  -•      I  -1 


OOCO 
orvj-i 


OOO 
a-  I  o 


OOO 
0^(M 

r-j  I  o 


ooo 


ooo  oo-i  ooo 
^(NiTv  -TOO  ooin 
^^tnosj  — 4>rrsj  co— to 
f—   I     ♦•M-COI     'fl-OOl     • 


7f  UJOI'-LI 

a-OOO 


Tl  II     •    • 

II  ooo 

OOr" 

OOsO 

0003 

oo-J- 

ootvj 

ooo     00-"    ooo 

OO-O 

OOO 

z  II  ~r -ooD 

lAtTtOO 

^^rri 

•o-fro 

O.-MvO 

•CrJ-^ 

o-o-c     o-i-f^-     o    o 

>oor- 

u  II  oom-" 

com-4 

m  1  o 

org-< 

-orn-i 

,J-CM-I 

-I'rifM      OiAAl      O      O 

(\Jro-« 

■ftrso 

Ct  II  o        • 

O  1     • 

\n       • 

^ 

-r  1    • 

~o 

r-  1    • «  CO  1    •  ii-  CO       • 

O   1      • 

<rr^    • 

-1     I     -1 


^  II   •  • 

11  oo<r 

cr,a 

OOCO 

OOCO 

OOO 

ocm 

oo-t 

oo-< 

OOfI 

OOf^ 

coco 

^  11  ^COOO 

cc   '.^-i. 

OJCCO 

cDsj-ro 

-}-vr<N 

OnOcO 

vOOvT 

OOOK 

.o-cin 

~CO-' 

'i~^^-A^A 

lOIVJ-l 

O   1  O 

,om-i 

mro— * 

-<rfl^ 

-KM—' 

mfsl-" 

.r\ 

r<>  1     • 

-^      • 

-0 

r-  1    • 

CO   1      • 

o 

O    1      • 

<5 

o     o 

-0      o 

r-     o 

O      O 

o    o 

o     O 

O       O 

.0      O 

-O      O 

,_4 

.^     1 

.-4 

rvJ       1 

— *        1 

—4 

— *       1 

11 

.. 

,    , 

,    , 

,   , 

,  , 

.  . 

II  OCtvJ  OOO 

;^  11  ^  ^r^  f<^f^f\i 

D  II  O^l-rs:  ~l-(vj-< 
re:  II  o  I    ••(!■—<       • 

II  CO     o  o     o 

II  -•      I  -• 

II 


00(M 

(^  I  o 


OO-O 

-1TSJ(M 

or>J— ' 


OOO 

OOCO 

oor- 

OOrO 

OOin 

CO 'A 

0~0fn 

(N  J-O 

O  Ah- 

-^>1-CM 

o-o.-^ 

-O.-NIO 

m     o 

CnC'CO 

O'Arsi 

O      O 

J^  1  o 

.ncMO 

-0 

r-  1    •-: 

t  r-  1    -4 

;■  cc       • 

o 

<--<  • 

OOCO 

OOro 

OO-" 

oom 

OOr<^ 

CO-l 

ooru 

oo-" 

oor- 

OvOCO 

••M-O-J- 

•O  J-tM 

.oco<r 

Jj>JT- 

O-or- 

fXJIMJJ 

-t-j-^r 

or-vi- 

Z)  II  oiniNi 

inm^ 

ro  1  O 

CC      O 

o     o 

inro-H 

roci-i 

ointN 

— l(M-< 

-r  1  o 

C£   11  CO    1      •  11 

■  .-<       • 

in       • 

(^ 

in      • 

-o       • 

r-  1    • 

CO  1    •«  o       • 

o 

II  cc      o 

o     o 

-o     o 

(^      O 

o     o 

o     o 

o     o 

o     o 

■o     o 

-o     o 

in     o 

11  ^      1 

-•      1 

" 

'^ 

'-' 

INJ         1 

-1      1 

•"* 

.   .  ..vo 

OOOfOO 

,   , 

«    » 

,  • 

*    • 

•  • 

•  • 

•  • 

•    • 

»  • 

o-r-oot\j 

occo 

OO-O 

OOU." 

OOCM 

oor- 

OCin 

OO-i 

oom 

oom 

COa3 

iOi»i7<    •    • 

00^30 

-■-•tvj 

0.:o-> 

COOO 

•r\'->o 

-l-rsio 

-c-oj- 

wr-oin 

.-M-Of" 

-TOO 

3  11  iA      o 

lAn— ' 

•OINi— I 

(vjmiM 

f^-.-NJ-" 

<i-i\i-i 

vrrM-< 

o-^nj 

-OCM-" 

-0      o 

i^<  11  o        • 

'A          • 

sT          .M<)-    \      • 

-o       • 

r--  (     • 

cc  1     • 

K-  CIJ  1     • 

o 

in       • 

-I     I     -.     1     -1 


O  II  o 

o 

o 

o 

o 

o 

o 

o 

o 

c 

O 

JO 

3  II  CO 

o 

o 

00 

sT 

-o 

< 

O 

<J 

CO 

o 

nj 

•o 

n 

O 

in 

in 

m 

■r 

■O 

r- 

CO 

■XI 

o 

■o 

r- 

o 

o 

o 

O 

sO 

-o 

,_t 

,-4 

fM 

,-4 

—4 

—4 

^ 

t- 

1- 

^— 

>— 

k- 

1— 

—4 

z 

?' 

J' 

z 

■:* 

.-• 

z 

^ 

:i' 

O  II  o 

LU 

m     Lu 

o 

lU 

oo 

Ul 

-1- 

LU 

00       lU 

-o 

m 

•J- 

lU 

<r 

LU 

in 

LU 

i^  11  r-niiu 

-ici:o 

inn:o 

roiiro 

ina:o 

Oa^O 

-Oft:o 

0( 

:i:i_) 

r-nco 

-^ 

f*-C 

ina 

— lO 

OC 

-•C 

—o 

in  a 

IOC 

vrr 

rotict 

rilcf 

rr 

morct: 

in  ore 

^  ty 

■1' 

in  I 

Of  or 

t^« 

nt 

-ocrn' 

►—on 

►— 

f^rv 

11 1 

I'^iY 

>!■ 

inr^LiJ 

inoriLi 

cf  01- 

iij 

cr.-i 

L';'  1 1' 

r^iy. 

LU 

ri-oruj 

O  II  o 

C.)  lU  0. 

a. 

-IIU 

0. 

lIw 

— *  ■  L*  o. 

— *iu 

LX 

—II 

lUO- 

-•u.  -L 

--t_L 

la. 

_£'-U 

Tests  of  Coupled-in-Motion  Weighing 


53 


00000  000C000  0  0  000  0  0ir>000  000  0 

00>o-Hf\joc~c\iaorr\r-(n^o>rvrvr(Mr-vj-r^>j"ir\>fir\vOro 
mvOir\.T»rs)>0(Ni'^oo«rcoc><NiiAoocr'-<0'NKT>>rcor~aor^ro 
^0l/^00>J•.O•-^-0-£)-^lP00rf^-H^CO^-N}■>J■^r^r^rf^^0^r^Lr^^0f^|/^ 

_,„^,^,H^(M— 1— IfVJ— <^-l— l(M— l(NJ— 4f\J— <-H— l<M— <-^(MrOf\Jr-« 


-J  in  00  — *  >r  r>- to  o  iTi  »r  CD  ro  r<^  >j- 00  ro  — <  CT>  rn  r- o  vO -H  vo  00  <NJ  m 

roir\OLrnn.oo— 'f\i(NifMf\jO'-'00-oo--<OLrv>'\io>}-— <rovj- 

OOOOOOOOOOOOOCOO— 'OOOOOOCOOO 

coooooooooooooooooooooooooo 
I       I   I   I  II  I  I   I       I   I       I 


incrr- 


OOOOOOOOOOOOOOOOOOOinOOOOOOO 

OO^O^CO— '>OOOa^incOOOOOCrO(7>ff>^O^Oi-.-\vOrO 

I  I      I     I    -H         I     I  I  .M  I    -"  II 


I      I    QC 
I    t-LU 

I  o 

O      00 

(MU.O 

•  LLIQf 

ooco 


oooooooooooooooocoooooooooo 

OOOOOOOOOOOOOOOOCOOOOOOOlOOO 

oo^rcocsoco^ocococr— ioaDaoaDcovr>3-ao>rv]-<%ir^ccoo 
ro'^iTviNjiMf — ir-'Niir\LOON3TMcocoao^c-.r>rr»-(N/r\i./>a>r-f- 

t^>->ro^Ov0^f-f\jf^^-f^a- CO  3^  c^o^c^oo '/>'-'•-' vOfNunu^ 
ro.-oinc;ooo--'0'N)(NJfMXifNji-Nif\](NjrviLr\'rvcoinir\Of\;coco 

— 1  ^  — 1  ^  ^  — <  — 1  ^  (%J  — I  —I  ^  ^  _<  ,-1  ^  ^  ^  r^  ^  —I  ^^  OVJ  t\j  ^  ^ 


f^OOOcO 


coooocooooooooooooooooooooo 
coooooooooooooooooooooooooo 


-H  oooooooooooooooocoooooooooo 


of 
Ilia: 
I  I  a:uj 
I  I  < 

I      I    UOO 
i/IO      </1 

t-ocrc 


OOOOOOOOOOOOO^J-OOOOOOOOOOrxJOO 

oooocoooooooooooooooooco:roo 


tn>/>ooooo.-^o-<i'noo-4-- 


•iCOOrsiOOO^OOO 


OO 

f\jm 


OOOOOOOOOOOOOOOOCOOOOOOOOOO 

0000000000000'"^  )COOOCCOOCCOOO 


ocfNivrc^ooc^Of^co— lOf«^r^^r^Xln^^OL^^>J•OL^^o^- 
.-^l^J— i,-Mt\j  f\j  ^  _c  rvj  — .  rsj  r\j  rxi  CM  (^ —i -<  — I  ,-\i     ^rvi(\j(M 


I   I   I 
I  I   1  I- 

1    I    I  o 

t-OO 

LU    •QtO 
t-0'-Li£ 


COOOOOOOOCOOOC^OOOOOOOOOOaoOO 
OOOOOOOOOOOOOT^OOOOOOOOOOOCO 


HfMO— <<NiOCOO— '(\irOOO— '!Vrrivr--i(NJC'-"NJCCOO 


Advertist'iiien  t 


54-1 


1^     ^ 


Do  you  need 

a  push  car  that 

can  carry 

a  frog? 


Safetran  Model-5000  Portable  Track  Car 

All  aluminum  construction  makes  the  Model-5000  the  lightest,  extra  capacity 

push  car  available. 

Transporting  loads  up  to  5000  lbs.  is  no  problem  for  the  all  welded  heavy  duty 

deck  and  frame. 

One  man  can  easily  handle  the  lightweight,  two  section,  all  aluminum  unit. 

It  can  be  quickly  and  easily  carried  to  track,  and  is  easily  assembled  with 

self-locking  device  that  hooks  the  two  sections  together.  Sockets  are  located 

so  that  the  handle  or  stakes  can  be  positioned  at  either  end. 

The  frame  of  the  IVIodel-5000  is  made  of  heavy  duty  aluminum  plate,  while 

the  deck  is  heavy  expandable  aluminum. 

The  fully  insulated  cast  aluminum  wheels  have  sealed,  prelubricated  roller 

bearings  for  smooth,  maintenance-free  service. 


Safetran  M-5000 
Specifications 


Weight  Capacity 5000  lbs. 

Frame  Construction Heavy  duty  aluminum  plate 

Deck Heavy,  expandable  aluminum 

Wheels Cast  aluminum- fully  insulated 

Bearing Ball,  pre-greased  and  sealed 

Deck  Size 52y2"  x  47' 

Total  Weight 156  lbs.  (78  lbs.  per  section) 

Height 7V2"  (above  rail) 

Handles 2  preshaped  aluminum  -  inter-changeable 

Construction All  welded 

Ordering  Reference:  Model-5000  Track  Car 
Part  No.  140230-X 


Safetran  Systems  Corporation 

7721  Nalional  Turnpike  •   LouPSville.KY  40214    •    (502)361-1691 


54-2 


Advertisement 


MEMBER 

RRI 

re  ^k. 


f 


Advertisement  54-3 


We've  a  lot 
going  for  you. 


We  call  it  "The  Big  Green,"  and  it's  all  go.  For  you. 

It's  what  we  put  into  every  one  of  our  railway  products  to 
give  you  the  big  return  you  want  and  need,  to  meet  required 
standards  on  your  roads. 

Ouranchors,  rail  joints,  heaters,  rail  and  flange  lubricators, 
and  renewal  insulation  give  you  the  edge  in  every  major 
investment  consideration. 

They're  built  to  give  you  longer,  trouble-free  performance. 

They're  built  for  fast  and  easy  installation. 

They're  built  to  save  manhours,  reduce  downtime,  keep  your 
trains  rolling. 

That's  where,  the  real  savings  dollars  are.  That's  where  the  big 
return  is.  Has  been.  Always  will  be. 

That's  why  you  should  talk  to  your  Portec  man  before  you 
invest  in  rail  anchors,  joints,  heaters  or  rail  and  flange 
lubricators,  and  renewal  insulation. 

The  big  green.  It's  as  close  as  your  phone. 

RAILWAY  PRODUCTS  DIVISION 
The  better  product  producing  people. 

PORTEC  inc 

300  Windsor  Drive  •  Oak  Brook,  Illinois  60521 
(312)325-6300  •  TWX  No.  91 0-651 -0212 


54-4 


Advertisement 


EXPERIENCED  SPECIALISTS 
IN  THE  REPAIRS  OF.... 
RAILROAD  STRUCTURES 


HJIHiHI  H  H  H  CORPORATION 

urzilb 


FOUNDATIONS,  UNDERPINNING  AND  INVESTIGATIONS 
AUGERCASTi'  Piles  -  placed  without  vibration 

•  For  new  foundations  and  underpinning 

•  Retaining  wall  piles.  Low  headroom  piles 

•  Tie-back  anchoring  system  for  excavations 

•  Tension  piles  and  anchors 

PRESSURE  GROUTING 

•  BAGPIPE  5/  Groutainerto  inflatable  forming  system 

•  Soil  stabilization  for  arresting  settlement  of  structures 

•  FIRM-UP^T)  chemical  grouting  for  consolidating  soils 

•  Consolidating  masonry  bridge  abutments  and  piers 


TM 


CONCRETE  AND  MASONRY  STRUCTURAL  REPAIRS 

•  Bridges,  dams,  power  plants  and  dry  docks 

•  Scour  repairs 

•  Tunnel  lining  repairs 

•  Repairs  to  precast,  concrete,  wood  and  steel  pile* 

PREPLACED  AGGREGATE  CONCRETE  (PAC) 

•  Cofferdam  seals 

•  Underwater  repairs,  piers  and  abutments 

•  High  density  concrete  for  shielding 

•  Concrete  and  masonry  structural  repairs 

•  Underwater  concrete 


ONE-SOURCE  MARINE  SERVICES 


•  Inspections  above  and  below  water 

•  Engineering  reports  of  Inspections 

•  Staff  of  experienced  divers  to  perform 
corrective  repairs 


•  Submit  budget  or  firm  quotes 

•  Complete  the  work  based  on  findings  or  at  the 
direction  of  Owner's  engineering  department 
or  consultant 


*  CoMrsd  bv  U.  S.  and  Canadian  PaMnia 


P.  O.   BOX   155    •    BRECKSVILLE,   OHIO  44141 


TELEPHONE  216/659-3141 


ATLANTA    •     BALTIMORE     •    CHICAGO     •     DETROIT     •     FT.  LAUDERDALE    •    HOUSTON,  .•  ^JACKSONVILLE 
MINNEAPOLIS    •    OMAHA    •   SEATTLE    •    TORONTO   •    TULSA       • 
AFFILIATES    LEE  TUR2ILLO  CONTRACTING  CO.    •    AUGERCAST  PI  LE  &  FOUNDATION  COMPANY 
TUR2ILL0C0NTRACTING  LTD.  .  ■      ' 


no  matter  how 
you  look  at  it 
there  is  just 
one  toilet 
that  stands  alone, 
one  toilet  that 
has  gained 
general  acceptance 
world  wide, 
one  toilet  familiar 
to  all  who  have  ever 
flown  in  an  airplane, 
traveled  in  a  bus, 
sailed  in  a  boat, 
or  lived  in  a 
recreational  vehicle, 
the  one  chemical 
retention  toilet 
now  available, 
designed  especially 


4^ 


to  recognize 

the  rugged  requirements, 
for  all  your 
sanitation  needs: 

locomotive 

caboose 

work  equipment . . . 

the  Vapor  NEWMATIC*  toilet, 
the  toilet  used 
by  more  than  40  railroads** 
become  more  familiar, 
write 

Transportation  Systems  Dh^. 
Vapor  Corporation 
6420  West  Howard  Street 
Chicago,  Illinois  60648 
In  Canada- 
Vapor  Canada  Limited 


VAPOR 

CORPORATION 


TRANSPORTATION  SYSTEMS  I 


'TM  Monogram  Industries,  Inc. 
**names  furnished  on  request 


Advertisement 


54-5 


TIE  HANDLER  from  RTW... 


with  24'fooUreach 
articulating  boom! 

Lifting  capacity-1500  lbs. at  12' 6 "to 
750  lbs.  fully  extended. 


•  New  rotating  deck  design 
...no  adjustments  needed 

•  Thermostatic  controlled 
oil  temperature  in 
hydraulic  circuit 


•  Low  maintenance 

•  Hydrodynamic  plus 
mechanical  brakes, 
on  all  four  wheels 


Many  other  features  for  high  production,  low  maintenance.  Choice  of  two 
other  tubular-type  booms  (all  interchangeable):  Fixed  24-ft..  and  manually 
adjustable  18-24-ft.  From  RTW,  the  people  with  the  longest  experience  in 
tie  handling.  Get  full  details  today.  Call  (215)  739-4281. 

OTHER  KTW  MtlNTEXiNCE  EtUIPMENT  ■  Saritct  Crinlers .  Cuss  Cfiaders  -  Surfice  Criolers  ■  Rail  Drills  •  Tie  Haalltrt  MEMBER 

JMPUU  A      RAILWAY  TRACK-WORK  CO.  2560  East  Tioga  St.,  Philadelphia,  Pa.  19134  IfPI 

**  ■    ^'      '  Agents:  Chicago- ESCO  Eq..ipment  Se.-iice  Co.  •  Houston -Service  Equipment  4  S;.pply  Company  ,,nMAr     T 

Los  Angeles -Simkins  Company  •  Louisville -T.  F.  Going  •  St   LOuis-R   E   Bell  Co  !!!!tm"J^ 

3   Piai-'ie:d  N  j  -  Esslern  Raii'oi<J  Equipment  Corp  •  Canada:  Montreal  -  Woodings-Canada  Ltd 


54-6 


Advertisement 


RAILROAD  TRACKS 

designed,  constructed 

amd  completely  maintained 


ROBT.  L  DEPRIZIO 
&  ASSOCIATES  INC. 


i;iSiS!E>Giat$i:;\^p^^  Oonstfuct^on  Compai 


"  ■'  "'■^-'  ■■'■-^-  ■  ■*■'- 


KERITE 
CABLE 


For  dependability  in  actual  use,  no  other  cable 
matches  Kerite.  We  believe  you  will  be  im- 
pressed by  the  evidence. 


THE  KERITE  COMPANY 

PRINCIPAL  OFFICES:  Boston;  Chicago;  New 
York;  Philadelphia;  San  Francisco;  and 
Seymour,  Connecticut  •  Sales  Representa- 
tion throughout  the  United  States.  A  sub- 
sidiary of  Harvey  Hubbell  Incorporated. 

RITE  insulation  that  makes  the  difference 


Advertisement 


54-7 


SWITCH  TAMPERS  FOR  ALL  YOUR  JOBS 


UNIVERSAL  UYT-2W75  YARD,  SWITCH  &  SPOT  TAMPER 


This  versatile  tamper  is  a  new  addition  to  the 
popular  Plasser  Universal  line.  Even  though  the 
UYT  2W75  has  a  lower  original  cost,  it  is  equipped 
with  two  of  the  exclusive  Plasser  four-tool  tamping 


heads  with  individually  tillable  tamping  arms, 
which  insures  the  tamping  of  every  tie  through 
switches  and  turnouts  without  the  use  of  outside 
or  ground  jacks. 


This  Universal  UYT  2V/75  tamper  is  particularly 
adaptable  for  yard  work  where  it  has  proven  itself 
as  a  money  saver.  The  reasonable  price  plus  its 
ability  to  do  a  fine  job  tamping  switches  and  doing 
spot  work  suggest  yard  assignment.  It  can  be 
equipped  with  automatic  lifting  and  leveling  equip- 


ment as  well  as  automatic  lifting  correction  with 
cross  level  indicator.  You  should  see  one  of  these 
tampers  in  service  and  we  will  be  pleased  to  make 
the  necessary  arrangements  for  you  to  do  so  at 
your  convenience.  You  will  be  convinced  that  it  is 
a  superior  machine. 


PLASSER  AMERICAN  CORPORATION 


GENERAL  OFFICES  &  PUNT 

2001    MYERS  ROAD 
CHESAPEAKE,  VIRGINIA  23324 


54-8 


Advertisement 


WELD  60-80 

STRAIGHT  OR  COMPROMISE 

*   JOINTS 
DAILY! 


THERMIT 


SELF-PREHEAT 
RAIL  WELDING 


THE  MODERN  IN-TRACK  METHOD 

•  AUTOMATIC,   ERROR-FREE  PRE-HEATING  AND 
TAPPING  OF  WELD  METALS 

•  EASY,  COLD  REMOVAL  OF  RISERS 

•  MINIMUM  GRINDING 

•  NO  EQUIPMENT  TO  PURCHASE  OR  LEASE 
COMPLETE  THERMIT  RAIL  WELDING  DE- 
TAILS PLUS  JOB-SITE  DEMONSTRATIONS. 

WRITE  OR  CALL 


ir       THERMEX  METALLURGICAL,  INC. 

A       LAKEHURST,  N.  J.  08733  •  (201)  657-5781 
^®  SALES  OFFICES  IN  MAJOR  CITIES 


Advertisement 


54-9 


3tu/unSnt 


RAILWAY     MOTOR     CARS 
AND      WORK^     EQUIPMENT 


■ 

- 

INSPECTION  MOTOR  CARS                  TRACK  LINING  LIGHT 

SECTION  MOTOR  CARS                         SPIKE  DRIVERS 

GANG  MOTOR  CARS                             TIE  REMOVERS 

PUSH  CARS  AND  TRAILERS                 TIE  HANDLERS 

HY-RAIL  EQUIPMENT                              RAIL  LIFTERS 

BALLAST  MAINTENANCE  CARS          TIE  SHEARS 

WEED  MOWERS                                        TIE  BED  SCARIFIERS 

TOW  TRACTORS                                      SPIKE  PULLERS 

RAIL  GRINDERS                                       TIE  PLUG  INSERTERS 

DERRICK  CARS                                         OIL  SPRAYERS 

HYDRAULIC  POWER  TOOLS                 TIE  SPRAYERS 

TRACK  LINERS                                          TIE  INSERTERS 



(Pe4 

ON 
CC 

Tutuuue. 

rHE   JOB 
UNTS 

"^ 

~- 

THESE   UNITS  ARE  ACTUATED   EITHER  COMPLETELY 

OR  PARTIALLY   BY  HYDRAULIC   POWER 

FAIRMONT  RAILWAY  MOTORS,  INC.,  FAIRMONT,  MINNESOTA  56031 

54-10  Advertisement 


A  tradition  of  service  .  .  . 


•  Water  Treatment  Chemicals  Protecting  Diesel  Cooling 
Systems  and  Steam  Generators 

•  Fuel  Oil  Additives 

•  Pollution   Control   Chemicals  and   Consulting   Services 


NALCa    CHEMICAL   COMPANY 

2901    BUTTERFIELD    ROAD    •    OAK   BROOK,    ILLINOIS    60521 


» 


Trademarks  of  Naico  Chemical  Company  |\|  /V  L.CS  O 


Advertisement 


54-11 


LORAM 

Modern  Maintenance 
of  Way  Equipment 

with  an  estabHshed 
track  record . . . 


WINCH  CART 


SHOULDER  BALLAST  CLEANER 


. . .  designea 
to  do  the  job 
easier,  quicker 
and  at  less  cost 
—  witti  your 

men  or 

ours! 


i"^.  -I 


III  •'csisi.jisir'idw    ii  'i  :s 


'*   II  •  ■  f^iss^iiiflir't^w    I  \:iirA 


MULTI  PURPOSE  MACHINE 


I      . 


«  1 


•SM'i ;  ill  V |fi!^||,^^F'4SIQli      IS  'i  iSiZ 


AUTOTRACK  WITH  PLOW  AND  SLED 


THE  ANSWER  TO  YOUR  1975  TRACK  REHABILITATION  PROGRAM 


MEMBER 

RRI 


LORAM  RAILWAY  MAINTENANCE  EQUIPMENT  FOR: 

•  Shoulder  Ballast  Cleaning  •  Raising  Track  •  Resurfacing  • 
Reballasting  •  Replacing  Ties  •  Undercutting  •  Ballast  Cleaning 

•  Rail  Grinding  Single  or  Multiple  track  — Mainline  or  Yard  tracks 

CONTRACT,  SALE  or  LEASE 


FOR  FULL  DETAILS 
OR  SHOWING  OF 
OPERATING  FILMS. 
WRITE  OR  CALL  TODAY 


MAINTENANCE  OF  WAY,  INC. 

3900  Arrowhead  Drive   •   Hamel,  MN  55340   U.S.A. 
PHONE:  (612)  478-6014  •  TELEX:  29-039T :  Cable.  LORAM 


54-12 


Advertisement 


BBW— 


en  you 
need  one  for 
the  road, 
make  it 
ChanneloC. 

The  True  Temper  Channeloc'  with  massive  and 
unique  channel  shape  provides  tremendous  grip- 
ping pow/er.  Its  great  tensile  strength  adds  years 
to  service  life  . . .  and  saves  replacement  costs. 

Channeloc  bar  stock  is  uniformly  thick,  result- 
ing in  even  heat-treating  to  avoid  softness  or 
brittleness.  The  Channeloc  design  assures  ample 
rail  contact  surface  for  maximutn  holding  power. 
Channeloc  is  applied  easily  and  quickly  with  mini- 
mum ballast  disturbance  . . .  and  can  be  reapplied 
to  save  your  road  maintenance  budget. 

True  Temper  has  produced  ever  two  hundred 
million  Channeloc  Rail  Anchors  Whon  you  need 
one,  make  sure  it's  Channeloc  proven  Shice 
1960. 


U-Shaped  cross  s 
great  tensile  strength 


Smooth  contours 
high  stress  points 


Rail  base  contact  areas 
smoothly  lormed  and 


Unilorm  bar  stock 
can  be  given  a 
heal-trealme 
IS  thorough  and 
even  throughout 
the  entire  metal 
Structure. 


hat 


I  RUE  I  EM  PER. 

An  Allegheny  Ludlum  Industries  Compaay 


Advertisement 


54-13 


The  Allegheny  Insulated  Rail  Joint- 

Designed  to  withstand  the  heaviest  traffic 
in  welded  rail 

This  modern  joint  cements  roil  ends  in  position  and  thereafter 
resists  all  forces  imposed  by  temperature  and  simultaneous  forces 
of  live  loads  to  move  them. 

This  joint  mokes  v/eided  rail  truly  continuous.  It  promises  you  years 
of  service  without  maintenance  costs.  It  reduces  rail  and  wheel  batter 
to  a  previously  unknown  minimum.  It  employs  the  safety  of  steel  splice 
bars.  It  can  be  assembled  in  the  shop  or  field.  It  has  been  tested  in 
service  and  AAR  laboratories.  It  saves  you  lots  of  money. 

Allegheny  Drop  Forge  Company 

Subsidiary  of  Tasa  Corporation 


2707  Preble  Avenue  •  Pittsburgh,  Pa.  15233 


54-14 


Advertisement 


Nordberg 

railway 

equipment. 


Saves  time 
and  money 
all  along 
the  line. 


SELF-PROPELLED 
ADZER 

HYDRA-SPIKER 
LINE  INDICATOR 
PLATE  PLACER 
POWER  JACK 
RAIL  DRILL 
RAIL  GANG  SPIKER 
RAIL  GRINDERS 

ONE  MAN  SCARIFIER 
AND  INSERTER 

SPIKE  HAMMER 

SPIKE  PULLER 

SPIKE  STRAIGHTENER 

SURFRAIL  GRINDER 

SWITCHLINER 

TRACK  INSPECTOR 

TIE  DRILL 

TIE  SPACER 

TRACKLINER 

DUN-RITE  GAGER 

X-LEVEL  INDICATOR 


Right  of  way 
maintenance  and 
construction  is  a  tough 
job,  and  getting  tougher. 
Nordberg  railway 
equipment  is  precision 
engineered  to  keep 
things  rolling  — to  get 
the  job  done  on  time, 
at  low  cost.  Write 
Rexnord  Railway 
Equipment  Division, 
Box  383,  Milwaukee, 
Wisconsin  53201. 


V 


Rexnofd 
//fffflf 


Advertisement 


54-15 


r 


CONCRETE 
PROBLEMS? 

OSMOSE  EPOXY  INJECTION 
MAY  BE  THE  ANSWER 

Osmose,  the  Company  synony- 
mous with  timber  bridges,  has 
now  diversified  into  concrete 


bridge  maintenance,  special- 
izing in  "welding"  structural 
cracks. 


This  proven  method  con- 
sists of  •  ANALYSIS  • 
CLEANING  •  SEALING  • 
CONTROLLED  PRESSURE 
INJECTION  •  DETAILED 
INSPECTION  REPORTS 


Restores  structural  integrity  under  traffic. 


RAILROAD  DIVISION 

4915  Monona  Drive 
Madison,  Wis.  53716 
608/222-6800 


54-16  Advertisement 


1E|EWE|D 

Rail  Maintenance  Service 

Rail  End  Welding 

Rail  End  Hardening  BDf 


MEMBER 


CWR  Joint  Normalizing  SSiFt" 

Frog  and  Switch  Welding 

Rail  Maintenance  Equipment 

Custom  Manufacturing  and  Fabrication 

Joint  Bar  Shims 

Rail  Anchor  Shims 

Rail  End  and  Frog  and  Switch 

Welding  and  Grinding  Machines 
CWR  Heating  and  Cooling  Equipment 
Rail  Flaw  Testing  Equipment 
Telebrineller  Portable  Hardness  Tester 


Infra-Rad  Heatar  for  Curing  Adhatlv*  Bended  Roll  Joints 


TELEWELD  INC.,  416  NORTH  PARK  ST.,  STREATOR,  ILL.  61364 

Write  for  details  of  the  TELEWELD  process  for  restoring  rail  ends. 


Advance   Report  of   Committee  4 — Rail 
Report  on  Assignment   5 

Rail  Research  and   Development 

W.  J.  Cruse  (cluiirman,  subcommittee),  B.  G.  Anderson,  R.  M.  Brown,  E.  T. 
Franzen,  R.  E.  Gorsuch,  R.  E.  Haacke,  V.  E.  Hall,  W.  H.  Huffman,  T.  B. 
HuTCHESON,  K.  H.  Kannowski,  W.  S.  Lovelace,  A.  B.  Merritt,  Jr.,  J.  L. 
Merritt,  C.  O.  Penney,  I.  A.  Reiner,  W.  A.  Smith. 

Your  committee  presents,  as  information,  tlie  following  report  on  the  second 
annual  inspection  of  a  service  test  installation  of  fully  heat-treated,  induction  head- 
hardened,  intermediate-manganese  and  standard  control-cooled  rail  on  the  Chessie 
System.  The  author  of  the  report  is  K.  W.  Schoeneberg,  senior  research  engineer. 
Research   and    Test   Department,    Association   of  American   Railroads. 


SUMMARY  OF  PERFORMANCE  OF  STANDARD-CARBON  AND  VARIOUS 

WEAR-RESISTANT  RAILS  IN  TEST  CURVES  ON  THE  CHESSIE  SYSTEM 

SECOND  REPORT 

By   K.   W.   Schoeneberg 

I — ABSTRACT 

This  report  summarizes  the  second  annual  inspection  of  a  service  test  installa- 
tion of  fully  heat-treated,  induction  head-hardened,  intermediate-manganese  and 
standard  control-cooled  rail  on  the  Chessie  System. 

The  field  inspection  is  part  of  tlie  cooperative  effort  on  rail  research  of  the 
American  Railway  Engineering  Association  (AREA),  the  American  Iron  and  Steel 
Institute  (AISI)  and  the  Association  of  American  Railroads  (AAR)  to  observe  and 
analyze  those  rails  in  curved  track  that  display  some  potential  for  improvement  in 
wear-resistance  and  retarding  the  onset  of  shelling. 

Measurements  were  made  and  recorded  of  curvature,  superelevation  and  gage 
of  four  service  test  curxes  located  near  Oakland,  Maryland.  General  track  condi- 
tions were  observed  also.  Rail  head  cross-section  contours  were  taken  and  recorded 
of  the  80  test  rails  contained  in  these  curves.  Rail  wear  has  been  calculated  for  the 
second  year  of  service  for  the  various  types  of  rail  in  test. 

II — ACKNOWLEDGEMENT 

Appreciation  is  hereby  acknowledged  of  the  original  invitation  of  J.  T.  Collin- 
son,  then  general  manager-chief  engineer,  now  vice  president-operations  and  main- 
tenance, Chessie  System;  and  the  continued  invitation  of  J.  W.  Brent,  chief 
engineer,  and  A.  L.  Maynard,  formerly  engineer  maintenance  of  way,  now  director- 
engineering  administration,  Chessie  System,  for  the  AAR,  AISI  and  AREA  to  par- 
ticipate with  Chessie  on  the  inspection  and  evaluation  of  their  rail  service  test  in- 
stallation. Sincere  appreciation  is  expressed  by  those  of  AAR,  AISI  and  AREA  for 
the  time  and  efforts  rendered  by  Chessie  personnel  listed  below  in  the  preparation 
and  conduct  of  this  inspection. 

55 
Bui.  654 


56 Bulletin  654 — American  Railway  Engineering  Association 

Inspection  of  the  rail  in  the  four  service  test  curves  near  Oakland,  Maryland 
was  made  on  July  30,  1974.  The  following  individuals  were  in  the  inspection  party: 

A.  L.  Maynard  — Chessie  System 

A.  J.  Kozak  — Chessie  System 

M.  Hawtof  — Chessie  System 

D.  S.  Young  — Chessie  System 

I.  A.  Reiner  — Chessie  System 

W.  H.  Chidley  — American  Iron  and  Steel  Institute 

G.  G.  Knupp  — Bethlehem  Steel  Corporation 

J.  H.  Martens  — Bethlehem  Steel  Corporation 

J.  L.  Giove  — U.  S.  Steel  Corporation 

D.  L.  Saxon  — U.  S.  Steel  Corporation 

G.  H.  Way  — Association  of  American  Railroads 

K.  W.  Schoeneberg — Association  of  American  Railroads 

III — INTRODUCTION 

As  part  of  the  programs  on  rail  research,  the  AAR  Research  and  Test  Depart- 
ment is  continuing  the  field  study  and  analysis  of  those  rails  that  continue  in  service 
which  show  some  potential  for  improvement  in  curve  wear  resistance  and  ability  to 
retard  the  onset  of  shelling.  Rails  that  are  heat-treated,  have  a  variance  in  chemical 
composition  from  that  of  standard  rail  or  which  are  unconventionally  produced  are 
part  of  this  study. 

The  field  inspections  are  carried  out  as  a  cooperative  effort  of  the  Rail  Research 
and  Development  Subcommittee  of  AREA  Committee  4-Rail,  the  AISI  Technical 
Subcommittee  on  Rail  and  Accessories,  the  AAR  Research  and  Test  Department  and 
the  railroad  on  whose  property  the  test  rails  are  installed. 

Through  this  and  several  other  field  service  tests  presently  being  progressed 
by  these  organizations,  rail  wear  data  as  well  as  tonnage,  track  component,  roadbed 
and  environment  data  are  being  generated.  The  correlation  of  these  data  will  result 
in  the  development  of  rail  wear  rates  for  various  combinations  of  track  and  service 
conditions.  A  further  correlation  of  these  rail  wear  rates  with  other  rail  metallurgi- 
cal and  economic  studies  data  can  set  forth,  as  an  end  product,  criteria  or  recom- 
mendations establishing  the  appropriate  selection  of  rail  by  section  (weight)  and 
kind  (standard,  alloy  or  heat-treated)  to  be  used  by  the  railroads  at  locations  of 
high    wear   or   short   calendar   rail  life. 

IV — DESCRIPTION    OF   TEST    RAILS 

The  Chessie  System  established  the  service  test  of  heat-treated,  alloy  and 
standard  rail  on  July  7,  10  and  11,  1972,  when  the  rails  were  installed  in  four 
curves  on  its  No.  2  or  eastbound  main  track  west  of  Oakland,  Maryland.  A  total 
of  80  rails  consisting  of  16  each  of  the  five  following  types  were  used: 

( 1 )  140  R  E  fully  heat-treated 

(2)  140  R  E  head-hardened 

(3)  140  R  E  intermediate-manganese 

(4)  140  R  E  standard-carbon  control-cooled — A 

(5)  140  R  E  standard-carbon  control-cooled — B 


Performance  of  Test  Rails  on  Chessie  System  57 

Four  rails  of  each  type  were  laid  out  for  each  of  the  four  different  curves,  two 
on  the  high  side  and  two  on  the  low  side  of  each  cur\e.  The  rails  were  randomly 
welded  together  in  10  rail  strings  by  the  electric-flash  Initt  method.  These  continu- 
ously welded  strings  were  then  installed  in  the  curves,  one  on  the  high  side  and 
one  opposite  on  the  low  side  of  each  of  the  four  curves.  The  four  test  curves  chosen 
for  this  test  are  of  \arying  nominal  curvature  and  superelevation  as  follows: 

Cur\e  No.  1,  .5° — .50'  (299.5  m  radius) — VA  in  (114. .3  mm)  superelevation 

Curve  Xo.  2,  8° — 28'  (206.5  m  radius) — 5    in  (127.0  mm)  superelevation 

Curve  No.  3,  4° — 00'  (436.6  m  radius) — 2/2  in  (    63.0  mm)  superelevation 

Curve  No.  4,  8° — 08'  (214.9  m  radius) — 5    in  (127.0  mm)  superelevation 

Figures  1  tiirough  4  show  detailed  information  of  location,  curve  layout  and 
placement  of  the  various  types  of  rails  in  each  of  the  four  test  curves. 

V — CONDUCT   OF   THE    INSPECTION 

The  inspection  party  examined  all  test  rails  in  each  of  the  four  test  curves, 
noting  the  condition  of  each  rail  as  well  as  noting  line  and  le^el  of  the  track  and 
conditions  of  the  other  track  components.  Rail  head  cross-section  contours  were 
taken  at  approximately  the  midpoint  of  each  of  the  80  test  rails.  The  wear  pattern 
of  each  is  shown  in  Figures  5  through  24.  The  gage  of  the  track  was  measured 
and  recorded  at  the  locations  where  the  rail  head  contours  were  taken.  Tliese  are 
also   shown   in   Figures   5  through  24. 

Stringlining  measvuements  were  made  to  check  the  degree  of  curvature  of 
each  curve,  particularly  in  the  body  of  the  curves  where  the  test  rails  were  located, 
as  a  means  of  verifying  the  original  degree  of  curvature  and  a  check  for  any  gross 
misahgnment.  The  curvature  measurement  taken  at  each  of  the  test  rail  locations  is 
shown  in  Figures  5  through  24. 

Superelevation  measurements  were  also  made  throughout  each  curve  and  these 
measurements  are  also  shown  for  each  test  rail  location  in  Figures  5  through  24. 

VI — RESULTS    OF   THE    INSPECTION 

The  four  curves  and  the  track  through  this  location  appear,  as  was  the  case  at 
the  first  inspection,  to  be  well  maintained  and  in  good  condition.  Drainage  of  the 
roadbed  and  ballast  section  was  generally  good  with  the  exception  of  one  location 
on  cur\'e  No.  2  where  a  muddy  pumping  ballast  condition  existed  on  the  low  or 
inside  of  the  curve. 

The  rail  luljricators,  noted  as  distributing  generally  heavy  to  moderate  amounts 
of  lubricant  as  of  the  1973  inspection,  appeared  to  be  inoperative  at  the  time  of 
this  inspection  because  of  the  lack  of  lubricant  on  the  rails  of  all  four  test  curves. 

Specific  observations  of  rail  conditions  of  each  curve  were  noted  as  follows: 
Curve  No.  1 

Head  checks  were  noted  on  high  side  rails  94L143  D20,  CT08943  C21  and 
CT08943  BIO. 

Curve  Xo.  2 

Rail  81L707  E38  had  head  checks  and  light  flaking  spots.  Rail  59R647  C26 
showed  hght  flaking  and  rail  CT08943  C22  had  some  head  checks.   Rail  85R812 


58  Bulletin  654 — American  Railway  Engineering  Association 

E21  had  one  lipht  flakinji;  spot  on  the  receiving  end.  Rail  IM19010  D6  had  con- 
tinuous  light  flaking  6  ft  of  leaving    (east)    end. 

Heavy  wear  was  noted  in  rail  IM 19010  B9  and  irregular  wear  pattern  in  rails 
CT07952  D17  and  IM19010  D6  from  apparent  truck  hunting,  probably  induced  by 
low-side  soft,  muddy,  pumping  areas. 

High-side  rail  181332  G16  was  not  seated  into  tie  plates. 

Curve  No.  3 

Head  checks  were  noted  in  rails  CT07952  B17  and  94L143  B20.  Head  checks 
and  light  flaking  spots  were  noted  in  rails  IM19010  Dl  and  63M022  E16. 

Slightly  abnormal  batter  was  noted  at  welded  joints  at  each  end  of  fully  heat- 
treated  rail  CT08943  B16  where  it  joined  standard  rails. 

There  were  slight  indications  of  corrugations  on  high-side  rail  181332  D4. 

Heavy  flow  at  end,  and  fin  on  field  side  appeared  on  rail  71R078  C27  in  low 
side   of  curve,   opposite   above-mentioned  corrugated  rail. 

Sliver  spots  in  rail  94L143  D9  and  several  heavy  slivers  near  middle  of  rail 
94L143  C24  were  noted. 

Curve  No.  4 

The  "raspy"  early  feeling  of  head  checks  was  noted  on  most  rails  in  high  side 
of  curve. 

Intermittent  very  light  flaking  spots  were  noted  on  rail  59R647  C23  in  high 
side  of  curve. 

Initial  iiidication  of  high-side  corrugations  was  noted  in  oblique  light  in  rails 
85R812  D20  and   181332   H18. 

There  was  a  small  sliver  on  field  side  of  head  at  middle  of  rail  94L143  D14, 
and  a  sliver  depression  3  ft  from  west  end  of  rail  94L143  D17. 

From  visual  observation  at  the  time  of  the  inspection  and  then  by  study  of  the 
rail  head  contour  tracings  of  all  four  curves,  more  metal  flow  was  noted  on  almost 
all  inside  or  low  rails,  and  more  curve  wear  was  noted  on  the  high  rails  than 
there  was  at  the  time  of  the  1973  inspection.  In  like  manner,  more  metal  flow  and 
curve  wear  were  noted  in  the  intermediate-manganese  and  standard  rails  than  in 
the  head-hardened  or  fully  heat-treated  rails. 

V\i — DISCUSSION 

The  track  containing  the  test  rails  carries  predominantly  eastbound  manifest 
mixed  freight  and  unit  coal  trains.  During  the  first  year  the  test  rails  were  in 
service,  August  1972  through  July  1973,  tonnage  over  this  territory  was  14.6  mil- 
lion gross  tons.  During  the  second  year  of  test  service,  from  August,  1973  through 
July  1974,  the  tonnage  was  16.3  million  gross  tons.  Thus  a  total  of  30.9  million 
gross  tons  of  traffic  has  been  over  these  rails  since  they  were  laid  in  track  in  July 
1972. 

Based  on  a  comparison  of  the  rail  head  contours  taken  in  July  1973  (after  one 
year  of  sei-vice)  and  those  taken  in  July  1974  (after  the  second  year  of  service) 
the  change  or  increase  in  rail  wear,  during  this  second  year,  was  plotted  and  calcu- 
lated by  planimeter  readings.  From  these,  calculations  were  made  of  the  amount 
(square  inches)  of  rail  wear  and  percent  of  rail  wear.  These  values  representing 
rail  head  metal  worn  away  during  the  second  year  of  service  are  thus  shown  for 
each  rail  head  cross-section  in  Figures  5  through  24. 


Performance  of  Test  Rails  on  Chessie  System 59 

As  noted  previously,  each  of  the  four  test  curves  contained  four  rails  of  the 
same  ty^Je,  tvi^o  in  the  low  side  and  two  in  the  high  side.  From  the  calculations 
made  of  the  amount  of  rail  head  metal  worn  away  of  each  rail,  the  average  of 
each  type  of  rail  on  each  curve  on  the  high  side  and  the  low  side  was  calculated. 

In  general,  most  of  the  test  rails  of  the  five  types  of  rail  on  the  low  side  of 
each  of  the  curves  displayed  a  marked  increase  of  metal  flow  between  the  1973 
and  the  1974  inspections.  They  showed  increases  of  from  light  to  medium  and 
from  medium  to  heavy  metal  flow  to  the  field  side  during  this  second  year  of 
service.  It  can  be  noted  that  in  some  cases  a  lip  formed,  indicating  metal  flow  to 
the  gage  side  also.  In  only  three  head-hardened  rails  and  two  fully  heat-treated 
rails  a  stable  or  non-increase  in  metal  flow  was  noted. 

Because,  in  this  rail  study,  we  are  particularly  interested  in  the  wear  character- 
istics of  the  high  rail,  the  average  amount  of  wear  in  square  inches  as  well  as 
the  corresponding  percent  of  wear  of  the  two  rails  of  each  type  in  the  high  rail  of 
each  of  the  curves  is  shown  in  Table  I.  The  average  amount  (square  inches)  of 
head  wear  versus  the  average  curvature  of  these  two  representative  rails  of  each 
type  are  shown  graphically  in  Figure  25. 

It  can  be  noted  that,  with  the  exception  of  the  intermediate-manganese  rail, 
the  standard,  head-hardened  and  fully  heat-treated  rails  displayed  a  trend  of  even 
or  very  slightly  increasing  amounts  of  wear  for  the  nominal  4-,  6-  and  8-degree 
curves,  respectively.  The  intermediate-manganese  rail  showed  an  increase  of  wear 
on  the  nominal  6-degree  curve  versus  the  nominal  4-degree  curve  with  a  slight 
decrease  in  wear  on  the  nominal  8-degree  cui-ve.  All  rails  display  a  sharp  increase 
in  wear  between  the  nominal  8  and  the  nominal  8/2-degree  curve  with  the  excep- 
tion of  one  of  the  standard  type  rails. 

VIII — CONCLUSIONS 

In  general,  low-rail  wear  and  metal  flow  and  high-rail  curve  wear  has  con- 
formed to  a  pattern  of  more  wear  and  flow  in  the  standard  and  intermediate- 
manganese  type  rails  and  less  wear  and  flow  in  the  treated  products  such  as  head- 
hardened   and  fully  heat-treated  rails. 

The  amounts  of  wear  recorded  particularly  in  the  high  rails  did  not  conform 
to  a  consistent  pattern,  but  were  erratic  even  with  an  averaging  approach.  Again, 
in  general,  the  treated  type  rails  did  perform  better  than  the  others  with  the 
exception  of  the  one  standard  type  rail  showing  slightly  less  wear  on  the  nominally 
8/2-degree   curve   than   the  head-hardened  and   the  fully  heat-treated  rails. 

The  rather  erratic  wear  pattern  was  evident  also  when  comparison  was  made 
between  the  nominal  degrees  of  curvature  of  the  four  test  cin^ves  and  the  average 
wear  of  each  of  the  five  types  of  rail  in  test.  The  raUier  constant  or  slightly  increas- 
ing average  amount  of  wear  calculated  for  the  nominal  4-,  6-  and  8-degree  curves 
in  contrast  with  the  sharp  increase  for  the  nominal  8/2-degree  curve  could  possibly 
have  been  caused  by  or  resulted  from  train  speeds  and  the  \ariations  of  curvature 
and  superelevation  as  noted  and  recorded  at  the  individual  test  rails  in  each  of  the 
curves. 


60  Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM  RAIL  TEST 
NEAR  OAKLAND,   MARYLAND 


High  Rail- 


D05611  C33 
Head-Hardened 


59RB47  B26 
Standard  -  A 


71R078C26 
Standard  -  A 


IM19010  F19  ' 
Int.    Mn  . 


94L143  D20 
Head- Hardened 


181332  F4 

Standard-  B  94L143E11  IM19010  B20  IM19010B18  CT08943  B17 

Head-Hardened       Int.    Mn.  Int.    Mn.  F.  H.  T. 


CT08943  C21 
F.  H.  T. 


CT08943  BIO 
F.H.T. 


IM19010  DU 
Int.    Mn. 


181332  A17 
Standard-  B 


73L669  C.8 
Head- Hardened 


LAYOUT  OF  140  LB.   RE  TEST  RAILS  -  CURVE  NO.    1 
NOMINAL  5°-50'  CURVE  (299.    5  m  RADIUS)—  4-1/2  IN.   SUPERELEVATION  (114.3  mm)NOMINAL 

MILE  POST  233.  1 


CHESSIE  SYSTEM  RAIL  TEST 
NEAR  OAKLAND,    MARYLAND 


High  Rail.. 


81L707  E38 
Hoad-H.irdened 


59R647  C26 
Standard  -  A 


CT08943  C22 
F.  H.  T. 


85R812  E21 
Standard  -  A 


?647  D2 
Standard- A 


181332  F20 
Standard-  B 


181332  Uia 
Sl;indard  -  B 


181332  F14 
Standard-  B 


CT07952  D17 
F.  H.T. 


181332  Gib- 
Standard-  B 


CT19017  F6 
F.  H.  T. 


801,680  E24 
Head-Hardened 


igh  Rail 


85R8I2  B20  '  -Low  Rail 

Standard  -A 


LAYOUT  OF  140  LB.   RE  TEST  RAILS  -  CURVE  NO.    2 
NOMINAL  8°-28'  CURVE  (206.5  m  RADIUS)  —  5  IN.   SUPERELEVATION    (127.0  mm)  NOMINAL 

MILE  POST  233.  2 


Performance  of  Test  Rails  on  Chessie  System 


CHESSIE  SYSTEM  RAIL  TEST 
NEAR  OAKLAND,   MARYLAND 


61 


High  Rail 


181332  C21 
Standard  -  B 


CT19017  E 
F.  H,  T. 


59R647  Dl 
Standard-  A 


'CT08943  B16'        "Tai332D4       '  ■94L143D9  IM19010F16 

jr_  H.  T.  Standard-  B  Head- Hardened       Int.    Mn. 


94L143  D21 
Head- Hardened 


CT08943  C19 


94L143  C24  1M19010  AIS 

Head-Hardened        Int.    Mn. 


CT07952  B17 
F.  H.  T. 


94L143  B20 
Head- Hardened 


IM19010  Dl 
Int.    Mn. 


63M022  E16 
Standard  -  A 


High  Rail 


LAYOUT  OF  140  LB.   RE  TEST  RAILS  -  CURVE  NO.    3 
NOMINAL  4«-00'  CURVE  (436.  6  m'R ADIUS)  -2-1/2  IN.   SUPERELEVATION    (63.  5  mm)  NOMINAL 

MILE  POST  234.  0 

FIGURE  3 


CHESSIE  SYSTEM  RAIL  TEST 
NEAR  OAKLAND,   MAR^.AND' 


High  Rail 


181332  C28 
Standard-  B 


'1M19010  B14 
Int.    Mn. 


94L143  D17 
Head- Hardened 


CT19017  C8 
F.H.T. 


85R812  D20 
Standard  -  A 


94L143  D16 
Head- Hardened 


CTi9017  BIO 
F.H.T. 


1M19010  D3  CT19017  E8  181110  013  66M022  DIG 

Int.    Mn,  F.H.T.  Standard-  B  Standard- A 


Standard- A 


CT19017  F8 
F.  H.  T. 


-High  Rail 


LAYOUT  OF  140  LB.   RE  TEST  RAILS  -  CURVE  NO.   4 
NOMINAL   8°-08'  CURVE  (214.  9  m  RADIUS)— 5  IN.   SUPERELEVATION     (127.  0  mm)NOMINAL 

MILE  POST  23^0 


62  Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   1  -  MILE  POST  233.1 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.0  sq.  in. 
(0.0  sq.  mm) 

0.0% 
D05611  C33 
Head- Hardened 


Low  Rail 


Gage 

57" 

(1.448  m) 


0.055  sq.  in. 
(35.49  sq.  mm) 

1.1% 
59R647  D15 
Standard -A 


High  Rail 


Location  1 
Curvature  6°  -  08'  (284.9  m  radius)  -  Superelevation  4  5/8  in.   (117.5  mm) 


0.05  sq.  in. 
(32.26  sq.  mm) 

1.0% 
59R647  B26 
Standard -A 


Low  Rail 


11 

0.07  sq.  in. 

1/ 
1/ 

(45.16  sq.  mm) 

Gage 

1.4% 

56-7/8" 

181332  G21 

(1.445  m) 

Standard-  B 

High  Rail 


Location  2 
Curvature  6°  -  08'  (284.9  m  radius)  -  Superelevation  4  7/8  in.   (123.  8  mm) 


FIGURE  5 


Performance  of  Test  Rails  on  Chessie  System 


63 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CLTIVE  NO.   1  -  MILE  POST  233.1 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.005  sq.  in. 
(3.23  sq.  mm) 

0.1% 
85R812  C23 
Standard  -  A 


Low  Rail 


Gage 

57" 
(1.448  m) 


0.075  sq.   in. 
(48.39  sq.  mm 

1.5% 
71R078  C26 
Standard  -  A 


High  Rail 


Location  3 
Curvature  6°  -  22'  (274.4  m  radius)  -  Superelevation  4/78  in.   (123.8  mm) 


"""=*!> 

N 

0.05  sq.  in. 

A 

(32.26  sq.  mm) 

1.0% 
CT08943  B21 

Gage 

57" 

F.H.T. 

1    (1.448  m) 
^ 

Low  Rail      y*""^ 

High  Rail 


Location  4 
Curvature  6°  -  15'  (279.  6  m  radius)  -  Superelevation  4  7/8  in.   (124.  8  mm) 


0.095  sq.   in. 
(61.29  sq.   mm) 

1.9% 
IM19010  F19 
Int.   Mn. 


FIGURE  6 


64 


Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  1  -  MILE  POST  233.1 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.045  sq.  in. 
(29.03  sq.  mm) 

0.9% 
181332  D14 
Standard-  B 


Low  Rail 


Gage 
56-13/16" 
(1.443  m) 


0.03  sq,  in. 
(19.36  sq.  mm) 

0.6% 
94L143  D20 
Head- Hardened 


High  Rail 


Location  5 
Curvature  6°  -  15'  (279.6  m  radius)  -  Superelevation  5  1/4  in.  (133.4  mm) 


^H^ 


0.05  sq.  in. 
(32.26  sq.  mm) 

1.0% 
181332  F4 
Standard  -  B 


Low  Rail 


Gage 
56-11/16" 
(1.440  m) 


0.04  sq.  m. 
(25.81  sq.  mm) 

0.8% 
CT08943  C21 
F.  H.  T, 


High  Rail 


Location  6 
Curvature  6°  -  00'  (291.2  m  radius)  -  Superelevation  4  3/4  in.  (120.7  mm) 


FIGURE  7 


Performance  of  Test  Rails  on  Chessie  System 


65 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   1  -  MILE  POST  233.1 


INSTALLED:    July  1972 


INSPECTED:   July  30,  1974 


0.00  sq.  in. 

>. 

(0.0  sq.  mm) 

0.0% 

Gage 

94L143  Ell 

56-5/8" 

Head- Hardened 

1  (1.438  m; 

Low  Rail         /^"^"^ 

0.04  sq.  in. 
(25.81  sq.  mm) 

0.8% 
CT08943  BIO 
F.H.T. 


High  Rail 


Location  7 
Curvature  6*^  -  15'  (279.6  m  radius)  -  Superelevation  4  15/16  in.  (125.4  mm) 


0.015  sq.   in. 
(9.68  sq.  mm) 

0.3% 
IM19010  B20 
Int.  Mn. 


Low  Rail 


/7 

' 

Gage 

56-3/4" 
(1.441  m) 

I 
1 

0.  095  sq.  in. 
(61.29  sq.  mm) 

1.9% 
IM19010  Dll 
Int.  Mn. 

High  Rail 


Location  8 
Curvature  6°  -  00'  (291.2  m  radius)  -  Superelevation  4  5/8  in,  (117.5  mm) 


FIGURE  8 


66  Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  1  -  MILE  POST  233.1 


INSTALLED:     July  1972 


INSPECTED:    July  30,  1974 


0.005  sq.  in. 
(3.23  sq.  mm) 

0.1% 
IM19010  B18 
Int.  Mn. 


Low  Rail 


0.08  sq.  in. 
(51.62  sq.  mm) 

1.6% 
181332  A17 
Standard  -  B 


High  Rail 


Location  9 
Curvature  6°  -  00'  (291.2  m  radius)  -  Superelevation  4  5/8  in.  (117.5  mm) 


0.00  sq.  in. 
(0.0  sq.  inm) 

0.0% 
CT08943  B17 
F.H.T. 


Low  Rail 


Gage 
56-5/8" 
(1.438  m) 


0.00  sq.  in. 
(0.0  sq.  mm) 

0.0% 
73L669  G8 
Head- Hardened 


High  Rail 


Location  10 

Curvature  5°  -  45'  (303.8  m  radius)  -  Superelevation  4  5/8  in  (117.5  mm) 


FIGURE    9 


Performance  of  Test  Rails  on  Chessie  System 


67 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  2  -  MILE  POST  233.2 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.105  sq.   in. 
(67.75  sq.  mm) 

2.1% 
81L707  E38 
Head- Hardened 


/^^"^^^ 

/ 

0.00  sq.   In. 

(0.0  sq.  mm) 

Gage 

0.0% 

56-3/4" 

59R647  D2 

(1.441  m) 

Standard-  A 

V 

\       Low  Rail          /• 

High  Rail 


Location  1 
Curvature  9°  -  15'  (189.0  m  radius)  -  Superelevation  4  7/8  in.  (123.8  mm) 


0. 15  sq.  in. 
(96.78  sq.  mm) 

3.0% 
59R647  C26 
Standard-  A 


High  Rail 


Gage 

56-5/8" 
(1.438  m) 


0.02  sq.   in. 
(12.90  sq.  mm) 

0.4% 
IM19010  FIO 
Int.  Mn. 


Low  Rail 


Location  2 
Curvature  8°  -  45'  (199.8  m  radius)  -  Superelevation  4  7/8  in.  (123.8  mm) 


FIGURE  10 


68 


Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   2  -  MILE  POST  233,2 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.085  sq.  in. 
(54.84  sq.  mm) 

1.7% 
CT08943  C22 
F.H.T. 


High  Rail 


Gage 
56-5/8" 
(1.438  m) 


0.015  sq.   in. 
(9.68  sq.  mm) 

0.3% 
CT08943  F17 
F.H.T. 


Low  Rail 


Location  3 
Curvature  8*^  -  45'  (199.8  m  radius)  -  Superelevation  4  3/4"  in.  (120.7  ram) 


0.17  sq.  in. 
(109.  68  sq.  mm) 

3.4% 
85R812  E21 
Standard  -  A 


High  Rail 


Gage 
56-9/16" 
(1.437  m) 


0.00  sq.  in. 
(0.0  sq.  mm) 

0.0% 
181332  F20 
Standard  -  B 


Low  Rail 


Location  4 
Curvature  8°  -  30'  (205.6  m  radius)  -  Superelevation  4  5/8  in.  (117.5  mm) 


FIGURE  U 


Performance  of  Test  Rails  on  Chessie  System 


69 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   2  -  MILE  POST  233.2 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.08  sq.   in. 
(51.62  sq.  mm) 

1.6% 
IM19010  B9 
Int.  Mn. 


High  Rail 


Gage 

56-7/8" 
(1.445  m) 


0.075  sq.  in. 
(48.39  sq.  mm 

1.5% 
181332  D15 
Standard-  B 


Low  Rail 


Location  5 
Curvature  8°  -  30'  (205.6  m  radius)  -  Superelevation  4  3/4  in.  (120.7  mm) 


0.095  sq.  in. 
(61.29  sq.  mm) 

1.9% 
181332  F14 
Standard  -  B 


High  Rail 


Gage 
56-13/16" 
(1.443  m) 


0.065  sq.  in. 
(41.94  sq.  mm) 

1.3% 
CT19017  F6 
F.H.T. 


Low  Rail 


Location  6 
Curvature  8°  -  45'  (199.8  m  radius)  -  Superelevation  4  5/8  in.  (117.5  mm) 


FIGURE  12 


70  Bulletin  654  —  American  Railway  Engineerinji  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   2  -  MILE  POST  233.2 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


\ 

0.175  sq.   in. 

(112.91  sq.  mm) 

\ 
\ 

3.5% 

Gage 

CT07952  D17 

\ 

56-7/8" 

F.H.T. 

(1.445  m) 

High  Rail 


0.005  sq.  in. 
(3.23  sq.  mm 

0.1% 
94L143  B12 
Head-  Hardened 


Low  Rail 


Location  7 
Curvature  8°  -  45'  (199.  8  m  radius)  -  Superelevation  4  7/8  in.  (123.  8  mm) 


^v      ^v 

0.29  sq.   in.                      y      \ 

(187.11  sq.  mm)             N      1 
5.8%                              \    1 

Gage 

IM19010  D6                           \ 

57" 

Int.  Mn.                                  N 

(1.448  m 

High  Rail 


0.00  sq.  in. 
(0.0  sq.  mm) 

0.0% 
94L143  B38 
Head- Hardened 


Low  Rail 


Location  8 
Curvature  8°  -  30'  (205.  6  m  radius)  -  Superelevation  4  7/8  in.  (123.  8  mm) 


FIGURE  13 


Performance  of  Test  Rails  on  Chessie  System 


71 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   2  -  MILE  POST  233.2 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.08  sq.   in. 
(51.62  sq.  mm) 

1.6% 
181332  G16 
Standard  -  B 


High  Rail 


Gage 

56-5/8" 
(1.438  m) 


0.01  sq.  in. 
(6.45  sq.  mm) 

0.2% 
IM19010  B4 
Int.  Mn. 


Low  Rail 


Location  9 
Curvature  8°  -  45'  (199.  8  m  radius)  -  Superelevation  5  1/4  in.  (133.4  mm) 


0.11  sq.  in. 
(70.97  sq.  mm) 

2.2% 
80L680  E24 
Head- Hardened 


High  Rail 


Gage 

56-5/8" 
(1.438  m) 


0.02  sq.   in. 
(12.90  sq.  mm) 

0.4% 
85R812  B20 
Standard- A 


Low  Rail 


Location  10 
Curvature  8°  -  22'  (208.9  m  radius)  -  Superelevation  5  1/16  in.  (128.  6  mm) 


FIGURE  14 


72  Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  3  -  MILE  POST  234,0 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.03  sq.  in. 
(19.36  sq.  mm) 

0.6% 
181332  C21 
Standard-  B 


Low  Rail 


Gage 
56-13/16" 
(1.443  m) 


0.07  sq.  in. 
(45.16  sq.  mm) 

1.4% 
59R647  Dl 
Standard  -  A 


High  Rail 


Location  1 
Curvature  4°  -  15'  (411.0  m  radius)  -  Superelevation  2  5/8  in.  (66.7  mm) 


0.05  sq.  in. 
(32.26  sq.  mm) 

1.0% 
CT219017  E5 
F.H.T. 


Low  Rail 


Gage 

56-3/4" 
(1.441  m) 


0.035  sq.  in. 
(22.58  sq.  mm) 

0.7% 
CT08943  B16 
F.H.T. 


High  Rail 


Location  2 
Curvature  4°  -  15'  (411.0  m  radius)  -  Superelevation  2  7/8  in.  (73.0  mm) 


FIGURE  15 


Performance  of  Test  Rails  on  Chessie  System 


73 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO,   3  -  MILE  POST  234.0 


INSTALLED:     July  1972 


INSPECTED:    July  30,  1974 


0.03  sq.   in. 
(19.36  sq.  mm 

0.6% 
71R078  C27 
Standard  -  A 


Low  Rail 


Gage 
56-5/8" 
(1.438  m) 


0.065  sq.  in. 
(41.94  sq.  mm) 

1.3% 
181332  D4 
Standard-  B 


High  Rail 


Location  3 
Curvature  4°  -  15'  (411.0  m  radius)  -  Superelevation  2  5/8  in.  (66.7  mm) 


-                    ^^=^ 

"S 

0.02  sq.  in. 

\ 

(12.90  sq.  mm) 

0.4% 

Gage 

181332  E29 

56-1/2" 

Standard  -  B 

(1.435  m) 

\       Low  Rail     /"^ 

0.015  sq.  in. 
(9.68  sq.  mm) 

0.3% 
94H43  D9 
Head- Hardened 


High  Rail 


Location  4 

Curvature  4°  -  22'  (400.0  m  radius)  -  Superelevation  2  5/8  in.  (66.7  mm) 


FIGURE  16 


74  Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  3  -  MILE  POST  234.0 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.015  sq.  in. 
(9.68  sq.  mm) 

0.3% 
IM19010  D7 
Int.  Mn. 


Low  Rail 


Gage 
56-3/4" 
(1.441  m) 


0.035  sq.  in. 
(22.58  sq.  mm) 

0.7% 
IM19010  F16 
Int.  Mn. 


High  Rail 


Location  5 

Curvature  4°  -  22'  (400.0  m  radius)  -  Superelevation  2  3/8  in.  (60.  3  mm) 


0.01  sq.  in. 
(6.45  sq.  mm) 

0.2% 
94L143  D21 
Head-Hardened 


Low  Rail 


Gage 
56-5/8" 
(1.438  m) 


0.07  sq.  in. 
(45.16  sq.  mm) 

1.4% 
181107  G27 
Standard-  B 


High  Rail 


Location  6 
Curvature  4°  -  15'  (411.0  m  radius)  -  Superelevation  2  5/8  in.  (66.7  mm) 


FIGURE  17 


Performance  of  Test  Rails  on  Chessie  Systei 


CHESSIE  SYSTEM,  NEAR  OAKLAND.  MARYLAND 
TEST  CURVE  NO.   3  -  MILE  POST  234.0 


75 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.00  sq.  in. 
(0.0  sq.  mm) 

0.0% 
CT08943  C19 
F.H.T. 


Low  Rail 


Gage 
56-7/8" 
(1.445  m) 


0.045  sq.  in. 
(29.03  sq.  mm) 

0.9% 
CT07952  B17 
F.H.T. 


High  Rail 


Location  7 
Curvature  4°  -  15'  (411.0  m  radius)  -  Superelevation  2  5/8  in.  (66.7  mm) 


—                        =t=-Ss 

^ 

0.015  sq.  in. 

\ 

(9.68  sq.  mm) 

0.3% 

Gage 

59R647  Bl 

56-3/4" 

Standard-  A 

(1.441  m) 

Low  Rail        z^*^ 

^ 

0.00  sq.  in. 
(0.0  sq.  mm) 

0.0% 
94L143  B20 
Head- Hardened 


High  Rail 


Location  8 
Curvature  4°  -  22'  (400.0  m  radius)  -  Superelevation  2  3/8  in.  (60.3  mm) 


FIGURE  18 


76 


Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  3  -  MILE  POSE  234,0 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.01  sq.  in. 

^ 

(6.45  sq.  mrh) 

0.2% 

Gage 

94L143  C24 

56-9/16" 

Head- Hardened 

(1.437  m) 

Low  Rail       ^""^^ 

Location  9 


0.03  sq.  in. 
(19.36  sq.  mm) 

0.6% 
IM19010  Dl 
Int.  Mn. 


High  Rail 


Curvature  4    -  15'  (411.0  m  radius)  -  Superelevation  2  1/2  in.  (63.  5  mm) 


0.005  sq.  in. 
(3.23  sq.  mm) 

0.1% 
IM19010  A12 
Int.  Mn. 


Low  Rail 


Gage 
56-9/16" 
(1.437  m) 


0.05  sq.  in. 
(32.26  sq.  mm) 

1.0% 
63M022  E16 
Standard-  A 


High  Rail 


Location  10 
Curvature  4°  -  15'  (411.0  m  radius)  -  Superelevation  2  l/2  in.  (63.  5  mm) 


FIGURE  19 


Performance  of  Test  Rails  on  Chessie  System 


77 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  4  -  MILE  POST  235,0 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.035  sq.  in. 
(22,58  sq.  mm) 

0.7% 
59R647  B23 
Standard  -  A 


Low  Rail 


Gage 
56-1/2" 
(1.435  m) 


0,11  sq.  in. 
(70.97  sq.  mm) 

2,2% 
IM19010  B14 
Int.  Mn, 


High  Rail 


Location  1 
Cuivature  8°  -  08'  (214,9  m  radius)  -  Superelevation  5  in.  (127,0  mm) 


0.025  sq,  in. 
(16.13  sq.  mm) 

0,5% 
94L143  E38 
Head- Hardened 


Low  Rail 


Gage 
56-5/8" 
(1,438  m) 


0.035  sq,  in. 
(22.58  sq.  mm) 

0.7% 
94L143  D17 
Head-Hardened 


High  Rail 


Location  2 
Curvature  7°  -  52'  (222,2  m  radius)  -  Superelevation  4  3/4"  (120  ,7  mm) 


FIGURE  20 


78 


Bulletin  654 — American  Railway  Engineering  Associati( 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  4  -  MILE  POST  235.0 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.02  sq.  in. 

~^ 

(12.90  sq.  mm) 

0.4% 

1      Gage 

94L143  D14 

I     56-5/8" 

Head- Hardened 

1  {1.438  m) 

V       Low  Rail        /""^^ 

0.025  sq.  in. 
(16.13  sq.  mm) 

0.5% 
CT19017  C8 
F.H.T. 


High  Rail 


Location  3 
Curvature  8°  -  00'  (218.5  m  radius)  -  Superelevation  4  3/4  in.  (120.7  mm) 


0.01  sq.  in. 

^ 

(6.45  sq.  mm) 

0.2% 

Gage 

IM19010  D22 

56-1/2" 

Int.  Mn. 

(1.435  m) 

\       Low  Rail       y""^ 

^ 

High  Rail 


Location  4 
Curvature  8°  -  30'  (205,  6  m  radius  -  Superelevation  5  in.  (127.0  mm) 


0.055  sq.  in. 
(35.49  sq.  mm) 

1.1% 
85R812  D20 
Standard  -  A 


FIGURE  21 


I 


Performance  of  Test  Rails  on  Chessie  System 


79 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.   4  -  MILB  POST  235.0 


INSTALLED:     July  1972 


INSPECTED:     July  30,  1974 


0.005  sq.  in. 

^ 

(3.23  sq.  mm) 

0.1% 

Gage 

181332  C28 

1     56-5/8" 

Standard  -  B 

1  (1.438  m; 

\         Low  Rail        ^^^ 

0.01  sq.  in. 
(6.  45  sq.  mm) 

0.2% 
94L143  D16 
Head- Hardened 


High  Rail 


Location  5 
Curvature  7*^  -  34'  (231.0  m  radius)  -  Superelevation  4  7/8  in.   (123.8  mm) 


0.005  sq.   in. 
(3.23  sq.  mm 

0.1% 
CT19017  BIO 
F.H.T. 


Low  Rail 


Gage 

56-5/8" 
(1.438  m) 


0.075  sq.   in. 
(48.39  sq.  mm) 

1.5% 
181332  H18 
Standard-  B 


High  Rail 


Location  6 
Curvature  8°  -  22'  (208.9  m  radius)  -  Superelevation  4  7/8  in.  (123.8  mm 


FIGURE  22 


80 


Bulletin  654 — American  Railway  Engineering  Association 


CHESSIE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  4  -  MILE  POST  235.0 


INSTALLED:     July  1972 


INSPECTED:   July  30,  1974 


0.015  sq.  in. 
(9.68  sq.  mm) 

0.3% 
IM19010  D8 
Int.  Mn. 

Gage 
56-3/4" 
(1.441m) 

v       Low  Rail        ^^^""""^ 

0.05  sq.  in. 
(32.26  sq.  mm) 

1.0% 
IM19010  DIO 
Int.  Mn. 


High  Rail 


Location  7 
Curvature  8°  -  00'  (218.5  m  radius)  -  Superelevation  4  7/8  in.  (123.8  mm) 


0.00  sq.  in. 
(0.0  sq.  mm) 

0.0% 
CT19017  E8 
F.H.T. 


Low  Rail 


Gage 
56-3/4" 
(1.441m) 


0.07  sq.  in. 
(45.16  sq.  mm) 

1.4% 
59R647  C23 
Standard-  A 


High  Rail 


Location  8 
Curvature  8°  -  00'  (218.5  m  radius)  -  Superelevation  5  1/8  in.  (130.2  mm) 


FIGURE  23 


I 


Performance  of  Test  Rails  on  Chessie  System 


81 


CHESSTE  SYSTEM,  NEAR  OAKLAND,  MARYLAND 
TEST  CURVE  NO.  4  -  MILE  POST  235.0 


INSTALLED:     July  1972 


INSPECTED:    July  30,  1974 


0.01  sq.  in. 
(6.45  sq.  mm) 

0.2% 
181110  D13 
Standard-  B 


Low  Rail 


Gage 

56-5/8" 
(1.438  m) 


0.065  sq.  in. 
(41.94  sq.  mm) 

1.3% 
CT19017  F8 
F.H.T. 


High  Rail 


Location  9 

Curvature  8°-00'  (218.5  m  radius)  -  Superelevation  4  3/4  in.  (120.7  mm) 


0.035  sq.  in. 
(22.58  sq.  mm 

0.7% 
66M022  D16 
Standard  -  A 


Low  Rail 


Gage 

56-5/8" 
(1.438  m) 


0.05  sq.  in. 
(32.26  sq.  mm) 

1.0% 
180991  E18 
Standard  -  B 


High  Rail 


Location  10 
Curvature  6°-45'  (258.9  m  radius)  -  Superelevation  4  3/8  in.  (111.1  mm) 


FIGURE  24 


82 


Bulletin  654 — American  Railway  Engineering  Association 


(Ba^Dui  aa-enbg)  -feaAV  P^e^H  aS^jaAy 


Performance  of  Test  Rails  on  Chessie  System 


83 


<J 
W 

Q 

<: 
w 

a 
I— ( 

< 


X 

■<* 

O 

0 

X 

'-' 

H 

h 

1 

to 

O 

CO 

O 

H 

o 

P^ 

2 

'"' 

0 

W 

Pi 

o 

u 

< 

p^ 

W 

w 

>-' 

hJ 

Oh 

W 

H-l 

Q 

^ 

s 

ro 

00 

t^ 

fvj 

vO 

^ 

ro 

r^ 

ro 

ro 

ro 

O 

OO 

00 

g 

CO 

r- 

vD 

r~- 

00 

,      ' 

a 

ro 

o 

ro 

o^ 

00 

o  o 

« 

« 

■ 

• 

• 

Z  °o 

ro 

00 

O^ 

o 

CO 

IT 

O 

in 

^ 

t^ 

00 

S?  "(^ 

W 

•~< 

•"• 

>    c 

51 

d 

xO 

o^ 

in 

00 

^ 

CO 

•  r-l 

■-' 

o 

—' 

'-' 

■"^ 

Z 

o 

o 

CD 

d 

o 

<n 

ro 

sD 

-* 

cr- 

^ 

r^ 

^ 

^' 

CD 

o 

b 

^  ° 

£ 

■^ 

^_i 

ro 

o 

CO 

. 

E 

a^ 

r^ 

sO 

o 

o 

o  o 

« 

• 

« 

• 

• 

S     CO 

, 

i-H 

00 

i-H 

ro 

o 

cr 

^ 

ro 

iri 

■"^ 

ro 

>   c 

^     .H 

•r-4 

iri 

^ 

00 

ro 

in 

O 

O 

o 

o 

o 

cr 

o 

o 

o 

o 

Cl 

w 

ro 

in 

o^ 

CO 

00 

^ 

^' 

^ 

r^ 

o 

o 

o 

__^  o 

a 

^ 

a^ 

cr- 

CO 

rt 

, 

a 

cr- 

CO 

ro 

xO 

00 

o  o 

a 

• 

• 

• 

• 

t-H 

00 

f-H 

o 

in 

Tt< 

^ 

xD 

ro 

>   c 

U     .r^ 

51 

•  1-1 

in 

in 

in 

in 

^ 

o 

o 

o 

o 

o 

'Z 

• 

. 

• 

cr 

o 

o 

CD 

o 

o 

ro 

■* 

r- 

ro 

00 

£^ 

^ 

^ 

o 

o 

o 

o 

^  "? 

a 

,.H 

vO 

00 

in 

I— t 

d  o 

a 

t^ 

in 

^ 

00 

^  ^ 

. 

00 

in 

ro 

vd 

ITI 

cr 

ro 

-* 

ro 

rJ 

S?  "" 

en 

>    fl 

^1      -H 

. 

in 

CI 

MD 

t^ 

CO 

•— ' 

^ 

•  H 

O 

o 

o 

o 

O 

z 

cr 

CO 

O 

o 

o 

o 

o 

1 

(U 

<; 

CQ 

ni    (U 

JJ 

P^ 

1 

1 

":!    <D 

'O 

ni 

>> 

•V 

T3 

J.    <u 

<0 

H 

u 

M 

^    C 

a 

ni 

n! 

a  "i 

1     0) 

•r-l 

'O 

XI 

T)  T3 

>     rt 

rt 

fl 

C 

5   c 

ri    »H 

1^    <u 

Pi 

rt 

nS 

4^1    ni 

<U    ni 

;:!    ^^ 

55 

W 

^2 

KE 

h  H 

DIRECTORY 

CONSULTING    ENGINEERS 


FRANK   R.  WOOLFORD 

Engineering    Consultant — Railroadt 

24  Josepha   Ave. 

San   Francisco,  Ca.  94132 

(415)  587-1569 

246  Seadrift   Rd. 

Stinson  Beach,  Ca.  94970 

(415)  868-1555 


^mm  WestenhofF  &  Novfck,  Inc. 
■yi     Consulting  Engineers 

Civil — Mechanical — Electrical 

Fixed  &  Movable  Bridges 

Soils,   Foundations,   Buildings 

Structural   &   Underwater   Investigations 

Planning,      Feasibility,      Design,      Inspection 

222    W.    Adams    St.,    Chicago,    III.    60606 
New   York  Washington  Panoma 


HAZELET  &  ERDAL 

Consulting   Engineers 

Design         Investigations         Reports 
Rxed    and    Movable    Bridges 

150  So.  Wacker  Dr.,   Chicago,   III.  60606 
Louisville        Cincinnati        Washington 


HIMTB 


HOW/Ano  NEEOLEB 
TAMtVIEM  SaECtOErjOOFF 


Feasibility  studies  and  design  services  for 

Bus  and  rail  transit  Terminals 

Regional  and  urban  planning  Parking 

Soils  and  foundations  Tunnels 

Structures  Utilities 
Environmental  Impact  studies 

Offices  in  28  cities  816  474-4900 

1805  Grand  Avenue,  Kansas  City,  Missouri  64108 


MODJESKI  AND  MASTERS 

ContufHng  Enghf*n 

Design,    Inspection   of  Construction   &   In- 
spection   of    Physical    Condition    of   Fixed 
&  Movable  Railroad   Bridges 

P.O.    Box   2345,    Harrisburg,    Pa.    17105 
1055  St.  Charies  Ave.,  New  Orleans,  La. 


CLARK,   DIETZ  AND 
ASSOCIATES-ENGINEERS,   INC. 

Consulting  Engineers 

Bridges     Structures,  Foundations,  Indus- 
trial Wastes  and  Railroad  Relocation 

211    No.   Race   St.,   Urbane,   III. 

Sanford,   Fla.  Memphis,  Tenn. 

Jackson,  Miss.  St.   Louis,  Mo. 

Chicago,  III. 


84-1 


84-2 


Directory  of  Consulting  Engineers 


<§» 


Engineers 
Designers     Planners 


PARSONS  "<»»••     location.     Shop 

RDIMrk'CDMOtrt:  foc"'»l*«.    Container/ 

BRINC-KbRHOI-F  Bulk     Cargo,     Handling 

OUADE  Utilities,     Bridges,    To«- 

^  nels.     Evaluations,     Ap- 

DOUGLAS  praisals.  Supervision 

ONE  PENN  PLAZA,  NEW  YORK,  NY  10001 

Boston         .        Denver        ,        Honolulu 
San  Francisco        .       Trenton 


HARDESTY  &   HANOVER 

Coniu/t/ng  Eng/necrs 

TRANSPORTATION 
ENGINEERING 

Highways       •       Railways 

Bridges — Fixed    and   Movable 

Design       •       Resident   Inspection 

Studies       •       Appraisals 

101    Park  Ave.,   New  York,  N.  Y.   10017 


THOAAAS  K.  DYER,  INC. 

Consulting  Engineers 

Railroads — Transit  Systems 
Track,  Signals,  Structures 

Investigations  and  Feasibility  Reports 
Planning,  Design,  Contract  Documents 

1762  Massachusetts  Avenue 
Lexington,  Mass.  02173 


nnniliGjetavitCatliefflfjaiiizaitoii 

""\3--..  CONSULTING  ENGINEERS 

165  W.'VVACKEP  DRIVE..  CHICAGO  60601 


SUBWAYS  .  RAILROADS  •  PUBLIC  TRANSIT 

TRAFFIC .  PARKING  .HIGHWAYS 
BRIDGES  .  PORT  DEVELOPMENT  •  AIRPORTS 
COMMUNITY  PLANNING  •  URBAN  RENEWAL 
MUNICIPAL  WORKS  •  INDUSTRIAL  BUILDINGS 
ENVIRONMENTAL  SCIENCE  AND  ENGINEERING 


■■^ 


IEC0 

RAILROAD 
DESIGN  &  ELECTRIFICATION 

Planning     •     Design 
Construction  Management 


INTERNATIONAL  ENGINEERING 
COMPANY,  INC. 

220  MONTGOMERY  STREET 
SAN  FRANCISCO,  CALIFORNIA  94104 


RILEY,  PARK,  HAYDEN  & 
ASSOCIATES,  INC. 

Consulting   Engineers 

Survey  Services,  Photogrammetry,  Gen- 
oral  Civil,  Bridges,  Railroads  &  indus- 
trial Park  Design. 

136  Marietta  St.,  N.  W. 
Atlanta,  Georgia  30303 

(404)   577-5600 


Directory  of  Consulting  Engineers 


84-3 


SVERDRUP  &  PARCEL  AND  ASSOCIATES,  INC. 

800  No.  Twelfth  Blvd.  •  St.   Louis.  Mo.  63101 

Boston  •  Charleston  •  Gainesville  •  Jacksonville 
Nashville  •  New  York  •  Ptioenix  •  San  Francisco 
Seattle      •      Silver  Spring      •      Washington,  D.C. 


•  design 

•  planning 

•  construction 
management 


SVERDRUP  & 
PARCEL 


CONSULTING  ENGINEERS 


I 


HIV  PORTER  AND  RIPA 
ASSOCIATES,  INC. 


ENGINEERING  •  PLANNING  ARCHITECTURE 

Design  Inspections  Reports 

Planning  Structures 

Environmental  Studies 

2M  Madison  Avenue,    M«rritt*wn,  NeiM  J*r(«y>T9ll 


RALPH  WHITEHEAD 
&  ASSOCIATES 

Consulting   Engineers 

Bridges,    Buildings,   Highways, 

Railroads,   Airports 

1945    RANDOLPH    ROAD 

CHARLOTTE,   NORTH   CAROLINA  28207 


SOROS  ASSOCIATES 

Consulting   Engineers 

Transfer  Terminals  &  Ports  For  Dry  Bulks, 

Liquids  &  Contoiners — Waterfront  Structures 

Materials  Handling  Systems 

575   Lexington  Ave. 

Nev*^  York,  N.  Y.   10022 

(212)   421-0400 

Rio  da  Janeiro  Santiago,  Chile 

Sydney,  Australia 


BAKKE  &  KOPP,  INC. 

Consulting  Engineers 

RAILWAY  AND  HIGHWAY  BRIDGES 

SPECIAL  AND  HEAVY  STRUCTURES 

INVESTIGATIONS  AND   REPORTS 

4915  W.  35lh  St.  Minneapolis,  MN  55416 

1612)   920-9383 


A.  J.  HENDRY,  INC. 


> 


CONSULTING  ENGINEERS 


SIGNALS  •  CONWIUNICATIONS  •  AUTOAAATION  •  EIECTRIFICATION 

RAILROADS  •  RAIL  TRANSIT 

SUITE  810  OSBORN  BUILDING 

ST.  PAUL,  MINNESOTA  55102  (612)  222  2787 


84-4 


Directory  of  Consulting  Engineers 


SPAULDING  ENGINEERING  CO. 

CONSULTING  ENGINEERS 

MEMBER 

AMERICAN  CONSULTING  ENGINEERS  COUNCIL 

1821    UNIVERSITY  AVENUE 

ST.  PAUL,  MINNESOTA  55104 

PHONE    612/644-5676 


TURNER  ENGINEERING 
COMPANY 

(SAWYER-PIEPMEIER) 

RAILROAD  ENGINEERING 

306  GAY  ST. 
NASHVILLE,   TENNESSEE   37201 

615-244-2144 
ALBANY,   NY      518-456-1994 


MORE  TON  MILES 

of  SERVICE 

and  LESS  MAINTENANCE 

with 


BALLAST 
CLEANING 


PEWO 
ERUICES 


RAIL 
GRINDING 


SoutKwm   Pacific 


mm: 


Discover  how  you  can  get  more  ton  miles  of 
service  at  less  maintenance  cost  by  using  Sf>eno 
Ballast  Cleaning  and  Rail  Grinding. 

THROUGHOUT  THE  CONTINENT 

FRANK  SPENO  RAILROAD  BALLAST  CLEANING  COMPANY,  INC. 

306  North  Cayuga  St.,  Ithaca,  New  York  14850 
ClarK  Street.  Box  219,  East  Syracuse,  New  York  13057 

SPENO  INTERNATIONAL,  S.A.  lEC-HOLOEN,  LTD. 

22  Pare  Chateau  Banquet,  Geneva.  Switzerland   .., 8180  Cote  de  Liesse  Road 

(For  Ra;l  G;_indmg  Onts.cie  the  Nor-h  DO§     Montreal.  Canada  H4T1G8 


TRASCO  Track  Skates 


Preferred  by  skatetnen 

Light 

Tough 

Balanced  hand  hold 

No  curl  tongue 

TRACK  SPECIALTIES 
COMPANY 

Box  729  Westport ,  Conn . 


American  Railway 

Engineering  Association— Bulletin 


Bulletin  655  November-December  1975 

Proceedings  Volume  77* 


CONTENTS 

PART   1— MANUAL   RECOMMENDATIONS 

Yards  and  Terminals  (14) 87 

Buildings    (6)    162 

Electrical  Energy  Utilization  (33) 181 

Environmental  Engineering  (13) 189 

Concrete  Ties  (Special  Committee) 193 

Roadway  and  Ballast  (1) 237 

Steel   Structures   (15)   249 

PART  2^REP0RTS  OF  COMMITTEES 

Highways  (9) 255 

Engineering  Records  and  Property  Accounting  (11) 273 

Yards  and  Terminals  (14) 279 

Directory  of  Consulting  Engineers 286—1 


'Proceedings  Volume  77  (1976)  will  consist  of  ABBA  Bulletins  654,  September- 
October  1975:  655.  November-December  1975;  656,  January-February  1976;  and  658, 
June-July  1976  (Technical  Conference  Report  issue).  Blue-covered  Bulletin  657,  .^rll- 
May  1976  (the  Directory  issue),  is  not  a  part  of  the  Annual  Proceedings  of  the  Aaaociatioa. 


BOARD  OF  DIRECTION 
1975-1976 

President 
J.  T.  Wakd,  Senior  Assistant  Chief  Engineer,  Seaboard  Coast  Line  Railroad,  500  Water 
St.,  Jacksonville,  FL  32202 

Vice  Presidents 
John  Fox,  Deputy  Chief  Engineer,  Canadian  Pacific  Rail,  Windsor  Station,  Montreal, 

PQ  H3C  3E4 
B.  J.  WoRLEY,  Vice  President— Chief  Engineer,  Chicago,  Milwaukee,  St.  Paul  &  Pacific 

Railroad,  Union  Station,  Room  898,  Chicago,  IL  60606 

Past  Presidents 

D,  V.  Sartore,  Chief  Engineer — Design,  Burlington  Northern,  Inc.,  176  E.  Sth  St.,  St. 

Paul,  MN  SS 101 
R.  F.  Bush,  Chief  Engineer,  Erie  Lackawanna  Railway,  Midland  BIdg.,  Cleveland,  OH 

44115 

Directors 
R,  W.  Pember,  Chief  Engineer — Design  and  Construction,  Louisville  &  Nashville  Rail- 
road, P.  O.  Box  1198,  Louisville,  KY  40201 

E.  Q.  Johnson,  Senior  Assistant  Chief  Engineer,  Chessie  System,  P.  O.  Box   1800, 

Huntington,  WV  25718 
W.  E.  FuHR,  Assistant  Chief  Engineer— Staff,  Chicago,  Milwaukee,  St.  Paul  k  Pacific 

Raibroad,  Union  Station,  Room  898,  Chicago,  IL  60606 
B.  E.  Pearson,  Chief  Engineer,  Soo  Line  Railroad,  Soo  Line  Bldg.,  Room  1520,  Minne- 

apoUs,  MN  55440 
P.  L.  Montgomery,  Manager  Engineering  Systems,  Norfolk  &  Western  Railway,  8  N. 

Jefferson  St.,  Roanoke,  VA  24042 
E.  C    HoNATH,  Assistant  General  Manager  Engineering,  Atchison,  Topeka  &  Santa  Fe 

Railway,  900  Polk  St.,  Amarillo,  TX  79171 
Mike  Rougas,  Chief  Engineer,  Bessemer  &  Lake  Erie  Railroad,  P.  O.  Box  471,  Green- 
ville, PA  16125 
J.  W.  DeVaixe,  Chief  Engineer  Bridges,  Southern  Railway  System,  99  Spring  St.,  S.  W., 

Atlanta,  GA  30303 
R.  L.  Gray,  Chief  Engineer,  Canadian  National  Railways,  P.  O.  Box  8100,  Montreal, 

PQ  H3C  3N4 
E.  H.  Waring,  Chief  Engineer,  Denver  &  Rio  Grande  Western  Railroad,  P.  O.  Box 

5482,  Denver,  CO  80217 
Wm.   Glavin,   General  Manager,  Grand  Trunk  Western  Railroad,   131  W.  Lafayette 

Blvd.,  Detroit,  MI  48226 
G.  H.  Maxwell,  System  Engineer  of  Track,  Union  Pacific  Railroad,  1416  Dodge  St., 

Omaha,  NE  68179 

Treasurer 
A.  B.  HiLLMAN,  Jr.,  Chief  Engineer,  Belt  Railway  of  Chicago,  6900  S.  Central  Ave., 

Chicago,  IL  60638 

Executive  Director 
Earl  W.  Hodgkins,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 
Assistant  to  Executive  Director 
N.  V.  Enoman,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Administrative  Assistant 
D.  F.  Fredley,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Published  by   the   American    Railway  Engineering   Association,   Bi-Monthly,   January-February,  April- 
May,   June-July,   September-October  and  November-December,   at 
59  East  Van  Buren  Street,  Chicago,  01.  60605 

Second  class  postage  at  Chicago,  III.,  and  at  additional  mailing  offices. 
Subscription  $15  per  annum 

Copyright  ©  1975 

AuBsicAH  Railway  Engineesing  Association 

All  rights  reserved. 

No   part    of    thb   publication    may   be   reproduced,    stored   in    an    information    or   data   retrieval 

ayatem,    or    transmitted,    in    any    form,    or    by    any    means — electronic,    mechanical,    photocopyins. 

ncording,  or  otherwise — ^without  the  prior  written  permisnon  of  the  publisher. 


PART   1 
MANUAL  RECOMMENDATIONS 


All  the  recommendations  submitted  by  committees  for  adoption  and 
publication  in  the  1976  Supplement  to  the  AREA  Manual  for  Railway  Engi- 
neering are  printed  in  this  issue  of  the  Bulletin.  These  recommendations  will 
be  formally  submitted  for  review  and  approval  to  the  Board  Committee  on 
Publications  and  the  AREA  Board  of  Direction.  Comments  or  objections  by 
Members  regarding  any  of  these  recommendations  should  be  submitted  to 
the  Executive  Manager  not  later  than  FEBRUARY  16,   1976. 


85 

Bui.   655 


Manual  Recommendations 
Committee   14 — Yards  and  Terminals 

Report   on   Assignment   B 

Revision  of  Manual 

G.  H.  Chabot  (chairman,  subcommittee),  all  members  of  Committee  14. 

Your  committee  submits  for  adoption  the  following  recommendations  with 
respect  to  Chapter  14  of  the  Manual: 

Delete  present  Part  1 — ^Terminals,  Part  2 — Passenger  Terminals,  Part  3 — Freight 
Terminals,  and  Part  4 — Locomotive  Terminals,  substituting  therefor  the  follo\ving 
completely  re\'ised  and  reorganized  material. 

AMERICAN  RAILWAY  ENGINEERING  ASSOCIATION 
MANUAL  FOR  RAILWAY  ENGINEERING 

CHAPTER  14 
YARDS  AND  TERMINALS 


FOREWORD 


This  chapter  deals  witli  tlie  engineering  and  economic  problems  of  location, 
design,  construction  and  operation  of  yards  and  terminals  used  in  railway  service. 
Such  problems  are  substantially  the  same  whether  railway's  ownership  and  use  is 
to  be  individual  or  joint.  The  location  and  arrangement  of  the  yard  or  terminal  as 
a  whole  should  pennit  tlie  most  convenient  and  economical  access  to  it  of  the  tribu- 
tary lines  of  railway,  and  the  location,  design  and  capacity  of  the  several  facilities 
or  components  witliin  said  yard  or  terminal  should  be  such  as  to  handle  the  tributary 
traffic  expeditiously  and  economically  and  to  serve  tlie  public  and  customer 
conveniently. 

In  the  design  of  new  yards  and  terminals,  the  retention  of  existing  railway 
routes  and  facilities  may  seem  desirable  from  the  standpoint  of  initial  expenditure 
or  first  cost,  but  may  pro\e  to  be  extra\agant  from  the  standpoint  of  operating  costs 
and  efficiency.  A  true  economic  balance  should  be  achie\  ed,  keeping  in  mind  possible 
future  trends  and  changes  in  traffic  criteria,  as  to  volume,  intensity,  direction  and 
character. 

Although  tliis  chapter  contemplates  the  establishment  of  entirely  new  facilities, 
the  recommendations  therein  will  apply  equally  in  the  rearrangement,  modernization, 
enlargement  or  consolidation  of  existing  yards  and  terminals  and  related  facilities. 
Parts    1    tlirough    4   incl.    formulate   specific   and   detailed   recommendations   relative 

87 


88         Bulletin  655 — American  Railway  Engineering  Association 

to  tlie  handling  of  freight,  regardless  of  the  type  of  commodity  or  merchandise,  at 
the  originating,  intermediate  and  destination  points.  Parts  5  and  6  relate  to  loco- 
motive and  passenger  facilities,  respectively,  and  Part  7  covers  miscellaneous  items 
and  facilities  which  may  be  found  in  yards  and  terminals,  necessary  for  the  general 
operation  and  function  of  railways.  Part  S — Scales,  describes  the  various  weighing 
systems  used  in  railway  service  and  is  included  as  a  part  of  this  chapter  since 
the  majority  of  scales  are  located  at  yards  and  terminals. 


TABLE   OF   CONTENTS 


Part   1   Generalities  Page 

Foreword    91 

1.1  Joint  Yards  and  Terminals   92 

1.2  Air  Rights   92 

1.3  Automatic  Car  Identification  System    92 

1.4  Environmental  Provisions    92 

1.5  Security    Requirements    93 

Part  2  Freight  Yards  and  Freight  Terminals 

Foreword    95 

2.1  General    96 

2.2  Track  Arrangement   96 

2.3  Yard    Components    97 

2.4  Hump  Classification  Yard  Design   99 

2.5  Flat  Classification  Yard  Design   110 

Part  3   Freight   Delivery   and   Transfer 

Foreword    Ill 

3.1  Freight   Houses    112 

3.2  Team  Yards    115 

3.3  Driveways    115 

Part  4  Specialized  Freight  Terminals 

Foreword    117 

4.1  Waterfront    118 

4.2  Rail-Truck    119 

4.3  Auto  and  Truck  Transport   123 

4.4  Bulk,  Sohd   129 

4.5  Bulk,  Liquid 130 

4.6  Merchandise    130 

Part  5  Locomotive  Facilities 

Foreword    133 

5.1  General    134 

5.2  Servicing   Facilities    135 

5.3  Inspection  Pits    136 

5.4  Diesel,   Diesel-Electric  and  Electric    137 

5.5  Steam    138 


Manual   Recommendations  89 

Part  6  Passenger  Facilities 

Foreword    141 

6.1  General    142 

6.2  Site    142 

6.3  Track  Arrangement    144 

6.4  Station   Proper    145 

6.5  Coach   Yard    152 

6.6  Modernization    157 

Part  7  Other  Yard  and  Terminal  Facilities 

Foreword    159 

7.1  Stores    160 

7.2  Storage    160 

7.3  Reclamation   161 


Manual  Recommendations 91 

Part  1 
Generalities 

FOREWORD 

This  part  deals  with  the  general  conditions,  factors,  features  and  requirements 
which  may  be  basically  common  to  or  directly  related  with  the  planning,  design, 
construction  and  function  of  yards  and  terminals  and  their  associated  facilities. 


CONTENTS 

Section  Page 

1.1  Joint  Yards  and  Terminals   92 

1.2  Air    Rights    92 

1.3  Automatic  Car  Identification  System   92 

1.4  Environmental  Provisions    92 

1.5  Security   Requirements    93 


92         Bulletin  655 — American  Railway  Engineering  Association 

1.1  JOINT  YARDS  AND  TERMINALS 

1.1.1  Economy 

(a)  It  is  not  axiomatic  that  a  joint  yard  or  terminal  under  one  management 
can  be  operated  more  economically  and  satisfactorily  than  two  or  more  separately 
operated  yards  or  terminals  of  the  same  aggregate  capacity. 

(b)  In  a  joint  yard  or  terminal,  a  single  organization  should  control  all  con- 
struction, operation,  maintenance  and  other  activities  within  the  tenninal  zone.  All 
employees,  including  those  of  the  participating  railways,  while  functioning  within 
the  yard  or  terminal  zone  should  be  subject  to  the  control  of  the  appropriate  oflBcers. 

1.1.2  Analyses 

(a)  A  joint  yard  or  terminal  should  not  be  undertaken  without  exhaustive 
comparable  analyses  of  what  may  be  attained  in  expedition,  economy  and  conveni- 
ence, under  the  arrangements  to  be  surrendered  and  under  those  proposed. 

(b)  A  joint  yard  or  tenninal  may  be  undertaken  where  analyses  justify  antici- 
pation of  its  economy  as  compared  with  other  available  alternatives,  or  where 
governmental  authority  or  popular  demand  has  substantially  the  force  of  mandate. 

1.1.3  Agreement 

A  joint  terminal  agreement  should  anticipate  and  definitely  cover  all  relation- 
ships between  and  among  the  owners,  the  users  and  tiie  management  of  the  joint 
facilities.  With  a  view  to  discovering  weaknesses  and  omissions  which  may  be 
overcome  in  a  new  agreement,  it  will  be  found  helpful,  before  drafting  it,  to  examine 
existing  agreements  and  consult  those  charged  with  their  administration. 

1.2  AIR  RIGHTS 

At  yards  and  tenninals  centrally  located  in  the  larger  cities,  space  over  the 
facilities  can  often  be  made  available,  with  advantage  and  profit,  for  commercial 
purposes  such  as  post  offices,  office  buildings  with  store  frontage  on  the  streets, 
hotels,  certain  manufacturing  enterprises,  and  the  like.  These  will  help  materially 
in  carrying  the  charges  on  capital  investments  and  tax  assessments  for  the  real  estate 
occupied. 

1.3  AUTOMATIC  CAR  IDENTIFICATION  (ACI)  SYSTEM 

Improved  yard  and  terminal  efficiencies  and  performance,  including  total  termi- 
nal control,  can  be  achieved  with  an  automatic  car  identification  (ACI)  system. 
One  report  on  the  subject  and  its  application  has  been  published  in  the  Proceedings, 
Vol.  72,  1973,  pages  230  and  231. 

1.4  ENVIRONMENTAL  PROVISIONS 

Any  yard  and  tenninal  design  must  consider  the  environmental  factors  and 
provide  for  the  minimum  controls  established  and  required  by  federal,  state  and 
local  laws,  directives  and  ordinances  applicable  to  land,  water,  air  and  noise  pollu- 
tion. Chapter  13 — Environmental  Engineering — deals  with  tliese  features  and 
requirements. 


Manual  Recommendations 93 

1.5  SECURITY  REQUIREMENTS 

1.5.1  Fire  Protection 

(a)  Hydrants  with  hose  houses  and  equipment  should  be  located  at  various 
points  within  the  yard  or  terminal  so  as  to  permit  the  use  of  at  least  two  streams  of 
water  on  any  structure.  Such  facilities  should  comply  to  applicable  codes  and 
regulations. 

(b)  Water  mains  and  hydrants  should  be  located  with  due  regard  to  future 
yard  or  terminal  expansion. 

(c)  Water  mains  should  be  built  in  loops,  if  practicable. 

(d)  Chemical  extinguishers  should  be  conveniently  placed  to  afford  protection, 
especially  against  oil  and  electric  fires. 

(e)  Fire  lanes  should  be  provided  for  access  to  all  buildings  by  fire  fighting 
equipment. 

1.5.2  Theft  and  Vandalism 

Protective  measures  must  be  carefully  considered  in  the  design  of  each  indi- 
vidual situation.  A  report  on  the  subject  of  theft  and  vandalism  is  contained  in  the 
Proceedings,  Vol.  75,  1974,  pages  609  to  611,  inch  Infonuation  on  this  subject  may 
be  obtained  from  the  Transportation  Research  Board,  National  Academy  of  Sciences, 
Washington,  D.C.,  report  No.  487,  Crime  and  Vandalism  in  Public  Transportation — 
5  Reports  (1974),  ISBN  0-309-02273-8,  64  pp. 


Manual  Recommendations 95 

Part  2 
Freight  Yards  &  Freight  Terminals 


FOREWORD 

This  part  deals  with  the  engineering  and  economic  problems  of  location,  design, 
construction  and  operation  of  all  the  facilities  provided  by  a  railway  company,  or 
by  railway  companies  in  common,  or  acting  jointly,  as  the  case  may  be,  to  handle 
freight  to  or  from  or  tlirough  and  witliin  a  given  district  on  behalf  of  such  railway 
company  or  companies. 

Conditions  of  demand  and  feasibiUty  vary  widely,  and  generally  each  case  of 
constructing  an  altogether  new  layout  on  a  large  scale,  or  of  remodeling  or  consoU- 
dating  an  extensive  existing  layout,  constitutes  an  essentially  basic  problem. 

Each  of  these  features  and  its  appurtenances,  with  a  full  knowledge  of  the 
average  and  maximum  demands  to  be  made  upon  it,  must  be  carefully  designed  to 
fulfill  its  particular  functions  expeditiously  and  economically. 

The  designation  "freight  yard"  (sometimes  called  marshaling  yard)  and  "freight 
terminal"  as  used  herein  are  only  relative  to  their  location  within  a  railway  system, 
have  similarity  in  meaning  and  may  perfonn  like  functions.  The  use  of  the  term 
"yard"  as  opposed  to  "terminal"  may  be  used  in  a  certain  interpretation  or  within 
a  certain  geographical  area  to  designate  an  essential  unit,  a  supplementary  adjunct 
or  a  tributary  to  a  terminal. 


CONTENTS 

Section  Page 

2.1  General    96 

2.2  Track  Arrangement   96 

2.3  Yard   Components    97 

2.4  Hump  Classification  Yard  Design   99 

2.5  Flat  Classification  Yard  Design   110 


96         Bulletin  655 — American  Railway  Engineering  Association 

2.1  GENERAL 

To  meet  traffic  requirements  a  yard  or  terminal  should  be  able,  even  in  peak 
periods,  to  receive  trains  promptly  upon  arrival,  perform  any  auxiliary  service  (such 
as  weighing,  icing,  feeding  and  watering  stock,  making  running  repairs,  etc.),  switch 
cars  into  tlieir  proper  classification  without  appreciable  delay,  and  dispatch  these 
cars  in   dieir  proper  position  in  outgoing  trains  in  minimum   time. 

The  number  of  yards  should  be  as  small  as  is  consistent  with  the  efficient  han- 
dling of  traffic. 

An  additional  yard  is  warranted  only  when  it  will  result  in  greater  economy 
than  the  enlargement  or  reconstruction  of,  or  substitution  of  a  new  yard  for,  an 
existing  yard  or  yards. 

Yard  or  terminal  layouts  should  provide  for  future  expansion  so  that  the  number 
and  length  of  die  tracks  in  diem  may  be  increased  as  required  with  niinimmn  inter- 
ference with  operation  or  minimum  relocation  of  existing  trackage. 

An  existing  yard  or  terminal  which  is  inadequate  to  handle  the  current  or  im- 
mediately prospective  traffic  should  be  enlarged,  or  redesigned  and  rebuilt,  or 
abandoned  in  favor  of  a  yard  or  teniiinal  in  a  different  location,  according  to  which 
of  these  alternatives  will  result  in  the  greatest  economy. 

Generally  in  computing  car  capacity  use  a  minimum  of  50  ft  per  car  for  all 
freight  car  tracks  other  than  repair  tracks  and  tracks  for  special  equipment. 

Yard  lighting  is  desirable.  The  economical  distribution  of  light  over  the  area 
involved,  so  as  to  provide  proper  intensity  of  illumination,  requires  careful  design. 
Recommendations  of  the  AAR  Engineering  Division  Committee  on  Electrical  Facili- 
ties— Fixed  Property,  should  be  consulted. 

An  adequate  drainage  system  is  essential. 

Communication  facilities  such  as  teletype,  pneumatic  tube  systems,  loud  speakers, 
ACI,  talkback,  paging  systems,  television,  telephones  and  radios  should  all  be  con- 
sidered to  expedite  operations. 

The  AREA  Proceedings  should  be  consulted  for  detailed  information. 

2.2  TRACK  ARRANGEMENT 

(a)  Main  tracks  should  not  pass  through  a  yard. 

(b)  Connections  to  die  main  track  from  the  receiving,  classffication  or  depar- 
ture tracks  should  be  as  direct  as  practicable. 

(c)  Crossovers  should  be  provided  as  required  to  facilitate  all  normal  and 
regular  movements  in  the  yard  or  between  the  yard  and  the  main  track,  and  their 
location  should  be  such  as  to  cause  minimum  interference  between  different  move- 
ments which   it  may  be  desirable  to  make  simultaneously. 

(d)  In  order  to  keep  die  distance  to  clearance  to  a  minimum,  the  angle  be- 
tween a  ladder  track  and  the  body  tracks  should  be  as  large  as  possible. 

(e)  Ladder  tracks  should  be  spaced  not  less  than  15  ft  center  to  center  from 
any  parallel  track,  and  when  such  parallel  track  is  another  ladder  track,  they  shoidd 
be  spaced  not  less  than  18  ft  center  to  center.  The  requirements  of  governing  bodies 
must  be  observed. 

(f)  Body  tracks  should  be  spaced  not  less  than  14  ft  center  to  center,  and 
when  parallel  to  a  main  track  or  important  running  track,  the  first  body  track  should 
be  spaced  not  less  than  20  ft  center  to  center  from  such  track,  subject  to  state  regu- 
lations on  clearances. 


Manual  Recommendations  97 

2.3  YARD  COMPONENTS 

2.3.1  Receiving  Yard 

(a)  The  number  of  receiving  tracks  should  be  such  that  tliere  will  be  one 
available  whenever  an  arriving  train  offers  to  enter  the  yard. 

(b)  The  length  of  receiving  tracks  should  be  such  that  each  will  acconnnodate 
a  complete  train,  including  assisting  locomotive  where  used.  It  is  desirable  in  some 
yards  to  have  a  few  short  receiving  tracks  located  on  the  side  of  the  yard  near  the 
rurming  track. 

(c)  It  is  desirable  that  the  gradient  of  the  receiving  tracks  be  such  tliat  band 
brakes  will  not  have  to  be  set  to  keep  the  cars  from  moving. 

(d)  Consideration  may  be  given  to  track  indicators  and  remotely  controlled 
switches  at  tlie  entrances  to  the  receiving  yard. 

2.3.2  Classification  Yard 

(a)  The  type  of  yard  which  should  be  adopted  in  any  given  case  depends 
upon  the  volume  and  character  of  traffic  to  be  handled  through  it,  and  the  train 
schedules.  The  decision  should  be  based  on  a  thorough  traffic  analysis  and  economic 
study. 

(  1 )  A  single  flat  yard  is  adapted  for  handling  traffic  where  the  total  number 
of  cars  is  small  and  the  number  of  switching  cuts  per  train  is  also  small. 

(2)  A  double  flat  yard  is  adapted  for  handling  traffic  where  the  total  num- 
ber of  cars  is  large  but  the  number  of  switching  cuts  per  train  is  small. 

(3)  A  gravity  yard  or  a  hump  yard  is  adapted  for  handling  traffic  where 
die  total  number  of  cars  is  large  and  the  number  of  switching  cuts  per 
train  is  also  large — also  in  special  cases  where  the  total  number  of  cars 
is  relatively  small  but  normally  received  in  a  short  period  of  time,  and 
the  number  of  switching  cuts  per  train  is  large. 

(4)  In  special  cases,  due  to  the  location  of  the  yard,  the  character  of  traffic, 
or  the  arrangement  of  schedules,  it  may  be  necessary  to  provide  a  dou- 
ble  flat   yard   or   a   hump   yard,   because   of  limited   time   for   handling. 

(b)  The  number  of  classification  tracks  should  be  such  that  there  will  be  at 
least  one  available  for  each  important  classification. 

(c)  The  lengtli  of  classification  tracks  should  be  such  that  each  will  normally 
hold  all  accumulated  cars  of  the  assigned  classification  until  they  are  to  be  moved 
off  tlie  classification  track  under  normal  operation. 

-  (d)  Where  cars  of  single  classification  accumulate  rapidly  enough  to  permit 
fonvarding  them  in  whole  trains,  it  is  desirable  to  make  up  and  dispatch  trains  from 
the  classification  tracks. 

2.3.3  Departure  Yard 

(a)  Departure  tracks  may  be  located  as  part  of  the  classification  yard  or  in 
a  separate  yard,  depending  upon  the  type  of  trains  dispatched. 

(b)  The  number  of  departure  tracks  should  be  such  that  there  will  be  one 
available   for   assembling   a   departing  train  whenever  necessary. 

(c)  The  length  of  departure  tracks  should  be  such  that  each  will  accommodate 
a  complete  train,  including  assisting  locomotives  where  used. 


98  Bulletin   655 — American  Railway  Engineering  Association 


(d)  The  gradient  of  departure  tracks  should  be  level,  if  possible.  If  adverse 
to  the  forward  movement  of  a  train,  it  should  be  at  least  20  percent  less  than  the 
ruling  gradient  to  be  encountered  by  that  train  during  its  road  trip. 

(e)  Compressed  air  at  suitable  pressure  should  be  piped  along  the  departure 
tracks,  and  sufficient  outlets  should  be  provided  to  permit  the  testing  of  the  air  brake 
equipment  on  die  cars  of  departing  trains. 

(f)  Consideration  should  be  given  to  the  installation  of  shove  indicators  located 
at  clearance  point  of  each  departure  track. 

2.3.4  Repair  Yard 

(a)  The  location  of  the  car  repair  yard  should  be  such  that  the  movement  of 
bad-order  cars  will  be  as  direct  as  practicable,  that  switching  the  repair  yard  will 
not  interfere  with  other  work,  and  that  repaired  cars  may  be  returned  readily  to  the 
classification   or   departure   yard,   as   required. 

(b)  The  capacity  of  the  repair  yard  depends  on  the  number  of  cars  to  be  re- 
paired daily.  Tracks  should  be  as  short  as  possible.  In  computing  capacities,  55  ft 
should  be  allowed  for  each  uncoupled  car. 

(c)  Repair  tracks  should  be  connected  at  both  ends  where  feasible.  The  tracks 
may  be  alternately  spaced  on  narrow  and  wide  centers,  the  narrow  spacing  to  be  not 
less  than  18  ft  and  the  wide  spacing  to  be  such  as  to  accommodate  mechanical 
equipment. 

(d)  A  paved  driveway  should  be  placed  between  the  repair  tracks  with  wide 
centers,  and  paving  is  also  desirable  between  the  tracks  with  the  narrow  centers. 
The  elevation  of  the  driveway  is  usually  tlie  same  as  the  top  of  rail.  Crossings  should 
be   spaced  at  approximately  8-car  intervals. 

(e)  Consideration  should  be  given  to  the  "one-spot"  repair  yard,  where  cars 
are  moved  by  mechanical  means  to  tlie  repair  building,  one  at  a  time,  repaired  and 
moved.  This  system  is  adaptable  to  one  or  more  tracks.  In  computing  the  capacity 
of  the  track  holding  the  cars,  a  minimum  of  50  ft  should  be  allowed  for  each  car. 

2.3.5  Local  Yard 

( Material  being  developed ) . 

2.3.6  Miscellaneous  Yard  Tracks  and  Facilities 

2.3.6.1  General 

All  miscellaneous  tracks  should  be  located  so  that  the  use  of  them  will  cause 
minimum  interference  with  other  operations  in  the  yard,  particularly  road  trains 
entering  and  leaving  the  yard. 

2.3.6.2  Switching  leads 

Switching  leads  should  be  designed  to  give  the  enginemen  working  on  them 
a  clear  view  of  switchmen  passing  signals  along  the  ladder  track.  This  may  not  be 
necessary  where  yard  crews  are  equipped  with  engine-to-ground  radio  communi- 
cation. Multiple  parallel  leads  with  well  placed  crossovers  should  be  provided  where 
traffic  is  heavy. 


Manual  Recommendations  99 


2.3.6.3  Caboose  tracks 

Caboose  tracks  should  be  doul)le-ended  and  located  so  as  to  permit  easy  access 
to  departure  tracks.  In  hump  yards  they  should  be  adjacent  to  the  pull-out  lead 
tracks  or  classification  tracks. 

2.3.6.4  Wrecker  equipment  track 

A  double-ended   track  for  the  storage  of  the  wreck  train  should  be  provided. 

2.3.6.5  Other  tracks 

(a)  Advance  tracks  somewhat  longer  than  the  maximum  train  length,  or  freight 
main  tracks  extending  to  or  beyond  the  outside  of  the  yard,  in  either  or  both  direc- 
tions, should  be  provided  as  required. 

(b)  Thorouglifare  tracks  should  provide  access  to  all  parts  of  the  yard  and 
between  the  locomotive  terminal  and  the  yard. 

(c)  Scale  tracks  should  be  so  located  that  weigh  cars  can  be  weighed  with  mini- 
mum delay  to  >ard  operation. 

(d)  Storage  ti-acks  may  be  required,  particularly  in  hump  yards  where  a  large 
number  of  empty  cars  are  held  for  supplying  local  industry  and  on-line  requirements 
which  may  restrict  operation  of  yard. 

(e)  Tracks  may  be  provided  in  hump  yards  for  by-passing  the  hump  with  certain 
cars,  or  to  provide  an  "escape"  route  from  the  retarder  area  to  tire  receiving  yard 
for  hvmip  engines. 

(f)  Hold  tracks  may  be  required. 

2.3.6.6  Allied  facilities 

Icing,  stock  pens,  LCL  transfer,  rail-truck  handling  and  other  allied  facilities 
should  be  located  so  that  cars  may  be  placed  with  minimum  delay  after  arrival  and 
be   readily  accessible  for  switching  or  placement  in  outbound  trains. 

2.4  HUMP  CLASSIFICATION  YARD  DESIGN 

2.4.1  General 

A  hump  classification  yard  should  be  designed  for  the  volume  and  character 
of  traffic  to  be  handled  and  should  provide  for  continuous  movement  while  humping 
witli  minimum  loss  of  time  between  successive  humping  operations;  also  for  the 
movement  of  cars  by  gravity  from  the  crest  to  their  proper  tracks  in  the  classification 
yard  without   damaging  impacts. 

Tracks  at  the  outbound  end  of  the  classification  yard  should  be  connected  to 
ladders  so  that  classifications  normally  assembled  in  one  train  may  be  assigned  to 
permit  gathering  from  one  ladder,  thus  providing  for  minimum  movement  of  pull- 
down engines.  A  sufficient  number  of  ladders,  with  lead  connections  to  departure 
tracks,  should  be  provided  to  permit  working  at  least  two  pull-down  engines  with 
minimum  interference. 

The  hump  end  of  the  receiving  yard  should  be  located  at  sufficient  distance 
from  the  crest  of  tlie  hump  to  provide,  if  required,  hot  oil  pit,  under-car  inspection 
pit,  connection  to  set-out  track  for  explosives,  and  for  a  connection  to  release  road 
engines.  A  second  track  leading  from  the  receiving  yard  to  the  hump  will  permit 
the  use  of  a  second  hump  locomotive  for  continuous  bumping  operations.  If  trains 


100       Bulletin  655 — American  Railway  Engineering  Association 

from  two  or  more  directions  are  to  be  humped  in  one  direction  over  the  hump,  pro- 
vision should  be  made  so  that  cars  can  be  moved  into  the  end  of  the  receiving  yard 
next  to  the  hump  with  minimum  interference  with  humping  operations. 

It  is  desirable  to  make  up  and  dispatch  trains  from  the  classification  tracks  if 
local  conditions  permit,  and  such  a  method  of  operation  usually  expedites  movements 
through  the  yard  and  reduces  the  expense.  This  requires  that  a  sufficient  number 
of  classification  tracks  be  long  enough  for  each  to  accommodate  a  full-length  out- 
going train,  or  that  lead  tracks  be  provided  at  the  outgoing  end  such  tliat  tlie  com- 
bined length  of  a  classification  track  and  a  lead  track  be  sufficient  for  a  full-length 
train,  thus  avoiding  unnecessary  doubling  over  or  interference  with  hump  operation. 
This  may  involve  a  temporary  reassignment  of  classification  during  tlie  inspection 
and  preparatory  time  of  a  departing  train. 

Departure  tracks  may  be  required  for  making  up  and  dispatching  trains,  de- 
pending on  local  conditions. 

Considerable  reclassification  of  cars  in  a  hump  yard  is  an  indication  of  an 
insufficient  number  of  classification  tracks. 

The  hump  office,  hump  signal  control,  and  other  communication  faciilities  should 
be  located  at  the  crest  of  the  hump  on  the  right  hand  side.  ( It  is  desirable  tliat  cars 
be  uncoupled  from  the  right  hand  side  so  that  the  forward  knuckle  will  be  open, 
as  the  impact  of  normal  coupling  will  often  close  the  rear  knuckle.) 

The  average  gradient  of  the  brack  leading  to  the  crest  of  the  hump  should  be 
such  as  to  permit  shoving  the  longest  and  heaviest  train  at  humping  speeds  con- 
sistent with  available  power. 

Other  desirable  appurtenant  facilities  include  intercommunication  and  paging 
systems  throughout  the  classification  yard  area;  telephone,  teletype  and  pnemnatic 
tube  systems  between  strategic  points,  including  the  general  yard  office,  the  hump 
office  and  retarder  operator  towers,  to  facilitate  handling  of  waybills,  inspection 
lists,  switch  lists,  etc.  In  addition,  a  multiple-channel  radio-telephone  communication 
system  connecting  the  various  offices  with  hump  engines  is  commonplace.  Adequate 
yard  lighting  is  particularly  necessary  in  tlie  retarder  area,  supplemented  as  required 
with  spotlighting  for  freight  car  identification.  Journal  oiling  facilities  and  inspection 
pits,  when  installed,  should  be  located  on  the  approach  side  of  the  hump,  suffi- 
ciently in  advance  of  the  crest,  to  be  in  the  clear  of  the  pin-pulling  operation. 

2.4.2  Retarder 

Many  factors  local  to  each  situation  affect  efficient  operation  of  a  retarder  yard, 
so  that  each  tenninal  must  be  studied  individually  to  produce  a  proper  design. 

The  classffication  tracks  at  the  hump  end  generally  should  be  connected  in 
groups,  with  minimum  distance  from  the  first  switch  of  the  group  to  the  farthest 
clearance  point.  The  leads  to  these  groups  should  be  connected  to  the  hump  lead  by 
sub-leads  in  the  shortest  possible  distance.  Space  should  be  provided  for  retarders 
to  be  located  ahead  of  each  group,  on  the  hump  lead,  and  in  some  cases  on  the  sub- 
leads.  Lap  switches,  short  turnouts,  curved  switch  points,  and  a  relatively  high 
degree  of  curvature,  are  of  desirable  assistance  in  obtaining  the  minimum  distances. 

The  number  and  location  of  retarders  depend  upon  the  number  of  groups  of 
tracks  and  the  type  of  layout.  The  lengtli  of  each  retarder  depends  upon  the  height 
of  hump  and  the  speed  of  operation  needed.  The  height  of  hump  depends  upon 
the  climate,  direction  of  prevailing  wind,  character  of  traffic  (empty  or  loaded  cars), 
and  to  meet  definite  elevation. 


Manual  Recommendations 101 

A  retarder  tower  or  towers  should  be  located  so  that  each  operator  will  have  a 
clear  view  of  cars  under  his  control.  The  towers  should  have  sufficient  height  so  that 
the  operator  can  obser\e  whether  tracks  are  filled  or  have  room  for  more  cars. 

Individual  switches  and  retarders  may  be  operated  by  remote  control  requiring 
one  or  more  tower  locations.  Where  more  than  on  tower  is  provided  tlie  work  should 
be  evenly  apportioned  among  the  operators  so  far  as  practicable.  Push  buttons  or 
programmed  switching  may  be  used  to  select  route  codes  from  which  switches  are 
operated  automaticalh'.  Likewise,  retarders  may  be  operated  by  push-button  selec- 
tion of  speeds  or  through   automatic  control  from  computers. 

For  a  completely  automatic  retarder  classification  yard,  certain  measuring  sec- 
tions with  unifonn  grades  are  required  in  order  to  determine  car-rolling  characteristics 
on  both  tangent  and  curved  track. 

2.4.3  Gradients 

2.4.3.1  Objective 

The  ideal  objective  is  die  design  of  a  series  of  gradients  so  that  each  car  will 
roll  to  and  stop  at  the  far  end  of  the  classification  yard,  or  will  roll  to  coupling  at 
an  acceptable   speed.   The  following  objectives   are   the  minimum   to  be  expected: 

(a)  Deliver  cars  having  a  practical  maximum  rolling  resistance  to  the  clearance 
point  under  adverse  weather  conditions. 

(b)  Deliver  cars  of  most  frequently  occurring  rolling  resistance  to  the  far  end 
of  the  yard. 

(c)  Permit  maximum   humping   rate  and  acceptable  coupling  speeds. 

The  clearance  point  of  a  classification  track  is  the  point  on  that  track  closest  to 
the  hump  which  will  meet  clearance  requirements  as  set  by  the  appropriate  state 
law  or  by  management.  Far  end  of  the  yard  is  the  point  on  any  classification  track 
most  distant  from  the  hump  which  it  is  desired  that  cars  should  reach. 

2.4.3.2  Rolling  resistance 

In  designing  grades  for  moving  railroad  cars  under  gravity,  it  is  necessary  to 
understand  what  is  meant  by  rolling  resistance.  It  is  caused  by  many  external  oppos- 
ing factors,  such  as  car  construction,  track  irregularities,  turnouts,  curves,  speed,  air 
friction,  wind,  temperature,  rain,  snow,  dirt,  etc.  The  measured  rolling  resistance 
for  the  same  car  will  show  a  wide  variation  depending  on  whether  the  car  is  acceler- 
ating or  decelerating  because  of  storing  kinetic  energy  in  the  rotating  wheels  and 
axles  or  in  using  it  up.  In  general,  rolling  resistance  can  be  defined  as  the  summation 
of  all  these  factors  opposing  the  free  rolUng  of  the  car.  Quite  obviously  the  rolling 
resistance  for  any  given  car  will  vary  depending  upon  the  factors  tliat  are  working 
to  oppose  free  rolling. 

For  gradient  design  purposes,  rolling  resistance  is  expressed  in  percent  of  grade 
necessary  to  just  overcome  the  opposing  factors.  For  example,  a  car  is  said  to  be  a 
0.4  percent  resistance  car  if,  when  placed  on  a  0.4  percent  uniform  tangent  grade 
and  given  a  small  initial  velocity,  it  keeps  rolling  without  accelerating  or  decelerating. 
Recent  tests  indicate  that  tlie  maximum  rolling  resistance  of  hard-roUing,  brake- 
free  cars  is  1.4  percent  while  the  minimum  rolling  resistance  of  easy- rolling  cars  is 
0.08  percent.  Strong  head  winds  may  increase  minimum  rolling  resistance  of  empty 
cars  to  2.0  percent.  The  most  frequent  rolling  resistance  is  about  0.20  percent  for 
loaded  cars  and  about  0.35  percent  for  empt>^  cars.  For  predicting  the  behavior  of 
cars  in  any  yard,  relevant  brake-free  data  should  be  used. 


102       Bulletin  655 — American  Railway  Engineering  Association 

2.4.3.3  Theory 

The  speed  of  a  car  rolUng  on  a  grade  can  be  found  at  any  point  by  means  of  the 
expression  A  =  0.0334F*  or  A  =  0.01  SSv*,  where  V  is  the  speed  of  the  car  in  miles  per 
hour,  V  is  the  speed  of  the  car  in  feet  per  second  and  h  is  the  velocity  head  of  the  car 
in  feet  at  the  point  under  consideration  and  is  the  vertical  distance  shown  in  Fig.  1. 


; : /P<?7--4  T/OA/AL 

*  HEAD 


/?OLL/NG    /?£S/5TA/\/C£   LOS3 


-h  =  VSLOC/TY 
/^£AD 


-h^  =£A/£/?Sr 

Meao 


Fig.   1 

The  velocity  head  h  can  be  found  from  the  expression 


h  = : — — — —  he  =  k  he 

Awr~     1 

where, 

A  =  Velocity  head  (translational  head),  in  feet. 

he  =  Energy  head,  in  feet.  This  quantity  is  the  sum  of  the  car's  translational  and  rota- 
tional energy  head  as  shown  in  Fig.  1. 
w  =  Weight  of  car's  wheels  and  axles,  in  pounds. 
W  =  Gross  weight  of  car,  in  pounds, 
r  =  Radius  of  gyration  of  the  car's  wheels  and  axles  with  respect  to  their  axis  of  rota- 
tion, in  inches. 
D  =  Car  wheel  diameter  at  tread,  in  inches. 

1 

I     4^?*     1 
'^     D'     W 

Awr^ 
Table  1  gives  the  value  of  the  constant    r^o    for  eight  33-in-nommal-diameter  car  wheels 

and  four  axles  and  for  eight  36-in-nominal-diameter  car  wheels  and  four  axles.  The 

recommended  values  of  k  for  various  design  assumptions  are  as  follows: 

Mixed  empty    cars    k  =  0.92 

Mixed  loaded  cars    k=.  0.98 

Effect  of  rotating  wheels  and  axles  neglected ^  =  l.OQ 


Manual  Recommendations 


103 


Table  1 


Nominal 

Wheel 
Diameter 

Axle  Size 

_2 
CONSTANT  ^^^  ,  IN  POUNDS 
d2 

Multiple  Wear  Wheels 

One  -  Wear  Wheels              | 

New 

Condemned 

for  Tread 

Wear 

New 

Condemned 

for  Tread 

Wear 

33" 

5-1/2  X  10 
6  X  11 
6-1/2  X  12 

'+,120 
i+,li+0 
1+,170 

2,1+10 
2,1+30 
2,1+60 

3,270 
3,300 
3,330 

2,380 
2,1+00 
2,1+1+0 

36" 

7  X  lii 

U,750 

2,580 

Less   Common 

When  the  cars  for  which  a  gradient  is  designed  are  predominantly  empty  or  pre- 
dominantly loaded,  are  of  the  same  general  type  and  their  rolling  characteristics  are 
reliably  known,  the  appropriate  value  of  k  can  be  obtained  from  Fig.  2a. 

Safe  throwing  of  switches,  retarding  and  weighing  of  cars  make  it  necessary 
for  the  designer  to  predetermine  the  spacing  of  cars  as  diey  roll  from  crest  to  clear- 
ance. This  can  be  done  by  computing  the  time  a  car  takes  to  roll  between  given 
points  using  one  of  the  following  two  methods: 

(a)  The  distance  studied  is  divided  into  a  number  of  increments  depending 
on  the  accuracy  desired.  The  velocity  head  at  the  midpoint  of  each  increment  is 
computed  or  scaled  from  a  scale  profile,  and  by  means  of  the  velocity  head  expres- 
sions or  the  graph  of  Fig.  2,  the  velocity  at  the  midpoint  of  each  increment  is  ob- 


10 

^ 

B 

/ 

/ 

f, 

/ 

/ 

/) 

. 

y 

2 

^ 

y 

n 

^ 

^ 

4  6  8  10  12 

Speed    in   miles   per   hour 
Fig.  2. 


14 


16 


18 


104       Bulletin  655 — American  Railway  Engineering  Association 


/.OO 
.99 
.98 
.97 


.94 


.93 


1.9Z 


^ 


.9/ 


.90 


•'I 

. 

_. 



-- 

—' 

"■ 

— 

J1 

>  1 

•/J 

;*» 

^^ 

^ 

-— 

-^ 

, 

-■ 

_- 

— 

^ 

i."- 

^" 

^^ 

i/fi 

tS- 

.-- 

'' 

'' 

-ol 

»f> 

^^^ 

^ 

^ 

a?' 

> 

t* 

^ 

,^ 

&^ 

rfl^H 

• 

A 

V 

/ 

Si 

fe-^ 

V 

/ 

A 

i^ 

i 

/ 

f 

t- 

f 

/ 

/ 

1 

/ 

s 

/ 

1 

i 

I 

2^H 

n 

^i 

O- 

ty. 

■  "^ 

— 

— 

— 

1 

r<l 

fi.  ■ 

yj 

i/j.*! 

-'*' 

,^ 

^ 

^^ — 

/ 

\ 

i-ii: 

Ijfi 

^ 

i«'>^l 

■Mt 

r,^ 

— 

" 

^^ 

\^- 

i 

{^^ 

|J 

^ 

3^ 

— 

~] 

f 

* 

A 

1^ 

ifji 

,€fi 

f^ 

»' 

4 

r 

J 

(^ 

^. 

.^ 

/ 

.i< 

,v^ 

z' 

/ 

/ 

a\ 

s 

/ 

/ 

f/ 

f 

/ 

/ 

■i^ 

/ 

4 

^ 

/ 

1 

1 

/ 

1 

/ 

1 

k 

t 

1 

1 

f 

/.OO 
.99 

.9si 


.9S  \ 
.94 


^ 


eo         40  60         80         /OO        /20        /40        /60        /80        ^00        ZZO       240       260 

G/k'O.53      WE/GHT    of    CAi9    //V     /,000  LBL 
Fig.  2a 


Manual  Recommendations 105 

tained.  The  length  of  the  increment  is  then  divided  by  the  velocity  corresponding 
to  its  midpoint  to  gi\e  tlie  time  the  car  takes  to  roll  through  that  particulai"  increment. 
When  these  increment  times  are  added  cumulatively,  the  time  a  car  takes  to  roll 
between  the  given  points  is  known. 

(b)  The  time  the  center  of  gravity  of  a  car  takes  to  travel  between  two  points 
"A"  and  "B"  connected  by  a  constant  gradient  can  be  found  from  the  expression 

T  =  0.249  -T—     V  hA+  ha  —  V  Aa      (provided  h^  is  not  equal  to  ha) 

where, 

r  =  Time  to  travel  from  point  "A"  to  point  "B",  in  seconds. 

L  =  Distance  from  point  "A"  to  point  "B  ',  in  feet. 
Ha  =  Velocity  head  at  point  "A",  in  feet. 
Ab=  Velocity  head  at  point  "B",  in  feet. 

When  points  "A"  and  "B"  are  connected  by  a  series  of  gradients,  the  time  T  is  computed 

for  each  gradient.  If  the  car  is  retarded  between  points  "A"  and  "B",  the  time  T  is 

computed  for  each  retardation.  If  Ha  =  ha,  the  speed  of  the  car,  v,  is  constant  and  T 

L 
can  be  found  from  T  :=  — ■ . 

V 

2.4.3.4  Design  factors 

(a)  Hump  height  for  a  classification  track  is  the  difference  in  elevation  between 
the  crest  of  the  hump  and  its  defined  clearance  point. 

(b)  The  track  on  the  approach  side  of  hump  crest  should  have  adequate  plus 
grade  of  sufficient  length  to  assure  easy  separation  of  single  or  multiple  cuts.  The 
vertical  curve  at  tlie  hmnp  should  be  of  minimum  lengtli;  care  should  be  taken  to 
make  certain  that  the  middle-ordinate  for  the  chord  equal  in  length  to  tlie  distance 
between  truck  centers  will  provide  clearance  for  the  lowest  equipment  that  is  ex- 
pected to  be  humped  and  prevent  binding  of  car  knuckles. 

(c)  For  proper  operation  of  a  switch  the  clear  space  between  die  rear  end  of 
one  car  and  the  front  end  of  the  succeeding  car  should  be  not  less  than  the  length 
of  the  track  circuit  protecting  that  switch.  Track  circuits  are  usually  55  to  58  ft 
long.  Cars  with  iimer  axle  centers  greater  than  the  length  of  die  track  circuit  will 
require  special  handling. 

(d)  A  track  scale  of  proper  length  and  location  when  installed  on  the  hmnp 
requires  a  gradient  from  die  crest  and  over  the  scale  wliich  will  provide  sufficient 
time  on  the  scale  alone  for  weighing  of  cars  of  maximum  lengdi,  minimum  lengtii, 
or  a  mixture  of  boUi,  with  due  consideration  of  variations  in  rolling  resistance. 

(e)  The  trend  toward  fidl  automation  in  hump  yards  necessitates  the  provision 
of  tangent  and  curve  rolling  resistance  measuring  sections  to  be  located  between  the 
crest  of  the  hump  and  die  group  retarder.  Recent  yard  installations  have  used  an 
accelerating  grade  not  to  exceed  6.0  percent  for  a  distance  of  70  ft,  more  or  less, 
at  the  crest  of  the  hump  to  assist  in  providing  the  proper  separation  of  cars.  The 
resistance  measuring  section  then  is  provided  on  an  accelerating  grade  of  2.0  percent, 
more  or  less,  to  the  master  retarder,  which  may  also  be  placed  on  a  grade  not  to 
exceed  6.0  percent.  Retarders  may  be  constructed  with  a  \'ertical  curve  at  the  lower 
end  which  facilitates  placing  the  first  switch  beyond  the  leaving  end  of  both  master 
and  group  retarders  as  close  to  the  retarders  as  possible. 


106       Bulletin   655 — American  Railway  Engineering  Assoc i a t i o n 

(f)  The  gradient  from  the  group  (last)  retarder  through  the  classification  tracks 
should  not  produce  unacceptable  acceleration  of  easy-rolling  cars  after  leaving  the 
group  retarder.  This  gradient  may  result  in  deceleration  of  other  cars,  requiring  the 
release  of  such  cars  from  the  group  retarder  at  higher  speeds.  The  gradient  within 
the  switching  area  for  a  group  may  be  made  decelerating  for  all  cars  to  permit  re- 
lease at  a  higher  speed  for  the  purpose  of  clearing  ladders  quicker  and  to  provide 
more  space  beween  cars  for  operating  switches  and  sending  cars  to  adjacent  tracks. 
The  design  of  this  part  of  tlie  hump  profile  is  important  to  obtain  maxinmm  humping 
capacity  with  minimum  damage  to  cars  and  contents. 

(g)  The  gradient  through  the  group  retarder  should  be  sufficient  to  start  most 
cars  should  they  be  stopped  in  the  retarder  and  should  preferably  be  at  least  0.8 
percent. 

(h)  The  gradients  between  the  crest  and  the  track  group  are  regulated  by  the 
hump  height,  tlie  length  and  location  of  retarders,  the  gradient  selected  through  the 
group  retarder,  tlie  gradient  required  for  the  track  scale  and  tlie  desired  speed  of 
cars   leaving  each   of  tlie   retarders,   as  follows: 

( 1 )  There  should  be  a  sufficient  lengtli  of  retarder  in  each  route  to  stop  a 
0.15  percent  resistance  car  of  maximum  gross  weight  in  die  group  re- 
tarder when  released  from  the  crest  at  the  design  humping  speed.  If  a 
pin-puller  retarder  is  used,  its  retarding  efi^ect  should  not  be  included  in 
computing  the  amount  of  retardation  required  between  crest  and 
clearance. 

Note:  The  majority  of  existing  retarder  yards  handling  mixed  traffic  have  been 
designed  for  cars  having  a  maximum  gross  weight  of  100  tons  on  4  axles  with  33-in- 
diameter  wheels.  Cars  of  heavier  gross  weights  and  having  wheels  of  larger  diameter 
shoidd  be  taken  into  consideration  in  providing  adequate  retardation  if  they  are 
likely  to  appear  in  large  numbers  at  any  yard. 

(2)  The  group  retarder  lengdi  should  be  sufficient  to  control  heavy  cars 
having  normal  rolling  resistance  variation  over  the  length  of  track  on 
which  cars  are  classified.  For  example,  a  group  retarder  having  a  velocity 
head  rating  of  5.5  ft  would  be  sufficient  to  control  heavy  cars  having  a 
rolling  resistance  from  0.12  percent  to  0.34  percent  over  a  distance  of 
2500  ft  from  the  leaving  end  of  die  group  retarder. 

(3)  The  master  retarder  should  be  of  sufficient  length  to  insure  that  a  car 
of  maximum  gross  weight  having  a  0.15  percent  resistance  will  move 
through  it,  closed  to  maximum  retardation,  and  leave  it  at  a  speed  which 
will  permit  stopping  in  the  group  retarder  when  the  car  is  uncoupled  at 
the  design  humping  speed.  The  elevation  at  the  lower  end  of  tlie  retarder 
should  be  such  that  the  exit  speed  (usually  8  to  14  niph)  will  permit 
adequate   separation   of  cars   between   die  master   and   group  retarders. 

(i)  Compensation  for  curve  resistance  may  be  made  by  compensating  gradients, 
by  additional  speed,  or  by  a  combination  of  both.  This  factor  is  of  major  importance 
in  the  design  of  gradients  between  the  group  retarder  and  clearance.  Curvature 
through  turnouts  should  be  included  with  other  curvature  when  calculating  curve 
resistance. 


Manual   Recommendations  107 


2.4.3.5  Formulas 

(a)  Hump  gradients 

The  following  formulas  may  be  used  in  designing  hmnp  yard  gradients  from 
the  crest  of  the  hump  to  the  clearance  point  of  a  classification  track. 

H  =  Hump  height  =  S,i?a*  +  S.R^^  -\-AC^  +  Sw2—  (F^)<. 
Hi  ^  H  —  Ha 

Ha='Diop  from  leaving  end  of  group  retarder  to  clearance  =  5a i22«  +  ^C.  + 
Swa  +  a 

Where, 

Subscript  "1"  refers  to  the  section  between  crest  and  leaving  end  of  group  retarder. 

Subscript  "2"  refers  to  the  section  between  leaving  end  of  group  retarder  and  clearance. 

Subscript  "A"  refers  to  hard-rolling  cars. 

Subscript  "e"  refers  to  easy-rolling  cars. 

Quantities  with  no  subscript  refer  to  the  area  between  crest  and  clearance. 

S  =:  Distance  in  feet. 

A  :=  Curvature  in  degrees  of  central  angle. 
(yH)o  =  Humping  velocity  head  in  feet. 

R  =:  Car  rolling  resistance  expressed  decimally. 

C  ^  Curve  resistance  in  feet  of  drop  per  degree  of  central  angle. 
Sw;j  =  Switch  resistance  in  feet  for  switches  beyond  the  group  retarder.  (Resistance  of 
switches  in  Section  "1"  is  not  included  as  a  separate  item  since  /?i»  is  made 
higher  than  R2h  to  include  switch  resistance.) 

a  r=  Difference  in  feet  between  velocity  head  at  clearance  and  velocity  head  at  leav- 
ing end  of  group  retarder  for  easy-rolling  cars.  This  will  be  a  positive  quantity 
if  car  is  accelerating  and  a  negative  quantity  if  car  is  decelerating. 

The  quantities  to  be  substituted  for  the  various  symbols  may  be  determined  from  tests 
at  yards  now  in  operation. 
Having  determined  the  required  vertical  drops  H  and  Hz,  these  drops  should  be  dis- 
tributed in  their  respective  areas  best  to  meet  the  operating  requirements.  There  is  no 
necessity  for  the  curve  compensation  included  in  Ha  to  be  applied  entirely  to  the  curve 
itself  and  part  or  all  of  it  may  be  put  in  advance  of  the  curve. 

If  it  is  desired  to  deliver  hard-rolling  cars  under  advei'se  conditions  to  a  point  farther 
down  in  the  classification  yard  than  just  to  the  clearance  point  as  defined  herein,  these 
same  formulas  will  apply  by  using  such  new  point  for  all  calculations  instead  of  the 
clearance  point. 

It  will  be  noted  that  the  expression  for  H  provides  a  total  drop  which  may  be 

different  for  each  track,  with  the  sides  of  the  yard  lower  than  the  center  because  of  the 

greater  curvature  in  the  outside  tracks.  The  following  are  practical  methods  of  application. 

( 1 )  Grade  the  classification  tracks  so  that  each  track  has  its  proper  amount  of 

curve  compensation.  This  is  done  by  detennining  the  drop  Hi  for  each 

track,  which  will  yield  a  yard  cross  section  made  up  of  a  series  of  steps. 

This  is   not  objectionable,  provided  the  difference  in  elevation  between 

adjacent  tracks  is  not  prohibitive.  This  method  provides  the  most  uniform 

roUing  conditions  beyond  the  last  retarder. 


108       Bulletin  655 — American  Railway  Engineering  Association 

(2)  Grade  all  tracks  of  the  same  group  in  one  plane  using  the  H  coiTCspond- 
ing  to  the  track  having  most  curvature  and  Ht  corresponding  to  the 
track  having  the  least  curvature.  This  method  requires  higher  releasing 
speeds  at  the  group  retarder  for  the  tracks  having  more  curvature. 

(b)  Body  track  gradients 

In  yards  handling  both  loads  and  empties,  gradients  below  the  group  retarder  must 
be  provided  on  the  basis  of  the  easy-rolling  cars  unless  such  cars  are  so  few  that  the 
operation  of  the  yard  will  not  be  slowed  up  appreciably  by  the  necessity  for  bringing 
them  practically  to  a  stop  in  the  last  retarder.  The  acceleration  of  easy-rolling  cars  after 
leaving  the  group  retarder  should  not  be  excessive  so  as  to  permit  higher  releasing  speeds 
at  the  group  retarder. 

The  gradient  of  the  body  tracks  should  be  about  0.08  percent  adjusted  to  meet  local 
conditions,  and  any  curves  that  there  may  be  in  the  body  tracks  should  be  compensated 
at  the  rate  of  0.025  ft  per  deg  of  central  angle  unless  such  curvels  are  so  located  that  there 
would  be  no  objection  to  the  cars  decelerating. 

It  is  advisable  to  have  an  adverse  grade  in  the  body  tracks  just  in  advance  of  where 
they  join  the  ladders  at  the  far  end  of  the  yard,  with  a  rise  of  not  less  than  the 
equivalent  of  4  mph. 

(c)  Retardation 

Retardation  is  obtained  from  the  equation: 

(VH) H,o  =  H^-\-  (VH)o  —  5ai2i,  —  Ai C. 

Where, 

(rfl')H+o  =  Total  retardation  for  hump  and  group  retarder. 

2.4.3.6  Example 

To  illustrate  the  aforementioned  principles,  the  following  example  for  northern  climates 
is  worked  out  analytically  and  the  results  shown  graphically  in  Fig.  3. 

Layout  Data 
Si  =  81Sft,&  =  Sl9ft 
Ai  =  22.65*',  Aj=22.6S» 
Sx«»=  0.24  ft  (0.06  ft  per  turnout) 

Design  Data 

Rik  =  1.4%,  R3%  =  0.9%  94  ft  scale  35  ft  from  crest. 

Ri,  =0.15%,  (F^)o  =  0.21  ft  —  2.5  mph  o  =  — 0.67  ft  corresponding  to  a  ve- 

Ra,  =  0.08%  lodty  of  6.0  mph  at  leaving 

C»  =  0.045,  C.  =  0.025  end  of  group  retarder,  and  a 

A;=  1.0  velocity  of  4.0  mph  at  clear- 
ance. 

Solution 
H  =  SiRtx -f-  S,Rc^  +^Ck  +  SW»—  {VH).  =  (815)  (0.014)  -f  (519)  (0.009) 

-f  (45.3)  (0.045)  -\-  (0.24)  —  (0.21)  =  18.15  ft,  locating  point  "A"  on  the 

profile 
ff,=  5a/2a.-|-  AsC.4-Swi-f  ffl  =(S19)   (0.0008)  -|-  (22.65)    (0.025)  -|-  (0.24) 

—  (0.67)  =  0.55  ft. 
ni=H-H»=  18.15—  0.55=  17.60  ft,  locating  point  "B"  on  the  profile. 


Manual  Recommendations 


109 


vj  ^    (£    <c 

3  rg  "   vo 

OP  O 

1 

i; 

01 

1^ 

8 

r  ' 

u  M    CM    <M 

O    lO  K)    fO 

in  t 

0 

3 

/ 

M 

2' 

1 

0 

X> 

1 

t'E+CI 

|U|Od 

1  ' 

4 

T , 

«3UDJO»J3 

V 

; 

< 

/      (/                 )   / 

1 

I 

il 

/ 

/// 

W, 

■s/ 

• 

1     L    /       V//// 

~i 

tffi 

^ 

E 

/      rl /A       i//'' 

OJ, 

T( 

E 

f  '  f   /// 

// 

U 

•i 

• 
u 

c 

//OO+EI 

i 

-■o               7 

f        A/  /  // 

£0 

2 

■o 

-ft 

1 

SoSk           1 

--\  i 

c 

■ 

j 

f        ////• 

»-o 

oOO        \ 

0 

/     r/f 

^ 

'    o 

H     ^      '" 

•- 

0 

1 

i/     /// 

o 

1    •" 
1    I'D 

'=^^ 

0 

^ 

1    , 

;/         1  // 

o 

"""S 

n   f 

> 
UJ 

1    «.do 

(eSo         1 

1 

.    1 

00 
0 

d 

2 

•  J  w    // 

o 

-      I     'S  SO) 

OL 

0 

(E-i 

n         r 

o 

®\  525 

vg                   -^fo 

-.^ 

a 

//        // 

6 

'^  V'S 

-                 Sr* 

3 

7        / 

71  N  ° 

T              T'^l 

^ 

lA^ 

/        / 

'i 

J   '  1 

0 

'        rf  si+e 

T 

?'«o         /O^ 

f 

7 

.    1 

-0,1     -'>^7/'" 

< 

/    00+/ 

r 
1 

\j         'c\j  /  0 

^  -• 

/ 

/ 

/        (\j  / 

I              lb/ 

u.  s 

/ 

2 

1 
1 

0^ 

j 

/ 

< 

1 

/'        / 

LiJ 

J 

_l 

;'               / 

^ 

_J 

\ 

Q_ 

/              / 

^ 

_ 

'u>  1          0  / 
-/          in/ 

0 

li- 

?' 

d'             m/ 

l; 

0 

'i 

'ri                       'i 

c 

(E. 

q: 

CL 

r* 

S6+C 

r 

1 
1 

y-y/-^ 

a-o 

1 

y 

'Sy             -^ 

0 

n 

E  *■ 

X  «i 

.1  1 

u 

tf^' 

1^ 

''^ 

s 

OE  +  2 

r 

y 

1 
1 

V 

UJ 

d 

1 

o^S^ 

0/. 

r  ■ 

O/V 

• 

7/ 

o 

u 

/  / 

v> 

CNJ 

> 

f  / 

T 

dujnii    (0   |t«J3 

^ 

/ 

1                          00  +  0 

\ 

\ 

Fig.  3. 


110       Bulletin  655 — American  Railway  Engineering  Association 

Point  C  is  located  by  using  a  1.2  percent  gradient  between  B  and  C. 
Point  E  has  been  located  by  the  3.0  percent  gradient  because  of  scale  requirements. 
Point  D  is  established  after  determining  the  lengths  of  the  group  and  bump  re- 
retarders. 

{yH)B.o  =17.60+  0.21  — (815)    (O.OOIS)  —  (22.65)    (0.025)  =  16.02  ft. 

Let  {yH)o  =6.24  ft,  then  (FF)h  =  9.78  ft. 

Let  the  minimum  exit  velocity  be  10  mph  from  the  master  retarder. 

10  mph  =  iM  ft  VH 
Elevation  of  point  D  =  — 9.78— (395)  (O.OOIS) —3.34  +  0.21  =  — 13.50  ft. 

Having  completed  the  ground  profile,  the  resistance  line  of  the  unretarded  0.15  and 
0.08  per  cent  car  is  drawn,  as  shown  in  Fig.  3.  To  obtain  the  resistance  line  of 
the  fully  retarded  0.15  percent  car,  point  D'  is  plotted  3.34  feet  above  point  D, 
equal  to  the  velocity  head  for  10  mph.  Points  C  and  B'  are  then  plotted  to 
yield  grades  parallel  to  those  of  the  resistance  line  of  the  unretarded  car.  The 
total  retardation  required  is  6.24  ft +9.78  ft  =16.02  ft.  If,  however,  the 
retardation  furnished  is  greater  than  16.02  ft,  the  hump  height  may  be  in- 
creased to  utilize  the  full  capacity  furnished  and/or  reduce  the  amount  of 
grading. 

All  rolling-resistance  values  used  in  tlie  example  are  accepted  empirical  averages 
susceptible  of  modification  after  more  research  data  are  obtained.  In  analyzing  an 
existing  yard  or  in  designing  a  new  one,  the  designer  must  recognize  that  the  same 
car  will  have  a  different  apparent  rolling  resistance  in  Section  1  than  it  will  have  in 
Section  2  because  it  is  generally  accelerating  in  Section  1  and  decelerating  in  Sec- 
tion 2.  It  is  noted  that  this  fact  has  been  considered  in  the  example  for  both  hard- 
roUing  cars  and  easy-rolling  cars. 

2.5  FLAT  CLASSIFICATION  YARDS  DESIGN 

2.5.1  General 

(Material  being  developed). 

2.5.2  Gradients 

(Material  being  developed). 

2.5.3  Design  factors 

(Material  being  developed). 


Manual   Recommendations  111 

Part  3 
Freight  Delivery  and  Transfer 


FOREWORD 


This  part  deals  with  the  engineering  aspects  of  freight  (commodities,  merchan- 
dise, etc.)  handling  at  the  points  of  origin  and  delivery,  in  carload  lot  or  less-than- 
carload  lot,  or  in  the  consolidation  of  LCL  freight  from  a  greater  to  a  lesser  number 
of  cars,  or  vice  versa,  or  where  it  is  desired  to  transfer  packaged  freight  from  foreign 
line  cars  into  home  line  cars  for  forwarding  to  destination.  The  facilities  are  essen- 
tially supplementary  units  and  should  be  so  located,  so  designed,  and  so  operated 
in  relation  to  each  other  and  to  the  lines  tributary  to  them,  as  to  give  the  most 
economical   results   for   the   railway   as   a  whole. 


CONTENTS 

Section  Page 

3.1  Freight  Houses 112 

3.2  Team  Yards    115 

3.3  Driveways    115 


112       Bulletin  655 — American  Railway  Engineering  Association 

3.1  FREIGHT  HOUSES 

3.1.1  General 

(a)  Where  tliere  is  a  choice  of  sites,  the  following  factors  should  be  considered 
in  the  selection: 

( 1 )  highway  accessibility, 

(2)  nearness  to  city  pick-up, 

(3)  space  for  future  expansion, 

(4)  proximity   to   existing   switching   service, 

(5)  space  for  a  new  yard  or  proximity  to  existing  supporting  yard, 

(6)  the  possible  inclusion  of  rail-truck  freight  facilities, 

(7)  economies  of  location  near  terminal  yards  even  though  remote  from  city, 
and 

(8)  relative  land  values. 

(b)  The  ultimate  size  of  the  freight  house  should  be  determined  in  advance 
from  consideration  of  the  type  and  average  amount  of  traffic  to  be  handled  through 
it  in  the  first  instance,  the  variation  of  the  peak  from  average  requirements  and  the 
probable  growth  of  requirements  during  the  period  in  which  the  cost  of  the  structure 
can  be  amortized.   The  initial  size  should  be  determined  by  the  immediate  needs. 

(c)  One  factor  in  obtaining  minimum  operating  costs  will  result  when  house 
tracks  are  placed  between  inbound  and  outbound  freight  houses  or  platforms  with 
trucking  connections.  This  factor  applies  to  all  large  facilities.  These  connections  can 
be  in  the  form  of  tunnels,  grade  crossings,  trucking  bridges,  or  by  extending  the 
trucking  platform  around  the  stub  ends  of  tracks. 

(d)  The  factors  of  design  for  a  freight  house,  such  as  car  capacity,  tailboard 
frontage,  floor  area,  width  of  house,  platforms,  conveyors,  bridges,  ramps  and  road- 
ways; and  in  the  case  of  a  two-level  house,  the  capacity  of  elevators  if  used,  should 
be  so  correlated  that  no  one  factor  will  limit  the  capacity  of  the  house. 

(e)  The  design  and  layout  of  the  facilities  should  be  such  as  to  require  the 
minimum  amount  of  labor  to  handle  freight,  and  where  economically  feasible, 
mechanization  should  be  exploited  to  the  maximum. 

( f )  The  economies  of  protecting  the  facility  and  operation  from  adverse  weather 
should  be  considered. 

3.1.2  Dimensions 

(a)  The  size  and  shape  of  the  house  should  take  into  consideration  the 
following: 

( 1 )  the  number  of  house  tracks, 

(2)  the  number  of  cars  to  be  set, 

(3)  total  tailboard  length, 

(4)  platform  space  required, 

(5)  location  of  roof  columns, 

(6)  type  of  operation  to  be  accommodated,  such  as  transfer  of  freight  be- 
tween car  and  car,  between  car  and  truck,  forwarder,  shipping  associa- 
tion, etc.,  and 

(7)  the  type  of  mechanical  freight-handling  equipment  to  be  used,  if  any. 

(b)  Platform  widths  should  be  arrived  at  by  allowing  from  6  to  8  ft  for  each 
conveyor  or  motorized  travel  lane,  with  sufficient  standing  space  outside  of  travel 


Manual   Recommendations 113 

lanes  for  parking  freight  trucks.  Standing  space  10  to  15  ft  wide  adjacent  to  car 
side  and  tliat  much  or  more  at  tailboard  side  is  desirable.  Larger  standing  areas  may 
be  required,  depending  on  the  amount  of  freight  and  length  of  time  it  is  to  be  held 
on  floor. 

(c)  Space  should  be  provided  for  offices,  toilets,  locker  and  lunch  room,  warm 
and  cool  rooms,  cooperage  shop,  storage  for  blocking  and  bulkhead  material,  and 
maintenance  shop  for  platfonn  equipment. 

3.1.3  Two-Level  Structvire 

(a)  Conditions  under  which  a  two-le\el  freight  house  are  required  are  excep- 
tional rather  than  ordinary.  Under  certain  topographical  or  other  physical  conditions, 
such  as  separate  track  and  highway  levels,  the  two-level  house  may  provide  die  only 
economical  solution,  eliminating  teamways,  ramps,  and  avoiding  interference  between 
teaming  and  switching  movements. 

(b)  A  t\\"0-level  freight  house  occupies  less  land  area  per  ton  of  capacity  than 
a  one-level  freight  house,  but  the  cost  of  construction  may  be  greater,  and  the  build- 
ing cannot  be  altered  as  readily  to  meet  changing  conditions. 

(c)  Trucking  costs  in  a  properly  designed  two-level  freight  house  are  less  tlian 
in  a  one-le\el  freight  house  of  the  same  capacity,  but  this  is  somewhat  offset  by 
the  cost  of  elevating  freight.  Although  mechanical  handling  by  towing  conveyors 
has  not  been  applied  to  two-le\el  freight  houses,  that  method  should  be  considered 
in  planning  new  or  in  modernizing  existing  houses. 

(d)  Stowing  costs  may  be  less  in  a  two-level  outbound  freight  house  than  in  a 
one-level  outbound  freight  house  if  the  loading  platform  is  located  in  the  middle 
of  the  outbound  setting  of  cars. 

(e)  A  combination  inbound  and  outbound  freight  house  of  the  two-level  type 
is  more  economical  to  operate  than  separate  inbound  and  outbound  freight  houses 
of  this  type. 

(f)  A  multi-level  inbound  freight  house  may  prove  an  economical  method  of 
securing  additional  storage  space  for  freight. 

3.1.4  Mechanized   Freight-Handling   Facilities 

(a)  Mechanical  equipment  in  a  freight  house  will  usually  include  one  or  a  com- 
bination of  the  following: 

( 1 )  mechanical  trucks, 

(2)  tractors  towing  platfonn  trucks, 

(3)  fork  lifts  and 

(4)  towing  conveyors. 

(b)  Minimum  lengths  of  haul  are  approximated  in  a  freight-house  layout  having 
a  vvddth  roughly  equal  to  its  length.  This  is  an  important  factor  where  hand  trucking 
is  to  be  employed.  It  is  much  less  important  with  tractor  towing  operation,  and  least 
important  with  towing  conveyors. 

(c)  When  volume  justifies  their  use,  con\eyor  chains,  either  overhead  or  en- 
cased in  floor,  towing  four-wheel  platform  trucks  can  normally  handle  90  to  95 
percent  of  the  freight-house  tonnage. 

(d)  Towing  conveyors  are  continuous  and  tow  both  loaded  and  empty  trucks 
usually  spaced  12  to  18  ft  apart.  Tra\el  speeds  up  to  175  ft  per  niin  are  in  use.  The 
conveyor  may  cross  the  freight  house  tracks  by  means  of  a  trucking  bridge  or  by 


114       Bulletin  655 — American  Railway  Engineering  Association 

ramping  down  to  a  grade  crossing  or  timnel  with  ramp  gradients  of  preferably  not 
more  than  6  percent.  With  floor-tyi^e  conveyors  it  is  possible  to  construct  grade 
crossings  so  that  the  chain  will  not  have  to  be  disconnected  to  allow  railroad  cars 
to  cross. 

(e)  Stop  switches  should  be  placed  along  conveyor  routes  at  about  every  otlier 
car  to  control  the  movement  of  the  chain  and  to  be  available  in  case  of  emergency. 

(f)  The  capacity  of  a  conveyor  line  is  the  product  of  the  number  of  loaded 
trucks  going  by  a  given  point  per  hour  and  the  net  load  per  truck.  The  net  load 
used  for  the  design  of  a  particular  house  should  be  determined  by  test  where 
possible. 

(g)  Up  to  the  present  time,  freight  elevators  have  been  the  principal  means 
for  vertical  transportation  of  freight;  however,  with  proper  ramps,  either  tractor- 
trailer  or  towing  conveyor  operations  are  possible  and  eliminate  the  need  for  elevators 
in  multi-level  facilities. 

3.1.5  Appurtenant  Facilities 

In  the  design  and  construction  of  a  freight  house,  the  following  must  be 
considered: 

( 1 )  paging  and  intercommunication  systems, 

(2)  centralized  checking, 

(3)  pneumatic  tube  systems, 

(4)  dock  offices, 

(5)  auxiliary  toilet  facilities, 

(6)  platform  scales, 

(7)  drinking  fountains, 

(8)  fire  protection, 

(9)  facilities   for  fuehng,   storing   and  maintaining  equipment, 

(10)  overhead  crane  for  handling  heavy  loads, 

(11)  facilities  for  transfer  of  tank  car  contents, 

( 12 )  highway   truck  scales  if  trucking   operation   is   involved,   and 

(13)  freight  house  canopies. 

3.1.6  House  Tracks 

(a)  The  capacity  of  inbound  tracks  should  be  such  that  no  more  than  one 
change  in  the  inbound  setting  of  cars  need  be  made  during  a  shift  of  freight-house 
operations,  and  this  change  may  be  made  during  the  lunch  hour. 

(b)  The  capacity  of  the  outbound  tracks  should  be  such  that  the  outbound 
setting  of  cars  may  be  left  undisturbed  during  the  shift  of  freight-house  operations. 

(c)  There  are  operating  advantages  in  having  a  platform  adjacent  to  each 
track;  however,  overall  economies  usually  dictate  trucking  through  one  or  more  cars. 

(d)  Spotting  cars  to  permit  trucking  through  them  requires  approximately  1% 
min  of  switch  engine  time  per  car  to  spot  and  recouple. 

(e)  State  regulations  and  type  of  cars  to  be  set  will  usually  dictate  track- 
centers,  side  clearance,  and  platform  heights.  Wlien  refrigerator  cars  are  to  be  used, 
tracks  preferably  should  be  depressed  and  platform  set  8  ft  from  center  line  of  track. 

3.1.7  Freight  Transfer  Stations 

(a)  A  freight  transfer  station  should  be  provided  where  it  is  desired  to  consoli- 
date LCL  freight  from  a  greater  into  a  lesser  number  of  cars,  or  vice  versa,  or  where 


Manual  Recommendations  115 

it  is  desired  to  transfer  package  freight  from  foreign  line  cars  into  home  line  cars 
for  forwarding  to  destination. 

(b)   The  width  of  transfer  platform  should  be  sufficient  to  accommodate: 

( 1 )  the  parking  of  trucking  equipment  at  track  sides,   and 

(2)  lanes  for  movement  of  the  type  of  equipment  used  in  moving  freight 
from  car  to  car. 

3.2  TEAM  YARDS 

3.2.1  General 

( a )  Location 

The  location  of  a  team  yard  should  be  such  that  it  will  be  convenient  for  use 
by  shippers  and  consignees,  and  also  as  convenient  as  possible  to  a  freight  house, 
so  that  the  receipt  and  shipment  of  freight  may  be  easily  under  control  of  the  freight 
agent's  force. 

(b)  Equipment 

( 1 )  A  crane  for  handling  heavy  freight  should  be  provided  when  required. 

(2)  A  motor  truck  scale,  with  office,  should  be  provided  near  the  main  en- 
trance to  the  team  yard  when  required. 

(c)  Tracks 

( 1 )  Switching  tracks  for  holding  and  working  cars  should  be  provided  in 
the  immediate  vicinity  of  the  team  tracks  and  so  arranged  as  to  facili- 
tate the  switching  of  these  tracks. 

(2)  The  spacing  of  tracks,  where  multiple  team  tracks  are  built,  may  be 
fixed  by  regulatory  bodies,  but  it  is  recommended  that  the  maximum 
distance  between  track  centers  be   13  ft. 

(3)  The  distance  between  track  centers  where  the  driveway  is  located  be- 
tween tracks,  should  be  10  ft  greater  than  the  width  of  the  driveway. 

3.3  DRIVEWAYS  (FREIGHT  HOUSE  AND  TEAM  YARD) 

(a)  Freight  house  and  team  yard  dri\eways  should  be  paved  and  maintained 
in  good  condition. 

(b)  The  widdi  of  a  freight  house  driveway  should  allow  trucks  to  be  backed 
up  to  die  freight  house  at  right  angles  and  leave  additional  room  for  two  thorough- 
fare lanes  for  moving  vehicles. 

(c)  Team-track  driveways  normally  .should  be  of  sufficient  widtli  to  allow  the 
longest  Single  unit  trucks  using  the  driveway  to  stand  at  right  angles  to  the  car, 
with  sufficient  space  remaining  in  front  of  the  truck  to  allow  another  truck  of  maxi- 
mum width  to  pass. 

(d)  Team  yard  driveways  should  be  hard-surfaced  and  liave  at  least  60  ft 
clear  width  between  cars. 

(e)  Driveways  between  buildings  or  between  a  building  and  a  team  track 
should  ha\'e  preferably  a  clear  wadth  of  110  to  150  ft,  with  the  latter  dimension  to 
be  used  if  parking  is  allowed  in  the  center  of  tire  driveway.  Driveways  at  ends  of 
buildings  should  be  not  less  than  60  ft  in  widtii. 

(f)  Inspection  and  hold  yard  two-lane  driveways  may  have  a  clear  width  of 
22  ft  between  cars. 


116       Bulletin  655 — American  Railway  Engineering  Association 

(g)  Stub-ended  driveways  serving  team  tracks  should  be  avoided.  Where  team 
tracks  are  more  than  20  cars  long  (per  single  track),  intermediate  connecting  cross 
drives  should  be  provided.  In  large  team  track  developments  where  exceptionally 
long  tracks  are  provided,  cross  drives  should  be  introduced  so  that  14  cars  per  track 
is  the  maximum  length  between  any  two  drives. 

(h)   For  otlier  information  and   data  see   Chapter  6 — Buildings. 


Manual   Recommendations  117 


Part  4 
Specialized  Freight  Terminals 


FOREWORD 


This  part  deals  with  the  engineering  and  economic  problems  of  location,  design, 
construction  and  operation  of  freight  terminals  for  the  expeditious  handling  of  a 
single  t>'pe  commodity  or  merchandise  as  opposed  to  the  handling  of  several  types 
of  commodity  or  merchandise  as  in  Part  3. 


CONTENTS 

Section  Page 

4.1  Waterfront    118 

4.2  Rail-Truck    119 

4. .3     Automobile  and  Truck  Transport    123 

4.4  Bulk,  Solid    129 

4.5  Bulk,    Liquid    130 

4.6  Merchandise    130 


Bui.  655 


118       Bulletin  655 — American  Railway  Engineering  Association 

4.1  WATERFRONT 

4.1.1  General 

A  water-front  terminal  provides  facilities  for  the  transfer  of  shipments  or  cargoes 
from  ship  or  barge  to  railway  cars  or  trucks,  and  from  railway  cars  or  trucks  to  ship 
or  barge.  The  facilities  consist  of  docks,  wharves,  piers  and  warehouses,  with  loading 
and  unloading  equipment  and  necessary  railway  tracks  and  roadways  for  transfer 
purposes. 

The  waterside  may  be  an  ocean,  lake  or  river,  but  is  usually  a  harbor  on  one 
of  these.  A  dock  is  the  facility  at  which  ships  are  moored.  A  dock  may  be  parallel 
to  the  shore  line,  in  which  case  it  is  called  a  wharf.  If  a  dock  is  built  at  an  angle 
ranging  from  acute  to  right  to  the  shore  line,  where  ships  can  be  moored  on  both 
sides,  tlie  structure  is  called  a  pier.  Whai"ves  and  piers  may  be  open  or  covered, 
depending  on  tlie  protection  needed  for  the  commodity  handled.  Some  piers  are 
used  for  short-term  storage  as  well  as  the  transfer  of  goods. 

4.1.2  Design 

In  designing  a  water-front  terminal  consideration  must  be  given  to  the  type  and 
quantity  of  freight  to  be  handled,  and  to  the  trackage  and  track  arrangement  required 
so  that  proper  switching  to  and  from  docks  can  be  provided.  The  facilities  on  land 
are  provided  to  economically  load  and  unload  commodities.  Docks  should  also  be 
equipped  with  necessary  conveyors,  pipelines,  car  dmnpers,  cranes,  hoppers  and  any 
other  facility  necessary  to  handle  special  commodities. 

4.1.3  Equipment 

Large  structural  cranes  may  be  built  over  docks  to  extend  over  ships  to  facilitate 
the  handling  of  loads.  Conveyor  systems  may  be  built  to  move  commodities  in  bulk 
or  in  units.  Some  important  docks  specialize  in  handling  one  commodity,  such  as 
ores,  coal,  grain,  fruit  (bananas),  automobiles  or  equipment,  or  to  transfer  railway 
cars  and  certain  merchandise. 

4.1.4  Track  Facilities 

(a)  Wliarves  may  be  served  by  tracks  parallel  to  the  wharf.  Occasionally 
wharves  are  equipped  with  tracks  constructed  adjacent  to  the  water's  edge,  and 
goods  are  handled  directly  between  the  ship  and  railway  cars. 

(b)  Piers  are  usually  provided  with  tracks  running  down  their  center  or  along 
tlie  edge.  Transfer  bridges  are  used  for  handling  railway  cars  to  and  from  ships, 
car  floats  or  ferries. 

(c)  Various  yards  for  railway  cars  are  a  part  of  a  water-front  terminal.  A  storage 
yard  is  usually  necessary  for  cars  held  for  loading  or  unloading  and  to  accumulate 
special  cars  for  a  particular  ship.  A  classification  yard,  with  or  without  receiving 
and  departure  yards,  storage  and  car  repair  yard,  may  be  provided,  depending  upon 
the  volume  of  traffic  handled. 

4.1.5  Storage 

Adequate  storage  space — ground  pier  or  covered  warehouse — ^is  essential  for 
commodities  awaiting  shipment.  The  arrangement  of  these  yards  and  storage  space 
is  important  so  there  will  be  the  minimum  of  interference  in  handling  cars  to  and 
from  the  yards  and  unloading  spots. 


Manual  Recommendations 119 


4.2  RAIL-TRUCK 

4.2.1  Types  of  Facilities 

(a)  End  loading  of  railroad  cars  is  accomplished  by  backing  the  tractor-trailer 
combination  on  a  flat  car  or  string  of  cars  from  a  platform  or  ramp  constructed  to 
car-floor  height. 

(b)  Side  loading  can  be  accomplished  by  the  use  of  a  fork  lift  truck,  a  platform 
at  car-floor  height,  or  by  the  use  of  special  equipment  which  permits  separation  of 
the  trailer  body  from  its  wheels  and  transfer  of  the  body  to  a  flat  car. 

(c)  Overhead  loading  can  be  accomplished  by  the  use  of  a  traveling,  overhead 
rail-mounted  or  tire-mounted  crane.  Either  the  entire  trailer  or  the  trailer  body 
without  wheels  can  be  handled  from  the  roadway  adjacent  to  the  track. 

The  three  types  of  facilities  described  above  are  illustrated  by  Figs.  4  to  6,  incl. 

4.2.2  Design  factors 

Detennining  factors  relative  to  the  location  of  the  facility  depend  upon  the 
potential  volume  of  traffic,  its  origin  and  destination  within  the  service  area,  the 
convenience  of  highway  access  and  the  necessity  for  economical  and  expeditious 
movement  of  railroad  cars.  As  many  as  8  (90-ft)  cars  in  a  string  can  be  efficiently 
used  in  end  loading  operations.  A  trailer  parking  area  of  at  least  one  and  one-half 
times  the  ti-ailer  capacity  of  the  loading  tracks  should  be  planned.  Many  installations 
have  a  parking  area  with  a  capacity  two  or  three  times   the  track  capacities. 

There  may  be  advantages  to  have  the  track  area  depressed  in  relation  to  the 
parking  area,  driveways  and  ramps.  The  tracks  used  to  spot  cars  for  loading  should 
be  on  tangent.  The  curvature  of  approach  tracks  should  be  limited  to  400-ft  radius 
(14  deg  20  min). 

The  larger  operations  will  require  an  office  and  locker  room  at  the  site.  A  tiuck 
scale  may  be  required.  Fencing  may  be  worthwhile  to  assist  policing.  Drainage  of 
track,  driveway  and  parking  area  must  be  considered.  Communication  facilities  within 
and  beyond  the  operation  area  should  be  provided  for  efficiency.  Facilities  for  repair 
of  truck  and  tie-down  equipment  may  be  required. 

4.2.3  Paving  requirements 

The  type  of  paving  or  surfacing  of  parking  area,  driveways  and  ramps  should 
be  selected  to  suit  the  intensity  of  use  anticipated.  The  ramps  may  be  of  wood, 
concrete  or  earth-filled  crib  construction.  Platform  walkways  adjacent  to  tracks 
should  be  considered  to  provide  easy  movement  of  men  from  one  car  to  another. 
Portable  ramps  can  be  used  to  eliminate  need  to  turn  cars.  Traffic  lines  will  facilitate 
parking  and  handling  of  equipment. 

4.2.4  Electrical  facilities 

Lighting  and  power  outlets  in  the  track  area  should  be  furnished  to  facilitate 
tie-down  operations.  Parking  areas  should  be  liglited  if  there  is  considerable  night 
operation. 


120       Bulletin  655 — American  Railway  Engineering  Association 


Manual  Recommendations 


121 


122       Bulletin  655 — American  Railway  Engineering  Association 


Manual   Recommendations 123 

4.3  AUTOMOBILE  AND  TRUCK  TRANSPORT 

4.3.1  Automobile  Transport 

4.3.1.1  General 

The  loading  and  unloading  of  finished  automobiles  requires  equipment  and 
plant  that  contribute  to  the  overall  expeditious  distribution  from  assembly  plants  to 
local  dealers.  Automobile  companies  place  a  premium  upon  total  time  in  transit  and 
do  consider  all  aspects  of  equipment  utilization,  interest  charges  and  delivered  auto 
condition. 

Loading  is  usually  accomplished  at  an  assembly  plant,  on  automobile  company 
property,  by  tlie  automobile  company  or  its  contractor.  The  actual  facilities  utilized 
are  similar  in  nature  to  the  unloading  facilities;  however,  there  are  exceptions  which 
must  be  given  consideration  on  an  individual  basis.  Exceptions  can  vary  from  loading 
inside  tlie  plant  witli  multi-level  cars  handled  by  a  transfer  table  to  and  from  a 
support  yard  to  simply  driving  the  finished  vehicle  to  a  more  conventional  loading 
facility  located  at  some  convenient  point  other  than  the  plant  itself. 

Unloading,  on  the  otlier  hand,  is  usually  accomplished  by  the  rail  carrier  or  its 
contractor,  on  railroad  company  property,  utilizing  facilities  provided  by  the  railroad 
company.  The  contractor  engaged  by  tlie  railroad  company  to  actually  perform  the 
unloading  task  will  more  than  likely  be  the  same  organization  engaged  by  an  indi- 
vidual automobile  company  to  prepare  and  deliver  units  via  highway  to  dealers. 
It  is,  therefore,  suggested  that  close  consultation  between  all  entities  involved  in  the 
automobile  distribution  process  be  maintained  during  the  design  phase  in  order  to 
assure  an  efficient  and  usable  facility. 

Examination  of  facilities  now  in  existence  discloses  a  wide  variety  of  sizes, 
shapes,  equipment,  trackage,  etc.,  as  dictated  by  such  factors  as  availability  of  real 
estate,  proximity  to  highway  networks  and  volumes  of  vehicles  handled.  A  typical 
flow  diagram  of  an  unloading  area  is  shown  as  Fig.  7.  Certain  factors  are  germane 
to  most  all  auto  unloading  or  loading  facilities.  They  are  enumerated  below  from 
the  unloading  viewpoint;  however,  tlie  factors  apply  equally  as  well  to  loading  areas, 
given  appropriate  modification  for  volume. 

4.3.1.2  Location 

Location  of  tlie  unloading  area  should  be  selected  for  its  proximity  to  dealers 
in  the  area  to  be  distributed  to  in  order  to  reduce  highway  mileage  to  the  minimum. 
It  should,  be  located  with  respect  to  the  railroads  main  trackage  so  as  to  minimize 
switching,  spotting  and  pulling  delays.  Consideration  should  also  be  given  to  tlie 
potential  of  vandalism  so  as  to  avoid  missile  damage  and  theft. 

4.3.1.3  Size 

The  size  of  the  unloading  facility,  its  trackage,  ramping  and  vehicle  storage 
areas,  should  be  large  enough  to  handle  the  maximum  expected  load  under  the  pro- 
posed operating  conditions.  Some  of  the  conditions  to  be  considered  are:  the  average 
work  week,  type  and  quantity  of  vehicles  handled  and  the  number  of  agencies  using 
the  same  facilities.  The  auto  production  and  distribution  process  by  its  very  nature 
requires  a  considerable  degree  of  advance  planning  including  volume  predictions. 
All  of  the  auto  maufacturers  can  and  do  make  rather  good  \  olume  predictions  which 
can  be  utilized  for  planning  purposes. 


124       Bulletin  655 — American  Railway  Engineering  Association 


STREET 


/^ 

J.     ^ 

,     "5 

UJ   cn 

': 

o   q 

;t 

^ 

> 

Manual   Recommendations  125 


4.3.1.4  Buildings 

Office  space,  washrooms  and  locker  facilities  should  be  adequate  to  provide  for 
future  needs  of  the  operation.  Communication  facilities  required  should  be  provided 
for.  Local  conditions  may  require  space  for  maintenance  of  highway  tractors  and 
predelivery  preparation  of  autos,  including  washing  and  undercoating. 

4.3.1.5  Surfaces — operating  and  storage  areas 

It  is  recommended  that  ^ehicular  operating  and  storage  areas  be  paved  and 
as  flat  as  possible,  limiting  loading  and  unloading  angles  to  eliminate  bumper  dam- 
age. The  area  should  be  graded  to  provide  proper  drainage. 

Parking  spaces  should  be  clearly  marked  in  an  arrangement  with  ample  center 
distances,  thereby  maximizing  turning  radii   and  minimizing  door  contact. 

4.3.1.6  Security 

The  entire  area  should  be  fenced  and  of  such  a  nature  as  to  discourage  unau- 
thorized entr\-  and  tlieft.  A  common  solution  is  barbed-wire-topped  chain  link  fenc- 
ing. Gating  and  fencing  should  be  so  arranged  as  to  segregate  new  car  storage  from 
employee  parking.  To  minimize  the  possibility  of  tlieft,  one  auto  manufacturer  rec- 
ommends that  new  vehicles  can  only  be  driven  out  of  the  storage  area  over  a  haul- 
away dock.  Provision  for  checking  employees  and  visitors  in  and  out  should  be  made. 
Locking  devices  on  all  gates  are  recommended. 

4.3.1.7  Lighting 

Lights  should  be  proxided  for  tlie  entire  area  of  sufficient  intensity  to  be  ade- 
quate for  loading,  unloading,  inspection  and/or  security. 

4.3.1.8  Multi-level  unloading  area 

This  area  should  be  placed  as  close  as  possible  to  the  center  of  operations  in 
order  to  minimize  travel  distances. 

(a)  Unloading  Tracks:  The  number  and  length  of  these  tracks  will  be  de- 
pendent upon  tlie  volume  of  rail  cars  handled  and  the  availability  of 
switching  ser\  ice.  Rail  cars  and  tlience  the  autos  on  them  may  not 
always  be  oriented  in  the  same  direction,  thereby  making  it  desirable  to 
provide  for  unloading  multi-le\els  from  either  end.  Since  the  backing  of 
automobiles  from  rail  cars  is  not  permitted,  the  alternative  to  providing 
facilities  to  unload  from  either  end  of  the  rail  car  is  to  turn  cars  on  a 
wye  or  turntable  prior  to  unloading.  This  may  not  be  desirable  from  an 
operating  or  time  standpoint.  Track  centers  and  surfacing  between  tracks 
should  be  sufficient  to  allow  passage  of  service  vehicles  for  the  purpose 
of  a]le\iating  tlie  problems  of  flat  tires,  missing  wheels,  dead  batteries, 
lack  of  gasoline   and  others   that  may  occur  with  the   automobiles. 

(b)  Unloading  Equipment:  Unloading  equipment  should  allow  quick  drive- 
off  of  automobiles.  Where  economically  justifiable,  the  ramp  should  be 
power  controlled  vertically  for  adjustment  to  deck  levels  as  well  as  hori- 
zontally to  adjoining  tracks.  Manufacturers  should  be  consulted  regarding 
maximum  ramp  angle  permitted.  At  points  where  it  is  considered  advis- 
able to  provide  unloading  in  either  direction,  one  of  two  methods,  otlier 
tlian  simply  turning  the  car,  can  be  employed.  Ramps  may  be  mounted 
on  flanged  wheels  and  rails  perpendicular  to  the  unloading  tracks.  This 
method  requires   a  certain  amount  of  switching  to  orient  the  rail  cars 


126       Bulletin  655 — American  Railway  Engineering  Association 

with  the  appropriate  ramp.  The  second  method  is  to  mount  the  ramps 
on  rubber  tires,  pave  the  unloading  track  area,  and  move  the  ramp  to  the 
cars   to  be  unloaded. 

4.3.1.9  Haul-away  loading  area 

The  provision  of  a  loading  dock  where  highway  trailers  can  be  spotted  for 
loading  is  recommended  in  order  to  reduce  loading  angle  and  decrease  loading  time. 
The  preference  of  the  specific  contractor  should  be  determined  to  assure  compatabil- 
ity  with  his  equipment,  the  dimensions  and  extent  of,  or  even  the  need  for,  this 
feature. 

4.3.2  Vertically  Loaded  Automobiles 

4.3.2.1  General 

Factors  regarding  location,  size,  buildings,  surfacing,  security  and  lighting 
enumerated  for  automobiles  on  conventional  tri-Ievels  apply  equally  as  well  to  ver- 
tically loaded  small  autos.  The  rail  car  itself  differs  from  multi-level  rail  equipment 
in  that  automobiles  are  loaded  vertically.  Five  doors,  holding  tliree  autos  each,  on 
either  side  of  the  car,  actually  serve  the  combined  functions  of  loading,  unloading 
and  securement  devices.  The  car  design  requires  special  consideration,  as  explained 
below,  for  anyone  engaged  in  planning  an  unloading  area  for  such  cars. 

4.3.2.2  Unloading  track  and  area 

The  number  of  tracks  and  their  lengths  will  be  dependent  upon  the  predicted 
volume  of  rail  cars.  A  paved  area  60  ft  wide  is  recommended  on  both  sides  of  the 
car  to  provide  adequate  unloading  and  maneuvering  space.  See  Fig.  8  for  dimensions. 

4.3.2.3  Unloading  equipment 

The  car  doors  themselves  serve  as  ramps  for  loading  and  unloading,  therefore, 
no  special  fixed  equipment  will  be  required.  A  mobile  machine  having  the  reach  and 
capacity  to  open  and  close  the  doors,  must  be  available. 

4.3.3  Truck  Transport 

4.3.3.1  General 

Factors  regarding  location,  size,  buildings,  surfacing,  security  and  lighting 
enumerated  above  for  automobiles  apply  equally  as  well  to  trucks.  The  rail  equip- 
ment and  the  placement  of  the  trucks  on  the  rail  equipment  differs.  Trucks  with 
cabs,  but  without  bodies,  are  commonly  shipped  in  "saddleback"  fashion  on  a 
specially  equipped  flat  car.  Thus,  tlie  use  of  a  crane  is  required  for  loading  and 
unloading.  While  the  loading  may  be  done  at  a  plant  site  exclusively  devoted  to 
trucks,  the  unloading  operation  can  conveniently  be  incorporated  into  and  made  a 
part  of  a  typical  automobile  unloading  facility. 

4.3.3.2  Unloading  track 

Truck  shipping  volumes  being  considerably  less  than  autos,  a  single  track  set 
apart  from,  but  adjacent  to,  auto  facilities  should  suffice.  Volume  and  economic  con- 
siderations will  dictate  the  degree  of  separation  from,  and/or  incorporation  within, 
auto  facilities. 

4.3.3.3  Unloading  facilities 

Trucks  loaded  in  "saddelback"  fashion  must  be  removed  from  the  truck  they 
have  been  set  upon  and  secured  to  for  transport  to  a  level  position  on  the  car  deck 


Manual  Recommendations 


127 


!?C)-0"- 


c,0'C;" 


I  I 
I  I 


QCJ))J    Ain-os 


Fig.  8 — ^Typical  unloading  area  for  autos  loaded  vertically. 


128       Bulletin  655 — American  Railway  Engineering  Association 


i    A-FRAME    RAI L     

■"   1  00    LB.     OR    LESS 


CI 


SWITLH    TIE        1  3  '  -6' 


que 

4_      CATENARY    POLE 


CROSS    TIE 


k  '  -0 


©      r 


E 


1 


2  '  -0 


ll 


2  '  -0 


r 



3 


CATENARY  POLES 
MAY  BE  PLACED 
ON  EITHER  SIDE. 


"J 


]  n 


—J 


[I 


5'-9  1/i 


^  TRACK 
SYM.  ABT.  4 


NOTE:   A-FRAME  CRANE  ELECTRICALLY 
PROPELLED.   HAS  DOUBLE 
FLANGED  WHEELS. 
TOTAL  WIDTH  15'0. 
SPACE  REQU I  RED  FOR  THIS 
FAC ILITY,  17  '3. 


Fig.  9 — Typical  layout  for  "A"  frame  truck  unloading. 


Manual   Recommendations 129 

before  being  started  and  driven  from  the  car.  The  job  can  be  accomplished  by  a 
mobile  crane  of  sufficient  capacity  operated  adjacent  to  the  rail  car  where  volume 
is  fight  and  the  need  only  occasional.  Where  volumes  require  a  greater  degree  of 
specialization,  it  is  recommended  that  an  "A"  frame  crane,  track  mounted  and 
electrically  operated  with  running  rails  located  outside  of  regular  track  rails,  be 
provided.  The  "A"  frame  straddles  the  car  to  be  unloaded  and  can  be  positioned 
to  handle  any  car  spotted  within  its  reach.  Fig.  9  details  a  tie  layout  to  accommo- 
date the  "A"  frame.  Access  to  the  unloading  ti-ack  for  pre-starting  service  should 
be  given  consideration.   Air  supply  sufficient  to   release  truck  brakes  is  a  necessity. 

4.4  BULK-SOLID 
4.4.1  Grain  Elevators 

4.4.1.1  General 

( a )  Track  facilities  to  serve  large  grain  elevators  involve  special  yard  design.  Co- 
operation between  the  elevator  engineer  and  the  railway  engineer  is  essential  to 
the  development  of  a  satisfactory  plan. 

(b)  The  location  of  elevator  site,  type  and  capacity  of  elevator,  topography  and 
local  conditions  will  influence  the  arrangement  of  tracks. 

(c)  When  selecting  the  site  consideration  should  be  given  to  property  values, 
possible  arrangement  of  connections  to  plant  tracks,  local  railway  operating  condi- 
tions, and  future  expansion  of  elevator  plant  and  of  existing  railway  facilities. 

(d)  Proposed  method  of  railway  operation  should  be  established  and  approved 
by  the  elevator  operating  company  and  operating  officials  of  the  railway. 

4.4.1.2  Types 

There  are  three  general  types  of  grain  elevators,  viz.,  (1)  rail  to  rail,  (2)  rail 
to  water,  and  (3)  water  to  rail.  Specific  plants  may  be  combinations  of  these  types. 

4.4.1.3  Tracks 

4.4.1.3.1  Loading  and  unloading 

(a)  The  number  and  capacity  of  unloading  tracks  will  depend  upon  the  type, 
arrangement  and  capacity  of  elevator  unloading  facilities,  but  may  be  limited  in 
some  cases  by  the  space  available. 

(b)  The  car  capacity  of  the  tracks  above  and  below  the  loading  or  unloading 
facilities  should  be  the  same. 

(c)  Where  the  car  capacity  of  the  unloading  tracks  on  each  side  of  the  unload- 
ing facilities  is  equal  to  the  nonnal  daily  unloading  capacity  of  tlie  elevator  plant 
during  the  grain  handfing  season,  and  where  the  car  capacity  of  the  loading  tracks 
on  each  side  of  the  loading  facilities  is  equal  to  the  normal  daily  business  handled, 
the  plant  switching  will  be  reduced  to  a  minimum. 

(d)  Double-ended  tracks  will  permit  the  continuous  movement  of  cars  in  one 
direction  and  facifitate  switching. 

(e)  Spur  unloading  tracks  may  necessitate  switching  cars  through  unloading 
shed  and  over  unloading  facilities,  requiring  the  use  of  idler  cars.  Locomotives  should 
not  be  permitted  to  enter  the  unloading  shed. 


130       B u lletin  655 — American  Railway  Engineering  Association 

(f)  Adverse  gradients  and  curvature  in  tracks  will  limit  the  capacity  of  car  haul 
and  should  be  avoided.  An  assisting  gradient  to  and  from  the  loading  and  unloading 
facilities  should  be  provided.  A  short  runoff  gradient  below  the  unloading  facilities 
will  speed  up  die  movement  of  empty  cars. 

(g)  Where  car  imloaders  are  used,  the  track  arrangement  should  provide  for 
the  relative  increased  capacity  of  this  device.  A  small  plant  locomotive  or  other 
special  car  handhng  equipment  should  be  considered  in  connection  with  car  un- 
loaders.  Flexibility  of  track  layout  in  the  vicinity  of  car  unloader,  to  facilitate  the 
operation  of  plant  locomotive,  should  be  given  special  attention. 

( h )  Loading  tracks  may  be  located  on  the  same  or  opposite  side  of  "workhouse" 
from  unloading  tracks. 

(i)  Certain  unloading  ti-acks  may  be  used  for  loading  or  to  augment  the 
capacity  of  the  loading  tracks. 

( j )  Some  of  the  auxiliary  buildings,  such  as  storeroom  and  dust  house,  may  be 
served  by  the  loading  tracks. 

4.4.1.3.2  Other  tracks 

(a)  A  running  track,  located  outside  of  unloading  shed,  should  be  provided 
where  double  ended  tracks  are  installed. 

(b)  A  separate  track  should  be  provided  to  serve  the  power  house. 
4.4.1.4  Storage  yard 

(a)  The  use  of  a  separate  storage  yard  will  require  additional  handling  of  cars; 
therefore  careful  consideration  should  be  given  to  the  advisability  of  such  a  yard. 

(b)  Where  the  elevator  is  located  near  an  existing  yard  and  sufficient  capacity 
is  available,  or  can  be  economically  provided,  a  separate  storage  yard  may  not  be 
required. 

(c)  A  separate  storage  yard  may  be  justified  where  it  can  be  used  to  augment 
the  existing  yard  during  seasonal  increases  in  business,  or  where  the  elevator  is 
located  some  distance  from  the  main  or  an  auxiliary  yard. 

(d)  The  capacity  of  either  the  loading  or  unloading  tracks,  or  both,  may  in- 
fluence the  necessity  for  a  separate  storage  yard,  as  well  as  the  capacity  of  such  a 
yard. 

(e)  Facilities  for  inspection  of  cars  and  lading  should  be  provided. 

4.4.2  Handling  systems   for   granular  material 

(To  be  developed). 

4.5  BULK-LIQUID 

(To  be  developed). 

4.6  MERCHANDISE  TERMINAL 

4.6.1  Produce  terminals 
4.6.1.1  General 

(a)  Produce  terminals  are  designed  for  expeditious  and  economical  distribution 
of  fruits,  vegetables,  and  sometimes  dairy  products,  eggs  and  poultry,  meat  and  meat 
products,  frozen  foods  and  sea  foods,  and  dry  groceries. 

(b)  Terminals  should  be  located  and  designed  to  handle  peak  business. 


Manual  Recommendations 


131 


(c)  A  union  terminal  serving  the  entire  trade  of  a  community  is  preferable. 

(d)  The  location  must  be  convenient  for  dealers,  with  easy  access  over  wide 
and  well  improved  highways  and  easy  gradients.  It  should  have  convenient  railway 
connections.   A   location   adjoining   a   railway   terminal   yard   is   advantageous. 

4.6.1.2  Functions  of  railway  and  marketing  facilities 

A  produce  terminal  should  be  considered  to  include  (a)  railway  facilities  and 
(b)    wholesale   marketing  facilities. 

(a)  Railway  facilities  include  the  primary  units  for  handling  carload  shipments 
prior  to  distribution  or  reconsigning.  Any  or  all  of  the  following  facilities  may  be 
required: 


1.  Receiving  and  delivery  yard. 

2.  Hold    and    inspection    yard;    with    or 

without    supplemental    classification 
tracks. 

3.  Team  yard. 

4.  Buildings    for    sorting,    reconditioning 

and  transferring  of  lading. 

5.  Administration  building. 

6.  Motor  truck  scales. 

7.  Buildings  for  coopering  and  supplies. 

8.  Buildings  for  heaters  and  supplies. 


9.  Rest  rooms  for  yard  crews,  stevedores, 
truck  operators  and  laborers. 

10.  Incinerator. 

11.  Communication  facilities. 

12.  Yard  lighting. 

13.  Icing  facilities. 

14.  A  track  system  for  serving  the  yards. 

15.  A  system  of  driveways  for  movements 

to  and  from  the  team  yard  and  the 
hold  and  inspection  yard. 

16.  Fire  protection  facilities. 


(b)  Wholesale  marketing  facilities  include  units  for  the  sale  and  distribution  of 
produce  and  may  be  situated  adjacent  to  or  within  easy  access  of  the  railway  facilities. 
In  either  case  certain  units  should  be  served  directly  by  railway  tracks.  Any  or  all  of  the 
following  units  may  be  required: 


1.  Buildings  divided  into  separate  stores. 

2.  Buildings  for  display  and  private  sales. 

3.  Buildings  for  display  and  auction. 

4.  Auction  rooms. 

5.  Offices,  restaurants,  etc. 

6.  Cold  storage  warehouse. 

7.  Bulk  delivery  platforms. 

8.  Ripening  facilities. 

9.  Reconditioning  facilities. 

10.  Motor  truck  and  other  scales. 

4.6.1.3  Layouts 


11.  Incinerator. 

12.  Communication  facilities. 

13.  Fire  protection  facilities. 

14.  Farmers'  market. 

15.  A    railway    track    system    serving    the 

buildings. 

16.  Driveways  serving  the  buildings. 

17.  Separate  buildings  for  individual  large 

firms. 

18.  Adequate  parking  areas. 


4.6.1.3.1  Track 

(a)  The  track  layout  should  be  as  compact  and  flexible  as  possible,  and  exten- 
sive enough  to  take  care  of  traffic  without  delay.  It  is  governed  by  the  number  of 
cars  handled  at  peak  periods,  the  different  kinds  of  produce  received,  and  tlie  average 
standing  time  until  cars  are  released. 

(b)  A  receiving  and  delivery  yard  is  sometimes  desirable  for  receiving  transfers 
from  various  roads  and  for  assembling  outbound  empties  and  reconsigned  cars. 

(c)  A  hold  and  inspection  yard  is  sometimes  provided.  This  yard  should  have 
two-lane  driveways  between  pairs  of  tracks  to  permit  access  for  inspection  and  icing 
from  trucks.  Inspection  platforms  are  sometimes  provided.  It  may  be  a  separate  yard 
or  combined  with  the  receiving  and  delivery  yard  or  with  a  small  classification  yard. 


132       Bulletin  655 — American  Railway  Engineering  Association 

(d)  Team  yards  should  have  ample  standing  capacity.  Extremely  long  tracks 
should  be  avoided. 

(e)  Track  centers  should  be  not  less  than  13  ft. 

4.6.1.3.2  Buildings 

(a)  Ample  floor  space  should  be  provided  for  mechanical  handling  from  cars  to 
warehouse  floor,  display  of  produce  and  assembly  of  various  lots  for  delivery  to  trucks. 

( b )  The  column  spacing  should  be  given  careful  study  and  be  as  wide  as  possi- 
ble, consistent  with  economic  design. 

(c)  The  back-up  space  for  trucks  should  be  as  liberal  as  possible. 

4.6.1.3.3  Platforms 

(a)  Platforms  used  for  inspection  or  jointly  for  inspection  and  handling  of 
produce  should  be  not  less  than  12  ft  in  width,  3  ft  5  in  above  top  of  rail  when  the 
center  line  of  tangent  track  is  5  ft  9  in  from  the  platform,  or  4  ft  7  in  above  top  of 
rail  when  tlie  center  line  of  tangent  track  is  8  ft  0  in  from  the  platform.  Platforms 
should  be  covered,  and  light  and  water  should  be  provided.  Roof  supports  should  be 
located  to  minimize  interference  with  handling  crates.  Space  for  crate  storage  and 
repairs  is  usually  required. 

(b)  House  platfoniis,  when  served  by  both  highway  vehicles  and  railway  cars, 
should  be  4  ft  4  in  above  top  of  rail  and  8  ft  from  the  center  line  of  tangent  track. 

(c)  Clearances  must  comply  with  state  regulations. 

4.6.1.4  Facilities 

4.6.1.4.1  Garbage  and  refuse  disposal 

Cars  should  be  thoroughly  cleaned  after  unloading,  and  all  refuse  and  garbage 
removed  from  platforms,  buildings,  etc.  Cleaning  of  cars  may  be  accomplished  on  a 
one-spot  basis  with  mechanized  devices.  Special  equipment  such  as  sweepers,  dump 
carts,  etc.,  should  be  provided  in  large  terminals.  Garbage  may  be  handled  by  city 
collection,  by  contract,  or  incinerated.  An  incinerator,  if  required,  should  be  of 
ample  capacity  to  handle  each  day's  collection  in  6  to  8  hr,  conveniently  located, 
and  designed  to  burn  garbage  having  a  high  water  content. 

4.6.1.4.2  Icing 

All  cars  in  team  and  hold  and  inspection  yards  should  be  accessible  for  icing, 
which  is  usually  done  by  contract  with  local  dealers.  Access  may  be  from  narrow 
driveways  or  from  icing  platforms. 

4.6.1.4.3  Miscellaneous 

(a)  Ample  drainage  is  essential  for  buildings  and  yards. 

(b)  Floodlighting  the  entire  area  is  desirable  in  addition  to  local  lighting. 

(c)  The  entire  area  should  be  strongly  and  closely  fenced  to  prevent  trespass. 

(d)  Definitely  assigned  entrances   and  exits  should  be  provided. 

(e)  A  cold  storage  warehouse,  if  required,  should  have  suitable  track  service 
and  convenient  means  of  communication  with  other  buildings. 

(f)  Adequate  parking  space  should  be  provided. 

(g)  Motor  truck  scales,  when  required,  should  be  located  at  a  point  convenient 
for  the  drivers  and  near  the  freight  ofiBce.  The  location  should  not  interfere  with 
truck  movements  in  the  driveways. 


Manual  Recommendations  133 


Part  5 
Locomotive  Facilities 


FOREWORD 


In  tlie  establishment  or  modification  of  any  large  railway  terminal  it  is  necessary 
to  detennine  whether  separate  locomotive  facilities  should  be  provided  for  freight 
and  passenger  equipment,  or  whether  both  types  should  be  handled  in  a  single 
facility.  Convenience,  expedition,  low  unit  operating  costs  and  carrying  charges  in- 
volved in  these  alternatives  must  be  given  proper  consideration.  Usually  a  single 
facility  is  more  efficient  and  produces  lower  unit  operating  costs. 

The  locomotive  facilities  must  be  correlated  to  all  other  faciilties  for  efficient 
handling  of  each  locomotive.  Servicing  facilities  required  for  the  various  types  of 
locomotives  should  be  arranged  in  an  efficient  sequence. 


CONTENTS 

Section  Page 

5.1  General    134 

5.2  Servicing   Facilities    135 

5.3  Inspection  Pits    136 

5.4  Diesel,  Diesel-Electric  and  Electric    137 

5.5  Steam   138 


134       Bulletin  655 — American  Railway  Engineering  Association 

5.1  GENERAL 

5.1.1  Requirements 

(a)  In  the  case  where  only  one  company  is  involved  which  has  locomotive 
facilities  that  can  be  readily  enlarged  to  meet  all  requirements,  economy  will  favor 
the  retention  of  such  facilities  in  service  unless  it  is  prohibitively  remote  from  either 
the  passenger  station  or  the  center  of  freight  activities. 

(b)  In  the  case  of  joint  freight  facilities  it  may  be  advisable,  as  in  joint 
passenger  terminals,  to  substitute  new  joint  freight  locomotive  facilities  for  several 
layouts  vmless  existing  separate  facilities  are  merely  coordinated  and  delegated  to 
joint  management  where  it  will  be   advisable   to  rely  upon  the  existing  facilities. 

( c )  New  locomotive  facilities  should  be  located  to  minimize  ( 1 )  usage  of  tracks 
on  which  tliere  are  other  movements,  (2)  reverse  or  conflicting  movements,  (3)  light 
engine  mileage  in  tlie  movement  of  locomotives  to  and  from  their  trains.  In  designing 
a  locomotive  terminal  layout  a  thorough  study  of  the  traffic  and  operating  require- 
ments of  the  terminal  should  be  made  jointly  by  the  engineering,  transportation 
and  mechanical  departments.  This  study  should  include  consideration  of  the  follow- 
ing data,  keeping  future  expansion  in  mind: 

Type  and  size  of  locomotives  to  be  handled. 

Number  of  locomotives   handled  in  each  direction  daily,  by  classes. 

Schedule  of  arrival  and  departure  of  locomotives,  by  classes. 

Number  of  locomotives  arriving  during  peak  period. 

Time  within  which  locomotives  arriving  must  be  hostled,  by  classes. 

Maximum  number  of  locomotives  in  tenuinal  at  one  time. 

Number  of  locomotives  repaired  daily,  by  classes  of  work. 

Number  of  locomotives  under  repair  at  one  time,  by  classes  of  work. 

Amount  of  fuel   (coal,  diesel  or  fuel  oil)   issued  daily. 

Amount  of  water  consumed  daily. 

Amount  of  sand  consumed  daily. 

Number  of  men  required  to  operate  the  terminal. 

5.1.2  Site  Selection 

The  selection  of  a  proper  site  requires  a  study  of  all  factors  affecting  costs  of 
construction  and  operation,  including  cost  of  preparing  site;  foundation  conditions 
and  drainage;  sewage  disposal,  water  supply  and  electricity;  relation  to  existing  or 
proposed  yards  and  to  passenger  and  freight  stations;  labor  supply,  including  housing 
facilities  and  transportation;  tax  rates;  and  availability  of  public  fire  fighting  apparatus 
and  stations. 

5.1.3  Track  layout 

(a)  All  locomotives  should  preferably  enter  the  locomotive  facilities  from  the 
same  end;  a  separate  exit  should  be  provided  for  flexibility  in  movement  to  insure 
that  the  facilities  will  not  be  tied  up  in  case  of  trouble  at  tlie  entrance. 

(b)  Entrance  tracks  should  be  so  located  and  of  such  capacity  as  to  permit 
the  prompt  receipt  of  locomotives  immediately  on  arrival,  with  space  between  those 
which  may  have  to  wait  their  turn  for  servicing.  Where  climatic  conditions  permit 
outside  storage  sufficient  tracks  should  be  provided  near  tlie  exit  for  holding  loco- 
motives already  prepared  for  service. 


Manual  Recommendations  135 


(c)  The   layout   should   provide    at   least   one    runaround    track    for    flexibility. 

(d)  At  the  ends  of  locomotive  runs  where  the  operation  requires  quick  turn- 
around service,  facilities  should  be  provided  for  standing  locomotives,  sanding, 
fueling   and  watering  with  or  widiout   inspection  pits. 

5.1.4  Buildings 

5.1.4.1  Office 

Adequate  office  facilities  should  be  provided  for  the  officer  in  charge  of  the 
terminal  and  his  staff. 

5.1.4.2  Amenity  and  service 

One  or  more  structures  of  fire-retardant  construction  should  be  provided  at  a 
convenient  location  to  house  the  following: 

(a)  Locker,    toilet    and    washrooms    for    employees. 

(b)  Storehouse  for  flagging  equipment,  supplies,  oil,  lanterns,  etc. 

5.1.4.3  Reference 

Complete  information  on  the  design  of  shop  buildings  and  other  buildings  re- 
quired in  an  engine  terminal,  together  with  pits  and  other  appurtenances,  will  be 
found  in  Chapter  6 — Buildings. 

5.1.5  Miscellaneous  facilities 

5.1.5.1  Communications 

(a)  Telephone 

(b)  Radio 

(c)  Paging — Talk-back  speakers 

(d)  Pneumatic  tube   (if  necessary) 

5.1.5.2  Lighting 

The  entire  locomotive  terminal  area  should  be  provided  with  adequate  lighting. 

5.2  SERVICING  FACILITIES 

5.2.1  Fueling  Stations 

(a)  Coaling  Stations 

Coahng  stations  should  be  located  to  serve  as  many  locomotives  as  possible  on 
their  regular  routes.  There  are  two  general  locations  for  coaling  stations,  those  at 
enginehouse  leads  at  terminals  and  those  adjacent  to  main  tracks  between  terminals. 
At  terminals,  coaling  stations  should  be  located  to  serve  both  inbound  and  outbound 
tracks  as  recommended  for  tlie  engine  terminal  layout.  Coal  stations  may  be  arranged 
readily  to  deliver  coal  on  one  or  more  tracks.  Each  location  should  be  studied  sepa- 
rately on  the  most  suitable  track  arrangement  for  that  particular  installation  selected. 

(b)  Fuel  Oil  Stations 

At  locations   where  oil  is  used  as  a   fuel  for  locomotives,   facilities  must  be 

provided  for  unloading,  storing  and  delivering  such  oil.  In  cases  where  the  fuel  oil 

used  is  a  heavy  type,  facilities  must  be  provided  for  heating  such  oil  while  being 

unloaded  as  well  as  in  storage  so  that  pumping  may  be  completed  in  a  minimum 
length  of  time. 


136       Bulletin  655 — American  Railway  Engineering  Association 

In  the  design  and  construction  of  fueling  stations  at  locomotive  facilities  pro- 
visions should  be  included  to  prevent  the  pollution  and  contamination  of  public 
waters  from  spilled  fuels  and  oils  through  surface  and  subsurface  waters,  sewers 
and  odier  conduits. 

5.2.2  Watering 

Sufficient  watering  facilities  should  be  provided  to  serve  all  locomotives  entering 
and  leaving  die  terminal. 

5.2.3  Sanding 

Sanding  facihties  should  be  provided  to  serve  all  locomotives  entering  and 
leaving  the  terminal.  Usually  tiiese  facilities  are  situated  adjacent  to  the  fuel  and 
water  facilities  so  that  locomotives  can  be  completely  serviced  at  one  location. 

5.2.4  Washing 

(a)  Steam  locomotives 

Facilities  should  be  provided  for  washing  locomotives  between  the  cinder  pit 
and  the  turntable.  Either  a  washing  platfonn  or  pit  should  be  constructed  with 
adequate  drainage  and  illumination. 

(b)  Diesel  and  electric   locom.otives 

Washing  facilities  should  be  placed  on  the  lead  track  when  possible.  Brushes 
and  spray  pipes  may  be  so  arranged  tliat  die  operation  is  automatic  when  the  loco- 
motive shunts  a  track  circuit  at  the  entrance  to  the  washer.  Some  hand  washing 
of  a  locomotive  may  be  necessary.  A  washing  platform  with  or  widiout  a  wash  pit 
to  facilitate  cleaning  the  underside  of  a  locomotive  may  be  found  desirable. 

5.2.5  Boiler  Washing 

(a)  In  diesel,  diesel-electric,  and  electric  locomotive  facilities,  boiler- washing 
facilities  should  be  provided  for  heat  generating  boilers  on  locomotives  used  in 
passenger,  mail  and  express  service. 

(b)  In  steam-locomotive  facilities,  boiler- washing  facilities  should  be  provided 
for  all  locomotives. 

5.2.6  Turning  Locomotives 

Unless  the  locomotives  to  be  handled  are  exclusively  of  the  type  with  operating 
controls  at  both  ends,  some  form  of  turning  facility  such  as  a  turntable,  a  balloon 
or  loop  track,  or  a  wye  track  must  be  provided. 

5.2.7  Portable  Servicing 

Portable  servicing  units  consisting  of  a  truck  equipped  with  sand  and  fueling 
facilities  may  be  desirable  for  servicing  diesel  switch  engines  at  a  large  terminal. 

5.3  INSPECTION  PITS 

Inspection  pits  are  usually  located  on  the  inbound  track  near  the  entrance  to 
the  terminal,  except  such  a  pit  as  described  in  5.4.1(g).  These  pits  should  have: 

(a)  Suitable  deptii  for  inspection  of  the  locomotives. 

(b)  Length  not  less  tiian  the  longest  locomotive  to  be  inspected. 

(c)  Adequate  drainage. 


Manual   Recommendations 137 

(d)  Stairway  for  convenient  access  and/or  tunnel  direct  to  the  inspectors' 
office. 

(e)  Fixtures  for  lighting  and  service  outlets. 

(f)  Telephone  supplemented  by  a  pneimiatic  tube  system  for  communication 
with  the  shop  supervisor's  office. 

5.4  DIESEL,  DIESEL-ELECTRIC  AND  ELECTRIC 

5.4.1  Shop  Building  and  Appurtenances 

(a)  The  size  of  the  building  is  determined  by  the  lengtli  of  units  and  the 
number  to  be  housed  simultaneously.  A  rectangular  structure  is  ideal  to  serve  the 
requirements.  \Vlien  locomotives  are  pooled,  the  back  shop  work  will  be  done  at  one 
or  more  system  shops,  and  the  building  for  such  work  \\'ill  generally  be  much  larger 
and  have  more  facilities  than  tlie  building  for  running  repairs  at  terminals  located 
between  such  system  shops.  The  structure,  however,  should  be  so  designed  as  to 
provide  facilities  for  either  running  repairs  or  heavy  repairs  as  outlined  above,  and 
should  include  a  machine  shop,  store  room,  parts  cleaning  and  parts-conditioning 
room,  wheel  supply  and  storage,  lunch  and  locker  room,  wash  rooms,  tool  rooms, 
toilets  and  office. 

(b)  Materials  used  in  construction  should  be  fire-retardant. 

(c)  The  number  and  length  of  tracks  should  be  sufficient  to  accommodate  all 
of  the  locomotives  to  be  housed  at  any  one  time.  Stub-end  heavy  repair  tracks  may 
have  certain  economic  advantages,  and  if  such  a  layout  is  used  there  should  be  at 
least  one  through  nmning  repair  track  along  side  of  the  heavy  repair  tracks.  The 
desirable  distance  between  track  centers  should  not  be  less  than  23  ft,  which  allows 
for  a  12-ft  wide  working  platform. 

(d)  The  length  of  pits  should  accommodate  the  longest  locomotive  consists. 

(e)  Wheel  storage  facilities  adjacent  to  repair  shops  should  be  provided  to 
assure  a  convenient  supply  of  wheels,  including  wheels  with  their  traction  motors 
attached. 

(f)  The  lubricating  oil  facilities  may  be  handled  in  the  repair  shop  proper  or 
in  a  separate  structure.  Fire-retardant  construction  should  be  employed.  Meters 
should  be  provided  to  measure  accurately  the  lubricating  oil  delivered  to  the  units. 
The  tanks  for  new  lubricating  oil  should  be  of  sufficient  size  to  handle  oil  in  carload 
lots.  Facilities  may  be  provided  for  reclaiming  worn  and  dirty  lubricating  oil  and 
should  include  tanks  to  collect  the  reclaimed  oil. 

(g)  When  pooled  locomotives  receive  schedule  maintenance  there  will  be  no 
need  for  them  to  enter  the  shop  building  for  days  at  a  time.  If  such  conditions  exist 
at  the  tenninal  a  track  with  an  inspection  pit  adjacent  to  the  shop  building  will  in 
most  instances  reduce  the  number  of  tracks  in  the  shop  building  by  at  least  one. 
Such  a  pit  should  be  long  enough  to  accommodate  several  sets  of  locomotive  imits 
and  should  be  near  enough  to  the  shop  building  for  the  shop  supervisor  to  direct 
the  activities  of  the  employees  on  this  pit.  Fueling  and  sanding  facilities  could  be 
located  along  this  track.  With  such  an  arrangement  it  will  mean  that  a  locomotive 
may  be  placed  on  the  pit  track  by  tlie  road  crew,  at  which  point  it  will  be  spotted 
for  the  necessary  fueling,  sanding  and  other  servicing  and  can  remain  there  until 
ordered  for  departure,  at  which  time  tlie  road  crew  may  move  the  locomotive  out  of 


138       Bulletin  655 — American  Railway  Engineering  Association 

the  engine  terminal.  This  will  result  in  real  economy,  since  hostling  required  within 
the  shop  building  area  will  be  eliminated. 

(h)  The  electric  trolley  and  other  wires  should  be  terminated  outside  of  the 
shop   building  handling  electric  locomotives. 
5.4.2  Blow-down  Facilities 

Standard  stone  ballast  grouted  with  cement  or  a  concrete  slab  should  be  pro- 
vided on  the  outbound  track  for  locomotives  used  in  passenger  service  on  which 
there  are  steam  generating  units  for  train  heating. 

5.5  STEAM 

5.5.1  Enginehouse 

(a)  The  circular  form  of  enginehouse  is  preferable  under  ordinary  conditions 
for  steam  locomotives.  The  structure  should  provide  facilities  for  running  repairs, 
heavy  repairs,  machine  shop,  store  room,  wheel  supply  and  storage,  lunch  and  locker 
rooms,  wash  rooms,  tool  rooms,  toilets  and  office.  The  length  of  stall  along  center 
line  of  tracks  should  be  at  least  20  ft  greater  than  the  over-all  length  of  the  loco- 
motive and  tender  so  as  to  provide  a  trucking  space  10  ft  wide  in  front  of  the  pilot 
and  space  in  which  to  detach  tlie  tender  and  provide  a  walkway  between  it  and  the 
engine  without  opening  the  door.  The  stall  angle  of  a  circular  enginehouse  should  be 
such  that  when  extended  beyond  a  half-circle  the  pit  tracks  will  line  up  across  the 
turntable.  Radial  stub-end  tracks  on  the  side  of  the  turntable  opposite  the  engine- 
house  and  in  line  with  pit  tracks  are  sometimes  desirable. 

