Full text of "Report"
Astro
TL
795. 5
. U53
2003
COLUMBIA
ACCIDENT INVESTIGATION REPORT
VOLUME 1
+
SUPPLEMENTAL
MATERIALS
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Report Volume I
August 2003
COLUMBIA
ACCIDENT iNVESTIGATIQN BOARD
On the Title Page
Tills was the crew pafcb for STS-107. The central element
of the patch was the microgravity symbol, (jg, flowing info
the rays of the Astronaut symbol. The orbital inclination was
portrayed by the 39-degree angle of the Earth's horizon to
the Astronaut symbol. The sunrise was representative of the
numerous science experiments that were the dawn of a new
ero for confinued microgrovify research on ffie /nfernofiona/
Space Station and beyond. The breadth of science conduct-
ed on this mission had widespread benefits to life on Earth
and the continued exploration of space, illustrated by the
Earth and stars. The constellation Columba (the dove) was
chosen to symbolize peace on Earth and the Space Shuttle
Columbia. In addition, the seven sfors represenf ffie STS-107
crew members, as well as honoring the original Mercury 7
astronauts who paved the way to make research in space
possible. The Israeli flag represented the First person from
that country to fly on the Space Shuttle.
On the Back Cover
This emblem memorializes the three U.S. human space flight
accidents - Apollo 1, Challenger, and Columbia. The words
across the top translate to: "To The Stars, Despite Adversity
- Always Explore"
This is a reproduction of the first printing of the Columbia Accident
Report as it appeared August 2003. subsequent errors corrected by
the CAIB have been included up to September 12th 2003.
Additional material in this book and on the accompanying CDROM
were selected by the editor Some minor aesthetic changes were
made to accomodate the new layout
httpJ/wwwapogeebooks.com
Editor: Robert Godwin
ISBN: I -894959-06-X
We acknowledge the financial support of the Government of
Canada through the Book Publishing Industry Development
Program for our publishing activities. Published by Collector's Guide
Publishing Inc., Box 62034, Burlington, Ontario, Canada, L7R 4K2 —
Printed and bound in Canada
Report VoLut
August 2003
This cause of exploration and discovery is not an option we clioose; it is a desire written in the human heart ...
We find the best amoni> us. send them forth into unmapped darkness, and pray they will return.
They ^o in peace for all mankind, and all mankind is in their debt.
- President George W. Bush. February 4. 2003
, pfiofograplied from Columbia on Jonuory 26, 2003, during (he STS-107 r
COLUMBIA
ACCIDENT INVESTIGATIDN BDAR[
Volume I
Part One
Chapter 1
1.1
1.2
1.3
1.4
1.5
1.6
Chapter 2
2.1
2.2
2.3
2.4
2.5
2.6
2.7,
Chapter 3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
Chapter 4
,4.1
'4.2
Part Two
Chapter 5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
Chapter 6
6.1
6.2
6.3
6.4
Chapter 7
7.1
7.2
7.3
In Memoriam 3
Board Statement 6
Executive Summary 9
Report Synopsis 11
The Accident
The Evolution of the Space Shuttle Program
Genesis of the Space Transportation System 21
Merging Conflicting interests 22
Shuttle Development, Testing, and Qualification 23
The Shuttle Becomes "Operational" 23
The C/;<(//t'/;.(,'t"/- Accident 24
Concluding Thoughts 25
Columbia's Final Flight
Mission Objectives and Their Rationales 27
Flight Preparation 31
Launch Sequence 32
On-Orbit Events 35
Debris Strike Analysis and Requests for Innagery 37
De-Orbit Burn and Re-Entry Events 38
Events Immediately Following the Accident 39
Accident Analysis
The Physical Cause 49
The External Tank and Foam 50
Wing Leading Edge Structural Subsystem 55
Image and Transport Analyses 59
On-Orbit Debris Separation - The "Flight Day 2" Object 62
De-Orbit/Re-Entry 64
Debris Analysis 73
Impact Analysis and Testing 78
Other Factors Considered
Fault Iree 85
Remaining Factors 86
Why the Accident Occurred
From Challenger to Columbia
The Cluillenger Accident and its Aftermath 99
The NASA Human Space Flight Culture 101
An Agency Trying to Do Too Much With Too Little 102
Turbulence in NASA Hits the Space Shuttle Program 105
When to Replace the Space Shuttle? 1 10
A Change in NASA Leadership 1 15
The Return of Schedule Pressure 1 16
Conclusion 1 17
Decision Making at NASA
A History of Foam Anomalies 121
Schedule Pressure 131
Decision-Making During the Flight of STS-107 140
Possibility of Rescue or Repair 173
The Accident's Organizational Causes
Organizational Cau.ses: Insights from History 178
Organizational Causes: Insights from Theory 180
Organizational Causes; Evaluating Best Safety Practices 182
Report VoLur
COLUMBIA
ACCIDENT INVESTIGATION BOARD
7.4 Organizational Causes: A Broken Safety Culture 184
7.5 Organizational Causes: Impact of a Flawed Safety Culture on STS- 107 189
7.6 Findings and Recommendations 192
Chapter 8 History as Cause: Columbia and Challenger
8. 1 Echoes of Challenger 195
8.2 Failures of Foresight: Two Decision Histories and the Normalization of Deviance 196