(b)  The  track  layout  should  be  designed  so  that  locomotives  which  do  not 
require  turning  may  be  serviced  without  crossing  the  turntable. 

(c)  All  approach  and  departure  tracks  to  and  from  the  turntable  should  line 
across  the  table  with  enginehouse  tracks  to  permit  convenient  movement  of  dead 
locomotives  or  carloads  of  supplies  into  or  out  of  the  enginehouse. 

(d)  Sufficient  tangent  should  be  provided  on  aU  tiuntable  approach  tracks  to 
permit  all  engine  trucks  to  be  on  straight  track  before  passing  onto  turntable. 

5.5.2  Blow-off  Facilities 

If  the  nmiiber  of  engines  serviced  justifies  tlie  installation  of  a  separate  blow-off 
pit,  it  should  be  furnished.  These  blow-off  pits  may  be  located  between  the  engine 
washing  facilities  and  the  turntable,  or  on  the  outbound  engine  lead.  The  blow-off 
pit  should  be  of  a  permanent  type  of  construction  and  should  be  provided  with 
sufficient  drainage.  The  pit  should  be  large  enough  to  prevent  overflowing  when  in 


5.5.3  Cinder  Handling 

Locomotive  cinders  must  be  disposed  of,  and  facilities  will  have  to  be  provided 
for  handling  cinders.  There  are  several  types  of  cinder-handling  facilities,  including: 

(a)  Cinders  discharged  directly  on  the  track  and  removed  by  shoveling, 

(b)  Shallow  shoveling  pits. 

(c)  Water  pits,  where  cinders  are  discharged  into  pits  containing  water,  from 
which  they  are  removed  and  loaded  into  cars  by  either  a  locomotive  or 
overhead  crane. 


Manual  Recommendations 139 

(d)  A  depressed  track  beside  or  between  die  incoming  tracks,  deep  enough 
to  accommodate  cars  into  which  cinders  are  chuted  directly  from  the 
locomotives. 

(e)  Mechanical  plant  \\here  cinders  are  discharged  into  hoppers  and  thence 
into  buckets  or  continuous  conveyors  into  cars. 

The  track  arrangement  in  the  cinder-handling  facility  must  be  studied  to  provide 
sufficient  standing  capacity'  to  accommodate  all  locomotives  which  cannot  be  immedi- 
ately serviced,  and  crossovers  and  other  connections  so  that  locomotives  requiring 
preferred  attention  may  be  dispatched  ahead  of  others  with  a  minimum  of  inter- 
ference. 


Manual  Recommendations  141 


Part  6 
Passenger  Facilities 


FOREWORD 


The  designation  "passenger  facilities"  as  here  employed,  comprising  mass  transit 
and  commuter  service,  includes  all  the  facilities  for  the  passenger  station  proper, 
mail  and  express  service,  track  and  street  approaches,  such  other  auxiliary  or  acces- 
sory features  as  may  be  included  witliin  a  prescribed  boundary  or  terminal  zone, 
and,  where  desirable  and  practicable,  a  locomotive  tenninal,  a  coach  yard,  and 
the  appurtenant  switching  facilities. 


CONTENTS 
Section  Page 

6.1  General    142 

6.2  Site 142 

6.3  Track  Arrangement    144 

6.4  Station   Proper    145 

6.5  Coach  Yards  152 

6.6  Modernization  157 


142       Bulletin  655 — American  Railway  Engineering  Association 

6.1  GENERAL 

(a)  Studies  for  such  passenger  facilities  should  be  made  by  a  committee,  repre- 
senting all  the  parties  at  interest,  composed  of  engineering,  transportation,  mechanical, 
signal  and  tiaffic  officers.  Preferably  the  officer  to  be  placed  in  charge  of  the  property 
for  operating  purposes  should  be  made  a  member  of  that  committee. 

(b)  Consistent  with  the  magnitude  and  importance  of  the  task,  men  having 
expert  knowledge  of  tlie  various  phases  of  the  problem  should  be  employed  under 
the  direction  of  the  committee  to  study  the  whole  situation.  These  experts  should 
determine  and  report  on  all  necessary  requirements  of  the  terminal. 

(c)  The  engineer  having  charge  of  the  design  of  the  contemplated  facilities, 
accompanied  when  practicable  by  members  of  the  committee  or  its  representatives, 
should  make  investigations  by  personal  inspection  of  terminal  situations  somewhat 
similar  to  the  one  in  contemplation;  talk  with  responsible  officers  of  similar  terminals; 
examine  the  facilities  there  provided  and  see  how  they  function;  obtain  comments 
from  the  men  operatingthe  terminals  visited;  get  their  suggestions  as  to  improve- 
ments which  experience  has  taught  them  might  be  made  to  advantage.  He  should 
also  accumulate  and  study  reports  that  have  been  written  covering  particular  proper- 
ties, and  also  the  books  and  articles  that  have  been  written  upon  the  general  subject; 
and  seek  infonnation  from  all  available  sources. 

(d)  The  handling  of  mail  and  express,  and  tlie  conjunction  thereof  witli  the 
handling  of  baggage,  are  essential  and  integral  parts  of  passenger  terminal  operation. 
The  necessary  facilities  should  be  planned  in  cooperation  with  the  express  and  postal 
officials  concerned. 

(e)  A  passenger  terminal  project  should  be  so  located  and  designed  as  to 
coordinate  as  far  as  reasonably  practicable  with  other  civic  activities.  Frequently 
it  is  found  desirable  to  make  general  civic  improvements  at  the  same  time  the  termi- 
nal is  being  constructed.  Modification  of  street  approaches  is  almost  always  involved. 
The  costs  should  be  assumed  by  the  parties  benefited.  Close  cooperation  between 
the  terminal  committee,  the  planning  board  of  the  city,  executive  officers  of  the 
city,  and  perhaps  other  civic  groups,  if  necessary  in  order  that  such  new  legislation 
as  may  be  necessary  shall  be  fair  and  equitable  to  all  parties  at  interest. 

(f)  The  designer  must  realize  that  a  large  passenger  terminal  is  subject  to 
vicissitudes  of  weather,  to  delays  and  derailments  to  trains,  to  late  connections,  to 
power  failures,  to  surges  in  traffic,  to  bad-order  equipment,  to  special  trains  or  cars 
requiring  special  handling,  to  excursion  travel,  and  to  jubilees,  conventions  and 
special  functions   at   irregular  periods. 

(g)  The  relations  which  should  exist  between  business  handled  and  the  size 
of  facilities  is  subject  to  variation  due  to  local  conditions,  class  of  traffic,  type  of 
service  rendered,  large  variation  in  estimates  of  normal  rush-hour  business  handled, 
and  the  varying  ideas  of  what  constitutes  adequate  service.  Table  2  outlines  the 
relations.  Committee  6 — Buildings,  should  be  consulted  in  the  design  of  such 
facilities. 

6.2  SITE 

The  site  for  the  terminal  should  have  a  balanced  maximum  composed  of  the 
following  characteristics: 

(a)  Accessibility — ^having  due  regard  to  modern  methods  of  transportation, 
land  values,  and  economic  requirements. 


Manual  Recommendations 


143 


Table  2 

Relations  Which  Should  Exist  Between  Business  Handled  and  the  Size  or 
Through  Passenger  Station  Facilities 


station  Facility 


Unit 


Number  or  Site  of  Facility  Required  for 

the  Normal  Number  of  Rusk-Hour 

Passengers  Indicated 


250 


500 


750 


10001   1500    2000    3000    4000    5000 


1.  Area  of  main  waiting 

room 

2.  Seating  capacity  of 

main  waiting  room. 

3.  Area  of  women's  wait- 

ing room 

4-  Total  area  for  waiting 

purposes 

6.  Total  seats  in  waiting 

areas 

6.  Total  area  of  lobby, 

concourse  and  all 
waiting  rooms 

7.  Area  of  men's  toilet 

rooms 

8.  Number  of  men's  water 

closets 

9.  Number  of  uriaals... 

10.  Number  of  men's  lava- 

tories  

11.  Area  of  women's  toilet 

rooms 

12.  Number  of  women's 

water  closets 

13.  Number  of  women's 

lavatories 

14.  Area  of  ticket  offices 

15.  Number  of  ticket 

windows 

16.  Number  of  telephone 

booths 

17.  Area  of  telegraph 

facilities 

18.  Total  area  of  dining 

and  lunch  rooms 

19.  Total  number  of  seats 

in  dining  and  liinch 
rooms 

20.  Area  of  kitchen 

21.  Area  of  news  stand 

22.  Number  of  barber  chairs 


23.  Area  of  baggage  room. . 

24.  Baggage  room  tail- 

board frontage 


100  eq   ft 
No.  of  seats 
100  sq  ft 
100  sq   ft 
No.  of  seats 

100  sq  ft 

100  sq  ft 

Number.. 
Number.. 

Number.. 

100  sq   ft 

Number.. 

Number.. 
100  sq   ft 

Number.. 

Number. - 

Sq  ft 

100  sq  ft 


Number.. 
100  sq  ft 

Sq   ft 

Number.. 


30 

143 

5 

55 
190 

80 

4 

6 
5 

3 

3 

7 

3 
4 

3 

3 

100 

9 


34 

5 

115 

2 


53 

213 

7 

88 
300 

152 
6 

9 

8 

5 
4 
9 

5 

7 

5 

4 

130 

14 

53 

8 

185 

3 


72 

270 

9 

116 

390 

208 

8 

12 
10 

7 

5 

12 

7 
9 

7 

5 

150 

19 


72 

11 

240 

3 


89 
315 

11 
137 
470 

256 

10 

15 
12 

9 

6 

14 

9 
11 

8 

7 

170 

24 


93 

14 

290 

4 


112 
400 
14 
167 
590 

320 

13 

19 
15 

11 

8 

17 

11 
14 

11 

10 

210 

34 


129 

20 

380 

4 


128 
465 
17 
195 
700 

376 
15 

23 

17 

13 

10 

19 

13 
17 

13 

13 

230 

43 


173 

26 

450 

5 


155 
570 
23 
238 
880 

472 

20 

29 
20 

18 

13 

23 

17 
21 

16 

19 

280 

63 

249 

38 

565 

6 


178 

665 

29 

275 
1050 

552 

26 

35 
23 

22 

16 

27 

21 
26 

18 

25 

310 

83 


327 

50 

695 

7 


Unit 


Baggage  Facilities  Required  for  the 

Indicated  Number  of  Pieces  of 

Baggage  Handled  Daily 


250 


100  sq  ft 
Lin'  ft  ... 


500      750     1000    1500    2000    3000    4000    5000 


87 
125 


112 

150 


166 
194 


219 
230 


Unit 


Parcel  Check  Room  Facilities  Required 

for  the  Indicated  Number  of 

Parcels  Handled  Daily 


250 


25.  Area  of  parcel  check 
room 


100  sq  ft 


500   750  1000  1500  2000 


10 


14 


18 


Unit 


Hand-Baggage  Facilities  Required  for 

the  Indicated  Number  of  Pieces  of 

Hand-Baggage  Handled  Daily 


250 


26.  Area  of  hand-baggage 
facilities 


100  sq   ft 


500 


750 


1000 


1500 


2000 


3000 


200 

750 

35 

306 

1200 

624 

31 

41 
25 

26 

18 

30 

25 


21 

31 

330 

102 


407 

62 

820 


272 
263 


144       Bulletin  655 — American  Railway  Engineering  Association 

(b)  Sufficient  size  and  suitable  shape  to  provide  for  a  proper  number  and 
length  of  tracks,  and  to  provide  for  future  growth  of  both. 

(c)  Ease  of  approach  from  all  the  associated  rail  lines,  witliout  excessive  curva- 
ture or  gradient,   and  preferably  witliout  grade  crossings. 

(d)  Room  for  proper  by-pass  tracks  and  for  the  spread  of  ladder  tracks,  to 
provide  for  free  movement  and  to  prevent  a  tie-up  of  the  yard  from  derailment  at 
the  throat. 

(e)  Room   for  auxiliary  facilities   conveniently  located,  such  as: 

( 1 )  Baggage,  mail  and  express. 

(2)  Parking  space  for  sleeping,  private   and  business  cars. 

(3)  Locomotive  terminal. 

(4)  Coach  yard. 

(5)  Automobile  parking. 

6.3  TRACK  ARRANGEMENT 

(a)  The  track  layout  should  be  such  as  may  be  required  to  accommodate 
straight-forwardly  and  without  interference  the  contemplated  schedule  movement 
of  trains  and  the  tributary  switching  movements  to  and  from  the  station,  with  a 
proper  margin  for  extra  sections  or  delayed  trains,  as  well  as  for  any  predictable 
increase  in  volume  of  traffic. 

(b)  The  track  layout  should  be  designed  with  length  between  turnouts  as 
required  for  the  proper  signal  indications,  and  necessary  clearances  as  required  for 
operation  of  track  circuits  so  that  a  system  of  fixed  signals  or  interlocking  may  be 
installed  whenever  desired  without  restricting  the  use  of  any  of  tlie  routes  or  the 
necessity  of  additional  track  changes. 

(c)  Station  tracks  should  be  provided  sufficient  in  number  to  accommodate 
at  one  time  the  contemplated  schedule  movement  of  trains,  witli  a  liberal  margin 
for  extra  sections  and  off-schedule  arrivals  or  departures,  and  should  be  of  such  clear 
length  and  lateral  spacing  as  may  be  required  to  fit  the  station  platform  layout  and 
to  accommodate  without  congestion  the  essential  functions  of  tlie  station  platform 
service.  While  the  number  of  station  tracks  is  largely  fixed  by  the  number  of  trains 
to  be  accommodated  at  periods  of  maximum  density,  it  also  to  some  extent  may 
depend  upon  the  type  and  size  of  die  station,  tlie  lengths  of  the  station  tracks,  the 
design  of  the  throat,  the  proximity  of  the  coach  yard  and  locomotive  terminal  facili- 
ties, the  character  of  traffic,  and  the  method  of  operation. 

(d)  Sufficient  throat  tracks  should  be  provided  to  permit  at  least  two  simul- 
taneous parallel  movements.  The  track  layout  should  be  sufficiently  flexible  to  provide 
for  complete  interchange  of  routes.  A  ratio  of  from  2.5  to  3.0  station  tracks  to  1 
throat  track  should  be  adequate  if  the  tliroat  is  properly  designed. 

(e)  A  sufficient  number  of  station  tracks  long  enough  to  accommodate  the 
maximum  length  trains,  and  so  located  as  to  assure  flexibility  of  operation,  should 
be  provided.  Possibility  of  future  increase  in  length  of  trains  should  be  considered. 

(f)  The  through  and  loop  types  of  station  are  superior  to  the  stub  station  from 
the  standpoint  of  train  operation. 

(g)  Loop  tracks  for  turning  bains  generally  expedite  service  and  effect 
economies. 


Manual  Recommendations 145 

(h)  The  possibilties  of  using  the  station  tracks  for  other  service,  such  as  freight 
interchange,  when  not  in  use  for  their  normal  purpose,  should  be  studied. 

(i)  Freight  or  industry  connections  on  the  station  approach  tracks  or  on  lines 
within  or  adjacent  to  the  terminal  zone  should  be  so  arranged  as  to  avoid  or  minimize 
interference  with  passenger  train  traffic. 

6.4  STATION  PROPER 

6.4.1  General 

The  station  proper  includes  all  the  facilities  required  for  the  complete  accommo- 
dation of  passengers  and  their  belongings  between  the  public  entrances  and  the 
trains;  also  such  facilities  as  the  railway  company  shall  provide  for  the  handling  of 
mail  and  express.  It  comprises: 

(a)  The  main  building,  which  includes  all  of  the  facilities  directly  needed  for 
the  comfort  and  convenience  of  passengers  prior  to  their  departure  or  subsequent 
to  their  arrival  on  trains. 

(b)  All  thoroughfares  connecting  the  main  building  with  the  station  platforms, 
such  as  fixed  or  moving  stairways,  elevators,  ramps,  and  other  passageways  and 
outside  concourses. 

(c)  The  station  tracks  and  tlie  appurtenant  platforms  on  which  passengers, 
baggage,  mail  and  express  are  loaded  upon  or  unloaded  from  trains,  including  the 
elevators,  ramps,  or  other  runways,  upon  which  baggage,  express  and  mail  are  trucked 
to  or  from  the  station  platform. 

(d)  All  other  buildings  to  accommodate  the  assembly  and  the  public  receipt 
and  delivery  of  baggage,  express  or  mail. 

(e)  All  roadways,  platforms  and  parking  spaces  to  accommodate  taxicabs  and 
other  public  and  private  vehicles,  handling  people  to  and  from  the  station,  including 
all  housing  and  shelter  thereof  not  embraced  in  the  main  building. 

6.4.2  Main  Building  Areas 

6.4.2.1  General 

(a)  The  principal  floor  areas  should  include  a  lobby,  a  waiting  room  or  rooms, 
a  passenger  concourse,  and  a  separate  women's  powder  room,  or  any  combination 
of  these  facilities. 

(b)  All  of  the  essential  functions  of  the  main  building  should  be  ser\'ed  on  a 
common  floor  level,  or  levels  so  nearly  common  as  to  be  connected  by  moderate 
ramps,  and  so  related  if  possible  to  the  station  track  level  that  no  stairways  shall  be 
required  to  reach  tlie  station  platform  level  in  stub  end  stations  or  to  reach  the 
thoroughfares   over  or  under  the  tracks,  as  the  case  may  be,  in  through  stations. 

(c)  The  lobby  should  front  upon  the  principal  public  entrances  and  exits,  and 
it,  solely  or  together  with  the  passenger  concourse,  should  be  the  business  area  of 
the  station.  The  principal  station  facilities,  such  as  information  booths,  ticket  office, 
baggage  check  counter,  parcel  check  room,  telephone  and  telegraph  facilities,  parcel 
checking  lockers,  etc.,  should  be  located  in  proper  sequence  along  the  line  of  travel 
and  clearly  indicated  to  avoid  confusion  and  to  reduce  the  walking  distance  of 
passengers  to  a  minimum. 

(d)  An  adequate  and  conspicuous  train  bulletin  board  and  a  public  announcing 
system  should  be  provided. 


146       Bulletin  655 — American  Railway  Engineering  Association 

(e)  The  general  waiting  room,  if  only  one  is  provided  separately  from  the 
passenger  concourse,  may  well  be  placed  at  one  side  of  the  line  of  travel  but  as 
comenient  as  practictable  to  the  passenger  concourse. 

(f )  If  the  fiuiction  of  the  general  waiting  room  is  to  be  served  in  common  with 
that  of  the  passenger  concourse,  provision  must  be  made  for  all  the  requirements  of 
a  waiting  room,  with  seating  facilities  so  situated  as  not  to  intrude  upon  the  maxi- 
mum areas  required  for  passage  of  persons  to  and  from  the  train  gates  or  for  those 
assembhng  thereat. 

6.4.2.2  Concourses 

(a)  Unless  its  function  is  combined  with  tliat  of  a  waiting  room,  a  separate 
passenger  concourse  is  essential  in  a  large  station.  Such  a  concourse  is  used  effectively 
in  many  stations  as  a  passageway  which  permits  arriving  passengers  to  reach  the 
street  or  departing  passengers  to  enter  from  the  street  without  passing  through  the 
lobby. 

(b)  It  should  be  possible,  and  is  exceedingly  advantageous  in  the  case  of  sub- 
urban service,  for  passengers  to  proceed  directly  to  and  fro  between  tlie  passenger 
concourse  and  the  street  without  passing  through  waiting  room  or  blocking  its  exits. 

(c)  The  elimination  of  conflicting  lines  of  travel  is  very  desirable  and  should 
receive  careful  study  in  the  design  of  the  station,  particularly  as  regards  the  segre- 
gation of  inbound  from  outbound  passengers,  and  of  commuters  from  through 
passengers. 

(d)  The  required  clear  width  of  passenger  concourse  depends  upon  the  char- 
acter and  amount  of  traffic  and  the  number  of  its  entrances  and  exits.  The  concourse 
should  be  large  enough  to  permit  the  gatfiering  of  a  full  trainload  at  a  gate  without 
a  blockade,  but  should  be  so  arranged  that  it  will  not  be  a  convenient  thoroughfare 
for  people  who  are  not  passengers. 

(e)  A  train  concourse  is  advantageous,  as  it  permits  serving  one  station  plat- 
form by  several  gates  or,  conversely,  the  serving  of  several  platforms  from  one  train 
gate.  In  stub  stations  it  peniiits  trucking  from  one  platform  to  another  without 
entering  the  passenger  concourse. 

(f)  A  clear  width  of  20  ft  for  a  train  concourse  is  adequate  if  it  is  not  used 
extensively  for  trucking. 

6.4.2.3  Ticket  offices 

(a)  Ticket  offices  should  be  located  adjacent  to  the  direct  line  of  travel,  so 
arranged  that  passengers  waiting  to  secure  tickets  will  not  interfere  with  the  general 
flow  of  traffic. 

(b)  Windows,  counters,  and  automatic  ticket  machines  may  be  provided  along 
the  passenger  concourse  for  the  sale  of  local  tickets. 

(c)  Wliere  a  large  number  of  commutation  tickets  are  issued  during  tlie  last 
2  or  3  days  of  the  month,  portable  booths  located  in  the  passenger  concourse  may  be 
desirable. 

6.4.2.4  Parcel   rooms   and  parcel   checking   lockers 

The  baggage  check  rooms  should  be  easily  accessible  to  inbound  and  outbound 
passengers  and  where  the  amount  of  business  justifies,  separate  counters  should  be 
provided  for  leceiving  and  delivering  baggage.  Self-service  checking  lockers  should 
be  installed  at  convenient  locations. 


Manual  Recommendations  147 


6.4.2.5  Toilet  and  washroom  facilities 

Pay  toilets  and  pay  washroom  facilities  should  be  provided.  However,  there 
shoidd  be  an  adequate  number  of  free  toilets  and  lavatories. 

6.4.2.6  Leased  and  rental  areas 

(a)  Concessions 

(1)  Concessions  of  proper  character  have  proved  profitable  in  most  stations 
and  are  desirable,  not  only  from  a  revenue-producing  standpoint,  but 
as  a  facility  which  adds  to  the  comfort  or  convenience  of  the  passenger, 

(2)  The  number  and  character  of  tliese  concessions  can  be  greatly  expanded 
in  tenninals  located  in  cities  of  large  size,  with  benefit  and  profit  to  all 
concerned. 

(3)  Concessions,  to  be  successful,  must  be  so  located  as  to  be  conspicuous 
and  easy  of  access.  They  must  be  neat  and  attractive  in  appearance  and 
well  lighted,  and  concessionaires  should  be  experienced,  responsible  and 
progressive. 

(4)  Booths  opening  directly  on  to  the  corridor,  where  service  is  rapid,  appeal 
more  to  the  commuter,  while  stores  appeal  to  the  through  traveler  and 
particuarly  to  the  transfer  passenger  who  has  time  to  spare. 

(h)  Office  space 

( 1 )  The  practice  of  constructing  rentable  office  space  in  connection  with 
passenger  stations  under  proper  circumstances  offers  opportunities  for 
assisting  in  carrying  the  interest  charge  resulting  from  the  construction 
of  stations. 

(2)  If  the  station  building  is  surmounted  by  an  office  building,  the  entrances 
to  the  latter  should  be  independent  of  the  station  so  tliat  office  employees 
will  not  be  required  to  pass  through  the  station.  Consideration,  however, 
should  be  given  in  tlae  design  of  certain  station  facilities  to  the  possible 
patronage   by   occupants   of   tlie  office   building. 

6.4.3  Station  Platforms 

6.4.3.1  General 

In  planning  a  passenger  terminal  it  is  important  to  devise  a  coordinated  arrange- 
ment between  the  track  layout  and  the  station  proper  which  will,  at  reasonable  cost, 
provide  maximum  con\enience,  expedition,  and  economy  in  rendering  all  the  platform 
services. 

Particularly  at  heavy  duty  stations,  it  is  extremely  desirable  that  baggage,  mail 
and  express  trucks  shall  not  ordinarily  have  to  traverse  or  occupy  platform  space 
being  used  for  the  accommodation  of  passengers. 

Determination  of  the  type  of  platform  ( i.e.,  combined  or  separate  trucking  and 
passenger)  best  suited  to  a  particular  situation  is  dependent  upon  the  character  and 
volume  of  the  \'arious  kinds  of  traffic  handled,  the  type  of  station  (i.e.,  stub,  tlirough 
or  loop),  the  location  and  type  of  approaches  to  tlie  platforms  for  the  various  kinds 
of  traffic,  the  relation  of  the  various  approaches  to  each  otlier,  the  relative  lengths 
of  platforms  and  trains,  space  available  for  station  track  and  platform  development, 
and  the  method  of  operation.  Because  there  are  so  many  variables  involved,  final 
conclusion  as  to  the  best  arrangement  in  any  case  can  hardly  be  reached  without 
thorough  study.  All  factors  affecting  a  particular  situation  must  be  analyzed  liefore 
this  determination  can  be  made. 


148       Bulletin  655 — American  Railway  Engineering  Association 

6.4.3.2  Platform  arrangement 

6.4.3.2.1  Heavy  traffic 

(a)  For  a  through  station,  with  track  level  below  or  above  tlie  station  floor 
level  (preferably  the  latter),  combined  platforms  should  be  installed,  sufficient  in 
lengtli  to  permit  bertliing  Uie  passenger  carrying  cars  in  the  center  zone  leaving  the 
end  zones  clear  for  tiucking.  Passengers  would  reach  or  leave  the  platforms  via 
ramps,  stairways  or  escalators  at  the  middle  of  the  platforms;  and  trucks  would 
reach  or  leave  the  platfoniis  by  elevators  or  ramps,  at  or  near  the  ends  connected 
with  subway  runways  and  assembly  areas.  If  platforms  cannot  be  built  to  such 
length  or  if  two  trains  are  regularly  berthed  on  the  same  track  simultaneously,  inter- 
ference between  passengers  and  trucking  will  result  and  the  installation  of  separate 
platforms  may  be  justified. 

(b)  For  a  loop  station,  the  same  assembly  as  above  specified  for  a  through 
station  should  be  provided,  but  with  truck  elevators  near  only  the  forward  ends  of 
tlie  platfonns. 

(c)  For  a  stub  station,  with  tracks  at  same  level  as  station  floor: 

( 1 )  If  all  trains  back  in,  combined  platforms  should  be  installed.  Provision 
should  be  made  for  all  trucks  to  reach  or  leave  the  station  platforms  near  the  outer 
ends,  via  elevators  or  ramps  connecting  with  subway  facilities. 

(2)  If  inbound  trains  head  in,  separate  platforms  should  be  provided  for 
passengers  and  trucks,  the  latter  to  reach  or  leave  their  platfonns  via  elevators  or 
ramps  connecting  with  subway  facilities. 

The  type  ( 2 )  layout  requires  so  much  more  area  and  platform  construction  than 
type  ( 1 )  that  type  ( 2 )  is  preferable  only  when  the  backing  in  of  all  trains  is  imprac- 
ticable or  when  the  volume  of  trafiic  handled  is  such  that  the  increased  cost  of  land 
and  facilities  required  by  type  (2)  is  justified  by  the  elunination  of  interference 
on  the  platforms. 

(d)  In  all  cases  where  truck  elevators  or  ramps  are  provided,  tmck  runways  at 
grade  across  the  tracks  should  also  be  provided  to  meet  demands. 

6.4.3.2.2  Light  traffic 

At  stations  where  both  passenger  and  truck  movements  will  be  relatively  light 
and  train  arrivals  and  departures  will  occur  mostly  at  separate  intervals,  a  careful 
predetermination  of  the  balance  between  investment  and  advantage  may  be  required 
to  decide  whether  or  not  grade  separation  is  justified,  either  for  passengers  or  for 
trucks,  and  which  method  of  rendering  the  platform  services  is  to  be  selected. 

In  such  situations,  and  also  at  some  heavy-duty  stations  where  attainment  of 
the  ideal  seems  impracticable  or  too  costly,  there  may  be  warrant  for  designing  the 
station  platforms  for  the  combined  use  of  trucks  and  passengers  throughout  their 
length. 

In  the  case  of  combined  platforms  on  which  the  loading  and  unloading  of 
baggage,  mail  and  express  is  confined  to  the  end  sections  tiiereof,  and  trucking 
tiirough  the  areas  devoted  to  the  loading  and  unloading  of  passengers  is  not  per- 
mitted, platform  widths  may  be  the  same  as  for  exclusive  passenger  platforms. 

6.4.3.3  Design  data 

(a)  Combined  passenger  and  trucking  platforms  at  heavy  duty  stations  should 
be  at  least  20  ft  in  width,  assuming  a  row  of  columns  located  in  tlie  center  of  the 
platform. 


Manual  Recommendations 149 

(b)  Exclusi\e  passenger  platforms  should  have  a  niiniinuni  uidth  of  13  ft, 
wliich  is  sufficient  to  accommodate  the  passengers  froui  one  arri\  ing  train,  one  line 
of  travel  for  passengers  to  a  departiug  train,  and  a  row  of  columns  in  the  center 
of  the  platform.  This  width  will  normally  meet  all  requirements  for  through  pas- 
senger train  operation,  ;xs  it  is  seldom  necessary  to  berth  two  arriving  trains  sinnil- 
taneously  at  the  same  platform. 

(c)  Exclusixe  trucking  platforms  without  columns  should  have  a  minimum 
width  of  11  ft  to  permit  2  tnicks  to  pass.  Where  die  \olume  of  trucking  is  sufficient 
to  justify  3  lanes,  a  minimum  of  16  ft  should  be  provided  to  avoid  blocking  the 
platfomi  when  2  trucks  are  serxing  cars  on  opposite  sides.  If  columns  are  necessary, 
platform  widths  should  be  increased  accordingly  and  columns  located  so  as  not  to 
interfere   with   trucking  lanes. 

(d)  In  combined  passenger  and  trucking  platforms  in  through  stations,  it  is 
desirable  to  have  a  clear  width  of  approximately  6  ft  on  one  side  of  the  stairs  to 
permit   trucking  operations   past  the  stairs. 

(e)  In  stations  where  a  large  number  of  passengers  must  be  handled  quickly, 
die  relation  of  platfomi  elevation  to  height  of  car  floor  should  be  considered  to 
expedite  the  handling  of  passengers.  However,  high  platforms  interfere  to  some 
extent  with  the  switching  and  inspection  of  equipment. 

(f)  In  a  through  station,  the  location  on  the  station  platform  of  tlie  approach 
to  the  concourse  has  a  bearing  on  the  required  capacity  of  the  approach.  If  it  is 
located  at  the  end  of  the  platform,  die  concentration  will  be  but  one-half  as  intense 
as  if  it  is  located  at  die  middle  of  the  platform,  although  the  duration  of  the  maxi- 
mum intensity  of  congestion  will  be  much  less  in  the  latter  case  than  in  the  former. 
If  a  double  approach  is  located  at  the  center,  the  intensity  of  the  concentration  will 
be  the  same  as  in  die  first  case,  and  the  duration  of  the  maximum  intensit\-  of  conges- 
tion will  be  die  same  as  in  the  second  case. 

(g)  In  large  terminals  where  a  large  quantity  of  U.  S.  storage  mail  is  handled, 
belt  con\e>ors  should  be  installed  to  move  die  bags  of  inbound  mail  from  the  cars  to 
a  primary  sorting  platform  if  not  directly  to  the  post  office.  From  a  primary  sorting 
platform  belt  coii\e>ors  can  be  used  to  move  the  mail  to  secondary  sorting  platforms. 
Electromechanical  sorting  systems  have  been  installed  in  metropolitan  area  stations 
to  handle  the  large  number  of  separations  fiom  a  primary  sorting  platform. 

To  expedite  die  handling  of  mail  an  ideal  arrangement  is  to  locate  the  Post 
Office  Department  building  adjacent  to  the  railroad  station  or  on  air  rights  over  rail- 
road terminal  propert>'.  Belt  con\e>ors  can  be  used  to  move  the  mail  sacks  and 
parcels  between   the  post  office  building  and  the  station  building. 

6.4.3.4  Elevators  and  escalators 

(a)  Baggage  elevators  are  desirable  at  both  ends  of  combined  passenger  and 
trucking  platforms  in  large  passenger  stations  where  trains  operate  in  both  directions 
through  the  station,  to  reduce  the  interference  between  trucking  operations  and 
passengers. 

(b)  Under  normal  conditions,  passenger  ele\'ators  are  not  recommended  as 
approaches  to  individual  passenger  platforms.  They  may  be  desirable  as  a  supplement 
to  stairways  for  the  use  of  the  aged  and  infirm. 

(c)  A  single  elevator  or  escalator  should  not  be  relied  upon  as  the  sole  means 
of  approach  to  a  station  platform. 

Bui.   655 


150       Bulletin  655 — American  Railway  Engineering  Association 

(d)  Escalators  have  a  niaxiniuni  carrying  capacity  of  approximately  5000  pas- 
sengers per  hour  for  32-in  width  and  8000  passengers  per  hour  for  48  in.  They  are 
being  used  successfully  in  both  suburban  and  dirough  passenger  service. 

6.4.3.5  Ramps 

6.4.3.5.1  Passenger 

( a )  Ramps  provide  ideal  means  for  movement  of  passengers  to  and  from  station 
platforms  if  they  can  be  so  installed  as  not  to  increase  materially  the  distance  traveled 
by  passengers,  and  do  not  materially  decrease  the  space  on  the  station  platform  avail- 
able for  the  accommodation  of  trains.  Good  results  can  be  accomplished  in  many 
cases  by  the  use  of  ho\h.  stairways  and  ramps. 

(b)  The  gradient  for  passenger  ramps  preferably  should  not  exceed  7  percent. 
The  ramp  surface  should  be  finished  witli  an  abrasive  or  non-skid  material. 

6.4.3.5.2  Trucking 

(a)  Ramps  are  a  very  desirable  means  of  providing  vertical  transportation  for 
trucking  operations,  if  the  design  of  the  station  is  such  as  to  pennit  their  installation 
without  a  material  sacrifice  in  space. 

(b)  Ramp  gradients  in  excess  of  8  percent  are  not  recommended.  The  ramp 
surface   should  be   finished  with   an   abrasive  or  non-skid  material. 

(c)  In  stub  terminals  where  separate  passenger  and  trucking  platfonns  are  used 
and  the  baggage,  mail  and  express  facilities  are  located  below  the  tracks,  the  utiliza- 
tion of  the  end  of  the  exclusive  trucking  platforms  adjacent  to  the  concourse  permits 
the  installation  of  trucking  ramps  without  sacrifice  of  space. 

(d)  The  minimum  clear  width  which  should  be  considered  for  trucking  ramps 
designed  to  accommodate  one  line  of  traffic  is  6  ft,  and  for  two  lines  of  traffic  is  11  ft. 

6.4.4  Characteristic  Requirements  of  Passengers 
6.4.4.1  Through  passengers 

(a)  Transfer  passengers  occupy  a  station  for  a  maximum  length  of  time  and 
require  more  extensive  facilities  per  passenger  than  resident  tlii'ough  passengers. 

(b)  Decreasing  the  time  interval  between  incoming  and  outgoing  trains  de- 
creases requirements  per  passenger  for  waiting  room  space  and  for  certain  other 
facilities. 

(c)  The  number  of  passengers  handled  during  the  rush  hour  does  not  alone 
determine  the  size  or  number  of  facilities  required.  Local  conditions  must  be  studied, 
as   they  aftect  requirements   for  any  particular  situation. 

(d)  The  size  or  numl^er  of  facilities  must  be  modified  to  make  allowance  for: 

( 1 )  Time  of  arriving  and  departing  trains,  and  the  span  in  minutes  between 
them. 

(2)  The  ratio  between  passeengers  commencing  or  terminating  their  journey 
and  transfer  passengers. 

(3)  Number  of  hold-over  passengers  arriving  or  departing  outside  of  the  rush 
hour  but  occupying  space  and  requiring  service  during  a  portion  of  the 
rush  hour. 

(4)  Departure  from  a  reasonably  uniform  spread  of  passengers  entering  and 
departing  within  tlie  rush  hour. 


Manual  Recommendations 151 

6.4.4.2  Suburban  or  commuter  passengers 

(a)  Suburban  passengers  occupy  a  station  for  a  minimum  length  of  time  and 
move  faster  than  the  through  passenger,  and  therefore  requirements  in  the  way  of 
station  facilities  per  passenger  are  substantially  less  for  a  suburban  passenger  tlian 
for  a  through  traveler. 

(b)  When  suburban  business  is  heavy,  it  is  desirable  to  separate  tlie  through 
and  suburban  service,  as  their  requirements  are  not  similar.  This  may  be  done  by 
handling  the  two  classes  of  service  at: 

1.  Different   levels.   This   requires   electrification. 

2.  Different  sides  or  ends  of  the  station. 

3.  Different  stations,   one  beyond  the  other. 

(c)  Indicator  boards  are  the  only  directional  information  required,  as  a  rule, 
by  commuters.  They  should  show  track  number,  scheduled  leaving  time,  and  essential 
identification  of  train. 

6.4.5  Services  and  Utilities 

6.4.5.1  Communication  facilities 

Teletype  machines,  telautographs,  pneumatic  tubes,  audible  interconununication 
systems,  and  other  electronic  devices,  may  be  used  to  advantage  to  supplement  tele- 
phones for  the  rapid  transmission  of  operating  information  between  train  directors, 
station  master,  information  booth,  bulletin  board  and  other  strategic  points.  A  public 
address    system    should    be   provided   for   announcing   train   infonnation. 

6.4.5.2  Electrical  service  outlets  at  station  tracks 

Electrical  service  outlets  at  station  tracks  should  preferably  be  located  between 
adjacent  tracks,  except  in  stations  having  separate  trucking  platfonns.  Direct-current 
battery  charging  outlets,  when  serving  two  tracks,  should  have  two  receptacles  and 
should  be  located  at  inten'als  of  two  average  car  lengths  along  those  tracks  used 
regularly  for  holding  passenger  cars  for  extended  periods.  Air-conditioning  outlets 
for  220-v  ac,  when  serving  two  tracks,  should  have  two  receptacles,  and  should  be 
located  at  intervals  of  one  average  car  length  along  those  tracks  used  regularly  for 
holding  either  direct-mechanical  or  electro-mechanical  air-conditioned  passenger 
cars. 

6.4.5.3  Steam,   air,   water   and   telephone   connections 

(a)  Steam  connections  should  be  provided  at  all  station  tracks  on  which  cars 
will  stand  without  locomotive  attached.  For  stub  tracks,  steam  connections  should 
be  located  at  the  ends,  one  connection  for  each  track.  For  through  tracks,  they  should 
be  placed  to  serve  each  track  at  tlie  point  or  points  where  the  rear  of  a  train  would 
nonnally  be  placed. 

(b)  Air  connections  should  be  provided  at  all  tracks  where  the  method  of  op- 
eration and  servicing  requires  that  an  air  brake  test  be  made  while  the  train  is 
standing  \\athout  locomotive  attached.  When  air  connections  are  installed,  they  should 
be  placed  at  the  same  locations  as  steam  connections.  At  stations  where  equipment 
may  be  watered,  hydrants  spaced  two  car  lengths  apart  (preferably  serving  two 
tracks)   should  be  provided. 

(c)  At  the  points  where  air  and  steam  connections  are  located  on  station  tracks, 
a  telephone  jack  may  be  provided  to  permit  the  connecting  of  the  train  telephone 
line  to  the  main  station  switchboard. 


152       Bulletin  655 — American  Railway  Engineering  Association 

6.4,6  Accessibility  and  Parking 

(a)  Street  approaches  should  receive  particular  attention  in  the  overall  planning 
to  pro\ide  convenient  access  and  sufRcient  capacity  but  by-passing  areas  of  traffic 
congestion.  Separate  routes  should  be  provided  so  that  pedestrian  traffic  and  vehicular 
traffic  can  be  safely  and  expeditiously  handled.  Ample  accommodation  for  vehicles 
handling  mail,  baggage  and  express  should  be  provided  in  a  manner  that  will  not 
impede  the  free  movement  of  public  transportation  vehicles,  private  conveyances, 
and  pedestrian  traffic. 

(b)  The  desirability  of  providing  subways  for  pedestrians  to  reach  the  opposite 
sidewalks  of  adjoining  streets  without  crossing  at  grade  should  be  considered.  Subse- 
quent installation  of  service  facilities  may  make  it  impractical  to  provide  such  pas- 
sageways in  the  future. 

(c)  Ample  provision  should  be  made  for  convenient  access  to  public  transpor- 
tation services  and  taxicab  service  within  or  adjacent  to  the  station.  It  is  essential 
that  taxicabs  be  able  to  promptly  reach  an  unloading  point,  move  freely  to  a  holding 
area,  and  to  reach  a  loading  point  for  passengers  leaving  the  station  without  inter- 
ference to  other  vehicular  traffic. 

(d)  Adequate  parking  space  convenient  to  the  station  for  railroad  patrons  is 
desirable.  In  some  places,  pay-parking  facilities  for  private  automobiles  have  been 
provided  for  the  accommodation  of  patrons.  See  AREA  Proceedings,  Vol.  60,  1959, 
page  294. 

6.5  COACH  YARDS 

6.5.1   General 

(a)  It  is  desirable  that  coach  yards  and  their  appurtenant  facilities,  incidental 
to  car  inspecting,  repairing,  battery  charging,  cleaning,  icing  and  watering,  and  all 
servicing  of  passenger  train  equipment,  should  be  an  integral  feature  of  every  large 
passenger  terminal,  whether  or  not  more  than  one  railway  is  accommodated,  and 
whether  or  not  the  forces  so  engaged  are  in  die  charge  of  the  terminal  management. 

(b)  In  some  joint  terminals  each  line  retains  jurisdiction  of  all  such  forces 
provided  for  servicing  its  own  equipment.  The  Pullman  Company  always  does  so. 
The  plan  of  having  all  servicing  of  railway  equipment  performed  with  terminal 
forces  would  seem   in  any  case  to  deserve  consideration. 

(c)  It  is  definitely  preferable  to  have  all  coach  yard  switching  performed  by 
and  under  full  control  of  the  terminal  management  in  all  cases  of  joint  operation 
where  the  coach  yard  is  an  integral  part  of  the  joint  terminal,  but  not  otherwise 
ordinarily. 

( d )  Facilities  usually  provided  in  a  coach  yard  will  in  most  cases  be  satisfactory 
for  servicing  streamline  trains  of  light  weight  non-articulated  equipment.  However, 
separate  and  specially  equipped  tracks  are  frequently  provided  for  servicing  certain 
streamline  trains,  either  articulated  or  non-articulated  which,  together  with  the 
locomotive,   are  regularly  operated  as   a   unit,   usually  in  quick  turn-around  service. 

(e)  Although  separate  facilities  may  be  provided  for  particular  trains  or  types 
of  equipment,  the  servicing  of  all  passenger  train  equipment  in  a  single  yard  is 
desirable. 

(f)  It  is  common  practice  to  hold  trains  for  cleaning  and  waiting  for  less  than 
24  hr  on  1  track. 


Manual   Recommendations 153 

6.5.2  Location 

(a)  The  coach  yard  should  be  placed  con\enient  to  the  station  and  mechanical 
facilities. 

(b)  The  location  of  a  coach  \ard  should  be  determined  by  the  economic  balance 
among  the  following  factors: 

( 1 )  Axailable  sites. 

(2)  Land  values. 

(3)  Cost  of  construction. 

(4)  Convenience  to  the  station  and  other  facilities. 

(5)  Cost  of  moving  equipment  between  station,  coach  yard  and  engine  house. 

(6)  Possible  need   for  future  expansion. 

6.5.3  Capacity 

The  capacity  required  in  a  coach  >'ard  depends  upon: 

(a)  Number  of  cars  and  trains  to  be  handled. 

(b)  Class  of  equipment. 

(c)  Standard  of  maintenance. 

(d)  Schedule  of  equipment  layoxer. 

(e)  Frequency  of  cleaning. 

6.5.4  Types 

There  are  two  general  types  of  coach  yard  layouts:  Stub  track  and  through 
track.  There  is  also  an  intermediate  type  made  up  of  through  tracks,  but  operated 
generally  as  two  systems  of  stub  tracks.  Operation  is  most  efficient  in  a  system  of 
through  tracks. 

6.5.5  Tracks 

(a)  Tracks  of  equal  length  and  equal  to  the  length  of  the  longest  trains  give 
greatest  operating  efBcienc>'. 

(b)  A  unifonii  spacing  of  not  less  than  20  ft  between  track  centers  is  desirable 
for  tracks  on  which  servicing  work  is  done.  Where  platforms  between  them  are 
obstructed  by  supports  to  overhead  service  lines,  brake  shoe  racks  or  above-platform 
service  outlets,  such  obstructions  should  be  located  off  center  of  platforms  to  provide 
a  wider  passageway  on  one  side.  Where  there  are  no  above-platform  obstructions, 
and  where  other  conditions  make  it  necessary,  the  spacing  may  be  reduced.  How- 
ever, consideration  should  be  given  to  the  clear  platform  width  required  for  the 
proper  performance  of  servicing  work  and  the  clearances  required  for  trucking 
equipment. 

(c)  Coach  yard  tracks  used  for  storage  of  extra  cars  do  not  require  particularly 
wide  spacing  or  any  special  car  servicing  features  other  than  steam  for  cold  weather 
storage  and  possibly  electricity  for  battery  charging  and  air-conditioning  equipment. 

(d)  Tracks  should  be  arranged  in  groups  at  the  leads  to  facilitate  switching. 
Auxiliary  leads  and  tail  tracks  of  ample  length  should  be  provided. 

(e)  Curvature  of  tracks  should  not  be  less  than  457-ft  radius  (12  deg  34  min) 
through  turnouts  or  otherwise. 

(f)  Coach  yard  tracks  should  be  placed  on  as  nearly  a  level  gradient  as  possi- 
ble. For  equipment  with  friction  bearings,  the  gradient  should  not  exceed  0.3  percent, 
and  for  roller  or  anti- friction  bearings  not  more  than  0.1  percent. 


154       Bulletin  655 — American  Railway  Engineering  Association 

(g)  A  wye  or  loop  track  should  be  proxided  for  turning  equipment.  Move- 
ments on  a  loop  track  are  more  expeditious. 

(h)   Special  tracks  for  making  up  or  breaking  up  trains  are  sometimes  required. 

(i)   Only  light  or  running  repairs  are  made  in  a  coach  yard. 

(j)  The  track  bed  in  coach  yards  should  be  well  drained. 

(k)  In  the  interests  of  cleanliness,  sanitation  and  possible  reduced  maintenance 
expense,  consideration  should  be  given  to  track  construction  calling  for  rails  supported 
by  longitudinal  concrete  slabs  with  paving  between  slabs  to  present  a  completely 
paved  area  which  can  be  washed.  Such  construction  is  especially  desirable  for  tracks 
at  commissary  platforms  or  on  which  diners  are  re-stocked. 

6.5.6  Platforms 

(a)  Platfomis  should  be  placed  between  all  tracks  on  which  cars  are  to  be 
serviced. 

(b)  Platform  construction  preferably  should  be  of  concrete,  crowned  not  less 
than  uj  in  to  tlie  ft.  The  width  will  vary  with  the  track  centers  and  the  type  of 
construction  supporting  adjacent  tracks.  The  edge  of  a  platform  adjacent  to  a  track 
constructed  with  ties  and  ballast  usually  is  placed  level  with  top  of  rail  and  approxi- 
mately 5  ft  6  in  from  the  center  of  the  track.  With  this  type  of  construction  a  combi- 
nation curb  and  gutter  should  be  placed  along  the  edges  of  platforms  with  gutters 
sloped  longitudinally  to  inlets  spaced  for  proper  drainage.  The  gutter  section  should 
provide  for  a  curtain  wall  of  suitable  depth  to  cut  off  excessive  seepage  to  the  plat- 
form bed.  If  any  service  lines  are  to  be  carried  below  the  surface,  the  platform  or 
curb   and  gutter  section  should  provide  for  conduits  as  required. 

6.5.7  Supply  Lines  and  Service  Outlets 

(a)  In  larger  yards  having  a  number  of  through  tracks,  and  where  it  is  desired 
to  keep  servicing  lines  below  ground,  generally  it  will  be  found  advantageous  to 
carry  the  supply  lines  across  the  yard  in  a  tunnel  or  pipe  conduit,  centrally  located 
and  with  outlet  boxes  to  serve  each  track. 

(b)  Water  hydrants  should  be  spaced  at  distances  apart  equivalent  to  the 
average  length  of  cars.  Although  hydrants  are  frequently  placed  in  alternate  spaces 
between  tracks,  there  is  substantial  advantage  in  locating  them  between  all  tracks. 
Frost  protection  should  be  provided  where  necessary.  Construction  of  water  hydrant 
outlets  should  comply  with  requirements  prescribed  by  the  United  States  Public 
Health  Service  and  other  bodies  having  jurisdiction  over  such  installations. 

( c )  Hot  water  is  usually  provided  at  convenient  locations. 

(d)  Low-pressure  air  connections  for  cleaning  should  be  spaced  the  same  as 
cold  water  hydrants.  For  testing  airbrakes,  high-pressure  air  connection  should  be 
provided  through  a  double  connection  at  the  center  of  the  track,  or  through  a  single 
connection  at  each  end  of  each  track. 

(e)  Electrical  service  outlets  in  coach  yards  having  alternately  wide  and  narrow 
track  centers,  preferably  should  be  located  in  the  center  of  tlie  narrow  service  plat- 
form. In  coach  yards  having  uniform  track  centers,  outlets  preferably  should  be 
located  at  the  edge  of  the  platform,  each  outlet  serving  only  one  track.  Direct-current 
battery  charging  outlets  when  serving  two  tracks,  should  have  two  receptacles  and 
should  be  located   at  intervals   of  one   average  car  length.   When  serving  only  one 


Manual   Recommendations  155 


track,  the  outlets  may  be  located  either  at  intervals  of  one  average  car  length,  with 
one  receptacle,  or  at  intervals  of  two  average  car  lengths,  with  two  receptacles. 
Air-conditioning  oudet  for  220-v  ac,  when  serving  two  tracks,  should  have  two 
receptacles  and  should  be  located  at  intervals  of  either  one  or  two  average  car  lengths, 
preferably  one,  along  those  tracks  used  for  servicing  either  direct-mechanical  or 
electro-mechanical  air-conditioned  passenger  cars.  When  serving  only  one  track, 
these  outlets  may  be  located  at  intervals  of  either  one  average  car  length,  with  one 
receptacle  at  each  location,  or  two  average  car  lengths,  with  two  receptacles. 

(f)  Steam  supply  connections  should  be  provided  in  the  same  manner  as  air 
cormections  for  testing  air  brakes. 

6.5.8  Inspection  and  Repair  Pits 

(a)  Where  underneadi  inspection  of  standing  cars  is  desired,  one  or  more  pits 
equal  in  length  to  the  longest  train  may  be  justified.  These  may  be  combination 
inspection  and  repair  pits  depending  on  their  location  in  the  yard.  If  underneath 
inspection  of  cars  in  motion  is  desired,  a  short  pit  located  on  the  yard  lead  or  the 
mechanical  washer  track  may  be  used.  Where  rails  are  elevated  above  adjacent 
paved  areas,  inspection  and  repair  work  will  be  facilitated  to  some  extent,  especially 
under  conditions  of  heavy  snow,  but  such  elevation  will  make  ramps  in  platform 
paving  necessary  at  fire  and  service  roadways  which  cross  the  yard. 

( b )  Pit  construction  preferably  should  be  of  concrete.  The  rails  can  rest  directly 
on  the  concrete  walls,  if  desired,  without  plates  and  cushions,  and  be  anchored  in 
place  by  bolted  down  rail  clips;  however,  better  results  will  generally  be  experienced 
with  rails  installed  on  bearing  plates  and  cushions.  The  pit  should  be  well  drained 
and  equipped  with  recessed  flood  lights  for  general  lighting  and  receptacles  for 
service   lights   and  small  tools. 

(c)  Where  all  inbound  trains  pass  over  a  single  pit  for  inspection,  other  tracks 
should  be  provided  for  servicing  and  repair  work.  Work  performed  at  such  a  single 
pit  should  be  confined  to  inspection  only  and  the  oiling  of  bearings  while  cars  are 
spotted  oxer  it  should  be  avoided  if  possible. 

(d)  Where  servicing  and  light  repair  work  is  done  on  an  inspection  pit,  several 
tracks,  each  with  a  full  train  length  pit  may  be  required,  the  number  depending 
on  tlie  number  and  schedule  of  the  trains  to  be  serviced  and  the  length  of  time  re- 
quired to  service  each  train.  A  multiple-track  pit  arrangement  should  provide  for 
several  wheel  drop  pits  with  jacking  pads  so  spaced  that  several  wheels  can  be 
dropped  simultaneously  on  any  given  track  with  a  minimum  of  car  spotting.  Each 
track  should  also  be  provided  with  the  other  facilities  for  the  complete  servicing 
of  cars,  such  as  paved  platforms,  service  outlets  for  water,  air,  steam  and  electricity, 
and  an  adequate  drainage  system. 

(e)  An  average  depth  of  pits  for  car  inspection  and  light  repairs  of  about  38 
in  below  the  top  of  running  rails  will  provide  good  working  space  below  cars, 
although  depths  ranging  from  25  to  54  in  are  in  use. 

(f)  Concrete  jacking  pads  should  be  provided  along  car  repair  track  pits.  The 
pads  should  be  built  integrally  with  the  track  pit  walls  and  extend  laterally  each 
side  a  minimum  of  6  ft,  from  the  center  of  the  track,  and  for  a  sufficient  distance 
along  the  track  each  way  from  the  drop  pits  to  provide  proper  jacking  space.  On 
track  pits  assigned  to  repair  work  only,  continuous  jacking  pads  extending  the  full 
lengtii  of  the  pit  are  desirable. 


156        Bulletin   655 — American  Railway  Engineering  Association 

(g)  An  inside  widtli  of  3  ft  for  repair  pits  will  provide  a  ledge  for  jacking  or 
blocking  on  the  inner  side  of  rails. 

(h)  A  jacking  pad,  at  least  one  car  in  length  and  continuous  between  rails  for 
center  jacking,  is  sometimes  provided  beyond  the  repair  pit  on  one  or  more  repair 
tracks. 

(i)  Consideration  should  be  given  to  covering  at  least  a  portion  of  the  area 
devoted  to  car  servicing  and  repair  work.  The  protection  afforded  by  a  building 
with  semi-covered  sides,  preferably  of  fireproof  construction,  will  reduce  the  expense 
of  conditioning  trains  and  expedite  repair  work  under  unfavorable  weather  condi- 
tions. Complete  housing  of  pits  on  tracks  assigned  to  repair  work  is  desirable,  but 
at  repair  pits  where  wheels  are  changed  or  truck  work  is  performed  the  housing 
should  be  at  least  sufficient  to  cover  a  car  spotted  either  way  over  tlie  wheel  drop  pits 
and  provide  a  passageway  at  end  of  car.  The  extent  of  the  enclosure  and  heating 
should  depend  on  the  severity  of  the  climate. 

( j )  At  coach  yards  where  locomotives  operating  on  unit  or  streamline  trains  are 
handled,  special  facilities  usually  are  necessary.  These  facilities  depend  upon  the 
types  of  locomotive  equipment  and  the  service  required. 

6.5.9  Other  Facilities 

(a)  The  yard  should  be  sufficiently  lighted  for  night  operation.  General  lighting 
can  be  provided  by  flood  lights  on  high  poles  or  towers,  or  by  lights  suspended  well 
above  top  of  car  level  and  spaced  about  a  car  length  apart  between  tracks.  General 
lighting  at  lower  levels  is  less  satisfactory  than  higher  level  lighting  because  of 
shadows,  improper  light  for  top  of  car  work  and  interference  with  switching  and 
other  operations  due  to  glare.  However,  when  the  general  lighting  system  cannot 
be  adapted  to  provide  the  additional  light  frequently  desired  at  certain  points  in 
the  yard,  supplemental  lights  on  low  standards,  either  fixed  or  portable,  may  be 
used. 

(b)  Provision  should  be  made  for  sufficient  storage  of  car  wheels.  Double  wheel 
tracks  for  mounted  wheels  should  be  spaced  6  in  between  track  centers.  If  extra 
or  replacement  power  units  or  trucks  are  stored  on  wheel  tracks,  adequate  housing 
for  tliese  units  should  be  provided. 

(c)  A  mechanical  train  washer  is  well  adapted  to  washing  the  sides  of  trains, 
especially  streamline  trains,  including  diesel  locomotives.  Mechanical  washing  of 
train  roofs  is  also  desirable,  but  due  to  variations  in  car  heights  and  roof  contours, 
as  well  as  to  numerous  roof  obstructions  on  present  equipment,  mechanical  washing 
is  usually  confined  to  the  sides,  roofs  and  ends  being  washed  by  hand.  The  track 
served  by  a  mechanical  washer  should  be  tangent  through  the  washer  and  for  at 
least  one  car  length  each  way.  Wliere  possible,  the  washer  should  be  at  a  fixed  loca- 
tion on  a  track  over  which  all  inbound  trains  to  be  washed  can  be  moved.  Where 
conditions  make  it  necessary  however,  a  washer  of  the  portable  type,  mounted  on 
cross  rails  to  serve  two  or  more  tracks  may  be  used.  Separate  washing  platforms 
are  usually  provided  for  locomotives  which  do  not  lend  themselves  to  mechanical 
washing. 

( d )  Suitable  cleaning  facilities  should  be  provided  for  rugs  and  carpets  which 
are  removed  from  cars  for  cleaning.  Air  cleaning  is  usually  done  on  open  platforms, 
preferably  roofed  over,  but  shampooing  facilities  should  be  enclosed. 


Manual   Recommendations  157 

(e)  Car  pullers  are  frequently  provided  to  reduce  switching.  The  portable, 
electric-powered  t>pe  is  flexible  and  well  adapted  to  this  serxice. 

(f)  In  >ards  where  diners  are  restocked,  c()mniissar\-  facilities  will  be  required. 

(g)  Other  facilities,   some  or  all  of  which  may  be  needed,  include: 

( 1 )  Service  building  pro\iding  offices,  toilet,  wash,  locker  and  lunch  rooms 

( 2 )  Storehouse 

(3)  Building  proxiding  space  for  necessary  repair  shops 

(4)  Refuse  disposal 

(5)  Fire  protection 

(6)  Bottling  plant  for  refilling  gas  c\linders 

(7)  Locomotive  fuel  oil  storage  with  lines  to  distributing  points. 

6.6  MODERNIZATION 

(a)  Because  of  changes  in  habits  and  in  facilities  available  for  travel  to  and 
from  terminals,  less  waiting  time  in  tlie  station  is  now  the  rule,  but  passengers  expect 
better  and  more  modern,  though  not  necessariK^  bigger  accommodations  in  the  con- 
course and  waiting  room,  when  buying  tickets  or  checking  baggage,  in  the  toilet 
facilities  and  in  general  serxice  conxeniences.  These  should  be  proxided  xxhen 
major  changes  are  made. 

(b)  A  single,  combined,  xxaiting  room  can  be  substituted  to  adxantage  for  the 
old  arrangement  of  txxo  separate  rooms,  but  a  proper  and  attractixe  poxxder  room 
for  xvomen  should  be  proxided. 

(c)  Substitution  of  a  closed-in  concourse,  xvith  a  tight  partition  betxxeen  it 
and  the  train  shed  in  place  of  an  open  grill,  xvidi  a  sufficient  supply  of  heat  to  make 
it  comfortable  for  passengers  in  winter  xxeather  is  desirable  and  is  becoming  a  general 
practice,  as  it  xvill  permit  the  use  of  die  concourse  as  an  adjunct  to  die  xvaiting 
room.  Many  passengers  prefer  to  xxait  xvhere  they  can  see  the  trains  if  they  can  do 
so  xvithout  discomfort. 

(d)  Care  should  be  taken  to  make  it  inconxenient  for  non-passengers  to  use 
tlie  concourse  and  passages  as  tlioroughfares,  as  such  use  may  interfere  xvith  patrons 
of  the  railroads. 

(e)  Directional  signs  should  be  gixen  particular  attention.  They  should  be 
displayed  conspicuously,  easy  to  see  but  not  gaudy,  and  they  should  be  repeated  so 
that  if  a  passenger  going  in  die  xvrong  direction  misses  one,  another  farther  along 
xvill  set  him  right.  This  is  especially  important  xvhere  corridors  are  long  and  xvinding 
and  facilities  are  at  different  lexels. 

(f)  Improvement  at  the  ticket  counter  by  the  substitution  of  larger  openings 
for  the  foniier  narrow  grilled  xvindoxvs  or,  at  points  xvhere  it  is  feasible  to  do  so, 
the  replacement  of  the  xvindoxvs  and  grills  by  an  open  counter  makes  for  a  more 
friendly  atmosphere.  Provision  for  protection  of  the  money  and  the  ticket  stock 
should  not  be  overlooked. 

(g)  Generally,  coin-locked  pa>'  toilets  should  be  substituted  for  some  of  die 
former  free  toilets  and,  at  the  larger  terminals  at  least,  coin-locked  dressing  rooms 
and  baths  may  be  provided  xx'here  xxarranted. 

(h)  Substitution  of  air  conditioning  (heating  and  cooling),  properly  planned, 
will  often  result  in  a  reduced  cost  for  its  operation  and  maintenance,  as  xxell  as  pro- 
viding better  service. 


158       Bulletin   655 — American   Railway  Engineering  Association 

(i)  Adequate  provision  for  parking  private  automobiles  while  waiting  for  trains 
should  be  provided  if  practicable. 

(j)  During  a  modernization  program,  consideration  should  be  given  to  possi- 
bilities of  overloading  the  existing  electric,  water,  and  steam  facilities.  Provisions 
should  be  made  to  increase  the  capacity  of  these  facilities  to  a  safe  level. 


Manual   Recommendations 159 

Part  7 
Other  Yard  and  Terminal  Facilities 


FOREWORD 


Tliis  part  deals  with  the  several  and  various  components  necessary  for  the 
function  and  operation  of  railways.  Although  these  components  such  as  store  facili- 
ties, material  yards,  etc.  are  normally  located  or  situated  in  yards  and  terminals 
they  are  not  intrinsic  to  them. 


CONTENTS 

Section  Page 

7.1  Stores    160 

7.2  Storage    160 

7.3  Reclamation    161 


160       Bulletin  655 — American  Railway  Engineering  Association 

7.1  STORES 

7.1.1  General 

The  stores  department  is  responsible  for  the  ordering,  care,  control  and  economic 
distribution,  and  in  some  instances  for  the  accounting  of  materials  and  supplies 
needed  for,  or  reclaimed  from,  the  constiuction,  maintenance  and  operation  of  the 
railroad.  The  size  and  extent  of  its  facilities  will  vary  in  accordance  with  the  require- 
ments of  the  road.  It  is  important  to  consult  tlie  chief  stores  officer  and  receive  his 
approval  concerning  any  plans  for  the  construction,  alteration  or  elimination  of  stores 
facilities. 

7.1.2  Types 

There   are  three  types   of  stores,  namely,  general,   district,  and  local. 

(a)  The  general  store,  also  known  as  a  system  or  regional  store,  is  the  largest 
store  umt  of  the  stores  department.  It  should  be  located  on  available  railroad  prop- 
erty and  usually  at  a  convenient  point  where  large  quantities  of  materials  and  supplies 
can  be  efficiently  received,  handled,  stored  and  shipped.  The  location  of  tliis  store 
will  also  be  greatly  influenced  by  the  traffic  problem  created  in  the  handling  of  these 
shipments  and  by  the  freight  charges  involved  on  off-line  items  received.  The  general 
store  will  also  operate  reclamation  and  scrap  yards  where  needed. 

(b)  The  district  and  local  stores  have  the  same  characteristics  and  functions 
as  the  general  stores,  except  that  they  are  much  smaller.  These  stores  are  generally 
established  on  larger  railroads  at  various  points  to  expedite  the  handling  of  materials 
and  supplies.  Such  stores  operate  under  the  jurisdiction  of  the  general  store. 

Stationary,  office  supplies  and  maintenance  of  way  materials  are  nonually  han- 
dled by  the  general  store.  Maintenance-of-way  materials,  however,  are  generally 
handled  in  separate  facilities.  Dining  car  service  supplies,  including  foodstuffs,  may 
be  handled  by  the  general  store,  but  in  many  instances  such  items  are  handled 
separately  at  major  terminals  in  a  local  store,  called  a  commissary. 

7.1.3  Buildings  and  Structures 

Storehouse  buildings  for  the  handling  of  all  materials  requiring  inside  storage 
should  be  constructed  so  as  to  create  the  most  efficient  and  expeditious  material 
storage  and  handling  methods.  Office  space  to  house  the  necessary  personnel  to  handle 
the  records  and  accounting  for  the  store's  operation  may  be  part  of  a  storehouse 
building  if  suitable.  Platform,  docks,  ramps,  racks  and  shelters  are  erected  according 
to  the  needs.  All  storage  buildings  and  related  facilities  should  be  served  with  tracks 
and  hard-surface  driveways  for  tlie  efficient  handling  of  materials  by  rail  or  by 
truck.  It  is  often  possible  to  pave  the  track  area  so  that  one  platform  at  car-floor 
level  can  serve  both  means  of  handling. 

7.2  STORAGE 

7.2.1  Material  Yards 

Theie  are  numerous  items  used  in  maintenance  of  way  and  of  equipment  that 
can  be  stored  out  of  doors;  these  items  are  handled  in  material  yards.  Whenever 
possible,  such  yards  should  be  located  adjacent  to  the  storehouse  area  so  that  track- 
age can  be  kept  to  a  minimum.  Material  is  stored  on  permanent  racks  and  platforms, 
and  the  areas  between  should  be  paved  to  facilitate  tlie  operation  of  rubber-tired 
handling  equipment  such  as   trucks,  loaders,  cranes,  etc. 


Manual  Recommendations 161 

The  storage  of  heavy  items  in  a  material  yard  is  usually  at  a  separate  loaition 
served  by  at  least  two  tracks  and  an  overhead  crane  or  other  types  of  cranes  of 
suitable  capacity.  The  material  is  stored  in  tlie  area  between  the  tracks,  one  track 
being  used  for  recei\  ing,  the  other  for  shipping. 

The  ideal  scrap  \ard  has  a  receiving  and  a  shipping  track  w  ith  the  sorting  area 
in  between  and  serxed  by  an  overhead  crane  of  suitable  capacity.  The  sorting  area 
should  be  hard  surfaced  and  the  driveways  serving  it  pa\ed  to  support  die  heavy 
wheel  loadings  of  truck  cranes  and  trailers  used  to  handle  scrap  within  the  yard. 
All  cranes  should  be  equipped  with  magnets. 

7.2.2  Lumber  and  Timber  Yards 

Lumber  products  are  not  generally  kept  in  large  quantities  at  the  general  store- 
house, but  are  frequently  shipped  direct  from  the  dealer  to  the  point  of  application. 
However  a  certain  quantiU'  of  lumber,  cross  and  switch  ties,  bridge  timber  and  poles 
must  be  stored.  These  products  require  outside  storage;  unseasoned  materials  should 
be  stored  on  permanent  racks  in  covered  storage  so  they  can  season  properly;  treated 
timbers  should  be  stored  in  the  manner  approved  by  the  stores  department  to  prevent 
loss  by  fire.  The  areas  between  the  racks  should  be  paved  and  the  piles  so  arranged 
that  fork-lift  tractors  or  truck  cranes  can  handle  these  materials  into  and  out  or 
onto  and  off  freight  equipment  on  a  track  serving  the  storage  yard.  This  track  is 
usually  in  the  center  of  the  yard  unless  the  area  is  too  large,  tlien  two  or  more  tracks 
serving  storage  areas  on  botli  sides  of  each  track  are  required,  and  tlie  tracks,  if 
possible,  are  connected  at  both  ends. 

7.2.3  Reser\e  Oil 

The  stores  department  may  be  called  upon  to  provide  large  storage  reserves  for 
fuel  oils.  When  the  size  and  location  of  die  facilities  have  been  determined,  the  tanks 
should  be  installed  in  accordance  with  the  requirements  set  forth  by  the  governing 
ordinances,  building  and  fire  codes. 

7.3  RECLAMATION 

7.3.1  Plant— General 

The  reclamation  plant  is  usually  located  at  the  same  point  and  adjacent  to  the 
scrap  yard  to  minimize  handling  of  materials.  The  reclamation  shop  building  sliould 
be  situated  between  a  receixing  and  a  shipjjing  track,  the  latter  depressed  to  facilitate 
the  loading  of  materials  coming  out  of  die  plant  for  forwarding  to  points  of  applica- 
tion or  storage.  The  size  of  the  shop  will  vary  with  the  amount  and  type  of  reclama- 
tion to  be  done.  Paved  roads  parallel  to  the  tracks  are  needed  for  the  operation  of 
truck  cranes;  a  large  area  adjacent  to  the  tracks  arjd  the  shop  building  should  be 
paved  so  that  materials  can  be  transported  in  and  out  of  the  building  with  motorized 
equipment. 

7.3.2  Rail  Plant 

Rail  requires  special  handling  in  general  reclamation,  and  the  plant  to  handle 
it  should  be  separate  from  odier  plants.  The  plant  layout  should  be  designed  for  the 
rapid  turnover  of  rail  and  would  consist  of  receiving  and  shipping  tracks  served  by 
overhead  or  other  types  of  cranes,  with  the  area  between  the  tracks  used  for  die 
straightening  presses,  the  cropping  operation,  drilling  rack,  hardening  apparatus, 
welding  and  classifying  prior  to  loading. 


162       Bulletin  655 — American  Railway  Engineering  Association 

Manual  Recommendations 
Committee  6 — Buildings 

Report  on  Assignment   1 

Design  Criteria  for  Maintenance  of  Way 
Equipment  Repair  Shops 

J.  G.  Robertson  (chairman  suhcommittee),  W.  F.  Armstrong,  D.  A.  Bessey,  S.  B. 
Holt,  K.  E.  Hornung,  P.  W.  Peterson,  L.  A.  Palagi,  R.  F.  Roberts,  H.  A. 
Shannon. 

Your  committee  submits  for  adoption  the  following  new  Part  9  for  Chapter  6 
of  the  Manual. 

Part  9 

Design  Criteria  for  Centralized  Maintenance  of 
Way  Equipment  Repair  Shops 

9.1  FOREWORD 

9.1.1  A  maintenance  of  way  equipment  repair  complex  provides  a  facility  for 
the  overhauling,  rebuilding  and  modifying  of  roadway  machines,  work  equipment 
and  specialized  power  tools,  which  are  used  in  maintenance  of  way  operations. 

9.2  SCOPE  AND  PURPOSE 

9.2.1  The  purpose  of  these  criteria  is  to  provide  a  description  and  layout  of 
facilities  for  a  centralized  work  equipment  shop  and  to  recommend  equipment  service 
areas.  Figures  1,  2  and  3  are  shown  as  aids  in  visualizing  a  typical  repair  shop  and 
tlie  layout  of  equipment   and  service  areas. 

9.2.2  Heating,  lighting,  plumbing  and  other  incidental  mechanical  items  would 
be  a  part  of  tliese  buildings;  however,  they  are  not  included  in  tliese  criteria. 

9.3  OPERATIONS 

9.3.1  The  major  operations  perfonned  in  a  centralized  maintenance  of  way 
repair  complex  are  dismantling,  cleaning,  repairing,  reassembling  and  painting. 

9.3.2  These  operations  are  supported  by  other  incidental  services,  such  as, 
carpentry,  steel  fabricating,  forging,  welding,  testing,  etc.,  in  order  to  make  it  pos- 
sible to  perform  minor  repairs  to  small  tools,  as  well  as  major  overhauls  to  self- 
powered  equipment. 


Manual   Recommendations 163 

9.4  LOCATION 

9.4.1  The  location  of  a  centralized  work  equipment  shop  should  be  as  close 
to  the  center  of  tlie  railroad  as  practical,  with  consideration  being  given  to  the  avail- 
ability  of  suitable  land,   rail  service,   available  manpower,   housing,   etc. 

9.4.2  Approximately  25  acres  are  required  for  a  large  complex. 

9.4.3  Some  railroads  have  converted  existing  shop  buildings  into  maintenance 
of  way  equipment  repair  shops  and  when  tliis  is  done,  the  location  of  the  repair 
complex   may  not  be   at  the   most  desirable  location. 

9.4.4  If  existing  buildings  are  to  be  used,  consideration  should  be  given  to  the 
amount  of  tra\el   time   required   to  bring  the  equipment  into  the  shop. 

9.5  ORGANIZATION 

9.5.1  The  shop  is  normally  a  part  of  the  engineering  department  and  operates 
under  tlie  jurisdiction  of  the  chief  engineer,  with  the  superintendent  of  work  equip- 
ment as   the  immediate  superxisor. 

9.5.2  On  a  large  railroad,  the  superintendent  and  staff  will  operate  a  shop  of 
200  employees,  more  or  less,  of  various  crafts. 

9.5.3  On  a  small  railroad,  fewer  employees  are  required  to  perform  the  necessary 
operations;    howexer,    the    organization    would    remain    essentially    the    same. 

9.6  TYPICAL  FACILITY  ARRANGEMENT 

9.6.1  The  complex,  as  shown  in  Figure  1,  is  comprised  of  three  buildings  with 
adequate  support  facilities,  such  as  cleaning  vats,  storage  areas,  lead  and  yard  tracks. 

9.6.2  Building  1  is  the  wash  area  and  houses  the  cleaning  vats.  Building  2  is 
the   main  shop,   which  is   shown  on   Figure  2,   and  building  3   contains  the  offices. 

9.6.3  The  main  shop  building  should  be  constructed  to  support  the  overhead 
cranes   and  other  smaller  cranes  throughout  the  shop. 

9.6.4  Buildings  1  and  2  should  be  adequately  equipped  with  compressed  air, 
oxyacetyiene  and  electric  arc  welding  outlets  at  convenient  locations,  and  they 
should  have  overhead  motorized  doors  of  sufficient  size  so  as  not  to  restrict  the 
movement  of  large  equipment  in  and  out  of  the  buildings. 

9.7  MATERIAL  HANDLING  EQUIPMENT 

9.7.1  Material-handling  equipment  is  a  prime  necessity  since  units  weighing 
up  to  150  tons  may  be  handled.  The  shop  buildings  should  have  overhead  traveling 
cranes,  bracket  cranes,  and  post  cranes  for  the  movement  of  material  within  the 
\arious  areas.  An  8-ton  wagon  crane  is  recommended  for  inaccessible  areas.  Small 
turntables  at  strategic  locations  should  be  placed  within  the  shop  to  facilitate  the 
moving  of  equipment  to  various  tracks. 

9.7.2  A  three-wheeled  cart  with  flat  bed  in  the  back  is  recommended  to  trans- 
port individual  parts.  Fork  lifts  are  recommended  to  move  material  on  pallets.  Full 
size  railroad  cars,  such  as  riding  cars,  flat  cars,  weed  spray  cars,  and  similar  track- 
mounted  equipment  may  be  moved  over  the  shop  tracks  by  use  of  a  heavy  duty 
rubber  tire  tractor  or  shop  mule. 

9.7.3  Figure  3  lists  special  siioiDS,  equipment  rej^air  and  the  material  handling 
equipment  recommended  for  each  area. 


164       Bulletin  655 — American  Railway  Engineering  Association 

9.8  PAINT  SHOP  (AREA  "A") 

9.8.1  Machines,  when  repaired,  are  painted  and  stenciled  in  this  shop.  It  should 
be  equipped  with  a  ramp  or  hoist  to  allow  painting  the  underside  of  machines  and 
have   adequate  bracket  cranes. 

9.8.2  The  painting  should  be  performed  in  a  booth  of  sufficient  size  to  accom- 
modate the  largest  piece  of  equipment  expected  to  be  repaired.  The  shop  should 
also  have  air  filtration  equipment  to  dissipate  the  paint  fog  to  prevent  its  being 
exhausted  into  the  atmosphere. 

9.8.3  A  sprinkler  or  fire-suppression  system,  explosion-proof  lighting,  heating 
and  ventilation  equipment  should  be  provided,  as  required  by  local  codes  and 
regulatory  agencies. 

9.8.4  The  paint  shop  operation  should  be  supported  by  steam  cleaning  and 
washing  facilities.  Provide  facilities  in  the  drainage  system  to  accumulate  sludge  and 
oil. 

9.9  CARPENTER  SHOP  (AREA  "B") 

9.9.1  All  wooden  assemblies  for  roadway  machines  and  work  equipment  are 
fabricated,  or  repaired,  in  this  area,  including  repairs  to  wooden  portions  of  motor- 
car decks. 

9.9.2  All  boxes  and  crates  are  made  in  this  area  for  items  requiring  tliem,  and 
wooden  shields  installed  on  windshield  glasses  to  protect  them  from  vandalism 
during  shipment. 

9.9.3  Canopy  tops,  windshields,  electric  windshield  wipers,  and  lights  are 
installed  on  motor  cars  after  they  have  been  released  from  Motor  Car  Repair  Area  "C". 

9.9.4  All  replacement  of  glass  and  repairs  to  seats  and  canvas  items  are  made 
in  this  area,  which  should  contain  a  canvas  rack,  large  cutting  table  and  an  industrial- 
type  sewing  machine. 

9.10  MOTOR  CAR  REPAIR  (AREA  "C") 

9.10.1  In  this  area  motor  cars  are  stripped,  repaired  and  reassembled.  Area 
should  be  equipped  with  a  single  dry  pedestal  grinder,  solvent  vat,  test  stands,  work 
bench,  hydraulic  press  and  sufficient  storage  for  new  and  rebuilt  engines  and  trans- 
missions. 

9.11  SHOP  EQUIPMENT  REPAIR  AND  MAINTENANCE  (AREA  "D") 

9.11.1  This  area  should  have  adequate  work  benches  and  material  storage  bins 
for  the  maintenance  machinist  in  charge  of  repairs  to  shop  machines,  cranes,  power 
plant   and   other   terminal   facilities. 

9.11.2  The  area  should  be  equipped  for  storing  and  handling  of  materials  needed 
by  shop  electricians  in  their  terminal  maintenance  work. 

9.11.3  All  electrical  assemblies  from  light  plants  and  electric  welders,  electric 
power  tools,   and  track  maintenance  junction  boxes  are  repaired  in  tliis  area. 

9.12  PAINT  SHOP  STORAGE  (AREA  "E") 

9.12.1  This  area  is  used  for  the  storage  of  non-flammable  paint  supplies,  stencils, 
brushes,  etc.  The  flammable  materials  are  stored  in  a  room  adjacent  to  Area  "A",  on 
the  outside  of  the  main  building. 


Manual   Recommendations 165 

9.12.2  Particular  attention  should  he  given  to  this  area  with  regard  to  insurance 
and  local  fire  regulations. 

9.12.3  A  sprinkler  system  or  fire-suppression  system  should  be  considered. 

9.13  ENGINE  REBUILD  AREA  (AREA  "F") 

9.13.1  All  large  gasoline  and  diesel  engines  are  stripped,  repaired,  reassembled, 
and  such  items  as  carburetors,  fuel  pumps,  and  air  cleaners  are  rebuilt  in  this  area. 

9.13.2  Machine  work  is  performed  in  this  shop,  such  as  reboring  cylinders,  line 
boring  of  main  bearings,  grinding  and  fitting  of  pistons,  fitting  and  applying  wrist 
pins,  facing  of  \al\e  seats,  grinding  of  valves,  and  reassembling  block  and  internal 
engine  parts. 

9.13.3  One-  and  two-cylinder  air-cooled  engines,  rail  saws,  small  light  plants 
and  other  such  items  are  repaired  and  tested  in  this  area  on  an  engine  test-out  stand. 

9.13.4  Large  gasoline  and  diesel  engines  should  be  tested  on  engine  dynamome- 
ter test  stands  and  fine  adjustments  made  before  engines  are  released  from  the  shop. 
Engines  should  be  broken  in  at  full  operating  RPM's  for  approximately  four  hours 
before  being  taken  off  the  test  stands. 

9.13.5  Noise  and  air  pollution  are  important  factors  in  the  design  of  this  area, 
which  must  be  in  compliance  with  local  codes  and  regulatory  agencies. 

9.13.6  Standby  and  repaired  engines  should  be  stored  in  this  area  until  needed. 
All  single-  and  twin-cylinder  track  motor-car  engines  are  stripped,  reworked  and 
reassembled. 

9.13.7  Provide  a  25-ton  hydraulic  press  and  engine  rebuilding  stands  to  facilitate 
the  handling  of  engine  units  while  they  are  undergoing  repairs  and  testing. 

9.13.8  Provisions  should  be  made  for  storage  of  gas  and  diesel  engine  and 
transmission  assemblies.  Repaired  assembUes  are  either  used  at  the  facility  or 
shipped  to  line  of  road  for  installation  on  out-of-service  machines. 

9.14  MACHINE  SHOP  (AREA  "G") 

9.14.1  This  shop  should  be  equipped  with  various  types  and  sizes  of  lathes, 
boring  mills,  drill  presses,  grinders,  milling  machines,  hydraulic  press  with  a  capa- 
bility of  handling  any  and  all  types  of  machine  work  required  by  centralized  work 
equipment  shop. 

9.15  HYDRAULIC  AND  ELECTRIC  REPAIR  (AREA  "H") 

9.15.1  All  hydraulic  assemblies  and  component  parts  stripped  from  engines 
are  placed  on  pallets  and  moved  to  the  receiving  area  of  this  shop,  where  all  makes 
and  types  of  hydraulic  equipment,  such  as  pumps,  rams,  valves  and  motors  are 
rebuilt. 

9.15.2  This  area  should  be  easy  to  clean  so  tliat  dust  will  be  kept  to  a  minimum. 

9.15.3  A  complete  parts  inventory  of  all  hydraulic  assemblies  and  components 
are  maintained  in  the  shop. 

9.15.4  This  area  should  be  equipped  with  a  hydraulic  test  stand  on  which  rebuilt 
as.semblies  can  be  tested  before  they  are  released  for  reinstallation  on  the  individual 
machines  undergoing  repair,  or  placed  in  the  hydraulic  unit  storage  area. 


166       Bulletin   655 — American  Railway  Engineering  Association 

9.15.5  All  hydraulic  hoses  used  in  connection  with  repairs  to  the  equipment 
throughout  the  entire  complex  are  fabricated  in  this  area.  The  area  should  be 
equipped  with  adequate  hose  and  fitting  storage  bins,  band  saw,  hydraulic  press, 
drill  press,   grinders,   a   hose   cut-off   machine   and   hose   fitting   application   machine. 

9.15.6  Provision  should  be  made  for  the  rebuilding  of  all  electric  vibrator  motors 
and  main  tamping  generators  from  track  maintainers  and  tamping  power  jacks.  The 
area  should  have  an  overhead  trolley  system  to  allow  the  motors  and  generators  to 
be  stripped,  reassembled  and  tested  on  an  "assembly  line"  basis. 

9.15.7  Provision  should  be  made  for  hydraulic  presses  strategically  placed, 
double  dry  grinders,  stator  coil  cutter  and  sand  blast  cabinet  for  cleaning  stator 
housings   after  the   coils   have   been  removed. 

9.15.8  Vibrator  motor  test  stand  should  be  provided  that  will  permit  several 
motors  to  be  tested  simultaneously. 

9.15.9  An  approved  type  furnace  for  removal  of  insulation  from  copper  wire 
should  be  provided. 

9.15.10  Space  should  be  provided  for  a  large  and  small  insulation  cutter,  insu- 
lation folder,  coil  winder  drives,  coil  taping  machine,  stator  hold  stands  and  an 
approved  type   furnace   for  removal  of  insulation  from  scrap  stator  coils. 

9.15.11  Large  tamping  motor  generators  are  tested,  and  all  rewound  stators, 
armatures  and  field  windings  are  dipped  into  insulating  varnish  and  baked  in  an  oven. 

9.16  LUNCH  AND  LOCKER  ROOMS  (AREA  T) 

9.16.1  Lunch  and  locker  room  facilities  should  be  provided  as  required  by 
applicable  codes,  and  provisions  should  also  be  made  for  lunch  tables  and  vending 
machines. 

9.17  TOILET  FACILITIES  (AREAS  "J"  AND  "Q") 

9.17.1  Toilet  facilities  and  water  coolers  should  be  provided  for  shop  forces 
at   centralized   locations    to   minimize   the   away-from-work   station   time. 

9.17.2  The  number  of  fixtures  required  is  governed  by  applicable  codes  and 
will  vary  depending  on  the  location. 

9.18  TOOL  ROOM  (AREAS  "K"  AND  "P") 

9.18.1  Tool  room  or  rooms  with  required  security  are  to  be  conveniently  located 
to  the  shops  they  sei^ve,  and  should  stock  all  power  and  hand  tools  used  throughout 
the  various  areas. 

9.19  STORES  OFFICE  (AREA  "L") 

9.19.1  A  stores  office  large  enough  to  accommodate  tlie  storekeeper  and  staff 
should  be  provided  adjacent  to  die  store  area. 

9.20  STORE  AREA  (AREA  "M ") 

9.20.1  The  store  area  should  be  located  as  near  as  possible  to  the  center  of  the 
complex   and   should  be   complete   with  racks   and  bins. 

9.20.2  Proper  attention  should  be  given  to  providing  adequate  security. 


Manual  Recommendations 167 

9.21  STEEL  FABRICATION  AREA  (AREA  "N") 

9.21.1  Space  should  be  provided  for  use  as  a  repair  and  test  area  for  all  types 
of  radiators   and  fuel   tanks.   A  cleaning  and  test  vat  should  be  provided. 

9.21.2  Adjustable  booths  should  be  provided  for  steel  fabrication  or  repair  of 
assemblies  made  by  boilermakers.  Individual,  5-ft-high,  canvas  or  plastic  shields 
should  completely  surround  each  booth  to  protect  other  employees  from  the  electric 
flash  created  by  wire  fed  welders. 

9.21.3  Space  should  be  allocated  for  storage  racks  for  bar  steel,  sheet  steel, 
angle  iron  and  pipe. 

9.22  SHEET  METAL  SHOP  (AREA  "O") 

9.22.1  All  sheet-metal  fabrication  work  and  repairs  to  the  sheet-metal  guards 
and  shrouds  for  various  machines  are  performed  in  this  shop.  Area  should  be  equipped 
with  adequate  machinery  to  handle  any  and  all  types  of  sheet-metal  work. 

9.23  BLACKSMITH  SHOP  (AREA  "R") 

9.23.1  An  electronic  eye  semi-automatic  shape  cutting  machine  should  be 
located  in  tliis  shop,  complete  with  steel  racks,  a  large  heating  furnace  and  a  machin- 
ist welding  booth,  where  tamping  shoes  are  reclaimed. 

9.23.2  A  forge,  a  large  and  small  hammer,  double  dry  grinder,  welding  booths, 
exliaust  ducting,  a  normalizing  furnace,  and  other  equipment  and  storage  areas,  as 
outlined  on  Figure  3,  should  be  located  in  tiiis  area. 

9.24  CONCLUSION 

9.24.1  The  maintenance  of  way  equipment  repair  complex,  as  outlined  in  these 
criteria,  is  representative  of  an  entirely  new  facility.  It  is  realized,  however,  that 
existing  facilities  may  be  converted  to  a  repair  shop,  and  the  configuration  of  the 
yards  and  buildings  may  not  be  ideally  suited  for  performing  the  repair  work  on  an 
assembly  line  basis.  Some  repair  facilities  are  located  in  smaller  shops  at  outlying 
districts,  which  cannot  adequately  serve  the  needs  of  the  entire  railroad,  but  an 
attempt  should  be  made  to  arrange  the  shop  similar  to  diose  in  Figures  1  and  2, 
to  minimize  unnecessary  movement  of  material  and  equipment. 


168       Bulletin  655 — American  Railway  Engineering  Association 


\ 

o 

o 

o 

J 

V          OB 

o   \ 

N 
\ 

^   s\  \\\^J 

iLil 


^  r    ,009  )r-^r 


-^r^r 


I  I  I 
I  '  I 

I  I  I 
i-i 


I  I  I 


rrrrj 


1 1 

\  \ 
\  \ 
\  \ 
\  \ 


\ 


\ 


M^ 


T~i" 


-J 


.1-1 


I 
I 
I 


/     / 


.    \    \ 


\ 


/     / 
/     / 
'     I 
I     I 
/     I 
/     / 
/     / 
/      / 

// 


\ 


\\ 


\\         \  (  / 

^  // 


/  / 

/  / 


Manual  Recommendations 


169 


Figure  2 


170       Bulletin  655 — American  Railway  Engineering  Association 


Figure  3— LEGEND  OF   DETAILS  FOR  TYPICAL  MAINTENANCE  OF  WAY 
EQUIPMENT  REPAIR  FACILITIES 


A.  PAINT  SHOP 

1.  Paint  Storage 

2.  Filter  Ducting 

B.  CARPENTER  SHOP 

1.  Carpenter  Shop  Storage 
2-5.  Lumber  and  Trailers 

6.  Plywood  Rack 

7.  Work  Bench 

8.  Table  Saw 

9.  Planer 

10.  Radial  Arm  Saw 
H.  Band  Saw 

12.  Glass  Rack 

13.  Upholstery  and  Canvas  Shop 

14.  Packing  and  Crating  Area 

C.  MOTOR  CAR  REPAIR 

1.  Solvent  Vat 
2-3.  Test  Stands 

4.  Work  Bench 

5.  Engine  &  Transmission  Storage 

6.  Hydraulic  Press 

D.  SHOP  EQUIPMENT  REPAIR  & 

MAINTENANCE 

E.  PAINT  SHOP  STORAGE 

F.  ENGINE   REBUILD  AREA 

1-6.  Diesel  Engine  Rebuild  Area 

7.  Assembly  Bench 

8.  Line  Boring  Machine 

9.  Pin  Fitter 

10.  Valve  Grinder 

11.  Cylinder   Boring  Machine 
12-13.  Cleaning  Solvent  Vat 

14.  Carburetor  Repair 
15-18.  Gas  Engine  Rebuild  Area 

19.  Dynamometer  Storage  Area 

20.  Dynamometer  Test  Stands 

21.  Gas  Engine  Storage  Area 

22.  Diesel  Engine  Storage  Area 

G.  MACHINE  SHOP  AREA 

1.  Storage  Area 
2-7.  Lathe  Area 

8.  Metal  Spray  Bench 

9.  Crankshaft  Grinder 

10.  Surface  Grinder 

11.  Horizontal  Miller 

12.  Layout  Table 

13.  Universal  Grinder 


14.  Internal  Grinder 

15.  Universal  Miller 

16.  Machine  Shop  Storage  Area 
17-18.  Drill  Press 

19.  Layout  Bench 

20.  Double  Dry  Grinder 

21.  Boring  Mill 

22.  Band  Saw 

23.  Tubing  and  Steel  Rack 

24.  Hydraulic  Press 

25.  Tool  Grinder 

H.  HYDRAULIC  AND  ELECTRICAL 
REPAIR  AREA 

1.  Tested  Unit  Storage  Area 

2.  Test  Bench 

3.  Bench 

4-7.  Hydraulic  Units  Repair  Area 

8.  Hydraulic  Shop  Work  Storage 
Area 

9.  Hydraulic  Hose  Cutting  Bench 

10.  Hydraulic  Hose  Fabrication 
Area 

11.  Storage  Area 

12.  Hose  and  Fitting  Bins 

13.  Oven 

14.  Wire  Rack 

15.  Coil  Winders 

16.  Dip  Vat 

17.  Sandblast  Cabinet 

18.  Battery  Room 

19.  Generator  and  Motor  Repair 
Area 

20.  Sim  Test  Stand 
21-22.  Rewind  Bench 

L    LUNCH  ROOM 
J.    TOILET  FACILITIES 
K.  TOOL  ROOM 
L.  STORES  OFFICE 
M.  STOREHOUSE 
N.  SHEET  STEEL  FABRICATION 
AREA 

1.  Radiator  &  Fuel  Tank  Repair 
Area 
2-5.  Adjustable  Booth  for  Steel 
Fabrication 

6.  Bar  Steel  &  Angle  Iron  Rack 

7.  Pipe  Rack 


Manual  Recommendations 


171 


Figure  3 

8.  Air  Resenoir  6c   Fuel  Tank 
Test  Area 

9.  Hydro  Test 

10.  Oxygraph  Table 

11.  Drill  Press 

12.  Brake 

13.  Rolls 

14.  Fonning  Table 

15.  Shear 

16.  Steel  Rack 

17.  Double  Dry   Grinder 

18.  Band  Saw 
O.  SHEETMETAL  SHOP 

1.  Threading  Machine 

2.  Fonning  Table 

3.  Heli-Arc  Welder 

4.  Spot  Welder 

5.  Circle  Cutter 

6.  Band  Saw 

7.  Rotex  Punch 

8.  Brake 

9.  Rolls 

10.  Forming  Table 
11-12.  Shears 

13.  Aluminum  Rack 

14.  Sheet  Steel  Rack 
P.  TOOL  ROOM 
Q.  TOILET  FACILITIES 
R.  BLACKSMITH  SHOP 

1.  Oxygraph  Machine 

2.  Steel  Plate  Storage 

3.  Forming  Table 

4.  Anvil 

5.  Forge 

6.  Quenching  Tank 

7.  Small  Hammer 

8.  Large  Hammer 

9.  Forming  Table 

10.  Pipe  Bender 
11-12.  Benches 

13.  Double   Dry  Grinder 

14.  Vise 

15.  Furnace 

16.  Work  Storage  Area 

17.  Sheet  Steel  Fabrication  Storage 
Area 

18.  Sheetmetal  Shop  Work  Storage 
Area 

19.  Tamping  Shoe  Reclaim  Area 

20.  Welding  Work   Storage   Area 


(Continued) 

21-25.  Welding  Boodis 

26.  Exhaust  Ducting 

27.  Normalizing   Furnace 
S.  HEAVY  ASSEMBLY  REPAIR  & 

RECLAIM  AREA 
T.  PILE   DRIVER   REPAIR  AREA 
U.  150-TON  O.H.  TRAVELING 

CRANE 
V.  HEA\'Y  ROADWAY  MACHINE 

REPAIR  AREA 
W.  LOADING  AREA 
X.  30-TON  O.H.  TRAVELING 

CRANE 
Y.  INTERMEDIATE  ROADWAY 

MACHINE    REPAIR  AREA 
Z.  15-TON  O.H.  TRAVELING 
CRANE 
A-A.   RAIL  &  TIE  GANG  EQUIP- 
MENT REPAIR  AREA 
B-B.    15-TON  O.H.  TRAVELING 

CRANE 
C-C.   OFFICE  BUILDING 
D-D.  TRANSFER  PIT 
E-E.   TRANSFER  TABLE 
F-F.    TRANSFER  TABLE  TRAILER 
G-G.  30-TON  O.H.  TRAVELING 

CRANE 
H-H.  CLEANING  VATS 
I-I.  LYE  VAT  WASH  AREA 
J-J.  STORAGE  AREA 
K-K.   CAR  &  EQUIPMENT  STORAGE 
AREA  TRACKS 
LEAD  IN  TRACKS: 

1.  "Circus"   Train,    Car   Repair 
&  Paint  Shop  Lead 

2.  "Circus"    Train    Loading    & 
Paint  Shop  Lead 

3.  Loading  Track 

4.  Loading  Track 

5.  Holding  Track 

6.  Test  Track  &  Heavy 
Equipment 

7.  Test  Track  &   Heavy 
Equipment 

8.  Pile  Dri\er  Test  Track 


172       Bulletin   655 — American  Railway  Engineering  Association 

Report  on   Assignment  2 

Design  Criteria  for  Elevated  Yard  Office  Buildings 

W.  C.  Humphreys  (chairman  subcommittee),  A.  C.  Cayou,  H.  R.  Helkeb,  R.  J. 
Martens,  G.  J.  Bleul,  L.  S.  Newman,  P.  W.  Peterson,  R.  E.  Phillips,  H.  A. 
Shannon. 

Your  committee  submits  for  adoption  the  following  new  Part  10  for  Chapter  6 
of  the  Manual. 

Part  10 
Elevated  Yardmasters'  Towers 

10.1  FOREWORD 

The  elevated  yardmasters'  tower  is  a  natural  development  which  resulted  from 
the  experience  of  railroads  that  located  supervisory  personnel  in  elevated  structures 
at  strategic  points  in  modern  classification  yards.  Based  on  this  experience,  many 
railroads  decided  to  provide  elevated  towers  for  yardmasters  in  all  types  of  yards  to 
increase  their  supervisory  potential. 

The  elevated  yardmasters'  tower  permits  the  yardmaster  to  visually  supervise 
yard  crews  and  yard  engine  operations,  and  tlius  develop  greater  switching  efficiency 
through  better  switch  crew  utilization.  The  elevated  tower  also  permits  better  utili- 
zation of  yard  tracks. 

Elevated  yardmasters'  towers  are  most  effective  in  yards  where  more  tlian  one 
yard  crew  is  working  at  the  same  time.  The  towers  are  generally  located  at  the 
switching  end  or  lead  end  of  tlie  yard. 

10.2  SITE  CONSIDERATIONS 

Inasmuch  as  the  primary  function  of  the  elevated  yardmasters'  towers  is  critical 
observation,  the  location  is  probably  the  most  important  consideration.  The  optimum 
height  from  top  of  rail  to  the  observation  tower  floor  is  generally  considered  to  be 
30  to  40  ft.  The  site  location  should  be  determined  by  tlie  track  geometry  of  the 
particular  yard  location.  As  a  rule  of  thumb,  the  tower  should  be  50  ft  back  from 
the  switching  lead  to  permit  observation  of  switching  operations,  and  at  the  center 
line  of  the  classification  tracks  to  permit  maximum  observation  down  the  lines  of 
classification  tracks. 

Many  yards  are  located  within  urban  areas,  and  are  crossed  by  overhead  struc- 
tures carrying  vehicular  traffic.  These  structures  often  make  it  quite  difficult  to 
detemiine  tlie  best  height  and  location  for  constructing  a  tower.  In  these  cases,  it 
is  extremely  helpful  to  secure  a  basket-mounted  high-reach  mobile  crane  and  have 
the  local  operating  supervisor  ride  the  basket,  and  adjust  the  height  and  location 
until  he  determines  the  position  which  is  most  suitable  for  the  tower.  The  tower 
floor   can   then   be   located   in   accordance   with   these   field-determined   dimensions. 


Manual  Recommendations  173 

10.3  TYPES 

Elevated  yardmasters'  towers  may  be  constructed  as  part  of  the  upper  story 
of  a  multi-story  yard  building,  as  an  additional  story  to  an  existing  yard  building,  or 
as  an  individual  prefabricated  metal  observation  tower  supported  by  a  structural 
frame. 

Inasmuch  as  individual  yardmasters'  towers  are  purely  functional  structures, 
economic  considerations  generally  dictate  that  they  be  constructed  of  structural 
steel.  Size,  height,  location,  and  other  considerations,  however,  may  indicate  that 
they  be  constructed  of  reinforced  concrete,  preformed  concrete  members,  or  masonry. 

10.3.1  Towers   Constructed  as   Part  of  Yard  Buildings    (See  Figures   1-4) 

An  elevated  yardmasters'  tower  may  sometimes  be  constructed  as  part  of  the 
upper  story  or  on  top  of  a  new  multi-story  yard  building.  This  lias  the  advantage  of 
reducing  tlie  tower  construction  cost  inasmuch  as  the  supporting  structure  is  provided 
by  tire  multi-story  building  structure,  and  square-foot  job  costs  will  be  substantially 
reduced.  In  addition,  costs  of  bringing  services  and  utilities  to  the  tower  are  virtually 
eliminated,  as  these  costs,  which  can  be  considerable,  would  be  chargeable  to  the 
main  building  structure. 

The  main  disadvantage  of  constructing  an  elevated  tower  as  part  of  a  multi- 
story building  is  that,  generally,  operating  requirements  dictate  that  a  yard  trans- 
portation building  be  constructed  at  a  site  which  is  not  the  most  advantageous  for 
locating  a  yardmasters'  tower. 

10.3.2  Towers   Constructed  as   an  Addition  to  an  Existing  Building 

In  some  instances,  elevated  yardmasters'  towers  are  constructed  on  the  roof  of 
an  existing  building.  The  generally  accepted  theory  is  that  this  is  cheaper  than 
building  a  separate  tower  on  a  structural  steel  tower  frame.  Experience,  however, 
indicates  that  in  most  cases  the  cost  of  remodeling  and  structurally  strengthening  an 
existing  building,  together  with  the  cost  of  a  new  tower  cabin,  is  close  to  or  the 
same  as  the  cost  of  a  new  separate  tower.  In  addition,  constructing  a  tower  on  an 
existing  building  has  the  same  disadvantage  as  constinicting  it  as  part  of  a  new 
multi-story  building,  in  that  existing  buildings  are  generally  not  located  at  a  suitable 
site  for  a  yardmaster's  tower. 

10.3.3  Individual  Prefabricated  Towers    (See  Figure  5) 

Individual  prefabricated  yardmasters'  towers  have  the  advantage  of  being 
almost  completely  flexible  with  respect  to  location.  Inasmuch  as  the  location  of  a 
tower  has  a  direct  bearing  on  its  main  function  of  observation,  this  is  a  prime  con- 
sideration. A  standard  elevated  yardmasters'  tower  plan  can  be  developed  which 
t;ikes  advantage  of  standard  components  and  shop  fabrication.  A  standard  30-ft-high 
tower  can  be  varied  in  height  between  30  ft  and  40  ft  by  varying  the  pedestal  height 
of  the  concrete  foundation  on  which  the  tower  is  supported. 

(Text  contimied  on  page  178) 


174       Bulletin  655 — American  Railway  Engineering  Association 


ELEVATION 


SECOND      FLOOR 


THIRD        FLOOR 


CAR       If A   1 
OFFI  -E 


Ti 


^ 


MFN  1—^ 


LOCKER   ROOM 


LUNCH   ROOM 


]MI 


FIRST    FLOOR 
Figure  1 


Manual   Recommendations 


175 


e 


liillllnlilinilllllllllUl 


jiiimiiii! 


iMTTTmr 


mm 


mm 
D 


ELEVATION 


SECOND 
FLOOR 


MT^ 


SW/TCH 
FOREMAN 


THIRD 
FLOOR 


ni 

I 

1 
1 

TRAIN 
MASTER 

r 

D 
TEf, 

YAR 
MAS 

1 

FOURTH 
FLOOR 


176       Bulletin  655 — American  Railway  Engineering  Association 


CONTROL 
TOWER 

, 

1 

ML 


jQ 


FOURTH 
FLOOR 


STORAGE 


-TBn 


THIRD 
FLOOR 


BA ITERY 
CHARGING 


ELECT 
ROOM 


CABOOSE 

SHOP 


\ 

El  [ 

H.t  I 


SECOND       FLOOR 


POWER 
ROOM 


BATTERY 
ROOM 


SPEC.  I 

A&T    *         LUNCH 

ROOM 


TELEGRAPH 
ROOM 


lifl 


n 


Lrffn 


)    ^ 


YARD 
FORMAN 


TTTTT 


mm 


EEffi 


LOCKER    ROOM 


FfflTfffm 


50/Z.  ER 
ROOM 


SIGNAL     SHOP 


FIR5T     FLOOR 
Figure  3 


Manual  Recommendations 


177 


ELEVATION 

Figure  4 


^ 


V 


^ 


CD  L3 


5'-d' 


^^ 


-1 

TOWER    FLOOR    PLAN 


UTILITY    FLOOR    PLAN 


TOWER     ELEVATION 


CROSS   SECTION 


Figure  5 


178       Bulletin   655 — American  Railway  Engineering  Association 

10.4  TOWER  CONSTRUCTION 

10.4.1  General  Construction  Materials 

The  materials  used  in  the  construction  of  a  tower  which  is  part  of  a  new  building 
will,  of  course,  be  determined  by  the  construction  and  aesthetics  of  the  overall 
building  structure.  Lightweight,  fire-resistant,  standard  components  should  be  used 
for  towers  constructed  on  top  of  existing  buildings,  and  in  the  construction  of  indi- 
vidual elevated  towers.  The  types  of  materials  to  be  considered  in  the  construction 
of  towers  are  structural  steel  or  aluminum  tube  framing,  masonry,  concrete,  standard 
window  wall  components,  insulated  metal  wall  components,  and  metal  flooring  and 
roof  decking  materials.  The  finish  flooring  material  may  be  vinyl,  or  vinyl  asbestos 
tile,  or  some  other  similar  material  which  is  easy  to  maintain.  Consideration  may 
also  be  given  to  carpeting.  Acoustical  treatment  is  an  important  consideration,  though 
not  essential.  The  installation  of  adequate  insulating  materials  is  of  prime  importance 
due  to  the  extensive  exposure  of  the  towers  and  the  large  areas  of  glass  required  for 
observation. 

Access  to  a  tower  constructed  as  part  of  a  new  building  is  usually  by  means 
of  interior  stairs.  Access  to  a  tower  constructed  on  top  of  an  existing  building  may 
be  by  means  of  interior  stairs,  or  by  extending  existing  stair  towers.  It  is  usually 
more  practical,  however,  to  construct  a  new  access  stair  on  the  outside  of  the  build- 
ing. Access  stairs  for  individual  elevated  towers  are  usually  open-metal  stairways 
constructed  around  the  outside  and  framed  into  the  structural  tower  frame. 

The  inclusion  of  elevators  should  be  considered  in  the  design  of  towers,  particu- 
larly where  they  are  included  as  part  of  a  multi-story  building  or  where  an  individual 
tower  is  to  be  constructed  over  30  ft  in  height. 

10.4.2  Mechanical  and   Electrical  Facilities   and  Equipment 

Yardmasters'  towers  of  all  types  should  be  provided  with  easily  accessible  toilet 
facilities.  Individual  towers  should  have  toilets  included  as  part  of  the  elevated 
tower  cabin.  Towers  constructed  as  part  of  a  new  multi-story  building  or  on  top  of 
an  existing  building,  should  have  toilets  located  either  in  the  tower,  or  close  by 
on  an  adjacent  floor.  Water  supply  lines  and  drainage  lines  for  individual  towers 
should  be  insulated  and  heat  traced  to  prevent  freezing. 

Yardmasters'  towers  should  be  adequately  heated  and  air-conditioned.  Special 
consideration  must  be  given  to  the  heating  and  cooling  design  due  to  the  exposure 
factor  and  large  amounts  of  exposed  glass  surface.  Although  any  type  fuel  and  heat- 
ing system  can  be  used  for  heating  the  tower,  electric  heating  has  many  advan- 
tages. Electric  heating  is  particularly  suited  to  individual  elevated  towers.  The  heat- 
ing can  be  either  combined  with  the  cooling  in  through  wall  units  or  be  individual 
base-board  units  or  unit  heaters. 

Care  must  be  given  in  the  design  of  the  lighting  to  incorporate  the  adjustments 
and  flexibility  required  to  provide  the  most  ideal  conditions  possible  to  perform 
the  outside  observance  task  at  all  times  of  the  day  and  night,  under  various  outside 
lighting  conditions. 

Good  general  lighting  must  be  provided,  also  spot  or  individual  shielded  lighting 
for  reading  panels,  consoles,  switch  lists,  etc.  Lighting  fixture  rheostats  must  be 
installed  on  all  general  lighting  to  furnish  the  required  contrast  between  inside  and 
outside  natural  lighting  conditions. 

Outside  yard  lighting  must  be  designed  and  located  in  conjunction  with  the 
tower  design  and  location,  so  that  it  will  not  blind  the  tower  occupant,  but  rather 
augment  his  observation  task. 


Manual  Recommendations 


179 


10.5  SPECIAL  FEATURES 

10.5.1  Tower  Size 

The  tower  should  be  minimal  in  size  and  tlie  floor  plan  developed  on  the  basis 
of  only  the  equipment  to  be  installed  in  die  tower,  with  minimal  space  around  the 
equipment  for  circulation  and  servicing  the  equipment.  The  location  of  equipment 
is  important  in  developing  the  maximum  visibility  factor  of  the  tower.  A  nominal 
10  ft  X  12  ft  size  is  adequate  in  most  cases  for  a  one-man  tower. 

10.5.2  Tower  Glazing  and  Glass    (See  Figure  6) 

Glazing  should  be  located  only  on  tlie  faces  of  the  tower  where  observation 
will  be  required.  This  is  usually  on  three  tower  walls,  with  the  fourth  wall  used  for 
a  door,  toilet  rooms,  service  panels,  etc. 

A  study  should  be  made  with  the  personnel  responsible  for  the  operation  to 
determine  the  best  orientation  of  die  tower  to  permit  die  optimum  required 
obser\ation. 

The  lower  glass  line  should  be  dictated  by  line  of  sight,  but  generally  should 
be  as  close  to  the  floor  as  possible,  allowing  enough  space  for  radiation,  service  out- 
lets, conduits,  etc.  The  upper  glass  line  should  be  located  approximately  5  ft  6  in 
abo\'e  the  floor,  or  at  the  eye  line  for  a  man  who  is  standing.  As  the  points  of  obser- 
\ation  are  all  below  eye  level  in  the  yard,  any  glass  above  this  point  is  superfluous. 
Elimination  of  glass  above  eye  level  reduces  sun  glare  and  sky  brightness. 


NSULATED 
OI_ASS 


XOWER  FLOOR 

l_IIME 


VERTICAL    GLASS  SLOPED    GLASS 

TYPICAL    TOWER  GLASS   DETAILS 


Figure  6 


180       Bulletin   655 — American  Railway  Engineering  Association 

It  is  extremely  desirable  to  use  double  glazing  for  all  windows  to  reduce  heat 
loss   and   elinunate   the  possibility   of  condensation   and  fogging  of   glass. 

The  use  of  heat-reducing  and  glare-reducing  glass  is  not  recommended  as  it 
reduces  night  visibility,  and  this  is  the  time  when  visibility  is  most  critical.  The 
additional  heat  gain  can  be  compensated  for  during  tire  day  by  providing  more  air 
conditioning,  but  there  is  no  way  to  compensate  for  the  visibility  loss. 

Tower  windows  may  be  installed  vertically  or  sloped.  There  are  proponents 
of  both  schools  of  thought  who  will  vigorously  defend  their  position.  Some  studies 
have  indicated  that  diere  are  no  advantages  in  installing  sloped  windows,  and  that 
there  are,  in  fact,  some  disadvantages.  Sloping  windows  put  additional  stress  on  the 
glass  and  make  it  more  susceptible  to  cracking.  This  is  especially  true  of  insulating 
glass.  Sloping  glass  also  tends  to  increase  distortion  and  reduce  vision  as  the  sight 
line  passes  through  a  greater  thickness  and  density  of  glass.  Each  individual  will 
have  to  develop  his  own  set  of  facts  and  make  his  own  decision  of  tiiis  feature  of 
the  design. 

The  use  of  vertical  pivoted  sash  for  towers  is  desirable  as  it  permits  washing 
windows  from  inside,  and  may  ehminate  the  need  of  an  outside  catwalk.  If  fixed 
sash  is  used,  a  catwalk  should  be  provided  for  washing  windows. 

The  maximum  standard-size  sash  should  be  used.  Generally,  the  use  of  vertical 
mullions  is  not  a  problem;  however,  care  should  be  taken  not  to  locate  a  mullion 
in  the  center  of  a  critical  viewing  area. 

10.5.3  Tower  Roof  Overhang 

Towers  should  be  constructed  with  adequate  roof  overhang  to  reduce  sun  glare, 
sky  brightness,  and  heat  transfer.  It  may  be  necessary  under  certain  conditions  to 
install  Venetian  blinds  or  transparent  colored  sun  screens. 

10.5.4  Tower  Relocation 

Individual  prefabricated  yardmasters'  towers  have  tlie  added  advantage  of  being 
relocatable.  They  are  usually  constructed  in  two  main  sections.  The  structural  steel 
tower  frame  can  be  fabricated  in  one  or  more  sections,  and  the  tower  cabin  fabricated 
in  another  section.  The  stairs  are  also  fabricated  in  sections.  When  tlie  need  arises 
to  relocate  a  tower  to  a  different  location,  the  tower  can  be  dismantled  and  relo- 
cated to  a  new  location. 


Manual   Recommendations 
Committee  33 — Electrical   Energy  Utilization 

Report   on   Assignment    1 

Electrification  Economics 

R.  J.  Berti  (chairman,  subcommittee),  W.  H.  Brodski,  W.  S.  Gordon,  M.  F. 
Cowing,  D.  T.  Jones,  H.  C.  Kendall,  K.  L.  Lawson,  M.  D.  Meeker,  A.  G. 
Raabe,  R.  p.  Reiff,  B.  a.  Ross,  L.  D.  Tufts,  K.  B.  Ullman. 

Your  committee  submits  for  adoption  the  following  Part  1  for  new  Chapter  33 
of  the  Manual. 

Part  1 

Method  of  Making  Electrification 

Economic  Studies 

1.1  GENERAL 

1.1.1  Objective 

The  prime  objective  of  an  electrification  economic  study  is  to  determine  if 
electric  operation  of  a  particular  railroad  is  more  advantageous  than  operation  widr 
another  form  of  power  which  may  or  may  not  be  in  actual  use.  This  is  written  from 
the  commercial  \ie\\'point  of  a  privately  operated  railroad. 

1.1.2  Basic  Procedure 

Each  identifiable  cost  associated  with  the  diff"erent  types  of  power  must  be 
quantified  for  economic  comparison.  Since  most  electrification  studies  will  cover  a 
period  between  20  and  50  years  into  the  future,  costs  should  be  separated  into  two 
basic  categories:  initial  one-time  expenses,  and  annual  costs  which  are  subject  to 
continuing  inflation.  Separate  inflation  rates  should  be  specified  for  each  annual 
cost  to  properly  compare  types  of  power  over  a  long  period  of  time.  Extra  care 
should  be  taken  in  determining  inflation  rates  since  they  will  be  compounded  over 
the  life  of  the  study.  Intangible  costs  and  benefits  or  liabilities  should  be  listed  for 
review  at  the  end  of  the  study,  unless  they  are  directly  associated  with  a  tangible 
cost. 

1.1.3  System  Operation 

Prior  to  any  detailed  analysis,  the  segment(s)  of  railroad  to  be  studied  nuist 
be  precisely  defined  as  well  as  the  basic  parameters  of  operation.  Train  size,  speed, 
frequency,  etc.,  should  be  made  constant  for  all  types  of  power  studied  to  permit 

181 
Bui.   655 


182       Bulletin   655 — American  Railway  Engineering  Association 

a  valid  initial  comparison.  The  detailed  study  should  include  the  economic  effects 
of  changing  the  operating  parameters  to  that  most  favorable  to  each  type  of  power 
being  compared. 

1.1.4  Electrical  Distribution  Systems 

A  cursory  review  of  the  various  types  of  electrical  distribution  systems:  tliird- 
rail  direct  current,  12.5-kv  alternating-current  catenary,  50-kv  alternating-current 
catenary,  etc.,  should  be  made  to  determine  which  system  or  combination  of  systems 
is  most  applicable  for  the  specific  case  under  study.  Detailed  analyses  can  start  after 
this   preliminary   determination   is   made. 

1.1.5  Data 

A  base  year  should  be  chosen  from  which  all  data  can  be  projected.  The  data 
for  this  base  year  must  be  as  reliable  as  possible,  thus  considerable  effort  should  be 
spent  to  review  all  sources  of  information  for  their  accuracy  and  completeness. 

1.2  TRAFFIC 

1.2.1  Gross  Ton  Miles 

Freight  Traffic — The  most  common  unit  for  computing  energy  and  maintenance 
costs  is  the  gross-ton-mile.  The  number  of  gross-ton-miles  operated  over  the  railroad 
under  study  should  be  thoroughly  reviewed  to  ascertain  what  percentage  of  the 
total  could  be  hauled  electrically.  Locals  or  trains  that  would  travel  only  a  short 
distance  over  electrified  territory  may  be  moved  more  economically  using  non- 
electric locomotives.  Total  annual  gross-ton-miles  can  then  serve  as  a  base  for  com- 
puting  energy    and   maintenance    cost   for    both    electric    and   non-electric    systems. 

1.2.2  Passenger  Trains 

Due  to  the  high  acceleration  and  speed  required  of  passenger  trains,  they  are 
frequently  treated  separately  from  the  freight  service.  If  they  are  present  and  being 
dealt  with  independently,  the  gross-ton-miles  generated  by  the  passenger  trains 
should  be  subtracted  from  the  total  being  hauled  electrically.  Since  passenger  trains 
outside  the  northeast  have  only  minimal  impact  on  electrification  studies,  their 
economics   are  not  covered  in  this  outline. 

1.2.3  Train  Size  and  Speed 

For  proper  comparison  of  energy  demands,  the  size  and  speed  of  typical  trains 
should  be  specified  for  operation  electrically  or  with  other  forms  of  power.  Initially, 
this  parameter  should  be  the  same  for  any  type  of  power;  however,  as  the  study 
becomes  more  detailed,  it  may  become  obvious  tliat  one  type  of  power  is  more 
economical  using  a  different  train  size  and  speed.  For  evaluation  purposes,  any 
changes  in  train  size  and  speed  should  be  a  separate  portion  of  the  study. 

1.2.4  Traffic  Projection 

The  facts  reviewed  in  the  study  for  traffic  projection  are  very  critical.  A  large 
growth  rate  when  compounded  over  many  years  can  saturate  the  existing  track  and 
signal  system  creating  a  requirement  for  CTC  or  additional  mainline  track.  Negative 
growth  rate  can  impact  the  study  outcome  by  causing  savings  to  diminish  in  the 
future. 


Manual  Recommendations  183 


1.2.5  Train  Schedules 

The  average  daily  traffic  must  be  specified  by  number  of  trains,  size  of  trains, 
and  die  timetable  schedule  of  trains.  The  maximum  daily  traffic  must  be  specified 
in  the  same  manner.  The  minimum  acceptable  train  performance  (train  speed,  size 
and  frequency)  under  emergency  conditions  (substation  outage,  excessive  train 
densit>',  etc.)   should  be  specified. 


1.3  CAPITAL  EQUIPMENT  COSTS 

1.3.1  Locomotives 

Based  on  tlie  traffic,  terrain,  train  size  and  schedules,  the  electric  locomotives' 
weight,  wheel  configiuation,  power  and  speed  capabilities  can  be  selected.  This 
selection  should  be  carefully  coordinated  with  the  builders  of  electric  locomotives 
to  insure  the  commercial  a\ailability  and  a  valid  cost  estimate.  Locomotives  with 
prime  movers  other  than  standard  diesel  engines  should  likewise  be  selected  with 
care. 

If  the  electrified  system  is  to  be  compared  to  diesel  locomoti\es  it  should  be 
detennined  whether  to  use  existing  types  of  diesel-electrics  or  for  comparison  use 
a  new  model  not  yet  manufactured.  As  with  electrics,  the  various  manufacturers 
should  be   consulted   to   insure   reliable   cost  data. 

Extreme  care  should  be  taken  to  insure  that  enough  locomotives  of  each  type 
have  been  pro\  ided  to  cover  peak  traffic  periods,  allow  downtime  for  scheduled  and 
unscheduled  maintenance,  and  provide  for  possible  future  schedule  changes  which 
would  require  more  locomotives  with  the  same  traffic.  Past  experience  has  shown 
the  electric  locomotive  to  have  a  higher  availability  and  utilization  than  other  types. 
Computer  generated  speed-time-distance  calculations  can  be  of  great  assistance. 
Energy  and  power-time-distance  calculations  made  at  the  same  time  are  invaluable 
in  computing  electric  power  consumption  and  cost  as  well  as  diesel  fuel  consumption 
and  cost. 

1.3.2  Locomotive  Facilities 

The  existing  mechanical  facilities  should  l^e  thoroughly  reviewed  to  determine 
what  changes  will  be  necessary  to  maintain  electric  locomotives.  Some  of  the  more 
modem  diesel  facilities  can  be  used  for  electric  locomotive  maintenance  with  virtu- 
ally no  changes,  while  old  roundhouse  operations  may  be  totally  unfit  for  any 
maintenance  work. 

Main-line  electrification  may  segment  the  remaining  diesel  service  to  such  a 
great  extent  that  new  diesel  maintenance  shops  must  be  built  to  care  for  the  diesels 
running  branch  lines  and  locals.  Maintenance  facilities  for  both  diesels  and  electrics 
should  be  an  important  factor  in  determining  the  end  points  for  an  initial  electrifica- 
tion project. 

High-voltage  catenary  is  not  to  be  recommended  inside  a  maintenance  shop 
where  the  risk  of  employee  injury  is  much  greater  due  to  the  type  of  work  being 
done.  If  it  becomes  necessary  to  have  high-voltage  inside  a  shop,  special  warning 
devices  should  be  installed  to  alert  all  workers  when  the  high-voltage  is  energized. 
Locomotive  cleaning  and  sanding  facilities,  which  will  be  used  by  both  diesels  and 
electrics,  should  be  checked  to  insure  safe  operation  with  the  electric  locomotives 
while  the  power  is  on. 


184       Bulletin   655 — American   Railway  Engineering  Association 

1.3.3  Power  Generating  Facilities 

Railroads  still  face  some  locations  where  it  is  more  economical  to  build  an  elec- 
tric generating  station  tlian  it  is  to  buy  power  from  the  local  utility  company. 
Locations  may  exist  where  local  power  is  unavailable.  If  railroad  owned  power 
generation  is  to  be  considered,  studies  by  specialized  electric  utility  engineers  will 
be   required   to   determine   capital,   operating   and  maintenance  costs. 

1.3.4  Power  Distribution  Systems 

A  study  should  be  made  to  determine  the  electrical  power  demand  of  each 
portion  of  the  railroad  to  be  electrified.  The  utility  companies  should  be  consulted 
to  locate  transmission  lines  in  the  area  suitable  for  use  by  the  railroad.  On  a  high- 
voltage  system,  it  is  advisable  to  try  and  arrange  for  adjacent  substations  to  be 
served  by  different  transmission  lines  in  order  to  minimize  the  possibility  of  power 
failure  which  would  affect  more  than  one  substation.  For  substations  located  at 
the  end  of  an  electrified  system,  consideration  should  be  given  to  the  installation  of 
two  transformers  connected  to  two  diflierent  transmission  lines  to  minimize  the  pos- 
sibility of  power  failure.  Sizing  of  the  transmission  line  will  be  based  on  maximum 
present  and  future  load.  It  is  frequently  more  economical  to  put  up  heavier  wire 
or  a  few  more  insulators  for  a  higher  voltage  transmission  line  during  initial  con- 
struction than  it  is  to  retrofit  after  the  load  demand  has  increased.  Single-phase 
unbalance  problems  may  be  encountered  and  could  require  special  substation 
connections. 

1.3.5  Substations 

Substations  are  used  to  step  the  high  transmission  line  voltage  down  to  the 
voltage  used  on  the  catenary  or  third  rail.  The  alternating  current  is  also  converted 
to  direct  current  at  a  substation  when  required  for  third  rail. 

Equipment  used  in  a  substation  should  be  capable  of  handling  high  overloads 
for  relatively  short  periods  of  time  without  failure.  Substation  transformers  can  be 
sized  to  permit  initial  loads  with  no  forced  cooling;  later,  forced  cooling  can  be 
added  to  support  the  increased  traffic  at  minimal  cost.  It  is  common  practice  to 
assume  that  a  substation  will  be  called  upon  to  supply  half  of  an  adjacent  substa- 
tion's load  during  an  emergency.  Railway  substation  transformers  should  be  equipped 
with  extra  bracing  to  prevent  damage  during  a  short  circuit.  Either  manual  and/or 
remote  control  should  be  provided  for  each  substation.  Provisions  should  be  made 
to  have  a  spare,  mobile  substation  which  will  serve  in  an  active  capacity  when  not 
being  used  as  a  replacement.  For  substations  located  at  the  end  of  an  electrified 
system,  consideration  should  be  given  to  the  installation  of  two  transformers  connected 
to  two  different  transmission  lines  to  minimize  the  possibility  of  power  failure. 

Phase  breaks  at  or  between  substations  should  be  equipped  with  manual  or 
remote  controlled  switch  gear  to  permit  isolating  or  energizing  adjacent  catenary 
sections. 

If  remote  control  of  substation  and  phase  breaks  is  contemplated  the  cost  of  a 
central  control  point  and  telemetry  circuits  cannot  be  overlooked. 

1 .3.6  Power  Transfer 

Two  primary  methods  are  used  to  transfer  electrical  power  to  the  railway  vehicle, 
third  rail  and  overhead  wire.  The  cost  of  third  rail  includes  the  special  contact  rail, 
insulators,  long  ties  or  special  brackets  to  mount  on  the  short  ties,  third-rail  covers, 


Manual   Recommendations  185 


right-of-way  fencing,  miscellaneous  hardware  and  installation  labor  costs.  Ice  and 
heavy  snow  cause  electrical  troubles  with  third-rail  systems  in  many  parts  of  the 
world. 

Overhead  wire  comes  in  several  different  configurations  with  vehicle  operating 
speed  being  tlie  determining  factor.  Simple  trolley  wire  can  be  used  for  yards  or 
track  where  the  speed  of  multiple  unit  consists  will  not  exceed  30  mph.  European 
tests  have  shown  that  stitched  trolley  wire  can  sustain  speeds  of  60  mph  with 
multiple-unit  consists.  However,  the  current  capacity  of  standard  trolley  wire  may 
limit  trolley  wire  use  to  relatively  low  power  situations.  The  simple  sagged  catenary 
is  generally  sufficient  for  speeds  up  to  120  mph.  Compound  or  stitched  catenary  is 
usually  recommended  for  operation  of  trains  above  120  mph.  Virtually  all  new 
catenary  construction  is  of  the  constant-tension  design  which  has  proven  able  to 
minimize  trouble.  At  certain  locations  where  power  demand  is  extremely  heavy, 
auxiliary  parallel  feeders  hung  from  the  supports  may  be  more  economical  than 
increasing  the  size  of  the  catenary  wire  or  adding  more  substations.  Catenary  con- 
struction costs  are  generally  more  dependent  on  terrain  than  third-rail  costs  due  to 
the  variation  in  support  distance.  Costs  for  overhead  catenary  should  include  wire, 
insulators,  supports,  support  foundations,  tensioning  devices,  miscellaneous  hardware, 
and  all  the  labor  to  install  the  system. 

Construction  of  both  diird-rail  and  overhead  systems  will  disrupt  railway  traffic 
and  require  special  material  trains.  Expenses  for  special  train  crews,  extra  train 
crews  and  items  such  as  flagman  protection,  should  be  added  to  the  cost  of 
construction. 

1.3.7  Clearance  Modification 

Situations  will  arise  with  both  third-rail  and  overhead  system  where  the  elec- 
trical clearance  requirements  will  necessitate  the  modification  of  nearby  structures 
such  as  platfomis,  bridges  and  tunnels.  Extremely  high  modification  costs  may 
dictate  a  lower  voltage  or,  in  some  cases,  a  short  segment  of  electrically  dead  catenary 
or  third-rail. 

1.3.8  Signal  Modification 

Because  of  electrical  interference  from  the  traction  power  system,  electrifica- 
tion is  not  compatible  with  most  types  of  signals  used  in  the  United  States.  A  detailed 
analysis  should  be  made  by  the  signal  department  to  determine  the  best  type  of 
modification  to  make  signals  compatible  with  the  particular  form  of  electrification 
being  considered.  Trackside  signal  lines  must  be  shielded  from  alternating  current 
power  systems.  The  cost  to  upgrade  a  signal  system,  such  as  installing  cab  signals, 
should  not  be  charged  to  electrification. 

1.3.9  Communications 

Most  open-wire  communications  circuits  near  an  alternating-current  power 
source  must  be  either  shielded  or  converted  to  microwave.  Microwave  is  frequently 
used  for  the  long-distance  circuits  while  shielded  cable  can  be  used  for  local  dis- 
tribution circuits.  Modern  thyristor  locomotives  have  been  known  to  generate  various 
forms  of  signals  which  radiate  beyond  the  railway  property  line.  Special  shielding 
of  power  circuits  may  be  required  in  urban  areas  to  prevent  interference  with  public 
communications   systems. 


186        Bulletin   655 — American  Railway  Engineering  Association 

1.4  ANNUAL  OPERATING  EXPENSES 

1.4.1  General 

The  annual  operating  expenses  are  critical  in  any  electrification  study  and 
should  be  very  carefully  derived.  The  electrification  of  a  railroad  has  the  potential 
to  affect  virtually  every  cost  encountered  in  daily  operations.  The  diff^erence  in  oper- 
ating expenses  bet\veen  two  or  more  propulsion  systems  is  what  creates  a  return 
on  investment  and  determines  which  system  is  the  most  economical  when  compared 
to  the  initial  capital  costs. 

1.4.2  Fuel  and  Energy 

The  cost  of  energy  or  fuel  delivered  to  locomotives  must  be  ascertained  for  each 
system  being  studied.  Fuel  costs  should  include  all  transportation,  pumping  and 
labor  costs.  Electric  energy  bills  usually  include  a  demand  charge,  energy  charge, 
fuel  adjustment  and  possibly  a  rental  on  some  fixed  equipment.  If  the  cost  of  fuel 
and  energy  are  changing  at  different  rates,  separate  inflation  factors  should  be  de- 
veloped for  each.  Attempts  to  increase  the  electrical  load  factor  frequently  result  in 
train  rescheduling  and  a  separate  option  in  the  final  analysis  of  electrification. 

1.4.3  Train  Crew  Wages 

Train  crews  may  be  paid  on  a  basis  that  will  change  after  electrification.  Fewer 
locomotives  with  less  weight  on  drivers  could  reduce  the  wages  earned  by  the  engine 
crew.  Higher  acceleration  and  top  speed  could  reduce  overtime  or  possibly  the 
number  of  crews  required  to  operate  a  particular  section  of  railroad. 

1.4.4  Locomotive  Maintenance 

The  cost  of  maintaining  locomotives  using  different  sources  of  power  is  usually 
one  of  the  most  important  aspects  of  any  electrification  study  and  frequently  requires 
the  most  time  and  effort  to  determine  precisely. 

All  costs  associated  with  maintaining  each  type  of  locomotive  should  be  care- 
fully derived  to  insure  that  a  true  comparison  is  given.  If  possible  each  cost  should 
be  broken  down  into  labor  and  material  for  application  of  die  appropriate  inflation 
factor.  It  is  essential  tliat  all  subdivisions  of  locomotive  maintenance  cost  be  included 
in  the  total.  Some  of  the  more  frequent  subdivisions  include:  locomotive  repairs, 
superintendency,  shop  machinery,  power  plant  machinery,  locomotive  servicing,  main- 
taining power  plants,  maintaining  fueling  facilities,  maintaining  maintenance  shops, 
insurance,  unemployment  insurance,  hospital  insurance,  personal  injuries,  health  and 
welfare  benefits,  old  age  retirement,  and  supplemental  annuities.  Recently,  it  has 
become  a  relatively  common  practice  to  capitalize  the  very  heavy  repairs  or  rebuild- 
ing of  locomotives;  these  costs  should  be  taken  into  account.  The  total  maintenance 
cost  is  most  easily  used  when  apportioned  on  a  gross  ton  mile  basis. 

However,  greater  accuracy  can  be  achieved  if  the  total  cost  can  be  divided 
into  portions  which  are  predominantly  a  function  of  unit  miles  operated,  horsepower- 
hours   generated,  or  chronological  age. 

The  cost  of  maintaining  diesel  electric  locomotives  can  be  easily  obtained  from 
existing  records,  while  costs  associated  with  maintaining  a  modem  electrical  loco- 
motive are  frequently  difficult  to  obtain  from  experience  in  North  America.  Cost 
projections  by  electrical  locomotive  builders  can  form  the  basis  for  the  total  cost, 
but  extensive  research  should  be  done  to  determine  the  cost  being  experienced  by 


Manual   Recommendations  187 


users  of  electric  locomotives.  Electrification  studies  frequendy  refer  to  electric  loco- 
moti\e  maintenance  cost  as  a  per  cent  of  the  diesel  locomotive  maintenance  cost  on 
a  gross  ton  mile  basis. 

1.4.5  Catenary  Maintenance 

While  modern  constant-tensioned  simple  catenary  systems  are  much  cheaper  to 
maintain  than  the  old  \-ariable-tensioned  compound  systems,  a  certain  amount  of 
adjushnent,  wire  replacement  and  repair  after  derailments  will  be  required.  Catenary 
maintenance  costs  are  influenced  by  terrain,  trackwork  complexity,  climate  and  rail 
traffic.  Existing  electrified  systems  should  be  reviewed  to  evaluate  tlie  catenary  main- 
tenance requirements  and  costs  prior  to  making  projections  for  a  new  system. 

Third-rail  maintenance  should  be  treated  in  the  same  manner  as  catenary 
maintenance. 

1.4.6  Substations   and   Transmission  Line   Maintenance 

The  cost  of  periodically  inspecting  transformer  oil,  switch  gear  operation,  sub- 
station facilities,  supervisory  control  systems,  and  clearing  trees  from  the  vicinity 
of  transmission  lines  should  be  estimated.  This  is  frequently  done  by  taking  a  small 
perc-entage   of    the    initial   installation   cost   as   being   the   annual   maintenance   cost. 

1.4.7  Signal   and  Communications  Maintenance 

Eliminating  the  open  line  wire  on  poles  frequently  associated  with  the  existing 
signal  system  usually  means  less  maintenance  of  the  system. 

If  cab  signals  or  other  signal  improvements  are  separately  justified,  no  effect 
will  be  felt  on  tlie  electrification  economics.  However,  if  electrification  is  the  justi- 
fication, such  as  installing  CTC  in  order  to  reduce  the  miles  of  catenary,  all  savings 
should   be   credited  to   electrification. 

1.4.8  Taxes 

The  large  expenses  required  for  electrification  should  be  thoroughly  reviewed  by 
tax  specialists  to  detennine  the  effects  on  taxes  paid  by  the  company.  The  increased 
valuation  frequently  increases  property  taxes  while  the  savings  when  translated  to 
increased  income  can  cause  greater  income  taxes. 

The  effect  on  taxes  made  by  various  investment  tax  credits,  depreciation  reserves, 
and  possibly   existing   unused   tax   credits   should  be  tlioroughly  reviewed. 

1.5  FINANCING 

Top  financial  officers  for  the  railroad  should  be  consulted  to  detenuine  which 
of  tlie  many  financial  aiTangements  would  be  best  suited  to  the  particular  system 
being  studied.  Cash-flow  studies  of  tlie  construction  period  are  frequently  requested 
by  both  railroad  officials  and  in\estment  bankers.  Cash-flow  projections  for  a  period 
of  30  or  more  years  after  the  project  is  completed  is  a  necessity  for  making  retmn-on- 
investment  calculations. 

1.6  MAINTENANCE  OF  WAY  CHANGES 

Installation  of  catenary  or  third  rail  will  cause  some  changes  in  maintenance 
of  way  techniques.  Third-rail  operation  will  require  about  20%  of  the  annual  new 
ties  to  be  longer  than  standard.  In  addition  to  tlie  increased  material  cost  of  the  long 
tie,   labor   to   unfasten   and  re-attach   the  third-rail  chair  and  insulator  must  be  in- 


188       Bulletin   655 — American  Railway  Engineering  Association 

eluded.  Care  must  be  exercised  by  tampers  around  impedance  bonds,  ground  wires, 
and  third  rails.  The  size  of  maintenance  equipment  is  frequently  restricted  by  a 
third-rail  system. 

Cranes  and  wrecking  derrick  booms  should  be  equipped  with  insulated  panto- 
graphs or  shields  when  working  under  catenary  to  avoid  a  grounding  contact  with 
the  wire.  Snow  plows  or  spreaders  operating  with  wings  will  be  restricted  by  cate- 
nary supports.  All  equipment  should  be  grounded  to  provide  a  positive  electrical 
path  for  accidental  contact  with  energized  circuits. 

1.7  INTANGIBLE  BENEFITS  AND  LIABILITIES 

During  an  electrification  study,  many  items  will  appear  which  have  little  mone- 
tary impact,  but  which  ofl:er  distinct  benefits  or  liabilities  for  electric  operation. 
Electrification  has  a  positive  impact  on  line-of-road  failures,  pollution  control,  noise 
and  exhaust  emissions,  performance  with  overload  capability,  performance  with 
superior  wheel-slip  systems,  and  the  option  to  use  different  types  of  fuel.  The  catenary 
can  be  tapped  at  remote  locations  to  provide  power  for  signals,  power  switches, 
switch  heaters,   lights,   and  wayside   buildings. 

Negative  aspects  of  electrification  involve  additional  work  when  clearing 
wrecks,  partial  or  total  system  shutdown  for  large  power  failures,  safety  problems 
with  the  exposed  electrical  system,  and  possible  under-utilization  of  locomotives. 
Extra  training  will  be  required  for  those  responsible  for  maintaining  both  electric 
and  diesel  locomotives. 


Manual  Recommendations 
Committee   13 — Environmental   Engineering 

Report  on  Assignment  4 

Industrial  Hygiene 

R.  S.  Bryan,  Jr.  (chairman,  subcommittee),  W.  D.  Peters  (vice  chairman,  subcom- 
mittee), W.  H.  Melgren,  T.  a.  Tennyson,  R.  Singer. 

Your  committee  submits  for  adoption  and  publication  in  Part  4,  Chapter  13  of 
the  Manual,  tlie  following  new  Section  4.7  Sanitation  Requirements  for  Portable 
Housing  Units. 

4.7   SANITATION   REQUIREMENTS  FOR  PORTABLE   HOUSING 
UNITS 

4.7.1  General 

(a)  The  term  "Portable  Housing  Unit"  or  "Portable  Accommodation  Unit" 
covers  all  self-contained  hving  accommodations  which  can  be  readily  lifted  from 
the  deck  of  a  flatcar  or  any  other  temporary  foundation. 

(b)  Portable  housing  units  should  be  inspected  every  six  months  under  a 
preventive  maintenance  schedule.  This  schedule  should  include  the  electrical  system, 
tlie  water  and  sewage  disposal  systems,  all  appliances,  heating  systems,  the  general 
condition  of  the  unit  as  well  as  good  housekeeping  practices. 

4.7.2  Utilization  of  Units 

(a)  Units  are  to  be  kept  clean  and  tidy,  floors  are  to  be  washed  at  regular 
inter\'als,  particularly  around  appliances.  All  washing  facihties  are  to  be  kept  in  a 
clean  and  sanitary  condition  and  grating  at  shower  stalls  must  be  cleaned 
periodically. 

(b)  Burning  cigarettes  ancd  matches  must  not  be  placed  or  extinguished  on 
counter  tops  or  linoleum  floors,  as  damage  wfll  result.  "USE  ASH  TRAYS." 

(c)  Under  no  circumstances  must  burning  matches,  cigarettes  or  ashes  be 
deposited  in  recirculating  flush-type  chemical  toilets.  These  units  are  constructed 
of  ABS  plastic  material  and  will  become  easily  damaged,  causing  inefficient  opera- 
tion of  the  unit 

(d)  Do  not  deposit  paper  towels,  wet-strength  tissue  paper  or  other  articles  in 
toilets.  Use  toilet  tissue  only.  These  units  are  equipped  with  a  self-cleaning  filter 
and  will  become  clogged  if  other  types  of  paper  are  used. 

(e)  If  toilets  other  than  recirculating  flush-type  chemical  toilets  are  used,  fol- 
low the  instructions  issued  with  the  toilet  unit. 

(f)  All  refuse  must  be  placed  in  covered  receptacles  provided. 

(g)  Each  employee  is  responsible  for  maintaining  his  quarters  in  a  clean  and 
tidy  condition. 

189 


190       Bulletin  655 — American  Railway  Engineering  Association 

4.7.3  Sanitation 

4.7.3.1  General 

(a)  It  is  imperative  that  the  area  around  all  housing  units  be  kept  clear  of  all 
refuse  and  sewage.  In  no  way  is  it  permissible  to  drain  sewage  on  the  ground 
between  or  adjacent  to  the  tracks. 

(b)  Cleanliness  and  sanitary  conditions  must  always  be  maintained  around 
toilet  and  wash  facilities. 

(c)  The  person  in  charge  of  tlie  housing  units  should  be  responsible  to  ensure 
that  sanitary  regulations  are  strictly  adhered  to. 

(d)  Local  regulations  must  be  met  witli  regard  to  dis^josal  of  all  waste,  garbage 
and  drainage  of  water  and  sewer  lines. 

4.7.3.2  Drinking  Water 

(a)  Water  for  human  consumption  must  be  obtained  from  a  source  approved 
by  health  authorities.  Water  obtained  from  a  doubtful  source,  such  as  wells,  lakes 
and  rivers  must  be  chlorinated.  A  simple  method  of  water  purification  is  as  follows: 
Add  1  ounce  of  commercial  bleach  solution  (5.25%  sodium  hypochlorite)  to  5  U.S. 
gallons  of  water  or  one  5-grain  Halazone  tablet  to  4  U.S.  gallons  of  water.  If  Hala- 
zone  tablets  are  used,  allow  one-half  hour  for  purification  period  due  to  tablet  dis- 
solving slowly. 

(b)  Water  Containers  and  Systems  for  Drinking  Water  and  Culinary  Purposes: 
All  containers  used  for  this  purpose  shall  be  tightly  covered  and  provided  with  a 
tap  outlet.  They  shall  be  sterilized  once  a  week,  or  more  often,  if  necessary  by 
filling  the  container  and  adding  1  ounce  of  commercial  bleach  for  a  5-gallon  con- 
tainer; 10  ounces  will  sterilize  a  50-gallon  container.  Closed  water  systems  equipped 
widi  filters  require  flushing  and  sterilization  annually;  systems  with  no  filters  require 
flushing  and  sterilization  every  three  months  or  more  often  if  contamination  is 
suspected.  Individual  disposable  cups  and  dispensers  shall  be  provided  and  used 
for  drinking  water.  Common  drinking  cups  or  dippers  are  prohibited. 

4.7.3.3  Refrigerators 

(a)  Ice  boxes  should  not  be  used  unless  essential,  and  when  used  shall  be 
emptied  and  washed  out  weekly  with  a  sterilizing  solution.  Electric  refrigerators 
shall  be  emptied,  defrosted  and  washed  out  once  a  month.  (Use  1  teaspoonful  of 
chlorox  to  1  ounce  of  detergent-bactericide  in  a  IM-gallon  pail  of  hot  water.)  An 
open  container  of  baking  soda  placed  in  refrigerators  will  assist  in  odor  control  and 
should  be  replaced  each  montii.  In  case  of  a  breakdown,  it  is  essential  perishable 
foods  be  obtained  on  a  day-to-day  basis,  particularly  in  warm  weather. 

4.7.3.4  Dishes  and  Utensils 

(a)  After  each  meal,  all  dishes,  utensils  and  equipment  shall  be  washed  and 
sterilized  using  1  ounce  of  detergent-bactericide  powder  to  1  gallon  of  hot  water 
in  a  sink  filled  with  hot  water.  Change  water  every  30  minutes.  Cracked  or  chipped 
dishes  and  damaged  table  utensils  shall  not  be  used  and  are  to  be  replaced.  Clean 
dishes  shall  be  stored  in  an  enclosed  cabinet  above  floor  level. 

4.7.3.5  Insect  Control 

(a)  It  is  essential  that  all  kitchen,  dining,  food  storage  and  personal  wash  areas 
be  kept  free  of  flies,  cockroaches  and  other  insects.  All  doors,  windows,  and  roof 
vents  shall  be  properly  screened  and  screen  doors  kept  securely  closed.  A  sufficient 


Manual  Recommendations 191 

supply  of  insecticide  and  spray  containers  shall  be  kept  on  hand.  Use  of  vapour 
strips  is  not  recommended. 

4.7.3.6  Cleaning  of  Kitchen,  Dining,  Food  Storage  and  Personal  Wash  Areas 

(a)  Floors  are  to  be  swept  and  washed  each  day.  All  table  tops  in  food  and 
dining  areas  shall  be  covered  with  a  smooth,  seamless,  impervious  material  and 
shall  be  washed  following  each  meal  using  1  ounce  of  chlorox  to  1  U.S.  gallon  of 
hot  water.  Shelving  and  cupboards  shall  be  maintained  in  a  clean  and  orderly  con- 
dition at  all  times.  The  use  of  food  and  vegetables  storage  bins  shall  be  eliminated. 
Food  preparation  areas  surrounding  cook  stoves  are  to  be  thoroughly  cleaned  and 
kept  free  from  food  spills,  grease  accumulations,  etc.  Foods  shall  be  removed  from 
tables  following  each  meal  and  not  replaced  until  20  minutes  before  the  next  meal 
serving  time.  Any  food  tJwt  is  unfit  or  of  a  suspicious  nature  is  to  be  condemned 
and  replaced.  The  walls  of  all  kitchen  and  dining  areas  shall  be  washed  down  a 
minimum  of  every  sLx  months  and  more  frequently  if  required,  using  /2  cup  chlorox 
to  1  U.S.  gallon  of  hot  water. 

4.7.3.7  Personal  Cleanliness 

(a)  Cooking  and  food-handling  personnel  shall  wash  their  hands  thoroughly 
with  hot  water  and  soap  before  starting  work  and  after  each  visit  to  the  toilet. 
Signs  shall  be  posted  to  this  effect.  Cooks  and  all  food-handling  personnel  shall  wear 
clean,  white  clothing  and  aprons  and  shall  carry  current  medical  cards. 

4.7.3.8  Garbage  and  Waste  Disposal 

(a)  Polyethylene  or  plastic  bags  shall  be  supplied  and  used  as  garbage  pail 
liners  and  shall  be  disposed  of  in  accordance  with  local  regulations,  or  by  burying 
in  a  covered  garbage  pit  where  permitted.  A  garbage  pit  shall  be  prepared  (where 
permitted)  and  located  not  less  than  100  ft  from  the  kitchen  car.  When  the  gang 
moves,  covers  will  be  removed  and  pits  filled  completely  with  earth.  All  liquid 
waste  water  shall  be  removed  by  approved  drainage  hoses  or  pipes  to  municipal 
sewers,  where  available,  or  to  prepared  sump  pits,  covered,  located  not  less  than 
50  ft  from  any  gang  car  or  unit.  When  this  method  is  used,  sump  pits  are  to  be 
completely  filled  and  covered  with  earth  when  the  gang  moves. 

4.7.3.9  Toilets 

(a)  Recirculating  Toilets  in  portable  accommodation  units  and  other  equip- 
ment shall  be  given  a  thorough  cleaning  and  recharging  every  5  to  8  days,  or  when 
liquid  appears  in  the  bottom  of  tlie  bowl.  To  empty  the  recirculating  toilet:  (1) 
ensure  drainage  piping  to  sewer  or  sump  pit  is  properly  attached  to  exterior  toilet 
drains;  (2)  open  the  valve  after  removing  the  front  skirt;  (3)  allow  waste  to 
thoroughly  drain  tiirough  drainage  hose  or  pipe  to  sewer,  sump  pit,  or  tank  truck; 
(4)  open  and  close  valve  as  required  to  rinse  thoroughly  and  flush  system  several 
times  using  clean  water;  (5)  close  valve  and  replace  skirt;  (6)  pour  three  meas- 
ured gallons  of  water  into  toilet  bowl,  press  flush  button  and  add  deodorant-bac- 
tericide,  in  accordance  with  manufacturers  instructions,  into  bowl  while  it  is  flushing. 
Once  recharged,  it  will  operate  effectively  for  approximately  80  usages  over  a 
5-  to  8-day  period.  Care  is  to  be  exercised  to  ensure  that  overfilling  in  the  recharge 
routine  above  does  not  occur,  causing  damage  and  malfunction  of  the  toilet. 
Whether  pit  privies  or  sump  pits  for  recirculating  toilets  are  used,  extreme  caution 
is  to  be  exercised  to  ensure  that  pollution  of  any  water  course  or  well  does  not 
occur. 


192        Bulletin  655 — American  Railway  Engineering  Association 

(b)  If  other  type  toilets  are  used,  they  must  be  in  compliance  with  local  health 
and  sanitary  regulations. 

4.7.3.10  Bunk  Cars  and  Accommodation  Units 

(a)  All  areas  shall  be  kept  in  a  neat  and  tidy  condition  at  all  times.  The  floors 
shall  be  swept  and  washed  a  minimum  of  once  per  week  or  more  frequently  if 
required.  All  windows  shall  be  screened.  All  units  and  bedding  shall  be  aired  regu- 
larly, preferably  once  per  week.  Outside  work  clothing  should  not  be  kept  or  hung 
in  sleeping  areas,  but  should  be  kept  in  areas  provided  for  this  purpose.  In  portable 
accommodation  units,  tlie  summer  circulating  fan  system  is  to  be  used  at  all  times 
in  warm  weather.  The  hanging  of  washing  in  rooms  or  sleeping  areas  is  prohibited. 
All  washing  is  to  be  hung  only  in  areas  provided  for  this  purpose.  All  windows 
shall  be  thoroughly  washed  inside  and  out  a  minimmn  of  twice  yearly. 

4.7.4  Shut-Down  of  Units 

(a)  If  units  are  to  be  shut-down  for  any  lengthy  period,  the  following  steps 
should  be  taken: 

1.  Drain  all  toilets  and  flush  thoroughly. 

2.  Drain  all  water  systems  in  all  type  units. 

3.  Open  all  faucets  at  sinks  and  showers. 


Manual   Recommendations 
Special  Committee  on  Concrete  Ties 

J.  R.  Williams  (chairman,  committee),  R.  J.  Brueske,  K.  C.  Euscorn,  W.  E.  Fuhr, 
C.  L.  Gattox,  M.  B.  Hansen',  D.  L.  JER^LAN•,  T.  C.  Netherton,  E.  L.  Robin- 
son, G.  H.  Way,  J.  W.  Weber. 

Your  committee  submits  for  adoption  and  publication  as  Part  10  of  Chapter  3 
of  the  Manual  the  following  perfomiance  specifications  for  concrete  ties  and  fasten- 
ings. These  specifications  are  a  revised  version  of  the  preliminary  specifications 
published  in  Bulletin  644,  September-October  1973.  The  corrections  to  the  prelimi- 
nary specifications  published  in  Bulletin  650,  November-December  1974,  have  been 
incorporated  therein. 

Part  10 
Concrete  Ties  (and  Fastening's) 

CONTENTS 

Section  Page 

Foreword    195 

10.1  General   Considerations    196 

10.1.1  Introduction    196 

10.1.2  Vertical  Loads    197 

10.1.3  Lateral  Loads   200 

10.1.4  Longitudinal    Loads     200 

10.1.5  Rail   200 

10.2  Material    201 

10.2.1  General    201 

10.2.2  Concrete    202 

10.2.3  Metal    Reinforcement    202 

10.2.4  Tie  Pads    205 

10.2.5  Insulation     205 

10.2.6  Fastenings    205 

10.3  Tie   Dimensions,   Configuration  and   Weight    206 

10.3.1  Special    Considerations    206 

10.3.2  Requirements    206 

10.4  Fle.xural  Strength  of  Prestressed  Monoblock  Ties   208 

10.4.1  Flexural  Performance   Requirements   for   Prestressed   Monoblock 
Designs    208 

10.4.2  Design    Considerations    208 

10.4.3  Test  Requirements  for  Approving  the  Design  of  a  Monoblock 

Tie   209 

193 


194       Bulletin  655 — American  Railway  Engineering  Association 


10.5  Flcxural  Strength  of  Two-Block  Ties   210 

10.5.1  Design  Flcwural  Requirements  for  Two-Block  Ties   210 

10.5.2  Test   Requirements   for  Approving   the   Design   of  a   Two-Block 
Tie    211 

10.6  Longitudinal   Rail   Restraint    211 

10.6.1     Requirements     211 

10.7  Lateral    Rail    Restraint    212 

10.7.1     Rail  Fastening  Requirements   212 

10.8  Electrical   Properties    212 

10.8.1     Requirements    212 

10.9  Testing  of  Monoblock  Ties    212 

10.9.1  Design  Tests  of  Monoblock  Ties 212 

10.9.2  Production  Quality  Control  of  Monoblock  Ties 217 

10.10  Testing  of  Two-Block  Ties    218 

10.10.1  Design  Tests  of  Two-Block  Ties   218 

10.10.2  Production  Quality  Control  of  Two-Block  Ties    220 

10.11  Recommended  Practices  for  Shipping,  Handling,  Application  and  Use..   221 

10.11.1  Shipping    221 

10.11.2  Handling   222 

10.11.3  Placement  and  Initial  Roadbed  Support   222 

10.11.4  Placement  of  Rail  and  Fastenings  in  New  Construction 222 

10.11.5  Tamping    223 

10.11.6  Track  Geometry   223 

10.12  Ballast    223 

10.12.1  General  Characteristics    223 

10.12.2  Quality  Requirements    223 

10.12.3  Grading    Requirements    223 

10.12.4  Handling    223 

10.12.5  Inspection    223 

10.12.6  Testing    224 

10.13  Commentary    224 

10.13.1  Flexural  Strength  of  Monoblock  Ties   224 

10.13.2  Fle.xural  Strength  of  Two-Block  Ties   225 

10.13.3  Longitudinal  Rail  Restraint   226 

10.13.4  Lateral  Rail  Restraint   227 

10.13.5  Electrical   Properties    228 


Manual   Recommendations 195 

FOREWORD 

This  specification  is  intended  to  provide  necessary  guidance  in  the  design,  manu- 
facture and  use  of  concrete  ties  and  their  components  for  main  Hue  standard  gage 
railway  track  systems.  The  specification  contains  minimum  performance  requirements 
of  components  for  concrete  tie  railway  track  based  on  a  variety  of  permissible  tie 
spacings  and  ballast  depths.  Track  constructed  of  tie  and  fastener  components  meeting 
the  specifications  applicable  to  the  anticipated  usage  should  be  expected  to  give 
satisfactory  performance  under  current  AAR-approved  maximum  axle  loads. 

The  specification  covers  materials,  physical  dimensions,  and  structural  strength 
of  prestressed  monoblock  and  prestressed  and  conventionally  reinforced  two-block 
concrete  ties.  In  addition,  longitudinal  and  lateral  load  restraint  requirements  as 
well  as  the  electrical  performance  requirements  of  rail  fastener  and  tie  combinations 
are  given.  Laboratory  tests  for  tlie  determination  of  the  suitability  of  new  designs 
are  specified,  as  are  necessary  quality-control  procedures  during  manufacture.  The 
specification  does  not  cover  techniques  nor  equipment  for  the  manufacture  of 
concrete  ties  or  fastenings. 

Where  current  specifications  or  recommended  practices  of  other  technical 
societies,  such  as  the  American  Society  for  Testing  and  Materials  or  the  American 
Concrete  Institute,  are  appropriate,  they  are  made  part  of  this  specification  by 
reference. 

The   following   definitions   are   applicable   to   this   specification: 

1.  Cross  Tie — A  transverse  component  of  a  track  system  whose  functions 
are  the  control  of  track  gage  and  the  transmitting  of  rail  loads  to  ballast. 

2.  Fastening — A  component  or  group  of  components  of  a  track  system 
which  affixes  the  rail  to  the  cross  ties. 

3.  Flexure  Strength — Resistance  to  bending. 

4.  Insert — A  device  for  securing  an  assembly  and/or  the  rail  to  the  tie.  It 
may  be  cast  in  the  tie  at  the  time  of  manufacture  or  placed  in  a  cored, 
cast  or  drilled  hole  in  the  tie. 

5.  Lateral  Load — A  load,  or  vector  component  of  a  load,  at  the  gage 
corner  of  the  rail  parallel  to  the  longitudinal  axis  of  tlie  tie,  and  perpen- 
dicular to  tlie  rail. 

6.  Longitudinal  Load — A  load  along  the  longitudinal  axis  of  a  rail. 

7.  Negative  Bending — Bending  of  a  concrete  tie  by  application  of  load 
that  produces  tension  in  the  top  surface  of  the  tie. 

8.  Positive  Bending — Bending  of  a  concrete  tie  by  application  of  a  load 
that  produces  tension  in  the  bottom  surface  of  the  tie. 

9.  Prestressing  Tendon — A  strand,  wire  or  bar,  within  a  concrete  member, 
which  under  tension,  precompresses  the  concrete. 

10.  Prestressed  Tie — A  tie  utilizing  precompressed  concrete  and  prestressing 
tendons  to  resist  flexure.  Under  design  loads  the  tensile  strength  of  the 
concrete  in  the  tension  faces  of  the  tie  is  not  exceeded. 

11.  Prestressed-Reinforced  Tie — A  reinforced  concrete  tie  which,  in  addi- 
tion to  longitudinal  reinforcing  steel,  uses  prestressing  tendons  to  resist 
bending  but  in  which  tension  exceeding  the  tensile  strength  of  the  con- 
crete may  occur  in  the  precompressed  concrete  under  design  loads.  If 
cracks  do  occur,  the  resulting  crack  widths  do  not  exceed  specified  values. 


196       Bulletin  655 — American  Railway  Engineering  Association 

12.  Pretensioned  Concrete  Tie — A  prestressed  concrete  tie  using  pretension 
tendons  to  precompress  concrete. 

13.  PosTTENSiONED  CONCRETE  TiE — A  prestressed  concrete  tie  using  post- 
tension  tendons  to  precompress  concrete. 

14.  PosTTENsiONED  Tendon — A  reinforcing  member  which  adds  structural 
strength  to  a  prestressed  concrete  tie  by  placing  it  in  compression.  This 
member  is  tensioned  after  the  setting  of  concrete. 

15.  Pretension  Tendon  (strand  or  wire) — A  reinforcing  member  which  adds 
structural  strength  to  a  prestressed  concrete  tie  by  placing  it  in  compres- 
sion. This  member  is  tensioned  prior  to  tlie  placement  of  concrete. 

16.  Rail  Seat — The  area  of  the  canted  plane  of  a  tie  on  which  rail  rests 
that  lies  within  the  confines  of  the  rail  base. 

17.  Reinforced  Concrete  Tie — A  tie  reinforced  with  deformed  steel  bars, 
welded  wire  fabric,  deformed  wire,  or  bar  or  rod  mats  and  using  non- 
precompressed  concrete.  Under  design  loads  the  tensile  strength  of  the 
concrete  in  tlie  tension  faces  of  the  tie  is  exceeded;  however,  tlie  resulting 
crack  widths  do  not  exceed  specified  values. 

18.  Reinforcement  or  Reinforcing  Steel — Steel,  excluding  prestressing 
tendons,  introduced  within  a  concrete  tie  to  improve  its  structural 
strength. 

19.  Structural  Crack — A  crack  originating  in  the  tensile  face  of  the  tie, 
extending  to  the  outermost  level  of  reinforcement  or  prestressing  tendons 
and  which  increases  in  size  under  application  of  increasing  load. 

20.  Vertical  Load — A  load  or  vector  component  of  a  load,  at  right  angles 
to  a  line  joining  the  two  rail  seats  of  the  tie  and  normal  to  the  longitudi- 
nal axis  of  the  rail. 

10.1  GENERAL  CONSIDERATIONS 
lO.I.l  INTRODUCTION 

In  supporting  and  guiding  railway  vehicles,  the  track  structure  must  restrain 
repeated  lateral,  vertical  and  longitudinal  forces.  As  elements  of  the  track  structure, 
individual  cross  ties  receive  loads  from  the  rails  or  fastenings  and  in  turn  transmit 
loads  to  the  ballast  and  subgrade.  Consequently,  the  design  of  a  tie  affects  and  is 
affected  by  characteristics  of  other  components  of  the  track  structure.  The  use  of 
concrete  railway  ties  introduces  different  considerations  into  the  design  and  installa- 
tion of  track  systems.  When  such  systems  are  properly  designed  and  the  component 
parts  properly  interrelated,  installed  and  maintained,  concrete  railway  tie  systems 
can   provide   track   of   superior  quaHty. 

The  analysis  of  requirements  for  such  systems  must  necessarily  involve  not  only 
the  tie  but  all  components  of  the  track  system,  their  interdependency  and  the  condi- 
tions under  which  they  must  be  applied.  Thus,  concrete  tie  track  systems  involve: 

•  The  rail,  tie,  fastenings,  ballast,  subgrade  and  base, 

•  The  quality  of  each  component,  method  of  manufacture,  installation  and 
maintenance, 

•  The  direction,  magnitude  and  frequency  of  traffic-imposed  loads;  the  effect 
of  environmental  factors  such  as  temperature  and  weather  and  the  overall 
economics  of  installation  and  maintenance,  and 


Manual   Recommendations 197 

•   The  need  to  support  train  weights  and  guide  railway  vehicles  while  restrain- 
ing repeated  lateral,  vertical  and  longitudinal  forces. 

The  performance  specifications  which  follow  provide  the  basic  guidance  needed 
in  the  selection,  design  and  application  of  concrete  railroad  tie  systems.  Success  in 
their  application  will  require  careful  supervision  on  the  part  of  the  engineer  to 
ensure  that  all  components  meet  required  standards  and  that  the  system  is  properly 
installed  and  maintained. 

10.1.2  VERTICAL  LOADS 

10.1.2.1  Tie  Spacing 

The  spacing  affects  rail  Hexure  stress,  compressive  stress  on  ballast  and  roadbed 
and  the  Hexure  stress  generated  in  the  ties  themselves.  For  a  given  set  of  tie  dimen- 
sions and  wheel  loads,  the  consequences  of  increasing  tie  spacing  are  higher  rail 
bending  moments  and  stresses  within  the  individual  ties.  For  the  case  of  constant 
tie,  ballast  and  subgrade  characteristics,  wider  tie  spacings  bring  about  larger 
track  depression  per  unit  of  wheel  load,  i.e.,  lowered  track  modulus.  Conversely, 
reduction  of  tie  spacing  lowers  unit  stress  and  increases  track  modulus. 

These  specifications  cover  concrete  ties  intended  for  track  designs  using  center- 
to-center  spacings  of  cross  ties  of  between  20  and  30  inches. 

10.1.2.2  Cross  Tie  Dimensions 

Use  of  longer,  wider,  or  stiffer  ties  which  increase  the  tie-to-ballast  bearing 
area  has  many  of  the  same  effects  as  reducing  tie  spacing.  There  are,  however, 
limits  beyond  which  an  increase  in  tie  size  is  ineffectual  in  reducing  track  stress 
and  increasing  track  modulus.  The  concentration  of  tie-to-ballast  load  decreases 
with  lateral  distance  from  the  rail.  The  rate  of  decrease  of  load  with  distance  is 
higher  for  flexible  tie  materials  and  designs.  There  is,  therefore,  a  point  beyond 
which  lengthening  tie  design  will  fail  to  significantly  reduce  unit  liearing  load.  There 
are,  in  addition,  required  right-of-way  clearances  and  machinery  limitations  which 
restrict  tie  length. 

Widening  tie  design  has  similar  benefits  to  increases  in  tie  length.  Widening 
tie  design,  however,  beyond  the  point  where  it  is  practical  to  compact  ballast  be- 
neath the  tie  is  ineffective. 

These  specifications  cover  tie  designs  between  7  ft  5  inches  and  9  ft  0  inches 
in  length  and  between  8  inches  and   13  inches  in  width  at  their  bottom  surface. 

10.1.2.3  Load  Distribution 

The  foregoing  discussion  and  the  requirements  following  presume  that  wheel 
loads  applied  to  the  rail  will  be  distributed  by  the  rail  to  several  ties.  This  distri- 
bution of  loads  has  been  confirmed  in  field  investigations.  The  distribution  of  load 
is  dependent  upon  tie  and  axle  spacing,  ballast  and  subgrade  reaction,  and  rail 
rigidity.  The  percentage  of  wheel-to-rail  load  carried  by  an  individual  tie  varies 
from  location  to  location.  A  conservative  estimate  of  the  distribution  is  given  in 
Figure  10.1.2.3.1.  While  rail  stiffness  does  influence  these  percentages,  its  effect 
is  small  compared  to  other  factors.  For  the  sake  of  simplification,  the  distribution 
factors  are  shown  only  as  a  function  of  tie  spacing.  The  values  chosen  are  intended 
to  offset  variations  resulting  from  other  influences. 

10.1.2.4  Impact  Factors 

The   requirements   of   these  specifications   are  based  on   calculations   including 


198       Bulletin  655 — American  Railway  Engineering  Association 


Fig.   10.1.2.3.1 — Approximate  percent  of  axle  load  carried  by  individual  tie. 


22.5  25 

CENTER  TO  CENTER  TIE  SPACING  IN  INCHES 
(1)  Sased  on  an  increase  of  10%  due  to  greater  mass  and  stiffness  of  concrete  ties. 


Manual   Recommendations 199 

an  assimied  impact  factor.  This  factor  is  a  percentage  increase  over  static  vertical 
loads  intended  to  estimate  the  dynamic  effect  of  wheel  and  rail  irregularities.  An 
impact  factor  of  150  percent  has  been  assumed. 

10.1.2.5  Ballast  and  Subgrade 

In  addition  to  tie  size  and  spacing,  ballast  depth  and  subgrade  modulus  are  also 
significant  in  the  manner  a  particular  track  design  restrains  vertical  loading.  Increas- 
ing ballast  depth  tends  to  spread  individual  tie  loads  over  a  wider  area  of  subgrade, 
thereby  reducing  the  unit  subgrade  load  and  consequent  track  depression.  Thus  the 
effect  of  increased  ballast  depth  can  be  similar,  within  limits,  to  that  of  reduced  tie 
spacing.  Stiffer  subgrades  do  not  require  as  low  a  ballast  pressure  as  more  flexible 
subgrades.  Consequently,  they  are  better  able  to  tolerate  wider  tie  spacings,  smaller 
ties,  more  shallow  ballast  depths,  or  all  three  without  failure  or  excessive  track 
depression. 

10.1.2.5.1  Ballast  and  Ballast  Pressure 

The  engineer  must  insure  that  the  design  of  track  does  not  result  in  over-stress 
of  ballast  or  subgrade.  To  do  so,  consideration  must  be  given  to  wheel  loads,  dis- 
tribution factor,  impact  factor,  unit  bearing  capacities  of  the  ballast  and  subgrade, 
and  to  cross  tie  dimensions  and  spacing. 

10.1.2.5.1.1  Ballast  Pressure 

While  tie-to-ballast  pressure  is  not  uniformly  distributed  across  or  along  the 
bottom  of  a  cross  tie,  an  approximate  calculation  can  be  made  of  "average"  pressure 
at  the  bottom  of  the  tie.  The  maximum  ballast  pressure  has  been  found  to  occur 
several  inches  below  this  interface.  Consequently,  the  calculated  value  of  average 
ballast  pressure  at  the  bottom  of  the  tie  understates  the  maximum  ballast  pressure. 
The  average  pressure  at  the  tie  bottom  is  equal  to  axle  load,  modified  by  distribution 
and  impact  factors,  and  di\ided  by  the  bearing  area  of  the  tie: 

-[^  +  ^](-f^)* 

Average  Ballast  Pressure  (psi)  =    -7 

where:       P  ^=  wheel  load  in  pounds. 

IF  =  Impact  factor  in  percent. 

DF  =  distribution  factor  in  percent   (from  Figiu-e   10.1.2.3.1). 

A  ^=  bearing  area  of  cross  ties  in  square  inches. 

The  recoimnended  ballast  pressiue  shovdd  not  exceed  85  psi  for  high-quality, 
abrasion-resistant  ballast.  If  lower  quahty  ballast  materials  are  used,  the  ballast 
pressure  should  be  reduced   accordingly. 

10.1.2.5.1.2  Subgrade  Pressure 

The  pressure  exerted  by  ballast  on  the  subgrade  depends  upon  the  tie-to-ballast 


°  For  example:  Given  8  ft  6  inches  long  by  12  inches  wide  concrete  ties,  what  is  the  calcu- 
lated value  of  bearing  pressure  for  a  locomotive  with  .30,000-lb  wheel  load  if  the  ties  are  to  be 
spaced  at  28  inches? 


IF 


l_          '        100 
Average  Ballast  Pressure   ( psi )    =    2P 


■]{-^) 


A 

_    60,000   (2.5)    (.57) 
~  102   X   12 

=        69.9  psi 


200       Bulletin  655 — American  Railway  Engineering  Association 

pressure,  the  load  distribution  pattern  through  the  ballast,  and  the  depth  of  ballast. 
Refer  to  Section  10.12. 

10.1.3  LATERAL  LOADS 

The  lateral  loads  generated  by  moving  railway  equipment  are  applied  by  wheel 
treads  and  flanges  to  the  rails,  which  in  turn  must  be  held  in  place  by  fastenings, 
ties  and  ballast. 

Lateral  stiff^ness  of  rail  distributes  lateral  loads  to  fasteners  and  their  ties. 
Structural  strength  of  fastenings  and  ties  hold  the  rail  to  gage.  The  mass  of  ties, 
friction  between  the  ties  and  ballast,  lateral  bearing  area  of  ties  (end  surface),  and 
the  mass  of  ballast  all  act  to  restrain  lateral  tie  movement. 

Lateral  track  stability  can,  therefore,  be  increased  by  decreasing  tie  spacing 
of  ties  of  similar  dimensions,  increasing  tie  mass,  increasing  end  bearing  area  of  ties 
per  unit  length  of  track,  and  by  increasing  frictional  resistance  between  ties  and 
ballast.  Structural  strength  of  fastenings  must  be  commensurate  with  the  lateral  load 
individual  ties  restrain,  which  in  turn  is  determined  by  lateral  rail  stiffness  and  tie 
spacing. 

The  magnitude  of  lateral  loads  which  must  be  restrained  depends  not  only 
upon  the  dimensions,  configuration,  weight,  speed  and  tracking  characteristics  of 
the  equipment,  but  also  upon  the  geometric  characteristics  of  the  track  structure. 
Both  the  gross  geometry — whether  the  track  is  straight,  curved  or  how  sharply 
curved — ^and  the  detail  geometry — the  irregularities  and  small  deviations  from  de- 
sign— influence  the  magnitude  of  lateral  load. 

These  specifications  cover  fasteners  capable  of  restraining  individual  lateral 
wheel-to-rail  loads  of  up  to  14,000  pounds  per  linear  foot  of  track  when  these  lateral 
loads  are  accompanied  by  vertical  loads  of  a  similar  magnitude. 

10.1.4  LONGITUDINAL  LOADS 

The  longitudinal  load  developed  by  the  combination  of  thermal  stress  in 
continuous  welded  rail  and  by  traffic  is  transferred  by  the  fastenings  to  the  ties  and 
ultimately  restrained  by  mass  internal  friction  of  ballast.  Consequently,  the  longi- 
tudinal bearing  area  (side  area)  of  ties  per  unit  of  track  length,  friction  between 
bottom  of  ties  and  ballast,  and  physical  properties  of  ballast  ultimately  determine 
the  track  resistance  to  longitudinal  movement.  Resistance  to  rail  movement  with 
respect  to  ties  is  determined  by  the  characteristics  of  fasteners.  While  total  restraint 
of  longitudinal  rail  movement  is  generally  desirable,  there  are  situations  where  such 
restraint  is  impractical  or  undesirable.  In  conventional  track  construction,  the  limiting 
factor  in  longitudinal  restraint  is  most  often  ballast  resistance.  These  specifications, 
therefore,  apply  to  track  designs  incorporating  a  minimum  of  210  square  inches  of 
side  of  tie  area  per  linear  foot  of  track  and  to  fasteners  for  use  on  such  track,  ofiFering 
1480  lb  resistance  to  longitudinal  rail  movement  per  linear  foot  of  rail. 

10.1.5  RAIL 

10.1.5.1  Flexure  Requirement 

The  interaction  of  rail  and  ties  has  been  discussed  in  Articles  10.1.3  and  10.1.4 
with  respect  to  distribution  factors,  tie  spacing,  and  vertical  loads.  The  flexure  stress 
generated  in  rail  under  load  is  a  function  of  applied  bending  moment  and  the  section 
modulus  of  rail.  Rail  bending  moment  is  in  turn  determined  by  wheel  load,  axle 
spacing,  and  track  modulus.  Most  modern  rail  sections  are  capable  of  bearing  current 


Manual   Recommendations 201 

wheel  loads  on  tie  spacings  of  up  to  30  inches  with  normal  ballast  support  without 
distress.  It  is  recommended  that  the  engineer  calculate  the  maximum  bending  stress 
for  rail  sections  lighter  than  100  lb/yd  if  their  use  is  anticipated.  The  following 
equation  may  be  used  for  this  purpose: 

_     Mc^  _     ?c    4/~E^" 
^  -       J  /     t    64a< 

Where:   S  =:  maximum  fiber  stress  in  rail  (psi). 

c  =  distance  from  neutral  axis  to  outer  edge  of  base  or  head  (inches). 

/  =  moment  of  inertia  of  rail  section  ( inches* ) . 

E  =  modulus  of  elasticity  of  steel  (psi). 

At  =  track  modulus  (pounds/inch/inch). 

P  =  wheel  load  (pounds). 


M 


I     El 
=   P      a/  ~^ —  =  bending  moment  ( inch-pounds  ] 


10.1.5.2  RaU  Joints 

(a)  To  achieve  the  maximum  benefits  and  economy  from  the  use  of  concrete 
raihoad  ties  it  is  recommended  that,  in  main-line  track,  they  be  used  in  conjunction 
with  continuous  welded  rail.  If  concrete  ties  are  used  in  conventional  bolted  track 
or  at  the  ends  of  continuous  welded  rail,  care  should  be  exercised  to  see  that  the 
juncture  of  two  rails  does  not  occur  over  a  concrete  tie.  The  magnitude  of  impacts 
on  a  tie  placed  under  the  juncture  of  two  rails  could  be  destructive  to  the  rail  seat 
and  fastenings   in  high-speed  track. 

(b)  It  is  recommended  that  concrete  ties  not  be  installed  within  the  limits 
of  insulated  joints  or  witliin  the  limits  of  special  timber  dimensions  of  turnouts  and 
crossovers. 

10.1.5.3  Effect  of  Mass  on  Track  Stability 

(Under  development) 

10.2  MATERIAL 

10.2.1  GENERAL 

Because  it  is  impractical  at  this  time  to  provide  a  performance  test  to  assure 
the  durability  of  concrete  ties  and  their  accessories,  it  is  necessary  to  include  specifi- 
cations for  the  materials  used  in  their  manufacture.  Deviation  from  the  material 
specifications  may  only  be  made  with  the  prior  approval  of  the  engineer. 


"Tor  example:  Given  track  modulus  of  3,000  Ib/inch/inch  and  90-lb  RA-A  rail  with 
I  =  38  7  inches*  and  c  =  2.54  inches,  what  tensile  stress  is  developed  under  a  30,000-lb  wheel 
load? 


-w- 


EI 


64/i 


=     30.000   (2.54)   y   ^30)    (10)«   (38.7) 


-gg^ y  64   (3,000) 


1968 


9     {  /l/     6046.8      j     =    17,362  psi 


"'First   Progress   Report    of   the    Special   Committee   on   Stresses    in   Track,    Vol.    19   AREA 
proceedings,  p.   887. 


202       Bulletin  655 — American  Railway  Engineering  Association 

10.2.2  CONCRETE 

The  minimum  28-clay-clesign  compressive  strength  of  concrete  used  for  concrete 
ties  shall  be  7000  psi  as  deteniiined  by  ASTM  Method  of  Test  C  39.  The  test  cylin- 
ders  shall  be  made  and  stored  as  specified  in  ASTM  Specification  C  31."* 

10.2.2.1  Cement 

Cement  shall  be  portland  cement  and  shall  meet  the  requirements  of  ASTM 
Specification  C  150.  Air-entraining  cement,  if  used,  shall  also  meet  the  requirements 
of  ASTM  C  150. 

10.2.2.2  Aggregates 

Both  fine  and  coarse  aggregates  shall  meet  the  requirements  of  the  AREA 
Specifications  for  Aggregates,  Part  1,  Section  C,  Chapter  8  of  the  AREA  Manual. 

10.2.2.3  Mixing  Water 

Mixing  water  shall  meet  the  requirements  of  the  AREA  Specifications  for  Mixing 
Water,  Part  1,  Section  D,  Chapter  8  of  the  AREA  Manual.  In  addition,  the  mixing 
water,  including  tliat  portion  of  the  mixing  water  contributed  in  the  form  of  free 
moisture  on  the  aggregates,  shall  not  contain  deleterious  amounts  of  chloride  ion."* 

10.2.2.4  Admixtures 

Additives  containing  chlorides  shall  not  be  used. 

10.2.2.5  Curing 

It  is  recommended  that  the  concrete  be  cured  by  a  method  or  procedure  such 
as  set  forth  in  Part  1,  Section  P,  Chapter  8  of  tlie  AREA  Manual. 

10.2.3  METAL  REINFORCEMENT 

10.2.3.1 

Wire  and  strands  for  tendons  in  prestressed  concrete  shall  conform  to  "Specifi- 
cations for  Uncoated  Seven-Wire  Stress-Relieved  Strand  and  Wire  for  Prestressed 
Concrete"  (ASTM  A  421).  Strands  or  wire  not  specifically  itemized  in  ASTM  A  416  or 
A  421,  including  stiands  with  constructions  other  than  those  listed  in  A  416,  may  be 
used  provided  they  conform  to  at  least  the  minimum  requirements  of  these  ASTM 
specifications  and  have  no  properties  which  make  them  less  satisfactory  than  those 
listed  in  ASTM  A  416  or  A  421. 

10.2.3.2 

High-strength  alloy  steel  bars  for  posttensioning  tendons  shall  be  proof- 
stressed  during  manufacture  to  85  percent  of  the  minimum  guaranteed  tensile 
strength.  After  proof  stressing,  bars  shall  be  subjected  to  a  stress-relieving  heat 
treatment  to  produce  the  prescribed  physical  properties.  After  processing,  the 
physical  properties  of  the  bars  when  tested  on  full  sections,  shall  conform  to  the 


d'  If  the  results  of  performance  tests  demonstrate  satisfactorily  to  the  user  that  the  resistance 
to  abrasion  and  weathering  of  the  concrete  is  adequate  in  the  railway  track  environment,  the  pro- 
visions  of  this  requirement  may  be  waived. 

<2>  A  chloride  ion  content  greater  than  400  ppm  might  be  considered  detrimental,  and  it 
is  recommended  that  levels  well  below  this  value  be  maintained  if  practicable. 

Chloride  ions  contained  in  the  aggregate  and  in  admixtures  should  be  considered  in  evaluating 
the  acceptability  of  total  chloride  ion  content  of  the  mixing  water.  (From  the  commentary  to 
ACI  318-71). 


Manual   Recommendations     203 

following  minimum  properties:  Yield  strength  (0.2  percent  offset):  0.85  f's  where 
f's  is  the  ultimate  strength  of  the  prestressing  steel.  Elongation  at  rupture  in  20 
diameters:   4  percent.  Reduction  of  area  at  rupture:   20  percent. 

10.2.3.3 

Reinforcing  jjars  shall  conform  to  one  of  the  following  specifications,  except 
that  yield  strength  shall  correspond  to  that  determined  by  tests  on  full-size  bars; 
and  for  reinforcing  bars  with  a  specified  yield  strength  of  the  reinforcing  steel,  fy, 
exceeding  60,000  psi,  /,,  shall  be  the  stress  corresponding  to  a  strain  of  0.35  percent: 

(a)  "Specifications  for  Deformed  Billet-Steel  Bars  for  Concrete  Reinforce- 
ment" (ASTM  A  615). 

(b)  "Specifications  for  Rail-Steel  Deformed  Bars  for  Concrete  Reinforce- 
ment" (ASTM  A  616).  If  bars  meeting  these  specifications  are  to  be 
bent,  they  shall  also  meet  the  bending  requirements  of  ASTM  A  615  for 
Grade  60. 

(c)  "Specifications  for  Axle-Steel  Deformed  Bars  for  Concrete  Reinforce- 
ment" (ASTM  A  617). 

10.2.3.4 

Plain  bars  for  spiral  reinforcement  shall  conform  only  to  the  strength  require- 
ments and  minimum  elongation  of  the  appropriate  specification  prescribed  in  Art. 
10.2.3.3. 

10.2.3.5 

Reinforcement  to  be  welded  shall  be  indicated  on  the  drawings  and  the  welding 
procedure  to  be  used  shall  be  specified.  The  ASTM  specification  shall  be  supple- 
mented by  requirements  assuring  satisfactory  weldability  by  this  procedure  in 
conformity  with  "Recommended  Practices  for  Welding  Reinforcing  Steel,  Metal 
Inserts,  and  Connections  in  Reinforced  Concrete  Construction"  (AWS  D  12.1). 
The  supplementary  specification  requirements  shall  be  designated  in  the  order,  and 
conformance  with  these  requirements  shall  be  confirmed  by  the  supplier  at  the  time 
of  delivery. 

10.2.3.6 

Bar  and  rod  mats  for  concrete  reinforcement  shall  be  the  clipped  type  con- 
forming to  "Specifications  for  Fabricated  Steel  Bar  or  Rod  Mats  for  Concrete  Rein- 
forcement"  (ASTM  A  184). 

10.2.3.7 

Plain  wire  for  spiral  reinforcement  shall  conform  to  "Specifications  for  Cold- 
Drawn  Steel  Wire  for  Concrete  Reinforcement"  (ASTM  A  82),  except  that  fy  shall 
be  the  stress  corresponding  to  a  strain  of  0.35  percent  if  the  yield  strength  specified 
in  the  design  exceeds  60,000  psi. 

10.2.3.8 

Welded  plain  wire  fabric  for  concrete  reinforcement  shall  conform  to  "Specifi- 
cations for  Welded  Steel  Wire  Fabric  for  Concrete  Reinforcement"  (ASTM  A  185), 
and  to  the  stipulation  of  Art.  10.2.3.7  regarding  measurement  of  fy,  except  that 
welded  intersections  shall  be  spaced  not  farther  apart  than  12  inches  in  the  direction 
of  the  principal  reinforcement. 


204        Bulletin   655 — American  Railway  Engineering  Association 

10.2.3.9 

Deformed  wire  for  concrete  reinforcement  shall  conform  to  "Specifications  for 
Deformed  Steel  Wire  for  Concrete  Reinforcement"  (ASTM  A  496),  except  that 
wire  shall  not  be  smaller  than  size  D-4"*  and  that  fy  shall  be  the  stress  corresponding 
to  a  strain  of  0.35  percent  if  the  yield  strength  specified  in  the  design  exceeds 
60,000  psi. 

10.2.3.10 

Welded  deformed  wire  fabric  for  concrete  reinforcement  shall  conform  to 
"Specifications  for  Welded  Deformed  Steel  Wire  Fabric  for  Concrete  Reinforcement" 
(ASTM  A  947)  and  to  the  stipulation  of  Art.  10.2.3.9  regarding  measurement  of  fy, 
except  that  welded  intersections  shall  be  spaced  not  farther  apart  than  16  inches  in 
the  direction  of  the  principal  reinforcement. 

10.2.3.11 

Steel  pipe  or  tubing  for  composite  members  shall  conform  to  one  of  the 
following: 

(a)  Grade  B,  ASTM  A  53. 

(b)  ASTM  A  500. 

(c)  ASTM  A  501. 

(d)  Grade  specified  by  the  manufacturer  and  supported  by  design  and  test 
data  subject  to  the  approval  of  the  engineer. 

10.2.3.12 

Structural  steel  used  in  conjunction  with  reinforcing  for  composite  members 
shall  conform  to  one  of  the  following: 

(a)  ASTM  A  36. 

(b)  ASTM  A  242. 

(c)  ASTM  A  440. 

(d)  ASTM  A  441. 

(e)  ASTM  A  588. 

(f)  Grade  specified  by  manufacturer  and  supported  by  design  and  test  data 
subject  to  the  approval  of  the  engineer. 

10.2.3.13  Reinforcement  Placement  and  Spacing 

The  placement  and  spacing  of  reinforcement,  prestressing  steel  and  prestressing       1 
ducts  shall  be  in  accordance  with  all  applicable  requirements  of  the  AREA  Manual, 
Chapter  8,   Part   1,   Section   H — Metal   Reinforcement   Placing,   as  revised   in   1970 
except   that  tolerances  for  placing  shall  meet  the  requirements  of  Art.    10.3.2.12.       1 

10.2.3.13a  Supports  ■ 

Reinforcement,  prestressing  steel,  and  ducts  shall  be  accurately  placed  and 
adequately  supported  before  concrete  is  placed  and  shall  be  secured  against  dis- 
placement within  permitted  tolerances.  Welding  of  crossing  bars  shall  not  be 
permitted  for  assembly  of  reinforcement  unless  authorized  by  the  engineer. 


<3*  Deformed  wire  is  denoted  by  the  letter  "D",  followed  by  a  number  indicating  the  wire's 
cross  sectional  area  in  himdredths  of  a  square  inch.  Thus,  the  minimum  size  deformed  wire 
permitted  in  this  specification  must  have  a  cross  sectional   area  of  0.04  square  inches. 


Manual   Recommendations 205 

10.2.4  TIE  PADS 

Abrasion-resistant  pads  or  abrasion-,  vibration-  and  impact-reducing  pads  shall 
be  used  between  the  rail  and  concrete  ties  on  all  main-line  or  other  heavy-traffic 
tracks  to  minimize  the  possibility  of  abrasive  action  in  the  rail  bearing  area  of  the 
ties.  It  is  recommended  tliat  such  pads  also  be  used  on  other  trackage. 

10.2.4.1  Polyethylene  Bearing  Pads 

Polyethylene  bearing  pads,  if  used,  shall  be  black  high-density  plastic,  60  to  65 
D-Durometer,  meeting  current  ASTM  Specification  D  1248,  Type  III,  Grade  3. 
Hardness  shall  be  stable  between  -f  140  F  and  — 40  F. 

10.2.4.2  Elastomeric  Bearing  Pads 

Elastomeric  bearing  pads,  if  used,  shall  be  of  weather-  and  petroleum-resistant 
materials.  Values  for  the  following  ASTM  Test  Method  Specifications  are  under 
study: 

(a)  ASTM  Test  Method  D  573  for  aging  in  air. 

(b)  ASTM  Test  Method  D  395,  Method  B,  for  compression  set. 

(c)  ASTM  Test  Method  D  518,  Procedure  A  and  D  518-61,  for  resistance 
to  the  atmospheric  ozone. 

(d)  ASTM  Test  Method  D  471  for  resistance  to  water. 

(e)  ASTM  Test  Method  D  471  for  resistance  to  oil. 

The  hardness  of  such  pads  shall  be  between  60  and  80  A-Durometer  as  specified 
by  the  purchaser.  A  tolerance  of  ±  5  shall  be  permitted  from  that  specified.  Pads 
using  ridges,  grooves  or  other  patterns  are  permissil^le,  providing  that  such  patterns 
do  not  reduce  the  protection  offered  by  the  pad. 

10.2.4.3  Other  Types  of  Bearing  Pads 

Bearing  pads  may  also  be  made  of  nylon,  laminated  fiber,  wood  or  other 
abrasion-resistant  material.  Such  pads  shall  be  used  only  with  the  approval  of  the 
engineer  and  shall  meet  specifications  provided  by  the  engineer. 

10.2.5  INSULATION 

Insulation  shall  be  used  where  necessary  to  prevent  interference  with  signal 
systems  and  deterioration  of  die  fastening  system  through  electrical  leakage. 

10.2.5.1  Nylon  Insulators 

Nylon  insulators,  if  used,  shall  meet  the  requirements  of  the  current  ASTM 
Specification  D  789,  Type  1,  Grade  2,  Specification  for  Nylon  Injection  Molding 
and  Extrusion  Materials. 

10.2.5.2  Other  Insulating  Materials 

Other  insulating  materials  such  as  epoxy  coatings  and  fiberglass  may  be  used 
if  desired  as  long  as  they  provide  sufficient  protection  against  electrical  leakage  and 
meet  the  approval  of  the  engineer.  (See  Art.   10.9.1.14). 

10.2.6  FASTENINGS 

All  fastening  components,  including  hardware  cast  into  the  tie,  shall  be  suitably 
resistant  to  corrosion  and  able  to  withstand  repeated  loads  within  the  railway  track 
environment  without  fatigue  failure  or  excessive  maintenance  requirements.  Use  of 
metals  of  widely  divergent  electrical  potential  in  contact  or  close  pro.ximity  to  one 
another  is  not  recommended. 


206       Bulletin   655 — American  Railway  Engineering  Association 

10.2.6.1  Cap  Screws  and  Rail  Clips 

Cap  screws  used  with  rail  clips  shall  be  a  minimum  of  %  inch  in  diameter  and 
of  sufficient  length  to  provide  a  minimum  engagement  of  1  inch  but  not  to  exceed 
1/2  inches.  They  shall  have  a  minimum  proof  load  of  28,400  lb. 

10.3  TIE  DIMENSIONS,  CONFIGURATION  AND  WEIGHT 

10.3.1  SPECIAL  CONSIDERATIONS 

10.3.1.1  Track  Machinery  Limitations 

In  addition  to  those  considerations  covered  in  Section  10.1  General  Considera- 
tions, the  following  maximum  dimensions  will  permit  tamping  with  many  present-day 
ballast  tamping  machines  and  will  allow  other  related  work  to  be  handled  in  a 
mechanized  manner: 

(a)  Tie  width  z=  13  inches 

(b)  Tie  depth  ==  10  inches 

(c)  Tie  length  =  9  ft  6  inches 

10.3.1.2  Weight 

For  ease  of  handling  it  is  recommended  tliat  the  weight  of  tie  not  exceed 
approximately  800  lb. 

10.3.2  REQUIREMENTS 

10.3.2.1  Length 

The  overall  nominal  length  of  concrete  ties  shall  not  be  less  than  7  ft  5  inches 
nor  more  than  9  ft  6  inches.  A  tolerance  of  plus  Jz  inch  or  minus  /a  inch  from 
nominal  length  is  permitted. 

10.3.2.2  Width 

The  minimum  width  of  ballast  bearing  area  of  tie  shall  not  be  less  than  8  inches. 
Width  of  tie  at  top  surface  from  rail  seat  area  to  end  of  tie  shall  not  be  less  than 
6  inches.  The  maximum  width  must  not  exceed  13  inches.  Tolerance  of  ±  Ys  inch 
from  nominal  width  is  permitted. 

10.3.2.3  Minimum  Depth 

The  minimum  design  depth  of  any  section  of  tie  shall  not  be  less  than  6  inches. 
A  manufacturing  tolerance  of  -f  }i  inch  and  —  Ys  inch  is  permitted  from  design 
depth. 

10.3.2.4  Maximum  Depth 

Maximum  design  depth  of  any  section  of  the  tie  shall  not  be  more  than  10 
inches.  A  manufacturing  tolerance  of  -f  }i  and  —  }a  inch  is  permitted  from  design 
depth. 

10.3.2.5  Track  Gage 

The  concrete  tie/rail  fastening  system  shall  hold  track  gage  to  ±  1/16  incli 
from  that  specified,  exclusive  of  mill  tolerance  in  rail.  Ties  shall  normally  be  manu- 
factured for  4  ft  8/2  inches  track  gage.  If  track  gage  other  than  4  ft  8/2  inches  is 
desired,  it  shall  be  so  specified  by  the  engineer.  The  center  line  of  the  tie  shall  be 
within  /4  inch  of  tlie  center  line  of  track  gage. 


Manual   Recommendations 207 

10.3.2.6  Rail  Cant 

The  rail  seat  shall  provide  for  a  cant  of  1  in  40  ±  2  toward  center  line  of  tie 
unless   otherwise   specified. 

10.3.2.7  Rail  Seat  Plane 

The  rail  seat  shall  be  a  flat  smooth  surface,   ±   1/32  inch. 

10.3.2.8  Differential  Tilt  of  Rail  Seats 

A  differential  tilt  in  the  direction  of  the  rail  of  one  rail  seat  to  the  other  shall 
(on  a  width  of  6  inches)    not  exceed  1/16  inch. 

10.3.2.9  Protrusion  of  Pretensioning  Tendons 

Strands  of  wires  shall  not  project  more  than  1  inch  beyond  the  ends  of  the  ties. 

10.3.2.10  End  of  Posttensioning  Tendons 

To  protect  against  corrosion,  the  ends  of  posttensioning  tendons  shall  not 
protrude  beyond  the  ends  of  the  ties  and  shall  be  covered  to  the  extent  specified 
in  Art.  10.3.2.11  with  concrete,  epoxy  grout  or  other  material  approved  by  the 
engineer. 

10.3.2.11  Concrete  Protection  for  Reinforcement  Against  Corrosion 

The  following  minimum  specified  cover  for  reinforcement,  prestressing  tendons, 
ducts,  or  prestressing  end  fittings'"   shall  be  as  follows: 

(a)  Prestressed,   precast   cross   ties    ( pretensioned   or  post- 
tensioned )     %  inch 

(b)  Reinforced,  precast  cross  ties: 

No.  6  bars,  /4-inch  wire,  and  smaller %  inch 

Other  bars    one  bar  diameter 

10.3.2.12  Tolerances  for  Placing  Reinforcement 

(a)  The  tolerance  for  clear  concrete  protection  (cover)  and  for  depth,  d,^"^ 
for  reinforcing  steel  shall  be  ±  Ys  inch;  for  prestressing  tendons  ±  1/16  inch. 

(b)  The  tolerance  for  longitudinal  location  of  bends  in  reinforcing  bars  shall 
be  ±  2  inches. 

(c)  The  tolerance  for  the  location  of  ends  of  reinforcing  bars  shall  be  ±  '2  inch. 

10.3.2.13  Surface  Finish 

(a)  The  top  and  side  surfaces  of  the  ties  shall  present  a  smooth,  uniform 
appearance.  A  random  scattering  of  surface  voids  will  not  be  cause  for  rejection. 
Heavy  concentrations  of  surface  voids  or  evidence  of  improper  mixing,  vibrating 
or  curing  will  be  cause  for  rejection. 

(b)  The  ends  of  the  ties  need  not  be  flat  planes  or  surfaces,  but  there  shall 
be  no  evidence  of  tearing  of  the  concrete  where  the  prestressing  strands  emerge  or 
of  any  void  in  contact  with  a  strand. 

(c)  Occasional  spalling  of  a  small  portion  of  rail  seat  shoulders  may  occur 
during  the  stripping  operation.  Such  spalling  will  not  be  cause  for  rejection  unless 
it  involves  that  portion  of  a  shoulder  against  which  the  heel  of  rail  fastening  clip 
bears. 


<*'  This   does    not    apply   to   the   ends   of  pretensioning  tendons  which   may   protrude   from   the 
end  of  the  tie.   See   also   Art.    10.3.2.9. 

<5)  Distance    from    extreme    compression    fiber  to    centroid   of   tension    reinforcement. 


208       Bulletin   655 — American  Railway  Engineering  Association 

(d)  Concrete  tics  shall  be  marked  with  indented  or  raised  letters  or  numerals 
to  identify  the  manufacturer,  type  of  tie  and  year  of  manufacture  as  approved  by 
the  engineer. 

10.4  FLEXURAL  STRENGTH  OF  PRESTRESSED  MONOBLOCK 
TIES 

10.4.1  FLEXURAL    PERFORMANCE    REQUIREMENTS    FOR    PRESTRESSED 
MONOBLOCK  DESIGNS 

Table  I 


Spacingi  ^ ) 
(Inches) 

21 

Required  Flexural  Capacity  (Inch- Kips)  Without  Cracking 

Length{  ^  ) 

Rail  Seat  -\- 

Rail  Seat—(  ^  ) 

Center  — 

Center  + 

8'-0 

220 

115 

200 

90 

24 

220 

115 

220 

90 

27 

220 

115 

240 

90 

30 

220 

115 

260 

90 

8'-3 

21 

225 

115 

200 

90 

24 

235 

115 

210 

90 

27 

250 

115 

220 

95 

30 

260 

115 

230 

100 

8'-6 

21 

225 

115 

200 

90 

24 

250 

115 

200 

90 

27 

275 

115 

200 

100 

30 

300 

115 

200 

110 

8'-9 

21 

250 

115 

200 

95 

24 

275 

115 

200 

100 

27 

300 

115 

200 

110 

30 

325 

115 

200 

120 

9'-0 

21 

275 

115 

200 

100 

24 

300 

115 

200 

105 

27 

325 

115 

200 

115 

30 

350 

115 

200 

125 

"'  For  existing  tie  designs  having  reduced  bottom  width  at  center  of  tie:  The  rail  seat  and 
center  positive  flexural  requirements  shall  be  increased  by  10%  and  the  center  negative  flexural 
requirements  shall  be  decreased  by  10%  (but  shall  not  be  less  than  150  inch-kips)  because  of 
the   redistributed   ballast   reaction   associated  with   such   designs. 

<2)  For  tie  spacings  other  than  those  shown,  flexure  requirements  shall  be  determined  by 
interpolation. 

<3)  The  values  shown  in  the  Rail  Seat  ( — )  column  are  based  on  elastic  fastenings  having 
an  overall  vertical  upward  spring  rate  in  the  range  of  200,000  to  350,000  lb  per  inch.  (This 
spring  rate  is  not  necessarily  linear  and  should  be  detemiined  in  the  0.00  to  0.02  inch  deflection 
range.   The   Rail   Seat  negative   values   may  not  be   adequate   for  more  rigid   fastenings. 


10.4.2  DESIGN  CONSIDERATIONS 

10.4.2.1 

As  well  as  satisfying  the  criteria  in  Table  I,  prestressed  concrete  monoblock 
ties  must  also  comply  with  other  criteria  which  accord  with  good  design  practice 
as  laid  down  in  ACI  Code  318. 


Manual  Recommendations  209 


10.4.2.2 

It  is  reconiiiiended  that  the  maximum  precompression  after  all  losses  at  any 
point  in  the  cross  ties  should  not  exceed  2,500  psi. 

10.4.2.3 

Furtliermore,  in  the  case  of  ties  to  which  the  rails  are  to  be  fastened  by  elastic 
fastening  systems,  there  should  be  a  minimum  pre-compressive  stress  at  any  vertical 
cross  section  through  the  rail  seat  area  of  150  psi  after  all  losses  and  without  any 
applied  load.  Because  the  precessional  wave  just  ahead  of  the  wheels  will  create  an 
uplift  force  from  the  rails  to  the  ties  and  because  the  magnitude  of  this  force  will 
depend,  among  other  things,  on  the  weight  of  the  ties  and  the  rigidity  of  the 
fastening  system,  this  minimum  pre-compressive  stress  should  be  higher  for  rigid 
fastening  systems. 

10.4.3  TEST  REQUIREMENTS  FOR  APPROVING  THE  DESIGN  OF  A  MONO- 
BLOCK  TIE 

10.4.3.1 

The  minimum  negative  and  positive  flexural  capacity  at  the  rail  seats  of  the  tie 
shall  be  as  shown  in  Table  I  for  the  tie  length  and  spacing  to  be  used  when  tested 
in   accordance   with   the   Rail  Seat  Vertical   Load  Test  described  in  Art.    10.9.1.4. 

10.4.3.2 

The  minimum  negative  flexural  capacity  at  the  center  of  the  tie  shall  be  as 
shown  in  Table  I  for  the  tie  length  and  spacing  to  be  used  when  tested  in  accord- 
ance with  the  Negative  Bending  Moment  Test  described  in  Art.   10.9.1.6. 

10.4.3.3 

The  minimum  positive  flexural  capacity  at  the  center  of  the  tie  shall  be  as  shown 
in  Table  I  for  the  tie  length  and  spacing  to  be  used  when  tested  in  accordance 
with  the   Positive  Bending   Moment  Test  described  in  Art.    10.9.1.7. 

10.4.3.4 

The  tie  must  meet  the  requirements  of  the  Rail  Seat  Repeated-Load  Test 
described  in  Art.   10.9.1.5. 

10.4.3.5 

The  tie  must  meet  the  requirements  of  the  Bond  Development  or  Tension 
Anchorage  Test  described  in  Art.   10.9.1.8. 


210       Bulletin   655 — American  Railway  Engineering  Association 

10.5  FLEXURAL  STRENGTH  OF  TWO-BLOCK  TIES 

10.5.1  FLEXURAL  PERFORMANCE  REQUIREMENTS  FOR  TWO-BLOCK  DE- 
SIGNS 

Table  II 
Requibed  Flexxtral  Capacity  (Inch-Kips)'*' 


Length  Tie 

Tie{  2 ) 

Railseat — 

Positive^  3 ) 

Railseat — Negative^  *  ) 

Block 

Spacing 

Inches 

Inches 

Reinf.  Tie 

P/S  Tie{  1  ) 

Reinf.  Tie 

P/S  Tiei  « ) 

30 

21 

150 

150 

105 

105 

24 

150 

150 

105 

105 

27 

150 

150 

105 

105 

30 

150 

155 

105 

110 

33 

21 

150 

150 

105 

105 

24 

150 

150 

105 

105 

27 

150 

155 

105 

110 

30 

155 

170 

110 

120 

36 

21 

150 

150 

105 

105 

24 

150 

155 

105 

110 

27 

155 

170 

110 

120 

30 

170 

185 

120 

130 

39 

21 

205 

225 

145 

160 

24 

225 

250 

160 

175 

27 

250 

275 

175 

195 

30 

270 

300 

190 

210 

42 

21 

250 

275 

175 

195 

24 

270 

300 

190 

210 

27 

295 

325 

210 

230 

30 

315 

350 

225 

245 

^1'  Prestressed  or  prestressed-reinforced. 

'-'  For  tie  spacings  other  than  those  shown,  the  flexure  requirements  shall  be  determined  by 
interpolation. 

"'  The  values  shown  in  the  Rail  Seat-Postive,  P/S  Tie  column  above  have  been  increased 
by  10%  to  allow  for  long-term  losses  in  prestressed  ties.  The  resulting  values  and  the  values 
shown  in  the  Rail  Seat-Positive,  Reinf.  Tie  column  above  have  been  rounded  ofiE  to  the  next  larger 
increment  of  5  inch-kips.  Where  applicable  they  also  have  been  increased  to  a  minimum  of  150 
inch-kips. 

<*^  0.7   X    Rail  Seat-Positive  requirement  rounded  to  the  next  larger  increment  of  5  inch-kips. 

10.5.1.1  Allowable  Cracking 

(a)  Reinforced  cross  ties  when  subjected  to  loads  producing  flexure  in  the 
blocks  must  crack  in  order  for  the  main  reinforcement  to  work.  Corrosion  of  steel 
reinforcement  is  related  to  crack  width  and  external  environment.  The  maximum 
crack  width  allowed  in  Art.  10.5. l.le.  Table  III,  should  not  contribute  to  corrosion 
of  steel  reinforcement  under  normal  railroad  environments. 

(b)  Cracks  shall  be  measured  on  the  side  surfaces  of  the  tie  blocks  at  a  level 
directly  opposite  the  reinforcement  closest  to  the  tension  face  of  the  tie.  If  it  is 
not  possible  to  measure  a  crack  at  this  level  due  to  chipping  of  the  concrete  or 


Manual  Recommendations  211 


surface    imperfections,    measurements    shall   be   taken   equidistant   above  and   below 
this  le\el  and  the  two  \alues  averaged  to  obtain  the  width  of  the  crack. 

(c)  Cracks  shall  be  measured  using  a  hand-held  graduated  microscope  of  suffi- 
cient power  and  accuracy  to  measure  crack  widdis  to  the  nearest  0.001  inch. 

(d)  Cracks  shall  not  extend  to  prestressing  tendons  or  longitudinal  reinforcing 
steel  of  less  than  %  inch  diameter. 

10.5.1. le  T.\BLE  III 


Xo.  of  Cracks* 

Max.  Width — Inch 

Avg.  Width — Inch 

1 

0.006 
0.006 
0.006 
0.006 

2 

0.005 

3 

0.004 

4  or  more. 

0.003 

'Per  side  per  tie  block 

10.5.2  TEST  REQUIREMENTS  FOR  APPROVING  THE  DESIGN  OF  A  TWO- 
BLOCK  TIE 

10.5.2.1 

The  minimum  positive  and  negative  flexural  capacity  of  the  tie  blocks  shall  be 
as  shown  in  Table  II  for  the  tie  block  length  and  tie  spacing  to  be  used  when 
tested  in  accordance  with  the  Rail  Seat  Positive  and  Rail  Seat  Negative  Moment 
Tests  described  in  Arts.  10.10.1.4  and  10.10.1.5. 

10.5.2.2 

The  ties  must  meet  the  requirements  of  the  Rail  Seat  Ultimate  Load  Test 
described   in  Art.   10.10.1.9. 

10.5.2.3 

The  ties  must  meet  the  requirements  of  the  Rail  Seat  Repeated  Load  Test 
described  in  Art.   10.10.1.8. 

10.5.2.4 

The  ties  must  meet  the  requirements  of  the  Center  Negative  and  Center  Posi- 
tive  Bending  Moment  Tests  described  in  Arts.   10.10.1.6  and   10.10.1.7. 

10.6  LONGITUDINAL  RAIL  RESTRAINT 

10.6.1  REQUIREMENTS 

Fastenings  for  concrete  ties  must  have  the  ability  to  restrain  longitudinal  move- 
ment of  rail  as  detennined  by  test  procedure  specified  in  Art.  10.9.1.12,  as  follows: 
21-inch  tie  spacing,  2600  lb  per  tie  per  rail. 
24-inch  tie  spacing,  2900  lb  per  tie  per  rail. 
27-inch  tie  spacing,  3300  lb  per  tie  per  rail. 
30-inch  tie  spacing,  3700  lb  per  tie  per  rail. 

Welded  rail  must  be  laid  at  the  proper  temperature  range  or  additional 
anchorage  provided  at  the  ends  of  strings. 


212       Bulletin  655 — American  Railway  Engineering  Association 

10.7  LATERAL  RAIL  RESTRAINT 

10.7.1  RAIL  FASTENING  REQUIREMENTS 

(a)  Track  constructed  of  concrete  ties  and  appropriate  fasteners  shall  not 
experience  gage  widening  of  more  than  }i  inch  when  lateral  wheel  loads  of  35,000  lb 
are  apphed  to  one  rail.  (See  Art.  10.9.1.13  for  design  tests.) 

(b)  If  a  concrete  shoulder  is  used  to  restrain  the  lateral  movement  of  the  rail, 
a  suitable  bearing  surface  shall  be  provided  to  transmit  the  lateral  forces  to  the  tie. 

(c)  Inserts  shall  be  arranged  to  distribute  the  load  uniformly  in  the  body  of 
the  tie  and  through  the  rail  bearing  area.  The  rail  support  insert  shall  withstand 
a  pullout  force  of  12,000  lb.  (See  Arts.  10.9.1.9.1,  10.9.1.11  and  10.9.1.13  for  design 
tests. ) 

10.8  ELECTRICAL  PROPERTIES 

10.8.1  REQUIREMENTS 

Individual  concrete  cross  ties  for  use  in  signal  circuit  tracks  togetlier  with  their 
fastenings  should  be  electrically  isolated  from  the  running  rails  so  as  to  provide  a 
minimum  impedance  of  20,000  ohms  per  tie  when  a-c  energy  of  10  volts,  60  Hertz 
is  applied.  (See  Art.   10.9.1.14  for  test  procedure.) 

10.9  TESTING  OF  MONOBLOCK  TIES 

10.9. 1  DESIGN  TESTS  OF  MONOBLOCK  TIES 

Prior  to  approval  of  concrete  tie  designs,  monoblock  concrete  ties  of  the  design 
under  study  shall  be  subjected  to  testing  for  compliance  with  these  specifications. 
The  tests  specified  herein  shall  be  performed  at  testing  facilities  approved  by  the 
engineer  within  30  days  of  casting. 

From  a  lot  of  not  less  than  ten  ties  produced  in  accordance  with  these  specifi- 
cations, four  ties  will  be  selected  at  random  by  the  engineer  for  laboratory  testing. 
For  design  testing  of  fastenings,  the  manufacturer  shall  also  furnish  a  section  of  the 
tie  or  a  concrete  block  with  rail  seat  and  rail  fastening  system  identical  to  the 
concrete  ties  furnished  for  testing. 

The  tie  block  and  each  of  the  four  ties  submitted  for  testing  shall  be  carefully 
measured  and  examined  to  determine  their  compliance  with  the  requirements  of 
Sections  10.2  and  10.3.  Upon  satisfactory  completion  of  this  examinatin,  the  tie  block 
and  two  ties,  which  shall  be  known  and  identified  as  Tie  "1"  and  Tie  "2",  shall  be 
subjected  to  performance  tests  specified  in  Arts.  10.9.1.4,  10.9.1.5,  10.9.1.6,  10.9.1.7, 
10.9.1.8,  10.9.1.9,  10.9.1.10,  10.9.1.11,  and  10.9.1.12.  The  remaining  two  ties,  which 
will  be  known  and  identified  as  Ties  "3"  and  "4",  will  be  retained  by  the  engineer 
for  further  test  use  (Art  10.9.1.14)  and  as  a  control  for  dimensional  tolerances  and 
surface  appearance  of  ties  subsequently  manufactured. 

10.9.1. 1  Sequence  of  Design  Tests  (Tie  "1") 

The  sequence  of  design  performance  tests  using  Tie  "1"  shall  be  as  follows: 

(a)  Rail  Seat  Vertical  Load  Tests  (described  in  Art.  10.9.1.4) — Shall  be  per- 
formed on  one  rail  seat,  hereinafter  designated  rail  seat  A. 

(b)  Negative   Bending  Moment  Test    (described  in  Art.    10.9.1.6). 


Manual   Recommendations 213 

(c)  Positive    Bending   Moment   Test    (described    in   Art.    10.9.1.7). 

(d)  Rail  Seat  Vertical  Load  Test  (described  in  Art.  10.9.1.4)— Shall  be  per- 
formed on  the  other  rail  seat,  hereinafter  designated  rail  seat  B. 

(e)  Rail   Seat   Repeated  Load  Test    (described  in  Art.    lOLQ.l.S)— Shall  be 
performed  on  rail  seat  B. 

(f)  Bond  Development,  Tendon  Anchorage,  and  Ultimate  Load  Test   (de- 
scribed in  Art.    10.9.1.8) — Shall  be  performed  on  rail  seat  A. 

10.9.1.2  Sequence  of  Design  Tests  (Tie  "2") 

The  sequence  of  design  performance  tests  using  Tie  "2"  shall  be  as  follows: 

(a)  Fastening  Insert  Test  (described  in  Art.  10.9.1.9) — Shall  be  performed 
on  all  inserts. 

(b)  Fastening  Uplift  Test  (described  in  Art.  10.9.1.10)— Shall  be  performed 
on  one  rail  seat. 

(c)  Electrical  Resistance  and  Impedance  Test  (described  in  Art.  10.9.1.14). 

10.9.1.3  Sequence  of  Design  Tests  (Tie  Block) 

The  sequence  of  design  performance  tests  using  the  tie  blocks  shall  be  as 
follows : 

(a)  Fastening  Repeated  Load  Test    (described  in  Art.   10.9.1.11). 

(b)  Fastening  Longitudinal  Restraint  Test   (described  in  Art.   10.9.1.12). 

(c)  Fastening   Lateral   Restraint   Test    (described   in   Art.    10.9.1.13). 

10.9.1.4  Rail  Seat  Vertical  Load  Test 

With  the  tie  supported  and  loaded  as  shown  in  Figure  VII,  a  load  increasing 
at  a  rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  tlie  load  (P) 
required  to  produce  the  specified  rail  seat  negative  moment  from  Art.  10.4.1,  Table  I 
is  obtained.  This  load  shall  be  held  for  not  less  than  3  minutes,  during  which  time 
an  inspection  shall  be  made  to  determine  if  structural  cracking  occurs.  In  like  man- 
ner, the  tie  shall  be  supported  and  loaded  as  shown  in  Figure  I  to  produce  the  rail 
seat  positive  moment  from  Art.  10.4.1,  Table  1.  An  illuminated  5-power  magnifying 
glass  may  be  used  to  locate  cracks.  If  structural  cracking  does  not  occur,  the  require- 
ments of  each  portion  of  tliis  test  will  have  been  met. 

10.9.1.5  RaU  Seat  Repeated-Load  Test 

Following  the  vertical  load  test  on  rail  seat  B,  the  load  shall  be  increased  at 
a  rate  of  5  kips  per  minute  until  the  tie  is  cracked  from  its  bottom  surface  up  to 
the  level  of  the  lower  layer  of  reinforcement. 

After  removal  of  the  static  rail  seat  load  necessary  to  produce  cracking,  and 
substitution  of  /l-inch  pads  for  those  shown  in  Figure  I,  the  tie  shall  be  subjected 
to  3  milhon  cycles  of  repeated  loading  with  each  cycle  varying  uniformly  from  4  kips 
to  the  value  of  I.IP.  The  repeated  loading  shall  not  exceed  600  cycles  per  minute. 
If,  after  the  application  of  3  million  cycles,  tlie  tie  can  support  the  rail  seat  load 
(I.IP),  the  requirements  of  this  test  will  have  been  met. 

10.9.1.6  Negative  Bending  Moment  Test 

With  the  tie  supported  and  loaded  as  shown  in  Figure  II,  a  load  increasing  at 
a  rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  the  load  required 
to  produce  the  specified  negative  center  design  moment  from  Table  I  is  obtained. 

Bui.   655 


214       Bulletin  655 — American  Railway  Engineering  Association 

The  load  shall  be  held  for  not  less  than  3  minutes,  during  which  time  an  inspection 
shall  be  made  to  determine  if  structural  cracking  occurs.  An  illuminated,  5-power 
magnifying  glass  may  be  used  to  locate  cracks.  If  structural  cracking  does  not  occur 
the  requirements  of  this  test  will  have  been  met. 

10.9.1.7  Positive  Bending  Moment  Test 

With  tlie  tie  supported  and  loaded  as  shown  in  Figure  III,  a  load  increasing 
at  a  rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  the  load  required 
to  produce  the  specified  positive  center  design  moment  from  Table  I  is  obtained. 
The  load  shall  be  held  for  not  less  than  3  minutes  during  which  time  an  inspection 
shall  be  made  to  determine  if  structural  cracking  occurs.  An  illuminated,  5-power 
magnifying  glass  may  be  used  to  locate  cracks.  If  structural  cracking  does  not  occur, 
the  requirements  of  this  test  will  have  been  met. 

10.9.1.8  Bond  Development,  Tendon  Anchorage,  and  Ultimate  Load  Test 

(a)  Pretensioned   concrete   ties   shall   be  tested  for   bond   development,   and 
ultimate  strength  as  specified  below: 

( 1 )  With  the  tie  supported  and  loaded  at  rail  seat  A  as  shown  in 
Figure  I,  a  load  increasing  at  a  rate  not  greater  than  5  kips  per 
minute  shall  be  applied  as  follows: 

(i)  If  initial  cracking  occurs  at  or  above  I.IP,  a  total  load  of  1.5P 
shall  be  applied   (the  load  P  shall  be  as  determined  in  "Rail 
Seat  Vertical  Load  Test"  for  positive  moment), 
(ii)  If  initial   cracking   occurs   below    I.IP,   a   total  load   of   1.75P 
shall  be  applied. 
If  there  is  no  more  than  0.001-inch  strand  slippage  determined  by  an 
extensometer  reading  to   1/10,000  suitably  attached  to  the  end  of  the 
tie,  the  requirements  of  this  test  will  have  been  met.  The  load  shall  then 
be  increased  until   ultimate  failure  occurs  and  the  maximum  load  ob- 
tained shall  be  recorded. 

(b)  Post-tensioned  concrete  ties  shall  be  tested  for  tendon  anchorage,  and 
ultimate  strength   as   specified  below: 

With  the  tie  supported  and  loaded  as  shown  in  Figure  I,  a  load 
increasing  at  a  rate  not  greater  than  5  kips  per  minute  shall  be  applied 
until  a  total  load  equal  to  that  specified  in  Art.  10.9.1.8  (a),  (i),  or  (ii)  is 
obtained.  If  the  tie  can  support  this  load  for  a  period  of  not  less  than 
5  minutes,  the  requirements  of  this  test  will  have  been  met.  The  load 
shall  then  be  increased  imtil  ultimate  failure  of  the  tie  occurs,  and  the 
maximum  load  obtained  shall  be  recorded. 

10.9.1.9  Fastening  Insert  Tests 

(a)  Threaded-Type  Inserts 

To  determine  the  ability  of  threaded  inserts  to  resist  the  bolt  tension  and  ability 
of  the  concrete  rail  seat  to  carry  any  differential  vertical  load  between  the  rail  and 
tlie  concrete  tie,  the  following  test  shall  be  performed  on  each  insert  as  shown  on 
Figure  IV.  An  axial  load  of  12  kips  shall  be  applied  to  each  insert  separately  and 
held  for  not  less  than  3  minutes,  during  which  time  an  inspection  shall  be  made  to 
determine  if  there  is  any  slippage  of  the  insert  or  any  severe  cracking  of  the  concrete. 
If  such  failures  occur,  then  the  requirements  of  this  test  will  not  have  been  met. 
Inability  of  the  insert  itself  to  resist  the  12-kip  load  shall  also  constitute  failure  of 
this  test. 


Manual   Recommendations 215 

Following  successful  completion  of  the  insert  pullout  test,  the  following  test 
shall  be  performed  on  each  rail  fastening  insert  to  determine  its  ability  to  resist 
turning.  A  high-strength  shoulder  bolt  of  the  proper  diameter  for  the  insert  being 
tested  and  having  a  threaded  length  of  1%  inches  shall  be  threaded  into  the  insert 
and  torqued  to  150  percent  of  the  torque  recommended  by  the  fastener  manufacturer 
for  normal  installation.  The  load  shall  be  held  for  not  less  than  3  minutes.  Ability 
of  the  insert  to  resist  this  torque  shall  constitute  passage  of  this  test. 

(b)   Other  Fastening  Inserts 

Other  fastening  inserts  shall  be  subject  to  the  pull-out  tests  and  torque  test  (if 
applicable)  in  accordance  with  the  manufacturer's  recommendations  and  as  approved 
by  the  engineer. 

10.9.1.10  Fastening  Uplift  Test 

An  18-  to  20-inch  piece  of  the  proper  section  of  rail  shall  be  secured  to  one 
rail  seat  using  a  complete  rail  fastening  assembly,  including  pads,  bolts,  clips  and 
associated  hardware,  as  recommended  by  the  manufacturer  of  the  rail  fastening 
system.  In  accordance  with  the  loading  diagram  in  Figure  V,  an  incremental  load 
shall  be  applied  to  the  rail.  The  load  P  (measured  load  plus  unsupported  tie  weight 
plus  frame  weight)  at  which  separation  of  tlie  rail  from  pad  or  pad  from  rail  seat 
(whichever  occurs  first)  shall  be  recorded.  The  load  shall  then  be  completely  released. 
A  load  of  2P  shall  then  be  applied.  The  inserts  shall  not  pull  out  or  loosen  in  the 
concrete  and  no  component  of  fastening  system  shall  fracture  nor  shall  the  rail  be 
released. 

10.9.1.11  Fastening  Repeated-Load  Test 

(a)  An  18-  to  20-inch  section  of  new  rail  from  which  loose  mill  scale  has 
been  removed  by  wiping  with  a  cloth  shall  be  secured  to  the  rail  seat  in  the  tie 
block  using  a  complete  rail  fastening  assembly.  In  accordance  with  the  loading 
diagram  in  Figure  V  determine  the  load  P  that  will  just  cause  separation  of  the  rail 
from  the  rail  seat  pad  or  the  pad  from  the  rail  seat  whichever  occurs  first.  This 
load  may  be  determined  during  the  Fastening  Uplift  Test  described  in  Article 
10.9.1.10  in  which  case  a  new  set  of  fastening  clips  shall  be  used  for  the  repeated 
load  test. 

(b)  An  18-  to  20-inch  section  of  new  rail  from  which  loose  mill  scale  has  been 
removed  by  wiping  with  a  cloth  shall  be  secured  to  the  rail  seat  in  the  tie  block 
using  a  complete  rail  fastening  assembly.  In  accordance  with  the  loading  diagram 
in  Figure  VI,  alternating  downward  and  upward  loads  shall  be  applied  at  an  angle 
of  20°  to  the  vertical  axis  of  the  rail  at  a  rate  not  to  exceed  300  cycles  per  minute 
for  3  million  cycles.  The  rail  shall  be  free  to  rotate  under  the  applied  loads.  One  cycle 
shall  consist  of  both  a  downward  and  an  upward  load.  The  magnitude  of  the  upward 
load  shall  be  0.6P  where  P  is  the  load  determined  in  part  (a)  of  this  article.  If 
springs  are  used  to  generate  the  upward  load  tlie  downward  load  shall  be  30  kips 
plus  0.6P.  If  a  double-acting  hydraulic  ram  is  used  to  generate  both  the  upward  and 
the  downward  load,  the  downward  load  shall  be  30  kips. 

This  repeated  load  test  may  generate  heat  in  elastomeric  rail  seat  pads.  Heat 
build-up  in  such  pads  must  not  be  allowed  to  exceed  140  F.  Heat  build-up  can  be 
controlled  by  reducing  the  rate  of  load  application  or  by  providing  periods  of  rest 
to  allow  cooling  of  the  pad  to  take  place. 

Rupture  failure  of  any  component  of  the  fastening  system  shall  constitute 
failure  of  this  test. 


216       Bulletin  655 — American  Railway  Engineering  Association 

For  this  test,  retorqueing  of  threaded  elements  subsequent  to  the  completion 
of  500,000  cycles  of  load  shall  not  be  permitted  without  the  written  approval  of 
the  engineer. 

10.9.1.12  Fastening  Longitudinal  Restraint  Test 

Following  the  performance  of  the  Fastening  Repeated  Load  Test,  above,  and 
without  disturbing  the  rail  fastening  assembly  in  any  manner  other  than  retorqueing 
anchor  bolts,  the  tie  and  fastening  shall  be  subjected  to  a  longitudinal  restraint  test. 
A  longitudinal  load  shall  be  applied  as  shown  in  Figure  X  in  increments  of  500  lb 
with  readings  taken  of  longitudinal  rail  displacement  after  each  increment.  Readings 
of  rail  displacement  shall  be  the  average  of  the  readings  of  two  dial  indi- 
cators reading  to  1/ 1000th  of  an  inch,  one  placed  on  each  side  of  tlie  rail  with 
tlieir  plungers  parallel  to  the  longitudinal  axis  of  the  rail.  The  load  shall  be  applied 
in  a  direction  coinciding  with  the  longitudinal  axis  of  the  rail.  The  load  shall  be 
increased  incrementally  until  a  load  of  the  value  specified  in  Art.  10.6.1  for  the  an- 
ticipated tie  spacing  is  reached.  This  load  shall  be  held  for  not  less  than  15  minutes. 
The  rail  shall  not  move  more  than  0.25  inch  during  the  initial  3-minute  period,  and 
there  shall  be  no  further  movement  of  the  rail  after  the  initial  3  minutes.  The 
fastening  shall  be  capable  of  meeting  the  requirements  of  this  test  in  either  direction. 
If  these  criteria  are  met,  the  tie  and  fastenings  will  have  successfully  passed  this  test. 

10.9.1.13  Lateral  Load  Restraint  Test 

With  a  suitable  length  of  new  rail  of  the  size  to  be  used  in  the  track  aflBxed 
to  the  tie  block  in  a  manner  appropriate  to  the  fastening  being  used,  the  entire 
assembly  is  supported  and  loaded  as  shown  in  Figure  XI.  The  loading  head  is  to  be 
fixed  against  translation  and  rotation.  The  wood  block  shall  be  10-in  x  10-in  x  ?i-in 
thick,  5  ply,  exterior  grade  plywood. 

(a)  A  preload  of  20  kips  is  to  be  appUed  to  the  rail  to  seat  the  rail  in  the 
fastening.  Upon  release  of  the  preload,  a  zero  reading  is  to  be  taken  on  the  dial 
indicators  which  measure  rail  translation.  Load  is  to  be  applied  at  a  rate  not  to 
exceed  5  kips  per  minute  until  either  41  kips  has  been  applied  or  the  rail  base  has 
translated  Va  inch,  whichever  occurs  first.  Inability  of  the  fastening  to  carry  the 
41  kip  load  with  /8  inch  or  less  of  rail  translation  shall  constitute  failure  of  this  test. 
Complete  failure  of  any  component  of  the  tie  or  fastening  is  cause  for  rejection. 

(b)  With  all  load  removed  from  the  rail,  a  roller  nest  is  placed  between  the 
fixed  loading  head  and  the  wood  block  on  the  rail  head.  The  roller  nest  shall  not 
offer  resistance  to  lateral  movement  of  the  rail  head.  After  taking  zero  readings  on 
the  dial  indicators,  which  measure  gage  widening  and  rail  translation,  a  load  of 
20.5  kips  is  to  be  applied  at  a  rate  not  to  exceed  5  kips  per  minute.  Rail  rotation, 
gage  widening  less  rail  translation,  greater  than  Vi  inch  shall  constitute  failure  of 
this  test. 

10.9.1.14  Electrical  Impedance  Test 

(a)  Two  short  pieces  of  rail  are  affixed  to  the  tie,  selected  from  Ties  "3"  and 
"4",  using  tie  pads,  insulators  and  fastenings  in  a  manner  appropriate  to  the  fastening 
system  to  be  used. 

(b)  The  complete  assembly  shall  be  immersed  in  water  for  a  minimum  of  6 
hours. 


Manual  Recommendations 217 

(c)  Within  1  hour  after  removal  from  water  an  a-c  10-volt  60-Hertz  potential 
is  applied  across  the  two  rails  for  a  period  of  15  minutes.  If  the  rails  are  rusty  or 
contain  mill  scale,  the  contact  points  must  be  cleaned. 

(d)  The  current  flow  in  amperes  is  read  using  an  a-c  ammeter  and  the  im- 
pedance determined  by  dividing  the  voltage   (10)   by  the  current  flow  in  amperes. 

(e)  If  the  ohmic  impedance  determined  in  (c)  above  exceeds  20,000'  ohms, 
the  tie  will  have  passed  the  test. 

10.9.1.15  Electrical  Short  Test 

The  two  inserts  of  each  rail  seat  shall  be  connected  together  electrically  and 
the  tie  checked  for  an  electrical  short  between  the  two  rail  seats.  The  check  shall  be 
made  by  connecting  one  side  of  a  commercial  110  volt  a-c  potential  to  one  rail  seat 
and  the  other  side  through  a  75-watt  light  bulb  to  the  opposite  rail  seat.  Lighting 
of  the  bulb  indicates  direct  short  circuit. 

10.9.2  PRODUCTION   QUALITY  CONTROL  OF   MONOBLOCK  TIES 

After  the  tie  and  rail  fastening  system  have  passed  the  tests  in  Art.  10.9.1  and 
have  been  approved  by  the  engineer,  further  production  of  these  items  may  proceed 
without  further  design  testing.  During  production  of  such  an  approved  design, 
quality-control  tests   must  be  performed  to  assure  a  unifonn,  high-quality  product. 

10.9.2.1  Daily  Production  Quality-Control  Tests 

The  following  production  quaHty-control  tests  shall  be  performed  prior  to  de- 
livery and  witliin  30  days  of  manufacture  on  one  tie  selected  at  random  from  every 
200  ties  or  fraction  thereof  produced  each  day: 

(a)  The  distance  from  center  of  track  to  center  of  rail  seats  shall  be  verified 
and,  by  use  of  a  template,  the  rail  seat  configuration  and  insert  location 
shall  be  verified  for  compliance  with  the  requirements  of  Art.   10.3.2. 

(b)  The   Rail   Seat  Vertical  Load   Test,   Art.    10.9.1.4,   shall  be  performed. 

(c)  The  Fastening  Insert  Test,  Art.  10.9.1.9,  shall  be  performed  on  one  insert 
per  tie. 

(d)  The  Electrical  Short  Test,  Art.  10.9.1.1.5,  if  applicable,  shall  be  performed. 

10.9.2.2  Additional  Quality-Control  Tests 

To  assure  the  production  of  cross  ties  and  rail  fastenings  which  comply  with 
these  specifications,  the  manufacturer  shall  institute  whatever  additional  quality- 
control  tests,  including  concrete  compressive  strength  tests  (see  Art.  10.2.2),  he  may 
deem  necessary, 

10.9.2.3  Failure  to  Pass  Production  Quality-Control  Test 

Should  any  test  tie  fail  the  tests  required  by  Art.  10.9.2.1,  two  additional  ties 
from  that  same  200-tie  lot  shall  be  tested.  In  the  event  either  of  these  ties  fails,  100 
percent  of  the  remainder  of  the  200-tie  lot  shall  be  either  tested  or  rejected. 

10.9.2.4  Disposition  of  Test  Ties 

Ties  that  pass  the  testing  requirements  and  are  not  cracked  or  otherwise  dam- 
aged after  testing  will  be  considered  acceptable  for  use  in  track. 


218       Bulletin  655 — American  Railway  Engineering  Association 

10.9.2.5  Bond  Development  or  Tendon  Anchorage  Quality-Control  Test 

One  tie  selected  at  random  from  every  2,000  ties  produced  shall  be  subjected 
to  tlie  Bond  Development  or  Tendonage  Anchorage  Test  described  in  Art.  10.9.1.8. 
If  the  tie  does  not  meet  the  requirements  of  10.9.1.8,  three  additional  ties  shall  be 
tested,  and  if  any  of  the  three  ties  do  not  meet  the  requirements  of  10.9.1.8,  the 
entire  lot  may  be  rejected  at  the  option  of  the  engineer 

10.9.2.6  Location  for  Inspection  and  Quality-Control  Testing 

Quality-control  testing  of  production  ties  may  be  performed  at  any  test  facility, 
including  such  facilities  at  the  manufacturer's  plant,  provided  they  meet  the  approval 
of  the  engineer.  Testing  may  be  observed  by  the  engineer  or  his  designated  repre- 
sentative if  he  so  elects.  Two  copies  of  the  results  of  all  such  tests  shall  be  sub- 
mitted to  the  engineer  within  7  days  of  the  performance  of  the  tests. 

10.10  TESTING  OF  TWO-BLOCK  TIES 

10.10.1  DESIGN  TESTS  OF  TWO-BLOCK  TIES 

Prior  to  approval  of  two-block  tie  designs,  concrete  ties  of  the  design  under 
study  shall  be  subjected  to  testing  for  compliance  with  these  specifications.  The 
tests  specified  herein  shall  be  performed  at  testing  facilities  approved  by  the  engi- 
neer within  30  days  of  casting. 

From  a  lot  of  not  less  than  ten  ties  produced  in  accordance  with  these  specifi- 
cations four  ties  will  be  selected  at  random  by  the  engineer  for  laboratory  testing. 
For  design  testing  of  fasteners  the  manufacturer  shall  also  furnish  a  section  of  the 
tie  or  a  concrete  block  with  rail  seat  and  rail  fastening  system  identical  to  the 
concrete  ties  furnished  for  testing. 

The  tie  block  and  each  of  the  four  ties  submitted  for  testing  shall  be  carefully 
measured  and  examined  to  determine  their  compliance  with  the  requirements  of 
Sections  10.2  and  10.3.  Upon  satisfactory  completion  of  this  examination,  the  tie  block 
and  the  two  ties,  which  shall  be  known  and  identified  as  Ties  "1"  and  "2",  shall 
be  submitted  to  performance  tests.  The  remaining  two  ties,  which  will  be  known 
and  identified  as  Ties  "3"  and  "4",  will  be  retained  for  further  use  and  as  a  control 
for  dimensional  tolerances  and  surface  appearances  of  ties  subsequently  manufactured. 

10.10.1.1  Sequence  of  Tests  (Tie  "1") 

The  sequence  of  design  tests  performed  with  Tie  "1"  shall  be  as  follows: 

(a)  Rail  Seat  Positive  Moment  Test   (described  in  Art.   10.10.1.4)   shall  be 
performed  on  each  rail  seat. 

(b)  Rail  Seat  Negative  Moment  Test  (described  in  Art.  10.10.1.5)  shall  be 
performed  on  each  rail  seat. 

(c)  Center   Negative   Bending   Moment  Test    (described  in  Art.    10.10.1.6). 

(d)  Center   Positive    Bending    Moment  Test    (described   in   Art.    10.10.1.7). 

(e)  Rail   Seat   Repeated   Load  Test    (described  in  Art.   10.10.1.8). 

(f)  Rail  Seat  Ultimate  Load  Test  (described  in  Art.  10.10.1.9). 

10.10.1.2  Sequence  of  Tests  (Tie  "2") 

The  sequence  of  design  tests  performed  with  Tie  "2"  shall  be  as  follows: 
(a)   Fastening  Insert  Tests  (described  in  Art.  10.10.1.10)  shall  be  performed 
on  all  inserts. 


Manual  Recommendations  219 


(b)  Fastening  Uplift  Test  (described  in  Art.  10.10.1.11)  shall  be  performed 
on  one  rail  seat. 

(c)  Electrical  Resistance  and  Impedance  Test  (described  in  Art.  10.10.1.15). 

10.10.1.3  Sequence  of  Tests  (Tie  Block) 

The  sequence  of  design  tests  performed  with  the  tie  block  shall  be  as  follows: 

(a)  Fastening  Repeated  Load  Test  (described  in  Art.  10.10.1.12). 

(b)  Fastening   Longitudinal   Restraint  Test    (described  in  Art.    10.10.1.13). 

(c)  Fastening  Lateral  Restraint  Test  (described  in  Art.  10.10.1.14). 

10.10.1.4  Rail   Seat  Positive  Bending  Moment  Test 

With  tie  supported  and  loaded  as  shown  in  Figure  I,  a  load  increasing  at  a 
rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  the  load  (P)  required 
to  produce  the  specified  rail  seat  design  positive  moment  from  Art.  10.5.2,  Design 
Flexural  Requirements  for  Two-Block  Ties,  Table  II,  is  obtained.  This  load  shall 
be  held  for  not  less  than  3  minutes,  during  which  time  an  inspection  shall  be  made 
to  determine  if  structural  cracking  occurs.  An  illuminated  5-power  magnifying  glass 
may  be  used  to  locate  cracks.  If  structural  cracking  does  not  occur  or  (in  the  case 
of  reinforced  or  partially  prestressed  ties)  crack  widths  do  not  exceed  the  widths 
specified  in  Art.  10.5.1.3  (c),  the  requir-ements  of  tliis  test  will  have  been  met. 

10.10.1.5  Rail  Seat  Negative  Bending  Moment  Test 

With  tie  supported  and  loaded  as  shown  in  Figure  VII,  a  load  increasing  at  a 
rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  the  load  (P)  required 
to  produce  the  specified  rail  seat  design  negative  moment  from  Table  II  is  obtained. 
This  load  shall  be  held  for  not  less  than  3  minutes,  during  which  time  an  inspection 
shall  be  made  to  determine  if  structural  cracking  occurs.  If  structural  cracking  does 
not  occur,  or  (in  the  case  of  reinforced  or  partially  prestressed  ties)  crack  widths 
do  not  exceed  the  widths  specified  in  Art.  10.5.1.3  (c),  the  requirements  of  this  test 
will  have  been  met. 

10.10.1.6  Center  Negative  Bending  Moment  Test 

With  the  tie  supported  and  loaded  as  shown  in  Figure  VIII,  a  load  increasing 
at  a  rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  a  load  of  7  kips 
causing  a  moment  of  35,000  inch-pounds  has  been  reached.  If  structural  cracking 
does  not  occur  on  the  gage  faces  of  the  blocks  and  the  deflection  at  the  center  of 
the  ties  does  not  exceed  0.5  inch,  the  requirements  of  this  test  will  have  been  met. 

10.10.1.7  Center  Positive  Bending  Moment  Test 

With  the  tie  supported  and  loaded  as  shown  in  Figure  IX,  a  load  increasing 
at  a  rate  not  greater  than  5  kips  per  minute  shall  be  applied  until  a  load  of  7  kips 
causing  a  moment  of  35,000  inch-pounds  has  been  reached.  If  structural  cracking 
does  not  occur  on  the  gage  faces  of  the  blocks  and  the  deflection  at  tire  center  of 
the  ties  does  not  exceed  0.5  inch,  the  requirements  of  this  test  will  have  been  met. 

10.10.1.8  Rail  Seat  Repeated-Load  Test 

With  the  tie  supported  and  loaded  as  shown  in  Figure  I,  one  rail  seat  of  the 
ties  shall  be  subjected  to  3  million  cycles  of  repeated  loading  with  each  cycle  vary- 
ing uniformly  from  4  kips  to  the  value  (I.IP)  required  to  produce  the  specified 
rail  seat  positive  bending  moment  from  Table  II. 


220       Bulletin  655 — American  Railway  Engineering  Association 

The  repeated  loading  shall  not  exceed  600  cycles  per  minute.  If,  after  tlie 
application  of  3  million  cycles,  the  tie  can  support  the  load  (I.IP),  the  requirements 
of  this  test  will  have  been  met. 

10.10.1.9  Rail  Seat  Overload  and  Ultimate  Load  Test 

With  the  tie  supported  and  the  other  rail  seat  loaded  as  shown  in  Figure  I, 
a  load  increasing  at  a  rate  not  greater  than  5  kijis  per  minute  shall  be  applied  until 
a  total  load  of  1.75P  is  obtained.  If  the  tie  can  support  this  load  for  a  period  of 
not  less  than  5  minutes,  the  requirements  of  this  test  will  have  been  met.  The  load 
shall  then  be  increased  until  ultimate  failure  of  the  tie  occurs,  and  the  maximum 
load  obtained  shall  be  recorded. 

10.10.1.10  Fastening  Insert  Tests 

(a)  Threaded-Type  Inserts 

The  test  procedure  specified  in  Art.  10.9.1.9  (a)  shall  be  used  to  determine 
the  acceptability  of  threaded-type  inserts. 

(b)  Other  Fastening  Inserts 

Other  fastening  inserts  shall  be  subject  to  the  pull-out  tests  and  torque  tests 
(if  applicable)  in  accordance  with  the  manufacturer's  recommendations  and  as 
approved  by  the  engineer. 

10.10.1.11  Fastening  Uplift  Test 

An  18-  to  20-inch  piece  of  rail  of  the  proper  section  shall  be  secured  to  one 
rail  seat  using  a  complete  rail  fastening  assembly,  including  pads,  bolts,  clips,  and 
associated  hardware,  as  recommended  by  the  manufacturer  of  the  rail  fastening 
system.  In  accordance  with  the  loading  diagram  in  Figure  V,  an  18-kip  load  shall 
be  applied  and  held  for  not  less  than  3  minutes.  The  inserts  shall  not  pull  out  or 
loosen  in  the  concrete  and  no  component  of  the  rail  fastening  system  shall  suffer 
any  permanent  deformation. 

10.10.1.12  Fastening  Repeated-Load  Test 

The  Fastening  Repeated-Load  Test  shall  be  performed  following  the  test  pro- 
cedure specified  in  Art.   10.9.1.11. 

10.10.1.13  Fastening  Longitudinal  Restraint  Test 

Following  the  performance  of  the  Fastening  Repeated-Load  Test,  Art.  10.10.1.12, 
and  without  disturbing  the  rail  fastening  assembly  in  any  manner  other  than  re- 
torqueing  anchor  bolts,  the  Fastening  Longitudinal  Restraint  Test  shall  be  performed 
following  the  test  procedure  specified  in  Art.  10.9.1.12. 

10.10.1.14  Fastening  Lateral  Restraint  Test 

The  tie  and  fastening  shall  be  tested  for  lateral  restraint  following  the  test 
procedure  specified  in  Art.  10.9.1.13. 

10.10.1.15  Electrical  Impedance  Test 

The  tie  and  fastening  shall  be  tested  for  electrical  conductivity  following  the 
test  procedure  specified  in  Art.   10.9.1.14. 

10.10.2  PRODUCTION   QUALITY  CONTROL  OF  TWO-BLOCK  TIES 

After  a  tie  and  rail  fastening  system  have  passed  tlie  tests  in  Art.  10.10.1  and 
have  been  approved  by  the  engineer,  further  production  of  these  items  may  proceed 


Manual   Recommendations 221 

without   further    design    testing.    During   production    of    such    an    approved    design, 
quality-control  tests  must  be  performed  to  assure  a  uniform  high-quality  product. 

10.10.2.1  Daily  Production  Quality-Control  Tests 

The  following  production  quality-control  tests  shall  be  performed  prior  to  de- 
livery and  within  30  days  of  manufacture  on  one  tie  selected  at  random  from  every 
200  ties  or  fraction  thereof  produced  each  day. 

(a)  The  distance  from  center  of  the  tie  to  the  center  of  the  rail  seats  shall 

be  verified  and  by  use  of  a  template,  the  rail  seat  configuration  (includ- 
ing shoulders  and  inserts  if  they  are  used)  shall  be  verified  for  com- 
pliance with  the  requirements  of  Art.  10.3.2. 

(b)  The  Rail  Seat  Positive  Moment  Test,  Art.  10.10.1.4,  shall  be  performed. 

(c)  The  Fastener  Insert  Test,  Art.  10.9.1.9,  shall  be  performed. 

(d)  The  Electrical  Impedance  Tests,  Art.   10.9.1.14,  if  applicable,  shall  be 
performed. 

10.10.2.2  Additional  Quality-Control  Tests 

To  assure  the  production  of  cross  ties  and  rail  fastenings  which  comply  with 
these  specifications,  the  manufacturer  shall  institute  whatever  additional  quality- 
control  test,  including  concrete  compressive  strength  tests  (see  Art.  10.2.2.1),  he 
may  deem  necessary. 

10.10.2.3  Failure  to  Pass  Production  Quality-Control  Test 

Should  any  test  tie  fail  the  tests  required  by  Art.  10.10.2.1  above,  two  additional 
ties  from  that  same  200-tie  lot  shall  be  tested.  In  the  event  either  of  these  ties  fails, 
100  percent  of  the  remainder  of  the  200-tie  lot  shall  be  either  tested  or  rejected. 

10.10.2.4  Disposition  of  Test  Ties 

Ties  that  pass  the  testing  requirements  and  are  not  cracked  or  otherwise 
damaged  after   testing  will  be   considered   acceptable  for  use  in  track. 

10.10.2.5  Rail  Seat  Overload  Quality-Control  Test 

One  tie  selected  at  random  from  every  2,000  ties  produced  shall  be  subjected 
to  the  Rail  Seat  Overload  Load  Test  described  in  Art.  10.10.1.9.  If  the  tie  does  not 
meet  the  requirements  of  Art.  10.10.1.9,  three  additional  ties  shall  be  selected  at 
random  and  tested.  If  any  of  the  three  additional  ties  do  not  meet  the  requirements 
of  Art.  10.10.1.9,  the  entire  lot  may  be  rejected  at  the  option  of  the  engineer. 

10.10.2.6  Location  for  Inspection   and  Quality-Control  Testing 

Quality-control  testing  and  inspection  of  production  ties  may  be  performed 
at  any  test  facility,  including  such  facilities  at  the  manufacturer's  plant,  provided 
they  meet  the  approval  of  the  engineer.  The  engineer  shall  be  notified  in  advance 
of  dates  scheduled  for  quality-control  tests.  Testing  may  be  observed  by  the  engineer 
or  his  designated  representative  if  he  so  elects.  Two  copies  of  all  such  tests  shall 
be  submitted  to  the  engineer  within  7  days  of  the  performance  of  the  tests. 

10.11  RECOMMENDED  PRACTICES  FOR  SHIPPING,  HANDLING, 
APPLICATION  AND  USE 

10.11.1  SHIPPING 

Concrete  ties  should  be  shipped  in  open-top  cars.  Ties  must  be  securely  braced 


222       Bulletin  655 — American  Railway  Engineering  Association 

for  transportation  to  prevent  any  movement  that  will  cause  damage.  Ties  shall  be 
shipped  in  a  horizontal  position  and  braced  with  wooden  spacer  blocks  in  such  a 
manner  that  the  top  surface  or  cast-in-place  hardware  does  not  contact  ties  loaded 
above.  Ties  shall  not  be  loaded  higher  than  the  top  of  the  cars  nor  more  than  six 
layers  deep.  The  purchaser  shall  specify  the  size  of  shipments  in  accordance  with 
unloading  facilities. 

10.11.1.1  Protection  of  Threaded  Inserts 

If  cast-in-place  threaded  inserts  are  included  in  ties,  they  shall  be  protected 
against  entry  of  water  and  foreign  matter  by  means  of  a  plastic  cap,  plug  or  other 
suitable  device  approved  by  the  engineer.  Caps  or  plugs  shall  be  placed  in  position 
at  the  time  of  manufacture,  left  in  place  during  shipping  and  not  removed  until 
fastenings  are  aflBxed  to  the  ties. 

10.11.2  HANDLING 

Unnecessary  handling,  redistribution  and  reloading  of  concrete  ties  should  be 
avoided.  To  the  extent  practical,  ties  should  be  distributed  in  proper  position  for 
use  without  further  handling.  They  shall  be  unloaded  from  cars  in  a  manner  that 
will  not  damage  the  ties.  In  no  case  shall  ties  be  dropped  from  a  truck  or  car  to 
the  roadbed. 

10.11.3  PLACEMENT  AND  INITIAL  ROADBED  SUPPORT 

In  new  construction  care  must  be  taken  to  insure  that  all  concrete  cross  ties 
are  uniformly  supported  on  the  roadbed  and  that  no  center-binding  conditions  de- 
velop prior  to  ballasting  and  tamping.  If  the  subgrade  condition  indicates  that  there 
is  inadequate  or  non-uniform  support  for  the  ties  before  placement  of  ballast,  a 
minimum  layer  of  3  inches  of  ballast  should  be  placed,  leveled  and  compacted  before 
placement  of  ties.  Ties  shall  be  installed  at  right  angles  to  the  center  line  of  track 
at  the  designed  spacing  prior  to  rail  installation. 

10.11.4  PLACEMENT  OF  RAIL  AND  FASTENINGS  IN  NEW  CONSTRUCTION 

10.11.4.1  Tie  Pads 

It  is  reconmmended  that  tie  pads  be  shipped  independendy  of  the  ties.  Rail  seats 
should  be  clean  and  ties  properly  positioned  prior  to  placement  of  pads.  Pads  should 
be  accurately  positioned  and  centered  on  the  rail  seat.  Use  of  adhesive  may  be 
desirable  to  hold  pads  in  place  until  rail  is  unloaded  and  fastened. 

10.11.4.2  Rail 

Rail  must  not  be  dropped  into  place.  Where  continuous  welded  rail  is  to  be 
used,  the  use  of  rollers  is  recommended  to  facilitate  its  unloading  and  reduce  the 
risk  of  dislocating  ties  and  tie  pads. 

10.11.4.3  Joints 

If  jointed  rail  is  to  be  used  (see  Art.  10.1.5.2)  special  fastenings  may  be  re- 
quired within  joint  bar  limits.  Care  must  be  exercised  to  see  that  such  fastenings 
are  clearly  distinguishable  and  ordered  in  the  proper  amount.  Care  should  also  be 
taken  to  see  that  the  actual  juncture  of  two  rails  does  not  occur  directly  over  a  tie. 

10.11.4.4  Fastenings 

It  is  recommended  that  fastenings  be  shipped  independently  of  ties.  Where 
more  than  one  type  of  fastening,  such  as  gage  and  field  fastenings  or  special  joint 


Manual  Recommendations 223 

fastenings,  are  to  be  used  they  shall  be  clearly  marked  to  avoid  confusion  and  avoid 
difficulties  during  their  distribution  and  application.  Fastenings  shall  be  applied  in 
the  manner  appropriate  to  their  design  and  approved  by  their  manufacturer.  If 
threaded  fasteners  are  used,  the  shank  at  tlie  screw  shall  be  dipped  in  petrolatum 
before  assembly. 

10.11.4.5 

In  corrosive  environments,  consideration  should  be  given  to  protecting  the 
external  components   of  fastenings. 

10.11.5  TAMPING 

Tamping  of  concrete  ties  should  be  in  accordance  with  the  provisions  of  Chapter 
5  of  the  Manual. 

10.11.6  TRACK  GEOMETRY 

(a)  It  is  recommended  that  concrete  ties  be  installed  on  curves  only  if  the 
curves  have  AREA-recommended,  or  equal,  spiral  approach  and  departure  transitions. 

(b)  It  is  recommended  that  concrete  ties  not  be  installed  in  curves  designed 
for  an  unbalanced  superelevation  greater  than  3  inches. 

10.12  BALLAST 

10.12.1  GENERAL  CHARACTERISTICS 

Prepared  ballast  for  use  with  concrete  ties  shall  be  of  hard,  strong,  angular, 
durable  particles,  free  from  injurious  amounts  of  deleterious  substances  and  conform- 
ing to  tlie  requirements  of  these  specifications.  The  most  successful  concrete  tie 
installations  to  date  have  used  sound  granite,  trap  rock,  or  similar  types  of  ballast 
and  such  types  of  ballast  are,  therefore  recommended  for  use  in  conjunction  with 
concrete  ties.  Current  and  proposed  research  may  indicate  that  other  ballast  mate- 
rials also  could  be  satisfactory. 

10.12.2  QUALITY  REQUIREMENTS 

(Under  study.) 

10.12.3  GRADING  REQUIREMENTS 

Ballast  grading  requirements  shall  be  in  conformity  witli  Chapter  1  of  the 
Manual. 

10.12.4  HANDLING 

Ballast  shall  be  handled  at  the  producing  plant  in  such  a  manner  that  it  is 
kept  clean  and  free  from  segregation.  It  shall  be  loaded  only  into  cars  which  are 
in  good  order,  tight  enough  to  prevent  leakage  and  waste  of  material,  and  which 
are  clean  and  free  from  rubbish  or  any  substance  which  would  foul  or  damage  the 
ballast.  The  producer  should  not  store  ballast  in  cone-shape  piles  or  make  re- 
peated i:)asses  of  his  equipment  over  the  same  levels  in  stock  pile  area.  Tlie  supplier's 
proposed  method  of  handling  ballast  shall  be  subject  to  the  approval  of  the  engineer. 

10.12.5  INSPECTION 

If  material  loaded  or  being  loaded  does  not  conform  to  these  specifications, 
the  inspector  shall  notify  the  supplier  to  stop  further  loading  until  tlie  fault  has 


224       Bulletin  655 — American  Railway  Engineering  Association 

been  corrected  and  dispose  of  all  of  the  defective  material  without  cost  to  the  rail- 
road. The  engineer  reserves  the  right  to  reject  any  car  of  ballast  arriving  at  the 
site  for  unloading  that  does  not  conform  to  the  specifications. 

10.12.6  TESTING 

Prior  to  installation,  the  supplier  shall  provide  tlie  engineer  with  certified  test 
results  of  ballast  classification,  quality,  and  grading  as  conducted  by  a  testing  labo- 
ratory accepted  by  the  engineer.  If,  during  ballast  installation,  the  supplier  changes 
the  source  of  ballast,  additional  certified  test  results  shall  be  provided.  The  supplier 
shall  receive  concurrence  of  the  engineer  as  to  the  use  of  testing  laboratory  to  make 
the  aforementioned  tests. 

Samples  of  the  finished  product  for  gradation  and  other  required  tests  shall 
be  taken  from  each  4,000  tons  of  prepared  ballast,  unless  otherwise  ordered  by  the 
engineer.  The  sample  shall  be  representative  and  shall  weigh  not  less  than  150  lb. 

The  supplier  shall  certify  that  ballast  delivered  to  the  railroad  is  typical  of 
tliat  upon  which  specified  tests  have  been  made. 

10.13  COMMENTARY 

10.13.1  FLEXURAL  STRENGTH  OF  MONOBLOCK  TIES 

Monoblock  ties  are  stiff  structural  members  that  are  loaded  by  the  rails  from 
the  top  and  are  supported  on  the  ballast  at  the  bottom.  The  loads  applied  at  the 
top  combined  with  the  support  reactions  at  the  bottom  will  produce  flexure  in  the 
ties.  Maximum  flexure  occurs  at  the  rail  seats  and  at  the  center.  Flexure  is  influenced 
by  a  number  of  factors  discussed  in  Section   10.1   General  Considerations. 

10.13.1.1  Wheel  Loads 

In  order  to  give  satisfactory  service  a  prestressed  monoblock  concrete  tie  should 
be  capable  of  withstanding  without  cracking  the  maximum  loads  likely  to  be  found 
in  service. 

10.13.1.2  Rail  Seat  Load 

The  rail  seat  load  is  that  load  transmitted  by  the  rail  to  the  rail  seat  of  the  tie. 

It  is  the  design  wheel  load  modified  by  the  distribution  and  impact  factors.  For 
various  tie  spacings  the  following  rail  seat  loads  are  used  to  determine  the  flexure 
requirements  in  Art.  10.4.2,  Table  I: 

Spacing,  Inches  Rail  Seat  Load,  Pounds 
30  61,500 

27  57,050 

24  52,600 

21  48,150 

As  rail  seat  loads  are  reduced  so  also  are  the  flexural  requirements  of  ties  and 
the  unit  pressures  on  the  ballast  and  subgrade. 

10.13.1.3  Ballast  Reaction 

The  load  transmitted  to  the  tie  is  resisted  by  the  ballast  at  the  interface  be- 
tween the  bottom  of  the  tie  and  the  ballast.  Immediately  following  tamping  the 
ballast  reaction  is  concentiated  under  the  tamped  portions  of  the  tie  with  little  if 
any  reaction  occurring  under  the  center  portion  of  the  tie.  This  condition  usually 


Manual  Recommendations 225 

produces  positive  flexure  at  the  rail  seats  and  the  tie  center.  Over  a  period  of  time, 
because  of  repeated  loads,  vibration  and  crushing  of  ballast,  the  ballast  will  gradually 
compact,  moving  away  from  the  areas  of  greatest  concentration.  The  tie,  therefore, 
settles  slightly  into  the  ballast,  allowing  the  center  portion  of  the  tie  to  pick  up 
a  portion  of  the  load  thus  reducing  the  amount  of  load  carried  by  die  tie  ends. 

Redistribution  of  ballast  reaction  will  continue  until  eventually  a  condition  of 
uniform  ballast  reaction  over  the  entire  length  of  the  tie  is  approached.  This  support 
condition  produces  positive  flexure  at  the  rail  seats  and  negative  flexure  at  the  center 
of  tie.  It  also  makes  possible  a  simple  analysis  for  flexure  in  the  tie  by  using  the 
formulas : 


(l)M,=-^ 


where 


Mr  =  Moment  at  the  rail  seat 

W  =  Total  vertical  load  in  pounds/inch  of  tie  length. 

Li  =  Distance  from  center  line  of  rail  to  end  of  tie. 

(2)    Mo  = — 5 — ■  — Mr  or  - — -^^ 5- — ^ 


where 


Mc  =  Moment  at  center  of  tie. 
L2  =  Distance  center  to  center  of  rails. 


2(Rail  Seat  Load) 


2Li  +  L2 


W  =  Total  vertical  load  in  pounds/inch  of  tie  length  = 

Mr  =  Moment  at  the  rail  seat 
Li  =  Distance  from  center  line  of  rail  to  end  of  tie. 
To  insure  ties  that  will  not  crack  under  normal  service  conditions  the  bending 
moments  produced  by  this  approach  are  considered  adequate. 

10.13.2  FLEXURAL  STRENGTH  OF  TWO-BLOCK  TIES 

Two-block  ties  consist  of  two  blocks  of  concrete  connected  by  a  third  member. 
Under  load,  flexure  will  occur  in  the  end  blocks,  and  while  flexure  does  occur  in  the 
connecting  element,  its  flexural  resistance  is  relatively  small,  thus  one  block  is  able 
to  deflect  with  respect  to  the  other. 

Consideration  of  distribution  factor,  impact  factor,  wheel  loads,  rail  seat  loads, 
and  tie  spacings  are  the  same  as  for  monobiock  ties. 

10.13.2,1  Ballast  Reaction 

For  two-block  ties  each  tie  block  must  distribute  a  full  rail  seat  load  to  the 
ballast.  Assuming  this  distribution  over  a  period  of  time  will  approach  uniformity, 
the  flexural  requirements  for  a  tie  block  may  be  determined  by  the  formula 

where 

Mr  =  Moment  at  the  rail  seat 

to  ^  Rail  seat  load  in  pounds/inch  of  tie  block  length. 
L  is  assumed  to  be  one-half  the  lengtli  of  the  tie  block. 
The  magnitude  of  the  terms  10  and  L  are  influenced  by  tie  block  length.  This 
influences  the  flexural  requirements. 

Flexural   requirements  for  five  lengths   of  tie  blocks  and  four  tie  spacings  are 


226       Bulletin  655 — American  Railway  Engineering  Association 

shown  in  Table  II.  Flexural  requirements  for  block  lengths  other  than  those  shown 
may  be  calculated,  but  in  no  case  should  the  rail  seat  positive  flexural  capacity  be 
less  than  150  inch-kips. 

10.13.2.2  Tie  Flexibility 

The  connecting  element  of  two-block  ties  should  be  sufficiently  stiff  to  maintain 
track  gage  and  tie  integrity  during  handling,  track  construction  and  track  mainte- 
nance. Under  load,  non-uniform  ballast  support  reactions  may  cause  differential 
deflection  between  the  blocks  of  a  tie.  The  connecting  element  must  therefore  be 
flexible  enough  to  accept  the  maximum  deflections  likely  to  occur  in  track  without 
damage  to  the  element  or  to  the  concrete  blocks. 

Minimiun  stiftness  and  specific  deflection  without  damage  requirements  have 
therefore  been  made  a  part  of  these  specifications. 

10.13.3  LONGITUDINAL  RAIL  RESTRAINT 

Rail  must  be  restrained  to  avoid  excessive  longitudinal  movement.  Longitudinal 
movement  of  rail  can  be  induced  by  temperature  change  and/or  traffic. 

10.13.3.1  Temperature-Induced  Loads 

The  longitudinal  force  due  to  temperature  change  may  be  determined  using 
the  formula 

(F-jrs  ^^ 


2RAE 

Where  F  c=  Total  force  in  poimds  required  to  fully  restrain  rail  against  any  rail 
movement  due  to  temperature  variation  from  the  rail  temperature  at 
laying.  (Use  formula  F  =  As'!>^T,  where  A  :=  area  of  rail  cross  section 
in  square  inches,  s  =  internal  temperature  stress  developed  in  the  rail 
by  the  restraining  forces,  s  =  30,000,000  X  1°  X  0.0000065  =  195  psi. 
AT  =  temperature  change  from  mean  laying  temperature  in  degrees  F) 

/  =  Joint  restraint  ( say  /  =z  0 ) . 

S  =  Average  tie  spacing  in  inches. 

R  =.  Average  tie  resistance  in  pounds  per  tie  per  rail. 

A  =  Area  of  rail  cross  section  in  square  inches. 

Ecz  Modulus  of  elasticity  (30,000,000  psi). 

D  =  Maximum  rail  end  movement  (say  0.375  inch). 

Solving  for  R: 

„_    F'S      __    35,870,087,2365    _,c,r>-,o 
2DAE    "        291,375,000       -^^-^-^^ 

Where   F  =  75°  X  195  X  12.95  =  189,394  lb 

D=0'.375  inch 

A  r=  12.95  sq  inches 

E  =  30,000,000  psi 

S  =  21  inches,  24  inches,  27  inches,  30  inches. 
For  21-inch  tie  spacing:   R  =  2585  lb   (say  2.6  kips) 
For  24-inch  tie  spacing:  Rr=2955  lb   (say  2.9  kips) 
For  27-inch  tie  spacing:   R=3324  lb   (say  3.3  kips) 
For  30-inch  tie  spacing:  R  =  3693  lb  (say  3.7  kips) 


Manual  Recommendations  227 


10.13.3.2  Traffic-Induced  Loads 

Only  the  larger  of  traffic-induced  loads  due  to  traction  or  braking  need  be  con- 
sidered as  tliey  cannot  occur  together  at  a  single  point  on  a  rail.  This  force  is  approxi- 
mately 10  kips. 

10.13.3.3  Tie  Spacing 

Since  only  about  50  percent  of  the  load  on  a  rail  is  carried  by  the  tie  directly 
under  it  with  the  two  adjacent  ties  carrying  the  remainder,  we  can  arrive  at  the 
maximum  force  expected  for  ties  spaced  as  follows: 

21-inch  spacing,  50%  of  10  kips  +  2.6  kips  =  7.6  kips 
24-inch  spacing,  50%  of  10  kips  -f  2.9  kips  =  7.9  kips 
27-inch  spacing,  50%  of  10  kips  -f  3.3  kips  =  8.3  kips 
30-inch  spacing,  50%  of  10  kips  +  3.7  kips  =  8.7  kips 

Since  the  greater  weight  of  train  should  provide  an  increased  friction  between 
rail  and  tie  and  bet\veen  tie  and  ballast,  it  is  felt  traffic-induced  loads  can  be  ig- 
nored insofar  as  longitudinal  restraint  is  concerned. 

The  restraint  provided  between  rail  and  tie,  howe\er,  need  not  exceed  the 
abihty  of  ballast  section  to  restrain  the  moxement  of  ties  longitudinally  in  the  ballast 
section.  It  may  also  be  assumed  that,  in  continuous  welded  rail,  some  of  the  longi- 
tudinal force  due  to  both  braking  and  traction  is  transmitted  ahead  and  behind  and 
absorbed  by  ties  not  under  or  adjacent  to  the  load.  In  studies  made  by  AREA  as 
reported  in  Vol.  56,  1955,  the  maximum  individual  tie  pressure  was  recorded  as 
2930  lb.  This  was  in  gravel  ballast  with  ties  spaced  an  average  of  19.5  inches  (24 
ties  per  rail).  The  study  further  concluded  that,  in  gravel  ballast,  the  holding  power 
of  such  ballast,  not  frozen,  should  not  be  considered  to  exceed  1200  lb  per  anchor. 
Slag,  limestone  and  granite  ballast  should  be  able  to  provide  greater  resistance  to 
tie  mo%ement. 

Concrete  ties  should  at  least  equal  the  restraining  ability  of  timber  ties. 

10.13.4  LATERAL  RAIL  RESTRAINT 

Truck  instability  may  occur  in  the  wheel-rail  interface  due  to  excessive  forces 
interacting  between  tlie  wheel  and  rail  in  the  lateral  direction.  These  lateral  forces 
tend  to  cause  wheel  Hanges  to  climb  the  gage  side  of  tlie  rail  when  there  is  excessive 
lateral  flange  pressure  in  relation  to  actual  vertical  loads.  These  lateral  pressures 
are  caused  by  one  or  more  of  the  following  conditions: 

(a)  Nosing  or  hunting  of  truck  assembhes  at  a  repetitive  frequency. 

(b)  Centrifugal  forces  on  curved  track. 

(c)  Impact  due  to  irregular  wheel  and/or  rail  alinement  or  configuration. 

(d)  Rotational  acceleration  of  the  vehicle  body  due  to  curvature  changes. 

(e)  Wheel  friction  from  curve  negotiation. 

10.13.4.1  Lateral  Forces 

A  rational  determination  of  lateral  force  requirements  on  track  fastenings  would 
be  to  develop  lateral  and  o\erturning  reactions  in  tlie  rail  base  to  the  degree  tliat 
the  wheel  flanges  will  climb  the  rail  before  the  rail  would  overturn.  This  limit  may 
be  determined  by  considering  the  ratio  of  lateral  force  to  vertical  load  necessary 
to  cause  flange  chmbing. 


228       Bulletin  655 — American  Railway  Engineering  Association 

Studies  made"*  show  that  a  ratio  of  vertical  loads  (Pi)  to  lateral  forces  (Pi) 
approaching  unity  will  permit  the  wheel  flanges  to  climb  the  rail.  Therefore,  using 
vertical  wheel  loads  of  35,000  lb  generated  l^y  a  high-horsepower  6-axle  locomotive 
as  design  criteria  for  maximum  vertical  loading  (Pi),  then  we  could  expect  a  maxi- 
mum lateral  pressure  (Pi)  to  also  be  in  the  order  of  35,000  lb.  Consequently,  con- 
sideration of  the  individual  lateral  forces  referred  to  in  Art.  10.13.4  need  not  be 
considered  since  lateral  forces  greater  than  35,000  lb  would  cause  wheels  to  climb. 

10.13.4.2  Lateral  Force  Distribution 

Reference  to  Fig.  10.2.3.1  covering  the  distribution  of  vertical  loads  to  ties 
indicates  that  the  tie  directly  imder  the  load  will  receive  from  45  percent  (20-inch 
centers)  to  60  percent  (30-inch  centers)  of  the  imposed  vertical  load  while  adjacent 
ties  will  each  receive  one-half  of  tlie  balance.  This  distribution  of  loading  is  a  func- 
tion of  the  rigidity  of  the  track  structure,  which  is  greatest  about  the  horizontal 
axis. 

However,  rail  stressed  about  the  vertical  axis  by  pressure  induced  by  a  wheel 
flange,  has  increased  stability  caused  by  torsional  rigidity  of  the  rail  and  the  effect 
of  the  weight  from  wheels  of  adjoining  trucks.  The  calculations  to  compare  the  two 
conditions  of  loading  are  complex,  but  for  our  purposes  the  resistance  to  bending  in 
the  vertical  and  horizontal  axis  are  in  the  same  order  of  magnitude  under  these 
conditions.  Therefore,  lateral  loads  applied  to  the  tie  may  be  expected  to  be  dis- 
tributed in  a  manner  similar  to  vertical  loads. 

Based  on  the  foregoing,  the  tie  fastening  system  accommodates  the  following 
design  stresses   in   combination: 

Horizontal  Reaction: 

Lateral  Force  X   Distribution  Factor   (DF) 
Vertical  Reaction: 

[(  ■^-'^'  ^--  X  ^i,^^)   -   ( J^-^fi^)]   X  OF 

10.13.5  ELECTRICAL  PROPERTIES 

10.13.5.1  Signal  Circuits 

The  engineer  must  give  consideration  to  the  electrical  environment  in  selecting 
concrete  tie  designs  and  specifications.  While  concrete  is  not  a  good  conductor  of 
electricity,  it  does  not  have  sufiicient  resistance  or  impedance,  particularly  when 
steel  reinforcement  is  in  close  proximity  to  rail  fastening  components,  to  insure 
trouble-free  operations  of  signal  appliances  depending  upon  electrical  isolation  of 
the  rail  if  the  rails  are  not  insulated  from  the  concrete.  From  the  viewpoint  of  signal 
operation,  the  value  of  concern  is  the  impedance  per  1,000  ft  of  track  rather  than 
tlie  impedance  per  tie.  The  former  includes  electrical  leakage  through  ballast  as 
well  as  the  ties  which  can  be  expected  to  perform  in  wet  trackage,  and  under  a 
variety  of  voltages,  both  ac  and  dc. 

10.13.5.2  Electric  Traction 

Electric  propulsion  systems  most  often  rely  upon  ground  return  through  track- 
age for  circuit  completion.  Under  these  circumstances,  it  is  desirable  that  the 
impedance  between  rails  and  ground  (ballast  and  subsoil)  not  exceed  certain  maxi- 
mum values. 


<i*  British   Railways,  Japanese   National  Railways  and  the  Association  of  American  Railroads. 


Manual  Recommendations 


229 


<t  LOAD 


Pk 


THE    FOLLOWING   FORMULA 
SHALL   BE    USED  TO 
DETERMINE    THE 
VALUE    OF   P 
P=     2M 


30"  TO    'L    track      ^  , 


POSITIVE     MOMENT  AT   THE 
RAIL   SEAT  AS   REQUIRED  IN 
TABLE   I  FOR  PRESTRESSED 
MONOBLOCK   TIES   OR   TABLE 
ni    FOR  TWO  BLOCK  TIES 


x'/2xWIDTH  OF  TIE  RUBBER 
SUPPORT  (50  DUROMET^R 
A  SCALE) 


2" 

M 


2"x!"xWIDTH  OF  TIE 
RUBBER     SUPPORT 
f50   DUROMETER 
A  SCALE) 
SUPPORT 


FIGURE  I      POSITIVE    RAIL   SEAT    MOMENT    TEST 


^  SUPPORT 


(t_  TRACK  AND  LOAD 


(^  SUPPORT 


30 


3"..3'\ 


Pn 


30 


2" 


lij- 


l"x  '/2"xWIDTH   OF  TIE 

RUBBER  (50  DUR-     |^-l4~ 
OMETER)  SUPPOF^jrin 


2" 


/5*sW 


THE    FOLLOWING    FORMULA 
SHALL    BE    USED  TO   DETERMINE 
THE   VALUE   OF  P 

P=2M 
27 

M  =  NEGATIVE    MOMENT  AT  THE    CENTER 
OF  THE  TIE   AS   REQUIRED  IN  TABLE  I 


2"xl"x WIDTH  OF  TIE  RUBBER 
SUPPORT  (50   DUROMETER 
A   SCALE) 


TIE    CENTER    NEGATIVE   MOMENT   TEST 


FIGURE  n 


230       Bulletin  655 — American  Railway  Engineering  Association 


(^   SUPPORT 


(^  TRACK  AND  LOAD      (£_  SUPPORT 


30 


Pn 


30 

l"xl/2"xWlDTH0FTIE 
.RUBBER    SUPPORT 
50  DUROMETER 
A    SCALE 


THE    FOLLOWING    FORMULA 
SHALL    BE    USED  TO   DETERMINE 
THE    VALUE  OF  P 

P=  2M 
27 

M=  POSITIVE    MOMENT  AT  THE    CENTER 
OF  THE  TIE  AS  REaOiRtD  iM  TaBlE  I 


TIE   CENTER    POSITIVE   MOMENT  TEST 


2"xl"x WIDTH  OF   TIE 
RUBBER   SUPPORT 
50  DUROMETER 
A    SCALE 


FIGURE  m 


(^  LOAD 
'P=I2  KIPS 


HIGH   STRENGTH   ROD 
THREADED    BOTH    ENDS 


-CONCRETE     TIE 


FIGURE  rZ 


SUPPORT  TO  BE  SEATED  IN 
HYDROCAL,  HYDROSTONE  OR 
OTHER  MATERIAL  APPROVED 
BY  THE  ENGINEER 


INSERT  PULLOUT  TEST 


Manual  Recommendations 


231 


LOADING  FRAME 


?.  LOAD  AND  RAIL 


(^  SUPPORT 
10" 


(I   SUPPORT 


SUPPORT 
OPPOSITE 
END  OF  TIE 


ELEVATION 


MIN 


MIN. 


SUPPORT  TO  BE  SEATED 
IN  HYDROCAL, HYDRO- 
STONE  OR  OTHER   MAT- 
ERIAL  APPROVED    BY 
THE    ENGINEER- 


CONCRETE    TIE 


BLOCKING  TO  PROVIDE 
UNIFORM  BEARING 
UNDER  RAIL  BASE 


END  VIEW 


FASTENER     UPLIFT    TEST 


FIGURE  3Z: 


232'       Bulletin  655 — American  Railway  Engineering  Association 


I 


t   OF  RAIL- 


FOR  DETERMINATION 
OF  P  SEE  ARTICLE 
10.9. 1. M  (a) 


-0.6  P  FOR  DOUBLE  ACTING 
HYDRAULIC  RAM 

-30  KIPS  FOR  DOUBLE  ACTING 
HYDRAULIC  RAM 

'30  KIPS  +  0.6P  FOR  SINGLE 
ACTING  HYDRAULIC  RAM  AND 
SPRING  NESTS 


GAGE  SIDE  OF  RAIL 


TIE  BLOCK  SECURELY 
FASTENED  TO  SUPPORT 


SUPPORT- 


FIGURE  m    FASTENING  REPEATED  LOAD  TEST 


Manual   Recommendations 


233 


?.  LOAD 


30"  TO    "t    TRACK 


THE    FOLLOWING    FORMULA 
SHALL   BE   USED  TO 
DETERMINE    THE 
VALUE   OF   P 
P=     2M 


M=  NEGATIVE  MOMENT  AT  THE 
RAIL  SEAT  AS  REQUIRED  IN 
TABLE  I   ORTABueH 

r'x  l/2"xWIDTH  OF  TIE 

RUBBER     SUPPORT 

(50    DUROMETER,A   SCALE) 


2x1  xWIDTH  OF  TIE 
I    RUBBER   SUPPORT 
J    (50  DUROMETER.ASCAUE) 

•L  SUPPORT 


FIGURE  Sn  RAIL    SEAT    NEGATIVE   MOMENT  TEST 


15 


w 


30" 


P  =  7K  MAX 


m 


30 


S 


52 


10" 


10 


TWO    BLOCK  TIE  CENTER    NEGATIVE    BENDING  TEST  FIGURE  3ffll 


234       Bulletin  655 — American  Railway  Engineering  Association 


15 


s 


30" 


P  =  7K  MAX. 


3  0" 


^ 


a 


10 


10" 


TWO    BLOCK  TIE  CENTER   POSITIVE  BENDING  TEST  FIGURE  K 


Manual   Recommendations 


235 


CO 


< 

I- 
liJ 


< 

z 

o 


o 


UJ 

I- 
< 


M 

UJ 
(T. 

CD 


236       Bulletin  655 — American  Railway  Engineering  Association 


P  (41 ,000  LBS) 


DIAL  GAGE    FOR 
READING    GAGE 
WIDENING- 


SUPPORT 


TEST    BED 


DIAL   GAGE 
FOR    READING 
TRANSLATION 


FIGURE    :ZL      FASTENING  LATERAL  RESTRAINT  TEST 


Manual  Recommendations 
Committee   1 — Roadway  and  Ballast 

Report  on   Assignment    1 

Roadbed 

F.  L.  Peckover  (chairman,  subcommittee),  J.  R.  Blacklock,  D.  H.  Cook,  G.  W. 
Deblin,  W.  a.  Eshbaugh,  J.  B.  Haegler,  H.  O.  Ireland,  H.  W.  Legro,  F.  H. 
McGuiGAN,  W.  C.  Murphy,  J.  E.  Newby,  S.  R.  Pettit,  P.  J.  Seidel,  W.  M. 
Snow. 

Your  committee  recommends  for  adoption  and  publication  in  the  Manual  as  an 
addition  to  present  Manual  material  in  Part  1 — Roadljed,  tlie  recommended  practice 
Section  1.4 — Maintenance,  as  published  in  Bulletin  651,  January-February  1975, 
pages  282  to  297,  with  the  following  editorial  changes: 

Page  287,  Fig.   1.4.4— change  to  Fig.   1.4.2. 

Page  288,  Art.  1.4.2.2,  2nd  last  sentence — change  Fig.  1.4.4  to  Fig.  1.4.2. 

Page  291,  Table  1.4.4— change  to  Table  1.4.1. 

Page  290,  Art.  1.4.3.3.3,  last  sentence— change  Table  1.4.4  to  Table  1.4.1. 

Page  297,  References,  item  3 — change  "To  be  presented  .  .  ."  to:  Peckover,  F.  L., 
Treatment  of  Rock  Falls  on  Railway  Lines,  Bui.  653,  June-July  1975,  p.  471-503. 


If  Section  1.4 — Maintenance,  is  approved  for  publication  in  Part  1 — Roadbed, 
of  Chapter  1  of  the  Manual,  the  following  editorial  changes  in  Section  1.1 — Explora- 
tion and  Testing,  and  Section   1.2 — Design,  will  be  necessary: 

Art.  1.1.2.3,  para.  1,  last  line  (p.  1-1-4):  delete  "Section  1.4 — Maintenance," 
substitute  "Article  1.4.3." 

Art.  1.2.1,  ]Dara.  3  (p.  1-1-11):  delete  "(to  be  prepared),"  substitute  "softening 
and  squeezing  of  subgrade,  frost  heaving  of  track,  rock  falls,  failures  of  earth  slopes, 
and  control  of  erosion." 

Art.  1.2.2.1.4,  para.  6,  last  sentence  (p.  1-1-14):  delete  "(see  Section  1.4— 
Maintenance)." 

Art.  1.2.2.1.7,  para.  3,  last  sentence  (p.  1-1-19):  delete  "under  Section  1.4 — 
Maintenance,  on.   .   ."  Substitute  "in  Article  1.4.2  on  maintenance  of  .  .  ." 

Art.  1.2.2.2.6,  2nd  sentence  (p.  1-1-21):  delete  "Section  1.4 — Maintenance," 
substitute  "Articles   1.4.3  and   1.4.5. ' 

Art.  1.2.3.6,  last  para.  (p.  1-1-26):  delete  "Section  1.3 — Construction,"  sub- 
stitute "Article  1.3.5." 

Art.  1.2.3.7,  3rd  para.,  2nd  .sentence  (p.  1-1-26):  delete  "Section  1.4 — Main- 
tenance," substitute  "Article  1.4.5." 

Table  1.2.5  (p.  1-1-32):  increase  print  size  for  table  number  and  title,  for  im- 
proved reference  purposes. 

Art.  1.2.4.3.3,  1st  para.,  2nd  sentence  (p.  1-1-28):  delete  "Culverts,"  substitute 
"Culverts  and  Drainage  Pipe." 

References    (p.   1-1-30),  item   (2):   delete:   "Chicago,"  substitute  "New  York." 

Art.  1.2.5.3,  3rd  para.,  2nd  line)  (p.  1-1-31):  after  "sub-ballast"  add  "(see 
Article  1.4.1.2.)." 

Art.  1.2.5.5,  5th  para.,  last  line  (p.  1-1-35):  delete  "Section  1.4 — Maintenance," 
substitute  "Article  1.4.1.4." 

237 


238      Bulletin    655 — American    Railway    Engineering    Association 

Report  on  Assignment  9 

Vegetation  Control 

H.  C.  Archdeacon  (chairman,  subcommittee),  H.  E.  Bartlett,  R.  H.  Bogle,  Jr., 
E.  B.  Grant,  T.  J.  Hernandez,  P.  R.  Houghton,  D.  N.  Johnston,  H.  E. 
McQueen,  J.  M.  Nunn,  G.  D.  Santolla,  W.  H.  Stumm. 

Your  committee  submits  for  adoption  and  publication  in  Part  9 — Vegetation 
Control,  Chapter  1  of  the  Manual,  the  accompanying  Table  3 — Susceptibility  of 
Woody  Species  to  Herbicide  Treatments. 

TABLE  3  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 

The  followlriR  treatments  are  typical  of  those  frequently  used.   This  list  Is 
not  intended  to  be  exhaustive.   Additional  Information  on  other  chemicals  is  available 
through  federal  and  state  agencies,  university  extension  services  and  suppliers.   The  letter 
code  for  treatments  is  not  intended  to  jlmply  anV  order  of  preference,  but  is  used  solely 
to  conserve  space  on  the  following  table: 

STEM  FOLIAr.E  SPRAYS 

A.  2,  A-DP  plus  2,  4-D.   2  lb.  plus  2  lb.  per  100  gal.  wateri 

B.  Ester  amine  and  oil  soluble  amine  of  2,  A-D  plus  2,  4,  5-T.   2  lb.  olus 

2  lb.  per  100  g^l.  water. 

C.  10  gal.  Ammonium  Sulfamate  solution  plus  1  qt.  surfactant  per  100  gal.  water. 

D.  Plcloram   plus  2,  4-D.     H    lb.  plus  2  lb.  per  100  gal.  water. 

E.  Dlcamba  plus  2,  4,  5-T  (or  2.  4-D),     1  lb,  plus  2  lbs.  per  100  gal.  water. 

DORMANT  CANE  SPRAYS 

F.  Ester  of  2,  4-D  plus  2,  4,  5-T.     3  lb.  plus  3  Ih .  per  100  gal.  oil. 
STUMP  OR  BASAL  SPRAY 

G.  Ester  of  2,  4-U  plus  2,  4,  5-T.     8  lb.  plus  8  lb.  per  100  gal.  oil. 
AERIAL  SPRAY 

H.   Ester  of  2,  4-D  plus  2,  4,  5-T.     6  lb.  plus  6  lb.  as  Invert  emulsion 

or  as  conventional  through  ralcrofoil  or  other  drift  control  devices  or  additives. 

DRY  PELLET  APPLICATIONS 


I.   Plcloram  lOZ  pellets.     60  to  85  lbs.  per  acre. 
SUSCEPTIBILITY  CODE 


S  -  Susceptible  (over  90X  rootkill) 

S-I  -  Susceptible  to  Intermediate  (70Z  to  90Z  rootkill) 

I  -  Intermediate  (50%  to  70Z  rootkill) 

I-P  -  Intermediate  to  Resistant  (30%  to  50%  rootkill) 

R  -  Resistant  (less  than  30%  rootkill) 


Manual  Recommendations 


239 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


1              SPECIES 

A 

B 

C 

D 

E 

F 

G 

II 

I 

Acacia  farneslana  hulsache 
Alder  (Alnus  spp. ) 

I 

I 

I-R 

S-I 

S-I 

s 

Common  (A.  serrulata) 
j     Red  (A.  rubra) 
j     Speckled  (A.  Incana) 
Apple  (Malus  spp. ) 

S 
S 
S 

s 
s 
s 

I 
I 
I 

s 
s 
s 

S 
S 
S 

s 
s 
s 

s 
s 
s 

s 
s 
s 

S-I 

I 

S-I 

Common  (M.  pumlla) 

I 

I-R 

R 

I 

S-I 

I 

s 

I 
s 

S 

Crab  (M.  ionesls) 
Arborvltae,  eastern 

I 

S 

I-R 

s 

S-I 

s 

s 

(Thuja  occidentalls) 

S-I 

R 

I-R 

s 

s 

s 

I-R 

s 

Ash  (Fraxinus  spp.) 

Blue  (F.  quadrangulata) 

s 

S 

I 

S-I 

s 

s 

s 

R 

S-I 

Red  (F.  Pennsylvanlca) 

I 

I-R 

I-R 

R 

s 

s 

s 

R 

Oregon  (F.  latlfolla) 

S 

S-I 

s 

s 
s 

s 
s 

R 
R 

R 

I 

White  (F.  amerlcana) 

I-R 

I-R 

I-R 

R 

s 

Black  (F.  nigra) 

I 

I-R 

s 

s 

s 

Aspen,  quaking 

(Populus  tremuloldes) 

S 

S-I 

S 

S 

s 

S-I 

s 

s 

Azalea  (Rhododendron  spp.) 

Piedmont  (R.  conescens) 

I-R 

I 

I 

I 

S-I 

S-I 

R 

Western  (R.  occldentale) 
Barberry,  Allegheny 

S 

I 

S 

S-I 

R 

(Berberis  canadensis) 

S 

I-R 

s 

I 

S-I 

S 
S 

s 

R 

Basswood  (Tllla  amerlcana) 

I-R 

I-R 

1-R 

s 

s 

Bayberry,  north 

(Myrica  Pennsylvania) 

S 

S 

S-I 

S 

I 

s 

s 

s 

Bearberry 

(Arctostaphylos  uvaursl) 

I 

I 

I 

I 

s 

s 

Beech,  American 

(Fagus  grandlfolla) 

I-R 

I-R 

I 

S-I 

S-I 

S-I 

S-I 

R 

s 

Birch  (Betula  spp.) 

Yellow  (B.  lutea) 

s 

S 

S-I 

S 

S 

s 

s 

s 

s 
s 

River  (B.  nigra) 

s 

s 

S-I 

S 

S 

s 

S 

s 

Gray  (B.  popull folia) 

s 

s 

S-I 

s 

s 

s 

s 

s 

s 

Paper  (B.  alba  var.  papyrifera) 

s 

s 

S-I 

s 

s 

s 

s 

s 

s 
s 
s 

Black  (B.  lenta) 

s 

s 

S-I 

s 

s 

s 

s 

s 

Blackberry  (Rubus  spp.) 

S-I 

s 

S-I 

s 

s 

s 

s 

s 

240      Bulletin    655 — American    Railway    Engineering   Association 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

C 

D 

E 

F 

G 

u 

I 

Blackgum  (Nyssa  sylvatlca) 

I 

I-R 

S-I 

s 

s 

s 

s 

s 

Blueberry  (Vaccinlum  spp.) 
Boxelder  (Acer  negundo) 

S-I 

S-I 

I-R 
S 

S-I 

s 
s 

S-1 
S-I 

s 

K 

R 

I 

s 

S-I 

Broom  scotch  (Gytlsum  scoparius) 

I-R 

I 

s 

s 

Buckbrush,  coral  berry 

(symphoricarpus  orbiculatus) 

S 

I 

s 

I 

S 

S-I 

I-R 

s 

Buckeye  (Aesculus  spp.) 

Ohio  (A.  glabra) 

Sweet,  yellow  (A.  octandra) 
Buckthorn  (Rhamnus  spp.) 

California  (R.  California) 

I-R 

S-I 

R 
R 

R 

I 

s 
s 

S-I 

s 
s 

s 

I-R 
I-R 

I 

Common  (R.  Cathartica) 
Hollyleaf,  redberry  (R.  Crocea 

var.  lliclfolla) 

R 
R 

I 
I 

S-I 
S-I 

s 
s 

I 
I 

Butternut  (juglans  clnerea) 
Button  bush,  common  (Cophalanthus 

occidentalis ) 

I-R 
S-I 

I-R 
R 

S-I 

I 

S-I 
S-I 

s 

s 

I-R 
I-R 

s 

s 

Cascara,  buckthorn  (Rhamnus  purshiana) 

I-R 

1-R 

S-I 

S-I 

s 

R 

Catalpa  (Cacalpa  spp.) 

Eastern  (C.  bignoniodes) 

S 

I 

S-I 

s 

I-R 

s 

Western  (C.  speclosa) 

I 

S-I 

s 

I-R 

Ceanothus  (Ceonothus  spp-.) 

Blue  blossom  (C.  thy rsl f lorus ) 
Chapparal  white  thorn(C.  leucodermis) 

S 

s 

S-I 

S 

I 
I 

s 
s 

s 
s 

S 
S 

Varnlshleaf  (C.  velutinus  var. 

laevigatus ) 

S-I 

s 

I 

s 

s 

S 

Deerbush  (C.  Integer rimus ) 
Wedgeleaf  (C.  cuneatus) 

S-I 

s 
s 

s 

I 

s 
s 

s 
s 

S 
S 

Mountain  whitethorn  (C.  Cordulatus) 

s 

s 

s 

s 

S 

Jersey  tea  (C.  americanus) 
Jimbrush  (C.  sorediatus) 

s 

s 

s 
s 

s 
s 

S 
S 

1  Cedar  (Juniperus  spp.) 

Eastern  red  (J.  Virginiana) 
Southern  red  (J.  silicicola) 

I 
I 

R 
R 

S 
S 

S-I 
S-I 

s 
s 

S-I 
S-I 

S-I 
S-I 

R 
R 

s 

s 

Chamise,  greasewood(Adenostoma 

Fasciculatum) 

S-I 

R 

S-I 

I 

s 

S 

s 

Cherry  (Prunus  spp.) 
Black  (P.  serotina) 

S-I 

S 

S 

S 

s 

S-I 

S-I 

I 

s 

Sweet  (P.  avium) 

s 

S 

S 

s 

s 

s 

s 

I 

s 

Choke  (P.  virginiana) 

1 

s 

S 

S 

s 

s 

s 

s 

S-I 

s 

Manual  Recommendations 


241 


TABLE  3  CCONTINUED]  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

c 

D 

E 

F 

G 

II 

I 

Chestnut  (Castenea  dentata) 

S 

S 

S-I 

s 

S 

s 

s 

S 

Chinkapin,  Allegheny  (Castenea  pumlla) 

s 

I 

s 

s 

I-R 

Chlnaberry  (mella  azedarach) 

I-R 

I-R 

I 

s 

R 

Coffeetree  (Gymnocladus  dioicus) 

S-I 

s 

s 

S-I 

Condulla,  lotewood  (Condulla  obtus- 

IfoXia) 

s 

S-I 

Cottonwood  (Populus  spp.) 

Plains  (P.  sargentll) 

S-I 

s 

s 

S-I 

s 

S-I 

s 

Rio  Grande  (P.  Hlallzenl) 

I 

s 

S-I 

s 

Eastern  (P.  deltoides) 

S 

S-I 

s 

S-I 

S-I 

s 

s 

s 

Downy,  black  (P.  het erophy 11a) 

S-I 

s 

s 

s 

Coyote  brush  (Baccharls  pilularlis) 

s 

R 

I 

s 

I 

Creosotebush  (Larrea  dlvarlcata) 

I 

R 

S-I 

S-I 

I 

s 

Chrlstnasberry ,  toyon  (Photlnla 

arbutlfolla) 

S-I 

I 

I 

s 

I 

Currant  (Rlbes  spp.) 

Gooseberry  (R.  montlgenum) 

s 

S 

S 

s 

S-I 

s 

Nutmeg  (R.  glutinasum) 

s 

s 

s 

S-I 

Prlckley  (R.  lacustre) 

s 

s 

s 

S-I 

Sierra  (R.  nevadense) 

s 

s 

s 

s 

S-I 

Sticky  (R.  vlscosisslmun ) 

s 

s 

s 

S-I 

Stink  (R.  bracteosum) 

s 

s 

s 

s 

S-I 

Trailing  black  (R.  laxlflorum) 

s 

s 

s 

S-I 

Wax  (R.  cereura) 

s 

s 

s 

S-I 

Western  black  (R.  petlolare)          | 

s 

s 

s 

s 

S-I 

Winter  (R.  sangulneum) 

s 

s 

s 

S-I 

Cypress  (Taxodlum  spp.) 

Common  baldcypress  (T.  distichum) 

I-R 

R 

s 

I 

I 

1 

I 

R 

s 

Pond  baldcypress  (T.  ascendens) 

R 

s 

I 

I 

I 

I 

R 

s 

Dangleberry  (Raylussacla  Frondosa) 

I 

I 

R 

s 

Deervetch,  broom  (Lotus  scoparlus) 

s 

I 

s 

S-I 

Devll-s  -  walkingstick(Aralia  splnosa) 

I 

S-I 

s 

I 

s 

s 

s 

Dewberry  (Rubus  spp.) 

I 

I 

R 

S-I 

s 

I-R 

s 

Dogwood  (Cornus  spp.) 

Pacific  (C.  nuttalll) 

S-I 

s 

S 

s 

s 

s 

I 

Flowering  (C.  Florida) 

s 

S 

s 

s 

s 

s 

I 

Elder  (Sambucus  spp.) 

Pacific  red  (S.  calllcarpa) 

S-I 

S-I 

s 

S-I 

S-I 

I 

s 

Blueberry  (S.  cerulea) 

S-I 

S-I 

s 

S-I 

S-I 

I 

s 

Common  (S.  Canadensis) 

i 

S-I 

S-I 

R 

1 

s 

S-I 

S-I 

I 
1 

s 

242      Bulletin    655 — American    Railway    Engineering   Association 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENT! 


SPECIES 

A 

B 

c 

D 

E 

F 

G 

II 

I_ 

Elm  (Ulmus  spp.) 

American  (U.  Americana) 

I 

I 

R 

S 

S 

S-I 

s 

I 

S 

Slippery  (U.  Fulva) 

I 

I 

R 

S-I 

s 

S-I 

s 

I 

s 

Winged  (U.  alata) 

I 

I 

R 

S-I 

s 

S-I 

s 

I 

S 

Evergreenchlnkapln  (Castanopsls  spp.) 

Sierra  (C.  Sempe rvlrens ) 

I 

I 

S-I 

s 

I 

Golden  (C.  Chrysophylla  var.  minor) 

S-I 

I 

S-I 

s 

I 

Filbert  beaked;  hazel  (Corylus  cornuta) 

S 

S 

S-1 

S 

I-R 

s 

s 

s 

s 

Fir  (Abies  spp.) 

White  (A.  concolor) 

I 

R 

S 

S 

s 

S-I 

S-I 

R 

s 

Balsam  (A.  bulsamea) 

I 

I-R 

S 

S^I 

S 

S-I 

S-I 

R 

s 

Grand  (A.  grandls) 

1-R 

R 

S 

s 

S 

S-I 

S-I 

R 

s 

Noble  (A.  procera) 

I-R 

R 

S 

s 

S 

S-I 

S-I 

R 

s 

Gallberry,  inkberry  (Ilex  glabra) 

S-I 

I-R 

S-I 

S-I 

I 

Goldenweed,  f leece (Haplopappus  arbor- 

escens) 

S 

s 

Gooseberry  (Ribes  spp.) 

California  (R.  Calif ornlcum) 

S 

s 

I 

S 

S-I 

Canada  (R.  oxyacanthoides ) 

S 

I 

s 

S-I 

Desert  (R.  velutlnum) 

S 

I-R 

s 

S-I 

Hupa  (R.  marshallli) 

S 

s 

S-I 

Sierra  (R.  roezlii) 

S 

s 

I-R 

s 

S-I 

Siskiyou  (R.  binominatum) 

S 

s 

R 

s 

S-I 

Tulare  (R.  tularense) 

s 

s 

S-I 

Whltestem  (R.  Inerme) 

S 

s 

S-I 

Gorse,  common  (Ulex  europeus) 

S 

I 

s 

S-I 

s 

Granjeno  (Celtis  pulllda) 

S-I 

s 

S-I 

s 

Grape,  riverbank  (vltls  riparia) 

S 

R 

S-I 

S-1 

s 

S-I 

s 

N.  fox  grape  (V,  labrusca) 

s 

S-I 

s 

Greasewood,  black  (Sarcobatus 

vermlculatls) 

s 

R 

I 

s 

I 

Greenbrier,  catbrler  (Smllax  rotundlfol- 

ia) 

I-R 

R 

I 

I 

R 

Hackberry  (Celtis  occldentalis) 

S-I 

R 

S-I 

I 

s 

S-I 

I 

s 

Hawthorn  (Crataegus  spp.) 

Cockspur  thorn  (C.  crus-galll) 

I 

I 

R 

S 

I 

I 

S-I 

I-R 

s 

Scarlet  (C.  coccinea) 

I 

S-I 

Flestry  (C.  succulenta) 

Manual  Recommendations 


243 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

c 

D 

E 

F 

r. 

H 

I 

Hazel  (Corylus  spp.) 

California  (C.  Callfornlca) 
American  (see  filbert) 

Hemlock  (Tsuga  canadensis) 

Hickory  (Carya  spp.) 

Bitternut  (C.  cordlformls) 
Hockernut  (C.  tonentosa) 

I 

S-I 
S-I 

s 
s 

R 

S-I 
S-I 

s 
s 
s 

S-I 
S-I 

S 
S 
S 

S-I 
S-I 

S 

s 
s 

s 
s 

S 

S 

S-I 

S-I 
S-I 

s 

S-I 

s 

s 
s 

R 
S-I 

s 
s 

S-I 
S-I 

Pecan  (C.  pecan) 
Pignut  (C.  glabra) 
Shagbark  (C.  orata) 
Shellbark  (C.  laclnlosa) 

S-I 
S-I 
S-I 
S-I 

S-I 
S-I 
S-I 
S-I 

S-I 

S-I 
S-I 

S-I 
S-I 

s 
s 

S-I 
S-I 
S-I 

S-I 

s 
s 
s 

Holly  (Ilex  amerlcana) 

Honeylocust  (Cledltsla  trlacanthos) 

I 

I 

S-I 

I 

s 

S-I 
S-I 

s 
s 

S-I 
S-I 

s 

S-I 

I-R 
S-I 

S-I 

s 

Honeysuckle  (Lonlecra  Japonlca) 

S-I 

S-I 

R 

S 

s 

s 

s 

S-I 

s 

Hophornbeam  (Ostrya  vlrglnlana) 

s 

I 

S 

s 

s 

s 

I-R 

s 

Hornbeam,  America  (Carplnus  carolinlana) 
llorsebrush,  llttleaf  (Tetradymla  glabrata 
llorsechestnut  (see  Buckeye) 

s 

I-R 

s 

s 

s 

s 

s 

S-I 

I-R 
I-R 

s 

Hydrangea,  smooth  (Hydrangea  aborescens) 

s 

s 

s 

s 

s 

s 

Juniper  (Junlperus  spp.) 
Alligator  (J.  deppeana) 
One-seeded  (J.  monasperma) 

I 

R 
R 

I 

I 
I 

S-I 
S-I 

I-R 

R 

S-I 
S-I 

Utah  (J.  osteosperma) 
Western  (J.  Occident  alls ) 

Kalmla  (Kalmla  spp.) 

Lambkill  (K.  angus 1 1  folia) 
Mountalnlaurel  (K.  latlfolla) 

Larch  (Larlx  spp.) 

Eastern  (L.  decldua) 

I 

I-R 
I-R 

R 
R 

I-R 
R 

R 

R 
R 

R 

I 

I-R 
I-R 

S-1 
S-I 

R 
I-R 

I-R 

I-R 
S-I 

R 

I-R 

S-I 

I 
I 

Western  (L.  Occident  alls ) 
Leatherwood,  Atlantic  (Dlrea  palustrls) 
Lilac  (Syrlnga  vulgaris) 
Locust  (Roblnla  pse udoac ac la) 

S-I 

I-R 

S 
S-I 
S-I 

S 
S 

S 

I-R 

I-R 

I-R 

S 

s 
s 
;-i 

S 

S-I 

S 

Hadrome,  Pacific  (Arbutls  raenzlesll) 

s 

s 

s 

s 

s 

Manzanlta  ( Arct os t apy los  spp.) 
Howell  (A.  hlspldula) 

s 

S 

r.reenleaf  (A.  patula) 
Hairy  (A.  Columbiana) 
Whlteleaf  (A.  vlsclda) 

s 

s 
s 
s 

R 

S 

I-R 

s 
s 
s 

s 
s 

s 

244      Bulletin    655 — American    Railway    Engineering   Association 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

c 

D 

F. 

F 

G 

II 

1 1 

Magnolia  (Map.nolla  spp.) 

Cucumbertree  (M.  acuminata) 

I 

S-I 

s 

I-R 

S 

s 

S-I 

S-I 

Sweetbay  (M.  virp.lnlana) 

R 

R 

R 

I 

I-H 

I 

Maple  (Acer  spp.) 

Red  (A.  rubrum) 

R 

I 

R 

S-I 

S-I 

s 

I-R 

s 

Silver  (A.  saccharlnum) 

I-R 

S 

s 

S 

S-I 

s 

Sugar  (A.  saccarophorum) 

S-I 

I-R 

I 

I 

S-I 

S-I 

s 

Vine  (A.  circlnatum) 

R 

I-R 

R 

I 

S-I 

S-I 

s 

Blgleaf  (A.  macrophy 11a) 

R 

R 

I 

S-I 

S-I 

s 

Mesquite,  honey (P ros op  is  jullflora  var. 

glandulosa) 

R 

S 

R 

S-I 

I-R 

s 

s 

Velvet  (Prosopis  jullflora  var. 

velutlna) 

S 

R 

I-R 

s 

Mockorange  (Phlladelphus  vlrginalus) 

S-I 

S-I 

s 

s 

Mount ainmahogany  (Cerocarpus  spp.) 

I 

I 

Mountain  misery,  bear  clover 

(Chamaebatla  follolosa) 

I 

I 

s 

Mulberry,  red  (Morus  rubra) 

I-R 

R 

I-R 

S-I 

I-R 

s 

Oak  (quercus  spp.) 

Black  (q.  nigra) 

S-I 

S-I 

S 

S-I 

S-I 

s 

S-I 

S-I 

Blackjack  (Q.  marllandica) 

S-I 

S-I 

s 

S-I 

S-I 

S-I 

S-I 

Bur  (Q.  macrocarpa) 

S 

S 

s 

S-I 

s 

S-I 

Canyon  live  (0.  chrysolepls) 

S-I 

s 

S-I 

California  scrub  (Q.  dumosa 

I 

s 

California  white  (Q.  lobata) 

s 

s 

Chestnut  (Q.  prinus) 

S-I 

s 

S-I 

I 

S-I 

s 

Live  (Q.  virginlana) 

S-I 

S-I 

S-I 

S-I 

s 

Pin  (Q.  palustrls) 

S 

S-I 

S-I 

S-I 

s 

S-I 

Post  (Q.  stellata) 

S 

S 

s 

S-I 

S-I 

s 

Laurel  (Q.  laurifolia) 

S-I 

S-I 

S-I 

s 

Red  (Q.  rubra  var.  borealis) 

S 

S-I 

S-I 

I 

S-I 

S-I 

S-I 

Scarlet  (Q.  coccinea) 

S 

S-I 

I 

I 

S-I 

S-I 

Swamp  white  (Q,  bicolor) 

s 

S 

S-I 

s 

Oregon  white  (Q.  garryana) 

s 

s 

s 

White  (Q.  alba) 

S 

s 

s 

S-I 

S-I 

s 

S-I 

Ocean  spray  (Halodlscus  discolor) 

S-I 

S-I 

s 

Oregongrape  (Mahonia  aquifolla) 

I 

I 

S-I 

I-R 

Osageorange  (Madura  pomifera) 

s 

R 

I 

S 

s 

S-I 

s 

Palmetto  (Saval  palmetto) 

S-I 

R 

I-R 

s 

S-I 

Pecan  (Carya  illinocnsis) 

I 

I 

I 

S-I 

s 

S-I 

Manual  Recommendations 


245 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

C 

D 

E 

F 

G 

H 

I 

Persimmon  (Ulospvros  virglniana) 

I 

R 

s 

s 

I 

S-I 

S-I 

s 

Pine  (Pine  spp.) 

E.  White  (P.  strobus) 

S-I 

R 

S 

S 

s 

S 

S-I 

I-R 

s 

Loblolly  (P.  caeda) 

S-I 

R 

S 

s 

s 

s 

s 

Lodgepole  (P.  contarta) 

S-I 

R 

S 

s 

s 

s 

s 

Longlcaf  (P.  palustrls) 

S-I 

R 

s 

s 

s 

s 

s 

Pitch  (P.  rigida) 

S-I 

R 

S 

s 

s 

s 

s 

Ponderosa  (P.  ponderosa) 

S-I 

R 

s 

s 

s 

Red  (P.  resionsa) 

I 

s 

s 

s 

s 

s 

Shortlcaf  (P.  echlnata) 

I 

R 

s 

s 

s 

s 

s 

Slash  (P.  caribaea) 

S-I 

I 

s 

s 

s 

s 

s 

Sugar  (P.  lambertlana) 

I 

s 

s 

s 

Table  mountain  (P.  pugens) 

S-I 

I 

s 

s 

Virginia  (P.  virglniana) 

S-I 

R 

I 

s 

S-I 

s 

s 

Western  white  (P.  monticola) 

I 

s 

S 

s 

s 

Jack  (P.  bankslona) 

S-I 

I 

s 

s 

s 

s 

s 

Plum  (Prunus  spp.) 

Chickasaw  (P.  angus tl folia) 

S 

s 

I 

s 

s 

S 

American  (P.  amerlcana) 

S-I 

S-I 

s 

I 

s 

Allegheny  (P.  alleghenlensls ) 

s 

I 

s 

s 

Poison  ivy  (Rhus  radlcans) 

S-I 

S-I 

s 

S-I 

S-I 

Poison  oak  (Rhus  spp.) 

Common  (R.  toxicodendron) 

S-I 

s 

s 

S-I 

I 

S-I 

s 

Pacific  (R.  dlverslloba) 

s 

s 

I 

1 

Poplar,  balsam  (Populus  balsamlfera) 

s 

S-I 

S-I 

s 

S-I 

S-I 

S 

s 

s 

White  (P.  alba) 

S-I 

S-I 

Prlcklyash,  common  (Zanthoxylum 

americanun) 

S-I 

I 

I-R 

S-I 

S-I 

s 

s 

Pricklypear  (Opuntia  spp.) 

Fragile  (0.  fragills) 

I 

R 

s 

I-R 

S 

I 

s 

Mission  (0.  megacantha) 

I 

s 

Plains  (0.  polyacantha) 

I 

s 

Spreading  (0.  humlfusa) 

I 

Privet,  swamp  (Forestlera  acuminata) 

R 

I-R 

R 

I 

S 

s 

s 

Rabbltbrush  ( Ch rysoth aranus  spp.) 

Douglas  (C.  viscldiflorus) 

I-R 

R 

s 

Greene  (C.  greenci) 

I 

s 

I 

Southwest  (C.  pulchellus) 

I-R 

I 

Bui.  655 


246      Bulletin    655 — American    Railway    Engineering   Association 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

c 

D 

E 

F 

G 

11 

I 

Raspberry  (Rubus  spp.) 

Red  (R.  Idaeus) 

S-I 

I 

S 

s 

s 

Black  (R.  occldencalls) 

S-I 

I 

S 

s 

s 

Redbus  (Cercis  spp.) 

Eastern  (C.  Canadensis) 

S-1 

I 

s 

s 

S-I 

S-I 

S 

S-I 

s 

Western  (C.  Occident  alls ) 

I 

s 

s 

S-I 

S-I 

s 

Redwood  (Sequoia  sempe rvlrens ) 

I 

I 

s 

S 

S 

I 

Redcedar,  western  (Thuja  pllcata) 

I 

R 

s 

S-I 

S-I 

I 

I 

R 

s 

Rhododendron  (Rhododendron  spp.) 

Canadian  (R.  Canadense) 

R 

R 

I 

I 

I-R 

R 

Pacific  (R.  macrophy Hum) 

R 

I 

Rosebay  (R.  maximum) 

R 

R 

R 

I 

I 

I 

Rose  (Rose  spp.) 

Arkansas  (R.  arkansana) 

I 

R 

S-I 

California  (R.  Californica) 

I 

Cherokee  (R.  laevigata) 

I 

R 

s 

McCartney  (R.  bracteata) 

S-I 

S-I 

R 

s 

S 

s 

Multiflora  (R.  multlflora) 

S-1 

•I 

R 

s 

S-I 

s 

Sweetbrlar  (R.  eglanterla) 

I 

R 

Sagebrush  (Artemisia  spp.) 

Big  (A.  tridentata) 

s 

S 

R 

s 

I-R 

S 

Black  (A.  nova) 

s 

s 

I-R 

California  (A.  Californica) 

s 

s 

I-R 

Sand  (A.  fllifolia) 

s 

s 

s 

I-R 

Silver  (A.  cana) 

s 

s 

I-R 

Salal  (Gaultherla  shallon) 

I-R 

1-R 

R 

I-R 

Salmonberry  (Rubus  spectabllis) 

S-I 

S-I 

R 

S-I 

I 

Saltbush,  fourwlng  (Atrlplex  canescens) 

S 

S 

R 

S-I 

Saltcedar  (Tamarlx  pentendra) 

I 

I 

I 

S-I 

I-R 

S-I 

S-I 

s 

Sassafras,  common  (Sassafras  albldun) 

S-I 

S-I 

S-I 

s 

S-I 

I 

s 

s 

Serviceberry  (Amalanchler  spp.) 

Allegheny  (A.  laevis) 

I 

S-I 

s 

I 

s 

Pacific  (A.  florida) 

S-I 

s 

Saskatoon  (A.  alnlfolia) 

S 

S-I 

S-I 

s 

Shadblow  (A.  Canadensis) 

s 

S-I 

s 

Snowberry  (Symphorlcarpos  spp.) 

Common  (S.  alba) 

s 

s 

I 

I 

Western  (S.  Occident  alls) 

s 

I 

Manual  Recommendations 


247 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

c 

D 

E 

F 

G 

H 

I 

Sourwood  (Oxydendrum  arboreun) 

I 

I-R 

R 

I 

I 

S 

S-I 

I 

s 

Splcebush,  common  (Llndera  benzoin) 

S 

S 

S 

S 

I 

S 

S 

S-I 

s 

Spire a  (Spiraea  spp.) 

Hardback  (S.  tomentosa) 

I 

X 

I 

I-R 

s 

S-I 

s 

Meadowsweet  (S.  alba) 

s 

I 

I-R 

Spruce  (Plcea  spp.) 

Black  (P.  marlana) 

1 

R 

R 

I 

S-I 

S-I 

S-I 

R 

s 

Engclnann  (P.  engelmanni) 

I-R 

R 

R 

S-I 

S-I 

s 

Norway  (P.  abies) 

I 

R 

R 

I 

S-I 

S-I 

s 

Red  (P.  rubens) 

I 

R 

R 

S-I 

I 

s 

Sitka  (P.  sitchensis) 

1-R 

R 

R 

S-I 

I 

s 

White  (P.  glauca) 

I 

R 

R 

S-I 

I 

s 

Sumac  (Rhus  spp.) 

Fragrant  (R.  aromatlca) 

S 

S-I 

R 

s 

S 

S-I 

S-I 

s 

s 

Laurel  (R.  laurlna) 

S 

R 

s 

S-I 

s 

Poison  (R.  vernix) 

s 

R 

S-I 

s 

Smooth  (R.  glabra) 

S-I 

S-I 

s 

s 

S-I 

s 

Staghorn  (R.  typhina) 

S 

S-I 

S-I 

s 

S 

S-I 

s 

Sweetfern  (Comptonia  peregrina) 

S-I 

I 

I 

I-R 

Sweetgum  (Liquidambor  styraciflua) 

S-I 

S 

S 

I 

I 

s 

s 

s 

s 

Sycamore  (Platanus  occi den  talis ) 

s 

s 

S 

s 

S-I 

s 

s 

s 

s 

Tamarack  (Larix  laricina) 

S-I 

I 

I 

S-I 

s 

S-I 

I-R 

s 

Tamarisk  (See  Saltcedar) 

Tanoak  (Lithocarpus  densiflorus) 

s 

I-R 

s 

s 

S-I 

Tarbush  (Flourensia  cernua) 

I 

R 

R 

I 

Tassajillo  (See  Pricklypear) 

Thiinbleberry ,  western  (Rubus  parviflorus) 

I 

I 

I-R 

s 

Titi  (Cliftonia  monophylla) 

s 

R 

S-I 

S-I 

S-I 

s 

Tree-of-heaven  (Ailanthus  altissima) 

s 

S-I 

I 

R 

s 

s 

I 

s 

Trumpetvine  (Campsis  radlcans) 

I 

I 

R 

S-I 

S 

I-R 

S-I 

Tulip  tree  (Li riodendron  styraciflua) 

s 

S-I 

I 

s 

S-I 

s 

s 

S-I 

s 

Viburnum  (Viburnum  spp.) 

Arrowwood  (V.  dentatum) 

s 

I 

I 

I 

S-I 

s 

I-R 

s 

Mapleleaf  (V.  ace rlf ollum) 

I 

I 

I 

S-I 

s 

Nannvberry  (V.  lentago) 

I 

I 

I 

S-I 

s 

Blackhaw  (V.  rufidulum) 

I 

I 

S-I 

I 

S-I 

s 

Virginia  creeper  (Parthenocissus 

quinque  folia) 

I 

I 

R 

I-R 

I-R 

248      Bulletin    655 — American    Railway    Engineering    Association 


TABLE  3  (CONTINUED)  -  SUSCEPTIBILITY  OF  WOODY  SPECIES  TO  HERBICIDE  TREATMENTS 


SPECIES 

A 

B 

C 

D 

E 

F 

G 

H 

1 

Wahoo,  eastern  (Euonymus  at ropurpureus ) 

S-I 

I-R 

S 

S 

I 

Walnut  (Juglans  nigra) 

S 

s 

S 

I-R 

S 

S 

S-I 

S 

Waxmyrtle  (Myrica  spp.) 

Pacific  (M.  californica) 

I 

I 

R 

R 

S-I 

s 

I-R 

s 

Southern  (M.  cerifera) 

I 

I 

R 

R 

S-I 

1 

s 

Whltebrush  (Aloysia  lycloldes) 

I 

R 

I 

Willow  (Sallx  spp.) 

Black  (S.  nigra) 

S-I 

S-I 

s 

S 

S 

I 

s 

s 

s 

Ditchbank  (S.  interior) 

S-1 

S-I 

s 

I 

s 

s 

Pacific  (S.  lasiandra) 

s 

s 

Red  (S.  laevigata) 

S-I 

I 

s 

Sandbar  (S,  exlgua) 

S-I 

s 

s 

White  (S.  alba) 

S-I 

Yellow  (S.  lutea) 

S-I 

Witchhazel  (Hamamells  spp.) 

Common  (H.  vlrglnlana) 

S 

s 

s 

S 

s 

s 

s 

s 

Southern  (H.  macrophylla) 

S 

Yaupon  (Ilex  vomitorla) 

I 

I 

S-I 

R 

I-R 

Yerbasanta  (Eriodictyon  spp.) 

California  (E.  Californicum) 

S-I 

I-R 

I 

Narrowleaf  (E.  angusti folium) 

S-I 

I-R 

Woolly  (E.  crassifolium) 

S-I 

Yellowwood  (Cladrast is lutea) 

S-I 

I-R 

's 

s 

I 

Yew  (Taxus  spp.) 

Florida  (T.  floridana) 

S-I 

R 

S-I 

S-I 

S-I 

R 

s 

Pacific  (T.  brevifolia) 

I-R 

S-I 

S-I 

s 

Yucca  (Yucca  elata) 

S-I 

I 

R 

I-R 

s 

S-I 

s 

Manual  Recommendations 
Committee   15 — Steel  Structures 

Report  on   Assignment  B 

Revision  of  Manual 

D.  L.  NoRD  (chairman,  Subcommittee  on  Revision  of  Manual),  J.  G.  Clark  (chairm.an. 
Subcommittee  on  Bibliography  and  Technical  Explanation  of  Various  Require- 
ments in  AREA  Specifications  Relating  to  Steel  Structures),  R.  I.  Simkins  (cfmir- 
man,  Subcommittee  on  Continuous  Welded  Rail  on  Bridges),  A.  J.  Wood 
(chairman,  Subcommittee  on  Welded  Steel  Railway  Bridges),  D.  S.  Bechly, 
A.  B.  Belfield,  Jr.,  E.  S.  Buxkenwald,  E.  Bond,  T.  J.  Boyle,  J.  C.  Bridge- 
farmer,  H.  L.  Chamberlain,  H.  B.  Cundiff,  L.  F.  Currier,  E.  J.  Daily,  A.  C. 
Danks,  J.  W.  Davidson,  F.  P.  Drew,  J.  L.  Durkee,  G.  F.  Fox,  J.  W.  Hart- 
MANN,  J.  M.  Hayes,  G.  E.  Henry,  C.  A.  Hughes,  L.  R.  Hurd,  M.  L.  Koehler, 
R.  C.  McMaster,  D.  V.  Messman,  W.  H.  Munse,  G.  E.  Morris,  R.  D. 
Nordstrom,  A.  L.  Piepmeier,  M.  Schifilacqua,  A.  E.  Schmidt,  F.  D.  Sears, 
H.  Solarte,  a.  p.  Sousa,  J.  E.  Stallmeyer,  Z.  L.  Szeliski,  J.  D.  Tapp,  Jr., 
W.  M.  Thatcher,  R.  N.  Wagnon,  C.  R.  Wahlen,  R.  H.  Wengenroth, 
W.   Wilbur. 

Your  committee  submits  for  adoption  the  following  revisions  to  the  SPECIFI- 
CATIONS FOR  STEEL  RAILWAY  BRIDGES,  Chapter  15  of  the  Manual: 

Page  15-1-15,  Art.  1.3.14.3 — Unit  stresses  for  combinations  of  loads,  and 
page  1.5-2-7,  Art.  2.3.2.3 — Unit  stresses  for  combinations  of  loads,  revise  as  follows: 

Change  title  of  Articles  by  adding  the  words  "or  wind  forces  only." 

Redesignate  subarticle  2.3.2.3  (c)   as  2.3.2.3  (d). 

Redesignate  subarticles  1.3.14.3  (b)  and  2.3.2.3  (b)  as  1.3.14.3  (c)  and  2.3.2.3 
(c),  respectively. 

Revise  the  last  lines  in  present  articles  1.3.14.3  (b)  and  2.3.2.3  (b)  to  read 
".  .  .  provisions  of  (a)  or  (b)  alone,"  and  delete  the  word  "other"  in  the  .second 
line. 

Subai-ticles   1.3.14.3   (a)   and  2.3.2.3   (a)   to  remain  as  written. 

Add  new  subarticles   1.3.14.3   (b)   and  2.3.2.3   (b)   to  read: 

"(b)  The  basic  allowable  unit  stresses  of  Section  1.4  shall  be  used  in  the 
proportioning  of  members  subject  to  stresses  resulting  from  wind  force  only,  as 
specified  in  Art.  1.3.8." 

On  page   15-1-18,  change  Art.   1.4.2   to  read  as  follows: 

1.4.2  Weld  Metal 

( a )  Groove  Welds 

Tension    or    compression    20,000  psi 

Shear   12,500 

(b)  Fillet  Welds 

Shear,  regardless  of  direction  of  applied  force. 

Electrodes    or   electrode-flux   combinations   with: 

60,000  psi  Tensile   Strength    "*  16,500 

70,000   psi  Tensile   Strength    *  19,000 

°but  not  to  exceed   12,500  psi  shear  stress  on  base  metal. 

249 


250      Bulletin    655 — American    Railway    Engineering    Association 

On  page  15-2-10,  change  Art.  2.4.2  to  read  as  follow.s: 

2.4.2  Weld  Metal 

In  the  formulas,  F„  =r  yield  point  of  l)ase  metal  as  specified  in  Art.  2.2.1 

(a)  Groove  Welds 

Tension  or  compression    55  F„ 

Shear   35  F„ 

(b)  Fillet  Welds 

Shear,   regardless  of  direction  of  applied  force. 
Electrodes  or  electrode-flux  combinations  with: 

70,000  psi  Tensile   Strength    "19,000  psi 

80,000  psi  Tensile   Strengtli    '22,000 

"but  not  to  exceed  0.35  Fy  shear  stress  on  base  metal. 
On  page  15-1-34,  delete  subarticle  (e)  of  Art.  1.11.4  and  redesignate  sub- 
articles  (f),  (g),  (h)  and  (i)  of  Art.  1.11.4  as  (e),  (f),  (g)  and  (h),  respectively. 
On  page  15-9-19,  delete  reference  to  Paragraph  (e)  in  Art.  9.1.11.4  and 
redesignate  the  references  to  Paragraphs  (f),  (g),  (h)  and  (i)  in  Art.  9.1.11.4  as 
(e),  (f),  (g)  and  (h),  respectively.  Cliange  the  word  "paragraph"  to  "subarticle" 
wherever  it  appears  in  Art.  9.1.11.4. 

On  page    15-3-5,   delete  Art.   3.1.12    (b). 

Revise,  as  follows,  proposed  new  Section  8.3 — Anchorage  of  Decks  and  Rails  on 
Steel  Bridges,  as  published  in  Bulletin  650,  November-December  1974,  pages  242- 
245: 

Art.  8.3.4.1  Movable  spans:   Add  new  paragraph  as  follows: 
"(b)   Deck  and  rails  shall  be  anchored  to  the  movable  span  as  specified  by  tlie 
engineer  to  prevent  movement  during  opening  and  closing." 

Delete  all  of  Art.  8.3.5  and  change  designation  of  Art.  8.3.6  to  8.3.5. 


Your  committee  also  submits  for  adoption  tlie  following  editorial  changes  in 
the  SPECIFICATIONS  FOR  STEEL  RAILWAY  BRIDGES,  Chapter  15  of  the 
Manual: 

On  page  15-2-2,  Art.  2.2.1  (c):  change  the  requirements  for  forged  steel  from 
A  235  or  A  237  to  A  668. 

On  page  15-2-2,  Art.  2.2.1  (c):  change  the  table  for  high-strength  structural 
steel  as  follows: 

1.  The  thickness  limitation  column  for  A  572,  Grade  60,  be  changed  from 
"To  1,  incl."  to  "To  1/4,  inch". 

2.  The  thickness  limitation  column  for  A  572,  Grade  50,  be  changed  from 
"To  1/2,  incl."  to  "To  2,  incl.". 

3.  The  applicable  to  shape  colvunn  for  A  588,  Fy  50,000  be  changed  to  "All." 

4.  The  applicable  to  shape  column  for  A  588,  Fy  46,000  be  changed  to  "None." 

5.  The   applicable   to   shape   column  for  A   572,   Grade  50,  be  changed  to 
"Groups  1,  2,  3  and  4." 

6.  The    applicable   to   shape   column  for  A  572,   Grade   42,   be  changed  to 
"Group  5." 

On  page   15-1-11,  revise  Art.    1.3.8  to  read: 

"(a)  The  wind  force  on  the  imloaded  bridge  shall  be  taken  at  50  lb  per  sq  ft 
of  surface  as  defined  in  Art.  1.3.7." 


Manual  Recommendations  251 


On  page  15-1-3,  revise  Art.  1.2.1  as  follows: 

1.  Change  the  requirement  for  forged  steel  from  A  235,  Class  E,  to  A  688, 
Class  D. 

2.  Delete  wrought  iron. 

On  page  15-1-3,  Art.  1.2.1  (a):  change  "Specifications"  to  "Designations"  and 
move  "current"  to  modify  requirements. 

On  page  15-2-2,  make  the  following  changes: 

1.  In   Art.   2.2.1    (a),   change   "Specifications"   to  "Designations"  and  move 
"ciurrent '  to  modify  requirements. 

2.  In  Art.  2.2.1   (c),  add  footnote  4  at  bottom  of  table:    ("4"  to  be  added 
to  all  but  first  column  at  left) 

"4  These  data  are  for  infonnation  only  and  are  current  as  of  May,  1975." 
On  page  15-9-4,  delete  the  last  sentence  of  the  first  paragraph  and  insert  the 
bibliography  reference   (2)    between  the  words  "tests"  and  "were"  in  the  next  to 
last  sentence  of  the  first  paragraph. 


Advertisement 


252-1 


The  Aifegheny  Insulated  Rail  Joint- 

Designed  to  withstand  the  heaviest  traffic 
in  welded  rail 


This  modern  joint  cements  roil  ends  in  position  and  thereafter 
resists  all  forces  imposed  by  temperature  and  simultaneous  forces 
of  live  loads  to  move  them. 

This  joint  makes  welded  rail  truly  continuous.  It  promises  you  years 
of  service  without  maintenance  costs.  It  reduces  rail  and  wheel  batter 
to  a  previously  unknown  minimum.  It  employs  the  safety  of  steel  splice 
bars.  It  can  be  assembled  in  the  shop  or  field.  It  has  been  tested  in 
service  and  AAR   laboratories.   It  saves  you   lots  of  money. 

Allegheny  Drop  Forge  Company 

Subsidiary  of  Tasa  Corporation 
2707  Preble  Avenue  •  Pittsburgh,  Pa.   15233 


252-2 


Advertisement 


I 


MEMBER 

m 

•lUrilux   la^k 


Advertisement  252-3 


We've  a  lot 
going  for  you. 


We  call  it  "The  Big  Green,"  and  it's  all  go.  For  you. 

It's  what  we  put  into  every  one  of  our  railway  products  to 
give  you  the  big  return  you  want  and  need,  to  meet  required 
standards  on  your  roads. 

Our  anchors,  rail  joints,  heaters,  rail  and  flange  lubricators, 
and  renewal  insulation  give  you  the  edge  in  every  major 
investment  consideration. 

They're  built  to  give  you  longer,  trouble-free  performance. 

They're  built  for  fast  and  easy  installation. 

They're  built  to  save  manhours,  reduce  downtime,  keep  your 
trains  rolling. 

That's  where  the  real  savings  dollars  are.  That's  where  the  bfg 
return  is.  Has  been.  Always  will  be. 

That's  why  you  should  talk  to  your  Portec  man  before  you 
invest  in  rail  anchors,  joints,  heaters  or  rail  and  flange 
lubricators,  and  renewal  insulation. 

The  big  green.  It's  as  close  as  your  phone. 

RAILWAY  PRODUCTS  DIVISION 

The  better  product  producing  people. 

PORTEC  nc 

300  Windsor  Drive  •  Ookerook,  Illinois  60521 
(312)325-6300  •  TWX  No.  91 0-651 -0212 


252-4 


Advertisement 


KERITE 
CABLE 


For  dependability  in  actual  use,  no  other  cable 
matches  Kerite.  We  believe  you  will  be  im- 
pressed by  the  evidence. 

THE  KERITE  COMPANY 

PRINCIPAL  OFFICES:  Boston;  Chicago;  New 
York;  Philadelphia;  San  Francisco;  and 
Seymour,  Connecticut  •  Sales  Representa- 
tion throughout  the  United  States.  A  sub- 
sidiary of  Harvey  Hubbell   Incorporated. 

RITE  insulation  that  makes  the  difference 


Advertisement 


252-5 


LORAM 

Modern  Maintenance 
of  Way  Equipment 

with  an  estabHshed 
track  record . . . 


WINCH  CART 


SHOULDER  BALLAST  CLEANER 


. . .  designea 
to  do  the  job 
easier,  quicker 
and  at  less  cost 
—  with  your 

men  or 

ours! 


I  I     I-   ^^ 

.  ,  Ii-. 


-•    111  •^^'SirJiSiriaiK 


^.1 


«     II  ■    I  »8S!^9;^lBiriiSlMi     i'.v^rA 


MULTI  PURPOSE  MACHINE 


I      . 


-    1 


TSM*,  ?  »■  vfij^HJb^rifillSlI     •&  'i  iS:z 


AUTOTRACK  WITH  PLOW  AND  SLED 


THE  ANSWER  TO  YOUR  1975  TRACK  REHABILITATION  PROGRAM 


M  E  M  B  £  R 

RRI 


LORAM  RAILWAY  MAINTENANCE  EQUIPMENT  FOR: 

•  Shoulder  Ballast  Cleaning  •  Raising  Track  •  Resurfacing  • 
Reballasting  •  Replacing  Ties  •  Undercutting  •  Ballast  Cleaning 

•  Rail  Grinding  SingleorMultipietrack-MainlineorYard tracks 

CONTRACT,  SALE  or  LEASE 


FOR  FULL  DETAILS 
OR  SHOWING  OF 
OPERATING  FILMS, 
WRITE  OR  CALL  TODAY 


MAINTENANCE  OF  WAY,  INC. 

3900  Arrowhead  Drive   •   Hamel,  MN  55340  U.S.A. 
PHONE:  (612)  478-6014  •  TELEX:  29-0397;  Cable.  LORAM 


252-6 


Advertisement 


RAItROAD  TRACKS 

designed,  constructed 

a^^d  completely  maintained 


ROBT.  L.  DEPRIZIO 
&  ASSOCIATES  INC. 


^||^^J^,J^g|io  C  n.v.rici'on  Compmy 


Advertisement 


252-7 


Safetran  System's  new,  portable 


44 


Rail  Whiz 

ABRASIVE  TYPE  RAIL  SANA^ 

Model  082000-X 


99 


Quick  Attachment  to  the  Rail  — 
5  seconds  or  less. 


Self-Centering  to  fit  any 
weight  of  rail,  60  lbs. 
through  152  lbs. 
(without  additional 
adapters  or  brackets). 


Vertical  and  Horizontal 
Resisters  insuring  a 
90°  cut. 


Accurate  cuts  provided 
by  the  unique  abrasive 
wheel  guide. 


Fully  reversible  power 
unit  support  arm  for  pre 
cision  rail  cuts  from 
either  side  of  rail  with  the 
engine  in  the  normal  up- 
right position  at  all  times. 


Accurate  rail  alignment  by  the 
fixture  "V"  type  rail  clamp. 


Rotation  of  cutting  wheel 

deflects  all  sparks  toward 

ground  at  all  times. 


Air  breather  intake  is  free 
of  abrasive  dust. 


Power  unit  can  be 

latched  up  (off  rail)  in 

the  upright  position  on 

either  side  rail  for 

starting  or  servicing. 


Safetran  superior 

abrasive  cutting  wheels 

cut  safe,  fast  and 

accurate. 


180°  rotation  of  saw 

permits  full  usage  of  blade 

without  sacrificing  a 

square  cut. 


Carrying  case  available. 


Patent  Pendini 


For  more  information  or 
demonstration  —  contact: 


Safetran  Systems  Corporation 

7721  National  Turnpike  •  Loursville,  KY  40214  •  (502)  361.1691 


252-8  Advertisement 


A  tradition  of  service  .  .  . 

*  Water  Treatment  Chemicals  Protecting  Diesel  Cooling 
Systems  and  Steam  Generators 

*  Fuel  Oil  Additives 

*  Pollution   Control   Chemicals   and   Consulting   Services 


NALCO    CHEMICAL   COMPANY 

2901    BUTTERFIELD    ROAD    •    OAK    BROOK,    ILLINOIS    60521 


M 


» 


Trademarks  of  Naico  Chemical  Company  |\|  /^  LC  C3 


Advertisement 


252-9 


Repair  at  10% 

of  replacement 

cost! 

The  structural  cracks  in  this 
bridge  are  being  "welded"  with 
epoxy.  Osmose  epoxy  injec- 
tion restores  structural  integrity 


without  service  interruptions  at 
a  fraction  of  replacement  cost. 


The  proven  OSMOSE  method: 

•  ANALYSIS  •  CLEANING 

•  SEALING  •  CONTROLLED 
PRESSURE  INJECTION 

•  DETAILED  INSPECTION 
REPORTS 


OSMOSE  RAILROAD  DIVISION 


4915  Monona  Drive 
Madison,  Wis.   53716 


252-10 


Advertisement 


TIE  HANDLER  from  RTW... 


■  >^ 

/it — ""l^^^^^^^^^^^B 

j^^r 

JwMii^'' 

^^^^^^^^^^^H^^^kI^'^"^ 

""'^-.'•x^><<^^^^'^.  •«wp|i^|^^^^^^^^^^^^^^^^^^H 

^^^^^^^^^^^^^■k^-^ 

with  24'foot'reach 
articulating  boom! 

Lifting  capacity-1500  lbs.  at  12' 6 "to 
750  lbs.  fully  extended. 


•  New  rotating  deck  design 
...no  adjustments  needed 

•  Thermostatic  controlled 
oil  temperature  in 
hydraulic  circuit 


•  Low  maintenance 

•  Hydrodynamic  plus 
mechanical  brakes... 
on  all  four  wheels 


Many  other  features  for  high  production,  low  maintenance.  Choice  of  two 
other  tubular-type  booms  (all  interchangeable):  Fixed  24-ft..  and  manually 
adjustable  18-24-ft.  From  RTW,  the  people  with  the  longest  experience  in 
tie  handling.  Get  full  details  today.  Call  (215)  739-4281. 

^^-"""''""'''^'^^  OTHEI ITW  MAINTENtNCE  ESUIPMENT  ■  Switch  Crinderi  •  Crass  binders  •  Surfice  Grinders  •  Rail  Drilll  •  Tie  Hanlleri  MEMBCR 

BVyUMj      RAILWAY  TRACK-WORK  CO.  2560  East  Tioga  St.,  Philadelphia,  Pa.  19134         I^P§ 

■^l   W     /         Agents:  Chicago- ESCO  Equipment  Service  Co.  •  Houston -Service  Equipment  &  Supply  Company         "* »    T 
Los  Angeles -Siml<ins  Company  Louisville -T.  F.  Going  •  St.  Louis -R.  E.  Bell  Co.  .MrTiKS'ii 

S   Plainfield,  N.  J.  -  Ea'Jern  Railroad  Equipment  Corp.  •  Canada:  Montreal  -  Woodings-Canada  Ltd. 


Advertisement 


252-11 


n 


WELD  60-80 

STRAIGHT  OR  COMPROMISE 

JOINTS 
DAILY! 


^«»!?f 


THERMIT 


SELF-PREHEAT 
RAIL  WELDING 


THE  MODERN  IN-TRACK  METHOD 

•  AUTOMATIC,   ERROR-FREE  PRE-HEATING  AND 
TAPPING  OF  WELD  METALS 

•  EASY,  COLD  REMOVAL  OF  RISERS 

•  MINIMUM  GRINDING 

•  NO  EQUIPMENT  TO  PURCHASE  OR  LEASE 
COMPLETE  THERMIT  RAIL  WELDING  DE- 
TAILS PLUS  JOB-SITE  DEMONSTRATIONS. 

WRITE  OR  CALL 


US.  THERMIT  INC 

Lakehurst,  New  Jersey  08733   •  (201)657-5781 


252-12 


Advertisement 


Channeloc 

Massive,  unique  channel  shape  pro- 
vides tremendous  gripping  power.  Its 
great  tensile  strength  adds  years  to 
service  life  .  .  .  and  saves  replacement 
costs.  Channeloc  is  applied  easily  and  quickly  with 
minimum  ballast  disturbance  .  .  .  and  can  be  re- 
applied. 

Cliploc' . . .  designed,  tested  and  proven  for  modern 
concrete  tie  installations.  Choose  from  standard 
Cliploc  or  insulated  Cliploc  with  permanent  fiber- 
glass-reinforced epoxy  for  100%  insulation. 


Two 
for  the 

l^/dVl...and  then  some! 


Cliploc' 


To  assure  continued  quality  control.  True  Temper 
maintains  a  Field  Service  Department.  These  field 
engineers  spot-check  rail  anchor  applications  and 
return  at  specified  intervals  to  check  in-service 
durability. 


mfRUE 

fS^SSf       RAtL\^/AY  AP 


Temper. 


PPLIANCE   DIVISION 


COMPAIMV   Of   ALLEGHENY 


INDUSTRIES 


#53iP 


#■    / 


'^^^^^^^m^^'^^^^^:^ 


Channeloc  is  protected  By  US  Patent  Numlaers  3,102,690  —  3.1 18,327 —  3,159.198.  Cliploc  is  protected  by  U  S  Pjicnt  Nurr 


Advertisement 


252-13 


■ 

\ 

INSPECTION  MOTOR  CARS 
SECTION  MOTOR  CARS 
GANG  MOTOR  CARS 
PUSH  CARS  AND  TRAILERS 
HY-RAIL  EQUIPMENT 
BALLAST  MAINTENANCE  CARS 
WEED  MOWERS 
TOW  TRACTORS 
RAIL  GRINDERS 
DERRICK  CARS 
HYDRAULIC  POWER  TOOLS 
TRACK  LINERS 

TRACK  LINING  LIGHT 

SPIKE  DRIVERS 

TIE  REMOVERS 

TIE  HANDLERS 

RAIL  LIFTERS 

TIE  SHEARS 

TIE  BED  SCARIFIERS 

SPIKE  PULLERS 

TIE  PLUG  INSERTERS 

OIL  SPRAYERS 

TIE  SPRAYERS 

TIE  INSERTERS 



(PiAfounance 

ON   THE   JOB 
COUNTS 

THESE  UNITS  ARE  ACTUATED  EITHER  COMPLETELY 
OR  PARTIALLY  BY  HYDRAULIC   POWER 


FAIRMONT  RAILWAY  MOTORS,  INC.,  FAIRMONT,  MINNESOTA  56031 


252-14  Advertisement 


1C|EWEJLD 

Rail  Maintenance  Service 

Rail  End  Welding 

Rail  End  Hardening  0Pf 


MBMBER 


CWR  Joint  Normalizing  "!I^ 

Frog  and  Switch  Welding  """"" 

Rail  Maintenance  Equipment 

Custom  Manufacturing  and  Fabrication 

Joint  Bar  Shims 

Rail  Anchor  Shims 

Rail  End  and  Frog  and  Switch 

Welding  and  Grinding  Machines 
CWR  Heating  and  Cooling  Equipment 
Rail  Flaw  Testing  Equipment 
Telebrineller  Portable  Hardness  Tester 


V  Infro-Rad   Haator  for  Curing   Adhativ*  Bendad  Rail  Joints 

TELEWELD  INC.,  416  NORTH  PARK  ST.,  STREATOR,  ILL.  61364 

Write  for  details  of  the  TELEWELD  process  for  restoring  rail  ends. 


PART  2 


REPORTS  OF  COMMITTEES 

Nofe:    Discussion    on    subcommittee    reports    herein    closes    on    January 
20,    1976. 


253 

Bui.   655 


Report  of  Committee  9 — Highways 


C.  A.  Christensen, 

Chairman 
L.   T.   Cerny, 

Vice  Chairman 
G.  U.  Mentjes, 

Secretary 


J.   E.   Spaxgleh 
J.  R.  Summers 
P.  A.  Shuster 
H.  L.  Michael 
C.  Shoemaker 
A.  O.  Kruse 
T.   P.   Cunningham 
C.  W.  Smith 
R.  E.  Skinner 
J.  L.  Whitmeyer 
P.    J.    McCuE 
W.  W.  Allen 
H.  J.  Barnes 
J.   M.   Bates 

J.   P.    BOLLING 

W.  B.  Calder 
A.  L.  Cabpenter 
J.  W.  Cruikshank 
F.  Daugherty 
R.  A.  Downey 
L.  L.  George 
R.  V.  Gilbert 
H.  D.  Hahn 
C.  I.  Hartsell  (E] 


WxM.  J.  Hedley  (E) 

D.  P.  Insana 

P.  G.  Jefferis,  Jr. 

M.  D.  Ken  yon 

R.  V.  Loftus 

R.  F.  MacDonald 

R.  A.  Mather 

J.  C.  Miller 

H.  G.  Morgan  (E) 

G.    S.    MUNRO 

R.  D.  Pamperl 

R.  H.  Patterson 

W.  C.  Pinschmidt  (E) 

J.  E.  Reynolds 

H.  A.  Richards 

F.  E.  Rosencranz 

P.  L.  Sehnert 

M.    R.    S PROLES 

D.  Veitch 

W.  E.  Webster 

H.    J.    WiLKINS 
H.    L.    WOLTMAN 
C.   H.   WORBOYS 

Committee 


(E)    Member  Emeritus. 

Those    whose    names    are    shown    in    boldface,    in    addition    to    the    chairman,    vice    chairman 
and    secretary,    are    the    subcommittee    chairmen. 

To   the   American   Railway  Engineering  Association: 

Your  Committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 

Progress   report  submitted   as   information    page  256 

1.  Grade  Crossing  Inventory  and  Accident  Report  Forms,   Records   and 
practices. 

Information  is  being  gathered  and  the  committee  expects  to  develop 
recommendations  for  new  report  forms  and  signs  in  the  coming  year. 

2.  Merits  and  Economics  of  Types  of  Grade  Crossing  Surfaces. 
Report  on  performance  of  railbound  concrete  slab  crossing  on  EJ&E  in 
Griffith,   Ind • Page  257 

3.  Summary    Reporting    of    Significant    Piil)Iications    on    Grade    Crossing 
Safety. 

Summarized  reports  furnished  as  information    page  258 

4.  Evaluation  of  Developments  in  Passive  and  Xon-Train-Actuated  Grade 
Crossing  Warnings. 

No  report  for  past  year's  acti\  ity. 

5.  Study  of   Motor  Vehicle   Codes   and   Drivers'   Licensing  Practices. 

Progress   report   submitted  as   information    page  263 

255 

Bui.   655 


256      Bulletin    655 — American    Railway    Engineering    Association 

6.  Air  Rights  for  Highways  Over  Railroad  Property. 

No  report  for  past  year's  activity.  Highway  Researcli  Board's  Report 
No.  142  has  recently  been  released  and  it  will  be  reviewed  by  tlie 
committee. 

7.  Evaluation  of  Developments  in  Train-Actuated  Grade  Crossing  Warn- 
ings, Collaborating  as  Necessary  or  Desirable  with  Communication  and 
Signal  Section,  AAR. 

No  report  for  past  year's  activity. 

8.  Investigate  Uses  and  Types  of  Rumble  Strips  and  Their  Adaptability 
for  Approaches  to  Highway-Railway  Grade  Crossings. 

Progress  report  submitted  as  information    page  264 

9.  Study  of  Public  Pedestrian  Crossings. 

Progress   report  submitted  as  information    page  266 

10.  Summary    Reporting    of    Administration    of    State    Crossing    Safety 
Programs. 
A  new  subject.  No  report  for  past  year's  activity. 

The  CoMMrrxEE  on  Highways, 

C.  A.  Christensen,  Chairman. 


Report  on  Assignment  B 

Revision  of  Manual 

J.  E.  Spangler  (chairman,  subcommittee),  J.  M.  Bates,  C.  A.  Christensen,  L.  T. 
Cerny,  J.  W.  Cruikshank,  F.  Daugherty,  R.  V.  Gilbert,  H.  D.  Hahn,  C.  I. 
Hartsell,  D.  p.  Insana,  P.  G.  Jefferis,  R.  V.  Loftus,  R.  F.  MacDonald, 
G.  U.  Mentjes,  J.  C.  Miller,  G.  S.  Munro,  R,  E.  Skinner,  David  Veitch, 
W.  E.  Webster,  Jr.,  C.  H.  Worboys. 

Consideration  is  now  being  given  to  revisions  in  portions  of  the  miscellaneous 
section  of  Chapter  9  of  the  Manual.  Proposals  include  the  substitution  of  the  DOT- 
AAR  Crossing  Inventory  Form  for  the  Highway  Grade  Crossing  Record  now  shown 
on  pages  9-M-6  and  9-M-7,  changes  in  the  Accident  Report  on  pages  9-M-4  and 
9-M-5,  revision  of  the  type  of  barriers  used  in  closing  grade  crossings  and  at  dead- 
end streets  on  pages  9-M-2  and  9-M-3,  and  deletion  of  sample  sheets  showing  record 
of  delays  at  grade  crossings   (pages  9-M-8  and  9-M-9). 


Highways 257 

Report  on  Assignment  2 

Merits  and  Economics  of  Types  of  Grade  Crossing  Surfaces 

p.  A.  Shuster  (chairman,  subcommittee),  W.  B.  Calder,  L.  T.  Cernv,  C.  A. 
Christensen,  J.  W.  Crudcshank,  T.  P.  Cunningham,  R.  A.  Downey,  R.  V. 
Gilbert,  H.  D.  Hahn,  C.  I.  Hartsell,  Wm.  J.  Hedley,  A.  O.  Kruse,  R.  V. 
LoFTus,  G.  S.  MuNRo,  R.  D.  Pamperl,  R.  H.  Patterson,  F.  E.  Rosencranz, 
G.  Shoemaker,  W.  E.  Webster,  Jr.,  C.  H.  Worboys. 

On  page  159  of  Volume  74  of  the  AREA  Proceedings,  there  is  a  report  on  an 
inspection  of  a  new  design  concrete  slab  crossing  in  the  vicinity  of  Diisseldorf, 
Germany,  by  a  committee  member. 

In  October  of  1973,  the  Elgin,  Joliet  &  Eastern  Railway  installed  four  of  these 
crossings  at  Broad  Street  in  Griffith,  Indiana,  at  the  request  of  the  city.  The  city 
contributed  tlie  additional  cost  of  these  slabs  over  the  cost  of  the  solid  timber  crossing 
that  the  railroad  had  intended  to  install  at  its  own  cost.  The  initial  reaction  to  the 
crossing  by  the  city  was  very  favorable,  with  smootli  riding  qualities  evident  to  the 
motorists.  However,  within  five  months  of  the  time  of  installation,  various  problems 
started  to  occur,  especially  the  breaking  of  the  hardware  holding  the  rail  to  the  steel 
rod  which  runs  under  the  rail  (in  this  design  crossing  there  is  no  direct  attachment 
of  the  crossing  slabs  to  the  cross  ties,  only  attachment  to  the  bar  running  under 
the  rail).  The  washers  and  bolts  and  spring  clips  experienced  breakage  and  the 
concrete-filled  bags  supporting  the  slabs  on  top  of  the  tie  experienced  an  approximate 
15%  failure  rate.  An  additional  problem  was  the  fact  that  the  insulation,  which  is 
required  if  this  crossing  is  used  with  track  circuits,  did  not  hold  up  and  numerous 
calls  of  the  signal  maintainer  were  necessary  on  overtime.  Considerable  bridge  and 
building  time  was  also  required  for  maintenance  of  the  crossings. 

At  present,  maintenance  is  stabilized  at  approximately  one  gang  day  (four  men 
per  gang)  every  two  months.  The  manufacturer  has  been  working  with  the  railroad, 
and  at  various  times  redesigned  hardware  and  insulation  were  substituted  for  that 
already  in  the  crossing.  The  manufacturer  has  now  proposed  a  new  type  insulation 
for  the  two  crossings  which  are  in  signal  territory  and  a  new  reactive  spring  washer 
to  absorb  some  of  the  stresses  in  the  hold-down  hardware. 

In  view  of  the  above  it  is  the  opinion  of  this  committee  that  this  crossing  should 
still  be  regarded  as  in  the  developmental  stage,  especially  if  use  on  heavy-duty  track- 
age is  involved.  During  all  tliis  time  the  highway  riding  qualities  have  remained 
smooth,  but  this  has  been  only  with  considerable  maintenance  on  die  railroad's  part. 
The  opinion  of  the  railway  is  that  it  would  have  been  better  to  install  the  railroad's 
standard  full-depth  timber  crossing,  as  this  design  can  often  go  with  no  maintenance 
for  ten  or  more  years  under  similar  conditions.  The  subcommittee  intends  to  report 
further  on  additional  developments  on  this  particular  crossing. 

This  is  a  progress  report  submitted  as  information. 


258      Bulletin    655 — American    Railway    Engineering    Association 

Report  on  Assignment  3 

Summary  Reporting  of  Significant  Publications  on 
Grade  Crossing  Safety 

H.  L.  Michael  (chairman,  subcommittee),  L.  L.  George  (vice  chairman,  subcom- 
mittee), W.  W.  Allen,  J.  P.  Bolling,  A.  L.  Carpenter,  L.  T.  Cerny,  C.  A. 
Christensen,  M.  D.  Kenyon,  A.  O.  Kruse,  R.  V.  Loftus,  P.  J.  McCue,  R.  A. 
Mather,  R.  D.  Pamperl,  R.  H.  Patterson,  H.  A.  Richards,  R.  E.  Skinner, 
C.  W.  Sauth,  J.  R.  Summers,  David  Veitch,  J.  L.  Whitmeyer,  H.  J.  Wilkins, 

H.   L.    WOLTMAN. 

INTRODUCTION 

The  Subcommittee  assignment  continues  to  be  the  reporting  in  summary  format 
of  significant  publications  or  developments  in  grade  crossing  safety.  This  year  four 
publications  and  progress  on  several  significant  research  projects  in  grade  crossing 
protection  are  reported. 

"The  Effectiveness  of  Automatic  Protection  in  Reducing  AccroENT  Frequency 

AND  Severity  at  Public  Grade  Crossings  in  California/'  California 

Public   Utilities   Commission,   Transportation   Division,  and 

Railroad    Operation    and    Safety    Branch,    Traffic 

Engineering  Section,  San  Francisco,  California, 

June  30,  1974. 

This  report  is  more  comprehensive  than  were  previous  annual  studies  of  this 
same  title.  The  executive  summary  of  the  report,  slightly  modified  in  the  opening 
paragraph,  summarizes  the  content  very  well  and  follows. 

This  study  was  sponsored  by  the  Office  of  Trafiic  Safety  of  California  to  assist 
the  California  Public  Utilities  Commission  in  performing  its  duties  related  to  grade 
crossing  regulation,  to  determine  the  scope  of  the  vehicle-train  accident  problem 
in  California,  to  gauge  the  effectiveness  of  various  types  of  warning  devices  being 
currently  advocated  by  the  Commission,  and  to  critically  investigate  tlie  possible 
use  of  warrants  or  criteria  to  assist  in  recommending  wliere  monies  should  be  spent 
on  railroad-highway  grade  crossing  warning  improvements.  The  study  provides  infor- 
mation regarding  the  installation  of  various  warning  devices  and  the  cost  to  the 
public. 

The  project  was  segregated  into  four  separate  studies  based  upon:  (1)  a  ques- 
tionnaire mailed  to  all  cities  and  counties  in  California;  (2)  an  examination  of  the 
before-and-after  accident  histories  of  1,552  grade  crossings  currently  protected  by 
automatic  devices;  (3)  a  summary  of  the  actual  and  estimated  costs  of  installing 
automatic  warning  devices  at  1,296  locations;  and  (4)  an  examination  of  the  feasi- 
bility of  using  warrants  or  criteria  to  assist  in  placing  grade  crossing  warning  devices. 

The  questionnaire  designed  to  appraise  local  concern  and  awareness  of  the 
vehicle-train  accident  problem  in  California  was  mailed  to  380  cities  and  counties. 
The  local  governmental  agencies  were  requested  to  describe  their  decision-making 
processes,  including  whether  or  not  they  used  specific  warrants  or  criteria,  how 
they  rated  the  relative  importance  of  several  physical  conditions  common  to  many 
pre-existing   hazard    indices,    sufficiency    rating   and    regression   equations    and  how 


Highways         259 

they  specifically  felt  about  the  j^racle  crossing  pio,i;iam  as  handled  by  the  Public 
Utilities  Commission. 

The  effectiveness  analysis  was  designed  to  assess  the  capacity  of  various  warn- 
ing devices  in  reducing  the  number  of  vehicle-train  accidents  and  their  related 
deaths  and  injuries.  In  all,  1,552  locations  were  chosen  where  automatic  warning 
was  installed  between  January  1,  1960,  and  December  31,  1970.  Compared,  for 
each  crossing,  were  the  number  of  accidents,  deaths  and  injuries  per  year,  and  the 
number  of  deaths  and  injuries  per  accident. 

In  order  to  gauge  the  installation  costs  of  automatic  warning,  1,296  locations 
were  chosen  where  automatic  warning  was  proposed  or  installed  between  January  1, 
1966,  and  December  31,  1973.  In  addition  to  listing  the  actual  or  estimated  in- 
stallation cost  at  each  location,  each  crossing's  previous  warning  devices,  number 
of  tracks,  railroad,  type  of  device  installed  and  the  proposed  year  of  installation 
were  documented. 

To  examine  the  possible  use  of  warrants  or  criteria  in  the  installation  of  auto- 
matic signals,  115  locations  were  chosen  at  random  from  the  1,552  crossings  used 
as  input  locations  for  the  effectiveness  analysis.  Only  crossings  presently  protected 
by  automatic  devices  were  chosen  for  the  purpose  of  examining  past  policies  of  the 
Commission  as  it  concerns  warning  improvement  to  try  to  pinpoint  any  discernible 
patterns.  The  detailed  information  on  each  crossing  was  used  to:  (1)  develop  a 
regression  equation  to  predict  accident  rates;  (2)  compare  several  hazard  indices 
and  sufficiency  rating  equations;  and  (3)  explore  the  use  of  joint  study  or  a  limited 
diagnostic  approach. 

The  four  separate  studies  included  in  this  project  have  shown  or  at  least  indi- 
cated the  following: 

( 1 )  There  is  little  concern  among  local  governmental  agencies  regarding 
the  grade  crossing  situation  in  California  as  it  exists  today. 

(2)  Many  agencies  feel  the  financial  responsibility  for  installation  of  auto- 
matic warning  should  be  borne  by  the  State  or  Federal  government. 

(3)  The  use  of  warrants  or  criteria  to  assist  in  the  installation  of  auto- 
matic warning  is  not  widespread,  although  many  agencies  feel  the  State 
should  adopt  criteria  or  warrants   in  some  form. 

(4)  Local  agency  engineers  responded  that  average  daily  vehicular  traffic, 
daily  train  traffic,  comer  visibility,  vehicular  and  train  speed,  in  that 
order,  are  the  most  important  physical  characteristics  to  be  considered 
when   contemplating  a   grade   crossing   warning  improvement. 

(5)  Responses  to  the  questionnaire  ranged  between  criticism  of  the  "dicta- 
torial and  seemingly  arbitrary  way  in  which  the  Commission  staff 
administers  the  program"  to  praise  for  the  grade  crossing  program  and 
a  desire  for  the  retention  of  the  informal  manner  as  presently  pursued 
by  the  Commission  staff. 

(6)  Vehicle-train  accidents  and  casualties  between  1965  and  1972  were 
reduced  by  41%. 

(7)  The  1,552  locations  examined  experienced  a  69%  reduction  in  the 
number  of  vehicle-train  accidents  per  year,  an  86%  reduction  in  deaths 
and  an  80%  reduction  in  the  number  of  injuries  per  crossing  year  after 
the  installation  of  automatic  warning  devices. 


260      Bulletin    655 — American    Railway    Engineering    Association 


(8)  Due  to  their  ability  to  seize  the  attention  of  approaching  motorists, 
both  flashing-light  signals  and  flashing  lights  with  automatic  gates 
ofi^er  the  ability  to  drastically  reduce  the  number  of  vehicle-train  acci- 
dents and  related  casualties. 

(9)  Keeping  in  mind  severely  limited  functional  definitions,  urban  grade 
crossings  bear  significantly  higher  vehicle-train  accident  rates  than 
rural  crossings  do,  and  are  less  affected  by  the  installation  of  auto- 
matic signals  in  terms  of  accident  reduction. 

( 10 )  Automatic  warning  has  its  limitations,  but  will  go  a  long  way  toward 
the  elimination  of  vehicle-train  accidents  if  combined  with  good  driver 
judgment. 

(11)  The  benefits  enjoyed  from  the  installation  of  automatic  warning  come 
at  the  expense  of  significant  public  and  private  investment,  the  cost  of 
installing  flashing  lights  averaging  $8,919  and  automatic  gates  $18,682 
over  the  1966  to  1973  period. 

( 12 )  By  1973,  the  average  cost  of  installing  flashing  lights  and  automatic 
gates  had  risen  to  $10,671  and  $23,534,  respectively. 

(13)  Some  factors  which  appear  to  affect  the  installation  cost  of  automatic 
warning  include  the  geometries  and  physical  conditions  of  the  cross- 
ing, the  type  of  device  installed,  the  proximity  of  adjacent  grade  cross- 
ings protected  by  automatic  devices,  the  complexity  and  sophistication 
of  track  circuitry  required,  and  finally,  the  railroad  involved. 

(14)  In  addition  to  the  installation  cost,  automatic  warning  requires  signifi- 
cant periodic  maintenance.  For  the  year  1972,  using  a  $30  per  relative 
unit  cost,  this  amounted  to  $456  average  at  crossings  protected  by 
flashing  lights  and  $949  at  crossings  protected  by  automatic  gates. 

( 15 )  Large  volumes  of  research  material  are  presently  available  concerning 
methods  of  determining  urgency  or  priority  of  warning  improvement 
of  railroad  crossings. 

( 16 )  No  universal  agreement  has  been  reached  between  the  interested 
parties  on  the  conclusions  of  the  past  studies,  and  the  actual  methods 
of  approach  from  hazard  index  equations  and  sufficiency  ratings  to 
predictive  equations  resulting  from  regression  analyses  have  come 
under  attack. 

(17)  The  attempt  to  design  a  regression  analysis  approach  to  predict  future 
accident  rates  from  simultaneous  combinations  of  several  independent 
variables  did  not  prove  fruitful.  It  is  the  staff's  opinion  that  this  is  due 
to  the  lack  of  accurate  data  over  the  study  period  and  the  small 
sample  size  because  of  the  low  incidence  of  vehicle-train  accidents. 

(18)  Hazard  index  and  sufficiency  rating  equations  generally  address  them- 
selves to  improvement  priorities  and  not  to  the  most  efficient  type  of 
warning  device. 

( 19 )  Due  to  the  multiplicity  of  characteristics  found  in  California's  trans- 
portation network,  it  is  the  Commission  staff's  position  that  single  equa- 
tions cannot  be  adopted  with  good  conscience  on  a  statewide  basis. 

(20)  The  method  favored  by  the  study  staff  incorporates  the  expertise  of  all 
parties  involved,  and  is  based  upon  the  joint  recommendations  of  rail- 
road, local  agency,  and  Commission  engineers.  The  limited  diagnostic 


Highways 261 

method  is  dependent  upon  accurate,  complete,  up-to-date  information 
on  each  crossing  within  a  jurisdiction  and  is  adaptable  to  any  number 
of  computational  priority  detemiinations. 
(21)  The  key  word  is  cooperation  backed  by  a  genuine  realization  of  the 
needs  and  constraints  of  the  parties  involved.  Any  method  or  set  of 
warrants,  or  criteria,  used  to  assist  in  determining  grade  crossing 
warning  improvements  will  run  into  difficulty  for  the  simple  reason 
that  three  separate  and  distinct  organizations  are  involved,  each  with 
its  own  needs,  constraints  and  responsibilities.  To  encourage  participa- 
tion, any  method  adopted  must  remain  flexible  and  receptive  to  all 
parties  concerned. 

Proceedings,    1974   National  Conference  on  Railroad-Highway  Crossing 
Safety,  Sponsored  by  U.S.  Deft,  of  Transportation,  August  19-22,  1974. 

The  report  contains  many  brief  articles  on  railroad-highway  crossing  safety  by 
practitioners  from  all  parts  of  the  United  States.  The  contents  are  best  summarized 
briefly  by  a  listing  of  the  tides  of  these  articles. 

Partners   in   Railroad-Highway   Grade   Crossing   Improxement  Programs 

Estabhshing  a  Grade  Crossing  Safety  Program 

Partners  in  Improvement  and  Establishing  a  Crossing  Safety  Program 

New  Approaches  to  Program  Management 

Establishing  the  Program  Mix 

Urban  Railroad  Relocation 

Research  and  New  Developments 

National  Crossing  Inventory  and  Numbering 

Proposed   National   Railroad-Highway  Crossing  Inventory 

Accident  and  Accident  Severity  Prediction  Equations 

New  Passive  Devices   (Pooled  Fund  Research  Project) 

In-\'ehicle  Warning  Systems  for  Railroad  Grade  Crossing  Applications 

Model  for  Evaluation  of  Alternative  Grade  Crossing  Resources 

Rail  Safety/Grade  Crossing  Warning  Research  Program 

"Railroad-Highway  Vehicular  Movement  Warning  Devices  at  Grade 

Crossings,"   IEEE   Transactions   on   Industry  Applications,   Vol. 

IA-11,  No.   2,   March-April   1975,   Paul  Longrigg. 

The  abstract  of  this  paper  is  as  follows: 

"Railroad  operations  have  for  many  years  been  plagued  with  poor  safety  per- 
formance at  grade  crossings.  Many  lives  are  lost  each  year  in  accidents  at  crossings, 
to  say  nothing  of  costly  injuries  and  property  damage  sustained.  The  situation  has 
gotten  worse  with  the  adxent  of  soundproofed  cars,  being  driven  at  high  speed  in 
c-onditions  of  poor  visibility.  Clearly,  then,  some  improved  method  of  warning 
motorists  as  they  approach  a  grade  crossing  is  needed.  Analysis  of  a  critical  en- 
counter between  a  road  veliicle  and  a  locomotive  reveal  that  the  presently  used 
equipment  is  inadequate  to  meet  the  needs  of  present-day  high-speed  vehicles.  A 
system  of  vehicular  mo\ement  warning  devices  is  described  in  this  paper  that  might 
improve  to  some  extent  die  safety  of  grade  crossing  operations.  Two  methods  are 
detailed.    One   involves   static   directional   sonic   devices   positioned   at   the   crossing; 


262      Bulletin    655 — American    Railway    Engineering    Association 

warning  activation  is  made  on  a  real-time  closing  velocity  determination.  The  other 
system  employs  a  special  variety  of  cattle-guard  in  the  roadway,  to  issue  a  tactile 
warning.  Both  systems  are  designed  to  give  adequate  warning  to  a  motorist  in  a 
critical  encounter  situation  as  he  approaches  the  crossing  with  a  convergent  loco- 
motive on  the  track(s).  A  bonus  feature  in  die  use  of  selectively  activated  static 
directional  sound  warning  sources  would  be  the  curtailment  of  urban  noise  levels, 
where  trains  presently  use  the  mobile  audible  source  to  issue  warnings." 

FrasT   Year   Review:    Protection   and   Advance   Warning   Signs   at   Railroad- 
Highway   Grade   Crossings,    Minnesota   Highway   Department, 
St.  Paul,  Minnesota,  December  1974 

This  brief  report  summarizes  the  condition  of  the  signs  and  the  accidents  at 
grade  crossings  on  two  Burlington  Northern  lines  where  new  or  improved  existing 
protection  signs  and  advance  warning  signs  were  installed  in  1973.  The  findings 
were  that  7.4%  of  the  signs  had  been  vandalized  (gunshot  damage)  in  tlie  first 
year  although  some  of  these  were  still  satisfactory  for  use.  Thirteen  of  580  signs 
were  missing  and  seven  others  were  in  need  of  replacement  or  re-erection. 

A  comparison  of  accidents  during  the  year  with  accidents  during  previous  pe- 
riods is  also  made.  No  conclusions,  however,  could  be  reached  as  the  after-period 
number  of  accidents  were  so  few. 

RESEARCH  IN  PROGRESS 

Considerable  research  and  implementation  continued  in  the  area  of  railroad- 
highway  grade  crossing  safety.  The  Norfolk  &  Western  Railway  reports  two  new 
studies  on  passive  signing  in  Ohio  using  yellow  crossbucks  with  black  border  with 
an  auxiliary  information  sign,  "Look  for  Train,"  also  being  used  in  one  of  the 
studies. 

The  State  of  Florida  is  carrying  out  the  mandate  of  legislation  effective  July  1, 
1972,  which  placed  regulatory  authority  over  public  rail-highway  crossings  in  the 
Department  of  Transportation  and  directed  that  a  program  be  adopted  which  would 
eliminate  hazards  at  such  crossings.  A  five-year  program  for  warning  devices  has 
been  adopted  with  completion  in  1980.  A  total  of  2,991  crossings  are  to  be 
signalized. 

The  Lieutenant  Governor's  Conference  at  its  meeting  in  1974  adopted  the 
following  Resolution: 

WHEREAS,  the  rail-highway  grade  crossing  is  one  of  the  most  critical  areas 
of  traffic  accidents  in  the  nation,  involving  7,000  injuries  and  1,500  deaths 
annually  on  our  streets,  roads  and  highways;  and, 

WHEREAS,  accidents  at  dangerous  crossings  can  be  completely  eliminated; 
and, 

WHEREAS,  there  is  an  urgent  need  to  afford  relief  to  the  environment  and 
to  avoid  the  economic  loss  to  society  from  traffic  delays  at  rail-highway  grade 
crossings  in  boda  urban  and  rural  areas; 

BE  IT  RESOLVED,  that  the  Congress  is  requested  to  appropriate  sufficient 
funds  for  mandatory  use  to  eliminate  hazardous  rail-highway  grade  crossings 
both  on  and  off  the  Federal-aid  system  by  constructing  overpasses  and  under- 
passes, relocating  streets  or  highways  to  eliminate  grade  crossings  and  clos- 
ing unnecessary  grade  crossings. 


Highways  263 


CONCLUSION 


The  availabiUty  of  funds  under  the  1973  Safety  Act  passed  by  Congress  em- 
phasized the  importance  of  impro\ing  safety  at  railroad-highway  grade  crossings 
and  provided  funds  for  initiation  of  such  improvements.  Although  the  State  high- 
way departments  appeared  to  be  slow  in  initiating  such  a  program,  there  are  clear 
indications  that  effective  programs  are  being  developed  and  that  many  improve- 
ments will  be  made.  It  should  be  emphasized,  however,  that,  as  Georgia  officials 
recently  pointed  out,  the  funds  allocated  for  1974-75-76  will  only  permit  improve- 
ment of  about  5%  of  the  total  grade  crossings  in  that  State.  Obviously  much  addi- 
tional work  is  required. 

In  \ie\v  of  these  facts  and  the  growing  activity  in  the  grade  crossing  field,  it 
is  recommended  that  the  assignment  of  this  subcommittee  be  continued  as  it  cur- 
rently e.xists. 


Report  on  Assignment  5 

Study  of  Motor  Vehicle  Codes  and 
Drivers'   Licensing   Practices 

A.  O.  Kruse  (chairman,  subcommitiee),  H.  W.  Barnes,  J.  M.  Bates,  J.  P.  Bolling, 
W.  B.  Calder,  a.  L.  Carpenter,  L.  T.  Cerny,  C.  A.  Christensen,  M.  D. 
Kenyox,  R.  A.  Mather,  G.  U.  Mentjes,  J.  E.  Reynolds,  P.  L.  Sehnert,  P.  A. 
Shuster,  J.  R.  Summers,  R.  F.  Spars,  H.  J.  Wilkins,  H.  L.  Woltman. 

In  January  of  1975  >our  committee  sent  letters  to  the  Governor's  safety  repre- 
sentatives of  all  of  tlie  States  and  Territories  forwarding  a  copy  of  a  model  section 
entitled,  "Railroad  Grade  Crossing  Information  for  Driver  License  Manuals." 

Replies  were  recei\ed  from  19  States,  the  District  of  Columbia  and  three  Terri- 
tories. All  replies  indicated  tliat  faxorable  consideration  \\ould  be  given  to  including 
the  information  in  future  editions  of  the  States'  drivers'  manuals  wliere  this  infor- 
mation is  not  now  a  part  of  the  manual. 

The  committee  plans  to  make  furtlier  contact  with  those  States  \\  hich  have  not 
responded. 

This  is  a  progress  report  submitted  as  infonnation. 


264      Bulletin    655 — American    Railway    Engineering   Association 
Report  on   Assignment  8 

Investigate  Uses  and  Types  of  Rumble  Strips  and  Their 

Adaptability  for  Approaches  to  Highway-Railway 

Grade  Crossings 

R.  E.  Skinnek  {chairman,  subcommittee),  W.  B.  Caldeh,  L.  T.  Cerny,  C.  A. 
Christensen,  R.  a.  Downey,  L.  L.  George,  C.  I.  Hahtsell,  J.  C.  Miller, 
G.  S.  MuNRO,  R.  H.  Patterson,  F.  E.  Rosencranz,  P.  L.  Sehnert,  P.  A. 
Shuster,  W.  E.  Webster,  Jr.,  H.  J.  Wilkins,  C.  H.  Worboys. 

The  use  of  "rumble  strips"  as  a  traffic  control  device  continues  to  be  a  subject 
of  interest  to  many  people  in  the  highway,  academic  and  railroad  fields.  As  evidence 
of  this  interest,  tlie  following  is  a  partial  list  of  a  number  of  publications  related 
to  this  subject. 

1.  "Effect  of  Rumble  Strips  on  Traffic  Control  and  Driver  Behavior,"  M.  L. 
Kermit  and  T.  C.  Hein,  Highway  Research  Board  Proceedings,  Vol.  41, 
1962,  pp  469-482. 

2.  "Rumble  Strips  at  Hazardous  Locations,"  Better  Roads,  Vol.  35,  No.  1, 
Jan.  1964,  pp  16-21. 

3.  "Effect  of  Rumble  Strips  at  Rural  Stop  Locations  on  Traffic  Operation," 
R.  D.  Owens,  Highway  Research  Record,  170,  1967,  pp  35-55. 

A  comprehensive  investigation  of  the  influence  of  rumble  strips  on  traffic 
operations  at  rural  stop  locations  showed  that  a  reduction  in  traffic  speed, 
better  stop  sign  observance  and  a  decreasing  trend  in  accidents  were 
obtained. 

4.  "Rumble  Strips  Used  as  a  Traffic  Control  Device,"  Highway  Focus, 
Vol.  4,  No.  3,  1972,  pp  35^1. 

Twenty-Three  experimental  rumble  strips  used  on  approaches  to  nine 
intersections  to  give  audible  warning  of  dangers  ahead.  Three  different 
Rumble  Strip  configurations  were  used  and  a  before  and  after  accident 
survey  showed  tliat  rumble  strips  can  be  used  as  a  temporary  method 
of  warning  motorists.  They  are  of  little  value  as  permanent  installations. 

5.  "Use  of  a  Rumble  Strip  to  Reduce  Maintenance  and  Increase  Driving 
Safety,"  R.  Gaboon,  Highway  Research  Board,  Special  Report  107,  1970, 
pp  89-98. 

An  experiment  to  design  recessed  rumble  strips  to  give  the  same  effect 
as  raised  markers.  These  recessed  rumble  strips  can  be  used  in  areas 
where   snow  plows   are  operated. 

6.  "Use  of  Rumble  Strips  to  Reduce  Maintenance  and  Increase  Driving 
Safety,"  K.  D.  Fairmont,  Utah  State  Department  of  Highways,  Interim 
Report  1968. 

7.  "Development  of  an  Effective  Rumble  Strip  Pattern,"  W.  R.  Belles, 
Traffic  Engineering,  Vol.  37,  No.  7,  1969,  pp  22-25. 

The  type,  purpose  and  action  of  various  itimble  strips  installed  in  the 
various  states  are  described.  The  problems  associated  with  an  experimental 
rumble  installation  on  durability  and  eftectivness  in  reducing  accidents 
are  also  discussed. 


Highways 265 

8.  "Rumble  Ships  Revisited,"  M.  L.  Kemiit,  Traffic  Engineering,  Vol.  38, 
No.  5,  1968,  pp  26-30L 

Accident  figures  before  and  after  the  installation  of  rumble  strips. 

9.  "In  Further  Support  of  Rumble  Strips,"  D.  W.  Hoyt,  Traffic  Engineering. 
Discusses  accident  reduction  at  nine  rumble  strip  installations  in  Illinois 
and  presents  pertinent  data  in  support  of  this  highway  feature  as  an 
effective   safety   device. 

10.  "Rumble   Strips  for  Safety,"   G.   J.   Lindman,   Highway  Focus. 

Some  traffic  control  devices  become  so  familiar  tliat  they  do  not  register 
in  a  driver's  mind,  while  monotonous  roads  can  lead  a  driver  into  a  semi- 
conscious state.  Rumble  strips  can  correct  this  problem  by  alerting  a 
driver  tlirough  an  audible  noise  and  vibration  through  the  steering  wheel. 
Accident   data   before    and   after   installation    are   presented. 

11.  "Grooved  Rumble  Strips  as  a  Traffic  Control  Device  in  Pennsylvania," 
R.  W.  Taylor,  A  Thesis  in  Civil  Engineering,  November,  1974,  Pennsyl- 
vania State  University,  Graduate  School,  Department  of  Civil  Engineering. 
A  conclusion  is  drawn  that  grooved  rumble  strips  are  effective  in  reducing 
accidents,  especially  in  concrete  pavements.  The  writer,  however,  sug- 
gests rumble  strips  be  used  as  an  interim  measure  (three  years)  until 
a  more  lasting  design  change  can  be  incorporated,  for  example,  traffic 
signal  installation. 

This  is  a  progress  report  submitted  as  information  with  tlie  recommendation 
that  this  assignment  be  continued  in  order  that  further  information  can  be  developed 
and  reported  to  the  Association. 


266      Bulletin    655 — American    Railway    Engineering    Association 

Report  on  Assignment  9 

Study  of  Public  Pedestrian  Crossings 

J.  L.  Whitmeyer  (chairman,  subcommittee),  W.  W.  Allen,  W.  B.  Calder,  A.  L. 
Carpenter,  L.  T.  Cerny,  C.  A.  Christensen,  J.  W.  Cruikshank,  T.  P.  Cun- 
ningham, F.  Daugherty,  H.  D.  Hahn,  C.  I.  Hartsell,  Wm.  J.  Hedley,  D.  P. 
Insana,  R.  F.  MacDonald,  G.  U.  Mentjes,  J.  C.  Miller,  J.  E.  Spangler, 
R.  F.  Spars,  D.  Veitch,  C.  H.  Worboys. 

Pedestrian  grade  crossings  are  an  important  safety  issue  to  both  the  railroads 
and  public  jurisdictions.  Although  relatively  few  such  crossings  exist  as  compared  to 
vehicular  grade  crossings,  which  pedestrians  also  use,  increasing  attention  is  being 
directed  to  improve  site  conditions  and  warnings  for  pedestrian  use. 

Unique  signs  and  automatic  warning  signals  for  pedestrian  crossings  have  been 
developed  in  three  states  (see  accompanying  appendices).  These  signs  and  devices 
closely  follow  the  pattern  of  standards  found  in  die  Manual  on  Uniform  Traffic  Con- 
trol Devices  relating  to  at-grade  railroad  crossings.  Although  standard  railroad  type 
flashing  signals,  gates  and  bells  are  in  use  at  some  crossings,  variations  range  from 
a  single  flashing-light  signal  with  one  red  light  in  each  direction  to  a  vertical  pair 
of  flashing  yellow  lights  and  sign.  A  few  signals  are  fitted  with  the  larger  12-inch 
roundels  for  maximum  light  distribution.  The  automatic  bell  continues  to  be  an 
eftective  audible  warning  to  pedestrians,  whetiier  used  alone  or  in  conjunction  with 
lights.  Railroads  favor  signs  and  signal  devices  which  are  stock  items  for  simplified 
maintenance  and  economic  reasons. 

Of  growing  importance  and  concern  are  the  "bikeway"  crossing  proposals 
resulting  from  recent  legislation.  A  California  city  is  actively  considering  the  adop- 
tion of  standards  to  cover  at-grade  bicycle  crossings  and  pathways  on  railroad  prop- 
erty. Their  proposal  calls  for  the  use  of  one  red  flashing-light  signal  with  back 
light  and  bell  at  each  crossing  to  include  a  sign  to  read  "BICYCLES  ONLY,"  similar 
to  the  State's  standard  pedestrian  sign. 

Railroad  opposition  to  pedestrian  and  bicycle  crossings  is  often  overruled  by 
State  authority.  A  recent  Wisconsin  order  specified  a  crossing  should  be  8  ft  wide, 
composed  of  black  top  widi  a  flange  plank,  provided  with  cross  bucks,  arterial 
"STOP"  signs  and  advance  warning  signs.  The  city  was  obligated  to  remove  vege- 
tation in  the  immediate  vicinity  of  the  crossing.  Subsequently,  the  railroad  granted 
an  easement  to  the  city  for  the  public  bicycle  trail  crossing  cross  its  right-of-way. 

Conversely,  cooperation  between  a  railroad  and  a  public  agency  often  results  in 
a  negotiated  license  agreement,  and  can  result  in  a  private  crossing  under  control 
of  the  railroad  with  the  city  indemnifying  the  railroad  through  public  liability  and 
property  damage  insurance  naming  the  city  and  railroad  as  co-insured. 

A  California  committee  composed  of  representatives  from  the  railroads,  cities. 
State  and  Commission  is  actively  engaged  in  a  study  of  bicycle  crossings  with  par- 
ticular emphasis  on  probable  need  for  bikeway  crossings  of  railroads  separate  from 
highway  crossing,  the  type  of  crossing  construction  which  should  be  considered, 
possible  use  of  dismount  barriers  and  need  for  automatic  warning  devices.  The  report 
is  expected  to  be  available  in  late  1976. 

This  report  is  submitted  as  information  with  recommendation  that  the  subject 
be  continued. 


Highways 


267 


Appendix  A 


California   Public  Utilities  Commission 

PEDESTRIAN  RAILROAD   GRADE  CROSSING   SIGN 

- 

* 18"     * 

■ 

r  r 

RAILROAD 

2" 

R>   /r 

3" 
t 

30" 

/xx\ 

1 

\y         x/ 

1 

CROSSING 

T 
2" 

PEDESTRIANS 

iV 

' 

ONLY 

t                } 

Black  Lettering   on  Whit 
Reflectorized  Silver  Ea 

e   or 
ckground 

268      Bulletin    655— American    Railway    Engineering   Association 

Appendix  B 

PEDESTRIAN  CROSSING  PROTECTION 
Flashing-light  Type 


Approximately 
8  feet 


& 


Crossing  Bell 


Pedestrian  Railroad 
Grade  Crossing  Sign 


4  inch  Pipe  Post 


Highways 


269 


Appendix  C 

RECOMMENDED    BY   TRAFFIC   ENGINEERING   DIVISION, 
CITY    OF   CHESAPEAKE,    VIRGINIA 

Pedesti'ian  Railroad  Grade  Crosslnp;  Sign 


Yellow 
Black  - 


Standard  Va.  Depv. 
of  Hwy.   Sign  W-$2-A 


?"  Red"  Lenses 
Flasher 


\      I 


PEDESTRIANS 
ONLY    " 

STOPIZ^ 

WHEN    FLASHING 


U2' 


Red  Letteiing  on  White  Background 


270      Bulletin    655 — American    Railway    Engineering   Association 


Appendix  D 


7^ 

^SIDEWALK 


V^ 


Public   Utility   Commissioner  of  Oregon,  Railroad  Division,  Standard  No.  2P 
Pedestrian  Flashing  Light  Signal    (Preliminary). 


Highways 


271 


Appendix  E 


OlirAR^fr-ENT    or   PUBLIC  WORKS 

BUREAU  OF  ENGINEERING 

CITY  OF   DE3   MCuNES,  IOWA 


Project:    BICYCLE      TRAILS 


-J 


WHITE 
ON  R£0 


BLACK 
ON    WHITE  V 


■^ 


r 


PRIVATE 

RJtR 


CROSSING 
V J 


Report  of  Committee   11 — Engineering  Records  and 
Property  Accounting 


R.  D.  Igou,  Chairman 
L.  F.  Grabowski, 

Vice  Chairman 
G.   R.   Gallagher, 

Secretary 

M.    F.    McCORCLE 


p. 

G.  McDermott 

w 

,  C.  Kanan 

R. 

L.  Ealy 

A. 

P.  Hammond,  Jr, 

C. 

J.  McDonald 

C. 

E.  Bynane 

J. 

C.    KiRCHEN 

F. 

B.  Baldwin  (E) 

P. 

J.   Beyer,  Jr. 

J. 

M.  Bourne 

W 

.  F.  Burt 

R. 

H.  Campbell 

J. 

R.  Cressman 

R. 

M.  Davis 

C. 

R.    DOLAN 

W 

.  V.  Eller 

L. 

D.  Farrar 

J. 

R.  Geary 

C. 

C.  Haire  (E) 

M 

.  J.  Hebert 

P. 

J.   Hendricksen 

E. 

H.  Hofmann 

P. 

R.  Holmes 

J. 

J.  Hoolahan 

L. 

W.  Howard 

x\.  J.  Hull,  Jr. 
G.  F.  Ingraham 
J.  W.  Kelly 
W.  F.  Liszewski 
R.  W.  Lively 
J.   G.  Maker 
J.  L.  Manthey 

D.  C.  Maris 

J.  C.  McKeague 
S.   Miller,  Jr. 
G.  L.  MuCHOW 
R.  F.  Nelson 
J.  J.  O'Hara 
C.  F.  Olson 
A.  H.  Patterson 
H.  L.  Rest  all  (E) 
J.  M.  Randles 
P.  W.  Roberts 
R.  S.  Shaw,  Jr. 
V.  E.  Smith 

E.  E.  Strickland 
J.  B.  Styles 

T.  A.  Valacak 
H.  R.  Williams 

Committee 


( E )    Member  Emeritus. 

Those    whose    names    are    shown    in    boldface,    in    addition   to    the    chairman,    vice    chairman 
and    secretary,    are    the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association 

Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 
No  revisions  to  report. 

2.  Bibliography. 

Progress  report,  submitted  as  infonnation   piige  274 

3.  Office  and  Drafting  Practices. 

No  report.  AFE  field  inventory  reports  and  as-built  plans  under  study. 

4.  Special  Studies. 

No   report.    Methods   for   preparing  standard  form   AFE   estimates  by 
mechanized  process  under  study. 

5.  Application  of  Data  Processing. 

Final    report    on    simplified    methods    of    allocating    recorded    cost    of 

reported   units,   submitted   as   information    page  274 

6.  Valuation  and  Depreciation. 

Progress  report,  submitted  as  infonnation    page  276 

7.  Revision    and    Interpretation    of    ICC    Accounting    Classifications. 

Progress  report,   submitted  as   information   page  277 

The  Committee  on  Engineering  Records  and  Property  Accounting, 

R.  D.  Icou,  Chairman 


273 


274      Bulletin    655 — American    Railway    Engineering    Association 
Report  on  Assignment  2 

Bibliography 

p.  G.  McDermott  (chairman,  subcommittee),  P.  J.  Beyer,  Jr.,  J.  R.  Chessman, 
C.  R.  DoLAN,  L.  D.  Farrar,  A.  P.  Hammond,  R.  D.  Igou,  J,  L.  Manthey, 
J.  J.  O'Hara,  E.  E.  Strickland,  T.  A.  Valacak. 

Your  committee  submits  the  following  report  of  progress,  presenting  additional 
references  with  annotations. 

OFFICE  PROCEDURE 

Reprographics,  September  1974,  page  13,  "Pre-printed  Overlay  Film  Saves 
Drafting  Time." 

A  forward-looking  manager  will  always  look  for  new  techniques  that  elimi- 
nate repetitive  drafting  chores. 

Modern  Office  Procedures,  June  1974,  "Calculators:  More  for  the  Money;" 
"Jackets:   A  Compact  Way  to  Dress  Up  a  File  System." 

Reprographics,  October  1974,  page  4,  "Reprographics  Techniques — Basic  Pho- 
tofabrication  Terminology." 

A  new  concept  involving  the  production  of  parts  through  the  use  of  chemical 
rather  than  physical  action. 

Reprographics,  October  1974,  page  11,  "Quantity  Production  of  Computerized 
Engineering  Drawings." 

Substitution  of  keyboards  and  lightpens  for  pencils  and  straightedges. 

Modern  Railroads,  February  1975,  pages  51-53.  "What  Price  Money." 

This  article  focuses  on  the  problem  of  how  can  railroads  carry  and  finance  debt 
at  12%  when  they  are  only  earning  4%. 

Progressive  Railroading,  March  1975,  pages  31-34.  "The  Future  of  Engineer- 
ing— M/W  Management." 

The  key  to  understanding  our  present  position  and  future  expectations  is  to 
acknowledge  that  certain  management  techniques  will  be  needed. 


Report  on  Assignment  5 

Application  of  Data  Processing 

A.  P.  Hammond,  Jr.  (co-chairman.  Subcommittee  on  Accounting  Phases),  C.  J. 
McDonald  (co-chairman.  Subcommittee  on  Engineering  Phases),  C.  E.  Bynane, 
R.  H.  Campbell,  C.  R.  Dolan,  R.  L.  Ealy,  W.  V.  Eller,  G.  R.  Gallagher, 
J.  G.  KmcHEN,  W.  F.  LiszEWSKi,  J,  B.  Styles,  H.  R.  Willl^ms. 

METHODS  OF  ALLOCATING  RECORDED  COSTS  TO 
REPORTED  UNITS  IN  THE  TRACK  ACCOUNTS 

The  compilation  of  ledger  values  for  the  track  accounts  is  becoming  increas- 
ingly burdensome.  It  is  recognized  throughout  the  industry,  particularly  by  those 
in  valuation  and  property  accounting  work,  that  steps  must  be  taken  to  develop  a 
less  complicated,  yet  acceptable,  method  of  compiling  these  ledger  values. 


Engineering  Records  and  Property  Accounting 275 

A  simplified  method  of  allocating  costs  recorded  in  the  books  of  accounts  to 
the  reported  track  account  units,  or  so-called  "average  pricing,"  is  considered  to 
be  the  best  solution  to  the  problem.  In  selection  of  a  system,  the  units  to  be  used 
and  the  method  of  developing  the  unit  cost  to  be  applied  will  vary  for  different 
carriers  depending  upon  the  type  and  condition  of  the  basic  record  and  the  detail 
reflected  therein. 

This  report  is  presented  as  a  brief  summary  of  the  answers  to  a  questionnaire 
submitted  to  members   of  the  full  committee. 

1.  The  valuation  section  was  selected  as  die  primary  segment  for  balancing 
costs  and  averaging  unit  costs. 

2.  Most  members  recommend  allocating  average  unit  costs  on  a  weighted 
basis  to  main  tracks,  branch  lines  and  side  tracks  by  valuation  sections 
to  units  in  the  track  accounts. 

3.  Nearly  all  the  members  responding  would  compile  actual  units  of  Ac- 
count 3,  Grading,  for  ledger  \alue  puiposes  and  several  would  do  the 
same  for  Account  11,  Ballast,  due  to  the  wide  variation  used  in  con- 
struction. The  majority  of  the  members  would  consolidate  units  by  rail 
pattern  weights  or  by  homogenous  rail  groups  for  the  other  track  ac- 
counts. Most  carriers  who  maintain  detailed  track  records  would  continue 
to  use  actual  recorded  quantities  in  allocating  average  unit  costs  to  de- 
velop ledger  values. 

4.  Establishing  units  for  controlling  averages  in  the  track  accounts  other 
than  Account  10,  Other  Track  Material,  poses  little  difficulty.  The  same 
results  can  be  obtained  whether  units  such  as  cubic  yard,  each,  mbm., 
cwt.,  gross  ton,  net  ton,  track  foot,  track  mile,  etc.  .  .  .  ,  or  combinations 
such  as  gross  ton  per  track  mile  are  used.  Account  10,  Otlier  Track  Ma- 
terial, has  numerous  minor  units  currently  recorded  in  the  property  rec- 
ords, and  most  members  recommend  consolidating  these  units  into  a  few 
major  units  for  controlling  averages.   Three  possible  units  are: 

(a)  Rail  displacement  materials   .   .   .  unit  each  or  cwt   (includes  frogs, 
swatches,   crossing  frogs,   etc.). 

(b)  Track  fastenings   .   .    .   unit  each  or  cwt    (includes  joints,   tie  plates, 

anchors,  etc.). 

(c)  Other  items   .   .    .   unit  each  or  cwt    (includes   bumping  posts,   rail 
flange  lubricators,  etc.). 

In  conclusion  the  committee  believes  that  tiiere  is  a  need  for  a  pricing  system 
to  be  developed  entailing  the  restructuring  of  valuation,  field  and  accounting  re- 
porting. These  reports  must  interface  with  the  computer  in  order  to  produce  the 
required  records,  controls  and  reports. 


276      Bulletin    655 — American    Railway    Engineering   Association 

Report  on  Assignment  6 

Valuation  and  Depreciation 

C.  E.  Bynane  (cluiirnuin,  subcommittee),  J.  R.  Chessman,  W.  V.  Eller,  G.  R. 
Gallagher,  L.  F.  Grabowski,  M.  J.  Hebert,  P.  J.  Hendricksen,  E.  H. 
HoFMANN,  P.  R.  Holmes,  N.  J.  Hull,  Jr.,  R.  D.  Igou,  J.  G.  Maher,  D.  C. 
Maris,  P.  G.  McDermott,  C.  J.  McDonald,  S.  Miller,  Jr.,  J.  B.  Styles, 
H.  R.  Williams. 

(A)  CURRENT  DEVELOPMENTS  IN  CONNECTION  WITH 
REGULATORY  BODIES  AND  COURTS 

ICC  Bureau  of  Accounts 

During  the  fiscal  year  1975  the  Commission  continued  its  five-year  cyclical 
review  of  equipment  depreciation  and  the  Accounting  and  Valuation  Board  issued 
32  railroad  equipment  depreciation  orders.  Depreciation  analyses  of  all  road  property 
accounts  for  all  eligible  Class  I  railroads  were  completed  during  fiscal  1975  and  51 
railroad   road   property  depreciation  orders  were   issued. 

The  road  property  depreciation  analyses  of  all  eligible  Class  I  railroads  reinforced 
the  tentative  findings  of  tlie  fiscal  1974  study  for  14  Class  I  carriers  in  that  the 
results  were  in  line  with  expectations,  and  tlie  anticipated  large  deficiency  in  past 
accrued  depreciation  has  not  developed.  As  mentioned  in  last  year's  report  of  this 
subcommittee,  problems  witli  salvage  determination  and  experience  were  particularly 
troublesome  in  the  deprication  analysis  and  the  chief  of  tlie  Depreciation  Branch  has 
advised  the  chairman  of  this  subcommittee  that  he  would  welcome  input  from  Com- 
mittee 11  members  on  their  views  with  respect  to  a  more  satisfactory  method  of 
accounting  for  salvage  proceeds. 

As  information,  an  Interim  Coordinator's  report  on  Ex  Parte  271,  Net  Investment 
— Railroad  Rate  Base  and  Rate  of  Return,  by  Commissioner  Dale  W.  Hardin  was 
issued  on  March  3,  1975,  345  ICC  410,  and  summarizes  the  findings  of  the  prelimi- 
nary analysis  of  the  1974  road  property  depreciation  study  for  the  14  Class  I  railroads. 
The  report  is  well  wordi  reading,  particularly  with  respect  to  the  discussion  about 
Accounts  3,  5  and  39  (grading,  tunnels  and  subways,  and  public  improvements — 
construction ) . 

Internal  Revenue  Service 

Closely  related  to  the  discussion  about  Accounts  3  and  5  in  the  above-mentioned 
Coordinator's  report  to  the  ICC  is  one  of  the  issues  decided  in  favor  of  the  taxpayer, 
Chesapeake  &  Ohio  Railway  and  affiliated  companies  versus  the  Commissioner  of 
Internal  Revenue,  Docket  Nos.  5904-70,  5646-71.64  TC-No.  35,  filed  June  2,  1975, 
wherein  it  was  decided  that  petitioner's  (C&O)  investment  in  grading  and  tunnel 
bores  had,  as  a  result  of  obsolescence  foreseeable  in  1954,  reasonably  determinable 
useful  lives  such  as  to  entitle  petitioner  to  depreciation  deductions  for  such  invest- 
ment in  tax  years  1954  through  1963. 

In  the  same  decision  there  are  two  other  subjects  treated  and  decided,  one  being 
ratable  depreciation  of  track  structures  based  on  obsolescence  foreseeable  in  1954 
wherein  the  taxpayer's  petition  for  such  deduction  was  denied,  the  other  subject 
being  the  determination  of  the  fair  market  value  of  petitioner's  recovered  reusable 


Engineering  Records  and  Property  Accounting 277 


rail  wherein  the  court  developed  its  version  of  a  compromise  between  the  IRS  and 
petitioner's  versions  which  produced  an  interesting  and  apparently  favorable  result 
for  die  petitioner. 

The   abo\e-nientioned   decision   in   full   is   reconunended  reading  for  everybody 
interested   in   \aluation    and    depreciation. 


Report  on   Assignment  7 

Revisions  and   Interpretations  of  ICC  Accounting 
Classifications 

J,  G.  KmCHEN  (chairman,  subcommittee),  J.  M.  Boubne,  T-  R-  Geaky,  N.  J.  Hull, 
G.  F.  Ingraham,  J.  W.  Kelly,  W.  F.  Lisze\\'ski,  J.  G.  Maher,  D.  C.  Maris, 
P.  G.  McDermott,  J.  McKeague,  S.  Mu-ler,  P.  W.  Roberts,  T.  A.  Valacak. 

This  is  a  progress  report,  presented  as  information,  on  changes  affecting  engi- 
neering records  and  property  accounting  only. 

ICC  Order  No.  32153  (Sub.  No.  5)  with  a  service  date  of  January  22,  1975, 
Accounting  for  Accumulated  Depreciation  on  Improvements  to  Leased  Property, 
establishes  a  new  and  separate  Account  733,  Accrued  Depreciation;  Improvements 
on  Leased  Propert>',  and  transfers  these  amounts  from  Account  785  which  now  is 
Accrued  Liability-;  Leased  Property,  and  will  include  only  the  lessee's  unsetded  liabili- 
ties to  the  lessor.  Eftecti\e  January  1,   1975. 

Notice  of  Proposed  Rulemaking  and  Order  No.  36125  with  a  service  date  of 
April  11,  1975,  Reporting  E.xtraordinary,  Unusual  or  Infrequently  Occurring  Events 
and  Transaction;  Prior  Period  Adjustments;  the  Effects  of  Disposal  of  a  Segment  of 
a  Business.  These  include  instructions  for  clarifying  the  criteria  for  extraordinary 
items,  for  prior  period  adjustments  and  reporting  rules  for  certain  accounting  changes 
and  provides  new  guidelines  for  detennining  materiality.  Also,  definitions  for  a 
segment  of  a  business  and  related  accounting  terms  and  instructions  for  reporting 
the  operating  results  and  gain  or  loss  on  disposal  of  a  segment. 

Notice  of  Proposed  Rulemaking  and  Order  No.  36137  with  a  service  date  of  May 
20,  1975,  Revision  of  Rules  on  Classification  of  Carriers.  This  proposal  would  in- 
crease the  minimum  railway  operating  rexenue  from  $5  to  $10-million  for  Class  I 
carriers  and  establish  time  period  for  qualifying  and  changing  classifications. 

Notice  of  Proposed  Rulemaking  and  Order  No.  36141  with  a  service  date  of 
April  1,  1975,  Corporate  Disclosure  Regidations,  would  require  carriers  to  re\eal 
in  their  annual  reports  details  of  their  parents  and  subsidiaries,  who  votes  dieir 
common  stock,  business  affiliations  of  the  company's  principal  officers  and  executi\  es 
and  details  of  long-  and  short-term  debt  and  financing  lease  arrangements. 


i 

I 


Report  of  Committee   14 — Yards  and  Terminals 


B.  H.  Price,  Chairman 

P.   C.   White, 
Vice  Chairman 

G.  H.   Chabot,  Secretary 

R.  F.  Beck 

H.  L.  Bishop 

J.  F.  Chandler 

H.  B.  Christiansox 

A.    W.    NiEMEYER 

C.  E.  Stoecker 


p.  E.  Van  Cleve 

C.  F.  Intlekofer 

J.  Zaenger 

J.  B.  Kerby 

R.    P.    AiNSLIE 

A.  S.  Krefting  (E) 

M.  J.  Anderson 

W.  L.   Krestinski 

J.  K.  AusT 

C.  J.  Lapinski 

R.  O.  Balsters 

J.  A.  LeMaire 

A.   E.   Blermann 

S.  J.  Levy 

\V.  O.  Boessneck  (E) 

E.  T.  LucEY 

R.  O.   Bradley 

S.  N.  MacIsaac 

R.  E.  Bredberg 

J.  G.  Martin 

H.  E.  Buchanan 

A.  Matthews,  Jr. 

C.  M.   Burnette 

H.  J.  McNally 

H.  P.  Clapp 

R.  E.  Metzger 

M.  K.  Clahk 

C.  H.  Mottier  (E) 

D.  y.  Clayton 

F.  J.  Olsen 

E.  H.  Cook 

W.  L.   Patterson 

A.  Y.  Dasburg 

J.  C.  Pinkston 

F.  D.  Day 

W.  P.  Rybinski 

D.  J.  DeIvernois,  Jr. 

W.  A.  Schoelwer 

P.  P.  Dunavant,  Jr. 

J.  G.  Skeen 

R.    D.    D\TfMAN 

W.  D.  Slater 

V.  H.  Freygang 

E.    SZAKS 

M.  R.  Gruber,  Jr. 

L.    G.    TiEMAN 

H.  L.  Haanes 

J.  N.  Todd  (E) 

J.  N.  Hagen 

A.  J.  Trzeciak 

D.  C.  Hastings 

H.  Watts,  Jr. 

I.  M.  Hawver 

J.  C.  Weiser 

Wm.  J.  Hedley 

C.  C.  Yespelkis 

L.  J.  Held 

J.  R.  Zebrowski 

F.  A.  Hess   (E) 

Committee 

(E)    Member  Emeritus. 

Those    whose    names    are    shown    in    boldface,    in    addition    to    the    chairman,    vice    chairman 
and    secretary,    are    the    subcommittee    chairmen. 

To   the  American   Railway  Engineering  Association: 

Your   committee   reports   on   the   following   subjects: 

B.  Revision  of  Manual. 

The  committee  has  completed  its  work  on  the  revision  of  Chapter  14 
of  the  Manual,  and  properly  voted  on  and  approved  the  revision  by 
letter  ballot.  The  revised  material  is  published  in  Part  I  of  this  Bulletin. 
Revision  of  tlie  glossary,  as  it  pertains  to  Chapter  14,  is  now  in  progress. 

1.  Classification  Yards: 

(a)  Gradients   for  Flat  and  Saucer  Yards. 

Final  report,  submitted  as  information,  with  the  recommendation 

that  it  be  considered  as  possible  future  Manual  material    page  280 

(b)  Yard   and   Terminal   Design   Criteria   to   Decrease   Car   Detention. 

Final  report,   submitted   as   information    page  283 

2.  Bulk  Material  Handling  System,  Collaborating  as  Necessary  or  Desirable 
witli  Committees  6,  8  and  15. 


279 


280      Bulletin    655 — American    Railway    Engineering    Association 

Work  is  progressing  on  this  subject  but  no  report  will  be  available  for 
at  least  a  year.  The  committee  has  expressed  willingness  to  present  an 
illustrated  feature  on  this  subject  at  the  Annual  Technical  Conference 
in  March. 

3.  Terminal  Facilities  for  Handling  Solid  Waste  Material  from  an  Ecology 
Standpoint,  Collaborating  as  Necessary  or  Desirable  with  Committee 
13. 

No  progress  has  been  made  on  this  subject  since  it  was  assigned. 
However,  a  new  subcommittee  chairman  has  been  appointed  and  it  is 
anticipated  tliat  substantial   progress  will  be  made  in  the  next  year. 

4.  Car  Rollability  Research. 

There  has  been  no  activity  concerning  this  subject  pending  further  ad- 
vice and  direction  from  the  Association. 

5.  Trends   in   Intermodal  Facilities. 

Progress  is  being  made  on  this  subject  and  it  is  anticipated  that  the 
subcommittee  will  make  its  report  in   1976. 

6.  Facilities  for  Line  Repair  and  Servicing  of  Diesel  Locomotives,  Col- 
laborating as  Necessary  or  Desirable  witli  Committees  6  and  13. 

A  preliminary  report  has  been  written  and  is  being  revised.  The  report 
on  this  subject  should  be  submitted  to  the  Association  in  1976. 

7.  Yard  System  Design  for  Two-Stage  Switching. 
No  progress  to  report  on  this  subject  at  this  time. 

The   Committee  on  Yards  and  Terminals, 

B.  H.  Price,  Chairman. 


Report  on  Assignment   la 

Gradients  For  Flat  and  Saucer  Yards 

p.  E.  Van  Cleve  (chairman,  subcommittee),  R.  O.  Balsters,  R.  F.  Beck,  R.  E. 
Bredberg,  C.  M.  Burnette,  G.  H.  Chabot,  D.  V.  Clayton,  A.  V.  Dasburg, 
F.  D.  Day,  P.  J.  DeIvernois,  Jr.,  R.  D.  Dykman,  J.  N.  Hagan,  D.  C.  Hastings, 
L.  J.  Held,  F.  A.  Hess,  J.  B.  Kerby,  J.  A.  LeMaire,  B.  H.  Price,  Jr.,  R.  J. 
Samoska,  p.  C.  White. 

This  progress  report  is  submitted  as  infonnation,  for  possible  future  Manual 
material. 

This  report  is  confined  primarily  to  the  "flat"  or  "saucer"  yard,  where  cars  are 
classified  by  the  shuttling  movement  of  the  switch  engine,  with  the  cars  being  "drilled" 
or  "kicked"  to  roll  freely  into  the  classification  tracks.  Not  included  in  the  scope  of 
this  report  are  the  retarder-less  low  hump  yard  or  the  flat  yard  where  cars  are 
shoved  to  rest. 

While  the  flat  and  saucer  yards  (hereafter  referred  to  collectively  as  flat  yards) 
far  outnumber  any  other  type  of  yard  in  use,  apparently  only  a  few  were  constructed 


Yards  and  Terminals  281 


with  gradient  design  as  a  primary  consideration.  In  most  cases,  the  apparent  over- 
riding factors  were  such  things  as  topographical  restraints,  grading  costs,  space 
limitations,  and  conformance  with  fixed  elevations,  such  as  adjoining  main-line  profile 
and  public  grade  crossings. 

An  analysis  of  subcommittee  member  responses  to  this  assignment  indicates 
tliat  during  the  past  decade  or  two  greater  emphasis  has  been  placed  on  designing 
and  building  flat  yards  with  optimmn  gradients  for  switching. 

A  review  of  flat  yards  where  gradient  has  been  a  major  design  factor  indicates 
the  following  preference  for  gradients  in  the  direction  of  switching  ( see  Figure  1 ) : 


-4— E- 


^ 


KI 


•DIRECTION    OF    SWITCHING 


FIGURE  I.    Flat  Yard  for  Single  Direction  Switching 

Segment  A — Switching  Lead  (or  Drill  Track).  Gradient  here  is  not  critical  since 
cars  are  nomially  released  on  or  close  to  the  ladder  ( Segment  B ) .  However,  since 
this  segment  accommodates  constant  bi-directional  movement,  the  gradient  should 
be  relatively  flat,  with  0.00  percent  preferred. 

Segments  B  and  C — Ladder  and  Switch  to  Clearance  Point.  The  preferred 
gradient  is  "slightly"  accelerating,  which  means  that  the  grade  must  descend  suffi- 
ciently to  overcome  rolling  resistances,  including  switch  and  curve  resistance.  The 
preferred  gradients  for  these  segments  range  from  -0.20  percent  to  -0.30  percent, 
although  one  railroad  used  a  0  percent  grade  for  die  ladder,  probably  on  the  premise 
that  cars  would  be  released  near  the  switch  of  their  classification  track. 

Segment  D — Clearance  Point  to  Clearance  Point.  The  preferred  design  gradient 
for  tliis  segment  is  "slightly"  decelerating,  ranging  from  -0.10  percent  to  0.00  percent. 

Segments  E,  F,  G — "Leaving"  End  of  Yard.  Segments  E  and  F  should  have 
sufficient  plus  gradient  to  prevent  roll-outs,  and  thus  minimize  the  need  for  retarders 
or  skates.  The  percent  gradient  selected  is  not  too  important  if  the  yard  is  to  be  used 
only  for  single-direction  switching. 

However,  when  conditions  permit,  it  is  highly  desirable  to  design  a  flat  yard 
for  switching  at  both  ends,  even  when  current  operations  might  not  require  double- 
end  switching.  Thus,  the  flat  yard  for  double-end  switching  would  have  gradients 
G,  F,  and  E,  the  same  as  A,  B,  and  C,  respectively,  and  gradient  D  would  be  eitlier 
level  or  slightly  descending  from  each  end  toward  the  center.  The  yard  profile  would 
resemble  a  saucer. 

Wliile  the  Manual  for  Railway  Engineering  contains  virtually  no  design  infor- 
mation for  flat  yards,  the  engineer  can  and  should  review  the  section  of  the  Manual 
on  hump  classification  yard  design,  as  much  of  this  material  can  be  applied  to  flat 
yard  design.  Having  done  this,  a  summary  of  the  primary  considerations  for  flat 
yard  design  is  as  follows: 


282      Bulletin    655 — American    Railway    Engineering    Association 

1.  Objective 

The  ideal  objective  is  tlie  design  of  a  series  of  gradients  so  that  each  car  will 
roll  to  and  stop  at  the  far  end  of  the  classification  yard,  or  will  roll  to  coupling  at 
an   acceptable   speed.   The   following  objectives   are   the  minimum   to  be  expected: 

(a)  Deliver  cars  having  a  practical  maximum  rolling  resistance  to  the 
clearance  point  under  adverse  weather  conditions. 

(b)  Deliver  cars  of  most  frequently  occurring  rolling  resistance  to  tire  far 
end  of  the  yard,  or  to  some  desired  intermediate  point,  if  block  size  does 
not  require  filling  the  track. 

(c)  Permit  maximum  switching  rate  and  acceptable  coupling  speeds. 

2.  Rolling  Resistance 

The  designer  must  be  familiar  with  car  rollability  and  the  factors  which  con- 
tribute to  rolling  resistance.  The  yard  gradients  must  be  tailored  for  the  prevailing 
climatic  conditions,  including  wind  speed,  wind  direction,  temperature,  rain  and 
snow.  Gradients  must  be  compensated  for  resistances  from  turnouts,  curves,  gage, 
and  possible  track  irregularities. 

3.  Equipment  and  Commodities 

The  designer  should  be  familiar  witli  the  type  of  equipment  to  be  used  and  com- 
modities to  be  handled.  A  predominance  of  roller-bearing  or  non-roller-bearing  cars 
will  affect  gradient  selection.  In  a  yard  where  mostly  empty  cars  or  bulk  commodi- 
ties are  handled,  it  is  possible  that  gradients  can  be  increased,  thus  creating  higher 
impacts,  but  increasing  the  percentage  of  cars  tliat  will  couple. 

4.  Yard  Configuration 

If  possible,  a  track  should  be  designated  for  each  classification  to  be  made. 
However,  it  should  be  remembered  that  a  flat  yard  is  best  suited  to  a  situation 
where  the  number  of  switching  cuts  is  small.  While  fairly  large  volmiies  of  cars 
can  be  handled  in  a  flat  yard,  a  large  number  of  cuts  reduces  its  effectiveness. 

Body  tracks  should  preferably  be  on  tangent  and  of  sufficient  capacity  to  hold 
the  volumes  of  each  classification  under  normal  circumstances. 

Ladders  should  be  designed  to  minimize  distance  to  clearance  point,  and  pro- 
vide maximum  yard  capacity.  Switches  should  be  as  close  together  as  possible  for 
efficient  hand  throwing.  Multiple  frog  angle  ladders  allow  the  designer  to  provide 
a  compact  layout;  however,  when  hand  tlirow  switches  are  used,  the  layout  must 
be  such  that  all  switch  stands  are  on  the  outside  of  tlie  ladder.  Inside  switch  stands 
should  be  used  only  when  push-button  power  switching  is  provided. 

5.  Gradients 

In  a  flat-yard  drilling  operation,  the  car  when  it  is  uncoupled  is  not  unlike  tlie 
car  leaving  a  group  retarder  in  a  hump  yard,  in  that  each  car  has  just  departed  from 
its  last  point  of  human  control.  Hence  the  basic  design  formula  for  the  hump  yard 
from  group  retarder  to  clearance  point  could  be  applied  to  flat  yard  design,  as 
follows: 

Drop  from  uncoupling  point  to  clearance  point  =  SRe  +  ^  C-{-SW  +  a 
where 


Yards  and  Terminals  283 


S  =  Distance  in  feet 
fl,  =  Rolling  resistance  for  easy   rolling  car  expressed   decimally 

A  z:^  Curvature  in  degrees  of  central  angle 

C  =  Curve  resistance  in  feet  of  drop  per  degree  of  central  angle 
Sti;  =  S\vitch  resistance  in  feet 

a  —  Difference  in  \elocity  head  at  clearance  and  velocity  head  at  uncoupHng 
point  for  easy  rolling  cars. 

The   gradients   in  the   body   tracks   must   not  produce   unacceptable   acceleration   of 
easy-rolling  cars. 

6.  Drainage 

The  flat  yard  will  have  a  natural  tendency  to  contain  water,  since  its  profile 
will  usually  take  the  shape  of  a  saucer.  Good  drainage  is  imperative  to  maintain 
good  track  grade,  ahgrmient  and  structure.  In  most  cases,  a  subsurface  drainage 
system  will  be  required,  unless  the  subgrade  is  very  porous. 


Report   on   Assignment    lb 

Yard  and  Terminal  Design  Criteria  to 
Decrease  Car  Detention 

R.  F.  Beck  (chairman,  subcommittee),  R.  P.  Aixslie,  C.  M.  Burnette,  C.  H.  Cil\bot, 
H.  B.  Christiansox,  D.  X.  Claytox,  A.  \'.  Dasburg,  F.  D.  Day,  P.  J.  DeIv^er- 
xois,  Jr.,  J.  X.  Hagax,  D.  C.  Hastings,  F.  A.  Hess,  C.  F.  Ixtlekofer,  J.  B. 
Kerry,  J.  A.  LeMauie,  S.  J.  Levy,  E.  T.  Lucey,  J.  G.  Martix,  H.  J.  McNally, 
W.  L.  Patterson-,  B.  H.  Price,  W.  A.  Schoelwer,  J.  G.  Skeex,  W.  D.  Slater, 
C.  E.   Stoecker,   L.   G.  Tiemax,  H.  Watts,  P.  C.  White,  J.  R.  Zebrowski. 

This  report  is  submitted  as  information,  with  the  recommendation  that  the 
subject  be  discontinued. 

The  basic  fundamentals  of  good  yard  and  terminal  design  have  not  changed 
throughout  the  years.  Newer  operating  and  organization  concepts,  together  with  the 
introduction  of  sophisticated  equipment,  pro\ide  us  with  an  opportunity  to  increase 
operating  efficiency,  thus  decreasing  car  detention  time.  Howexer,  the  basic  funda- 
mentals of  yarding  the  train,  classifxing  tlie  cars  and  departing  die  train  in  the 
minimum  amount  of  time  and  at  the  least  cost  have  not  changed.  Therefore,  the 
criteria  for  yard  and  terminal  design  cannot  concern  itself  solely  with  the  physical 
plant,  but  must  also  include  the  design  of  the  organization  and  die  operating  plan. 
In  other  words,  the  design  criteria  must  be  viewed  as  a  major  system  with  both  the 
designer  and  operator  playing  an  integral  part.  Failure  of  any  one  of  the  many  sub- 
systems can  increase  car  detention  time,  and  tiiis  important  concept  must  be  recog- 
nized by  all  concerned. 

Continuous  new  developments  in  the  data  processing  field,  together  with  newer 
organization  concepts  have  made  possible  computerized,  real-time  car  moxement 
and  information  systems.  Railway  operations  are  a  fertile  field  for  this  new  technology 
and  substantial  progress  can  be  made  in  operating  efficiency,  thus  reducing  cost  and 
at  the  same  time  iiiipro\ing  customer  ser%ice.  Mo\enient  of  cars  through  the  receiv- 
ing, classification,  and  departure  functions  is  an  integral  part  of  such  a  system.  Such 


284      Bulletin    655 — American    Railway    Engineering   Association 

a  system  maintains  a  perpetual  inventory  of  cars  by  track  location  in  which  all  cars 
are  under  the  constant  sui-veillance  of  the  system,  thus  providinji  for  maximum  car 
utilization.  Car  infonnation  and  location  on  a  real-time  and  exception  basis  are 
immediately  available  via  an  increasing  variety  of  output  devices  which  are  an 
indispensable  aid  to  the  planning  process.  Such  systems  also  permit  the  exercise 
of  overall  control  of  yard  and  terminal  operations  and  can  be  made  an  integral  part 
of  a  railroad-wide  management  information  system.  The  key  to  the  success  of  such 
systems  is  the  development  of  a  complete  and  dependable  car  record  as  soon  as 
possible.  This  is  of  paramount  importance  because  such  information  is  vital  to  the 
financial,   statistical,  cost,   traffic,  accounting  and  other  staff  functions. 

The  computer  and  related  interface  equipment  have  made  possible  the  virtual 
complete  automation  of  the  entire  classification  operation.  Automatic  car  identification 
coupled  with  mini-computers  and  other  devices  can  automatically  input  car  infor- 
mation into  the  system.  Thus  the  complete  control  of  receiving,  classification  and 
departure  operations  becomes  but  a  subsystem  of  the  overall  car  movement  and 
information  system. 

The  following  overall  and  specific  criteria  should  be  considered  when  attempting 
to  reduce  car  detention  time.  All  of  the  items  listed  may  or  may  not  bear  on  any 
particular  installation  depending  upon  the  type  of  facility  being  studied.  The  follow- 
ing information  also  directly  relates  to  flat  yards  although  some  modification  of  the 
criteria  may  be  required. 

I.  Determine  Workload  for  the  Terminal 

A.  Forecast  rail  network  transport  demand. 

B.  Estimate  demands  on  the  terminal: 

1.  Number  and  size  of  car  blocks. 

2.  Train  schedules. 

3.  Interchange,   industry,   intermodal  and  other  services. 

II.  Overall   Design   Considerations   Relating  to   Terminal   Operations 

A.   Avoid  interference  between  movements,  minimize  total  car  movement,  and 
optimize   all   transportation   operations: 

1.  Track  and  related  facilities: 

(a)  strategically  located  crossovers,  connections,  leads,  and  tracks, 

(b)  ample    running    tracks    and    escape    routes    for    arriving,    switching, 
classification,    departure,    and   other   movements, 

(c)  dual    hump    tracks    and    scissor    crossovers, 

(d)  remote   control   power  operated  switches,   route  control,  shove  indi- 
cators, and  signaling, 

(e)  track  facilities  for  special  transportation  functions  including  auxiliary, 
local,   through   yards,   etc., 

(f)  sufficient  space  between  tracks  for  yard  lighting,  specialized  equip- 
ment, car  inspection,  and  running  repairs, 

(g)  space  for  expansion, 

(h)   dragging  equipment  and  broken  flange  detectors,  journal  and  track 

oilers, 
(i)    movement  sensors,  automatic  car  identification  and  blue  flag  systems, 
( j )    yard  cleaning  equipment,  switch  heaters,  snow  blowers,  and  related 

snow  removal  equipment. 


Yards  and  Terminals  285 


2.  Ancillary  facilities: 

(a)  lighting   for  safe   and   optiiniiin   night   operations, 

(b)  towers  and  control  facilities  to  monitor  and  manage  operations, 
combined   where   possible,   to   avoid   duplication, 

(c)  comnumication  systems  including  radio,  loudspeakers,  pneumatic 
tube  systems,  digital  displays  and  printouts,  television  and  teletype, 

(d)  roadways,  parking  areas,  drainage,  noise  and  pollution  control, 
sewage   disposal,   water  supply,   fire  protection,  etc., 

(e)  engine  and  caboose  servicing,  car  repair,  car  cleaning,  piggyback, 
refrigerator  servicing  and  other  facilities  at  strategic  locations, 

(f)  crew,  office,  and  miscellaneous  buildings, 

(g)  noise   level   and   other   environmental   considerations. 

3.  Speed   the   movement  of  cars   through  receiving,   classification,   departure 
and  other  terminal  yards  and  tracks: 

(a)  computerized  automatic  humping,  switching,  speed  control,  weighing, 
distance  to  go,  etc., 

(b)  real  time  and  historical  digital  print  and  readouts  of  all  car  move- 
ment  information   required   by   transportation   operation, 

(c)  all   car   movement   information   required   by   other   departments, 

(d)  automatic    trouble-shooting    information. 

4.  Reliable  facilities: 

(a)  easy  to  maintain  facilities,  holding  down  time  to  a  mininunn, 

(b)  level  of  maintenance  to  limit  derailment  and  program  downtime 
of  facilities  based  upon  an  overall  sound  preventive  maintenance 
program, 

(c)  backup  systems  in  important  areas  such  as  power  supply,  com- 
nmnications,    and   computer   systems, 

(d)  safety  and  security  of  operation. 

5.  Trained  personnel  and  the  simplest  operating  procedures  and  equipment. 

B.    Use   two  stage   or  other  forms  of  nudtiple  pass  sorting  wherever: 

1.  The   desired  number  of   blocks   greatly  exceeds  the  number  of  available 
classification  tracks,  or 

2.  Numerous  blocks  are  desired  for  a  train. 

III.  Specific  Design  Considerations  Relating  to  Car  Movement 

A.  Receive  cars   quickly  with  minimum  interference: 

1.  Track   design   to   avoid   interference   between   moves. 

2.  Sufficient  trackage  for  near-peak  requirements. 

3.  Tracks   of  sufficient  capacity  to  avoid  doubling. 

4.  Alignment  and  gradients  to  eliminate  derailments  and   runouts. 

B.  Classify  cars  at  a  maximum  practical  rate  consistent  with  the  overall  trans- 
portation operations: 

1.  Weigh   cars   accurately   and   economically  without   slowing   the   humping 
rate. 

2.  Avoid  catchups  in  the  classification  area: 

(a)  bleed   cars    thoroughly   to    avoid   sticking   brakes, 

(b)  speed  movement  throughout  all  classification  tracks  as  much  as 
possible, 

(c)  multiple   cuts,   where   permissible. 


286      Bulletin    655 — American    Railway    Engineering   Association 

3.  Utilize   the   best   economical   track  arrangements,   gradients,  and  control 
systems   based   upon  AREA  recommendations   taking  into  account: 

(a)  wind,   temperature,   snow,    sleet,   fog,   moisture,   storms, 

(b)  type   of   tiaific   including  long,   short,   empty   and  loaded  cars, 

(c)  range  of  rolling  resistance, 

(d)  predominance  of  resistance  for  type  of  cars  handled, 

(e)  easy  separation  of  cuts, 

(f)  minimum  distances  between  crest  and  clearance  points,  utilizing 
lap  switches, 

(g)  capacity   of  retarders   to   handle   design  parameters, 
(h)  capacity  of  control  system  and  components, 

(i)    track  cmvature, 

(])    starting  cars  that  have  been  stopped  in  the  retarders. 

4.  Release  cars  from  retarders  at  speeds  consistent  with  minimum  car  and 
lading  damage: 

(a)  use  of  decelerating  gradients  immediately  beyond  the  group  re- 
tarders with  as  short  a  switching  length  as  possible  with  maximum 
turnout  speeds, 

(b)  design  for  as  low  a  curvature  as  possible  togetlier  with  the  optimum 
number   of   tracks  per   group   consistent  with  the  foregoing, 

(c)  provide  non-accelerating  gradients  on  tangent  track  for  preponderance 
of  cars  humped, 

(d)  provide  devices  to  assist  cars  around  curves  to  help  reduce  the 
range  of  rolling  resistance, 

(e)  deliver    cars    to    clearance    point    at    the    most   advantageous    speed, 

(f)  design  for  optimum  track  length  in  classification  yard  consistent 
with  operating  requirement  keeping  in  mind  the  range  of  rolling 
resistance. 

C.  Provide  for  as  continuous  a  classification  operation  as  practical  by  considering: 

1.  Interference   between  road,   yard,   and  hump  engines. 

2.  Travel  time  between  receiving  yards  and  the  hmiip  lead. 

3.  Time  between  successive  cuts  on  the  hump  lead. 

4.  Escape  routes  for  trimmers  and  other  moves  from  the  hump  end. 

5.  Caboosing    time    tlirough    efficient   track   layout   and   servicing   facilities. 

D.  Reduce  hump   engine   trimming  time   to   an  absolute  minimum: 

1.  Classify  cars  to  die  correct  track. 

2.  Minimize   catchups   by  correct  design  and  control  systems. 

3.  Assign  classifications  to  serve  tlie  maximum  spread  of  cars  being  humped. 

4.  Provide  an  optimum  number  of  classification  tracks. 

E.  Remove  cars  and  trains  from  the  classification  yard  promptly: 

1.  Skates,   retarders,   uphill  gradients   or  otiier  means   of  avoiding  runouts. 

2.  Recoupling  aids  to  keep  couplers  open. 

3.  Long  leads  to  interior  of  groups  to  speed  up  operation  and  reduce  travel 
time.  Design  leads  to  minimize  travel  time  in  pull  down  operations. 

4.  Coordinate  all  mechanical  and  transportation  departure  functions,  prefer- 
ably from  one  location. 

5.  Track  centers  as  wide  as  possible  to  permit  mechanized  inspections. 

6.  Sufficient  yard  air. 

7.  Efficient  waybill  procedures. 

8.  Track  facilities  similar  to  tliose  recommended  for  receiving  yards. 


DIRECTORY 

CONSULTING    ENGINEERS 


FRANK  R.  WOOLFORD 

Enginaering   Consultant — Railroadi 

24   Josepho    Ave. 

San   Francisco,  Co.  94132 

(415)  587-1569 

246  Seodrift   Rd. 

Stinson  Beach,  Co.  94970 

(415)  868-1555 


mj|M  Westenhoff  &  Novick,  Inc. 
■Ta    Consulting  Engineers 

Civil — Mechanical — Electrical 

Fixed  &  Movable  Bridges 

Soils,  Foundations,  Buildings 

Slrvctural  &  Underwater  Investigations 

Planning,     Feasibility,     Design,     Inspection 

222   W.   Adams   St.,   Chicago,   III.   60606 
New   Yoric  Washington  Ponamo 


HAZELET  &  ERDAL 

Consulting   Engineers 

Design         Investigations         Reports 
Fixed    and    Movable    Bridges 

150  So.  Wocker  Dr.,  Chicago,  III.  60606 
Louisville        Cincinnati        Washington 


HIMTB 


Feasibility  studies  and  design  services  for 

Bus  and  rail  transit  Terminals 

Regional  and  urt>an  planning  Parking 

Soils  and  foundations  Tunnels 

Structures  Utilities 
Environmental  Impact  studies 

Offices  in  28  cities  816  474-4900 

1805  Grand  Avenue.  Kansas  City,  Missouri  64108 


MODJESKi  AND  MASTERS 

Consw/ffng  Enginowa 

Design,   Inspection  of  Construction  !■  In- 
spection   of   Physical    Condition   of   Hxed 
&  Movable  Railroad   Bridges 

P.O.   Box   2345,   Horrisburg,   Pa.   17105 
1055  St.  Charles  Avn.,  New  Orleans,  La. 


CLARK,  DIETZ  AND 
ASSOCIATES-ENGINEERS,  INC. 

Consulting  Eng/neers 

Bridges    Structures,  Foundations,  Indus- 
trial Wastes  and  Railroad  Relocotion 

211    No.  Race  St.,  Urbona,  III. 

Sanford,   Fla.  Momphit,  Twin. 

lockson.  Miss.  St.   Louis,  Me. 

Chicago,  III. 


286-1 


286-2 


Directory  of  Consulting  Engineers 


(I) 


Engineers 
Designers     Planners 


PARSONS 

BRINCKERHOFF 

QUADE 

DOUGLAS 


Route  location.  Shop 
Facilities,  Container/ 
Bulk  Cargo,  Handling 
Utllltlei,  Bridget,  Tun- 
nels, Evaluotlont,  Ap- 
praisals, Supervision 


ONE  PENN  PLAZA,  NEW  YORK,  NY  10001 


Boston         ,        Denver 
San   Francisco 


,        Honolulu 
Trenton 


HARDESTY  &  HANOVER 

Contu/fing  Engln»»n 

TRANSPORTATION 
ENGINEERING 

Highways      •       Railways 

Bridges — Fixed   and   Movable 

Design       •       Resident   Inspection 

Studies      •      Appraisals 

101    Park  Ave.,  New  York,  N.  Y.    10017 


THOAAAS  K.  DYER,  INC. 

Consulting  Engineers 

Railroads — Transit  Systems 
Track,  Signals,  Structures 

Investisationt  and  Feasibility  Reports 
Planning,  Design,  Contract  Documents 

1762  Massachusetts  Avenue 
Lexington,  Mass.  02173 


SUBWAYS  •  RAILROADS  •  PUBLIC  TRANSIT 

TRAFFIC  .  PARKING  •  HIGHWAYS 
BRIDGES  .  PORT  DEVELOPMENT  •  AIRPORTS 
COMMUNITY  PLANNING  •  URBAN  RENEWAL 
MUNICIPAL  WORKS  •  INDUSTRIAL  BUILDINGS 
ENVIRONMENTAL  SCIENCE  AND  ENGINEERING 


IEC0 

RAILROAD 
DESIGN  &  ELECTRIFICATION 

Planning     •     Design 
Construction  Management 


INTERNATIONAL  ENGINEERING 
COMPANY,  INC. 

220  MONTGOMERY  STREET 
SAN  FRANCISCO.  CALIFORNIA  94104 


RILEY,  PARK,  HAYDEN  & 
ASSOCIATES,  INC. 

Consulting    Engineers 

Survey  Services,  Photogrammetry,  Gen- 
eral Civil,  Bridges,  Railroads  &  Indus- 
trial Parle  Design. 

136  Marietta  St.,  N.  W. 
Atlanta,  Georgia   30303 

(404)    577-5600 


Directory  of  Consulting  Engineers 


28&-3 


SVERDRUP  &  PARCEL  AND  ASSOCIATES,  INC. 

800  No.  Twelfth  Blvd.  •  St.  Louis.  Mo.  63101 

Boston  •  Charleston  •  Gainesville  •  Jacksonville 
Nashville  •  New  York  •  Phoenix  •  San  Francisco 
Seattle     •      Silver  Spring      •      Washington.  D.C. 


design 

planning 

construction 
management 


CONSULTING  ENGINEERS 


IHiV  PORTER  AND  RIPA 
ASSOCIATES,  INC 

ENGINEERING  PL.AMNING  ARCHITECTURE 

Design  Inspections  Reports 

Planning  Structures 

Environmental  Studies 

20«   Madison    Av*nu*.    Marrislewn,  New  Jrrsty  (TtU 


SPAULDING  ENGINEERING  CO. 

CONSULTING  ENGINEERS 

MEMBER 

AMERICAN  CONSULTING  ENGINEERS  COUNCIL 

1821    UNIVERSITY  AVENUE 

ST.  PAUL,  MINNESOTA  55104 

PHONE  612/644-5676 


SOROS  ASSOCIATES 

Consulting   Engineers 

Transfer  T«rniInaU  &  Ports  For  Dry  Bulk*, 

Liquids  &  Contoinars — Wot«rfront  Strvcturwt 

Materials  Hondltna  Systems 

575   Lexington  Ave. 

New  York,  N.  Y.   10022 

(212)   421-0400 

Rio  de  Janeiro  Santiago,  Chilo 

Sydney,  Australia 


BAKKE  &  KOPP,  INC. 

Consulting  Engineers 

RAILWAY  AND  HIGHWAY  BRIDGES 

SPECIAL  AND  HEAVY  STRUCTURES 

INVESTIGATIONS  AND  REPORTS 

4915  W.  35th  St.  Minneapolis,  MN  55416 

(612)   920-^383 


A.  J.  HENDRY,  INC. 


> 


CONSULTING  ENGINEERS 


SIGNALS  •  CONIMUNICATIONS  •  AUTOMATION  •  ataRlflCATION 
RAILROADS  •  RAIL  TRANSIT 


SUITE  810  OSBORN  BUILOINS 
ST.  PAUL.  ^AINNESOTA  55102 


»12)  222  2717 


286-4 


Directory  of  Consulting  Engineers 


TURNER  ENGINEERING 
COMPANY 

(SAWYER-PIEPMEIER) 

RAILROAD  ENGINEERING 

306  GAY  ST. 
NASHVILLE,  TENNESSEE   37201 

615-244-2144 
ALBANY,    NY      518-456-1994 


HOWARD  J.  BELLOWS 

ESTIMATING   CONSULTANT 
FOR   TRACKWORK 

Railroads    A    Rapid    Transit   Systems 

725   DALRYMPLE   ROAD 

Apt.   8-E 

ATLANTA,  GA.   30328 

404-393-0390 


MORE  TON  MILES 

of  SERVICE 

and  LESS  MAINTENANCE 

with 


ERVICES 


BALLAST 
CLEANING 


RAIL 


GRINDING 


Soutk*m  Pociftc 


ntQ 


—  CP 
Rail 


Discover  how  you  can  get  more  ton  miles  o< 
service  at  less  maintenance  cost  by  using  Spenp 
_:,,,       Ballast  Cleaning  and  Rail  Grinding. 

THROUGHOUT  THE  CONTINENT 

FRANK  SPEND  RAILROAD  BALLAST  CLEANING  COMPANY,  INC. 

306  North  Cayuga  St.,  Ittiaca,  New  York  14850 
Clark  Street.  Box  219,  East  Syracuse,  New  York  13057 

SPENO  INTERNATIONAL,  S.A.  lEC-HOLDEN,  LTD. 

22  Pare  Chateau  Banquet,  Geneva,  Switzerland   8180  Cote  de  Liesse  Road 

(For  Ra.l  G-^ndrg  Outside  the  Ncth  RPI    Montreal,  Canada  H4T1G8 

Amer.cjn  Contii'enlj  ...  ,  ,J^ 


TRASCO  Track  Skates 


Preferred  by  skatemen 

Light 

Tough 

Balanced  hand  hold 

No  curl  tongue 

TRACK  SPECIALTIES 

COMPANY 
Box  729  Westport ,  Conn .    ^ 


y.  fc ,   J>  fa  ///^  e  yer 

RECEIVED 

MAR  0  4  1976 

American  Railway  j.  l  sTAujira 

Engineering  Association— Bulletin 


Bulletin  656  January-February   1976 

Proceedings  Volume  77* 


CONTENTS 

REPORTS  OF  COMMITTEES 

Scales   (Special   Committee) 2*' 

Economics  of  Railway  Construction  and  Maintenance  (22) 299 

Environmental    Engineering    (13) 323 

Maintenance  of  Way  Work  Equipment  (27) 333 

Clearances  (28) 337 

Buildings  (6) 341 

Timber  Structures  (7) 351 

Concrete  Structures  and  Foundations  (8) 353 

Steel   Structures   (15) 359 

Roadway  and  Ballast  (1) 363 

Ties  and  Wood  Preservation  (3) 367 

Rail   (4) 373 

Economics  of  Plant,  Equipment  and  Operations  (16) 383 

Engineering  Education  (24) 401 

Electrical  Energy  Utilization  (33) 403 

VANCOUVER   REGIONAL  MEETING 

Luncheon  Address  by  A.  F.  Joplin 415 

Address — Railway  Signaling,  by  H.  W.  Trawick 419 

Address — Railway    Bridges    on    Canadian    National's    Mountain    Region,    by 

L.  R.  Morris 425 

Address — Investigation    into   Causes   of   Rail   Corrugations,   by   J.   Kalousek, 

R.    Klein    429 

Address — Rock    Slope    Stability    on    Railway    Projects,    by    C.    O.    Browner, 

Duncan    Wyllie    449 

Directory  of  Consulting   Engineers 474—1 


•Proceedings  Volume  77  (1976)  will  consist  of  AREA  Bulletins  654,  Septembei^ 
October  1975;  655,  November-December  1975;  656,  January-February  1976;  and  858, 
June-July  1976  (Technical  Conference  Report  issue).  Blue-covered  Bulletin  657,  April- 
May  1976  (the  Directory  issue),  is  not  a  part  of  the  Annual  Proceedings  of  the  Association. 