8.3 System Effects: The Impact of History and Politics on Risky Work 197
8.4 Organization. Culture, and Unintended Consequences 199
8.5 History as Cause: Two Accidents 199
8.6 Changing NASA's Organizational System 202
Part Three A Look Ahead
Chapter 9 Implications for the Future of Human Space Flight
9.1 Near-Term: Return to Flight 208
9.2 Mid-Term: Continuing to Fly 208
9.3 Long-Term: Future Directions for the U.S. in Space 209
Chapter 10 Other Significant Observations
10. 1 Public Safety 213
10.2 Crew Escape and Survival 214
10.3 Shuttle Engineering Drawings and Closeout Photographs 217
10.4 Industrial Safety and Quality Assurance 217
10.5 Maintenance Documentation 220
10.6 Orbiter Maintenance Down Period/Orbiter Major Modification 220
10.7 Orbiter Corrosion 221
10.8 Brittle Fracture of A-286 Bolts 222
10.9 Hold-Down Post Cable Anomaly 222
10. 10 Solid Rocket Booster External Tank Attachment Ring 223
10.1 1 Test Equipment Upgrades 223
10. 1 2 Leadership/Managerial Training 223
Chapter 11 Recommendations 225
Part Four Appendices
Appendix A The Investigation 231
Appendix B Board Member Biographies 239
Appendix C Board Staff 243
Supplemental Material - NASA Press Conference on the Space Shuttle Columbia Sean O'Keefe.Administrator 249
Report Volume I August ZOOS
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Board Statement
For all those who are inspired by flight, and for the nation
where powered flight was first achieved, the year 2003 had
long been anticipated as one of celebration - December 1 7
would mark the centennial of the day the Wright Flyer first
took to the air. But 2003 began instead on a note of sudden
and profound loss. On February 1, Space Shuttle Coliimhici
was destroyed in a disaster that claimed the lives of all seven
of its crew.
While February 1 was an occasion for mourning, the efforts
that ensued can be a source of national pride. NASA publicly
and forthrightly informed the nation about the accident and
all the associated information that became available. The Co-
lumbia Accident Investigation Board was established within
two hours of the loss of signal from the returning spacecraft
in accordance with procedures established by NASA follow-
ing the Challenger accident 17 years earlier.
The crew members lost that morning were explorers in the
finest traditiow, and since then, everyone associated with the
Board has felt that we were laboring in their legacy. Ours, too,
was a journey of discovery: We sought to discover the con-
ditions that produced this tragic outcome and to share those
lessons in such a way that this nation's space program will
emerge stronger and more sure-footed. If those lessons are
truly learned, then Columbia's crew will have made an indel-
ible contribution to the endeavor each one valued so greatly.
After nearly seven months of investigation, the Board has
been able to arrive at findings and recommendations aimed
at significantly reducing the chances of further accidents.
Our aim has been to improve Shuttle safety by multiple
means, not just by correcting the specific faults that cost
the nation this Orbiter and this crew. With that intent, the
Board conducted not only an investigation of what happened
to ColiiDihia, but also - to determine the conditions that al-
lowed the accident to occur - a safety evaluation of the en-
tire Space Shuttle Program. Most of the Board's efforts were
undertaken in a completely open manner. By necessity, the
safety evaluation was conducted partially out of the public
view, since it included frank, off-the-record statements by
a substantial number of people connected with the Shuttle
program.
In order to understand the findings and recommendations in
this report, it is important to appreciate the way the Board
looked at this accident. It is our view that complex systems
almost always fail in complex ways, and we believe it would
be wrong to reduce the complexities and weaknesses asso-
ciated with these systems to some simple explanation. Too
often, accident investigations blame a failure only on the
last step in a complex process, when a more comprehensive
understanding of that process could reveal that earlier steps
might be equally or even more culpable. In this Board's
opinion, unless the technical, organizational, and cultural
recommendations made in this report are implemented, little
will have been accomplished to lessen the chance that an-
other accident will follow.
From its inception, the Board has considered itself an inde-
pendent and public institution, accountable to the American
public, the White House. Congress, the astronaut corps and
their families, and N.ASA. With the support of these con.stitu-
ents, the Board resolved to broaden the scope of the accident
investigation into a far-reaching examination of NASA's
operation of the Shuttle fleet. We have explored the impact
of NASA's organizational history and practices on Shuttle
safety, as well as the roles of public expectations and national
policy-making.