BOARD  OF  DIRECTION 

1975-1976 

President 
J.  T.  Ward,  Senior  Assistant  Chief  Engineer,  Seaboard  Coast  Line  Railroad,  500  Water 
St.,  Jacksonville,  FL  32202 

Vice  Presidents 
John  Fox,  Deputy  Chief  Engineer,  Canadian  Pacific  Rail,  Windsor  Station,  Montreal, 

PQ  H3C  3E4 
B.  J.  WORLEY,  Vice  President— Chief  Engineer,  Chicago,  Milwaukee,  St.  Paul  &  Pacific 

Railroad,  Union  Station,  Room  898,  Chicago,  IL  60606 

Past  Presidents 

D.  V.  Sartore,  Chief  Engineer — Design,  Burlington  Northern,  Inc.,  176  E.  Sth  St.,  St. 

Paul,  MN  SS 101 
R.  F.  Bush,  Chief  Engineer,  Erie  Lackawanna  Railway,  Midland  Bldg.,  Cleveland,  OH 
441  IS 

Directors 
R.  W.  PEifBER,  Chief  Engineer — Design  and  Construction,  Louisville  &  Nashville  Rail- 
road, P.  O.  Box  1198,  Louisville,  KY  40201 

E.  Q.   Johnson,  Senior  Assistant   Chief  Engineer,   Chessie  System,  P.  O.  Box   1800, 

Huntington,  WV  2S718 

W.  E.  FuHR,  Assistant  Chief  Engineer— Staff,  Chicago,  Milwaukee,  St.  Paul  &  Pacilic 
Railroad,  Union  Station,  Room  898,  Chicago,  IL  60606 

B.  E.  Pearson,  Chief  Engineer,  Soo  Line  Raikoad,  Soo  Line  Bldg.,  Room  1520,  Minne- 
apolis, MN  55440 

P.  L.  Montgomery,  Manager  Engineering  Systems,  Norfolk  &  Western  Railway,  8  N. 
Jefferson  St.,  Roanoke,  VA  24042 

E.  C.  HoNATH,  Assistant  General  Manager  Engineering,  Atchison,  Topeka  &  Santa  Fe 
Railway,  900  Polk  St.,  Amarillo,  TX  79171 

Mike  Rovgas,  Chief  Engineer,  Bessemer  &  Lake  Erie  Railroad,  P.  O.  Box  471,  Green- 
ville, PA  16125 

J.  W.  DeValle,  Chief  Engineer  Bridges,  Southern  Railway  System,  99  Spring  St.,  S.  W., 
Atlanta,  GA  30303 

R.  L.  Gray,  Chief  Engineer,  Canadian  National  Railways,  P.  O.  Box  8100,  Montreal, 
PQ  H3C  3N4 

E.  H.  Waring,  Chief  Engineer,  Denver  &  Rio  Grande  Western  Raikoad,  P.  0.  Box 
5482,  Denver,  CO  80217 

Wm.   Glavin,    General  Manager,   Grand  Trunk   Western   Railroad,   131   W.  Lafayette 
Blvd.,  Detroit,  MI  48226 

G.  H.  Maxwell,  System  Engineer  of  Track,  Union  Pacific  Railroad,  1416  Dodge  St., 
Omaha,  NE  68179 

Treasurer 

A.  B.  HiLLMAN,  Jr.,  Chief  Engineer,  Belt  Railway  of  Chicago,  6900  S.  Central  Ave., 
Chicago,  IL  60638 

Executive  Director 

Earl  W.  Hodgkins,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Assistant  to  Executive  Director 
N.  V.  Engman,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Administrative  Assistant 
D.  F.  Fredley,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Published    by    the    American    Railway    Engineering   Association,    Bi-Monthly,    Januaiy-Febniary,   April- 
May,  June-July,  September-October  and  November-December,  at 
S9  East  Van  Buren  Street,  Chicago,  111.  60605 
Second  class  postage  at  Chicago,  111.,  and  at  additional  mailing  offices. 
Subscription  $15  per  annum 
Copyright  ©  1976 
American  Railway  Engineering  Association 
All  rights  reserved. 
No    part    of    this   publication    may   be   reproduced,    stored   in    an    information    or   data    retrieval 
system,     or    transmitted,    in    any    form,    or    by    any    means — electronic,    mechanical,    photocopying, 
recording,   or  otherwise — without  the  prior  written  permission  of  the  publisher. 


Report  of  the  Special  Committee  on  Scales 


F.  D.  Day,  Chairman 
V.    H.   Freygang, 

Vice  Chairman 
M.  R.  Gruber,  Jr., 

Secretary 


l.  l.  lowehy 
Emil  Szaks 
B.    F.    Banks 
N.  A.  Wilson 
O.  T.  Almarode 
R.  F.  Beck 
R.  T.  Brumbaugh 
H.  E.  Buchanan 
E.  W.  Buckles 
G.  H.  Chabot 
J.  L.  Dahlrot 
R.  H.  Damon,  Jr. 
T.  A.  DeAlba 

0.  C.  Denz 

J.    L.    FiNNELL 

J.  E.  Foreman,  Jr. 
G.  F.  Graham 
J.  A.  Hawley 

1.  M.  Hawvek 
L.  J.  Held 

A.  L.  Hunter 


D.  K.  Johnstone 

D.  E.  Keeper 
S.  H.  Levinson 

V.    L.    LOWERY 

P.   J.    McCoNVILLE 

E.  J.  MicoNO 
R.  E.  Park 
N.  S.  Patel 
B.  H.  Price 
W.  H.  Rankin 
S.  H.  Raskin 
A.  E.  Robinson 
J.  J.  Robinson 
K.  D.  Tidwell 
J.  N.  Todd 

L.  J.  Walker 
P.  C.  White 
J.  Zaenger 


Committee 


Those  whose   names   are   shown   hi  boldface,   in   addition  to  the  chairman,   vice   chairman  and 
secretary,    are   the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 

Your  committee  reports  on  the  following  subjects: 


B.  Revision  of  Manual. 

Proposed  Belt  Conveyor  Scale   Rules,  submitted  as  information 


page  288 


1.  Location  of  Scales  for  Coupled-in-Motion  Weighing. 

Progress  report,  presented  as  information    page  295 

2.  Survey  of  All  Scales  in  America  Used  for  Weighing  Railroad  Cars. 

No  report. 

3.  Statistical  Data  for  Coupled-in-Motion  Weighing  and  Testing. 

An  advance  report  on  this  assignment  was  published  in  Bulletin  654, 
September-October  1975. 

4.  NBS    Handbook    44    Joint    Study   with    State    Weights    and    Measures 
Officials. 

No  report. 

The  Special  Committee  on  Scales, 

F.  D.  Day,  Chairman. 


287 


Bui.  656 


288       Bulletin  656 — American  Railway  Engineering  Association 
Report  on  Assignment  B 

Revision  of  Manual 

L.  L.  LowERY  (chairman,  stihcommittee),  all  members  of  the  Special  Committee  on 
Scales. 

Your  committee  presents,  as  infomiation  only,  the  following  belt  conveyor  scale 
rules.  These  rules,  with  possible  minor  revisions,  will  be  submitted  for  adoption  and 
publication  in  the  Manual  in  1976,  following  letter  ballot  approval  by  the  committee. 

PROPOSED  BELT  CONVEYOR  SCALE  RULES 
S.2.28  BELT  CONVEYOR  SCALES 

5.2.28.1  Definition 

The  following  is  intended  to  apply  to  devices  installed  on  belt  conveyors  for 
the  purpose  of  weighing  bulk  materials  carried  by  conveyors  to  ascertain  weights, 
and  to  the  system  to  which  they  are  applied  and  become  part  of. 

5.2.28.2  Capacity 

The  system  should  be  designed  and  rated  so  that  material  flowing  over  the  scale 
will  remain  within  50%  to  98%  of  scale  capacity  and  should  be  adequate  and  constant. 

5.2.25.3  Conveyors 

(a)  Each  conveyor  on  which  a  belt  scale  is  located  should  be  rigid  in  design 
and  so  constructed  that  it  is  free  from  vibration  and  is  not  subject  to  stress  that 
would  cause  any  deflection.  It  should  not  exceed  1,000  ft  in  length  from  center  of 
head  pulley  to  center  of  tail  pulley. 

(b)  Each  conveyor  on  which  a  belt  scale  is  located  should  be  equipped  with  a 
gravity  take-up  that  is  of  adequate  weight  so  as  not  to  allow  slippage  of  the  belt 
on  the  drive  pulley.  With  such  weight  properly  weighted,  the  belt  should  remain  in 
contact  with  all  troughing  idlers  in  the  weight-sensing  element  area  at  all  times. 

(c)  The  conveyor  on  which  the  scale  is  located  should  be  free  from  interference 
from  all  other  operations. 

(d)  The  system  should  be  so  designed  that  the  complete  contents  of  each  indi- 
vidual car  may  be  guaranteed  to  pass  over  the  scale. 

(e)  Incline  of  the  conveyor  belt  should  not  be  in  excess  of  18  to  20  degrees. 

5.2.28.4  Infeeds 

(a)  Sufficient  impact  idlers  should  be  provided  in  the  conveyor  imder  each  infeed 
so  as  not  to  cause  a  deflection  of  the  belt  during  the  time  material  is  being  introduced. 

(b)  All  infeed  gates,  feeders,  etc.,  should  be  positive  in  action  and  so  designed 
that  material  will  flow  freely  through  them  when  opened  or  placed  in  operation. 
They  should  also  be  positive  in  their  closing  action  so  that  leakage  does  not  occur. 

5.2.28.5  Instrumentation 

(a)  A  rate-of-flow  indicator  should  be  installed  and  correctly  calibrated.  The 
indicator  should  also  be  equipped  with  a  24-hour  disc  or  strip  chart  to  serve  as  a 


Scales 289 

permanent  record,  along  with  a  high  and  low  cut-off  alarm  system.  This  is  to  help 
prevent  under  or  overloading  of  the  scale.  The  alann  should  be  operational  at  not 
lower  than  35^  or  greater  than  98%  of  scale  capacity.  The  type  of  alarm  used  (i.e., 
audio  or  visual)  should  be  determined  by  the  merits  of  each  individual  application. 
Such  system  should  not  be  outfitted  with  a  switch  to  disconnect  either  the  chart  or 
alarm  system.  Any  exceptions  to  this  rule  will  be  at  the  discretion  of  the  serving  rail 
carrier  or  its  agent. 

(b)  A  fast-count  totalizer  should  be  installed  and  should  register  in  units  of 
1/10  of  a  ton,  or  as  determined  by  the  serving  rail  carrier. 

(c)  A  ticket  or  tape  printer  (detemiined  by  each  individual  application)  and 
printing  to  the  equivalent  numerals  as  indicated  in  (b),  should  be  installed.  It  is 
essential  that  the  printer  mounting  will  guarantee  vibration-free  operation. 

5.2.28.6  Cabinets 

(a)  Scale  and  instrumentation  cabinets  should  be  purged  witli  clean,  dry  air. 

(b)  Where  scales  and  component  parts  are  subject  to  a  rapid  or  extreme  change 
in  temperature,  heaters  should  be  installed  as  suggested  by  manufacturer. 

(c)  Scales  located  near  large  bodies  of  water,  operations  that  require  use  of 
quantities  of  water,  or  any  area  of  high  humidity,  should  have  heaters  installed  in 
scales  and/or  instrumentation  as  suggested  by  manufacturer. 

5. 2.28.7  Protection  of  Scales   and  Instrumentation 

(a)  Scales  and  especially  instrumentation  should  be  protected  from  the  elements 
by  weather-proof  structures.  Control  rooms  that  house  instruments  should  be  air 
purged  with  air  conditioning,  fans  with  filters,  heaters,  etc.,  so  that  a  dust-free  area  of 
greater  density  will  be  created  on  the  inside  than  is  outside.  Such  system  is  required 
to  preserve  all  electronic  instnunents. 

(b)  Scale  housing  and  instrumentation  should  be  securely  locked. 

5.2.28.8  Wind  Screens 

Wind  screens   should  be  erected   around  the  entire  weighing  element. 

5.2.28.9  Guards 

(a)  Sufficient  guards  should  be  erected  around  "live"  scale  parts  located  near 
walk-ways  so  that  persons  will  not  touch  such  parts  or  deposit  equipment  in  their 
vicinity. 

(b)  In  some  cases,  "live"  parts  of  scales  should  be  painted  in  contrasting  colors 
so  as  to  warn  persons  against  touching  them.  The  application  of  this  Rule  will  be  at 
the  discretion  of  the  serving  carrier  or  its  agent. 

5.2.28.10  Interference 

Hydraulic  machinery,  large  motors,  or  any  equipment  which  will  cause  excessive 
vibration  or  noise  should  not  be  placed  in,  or  affixed  to,  the  control  room. 

5.2.28.11  Access  to  Scale 

Adequate  access  to  scale  should  be  provided.  This  includes  a  walk-way,  step, 
etc.,  so  that  servicing  can  be  accomplished  with  ease. 


290       Bulletin  656 — American  Railway  Engineering  Association 

5.2.28.12  Simulated  Load  Testing  Equipment 

Adequate  simulated  load  testing  equipment,  to  be  applied  on  the  belt  over  the 
weight-sensing  element,  approximating  80%  of  the  rated  capacity  of  the  weighing 
system,  is  required.  A  suitable  storage  area  should  be  provided  so  tliat  such  equipment 
does  not  rust  or  deteriorate  from  abrasive  or  coating  action.  See  S.2.28.15. 

Note:  The  following  suggested  practices,  if  followed,  will  greatly  facilitate  testing 
and  operation  of  the  system. 

1.  At  least  two  persons  or  more  on  location  should  be  thoroughly  familiar 
with  the  scale  and  its  operation. 

2.  Control  over  entire  system  should  be  exercised  by  the  scale  operator  to 
insure  adequate  loading  of  the  weighing  device. 

3.  Unautliorized  personnel  should  be  discouraged  from  loitering  in  the  scale 
and  instrumentation  areas. 

4.  Where  test  chains  are  used,  adequate  cables,  bridles,  hooks,  etc.,  should  be 
provided  to  hold  the  chains  in  place  on  the  belt  as  recommended  by  tlie 
scale  manufacturer. 

5.2.28.13  Tolerance  Values 

(a)  Material  Test  Tolerance 

All  belt  scales  should  be  material-tested  and  adjusted  to  within  0.25%  with 
repeatability.  The  spread  between  plus  or  minus  figures  should  not  exceed  0.25%. 

(h)  Maintenance  Tolerance 

All  belt  scales  should  maintain  a  0.5%  tolerance  between  material  used.  The 
spread  between  plus  or  minus  figures  should  not  exceed  0.5%. 

(c)  Zero  Tolerance 

All  belt  scales  should  maintain  a  zero  balance  of  0.1%  for  10  minutes  before  use, 
and  after  sufficient  warm-up  of  the  belt. 

(d)  Repeatability  Tolerance 

All  belt  conveyor  scales  using  simulated  load  testing  equipment  should  be  tested 
for  a  repeatability  of  not  greater  than  0.1%  for  at  least  5  consecutive  tests.  The 
spread  between  plus  or  minus  figures  should  not  exceed  0.1%. 

5.2.28.14  Types  of  Tests  Defined 

(a)  Material  Testing 

All  belt  conveyor  scales  should  be  material-tested  before  acceptance.  Three  to 
five  such  tests  are  required,  with  10  to  15  car  (or  in  some  cases  heavy  truck)  loads 
per  test.  If  the  weighing  system  is  designed  for  individual  car  weights,  the  weight 
of  each  individual  car  should  be  in  tolerance. 

(b)  Maintenance  Testing 

All  belt  conveyor  scales  should  be  maintained  within  a  0.5%  tolerance  between 
material  tests,  by  using  a  simulated  load  test.  Such  tests  should  be  conducted  on  a 
weekly  basis,  preferably  as  soon  after  actual  use  of  die  belt  as  possible. 

(c)  Repeatability  Test 

All  belt  conveyor  scales  should  be  tested  for  repeatability  each  time  a  Main- 
tenance Test  is  made  and  before  Material  Tests  are  run. 


Scales 291 

S.2.28.15  Standard  Procedure  for  Tests 

(a)  Scale  and  entire  installation  should  be  checked  for  confomiity  with  the 
above-listed  rules  and  regulations.  The  scale  and  all  component  parts  should  be  com- 
pletely installed  and  in  good  operating  condition  before  any  tests  will  be  made. 

(b)  The  belt  length  and  weight  of  chains  per  foot  should  be  accurately  measured 
so  as  to  determine  tons  per  foot  of  belt  travel  during  chain  tests. 

(c)  The  belt  should  be  run  at  least  20  minutes  before  test  begins  in  order  to 
warm  it  up.  At  temperatures  below  40  F,  the  wann-up  time  should  be  of  longer 
duration. 

(d)  Following  warm-up,  belt  should  be  run  for  at  least  10  minutes  to  detennine 
zero  of  scale.  During  this  time,  the  zero  reading  should  be  constant. 

(e)  After  establishing  that  tlie  scale  holds  its  zero,  10  circuits  of  the  belt  should 
be  run  with  the  simulated  load  testing  equipment  in  place  on  belt.  In  some  instances, 
where  the  belt  is  long,  only  three  circuits  of  the  belt  are  required. 

If  test  chains  are  used,  they  should  be  held  securely  in  place  on  the  belt  as  the 
scale  manufacturer  recommends. 

If  tests  utilizing  other  than  the  above  methods  are  contemplated,  tlie  approval 
of  the  serving  rail  carrier  or  its  agent  should  be  secured. 

Note:  When  other  than  test  chains  are  used,  onhj  idlers  of  the  highest  quality 
and  requiring  lubrication  daily  should  he  used.  Such  idlers  should  he  insialled  on  the 
iceighing  element  and  for  at  least  jive  idler  spaces  before,  and  for  at  least  five  idler 
spaces  after,  the  weighing  element.  Further,  each  week  correct  idler  level  should  he 
determined  with  a  string  level.  If  any  one,  or  more,  of  the  above  named  idlers  are 
out  of  level,  the  scale  shotdd  not  be  used  until  correction  is  made.  Idlers  with  loorn 
bearings  should  be  replaced. 

(f)  Five  more  simulated  load  tests  should  then  be  run,  with  results  of  each  test 
reading  within  0.1%  of  the  first  test  outlined  in  paragraph  (e)  above.  This  will 
establish  repeatability. 

(g)  If  the  scale  has  repeatability,  15  loads  should  tlien  be  weighed  over  the  scale, 
at  50%  to  98%  capacity.  A  load  is  construed  as  a  rail  car  load  or  truck  load  of  high 
capacity. 

Note:  In  instances  where  procurement  of  rail  cars  proves  difficult,  10  loads  per 
test  may  be  substituted.  This  is  a  calibration  test  and  may  have  to  be  made  several 
times  in  order  to  bring  the  iceighing  device  within  the  acceptable  tolerance  of  0.25%. 

(h)  After  the  scale  has  been  properly  calibrated,  three  separate  material  tests, 
all  within  0.25%  with  material  being  loaded  at  50%  to  98%  of  capacity,  should  then  be 
made.  Each  test  should  consist  of  15  loads.  (Here  again  10  loads  per  test  may  be 
substituted  in  the  event  rail  cars  are  difficult  to  obtain.) 

(i)  Following  three  successful  material  tests,  five  simulated  load  tests  should 
again  be  made  in  order  to  establish  a  calibration  factor,  if  needed. 

( j )  On  successful  completion  of  all  tests,  the  scale  should  again  be  checked  for 
zero.  At  this  time,  it  will  also  be  established  that  a  service  contract  has  been  con- 
summated with   a   qualified  belt  scale  service   organization. 

(k)  Material  scale  tests  should  be  made  once  every  six  months,  or  as  directed 
by  the  serving  rail  carrier  or  its  agent. 


292       Bulletin  656 — American  Railway  Engineering  Association 

(1)  The  material  acceptance  tolerance  of  0.25^  should  be  maintained  for  30 
days,  and  at  any  time  the  scale  is  overhauled  or  material  tested  by  an  authorized 
scale  man. 

(m)  A  maintenance  tolerance  of  0.5%  should  be  maintained  by  the  user  at  all 
times  after  the  scale  is  accepted.  This  may  be  assured  by  conducting  tests  at  least 
once  a  week  as  outlined  in  paragraph  (i)  above,  using  the  established  calibration 
factor. 

(n)  The  rail  carrier  should  be  contacted  at  least  two  weeks  before  material 
tests  are  made  to  insure  that  sufficient  cars  are  available. 

(o)  Copies  of  weekly  tests  should  be  made  available  to  the  serving  rail  carrier 
or  its  agent. 

(p)  Proof  of  weight  for  belt  conveyor  scales  should  be  in  the  form  of  a  printed 
weight  ticket  and  rate-of-flow  chart  showing  the  scale  was  utilized  between  50% 
and  98%  of  its  capacity.  The  rate-of-flow  chart  should  be  dated  corresponding  widi 
cars  in  loading  or  unloading  sequence.  All  of  these  records  should  be  preserved 
together. 

(q)  In  instances  where  material  testing  can  be  satisfactorily  performed  weekly. 
Simulated  Load  Tests  are  not  required.  Copies  of  weekly  tests,  however,  should  be 
made  available  to  the  serving  rail  carrier  or  its  agent.   (See  S.2.28.12) 

Definition  of  Terms  Used  in  Connection  with  Belt  Conveyor  Scales 

Air  Purge:  The  act  of  creating  an  atmosphere  greater  on  the  inside  than  outside, 
using  clean,  dry  air,  to  discourage  dust  and  other  foreign  matter. 

Belt  Conveyor:  An  endless  moving  belt  for  transporting  material  from  place  to 
place.* 

Belt  Conveyor  Scale;  (  Belt  Scale  ) ;  (  Conveyor  Scale  ) :  A  device  installed 
on  a  belt  conveyor  to  measure  the  weight  of  bulk  material  being  conveyed." 

Bend  Pulley:  A  roller  placed  on  the  return  side  (underside)  of  a  conveyor  belt 
to  turn  its  direction  or  to  measure  speed  of  belt. 

Cable  Conveyor:  A  belt  conveyor  utilizing  cable  or  rope  as  the  supporting  member 
for  the  conveyor  on  which  the  idlers  are  mounted. 

Calibrated  Plate:  A  suitable  metal  plate,  provided  by  the  scale  manufacturer, 
determined  to  have  the  same  effect  on  a  nuclear  scale  as  a  specified  load  or 
bulk  material  on  the  belt  conveyor.  A  calibrated  plate  is  the  equivalent  of  a  test 
chain  or  test  weights  used  with  other  types  of  belt  conveyor  scales.* 

Chain:   See  Test  Chain. 

Chart  Recorder:  A  device  used  with  a  belt  conveyor  scale  which  records  the  rate- 
of-flow  of  bulk  material  over  the  scale  at  any  given  time.  A  recorded  chart 
together  with  a  record  of  weight  constitutes  proof  of  weight. 

Concave  Curve:  A  change  in  the  angle  of  inclination  of  a  belt  conveyor  where 
the  center  of  the  curve  is  above  the  conveyor.* 

Convex  Curve:  A  change  in  the  angle  of  inclination  of  a  belt  conveyor  where  tlie 
center  of  the  curve  is  below  the  conveyor.* 

Conveyor  Stringers:  Support  members  for  the  conveyor  on  which  the  idlers  are 
mounted. 


*  Taken   from    National   Bureau  of   Standards   Handbook   44. 


Scales 293 

Counter  (  Remote  ) :  A  numerical  display  in  a  location  remote  from  the  scale 
showing  the  tons  (or  pounds)  of  material  that  have  been  conveyed  over  the 
scale. 

Disc  Chart:  See  Chart  Recorder. 

Drive:  The  device  or  apparatus  used  to  transmit  energy  from  a  motor  to  move  the 
conveyor  belt. 

Feeders:   See  Infeed. 

Gate:   See  Infeed. 

Gravity  Type  Wipers:  A  scraping  or  wiping  device  used  to  clean  residue  from  the 
belt  on  the  return  side  ( underside )  of  the  belt  in  the  vicinity  of  the  head  pulley. 
The  \\'iper  is  affixed  to  one  end  of  an  ann  which  has  a  weight  hanging  from  the 
other  end.  The  weight  is  such  that  the  wiper  is  held  against  the  belt. 

Head  Pulley:  The  pulley  at  tlie  discharge  end  of  the  belt  conveyor.  The  power 
drive  to  drive  the  belt  is  generally  applied  to  the  head  pulley." 

Idler  Space:  The  center-to-center  distance  between  idler  rollers  measured  parallel 
to  the  belt." 

Idler  Fr.\me:  The  frame  or  device  which  holds  the  idler  rollers,  affixed  to  the 
conveyor  stringers. 

Idler  or  Idler  Rollers:  Freely  turning  cylinders  mounted  on  a  frame  to  support 
the  conveyor  belt.  For  a  flat  belt  the  idlers  may  consist  of  one  or  more  horizontal 
cylinders  transverse  to  the  direction  of  belt  travel.  For  a  troughed  belt,  the 
idler  will  consist  of  one  or  more  horizontal  cylinders  and  one  or  more  cylinders 
at  an  angle  to  the  horizontal  to  lift  the  sides  of  the  belt  to  fonn  a  trough.* 

Infeed:  The  gate,  short  belt,  vibrator  feeder,  stroker  feeder,  etc.,  that  deposits 
material  on  the  belt  conveyor  to  be  weighed. 

Integrator:  The  "heart"  of  the  belt  conveyor  scale.  A  device  which  integrates  tlie 
speed  of  the  belt  with  the  weight  of  the  material  to  produce  tons  (or  pounds) 
per  hour.  The  integrator  may  be  electronic  or  mechanical  and  may  be  one  of 
numerous  patented  designs. 

Lagged  Pulley:  See  Swedged  Pulley. 

L0.A.DING  Point:  The  location  at  which  material  to  be  conveyed  is  applied  to  the 
conveyor. 

Master  Totalizer:   See  Totalizer. 

Nuclear  Type  (non-contract)  Scale:  A  device  consisting  of  a  source  of  nuclear 
radiation  and  a  detector  for  that  radiation.  Absorption  of  radiation  determines 
the  mass  of  the  material  passing  between  the  source  and  the  detector." 

Printer:  A  device  used  to  imprint  on  tickets,  tape,  or  other  papers,  tlie  tons  (or 
pounds)  of  material  Uiat  have  passed  over  the  scale  in  a  given  time.  (Such  as 
per  car  or  per  train  weights.) 

Pulley:  A  cylindrical  roller  over  which  the  belt  passes  to  change  direction,  such  as 
the  head  pulley  or  tail  pulley  or  bend  pulley. 

Rate-of-Speed  Detector:  A  device  usually  operated  in  conjunction  with  electronic 
load  cell  belt  conveyor  scales  which  transmits  the  speed  of  tlie  belt  to  tlie 
integrator.  Several  types  are  in  use,  the  most  popular  being  eitlier  a  small 
generator  whose  voltage  output  is  in  direct  relationship  to  the  speed  of  the  belt; 


'  Taken    from    National    Bureau   of    Standards    Handbook    44. 


294       Bulletin  656 — American  Railway  Engineering  Association 

or  a  slotted  disc  mounted  between  a  photo  electric  cell  and  light  source  which 
converts  each  pulse  of  light  to  an  electronic  signal  to  the  integrator. 

Rated  Capacity:  That  value  representing  the  weight  tliat  can  be  delivered  by 
the   device   in  one  hour.* 

Registration:  The  unit  of  weight  in  which  the  scale  is  calibrated,  such  as  5,000  lb, 
tons,  long  tons,  metric  tons,  etc. 

Rope  Conveyor:  See  Cable  Conveyor. 

Simulated  Weight  Test:  A  test  using  artificial  means  of  loading  the  scale  to  deter- 
mine the  perfonnance  of  a  belt  conveyor  scale.* 

Skirting:  Stationary  side  boards  or  sections  of  belt  conveyor  attached  to  the  con- 
veyor support  frame  or  otlier  stationary  support  to  prevent  tlie  bulk  material 
from  falling  off  the  side  of  the  belt*  Usually  used  at  infeeds. 

Snubbed  Pulley:   See  S wedged  Pulley. 

Stringer:   See  Conveyor  Stringer, 

Strip  Chart:   See  Chart  Recorder. 

Strip  Heater:  A  thermostatically  controlled  heading  strip  (usually  of  the  Calrod 
type)  used  to  heat  the  scale  or  component  parts  sufficiently  to  prevent 
condensation. 

S wedged  Pulley:  A  drive  pulley  with  a  vulcanized  rubber  coating  molded  in  a  high 
friction  pattern  to  prevent  slippage  of  the  belt  under  load. 

Swivel  Idler:  An  idler  frame  pivoted  in  its  center  to  the  idler  stringers  so  tliat  it 
may  change  position.  Tracking  idlers  are  mounted  beside  the  troughing  idlers 
so  that  if  the  belt  rides  off  center  the  pressure  on  the  tracking  idler  forces  the 
swivel  idler  to  turn,  thus  realigning  the  belt  on  the  conveying  idlers. 

Tail  Pulley:  The  pulley  at  tlie  opposite  end  of  the  conveyor  from  the  head  pulley.* 

Take-up:  A  device  to  assure  sufficient  tension  in  a  conveyor  belt  that  the  belt  will 
be  positively  driven  by  the  drive  pulley.  A  gravity  take-up  consists  of  a  hori- 
zontal pulley  free  to  move  in  either  tlie  vertical  or  horizontal  direction  with 
the  dead  weights  applied  to  the  pulley  shaft  to  provide  the  tension  required. 
A  jack  or  screw  take-up  consists  of  a  device  that  must  be  manually  adjusted 
to  move  the  tail  pulley  to  increase  or  decrease  tension.  A  hydrauUc  take-up 
consists  of  hydraulic  cylinders  mounted  on  either  side  of  both  ends  of  the  tail 
pulley.  Wlien  properly  activated,  the  hydraulic  cylinders  will  move  tlie  tail 
pulley  to  increase  or  decrease  tension  on  the  belt. 

Take-up  Guides:  Guides  or  tracks  on  either  side  of  the  gravity  take-up  weight  to 
prevent  horizontal  movement  of  that  weight. 

Test  Chain:  A  device  consisting  of  a  series  of  rollers  or  wheels  linked  together  in 
such  a  manner  as  to  assure  uniformity  of  weight  and  freedom  of  motion  to 
reduce  wear,  with  consequent  loss  of  weight  to  a  minimum.* 

Totalizer:  A  device  used  witli  a  belt  conveyor  scale  to  indicate  the  weight  of  ma- 
terial which  has  been  conveyed  over  the  scale.  The  master  weight  totalizer  is 
the  primary  indicating  element  of  the  belt  conveyor  scale.  An  auxiliary  vernier 
counter  used  for  scale  calibration  is  not  (necessarily)  part  of  tlie  master  weight 
totalizer.  Auxiliary  remote  totahzers  may  be  provided.  The  totalizer  shows  the 
accumulated  weight  and  may  be  non-resettable  or  may  be  reset  to  zero  to 
measure  a  definite  amount  of  material  conveyed. 


*  Taken    from    National    Bureau   of    Standards    Handbook    44. 


Scales 295 

Tracking  Idlers:  Usually  small  c>linders  vertically  mounted  on  shafts  affixed  to 
a  swivel  idler  frame.  The  purpose  is  to  allow  the  side  of  the  belt  to  rub  against 
the  tracking  idler,  forcing  the  swi\el  idler  frame  to  turn,  thus  realigning  the  belt. 

Training  Idlers:  Idlers  of  special  design  or  mounting  intended  to  shift  the  belt 
sideways  on  the  conveyor  to  assure  the  belt  is  centered  on  the  conveying  idlers.* 

Tripper:  A  device  for  unloading  a  belt  conveyor  at  a  point  between  the  loading 
point  and  die  head  pulley.** 

Wing  Pulley:  A  pulley  usually  used  as  tire  tail  pulley,  made  of  widely  spaced 
metal  bars  in  order  to  set  up  a  vibration  to  shake  loose  material  off  the  under- 
side (return  side)  of  tlie  belt.  The  use  of  such  a  pulley  is  definitely  not  recom- 
mended unless  the  conveyor  stringers  under  the  scale  are  thoroughly  braced 
with  their  own  support. 

Wiper:   See  Gravity  Type  Wiper. 


'  Taken    from    National    Bureau   of    Standards    Handbook    44. 

Report   on   Assignment   1 

Location  of  Scales  for  Railroad 
Coupled-in-Motion  Weighing 

E.  SzAKS  (chairman,  subcommittee),  R.  F.  Beck,  H.  E.  Buchanan,  J.  L.  Dahlrot, 
O.  C.  Denz,  J.  L.  FiNNELL,  J.  A.  Hawley,  I.  M.  Hawver,  V.  L.  Lovitery, 
E.  J.  MicoNo,  N.  S.  Patel,  K.  D.  Tidwell. 

A  SUGGESTED  GUIDE  FOR  SELECTING 
A  COUPLED-IN-MOTION  WEIGHING  SYSTEM  SITE 

The  prerequisites  in  selecting  a  site  for  installation  of  a  coupled-in-motion 
weighing  system  are  those  which  will  permit  the  entire  train  to  be  weighed  to  move 
over  the  predetermined  point  in  such  a  manner  that  the  effects  upon  weight  transfer 
from  car  to  car  will  be  minimized  in  weighing  functions.  The  train  must  approach 
the  facility  and  move  over  the  weighing  device  at  a  constant,  steady  speed  of  be- 
tween 3  to  5  mph,  but  not  to  exceed  6  mph.  The  train  should  be  moved  over  the 
facility  in  a  slow,  steady  movement,  that  is,  one  in  which  the  train  is  not  being  pulled 
with  tlie  ( diesel )  locomotive  throttle  in  more  than  the  first  or  second  position,  gener- 
ating about  200  amp  of  power,  so  as  to  prevent  the  train  being  stretched  severely. 
At  the  same  time,  tlie  train  should  not  be  bunched,  or  shoved  by  its  rear  end,  as  a 
result  of  using  either  the  independent  or  dynamic  brakes.  The  train  handling  must 
be  such  as  to  prevent  all  slack  action.  All  automatic  air  brakes  and  hand  brakes 
on  cars  must  be  fully  released. 

The  number  of  cars  to  be  handled  at  a  given  time  over  the  weighing  device 
should  be  given  careful  consideration.  The  maximum  number  of  cars  to  be  handled 
in  a  single  train  may  dictate  the  grade  and  curvature  which  can  be  tolerated  to 
maintain  the  proper  weighing  speed,  and  at  the  same  time  cause  cars  to  move  over 
the  device  in  such  a  manner  as  to  produce  acceptable  results.  Generally,  die  site 
selection  should  be  such  that  the  existing  grade  and  curvature  will  so  compensate 
for  each  other  that  cars  will  move  over  the  device  in  a  non-accelerating  mode. 


296       Bulletin  656 — American  Railway  Engineering  Association 

Additionally,  the  device  should  be  located  so  tliat  a  train  originating  and  having 
cars  to  be  weighed  would  pass  over  the  weighing  device  without  change  of  consist 
or  train-order  standing.  The  foregoing  condition  is  one  requiring  special  consideration 
where  car  identification  may  become  a  concern.  Bi-directional  use  of  the  device, 
eitlier  pushing  or  pulling,  should  be  an  item  to  be  recognized. 

The  coupled-in-motion  type  of  weighing  requires  a  high  standard  of  mainte- 
nance, in  fact,  a  standard  approaching  perfection  of  maintenance  work.  The  high 
standard  of  maintenance  is  necessary  to  insure  that  the  approach  and  retreat,  the 
ballasted  track  on  either  end  of  the  device,  and  tlie  weight  or  load-receiving  elements 
will  be  stable  in  that  the  dynamics  of  moving  cars  will  be  minimized. 

Before  a  site  is  definitely  selected,  a  test  train  or  trains  having  the  proposed 
consist  to  be  weighed  should  be  run  over  the  site.  Observers  on  both  the  engine 
and  on  the  ground  should  carefully  check  tlie  actual  train  handling  requirements  at 
the  proposed  site. 

It  is  desirable  to  prepare  a  questionnaire  which  might  point  out  a  number  of 
items  necessary  to  be  considered  for  the  proposed  location  of  the  weighing  device. 
Questions  contained  in  tlie  evaluation  are  oriented  to  stimulate  interest  in  planning 
for  operating  or  transportation  conditions,  construction,  maintenance  and  other 
factors  which  may  have  an  effect  upon  the  location  of  the  weighing  system.  There 
are  seven  general  scopes  listed  as  items  to  be  followed.  These  seven  scopes  are  out- 
lined as  follows: 

1.  Train  Handling 

1.1.  What  will  be  the  maximum  number  of  cars  handled  in  a  train  or  cut  of 
cars  at  one  time? 

1.2.  What  will  be  the  minimum  number  of  cars  handled  in  a  train  or  cut  of 
cars  at  one  time? 

1.3.  Can  the  train  speed  be  reduced  without  use  of  the  automatic  air  brake 
as  the  train  approaches  the  scale  site? 

1.4.  Must  train  be  stopped  before  being  weighed? 

1.5.  If  stopped,  can  a  speed  of  5  mph  be  attained  before  reaching  the  scale 
site  without  slack  action? 

1.6.  Will  train  brakes  be  fully  released? 

1.7.  Can  train  speed  be  controlled  using  diesel  dynamic  brake? 

1.8.  Can  train  speed  be  controlled  using  diesel  independent  brake? 

1.9.  Will  train  be  shoved  by  its  rear  end  moving  over  scale? 

1.10.  Will  train  be  bunched  moving  over  track  scale? 

1.11.  Will  engineer  use  throttle  to  pull  train  over  track  scale? 

1.12.  Will  engineer  use  more  than  throttle  position  No.  2  or  about  200  amp 
power  to  pull  train  over  scale? 

1.13.  Will  train  be  stretched  moving  over  scale? 

1.14.  If  stretched,  can  vertical  movement  of  couplers  be  observed? 

1.15.  Can  slack  action  be  prevented? 

1.16.  Will  train  drift  over  the  scale  site? 

1.17.  If  the  train  is  stopped  on  the  scale  for  any  reason,  can  it  be  started  again 
without  slack  action? 


Scales 297 

1.18.  If  stop  is  made  on  scale,  can  the  train  be  started  witliout  taking  slack? 

2.  Train  Operation 

2.1.  Will    train    be    delayed    approaching    track    scale    due    to    train    handling 
characteristics? 

2.2.  Will  following  trains  be  critically  delayed? 

2.3.  WiU  opposing  trains  be  critically  delayed? 

2.4.  Does  the  track  scale  location  permit  holding  a  train  to  be  weighed? 

2.5.  Does  the  track  scale  location  pennit  holding  a  train  that  has  been  weighed? 

2.6.  Must  all  trains  pulling  over  the  track,  pull  over  track  scale?   (Maximum 
speed  10  mph) 

2.7.  Will  difficulty  be  encountered  in  train  handling  account  of  slack  action, 
the  result  of  grade  conditions? 

2.8.  Will   difficulty   be   encountered   in   train   handling  because   of  over-speed? 

2.9.  Will  train  stall  on  scale? 

2.10.  Is  scale  location  desirable  for  bi-directional  weighing? 

2.11.  Is   scale  location   desirable   for  westbound  weighing  only? 

2.12.  Is  scale  location  desirable  for  eastbound  weighing  only? 

2.13.  Will  train  consist  be  changed  due  to  set-off  westbound? 

2.14.  Will  train  consist  be  changed  due  to  pickup  westbound? 

2.15.  Will  train  consist  be  changed  due  to  set-off  eastbound? 

2.16.  Will  train  consist  be  changed  due  to  pickup  eastbound? 

2.17.  WiU  scale  location  adversely  affect  train  operation  beyond  the  scale  site? 

2.18.  Will  train  operation  leaving  scale  be  adversely  affected  critically  account 
of  wet  rail  conditions  otherwise  not  encountered? 

3.  Physical  Characteristics 

(Witliin  200  car  lengths  maximum  cut  or  train  length  in  botli  directions  from 
track  scale  location) 

3.1.  Is  grade  satisfactory  approaching  scale?  To  satisfy  1.9  and  1.12. 

3.2.  Is  grade  satisfactory  leaving  scale?  To  satisfy   1.9  and  1.12. 

3.3.  Is  track  alignment  less  than  4"    approaching  the  scale  site? 

3.4.  Is  track  alignment  less  than  4°  leaving  the  scale  site? 

3.5.  Can  a  train  or  cut  of  cars  move  over  the  scale  without  the  use  of  sand 
under  the  locomotive? 

4.  Easy  Accessibility  to  Scale 

4.1.  During  construction? 

4.2.  For  daily  maintenance? 

4.3.  For  supervising  operations? 

4.4.  To  prevent  vandalism? 

5.  Local  Operations 

5.1.  Will  scale  location  interfere  with  local  or  mine  run  operations? 

5.2.  Will  scale  location  adversely  afifect  local  operations? 

5.3.  Does  scale  location  require  dead  or  running  rail  design? 


298       Bulletin  656 — American  Railway  Engineering  Association 

6.  Scale  Geography 

6.1.  Will   scale  location   interfere  with   operations   during  construction  period? 

6.2.  Will  scale  be  located  so  as  to  be  affected  by  high  water  conditions? 

6.3.  Will  snow  conditions  affect  operation  of  scale? 

6.4.  Will  winter  snow  and  ice  accumulation  be  controlled? 

6.5.  Can  scale  location  be  adapted  to  bi-directional  weighing? 

6.6.  Will  scale  location  permit  push  and  pull  weighing  in  both  directions? 

6.7.  Is  scale  attendant  required?  Will  remote  ACI  be  used? 

6.8.  Is  the  use  of  a  spring  switch  at  tlie  exit  end  of  scale  pullout  track  objection- 
able? 

6.9.  Will  the  scale  be  located  within  yard  limits? 

6.9.1.  Will  the  location  of  the  device  reflect  delay  to  switching  operations? 

6.10.  WiU  the  scale  be  outside  of  yard  limits? 

6.11.  Will  operating,   transportation  or  maintenance  agreements  enter  into  the 
selection  of  a  scale  site? 

6.12.  When  the  weighing  system  fails,  what  course  of  action  will  be  followed? 
(Load  Cells)    (Cabling) 

6.12.1.  Take    trains    to    another   location   for   weighing? 

6.12.2.  Back   train   over   the   scale   installation   and   attempt  to   rerun   or 
re  weigh? 

6.12.3.  Hold  train  for  scale  to  be  repaired? 

6.13.  Is  the  location  of  the  proposed  scale  proper  from  an  operating  standpoint? 

6.14.  Would  another  location  of  the  proposed  scale  be  preferred  from  an  oper- 
ating standpoint? 

6.15.  If  another  location  should  be  considered,  please  explain. 

6.16.  What  types  of  freight  will  be  weighed  on  the  proposed  device? 

6.17.  What  types  of  cars  will  be  weighed? 

6.18.  Can  weight,   rate,   freight  charges   and  other  infomiation  be  applied  to 
"waybill"  witliout  delay  to  the  train? 

6.19.  Must   a  completed  "waybill"   document  accompany  the  car  after  it  has 
been  weighed,  or  may  it  travel  with  another  type  of  document? 

7.  Testing  Requirements 

7.1.  Will  device  location  permit  testing  at  the  required  intervals  without  undue 
delay? 

7.2.  Are  rail  cars  readily  available  for  testing  purposes? 

7.3.  Are  crews  readily  available  for  testing? 

7.4.  Is  a  static  scale  readily  available  for  coupled-in-motion  testing  procedures, 
if  it  be  necessary? 

7.5.  Does  the  static  scale  used  for  comparison  purposes  meet  a  strain  test  of 
zero  error? 

7.6.  Refer  to  AREA  Manual,  Chapter  14,  Part  S— Scales   (1973),  Items  S.1.1 
and  S.1.1.2. 


Report  of  Committee  22 — Economics  of  Railway- 
Construction  and  Maintenance 


R.  W.  Bailey 

.^Kl^m^ 

F.  S.  Barkeh 

/^^^ 

A.  S.  Barr 

/              "  .^sSitll 

L 

C.  D.  Barton 

A.    BORXHOFT 

J.  W.  Brent 
R.  G.  Brohaugh 

^jM 

i 

J.  S.  Busby 

r 

L.  B.  Cann,  Jr. 

^'^iml^^M 

1 

A.  W.  Carlson 
J.  R.  Clark 
W.  H.  Clark 
S.  A.  Cooper 
M.  H.  Dick 

H.    B.    DuRRANT 

L.  C.  Gilbert 
Wm.  Glavin 
C.  R.  Harrell 

H.    C.    MiNTEER, 

Chairm 

an 

W.  H.  Hoar 

John   Fox,  Vice 

Chairman 

B.  G.  Hudson 

P.    A.    COSGROVE, 

Secretary 

|.  C.  Hunsberger 

J.  A.  Caywood 

J.  T.  Hunter 

J.  T.  Sullivan 

R.  D.  Johnson 

J.  A.  Naylor 

C.  Johnston 

Mike  Rougas 

H.  W.  Kellogg  (E 

T.  P.  Woll 

H.  W.  Kimble 

W.  J.  Jones 

W.  E.  Laird 

A.   E.   Shaw,  Jr 

G.    LiLJEBLAD 

H.  B.  Berkshire 

L.  A.  Loggins   (E) 

R.   J.    ASCHMEYER 

J.     M.     LO-WTIY 

A.  L.  Maynard 
J.  R.  Miller 

E.  T.  Myers 

G.  M.  O'Rourke  (E) 

M.  E.  Paisley 

R.  W.  Pember 

G.  G.  Phillips 

C.  T.  PoPMA 

R.  W.  Preisendefer 

F.  L.  Rees 
M.  S.  Reid 

C.  L.  Robinson 

G.  E.    SCHOLZE 

H.  W.  Seeley 
R.  G.  Simmons 
N.  E.  Smith 
W.  B.  Stackhouse 
J.  St.\ng 

J.  E.  Sunderland 
W.  A.  Swartz 
S.  W.  Sweet 

D.  D.  Thomas 
H.  J.  Umberger 
J.  D.  Vaughan 
I.  T.  Ward 

"G.  E.  Warfel 
G.  H.  Winter 

F.    R.    WOOLFORD    (E) 
B.    J.    WORLEY 

Committee 


(E)   Member  Emeritus. 

Those  whose   names   are   shown   in  boldface,  in  addition  to  the   chairman,   vice  chairman  and 
secretar>-,    are   the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 

Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 

A  complete  revision  of  Chapter  22  of  the  Manual  was  published  in 
Bulletin  645,  November-December  1973.  Portions  of  the  new  material 
were  reviewed  and  revised  during  the  past  year,  and  the  entire  new 
chapter,  as  revised,  has  been  approxed  by  the  Board  of  Direction.  It 
will  be  issued  in  the  1975  Manual  Supplement. 

1.  Analysis  of  Operations  of  Railways  That  Ha\e  Substantially  Reduced 
the  Cost  of  Construction  and  Maintenance  of  Way  Work. 

Progress  report,  submitted  as  information    page  301 

2.  Study   to   Establish   New  Equated  Mileage  Parameters. 
Study  is  in  progress  and  will  be  continued. 

3.  Economics  of  Producing  Continuous  Welded  Rail  by  In-Track  Welding. 
Study  has  been  made  and  a  report  on  this  subject  will  be  submitted 
in  the  committee's  next  report. 


299 


300       Bulletin  656 — American  Railway  Engineering  Association 

4.  Use  of  Track  Analyzer  Car  in  Inspection  of  Track  and  Maintenance 
Planning. 

A  progress  report  is  being  prepared. 

5.  Comparative  Costs  of  Cleaning  Ballast  Vs.  Ballast  Replacement  in 
Track  Rehabilitation. 

Final  report,  submitted  as  information    page  312 

6.  Economics  of  Installing  Bonded  Insulated  Joints  in  Field  Vs.  Shop 
Fabrication,  and  Economics  of  Bonded  Joints  Vs.  Field  Welds  to 
Connect  CWR. 

Final  report,  submitted  as  information    page  318 

7.  Determine  the  Economics  of  Work  Equipment  Vs.  Small  Machines  or 
Hand  Labor  on  High-Density  Lines  with  Limited  Track  Time. 

No  report. 

The  Committee  on  Economics  of  Railway 
Construction  and  Maintenance, 

H.  C.  MiNTEER,  chairman. 


Cljarles!  3^ap  Mvigfyt 

1885=1974 

Charles  Ray  Wright,  retired  assistant  chief  engineer  of  the  former  New  York, 
Chicago  &  St.  Louis  Railroad  (now  part  of  the  Norfolk  &  Western  Railway),  passed 
away  at  his  home  in  Cleveland,  Ohio,  on  September  4,  1974,  at  the  age  of  89. 

Mr.  Wright  was  born  at  Ravenna,  Ohio,  on  June  10,  1885.  He  was  educated  in 
the  public  schools  and  the  Case  Institute  of  Applied  Science  and  entered  the  service 
of  the  NYC  &  St  L  in  the  engineering  department  on  April  16,  1906.  After  serving 
in  various  positions  in  the  engineering  department,  he  was  appointed  division 
engineer  on  September  15,  1919,  serving  in  that  capacity  on  several  divisions  until 
his  appointment  as  assistant  chief  engineer  on  September  1,  1940.  He  retired  on 
July  1,   1955,   after  more  than  49  years  of  continuous  railroad  service. 

Mr.  Wright  joined  the  AREA  in  1920  and  was  for  many  years  an  active  and 
valuable  member  of  Committee  22.  After  his  retirement,  he  was  elected  a  Member 
Emeritus. 


Economics  of   Railway   Construction   and    Maintenance 301 

Report  on   Assignment    1 

Analysis  of  Operations  of  Railways  That  Have 

Substantially  Reduced  the  Cost  of  Construction 

and  Maintenance  of  Way  Work 

J.  T.  Sullivan  (chairman,  subcommittee),  Arlie  Bornhoft,  L.  B.  Cann,  Jr.,  A.  W. 
Carlson,  W.  H.  Hoar,  B.  G.  Hudson,  R.  W.  Preisendefer,  W.  B.  Stackhouse, 
D.  D.  Thomas,  J.  T.  Ward,  H.  E.  Wilson. 

This  report  is  submitted  as  information.  It  deals  with  the  Canadian  Pacific 
Limited,  Weston  Frog  and  Switch  Manufacturing  Shop  at  Winnipeg,  Manitoba, 
Canada.  This  report  further  deals  with  the  double-tracking  of  the  Canadian  National 
Railways'  Prairie  Region  utilizing  concrete  crossties  and  welded  rail.  Information 
for  this  report  was  obtained  in  conjunction  with  a  meeting  of  Committee  22  held 
on  June  9  and  10,  1975,  at  Winnipeg. 

The  CP's  Weston  Frog  and  Switch  Manufacturing  Shop  fabricates  all  types 
of  special  trackwork  products  for  exclusive  use  on  the  CP  system.  Research,  develop- 
ment, and  engineering  is  performed  by  the  office  of  the  chief  engineer  with  all 
trackwork  production  under  the  supervision  of  the  motive  power  and  rolling  stock 
department  in  accordance  with  CP  and  AREA  specifications. 

The  present  shop  is  the  outgrowth  of  two  separate  system  shops  now  integrated 
into  one  shop  centrally  located  at  the  mid-point  of  the  CP  system.  Research  for  the 
modernization  of  this  shop  started  in  1969  with  complete  investigation  into  each 
manufacturing  phase  to  facilitate  use  of  existing  machinery  and  select  die  most 
modern  equipment  to  meet  present  and  future  trackwork  production  requirements. 
Originally,  the  former  shops,  located  at  Winnipeg  and  Montreal,  employed  approxi- 
mately 145,  but  with  modernization  and  improved  manufacturing  techniques,  this 
force  has  been  reduced  to  75,  including  supervision.  Shop  construction  commenced 
in  1971  in  conjunction  with  machinery  procurements,  etc.,  and  trackwork  production 
continued  on  a  reduced  scale.  Completion  of  the  shop  was  in  late  1972,  although 
the  CP  is  continually  upgrading  with  small  machines,  tooling,  jigs,  fixtures  to  con- 
stantly improve  techniques  and  productivity. 

This  shop  manufactures  parts  for  a  complete  turnout,  including  heel-block 
assemblies,  guard  rails,  switch  stand  assemblies,  plates,  switch  points,  frogs,  and  bolts. 
Also,  special  rail  assemblies,  rail-bound  manganese  and  diamond  crossings,  and 
double-slip  switches  are  fabricated.  Insulated  gage  plates,  riser  slide  plates,  turnout 
plates,  special  flat  seat  tie  plates,  and  miscellaneous  cut  seat  plates  are  produced. 

The  rail  required  for  trackwork  products  is  brought  into  the  shop  area  via  rail 
where  it  is  ofl:-loaded  by  overhead  gantry  cranes.  The  cranes  then  handle  the  rail 
into  a  cropping  saw  where  it  is  cut  to  various  lengths  for  product  manufacture.  From 
tliis  location,  the  precut  sections  are  moved  into  tlie  main  shop  building  by  means  of 
a  conveyor  which  passes  through  the  wall  of  the  building.  Once  inside,  the  sections 
are   handled  by   overhead  cranes   to   the   various  product  manufacturing  locations. 

When  manufacturing  switch  points,  the  necessary  straps  are  fastened  to  the 
precut  rail  sections,  the  clamped  assembly  is  placed  into  a  drill  wlicre  all  holes  are 
drilled  simultaneously,  and  from  there,  the  drilled  section  is  passed  to  milling 
machines  which  are  programmed  for  final  machining  of  the  appropriate  point.  The 


302       Bulletin  656 — American  Railway  Engineering  Association 

two  mainline  rail  sections  for  the  CP  are  132  RE  and  115  RE  with  considerable 
maintenance  requirements  for  existing  130  RE-HF  and  100  RE-HF  sections.  Switch 
point  production  in  these  sections  consists  of  11  ft,  16  ft  6  in.,  and  22  ft  lengths 
with  limited  quantities  of  13  ft  and  39  ft  cun'ed  points  for  use  in  No.  20  turnouts. 

The  CP  uses  the  built-up  design  guard  rail  with  adjustable  blocks  with  all 
132-lb  and  115-lb  rails  produced  in  special  chrome  rail.  Guard  rail  lengths  are  8  ft 
3  in.,  11  ft  6  in.,  13  ft  8  in.,  and  18  ft.  Manganese  steel  guard  rails  are  no  longer 
used  on  the  CP. 

Complete  heelblock  assemblies  for  four-hole  design,  fixed  position,  with  no 
sliding  heel  are  fabricated.  The  assemblies  consist  of  block,  joint  bars  and  shoulder 
bolts,  complete. 

Switch  stands  are  complete  assemblies  for  use  as  ground,  low  intermediate  and 
high  position  complete  with  eye  bolts,  masts,  and  targets. 

Rail-bound  manganese  steel  frogs  are  machined  and  assembled.  In  addition, 
some  spring  frogs  are  manufactured  for  specific  locations.  To  supplement  new  frog 
requirements,  the  CP  has  two  reclamation  frog  shops  located  at  Montreal  and  Leth- 
bridge.  The  rebuilds  are  primarily  rail-bound  manganese  with  some  built-up  and 
solid  manganese. 

All  new  frog  construction  utilizes  special  chrome  rail  M'ith  explosive  depth 
hardening  of  the  manganese  steel  insert  castings.  Approximately  15  miles  from  the 
shop  area,  the  CP  has  an  area  for  perfonnance  of  depth  hardening.  At  this  location, 
there  is  a  work  platform  approximately  5  ft  in  height,  10  to  12  ft  in  width,  and 
approximately  30  ft  long.  This  structure  is  built  with  wooden  timber  sidewalls 
witli  the  center  filled  with  sand.  Transport  to  this  site  is  by  specially  equipped  truck 
with  a  bed  and  boom  for  handling  the  steel  inserts.  The  truck  is  also  equipped  with 
a  special  box  for  movement  of  explosives  from  the  storage  magazine  to  the  work 
platform. 

The  casting  is  placed  on  the  sand  bed  of  the  platform,  thoroughly  cleaned,  and 
adhesive  added  to  the  clean  casting  before  applying  sheet  type  explosive.  The  ex- 
plosion  is   then   set   off   from   a   remote  position   by  a  detonator,   with   each  casting 


immJ 

i£^^ 

I 

xm     «  - 

'""^^gmj 

Fig.    1 — Preparing    frog    casting    for    depth    hardening. 


Economics  of   Railway   Construction   and    Maintenance 303 


Fig.  2 — Frog  casting  ready  for  explosii 


304       Bulletin  656 — American  Railway  Engineering  Association 

receiving  three  blasts.  Tlie  first  shock  results  in  approximately  300  Brinell  hardness, 
the  second  340  to  350,  and  the  third  375.  Depth  hardening  by  this  process  has  proven 
able  to  proN'ide  a  service  life  of  100,000,000  to  120,000,000  tons  where  previously 
60,000,000  tons  was  normal  for  a  frog  casting  on  the  CP  line.  At  the  present  time, 
this  method  of  depth  hardening  costs  approximately  $250  per  casting. 

Weston  Fhog  and  SwrrcH  Manufacturing  Shop 
1974  Production 

Switch  points    (varying  lengths)    1,663  each 

Guard  rail   assembly    492  each 

Heelblock  assembly 294  each 

Switch   stand   assembly    484  each 

Plates    ( various    types )     23,000  each 

Frogs   ( new )    454  each 

Frogs    ( reclaimed )     600  each 

Special   rail   assemblies    2,641  tons 

This  modern  shop  is  well  equipped  to  supply  the  needs  of  the  CP. 
The  CP  is  well  pleased  with  the  results  of  their  operation  and  feel  that  the 
expenditures   for   construction   have  been  economically  justified  by  results  to  date. 

DOUBLE-TRACKING  ON  THE  CANADIAN  NATIONAL 

On  June  10,  Committee  22  inspected  new  mainline  hack  construction  being 
performed  by  the  Canadian  National  Railways  on  its  Prairie  Region.  The  CN  is 
constructing  a  second  mainline  from  Winnipeg  to  Portage  on  the  Rivers  subdivision, 
Mile  6.87  to  Mile  52.17.  The  project  calls  for  the  installation  of  two-directional 
double-track  CTC  with  intermediate  signals  for  following  moves.  Track  will  be 
signalled  for  80  mph  operation.  Double  high-speed  crossovers  will  be  installed  at 
Mile  14.3  and  a  passing  track  will  be  constructed  at  Mile  32  to  Mile  33.5  which 
is  to  be  situated  between  the  two  main  tracks  where  it  may  be  used  as  a  crossover 
as  well  as  for  overtake  in  both  directions  by  trains  on  either  track.  At  the  Assiniboine 
River  bridge.  Mile  50.5,  single  track  will  be  maintained  wih  No.  20  equilateral 
turnouts  placed  at  both  ends  wliich  will  give  additional  capabilities.  The  new  aline- 
ment  will  have  a  paralleling  track  on  15-ft  track  centers  with  the  existing  line. 

The  track  section  is  to  be  built  using  concrete  crossties  on  24-in.  centers  carrying 
132  RE  rail  in  1,170-ft  strings.  Project  calls  for  496,566  lin  ft  of  132-lb  continuous 
welded  rail.  The  strings  are  being  joined  by  thermite  welding  in  the  field.  Approxi- 
mately 121,000  concrete  crossties  will  be  installed.  New  turnouts  will  include  four 
No.  20  equilaterals,  eight  No.  20  turnouts,  eighteen  No.  12  turnouts  and  one  132-lb 
manganese  diamond.  Three  prestressed  bridges  are  to  be  located  at  Mile  17.3,  Mile 
30.8  and  Mile  49.3.  This  project  will  include  12  power  switches,  34  CTC  signals, 
approximately  250,000  ft  of  underground  cable,  750,000  ft  of  line  wire,  170  DC 
track  circuits,  and  12  compressed  air  snow  removal  systems  at  four  sites. 

Grading  is  being  performed  by  a  contractor,  and  it  is  estimated  that  450,000 
cu  yd  of  material  will  be  moved  when  constructing  the  subgrade.  Approximately 
392,000  cu  yd  of  sub-ballast  is  to  be  brought  by  air-dump  cars  from  River  Manitoba, 
a  200-mile  round  trip.  The  subgrade  cross-section  is  to  have  no  less  than  21  in.  of 
pit-run  sub-ballast  topped  with  12  in.  of  crushed  rock  ballast  under  the  tie,  giving 
full  depth  of  crushed  rock  of  18  in.  once  the  cribs  have  been  filled.  Approximately 

(Text  continued  on  page  309) 


Economics  of   Railway   Construction   and    Maintenance  305 


Fig.  3 — Concrete  ties  and  welded  rail  on  the  CN. 


306       Bulletin  656 — American  Railway  Engineering  Association 


' "  ^  ^>?- ''  i. 


Fig.  4 — Thermite  welding  on  the  CN. 


Economics  of   Railway   Construction   and    Maintenance 307 


Fig.  5 — No.  20  turnout  under  construction. 


308       Bulletin  656 — American  Railway  Engineering  Association 


Fig.   6 — Unloading   concrete   crossties   onto   the   roadbed. 


Economics  of   Railway   Construction   and    Maintenance  309 


Fig.  7 — Distributing  and  spacing  concrete  crossties. 

238,000  cu  yd  of  crushed-rock  ballast  will  be  brought  in  by  work  train  from  Wat- 
comb,  a  600-mile  round  trip. 

Concrete  crossties  are  transported  on  special  tie  cars  with  each  car  having  six 
bundles  of  30  ties  each,  or  180  ties  per  car.  The  ties  are  off-loaded  tlirough  use  of 
an  off-track  mobile  crane  driving  on  compacted  subgrade  and  utilizing  a  specially 
manufactured  steel  tie-handling  rack.  The  rack  is  placed  under  the  bundle,  lifted 
from  the  car,  and  placed  at  intervals  on  two  wooden  ties  positioned  on  the  subgrade. 
Unloading  of  ties  is  dependent  upon  the  amount  of  track  time;  however,  the  operation 
is  capable  of  unloading  as  many  as  eight  carloads  per  worktrain  day. 

Once  the  ties  are  unloaded  on  the  roadbed,  they  are  distributed  tlirough  the  use 
of  a  rubber-tired  straddle-axled  crane  and  anodier  special  lifting  device.  The  ties 
are  handled  six  at  a  time  from  the  bundles  and  placed  at  tlie  proper  spacing.  Proper 
alinement  of  ties  is  controlled  by  a  specially  made  gage  which  runs  on  the  near  rail 
of  the  adjacent  track.  The  concrete  crossties  are  manufactured  to  CN  specifications, 
rail  fasteners  are  applied  by  a  six-man  gang  using  sledge  hammers;  however,  this 
process  is  to  be  mechanized  in  the  near  future. 

Once  ties  are  unloaded  and  properly  spaced,  welded  rail  is  unloaded  from  a  rail 
train  to  tlie  ties.  The  rail  is  off-loaded  from  tlie  end  of  a  rail  car  of  the  worktrain 
occupying  the  dead  track  to  specially  designed  rollers.  This  eliminates  delays  incurred 
by  heavy  mainline  traffic.  Once  the  rail  is  placed  on  tlie  tie  seat,  the  tie  pad  is 
applied,  after  which  the  rail  is  fastened  to  the  tie. 

In  summary,  the  project  which  started  in  1973  is  scheduled  for  completion 
in  1976  and  will  result  in  a  double-track  mainline  track  structure  consisting  of 
concrete  crossties  and  132-lb  welded  rail.  In  1974  this  section  of  tlie  CN's  track 
handled  40  trains  per  day  with  43.8  million  gross  tons.  Annual  tonnage  is  expected 
to  increase  to  80  million  gross  tons  in  1980  and  85  million  gross  tons  in  1985. 


310       Bulletin  656 — American  Railway  Engineering  Association 


Fig.  8 — Applying  rail  fasteners. 


Economics  of   Railway   Construction   and    Maintenance  311 


Fig.  9 — Portable  roller  used  in  unloading  welded  rail  from  worktrain  to  concrete 

ties  on  roadbed. 


312       Bulletin  656 — American  Railway  Engineering  Association 

Report  on  Assignment  5 

Comparative  Costs  of  Cleaning  Ballast  Versus  Ballast 
Replacement  In  Track  Rehabilitation 

W.  J.  Jones  (chairman,  subcommittee),  A.  S.  Barr,  J.  S.  Busby,  J.  R.  Claiuc,  H.  W. 
Kellogg,  Guy  Liljeblad,  E.  T.  Myers,  Mike  Rougas,  G.  E.  Scholze,  J.  E. 
Sunderland. 

Yovir  subcommittee  submits  the  following  reiJort  as  information.  Comments  and 
criticisms  are  welcome. 

Cutbacks  in  rail  and  tie  renewals  are  commonplace  during  periods  of  depressed 
business  activity  because  of  tlie  large  amount  of  money  involved  in  such  items.  To 
a  lesser  extent,  retrenchments  also  occur  in  reballasting  programs.  However,  by  and 
large,  a  certain  amount  of  maintenance  money  is  expended  for  ballast  in  tlie  day-to- 
day maintenance  of  track. 

In  the  aggregate,  the  value  of  ballast  that  is  consumed  annually  represents  a 
sizeable  sum.  The  AAR  reported  that  Class  I  carriers  spent  $36,837,000  for  ballast 
in  1973  and  $45,183,000  in  1974,  excluding  transportation  costs. 

Ballast  Is  Indispensable  to  the  Safety  of  Track 

Unless  a  full  ballast  section  (of  quality  material)  is  maintained  at  all  times, 
track  will  develop  irregularities  in  surface,  line,  and  gage.  The  nmnber  of  slow  orders 
required  will  rise.  Joint  pumping  will  increase,  accelerating  joint  wear  and  rail-end 
batter.  Partially  exposed  ties  are  more  vulnerable  to  destruction  by  a  derailed  wheel. 
Threat  of  sun-kinks  will  multiply.  The  overall  result  will  be  a  sharp  increase  in  the 
cost  of  ordinary  track  maintenance  or  a  reduction  in  maintenance  standards.  Thus, 
it  is  apparent  that  a  relatively  substantial  quantity  of  ballast  must  be  provided  almost 
daily,  on  almost  all  roads. 

There  are  330,000  miles  of  railroad  track  in  this  country.  Assuming  an  average 
of  2,500  cu  yd  of  ballast  per  mile  and  a  cost  of  $4.00  per  yard  for  ballast  in  place 
(conservative  at  today's  prices),  we  find  that  ballast  represents  an  asset  worth  $3.3 
biUion.  Accordingly,  everything  practical  should  be  done  to  protect  this  investment 
and,  concurrendy,  to  economize  in  ballast  expenditures,  wherever  possible. 

An  adequate  ballast  section  is  indispensable  to  the  efficient  maintenance  of 
every  class  of  track.  Basically,  ballast  consists  of  selected  materials  placed  on  the 
roadbed  for  the  purpose  of  holding  the  track  to  the  desired  line  and  surface.  For 
ballast  to  be  considered  "adequate,"  it  must  possess  specific  physical  properties  and 
it  must  meet  fixed  functional  requirements. 

Requirements  of  Good  Ballast 

Good  ballast  should  be  sound,  hard,  tough,  clean,  heavy,  sharp-faced  and 
nonconductive.  Desirably,  ballast  should  be  available  in  abundant  supply,  close  to 
the  point  of  use,  and  at  an  economical  price  per  cubic  yard.  Ballast  gradation  between 
minimum  and  maximum  allowable  sizes  should  be  such  as  to  pennit  ballast  to  com- 
pact readdy  in  the  track. 

To  be  functionally  satisfactory,  ballast  should: 

1.  Provide  a  firm  bearing  for  the  ties  and  distribute  the  wheel  loads  uniformly 
over  the  roadbed. 


Economics  of   Railway   Construction   and   Maintenance 313 

2.  Provide  propei-  drainage. 

3.  Afford  a  means  for  the  elimination  or  reduction  of  capillary  action. 

4.  FiU  the  spaces  behveen  the  ties  and  form  a  shoulder  from  tie  ends  to  sub- 
grade,  thereby  holding  the  ties  in  the  proper  position,  while  resisting 
lateral  forces  exerted  by  the  wheel  against  the  rail. 

5.  Retard  vegetal  growth  within  tlie  track  area. 

6.  Facilitate   track  work,   particularly  during  periods  of  rainy  weather. 

7.  Provide  resilient  and  elastic  support  of  ties  and  rail. 

Foul  Ballast  Adversely  Affects  Maintenance 

With  respect  to  the  physical  properties  of  good  ballast,  aU  of  them  are  relatively 
permanent  by  nature,  except  one — cleanliness.  Ballast  commences  to  get  dirty  soon 
after  it  is  put  in  track  and  subjected  to  traffic.  Fine  particles  of  dirt  and  other  foreign 
matter  enter  the  ballast  from  spilled  lading,  locomotive  sanding,  wind-  and  water- 
carried  soils,  subgrade  material  working  into  the  ballast,  and  attrition  of  the  ballast 
itself. 

Water  enters  the  ballast  from  above  as  rainfall  and  from  below  by  capillary 
action.  When  water  and  dirt  combine,  drainage  is  impaired.  Vegetal  growth  is  en- 
couraged; ties  pump;  line  and  surface  deteriorate;  and  wear  of  rail,  fastenings  and 
ties  accelerates.  Ballast  loses  its  resiliency  and  is  no  longer  capable  of  properly 
distributing  loads  from  the  track  to  the  subgrade.  Moreover,  as  determined  recently 
in  the  Track-Train  Dynamics  studies,  increased  lateral  forces  are  encountered  in 
track  with  frozen  ballast,  or  tightly  consolidated  ballast  polluted  by  sand. 

As  the  ballast  becomes  fouled,  track  maintenance  becomes  more  difficult  and 
more  expensive.  The  condition  soon  reaches  the  point  that  something  must  be  done. 
The  maintenance  manager  must  decide  whether  to  clean  part  or  all  of  the  ballast 
section,  plow  out  the  dirty  ballast  and  provide  an  entire  new  section  of  fresh  ballast, 
or  make  a  nominal  surfacing  raise  on  existing  ballast  and  fill  in  the  voids  surrounding 
the  ties  with  fresh  ballast. 

Source  of  Information 

In  order  to  learn  what  is  being  done  in  this  regard  and  to  develop  the  cost 
associated  with  current  practices,  a  questionnaire  was  sent  to  representatives  of  30 
railroads.  Twelve  written  replies  were  received  and  verbal  infonnation  was  supplied 
from  four  others.  The  answers  were  tabulated  and  unweighted  averages  computed 
without  regard  for  miles  of  lines  maintained,  tonnages  carried,  etc. 

The  replies  were  quite  similar  and  are  summarized  as  follows: 

1.  Quality  ballast  is  preferred  over  inferior .  grades,  even  though  first  cost 
is  greater  and  longer  haul  involved. 

2.  Ballast  supply  is  adequate  for  all  needs  for  all  responding  roads. 

3.  Ballast  cars  are  in  short  supply  on  two-thirds  of  the  roads  responding  to 
questionnaire. 

4.  Average  cost  of  ballast  is  $2.70  per  cubic  yard,  FOB  car.^ 

5.  Ballast  is  hauled  an  average  of  155  miles  from  source  to  point  of  use. 

6.  Ballast  moves  on,  and  is  unloaded  by,  through  freight  in  the  majority 
of  cases.  When  not  unloaded  by  through  freight,  cars  are  set  out  for 
pick-up   and  dmnping  by  work  train. 

7.  Average  cost  of  work  train  is  $525  for  a  12-hour  day. 


1  All  prices,  wages,   rates,  etc.,   are  based  on   1974   figures. 


314       Bulletin  656 — American  Railway  Engineering  Association 

8.  In  retimbering  ahead  of  surfacing  operation,  an  average  of  611  cross 
ties  per  mile  are  installed  by  the  tie  gang  at  an  average  labor  cost  per  tie 
of  0.65  man-hour.^  This  compares  to  0.19  man-hour  per  tie  where  ties 
are  installed  in  conjunction  with  operation  of  undertrack  plow.  (Cost 
figure  for  ties  renewed  while  undercutting-cleaning  was  not  available.) 

9.  An  average  of  414  cu  yd  of  ballast  per  mile  are  required  for  2-in.  sur- 
facing raise  and  700  cu  yd  for  3-in.  raise,  compared  to  2,528  cu  yd 
behind  plow  and  525  cu  yd  with  undercutter-cleaner. 

10.  An  average  of  420  track  feet  per  hour  are  undercut  and  cleaned,  6  in. 
below  bottom  of  ties.  Daily  production  with  undertrack  plow  is  3,660  ft. 

11.  Surfacing  raises  are  made  every  4  to  5  years.  Interval  between  under- 
cutting-cleaning is  9  years.  Customarily,  the  undertrack  plow  is  used 
only  once  at  a  given  location,  to  dispose  of  an  inferior  quality  or  heavily 
polluted  ballast. 

12.  The  majority  of  the  respondents  advised  that  their  interest  in  under- 
cutting-cleaning would  heighten  if  they  could  be  assured  of  1,000  ft  per 
hour   production. 

Advantages   of  Undercutting-Cleaning 

1.  Removing  all  the  ballast  from  the  track  to  a  specified  depth  below  the 
bottom  of  tie,  screening  out  the  dirt,  sand  and  otlier  undesirable  material, 
and  returning  tlie  clean  ballast  to  the  track  for  making  an  appropriate 
raise  is  the  only  sure  way  of  restoring  resiliency  and  drainage  to  the  track. 

2.  Established  grades  are  preserved.  This  is  particularly  important  with 
respect  to  meeting  existing  track  crossings  and  road  crossings  at  grade, 
bridge  ends,  station  platforms  and  turnouts.  Also,  established  grade  rela- 
tionship with  adjoining  tracks  is  not  disturbed,  thus  precluding  the  need 
for  reworking  or  raising  walkways  and  inner  track  areas. 

3.  Vertical  clearances  in  tunnels  and  beneath  overhead  structures  are  not  ad- 
versely afi^ected.  Occasionally,  oppoitunity  exists  to  improve  upon  tlie 
clearance. 

4.  Subgrade  widths  remain  unaltered,  thereby  avoiding  the  expense  involved 
in  restoring  or  widening  embankments  to  adequately  support  the  track  or 
to  prevent  loss  of  ballast. 

5.  It    helps    to    preserve    dwindling    resources    of   ballast    material. 

Disadvantages 

1.  Rate  of  progress  with  present  equipment  is  relatively  slow.  Usually  a 
minimum  of  three  to  four  hours  undisturbed  track  occupancy  is  necessary 
to  justify  the  expense  of  set-up  and  making  run-off.  Excessive  train  delays 
are  frequent.  (Improvements  are  being  made  in  the  design  and  method 
of  operation  of  the  equipment  aimed  at  speeding  up  undercutting- 
cleaning.  ) 

2.  A  substantial  portion  of  ballast  is  wasted.  For  efiiciency  of  cleaning  opera- 
ation,  screen  openings  must  be  large  enough  for  pollutants  to  pass  freely, 
at  an  acceptable  rate  of  production.  Too  large  a  screen  opening  results 
in  an  increase  in  ballast  wastage.  Too  small  an  opening  causes  the  screen 
to  overload  or  results  in  a  less  than  satisfactory  job  of  cleaning. 


2  Average  hourly  rate  for  laborer  is  $4,624,   and  for  foreman  $5,565. 


Economics  of   Railway   Construction   and   Maintenance 315 

3.  During  periods  of  restricted  maintenance  allowances,  there  may  not  be 
sufficient  allowance  to  support  the  operation. 

4.  To  be  economically  feasible,  there  must  be  enough  work  for  the  under- 
cutter-cleaner  to  justify  the  cost  of  the  equipment. 

5.  The  cleaning  operation  produces  a  lot  of  dust  which  is  drawing  more  and 
more  attention  by  ecologists.  Some  incorporated  areas  prohibit  the  use 
of  ballast  cleaning  equipment  and  issue  citations  when  the  equipment  is 
operated. 

Shoulder  Ballast  Cleaning 

Shoulder  ballast  cleaning  produces  worthwhile  benefits.  However,  this  operation 
is  not  to  be  performed  in  lieu  of  undercutting-cleaning  nor  is  shoulder  ballast 
cleaning  considered  as  a  substitute  for  a  surfacing  raise. 

The  ballast  in  the  shoulders  makes  up  35%  to  40%  of  the  total  ballast  section. 
It  is  essential  for  the  shoulders  to  be  kept  open  so  that  water  will  not  impound  in 
the  track.  Keeping  the  shoulders  clean  will  aid  in  preventing  the  formation  of 
"mud-socks"  at  tie  ends.  Additionally,  clean  shoulders  will  permit  some  leaching  out 
of  dirt  and  sand  from  the  "cribs"  and  "eyes."  Unfortunately,  however,  once  the 
ballast  under  the  ties  is  fouled  and  consolidated  to  tire  point  that  it  has  lost  its 
cushion,  and  drainage  is  impaired,  shoulder  cleaning  cannot  materially  mitigate  the 
problem. 

Application  of  Undertrack  Plow 

It  is  not  economical  to  contend  with  an  inferior  grade  of  ballast.  For  years 
native  materials,  gravels,  cinders,  soft  sedimentary  rock  and  other  materials — 
locally  available — were  frequently  used  as  ballast  on  branch  lines,  secondary  mains 
and — in  some  cases — on  primary  mains,  due  to  the  ease  of  accessibility  and  cost  of 
such  ballast.  However,  the  increase  in  axle  loads  and  die  increase  in  train  speeds 
soon  proved  the  inadequacy  of  subquality  ballast.  The  sooner  it  is  replaced  with 
quality  ballast,  the  better,  from  all  standpoints. 

The  quickest  and  most  economical  way  to  dispose  of  unwanted  ballast  is  by 
use  of  the  undertrack  plow.  There  are  locations,  however,  where,  due  to  physical 
restrictions  and  clearances,  it  is  not  feasible  to  plow,  e.g.,  through  station  platforms, 
in  tunnels   and  beneath  overhead  structures  with  tight  vertical  clearance. 

The  principal  advantage  of  the  imdertrack  plow  in  skeletonizing  track  is  its 
high-production  capacity.  Other  advantages  are:  ( 1 )  Ties  are  renewed  at  very  low 
unit  cost,  (2)  Selection  of  ties  for  renewal  is  facilitated  and  a  better  job  of  marking 
is  possible  since  the  whole  tie  is  visible,  and  (3)  Where  necessary,  track  realignment 
is   performed  with  minimum   efl^ort. 

Disadvantages  are:  (1)  Track  must  be  occupied  by  maintenance  crew  for  a 
relatively  long  period  of  time  before  track  is  readied  for  resumption  of  traflBc;  (2) 
The  operation  usually  results  in  heavy  tie  renewals,  which  could  represent  too  large 
a  percentage  of  the  available  tie  program;  (3)  Adjustments  must  be  made  in  grade 
at  crossings,  bridge  ends  and  switches,  else  other  methods  must  be  employed  to 
remove  ballast  in  approach  to  such  fixed  grade  points;  ( 4 )  A  large  quantity  of  ballast 
must  be  available  on  a  daily  basis  to  fill  in  the  skeletonized  track.  This  requires  an 
adequate  supply  of  ballast  cars  to  keep  the  program  moving  forward  (two-thirds 
of  the  respondents  to  questionnaire  advised  that  ballast  cars  were  in  short  supply); 
and  (5)  Slow  orders  are  usually  extensive  in  length  and  duration  and  involve 
comparatively  low  speeds. 


316       Bulletin   656 — American  Railway  Engineering  Association 

Pros  and  Cons  in  Making  Surfacing  Raises 

Historically,  it  has  been  the  practice  on  the  majority  of  railroads  in  this  country 
for  tracks  to  be  gi\'en  periodic  surfacing  raises  to  improve  the  riding  quality.  Except 
for  special  locations,  such  as  on  mountain  grades  where  locomotive  sanding  occurs, 
and  in  isolated  locations,  e.g.,  where  ballast  section  has  been  fouled  with  silt  from 
Hooding,  very  little  out-of-face  cleaning  of  ballast  is  done.  The  majority  of  returns 
to  questionnaire  indicates  that  ballast  cleaning  has  never  been  performed  on  those 
properties.  Instead,  whenever  ballast  fails  to  function  as  intended,  a  nominal  track 
raise  is  made  on  the  old  ballast  and  fresh  ballast  is  brought  in  to  fill  the  voids 
around  the  ties. 

With  modern  machinery,  supported  by  a  relatively  small  crew,  it  is  possible 
to  surface  track  quickly  and  economically.  Other  advantages  are:  (1)  Maintenance 
of  existing  tie  bed  compaction,  (2)  Does  not  require  taking  track  out  of  service 
very  long,  and  (3)  Does  not  require  a  large  quantity  of  ballast  at  any  one  time,  nor 
a  large  number  of  ballast  cars. 

Disadvantages  are  considerable.  Principal  ones  are:  (1)  Benefits  are  short-lived 
and  value  of  new  ballast  is  not  fully  realized  since  track  is  raised  on  existing  ballast 
(with  vaiying  degrees  of  contamination)  and  new  ballast  is  spread  as  top-coat  on 
top  of  die  ballast  section;  (2)  What  clean  ballast  there  is  in  the  cribs  that  finds  its 
way  beneath  the  ties  is  subject  to  rapid  contamination  from  the  dirty  ballast  below; 
(3)  Frequent  raising  of  track  surface,  coupled  with  normal  deterioration  of  embank- 
ments, results  in  placing  track  on  a  pinnacle.  To  correct  this  condition  requires 
restoration  and/or  widening  of  the  subgrade  to  prevent  loss  of  ballast  and  creation 
of  centerbound  track;  (4)  Bridge  structures  and  crossings  must  be  raised  compatible 
to  raise  in  track  grade.  This  involves  extra  expense. 


SUMMARY 

1.  A  clean  ballast  section  is  essential  to  the  economical  maintenance  of  track. 

2.  When  ballast  fouls  to  the  point  of  losing  its  resiliency  and  cushion,  the  cost 
of  track  maintenance  rises,  or  the  track  standard  must  be  reduced. 

3.  Ballast  in  track  represents  a  sizeable  investment. 

4.  Average  cost  of  high-speed  primary  main  line  ballast  is  $2.70  per  cubic  yard, 
FOB  car,  at  loading  site.  Cost  of  transporting  and  placing  ballast,  including 
ownership,  operation  and  maintenance  of  equipment  expense  plus  maintenance  of 
way  labor,  etc.,  brings  the  cost  of  ballast  in  place  to  $4.00,  or  more,  per  cubic  yard. 

5.  There  is  approximately  one-half  (0.5)  cubic  yard  of  ballast  per  lineal  foot 
of  track,  where  standard  ballast  section  calls  for  8  in.  of  ballast  under  the  tie.  This 
equates  to  a  ballast  value  in  excess  of  $2.00  per  foot  of  track. 

6.  Thus,  if  track  can  be  undercut  to  a  depth  of  8  in.  and  the  ballast  screened 
at  a  cost  of  less  than  $1.60  per  foot,  then  undercutting-cleaning  is  the  economical 
method  to  adopt.  (It  is  assumed  that  20%  of  the  ballast  will  be  lost  in  the  cleaning 
process  when  much  of  the  minus  %-m.  material  passes  through  the  screen  with  the 
dirt  and  sand. )  From  Appendix  A  we  find  that  cost  to  clean  ballast  computes  to 
$1.06  per  track  foot. 

7.  Undercutting-cleaning  provides  the  most  positive  and  practical  method  of 
restoring  ballast  to  its  original  condition.  However,  it  is  recognized  that  there  can 


Economics  of   Railway    Construction   and   Maintenance 317 


be  local  considerations  precluding  the  use  of  die  undercutter-cleaner.  In  such  cases, 
of  necessity,  other  methods  must  be  employed  to  reinstate  those  properties  and 
functions  inherent  in  good  ballast,  so  that  ballast  will  fulfill  all  of  its  intended 
functions. 

APPENDIX  A 

ESTIMATED  COST  TO  CLEAN  BALLAST  WITH 
THE  UNDERCUTTER-CLEANER 

ASSUMPTIONS 

New  machine  cost — $500,000 

Machine  life — 12  years 

Interest  at  8?  on  undepreciated  value 

ANNUAL  COST 

Depreciation    $  41,670 

Interest    21,600 

Maintenance   50,000 

Fuel  and  supplies 25,000 

Mechanic    (including    additives)     19,500     $157,770 

Labor:    (Including  additives) 

Operators    (2)    39,000 

Laborers  (Foreman  -f  8  men)    115,080       154,080 

TOTAL   $311,850 


PRODUCTION 

An  average  of  420  ft/hour,  3  hours  daily, 
working  90%  of  the  time.' 

420  X  3  X   5  X  52   (.90)   =  294,840  track  feet 

COST  TO  UNDERCUT  AND  CLEAN  PER  TRACK  FOOT  $1.06 


'  The    new    equipment    being    manufactured    offers    increased    production    and    efficiency    with 
almost   100%  assurance  of  further  economies. 


318       Bulletin  656 — American  Railway  Engineering  Association 

Report  on   Assignment  6 

Economics  of  Installing  Bonded  Insulated  Joints  in 

Field  Vs.  Shop  Fabrication  and  Economics  of 

Bonded  Joints  Vs.  Field  Welds  to 

Connect  CWR 

A.  E.  Shaw,  Jr.  (chairman,  subcommittee},  R.  J.  Aschmeyer,  A.  Bornhoft, 
W.  Glavin,  C.  R.  Harrell,  J.  R.  Miller,  G.  G.  Phillips,  D.  D.  Thomas, 
H.  J.  Umberger,  J.  T.  Ward. 

ECONOMICS  OF  INSTALLING  BONDED  INSULATED  JOINTS  IN 
FIELD  VS.  SHOP  FABRICATION 

The  bonded  insulated  joint  has  been  in  production  and  available  to  the  industry 
for  about  5  years.  Presently,  they  are  manufactured  by  at  least  3  companies  and 
in  appearance  and  construction,  they  are  very  similar.  The  joint  consists  of  a  special 
steel  joint  bar  with  a  permanently  bonded  insulation  material  on  the  side  of  the  bar 
toward  the  rail.  This  bar  is  bonded  to  the  rail  joint  by  epoxy  material  and  held  in 
place  by  either  high-strength  bolts  or  fasteners. 

The  procedure  for  installation  in  the  field  is  fairly  complex  and  must  be  ad- 
hered to  or  failures  will  result.  A  typical  instruction  for  instaUing,  broken  into 
functions,  is  as  follows: 

1.  Cut  and  Drill 

(a)  Rail  is  cut  with  rail  saw  if  necessary.  Care  must  be  taken  to  ensure  a 
vertical  cut. 

(b)  Rail  holes  are  located  using  templet. 

(c)  Rail  holes  are  drilled  with  single  rail  drill  using  flat-head  drill  bits, 
1-5/16  in. 

(d)  Grinder  deburrs  and  hones  holes  carefully.  Rail  brand  and  any  burrs  on 
rail  ends  are  ground  off. 

(e)  Rail  ends   are  flame-hardened  with  oxyacetylene  torch. 

2.  Sandblasting 

(a)  Sand-blast  rail  ends  about  19  in.  from  each  end  to  remove  all  scale  and 
rust. 

3.  Apply  Bars 

(a)  Rail  ends  are  examined  to  see  if  they  are  in  tension  or  compression. 

(b)  In  compression,  a  hydraulic  jack  opens  the  ends,  the  end  post  is  inserted, 
and  the  jack  removed. 

(c)  In  light  tension,  sufficient  anchors  are  removed  and  rails  are  pulled 
with  railpuUer  to  tlie  end  post,  and  anchors  are  replaced.  If  gap  remains, 
it  is  closed  by  heating. 

(d)  Blast-cleaned  areas  of  rails  are  washed  with  special  solvent. 

(e)  Heat  is  directed  to  the  sides  of  the  rail  until  the  top  of  the  head  reaches 
200  F. 


Economics  of   Railway   Construction   and    Maintenance 319 


(f)  At  temperature,  the  blast-cleaned  area  is  lighdy  washed  widi  solvent, 
the  rail  hole  bushings  are  installed  and  the  joint  bars,  which  have  been 
spread  with  epoxy  cement  during  die  preparation  of  the  rails,  are  put 
in  place. 

(g)  High-strength  bolts  or  fasteners  are  used.  They  are  put  through  one 
bar  and  the  bar  is  moved  into  position  against  the  rail.  This  allows  a 
visible  check  to  see  that  they  do  not  push  out  the  rail  hole  bushings. 
The  odier  bar  (flange  side)  is  mounted  on  the  protruding  bolts  or 
fasteners. 

(h)   The  bolts  or  fasteners  are  pulled  up  from  the  center  alternately  to  each 

end. 
(i)    Heat  is  applied  and  bars  are  brought  to  200  F.  At  200  F,  heat  is  cut 

back  and  bars  maintained  at  200  F  for  10  minutes. 

4.  In  Service 

(a)  If  rail  traffic  is  expected,  the  joint  is  cooled  to  150  F  with  water  spray 
from  a  garden  sprayer. 

(b)  Because  elapsed  time  of  all  fimctions  is  approximately  one  hour,  however, 
because  advance  joints  are  in  preparation,  the  average  time  is  much 
lower. 

Some  railroads  feel,  to  ensure  quality  control,  they  cannot  use  field-installed 
joints;  therefore,  they  have  the  bonded  insulated  joint  made  up  in  a  piece  of  rail 
at  a  shop  and  dien  this  section  of  rail  is  installed  in  track  by  field  welding  the  two 
ends  or  the  use  of  standard  joint  bars.  An  analysis  has  been  made  of  various  railroads 
and  transit  companies  comparing  the  installation  of  bonded  insulated  joints,  which 
are  fabricated  at  a  shop,  shipped  to  the  field,  and  then  installed  in  track  vs.  bonded 
insulated  joints  installed  directly  in  track. 

A  questionnaire  was  sent  to  32  railroads  and  6  transit  companies  representative 
of  the  industry.  Twenty-six  railroads  and  five  transit  companies  responded.  Of  these 
companies,  all  but  three  railroads  are  using  bonded  insulated  joints  to  varying 
degrees.  Three  transit  companies  use  them,  one  does  not,  and  one  could  supply  no 
information.  Ten  railroads  and  two  transit  companies  use  only  shop  fabrication. 
Four  railroads  and  one  transit  company  use  field  application  only.  The  remainder 
of  the  respondents  use  both  shop  and  field  installations. 

For  shop  fabrication,  five  railroads  and  one  transit  company  reported  using 
39-ft  lengths  of  rail  including  the  insulated  joint.  Four  railroads  reported  using  13-ft 
lengths.  The  remaining  railroads  and  transit  companies  use  rail  lengths  varying  from 
11  to  26  ft,  including  the  joints.  Ele\en  companies  stated  they  did  not  offset  the 
joint  in  the  rail  for  balance  in  handling  and  eight  reported  they  did.  In  general, 
the  companies  using  longer  lengths  of  rail  offset  the  joint. 

All  respondents  reported  either  using  fully  heat-treated  rail,  mill  end-hardened 
or  field  end-hardened  rail  in  both  shop  and  field  installation  of  joints.  Eighteen  re- 
spondents reported  AREA  specifications  for  end  squareness  to  be  satisfactory  for 
installation  of  bonded  insulated  joints.  Four  reported  squareness  to  be  unsatisfactory 
and  recut  each  piece,  placing  the  end  post  between  the  mating  cut  ends. 

Failure  rate,  defined  as  a  joint  which  had  epoxy  cement  bond  failure  within 
30  days  after  being  installed  in  track,  has  been  negligible.  Most  companies  reported 
no  failures,  and  those  that  reported  failures  indicated  they  were  less  than  1%  with 
the   exception   of   one   railroad  which   indicated   it  had  75%   failure   in  field-applied 

Bui.  656 


320       Bulletin  656 — American  Railway  Engineering  Association 

joints.  However,  this  same  railroad  reported  no  failures  in  shop-fabricated  joints. 
One  railroad  with  over  7,000  shop-fabricated  joints  installed  within  the  last  five 
years  reported  no  failures. 

The  number  of  bonded  insulated  joints  in  track  as  reported  by  the  different 
companies  varied  greatly  from  2-7,000  but,  of  course,  this  is  to  be  expected  as  the 
length  of  time  they  have  been  in  use  varied  from  one  to  five  years.  The  railroad 
reporting  7,000  joints  in  track  also  reported  using  tliem  the  longest.  Also,  the  various 
railroads  and  transit  companies  surveyed  had  vastly  different  mileages  and  operating 
conditions. 

All  of  the  companies  surveyed  indicated  they  were  well  satisfied  with  the 
success  of  this  type  of  joint  and  most  indicated  they  intended  to  use  more  of  them 
in  the  future.  Several  were  awaiting  results  of  their  tests  before  moving  further. 
One  railroad  reported  using  standard  joint  bars  to  fasten  shop-fabricated  joints  to 
adjacent  rails,  one  reported  using  both  joint  bars  and  field  welding.  The  remainder 
of  respondents  reported  field  welding  of  the  joint  assembly. 

The  cost  of  shop  fabrication  of  bonded  insulated  joints  varied  so  greatly,  as 
reported  by  the  respondents,  that  an  average  figure  would  be  meaningless.  Various 
manufacturers  report  they  charge  $20  to  $35  for  installation  of  a  joint  on  rail  received 
at  their  shop.  Material  costs  of  joint  and  shipping  of  rail  to  and  from  shop  are 
additional.  One  large  railroad,  which  reported  having  over  7,000  bonded  joints  in 
track,  indicated  the  cost  to  fabricate  in  their  shop  to  be  $35  per  joint.  The  average 
cost  of  installing  the  section  of  rail,  including  bonded  insulated  joints  by  respondents 
who  field  weld  them  in  track,  was  $210  each. 

The  average  cost  of  field  installation  of  bonded  insulated  joints  was  reported 
to  be  $120  each.  The  question  was  asked  as  to  the  estimate  of  aimual  savings  by 
using  bonded  joints  vs.  other  types.  All  reported  not  enough  experience  as  yet  to 
compare.  A  number  of  companies  felt  the  savings  would  be  substantial  as  time 
went  on. 

The  bonded  insulated  joint  has  been  around  for  a  relatively  short  time;  however, 
judging  from  the  response  and  answers  to  the  questionnaires  sent  out,  its  acceptance 
and  use  is  certainly  reducing  the  labor  cost  of  maintaining  the  many  thousands 
of  insulated  joints  in  use  over  the  country.  It  appears  the  field  installation  is  more 
economical. 

ECONOMICS  OF  BONDED  JOINTS  VS.  FIELD  WELDS  TO  CONNECT  CWR 

The  laying  of  continuous  welded  rail  has  markedly  reduced  maintenance  by 
eliminating  nearly  all  of  the  bolted  joints,  but  on  those  remaining,  connecting  tlie 
strings  together,  maintenance  has  increased  greatly  because  of  stresses  they  are 
subjected  to  in  cold  weather  with  resulting  excessive  end  gaps,  broken  and  damaged 
bolts,  and  in  severe  cases,  pull-aparts.  In  addition,  the  large  end  gaps  cause  excessive 
normal  batter  with  more  than  normal  surfacing  required. 

In  order  to  detemiine  the  economics  of  connecting  strings  of  CWR  together 
with  field  welds  vs.  bonded  joints,  an  analysis  has  been  made  of  various  railroads 
and  transit  companies  as  to  tlieir  practice.  A  questionnaire  was  sent  to  32  railroads 
and  6  transit  companies  representative  of  the  industry. 

Five  transit  companies  returned  the  questionnaire;  three  reported  they  used 
thermite  type  field  welds  for  connecting  strings  of  CWR,  and  tlie  other  two  did  not 
or  had  no  information.  The  cost  of  installation,  including  material,  ranged  from  $80 
to  $400  per  joint  with  an  average  of  $240.  No  transit  companies  reported  using 
bonded  joints.  Failure  of  field  welds  was  reported  very  low,  less  than  2  percent. 


Economics   of   Railway   Construction   and    Maintenance 321 

Twenty-six  railroads  responded  and  of  them,  two  ha\e  no  welded  rail,  and  two 
have  welded  rail  but  use  standard  joint  bars  for  connecting  the  strings.  The  remaining 
lines  use  thermite  type  field  welds  for  connecting  strings  of  CWR.  Two  lines  also 
use  bonded  joints,  three  railroads  either  use  bars  which  have  been  ground  at  the 
center  to  fit  over  the  upset  material  of  the  weld,  or  a  "safety  strap."  One  hne  uses 
these  only  on  high  side  of  curves  2°   and  over. 

Costs  of  installing  field  welds  ranged  from  $60  to  $150  with  the  average  being 
894  each.  The  a\erage  cost  of  installing  bars  or  "safety  straps"  was  reported  to  be 
$33  a  joint. 

Failure  rate  was  reported  \ery  low  on  both  field  welds  and  bonded  joints — 
less  than  2  percent. 

The  results  of  the  sur\e>'  indicate  there  are  few  railroads  using  bonded  joints 
to  comiect  strings  of  CWR  and  there  appears  to  be  no  economic  savings  by  so  doing. 


Report  of  Committee   13 — Environmental  Engineering 


C.  E.  DeGeer,  Chairman 
W.  H.  Melgren, 
Vice  Chairman 
A.  J.   Dolby,  Secretary 


R.  C.  Brownlee 
R.  R.  Holmes 
T.  W.  ZWICK 
R.  S.  Bryan,  Jr. 

L.    R.    BURDGE 

D.  S.  Krieter 
Barbara  J.  Rust 
W.  F.  Arksey 
A.  F.  BuTCosK 

W.    M.    CUMMINGS 

W.  p.  Cunningham 

J.    C.    DiETZ 

J.  H.  Flett 

J.    W.    GWYN 

W.  M.  Harrison 
T.  L.  Hendrlx 
K.  K.  Hersey 
J.  D.  HoFF,  H 
D.  J.  Inman 
F.  O.  Klemstine 

R.    M.    LiNDENMUTH 

F.  L.  Manganaro 


W.  D.  Mason,  Jr. 
R.  G.  Michael 

C.  F.  Muelder 
E.  T.  Myers 
G.  H.  Nick 

M.   F.   Obrecht 
L.  W.  Pepple 
W.  D.  Peters 
Robert  Singer 
R.  J.  Spence 
T.  A.  Tennyson 

L.    R.    TiERNY 

J.  W.  Webb,  Jr. 

D.  R.  York 

M.   L.  Williams 
R.  G.  Bielenberg 

E.  S.  Johnson 
R.  J.  Thompson 

J.  J.   DWYER   (E) 

H.  L.  McMuLLiN  (E) 
Committee 


(E)    Member  Emeritus. 

Those   whose   names   are   shown   in   boldface,  in   addition  to  the  chairman,  vice   chairman  and 
secretary,    are   the    subcommittee    chairmen. 

To  the  Anwrican  Railway  Engineering  Association: 

Your  committee  reports  on   the  following  subjects: 

B.  Revision  of  Manual. 

Under  way  is  the  continual  updating  of  "Glossary  of  Terms"  and  "Di- 
rectories  of  Pollution   Control  Agencies." 

1.  Water  Pollution  Control. 

Progress  report  on  "Box  and  Hopper  Car  Cleaning,"  presented  as 
infonnation page  325 

2.  Air  Pollution  Control. 

The  assignment  to  "Investigate  Guide  Standards,  Including  Instrumenta- 
tion for  Preliminary  Measurements  of  Stationary  Stack  Emissions," 
will   be   continued   to   include   latest   government   requirements. 

3.  Land  Pollution  Control. 
No  report. 

4.  Industrial  Hygiene. 

Section  4.7  "Sanitation  Requirements  for  Portable  Housing  Units,"  was 
published  in  Part  1  of  Bulletin  655,  November-December  1975,  with 
the  recommendation  that  it  be  adopted  and  published  in  the  Manual. 

5.  Plant  Utilities. 
No  report. 


323 


324       Bulletin  656 — American  Railway  Engineering  Association 

6.  Corrosion  Control. 

Progress  report,  "Use  of  Plastic  Pipe,"  presented  as  information    ....   page  327 

7.  Noise  Pollution  Control. 
No  report. 

The  Committee  on  ENvmoNMENTAL  Engineering, 

C.  E.  DeGeer,  Chairman. 


1915=1975 

John  L.  Engler,  construction  engineer  for  the  Atchison,  Topeka  &  Santa  Fe 
Railway  at  Topeka,  Kansas,  died  on  February  5,  1975,  at  Topeka. 

Mr.  Engler  was  born  on  June  16,  1915,  at  Chapman,  Kansas,  and  was  graduated 
from  Chapman  High  School.  He  received  his  degree  in  civil  engineering  from  Kansas 
State  University,  Manhattan,  Kansas,  and  joined  the  Santa  Fe  Railway  in  1937  as 
a  chainman  at  Topeka.  During  1938  and  1939  he  worked  for  the  Kansas  State  High- 
way Commission,  returning  to  the  Santa  Fe  Railway  in  June  1939. 

Mr.  Engler  entered  military  service  in  1941,  and  following  World  War  II  he 
worked  as  an  admeasurer  for  the  Panama  Canal  and  as  a  design  engineer  for  the 
U.S.  Bureau  of  Reclamation  in  Nebraska  before  returning  to  the  Santa  Fe  in  1953  at 
Topeka.  Mr.  Engler  was  promoted  to  assistant  engineer  in  1956  and  construction 
engineer  with  headquarters  in  Topeka  in  1971. 

We  of  Committee  13  knew  John  as  dedicated  engineer  who  contributed  much 
to  the  work  of  our  committee. 


Environmental  Engineering 325 

Report  on  Assignment   1 

Water  Pollution  Control 

R.  C.  Brownlee  (chairman,  subcommittee),  R.  G.  Bielenberg,  L.  R.  Burdge,  C.  E. 
DeGeer,  J.  W.  GwYN,  D.  J.  Inman,  E.  S.  Johnson,  R.  M.  Lindenmuth, 
P.  M.  Miller,  R.  J.  Thompson,  D.  R.  York. 

PROBLEMS  IN  THE  DISPOSAL  OF  WASTE  FROM  BOX  CAR  AND 
HOPPER  CAR  CLEANING 

Your  committee  submits  as  information  the  following  report  pertaining  to  the 
disposal  of  wastes  from  box  car  and  hopper  car  washing,  with  the  intention  of 
developing  furtiier  information  and  data  for  eventual  submission  for  publication 
in  die  Manual. 

General 

As  with  other  railroad  pollution  problems,  in  order  to  reduce  the  initial  pollution, 
and  to  obtain  the  most  economical  and  efficient  control,  it  is  essential  to  have  the 
cooperation  of  all  departments  of  the  railroad.  To  insure  this  cooperation,  it  is  most 
desirable  to  have  pollution  control  administered  by  the  chief  executive  officer  of  the 
railroad. 

Waste  from  box  car  and  hopper  car  washing  facilities  presents  a  most  difficult 
problem  for  treatment  and  disposal.  Large  facilities  present  little  chance  for  inven- 
tory or  pre-inspection  of  the  cars,  and  the  logistics  involved  in  switching  the  cars 
to  avoid  shock  loadings  on  the  treating  facilities  make  this  practice  unfeasible.  Treat- 
ment facilities  must  therefore  be  designed  on  the  basis  that  concentrations  of  pollutant 
constituents  in  wastewater  will  be  variable  and  impossible  to  anticipate.  Technology 
is  available  for  the  treatment  of  practically  all  organic  compounds;  however,  removal 
of  high  concentrations  of  dissolved  solids  common  to  washwaters  is  difficult  and 
expensive. 

Precleaning  Cars 

Dissolved  salts  and  otlier  solids  cannot  be  treated  biologically  and  cannot  be 
filtered.  A  logical  approach  to  die  problem  of  high  concentrations  of  dissolved  solids 
in  the  wastewater  is  to  remove  the  soluble  solids  from  the  cars  in  a  dry  form  rather 
than  attempting  to  remove  them  from  solution  in  the  wastewater. 

Box  cars  can  be  hand-swept  or  vacuumed,  provided  that  consideration  be  given 
to  health  hazards,  control  of  air  pollution,  and  collection  and  disposal  of  the  dry 
material.  Precleaning  of  hopper  cars  can  be  accomplished  to  varying  degrees  by 
opening  the  hopper  doors  ahead  of  the  washer  facility.  The  cars  may  be  vibrated 
with  mechanical  vibrators  or  shaken  with  an  engine  to  facilitate  removal  of  dry 
material.  Sand  or  grit  blasting  of  hopper  cars  has  been  considered  by  some  railroads. 
Pollution  control,  health  hazards  and  disposal  of  dry  materials  must  be  given 
proper  consideration. 

Washwater  Characteristics 

Commodities  commonly  carried  by  box  and  hopper  cars  and  which  find  their 
way  into  the  wastewaters  from  washing  facilities  can  generally  be  classified  as 
"organic"  or  "inorganic."  Organic  materials  such  as  grains,  sugar,  cereals,  oils,  and 
meals  contribute  high  concentrations  of  BOD  and  suspended  solids  to  the  wastewater. 


326       Bulletin  656 — American  Railway  Engineering  Association 

Inorganics  common  to  car  washer  wastewaters  include:  potash  which  contributes 
liigh  concentrations  of  chlorides  and  potassium  in  dissolved  forms;  cement  and  lime 
which  raise  the  pH  of  the  wastewater  and  combine  with  insolubles  to  form  deposits 
in  tile  drain  lines;  fertilizers  which  are  soluble  in  water  and  contribute  nutrients 
such  as  sulphates,  nitrogen  compounds  and  phosphates;  borates  which  are  somewhat 
soluble  in  water  and  toxic  to  many  plants;  sand,  coal  and  ores  which  are  slightly 
soluble  and  may  contribute  heavy  metals  to  the  wastewater. 

Common  problems  associated  witli  treatment  of  car  washer  wastewater  include 
the  removal  of  suspended  solids,  reduction  of  BOD,  identification  and  containment 
of  toxic  compounds,  the  adjustment  of  pH,  and  the  difficult  problem  of  excessive 
concentrations   of   dissolved  solids.    Removal   of  nutrients  must  also  be   considered. 

Treatment  Methods 

Generally,  primary  treatment  of  wastewater  from  car  washer  facilities  should 
accomplish  the  removal  of  floating  and  settleable  solids.  Primary  treatment  should 
include  ponding  of  the  wastewater  in  order  to  bufi^er  shock  loads  resulting  from 
washing  cars  containing  the  same  type  of  commodity. 

Primary  treatment  facilities  should  include  a  sloping  pad  on  the  washer  facility 
to  retain  heavy  settleable  solids,  a  small  grit  chamber  at  the  edge  of  the  pad  with  a 
solids  dragout  device  for  removal  of  floating  and  settleable  solids,  and  a  settling 
pond  sized  to  buffer  shock  loads  and  afford  retention  time  for  clarification  of  smaller 
floating  and  settleable  solids. 

Secondary  treatment  of  wastewater  may  include  lagoons,  aeration  equipment  or 
trickhng  filters.  In  favorable  climates  reasonably  efficient  BOD  removal  can  be 
accomplished  by  floculative  and  aerobic  lagoons.  Additional  biological  treatment 
is  accomplished  by  surface  aerators  in  lagoons,  diffused  aeration  in  lagoons,  spray 
ponds,  activated  sludge  facilities  and  trickling  filters.  Activated  sludge  plants  are 
available  from  vendors  as  packaged  plants  ready  to  set  on  foundations. 

Tertiary  treatment  for  removal  of  suspended  solids  and  nutrients  can  be  accom- 
plished by  floculation-sedimentation,  air  floatation  systems  and  various  other  methods 
for  stripping  nutrients. 

Receiving  Waters 

The  degree  of  treatment  required  will  vary  according  to  the  pollutant  contents 
of  tlie  wastewater  and  die  effluent  criteria  that  are  required  for  discharge  into  streams 
or  municipal  sewers,  based  on  the  economics  involved.  Generally,  tlie  allowable 
limitation  on  concentrations  of  dissolved  solids  and  nutrients  make  the  discharge 
of  wastewater  into  storm  sewers  or  other  open  waterways  and  lakes  impossible  even 
with  extensive  pretreabiient  of  the  wastewater.  Evaporation  ponds  and  irrigation  offer 
alternatives  in  certain  areas  which  have  favorable  climatic  conditions  and  where  suffi- 
cient property  is  available  to  accommodate  tliese  methods.  Gonsideration  must  be  given 
to  suppression  of  odors  and  the  prevention  of  percolation  of  wastewater  into  ground- 
water strata.  Generally,  it  is  more  economical  to  discharge  the  wastes  into  municipal 
sanitary  sewers  as  it  requires  less  treatment. 

Summary 

Remember — clear  water  is  not  necessarily  clean  water.  Wastewater  which  has 
been  conventionally  treated  for  the  removal  of  BOD,  suspended  solids  and  other 
objectionable  constituents  may  still  contain  extremely  high  concentrations  of  dissolved 


Environmental  Engineering 327 


salts.  This  treated  wastewater,  although  it  may  appear  clean,  can  actually  be  unfit 
for   discharge   into  waterways   or  even  municipal  sanitary  sewers. 

The  major  problems  associated  with  the  disposal  of  wastewater  from  box  car 
and  hopper  car  washing  lies  not  in  con\entional  treatment  of  the  effluent,  but  in 
the  reduction  of  the  concentration  of  dissoKed  solids.  From  the  standpoint  of  waste 
disposal,  it  is  infinitely  easier  to  handle  soluble  solids  in  tlieir  dry  form  than  to 
dissolve  them  in  the  washwater  and  then  try  to  remoxe  them  from  the  wastewater. 


Report   on   Assignment   6 

Corrosion  Control 

D.   S.   Krieter  (chairman,  subcommittee),  J.   H.   Flett,  F.  O.  Klemstine,  W.  D. 
Mason",  Jr.,  R.  G.  Michael. 

Your  committee  submits  the  following  report  on  the  Use  of  Plastic  Pipe  as 
information. 

USE  OF  PLASTIC  PIPE 
GENERAL 

Plastic  pipe  can  be  used  in  a  variety  of  piping  applications  in  the  railroad 
industry'  where  strength,  chemical  resistance  and  ease  of  installation  play  important 
roles.  Plastic  pipe  is  found  in  such  railroad  applications  as  water  mains,  chemical 
feed  lines  for  cooling  towers  and  waste  treatment  facilities,  drainage  lines  and  loco- 
motive wash  racks.  It  is  the  intent  of  this  committee  report  to  serve  as  a  guide  in 
selecting  the  proper  type  of  plastic  pipe  based  on  tlie  material  to  be  handled.  Since 
plastic  pipe  in  many  cases  is  competitive  in  cost  with  steel,  it  is  important  to  check 
the  operating  conditions  for  such  parameters  as  high  temperature  and/or  pressure 
since  the  use  of  plastic  pipe  under  these  conditions  is  largely  restricted. 

By  far  the  most  commonly  used  types  of  plastic  pipe  are  polyethylene  and 
polyvinyl  chloride  ( P^'C ) .  Certain  \'ariations  of  these  exist  in  the  form  of  high-  and 
low-density  polyethylene  and  chlorinated  poly\inyl  chloride  (CP\'C).  In  addition, 
there  is  axailable  a  polypropylene  pipe  which,  altliough  less  common  than  PVC  and 
polyetliylene,  has  certain  desirable  characteristics.  There  is  also  a  widespread  use 
of  acrylonitrile  butadiene  styrene  (ABS)  and  polyester  and  epoxy  glass  reinforced 
pipe.  The  application  for  each  type  of  pipe  depends  not  only  on  the  operating 
temperature  and  pressure  of  the  material  to  be  transported,  but  on  the  chemistry 
of  the  material  and  in  some  cases,  location.  The  general  physical  and  chemical  charac- 
teristics of  each  t\pe  of  pipe  are  briefly  outlined  in  the  following  sections,  and  care 
should  be  taken  to  avoid  selecting  a  plastic  pipe  which  may  be  wholly  unsuitable 
for  the  intended  application. 

The  polyethylene  pipes  generally  have  the  lowest  operating  temperatures  and 
pressure  ranges  followed  by  PVC,  ABS,  CPVC  and  glass  fiber  reinforced  epoxy  in 
that  order.  Among  the  most  common  uses  for  polyetliylene  pipe  include  low-pressure 
water  systems;  small  above-ground  drainage  lines;  natural  gas  lines;  distilled, 
demineralized,  and  zeolite  water  hues;   corrosive  liquids  and  gases. 

Polyvinyl  chloride  pipe  (PVC)  finds  widespread  use  in  pressure  piping  and 
drainage  systems,  water  service,  drain,  waste  and  vent  systems,  gas  service,  chemical 


328       Bulletin  656 — American  Railway  Engineering  Association 

feed  piping  and  water  well  casings.  This  type  of  pipe  is  definitely  not  suitable  for 
piping  certain  petroleum   products    (e.g.,   gasoline,  fuel  oil). 

Chlorinated  polyvinyl  chloride  (CPVC)  pipe  is  used  mainly  for  hot-  and  cold- 
water  distribution  systems  and  hot  and  cold  chemical  piping. 

Acrylonitrile  butadiene  stryene  pipe  (ABS)  is  used  in  many  railroad  applications 
involving  drain,  waste  and  vent  systems,  pressure  piping  and  drainage  systems,  water 
service  and  gas  service. 

Glass  fiber  reinforced  epoxy,  being  one  of  tlie  most  durable  types  of  plastic  pipe, 
is  usually  used  for  severe  piping  conditions  where  the  other  types  are  not  suitable. 
One  of  the  most  prominent  railroad  uses  is  in  locomotive  wash  rack  piping  where 
hot   corrosive   chemicals   are   piped   under  high   pressure. 

POLYETHYLENE  PLASTIC  PIPE 

Properties 

Generally,  they  are  insoluble  below  50  C,  but  at  higher  temperatures  high- 
and  low-density  polyethylenes  are  soluble  in  hydrocarbons  and  chlorinated  hydro- 
carbons. The  polyethylene  pipes  are  decomposed  by  strong  oxidizing  agents  (fuming 
HNOs  and  H2SO1),  slowly  attacked  by  halogens  and  chlorinating  agents  (chlorosul- 
phonic  acid,  phosgene,  thionyl  chloride).  Solvents  at  elevated  temperatures  include: 
toluene,  xylene,  tetralin,  carbon  tetrachloride,  trichloroethylene  and  perchloroethylene. 
They  are  relatively  insoluble  and  unaffected  by  polar  solvents  (alcohols,  esters, 
ketones),  vegetable  oils,  water,  alkalis,  most  concentrated  acids  (including  HF) 
and  at  room  tempera tiu'e,  ozone  (in  absence  of  ultra-violet  light). 

Moisture 

Polyethylene  pipe  is  very  resistant  to  water  witli  an  increase  in  weight  after 
immersion  at  20  C  (68  F)  for  a  year,  of  less  tlian  0.2%.  Higher  temperatures  could 
bring  about  a  chemical  change  with  an  increase  in  water  absorption.  As  previously 
mentioned,  polyediylene  is  widely  used  for  chemical  feed  lines  under  ambient  tem- 
perature conditions. 

Permeability 

Transmission  of  gases  and  vapors  would  be  least  in  high-density  polyethylene 
pipe.  Permeability  with  organic  vapors  is  lowest  with  strongly  polar  materials  and 
rises  according  to  the  following  general  order:  alcohols,  acids,  nitroderivatives,  alde- 
hydes   and    ketones,    esters,    ethers,    hydrocarbons    and    halogenated    hydrocarbons. 

Melting  Point 

For  low-density  polyethylene  pipe  this  range  would  be  109-125  C  (228-257  F), 
and  for  high-density  pipe,  130-135  C  (266-275  F). 

Mechanical  and  Physical  Properties 

It  is  difficult  to  correlate  tlie  stress-strain  properties  of  polyethylene  pipe  with 
basic  characteristics  such  as  density,  crytallinity  and  melt  flow  index,  since  the 
conditions  of  preparation  of  the  specimen  and  the  test  itself  greatly  affect  the  results. 
In  general,  however,  properties  involving  small  defonnations  (e.g.,  modulus,  creep) 
depend  upon  crystallinity  and  thus  upon  density;  for  large  deformations  (e.g.,  tensile 
strength,  creep  rupture),  molecular  weight  and  branching  appear  to  be  determining 
factors. 


Environmental  Engineering 329 

POLYPROPYLENE  PLASTIC  PIPE 

Properties 

Polypropylene  pipe  can  be  decomposed  by  strong  oxidizing  agents  (e.g.,  HNOa, 
bromine,  oleum),  especially  when  warm  (i.e.,  very  readily  attacked  by  hot  con- 
centrated H2SO4).  It  is  dissolved  only  at  elevated  temperatures  by  aromatic  hydro- 
carbons (e.g.,  xylene,  tetralin,  decalin),  and  chlorinated  hydrocarbons  (e.g., 
chlorofonn,  trichloroethylene )  above  80  C  (176  F).  It  is  swollen  by  aromatic 
hydrocarbons  and  chlorinated  hydrocarbons  at  room  temperature,  also  by  esters, 
etliers  and  by  various  aqueous  oxidizing  agents  (e.g.,  10%  HNO3,  10%  KMnOj,  dilute 
H2O2).  It  is  relatively  unaffected  by  many  organic  liquids  at  room  temperature 
(e.g.,  alcohols,  glycols),  and  aqueous  solutions  including  moderately  concentrated 
acids  and  alkalis  but  less  satisfactorily  above  60  C  ( 140  F ) .  In  brief,  polypropylene 
pipe  is  more  readily  oxidized  than  polyethylene,  the  rate  of  attack  and  range  of 
reagents  increasing  with  temperature  use,  and  may  not  be  suitable  for  use  in  certain 
types  of  chemical  feeding  applications. 

Moisture 

The  increase  of  weight  of  polypropylene  pipe  after  six  months  submergence 
in  aqueous  environment  at  20  C  (68  F)  is  under  0.5%;  at  60  C  ( 140  F)  it  is  under  2%. 

Mechanical  and  Physical  Properties 

Tensile  strength  of  general-purpose  polypropylene  pipe  is  2.8  to  3.5  kg/mm^ 
(4,126  to  5,426  psi). 

Impact  strength  of  general-purpose  grade  is  0.4  to  2.2  ft-lb/in.  of  notch;  of 
high-impact  grade,  1.5  to  12  ft-lb/in.  of  notch.  Polypropylene  pipe  has  poor  impact 
strength  at  sub-zero  temperatvires,  as  the  glass  temperature  lies  between  4  and  — 12  C 
(39  and  10  F),  and  its  use  under  tliese  circumstances  should  be  avoided. 

POLYVINYL  CHLORIDE  PIPE 

Properties 

Polyvinyl  chloride  pipe  can  be  dissolved  by  tetrahydrofuran,  cyclohexanone, 
methyl  ethyl  ketone  and  dimethylformamide,  also  by  mixtures  of  solvents  such  as 
acetone  with  carbon  disulfide,  carbon  tetrachloride  or  benzene  and  etliyl  acetate 
with  carbon  tetrachloride.  PVC  pipe  can  become  swollen  by  aromatic  and  chlorinated 
hydrocarbons,  nitroparaffins,  acetic  anhydride,  aniline  and  acetone.  It  is,  however, 
relatively  unaffected  by  water,  concentrated  alkalis,  non-oxidizing  acids,  hypochlorite 
solutions,  aliphatic  hydrocarbons,  oils  and  ozone.  Decomposition  can  occur,  however, 
by  concentrated  oxidizing  acids  (HoSOi,  HNO3,  HsCrOi)  which  slowly  attack  the 
polymer.  The  particular  rate  of  decomposition  may  be  increased  in  the  presence  of 
lime  or  iron  or  their  compounds. 

Generally  for  PVC  pipe,  chemical  stability  is  good  and  weatherability  is  excellent, 
but  it  is  adversely  affected  by  ultra-violet  light.  Rigid  PVC  surface  absorption  of 
water  after  32  days  immersion  at  20  C  (68  F)  was  5  g/nr  (0.001  Ib/ft^),  for  the 
plasticized  PVC  this  is  as  high  as  200  g/nr  (0.04  lb/ft").  Absorption  increases 
greatly  with  temperature.  Rigid  PVC  pipe  is  brittle  below  —40  C  (—40  F),  hard 
and  tough  at  room  temperature  and  softens  at  80  to  85  C  ( 176  to  185  F).  Plasticized 
PVC  is  flexible  down  to  —50  C  (—58  F)  and  serviceable  up  to  75  C  (167  F).  In 
air  above  100  C  (212  F)  both  rigid  and  plasticized  PVC  decompose,  and  full  de- 
composition occurs  above  180  C  (356  F).  This  pipe  finds  widespread  use  as 
underground  water  mains. 


330       Bulletin  656 — American  Railway  Engineering  Association 

Mechanical  Properties 

Tensile  strength  of  rigid  PVC  =  4.25  to  5.6  kg/mnr  (6044.8  to  7964.9  psi) 
and  falls  with  a  rise  of  temperature. 

Compression  strength  of  rigid  PVC  is  5.6  to  6.7  kg/mm''  (7964.8  to  9529.4  psi). 

Impact  strength  of  rigid  PVC  is  0.8  ft-lb/in.  of  notch;  the  elastic  modulus 
(Young's)  of  rigid  PVC  is  about  280  kg/mnr  (394,244  psi). 

POLYESTER  AND  EPOXY  PIPE 
(GLASS  REINFORCED) 

Properties 

The  properties  given  relate  to  the  general-purpose  grades  of  polyester  and 
epoxy  pipes  available.  These  pipes  are  relatively  unaffected  by  aliphatic  hydrocarbons 
(petrol,  mineral  oils,  non-polar  chlorinated  hydrocarbons  (carbon  tetrachloride, 
tetrachloroethylene ) ,  alcohol,  non-o.\idizing  acids,  organic  acids  and  salt  solutions. 
Polyester  pipe  can  be  decomposed  by  polar  chlorinated  hydrocarbons  (chloroform, 
trichloroetliylene ) ,  ketones,  phenol,  aniline,  esters  (ethyl  acetate),  alkalis  and 
oxidizing  acids. 

Water  resistance  for  polyester  pipe  is  generally  very  good  with  an  average  weight 
increase  after  one  year  in  water  at  25  C  (77  F)  of  approximately  1.1%. 

Mechanical  Properties 

At  low-temperatures,  glass-reinforced  polyester  pipe  exhibits  increases  in  certain 
properties  due  to  stiffening.  Among  these  are  the  tensile,  flexural  and  compression 
strengths  which  are  reported  to  rise  to  values  as  much  as  50  to  100%  higher  than 
at  25  C  (77  F).  Due  to  the  many  kinds  of  polyester  and  epoxy  reinforced  pipes 
cxurently  on  the  market,  it  becomes  very  difficult  to  accurately  summarize  such 
parameters  as  tensile  and  compression  strengths  of  this  class,  and  it  is  suggested  that 
the  user  contact  tlie  manufacturer  for  specifications  on  a  particular  application.  The 
liber  glass  reinforced  pipes  seem  to  be  a  popular  choice  for  locomotive  wash  rack 
piping  and  condensate  return  lines  to  boilers.  This  is  due  not  only  to  ease  of  installa- 
tion and  cost,  but  long-run  serviceability  under  extreme  pH  and  pressure  conditions. 
Certain  grades  of  epoxy  fiber  glass  pipe  have  successfully  been  used  in  chemical  feed 
lines  for  locomotive  wash  rack  at  pressure  of  400  psi  and  temperature  of  60  C  (140  F). 

REFERENCES 

1.  The   Chemist's   Companion,   John   W^iley   and   Sons,   Inc.,   New  York;    1972,   pp. 
414-416. 

2.  Handbook  of  Common  Polymers,  Chemical  Rubber  Company,  Cleveland,  Ohio, 
1971,  pp.  3-13,  22-27,  110-119,  258,  268-271. 

3.  Textbook  of  Polymer  Science,  John  Wiley  and  Sons,  Inc.,  New  York,  1971,  pp. 
4,  124,  215,  386-388,  419-i22,  506-507. 

4.  W.  J.  Engle,  Atr  Force  Civil  Engineer,  Vol.  10,  No.  4,  1969,  pp.  32-r 

5.  M.  F.  Obrecht  and  J.  R.  Myers,  Heating /Piping/  Air  Conditioning,  August  1973, 
p.  59. 

6.  I.  C.  Brown  et  al.  Plastic  Pipe  and  Its  Uses  on  Railroads,  AREA  Proceedings,  Vol. 
61,  1960,  pp.  303-306. 


Environmental  Engineering 


331 


tJfl 

SS 

"8 

«-2 

:g 

H'*^ 

Ji 

bD  tp+>  rH 

H    B  H  O 

H    <S  Vi  ^  4^ 

TJ    -I  O 

-«  •«  a  ■>.-<! 

9  C  CI  <n 

»      •  H  O  Jl 

TI  to  H  tj 

c  -a  (1)  H  »j 

O     0)  Li  en  O 

>     «  D.  C  I^ 

O    5  O  »<  3 

(0    -P  O  -P  fn 


■:^  S 


(U    o    c     - 


<-i    aj   «}  =     n 


a^ 


p  a 

5  o 

•H 

■p  -p 

(D  n 

>  c 

iH  a) 


^9 


II 


■I 


a3 


I 

8, 


n   H  H  P    -4 


S^ 


(D  oil  W 


I         4)  -P  jQ 

I  jj  o  10  n 

I  a  n  a 

!   O    03  o   L 

•-f   -t^  ri    0 

i-l    to  H 


10  J3 

o  d 


•H    W 


*  e 


i:-g 


0  (,■■ 

o  ii, 
tlS  to< 


s-s 


n  -p  p, 
o  e 

__  _  «   (0    (D 

43    O,  »  bo  4)  ft-*J 

4:>    Cj3  o  E 

b.0       o  «  C  .rt  :» 

□     4  a>  d  o 

4)    PI  "O  O  -P.  T3  iH 

(^    C!  O  C  to  O 

-P    («  O  <a  -H  O  +3 

Ul    Pi  bO-p  CO  bO  0] 


•p  q    «-p  4h 

hp  3  43  u  o  d 

a -p  a  :3  o  o  e 

+3mMonHx!'H 

to   Cf-toa  4-Pn 

U  <a        4)  S        c 

+>  9)  H  -P  to  V^    aJ 

o  j:  >H  lO  o  a. 


s-afe 


ISd 


I  x:  xi 
bfl  5  2  >  >,%,  -H  a 

•H     OXIO+'-PCh'H 
X    ClOOrHt-lin«-irH 


I 


s  5  ^ 
o  o 

•a      H    r] 
irH     P    E? 

OS© 

o   c  x: 
H    o 

-P  "O 
-P      O   rS     M 

I  O    tH    o    c 


«  ^ 

O  10 

-  -H   to 

tf. 

a>  Q. 

p,  n 

«.P 

>    0) 

>, 

■a  m 

t~s- 

cl 

CV  ITS 

00  vOv 

CM   -4 

CV   <V 

Q  O  ( 

8  bfl  o 

-p  o.  o 
o 

ja  «  s 

o8  ^  ^   bfl 

M  to  q 

r-4  O  t>    Q. 

O  Q.  u.  p. 


^   4H   bo  03 


\0  t~-  f^  »J 

sQ  sQ  rH  vO 

.  ,  -^  ^  1^  lA 

fV  Oj   Oi  rv  fV 


Vl  Vi 

•r.  rH  ^O  [^ 

ro  vf  o  -D 

i^  o:  -r  -<f 

HrvoJcv 

'  s:  a  s:  s 

E-.  EH  E-"  E-< 
\  -4  <i  <t  -x 


-4  rr\f\ 

9  «   e 

•g  •«  -o 

w    (0    CO 


»-<  r-(  (^;    f»\ 

i;   J,  t".  S. 


H 


Li    I? 


«^ 


si 


Report  of  Committee  27 — Maintenance  of  Way 
Work  Equipment 


F.   H.   Smith,   Chairman 

C.  H.  Olds, 
Vice  Chairman 

D.  E.    Crawford, 
Secretary 

W,  A.  MacDonald 

J.    P.    ZOLLMAN 

V.  R,  Ehquiaga 


W.  F.  Cogdill 
M.  L.  Stone 
P.  V.  Divine 
E.  T.  Daley 

W.    J.    GOTTSABEND 

L.  J.  Calloway 
L.  E.  Conner 
R.  E.  Dove 
R.  P.   Drew 
J.  M.  Driehuis 
H.  F.  Dully 
y.  O.  Elliott 
"E.  H.  Fisher 
W.  D.  Gilbert 
R.  E.  GoRSucH 
O.  T.  Harmon,  Jr. 
S.  R.  Horn 

N.    W.    HUTCHESON    (E) 

C.  Q.  Jeffords 
R.  M.  Johnson 
J.  Kelly 

M.  E.  Kerns  (E) 
C.  F.  King 
W.  F.  Kohl 
W.  E.  Kropp  (E) 
H.   F.  Longhelt 


R.  L.  Matthews 
C.  E.  McEntee 
A.  E.  MoRRiss,  Jr. 
R.  E.  Murbock 
T.  J.  O'Donnell 

C.  A.  Peebles 

J.  R.  Pollard,  Jr. 

A.  G.  Pronovost 
J.  E.  Quirk 

R.  S.  Radspinner 

D.  F.  Richardson 

B.  F.    RiEGEL 

T.  R.  RiGSBV 
J.  W.  Risk  (E) 

R.  T.  RUCKMAN 
D.  R.  SCHENCK 
D.    SCHULZ 

J.  R.  Smith,  Jr. 

J.  T.  Smith 

"S.  E.  Tracy  (E) 

C.  R.  Turner 

J.  L.  Van  Meter 
S.  W.  Walker 
N.  White 
J.  W.  Winger 

Committee 


(E)    Member   Emeritus. 

Those   whose   names   are   shown   in  boldface,   in   addition  to  the  chairman,  vice  chairman   and 
secretary,    are   the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 

Your   committee   reports   on   the   following   subjects: 

B.  Revision  of  Manual. 
No  report. 

1.  Reliability  Engineering  as  Applicable  to  Work  Equipment  Design  and 
Manufacture. 

No  report. 

2.  Machine    Design — Hydraulic    and    Electrical    Systems. 

Progress  report,  presented   as  information    P'lge  334 

3.  Machine  Design — Engines. 
No  report. 

4.  Machine   Design — Drive  Train,   Including   Clutch,   Transmission,   Final 
Drive  and  Power  Take-Offs. 

No  report. 

5.  Machine   Design — Bearings,    Suspension,   Frame   and   Brakes. 
No  report. 

333 


334       Bulletin  656 — American  Railway  Engineering  Association 

6.  Study  Design  of  Cars  Used  by  Maintenance  of  Way  Department,  Such 
as  Ballast  Cars,  Equipment  Transport,  Tie  Cars,  Rail  Cars,  Etc. 

No  report. 

7.  Temperature  Compensated  Stress-Adjustment  Equipment  for  Use  During 
or  After  Laying  CWR,  Collaborating  as  Necessary  or  Desirable  with 
Committee  4. 

No  report. 

8.  Applied    Metallurgy — Maintenance    of    Way    Work    Equipment. 
No  report. 

9.  Data  Processing  for  Work  Equipment  Evaluation,  Information  and 
Control,  Collaborating  as  Necessary  or  Desirable  with  Committee  32. 
No  report. 

The  Committee  on  Maintenance  of  Way  Work  Equipment, 

F.  H.  Smith,  Chairman. 


Report  on  Assignment  2 

Machine  Design^ — Hydraulic  and  Electrical  Systems 

J.   p.   ZoLLMAN  {chairman,   subcommittee),  L.   E.   Conner,  D.  C.  Johnson,  M.  E. 
Kerns,  A.  E.  Morriss,  Jr.,  Dave  Schulz,  C.  R.  Turner,  J.  L.  Van  Meter. 

Your  committee  submits  tlie  following  report  as  information  for  guidance  of 
equipment  manufacturers  and  railway  maintenance  personnel  in  the  design,  con- 
struction and  evaluation  of  hydraulic  systems. 

Hydraulic  systems  shall  conform  to  the  specifications  of  the  National  Fluid 
Power  Association  (NFPA),  American  National  Standards  Institute  (ANSI)  and 
International  Standards  Organization  (ISO),  except  that  where  a  conflict  occurs,  the 
following  will  apply: 

1.  Upon  completion  of  manufacture  and  before  any  operation  shall  begin,  all 
parts  of  the  hydraulic  system  shall  be  clean  and  free  from  scale,  rust,  dirt  and  any 
other  contaminant.  Threads,  flares,  holes,  cuts  and  machining  must  be  deburred 
and  cleaned. 

2.  Hydraulic  reservoirs  of  10-gal  capacity  or  larger  shall  be  designed  with  the 
following  considerations : 

a.  Place  the  bafile(s)  in  the  reservoir  so  as  to  separate  the  pump  inlet  port 
from  the  settling  part  of  the  reservoir.  The  baffle(s)  should  direct  the  flow 
toward  the  reservoir  walls  for  maximum  cooling  capacity  and  maximum 
lay-over  time. 

b.  Provide  sufficiently  large  access  panels  for  complete  periodic  cleaning, 
maintenance  and  inspection. 

c.  Provide  an  air  inlet  large  enough  to  maintain  conditions  of  Item  12.  The 
air  inlet  shall  be  equipped  with  a  25  micron  or  liner  filter,  A  cartridge  type 
is  preferred. 


Maintenance  of  Way  Work  Equipment 335 

d.  Provide  a  filler  with  at  least  a  100-mesh  screen  protected  from  external 
damage  with  a  minimum  capacity  of  5  gal  per  minute  with  500  SSU  fluid 
viscosity  and  with  a  filler  cap  that  can  be  locked  with  a  large  railroad 
padlock. 

e.  Provide  thermometer  to  indicate  reservoir  operating  temperature  at  the 
add-point  fluid  level  and  protected  from  damage. 

f.  Provide  a  static  fluid  level  gage  to  show  full-point  and  add-point  pro- 
tected from  damage. 

g.  When  immersion  heaters  are  provided  to  control  fluid  viscosity  during 
cold  weatlier  start-up,  place  the  heater(s)  so  removal  is  possible  without 
draining  reservoir. 

h.  A   non-integral   reservoir   is   preferred. 

3.  Fluid  temperature  shall  not  exceed  180  F  maximum  in  the  reservoir  outlets 
while  operating  in  a  110  F  ambient  temperature.  The  minimum  fluid  temperature 
after  45  minutes  operation  shall  be  85  F  with  ambient  temperature  of  20  F. 

4.  A  full-flow  testing  tee(s)  shall  be  provided  adjacent  to  the  pressure  side 
of  hydraulic  pump(s).  A  return-line  full-flow  tee  shall  be  placed  ahead  of  return 
line  filter. 

5.  Where  failure  of  power  plant  or  pump  can  immobilize  components  in  a 
position  which  could  prevent  moving  the  machine,  an  emergency  hand  pump  shall 
be  provided  in  the  circuit.  Large  machines  shall  be  equipped  with  battery-operated 
emergency  pump  where  more  than  5  minutes  are  required  to  move  all  components 
within   the   clearance   diagram   of  the   track   occupied,   by  means   of  a  hand  pump. 

6.  The  total  return  and/or  pressure  line  flow  shall  pass  through  filters  rated 
at  25  microns  or  finer  equipped  with  a  condition  indicator. 

a.  In  closed  loop  systems,  filtration  as  recommended  by  pump  manufacturer 
will  apply. 

b.  Magnetic   particle   attraction  shall  be  provided  in   the   filters   or  reservoir. 

c.  Filtration  of  the  return  flow  from  the  pilot  section  of  pilot-operated  valves 
is  not  required. 

7.  All  hydraulic  hose  assemblies  exposed  to  the  below-listed  pressures,  or  less 
pressure,  must  have  reusable  screw-together  hose  fittings.  On  all  metallic  wire- 
reinforced  hose  using  reusable  hose  fittings,  the  outermost  layer  of  wire  reinforce- 
ment must  be   braided   for  fitting  retention. 


Pressure 

Hose  I.D.  Size 

PSI 

(Inches) 

5500 

}i 

4500 

% 

4000 

^ 

3250 

% 

3000 

% 

2500 

1 

2250 

m 

1750 

m 

1250 

2 

a.  Hoses  must  be  protected  from  abrasion,  excessive  bending  and  excessive 
heat. 


336       Bulletin  656 — American  Railway  Engineering  Association 

b.  Hose  and  fluid  conductors  must  have  a  bursting  pressure  safety  factor  of 
four. 

c.  Hose  is  preferred.  Where  tubing  is  used,  37-degree  flared  ends  are  required. 

8.  Tubing  and  piping  shall  be  mounted  to  minimize  vibration,  and  tubing 
shall  have  only  gentle  bends  to  change  direction  or  compensate  for  thermal  expan- 
sion. Tube  bend  radii  shall  not  be  less  than  three  times  the  inside  diameter. 

9.  Wherever  practicable,  valves  shall  be  manifold  mounted. 

10.  Complete  circuit  diagram  shall  be  provided.  Only  NFPA,  ANSI  and  ISO 
symbols  shall  be  used  in  graphical  diagrams.  Pictorial  and  cutaway  diagrams  are 
also  permissible  where  they  add  to  the  ease  of  understanding  tlie  circuit.  Diagrams 
shall  be  large  enough  to  be  easily  followed  for  trouble  shooting. 

11.  Galvanized  pipe  and  fittings  shall  not  be  used. 

12.  The  vacuum  at  the  pump  inlet(s)  shall  not  be  more  tlian  60%  of  pump 
manufacturer's  recommendations  or  4  inches  mercury,  whichever  is  less  at  standard 
conditions.  Test  opening  shall  be  provided. 


L.    ScHMiTZ,    Chairman 
L.  R.  Beattie, 

Vice  Chairman 
J.  E.  Beran,  Secretary 


Committee  28~ 

-Clearances 

R.  R.   Snyder 

C.  F.  Intlekofer 

D.  W.  LaPorte 

E.  W.  Jantz 

E.  E.  Kessler 

R.  G.  Klouda 

W.   S.   TUSTIN 

A.   J.    KOZAK 

F.  A.  SvEc 

E.  C.  Lawson 

M.  L.   Power 

G.  W.  Martyn 

P.  T.  Sarris 

A.  Mooney 

E.  Berenot 

J.  R.  Moore 

E.    S.    BlRKENWALD    (E) 

W.    E.    MORGUS 

A.  V.  Bodnar 

F.  B.  Persels 

G.  M.  Buck 

C.  E.  Peterson  (E) 

R.  P.  Christman 

R.  T.  Pritchett 

J.    E.    COSKY 

W.    P.    SiLCOX 

J.  A.  Crawford 

E.  C.  Smith 

S.  M.  Dahl  (E) 

C.  H.  Stephenson 

M.  E.  Dust 

J.  E.  Teall 

C.  W.  Farrel 

W.  J.  Trezise 

G.  E.  Henry 

M.  Van  Kuixen 

J.     C.     HOBBS 

M.  E.  Vosseller 

G.   P.   HUHLEIN 

L.  R.  HuRD 

Cotnmittee 

(E)   Member  Emeritus. 

Those   whose   names   are   shown   in  boldface,  in   addition  to  the  chairman,  vice  chairman  and 
secretary,    are    the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 
Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 
No  report. 

1.  Investigate  the  Practicability  of  Using  Disposable  Coded  Placards  for 
Identifying  Shipments  of  Excessive  Dimension  and/or  Weight  that 
Could  Be  Used  in  Conjunction  with  the  Automatic  Car  Identification 
System. 

The  title  and  purpose  of  this  subcommittee  has  been  revised  to  "Investi- 
gate the  Practicability  of  Using  Disposable  Placards  or  Other  Appro- 
priate Marking  for  Identifying  Shipments  of  Excessive  Dimensions 
and/or  Weight."  This  change  was  felt  necessary  due  to  tlie  Automatic 
Car  Identification  System  not  being  fully  developed  as  intended  and 
a  standard,  easily  recognized  placard  being  more  practical  and  better 
serving  die  purpose  of  identifying  these  loads.  Current  placards  of 
various  railroads  are  now  being  studied  as  a  possible  basis  for  a  new 
common  design. 

2.  Compilation  of  the  Railroad  Clearance  Requirements  of  the  Various 
States. 

State  clearance  law  changes  are  continuing  to  be  compiled  and  a  revised 
tabulation  will  be  published  when  a  significant  revision  or  revisions 
are  accumulated. 


337 


338       Bulletin  656 — American  Railway  Engineering  Association 

3.  Investigate  New  Methods  and  Development  of  Equipment  for  Recording 
Measurements  of  Clearance  of  Structures  Along  Right-of-Way  and 
Overall  Dimensions  of  Cars  and  Loads. 

Progress  report,  submitted  as  information    page  339 

4.  Restudy  and  Possibly  Revise  "Clearance  Diagrams — Fixed  Obstruc- 
tions,"  Now   in   the   Manual. 

No  report. 

5.  Revise  "Suggested  Methods  of  Presenting  Published  Clearances,"  Now 
in  the  Manual. 

A  suggested  new  format  has  been  developed  for  presenting  clearance 
information  in  Railway  Line  Clearances.  However,  it  was  felt  that  a 
canvas  of  subscribers  by  questionnaire,  using  the  suggested  format  as 
a  basis,  could  coordinate  the  needs  and  desires  of  all  concerned  in  a 
final  design  that  would  be  the  most  acceptable  and  usable  by  the 
greater  majority  if  not  all  who  use  the  publication.  This  will  be  done 
in  the  near  future. 

9.  Investigate  the  Possibility  of  Including  the  Truck  Center  Dimension  of 
All  Cars  in  the  Official  Railway  Equipment  Register,  Collaborating 
as  Necessary  or  Desirable  with  the  Mechanical  Division,  AAR. 
This  investigation  has  just  been  completed  and  it  was  found  to  be 
possible  to  include  this  additional  information  in  the  publication  by 
action  of  the  individual  railroads  and  car  owners.  A  formal  report  is 
now  being  prepared. 

The  Committee  on  Clearances, 

L.  ScHMiTZ,  Chairman. 


Clearances 339 

Report   on   Assignment  3 

Investigate  New  Methods  and  Development  of 

Equipment  for  Recording  Measurements  of 

Clearances  of  Structures  Along   Right-of- 

Way  and  Overall  Dimensions  of 

Cars  and   Loads 

W.  S.  TusTiN  (chairman,  subcommittee),  E.  Berendt,  C.  W.  Parrel,  G.  P.  Huhlein, 
R.  G.  Klouda,  W.  E.  Morgus,  R.  R.  Snyder. 

A  questionnaire  submitted  to  all  members  of  Committee  28  requesting  infor- 
mation on  their  metliods  of  obtaining  clearances  and  clearing  shipments  resulted  in 
replies  from  20  raihoads.  Of  this  representative  20,  11  railroads  reported  obtaining 
their  field  clearance  measurements  manually  with  a  survey  party,  three  reported  a 
combination  of  the  manual  method  and  the  use  of  a  "feeler"  type  clearance  car, 
three  reported  use  of  the  "feeler"  type  clearance  car  only,  and  the  remaining  three 
reported  use  of  a  photographic  "scope"  car.  Two  new  methods  mentioned  were 
stereoscopic  photography  used  by  the  Swiss  Federal  Railways  and  a  system  using 
photoelectric  cells.  However,  these  methods  are  not  currently  being  used  in  this 
country  and  there  was  not  enough  information  available  for  proper  evaluation. 

Five  railroads  of  the  representative  20  reported  using  computers  in  clearing 
oversize  sliipments  on  tlieir  lines,  the  remaining  15  using  the  old  clearance  chart 
method,  however,  three  of  these  indicated  they  were  currently  developing  computer 
programs. 

Investigation  on  this  subcommittee  assignment  has  been  completed  and  a  final 
report  now  being  prepared  detailing  the  various  current  methods  of  obtaining 
clearance  infonnation  in  this  country.  This  will  be  submitted  for  possible  inclusion 
in  tlie  Manual  when  completed. 


Report  of  Committee  6 — Buildings 


W.  C.  Sturm,  Chairman 

E.    P.    BOHN, 

Vice  Chairman 
O.  C.  Denz,  Secretary 


T.  H.  Seep 
J.   G.  Robertson 
W.  C.  Humphreys 
Richard  Hale 
j.  a.  comeau 
D.  A.  Bessey 
W.  F.  Abmstkong 
S.  D.  Arndt 

F.  R.  Bartlett 

G.  J.  Bleul 
G.  T-  Ghamraz 

F.  b.  Day 

C.    M.    DiEHL 

G.  W.   Fabrin 

C.  S.  Graves  (E) 
A.  R.  Gualtieri 
W.  G.  Harding  (E) 
J.  W.  Hayes 
H.  R.  Helker 
S.  B.  Holt 


K.    E.    HORNUNG 

C.  R.  Madeley 
R.  J.  Martens 
R.  W.  Milbauer 
L.  S.  Newman 
John  Norman 
L.  A.  Palagi 
T.  F.  Peel 
P.  W.  Peterson 
R.   E.  Phillips 

R.    D.    POWRIE 

R.  F.  Roberts 
J.  H.  Rump 

J.    E.    SCHAUB    (E) 

H.  A.  Shannon,  Jr. 

J.  S.  Smith 

S.  G.  Urban 

W.  M.  Wehner 

T.  S.  Williams  (E) 

Committee 


(E)    Member  Emeritus. 

Those   whose   names   are   shown   in   boldface,  in  addition  to  the  chairman,   vice   chairman   and 
secretary,    are    the    subcommittee    chairmen. 

To  the  American  Raitway  Engineering  Association: 
Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 

Subcommittee  assisted  on  Assignments  1  and  2  in  placing  report  in 
decimal  format  for  publication  as  Manual  material.  Subcommittee  to 
review  Chapter  6  of  the  Manual  for  possible  revision  and  upgrading. 

1.  Design  Criteria  for  Maintenance  of  Way  Equipment  Repair  Shops. 
Final  report,  submitted  for  adoption  and  publication  in  the  Manual, 
was  printed  in  Part  1  of  Bulletin  655,  November-December  1975. 

2.  Design  Criteria   for  Elevated  Yard  Office  Buildings. 

Final  report,  submitted  for  adoption  and  publication  in  the  Manual, 
was  printed  in  Part  1  of  Bulletin  655,  November-December  1975. 

3.  Design  Criteria  for  Freight  Forwarding  Facilities. 
Outline  for  proposed  report  reviewed  at  summer  meeting. 

4.  Inspection  and  Maintenance  of  Railway  Buildings. 

A  series  of  reports  on  various  components  of  railway  buildings  will 
be  submitted  under  this  assignment.  The  first  report,  which  will  cover 
inspection   and   maintenance   of   roofs,   will   be   published   in   1976. 

5.  Architectural   Design   Competition. 

Report  on  progress  of  tlie  Competition  and  the  Competition  Problem 
submitted  as  information    page  342 

The  Committee  on  Buildings, 
Walter  Carson  Sturm,  Chairman. 

341 


342       Bulletin  656 — American  Railway  Engineering  Association 

Report  on  Assignment  5 

Architectural  Design  Competition 

D.  A.  Bessey  (chairman,  subcommittee),  E.  P.  Bohn,  J.  A.  Comeau,  F.  D.  Day, 
G.  W.  Fabrin,  R.  Hale,  J.  W.  Hayes,  S.  B.  Holt,  K.  E.  Hornung,  W.  C. 
Humphreys,  C.  R.  Madeley,  R.  J.  Martens,  R.  W.  Milbauer,  L.  S.  Newman, 
L.  A.  Palagi,  p.  W.  Peterson,  R.  E.  Phillips,  R.  D.  Powrie,  J.  G.  Robertson, 
J.  H.  Rump,  H.  A.  Shannon,  W.  C.  Sturm,  S.  G.  Urban. 

Your  committee  submits  the  following  report,  as  information,  on  tlie  direction 
of  an  Architectural  Design  Competition  for  college  and  University  students: 

GENERAL  STATEMENT 

The  AREA  Board  of  Direction  at  its  meeting  on  March  25,  1975,  approved 
the  funding  of  an  Architectural  Design  Competition  for  college  and  university 
students  during  the  Fall  of  1975. 

In  staffing  the  architectural  or  building  departments  of  railway  companies  it 
is  necessary  to  familiarize  tlie  architectural  students  throughout  the  United  States 
and  Canada  with  railroad  architecture  and  to  bring  about  an  awareness  of  employ- 
ment opportunities  in  the  railroad  industry.  There  is  a  definite  need  to  improve 
communications  between  the  railroad  industry  and  colleges  and  universities  having 
architectural  programs. 

The  idea  of  conducting  an  Architectural  Design  Competition  was  originally 
proposed  in  1971  which  resulted  in  the  fonnation  of  a  special  subcommittee  to 
contact  various  universities  and  to  prepare  a  preliminary  draft  of  the  program.  Upon 
receiving  favorable  response  from  the  universities,  the  subcommittee  proceeded 
to  develop  the  program. 

The  building  selected  by  the  committee  for  the  competition  was  a  control 
tower  and  service  building  for  a  railroad  classification  yard.  It  was  felt  by  the 
committee  that  this  type  of  building  would  offer  the  participating  student  a  challeng- 
ing and  informative  project. 

The  preliminary  draft  of  the  Competition  was  sent  to  79  colleges  and  universities 
in  the  United  States  and  10  in  Canada;  as  of  October  1,  1975,  27  universities,  24  in 
the  United  States  and  3  in  Canada,  have  elected  to  participate.  Approximately  800 
students  will  be  involved  in  the  Competition.  A  representative  of  Committee  6  has 
been  assigned  to  each  school  participating.  He  will  act  as  an  advisor,  who  will  assist 
the  school's  architectural  staff  in  matters  dealing  with  the  Competition.  D.  A.  Bessey, 
a  former  chairman  of  Committee  6,  has  been  appointed  director  of  the  Competition 
and  will  administer  the  Competition  for  the  committee. 

The  entries  will  be  judged  by  a  panel  of  seven  railroad  architects  who  are 
members  of  Committee  6  and  who  represent  a  general  cross  section  throughout  the 
United  States  and  Canada.  All  entries  are  to  be  submitted  to  the  director  of  the 
Competition  by  January  31,  1976,  and  will  be  judged  in  mid-February. 

Cash  awards  of  $500  for  first  prize,  $250  for  second  prize  and  5  honorable 
mentions  of  $50  each  have  been  authorized  by  the  Association.  The  winning  student 
will  be  invited  to  appear  at  the  Annual  Technical  Meeting  of  the  AREA  to  be  held 
at  the  Palmer  House  in  Chicago,  and  will  give  a  presentation  of  his  winning  entry 
on  March  23  as  part  of  a  special  feature  to  be  presented  by  Committee  6. 


Buildings 


343 


The  members  of  Committee  6  have  devoted  considerable  time  and  effort  in  the 
preparation  and  implementation  of  the  Competition.  The  committee  is  looking  for- 
ward to  an  interesting  and  worthwhile  relationship  between  the  railroad  industry 
and  the  architectural  students  in  colleges  and  universities  throughout  the  United 
States  and  Canada. 


LIST  OF  PARTICIPATLXG  UNIVERSITIES 


University  of  Arkansas 
Fayetteville,  Arkansas 
E.  F.  Jones,  Chairman 

University  of  .Arizona 

Tucson,    Arizona 

Robert  E.  McConnell,  Dean 

Arizona  State  University 

Tempe,  .Arizona 

Robert  G.  Hershberger,  Dean 

Ball  State  University 

Muncie,  Indiana 

Anthony  J.  Costello,  Dean 

Boston  Architectural  Center 

Boston,  Massachusetts 

Sanford  R.  Greenfield,  Director 

University  of  California 

Berkeley,  California 

Richard  C.   Peters,   Chairman 

Catholic  Universit>'  of  America 
\Va.shington,   D.   C. 
Forrest  Wilson,  Chaimian 

Clemson  University 
Clemson,  South  Carolina 
Harlan  E.   McClure,  Dean 

University   of   Colorado 

Boulder,   Colorado 

Robert   C.    Utzinger,   Director 

University    of    Detroit 
Detroit,   Michigan 
Brvmo  Leon,  Dean 

Georgia  Institute  of  Technology 

Atlanta,  Georgia 

Paul  M.   Hefternan,   Director 

Harvard   University 
Cambridge,  Massachusetts 
George  Anselevicius,  Chairman 

University    of    Illinois 
Urbana,    Illinois 
G.  Day  Ding,  Head 

University   of   Kentucky 
Lexington,   Kentucky 
Anthony   Eardley,    Dean 


University'  of  Minnesota 
Minneapolis,  Minnesota 
Ralph  Rapson,  Head 

University  of  Nebraska 

Lincoln,    Nebraska 

W.  Cecil  Steward,  Dean 

University  of  Notre  Dame 

South   Bend,   Indiana 

.Ambrose  M.  Richardson,  Chairman 

Oklahoma  State  University 
Stillwater,    Oklahoma 
Mark  T.  Jaroszewicz,  Head 

University  of   Oregon 

Eugene,    Oregon 

Wilmot  G.  Gilland,  Head 

Pratt  Institute 
Brooklyn,   New  York 
Alan  J.   Forrest,  Director 

Rhode   Island  School  of  Design 
Providence,  Rhode  Island 
Derek  Bradford,  Dean 

University  of  Southern  California 
Los    Angeles,    California 
Gerald  G.  Weisbach,  Asso.  Dean 

Texas  Tech  University 

Lubbock,  Texas 

Nolan  E.  Barrick,  Chairman 

Tuskegee  Institute 
Tuskegee,  Alabama 
Charles  C.  Hight,  Head 

University  of  Calgary 
Calgary,    Alberta,    Canada 
James  McKeller,  Head 

Nova  Scotia  Technical  College 
HaUfax,  Nova  Scotia,  Canada 
P.  Manning,  Director 

University  of  Waterloo 
Waterloo,   Ontario,   Canada 
Fraser  Watts,  Director 


344       Bulletin  656 — American  Railway  Engineering  Association 
RULES  OF  THE  COMPETITION  AND  PROGRAM 


ARCHITECTlim 
COMPETITION 


CONTROL  TOWER 

AND 

SERVICE    BUILDING 

FOR 

RAILROAD 
CLASSIFICATION    YARD 


I  liMERICAN 
I   llAILWAY 
I   HNGINEERING 
m   ttsSOCIATION 


COMMITTEE 


6 


BUILDINGS 


Buildings 345 

AMERICAN  RAILWAY  ENGINEERING  ASSOCIATION 

The  American  Railway  Engineering  Association  is  a  non-profit  organization 
whose  objective  is  the  advancement  of  knowledge  pertaining  to  the  scientific  and 
economic  location,  construction,  operation  and  maintenance  of  railways.  Founded 
in  1899,  its  membership  is  primarily  composed  of  employees  of  the  Engineering 
Departments  of  Railway  Companies.  Committee  6,  which  is  sponsoring  this  Compe- 
tition, is  the  Buildings  Committee  of  the  American  Railway  Engineering  Association, 
whose  membership  consists  of  Architects,  Building  Engineers  and  Designers. 

Rules  of  the  Competition 

Judging  of  the  Competition 

The  entries  in  tlie  Competition  will  be  impartially  judged  based  on  aptness  of 
tlie  solution  and  originality  of  design.  The  judges  will  be 

R.  Hale,  Architect,  Atchison,  Topeka  &  Santa  Fe  Railway,  Los  Angeles,  Calif. 

AA  in  Architecture,  Los  Angeles  City  College  and  BA  in  Architecture,  University 
of  Southern  California.  License:   California  &  Arizona.  Certified:   NCARB. 

K.  E.  Hornung,  Assistant  Chief  Engineer — Structures,  The  Milwaukee  Road,  Chicago. 
Architectural  Engineering,  Iowa  State,  and  BA,  University  of  Minnesota.  License: 
Illinois,   Iowa,  Minnesota  and  Wisconsin. 

W.  C.  Humphreys,  Architect,  Penn  Central  Transportation  Company,  Philadelphia,  Pa. 
Illinois  Institute  of  Technology,  Chicago,  and  Pratt  Institute,  Brooklyn,  N.  Y. 
License:  Illinois,  New  York,  Pennsylvania,  Minnesota,  Connecticut  and  New 
Jersey. 

L.  S.  Newman,  General  Architect,  St.  Louis-San  Francisco  Railway,  Springfield,  Mo. 
BA  in  Architecture,  Oklahoma  State  University,  Stillwater,  Okla.  License: 
Missouri  and  Tennessee. 

L.  A.  Palagi,  Architect,  Ellington  Miller  Co.,  Chicago. 
Illinois  Institute  of  Technology.  License:   Illinois. 

R.  D.  Powrie,  Senior  Architect,  Canadian  Pacific  Rail,  Montreal,  Que. 

BA,    University  of  Toronto.   License:    Order  of  Architects  of  Quebec, 

S.  G.  Urban,  Architect  (Retired),  Missouri  Pacific  Railroad. 

Master  of  Architecture,  Washington  University,  St.  Louis,  Mo.  License:  Missouri 
and  Texas. 

Method  of  Submission 

Entries  shall  be  submitted  on  two  white  illustration  boards  measuring  30  inches 
by  40  inches  securely  fastened  together.  No  name  or  school  affiliation  shall  appear 
on  the  face  of  the  board.  Name  and  address  of  entrant  together  with  school  affiliation 
shall  be  placed  on  the  reverse  side  of  each  board  in  an  area  3  inches  by  5  inches  and 
shall  be  covered  by  an  opaque  white  index  card  securely  taped  so  name,  address 
and  affiliation  cannot  be  seen.  Boards  shall  be  shipped  together  so  that  both  parts 
of  each  entry  may  be  numbered  vipon  arrival.  Boards  shall  be  titled  as  shown  in 
Exhibit  1. 

Date  of  Submission 

Entries  shall  be  sent  to  the  Director  of  the  Competition: 


346       Bulletin  656 — American  Railway  Engineering  Association 

D.   A.   Bessey,  Architect 

Chicago,   Milwaukee,   St.  Paul  &  Pacific  Railroad 

Room  809,  516  W.  Jackson  Blvd. 

Chicago,  Illinois  60606   (Telephone:   312-236-7600) 

Entries  must  be  received  prior  to  midnight,  January  31,  1976,  to  be  con- 
sidered. Winners  will  be  notified  no  later  than  February  20,  1976. 

Awards 

The  following  awards  will  be  made: 

First  Prize         $500 
Second  Prize         $250 
Honorable  Mention  (5)  $  50  each 

Drawings  to  Become  Property  of  AREA 

All  drawings  entered  will  become  the  property  of  the  American  Railway 
Engineering  Association.  Drawings  may  be  published  in  the  Proceedings  of  tlie 
Association  and  in  industry  trade  publications  at  the  discretion  of  the  Association. 

Winner  to  Appear  at  Annual  Technical  Conference 

The  first-place  winner  will  be  invited  to  appear  at  the  Annual  Technical  Con- 
ference of  the  Association  to  be  held  at  the  Palmer  House,  Chicago,  on  March  23, 
1976.  Winner  shall  be  prepared  to  give  a  10-minute  oral  presentation  of  his  entry. 
Travel,  lodging  and  food  for  the  winner  shall  be  arranged  and  paid  for  by  the 
Association. 

Presentation  Requirements 

The  "Design  Presentation"  should  be  considered  as  the  presentation  normally 
given  by  an  architect  to  a  client.  It  should  be  executed  in  a  professional  manner. 
Presentation  requirements  are  as  follows: 

1.  Site  plan  at  1/16"  =  I'-O" 

2.  All  floor  plans  at  Js"  =  I'-O"  with  indication  of  furniture  and  equipment 

3.  Two  elevations  at  %"  =  I'-O"  indicating  finish  materials 

4.  Cross  section  at  M"  =  I'-O"  indicating  materials  used  in  consruction 

5.  Perspective  of  building 

Note:  Site  plan,  floor  plans,  elevation  and  section  to  be  done  in  black  and 
white.  Color  may  be  used  on  perspective  only. 

Inquiries 

Inquiries  shall  be  made  to  the  director  of  the  Competition  and  his  decisions 
shall  be  final  and  binding. 

Note:  A  draft  of  a  report  on  Elevated  Yardmaster's  Towers  prepared  by  AREA 
Committee  6  and  containing  recommendations  for  the  design  of  this  type  of  structure 
is  attached.  It  is  to  be  noted  that  information  included  in  this  report  is  of  recom- 
mendatory nature  and  is  not  binding  upon  the  railroads  or  participants  in  the  compe- 
tition but  is  submitted  as  information  only. 

W.  C.  Sturm,  Chairman  E.  P.  Bohn,  Vice  Chairman 

Senior  Project  Engineer  Engineer  Buildings 

Elgin,  Joliet  &  Eastern  Railway  Louisville  &  Nashville  Railroad 

Joliet,  111.  Louisville,  Ky. 


Buildings 


347 


Exhibit  1 


CONTROL   TOWER    AND    SERVICE    BUILDING 
^4   FO»     RAILROAD    CLASSIFICATION    YARD 


AREA    COMMITTEE     6 
COMPETITION 


coja 

'Mm. 


zo' 


40 


(REAR  Of    BOARD  ) 


348       Bulletin  656 — American  Railway  Engineering  Association 

The  Problem 

General  Scope 

The  problem  consists  of  a  design  for  a  Control  and  Service  Bulding  for  a 
railroad  classification  yard.  A  classification  yard  is  a  railroad  facility  that  receives 
freight  trains  and  individual  freight  cars  that  are  uncoupled  and  classified  into 
nuinerous  yard  tracks  where  trains  are  made  up  and  dispatched  to  various  desti- 
nations. The  particular  type  of  classification  yard  in  this  problem  is  commonly  called 
a  "hump  yard. "  The  operation  of  the  hump  yard  involves  the  uncoupling  of  cars 
at  the  top  of  an  incline  allowing  tlie  cars  to  move  by  gravity  down  the  incline  and 
be  automatically  switched  into  various  yard  tracks.  There  are  devices  called  retarders 
tliat  apply  pressure  against  the  wheels  of  the  freight  cars  as  they  move  down  the 
incline  which  regulate  their  speed.  The  Building  in  the  problem  is  the  central  control 
point  for  the  entire  hump  yard  operation. 

The  Building  will  house  air  compressors  which  produce  compressed  air  to 
operate  the  retarding  equipment.  There  will  also  be  shop  facilities  to  maintain  the 
equipment,  welfare  and  washroom  facilities  for  employees,  electronic  equipment, 
computer  room  and  the  operators  control  station. 

Site  Information 

The  Building  will  be  located  south  of  tire  classification  yard  tracks  as  indicated 
on  the  site  plan   (Exhibit  2). 

Provide  parking  facilities  for  30  automobiles  which  shall  be  located  soutli  of 
the  building  and  separated  from  the  railroad  yard  operation. 

The  railroad  property  line  is  parallel  to  tlie  main  hump  track  and  is  located 
200  ft  south  of  the  proposed  building  location.  Parallel  to  the  railroad  right-of-way 
line  is  a  frontage  road  widi  a  100-ft  right-of-way.  Beyond  the  frontage  road  is  a 
four-lane  interstate  highway  with  a  residential  development  located  south  of  the 
interstate  highway. 

There  is  a  mass  transit  bus  line  operating  on  the  frontage  road. 

Zoning  Ordinances 

A  nearby  airport  restricts  the  total  height  of  buildings  to  45  ft. 

Building  Code 

Current  edition  of  Uniform  Building  Code  or  National  Building  Code  of  Canada. 

Fire  Limits 

Building  shall  be  of  fire-resistant  construction. 

Building  Design  Criteria 

1.  Compressor  room  widi  a  minimmn  of  600  sq  ft  containing  two  air  compres- 
sors. The  compressors  measure  5  ft  x  10  ft  x  6  ft  high,  weigh  8,000  lb  each  and  are 
mounted  on  vibration  absorption  pads.  The  electric  control  cabinet  for  the  compres- 
sors will  be  wall-mounted  with  a  dimension  of  2  ft  deep  x  18  ft  long  x  6  ft  high. 

2.  Small  elevator — maximum  four  passengers. 

3.  Mechanical   room   for  heating   and   air-conditioning  equipment. 

4.  Shop  and  storage  room  for  moderately  heavy  bench  work.  Area  shall  be  a 
minimum  of  500  sq  ft  and  shall  be  used  for  repauing  "car  retarding  equipment." 
The  largest  component  of  this  equipment  weighs  300  lb. 


Buildings 349 

5.  Washroom  facilities  for  yard  switching  crews  and  maintenance  personnel, 
consisting  of  locker  room,  toilet  room  and  lunch  room  area.  The  vending  machines 
are  to  be  located  in  the  lunch  room  area.  Locker  room  to  accommodate  seventy 
18-  X  18-  X  72-in.  lockers.  Lockers  may  be  back  to  back.  A  maximum  of  30  personnel 
will  occupy  this  space  at  any  one  time. 

6.  Electronic  equipment  room  witli  minimum  of  800  sq  ft.  The  equipment 
which  controls  tlie  operation  of  the  car  retarders  and  switching  is  mounted  on  shelf 
type  racks  2  ft  wide  x  4  ft  long  and  8  ft  6  in.  high.  The  equipment  racks  are  installed 
in  rows  with  a  minimum  of  4-ft  aisles  between  racks  with  access  to  both  sides  of 
racks. 

7.  Storage  room  of  a  minimum  of  200  sq  ft  for  electronic  parts  which  shall  be 
adjacent  to  electronic  equipment  room. 

8.  An  area  for  light  bench  work  to  repair  electronic  component.  The  largest 
of  these  components  weighs  20  lb.   This  repair  function  is  a  one-person  operation. 

9.  Communication  equipment  area  with  a  minimum  of  200  sq  ft. 

10.  Operators  control  room  with  a  minimum  of  200  sq  ft.  The  room  shall  contain 
a  control  console  which  is  an  8  ft  long  x  3  f t  wide  table.  The  operator  sitting  at  the 
table  shall  have  a  clear  view  to  the  east,  north  and  west  and  shall  be  able  to  view 
the  ground  at  a  point  70  ft  nortli  of  the  building  and  beyond.  The  top  of  the  table 
shall  be  35  ft  above  ground  level. 

11.  Computer  room  with  a  minimum  of  500  sq  ft,  which  shall  contain  a  raised 
floor  12  in.  above  the  structural  floor  which  shall  contain  power  and  control  cables 
for  the  computer  equipment. 

12.  Office  for  computer  room  supendsor  and  two  clerks. 

13.  Toilet  facilities  for  control  room  operator  and  computer  room  personnel. 
There  will  be  a  maximum  of  four  people  of  each  sex  at  any  one  time  and  tliere  shall 
be  separate  toilet  facilities  for  men  and  women. 

General  Information 

The  railroad  yard  and  the  general  site  in  the  vicinity  of  die  building  shall  be 
restricted  to  railroad  employees  only. 

The  hump  yard  operation  is  carried  out  24  hours  a  day,  seven  days  a  week. 

The  building  shall  he  air-conditioned. 

There  shall  be  two  air  reservoir  tanks  located  east  or  west  of  the  building  and 
relatively  close  to  the  compressor  room.  Tank  size  is  8  ft  in  diameter  and  30  ft  long. 

The  car  retarder  system  produces  a  high-frequency  sound  of  120  decibels  at 
100  ft. 


350       Bulletin  656 — American  Railway  Engineering  Association 


Report  of  Committee  7 — Timber  Structures 


W.  S.  Stokely, 
Chairman 

J.    A.    GlSTAFSON, 

Vice  Chairman 
J.  W.  Chambers, 
Secretary 


J.    BUDZILENI 

J.  M.  Helm 

j.  H.  HuzY 

G.  X.  Sells 

R.  C.  Moody 

H.  R.  Stokes 

B.   T.  King 

G.  K.  Clem 

M.  J.  Marlow 

R.  E.  Anderson 

T.  E.  Brassel 

F.  H.  Cramer  (E) 

M.  J.   Crespo 

A.  R.  Dahlberg 

B.  E.  Daniels 
H.  E.  Dearing 

K.  L.  DeBlois  (E] 
D.  J.  Engle 
S.  L.  Goldberg 
D.  C.  Gould 
R.  W.  Gunther 
J.  A.  Hawley 


W.  C.  Kirkland 
D.  I.  Kjellman 
H.  G.  Kriegel 

L.    R.    KUBACKI 
R.    E.    KUEHNER 

C.  V.  Lund  (E) 

D.  H.  McKibben 

C.  H.  Newlin 
W.  A.  Oliver 
\.  I.  Pinson 
R.  P.  Rasho 

J.  J.  Ridgeway 

D.  y.  Sahtore 

F.  E.   Schneider   (E) 

J.  W.  Storer 

R.  W.  Thompson,  JR- 

W.  A.  Thompson 

J.  B.  WeRxNer 

N.  E.  Whitney 

A.  Youhanaie 

S.  J.  Zajchowski 

Committee 


( E )    Member  Emeritus. 

Those  whose  names   are  shown  in  boldface,  in   addition  to   the   chairman,   vice   chainnan  and 
secretary,    are    the    subcommittee    chairmen. 

To  the  American    Railway   Engineering  Association: 
Your  committee  reports  on  the  following  subjects: 

B.   Re\ision  of  Manual. 
Xo  report. 

2.  Grading  Rules  and  Classification  of  Luml>er  for  Railway  Use;  Speci- 
fications for  Structural  Timber,  Collaborating  with  Other  Organizations 
Interested. 

Xo  report. 

3.  Specification  for  Design  of  Wood  Bridges  and  Trestles. 
No  report. 

4.  Methods  of  Fireproofing  Wood  Bridges  and  Trestles,  Including  Fire- 
Retardant  Paints. 

Final  report,   submitted  as  information    page  352 

5.  Design  of  Structural  Glued-Laminated  W'ood  Bridges  and  Trestles. 
Xo  report. 

7.  Repeated  Loading  of  Timber  Structures. 
Xo  report. 

8.  Protection  of  Pile  Cut-Offs;  Protection  of  Piling  Against  Marine 
Organisms    by    Means    Other   Than    Preservative. 

No  report. 


Bui.  656 


351 


352       Bulletin  656 — American  Railway  Engineering  Association 

9.  Stud>-    of    In-PIace   Presei-vative    Treabiient   of   Timber   Trestles. 
No  report. 

10.   Non-Destructive  Testing  of  Wood. 
No  report. 

The  Committee  on  Timber  SxRUCTtrRES, 

W.  S.  Stokely,  Chairman. 


Report  on  Assignment  4 

Methods  of  Fireproofing  Wood  Bridges  and  Trestles, 
Including  Fire-Retardant  Paints 

G.  N.  Sells  (chairman,  subcommittee),  B.  J.  King,  M.  J.  Marlow,  B.  E.  Daniels, 
D.  H.  McKiBBEN,  N.  E.  Whitney,  J.  B.  Werner,  J.  W.  Stoker,  H.  G.  Kriegel. 

Your  committee  submits  the  following  report  as  information.  Due  to  the 
inactivity  of  research  in  this  field,  the  committee  recommends  tliat  the  subject  be 
discontinued  until  such  time  as  new  products  are  available  and  warrant  the  re- 
creation of  a  subcommittee. 

The  reader  is  directed  to  reports  on  this  topic  in  the  reports  of  Committee  7 
contained  in  AREA  Proceedings,  Volumes  40,  42,  51,  54,  55,  56,  57,  59,  61,  62 
and  64. 

Currently  there  are  two  products  being  actively  marketed  in  die  area  of  timber 
fireproofing.  Both  are  known  by  proprietary  names.  One  of  the  products  is  designed 
to  be  applied  to  a  completed  structure,  the  second  is  applied  to  the  timber  members 
by  a  plant  process  prior  to  assembly  to  a  structiu-e. 

A  member  road  reports  the  following  experience  with  an  applied  type  product 
placed  in  service  in  July  of  1974. 

The  material  was  applied  to  twenty  6-pile  bents  averaging  8  ft  in  height  with 
one  pair  of  sway  braces  ( no  sash  brace )  and  the  exposed  sides  of  caps,  stringers  and 
decking. 

An  estimated  9300  sq  ft  of  surface  in  tlie  bents  and  decking  was  coated  with 
approximately  345  gal  of  the  material  to  a  thickness  of  45  mils.  Spraying  time  was 
approximately  1200  sq  ft  per  hour. 

The  installation  was  made  very  closely  following  the  manufacturer's  recom- 
mendations and  guidelines  with  one  exception.  The  pump  was  placed  directly  in 
the  drum  and,  in  the  other  bung,  a  pressure  relief  valve  and  gage  were  inserted, 
making  the  drum  a  pressure  pot  instead  of  using  the  prescribed  pressvire  pot.  This 
eliminated  tiie  labor  of  transferring  the  material  as  well  as  cleaning  up  tlie  pressure 
pot. 

Sufficient  time  has  not  yet  elapsed  to  fully  evaluate  the  durability  of  the  material; 
however,  one  inspection,  at  age  7  months,  showed  no  change  in  the  appearance 
or  features  of  the  material  as  applied. 


Reporf  of  Committee  8 — Concrete 
Structures  and  Foundations 


T.  L.  Fuller,  Chairman 
J.  W.  DeValle, 
Vice  Chairman 
R.  J.  Brueske 
T.  R.  Moore 
G.  W.  Cooke 
J.  M.  Williams 
J.  R.  Williams 
T.  R.  Kealey 
W.  F.  Baker 
E.  R.  Blewitt 
W.  E.  Brakenstek 
X.  D.  Bryant 


G.  F.  Dalquist 
M.  T.  Davisson 

J.    T.    DOHERTY 

B.  M.    DORNBLATT 

R.  A.  DoRscH 

D.  H.  DowE  (E) 
M.  E.  Dust 

F.  C.  Edmonds 
J.  A.  Erskine 
Benard  Fast 

G.  W.  Gabert 
W.  L.  Gamble 

E.  F.  Grecco 

R.  J.  Hallawell 
W.  A.  Hamilton,  Jr. 

C.  W.  Harman 
P.  Haven,  U 
W.  P.  Hendrix 

J.    O.    HOLLADAY 

A.  K.  Howe 
W.  R.  Hyma 

J.   R.   IWINSKI 

T.  F.  Jacobs 

F.  a.  Kempe 
R.  H.  Kendall 

F.  W.  Klaiber 
Louis  Lange,  Jr. 
R.  H.  Lee 

G.  F.  Leyh 
J.  K.  Lynch 
E.  F.  Manley 


E.  C.  Mardorf 
J.  F.  Marsh 
R.  J.  McFarlin 
L.  M.  Morris  (E) 
E.  S.  Neely,  Sr. 
David  No\ick 
R.  E.  Pearson 
J.  A.  Peterson 
J.  E.  Peterson 
M.  Pekarsky 
H.  D.  Reilly 
E.  D.  Ripple 

E.   E.   RUNDE 

H.  R.  Sandberg 

J.  H.  Sawyer,  Jr. 

M.  P.  Schindler 

J.  E.  Scroggs 

J.  R.  Shafer 

J.  P.  Shedd 

L.  F.  Spaine 

C.  H.  Splitstone  (E) 

W.  B.  Stanczyk 

R.  G.  Stilling 

Anton  Tedesko 

M.    FUAT  TiGRAK 

W.  J.  VENxm 
J.  W.  Weber 
J.  O.  Whitlock 
W.  R.  Wilson  (E) 

Committee 


(E)   Member  Emeritus. 

Those  whose   names   are   shown   in  boldface,   in   addition  to  the   chainnan  and  vice   chairman 
are    the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 

Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 

No   manual   recommendations   made  this   year. 

1.  Design  of  Masonry  Structures,  Collaborating  as  Necessary  or  Desirable 
with  Committees  1,  5,  6,  7,  15  and  28. 

Brief   status  statement    page  354 

2.  Foundations  and  Earth  Pressures,  Collaborating  as  Necessary  or  Desir- 
able with  Committees  1,  6,  7  and  15. 

Brief  progress  report,  submitted  as  information page  355 

3.  Waterproofing   for   Railway   Structures,   Collaborating   as   Necessary   or 
Desirable  with  Committees  6,  7  and   15. 

Brief  progress  report,  submitted  as  information   page  355 


353 


354       Bulletin  656 — American  Railway  Engineering  Association 

4.  Concrete  Components  for  Timber  Trestles,  Collaborating  as  Necessary 
or  Desirable  with  Committee  7. 

Brief  progres  report,  including  drawing,  submitted  as  information    .  .    page  355 

5.  Pier  Protection  (Fender  Systems)  at  Spans  on  Navigable  Streams,  Col- 
laborating as  Necessary  or  Desirable  with  Committees  7  and  15. 

Brief  progress  report,  submitted  as  information page  357 

The  Committee  on  Concrete  Structures  and  Foundations, 

T.  L.  Fuller,  Chairman. 

Report  on  Assignment   1 

Design  of  Masonry  Structures 

J.  R.  Moore  (chairman,  subcommittee),  W.  F.  Baker,  W.  E.  Brakensiek,  J.  "W. 
DeValle,  J.  T.  Doherty,  R.  A.  Dorsch,  M.  E.  Dust,  F.  C.  Edmonds,  J.  A. 
Erskine,  T.  L.  Fuller,  G.  W.  Gabert,  W.  L.  Gamble,  E.  F.  Grecco,  W.  A. 
Hamilton,  C.  W.  Harman,  W.  R.  Hyma,  F.  A.  Kempe,  F.  W.  Klaiber, 
R.  H.  Lee,  G.  F.  Leyh,  J.  K.  Lynch,  J.  F.  Marsh,  R.  E.  Pearson,  J.  E.  Peter- 
son, E.  D.  Ripple,  J.  H.  Sawyer,  J.  E.  Scroggs,  R.  K.  Shortt,  L.  F.  Spaine, 
A.  Tedesko,  M.  Fuat  Tigrak,  W.  J.  Venuti,  J.  W.  Weber,  J.  O.  Whitlock, 
J.  R.  Williams,  W.  R.  Wilson. 

The  subcommittee  is  continuing  work  on  changing  design  loading  to  E-80 
from  E-72  and  other  upgrading  of  tlie  design  portions  of  Chapter  8  of  the  Manual. 

Work  has  continued  on  ultimate  strength  load  factor  design  as  a  possible 
alternate  to  working  stress  design  for  concrete  bridges.  Standard  concrete  spans 
(designed  by  working  stress  method)  are  being  analyzed  by  load  factor  design  and 
ultimate   strength  methods   to   develop   correlations  between  the  methods. 


Concrete   Structures   and   Foundations 355 

Report  on  Assignment  2 

Foundations  and  Earth  Pressures 

G.  W.  Cooke  (cliairman,  subcommittee),  G.  F.  Dalquist,  M.  T.  Davisson,  B.  M. 

DORNBLATT,      B.     FaST,     P.     HaVEN,     II,     R.     J.     HalLAWELL,     J.     D.     HOLLADAY, 

T.   R.   Kealey,   R.   H.   Kendall,  E.  F.  Manley,  E.  C.   Mardorf,  D.  Novick, 
M.  P.  ScHiNDLER,  J.  R.  Shafer,  W.  B.  Stanczyk. 

Revisions  to  Manual  material  submitted  for  adoption  were  published  in  Bulletin 
650.  This  included  entire  new  Part  3 — Specifications  for  Design  of  Spread  Footings. 

Work  is  in  progress  on  revisions  to  Part  4 — Pile  Foundations,  and  to  Drilled 
Shafts  and  Caissons,  originally  published  as  information  in  Bulletin  641,  January- 
February   1973. 

Work  is  in  progress  to  discover  reasons  for  inconsistencies  in  the  results  obtained 
using  the  Coulomb  and  Boussinesq  fonnula  in  Part  20  for  point,  line  and  strip 
surcharge  loadings. 


Report  on  Assignment  3 

Waterproofing  for  Railway  Structures 

J.   M.  Williams  (chairman,  sxih committee),  E.  R.  Blewitt,  W.  P.  Hendrix,  A.  K. 
Howe,  J.   R.   Iwinski,  L.  Lange,   M.  Pdcarsky,  H.  D.  Reilly,  E.  E.  Runde, 
R.  G.  Stilling. 

Work  is  in  progress  for  possible  inclusion  of  ethylene-propylene-diene-monomer 
(EPDM)  as  an  alternate  to  butyl  membrane  or  rubberized  asphalt  and  plastic  film 
membrane. 

Report  on   Assignment  4 

Concrete  Components  for  Timber  Trestles 

J.   R.   Williams  (cJiairman,  subcommittee),  W.  F.  Baker,  J.  W.  DeValle,  G.  W. 
Harman,  J.  R.  Iwinski,  E.  E.  Runde,  J.  E.  Scroggs. 

The  subcommittee  has  completed  plans  for  a  precast,  prestressed  concrete  cap/ 
sill  for  usage  in  timber  trestles.  This  was  developed  to  meet  tlie  various  requirements 
of  railroads  presently  using  concrete  caps  in  conjunction  with  suppliers  of  those 
caps.  Standardization  on  the  recommended  cap  should  benefit  both  users  and 
suppliers.  Typical  connection  details  were  not  developed,  as  it  is  felt  that  these 
details   come  under  the  jurisdiction  of  Conunittee  7 — Timber  Structures. 

Details  of  cap/sill  are  shown  as  information  in  the  accompanying  drawing. 
(See  page  356). 


356       Bulletin  656 — American  Railway  Engineering  Association 


AMERICAN    RAILWAY  ENGINEERING  ASSOCIATION 

PRESTRESSED   CONCRETE  CAP  AND/OR  SILL 
FOR  TIMBER  PILE  TRESTLE 


0"  TO  8"                                    "X"  SPACES  AT.  8"  EACH 

VARIES 

A         ''          (li         ''          ill         ''          iTi         ''          iT)         1'^ 

1   1                      1   1                      1   lYl^HOLE  1    [                      1   1 

PLAN  VIEW 


0"  TO  8"  4"  "X"  SPACES    AT  8"  EACH 


il>HOLE 


M 


> 


ELEVATION 


GENERAL  NOTES 

1.  CAP  TO  BE  MANUFACTURED  IN  ACCORDANCE 
WITH    A.R.E.A.  SPECIFICATION  8-17. 

2.  CONCRETE  =  6,000  RSI  AT  28  DAYS 

3.  CEMENT  =  A. S.T.M.   CI50  UNLESS  NOTED 

4.  AGGREGATES'  3/4"  MAX. 

5.  STRAND  =  A. S.T.M.   A4I6 

6.  REINFORCING  =  A. S.T.M.  A82 

7.  FINISH  =  AS  FORMED,  FREE  FROM  HONEYCOMBS 

OR  VOIDS 

8    ALL  HOLES  TO  BE  OPEN,  FULL  SIZE  AND 
TRUE.  CLOSED  OR  MISALIGNED  HOLES  MUST 
BE  REAMED  OUT  TO  FULL  SIZE  BEFORE 
LEAVING  PLANT. 

9.  TAPERED  CAP  WEIGHS  222  LBS.  PER  LIN.  FT. 
RECTANGULAR  CAP  I4i/2"x  15",  WEIGHS  226  LBS. 
PER  LIN.  FT. 

lO  IT  IS  INTENDED  THAT  THE  UNIT  WILL  BE  CAST 
IN  THE  UP-SIDE  DOWN  MANNER  SO  THAT  THE 
BEARING  SURFACE  FOR  THE  STRINGERS  WILL 
BE  SMOOTH  AND  FLAT.  THE  TAPER  SHOWN  IS 
FOR  EASE  OF  REMOVAL  FROM  FORMS.  THE 
UNIT  MAY  BE  CAST  IN  THE  RECTANGULAR 
SHAPE  WITHOUT  TAPER  AT  THE  OPTION  OF  THE 
MANUFACTURER. 

II.  FOR  DETAILS  OF  HARDWARE  AND  FASTENINGS 
REFER  TO  CHAPTER  7  OF  THE  MANUAL. 


.250  SPIRAL 
AT  31/2  IN.  PITCH 

I2-I/2IN,DIA, 
250X STRANDS 
AT  24,600  LBS 
EACH 


TYPICAL  SECTION 

TOLERANCES 
OVERALL    DIMENSIONS: 

LENGTH -2  IN. 

WIDTH +1/4  IN. 

DEPTH +1/8  IN. 

ALIGNMENT: 
VARIATION  FROM  STRAIGHT  LINE 

HORIZONTALLY + 1/4  IN. 

VERTICALLY ±'/eiN. 

HOLE  SPACING:   8  IN ±1/2  IN. 


THE  3/4"  CHAMFER  AT  THE  TOP  CORNERS 
SHALL  BE  SPECIFIED  AS  A  MAXIMUM. 


Concrete   Structures   and   Foundations 357 

Report   on   Assignment   5 

Pier  Protection    (Fender  Systems)    at  Spans  on 
Navigable  Streams 

T.    R.    Kealey    (chairman,    subcommittee),    W.    F.    Baker,    R.    J.    Brueske,    J.    W. 
De\'alle,  T.  L.  Fuller,  C.  W.  Harman,  W.  R.  Hv^L'^,  J.  R.  Iwinski,  E.  E. 

RUNDE,   J.    E.    SCROGGS,   J.    O.    WhITLOCK,   J-    R-   WiLLIAMS. 

This  is  die  first  year  of  this  subcommittee.  Work  is  in  progress  in  preparation 
of  design  factors  for  fender  systems,  exposure  conditions,  study  of  forces  exerted 
by  moving  \essels  and  t\-pes  of  fender  systems  presently  being  utiHzed. 


Report  of  Committee   15 — Steel  Structures 


L.  F.  Currier,  Chairman 
D.  S.  Bechly, 
Vice  Chairman 

D.  L.  NoRD 
W.  D.  Wood 
F.  P.  Drew 
C.  A.  Hughes 
J.  G.  Clark 

R.    I.    SiMKINS 

H.  A.  Balke 
J.     E.  Barrett 
Jan  Berger 

L.    N.    BiGELOW 

E.  S.    BiRKENWALD    (E) 


Edward  Bond 
T.   J.   Boyle 
J.  C.  Bridgefarmer 
C.  J-  Burroughs 
H.  L.  Chamberlain 
R.  W.  Christie 

H.    B.    CUNDIFF 

E.  J.  Daily 

A.  C.  Danks 

T.  W.  Davidson 

L.  D.  Davis 

E.   B.  Dobranetski 

J.    L.    DURKEE 

N.  E.  Ekrem 
T.  W.  Fisher 
"G.  F.  Fox 

G.  K.  GiLLAN 
C.    E.    GiLLEY 

J.  W.  Hartmann 
J.  M.  Hayes  (E) 
G.  E.  Henry 
L.  R.  HuRD 
R.  D.  Hutton 
m.  l.  koehler 
l.  r.  kubacki 
Andrew  Lally 
E.  M.  Laytham 
K.  H.  Lenzen 
A.  D.  M.  Lewis 
H.  B.  Lewis 
H.  M.  Mandel 
R.  C.  McMaster 


James  Michalos 

D.  V.  Messman  ( E ) 
G.  E.  Morris,  Jr. 
Fred  Moses 

r.  h.  moulton 
v.  v.   mudholkar 

W.    H.    MUNSE 

R.  D.  Nordstrom 
W.  H.  Pahl,  Jr. 

A.    L.   PlEPMEIER 
R.    G.    PlERRJES 

F.  a.  Reickert 
W.  W.  Sanders,  Jr. 

M.    SCHIFALACgUA 

A.  E.  Schmidt 

F.  D.  Sears 

G.  R.  Shay 
Hernan  Solarte 
A.  P.   SOUSA 

J.  E.  Stallmeyer 
Z.  L.  Szeliski 

E.  S.  Thoden 

W.  M.  Thatcher 

R.  N.  Wagnon 

C.  R.  Wahlen 

R.  H.  Wengenroth 

W.  Wilbur 

E.  N.  Wilson 

A.  J.   Wood 

J.  A.  Zeleznikar 

Committee 


(E)    Member  Emeritus. 

Those  whose   names   are   shown   in  boldface,  in  addition  to  the  chairman  and  vice  chairman, 
are   the    subcommittee   chairmen. 

To  the  American  Railway  Engineering  Association: 
Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 

Revisions    to    Specifications   for   Steel   Railway  Bridges   submitted   for   adoption 
were  published  in  Part  1  of  Bulletin  655,  November-December  1975. 

1.  Develop   Criteria  for  the   Design  of   Unloading  Pits,  Collaborating  with  Com- 
mittees 7  and  8. 

No  report. 

2.  Obtain   Data   From    Wliich   the   Frequency   of   Occurrence   of   Maximum   Stress 
in  Steel  Railway  Bridges  May  Be  Detennined  Under  Service  Loading. 

No  report. 

3.  Protection  of  Steel  Surfaces. 
No  report. 


359 


360       Bulletin  656 — American  Railway  Engineering  Association 

7.  Bibliography    and   Technical   Explanation    of   Various    Requirements    in    AREA 
Specifications  Relating  to  Iron  and  Steel  Structures. 

No  report. 

10.  Continuous   Welded   Rail   on  Bridges,   Collaborating  as  Necessary  or  Desirable 
\\'ith  Committee  4. 

Revisions   to    Specifications    submitted   for   adoption    were   published   in   Part    1 
of  Bulletin  655,  November-December  1975. 

The  Committee  on  Steel  Structures, 

L.  F.  Currier,  Chairman. 


Iron  and  Steel  structures  361 


3Rolanb  barker  Babisf 
1884=1974 

Roland  Parker  Davis,  Life  Member  of  the  American  Railway  Engineering 
Association  and  Member  Emeritus  of  Committee  15 — Steel  Structures,  died  on 
December  11,   1974,  at  his  home  in  Morgantovvn,  West  Virginia. 

He  became  a  Member  of  AREA  in  1914  and  a  Life  Member  in  1949.  He  had 
been  a  member  of  Committee  15  for  many  years  and  became  Member  Emeritus 
upon  his  retirement  from  West  Virginia  University  in  1955.  He  is  well  remembered 
for  his  wise  counsel  during  his  tenure  on  Committee  15.  He  contributed  much  to 
the   development   of  specifications   for  the   design  of  steel  bridges. 

He  was  bom  on  August  2,  1884,  at  Beverly,  Massachusetts,  the  son  of  Parker 
Stephen  and  Julia  Andrews  Davis.  Upon  completing  his  education  in  the  public 
schools  at  Be\erly,  he  entered  die  Massachusetts  Institute  of  Technology  from  which 
he  received  the  S.  B.  degree  in  1906.  After  working  as  a  draftsman  for  the  American 
Bridge  Company  for  one  year,  he  resumed  his  education,  entering  Cornell  University 
from  which  he  was  graduated  with  tiie  M.C.E.  degree  in  1908.  He  was  married 
to  Bessie   Belle  Strantzch  of  Springfield,  Missouri,  on  June  16,  1910. 

Dr.  Davis  continued  at  Cornell  University,  serving  as  an  instructor  in  engineering 
while  pursuing  studies  and  research  leading  to  his  doctorate,  which  was  awarded 
in  1914.  He  joined  the  faculty  of  West  Virginia  University  in  1911,  as  associate 
professor  in  the  Department  of  Civil  Engineering.  He  subsequently  served  as  pro- 
fessor and  head  of  structural  engineering,  associate  dean  of  the  college  of  engineering, 
and  in  1932  was  elevated  to  tlie  position  of  dean  of  the  College  of  Engineering 
which  he  held  until  his  retirement  in  1955. 

In  addition  to  his  teaching  appointments  at  West  Virginia  University,  he  also 
served  the  State  of  West  Virginia  as  bridge  engineer  beginning  in  1914.  He  was 
infiuential  in  organizing  the  State  Road  Commission  of  West  Virginia,  which  was 
formed  in  1919.  When  its  headquarters  were  moved  from  Morgantown  to  Charleston, 
he  continued  to  serve  as  a  consultant  to  the  Commission's  bridge  department. 

Although  his  services  were  largely  devoted  to  the  State  of  West  Virginia,  he 
served  as  a  consultant  in  connection  witii  the  design  and  construction  of  the 
Thatcher  Ferry  Bridge  over  the  Panama  Canal,  completed  in  1962. 

He  was  active  in  several  professional  and  technical  organizations.  He  served 
as  a  director  of  the  American  Society  of  Civil  Engineers  from  1937  to  1939.  He  was 
vice  president  of  ASCE  in  1940.  He  was  made  an  Honorary  Member  of  ASCE  in 
1968.  He  was  a  member  of  Tau  Beta  Pi  and  Sigma  Xi,  and  a  National  Honor  Member 
of  Chi  Epsilon.  He  had  been  a  member  of  the  Kiwanis  for  over  50  years. 

He  was  the  co-author  of  two  major  l)ooks,  both  written  in  coHaboration  with 
the  late  Professor  H.  S.  Jacoby  of  Cornell  University:  Foundations  of  Bridges  and 
Buildings,  1914  and  1925,  and  Timber  Design  and  Construction,  1929. 

He  is  survived  by  his  wife,  Bessie  Belle  Strantzch  Davis;  a  nephew  who  grew 
up  in  his  home,  J.  A.  W.  Davis;  a  brother,  Clifford  Davis  of  Massachusetts;  a  sister, 
Mrs.  Elsie  Davis  Upton  of  Beverly,  Massachusetts;  and  several  other  nieces  and 
nephews. 

E.     S.     BlRKENWALD 

J.   M.   Hayes 


Report  of  Committee   1 — Roadway  and  Ballast 


E.  L.  Robinson, 
Chairman 

N.  E.  Whitney, 
Vice  Chairman 

W.  J.  Sponseller, 
Secretary 

M.  B.  Hansen 

F.  L.  Peckover 
C.  E.  Webb 

J.    L.    ViCKERS 

W.  M.  Dowdy 
R.  L.  Williams 
J.  B.  Farris 
H.  C.  Archdeacon 


A.  G.  Altschaeffl 
R.  D.  Baldwin 

H.  E.  Bartlett 
C.  W.  Bean 
R.  H.  Beeder  (E) 
R.   J.   Bennett 

C.  R.  Bergman 
T.  R.  Blacklock 
R.  H.  Bogle,  Jr. 

E.    W.    BURKHARDT 

B.  E.  Butterbaugh 
R.  M.  Clementson 

D.  H.  Cook 
M.  W.  Cox 
G.  W.  Deblin 
H.  K.  Eggleston 
G.  E.  Ellis 

W.  P.  Eshbaugh  (E) 

E.  E.  Farris 
T.  J.  Faucett 
G.  C.  Fenton 
J.  S.  Fluke 

F.  B.  Grant 

J.  B.  Haegler,  Jr. 
R.  T.   Haggerstrom 
W.  T.  Hammond 
R.  D.  Hellweg 
T,  J.  Hernandez 
P.  R.  Houghton 
H.  O.  Ireland 

G.  Jess 

B.  J.  Johnson 


D.  N.  Johnston 
J.  A.  KUHN 

H.  W.  Legro  (E) 
W.  S.  Lovelace 

K.    J.    LUDWIG 

J.  K.  Lynch 

F.  H.  McGuigan 

H.  E.  McQueen 

B.    C.    MOHL 

W.  G.  Murphy 
J.  E.  Newby 

F.  P.  Nichols,  Jr. 

J.    M.    NUNN 

R.  V.  Perrone 
R.  H.  Peterson 
W.  B.  Peterson 
S.  R.  Pettit 
H.  E.  Richards 

G.  D.  Santolla 
P.  J.  Seidel 

W.  M.  Snow 

E.  H.  Steel 
W.  H.  Stumm 

F.  A.  Tijan,  Jr. 
R.  H.  Uhrich 

S.  S.  Vinton  (E) 
M.  E.  Vosseller 
J.  B.  Wackenhut 
A.  J.  Wegmann  (E) 

Committee 


(E)    Member  Emeritus. 

Those   whose   names   are  shown  in  boldface,   in   addition  to  the   chairman,   vice   chairman  and 
secretar>',    are   the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 

Your  committee  reports  on  the  following  subjects: 

1.  Roadbed. 

Publication  in  the  Manual  of  Section  1.4 — Maintenance,  was  recom- 
mended in  Part  1  of  the  November-December  1975  Bulletin.  This 
completes  revision  of  the  entire  Part  1 — Roadbed,  of  the  Manual. 

2.  Ballast. 

Progress  report  on  ballast  research  presented  as  information    page  364 

3.  Natural  Waterways. 

A  draft  of  a  proposed  revision  to  Part  3,  Section  34,  has  been  com- 
pleted and  will  be  ready  for  publication  in  the  November-December 
1976  Bulletin. 

4.  Culverts  and  Drainage  Pipe. 

A  study  is  vmderway  to  investigate  the  need  for  test  specifications  for 
aluminum  pipe  and  its  application  in  the  railroad  roadway. 


363 


364       Bulletin  656 — American  Railway  Engineering  Association 

5.  Pipelines. 

Consideration  is  being  given  to  provide  recommendations  for  use  of 
casing  pipe  larger  than  42-inch  diameter. 

6.  Fences. 
No  report. 

8.  Tunnels. 
No  report. 

9.  Vegetation  Control. 

A  Manual  addition,  Table  3 — Susceptibility  of  Woody  Species  has 
been  published  in  Part  1  of  the  November-December  1975  Bulletin. 
Part  9  of  the  Manual  requires  constant  review  due  to  environmental 
control  laws  concerning  the  use  of  some  chemicals.  This  is  a  con- 
tinuous task  for  your  committee. 

The   Committee   on   Roadway  and  Ballast, 

E.  L.  Robinson,  Chairman. 


Report  on  Assignment  2 

Ballast 

C.  E.  Webb  (chairman,  subcommittee),  R.  H.  Beeder,  R.  J.  Bennett,  E.  W.  Burk- 
HARDT,  H.  K.  Eggleston,  G.  E.  Ellis,  R.  D.  Hellweg,  J.  K.  Lynch,  F.  P. 
Nichols,   R.   H.  Peterson,  W.  B.  Peterson,  R.  H.  Uhrich. 

The  following  report  on  ballast  research  is  presented  as  information. 

BALLAST  AND  FOUNDATION  MATERIALS 
RESEARCH  PROGRAM 

The  Department  of  Civil  Engineering  of  the  University  of  Illinois  at  Urbana- 
Champaign  is  currently  conducting  a  broadbased  research  program  in  the  areas  of 
ballast  and  subgrade  materials,  via  a  contract  with  tlie  Association  of  American 
Railroads.  This  AAR-U  of  I  contract  is  part  of  a  larger  project  sponsored  by  the 
U.S.    Department    of   Transportation,    Federal    Railroad   Administration. 

A  review  committee  consisting  of  W.  S.  Autrey,  chief  engineer  System,  Atchison, 
Topeka  &  Santa  Fe,  R.  M.  Browai,  chief  engineer.  Union  Pacific,  C.  E.  Webb,  assistant 
vice  president,  Southern  Railway,  and  F.  L.  Peckover,  engineer  of  geotechnical 
services,   Canadian  National,  was  established  for  this  program. 

The  general  extent  of  the  research  is  to  conduct  an  investigation  of  die  physical 
properties,  behavioral  characteristics,  and  associated  economics  of  commonly  em- 
ployed railroad  ballast  and  foundation   (subgrade)   materials. 

The  nature  of  the  six  phases  of  activity  of  tlie  project  as  well  as  their  status 
are  as  follows. 

Phase  I:  Technical  Data  Bases 

The  relevant  literature  pertaining  to  the  pertinent  properties  of  granular 
materials  and  fine-grained  soils,  ballast  materials,  and  analytical  structural  models. 


Roadway   and   Ballast 365 


has    reen   reviewed.    A   report   entitled,    "Technical    Data   Bases   Report,"   has   been 
completed. 

Phase  II:    Development  of  a  Structural  Model  and  Materials 
Evaluation  Procedures 

A  "mechanistic  structural  analysis  model"  has  been  developed  and  testing 
procedures  established  for  evaluating  the  properties  of  tlie  ballast  and  foundation 
materials  needed  as  inputs  to  the  structural  model.  The  finite  element  structural 
analysis  model  considers  the  stress-dependent  behavior  of  the  ballast  and  founda- 
tion materials.  The  structural  model  output  includes  stresses  and  displacements  in 
tlie  ballast  and  foundation  materials,  tie  plate  reactions,  rail  moments  and  deflec- 
tions, and  tie  moments  and  deflection.  A  report  entitled,  "Development  of  a 
Structural  Model  and  Materials  Evaluation  Procedures,"  has  been  completed. 

Pil\se  III:    Parameter  Studies  and  Sensitivity  Analyses 

The  structural  model  was  utilized  to  establish  tlie  eftects  of  major  design 
parameters  on  the  response  of  the  track  support  system.  The  parameters  considered 
included:  1)  subgrade  soil  resilience  properties,  2)  ballast  and  sub-ballast  material 
resihence  properties,  3)  ballast  and  sub-ballast  diicknesses,  4)  ballast-tie  parameters, 
and  5)  rail-tie  parameters.  A  summary  report  for  Phase  III  is  being  prepared  for 
submission  to  AAR. 

Phase  IV:  Materials  Evaluation  Study 

A  series  of  laboratory  tests  are  being  conducted  with  selected  foundation  soils 
and  ballast  and  sub-ballast  materials  to  determine  their  pertinent  engineering 
properties.  The  ballast,  sub-ballast,  and  foundation  materials  selected  for  inclusion 
in  the  laboratory  study  represent  a  range  in  both  engineering  properties  and  t\'pes 
and  sources  of  materials.  In  addition  to  the  standard  AREA  specification  tests, 
repeated-load  triaxial  tests  (elastic  and  permanent  deformation  measurements), 
particle  index  tests,  crushing  value  tests,  lateral  restraint  capability  tests,  and  ballast 
degradation  tests  (1  X  10"  load  repetitions)  are  being  conducted.  Phase  I\'  activities 
have  not  yet  been  completed. 

Phase  V:  Economic  Evaluation 

Costs  associated  with  the  use  of  various  types  of  ballast  material  w  ill  be  identi- 
fied and  the  cost  eftectiveness  of  the  ballast  materials  ranked  both  as  to  transportation 
costs  and  stabilitv'.  Phase  V  has  not  >et  been  completed. 

Phase  M:   Prepar.\tion  of  Conclusions,  Summary  and  Recommendations 

Data  and  information  obtained  from  the  technical  literature  and  that  developed 
in  the  project  will  be  summarized  and  analyzed.  Appropriate  conclusions  and  rec- 
ommendations will  be  developed  and  areas  of  technological  need  will  be  identified. 

The  principal  project  investigators  are  Dr.  Q.  L.  Robnett,  Dr.  M.  R.  Thompson, 
and  Dr.  W.  W.  Hay  of  tlie  University  of  IlHnois.  The  principal  investigator  on  the 
entire  contract  is  Dr.  Gregory  C.  Martin  from  the  Association  of  American  Raiboads. 

The  availabilit>  of  completed  reports  can  be  obtained  by  writing  to  the  Asso- 
ciation of  American  Raflroads  Technical  Center,  3140  S.  Federal  St.,  Chicago,  IL 
60616. 


Report  of  Committee  3 — Ties  and  Wood  Preservation 


C.  p.  Bird,  Chairman 

E.  M.    ClMMINGS, 

Vice  Chairman 
J.  E.  HiNSON,  Secretary 

F.  J.  Fudge 


J.  T,  Skerczak 
R.  J.  Shelton' 

L.    C.    COLLISTER 

K.  C.  Edscorn 
G.  H.  Way 

J.  \V.  A.  Acer 

H.  C.  Archdeacon 

W.  F.  .Arksey 

A.  B.  Baker 
S.  L.  Barkley 
W.  W.  Barnette 
R.  S.  Belcher  (E) 
G.  W.  Brenton 

C.  A.  Burdell 

C.  S.  Burt  (E) 

D.  Carter 
M.  J.  Crespo 
D.  L.  Davies 

R.  F.  Dreitzler 
I.  A.  Eatox 
D.  E.  Embling 
W.  E.  FUHR 

B.  J.  Gordon 


J.  K.  Gloster 
D.  C.  Gould 
R.  D.  Hellweg 
R.  P.  Hughes  (E) 

G.    P.    HUHLEIN 

R.  G.  Huston 
R.  E.  Kleist 
L.  W.  Kistler  (E) 
M.  A.  Lane 

D.  B.  Mabry 
G.  H.  Xash 

T.    J.    O'DONNELL 

R.  B.  Radkey 

H.  E.  Richardson 

R.  H.  Savage 

K.  W.  Schoeneberg 

G.  D.  Summers 

R.  C.  Weller 

F.  M.  Whitmore 

J.  L.  Williams 

E.  L.  Woods 
R.  G.  Zeitlow 

Committee 


(E)    Member  Emeritus. 

Those    whose    names    are    shown    in    boldface,    in    addition    to    the    chairman,    vice    chairman 
and    secretary',    are    the    subcommittee    chairmen. 

To  the  American  Raihvatj  Engineering  Association: 

Your  committee   reports  on  the  following  subjects: 

B.  Revision  of  Manual. 

Revision  of  Manual  Parts  1  to  9  \\as  completed  in  1973,  submitted  for 
re\ae\v  and  approxal  to  tlie  Board  Committee  on  Publications  and  the 
AREA  Board  of  Direction  and  has  now  been  approved  for  publication. 
Further  revisions  to  Part  10,  Specification  for  Concrete  Ties  (and 
Fastenings),  have  been  proposed  and  the  revised  specification  was 
published  in  Part  1  of  the  November-December  1975  Bulletin,  for 
reconsideration. 

2.  Cross  and  Switch  Ties. 

Report  on  1975  treating  plant  inspection    page  368 

3.  Wood  Presenatixes. 

Brief  progress  report  on  investigation  of  3  APR6  preservative  is  pre- 
sented   as    information    P^ige  368 

4.  Preser\ative  Treatment  of  Forest  Products. 
No  report. 

5.  Service  Records  of  Forest  Products. 

(a)   Aimual  Tie  Renewal  Statistics  as  Compiled  by  the  Economics  and 
Finance  Department,  AAR. 

These  statistics  were  published  as  an  advance  report  in  Bulletin 
654,  September-October  1975. 


367 


368       Bulletin  656 — American  Railway  Engineering  Association 

(b)   Investigate  Suitability  of  Imported  Cross  Ties. 

A  brief  progress  report  is  presented  as  information page  369 

6.  Collaborate  with  AAR  Research  Departinent  and  Otlier  Organizations 
in  Research  and  Other  Matters  of  Mutual  Interest. 
No  report. 

The  Committee  on  Ties  and  Wood  Preservation, 

C.  P.  Bird,  Chairman. 


Reporf  on  Assignment  2 

Cross  and  Switch  Ties 

J.  T.  Skerczak  (chairman,  subcommittee),  H.  C.  Archdeacon,  W.  W.  Barnette, 
C.  P.  Bird,  C.  A.  Burdell,  M.  J.  Crespo,  E.  M.  Cumnungs,  F.  J.  Fudge, 
J.  K.  Gloster,  J.  E.  HiNsoN,  M.  A.  Lane,  G.  H.  Nash,  H.  A.  Richardson, 
R.  H.  Savage,  K.  W.  Schoeneberg,  R.  C.  Weller,  R.  G.  Zietlow. 

Extent    of    Adherence    to    Specifications    for    Cross    and    Switch 
Ties  as  Observed  on  Field  Inspection 

On  May  21st,  1975,  12  members  of  Committee  3  inspected  cross  and  switch 
ties  at  a  treating  plant  in  Muncy,  Pa.  The  plant  was  found  to  be  neat  and  clean 
with  very  good  drainage  and  generally  excellent  housekeeping.  Ties  were  stacked 
9x2  for  the  Reading  Company  and  9x1  for  the  Penn  Central  to  a  height  of  17 
rows. 

Ties  in  storage  were  predominantly  mixed  oak  with  lesser  amounts  of  mixed 
hardwoods.  Ties  were  inspected  visually  at  unloader-separator-trimmer.  Quality  was 
generally  good,  selective  dowelling  being  used  for  anti-splitting  control.  Tie  sizes 
were  in  accordance  with  AREA  specifications. 

The  plant  treats  approximately  1,200,000  ties  annually  with  60/40  and  80/20 
creosote-coal  tar  solutions,  to  net  retentions  of  6  and  7  lb  per  cu  ft,  using  vapor 
drying  and  Rueping  metliods,  adhering  to  AREA  specifications. 

Report  on   Assignment  3 

Wood  Preservatives 

R.  J.  Shelton  (chairman,  suhcommittee),  C.  P.  Bird,  C.  A.  Burdell,  L.  C. 
CoLLiSTER,  D.  L.  Davies,  F.  J.  FuDGE,  J.  E.  HiNSON,  G.  H.  Way. 

Your  committee  submits  the  following  progress  report  as  information,  pertaining 
to  the  evaluation  of  "3APR6"  as  a  wood  preservative. 

In  1974,  Subcommittee  3  was  approached  by  an  eastern  manufacturer  of  wood 
preservatives  to  evaluate  for  approval  its  preservative,  "3APR6." 

The  preservative  and  process  were  described  as  a  water-soluble  monomer  intro- 
duced into  the  wood  cells  in  a  closed  cylinder  by  first  applying  a  high  vacuum  for 
one-half  hour  followed  by  introduction  of  the  liquid  monomer  into  the  cylinder  under 


Ties  and  Wood  Preservation 369 

pressure  for  one-half  hour  to  help  increase  penetration.  Polymerization  of  the 
monomer  then  takes  place  in  tlie  wood. 

Upon  visiting  the  plant,  the  subcommittee  decided  that  the  preservative  may 
have  some  merit  and  should  be  evaluated.  It  was  verified  tliat  21  ties  which  had 
been  treated  with  "3APR6"  had  been  in  service  at  Easton,  Pennsylvania  for  over 
seven  years.  A  visit  to  this  site  was  scheduled  for  the  joint  field  trip  of  the  AREA 
Committee  and  RTA  Research  Group  for  May  22,  1975.  Three  of  the  21  ties  were 
marked  for  removal  for  furdier  testing.  One-half  of  each  of  these  ties  was  shipped 
to  the  Forest  Utilization  Lab  at  Mississippi  State  University  for  soil  block  and 
strength  tests.  These  ties  have  been  removed  and  tlie  tests  at  Mississippi  State 
University  are  now  under  way. 

The  manufacturer  is  also  having  several  independent  laboratories  evaluate 
its  "3APR6."  Plate  wear  tests  will  be  run,  but  plans  for  this  test  have  not  been 
finalized. 

At  present,  the  subcommittee  is  not  trying  to  draw  any  conclusions  as  to  the 
merit  of  the  product,  but  is  collecting  as  much  data  from  as  many  different  sources 
as  possible.  After  these  data  are  collected,  it  will  be  reviewed  by  Subcommittee  3, 
at  which  time  we  will  make  recommendations  to  Committee  3  as  to  the  acceptance 
of  "3APR6"  as  a  preservative  for  ties  and  wood  products. 

Report  on  Assignment  5 

Service  Records  of  Forest  Products 

K.   C.   Edscorn  (chairman,  subcomtnittee),  L.  C.  Collister,  M.  J.  Crespo,  E.  M. 
CuMMiNGs,  J.  K.  Closter,  H.  E.  Richardson,  R.  H.  Savage,  G.  D.  Summers. 

Your  committee  submits  the  following  report,  as  information,  on  the  beginning 
of  its  investigation  to  determine  the  suitability  of  various  woods  which  have  been 
imported  into  the  United  States  for  use  as  cross  ties. 

In  order  that  it  might  be  determined  which  railroads  have  foreign  species  of 
wood  in  use  as  cross  ties,  a  letter  was  sent  to  the  17  largest  Class  I  roads  asking 
them  to  list  the  number  and  species  in  track  as  well  as  date  of  installation,  location, 
type  of  preservative  treatment  and  class  of  track.  Replies  were  received  from  10 
railroads  only  4  of  which  indicated  they  have  installations  of  foreign  woods.  These 
are  shown  in  the   accompanying  table.    (See  pages   370-371). 

We  will  continue  to  gather  infomiation  about  the  service  and  durability  of 
the  cmTent  installations  so  that  progress  on  this  assignment  can  be  reported  in 
subsequent  Bulletins.  It  is  obvious  that  several  years  of  service  will  be  required 
before  a  sound  evaluation  can  be  made. 


370       Bulletin  656 — American  Railway  Engineering  Association 


1^' 


.3 


I 


Q 
O 
O 

§ 

in 
O 


en 
O 

g 


S  -S 

? 

11 
o  S 

o 

•-J^ 

£j  *J 

^^ 

t3 

<»-^ 

4J   lO 

«'« 

ai> 

Q  ^ 

C/3   r-4 

t-H 

^ll 

o 

i-H 

5S  s 

l^:^ 

w 

CS 

9 

K     U 

■TJ 

S     » 

n 

i:f^'« 

O 

J^.S 

K 

« 


o 

jj  'id  c^  "id  °o 

g  Ph  CO    Cm  CO 


H 
<!  ^ 


■^  CO      -w 


in 

CO 
>H   QO 

Z  f>i 


."•^    J2  "5    T3    Hi 


c3  O) 


PM 


j)^  WW  otZ 


in 


fe     S5 


in 


Cs| 

o 

I— 1 

Oi 

Th 

o 

CO 

o 

CO 

a> 

Tf< 

CO 

o 

u 
< 

«<: 

DO 
O  P5 

C/3  i-J 


3 


pq 


I 


^  c«  ^ 

a  a^ 

0<  bO 

w  tn  Vh 

O  OS  0) 

^  ^  =§ 

<i  <i  Q 


J    ^3    ,5 
O      cS 

>>    &   Is 

.<     CA     K^ 


Shu 


Ph 


p^ 


Ties  and  Wood  Preservation 


371 


inioioiomioiDioioio^cioinioic 


o  g 

8 


00 


3 

fl 

►5* 

s 

> 

"1 

^ 

>'^ 

^H 

^U 

oo 

00  (J 


U5 


afe 


c-i  23  S  l^  ^  f^i 

"-"     1— I     05     r-H     CO     CO 


8 


m 


n 


Kin 


<o  o 


«  w 

on  1-4 


PL, 


'yi     o 


o 

a    (D 

-^  i 


D4 


(Tl 

tfl 

n 

,^ 

(li 

^ 

ci 

3 

*3 

be 

rt     (U  '-H    "—2    .^ 


P     rt     o 


a 

I 


■^ 

8 

p 

U 

^ 

a 

2 

■c 

■a 

p 

S 

ffi 

J?u 


Report  of  Committee  4 — Rail 


R.  M.  Brown,  Chairman 

H.    F.    LONGHELT, 

Vice  Chairman 
A.  B.  Merritt,  Jr., 

Secretary 
R.  F.  Bush 

R.    C.    POSTELS 

W.  J.  Cruse 
E.  T.  Franzen 
G.  H.  Maxwell 
R.  E.  GoRsucH 
E.  H.  Waring 
D,  H.  Stone 

L.    A.   LOGSDON 


V.  R.  Terrill 

J.  I.  Adams 

B.  C  Anderson 

S.  H.  Barlow 

D.  A.   Bell 

R.  E.  Catlett,  Jr. 

L.  S.  Crane 

P.  K.  Cruckshank 

Daniel  Danyluk 

A.  R.  DeRosa 
Emil  Eskengren 
R.  C.  Faulkner 
M.  A.  Ferguson 

B.  R.  Forcier 
W.  H.  Freeman 
A.  H.  Galbraith 
R.  G.  Garland 
G.  H.  Geiger 
W.  J.  Gilbert 

R.  L.  Gray 
J.  H.  Greason,  Jr. 
R.  E.  Haacke 
V.  E.  Hall 

C.  C.  Herrick 
W.  H.  Huffman 
T.  B.  Hutcheson 
A.  V.  Johnston 
K.  H.   Kannowski 
R.  R.  Lawton 
W.  S.  Lovelace 
J.  F.  Lyle 

T.  C.  Mackenzie 


Ray  McBrian  (E) 

T.  L.  Merritt 

"B.  R.  Meyers  (E) 

F.  W.  Michael 

C.  E.  Morgan  (E) 

G.  L.    MUHDOCK 

B.  J.  Murphy 

B.  F.  Overbey 

C.  F.  Parvin 
C.  O.  Penney 

G.  L.  P.  Plow  (E) 

T.  M.  Rankin 

"M.   S.   Reid 

I.  A.   Reiner 

R.  B.  Rhode 

H.  L.  Rose 

C.  N.  Scott 

A.  E.  Shaw,  Jr. 
L.  H.  Shisler 
W.  A.  Smith 

B.  D.  Sorrels 

C.  L.  Stanford 
R.  K.  Steele 
Erich  Thomsen 
G.  S.  Triebel 
M.  S.  Wakely 
G.  H.  Way 

C.  E.  Weller 

S.   T.   WiECEK 

H.  M.  Williamson 

M.   J.   WiSNOWSKI 

Committee 


(E)    Member  Emeritus. 

Those  whose  names   are  shown  in  boldface,   in  addition  to  the  chairman,  vice  chairman,   and 
secretan.',    are   the   subcommittee   chairmen. 

To   the  American   Railway  Engineering  Association: 

Your  committee   reports  on  the  following  subjects; 

B.  Revision  of  Manual. 
No  report. 

1.  Collaborate  witli  AISI  Technical  Subcommittee,  Welding  Contrac- 
tors, Suppliers  of  Field  Wielding,  Rail  Grinding  and  Rail  Testing 
Conhactors  on  Matters  of  Mutual  Interest. 

No  report. 

2.  Collaborate  with  AISI  Technical  Committee  on  Rail  and  Joint  Bars  in 
Research  and  Otlier  Matters  of  Mutual  Interest. 

(a)  Study  the  subject  of  obtaining  rails  longer  tlian  39  ft.,  looking 
to  developing  die  optimum  length  of  rail  that  will  be  acceptable, 
based  on  handling  metliods,  supply  of  cars  for  shipping,  the 
number  of  rails  which  can  be  obtained  from  steel  company  ingot 
molds,    and    other    necessary   considerations. 

No  report. 


373 


374       Bulletin  656 — American  Railway  Engineering  Association 

3.  Rail  Failure  Statistics. 

Brief  status  statement,  included  in  Commentary. 

4.  Up-date  Data  on  Methods  and  Equipment  for  Making  Welding  Repairs 
to  Rail  and  Turnouts. 

No  report. 

5.  Rail  Research  and  Development. 

Progress  report,  submitted  as  information page  376 

6.  Joint  bars:    Design,  Specifications,  Service  Tests,  Including  Insulated 
Joints  and  Compromise  Joints. 

No  report. 

7.  Laying  of  Continuous  Welded  Rail. 

Statistics  showing  track  miles  of  CWR  laid  by  years  since  1933,  sub- 
mitted as  information    page  376 

8.  Maintenance  of  Continuous  Welded  Rail. 

Brief  status  statement,  included  in  Commentary. 

9.  Standardization  of  Rail  Sections. 

Progress  report,  submitted  as  information page  382 

10.  Effect  of  Heavy  Wheel  Loads  on  Rail. 
No  report. 

11.  Field  Welding. 
No  report. 

12.  CWR  Field  Handbook. 

Brief  status  statement,  included  in  Commentary. 


COMMENTARY 

On  September  27,  1975,  recommendation  was  submitted  by  Chairman  Brown 
of  Committee  4  to  the  Board  of  Direction  for  approval  to  consolidate  Assignment  3, 
"Rail  Failure  Statistics,"  and  Assignment  9,  "Standardization  of  Rail  Sections,"  into 
one  revised  Assignment  3,  "Rail  Statistics." 

In  the  past,  reports  on  both  Assigmnents  3  and  9  of  Committee  4  have  been 
confined  to  rail  statistics.  Assignment  3  covering  a  compilation  of  data  on  rail  failures 
illustrated  by  numerous  statistics  and  graphs,  and  Assignment  9,  a  brief  statistical 
summary  of  the  annual  tonnage  rolled  and  shipped  from  Canadian  and  United  States 
rail  mills  in  each  individual  rail  section. 

In  connection  with  Assignment  3,  the  last  report  of  rail  failure  statistics  was 
made  in  Bulletin  641  of  January-February  1973.  These  statistics  were  discontinued 
in  1973  as  it  was  recognized  that  the  statistics  being  assembled  had  little  or  no  value 
as  efforts  were  being  made  to  compile  these  numbers  from  all  railroads  in  the  country 
and  the  majority  of  the  roads  that  were  attempting  to  report  did  not  maintain  the 
records  that  were  necessary  to  furnish  Committee  4  with  reliable  statistics;  conse- 
quently, the  statistics  tliat  were  published  weren't  realistic. 

Since  that  time,  however,  the  FRA  and  Congress  have  become  deeply  involved 
in  the  problem  of  upgrading  railroads  throughout  the  country  and  in  so  doing  have 


Rai_l 375 

been  attempting  to  develop  numbers  from  any  source  to  support  the  effort.  The 
condition  of  raU  in  tracks  of  the  American  Railroads  is,  of  course,  one  of  the  primary 
problems  within  the  industry  and  one  of  the  largest  items  of  expense  required  to 
upgrade  the  properties  that  are  in  trouble.  Consequently,  the  FRA  has  been  attempt- 
ing to  assemble  data  for  its  own  use  and  for  presentation  before  congressional 
committees  on  these  rail  conditions,  and  both  FRA  and  congressional  conuuittees 
have  been  critical  of  the  fact  that  the  AREA,  representing  the  engineering  arm  of 
the  industry,  doesn't  have  any  statistics  such  as  those  we  attempted  to  assemble  on 
rail  failures  to  further  their  study  of  our  problems. 

When  this  matter  was  brought  up  at  the  last  Rail  Committee  meeting  in  Chicago 
on  June  16-17,  1975,  it  was  discussed  thoroughly  and  it  was  the  consensus  of  all 
present  that  we  should  attempt  to  assemble  such  statistics  to  the  extent  that  they 
are  available  from  major  roads  which  do  maintain  reliable  records  on  rail  defects. 
Consequently,  it  was  concluded  that  we  would  again  attempt  to  assemble  such 
statistics  only  from  those  roads  who  can  furnish  reliable  numbers  and  at  least  have 
these  available  for  future  reference  within  the  industry  and  a\ailable  to  Government 
agencies  for  their  use  as  required. 

As  stated  above,  both  of  these  assignments  are  primarily  confined  to  rail  sta- 
tistics which  are  very  beneficial  and  worthwhile;  however,  compilation  of  rail 
statistical  data  does  not  require  or  justify  the  assignment  of  two  separate  subcom- 
mittees presently  represented  by  27  different  members  of  Committee  4  and  it  was 
therefore  recommended  assignments  3  and  9  be  consoHdated  into  one  revised  Assign- 
ment 3,  "Rail  Statistics."  This  recommendation  was  appro\'ed  by  the  Board  of 
Direction  at  its  meeting  November  13,  1975. 

It  also  has  been  apparent  Committee  4  has  an  area  of  conflict  with  Committee 
5 — Track,  as  Chapter  5-5-4,  "Laying  Continuous  Welded  Rail  (CWR),"  and 
Chapter  5-5-4.1,  "Maintenance  of  Continuous  Welded  Rail,"  are  also  the  same 
subjects  of  Committee  4 — Rail,  Assignments  7  and  8,  respectively. 

In  view  of  this  conflict,  Committee  4  presented  tliis  matter  to  the  Board  of 
Direction  and  on  November  13,  1975,  the  Board  transferred  Assignments  7  (Laying 
of  Continuous  Welded  Rail),  8  (Maintenance  of  Continuous  Welded  Rail)  and  12 
(CWR   Field    Handbook)    from   Committee   4 — Rail   to   Committee   5 — Track. 

The  Committee  on  Rail, 

R.  M.  Brown,  Chairman. 


376       Bulletin  656 — American  Railway  Engineering  Association 

Report  on  Assignment  5 
Rail   Research  and   Development 

W.  J.  Cruse  (chairman,  subcommittee),  B.  C.  Anderson,  R.  M.  Brown,  Daniel 
Danyluk,  a.  R.  DeRosa,  G.  H.  Geiger,  R.  E.  Gorsuch,  R.  E.  Haacke,  W.  H. 
Huffman,  T.  B.  Hutcheson,  H.  F.  Longhelt,  W.  S.  Lovelace,  T.  C. 
Mackenzie,  A.  B.  Merritt,  Jr.,  J.  L.  Merritt,  C.  O.  Penney,  J.  M.  Rankin, 
W.   A.    Smith,   R.   K.   Steele,   D.   H.   Stone,  G.   H.   Way,  M.  J.   Wisnowski. 

Advance  progress  report  was  published  in  Bulletin  654,  September-October 
1975. 

Field  inspections  were  carried  out  as  a  cooperative  effort  of  die  Rail  Research 
and  Development  Subcommittee  of  AREA  Gommittee  4 — Rail,  the  AISI  Technical 
Subcommittee  on  Rail  and  Accessories  and  the  AAR  Research  and  Test  Department. 

On  July  30,  1975,  an  inspection  was  made  of  a  service  test  installation  of  fully 
heat-treated,  induction  head-hardened,  intermediate  manganese  and  standard  control- 
cooled  rail  on  the  Ghessie  System  in  the  vicinity  of  Oakland,  Maryland.  On  August 
19,  20  and  21  inspections  of  service  test  installation  of  fully  heat-treated,  induction 
head-hardened,  high  silicon  and  standard  control-cooled  rail  on  the  Burlington 
Northern  in  Montana  and  Washington  were  made.  The  report  of  their  findings  will 
be  made  available  in  1976. 

As  information,  the  Ad  Hoc  Committee  on  Rail  Research,  made  up  of  representa- 
tives of  AREA,  AAR  and  AISI,  have  contacted  a  number  of  railroads  throughout 
this  country  and  Canada  and,  with  their  cooperation,  established  a  number  of  new 
rail  test  sites  for  gathering  rail  defect  statistics.  This  effort  is  part  of  the  ongoing 
cooperative  research  work  having  to  do  with  the  study  of  rail  defects  and  the 
metallurgy  of  rail  steels. 

Report  on  Assignment  7 

Laying  of  Continuous  Welded  Rail 

G.  H.  Maxwell  (chairman,  subcommittee),  R.  M.  Brown,  Daniel  Danylxik, 
A.  R.  DeRosa,  Emil  Eskengren,  A.  H.  Galbraith,  R.  G.  Garland,  W.  J. 
Gilbert,  R.  L.  Gray,  R.  E.  Haacke,  L.  A.  Logsdon,  H.  F.  Longhelt,  A.  B. 
Merritt,  Jr.,  B.  J.  Murphy,  R.  C.  Postels,  R.  B.  Rhode,  H.  L.  Rose, 
A.  E.  Shaw,  Jr.,  B.   D.  Sorrels,  E.  H.  Waring,  C.  E.  Weller. 

Your  committee  submits  as  information  the  following  statistics  showing  tlie 
number  of  track  miles  of  CWR  laid  by  years  for  the  period  1933  to  1974,  inclusive. 


Rail 


377 


s   ^ 


>2  *- 


2  cfl-^ 


St^ 


SB- 


CO  CO  O  Ol  o  c 

CO  O  lO  -f  OC  C5 

o>  CO  ■*  30  oi  -^ 

O  CO  Tt"  ^-1  01 


Ol 


CO 


Tj<  CO  00 
l>  CD  00 

O  CO 


in  t^  3  2; 


o 
d  I  ci 

lO  I  C5 
fM    CI 


lO 

00 

CO 

rM  1 

1    1  '^^ 

§(>. 

00 

Ol 

1  If2 

CO 

05 

00 

§     1       1 

1     1   '=> 
1     1  ^ 

■H- 

00 

O 

1     1 

1 

1 

1      I 

1    1    1 

1  1 

1 

1 

1        1 

1 

00 

Mil' 

1       ■     1 

1     1 

1 

1 

1      1 

' 

oi 

'      ' 

' 

1    1    1 

1  1 

1 

1 

1        1 

1 

1    1    1    1 

CD 

1             1 

oc 

~~  o 

CO 

Tf 

CD 

00 

1     1 

1 

1 

I      I 

1 

^ 

1      1 

1 

I  <^    1 

■^  oi 

r-^ 

I 

1    ^ 

1 

1       I       1    ^     1 

1      1    '~* 

1     1 

1      1 

1 

r- 

1      1 

1 

1          1 

-1  in 

1 

1 

1 

1       1       1    '^      1 

1     1  t^ 

^ 

CO 

1 

c 

g 

—  SS  m 

2 

c 

U4 

fa 

o 

1—1 

stern 

St.  Par 
&  Pac 
&  So. 

n  Co. 

5 

C     p 

u 

Aroostook 
Co.  of  Chica 
&  Lake  Erie 

.£  5 

> 

z 

o 
OS 

iystem 
ke  Western 
&  Illinois  Mi 
&  Western  1 
&  North  We 
Milwaukee, 
Rock  Island 
South  Shore 
Union  Static 

ti  Union  Ten 
West  Pullm; 
Id 

u« 

rt 

Q 

£ 

=3  =3 

-g 

=3  £ 

CA) 

D    O 

o 

o  o"  o"  o  o 

rt    -r   *^ 

c4 

= 

.? 

rf 

•;::: 

1 1 

c 

c  S' 

u 

_0 
'7. 

M   M   bC  bp  M 

L)    o    o  ,o  _o 

<<<<<<<-<-<-<<mmmmm 

uuuuuuuuouuuu 

378       Bulletin  656 — American  Railway  Engineering  Association 


U 


^S 


CO 
"8  ^'^ 


2 
I'd 


5J^ 


;§^ 


q  q 

CO  CO 

CD  05 


IC  o  o 

CO  O  CI 

05 

1-1  00  lO  W5 
Tt<  00  05  ■^ 

00   -H 

00  00  t^    1 
oi  CO         1 
CO  oi 

1  '^  1 
1  Tf<   1 

1    O  O  O  05 

1              r^^O^ 

i-H 

1    lO  CO 

00  IC 

O  Gi 


So 

00 

CO 

TJH 

CO 

05  in  o-i 

O 

CO  CO  O 

O  O  1> 

o  o 
t-  o 

1^ 

IS  i 

1  05  o  t-    1 

1    O     1 

1  o    1 

T— 1 

I  1    05  05  CO 

II  CO  tM 

O  "Xi 


-o 


-^  2  S 

C/:3  HH    HH 

o  ca  =a 

qj  O    ^ 


=  W    fi    g    a;    s 


=« 

=3 

rt 

^-^ 

tn 

u 

o 

2 

=3 

'n 

oaH 

:^ 

•Sh 

05 

^ 

0 

S 

o  'o 

■5 

w 

O 

c 

ii  ti 

^ 

+-* 

O 

(Li 

(D 

OJ 

0)    (D 

3 

M 

UQQQQQQw 

=a 


»8   § 

W  W  fe  ta 


br 

>-< 

M 

<-M 

O 

03 

o 

1 

c 

1 

"1 

03 

c 

3 

H 

so 

1 

=3 
03 

m 

n 

c 
U 

c 

rt 

c 

11 

O 

-O 

3 

o 

c 

<1; 

•""] 

OOOOUffiffi 

>-H 

3    ^ 
1^    J2 


^  C/3  <1 


^    .JIh      CA    '^ 


.5  w) 

s.s 

(U    3 

C    o3  -C  O 

•3    C  HH  -S 

S  =«  y 

'"'  o  a> 
to   o  CO  ^  "— '   rj 


0)  ■Sf'  bC 


^  W  vJ 


03  3 

CO  -w      _  .  . 

3  3  -ii  _3    3    -. 

oj  0)    03  U    O    O 


Rail 


379 


Sf- 


(-> 

Ol 

s-^: 

,— 1 

"** 

a;>K 

■"^ 

^ 

^^ 

* 

■w 

Tf 

u 

Vi 

s   . 

on 

■Si; 

CO 

00  -^ 

CI 


CO  o 

Ol  O 

o 

o 

o 

CO 

o 

CO 

C  lO   -H 

-<r  c  C5 

s 

00 

IS  1 

CO 

IS  1 

1  °o 

I  ¥>  t~-  (^i 

CO  ^  o 

lO  00 


^  q 

O    T}< 

c 

c 
o 

•X3 


3 

c 

be  >^ 

C    « 

-^ 


z 

rt 

v: 

=« 

i: 

£; 

(1> 

Qj 

.4_» 

u 

o 

> 

c 

'^ 

o 

-:; 

rt 

SS 

r.   '^    y 


Ucc 


-^-^     :^-i^ 


« 

c/l 

Q 

O 

=a 

c^ 

(U 

c 

^ 

r^ 

0^ 

c 

Q 

■:;^ 

-:<! 

O 

^ 

^ 

5 

m 

c 

CO 

CO  CO          O 
00  t-  O          00 

i  1 

1?  1  1 

1   l^??S  l§ 

Ol  00 

00  05  in 
d  r>i  lo 

00  lO  CO 


O  .s^-r:  •::    M   M 


?;  .:£  c  o  c  c  := 

;:^    x    w]    vj    ;:;    C    C 

.s  .i2  .;£  .i3   c  c   c 


C  -r-.  '^  ■=  == 


=^  U.   =<5 

.    C 


s 
W 

c       ^ 
•2      ^ 

O    f^    aj  -r 

■^  ph  ;s  - 


(U  ^   j_, 


ii  ^  s  <  '5 


CC        -e   o 


o 


C  CD  „ 


^    O    6  ?    S 

<J    b    s  >■    IJ 

2-5  >Q 


fe  « 


^j:^  =;< 


^.^  a 


OJ      r-'    be 


Z2 


J  ^  i;  5  £  :5  .^  s  .^  o  i 


£    ii^  O    3    ;=■    3    3 
ri    -    ^    ^    =    O    cs 


C     3 
J     2 


;5   Oh   C^  CO   C/^   C/: 


380       Bulletin  656 — American  Railway  Engineering  Association 


U 


^ 


1— I      a 


•5  if 


§^ 


Tf  t-  o  o 
CD  oi  Tr  CO 

CD  CD  ^'  Tj^ 
CD  05  t^  -* 
Ol  CD  05  O 
O]  CO  lO 


fM  05  r- 

a>  lo  Oi 

^  05 


O  I>  ^  o 

cr;  ^  p  f>] 

00  CO  CD  o 

(M  fM  --H  05 

I— I  CO  CO  00 


CD 


CO   —I 

CO  ■*  O  1> 

05  05  IC  CD     \   ai 

CO  i-H 


fSi  in 

CO  fM 

05  CD 
lO  CO 
00 


00  oi  in 

t-    T}<    CO 


o 
U 

c 

>^            ?? 

^ 

J 

03 

^      d;> 

o 

«  o<  c^-^ 

CC 

IS  Js    .   ^  c 

w  2 

^d 

PM 

Rail 
Rai 
R.R 

eoria 
ernii 

ID 
C 

lern 
burg 
linal 
do,  P 
do  T 

^ 

PL, 

c 

c 
o 

o 
o 

o 

o  js  <u  o  o 

.2 
'S 

'c 

s 

C/D  ^ 

l/J 

CA) 

CT)  (72  H  H  H 

hJ 

U' 

K> 

CD    TH 

CO    a 
oq    > 


g 


^  r 


•    S  ►* 
oi    C  ctf 

2  ^^ 


CM    1-   — 

cj  C   C 
HcnH 


O  CD  O  CD 

oi  f>i  I  00  o 

tT  CO  I         o 

CO  ^ 


O   r-l 

CO 
CD 

CO 

1> 

in  m    1 

\^     I       1 

CO 

in      in 

Tt<       CO 

05    I  d 


l-l 

g 
P 
z 
o 
U 

I 

03 

H 

o 

Q 

I 

O 

tit 


U 


o  in 

-* 
^ 

00 
CO 

I>  00 

in  t^ 

in  1— 1 
CO  .-1 

00   -H 
1— 1 

r 

05 
00 

as 

PQ 


-5 

g  qn 


13 


zpc; 


C    C 

03    o3 

uu 


^1 


j3 

'C 

O 

c 

ZO 

(1-1  •*-' 


o 

c 

2;  X  fe 
3    (D    o 

CVHH 


Rail 381 

Track  Miles  of  Continuous  Welded  Rail  Laid  By  Years,   1933-1974 


1933    

0.16 

1934   

0.95 

1935   

4.06 

1936   

1.52 

1937   

31.23 

1939   

6.04 

1942   

5.48 

1943   

6.29 

1944   

12.88 

1945   

4.8] 

1946   

3.91 

1947   

18.70 

1948    

29.93 

1949    

33.05 

1950    

50.25 

1951    

37.25 

1952   

40.00 

1953   

80.00 

19.54   

87.00 

Oxy-  Electric 

acetylene  Flash               Total 

1955 194.50  72.0      266.50 

1956  372.33  89.10     461.43 

1957  390.47  159.65     550.12 

1958  148.11  312.13     460.24 

1959  378.65  691.92  1070.57 

1960  299.42  961.20  1260.62 

1961  94.13  926.50  1020.63 

1962  310.59  1183.34  1493.93 

1963  497.52  1360.48  1858.00 

1964  586.76  1796.74  2383.50 

1965  700.59  1655.74  2356.33 

1966 746.61  1984.71  2731.32 

1967  784.28  1800.27  2584.55 

1968  643.10  2543.61  3186.71 

1969  674.35  2930.01  3604.36 

1970 800.30  5378.32  6178.62 

1971  504.28  3604.72  4109.00 

1972 422.91  4011.29  4434.20 

1973  465.68  4084.27  4767.37" 

1974  273.79  4183.48  4457.27 


49688.78' 


Bre.'Vk-Down  of  Continuous  Welded  Rail  Laid  in  1974 — Track  Miles 


Main   Track 

Sidings  &  Yard  Tracks 


Total  includes  217.42  miles  reported  by  Norfolk  &  Western  in  1973,  but  breakdown 
not  available. 


Oxyacetylene 

Electric 

Flash 

New 

Secondhand 

New 

Secondhand 

Totals 

113.03 

147.64 

2437.76 

1542.39 

4240.82 

.31 

12.81 

6.47 

196.86 

216.45 

113.34 

160.45 

2444.23 

1739.25 

4457.27 

382       Bulletin  656 — American  Railway  Engineering  Association 


Report  on  Assignment  9 

Standardization  of  Rail  Sections 

E.  H.  Waring  (chairman,  subcommittee),  R.  M.  Brown,  R.  F.  Bush,  P.  K.  Cruck- 
SHANK,  W.  J.  Gilbert,  W.  H.  Huffman,  H.  F.  Longfelt,  A.  B.  Merritt,  Jr., 
F.  W.  Michael,  B.  J.  Murphy,  B.  F.  Ovehbey,  R.  C.  Postels,  J.  M.  Rankin, 
I.  A.  Reiner,  G.  S.  Triebel,  G.  H.  Way,  M.  J.  Wisnowski. 

During  the  past  year,  Subcommittee  9  has  secured  from  the  American  Iron 
and  Steel  Institute  Technical  Committee  on  Railroad  Materials  a  summary  of  the 
tonnage  of  rail  shipped  from  Canadian  and  United  States  steel  mills  to  North  Ameri- 
can Railroads.  A  tabulation  of  this  information  is  included  herewith. 

It  is  noted  that  891,382  tons  or  87.52%  of  tlie  total  rail  shipped  was  in  sections 
to  which  it  is  recommended  that  purchases  of  new  rail  be  limited. 

Consolidated   Report   of   Rail   Shipped   to   North  American   Railroads   from 
North  American  Rail  Producing  Mills  in  1974  by  Weight  and  Section 


Tons 

Weight 

Section 

%  Total 

Shipped 

140' 

AREA 

6.11 

62,203 

136* 

AREA 

14.43 

147,033 

133 

AREA 

8.30 

84,514 

132* 

AREA 

36.24 

369,176 

131 

AREA 

0.01 

60 

130 

AREA 

0.05 

559 

130 

PS 

0.03 

286 

122 

CB 

2.59 

26,398 

60  KG/M 

UIC 

0.01 

89 

119* 

AREA 

6.08 

61,920 

115* 

AREA 

17.19 

175,094 

112 

AREA 

0.09 

872 

100* 

AREA 

5.61 

57,101 

100 

ARA-A 

0.96 

9,792 

90* 

ARA-A 

1.86 

18,855 

85 

CP 

0.18 

1,821 

75 

BS-11 

0.26 

2,673 

*  Recommended  section 


TOTAL 


100.00 


1,018,446 


Report  of  Committee  16 — Economics  of  Plant,  Equipment 

and  Operations 


M.  B.  Miller, 

Chairman 
L.  A.  Durham,  Jr., 

Vice  Chairman 
M.  J.  Shearer,  Jr., 

Secretary 

G.   RUGGE 

J.    R.    WiLMOT 

T.    C.    NORDQUIST 

R.  p.  Hoffman 

D.  H.  Noble 

T.  D.  Kern 

R.  D.  Penhallegon' 

J.  C.  Martin 

"R.  E.  .\hlf 


C.  Bach 

J.  W.  Barriger  (E) 

J.  \\'.  Barriger 

K.  W.  Bradley 

W.  G.  Byers 

R.  L.  Carstens 

J.  B.  Clark 

R.  P.  Corxwell 

L.  P.  Dl\mond 

W.  T.  Dlxon 

R.  H.  Dunn 

G.  B.  DuTTON,  Jr. 

J.  J.  Eash 

S.  Fog  ARTY 

J.  A.  Forbes 

B.  G.  Gallagher 

G.  R.  Gaspard 

A.  J.  Gellman 

A.  M.  Handwerker 

G.  E.  Hartsoe 

W.  W.  Hay 

L.  W.  Haydon 

J.  P.  Holland 

M.  C.  Holowaty 

E.  C.  HONATH 

G.  R.  Janosko 
H.  C.  Kendall 
T.  J.  Lamphier 
R.  J.  Lane 
A.  S.  Lang 
K.  L.  Lawson 
J.  H.  Marino 
R.  G.  Maughan 


R.  McCann 

R.  L.  McMurtrie 

C.  J.  Meyer 

R.  L.  Milner  (E) 

J.  Neben 

J.  F.  Pabtridge 

W.  L.  Paul 

J.  S.  Reed 

F.  J.  Richter 

V.  J.  Roggeveen 

A.  L.  Sams 

R.  J.  Schiefelbein 

J.  H.  Seamon 

T.  C.  Shedd 

L.  K.  SiLLCOx  (E) 

M.  L.  Silver 

T.  H.  Sjostrand 

J.  J.  Stark,  Jr. 

J.  M.  Suss  MAN 

G.  M.  Tabor 

J.  E.  Teal  (E) 

C.  L.  TowLE  (E) 
R.  Turner 

D.  E.  Turney,  Jr. 
K.  B.  Ullman 

H.  Wanaselja 

L.  E.  Ward 

F.  Wascoe 

D.  M.  Weinroth 

D.  B.  Weinstein 

P.  B.  Wilson 

T.  D.  WoFFORD,  Jr. 

Committee 


( E )    Member  Emeritus. 

Those  whose  names   are  shown  in  boldface,   in   addition  to  the  chairman,  vice  chairman,   and 
secretar>-,    are   the   subcommittee   chairmen. 

To  the  American  Railway  Engineering  Association: 

Your  committee  reports  on  the  following  subjects: 

B.  Revision  of  Manual. 
No  report. 

2.  Engineering  Methods  and  Economic  Considerations  Involved  in 
Improving  the  Quality  of  Transportation  Service. 

Final  report,  presented  as  information   page  384 

3.  Determination  of  Factors,  Including  Various  Traffic  Volumes,  Af- 
fecting Maintenance  of  Way  E.\pense  and  Effect  of  Using  Such 
Factors,  in  Terms  of  Equated  Mileage  or  Other  Derived  Factors, 
for  Allocation  of  Available  Funds  to  Maintenance  of  Way,  Col- 
laborating as  Necessary  or  Desirable  with  Committees  11  and  22. 


Bui.   656 


383 


384       Bulletin  656 — American  Railway  Engineering  Association 

(a)  Additional    Maintenance    Cost    Due    to    Operating    100-Ton 

Unit  Trains. 
No  report. 

4.  Economic    Evaluation    of   Methods   for   Reducing   the   Probability 
of  Derailments. 

No  report. 

5.  Economics  of  Freight  Cars  with  Characteristics  Approaching  the 
Limits  of  Accepted  Designs. 

No  report. 

6.  Factors  Involved  in  Rationalization  of  Railway  Systems. 
No  report. 

7.  Applications  of  Industrial  Engineering  Functions  to  the  Railroad 
Industry. 

No  report. 

8.  Economics  of  Systems  for  Control  of  Train  Operation, 
No  report. 

The  Committee  on  Economics  of  Plant,  Equipment  and  Operations, 

M.  B.  Miller,  Chairman. 


Report  on  Assignment  2 

Engineering  Methods  and  Economic  Considerations 

Involved  in  Improving  the  Quality  of 

Transportation  Service 

J.  R.  WiLMOT  (chairman,  subcommittee),  D.  B.  Weinstein  (vice  chairman,  sub- 
committee), J.  W.  Barriger,  W.  J.  Dixon,  G.  R.  Gaspard,  A.  J,  Gellman, 
J.  P.  Holland,  J.  H.  Marino,  J.  S.  Reed,  T.  C.  Shedd,  M.  L.  Silver,  J.  M. 
SussMAN,  H.  Wanaselja,  L.  E.  Ward,  F.  Wascoe,  D.  M.  Weinroth. 

This  is  a  final  report,  presented  as  information. 

Quality  is  an  intangible  which  is  not  readily  susceptible  to  exact  definition 
or  measurement.  As  anyone  who  watches  TV  commercials  knows,  it  means  differ- 
ent things  to  different  people  and  it  may  mean  different  things  to  the  same  person 
at  different  times  and  in  different  places. 

The  scope  of  this  report  is  confined  to  quality  in  railroad  freight  service.  The 
principal  elements  of  quality  in  the  order  of  their  probable  awareness  to  most  cus- 
tomers are: 

1.  Rehabihty 

a.  In  arrival  at  destination 

b.  In  elapsed  time 

c.  In  equipment  availability 


Economics  of  Plant,   Equipment  and  Operations 385 


2.  Schedule  Compatibility  with  Customer's  Requirements 

a.  In  departure  and  arrixal  times 

b.  In  elapsed  time 

3.  F"reedom  from  loss  and  damage 

Loss  and  damage,  the  last  item  on  the  preceding  list,  is  different  from  die 
others.  Both  its  extent  and  its  cost  can  be  measured,  and  the  railroad  industry  has 
long  been  aware  of  the  desirabihty  of  minimizing  them.  There  is  a  voluminous 
record  of  the  efforts  towards  that  objective  and  of  occasional  accomplishments.  This 
aspect  of  quality  will  not  be  covered  in  this  report. 

The  proper,  or  acceptable,  level  of  quality  will  vary  with  commodities  and  with 
customers.  On  traffic  for  which  there  is  intermodal  competition  the  railroads  must 
at  least  match  the  quality  of  the  other  mode  (usually  truck)  or  offer  a  rate  at  a 
discount  below  the  truck  rate,  or  accept  the  alternative  of  foregoing  the  traffic. 
Here,  an  economic  equation  must  answer  whether  the  costs  to  the  railroads  of 
bringing  their  quality-  of  service  up  to  the  truck  level  can  be  accomplished  without 
increasing  rates  above  those  of  the  truckers.  On  traffic  which  is  captive  to  tlie 
railroads  an  vmacceptable  level  of  quality  will  in  the  short  run  put  the  railroad 
and  the  customer  in  an  adversary  stance  both  in  day-to-day  operations  and  in 
regulatory  proceedings  and  in  the  long  run  will  lead  the  customer  to  seek  pro- 
duction and  distribution  methods  and  locations  which  minimize  rail  transportation. 
Normally,  improvements  in  railroad  methods  and  procedures — sometimes  in  con- 
junction with  modifications  in  the  customer's  practices — should  be  the  means  of 
bringing  substandard  service  up  to  the  level  required  by  the  customer.  Tradeoffs 
between  functions  should  be  sought  to  hold  the  rate  or  the  customer's  total  costs 
to  existing  levels.  There  will  be  occasions  when  substandard  service  reflects  a  de- 
pressed rate,  and  an  improvement  in  service  quality  will  be  contingent  upon  an 
upward  adjustment  of  the  rate. 

At  the  time  when  the  railroads  provided  virtually  the  only  intercity  freight 
transportation  the  quality  of  service  produced  by  conventional  railroad  operating 
practices  was  the  quality  expected  by  customers.  These  conventional  practices 
were — and  frequently  still  are — oriented  toward  operating  convenience  rather  than 
customer  service.  The  growth  of  other  transport  modes  has  been  paralleled  by 
changes  in  industrial  production  and  distribution  patterns.  A  large  part  of  the  goods 
in  today's  economy  are  in  the  hands  of  companies  of  national  scope  with  control  of, 
or  an  overview  interest  in,  their  product  from  raw  material  source  through  process- 
ing or  component  production  to  manufacture  or  assembly  to  distribution  center. 
Long  hauls  may  be  required  between  each  step,  requiring  an  integration  of  trans- 
portation with  production.  In  this  scheme,  in  order  to  optimize  production  schedules, 
the  reliability,  or  predictability,  of  transportation  movements  has  taken  on  much 
greater  importance.  Concurrently,  centralization  of  industrial  planning  has  brought 
a  greater  sophistication  in  the  treatment  of  the  time  value  of  money,  which  ap- 
pears in  efforts  to  minimize  investment  in  goods  flowing  through  the  production 
and  distribution  process,  with  resulting  lower  inventory  margins  to  protect  against 
irregularities  in  transportation  schedule  performance.  The  railroads,  as  well  as 
industrial  companies,  have  become  aware  of  the  time  value  of  money,  as  is  evident 
from  the  fact  that  every  car  in  the  railroad-owned  fleet  is  no  longer  priced  for  off- 
line  rental   at  one   dollar  per  day. 


386       Bulletin  656 — American  Railway  Engineering  Association 

For  the  customer  who  has  a  traffic  movement  tied  to  a  particular  railroad, 
sei'vice  failures  or  car  shortages  may  stop  his  production  line  or  leave  his  dealers 
out  of  stock.  While  this  railroad  may  be  the  customer's  only  railroad,  this  customer 
is  not  the  railroad's  only  customer.  The  railroad's  objective  is  to  integrate  this  cus- 
tomer's traffic  into  its  network  in  a  manner  that  will  produce  a  profit  over  a  year's 
time.  Satisfying  the  customer's  requirements  calls  for  more  accommodation  on  the 
part  of  the  railroad  than  of  the  customer.  For  example,  railroad  schedules  and  the 
records  by  which  performance  is  usually  measured  are  nomially  in  terms  of  tenninal- 
to-terminal  time,  but  the  customer's  reliability  requirements  are  in  tenns  of  dock- 
to-dock  time. 

There  must  be  a  meeting  of  the  minds  on  the  level  of  quality  required  and 
the  acceptable  attainment  level.  Railroad  line-haul  service  cannot  be  performed 
under  exactly  identical  conditions  from  day  to  day,  and  unlike  a  product,  units 
that  do  not  meet  the  quality  standard  cannot  be  rejected  by  either  a  quality-control 
inspector  or  the  customer. 

The  association  between  quality  and  productivity  was  pointed  out  in  the  re- 
port of  the  Task  Force  on  Railroad  Productivity  in  1973.^  This  report  highlights 
some  of  the  impediments  to  greater  productivity  which  must  be  overcome.  One 
of  these  is  the  diffusion  of  proprietary  responsibility  among  a  large  niunber  of 
companies,  while  at  the  same  time  each  company,  on  the  average,  must  share 
about  one-half  of  its  traffic  with  other  companies.  The  result  has  been  that  invest- 
ments and  methods  directed  at  upgrading  the  quality  of  service  have  been  more 
frequent  when  applied  to  the  half  of  the  traffic  which  is  single-hne  than  to  the 
half  which  is  interline.  The  interline  traffic  tends  toward  longer  hauls  of  higher- 
rated  commodities,  but  agreement  between  companies  on  the  costs  and  benefits 
of  service  improvement  has  not  been  easy. 

The  Productivity  report  brings  out  that  most  railroad  mergers  have  been  paral- 
lel ones,  emphasizing  cost  reductions  by  avoiding  duplications  of  plant  and  service. 
Savings  in  costs  and  improvements  in  service  are  not  mutually  exclusive,  but,  as 
the  report  states,  trucking  company  mergers  are  usually  end-to-end,  with  improve- 
ments in  service  the  primary  objective.  For  this  reason  and  others,  not  all  readily 
adaptable  to  the  railroad  industry,  a  single-line  strategy  in  the  trucking  industry 
has  resulted  in  interline  hauls  with  their  divided  responsibility  being  exceptional, 
a  feature  which  should  be  recognized  in  railroad  service. 

The  authors  of  Improving  Railroad  Productivity  found  five  particularly  promis- 
ing areas  for  innovation,  which  are:  (1)  the  development  of  a  containerization 
strategy;  (2)  a  freight  car  management  system;  (3)  revised  train  scheduling  and 
operations  (especially,  shorter,  more  frequent  trains);  (4)  costing,  pricing  and 
profit  analysis;  and  (5)  improved  management  planning.  These  areas  in  the  context 
of  the  report  are  associated  with  improved  productivity.  Throughout  the  report, 
however,  there  is  a  very  clearly  implied  association  between  improvement  in  pro- 
ductivity and  improvement  in  quality  of  service,  revenue  and  profit. 

A  recent  dialogue  on  productivity  and  its  association  with  quality  in  transporta- 
tion appeared  with  the  fuel  crisis.  Several  tabulations  from  neutral  sources  were 
published  showing  energy  consumption  per  ton-mile  for  various  transport  modes, 
with  highly  favorable  rankings  for  the  rail  mode.  Some  trucking  industry  spokes- 
men have  protested,  however,  that  a  truck  ton-mile  and  rail  ton-mile  are  not  equal. 


I  Improving  Railroad  Productivity,   Final  Report   of  the  Task  Force  on  Railroad  Productivity; 
National   Commission   on   Productivity   and  the   Council   of  Economic  Advisers,   November   1973. 


Economics  of  Plant,  Equipment  and  Operations  387 

because    they   contend    that   the   former   contains    a   higher   quahty   component,   for 
such  factors  as  speed,  reliabiUty  and  unified  control  from  dock  to  dock. 

The  MIT/Southem  Railway  Study 

Probably  the  most  fully  documented  study  on  the  quality  of  railroad  service — 
specifically,  on  the  key  aspect  of  rehability — \\as  performed  by  the  Massachusetts 
Institute  of  Technology  for  the  Federal  Railroad  Administration  during  1971  and 
1972.  Following  the  report  of  its  investigation  and  research,  from  November  1972 
to  January  1974,  MIT  with  FRA  funding  made  a  case  study  on  tlie  Southern  Rail- 
way to  implement  and  apply  its  findings  under  actual  operating  conditions.  The 
results  of  this  case  study  were  published  in  Miirch   1974." 

One  region  of  the  Southern  was  selected  for  the  stud>',  and  the  first-phase 
activity  was  the  collection  of  data  on  current  performance  at  the  levels  of  origin- 
destination,  corridor,  yard,  and  train,  with  which  reliability  was  measured.  The 
ability  of  the  Southern's  management  information  system  to  measure  reliability  be- 
fore and  after  implementation  of  recommended  changes  was  critical  to  the  success 
of  the  case  study  and  such  an  ability  should  be  a  part  of  any  service  improvement 
program. 

Sample  pages  of  two  regular  reliability  reports  produced  by  the  Southern  are 
illustrated.  Figure  1  is  a  reproduction  of  one  page  (for  one  origin)  of  a  monthly 
summary  of  transit  time  between  major  terminal  pairs  on  the  system.  For  example, 
from  Origin  CIXCI  (Cincinnati)  to  Destination  NO  LA  (New  Orleans)  785  cars 
moved  during  the  month,  on  639  of  which  sufficient  data  were  captured  for  proc- 
essing in  the  report.  The  mean  time  of  the  639  cars  was  91  hours.  The  greatest 
concentration  of  traffic  in  four  consecutive  12-hour  periods  of  trip  time  was  75 
percent  (see  "Four  Period"  column),  the  sum  of  the  percentages  in  frequency  dis- 
tribution columns  6,  7,  8  and  9,  by  period,  with  a  difference  of  1  percentage  point 
due  to  rounding. 

Figure  2  is  a  reproduction  of  a  page  of  tlie  supporting  detail  for  Figure  1.  The 
first  four  lines  of  data  show  for  the  639  cars  measured  in  Figure  1  the  origin  and  des- 
tination tenninal  times  bracketed  in  4-hour  periods  and  the  total  transit  time  ex- 
cluding origin  and  destination  terminal  time  bracketed  in  12-hour  periods.  The 
following  blocks  of  data  show  for  the  cars  moving  between  die  origin-and-destina- 
tion  pair  by  each  of  several  alternate  routes  the  origin  and  destination  time  as  in 
the  summary  block,  with  the  additional  breakdown  of  the  total  transit  time  into 
hue-haul  time  between  each  terminal  in  6-hour  brackets  and  intermediate  terminal 
time  in  4-hour  brackets. 

The  Southern  is  continuing  to  develop  its  perfonnance  measurement  reporting 
and  is  using  an  improved  version  of  the  reports  illustrated  here.  Reference  is  now 
made  to  standard  trip  times,  together  with  other  measures  which  facilitate  identi- 
fication of  variations  from  acceptable  performance. 

The  study  team  selected  situations  on  the  Southern  for  testing  strategies  for 
rehabilit>-  improvement,  based  on  its  prior  investigation  and  research.  Any  such 
strategy,  it  concluded,  must  achieve  one  or  more  of  the  following  results :  ( 1 )  im- 
prove reliability  of  local  service  at  origin  or  destination;  (2)  improve  reliability  of 
train    connections    at    intermediate    yards;    (3)    improve   the   consistency   of   routing 


-  MIT    Report    No.    R74-28,    Improving   Railroad   Reliability:    A   Case   Study   of  the   Southern 
Railway;    Studies   in   Railroad   Operations   and   Economics,   Volume    10,   by   Carl   D.   Martland. 


388       Bulletin  656 — American  Railway  Engineering  Association 


>  Hf    I    C   r=  rr  r\    1 


J  f-T  -*    I     I    r-  < 


,  T^  -4    <   •€  t^   < 


1  r-  («■  c  r^  c 


«  «  «  «  «    «  « 


D  < 
C  K 
X  Z 


lu  3U. 

=  ►•O 

<  Z  VI 

s 

bO 

I    r^    I    C  f^  H  o-  m  I 

r^  H  rf 

«    «    »    « 

I      I      \    r^tntr,  C  I  I 

t      I      I      I      I      I      I  I  I 

I    I    r    I    I    I    I  I  I 


1  r-  o  csj  H  c  < 


o:      of  p 

3      13  D      r-  c  ^  r--  f 
to      o  •-■      in  o  cr  *f  ( 


)  rf  n  m  o  h-  < 


§x 


c    m 

>-  >3 

=  oz 
nx 

€Cf>X 

t-zt- 

—  o  - 
pnec 

OOQ. 

ZX  I 
UJ  HO 


U.  MO. 

u.  aevi 

<o 

tc     < 

H  Ul 

x« 


H        H  H        H        H  H 


t^      H  o*  •«■  1*^  ^^  o  o*  *o  in  c  rf  > 


)'Or-<r'O«a'rtO'«0       T^c 


v)r3      •*-r^cor^mi^inff>*rgHH'^ooo*r^r-'Oric>iHr-o>fnrf      ttiMr^fna* 

oc  fcO  ra  o  r^  tn       HO-       rg  rf  ^  r1       ^ 'J- rt  u>  H       rt -O  rf  *  H 


xo« 
>-  x« 

X  QO. 

zu> 

I-  310 

z  o 
Ul  no 

U  ZIU 


1  o  o  r^  0^  ^  ^  r^  rg  r- r^  <D  H       o  m  r^  *r  c 


h-  M  >  Z  to  X -t -J  »- Z  <  I/)  >  <  O  O  -J  (/I  >  •-•  Z  X  n  J  <  o  u  o 

<  ■-•  UJ  <  3  z  »- ac  >- »- m  n  ^  > -J  n  >  ^  X  >  o  a  M  ■-• -I  >- z  < 

z  z  X -I  o  a:  z  <  <  in  _i  _j  z  z  I- UJ  UJ  u  o  13  o  z  fic  n      >-*-•> 

►-  Z  i/ll-  3  —  UJ  I  I  X  O  O  <«  mot  «  <  Z  0"«  UJ  UJ  ooo  oc  < 

>-  <  <  <  <  p)  u  u  Ljuu  u  n  n  uiuo ->:x:  _i  z  z  z  zz  o.  a  10 


►- 
I  tf'* 

za.  I 
m  wio* 
azo 
>«  I 
ZK  <o 


19        UOUOOOOt 


JOUOUOOUOUUUUUO 


I    I   I 
•  •  • 


Economics  of  Plant,  Equipment  and  Operations 


389 


«r  rt 


c  c 


I"  OZ  111 

3  zo  s: 


xzzz  iiixiiii      m      ixiiiiiii; 


en  z       »-  — 

a:  I       >-o. 
»-      zo 


oo 

J- 

^- 

C3C 

> 

l-a. 

X  u. 

••-• 

(  H  r^    H  H  r1  r1  r^ 


rt  H  M  rl  » 


OHO(sr->o->f-o 


o  uj  a.  z 

0.0  2*^ 
O  O 

U.O  < 
««       »-   • 

oec  zoz 


za.  o 
—  rat 

o.  o 

30C  C 

o  o  * 


1      —  rao. 

-I-    30C 


or- 
:  a.   I 

-  fco  a- 

-  z  o 


"  XXX 

«  lo  <  _l  >-        Z 

OZ-J<  OlU<UJZUJ. 

z<      t-  zz-iza:z 


3         D  3         D 

<         <  <         < 

I         I  I         X 

Z         Z         I        <  -t 

}iii<uJO  UJZUJ_J< 

rz-izozaz      t- 

.«»-  —  <  ««_oo 


X         I  _ 

z  z  <  : 


,  X  •-  ^  ^  o  o 


390       Bulletin  656 — American  Railway  Engineering  Association 

between  origin  and  destination;  (4)  reduce  the  number  of  times  cars  are  switched; 
or  (5)  reduce  the  number  of  extraordinary  delays  caused  by  no-bills,  misroutes 
and  mechanical  failures. 

Five  distinct  tests  were  made  in  the  case  study.  These  will  be  described  briefly 
to  show  the  diversity  of  approaches  to  the  improvement  of  reliability. 

1.  The  first  test  situation  involved  the  irregular  performance  of  Trains  93 
and  4  between  D  and  A,  resulting  in  very  poor  service  between  those 
points.  The  implemented  recommendations  were  to  operate  tlie  trains 
on  a  daily  schedule  rather  than  irregularly,  to  operate  them  beyond  A  to 
E  with  stops  only  to  pick  up  and  set  off  cars  at  A,  to  assign  tsvo  sets  of 
power  exclusively  to  these  trains,  and  to  use  the  trains  for  A — E  traffic 
as  well  as  D — E  traffic. 

2.  The  problem  for  which  the  second  test  sought  a  solution  was  one  of  long 
delays  on  high-cost  empty  cars  between  the  time  they  were  released  by 
the  industry,  passed  through  a  satellite  yard  and  departed  on  an  out- 
bound train  from  the  classification  yard,  A.  The  trouble  was  traced  to 
the  satellite  yard,  and  the  implemented  recommendation  was  that  per- 
formance standards  be  set  for  the  satellite  yard  to  the  end  that  all  empties 
in  the  yard  at  midnight  would  arrive  at  Yard  A  by  10:00  am  and  that 
empties  should  not  remain  in  the  satellite  yard  more  than  20  hours. 

3.  The  third  test  revolved  around  poor  origin  and  destination  performance 
on  an  agricultural  commodity  originating  at  local  stations  and  assembled 
at  Yard  K  for  movement  on  through  trains.  Investigation  disclosed  that 
much  of  the  traffic  was  humped  at  two  or  more  classification  yards  and 
that  connections  at  Yard  K  from  local  trains  to  96,  the  tlirough  train 
handling  the  traffic,  required  more  than  25  hours  on  the  average.  The 
recommended  strategy,  which  was  tested,  was  to  operate  Train  96  on  a 
scheduled  daily  basis  rather  than  irregularly  from  Yard  K  to  Yard  C,  to 
move  all  traffic  for  C  and  beyond  in  a  single  block  to  Yard  C,  and  when- 
ever possible  to  block  cars  for  C  and  beyond  prior  to  their  arrival  at  K 
and  thus  bypass  classification  at  K. 

4.  For  the  fourth  test,  the  problem  was  that  more  than  20  percent  of  the 
cars  from  Yard  F  to  Yard  E  instead  of  moving  direct  on  Train  34  moved 
on  Train  15  to  Yard  A,  an  intermediate  point,  where  they  were  humped 
and  dispatched  on  one  of  several  trains,  with  added  transit  time  of  10 
to  40  hours.  The  recommendations  made  effective  were  to  move  traffic 
from  Yard  F  to  Yard  E  on  Train  34  whenever  possible,  but,  in  default, 
to  hold  for  Train  34  the  next  day  (4  pm)  rather  than  for  Train  15  (next 
day,  8  am),  and  as  a  last  resort  to  move  traffic  on  Train  15  only  if  Yard 
F  is  congested  or  Train  34  will  be  unable  to  handle  the  traffic. 

5.  The  fifth  test  was  directed  to  the  problem  at  Yard  D,  which  was  not 
unique.  Inbound  to  outbound  train  connections  were  unreliable,  with  ap- 
proximately 15  percent  of  the  cars  humped  missing  their  proper  connec- 
tion, and  the  time  for  more  than  20  percent  of  actual  connections  was  in 
excess  of  24  hours.  Average  scheduled  and  available  yard  times  were  both 
13  hours,  but  average  actual  yard  time  was  20  hours.  The  implemented 
recommendations  were  to  reschedule  one  train  to  depart  from  Yard  D  3 
hours  later  and  another  train  to  arrive  2  hours  earlier.  This  was  the  only 


Economics  of  Plant,   Equipment  and  Operations 


391 


TABLE    1 
SUMMARY  OF  THE  TEST  PROGRAM 


Test         Implemented 
No.           Recommendation 

Cars/Day 

Increase    in 
Pel  labi 1 1 ty 

Decrease    in 
Trip  Times 

Decrease 
In  Cost 

1.      Operate   run-through   trains 
between  D  and  E_ 

Predicted 
Actual 

200 
180 

21% 
14i 

16  hours 
19   hours 

$15,000 
$15,000 

2.      Monitor   industrial    switch- 
ing near  A 

Predicted 
Actual 

60 
40 

lO'i 
15- 

18  hours 
21    hours 

$  5.000 
$  6,000 

3.     Allocate  more  power  and  re- 
vise local   operating  pro- 
cedures  for  agricultural 
traffic   from  K 

Predicted 
Actual 

68 
72 

25% 
14? 

18  hours 
18  hours 

1 
$  4,000 
$  6.000 

4.      Move   through  cars  only  on 
the  runthrough  train  from 
L  t-o  L    * 

Predicted 
Actual 

40 
40 

10" 
2",* 

12  hours 
10  hours* 

$  2,500 
S  2.00C* 

5.     Revise  train  schedules   to 
reduce  unreliable  connec- 
tions at  D 

Predicted 
Actual 

200 
210 

\QX 

4  hours 

** 

$  4,000 

*       This   improvement  did  not  result   from  the   test  program. 
**     rompirablp  result's   ire  not   available 

Source:      MIT  Report   No.    R7A-23,    Table   5-1. 


one  of  the  test  programs  for  which  the  results  could  not  be  measured. 
During  the  implementation  period  major  network  changes  on  the  Southern 
(significant  schedule  revisions  for  six  other  trains  as  a  result  of  the  open- 
ing of  the  new  Sheffield  Yard  and  major  roadway  work  on  one  of  the 
lines  converging  on  Yard  D)  obscured  the  impact  of  the  two  schedule 
changes  of  the  test  program. 

As  depicted  in  Table  1,  the  four  test  programs  for  which  results  could  be 
measured  were  successful  in  showing  improvements  in  reliability,  decreases  in  transit 
times,  and,  in  three  cases,  decreases  in  costs. 

This  case  study  vdth  its  three  diverse  sponsors  was  unique  in  its  approach  to 
the  problem  of  railroad  reliability,  and,  more  important  for  the  railroad  industry, 
in  the  depth  of  the  reporting  of  the  study,  with  quantitative  results. 

The  report  states  that  the  problem-solving  approach  and  procedure  of  the  test 
program  consisted  of  the  seven  following  steps:   (1)  define  the  objective;   (2)  meas- 


392       Bulletin  656 — American  Railway  Engineering  Association 

lire  current  performance;  (3)  identify  a  manageable  set  of  problems;  (4)  identify 
potential  solutions;  (5)  evaluate  potential  solutions;  (6)  select  and  implement  the 
best  policies  for  a  trial  period;  and  (7)   monitor  and  record  the  impacts. 

The  recommendations  which  were  implemented  in  the  test  program  evolved 
under  consideration  of  the  following  criteria:  (1)  Feasihility  of  implementation  by 
the  Southern  on  short  notice;  (2)  Measurahility  of  predicted  and  actual  impacts; 
(3)  Effectiveness,  in  tenns  of  a  substantial  improvement  in  Southern  service  with  a 
minimal  increase  in  costs;  and  (4)  Impact,  in  terms  of  important,  high-volume  traf- 
fic movements. 

Other  Research  and  Applications 

The  fully-documented  case  study  on  the  Southern  Railway  involved  several 
tests  directed  at  improving  service  directly,  or  indirectly  through  better  car  utiliza- 
tion, by  making  localized  changes  in  road  and  yard  schedules,  traffic  assignment 
to  trains  and  power  assignments. 

The  subject  of  quality  of  service  and  the  need  for  its  improvement  is  such  a 
broad  one  that  research  and  applications  have  been  diverse.  Local  changes  with 
service  objectives  are,  of  course,  being  made  somewhere  almost  every  day,  but 
without  the  benefit  to  the  industry  of  recorded  research  and  measurement  of  re- 
sults. Reported  activity  is  frequently  on  the  development  of  systemwide  concepts 
or  procedures.  A  brief  review  of  a  selection  of  endeavors  on  quality  improvement 
follows. 

CP  Rail.^  The  MINDISC  total  distribution  cost  model  was  developed  for  use  in 
conjunction  with  the  FRATE  operating  cost  model.  Factors  considered  include  the 
level  of  reliability  customers  are  willing  to  pay  for,  the  fact  that  most  trains  carry 
cars  with  varying  levels  of  customer  reliability  requirements,  and  the  tradeoffs  be- 
tween advertising  faster  schedules  and  seeking  maximum  reliability  with  existing 
schedules.  In  a  test  of  the  model  for  a  train  with  a  specific  consumer  product, 
locomotive  units  were  assigned  through  a  range  of  2  to  8,  and  costs  were  deter- 
mined for  door-to-door  transit  times  from  2.5  to  5  days  with  99  percent  reliability. 
For  theoretical  perfect  service  total  distribution  cost  was  reduced  by  $2.50  per  ton 
but  railroad  costs  were  increased  by  $5.00  per  ton.  This  illustration  was  not  given 
to  demonstrate  that  improved  service  is  uneconomic  but  to  show  the  capability  of 
the  model  in  simulating  an  idealized  level  of  service,  at  some  level  below  which 
it  would  find  the  economic  optimum  level. 

Denver  6-  Rio  Grande  Western.*  Following  research  and  simulation,  the  first  broad 
application  of  a  policy  of  running  shorter,  faster  and  more  frequent  trains  was  in- 
stituted in  1964.  Several  characteristics  of  the  railroad  made  it  a  favorable  site  for 
a  test  of  the  policy.  Perhaps  the  most  significant  was  the  opportunity  to  eliminate 
a  substantial  amount  of  main-line  helper  service.  A  "before  and  after"  comparison 
of  system  statistics — in  which  the  effects  of  the  short,  fast  train  policy  are  reflected 
— for  the  years  1963  and  1966  is  summarized  below: 


*  "Some  Thoughts  on  the  Reliability  of  Railroading"  by  Peter  J.  Detinold,  Special  Assistant, 
Research;  in  Transporting   Research  Forum  Proceedings,   1972,  Page  505. 

*  Company  documentation. 


Economics  of  Plant,  Equipment  and  Op 

lerations 

;                  393 

1963 

1966 

Percent  Change 
Actual      Adjusted'* 

Trailing  Gross  Ton-Miles 
( Millions ) 

11,600 

14,811 

-f-27.7 



Crew   Costsf    (Thousands) 

$6,324 

$8,772 

+38.7 

+  11.3 

Gross  Tons  per  Train 

3,481 

2,876 

-17.4 

— 

Average  Speed   (MPH) 

22.3 

25.4 

+  13.9 

— 

Train-Miles  ( Thousands ) 

3,333 

5,150 

+54.5 

+26.9 

Horsepower  per  Unit 

1,600 

2,017 

+26.1 

— 

Unit-Miles   (Thousands) 

15,223 

20,009 

+31.4 

— 

Horsepower-Miles    ( Millions ) 

24,357 

40,3.58 

+  65.7 

+38.0 

No.  of  Units 

187 

187 

0 

-  1.1 

Car-Miles  per  Car-Day 

44.4 

53.7 

+20.9 

— 

Car-Days  (Thousands) 

4,788 

4,515 

-  5.7 

-17.4 

Adjusted  Increase  in  Operating 

Costs 

$2,373,000 

Adjusted  Savings:   Locomotive 

Ownership 

60,000 

Car  Hire 

3,080,000 

Net  Potential  Saving  $    767,000 

'  Adjusted   to   eliminate   changes   due   to   increases   in  wage   rates   and   fringe 

benefits  and  in  traffic  volume. 
t  Wages  and  fringe  benefits. 

Frisco/'  The  Quality  Control  Section  was  established  in  1964.  Among  its  accom- 
plishments are  the  TSE  Report  (Terminal  Service  Evaluation),  measuring  elapsed 
time  between  pairs  of  events  (e.g.,  arrival  until  movement)  at  12  terminals,  with 
a  summary  analysis  of  missed  per  diem  situations,  and  train  performance  sum- 
maries of  selected  trains  with  exception  comparisons  of  actual  movement  with 
schedules  in  the  computer  file.  These  reports  influenced  decisions  to  revise  priorities 
in  capital  improvements  because  more  delays  than  had  been  thought  were  occur- 
ring on  the  road  and  fewer  in  terminals,  and  led  to  development  of  a  computer- 
generated  train-meet  calculator  to  determine  where  passing  tracks  should  be  ex- 
tended and  to  substituting  advance  sections  for  second  sections  whenever  possible. 
Illinois  Central  Gulf/  A  comprehensive  study  was  made  of  the  Memphis  terminal, 
as  a  test  case,  to  identify  proposed  rule  changes  which  would  enable  the  railroad 
to  improve  the  quality  of  service  as  a  result  of  more  efficient  yard  operations  and 
better  car  utilization.  The  changes  are  in  five  categories:  labor  rules  applying  to 
yard  crews  (e.g.,  crews  to  report  daily  to  regular  assignments  in  lieu  of  calls); 
labor  rules  applying  to  road  crews  (e.g.,  crews  to  put  away  trains  at  any  number 
of  yards  in  terminal  as  directed  by  yardmaster);  labor  rules  applying  to  both  yard 
and  road  crews  (e.g.,  abolish  yard  limit  rules);  rules  applying  to  customers  {e.g., 
customers  to  be  charged  for  rejecting  cars  which  meet  their  specifications;  demur- 
rage charges  to  be  increased);  interchange  rules  (ICG  could  change  designated 
interchange  tracks  for  deliveries  by  other  railroads  on  an  hour-to-hour  basis;  per 
diem  to  be  calculated  and  prorated  on  an  hourly  basis). 
Missouri  Pacific.'  TCS   (Transportation  Control  System)   was  developed  with  design 


^  RaUway  Age,  July  31,  1972,  page  24. 

'  "A  Proposal  to  Iniprove  Railroad  Terminal  Performance  Through  Changes  in  Present  Rules" 
by  Larry  A.  Hemdon,  Manager,  Operating  Data  Planning;  in  Transportation  Research  Forum 
Proceedings,    1973,  Page  213. 

|^"Mopac's  Transportation  Control  System — A  System's  Approach  to  Achieving  Service  Relia- 
bility" by  Guerdon  Sines,  Director,  Information  and  Controls  Systems;  in  Transportation  Research 
Forum   Proceedings.    1972,   Page   513, 


394       Bulletin  656 — American  Railway  Engineering  Association 

objectives  to:  Increase  service  reliability  through  more  consistent  availability  of 
empties  and  more  consistent  movement  of  loads  and  empties;  reduce  transportation 
costs  and  maintain  them  at  levels  permitting  competitive  pricing  by  controlling 
commitments  of  cars,  power,  crews  and  plant;  reduce  clerical  costs  in  information 
generation  by  reducing  the  association  between  peaking  in  yard  and  road  car 
activity  at  terminals  and  peaking  in  the  accompanying  billing  and  data  processing 
work;  improve  communication  with  customers  by  eliminating  redundant  fonns  and 
messages;  improve  the  quality  of  management  reports  by  moving  from  reports  of 
statistical  averages  toward  ones  with  greater  sensitivity  to  significant  variations. 
Rock  Island.^  In  1971,  with  the  objective  of  improving  the  utilization  of  covered 
hopper  cars  which  were  in  short  supply,  novel  rates  were  published  on  com  and 
soybeans  from  the  Midwest  to  Gulf  ports  for  export.  A  series  of  at  least  five  ship- 
ments of  not  less  than  5,000  tons  each  must  be  made  in  not  more  than  54  cars 
(up  to  64  in  light-rail  origin  territory),  which  must  be  committed  to  a  series  of 
consecutive  trips,  vdth  hmited  loading  and  unloading  times.  The  rates  are  lowest 
when  all  the  cars  are  loaded  at  one  elevator,  with  options  for  two  elevators  ( a  mini- 
mum of  15  cars  from  one  elevator)  and  for  any  number  of  elevators  in  a  group 
(a  minimum  of  5  cars  per  elevator).  Lower  rates  are  provided  in  lieu  of  a  mileage 
allowance  when  private  cars  are  used.  Successive  shipments  need  not  be  from  the 
same  origins.  Examples  demonstrated  rate  reductions  ranging  from  13  to  17  percent 
and  a  22  percent  reduction  in  variable  costs.  During  the  first  year,  while  various 
elevators  were  in  the  process  of  gearing  up  to  take  advantage  of  the  rates,  45 
trains  moved  under  the  provisions  of  the  new  tariffs,  with  an  average  round-trip 
tumaroiuid  per  car  of  8.9  days,  an  improvement  over  the  10  days  estimated  when 
the  rates  were  proposed.  Not  only  was  service  thus  improved,  but  when  compared 
with  average  times  for  single-car  shipments  in  this  traffic  of  21  days  without 
transit  and  28  days  when  transited,  the  21,832  car-days  required  to  move  2,449 
carloads  represented  a  saving  equivalent  to  the  addition  to  the  fleet  of  81  new 
cars  if  the  traffic  had  moved  in  single  cars  without  transit  or  128  new  cars  if  the 
single-car  shipments   had  been  transited. 

Santa  Fe.  A  new  pattern  of  long-distance  freight  train  scheduling  was  initiated  in 
1973.  Instead  of  fleeting  trains,  which  causes  congestion  on  both  line  of  road  and 
in  terminals,  schedules  were  adjusted  to  achieve  evenly  spaced  departures  for 
Chicago-Southern  California  trains,  Chicago-Northern  California  trains,  Chicago- 
Texas  trains,  and  Chicago-Denver  trains.  Similar  scheduhng  was  done  for  trains 
out  of  Kansas  City  to  the  same  destinations.  A  corresponding  pattern  of  east  and 
northbound  departures  from  California,  Texas  and  Denver  is  in  effect.  Also,  RHF 
(Regular  High  Frequency)  schedules  are  in  effect  between  California  and  Texas. 
The  annulling  of  trains  in  the  light-traffic  direction  is  prohibited.  The  results  of 
this  type  of  operation  have  been  more  reliable  service  and  better  car,  locomotive, 
caboose  and  facilities  utilization. 

Southern  Pacific."  TMIS    (Terminal  Management  Information  System)   was  devel- 


8  Corn  and  Soybeans  Midwest  to  Gulf  Ports,  for  Export,  339  ICC  595  (1971),  and  com- 
pany documentation. 

*  "Use  of  Computers  in  Measuring  and  Evaluating  Terminal  Operations"  by  T.  A.  Lewis, 
Special  Assistant,  Operating  and  Terminal  Systems;  in  Transportation  Research  Forum  Proceed- 
ings,   1973,   page   229. 


Economics  of  Plant,   Equipment  and  Operations 395 

oped,  which  produces  reports  of  car  movements  completed,  cost  per  car  movement, 
car  movements  completed  on  schedule  and  average  hours  per  car  movement.  Fur- 
ther, from  a  100^  sample  of  the  data,  a  summary  of  condensed  significant  informa- 
tion is  produced.  An  analysis  of  the  results  of  the  system  at  one  terminal  disclosed 
that  the  cost  per  car  movement  was  reduced  from  $10.83  to  $9.01,  that  schedule 
performance  increased  from  74  percent  to  83  percent,  and  that  the  average  hours 
per  car  movement  were  reduced  from  2.3.3  to  21.0. 

"Studies  in  Railroad  Operations  and  Economics."  A  series  of  reports  under  the 
above  title  has  reached  17  volumes,  of  which  the  first  15  deal  with  railroad  freight 
service  reliabihty.  The  reports  cover  research  performed  by  the  Massachusetts 
Institute  of  Technology,  with  funding  for  the  most  part  by  the  Federal  Railroad 
Administration.  One-paragraph  abstracts  of  most  of  the  \'olumes  follow. 

Volume  1:  Railroad  Car  Movement  Reliability:  A  Preliminary  Study  of 
Line-Haul  Operations.  Authors:  A.  S.  Lang  and  R.  M.  Reid.  Date: 
October  1970.  MIT  Report  No.  R70-74.  Sponsoring  Agency:  Union 
Pacific  Foundation. 

Data  on  road  train  delays  due  to  various  types  of  mechanical  failures  and 
derailments  and  on  the  duration  of  these  delays  were  collected  for  a  total 
of  1,065  trains  operating  over  a  single  main-line  division  during  a  two- 
month  period.  These  delays  were  classified  by  major  type  (brake,  coupler, 
and  other  type  of  failures,  not  including  engine  failures)  and  by  causal 
factors  (train  length,  trailing  tonnage,  and  track  profile)  operative  at  the 
time  of  the  failure. 

Volume  2:  Rail  Trip  Time  Reliability:  Evaluation  of  Performance  Measures 
and  Analysis  of  Trip  Time  Data.  Author:  Carl  D.  Martland.  Date: 
June  1972.  MIT  Report  No.  R72-37.  Sponsoring  Agency:  Federal  Rail- 
road Administration,  U.  S.  Department  of  Transportation. 
After  evaluating  alternative  measures  within  a  logistics  framework,  this 
report  recommends  two  measures  of  reliability,  the  maximum  percentage  of 
cars  whose  trip  times  fall  in  a  consecutive  two  or  three  day  period  of  the 
trip  time  distribution  (the  2-  or  3-day  %)  and  the  percentage  of  cars  arriv- 
ing after  this  period  (the  %-late).  Nevertheless,  a  dialogue  with  shippers  is 
necessary  before  the  most  appropriate  measures  can  be  determined  for  a 
specific  situation.  Using  these  measures,  origin-to-destination  (O-D)  data 
for  three  railroads  are  analyzed  to  discover  the  nature  of  O-D  relialiility. 
The  typical  trip  time  distribution  was  found  to  be  unimodal  with  extreme 
value  concentrated  on  the  high  side,  with  a  3-day-%  between  60  and  95, 
and  with  a  %-late  less  than  25.  There  is  no  simple  cause  of  unreliability. 
Although  yard  classifications  are  found  to  affect  rehability  much  more  than 
does  distance,  detailed  train  information  is  necessary  to  predict  the  nature 
of  this  impact  for  a  particular  O-D  pair.  In  general,  however,  reducing  the 
number  of  classifications  or  improving  yard  operations  will  impro\'e  both 
reliability  and  mean  trip  times. 

Volume  3:    Determinants  of  Line  Haul  Reliability.  Authors:    Kenneth   Bclo- 

varac  and  James  T.  Kneafsey.  Date:  June  1972.  MIT  Report  No.  R72- 

38.   Sponsoring  Agency:    FRA. 

This  work  examines  in  detail  the  variance  in  arrival  time  and  its  components 

for  a   total  of   1197   trains   operating  over  three   different  runs    (of  a  single 


396       Bulletin  656 — American  Railway  Engineering  Association 

railroad)  varying  from  150  to  270  miles  in  length.  Their  data  showed 
standard  deviations  of  arrival  times  which  typically  ranged  from  one  to 
three-and-a-half  hours  for  trains  operating  on  a  half  dozen  different  sched- 
ules. More  important,  the  analysis  of  their  data  showed  that  the  variability 
in  departure  time,  in  running  time  (excluding  stops  and  delays),  and  in 
intemiediate  yard  time  were  the  major  contributors  to  arrival  time  variance. 
Standard  deviations  of  departure  times  (from  the  initial  terminal)  were  on 
the  order  of  45  minutes  to  an  hour-and-a-half,  of  running  times  from  45 
minutes  to  two-and-a-half  hours,  and  of  intermediate  yard  times  from  one- 
half  an  hour  to  an  hour. 

Volume  4:  The  Impact  of  Classification  Yard  Performance  on  Rail  Trip  Time 
Reliability.  Authors:  Robert  M.  Reid,  John  D.  O'Doherty,  Joseph  M. 
Sussman  and  A.  Scheffer  Lang.  Date:  June  1972.  MIT  Report  No. 
R72-39.    Sponsoring  Agency:    FRA. 

Yard  reliability  emerges  as  a  problem  of  central  importance  to  overall  move- 
ment reliability.  Detailed  studies  of  three  yards  suggest  that  10  to  20%  of 
all  cars  miss  their  most  appropriate  outbound  train  connections,  although 
performance  varies  not  only  between  yards,  but  between  inbound-outbound 
train  pairs  at  the  same  yard.  It  is  possible  to  express  the  probability  of 
making  a  connection  as  an  increasing  function  of  the  time  available  to  make 
the  connection,  since  the  extra  time  offsets  both  arrival  delays  and  conges- 
tion delays.  The  greatest  cause  of  delay,  however,  is  the  cancellation  of  out- 
bound trains  or  blocks.  Extraordinary  delays  caused  by  rips  and  no-bills 
appear  to  be  a  relatively  small  problem. 

Volume  5:  Models  for  Investigating  Rail  Trip  Time  Reliabilittj.  Author: 
Joseph  F.  Folk.  Date:  June  1972.  MIT  Report  No.  R72-40.  Sponsoring 
Agency:   FRA. 

The  unreliability  of  the  trip  time  of  railroad  freight  shipments  is  often 
given  as  the  reason  for  the  railroads'  loss  of  traffic  to  competing  modes  of 
transport.  This  report  investigates  various  operating  pohcies  and  practices 
affecting  reliability  through  the  use  of  two  simulation  models.  A  network 
model  is  developed  which  simulates  the  day-to-day  movement  of  cars  through 
a  portion  of  a  rail  network,  while  another  model  simulates  the  journey  of  a 
single  car  moving  through  a  series  of  yards.  The  objectives  of  these  models 
are  similar;  namely,  to  study  the  network  effects  on  reliability  of  operating 
policies  such  as  a)  holding  outbound  trains  for  more  traffic,  b)  cancelling 
outbound  trains,  c)  altering  scheduled  connection  times  at  yards,  and 
d)  running  shorter,  more  frequent  trains  between  yards.  Major  conclusions 
of  this  report  include  the  result  that  railroad  operating  policies  do  have  a 
substantial  effect  on  car  movement  reliability.  Also,  improvements  in  re- 
liability might  not  necessarily  require  increases  in  operating  costs,  and 
could  lead  to  improvements  in  other  performance  measures  as  well,  such 
as  a  decrease  in  mean  transit  time. 

Volume  6:   Some  Analijses  of  Railroad  Data.  Author:  Joseph  F.  Folk.  Date: 

June  1972.  MIT  Report  No.  R72-41.  Sponsoring  Agency:   FRA. 
This   report  presents    data   from   several   railroads   on   yard,   link,    and   total 
origin-to-destination  performance.   Topics   analyzed  include  train  arrivals  as 
functions   of  train   length   and  the   day  of  the  week,   line  haul  times,   de- 


Economics  of  Plant,   Equipment  and  Operations  397 

parture  times,  receiving  yard  delays,  total  yard  times,  missed  connections, 
and  trip  time  standard  deviations.  Such  data  analysis  is  necessary  to  insure 
a  realistic  choice  of  parameter  xalues  and  modelling  concepts  in  conjunction 
with  the  simulation  models  discussed  in  Volume  5,  Models  for  Investigating, 
Rail  Trip  Time  Reliability.  The  data  and  results  given  in  this  report  can  also 
be   helpful    to   future   work   on   railroad   reliability. 

Volume  7:   A  Brief  Review  of  Various  Network  Models.  Author:   Joseph  F. 

Folk.   Date:   June   1972.  MIT  Report  No.  R72-42.  Sponsoring  Agency: 

FRA. 
In  the  past  decade,  the  railroad  industiy  has  developed  various  types  of 
models  to  investigate  different  operating  problems  and  policies,  as  well  as 
proposed  changes  in  the  physical  plant  of  a  railroad.  This  report  presents 
a  review,  as  opposed  to  an  evaluation  of  a  subset  of  these  models  which 
could  be  called  railroad  network  models.  Two  basic  types  of  network  models 
are  reviewed:  simtdation  models  and  optimization  models.  In  the  network 
simulation  models  re\'iewed,  car  movements  through  a  network  are  simu- 
lated for  a  fixed  set  of  train  schedules  and  route  structures.  Changes  in 
operating  policies  are  tested  by  making  appropriate  changes  in  either  the 
input  data  deck  or  the  internal  logic  of  the  simulation  program.  "Optimal" 
operating  policies  are  foimd  through  trial-and-error  methods.  The  network 
optimization  models  reviewed  optimize  train  schedules  (or  in  one  case,  a 
railroad  network)  for  a  fixed  traffic  demand.  Quantities  one  might  vary  in 
an  optimization  model  include  traffic  levels,  network  configuration,  cost 
indexes,  and  parameters  such  as  train  speeds  and  processing  rates  at  yards. 

Volume  8:  Reliability  in  Railroad  Operations.  Authors:  A.  Scheffer  Lang 
and  Carl  D.  Martland.  Date:  October  1972.  MIT  Report  No.  R72-74. 
Sponsoring  Agency:   FRA. 

As  a  first  step,  the  project  staff  analyzed  yard,  line-haul,  and  trip  time  data 
from  eight  railroads  and  found  that  unreliability  is  evident  in  all  phases  of 
rail  operations.  Yard  delays,  many  of  which  are  caused  by  unreliable  train 
operations,  are  the  greatest  cause  of  trip  time  unreliability.  Changes  in  oper- 
ations, capital  improvements,  and  institutional  changes  can  all  help  improve 
reliability.  Moreover,  capital  investment,  especially  in  improved  mechanical 
reliability  of  equipment,  will  have  a  less  significant  and  immediate  impact 
than  operating  changes  such  as  through-blocked  trains  and  increased  sched- 
ule adherence.  A  dialogue  between  shippers,  railroads,  labor,  and  manage- 
ment is  critical  to  the  success  of  a  program  for  improving  reliability. 

Volume  9:  Reliability  in  Railroad  Operations:  Executive  Summary.  Authors: 
Joseph  M.  Sussman,  Carl  D.  Martland  and  A.  Scheffer  Lang.  Date: 
December  1972.  MIT  Report  No.  R73-4.  Sponsoring  Agency:  FRA. 

As  a  first  step,  the  project  staff  analyzed  yard,  line-haul,  and  trip  time  data 
from  eight  railroads  and  found  that  unreliability  is  evident  in  all  phases  of 
rail  operations.  Yard  delays,  many  of  which  are  caused  by  unreliable  train 
operations,  are  the  greatest  cause  of  trip  time  unreliability.  Changes  in 
operations,  capital  improvements,  and  institutional  changes  can  all  help 
improve  reliability.  Moreover,  capital  investment,  especially  in  improved 
mechanical  reliability  of  equipment,  will  have  a  less  significant  and  imme- 


398       Bulletin  656 — American  Railway  Engineering  Association 

diate  impact  than  operating  changes  such  as  through-blocked  trains  and 
increased  schedule  adherence.  A  dialogue  between  shippers,  railroads,  labor, 
and  management  is  critical  to  the  success  of  a  program  for  improving 
reliability. 

Volume  10:  Improving  Railroad  Reliability:  A  Case  Stttcly  of  the  Southern 
Raihvay.  Author:  Carl  D.  Martland.  Date:  March  1974.  MIT  Report 
No.  R74-28.  Sponsoring  Agency:  FRA. 
This  report  serves  three  major  functions:  it  analyzes  O-D,  yard,  and  line- 
haul  performance  over  a  large  portion  of  the  Southern  system;  it  sum- 
marizes a  set  of  procedures  for  improving  reliabihty  on  any  railroad,  and 
it  describes  in  detail  the  test  program  carried  out  on  the  Southern.  The 
major  product  of  this  research,  this  test  program  demonstrated  that  re- 
liability can  be  improved  in  the  short  run,  that  tliis  need  not  initially  involve 
added  capital  or  operating  expense,  and  that  this  will  also  result  in  lower 
trip  times.  By  changing  train  schedules  and  operating  procedures  for  three 
traffic  flows,  involving  300  cars/day.  Southern  improved  rehability  about 
15%,  reduced  trip  times  by  nearly  a  day,  and  saved  approximately  $25,000/ 
month  in  car  utilization  expense. 

Volume   11:   Improving  Railroad  Reliability:  A  Case  Study  of  the  Southern 
Railway,  Executive  Summary.  Authors:  Joseph  M.  Sussman  and  Carl  D. 
Mardand.    Date:    March    1974.    MIT    Report    No.    R74-29.    Sponsoring 
Agency:   FRA. 
This  report  presents  the  major  results  and  basic  conclusions  of  this  research 
project.    The    major   product    of   the   project   was    the   test   program,    which 
demonstrated   that   reliability   can   be  improved   in   the   short  run,   that  this 
need  not  initially  involve  added  capital  or  operating  expense,  and  that  this 
will  also  result  in  lower  trip  times.  By  changing  train  schedules  and  operat- 
ing procedures   for   three  traffic  Hows   involving  300  cars/day.  Southern  im- 
proved reliability  about  15%,  reduced  trip  times  by  nearly  a  day,  and  saved 
approximately   $25,000/month   in   car  utilization   expense. 

Volume  12:  Procedures  for  Improving  Railroad  Reliability.  Author:  Carl  D. 

Martland.    Date:    March    1974.    MIT    Report    No.    R74-30.    Sponsoring 

Agency:  FRA. 
This  report  defines  an  experimental  procedure  with  which  any  railroad  can 
start  to  improve  reliability.  The  success  of  the  test  program  implemented  by 
the  Southern  Railway  (see  Volume  10)  demonstrates  that  the  procedure 
not  only  works,  but  ofi^ers  potential  operating  and  economic  benefits  to  rail- 
roads that  adopt  it.  In  addition  to  describing  the  basic  procedure,  this  re- 
port discusses  data  processing  capabilities,  alternatives  for  improving  reliabil- 
ity, and  methods  for  evaluating  these  alternatives.  The  report  closes  with 
recommendations  to  the  government  and  to  the  industry  for  improving  rail- 
road reliability. 

Volvune   15:    A   Model  of  Rail/Truck  Competition  in.  the  Intercity  Freight 

Market.  Author:   Brian  C.  Kullman.  Date:  December  1973.  MIT  Report 

No.  R74-35.  Sponsoring  Agency:   FRA. 

This  report  proposes  a  model  based  on  the  logit  function  to  predict  the  rail 

and  truck  market  share  for  specific  city  pairs  and  commodity  groups.  Effort 


Economics  of  Plant,  Equipment  and  Operations 399 

was  devoted  to  the  problem  of  introducing  both  transport  service  variables 
and  shipper's  logistic  variables  into  the  model.  The  model  was  calibrated 
with  data  from  the  1967  Census  of  Transportation  and  from  various  carriers. 
Significant  regressions  were  obtained  from  linear  logit  models  once  the  proper 
variables  were  identified.  Theoretical  monetary  values  of  carriers'  services 
were  compared  to  the  empirical  values  in  the  model,  indicating  that  shippers 
pay  more  for  quality  service  than  predicted;  this  result  may  be  due  to  bias 
in  the  model  introduced  by  use  of  aggregated  and  unreliable  data.  It  is  con- 
cluded that  further  research  using  this  model  form  with  more  disaggregate 
data  could  yield  significant  improvements  in  results  and  provide  valuable 
information  for  public  and  private  transportation  planning. 

Summary 

Quahty  is  not  measurable  in  exact  terms,  certainly  if  the  subject  is  a  service 
and  not  a  product.  For  railroad  freight  service  it  is  a  composite  of  several  elements, 
varying  in  relative  importance  from  case  to  case,  which  individually  are  measurable 
in  terms  of  time  or  of  cars  available  for  loading. 

QuaUty  has  taken  on  new  significance  in  the  railroad  industry  with  the  loss 
of  traffic  to  other  common  carrier  modes  and  private  carriage,  with  not-wholly- 
unrelated  increases  in  railroad  costs. 

Fortunately,  but  with  a  time  lag,  it  has  become  apparent  that  computers  provide 
a  means  of  collecting  and  organizing  the  masses  of  data  with  which  individual 
elements  of  quality  or  the  inputs  to  those  elements  can  be  measured.  With  measure- 
ment, problem  areas  can  be  identified.  The  results  of  a  corrective  change,  or  tests 
of  alternates,  can  be  measured.  Policy  concepts  can  be  simulated  and  their  effective- 
ness measured. 

Applications  of  the  quality  improvement  process  have  been  in  some  cases 
localized,  directed  at  spot  operating  situations,  and  in  other  cases  of  system-wide 
extent,  directed  at  operating  policies  or  at  broad  concepts  of  carrier-customer 
interface   in   operations,   costs   and  pricing. 

Reports  on  the  cost  effectiveness  of  quality  improvement  policies  have  not  been 
frequent,  but  some  of  the  cases  cited  in  this  report  show  that  better  service  has 
reduced  costs.  With  proper  control,  in  other  cases  a  net  gain  may  come  from  the 
revenue  side  through  added  or  retained  traffic.  While  traffic  was  still  at  near-peak 
levels  in  1974,  there  was  evidence  that  improving  car  control  procedures  in  the 
industry  were  bringing  increases  in  car  utilization  with  consequent  reductions  in 
car  shortages  and  lost  traffic. 

Economic  considerations  and  a  strategy  for  survival  dictate  that  the  proper 
level  of  quality  of  service  is  the  highest  level  that  the  railroad  can  provide  at  a 
reasonable  profit  and  which  has  a  perceived  value  which  the  customer  is  willing 
to  pay  for.  Engineering  methods  and  management  controls  are  the  means  by  which 
these  criteria  can  be  brought  into  balance  for  the  greatest  number  of  traffic 
movements. 


I 


Report  of  Committee  2A — Engineering  Education 


B.  M.  Davidson, 
Chairman 

C.  T.    POPMA, 

Vice  Chairman 
T.  G.  ScHULTz,  Secretary 
W.  R.  Catching 
W.  A.  Oliver 
C.  T.  Yahbhough 


C.  D.  Chambers 
R.  M.  Brown 

E.  Y.  Huang 

D.  N.    CORTRIGHT 

J.  F.  Pearce 

V.    J.    ROGGEVEEN 

T.  M.  Adams 

W.    S.  AUTREY 

J.  B.  Babcock  (E) 
J.  A.  Barnes 
R.  H.  Beeder  (E) 
D.  R.  Bergmann 
J.  R.  Blacklock 

D.  M.  Brinker 
A.  M.  Gary 
A.  W.  Cooper 

T.  P.  Cunningham 
J.  F.  Davison 
L.  A.  Durham,  Jr. 
J.  T.  Evans 
J.  Fox 

E.  T.  Franzen 
L.  C.  Gilbert 
W.  W.  Hay 

P.  L.  Heineman 
W.  P.  Houwen,  Jr. 


W.  H.  Huffman 

H.  E.  Hurst 

T.  B.  Hutcheson 

E.  Q.  Johnson 

F.  O.  Johnson 

A.  V.  Johnston 
C.  Johnston 

T.  D.  Kern 

C.  E.  Law 
R.  H.  Lee 

K.   H.  Lenzen 

B.  B.  Lewis  (E) 
R.  H.  Michael 
S.  H.  Raskin 

D.  V.  Sartore 
P.  S.  Settle 
W.  D.  Smoak 

R.   M.   SOBERMAN 

D.  M.  Tate 

G.  H.  Way 

G.  E,  Weller 

H.  M.  Williamson 

D.  L.  Wilson 

B.   J.   WORLEY 

Committee 


(E)   Member  Emeritus. 

Those  whose  names  are  shown  in  boldface,  in  addition  to  the  chairman,  vice  chairman  and 
secretary,   are   the   subcommittee   chairmen. 

To  the  American  Railway  Engineering  Association: 

Your  committee  reports  on   the  following  subjects: 

1.  Recruiting. 
No  report. 

2.  Summer  Employment. 

Progress  report,  presented  as  infomiation page  402 

3.  Student  Cooperative  Programs. 
No  report. 

4.  Student  Affiliates. 
No  report. 

5.  Continuing  Education. 
No  report. 

6.  Speakers. 
No  report. 

7.  Project  Case  Studies. 
No  report. 


401 


402       Bulletin  656 — American  Railway  Engineering  Association 

8.  Exchange  of  Professional  Staifs. 
No  report. 

9.  Research  Resource  Availability. 
No  report. 

The  Committee  on  Engineering  Education, 

Dr.  B.  M.  Davidson,  Chairman. 

Report  on  Assignment  2 

Summer  Employment 

W.  A.  Oliver  (chairman,  subcommittee),  A.  M.  Gary,  A.  W.  Cooper,  J.  F.  Davison, 
E.  T.  Franzen,  a.  V.  Johnston,  D.  V.  Sartore,  D.  L.  Wilson. 

In  accordance  with  its  practice,  established  in  1959,  Committee  24  canvassed 
the  railroads  during  December  1974  concerning  their  1975  summer  employment 
needs  for  engineering  students.  A  brief  but  formal  questionnaire  was  sent  to  the 
chief  engineering  and  maintenance  officers  and  chief  personnel  officers  of  the  rail- 
roads of  the  United  States  and  Canada  requesting  information  about  their  require- 
ments for  the  summer  of  1975. 

Herewith  is  a  summary  of  Subcommittee  2  Summer  Employment  Survey  results 
for  1975.  There  was  a  total  of  41  of  the  questionnaires  that  went  to  some  125 
major  railroads  requesting  information  concerning  their  summer  employment  needs. 
Four  indicated  that  they  wanted  their  offerings  listed  in  the  Subcommittee  2  letter 
that  goes  to  125  engineering  colleges. 

Such  a  poor  return  of  questiormaires  by  the  railroads,  which  return  has  been 
decreasing  for  the  past  several  years,  raised  a  question  concerning  the  value  to  the 
railroads  of  the  annual  summer  employment  program  carried  on  by  Subcommittee  2 
of  Committee  24.  Consequently,  at  the  meeting  of  the  committee  on  March  26, 
1975,  it  was  decided  to  discontinue  the  program  temporarily. 

The  offerings  of  employment  by  the  four  railroads  returning  favorable  ques- 
tionnaires were  tabulated  and  sent  out  to  the  engineering  colleges  following  the 
regular  practice.  This  tabulation  and  accompanying  letter  was  placed  in  the  mail 
on  February  26,  1975. 


Report  of  Committee  33 — Electrical  Energy  Utilization 


R.  U.  Cogswell, 

Chairman 
L.  D.  Tufts, 

Vice  Chairman 
B.  A.  Ross, 

Special  Assistant 


H.  Rappaport 

R,  J.  Berti 

E.  C.  Anderson 

E.  K.  Farhelly 
C.  G.  Nelson 

F.  T.  Snider 

R.  A.  Senffner 

B.  Anderhous 
J.  A.  Angold 
A.  R.  Babker 
T.  B.  Bamford 
R.  F.  Breese 
W.  H.  Brodsky 

C.  A.  Bunker 
N.  P.  Cain 

R.  F.  Carter 
W.  J.  Clarke 
A.  B.  CosTic 
A.  G.  Craig,  Jr. 
L.  L.  Earley 
R.  A.  Falcon 
H.  T.  FoY 
W.  S.  Gordon 
M.  F.  Cowing 


E.  M.  Hastings,  Jr. 
R.  L.  Henderson 

D.  T.  Jones 
H.  C.  Kendall 

E.  W.  Koch 
K.  L.  Lawson 
A.  W.  Lewis 

K.    LOEBL 

R.  W.  McKnight 
H.  S.  March 
M.  D.  Meeker,  Jr. 
K.  S.  Niemond 
A.  G.  Raabe 

R.    P.    RiEFF 

E.  B.  Shew 
J.  J.  Schmidt 
M.  J.  Shearer 
W.  H.  Siemens 
J.  L.  Sinclair 

D.  M.  Twine 
K.  B.  Ullman 

E.  F.  Weitz 


Committee 


Those   whose   names   are   shown   in  boldface,   in   addition  to  the  chairman,   vice  chairman   and 
special    assistant,    are   the    subcommittee    chairmen. 

To  the  American  Railway  Engineering  Association: 

Your   committee  reports  on  the   following  subjects: 

B.  Revision  of  Manual. 

A  determination  has  been  made  on  which  portions  of  the  old  AAR 
Electrical  Manual  should  come  under  this  committee's  responsibility. 
The  technical  content  of  these  sections  are  under  review. 

1.  Electrification  Economics. 

A   complete   revision    to   the    Electrification    Economics   Section   of  the 

Manual  was   submitted   for  adoption   and  was  published  in  Part   1  of 

Bulletin    655,    November-December    1975.    Work    is   now   focusing   on 

techniques    to    reduce    electrification    construction   costs. 

Paper  entitled  "Railroad  Electrification — A  Status  Report"  is  submitted 

as  information page  404 

2.  Electrical  Clearances. 

Report  of  committee  in  regard  to  clearances  under  structures  on  lines 
that  are  or  may  be  electrified,  along  with  drawing  entitled  "Proposed 
Clearance  Specifications  to  Provide  for  Electrification,"  was  submitted 
to  letter  ballot  vote  of  the  Voting  Members  of  the  AAR  Engineering 
Division  and  was  overwhelmingly  adopted,  effective  December  12, 
1975.  Work  has  commenced  on  producing  an  electrified  railroad  profile 
diagram. 


403 


404       Bulletin  656 — American  Railway  Engineering  Association 

3.  Voltage  Standards. 
No  report. 

4.  Catenary/Pantograph  Systems. 
No  report. 

5.  Signal  and  Communications  Protection  in  Electrified  Territory. 
No  report. 

6.  Power  Supply  and  Distribution. 
No  report. 

7.  Contact  Rails. 
No  report. 

8.  Wire  and  Cable. 
No  report. 

9.  Illumination. 
No  report. 

The  Committee  on  Electrical  Energy  Utilization, 

R.  U.  Cogswell,  Chairman. 


Report  on  Assignment  1 

Electrification  Economics 

R.  J.  Berti  (chairman,  subcommittee),  W.  H.  Brodski,  W.  S.  Gordon,  M.  F.  Cowing, 
D.  T.  Jones,  H.  C.  Kendall,  K.  L.  Lawson,  M.  D.  Meeker,  A.  G.  Raahe, 
R.  P.  Reiff,  B.  a.  Ross,  L.  D.  Tufts,  K.  B.  Ullman. 

Your  committee  presents  as  information  the  following  status  report  on  railway 
electrification.  It  was  originally  presented  at  a  Western  Sectional  Meeting  of  the 
AAR  Communication  and  Signal  Section. 

RAILROAD  ELECTRIFICATION— A  STATUS  REPORT 
By  Hugh   C.   Kendall 

Senior   Consultant 

Technical   Marketing 

General    Railway   Signal    Company 

A   Unit  of   General    Signal 

At  a  recent  conference  on  railroad  electrification  sponsored  by  the  Railway 
Systems  and  Management  Association,  Keith  Campbell,  senior  executive  officer  of 
CP  Rail,  observed:  "The  relationship  between  the  American  railroad  industry  and 
electrification  is  the  history  of  a  flirtation  which  has  been  going  on  for  some  70 
years.  There  have  been  cases,  it  is  true,  where  the  flirtation  has  led  to  some  tangible 
results;  but  where  this  has  happened,  the  offspring  have  not  been  able  to  carry  on 
the  line.  The  question  today  is  whether  the  old  lady  is  more  attractive  than  in  her 
youth,  and  if  so,  whether  the  flirtation  should  be  brought  to  an  end  by  a  general 
application  of  matrimony  and  all  that  goes  with  it." 


I 


Electrical   Energy  Utilization 405 

There  are  many  who  believe  that  the  old  lady  is  indeed  more  attractive  today 
than  she  has  ever  been  before.  The  passage  of  time  has  brought  about  many  changes 
in  the  electrification  picture  which  bring  decision  makers  once  again  to  the  con- 
sideration of  railroad  electrification.  All-electric  motive  power  has  continued  to 
improve  as  a  result  of  general  technological  advances  and  of  specific  efforts  in  other 
countries  with  electrified  railroads.  In  addition,  the  trends  in  competing  modes  of 
transportation  show  continued  problems  of  congestion  and  fuel  consumption.  New 
knowledge  and  sensitivity  to  the  depletion  of  natural  and  environmental  resources, 
particularly  fuels  and  air  quality,  also  motivate  a  further  evaluation  of  all-electric 
motive  power  as  an  alternative  to  diesel-electric  operations.  These  developments 
heighten  the  need  to  review  the  assumptions,  data  and  results  of  past  studies  and  to 
evaluate  the  current  possibilities  in  a  comprehensive  and  systematic  fashion. 

In  the  following  paragraphs,  I  will  take  up  a  number  of  questions  which  are 
frequently  asked  about  railroad  electrification. 

(1)  What   is   meant  by  high-voltage  commercial  frequency  electrification? 
The  Association  of  American  Railroads  and  the  American  Railway  Engineering 

Association  have  recommended  25  or  50  kv  at  60  Hz  for  high-voltage  electrification. 
At  the  present  time,  two  captive  coal-hauling  railroads  in  this  country  have  been 
electrified  at  high-voltage  commercial  frequency.  Both  of  these  railroads  represent 
new  trackage  and  went  into  service  as  electrified  operations.  The  Muskingham 
Electric  Railroad  in  southeastern  Ohio  serves  the  Muskingham  River  Plant  of  the 
Ohio  Power  Company.  This  railroad  is  15  miles  long  and  is  electrified  at  25  kv  60 
Hz.  Two  trains  are  involved  in  the  coal-hauling  operation;  however,  only  one  train 
is  permitted  on  the  mainline  at  any  given  time.  On  this  basis,  train  separation  prob- 
lems do  not  exist,  and  the  railroad  operates  without  benefit  of  a  signal  system. 
Provisions  for  automatic  train  operation  have  been  incorporated  in  the  system  using 
intermittent  wayside  devices  to  control  the  speed  of  the  trains. 

The  Black  Mesa  and  Lake  Powell  Railroad  serving  the  Navajo  Electric  Gener- 
ating Station  of  the  Salt  River  project  near  Page,  Arizona,  is  electrified  at  50  kv  60 
Hz.  This  railroad  is  78  miles  long.  Only  one  train  is  involved  in  the  coal-hauling 
operation,  and  the  railroad  operates  without  benefit  of  a  signal  system. 

The  remaining  railroads  in  this  country  which  have  electrified  operations  use 
"special  power"  which  is  derived  from  the  commercial  frequency  utility  power  grid. 
Portions  of  the  Penn  Central,  for  instance,  are  electrified  at  11  kv,  25  Hz.  Conversion 
equipment  is  required  to  supply  the  "special  power"  used  in  these  systems.  The 
cost  of  maintaining  and/or  replacing  conversion  equipment  as  it  wears  out  has 
become  a  major  factor  in  the  cost  of  energy  used  in  these  operations.  The  primary 
reason  for  the  railroads'  using  "special  power"  can  be  traced  to  insunnountable 
technical  problems  in  electric  motive  power  design  at  the  time  these  properties 
were  electrified,  making  it  impractical  to  use  commercial  power  directly  from  the 
utility  power  grid  to  feed  the  catenary. 

(2)  Why  are  railroads  in  this  country  so  far  behind  foreign  railroads  in  their 
conversion  to  electrified  operation? 

The  question  is  largely  one  of  economics.  Railroads  in  this  country  are  private 
corporations  run  for  the  benefit  of  stockholders  interested  in  good  earnings  and  long- 
term  corporate  growth.  American  railroads  in  general,  due  to  government  regulations, 
have  been  unable  to  generate  sufficient  cash  from  railroad  operations  to  take  advan- 
tage of  the  long-term  conservation  of  capital  which  would  be  possible  by  utilizing 


406       Bulletin  656 — American  Railway  Engineering  Association 

all-electric  as  compared  to  diesel-electric  motive  power.  Capital  expenditures  by  the 
railroads  have  been  limited,  by  and  large,  to  those  improvements  which  could  be 
clearly  justified  on  the  basis  of  acceptable  rates  of  return  on  the  capital  invested. 
Wliile  electrification  has  been  shown  to  have  a  positive  rate  of  return  on  the  projected 
investment,  electrification  of  high  density  lines  has  not  been  widely  adopted  by 
American  railroads  thus  far  because  of  more  pressing  capital  requirements. 

Unlike  American  railroads,  foreign  railroads  are  nationalized.  Railroad  improve- 
ments are  financed  by  the  federal  treasury,  with  the  main  purpose  being  to  provide 
the  required  transportation  services  in  the  best  possible  manner,  with  particular 
emphasis  being  placed  on  the  conservation  of  energy  and  the  use  of  indigenous 
sources  of  energy  wherever  possible.  Losses  incurred  by  foreign  railroads  in  providing 
the  overall  transportation  required  run  into  millions  of  dollars,  but  are  offset  by 
direct  federal  subsidies.  On  this  basis,  foreign  countries,  particularly  Europe,  have 
rebuilt  many  of  their  railroads  since  World  War  II  by  converting  directly  from  steam 
motive  power  to  all-electric  motive  power,  bypassing  the  diesel-electric  phase.  The 
quantum  jump  in  efficiency  between  steam  and  all-electric  motive  power  is  only 
slightly  more  tlian  tlie  jump  from  steam  to  diesel-electric  power.  The  abihty  of 
all-electric  motive  power  to  utilize  a  wide  range  of  indigenous  energy  sources  has 
been   an   important  factor  favoring  electrification   of  foreign  railroads. 

(3)  Wliat  has  created  the  rebirth  of  interest  in  U.S.  railroads  toward 
electrification? 

The  transportation  demands  placed  on  U.S.  railroads  by  World  War  II  left  the 
properties  in  need  of  large  capital  expenditures  for  plant  restoration  and  improve- 
ments. The  diesel-electric  locomotive  proved  itself  during  the  war  as  being  a  quantum 
jump  ahead  of  the  steam  locomotive  in  efficiency  and  cost  of  operation.  Electrification 
received  a  minor  rebirth  of  interest  among  the  railroads  immediately  after  the  war 
as  an  alternate  to  diesel-electric  motive  power.  The  large  amount  of  capital  required 
for  the  electrified  fixed  plant,  however,  was  not  available  to  the  railroads.  In  addition, 
the  promotion  of  diesel-electric  locomotives  by  their  manufacturers  was  not  matched 
by  the  manufacturers  of  all-electric  locomotives  or  by  the  electric  utility  industry. 

Following  the  wholesale  conversion  of  railroad  motive  power  from  steam  to 
diesel-electric  after  the  war,  electrification  remained  in  the  background  until  the 
mid-60's,  at  which  time  it  became  apparent  to  railroad  managements  that  diesel- 
electric  motive  power  purchased  in  tlie  early  50's  was  becoming  worn  out  and  would 
shortly  require  replacement.  In  reahty  the  longevity  of  diesel-electric  motive  power 
turned  out  to  be  much  less  than  what  had  originally  been  expected.  The  interest 
in  electrification  at  that  time,  however,  was  short-lived  since  many  railroads  were 
so  heavily  committed  to  keeping  their  diesel-electric  fleet  going  through  a  rebuilding 
program   that   few   managements   could  be   swayed   away   from  short-term   thinking. 

A  major  breakthrough  in  all-electric  locomotive  design  occurred  in  the  mid-60's 
with  the  application  of  thyristors  and  silicon  diodes  for  locomotive  power  conversion 
and  control.  The  dramatic  savings  in  cost  and  freedom  of  maintenance  of  the  new 
solid-state  power  package  as  compared  to  prior  technology  made  headlines  in  the 
motive  power  fraternity. 

By  the  end  of  the  60's  the  subject  of  electrification  could  no  longer  be  ignored 
since  the  second  generation  of  diesel-electric  locomotives  bought  since  the  war  were 
beginning  to  wear  out.  This,  coupled  with  a  promotion  program  on  the  part  of  the 
electric  utility  industries  to  sell  electricity  to  the  railroads,  led  to  the  present  rebirth 
of  interest  in  railroad  electrification.   The  energy  crisis  has  strengthened   the  cause 


Electrical  Energy   Utilization 407 

of  electrification  since  all-electric  motive  power  is  the  only  means  by  which  railroad 
inter-city  freight  can  be  hauled  by  indigenous  fuel  other  than  oil. 

(4)  What    are    the    primary    benefits    of    electrification    to    railroad    operations? 
The   perfonnance   of   an   all-electric   locomotive   is   vastly   superior   to  a   diesel- 

electric  of  the  same  weight,  the  reason  being  the  ability  of  the  all-electric  locomotive 
to  be  operated  for  short  periods  of  time  at  a  horsepower  rating  at  the  rail  which 
greatly  exceeds  that  of  the  largest  diesel-electric  locomoti\es  which  can  be  built. 
Because  of  sophisticated  wheel-slip  control,  the  effective  adhesion  of  an  all-electric 
locomotive  can  be  as  much  as  50^  higher  than  a  diesel-electric.  High  adhesion  per- 
fonnanc-e,  coupled  with  tlie  short-tenn  overload  capabilities  of  all-electric  locomotives, 
has  the  effect  of  substantially  reducing  tlie  number  of  locomotives  required  in  the 
motive  power  fleet. 

All-electric  locomotive  maintenance  has  been  demonstrated  to  be  less  than 
305e  of  that  required  for  a  diesel-electric,  resulting  in  much  greater  availability  of 
all-electric  motive  power.  Finally,  the  life  of  an  all-electric  locomoti\e  is  generally 
considered  to  be  well  in  excess  of  30  years  as  compared  to  the  life  of  a  diesel- 
electric  which  is  between  12  and  15  years.  From  a  capital  conservation  standpoint, 
the   longevity   of  all-electric  moti\e   power  strongly  favors  electrification. 

(5)  What  are  some  of  tlie  disadvantges  of  electrified  operations  as  compared  to 
diesel-electric? 

a.  The  diesel-electric  locomotive  is  an  extremely  versatile  source  of  motive 
power,  capable  of  running  coast  to  coast  o\'er  a  number  of  different  railroads  merely 
by  serx'icing  it  at  terminals.  Substantial  shifts  of  motive  power  from  one  railroad 
to  another  to  meet  seasonal  traffic  demands  is  being  practiced  on  a  number  of  U.S. 
railroads.  A  typical  example  of  this  is  the  shift  in  motive  power  between  the  Union 
Pacific  and  Norfolk  &  Western  whose  seasonal  traffic  peaks  occur  several  months 
out  of  phase.  The  ad\ent  of  electrification  would  not  end  such  practices,  but  would 
limit  the  amount  of  moti\e  power  which  could  be  shifted,  inasmuch  as  an  electric 
locomotixe  fleet  would  need  to  remain  under  a  catenary.  It  can  truthfully  be  said, 
therefore,  that  the  flexibility'  of  the  diesel-electric  locomotive  as  it  is  presently  being 
exploited  by  U.S.  railroads  would  be  difficult  to  match  by  all-electric  motive  power. 

b.  The  fleeting  of  trains  is  a  common  practice  on  many  railroads.  Under  such 
operations  a  number  of  trains  are  dispatched  o\er  a  relatively  short  period  of  time. 
With  diesel-electric  locomotives,  all  that  is  required  to  implement  such  an  operation 
is  a  sufficient  number  of  locomotivs  ser\iced  and  ready  to  go.  Using  all-electric 
motive  power,  however,  fleeting  practices  might  need  to  be  curtailed  on  the  basis 
of  the  high  electric  demand  charges  which  might  be  incurred.  The  electric  bill  is 
usually  made  up  of  three  distinct  parts,  namely:  demand  charge,  energy  charge  and 
special  facihties  charge.  The  demand  charge  frequently  is  based  on  the  highest 
15-  or  30-minute  kw  load  as  seen  by  the  electric  utility  at  a  gi\'en  substation.  The 
demand  charge  frequently  accounts  for  50%  to  70%  of  the  total  electric  bill.  Because 
of  this,  effective  demand  control  becomes  an  important  element  in  minimizing  oper- 
ating costs.  The  train  dispatcher  on  an  electrified  railroad  for  economic  reasons  must 
work  closel>-  with  the  power  dispatcher.  The  duties  of  each  dispatcher  are  clear  and 
well  defined;  however,  they  do  not  necessarily  complement  one  another.  For  instance, 
heavy  movements  of  freight  at  night  might  be  attractive  to  the  power  dispatcher 
because  of  the  availability  of  power  at  off-peak  rates.  Such  operations,  however, 
could  well  be  quite  unattractive  to  the  train  dispatcher. 


408       Bulletin  656 — American  Railway  Engineering  Association 

c.  The  hazards  to  personnel  posed  by  a  catenary  energized  at  25-50  kv  and 
located  a  mere  25  ft  off  the  ground  need  not  be  emphasized.  The  hazards,  of  course, 
are  great.  All  employees  nuist  be  thoroughly  trained  in  proper  safety  measures.  The 
overhead  power  system  poses  additional  problems  in  clearing  wrecks,  but  experience 
has  shown  that  the  catenary  can  usually  be  repaired  before  the  track  is  returned  to 
service. 

d.  The  reliability  of  high-voltage  primary  transmission  systems  is  very  good; 
but  when  a  power  outage  does  occur,  it  could  mean  that  operations  must  be  reduced, 
or  in  the  extreme  case  terminated,  until  power  is  restored. 

(6)  What  is  meant  by  "modern  electrification  technology?" 

Heavy  emphasis  on  electrification  by  foreign  railroads  over  the  past  20  years 
has  led  to  a  number  of  technological  breakthroughs  in  the  design  of  all-electric 
locomotives,  catenary  structures,  substations  and  communication  and  signal  equip- 
ment. Some  of  these  developments  are: 

a.  The  successful  application  of  thyristors  and  silicon  diodes  to  all-electric 
locomotive  power  conversion  and  control  packages  has  made  obsolete 
the  use  of  mercury  arc  rectifiers  and  tap  changing  transformers. 

b.  "Hie  adhesion  performance  of  all-electric  locomotives  has  been  substan- 
tially enhanced  by  the  development  of  highly  sophisticated  wheel-slip 
control  packages  as  an  adjunct  to  the  main  solid-state  conversion  and 
control  packages. 

c.  Due  to  the  lightweight  catenaries  involved  in  high-voltage  electrification, 
low-cost  catenary  structures  have  been  designed  whose  material  and  in- 
stallation costs  are  substantially  less  than  for  lower  voltage  catenary  systems. 

d.  Substantial  advances  have  been  made  in  the  signal  field  through  the  de- 
velopment of  ac-immune  dc  track  appliances  such  as  relays,  signal 
mechanisms  and  switch  machines. 

Foreign  developments  have  been  made  largely  by  commercial  firms  involved 
in  the  supply  of  electrification  material.  Some  government  money  has  been  avail- 
able to  offset  development  expenditures.  Considerable  government  money  has  been 
available  to  government  agencies  engaged  in  electrification  research.  With  the  re- 
newed interest  in  railroad  electrification  in  this  country,  many  U.S.  firms  have 
undertaken  equipment  development  programs  specifically  geared  to  the  electrifica- 
tion needs  of  North  American  railroads,  which  differ  in  many  respects  from  foreign 
railroads. 

(7)  What  changes  would  he  required  to  existing  signal  facilities  to  make  them 
compatible  with  electrification? 

The  proximity  of  a  high-voltage  catenary  to  open-wire  signal  and  communica- 
tion lines  paralleling  the  railroad  would  expose  these  circuits  to  the  effects  of  electro- 
magnetic and  electrostatic  induction.  High  voltages  would  be  induced  into  these 
circuits,  creating  hazards  to  personnel  as  well  as  introducing  the  possibility  of  mal- 
function of  apparatus  which  is  connected  to  these  circuits.  In  addition,  harmonics 
of  the  60-Hz  propulsion  energy  as  well  as  noise  would  be  induced  into  communica- 
tion circuits,  causing  the  signal-to-noise  ratio  to  be  degraded.  Finally,  the  common 
use  of  the  track  for  propulsion  current  return  as  well  as  train  detection  purposes 
poses  special  problems  in  the  track  circuit  area. 

Present  signal  systems  would  require  modification  as  follows: 


Electrical   Energy   Utilization 409 

a.  Double-rail  dc  track  circuits  would  require  replacement  with  either  single- 
rail  dc  track  circuits  using  ac-immune  track  relays  or  with  double-rail  ac 
track  circuits  operating  at  a  frequency  which  is  not  harmonically  related 
to  60  Hz. 

b.  Open-wire  line  circuits  must  be  eliminated  or  placed  in  grounded  shielded 
cable,  preferably  buried  along  the  right-of-way. 

c.  Instrument  housings  and  all  wayside  equipment  must  be  properly 
grounded,  and  cables  interconnecting  wayside  equipment  with  instrument 
housings  must  be  either  shielded  or  kept  within  specified  lengths. 

d.  Protective  devices  must  be  installed  to  protect  personnel  and  equipment 
during  traction  system  fault  conditions. 

e.  Open-wire  signal  power  lines  carried  on  catenary  supports  must  be  high 
voltage  and  suitably  insulated  in  view  of  the  induction  effects  of  the 
catenary. 

f.  Rail  bonding  and  cross  bonding  must  be  adequate. 

g.  Switch  circuit  controllers  must  be  heavy-duty  types. 

h.  Signal  heads  may  have  to  be  relocated  for  proper  sighting  due  to  the 
catenary  supports. 

i.  The  immunity  of  line  relays,  switch  machines  and  signal  heads  used  in 
present  signal  systems  to  th©  effects  of  electromagnetic  and  electrostatic 
induction  at  60  Hz  is  quite  high.  It  is  essential,  however,  that  the  im- 
munity level  of  this  equipment  not  be  exceeded  even  under  traction 
system  fault  conditions.  This  requirement  necessitates  an  examination  of 
all  presently  used  wayside  apparatus  to  ensure  that  adequate  immunity 
levels  exist.  Equipment  which  cannot  measure  up  must  not  be  used. 

(8)  How  many  railroads  are  actively  considering  high-voltage  electrification  at 
the  preseiU  time? 

Ten  railroad  systems  have  electrification  studies  in  progress. 

(9)  What  typical  cost  figures  and  assumptions  have  been  used  in  these  studies? 

(a)  Based  upon  1975  constant  dollars,  the  following  typical  cost  figures  have 
been  used: 

Description  Typical  Figure 

Substations   (50KV)  $12,000-$20,000/Track  Mile" 

Catenary  (50KV)  $65,000-$95,000/Track  Mile* 
Signal  and  Communication  Conversion  $28,000/Track  Mile 

Annual   Catenary   Maintenance  $1,000/Track  Mile 

All-Electric  Locomotives  $125/HP 

Diesel-Electric  Locomotives  $150/HP 

All-Electric  Locomotive  Maintenance  $.22/Unit  Mile 

Diesel-Electric  Locomotive  Maintenance  $.60/Unit  Mile 

Electric  Energy  $.027/KWH 

Diesel  Fuel  $.27/Gal. 

(b)  The  following  assumptions  have  been  made: 

Electric  Energy  Requirements  25  KWH/1000  GTM 

Diesel  Fuel  Requirements  1.9  gal/1000  GTM 


410       Bulletin  656 — American  Railway  Engineering  Association 

All-Electric  Locomotives  Required  3.4-4. 5/Million  GTM" 

Diesel-Electric   Locomotives   Required  6.8/Million  GTM 

All-Electric  Locomotive  Adhesion  28% 

Diesel-Electric  Locomotive  Adhesion  18% 

All-Electric  Locomotive  Life  30  Years 

Diesel-Electric  Locomotive  Life  15  Years 

Annual  Interest  Rate  8.5% 

Annual  Traffic  Growth  Rate  3% 

Annual  Inflation  Rate  5% 

Annual  Electric  Energy  Inflation  Rate  5% 

Annual  Diesel  Fuel  Inflation  Rate  5% 

Electrification  Cost  Payback  Period  12  Years 

Electrification  Study  2,000  Track  Miles 

*  Dependent  upon  terrain. 

(10)  With  shortages  of  electricity  and  "brown-outs"  in  certain  sections  of  the 
country,  will  there  be  enough  power  available  to  enable  railroads  to  elec- 
trify their  operations? 

If  the  proposed  20,000  route  miles  of  high-density  mainlines  in  this  country 
were  to  be  electrified  by  1990,  the  electric  energy  required  would  be  less  than  3% 
of  the  national  supply.  New  power-plant  construction,  principally  nuclear  plants, 
has  been  seriously  curtailed  in  recent  years  due  to  environmental  considerations. 
The  long-range  plans  of  the  electric  utility  industry,  however,  are  adequate  to 
cover  the  railroad  power  requirements  in  the  event  of  future  wide-scale  electrifica- 
tion. Since  considerable  electrification  is  planned  to  take  place  in  areas  which  are 
remote  from  present  generating  facilities,  it  is  expected  that  new  generating  facili- 
ties would  be  built  specifically  to  serve  these  areas  in  the  event  of  electrification. 
The  present  limited  shortage  of  electric  energy  is  not  expected  to  be  permanent  if 
the  electric  utility  industry  is  permitted  to  expand  in  accordance  with  present  plans. 

(11)  What  is  the  energy  effectiveness  of  all-electric  versus  diesel-electric  mo- 
tive power? 

The  movement  of  one  ton  of  freight  a  distance  of  one  mile  on  level  track  re- 
quires approximately  700  Btu's  of  energy.  It  makes  little  diff^erence  whether  the 
freight  is  moved  by  all-electric  or  diesel-electric  motive  power,  from  an  energy- 
effectiveness  standpoint,  since  there  are  inefficiencies  associated  with  each  form  of 
motive  power.  It  has  been  stated  that  one  ton  of  freight  can  be  moved  by  rail  on 
level  track  an  equal  distance,  whether  a  given  amount  of  fuel  oil  is  consumed  by 
a  diesel-electric  locomotive  or  consumed  in  a  boiler  at  a  stationary  electric  gen- 
erating plant  and  utilized  by  an  all-electric-locomotive. 

(12)  What  about  the  energy  cost  of  using  all-electric  versus  diesel-electric  mo- 
tive power? 

A  given  amount  of  energy  has  a  price  tag  which  is  a  function  of  the  form  in 
which  the  energy  is  purchased.  The  price  of  diesel  fuel,  for  instance,  reflects  the 
costs  of  fuel  storage  and  transportation  to  where  it  is  needed,  over  and  above  the 
basic  cost  of  the  oil  itself.  The  cost  of  electric  energy  reflects  the  costs  of  storage 
and  transportation  of  the  coal  used  to  produce  it,  the  inefficiencies  of  stationary 
generating  plants,  and  the  costs  of  the  distribution  system,  including  catenary 
required  to  deliver  electric  energy  to  its  point  of  use  on  a  railroad.  Whereas  elec- 
tric  energy  over  the  years  has  been  slowly  climbing  in  price,   the  cost  of  diesel 


Electrical   Energy   Utilization 411 

fuel  has  been  rising  rapidly.  Taking  all  factors  into  consideration,  the  energy  costs 
of  diesel  vs.  electric  operations  on  railroads  would  be  approximately  the  same  if 
diesel  fuel  cost  27  cents  a  gallon,  electricity  cost  2  cents  per  kwh.  For  many  years, 
diesel  fuel  could  be  purchased  by  the  railroads  for  approximately  14  cents  a  gal- 
lon, with  electric  rates  at  approximately  1.2  cents  per  kwh.  On  this  basis,  electric 
operations  were  at  a  disadvantage  as  compared  to  diesel  operations  from  an  energy- 
cost  standpoint.  During  this  past  year,  however,  the  costs  of  diesel  fuel  have  sky- 
rocketed in  comparison  to  the  present  cost  of  electricity.  Under  these  conditions, 
electrification  has  more  to  offer. 

(13)  What  timetable  is  foreseen  for  the  electrification  of  the  major  Jugh-density 
mainlines  in  this  country? 

There  is  a  wide  difference  of  opinion  as  to  the  timetable  for  railroad  electrifi- 
cation in  this  country';  however,  it  is  generally  felt  that  major  electrification  projects 
will  not  take  place  much  before  the  end  of  this  decade,  when  sufficient  time  will 
ha\e  elapsed  to  iron  out  the  raihoad  crisis  in  the  northeast,  enabling  the  Federal 
Government  to  implement  its  position  with  regard  to  aid  to  railroads  in  other 
parts  of  the  coimtry.  Prior  to  the  80's,  however,  a  number  of  small  electrification 
projects  should  be  in  e\idence.  These  projects  will,  for  the  most  part,  be  captive 
railroad  operations  involved  in  hauling  coal  and  ore. 

(14)  What  is  the  position  of  the  Federal  Government  toward  railroad  electrifi- 
cation? 

The  Federal  Railroad  Administration  stongly  favors  the  electrification  of  high- 
density  mainlines  in  this  country  as  a  vital  step  in  preserving  and  strengthening 
this  country's  railroads.  Legislation  which  is  pending  in  Congress  could  be  influ- 
enced by  the  position  of  the  FRA  in  this  regard.  The  FRA  has  also  recommended 
that  funds  be  made  available  to  the  Department  of  Transportation  for  research  on 
electrification  and  the  implementation  of  test  trackage  for  evaluation  purposes. 
The  energy  crisis  has  heightened  government  interest  toward  railroad  electrification 
as  one  obvious  means  to  conserve  our  dwindling  supplies  of  indigenous  oil.  Rail- 
road electrification  is  the  only  means  by  which  inter-city  freight  could  be  moved 
by  the  railroads  using  coal  or  nuclear  energy  soiu^ces. 

(15)  From   an   economic  standpoint,   how    much   mainline  can  he  justified  for 
electrification? 

The  recently  completed  study  by  the  Pan-Technology  Consulting  Corporation 
for  the  Federal  Railroad  Administration  based  its  conclusions  on  the  economic 
climate  prior  to  1973.  On  this  basis  electrified  operation  of  mainlines  in  this  coun- 
try appeared  to  be  warranted  if  annual  traffic  densities  were  above  39  million 
gross  ton  miles  per  mile  of  track.  Under  this  criterion,  approximately  15,000  miles 
of  mainline  were  considered  economically  justified.  The  report  further  concluded 
that  based  on  the  projected  growth  of  traffic  by  the  year  2000  that  30,000  miles 
of  mainline  probably  could  justify  electrification.  At  that  time  electrified  mainhnes 
were  projected  to  be  carrying  approximately  805?  of  the  annual  traffic  tonnage. 

(16)  What   is  the  single  most  important  reason  why  railroads  in  this  country 
are  actively   looking  toward  electrification  at  this  time? 

Worldwide  experience  with  electrification  has  pointed  out  that  under  practi- 
cally all  conditions,  electric  motive  power  off^ers  by  far  the  most  efficient  and  eco- 
nomical means  available  for  the  movement  of  rail  traffic. 


412       Bulletin  656- 

-American 

Railway  Engineering  Association 

Foreign  Railroad  Electrification 

Route  Miles 

Percent  of 

Cotiutnj 

Electrified 

Total  Route  Miles 

Russia 

22,780 

27 

France 

5,520 

24 

West  Germany 

5,160 

28 

Italy 

4,950 

48 

Sweden 

4,350 

61 

Japan 

3,860 

29 

Poland 

2,180 

15 

England 

2,070 

17 

Spain 

1,970 

23 

Switzerland 

1,790 

99 

Norway 

1,420 

54 

Austria 

1,320 

39 

Czechoslovakia 

1,210 

10 

Netherlands 

1,010 

52 

Belgium 

700 

24 

Portugal 

470 

27 

U.S.  Railroad  Electrification 

Route 

Propulsion 

Railroad 

Location 

Miles 

Power 

Illinois   Central   Gulf 

Chicago-Richton,  111. 

37    1,500  Volts  DC 

Chicago  South  Shore  & 

South  Bend 

Chicago-S 

outh    Bend,    Ind. 

76    1,500  Volts  DC 

Erie  Lackawanna 

Hoboken-Dover,  N.J. 

80    3,000  Volts  DC 

Penn  Central 

New  Haven-Washington,  D.C. 

762    11 

KV,   25  Hz 

AC 

Philadelph 

ia-Harrisburg,  Pa. 

Reading 

Philadelph 

ia.  Pa. 

88    12 

KV,   25  Hz 

AC 

Muskingum   Electric 

Zanesville, 

Ohio 

15    25 

KV,   60  Hz 

AC 

Black  Mesa  &  Lake 

Powell 

Page,  Arizona 

78    50 

KV,   60  Hz 

AC 

TOTAL 


1136 


Electrical  Energy  Utilization 

413 

U.S.  Rapid  Transit  Systems 

Route 

Propulsion 

System 

Location 

Miles 

Power 

CTA 

Chicago,  111. 

89 

600  Volts  DC 

Long  Island 

New  York-Mineola,  N.Y. 

150 

600  Volts  DC 

MBTA 

Boston,  Mass. 

65 

600  Volts  DC 

NYCTA 

New  York,  N.Y. 

251 

600  Volts  DC 

Penn  Central 

New  York-Harmon-White  Plains 

69 

600  Volts  DC 

Philadelphia 

Transportation   Co. 

Philadelphia,  Pa. 

27 

600  Volts  DC 

PATH 

New  York-Newark,    N.J. 

14 

600  Volts  DC 

WMATA 

Washington,  D.C. 
(Under  Construction) 

97 

600  Volts  DC 

PATCO 

Philadelphia-Lindenwold,  N.J. 

15 

650  Volts  DC 

CTS 

Cleveland,  Ohio 

20 

650  Volts  DC 

BART 

San  Francisco,  Calif. 

75 

1,000  Volts  DC 

TOTAL 


872 


Advertisement 


-J  11-1 


WELD  60-80 

STRAIGHT  OR  COMPROMISE 

*   JOINTS 
DAILY! 


THERMIT 


SELF-PREHEAT 
RAIL  WELDING 


THE  MODERN  IN-TRACK  METHOD 

•  AUTOMATIC,   ERROR-FREE  PRE-HEATING  AND 
TAPPING  OF  WELD  METALS 

•  EASY,  COLD  REMOVAL  OF  RISERS 

•  MINIMUM  GRINDING 

•  NO  EQUIPMENT  TO  PURCHASE  OR  LEASE 
COMPLETE  THERMIT  RAIL  WELDING  DE- 
TAILS PLUS  JOB-SITE  DEMONSTRATIONS. 

WRITE  OR  CALL 


US.  THERMIT  INC 


Lakehurst,  New  Jersey  08733   •  (201)657-5781/ 


414-2 


Advertisement 


Portec's  On 
the  Move. 

4  Ways  We're 
Aggressively 
Supporting 
Your  Progress. 

Portec's  Transportation  Products 
Group  has  been  streamlined  and 
expanded.  To  provide  you  with 
better  service  for  your  track  and 
transportation  needs.  And  to 
develop  new  products  for  the 
challenging  years  ahead.  Listed 
here  are  some  of  the  Portec  products 
that  have  gained  world-wide 
acceptance.  Watch  for  news  of 
further  developments  —  the  kind  of 
innovations  you  expect  from  a  leader 
like  Portec.  / 

Paragon  Division 

Auto  Racks  ^ 

New  Fully  Enclosed  Multi-Levels 

with  Tri-Fold  Doors 
Bi-Level  Racks 
Tri-Level  Racks 
End  Door  Enclosure  — 

Multi-Level  Racks 

Other  Equipment 

Frame  Cars 

Cable  Reel  Cars 

Ingot  Mold  Cars 

Special  Equipment  Components 


Railway  Products  Division 

Rail  Anchors 
Improved  Fair® 
XL-1  Fair® 

Insulated  Rail  Joints 

Poly-Insulated 

Portec-Bond 

Continuous 

Armored  Continuous 

Components  for  Insulated  Rail  Joints 

Poly  Plates 

Double-Filament-Wound  Bushings 

Blue  Ribbon  Nylon  Epoxy  End  Posts 

Non-Insulated  Rail  Joints 
Portec-Bond 
Headfree  Toeless 
Headfree  Flanged 
Compromise 

Rail  Joint  Renewal  Insulation  Kits 
Mark  II  -  polymer  insulation 
Mark  III  -  polymer  insulation 

Rail  and  Flange  Lubricators 
Single  Rail 
Double  Rail 
Four  Bar  Type 

Rail  Joint  Heater 
Portable  Model  75  -  for  bonding 
joints 

Ties 

Wood  Ties 

DowMac  Concrete  Ties 

New  Products  in  1976 

Curv-Bloc 

Reinforcing  Strap  for  CWR 


Advertisement 


414-3 


RMC  Division 

Track  Machines 

Anchor  Adjusting  Machine 

AnchorMaster 

Auto-Spiker 

Ballast  Distributor  — 

Distributor/ Cleaner 
BoltMaster 
Bridge  Tool  Machine 
Brush  Cutter 
Clip  Tightener 
Compressor  Cart 
LineMaster 

Rail  and  Joint  Straightener 
Rail  Saw-Drill  Combination 
SpikeMaster 
Spiker-Spacer 
TieMaster 
Tie  Plate  Broom 
Tie  Unloader 
Track  Broom 
Tampers 

Hydramatic-16 

Hydraulic-16 

Multi-Purpose  8 

Hydraulic  8 

Jack 

Switch  Spot 

Spot  Switch 

Snow  Blower 

Typhoons 

Hurricane  Jets 

Rail  Laying  Equipment 

Dual  Welded  Rail  Laying  Equipment 

Gauging  Machine 

Plug  Setter 

Rail  End  Hardening  Machine 

Rail  Oiler 

Rail-Laying  Auto-Spiker 

Rail  Anchor  Cart 

Scrap  Loader 

Spike  Distributor  Cart 

Tie  Plate  Gauger 


Spot  Systems 

Car  and  Locomotive  Pullers 

Jacks,  Jib  Cranes 

Retarders 

Shipping  Systems  Division 

Rail  Car  Tie-Down  Systems  and 
Components  for: 

Vehicles 

Automobiles,  Trucks,  Other  Vehicles 

Tractors,  Farm  Implements 

Heavy  Construction  Equipment 

Materials 

Automobile  and  Truck  Frames 

Lumber 

Cable  Reels 

Steel,  Steel  Plate,  Steel  Coil, 
Aluminum  Ingot 

Containers 

Fixed  and  Retractable  Locks 

Special  Components  for  Freight  Cars 

Bridge  Plates 

Hardened  Brake  Pins 

Center  Plates 

Other  Equipment 

Special  Tie  Down  Systems  for  Flat 
Bed  Trailers  —  fixed  and 
retractable  twist  lock  assemblies 
for  trailers  and  container  chassis 


PORTEG 


inc. 


Transportation  Products 

;MM)  W  indsiir  Drivi!,  Oak  Hniok.  Illinois  60521 
Tolophom- (:n2)  :i25-(i:<00 


414-4 


Advertisement 


RAILWAY      MOTOR      CARS 
AND      WORK      EQUIPMENT 


INSPECTION  MOTOR  CARS 
SECTION  MOTOR  CARS 
GANG  MOTOR  CARS 
PUSH  CARS  AND  TRAILERS 
HY-RAIL  EQUIPMENT 
BALLAST  MAINTENANCE  CARS 
WEED  MOWERS 
TOW  TRACTORS 
RAIL  GRINDERS 
DERRICK  CARS 
HYDRAULIC  POWER  TOOLS 
TRACK  LINERS 


TRACK  LINING  LIGHT 

SPIKE  DRIVERS 

TIE  REMOVERS 

TIE  HANDLERS 

RAIL  LIFTERS 

TIE  SHEARS 

TIE  BED  SCARIFIERS 

SPIKE  PULLERS 

TIE  PLUG  INSERTERS 

OIL  SPRAYERS 

TIE  SPRAYERS 

TIE  INSERTERS 


(PeAfnmance 


THESE  UNITS  ARE  ACTUATED  EITHER  COMPLETELY 
OR  PARTIALLY  BY  HYDRAULIC  POWER 


FAIRMONT  RAILWAY  MOTORS,  INC.,  FAIRMONT,  MINNESOTA  56031 


Advertisement 


414-^ 


Repair  at  10% 

of  replacement 

costs 

The  structural  cracks  in  this 
bridge  are  being  "welded"  with 
epoxy.  Osmose  epoxy  injec- 
tion restores  structural  integrity 


without  service  interruptions  at 
a  fraction  of  replacement  cost. 


The  proven  OSMOSE  method: 

•  ANALYSIS  •  CLEANING 

•  SEALING  •  CONTROLLED 
PRESSURE  INJECTION 

•  DETAILED  INSPECTION 
REPORTS 


OSMOSE  RAILROAD  DIVISION 


4915  Monona  Drive 
Madison,  Wis.   53716 


414-6 


Advertisement 


CABLE 


For  dependability  in  actual  use,  no  other  cable 
matches  Kerite.  We  believe  you  will  be  im- 
pressed by  the  evidence. 


THE   KERITE  COMPANY 

PRINCIPAL  OFFICES:  Boston;  Chicago;  New 
York;  Philadelphia;  San  Francisco;  and 
Seymour,  Connecticut  •  Sales  Representa- 
tion throughout  the  United  States.  A  sub- 
sidiary of  Harvey  Hubbell  Incorporated. 

RITE  insulation  that  makes  the  difference 


Advertisement 


414-7 


RTW  PORTABLE 
RAIL  GRINDERS... 


A  model  for  every  requirement. 

With  over  65  years  of  grinder  experience,  RTW  has 
developed  the  most  complete  line  of  versatile,  portable 
grinders  available  to  the  industry.  Whatever  your  need, 
there's  a  RTW  model  especially  designed  for  the  job. 

•  E-72  (shown  above),  a  flex-shaft  power  plant  with  a  variety  of  attachments 
for  multipurpose  use. 

•  E-1  (shown  below),  a  lightweight  flex-shaft  grinder  available  with  straight 
and  cup-wheel  hand  piece. 

•  P-6-L,  for  high-speed  precision  grinding  of  frogs  and  rail  joints. 

•  P-16  DSP.,  a  heavy  duty  unit  designed 
for  removing  overflow  metal  from  all 
types  stock  rails  and  switch  points. 

•  JG-970,  dual  head,  cross  grinder  for  high- 
production  rail  slotting. 

•  X-60,  a  single  head  cross  grinder. 

•  P-45-A,  cup-wheel  surface  grinder  for 
reforming  welded  rail  ends. 

Write  for  detailed  specification  sheets  on 
these  and  other  high-performance 
equipment  by  RTW. 


other  RTW  Maintenance  Equipment 

Grinders  (many  additional  models  not  listed  above) 
Tie  Handlers  •  Anchor  Cnbbers 


MEMBER 

RPI 


(rtw) 

RAILWAY  TRACK-WORK  CO.  2560  East  Tioga  St  .  Philadelphia.  Pa   19134 

Agents;  Chicago— ESCO  Equipment  Service  Co  •  Houston  — Service  Equipments  Supply  Company 

Los  Angeles— Si mklns  Company  •  Louisville— T  F  Going  •  St  Louis— R  E  Bell  Co 

S  Plainfield.  N  J  —Eastern  Railroad  Equipment  Corp  •  Canada:  Montreal— Woodings-Canada  Ltd. 

Export:  American  Equipment  Co  ,  Boca  Raton.  Florida 


414-8 


Advertisement 


The  Allegheny  Insulated  Rail  Joint- 

Designed  to  withstand  the  heaviest  traffic 
in  welded  rail 


This  modern  joint  cements  rail  ends  in  position  end  thereafter 
resists  all  forces  imposed  by  temperature  and  simultaneous  forces 
of  live  loads  to  move  them. 

This  joint  makes  welded  rail  truly  continuous.  It  promises  you  years 
of  service  without  maintenance  costs.  It  reduces  rail  and  wheel  batter 
to  a  previously  unknown  minimum.  It  employs  the  safety  of  steel  splice 
bars.  It  can  be  assembled  in  the  shop  or  field.  It  has  been  tested  in 
service  and  AAR  laboratories.  It  saves  you  lots  of  money. 

Allegheny  Drop  Forge  Company 

Subsidiary  of  Tasa  Corporafion 
2707  Preble  Avenue  •  Pittsburgh,  Pa.  15233 


Advertisement 


414-9 


HoH  one  man  can  do 
the  Hork  of  four.  Safely. 


With  Safetran's  E-Z  Gauger,  one  man  can 
check  track  gauge,  realign  off -gauge  track,  and 
hold  the  rails  at  correct  gauge  while  respiking. 

Alone. 

On  curves,  bridges,  and  scales.  At  switch- 
points,  frogs,  and  high-speed  turnouts.  On  the 
mainline.  In  welded  rail  areas.  Fully  insulated 
for  use  in  signal  territory. 

Safely,  accurately,  and  easily. 

The  key  is  the  E-Z  Gauger,  a  rather 
remarkable  little  piece  of  equipment.  Only 
42  pounds  and  69-inches  long,  the  E-Z 
Gauger  is  ruggedly  constructed  of  all 
steel,  and  precisely  engineered  for 
accuracy  and  ease  of  operation. 

Want  to  know  more?  Contact  us. 


Safetran  Systems  Corporation 

7721  National  Turnpike  •  Louisville,  KY  4021 4    •     (502)361-1691 


Advertisement 


LORAM 

Modern  Maintenance 
of  Way  Equipment 

with  an  established 
track  record . . . 


WINCH  CART 


. . .  designea 
to  do  the  job 
easier,  quicker 
and  at  less  cost 
—  with  your 

men  or 

ours! 


AUTOTRACK  WITH  PLOW  AND  SLED 


THE  ANSWER  TO  YOUR  TRACK  REHABILITATION  PROGRAM 


JlPf 

«AMW«r        J 

miiommg»»    I 


LORAM  RAILWAY  MAINTENANCE  EQUIPMENT  FOR: 

•  Shoulder  Ballast  Cleaning  •  Raising  Track  •  Resurfacing  • 
Reballasting  •  Replacing  Ties  •  Undercutting  •  Ballast  Cleaning 

•  Rail  Grinding  Single  or  Multiple  track— Mainline  or  Yard  tracks 

CONTRACT,  SALE  or  LEASE 


FOR  FULL  DETAILS, 
OR  SHOWING  OF 
OPERATING  FILMS. 
WRITE  OR  CALL  TODAY 


MAINTENANCE  OF  WAY,  INC. 

3900  Arrowhead  Drive  •  Hamel,  MN  55340  U.S.A. 
PHONE:  (612)  47B-60U  •  TELEX:  29-0391;  Cable,  LORAM 


Advertisement 


414-11 


Solid 


Design  and  construction  features  of  the 
hook,  throat  and  pad  work  together  to 
provide  real  gripping  force  with 
enormous  reserve  power 


Positive  anti-overdrive  stop. 


Generous  hook  and  throat 
base  pads  assure  positive 
seating      firm  grip. 


Stamped  code  identifies 
rail  size  application. 


ChaimeloG 


Channeloc  presents  a  deep,  full  length  profile  to  the  tie  for  maximum 
tie-bearing  integrity.  Its  large,  smooth  bearing  surface  enables 
Channeloc  to  evenly  transfer  the  thrust  of  rail  creep  to  the  tie 
witfTOut  affecting  service  life  of  the  tie,  plate  or  spike. 

Channeloc  is  easily  applied,  removed  and  re-applied. 


t  NombefS3  102,690-3  1l8.-327-3tS9.19e 


IRUE  lEMPER. 

An  Allegheny  Ludlum  Industries  Company 


414-12  Advertisement 


TCLEWELD 


INC- 


MEMB  Bft 


Rail  Maintenance  Service 

Rail  End  Welding 

Rail  End  Hardening  DOK 

CWR  Joint  Normalizing  lf"f' 

Frog  and  Switch  Welding  """^^ 

Rail  Maintenance  Equipment 

Custom  Manufacturing  and  Fabrication 

Joint  Bar  Shims 

Rail  Anchor  Shims 

Rail  End  and  Frog  and  Switch 

Welding  and  Grinding  Machines 
CWR  Heating  and  Cooling  Equipment 
Rail  Flaw  Testing  Equipment 
Telebrineller  Portable  Hardness  Tester 


tnfra-R«d   Heatar  for   Curing    Adhetiv*  Bonded  Rail  Joints 


TELEWELD  INC.,  416  NORTH  PARK  ST.,  STREATOR,  ILL.  61364 

Write  for  details  of  the  TELEWELD  process  for  restoring  rail  ends. 


REGIONAL  MEETING 

OCTOBER  30,   1975 

HOTEL   VANCOUVER,   VANCOUVER,   B.C.,   CANADA 


Luncheon  Address 

By  A.  F.  Joplin 

Vice    President    Operation    and    Maintenance 
CP   Rail 

This  is  the  time  of  the  year  when  most  of  us  who  are  involved  in  maintenance 
of  way  and  structures  on  our  various  properties  are  looking  back  at  what  we  under- 
took to  do  during  the  summer  months  and  are  looking  forward  to  what  we  propose 
to  do  in  the  coming  year.  In  other  words,  this  is  budget  preparation  time.  It  is  also 
a  time  when  all  of  us  have  to  give  some  thought  to  just  exactly  where  we  have 
been,   where  we  might  be   going. 

I  am  sure  by  now  you  are  more  than  tired  of  hearing  about  transportation 
problems.  In  both  Canada  and  the  United  States,  there  is  no  lack  of  "solutions"  to 
the  perceived  problems  of  transportation.  In  Canada  and  the  United  States  many 
are  certain  that  the  only  true  way  to  handle  any  problem  is  to  nationalize  everything 
in  sight  or  if  you  don't  nationalize  it,  subsidize  it.  Many  see  our  economy  as  a  horn 
of  plenty  without  depth  from  which  pours  forth  an  endless  stream  of  goodies,  simply 
because  they  say  so.  Everyone  knows  how  to  run  a  railroad!  If  you  haven't  got  any 
ideas   and  haven't  expressed  them,   then  you  are  in  a  minority — everyone  else  has. 

Where  is  the  engineer  in  all  this?  Mostly  he  is  silent,  just  busy  trying  to  be  part 
of  the  solution  rather  than  part  of  the  problem.  As  a  result,  his  advice  and  counsel 
for  the  most  part  are  just  not  heard. 

It  seems  to  me  that  in  many  of  the  significant  undertakings,  in  both  our  coun- 
tries, we  are  not  paying  much  heed  to  die  lessons  to  be  learned  in  the  development 
of  our  economy.  We  seem  to  be  ignoring  the  large  base  of  practical  common  sense 
developed  in  our  railroad  technology  in  the  last  150  years. 

I  am  sure  many  of  you  read  the  August  issue  of  Fortune,  in  which  the  debacle 
of  BART  was  detailed.  Now  you  and  I  know  that  sooner  or  later  the  BART  system 
will  be  put  into  acceptable  running  order.  But  at  what  cost?  Here  is  a  case  where 
practical  down-to-earth  philosophy  was  deserted.  Lessons  learned  elsewhere  in  our 
industry  were  ignored.  Any  new  system  as  complex  as  BART  is  bound  to  have  trou- 
bles— these  are  to  be  expected — they  certainly  should  be  planned  for.  The  stunning 
fact  that  escaped  the  planners  was  the  very  simple  maxim — which  all  practicing 
engineers  are  familiar  with — that  if  more  than  10%  of  project  is  new  technology, 
it  is  going  to  have  serious  problems  in  working  out  the  differences  between  the 
drawing  board  and  the  real  live  practical  world  of  meeting  the  day-to-day  require- 
ments effectively  and  on  time. 

A  very  amateurish  approach.  I  chose  BART  because  of  its  recent  emergence, 
but  there  are  many  other  areas  where  tiie  same  results  can  be  anticipated.  It  seems 

415 
Bui.  656 


416        Bulletin  656 — American  Railway  Engineering  Association  

to  me  that  a  knowledge  of  Murphy's  Law,  which  all  engineers  learn  early  in 
their  career,  would  have  prevented  some  of  these  fiascos. 

In  both  our  countries  we  have  large,  uninformed  groups,  extremely  critical  of 
railroads,  who  want  to  take  over  our  rights-of-way  and  fill  them  with  passenger 
trains — all  of  them  travelling  at  120  mph.  They  overlook  the  most  important  job  we 
do — carrying  our  nation's  commerce.  Just  to  put  this  in  perspective:  last  year  in 
the  United  States  some  200,000  route  miles  of  freight  railroads  grossed  $8.5  billion 
of  freight  revenue;  in  the  same  year  Amtrak  on  23,941  miles  of  operating  route  miles 
grossed  $256.9  million. 

In  Canada,  Canadian  National  and  CP  Rail  operated  24,000  route  miles  in 
freight  service  for  a  gross  of  $2.0  billion  and  16,000  route  miles  of  passenger  service 
for  a  gross  revenue  of  $211  million.  You  will  note  I  said  "gross  revenue" — in  both 
of  our  countries  passenger  services  require  a  considerable  infusion  of  outside  money 
to  keep  them  alive.  Included  in  the  gross  revenue  of  passenger  services  mentioned 
above  ($211  million),  are  Government  payments  amounting  to  some  $113  million. 
In  the  Canadian  Government's  recent  paper  on  Transportation  in  Canada,  it  was 
pointed  out  that  it  would  have  been  cheaper  in  many  cases  to  have  purchased  bus 
or  air  tickets  for  the  train  travellers  rather  than  keep  the  rail  passenger  services 
running. 

There  are  many  who  will  say  both  the  railways  and  the  public  generally  have 
their  priorities  all  wrong.  In  seeking  to  find  what  services  the  public  will  pay  for 
and  what  services  they  reject  by  not  using  and  paying  for  them,  we  are  missing 
the  big  picture  of  the  public  good.  They  say  the  only  answer  is  to  nationalize  the 
services  and  in  some  mysterious  way  this  will  produce  savings  and  improvements 
in  service.  They  naively  ignore  the  lessons  that  can  be  learned  simply  by  observation 
of  the  results  in  those  nations  that  have  experienced  the  "benefits"  of  nationalization. 

Railroading  in  Canada  and  the  United  States  is  facing  serious  problems.  Most 
of  these  problems  arise  from  the  shackles  that  well  meaning  but  misguided  govern- 
ment agencies  apply.  The  justification  for  this  interference,  advocated  by  the  amateur 
meddlers,  is  that  it  is  supposed  to  result  in  more  "equitable"  rates — a  more  "respon- 
sive" transportation  system — claiming  that  competition  can  lead  to  inefficiency  and 
higher  costs — yet  at  the  same  time  holding  that  railways  do  not  have  enough  compe- 
tition and  so  must  be  regulated  because  the  marketplace  cannot  operate  freely. 

I  sometimes  get  the  impression  that  we  have  to  recognize  the  presence  of  a 
new  development  which  might  be  called  the  "bureaucratic  empire-building  syn- 
drome." Its  appeal  is  subtle  and,  in  my  view,  Canadians  and  Americans  must  be  alert 
to  avoid  the  pitfalls  and  costs  inherent  in  this  trend. 

It  works  this  way:  A  public  servant  says  that  "the  public  wants  this  or  that," 
or  "there  is  a  great  need  to  protect  the  public  from  this."  In  almost  every  case  what 
is  prescribed  as  the  remedy  is  a  larger  government  role  in  our  business  economy. 
It  will  be  axiomatic,  of  course,  that  a  whole  new  apparatus  of  government  will  have 
to  be  set  up  to  achieve  the  remedy.  Whether  it  be  transport,  or  oil,  or  dairy  farming, 
or  uranium  mining,  or  whatever,  the  theme  is  the  same — the  government  must  do 
something  because  the  people  want  it.  But  do  they?  Do  the  great  majority  of  the 
free  souls  who  live  on  the  North  American  continent  really  believe  a  government- 
operated  economy  would  meet  their  needs  better?  Are  they  really  ready  to  surrender 
their  private  initiatives  to  the  politically-oriented  activities  of  the  bureaucratic 
empire  builders?  I  think  not.  But  in  our  world  of  instant  communications  where  the 
most  ill-informed  can  be  heard,  read,  seen  and  believed,  we  run  a  great  risk  that 


Regional  Meeting  Address  by  A.  F.  Joplin 417 


we  will  be  conned  into  an  economic  way  of  life  completely  foreign  to  our  needs  and 
instincts — and  at  great  costs. 

Governments  are  not  a  substitute  for  informed  and  well  directed  market- 
oriented  enterprise.  There  may  be  room  for  governments  to  set  guidelines  and 
policies,  and  these  can  be  accepted — especially  if  tliey  have  done  their  homework. 
But  to  substitute  bureaucrats  for  trained  managers  is  just  plain  suicide. 

I  would  not  want  you  to  think  that  I  am  saying  everything  we  do  is  perfect — 
that  we  have  nothing  to  learn  from  other  cultures  from  other  people — far  from 
it.  I  recently  had  the  opportunity  to  visit  with  the  railways  in  the  Soviet  Union.  I 
must  say  I  was  impressed.  We  were  told  they  were  run  at  a  profit — and  they  well 
might  be — even  using  our  capitalistic  standards.  I  must  say  I  was  impressed  by  their 
operating  statistics.  Nearly  half  of  all  freight  traffic  carried  by  railways  in  the  world 
mo\'es  on  So\iet  railways.  This  is  accompfished  on  138,000  route-kilometers  (equiva- 
lent to  82,000  miles)  of  rail  fine,  one-third  of  which  is  two-track  and  in  some  cases 
three-track.  With  about  2)2  times  the  route  miles,  the  North  American  railroads 
produced  less  than  one-third  the  gross-tonne-kilometers  of  freight  service.  The 
Soviets  do  not  have  much  of  an  unprofitable  branch  line  problem.  I  was  also  im- 
pressed by  tlie  four  hours  to  load  and  tlie  four  hours  to  unload  that  the  Russian 
shipper  achieves.  They  seem  to  be  able  to  manage  the  demurrage  question  quite 
well. 

In  the  Soviet  Union,  a  full  crew  consists  of  a  mechanic  and  a  helper  in  the 
engine,  and  a  red  flag  tied  on  behind.  W.  L.  Thornton  of  the  Florida  East  Coast 
recently  wrote  a  letter  to  U.S.  Congress  on  archaic  work  rules.  One  certainly  cannot 
say  that  the  Soviet  railways  are  at  any  disadvantage  when  it  comes  to  full-crew 
laws. 

Despite  all  our  handicaps,  the  management  of  our  railways  on  this  continent 
have  produced  a  transportation  system  which  is  universally  acknowledged  as  the  best 
in  the  world.  Not  only  do  our  railways  provide  faster  and  more  reliable  service,  but 
they  do  so  at  charges  to  the  user  considerably  less  than  anywhere  else  in  the  world. 
I  think  if  you  are  going  to  criticize  our  railway  managers,  you  also  have  to  give  them 
the  credit  that  is  their  due  for  what  are,  undoubtedly,  their  successes. 

I  know  it  is  going  to  take  more  than  the  few  voices  that  are  now  raised  by 
those  working  our  industry  to  have  any  significant  impact  on  the  clamor  that  can 
be  raised  by  the  amateurs.  We  should  not,  however,  let  this  stop  us  from  having 
our  say.  To  this  end  I  have  written  an  editorial — if  you  cannot  beat  them,  join 
them.  Now  this  is  a  pretty  amateur  editorial.  I  doubt  whether  Luther  S.  Miller 
[Railway  Age]  or  Tom  Shedd  [Modern  Railroads]  will  lose  much  sleep  over  my 
entry  into  the  editorial  writing  field.  It  may  just  point  up  the  kind  of  difficulty  an 
amateur  can  get  into  when  he  steps  out  of  his  field — maybe  there  is  a  lesson  here. 
There  is  only  one  difficulty  with  all  this:  the  editorial  probably  won't  get  published; 
thus  I  am  pleased  that  you  provided  me  with  a  platform  so  that  my  editorial  at 
least  gets   a  hearing.   I   head  it  with  the  title,  "Mr.   Wellington's  Engineer." 


MR.  WELLINGTON'S  ENGINEER 

The  developing  crises  of  scarce  resources  and  the  forecasted  demands  on  all 
segments  of  economy,  in  particular  transportation,  are  occupying  considerable  public 
thought  and  debate.  Wlien  you  add  to  this  the  impact  of  inflation,  tight  money, 
public  participation  as  external  constraints,  the  ability  of  engineering  organizations 


418        Bulletin  656 — American  Railway  Engineering  Association 

to  function  effectively  is  reduced.  In  searching  for  answers  to  ameliorate  these  ex- 
ternal problems,  insufficient  attention  has  been  given  to  the  many  ways  engineers 
can  effectively  perform  their  work. 

A.  M.  Wellington  wrote  the  pre-emptive  work  on  railroad  construction,  "The 
Economic  Theory  of  Railway  Location,"  at  the  turn  of  the  century.  When  defining 
engineering,  he  said:  "To  define  it  rudely  but  not  inaptly,  it  is  the  art  of  doing  that 
well  with  one  dollar  which  any  bungler  can  do  widi  two  after  a  fashion,"  and  he 
added,  "and  yet  there  is  no  field  of  professional  labor  in  which  a  limited  amount 
of  modest  incompetency,  at  $150  per  month,  can  set  so  many  picks  and  shovels  and 
locomotives  at  work  to  no  purpose  whatever."  Much  has  been  said — and  most  of  it 
in  a  derogatory  nature — regarding  tlie  lack  of  the  ability  to  see  the  big  picture  in 
planning  rail  facilities,  the  reluctance  to  accept  the  new  "space  age"  technology  or 
the  acknowledgement  of  human  values  and  social  impact  in  developing  transpor- 
tation  systems — in  particular,   rail   systems   for  freight   and  passengers. 

Some  writers  enjoy  emphasizing  negative  things.  They  enjoy  being  critical.  We 
can  accept  that  as  part  of  the  job  and  can  live  with  it.  We  have  to  make  correct 
decisions  even  if  they  are  unpopular. 

Not  all  engineering  has  been  developed  with  the  imagination  that  it  should 
have  had.  In  many  cases  it  is  possible  to  improve  the  aesthetic  and  human  values 
at  little  or  no  cost.  There  is  surely  one  matter  in  which  engineers  could  do  more. 
Certainly  we  should  attempt  to  inform  politicians  and  persuade  them  to  tell  tlie 
public  truthfully  what  are  the  real  costs  of  things  being  demanded,  whether  this  be 
some  exotic  form  of  passenger  transport  or  artificially  constructed  freight  rates  to 
foster  the  development  of  one  region  of  the  country  over  another. 

In  some  instances,  leaders  of  public  thought,  attributing  Talleyrand's  remarks 
regarding  war  and  professionals  to  either  Winston  Churchill  or  Abraham  Lincoln, 
will  say  that  these  are  much  too  important  matters  to  be  dealt  with  by  generals. 
As  a  result  a  veritable  babble  of  opinions  and  recommendations  are  spewed  forth  or 
are  proposed  as  simple  solutions  to  the  difficult  choices  which  we  must  make  in 
meeting  the  demands  for  transportation.  These  "solutions"  are  for  the  most  part 
ill-informed  or  not  informed  at  all,  or  very  thoughtful  and  comprehensive — depend- 
ing on  which  side  of  the  argument  you  are.  One  thing  for  certain — they  are  loudly 
stated. 

At  no  time  has  the  need  for  making  tlie  right  decisions  been  more  necessary. 
The  creation  of  capital  in  the  next  decade  both  in  Canada  and  in  the  United  States 
is  likely  to  fall  far  short  of  the  "demands"  that  are  being  created  in  our  society  by 
expectations  raised  by  those  who  advocate  the  "free  lunch"  theory  of  nationalized 
industries  or  who  say  "business  can  afford  it."  This  is  no  time  to  ignore  the  lessons 
painfully  learned  by  the  diligent  and  professional  application  of  our  particular  craft 
and  art.  This  is  no  time  for  the  armchair  generals  to  learn  the  basic  truths  about 
applying  science  and  technology  in  sorting  out  the  dilemma  we  face  in  matching 
our  demands  to  our  ability  to  produce — now  is  the  time  to  pay  heed  to  Mr.  Welling- 
ton's definition  of  "engineering." 


Railway  Signalling 

By   H.   W.   Trawick 

Engineer   of    Signals 
CP    Rail 

It's  a  pleasure  for  me  to  participate  in  this  AREA  Regional  Meeting.  Even 
though  signals  are  a  part  of  the  maintenance  of  way  department  on  our  railway, 
and  many  other  railways  have  a  similar  type  of  organization,  there  seems  to  be 
insufficient  interplay  between  signals  people  and  other  maintenance  of  way  staff. 

One  of  our  regional  engineers,  some  years  ago,  used  to  refer  to  his  signal  staff 
as  the  "mystery  boys."  He  wasn't  quite  sure  what  they  did,  nor  why,  as  long  as 
there  were  no  train  delays  at  signals  and  tliey  stayed  within  tlieir  budget.  On  the 
otiier  hand  the  "mystery  boys"  were  never  too  eager  to  share  their  problems  and 
experiences  with  others.  A  strange  attitude — and  while  it  is  not  so  prevalent  these 
days  it  still  exists.  Perhaps  gatlaerings  such  as  this  will  help  to  change  it  even 
further. 

So  for  the  next  few  minutes  I  will  talk  a  little  about  some  of  the  history  of 
signals  and  control  systems  and  about  some  of  the  things  we  do  in  signals  and  why 
we  do  them  the  way  we  do.  Hopefully  diis  will  dispel,  if  it  exists,  some  of  the 
"mystery." 

Tlie  purpose  of  a  railway  signal  department  is  to  provide  safe  and  efficient 
train  operation — of  course  at  a  reasonable  cost.  The  emphasis  is  on  safety  but  over 
the  years  it  has  developed  that  signal  systems  have  much  to  offer  the  railway  in 
the  way  of  efficiency  and  expedition  of  train  movements.  In  tlie  early  days  of  rail- 
roading as  soon  as  a  railway  could  afford  a  second  engine,  the  problem  of  keeping 
them  apart  had  to  be  considered.  So  railway  operations  developed  a  simple  system 
of  time  spacing  by  timetable.  However,  if  one  train  lost  time  train  crews  had  to 
rely  on  sight  to  maintain  safety.  A  meet  with  two  trains  was  often  a  problem 
especially  if  they  did  not  sight  one  another  in  the  vicinity  of  a  siding.  When  the 
trains  met  one  another  on-line,  violent  arguments  occurred  as  to  which  train  was 
to  back  up. 

One  solution  that  was  developed  was  to  erect  a  post,  a  "block  post,"  along- 
side the  track,  and  the  first  train  to  arrive  at  the  post  had  the  right-of-way  and 
the  otiier  had  to  back  to  the  siding.  This  system,  however,  had  its  problems  when 
the  race  for  the  post  ended  in  a  tie. 

As  traffic  and  train  speeds  increased,  more  reliable  systems  had  to  be  developed. 
One  system,  about  1830,  used  a  ball  or  a  basket  hoisted  on  a  mast.  When  the  track 
was  clear  the  ball  was  hoisted  to  the  top  of  the  mast.  When  an  operator  at  one 
station  sighted  the  ball  at  the  next  station,  through  his  telescope,  he  hoisted  the 
ball  to  the  top  of  the  mast  as  a  signal  for  his  train  to  proceed.  This  was  the  first 
"high  ball."  Some  of  these  ball  signals  remained  in  use  for  many  years  and  eventually 
the   telegraph   message   replaced   the   telescope. 

One  time,  on  a  railway  using  ball  signals,  when  a  train  arrived  at  a  station 
considerably  behind  schedule,  the  conductor  received  a  scathing  message  from  his 
superintendent  enquiring  as  to  tlie  reason  for  the  delay.  The  conductor's  somewhat 
colorful  message  in  reply  read:   "Held  by  the  balls  at  Bellow's  Falls." 

However,  the  common  metliod  of  controlling  trains  was  the  timetable.  This 
was  fine  as  long  as  trains  all  ran  on  time;  however,  delays  were  inevitable,  some- 
times of  course  they  were  of  very  long  duration. 

419 
Uul.  656 


420       Bulletin  656 — American  Railway  Engineering  Association 

One  day  in  about  1856  a  railway  superintendent  was  riding  a  train  operating 
under  timetable  scheduling  and  was  forced  to  wait  at  Station  "D"  for  a  train  that 
was  considerably  late.  Eventually  the  irritated  superintendent  sent  a  telegram  to 
Station  "B"  to  hold  the  opposing  train  until  the  arrival  of  his  train.  The  engineman 
in  the  superintendent's  train  did  not  want  to  proceed  because  this  was  against  the 
rules.  Finally,  the  superintendent  put  the  instructions  to  move  in  writing  and  gave 
it  to  the  engineman.  Thus,  the  first  train  order  was  born,  and  this  is  the  basis  for 
timetable  and  train  order  operation  still  much  in  use  today. 

Some  other  concerns  in  operating  trains  were  how  to  control  them  at  junctions 
and  at  crossings  witli  other  lines.  Systems  were  developed  using  wires  or  rods  and 
pipes  connected  to  signals  which  by  now  were  of  the  semaphore  type,  and  oper- 
ated by  levers.  Eventually  the  mechanical  interlocking  machine  was  developed 
and  an  ingenious  arrangement  of  dogs  and  latches  assured  that  signals  were  dis- 
played in  proper  sequence  to  trains.  These  were  the  early  "solid  state"  systems. 

In  1872  Dr.  William  Robinson  invented  the  track  circuit  and  his  invention 
led  to  the  automatic  operation  of  signals  by  the  train  itself.  Modern  signalling  has 
evolved  from  this  development  and  the  basis  of  signalling  on  this  continent  is  still 
the  track  circuit. 

Since  this  is  the  basis  of  our  modern  signal  system  let's  briefly  see  how  it 
operates.  The  rails  form  the  conductors  for  the  circuit.  At  one  end  a  battery  is 
connected  across  the  rails  and  a  relay  is  connected  across  the  other  end.  The  cur- 
rent flows  dovm  one  rail  through  the  relay  and  back  to  the  battery;  holding  the 
relay  energized.  Note  that  this  closes  a  relay  contact  which  holds  the  signal  clear. 
When  a  train  arrives  on  tliis  section  of  track  the  signal  must  assume  the  "stop" 
position.  The  wheels  and  axles  are  conductors  of  electrical  energy  and  now  cun-ent 
flows  through  them  instead  of  the  relay.  This  causes  the  contact  to  open  and  the 
signal  goes  to  stop.  This  is  an  oversimplified  illustration  of  a  track  circuit  and 
signal  system  but  it  illustrates  the  basic  principles. 

Now  there  are  many  types  of  track  circuits  employing  fairly  sophisticated 
equipment,  and  they  may  vary  in  length  from  50  ft  long  to  15,000  ft  long  or  more. 
Some  are  straight  dc,  some  use  ac.  There  are  coded  track  circuits  which  operate 
on  a  basis  of  several  pulses  or  cycles  per  minute,  such  as  code  rates  of  75,  120  and 
180  per  minute.  These  can  be  used  to  convey  information  between  signals,  as  well 
as  merely  detecting  the  presence  of  a  train.  Other  types  of  track  circuits  operate 
at  higher  frequencies  in  the  audio  frequency  range.  These  may  be  superimposed 
on  top  of  a  dc  circuit  for  certain  purposes,  such  as  control  of  highway  crossing 
signals,  and  may  reduce  the  need  for  insulated  joints.  Other  systems  are  in  use 
which  detect  the  motion  of  a  train.  At  a  highway  crossing  when  the  system  detects 
that  a  train  has  stopped  or  reversed  and  is  no  longer  moving  toward  the  crossing, 
it  may  cause  the  crossing  signals  to  stop  operating. 

If  I  spent  considerable  time  discussing  the  track  circuit  it  is  because  it  is  the 
basic  element  of  all  modern  signal  systems,  particularly  on  this  continent.  Other 
systems  without  track  circuits  have  occasionally  been  used,  usually  where  track 
circuits  may  be  difficult  to  operate — for  example  where  steel  ties  are  used.  Such 
systems  cannot  detect  broken  rails  and  obstructions  on  the  track.  Detecting  switch 
point  position  may  also  be  complex.  Because  of  the  deficiencies  in  systems  that  do 
not  continuously  detect  the  presence  of  a  train,  they  have  not  been  acceptable  on 
North  American  railways. 


Regional  Meeting  Address  by  H.  W.  Trawick 421 

As  was  said  earlier  safety  is  a  prime  factor  in  signalling.  You  have  seen  how 
the  track  circuit  contributes:  when  the  circuit  is  unoccupied  the  relay  is  energized; 
if  the  circuit  is  interfered  with  for  any  reason  it  causes  the  relay  to  de-energize 
and  this  creates  the  safe  condition. 

Let's  look  a  little  further  at  how  safety  is  provided  in  a  system.  Everyone  has 
heard  the  tenn  "Fail-Safe."  AAR  defines  it  this  way:  "A  term  used  to  designate 
a  signaUing  design  principle,  the  objective  of  which  is  to  eliminate  tlie  hazardous 
effects  of  a  failure  of  a  component  or  system."  Additionally,  General  Order  E-14 
of  the  Railway  Transport  Committee  contains  this  clause:  "The  apparatus  shall, 
so  far  as  possible,  be  installed  and  circuits  so  arranged  that  failure  of  any  part  of 
the  system  affecting  the  safety  of  train  operation  will  cause  all  signals  affected  to 
give  the  most  restrictive  indications  which  conditions  require."  The  Federal  Rail- 
road Administration  in  the  United  States  has  a  similar  regulation. 

In  order  to  meet  these  regulations  and  principles  all  elements  of  a  system 
must  be  considered.  It  is  necessary  then  to  consider  the  following: 

Design 

Installation 

Apparatus 

Inspection 

Testing 

Maintenance 

In  designing  a  system,  as  far  as  possible,  the  "closed  circuit"  principle  must  be  fol- 
lowed. This  principle  provides  a  normally  energized  control  function  which,  when 
energy  is  interrupted,  causes  the  control  function  to  assume  its  most  restrictive 
condition.  Where  possible,  relay  contacts  are  inserted  in  both  positive  and  nega- 
tive sides  of  vital  circuits.  Standby  power  systems  are  provided  in  the  event  of 
failure  of  primary  power  supplies.  Changed  conditions  in  one  control  circuit  must 
not  adversely  affect  another  circuit.  Installation  of  equipment  must  be  strictly  in 
accordance  with  approved  plans,  procedures  and  practices. 

Apparatus  used  in  signal  systems  is  built  to  extremely  rugged  and  reliable 
standards.  For  example,  relays  used  in  circuits  aftecting  safety  are  constructed  such 
tliat  gravity  will  force  contacts  from  the  energized  position  when  no  current  is 
available  at  the  relay  coils.  Relay  contacts  are  manufactured  of  materials  that  will 
not  weld  together  when  subjected  to  surges  or  overloads.  They  are  sealed  in  rugged, 
weather-resistant,  transparent  covers. 

Before  signal  systems  are  placed  in  service,  inspections  and  tests  are  made  to 
assure  that  the  system  is  installed  according  to  approved  plans  and  that  it  does 
function  as  intended.  It  must  not  only  be  known  that  plans  and  installations  are 
correct,  but  they  must  be  observed  to  be  correct  by  operational  tests  that  verify 
that  all  signals  display  proper  aspects  for  all  conditions  of  train  operation. 

Of  course,  after  systems  are  placed  in  operation  they  must  be  adequately  main- 
tained. Signal  maintainers  and  other  signal  staff  must  be  vigilant  to  determine  that 
all  systems  will  operate  as  intended.  There  are  many  rules  which  detail  frequency 
and  types  of  tests  that  must  be  carried  out  on  signal  systems  to  assure  Uiey  are  in 
proper  operating  condition.  This  also  requires  alertness  on  the  part  of  others  in  the 
maintenance  of  way  department  to  assure  that  insulated  joints  are  properly  main- 
tained, that  connections  to  the  track  are  not  broken  or  disturbed,  that  switches  are 
properly  adjusted. 


422       Bulletin  656 — American  Railway  Engineering  Association 

In  addition  to  railway  or  block  signals,  there  are  many  other  systems  and  de- 
vices on  a  railway  whose  purpose  is  to  provide  safe  operations.  Everyone  is  of 
course  familiar  with  the  highway  crossing  signal.  All  the  principles  outlined  above, 
so  far  as  possible,  are  used  in  these  systems.  It  is  discouraging  to  tlie  signalmen 
that  in  spite  of  the  best  efforts  of  many  people,  so  many  motorists  are  so  careless 
at  crossings. 

Some  other  safety  items  on  the  railway  are  slide  and  falling-rock  detectors, 
dragging-eqnipment  detectors,  hot-box  detectors  and  others.  CP  Rail  is  presently 
in  the  process  of  installing  a  cracked-wheel  detector  on  a  developmental  basis.  This 
system  uses  high-frequency  soundwaves  to  examine  a  car  or  locomotive  wheel  while 
a  train  moves  over  a  special  rail  section.  When  the  system  detects  a  wheel  flaw  it 
provides  an  automatic  alarm  in  addition  to  recording  the  defect  on  an  event 
recorder. 

We  have  essentially  been  discussing  the  safety  of  systems,  now  let  us  see  how 
they  can  improve  efficiency  and  expedite  train  operations. 

Eventually,  to  improve  safety  automatic  block  signals  were  added  to  the  time- 
table and  train  order  system.  However,  unless  operators  are  readily  available  to 
deliver  orders  to  trains,  changes  to  meets  and  passes  cannot  be  easily  made.  In 
heavier  traffic  territories  where  there  is  a  delay  to  one  train,  there  may  be  a  snow- 
ball effect  and  several  delays  may  occur  to  many  trains. 

Suppose  we  could  devise  a  means  of  combining  our  automatic  block  systems 
and  the  delivery  of  train  orders  or  operating  instructions  to  a  station.  We  might 
have  the  dispatcher  located  at  a  control  console  which  would  be  coimected  to  each 
station  to  which  he  would  dispatch  orders,  and  the  control  console  could  auto- 
matically receive  reports   on  train  location  and  field  conditions. 

Well,  if  we  do  that,  we  come  up  with  a  CTC  system.  Instead  of  getting  re- 
ports and  issuing  instructions  only  at  the  stations  we  can  do  these  things  at  every 
siding  end.  All  operating  instructions  to  the  train  can  be  conveyed  by  the  signals. 
Additionally,  reports  of  track  condition,  train  location  and  signal  position  is  re- 
ported to  the  dispatcher  at  his  console. 

If  we  want  to  further  improve  our  operations  we  can  easily  add  power  switch 
machines  so  that  now  the  dispatcher  can  control  all  the  switches. 

Now  let's  look  at  a  typical  console.  By  means  of  lights  the  dispatcher  knows 
the  position  of  every  train  on  his  territory,  and  the  position  of  signals  and  switches. 

CTC  is  really  a  combination  of  two  systems.  One  is  the  safety  system  using 
all  vital  components  which  are  located  in  the  field.  The  other  system  is  a  commu- 
nicating link  that  connects  the  dispatcher  to  the  locations  in  the  field,  such  as 
switches  and  signals  at  siding  ends.  The  field  or  vital  system  determines  the  loca- 
tion of  trains;  it  interlocks  signals  and  switches  so  that  dangerous  situations  will 
not  occur,  even  in  the  event  of  a  dispatcher  error.  For  example,  it  will  not  allow 
signals  to  be  displayed  for  conflicting  movements  or  for  movement  over  an  open 
switch.  It  is  the  field  or  vital  system  that  reacts  to  broken  rails,  snow  slides  or 
other  events  that  may  cause  unsafe  conditions.  The  communication  link  merely 
provides  a  connection  from  field  to  dispatcher  and  in  operation  the  dispatcher  uses 
it  to  request  actions  in  the  field  and  it  informs  the  dispatcher  of  field  conditions. 
It  is  not  a  vital  system  and  it  may  use  microwave,  radio,  open  line  wire  or  cable. 
Frequently  electronic  or  solid-state  equipment  is  used  in  this  link. 

Here  are  some  of  the  benefits  of  CTC: 


Regional  Meeting  Address  by  H.  W.  Trawick         423 

1.  Increases  safety. 

2.  Reduces  delays  due  to  meets  and  passes. 

3.  Provides  operating  flexibility  to  handle  delays  or  emergencies. 

4.  Eliminates  unnecessary  stops. 

5.  Permits  better  use  of  personnel. 

In  our  comparisons  on  CP  Rail  of  territories  where  CTC  has  replaced  time- 
table and  train  order  operation  we  have  found  average  time  savings  of  30  minutes 
to  1  hour  for     freight  trains  per  subdivision,  depending  upon  the  type  of  territory. 

Operationally,  CTC  is  a  very  simple  system  and  engineman  needs  only  watch 
the  signals — green  for  go,  red  for  stop,  with  certain  other  signals  conveying  other 
types  of  information. 

CTC  also  provides  a  real  benefit  in  large  and  congested  terminals.  In  com- 
plex areas  with  the  dispatcher  coordinating  all  movements,  efficiency  is  increased 
for   both   through   trains   and   switching   movements. 

Some  railways  are  now  considering  the  use  of  a  digital  computer  in  the  dis- 
patcher's office  to  further  assist  tlie  dispatcher  in  doing  his  job  better.  Train 
graphs  can  be  replaced  by  automatic  printouts.  Many  meets  can  be  made  auto- 
matically. A  dispatcher  may  test  out  on  the  computer  various  alternatives  for 
meets  and  passes  to  determine  how  it  may  be  done  most  advantageously.  This 
may  well  be  useful  in  scheduling  time  for  work  gangs  to  provide  more  on-track 
time. 

Information  concerning  trains,  such  as  consist,  length  of  train,  times  at  vari- 
ous points  may  be  displayed  on  cathode  ray  tubes.  If  required,  information  can  be 
displayed  for  use  of  the  superintendent,  transportation  department  and  others  on 
CRT's   located   at  remote  points. 

The  computer  may  be  used  to  make  certain  system  checks  and  provide  infor- 
mation useful  to  the  signal  maintenance  staff  concerning  equipment  condition. 

We  are  now  in  the  early  stages  of  such  a  study  at  one  control  office  on  CP 
Rail. 

On  CP  Rail  the  signal  department  has  been  involved  with  automatic  car 
identification  since  its  inception.  As  you  know  this  is  an  optical  system  using  a 
high-intensity  light  source  directed  to  a  reflective  label  on  rolling  stock.  The  system 
detects  reflected  light  from  the  labels  and  translates  it  into  car  number  and  owner- 
ship. 

ACI  is  now  a  controversial  matter  and  is  under  special  study  by  the  AAR  Re- 
search and  Test  Department.  Some  railways  have  not  made  use  of  ACI,  and  even 
those  that  have  to  date  have  not  been  too  diligent  in  label  maintenance.  The  result 
is  that  the  i^ercentage  of  good  label  readability  is  only  about  85^. 

The  Operating-Transportation  General  Committee  of  AAR  is  now  considering 
the  Research  Department  report  and  will  make  a  recommendation  to  the  AAR 
Board  of  Directors  as  to  whether  the  present  optical  system  should  be  scrapped 
and   some   new  system   introduced. 

A  personal  opinion  is  tliat  tlie  present  system  should  be  retained  and  improved 
along  with  a  reasonable  eftort  by  railways  to  maintain  labels.  That  opinion  is 
based  on  the  fact  the  ACI  is  a  useful  railway  tool,  tliat  50-75  million  dollars  have 
been  invested  in  it,  and  that  if  a  new  system  could  be  chosen  today,  it  is  likely  not 
to  find  ready  acceptance  and  railway  would  probably  not  have  an  ACI  system  for 
about  10  years. 


424        Bulletin  656 — American  Railway  Engineering  Association 

Another  aspect  of  the  signalman's  work  is  in  the  hump  yard.  Our  most  modern 
yard  is  Alyth  Yard  in  Calgary.  Many  new  developments  of  equipment  and  ideas 
went  into  Alyth  and  e\'en  after  4  years  much  of  it  still  serves  as  a  model  for  new 
yards  being  built  today. 

The  basic  requirement  at  Alyth  was  how  to  design  a  yard  capable  of  handling 
large  volumes  of  traffic  and  fit  it  into  a  confined  area.  The  basic  objective  was  to 
supply  tools  that  would  permit  supervisors  to  do  a  better  job.  This  meant  the  sys- 
tem would  perform  all  routine,  repetitive  tasks,  provide  meaningful  information  in 
a  form  and  at  a  time  convenient  to  the  user.  He  then  has  the  means  to  make  deci- 
sions required. 

There  must  also  be  means  to  improve  communications  so  that  decisions  can 
be  acted  upon.  The  central  device  to  achieve  tlie  objectives  is  the  digital  computer. 
Other  devices  include  CRT's,  teleprinters,  ACI  scanners,  an  electronic  scale,  loco- 
motive  speed   control,   radar  and  many  others. 

Just  about  every  aspect  of  railway  signalling  is  used  at  Alyth  Yard. 

I  have  attempted  to  teU  you  some  of  the  things  we  do  as  signalmen.  I  hope 
I  have  created  a  little  interest  in  the  work  of  signalmen  toward  improving  our 
railway  operations. 

Because  the  track  circuit  is  the  basic  element  of  signalling,  I  discussed  it  at 
some  length.  Another  reason  was  that  tliis  is  in  an  area  where  your  people  are 
very  much  involved.  Remember  the  design  of  this  element  is  such  that  interference 
or  improper  conditions  cause  it  to  drop  out.  Therefore  we  rely  on  you  to  maintain 
switches  in  proper  adjustment,  to  provide  clean  ballast,  to  avoid  damage  to  bonds 
and  track  connections  by  track  machinery,  to  maintain  insulated  joints.  If  these 
are  not  properly  done,  the  result  may  be  train  delays  and  in  some  cases  create 
unsafe  conditions. 

I  hold  you  earlier  the  story  of  the  regional  engineer  who  referred  to  his 
signal  people  as  "mystery  boys."  The  reason  for  that  reference  is  because  he  didn't 
understand  their  work  and  he  really  didn't  care  to  understand — but  just  keep 
things  running  smoothly. 

Unfortunately  that  is  the  attitude  of  many  maintenance  of  way  engineers. 
They  are  preoccupied  with  their  major  sphere,  their  own  area  of  experience;  and 
so  they  should  be,  because  nothing  is  more  basic  to  a  railway  than  the  ballast,  the 
ties,  the  rails,  the  bridges,  the  buildings.  Signals  are  an  adjunct  but  they  are  an 
operations  adjunct,  and  in  your  signal  engineer  you  have  an  operating  man  on 
your  staff.  Encourage  him  to  communicate  and  deal  directly  with  operations  officers. 
Involve  him  in  your  planning  as  early  as  possible.  Signal  requirements  may  have  a 
major  influence  on  your  plan.  He  can  give  you  the  operations  viewpoint.  He  has 
to  be  in  on  early  planning  because  he  is  faced  with  long  lead  times  in  obtaining 
equipment.  Signal  equipment  does  not  come  oif  the  shelf,  it  must  be  tailor-made 
to  suit  operating  requirements. 

In  conclusion,  use  your  signal  engineer,  give  him  the  responsibility  and  also 
the  authority  to  achieve  his  purpose,  and  the  purpose  of  all  of  us — to  provide  safe 
and  efficient  train  operation. 


Railway  Bridges  on  Canadian  National's 
Mountain  Region 

By  L.  R.  Morris 

Regional    Engineer,    Bridges    &    Structures 
Canadian    National    Railways 

Introduction 

The  main  routes  of  Canadian  National's  Mountain  Region  generally  speaking 
were  built  in  the  period  1912  to  1914.  The  Region  consists  of  Alberta,  British 
Columbia,  a  small  portion  of  Saskatchewan,  and  a  line  into  tlie  Northwest  Terri- 
tories, and  presently  has  about  5,000  miles  of  trackage.  The  major  bridges  were 
built  with  steel  superstructures  and  concrete  substructures,  while  the  smaller 
bridges  were  of  wood  trestle  constiaiction. 

Through  tlie  years,  barring  fires,  floods,  derailments,  collisions  and  similar 
disasters,  bridge  problems  have  been  relatively  minor.  The  original  designers  may 
have  been  overly  cautious  from  our  present-day  point  of  view,  but  praise  God 
they  were.  We  still  are  blessed  with  excellent  bridges,  many  of  which  have  carried 
traffic  for  over  60  years. 

Permanent  Bridges 

There  are  about  400  permanent  bridges  on  CN's  Mountain  Region,  many  of 
which  were  built  at  the  time  of  original  construction.  In  general  they  consisted  of 
tvvo  major  types.  One  was  the  familiar  viaduct  on  concrete  pedestals,  the  other 
consisted  of  steel  girders  or  trusses  on  concrete  piers.  Many  of  them  had  wood 
trestle  approaches,  and  the  bridge  extended  from  bank  to  bank  of  the  river.  De- 
sign in  those  early  days  was  very  simple.  The  design  data  sheets  for  a  girder,  for 
instance,  consisted  of  no  more  than  a  few  lines.  They  were  all  riveted  construction, 
of  course,  and  usually  the  details  were  kept  quite  simple.  The  piers  were  mostly 
of  concrete  construction  and  even  though  very  little  was  known  about  the  design 
of  concrete  mixes,  many  of  our  piers  are  still  in  good  condition.  The  decks  of 
the  steel  bridges  almost  invariably  consisted  of  timber  ties  supporting  the  rails. 

Today,  many  of  the  bridges  built  60  years  ago  are  still  carrying  traffic  and 
performing  very  well.  It  is  a  tribute  to  the  original  designers  that  maintenance 
costs  have  been  low.  Painting  has  been  carried  out  on  a  more  or  less  regular  cycle 
— ranging  from  5  years  in  the  damp,  coastal  climates,  to  20  years  in  the  dry,  windy 
prairies.  Timber  decks,  which  were  untreated  in  the  early  days,  had  to  be  replaced 
on  about  a  10-year  cycle  in  the  warm,  damp  areas  and  a  20-year  cycle  in  the  dry, 
cold  areas. 

In  1929  creosoted  ties  were  first  used,  but  only  on  a  selected  basis.  Being  the 
cautious  lot  railway  bridge  engineers  are,  it  was  not  until  the  mid-50's  that  it  was 
finally  proven  to  us  that  treatment  was  always  a  good  thing  and  from  then  on  all 
new  decks  were  fully  creosoted.  It  is  interesting  to  note  that  some  1929  treated 
ties  are  still  in  service  on  our  main  line. 

In  1970,  thanks  to  an  idea  gleaned  from  the  Rock  Island  Railroad,  we  started 
a  program  of  replacing  some  timber  decks  with  pre-tensioned  concrete  slabs  sup- 
porting a  ballasted  track  and  we  now  have  about  20  such  decks.  There  are  limita- 
tions to  this  application,  of  course,  because  on  through  truss  bridges  the  clearance 
is  restrictive,  and  on  many  girders  the  cost  of  strengthening  to  take  tlie  extra 
weight  is  prohibitive. 

425 


426        Bulletin  656 — American  Railway  Engineering  Association 

Wood  Trestles 

Up  until  just  a  few  years  ago,  the  standard  bridge  for  small  crossings  was  the 
wood  trestle.  In  fact  it  still  is  the  standard  bridge  for  our  branch  lines.  At  the 
present  time,  we  have  about  700  wood  trestles  on  tlie  Region. 

The  original  timber  was  always  untreated,  but  in  1929  our  first  fully  treated 
ballasted-deck  wood  trestle  was  built  and  today  many  are  still  in  existence.  How- 
ever, that  old  cautious  nature  prevented  the  full-scale  use  of  treated  timber  until 
the  mid-50's.  The  intervening  25  years  saw  some  fully  treated  structures,  some  par- 
tially treated,  and  some  untreated. 

The  ballasted-deck,  fully  treated  timber  trestle  has  been  the  finest,  most  eco- 
nomical structure  for  railway  bridges  ever  devised  and  would  still  be  if  conditions 
were  the  same  as  in  the  past.  However,  times  change,  and  whether  we  like  it  or 
not,  and  whether  we  call  it  progress  or  not,  we  have  to  face  it. 

First  of  all,  traffic  volumes,  car  weights  and  speeds  increased  significantly.  This 
in  itself  would  not  necessarily  have  changed  the  picture  regarding  wood  trestles. 
If  a  wood  trestle  is  perfectly  built  and  by  that  I  mean  timbers  well-seasoned,  straight 
and  true,  cut-offs  dead  level,  connections  perfectly  fitting,  piles  straight  and  un- 
checked, then  it  can  still  stand  a  fair  amount  of  modern  traffic.  However,  within 
the  last  20  or  25  years,  many  other  things  started  to  change.  It  became  harder 
and  harder  to  get  sound,  seasoned  timber  and  piling.  We  received  poorer  materials, 
experienced  carelessness  in  construction  and  there  wasn't  time  for  the  old  pride  in 
craftsmanship.  As  a  result,  we  have  many  wood  trestles  with  twisted  caps  and 
stringers,  poor  cut-offs,  small  diameter  and  crooked  piles  and  other  assorted  ills. 

With  the  onslaught  of  modern  rail  traffic — 130-ton  cars,  unit  trains,  higher 
speeds — the  wood  trestle  hterally  started  to  fall  apart.  Splitting  and  checking  of 
piles  and  caps  accelerated;  ties  actually  started  to  break  up  before  their  expected 
life-span  was  over;  bolts  would  loosen  up  excessively  and  in  some  instances  piles 
were  driven  down  under  the  dynamic  forces  of  unit  trains. 

There  is  the  possibility  of  a  perfectly  fitting  wood  trestle,  built  of  sound  tim- 
ber and  piling,  being  able  to  stand  up  to  a  certain  amount  of  modern  rail  traffic. 
However,  another  culprit  entered  the  picture,  or  rather  finally  became  significant. 
Through  the  years  trestle  fires  would  occur  from  time  to  time,  and  they  were  pretty 
well  accepted.  After  the  panic  of  a  bridge  burn-out  was  over,  the  statistics  would 
be  dragged  out  and  the  overall  losses  due  to  bridge  fires  would  be  assessed  against 
the  cost  of  eliminating  wood  bridges;  and  the  conclusion  would  be  that  it  would 
not  pay  to  take  any  major  steps  to  change  the  situation.  As  a  trestle  on  the  main 
line  came  up  for  rebuild,  it  sometimes  would  be  built  with  pennanent  materials, 
but  very  often  a  new  wood  trestle  would  be  the  replacement.  This  policy  resulted 
in   very  little   reduction   in  the   total  number  of  wood  trestles. 

However,  it  is  one  thing  to  look  at  statistics  on  a  sheet  of  paper  and  quite 
another  to  be  faced  with  your  main  line  cut  because  of  a  bridge  fire,  for  two  or 
three  weeks.  At  a  time  like  that  the  statistics  don't  seem  to  impress  your  executive 
management.  And  when  you  get  two  such  fires  just  one  day  apart,  then  a  major 
change   in   thinking  results. 

This  then,  was  our  situation  late  in  1969.  There  was  a  total  of  about  800  wood 
trestles  on  the  Region,  350  of  them  on  main,  critical  routes,  and  100  of  these  on 
heavy-traffic,  unit-train  territory.  And  the  projections  for  traffic  volume  in  the  future 
were  staggering.  As  a  result,  a  large  program  of  elimination  of  wood  trestles  was 


Regional  Meeting  Address  by  L.  R.  Morris  427 

started   in    1970   and   since   then   o\er   100  ha\'e   been   replaced,   with   the   program 
continuing. 

As  an  additional  and  in  a  sense  an  interim  measure  towards  reducing  losses 
due  to  trestle  and  deck  fires,  a  program  of  spraying  a  fire  retardant  coating  on  all 
open-deck  trestles  and  steel  bridges  on  our  main  routes,  was  begun  in  1971  and  is 
nearly  completed. 

Wood  Trestle  Replacements 

Replacements  of  wood  trestles  have  taken  several  forms.  Where\'er  possible, 
we  will  install  cuKerts  and  fill.  Culverts  almost  always  are  corrugated  steel.  Many 
things  prevent  the  installation  of  culverts  and  fill,  of  course.  Soil  conditions  may 
be  poor;  hydraulics  may  dictate  against  the  practice;  the  provision  for  fish  passage 
may  be  too  costly;  source  of  fill  material  may  be  too  far  away;  property  problems 
may  be  impossible  to  solve. 

Permanent  bridges  have  taken  several  forms.  For  longer  spans,  welded  plate 
girders  are  used,  with  either  concrete  or  steel  decks,  and  ballasted  track.  Shorter 
spans,  up  to  about  45  ft,  consist  of  pre-tensioned  concrete  box  beams,  post- 
tensioned  trans\  ersely,  or  steel  beams  with  concrete  slab  decks,  or  steel  beams 
with  steel  deck  plates.  Substructures  consist  of  conventional  piers,  steel  H-piles,  or 
steel  pipe  piles  filled  with  concrete,  with  concrete  caps,  or  steel  H-piles  \\'ith  steel 
beam  caps. 

Xew  bridges  are  sometimes  constructed  on  a  pennanent  line  diversion,  espe- 
cially a  large  structure,  but  many  of  the  smaller  bridges  are  built  on  the  existing 
aligmnent.  The  need  to  keep  interference  with  traffic  to  a  minimum  accounts  for 
the  rather  odd  appearance  of  many  of  our  piers.  Piles  are  driven  outside  the  exist- 
ing trestle,  on  either  side,  and  they  then  require  a  much  longer  cap  than  normal. 
Howe\'er,  this  enables  the  entire  substructure  to  be  built  \\'ith  very  little  inter- 
ference to  rail  traffic.  The  spans  are  then  placed  with  a  one-day  shut-down  of  the 
line.  We  naturally  try  to  keep  the  track  closures  to  a  minimum  and  replace  as  many 
spans  in  one  day  as  possible.  Our  biggest  single  project  of  diis  nature  was  a 
44-hour  closure  in  which  14  wood  bridges  were  replaced  with  permanent  structures. 
Generally,  however,  we  work  the  projects  in  smaller  groups  of  3  or  4  replacements 
in  a  closure  of  about  12  hours.  A  very  cooperative  and  patient  transportation 
department   makes    this    program    possible. 

Inspections 

Our  programs  of  replacements  and  repairs  are  based  on  various  inspections 
made  on  a  continual  basis.  Steel  bridges  are  inspected  in  detail  annually.  Concrete 
substructures  are  inspected  in  detail  on  a  much  longer  cycle,  depending  on  condi- 
tion. River  bed  soundings  are  taken  in  varying  cycles  depending  on  stream  bed 
and  flow  conditions.  Timber  trestles  are  inspected  at  least  annually  but  in  many 
cases  much  more  frequently.  As  a  timber  bridge  reaches  a  point  where  decay  could 
be  starting,  borings  are  taken  to  assess  the  incidence  of  loss  of  sound  material.  In 
spite  of  our  fairly  rapid  replacement  of  wood  trestles  on  main  routes,  we  still  have 
a  total  of  about  700  left  on  the  Region,  and  of  these  over  400  are  on  branch  lines, 
the  replacement  of  which  are  made  with  new  wood  trestles  if  they  cannot  be  filled. 

Naturally  these  trestles  are  kept  going  for  as  long  as  possible  and  we  have 
carried  out  a  good  deal  of  in-place  treatment.  Piling  is  dug  out  and  wrapped  with 
a   preservative-coated   bandage   and   backfilled.   Above-ground   piling  and   timber  is 

Bui.  656 


428        Bulletin  656 — American  Railway  Engineering  Association 

bored  and  filled  with  preservative.  This  operation  is  coupled  with  a  full-scale  in- 
spection by  boring,  the  holes  being  filled  with  preservative  before  being  plugged. 
A  good  deal  of  our  inspection  and  in-place  treatment  is  carried  out  by  contract 
rather   than   with   our   own   crews. 

An  area  with  which  we  have  not  so  far  been  troubled  is  that  of  metal  fatigue. 
Thanks  to  the  conservative  designs  in  the  beginning,  and  the  fact  that  1912  is  not 
really  old  compared  with  some  railway  bridges  in  other  parts  of  the  continent,  our 
steel  bridges  have  given  no  trouble  along  these  lines.  We  have  under  extensive 
study,  however,  a  bridge  built  in  1905,  to  quite  a  light  design,  by  the  Federal 
Government.  This  bridge  is  used  by  three  railways  and  since  CN  is  the  major  user, 
we  have  been  charged  with  the  responsibility  of  inspection  and  assessment  of 
structural  sufficiency.  The  results  of  the  current  study  will  serve  the  dual  purpose 
of  evaluation  of  the  bridge  itself,  as  well  as  establish  a  pattern  of  future  studies 
of  otiier  bridges. 

Disasters 

One  of  the  things  we  try  to  avoid  in  all  areas  of  life,  and  the  field  of  railway 
bridges  is  no  exception,  is  that  of  accidents  and  disasters.  However,  they  do  happen. 
And  in  spite  of  the  financial  losses  to  the  company,  and  the  headaches  and  heart- 
aches of  all  those  involved,  they  are  very  often  extremely  interesting  and  certainly 
are  the  items  that  make  the  news.  Therefore  a  dissertation  on  CN's  Mountain 
Region  bridges  would  not  be  complete  without  stating  that  we  are  not  immune  to 
such  happenings. 

Fires  have  already  been  mentioned.  We  have  had  ships  destroy  portions  of 
bridges;  ice  rise  up  suddenly  above  the  pedestals  of  a  viaduct  and  push  it  over; 
major  piers  scoured  out  and  collapse  taking  their  spans  with  them;  flood  waters 
take  out  2  pedestals  of  a  4-legged  tower  and  do  no  further  damage  (the  tower 
remained  upright! ) ;  derailments  destroy  decks  and  truss  spans;  rock  slides,  and 
snow  slides  take  out  spans  (one  steel  span  was  never  found!).  We  have  survived 
all  of  tliese  disasters  and  learned  a  good  deal  from  them. 

New  Lines 

Not  all  of  CN's  Mountain  Region  was  built  in  the  period  1912-1914.  Several 
new  lines  have  been  built  since  tliat  time,  notably  the  Kitimat  branch  in  Northern 
British  Columbia,  the  Great  Slave  Lake  Railway  in  Northern  Alberta  and  the 
Northwest  Territories,  and  the  Alberta  Resources  Railway  in  Northern  Alberta. 
These  have  included  a  considerable  number  of  bridges. 

The  new  structures  on  these  lines  are  of  several  types,  generally  following 
the  old  pattern  of  steel  viaducts,  or  girders  and  trusses  on  concrete  substructures. 
The  steel  structures  are  all-welded,  with  field  connections  of  high-strength  bolts. 
Generally  decks  have  been  of  treated  timber,  but  I  believe  we  will  be  looking  at 
all  ballasted  decks  in  the  future. 

The  total  inventory  of  bridges  presently  on  the  Region  is  over  1100.  With  the 
program  of  replacement  of  wood  trestles  only  one-third  along  the  way,  and  the 
possibility  of  new  lines  being  built  in  the  near  future,  the  subject  of  railway  bridges 
will  be  with  us  for  many  years  to  come. 


Investigation   into  Causes  of  Rail  Corrugations 


By  J.   Kalousek,  R.   Klein 

CP   Raii 


1.  INTRODUCTION 


During  the  last  decade,  CP  Rail  has  experienced  a  substantial  increase  in 
traffic  density  accompanied  by  the  introduction  of  100- ton-capacity  cars  and  in- 
creased loconioti\e  horsepower.  These  advances  increased  the  productivity  of  our 
rail  transportation  network  and  improved  the  competitiveness  of  our  operations. 
On  the  other  hand,  these  changes  have  been  associated  with  increased  wear  and 
tear  of  tlie  permanent  way.  Substantial  wear  and  abrasion  \A'as  first  experienced 
on  the  high  rail.  To  combat  this  problem,  cur\e  lubricators  were  introduced  with 
a  great  deal  of  success.  Ho\\e\er,  reduced  flange  abrasion  resulted  in  an  increase 
in  the  incidence  of  rail  corrugation. 

Rail  corrugations  we  experience  most  are  those  with  a  wavelength  (pitch)  in 
the  range  of  8  to  28  inches.  In  order  to  avoid  any  confusion,  it  should  be  men- 
tioned that  two  other  types  of  rail  corrugations  are  known  to  railroaders.  One  type 
has  a  wa\elength  in  the  range  of  2  to  3  inches  and  is  often  referred  to  as  "wash- 
board rail"  or  "roaring  rail."  It  is  the  t\pe  of  rail  cornigation  which  has  recently 
received  most  of  the  attention  in  railroading  and  scientific  literature"  "■''.  The  other 
type  of  rail  corrugation,  mentioned  in  current  literature'"',  has  a  wa\elength  in  the 
range  of  72  to  108  inches,  but  it  may  also  be  categorized  by  some  railroaders  as 
track  irregularities.  In  this  paper,  we  are  solely  concerned  with  the  observations, 
formation  mechanics  and  possible  cures  for  rail  corrugations  with  a  wa^•elength 
of  8  to  28  inches  <*'". 

2.  OBSERVATIONS 

Rail  corrugations  predominantly  appear  on  the  nmning  surface  of  the  low  rail 
in  a  curse  as  seen  in  Figure  1.  These  rail  corrugations  are  always  associated  with 
flaking  of  rail  metal  as  may  be  observed  at  the  center  of  focus.  They  usually  appear 
opposite  the  location  where  wheel  flanges  contact  the  high  rail.  They  also  are 
deeper  toward  the  field  side  of  the  rail. 

Rail  corrugations  may  also  occur  on  the  high  rail  as  shown  in  Figure  2.  The 
characteristic  flaked  or  slightly  shelled  pattern  may  be  obser\'ed  on  the  high  rail 
illustrated  in  this  figure.  The  cornigations  valleys  are  at  the  locations  of  most  in- 
tense flaking  and  they  are  deepest  at  the  gauge  comer  of  the  rail. 

Occasionally,  we  find  corrugations  on  tangent  track  as  shown  in  Figure  3  but 
this  is  not  too  common.  In  this  particular  location,  the  growth  of  corrugations  has 
been  accentviated  by  over-lubrication  of  the  track  and  the  absence  of  grinding. 
This  section  of  track  is  located  on  a  bridge  and  grinding  was  not  carried  out  be- 
cause of  the  risk  of  fire.  The  occurrence  of  rail  corrugations  on  the  high  rail  and 
tangent  track  is  rather  infrequent  on  CP  Rail  lines.  The  rail  corrugations  forming 
on  low  rails  are  predominant  and,  therefore,  we  will  devote  most  of  our  attention 
to  them. 

Figure  4  shows  the  field  side  of  the  low  rail  where  the  rail  corrugations  are 
in  the  initial  stage  of  their  de\elopment.  The  areas  on  tlie  railhead  which  are  not 
hatched   point   to  the   increased   rate   of  plastic   flow  of  metal  in  the   surface  layer 

429 


430        Bulletin  656 — American  Railway  Engineering  Association 

of  the  railhead.  These  locations  may  be  classified  as  the  "low  spots"  or  "valleys" 
of  rail  corrugations.  Plastic  flow  may  be  also  observed  in  the  neighboring  hatched 
areas,  but  this  flow  is  uniform  over  large  sections  of  rail  and  is  not  of  concern. 
The  reason  for  the  diflcrence  between  these  two  modes  of  plastic  flow  can  be 
found  in  a  closer  examination  of  surface  cracks. 

Figure  5  shows  that  the  top  surface  of  the  rail  is  flaked.  Closer  examination 
of  the  flakes  and  associated  crack  pattern  reveals  more  intense  flaking  and  the 
occurrence  of  more  critical  cracks  in  the  corrugation  valleys.  This  suggests  tliat  the 
formation  of  corrugation  valleys  is  associated  with  increased  plastic  flow  of  metal 
which  has  been  accentuated  by  an  increased  incidence  of  cracks  and  depletion  of 
metal  from  the  railroad  through  flaking. 

This  trend  may  be  already  observed  on  rails  not  yet  corrugated.  Figure  6 
shows  a  low  rail,  which  has  accumulated  approximately  8  MGT  of  traffic.  To 
reveal  the  initial  stages  of  crack  development  on  the  rail  surface,  grease  was  wiped 
away  in  two  locations.  The  location  on  the  right-hand  side,  the  close-up  of  which 
is  shown  in  Figure  7,  exhibits  a  single  longitudinal  crack.  The  location  on  the 
left-hand  side  of  the  same  rail  (Figure  8)  exhibits  two  longitudinal  cracks.  This 
spontaneous  non-imiformity  in  crack  initiation  indicates  that  these  cracks  are  of  a 
surface  fatigue  origin  and  that  corrugation  formation  mechanics  might  be  related 
to  surface  fatigue.  For  this  reason,  we  have  investigated  the  cracks  in  more  detail 
with  a  Scanning  Electron  Microscope  and  discovered  a  large  incidence  of  spherical 
particles  as  shown  in  Figure  9.  The  magnification  is  approximately  1,250  diameters. 
These  spherical  particles  are  typical  of  surface  fatigue  failures  of  lubricated  ma- 
chine components  such  as  roller  bearings,  gears  and  also  rails,  thus  confirming  the 
surface  fatigue  nature  of  rail  flaking. 

The  question  now  arises  as  to  how  we  can  relate  the  surface  fatigue  and 
plastic  flow  of  metal  to  formation  of  rail  corrugations.  The  answer  to  this  question 
is  ratlier  complex  since  additional  factors  such  as  tlie  distribution  and  magnitude 
of  contact  stresses,  tangential  forces,  dynamical  loadings,  strength  of  rail  material, 
lubrication  and  wear  play  a  significant  role  in  corrugation  formation  mechanics. 

3.  FORMATION  MECHANICS  OF  RAIL  CORRUGATIONS 

The  explanation  of  rail  corrugation  formation  may  be  simplified,  if  we  con- 
sider first  the  plastic  flow  of  railhead  metal  and  then  surface  fatigue.  Other  factors 
influencing  corrugation  formation  mechanics  will  be  dealt  with  within  these  two 
subsections. 

3.1  Plastic  Flow 

Perhaps  the  best  way  to  start  the  explanation  of  jjlastic  flow  is  to  consider  the 
basic  aspects  of  Hertzian  theory  of  contact  stresses.  The  contact  stresses  may  be 
assessed  if  the  wheel  and  rail  are  represented  by  two  cylinders  crossing  each  other, 
as  shown  in  Figure  lOA. 

The  area  of  contact  between  these  two  cylinders  is  usually  ellipitical.  A  knowl- 
edge of  mechanical  properties  of  wheel  and  rail  materials  together  witii  the 
knowledge  of  contact  geometry  enable  us  to  calculate  the  contact  stresses.  Their 
distribution  is  shown  graphically  in  Figure  lOB.  The  maximum  value  of  vertical 
stress  fz  can  be  designated  as  maximum  pressure  Pmai  since  all  contact  stresses  are 
compressive.  It  is  convenient  to  use  Pmax  as  a  basic  parameter  describing  the  dis- 
(Text  continued  on  page  439) 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein 431 


1   i.Ulll 


432       Bulletin  656 — American  Railway  Engineering  Association 


Figure  2 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein 


433 


Figure   '■> 


434       Bulletin  656 — American  Railway  Engineering  Association 


-.\^jL 


w .CTWwmii  .M 


<l 


Figure  5 


Regional  Meeting  Address  by  J.  Kalousek.  R.  Klein 435 


Figure  (i 


Figure  7 


436        Bulletin  656 — American  Railway  Engineering  Association 


Figure  8 


Figure  9 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein  437 


(A)     IDEALIZED    CONTACT    BETWEEN    RAIL    HEAD    AND    WHEEL. 


^  ^g  VALUES    OF    PRINCIPLE    STRESSES    (T^  '    <^y ' 

y    y'      tfz    AND    SHEARING    STRESS    r     (Ib/inch^j 


DEPTH  |z 

(B)   DISTRIBUTION  OF  STRESSES  IN  CONTACT  ZONE, 


FIGURE  10 


438        Bulletin  656 — American  Railway  Engineering  Association 


(A) 


3/4"  FLANGEWAY  CLEARANCE 

1/4"  WIDE  GAUGE  (INSTALLED) 

r"    TOTAL  (NEW  WHEELS,  NEW  RAILS) 


=  1" 
1/4" 
1/4  " 


AS  IN  (A) 

WHEEL  FLANGE  WEAR 

RAIL  SIDE  WEAR 


1-1/2"  TOTAL  (WORN  WHEELS,  WORN  RAILS) 

// //  • 


(C)        D  =  1"  AS  IN  (A) 

3/8"  WHEEL  FLANGE  WEAR 

3/8"  RAIL  SIDE  WEAR 

1/4"  DYNAMIC  GAUGE  WIDENING 


2" 


TOTAL  (BADLY  WORN  WHEELS  AND  RAILS, 
HIGH  DYNAMICAL  LOADINGS) 


FIGURE  11:   CONTACT  GEOMETRY  BETWEEN  WHEEL  AND  LOW  RAIL  IN  CURVES, 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein 


439 


tribution  of  contact  stresses  because  for  any  value  of  F,„„x,  the  distribution  of 
principle  stresses  Oi,  <J,j,  <Jt  and  shearing  stress  f  resembles  that  shown  in  this  figure. 
The  stress  considered  most  critical  in  development  of  subsurface  cracks  is  the 
maximum  shearing  stress  Tm«r  which  occurs  between  0.1-0.3  inch  below  the  run- 
ning  surface   of   the   rail. 

This  distribution  of  contact  stresses  is  valid  only  in  the  case  of  static  contact 
between  two  elastic  bodies  of  perfect  shape  and  smooth  surface.  Additional  factors, 
which  may  significantly  influence  the  Hertzian  distribution  of  contact  stresses, 
such  as  work  hardening  of  wheel/rail  materials,  presence  of  surface  frictional  forces 
in  the  zone  of  contact,  lubrication  and  wear,  must  be  considered  if  the  actual 
wheel/rail   interaction  is   to  be  understood. 

Three  examples  of  the  possible  relative  positions  between  wheel  and  low  rail 
are  depicted  in  Figure  11  for  9°-12°  cur\'es.  Assuming  that  the  wheelset  is  in 
flange  contact  witli  the  high  rail,  the  relative  position  of  wheel  and  low  rail  may 
be  represented  for  convenience  by  the  distance,  D,  between  the  wheel  flange  and 
gauge  side  of  the  rail.  With  no  wear,  this  distance  is  comprised  of  the  flange  way 
clearance  /i-inch  plus  a  preset  wide  gauge  of  /4  inch  totalling  1  inch  as  shown  in 
Figure  11  A.  If  both  the  high  rail  and  wheels  are  worn  by  M  inch  the  distance,  D, 
between  the  wheel  and  low  rail  is  increased  to  1/2  inches  as  shown  in  the  second 
sketch.  If  we  consider  severe  wear,  and  add  to  this  the  magnitude  of  dynamical 
gauge  widening  /4  inch,  the  reversed  curvature  of  the  wheel  rim  (often  referred  to 
as  the  false  flange)  may  be  brought  very  close  to  the  center  of  the  low  rail.  The 
contact  stresses  in  terms  of  Pmox  experienced  by  wheel  and  rail  under  these  and 
other  possible  conditions   are  presented  in  Table   1. 

The  pressure  P,„oi  is  calculated  according  to  a  simplified  formula  for  36-inch- 
diameter  wheel  carrying  a  33,000-lb  load  (which  corresponds  to  a  100-ton  capacity 


SIMPLIFIED  CONTACT  STRESS  FORMULA  FOR  P„^„:   P„,^  =  \    (\f           ^? '  "  '   W'       WHERE 

ITiaA      maA     \\        £.           1    ±~  »   J 

G  =  11.5  X  10'  psi;   v=  .29   R^  =  18"  ,   R'^  =  =« ,   R'j^  =  lO"  ,   R^  =  » ,   W  =  33,000  lb. 

/ariable     (psi)         Remarks 

«'w 

Variable    (psi)            Remarks 

10 

215,800 

New  rail,  new  wheel 

" 

215,800 

New  wheel,  new  rail 

15 

133,700 

Flattened  rail,  new 
wheel 

-10 

108,600 

Worn  hollow  wheel  on  top 
of  new  rail 

5 

300,400_ 

Edge  of  rail,  new  wheel 

10 

J00,400 

False  flange  on  top  of 
new  rail 

3 

397,400 

Edge  of  rail,  new  wheel 

5 

338,400 

False  flange  on  top  of 
new  rail 

2 

504,400 

Edge  of  rail,  new  wheel 

5 

773,300 

False  flange  on  edge  of 
new  rail  (Rj^  =  1.25") 

1.25 

672,300 

Edge  of  new  rail, 
inflection  point  of  worn 
wheel 

5 

436,000 

Same  as  above  but  empty 
car  W  =  5,600  lb. 

TABLE  1:   CONTACT  STRESSES  FOR  VARIOUS  WHEEL  RAIL  GEOMETRIES. 


440        Bulletin  656 — American  Railway  Engineering  Association 

car).  The  effect  of  cross-sectional  curvature  of  railhead  on  the  magnitude  of  con- 
tact stresses  is  illustrated  in  the  first  colunni,  whilst  the  effect  of  wheel  profile 
cur\atures  is  presented  in  the  second  column.  As  the  effective  crown  radius  of  the 
rail  decreases  toward  the  edge  of  the  rail,  the  magnitude  of  contact  stresses  in- 
creases. Similarly,  as  the  false  flange  curvature  decreases,  the  contact  stresses 
increase  substantially.  No  doubt,  some  of  these  values  exceed  the  yield  stress  of  the 
rail  material. 

It  was  mentioned  previously  that  the  most  critical  stress  in  the  theory  of  con- 
tact stresses  is  the  maximum  shear  stress.  Therefore,  it  is  desirable  to  know  the 
yield  of  material  in  shear  rather  than  in  tension.  The  yield  in  shear  may  be  con- 
veniently obtained  from  a  hardness  test  since  the  resistance  of  material  to  shear 
is  directly  proportional  to  its  hardness.  From  a  practical  sense,  the  higher  the 
hardness  of  rail  steel,  the  better  it  can  withstand  the  contact  stresses.  The  actual 
value  of  the  contact  stresses  above  which  the  rail  material  will  always  yield  is 
termed  the  plasticity  limit.  The  plasticity  limits  of  carbon  and  chromium  rails  are 
approximately  250,000  psi  and  320,000  psi,  respectively,  assuming  that  the  surface 
layer  of  rail  material  has  been  already  work-hardened,  say,  after  the  passage  of 
the  first  train  over  those  rails. 

It  should  be  pointed  out  that  the  theory  of  Hertzian  stresses  is  applicable 
only  witliin  the  elastic  limits  of  a  material  and  should  not  be  employed  to  explain 
plastic  flow.  When  yield  occurs,  no  pressures  significantly  above  the  yield  can 
develop  within  the  rail  material.  Although  the  stress  cannot  be  built  up  significantly 
above  the  plastic  limit,  parameter  P»u/j  may  still  give  the  indication  of  the  rate  of 
plastic  flow.  As  Pmax  increases  above  the  plastic  limit,  so  does  the  rate  of  plastic 
flow.  Hence,  the  underlined  values  in  Table  1  illustrate  situations  where  both 
carbon  and  chromium  rail  will  yield  and  exhibit  sustained  plastic  deformation.  The 
numbers  underlined  by  a  dashed  line  refer  to  situations  in  which  only  carbon  rail 
will  yield. 

Our  examination  of  contact  stresses  is  not  over  yet  since  the  above  mentioned 
plasticity  limits  may  be  applied  with  reasonable  accuracy  to  tangent  track  only. 
In  the  case  of  curves,  the  continuing  presence  of  lateral  friction  forces  must  be 
taken  into  account.  These  are  shown  in  Figure  12. 

To  simplify  our  analysis,  it  is  assumed  that  the  wheelsets  negotiate  curves  at 
an  equilibrium  speed  and  that  die  rolling  radii  of  both  wheels  are  the  same.  When 
the  wheelset  rolls  forward  a  distance  d,  it  is  displaced  laterally  a  distance  ^c?  due 
to  flanging.  Since  the  wheelset  slides  rather  than  rolls  in  the  lateral  direction,  the 
amount  of  force  required  to  laterally  displace  each  wheel  is  equal  to  the  product 
of  the  coefficient  of  friction,  M,  and  normal  force,  W. 

It  can  be  shown  that  the  orientation  of  the  lateral  components  of  wheel/low- 
rail  forces  are  such  that  tlie  low  rail  is  pushed  toward  the  field  side  and  the 
wheelset  is  pushed  toward  the  high  rail.  On  the  high  rail,  the  frictional  tread 
force  and  flange  force  act  simultaneously.  The  flange  force  is  the  sum  of  the  two- 
wheel  frictional  forces.  The  net  result  is  that  the  high  rail  is  pushed  toward  the 
field  and  the  wheelset  is  pushed  toward  the  center  of  the  curve.  It  must  be  empha- 
sized that  the  frictional  tread  forces  and  flange  force  are  directly  responsible  for 
increased  wear  and  tear  of  track  in  curves.  For  example,  they  contribute  to  "cut- 
ting in"  of  both  tie  plates  on  the  field  side. 

At  the  wheel/rail  interface,  the  tread  forces  significantly  modify  the  distribu- 
tion of  contact  stresses.  The  higher  the  coefficient  of  friction,  the  closer  the  maxi- 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein 441 


FIGURE  12:   LATERAL  COMPONENTS  OF  FORCE  VECTOR 
IN  THE  WHEEL/RAIL  CONTACT  ZONE 


442        Bulletin  656 — American  Railway  Engineering  Association 


Type  of  rail 

Carbon 

P    fpsi] 
max  \-^    J 

Chromium 

P    fpsi] 
max  >-'^  ■* 

Case  of  pure  rolling 
(tangent  track) 

250,000 

320,000 

Case  of  rolling  with 
frictional  lateral 
forces  (curves) 
ji  =  ,26 

185,000 

240,000 

TABLE  2; 


MAXIMUM  CONTACT  STRESSES  THE  RAIL  MATERIAL  CAN 
WITHSTAND  WITHOUT  SUSTAINED  PLASTIC  FLOW. 


mum  shear  stress  is  brought  to  the  surface.  This  results  in  a  proportionate  reduc- 
tion of  tlie  carrying  capability  of  rail  material.  The  extent  to  which  the  plasticity 
limit  can  be  lowered  by  the  tread  forces  in  terms  of  Pmax  is  shown  in  Table  2. 
With  a  coefficient  of  friction  of  0.26,  the  carbon  rail  can  tolerate  only  185,000  psi 
in  curves  without  sustained  plastic  flow.  For  coefiicient  of  friction  values  lower  than 
0.26,  the  plasticity  limit  increases  and  at  coefficient  of  friction  0.0,  the  plasticity 
limit  is  maximum.  It  may  be  interesting  to  note  tliat  the  plasticity  limit  of  chromium 
rail  in  curves,  approximately  240,000  psi,  is  somewhat  less  than  the  plasticity  limit 
of  carbon  rail  in  tangent  track.  In  a  practical  sense,  the  values  of  plasticity  limit 
suggest  that  each  time  the  false  flange  runs  close  to  the  edge  or  over  the  top  sur- 
face of  the  rail,  both  carbon  and  chromium  rail  will  plastically  deform. 