In this process, the Board identified a number of pertinent
factors, which we have grouped into three distinct categories:
i) physical failures that led directly to Columbia'?, destruc-
tion; 2) underlying weaknesses, revealed in NASA's orga-
nization and history, that can pave the way to catastrophic
failure; and 3) "other significant observations" made during
the course i)f the investigation, but which may be unrelated
to the accident at hand. I^eft uncorrected, any of these factors
could contribute to future Shuttle losses.
To establish the credibility of its findings and recommenda-
tions, the Board grounded its examinations in rigorous sci-
entific and engineering principles. We have consulted with
leading authorities not only in mechanical systems, but also
in organizational theory and practice. These authorities' areas
of expertise included risk management, safety engineering,
and a review of "best business practices" employed by other
high-risk, but apparently reliable enterprises. Among these
are nuclear power plants, petrochemical facilities, nuclear
weapons production, nuclear submarine operations, and ex-
pendable space launch systems.
NASA is a federal agency like no other. Its mission is
unique, and its stunning technological accomplishments, a
source of pride and inspiration without equal, represent the
best in American skill and courage. At times NASA's efforts
have riveted the nation, and it is never far from public view
and close scrutiny from many quarters. The loss oi Columbia
and her crew represents a turning point, calling for a renewed
public policy debate and commitment regarding human
space exploration. One of our goals has been to set forth the
terms for this debate.
Named for a sloop that was the first American vessel to
circumnavigate the Earth more than 200 years ago, in 1981
Columbia became the first spacecraft of its type to fly in Earth
orbit and successfully completed 27 missions over more than
two decades. During the STS-107 mission, Columbia and its
crew traveled more than six million miles in 16 days.
The Orbiter's destruction, just 16 minutes before .scheduled
touchdown, shows that space flight is still far from routine.
It involves a substantial element of risk, which must be
recognized, but never accepted with resignation. The seven
Columbia astronauts believed that the risk was worth the
reward. The Board salutes their courage and dedicates this
report to their memor>'.
Report Volume I
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BDARD
A^.^.
'Harold W. Gehman, Jr.
Admiral. U.S. Ncivy (retired)
Chairman
AJ-
d.lB
John L. Barr\
Major General, U.S. Air Force
0 James N. Hallock. Ph.D.
Manager. Aviation Safety Division. DOTIRSPA Volpe Center
G. Scott Hubbard
Director. NASA Ames Research Center
Douglas D. OsheroffTPh.D.
Professor. Stanford University
>0 Roger E. Tetrault
Chairman and CEO, McDerinott International (retired)
Steven B. Wallace
Director. FAA Office of Accident Investigation
Duane W. Deal
Brigadier General. U.S. Air Force
Kenneth W. Hess
Major General, U.S. Air Force
John M. LogsdoiyPh.D.
Professor. George Washington University
de, Ph.D.
alifornia at San Diego
^.^.iuJ^
Stephen A. Turcotte
Rear Admiral, U.S. Navy
'U^
Sheila E, Widnall. Ph.D
Professor. Massachusetts Institute of Technology
Report volume I A u t3 u s t 20D3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Executive Summary
The Columbia Accident Investigation Board's independent
investigation into the February 1 , 2003, loss of the Space
Shuttle Colimihia and its seven-member crew lasted nearly
seven months. A staff of more than 1 20, along with some 400
NASA engineers, supported the Board's 13 members. Inves-
tigators examined more than 30,000 documents, conducted
more than 200 fomial interviews, heard testimony from
dozens of expert witnesses, and reviewed more than 3,000
inputs from the general public. In addition, more than 25.000
searchers combed vast stretches of the Western United States
to retrieve the spacecraft's debris. In the process, Colnnihia's
tragedy was compounded when two debris searchers w ith the
U.S. Forest Service perished in a helicopter accident.
The Board recognized early on that the accident was prob-
ably not an anomalous, random event, but rather likely root-
ed to some degree in NASA's history and the human space
flight program's culture. Accordingly, the Board broadened
its mandate at the outset to include an investigation of a wide
range of historical and organizational issues, including polit-
ical and budgetary considerations, compromises, and chang-
ing priorities over the life of the Space Shuttle Program. The
Board's conviction regarding the importance of these factors
strengthened as the investigation progressed, with the result
that this report, in its findings, conclusions, and recommen-
dations, places as much weight on these causal factors as on
the more easily understood and corrected physical cause of
the accident.