Due  to  tile  dynamic  nature  of  the  track/train  interaction,  vertical  loads,  lateral 
tread  forces,  dynamic  (and  static)  wide  gauge  as  well  as  the  coefficient  of  fric- 
tion in  the  zone  of  contact  are  continuously  varying  along  the  rail  paths  in  curves. 
Hence,  the  magnitude  of  contact  stresses  and  the  plasticity  limit  are  subject  to 
random  fluctuations.  However,  more  experimental  work  is  needed  to  determine 
whether  the  intennittent  pounding  of  peak  dynamical  forces  at  exactly  the  same 
location  on  rail  produce  the  corrugation  valleys  or  whetlier  other  parameters,  such 
as  localized  wide  gauge  and/or  development  of  fatigue  cracks  governs  the  initial 
location  of  corrugation  valleys.  It  is  the  opinion  of  the  authors  tliat  the  random 
nature  of  frictional  tread  force  and  random  initiation  of  fatigue  cracks  are  most 
conducive  to  the  formation  of  rail  corrugations. 

3.2  Surface  Fatigue 

Based  on  the  observations  described  at  the  beginning  of  this  presentation,  it 
was  suggested  that  plastic  flow  in  combination  with  surface  fatigue  are  predomi- 
nantly responsible  for  the  formation  of  rail  corrugation.  Plastic  flow  of  rail  material 
was  briefly  dealt  with  in  the  first  portion  of  this  presentation  and  it  now  remains 
to  cover  the  subject  of  surface  fatigue. 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein  443 


5x10^ 


<    10 


5x10' 


I       ,      .     ,     ,    I , I       , 


5x10'  10°  5x10'  10' 

NUMBER    OF    CYCLES    -    N 
FIGURE    13:       SURFACE    FATIGUE    S-N    DIAGRAM 


Surface  fatigue,  sometimes  referred  to  as  contact  fatigue,  deals  with  surface 
or  subsurface  failure  of  material  which  is  repeatedly  in  contact  with  some  loading 
member.  Due  to  the  large  xariety  of  possible  wheel/rail  contact  geometries  and 
the  effect  of  frictional  forces  and  other  parameters  on  the  distribution  of  contact 
stresses,  contact  fatigue  failure  of  rail  material  can  take  any  of  the  following 
forms:  pitting,  flaking,  spalling  and  shelling.  Each  of  these  contact  fatigue  mani- 
festations can  be  analyzed  in  two  stages.  The  first  stage  is  crack  initiation  and  the 
second  is  crack  propagation.  A  crack  may  initiate  at  two  locations:  at  or  very  near 
the   surface   and  a  short  distance  below. 

Cracks  originating  at  the  surface  later  develop  into  flaking  and  are  therefore 
subject  to  further  analysis.  The  first  stage  of  crack  development  arises  from  a 
number  of  loading  cycles  at  a  specified  load  or  contact  stress.  Figure  13  shows  a 
typical  surface  fatigue  "Stress — Number  of  Cycles"  diagram.  The  number  of 
cycles  or  number  of  passages  of  wheel  over  a  small  section  of  rail  are  plotted  on 
the  horizontal  axis.  The  contact  stresses  in  terms  of  P,„„r,  which  take  into  account 
the  magnitude  of  load  and  geometry  of  contact,  are  plotted  on  the  vertical  axis. 
The  experimental  points  plotted  in  tliis  S-N  diagram  were  obtained  under  full 
lubrication  conditions  in  the  zone  of  contact  and  exhibit  large  scatter  which  is 
rather  typical  of  surface  fatigue.  The  surface  fatigue  diagram  shown  in  Figure  13 
describes  surface  fatigue  behavior  of  plain  carbon  steel  and  indicates  that  the 
crack  dexelops  after  accumulation  of  approximately  M  million  cycles  at  P „,,,.,■  = 
250,000  psi  and  after  accumulation  of  1  million  cycles  at  Pm„x  =:  150,000  psi. 
Utilizing  this  information,  it  has  been  calculated  that  on  lines  with  an  annual  traffic 
density  of  45—50  MCT,  surface  cracks  develop  30  to  40  days  after  new  carbon  rail 
is  placed  in  service.  With  chromium  rail,  this  period  is  extended  by  10  to  20  days. 

Bui.  656 


444        Bulletin  656 — American  Railway  Engineering  Association 

In  fact,  Fij^uit's  6  to  8  show  cracks  already  initiated  on  the  surface  of  chroniimu 
rail   which   was   in   service   for  approximately  two   months. 

If  full  lubrication  is  not  satisfied  and  some  natural  wear  occurs,  crack  initiation 
and  development  of  flakes  may  be  delayed.  Ultimately  where  there  is  sufficient 
wear,   fatigue  crack  initiation  may  never  occur. 

Accumulation  of  lubricant  on  the  rail  surfaces  plays  a  significant  role  in  the 
development  of  surface  fatigue.  This  is  illustrated  in  more  detail  in  Figure  14.  The 
primary  role  of  the  lubricant  is  to  reduce  flange  wear  on  the  gauge  side  of  the 
high  rail.  Nevertheless,  the  lubricant  is  gradually  squeezed  out  of  the  flange  con- 
tact zone  and  to  insure  adequate  lubrication  in  the  flange  contact  zone,  the  lubri- 
cant must  be  continuously  replenished  by  track-side  lubricators.  Lubricant  "squeezed 
from"  the  zone  of  contact  is  then  deposited  on  the  edge  of  the  wheel  flange  as 
well  as  on  the  wheel  false  flange.  From  the  wheel  false  flange,  excess  lubricant 
deposits  on  the  top  running  surface  of  the  low  rail,  where  it  promotes  surface 
fatigue  crack  development  and  flaking. 

The  manner  in  which  lubricant  contributes  to  crack  propagation  and  subse- 
quent flaking  is  shown  in  Figure  15.  A  passing  wheel  first  closes  the  crack  and 
"locks  in"  the  lubricant  (Figure  15A,  Section  1-1).  During  further  travel  of  the 
wheel  (Figure  15A,  Section  2-2),  the  pressure  of  the  lubricant  layer  within  the 
contacting  surface  is  hydro-dynamically  transmitted  to  the  lubricant  located  at  the 
root  of  the  crack  where  a  maximum  pressure,  P,„„j--  and  maximum  tangential 
stress,  T,,,,,,,,  act  simultaneously.  Whilst  this  mechanism  uniformly  enhances  the 
growth  of  a  crack  in  the  case  of  longitudinally  oriented  cracks  (Figrue  15B),  it 
usually  results  in  formation  of  rail  corrugations  and  more  severe  defects  such  as 
transverse  fissures  with  oblique  and  intersecting  cracks   ( Figure  15C ) . 

The  presence  of  surface  cracks  and  flaking  contributes  to  deterioration  of  rail 
life  in  two  ways.  Firstly,  they  disrupt  the  homogenity  of  rail  metal  at  the  surface 
and  significantly  redistribute  contact  stresses  which  results  in  a  reduction  of 
resistance  to  plastic  flow.  Secondly,  the  cracks,  in  combination  with  the  presence 
of  frictional  tread  force,  enhance  the  depletion  of  metal  from  the  surface  layer  of 
rail  metal  through  flaking. 

In  summary,  the  amount  of  plastic  flow  and  flaking  are  functions  of  the  verti- 
cal load,  contact  geometry,  frictional  tread  force,  initiation  and  propagation  of 
surface  cracks,  all  of  which  are  random  functions  in  time  and/or  spatial  position. 
As  a  consequence,  the  rate  of  plastic  flow  and  the  rate  of  flaking  are  also  random 
functions  with  time  and/or  spatial  position  and  are  therefore  most  conducive  to 
the  growth  of  rail  corrugations.  As  the  dynamical  loads  become  more  severe,  the 
rate  of  corrugation  formation  and  propagation  accelerates. 

4.  METHODS  TO  REDUCE  OR  ELIMINATE  RAIL  CORRUGATIONS 

Perhaps  the  best  way  to  prevent  or  reduce  the  formation  of  rail  corrugations 
is  to  eliminate  or  alleviate  the  principle  contributing  factors.  These  factors  may  be 
categorized  as  follows: 

a)   Wheel  Rail  Contact  Geometry 

In  this  area,  it  is  desirable  to  eliminate  high  contact  stresses  which  contribute 
to  plastic  flow  and  early  development  of  surface  fatigue  cracks.  Possible  measures 
to  accomplish  the  above  involve: 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein 


445 


DISCHARGE 
DIRECTION 
OF  FLAKED 
METAL 


FIGURE  14:   RELATIVE  POSITIONS  OF  WHEEL  ON  RAIL  DURING  CURVE 
NEGOTIATION 

(A)  HIGH  RAIL 

(B)  LOW  RAIL 


446       Bulletin  656 — American  Railway  Engineering  Association 


ij  2J    3i 


WHEEL 


LOW    RAIL 


SECTION    1-1 


(A) 


SECTION    2-2 


FIGURE    15:       SIMPLIFIED    MECHANICS    OF    CRACK    PROPAGATION 


Regional  Meeting  Address  by  J.  Kalousek,  R.  Klein 447 

i)   Elimination  of  Wide  Gauge  in  Track 

Alle\iati()n  of  wide  gauge  may  be  achiexed  by  installation  of  longer  tie 

plates,    gauge   rods,   hardwood   ties,   concrete   ties,   and/or  other   possible 

measures, 
ii)   Elimination  of  False  Flanges  on  Wheels 

Improvement  may  be  accomplished  by  changing  the  condemning  limits 

on    wheels,    relocation   of   brake    shoes    into    "overhang"   position   and/or 

other  measures, 
iii)    Reduction  of  Railhead  Curvature 

Reduced  stresses  would  result  if  the  field  side  of  the  low  rail  was  ground 

to  a  shallower  radius  immediately  after  being  placed  in  track, 
iv)   Modification  of  AAR  Wheel  Profile 

Appropriate  changes  in  wheel  profile  may  decrease  the  level  of  contact 

stresses  and  flange  wear. 

b)  Lateral  Frictional  Force 

Flange  contact  may  be  minimized  by  installation  of  self-steering  trucks  into 
unit  trains.  A  few  experimental  designs  of  self-steering  trucks  were  recently  devel- 
oped and  tested.  The  results  of  test  programs  are  encouraging;  however,  the  full 
utilization   of  self-steering  trucks  is  hampered  by  high  cost. 

c)  Surface   Fatigue   and  Plastic  Flow 

Improvements  with  respect  to  surface  fatigue  and  plastic  flow  may  best  be 
achieved  through  improvements  in  rail  metallurgy.  The  objective  of  such  improve- 
ments would  be  to  increase  rail  strength  and  hardness  while  maintaining  ductility 
and  fracture  toughness. 

d)  Friction,   Lubrication  and  Wear  (Trihology) 

In  tliis  area,  an  improved  lubrication  policy  should  be  developed,  which  would 
ensure  proper  lubrication  in  the  zone  of  flange  contact  and  prevent,  at  the  same 
time,  accumulation  of  grease  on  the  top  surface  of  the  low  rail.  The  resulting  in- 
creased natural  wear  on  the  running  surface  of  low  rail  would  delay  development 
of  surface  fatigue  defects  and  thus  decrease  the  need  for  grinding.  An  optimized 
lubrication  practice  would  provide  an  additional  benefit  of  improved  adhesion  for 
traction. 

e)  Dynamic  Loadings 

Any  measures  aimed  at  reduction  of  the  magnitude  of  dynamical  loadings 
through  improvements  in  the  design  of  rolling  stock  and  track  maintenance  will 
considerably  alleviate  the  pace  of  corrugation  formation  and  propagation. 

It  is  certain  that  a  combination  of  the  above  changes  will  have  to  be  imple- 
mented, in  the  ne.xt  few  years,  by  those  railways  in  Nortli  America  that  are  at  or 
approaching  traffic  levels  of  40  MGT  per  year  on  sections  of  their  lines. 

REFERENCES 

1.  P.  R.  Nayak:  "Contact  Vibrations  of  a  Wheel  on  a  Rail",  Journal  of  Sound  and 
Vibration  (1973)  23(2)  277-392. 

2.  K.  Werner:  "Corrugation  and  Pitting  of  Rolling  Surfaces — Are  They  Contingent 
Upon  Ultrasonics?"  Wear  32,  (1975)  233-248.  (Originally  appeared  in  German 
in  "Eisenbahntechnische  Rundschan"  22(1973)    142-149). 


1 


448        Bulletin  656 — American  Railway  Engineering  Association 

3.  M.    Srini\asan:    "Prevention    and    Cure    of    Rail    Corrugation",    Railway    Gazette 
International,  March   1975. 

4.  R.  G.  Read:   "The  Rail  for  High  Intensity  Mineral  Traffic",  AREA  Bulletin  No. 
639  (1974)   38-59. 

5.  F.  E.  King:  "Tests  on  B.C.  South  Line  Clearwater  Subdivision",  CNR  Technical 
Research  Report,  February  28,  1975. 

6.  J.    Kalousek:    "Track/Train    Dynamics    Report    No.    4 — Rail    Corrugations",    CP 
Department  of  Research,  Report  No.  S488-75,  February  1975. 

7.  "Effective  Correction  of  Long-Wave  Rail-Surface  Corrugation  Wear  on  Finnish 
State   Railways".    Rail   Engineering   International,   February-March    1975,   74-75. 


Rock  Slope  Stability  on  Railway  Projects 

by 

C.   O.   Browner,   P.   Eng. 

Principal, 

and 

Duncan   Wyllie,   P.   Eng. 
Senior   Engineer 

Colder   Associates 
Consulting    Geotechnical    Engineers 

INTRODUCTION 

There  has  been  a  general  increase  in  rail  traffic  through  the  western  mountain 
regions  of  Canada  and  the  United  States  in  recent  years;  for  example,  traffic  on  the 
Canadian  Pacific  in  the  Pacific  Region  has  almost  doubled  since  1968.  With  much 
of  the  rail  lines  constructed  in  tortuous  mountain  terrain,  numerous  high  soil  and 
rock  cuts  result. 

It  has  been  a  common  concept  that  because  most  of  these  cuts  are  over  50 
to  over  100  years  old  the  slopes  have  become  stabilized  vdth  time.  In  actual  fact  the 
increase  in  frequency,  weight  and  length  of  trains  in  the  past  decade  is  increasing 
stress  in  the  trackside  slopes.  As  a  result,  unless  stabilization  programs  are  devel- 
oped, an  increase  in  rock  fall  and  slope  failures  can  be  expected  as  the  volume  of 
traffic  continues  to  increase. 

A  number  of  failures  have  occurred  recently  that  have  caused  derailments  and 
loss  of  life.  In  addition,  the  courts  in  Canada  no  longer  accept  slides  as  an  "Act  of 
God." 

Fortunately  our  knowledge  of  rock  mechanics  and  rock  slope  stability  has 
increased  greatly  in  the  past  decade.  (Brawner  1966,  1967,  Brawner  and  Milligan, 
1971,  Hoek  and  Bray  1974.)  Based  on  this  knowledge  and  experience  it  is  now 
possible  to  define  most  of  the  potential  areas  of  rock  instability  and  to  develop  a 
rational  and  practical  program  to  improve  stability. 

This  paper  defines  the  factors  which  contribute  to  instability  of  rock  slopes 
and  outlines  procedures  to  improve  stability.  Specific  recommendations  are  sug- 
gested for  new  construction.  To  illustrate  an  effective  approach,  the  recent  program 
developed  for  the  Canadian  Pacific  is  described. 

FACTORS  WHICH  INFLUENCE  ROCK  SLOPE  STABILITY 

Rock  slope  staliility  is  influenced  by  many  factors.  In  order  to  assess  potential 
problems  it  is  necessary  to  be  familiar  with  these  factors.  In  addition  the  program 
of  stabilization  selected  must  take  into  consideration  the  cause  of  instability. 

One  of  the  basic  concepts  is  that  the  assessment  of  stability  must  be  based  on 
the  geologic,  hydrologic,  climatic,  topographic,  rail  traffic  and  environmental  con- 
ditions at  the  specific  site.  Most  important  of  all  are  the  geologic  conditions.  Since 
the  structural  geology  conditions  frequently  differ  greatly  over  short  distances,  each 
rock  slope  must  be  investigated  individually.  The  more  important  factors  which 
influence  stability  are  summarized  below. 

449 


450        Bulletin  656 — American  Railway  Engineering  Association 

a.  Geologic  Conditions 

Rock  which  is  sound  or  has  joints  which  are  discontinuous  over  short  distances 
and  which  are  randomly  oriented  will  stand  vertically  for  great  heights.  The 
theoretical  height  for  a  vertical  slope  is  given  by: 

Qu  Where  He  is  the  vertical  height  of  the  slope  in  feet 

^r  Q„  is  the  unconfined  compressive  strength  in  Ib/scj  ft 

W,  is  the  unit  weight  of  the  rock  in  pounds. 

For  example  for  a  soft  rock  with  a  strength  of  3000  psi  the  vertical  height 
computed  is  about  2600  ft. 

In  nature,  vertical  slopes  of  this  magnitude  are  unusual.  Consequently  it  is 
apparent  that  weaknesses  in  tlie  rock  dicLate  the  maximum  height  and  angle  at  which 
the  slope  will  be  stable.  These  weaknesses  include  faults,  shears,  joints,  bedding 
planes,   zones   of   weathering   or   hydrothermal   alteration. 

When  these  weaknesses  exist  the  most  important  factor  is  the  orientation  and 
dip  of  the  weakness  relative  to  the  slope.  Figure  1  illustrates  various  orientations 
of  weaknesses.  The  most  critical  conditions  are  weaknesses  or  combinations  of  weak- 
ness which  dip  out  of  the  slope.  In  these  instances  if  tlie  shear  strength  along  the 
discontinuity  is  exceeded,  failure  will  occur.  The  shear  strength  is  influenced  by  the 
roughness  along  the  discontinuity  and  presence  of  weak  material,  such  as  fault  gauge, 
altered  infill,  calcite  stringers,  etc. 

b.  Groundwater 

The  frictional  force  developed  along  a  discontinuity  is  proportional  to  the  nor- 
mal force  acting  on  the  failure  plane.  If  water  exists  in  the  discontinuity  the  normal 
force  is  reduced  by  the  buoyant  force  exerted  by  the  water.  With  a  water  table 
near  ground  surface  the  factor  of  safety  of  a  rock  slope  is  about  35  per  cent  less 
than  that  if  the  slope  were  drained. 

In  areas  where  freezing  temperatures  occur  stability  can  be  reduced  as  a  result 
of  freezing  of  the  surface  of  the  slope.  This  restricts  drainage  and  may  result  in  the 
build  up  of  cleft  water  pressures  in  the  slope. 

c.  Climatic  Conditions 

The  seasonal  variations  range  from  cold  winters  with  heavy  snowfall  to  hot 
summers  with  occasional  heavy  rainstorms.  The  major  effects  of  the  weather  on 
slope  stability  other  than  changes  in  ground-water  levels,  are  the  combination  of 
freeze-thaw,  wet-dry  and  chemical  alteration.  When  water  accumulates  in  cracks 
and  freezes,  the  forces  of  expansion  can  be  sufficient  to  move  considerable  masses 
of  rocks  and  stability  can  deteriorate  with  time.  Conditions  are  normally  most  critical 
during  freeze/thaw  and  snow  melt  periods  in  the  spring. 

In  tropical  climates  severe  weathering  effects  are  likely  to  have  a  great  influence 
on  staliility. 

d.  Vibration 

Vibration  stress  due  to  train  traffic  can  lead  to  rock  fall  or  slope  failure.  The 
frequency  and  length  of  the  vibration  influences  the  stability.  Unit  trains  provide  a 
more  uniform  frequency,  and  the  great  length  of  these  trains  increases  the  length  of 
time  the  vibration  occurs.  Both  factors  tend  to  reduce  stability. 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  451 

e.  Blasting 

Excavation  techniques  used  in  railway  construction  up  until  about  5  to  10 
years  ago  gave  little  consideration  to  the  effect  upon  the  rock.  Figure  2  (a)  shows 
the  general  relationship  between  weight  of  explosive,  distance  from  the  blast  point 
and  particle  velocity,  which  can  be  related  to  rock  damage.  It  should  be  readily 
apparent  that  the  amount  of  explosives  detonated  at  one  time  should  be  limited. 
This  can  be  done  readily  by  using  delays. 

Great  advances  have  lieen  made,  particularly  in  Sweden,  to  develop  controlled 
blasting  (Langefors  and  Kihlstrom,  1967).  Preshear  and  cushion  techniques  now 
allow  many  rock  slopes  to  be  excavated  steeper  and  with  lower  maintenance  re- 
quirements. Figure  2   (b). 

f.  Earthquakes 

Much  of  the  west  coast  of  North  America  is  in  an  earthquake  active  zone.  The 
present  state  of  the  art  does  not  yet  allow  prediction  or  warning  of  earthquakes. 
Large  earthquakes  can  cause  major  slides  in  rock,  e.g.,  the  major  slide  on  the  Madison 
River  in  West  Yellowstone,  Montana,  caused  by  an  earthquake  with  a  magnitude  of 
7.5  to  7.8  on  the  Richter  scale.  Lesser  earthquakes  will  frequently  result  in  localized 
rock  fall. 

Types  of  Rock  Instability 

In  order  to  assess  the  potential  of  rock  instability  it  is  essential  to  define  the 
types  of  failure  that  present  the  greatest  hazard  to  the  operation  of  a  railway. 
Different  types  of  failure  and  different  causes  of  failure  require  different  methods 
of  stabilization.  The  most  frequent  types  of  instability  and  the  most  common  asso- 
ciated causes  are  summarized  in  Figure  3. 

The  great  influence  that  geology  and  water  have  on  stability  must  be  recognized. 

Evaluation  of  Stability 

The  evaluation  of  rock  stability  is  frequently  best  considered  in  two  stages. 
Stage  1  is  the  gathering  of  relevant  geological,  topographic,  climatic,  hydrologic  and 
train  operating  data  incorporating  a  site  inspection  and  site  mapping.  Air  photo 
interpretation  is  frequently  very  useful  at  this  stage.  Frequently  evaluation  of  data 
obtained  from  this  program  will  be  sufficient  to  assess  stability  and  if  a  potentially 
dangerous  situation  is  believed  to  exist,  a  program  to  improve  stability  can  be 
developed.  Where  the  potential  of  instability  is  primarily  a  danger  of  local  rockfall, 
a  Stage  1  program  is  usually  adequate. 

When  the  initial  study  reveals  the  potential  of  large-scale  failure  or  failure 
which  could  have  serious  consequences,  a  more  extensive  investigation  may  be 
necessary.  This  may  include  the  necessity  to  drill  boreholes,  and  orient  the  core 
by  down-the-hole  photography,  borehole  periscope  or  other  means.  The  performance 
of  shear  tests  on  joints  or  infill  material,  detennination  of  water  pressure  in  the 
joints  using  piezometers  and  the  performance  of  stability  computations.  These  tech- 
niques are  reasonably  well  developed.   (Hoek,   1975). 

Figure  4  shows  typical  equipment  used  for  such  studies. 

Very  few  engineers  have  extensive  experience  in  rock  mechanics  so  that  advisors 
or  consultants  should  be  selected  only  after  a  thorough  assessment  of  thei;r 
qualifications. 


452        Bulletin  656 — American  Railway  Engineering  Association 

Methods  of  Control 

Three  major  approaches  may  be  used  separately,  or  in  combination  in  the 
development  of  a  realistic  program  to  control  stability. 

1.  Stabilization. 

2.  Protection. 

3.  Warning  Systems. 

The  prime  purpose  is  to  provide  a  reasonably  practical  degree  of  safety  within 
the  limits  of  a  justifiable  expenditure  of  dollars.  However,  it  must  be  recognized 
that  it  is  physically  impossible  to  protect  the  railway  against  all  possible  failures. 
While  our  kowledge  in  the  field  of  rock  mechanics  is  advancing  rapidly  it  is  not 
economically  or  practically  possible  to  locate  or  predict  all  of  the  potentially  unstable 
areas,  and  secondly,  that  the  money  required  to  provide  nearly  100  per  cent  safety 
is  extremely  high. 

1.  Stabilization — Stabilization  of  rock  slopes  is  justified  where  the  cause  and 
extent  of  failures  or  potential  failures  can  be  defined  and  where  the  cost  of  the 
stabilization  can  be  justified. 

The  method  and  extent  of  the  stabilization  program  must  be  based  on  a  definitive 
site  investigation. 

Stabilization  procedures  include  the  following: 

•  Excavation  or  resloping. 

•  Drainage  (surface  and  subsurface). 

•  Surface  stabilization. 

•  Support  systems. 

Details  and  comments  for  stabilization  procedures  are  shown  in  Figures  5,  6, 
7,  8  and  9. 

2.  Protection — ^Protection  involves  the  prevention  of  rock  from  falling  on  the 
track.  The  type  of  protection  depends  on  the  volume,  size  and  frequency  of  potential 
falling  rock,  the  geometry  of  the  slope  (rolling  or  free  falling  rock  potential)  and 
the  frequency  and  type  of  train  traffic. 

Where  large  volumes  of  falling  rock  occur  very  expensive  procedures  such  as 
tunnels  or  rock  sheds  can  be  justified.  At  other  areas,  slope  or  ditch  treatment  will 
frequently  be  eftective. 

One  of  the  most  eftective  procedures  is  to  develop  deep  catchment  ditches  on 
the  inner  side  of  the  track.  Alternatively,  catch  walls  can  be  constructed.  One  of 
the  most  efficient  and  economical  types  is  the  gabion  wall  which  can  be  varied  in 
height  and  is  flexible  under  impact. 

Where  rock  slopes  exist  at  sidings,  consideration  should  be  given  to  using  the 
outer  track  for  the  mainline  traffic. 

Details  and  comments  of  protection  procedures  are  given  in  Figures  10,  11 
12  and  13. 

3.  Warning  Systems — Warning  systems  are  used  where  occasional  falls  are 
expected  but  it  is  believed  the  cost  of  protection  or  stabilization  would  be  extremely 
difficult  and  expensive. 

The  most  common  warning  system  comprises  electric  fences.  These  are  usually 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  453 

connected  into  the  signal  system.  Witli  this  method  there  is  less  than  100  per  cent 
probability  of  providing  sufficient  warning  to  the  locomoti\e  engineer  so  he  can 
stop.  For  example,  if  the  slide  or  fall  occurs  while  die  train  is  in  the  block  the  engi- 
neer will  not  be  warned.  In  addition  some  slides  are  caused  by  train  vibration.  In 
these  instances  the  slide  ma\'  hit  the  train  behind  the  locomotive.  The  Japanese  have 
transmitters  connected  to  fences  which  improve  the  probability  of  warning. 

Ice  and  snow  in  the  winter  frequently  cause  the  wires  to  break.  A  combined 
heating  and  signal  cable  is  suggested  as  a  solution. 

In  many  locations  single  wire  warning  systems  would  be  inadequate. 

One  point  of  caution  is  made.  Whenever  a  warning  fence  is  installed  it  will 
probably  become  a  permanent  installation.  Even  if  stabilization  is  carried  out  later, 
transport  commissions  or  unions  may  oppose  its  removid. 

Prior  to  the  installation  of  warning  fences  any  obvious  precarious  rock  on  the 
slope  should  be  removed  or  scaled. 

Considerable  research  is  being  carried  out  to  improve  warning  systems.  Such 
program  includes  vibration  meters,  robot  patrols,  TV  monitoring,  guided  radar,  laser 
detection,  etc.  None  of  these  as  yet  has  been  developed  to  a  state  of  economical 
acceptability. 

Details  and  comments  for  warning  procedures  are  given  in  Figure  14  and  15. 

New  Construction 

New  railway  construction,  particularly  for  resource  development  and  recon- 
struction to  provide  double  trackage,  reduced  grades  or  curvature  may  require  rock 
exca\ation.  The  past  practice  has  generally  been  to  specify  that  new  slopes  in  rock 
be  cut  to  }i  to  1  and  that  shallow  "V"  type  ditches  be  used.  These  slopes  were  not 
designed  according  to  the  strength  or  quality  of  the  rock.  With  the  knowledge  that 
now  exists  in  rock  mechanics,  the  stable  slope  angle  can  be  determined  with  reason- 
able success  and  at  reasonable  cost. 

Where  the  rock  strength  or  where  the  geologic  structiue  is  favorable  rock 
slopes  can  be  cut  vertical.  This  will  reduce  quantities,  allow  wider  ditches  to  be 
used  and  result  in  rock  falls  dropping  vertically  into  the  inner  ditch  instead  of 
bouncing  or  rolling  onto  the  track.   (See  Figure  16). 

Where  geologic  structural  weaknesses  dip  out  of  the  slope  at  a  steep  angle 
the  slope  should  be  cut  to  this  angle.  Figure  1   (c). 

Controlled  blasting  using  preshear  or  cushion  blasting  should  be  specified  for 
the  excavation  of  all  rock  slopes  where  the  geologic  structure  is  oriented  favorably 
for  stability.  The  rock  in  the  slope  will  be  subjected  to  less  damage  due  to  seismic 
acceleration  forces  which  can  break  rock  and  open  joints  for  tens  of  feet  back  from 
the  slope.  As  a  result  steeper  slopes  can  be  excavated  and  the  slopes  will  ravel  less, 
requiring  much  less  maintenance  over  the  years.  Figure  17  shows  cut  slopes  de- 
veloped using  controlled  blasting. 

A  Typical  Rock  Stability  Program 

To  illustrate  a  working  approach  to  the  development  of  a  rock  stability  program 
with  the  \iew  to  reduce  the  risk  of  slides  and  rock  falls  and  to  reduce  maintenance 
costs,  the  program  developed  with  the  Canadian  Pacific  on  over  1500  miles  of  track 
is  described. 

For  Stage  1,  a  review  of  air  photograplis,  topographic  maps,  climatic  data  and 
railway  plans  was  performed.  This  was  followed  by  an  inspection  of  cut  slopes 
along  the  track  by  motor  car  with  a  division  engineer,  a  roadmaster  or  an  assistant 
roadmaster.    The   stability   of   the    slopes   was   rated   into   five   categories    ( Table    1 ) 


454        Bulletin  656 — American  Railway  Engineering  Association 

according  to  an  estimate  of  the  probability  of  failure.  This  took  into  account  the 
geology  and  rock  conditions,  slope  geometry,  ditch  dimensions,  hydrology  and  slope 
seepage  and  past  experience  with  slides  or  falls  at  the  site. 

A  program  was  instituted  to  record  all  slides  and  rock  falls  of  a  size  that  could 
be  dangerous  to  train  traffic.  This  form  included  data  on  time,  location,  size,  sight 
visibility,  weather  conditions  preceding  movement,  type  and  size  of  movement, 
estimated  cause  of  movement,  problem  created,  action  taken.  Forms  such  as  this 
lend  themselves  to  computer  punch  cards  and  computer  retrieval  at  a  later  date. 
Areas  of  more  frequent  occurrences  should  be  investigated  in  detail  on  a  priority 
basis  to  assess  the  need  and  method  of  improving  stability. 

A  lecture  and  site  inspection  workshop  was  prepared  and  attended  by  engi- 
neering staff,  roadmasters  and  foremen.  This  program  described  the  influence  of 
geology,  groundwater,  vibration  and  climatic  conditions  on  stability,  outlined 
methods  of  assessing  stability  and  described  procedures  for  stabilizing  the  rock  slopes. 
Numerous  case  examples  were  reviewed. 

For  the  Stage  2  program,  priority  areas  where  stabilization  was  considered 
to  be  the  most  urgent  were  established,  a  detailed  inspection  was  made  of  each, 
stabilization  requirements  were  defined  (Figure  18),  and  specifications  were  pre- 
pared. Construction  commenced  on  these  priority  areas  and  continues  until  the 
annual  budget  allocation  is  expended.  At  this  time  further  priority  areas  are  being 
defined  to  establish  next  year's  program. 

REFERENCES 

Brawner,  C.  O.,  1966,  "Slope  Stability  in  Open  Pit  Mines,"  Western  Miner,  October 
1966. 

Brawner,  C.  O.,  1967,  "Rock  Slope  Stability  in  Highway  Construction,"  48th  Con- 
ference, Canadian  Good  Roads  Association,   1967. 

Brawner,  C.  O.  and  Milligan,  V.,  1971,  editors,  "Stability  in  Open  Pit  Mining,"  The 
American   Institute   of   Mining   Engineers,   New   York. 

Hoek,  E.  and  Bray,  J.  W.,  1974,  "Rock  Slope  Engineering,"  The  Institution  of 
Mining  and  Metallurgy,  London. 

Langefors,  V.  and  Kihlstrom,  B.,  1967,  "The  Modern  Technique  of  Rock  Blasting," 
John  Wiley  and  Sons. 

Ritchie,  A.  M.,  1963,  "The  Evaluation  of  Rockfall  and  its  Control,"  Highway  Record, 
Vol.   17. 


{ 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  455 


(a)   Massive  granite  rock.   Joints 
have  random  orientation.   This 
slope  can  be  cut  vertically 
with  controlled  blasting. 


')   Bedded  slate  with  joints  dipping  out 
of  the  slope  at  55*^.   This  dip  angle 
contro;iled  the  allowable  slope  angle. 


(b)   Horizontally  bedded  soft 

sedimentary  rock.  Favorable 
structural  orientation  will 
allow  vertical  slope. 


BSI 

1 

i 

/ 

•%% 

* 

r::- 

<'/ 

^ 

1 

{d)      Bedded  rock  dipping  into  slope. 

Ravelling  will  occur  due  to  cantilever 
type  toppling  failure.  Slope  angle  of 
70°-75°  suggested. 


Figure  1  -  Rock  slopes  with  different  orientations  of  structural  geologic 
weaknesses,  each  of  which  influences  stability  and  stable  allowable  slope 
angle. 


456       Bulletin  656 — American  Railway  Engineering  Association 


O     U)    J3     V4     dJ     (0    .-t 


u  D  nj  -o  r-i        1-1 

C  T3  j:    0)  W    0)   -H 

3  O  <U  1-1  (-1    3    (0 

•-H  o  a  o  oj 

•j-i  >j  o   P  S 


dJ   c   1-1    a   dj 
■u  iJ   a.  00  H 


O    4J   H   T3     0) 


iH 

<u 

O 

J= 

> 

tn 

TJ 

U) 

aj 

cfl 

o 

a 

(fl 

0)     3   T3   13 
<1)  iJ     D*    4)    -H 


EU-lOU0Cn4J,H 
O    -H     O     X     U     ttJ    -H     O 


aoNvu  Noisao 


141)  M  '^otifi   jta    iftjDip  JO    igftiiM    umiiniM 


<u 

U) 

CI. 

oc 

(U 

o 

<fl 

U) 

r-i 

M 

n) 

0) 

<U 

<U 

x: 

> 

t-i 

4) 

4J 

(0 

u 

x; 

H 

c 

4-1 

u 

•H 

:^ 

O 

>^ 

tC 

(U 

4-1 

4-1    rH     N     C    JD 
•H     01   -H    -H     « 


^     Vj     4)     O     C 


« 

(U 

V    &0 

« 

■H 

> 

a.  t-i 

XI 

U-l 

01 

OJ  jC 

u 

0 

8 

r-H 

00  o 

4; 

o 

M 

j= 

J^ 

£ 

•H 

rt   4) 

4J 

to 

8 

4J 

^  j= 

U 

■H       • 

M 

O     4-J 

tfl 

u    m 

O 

N 

1 

D-14-4      W 

4-1 

4J 

S 

6 

o  < 

U3 

41     0 

a 

T3 

4-1     0 

3 

4J 

C 

CO 

X 

a 

£ 

OJ 

4)     OJ 

•H 

00    • 

4-1 

M    a 

o 

X 

•H    ^^ 

X 

00  c 

^ 

n) 

4)  m 

41 

rt 

B 

U    C 

rt    c 

o 

01 

41 

U-l 

T3    -H 

00 

C     4-1 

0 

C    4J 

(fl 

•H     C 

n)   -H 

^ 

•H 

c 

TD 

cfl 

00  (0 

0 

01  c 

41 

C    B 

•H 

u  o 

U 

•H 

4-1 

d  o 

X 

4-1     M 

D 

rt 

M    4; 

•H 

4-1    ^ 

^ 

3   X 

1-1 

w    o 

0 

a)    00 

CO    -H     O    O     4)   -H 
>    T3     M    >-<     M    X 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  457 


TYPE  OF  INSTABILITY 

FREQUENCY  OF  OCCURRENCE 

MOST  COMMON  FACTORS 
CONTRIBUTING  TO  INSTABILITY 

Rock  Slides 
(100  cu.  yds.  or 
more) 

Very  infrequent 

Geological  weaknesses  bounding  large 
rock  volumes  which  dip  out  of  the 
slope.   Weak  and  weathered  rock. 
High  water  pressures.   Vibrations 
from  trains.    Earthquakes. 

Block  or  Wedge 
Failures 

Infrequent 

Geological  weakness  bounding  blocks 
or  wedges  of  rock.   High  water 
pressures.   Adverse  climatic 
conditions  or  variations.   Vibrations 
from  trains.   Earthquakes. 

Rock  Falls 

Ranges  from  high 
frequency  in  steep 
blocky  rock  to 
Infrequent  in  massive 
rock. 

Weathering,  temperature  change, 
freezing  and  thawing,  wetting  and 
drying,  water  pressures  in  joints, 
root  prying,  joints  dipping  out  of 
the  slope,  vibration  of  trains, 
presence  of  weak  gouge  in  faults  and 
shear  zones  which  dip  out  of  slope. 
Some  falls  originate  well  above 
right-of-way.   Poor  blasting  control 
on  new  projects. 

Running  Slopes  - 
Boulders  and  Talus 

Frequent  in  areas  of     Slopes  originally  cut  steeper  than 
talus,  till  slopes       the  angle  of  repose,  erosion  under- 
and  coarse  gravel        cutting  boulders  or  more  resistant 
slopes.                 rock. 

Debris  Avalances 

Infrequent 

Slides  and  trees  falling  into  and 
carrier'  by  water  in  gullies  and  by 
snowslides. 

Slope  Erosion 

Frequent  in  areas  of 
high  precipitation. 
More  probable  on  new 
construction. 

Heavy  to  very  heavy  precipitation 
or  snow  melt  on  exposed  slopes. 
Frequently  more  of  a  problem  on 
slopes  on  new  construction. 

FIGURE  3  -  TYPES  AND  CAUSES  OF  INSTABILITY 


458        Bulletin  656 — American  Railway  Engineering  Association 


T3    O    >s   (K 


■a     C   J3     CD    >^ 

(1)   m   nj  -H  u 


COO        ra 

0)   -H   U-i     >,,  4-1 


^   01   ij   n 


a 

o 

^ 

■H 

C 

ffl 

<u  <u   u 

t) 

•H 

o 

a  E   <u 

3 

o 

o 

•rt 

ig  u 

o- 

01 

u 

Ji 

m 

<u 

<U    -H    -H 

W 

oo 

n 

3 

r-l    73    T3 

U-l 

■u 

O 

o 

o 

f 

iH 

o 

en 

•H 

j: 

X    0)    0) 

n 

>4 

QJ 

QJ    oo    00 

-a- 

Vj 

j= 

T! 

0) 

^J 

i-i  ^   b 

3 

4J 

V 

Ul 

0 

d) 

oc 

.H 

m 

m  J  J 

u 

u 

r. 

•H 

01 

3 

3 

V 

ra 

>-l 

Oil 

U 

M 

4J 

(11 

,-^ 

^-^  ^^  ^^ 

■H 

u 

■1-' 

OJ 

X 

ra 

J3   <j  -a 

It.    to    m  o    3 


/ 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie 


459 


(a)   EXCAVATION 


(1)   Scaling 

See  Fig.  6(d)  (b) 


(11)  Trimming 

See  Fig.  6(c) 


(ill)  Slope  Flattening 


(b)   DRAIKAGE 


(1)   Runoff  Diversion 
See  Fig.  7(c) 


(il) 


Slope  Drainage 
See  Fig.  7  (a)  (b) 


(ill)   Ice  Glacier 
Reduction 


Most  applicable  to  rock  faces  with  Infrequent 
randon  oriented  geologic  discontinuities. 
Generally  required  at  least  once  every  tvo 
years  in  areas  of  extreme  climatic  conditions 
(Rain,  snow,  numerous  freeze-thaw  cycles). 

A  geologic  appraisal  can  successfully  locate 
most  rocks  that  should  be  scaled.   Normally 
not  recommended  where  much  of  the  rock  joints 
dip  out  of  the  slope  or  where  very  blocky  rock 
exists.   Perforned  by  hand  from  ropes  or  boons. 
Use  explosives  with  care  as  vibration  may  loosen 
other  rocks. 

Develop  hydraulic  scaling  tools. 
A  basic  stabilization  technique. 

Rock  promontories  or  larger  blocks  nay  require 
removal.    Usually  by  drilling  and  blasting. 
Use  parallel  drill  holes  wherever  possible  and 
drill  parallel  to  required  face  line. 

Where  excessive  rock  falls  occur  or  where  the 
Joints  or  bedding  dips  out  of  slope  the  slope 
can  be  flattened.   A  uniform  slope  may  be 
used  or  the  cut  can  be  benched.    The  bench 
should  be  wide  enough  to  clean  out  since 
falling  rock  from  above  may  bounce  from  a 
debris  filled  bench  onto  the  track.    The  sane 
procedure  can  be  used  for  gravel,  till  and 
boulder  slopes. 


Ifliere  water  runs  over  the  face  of  the  slope 
attempts  should  be  made  to  intercept  and 
divert  the  water  behind  the  crest.    Ditches 
may  require  lining. 


The  most  common  method  is  to  drill  horizontal 
drain  holes  into  the  slope  on  10  to  25  ft. 
centers  to  distances  of  at  least  20  ft.  and 
not  more  than  0.25  times  the  slope  height. 
If  the  holes  collapse  perforated  plastic  pipe 
should  be  installed.    If  ice  glaciers 
develop  the  drains  oust  be  Insulated  or 
heated  with  heating  cables.    A  track  mounted 
percussion  unit  could  be  designed  for  rapid 
Installation.    The  drains  are  particularly 
effective  in  soft  rock. 
A  basic  stabilization  technique. 

Some  of  the  slope  face  seepage  which  freezes 
can  usually  be  intercepted  in  the  slope  with 
horizontal  drain  holes.    They  nay  require  a 
steep  inclination  or  installation  under  the 
track.   The  concept  is  to  lower  the  water 
level  in  the  slope.   At  bad  locations 
electric  or  propane  radiant  heaters 
installed  on  poles  and  directed  at  the 
glacier  area  could  control  the  freezing. 


Figure  5 — Summary  of  stabilization  procedures  for  rock   slopes. 


460        Bulletin  656 — American  Railway  Engineering  Association 


(c)   SURFACE  STABILIZATION 


(1)   Shotcrete 
See  Fig.  e 


(ii)  Shotcrete  plus 
vlre  mesh 


(ill)  Dry  rock  walls 
on  slope. 


(d)   SUPPORT  SYSTEMS 


(1)   Buttresses 

See  Fig.  9  (a)  (b) 


(11)  Rock  Bolts  and 
Cables 
See  Fig.  9  (d) 


(111)   Rock  Douells 


(Iv)   Anchor  BeaBs  and 
Kails 


(v)   Bolted  Wire  Mesh 
See  Fig.  9  (c) 


Sprayed  on  concrete  to  minimize  further  slope 
face  deterioration  and  to  seal  exposed  Joints. 
Particularly  applicable  to  blocky  slopes. 
Surface  must  be  cleaned  and  wetted  prior  to 
application.    Thickness  of  14-2  Inches  normally 
adequate.    Not  necessary  to  cover  massive 
faces  -  only  8-10  Inches  beyond  Joints. 
Frequent  drain  openings  must  be  left  so  water 
pressure  does  not  build  up.    Can  use  pipes  or 
leave  occasional  joints  unshotcreted. 
A  basic  stabilization  technique. 

Where  the  rock  is  very  blocky  and  the  blocks 
are  small  the  shotcrete  may  require  reinforce- 
ment.   Wire  mesh  can  be  pegged  to  the  face  and 
shotcreted  over.    The  wire  mesh  size  depends  on 
rock  conditions  and  slope  height. 

Where  shallow  rock  or  soil  slopes,  are  ravelling 
•a  dry  rock  wall  face  can  provide  support  and  will 
be  free  draining.    The  base  rocks  must  be  on  a 
firm  foundation. 


Used  to  support  large  volumes  of  rock  which  would 
otherwise  have  to  be  excavated  or  where  key  rocks 
retain  large  volumes  above.    Ensure  the 
buttress  is  designed  to  take  the  line  of  thrust. 
May  require  reinforcing  or  anchor  grouting  to 
the  rock  mass.    Can  be  built  up  with  shotcrete. 
For  smaller  volumes  may  consist  of  dry  rock 
packing. 

Used  to  tie  key  rocks  which  if  removed  would 
undermine  support  for  other  rocks.    For  smaller 
blocks  use  bolts  for  large  blocks,  consider 
cables.    To  develop  maximum  stability  they 
should  be  tensioned  and  then  grouted  full  length. 

This  Increases  shear  strength  of  the  joint, 
prevents  stress  relaxation,  and  minimizes 
corrosion.    Rock  bolt  installations  should 
be  properly  designed  to  develop  a  conputed 
load.    Special  bolt  head  design  may  be 
necessary  in  soft  rock.    May  be  used  in 
conjunction  with  shotcrete.    A  basic 
stabilization  technique. 

Dowells  conprising  reinforcing  steel  or  scrap 
rail  can  be  grouted  into  drill  holes  located 
at  the  toe  of  rock  blocks  to  prevent  then  fron 
sliding.    The  size,  depth  and  spacing  of  the 
dowells  depends  on  the  rock  block  size  and 
slope  angle  of  the  joint. 

Anchored  beams  can  be  used  to  support  larger 
areas  of  rock  face.    May  be  used  in  conjunction 
with  shotcrete  and  wire  mesh.    Usually  very 
expensive. 

May  be  used  where  large  areas  of  a  rock  face 
contains  blocky  Jointed  rock.    Use  corrosion- 
resistant  mesh.    Mesh  size  depends  on  rock 
size  and  bolt  spacing. 


Figure  5  (continued) 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  461 


OJ 

cn 

x: 

3 

C 

4-1 

Xi 

•H 

•H 

ca 

CO 

U 

CO 

u 

u 

(U 

S>M1-. 

03 

c 

> 

rH 

c 

o 

o 

<Xr-{ 

3 

U 

o 

<U     CO 
<U   -H 

U 

J= 

o 

4J     4-1 

CO 

u 

u 

W      C 

■H 

<U 

a 

x: 

(U 

0)     4J 

•H 

S 

y 

JS    o 

^  4-1  :s  o  to 


t)0-H 
C    > 


H  ^  -H   XI 

a,  ^  M-i  o  0.0 

!U    tj   u-i  to  o. 

U)  4-1  T3  -H 


CVi 


(U 

60 

o. 

c 

o 

0 

iH 

I-l 

cn 

cfl 

x: 

bu 

>^ 

•H 

XI 

•a 

>.r^ 

h 

(U 

(U  j3 

> 

^  1. '  ■'    IL  -V  -^A^ 


rH     )-l      CO      <U 

CO    (U  ^  X 
X3     CO     O 


?Ui*  y- 


4> 


x:  4J 

4-1     (U 

CO 

(U 

CO  ^ 

•H 

J= 

<u  o 

x; 

4J 

3    3 

H 

XI 

c 

CO 

0) 

(U 

ex 

60  J= 

(U 

C     4-1 

vJ 

CU 

•H 

i) 

•a 

-H  e 

■V 

CO    0 

CO 

•o 

O    P 

O 

c 

CO   H-l 

l-^ 

CO 

462        Bulletin  656 — American  Railway  Engineering  Association 


f%^S^- 


u    C  u 

(U     00  -H 

a.•r^  -a 
o  m 
•-<  <u  -a 
tn  -o  C 
n 
c  <u 
o  a  c 
o   o 


a) 

ni 

'-i 

o 

ra 

U 

Of 

1-. 

T 

CO 

■o 

c 

XI 

tn 

(U 

0) 

C 

m 

IJ 

> 

r-H 

(ij 

n 

•H 

ro 

ra 

0) 

D. 

n) 

O 

n. 

H 

m 

4-1 

> 

o 

4J 

M 

m 

m 

c 

C 

n 

X 

01 

o 

U) 

O 

0 

o 

(U 

o 

N 

N 

>J 

r 

X 

^r^ 

QJ 

^ 

■H 

■H 

m 

^ 

u 

U-l 

M 

C 

•H 

0 

^ 

o 

o 

0 

QJ 

£ 

D 

■X. 

u 

>-l 

K 

u 

J3 

jj 

•H 

Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie 


463 


1 

i 

1       a! 

Q\  UBS* 

.^.       J 

464   Bulletin  656 — American  Railway  Engineering  Association 


(a)   Concrete  buttress  placed  to 

support  massive  rock  slab  above 
the  road  bed. 


(b)   Anchored  reinforced  concrete 
buttresses  placed  to  support 
foliated  granite  rock  high  up 
on  a  slope. 


(c)   Anchor  bolts  with  wire  mesh  to 
positively  control  rockfall. 


(d)   Anchor  bolt  used  to  stabilize 
rock  block.   All  bolts  should 
be  tensioned  and  grouted. 


Figure  9  -  Support  Systems. 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  465 


■o 

41 

^    ^ 

c 

■D 

X 

u                -O                I" 

J3     U    <-. 

oi                   c    m         o 

^  C    (D 

^  >^    o  Ji    nj  « 

X         H<U4-<«           O.         <JO 

OJ                 >,   C    tfl 

i 

nj  -a    nj      .     O 

'^  -H          5    0         ^  ^    >>^ 

c<u(u^^3a)u 

-H      «     Q.  *H     C   J3      C 

b*               >.  u)    M 

U    &r->  ji           D         -O                 O 

T3«t«0l*0-H      O 

uwa>-oj=oj<:uat     • 

*J^.-*TJ     (UJiQ>T3 

c         n  ^   a 

GO           J=   T3 

c    o  a  bJ 

>s-0  '^     >                   0   «*-    *-t     C     O 

C     <U     U     01 

Ji      (0              --H    -O     *J 

O   X   -H  13 

U   4J        -o          w 

io^'c'^'S   o"   io   uH'oI 

o   c        o     - 

>, 

1          X         -O     >N 

«   ^     3  "flj 

:s 

JS-HO            4J       .*J3-'^Qjn] 

T3            --. 

Me        01  w  -. 

a>              Q.  0)    S 

S5 

X           -^     C    1)    <1> 

H 

c        «*-.    «    o   c    o  ^ 

■DOeflu-^O-'O 

^     >,         X     «    w 

.-•   0)             i^         01         k.    ni 

•-.^nJ^V-aiQJjaa 

ui        L^   a. 

^ 

^>     .£UwxBa.^-T3 

woj:*-»o60>         « 

C    00  n)    tg 

^o-Hu-o£3oooac 

u    O               C    1-  -^    c 

ajarS'-'         oc        ^c>n 

(Ui--aw0(ow«£ 

'qu-Ho^^TS'^naJto 

Uh*J^    —    (J'-<C      UO 

tn       -^Tj^ojc       -o« 

a>   a   i-*             XI   «)    en              <u 

>   at       ^   00  o 

J=     0    -^     U    -O                    rH     >,»«    J3 

jr  £  ji       j3   X    Of   o 

■H  j3        a    o   u 

X 

UUl-£-H(UWrH^O 

rj           ^ 

*J   ^     U    W     3     a^     flJ     U           T3 

^                       OOUU.nj4J- 

[fl   «*H     >sJ=     U     4>     «     OJ    w 

0*  *j       -a     -^ 

>>           W      n    W    -H-H 

■O^X4JX:^0           ^C3 

D          rt   X    C  79  w 

^w>MCni.            300 

2        u    u  a>       <J 

a.  q    t>o--<                     •   u        x; 

-H  -o        j£         rt         u  ^ 

a*«c^     --o^oj^cm 

«j         w  ja 

ai        ^u4.c<flo.j-^ 

0             X  -^^  o- 

-S^iiiS'-r  §1;.  § 

3    tn         o  ^         u    (0    > 

*«    w     0^     (5 

•r^   01        cj  -a   « 

•     M    «-•    <U     3     U 

e  a 

B   c«  "oJ  « 

MW.«4,C0O.OO 

uSuwo'^^atm 

j:  J=         ui 

XX                   V-        >.     ^4 

D.          O     rt           ex 

u<-<CL<iim^<i)^         C'-' 

flj             «1    r-<    1)     C 

•0-^.            WOOW            4I3.J 

u               n]  w    «  >> 

•HOSOIOCOMMOO 

(3-5^^-5   3   IflSw 

X     <1>            C     n     Li 

^  ^s-s-sa 

:»>.w^a.flG.ofl^^ 

u  -a    >  ^ 

>  X         t-t    o    o 

CL 

H         OJ 

1 

j: 

fl 

O 

o 

a 

E 

U-     Uj 

e 

•H   .--> 

SS 

u  (». 

JZ  U.    u 

H 

a. 

= 

n   <u  ^ 

ra  o 

o 

T3 

H 

O  CO 

a 

-' 

^ 

^ 

W   jj 

«        u  -a   I.         .                  a. 

-.        f   oj   o  -a  ^                  oj 

a>        (Q  X        at   bo                 Qj 

^ 

a         u  m   If,   u  -^                   iJ 

*«  —  j:                  M 

«          >%             X  ^               tz 

Xi         >. 

o   o.  c 

moos                                c 

D.*«    ^     C           w     QJ 

•^  ^  ""  ^  «■ 

>-        w    .   o   o-  to                   .       ^ 

•o        a 

n           ^  ki  u  ^                I.  01 

>.^ 

>,T3     O            M                                  CO   «t^   -O 

•o   to   o 

m^afljo.       <u                 ^(flw 

0*     3    fc> 

CU^lJ^UU                          3ttlK 

j<:    I-    u  ^   <o    >.                  <u 

S  i   in   M 

3cu4jaj^n                  00       T^ 

OJ      0     C    r-l    JI 

t-l/D           uui                          <Ut.3 

'  OJ    S   o. 

3M«I05>,                                UCUtJ- 

u    u-  u   at   v  ^                  > 

ftjo-wj:        niJ.:                  t->«aj 

c   >. 

C     fl           3    (l> 

xoioiu       au.          -.^i. 

73    1-.    a.       V)   «  i-»              m 

(0     >  X          X 

U    k*    C                       O    >>                      O 

01                    60                  C       • 

.-.     (U    tJ  .-»    *j 

C^O'^-in*.                   >.        n 

eg         uoot-o                         kitn^ 

C^QJ-HWiJ-^S            U 

>    OJ    o    c    <u 

-il-                  UOJOI                          11   ^ 

X          -H 

g 

nsoiauxj:                  >(u>. 

o>>(i»a>.-HCo-t 

>u^OMMu                       en 

"Sc-'S.-           £i  ^ 

Bci-i-H>(QO>        c: 

O          X    u    >-• 

n  "4-.  *j 

§ 

U    -r-t 

t,        So.o-o--'                  nt.M 

Qj      03     >,    Ot 

o    u)   u  j:   u  -H                                   c 

0*     QJ     U     C                   O     >.          *-> 

•O            n   T3     0 

01        w        --wo              m--H 

-   >,  a  -H  w 

a>         o. 

^  S-^-5  g 

m-oin         v-ui-.^              <u         c 

H     3     <0   X     60X    -H     OJ           T) 

X  J^    o 

c  ^  T3    u    o         «                     D-tH 

0»   TS            a     l-            WE            C 

u)    3   «    w  -a 

S-hSoi                •'>.                0          J 

>0)0><0w           0)           O 

^    --H             c 

M(ftX>U           bta                  ^ 

^  C    O    0     >. 

10     O     01      ■     O     E                   10 

o         U 

X         —1 

01  -O                  J5  T3     a                                60     . 

i.a.tnc^^t**        -o 

a    • 

•occmB              m             ^         tf) 

■O    V.      . 

•^(OO'H-3-D-^'^                   U            C 

»*-    li    c  -o 

X    11    >    "J    > 

rt-Suu        ojrH             o-ao 

3    C   X  T3     U 

a-a  ^  M             CO             I.       - 

■O     Mv^     "^     U    ^           J            « 

0,  S  S-S^     §  '        0,  Sii 

1)    73     4J    U-i 

O;     (A  ^    X  ^ 

X  X 

.5  *:;!  ^  3  - 

M-r^W                                  *JM                        V-'^'O 

■r^      m    T3     *J 

>L  >    o>  "S  Ti 

<iiu.oa(>,            c             <ut3C 

sniCMrtwca        Q> 

g^^fg    tiS       §gs 

(flL<03<-'U30         X 
U-iT3OT300«*J3          3 

rd    0    O   3 

g  t^iis:: 

'M  JZ   1^ 

"^  ?  £  5  Si 

C   a   u  -n 

Q   *J  M-t 

^    b   H    fl)     CL 

^ 

H 

c  ^^ 

^                                       ^ 

z 

« 

f2  w 

e 

e 

Q 

-                                          ZU 

Z 

< 

x'^ 

o 

o 

1 

X 

00                                                     M    U 

t-l 

VI 

H 

j: 

X  7^ 

^ 

-H                                                      .J 

^ 

u.                                      u 

(*« 

o 

o 

^  % 

V 

O 

iu 

<%                  i 

« 

S 

m 

_] 

is.  w 

«                                       ^ 

T3 

"^ 

^ 

^ 

"^ 

466 


Bulletin  656 — American  Railway  Engineering  Association 


0)    D 

Hi    u 


■o    O         -u 


w  C    3 


01  ra 

c 

D.  4h 

to 

« 

to  ^ 

c 

u 

01 

V4       !J 

0) 

u 

T3     O 

XJ 

T3 

l-< 

c 

r. 

x: 

•H 

ro 

ai 

tn    tn 

to 

,—1 

CU    -u 

id 

^ 

E    C 

(U 

to 

(U 

J^ 

c 

4J 

OJ     > 

u 

Regional  Meeting  Address  by  C.  O.  Brawner,  P.  Wyllie 


467 


(a) 


(b) 


Figure  12  -  Ditch  Catclimcnt  Control. 
One  of  the  most  underated  rockfall 
control  techniques  is  the  vise  of  deep 
catcliment   ditches.   V/here  possible 
ditches  should  be  wide  enough  for 
equipment  to  clean  out. 

(a)   Ravelling  slope  containing  large 
boulders  which  can  be  caught  with 
adequate  ditch. 


(b)   Large  rock  (20  cu. 
by  shallow  ditch. 


yds.)  caught 


(c)   Highway  catch  ditch  developed  to 
catch  erosion  wash  and  rockfall. 


(c) 


468        Bulletin  656 — American  Railway  Engineering  Association 


(c) 


(d) 


(e) 


Figure  13  -  Catchment   Techniques. 

(a)  Wire  mesh  fences  -  only  suitable 
to  catch  small  rock. 

(b)  Dry  rock  walls  -  Suitable  to 
reduce  slope  gradient. 

(c)  Concrete  catch  walls  -  effective 
but  expensive   and  subject  to 
breakage  due  to  rigidity. 

(d)  Gabion  walls  -  effective  and  resilient 
Variable  heights  are  possible. 
Vertical  back  face  is  essential. 

(e)  Metal  binwalls  -  efficient  retaining 
structures,  adjust  to  foundation 
condit  ions. 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie 


469 


(a)   Visual  Inspection 


(b)   Air  Photo 

Interpretation 


(c)   Review  of  Records 


(d)   Track  Patrols 


(e)   Instrumentation 


(f)   Electric  Warning 
Fences. 
See  Fig.  15 


(g)   Vibration  Meter 
Instnl latlons 


Periodic  inspection  of  rock  faces  and  slopes  will 
frequently  indicate  locations  of  potential  slide 
conditions.    The  most  important  features  are 
adversely  dipping  weaknesses  in  the  rock  on  which 
falls  will  slip  and  the  presence  of  water  pressure 
often  indicated  by  seepage. 

Large  scale  features  relating  to  slides  and  avalanches 
often  indicate  potentially  unstable  conditions 
developing.    Air  photographs  are  of  limited  use  in 
rock  fall  assessment  due  to  scale  llnitations. 

Records  should  be  kept  of  all  rock  fall  occurrences, 
slides  and  avalanches.    Annual  review  of  this  data 
will  pinpoint  areas  where  more  frequent  falls,  etc. 
occur. 

In  some  hazardous  areas,  during  very  adverse  climatic 
conditions  or  during  spring  melt  periods  track  patrols 
prior  to  train  movement  have  been  used. 

The  major  stability  concern  on  the  railway  is  the 
occurrence  and  potential  of  rock  falls.   Usually  the 
volumes  are  less  than  10  cu.  yds.   Vfarning  instrument- 
ation used  on  rock  slope  stability  programs  in  mining 
are  generally  not  applicable  due  to  the  high  cost  of 
the  great  number  of  installations  that  would  be 
required.    The  most  practical  program  is  to  observe 
movement  across  cracks. 

(a)  Driving  wooden  plugs  and  observing  plug 
behaviour. 

(b)  Painting  across  cracks  and  observe  paint. 

(c)  Put  plaster  in  cracks  and  observe  plaster. 

The  most  common  warning  system  used  in  Canada. 
Fences  are  of  two  general  types  -  tension  trip  and 
broken  wire  trip.    When  rock  or  other  falls  or 
debris  fall  and  hit  the  fence  the  block  signals  are 
automatically  changed.    For  maximum  statistical 
warning  coverage,  electric  fences  should  be  connected 
also  to  the  dispatchers  office.    For  consideration, 
suggest  also  that  a  radio  signal  be  activated  from 
the  area  of  the  fence  to  be  picked  up  in  all  train 
cabs  when  they  come  within  3-5  miles. 

The  greatest  application  for  fences  if  for  very  high 
slopes  where  the  cost  of  stabilization  would  be 
extreme.    Slopes  less  than  about  100  feet  high  can 
generally  have  the  surface  stabilized  for  less 
cost  than  installing  and  maintaining  a  fence. 

Snow  and  ice  cause  severe  maintenance  problems  in 
winter.   It  Is  suggested  for  consideration  that 
heating  cable  be  tried  as  the  fence  wire. 

There  are  some  areas  where  surface  stabilization  could 
be  sufficiently  successful  to  allow  removal  of  the 
warning  fence.    It  should  be  resolved  whether  this 
could  psychologically  be  done. 


Experimental  at  this  stage, 
being  monitored. 


A  test  install; 


FIGURE    K   -    SUMMARY   OF   WARJJING   METHODS 


470        Bulletin  656 — American  Railway  Engineering  Association 


Figure  15 — Electric  warning  fence  below  high,  steep  rock  slope  which  is  connected 
into  track   signal   system. 


Regional  Meeting  Address  by  C.  O.  Brawner,  D.  Wyllie  471 


Rock  will  generally  be  reLained 
on  slopes  flatter  than  1-1/2:1, 
the  approximate  angle  of   repose. 


Ditch 


Figure  16  -  Provided  the  rock  strength  and  geologic  structure  is  favourable 
and  controlled  blasting  is  used,  vertical  slopes  should  be 
considered.   This  will  reduce  quantities  to  allow  a  wider 
ditch  and  reduce  maintenance.   Ditches  should  be  wide  and  deen 
enough  to  act  as  a  catchment. 


472   Bulletin  656 — American  Railway  Engineering  Association 


(a)   Comparison  of  rock  slope  using  uncontrolled  and  controlled 
blasting. 


(b)   Rock  slope  developed  using  preshear  blasting. 
Close  control  over  drill  hole  alignment  is 
necessary. 


Figure  17  -  Controlled  blasting  to  develop 
uniform  slopes  in  competent  granite. 


Regional  Meeting  Address  by  C.  O.  Brawner,  P.  Wyllie  473 


Figure  18  -     DETAILED      APPRAISAL 
STABILITY     ASSESSMENT 


STABILITY      ASSESSMENT 


Region     Pacif 
Mileage    2A.9 


PRIORITY  RATINC; 


i-'ui-  ivision 


Date  Apr.  10/75 


Train  Traffic   Very  Heavy 


Alignment  slight  curve 


Sight  Visibility  AOO  ft.  West;  800  ft.  East 


Average  Climatic  Conditions  High  winter  snowfall,  hot  dry  summers 
Past  Stability  Record   Several  local  blocks 


DESCRIPTION  OF  SITE 


Cut   CSJ     Fill  HD  Other  CZl      

Height   50  ft.    Length  

Rock  cm     Soil  IZD      Other  CD  

Geologic  Description  Blocky  faulted  granite  -  3  major  faults.  Random  joints. 


Evidence  of  Water     Slight  seepage 


Ifork  Space  Available  Limited 


DESCRIPTION  OF  POTENTIAL  INSTABILITY  -  (TYPE,  tlAGMITUDE,  SERIOUSNESS) 

Very  large  block  could  fail  at  east  tunnel  portal.   Also  -  second  block  60  ft.  east 
of  portal. 

Tunnel  has  thin  roof  -  some  rockfalls  will  cause  daylight 


DETAILS  OF  RECOMMENDED  STABILIZATION 

Put  in  8  -  1-1/4"  dowels  at  lower  edge  of  rock  -  shotcrete  fault  around  dowels 

A  -  1-1/4"  dowels  at  second  block. 

Shotcrete  entire  tunnel  roof  and  side  and  tunnel  portal 

PHOTOGRAPH  OF  SITE 


^•^^^ 


474       Bulletin  656 — American  Railway  Engineering  Association 


TABLE  1 


TABLE  OF  PRIORITY  RATINGS 


A  -  Moderate  probability  of  failure  of  sufficent  volume  to  result  in  derailment 
if  failure  undetected. 


B  -  Some  probability  of  failure  of  sufficient  volume  to  result  in  derailment 
if  failure  undetected. 


C  -  Moderate  probability  of  failure  of  small  volumes  which  might  reach  the 
track. 


D  -  Moderate  probability  of  localized  rocks  or  rockfalls  occurring  during 
extreme  climatic  conditions  -  Very  heavy  rainfall  or  runoff,  extreme 
freeze-thaw  cycles,  etc. 


E  -  Slight  possibility  of  localized  failures  under  extreme  climatic  conditions. 
Generally  shallow  cuts. 


DIRECTORY 

CONSULTING    ENGINEERS 


FRANK  R.  WOOLFORD 

Engineering   Consultant — Railroadt 

24  Josepha  Ave. 

San   Francisco,  Ca.  94132 

(415)  587-1569 

246  Seadrift   Rd. 

Stinson  Beach,  Ca.  94970 

(415)  868-1555 


Vkf 


WestenhofF  &  Novick,  Inc. 
Consulting  Engineers 

Civil — Mechanical — Electrical 

Fixed  &  Movable  Bridges 

Soils,  Foundations,  Buildings 

Structural  &  Underwater  Investigations 

Planning,     Feasibility,     Design,     Inspection 

222   W.  Adams   St.,   Chicago,   III.   60606 
New  Yoric  Washington  Panama 


HAZELET  &  ERDAL 

Consulting   Engineers 

Design         Investigations        Reports 
Fixed    and    Movable    Bridges 

150  So.  Wacker  Dr.,  Chicago,  III.  60606 
LeulsvilU       Cincinnati       Washington 


HIMTB 


Feasibility  studies  and  design  services  for 

Bus  and  rail  transit  Terminals 

Regional  and  urban  planning  Pailcing 

Soils  and  foundations  Tunnels 

Stnictures  Utilities 
Environmental  Impact  studies 

Offices  in  28  cities  816  474-4900 

1805  Grand  Avenue,  Kansas  City,  Missouri  64108 


MODJESKI  AND  MASTERS 

Cen*«fffn0  EogtiioMi 

Design,   inspection  of  Construction  !>  In- 
spection  of   Physical   Condition   of   Fixed 
&  Movable  Railroad  Bridges 

P.O.   Box  2345,   Harrisburg,   Pa.   17105 
1055  St.  Charles  Ave.,  New  Orleans,  La. 


CLARK,  DIETZ  AND 

ASSOCIATES-ENGINEERS,  INC. 

Consulting  Engineers 

Bridges    Structures,  Foundations,  Indus- 
trial Wastes  and  Railroad  Relocattoe 

211    No.  Race  St.,  Urfcana,  III. 

Sanford,  Fla.  Memphis,  Tenn. 

Jackson,  Miss.  St.  Louis,  Mo. 

Chicago,  III. 


474-1 


474-2 


Directory   of    Consulting   Engineers 


ih 


Engineers 
Designers     Planners 


PARSONS  Route     Locotion,     Shop 

»»...  .^.^.-rNi  i/^F-.-  Facilities,    Container/ 

BRINCKERHOFF  BuIIc     Cargo,      Handling 

nilAHF  Utilities,     Bridget,    Tun- 

yvj/AL/c  ^^,j      Evaluations,     Ap- 

DOUGLAS,     Inc.  pralsals.      Supervision 

ONE  PENN  PLAZA,  NEW  YORK,  NY  10001 


Boston        •        Denver 
San  Francisco 


,        Honolulu 
Trenton 


HARDESTY  &  HANOVER 

Conaulting  Cnglnrntt 

TRANSPORTATION 
ENGINEERING 

Highways      •       Railways 

Bridges — Fixed  and   Movable 

Design       •       Resident   Inspection 

Studies      •      Appraisals 

101    Parle  Ave.,  New  York,  N.  Y.   10017 


THOMAS  K.  DYER,  INC. 

Consulting  Bnginews 

Railroads — ^Transit  Systems 
Track,  Signals,  Structures 

Invettlgolieni  and  Feasibility  R*|Mrts 
ffonnlng.  Design,  Cenlract  Decumenls 

1762  MotMclNitetl*  Avmhm 
LMiingten,  Mom.  02173 


npnil]eDe[euw,Cdtl]e[D[ganizdtion 

UUU  CONSULTING   ENGIMEERS 

165  W.  WACKER  DRIVE  •  CHICAGO  60601 


SUBWAYS  .  RAILROADS  •  PUBLIC  TRANSIT 

TRAFFIC .  PARKING  •  HIGHWAYS 
BRIDGES  •  PORT  DEVELOPMENT  •  AIRPORTS 
COMMUNITY  PLANNING  •  URBAN  RENEWAL 
MUNICIPAL  WORKS  .  INDUSTRIAL  BUILDINGS 
ENVIRONMENTAL  SCIENCE  AND  ENGINEERING 


IEC0^ 

RAILROAD 
DESIGN  &  ELECTRIFICATION 

Planning     •     Design 
Construction  Management 


INTERNATIONAL  ENGINEERING 
COMPANY,  INC. 

220  MONTGOMERY  STREET 
SAN  FRANCISCO,  CALIFORNIA  94104 


RILEY,  PARK,  HAYDEN  & 
ASSOCIATES,  INC. 

Centwff/ng   Englifwt 

Survey  Services,  Photogrammetry,  Gen- 
eral Civil,  Bridges,  Railroads  ft  Indus- 
trial Park  Design. 

136  Marietta  St.,  N.  W. 
Atlanta,  Georgia  30303 

(404)   577-5600 


Directory   of   Consulting   Engineers 


474-3 


SVEROROP  &  PARCa  AND  ASSOaATES.  INC 

800  No.  Twelfth  Blvd.  •  St.  Louis,  Mo.  63101 

Boston  •  Oiarleston  •  Gainesville  •  Jacksonville 
Nashville  •  New  YorV  •  Phoenix  •  San  Francisco 
Seaille     •     Silver  Spring      •      Washington,  D.C. 


•  design 

•  planning 

•  construction 
management 


CONSULTING  ENGINEERS 


I  Mir  PORTER  AND  mPA 
ASSOCIATES,  INC 

Consulting   Engineers — Planners 

Design       '       Inspections      -      Reports 

Planning       •       Structures 

Environmental  Studies 

20«   Madison    Avcnu*,    Morristown,  New  Jersey  079tO 


SPAULOING  ENGINEERING  CO. 

CONSULTING  ENGINEERS 

MEMBER 

AMERICAN  CONSULTING  ENGINEERS  COUNCIL 

1821    UNIVERSITY  AVENUE 

ST.   PAUL,  MINNESOTA  55104 

PHONE  612/644-5676 


SOROS  ASSOCIATES 

Consulting   Engineers 

Transfer  Termlnati  &  Ports  For  Dry  Bulks, 

Liquids  &  CentaiiMrs — Waterfront  Structure* 

Materials  Hondltng  Systems 

575   L«xington  Ave. 

New  York,  N.  Y.   10022 

(212)   421-0400 

Rio  de  Janeiro  Santiago,  Chil* 

Sydney,  Australia 


BAKKE  &  KOPP,  INC. 

Consulting  Engineer* 

RAILWAY  AND  HIGHWAY  BRIDGES 

SPECIAL  AND  HEAVY  STRUCTURES 

INVESTIGATIONS  AND  REPORTS 

4915  W.  35lh  St.  Mlnnecpolis,  MN  55416 

(612)   920-93*3 


A.  J.  HENDRY,  INC. 


> 


CONSULTING  ENCDSERS 


SIGNALS  •  COMMUNICATIONS  •  AUTOMATION  •  EliaRIFICATlON 

ItAILROADS  •  RAIL  TRANSIT 

SUITE  SIO  OSSORN  BUILDING 

ST.  PAUL.  MINNESOTA  isi02  <61Z)  222  2787 


474-4 


Directory   of   Consulting   Engineers 


TURNER  ENGINEERING 
COMPANY 

(SAWYER-PIEPMEIER) 

RAILROAD  ENGINEERING 

306  GAY  ST. 
NASHVILLE,   TENNESSEE   37201 

615-244-2144 
ALBANY,   NY      518-456-1994 


Railroads    •    Rapid  Transit 

Electric  Traction   Power 

Signals  and  Train   Control 

Communications    •    Substations  . 

Operations  Analysis  and  Simulation 

Power  Generation    •    Urban   Planning 

Gibbs  Si  Hill,  Inc. 

ENGINEERS,  DESIGNERS.  CONSTRUCTORS 

393  Seventh  Avenue,   New  York,  N.Y.   10001 

A  Subsidiary  of  Dravo   Corporation 


GENTEG  CENTRAL  TECHNOLOGY,  INC 

Railroad  Consultants 

OPERATION  ENGINEERING 

RESEARCH  ROUTE  LOCATION 

MANAGEMENT     CONSTRUCTION 


Dulles    International   Airport 
P.O.   Box  17411 
Washington,  O.C.  20041 


(703)  471-7070 
Cable:  CENTEC 
Telex:  89-9493 


WOLCHUK  and  MAYRBAURL 
CONSULTING  ENGINEERS 

RAILWAY  AND  HIGHWAY  BRIDGES 

SPECIAL  STRUCTURES 

DESIGN— INVESTIGATIONS— REPORTS 

432  PARK  AVE.  S.,  NEW  YORK,  NY  1 001 6 
(212)   689-0220 


MORE  TON  MILES 

of  SERVICE 

and  LESS  MAINTENANCE 

wHh 


PENO 
ERVICES 


BALLAST 
CLEANING 


RAIL 


GRINDING 


SoutK*m   Pacific 


,  -  *  J®!^  ^; «™"  KjiAi 


Discover  how  yoa  can  get  more  ton  miles  of 
■JE  service  at  less  maintenance  cost  by  using  Speno 

,,:'  Ballast  Cleaning  and  Rait  Grinding. 

THROUGHOUT  THE  CONTINENT 

FRANK  SPENO  RAILROAD  BALLAST  CLEANING  COMPANY,  INC. 

306  North  Cayuga  St  ,  Ithaca,  New  York  14850 
Clark  Street.  Box  219,  East  Syracuse,  New  York  13057 

SPENO  INTERNATIONAL  S.A.  lEC-HOLDEN,  LTD. 

22  Pare  Chateau  Banquet.  Geneva,  Switzerland   8180  Cote  de  Liesse  Road 

(For  Rail  Gr  ndmg  Ou',.-3c  !he  Nor'h  RPI    Montreal,  Canada  H4T1G8 


TRASCO  Track  Skates 


Preferred  by  skatemen 

Light 

Tough 

Balanced  hand  hold 

No  curl  tongue 

TRACK  SPECIALTIES 

COMPANY 
Box 729  Westport,Conn. 


( 


*•.  C  kjj-eLtim^ytc 


JZL 


RECEIVED" 
AU 

American  Railway  ^^^,^,,,^^ 

Engineering  Association— Bulletin 


Bulletin  658  June-July  1976 

Proceedings  Vol.  77* 


TECHNICAL  CONFERENCE   REPORT  ISSUE 

CONTENTS 

President's  Address 487 

Special    Features    491 

Installation  of  Oflficers 667 

AAR  Engineering  Division  Session 673 

Report  of  Executive  Director    681 

Report  of  Treasurer    691 

AREA  Constitution 697 

Directory — Consulting    Engineers 717 


•Proceedings  Volume  77  (1976)  will  consist  of  AREA  Bulletins  634,  September- 
October  1975:  655,  November-December  1973;  656,  January-Febraary  1976;  and  658. 
June-July  1976  (Technical  Conference  Report  issue).  Blue-covered  Bulletin  857,  April- 
May  1976   (the  Directory  issue),  is  not  a  part  of  the  Annual  Proceedings  of  the  Association 


BOARD  OF  DIRECTION 
1976-1977 

President 
JoHK    Fox,    Chief    Engineer,    Canadian    Pacific   Rail,   Windsor   Station,   MonUcal,  PQ 
H3C  3E4 

Vice  Presidents 
B.  J.  WoKJLEY,  Vice  President— Chief  Engineer,  Chicago,  Milwaukee,  St.  Paul  &  Pacific 

Railroad,  Union  Station,  Roona  898,  Chicago,  IL  60606 
W.  S.  AuTREY,  Chief  Engineer  System,  Atchison,  Topeka  &  Santa  Fe  Railway,  80  E. 

Jackson  Blvd.,  Chicago,  IL  60604 

Past  Presidents 
R.  F.  Bush,  Chief  Engineer— Special  Projects,  Consolidated  Rail  Corporation,  6  Penn 

Center  Plaza,  Room  1640,  Philadelphia,  PA  19104 
J.  T.  Wakd,  Senior  Assistant  Chief  Engineer,  Seaboard  Coast  Line  Railroad,  500  Water 

St.,  Jacksonville,  FL  32202 

Directors 
P.  L.  Montgomery,  Manager  Engineering  Systems,  Norfolk  &  Western  Railway,  8  N. 

Jefferson   St.,   Roanoke,  VA   24042 
E.  C.  HoNATH,  Assistant  General  Manager  Engineering,  Atchison,  Topeka  &  Santa  Fe 

Railway,  900  Polk  St.,  Amarillo,  TX  79171 
Mike  Rougas,  Chief  Engineer,  Bessemer  &  Lake  Erie  Railroad,  P.  O.  Box  471,  Green- 
ville, PA  16125 
J.  W.  DeVaixe,  Chief  Engineer  Bridges,  Southern  Railway  System,  99  Spring  St.,  S.  W., 

Atlanta,  GA  30303 
E.  H.  Waring,   Chief  Engineer,  Denver  &  Rio  Grande  Western  Railroad,  P.  O.  Box 

5482,  Denver,  CO  80217 
Wm.   Glavin,    General   Manager,   Grand  Trunk  Western   Railroad,   131   W.  Lafayette 

Blvd.,  Detroit,  MI  48226 
G.  H.  Maxwell,  System  Engineer  of  Track,  Union  Pacific  Railroad,  1416  Dodge  St., 

Omaha,  NE  68179 
J.  W.  Brent,  Chief  Engineer,  Chessie  System,  P.  0.  Box  6419,  Cleveland,  OH  44101 
L.  F.  Ctjrrier,  Engineer — Structures,  Louisville  &  Nashville  Railroad,  P.  O.  Box  1198, 

Louisville,  KY  40201 
T.   L,  FxnxER,  Engineer  of  Bridges,   Southern  Pacific  Transportation   Company,  One 

Market  St.,  San  Francisco,  CA  94105 
J.  A.  Barnes,  Assistant  Vice  President  &  Chief  Engineer,   Chicago  &  North  Western 

Transportation  Company,  500  W.  Madison  St.,  Chicago,  IL  60606 

Treasurer 
A.  B.  EIillman,  Jr.,  Chief  Engineer,  Belt  Railway  of  Chicago,  6900  S.  Central  Ave., 
Chicago,  IL  60638 

Executive  Director 
Earl  W.  Hodgkins,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Assistant  to  Executive  Director 
N.  V.  Engman,  59  E.  Van  Buren  St.,  Chicago,  IL  60605 

Administrative  Assistant 
D.  F.  Fredley,  59  E,  Van  Buren  St.,  Chicago,  IL  60605 


Published    by    the    American    Railway    Engineering   Association,    Bi-Monthly,    January-FetMTiary,    AjMil- 

May,  June-July,  September-October  and  November-December,  at 

59  East  Van  Buren  Street,  Chicago,  111.  60605 

Second  class  postage  at  Chicago,  111.,  and  at  additional  mailing  offices. 

Subscription  $15  per  annum 

Copyright  ©  1976 

.\uxKicAN  Rail  WAY  Encineesino  Associatiom 

All  rights  reserved. 

No    part    of    this    publication    may    be    reproduced,    stored    in    an    information    or    data    retrieval 

system,     or     transmitted,     in     any     form,     or    by    any    means — electronic,     mechanical,    photocopying 

recording,     or    otherwise — without    the    prior    written    permission    of    the    publisher. 


PROCEEDINGS 

SEVENTY-FIFTH  TECHNICAL  CONFERENCE 

American  Railway  Engineering 
Association 


March  22-24,   1976 
PALMER  HOUSE,   CHICAGO 


VOLUME  77 


AMERICAN    RAILWAY   ENGINEERING   ASSOCIATION 

59   Easf  Van    Buren    Street 

Chicago,    Illinois    60605 


475 

Bui.   65S 


OFFICERS,   1975-1976 


J.  T.  Ward 
President 

St.    Asst.    Chf.    Engr.,    S.C.L.    RR. 


John  Fox 
Sr.  Vice    President 

Chief  Engr. 
C.  P.   Ltd. 


R.  F.  Bush 
Past  President 

Chf.   Engr.-Spec.   Proj. 
ConRail 


B.    J.    WORLEY 

Jr.  Vice  President 

Vice    Pres 
C.  M.  St. 

;.-Chf.    Engr. 
P.  &  P.  RR. 

....'^ 

Hi^^'-"'- 

K 

«*9»«>r?-. 

'^t^ 


Ib^ 


A.  B.  HiLLMAN,  Ja 
Treasurer 

Chief  Engr. 
Belt  Ry.  of  Chicago 

476 


D.  V.  Sartore 
Past  President 

Chf.  Engr.  Design 
B.  N.,  Inc. 


Earl  W.  Hodgkins 

Executive  Director 

and  Secretary 

AREA 


DIRECTORS,   1975-1976 


R.  W.  Pember 

1973-76 

Chf.  Engr.- 
Des.  &  Const. 
L.  &  X.  RR. 


E.  Q.  Johnson 
1973-76 

Sr.  Asst.  Chf.  Engr. 
Chessie  Sys. 


W.   E.   FuHR 

1973-76 

Asst.  Chf.  Engr.-Staff 
C.  M.  St.  P.  &  P.  RR. 


B.  E.  Pe.^rson 
1973-76 

Chief  Engr. 
Soo  Line  RR. 


^ 

fa 

1^' 

:  W 

] 

p.  L.  Montgomery 

1974-77 

Mgr.  Engrg.  Sys. 
X.&\V.  R\ . 


E.    C.    HONATH 

1974-77 

Asst.  Gen.  Mgr.  Engrg. 
A.  T.  &  S.  F.  Ry. 


Mike  Rougas 

1974-77 

Chief  Engr. 
B.&L.  E.  RR. 


J.  W.  De  Valle 

1974-77 

Chf.  Enirr.  Bridges 
Sou.  Rv.  Svs. 


R.  L.  Gray 
1975-76 

Spec.  Advisor 

Toronto   Area  Tran. 

Oper.  Auth. 


E.   H.  Waring 

197.5-78 

Chief  Engr. 
D.&R.G.W.  RR. 


Bui.   C58 


Wm.  Glavin 

1975-78 

Gen.  Mgr. 
G.T.W.  RR. 

477 


3.  H.  Maxwell 

1975-78 

Sys.  Engr.  Track 
U.P.  RR. 


CONTENTS 

Page 

Officers,   1975-1976 476 

Directors,   1975-1976 477 

Technical    Conference    Program 479 

Nominating    Committee   and   Tellers   Committee,    1976   Election 482 

Successful   Canciidates   in    1976   Election 483 

Address    by   President   John   T.    Ward 487 

Special    Features: 

Address — Description    of   Architectural    Competition    Sponsored    by   AREA    Committee 

6 — Buildings,   by  D.   A.   Bessey 493 

Address — Track  Maintenance  for  High-Speed  Trains,   by  Harold  H.  Jenkins 499 

Address — Hot  Box   Detector   Data   Analyzer  System,   by   W.   Friesen 521 

Address — "The    Quiet    One,"    Burlington    Northern's    Northtown    Yard,    by    M.    B. 

Walker 555 

Address — The    Load    Spectrum    for    the    Fraser    River    Bridge    at    New    Westminister, 

B.    C,       by    R.    A.    P.    Sweeney    561 

Address — An  Investigation  of  the  Estimated  Fatigue  Damage  in  Members  of  the 
380-Ft  Main  Span,  Fraser  River  Bridge,  by  John  W.  Fisher  and  J.  Hartley 
Daniels 577 

Address — Data     Bases:     Help     or     Harassment    for    Engineering     Management,     by 

Charles    F.    Wiza    597 

Address — Rail    Wear   and    Corrugation    Studies,    by   F.    E.    King   and   J.    Kalousek   __    601 

Address — High-Strength  Chromium-Molybdenum  Rails,  by  Y.  E.  Smith,  J.  M.  Sawhill, 

Jr.,   W.   W.   Cias   and   G.  T.   Eldis 621 

Address — Innovations  in   Frog  and  Switch  Design,  by  E.   H.  Taylor 652 

Address — C&NW's   "BUC"    (Ballast  Undercutter-Cleaner) ,  by  R.  W.  Bailey 665 

Installation   of   Officers 669 

AAR  Engineering  Division  Session: 

Remarks    by    Division    Chairman    John    T.    Ward    675 

Address — A  Time  for  Challenge,  by  D.  C.  Hastings 677 

Report   of   Executive   Director   Earl    W.    Hodgkins 683 

Report   of  Treasurer   A.    B.    Hillman,    Jr. 693 

AREA    Constitution    699 

478 


AMERICAN   RAILWAY  ENGINEERING  ASSOCIATION 
75th  ANNUAL  TECHNICAL  CONFERENCE 

ASSOCIATION   OF  AMERICAN   RAILROADS 
ENGINEERING  DIVISION 

1976  ANNUAL  MEETING 

MARCH   22-24,   1976 
Palmer  House,   Chicago 

PROGRAM 
Monday,  March  22 

Opening  Session — Red  Lacquer  Room    (4th  Floor) — 9:30  am 

Invocation — Dr.  Kenneth  Hildebrand,  Pastor  Emeritus,  Central  Church  of  Chicago 

Recognition  of  speakers  table  guests 

Presidential    Address — John    T.    Ward,    Senior   Assistant   Chief   Engineer,    Seaboard 
Coast  Line  Railroad 

Report  of  Treasurer — Arthur  B.  Hillman,  Jr.,  Chief  Engineer,  Belt  Railway  of  Chicago 

Report  of  Executive  Director — Earl  W.  Hodgkins,  AREA 

Greetings  from  Railway  Engineering-Maintenance  Suppliers  Association — Harry  D. 
Campbell,  President 

Description  of  Architectural  Competition  Sponsored  by  AREA  Committee  6 — Build- 
ings (Illustrated)  and  Presentation  of  Award  to  Student  Winner — D.  A.  Bessey, 
Architect,   Chicago,    Milwaukee,    St.    Paul   &  Pacific   Railroad 
Description  of  Winning  Entry  by  Student  Winner 

Maintaining  Track  for  High-Speed  Trains — Harold  Jenkins,  Permanent  Way  Engi- 
neer, British  Rail 

479 


480  Bulletin  658 — American  Railway  Engineering  Association 

Engineering   Division  Session — Red  Lacquer  Room — 1:30  pm 

Recognition  of  speakers  table  guests 

Remarks  by  Chairman  John  T.  Ward 

Remarks  by  R.  R.  Manion,  Vice  President,  Operations  and  Maintenance  Department, 
AAR 

Remarks  by  Dr.  W.  J.  Harris,  Jr.,  Vice  President,  Research  and  Test  Department, 
AAR 

Address  by  D.  C.  Hastings,  Chairman,  AAR  Operating-Transportation  Division; 
Executive  Vice  President,   Seaboard  Coast  Line   Railroad 

Up  Date  on  IFAST  at  Pueblo,  Colorado  (Illustrated)— Dr.  G.  C.  Martin,  Director 
of  Dynamics  Research,  AAR,  and  Dr.  R.  M.  McCafferty,  Program  Manager, 
Improved  Track  Performance  Research,  Federal  Railroad  Administration 

Ballast  and  Foimdation  Materials  Research  Program  (Illustrated)  (Committee  1 — 
Roadway  and  Ballast) — Dr.  G.  C.  Martin,  AAR,  and  Dr.  M.  R.  Thompson, 
Professor  of  Civil  Engineering,  University  of  Illinois 

Developments  in  Timber  Ties  (Illustrated)  (Committee  3 — Ties  and  Wood  Preser- 
vation)— H.  M,  Williamson,  Consulting  Engineer;  Retired  Chief  Engineer, 
System,  Southern  Pacific  Transportation  Company 

REMSA   RECEPTION — Grand    Ballroom — 6:30   pm-8:00   pm 


TUESDAY,  MARCH  23 

Technical   Session — Red  Lacquer  Room — 8:30  am 

Computer  Analysis  of  Hot  Box  Detector  Signals  (Illustrated) — Walter  Friesen, 
Senior    Design   Engineer — Signals,    Canadian   National    Railways 

The  Quiet  One — Noise  Abatement  Dealing  with  Retarders  in  the  New  Northtovra 
Yard  (Illustrated)  (Committee  13 — Environmental  Engineering) — M.  B. 
Walker,  Assistant  Director — Signal  Engineering,  Bvulington  Northern,  Inc. 

Fatigue  Study  of  New  Westminster  Bridge  (Illustrated)  (Committee  15 — Steel 
Structures) — Dr.  J.  W.  Fisher,  Professor  of  Civil  Engineering,  Fritz  Engineer- 
ing Laboratory,  Lehigh  University,  and  R.  A.  P.  Sweeney,  Structural  Engineer, 
Canadian  National  Railways 

Solving  a  DiflBcult  Foimdation  Problem  ( Illustrated )  ( Committee  8 — Concrete  Struc- 
tures and  Foundations) — Dr.  W.  L,  Gamble  and  Dr.  M.  T.  Davisson,  Professors 
of  Civil  Engineering,   University  of  Illinois 


Conference  Program  481 


ANNUAL  LUNCHEON— GRAND  BALLROOM— 12:00  NOON 

Presentation  of  guests  at  speakers  table 

Presentation  of  newly  elected  officers 

Address  by  W.  T.  Rice,  Chairman  of  the  Board,  Seaboard  Coast  Line  Railroad 

Technical   Session — Red  Lacquer  Room — 2:00  pm 

Motion  Picture  on  Northern  Alberta  Railways 

Snow  Control  by  Model  Analysis  (Illustrated) — F.  H.  Theakston,  Partner,  Morrison, 
Hershfield,   Theakston   and   Rowan 

Laminated  Wood  Materials  for  Bridge  Decking  ( Illustrated )  ( Committee  7 — Timber 
Structures) — T.  E.  Brassell,  Director  of  Technical  Services,  American  Institute 
of  Timber  Construction 

Precast  Concrete  (Illustrated)  (Committee  8 — Concrete  Structures  and  Foundations) 
— J.  G.  White,  Vice  President  and  General  Manager,  Con-Force  Costain  Concrete 
Tie  Co.  Ltd. 

Data  Bases:  Help  or  Harassment  for  Engineering  Management  (Committee  32 — 
Systems  Engineering) — C.  F.  Wiza,  Manager — Methods  and  Planning,  Illinois 
Central  Gulf  Railroad 

WEDNESDAY,  MARCH   24 

Technical   Session — Red   Lacquer   Room — 8:30   am 

Rail  Flow  and  Corrugation  Studies  (Illustrated)  (Committee  4 — Rail) — Dr.  Joseph 
Kalousek,  Research  Engineer,  Canadian  Pacific  Rail,  and  F.  E.  King,  Senior 
Technical  Advisor,  Canadian  National  Railways 

High-Strength  Chrome  Molybdenum  Rail  Steel  (Illustrated) — Y.  E.  Smith,  Research 
Supervisor,  Climax  Molybdenum  Company  of  Michigan 

Iimovations  in  Frog  and  Switch  Design  (Illustrated)  (Committee  5 — Track) — E.  H. 
Taylor,  Supervisor  of  Track  Development,  Canadian  Pacific  Rail 

C&NW's  BUG  (Ballast  Undercutter  Cleaner)  (Illustrated)  (Committee  27 — Mainte- 
nance of  Way  Work  Equipment) — R.  W.  Bailey,  Director  of  Maintenance  Plan- 
ning, Chicago  &  North  Western  Transportation  Company 

Installation  of  Officers 

Adjournment 


482 


Bulletin  658 — American  Railway  Engineering  Association 


Nominating  Committee,   1976  Election 

Past  Presidents 
Q.  Johnson,  Chairman 


Senior  Assistant  Chief  Engineer,  Ches- 
sie  System 

A.  L.  Sams 

Vice    President,    DeLeuw,    Gather    6c 
Company 

R.  M.  Brown 

Chief    Engineer,    Union    Pacific    Rail- 
road 
D.  V.  Sartore 

Chief     Engineer — Design,     Burlington 
Northern,    Inc. 

R.  F.  Bush 

Chief  Engineer — ^Special  Projects,  Con- 
solidated Rail  Corporation 


Elected  Members 
J.  E.  Sunderland  (East) 

Director  Engineering  Programs,  Ches- 

sie  System 
D.  S.  Bechly   (South) 

Engineer — Structures,    Illinois    Central 
Gulf  Railroad 
L.  G.  Collister  (West) 

Manager   Tie   &   Timber   Department, 
Atchison,  Topeka  &  Santa  Fe  Rail- 
way 
Bernard  Fast  (Canada) 

Assistant  Regional  Engineer,  Canadian 
Pacific  Rail 
C.  L.  Gatton   (At  Large) 

Assistant  Clijief  Engineer — Mainte- 
nance of  Way,  Louisville  &  Nash- 
ville Railroad 


Committee  of  Tellers,   1976  Election 

The  following  committee  was  appointed  to  canvass  the  ballots  for  Officers  and 
Directors  and  for  Members  of  the  Nominating  Committee,  the  count  being  made  on 
February  20,  1976. 


W.  S.  Stokely,  Chairman   W.  F.  Burt 


N.  E.  Whitney,  Jr., 

Vice  Chairman 
L.  R.  Beattie 
J.  E.  Beran 
D.  E.  BucHKO 

J.    BUDZILENI 


J.    L.    HODSON 

G.  H.  Hogue 
R.  W.  Janssen 
D.  C.  Knuth 
C.  R.  Lund 
G.  W.  Mahn,  Jr. 


W.  B.  Stanczyk 
P.  H.  Swanson 
R.  Urbano 
R.  A.  Vollrath 
R.  L.  Williams 
D.  R.  York 


Successful  Candidates  in   ]976  Election 

For  President 
John  Fox,   Chief  Engineer,  Canadian  Pacific  Rail,  Montreal,  Que. 

For  Senior  Vice  President* 

B.    J.    Worley,    Vice    President — C^hief    Engineer,    Chicago,    Milwaukee,    St.    Paul   & 
Pacific   Railroad,  Chicago 

For  Junior  Vice  President 

W.  S.  Autrey,  Chief  Engineer  System,  Atchison,  Topeka  &  Santa  Fe  Railway, 
Chicago 

For  Directors 

East: 

J.   W.   Brent,   Chief  Engineer,  Chessie  System,  Cleveland,  Ohio 

Smith: 

L.    F.    Currier,    Engineer — Structures,    Louisville   &   Nashville   Railroad,   Louis- 
ville, Ky. 

West: 

T.   L.   Fuller,   Engineer   of   Bridges,   Soutliern  Pacific  Transportation   Company, 

San  Francisco,  Calif. 
J.    A.   Barnes,   Assistant  Vice   President   &  Chief  Engineer,   Chicago   &   North 

Western   Transportation   Company,   Chicago 

For  Members  of  1976  Nominating  Committee 

East: 

J.   J.    Ridgeway,    Director — Engineering   Services,   Bessemer  &   Lake   Erie   Rail- 
road, Greenville,  Pa. 

South: 

C.    E.    Webb,    Assistant    Vice    President — Engineering    &    Research,    Southern 
Railway,  Washington,  D.  C. 

West: 

R.  E.  Frame,  District  Engineer,  Southern  Pacific  Transportation  Company,  San 
Francisco,  Calif. 

Canada: 

A.  E.  Speers,  Regional  Engineer  Administration,  Canadian  National  Railways, 
Toronto,    Ont. 

At  Large: 

R.  E    Haacke.  District  Engineer,  Union  Pacific  Railroad,  Portland,  Ore. 


*  Under  the  provisions  of  the  AREA  Constitution,  B.  J.  Worley  advances  automatically  from 
Junior   Vice   President    to   Senior   Vice   President. 

483 

Bui.  058 


PRESIDENT'S  ADDRESS 


485 

Bui.  058 


Address  by  President  John  T.  Ward* 

Welcome  to  the  75th  Annual  Technical  Conference  of  the  American  Railway 
Engineering  Association.  This  welcome  is  directed  to  all  memljers  and  guests  of 
the  Association,  but  I  wish  to  add  a  special  or  particular  welcome  to  the  ladies 
who  are  gathered  near  the  front  of  the  meeting  room.  It  is  always  a  pleasure  to 
have  you  attend  this  opening  session,  and  I  trust  you  will  remain  for  as  much  of 
the  program  as  you  desire. 

Somewhere  along  the  way,  I  heard  the  story  of  an  elderly  black  preacher  who 
expounded  Sunday  after  Sunday  on  the  "Status  Quo."  This  went  on  for  some  time, 
when  finally  one  of  his  parishioners  got  up  nerve  enough  to  ask  him,  "What  is 
dis   Status   Quo?"  The  pastor's  response  was,   "That's  Latin  for  the  mess  we's  in." 

This  is  said  to  point  up  the  fact  that  the  rail  industry,  with  which  all  of  us 
are  associated  in  one  way  or  another,  has  been  in  somewhat  of  a  mess  during  the 
year  just  ending.  Possibly  a  better  choice  of  words  would  be  unstable  or  unsettled. 
Regardless  of  which  descriptive  word  is  used  for  the  state  of  the  industry,  it  has 
been  a  rather  trying  year  for  the  group  seated  in  this  room  today. 

The  year  began  with  less  rail  traffic,  resulting  in  reduced  revenues.  This  caused 
a  chain  reaction  towards  lesser  maintenance  appropriations  and  restrictions  on 
travel  for  most  railroad  employees,  and  particularly  for  maintenance  employees,  with 
the  result  that  AREA  has,  likewise,  felt    the  brunt  of  all  of  this  in  its  activities. 

Additionally,  the  Association's  executive  director.  Earl  W.  Hodgkins,  was  away 
from  the  office  for  approximately  four  months  as  a  result  of  bypass  heart  surgery. 
This  slowed  down  somewhat  the  activities  of  AREA,  although  the  yeoman  job  done 
by  Don  Fredley  and  Norris  Engman,  as  well  as  others  on  the  staff,  plus  the  support 
of  the  Board  of  Direction,  allowed  the  work  to  be  accomplished  as  necessary.  The 
special  thanks  of  the  Association  are  expressed  to  Don  and  Norry  for  their  very  able 
assistance  while  Earl  was  unavailable.  It  must  he  reported,  however,  that  Earl  con- 
tinued to  undertake  considerable  work  of  your  Association  at  home  while  recuper- 
ating, including  the  many  details  of  this  Technical  Conference  which  fall  within 
his  bailiwick. 

What  has  been  accomplished  during  the  year?  Your  Association  had  a  very 
excellent  Technical  Conference  last  March  here  at  the  Palmer  House,  headed  up 
by  immediate  Past  President  Bob  Bush.  The  program  was  excellent,  as  evidenced 
by  the  large  attendance  at  each  of  the  presentations.  Very  able  assistance  was 
offered  by  many  members  of  AREA  in  suggesting  track  components  and  configura- 
tions which  might  be  incorporated  in  the  accelerated  service  testing  loop  under 
construction  by  the  Federal  Railroad  Administration  at  Pueblo,  Colo.  This  facility 
is  scheduled  to  l>e  in  service  by  mid-year.  In  October,  there  was  the  annual  Regional 
Meeting  in  Vancouver,  B.  C,  attended  by  approximately  225  members  and  guests. 
The  program  for  this  latter  meeting  was  developed  by  Vice  President  John  Fox, 
and  it  was  a  good  one.  In  between  the  Technical  Conference  and  Regional  Meet- 
ing, as  well  as  before  and  after,  the  work  of  the  19  standing  committees  and  one 
special  committee  of  your  Association  was  progressed — some  quite  actively,  while 
certain  other  committees  reacted  in  just  a  mediocre  manner. 

It  is  this  latter  phase  of  the  work  of  AREA  to  which  it  is  desirable  that  I 
address   myself   at   the   moment.   The   objectives   of   your   Association   are   advanced 


'  Senior   Assistant   Chief   Engineer,    Seaboard   Coast   Line   Railroad,   Jacksonville,   Fla. 

487 


488  Bulletin  658 — American  Railway  Engineering  Association 

through  tlie  work  of  its  committees  in  two  ways,  and  these  certainly  are  the  heart 
and  soul  of  the  organization.  First,  the  development  of  informaMon  pertinent  to 
their  assignments  which  may  be  presented  to  the  membership  as  a  whole  "as 
information"  and,  secondly,  the  formulation  of  recommended  practices  to  be  sub- 
mitted for  adoption  and  publication  in  the  Manual  for  Railway  Engineering  or 
Portfolio  of  Trackwork   Plans. 

It  is,  therefore,  of  the  utmost  importance  that  the  work  of  AREA  committees 
be  pursued  with  vigor  and  dispatch  in  order  that  the  aforementioned  results  will 
be  completely  fulfilled.  There  are  many  ways  this  may  be  accomplished.  Member- 
ship attendance  at  all  committee  meetings  is,  of  course,  highly  desirable,  but  in 
this  day  of  suppressed  travel,  because  of  decline  in  revenues,  may  not  be  entirely 
possible.  It  is  important,  however,  that  the  membership  be  selective  in  the  meet- 
ings attended  and  certainly  be  cognizant  of  the  ongoing  activity  of  committee  work 
by  fully  reading  all  correspondence,  participating  in  same  to  the  extent  necessary 
to  progress  a  given  assignment,  and,  particularly,  to  respond  to  all  questionnaires 
submitted   by   committees. 

Additionally,  all  committee  chairmen  have  been  urged  to  recommend  only 
those  assignments  which  can  be  pursued  to  an  early  conclusion,  to  set  completion 
schedules  on  authorized  assignments  and  to  check  with  subcommittee  chairmen 
from  time  to  time  to  insure  that  each  assignment  is  being  progressed  accordingly. 
Only  in  this  manner  can  the  desired  results  of  committee  activity  be  accomplished. 

The  AREA  Board  of  Direction  and,  particularly  its  Committee  on  Technical 
Activity,  chairmanned  by  Director  Mike  Rougas,  has  urged  each  of  the  commit- 
tees to  progress  their  work  accordingly.  As  stated  above,  I  am  happy  to  report 
that  many  have  reacted  favorably  in  this  regard,  but  there  are  some  whose  work 
leaves  something  to  be  desired.  It  is  in  this  latter  area  that  improvement  must  be 
accomplished.  This  of  course,  is  no  different  from  any  other  organization,  wherein 
it  appears  difficult  always  to  obtain  a  full  100%  participation. 

Your  Association's  membership  has  continued  to  increase  during  the  year  under 
the  leadership  of  the  Committee  on  Membership,  chairmanned  by  Director  Doc 
Pember.  AREA  is  also  financially  stable.  Further  detailed  reports  in  this  regard  will 
fellow  from  the  Executive  Director,  Earl  Hodgkins,  and  Treasurer  Art  Hillman. 
A  number  of  the  new  memljers  are  consultants  and  others  are  from  the  supply 
industry.  We  need  to  concentrate  our  efforts  in  interesting  some  of  our  associates 
in  the  rail  industry  in  membership  in  AREA,  and  particularly  any  new  engineers 
who  may  be  working  with  us.  The  expertise  of  these  rail  employees  is  very  vitally 
needed  in  the  work  of  your  Association. 

This  year,  there  have  been  a  number  of  requests  for  purchase  of  AREA  Man- 
uals for  Railway  Engineering  and  Portfolios  of  Trackwork  Plans.  These  requests 
have  come  principally  from  consultants  and  foreign  countries,  but  it  bears  out  the 
fact  your  Association  is  well-thought-of  worldwide.  These  sales  have,  of  course, 
aided  the  financial  condition  of  the  organization.  Additionally,  in  this  day  of  rising 
costs,  your  Board  of  Direction  found  it  necessary  to  increase  the  cost  of  registra- 
tion at  this  Technical  Conference  to  $10.  Checking  l:)ills  against  receipts  for  these  fine 
facilities  at  the  Palmer  House  for  the  past  couple  of  years,  it  was  determined  that 
your  Association  was  running  in  the  red  in  this  item  of  the  budget,  and  die  in- 
crease in  registration  cost  was,  therefore,  inevitable.  These  are  just  two  areas  of 
finance  which  I  elected  to  lift  up  and  comment  on  at  this  time.  There  are  others, 
of  course,  and  these  are  being  watched  very  carefully  on  a  continuing  basis  by 
the  Committee  on  Finance,  headed  by  Past  President  Bob  Bush. 


Address  by  President  Ward  489 


During  this  past  year,  a  Manual  chapter  was  assigned  to  the  Committee  on 
Electrical  Energy  Utilization.  This  group  has  been  designated  as  Committee  33. 
This   is   particularly   important   in   light   of  present-day   activity   in   electrification. 

This  is  just  a  thumb-nail  sketch  of  some  of  the  activities  of  your  Association 
during  the  year  just  closing.  M>-  personal  thanks  are  expressed  to  Earl  Hodgkins, 
Don  Fredley  and  Norry  Engman  for  their  able  assistance  in  all  phases  of  the  work 
this  year.  A  particular  note  of  appreciation  is  directed  to  the  entire  Board  of 
Direction  who  tra\'eled  many  miles  upon  call  for  meetings,  lx)th  regular  and 
special,  in  order  to  participate  in  and  further  tlie  ongoing  work  of  AREA.  Witliout 
such  support,  the  desired  results  could  certainly  not  have  been  obtained. 

Certainly,  the  Conference  Operating  Committee,  headed  by  Bruce  Miller,  and 
who  was  ably  assisted  by  many,  must  be  praised  for  the  excellent  arrangements 
in  respect  to  these  meetings.  It  must  be  realized  there  are  many  hours  spent 
behind  the  scenes  by  this  fine  committee,  and  the  smoothness  of  the  operations 
simply  does  not  come  into  being  without  such  dedication. 

The  Association  expresses  appreciation  for  the  cooperation  during  the  year 
of  its  many  friends  in  the  supph'  industry  and  for  their  help  in  advancing  the 
cause  of  the  rail  industry,  as  a  whole,  and  AREA.  It  is  through  such  associations 
diat  our  jobs  are  made  easier.  Thank  you,  also,  for  your  excellent  attendance  at 
this  Technical  Conference. 

It  would  be  an  error  in  judgment  to  close  without  saluting  tlie  nation  on  its 
200tli  birthday.  I  am  particularK'  pleased  to  l>e  a  part  of  it  and  it  is  always  thrill- 
ing to  hear  and/or  see  the  action  in  respect  to  the  bicentennial  celebration  on 
radio,  tele%ision,  the  beautiful  presentation  at  Disney  World,  and  the  like.  These 
will  continue  throughout  the  year  and  will  certainly  add  to  the  efforts  of  all  in 
the  celebration. 

Business  boomed  during  the  mid- 18th  century  war  with  France.  American 
merchants  traded  freely  with  the  enemy  at  the  same  time  they  supplied  the  British 
army.  At  the  close  of  the  war,  howe\  er,  there  followed  a  traditional  postwar  letdown 
and  this  was  America's  first  depression.  This  was  a  shock  to  Americans,  and  they 
really   never   got   over   it,    even   when   prosperity   returned. 

There  were  many  causes  for  the  American  Re\olution  200  years  ago.  The  most 
important,  however,  was  the  threat  to  the  dream  of  an  economically  comfortable 
life  which  had  brought  most  Americans  to  these  shores  initially,  along  with  the 
desire  to  be  independent  and  free  from  oppression. 

Does  this  not  strike  a  parallel  with  conditions  as  they  exist  today?  As  stated 
in  my  opening  remarks,  the  year  just  closing  has  been  a  rather  tr>'ing  one.  Possibly 
it  was  not  a  depression,  as  such,  but  it  was  bordering  close  thereon  for  whatever 
it  may  be  called.  The  economy,  however,  is  now  on  the  way  up  and,  hopefully, 
it  will  continue.  This  will  make  the  job  easier  for  all  of  us.  As  was  noted  in  the 
January  issue  of  Railway  Tracks  and  Structures,  "The  next  ten  years  are  going  to 
be  the  most  exciting  period  ever  experienced  by  maintenance  of  way  men  every- 
where in  the  United  States."  Let's  get  going. 

Thank  you  for  the  honor  I  ha\e  had  this  year  in  serving  as  President  of  AREA. 
It  has  been  a  pleasure,  and  certainly  has  been  a  high  point  in  my  career  in  the 
rail    transportation   field. 


SPECIAL  FEATURES 


491 


Description  of  Architectural  Competition  Sponsored 
by  AREA  Committee  6^Buiidings 

77-658-1 

By  D.  A.  BESSEY 

Architect 
Chicago,   Milwaukee,    St.    Paul   &   Pacific   Railroad 

Article  I,  Sections  1  and  2,  of  the  American  Railway  Engineering  Association 
Constitution  reads  as  follows: 

"The  name  of  this  Association  shall  be  the  American  Railway 
Engineering  Association.  The  objective  of  the  Association  shall 
be  the  advancement  of  knowledge  pertaining  to  the  scientific 
and  economic  location,  construction,  operation  and  maintenance 
of  Railways." 

I  am  assuming  that  the  purpose  of  the  Association,  therefore,  is  to  assist  the 
engineers,  architects  and  all  other  people  involved  in  the  engineering  asiject  of 
our  industry.  So — it  appears  this  is  our  purpose  for  being  here.  This  very  definitely 
justifies   our   existence. 

Now,  we  of  Committee  6,  with  a  membership  comprised  of  architects  and 
engineers  direcdy  engaged  in  the  design,  construction  and  maintenance  of  our 
buildings,  ha\e,  over  a  number  of  years,  discussed  a  problem  that  not  only  seems 
unique  to  us,  but  possibly  is  unique  to  all  engineering  staffs  on  the  American 
railroads.  And  that  is  in  our  particular  case,  in  the  staffing  of  architecture  or  build- 
ing departments,  we  find  it  is  definitely  necessary  to  familiarize  the  architectural 
students  throughout  the  U.  S.  and  Canada  with  radroad  architecture  and  to  bring 
about  an  awareness  of  emplojTnent  opportunity  in  the  railroad  industr\'.  We  feel 
that  tliere  has  been  a  definite  need  to  improxe  tlie  communication  between  the 
railroad  industry'  and  the  colleges  and  universities  which  offer  an  architectural 
program  in  their  curriculum.  During  the  process  of  attaining  a  degree  in  architec- 
ture, the  architectural  student  has  numerous  design  classes  which  involve  the 
solution  of  problems,  and  in  many  cases,  the  architectural  problems  are  obtained 
from  corporations  or  associations,  and  the  process  of  solving  tlie  problem  is  part 
of  the  class  procedure. 

It  was  with  knowledge  of  this  process  that  the  AREA  Committee  6  Archi- 
tectural Competition  idea  came  to  life. 

In  December  of  1971  the  idea  of  an  Architectural  Competition  sponsored 
by  AREA  was  submitted  to  Committee  6  by  W.  C.  Stunn  who  is  presently  chair- 
man of  the  committee.  The  proposal  was  generally  accepted  by  the  committee 
and  we  pursued  it  further.  We  made  inquiries  of  architectural  schools  throughout 
the  country.  We  even  contacted  the  American  Institute  of  Architects  to  get  a  feel 
for  the  proposal.  The  reaction  of  uni\ersities  that  were  contacted  was  favorable,  so 
in  1974  a  committee  was  appointed  to  further  pursue  die  proposed  Architectural 
Competition.  At  this  time  the  special  committee  composed  a  preliminary  draft  of 
an  Architectural  Competition  Problem.  The  Problem  that  was  chosen  was  the 
design  of  a  control  tower  and  service  building  for  a  railroad  classification  yard. 
Committee  6  had  just  cx)mpleted  a  report  on  elevated  yardniasters   towers  which 


Note:   Discussion  open  until  October   15,   1976. 

493 


494  Bulletin  658 — American  Railway  Engineering  Association 

has  l)een  submitted  for  information  and  will  eventually  become  a  part  of  Chap- 
ter 6  and,  it  seemed  like  a  logical  type  building  to  use  for  this  Competition. 

I  would  like  to  present  a  short  pictorial  story  of  the  Architectural  Competi- 
tion project.  [The  slides  presented  are  not  reproduced  herein.] 

"What  does  a  railroad  architect  do — design  box  cars?"  I've  heard  that  ques- 
tion for  the  last  25  years.  But  now  I'm  sure  that  there  are  hundreds  of  architectural 
students  throughout  the  United  States  and  Canada  that  have  a  much  clearer 
understanding   of  railroad   architecture. 

On  March  25,  1975,  the  Board  of  Direction  of  AREA  approved  the  project 
and  allocated  the  necessary  funding  to  carry  out  the  Architectural  Design 
Competition. 

A  prehminary  draft  of  the  Architectural  Competition  Problem  was  sent  to 
79  colleges  and  universities  in  the  U.  S.  and  10  in  Canada,  for  a  total  of  89  schools 
of  architecture.  A  total  of  26  universities  responded  positively  and  indicated  that 
they  wished  to  consider  participation  in  the  Competition. 

At  the  June  meeting  of  Committee  6  the  final  draft  of  the  Architectural 
Problem  was  completed  by  the  membership  at  large.  A  representative  from  the 
membership  of  Committee  6  was  appointed  to  each  school  taking  part  in  the  Com- 
petition. This  representative  kept  in  close  contact  with  the  college  or  university 
and  assisted  the  school's  Architectural  staff  in  all  matters  dealing  with  the  Compe- 
tition. In  many  cases,  the  representative  arranged  for  the  students  involved  in  tlie 
project  to  visit  railroad  installations.  At  this  same  meeting  a  panel  of  7  judges, 
all  members  of  Committee  6,  were  appointed.  Included  on  the  panel  were  7  archi- 
tects with  excellent  credentials  holding  registration  in  13  States  and  1  Province 
in  Canada. 

The  Competition  Problem  was  typed  and  copies  of  the  Problem  were  printed, 
thanks  to  the  EJ&E  Print  Shop.  Approximately  900  copies  of  the  Competition  were 
mailed  out  to  the  26  universities  which  indicated  an  interest  in  taking  part  in 
the  Architectural  Competition.  We  only  worked  with  the  university  and  did  not 
work  directly  with  the  students  in  conducting  the  Competition. 

[A  list  of  the  participating  universities  may  be  found  in  the  report  of  Com- 
mittee 6  as  published  in  Bulletin  656,  January-Febmary  1976.] 

The  entries  were  mailed  to  my  office  and  I  received  most  of  them  by  Janu- 
ary 31.  The  Competition  was  judged  in  Chicago  on  February  9  and  10.  A  total 
of  96  entries  was  received  from  14  schools. 

All  entries  that  were  received  were  pre-judged  prior  to  the  9th  and  10th  of 
February  to  determine  if  there  were  any  great  deviations  from  the  rules  of  the 
Competition.  All  entries  were  numbered  and  the  name  of  the  architectural  student 
was  concealed. 

The  judging  took  place  on  February  9  and  10.  On  the  first  day  of  judging,  the 
judges  reviewed  all  the  96  entries  and  graded  them  on  the  basis  of  1  to  9.  At  the 
close  of  the  day,  the  judges  had  narrowed  the  96  entries  down  to  23.  As  the  judges 
finished  grading  the  entries  the  tally  clerks  calculated  the  scores.  On  the  second 
day  of  judging  the  remaining  entries  were  reduced  to  7.  From  the  7,  the  1st  place, 
2nd  place  and  5  Honorable  Mentions  were  chosen. 

Now  I  would  like  to  announce  the  winners  of  the  AREA  Committee  6  Architec- 
tural Competition.  The  5  students  receiving  Honorable  Mention  and  who  will  be 
awarded  a  $50  prize  are  as  follows:  Allen  L.  Brown — Oklahoma  State  University; 


Remarks  by  Don  McGee  495 


Glenn  Philips — Oklahoma  State  Uni\'ersity;  Christopher  M.  Conley — University 
of  Illinois;  Gary  Westfall — University  of  Illinois;  and  Dennis  L.  Norton,  Georgia 
Institute  of  Technology. 

The  second  place  winner,  who  will  receive  a  $250  prize,  is  Robert  Mease — 
Texas  Tech  University.  It  now  gives  us  great  pleasure  to  introduce  the  architectural 
student  winning  1st  place — Don  McGee  of  Texas  Tech  University. 

REMARKS  BY  DON  McGEE,  TEXAS  TECH  UNIVERSITY 

Mr.  Bessey  and  members  of  the  American  Railway  Engineering  Association, 
thank  you  for  the  opportunity  of  representing  my  school  and  myself  here  in  Chi- 
cago. I  consider  this  award  a  great  honor  and  asset  not  only  for  myself  but  also 
for  Texas  Tech  University.  The  students  and  faculty  are  honored  that  your  first 
and  second  place  awards  went  to  Texas  Tech  students. 

Before  I  begin  the  explanation  of  my  design,  I  thought  you  might  enjoy  hear- 
ing  some   general   information   concerning   Texas   Tech. 

Texas  Tech  University  is  located  in  Lubbock  on  the  South  Plains  of  Texas. 
Approximately  22,000  students  and  5,000  faculty  members  are  accommodated  on 
one  of  the  largest  campuses  in  America  which  is  in  excess  of  1,800  acres.  Students 
have  their  choice  of  studying  in  six  colleges  and  three  schools.  There  are  cur- 
rently in  excess  of  800  students  enrolled  in  architecture  which  is  a  department  of 
the  College  of  Engineering.  The  department  offers  a  Bachelor  of  Architecture  degree 
with  options  in  design,  structures,  history,  and  urban  design.  The  department  is 
housed  in  a  modern  12-level  facility  which  is  connectetl  with  the  art  department 
by  a  sub-level  courtyard. 

Approximately  70  senior  architecture  students  and  four  faculty  members  were 
involved  with  the  AREA  Architectural  Competition.  I  would  like  to  take  this  time 
to  thank  Professor  Burran  and  the  senior  design  faculty  and  fellow  students  for 
their  assistance  and  constructive  criticism  in  the  development  of  my  project. 

Since  I  had  never  been  exposed  to  railroad  control  towers,  service  buildings, 
and  classification  yards,  I  had  to  almost  totally  rely  on  the  problem  statement  for 
all  my  information.  The  people  responsible  for  writing  the  problem  statement 
deserve  some  special  recognition  for  providing  such  clear  and  concise  design  criteria. 
This  excellent  conmiunication  was  definitely  a  controlling  factor  in  the  result  of 
my   work. 

After  reading  and  studying  the  problem  statement,  my  major  objectives  were  to 
soke  the  specific  problems  posed  in  the  program:  to  design  an  economically  fea- 
sible facility  that  could  easily  be  implemented,  and  to  design  an  aesthetically 
pleasing  facility'  that  would  express  its  function.  The  major  problems  to  be  solved 
that  I  isolated  out  of  the  problem  statement  are: 

1.  The  problem  of  controlling  noise  generated  from   yard  operations  and   that 
noise  generated  from  within  the  facility  itself. 

2.  The  problem  of  separating  various  work  areas. 

3.  The  problem  of  insufficient  views  from  the  facility. 

4.  The  problem  of  coordinating  the  various  functions  of  the  facility  in  a  logi- 
cal order. 

5.  The  problem  of  creating  an  aesthetically  pleasing  facility. 

6.  The   problem   of   selecting   mechanical   and   structural   systems   which   could 
accommodate  the  various  environmental  demands  of  the  facility. 


496  Bulletin  658 — American  Railway  Engineering  Association 

The  next  step  was  to  use  the  information  made  available  to  me  and  additional 
research  to  find  the  solutions  to  the  isolated  problems. 

One  of  my  major  concerns  is  to  protect  employees  and  highly  sensitive  equip- 
ment from  the  intense  sound  generated  by  the  retarders  located  in  the  hump  yard. 
This  problem  is  handled  in  several  ways: 

1.  Lowering  a  portion  of  the  building  below  grade. 

2.  Building  berms  around  the  facility  to  reflect  sound  waves. 

3.  By  using  as  few  windows  as  possible  and  locating  only  the  vdndows  in  the 
control  tower  facing  the  tracks.  All  exterior  windows  are  also  double  glazed. 

4.  No  doors  are  allowed  to  open  directly  into  the  yard. 

5.  All   skylights   are   double  glazed. 

6.  The  selections  of  building  materials  are  chosen  for  their  mass  to  restrict 
sovmd  waves.  These  materials  include  concrete  block,  concrete  panels,  rigid 
insulation,  and  river  rock. 

7.  Using  spaces  seldom  used  by  employees  as  buffer  zones  adjacent  to  the 
tracks. 

The  solution  to  the  problem  of  noise  generated  from  within  the  facility  is  to 
simply  concentrate  and  isolate  these  noise  generators  from  the  rest  of  the  facility. 
As  a  result,  the  shop,  mechanical  equipment  room,  and  compressor  room  are 
actually  contained  in  a  separate  building  and  then  located  next  to  the  locker  rooms 
so  that  any  escaping  noise  does  not  disturb  sensitive  equipment  and  employees. 

It  is  very  important  to  separate  the  various  facilities  and  work  areas  with 
as  few  physical  elements  as  possible. 

Due  to  the  nature  of  the  surrounding  areas,  which  contain  railroad  tracks,  an 
interstate  highway,  and  a  nearby  airport,  I  felt  that  there  weren't  any  significant 
visual  attractions  to  capitalize  on.  So  without  any  available  views,  the  facility  is 
designed  to  look  inward  instead  of  outwards.  An  environment  has  to  be  created 
since  an  appropriate  one  is  not  available.  As  one  enters  the  facihty  he  must  pass 
through  some  transitional  areas.  These  transitional  areas  act  as  buffers  between  the 
harsh  exterior  environment  and  the  "new"  environment.  The  "new"  environment  is 
achieved  through  the  use  of  a  large  space  at  a  human  scale.  The  space  is  given  an 
indoor-outdoor  relationship  by: 

1.  Using  the  same  materials  that  are  used  on  the  exterior. 

2.  Introducing  vegetation  through  the  use  of  planters. 

3.  Placing  a  large  window  wall  adjacent  to  the  enclosed  landscaped  court- 
yard. 

4.  Introducing  natural  light  through  the  skylights  and  from  the  window  wall. 

The  space  not  only  accommodates  many  functions,  but  serves  as  an  interior 
courtyard  which  is  viewed  from  other  spaces,   such  as  the  office  area. 

The  diffierent  functions  of  the  facility  are  located  so  that  they  can  operate 
efficiently.  The  electronic  equipment  room,  electronic  storage  room,  electronic  equip- 
ment repair  area  all  rely  on  each  other,  so  they  are  located  accordingly.  The 
office,  computer  room,  and  communication  room  also  have  complementing  func- 
tions and  are  located  accordingly.  This  area  is  located  near  to  the  vertical  access 
to  control  tower  because  of  their  electronic  and  coiiununication  relationship.  The 
control  tower  location  is  a  result  of  obtaining  the  best  possible  views  in  order  to 
maintain  control  over  yard  operations.  The  control  tower's  form  also  expresses  this. 


Address  by  D.  A.  Bessey  497 


The  service  corridor  in  die  control  tower  is  designed  to  keep  the  service  func- 
tions (rest  room  and  vertical  transportation)  to  the  control  room  from  interfering 
with  its  function.  All  rest  rooms  and  locker  rooms  are  off  the  interior  courtyard  for 
convenience.  This  courtyard  becomes  the  heart  of  the  facility.  It  controls  all  of 
the  traffic  to  and  from  the  different  spaces.  The  rest  rooms  and  locker  rooms  are 
designed  for  efficiency  in  flow.  The  shop,  mechanical  equipment  room,  and  com- 
pressor room  are  located  near  each  other,  not  only  to  concentrate  noise,  but  due 
to  their  interdependence  on  each  other  through   their  function   and  maintenance. 

An  attempt  is  made  to  improve  the  surrounding  environment  by  creating 
an  aesthetically  pleasing  facility.  The  equipment,  such  as  the  air  reservoir  tank  and 
cooling  tower,  that  must  be  outside  are  concentrated  in  one  area  and  screened. 
This  area  becomes  part  of  the  overall  architectural  statement.  The  parking  area 
is  not  located  directly  in  front  of  the  facility,  but  located  to  the  side  and  bermed 
and  landscaped  to  de-emphasize  it.  This  also  keeps  the  parking  facilities  from 
becoming  just  a  sea  of  concrete  and  asphalt.  All  elevations  were  studied  with 
composition  and  human  scale  considerations. 

Due  to  the  diverse  activities  that  take  place  in  the  facility  each  activity  re- 
quires a  different  environment,  for  instance,  the  computer  equipment  must  remain 
at  a  constant  temperature.  This  is  achieved  through  the  use  of  a  zoned  mechani- 
cal system.  Each  zone  can  l)e  controlled  independently  of  the  other  zones.  Load- 
bearing  walls  and  open-web  steel  joists  are  used  to  provide  spaces  with  clear  spans 
for  flexibility. 

Thank  you  again  for  this  honor.  This  will  certainly  be  an  asset  in  my  career. 
I  hope  that  I  have  fulfilled  my  job  of  proxiding  you  with  a  functional,  economically 
feasible,   and   implementable   facility. 

CONCLUDING  REMARKS  BY  MR.  BESSEY 

At  this  time  I  would  like  to  ask  Mr.  Ward  if  he  would  make  the  presenta- 
tion of  the  1st  place  award  to  Don  McGee. 

[President  Ward  presented  to  Don  McGee  a  placque  and  a  check  for  $500.] 

Thank  you,  Mr.  Ward.  Once  again  I  would  like  to  congratulate  you,  Don 
McGee,  for  your  first  place  award  and  assign  you  the  responsibility  of  representing 
the  some  800  to  850  students  throughout  the  U.  S.  and  Canada  who  were 
involved  in  this  Architectural  Competition. 

In  addition  to  the  placque  and  certificate  that  was  awarded  to  Mr.  McGee, 
similar  certificates  were  awarded  to  Mr.  Mease,  and  the  5  Honorable  Mention 
students.  Certificates  of  Merit  will  be  mailed  to  each  of  the  96  students  who 
submitted  an  entiy. 

It  is  our  hope  to  maintain  correspondence  with  not  only  these  universities 
that  entered  the  Competition,  but  all  universities  throughout  the  U.  S.  and 
Canada.  This  has  been  an  extremely  rewarding  undertaking  and  I  am  pleased  to 
have  been  a  part  of  it.  On  behalf  of  Committee  6  and  all  those  people  on  the 
Committee  that  worked  on  the  Competition  and  all  the  students  who  took  part 
in  it,  I  would  certainly  like  to  thank  the  Association  for  sponsoring  and  funding 
this  Competition. 

I  guess  at  this  point  I  could  thank  a  lot  of  people. 

I  certainly  must  recognize  Wally  Sturm  in  the  part  he  played  in  this  Com- 
petition helping  to  write  the  program,  printing  and  mailing  the  Competition  to 
the  Universities. 


498  Bulletin  658 — American  Railway  Engineering  Association 

Dick  Milbaucr  arraiij^ed  tor  all  the  awards,  placqncs  and  certificates. 

The  Judges — who  not  only  put  in  a  full  two  days,  but  spent  considerable 
time  preparing  for  the  judging  process. 

The  15  representatives  of  Committee  6  who  went  to  the  imiversities,  worked 
with   the   students   and   with  the  professors. 

All  the  rest  of  the  meml>ers  of  Committee  6  who  have,  for  the  past  three  or 
four  years,  worked  on  this  project  either  by  contacting  universities  initially,  helping 
write  the  program,  helping  write  the  judging  process  and  all  the  other  numerous 
things  that  had  to  be  done  to  make  tliis  project  a  great  success. 

All  in  all,  of  the  36  members  of  Committee  6,  approximately  30  were  in- 
volved in  the  Competition  in  one  way  or  the  other — as  a  judge,  as  a  representative, 
writing  the  program  and  making  the  initial  contacts  with  the  universities. 

As  director  of  the  Competition,  I  am  a  past  chairman  of  Committee  6;  Wally 
Sturm  is  the  present  chairman  of  Committee  6;  and  of  the  judges,  Ken  Hornung, 
past  chairman  of  Committee  6;  Bill  Humphreys,  past  chairman  of  Committee  6; 
Stan  Urban,  past  chairman  of  Committee  6,  and  the  only  other  past  chairman, 
John  Hayes,  retired  architect,  Burlington  Northern,  made  some  initial  contacts 
with  universities.  So — past  chairmen  of  Committee  6 — don't  fade  away! 

In  my  conversations  with  numerous  imiversities  over  a  period  of  the  last  year, 
and  especially  the  last  few  weeks  of  the  Competition,  I  received  feedback  from 
these  schools  that  not  only  are  they  interested  in  remaining  closely  affiliated  with 
the  railroad  industry  in  the  school  of  Architecture,  but  other  schools  on  the  uni- 
versity campuses  are  considering  re-installing  railroad-oriented  courses  tliroughout 
their  engineering  school.  So  if  this  Competition  has  done  anything,  it  has  re- 
created an  interest  among  the  universities  throughout  the  U.  S.  and  Canada  to 
develop  and  maintain  a  closer  relationship  between  the  civil  and  structural  engi- 
neers, mechanical  engineers,  architectural  and  all  other  engineering-based  schools 
with  the  railroad  industry. 

The  first  few  lines  of  our  Constitution  describe  our  purpose.  But,  we  cannot 
carry  out  the  engineering  functions  of  our  railroad  without  the  ability  to  staff 
our  offices  with  the  civil  and  structural  engineers,  mechanical  and  general  engi- 
neering people  and  the  architects  from  the  campuses  from  the  colleges  and  univer- 
sities throughout  the  U.  S.  and  Canada.  I  am  pleased  diat  this  project  has  opened 
some  doors  and  has  created  some  interest  among  the  students  who  will  some  day 
become  a  part  of  our  industry  and  will  some  day  be  a  part  of  this  organization — 
and  will  help  us  live  up  to  the  first  three  or  four  lines  of  our  Constitution. 

I  am  very  pleased  to  have  been  a  part  of  this  project.  I  am  very  proud  to  be 
a  member  of  Committee  6  and  I  am  very  proud  to  be  a  member  of  American  Rail- 
way   Engineering    Association. 

I  think  we  have  taken  a  giant  step  forward. 


Track  Maintenance  for  High-Speed  Trains 

77-658-2 

By  HAROLD   H.   JENKINS,   C.E.,  M.I.C.E. 

Permanent   Way    Engineer 
British    Railways    Board 

In  order  to  understand  British  Railways'  readiness  to  accept  on  its  main  lines 
high-speed  trains,  it  is  necessary  to  explain  very  briefly  changes  that  have  already 
taken  place  in  BR's  track  structure. 

Immediately  after  the  war,  the  railway  system  was  in  a  relatively  poor  state 
of  maintenance,  with  an  overall  speed  limit  of  75  mph,  due  to  shortages  of  material 
and  labor  throughout  the  war  period.  The  methods  of  maintenance  were  almost 
entirely  manual.  Labor,  especially  of  the  right  quality,  was  difficult  to  obtain,  and 
to  hold.  Railway  track  jobs  offered  lieavy  work,  in  all  weathers,  and  relatively  low 
wages,  and  compared  with  jobs  on  offer  in  the  expanding  motor  trade  were 
unattractive. 

BR's  track  at  this  time  was  mainly  bull-head  rail,  95  lb/yd,  on  chaired, 
creosoted  softwood  sleepers.  Its  life  in  the  main  line  was  between  17  and  25 
years.  (Photograph  1)  The  standard  sleeper  spacing  was  2  ft  6  in.  and  depth  of 
ballast  under  sleeper  5  or  6  in.  Ballast  was  mainly  limestone.  The  day-to-day 
maintenance  was  carried  out  by  small  gangs  (5,  6  or  8  men  including  the  Ganger). 
The  manning  for  daily  maintenance  was  approximately  1  man  per  track  mile. 
The  track  renewals  were  usually  carried  out  in  /2-mile  or  /i-mile,  occasionally 
1-mile,  lengths.  This  work  was  normally  carried  out  on  Sundays  and  preparation 
and  finishing  work  on  weekdays.  The  relaying  gang  (18  to  21  men)  supplemented 
on  the  Sunday  by  maintenance  men  carried  out  this  work.  In  addition  there  were 
extra  gangs  for  drain  and  earth-work  maintenance.  This  system  \\'as  highly  labor 
intensive. 

The  first  priority  was  to  restore  the  tracks  for  90  mph  running.  Trials  just 
prior  to  the  war  with  flat-bottom  rails  109  and  113  indicated  economies  especially 
in  the  displacement  of  the  cast  iron  "chair"  and  its  wooden  or  steel  key. 

The  need  for  more  ballast  under  tlie  sleepers  was  apparent.  BR  then  pro- 
duced a  desired  standard  of  flat-bottom  rails  on  baseplates  with  "Elastic"  or 
"McBeth"  spikes  and  increased  required  ballast  depth  below  sleeper  bottom  to 
8  in.,  with  shoulders  12  in.  wide  from  sleeper  ends.   (Also  shown  in  Photograph  1) 

The  scarcity  of  timber  during  the  war  period  encouraged  the  development  of 
concrete  sleepers.  The  earliest  type,  known  as  a  "pot"  sleeper,  consisted  of  two 
concrete  blocks,  one  under  each  rail,  and  connected  by  steel  angle  tie-bars  to 
hold  gauge.  Cast  iron  chairs  (baseplates)  for  bull-head  rail  were  fixed  by  bolts  set 
into  tlie  concrete.  Although  tlie  concrete  blocks  did  not  crack  or  breakup  under 
traffic,  considerable  difficulty  was  experienced  in  trying  to  maintain  the  track 
gauge.  The  blocks  were  apt  to  tilt  either  inwards  or  out\\'ards  and  produced  unac- 
ceptable gauge  variations.  After  a  year  or  so  their  use  was  restricted  to  sidings; 
those  in  nmning  lines  were  removed  and  used  as  drainage  channel  block  walls,  and 
even  small  retaining  walls.   Finally  the  use  even  in  sidings  was  banned. 

Experiments  with  monoblock  prestressed  concrete  sleepers  continued  and  the 
El  type  using  CI  chairs  and  bull-head  rail  were  proving  successful.  (Photograph  2) 


Note:   Discussion  open  until  October   15,   1976. 

499 


500 


Bulletin  658 — American  Railway  Engineering  Association 


Photograph  1 — (Foreground)  BS  95-lb  bull-head  rail,  softwood  sleepers,  cast-iron 
chairs,  steel  keys.  (Background)  BS  109-lb  flat-bottom  rail,  softwood  sleepers,  base 
plates,  Elastic  Spikes. 


-^l|S5rT%'**^ 


Photograph  2 — Early  "El"  type  concrete  sleepers  for  bull-head  rail. 


Address  by  Harold  H.  Jenkins  501 

About  this  time,  timber  sleepers  were  increasing  rapidly  in  price.  The  life  of 
a  wooden  sleeper  varied  considerably,  depending  not  only  on  differences  in  spe- 
cies, but  also  on  differences  in  climatic  conditions,  and  in  resistance  to  decay. 
Differences  in  life  were  apparent  even  with  sleepers  cut  from  the  same  species  in 
the  same  forest  Init  from  different  trees. 

Trials  were  made  with  specially  selected  hardwoods  (Australian  Jarrah).  The 
results  of  the  trials  showed  that  the  Jarrah  sleeper  had  a  significantly  increased 
life  compared  with  softwood  and  the  behavior  of  the  Jarrah  was  much  more 
consistent.  However  even  without  the  need  to  treat  with  creosote,  the  Jarrah  sleeper 
was  much  more  expensive. 

Development  of  concrete  sleepers  proceeded  fairly  rapidly  and  it  became 
obvious  that  it  was  feasible  to  design  a  concrete  sleeper  for  any  type  of  loading, 
any  type  of  rail  and  any  type  of  gauge.  Furthermore  the  sleeper  life  could  be 
extended  well  beyond  that  of  any  wooden  sleeper. 

The  increasing  costs  of  labor  indicated  the  need  for  a  track  assembly  with 
minimum  maintenance.  A  concrete  sleeper  with  long  life  was  the  obvious  solution, 
but  the  rail  fastenings  then  available  required  considerable  maintenance  attention. 
Developments  and  trials  with  all  known  and  many  new  types  of  fastenings  were 
tried;  at  one  time  BR  had  under  trial  in  the  running  lines,  over  30  different  types 
of  fastenings,  including  the  best  of  those  used  in  Europe. 

It  soon  became  apparent  that  the  assembly  requiring  minimum  maintenance 
was  that  which  did  not  require: 

(a)  Any  screw  or  nut. 

(b)  Any  plug  in  the  sleeper  to  take  another  metal  insert  of  any  kind. 

(c)  Any  reliance  of  a  cast  concrete  shoulder  to  hold  gauge. 

The  reasons  being: 

Screws  and  nuts  require  regular  attention;  tightening  as  they  work  loose,  and 
oiling  to  prevent  rusting  and  seizing  up. 

Plugs  (wood,  rubber,  plastic,  etc.)  in  concrete  sleepers  eventually  work  loose 
and  cause  serious  problems  in  correction,  and  on  BR's  main  lines,  within  10  years  of 
installation,  all  such  assemblies  will  have  to  be  removed  or  provided  with  expen- 
sive temporary  maintenance  fastenings  until  complete  replacement  can  be  car- 
ried out. 

Similarly,  evidence  indicates  that  concrete  shoulders  cannot  alone  be  relied 
upon  to  keep  gauge.  In  time  the  vibration  and  repetitive  lateral  loadings  will 
almost  certainly  cause  the  concrete  shoulder  to  deteriorate  and  crumble,  well  within 
the  expected  life  of  modem  concrete  sleepers  of  the  F23,  F27  types.  (Photograph  3) 

In  these  modern  types,  the  problem  has  been  overcome  by  casting  hoops  or 
metal  inserts  in  the  sleeper  for  use  not  only  as  part  of  the  fastening  fixing  but 
also  as  the  gauge  stop.  After  the  completion  of  many  years  of  testing,  BR  has 
standardized  on  the  F27  prestressed  concrete  sleeper  with  the  Pandrol  fastening. 
The  rail  is  seated  on  a  rail  pad  ( niliber-bonded  cork  or  similar)  specially  designed 
to  provide  in  the  assembly  sufficient  elasticity  to  cushion  the  effects  of  dynamic 
loadings — in  particular  to  absorb  the  rail  deflection  due  to  the  procession  and 
recession  waves  caused  by  each  axle,  and  at  the  same  time  to  retain  with  the 
Pandrol  fastening,  adequate  toe-load,  resistance  to  rail  creep  and  torsional  move- 
ment of  the  rail. 


502 


Bulletin  658 — American  Railway  Engineering  Association 


Photograph  3 — Latest  concrete  sleepers,  F27. 


The  malleable-iron  insert  designed  to  hold  the  Pandrol  fastening  is  fixed 
into  the  mold  when  casting  the  sleeper  and  provides  a  positive  gauge  stop  which 
enables  accurate  gauge  to  be  guaranteed.  The  Pandrol  clip  is  driven  into  the  in- 
sert and  onto  the  rail  foot  (on  BR  an  insulator,  preferably  with  a  metal  cover  plate, 
is  used  for  track  circuiting  purposes). 

The  assembly  has  no  nuts  and  no  screws  to  work  loose,  nor  to  be  tightened 
nor  oiled;  it  has  no  baseplates  with  fastenings  requiring  additional  tolerances  so 
that  it  has  an  accurate  initial  and  lasting  gauge.  In  other  words  it  is  virtually  a 
maintenance-free  fastening  assembly. 

Meanwliile  further  developments  in  welding  techniques  enabled  the  change- 
over to  continuous  welded  rail  and  tlie  elimination  of  joints  in  the  track.  This  meant 
that  greater  thermal  forces  had  to  be  resisted  by  the  sleepers,  i.e.,  in  the  lateral 
direction  to  prevent  buckling  of  the  track  in  hot  weather  and  in  tlie  longitudinal 
direction  in  all  weathers  to  prevent  sleepers  moving  forwards  or  backwards  with 


Address  by  Harold  H.  Jenkins  503 


the  changing  rail  temperatines,  and  finally  vertically  to  prevent  upwards  distortion. 
For  all  these  puiposcs  the  hea\y  concrete  sleeper  was  ideal — and  although  some 
lengths  were  installed  on  baseplated  wooden  sleepers,  at  least  25%  more  sleepers 
were  necessary  per  mile  than  if  concrete  sleepers  were  used. 

At  this  time  BR  were  installing  about  500  miles  each  year  of  continuous 
wielded  rail  (CWR)  with  concrete  sleepers,  at  2-ft.  6-in.  spacings  and  some  lengths 
with  hardwood  sleepers  at  2-ft  spacings. 

With  the  "Beeching"  cuts  in  the  total  mileage  of  the  BR  system,  some  lines 
containing  the  bull-head  rtiils  and  earlier  concrete  sleepers  were  taken  up  after 
20  years  or  more  in  the  track.  The  condition  of  these  concrete  sleepers  was  so  good 
that  it  was  decided  to  take  off  the  bull-head  chairs  and  replate  them  for  use  with 
Hat-bottom  rail.  Several  hundreds  of  thousands  have  been  so  modified  and  put 
back  into  the  tracks  for  a  further  long  life. 

It  should  be  noted  that  the  prestressed  concrete  sleeper  is  designed  to  carry 
the  specified  dynamic  loadings  foreseen  for  the  life  of  the  sleeper.  The  design  can 
be  modified  to  suit  any  other  type  of  dynamic  loadings — heavier  (or  lighter  axles). 
Prestressed  sleepers  (of  the  BR  type)  have  been  made  suitable  for  the  33-ton 
axles  on  the  Canadian  National  Railways  and  iron  ore  lines  in  Australia,  whilst 
on  BR  special  types  have  been  made  for  use  at  heavily  worked  joints,  for  single- 
and  double-checked  curve,  and  shallower  types  for  use  in  places  with  restricted 
headroom,  e.g.,  in  tunnels  of  small  diameter,  under  overhead  electric  wires  where 
it  is  not  practicable  to  lower  out,  under  bridges,  etc. 

So  far  BR  have  laid  in  nearly  20  million  concrete  sleepers  (equivalent  to 
approximately  8500  miles)  and  for  the  last  eight  years  have  averaged  1.2  million 
per  annum,  with  a  similar  rate  programmed  for  the  next  5  years.  The  number  of 
failures  is  exceedingly  small,  and  when  they  have  occurred  have  always  been 
associated  with  poor  track  maintenance,  epecially  insufficient  ballast  on  temporary 
jointed   track — awaiting   the   installation   of   continuous   welded   rails. 

Meanwhile  labor  was  becoming  more  and  more  expensive  and  difficult  to 
obtain,  and  it  was  essential  that  the  existing  labor  force  be  used  more  efficiently, 
and  the  requirement  for  labor  had  to  be  reduced.  This  led  to  the  need  for  mechani- 
zation, to  the  need  for  track  reciuiring  less  attention  and  more  planning  of  the  work. 
It  was  the  introduction  of  Work  Study  (work  measurement  and  method  study) 
that  for  the  first  time  provided  accurate  infomiation  of  the  actual  work  involved 
in  each  and  every  task;  e.g.,  it  indicated  nearly  50%  of  all  the  labor  used  was  spent 
on  joint  maintenance.  The  method  study  indicated  better  ways  of  doing  the  job. 
With  the  unions'  cooperation.  Work  Study  coupled  with  a  bonus  incentive  scheme 
was  introduced.  It  took  approximately  four  yejxrs  to  introduce  it  all  over  BR  and 
the  results  were  outstanding — the  labor  requirement  was  reduced  by  about  30%. 
The  output  per  man  increased  by  50%.  Abortive  and  umiecessary  work  was  elimi- 
nated and  more  essential  work  was  carried  out. 

From  the  data  and  information  obtained,  the  actual  cost  of  any  operation 
was  available.  These  facts  enabled  financial  justifications  to  be  correctly  assessed 
for  continuous  welded  rail  instead  of  jointed,  for  concrete  sleepers  instead  of  hard- 
wood or  softwood  sleepers  and  last  but  by  no  means  least  for  the  purchase  of 
heavy  relaying  and  maintenance  machines  to  reduce  still  furtlier  the  labor  rec^uire- 
ments.  So  around  about  1963-64  my  then  chief  civil  engineer,  A.  N.  Rutland, 
put  all  these  developments  together  and  formulated  new  plans  for  BR's  future  track 
maintenance  and  renewals. 


504  Bulletin  658 — American  Railway  Engineering  Association 

With  the  BR  Board's  approval  mechanization  proceeded  apace  and  purchases 
were  made  of  automatic  tamping  machines,  lining  machines,  ballast  cleaners,  etc,  etc., 
all  fully  financially  and  technically  justified.  Standardization  of  the  main-line  track 
structure  was  introduced.  FB  llOA  (later  FB  113)  rails  (53  tons  (short)  sq.  in. 
tensile  steel)  in  continuous  welded  rail  with  F27  prestressed  concrete  sleepers, 
Pandrol  clips,  rubber-bonded  cork  rail  pads,  plastic  insulators  and  minimum  depth 
of  ballast,  minimum  width  of  ballast  shoulders.  (Also  shown  in  Photograph  3) 

The  "Butland"  plan  included  "premature"  renewals  (instead  of  replacing  only 
life-expired  track)  which  enabled  tlie  10  selected  major  routes  of  the  system  to  be 
relayed  to  the  new  standard  within  approximately  5  years.  It  is  on  these  routes  that 
the  high-speed  trains  are  scheduled  to  run,  and  will  commence  this  year. 

During  the  same  period  of  development,  studies  with  freight  vehicles  at 
28-ton  (short)  axles  proceeded,  and  accepted  for  running  at  60  mph  (100  km/h), 
and  experience  since  indicates  no  increase  in  rail  failures,  although  the  rate  of 
track   settlement   has  increased   indicating  a  need  for  marginally  earlier  tamping. 

The  28-ton  axle  is  about  the  Hmit  for  the  class  of  rail  steel  with  tensile  strength 
of  53  short  tons/sq.  in.  (70  kg  mm")  which  exists  throughout  BR.  It  should 
be  noted  that  none  of  the  continental  railways,  even  with  the  steel  70  kg  mm"  and 
90  kg  mnr  tensile  strength  has  accepted  22  tonne  (24/2  short  tons)  axles. 

The  demand  for  higher  speeds  has  been  universal  and  with  the  Japanese  com- 
mencing services  at  200  km/h  the  demand  in  Europe  increased. 

Numerous  studies  were  in  hand  on  BR  and  on  the  Continent.  In  Europe  high 
speed  is  usually  regarded  as  160  km/h  (100  mph)  up  to  300  km/h  (186  mph) 
and  very  high  speed  above  300  km/h  (186  mph).  Experts  consider  that  400  km/h 
(250  mph)  is  likely  to  be  the  maximum  for  the  steel  wheel  on  steel  rail  witli 
present  knowledge  of  adhesion,  braking  and  acceleration. 

The  BR  studies  covered  first  the  running  of  conventional  type  trains  at  speeds 
of  125  mph  (200  km/h)  on  existing  tracks  witii  tlie  possibilities  of  speeds  up  to 
186  mph  (300  km/h)  on  new  tracks,  and  secondly  the  running  of  "tilting"  trains — 
the  APT  (Advanced  Passenger  Train)  on  existing  tracks  with  high  cant  deficiencies 
at  speeds  up  to  155  mph  (250  km/h). 

The  track  problems  arising  from  increasing  the  speeds  of  conventional  trains 
on  the  main  lines  to  125  mph  were  easy  to  pin-point  but  more  difficult  to  assess 
in  work  load.  The  increased  speed  would  produce  increased  dynamic  loadings, 
and  increased  lateral  loadings,  but  no  real  data  was  available.  Numerous  tests 
were  carried  out  with  different  locomotives  running  at  speeds  from  20  mph  in 
steps  of  10  mph  to  130  mph  and  the  vertical  forces  recorded  at  the  axle-boxes  and 
on  load-measuring  baseplates  on  the  sleepers,  including  a  preformed  vertical 
irregularity  ("dip"),  and  from  all  these  tests  it  was  possible  to  derive  a  formula 
linking  tlie  speed,  axle-loading,  unsprung  mass,  track  irregularity,  etc.,  to  the 
vertical  forces. 

Although  this  formula  does  not  provide  the  absolute  forces  it  does  provide  an 
indication  of  relative  vertical  forces  which  would  be  experienced.  It  was  decided 
to  accept  the  vertical  forces  produced  by  the  Deltic  locomotive  running  at  100  mph 
as  the  maximum  reference  limit.  This  type  of  locomotive  had  been  in  regular 
service  for  many  years  and  its  effects  on  track  maintenance  fairly  well  established. 

The  vertical  forces  considered  to  be  most  important  are  those  (known  as 
the  P2  forces)  that  are  transmitted  to  the  rail  and  through  to  the  ballast  and  the 
impact  forces   (known  as  PI  forces)   at  the  joint  or  irregularity  which  are  experi- 


Address  by  Harold  H.  Jenkins  505 


enced  only  by  the  rail.  It  was  agreed  to  accept  a  "dip"  of  0.2  radians  (Vz  in.  dip 
over  20-ft)  as  the  "fixed"  maximum  irregularity  for  all  future  comparative  meas- 
urements of  vertical  forces,  and  therefore  the  Deltic  Locomotive  nmning  at  100  mph 
over  such  an  irregularity  would  produce  the  maximum  acceptable  vertical  forces, 
and  these  have  been  calciJated  and  checked  by  measurements  to  be 

PI  52  tons  per  wheel  (58)2  short  tons) 
P2  34  tons  per  wheel   (38J2  short  tons) 

The  formulas  are  shown  in  Fig.  1. 

It  can  be  seen  tliat  the  PI  force  is  related  to  speed  and  size  of  imegularity, 
and  insignificandy  relative  to  unsprung  mass.  It  is  the  PI  force  that  causes  rail 
batter  but  is  of  such  short  duration  that  whilst  it  contributes  to  forces  in  the  rail, 
and  at  bolt  holes  it  has  practically  no  effect  on  the  sleepers  nor  on  the  ballast. 

The  P2  force  is  the  vertical  force  which  contributes  to  the  rail  stresses  includ- 
ing bolt  holes  and  is  then  transmitted  through  the  rail  to  the  sleepers  and  to  the 
ballast.  It  must  be  noted  that  the  formulas  are  considered  satisfactory  for  compari- 
son of  vehicles  \\ith  modem  suspension  systems.  They  are  not  completely  satisfac- 
tory for  evaluating  the  forces  produced  by  older  type  freight  vehicles  with  single 
suspension  systems  as  the  "sprung  mass"  in  these  older  vehicles  does  have  an 
increasing  effect  with  speed. 

For  all  vehicles  the  "wheel  flat"  is  a  very  important  factor  and  on  BR  per- 
missible maximum  hmits  are  laid  down  for  each  type  of  vehicle  and  speed  band. 
The  high-speed  conventional  trains  (HST's)  for  service  running  have  axle 
loads  of  I8J2  short  tons  (16)3  Imperial  tons)  and  unsprung  mass  of  2?i  short  tons, 
and  the  relative  PI  forces  would  be  67  short  tons  per  wheel  and  the  critical  P2 
force  35  short  tons  (33  Imperial  tons).  (Photograph  4) 

It  is  true  that  with  continuous  welded  rail  and  main-hne  standards  the 
irregularity  used  as  a  basis  is  most  unlikely  to  be  present  in  practice  so  that  the 
PI  force  excess  has  been  accepted  and  the  P2  force  is  actually  less  than  that 
produced  by  the  Deltic.  This  means  that  provided  the  lateral  forces  are  no  greater 
than  tliose  of  the  Deltic  today  then  there  is  no  increase  in  the  rate  of  track 
deterioration. 

The  lateriU  forces  are  mainly  comprised  of  guiding  forces  tlirough  curved 
track  and  centrifugal  forces  due  to  cant  deficiency.  Obviously,  increasing  the 
speed  on  existing  cant  and  curves  will  increase  the  lateral  forces.  BR's  standard  for- 
mulas for  cant  and  curvature  are  fairly  well  kTiown  and  only  recently  a  working 
party  of  UIC  was  set  up  to  examine  all  the  limits  fixed  by  its  members  and  set  out 
recommended  limits  for  every  i^arameter.  BR  is  the  only  member  administration 
which  at  present  meets  every  one  of  the  recommendations. 

The  principle  BR  limits  concerning  high  speed  nmning  are: 

Maximum  actual  cant 6     in.   ( 150mm) 

Maximum   deficiency    4/4  in.   ( 110mm) 

Desirable  rate  of  change  of  cant  or  deficiency  ....    l/s  in.   (    35mm)  per  sec 
Maximum  permitted  rate  of  change  of  cant 

or  deficiency   2/8  in.   (   55mm)  per  sec 

(a)   The  maximum  actual  cant  of  6  in.   is  very  similar  to  that  adopted  by 
most  major  railway  administrations  with  standard  gauge.  It  is  so  limited 


506 


Bulletin  658 — American  Railway  Engineering  Association 


6  8  10  12 

TIME    (milusecs) 


DYNAMIC    INCREMENT   OF    PI 

DYNAMIC 

INCREMENT    OF     P2 

DEPENDS    MAINLY     UPON     ! 

DEPENDS    MAINLY     UPON     : 

SPEED 

V 

SPEED 

V 

JOINT     ANGLE 

a 

JOINT     ANGLE 

0( 

CONTACT  STIFFNESS 

Kh 

UNSPRUNG  VEHICLE  MASS 

Mu 

EFFECTIVE   TRACK    MASS 

Me 

TRACK    BALLAST  STIFFNESS 

Ks 

UNSPRUNG    VEHICLE    MASS 

Mu 

TRACK    BALLAST   DAMPING 

Cs 

EQUIVALENT  TRACK  MASS 

Mt 

••     STIFFNESS 

Kt 

••     DAMPING 

1 

Ct 

P2=  P0  +  2OCV. 

Mu 

2 

1  -  Ct.TT 

yKT.Hu 

Mu  +  Mt 

4Kt.{Mu+Mt) 

Fig.  1 


Address  by  Harold  H.  Jenkins 


507 


BRs  high-speed  train  (H.S.T. 


because  of  the  possibiUty  of  overturning  if  a  van  is  left  standing  on 
6  in.  canted  track  (1  in  10)  in  high  winds  or  gales, 
(b)  After  numerous  trials  the  ma.ximum  deficiency  and  the  rate  of  change 
of  cant  (or  rate  of  change  of  deficiency)  were  all  selected  as  the  limits 
for  reasonable  passenger  comfort  (including  walking  in  the  train  cor- 
ridors or  eating  in  the  restaurant  car).  They  are  therefore  arbitrary 
limits  and  not  factors  of  safety — so  that  if  means  can  be  found  to 
maintain  passenger  comfort  then  higher  deHciences  and  rates  of  change 
of  cant  will  be  possible.  This  is  the  idea  behind  "tilting  body"  trains 
and  BR's  APT's.  The  limit  will  then  have  to  be  set  by  the  track 
resistance  to  lateral  forces  arising  from  higher  deficiencies  and  higher 
speeds. 

In  order  that  the  existing  tracks  could  be  made  suitable  for  higher  speeds 
(125  mph)  considerable  re-canting,  re-lining  and  more  difficult  re-transisioning 
has  had  to  be  carried  out.  There  were  many  problems;  in  a  few  instances 
re-lining  meant  virtually  re-routing,  and  in  others  the  full  requirement  was  virtually 
impracticable  and  some  speed  restrictions  l>elow  125  mph  will  remain.  The 
increased  speeds  have  necessitated  the  removal  of  all  unmanned  le\el  crossings 
in  the  majority  of  cases. 

Thus  the  problems  of  vertical  forces  and  lateral  forces  were  contained,  but 
whilst  the  track  tolerances  at  installation  laid  down  for  today's  main-line  speeds 
are  acceptable  for  125  mph,  the  minimum  maintenance  tolerances  need  tightening 
up.  High-speed  trains  are  much  more  susceptible  to  track  irregularities,  and  there- 
fore the  rate  of  deterioration  of  line  and  level  must  be  halted  earlier  than  with 
present  line  speeds.  This  has  meant  laying  down  a  more  frequent  cycle  of  main- 
tenance attention. 


508 


Bulletin  658 — American  Railway  Engineering  Association 


Tolerances  for  High-Speed  Lines 
100  mph  (160  km/h)  Lines  125  mph  (200  km/h)  Lines 

Installation  Mtce  Installation  Mtce 


( mm ) 

in.       mm 

in.     ( mm ) 

in.       mm 

in. 

Gauge 

(-1) 

1/16  (-1) 

1/16  (-1) 

1/16  (-1) 

1/16 

(+4) 

3/16  (-f?) 

5/16  (-f3) 

1/8  (+6) 

1/4 

Cant 

(±2) 

1/8  (±6) 

1/4  (±2) 

1/8  (±5) 

3/16 

Twist 

(over  3  metres) 

I  in  600 

1  in  400 

1  in  750 

1  in  500 

Alignment 

over 

20  metres 

over- 

(±4) 

3/16  (±5) 

4/16  (±3) 

1/8  (±4) 

3/16 

lapping  chords 

Gauge 

:   (1432  mm)  4  ft  8-3/8  in. 

It  is  true  these  tolerances  are  tight  and  difficult  to  obtain,  but  before  they 
were  fixed  a  detailed  survey  was  made  of  the  actual  gauge  and  cant  on  many 
curves   and  it  was   found: 


Gauge 

100  mph  lines:   Worst  wide  (+4mm)   3/16  in. 
Worst  tight  (— 6nun)    1/4  in. 
90  mph  lines:   Worst  wide   (-|-8mm)   3/8  in. 
Worst  tight  (0.)   0  in. 


Cant 

1 8mm  over  10  metres 
r5/16  in.  over  10  ft 

1 9mm  over  3  metres 
j  3/8  in.  over  10  ft 


Whilst  by  far  the  majority  of  readings  fell  within  the  specified  tolerances. 

The  best  results  came  from  the  F27/F23  type  concrete  sleepers. 
The  minimum  radii  for  vertical  curves  are: 


(.Olg) 


100  mph 
125  mph 
250  mph 


Recommended 

Radius 
12.6  miles 
19.5  miles 
78.2  miles 


(.03g)    Minimum  permissible 

Radius 

4.2  miles 

6.5  miles 

26.1  miles 


Ballast 

It  is  most  important  that  tracks  for  high-speed  lines  have  adequate  depth  of 
good  ballast.  The  rate  of  deterioration  of  line  and  level  depends  to  a  large  extent 
on  the  quality  of  ballasting.  BR's  new  specification  states  that  the  ballast  shall  be 
good  natural  hard  stone,  angular  in  shape  with  all  dimensions  nearly  equal,  and 
meet  the  following  requirements: 

1.  Wet  Attrition  Value.  Not  exceeding  6%  for  main-  and  high-speed  lines   (8% 


is  permitted  for  secondaiy  lines  where 
Crushing  Value.  Not  to  exceed  30%. 
Impact  Value.  Not  to  exceed  25%. 
Flakiness  Index.  Not  to  exceed  50%. 


1%  is  not  readily  obtainable). 


5.  Elongation  Index.  Not  to  exceed  50%. 


Address  by  Harold  H.  Jenkins  509 

Ballast  Size — Square  Mesh   Sieve. 
50  mm  (2m.)   all  to  pass. 
28  mm  (1-1/8  in.)   Not  less  than  80%  retained. 
14  mm  (  9/16  in.)   None  to  pass. 

The  80%  to  be  general  graduation  in  sizes  between  50  mm  and  28  mm  (2  in. 
to   1-1/8  in.). 

E.\perience  with  available  stone  on  BR  indicates  that  the  wet  attrition  value 
is  critical,  and  that  nearly  all  stone  with  low  attrition  values  usually  satisfied  the 
other  limits,  and  if  not  is  seen  easily.  Basalts  and  granites  usually  have  wet  attri- 
tion values  of  2%  to  5%,  although  a  few  exceed  6%  and  are  not  used.  Limestones, 
which  are  abundantly  a\ailable,  usuall>-  ha\e  wet  attrition  values  exceeding  8%, 
and  only  a  few  sources  are  satisfactory. 

It  is  found  tliat  stones  with  high  wet  attrition  values  form  fine  particles  which 
combine  with  rain  water  to  form  a  slurry  which  finds  its  way  under  the  sleepers 
to  start  "pumping"  of  the  sleeper.  This  creates  voids  under  the  sleeper  and  if  not 
attended  to,  the  '"pumping"  spreads  to  adjacent  sleepers  and  line  and  level  deterio- 
rate rapidly.  Briefly,  the  wet  attrition  value  is  obtained  by  taking  a  .30-lb  sample, 
washing  and  drying  (100°-110°  C),  cooHng  and  weighing,  and  then  placing 
in  a  cylinder  to  which  is  added  equal  weight  of  water.  The  cylinder  is  rotated 
10,000  times  at  30-.33  revolutions  per  minute.  The  amount  retained  on  a  BSh  07 
sieve,  approximately  1/10  in.  mesh,  is  washed  and  dried  and  the  loss  of  weight 
as  a  percentage  of  the  original  is  the  wet  attrition  \alue. 

Many  of  you  will  have  seen  BR's  proposed  16  track  categories  (published  in 
1971).  Experience  and  more  reliable  information  of  actual  tonnages  passing  and 
actual  maintenance  work  necessary  ha\e  necessitated  a  change  in  the  tonnage 
bands.  Attention  was  drawn  to  this  by  the  wide  variation  of  work-load  in  Cate- 
gory (1)  track  0  to  6  million,  as  compared  with  Category  (2)  6  to  12  million. 
The  new  categories  which  are  proposed  for  introduction  this  year  are  as  follows: 

Tormage          Annual  Tonnage        ( Millions  Old  Annual  Tonnages  ( Millions 

Short  Tons )  Short  Tons ) 

(23^)  0-6  million 

(2!4-5M)                       6-12  million  (   6?i-13J4) 

(5M-13M)                     12-18  milhon  ( 13/'^20JO 

(over  13J^)                     18  and  over  (over  20«) 

The  speed  bands  remain  unaltered: 

A  100  mph  to  125  mph 

B  75  mph  to     99  mph 

C  50  mph  to     74  mph 

D  Below  50  mph 

It  transpires  that  at  present  there  are  no  New  Category  A  lines  carrying  less 
than  5/2  million  short  tons  so  the  categories  concerned  with  high-speed  services 
are  Categories  A3  and  A4  only. 

The     recommended     maintenance    cycles     for     these     two     liigh-speed    category 
lines  are: 

1.  Patrolling — .3  times  a  week   (safety  union  requirement). 

2.  Track  geometry  recording  car  runs — .3  times  a  year. 


and 

per  Year 

1 

0-  2  million 

2 

2-  5  million 

3 

5-12  million 

4 

12  and  over 

510  Bulletin  658 — American  Railway  Engineering  Association 

3.  Rail  flaw  detection  car  runs — twice  a  year  (plain  line). 

4.  Manual  ultrasonic  testing — 3   times   a  year   (switches  and  frogs). 

5.  Tamping/lining  machines — Every  9  months  (category  A4)  Every  12 
months  (category  A3).  Intermediate  manual  packing  of  adjustment 
switches  and  insulated  joints,  etc. 

6.  Kango,  or  machine  or  manual  packing — 3  times  a  year  (switches  and 
frogs). 

The  fixed  manning  on  site  (excluding  machine  workers)  per  mile  of  track: 

Cat.  A4         Cat.  A3 
man  man 

1.  Allow  for  attention  to  fastenings,  chps, 

pads,  insulators,  etc.,  etc   0.012  0.008 

2.  Allow  for  attention  to  adjustment  switches    0.006  0.004 

3.  Allow  for  attention  to  ballast   0.090  0.063 

4.  Miscellaneous    0.003  0.002 


0.111  0.077 


5.  Patrolling    ( per   mile   of   inspection )     0.079  0.075 

6.  Off-track    work,    grass-cutting,    weeds,    fences,    drains, 

etc 0.110 

(per  geographical  mile)    (per  mile  if  2-track  railway)   0.055  0.055 


0.134  0.130 


The  Tamping/Lining  Service 

Tamping  machines  have  developed  rapidly.  BR  issues  its  own  specification 
(about  100  pages)  for  each  machine.  It  may  be  of  interest  to  follow  some  of  the 
reasons  for  these  changes. 

If  you  assume  you  require  a  track  maintenance  machine  to  run  on  BR: 

1.  It  must  satisfy  the  signal  engineers  minimum  requirements  for  safety 
of  track  circuit  working  which  means  it  must  have  not  less  than  3  axles 
each  with  9  short  ton  minimum  loading. 

2.  It  must  satisfy  Movement  Departments  "punctuality"  requirement  which 
means  it  must  be  able  to  run  into/and  out  of  Section  at  not  less  than 
55  mph. 

3.  It  must  satisfy  chief  mechanical  engineers  anti-derailment  requirement 
of  a  specified  ride  index  (lateral  and  vertical  forces). 

These  tliree  conditions  can  only  be  met  with  a  vehicle  with  bogies,  and 
weighing  at  least  27  tons  (short). 

Agreements  with  Unions  stipulate: 

4.  Operator  must  have  direct  visibility  immediately  in  front  of  vehicle 
when  travelling  and  working.  This  means  either  a  tall  central  control 
position  (impossible  with  BR's  low  headroom)  or  a  cab  at  each  end 
fully  fitted  with  all  rvmning  and  operating  controls. 

5.  Cabs  must  be  waterproof,  soundproof  and  air-conditioned.  The  noise 
levels  have  to  be  reduced  to  meet  "Health  and  Safety  at  Work,"  a 
recent  Parliamentary  Act. 


Address  by  Harold  H.  Jenkins  511 

6.  Because  it  may  work  under  overhead  electric  wires,  there  is  danger  for 
a  man  standing  on  the  vehicle  floor,  and  raising  a  hammer/spanner 
within  arcing  distance  of  the  live  wires,  so  that  the  vehicle  must  be 
fully  covered  by  a  roof. 

7.  These  conditions  are  essential  for  all  machines  required  to  move  on  or 
adjacent  to  any  lines  open  to  traffic.  The  "Union"  requirements  are 
enforceable  for  all  such  equipment,  but  the  "ride  index"  and  track 
circuiting  requirements  (which  together  eliminate  the  possibilities  of 
2-axle  machines)  do  not  apply  to  lines  completely  under  engineer's 
occupation,  if  they  can  be  conveyed  to  the  site  on  a  wagon  or  by  road. 

These  basic  requirements  are  fully  satisfied  by  die  latest  types  of  track 
maintenance  machines. 

Recent  investigations  have  proved  that  the  accuracy  of  the  finished  level 
and  finished  line  increases  as  the  measuring  base  increases,  and  investigations 
continue  into  the  use  of  low-powered  laser  beams  as  a  means  of  extending  the 
measuring  bases,  without  creating  any  safety  hazard  for  men  working  on  or  near 
the  tracks. 

Obviously  in  a  complete  on-track  mechanization  system  adequate  occupa- 
tions of  the  line  are  essential.  On  some  of  the  high-speed  routes  "reversible"  (or 
two-way)  signalling  is  being  introduced.  On  others,  "gaps"  are  being  provided 
in  the  time  tables;  in  some  cases  these  will  still  only  be  available  during  the 
nights  or  Sundays.  A  computerized  program  is  already  in  use  for  optimization  of 
line  occupations,  maintenance  and  renewal  items  and  available  resources.  Other 
noteworthy  introductions   are: 

1.  Rail  Flaw  Detection  Service  (Photograph  5) 

BR,  in  conjvmction  with  Wells  Krautkramer  developed  a  2-car  ultrasonic 
rail  inspecting  unit,  which  came  into  service  in  1971.  This  2-car  set  has  basically  one 
"instrument"  car  and  one  "staff  amenity"  car — including  sleeping  accommodation 
for  the  crew.  The  standard  type  ultrasonic  probes  are  used,  sliding  on  the  rail 
surface. 

Probes  at  1,  30°  and  70°  to  the  vertical  enable  defects  to  be  located  through 
the  whole  of  the  head  and  web  of  the  rail  and  in  particular  at  and  under  bolt 
holes.  The  ultrasonic  information  is  transformed  and  recorded  on  35-mm  film 
which  at  the  end  of  a  run  (usually  representing  100  miles  of  track  per  night)  is 
dispatched  for  processing  and  returned  to  an  evaluation  center  where  it  is  manually 
inspected  and  interpreted.  The  evaluation  is  time-consuming,  tedious  and  exact- 
ing. In  conjunction  with  the  Atomic  Energy  Authority  at  Harwell  an  Automatic 
Scanning  Device  coupled  with  computerized  evaluation  has  now  been  installed 
at  the  evaluating  center.  It  has  completed  its  trials  and  as  expected  produces 
results  even  more  accurate  than  the  most  expert  of  evaluators,  and  of  course  in  a 
small  fraction  of  the  time. 

The  next  development  already  being  studied  and  found  to  be  feasible  is  the 
elimination  of  the  filming  process,  and  to  transform  the  ultrasonic  information 
suitable  for  immediate  scanning  and  evaluation  either  by  a  computerized  system 
on  the  train  itself,  or  by  recording  direct  to  a  "floppy  disc"  which  is  then  scanned 
and  evaluated  at  the  existing  evaluation  center. 

When  the  divisional  engineer  receives  the  rejiort  of  a  run,  he  arranges  for  a 
manual  ultrasonic  inspection  of  each  fault  reported,  and  ensures  the  necessary 
action  is  taken  and  reports  back  accordingly  to  tlie  center. 


512 


Bulletin  658 — American  Railway  Engineering  Association 


Jm 


CHIEF  CIVIL  ENGlNEEft 
BRITISH  RAIU\A#VYS  BOARD 


ULTRASONIC  tlEST 


mmmmm^^ms- 


photograph  5 — Ultrasonic  rail  flaw  detection  car. 


2.  Track  Geometry  Recording  Car 

The  difficulty  of  obtaining  a  passage  on  the  main  lines  for  slow-moving  record- 
ing cars  has  become  more  and  more  difficult  as  speeds  and  densities  of  traffic 
increase.  BR  decided  to  construct  its  own  car  capable  of  rurming  as  part  of  the 
high-speed  trains  or  with  its  own  locomotive  at  125  mph,  or  as  part  of  any  other 
train  including  existing  90  mph  and  100  mph  services. 

The  basic  parameters  are: 

1.  Vertical  profile  (left  and  right). 

2.  Horizontal  profile   (alignment). 

3.  Cross  level. 

4.  Curvature. 

5.  Gauge. 

6.  Vertical  slope. 

7.  Ride  index. 

and  the  following  derivations: 

8.  Vertical  slope. 

9.  Horizontal  slope. 

10.  Equilibrium  speed. 

11.  Dynamic  cross  level. 

12.  Twist  (2  different  wheel  bases). 

The  measuring  systems  had  to  be  all  non-oontact  ones  to  enable  accuracy 
of  recordings  at  125  mph.  This  has  been  achieved  by  the  use  of  inertial  sensors, 
accelerometers,    transducers,   gyroscopes    and   optical   scanners.    The   data  produced 


Address  by  Harold  H.  Jenkins  513 

are  then  electronically  processed  to  produce  print-outs  as  required.  The  major 
faults  are  marked  on  the  track  by  automatically  fired  "paint  bullets."  It  is 
intended  to  obtain  a  true  record  of  every-  section  of  BR  track  from  which  future 
maintenance  standards  will   be  set  for  each  parameter. 

Information  of  the  traffic  carried  over  each  section  will  be  fed  into  the  com- 
puter and  after  successive  runs  the  rate  of  actual  deterioration  will  be  calculated 
for  each  of  the  important  parameters,  and  this  will  enable  the  next  periods  of  main- 
tenance attention  to  be  forecast,  reasonably  accurately.  Linking  this  information 
with  possible  line  occupations,  available  machines  and  odier  resources  will  enable 
the  maintenance  requirements  to  be  scheduled  at  least  12  months  ahead  using  the 
computerized  program  already  mentioned.  The  greatest  task  is  feeding  in  accurate 
track  component  details,  t>pc,  age,  condition,  etc.,  for  the  whole  system,  but 
this  work  is  in  hand. 

There  ha\e  been  many  other  developments  but  due  to  the  need  to  limit  the 
length  of  this  paper  they  can  only  be  mentioned  briefly,  e.g.: 

(a)  Track  Circuits 

Glued  insulated  joints  are  in  regular  use  on  electrified  lines.  These  are  of  2 
types,  1.  The  Edilon  glued  joint  (polyester  resin),  and  2.  The  "BR"  type  (epoxy 
resin)    with   "Huck  type"  fastenings. 

These  joints  are  tested  to  115  tons  longitudinal  force  before  acceptance.  After 
4  years,  failures  recorded  are  less  than  2  per  1000  joints. 

On  non-electrified  lines  joindess  track  circuits  (Aster  ty-pe)  are  being  installed 
as  rapidly  as  possible.  Recent  dexelopnients  indicate  that  possibilities  now  exist  for 
a   reasonably   priced   jointless   track   circuit   suitable  for  electrified  lines. 

(b)  Welding 

Flashbutt  welding  is  carried  out  at  six  depots  spread  throughout  BR;  each  depot 
has  only  one  main  welding  machine.  SLxty-foot  lengdis  are  welded  into  lengths  up  to 
1320  ft.  Developments  have  taken  place  in  the  straightening  and  finishing  of  the 
welds.  The  equipment  used  is  supplied  by  "A.I."  Welders  Ltd.,  of  Inverness,  Scot- 
land. Failures  of  flashbutt  welds  in  tlie  track  are  rare. 

Considerable  eftort  has  been  made  to  improve  the  thennite  welds.  The  main 
problems  were  lack  of  straightness,  cupping  at  the  weld,  and  lack  of  fusion.  Every 
failed  weld  is  sent  to  the  laboratory  for  detailed  investigation.  The  results  have 
shown  that  in  e\'ery  case  quality  of  workmanship  has  been  the  cause.  This  is  under- 
standable as  the  work  has  to  be  carried  out  in  all  weatliers  and  usually  during 
darkness  and  under  pressure  to  restore  the  lines  to  traffic.  Development  has  been, 
in  conjunction  with  the  Elecktro-Thermit  Co.,  to  produce  a  method  less  susceptible 
to  workmanship  and  this  has  been  achieved  by  using  a  system  where  the  pre-heating 
time  is  far  less  critical. 

(c)  Manual  Packing 

It  is  important  to  ensure  that  local  pumping  of  tiie  sleepers  is  prevented, 
especially  on  high  speed  or  heavily  used  lines.  Instances  occur  at  the  introduction 
of  a  replacement  rail,  a  replacement  insulated  joint  or  weld  that  the  track  bed  is 
disturbed  at  that  point,  perhaps  only  one  or  two  sleepers,  but  left  unconsolidated. 
This  creates  bad  spots  which  if  left  imtreated  develop  rapidly  and  extend.  It  is 
generally  impracticable  to  bring  in  the  large  tamping  machines,  and  BR  use  portable 
equipment — Kango   Generators   and   Kango   Electric   Hammers.    Some   of   these  are 


514  Bulletin  658 — American  Railway  Engineering  Association 

2-man  sets,  others  4-man  sets.  The  hammers  are  equipped  with  specially  designed 
ballast  tools.  Their  use  enables  the  troublesome  spots  to  be  dealt  with  quickly  and 
the  track  kept  to  the  high  standard  and  left  until  the  next  on-track  machine  sched- 
uled tamping.  The  Kango  equipment  is  used  even  more  frequently  for  tamping 
regularly  switches  and  frogs.  BR  has  in  regular  use  over  1000  sets  of  Kango 
Equipment. 

(d)  Rail  Drilling  and  Rail  Sawing 

The  problems  associated  with  drilling  holes  in  rails  without  creating  starting 
points  for  a  crack  have  been  largely  overcome  by  re-thinking  the  process  of  drilling. 
As  a  result  the  best  combination  of  speed,  pressure  and  angle  of  cutting  edge  of  the 
drill  has  been  found.  These  are  incorporated  in  all  new  rail  drilling  equipment  and 
BR  has  now  standardized  on  the  "Stumec"  equipment  for  rail  drilling  and  sawing. 
Since  their  introduction  the  number  of  bolt  hole  failures  has  fallen  steadily. 

(e)  Destressing  and  Restressing 

BR  adopted  several  years  ago  tlie  policy  of  stretching  a  rail  to  its  required 
calculated  "stress  free"  length.  The  equipment  used  has  to  be  capable  of  pulling 
with  a  force  of  100  tons  (22,400  lb).  Two  makes  of  machine  are  in  use:  the  "Green- 
side"  equipment  and  the  "Permaquip"  machine;  both  give  equally  satisfactory 
results. 

(f)  On-Track  Maintenance  Machines 

BR's  detailed  specifications  already  mentioned  are  regarded  by  manufacturers 
as  the  strictest  and  most  demanding  of  all  administrations — ^but  these  specifications 
have  been  compiled  on  actual  service  experience,  actual  safety  requirements  and 
the  need  for  maximum  utilization  and  minimum  interruption  to  work  on  restricted 
availability  of  line  occupations. 

BR's  present  on  track  maintenance  equipment  is  shown  in  Fig.  2.  (Photographs 
6  and  7  are  examples) 

(g)  On-Track  Relatjing  Machines 
Two  types  are  in  regular  use: 

1.  The  Twin  Jib  Crane — this  can  only  be  used  where  two  lines  run  along- 
side each  other,  as  the  equipment  runs  on  one  road  and  relays  the  other. 
As  most  of  BR  is  double  (or  quadruple)  track  this  is  a  very  useful  piece 
of  equipment  and  can  be  used  for  "panel"  laying  (60-ft  rails  wdth  sleepers 
attached)  or  direct  sleeper  laying  (up  to  60  concrete  sleepers  correctly 
spaced  at  each  lift).  (Photograph  8)  The  continuous  welded  rail  is  placed 
in  both  methods,  after  the  panels  of  sleepers  have  been  placed.  BR  has 
47  such  machines,  some  self-propelled,  others  requiring  a  locomotive. 
(Photograph  8)  Rate  of  working  averages  10  each  60-ft  sections  out  and 
10  new  60-ft  stretches  in  per  hour.  In  good  circumstances  13  sections 
in  and  out  are  obtained. 

2.  Gantry  Type  Equipment — The  difficulties  of  obtaining  possession  of  two 
tracks  simultaneously  led  to  the  development  of  single-line  gantries  of 
the  Portal  type.  The  new  long  welded  rails  are  laid  out  alongside  the  outer 
ends  of  the  sleepers  of  the  track  to  be  relayed.  The  Gantries  running  on 
the  long  welded  rails  (gauge  10  ft  6  in.)  lift  out  the  old  track  in  panels 
and  bring  in  the  new  sleepers — either  on  their  own  or  with  second-hand 
60-ft  rails.  The  rate  of  working  is  on  average  10  sections  in  and  out  per 


Address  by  Harold  H.  Jenkins 


515 


ON  TRACK  MACHINES 

1976 

TAMPERS 

PLASSER 

05E 

13 

•• 

06 

50 

JOINT 

1 

TAMPER-LINERS 

PLASSER 

SLC 

20 

07-16 

38 

TAMPER-LINER-CONSOLIDATORS 

PLASSER 

CTH 

22 

P   &  C  TAMPERS 

PLASSER 

07-275 

6 

•• 

07-16-275 

3 

LINING  MACHINES 

PLASSER 

AL   203 

35 

AL  250 

13 

BALLAST   CONSOLIDATORS 

ROBEL 

5 

PLASSER 

VDH   800 

24 

HATISA 

D8 

16 

BALLAST   REGULATORS 

PLASSER 

US  P.  3/4000 

lO 

•• 

..        5000 

12 

HATISA 

R  7 

lO 

BALLAST   CLEANERS 

PLASSER 

RH  62 

20 

HATISA 

(OLD  TYPES) 

23 

•• 

C  311 

2 

TRACK  RECORDERS 

HATISA 

PV6 

12 

RELAYING   MACHINES 

BRITISH 

TWIN  JIB 

47 

SECHAFER 

ISIMCLE  irXE) 

(H(,H8.H9) 

16 

(ON  order; 

6EISHAR 

SINGLE  LINE 

3 

Fig.  2 


516 


Bulletin  658 — American  Railway  Engineering  Association 


Photograph  6 — Plasser  ballast  cleaner. 


Photograph   7 — Long-chord   leveling,   lining   and   tamping  machine. 


Address  by  Harold  H.  Jenkins 


517 


Photograph  8 — BR's  twin  jib  self-propelled  track  layer. 


Bui.   058 


518 


Bulletin  658 — American  Railway  Engineering  Association 


Photograph  9 — Secmafer  gantry  track  layer  with  sleeper  beam. 


hour  but  frequently  rates  of  13  sections  in  and  out  are  achieved  for  lengths 
of  50  chains   (3300  ft)  in  one  Sunday  occupation. 

BR  has  12  Secmafer  M6  and  M8  Gantries  capable  of  taking  up  and 
laying  panels  only,  and  3  sets  of  M9  Gantries  with  an  automatic  pick-up 
sleeper  beam.  Those  machines  with  the  beam  can  carry  up  to  60  concrete 
sleepers,  (2  rail  lengths  of  sleepers  correctly  spaced  and  "interleaved"). 
The  machines  remove  4  lengths  of  old,  then  the  ballast  machine  moves 
in  and  scarifies  the  old  sleeper  beds  and  reprofiles  the  ballast  ready  for 
the  new  sleepers.  The  beam  tlaen  places  its  alternative  sleepers  and  moves 
ahead  to  place  the  remainder  so  that  two  complete  rail  lengths  of  sleepers 
are  laid.  (Photograph  9) 

BR  takes  dehvery  this  month  of  three  sets  of  Geismar  "Pluto  Mark 
lU"  gantries.  These  are  built  to  BR's  specification  and  can  be  used  either 
for  panel  laying  or  with  the  automatic  beam  sleepers  only.  The  specified 
rate  of  working  is  not  less  than  13  such  60-ft  sections  per  hour.  (Photo- 
graph 10) 

Rail  Changing  Machine 

In  the  early  1980's  BR  can  expect  to  be  required  to  re-rail  about  200  miles  of 
CWR  a  year  increasing  in  the  late  1980's  to  500  miles.  Experiments  are  being  carried 
out  to   find  the  best  equipment.   One  machine  now  on  trial  is  a  Plasser  machine 


Address  by  Harold  H.  Jenkins 


519 


Photograph   10 — Geismar  gantry  track  layer  with  sleeper  beam. 


(Photograph  11)  which  is  expected  to  work  at  walking  pace,  i.e.,  3  to  4  miles  of 
changing  both  rails. 

The  changes  in  BR's  track  structure  including  the  improved  alignments,  transi- 
tion curves  and  canting  as  described,  together  with  the  maintenance  procedures 
outlined  explain  BR's  abiUty  to  introduce  125  mph  services  this  year.  Full  evaluation 
of  the  effects  of  high-speed  tiains  on  the  wear  and  safety  of  the  track  has  been 
made  and  it  can  be  seen  that  these  high  speeds  can  be  obtained  at  only  marginally 
increased  costs  of  track  maintenance. 

The  first  of  the  conventional  type  high-speed  trains  (HST)  from  the  batch  pro- 
duction was  delivered  this  montli  and  is  shown  in  Photograph  4. 

Further  work  is  still  in  hand  concerning  the  effects  of  lateral  forces  by  the  APT 
tilting  train  running  with  cant  deficiencies  up  to  12  in.  The  work  is  not  complete 
but  tests  indicate  that  with  deficiencies  exceeding  8  in.  that  small  lateral  movement 
of  the  track  (1/25  in.)  can  be  expected  after  passage  of  each  high-speed  train  on 
track  with  unconsohdated  ballast  (i.e.,  after  tamping,  or  ballast  cleaning,  relaying 
etc.).  Indications  are  that  stability  is  not  restored  until  some  200,000  tons  of  traffic 
have  passed.   (The  APT  train  is  shown  in  Photograph  12) 

Load  measuring  wheels  are  used  to  measure  lateral  forces,  and  it  seems  that 
recent  measurements  indicate  a  correlation  between  the  flange  forces  and  the  forces 
at  the  axle-box.  The  measurement  of  track  resistance  is  even  more  difficult,  and 
special  on-track  vehicles  are  being  constructed  to  measure  the  forces  required  to 
shift  the  track  laterally.  It  is  hoped  these  experiments  will  be  completed  within 
the  next  12  months.  The  lateral  forces  comprise  (a  -f  b)  forces  where  (a)  = 
Quasi-Static  Forces  arising  from — 

1.  Cant  deficiency. 

2.  The  asymmetry  between  leading  and  traihng  wheelsets  of  bogies. 

3.  Aligrmient  of  wheelsets  in  bogie  frame. 


520  Bulletin  658 — American  Railway  Engineering  Association 


Photograph  11 — Plasser  rail  changing  machine. 


Photograph    12 — BR's    Advanced    Passenger   Train    (APT). 


Address  by  W.  Friesen  521 


and   (b)  =  Dynamic  Forces. 

4.  From  body  and  primary  sprung  masses  due  to  track  irregularities. 

5.  From  repose  to  the  unsprung  masses  due  to  track  irregularities. 

With  tests  at  6°,  7°,  8°,  9°,  10°  and  12°,  measurements  of  peak  lateral  forces 
exceeding  10  tons  (22,400  lb)  at  slight  track  irregularities  have  already  been 
measured.  Nevertheless  present  indications  are  that  deficencies  up  to  9°  will  prove 
to  be  acceptable  on  concrete-sleepered  track.  It  is  unlikely  that  such  deficiencies 
will  be  permissible   on  wooden-sleepered   track. 

The  tests  so  far  on  lateral  resistance  of  track  indicate  that  over  90%  of  the 
resistance  is  pro\  ided  by  the  friction  between  the  base  of  the  .sleeper  and  tlie  ballast. 
Heavy  concrete  sleepers   therefore  ha\e  a  distinct  advantage. 


Hot  Box  Detector  Data  Analyzer  System 

77-658-3 

By  W.   FRIESEN 

Senior   Design    Engineer— Signals 
Canadian   National    Railways 

Synopsis 

Irrfrai-ed  detectors  are  now  being  used  to  scan  train  wheel  bearings  for  abnormal 
lieat.  In  these  hot  box  detector  (H.B.D.)  systems  the  most  unpredictable  factor 
in  the  production  of  consistent,  reliable  results  has  been  the  method  of  interpreting 
the  data.  At  present,  the  detector  readings  are  recorded  on  paper  tape  and  the 
resulting  ti-ain  heat  profile  is  manually  analyzed.  Unfortunately,  however,  this  method 
of  analysis  is  only  accurate  if  the  tape  reader  is  intimately  familiar  witii  all  the  pulse 
patterns  that  the  H.B.D.  system  may  generate.  An  effort  to  provide  consistent  accu- 
rate analysis  of  the  H.B.D.  data  is  resulting  in  the  de\elopment  of  a  computerized 
analysis  system.   Fig.    1   is   a  map  of  the  Canadian  National's  H.B.D.  installations. 

Fig.  2  shows  both  the  physical  plant  layout  and  tlie  data  processing  system 
block  diagram  for  a  typical  hot  box  detector  field  installation.  In  this  configuration, 
detectors  1  and  4  are  used  to  initialize  the  system  and  to  establish  tlie  direction  of 
train  mo\ement;  east  or  west,  respectively.  The  infrared  sensor  itself  produces  a 
voltage  related  to  the  intensity  of  the  heat  radiation  incident  widiin  its  solid  angle 
of  sight.  Nomially  oH^,  this  sensor  is  gated  on  with  wheel  detector  2  or  3,  depending 
upon  the  established  direction  of  train  travel,  to  ensure  the  generation  of  heat  infor- 
mation only  when  the  bearing  itself  is  over  the  scanner. 

A  train  coming  to  the  H.B.D.  location  from  wheel  detector  1  estabhshes  direc- 
tion of  travel  when  detector  2  is  activated.  At  that  point  the  infrared  sensor  is  gated 
on  and,  with  the  wheel  now  over  its  line  of  sight,  scans  the  overhead  wheel  bearing. 
The  moment  the  wheel  arrives  at  wheel  detector  3,  the  sensor  is  turned  off  to  avoid 
scanning  the  rest  of  the  train.  This  sequence  of  operation  of  wheel  detectors  2  and 
3  is  repeated  for  every  wheel  on  a  train.  The  gating  of  senor  1  is  only  effective  for 
the  first  wheel  at  the  beginning  of  the  train  as  direction  needs  to  be  established  only 
once.  Activation  of  any  wheel  sensor  keeps  the  "Train  Present"  signal  on. 


Xote:   Discussion  open  until  October  15,  1976. 


522  Bulletin  658 — American  Railway  Engineering  Association 

After  each  heat  pulse  is  generated,  it  is  sent  to  the  pulse  processor  where  it  is 
peak  detected,  then  amplified  and  buffered  to  drive  the  carrier  transmitter.  The 
carrier  transmitter  relays  the  peak  value  to  a  central  receiving  office. 

A  typical  H.B.D.  Scanner  is  shown  in  Fig.  3. 

The  overall  block  diagram  of  the  typical  data  handling  system  for  a  H.B.D. 
location  is  shown  in  Fig.  4.  Each  field  location  has  two  infrared  detectors,  one  for 
each  side  of  the  train,  and  information  coming  from  each  is  separately  transmitted 
and  received.  Whenever  a  train  enters  a  detector  location,  the  output  of  the  data 
control  unit  activates  a  relay  which  is  used  to  key  "ON"  the  two  carrier  transmitters 
for  that  location.  At  the  central  office,  where  all  H.B.D.  outputs  are  read,  the  heat 
data  from  each  side  of  the  tiain  is  received  on  separate  channels  and  each  channel 
is  fed  to  one  pen  of  a  two-pen  recorder.  Each  of  the  two  receivers  per  location 
also  has  a  carrier  presence  indication  to  provide  location  status.  Train  presence 
over  the  H.B.D.  site  is  generated  by  AND'ing  the  two  carrier  presence  outputs 
while,  between  trains,  the  two  carrier  channels  are  alternately  gated  on  for  the 
verification  of  each.  The  pen  recorder,  normally  off,  is  started  with  tlie  appearance 
of  the  train  presence  indication.  An  audible  and  visual  alarm  device  is  used  to  alert 
the  tape  reader  of  predefined  heat  alarm  levels. 

Fig.  5  shows  a  typical  output  and  the  interaction  between  train  present  and 
the  recorder  data  output.  Note  tlie  first  car  shows  characteristically  high  pulses. 
This  is  because  it  is  a  roller-bearing  car  and  appears  to  be  hot,  but  in  actual  fact 
only  more  of  the  generated  heat  is  visible. 

In  Fig.  6  we  can  see  that  on  a  car  equipped  with  roller  bearings  there  is  no 
journal  oil  box  to  impede  the  line  of  sight  of  the  infrared  sensor.  This  causes  the 
higher  characteristic  pulse  seen  on  Fig.  5. 

Reasons  for  Automated  Analysis 

Considering  the  type  of  system  described  it  can  be  seen  that  there  are  several 
factors   which   influence  the  ability  of  the  system  to  detect  hot  boxes.   They  are: 

1.  Interpretation  of  the  data  on  the  paper  recordings  depends  on  people 
and   thus   is  not  consistent. 

2.  Emotional  state  of  mind  of  the  tape  reader  greatly  influences  the  system 
performance. 

3.  Eriiployee  mobility  makes  it  difficult  to  maintain  a  good  data  evaluation 
standard. 

4.  It  is  a  full  stereo  system  and  as  such  each  rail  could  have  a  different 
system  gain  factor,  thus  generating  false  alarms  on  the  fixed  alarm  system. 

5.  Noise  generated  by  electrical  storms  sets  off  alarms  and  tends  to  make 
tape  readers  disgusted  with  the  system,  thereby  reducing  their  ability  to 
effectively  read  the  tapes. 

Fig.  7  shows  how  electrical  interference  can  generate  many  false  outputs  in  an 
unfiltered  system   and  how   (channel  2)   filtering  can  greatly  reduce  this  problem. 

Benefits  from  Automated  Data  Evaluation 

Fig.  8  lists  the  benefits  of  an  automated  evaluation  system  to  the  user  of  hot 
box  detector  data  (Transportation  Department). 

Fig.  9  hsts  the  benefits  of  an  automated  evaluation  system  to  the  hot  box 
detector  maintainers  and  technicians.  Better  maintenance  is  made  possible  by  closer 
system  observation  using  statistical  evaluation  made  possible  by  the  computerized 
system. 


Address  by  W.  Friesen  523 


Configuration  of  automated  systems  can  be  as  different  as  the  people  designing 
them.  Shown  in  Fig.  10  is  one  possibiHty  and  the  uses  for  the  various  in/output 
devices. 

The  CN  Data  Analysis  System 

On  the  block  diagram  shown  in  Fig.  11  it  can  be  seen  that  the  main  element 
is  Computer  Automation  LSI2/20,  mini  computer  with  32K  core  and  a  4.2M  word 
DISC.  This  provides  the  ability  (intelligence)  to  control  the  various  interfaces  and 
I/O  devices  as  well  as  evaluate  the  data  and  detect  hot  boxes. 

As  can  be  seen  on  Fig.  12  the  hardware  (with  complete  spares)  is  mounted  in 
three  19-in.  racks.  The  I/O  devices,  shown  beside  the  computers,  may  be  mounted 
any  reasonable  distance  away.  This  allows  operators/dispatchers  to  have  a  cathode 
ray  tube   (C.R.T. )    on  their  desks. 

In  Fig.  13  we  can  see  the  full  complement  of  output  devices  used.  One  printer, 
C.R.T.  and  analogue  recorder  are  actually  located  in  the  tape  readers/dispatchers 
office.  The  tape  reader  may  recall  any  train  (presently  programmed  for  close  to  24 
hours  storage)  for  re-evaluation,  viewing  of  the  digitized  data  or  output  on  the 
analogue  recorder.  Additionally  an  analogue  recording  is  automatically  produced  if 
the  computer  is  not  able  to  evaluate  the  train.  Control  of  the  system  is  achieved 
with  the  maintainers  C.R.T.,  where  such  things  as:  I/O  device  assignment,  data 
evaluation  parameters,  noise  filtering  parameters,  etc.,  may  be  changed.  The  main- 
tainers devices  also  act  as  back  up  units  (spares)  in  tlie  event  of  a  failure.  In  addi- 
tion to  the  previously  mentioned  recordings  tlie  maintainers'  recorder  is  automatically 
switched  to  the  carrier  output  of  any  location  not  sending  in  good  data,  thus 
providing  a  direct  analogue  recording  of  the  signals  so  that  all  symptoms  can  be 
seen.  If  this  were  not  done  only  the  filtered/ digitized  data  would  be  available  from 
the  computer  memory. 

Training  of  personnel  is  greatly  simplified  by  the  use  of  a  "HELP"  command. 
This  results  in  an  output  listing  of  all  the  system  commands  and  shows  the  function 
of  each  one.  The  commands  listed  in  Fig.  14  are  only  those  available  on  that  par- 
ticular C.R.T.   and  are  ob\'iously  different  for  the  maintainer  and  the  tape  reader. 

The  alarm  panel  shown  in  Fig.  15  is  used  by  the  tape  readers  to  call  attention 
to  the  fact  that  an  abnormality  has  occurred.  The  alarm  must  then  be  acknowledged 
on  the  C.R.T.  before  it  is  turned  off.  The  computer  fails  and  self  check  alarms  are 
activated  whenever  there  is  a  failure  of  the  system  hardware  or  software.  The  quality 
of  this  check  system  is  quite  high  but  only  experience  will  indicate  if  it  is  adequate. 

A  listing  of  all  the  trains  past  a  particular  location  can  be  obtained  by  keying 
in  the  appropriate  command  on  the  C.R.T.  Shown  in  Fig.  16  is  the  list  of  messages 
from  one  location  ( Newtonsville  North  "NVN").  The  one  line  messages  show  all 
the  important  data  associated  with  the  train. 

An  example  of  the  command  format  used  in  the  system  to  request  stored  data 
can  be  seen  in  Fig.  17.  All  data  requests  are  based  on  train  sequence  number  and 
location. 

The  list  of  numbers  on  Fig.  18  shows  in  hexadecimal  code  what  data  is  in 
memory  for  the  train.  All  data  including  pulses  is  stored  so  that  re-evaluation  with 
different  parameters  is  made  possible.  (An  explanation  of  the  hst  is  given.) 

An  overview  of  the  system  can  be  seen  in  the  block  diagram.  Fig.  11.  The  data 
enters  the  computer  through  CN  designed  interfacing.  Peak  detection  of  the  heat 


524  Bulletin  658 — American  Railway  Engineering  Association 

infoiTiiation  is  accomplished  external  to  the  computer  because  I/O  speeds  are  not 
fast  enough  to  collect  accurate  values  from  the  24  locations  in  the  system. 

An  item  of  particular  importance  is  the  self  checking  system.  This  system 
outputs  information  from  the  computer  which  is  routed  back  to  the  input  for  verifi- 
cation. If  any  channel  or  other  part  of  the  system  becomes  defective  an  alarm 
message  is  generated  and  the  tape  reader  is  alerted  via  the  alarm  panel. 

System  Outputs 

The  outputs  shown  in  Figs.  19  through  23  are  from  the  engineering  model 
which  was  tested  in  1974.  These  examples  were  selected  because  they  exemplify  the 
main  points  of  interest  very  well  and  show  the  reasons  for  certain  design  parameters. 

Fig.  19  shows  a  typical  output  for  a  train  with  no  problem.  The  top  portion 
shows  the  normal  paper  recording  and  the  bottom  shows  the  computer  print-out. 
An  important  thing  to  note  here  is  that  on  tlie  average  one  side  of  the  output 
(Rail  1)  is  1.2  mm  higher  than  the  other.  The  effect  of  this  difference  is  minimized 
by  the  use  of  ratios  relating  only  to  one  side  of  the  car.  This  can  be  seen  in  tlie 
fact  that  the  maximum  train  side  ratios  (NMTSR  and  SMSTR)  are  almost  the  same 
even  tliough  the  actual  values  are  considerably  different. 

Figs.  20,  21  and  22  show  how  the  use  of  ratios  normalizes  tlie  data  in  spite 
of  some  rather  large  differences  in  absolute  pulse  values.  These  differences  in  value 
are  due  to  different  system  gain  settings  in  the  scanners.  In  spite  of  variations  be- 
tween 8.3  mm  and  11.3  mm  on  the  analogue  recording  the  car  side  ratios  (CSR) 
varied  by  only  0.02  (1.96  to  1.98).  This  consistency  in  evaluation  is  made  possible 
in  spite  of  absolute  values. 

Fig.  23  is  an  actual  hot  box  graph  and  computer  printout.  The  order  of  magni- 
tude of  ratios  (bodi  car  side  ratio  (CSR)  and  train  side  ratio  TSR)  can  be  seen 
when  a  single  wheel  is  hot.  If  two  wheels  were  hot  the  T.S.R.  would  be  much  tlie 
same  but  C.S.R.  woud  be  smaller.   (Maybe  even  in  a  non-alarm  zone). 

The  train  graph,  Fig.  24,  shows  a  string  of  pulses  at  the  end  of  the  train,  which 
are  actually  pedestal  pulses  generated  at  the  hot  box  detector  field  location.  Use  of 
this  information  allows  data  to  be  normalized  so  tliat  heat  evaluation  is  done  only 
on  heat  information,  not  on  heat  plus  pedestal  as  is  being  done  in  the  manual  sys- 
tems. If  noniialized  data  is  not  used  the  weighting  factor  of  high  pedestals  will 
result  in  small  ratios  and  thus,  potentially,  a  hot  box  may  be  missed. 

Digital  Transmission  System 

Analogue  carrier  systems,  which  are  being  used  to  transfer  infonnation  from 
the  field  sites  to  the  central  office,  are  subject  to  many  types  of  noise  interference. 
This  noise  may  be  generated  by  lighting,  line  cross  talk,  carrier  drop  out,  etc.,  and 
usually  results  in  either  spurious  data  or  a  loss  of  data,  thus  making  it  very  difficult 
to  correctly  recognize  and  evaluate  the  heat  information. 

A  digitizer/transmitter  has  been  developed  by  the  Canadian  National  Technical 
Research  Department  for  use  at  tlie  hot  box  detector  field  sites.  The  "digital  trans- 
mission system"  peak  detects  the  information  from  the  bolometer  and  converts  it 
into  an  8  bit  digital  "Word".  These  words,  together  with  wheel  spacing  information, 
are  stored  in  a  2,024  word  (8  bits  each)  memory  for  later  transmission.  When  the 
train  present  signal  goes  away  the  entire  message  is  transmitted  to  the  oflBce  using 
a  standard  FSK  carrier  system.  To  eliminate  the  problem  of  noise  destroying  the 
message  it  has  both  parity  and  block  checks  as  well  as  being  transmitted  five  times. 


Address  by  W.  Friesen  525 


Self  enhancement  of  the  five  transmission  results  in  a  very  secure  system  which 
can  reproduce  a  good  message  even  tliough  portions  of  tlie  individual  transmissions 
are  destroyed. 

Because  the  above-mentioned  system  is  in  the  final  development  stages  its  actual 
performance  record  cannot  be  discussed,  but  it  is  fairly  obvious  that  a  much  better 
quality  of  data  will  be  made  available  to  the  tape  re<tders  or  the  computerized 
analysis  system.  Along  with  this  improvement  there  should  be  considerable  savings 
in  maintenance  since  no  calibration  or  adjustments  of  the  carrier  is  required  (aside 
from  line  level  settings).  This  calibration  (and  linearity  check)  procedure  should 
be  done  about  twice  a  year  in  order  to  guarantee  good  performance  on  the  analogue 
carrier. 

Fig.  25  (not  reproduced  herein)  is  the  field  digitizer  unit  showing  the  front 
panel  (test  and  display)  and  the  shielded  electronics  cage.  The  unit  is  5)2-in.  high 
and  fits  onto  a  19-in.  communications  rack. 

In  Figs.  26  and  27  the  cover  of  the  electronics  shield  has  been  removed  to  ex- 
pose the  hardware  which  accomplishes  peak  detection,  D/A  conversion,  memory  and 
control  logic.  As  can  be  seen  in  these  pictures  it  is  not  a  monumental  task  to  build 
a  system  which  will  greatly  enliance  the  performance  of  the  data  transmission  system 
and  as  technology  advances  the  digitizing  system  will  become  even  simpler. 

General 

Some  fringe  benefits  of  the  automated  analysis  system  are  such  things  as: 

•  train  speed  checks 

•  trains  aren't  lost  due  to  out-of-ink  or  out-of-paper  situations 

•  lightning  generally  will  not  set  off  the  alarms  and  thus  the  tape  reader  is 
not  annoyed 

•  statistical  evaluation  of  data  base  allows  trends  and  anomalies  to  be  recog- 
nized and  handled 

•  better  overall  system  calibration  and  consistency  of  data  input  made  possi- 
ble by  a  common  standard   (data  analyzer) 

•  no    paper   tape   is    required   for   system    operation   and   therefore   recorder 
maintenance  is  minimized. 

Figs.  28  to  34  show  various  views  of  the  hardware  used  to  implement  the 
analyzer  system  in  an  office  with  up  to  32  hot  box  detector  systems  reporting.  These 
pictures  show  tlie  system  installed  on  the  Canadian  National  at  Belleville,  Ontario, 
and  operates  24  hot  box  detector  locations.  Although  an  engineering  model  of  the 
system  working  with  4  hot  box  detectors  was  installed  at  Belleville  in  1974,  tlie 
present  24-location  system  has  just  been  installed  in  February  of  tliis  year. 

Thank  you  for  your  attention.  I  hope  that  this  brief  description  of  our  effort 
to  improve  the  hot  box  detection  system  has  been  informative  and  interesting. 


526  Bulletin  658 — American  Railway  Engineering  Association 


Fig.  1 


Address  by  W.  Friesen 


527 


). 

'^                                                                          ^ 

"?- 

LABRAOOS                                ,      '       >* 

I       1 

' — 1 

1 

^\>'V 

1^ 

\ 

O         \ 

(S^ 

IX^ 

Si 

1                            (JUEBEC 

fM\^ 

ly 

1  /             -jLL  >^     ."   r,   -     '  ^^  gB^-i^ 

^^^'0- 

*<»f4. 

/ 

i^^F^^^^^^^w 

^Z' 

s>^ 

,/•> 

KM.'^i  ^  ^j^ooGAN  ^y^*^ 

w-A. 

'.^ 

JSj^f 

\            1^           4 

^^"""^     y  (/  f 

'    \      *  ■* 

.  "aSSiKKjetg^    1          '"  fsM 

^«r      *     .'^                /^         V.     / 

•'^»"'^V 

"■V  ' '  c^         ^3                ^^■'^ 

*  -  .^\ 

W »~X. 

</*^f^^  arv^^^jy^^^' 

^" 

'^                                                                              ATL 

ANtir   orEAN 

G 

^^'■y 

> 

i     \ 
\    5          ) 

^-,^ 

1 

DATt 

REVISIONS 

P 

^ 

CANADIAN  NATIONAL  RAILWAYS 

SUll 

;9i-a 

l^jy;HEN>Bffnt/*S:-0^-5) 

O-HOI  BOX   DET.    '7707 
0-.     1-       „         -       'M09 

X  =IN  SERVICE 

X  =9EA0  OUT    POINTS 

(rl-7^ 

UPOAICD  lOENO  Of    197a 

I' 

.NAL     EN>,,NEEBlNG ■"SFT-rT; 1 

6   1-76 

UPOaTEO  TOEWDOP    1975. 

f- 

MONTREAL 

8     .iNUAR».S7< 

CM 

HOT    BOX    CtTECTOl    LOCATIONS 
ENTIRE    SYSTEM 

S-DG-5 

528 


Bulletin  658 — American  Railway  Engineering  Association 


WHEtL    SEASINS 


n-  •*■  — S      r—  —  —  -I       f—  —  — — 1 


l^i^c     I— leoLOMrrts'— lAMFUFiEBt- 
I   '^'^^    II  II  I 

L..^ -i      I- -I       (__ I 


1 I 


PEAK    DfTECTcO    HEAT    ?V. 


CASRIER    KEY 


Fig.  2 — Field  equipment. 


Address  by  W.  Friesen 


529 


Fig.  3 


HUD     OAIA    PROCESSING    SVSIEH    PEH    LOCAKON 


Fig.  4 


530 


Bulletin  658 — American  Railway  Engineering  Association 


TYPICAL  KBO.  RECOROER    OUTPUT 

1 — I — I — I  —I — I — I — 1 — I — I — I — < — I — I — I — I — I — H— I — I — I — I — 1 — I — y 


-■iL— rf' 


IHl^Ei^ 


^Pi 


ICHANNEL*!  [ 


::i:s7|^;Hn^Sfe5M^ltp 


iiii,m4niiu»ii-iwiiuuyiaun 


■.m,^Mi^MiX!>miBs^"^lM3l 


-i 1— I 1 1 1 1       I       I       I       I       I       I       I       I       I      H 1- 

HmcoHoma  cmaktii 


-Ili^iyihlHi-IIMnJlrfMHHIl^MPK^ ,     \-^ 


S-MmSEC/ 


EXPMttEO  TIME  SCALE 
OP  A  SINGLE  PULSE 


1   Q-PIRST   HEAT  PULSE  ARRIVES 

fpTRAIN   PRESENCE 
^    INOICATION    BESINS 


LAST  HEAT  PULSE  ARRIVES  T\ 


(~S  TRAIN    PRESENCE 
\J     INOICATION    ENDS 


Fig.  5 — ^H.B.D.  receiver  outputs,  heat  data  and  train  presence. 


Address  by  W.  Friesen 


531 


Fig.  6 


Fig.  7 — Train  presence  detection  on: 

1.  Servo  (manual  system), 

2.  H.B.D.  analyzer. 


532  Bulletin  658 — American  Railway  Engineering  Association 


POTEMTIAL  BENEFITS  g  COlVg^lfMCCS 

<USER) 

1)  C0N5ISTAWT  Df  PENDABLE  RWL  TIME  EVALUATION). 

2)  RELIABLE  DATA  EVALUATION. 

•  MO'OUT  OF  INJC'PROBLEM. 

•WO 'system  shut  down*  because  of  woise. 

•FALSE  ALARMS    DOE  TO  WOISE    REDUCED 
•CROSS  TALIC    ON    OATA    EFFECTIVELY    HAWDLED. 

3)  IMPROVED  DATA  EVALUATION  PERFORMANCE. 

•HIGHER  MO.  OF  TRAINS  STOPPED  ARE  FOUKD   HOT. 

4)  DATA  STORED  FOR  LATER  REFEREWCE  IF  WEEDED. 
5)REDUCT|0M  IN  AMOUNT  OF  PAPER  TAPE  USE:D. 

•PRESENT   COST    APPROXIMATIVELV   $5000-»  PER  YEAI^. 

6)  TRAIN   SPEED  ONI  OUTPUT. 

•  PRESET    MAXIMUM   ALARM. 

7)  STATISTICAL  [VALUATIOW  OF  ALARMS.  DATA.  TRAINS,5P£ED,ECT. 

8)  A  COMPUTER  GENERATfD  SEMI  MONTHLY  HBO  PERFORMANCE  K[PORI 

•  HBD-I    FORMS 

9)  HANDS  OFF  DATA  ANALYSIS. 

Fig.  8 


Address  by  W.  Friesen  533 


POTENTIAL  BENEFITS  g  CQMVEMENCfS 

(MAINTENANCE) 

1)  REAL  TIME  SYSTEM  ALARM. 

•POWER  FAILURE^LINE  BREAK, TRAIN  BUT  NO  DATA,®TC.., 
•COMPUTER    FAILURE 

2)5CANMER    PERFORMAMCE    MOWITOR, 

•AVERAGE    PULSE    AMPLITUDE 
•SCAWMER  GAIN    VARIATION 

3)  SITE  TO  SITE  CALIBRATION  DIFF,  CAW  BE 
ELIMINATED  DUE  TO  REFINED  STATISTICS. 

4)  RECORD  OF  ALL  NOISY  OR  ABNORMAL  OUTPUTS 
STORED   FOR  REFERENCE, 

5)  COMPONENT  FAILURE  STATISTICS  t  RECORDS. 

•  Eg:    teNSES,  PUISE  PROCESSOR, ere... 

Fig.  9 


534 


Bulletin  658 — American  Railway  Engineering  Association 


POS!iei£  (VISUALIZED)  J^  DEVICES 


Mt^JtOM 


(cr.  k 


•POSSIBLf  TO  HAVf  MORE  THAN  ONF* 

•  USED  FOR  IMMEDIATE  OUTPUT  OF  ALARMS 
STATISTICAL  DATA  .ere... 

•  USED  FOR  REQUESTING  A  TRAIN 'RfCALI, 

•  POSSIBLE  TO  HAVE  MORE  THAN  ONE. 

•  USED  FOR  HARP  COPY  RECORD  OF  AIL  TRAINS. 

•  WIU  PRINT  OPPERATORS  RESP0W5f  TO  AURMSi 

•  PRIMTS  RECORD  OF  ALL  RECALL  AaiVITY 

•R«tRTAPE(«,M«.  OUTPUT  OF  TRAIN. 

•  PRODUCED  IF  REQUESTED  8Y  DISPATCHER 

•  REPRODUaiON  or  TRAIN  IN  ORIGINAL 
PULSE  PATTERN. 

Fig.  10 


Address  by  W.  Friesen 


535 


536 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  12 


Fig.  13 


Address  by  W.  Friesen 


537 


mmmmmm 


ivHticinMi  n  lonmE 
tis-ffiDnr  Sims  if  ml  uk^kukb 


isMranfRL  iMn  lUiPisr 

WiHJSf  mm  iBipt_ 
hmkum  mvt  II  iQVKi 
wm-mmmmmwmm 


WMmm  1MIH  w  tPOMiii  lis^^ 


Fig.  14 


538  Bulletin  658 — American  Railway  Engineering  Association 


TaOALARM  PANEL  ^ 


Fig.  15 


Address  by  W.  Friesen 


539 


T  i('iE=wtiyiiif- 

FlCKIJuWLEL'iJEC' 


TRrrtXM      ME-HlOERS 


80HVN 
SIHVN 

S3NVN 
84NVH 


ui2r- 

8231- 

is-es- 

eS34- 


•45.  2 
■45.  i) 
■45.^ 
■131.  U 
■bd.  » 

■ee.  4 


is-es-rs 

04-64- r6 
05-04- (6 
©5-04- To 
03-04- i-"o 
05-04- ?6 
05-04- Tb 


Cl=lRS=e01 

CRh:S=0S3 
CHftS=082 
tMRS=0;-'4 
ChRS=065 
Ch(RS=OO0 


SFEaD=^08'i' 
SPEfcC'-ei4 
SPEED=04e 
SPEED=043 
-S^tED=w46 
SFEEb=04^ 
Sf-EED=108 


HO  wLHkHS 

NO  mLhRMS 
NO  HLHRI'IS 

■NU  HLMRMS  - 

NO    HLHRI'IS 
lURBo-NO    EVhLUHUoW 


iSONVt'i 0^X6-24.  2 e5-04- 


CrtRS=000 
ChRS=003 
CrtRS=Owr 
C8RS=002 
CHRb=000 
CriRiJ-OutJ 


iftt.U-V3'*S NO    hLnKI'IS 


3?NVt4 
83NV^4 
14NVr^ 
15NVri 
leiNVN 


io4 
1222 
140? 
091  r 

0333 

lusr 


■56.  3 
•54.  1 

■09.  9 
-22.  1 
■£1.  6 


05-04-?© 
05-04- To 
05-04- rb 
OS-04-r© 
Or-04-rb 
Of    04    TO 


SPEEL'=10i' 

SPEE[,'=05i/ 

SFt£E'=«56- 

SPEEL'=03S' 

SPEEL'=105 

OI'ECD- 100 


I URBO-Nu    EVftLUa I  1  UN 
NO    HLHRI'IS 

HO  hlhri-*s- 

NO    HU-tRMS 

lURBO-NO    EVHLUHlIUN 

lURDQ    NO    CVTILUI 1 1  Iur< 


17NVN      1143-35.  6 


O.- 


-04-ro 


ChRS=002 


JPEED=05S         NO    HLHRI'IS 


S^JHVN  2122-24.8-05-04- 
94NVN  2145-05.  3  05-04- 
rONVN       1503-42.  0       04-04- 


72NVI< 
73NVN 
~4HVH 
rSNVN 

i_A. 


1000  43.  r 
1731-33.  4 
1343-47.  0 

2e05'-±i.- 1 

2134-55.  7 
TIMF 


04    04    r  i-J 
04-04- rii 
04-04-76 
04-04—76- 
04-04-76 

"datT 


eHRS=e-ii 

CfiR5=0e3 
CHK5=0*i'7 

LliR'3-'Cil3 

ChR5=044 

CHRS=034 

CHRS=weO- 

ChRS=011 


SPEEi'=t>e'4- 

SPEED='0S7 

SPEEL'=O40 


NO-HLHRHS 
NO  HLHRI'IS 
NO    HLHRI'IS 


SFE£D--0y2 
SPEED=045 
SPEEC'=051 
SPEED=±±0 
SPEED=QS4 


HO    IlLHKI'tS 

NO    HLHRI'IS 
HLHRI'IS 
-  lORBO-NO-  EVflLUMi  I  UN 
NO    HLHRI'IS 


SEQ.    LOC. 
No.     NAME 


Fig.  16 


EVL 

LOCHI 10H=HVH 

SEGlUENLE    »=75 
HCKNOl'iLEDuED    HI    0005 


731-JVN      2134-5.= 


Cl=lRS=ail         SPEED=034         NO   HLHRI'IS 


Loom  luU-l'iVI'J 
SEQUENi.E    #=7S 
HCIsNOWLEDoEb 


H I     yoOb 


Fig.  17 


540 


Bulletin  658 — American  Railway  Engineering  Association 


TRFHIM       OF»~rf=l       ROl_l_OW: 


ao4B 

4>544 
4444 
■  l.>44 


^•8^4 
IbHfc 
4444 
4444 
.i.l44 


HEUl 

its*;- 
y444 
4444 


4444 
4444 
4444 
4444 


4444 
4444 
4444 
4444 
4444 


4444 
4444 
4444 
4444 
4444 


6064 — ywu4 — yuUw 


F3y5 
3406 
IBCii- 
06OB 
2o2'3 
S4;;*: 


ICHB 
H4tiy 

25oi 

eyert 


y-ii-E 
44ye 


iiigiiiM — wywLi 


2C2i=l 
2E2c: 
2R2.rt 
2ri2S 
2620 


yywH 


yySi 
yy  TD 
yySi. 
yOHC 
yySl 


i«;i*^ia UUfcJH ma.ao 


:i=:22' 
i:y2D 

ia23 


yyyn 
yyOi" 
yij^o. 
oewH 

0005 


yOi.± 
yy^i 
Qi5Z- 
yyJi.J. 
yy2F 


ii£24 

2E2S 
2E2d 


yyyH 
yyyR 

yytiiH 


yy-+b 
ylul 

.  idki4  r. 

yiai'8 
Qy'+o 


!I22i3 


OyyS 
yyyy 

yeicHS 
Qgjyrt 
yijiji' 


y6J45 
yyyd 

.  Ijkj4«i 
oiEF 
ye45 


2C23 
2h24 


iti2E 


yyyH 

kjyOH 

uijyM 
ytSyH 
yetJB 


Qy4D 
yi£H 
yy45 
6y98 
yytis 


ie2E 

ZfiZQ 
2H23 
242C 
3m2S 


yytiB 
yyyrt 
yt-jyH 
oeyrt 
e©i3H 


yQ-^5 

tjy4-f; 
ylBL 
itiy46 


222b 
i       1628 

322H 


yyyn 
(iiyySi 

ijyeB 

QyyH 

ytit'B 


i-j£i46 
ylEH 
804  7  _ 

0y46 


4M4C 


yyyB 
yC'tii" 

tujly 


0846 
1E2L 
yy.  y 


Fig.  18 


Address  by  W.  Friesen 


541 


TAPE    ANALYSIS   REPORT 


TAPE(S)    FROM:  J^  BSlltU-J-J. -  Jg ^JJJ.  J'<^   ^ ^ 


OBSERVATIONS. 


\JedcLL     f^r     -Hie    tral,-^.     The     >vi<<~r    y^Ctfi(rS 

^y-fe        •erj      Si't^A.  lay      TKoucgk- 


48MVS 


KIN6ST0N   SUB 


2125   22-03-74 


TEST* 
PCS  FROM  FRT  INC  ENG       CSR       TSR       STATUS      12345' 


SI 


GNED  _^^-^^^ic:r:r_  tit l e  ji£.  jL£y_  g><^  _  0 AT E  J^3//y 


Fig.  19 


542 


Bulletin  658 — American  Railway  Engineering  Association 


TAPE    ANALYSIS   REPORT 


T APE  ( S )    FROM:  l^JUUSyJJrhi .^O^TJL  -  LoC^O 


OBSERVATIONS.: 


•*    UoiSi.    at      Fro a'T    i^Aar-fcJ. 


-  ri..r    p..h^    J^L^      --    rsgy    A/TSA^ 


=    3.51   X   ^.3  =•    f.Sr^t^ 


—     GRf^fiH      sV\auj:L         tOvvtyw 


— ^-    sag    foM.u.    u^^  g^'^^^  ^^.^ 

90MVS  KINGSTON   SUB 

PCS    FROM    FRT    INC    ENG  CSR 

Oil    NT      on      NT    on  1.97 


<z>f 

11^16 

08 -{03^  7  4 

TEST* 

TSR 

STATUS 

12345 

2.51 

HOT 

W*** 

NMTSR    -2.51  SMTSR   -1.43  NTSA   =033  STSA    =032 

015    CARS    INC    ENG         08  4   MPH 

END 

SI 


GNED  ^^^g^^.^^~--___  TITLE  ,jr^4^^£^£__    DATE^^^£. 

Fig.  20 


Address  by  W.  Friesen 


543 


TAPE    ANALYSIS   REPORT 


TAPE{S)    FROM:  ^^I^BSJ %AUJld- A^^.<i^ 


OBSERVATIONS. 


"     Si\c&     CSR  JT^R    Are    tU    Sa^i  a^'^9dA^i/S    fkt% 
Locaf'.OA    af>j>^arita    k^^i,    A.<ri.    q/^JA SgT/.ny. 


iper  i 


a2CDS  KING ST CN   SUB 

PCS    FBGM    FRT    INC    tNG  CSR 


X444      08-/0a>-74 


-§k'. 


iSK 


biPTCS 


lEsi  » 
12345 


u 1 1    NT      0 1 1       MT    U  1  I 


2.65 


H'JT 


SI 


hPITSR    =»2.65  SMTbK    =1.30  NJsA    =0^U  blSA    =U^3 

013    UAKb    INU    E>)G         ub5   "ifTi 

GNED  _ /^^^^^^^rr^z:-  ''''''' I- ^  i  1  -P-f  ■£  -^>l'^j.    0 ^^ E  /<J/J^jy_ 

Fig.  21 


544 


Bulletin  658 — American  Railway  Engineering  Association 


TAPE    ANALYSIS   REPORT 


TAPE  ( S )    FROM:  ^ £  2di^ _-5p.^TVL -^ c.j3_2_ 


OBSERVATIONS.: 


-  Hol'i-''       CS^t  /  Tse   arc    r^  Sny,^  a^   feef*/** 
■Hot  p  Ig^.  v^WkC   -Tse  X  A/rs;j 


09  CCS 


KINGSTON   SUB 


M39 


10-(65>7 


TEST* 
PCS    FROI    FHT    INC    ENG  CSR  TSR  ST/^TUS  12345 


008    NT      008      NT    008 


1.98 


nMTSR  a2.62     SMTSR  =tl./i0     NTSA  =043      STSA  =0^5 

Oil  CARS  INC  ENG    047  MPH 

END 


SIG 


NED  ^^^^£:'_ TITLE  ^J>^^_^^jy^_  _    DATE  2<}/.t//t.. 

Fig.  22 


Address  by  W.  Friesen 


545 


TAPE    ANALYSIS   REPORT 


TAPE(S)  F ROt^ :  JLe'M^^^^rjf ie.^Li'J-- 


OBSERVATIONS. 


-    D^t^icT^.a 

Uo1      v5oX 

i/,T./K(ii     o-P      C.s<^    aA<L''rs/i' 

■far         V«ri-i 

\a.rcL.e.    k£At  c>^lsc<L  . 

„  li 

\  5     <:r;;i    t^ss    rLz^     ^-T^iv^ 

'  Ts  a"    U,:^ 

t-fo..^      (/t-^-^    /fli'^e.-J"/  Tl-Jr£  I\aA 

ke«»A     fvoo    i^/o 

vjIUuM  KINGSTON    SUB 

PCs    rHQn    I-Ki    InC    LNG  ubrt 


01 

2a«5 

14-(J_3*7^ 

l£.blr 

K 

ijTP.iUS 

lyj^b 

SI 


G  N  ED  _^:^fe^r:z-=-_  _  _  TIT  L  E  _S-/  j)/i _^'l-_  _    D AT  E  (i/V/7J^_ 

Fig.  23 


546 


Bulletin  658 — American  Railway  Engineering  Association 


Address  by  W.  Friesen 


547 


Fig.  20 


548 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  27 


Address  by  W.  Friesen 


549 


Fig.  28 


Uul.   G58 


550 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  29 


Address  by  W.  Friesen 


551 


Fig.  30 


ST  PANEL 


MV^         MVN 


LfJ 


I  P  t 

TPi  A 

• 

9 

• 

e 

• 

# 

• 

e 

• 

• 

• 

O 

1' 

"• 

• 

• 

# 

« 

<» 

« 

» 

TEST  PANEL 


Fig.  31 


552 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  32 


Address  by  W.  Friesen 


553 


Fig.  33 


554 


Bulletin  658 — American  Railway  Engineering  Association 


I  I 


B.D. 


Data  Acquisit 


ANALYZER  T 


OMTRAIM  SII^ULATOR 

... —  WORTH    RAlt- 


%  -* 


%  QL^^^^feii  ^ 


m  •  %.  M 


^.^^i-..       .:.. 


Fig.  34 


"The  Quiet  One,"  Burlington  Northern's  Northtown 
Yard,  Minneapolis,  Minn. 

By  M.   B.   WALKER 

Assistant   Director— Signal    Engineering 
Burlington    Northern,    Inc. 

Burlington  Northern  is  justifiably  proud  of  the  results  of  efforts  to  quiet  the 
noise  of  retardation  of  cars  on  the  hump  at  Northtown  Yard.  Not  all  retarder 
screeching  is  gone  and  we  still  ha\e  the  low-frequency  rumbling  created  by  retarder 
action  on  the  cars,  but  what  screeching  now  exists  is  very  tolerable  and  occurs  only 
occasionally  with  the  heaviest  cars. 

This  situation  owes  a  debt  to  the  efforts  of  many  men  who  spent  hours  searching 
for  an  answer — to  the  signal  supply  companies.  General  Railway  Signal  Company 
(GRS),  and  Union  Switch  and  Signal  Division,  WABCO — and  to  a  number  of  rail- 
way companies   which  participated  heavily  in  the  research. 

I  wish  also  to  acknowledge  the  source  of  some  of  the  material  presented  here 
today: 

"Noise  Problem  Involving  Retarders,"  September  2.5,  1972,  by  \^  K.  South- 
worth,    Burlington    Northern,    Inc. 

"Retarder  Noise  Abatement,"  October  1,  1973,  by  D.  E.  Turner,  General 
Railway    Signal   Company. 

"Noise  Reduction  in  Classification  Yards,"  October  1,  1973,  by  R.  M.  Karovv, 
WABCO,   Union   Switch   and   Signal   Division. 

Before  we  look  at  what  was  actually  done  at  Burlington  Northern's  Northtown 
Yard  to  abate  the  retarder  noise,  let's  review  very  briefly  what  Nortlitown  Yard  is 
and  where  located.  This  yard — 3.2  miles  in  length — was  constructed  on  top  of  three 
existing  yards,  required  extensive  excavation,  relocation  of  city  utilities,  erection 
of  a  four-lane  overhead  bridge  to  eliminate  a  busy  grade  crossing  in  the  vicinity  of 
the  new  hump,  and  is  primarily  for  classification  of  eashvard  trains.  Our  Gavin 
Yard  in  Minot,  North  Dakota,  classifies  most  westward  trains.  We  expect  to  classify 
3000  cars  per  day  over  the  hump,  terminate  16  trains,  originate  19  trains,  and  handle 
10  through  trains  together  with  28  transfer  trains  within  the  Twin  Cities  area. 

The  yard  is  oriented  in  a  north-south  direction;  the  southern  portion  lies  in 
northeast  Minneapolis,  the  northern  portion  lies  in  Fridley,  and  immediately  to  the 
east  of  the  hump  and  bowl  tracks  is  the  community  of  Columbia  Heights.  You  see, 
then,  we  are  contending  with  noise  ordinances  from  three  separate  cities. 

A  brief  history  of  efl^orts  concerning  retarder  noise  abatement  is  in  order.  Any- 
one who  has  ever  been  in  the  close  proximity  of  a  retarder  in  action  knows  that 
the  emitted  sound  is  deafening  and  many  times  crosses  the  threshold  of  pain.  Because 
the  human  ear  is  most  sensitive  to  frequencies  in  the  range  500  to  5000  cycles  and 
because  a  retarder  in  action  creates  extremely  high  sound  lev  els  in  the  2000  to  4000 
cycle  range,  all  within  hearing  range  of  such  retarders  become  very  annoyed.  It  is 
the  abatement  of  sounds  in  the  2000  to  4000  cycle  range  that  concerns  us  today 
since  the  low  frequency,  grating,  rattling,  or  rumbling  noises  do  not  carry  far  and 
give  no  particular  trouble. 


Note:    Discussion  open   until   October   15,   1976. 

555 


556  Bulletin  658 — American  Railway  Engineering  Association 

Some  of  the  earliest  attempts  to  suppress  retarder  screeching  involved  changing 
brake  shoe  hardness,  composition  or  configuration.  Softer  shoes,  that  is  shoes  with 
a  hardness  of  Brinell  200  instead  of  Brinell  290,  were  installed;  however,  no  appre- 
ciable reduction  in  noise  was  obtained  and  shoe  wear  was  considerably  accelerated. 

Next,  ductile  iron  shoes  were  tested.  Ductile  iron  is  produced  by  a  casting 
process  and  contains  a  fair  amount  of  free  graphite  dispersed  throughout  the  metal 
and  has  a  hardness  approximately  equal  to  that  of  the  original  brake  shoes.  The 
incidence  of  screech  was  reduced  about  30  percent  over  the  standard  steel  shoe 
while  shoe  wear  was  four  to  five  time  that  of  standard  shoes. 

Another  innovation  was  tested  by  WABCO  engineers  who  machined  a  mitered 
slot  lengthwise  in  the  face  of  a  retarder  brake  shoe  into  which  was  pressed  Cobra 
brake  shoe  fibre.  This  shoe  lasted  for  86  cars  under  test,  at  which  time  the  force 
caused  by  the  wedging  action  of  the  wheel  destroyed  the  lower  edge  of  the  shoe. 

Abex  Corporation  fabricated  cast  shoes  to  fit  its  retarders  and  tests  indicated 
good  noise  abatement  properties  if  car  speeds  are  held  below  6  mph.  WABCO  tried 
Fabreka  pads  in  its  brake-shoe  mounting  to  provide  resiliency  but  couldn't  keep 
the  shoe  bolts  tight.  Inert  retarders  have  been  sprayed  with  various  coatings  but 
they  either  didn't  adhere  well  or  did  little  to  eUminate  noise.  Vertical  grooves  were 
cut  in  the  brake  rail,  /4-in.  wide  every  4  in.  along  the  rail  with  no  screech  elimina- 
tion. Diesel  oil  was  sprayed  on  inert  retarder  rails  as  cars  were  pulled  through  with 
reduction  in  screech,  but  the  continuous  oil  spray  was  objectionable  due  to  ground 
contamination  and  reduction  in  retardation. 

Brake  shoes  were  prepared  having  I-in.-diameter  holes  drilled  into  the  face 
of  the  shoe,  as  many  as  could  be  accommodated  by  the  shoe  face,  and  for  the  full 
length  of  the  shoe.  These  holes  were  then  plugged  with  lead.  This  did  reduce  the 
screech  some  but  also  reduced  the  retarding  effort. 

One  of  the  more  successful  attempts  to  eliminate  wheel  screech  was  made  in 
1965  by  Iron  Ore  Company  of  Canada  on  a  WABCO  inert  retarder.  The  face  of 
the  shoe  was  slotted  the  entire  length,  /s-in.  wide  and  1-in.  deep  and  packed  with 
a  lubricant.  The  last  report  stated  screeching  reduced  approximately  75%  with  no 
extensive  loss  of  shoe  life. 

Shoes  with  inserts  of  molydisulfide  and  with  inserts  of  graphite  were  tried  with 
Uttle  or  no  results.  It  is  to  be  noted  that  in  these  tests  involving  shoe  composition 
or  inserts  the  shoe  had  a  very  high  rate  of  wear,  eliminated  only  a  small  percentage 
of  screeching  and  when  a  car  did  screech  it  did  so  at  the  same  sound  pressure  levels 
as  before  tiie  test. 

WABCO  tried  interrupting  retarder  beam  and  shoe  arrangements  since  obser- 
vations seemed  to  suggest  a  correlation  between  the  shoe  length  and  time  taken 
to  induce  screeching.  At  one  yard  they  tapered  the  ends  of  the  shoes  with  a  cutting 
torch  all  through  the  retarder  while  at  other  yards  they  installed  entering  and  leav- 
ing beams  every  three  cylinders.  The  results  were  negligible. 

All  the  foregoing  is  a  sort  of  prehistory.  When  Burlington  Northern  began 
planning  Northtown  Yard  one  of  tlie  obstacles  that  had  to  be  overcome  was  restric- 
tive sound  pressure  ordinances,  that  is,  noise  ordinances.  For  example,  one  com- 
munity bordering  the  proposed  yard  passed  an  ordinance  liiniting  pressure  levels  in 
the  octave  band  1200  to  2400  cycles  to  33  db  and  in  the  octave  band  2400  to  4800 
cycles  to  20  db. 

Here  are  some  typical  decibel  values  encountered  in  daily  life: 


Address  by  M.  B.  Walker  557 


Rustling  leaves — 20  db  (Note  this  is  tlie  maximum  level  we  were  allowed  for 

the  2400-4800  cycle  octave  band.) 
Soft  whisper  at  5  ft — 34  db  (Note  tliis  is  the  maximum  level  we  were  allowed 

for  the   1200-2400  cycle  octave  band.) 
Normal  suburban  residential  area — 43  db. 
Typical  office — 70  db. 
Car  wheels  in  rctarder  at  15  ft — 100  to  134  db. 

It  is  interesting  to  note  that  the  community  which  set  tlie  low  noise  levels  of 
20  and  30  db  mentioned  above  is  very  likely  in  violation  of  its  own  ordinance.  Cer- 
tainly   Burlington    Northern    was   facing    a   potential    problem   with   retarder   noise. 

In  1970  Burlington  Northern  engaged  the  consulting  firm  of  Bolt,  Beranek  and 
Nev^Tnan  (BBN),  sound  specialists,  to  study  the  problem  of  retarder  noise  and 
invited  General  Railway  Signal  Company  and  WABCO  to  cooperate  in  a  joint  effort 
to  find  a  solution.  WABCO  decided  to  work  independently  with  its  own  consultant 
and  GRS  began  work  with  Burlington  Northern  and  BBN. 

As  a  result  of  studies  made  by  BBN  it  was  concluded  diat  tlie  car  wheel  was 
the  sound  generator  and  was  set  into  vibration  by  tlie  slip-stick  phenomena  between 
wheels  and  brake  shoes  called  spragging.  As  a  wheel  is  squeezed  in  the  retarder 
betsveen  the  brake  shoes  it  tends  to  be  gripped  and  then  to  slip  somewhat  like  a 
piece  of  chalk  chattering  on  a  black  board.  The  screech  is  the  audible  e\ddence  of 
the  wheel  vibration. 

The  race  was  on  to  find  a  way  to  abate  the  wheel  screech  of  retarders  so 
Northtown  Yard  could  use  its  humping  operation.  At  Pasco  Yard,  Burlington  North- 
ern, BBN  and  GRS  conducted  tests  on: 

1.  Vertical  sound  barriers. 

2.  Sand  damping  of  retarder  members. 

3.  Wheel  damping. 

4.  Water   saturation   of   retarder   shoes   and   car   wheels. 

5.  Lubricants  apphed  to  retarder  shoes  and  car  wheels. 

At  North  Kansas  City  Yaid,  Burlington  Northern  and  WABCO  conducted 
tests  on: 

1.  Soimd  barriers. 

2.  Lubricants  applied  to  retarder  shoes  and  car  wheels. 

3.  Pulsating  air  supply  to  retarders. 

Theoretical  calculations  on  sound  barriers  indicated  we  could  expect  a  20  to 
30  db  reduction  in  sound  pressure  levels  along  a  line  perpendicular  to  the  center  of 
the  barrier  wall.  The  Pasco  barrier  was  of  temporary  construction,  96  ft  long,  of 
^-in.  pl>'^vood  faced  with  6J2  in.  of  fiberglass  insulation.  The  main  wall  was  12  ft 
above  ground  level  and  approximately  9  ft  above  top  of  rail.  At  the  top,  a  2-ft 
hinged  section  of  wall  was  arranged  so  it  could  be  in  the  vertical  position  or  any 
desired  angle  toward  tlie  track  to  form  a  deflecting  baffle.  The  absorption  coefiicient 
of  the  fiberglass  wool  was  0.8,  a  relatively  good  factor.  Measurements  indicated 
the  barrier  provided  between  20  and  23  db  attenuation.  No  significant  difference  in 
attenuation  was  noted  with  the  adjustable  portion  positioned  at  45°  above  the 
horizontal. 


558  Bulletin  658 — American  Railway  Engineering  Association 

The  sound  barrier  at  BN's  North  Kansas  City  Yard  was  designed  by  WABCO 
and  is  of  a  more  pennanent  nature.  The  base  and  foundations  are  10x10  in.  timbers, 
the  framework  2x6  in.  fir  and  the  panels  are  corrugated  transite  to  which  an  acous- 
tical lining  was  glued.  All  wood  work  is  creosote  treated  and  the  panels  are  slanted 
about  30°  from  vertical  toward  the  retarders.  Sound  level  readings  taken  at  a  point 
100  ft  from  and  pci"pendicular  to  the  center  of  the  retarder  indicated  a  25  decibel 
reduction  in  noise  level. 

Sound  damping  of  tlie  retarder  shoe  beams  was  achieved  by  adapting  frames 
to  the  inside  and  outside  beams  to  hold  sand  bags.  The  arrangement  was  applied 
to  the  first  section  of  a  group  retarder;  however,  limited  clearance  above  the  beams 
restricted  the  amount  of  sand  that  could  be  applied.  Sand  bags  were  placed  in  the 
frames  and  loose  sand  packed  around  the  bags  and  over  tlie  top  of  the  beams  for 
a  total  weight  of  approximately  6000  lb.  The  beams  were  obser\'ed  to  be  canted 
outward  from  the  rail  due  to  the  outboard  weight  and  there  was  apprehension  that 
the  retarder  would  respond  too  slowly;  however,  functioning  was  correct.  Impact- 
excited  vibrations  were  significantly  reduced  but  diere  was  very  little  effect  on  wheel 
screech. 

Wheel  damping  tests  were  scheduled  involving  rubber-like  pads  cemented  to 
both  the  inside  and  outside  surfaces  of  car  wheels.  Due  to  the  difficulty  of  applying 
damping  pads  to  the  wheels,  to  the  inconclusive  results  and  to  the  improbability 
that  all  cars  could  be  so  treated,  these  tests  were  never  repeated.  An  alternate 
damping  test  was  carried  out  at  Pasco  Yard  by  fitting  six  sections  of  a  group  retarder 
witli  wooden  members  consisting  of  2x6  in.  planks  supported  on  steel  frames  bolted 
to  the  shoe  beams.  The  damping  bars  were  spring-loaded  to  provide  about  50  lbs 
pressure  against  the  side  of  die  wheels.  There  was  insufficient  clearance  between 
truck  sides  and  damper  frames  which  caused  enough  damage  to  prompt  abandon- 
ment of  this  test. 

A  water  test  was  conceived  because  it  has  been  recognized  that  retarder 
squeal  is  often  absent  under  certain  moist  conditions.  In  an  attempt,  and  again 
at  Pasco  Yard,  to  simulate  tliese  conditions,  we  applied  a  water  spray  to  a  group 
retarder,  completely  drenching  tlie  shoes  and  the  wheels  of  tlie  test  cars.  The  test 
result  was  negative. 

The  next  logical  test  seemed  to  be  lubrication  of  the  retarder  shoes.  Mathe- 
matical calculations  by  BBN  indicated  the  lubricant  must  have  a  stick-slip  ratio 
of  less  than  1.0.  The  first  lubricant  tried  had  a  ratio  of  0.78  and  was  initially  brushed 
on  the  faces  of  shoes  in  a  group  retarder.  Extra-heavy  cars  were  humped  into  this 
group  as  single  car  cuts  and  maximum  retardation  was  applied  in  an  attempt  to 
produce   screeching.    None  of   the  cars   emitted  screech. 

The  same  cars  were  retrieved  and  again  humped  into  tlie  previously  treated 
group,  with  no  screech  generated  in  either  the  master  or  group  retarder.  Enough 
residual  oil  remained  on  the  wheels  to  cause  loss  of  retardation  in  the  master 
retarder.  The  same  cars  were  again  retrieved  and  were  then  humped  into  a  diflFerent, 
untreated  group.  The  cars  were  again  difficult  to  control  in  the  master;  however, 
they  were  stopped  easily  in  the  untreated  group  retarder.  Again,  no  screech  was 
emitted   by   either   the  master  nor  untreated   group   retarder. 

Direct  lubrication  of  brake  shoes  eliminated  screeching  but  is  laborious  of 
application  and  difficult  to  control,  so  the  next  stop  was  to  carry  the  lubricant  in 
a  water  solution  which  is  the  way  Burlington  Northern  went  at  Northtov^m  Yard. 
A  test  was  conducted  at  Pasco  Yard  using  a  55-gal  drum  for  mixing  and  storage, 


Address  by  M.  B.  Walker  559 


and  a  small  motor-driven  irrigation  pump  was  used  to  deliver  tlie  solution  to  lengths 
of  perforated  garden  soaker  hoses  layed  along  the  retarder  shoe  beams. 

The  arrangement  produced  a  fine  spray  mist  which  enveloped  the  car  wheel  as 
it  passed  dirough  the  retarder.  The  dramatic  results  demonstrated  clearly  for  the 
first  time  that  screeching  could  be  eliminated  during  passage  of  a  car  Uirough  a 
retarder.  Continued  experimentation  with  a  variety  of  water-soluble  oils  produced 
a  combination  which  virtually  eliminated  the  screech  from  all  cars  with  loss  of 
retardation  estimated  at  approximately  10%. 

The  oil  used  is  Texaco  No.  1609,  soluble,  heavy-duty,  having  a  high  extreme 
pressure  property,  which  is  formulated  to  mix  readily  with  water  and  have  a  stable 
emulsion  widi  good  rust  protection  characteristics.  The  results  of  all  experiments 
indicated  that  a  2%  mixture  of  this  oil  with  water  either  eliminated  all  screeching  or, 
in  worst  cases,  drastically  reduced  the  sound  pressure  level  of  those  cars  that  did 
screech.  Since  Northtown  Yard  lies  adjacent  to  communities  with  very  restrictive 
noise  ordinances  it  was  necessary  to  use  a  retarder  noise  abatement  system  that  is 
100%  effective  so  the  decision  was  made  to  use  the  spray  concept  together  with  sound 
barriers. 

At  Northtown  tlie  emulsified  oil  and  water  mixture  is  delivered  to  the  retarder 
shoes  and  car  wheels  in  a  spray  fog  at  30  psi  at  the  nozzles.  A  /i-in.-diameter  mani- 
fold runs  the  entire  length  of  the  retarder  on  the  outside  of  each  side  with  the 
manifolds  controlled  in  two  sections.  The  entering  section  extends  for  two-thirds 
the  length  of  the  retarder  and  the  leaving  section  extends  through  tlie  bottom  1/3 
of  the  retarder.  The  spray  nozzles  are  set  into  the  manifolds  on  3  ft  8  in.  centers 
thus  creating  a  very  fine  spray  for  die  entire  length  of  retardation.  Each  of  these 
manifold  sections  is  individually  controlled  either  by  the  computer  when  in  humping 
mode  or  manually  by  push  button  on  the  control  console. 

Cars  are  sprayed  according  to  their  weight  so  that  every  extra  heavy  and  heavy 
car  is  sprayed,  with  medium  and  light  cars  having  approximately  every  third  or 
fourth  car  sprayed.  The  actual  sequence  of  spraying  is  calculated  by  the  computer 
on  the  basis  of  car  weights  and  the  mixture  of  cars. 

The  retarders  are  mounted  on  concrete  foundations  constructed  so  as  to  return 
the  residual  mixture  to  sumps  located  at  the  downhill  end  of  the  retarders  from 
whence  it  is  pumped  to  a  reclaiming  plant  housed  in  a  nearby  building.  The  collect- 
ing sumps  consist  of  a  section  of  concrete  pipe  4  ft  in  diameter  with  a  poured 
concrete  floor  into  which  is  placed  a  submersible  pump  controlled  by  a  high-low 
limit  switch.  A  cycle  tinier  is  provided  to  limit  frequency  of  operation  of  the  pump. 
This  allows  the  sump  to  be  pumped  dry  once  after  the  start  of  a  heavy  rainfall  after 
which  the  sump  is  allowed  to  overflow  the  relatively  clear  water  into  an  industrial 
sewer.  The  amount  of  oil  remaining  in  the  collection  system  under  these  conditions 
is  small  and  can  easily  be  handled  by  the  sewer  with  no  problem.  This  insures  at 
the  .same  time  diat  excess  water  does  not  get  into  the  noise  control  system  and  dilute 
the  mixture  l>eyond  a  useful  level. 

In  the  reclaiming  plant  the  incoming  mixture  is  settled  in  a  receiving  tank, 
right,  where  large  particulate  and  scum  are  removed.  After  this,  the  mixture  is  pumped 
through  in-line  filters,  which  remove  small  particulate,  to  a  2000-gal  mixing  tank, 
left,  where  metered  oil  and  water  is  added  to  reconstitute  as  required.  The  supply 
of  water  is  direct  from  commercial  lines  and  the  supply  of  oil  is  pumped  from  a 
15,000-gal  below-ground  storage  tank.  In  winter  ethylene  glycol  is  metered  into  the 
mixing  tank  in  proper  amounts  to  prevent  freezing  at  the  expected  low  temperatures 
for  the  next  24  hours.  This  antifreeze  is  stored  in  a  below-ground  30,000-gal  tank. 


560  Bulletin  658 — American  Railway  Engineering  Association 

After  agitation  into  a  homogeneous  solution  the  refreshened  mixture  is  pumped 
into  a  2000-gal  supply  tiink  from  whence  it  is  delivered  at  90  psi  back  to  the 
retarders  for  pressure  reduction  to  tlie  spray  manifolds. 

The  receiving  tank,  mixing  tank,  and  supply  tank  are  located  in  the  reclaim 
building  for  ease  of  operation  and  maintenance.  Sizing  of  tanks  was  calculated  to 
hold  a  24  hour  supply  of  material. 

Eight-foot-high  sound-absorbing  barriers  extending  6  ft  above  top  of  rail  and 
overhanging  both  ends  of  the  retarders  by  approximately  11  ft  were  installed  on 
both  sides  of  all  retarders.  These  barriers  are  supported  by  the  above-mentioned 
concrete  retarder  foundations  and  are  made  up  of  panels  4  ft  high  and  8  ft  long 
held  in  vertical  I-beam  members  so  that  sections  may  be  removed  to  gain  access  to 
the  retarder  for  maintenance.  Doors  are  provided  in  front  of  each  retarder  operating 
mechanism  for  the  same  reason.  A  wind  loading  of  30  lb  per  sq  ft  was  used  in  the 
design. 

The  efiFectiveness  of  the  noise  abatement  e£Fort  related  to  the  hump  retarders 
may  readily  be  judged  by  actual  observation.  With  the  spray  system  operating  with 
the  correct  mixture  of  oil  and  water,  car  after  car  passes  through  the  retarders 
without  a  screech.  Occasionally,  an  extra-heavy  car  will  just  start  to  screech  as  the 
car  reaches  exit  speed  and  will  have  the  screech  chopped  off  as  the  retarder  opens. 
With  the  sound  barriers  doing  their  part,  this  brief  and  occasional  screech  goes 
urmoticed. 

The  sound  barriers  at  Northtown  are  performing  at  a  sound  level  attenuation 
of  about  20  dbA  in  accordance  with  the  manufacturer's  published  performance 
capabilities.  One  must  keep  in  mind  that  these  measurements  are  taken  at  a  point 
50  ft  from  and  perpendicular  to  the  center  of  the  barrier  and  at  rail  height.  The 
figure  also  represents  the  maximum  capabilities,  and  as  one  moves  away  from  this 
center  line  position  of  the  barrier  towards  the  ends  of  the  barrier  or  travels  vertically 
in  relation  to  the  barrier,  the  attenuation  capabilities  decrease. 

Loss  of  oil  and  water  mixture  due  to  evaporation  and  carry  down  into  the  yard 
is  much  less  than  expected  and  what  is  tracked  down  into  the  bowl  acts,  together 
with  rail  surface  lubricators,  to  reduce  curve  resistance. 

Associated  with  the  noise  abatement  efforts  at  the  hump  was  the  consideration 
given  to  the  elimination  of  wheel  screech  associated  with  the  skate  retarders  located 
at  the  puUout  end  of  the  bowl  tracks.  Traditionally,  these  skate  retarders  have  been 
inert,  and  cars  were  simply  pulled  through  giving  rise  to  intolerable  sound  pressure 
levels.  Since  Burlington  Northern  was  faced  with  such  stringent  restrictions  con- 
cerning sound  levels  at  Northtown,  the  decision  was  made  to  provide  releasable 
skate  retarders.  Those  installed  at  NorthtowTi  are  GRS  Model  F-4  operable  weight 
responsive,  powered  by  Bellows-Valvair  hydraulic  units.  Each  hydraulic  unit  powers 
four  skate  retarders,  thus  there  are  16  such  units  involved. 

When  the  pullout  yardmaster  desires  to  pull  a  bowl  track  he  requests  the  hump 
yardmaster  to  release  the  associated  skate  retarder.  After  necessary  blocking  is  per- 
formed at  the  hump  end  of  the  track  to  prevent  humping  cars  into  tracks  with 
released  skate  retarders,  the  computer  sends  a  command  to  tlie  field  enabling  the 
release  circuit  at  the  skate  retarder  where  a  trainman  must  operate  a  key  switch 
before  the  retarder  will  open.  After  passage  of  the  car  movement  the  trainman 
removes  his  key  from  the  key  switch  and  the  retarder  will  automatically  reclose. 

As  previously  pointed  out,  lying  to  the  east,  between  the  yard  and  residential 
areas,  is  a  65-ft  bluff  created  by  excavations  for  the  yard.  On  top  of  this  bluff  was 
constructed  a  10-  to  15-ft  mound  so  that  the  combination  of  the  bluff  and  the  mound 


Address  by  R.  A.  P.  Sweeney  561 

would  also  act  as  a  sound  barrier  shielding  tiie  concerned  residents  from  yard  noises. 
By  eliminating  retarder  squeal  at  both  ends  of  the  \ard,  b>-  use  of  sound  barriers  at 
the  hump  retarders,  and  by  having  a  convenient  bluff  to  the  east  where  there  are 
residential  areas,  Burlington  Northern  has  been  able  to  create  an  exceptionally  quiet 
yard. 


The  Load  Spectrum  for  the  Fraser  River  Bridge 
at  New  Westminster,  B.C. 

77-65 8-S 

By  R.  A.  P.   SWEENEY 

Structural    Engineer 
Canadian   National    Railways 

INTRODUCTION 

"The  thought  of  a  steel  member  suddenly  faihng  after  years  of  service  brings 
a  chill  to  any  engineer.  This  possibility  turned  to  reality  on  December  15,  1967, 
with  the  collapse  of  the  Point  Pleasant  Bridge  connecting  Point  Pleasant,  West 
Virginia  and  Kanauga,  Ohio.  Forty-six  persons  were  carried  to  their  deaths  when  an 
eyebar  failed  and  the  bridge  suddenly  collapsed  into  the  Ohio  River  carrying  31 
of  the  37  vehicles  on  the  bridge  with  it.  This  tragic  event  'which  occurred'  during 
the  evening  rush  hour  has  focused  the  attention  of  bridge  engineers  throughout  the 
world  on  the  safety  of  existing  steel  bridges."  (1),  (2),  (3)^ 

In  late  1971  the  writer  was  asked  to  investigate  the  fatigue  problem  in  a  general 
way  in  order  to  determine  what  procedures  should  be  used  to  evaluate  Canadian 
National's  over  3500  steel  bridges.  This  study  is  still  continuing. 

In  order  to  avoid  a  calamity  of  the  magnitude  of  the  Point  Pleasant  failure,  the 
heavily  tra\elled  east-west  main  lines  carrjing  more  than  10  million  gross  tons  annu- 
ally were  examined.  Of  the  bridges  evaluated,  by  far  the  weakest  from  the  point 
of  view  of  absolute  strength  and  gross  tonnage  was  the  Fraser  River  Bridge  at  Mile 
118.5  of  CN's  Yale  Subdivision. 

The  Fraser  River  bridge  is  one  of  the  largest  rail-water  crossings  in  Canada. 
It  has  a  total  length  of  about  2000  ft  with  additional  extensive  timber  pile  ap- 
proaches. The  bridge  is  owned  by  the  Public  Works  Department  of  Canada  and 
is  used  by  three  railways,  namely:  Canadian  National,  Burlington  Northern  and 
British  Colmnbia  Hydro.  Canadian  National  Railways  is  the  main  user  and  has  the 
responsibihty  for  inspection. 

Since  the  bridge  was  built  in  1904  (see  Figure  1),  is  of  rather  weak  design 
(Cooper  E40  at  today's  stresses)  and  carries  all  CN  trafiSc  to  Vancouver,  Canada's 
third  largest  city,  with  a  heavy  percentage  of  unit  trains,  Canadian  National  arranged 
for  an  investigation  of  its  remaining  useful  life.  (4),  (5). 

A  firm  maximmn  life  could  not  be  established  witliout  precise  data  on  the  loads 
to  which  the  bridge  has  been  and  will  be  subjected.  This  paper  describes  the  load 
spectrum  used  to  analyze  the  bridge  with  particular  reference  to  the  useful  life  of 
the  hangers  of  the  main  380-ft  span  (Figure  2). 


''■  Numbers  in  parenthesis  indicate  references  listed  at  the  end  of  this  report. 
Note:  Discussion  open  until  October  15,  1976. 


562 


Bulletin  658 — ^American  Railway  Engineering  Association 


Figure  1 


Figure  2 


Address  by  R.  A.  P.  Sweeney  563 


I.  TRAFFIC  DENSITIES  AND  PROJECTIONS 

Figure  3  shows  the  actual  and  projected  gross  tonnages  in  miUion  gross  tons 
per  mile  for  the  period  1930  to  1980.  The  upsurge  in  traffic  from  1970  is  tlie  result 
of  the  introduction  of  unit  trains.  During  tlris  study  reasonably  accurate  carload 
data  from  1967  to  the  present,  and  odd  snapshot  type  studies  before  that  year  were 
available.  The  study  showed  tliat  tlie  fatigue  analysis  was  not  sensitive  to  relatively 
large  errors  in  the  predicted  car  cycles  before  1967. 

Annual  tonnages  (Figure  3)  across  the  bridge  did  not  exceed  10  million  gross 
tons  before  1963,  but  by  1970,  18  million  gross  tons  were  recorded.  The  marketing 
projection  anticipates  60  million  gross  tons  or  full  line  capacity  by  1980. 

Sources  of  Data 

The  most  reliable  source  of  historical  data  is  the  conductor's  train  journals. 
These  were  not  available  for  the  full  period  and  when  available  are  extremely 
unwieldy.  Two  independent  computerized  data  bases  were  a\ailable.  The  first  is 
the  CN  car  file  which  is  made  from  the  journals,  and  the  second  is  the  waybill  file 
made  from  the  waybills.  These  togetlier  with  the  bridge  tender's  annual  car  counts 
and  a  number  of  short-term  studies  done  in  the  past  based  on  conductor's  journals 
were  used  to  set  up  die  historical  data. 

The  projection  used  for  future  traffic  was  based  on  then  current  ( 1974)  company 
forecasts  by  a  special  group  set  up  to  study  traffic  density  problems  in  the  Vancouver 
area.   Two   alternative   forecasts   were   also   investigated,   but   are   not  reported    (4). 

II.  RASIC  CAR  CYCLE  DATA 

Past  Traffic 

As  a  sample  the  1973  distribution  based  on  the  CN  car  file  data  base  is  as 
shown: 


1973  Frequency  Distribution 

Range 
Tons 

Tons 

Cars 
Per  Annum 

7c  of 
Total 

7c  of 
Loaded 

0-20 

10 

20,445 

4.9 

N/A 

20-40 

30 

234,117 

55.9 

N/A 

40-60 

50 

23,876 

5.7 

N/A 

60-80 

70 

33,582 

8.0 

23.9 

80-100 

90 

32,878 

7.8 

23.5 

100-120 

110 

9,418 

2.2 

6.7 

120-131. .5 

125.75 

64,152 

15.3 

45.8 

131.5-140 

135.75 

329 

0.1 

>  140 

2 

0.0 

Total  Cars 

418,799 

Gross 

Tonn 

age:   22,545,392 

Average 

Gross 

;  Per  Car:   54  tons 

The  AAR   average  for  this  same  period  was  56.9  tons. 
Similar  tables  were  made  for  all  previous  years   (4). 


564 


Bulletin  658 — American  Railway  Engineering  Association 


S3im  Noi   ssoao   Nomw 


X 

o 


-S 


3 

01    IT  f  •* 


3: 

■z^ 

>- 

I— 

t_> 

' 

1 — 

-=c 

1 

1 

1 — 

C2 

1 

rr- 

Cu 

»— « 

u.\ 

LU 

c:) 

LU 

>- 

<^ 

ej 

CS 

f.l 

rr' 

_j 

f~l^ 

■=r 

"=r 

1 1  1 

^^ 

^: 

eel 

r>^ 

C  J 

Ll.l 

:pt 

V'\ 

O 

ll  1 

C   J 

CD 

li  1 

-p^ 

Qi 

1 — 

h- 

e3 

l^ 

<— > 

IT" 

<I 

LU 

h- 

a 

C3 

■i^. 

Oi 

1 

III 

UJ 

z: 

1 

1— 

1— 

C-) 

z: 

III 

i_) 

c_> 

I— 

...1 

•— H 

LU 

111 

<r 

>— « 

fr— 1 

—3 

C/) 

h- 

Ll_ 

i    > 

C3 

C/) 

IJLl 

etc 

Oi 

c  ) 

> 

rr-. 

H- 

Cl. 

O- 

CD 

2: 

•a: 

t_5 

<a: 

Address  by  R.  A.  P.  Sweeney 


565 


In  order  to  complete  the  picture  an  assumption  had  to  be  made  with  regard 
to  locomotives,  since  except  for  unit  trains  the  number  of  locomotives  is  not  precisely 
known.  It  was  assumed  that  on  the  average,  except  for  unit  trains,  there  was  one 
locomotive  for  every  30  cars.  The  table  below  summarizes  tlie  relevant  CN  traffic 
to  the  end  of  1973.  Since  car  loads  weighing  less  than  80  tons  gross  do  not  influence 
the  fatigue  life  of  this  bridge,  they  are  ignored  in  the  following  tabulation. 


Summary   of   Car  Cycles   to    1973 


Range 

1967  to 

1961  to 

1940  to 

1904  to 

Total 

Total 

Tons 

1973,  inc. 

1966 

1960 

1940 

CN 

All  Roads 

80-100 

161,703 

174,000 

445,000 

80,000 

860,000 

1,169,000 

100-120 

74,977 

31,200 

102,000 

— 

208,000 

282,000 

120-131.5 

106,620* 

780 

— 

— 

107,000 

145,000 

131.5-140 

329 

20 

— 

— 

300 

407 

>140 

2 

— 

— 

— 

2 

3 

Locomotives 

370,000 

503,000 

Unit  Trains 

112,000 

— 

— 

— 

112,000 

— 

Their  Locos. 

4,200 

— 

— 

— 

4,200 

— 

*  Unit  trains  excluded. 

To  obtain  the  total  for  all  roads,  i.e.,  CiN,  BN  and  BCH,  CN  traffic  has  been 
multiphed  by  1.36.  Tlie  figure  1.36  is  the  mean  value  over  the  last  decade  based 
on  the  bridge  tender's  car  count  (4).  The  assumption  here  is  that  the  traffic  pattern 
for  these  roads  is  the  same  as  CN's  for  heavy  traffic  with  the  exception  of  unit 
trains. 

Future  Traffic 

Using  the  figures  supplied  by  the  co-ordinator  of  the  Vancouver  Terminal 
Study  (see  Figure  4)  and  using  average  car  types  for  each  major  commodity  (4), 
the  following  table  was  derived: 

1974-1980 
Includes  CN,  BN  &  BCH 


Range 

%of 

Line 

G.T. 

Cars' 

Total 

1 

100-120 

447,600 

7.9 

2 

120-131.5 

925,600 

16.3 

3 

Locos. 

178,000 

3.1 

Total 

5,681,000 

Line  1  consists  of  predicted  grain  moves  only. 

Line  2  consists   of  predicted  coal,   sulphur,   potash,  phosroc  and  5%  of  remaining 

loaded  cars  less  express  and  passenger  cars   (6,  p.  108). 
Line  3  consists  of  three  locomotives  per  unit  train  as  per  unit  train  specffications, 

two  units  per  passenger  train  and  one  unit  per  each  remaining  40  car  group. 


^  For  the  entire  period. 


566 


Bulletin  658 — American  Railway  Engineering  Association 


-C   to 

*>  >> 

I  ^  : 


F3 


r^      (n      <n      f^ 


<>■  O^  (J^  O         OS         (js. 


?    R 

CO 

^ 

3 

fi 

N         0~< 

r^ 

-* 

^ 

-^ 

>" 

>         O 

vO 

NO 

■7 

-* 

vO 

°  ^ 


g    :3    :3 

-^        O         CO 


H         C^         fV         (V         c<\ 


^    :i    :J 


5     3 

CD 

3 
S 

3 

3 

^    d 

O 

O 

3 

CO 

C^ 

N         f\ 

t^ 

n 

-» 

-* 

-* 

•^         CO 

rH 

NO 

■O 

c~ 

r- 

n    3 

:! 

5 

CM 

5?; 

J^      P 

s 

:3 

nO 

o 

^ 

M          CM 

c^ 

C-, 

n 

r\ 

-* 

*         CO 

cv 

-: 

NO 

". 

CO 

^   & 


a  a  a  f^ 


CTn         ITv         C?N         C7\         CTv         (7\         (>» 
rH         rH         rH         rH         rH         rH         rH 


1   c  E  a 


t- 

C-- 

./^ 

CM 

o 

^ 

o 

ON 

C5 

r^ 

-» 

K 

VN 

CO 

s 

■-J 

^ 

r! 

UN 

w 

CO 

rH 

On 

vO 

(r-i 

u 

« 

tN. 

CO 

o 

^ 

CM 

!^ 

C?N 

00 

CTn 

O 

■a 

1 

CO 

en 

q 

CM 
CO 
en 

■^ 

M 

'^ 

rH 

r-1 

r-i 

i- 

O 

tn 

NO 

00 

r-l 

~* 

NO 

00 

« 

>: 

CM 

OJ 

CM 

cn 

en 

<n 

<n 

JN- 

ON 

NO 

CD 

C-- 

CM 

iH 

P4 

o 

rH 

nO 

CV 

CD 

WN 

s 

' 

UN 

NO 

NO 

C^ 

CD 

:| 

:| 

:| 

ce 

4 

?< 

CM 

_ 

y 

r-i 

rH 

r-t 

rH 

NO 

(-• 

On 

Si 

w\ 

o 

>-> 

" 

vO 

o 

CM 

a: 

-* 

*" 

«> 

■^ 

^ 

NO 

O 

CNJ 

rH 

CM 

NO 

CNJ 

rH 

-» 

►J 

H 

rf 

NO 

O 

d 

NO 

SI 

^ 

-* 

tH 

rH 

rH 

rH 

^^ 

n 

o 

O 

O 

o 

en 

^ 

CM 

K; 

^ 

^ 

KJ 

f;; 

Rf 

E-< 

3 

nO 

« 

8 

•cS 

rH 

t^■  ■■ 

o 

-* 

00 

>n 

03 

o 

E 

on 

-» 

-» 

-» 

M 

!/> 

m 

-* 

c\ 

NO 

u 

CN- 

c? 

^ 

^t 

s? 

f^ 

N? 

e 

F- 

c 

1 

!^ 

^ 

O 

CO 

CM 

H 

On 

^ 

3 

^ 

^ 

^ 

s 

en 

CM 

R 

>c\ 

lA 

NO 

-o 

C-- 

00 

CTn 

CO 

tN. 

o 

nO 

ri 

rH 

l/> 

UN 

00 

s? 

7i 

S 

•-I 

rH 

c 

a 

en 

en 

CM 

?a 

5 

^ 

en 

nO 

en 

5H 

m 

r^ 

n: 

t- 

-* 

^ 

g 

a 

t-- 

r- 

■-I 

•-I 

rH 

^ 

Address  by  R.  A.  P.  Sweeney  567 

The  above  is  referred  to  as  the  Full  Market  Analysis  prediction.  Two  other 
market  projections,  not  detailed  here,  were  also  carried  out. 

Summary,  Car-Cycle  Data 

The  most  important  traffic  insofar  as  the  life  of  this  bridge  is  concerned  is  that 
occurring  between  1970  and  1980.  More  tonnage  will  cross  tlie  structure  in  tliis 
decade  than  in  its  entire  previous  history.  The  annual  gross  million  tons  will  go 
from  roughly  18  in  1970  to  60  in  1980. 

III.  LOAD  SPECTRUM  FROM  TRAINS 

Analytical  Study 

The  basic  train  and  car  crossing  data  outlined  above  were  used  to  define  the 
probable  load  spectrum  that  the  Fraser  River  Bridge  was  subjected  to  from  1904  to 
1973  and  projected  to  1980,  at  which  time  the  traffic  was  assumed  to  have  reached 
saturation.  Each  year  after  1980  was  assumed  to  carry  the  same  traffic  as  that  for 
the  year  1980. 

1.  Cijcles  per  Vehicle 

Available  field  data  show  that  the  passage  of  trains  over  a  bridge  produces 
major  stress  cycles  for  axle  and  truck  loaded  members  such  as  hangers  and  floor- 
beams,  with  superimposed  vibrational  cycles  (6),  (7),  (12).  For  most  structures 
the  superimposed  vibrational  cycles  are  small  enough  to  be  neglected  as  the  AASHO 
Road  Test  Studies  confirmed  (8). 

Strain  measurements  on  hanger.  Mi  Li  of  the  380-ft  through  truss  span  of  the 
Fraser  River  Bridge  confirmed  the  theoretically  calculated  cyclic  variation  of  stress 
range  and  showed  that  there  is  essentially  one  cycle  per  car  with  very  little  super- 
imposed vibrational  cycles.  Figure  3.1  compares  a  portion  of  a  record  of  a  unit 
coal  train  witli  the  theoretically  calculated  variation  assuming  space  frame  behavior. 
The  comparison  is  within  experimental  error.  Random  samples  of  all  other  car  types 
using    die    bridge    compared    as    favorably   with    their   theoretical   force-time   plots. 

2.  Probability  Density  in  Each  Weight  Group 

The  field  data  from  many  previous  studies  of  highway  and  railroad  traffic  also 
indicates  that  the  frequency-of-occurrence  data  can  often  be  idealized  reasonably 
well  by  use  of  the  Rayleigh  curves,  which  defines  a  family  of  skewed  probabihty- 
density  curves.  This  approximation  is  currently  being  used  to  develop  stress-cycle 
criteria  for  AREA  Committee  15. 

The  nondimensional  mathematical  expression  defining  a  truncated  Rayleigh 
curve  is  given  by   (9). 

p'  =  1.011  X  e''^'-^'*  (3.1) 

where 

^         Pr  —  Prmin        „ 
^  -  P^d—  ^  ^ 

Prmin  is  the  minimum  force  in  the  spectrum 

Prd  is  a  parameter  which  is  a  measure  of  the  dispersion  of  the  data 
The  root-mean-square  force  range  for  the  distribution  is  given  by 
PrRMS  =  Prmin  +   Prd  (3.2) 

A  Rayleigh  distribution  was  not  used  for  the  load  spectrum  since  the  actual 
spectrum  was  available.   The  use  of  the  actual  spectrum  is  preferable  when  it  is 


568 


Bulletin  658 — American  Railway  Engineering  Association 


8 

lO 

z 
o 


in 


i\ 


o 


■5 


o 


CM 
O 

o 

X 

Q. 


X 

a 


a 
o 

en 

i 
t 

o 

g 


is! 


X 

Q. 

Z 


Address  by  R.  A.  P.  Sweeney 


569 


40 


30 


20 


10 


K^ 


\\ 


■;  \ 


Mi 


mM 


steam 
Locomotives 


K 


55  65  75  85  95 

HANGER   FORCE  ,  kips 


105 


115 


Figure  3.2 — Load  frequency   (simple  truss   analysis)   up  to   1973. 


available.  The  FHWA  nationwide  load  spectrum  used  to  derive  the  AASHTO  fatigue 
provisions  is  bimodal  (10).  A  similar  traffic  pattern  exists  over  the  Eraser  River 
Bridge.  The  two  peaks  can  be  seen  in  Fig.  3.2.  This  reflects  the  effect  of  the  heavy 
unit  train  traffic  over  the  Fraser  River  Bridge  (see  Fig.  3.2).  The  obvious  conclusion 
is  that  if  any  one  commodity  represents  a  substantial  proportion  of  the  traffic,  it 
must  be  considered  independently.  A  pure  Rayleigh  approximation  with  only  one 
peak  can  be  in  substantial  error. 

Examining  the  distribution  of  loaded  unit  train  vehicles  from  tests  on  the 
Fraser  River  Bridge  and  the  far  more  exhaustive  data  on  cars  loaded  over  110  tons 
on  a  line  which  feeds  traffic  to  the  bridge  (11),  it  is  quite  evident  that  100-ton- 
capacity  cars  used  in  bulk  service  are  loaded  close  to  their  rated  capacity. 

Since  most  of  the  cars  in  the  120-  to  131. 5- ton  range  crossing  the  Eraser  River 
Bridge  are  carrying  bulk  commodities,  and  since  the  110-  to  120-ton  cars  are  put 
in  the  next  lower  class  interval,  these  cars  are  assumed  to  be  loaded  to  their  rated 
capacity.  Test  measurements  on  the  Fraser  River  Bridge  made  in  June  1975  confirmed 
this  assumption.  Cars  in  lower  weight  ranges  follow  a  Rayleigh  distribution  (5). 
Thus,  except  for  the  120  to  131.5  group,  each  car  or  locomotive  in  an  interval  of 
car  or  locomotive  loadings  was  assumed  to  result  in  a  force  range  Rayleigh  frequency 
distribution  as  shown  in  Fig.  3.3.  As  an  example,  this  results  in  a  RMS  load  for 
the  load  interval  80-100  tons  of  89.2  tons  as  illustrated. 

3.  Frequency  Distribution  up  to  1973 

The  force  range  P  acting  on  a  hanger  was  evaluated  from  force-time  plots 
assuming  plane  truss  behavior.  The  resulting  value  is  adjusted  to  account  for  actual 
behavior.  These  provided  the  hanger  force  for  several  locomotive-car  combinations. 


570 


Bulletin  658 — American  Railway  Engineerinj^  Association 


1.378 

Prd 

,,.  1 

— 1~- 

3 

Prd 

^    0.6 

->>v 

>- 

> 

K 

\ 

CO 

\ 

■z. 

_ 

\ 

Ld 

V 

O 

\ 

XL  0.4 

\ 

_j 

y 

V- 

\ 

CO 

/ 

C\J 

\ 

< 

O 

-  / 

(J) 

00 

\ 

q: 

J 
1 

CO 

\^ 

^  0.2 
n 

1 

2 

q: 

X 

80 


90 
CAR    WEIGHT  ,  tons 

Figure  3.3 — Assumed  car  weight  distribution  in  80-100  ton  car  load  interval. 


100 


Of  the  76,500  steam  units,  80%  were  assumed  to  be  transfer  units  as  the  bridge 
is  in  a  terminal  area.  The  balance  was  assumed  to  be  Northern  Class  units.  The 
remaining  293,500  diesel  units  were  assumed  to  be  composed  of  235,000  single 
unit  trains  with  the  remaining  units  in  trains  with  2  or  3  units  per  train. 

The  cars  in  each  weight  class  were  assumed  to  be  placed,  in  proportion  to  their 
frequency,  after  the  diesel  locomotive  units.  All  stress  cycles,  except  for  unit  trains, 
were  increased  by  the  factor  1.36  to  account  for  other  roads  using  the  structure. 
These  assumptions  resulted  in  the  following  force  range  distribution  for  the  cars  and 
locomotives  crossing  the  bridge  (Tables  1  and  2)  up  through  1973. 

The  results  in  Tables  1  and  2  were  used  to  evaluate  the  effective  range  of  force 
under  the  random  variable  cycles  of  load  that  were  applied  to  the  hangers.  Both 
the  RMS  and  the  Miner's  equivalent  force  range  were  evaluated,  as  recent  studies 
have  shown  that  both  provide  reasonable  estimates  of  the  cumulative  effects  of 
variable  cycle  loading  (9). 

The  root-mean-square  force  range  corresponding  to  the  2,217,810  force  cycles 
in  Tables  1  and  2  was  detennined  as: 


PrRMS  =    [2   (a.Pr)]' 
=   71.7  kips 


(3.3) 


Address  by  R.  A.  P.  Sweeney 


571 


Table  1 — Stress  Cycles  Up  to  1973  From  Cars 


RMS 

Frequency 

Force  on 

Type  (tons)            PRMS  (tons) 

After  Loco. 

After  Car 

Hanger,  kips" 

80   -100                    89.2 

262,970 

— 

61.8 

— 

906,630 

58.3 

100    -120                   109.2 

63,602 

— 

75.6 

— 

219,278 

71.4 

120    -131.5               131.5 

32,717 

— 

91.0 

— 

112,802 

86.1 

131.5-140                   134.0 

90 

— 

92.8 

— 

321 

87.7 

Unit  train 

131.5                           131.5 

1,400 

— 

91.0 

ior. 

110,600 

86.1 

•  Assuming  plane  truss  behavi 

Table  2 — Stress 

Cycles  Up  to 

1973 

From  Locomoti> 
Frequency  X 

,ES 

RMS 
Force  on 

Tijpe 

Frequency 

1.36 

Hanger  kips' 

Single  Unit-Northern 

15,300 

20,808 

121.0 

Single  Unit-Transfer 

61,200 

82,232 

111.2 

Single  Unit  Diesel 

235,000 

319,600 

78.0 

2  or  3  Unit  Diesel 

29,250 

39,780 

78.0 

29,250 

39,780 

94.0 

Unit  Trains 

1,400 

1,400 

78.0 

2,800 

2,800 

94.0 

"  Assuming  plane  truss  behavior. 
The  Miner's  equivalent  force  range  is  defined  by: 
PrMINER  =    [  ^  aiPi"  ]'" 
=    73.4  kips 


(3.4) 


It  is  readily  apparent  that  both  methods  >ield  about  the  same  effective  force 
range. 

4.  Frequency  Distribution  Up  to  1980 

For  the  period  1974-1980,  the  protection  indicates  tliat  there  will  be  101,988 
trains  with  178,000  locomoti\'es.  Unit  trains  will  number  19,534.  Of  the  remaining 
82,454  trains,  36,944  were  assumed  to  have  2  locomotives  and  45,510  trains  were 
assumed  to  have  a  single  locomotive. 

Cars  in  each  weight  class  were  treated  as  in  the  1904-1973  period.  The  follow- 
ing Table   3   summarizes   the  force  cycles  for  this  period. 


572 


Bulletin  658 — American  Railway  Engineering  Association 


Table  3 — Force  Cycles  From   1974-1980 


Type 

PRMS  (to 

Locomotives 

— 

Cars  (tons) 

80-100 

89.2 

100-120 

109.2 

120-131.5 

131.5 

frequency 

Force,  kips'  " 

101,988 

78.0 

76,012 

94.0 

93,215" 

61.8 

321,374 

58.3 

16,624* 

75.6 

430,976 

71.4 

34,376* 

91 

891,224 

86.1 

"  Adjacent  to  locomotive. 
°"  Assuming  plane  truss  behavior. 

When  the  variable  force  cycles  in  Tables  1,  2  and  3  are  combined,  the  effective 
force  range  for  the  4,183,599  cycles  becomes 

PrRMS        =  74.7  kips 

PrMINER  =  75.9  kips 
5.  Frequency  Distribution  After  1980 

The  traffic  pattern  for  each  year  after  1980  was  assumed  to  be  at  saturation 
which  results  in  the  following: 

Table  4 — Force   Cycles   Per  Annum  After   1980 


Type 

PRMS  (to 

Locomotives 

Cars 

80-110 

89.2 

100-120 

109.2 

120-131.5 

131.5 

Frequency 

Force,  kips* 

16,330 

87.9 

12,170 

83.2 

16,100 

61.8 

55,400 

58.3 

2,300 

75.6 

59,500 

71.4 

6,290 

87.9 

163,060 

83.2 

331,150  cycles  per  annum 


"  Assuming  plane  truss  behavior. 


6.  Summary  of  Field  Test  Results 

Three  series  of  field  measurement  were  taken;  a  series  in  June  1975  and  two 
series  in  August  referred  to  as  the  T  and  S  series.  The  maximum  amount  of  life  used 
by  cyclic  variation  was  calculated  for  Hanger  Mi  Li  for  the  three  series  of  tests. 
Figure  3.4  shows  a  plot  with  the  measured  cycles  scaled  by  10*  indicating  how  this 
was  done  for  the  June  series  of  tests. 

A  least  life  occurs  when  the  root-mean-square  stress  range  is  nearest  to  tlie 
failure  curve  as  derived  from  laboratory  fatigue  tests.  The  least  life  occurs  in  this 
case  when  all  cars  greater  than  80  tons  gross  are  included.  Nevertheless,  it  is  readily 


Address  by  R.  A.  P.  Sweeney 


573 


< 

cr     5 


•Category  E 


Minimum -'''^459" 


Sr  =  ^RMS  ^  0-55  X  30  X  10^  x  23.09  x  0.735/8.65 

Seeled   by  10'* 

Pf,f^,3=  152.4  X 10"^  X  0.55  x  30  x  lo'  x  23.09  =  58.0  kips  at  422  cycles 


CYCLES 
Figure    3.4 — Frequency   vs.    effective    stress    range. 


10' 


80 


60  — 


I 8   Series 

Record    S-4 

VVinniondy  Coal  £  Locos  S-2 

n  =393 

.  ^RMS 

161.1 


40 


20 


Mean ^ 

60.6         ll 


\h\  .. 


Mean 


60.6 


J 


T  Series 
^MS  Record  T-17 

62.9         Luscar 
Coal 
n  =  380 


tih. 


40  60  80  40  60  80 

AXLE     LOAD    ,  kips  AXLE    LOAD  ,   kips 

Figure   3.5 — Unit  train   axle   loads — August   tests. 


574 


Bulletin  658 — American  Railway  Engineering  Association 


apparent  from  Fig.  3.4  tliat  not  much  difference  in  life  results  by  including  all  cars 
over  60  tons  or  only  over  100  tons  gross,  as  all  points  are  about  equi-distant  from 
the  fiiilure  curve.  Hence,  tlie  use  of  cars  weighing  in  excess  of  80  tons  provides  a 
reasonable  means  of  assessing  the  fatigue  damage. 

It  is  known  tliat  the  unit  train  in  test  T  and  the  one  in  test  S  were  underloaded. 
A.\le  loads  were  recorded  during  the  S  and  T  test  series.  The  results  of  these  measure- 
ments are  summarized  in  Fig.  3.5.  The  mean  axle  load  is  seen  to  equal  60.6  kips 
which  is  about  8%  less  than  the  anticipated  mean  of  64.8  kips.  The  theoretical  value 
after  correcting  for  this  underloading  is  64.3  kips  for  unit  trains. 

Table  5  shows  the  RMS  force  values  and  the  number  of  cycles  considered  for 
the  three  test  groups.  Also  shown  is  the  1975  RMS  value  corrected  for  space  frame 
action.  The  data  summarized  in  Table  5  show  that  unit  trains  result  in  stress  cycles 
that  are  in  very  good  agreement  with  the  stress  cycles  estimated  from  1975  traffic 
projections.  The  effective  stress  cycles  for  all  train  traffic  was  measured  to  be  shghtly 
less  than  predicted  from  the  traffic  projections.  This  difference  varied  from  7  to  10% 
on  the  conservative  side.  The  frequency  of  occurrence  of  the  measured  stress  cycles 
was  in  good  agreement  witii  the  projected  frequency  for  the  1974-80  time  period 
(36.8%  measured  vs.  34.6^  projected). 

The  experimental  field  measurements  have  confirmed  the  applicability  of  apply- 
ing the  traffic  projections  to  evaluate  the  stress  cycles  in  the  members  of  the  Fraser 
River  Bridge.  An  accurate  assessment  of  the  member  forces  can  be  made  using  an 
appropriate  analysis  procedure.  Hence,  the  equivalent  static  force  range  for  the 
intervals  1904  to  1973,  1974  to  1980  and  from  1980  onward  can  be  used  to  deter- 
mine the  eftective  stress  range  for  these  intervals. 


Table 

5— Measured    Member 

Force 

All  Trains 

Unit  Trains 

Test 

PRMS,  kips 

Effective  Cycles 
Over 
Total  Cycles 

PRMS,  ki 

ps 

Effective 
Cycles 

June  '75 

58.1 

422/984 

70.6 

182 

T 

56.1 

178/568 

64.1 

95 

T 

56.3 

172/568 

63.9 

95 

S 

Average 

55.2 

183/605 

36.8% 

61.7 

95 
51.8% 

Predicted 
projected 

(1975) 
traffic) 

62.6 

34.6% 

69.8' 

51.7% 

"  For  T  &  S  series  the  estimated  member  force  is  64.3  kips  if  underloading  is  considered 
for  the   120-131.5  ton  vehicles. 

7,  Impact  and  Roll  Effects 

Impact  and  roll  effects  increase  the  static  force  by  an  indeterminate  dynamic 
interval.  The  influence  of  this  variable  on  the  stress  cycle  response  is  completely 
random  and  seldom  if  ever  produces  the  full  design  stress  range.  In  this  study  it 
was  assumed  that  the  dynamic  increment  was  also  distributed  in  a  skewed  manner. 
The  assimied  distribution  is  shown  in  Fig.  3.6.  The  maximum  value  was  assumed 
to  be  the  full  17.7%  provided  by  the  AREA  specification  for  10  mph.  The  minimum 
combined  eftect  of  impact  and  roll  was  taken  as  0.95.  This  is  reasonably  compatible 


Address  by  R.  A.  P.  Sweeney 


575 


0.6  r— 


!^    0.4 


■a: 


DYNAMIC      FACTOR 
Figure   3.6 — Assumed   variation    of   dynamic   increment. 


witlt  available  studies  which  indicate  that  at  times  the  member  sees  less  than  the 
static  stress  range.  The  root-mean-square  of  the  skewed  dynamic  increment  was 
detemiined  to  be  1.054. 

A  calculation  of  the  static  increment  for  an  SD-40  locomotixe  produces  an 
effective  unsprung  axle  weight  of  roughly  15%  X  65.75  =  9.86  kips  which  when 
compared   to   the   static   calclulated  force   in   the   hanger  gives   an   impact  of   1.054. 

Field  Tests  on  the  Fraser  River  Bridge 

All  the  field  measurements  except  for  a  few  of  the  S  series  were  made  with 
signal  filters  with  roll-off  frequencies  from  10  to  14.2  Hertz  (Hz).  This  did  elimi- 
nate certain  impact  effects  at  10  mph  and  upwards.  For  this  reason  a  special  series 
of  impact  tests  were  conducted  using  three  locomotives. 

Impacts  increased  witli  train  speed  as  expected.  The  a\'erage  impact  at  20  mph 
in  the  loaded  direction  was  1.12.  This  is  very  close  to  the  RMS  value  calculated  as 
follows : 


Vertical  impact: 
Rolling  impact: 


Speed  correction: 


38.9% 
20.0 

58.9% 
0.6     20  mph 


35.4% 


The  RMS  value  between  0.95  and  1.34  is  1.136  for  20  mph.  The  minimum 
measured  impact  coefficient  was  0.956  which  is  very  close  to  the  assumed  minimum 
of  0.95.  The  average  measured  impact  at  10  mph  in  the  loaded  direction  was  1.054. 


576  Bulletin  658 — American  Railway  Engineering  Association 

In  the  pin  plate  the  measured  values  were  somewhat  higher  presumably  due  to 
a  certain  amount  of  ringing  in  the  plate.  At  20  mph  the  impact  was  1.17  in  the 
loaded  direction  with  some  evident  ringing  at  28  Hz.  At  10  mph  the  impact  in 
the  pin  plate  was  1.071.  Since  the  slow  order  on  the  bridge  is  set  at  8  mph  the 
average  impact  for  tlie  hanger  was  taken  as  1.054. 

Sensitivity  of  the  Analysis 

The  calculations  show  that  a  5%  change  in  the  predicted  number  of  loaded  131.5 
gross  ton  cars  had  a  negligible  effect  on  the  calculated  life,  as  the  difference  between 
the  full  market  analysis  prediction  and  alternate  one  is  less  than  a  year.  Only  a 
significant  change  would  make  a  difference. 

CONCLUSION 

Historical  data  were  scanned  to  produce  a  load  spectrum  for  past  traffic. 

Future  traffic  was  estimated  based  on  marketing  projections.  The  years  1974 
and  1975  were  used  to  check  these  projections  and  the  comparison  was  favorable. 

The  effect  of  ignoring  cars  less  than  80  tons  was  shown  to  be  negligible.  Strain 
measurements  indicated  that  there  was  essentially  one  cycle  per  car,  and  confirmed 
the  assumed  impact  percentage  based  on  an  RMS  value  of  a  Rayleigh  distribution. 

On  this  bridge  bulk  commodities  in  unit  trains  represent  a  substantial  proportion 
of  die  traffic.  Cars  over  80  tons  gross  represented  more  than  25%  of  the  traflBc  in 
1975,  with  16%  of  the  total  traffic  in  the  120  to  131.5  ton  range. 

Figures  reported  by  Drew  (6)  in  1968  that  no  more  than  5%  of  all  loads  are 
near  the  maximum  appears  to  be  valid  only  in  cases  where  unit  trains  are  not 
significant  and  furthennore  appears  only  valid  for  the  past  decade.  As  time  goes  on 
and  railroads  become  more  efiBcient,  this  figure  will  creep  upwards.  On  CN's  main 
line  through  the  Rockies  a  25%  figure  for  the  120-131.5  ton  group  is  anticipated 
within  the  next  decade.  Further  studies  on  other  CN  lines  are  being  conducted  to 
see  if  this  increase  can  be  expected  elsewhere. 

Finally,  the  experimental  field  measurements  confirmed  the  applicability  of 
applying  the  traffic  projections  to  evaluate  the  stress  cycles  in  the  members  of  the 
Fraser  River  Bridge. 

REFERENCES 

1.  W.  J.  Cain  and  C.  Seim,  "Carquinez  West  Bridge  Eyebar  Investigation — Phase 
I,"  May  1974,  Toll  Bridge  Administration,  Department  of  Transportation,  State 
of  California,  San  Francisco,  Calif. 

2.  Charles  F.  Scheffey,  "Point  Pleasant  Bridge  Collapse — Conclusions  of  the  Federal 
Study,"  Civil  Engineering,  ASCE,  July  1971,  pp.  41-45. 

3.  Daniel  Dicker,  "Point  Pleasant  Bridge  Collapse  Mechanism  Analyzed,"  Civil 
Engineering,  ASCE,  July  1971,  pp.  61-66. 

4.  R.  A.  P.  Sweeney,  "Investigation  of  the  Remaining  Useful  Life  of  the  Fraser 
River  Bridge,  New  Westminster,  B.C.,"  Phase  I,  Jan.  31,  1975,  Canadian  National 
Railways,  Montreal,  Quebec. 

5.  J.  W.  Fisher  and  J.  Hartley  Daniels,  "Report  on  Investigation  of  the  Estimated 
Fatigue  Damage  in  Components  of  the  Fraser  River  Bridge,  New  Westminster, 
B.C.,"  for  Canadian  National  Railways,  Montreal,  Quebec,  February  1976. 

6.  W.  H.  Munse,  J.  E.  Stallmeyer  and  F.  P.  Drew,  "Structural  Fatigue  and  Steel 
Railroad  Bridges,"  Proceedings  of  AREA  Seminar,  1968,  AREA  Chicago. 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels 577 


7.  Association  of  American  Railroads,  "Field  Investigation  of  Two  Truss  Spans 
on  the  Southern  Pacific  Company,"  May  1968,  Report  ER-82,  AAR  Research 
Center,  Chicago. 

8.  J.  W.  Fisher  and  I.  M.  Viest,  "Fatigue  Life  of  Bridge  Beams  Subjected  to  Con- 
trolled Truck  Traffic,"  Proceedings,  Seventh  Congress,  lABSE,  1964. 

9.  C.  G.  Schilling,  K.  H.  Klippstein,  J.  M.  Barsom  and  G.  T.  Blake,  "Fatigue  of 
Welded  Steel  Bridge  Members  under  Variable-Amplitude  Loadings,"  NCHRP 
Research  Results  Digest  No.  60,  April  1974. 

10.  J.   W.   Fisher,  "Guide  to    1974  AASHTO  Fatigue  Specifications,"  AISC,   1974, 
AISC,   New  York. 

11.  F.  E.  King,  "Tests  on  B.  C.  Soutli  Line  Clearwater  Subdivision,"  CN  Technical 
Research   Center,   Montreal,   Quebec,   February  28,   1975. 

12.  F.   P.    Drew,  "Recorded   Stress  Histories  in  Railroad  Bridges,"  Journal  of  the 
Structural  Division,  ASCE,  Vol.  94,  ST  12,  Dec.  1968. 


An  Investigation  of  the  Estimated  Fatigue  Damage  in 
Members  of  the  380-ft  Main  Span,  Fraser  River  Bridge 

By 
JOHN  W.   FISHER 

Professor  of   Civil    Engineering 

Fritz   Engineering    Laboratory 

Lehigh    University,    Bethlehem,    Pa. 

and 

J.  HARTLEY  DANIELS 

Associate   Professor  of   Civil   Engineering 

Fritz   Engineering    Laboratory 

Lehigh    University,    Bethlehem,    Pa. 

INTRODUCTION 

Older  railroad  bridges  which  have  accumulated  or  are  projected  to  accumulate 
large  numbers  of  stiess  cycles  may  experience  fatigue  crack  growth  from  their  riveted 
connections  or  other  structural  details  such  as  pin  plates  and  weldments.  This  is 
particularly  true  of  those  structures  built  to  carry  loads  that  are  not  much  greater 
than  most  of  the  traffic  using  the  bridge. 

The  Fraser  River  Bridge  at  New  Westminster,  British  Columbia,  is  typical  of 
this  type  of  structure,  as  it  was  built  in  1904  to  a  weak  design  and  presently  carries 
most  of  Canadian  National  Railways'  traffic  to  Vancouver.  A  large  percentage  of 
the  current  and  projected  traffic  is  of  unit  trains.  Sweeney  in  a  companion  paper  ( 1 )  * 
has  examined  the  load  spectrum  for  past  traffic  and  for  future  traffic  based  on 
marketing  projections. 

In  this  paper  the  load  spectrum  defined  in  Ref.  1  is  used  to  assess  the  actual 
stress  spectrum  developed  in  the  members  of  the  structure  in  the  most  highly 
stressed  regions  so  that  an  evaluation  of  their  fatigue  life  can  be  made. 


"  Numbers  in  parenthesis  indicate  references  listed  at  the  end  of  this  report. 
Note:    Discussion  open  luitU  October   16,   1976. 


578  Bulletin  658 — American  Railway  Engineering  Association 

Canadian  National  arranged  for  strain-gage  measurements  of  certain  bridge 
members  to  assist  with  the  analytical  determination  of  tlie  stress  resultants  and  to 
verify  the  applicability  of  applying  tiaffic  projections  to  evaluate  stress  cycles.  Earlier 
tests  had  demonstrated,  for  example,  that  hangers  could  be  expected  to  exhibit 
erratic  behavior  and  unpredictable  stresses  adjacent  to  a  floorbeam  (2). 

This  paper  summarizes  Uie  evaluation  of  the  most  critical  hangers  and  tlie 
stringers  of  the  main  380-ft  fixed  span. 

STRESS  RESULTANTS  IN  HANGER  MXi  AND  PIN-PLATES  AT  Mi 

Hanger  MiLi  and  the  floorbeam  and  stringers  are  shown  in  Fig.  1  for  tlie  380-ft 
fixed  span.  The  hanger  above  the  floorbeam  connection  consists  of  four  angles  6  x 
SJa  x  %  plus  two  fill  plates  332  x  ii  riveted  to  a  ITJz  x  7/16  web  plate  as  shown. 
Additional  %  fill  and  splice  plates  make  up  the  cross-section  near  the  floorbeam 
connection.  The  original  hanger  in  1904  consisted  of  four  angles  6  x  3/2  x  ^  plus  a 
system  of  2J2  x  %  lattice  bars.  The  lattice  bars  were  removed  in  1923  and  replaced 
with  a  solid  web  plate.  As  a  result  the  web  plate  is  discontinuous  near  the  top  of 
the  connection  between  the  hanger  and  floorbeam  as  shown  by  the  dashed  line  in 
Fig.  1.  The  connection  at  Mi  consists  of  two  11/16  pin  plates  bearing  on  a  5.41-in.- 
diameter  steel  pin. 

The  riveted  built-up  floorbeam  which  is  bent  upwards  and  partly  haunched 
between  the  stiingers  and  the  truss  is  attached  to  hanger  MiLi  above  Li  using  a 
pair  of  6  x  4  X  /8  connection  angles.  Between  stringers  the  floorbeam  consists  of 
pairs  of  6  X  6  X  9/16  angles  top-  and  bottom-riveted  to  a  51  x  %  web  plate. 

Wheel  loads  are  transmitted  to  the  floorbeam  and  thus  to  hanger  MiLi  dirough 
a  rail  and  tie  system  bearing  on  a  pair  of  built-up  stringers  placed  symmetrically 
48  in.  either  side  of  the  bridge  centerline.  The  stringers  consists  of  pairs  of  6  x  6  x 
7/16  angles  top-  and  bottom-riveted  to  a  42  x  fs  web  plate.  The  stringers  are  attached 
to  the  floorbeams  using  a  pair  of  connection  angles  as  shown  in  Fig.  1.  The  floor- 
beam  reaction  is  theoretically  carried  by  hanger  MiLi  between  the  floorbeam  con- 
nection and  Ml. 

Two  different  analytical  models  were  used  for  tlie  stress  analyses  of  the  main 
380-ft  span.  The  first  was  a  plane  simple  truss  model.  This  is  tlie  usual  analytical 
model  assumed  in  the  linear  stress  analysis  of  a  trussed  bridge  span  as  it  normally 
provides  an  upper  bound  to  overall  member  stress  resultants.  In  this  study,  one 
380-ft   plane   truss   was   isolated,   in  which   all  joints  were  assumed  pin-connected. 

The  second  was  a  three-dimensional  model,  developed  specifically  for  this 
study  to  closely  simulate  die  behavior  of  the  entire  380-ft  span  including  both  trusses 
and  all  major  load-carrying  intennediate  members.  The  model  used  in  the  computer 
solution  is  shown  in  Fig.  2.  Due  to  symmetry  about  the  bridge  centerline,  only  one 
truss  is  shown.  Since  the  analysis  was  concerned  primarily  with  stress  resultants 
in  hanger  MiLi  only  major  load-carrying  members  believed  to  have  a  significant 
influence  on  MXi  stress  resultants  were  retained  in  the  vicinity  of  hanger  MiLi. 
The  influence  of  the  structure  beyond  nodes  29,  30  and  31  was  included  by  specify- 
ing displacement  conditions  obtained  from  a  separate  plane  frame  truss  analysis. 
The  stringer  at  node  29  was  assumed  continuous.  Nodes  midway  between  the  trusses 
were  constrained  to  displace  only  vertically  and  horizontally  because  of  symmetry. 
Pin  joints  were  assumed  pinned  in  the  analysis.  Gussetted  joints  were  assumed 
continuous. 


J 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels 


579 


Fill  3/1  X  '/4 


Fig.  1 — Hanger  MiLi,  floorbeam  at  Li  and  pin-plates  at  Mi. 


580 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  2 — Member  and  node  numbering  for  three-dimensional  framed  truss  model. 


Stresses  in  the  Hanger 

(a)  Plane  Simple  Truss  Model 

The  plane  simple  truss  model  would  imply  that  only  axial  force  exists  in 
hanger  MiLi.  This  is  a  result  of  considering  only  a  plane  simple  truss  and  assuming 
that  the  load  is  directly  applied  at  panel  point  Li.  In  reality,  the  load  is  applied 
through  the  floorbeam.  The  actual  stress  resultants  in  hanger  MiLi  can  be  approxi- 
mated by  considering  the  hanger-floorbeam  frame  action. 

Fig.  3  shows  a  simplified  floorbeam-to-hanger  frame  model  often  used  in 
conjunction  with  a  plane  simple  truss  analysis  to  obtain  stress  resultants  in  the 
hanger  (3). 

By  superposition,  the  combined  axial  and  flexural  stress,  cr  (ksi),  at  a  cross 
section  of  the  hanger  between  Mi  and  the  top  of  the  connection  to  the  floorbeam 
can  be  computed  as: 


0.0178Phy 


(tension  positive) 


(1) 


where  A  =  gross  or  net  section  area   (in.^) 

Ix  =  gross  or  net  section  moment  of  inertia  about  the  major  axis  (in.*) 
h   =  distance  from  Mi  to  cross  section  under  consideration  (in.) 
y    =  distance  from  hanger  centroid  to  point  in  the  cross  section  (in.) 
P  =  hanger  axial  force  in  kips 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels 


581 


Floorbeam  -  Hanger 
Frame 


Fig.  3 — Floorbeam-hanger  frame  model. 


Bui.   658 


582  Bulletin  658 — American  Railway  Engineering  Association 

(b)   Three-Dimensional  Model 

The  three-dimensional  model  reasonably  approximates  the  continuity  con- 
ditions in  the  actual  bridge  span.  In  terms  of  a  load  P  at  tlie  stringer-floorbeam 
connection,  the  combined  axial  and  flexural  stress,  <t  (ksi),  in  the  hanger  between 
Ml  and  the  top  of  tlie  hanger  to  floorbeam  connection  is  computed  as  follows : 

„  _     0.8194P     ^    (0.0169h-0.0086)Py    ^    (0.0007h-0.1221)Px,  ,     ,„, 

'^ T ±  -^ z —^   ± = — (tension  pos.)     (2) 

A  Ix  ly 

where  A,  L,  L  and  y  are  as  defined  above,  P  is  the  concentrated  load  in  kips  at 
node  5  (Fig.  2),  and 

ly  =  gross  or  net  section  moment  of  inertia  about  the  minor  axis   (in.*) 
X    =  distance  from  hanger  centroid  to  point  in  the  cross  section  (in.) 

The  coefficient  0.8194  is  the  axial  force  in  the  hanger  which  results  from  a 
unit  load  at  tlie  stringer-floorbeam  connection. 

For  normal  downward  loading  P,  the  first  tenn  produces  axial  tension;  the 
second  term  produces  axial  tension  on  the  face  of  the  hanger  towards  node  5  except 
near  M;  the  third  term  produces  tension  in  the  lower  part  of  tlie  hanger  on  the 
side  of  the  hanger  towards  node  3  (Fig.  2)  and  on  the  opposite  side  in  the  upper 
part  of  the  hanger. 

Analysis  of  Stress  Resultants  in  Pin-Plates  at  Mi 

The  plane  simple  truss  model  assumed  a  pin  connection  at  Mi.  The  three- 
dimensional  model  assumed  continuity  at  Mi.  The  boundary  conditions  at  Mi  will 
have  negUgible  influence  on  the  calculation  of  stress  resultants  near  the  hanger 
to  floorbeam  connection  because  of  the  flexibility  of  tiie  hanger  relative  to  the 
floorbeam.  However,  the  boundary  condition  assumed  at  Mi  will  have  a  pronounced 
eflect  on  tlie  distribution  of  hanger  stress  resultants  to  each  of  the  two  pin-plates 
at  Ml. 

If  only  axial  force  exists  in  the  hanger,  and  both  pin-plates  share  tlie  force 
equally,  then  tlie  change  in  pin-plate  forces  due  to  frame  action  of  the  hanger- 
floorbeam  can  be  calculated  in  both  the  simple  truss  or  three-dimensional  models. 

For  the  plane  simple  truss  model,  the  results  of  the  frame  analysis  (Fig.  3) 
can  be  used  to  estimate  the  pin-plate  forces.  Assuming  tliat  both  plates  are  in 
bearing  under  the  hanger  stress  resultants,  the  rotation  of  the  hanger  at  Mi  will 
be  essentially  zero.  The  moment  at  Mi  is  resisted  by  the  couple  17.875  5F  where  5F 
is  the  increment  of  pin-plate  force  in  kips  and  the  distance  between  pin-plates  is 
17.875  in.  Superimposing  this  result  with  the  hanger  axial  force  P  the  individual 
pin-plate  forces  F  can  be  calculated  from, 

F  =  -^-±  0.12P  kips  (3) 

where  the  trackside  pin-plate  will  carry  the  smaller  force. 

The  three-dimensional  model  yields  individual  pin-plate  forces  equal  to: 

F  =  _0:^9P  _^  0.00048P  kips  (4) 

Finite  Element  Analysis  of  Pin-Plate 

To  assist  in  evaluating  the  fatigue  strength  of  the  pin-plates,  a  finite  element 
analysis  was  carried  out.  Since  the  pin-plate  was  essentially  symmetric,  only  one-half 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels  583 

of  the  pin-plate  was  modeled  and  used  for  tlie  finite  element  analysis.  The  finite 
element  model  is  shown  in  Figure  4.  The  loads  showTi  at  the  end  of  the  plate 
provided  an  average  net  section  stress  of  10  ksi.  The  finite  element  program  SAP 
IV  was  used  to  perform   the  finite  element  analyses.    (4) 

The  bearing  of  the  pin-plate  on  the  pin  was  modeled  by  connecting  radial  and 
tangential  elastic  supports  to  nodes  at  the  pin  interface.  The  radial  and  tangential 
support  stiffness   was  taken  as: 

Kr  =  AE/D 

Kt  =  0.3  Kr  (5) 

where  Kr  :=  radial  stiffness,  Kx  =  tangential  stiffness,  A  =  bearing  area,  D  —  pin 
diameter  and  E  =:  modulus  of  elasticity. 

Fig.  5  shows  the  principal  tensile  stress  contour  plot  that  results  when  the 
average  net  section  stress   is   10  ksi.   Only  the  region  near  the  pin  hole  is  shown. 

Since  strain  measurements  were  obtained  on  the  inside  pin-plate  of  tlie  west 
hanger  MiLi,  these  measurements  were  compared  with  the  predicted  strains.  The 
force  going  into  the  pin-plate  was  measured  to  be  about  43  kips.  This  would  result 
in  an  average  net  section  stress  of  5  ksi.  Fig.  6  shows  the  predicted  stress  gradient 
across  the  net  section  and  compares  it  mth  tlie  measured  stresses.  The  results  are 
in  good  agreement. 

Correlation  of  Predicted  Stresses  with  Field  Measurements 

The  results  of  static  load  tests  conducted  by  the  CNR  were  compared  to  tlie 
predicted  stresses  using  the  results  of  the  three-dimensional  model. 

Table  1  shows  the  correlation  in  the  west  hanger  between  predicted  stress,  a^p, 
and  measured  stress,  ff„,,  (ksi).  The  predicted  stresses  are  computed  separately  from 
each  of  the  three  tenns  of  Eq.  2.  The  gages  on  the  west  hanger  were  located  so 
that  the  gross  cross  section  is  effective. 

Table    1      Correlation  of   Predicted  and  Measured   Stresses: 


West 

Hanger  (ksi) 

Major  Axis 

Minor  Axis 

Gages 

Section 

A>:ial  Stress 

Bending  Stress 

Bending  Stress 

O 
0          0               m 
P     m    — 

P 

a 
O            0               rn 
P     m    ^ 
P 

a 
a           o               m 
P      m     — 

P 

2-6  Gross      3.25      3.11      0.96      2.08      2.55      1.22      0.02      0.22      11.0 

7-11  Gross      3.25      3.15     0.97     0.94      2.55      2.71   -0.27     0.22  -0.81 

The  correlation  between  predicted  and  measured  axial  stresses  at  both  cross 
sections  is  quite  good.  Fig.  7  shows  the  measured  and  predicted  axial  force  response 
for  a  portion  of  a  unit  train  which  confirms  tlie  applicability  of  the  spac-e  frame 
analysis. 

Table  1  shows  that  the  correlation  between  predicted  and  measured  major 
and  minor  axis  bending  stresses  at  both  cross  sections  of  the  west  hanger  is  poor. 

Obser\ations  of  strains  in  the  pin-plates  near  Mi  of  the  west  hanger  during 
passage  of  trains  over  the  bridge  indicated  that  the  pin-plates  are  not  both  initially 
in  contact  with  the  pin  at  Mi.  It  was  observed  that  when  the  bridge  was  unloaded 


584 


Bulletin  658 — American  Railway  Engineering  Association 


— 

IX) 

■CO 
N 
3; 

-^ 

-X 

r 

Fig.  4 — Finite   element   model   of   pin-plate. 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels 


585 


Fig.  5 — Principal    tensile    stress    contour    plot    for    pin-plate. 


586 


Bulletin  658 — American  Railway  Engineering  Association 


20 


5    I5|— 
o 

UJ 
V) 

UJ   10  — 


in 

(E 


0  12  3  4  5  6  7 

DISTANCE   FROM    HOLE    EDGE   ,  in. 

Fig.  6 — Comparison  of  predicted  and  measured  stresses  on  net  section  of  pin-plate. 

the  waterside  pin-plate  did  not  bear  on  the  pin.  As  loading  increased  the  trackside 
pin-plate  initially  carried  the  hanger  force  as  shown  in  Fig.  8.  The  exterior  pin-plate 
did  not  bear  until  the  hanger  was  subjected  to  high  loads.  An  analysis  showed  that 
if  the  correlation  at  both  gaged  cross  sections  is  assumed  to  be  unity  in  Table  1, 
this  implies  that  the  axial  force  in  the  west  hanger  is  shared  between  the  trackside 
and  waterside  pin-plates  in  the  ratio  70  to  30  percent,  respectively. 

Table  2  shows  the  correlation  in  the  east  hanger  between  predicted  stress,  <Tp, 
and  measured  stress,  or,,,^  in  ksi,  for  the  same  loading. 


Table   2      Correlation  of  Predicted  and  Measured  Stresses; 


\ 

Avero9«    Ntt    Section  Stress  =  5  ksi 

—        \ 

\^^                      r-Finite  Element  Analysis 

1 

^^"^--....^^#20A 

^^"^"*^-^^_^_^  #21 

i                  1                  1                  1 

#20 

East  Hanger     (v^i^ 

Major  Axis 

Minor  Axis 

Ga^es 

Section        Axial    Stress 

Bending   Stress 

Bending  Stress 

a 
o         o             m 
p          n,          — 

P 

a 
a           a             m 
p             m          — 

P 

a 
o            o                m 
p             m            — 

P 

22-26  Gross      3.25      3.33     1.02      2.08      2.02      0.97      0.02     0.2A     12.0 

27-31  Gross      3.25      3.26     1.00     0.94      1.01      1.07   -0.27      0.22        0.81 


Except  for  the  minor-axis  bending  stresses,  the  correlation  of  axial  stresses  and 
major-axis  bending  stresses  is  quite  good  for  the  east  hanger.  The  latter  indicates 
that  both  pin-plates  at  Mi  are  in  nearly  equal  bearing.  This  condition  was  also 
observed  during  passage  of  trains  over  the  bridge.  Since  the  minor  axis  bending 
stresses   are  low,  correlation   was  not  expected  to  be  good. 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels 


587 


Calrnlated  =  Simple    Truss 
Space  Frame 


UN=X     I  L'NFX  UNPX  lUNPX  100924 


CN5I24  CN5I24  CN  5001 


Fig.  7 — Comparison   of   unit  train  response   with   predicted  axial   strain. 


Trackslde 


-V 


tension 


Waterside 


Fig.  8 — Strain    in    pin-plates    of    west    hanger. 


ESTIMATED  FATIGUE  STRENGTH  OF  RIVETED 
MEMBERS  AND  PIN-PLATES 

Fatigue  Strength  of  Riveted  Members 

Tests  of  riveted  joints  have  demonstrated  that  crack  growth  usually  originates 
at  the  rivet  hole  in  a  region  of  high  stress  concentration  (5).  Almost  all  fatigue 
data  on  riveted  joints  has  been  acquired  on  small  butt  joints  (5),  (6),  (7),  (8), 
(9).  This  work  was  performed  at  the  University  of  Illinois,  Northwestern  University, 
Purdue  University  and  in  Germany.  Investigators  examined  the  influence  of  the 
bearing  ratio,  the  effect  of  rivet  clamping  force,  the  rivet  pattern  and  other  variables. 
Most  of  the  data  was  obtained  from  tests  on  A  7  steel  joints. 

The  test  results  from  all  of  the  available  sources  are  plotted  in  Fig.  9.  The  stress 
range  on  the  net  area  is  plotted  as  a  function  of  cycle  life.  There  is  substantial  scatter 
in  the  test  data  which  mainly  reflects  the  influence  of  clamping  force  and  probable 
variation  in  the  initial  flaw  condition.  When  extreme  bearing  ratios  are  ignored, 
especially   with   reduced   clamping  force,   the   cttcct  of  bearing  does   not  appear  as 


588 


Bulletin  658 — American  Railway  Engineering  Association 


*^  » 

>  fe  S  •"•  '^  ® 

b     _•  I:  OJ  CM   K) 


3      3 

u.  u. 


Ijj 

3 


D    •    o    X    <  -4- 


!«M  '  39NVd  SS3aiS   N0I103S   13N 


Q     O       Q  O 

iS    ^      k5         cm 


Q 

(/) 

UJ 

_l 

w 

o 

V 

a> 

o 

s 

in 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels  589 

critical  a  variable.  The  bearing  ratios  of  2.74  and  3.8  far  exceed  pennissible  and 
recommended  levels.  No  tests  were  included  in  Fig.  9  when  the  specimens  were 
subjected  to  stresses  which  far  exceeded  die  yield  point  on  the  net  section.  In  many 
of  these  tests  when  the  R  ratio  was  taken  as  M,  the  stress  approached  the  tensile 
strength.  As  was  noted  in  Ref.  10,  the  data  from  specimens  that  exceed  the  yield 
point  are  not  representative  of  the  conditions  that  occur  in  actual  stnictures.  Also 
shown  in  Fig.  9  are  recent  tests  on  large  scale  specimens  which  simulated  joints 
in  an  ore  bridge  (11).  The  points  that  are  indicated  as  small  cracks  were  subse- 
quently fitted  with  high-strength  bolts  and  showed  substantial  improvements  in 
fatigue  strength. 

For  design  purposes  the  data  on  riveted  joints  are  compared  with  the  fatigue 
relationship  defined  by  Category  D  of  the  AASHTO  specification  (12).  This  cate- 
gory has  been  used  to  define  the  strength  of  riveted  joints  in  the  design  recom- 
mendations now  being  developed  by  Subcommittee  4,  AREA  Committee  15 — Steel 
Structures.  It  is  visually  evident  that  Category  D  provides  a  lower  confidence  limit 
to  the  available  test  data  on  riveted  joints.  Category  D  will  be  used  in  this  report 
to  define  die  fatigue  behavior  of  the  riveted  memljers  of  the  Fraser  River  Bridge. 

Fatigue  Strength  of  Pin-Plates 

Since  test  data  are  not  available  on  pin-plates,  it  is  necessary  to  estimate  their 
fatigue  strength.  Tlie  fracture  mechanics  approach  to  crack  propagation  is  the  most 
rational  method  currently  available  for  predicting  the  fatigue  life.  It  has  been  used 
to  provide  an  explanation  of  the  fatigue  crack  growth  of  a  number  of  welded  steel 
details  (13),  (14),  (15).  These  studies  have  shown  that  the  crack  growth  rate  of 
structural  steels  can  be  taken  as: 

^^-=  2  X  10-^"  ^r  (6) 


dX 

for  all  details,  where  -^K  is  the  range  of  tlie  stress-intensity  factor  K.  Basic  crack 
growth  studies  have  provided  similar  results. 

To  permit  evaluation  of  the  stress  intensity  factor  on  the  axis  of  the  pin-plate 
holes,  the  finite  element  analysis  was  made  to  define  the  state  of  stress.  The  pin- 
plate  stress  results  showed  that  the  highest  stress  location  is  at  the  surface  of  the 
pin-plate  hole  (see  Fig.  6).  The  stress  gradient  on  the  net  section  of  the  pin-plate 
is  produced  by  the  geometric  condition  of  the  detail  and  its  loading  configuration. 

Closed  form  analytical  solutions  for  K  do  not  exist  for  the  pin-plate  geometry 
showTi.  The  finite  element  solution  showed  the  stress  concentration  eifect  was  4.16 
at  the  hole  edge  and  decayed  rapidly  away  from  the  hole  edge. 

The  stress  field  in  the  plate  near  the  hole  was  observed  to  be  defined  by  the 
stress  concentration  decay  function  defined  in  Ref.  13  for  crack  sizes  less  than  the 
plate  thickness  in  length. 

If  the  stress  distribution  is  given  in  function  form,  die  geometric  correction 
factor  for  the  stress  intensity  factor  can  be  determined  from  the  relationship   (16) 

K  =  V-a^    i         ^-—-  (7) 

This  is  similar  to  the  influence  function  method  used  in  Ref.  17.  The  redistribution 
of  the  non-uniform  stress  field  is  accounted  for  as  a  crack  grows.  This  yields  a 
relationship  Fg  equal  to 


590 


Bulletin  658 — American  Railway  Engineering  Association 


40 
30 

'■20  — 


h-   10- 


1     '   1   /I/I 

y-Oj  =  0.002" 

^01  =  0.004" 
Ji^^^       ^a\  =  0.010" 

.  o 

1     1    1  1  1 

\                                                                                        ^^^"^^-..^ 

1                  ,           .       1      1     1    1   1  1  1                  1           1       1      1     1    1  1  il 

10= 


10* 


CYCLE     LIFE 
Fig.  10 — ^Predicted    fatigue    strength   of   pin-plates. 


10^ 


Fo  =  4.16  j    1  _  3.215  (4)1  +  X  ^'-'''^  (1)^     - 

Hence,  the  stress  intensity  factor  for  the  pin-plate  is  given  by 

K  z=  Fg  q  or  V"^  (9) 

where  q  is  a  crack  shape  factor  that  varies  from  2/t  to  1.  For  the  pin-plates  being 
examined,  the  holes  were  drilled  and  hence  tlie  initial  flaw  condition  expected  at 
such  a  hole  should  not  exceed  the  small  discontinuities  expected  at  such  edges 
(i.e.,  0.001  to  0.004  in.). 

The  stress  range-cycle  life  relationship  for  the  pin-plates  was  estimated  from 
Eqs.  5  and  8.  The  results  of  this  evaluation  are  plotted  in  Fig.  10  and  compared 
with  fatigue  strength  Categories  D  and  E  (12).  Fig.  10  shows  that  for  the  expected 
comer  crack  at  the  hole  edge  (q  v— ,  2/7r),  the  fatigue  strength  of  tlie  pin-plate 
is  between  Category  D  and  E.  Since  the  crack  shape  factor  q  may  be  shghtly 
greater  than  2/t,  it  appears  reasonable  to  use  Category  E  to  define  tlie  fatigue 
strength  of  the  pin-plates.  This  would  also  allow  for  an  above-average-size  initial 
discontinuity  at  the  hole  edge   (up  to  0.010  in.). 

EVALUATION  OF  FATIGUE  DAMAGE 

The  predicted  nominal  forces  in  the  hanger  for  the  random  load  spectrum 
defined  by  Sweeney  in  Ref.  1  was  used  to  estimate  the  cumulative  damage  in  the 
hanger  and  pin-plates  of  the  380-ft  fixed  span.  The  experimental  studies  carried  out 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels  591 

by  CN  Research  showed  tliat  tlie  structure  was  acting  more  nearly  like  a  space 
frame  than  a  pin-ended  truss  structure  ( see  Fig.  7 ) .  However,  measurements  under 
static  loading  indicated  some  variability  depending  on  the  location  of  the  test  load. 
It  appeared  that  the  full  stringer  continuity  was  not  always  available.  The  analysis 
indicated  that  the  predicted  nominal  axial  forces  assuming  plane  simple  truss 
behavior  should  be  adjusted  by  a  factor  of  0.82  to  reflect  the  joint  fixity  of  the  truss 
and  the  continuity  of  the  stringers. 

An  impact  factor  of  1.054  was  applied  to  the  predicted  hanger  forces  to  account 
for  uncertainties  in  the  analysis,  provide  a  margin  for  unaccounted  variables,  and 
because   impact   effects   were  filtered  out  above   10   to   14   Hz. 

Estimated  Damage  in  Hanger  MXi 

Since  the  floorbeam  hanger  connections  had  been  strengthened  in  1923  by  the 
removal  of  the  hanger  lacing  and  the  addition  of  a  solid  web  plate  and  spfice  plates, 
it  was  necessary  to  examine  the  hanger  at  two  locations.  At  the  hanger-floorbeam 
connection,  the  gross  section  was  provided  by  four  angles  6  x  3/2  x  %,  two  plates 
16/2  x  %,  one  plate  10^  x  %  and  one  plate  10^  x  11/16  in.  This  provided  much  higher 
cross-section  area  and  moments  of  inertia  Ixx  and  lyy  at  the  hanger  section  sub- 
jected to  tlie  largest  moments  from  floorbeam  end  rotation  and  twist. 

The  space  frame  analysis  indicated  that  the  highest  stressed  cross-section  in 
the  hanger  MiLi  at  the  floorbeam-hanger  connection  is  located  just  at  the  hanger 
web  splice  where  five  rivet  holes  occur.  Using  net  section  properties,  the  critical 
stress  range  at  the  most  highly  stressed  rivet  hole  was  derived  from  Eq.  2.  The 
coefficient  for  weak  axis  bending  was  increased  to  reflect  the  actual  measured 
response  at  the  hanger  connection.  Variability  in  stringer  continuity  is  believed  to 
be  the  cause  for  the  variation  in  strain  across  the  inside  face  of  the  hanger. 

,  _    0.82  P        35.00  P        0.80  P        ^  nft^^'^R  p  nn^ 

+        mnn        +        ,.0       =   0.06536   P  (  10) 


29.42  '  1099  '  143 
where  P  is  the  force  assuming  plane  truss  behavior  defined  in  Chapter  HI  of  Ref.  1. 
Both  the  RMS  and  Miners  equivalent  force  range  were  evaluated  and  found  to 
be  less  than  2%  different.  These  values  are  summarized  in  Table  3. 


Table 

3  Nomiaal 

Hanger  Fore 

e* 

Time  Interval 

No.  of  Cycles 

p 
RMS 

^MINER 

up  to  1973 

2,217,810 

71.7 

kips 

73.4  kips 

up  to  1980 

4,183,600 

74.7 

75.9 

up  to  1985 

5,839,350 

75.3 

76.3 

up  to  1990 

7,A95,100 

75.6 

76.6 

*Assuraing   plane   sinple   truss   behavior;    see   Reference   1   for  detailed 
description  of    load  spectrun 

The  coefficients  in  Eq.  10  have  been  adjusted  to  account  for  space  frame 
behavior.  The  resulting  efi^ective  stress  ranges  at  the  hanger-floorbeam  connection, 
including  the  impact  factor  1.054,  are  shown  in  Fig.  11  and  compared  with  Gate- 


592 


Bulletin  658 — .\ineiican  Railway  Engineering  Association 


(A 

w 
O 
Q> 

>» 

in 

CM 


10  — 


tf> 


o 

z 
< 

in 
ifi 

Ld 

q: 


5- 


-^ 

L 

— 

1973  • 

1 

1980  •©          A 

A^Cat.  D 

*** 

2>    5?     g 

• 

Hanger  at  floor  beam  connection 

0 

Hanger  at  most 

critical  section 

A. 

Stringers  -  25  years    old 

1 

1            1        t 

1     ■     1    1   1  1                    1 

2- 


10' 


10^ 


Fig.  11 — Comparison  of  effective  stress  range  in  hanger  and  stringers  of  380-ft  fixed 
span  with  fatigue   strength  of  riveted  joints.   (See  Fig.   12  for  pin-plates.) 


gory  D.   It  is  readily  apparent  that  no  difficulty  should  be  encountered  with  the 
hanger  near  the  floorbeam  until  after  2000. 

Under  nonnal  circumstances  the  moment  along  the  hanger  lengtii  would  be 
expected  to  vary  from  a  maximum  at  tlie  hanger-floorbeam  connection  to  a  minimum 
at  the  pin-plate  end.  This  was  observed  for  the  east  hanger  but  was  not  the  case 
at  the  west  hanger.  The  field  measurements  showed  that  the  west  hanger  pin-plates 
were  not  carrying  the  same  load.  Initially  only  the  inside  pin-plate  was  in  bearing. 
The  outside  pin-plate  picked  up  load  only  after  it  seated  and  came  into  bearing 
(see  Fig.  8).  This  end  eccentricity  meant  that  the  moment  along  the  west  hanger 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels  593 

length  was  nearly  constant.  The  moment  about  tlie  hanger  weak  axis  was  very 
small  away  from  the  hanger-floorbeam  connection  and  was  ignored. 

The  most  highly  stressed  rivet  hole  was  at  the  angle-web  connection.  The 
stress  at  tliis  location  is  given  by 

„_    0.82  P         3.916  X  8.148  P_  ,      . 

~     20.39    +  1073  -  ""^^  ^  ^    ^ 

The  effective  stress  ranges  adjusted  for  an  impact  factor  of  1.054  are  also 
plotted  in  Fig.  11.  The  results  demonstrate  tliat  hanger  MiLi  is  not  in  danger  of 
failure  before  the  year  2000.  Since  the  unequal  distribution  of  load  in  the  pin-plates 
was  most  severe  in  the  west  hanger,  it  represents  the  worst  condition. 

Estimated  Damage  in  Pin-Plates   (MXi) 

The  maximum  expected  force  to  be  carried  by  the  most  highly  stressed  pin- 
plate  was  40  to  50%  of  the  nominal  hanger  force.  However,  field  measurements 
demonstrated  clearly  that  the  pin-plates  of  the  west  hanger  were  not  sharing  the 
load  as  expected  (see  Fig.  8).  As  a  result,  the  inside  pin-plate  was  observed  to 
carry  73.5%  of  the  load.  Hence  for  purposes  of  evaluation,  the  effective  force  acting 
on  the  most  highly  loaded  pin  was 

P  ^  0.735  X   1.054  X  0.82  P  —  0.635  P  (12) 

where  P  is  defined  in  Table  3.  Since  the  net  .section  area  was  used  to  define  the 
details  fatigue  strength  (see  Fig.  10)  the  resulting  nominal  net  section  stress  on 
the  pin-plate  is  P/8.656. 

These  results  are  plotted  in  Fig.  12  and  compared  with  Category  E.  This 
shows  that  a  critical  condition  develops  as  1985  is  approached.  The  probability 
for  failure  of  this  highly  stressed  pin-plate  is  great  thereafter.  Since  the  design  line 
is  based  on  the  lower  bound  fatigue  strength,  failure  will  depend  greatly  on  the 
condition  of  the  pin-plate.  When  the  pin  plates  are  sharing  the  load  about  equally 
as  was  the  case  for  the  east  hanger,  the  effective  force  is  P  —  0.44P.  This  results 
in  effective  stress  ranges  between  3.7  and  4  ksi  as  shown  in  Fig.  12.  This  shows 
that  the  fatigue  strength  of  the  east  hanger  pin-plates  are  adequate  well  beyond 
the  year  2000. 

Estimated  Damage  in  Stringers 

Strain  measurements  were  made  near  midspan  on  a  bottom  flange  angle  of  the 
west  stringer  between  LiL-.  These  measurements  confirmed  that  the  stiinger  was 
subjected  to  some  strain  reversal  and  acted  with  some  degree  of  continuity.  An 
examination  of  the  strain  response  indicated  that  the  stringer  was  subjected  to  about 
the  same  number  of  stress  cycles  as  was  experienced  by  the  hanger  MiLj.  Fig.  13 
shows  the  measured  stress  spectrum  which  was  used  to  assess  the  fatigue  resistance 
of  the  stringers.  This  results  in  measured  effective  stress  ranges  of  S,i!.m.s  =  7.43 
ksi  and  S,.mim:r  =  7.54  ksi. 

These  measured  values  of  effective  stress  range  were  made  on  the  top  surface 
of  the  bottom  flange  angle.  When  adjusted  to  the  bottom  edge  of  the  rivet  holes  at 
tlie  web-angle  connection,  which  is  the  critical  location,  these  stress  ranges  are 
reduced  by  about  8%.  However,  the  stress  range  should  be  increased  by  several 
other  factors  when  estimating  damage  over  the  full  life  of  the  structure.  Since  the 
records  were  filtered  for  roll-oft'  frequencies  above  10  to  14  Hz,  the  full  effect  of 
impact  was  not  taken  into  account.  Records  were  acquired  with  the  filters  removed 


594 


Bulletin  658 — American  Railway  Engineering  Association 


Cat.    E 


•    Pin  Plate    M, L|   (west) 
o    Pin  Plate     M,  L,    (east) 

I I I I l—L 


J I I I I l_ 


I0« 


4        S      6     7 


10' 


10" 


CUMULATIVE     CYCLE    LIFE 

Fig.  12 — Comparison  of  effective  stress  range  in  pin-plates  with  their 
predicted  fatigue  strength. 


0.5- 


0.4- 


>- 
t 
en 

iiJ    0.3 
o 

>■ 


g    0.2 

CD 
O 

q: 

Q. 


0.1 


ro 


K 

to 


J2 


tm 


6  7  8  9  10 

STRESS  range;  Ksi 
Fig.  13 — Measured   stress   distribution  in  the   stringers. 


Report  by  John  W.  Fisher,  J.  Hartley  Daniels  595 

and  suggest  that  higher  peak  stresses  were  probable.  Based  on  the  relative  differ- 
ence between  the  response,  a  factor  of  1.04  appears  appropriate.  The  second  factor 
is  the  underloading  that  was  observed  for  the  unit  trains  of  the  T  and  S  series. 
These  suggested  a  correction  of  1.085  should  be  applied  to  the  strain  cycles  of  unit- 
train  car  loading.  The  other  trains  crossing  the  bridge  were  not  affected.  This  was 
found  to  increase  the  effective  stress  range  by  a  factor  of  1.035. 

One  other  factor  should  be  considered  when  estimating  fatigue  damage  in 
the  stringers.  The  measured  strains  were  obtained  for  the  gross  section.  To  adjust 
to  the  net  section  stress,  an  additional  increase  of  10%  is  necessary. 

As  a  result  of  the  adjustments  for  the  point  of  crack  initiation,  maximum 
moment,  greater  impact  and  heavier  axle  loads,  tlie  adjusted  values  of  effective 
stress  range  are  increased  by  1.04  X  1035  X  1-10  H-  1.08  ^  1.10.  Hence  the 
effective  stress  range  becomes:  Sihms  =  8.17  ksi  and  S,. miner  =  8.29  ksi.  These 
\'alues  are  also  plotted  in  Fig.  11.  This  shows  that  fatigue  cracking  could  be 
expected  in   the  stringers   about   1979. 

Since  the  stringers  are  predicted  to  reach  their  lower  bound  fatigue  strength 
in  1979  it  is  appropriate  to  discuss  the  significance  of  this  observation.  This  does 
not  mean  that  large  numbers  of  stringers  will  immediately  crack.  The  lower  bound 
fatigue  strength  defines  the  worst  condition.  As  the  fatigue  test  data  plotted  in 
Fig.  9  shows,  large  variation  in  life  can  be  expected.  Also,  since  tlie  riveted  stringers 
have  two  tension  flange  angles  and  a  web  plate,  failure  of  one  element  will  not 
result  in  immediate  collapse  of  the  member.  It  should  be  possible  to  detect  a  failed 
component  before  a  severe  collapse  occurs. 

SUMMARY  AND  CONCLUSIONS 

An  analysis  of  tlie  most  highly  stressed  hangers  and  the  stringers  of  the  main 
380-ft  fixed  span  of  the  Fraser  River  Bridge  has  indicated  that  fatigue  cracking  can 
be  expected.  The  stringers  were  predicted  to  reach  their  lower  bound  fatigue 
strength  in  1979  based  on  the  traffic  defined  by  Sweeney  in  Ref.  1.  The  hanger  pin- 
plates  which  had  unequal  distribution  of  load  were  predicted  to  reach  their  lower 
bound  fatigue  strength  in  1985.  The  RMS  and  Miners  rule  assessment  of  fatigue 
damage  provided  comparable   results. 

The  method  used  to  assess  tlie  fatigue  damage  in  the  hangers  and  stringers  of 
the  Fraser  River  Bridge  can  be  used  on  other  bridge  structures  as  well.  The  frequency 
and  magnitude  of  force  or  moment  can  be  estimated  from  traffic  using  the  structure. 
Only  cars  80  tons  or  heavier  and  locomotives  will  normally  need  to  be  considered 
on  comparable  structures.  The  effect  of  lighter  cars  should  be  examined  on  weaker 
structures. 

In  order  to  accurately  assess  die  significance  of  the  applied  loads,  a  space 
frame  analysis  will  normally  be  required  for  all  structures.  The  behavior  of  truss 
spans  can  range  from  plane  truss  to  space  frame  behavior  with  full  continuity. 
Hence  only  field  measurements  of  tlie  stress  in  critical  components  can  determine 
the  actual  behavior  and  the  applicable  analysis.  In  the  case  of  the  hangers  of  the 
Fraser  River  Bridge  this  was  found  to  make  a  15  to  20%  difference  in  the  actual 
stress  range.  In  fatigue  life  evaluation,  a  10%  variation  in  stress  range  can  mean  a 
36%  variation  in  permissible  stress  range  cycles.  For  the  Fraser  River  Bridge  this 
means  a  difference  in  life  of  about  six  years  at  the  current  rate  of  loading. 

Care  should  be  exercised  in  evaluating  tlie  fatigue  damage  of  hanger  connections 
at  Hoorbeams.   Here  the  high  bending  stresses  from  the  end  rotation  and  twist  of 


596  Bulletin  658 — American  Railway  Engineering  Association 

the  floorbeani  must  he  properly  assessed.  These  stresses  arc  particularly  sensitive 
to  stiffness  and  geometry  of  the  connection.  Care  should  also  be  taken  when  inter- 
preting field  measurements.  The  possibility  for  unequal  distribution  of  force  to 
various  components  as  was  the  case  with  the  pin-plates  on  the  west  hanger  MiLi, 
should  be  carefully  examined. 

ACKNOWLEDGEMENTS 

The  authors  would  like  to  acknowledge  the  assistance  provided  throughout  this 
study  by  various  staff  members  of  the  Canadian  National  Railways. 

Thanks  are  due  to  Z.  L.  Szeliski,  engineer  of  bridges  and  structures,  for  his 
assistance  and  suggestions.  R.  A.  P.  Sweeney,  structural  engineer,  provided  invalu- 
able assistance  at  all  stages,  including  the  field  inspection,  acquisition  of  the  field 
test  data,   and  assistance  with  the  data  analysis. 

The  strain  gage  test  series  were  carried  out  under  tlie  supervision  of  Dr.  W.  N. 
Caldwell,  senior  research  engineer,  and  J.  F.  Scott,  research  engineer.  This  included 
the  pilot  studies  carried  out  by  Dr.  Caldwell  and  Mr.  Sweeney  and  the  more 
extensive  measurement  acquired  by  R.  M.  Hardy  and  Associates,  Ltd.  under  die 
supervision  of  Mr.   Scott. 

REFERENCES 

1.  R.  A.  P.  Sweeney,  "Load  Spectrum  for  Eraser  River  Bridge  at  New  Westminster, 
B.C.,"  Proceedings  AREA,  Vol.  77,  1976. 

2.  Association  of  American  Railroads,  "Field  Investigation  of  Two  Truss  Spans 
on  the  Southern  Pacific  Company,"  May  1968,  Report  ER-82,  AAR  Research 
Center,  Chicago. 

3.  James  Michalos  and  J.  M.  Louw,  "Properties  for  Numerical  Analyses  of  Gusseted 
Frameworks,"  Proceedings,  AREA,  Vol.  58,  p.  7. 

4.  K.  J.  Bathe,  E.  L.  Wilson  and  F.  E.  Peterson,  "SAP  IV — A  Structural  Analysis 
Program  for  Static  and  Dynamic  Response  of  Linear  Systems,"  Report  EERC 
73-11,  Earthquake  Engineering  Research  Center,  University  of  California  at 
Berkeley,  June  1973,  Rev.  April  1974. 

5.  J.  F.  Parola,  E.  Chesson,  Jr.  and  W.  H.  Munse,  "Effect  of  Bearing  Pressure 
on  Fatigue  Strength  of  Riveted  Connections,"  Bulletin  481,  Engr.  Exp.  Station, 
Univ.  of  Illinois,  Vol.  63,  No.  27,  Oct.   1965. 

6.  K.  H.  Lenzen,  "The  Effect  of  Various  Fasteners  on  the  Fatigue  Strength  of  a 
Structural  Joint,"  AREA  Bulletin  481,  Vol.  51,  June-July  1949. 

7.  W.  M.  Wilson  and  F.  P.  Thomas,  "Fatigue  Tests  of  Riveted  Joints,"  Bulletin 
302,  Univ.  of  111.,  1938. 

8.  F.  Baron  and  E.  W.  Larson,  Jr.,  "The  Effect  of  Grip  upon  Fatigue  Strength 
of  Riveted  and  Bolted  Joints,"  2nd  Progress  Report,  Proj.  5,  Nortihwestern  Univ., 
1951. 

9.  F.  Baron,  E.  W.  Larson,  Jr.,  and  K.  J.  Kenworthy,  "The  Effect  of  Rivet  Pattern 
on  the  Fatigue  Strength  of  Structural  Joints,"  Prog.  Report  Proj.  6  and  7,  North- 
western Univ.,    1953. 

10.  J.   W.   Fisher  and  J.   H.   A.   Struik,  "Guide  to  Design  Criteria  for  Bolted  and 
Riveted  Joints,"  Wiley  Interscience,   1974, 

11.  H.  S.  Reemsnyder,  "Fatigue  Life  Extension  of  Riveted  Structural  Connections," 
Journal  of  the  Structural  Division,  Vol.  101,  ST  12,  Dec.  1975, 


Report  by  John  W.   Fisher,  J.   Hartley  Daniels 597 

12.  AASHTO,   1974  Interim  AASHTO  Specifications,  Art.   1.7.3. 

13.  J.  W.  Fisher,  P.  A.  Albrecht,  B.  T.  Yen,  D.  J.  Klingerman  and  B.  M.  McNamee, 
"Fatigue  Strength  of  Steel  Beams  with  Transverse  StifFeners  and  Attachments," 
NCHRP  Report   147,  Transportation  Research  Board,   1974. 

14.  M.  A.  Hirt  and  J.  W.  Fisher,  "Fatigue  Crack  Growth  in  Welded  Beams,"  Engi- 
neering Fracture  Mechanics,   \'ol.  5,   1973. 

15.  S.  J.  Maddox,  "Assessing  the  Significance  of  Flaws  in  Welds  Subject  to  Fatigue," 
Welding   Research   Supplement,   September   1974,   \'ol.   53,    No.   9. 

16.  P.  Albrecht  and  K.  Yamada,  "Rapid  Calculation  of  Stress  Intensity  Factors," 
paper  submitted  for  publication  in  the  Journal  of  the  Structural  Division,  ASCE, 
1975. 

17.  T.  A.  Cruse  and  P.  M.  Besumer,  "Residual  Life  Prediction  for  Surface  Cracks 
in  Complex  Structural  Details,"  Journal  of  Aircraft,  Vo}.  12,  No.  4,  pp.  369- 
375,  April  1975. 


Data  Bases:   Help  or  Harassment  for 
Engineering  Management 

77-658-7 

By  CHARLES  F.  WIZA 

Production    Control    Engineer 
Illinois    Central    Gulf    Railroad 

\\Tiat  would  happen  if  upon  your  return  to  your  respective  offices  you  would 
find  a  Federal  Railroad  Administration  official,  and  he  said  that  by  tomorrow  he 
needs  to  know:  How  many  ties  did  you  install  on  line  segment  A  in  tlie  last  five 
years? 

Your  responses  would  probably  fall  into  three  basic  categories.  First,  total  chaos 
— ha\ing  \ery  little  ability  to  recount  tie  installation  information.  Second,  controlled 
chaos — sending  a  task  force  pouring  through  manual  records  to  find  the  tie  installa- 
tion information.  And  third — a  relaxed  attitude  for  sure — we'll  punch  that  request 
right  into  our  black  box  known  as  a  computer,  watch  tlie  lights  blink  awhile,  and 
have  the  results  first  thing  in  tlie  morning. 

This  last  response  is  the  one  I  am  here  to  discuss  today — Data  Bases:  Help, 
or  Harassment  for  Engineering  Management.  Hopefully,  you  will  see  that  they  are 
a  help  and  will  be  using  this  concept  in  the  future. 

First,  what  is  a  data  base?  Simply  put,  it  is  an  inventory  of  information.  This 
infomiation  can  be  stored  as  simply  as  on  index  cards,  more  sophisticatedly  on 
punched  cards  for  mechanical  sorting,  or  in  computers  for  electionic  data  processing. 

Although  the  temi  "data  base"  may  be  new,  the  concept  certainly  is  not.  Bridge 
lists  and  track  profiles  have  been  in  existence  as  long  as  railroads.  Mechanized  data 
bases  arrived  in  the  early  1960's  when  se\'eral  roads  computerized  their  work  equip- 
ment imentories.  Presentations  at  previous  Technical  Conferences  have  dealt  with 
indi\idual   data  bases,   specifically   structures   inventories. 

Why  the  big  push  for  data  bases  now?  There  are  two  big  reasons:  First,  the 
needs  of  railroads,  and  of  engineering  departments  have  changed.  No  longer  are 
vast  sums  of  money  axailable  for  maintenance  and  improvements.  Today's  economic 


Note:    Discussion  open  until  October  15,   1976. 


598  Bulletin  658 — American  Railway  Engineering  Association 

conditions  dictate  that  the  greatest  possible  rate  of  return  be  attained  for  the  main- 
tenance dollar.  The  information  in  data  bases  can  provide  quantifiable  answers  for 
maintenance    planning,    increase    productivity,   and    optimize    equipment    utilization. 

Second,  as  far  as  data  bases  are  concerned,  the  wheel  has  been  invented.  Much 
like  pocket  calculators,  their  availability  has  increased  while  costs  have  decreased. 
Each  road  need  not  go  off  independently  trying  to  blaze  a  new  trail.  Some  railroads, 
as  well  as  commercial  concerns,  have  already  swept  a  fairly  wide  path  in  the  con- 
cepts, designs  and  implementation  of  data  bases.  With  the  advent  of  this  technology 
more  and  more  people  in  all  levels  of  management  are  realizing  the  need  for  fast, 
accurate   data   retrieval   and  manipulation. 

What  then  is  tlie  state  of  the  art  of  data  bases  with  respect  to  maintenance  of 
way,  and  more  important,  what  are  the  benefits  of  such  data  bases? 

One  road  maintains  a  partial  rail  inventory  of  its  traditional  new  rail  territory 
— those  h-acks  having  the  highest  traffic  densities,  carrying  the  most  profitable 
commodities,  and  being  located  in  the  most  severe  curvature /gradient  terrain.  This 
inventory  is  used  to  determine  the  priority  of  rail  replacement  and  to  select  the 
most  economical  rail  type. 

An  extension  of  this  limited  rail  inventory  is  exhibited  by  another  road  which 
inventories  all  rail  and  turnouts,  including  main  line,  branch  line,  industry  spurs, 
and  yard  tracks.  In  addition  to  the  rail  data,  information  regarding  surfacing,  tie 
installation,  rail  testing,  and  weed  spraying  is  being  collected.  When  completed, 
tliis  data  base  will  provide  a  basic  track  characteristics  file  \^'hich  will  greatly  aid 
in  developing  all  rencwel  and  maintenance  programs. 

These  two  cases  are  examples  of  independent  data  bases  which  are  very  fine 
for  particular  data  recall.  They  fit  in  very  well  for  line  segment  analysis  where  the 
question  to  be  answered  is  "What  do  we  have  out  there?"  Instead  of  paging  through 
rail  charts  and  condensed  profiles  to  manually  retrieve  the  desired  information,  the 
data  could  be  obtained  much  quicker  and  more  accurately  if  a  computerized  data 
base  were  available. 

Now  suppose  upon  returning  to  your  office,  you  find  that  your  budget  for  the 
remainder  of  the  year  was  being  reduced  by  20  percent.  The  question  now  is  not 
only  one  of  data  recall — what  do  I  have  that  needs  to  be  replaced,  but  what  are 
the  benefits — which  lines  have  the  greatest  traffic  density  and  must  be  maintained, 
and  where  can  money  be  saved  by  reducing  derailments? 

What  you  need  now  is  an  integrated  data  base  system;  that  is,  for  each  segment 
not  only  is  engineering  information  needed,  but  operating  and  traffic  data  as  well. 
One  road  has  taken  a  step  forward  in  data  base  development  and  installed  such  a 
system.  For  each  milepost,  six  independent  inventories  or  files,  dealing  with  track 
characteristics,  derailments,  track  defects,  bridges,  track  profiles  and  traffic  densities 
are  kept  up.  By  being  able  to  concurrently  search  each  file  for  certain  characteristics 
or  milepost  information,  much  more  data  are  available  at  a  single  time  and  much 
"cross-indexing"  can  be  done. 

The  benefits  of  such  an  integrated  system  are  very  great.  The  previous  question 
can  be  quantifiably  answered.  Quickly  and  accurately,  the  exact  location  of  sub- 
standard track  sections  can  be  pinpointed  on  the  most  economically  justifiable  line 
segments.   From  this  listing,  repair  priorities  can  be  set. 

Such  an  integrated  data  base  system  also  embraces  research  for  behavioral 
patterns.  Example,  rail  wear  can  be  pinpointed  as  to  curve,  grade,  traffic  density, 
and  tie  and  surface  conditions. 


Address  by  Charles  F.  Wiza  599 

The  track  characteristic  file  points  out  another  new  tool  in  information  process- 
ing— that  of  the  track  geometry  car.  Such  cars,  now  in  use  on  several  different 
roads,  pro\  ide  information  on  such  things  as  cross  level,  surface,  gauge  and  align- 
ment, thus  pro\  iding  an  excellent  condition  inventory  of  the  property.  This  condition 
in\entory  is  a  must,  since  it  is  of  litde  use  to  know  exactly  what  is  sitting  out  there 
without  knowing  what  condition  it  is  in. 

One  further  extension  of  tlie  integrated  data  base  concept  is  currently  being 
developed.  Under  this  system,  a  mile-by-mile  record  of  physical  characteristics  and 
descriptions  will  be  built  plus  a  similar  record  of  dollar  accounting  information. 
This  system  will  be  dri\en  by  a  single,  all-purpose  reporting  form  which  will  provide 
all  the  necessary  engineering  and  expense  data. 

Existing  data  bases  are  exclusively  by  and  for  maintenance  of  way  departments. 
They  are  maintained  through  separate  engineering  department  fomis  with  other 
paperwork  being  necessary  to  maintain  accounting  department  needs. 

There  are  many  testimonials  and  bouquets  for  data  bases  and  data  processing 
in  general,  some  of  which  already  have  been  alluded  to.  More  and  more  are  forth- 
coming every  day,  especially  from  the  Northeast  Conidor.  Existing  data  bases  are 
providing  infomiation  and  answers  to  questions  which  would  take  many  man-mondis 
to  otherwise  research.  If  these  data  were  not  readily  accessible,  I  shudder  to  think 
where  that  problem  would  be  now. 

So  far  I  have  shown  what  data  bases  are  and  can  do.  They  are  and  can  be  a 
tremendous  help,  only  if  properly  designed,  implemented,  and  maintained.  If  not 
so,  they  can  indeed  be  a  harassment. 

There  are  several  ground  rules  which  must  be  laid  down  before  any  system 
can  be  designed.  First,  there  must  be  a  definite  commitment  from  management  for 
such  a  system.  This  means  you.  You  must  want  the  system,  use  it  and  ensure  that 
it  is  properly  maintained.  If  \ou  are  not  enthusiastic  about  it  and  do  not  instill 
this  feehng  to  your  subordinates,  then  regardless  of  how  technically  sound  the 
system  is,  it  will  falter  and  become  another  white  elephant. 

The  second  ground  rule  is  to  make  sure  of  a  definite  purpose  or  intent  in  tlie 
design  of  the  system.  Information  must  be  provided  to  meet  specific  ends  such  as 
to  prevent  derailments,  minimize  slow  orders,  or  provide  a  satisfactory  quality  of 
ride. 

With  these  ground  rules  met,  what  next?  There  are  three  things  to  consider: 
what  type  of  data  is  needed,  how  to  obtain  it,  and  how  to  design  and  maintain 
the  data  base  to  ensure  current,  accurate  data  at  minimum  cost. 

Decisions  as  to  the  types  of  data  to  be  contained  in  the  data  base  must  be  made 
by  you,  those  directly  concerned.  There  is  no  golden  rule,  nor  necessarily  rule  of 
diumb  for  the  data  base  contents.  Each  one  can  be  custom-made  to  the  user's 
purposes. 

There  are  several  schemes  available  for  obtaining  the  necessary  physical  infor- 
mation. The  most  precise,  but  most  costly  and  time  consuming  way  would  be  to 
physically  inventory  the  property.  The  most  practical  and  economical  way  is  to 
transcribe  as  much  existing  data  as  possible.  It  is  amazing  how  much  information 
will  already  be  available  from  condensed  profiles,  bridge  lists,  signal  lists  and  the 
like.  Once  the  transcription  is  complete,  it  can  be  field  verified,  and  any  incorrect 
or  missing  information  compiled.  Another  approach  is  to  estabhsh  a  bench  mark 
work  date,  start  from  zero,  and  proceed  to  build  the  data  base  as  material  is  installed. 


600  Bulletin  658 — American  Railway  Engineering  Association 

Besides  defining  and  initializing  die  data  base,  some  consideration  must  be 
given  to  die  retrieval  and  manipulation  routines  necessary  to  fully  utilize  the  systems. 
These  routines  can  be  custom-built,  as  has  been  the  case  in  most  instances,  or  a 
"canned"  report  generating  system  could  be  installed  to  produce  tlie  desired  outputs. 

Maintaining  the  system  is  a  must.  The  railroad  is  a  dynamic  entity  and  die  data 
base  must  reflect  these  changes.  After  all,  how  good  is  a  month-old  newspaper.  The 
key  to  the  maintenance  of  the  data  base  is  the  source  document,  ideally  one  all- 
purpose  fomi  to  provide  engineering  and  accounting  data.  Regardless  if  multiple 
forms  are  used,  they  shovdd  be  simple,  straightforward,  with  as  much  pre-printed 
data  as  possible.  Such  forms  reduce  paperwork  and  provide  one  set  of  figures  for 
purposes  of  maintenance  planning  and  expense  monitoring.  It  must  be  remembered 
diat  diese  source  documents  are  not  meant  to  be  harassments,  rather  means  to  ob- 
taining the  required  answers  for  management  questions. 

Today  I  have  attempted  to  whet  your  whistle  so-to-speak  for  data  bases  and 
tried  to  show  that  the  information  explosion  should  be  a  help,  not  a  harassment 
to  engineering  management.  I  have  been  fortunate  in  that  I  have  been  able  to  visit 
some  of  the  various  railroads  throughout  this  continent  and  observe  what  they  are 
doing  \vitii  regard  to  infonnation  processing.  When  I  graduated  from  college  a 
handful  of  years  ago,  I  thought  that  I  had  a  prety  good  appreciation  for  what  a 
computer  could  do  in  terms  of  pure  "number  cnmching."  Here,  I  hope  I  have 
conveyed  the  added  appreciation  I  have  recently  learned  for  data  base  processing. 

I  am  by  no  means  an  expert  in  the  field  of  data  bases  nor  maintenance  of  way. 
The  Board  of  Direction  of  the  AREA  has  charged  Committee  32 — Systems  Engi- 
neering, widi  presenting  a  symposium  on  data  bases  for  maintenance  of  way.  This 
symposium  tentatively  scheduled  to  be  held  along  with  the  Regional  Meeting  m 
Pittsburgh  this  fall,  will  be  given  by  the  experts  in  railroad  engineering  data  bases. 
Within  the  next  few  days,  each  chief  engineer  will  receive  a  letter  informing  him 
of  Committee  32's  intentions  for  the  symposium,  and  requesting  comments.  I  hope 
you  will  support  the  idea,  and  that  you  will  attend  the  symposium.  See  you  there. 


Rail  Wear  and  Corrugation  Studies 

77-658-B 

By 
F.   E.   KING 

Senior   Technical    Advisor 
Canadian    National    Railways 

and 

J.   KALOUSEK 

Research    Engineer 
Canadian   Pacific   Rail 

These  are  case  shidies  of  rail  wear  problems  occurring  on  two  Canadian  railways' 
main  lines  in  the  Rocky  Mountains.  The  problem  arose  about  1969  with  the  intro- 
duction of  unit  trains  for  hauling  coal,  potash  and  sulfur.  These  unit  trains  consisted 
of  identical,  full\-  loaded  100-ton-capacity  \ehicles  having  a  gross  weight  on  rail 
of  263,000  lb. 

Table  I  shows  for  the  Canadian  National  Railways'  line  a  traffic  split  by  vehicle 
type,  excluding  tonnage  generated  by  empty  cars,  passenger  trains,  and  locomotives. 
Note  that  on  the  average  100-ton  cars  are  loaded  to  94%  of  their  rated  capacity, 
while  50-  and  70-ton  cars  are  loaded  to  74%  of  their  rated  capacity. 

Fig.  1  shows  a  frequency  histogram  of  gross  car  weights  tlirough  a  section 
of  Canadian  Pacific  Rail  line.  Note  that  the  heaxy  loaded  movement  is  in  the  west- 
ward direction  and  is  in  die  130-140  ton  range.  The  column  in  the  20-30  ton  range 
shows  tliat  empty  car  return  mo\ement  is  in  the  eastbound  direction.  The  inter- 
mediate columns  represent  mixed  freight. 

In  the  mountainous  territory  sharp  curves  are  frequently  encountered.  The 
combination  of  heavy  vehicles,  large  annual  tonnages  and  curved  track  resulted  in 
greatly  accelerated  rail  wear  in  curves.  The  rail  wear  was  much  greater  than  would 
be  anticipated  based  only  on  increased  annual  tonnage. 

Examination  of  the  train  consists  confirmed  that  nearly  all  of  the  100-ton  cars 
moved  in  unit  ti^ains.  Since  the  basic  design  of  all  capacities  of  freight  car  trucks 
is  die  same,  the  rail  wear  problems  are  more  accurately  attributable  to  100-ton 
carloadings.  It  is  apparent  diat  in  going  to  100-ton  carloadings  we  ha\'e  unwittingly 
stepped  over  a  threshold  and  are  now  sufl^ering  puniti\e  rail  damages  on  lines  where 
sharp  curves  are  frequently  encountered.  The  role  of  tiie  unit  train  has  been  to 
bring  this  problem  into  sharper  focus.  The  need  for  a  program  of  remedial  action 
to  improve  existing  services  and  for  the  exercise  of  caution  in  designing  new  services 
is  now  apparent. 

UNDERSTANDING  THE  PROBLEM 

For  any  remedial  action  to  be  effectixe,  the  causes  of  the  problem  and  the 
nature  of  the  remedial  action  must  be  understood.  We  will,  dierefore,  attempt  to 
deal  with  the  subject  by  posing  the  following  questions,  and  then  attempting  to 
answer  them  in  a  manner  that  can  be  understood  by  people  of  xarying  educational 
backgrounds  and  work  experience: 

How  Severe  Is  the  Problem? 

What  Are  the  Causes  of  Accelerated  Rail  Wear? 

What  Remedial  Action  Is  Required  and  by  Whom? 


Xote:    Discussion  open   until  October   16,   1976. 

601 


602 


Bulletin  658 — American  Railway  Engineering  Association 


1972  Traffic  Carried  by  Vehicles  of  50,  70  and  100  Ton  Capacity 


Car  Capacity 
(Nominal) 

Number  of  Cars 

Gross  Tonnage 

Gross  Tons/Car 

%  Car   1 
Capacic-.. 

Actual 

Gross 
Limit 

40-50  tons 

126,487 

8,257,315 

65.3 

88.5 

74 

70  tons 

41,595 

3,374,630 

81.1 

110.0 

74 

100  tons 

59,261 

7,306,415 

123.3 

131.5 

94 

TOTAL 

227,343 

18,938,360 

.35- 

.3- 

>- 

- 

u 

z 
u 

.25- 

3 

C) 

- 

LU 

a: 

.2- 

u 

• 

> 

< 

,15- 

_l 

llJ 

q: 

.1- 


.05 


0 


WESTWARD  DIRECTION 
EASTWARD  DIRECTION 


Iz 


zz 


V, 


■  /, 


/ 


77]rr7-\'  /; 


0     10.20  30  -10    50  60  70   60  90  100110  120  130140 
GROSS    TONS/CARS 

Fig.    1 — ^Frequency   histogram   of   gross   car  weight  through   Shuswap   Subdivision. 


Report  by  F.  E.  King,  J.  Kalousek 603 

HOW  SEVERE  IS  THE  PROBLEM? 

The  problem  occurs  to  some  extent  on  all  curxes  but  seems  to  be  more  trouble- 
some on  the  shaiper  curves  of  4°  and  up.  CN  has  made  rather  extensive  analyses 
deriving  data  from  traffic  splits  by  gross  carloadings  from  1967  to  1974,  from  rail 
replacement  data  from  1964  to  1974,  and  from  annual  gross  tonnages  back  to  1960. 
There  is  a  clearly  discernible  trend  of  severely  escalating  replacement  rates  as  the 
percentage  of  fully  loaded  100-ton  cars  increases.  It  appears  that  we  can  anticipate 
replacing  about  one-third  of  track  in  these  curves  annually  if  the  present  traffic 
patterns  and  replacement  rates  are  sustained. 

On  Canadian  Pacific  trackage,  these  problems  coincided  witli  the  dramatic 
increase  in  freight  traffic  which  nearly  doubled  in  the  period  between  1964  and  1969. 
On  CP  Rail,  the  gross  tonnages  are  higher  and  the  curvatures  are  sharper,  therefore 
the  problem  is  even  more  serious.  This  problem  also  occurs  in  other  locations  where 
substantial  numbers  of  heavy  xehicles  operate  on  curved  track. 

Curve  wear,  head  flow  and  rail  corrugations  also  occur  on  other  railways  in 
Canada  and  elsewhere  in  tlie  world.  In  planning  new  unit-train  movements,  it  is 
important  to  consider  the  percentage  of  curved  trackage  over  which  the  trains  will 
operate.  Otherwise,  greatly  accelerated  rail  wear  may  occur  and  the  rates  charged 
by  the  railroad  may  not  be  fully  compensatory. 

WHAT  ARE  THE  CAUSES  OF  ACCELERATED  RAIL  WEAR? 

The  accelerated  rail  wear,  although  closely  linked  with  unit-train  operation 
is,  in  fact,  a  direct  consequence  of  overloading  of  the  rail  by  the  fully  loaded  100- 
ton  cars   used  in  these   trains.   The   rail  wear  takes   three  forms: 

(a)  Gauge  face  wear  on  the  high  rail. 

(b)  Head  flow  on  the  low  rail. 

(c)  Corrugations  of  wavelengths  of  8  to  30  in. 

Each  of  these  is  caused  by  a  different  mechanism  or  mechanisms  and  will 
be  treated  separately,  although  head  flow  and  corrugation  often  occur  on  the  same 
rail.  Before  discussing  these  causes,  I  would  like  to  point  out  again  that  this  accel- 
erated wear  is  much  greater  tlian  would  be  expected  due  to  tonnage  increases  alone. 
Neither  is  overspeeding  or  underspeeding  in  curves  a  necessary  condition,  since 
this  wear  will  take  place  when  the  vehicles  are  passing  through  the  curve  at  tlie 
designed  speed.  However,  overspeeding  or  underspeeding  does  aggravate  the  con- 
dition and  should  not  be  permitted. 

Gauge  Face  Wear 

The  rate  of  gauge  face  wear  on  the  rail  is  obviously  affected  by  the  rail 
properties,  for  example,  the  harder  the  rail,  the  lower  the  expected  rate  of  wear. 
However,  for  any  given  rail  steel,  gauge  face  wear  on  the  side  of  the  high  rail  in 
curved  track  is  caused  by  vehicle  tracking  problems.  Existing  vehicles,  both  loco- 
motives and  cars,  do  not  track  very  well  in  curves.  A  brief  exposition  of  this  tracking 
problem  is  given  here. 

Gauge  face  wear  is  a  function  of  the  four  parameters  listed  below: 
Mf  =  The  coefficient  of  friction  between  the  flange  and  the  gauge  face  of  the 
rail  at  the  point  B  as  shown  in  Fig.  2. 


604 


Bulletin  658 — American  Railway  Engineering  Association 


POINT  OF  CONTACT 
ON  TREAD 


POINT  OF  CONTACT/ 
ON   FLANGE-^ 


ANGLE ';^' 


Fig.  2 — Wheel-rail  contact. 


j8  ,  =  The  angle  of  the  tangent  to  the  flange  at  tlie  contact  point  between  the 

wheel  and  the  rail,  measured  from  the  horizontal  position  also  as  shown 

in  Fig.  2. 
a    z=  The  angle  of  attack  between  the  flange  of  the  wheel  and  the  gauge  face 

of  the  rail  as  shown  in  Fig.  3. 
Ff  ^=  Flange  force  which  is  equal  to  the  sum  of  two  components  as  given  in 

the  equation: 

Ff  c=  2  /^e  N  +  H 

The  term  "2  Me  N"  is  the  lateral  component  of  the  tread  creep  force 
required  to  slide  the  wheels  laterally  in  the  curve.  The  tenii  "H"  is  the 
lateral  thrust  due  to  unbalanced  centrifugal  forces,  alignment  irregulari- 
ties, dynamic  efl^ects  such  as  vehicle  rocking  and  the  interaxle  forces  on 
the  truck.  The  forces  are  illustrated  in  Fig.  4. 

It  is  apparent  that  reduction  in  gauge  face  wear  as  well  as  wheel  flange  wear 
can  be  effected  by  reducing  the  magnitude  of  tliese  four  parameters  Mr,  /3,  a  and  Fr. 
Increasing  the  hardness  of  the  rail  will  also  decrease  the  rate  of  rail  wear.  There- 


Report  by  F.  E.  King,  J.  Kalousek 


605 


Fig.  3 — Angle  of  attack  between  wheel  flange  and  rail. 


Ff  =  2/^eN*H 


Fig.  4 — Lateral  forces  on  curves. 


fore,  the  maximum  benefits  will  be  achieved  if  the  use  of  harder  rail  steel  in  curves 
is  accompanied  by  measures  designed  to  reduce  the  four  parameters  listed  above. 
The  value  of  die  coefficient  of  friction  Mf,  can  be  reduced  by  judicious  use  of 
track-mounted  wheel  flange  oilers.  The  angle  j3  cannot  readily  be  changed  since  this 
angle  should  not  be  appreciably  less  than  70°  because  of  the  danger  of  the  wheel 
flange  climbing  the  rail.  Also,  it  should  not  be  greater  than  about  80°  because  of  the 
danger  of  derailment  at  switch  points.  The  angle  of  attack  a  and  the  flange  force 


606 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  5 — New  AAR  wheel  profile. 


can  be  reduced  by  proper  combination  of  sufficient  wheel  tread  conicity  and  flange- 
way  clearance  to  help  the  wheelset  to  steer  itself  around  the  curve.  The  interaction 
of  these  two  parameters  is  quite  complex  and  requires  further  explanation. 

The  standard  Association  of  American  Railroads  (AAR)  new  wheel  profile  has 
two  major  defects  in  its  curving  capability.  These  are  insufficient  conicity  and  two- 
point  contact  in  curves.  The  conicity  of  1  in  20  or  0.05  limits  the  ability  of  a  single 
wheelset  to  negotiate  curves  without  flanging  to  those  curves  which  are  less  than 
2.4°.  The  two-point  contact  allows  the  flange  of  the  wheel  to  scrub  the  side  of  the 
rail  in  curves.  Both  tlie  defects  can  be  minimized  by  special  profiles  having  conicities 
3  to  5  times  greater  than  the  new  AAR  profile  and  shaped  to  avoid  two-point  contact. 
Fig.  5  shows  a  new  AAR  wheel  profile  with  contact  at  both  the  flange  and  crown 
of  a  new  132-lb  rail.  Fig.  6  shows  a  special  experimental  profile  designed  to  give 
sufficient  conicity  to  allow  a  single  wheelset  to  pass  through  most  main  line  curves 
without  flanging  and  two  point  contact. 

Special  wheel  profiles  alone  on  standard  freight  car  trucks  will  not  make  the 
wheelsets  negotiate  curves  in  a  flange-free  condition  because  this  truck  does  not  have 
the  ability  to  align  the  wheelsets  radially  in  the  curve.  The  special  profile  will, 
however,  reduce  wheel  flange  and  rail  gauge  face  wear.  Canadian  National  is  pres- 
ently testing  and  evaluating  the  comparative  wear  characteristics  of  new  AAR 
profiles  against  the  experimental  profile  shown  in  Fig.  6. 


Report  by  F.  E.  King,  J.  Kalousek 


607 


Fig.  6 — Experimental  wheel  profile. 


Since  the  flange  force  Ft  =  2Me  N  +  H,  as  shown  in  Fig.  4,  it  can  be  reduced 
by  diminishing  either  or  both  tliese  components.  The  term  2  /^eN  is  the  lateral 
component  of  the  tread  creep  forces  required  to  slide  the  wheels  laterally  in  a  curve, 
where  Me  is  the  effective  lateral  tread  coefficient  of  adhesion  and  N  is  the  wheel 
load  normal  to  the  rail.  The  coefficient  Me  depends  on  the  angle  of  attack  a;  and  can 
vary  from  zero  at  zero  angle  of  attack  to  M  the  limit  of  wheel  rail  adhesion  at  an 
angle  of  attack  of  about  1°  as  shown  in  Fig.  7.  Thus,  if  the  wheelset  has  sufficient 
tread  conicity  and  the  ability  to  align  itself  radially  in  the  curve,  this  term  MeN, 
will  become  zero.  With  existing  AAR  profiles  and  standard  three-piece  trucks,  the 
angle  of  attack  a  often  exceeds  1°  and  the  value  Me  approaches  M,  the  limit  of 
wheel-rail  adhesion.  This  gives  rise  to  very  high  values  of  tread  creep  force  which 
can  range  from  9,800  to  23,000  lb  for  typical  values  of  M  between  0.15  and  0.35 
and  a  wheel-load  of  32,875  lb  ( 100- ton  vehicle).  This  can  be  considered  to  be  a 
major  component  of  flange  force  and  the  importance  of  achieving  a  minimized  angle 
of  attack  a  through  the  combined  use  of  profiled  wheels  and  improved  truck  design 
with   radial   curving   ability   can   hardly   be   overemphasized. 

The  other  component  of  flange  force  H,  the  lateral  tiirust,  is  due  to  unbalanced 
centrifugal  forces,  alignment  and  cross  level  irregularities,  dynamic  eftects  such  as 
car  rocking  and  interaxle  forces  on  the  trucks.  This  component  can  be  reduced  by 


608 


Bulletin  658 — American  Railway  Engineering  Association 


EFFECTIVE 
LATERAL 
COEFFICIENT 
OF  ADHESION 


y(A   LIMIT  OF  WHEEL-RAIL  ADHESION 


C<     ANGLE   OF  ATTACK 
Fig.   7 — Effective   lateral  coefficient  of   adhesion   versus   angle   of   attack. 


LOZENGED 
CONFIGURATION 


SQUARE 
CONFIGURATION 


RADIAL 
CONFIGURATION 


MAX 
POSITIVE 
ANGLE  OF 
ATTACK 


POSITIVE 
ANGLE  OF 
ATTACK 


ZERO 
ANGLE  OF 
ATTACK 


Fig.  8 — Angle  of  attack  of  leading  wheel  in  curves. 


Report  by  F.  E.  King,  J.  Kalousek  609 


diminishing  or  eliminating  tliese  conditions.  Interaxle  forces  arise  because  the 
existing  freight  car  truck  does  not  permit  the  axles  to  align  themselves  radially 
in  a  ciu^e,  pre\enting  the  wheel  flange  from  assuming  a  zero  angle  of  attack.  In 
addition,  the  clearances  between  the  miijor  components  of  the  truck  permit  tiie  truck 
side  frames  to  lozenge  fiurther  increasing  tlie  angle  of  attack.  Fig.  8  shows  the  angle 
of  attack  of  the  leading  wheel  in  curves  for  the  three  configurations,  lozenged, 
square  and  radial. 

From  tlie  abo\e  discussion,  it  can  be  seen  that  there  will  be  minimal  lateral 
force  in  cur\es  if  four  conditions  are  met  simultaneously: 

1.  The  vehicles  pass  tlirough  die  cur\e  at  the  exact  speed  for  which  die  cur\'e 
is  banked. 

2.  The  curve  has  no  alignment  and  cross-le\el  irregularities. 

3.  The  wheel  treads  have  sufficient  conicity  and  flangeway  clearance  to  steer 
the  w^heelsets  in  the  curve  without  flanging. 

4.  Vehicle  trucks   allow   the  axles  to  align  radially  under  the  action  of  tread 
creep  forces. 

Since  the  forc-e  on  tlie  flange  increases  with  increasing  angle  of  attack  and  since 
flange  wear  on  the  wheel,  gauge  face  wear  on  die  rail,  and  curxing  resistance  all 
increase  directly  with  the  angle  of  attack,  the  benefits  to  be  derixed  from  a  truck 
design  which  permits  radial  action  are  ob\ious.  A  prototype  truck  with  radial  cuning 
capability'  is  currently  under  test  at  the  Canadian  National  Technical  Research  Center. 

Rail  Head  Flow 

Rail  head  flow  is  found  on  the  low  rail  in  curves  in  British  Columbia  and  is 
caused  by  excessive  pressure  at  the  point  of  contact  between  tlie  wheel  and  the  rail. 
The  mechanism  which  is  believed  responsible  for  this  excessive  contact  pressure 
is  described  in  this  section. 

Both  the  wheel  and  the  rail  ha\'e  curved  surfaces  at  their  point  of  contact. 
The  first  satisfactory  solution  for  contact  stresses  occurring  between  t\\'0  elastic 
bodies  having  curved  surfaces  was  provided  by  Hertz  in   1881. 

For  a  steel  wheel  on  a  steel  rail,  the  maximum  compressive  stress  qo  can  be 
approximated  using  the  following  formula: 


qo  =  2.36  XlO^  -  {^y    (P)' 


where  qo    =  the  maximum  compressive  stress  in  pounds  per  square  inch. 
P      =  tlie  imposed  wheel  load  in  pounds. 

R    -     Ri       R'l        R.  ^  R'. 

Ri    =  the  radius  transverse  to  the  tread  in  inches. 

R'l   =1  the  radius  of  the  wheel  in  inches. 

Ro    z=  the  crown  radius  of  the  rail  head  in  inches. 

R'o  =  the  track  curvature  in  the  \ertical  direction. 

Since  there  is  virtually  no  vertical  curvature,  R'2  approaches  00.  There- 
fore,           can  be  assessed  to  be  always  equal  to  zero  and  this  term 

R'. 
can   be   eliminated   from    the   calculation    of   maximum    contact   stress. 


610 


Bulletin  658 — American  Railway  Engineering  Association 


effect  of    n(-;:i<ji)    i>.aviinfLi-i  s   on   ci^ 

,     "   2.36  X   lo''     ,:,?.,    '''   (..)    '/-^ 


K 


1 



Ch.:rvjo 

Ill' 

i;o. 

Pouiu! 

0 

3 :! »  7  'j 

1 

27''.00 

2 

3 

2V'jOO 

4 

5 

C 

7 

G 

^_  . :_- .^::^: 

.-:.-.::=:-.:-z 

i'ln    r.T! 


-10.0 
f  6.  0 
+    2.0 

- 1  r. .  0 


"1 
j:::;. 


1  ('- .  1 
ic. ' 


1/3 


32.03 
30.  ]B 
3  2.03 
30.  1  « 
32.03 
32.0  3 
3  2.03 
3  2.03 
32.03 


i}y'' 


0  .  2  'J 
C.2'J 
0.  30 
0.  3  0 
0.25 
0.  20 
0  .  '1 7 
0.7'". 
0.  1  0 


219 
20G 
227 
210 
190 
ISl 
355 
57  0 

no 


1 



Cha.,o 

i\i 

i \  '"    " 

\ 

: 

-    G 

\-    -1 

..    ,1 

!• 

-)  3 

-31 

}02 

MCO 

-50 

!( 

N.B.        (1)     Hl.iiik    r.pacor.    in    dorjiijn    p.ir.ir;rj|.or£;    coluiMif; 

CI  Kill 'JO      SO. 

(2)    V.iliK-:;    of    q„   .'-.lioi/n    for   c)i;i:iij.>:;    ?6   onri    S7 
o.xccoa    the    ela.-aic    lii.iit    of    rail    ;;lccl. 
T'ao    iiiii  Loria.  1    will    yioUi    arui    flow    at    i;oir.o 
lov;cr    valuo. 


The  above  fomiula  can  be  used  to  assess  the  relative  importance  of  these 
variables  in  generating  the  maximum  contact  stress,  Qo.  Table  2  shows  tlie  effect 
of  varying  the  design  parameters,  P,  Ri,  R'l  and  Rj.  In  this  table,  the  standard  for 
comparison  (change  mmiber  0)  is  a  fully  loaded,  100-ton-capacity  vehicle  mounted 
on  new  AAR  profile  wheels  of  36-in.  diameter.  The  wheels  run  on  a  new  132-lb 
rail  section  with  a  head  radius  of  10  in.  Under  these  conditions,  the  maximum  con- 
tact stress  is  estimated  to  be  219,000  psi. 

Table  2  shows  that  changes  in  the  radius  transverse  to  the  wheel  tread  are 
responsible  for  the  head  flow  conditions  found  on  the  low  rail  in  curves. 

Figure  9  shows  the  value  Ri,  the  radius  across  the  tread,  may  be  infinitely 
large,  negative  or  positive,  depending  on  the  wear  condition  of  the  wheel.  When 
the  wheel  is  new,  the  coned  surface  is  a  straight  line  in  the  contact  plane  and  Ri 

becomes  infinite  and  —  becomes  zero.  This  is  the  comparison  case:    change  No. 
Ri 


Report  by  F.  E.  King,  J.  Kalousek 


611 


219,000    psi 


iD 


570,000    psi 


qo   -    151,000    psi 


NEW  V'/hlEEL 
1  IN  20  TAPER  ACROSS 
TREAD 


WORN  WHEEL 
TREAD   WORN  HOLLOW 
WITH   REVERSE  CURVATURE 


Fig.  9 — Transverse  tread  radius,  Ri. 


zero  and  q„  equals  219,000  psi  as  shown  in  the  table.  When  the  wheel  is  worn, 
the  central  portion  of  the  tread  hollows  out  to  approximately  15  in.  radius.  By 
convention,  tliis  radius  is  considered  negative  for  purposes  of  calculation.  This 
condition  is  shown  as  change  No.  5,  giving  a  value  of  qo  equal  to  151,000  psi,  or 
a  reduction  of  31%  over  the  standard  for  comparison. 

At  the  edge  of  the  worn  tread,  a  reverse  curvature  of  2  in.  to  6  in.  may  develop 
as  shown  in  Fig.  9.  With  reverse  curvatures  of  6.0  in.  and  2.0  in.  values  of  qo  of 
355,000  and  570,000  psi,  respectively,  would  be  developed  if  the  material  did  not 
yield,  giving  increases  of  62  and  160%.  These  are  shown  in  the  table  as  change  Nos. 
6  and  7.  These  values  of  maximum  compressive  stress  exceed  the  elastic  limit  of 
steel  and  the  material  will  yield  and  flow  at  some  lower  value.  It  is  this  reverse 
curvature  on  the  edge  of  the  wheel  tread  which  is  responsible  for  the  head  flow 
problems  encountered  on  our  lines. 

Fig.  10  shows  that,  provided  sufficient  flangeway  clearance  exists  between  the 
wheels  and  the  rails,  the  outer  convex  portion  of  tlie  wheel  tread  can  ride  up  on 
the  rail  head.  It  can  be  shown  that  under  conditions  which  are  not  considered  con- 
demnable  the  outside  edge  of  the  wheel  can  be  0.6  in.  inside  the  field  side  of  the 
rail  and  the  center  of  the  reverse  curvature  may  therefore  contact  the  rail  1  in.  or 
more  from  the  field  side.  This  condition  is  essentially  point  loading  and  generates 
maximum  contact  stresses  several  times  that  developed  for  a  new  coned  wheel.  This 
point  loading  is  illustrated  in  Fig.    10  for  actual  sections  of  worn  wheel  and  rail. 

Fig.  11  shows  graphically  the  effect  of  transverse  tread  radius  on  maximum 
wheel  rail  contact  stresses  for  a  fully  loaded  100-ton  car  on  36-in. -diameter  wheels 
and  a  fully  loaded  70-ton  car  on  33-in. -diameter  wheels.  Note  that  the  effect  of 
reduction  of  gross  rail  load  on  the  maximum  contact  stress  is  rather  small,  being 


612 


Bulletin  658 — American  Railway  Engineering  Association 


'fTl 


•|f.': 


rr^'^v 


I-?.' 


m'^^ 


-06 


Maximum  Compressive  Stress 
Approximately  500,000  PSI  or  at 
least  4  times  the  stress  necessary 
to  cause  permanent  surface  deformation 


Fig.    10 — Contact  between  wheel   and   rail   in   curves. 


Report  by  F.  E.  King,  J.  Kalousek 


613 


iHHF 


hUXLMUM  U'HEEL  RAIL  CONTACT  STRESSES  -  q^ 
Effect  of  Transverse  Tread  Radius  -  R, 


-800 


700 


—  600 


-o 500  — 


—  w  «0C 


■-■!  - 

-   r 

:i: 

— ioo 

IJ- 

0.0 


!':; 


LHir:.:: 


-300 


-200  


Fig.  11 — Maximum  wheel  rail  contact  stresses. 


Bui.  058 


614 


Bulletin  658 — American  Railway  Engineering  Association 


Fig.  12 — Rail  wear  examples. 


about  3%.  Even  if  the  70-ton  car  were  fitted  with  36-in.-diameter  wheels,  the  reduc- 
tion would  not  exceed  6%.  Thus,  the  remedial  action  to  eliminate  head  flow  must 
involve  tlie  elimination  of  this  reverse  curvature  condition  on  tlie  worn  wheel  tread. 


RAIL  CORRUGATIONS 

Rail  corrugations  present  one  of  the  most  challenging  problems  of  our  day 
to  the  railway  engineer.  The  problem  is  rather  complex  and  has  been  experienced 
for  a  considerable  length  of  time.  Perhaps,  the  first  difiBculty  in  coming  to  grips 
with  the  problem  lies  in  the  fact  that  the  term  corrugation  in  North  American  rail- 
road terminology  is  used  to  describe  a  short  wavelength  form,  1  in.  to  3  in.,  as  well 
as  a  long  wavelength  form  8  in.  to  24  in. 

Short  wavelength  corrugations,  often  referred  to  as  "washboard  rail"  or  "roaring 
rail,"  occur  most  frequently  on  mass  transit  lines.  These  corrugations  are  primarily 
a  source  of  noise  pollution,  disturbing  both  passengers  and  residents  living  near  the 
track.  This  "roaring  rail"  results  in  accelerated  deterioration  of  rolling  stock  and 
track  components,  but  does  not  constitute  a  serious  operating  hazard. 

Long  wavelength  corrugations  appear  most  often  on  routes  with  large  annual 
tonnages  (20  MGT  or  more)  and  high  axle  loadings  (30  tons  typically).  Unlike 
the  short  wavelength  form,  long  wavelength  corrugations  present  an  operating  hazard. 
If  these  corrugations  are  allowed  to  grow  deeper  with  time,  derailments  may  occur 
either  as  a  result  of  wheel  lift  or  rail  failure  due  to  an  increased  level  of  dynamic 
loadings.  To  avoid  this  failure  risk,  the  growth  of  corrugations  must  be  controlled 
by  periodic  grinding.  Apart  from  the  potential  derailment  hazard,  rail  corrugations 
create  substantial  operating  difficulties  for  railroads  due  to  temporary  slow  orders 
which  have  to  be  imposed  from  time  to  time  and  because  of  the  track  occupancy 
time  required  for  rail  grinding  and  rail  replacement.  The  total  costs  incurred  by  a 
railroad  due  to  rail  corrugations  have  never  been  accurately  quantified.  The  annual 
rental  cost  of  the  specialized  grinding  equipment  and  operators  can  easily  amount 


Report  by  F.  E.  King,  J.  Kaloiisek  615 


to  $0.75  million.  Costs  incurred  as  a  result  of  rail  replacements,  additional  wear 
and  tear  on  rolling  stock,  and  lading  damage  are  appreciable,  but  are  difficult  to 
quantify.  A  fundamental  understanding  of  the  factors  which  contribute  to  the  forma- 
tion and  propagation  of  long  wavelengtli  corrugations  is  necessary  to  formulate 
proper    remedial    action    and    thereby    achieve    appreciable    savings    to   the   railroad. 

Where  Do  Rail  Corrugations  Occur? 

In  general,  rail  corrugations  appear  on  the  running  surface  of  low  and  high 
rails  in  curves,  on  tangent  track,  and  on  frogs. 

The  occurrence  of  rail  corrugations  on  tangent  track  is  very  infrequent  and 
we  will,  therefore,  devote  our  attention  only  to  rail  corrugations  on  curves.  CP  and 
CN  experience  corrugations  on  the  low  rail,  where  tliey  are  usually  most  prevalent, 
before  they  appear  on  the  high  rail. 

In  contrast,  on  railways  exclusively  hauling  mineral  traffic,  rail  corrugations 
appear  first  and  are  predominant  on  the  high  rail.  In  both  cases,  corrugations  are 
usually  deeper  on  the  inner  side  of  the  curved  rail,  that  is,  on  the  field  side  of  the 
low  rail  and  on  the  gauge  side  of  the  high  rail. 

To  determine  the  longitudinal  characteristics  of  rail  corrugations,  we  have 
measured  corrugation  profiles  on  a  point  by  point  basis  along  the  centerline  of  the 
railhead.  These  profiles  were  completely  random  in  shape,  depth  and  length.  Subse- 
quently, we  measured  the  depth,  and  length  of  the  corrugations  on  a  low  rail  through- 
out the  entire  curve.  Fig.  13  shows  tlie  resulting  frequency  histogram  of  corrugation 
wavelength  or  pitch.  The  mean  length  was  calculated  as  approximately  ISii  in.  and 
the  mode  at  12  in. 

What  Are  the   Possible   Causes  of  Rail  Corrugations? 

The  periodicity  of  the  corrugation  pitch  correlates  reasonably  well  with  some 
of  the  reasonant  frequencies  of  the  track-train  system,  but  no  distinct  correlation 
peak  could  be  found  between  track-train  harmonics,  operational  speeds,  and  corru- 
gation pitch.  The  variables  in  car  design,  loadings,  and  track  substructure  make  it 
quite  unlikely  that  dynamical  peaks  repeat  exactly  at  tlie  same  locations  on  un- 
corrugated  rail.  These  two  aspects  of  dynamical  loadings  reinforce  the  opinion  that 
the  presence  of  dynamical  loadings  alone  is  not  sufficient  to  initiate  formation  of 
corrugations. 

If  corrugations  are  not  "initiated"  by  dynamical  loads,  what  other  mechanisms 
are  involved?  Several  other  mechanisms  have  been  suggested  to  explain  the  initiation 
of  rail  corrugations.  One  school  of  thought  believes  corrugations  are  related  to  contact 
vibrations.  Contact  vibration  theory  states  that  a  small  volume  of  wheel/rail  material 
in  the  zone  of  contact  can  be  excited  by  the  roughness  of  the  wheel  and  rail  surfaces 
to  vibrate  at  its  natural  frequency.  The  compressive  dynamical  contact  vibration 
peaks  accelerate  wear  and  contribute  to  plastic  deformation  of  rail  metal  which 
may  initiate  fonnation  of  corrugations.  Whilst  this  tlieory  correlates  well  with  forma- 
tion of  "roaring  rail,"  there  is  no  experimental  data  as  yet  available  which  may  be 
used  to  test  this  theory  and  its  applicability  to  long  wavelength  corrugation 
formation. 

Many  railroaders  and  researchers  have  suggested  that  corrugations  are  initiated 
by  a  "stick-slip"  effect  of  the  wheelset  during  curve  negotiation.  The  stick-slip  effect 
results  from  the  fact  that  the  wheelset  acts  as  one  piece  and  the  wheel  on  the  high 
rail  must  travel  further  than  the  one  on  the  low  rail  during  curve  negotiation. 
Assuming  that  the  effective  radius  is  the  same  for  both  wheels,  the  wheel  on  the 


616 


Bulletin  658 — American  Railway  Engineering  Association 


>- 
U 

z 
u 

o 

LlI 
01 

Ll 


50 


f4 
u 
u 

z 

UJ 

q: 
O 

Ll 

O 


30 


20- 


10- 


0 


t 


4      5      8     10    12    14     16    18    20    22  24   26  2S    30  32    34 
LENGTH  OF  CORRUGATION    (INCH) 


MEAN:         15.4  in.     STANDARD  DEVIATION;    4.6 
MODE:        12.0    in.     SKEWNESS;  1.4 

MEDIAN:      14.4  in,     CURTOSIS  :  3.25 

Fig.    13 — Frequency   histogram    of   corrugation    length. 


high  rail  would  be  forced  to  rotate  more  tlian  the  wheel  on  the  low  rail.  This  differ- 
ential in  wheel  revolutions  places  the  axle  in  torque  until  the  adhesion  forces  at  the 
wheel/rail  interface  become  insufficient  on  eitlier  the  high  or  low  rail  resulting  in 
a  "shp"  effect.  Once  slip  occurs,  tlie  adhesion  forces  are  restored,  and  the  wheels 
"stick."  The  entire  process  occurs  in  a  very  short  period  of  time  and  is  repeated 
over  and  over  again.  If  the  "stick-slip"  occurs  on  uncornigated  rails,  it  may  initiate 
formation  of  corrugations. 

Experimental  data  are  needed  to  understand  the  role  which  any  "stick-slip" 
effect  might  have  in  corrugation  formation.  Canadian  Pacific  and  the  National 
Research  Council  of  Canada  will,  at  the  request  of  the  AAR,  carry  out  field  testing 
later  this  year  to  record  the  behavior  of  wheelsets  during  curve  negotiation. 

Other  theories  and  suggestions  have  been  proposed  to  account  for  initiation 
of  rail  corrugations.  We  have  limited  our  discussion  only  to  those  which  are  most 
frequently  mentioned  in  connection  with  corrugation  formation.  It  is  quite  possible 
that  any  one  or  combination  of  all  three  mechanisms  mentioned  above  may  be  a 
contributing  factor  in  corrugation  formation.  We  believe,  however,  that  plastic  flow 
and  surface  fatigue  in  the  top  layer  of  rail  head  material  are  the  most  significant 
factors    contributing   to   formation   of   long   wavelength   corrugations. 


i 


Report  by  F.  E.  King,  J.  Kaloiisek  617 

Surface  Fatigue  and  Plastic  Flow 

In  the  first  portion  of  this  presentation,  tlie  presence  of  high  contact  stresses 
was  demonstrated,  namely,  in  the  case  of  wheels  with  a  reverse  curvature  running 
on  top  of  the  low  rail.  The  yield  stress  of  the  rail  material  is  exceeded  and  metal 
flow  results.  During  the  first  few  loading  cycles  by  passing  wheels,  the  surface  layer 
of  rail  material  is  plastically  compressed  and  a  residual  stress  acting  parallel  to  tlie 
surface  is  introduced.  During  subsequent  passages  of  wheels,  the  rail  material  is 
subjected  to  the  combined  action  of  residual  and  contact  stresses  and  further 
yielding  becomes  less  likely.  This  process  is  referred  to  by  metallurgists  as  cold- 
working  of  material  and  when  it  is  confined  to  rolling  contact,  it  is  referred  to  as 
"shakedown."  The  maximum  load  for  which  the  rail  material  can  still  be  cold- 
worked  is  called  shakedown  limit  or  plasticity  limit.  In  other  words,  if  the  magnitude 
of  contact  stresses  falls  bet\veen  the  elastic  and  plastic  limits,  the  rail  material 
cold-works  and  the  system  "shakes  down"  to  the  elastic  cycle  of  stress.  Overstressing 
of  rail  material  above  the  plastic  limit  results  in  continuous  and  cumulative  plastic 
deformation  of  rail  material. 

Under  the  conditions  of  pure  rolling  such  as  in  the  case  of  rolling  wheelsets 
on  tangent  track  without  braking  or  traction,  the  plasticity  limit  is  proportional 
to  hardness  of  rail  metal: 

qpi  ;:=i  -^DPH   (after  K.  L.  Johnson) 

where  DPH  is  the  Vickers  diamond  pyramid  hardness.  Under  the  presence  of  tractive 
forces  in  the  zone  of  contact,  caused  by  traction,  braking  or  lateral  curving  forces, 
the  plasticity  limit  decreases  with  increasing  effective  coefficient  of  friction  as  shown 
in  Fig.  14.  In  this  figure,  the  eftective  coefficient  of  friction  is  presented  as  the 
ratio  of  tractive  force  to  normal  load  Ft/P.  In  reality,  this  means  that  the  beneficial 
effects  of  cold-working  of  rail  materials  in  curves  is  lost  when  the  efl^ective  coefficient 
of  friction  reaches  a  value  of  0.26. 

Table  3  indicates  the  plasticity  limits  q,,i  for  various  rail  materials  in  terms 
of  maximum  Hertzian  contact  pressure.  In  calculating  the  plasticity  limits,  a  value 
of  0.16  was  considered  as  typical  for  wheel/rail  adliesion  in  lubricated  curves.  These 
values  are  approximate  and  may  vary  somewhat  with  metallurgical  properties  of 
rail  material.  The  rail  head  hardness  range  of  250-270  BHN  corresponds  to  plain 
carbon  rail,  310-330  BHN  to  manganese-vanadium  or  chromium  rails  and  360-380 
BHN  to  fully  heat-treated  or  curvemaster  rails.  The  increase  in  plasticity  limit  and 
resulting  reduction  in  head  flow  with  increasing  rail  head  hardness  is  self-evident 
in  this  table.  The  table  also  indicates  that  installation  of  premium  rails  in  curves 
is  advantageous  on  lines  where   100- ton-capacity  cars  are  used  extensively. 

During  initial  cold-working  and  homogeneous  plastic  flow,  conditions  are  being 
formed  within  the  rail  material  which  will  lead  to  localized  failure.  Cracks  may 
develop  at,  or  very  near,  the  rail  surface  or  a  short  distance  below  it.  The  large 
variation  in  possible  wheel/rail  contact  geometries  and  the  effect  of  frictional  forces 
and  other  parameters  on  the  distribution  of  contact  stresses,  may  cause  the  railhead 
material  to  fail  due  to  flaking,  pitting,  spalling  or  subsurface  shelling.  These  failures 
fall  under  the  common  category  of  surface  fatigue  or  contact  fatigue.  Each  of  these 
contact  fatigue  manifestations  develops  in  hvo  stages.  The  first  stage  is  crack  initia- 
tion and  the  second  is  crack  propagation.  The  cracks  which  initiate  at  the  surface 
give  rise  to  flaking  on  the  low  rail  or  spalling  on  the  high  rail  and  contribute  sig- 
nificantly to  the  initiation  of  corrugations. 


618 


Bulletin  658 — American  Railway  Engineering  Association 


2.0 


1.5- 


< 

Q 


1.0 


< 

u 

t— 
cr 

> 


.5- 


■ 

N^^^                         CONTINUOUSLY    PLASTIC 
-    SHAKEDOWN     ^X^'^'V;^ 

-=.£tdsr(c_ 

.-..OyV^^^ 

ELASTIC 

1^^ 

1           1 

1                .11                 .                 1 

.1  .2  .3  A  .i 

RATIO  OF  TRACTIVE   FORCE  TO   NORMAL  LOAD 

Fig.    14 — The   effect   of  tangential  force   on   the   elastic   and  plasticity  limits. 


The  mechanics  of  surface  crack  initiation  and  growth  have  been  dealt  with  in 
detail  at  the  AREA  Regional  Meeting  held  in  Vancouver  in  1975  and  are  published 
in  AREA  Bulletin  No.  656.  To  avoid  repetition,  only  tlie  main  points  concerning 
the  role  which  cracks  play  in  corrugation  formation  will  be  summarized  here.  Once 
the  cracks  form: 

(a)  they  disrupt  the  homogenity  of  the  surface  layer  of  rail  metal  and  signifi- 
cantly redistribute  contact  stresses,  which  results  in  a  reduction  of  rail 
metal  resistance  to  plastic  flow; 

(b)  in  combination  with  lateral  tractive  force,  cracks  enhance  the  depletion 
of  metal  from  the  surface  layer  through  flaking  or  gauge  corner  spalling; 

(c)  inside  the  cracks,  a  significant  amount  of  wear  debris  may  form  which  can 
lead  to  accelerated  depletion  of  metal  from  within  the  crack. 

In  locations  where  cracks  are  more  numerous  or  where  they  grow  at  an  accel- 
erated pace,  head  flow  is  more  rapid,  depletion  of  metal  from  the  head  is  greater 
than   in   the   neighboring   locations   and  corrugation   valleys   are  thus   formed. 


Report  by  F.  E.  King,  J.  Kalousek 


619 


TABLE    III 


Plasticity   Limits    for   Various   Rail 
Materials    and   Rolling   Conditions 


Plasticity  limits  q  , 

psi)  for 

rail  hardness  ranges  of:            | 

250-270 

310-330 

360-380 

BHN 

BHN 

BHN 

Case  of  pure  rolling 

(tangent  track) 

250,000 

305,000 

365,000 

Case  of  rolling  with 

lateral  tractive  forces 

(curves) 

185,000 

225,000 

275,000 

Remedial  Action 

Remedial  action  required  to  correct  both  gauge  face  wear  and  corrugations  must 
be  optimized  in  such  a  way  that  the  maxinuun  service  Hfe  of  rails  and  \\heels  is 
realized. 

Gauge  face  wear  may  be  best  alle\ iated  by  correcting  \ehicle  tracking  deficien- 
cies. The  first  deficiency  arises  from  the  fact  that  wheel  profiles  do  not  ha\e  sufficient 
conicit\'  to  steer  the  wheelset  around  most  curves  without  flanging.  The  second 
tracking  deficiency  is  that  vehicle  trucks  are  not  designed  to  allow  the  axles  to  align 
themselves  radially  in  curves.  To  correct  for  head  flow  and  corrugations,  it  is 
necessary  to  prevent  reverse  curvature  on  the  outside  of  the  wheel  tread  from 
running  on  the  top  of  the  rail.  This  can  be  done  by  reducing  or  eliminating  the 
reverse  curvature  on  the  tread  of  the  wheel  and  by  close  control  of  excessive 
flangeway  clearance  whether  due  to  gauge  face  wear,  wide  gauge  or  wheel  flange 
wear. 

The  experience  of  the  two  major  Canadian  railways  indicates  that  the  following 
remedial  measures  also  have  considerable  merit  and  should  be  incorporated  into 
the  remedial  action  program.  These  are: 

(a)  Judicious  use  of  flange  oilers  to  reduce  wear.  Under-  and  over-lubrication 
of  track  has  a  negative  eftect  on  rail  life.  Under-lubrication  leads  to 
excessive  gauge  face  wear  and  o\er-luI)rication  leads  to  early  occurrence 
of  rail  corrugations. 

(b)  The  use  of  rail  steel  with  higher  yield  point  to  reduce  gauge  face  wear, 
head  flow  and  effects  of  surface  fatigue.  The  wear  rate  of  steel  is  indirectly 
proportional  to  hardness,  the  load  required  to  produce  yield  is  proportional 
to  the  cube  of  rail  yield  strengdi  and  the  resistance  to  surface  fatigue  is 
approximately   proportional    to    second   power   of   rail   hardness. 

(c)  Timely  grinding  of  the  rail  head  to  remove  existing  cornigations  before 
these  become  so  deep  that  grinding  becomes  inefi^ective. 


620 


Bulletin  658 — American  Railway  Engineering  Association 


(d)  Avoidance  of  overspeed  or  underspeed  in  curves  as  this  aggravates  all  wear 
conditions. 

For  convenience,  recommended  remedial  actions  are  given  in  the  accompanying 
tabulation. 

Function    Responsible 
For   Applying   Action 

Equipment 


Remedial  Action 
Buy   and   maintain   all 
wheels  to  a  special  profile 
with    increased    conicity. 


2.  Eliminate  reverse  curva- 
ture on  outside  of  wheel 
tread. 

3.  Develop  and  use  a  truck 
with  improved  curving 
properties. 

4.  Maintain  close  control  of 
wide  gauge  in  curves. 

5.  Maintain  and  optimize 
the  use  of  existing  flange 
oilers. 

6.  Use  rail  steel  with  higher 
yield  point  and  hardness. 

7.  Grind  rail  corrugations. 

8.  Avoid  overspeed  or  un- 
derspeed in  curves. 


Purpose  of  Action 
To  reduce  gauge  face  wear 
on  high  rail  in  curves.  Also 
increases  wheel  life  and  re- 
duces head  flow  and  corru- 
gations on  low  rail. 
To  reduce  or  eliminate  head 
flow  and  corrugation  on  the 
low  rail  in  curves. 
Eliminate   or   reduce   gauge 
face  wear.  Also  reduces  head 
flow  and  corrugation. 
Eliminate  or  reduce   head 
flow  and  corrugation. 
Reduce  gauge  face  wear. 


Reduces  gauge  face  wear, 
head  flow  and  effects  of  sur- 
face fatigue. 

Remove    existing    corruga- 
tions. 
Aggravates  all  conditions. 


Equipment 

Equipment      (with 
technical    research ) 

Engineering 

Engineering 

Engineering 

Engineering 
Transportation 


CONCLUSION 


The  mechanisms  causing  rail  wear  and  tear  have  been  described.  Effective 
remedial  action  is  possible  but  requires  a  concerted  effort  by  the  engineering,  equip- 
ment and  transportation  functions.  There  is  no  "quick  fix"  that  can  be  bought  and 
applied.  Moreover,  it  must  be  realized  that  although  effective  action  can  be  initiated 
almost  immediately,  it  may  be  some  time  before  the  full  benefits  can  be  assessed. 
However,  if  no  action  is  taken,  the  situation  will  not  improve  or  go  away,  it  can 
only  deteriorate.  If  we  wish  to  move  bulk  commodities  economically  in  unit  trains, 
we  must  attack  the  problem  in  an  organized  manner. 


High-Strength  Chromium-Molybdenum  Rails 

77-658-9 


By  Y.   E.  SMITH,  J.  M.   SAWMILL,  JR., 
W.  W.   CIAS,   G.  T.   ELDIS 

ABSTRACT 

A  laboratory  study  was  conducted  with  tlie  aim  of  developing  an  as-rolled 
rail  of  over  100  ksi  (689  N/mm")  yield  strength.  A  series  of  compositions  providing 
both  pearHtic  and  bainitic  microstructures  was  evaluated.  A  fine  pearlitic  structure 
was  developed  in  a  0.73%  C  —  0.83%  Mn  —  0.16%  Si  —  0.75%  Cr  —  0.21%  Mo  steel 
by   simulating   the   mill   cooling   rate   of   132-lb/yd    (65.5-kg/m)    rail. 

Two  100-ton  commercial  heats  were  made  of  tliis  approximate  composition  and 
processed  into  132-lb/yd  (65.5-kg/m)  rail.  Samples  tested  in  the  laboratory  ranged 
from  109  to  125  ksi  (750  to  860  N/mnr)  in  yield  strength.  The  chromium- 
molybdenum  rails  also  exhibited  excellent  fracture  toughness  and  fatigue  properties. 
Sections  of  the  rail  were  joined  by  both  flash-butt  welding  and  thermite  welding. 
The  hardness  peaks  produced  in  the  flash-butt  welds  could  be  reduced  by  applying 
either  a  postweld  current  or  an  induction  heating  cycle.  The  high-strengtli  chromium- 
molybdenum  rails  have  been  in  service  for  over  eight  months  in  curved  sections  of 
an  ore  railway  that  carries  over  55  million  gross  long  tons  per  year. 

INTRODUCTION 

One  of  the  outstanding  problems  for  heavily  traveled  railroads  throughout  the 
world  is  an  excessively  high  rate  of  rail  deterioration,  especially  in  curved  sections 
of  track.  The  problem  is  particularly  acute  on  ore  railroads,  where  every  car  is  heavily 
loaded,  and  on  main  lines,  which  are  also  subjected  to  high  gross  annual  tonnages. 
Axle  loadings  now  often  exceed  30  tons,  and  a  high  traffic  volume  at  high  axle 
loadings  can  result  in  the  annual  tonnage  being  in  the  range  of  30  to  55  million 
gross  tons.  At  lower  levels  of  loading,  rails  deteriorate  by  the  classical  mechanism 
of  surface  wear  and  abrasion.  However,  with  a  combination  of  high  loading  and 
high  gross  tonnage,  rails  deteriorate  at  a  much  faster  rate  by  undergoing  plastic 
flow  and  surface  fatigue.^  In  general,  these  two  modes  of  failure  are  best  resisted 
by  increases   in  rail  yield  strength   and   tensile  strength,  respectively.^ 

As  this  study  was  initiated,  most  of  the  commercially  available  alloy  rails  were 
below  100  ksi  (689  N/mm")  yield  strength.^  It  was  the  objective  of  this  work  to 
develop  an  alloy  rail  steel  over  100  ksi  (689  N/mm^)  yield  strength  and  around 
160  ksi  (100  N/mm")  tensile  strength.  These  improved  properties  were  to  be 
achieved  by  balancing  the  alloy  composition  to  obtain  transformation  to  a  fine  micro- 
structure,   with  the  strength  possibly  being  supplemented  by  carbide  precipitation. 

An  additional  objective  of  this  work  was  to  develop  commercially  feasible 
welding  procedures   for  joining  the  high-strength  rails. 

LABORATORY  DEVELOPMENT  OF  RAIL  STEEL 

It  was  recognized  at  the  beginning  of  this  effort  that  processing  a  steel  on  the 
very  small  scale  tliat  is  available  in  the  laboratory  would  have  serious  scale-up 
problems  when  the  results  were  ultimately  applied  to  the  production  of  a  commercial 


Note:   Discussion  open  until  October  16,   1976. 

621 


622  Bulletin  658 — American  Railway  Engineering  Association 

heat  of  I32-lb/yd  (65.5-kg/m)  rail.  Much  consideration  was  given  to  taking  these 
scale-up  problems  into  account  and  making  the  appropriate  adjustments  in  the 
experimental  techniques. 

Experimental  Procedures 

Laboratory  steels  were  made  from  liigli-purity  charge  materials.  Most  of  the 
heats  (those  with  a  "P"  in  the  heat  number)  were  argon-melted  to  prevent  exces- 
sively high  nitrogen  contents  that  occur  as  a  result  of  melting  in  a  small  induction 
furnace.  It  was  later  decided  that  this  precaution  was  not  necessary.  The  heats 
ranged  in  size  from  55  to  75  lb  (25  to  34  kg).  They  were  poured  into  copper 
chilled  tubular  steel  molds.  The  compositions  are  presented  in  Table  1.  The  ingots 
were  forged  and  rolled  in  order  to  produce  bar  stock  for  tensile  specimen  blanks. 
The  specimen  blanks  were  reheated  to  1850  F  (1010  C)  and  cooled  at  rates  to 
simulate  the  cooling  of  132-lb/yd  (65.5  kg/m)  rail  on  a  mill  cooling  bed.  The 
cooling  rate  was  controlled  by  making  bundles  of  bars  to  increase  tlie  thermal  inertia 
accordingly.  The  specific  cooling  schedules  employed  are  described  in  Table  2. 
The  cooling  schedules  included  relatively  slow  cooling  at  lower  temperatures  to 
simulate  the  box-cooling  treatment  normally  given  to  rails  to  avoid  hydrogen-induced 
cracking.  The  tensile  specimen  had  a  M-in.  (13-mm)  diameter  reduced  section  with 
a  2-in.  (51-mm)  gauge  length.  The  strain  rates  were  18  and  120%/hour  in  the  elastic 
and  plastic  ranges,  respectively.  Hardness  tests  and  microstructual  examinations 
were  made  on  the  broken  halves  of  tensile  specimens. 

Laboratory  Results  and  Discussion 

The  tensile  testing  and  hardness  results  that  were  obtained  on  the  control- 
cooled  specimens  are  presented  in  Table  2.  The  microstrucures  are  presented  in 
Figures  1  through  6.  Steel  A  was  included  as  a  base  composition,  representative  of 
commercial  carbon  steel  rail.  The  62  ksi  (427  N/mm")  yield  strength  shown  in 
Table  2  is  typical  for  such  a  product.  The  pearlitic  microstructure  of  Figure  1(a) 
is  also  typical  for  rails  of  this  composition  in  the  as-rolled  condition. 

The  first  experimental  steels  that  were  made  were  designed  to  increase  yield 
strengdi  by  developing  a  bainitic  microstructure.  Steels  C  and  E  represent  different 
approaches  in  developing  this  microstructure  by  using  silicon-molybdenum  and 
chromium-molybdenum  combinations,  respectively.  Vanadium  was  included  in  the 
former,  with  the  aim  of  obtaining  some  precipitation  strengthening.  Upon  employing 
the  conventional  rail  cooling  cycle  for  132-lb/yd  (65.5-kg/m)  rails,  which  involved 
slowing  the  cooling  rate  at  1000  F  (535  C),  yield  strengths  of  106  to  119  ksi  (731 
to  820  N/mm^)  were  produced.  The  microstructure  of  Steel  C,  in  Figure  1(b), 
is  completely  bainitic,  while  that  of  Steel  E,  in  Figure  2(a),  is  largely  bainite  with 
some  fine  pearlite.  An  attempt  was  made  to  adjust  the  cooling  schedule  of  Steel  C 
to  increase  the  probability  of  attaining  precipitation  strengthening.  A  pair  of  speci- 
mens were  subjected  to  the  same  initial  cooling  rate,  but  the  slower  cooling  rate 
(to  simulate  box  cooling)  was  begun  at  1100  F  (595  C).  The  resulting  yield  strength 
of  140  ksi  (965  N/mm")  suggests  that  some  precipitation  strengthening  may  have 
been  developed.  The  microstructure,  shown  in  Figures  2(b)  and  5(a),  is  a  mixture 
of  fine  pearlite  and  bainite. 

In  general,  the  bainitic  compositions  offer  promising  yield  strengths,  but  there 
was  much  concern  regarding  tlie  relatively  low  transformation  temperatures  involved. 
Since  rails  are  normally  transferred  to  the  cooling  box  by  a  magnetic  crane,  trans- 
formation must  be  substantially  complete  around  1000  F   (535  C).  As  a  result  of 


High-Strength  Chromium-Molybdenum  Rails  623 

this   requirement,   further   efforts   were   directed   toward   developing  pearlitic   micro- 
structures   that  would   form  at  higher  temperatures. 

A  pearlitic  microstructure  was  attained  by  reducing  the  molybdenum  content 
of  Steel  E.  It  may  be  recalled  [Figure  2(a)]  tliat  Steel  E  exhibited  a  partially 
pearlitic  microstructure.  In  general,  of  the  alloying  elements  in  Steel  E,  molybdenum 
is  the  strongest  in  its  influence  on  shifting  the  pearlite  nose  to  the  right  in  the 
continuous-cooling  transformation  diagram.  Reducing  the  molybdenum  to  0.31%, 
and  cooling  according  to  the  established  schedule,  produced  the  very  fine  pearlitic 
microstructure  of  Steel  J  showoi  in  Figures  3(a)  and  5(b).  It  is  unresolvable  at 
a  magnification  of  XIOOO,  but  clearly  defined  by  the  carbon  replica  at  X5000.  The 
steel  has  a  yield  strength  of  126  ksi  (869  N/mm^)  and  a  hardness  of  388  HE. 

As  this  study  was  being  performed,  tliere  was  conflicting  information  from 
various  sources  as  to  the  actual  cooling  rate  of  132-lb/yd  (65.5  kg/m)  rail,  in  the 
high  temperature  range  prior  to  box  cooling.  At  one  point,  the  availability  of  new 
information  resulted  in  a  change  from  cooling  schedule  1,  in  Table  2,  to  cooling 
schedule  2.  One  group  of  experimental  steels  was  processed  using  this  slower  cooling 
rate.  It  was  subsequently  determined  that  cooling  schedule  1  was  closer  to  the 
actual  mill  coohng  rate. 

The  investigation  of  the  sensitivity  of  Steel  J  to  variations  in  molybdenum 
content  involved  several  compositions,  including  Steel  M.  The  lower  molybdenum 
content  of  Steel  M,  combined  with  the  slower  cooling  rate  of  cooling  schedule  2, 
resulted  in  tlie  coarser  pearlite  of  Figures  3(b)  and  5(c).  The  yield  strength  of 
87  ksi  (600  N/mm^)  is  consistent  with  the  coarser  pearlite  spacing.  It  was  ultimately 
concluded  that  as  molybdenum  is  reduced  in  this  C-Mn-Cr-Mo  rail  steel,  at  a  fixed 
cooling  rate,  bainite  disappears  leaving  a  very  fine  pearlite.  As  molybdenum  is 
reduced  further,  the  pearlite  becomes  more  coarse.  Therefore,  the  finest  and  highest- 
strengtli  pearlite  is  obtained  by  employing  the  amount  of  molybdenum  that  is  just 
less  than  that  required  to  produce  bainite.  This  effect  is  demonstrated  by  tiie  speci- 
men of  Steel  M  that  was  cooled  according  to  cooling  schedule  IB  in  Table  2.  The 
hardness  is  415  HB,  while  the  microstructure  (not  shown)  is  almost  completely 
fine  pearlite,  with  a  small  amount  of  bainite.  The  fact  that  this  specimen  was  not 
slow-cooled  in  the  low  temperature  range  is  not  considered  important,  because 
most  of  the  microstructure  was  transformed  by  the  time  the  specimen  reached 
1000  F  (535  C). 

Steels  Q  and  R  were  made  at  0.28%  Mo  to  allow  sufficient  hardenability  to 
obtain  the  finest  pearlite  at  the  slower  cooling  rate  involved.  Vanadium  was  included 
in  Steel  R  in  an  attempt  to  precipitation  strengthen  the  pearlite.  The  optical  micro- 
structures  of  the  two  steels  were  identical.  That  of  Steel  R  is  shown  in  Figure  4(a). 
The  replica  electron  micrographs  of  Steels  Q  and  R  are  presented  in  Figures  6(a) 
and  6(b),  respectively.  The  hardness  of  the  steels  was  similar  at  418  to  430  HB; 
however,  there  was  a  notable  difference  in  yield  strength.  The  higher  yield  strength 
of  Steel  R  (Table  2)  is  apparently  attributable  to  the  vanadium,  possibly  due  to 
some  precipitation  strengthening. 

In  the  course  of  planning  for  die  melting  of  a  commercial  heat,  it  was  reaffirmed 
that  the  faster  cooling  rate  of  cooling  schedule  1  in  Table  2  was  more  realistic  for 
132-lb/yd  (65.5  kg/m)  rail.  Steels  S  and  T  were  prepared  with  die  goal  of  finalizing 
the  molybdenum  content  for  the  commercial  heat,  aiming  for  a  minimum  yield 
strength  of  100  ksi   (758  N/ninr)   in  an  as-rolled  rail.  Steels  S  and  T,  with  0.21 


624  Bulletin  658 — ^American  Railway  Engineering  Association 


and  0.24%  Mo,  respectively,  satisfied  the  yield  strength  requirement.  The  fine 
pearlitic  microstructure  of  Steel  S  is  shown  in  Figures  4(b)  and  6(c).  On  the  basis 
of  these  results,  it  was  decided  to  proceed  with  a  commercial  mill  trial. 

COMMERCIALLY  PRODUCED  CHROMIUM-MOLYBDENUM  RAIL 

Production  and  Evaluation  Procedures 

The  first  trial  production  heat  of  tlie  newly  designed  composition  of  chromium- 
molybdenum  rail  was  made  at  CF&I  Steel  Corporation.  The  100-ton  BOF  heat 
(Heat  11406)  was  aluminum-killed  and  poured  into  twenty-one  5-ton  ingot  molds 
with  hot  tops.  Six  of  the  ingots,  Numbers  3,  5,  7,  13,  15,  and  17,  were  treated  with 
Hypercal,  a  Ca-Si-Al  deoxidation  agent,  added  in  the  amount  of  6  lb/ton  (2.7  kg/ 
ton)  in  an  effort  to  improve  fracture  toughness  by  affecting  the  type,  amount,  and 
distribution  of  nonmetallic  inclusions.  The  ingots  were  soaked  and  then  directly 
rolled  into  132-lb/yd  (65.5-kg/m)  rail  in  31  passes.  Five  rails,  designated  A  through 
E  in  sequence  from  the  top  to  the  bottom  of  the  ingot,  were  obtained  from  each 
ingot.  The  hot-rolled  rails  were  hot-sawed  and  deposited  on  the  cooling  bed  until 
they  were  placed  in  a  cooling  box  in  the  usual  manner  to  prevent  flake  cracking. 

Samples  of  the  chromium-molybdenum  rail  were  subjected  to  a  thorough  labo- 
ratory evaluation,  including  metallography,  tensile  testing,  hardness,  and  fracture 
toughness  testing.  The  laboratory  techniques  were  the  same  as  those  employed  in 
tlie  above-described  evaluation  of  laboratory  steels.  The  fracture  toughness  test 
specimens  were  taken  from  the  web  section  of  the  rails.  Compact  tensile  specimens 
were  prepared  so  that  the  direction  of  crack  propagation  was  perpendicular  to  tlie 
rolling  direction. 

On  the  basis  of  the  satisfactory  properties  of  tlie  first  heat,  a  second  heat  of 
similar  size  was  melted.  The  second  heat  (Heat  12547)  was  the  same  as  the  first 
in  both  composition  and  melting  practice.  However,  no  Hypercal  treatment  was 
used,  as  it  was  not  considered  necessary  for  obtaining  satisfactory  properties. 

Commercial  Product  Results  and  Discussion 

The  composition  of  two  commercial  heats  of  chromium-molybdenum  rail  is 
showTi  in  Table  1.  The  mechanical  property  results  presented  in  Table  3  confirm 
that  the  desired  level  of  strength  was  attained.  The  rail  head  hardness  is  about  340 
to  360  HB,  and  the  yield  strength  is  in  the  range  of  109  to  125  ksi  (751  to  865 
N/mm").  It  was  initially  suspected  that  a  difference  in  prior  austenite  grain  size 
was  the  reason  for  a  lower  molybdenum  level  being  sufficient  for  producing  the 
desired  properties  in  the  commercial  heat.  If  tlie  commercial  heat  had  a  larger 
austenite  grain  size  than  the  laboratory  heats,  this  would  account  for  an  increment 
of  hardenability.  Most  of  the  laboratory  steels  had  austenite  grain  sizes  of  ASTM 
6  or  7,  with  the  average  being  ASTM  6.5,  as  determined  by  the  fracture  grain  size 
technique.  A  specimen  from  Heat  11406  was  tested  the  same  way  and  found  to 
be  ASTM  6.  This  grain  size  is  consistent  with  the  fact  that  the  heat  was  aluminum 
deoxidized,  but  it  leaves  unexplained  the  apparent  difference  in  hardenability  be- 
tween the  laboratory  and  commercial  steels.  Another  possible  explanation  for  the 
difference  is  that  the  laboratory  specimens  are  cooled  from  a  reheat,  while  the 
commercial  rails   are   cooled  directly  from  hot-rolling. 

A  Hypercal  inoculation  treatment  was  given  to  several  ingots  of  tlie  first  com- 
mercial heat.  This  calcium-silicon-aluminum  deoxidation  agent,  which  was  added 
in  the  amount  of  6  lb   (2.7  kg)  per  ton,  had  a  significant  effect  on  the  shape  of 


High-Strength  Chromium-Molybdenum  Rails  625 

sulfide  inclusions,  as  shown  in  Figure  7.  However,  the  fracture  toughness  results 
for  Rails  4B  and  5C  in  Table  3  show  that  the  fracture  toughness  was  not  affected 
by  the  change  in  inclusion  shape.  This  is  presumably  because  the  fracture  direction 
was  perpendicular  to  the  elongated  inclusions.  Tests  were  conducted  in  this  direc- 
tion because  it  is  die  direction  of  crack  propagation  for  rail  failure. 

It  should  be  noted  that  the  fracture  toughness  of  Rail  IOC  of  Heat  12547  is 
notably  higher  than  the  fracture  toughness  measured  on  the  rails  from  Heat  11406. 
This  Kie  value  of  43.5  ksiViny  (47.8  MN/m'''=)  for  Rail  IOC  is  at  the  level  of 
fracture  toughness  normally  found  in  lower  strength  carbon-manganese  rails  tliat 
are  vacuum  degassed.  Rail  IOC  also  has  higher  elongation  and  reduction  in  area 
values  than  were  observed  on  the  first  heat.  It  may  be  observed  that  the  elongation 
and  reduction  in  area  values  obtained  for  the  first  commercial  heat.  Heat  11406, 
are  low  relative  to  the  test  results  on  the  laboratory  steels.  On  the  basis  of  the 
laboratory  results,  it  is  suggested  that  the  higher  ductility  and  fracture  toughness 
values  exhibited  by  Rail  IOC  from  Heat  12547  are  more  representative  of  what  should 
be  expected  of  the  chromium-molybdenum  rail.  Additional  commercial  product 
tiiat   was   produced   as   this   paper  was   being  reviewed  confirmed  this   conclusion. 

Representative  microstructures  of  the  chromium-molybdenum  rail  are  presented 
in  Figures  8  and  9.  The  rail  head  is  very  fine  pearlite,  as  were  tlie  laboratory  steels. 
The  web  and  flange  (not  shown)  are  both  predominantly  fine  pearlite,  with  some 
bainite.  Also,  near  the  center  of  the  web,  occasional  tliin,  light  streaks  may  be 
observed  in  the  microstructure,  as  marked  in  Figure  10.  These  streaks  were  found 
to  be  cross  sections  of  very  thin  martensitic  regions  that  lie  in  the  plane  of  the  web. 
It  was  established  by  electron  probe  microanalysis  tliat  these  martensitic  regions  are 
rich  in  chromium  and  manganese.  They  are  apparently  regions  of  interdendritic 
segregation  in  the  ingot.  It  should  be  noted  that  the  compact  tensile  specimens 
that  were  employed  for  the  fractvire  toughness  determination  were  taken  from  the 
web  of  Rail  IOC,  from  which  the  sample  shown  in  Figure  10  was  cut.  The 
martensite  probably  did  not  aftect  the  Kic  value  because  of  tlie  small  amount  present 
and  its  anisotrojjic  distribution  in  the  plane  of  the  web.  For  the  same  reasons,  these 
thin  regions  of  martensite  are  believed  to  have  a  negligible  influence  on  the  otlier 
mechanical  properties  of  the  rail. 

The  distribution  of  the  hardness  over  a  rail  cross  section  is  shown  in  Figure  11. 

A  short  section  of  chromium-molybdenum  rail  was  subjected  to  a  rolling  contact 
fatigue  (cradle  rolling  load)  test  at  the  AAR  Technical  Center.  The  test  employs 
a  single,  full-size  wheel  under  a  50,000-lb  (22,400-kg)  load  that  is  intended  to 
simulate  a  50%  overload  condition.  The  test  normally  produces  shelling  in  standard 
carbon-manganese  rails  in  3-million  cycles.  The  test  on  the  chromium-molybdenum 
rail  was  discontinued  after  5-million  cycles,  with  no  significant  deterioration  of  the 
rail,  as  determined  by  ultrasonically  testing  each  week  during  the  test. 

The  abrasive  wear  resistance  of  the  head  of  a  chromium-molybdenmn  rail  was 
evaluated  by  a  pin  abrasion  test.*  The  weight  loss  was  0.095  gram,  which  was  88% 
of  the  weight  loss  sustained  by  the  head  of  a  standard  AREA  carbon  steel  rail. 

WELDING  OF  CHROMIUM-MOLYBDENUM  RAILS 

Flash-Butt  Welding 

To  evaluate  the  weldability  of  the  chromium-molybdenum  rail,  several  132-lb/yd 
(65.5  kg/m)  sections  were  flash-butt  welded  by  Chemetron  Corporation.  One  weld 
was  subjected  to  a  postweld  current  that  slowed  the  cooling  rate  after  flashing,  in 


626  Bulletin  658 — American  Railway  Engineering  Association 

orcU-r  to  promote  thf  formation  of  higher  temperature  transformation  products  and 
thereby  limit  the  presence  of  martcnsite.  As  an  additional  effort  to  improve  weld- 
zone  properties,  one  of  the  welds  that  was  made  according  to  the  standard  flash 
cycle  was  sent  to  Teleweld,  Inc.,  for  an  induction  tempering  treatment.  Preliminary 
laboratory  tests  defined  the  time-temperature  parameters  required  for  tempering. 
The  welds  tliat  were  produced  by  the  above  three  procedures  were  sectioned  and 
evaluated  by  hardness  traverses,  metallographic  methods,  and  bend  testing. 

Tempering  would  normally  be  perfonned  after  the  weld  had  cooled  to  tem- 
peratures near  ambient,  but  induction  heating  could  be  used  earlier  in  the  operation 
to  interrupt  cooling.  This  procedure  was  evaluated  by  laboratory  simulations. 

A  Schlatter  flash-welding  unit  with  an  NCG  Sciaky  control  was  employed  in 
performing  the  flash-butt  welding  operations  at  Chemetron.  Preheating  was  accom- 
plished by  10  current  impulses  of  about  95,000  amperes  and  3  to  3.5  seconds 
duration,  separated  by  0.5  second.  Flashing  took  place  in  24  to  37  seconds  followed 
by  application  of  the  upset  force  that  produced  the  weld.  A  current  of  95,000 
amperes  was  held  for  2.5  to  3.0  seconds  after  the  initiation  of  upset,  with  the  upset 
force  being  held  for  9  seconds.  Up  to  this  point,  the  procedure  was  typical  of  that 
normally  used  to  weld  132-lb/yd  (65.5  kg/m)  rail.  After  shearing  off  the  flash, 
the  electrodes  were  put  back  in  place,  in  the  case  of  the  weld  that  was  to  receive 
the  postweld  current.  A  current  of  95,000  amperes  was  applied  for  a  5-second 
duration  exactly  60  seconds  after  the  beginning  of  upset. 

To  define  an  appropriate  tempering  heat  treatment,  sections  were  cut  from 
the  head  of  a  flash-butt  weld  performed  by  the  normal  procedure,  and  short-time 
tempering  treatments  were  performed  on  the  sections  in  a  lead  bath.  It  was  deter- 
mined from  a  Larson-Miller  plot  that,  for  a  15-second  hold  time,  a  tempering 
temperature  of  1230  F  (665  C)  would  be  required  to  reduce  the  maximum  weld 
hardness  to  41  HRC  and  a  tempering  temperature  of  1280  F  (690  C)  would  be 
required    to    reduce    the    maximum    hardness    to    40    HRC. 

Having  defined  the  desirable  tempering  temperature,  another  flash-butt  weld 
that  was  performed  by  die  standard  procedure  was  sent  to  Teleweld  for  a  full-scale 
tempering  experiment.  Two  induction  heating  coils  were  constructed  and  connected 
in  series,  at  Teleweld,  to  simulate  induction  tempering  at  two  adjacent  stations  in 
a  flash- welding  operation.  The  16- turn  coils  were  wrapped  around  the  entire  rail 
cross  section,  separated  by  %  in.  ( 13  mm )  from  the  head  and  edges  of  the  flange. 
One  coil  was  centered  on  the  weld.  The  35-kva  power  supply  was  capable  of 
delivering  an  AC  current  of  300  amperes  at  120  volts  and  1000  Hertz.  The  first 
application  of  power,  for  2.5  minutes,  heated  the  rail  to  780  F  (415  C),  as  measured 
by  a  thermocouple  on  top  of  the  head.  The  power  was  then  turned  off  for  1  minute 
to  simulate  cooling  of  the  rail  as  it  was  moved  to  the  second  induction  heating 
station.  The  power  was  then  applied  for  2.5  minutes  more  to  develop  a  peak  tem- 
perature of  1260  F   (680  C).  The  weld  was  then  air-cooled  to  room  temperature. 

Evaluation  of  Flash-Butt  Welds 

A  weld  hardness  profile  that  was  obtained  by  making  a  traverse  across  a  flash- 
butt  weld  on  a  cross  section  of  the  rail  head  is  presented  in  Figure  12.  This  hard- 
ness profile  is  for  the  standard  welding  procedure,  which  is  shown  to  produce  a 
hardness  peak  of  about  8  to  10  HRC  points  above  the  base-metal  hardness  and  a 
hardness  trough  of  about  6  to  7  HRC  points  in  the  heat- affected  zone  (HAZ)  of 
the  weld. 


High-Strength  Chromium-Molybdenum  Rails  627 

The  variation  in  carbon  content  near  the  fusion  line  was  determined  from  slices 
approximately  0.02  in.  (0.5  mm)  thick  that  were  sectioned  from  near  tlie  weld 
line  of  the  head.  These  results  are  also  presented  in  Figure  12  and  show  that 
decarburization  occurs  during  flashing.  The  lower  carbon  content  of  this  center 
region  prevents  the  formation  of  martcnsite,  allowing  the  hardness  at  the  center 
of  the  weld  to  be  about  eciual  to  the  original  rail  liardness.  Within  less  than  an 
inch  from  the  weld  centerline,  the  hardness  is  unaffected  by  the  welding  operation. 
The  hardness  peak  just  outside  the  weld  line  is  caused  by  partial  transformation 
to  martensite.  The  adjoining  hardness  trough  is  a  manifestation  of  the  spheroidization 
of  pearlite  in  the  region  that  was  heated  to  a  peak  temperature  just  short  of 
austenitization.  The  full  cross  section  of  the  web  of  the  weld  made  by  the  standard 
procedure  is  shown  in  Figure  13(a).  The  white  streaks  highlight  tlie  martensite 
that  forms  upon  cooling  from  welding.  One  of  the  martensite  streaks  is  shown  at 
higher  magnification  in  Figure  14(a).  The  eff^ects  of  a  postweld  current  on  the 
hardness  profiles  through  the  weld  in  various  parts  of  the  rail  are  shown  in  Table  4. 
The  maximum  hardness  is  somewhat  reduced  by  this  treatment.  The  cross  section 
of  the  web  of  the  weld  subjected  to  the  postweld  current  is  shown  in  Figure  13(b). 
The  cooling  delay  introduced  by  this  additional  heating  step  reduced  the  martensite 
at  the  hardness  peak  to  about  5%. 

The  weld  hardness  profile  that  results  from  postweld  tempering  is  presented 
in  Figure  15.  The  corresponding  profile  for  the  untempered  weld  is  also  shown 
in  tliis  figure  for  reference.  The  induction  tempering  treatment  was  successful  in 
lowering  the  hardness  peaks.  The  structure  of  the  weld  was  similar  to  that  of  the 
standard  flash-butt  weld  [Figure  13(a)]  except  that  tlie  streaks  which  had  appeared 
white  in  the  untempered  weld  [Figure  14(a)]  were  gray  in  the  tempered  weld 
[Figure  14(b)]. 

Brinell  tests  were  performed  in  the  above  three  welds  on  top  of  the  head  where 
the  Rockwell  traverses  had  indicated  that  the  hardness  was  at  a  maximum.  The 
flash-butt  welds  that  received  standard,  postweld  current,  and  tempering  treatments 
exhibited  maximum  Brinell  hardness  values  of  415,  371,  and  368  HB  at  distances 
from  the  weld  line  of  0.35,  0.25,  and  0.38  in.  (9,  6,  and  10  mm),  respectively. 
Thus,  Brinell  tests  performed  on  top  of  the  head  could  be  used  as  a  check  on  the 
welding   operation. 

Bend  specimens,  of  rectangular  cross  section,  were  cut  from  the  rails  at  the 
junction  of  the  web  and  the  flange,  with  each  of  the  three  types  of  welds,  (a) 
standard  weld,  (b)  postweld  current,  and  (c)  tempered  weld.  The  specimens  were 
cut  longitudinal  to  the  rails,  with  the  weld  lines  at  the  centers  of  the  specimens. 
The  specimens  were  tested  in  three-point  bending  at  slow  strain  rates,  with  the 
maximum  load  being  used  to  calculate  the  fracture  stress,  by  the  formula  that 
describes  the  bending  of  a  simple  rectangular  beam.  The  fractvire  stresses  are  pre- 
sented in  Table  5. 

Laboratory    Simulation    of   Interrupted   Cooling   by   Induction   Heating 

Induction  tempering  would  be  performed  on  welds  that  had  cooled  below  tlie 
martensite  transformation  temperature.  This  temperature  is  normally  not  reached 
until  at  least  20  minutes  after  upset.  If  induction  heating  is  used  earlier  in  tlie 
flash-butt  welding  operation,  martensite  will  not  form  becau.se  cooling  can  be  inter- 
rupted to  force  nearly  complete  transformation  to  fine  pearlite.  In  a  laboratory 
experiment  to  evaluate  the  feasibility  of  tliis  approach,  chromium-molybdenum  rail 
sections  were  heat-treated  using  programs  that  approximated  the  thermal  cycle  of 


628  Bulletin  658 — American  Railway  Engineering  Association 

the  high-temperature  region  of  a  flash-butt  weld,  plus  several  heating  cycles  obtain- 
able with  postweld  induction  heating  equipment.  Examples  of  the  thermal  cycles 
used  are  shown  in  Figure  16  and  listed  in  Table  6.  Since  flash-butt  welds  are 
normally  performed  at  a  rate  of  about  2.5  to  6  minutes  per  weld,  these  heat 
treatments  cover  the  range  of  anticipated  production  conditions  if  induction  heating 
is  applied  at  tlie  fourth  station  (flash  welding  being  the  first  station).  The  results 
shown  in  Table  6  show  that  all  specimens  heated  above  1100  F  (595  C),  regardless 
of  the  time  at  which  heating  was  initiated,  exhibited  a  hardness  of  less  tlian  37 
HRC  or  370  HB.  The  levels  of  hardness  and  martensite  content  measured  in  the 
normal  weld  thermal  cycle  ( No.  1 )  are  higher  than  the  maximum  levels  measured 
in  the  actual  flash-butt  welding  of  chromium-molybdenum  rail  because,  during 
simulation,  plastic  deformation  and  decarburization  were  not  operative;  thus,  the 
hardness  and  martensite  levels  presented  in  Table  6  are  probably  higher  than  the 
levels  anticipated  in  actual  flash-butt  welds  that  are  induction  heated  at  the  fourth 
station.  The  results  of  Table  6  also  show  that  there  is  a  wide  range  of  times  ( between 
5  and  15  minutes  after  upset)  at  which  induction  heating  could  be  initiated  to 
significantly  reduce  the  hardness  and  amount  of  martensite  in  a  flash-butt  weld. 
Of  course,  if  induction  heating  is  applied  later  in  the  operation,  any  martensite  that 
formed  would  be  tempered,  as  discussed  previously. 

In  general,  the  postweld  current  and  induction  heating  treatments,  used  either  to 
interrupt  cooling  or  temper  the  weld,  appear  to  be  technically  feasible  means  of 
lowering  the  hardness  peaks  in  chormium-molybdenum  rail  flash-butt  welds.  The 
postweld  current  treatment  could  be  performed  on  existing  welding  units  without 
modification.  However,  this  treatment  lengthens  the  welding  cycle  by  as  much  as 
3  minutes,  depending  upon  tlie  specific  procedure  used,  and  would  therefore  reduce 
flash-butt  welding  productivity  accordingly.  On  the  other  hand,  induction  heating 
would  require  the  addition  of  heating  coils  at  other  stations  downstream  from  the 
flash-welding  operation,  but  would  allow  maintaining  welding  productivity. 

THERMITE  WELDING 

Welding  Procedure 

Several  chromium-molybdenum  rails  of  Heat  12547  were  welded  by  the  Perm 
Central  Transportation  Company  using  the  Boutet  thermite  welding  process.  The 
ends  to  be  welded  were  aligned  with  a  1-in.  (25-mm)  gap  between  them.  Ceramic 
mold  sections  were  placed  on  both  sides  of  the  rail  ends,  and  a  third  base  section 
covered  the  bottom  of  the  gap.  Clamps  held  the  mold  together,  and  a  sealant  was 
apphed  to  eliminate  the  possibility  of  hot  metal  flow  between  mold  sections  or 
between  the  mold  and  the  rail.  The  rail  ends  were  then  preheated  for  20  to  25 
minutes  by  directing  a  flame  down  through  the  top  of  the  mold.  A  crucible  containing 
the  thermite  mix  was  put  in  place  over  the  mold  after  the  torch  was  removed.  The 
thermite  mix  was  ignited,  and,  after  a  reaction  time  of  about  22  to  28  seconds,  the 
metal  ran  into  the  mold  through  self- tapping  plugs.  After  a  period  to  allow  solidifi- 
cation of  the  weld  metal,  the  mold  was  removed  and  the  risers  knocked  off. 

Evaluation  of  Thermite  Weld 

The  thermite  welds  were  evaluated  by  hardness  traverses  and  metallographic 
inspection,  as  were  the  flash-butt  welds.  In  addition,  the  fusion  zone  was  analyzed 
for  carbon,  and  spectrographic  analyses  were  conducted  for  alloying  elements.  A 
sample  of  the  ferrous  portion  of  the  thermite  mix  was  also  analyzed  to  detect  the 
presence  of  alloying  elements, 


High-Strength  Chromium-Molybdenum  Rails     629 


The  hardness  profile  of  one  of  the  dierniite  welds  is  shown  in  Figure  17.  The 
relatively  flat  hardness  peaks  in  die  HAZ  adjacent  to  die  fusion  zone  are  only  about 
40  HRC,  somewhat  lower  than  those  developed  by  flash-butt  welding.  The  lower 
peak  hardness  and  larger  heat-affected  zones  are  indicative  of  the  higher  heat  input 
and,  thus,  slower  cooling  rate  of  tlie  thermite  weld.  The  soft  region  in  the  fusion 
zone  is  about  VA  in.  (31  mm)  wide,  notably  larger  than  the  soft  spots  developed 
in  the  HAZ  regions  of  flash-butt  welds. 

Replica  electron  micrographs  of  four  representative  points  on  the  hardness 
traverse  are  presented  in  Figure  18.  These  four  locations  are  marked  on  the  hardness 
profile  of  Figure  17  by  the  letters  a,  b,  c,  and  d.  The  fine  pearlite  of  the  unaffected 
base  metal  is  shown  in  Figure  18(a).  The  spheroidized,  softened  region  of  minimum 
hardness  in  the  HAZ  is  shown  in  Figure  18(b).  The  reaustenitized  region  of  the 
HAZ  that  transformed  back  into  fine  pearlite  is  shown  in  Figure  18(c).  Figure 
18(d)  shows  tlie  coarse  pearlite  of  the  fusion  zone  that  is  of  somewhat  lower 
hardness. 

The  fusion  zone  of  the  thermite  weld  is  softer  primarily  because  of  the  lower 
carbon  and  alloy  contents,  as  shown  in  Table  7.  This  region  is  intermediate  in  alloy 
composition  between  the  base  metal  and  Uie  thermite  mixture,  which  contained  no 
alloy  except  for  a  small  amount  of  manganese.  The  hardness  of  this  region  could 
be  brought  up  to  the  level  of  the  base  metal  by  using  a  similarly  alloyed  thermite 
mixture. 

INSTALLATION  OF  CHROMIUM-MOLYBDENUM  RAIL 

The  chromium-molybdenum  rails  from  the  two  CF&I  heats  have  been  placed 
in  service  as  part  of  a  high-strength  rail  test  program  by  the  Mt.  Newman  Mining 
Company  in  Australia.  The  rails  were  installed,  along  with  other  types  of  high- 
strength  rail,  in  specifically  selected  curved  sections  of  track.  This  265-mile  (490-km) 
long  rail  line  is  regularly  traversed  by  130-car  trains  of  iron  ore  cars,  with  a  gross 
weight  of  120  long  tons  each,  divided  among  four  axles.  Ten  trains  per  day  provide 
an  annual  loading  of  about  55  million  gross  long  tons.  The  chromium-molybdenum 
rails   have   thus   far  experienced   eight   months  of  trouble-free   service. 

SUMMARY 

A  series  of  steels  was  prepared  in  the  laboratory,  processed  to  simulate  rail 
cooling,  and  evaluated  for  mechanical  properties.  Yield  strengths  of  up  to  162  ksi 
(1117  N/nim^)  were  obtained,  with  both  pearlitic  and  bainitic  steels  being  investi- 
gated. A  0.73%  C  —  0.83%  Mn  —  0.16%  Si  —  0.75%  Cr  —  0.21%  Mo  steel,  with  a  fine 
pearlitic  microstructure,  exhibited  a  100  ksi    (689  N/nim")    yield  strength. 

Two  100-ton  commercial  heats  were  made  of  this  approximate  composition 
and  processed  into  132-lb/yd  (65.5  kg/m)  rail.  The  yield  strengths  ranged  from 
109  to  125  ksi  (750  to  860  N/nim"),  and  the  fracture  toughness  (Ku-  value)  ranged 
from  36  to  44  ksi \/ in.  (40  to  48  MN/n^'^).  The  microstructure  of  this  product 
was  predominantly  fine  pearlite,  with  small  amounts  of  bainite  in  the  web  and 
flange.  An  accelerated  (high  load)  rolling  contact  fatigue  test  showed  no  significant 
deterioration  after  5-million  cycles. 

Test  welds  were  made  in  commercial  rail  in  both  flash-butt  welding  and 
thermite  welding  processes,  and  laboratory  simulations  demonstrated  the  effective- 
ness of  induction  heating  the  chromium-molybdenum  flash-butt  welds  to  control 
the  microstructure.    Standard  fl^sh-butt  welding  produced  weld  hardness  peaks  of 


630  Bulletin  658 — American  Railway  Engineering  Association 

about  10  HRC  abo\e  the  35  HRC  rail  head  hardness  and  martensite  bands  near  the 
weld  line.  Either  a  postvveld  current  in  the  flash-welding  machine  or  heating  at 
another  station  could  be  used  to  significantly  reduce  the  maximum  hardness  and 
practically  eliminate  the  martensite  bands.  Induction  tempering  of  a  weld  that  was 
flash-butt  welded  using  normal  procedures  also  reduced  the  maximum  weld  hardness. 
Somewhat  lower  hardness  peaks  resulted  from  welding  by  the  Boutet  thermite 
process,  and  tlie  fusion  zone  was  relatively  soft.  The  weld-metal  hardness  could 
be  increased  by  alloying  the  thermite  mixture.  The  high-strength  chromium- 
molybdenmn  rails  have  been  welded  into  curved  sections  of  a  high  gross  tonnage 
ore  railroad. 

ACKNOWLEDGMENTS 

The  authors  would  like  to  recognize  tlie  eflorts  of  several  other  organizations 
tliat  contributed  to  this  work,  including  CF&I  Steel  Corporation,  which  produced  the 
commercial  rail,  Chemetron  Corporation,  Teleweld,  Inc.,  and  Penn  Central  Trans- 
portation Company,  which  performed  the  various  welding  operations,  and  the 
Technical  Center  of  the  Association  of  American  Railroads,  which  conducted  a 
rolling  contact  fatigue  test. 

Witliin  the  Climax  Research  Laboratory,  the  authors  appreciate  the  efforts  of 
Dr.  D.  E.  Diesburg  for  providing  the  fracture  toughness  measurements  and  V.  Biss 
for  electron  microscopy. 

REFERENCES 

1.  R.  G.  Read,  "Rail  for  High  Intensity  Mineral  Traffic,"  Rail  Track  Materials 
Seminar,  B.H.P.  Melbourne  Research  Laboratories,  Clayton,  Victoria,  Australia, 
October   1971. 

2.  I.  Mair,  "Material  Aspects  of  Rail  Design,"  Rail  Track  Materials  Seminar,  B.H.P. 
Melbourne    Research    Laboratories,    Clayton,    Victoria,    Australia,    October    1971. 

3.  S.  Marich,  "Overseas  and  Future  Developments  of  Rail  Steels,"  Rail  Track 
Materials  Seminar,  B.H.P.  Melbourne  Research  Laboratories,  Clayton,  Victoria, 
Australia,   October  1971. 

4.  J.  Muscara  and  M.  J.  Sinnott,  "Construction  and  Evaluation  of  a  Versatile  Abra- 
sive Wear  Testing  Apparatus,"  Metals  Engineering  Quarterly,  May  1972. 


High-Strength  Chromium-Molybdenum  Rails 


631 


Table  1 
Conipos  it  ions  of  Experimental  and  Coniniercial  Kail  Steels 


Steel 

Heat 

Element,  7 

Ingot 

C 

Mn 

Si 

Cr 

Mo 

V 

Al 

N 

P 

S 

A 

P924 

0.75 

0.81 

0.15 

0.05 

0.007 

(0.015)' 

(0.015) 

C 

P928B 

0.74 

0.80 

1.04 

-- 

0.40 

0.09 

0.04 

0.006 

(0.015) 

(0.015) 

E 

P925 

0.75 

0.81 

0.17 

0.73 

0.40 

-- 

0.04 

0.007 

(0.015) 

(0.015) 

J 

P974 

0.78 

0.82 

0.14 

0.75 

0.31 

-- 

(0.04) 

(0.007) 

(0.015) 

(0.015) 

M 

P994B 

0.76 

0.81 

0.14 

0.74 

0.23 

-- 

(0.04) 

(0.007) 

(0.015) 

(0.015) 

Q 

P995C 

0.76 

0.92 

0.14 

0.81 

0.28 

-- 

(0.04) 

(0.007) 

(0.015) 

(0.015) 

R 

P995D 

0.76 

0.92 

0.13 

0.80 

0.28 

0.056 

(0.04) 

(0.007) 

(0.015) 

(0.015) 

S 

1095A 

0.78 

0.88 

0.17 

0.79 

0.24 

-- 

(0.04) 

(0.007) 

(0.015) 

(0.015) 

T 

1096A 

0.73 

0.83 

0.16 

0.75 

0.21 

-- 

(0.04) 

(0.007) 

(0.015) 

(0.015) 

Commercial 

11406 

0.78 

0.84 

0.22 

0.72 

0.18 

-- 

ND*' 

ND 

0.026 

0.022 

Commercial 

12547 

0.77 

0.89 

0.20 

0.76 

0.16 

-- 

ND 

ND 

0.014 

0.034 

Numbers  in  parentheses  are  aim  compositions,  not  analyzed. 


ND 


not  determined, 


Table  2 

Mechanical  Propertits  of  l^xpcr imental  Steels  Subjected  to  Simulnti'd 
Rail  Cooling  for  132-lb/yd  (65.5-k.g/m)  Rails 


Steel 

Cooling 
Schedule^ 

Hardness, 
HB 

0.27,  Offsrt 

Yield 

Stren>;th, 

ksi  (N/mni^) 

Tensi Ic 
Strength, 
ksi  (N/mm^) 

I'.longat  ion, 

7, 

Reduction 
in  Area, 

7 

A 

1 

-- 

62   (427) 

129   (889) 

12.2 

22 

C 

1 

-- 

106   (731) 

153  (1055) 

10.6 

29 

C 

lA 

-- 

140   (965) 

184  (1269) 

10.8 

25 

E 

1 

-- 

119   (820) 

165  (1138) 

11.6 

31 

J 

1 

388 

126   (869) 

181  (1248) 

13.5 

42 

M 

2 

325 

87   (600) 

152  (1048) 

12.8 

33 

M 

IB 

415 

-- 

-- 

-- 

-- 

Q 

2 

418 

136   (938) 

190  (1310) 

12.6 

41 

R 

2 

430 

162  (1117) 

211  (1455) 

11.5 

37 

S 

1 

361 

120   (827) 

190  (1310) 

12.5 

37 

T 

1 

330 

100   (689) 

163  (1124) 

13.0 

39 

Cooling  Schedules: 

1  Cooled  from  1600  F  (870  C)  to  1000  V    (535  C)  in  18  minutes, 
followed  by  furnace  cooling  from  1000  F  (535  C) . 

lA   Same  cooling  curve  as  above,  with  furnace  cooling  from  1100  F  (595  C) 
IB   Same  cooling  curve  as  (1)  continutd  to  room  tempt  rntiirt  . 

2  Cooled  from  1600  F  (870  C)  to  1000  F  (535  C)  in  22  minutes,  followed 
by  furnace  cooling  from  1000  F  (535  C) . 


632 


Bulletin  658 — American  Railway  Engineering  Association 


XI 


•a 

1— 1 

d) 

■rA 

o 

CO 

3 

pc: 

T) 

O 

H 

H 

3 

Oi 

C 

OJ 

>^  XJ  1 

t— I 

XI 

i—l 

>N 

CO 

1-4 

•f-4 

o 

o 

s 

M 

1 

01 

R 

h 

3 

H 

-^ 

o 

R 

u 

o 

u 

14-1 

x: 

o 

u 

to 

^-^ 

q; 

e 

•H 

'-*^*^ 

4J 

tan 

1-1 

^ 

0) 

1 

a.  ml 

o 

i-i 

in 

PU 

vO 

"^ 

1      •. 

TD      </) 

c^ 

1 

oo 

1 

CM 

CNl 

1 

u   tn  m 

<t 

1 

in 

1 

-J- 

in 

1 

to   OJ  a: 

en 

m 

m 

on 

X   c 

,-^ 

-CM 

tr--. 

MT-l 

^-^ 

y-^ 

,-— ^ 

i^    B 

en 

vO 

00 

01          -^ 

• 

• 

• 

^co'g 

t:^ 

O 

r^ 

m 

;£^ 

<}■ 

4-1    en   ^ 

1 

^.^ 

1 

1 

1 

N_X 

O     OJ 

1 

1 

1 

1 

to    C  ,• 

CO 

o 

m 

i-i  x;   c 

• 

• 

Cl,      {jOl-r-l 

m 

o 

on 

3     ^ 

on 

<}• 

<}• 

O      -r-t 

w 

H    w 

(U 

-:»; 

4-1 

d     - 

P 

O     CO 

0) 

•r-(       QJ 

o  m 

CNl     ^ 

m  1^ 

m  CM 

a 

4-1     J-l 

•     • 

1 

•         • 

1 

• 

1 

o 

o  <  s-s 

m  m 

1 

CO    00 

1 

CNJ     <f 

<f  in 

1 

u 

3 

1—1     r-l 

r-l     r-( 

CM    CNl 

PU 

T3     d 
0)    -I-I 

r-4 

Pi 

to 

O 

1 

•r-t 

CO       - 

d 

00  d 

o  o 

m  in 

O     OvJ 

m  en 

CO 

d  o 

•     • 

1 

•     • 

1 

• 

•     • 

1 

j2 

O    -H    ^S 

CXD   (» 

1 

m  m 

1 

cr\  a\ 

r-4     1-1 

1 

o 

rH     4J 

r-l     r-l 

0) 

W 

S 

•■^  •"X 

•— N   ^^ 

/'"s  y^ 

/— S    ^-N 

^^ 

ON    O 

r-l    r-l 

\D  cn 

a^  \D 

-<Nl 

(X)  cr> 

r^  r^ 

00   o 

CM    O 

0)            -^     g 

r-l    r-l 

CM    CM 

r-l    CM 

CM    CM 

4J      0)     4J      E 

r-l    r-l 

r-l    r-l 

1-1    r-l 

r-l     r-l 

CO    r-l     bO^- 

>^-^   *wX 

1 

\-^  ^-' 

1 

v«^   x_^ 

S— -'    V— ^ 

1 

e  -H  d  s 

1 

1 

•H      tfl     0)    ^^ 

<!-  vo 

OO  en 

o  m 

CM    O 

4J   d  »^ 

•      • 

• 

•       • 

r-l       <U     4-1     T-l 

CM    CNl 

<f  <t 

tN   -Cf 

00  m 

13    H    W     to 

r~  r- 

cx>  00 

r^  r^ 

r^  r^ 

^ 

r-l    1—1 

r-l    r-l 

r-l     r-l 

r-l    t-l 

4J                        <--~- 

^-s  ^-v 

^-^  .—v 

/-N  ^-^ 

/■-v  .'-N 

01                '<N 

<Tl     r-4 

vo  <^ 

r-l  m 

O    vD 

CO            -^6 

<f  m 

^    vO 

in  ^ 

CM    00 

>4-l    -O     AJ      B 

1^     f^ 

00   00 

r^  r^ 

00  r^ 

M-l    r-l      (30^-- 

V— '  v-' 

1 

s»^   ^—^ 

1 

^-^  v»^ 

^^-X    N-X 

1 

O    OJ    d  !a 

1 

1 

•H      QJ    — ^ 

t^  o 

^  on 

O    t3N 

o  o 

6^     >-!      >-l 

• 

•     • 

• 

•      • 

CNJ              4-1    ■r4 

C»    CJN 

m  m 

ON     O 

CTn    <t 

C/3     CO 

o  o 

CVj     CNJ 

O    r-l 

r-4     r-l 

O                      ^ 

r-l    r-l 

r-4    I-I 

r-l    r-l 

rH    r-l 

d    d 

QJ      O 

E    •-" 

T3 

TJ 

T3 

X) 

•rl      4J 

CO 

X 

CO 

^ 

CO 

■     to 

X 

O     CO 

01 

OJ 

0) 

QJ 

QJ 

0) 

QJ 

Q>      O 

X 

2 

ffi 

5 

ffi 

X 

^ 

(X    o 

C/)    1-1 

4J 

d 

r-l 

r-l 

4J      QJ 

CO 

CO 

o    E 

QJ 

o 

o 

QJ 

60    4J 

d 

p 

u 

d 

d    CO 

o 

a; 

OJ 

o 

M     Q) 

z 

a 

a- 

2 

M 

>. 

>N 

H 

X 

X 

d 

r-l 

o 

•H 

PQ 

u 

< 

U 

■H 

CO 

<^ 

in 

m 

o 

4J 

pts 

r-l 

r-l 

(d 

d 

M 

vD 

r^ 

•(-( 

4J 

O 

<}■ 

CO 

CO 

<t- 

m 

a> 

<u 

t-l 

C^J 

p 

X 

1—1 

r-l 

High-Strength  Chromium-Molybdenum  Rails 


633 


Table  4 

Maximum  and  Minimum  Hardness  Measured  in  the 
Region  of  the  Flash-Butt  Weld 


Location 
of  Traverse 

Maximum/Minimum  Hardness,  HRC 

Welded  with 
Standard  Method 

Welded  with 
Postweld  Current 

Top  of  Head 
Center  of  Head 
Web 
Flange 

43.6/31.8 
46.5/29.63 

48.3/29.9 
46.3/29.8 

42.4/26.5 
44.0/25.7 
45.0/29.9 
40.2/28.5 

Average  of  four  traverses. 


Table  5 

Bend  Test  Results  for  Chromium-Molybdenum 
Flash-Butt  Welds 


Type  Weld 

Average  Fracture  Stress, 
ksi  (N/mm^) 

Standard 
Method 

Current  Applied 
after  Upset 

Induction 
Tempered 

216  (1490) 
237  (1630) 
228  (1571) 

634 


Bulletin  658 — American  Railway  Engineering  Association 


Table   6 

Results    of   Hardness   Tests    Pcrfomed   on   Chronium-Molybdenur.i  Rail   Specimens 

Hint   TrL-atid    to   Sinulatc   a    I'lash-U'e  Id   Thc-rrial    CycK'   nnd   '.>i  :'l\ri.nt 

Hcatini;    Cycles    I'sed    to    Interrupt    i:oolin^ 


Peak  Temperature 

Average 

Speciircn 

Cool  in*;  Tine   between 

I'pset   and    Interruption 

of   Coolini;,    rain 

Temperature   at 
Initiation   of   Second 
Heating   Cycle,    F    (C) 

during   Second 
Heating   Cvcle, 
F    (C) 

Hardness 

.Martens  itv  , 

HB 

"- 

HRC 

(3000   kg) 

1 

Simulation  of 

'.s'eld   Therral   Cycle 

55."   1       578 

■5  5 

2 

15 

390    (200) 

1250    (575) 

34.7 

341 

10 

3 

10 

535    (280) 

1280    (695) 

34.1 

326 

10 

■i 

10 

535    (280) 

1150    (620) 

37.6 

366 

5 

5 

10 

525    (275) 

1100    (595) 

39.4 

363 

3 

6^ 

5 

885    (475) 

1255    (680) 

35. S  j       331 

5 

-a 

5 

880    (470) 

1255    (uSO) 

35.2  1       331 

5 

8 

5 

890    (475) 

1035    (555) 

40.7    1       409 

15 

Specimens    6   and    7    were    given   approxiraately    the    same    heat    tre 


Table  7 

Chemical  Compositions  of  Chromium-Molybdenum 

Rail,  Thermite  Mixture,  and  Weld  Zone 

of  Thermite  Weld 


Sample 

Element,    7, 

C 

.Mn 

Si 

P 

S 

Cr 

Mo 

Ni 

Rail 

0.77 

0.89 

0.20 

0,014 

0.034 

0.7  6 

0.16 

na'^ 

Thermite   Mixture 

NA 

0.35 

NA 

NA 

NA 

Nil 

Nil 

0.029 

Weld    Zonp 

0.59 

0.87 

0.32 

NA 

NA 

0.17 

0.09 

NA 

NA  =  not  analyzed 


High-Strength  Chromium-Molybdenum  Rails 


635 


TL   Nital  XIOOO 

(a)  Steel  A--0.75C-0.8lMn-0.15Si  (Base  Composition) 


2%  Nital 


XIOOO 


(b)  Steel  C--0.74C-0.80Mn-l.04Si-0.40Mo-0.09V 
Cooling  Schedule  1 

Figure  1   Experimental  Alloy  Rail  Steels--I 


636 


Bulletin  658 — American  Railway  Engineering  Association 


27c  Nital  XIOOO 

(a)  Steel  E--0.75C-0.8lMn-0.17Si-0.73Cr-0.40Mo 


27o  Nital 


XIOOO 


(b)  Steel  C--0.74C-0.80Mn-l.04Si-0.40Mo-0.09V 
Cooling  Schedule  lA 

Figure  2  Experimental  Alloy  Rail  Steels--II 


High-Strength  Chromium-Molybdenum  Rails 


637 


2%  Nital  XIOOO 

(a)    Steel   J--0.78C-0.82Mn-0.14Si-0.75Cr-0.3lMo 


(b)  Steel  M--0.76C-0.8lMn-0.14Si-0.74Cr-0.23Mo 


Figure  3  Experimental  Alloy  Rail  Steels--III 


638 


Bulletin  658 — American  Railway  Engineering  Association 


2%  Nital  XIOOO 

(a)  Steel  R--0.76C-0.92Mri-0.13SL-0.80Cr-0.28Mo-0.056V 


27o  Nital  XIOOO 

(b)  Steel  S--0.78C-0.88Mn-0.17Si-0.79Cr-0.24Mo 


Figure  4  Experimental  Alloy  Rail  Steels--IV 


High-Stxength  Chromiiim-Molybdemim  Rails 


639 


%!.rf^if:»*'*rf^/r-*»"  .^:-5'*fcak*P^*>s^?^.-.  -:. 


'^'jTV. 


X5000 


(a)  Steel  C--0.74C-0.80Mn-l.04Si- 
0.40MO-0.09V 
Cooling  Schedule  lA 


V. 


X5000 


(b)  Steel  J--0.78C-0.82Mn-0.14Si- 
0.74Cr-0.3lMo 


-A\i.'>i'\V*S\V%vit  .- 


X5000 


(c)  Steel  M--0.76C-0.8lMn-0.14Si- 
0.74Cr-0.23Mo 

Figure  5  Replica  Electron  Micrographs  of  Experimental 

Alloy  Rail  Steels--I 


640 


Bulletin  658— American  Railway  Engineering  Association 


'^f^^^^^'^'^!^!^^ 


■'i^mMMMmm 


X5000 


(a)  Steel  Q--0.76C-0.92Mn-0.14Si- 
0.8lCr-0.28Mo 


X5000 


(b)  Steel  R--0.76C-0.92Mn-0.13Si- 
0.80Cr-0.28Mo-0.056V 


;, 


^S 


X5000 


(c)  Steel  S--0.78C-0.88Mn-0.17Si- 
0.79Cr-0.24Mo 

Figure  6  Replica  Electron  Micrographs  of  Experimental 

Alloy  Rail  Steels--II 


High-Strength  Chromium-Molybdenum  Rails 


641 


XIOOO 


(a)  Rail  4b 


>§• 


XIOOO 


(b)  Hypercal-Treated  Rail  13A 


Figure  7  Typical  Nonmetallic  Inclusions  in  the 
Longitudinal  Web  Sections  of 
Chromium-Molybdenum  Rails 
from  Heat  11406 


642 


Bulletin  658 — American  Railway  Engineering  Association 


X500 


47o  Picral 
(b) 


X5000 


Figure  8   Optical  and  Replica  Electron  Micrographs  of 
the  Longitudinal  Head  Section  of 
Chromium-Molybdenum  Rail  4b 
from  Heat  11406 


High-Strength  Chromium-Molybdenum  Rails 


643 


X5000 


(b) 


Figure  9  Optical  and  Replica  Electron  Micrographs 
the  Longitudinal  Web  Section  of 

Chromium-Molybdenum  Rail  4b 
from  Heat  11406 


644 


Bulletin  658 — American  Railway  Engineering  Association 


47o  Picral 


X500 


Figure  10  Optical  Micrograph  of  Longitudinal  Web  Section 
of  Chromium-Molybdenum  Rail  IOC  from 
Heat  12547  Shoving  Isolated 
Martensite  Streaks 


High-Strength  Chromium-Molybdenum  Rails 


645 


388 


415 


415 


363 


406    393  363    352   363  388   393 


Figure  11   Brlnell  Hardness  Survey  of  the  Cross  Section 
of  Chromium-Molybdenum  Rail  lOC 
of  Heat  12547 


Bill.  058 


646 


Bulletin  658 — American  Railway  Engineering  Association 


25 


20 


DISTANCE  FROM  THE  WELD  LINE,  MM 
15  10  5  0  5  10  15  20  25 

-I \ 1 1 1 1 1 1 r 


45 


40 


-^-~ 


•Q 


HARDNESS 


S   35 


_     O — ■( 


30 


25 


\      / 
\  / 


/ 
/ 
/ 
/ 

/ 
/ 


.-■or' 


,^. 


CARBON 
CONTENT- 


I       I       I I I I L 


1.0 


^ 


o 


V 


'      I      ' I L 


0.9 


0.8 


-  0,7 


1.0 


0.5  0  0.5 

DISTANCE  FROM  THE  WELD  LINE,  IN. 

Figure  12     Hardness  Traverse  on  Sections  Cut  from  the  Head  of  Flash-Butt  Welded 
Chromium-Molybdenum  Rail  5C  from  Heat   11406 


High-Strength  Chromium-Molybdenum  Rails 


647 


47o  Nital  X3.3 

(a)  Welded  Using  Standard  Procedure 


4%  Nital 
(b)  Welded  Using  Postweld  Current 


X3,3 


Figure  13  Macrographs  of  the  Web  Section  in  Flash- 
Butt  Welds  Performed  in  Chromium- 
Molybdenum  Rail 


648 


Bulletin  658 — American  Railway  Engineering  Association 


10%  Potassium  meta-Bisulf ite       X500 
(a)  Welded  Using  Standard  Procedure 


10%  Potassium  meta-Bisulf ite        X500 

(b)  Welded  Using  Standard  Procedure 
and  Induction  Tempering 

Figure  14  Micrographs  of  Martens ite  Bands  in  The  Web 
Section  of  Flash-Butt  Welds  Performed 
in  Chromium-Molybdenum  Rail 


High-Strength  Chromium-Molybdenum  Rails 


649 


25 


20 


DISTANCE  FROM  THE  WELD   LINE,  MM 
15  10  5  0  5  10  15         20 


25 


1 1 1— 

TEMPERED 

--A AT    1260  F 

(680  C) 


40 


35 


30  - 


25  - 


STANDARD 
PROCEDURE 


J I I L 


J I L 


III' I I I L 


1.0 


0.5  0  0.5 

DISTANCE  FROM  THE  WELD   LINE,  IN. 


1.0 


Figure   15     Hardness  Traverses  Located  0.2  Inch  (5  mm)  from  the  Top  of  the  Head  in  Both 
As-Welded  and  Tempered  Flash-Butt  Welds  in  Chromium-Molybdenum 
Rail  4B  of  Heat  11406 


2000 


1500 


9z   1000  - 


500 


I  I  'I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  I  II  I  I  I  I  I 

NORMAL  WELD  THERMAL  CYCLE  (NO.  1) 


-NO.  6 


1200 

1100 

1000 

900 

son 

700 
600 
500 

400 
300 
200 
100 


5      10      15      20      25 
TIME  FROM  START  OF  COOLING,  MIN 


30 


35 


Figure    16    Thermal  Cycles  of  Specimens   Heat  Treated  to  Simulate  a  Flash-Butt  Weld  (No.   1)  and 
a  Flash-Butt  Weld  plus  Different  Postweld  Heat  Treatments  (Nos.   3,  5,  and  6) 

The  numbers  refer  to  the  specimens  listed  in  Table  6. 


650 


Bulletin  658 — American  Railway  Engineering  Association 


CENTIMETERS 

6  8         10       12 

T 


16  24  32  40 

EIGHTHS  OF  AN   INCH 


48 


56 


Figure   17     Hardness  Profile  of  Thermite  Weld   in  Chromium-Molybdenum   Rail 


High-Strength  Chromium-Molybdenum  Rails 


651 


^■^ r!!^ 

X5000 
(a) 


'/  .t  .< 


L£:; 


X5000 
(b) 


X5000 


(c) 


X5000 


(d) 


Figure  18 


Replica  Electron  Micrographs  of  Selected 
Areas  along  Hardness  Profile 
(Figure  17)  of  Thermite 
Weld  in  Chromium- 
Molybdenum  Rail 


652  Bulletin  658 — American  Railway  Engineering  Association 

Innovations  in  Frog  and  Switch  Design 

77-658-10 

By  E.   H.  TAYLOR 

Supervisor  Track   Design   and    Development 
Canadian   Pacific   Rail 

Acknowledgment 

The  author  wishes  to  express  his  sincere  thanks  to  the  following  men  for  tlieir 
cooperation  and  assistance  in  the  development  and  design  of  many  aspects  of  the 
special  trackwork  discussed  herein:  J.  Fox,  chief  engineer,  CP  Rail;  G.  Sinclair, 
engineer  of  tests,  CP  Rail;  C.  N.  King,  retired  senior  engineer,  CP  Rail;  and  E.  Frank, 
chief  engineer,  Abex  Corp.,  Trackwork  Products. 

I  wish  to  express  my  appreciation  for  tlie  invitation  to  speak  on  behalf  of  CP 
Rail  and  to  elaborate  on  tliis  progressive  project — "Innovations  in  Frog  and  Switch 
Design." 

The  purpose  of  this  paper  is  to  outline  the  continuing  development  of  CP  Rail 
in  frog  and  switch  design.  This  development  is  dictated  by  our  requirement  to 
handle  single-track  trafiBc  in  CTC  territory  of  approximately  50  million  gross  tons, 
per  mile,  per  annum  on  our  main  line  west  of  Golden  to  Vancouver  which  traverses 
the  Rocky  Mountains,  Selkirk  and  Cascade  mountain  ranges  with  grades  up  to  2.2% 
and  curvature  up  to  12°.  In  addition  to  the  usual  type  freight  trains,  this  route 
also  handles  our  unit  coal  trains. 

At  present  tliere  are  a  number  of  frog  designs  constructed  in  a  variety  of 
manufacturing  methods  and  materials  with  a  preference  by  many  railroads  for  a 
certain  type  design.  However,  it  is  generally  accepted  that  either  rigid  or  spring 
railbound  manganese  steel  frogs  are  the  most  desirable  frog  type  for  use  in  single- 
track,  heavy-tonnage  main  lines. 

CP  Rail's  investigation  commenced  in  1968  and  was  prefaced  witli  the  following 
criteria:  frog  design,  material,  and  construction.  Our  existing  frog  design  was  to  a 
modified  AREA  heavy-wall  insert  casting  with  the  7-in.  heel  spread.  This  design 
had  been  in  service  for  some  10  years  superseding  the  AREA  light-wall  design  with 
4?4-in.  heel  spread.  This  heavy  wall  designed  frog  in  115-lb  and  132-lb  rail  sections 
had  proven  to  be  adequate  in  most  locations.  However,  with  the  increased  wheel 
loads  and  higher  speeds,  serious  casting  problems  were  becoming  more  apparent. 
This  initially  was  considered  a  material  problem. 

It  is  acknowledged  that  the  use  of  high  manganese  steel  will  provide  the  best 
wearing  surface  and  resistance  to  abrasion  and  deformation  from  heavy  impact  than 
any  otlier  type  materials  for  frog  insert  castings.  In  addition  it  has  been  substantiated 
that  some  form  of  depth  hardening  in  a  manganese  steel  casting  will  substantially 
increase  its  initial  life.  Initial  life  is  defined  as  from  the  first  installation  until 
sufficient  wear  occurs  to  require  rebuilding  by  welding.  Laboratory  tests  conducted 
by  the  AAR  Technical  Center  on  manganese  track  work  castings,  hardened  by  the 
explosive  process,  have  shown  that  hardened  castings  will  resist  wear  and  batter 
in  a  superior  manner   to  unhardened  castings. 

The  two  graphs  on  Fig.  1  show  the  progressive  wear  results  throughout  the  test 
in  the  critcial  areas  on  the  point  and  wing  opposite  the  point  area.  Average  values 
for  three  castings  were  plotted  in  each  category.  It  will  be  noted  tliat  the  rate  of 


Note:   Discussion  oijen  until  October  15,  1976. 


Address  by  E.  H.  Taylor 


653 


70 


60 


50 


§40 

d 

< 
W30 


20 


10 


30 


20 


X. 

<  lOf 


UNHARDENED  casting  (Ave.  3 ) 


EXPLOSIVELY    HARDENED  CASTING  (Ave.  3)  — 


200,000        400,000        600,000        800,000      1,000,000 
CYCLES    OF    ROLLING    LOAD  MACHINE 
AVERAGE  WEAR   ON  POINT 


UNHARDENED  casting  (Ave.  a) 


200,000       400,000        600,000        800,000     1,000,000 
CYCLES    OF   ROLLING    LOAD  MACHINE 

AVERAGE  WEAR  ON  WING-OPPOSITE  POINT 


Fig.  1 — Rolling-load  wear  results  on  manganese  insert  castings. 


654  Bulletin  658 — American  Railway  Engineering  Association 

wear    increased   in    a    manner    approaching    a    straight   line    between   200,000    and 
1,000,000  cycles. 

These  test  results  were  produced  on  a  rolling-load  machine  which  operated  with 
a  30,000-lb  wheel  load  for  1,000,000  cycles.  This  produced  30,000,000  tons  of 
rolling  load  on  each  specimen,  divided  equally  as  to  direction,  which  is  equivalent 
to  a  frog  insert  casting  having  60,000,000  gross  tons  of  traffic.  These  results  repre- 
sent an  expected  initial  frog  insert  service  life  of  approximately  3  to  1 — hardened 
versus  unhardened  manganese  insert  castings. 

On  CP  Rail  all  aspects  of  frog  manufacture  were  tlioroughly  investigated  and 
the  initial  change  was  in  the  adoption  of  the  elastic  stop  nuts  in  place  of  the 
conventional  spring  washer  and  square  nut  with  heavier  designed  rail  headlock  and 
rail  washers.  Laboratory  and  in- track  tests  were  conducted  and  it  was  substantiated 
that  this  lock  nut  under  all  track  conditions  provides  the  best  type  locking  device  to 
resist  back-off  and  reduce  maintenance.  All  special  trackwork  components,  i.e.  frogs, 
diamond  crossings,  switches,  etc.,  are  now  equipped  with  the  heavy  series  elastic 
stop  nuts. 

Based  on  the  results  obtained  from  tliese  investigations  a  series  of  in-track 
frog  tests  were  made  using  standard  No.  13,  132-lb  RE  railbound  manganese  frogs. 
Our  first  test  frogs  were  installed  on  the  Mountain  and  Shuswap  Subdivisions  in 
April  1970.  These  frogs  were  equipped  with  explosive-hardened  and  unhardened 
manganese  inserts  with  standard  carbon  rail.  Regular  field  inspections  were  carried 
out  and  profilometer  readings  were  taken.  After  approximately  18  months  of  service 
and  60  million  gross  tons  of  traffic,  the  standard  frogs  with  unliardened  inserts  at 
certain  locations  were  removed  from  track  due  to  excessive  wear,  primarily  in  the 
point  area  of  wheel  transfer. 

I  would  like  to  draw  your  attention  to  sections  in  B-B  and  C-C  on  Fig.  2. 
These  two  areas  of  wheel  transfer  are  invariably  subjected  to  excessive  wear.  Please 
note  in  section  C-C  the  collapse  in  the  casting  in  the  point  area — standard  unhard- 
ened insert  right-hand  side.  In  general  the  explosive-hardened  frogs  provided  ap- 
proximately 40  months  of  service  and  115  million  gross  tons  of  traffic.  A  number 
of  explosive-hardened  frogs  were  removed  from  track  due  to  manganese  batter  and 
flow — specifically  in  the  area  of  wheel  transition  from  the  wing  to  the  point 
approximately  20  in.  to  22  in.  from  the  M-in.  point.  This  depression  is  tlie  result  of 
the  wheels  with  a  false  flange  running  on  the  wing  of  the  casting,  and  on  cross  over 
dropping  into  the  flangeway  resulting  in  heavy  impact  in  a  very  locafized  area. 
Excessive  rail  flow  developed  in  areas  of  wheel  run-off  from  tlie  manganese  insert, 
point  rail  junction  and  heel  extension  easer. 

Conclusive  results  obtained  from  the  first  series  of  frog  test  installations  indi- 
cated that  standard  railbound  manganese  frogs  with  explosive-hardened  inserts  had 
twice  the  initial  service  life  expectancy  over  frogs  with  unhardened  manganese 
inserts. 

The  magnitude  of  the  possible  savings  involved  provided  the  incentive  to 
continue  this  investigation.  Sample  test  frogs  that  were  removed  from  track  due  to 
service  failures  were  completely  examined.  Rail  flow  on  point  rails  and  wing  rails, 
also  rail  end  batter,  indicated  that  improved  rail  steel  properties  were  positively 
required.  Investigation  into  the  availability  of  improved  rail  steel  that  would  suflBce 
for  special  trackwork  manufacture  indicated  that  two  alternatives  existed — fully 
heat-treated  or  chromium  alloy  rails. 


Address  by  E.  H.  Taylor 


655 


Q 

\  ^ 

0 

]J^ 

z  n 

Z 

o 

H             t 

■^">N      »- 

O 

A  9 

UJ 

1  "y 

(A 

J(fl 

z 

z 

0        \ 

0 

F       ^ 

"-^    ^- 

o 

A  " 

UJ 

}  ^ 

0) 

i  <fl 

656 


Bulletin  658 — American  Railway  Engineering  Association 


MECHANICAL 
PROPERTIES 

AREA  CONTROL 
COOLED    CARBON 

CHROMIUM 

(ALGOMA  CANADA) 

FULLY 
HEAT-TREATED 

(BETHLEHEM   STEEL) 

YIELD 

STRENGTH 

(KSI) 

66-88 

100 

114 

ULTIMATE     TENSILE 

STRENGTH 

(KSI) 

100-138 

160 

172 

ELONGATION 

% 

9-20 

12 

13 

REDUCTION 
AREA   % 

15 

15 

35 

HARDNESS 
BHN 

235-260 

295-325 

315-370 

Fig.  3 — Mechanical  properties  of  commercial  rail  steels. 


Fig.  3  shows  the  comparison  of  mechanical  properties  for  standard  carbon, 
fully  heat-treated  and  chrome  rails.  The  mechanical  properties  for  chrome  rail  are 
not  quite  as  good  as  fully  heat-treated  rail.  However,  chrome  rail  is  available  from 
the  steel  mill  in  Canada  whereas  fully  heat-treated  rail  is  not  available  at  present. 
Subsequent  tests  with  frogs  and  switches  fabricated  with  fully  heat-treated  and 
chrome  rails  substantiated  the  research  recommendations.  Rail  flow  characteristics 
in  all  areas  were  greatly  reduced.  At  present,  on  CP  Rail,  all  special  trackwork, 
i.e.,  switch  points,  stock  rails,  guard  rails,  frogs,  etc.,  are  manufactured  exclusively 
with  chrome  rail. 

A  number  of  defective  unhardened  frog  inserts  were  sectioned  and  shape- 
measured  with  confirming  results  that  the  center  point  section  of  the  casting  in 
the  wheel  transition  area  had  partially  collapsed.  This  was  due  to  the  previously 
mentioned  localized  repeated  wheel  impacts.  Wheel  jump  produced  by  casting  wear 
and  longitudinal  flexing  in  tlie  point  area  of  the  insert  produced  wheel  bounce  with 
related  high  impact  and  repeated  localized  spot  failures. 

Defective  explosive-hardened  frog  inserts  were  also  sectioned  and  found  to  have 
a  number  of  crack  proi^agations  developing  in  tlie  underside  of  the  castings  in  the 
point  area.  These  were  considered  tensile  failures  due  to  excessive  stresses. 

Research  has  shown  that  merely  increasing  the  thickness  of  casting  sections 
where  weaknesses  develop  is  not  necessarily  the  answer.  Mass  does  not  always 
ensure  added  strength.  In  fact,  heavy  mass  will  reduce  the  strength  of  manganese 
castings  because  of  internal  defects  inherent  in  tlie  manufacturing  process  usually 
employed — for  example,  limited  amount  of  feeders,  etc. 


Address  by  E.  H.  Taylor  657 


An  example  of  one  type  of  defect  resulting  from  improper  design  is  the  shrink 
cavity  resulting  from  too  great  a  mass.  The  thinner  sections  and  outer  walls  chill 
and  set  quickly  after  pouring,  while  the  heavy  mass  in  the  interior  is  still  molten. 
As  the  outer  surface  solidifies,  it  draws  on  the  molten  mass  to  fill  the  shrinkage 
and  the  result  is   a  ca\ity   in   the  interior  of  the  large  mass. 

In  addition  to  the  danger  of  shrink  cavities  in  the  regions  of  unequal  sections, 
it  has  been  found  that  thick  sections,  even  though  made  uniform,  may  develop 
internal  defects  during  the  heat-treatment  of  die  casting.  During  the  quench,  the 
chill  from  the  water  on  the  outer  surfaces  will  produce  total  shrinkage  while  the 
interior  of  die  casting  is  still  at  a  high  temperature.  Subsequent  cooling  and  shrink- 
ing of  the  interior  is  likely  to  produce  a  concealed  inner  crack,  or  what  is  known  as 
"inner  check."  In  service,  due  to  repeated  alternating  stresses  from  wheels  loads, 
diis  check  develops  until  it  progresses  to  die  surface  of  the  casting. 

The  conclusions  resulting  from  many  aspects  of  research  in  frog  casting  design 
indicated  that  an  improved  t>"pe  of  manganese  insert  was  a  prime  requirement.  The 
frog  insert  was  redesigned  and  is  shown  on  Hg.  4. 

Fig.  4  shows  t\vo  types  of  manganese  insert  cross  sections.  The  original  test 
frog  inserts  were  constructed  to  the  CP  Rail  modified  AREA  heaxy-wall  design, 
shown  on  the  left-hand  side.  The  cross  section  shown  on  the  right  hand  side  is  a 
modified  integral-base  design  with  a  structure  of  near-uniform  thickness.  The 
\ertical  rib  in  the  point  area  reduces  casting  flexing  and  assists  in  transmitting  the 
wheel  load  to  the  base.  Greater  structural  strength  is  desirable  for  explosive  depth 
hardening,   and  inserts  to  this  design  will  offer  longer  life  in  tlie  rebuilt  condition. 

Diamond  crossings  with  diis  general  casting  design  configuration  and  depdi 
hardening  ha\e  proxided  substantially  increased  serxice  life  over  the  current  AREA 
open-t>pe  design  and  are  presently  used  by  many  American  railroads.  CP  Rail  has 
used  this  diamond  crossing  design  for  some  15  years  and  acquired  extremely  good 
crossing  life. 

Fig.  5  depicts  die  new  design  of  depressed  and  shortened  heel  tail  section  for 
the  insert  casting.  Numerous  problems  haxe  occurred  in  this  area,  especially  with 
the  4?4-in.  heel  design.  Investigation  and  subsequent  design  has  iiroduced  die 
following: 

•  The  depressed  tail  is  ideally  suited  for  the  casting  design  with  a  7-in.  heel 
spread  only,  and  the  false  flange  easer  is  relocated  into  the  insert  body  with 
the  vertical  rib  located  under  the  easer  slope. 

•  Top  of  casting  tail  is  reduced  in  height  by  approximately  M-in.  below  top  of 
rail  and  eliminates  false  flange  contact. 

The  merits  of  this  design  are  as  follows: 

•  Insert   casting   tail   fracture   at   heel  junction   is   practically   eliminated. 

•  Castings  are  shortened  with  reduced  costs  for  insert  and  shop  fitting. 

•  Reclamation  by  welding  and  mamtenance  by  slotting  in  the  tail  section  are 
eliminated. 

•  Wheel  easer  transitions  occur  on  manganese  insert  surfaces  and  this  further 
reduces  wear  and  maintenance  on  die  point  rails  etc. 


658 


Bulletin  658 — American  Railway  Engineering  Association 


Lj 


z 

o 

w 

UJ 

H 

o 

7 

UJ 

O 

(/) 

a 

< 

^ 

QQ 

< 

3 

-I 

H 

< 

0 

CC 

< 

o 

is?    }li 

Z      Z 

o 


CO 


Q  o 

UJ      li.  h- 

^    5  o 

O  UJ 


CO 

H 

$   LU 
±   Q 


z 
o 

0) 

LU 

S    _i 

^  >. 

<      UJ 
< 

2  oc 
•-  < 
o 

^      Q 

w    S 


LU 
LU 

I- 

co 

LU 
(0 
LU 

Z 

< 
o 

z 
< 


Q 
O 


to 


Address  by  E.  H.  Taylor 


659 


PLAN    VIEW 


SLOPE  Vj  JN   9 


Vo- 


r'6 


SECTION    A-A 


^ 


J2l-»RE  132'-Bre 

SECTION    B-B 


DEPRESSED  TAIL    NQ13- 132^-^RE   R.B.M.   FROG 
CP  Rail    DESIGN 

Fig.  5 


Figs.  6  and  7  are  photos  of  frogs  in  service  with  depressed  tails  showing  the 
false  flange  contact  on  the  easer.  To  date,  excellent  results  have  been  obtained  with 
this  design. 

Fig.  8  is  a  typical  cross  section  of  a  manganese  insert  tliat  was  explosive  depth- 
hardened  showing  the  hardness  transitions  and  contour  pattern.  Extensive  explosive 
depth-hardening   tests   were  conducted  with  the   following  results. 

1.  Depth  of  hardening  increases  with  the  number  of  explosions,  at  least  up  to 
a  number  of  three. 

2.  The  depth  of  hardness  raised  above  Re  20,  doubled  between  the  first  and 
second  explosions. 

3.  The  depth  of  hardening  is  not  the  same  for  differently  shaped  portion  of 
the  insert  because  of  reflection  of  shock  waves. 

4.  The  maximum  surface  hardness  was  found  to  be  sHghtly  in  excess  of  400 
BHN  with  the  tliree-shot  application  using  Du  Pont  Detasheet  "C"  Flexible 
Explosive,  weight  2  gm/in.* 

5.  Hardness  values  in  excess  of  400  BHN  are  not  considered  to  be  any  more 
effective  at  increasing  frog  insert  life. 


660  Bulletin  658 — American  Railway  Engineering  Association 


Fig.  6 — Photo  of  depressed  tail. 


Fig.  7 — Photo  of  depressed  tail. 


Address  by  E.  H.  Taylor 


661 


388 


401 


388 


HARDNESS   LEGEND   BHN 
EIj]     331-401 
r      i     285-331 


250-285 
220-250 
200-220 


TYPICAL    INSERT   SECTION 

EXPLOSIVE   DEPTH    HARDENED 

FLEXIBLE   SHEET  EXPLOSIVE 

3  SHOT   APPLICATION 

2  gm/in^ 

Fig.  8 


6.  As  the  major  weakness  of  a  manganese  steel  insert  is  the  softer  metal 
beneath  the  work-hardened  surface,  a  good  depth  of  hardening  is  considered 
the  prime  factor. 

Conclusive  results  have  shown  that  light  wheel  loads  tend  to  produce  die 
surface  hardening  while  heavy  loads  cause  deeper  hardening  and  more  extensive 
flow. 

The  complete  explosive  depth-hardening  process  has  been  instituted  in  con- 
junction witli  our  frog  shop  manufacturing  and  all  manganese  steel  castings  used  in 
CP  Rail  system  are  explosive  depth-hardened. 

A  complete  study  has  been  conducted  on  the  wheel  action  through  frogs  and 
guard  rails  also  the  effects  of  truck  skewing.  Numerous  field  conditions  of  fractured 
bolts  in  bolted  guard  rails,  hooks  or  kinks  in  main  line  stock  rails,  lateral  movement 
of  frogs,  excessi\e  wear  in  the  frog  throat  and  many  more  problems  have  all  been 
experienced.  A  number  of  metliods  ha\e  been  devised  and  a  summary  of  recom- 
mendations is  as  follows; 

Rigid  Frog — For  a  facing-point  moxement,  a  guard  rail  should  l>e  so  located 
that  the  guard  rail  flare  is  directly  adjacent  to  the  frog  throat  so  tiiat  both  throat 
flare  and  guard  rail  flare  exert  almost  simultaneous  wheel  flange  pickup.  Conversely, 
during  the  trailing  point  movement  guard  rail  flare  and  frog  wing  rail  flare  should 
be  directly  opposite.  The  combination  of  wide  gauge  or  tight  guard  rail  flangeway 
in  conjunction  with  incorrect  lateral  guard  rail  settings  are  generally  responsible  for 
lateral  motion  in  both  the  frog  and  stock  rails,  also  excessive  wear  on  the  frog  point, 
throat  and  guard  rail.  Special  through  insulated  gauge  plates  are  recommended  to 
reduce  or  eliminate  these  conditions. 


662 


Bulletin  658 — American  Railway  Engineering  Association 


13  8  GUARD  RAIL   ,^  FLAT  HOOK  TWIN  TIE  FLATK 


G  R^H^H  a  M.ii^l5,.H  &_ a 


FLAT    TIE    PLATE 


N013-132'^RE    INSTALLATION 


^INSULATED  THROUGH 
\        GAUGE   PLATE 


SECTION  A-A  SECTION  BB 

TYPICAL    INSTALLATION 

GUARD    RAILS   AND   GAUGE   PLATES 
Fig.  9 


Fig.  9  shows  tlie  recommended  guard  rail  location  relative  to  the  frog  previously 
described;  also  shows  the  installation  of  the  through  insulated  gauge  plates  in  the 
toe  and  heel  areas  of  tlie  frog.  Note  in  section  view  the  use  of  the  Pandrol  Clip 
which  is  an  ideal  fastener  for  rail  and  plate  in  special  applications.  At  present  all 
guard  rail  lengths  are  designed  to  suit  the  specific  frog  parameters  described  above. 

In  Fig.  10 — Guard  rail  flare  at  toe  of  frog,  and  Fig.  11 — Guard  rail  flare  at 
heel  of  frog,  note  wheel  flange  pick-up.  In-track  installations  with  through  insulated 
gauge  plates  have  substantiated  this  approach.  After  approximately  one  year  of 
service  both  main  and  turnout  tracks  have  been  maintained  vdthin  1/16-in.  of 
gauge  and  related  wear  conditions  have  been  greatly  reduced. 

CP  Rail  switch  design  parallels  AREA  design  recommendations  in  many  aspects. 
Straight  and  curved  switches  with  uniform  risers  in  39-ft  and  13-ft  curved;  22-ft, 
16-ft  6-in.  and  11-ft  straight,  are  used  with  switch  point  planing  to  AREA  design 
detail  4,000  and  5,100.  All  power  switches  are  equipped  with  vertical  switch  rods, 
offset  fixed  heel  blocks  to  AREA  design  2125  and  adjustable  rail  braces. 


Address  by  E.  H.  Taylor 


663 


Fig.  10 — Photo  of  toe  end  of  guard  rail. 


Fig.  11 — Photo  of  heel  end  of  guard  rail. 


664  Bulletin  658 — American  Railway  Engineering  Association 

Areas  of  \'ariation  are  as  follows:  all  switch  point  top  cut  planing  is  contoured 
to  the  original  rail  head  shape  ratlier  than  the  conventional  flat  cut  with  a  /B-in. 
radius.  This  design  has  reduced  the  gauge  line  rail  flow  and  required  maintenance 
grinding.  All  reinforcing  straps  and  rail  stops  are  bolted  to  the  switch  points  with 
hexagonal  head  cap  screws  and  elastic  stop  nuts.  This  provides  for  adjustment  when 
fretting  of  mating  parts  has  stabilized.  During  reclamation  the  removal  of  straps, 
bolts,  etc.,  which  represent  approximately  40%  of  the  cost  of  a  new  switch  point, 
is  greatly  facilitated. 

Field  investigation  of  chipped  or  scalloped  switch  points  has  indicated  that  in 
the  straight  tlirough  position  the  stock  rail  bending  has  not  been  sufficient  and  the 
normally  protected  point  has  been  exposed  to  wheel  contact.  All  stock  rails  are  now 
shop  bent  where  tlie  vertex  location  and  bend  is  more  precise  and  switch  point  tip 
is  protected.  In  addition,  the  complete  assembly  consisting  of  the  bent  stock  rail, 
switch  point  and  heel  block  assembly  is  considered  tlie  ideal  metliod  of  shop  manu- 
facture and  this  greatly  facilitates  field  installation.  This  practice  is  presently  being 
carried  out  on  CP  Rail. 

Field  investigation  of  gauge  throughout  tlie  switch  area  has  generally  indicated 
that  the  point  of  switch  is  held  to  gauge  witli  the  insulated  gauge  plates,  but  wide 
variations  in  gauge  have  been  experienced  from  the  third  rod  through  the  heel 
tvirnout  area.  To  rectify  tiiis  gauge  problem,  which  is  detrimental  to  switch  point 
alignment  and  adjustment,  resulting  in  increased  wear  and  maintenance,  all  main- 
line power  switches  are  being  equipped  with  insulated  gauge  plates  at  the  third  rod 
and  heel  locations.  These  plates  also  assist  during  the  installation  of  new  svdtches. 

Special  flat  seat  double  shoulder  tie  plates  are  used  tliroughout  the  turnout 
in  order  to  eliminate  the  gauge  alignment  transitions  at  the  heel  of  switch  and  toe 
and  heel  of  frog.  Specially  developed  track  bolts  witii  extruded  shank,  cold-rolled 
threads,  are  used  with  elastic  stop  nuts  in  standard  rail  joints  within  tlie  turnout 
area.  Chrome  rails  are  used  throughout  the  turnout  area  and  this  has  resulted  in 
reduced  rail  end  batter  and  flow  at  new  rail  cuts;  also  reduced  flow  over  standard 
carbon  rails  when  used  in  die  vertical  position. 

The  cumulative  efl^ect  of  many  aspects  of  design  have  produced  a  main  line 
turnout  that  has  provided  a  significant  improvement  in  service  life  with  reduced 
maintenance  and  corresponding  costs. 

Conclusion 

I  have  attempted  to  illustrate  some  of  the  more  interesting  innovations  in 
special  trackwork  design  and  development  which  are  presently  ongoing  in  CP  Rail. 
We  are  currently  involved  in  the  evaluation  and  development  of  special  switch 
designs,  new  designs  of  railbound  manganese  spring  frogs  and  investigation  into 
the  design  and  use  of  swing-nose  frogs.  These  are  a  few  of  the  challenging  problems 
which  railroads  must  cope  with  in  the  ever-increasing  demands  for  low-cost  and 
reliable  transportation  service 


C&NW's  ''BUG"    (Ballast  Undercutter-Cleaner) 

77-658-1 J 

By  R.  W.   BAILEY 

Director   of   Maintenance    Planning 
Chicago   &   North   Western   Transportation   Company 

The  Chicago  &  North  Western  Transportation  Company  began  using  a  quartzite 
ballast  20  years  ago  on  our  3900  track  miles  of  primary  main  line.  This  ballast  is 
classified  in  between  No.  4  and  No.  5  in  the  AREA  Ballast  Specifications  in  sizes 
from  1/4-in.  to  /2-in.  During  this  period  ballast  rehabilitation  consisted  of  plowing 
out  the  fouled  slag,  limestone  or  gravel  ballast  to  build  up  tlie  shoulder  and  then  to 
surface  with  30  to  40  cars  of  new  ballast  per  mile.  After  an  initial  life  of  5  to  10 
years  with  spot  surfacing  only,  the  track  was  maintained  by  dumping  10  to  12  cars 
of  ballast  per  mile  and  raising  approximately  1-in.  to  give  a  new  surface.  This 
process  had  a  short  life,  often  only  a  year  or  two  in  muddy  areas,  and  had  to  be 
repeated  to  maintain  an  acceptable  operating  speed. 

We  reasoned  that  the  original  material,  a  hard  quartzite,  was  still  under  the 
tie  and  could  be  salvaged  if  the  contamination  could  be  removed.  We  tlierefore 
began  a  study  on  what  we  felt  was  taking  place  and  the  following  movie  illustrates 
our  findings. 

( Movie  was  shown. ) 

The  process  just  illustrated  had  to  be  justified  financially  to  our  management 
for  them  to  provide  funds  for  its  purchase  and  operation. 

To  cite  some  general  considerations,  we  calculated  that  raising  the  track  3-in. 
and  undercutting  12-in.  would  result  in  the  cleaning  of  55  cars  of  compacted  mate- 
rial per  mile.  If  our  recovery  of  this  material  was  to  be  70%,  we  would  salvage  38  cars 
per  mile.  Based  on  today's  ballast  cost  from  our  own  pit  of  $140  per  car,  the 
undercutting-cleaning  would  save  an  "out  of  pocket"  ballast  cost  of  $5300  per  mile. 
However,  it  must  be  recognized  that  the  ballast  in  place  has  a  value  two  times  the 
pit  cost  when  the  transportation  charges  and  equipment  costs  are  included.  On 
our  railroad  if  the  average  ballast  mileage  is  250  miles,  the  value  of  ballast  per  mile 
in  place  is  1.7  times  the  pit  cost  or  $9100. 

To  salvage  tlais  material  we  must  have  machine  and  labor  costs.  Annual 
charges  for  depreciation  of  tiie  equipment,  interest  on  investment,  maintenance  at 
16%  of  investment,  fuel,  lubricants,  salaries  and  additions  for  four  men,  their 
expenses,  insurance  and  miscellaneous  contingencies,  indicated  that  to  salvage  $5300 
of  ballast  would  cost  55  to  60%  of  tlie  material  cost.  The  net  savings  would  be 
approximately  $6000  in  ballast  per  mile. 

In  1975  our  program  work  was  sharply  reduced  to  conform  with  economic 
conditions  and  it  was  decided  to  lease  "BUG"  to  other  railroads. 

In  tlie  4th  quarter,  die  economic  picture  changed  and  on  November  4tli  we 
began  operating  tlie  equipment  in  a  problem  area  in  Iowa  for  13  days  before  we 
froze  up.  We  averaged  5  hours  undercutting  daily,  due  to  train  operations,  and  584 
track  feet  per  hour. 

These  limited  operating  statistics  neither  confirm  nor  deny  our  assumptions 
on  savings  but  do  indicate  the  machine's  productive  capabilities  to  clean  ballast  at 
a  rapid  rate. 

665 


INSTALLATION  OF  OFFICERS 


667 


Installation  of  OfRcers 

PREsroEXT  W.vrd:  I  would  like  to  install  the  newly  elected  officers  of  the 
Association  at  this  tiine.  This  is  a  short  but  important  and  impressive  ceremony 
and  will  let  each  of  you  become  more  acquainted  with  the  officers  you  have  elected. 
So,  with  your  permission,  I  will  proceed  with  the  installation  ceremony. 

To  make  room  for  new  officers  and  directors  a  certain  number  of  them  com- 
plete their  service  on  the  Board  of  Direction  each  year.  It  is  with  mLxed  feelings 
that  we  see  these  changes  take  place. 

I  w  ant  to  thank  each  member  of  die  Board  for  his  counsel,  advice  and  support, 
and  especially  those  members  who,  having  completed  their  temi  of  office,  are 
retiring  from  the  go\eming  body  of  die  Association.  The  close  of  this  technical 
conference  completes  the  services  on  the  Board  of  Past  President  D.  V.  Sartore, 
chief  engineer — design,  BurUngton  Xordiern.  The  AREA  Constitution  provides  that 
past  presidents  will  remain  on  the  Board  for  two  years  after  completion  of  their 
term  as  president.  We  are  deeply  indebted  to  Mr.  Sartore  for  his  long  and  outstanding 
service  to  our  Association — both  in  an  official  and  an  unofficial  capacity — and, 
although  he  will  be  off  the  Board,  I  am  sure  he  still  will  be  called  upon  for  counsel 
and  advice  as  important  matters  come  up. 

Don,  will  you  please  stand  so  we  may  give  you  the  applause  you  so  richly 
deserve. 

( Applause ) 

President  Ward  (continuing):  Other  members  of  the  AREA  Board  of  Direc- 
tion completing  their  term  of  service  are  these  directors:  R.  W.  Pember,  chief 
engineer,  design  and  construction,  Louisville  and  Nashville  Railroad;  E.  Q.  Johnson, 
senior  assistant  chief  engineer,  Chessie  System;  W.  E.  Fuhr,  assistant  chief  engineer — 
staff,  Cliicago,  Milwaukee,  St.  Paul  and  Pacific  Railroad;  and  B.  E.  Pearson,  chief 
engineer,   Soo  Line  Railroad. 

These  men  have  served  our  Association  well  in  their  official  capacity  on  the 
Board  and  I  want  to  express  our  deep  appreciation  to  each  of  them. 

Will  Messrs.  Pember,  Johnson,  Fuhr,  and  Pearson  please  stand  and  permit  us  to 
show  our  appreciation  for  their  service. 

( Applause ) 

President  Ward  (continuing):  It  is  now  my  privilege  and  pleasure  to  install 
the  new  directors  you  have  elected  for  tlie  ensuing  year.  As  I  read  your  name,  please 
come  to  the  speaker's  table  through  the  walkway  adjacent  to  the  podium,  and  take 
a  place  at  my  right. 

J.  W.   Brent,  chief  engineer,  Chessie  System — from  the  East  District. 

L.  F.  Currier,  engineer-structures,  Louisville  &  Nashville  Railroad — from  the 
South  District. 

T.  L.  Fuller,  engineer  of  bridges,  Southern  Pacific  Transportation  Company — 
from  the  West  District. 

J.  A.  Barnes,  assistant  vice  president  and  chief  engineer,  Chicago  &  North 
Western   Transportation   Company — from    the    West   District. 

Gentlemen,  I  welcome  \ou  as  directors  of  the  American  Railway  Engineering 
Association.  These  are  offices  of  high  honor  and  responsibility  you  are  assuming. 
I  hope  you  will  enjoy  your  service  on  the  Board  of  Direction  and  will  bring  much 
value  to  its  deUberations.  Congratulations.  You  may  be  seated. 

669 


670  Bulletin  658 — American  Railway  Engineering  Association 

Our  newly  elected  junior  vice  president  is  W.  S.  Autrey,  chief  engineer  system, 
Atchison,  Topeka  &  Santa  Fe  Railway. 

Mr.  Autrey,  will  you  please  come  to  the  platform. 

Mr.  Autrey,  I  congratulate  you  upon  your  election  as  junior  vice  president 
and  return  to  our  Board  of  Direction. 

The  new  senior  vice  president  is  B.  J.  Worley,  vice  president  and  chief  engi- 
neer, Chicago,  Milwaukee,  St.  Paul  &  Pacific  Railroad. 

Mr.  Worley,  will  you  please  come  to  the  platform. 

Mr.  Worley,  I  congratulate  you  on  your  advancement  to  senior  vice  president 
and  continued  service  on  the  governing  body  of  our  Association.  I  know  that  you 
will   discharge    this   greater   responsibility   with   distinction. 

You  and  Mr.  Autrey  will  make  a  splendid  team  of  vice  presidents.  Please  be 
seated. 

Our  new  president  is  John  Fox,  chief  engineer,  Canadian  Pacific  Rail. 

Mr.  Fox,  I  congratulate  you  upon  your  election  to  tlie  highest  position  of  honor 
in  the  American  Railway  Engineering  Association.  I  share  tlie  confidence  which  has 
been  placed  in  you  by  our  membership  and  it  is  with  pleasure  and  satisfaction  that 
I  turn  over  the  responsibility  of  AREA  President  to  you  at  the  end  of  this  meeting. 


President  Ward:  We  have  now  completed  the  scheduled  program  for  the 
75th  Annual  Technical  Conference  of  tlie  American  Railway  Engineering  Association 
and  the  1976  Annual  Meeting  of  the  Engineering  Division,  Association  of  American 
Railroads. 

You  will  be  interested  to  know  that  the  registration  for  our  1976  meetings  is: 
railroad  men  470;   non-railroad  men   510;   total  registration  980. 

It  is  now  time  to  turn  over  the  Association  to  our  new  president  and  to  adjourn 
these  meetings.  Before  doing  so,  however,  I  want  to  take  this  opportunity  to  thank 
all  who  contributed  to  the  work  of  our  Association  during  the  past  year  and  to  the 
success  of  this  Conference.  The  AREA  has  had  a  successful  and  productive  year  in 
spite  of  difficult  conditions.  This  has  happened  because  so  many  of  you  gave  so 
generously  of  your  time  and  effort,  which  I  assure  you,  has  been  greatly  appreciated. 

There  are  so  many  to  whom  I  am  personally  indebted  that  I  cannot  possibly 
name  them  all  here,  but  I  do  want  to  express  my  personal  appreciation  for  the 
splendid  cooperation  of  our  officers  and  directors,  our  committee  chairmen  and 
the  active  committee  members,  and  all  others  who  contributed  in  any  way  to  the 
success  of  the  1975-1976  Association  year.  I  especially  want  to  express  my  sincere 
appreciation,  and  the  appreciation  of  the  Association,  to  our  headquarters  staff  for 
the  manner  in  which  they  have  conducted  the  affairs  of  the  AREA  during  the  past 
year.  Their  attention  to  the  multitude  of  details  in  the  planning  and  execution  of 
the  many  Association  activities  and  programs,  and  their  efforts  in  connection  with 
the  important,  world-wide-used  AREA  publications,  many  times  under  most 
difficult  circumstances,  has  been  invaluable  to  the  Association,  the  Board  of  Direction, 
and  to  me.  They  deserve  the  maximum  extent  of  our  support,  patience  and  under- 
standing. 

The  Conference  Operating  Committee,  under  the  direction  of  its  manager, 
Bruce  Miller,  Penn  Central,  did  its  usual  outstanding  job  in  connection  with  operating 
this  conference  in  accordance  with  the  plans  and  arrangements  made  by  the  Asso- 
ciation's stafF.  These  well-planned  and  well-operated  conferences  do  not  just  happen. 


Installation  of  Officers  671 


Other  than  our  past  presidents,  few  members  are  in  a  position  to  know  the  multitude 
of  details  handled  by  this  committee  during  our  conferences  and  how  easily  things 
could  go  awry  if  it  were  not  for  tlieir  diligence. 

I  join  Mrs.  Ward  in  tlianking  all  of  those  ladies  who,  witli  Mrs.  Fox,  Mrs. 
Worley  and  Mrs.  Hodgkins,  ga\'e  so  generously  of  their  time  in  assisting  with  tlie 
functions  of  our  conference  planned  expressly  for  our  wives.  You  have  our  grateful 
appreciation. 

Is  there  any  further  business  to  come  before  this  meeting? 

(At  this  point,  Past  President  T.  B.  Hutcheson  asked  for  the  privilege  of  the 
floor  and  presented  President  Ward  with  the  AREA  plaque.) 

President  Ward  ( continuing ) :  It  now  gives  me  great  pleasure  to  formally 
install  oxir  new  president,  and  I  request  him  to  join  me  at  this  podium. 

Mr.  Fox,  I  congratulate  you  upon  your  election  to  the  highest  position  of  honor 
in  the  American  Railway  Engineering  Association,  and  I  now  proclaim  you  President. 
In  taking  this  action,  I  also  proclaim  Mrs.  Fox  as  tlie  unofficial  "First  Lady"  of  the 
Association. 

I  share  the  confidence  which  has  been  placed  in  you  by  our  membership  and 
it  is  with  pleasure  and  satisfaction  that  I  turn  over  the  responsibility  of  President 
to  you. 

In  doing  this,  I  want  to  present  you  with  this  gold  pin,  which  bears  the  words 
engraved  on  the  back: 

JOHN  FOX 

PRESIDENT 

1976-1977 

This  is  the  official  emblem  of  the  AREA  and  I  am  sure  you  will  wear  it  with 
equal  pleasure  to  yourself  and  honor  to  the  Association. 

(President  Fox  responded  and  then  continued  as  follows): 

PREsroENT  Fox:  Before  I  adjourn  this  conference,  I  would  like  to  remind  all 
members  of  the  Board  of  Direction,  including  the  former  members  and  new  mem- 
bers, and  all  the  members  of  the  Conference  Operating  Committee,  that  we  will 
have  a  joint  luncheon  together  in  the  Wabash  Parlor  on  the  tliird  floor  of  this  hotel 
immediately  following  the   adjournment  of  this   meeting. 

The  luncheon  will  be  followed  by  the  post-conference  meeting  of  tlie  AREA 
Board  of  Direction  in  Private  Dining  Room  9. 

Before  closing  this  Technical  Conference  of  AREA,  is  there  any  further  business 
to  come  before  the  meeting? 

(At  this  point  A.  F.  Joplin,  vice  president,  operation  and  maintenance,  Canadian 
Pacific  Rail,  asked  for  the  privilege  of  the  floor  and  spoke  as  follows ) : 

A.  F.  Joplin:  It  is  my  pleasure  to  express  to  John  Fox  on  behalf  of  his  colleagues 
in  Canadian  Pacific  our  great  pride  and  admiration  in  the  high  honor  he  has 
attained.  I  am  sure  that  this  feeling  is  shared  by  all  Canadians.  Many  Canadians 
from  CP  Rail  serve  in  this  Association,  and  we  feel  that  his  elevation  to  this  office 
reflects  the  great  hand  of  friendship  and  cooperation  that  exists  between  our  two 
countries. 

Mr.  Fox,  as  you  may  know,  has  worked  his  way  through  each  level  of  our 
railway  and  on  February  1  of  this  year  was  appointed  chief  engineer  of  Canadian 
Pacific.  Similarly  he  has  worked — you  notice  my  emphasis  on  work,  because  that  is 


672  Bulletin  658 — American  Railway  Engineering  Association 

what  it  takes — he  has  worked  his  way  through  the  various  committees  and  service 
offices    of   this    Association,    and   is   signally   honored    this   day. 

Mr.  President,  on  behalf  of  your  associates  in  Canadian  Pacific  may  I  present 
to  you  this  gavel  to  wield  during  your  tcnn  of  office  in  tliis  Association.  It  is  made 
from  a  tie  from  our,  your,  railway  from  the  Newport  subdivision  at  M4.1  Quebec 
Central  Railway  installed  in  1956.  This  tie  has  served  us  well  in  its  first  life — may 
it  serve  you  well  in  your  term  of  office — and  later  serve  as  a  happy  memento  of  this 
occasion  and  an  expression  of  our  confidence  in  your  ability  to  discharge  the  duties 
of  this  high  office  so  as  to  reflect  greatly  to  the  credit  of  yourself  and  this  Association. 

President  Fox:  Thank  you  very  much  Mr.  Joplin.  It  is  my  pleasure  to  accept 
this  gavel  in  the  friendly  spirit  in  which  it  has  been  presented.  I  appreciate  this 
gift,  coming  as  it  does  from  my  friends  and  associates  in  CP  Rail  Engineering 
Department.  This  gavel  will  greatly  assist  me  in  carrying  out  my  duties  as  presiding 
officer  at  meetings  of  this  Association  during  the  next  year. 

I  should  like  to  thank  Mr.  Ward  for  his  kind  remarks  and  would  like  to  take 
tliis  opportunity  to  say  to  John,  congratulations  on  a  job  well  done  during  his  tenure 
as  President. 

Members  of  the  American  Railway  Engineering  Association,  it  is  indeed  an 
honor  to  be  chosen  by  you  to  be  president  of  this  fine  and  progressive  Association. 
I  greatly  appreciate  the  confidence  tliat  you  have  shown  in  me  and  consider  that 
the  election  of  a  Canadian  railway  engineer  to  head  this  Association  during  this, 
your  Bi-Centennial  year,  to  be  a  signal  honor  for  Canadians.  With  the  help  of  all 
the  officers,  directors,  committees,  members  and  staff  which  has  always  been  fully 
given,  I  know  that  the  coming  year  will  be  a  successful  one  for  the  Association  and 
myself. 

I  should  now  like  to  introduce  to  you  my  devoted  life  partner  who  will  be 
the  Association's  First  Lady  for  the  next  year — my  wife  Janet;  with  Janet  is  my 
eldest  son,  John. 

If  there  is  no  further  business,  the  75th  Annual  Technical  Conference  of  the 
American   Railway  Engineering  Association  will  adjourn  sine  die. 


AAR  ENGINEERING  DIVISION  SESSION 


673 


Remarks  by  Division  Chairman  John  T.  Ward* 

This  morning,  most  of  you  were  present  when  I  welcomed  you  to  tlie  opening 
session  of  the  AREA  Technical  Conference.  Now  it  gives  me  great  pleasure  to 
welcome  you  to  tlie  1976  Annual  Meeting  of  the  Association  of  American  Railroads, 
Engineering  Division  of  its  Operations  and   Maintenance  Department. 

What  is  the  relationship  between  tlie  AAR  Engineering  Division  and  the  AREA? 
The  governing  body  of  AREA  consists  of  a  Board  of  Direction  totaling  17  elected 
by  the  membership.  The  governing  body  of  the  Engineering  Division  is  a  General 
Committee  appointed  by  die  vice  president  of  the  Operations  and  Maintenance 
Department,  and  consists  of  the  same  17  members  forming  the  AREA  Board  of 
Direction,  plus  an  additional  group,  making  the  total  on  the  ED  General  Committee 
a  maximum  of  21.  In  the  latter  instance,  tliere  is  only  one  member  from  any  family 
of  lines,  making  it  necessaiy  on  occasions  to  substitute  for  one  or  more  of  the  Board 
of  Direction,  thereby  distributing  tlie  membership  among  as  many  member  lines 
as   possible. 

The  AREA  is  a  private  organization,  and  while  it  has  considerable  technical 
expertise  among  its  membership,  permitting  the  furUiering  of  its  objectives  in  the 
advancement  of  knowledge  pertaining  to  tlie  scientific  and  economic  location,  con- 
struction, operation  and  maintenance  of  railways,  tliere  is  no  opportunity  for  any 
action  which  would  be  binding  upon  a  particular  carrier.  On  the  other  hand,  the 
AAR  Engineering  Division,  through  its  General  Committee,  as  described  previously, 
may  do  so  with  proper  approvals. 

A  few  remarks  are  now  in  order  to  acquaint  you  with  the  work  of  the  Engi- 
neering Division  for  the  year  just  closing.  The  Division  has  been  an  aid  to  the  rail 
industry  and  will  continue  to  be  so  in  the  future  as  engineering  problems  arise 
requiring    consideration    or    recommendations    for   possible    solutions. 

The  ED  General  Committee  met  four  times  during  the  year  to  discuss  and 
progress  various  matters  relating  to  the  work  of  the  committee.  The  first  such  meeting 
was  held  following  die  1975  annual  meeting  of  the  Engineering  Division  held  at  the 
Palmer  House  in  Chicago  last  March. 

During  the  year,  a  liaison  committee  was  appointed  from  the  membership  of 
the  ED  General  Committee  to  provide  direction  and  close  relations  with  the  Federal 
Railroad  Administration  on  problems  and  other  matters  of  mutual  interest.  This 
committee  has  reviewed  many  suggested  changes  in  the  ERA  Track  Safety  Standards 
and  is,  at  the  moment,  handling  for  possible  revisions. 

This  same  liaison  committee  formed  the  nucleus  of  a  new  task  force  charged 
with  the  responsibility  of  developing  the  costs  to  the  rail  industry  of  government 
regulations  associated  with  fixed  property  engineering  and  maintenance  of  way. 
Hopefully,  this  will  result  in  the  industry  recovering  all,  or  certainly  a  part,  of  such 
costs.  This  is  particularly  in  regard  to  costs  associated  with  inspections,  etc.,  related 
to  the  ERA  Track  Safety  Standards,  with  which  we  are  all  familiar. 

Still  another  task  force  of  the  Engineering  Division  reviewed  in  detail  the 
Occupational  Safety  and  Health  Standards,  following  which  recommendations  were 
made  to  the  AAR  on  certain  changes  that  might  be  considered  should  the  standards 
be  adopted  by  the  ERA. 


•  Senior  Assistant   Chief  Engineer,   Seaboard  Coast  Line  Railroad. 

675 


676  Bulletin  658 — American  Railway  Engineering  Association 

The  General  Committee  reviewed  the  FRA's  plans  to  install  a  test  loop  track 
at  Pueblo,  Colo.,  and  made  recommendations  to  the  AAR  Research  and  Test 
Department  relative  to  general  layout,  specific  track  geometry  and  certain  support 
facilities. 

In  response  to  a  request  from  tlie  Federal  Highway  Administration  to  the  AAR 
for  a  recommendation  for  appropriate  clearances  for  highway  grade  separation 
structures  over  railroads  either  electrified  or  expected  to  be  electrified,  the  Engi- 
neering Division's  Committee  on  Electrical  Facilities  (Fixed  Properties)  submitted 
a  report  and  drawing  recommending  clearances.  The  ED  General  Committee 
approved  tlie  report  and  drawing,  with  some  modifications,  with  same  subsequently 
having  been  approved  by  the  ED  voting  representatives  of  the  AAR  member  roads. 

The  above  is  just  a  brief  outline  of  what  has  taken  place  this  year  in  the 
Engineering  Division,  and  I  sincerely  trust  it  has  aided  in  clearing  any  question  in 
your  minds  of  what  may  have  been  accomplished. 


A  Time  for  Challenge 


By  D.  C.   HASTINGS 

Executive   Vice    President,    Seaboard    Coast    Line    Railroad; 
Chairman,   AAR   Operating— Transportation   Division 

Almost  200  years  ago  when  the  United  States  of  .\merica  had  its  beginning  as 
a  new  government,  a  new  concept  of  government — a  government  which  had  as  its 
foundation  the  highest  Christian  principles — one  of  its  founders  or  authors,  Benjamin 
Frankhn,  said,  "He  who  would  incorporate  in  public  affairs  the  principles  of 
Christianity  would  revolutionize  the  world."  That's  exactly  what  they  did!  Basically 
they  provided  for  the  freedom  of  man.  They  provided  for  the  preservation  of  the 
dignity  and  the  worth  of  every  single  individual.  And  predicated  on  this  they 
brought  hope  to  the  world.  And  this  system  of  government  still  brings  hope  to  the 
world. 

This  hope  though  is  based  on  the  concept  that  man  can  be  free  and  live  free. 
And  that  concept  has  been  tlie  basis  of  what  we  call  today  our  free  enterprise 
system.  With  such  a  system  our  nation  has  grown  into  one  that  has  been  the  envy 
of  the  world.  But  our  nation  and  its  system  is  under  attack.  It  is  under  attack  both 
directly  and  indirectly,  even  by  those  who  don't  realize  they  are  attacking  it.  Our 
free  enterprise  system  is  facing  its  greatest  test  in  its  entire  history,  and  when  people 
say  this  is  a  young,  new  country,  don't  be  fooled  by  that  statement.  Our  country 
as  now  constituted  is  one  of  the  oldest  forms  of  government  now  in  existence. 

There  are  practically  no  countries  in  the  world  today  that  have  the  same  fonn 
of  government  they  had  200  years  ago — but  we  still  have  ours — and  when  people 
seek  to  attack  the  free  enterprise  system  I  think  we  ought  to  remember  three 
characteristics  of  our  American  way  of  life. 

One  of  them  is  our  great  resources.  I  refer  to,  in  addition  to  our  natural 
resources — our  people.  The  people  of  America  are  the  greatest.  They  rise  to  the 
occasion.  They  have  always  risen  to  the  occasion.  They,  as  a  people,  sometimes  do 
some  stupid  things,  but  when  the  real  crisis  comes  you  can  count  on  the  people 
of  America  to  come  up  with  the  solutions. 

The  second  is  our  capacity  to  do  anything  that  is  required  when  the  time  comes. 
America  has  great  capacity.  With  only  6%  of  the  world's  population,  we  produce 
over  37%  of  the  world's  goods. 

The  third  is  that  the  America  we  know  has  heart.  We  feed  more  people,  take 
care  of  more  hungry  people  and  more  disabled  people  than  any  other  country  in 
tire  world.  We  have  compassion  and  have  demonstrated  it  over  the  years.  What 
otlier  country  in  the  history  of  the  world  has  ever  been  brutally  attacked  by  another 
and  after  a  bloody  war  has  beaten  it  and  then  turned  right  around  and  spent 
hundreds   of  millions   of  dollars   in  its  rehabilitation? 

This  is  the  American  way  and  regardless  of  what  people  in  the  world  might 
say  about  it — accusing  us  of  decadence,  with  inabihty  to  meet  the  test  of  the  times 
and  anything  else  you  can  think  of — most  of  them  would  give  their  right  arm  to 
live  here. 

Yes,  we  are  under  attack  and  there  is  no  question  about  it.  One  of  the  most 
vicious  attacks  on  our  free  enterprise  system  is  posed  by  the  situation  confronting 
die  railroads  today.  In  order  to  look  at  that  problem  properly  and  in  the  right 
perspective,  we  need  to  look  at  transportation  in  general. 

677 

Rill.   G5S 


678  Bulletin  658 — American  Railway  Engineering  Association 

Transportation,  as  we  all  know,  is  a  vital  part  of  our  free  enterprise  system. 
You  remember  in  your  courses  in  economics  in  college  you  were  taught  that  if  you 
had  a  raw  material,  plenty  of  capital  and  adequate  labor  you  could  start  up  a 
commercial  or  industrial  enterprise.  One  big  factor,  however,  was  left  out  and  tliat 
is  transportation. 

No  raw  material  is  worth  anything  until  it  has  transportation  applied  to  it  to 
get  it  where  it  is  needed — and  no  refined  or  manufactured  product  has  any  appre- 
ciable value  until  it  is  transported  to  the  point  of  consumption.  So  transportation 
is  the  fourth  ingredient — raw  material,  capital,  labor  and  transportation — and  when 
any  one  of  tliese  four  things  loses  its  characteristic  of  freedom  it  becomes  national- 
ized— then   the  whole  ball  begins  to  unravel. 

Now  when  we  consider  the  transportation  system  in  America  today  the  railroads 
become  the  major  factor.  They  are,  first  of  all,  the  only  true  or  real  common  carrier. 
They  take — in  fact  they  have  to  take — anything  everywhere.  They  are  the  principal 
carrier  in  our  transportation  system  and  as  such  they  are  a  vital  part  of  our  free 
enterprise  system. 

If  the  railroads  are  vmable  to  continue  as  a  free  enterprise  the  whole  transpor- 
tation business  falls  apart  and  it  is  high  time  that  everyone  in  America  understands 
this.  Every  report  to  the  Congress,  of  which  the  have  been  six,  beginning  in  1934 
and  ending  with  the  Smadiers'  Report  in  1959,  has  concluded  with  the  fact  that  if 
the  railroads  are  nationalized  the  whole  agricultural,  industrial  and  commercial  life 
of  America  would  be  at  the  mercy  of  the  Govermiient.  And  if  that  happens,  dowoi 
the  drain  would  go  the  whole  free  enterprise  system.  So  we  should  accept  the  fact 
that  unless  the  railroads  can  make  it,  our  very  way  of  life  is  in  jeopardy. 

Now  as  we  all  know,  our  nation's  railroads  are  in  trouble.  The  year  1975  was 
one  of  the  worst  in  tlie  history  of  the  nation  when  the  industry  is  looked  at  on  a 
national  basis.  Earnings  were  down,  maintenance  was  deferred,  capital  was  getting 
harder  to  acquire  and  in  general  the  situation  was  not  good.  The  recently  passed 
Railroad  Revitalization  and  Regulatory  Reform  Act  of  1976  may  be  of  some  benefit — 
but  it  is  not  the  answer  to  the  maiden's  dream! 

While  things  may  look  bad,  there  are  three  things  about  the  railroad  industry 
that  we  should  always  remember: 

First  of  all  they  have  to  have  us!  America  cannot  survive  without  the  railroad 
industry.  We  are  essential  to  the  American  way  of  life. 

Secondly,  if  die  energy  crisis  is  ever  to  be  solved,  the  answer  lies  in  the 
transportation  of  materials  by  rail,  since  we  are  not  only  the  most  efficient  mode 
of  transportation  in  energy  consumption,  but  also  we  are  tlie  only  mode  that  can 
move  coal  in  the  quantities  and  to  all  the  places  tliat  will  be  required.  Barges  and 
pipelines  may  be  talked  about  but  they  can  never  do  tlie  total  job. 

Thirdly,  if  the  railroads  were  nationalized  the  problems  would  still  exist.  None 
of  our  present  problems  would  be  solved.  Therefore,  what  we  need  is  to  solve  the 
problems  and  if  we  do — we  then  have  a  viable  segment  of  the  free  enterprise 
system. 

Our  problems  are  many  and  are  as  well  known  to  each  of  you  as  they  are  to 
me.  The  RR  &  RR  Act  of  1976  is  only  a  "Birdie  Hop"  in  the  game  of  "  'May  I'  be 
an  equally  treated  industry."  I  will  not  attempt  to  enumerate  all  the  things  that 
confront  us  except  to  say  that  added  to  all  the  regulations  and  restrictions  that 
began  with  the  Interstate  Commerce  Act  in  1886,  we  have  the  new  regulations 
that  have  come  along  in  the  late  60's  and  early  70's:  (1)  Mechanical  Safety 
Standards,    (2)    Track  Safety  Standards,    (3)    Hours  of  Service  Act  Revisions,    (4) 


Address  by  D.  C.  Hastings  679 


Pollution  control  regulations  (noise  included),  (5)  E.E.O.C.  requirements,  (6) 
Invasion  of  OSHA  into  the  railroad  world,  (7)  The  myriad  of  FRA  regulations 
running  from  how  we  switch,  etc.,  to  how  we  word  and  even  apply  our  transporta- 
tion operating  rules,  and  (8)  die  dozens  of  recommendations  that  emanate  from 
the  National  Transportation  Safety  Board — which  agency  seems  to  think  that  every 
railroad  accident  could  have  been  avoided  if  management  had  just  done  something 
that  to  diose  of  us  who  have  been  in  this  racket  a  few  years  know  borders  on  being 
absurd. 

While  we  need  freedom  from  many  of  these  shackles,  we  must  also  take  a  look 
at  ourselves  too  and  see  what  we  can  do  from  witiiin  to  improve  our  position.  We 
may  diink  that  tlie  diesel  locomotive,  the  mechanization  of  track  maintenance,  CTC, 
die  computer,  etc.,  ha\e  exhausted  our  efforts  to  be  more  efficient;  however,  the  fact 
remains  that  we  nui.st  find  ways  of  being  more  efficient,  and  I  know  of  no  better 
group  to  do  something  in  diis  area  dian  you!  We  all  have  management  objectives 
and  they  vary  from  railroad  to  railroad,  but  I  think  that  today's  managements  have 
one  common  objective  and  that  is  SURVIVAL!  I  don't  mean  to  sound  discouraged — 
for  I  am  not!  I  mean  that  we  all  should  be  challenged  to  preserve  our  great 
industry  as  a  free  enterprise,  because  in  so  doing  we  will  preserve  the  free  enterprise 
system  in  America,  we  will  preserve  our  way  of  life — and  I  know  that  you,  along 
with  all  other  railroaders,  are  equal  to  this  task. 

Reflect  for  a  moment  on  our  history — the  problems  that  faced  our  forefatliers 
and  how  they  came  out  when  times  were  so  tough  as  to  seem  unsolvable. 

Remember  in  1776  when  the  entire  military  might  of  America  was  gathered  at 
Valley  Forge — they  were  ill-housed,  ill-clothed,  ill-fed — but  they  were  never  dis- 
couraged. They  were  challenged  by  their  great  leader  and  they  had  the  spirit  to  win! 
They  did. 

In  1812  this  little  nation  of  ours  with  such  great  ideals  was  attacked  by  the 
greatest  power  in  the  world  and  our  Capitol  was  burned  to  the  ground.  But  we 
came  out  of  that  because  we  were  challenged  by  our  leader  and  we  won. 

In  1865  we  were  faced  with  rebuilding  a  country  torn  apart  by  the  worst  Civil 
War  any  nation  had  ever  endured  and  we  came  out  of  that  crisis. 

In  1917,  after  desperately  trying  to  stay  out  of  a  war,  we  found  ourselves 
again  plunged  into  a  conflict  that  we  were  ill-prepared  to  fight,  but  we  rose  to  the 
occasion  and  we  won. 

In  the  1930's  we  found  a  situation  only  a  little  worse  than  the  depression  of 
1975  and  we  came  out  of  that. 

In  1941  we  again  engaged  in  a  World  Conflict  that  we  were  hardly  prepared 
to  fight,  but  we  rose  to  the  occasion  and  we  won  diat  one! 

I  think  we  will  come  out  of  tiiis  too — because  we  are  challenged  to  preserve 
that  which  we  love — our  country,  our  way  of  life,  and  our  industry — and  it  is  the 
very  least  we  can  do  to  improve  it  and  pass  it  on  as  a  viable  free  enterprise  to  those 
who  come  after  us.   I  close  with  a  poem  tiiat  expresses  this  quite  well: 

An  old  man,  traveling  a  lone  highway. 
Came  at  the  evening  cold  and  gray. 
To  a  chasm  vast  and  deep  and  wide, 
Through  which  was  fltmg  a  sullen  tide. 

The  old  man  crossed  in  the  twilight  dim. 
The  sullen  stream  held  no  fears  for  him. 
But  he  turned  when  safe  on  the  other  side, 
And  built  a  bridge  to  span  the  tide. 


680  Bulletin  658 — American  Railway  Engineering  Association 

"Old  man,"  cried  a  fellow  pilgrim  near; 
"You're  wasting  your  time  in  building  here; 
Your  journey  will  end  the  closing  day. 
You  never  again  will  pass  this  way. 

"You've  crossed  the  chasm  deep  and  wide. 

Why  build  you  this  bridge  at  eventide?" 

The  builder  lifted  his  old  gray  head: 

"Good  friend,  on  the  path  I've  come,"  he  said, 

"There  followeth  after  me  this  day 

A  youth  whose  feet  must  pass  this  way. 

"This  stream,  which  has  been  as  naught  to  me. 
To  that  fair-haired  youth  may  a  pitfall  he; 
He,  too,  must  cross  in  the  twilight  dim — 
Good  friend,  I'm  building  this  bridge  for  him." 


Advertisement 


680-1 


RTW  PORTABLE 
RAIL  GRINDERS... 


A  model  for  every  requirement. 

With  over  65  years  of  grinder  experience,  RTW  has 
developed  the  most  complete  line  of  versatile,  portable 
grinders  available  to  the  industry.  Whatever  your  need, 
there's  a  RTW  model  especially  designed  for  the  job. 

•  E-72  (shown  above),  a  flex-shaft  power  plant  with  a  variety  of  attachments 
for  multipurpose  use. 

•  E-1  (shown  below),  a  lightweight  flex-shaft  grinder  available  with  straight 
and  cup-wheel  hand  piece. 

•  P-6-L,  for  high-speed  precision  grinding  of  frogs  and  rail  joints. 

•  P-16  D.S.P.,  a  heavy  duty  unit  designed 
for  removing  overflow  metal  from  all 
types  stock  rails  and  switch  points. 

•  JG-970,  dual  head,  cross  grinder  for  high- 
production  rail  slotting. 

•  X-60,  a  single  head  cross  grinder. 

•  P-45-A,  cup-wheel  surface  grinder  for 
reforming  welded  rail  ends. 

Write  for  detailed  specification  sheets  on 
these  and  other  high-performance 
equipment  by  RTW. 


RTW 


Other  RTW  Maintenance  Equipment 

Grinders  (many  additional  models  not  listed  above) 
Tie  Handlers  •  Anchor  Cribbers 


RPI 


RAILWAY  TRACK-WORK  CO.  2560  East  Tioga  St  .  Philadelphia.  Pa   19134 

Agents,  Chicago— E SCO  Equipment  Service  Co  •  Houston  — Service  Equipment  &  Supply  Company 

Los  Angeles— Si mkins  Company  •  Louisville— T.  F  Going  •  St,  Louis  — R  E  Bell  Co 

S  Plainfield,  N, J, —  Eastern  Railroad  Equipment  Corp  •  Canada:  I\/lontreal— Woodings-Canada  Ltd. 

Export;  American  Equipment  Co.,  Boca  Raton.  Florida 


680-2 


Advertisement 


ai   it 


Portec's  On 
the  Move. 

4  Ways  We're 
Aggressively 
Supporting 
Your  Progress. 

Portec's  Transportation  Products 
Group  has  been  streamlined  and 
expanded.  To  provide  you  with 
better  service  for  your  track  and 
transportation  needs.  And  to 
develop  new  products  for  the 
challenging  years  ahead.  Listed 
here  are  some  of  the  Portec  products 
that  have  gained  world-wide 
acceptance.  Watch  for  news  of 
further  developments  —  the  kind  of 
innovations  you  expect  from  a  leader 
like  Portec. 

Paragon  Division 

Auto  Racks 

New  Fully  Enclosed  Multi-Levels 

with  Tri-Fold  Doors 
Bi-Level  Racks 
Tri-Level  Racks 
End  Door  Enclosure  — 

Multi-Level  Racks 

Other  Equipment 
Frame  Cars 

Cable  Reel  Cars 

Ingot  Mold  Cars 

Special  Equipment  Components 


Railway  Products  Division 

Rail  Anchors 

Improved  Fair® 
XL-1  Fair® 

Insulated  Rail  Joints 

Poly-Insulated 
Portec-Bond 
Continuous 
Armored  Continuous 
Components  for  Insulated  Rail  Joints 
Poly  Plates 

Double-Filament-Wound  Bushings 
Blue  Ribbon  Nylon  Epoxy  End  Posts 

Non-Insulated  Rail  Joints 

Portec-Bond 
Headfree  Toeless 
Headfree  Flanged 
Compromise 

Rail  Joint  Renewal  Insulation  Kits 
Mark  II  -  polymer  insulation 
Mark  III  -  polymer  insulation 

Rail  and  Flange  Lubricators 
Single  Rail 
Double  Rail 
Four  Bar  Type 

Rail  loint  Heater 

Portaole  Model  75  -  for  bonding 
joints 

Ties 

Wood  Ties 

DowMac  Concrete  Ties 

New  Products  in  1976 

Curv-Bloc 

Reinforcing  Strap  for  CWR 


Advertisement 


680-3 


RMC  Division 

Track  Machines 

Anchor  Adjusting  Machine 

AnchorMaster 

Auto-Spiker 

Ballast  Distributor  — 

Distributor/Cleaner 
BoltMaster 
Bridge  Tool  Machine 
Brush  Cutter 
Clip  Tightener 
Compressor  Cart 
LineMaster 

Rail  and  Joint  Straightener 
Rail  Saw-Drill  Combination 
SpikeMaster 
Spiker-Spacer 
TieMaster 
Tie  Plate  Broom 
Tie  Unloader 
Track  Broom 

Tampers 

Hydramatic-16 

Hydraulic-16 

Multi-Purpose  8 

Hydraulic  8 

Jack 

Switch  Spot 

Spot  Switch 

Snow  Blower 

Typhoons 

Hurricane  Jets 

Rail  Laying  Equipment 

Dual  Welded  Rail  Laying  Equipment 

Gauging  Machine 

Plug  Setter 

Rail  End  Hardening  Machine 

Rail  Oiler 

Rail-Laying  Auto-Spiker 

Rail  Anchor  Cart 

Scrap  Loader 

Spike  Distributor  Cart 

Tie  Plate  Gauger 


Spot  Systems 

Car  and  Locomotive  Pullers 
Jacks,  Jib  Cranes 
Retarders 

Shipping  Systems  Division 

Rail  Car  Tie-Down  Systems  and 

Components  for: 
Vehicles 

Automobiles,  Trucks,  Other  Vehicles 

Tractors,  Farm  Implements 

Heavy  Construction  Equipment 

Materials 

Automobile  and  Truck  Frames 

Lumber 

Cable  Reels 

Steel,  Steel  Plate,  Steel  Coil, 
Aluminum  Ingot 

Containers 

Fixed  and  Retractable  Locks 

Special  Components  for  Freight  Cars 

Bridge  Plates 

Hardened  Brake  Pins 

Center  Plates 

Other  Equipment 

Special  Tie  Down  Systems  for  Flat 
Bed  Trailers  —  fixed  and 
retractable  twist  lock  assemblies 
for  trailers  and  containerchassis 


I'uiciJbtjp 


inc. 


Transportation  Products 

3()<)  Wiiulsdi-  Drivo,  Oak  Brook,  Illinois  Cj052l 
Telephone:  (:U2)  :<2r)-():J(Kl 


680^ 


Advertisement 


Tai/imont 


RAILWAY      MOTOR      CARS 
AND     WORK      EQUIPMENT 


^^^B 

ss 

^^^^^E 

^^H 

^^^^^E 

^Hi 

^^^^^E 

BH 

^^^^^E 

^IH 

^^^^E 

■■1 

^^^^^E 

HHB 

^^^^^E 

BHH 

^^^^^E 

^■i 

^^^^^E 

HHi 

^^^^^E 

■■■ 

^^^^^E 

HH 

^^^^^E 

HBH 

^^^^^E 

HiH 

^^^^^E 

^■1 

^^^^^E 

^^B 

^^^^^E 

l^Hj 

^^^^^E 

IHH 

^^^^Hi 

I^BI 

^^^^^E 

■■ 

^^^^^E 

HBB 

^^^^^■i 

■■ 

^^^^^E 

HBI 

^^^^^E 

HHI 

^^^^^E 

^■1 

^^^^^E 

IHH 

^^^^^E 

■■i 

^^^^^E 

I^B 

^^^^^E 

■■■ 

^^^^^E 

I^^B 

^^^^^E 

^^H 

^^^^^E 

^^H 

^^^^^E 

i^H 

^^^^h 

■■1 

ON   THE  JOB 
COUI^tS 

INSPECTION  MOTOR  CARS 
SECTION  MOTOR  CARS 
GANG  MOTOR  CARS 
PUSH  CARS  AND  TRAILERS 
HY-RAIL  EQUIPMENT 
BALLAST  MAINTENANCE  CARS 
WEED  MOWERS 
TOW  TRACTORS 
RAIL  GRINDERS 
DERRICK  CARS 
HYDRAULIC  POWER  TOOLS 
TRACK  LINERS 


TRACK  LINING  LIGHT 

SPIKE  DRIVERS 

TIE  REMOVERS 

TIE  HANDLERS 

RAIL  LIFTERS 

TIE  SHEARS 

TIE  BED  SCARIFIERS 

SPIKE  PULLERS 

TIE  PLUG  INSERTERS 

OIL  SPRAYERS 

TIE  SPRAYERS 

TIE  INSERTERS 


THESE  UNITS  ARE  ACTUATED  EITHER  COMPLETELY 
OR  PARTIALLY  BY  HYDRAULIC  POWER 


FAIRMONT  RAILWAY  MOTORS,  INC.,  FAIRMONT,  MINNESOTA  56031 


Advertisement 


680-5 


The  Allegheny  Insulated  Rail  Joint- 

Designed  to  withstand  the  heaviest  trafRc 
in  welded  rail 


This  modern  joint  cements  roil  ends  in  position  and  thereafter 
resists  all  forces  imposed  by  temperature  and  simultaneous  forces 
of  live  loads  to  move  them. 

This  joint  makes  welded  rail  truly  continuous.  It  promises  you  years 
of  service  without  maintenance  costs.  It  reduces  rail  and  wheel  batter 
to  a  previously  unknown  minimum.  It  employs  the  safety  of  steel  splice 
bars.  It  can  be  assembled  in  the  shop  or  field.  It  has  been  tested  in 
service  and  AAR   laboratories.  It  saves  you  lots  of  money. 

Allegheny  Drop  Forge  Company 

Subsidiary  of  Tasa  Corporation 
2707  Preble  Avenue  •  Pittsburgh,  Pa.   15233 


680-6 


Advertisement 


Reduce  Maintenance  Costs 
Increase  Ton  IVIiles  of  Service 


with 

^^4 

■ 

i) 

P 

1 

PEWO 

RAIL 

ERVICES 


,i»-^^ 


SoutKam  fnacific 


Discover  how  to  get  more 
ton  miles  of  Service,  w/liiie  -       , 

reducing  track  maintenance  and 
Increasing  rail  life,  by  using  Speno 
Ballast  Cleaning  and  Rait  Grinding. 

THROUGHOUT  THE  CONTINENT 

SPEND  RAIL  SERVICES,  Inc. 

An  Affiliate 'of  Trans  Union  Corporation 
Clarl<  Street,  Box  219,  East  Syracuse,  New  Yori<  13057 

SPENO  INTERNATIONAL,  S^A.  lEC-HOLDEN,  LTD. 

22  Pare  Chateau  Banquet,  naff  8^®°  '^•''®  **®  ^'®®^®  "°^^ 

Geneva,  Switzerland  ■»'▼■  Montreal,  Canada  H4T1G8 

(For  Hail  Grinding  Outside  the  North  American  Continent)  :;"  :X 


Ad\'ertisement 


680-7 


Thermit 


way! 


...>*  MODERN,  SELF-PREHEAT  METHOD  OFFERING: 

D     AUTOMATIC,  ERROR-FREE  PRE-HEATING  AND  TAPPING 

OF  WELD   METALS 
D     EASY,  COLO  REMOVAL  OF  RISERS 
D     NO  EQUIPMENT  TO  PURCHASE  OR  LEASE 

Call  or  Write  For  FREE  Details... Plus,  Job-Site  Demonstration 


US.  THERMIT  INC 


Lakehurst.  New  Jersey  08733  •  (201)657-5781  Teiex;  TEGOWHP  710-568-1352 


680-8 


Advertisement 


KERITE 
CABLE 


Mf  MOr/f 


For  dependability  in  actual  use,  no  other  cable 
matches  Kerite.  We  believe  you  will  be  im- 
pressed by  the  evidence. 


THE   KERITE  COMPANY 

PRINCIPAL  OFFICES:  Boston;  Chicago;  New 
York;  Philadelphia;  San  Francisco;  and 
Seymour,  Connecticut  •  Sales  Representa- 
tion throughout  the  United  States.  A  sub- 
sidiary of  Harvey  Hubbell   Incorporated. 

RITE  insulation  that  makes  the  difference 


"^iM^yiiMK- 


Advertisement 


680-9 


Safetran's  new,  portable,  heavy  duty: 


Whiz 


w 


ABRASIVE  TYPE  RAIL  SAW 

Model  082000-X 


Quick  Attachment  to  the  Rail. 


Sel(-Cenlering  to  lit  any 
weight  ot  rai(.  60  lbs. 
through  152  lbs. 
(without  additional 
adapters  or  brackets). 


Support  arm  pivoted 
lor  oscillating  cutting 
action. 


Accurate  cuts  provided 
by  the  unique  abrasive 
wheel  guide. 


Fully  reversible  power 
unit  support  arm  lor  pre- 
cision rail  cuts  Irom 
either  side  ol  rail  with  the 
engine  in  the  normal  up- 
right position  at  all  times. 


Lightweight  —  Saw  -  44  Lbs. 

Fixture  -  37.5  Lbs 


Relation  ol  cutting  wheel 

deflects  all  sparks  toward 

ground  at  all  times. 


Air  breather  intake  is  tree 
of  abrasive  dust. 


Power  unit  can  be 

placed  on  either  side 

ol  the  rail  (in  upright 

position)  lor  starting 

or  servicing. 


Sa  let  ran  superior  14" 

abrasive  cutting  blades 

cut  safe,  last  and 

accurate. 


180°  rotation  ol  saw 
permits  lull  usage  ol  blade. 


Carrying  case  available. 


for  more  information  or 
demonstration  —  contact: 


■^.^^^'■^^4^ 


Safetran  Systems  Corporation 

7721  National  Turnplka  •  Louiavllla.  KV  <0214  •  (502)  3(1-ieS1 


680-10  Advertisement 


CLEARANCES 

RAILWAY  LINE 
CLEARANCES 

Presents  vertical  and  horizontal  clearances,  and  weight  limita- 
tions for  more  than  250  railroads  of  North  America.  Also  selected 
maps,  instructions,  and  A.A.R.  diagrams.  Published  annually  in 
June  with  interim  change  circulars.  Subscription  $8  ($5  to  reg- 
istrant companies).  N.Y.  residents  add  sales  tax. 


EQUIPMENT 

THE  OFFICIAL  RAILWAY 
EQUIPMENT  REGISTER 

Describes  by  reporting  marks  and  series  numbers  freight  cars 
operated  by  railroads  and  private  car  companies  of  North  Amer- 
ica, with  inside  and  outside  dimensions,  cubic  and  pounds 
capacities,  A.A.R.  Mechanical  Designations  and  Car  Type  Codes. 
Includes  interchange  points  for  railroads  and  home  points  for 
private  car  owners,  with  instructions  regarding  payments,  move- 
ments and  repairs.  Separate  section  for  railroad-owned  heavy 
capacity  and  special  type  flat  cars,  and  A.A.R.  Car  Service  and 
Car  Hire  Rules,  plate  diagrams,  and  selected  circulars  and 
directives.  Complete  list  of  A.A.R.  Reporting  Marks  and  Uni- 
form Alpha  Codes.  Published  quarterly.  Subscription  $45  ($34 
to  registrant  companies).  Single  copy  $15  ($10  to  registrant 
companies). 


PUBLISHED  BY 

NATIONAL  RAILWAY  PUBLICATION  COMPANY 

424  WEST  33rd  ST.  •  NEW  YORK,  N.Y.  10001  •  (212)  563-3319 


Advertisement 


LORAM 

Modern  Maintenance 
of  Way  Equipment 

with  an  established 
track  record . . . 


WINCH  CART 


SHOULDER  BALLAST  CLEANER 


. . .  designea 
to  do  the  job 
easier,  quicker 
and  at  less  cost 
—  witti  your 

men  or 

ours! 


rrSllQI'i'HB   V|MK:||.^^|r'i|£PIS||       i|{rj,<^ 


AUTOTRACK  WITH  PLOW  AND  SLED 


THE  ANSWER  TO  YOUR  TRACK  REHABILITATION  PROGRAM 


M£M  B  £/t 

fPf 


LORAM  RAILWAY  MAINTENANCE  EQUIPMENT  FOR: 

•  Shoulder  Ballast  Cleaning  •  Raising  Track  •  Resurfacing  • 
Reballasting  •  Replacing  Ties  •  Undercutting  •  Ballast  Cleaning 

•  Rail  Grinding  Single  or  Multiple  track— Mainline  or  Yard  tracks 

CONTRACT,  SALE  or  LEASE 


FOR  FULL  DETAILS 
OR  SHOWING  OF 
OPERATING  FILMS. 
WRITE  OR  CALL  TODAY 


MAINTENANCE  OF  WAY,  INC. 

3900  Arrowhead  Drive  •  Hamel,  MN  55340  U.S.A. 
PHONE:  (612)  478-6014  •  TELEX:  29-0391;  Cable.  LORAM 


680-12 


Advertisement 


Nordberg 

railway 

equipment. 


Saves  time 
and  money 
ail  along 
the  line. 


SELF-PROPELLED 
ADZER 

HYDRA-SPIKER 

LINE  INDICATOR 

PLATE  PLACER 

POWER  JACK 

RAIL  DRILL 

RAIL  GANG  SPIKER 

RAIL  GRINDERS 

ONE  MAN  SCARIFIER 
AND  INSERTER 

SPIKE  HAMMER 

SPIKE  PULLER 

SPIKE  STRAIGHTENER 

SURF-RAIL  GRINDER 

SWITCHLINER 

TRACK  INSPECTOR 

TIE  DRILL 

TIE  SPACER 

TRACKLINER 

DUN-RITE  GAGER 

X-LEVEL  INDICATOR 


■^ 


Right  of  way 
maintenance  and 
construction  is  a  tough 
job,  and  getting  tougher. 
Nordberg  railway 
equipment  is  precision 
engineered  to  keep 
things  rolling  — to  get 
the  job  done  on  time, 
at  low  cost.  Write 
Rexnord  Railway 
Equipment  Division, 
Box  383,  Milwaukee, 
Wisconsin  53201. 


V 


Rexnord 
IIIUMK 


•^f^i 


Ad\'ertisement 


680-13 


Solid 


Design  and  construction  features  of  the 
hook,  throat  and  pad  work  together  to 
provide  real  gripping  force  with 
enormous  reserve  power. 


Positive  anti-overdrive  stop. 


Generous  hook  and  throat 
base  pads  assure  positive 
seating. .  firm  grip. 


Stamped  code  identifies 
rail  size  application. 


Channeloc 


Channeloc  presents  a  deep,  full  length  profile  to  the  tie  for  maximum 
tie-bearing  integrity.  Its  large,  smooth  bearing  surface  enables 
Channeloc  to  evenly  transfer  the  thrust  of  rail  creep  to  the  tie 
without  affecting  service  life  of  the  tie,  plate  or  spike. 

Channeloc  is  easily  applied,  removed  and  re-applied. 


>  protected  by  U  S  Paierii 


;  3  1 02.690-3  1 1 8.-327-3. 1  59, 1 98 


mue  lEMPER. 

An  Allegheny  Ludlum  Industries  Company 


680-14 


Advertisement 


ROOC 


r 


PRODUCTIVITY  MACHINES 
for  maintaining 

track  standards 


Anchor  Master,  one  of  40  RMC  machines  for  maintaining  track  standards. 


PORHEC 


inc. 


RMC  Division 

P.O.  Box  1888 

Pittsburgh,  Pennsylvania  15230 

Telephone:  (412)  782-1000 


Advertisement 


680-15 


Repair  at  10% 

of  replacement 

cost! 

The  structural  cracks  in  this 
bridge  are  being  "welded"  with 
epoxy.  Osmose  epoxy  injec- 
tion restores  structural  integrity 


without  service  interruptions  at 
a  fraction  of  replacement  cost. 


The  proven  OSMOSE  method: 

•  ANALYSIS  •  CLEANING 

•  SEALING  •  CONTROLLED 
PRESSURE  INJECTION 

•  DETAILED  INSPECTION 
REPORTS 


OSMOSE  RAILROAD  DIVISION 


4915  Monona  Drive 
Madison,  Wis.  53716 


680-16  Advertisement 


TELEWELD 


INC. 


MEMBER 


Rail  Maintenance  Service 

Rail  End  Welding 

Rail  End  Hardening  0Df 

CWR  Joint  Normalizing  ffff' 

Frog  and  Switch  Welding 

Rail  Maintenance  Equipment 

Custom  Manufacturing  and  Fabrication 

Joint  Bar  Shims 

Rail  Anchor  Shims 

Rail  End  and  Frog  and  Switch 

Welding  and  Grinding  Machines 
CWR  Heating  and  Cooling  Equipment 
Rail  Flaw  Testing  Equipment 
Telebrineller  Portable  Hardness  Tester 


Infra-RMl  H*at*r  for  Curing  AdhMlv*  Bonded  Roll  Joints 


TELEWELD  INC.,  416  NORTH  PARK  ST.,  STREATOR,  ILL.  61364 

Write  for  details  of  the  TELEWELD  process  for  restoring  rail  ends. 


REPORT  OF  EXECUTIVE  DIRECTOR 


681 

BnL  6S8 


1 


Report  of  the  Executive  Director 

March  24,  1976 

To  THE  Members: 

The  1975  Association  year  w  as  a  success  from  most  aspects.  Membership  remains 
high,  with  a  loss  of  only  five  members  during  the  year,  a  good  showing  in  view  of 
the  economic  difficulties  experienced  by  tlie  railroads.  Financially,  the  AREA  had 
an  adequate  year.  While  our  financial  statement  for  the  year  shows  a  deficit  of 
$9814,  this  was  due  to  the  necessity  of  replacing  our  stock  of  Manual  binders  and 
will  be  recaptured  over  a  two-  to  three-year  period  from  the  sale  of  Manuals. 
Otherwise,  actual  receipts  closel>  matched  actual  expenditures.  To  maintain  receipts 
at  the  highest  possible  level,  the  Board  of  Direction  and  staff  of  the  Association 
solicit  the  active  cooperation  and  support  of  AREA  members  by  interesting  others 
in  becoming  members,  by  paying  their  annual  dues  early  in  the  year,  and  by  bringing 
the  AREA  Bulletin  to  the  attention  of  supply  companies,  contractors  and  consulting 
engineers  as  a  prime  advertising  medium. 

Major  Meetings  During  1975  Association  Year 

The  11th  Regional  Meeting  of  the  Association  was  held  at  the  Hotel  Vancouver, 
Vancouver,  B.  C,  Canada,  on  October  30,  1975.  It  was  attended  by  221  AREA 
members  and  guests.  The  meeting  was  organized  and  directed  by  John  Fox,  then 
assistant  chief  engineer,  now  chief  engineer,  Canadian  Pacific  Rail,  and  chairman  of 
the  AREA  Board  Committee  on  Regional  Meetings.  It  was  presided  over  by  AREA 
President  John  T.  Ward,  senior  assistant  chief  engineer.  Seaboard  Coast  Line 
Railroad. 

The  75th  Technical  Conference  of  the  AREA  and  the  1975  Annual  Meeting 
of  the  Engineering  Division,  Association  of  American  Railroads,  was  held  at  the 
Palmer  House,  Chicago,  on  March  22-24,  1976.  Total  registration  was  980,  comprised 
of  470  railroad  men  and  510  non-railroad  men,  and,  in  addition,  156  ladies.  The 
program  of  the  Conference  consisted  entirely  of  features — some  general,  others 
.sponsored  by  our  technical  committees.  No  committee  reports  were  given  since  all 
of  them  had  been  published  in  tlie  various  issues  of  tlie  Bulletin  prior  to  the 
Conference.  The  Engineering  Division  Session  was  held  on  Monday  afternoon, 
March  24,  and  consisted  of  reports  on  the  activities  of  the  Division  during  1975 
and    a   number   of   timely    and   informative   addresses   and   illustrated   presentations. 

The  1976  meetings  were  presided  over  by  John  T.  Ward,  senior  assistant  chief 
engineer,  Seaboard  Coast  Line  Railroad,  president  of  the  AREA  and  chainnan  of 
the  AAR  Engineering  Division.  The  address  at  the  Annual  Luncheon  was  given  by 
W.  T.  Rice,  chairman  of  the  Board,  Seaboard  Coast  Line  Railroad. 

MEMBERSHIP 

As  mentioned  above,  the  membership  statistics  show  a  loss  of  five  members 
during  the  year,  a  warning  to  AREA  members  not  to  relax  their  efforts  to  interest 
their  friends  and  associates  both  inside  and  outside  the  railroad  industry,  and  allied 
to  it,  in  AREA  membership.  Approximately  250  new  members  are  needed  each  year 
simply  to  overcome  normal  attrition.  A  wide  range  of  people  are  qualified  for  AREA 
membership,  and  would  benefit  by  it,  as  would  the  Association.  These  qualifications 

683 


684 


Bulletin  658 — American  Railway  Engineering  Association 


are  given  in  Article  II,  Sections  A,  B,  E  and  F,  of  the  AREA  Constitution  ( see  pages 
699  to  701  in  this  Bulletin.)  Yovu  help  is  earnestly  solicited  in  this  vital  area  of 
Association  efforts. 


Membership 


Membership  Years 


1974 


1975 


(Cor- 
rected) 


Membership  as  of  January   1    

Nevv'  Members  during  year    210 

Reinstatements  during  year    12 

Gain  or  Loss  in  Junior  Members +24 


3391 


3328 


175 

5 

—  14 


246 


166 


Deceased  during  year 
Resigned  during  year  . 
Dropped  during  year  . 


.30 
48 
90 


43 
32 
96 


168 


171 


Net  Gain  or  Loss    +  78 


-     5 


3469 


3323 


Membership  Classification  by  Years 


The  year  1968  begins  on  February  1  and  ends  on  December  31.  Each  succeed- 
ing year  begins  on  January  1  and  ends  on  December  31. 


1968 


1969 


1970 


1971 


1972 


1973 


1974 


1975 


Life    433  437 

Member     ...  2659  2577 

Associate   ...  258  264 

Junior    56  55 

Honorary     .  . 


Totals    3406 


3333 


443 

451 

560 

562 

472 

474 

2579 

2502 

2549 

2492 

2500 

2509 

257 

244 

247 

232 

238 

241 

62 

67 

96 

105 

111 

93 

3352 

6 

6 

3341 

3264 

3391* 

3328"* 

3326 

*•  Adjusted  from   3310  to  match  carryover  numbers  with  existing  records. 
*"  Corrected  from  3469  by  actual  count  of  membership  cards  on   12—31—74. 

Deaths    During    1975    Association    Year 

From  May  1,  1975  to  March  24,  1976,  notice  was  received  at  Association  Head- 
quarters of  the  deaths  of  36  members,  4  more  than  the  previous  year  and  6  fewer 
than  2  years  ago. 

One  of  the  deceased  was  a  past  president  (1966-1967)  of  the  Association — 
J.  M.  Trissal  (M  '33,  L  '70),  retired  vice  president — real  estate,  Ilhnois  Central 
Railroad.  He  was  also  a  member  of  Committee  9 — Highways,  1942  to  1969,  serving 
as  chainiian,  1959-1961;  and  a  member  of  former  Committee  18 — Electricity,  for 
some  10  years.  Another  was  a  past  director  (1941-1943)— C.  E.  Smith  (M  '09,  L  '45), 
retired  vice  president.  New  York,  New  Haven  &  Hartford  Railroad.  Mr.  Smith 
was  a  member  of  Committee  15 — Steel  Structures,  1911-1921;  Committee  14 — Yards 
and  Terminals,  1922-1926;  and  Committee  21 — Economics  of  Railway  Location, 
1930-1938. 


Report  of  Executive  Director 


685 


COMMITTEES   OF    1975    BOARD   OF   DIRECTION 


Executive 

J.  T.  Ward,  Chairman 
John  Fox 
b.  j.  worley 

D.  V.  Sartore 
R.  F.  Bush 

Membership 

R.  W.  Pember,  Chairman 

B.  E.  Pearson 

P.  L.  Montgomery 

Mike  Rougas 

R.  L.  Gray 

Finance 
R.  F.  Bush,  Chairman 

B.    H.    WORLEY 

E.  Q.  Johnson 
J.  W.  DeValle 
E.  H.  Waring 

Research 

R.  M.  Brown,  Chairman 

D.  V.   Sartore 

E.  Q.  Johnson 
Mike  Rougas 
R.  L.  Gray 

G.  H.  Maxwell 

Technical   Activity 
Mike  Rougas,  Chairman 
R.  W.  Pember 
W.  E.  Fuhr 
J.  W.  DeValle 
E.  H.  Waring 


Publications 

John  Fox,  Chairman 

D.  V.  Sartore 

P.  L.  Montgomery 

E.  C.    HONATH 

J.  W.  DeValle 

Regional    Meetings 
John  Fox,  Chairman 
E.   Q.  Johnson 

E.    C.    HoNATH 

William  Glavin 
G.  H.  Maxwell 

Conference   Programs 
R.  L.  Gray,  Chairman 
B.  J.  Worley 
B.  E.  Pearson 
P.  L.  Montgomery 
William  Glavin 

Advertising    (Special) 
E.  G.  Honath,  Chairman 
R.  F.  Bush 
W.  E.  Fuhr 
E.   H.   Waring 
G.  H.  Maxwell 


A  number  of  other  deceased  meml:)ers  are  worth>  of  note,  either  for  the  promi- 
nent positions  they  had  attained  or  for  the  many  years  they  had  devoted  to  committee 
service.  They  are:  N.  V.  Back  (M  '51),  retired  chief  engineer,  Toronto,  Hamilton  & 
Buffalo  Railway;  Edgar  Bennett  (M  '20,  L  '55),  retired  assistant  chief  engineer, 
Southern  Railway,  member  of  Committee  27 — Maintenance  of  Way  Work  Equip- 
ment, 1940-1956,  serving  as  chairman  194&-1948;  O.  C.  Benson  (M  '28,  L  '66), 
retired  director  of  budgets,  Boston  &  Maine  Corporation,  member  of  Committees 
9— Highways,  1948-1953,  5— Track,  1956-1958,  27— Maintenance  of  Way  Work 
Equipment,  1958—1961,  and  22 — Economics  of  Railway  Construction  and  Mainte- 
nance, 1961-1968;  H.  M.  Booth  (M  '24,  L  '60),  retired  division  engineer,  St.  Louis- 
San    Francisco    Railway,    member    of    Committees    6 — Buildings,    1949-1961,    and 


Bui.  G58 


686  Bulletin  658 — American  Railway  Engineering  Association 

14 — Yards  and  Terminals,  1961-1965;  L.  B.  Cann  (M  '48),  chief  engineer,  Richmond, 
Fredericksburg  &  Potomac  Railroad,  member  of  Committees  27 — Maintenance  of 
Way  Work  Equipment,  1951-1963,  and  22 — Economics  of  Railway  Construction 
and  Maintenance,  1964  until  time  of  his  death;  R.  P.  Davis  (M  '14,  L  '49),  dean 
emeritus.  College  of  Engineering,  West  Virginia  University,  member  of  Committees 
15 — Steel  Structures,  1923  until  the  time  of  his  death,  having  been  elected  Member 
Emeritus  in  1955,  and  24 — Engineering  Education,  1942  until  the  time  of  his  death, 
having  been  elected  Member  Emeritus  in  1959;  R.  P.  Hughes  (M  '22,  L  '57),  member 
of  former  Committee  17 — Wood  Preservation,  1934-1960,  and  of  Committee  3 — 
Ties  and  Wood  Preservation,  1953  until  the  time  of  his  death,  having  been  elected 
Member  Emeritus  in  1963;  L.  S.  Jeffords  (M  '20,  L  '63),  retired  vice  president 
operations,  Atlantic  Coast  Line;  A.  S.  Krefting  (M  '35,  L  '70),  retired  chief  engineer, 
Soo  Line  Railroad,  member  of  Committee  14 — Yards  and  Terminals,  1945  until  the 
time  of  his  death,  having  served  as  chairman,  1956-1958,  and  having  been  elected 
Member  Emeritus  in  1974;  W.  B.  Leaf  (M  '39,  L  '64),  retired  research  physicist, 
Denver  &  Rio  Grande  Western  Railroad,  member  of  Committees  13 — Environmental 
Engineering,  1943-1949,  and  4— Rail,  1949-1959;  J.  P.  Morrissey  (M  '44,  L  '69), 
retired  engineer — staff,  Erie  Lackawanna  Railway,  member  of  Committees  22 — 
Economics  of  Railway  Construction  and  Maintenance,  1951-1959,  and  31 — Continu- 
ous Welded  Rail,  1966-1973;  R.  A.  Shier  (M  '49),  director  of  engineering,  Canadian 
Transport  Commission;  M.  M.  Stansbury  (M  '47,  L  '72),  retired  engineer  roadway 
equipment,  Norfolk  &  Western  Railway,  1948-1973;  L.  J.  Sverdrup  (M  '39,  L  '75), 
chairman  of  the  board  and  chief  executive  officer,  Sverdrup  &  Parcel  and  Associates, 
Inc. 

ACTIVITIES  OF  TECHNICAL  COMMITTEES 

Assignments 

During  1975  the  20  technical  committees  of  the  Association,  including  the 
Special  Committee  on  Scales,  worked  on  165  assignments,  10  of  which  were  new. 
The  work  of  the  Special  Committee  on  Concrete  Ties  involved  the  revamping  of 
the  preliminary  Specification  for  Concrete  Ties  and  Fastenings  it  had  developed  and 
published  in  Bulletin  644,  September-October  1973;  and  pubhshing  the  revised 
version  in  Part  1  of  Bulletin  655,  November-December  1975,  with  the  recom- 
mendation that  it  be  adopted  and  published  in  the  Manual  as  Part  10,  Chaper  3. 
During  the  year  the  Board  of  Direction  assigned  a  number  to  the  Committee  on 
Electrical  Energy  Utilization — No.  33. 

AREA  committee  work  is  directed  toward  the  preparation  of  reports  for  infor- 
mation, toward  revising  material  appearing  in  the  AREA  Manual  for  Railway 
Engineering  and  the  Portfolio  of  Trackwork  Plans,  and  toward  carrying  out  .special 
projects  related  to  their  assigrunents. 

The  1975  statistics  show  that  our  20  standing  committees  produced  one  or 
more  information  reports  on  40  of  their  165  assignments  (not  including  Assign- 
ment A).  In  addition,  the  standing  committees  submitted  8  reports  containing 
Manual  recommendations,  and  the  Special  Committee  on  Concrete  Ties  one  such 
report,  all  of  which  were  published  in  Part  1  of  the  November-December  Bulletin, 
separate  from  the  committee  reports.  Furthermore,  most  committees  presented  brief 
status  statements  with  respect  to  assignments  on  which  they  made  no  formal  report. 

During  1976  the  technical  committees  as  a  whole  will  work  on  155  assignments, 
12  of  them  new. 


Report  of  Executive  Director  687 

Classification  of  Material 

The  work  of  AREA  committees  during  1975  was  so  diversified  tliat,  as  in  other 
years,  it  is  impossible  to  do  other  tlian  refer  to  it  in  general  terms  in  a  report  such 
as  tliis.  However,  tlie  following  is  a  general  categorical  classification  of  the  results  of 
this  work  as  published  in  the  technical  Bulletins  of  the  Association. 

Recommendations  pertaining  to  the  development,  revision  or  deletion  of  19 
different  specifications  and  recommended  practices  for  inclusion  in  the  AREA 
Manual;    30  reports   on  current  developments   in  engineering  practice  and  design; 

I  report  on  current  developments  in  systems  engineering,  data  processing  and  the 
use  of  computers  to  solve  problems  in  railway  construction,  operation  and  main- 
tenance; 1  report  dealing  with  pollution  control;  2  reports  dealing  with  the  training 
and  recruitment  of  employees;  3  economic  and  analytical  studies;  4  reports  on 
relations  with  public  authorities;  4  reports  dealing  witli  statistics;  and  1  bibliography. 

Committee  work  affecting  the  AREA  Manual  included  the  presentation  of  1 
specification  for  adoption;  the  revision  of  1  specification;  the  presentation  of  2 
tentative  specifications;  the  presentation  of  5  recommended  practices  for  adoption; 
and  the  revision  or  rewriting  of  10  recommended  practices. 

Discussion  Section 

During  the  1975  Association  year,  subcommittee  reports,  papers  and  addresses 
published  in  the  technical  issues  of  tlie  Bulletin  were  again  advertised  as  open  for 
discussion. 

Personnel  of  Committees 

At  tlie  beginning  of  die  1975  Association  year  1072  members  were  assigned  to 
1166  places  on  the  Association's  20  technical  committees.  This  compares  with  1090 
members  assigned  to  1186  places  at  the  beginning  of  tlie  previous  year.  In  addition, 

II  members  were  assigned  to  the  Special  Committee  on  Concrete  Ties. 

AREA  committees  again  were  limited  to  a  maximum  membership  of  70  and  to 
the  number  from  each  railroad  depending  on  the  total  number  of  AREA  members 
on  the  railroad. 

In  the  1975  Handbook  of  Committee  Activity  the  names  of  committee  chair- 
men, vice  chairmen,  secretaries  and  subcommittee  chairmen  were  again  shown  in 
boldface  type  at  the  head  of  each  committee  roster. 

The  number  of  members  so  far  assigned  to  committees  for  1976  ( as  of  April  1 ) 
is  somewhat  higher  than  a  year  ago;  specifically  1080  members  assigned  to  1178 
places. 

Committee  Meetings 

To  progress  work  on  their  assigmiients  the  20  standing  AREA  technical  com- 
mittees held  a  total  of  42  meetings  during  the  1975  Association  year,  4  fewer  tlian 
during  the  previous  year.  In  addition,  the  Special  Committee  on  Concrete  Ties  held 
1  meeting  in  1975.  As  is  usually  the  case,  the  majority  of  these  meetings  were  held 
at  Chicago  or  at  points  cential  to  the  largest  number  of  committee  members.  The 
exceptions  were  scheduled  to  permit  inspections  of  facilities,  operations  or  projects 
which  could  be  seen  only  by  going  to  those  points. 

Of  the  42  meetings  held  during  the  1975  Association  year,  18  were  held  at 
Chicago;  2  each  were  held  at  Memphis,  Tenn.,  St.  Louis,  Mo.,  and  St.  Paul,  Minn., 
and  18  were  held  at  as  many  other  cities. 


688  Bulletin  658 — American  Railway  Engineering  Association 

The  number  of  meetings  held  during  the  year  by  each  committee  was  dictated 
by  the  scope  of  tlieir  work  and  odier  considerations.  Accordingly,  1  committee  held 
4  meetings,  5  committees  each  held  3  meetings,  10  committees  each  held  2  meetings, 
2  committees  each  held  1  meeting,  and  1  committee  held  no  meeting. 

ASSOCIATION  PUBLICATIONS 

In  1975  the  AREA  Bulletin  was  again  published  on  the  scheduled  five-time 
basis.  The  Bulletin  Issues  in  Proceedings  Volume  77,  1976,  are  Nos.  654,  September- 
October  1975;  655,  November-December  1975;  656,  January-February  1976;  and 
658,  June-July  1976.  Bulletin  657  is  the  blue-covered  April-May  Directory  Issue, 
which  is  not  a  part  of  the  Annual  Proceedings  of  die  Association. 

The  1975  Handbook  of  Committee  Activity  was  published  in  April  and 
distributed  to  all  committee  members  at  that  time. 

The  Manual  recommendations  of  committees  as  published  in  Part  1  of  Bulletin 
645,  November-December  1973,  and  Part  1  of  Bulletin  650,  November-December 
1974,  were  approved,  with  certain  exceptions,  by  the  Board  of  Direction  at  its 
meeting  on  August  13,  1975.  The  approved  material  in  both  Bulletins  was  com- 
bined and  issued  in  a  single  Supplement,  known  as  the  1974-1975  Supplement. 
The  Supplement  consists  of  349  sheets  (698  pages)  and  includes  three  complete 
Manual  chapters:  3 — Ties  and  Wood  Preservation,  22 — Economics  of  Railway 
Construction  and  Maintenance,  and  28 — Clearances.  The  revised  sheets  for  Chapter 
15  include  a  completely  rewritten  Specification  for  Movable  Railway  Bridges. 

No  Supplement  to  the  AREA  Portfolio  of  Trackwork  Plans  was  issued  in  1974 
or  1975. 

A  letter  dated  January  9,  1976,  was  sent  to  AREA  members  in  regard  to  the 
availability  of  the  Volume  76  (1975)  Bulletin  Binder.  Attached  to  this  letter  was 
a  simple  order  form  for  the  use  of  members  desiring  to  purchase  one  or  more  copies 
of  these  binders.  The  member  price  of  the  Volume  76  binder  was  established  at 
$5.00  each,  including  handling  and  shipping  ( $5.50  each,  including  shipping  and 
handling,  for  members  in  Central  and  South  America  and  overseas  countries).  Each 
of  these  hard-cover  book-type  binders  is  designed  to  house  all  the  Bulletins  in  a 
publication  year,  which  starts  with  the  September-October  issue  and  ends  witli  the 
June-July  issue,  widi  the  exception  of  die  blue-covered  April-May  Directory  issue 
which  is  not  punched  for  binding. 

The  June-July  1975  Bulletin  contained  all  material  presented  at  the  March 
1975  Technical  Conference  having  technical  and  historic  interest — the  president's 
address,  reports  of  the  executive  director  and  treasurer,  features  and  committee 
reports  not  previously  published  in  die  committee  report  Bulletins. 

The  January-February  1976  Bulletin  contained,  in  addition  to  committee 
reports,  five  of  the  addresses  presented  at  the  Regional  Meeting  held  at  Vancouver, 
B.   C,  on  October  30,   1975. 

LOOKING  AHEAD 

The  next  Annual  Technical  Conference  of  the  AREA  will  be  held  at  the  Palmer 
House,  Chicago,  on  March  29-31,  1977.  In  conjunction  therewith.  Railway  Engi- 
neering-Maintenance Suppliers  Association,  Inc.  (REMSA)  will  stage,  at  McCormick 
Place,  Chicago,  an  exhibit  by  more  than  100  companies  showing  their  latest  develop- 
ments in  machines,  equipment  and  materials  used  in  railway  engineering  and 
maintenance  operations. 


Report  of  Executive  Director  689 

The  next  Regional  Meeting  will  be  held  at  Pittsburgh,  Pa.,  on  October  21, 
1976.  Arrangements  and  planning  for  the  meeting  are  under  the  direction  of  AREA 
Director  Mike  Rougas,  chief  engineer,  Bessemer  &  Lake  Erie  Railroad.  In  1977  the 
Regional  Meeting  will  be  held  at  New  Orleans,  La. 

As  reported,  our  membership  le\el  remains  high,  considering  die  reduction  of 
engineering  employees  on  the  railroads,  die  imfa\orable  economic  situation  that 
has  prevailed,  and  other  factors  which  pre\ented  participation  in  Association  activi- 
ties, and  our  financial  situation  remains  sound — the  Association  is  still  going  strong. 
Keeping  it  strong  will  require  that  the  Association  accomplish  its  professional 
responsibilities  in  behalf  of  the  engineering  profession  and  tiie  raihoad  industry 
expeditiously  and  efficiently,  and  this  it  can  do  with  the  active  support  of  its  officers, 
directors  and  members,  and  all  railroad  engineering  and  maintenance  officers. 

Respectfully  submitted. 

Earl  W.  Hodgkins, 
Executive  Director  and  Secretary 


Beceageb  jHcmbersi 

N.  V.  Back  (M  '51) 
Retired    Chief    Engineer,    Toronto,    Hamilton    &    Buffalo    Railway,    Hamilton,    Ont. 

A.  L.  Bartlett  (M  '20,  L  '49) 
Laguna  Hills,  Calif. 

B.  A.  Bates  (M  '28,  L  '63) 
Retired   Industrial   Engineer,   Southern   Railway  System,   McAdenville,   N.   C. 

Edgar  Bennett   (M  '20,  L  '55) 
Retired    Assistant    Chief    Engineer,    Southern    Railway    System,    Knoxville,    Tenn. 

O.  C.  Benson  (M  '28,  L  '66) 
Retired   Director   of   Budgets,   Boston  &  Maine  Corporation,   Concord,   N.   H. 

H.  M.  Booth  (M  '24,  L  '60) 
Retired    Division    Engineer,   St.   Louis-San    Francisco   Railway,    Greenville,   N.    C. 

D.  C.  Bowman  (M  '28,  L  '60) 
Retired   Engineer   and   Contractor,   St.    Louis,    Mo. 

L.  B.  Cann,  Jr.  (M  '48) 
Chief   Engineer,    Richmond,    Fredericksburg   &   Potomac   Railroad,    Richmond,    Va. 

R.  P.  Davis  (M  '14,  L  '49) 
Dean   Emeritus,    College   of   Engineering,   West   Virginia   University,    Morgantown,    W.    Va. 

J.  M.  Farris    (M   '64) 
Assistant    Engineer,    Southern    Railway    System,    Atlanta,     Ga. 

T.  W.  Fatherson  (M  '10,  L  '40) 
Retired    General    Superintendent,    Treraont    &    Gulf    Railway,    Denver,    Colo. 

F.  P.  Funda  (M  '20,  L  '55) 
Retired  Division   Engineer,   Chicago,  Rock  Island  &  Pacific  Railroad,   Peoria,   111. 

C.  D.  HoRTON  (M  '27,  L  '52) 
Retired  Clearance  Engineer,  Erie  Railroad,   St.   Petersburg,   Fla. 

R.  P.  Hughes  (M  '22,  L  '57) 
Retired   Inspector,   Tie   and   Timber  Treating  Department,   Atchison,   Topeka  &  Santa   Fe   Railway, 

San  Jose,  Calif. 

A.  C.  J.ACK  (A  '27,  L  '65) 
Consultant,  Lock  Spikes,  Pittsburgh,  Pa. 


690  Bulletin  658 — American  Railway  Engineering  Association 

L.  S.  Jeffords  (M  '20,  L  '63) 
Retired    Vice    President    Operations,    Atlantic    Coast    Line    Railroad,    Jacksonville,    Fla. 

A.  S.  Krefting  (M  '35,  L  '70) 
Retired    Chief   Engineer,   Soo   Line   Railroad,    Minneapolis,   Minn. 

B.  J.  Lampert  (M  '73) 

Resident    Engineer,    Bechtel    Associates,    Iowa    City,    Iowa 

W.  B.  Leaf  (M  '39,  L  '64) 
Retired   Research   Physicist,   Denver  &   Rio   Grande  Western   Railroad,   Denver,   Colo. 

C.  W.  Meyer  (M  '58) 
Retired  Assistant  to  Valuation  Engineer,  System,  Atchison,  Topeka  &  Santa  Fe  Railway,  Topeka,  Kans. 

J.  P.  MoRRissEY,  Jr.  (M  '44,  L  '69) 
Retired   Engineer — Staff,    Erie   Lackawanna   Railway,    Bay   Village,   Ohio 

C.  W.  Murdaugh  (A  '43,  L  '74) 
Portsmouth,  Va. 

C.  W.  Murphy  (M  '56) 

Assistant  Supervisor  of  Track,  Patapsco  &  Back  Rivers  Railroad,  Sparrows  Point,  Md. 

T.  H.  Patrick  (M  '57) 
Retired  Supervisor  Tie  Bureau,   Chicago,  Milwaukee,  St.   Paul  &  Pacific  Railroad,   Modesto,   Calif. 

C.  B.  Patterson  (A  '11,  L  '46) 
Retired   Assistant   Engineer,   Ohio  State   Department   of   Highways,   Toledo,   Ohio 

R.  H.  Peterson  (M  '62) 
Railroad   Safety  Specialist,   National  Transportation  Safety  Board,  Washington,  D.   C. 

R.  B.  Shepard,  Jr.  (M  '15,  L  '50) 
Retired,    Southern    Services,    Inc.,    Birmingham,    Ala. 

R.  A.  Shier  (M  '49) 
Director   of   Engineering,    Canadian   Transport   Commission,   Ottawa,   Ont. 

C.  E.  Smith  (M  '09,  L  '45) 
Retired    Vice   President,    New    York,   New   Haven   &   Hartford   Railroad,   New   Haven,   Conn. 

M.  M.  Stansbury  (M  '47,  L  '72) 
Retired   Engineer   Roadway   Equipment,   Norfolk   &  Western   Railway,    Bellevue,    Ohio 

J.  H.  Stinebaugh  (M  '59) 
Supervisor   Water  Service   and   Roadway  Machines,   Illinois   Central   Gulf   Railroad,    Carbondale,   111. 

L.  J.  Sverdrup  (M  '39,  L  '75) 
Chairman    of   the   Board  and   Chief   Executive  Officer,   Sverdrup  &   Parcel  and  Associates,   Inc., 

St.  Louis,  Mo. 

J.  M.  Trissal  (M  '33,  L  '70) 
Retired   Vice   President — Real   Estate,   Illinois   Central   Railroad,   Flossmoor,   111. 

R.  W.  Webb  (M  '50) 
Division    Engineer,    Canadian    Pacific    Limited,    Montreal,    Que. 

D.  W.  Wessells  (A  '66) 
Streeter-Amet,  Grayslake,  111. 

J.  W.  Westwood  (M  '44,  L  '69) 
Retired   Division    Engineer,   New   York   Central   System,    Kansas   City,   Mo. 


REPORT  OF  TREASURER 


691 


Report  of  the  Treasurer 

December  31,  1975 

To  THE  Members: 

The  year  1975  was  a  good  year  financially  for  your  Association  in  that  our 
actual  receipts  very  closely  matched  our  actual  expenditures,  which  were  under  our 
budgeted  expenditures. 

Last  year  I  reported  that  our  approved  budget  for  1975  anticipated  that 
expenditures  would  exceed  receipts  by  more  than  $11,000.  This  was  due  to  replacing 
the  inventory  of  Manual  binders  and  is  to  be  recaptured  over  a  2-  to  3-year  period 
from  the  sale  of  Manuals. 

We  estimated  receipts  of  $138,350  compared  with  actual  receipts  of  $138,432. 
Total  expenditures  amounted  to  $148,246  compared  with  our  budget  of  $150,000. 
The  net  result  is  a  deficit  of  $9,814  instead  of  the  $11,000  that  was  estimated  by 
Executive  Director  Earl  Hodgkins.  Earl  and  his  able  assistants,  Nome  Engman  and 
Don  Fredley,  are  to  be  congratulated  for  keeping  such  a  tight  rein  on  expenditures. 

In  past  years  I  have  talked  about  tlie  high  esteem  our  publications  receive  in 
and  about  the  industry.  This  was  especially  evident  in  1975  when  publication  sales 
amounted   to   $56,830  as  compared  with  $30,429  in   1974. 

We  can  maintain  our  healthy  financial  situation  if  our  members  and  associates 
will  promote  use  of  the  Manual  and  Portfolio  of  Trackwork  Plans  as  well  as  use  of 
the   Bulletin   as   an   advertising  medium. 

Following  is  the  General  Balance  Sheet  for  December  31,  1975;  the  Statement 
of  Receipts  and  Expenditures  for  Calendar  Year  1975;  the  Comparative  Statement 
of  Receipts  and  Expenditures  for  the  Last  20  Years;  and  the  Comparative  Statement 
of  Association  Equity  as  of  December  31,  1974  and  1975. 

A.  B.  HiLLMAN,  Jr.,  Treasurer 


693 


694  Bulletin  658 — American  Railway  Engineering  Association 


GENERAL  BALANCE  SHEET 

DECEMBER  31,  1975 

Assets : 
Cash: 

Checking  Account   $     2,611.48 

Special  Deposit   75,324.07 

Petty    Cash    50.00 

Total  Cash   $77,985.55 

Accounts    Receivable    221.13 

Inventory  of  Publications: 

Manual  For  Railway  Engineering $  10,997.05 

Portfolio   of  Trackwork  Plans    450.00 

Bulletins    300.00 

Proceedings     100.00 

Newsletter     

Other   Publications    120.00 

Total  Inventory  of  Publications $11,967.05 

Other  Assets: 
^•Prepaid   Postage    $        833.57 

Furniture   and   Fixtures    1,000.00 

Investments     42,000.00 

Total  Other  Assets    43,833.57 

Total  Assets   $134,007.30 

Liabilities  and  Association  Equity: 

Member  Dues  Paid  in  Advance $        

Association  Equity    134,007.30 

Total  Liabilities  and  Association  Equity   ....  $134,007.30 


Prepaid  Postage: 

Second  Class  deposit — Madison    $  150.00 

Postage    Meter     613.57 

Postal  Stamps 70.00 


Total  Prepaid  Postage    $        833.57 


Report  of  Treasurer  695 


STATEMENT  OF  RECEIPTS  AND  EXPENDITURES 
CALENDAR  YEAR  1975 

Receipts 
Current  Receipts: 

Membership  Accounts: 

Member   and  Associate   Dues    $55,498.27 

Student  Affiliate  Dues    155.00 

Entrance  Fees    1,960.00 

Total  Membership  Accounts $57,613.27 

Publications : 

Manual  For   Railway  Engineering    $34,586.75 

Portfolio  of  Trackwork  Plans  11,300.10 

Bulletins    4,375.75 

Proceedings     1,894.50 

Specifications    4,673.15 

Handling    and    Shipping    4,768.41 

Total    from    Publications    $61,598.66 

Other  Sources: 

Advertising  in  Pubhcations    $  8,204.99 

Annual  Conference  Registration  Fees    6,637.06 

Interest  on  Investments    2,599.65 

Miscellaneous    1,778.03 

Total  Other  Sources   $19,219.73 

Total  Receipts   $138,431.66 

Expenditures 
Ciu^rent  Expenses: 

Salaries  and  Wages    $42,109.64 

Soc.   Security,   Ins.,   and  Unempl.   Tax    3,396.21 

Retirement  Benefit 3,152.28 

Manual  For  Railway  Engineering    26,581.39 

Portfolio  of  Trackwork  Plans    276.10 

Bulletins    and    Proceedings    43,237.22 

Newsletter     1,296.36 

Shipping  Charges    5,594.51 

Stationery  and  Printing 3,378.91 

Supplies     412.09 

Refunds  and  Miscellaneous    1,683.31 

Rent 1,045.00 

Telephone  374.25 

Committee  and  Traveling  Expenses 2,232.12 

Professors    Expenses    5,256.47 

.Annual  Conference    8,220.20 

Extraordinary    

Total    Expenditures     $148,246.06 

Excess  of  Receipts   over  Expenditures    $   (9,814.40) 


696 


Bulletin  658 — American  Railway  Engineering  Association 


COMPARATIVE  STATEMENT  OF  RECEIPTS  AND  EXPENDITURES 
FOR  THE  LAST  20  YEARS 


Receipts  Expenditures 

1956  $79,351.11  $70,336.17 

1957  85,429.31  89,830.57 

1958  81,454.56  77,348.92 

1959  80,407.16  80,297.48 

1960  81,138.79  83,978.29 

1961  83,461.73  73,410.20 

1962  76,097.28  87,344.12 

1963  73,653.48  66,156.99 

1964  74,834.81  78,118.66 

1965  81,336.73  73,895.90 

1966  84,590.91  80,454.00 

1967  78,724.17  101,087.51 

1968  97,639.94  111,054.20 

1969  109,893.16  112,741.62 

1970  113,245.85  108,305.33 

1971  113,756.51  116,003.93 

1972  128,208.01  125,534.70 

1973  110,193.20  108,148.33 

1974  112,549.90  112,153.50 

1975  138,431.66  148,246.06 


Increase 

or 

(Decrease) 

$  9,014.94 

(4,401.26) 

4,105.64 

109.68 

(2,839.50) 

10,051.53 

(11,246.84) 

7,496.49 

(3,283.85) 

7,440.83 

4,136.91 

(22,363.34) 

(13,414.26) 

(2,848.46) 

4,940.52 

(2,247.42) 

2,673.31 

2,044.87 

396.40 

(9,814.40) 


COMPARATIVE  STATEMENT  OF  ASSOCIATION  EQUITY 
AS  OF  DECEMBER  31,  1974  AND  1975 


1975 

Assets: 

Cash    $  77,985.55 

Accounts  Receivable   221.13 

Inventory  of  Publications 11,967.75 

Other   Assets    43,832.87 

Total    Assets    $134,007.30 

Liabilities  and  Association  Equity: 

Member  Dues  Paid  in  Advance   .  .  $        

Association   Equity    134,007.30 


Total  Liabilities  and  Association  Equity    .  $134,007.30 


1974 

$  84,385.33 

974.65 

13,910.00 

44,551.72 

Increase 

or 

(Decrease) 

(6,399.78) 
(753.52) 

(1,942.25) 
(718.85) 

$143,281.70 

(9,814.40) 

$       

143,821.70 

(9,814.40) 

$143,821.70 

(9,814.40) 

CONSTITUTION 


697 


American  Railway  Engineering 
Association 


CONSTITUTION 

Revised  to  February  8,  1974 


Article  I 

Name,  Object  and  Location 

1.  Name 

The  name  of  this  Association  shaU  be  the  AMERICAN  RAILWAY  ENGINEERING 
ASSOCIATION. 

2.  Object 

The  object  of  the  Association  shall  be  the  advancement  of  knowledge  pertaining 
to  the  scientific  and  economic  location,  construction,  operation  and  maintenance  of 
railways. 

3.  Means  to  be  Used 

The  means  to  be  used  for  this  purpose  shall  be: 

(a)  The  investigation  of  matters  pertaining  to  the  object  of  the  Association  through 
Study  and  Research  Committees. 

(b)  Meeting  for  the  presentation  and  discussion  of  papers,  and  for  action  on  the 
recommendations  of  committees. 

(c)  The  publication  of  papers,  reports  and  discussions. 

4.  Conclusions 

The  conclusions  adopted  by  the  Association  shall  be  recommendatory. 

5.  Location 

The  office  of  the  Association  shall  be  located  in  Chicago,  111. 

Article  II 

Membership 

1.  Classes 

The  membership  of  this  Association  shall  be  divided  into  five  classes:  Members, 
Life  Members,  Honorary  Members,  Associates  and  Junior  Members. 

2.  Qualifications 

A.  General 

(a)  An  applicant  to  be  eligible  for  membership  in  any  class  other  than  that  of 
Junior  Member  shall  be  not  less  than  25  years  of  age. 

699 


700  Bulletin  658 — American  Railway  Engineering  Association 

(b)  To  be  eligible  for  membership  in  any  class,  or  for  retention  of  membership  as  a 
Member,  an  Associate  or  a  Junior  Member,  a  person  shall  not  be  engaged  directly  or 
primarily  in  the  sale  to  the  railways  of  appliances,  supplies,  patents  or  patented  services. 

(c)  The  right  to  membership  shall  not  be  terminated  by  retirement  from  active 
service. 

(d)  In  determining  the  eligibility  for  membership  in  any  class,  graduation  in  engineer- 
ing from  a  school  of  recognized  standing  shall  be  considered  as  equivalent  to  three  years 
of  active  practice,  and  satisfactory  completion  of  each  year  of  work  in  such  school, 
without  graduation,  shall  be  considered  as  equivalent  to  one-half  year  of  active  practice. 

(e)  In  determining  the  eligibility  for  Member  under  Section  B  (a)  of  this  Article, 
each  year  of  practical  experience  in  engineering,  or  in  science  related  thereof,  prior  to 
employment  on  a  railway,  if  such  experience  were  of  the  same  specialized  character  as 
the  current  work  of  the  applicant,  shall  be  considered  as  equivalent  to  one  year  of 
railway  service. 

B.  Member 

A  Member  shall  be: 

(a)  A  railway  engineer  or  officer  who  has  had  not  less  than  five  years'  experience 
in  the  location,  construction,  operation  or  maintenance  of  railways  and  who  is  employed 
by  a  common-carrier  railway  corporation,  by  an  approved  association  of  railroads  or 
railway  engineers  or  officers,  or  by  a  non-common-carrier  railway  if  primary  duties 
consist  entirely  or  primarily  of  the  location,  construction,  operation  or  maintenance  of 
a  railway  plant  and  facilities. 

(b)  A  dean,  professor,  assistant  professor,  or  equivalent  in  engineering  in  a  university 
or  college  of  recognized  standing,  or  an  instructor  or  equivalent  in  such  university  or 
college,  who,  with  an  engineering  degree,  has  had  at  least  two  years'  experience  in 
teaching  engineering. 

(c)  An  engineer  or  member  of  a  public  board,  commission  or  other  official  agency 
who,  in  the  discharge  of  regular  duties,  deals  with  railway  problems, 

(d)  An  editor  of  a  trade  or  technical  magazine  who,  in  the  discharge  of  regular 
duties,  deals  with  railway  problems,  and  who  has  had  the  equivalent  of  five  years' 
engineering  or  railway  experience. 

(e)  A  consulting  engineer  or  contractor,  or  an  engineer  in  their  employ,  engaged  in 
the  engineering,  construction  and  maintenance  of  railroad-related  facilities  or  an  engineer 
employed  by  a  technical  service  or  research  and  development  organization  who  has  had 
the  equivalent  of  five  years'  engineering  experience. 

(f)  An  officer  or  engineer  of  an  engineering  or  scientific  society  or  association 
whose  aims  and  objectives  are  compatible  with  the  aims  and  objectives  of  this 
association. 

C.  Life  Member 

A  Life  Member  shall  be  a  Past  President  of  the  Association  who  has  been  retired 
under  a  recognized  retirement  plan,  or  a  Member  or  an  Associate  who  has  paid  dues 
for  35  years  or  who  has  been  retired  under  a  recognized  retirement  plan  and  has  paid 
dues  for  not  less  than  25  years. 

D.  Honorary  Member 

(a)  An  Honorary  Member  shall  be  a  person  of  acknowledged  eminence  in  railways 
engineering  or  management. 

(b)  The  number  of  Honorary  Members  shall  be  limited  to  ten. 


Constitution  701 


E.  Associate 

An  Associate  shall  be: 

(a)  A  member  of  a  railway  supply  company  or  association  who  meets  the  qualifica- 
tions of  Section  2,  Paragraph  A  (a)  and  (b). 

(b)  A  person  qualified  by  training  and  experience  to  cooperate  with  Members  in  the 
object  of  this  Association,  but  who  is  not  qualified  to  become  a  Member. 

F.  Junior  Member 

(a)  A  Junior  Member  shall  be  not  less  than  21  years  of  age,  shall  have  had  not 
less  than  three  years'  experience  in  the  location,  construction,  operation  or  maintenance 
of  railways,  and  shall  be  an  employee  of  a  railway  corporation,  or  one  of  the  organiza- 
tions or  institutions  listed  under  Section  B  of  this  Article,  or  a  railway  supply  company 
if  qualified  under  Section  2,  Paragraph  A  (b)   of  this  Article. 

(b)  Membership  in  this  classification  in  the  Association  shall  terminate  at  the  end 
of  the  calendar  year  in  which  individual  becomes  30  years  of  age. 

(c)  A  Junior  Member  may  make  application  for  membership  in  another  grade  at 
any  time  when  eligible  to  do  so. 

3.  Transfers 

The  Board  of  Direction  shall  transfer  from  one  class  of  membership  to  another, 
or  may  remove  from  membership,  any  person  whose  qualifications  so  change  as  to 
warrant  such  action. 

4.  Rights 

(a)  Members,  and  Life  Members  who  were  formerly  Members,  shall  have  all  the 
rights  and  privileges  of  the  Association.  Life  Members  who  were  formerly  Associates 
shall  continue  to  have  all  the  rights  and  privileges  of  Associates. 

(b)  Honorarj'  Members  shall  have  all  the  rights  and  privileges  of  the  Association 
except  those  of  holding  elective  office,  provided,  however,  that  Members  or  Life  Members 
who  are  elected  Honorary  Members  shall  retain  all  the  rights  and  privileges  of  the 
Association. 

(c)  Associates  and  Junior  Members  shall  have  all  the  rights  and  privileges  of  the 
Association  except  those  of  voting  and  holding  elective  office. 


Article  III 
Admission,  Resignation,  Expulsion  and  Reinstatement 

1.  Charter  Membership 

The  Charter  Membership  of  this  Association  consisted  of  all  persons  elected  to 
membership  before  March  IS,  1900. 

2.  Application  for  Membership 

(a)  A  person  desirous  of  membership  in  this  Association  shall  make  application 
upon  the  form  provided  by  the  Board  of  Direction.  In  the  event  that  Junior  Membership 
is  desired,  the  applicant  shall  so  state. 

(b)  The  applicant  shall  give  the  names  of  at  least  three  Members  of  this  Asso- 
ciation to  whom  personally  known.  Each  of  these  Members  shall  be  requested  to  certify 
to  a  personal  knowledge  of  the  applicant  with  an  opinion  of  the  applicant's  qualifications 
for  membership. 


702  Bulletin  658 — American  Railway  Engineering  Association 

(c)  If  an  applicant  is  not  personally  known  to  as  many  as  three  Members  of  this 
Association,  the  names  of  well-known  persons  engaged  in  railway  or  allied  professional 
work  to  whom  the  applicant  is  personally  known  shall  be  substituted,  as  necessary,  to 
provide  a  total  of  at  least  three  references.  Each  of  these  persons  shall  be  requested 
to  certify  to  a  personal  knowledge  of  the  applicant,  with  an  opinion  of  the  applicant's 
qualifications  for  membership. 

(d)  No  further  action  shall  be  taken  upon  the  application  until  replies  have  been 
received  from  at  least  three  of  the  persons  named  by  the  applicant  as  references. 

3.  Election  to  Membership 

(a)  Upon  completion  of  the  application  in  accordance  with  Section  2  of  ihis  Article 
the  Board  of  Direction  through  its  Membership  Committee  shall  consider  the  application 
and  make  such  investigation  as  it  may  consider  desirable  or  necessary. 

(b)  Upon  completion  of  such  consideration  and  investigation,  each  member  of  the 
Board  of  Direction  shall  be  supplied  with  the  required  information,  together  with  the 
recommendation  of  the  Membership  Committee  as  to  the  class  of  membership,  if  any, 
to  which  the  applicant  is  eligible,  and  the  admission  of  the  applicant  shall  be  canvassed  by 
ballot  among  the  members  of  the  Board  of  Direction. 

(c)  In  the  event  that  an  application  has  been  made  under  the  provisions  of  Section 
2,  Paragraphs  (a)  and  (b)  of  this  Article,  a  two-thirds  affirmative  vote  of  the  entire 
Board  of  Direction  shall  be  required  for  election. 

(d)  In  the  event  that  an  application  has  been  made  under  the  provision  of  Section 
2,  Paragraphs  (a)  and  (c)  of  the  Article,  a  unanimous  affirmative  vote  of  the  entire 
Board  of  Direction  shall  be  required  for  election. 

4.  Subscription  to  the  Constitution 

An  applicant  for  any  class  of  membership  in  this  Association  shall  declare  willing- 
ness to  abide  by  the  Constitution  of  the  Association  in  the  application  for  membership. 

5.  Honorary  Member 

A  proposal  for  Honorary  Membership  shall  be  endorsed  by  ten  or  more  Members 
of  the  Association  and  a  copy  furnished  each  member  of  the  Board  of  Direction.  The 
nominee  shall  be  declared  an  Honorary  Member  upon  receiving  a  unanimous  vote  of  the 
entire  Board  of  Direction. 

6.  Resignation 

The  Board  of  Direction  shall  accept  the  resignation,  tendered  in  writing,  of  any 
person  holding  membership  in  the  Association  whose  obligations  to  the  Association  have 
been  fulfilled. 

7.  Expulsion 

Charges  of  misconduct  on  the  part  of  anyone  holding  membership  in  this  Association, 
if  in  writing  and  signed  by  ten  or  more  Members,  may  be  submitted  to  the  Board  of 
Direction  for  examination  and  action.  If,  in  the  opinion  of  the  Board  action  is  war- 
ranted, the  person  complained  of  shall  be  served  with  a  copy  of  such  charges  and  shal) 
be  given  an  opportunity  to  answer  them  to  the  Board  of  Direction.  After  such  oppor- 
tunity has  been  given,  the  Board  of  Direction  shall  take  final  action.  A  two-thirds 
affirmative  vote  of  the  entire  Board  of  Direction  shall  be  reauired  for  expulsion. 


Constitution  703 


8.  Reinstatement 

(a)  A  person  having  been  a  Member,  an  Associate  or  a  Junior  Member  of  tiiis 
Association  and  having  resigned  such  membership  while  in  good  standing  may  be 
reinstated  by  a  two-thirds  affirmative  vote  of  the  entire  Board  of  Direction. 

(b)  A  person  having  been  a  Member,  an  Associate  or  a  Junior  Member  of  this 
Association  and  having  forfeited  membership  under  the  provisions  of  Article  IV,  Section 
3,  may,  upon  such  conditions  as  may  be  fixed  by  the  Board,  be  reinstated  by  a  two-thirds 
affirmative  vote  of  the  entire  Board  of  Direction. 


Article  IV 

Dues 

1.  Entrance  Fee 

(a)  An  entrance  fee  of  $10  shall  be  payable  to  the  Association  with  each  application 
for  membership  other  than  Junior  Membership.  This  sum  shall  be  returned  to  an  applicant 
not  elected. 

(b)  An  entrance  fee  of  $S  shall  be  payable  to  the  Association  with  each  appUcation 
for  Junior  Member,  which  sum  shall  be  returned  to  an  applicant  not  elected.  When  a 
Junior  Member  transfers  to  the  Member  or  Associate  Member  class  the  previously  paid 
$S  entrance  fee  shall  be  credited  towards  the  entrance  fee  for  the  class  to  which  trans- 
ferring. However,  the  Junior  Member  entrance  fee  shall  not  be  returnable  should  the 
individual  resign  from  the  Association  or  allow  membership  to  lapse.  Neither  shall 
it  be  applicable  to  the  dues  for  any  year. 

2.  Annual  Dues 

(a)  The  annual  dues  for  each  Member  and  each  Associate  shall  be  $20. 

(b)  The  annual  dues  for  each  Junior  Member  shall  be  $7.50. 

(c)  Life  Members  and  Honorary  Members  shall  be  exempt  from  the  payment  ot 
dues.  Life  Members  desiring  to  continue  to  receive  the  Bulletins  and  Proceedings  of  the 
Association  may  do  so  by  paying  a  subscription  fee  prescribed  by  the  Board  of  Direction 

3.  Arrears 

A  person  whose  dues  are  not  paid  before  April  1  of  the  current  year  shall  be  notified 
by  the  Executive  Officer-Secretary.  If  the  dues  are  still  unpaid  on  July  1,  further  notice 
shall  be  given,  informing  the  person  that  he  or  she  is  not  in  good  standing  in  the 
Association.  If  the  dues  remain  unpaid  by  October  1,  the  person  shall  be  notified  that 
he  or  she  will  no  longer  receive  the  publications  of  the  Association.  If  the  dues  are  not 
paid  by  December  31,  the  person  shall  forfeit  membership  without  further  action  or 
notice,  except  as  provided  for  in  Section  4  of  this  Article. 

4.  Remission  of  Dues 

The  Board  of  Direction  may  extend  the  time  of  payment  of  dues,  and  may  remit 
the  dues  of  any  Member,  Associate  or  Junior  Member  who,  for  good  reason,  is  unable 
to  pay  them. 

Article  V 
Officers 
1.  Officers 

(a)  The  officers  of  the  Association  shall  be  a  President,  two  Vice  Presidents, 
two  Past  Presidents,  twelve  Directors,  an  Executive  Officer-Secretary,  and  a  Treasurer. 


704  Bulletin  658 — ^American  Railway  Engineering  Association 


(b)  The  President,  the  Vice  Presidents,  the  Directors  and  the  two  Past  Presidents 
on  the  Board  of  Direction  shall  be  Members  and  shall  act  as  the  trustees  and  have  the 
custody  of  all  property  belonging  to  the  Association. 

(c)  The  Executive  Officer-Secretary  and  the  Treasurer  shall  be  appointed  by  the 
Board  of  Direction. 

2.  Term  of  Office 

The  term  of  office  of  the  President  shall  be  one  year,  of  the  Vice  Presidents  two 
years  and  of  the  Directors  three  years.  The  term  of  each  shall  begin  at  the  close  of 
the  annual  technical  conference  at  which  elected  and  continue  until  a  successor  is 
qualified.  All  other  officers  and  employees  shall  hold  office  or  position  at  the  pleasure 
of  the  Board  of  Direction. 

3.  Officers  Elected  Annually 

(a)  There  shall  be  elected  prior  to  or  at  each  annual  technical  conference  a  Presi- 
dent, one  Vice  President  and  four  Directors. 

(b)  The  candidates  for  President  and  for  Vice  President  shall  be  selected  from 
the  members  or  past  members  of  the  Board  of  Direction 

4.  Conditions  of  Re-election  of  Officers 

A  President  shall  be  ineligible  for  re-election,  except  as  provided  for  in  Section  S  (e) 
of  this  Article.  Vice  Presidents  and  Directors  shall  be  ineligible  for  re-election  to  the  same 
office,  except  as  provided  for  in  Section  5  (e)  of  this  Article,  until,  at  least  one  full 
term  has  elapsed  after  the  end  of  their  respective  terms. 

5.  Vacancies  in  Offices 

(a)  If  a  vacancy  should  occur  in  the  office  of  President,  as  set  forth  in  Section  6 
of  this  Article,  the  senior  Vice  President  shall  immediately  and  automatically  become 
President  for  the  unexpired  term. 

(b)  If  a  vacancy  should  occur  in  the  office  of  the  senior  Vice  President,  due  to 
advancement  under  Section  S  (a)  of  this  Article,  or  for  reasons  set  forth  in  Section  6 
of  this  Article,  the  junior  Vice  President  shall  automatically  become  senior  Vice  President 
for  the  unexpired  term. 

(c)  If  a  vacancy  should  occur  in  the  office  of  the  junior  Vice  President,  due  to 
advancement  under  Section  5  (b)  of  this  Article,  or  for  reasons  set  forth  in  Section  6 
of  this  Article,  the  Board  of  Direction  shall  by  the  affirmative  vote  of  two-thirds  of  its 
entire  membership,  select  a  junior  Vice  President  from  the  members  or  past  members 
of  the  Board  of  Direction 

(d)  A  vacancy  in  the  office  of  Director,  due  to  advancement  of  a  Director  to  junior 
Vice  President  under  Section  S  (c)  of  this  Article,  or  for  reasons  set  forth  in  Section  6 
of  this  Article,  shall  be  filled  by  the  Board  of  Direction  by  the  affirmative  vote  of 
two-thirds  of  its  entire  membership, 

(e)  An  incumbent  in  any  office  for  an  unexpired  term  shall  be  eligible  for  re-election 
to  the  office  held;  provided,  however,  that  anyone  selected  to  fill  a  vacancy  as  Director 
shall  be  eligible  for  election  to  that  office,  excepting  that  such  appointee  filling  out  an 
unexpired  term  of  two  years  or  more  shall  be  considered  as  coming  within  the  provisions 
of  Section  4  of  this  Article. 


Constitution  705 


6.   Vacation  of  Office 

(a)  In  the  event  of  the  death  of  an  elected  officer,  or  resignation  from  office,  or 
if  the  officer  should  cease  to  be  a  Member  of  the  Association  as  provided  in  Section  2 
(B),  Article  II;  Section  6  or  7,  Article  III;  or  Section  3,  Article  IV,  the  office  shall  be 
considered  as  vacated. 

(b)  In  the  event  of  the  disability  of  an  officer  or  neglect  in  the  performance  of  duty 
by  an  officer,  the  Board  of  Direction,  by  the  affirmative  vote  of  two-thirds  of  its  entire 
membership  shall  have  the  power  to  declare  the  office  vacant. 


Article  VI 
Nomination  and  Election  of  Officers 

1.  Nominating  Committee 

(a)  There  shall  be  a  Nominating  Committee  composed  of  the  five  latest  living  Past 
Presidents  of  the  Association,  who  are  Members,  and  five  Members  who  are  not 
officers. 

(b)  The  five  Members  who  are  not  Past  Presidents  shall  be  elected  annually  for  a 
term  of  one  year,  when  the  officers  of  the  Association  are  elected. 

(c)  The  senior  Past  President  who  is  a  member  of  the  committee  shall  be  the 
chairman  of  the  committee.  In  the  absence  of  the  senior  Past  President  from  a  meeting 
of   the  committee   the   Past   President  next   in   seniority   present   shall   act   as  chairman. 

(d)  If  one  or  more  Past  Presidents  are  unable  to  act  as  members  of  the  committee 
through  disability,  the  President  shall  have  the  authority  to  appoint  an  equivalent  num- 
ber of  eligible  next  senior  Past  Presidents  to  the  committee  as  ordinary  members. 

(e)  If  one  or  more  elected  members  of  the  committee  are  unable  to  act,  through 
death  or  disability,  the  President  shall  have  the  authority  to  appoint  as  replacements  an 
equivalent  number  of  the  senior  unsuccessful  candidates  for  election  to  the  committee. 

2.  Method  of  Nominating 

(a)  At  least  three  months  prior  to  the  annual  technical  conference,  the  Chairman 
shall  call  a  meeting  of  the  committee  at  a  convenient  place,  at  which  nominees  for  the 
several  elective  offices  shall  be  selected  as  follows: 

Number  of  Candt- 

Number  of  Candi-  dates  to  be 

dates  to  be  named  elected  at  the 

by  the  Nominating  Annual  Election 

Office  to  be  Filled                                          Committee  of  Officers 

President    1  1 

Vice    President    1  1 

Directors    8  4 

Nominating  Committee    10  S 

(b)  The  nominations  for  Director  shall  maintain  the  territorial  balance  prescribed 
in  Article  VII,  Section  1,  Paragraph  (b),  to  the  maximum  extent  practicable.  In  this 
connection,  the  nominations  for  Director  shall  be  predicated,  insofar  as  practicable,  on 
the  following  three-year  repeating  pattern  of  Director  positions  to  ensure  adequate 
territorial  distribution: 


706  Bulletin  658 — American  Railway  Engineering  Association 

First  Year  Second  Year  Third  Year 

East— 2  East— 1  East— 1 

South— 1  West— 2  South— 1 

West— 1  Canada— 1  West— 2 

Nominations  in  any  one  year  shall  be  double  the  number  of  positions  available  for 
each  district  that  year,  with  the  nominations  listed  separately  by  districts. 

(c)  The  elected  members  of  the  Nominating  Committee  each  year  shall  include 
one  from  each  district  represented  on  the  Board  of  Direction  and  one  at-large  member. 
Nominations  in  any  year  shall  be  double  the  number  of  positions  available  for  each 
district,  with  the  nominations  listed  separately  by  districts. 

(d)  The  Chairman  of  the  Nominating  Committee  shall  send  the  names  of  the 
nominees  to  the  President  and  Executive  Officer-Secretary  within  IS  days  after  the 
meeting  of  the  Nominating  Committee,  and  the  Executive  Officer-Secretary  shall  report 
the  names  of  these  nominees  to  the  members  of  the  Association  not  less  than  60  days 
prior  to  the  annual  technical  conference. 

(e)  At  any  time  prior  to  30  days  before  the  annual  meeting  of  the  Nominating  Com- 
mittee, any  ten  or  more  Members  may  send  to  the  Executive  Officer-Secretary  nomina- 
tions for  any  elective  office  for  the  ensuing  year  for  consideration  by  the  Nominating 
Committee,  signed  by  such  Members. 

(f)  If  any  person  nominated  shall  be  found  by  the  Board  of  Direction  to  be 
ineligible  for  the  office  for  which  nominated,  or  should  a  nominee  decline  such  nomina- 
tion, the  name  shall  be  withdrawn.  The  Board  of  Direction  may  fill  any  vacancies  that 
may  occur  in  the  list  of  nominees  up  to  the  time  the  ballots  are  sent  out. 

3.  Ballots  Issued 

Not  less  than  60  days  prior  to  each  annual  technical  conference,  the  Executive 
Officer-Secretary  shall  issue  a  ballot  to  each  voting  Member  of  record  who  has  paid 
dues  to  or  beyond  December  31  of  the  previous  year,  listing  by  districts  the  several 
candidates  to  be  voted  upon.  When  there  is  more  than  one  candidate  for  any  oiffice, 
the  names  shall  be  arranged  on  the  ballot  in  the  order  within  each  district  that  shall 
be  determined  by  lot  by  the  Nominating  Committee.  The  ballot  shall  be  accompanied 
by  a  statement  giving  for  each  candidate  his  or  her  record  of  membership  and  activities 
in  the  Association. 

4.  Substitution  of  Names 

Members  may  remove  names  from  the  printed  ballot  Hst  and  may  substitute  the  name 
or  names  of  any  other  person  or  persons  eligible  for  any  office,  but  the  number  of  names 
voted  for  each  office  on  the  ballot  must  not  exceed  the  number  to  be  elected  at  that 
time  to  such  office. 

5.  Ballots 

(a)  Ballots  shall  be  placed  in  an  envelope,  sealed  and  endorsed  with  the  name  of 
the  voter,  and  mailed  to  or  deposited  with  the  Executive  Officer-Secretary  at  any  time 
previous  to  the  closure  of  the  polla 

(b)  A  voter  may  have  the  privilege  of  withdrawing  his  ballot,  for  the  purposes 
of  casting  another,  or  otherwise,  at  any  time  up  to  ten  working  days  prior  to  the 
closure  of  the  polls.  After  that  date,  no  ballot  shall  be  subject  to  withdrawal  or 
revision. 

(c)  Ballots  received  in  unendorsed  envelopes,  or  from  persons  not  qualified  to  vote, 
shall  not  be  counted. 


Constitution  707 


(d)  The  ballots  and  envelopes  shall  be  preserved  for  not  less  than  ten  days  after 
the  vote  is  canvassed. 

5.  Closure  of  Polls 

The  polls  shall  be  closed  at  12  o'clock  noon  at  least  30  days,  but  not  more  than 
45  days,  prior  to  the  first  day  of  the  annual  technical  conference.  The  ballots  shall  be 
counted  soon  thereafter  by  tellers  appointed  by  the  President  of  the  Association. 

7.  Election 

(a)  The  persons  who  shall  receive  the  highest  number  of  votes  for  the  offices  for 
which  they  are  candidates  shall  be  declared  elected. 

(b)  In  case  of  a  tie  between  two  or  more  candidates  for  the  same  office,  the 
Members  present  at  the  annual  technical  conference  shall  elect  the  officer  by  ballot  from 
the  candidates  so  tied 

(c)  The  presiding  officer  shall  announce  at  the  annual  technical  conference  the 
names  of  the  officers  elected  in  accordance  with  this  Article, 


Article  VII 
Management 
1.  Board  of  Direction 

(a)  The  Board  of  Direction  shall  be  the  governing  body  of  the  Association  and 
shall  manage  the  affairs  of  the  Association  in  accordance  with  the  Constitution  of 
the  Association,  and  shall  have  full  power  to  control  and  regulate  all  matters  not  other- 
wise provided  for  in  the  Constitution.  It  shall  be  composed  of  seventeen  Members  of 
the  Association,  and  shall  include  the  President  and  two  Vice  Presidents  of  the  Asso- 
ciation, the  two  living  junior  Past  Presidents,  and  twelve  elected  Directors.  The  nomina- 
tion and  election  of  the  Officers  and  Directors  shall  be  in  accordance  with  the  procedures 
set  forth  in  Article  VI  herein. 

(b)  Furthermore,  the  membership  shall,  insofar  as  possible,  include  proportional 
representation  from  the  territorial  divisions  contained  in  the  "List  of  Principal  Railroads 
Showing  Allocation  to  Geographical  Groups"  (published  in  the  current  issue  of  The 
Official  Railway  Equipment  Register). 

Accordingly,  the  twelve  Directors  shall  be  elected  in  accordance  with  Article  VI, 
Section  2,  to  fit,  insofar  as  possible,  the  following  general  plan  for  territorial 
representation: 

Four  from  the  Eastern  District;  two  from  the  Southern  District;  five  from  the 
Western  District,  including  the  Northwestern,  Central  Western  and  Southwestern  Dis- 
tricts; and  one  from  Canada. 

(c)  The  President  and  two  Vice  Presidents  of  the  Association  and  the  two  Past 
Presidents  on  the  Board  of  Direction  shall  be  at-large  members  of  the  Board. 

(d)  Vacancies  occurring  in  Director  positions  prior  to  normal  expiration  of  term 
of  office  shall  be  filled  by  the  Board,  insofar  as  possible,  from  the  district  represented 
by  the  previous  incumbent, 

(e)  The  Board  of  Direction  shall  meet  within  thirty  days  after  each  annual  tech- 
nical conference,  and  at  such  other  times  as  the  President  may  direct.  Special  meetings 
shall  be  called  on  request,  in  writing,  of  five  members  of  the  Board  of  Direction. 

(f)  Seven  members  of  the  Board  of  Direction  shall  constitute  a  quorum. 


708  Bulletin  658 — American  Railway  Engineering  Association 

2.  Executive  Committee 

(a)  An  Executive  Committee  of  the  Board  of  Direction  shall  be  constituted 
annually  and  shall  consist  of  the  President  and  two  Vice  Presidents  of  the  Association 
and  the  two  Past  Presidents  on  the  Board  of  Direction.  The  Executive  Committee  shall 
be  subject  to  confirmation  of  the  Board  of  Direction  each  year  at  the  first  meeting  of 
the  Board  following  the  Convention.  The  President  of  the  Association  shall  be  the 
chairman  of  the  Executive  Committee. 

(b)  The  Executive  Committee  shall  possess  and  may  exercise  during  intervals 
between  meetings  of  the  Board,  all  of  the  powers  of  the  Board  on  matters  which  in  the 
judgment  of  a  majority  of  the  Executive  Committee  cannot  properly  be  delayed  until 
the  next  meeting  of  the  Board.  Actions  of  the  Executive  Committee  shall  be  authorized 
by  a  concurring  majority  of  its  full  membership  and  shall  be  reported  to  the  Board  of 
Direction  at  its  next  meeting, 

(c)  The  Executive  Committee  may  be  dissolved  at  any  time  by  action  of  a  majority 
of  the  full  membership  of  the  Board  of  Direction.  Following  such  dissolution,  the  Execu- 
tive Committee  may  be  re-created  with  personnel  different  than  prescribed  in  Paragraph 
(a)  herein  at  any  time  prior  to  the  annual  technical  conference  by  action  of  a  majority 
of  the  full  membership  of  the  Board.  However,  if  the  Executive  Committee  is  not 
re-created  prior  to  the  next  annual  technical  conference  it  automatically  shall  come 
under  the  provision  of  Paragraph  (a)  herein  unless  the  Board  of  Direction  decrees 
otherwise. 

3.  President 

The  President  shall  have  general  supervision  of  the  affairs  of  the  Association,  shall 
preside  at  meetings  of  the  Association,  the  Board  of  Direction  and  the  Executive  Com- 
mittee of  the  Board  of  Direction,  and,  by  virtue  of  his  office,  shall  be  a  member  of  all 
committees,  except  the  Nominating  Committee. 

4.  Vice  Presidents 

The  Vice  Presidents,  in  order  of  seniority,  shall  preside  at  meetings  in  the  absence 
of  the  President. 

5.  Treasurer 

The  Treasurer  shall  pay  all  bills  of  the  Association  when  properly  certified  by  the 
Executive  Officer-Secretary  and  approved  by  the  Finance  Committee.  He  shall  make 
an  annual  report  as  to  the  financial  condition  of  the  Association  and  such  other  reports 
as  may  be  called  for  by  the  Board  of  Direction. 

6.  Executive  Officer-Secretary 

The  Executive  Officer-Secretary  of  the  Association  shall  be  appointed  by  the  Board 
of  Direction  to  manage  the  affairs  of  the  Association  under  the  direction  of  the  Presi- 
dent and  the  Board  of  Direction.  This  officer  shall  use  the  title  "Executive  Director," 
or  such  other  title  as  the  Board  of  Direction  may  direct,  except  that  on  legal  papers  or 
on  other  documents,  at  his  or  her  discretion,  the  title  "Secretary"  shall  be  used.  This 
officer  shall  serve  as  secretary  of  the  Board  of  Direction  and  of  the  Executive  Committee 
of  the  Board  of  Direction. 

The  Executive  Officer-Secretary  shall  attend  the  meetings  of  the  Association,  the 
Board  of  Direction,  and  the  Executive  Committee  of  the  Board  of  Direction,  prepare 
the  business  therefor,  and  record  the  proceedings  thereof.  Furthermore,  this  officer  shall 
see  that  all  money  due  the  Association  is  collected,  is  credited  to  the  proper  accounts, 
and   is  deposited  in  the  designated  depository  of  the  Association,  with  receipt  to  the 


Constitution  709 


Treasurer  therefor.  This  officer  shall  personally  certify  to  the  accuracy  of  all  bills  and 
vouchers  on  which  money  is  to  be  paid.  In  addition,  shall  invest  all  funds  of  the  Asso- 
ciation not  needed  for  current  disbursements,  as  shall  be  recommended  by  the  Finance 
Committee  of  the  Board  of  Direction  and  approved  by  the  Board  of  Direction,  with 
notification  to  the  Treasurer  of  such  investments. 

The  Executive  Officer-Secretary  shall  be  responsible  for  the  handling  of  the  cor- 
respondence of  the  Association,  shall  make  an  annual  report  to  the  Association,  shall 
have  direct  charge  of  the  property  and  quarters  of  the  Association,  shall  direct  the  work 
of  the  secretaries,  assistant  secretaries  and  other  employees  of  the  Association,  and  shall 
perform  such  other  duties  as  the  Board  of  Direction  may  prescribe. 

7.  Auditing  of  Accounts 

The  financial  accounts  of  the  Association  shall  be  audited  annually  by  an  accountant 
or  accountants  approved  by  and  under  the  direction  of  the  Finance  Committee. 

8.  Administrative  Committees 

At  the  first  meeting  of  the  Board  of  Direction  after  the  annual  technical  conference, 
the  following  Administrative  Committees,  each  consisting  of  not  less  than  three  members, 
shall  be  appointed  by  the  President.  The  personnel  of  these  committees  shall  be  subject 
to  approval  by  the  Board  of  Direction. 

Finance 
Membership 
Publications 
Research 

Technical  Activity 
Conference  Program 

Other  special  Administrative  Committees  may  be  appointed  by  the  President  at 
any  time,  and  reappointed  annually,  if  necessary,  their  personnel  being  subject  to 
approval  by  the  Board  of  Direction 

Membership  on  Administrative  Committees  shall  be  restricted  to  members  of  the 
Board  of  Direction,  except  that  one  or  two  members  of  the  Administrative  Committee 
on  Research  may  be  past  members  of  the  Board  of  Direction. 

9.  Study  and  Research  Committees 

The  Board  of  Direction  may  establish  continuing  or  special  Study  and  Research 
Committees  to  investigate,  consider,  and  report  upon  subjects  appropriate  to  the  object 
of  the  Association,  as  set  forth  in  Art.  I. 

10.  Duties  of  Administrative  Committees 

(a)  Finance 

The  Finance  Committee  shall  have  immediate  supervision  of  the  accounts  and 
financial  affairs  of  the  Association;  shall  approve  all  bills  before  payment,  and  shall 
make  recommendations  to  the  Board  of  Direction  as  to  the  investment  of  funds  and 
other  financial  matters.  The  Finance  Committee  shall  not  have  the  power  to  incur 
debts  or  other  obligations  binding  the  Association,  nor  authorize  the  payment  of  money 
other  than  the  amounts  necessary  to  meet  ordinary  current  expenses  of  the  Association, 
except  by  authority  of  the  Board  of  Direction. 

(b)  Membership 

The  Membership  Committee  shall  investigate  applicants  for  membership  and  shall 
make  recommendations  to  the  Board  of  Direction  with  reference  thereto. 


710  Bulletin  658 — American  Railway  Engineering  Association 

(c)  Publications 

The  Publications  Committee  shall  have  general  supervision  over  the  publications 
of  the  Association,  including  the  Manual  and  the  Portfolio.  The  Publications  Commit- 
tee shall  not  have  the  power  to  incur  debts  or  other  obligations  binding  the  Associa- 
tion, nor  authorize  the  payment  of  money  except  by  authority  of  the  Board  of 
Direction, 

(d)  Research 

The  Research  Committee  shall  encourage  and  coordinate  the  research  activities  of 
the  Association,  in  the  course  of  accomplishment  of  which  it  shall  review  and  pass 
upon  the  recommendations  of  Study  and  Research  Committees  for  research  projects  and 
shall  report  thereon  to  the  Board  of  Direction,  recommending  for  approval  specific 
projects  initiated  by  these  committees  or  by  the  Research  Committee  and  recommending 
allotments  of  funds  for  these  projects  in  the  research  budget  of  the  Association  of 
American  Railroads  or  from  other  sources  compatible  therewith;  shall  collaborate  closely 
with  the  research  staff  of  the  Association  of  American  Railroads  and  other  organiza- 
tions; and  when  called  upon  by  the  Vice  President — Research  or  the  Vice  President- 
Operations  and  Maintenance  of  that  association,  members  of  the  Research  Committee 
shall  engage  in  the  activities  of  advisory  committees  or  groups  of  that  organization  and 
shall  report  from  time  to  time  to  the  Board  of  Direction  on  those  activities. 

(e)  Technical  Activity 

The  Technical  Activity  Committee  shall  monitor  and  give  direction  to  the  activities 
of  Association  Study  and  Research  Committees,  and  review  the  activity  of  the  person- 
nel assigned  thereto.  It  shall  review  and  pass  upon  the  recommendations  of  those  com- 
mittees for  subjects  to  be  investigated,  considered,  and  reported  on  by  those  commit- 
tees during  the  ensuing  Association  year,  and  shall  report  thereon  to  the  Board  of  Direc- 
tion for  its  approval.  The  Technical  Activity  Committee  shall  have  authority  to  assign 
additional  subjects  or  change  the  scope  of  any  existing  subjects  at  any  time  during  the 
year,  reporting  its  action  thereon  to  the  Board  at  its  next  regular  meeting. 

This  Committee  also  shall  review  and  pass  upon  applications  of  members  for 
appointment  to  Study  and  Research  Committees,  and  shall  appoint  the  chairman  and 
vice  chairman  of  each  such  committee  and  make  a  report  thereon  to  the  Board  of 
Direction  for  its  approval.  Should  an  unexpected  vacancy  in  the  chairmanship  or  vice 
chairmanship  of  any  such  committee  occur,  the  Technical  Activity  Committee  shall  have 
authority  to  fill  such  vacancy  immediately,  reporting  its  action  thereon  to  the  Board 
at  its  next  regular  meeting. 

(f)  Conference  Program 

The  Conference  Program  Committee  shall  develop  the  program  of  the  annual  tech- 
nical conference  with  the  assistance  of  the  Study  and  Research  Committees,  the  Board 
of  Direction,  the  Executive  Officer-Secretary,  and  others. 

11.  Special  Committees 

The  Board  of  Direction  may  appoint  special  committees  to  examine  into  and  report 
upon  any  subject  connected  with  the  objects  of  this  Association. 

12.  Discussion  by  Non-Members 

The  Board  of  Direction  may  invite  discussions  of  reports  from  persons  not  members 
of  the  Association. 

13.  Sanction  of  Act  of  Board  of  Direction 

An  act  of  the  Board  of  Direction  which  shall  have  received  the  expressed  or  implied 


Constitution  711 


sanction  of  the  membership  at  the  next  annual  technical  conference  of  the  Association 
shall  be  deemed  to  be  the  act  of  the  Association, 

ArUcIe  VIII 
Meetings 

1.  Annual  Technical  Conference 

(a)  The  Annual  Technical  Conference  of  the  Association  shall  be  held  in  the  City 
of  Chicago,  111.,  or  in  such  other  city  as  may  be  determined  by  the  affirmative  vote 
of  two-thirds  of  the  entire  membership  of  the  Board  of  Direction.  The  technical  con- 
ference in  any  year  shall  be  held  on  dates  determined  by  the  affirmative  vote  of  two- 
thirds  of  the  entire  membership  of  the  Board  of  Direction. 

(b)  The  Executive  Officer-Secretary  shall  notify  all  members  of  the  Association 
of  the  time  and  place  of  the  annual  technical  conference  at  least  30  days  in  advance 
thereof. 

(c)  The  order  of  business  at  the  annual  technical  conference  of  the  Association 
shall     be: 

.■\ddress  of  the  President 

Reports  of  the  Executive  Officer-Secretary  and  the  Treasurer 

Committee  and  other  presentations 

Unfinished  business 

N'ew  business 

Installation  of  officers 

.Adjournment 

(d)  This  order  of  business  may  be  changed  by  the  presiding  officer. 

(e)  The  proceedings  shall  be  governed  by  "Robert's  Rules  of  Order"  except  as 
otherwise  herein  pro\ided. 

(f)  Discussions  shall  be  limited  to  Members  and  to  those  others  invited  by  the 
presiding  officer  to  speak. 

2.  Special  Meetings 

Special  meetings  of  the  Associations  may  be  called  by  the  Board  of  Directions  on  its 
own  initiative,  and  may  be  so  called  by  the  Board  of  Direction  upon  written  request 
of  100  Members.  The  request  shall  state  the  purpose  of  such  meeting. 

The  call  for  such  special  meeting  shall  be  issued  not  less  than  ten  days  in  advance 
of  the  propyosed  date  of  such  meeting  and  shall  state  the  purpose  and  place  of  the 
meeting.  No  other  business  shall  be  taken  up  at  such  meeting. 

3.  Quorum 

Twenty-five  Members  shall  constitute  a  quorum  at  all  meetings  of  the  .Association 

Article  IX 
Amendment 
1.   Amendment 

Amendment  of  this  Constitution  may  be  proposed  by  written  petition  signed  by 
not  less  than  ten  Members  of  the  Association,  and  shall  be  acted  upon  in  the  following 
manner: 

The  proposed  amendment  shall  be  presented  to  the  Executive  Officer-Secretary  who 


712  Bulletin  658 — American  Railway  Engineering  Association 

shall  send  a  copy  to  each  member  of  the  Board  of  Direction  as  soon  as  received.  If  a 
majority  of  the  entire  Board  of  Direction  so  votes,  the  matter  shall  be  submitted  to 
the  voting  members  of  the  Association  by  letter  ballot. 

Amendment  to  the  Constitution  also  may  be  proposed  by  majority  affirmative  vote 
of  the  entire  Board  of  Direction,  and  the  proposed  amendment  then  submitted  to  the 
voting  members  of  the  Association  by  letter  ballot. 

Sixty  days  after  the  date  of  issue  of  the  letter  ballot,  the  Board  of  Direction  shall 
canvass  the  ballots  which  have  been  received,  and  if  two-thirds  of  such  ballots  are  in 
the  affirmative  the  amendment  shall  be  declared  adopted  and  shall  become  effective 
immediately.  The  result  of  the  letter  ballot  shall  be  announced  to  members  of  the 
Association. 


Index  to  Proceedings,  Vol.  77,    1976 


—  A  — 

Annual  Technical  Conference,  president's  ad- 
dress,   487 

— program,   479 

Architectural  Competition,  descriiition  of  b\ 
D.    A.    Bessey,    493 

• — participating   universities,    343 

— rules    for,    345 

Association  of  American  Railroads  (see  Engi- 
neering   Division,    AAR) 


—  B  — 

Bailey,  R.  W.,  address,  "C&NW's  Ballast  Un- 
dercutter-Cleaner,"    665 

Ballast,  cost  of  cleaning  versus  replacement  in 
track  rehabilitation,  312 

— research   program,   364 

— undercutter-cleaner   on   C&X^^',    665 

Bessey,  D.  A.,  address,  "Description  of  Archi- 
tectural Competition  Sponsored  by  AREA 
Committee    6 — Buildings,"    493 

Brawner,  C.  O.,  address,  "Rock  Slope  Stability 
on  Railway  Projects,"  presented  at  Van- 
couver  Regional   Meeting,   449 

Bridges,  steel  railway,  specifications  for.  Man- 
ual recommendations,  249 

Bridges,    timber,    concrete   components    for,    355 

— -iuethods  of  fireproofing,  352 

British  Railways,  track  maintenance  for  high- 
speed trains,  address  by  H.  H.  Jenkins, 
499 

Buildings,    committee    report,    341 

— Architectural    Design    Competition,    342 

— elevated  yardmasters'  towers.  Manual  recom- 
mendations,  172 

Burlington  Northern,  Inc.,  noise  abatement  at 
Northtown  Yard,  address  by  M.  B.  ^^'alker, 
555 


—  c  — 

Canadian  National  Railways,  bridges  on  Moun- 
tain  Region,   425 

— double  tracking   on,   304 

■ — -Eraser  River  Bridge,  investigation  of,  561, 
577 

Canadian  Pacific  Rail,  innovations  in  frog  and 
switch  design,  address  by  E.  H.  Taylor, 
652 

— frog  and  switch  manufacturing  shop,   301 

Cars,   freight,   disposal   of  waste   from,   325 

Chessie  System,  service  test  of  standard  carbon 
steel  rail  and  various  wear  resistant  rails, 
55 

Chicago  &  North  Western  Transportation  Com- 
pany,   ballast    undercutter-cleaner,    665 

Cias,  W.  W.,  address,  "High-Strength  Chro- 
mium-Molybdenum  Rails,"   621 

Clearances,   committee   rei^ort,   337 

— new  methods  and  equipment  for  recording, 
339 

College    students,    summer    enip!o>ment   of,    402 

Concrete    components    for    timber    trestles,    355 

Concrete  Structures  and  Foundations,  commit- 
tee report,   353 

Concrete  ties   (see  Ties,  concrete) 


Continuous  welded  rail,  statistics  on  track  miles 

laid,   376 
Crossings,  highway-railway  grade^jconcrete  slab, 

performance  of  on  EJ&E,  257 
— motor    vehicle    codes    and    drivers'    licensmg 

Ijractices   relating  to,    263 
— public    i^edestrian,    266 
— rumble   strips    for   approaches   to,    264 
— safety    at,    summary    reporting    of    significant 

developments,   258 


—  D  — 

Data  bases,  address  on  by  C.  F.  Wiza 
Data    processing,    application    in    allocating    re- 
corded costs  to  reported  units  in  the  track 
accounts,   274 
D.ivis,   R.   P.,   memoir,  361 


—  E  — 

Economics  of  Plant,  Equipment  and  Operations, 
committee  report,   383 

Economics  of  Railway  Construction  and  Main- 
tenance, committee  report,  299 

Eldis,  G.  T.,  address,  "High-Strength  Chro- 
mium-Molybdenum Rails,"  621 

Election  of  officers,   nominating  committee,  482 

— successful  candidates,  483 

— tellers  committee,  482 

Electrical  Energy  Utilization,  committee  report, 
403 

Electrification,  method  of  making  economic 
studies.   Manual   reconunendations,    181 

Electrification,  railroad,  status  report  on,  by 
H.   C.   Kendall,  404 

Elgin,  Joliet  &  Eastern  Railway,  performance  of 
concrete  slab  crossings,  257 

Engineering  Division,  AAR,  annual  meeting 
session,    673 

— remarks  bv  D.   C.   Hastings,    677 

—remarks  by  J.  T.  Ward,  675 

Engineering    Education,    committee    report,    401 

Engineering  Records  and  Property  Accounting, 
committee  report,   273 

— bibliography  on,   274 

Engler,   J.    L.,   memoir,   324 

Environmental  Engineering,  committee  report, 
323 

Executive  director,  report  of,  683 


—  F  — 

Eraser  River  Bridge,   investigation  of,   561,  577 

Freight,  delivery  and  transfer.  Manual  recom- 
mendations,  111 

Freight   terminals    (see  Terminals,   freight) 

Freight  yards    (see  Yards,  freight) 

Friesen,  W.,  address,  "Hot  Box  Detector  Ana- 
Kzer   System,"    521 

Frogs,  design  innovations,  address  by  E.  H. 
Taylor,^  652 

— riilbound  manganese  steel,  explosive  harden- 
ing of  on  Canadian   Pacific,   302 


713 


714 


Index 


—  H  — 

Hastings,   D.    C,    address,    "A   Time   for   Chal- 
lenge,"  677 
Highways,  committee  report,  255 
Hilhnan,  Jr.,  A.  B.,  report  of  treasurer,  693 
Hodgkins,  E.   W.,  executive  director,  report  of, 
683 

Hot    box    detector,    data    analyzer    system    for, 

address  by  W.   Friesen  521 
Housing,    portable,    sanitation    requirements    for. 

Manual   recommendations,    189 


Installation   of   oflBcers,    669 

Interstate  Commerce  Commission,  Bureau  of 
Accounts,  activities  in  valuation  and  de- 
preciation, 276 

— accounting  classifications,  revisions  and  in- 
terpretations of,  277 


Jenkins,    H.    H.,    address,    "Track    Maintenance 

for  High-Speed  Trains,"  499 
Joint    bars,    bonded,    economics   of   versus   field 

welds  to  connect  CWR,  320 
— bonded,   insulated,   economics  of  installing  in 

field  versus  shop   fabrication,   318 
Joplin,   A.    F.,   luncheon   address    at   Vancouver 

Regional  Meeting,  415 


—  K  — 

Kalousek,  J.,  address,  "Investigation  into  Causes 
of  Rail  Corrugations,"  presented  at  Van- 
couver Regional   Meeting,  429 

— address,  "Rail  Wear  and  Corrugation  Stud- 
ies,"  601 

Kendall,  H.  C,  status  report  on  railroad  elec- 
trification, 404 

Kerr,  Arnold  D.,  report,  "Principles  and  Cri- 
teria for  the  Design  of  a  Railroad  Track 
Test  Facility,"  1 

King,  F.  E.,  address,  'TRail  Wear  and  Corru- 
gation Studies,"  601 

Klein,  R.,  address,  "Investigation  into  Causes 
of  Rail  Corrugations,"  presented  at  Van- 
couver Regional  Meeting,  429 


—  L  — 

Locomotive   facilities.   Manual   recommendations, 
133 


—  M  — 

Maintenance  of  Way  Work  Equipment,  com- 
mittee report,  9,  333 

Morris,  L.  R.,  address,  "Railway  Bridges  on 
Canadian  National's  Mountain  Region," 
presented  at  Vancouver  Regional  Meeting, 
425 


—  N  — 

Nominating  committee   (see  Election  of  officers) 


o 


Officers,   election  of    (see   also   Election  of  offi- 
cers) 
—installation  of,   669 


—  P  — 

Passenger    facilities.    Manual    recommendations, 

141 
Piers,    protection    of    at     spans    on    navigable 

streams,  357 
Pipe,   plastic,   types   and   applications,   327 
Plastic  pipe   (see  Pipe,  plastic) 


—  R  — 

Rail,  committee  report,   373 

— continuous  welded  (See  Continuous  welded 
raU) 

■ — corrugations,  causes  of,  429 

— high-strength  chromium-molybdenum,  621 

■ — ^research  and  development,  376 

■ — -standard  carbon  steel,  summary  of  perform- 
ance of  in  test  curves  on  Chessie  System, 
55 

■ — tonnages  shipped  by  weight  and  section  in 
1974,   382 

— wear  and  corrugation  studies,  address  on  by 
F.  E.  King  and  J.  Kalousek,  601 

— wear  resistant,  summary  of  performance  of 
in  test  curves  on  Chessie  System,   55 

Reclamation,    Manual    recommendations,    161 

Regional  Meeting,  Vancouver 

— address,  "Investigation  into  Causes  of  Rail 
Corrugations,"  by  J.  Kalousek,  R.  Klein, 
429 

— address,  "Railway  Bridges  on  Canadian  Na- 
tional's Mountain  Region,"  by  L.  R.  Mor- 
ris,  425 

— address,  "Railway  Signalling,"  by  H.  W. 
Trawick,  419 

— address,  "Rock  Slope  Stability  on  Railway 
Projects,"  by  C.  O.  Brawner  and  Duncan 
Wyllie,  449 

— ^luncheon   address  by  A.   F.   Joplin,   415 

Roadway  and  Ballast,  committee  report,  363 

Rock    slope    stability    on    railway   projects,    449 


—  s  — 

Sawhill,  Jr.,  J.  M.,  address,  "High-Strength 
Chromium-Molybdenum   Rails,"    621 

Scales,   belt   conveyor,   proposed   rules  for,   288 

Scales,  Special  Committee  on,  committee  re- 
port, 25,  287 

Scales,  track,  location  of  for  coupled-in-motion 
weighing,   295 

- — statistical  data  for  coupled-in-motion  weigh- 
ing  and   testing,    25 

Signalling,  railway,  address  presented  by  H.  W. 
Trawick  at  Vancouver  Regional  Meeting, 
419 

Smith,  Y.  E.,  address,  "High-Strength  Chro- 
mium-Molybdenimi   Rails,"   621 

Steel   Structures,   committee   report,   359 

Stores,    Manual    recommendations,    160 

Sweeney,  R.  A.  P.,  address,  "The  Load  Spec- 
trum for  the  Fraser  River  Bridge  at  New 
Westminster,  B.   C,"   561 

Switches,  design  innovations,  address  by  E.  H. 
Taylor,  652 


Index 


715 


__T  — 

Taylor,    E.    H.,    address,    "Innovations    in    Frog 

and  Switch  Design,"  652 
Tellers  committee    (see  Election  of  officers) 
Terminals,     freight,     Manual     recommendations, 

95 
— specialized,    Manual  reconmiendations,    117 
Ties,    concrete,    specifications    for.    Manual    rec- 
ommendations,  193 
Ties  and  Wood  Preservation,  committee  rei^ort, 

13,  367 
Ties,  wood  cross 
— annual   renewal    statistics,    13 
- — extent  of  adherence  to  specifications  for,  368 
— foreign  species,  suitability  of,  369 
Timber  Structures,  committee  report,  351 
Track    maintenance,    for    high-speed   trains,    ad- 
dress on  by  H.  H.  Jenkins,  499 
Track  Scales    (see  Scales,  track) 
Track  test  facility,  design  of,  report  by  Arnold 

D.  Kerr,  1 
Trains,   high-speed,   track   maintenance   for,    ad- 
dress by  H.  H.  Jenkins,  499 
Transportation,    improving    quality    of,    384 
Trawick,  H.  W.,  address,   "Railway  Signalling," 
presented  at   Vancouver  Regional  Meeting, 
419 
Treasurer,  report  of,  693 

—  u  — 

University   students    (see   College    students) 

—  V  — 

Vegetation    control,    Manual    recommendations, 
238 


—  w  — 

Walker,  M.  B.,  address,  "The  Quiet  One— ^ 
Burlington  Northern's  Northtown  Yard," 
555 

Ward,   J.   T.,   president's   address,   487 

— remarks  at  Engineering  Division,  AAR,  an- 
nual meeting  session,   675 

Waste  disposal,  325 

Waterproofing,   for  railway  structures,   355 

Wiza,  C.  F.,  address,  "Data  Bases:  Help  or 
Harassment  for  Engineering  Management," 
597 

Wood  preservatives,  evaluation  of  "3APR6," 
368 

Work  equipment,  maintenance  of  way,  repair 
organizations,  9 

— repair  shops,  design  criteria.  Manual  recom- 
mendations,   162 

Wright,  C.  R.,  memoir,  300 

Wyllie,  Duncan,  address,  "Rock  Slope  Stability 
on  Railway  Projects,"  presented  at  Van- 
couver Regional  Meeting,  449 


—  Y  — 

Yards,  design  criteria  to  decrease  car  detention, 

283 
— flat   and   saucer,   gradients   for,    280 
— freight.    Manual   recommendations,   95 
— noise    abatement    at   on   Burlington   Northern, 

address  by  M.   B.   Walker,   555 
Yards   and  Terminals,   committee   report,   279 
■ — Manual  recommendations,    87 


DIRECTORY 

CONSULTING    ENGINEERS 


FRANK   R.  WOOLFORD 

Enginaering    Consultant — Railroads 

24   Josepha   Ave. 

San   Francisco,  Ca.  94132 

(415)  587-1569 

246   Seadrift   Rd. 

Stinson  6«ach,  Ca.  94970 

(415)  868-1555 


V¥ 


Westenhoff  &  Novick,  Inc. 
Consulting  Engineers 
Civil — Mechanical — Electrical 

Fixod  &   Movable  Brldgas 

Soils,  Foundations,  Buildings 

Structural   &  Undarwatar   Investigation! 

Planning,      Faasibility,      Design,      Inspectloii 

222   W.    Adams    St.,    Chicago,    III.    60606 
New    Yori<  Washington  Panama 


HAZELET  &  ERDAL 

Consulting   Engineers 

Design         Investigations         Reports 
Fixed    and    Movable    Bridges 

150  So.  Wacker  Dr.,  Chicago,  III.  60606 
Leuiiville        Cincinnati        Washington 


HMTB 


Feasibility  studies  and  design  services  for 

Bus  and  rail  transit  Terminals 

Regional  and  urban  planning  Parlcing 

Soils  and  foundations  Tunnels 

Structures  Utilities 
Environmental  Impact  studies 

Offices  in  28  cities  816  474-4900 

1805  Grand  Avenue,  Kansas  City,  Missouri  64108 


MODJESKI  AND  MASTERS 

Conra/ffng  Ewglw— w 

Datign,   Inspection   of   Gsnstnictioo  &  In- 
spection   of    Physical    Condition    of   Fixed 
&   Movable   Railroad   Bridges 

P.O.   Bex  234S,  Harrisburg,  Pa.   17105 
10S5  St.  Charies  Ave.,  New  Orleans,  Lo. 


CLARK,  DIETZ  AND 

ASSOCIATES-ENGINEERS,  INC. 

CofituMng  Engin^mn 

Bridget    Structures,  Foundations,  Indet- 
trial  Wastes  and  Railroad  Relocation 

211    No.  Race  St.,  Uifaana,  III. 

Sanford,  Flo.  Meaphis,  Tean. 

Jackten,  Miss.  St.   Lovis,  Me. 

Chicago,  III. 


716-1 


716-2 


Directory  of  Consulting  Engineers 


<§^ 


Engineers 
Designers     Planners 


PARSONS 
BRINCKERHOFF 

QUADE 
DOUGLAS,    Inc. 


Route  Location,  Shop 
Facilities,  Container/ 
Bulk  Cargo,  Handling 
Utilities,  Bridges,  Tun- 
nels, Evaluations,  Ap- 
praisals,     Supervision 


ONE  PENN  PLAZA,  NEW  YORK,  NY  10001 

Boston        .        Denver        .        Honolulu 
San   Froncisco         •        Trenton 


HARDESTY  &   HANOVER 

Contufflng  Englifn 

TRANSPORTATION 
ENGINEERING 

Highways       •       Railways 

Bridges — Fixed    and    Movable 

Design       •       Resident   Inspection 

Studies       •       Appraisals 

101    Park  Ave.,   New  York,  N.  Y.   10017 


THOAAAS  K.  DYER,  INC. 
Consu/fing  Engine9rs 

Railroads — Transit  Systems 
Track,  Signals,  Structures 

InvMligatlons  and  Feasibility  R«|>ortt 
Planning,  Design,  Contract  Documents 

1762  MostfKhuselts  Avonwe 
Lexington,  Mou.  02173 


npflllieDeteuvnCailiefOrjanizaiion 

l*UU  CONSULTING  ENGINEERS 

165  W.  WACKERVDRIVE  •  CHICAGO  60601 


SUBWAYS  •  RAILROADS  •  PUBLIC  TRANSIT 

TRAFFIC  •  PARKING  •  HIGHWAYS 
BRIDGES  •  PORT  DEVELOPMENT  •  AIRPORTS 
COMMUNITY  PLANNING  •  URBAN  RENEWAL 
MUNICIPAL  WORKS  •  INDUSTRIAL  BUILDINGS 
ENVIRONMENTAL  SCIENCE  AND  ENGINEERING 


IEC0 

RAILROAD 
DESIGN  &  ELECTRIFICATION 

Planning     •     Design 
Construction  Management 


INTERNATIONAL  ENGINEERING 
COMPANY,  INC. 

220  MONTGOMERY  STREET 
SAN  FRANCISCO,  CALIFORNIA  94104 


RILEY,  PARK,  HAYDEN  & 

ASSOCIATES,  INC. 

Consulting    Bngln—rs 

Survey  Services,  Photogrammetry,  Gon- 
•rol  Civil,  Bridges,  Railroads  &  Indus- 
trial  Park   Design. 

136  Marietta  St.,  N.  W. 
Atlanta,   Georgia  30303 

(404)   577-5600 


i 


Directory  of  Consulting  Engineers 


716-3 


SVERDRUP  &  PARCEL  AND  ASSOCIATES,  INC. 

800  No.  Twelfth  Blvd.  •  St.  Louis,  Mo.  63101 

Boston  •  Charleston  •  Gainesville  •  Jacksonville 
Nastiville  •  New  York  •  Phoenix  •  San  Francisco 
Seattle      •      Silver  Spring      •      Washington,  D.C. 


•  design 

•  planning 

•  construction 
management 


CONSULTING  ENGINEERS 


I 


lUr  PORTER  AND  RIPA 
ASSOCIATES,  INC. 


Consulting   Engineers — Planners 

Design  Inspections      •      Reports 

Planning       •       Structures 

Environmental  Studies 

200   Madison   Avenue,    Morristown,  New  Jersey  07$(0 


SPAULDING  ENGINEERING  CO. 

CONSULTING  ENGINEERS 

MEMBER 

AMERICAN  CONSULTING  ENGINEERS  COUNOL 

1821    UNIVERSITY  AVENUE 

ST.   PAUL,   MINNESOTA  55104 

PHONE   612/644-5676 


SOROS  ASSOCIATES 

Consulting   Engineers 

Transfer  Terminolt  &  Ports  For  Dry  ftwlks. 

Liquids  &  Contoinors — Wotorfront  Strvctur«« 

Materials   Hondling   Systsmt 

575    Lexington   Ave. 

New   York,   N.   Y.    10022 

(212)    421-0400 

Rio  d*  Janeiro  Santiago,  Chil* 

Sydney,  Australia 


HOWARD  J.  BELLOWS 

ESTIMATING  CONSULTANT 
FOR  TRACKWORK 

Ratlnadt    &    Rapid   Transit   Systtmt 

725   DALRYMPLE   ROAD 

Apt.   8-E 

ATLANTA,  GA.   30328 

404-393-0390 


WHITMAN,  REQUARDT 
&  ASSOCIATES 

Engineers  Consultants 

Complete  Engineering  Services 

BALTIMORE,  MARYLAND 


716-1 


Directory  of  Consulting  Engineers 


TURNER  ENGINEERING 
COMPANY 

(SAWYER-PIEPMEIER) 

RAILROAD  ENGINEERING 

306  GAY  ST. 
NASHVILLE,    TENNESSEE    37201 

615-244-2144 
ALBANY,    NY      518-456-1994 


Railroads    •    Rapid  Transit 

Electric  Traction    Power 

Signals  and  Train   Control 

Communications    •    Substations 

Operations   Analysis   and   Simulation 

Power  Generation    •    Urban    Planning 

Gibbs  a  Hili  Inc. 

ENGINEERS,  DESIGNERS.  CONSTRUCTORS 

393  Seventh  Avenue,   Now  York,   N.Y.   10001 

A  Subsidiary  of  Dravo  Corporation 


CENTEC  CENTRAL  TECHNOLOGY,  INC 

Railroad  Consultants 

OPERATION  ENGINEERING 

RESEARCH  ROUTE  LOCATION 

MANAGEMENT     CONSTRUCTION 


Dulles    international    Airport 
P.O.    Box   17411 
Wasliington,   D.C.   20041 


(703)  471-7070 
Cable:  CENTEC 
Telex:   89-9493 


WOLCHUK  and  MAYRBAURL 
CONSULTING  ENGINEERS 

RAILWAY  AND  HIGHWAY  BRIDGES 

SPECIAL  STRUCTURES 

DESIGN— INVESTIGATIONS— REPORTS 

432  PARK  AVE.  S.,  NEW  YORK,  NY  10016 
(212)   689-0220 


w 


RALPH  WHITEHEAD&  ASSOOATES 

ConsJtiig  Engneers  •  Qiariotte  Adanta 


P.O.  Box  4301 

CharloHe,   N.C.  28204 

Telephone  704-372-1885 

BRIDGES   •    HIGHWAYS    •    RAILROADS 

•   RAIL  &  BUS  TRANSIT  • 

AIRPORTS   •   BUILDINGS 


BAKKE  KOPP   BALLOU&McFARLIN.INC. 
CONSULTING  ENGINEERS 


Bridges 
Special  &  Heavy  Structures 
Investigations  &  Reports 


7505  WEST  HIGHWAY  SEVEN 

ST.  LOUIS  PARK,  MINNESOTA  55426 

(612)933-8880 


^ 


TRASCO  Track  Skates 


Preferred  by  skatemen 

Light 

Tough 

Balanced  hand  hold 

No  curl  tongue 

TRACK  SPECIALTIES 
COMPANY 

Box  729  Westport ,  Conn .