The physical cause of the loss of Coliimhia and its crew was
a breach in the Thermal Protection System on the leading
edge of the left wing, caused by a piece of insulating foam
which separated from the left bipod ramp section of the
External Tank at 81.7 seconds after launch, and struck the
wing in the vicinity of the lower half of Reinforced Carbon-
Carbon panel number 8. During re-entry this breach in the
Thermal Protection System allowed superheated air to pen-
etrate through the leading edge insulation and progressively
melt the aluminum structure of the left wing, resulting in
a weakening of the structure until increasing aerodynamic
forces caused loss of control, failure of the wing, and break-
up of the Orbiter This breakup occuired in a flight regime in
which, given the current design of the Orbiter, there was no
possibility for the crew to survive.
The organizational causes of this accident are rooted in the
Space Shuttle Program's history and culture, including the
original compromises that were required to gain approval for
the Shuttle, subsequent years of resource constraints, fluc-
tuating priorities, schedule pressures, mischaracterization of
the Shuttle as operational rather than developmental, and lack
of an agreed national vision for human space flight. Cultural
traits and organizational practices detrimental to safety were
allowed to develop, including: reliance on past success as a
substitute for sound engineering practices (such as testing to
understand why systems were not performing in accordance
with requirements); organizational barriers that prevented
effective communication of critical safety information and
stifled professional differences of opinion; lack of integrated
management across program elements; and the evolution of
an informal chain of command and decision-making pro-
cesses that operated outside the organization's rules.
This report discusses the attributes of an organization that
could more safely and reliably operate the inherently risky
Space Shuttle, but does not provide a detailed organizational
prescription. Among those attributes are: a robust and in-
dependent program technical authority that has complete
control over specifications and requirements, and waivers
to them; an independent safety assurance organization with
line authority over all levels of safety oversight; and an or-
ganizational culture that reflects the best characteristics of a
learning organization.
This report concludes with recommendations, some of
which are specifically identified and prefaced as "before
return to flight." These recommendations are largely related
to the physical cause of the accident, and include prevent-
ing the loss of foam, improved imaging of the Space Shuttle
stack from liftoff through separation of the External Tank,
and on-orbit inspection and repair of the Thermal Protec-
tion System. The remaining recommendations, for the most
part, stem from the Board's findings on organizational
cause factors. While they are not "before return to flight"
recommendations, they can be viewed as "continuing to fly"
recommendations, as they capture the Board's thinking on
what changes are necessary to operate the Shuttle and future
spacecraft safely in the mid- to long-term.
These recommendations reflect both the Board's strong sup-
port for return to flight at the earliest date consistent with the
oveiriding objective of safety, and the Board's conviction
that operation of the Space Shuttle, and all human space-
flight, is a developmental activity with high inherent risks.
A view from inside f/ie Launch Control Center as Columbia rolls ouf
fo Launch Complex 39-A on December 9, 2002.
Report Vouuf
Columbia sits on Launch Complex 39-A prior to STS107.
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Report Synopsis
The Columbia Accident Investigation Board's independent
investigation into the tragic February 1 , 2003. loss of" the
Space Shuttle Coltinihia and its seven-member crew lasted
nearly seven months and involved 13 Board members,
approximately 120 Board investigators, and thousands
of NASA and support personnel. Because the events that
initiated the accident were not apparent for some time,
the investigation's depth and breadth were unprecedented
in NASA history. Further, the Board determined early in
the investigation that it intended to put this accident into
context. We considered it unlikely that the accident was a
random event; rather, it was likely related in some degree
to NASA's budgets, histoi^y. and program culture, as well
as to the politics, compromises, and changing priorities of
the democratic process. We are convinced that the manage-
ment practices overseeing the Space Shuttle Program were
as much a cause of the accident as the foam that struck the
left wing. The Board was also influenced by discussions
with members of Congress, who suggested that this nation
needed a broad examination of NASA's Human Space Flight
Program, rather than just an investigation into what physical
fault caused Coliinihia to break up during re-entry.
Findings and recommendations are in the relevant chapters
and ail recommendations are compiled in Chapter I 1.
Volume I is organized into four parts: The Accident: Why
the Accident Occurred: A Look Ahead; and various appendi-
ces. To put this accident in context. Parts One and Twci begin
with histories, after which the accident is described and then
analyzed, leading to findings and recommendations. Part
Three contains the Board's views on what is needed to im-
prove the safety of our voyage into space. Part Four is refer-
ence material. In addition to this first volume, there will be
subsequent volumes that contain technical reports generated
by the Columbia Accident Investigation Board and NASA,
as well as volumes containing reference documentation and
other related material.
Part One: The Accident
Chapter I relates the history of the Space Shuttle Program
before the Cluilleiii;i'r accident. With the end looming for
the Apollo moon exploration program, NASA unsuccess-
fully attempted to get approval for an equally ambitious
(and expensive) space exploration program. Most of the
proposed programs started with space stations in low-Earth
orbit and included a reliable, economical, medium-lift
vehicle to travel safely to and from low-Earth orbit. After
many failed attempts, and finally agreeing to what would
be untenable compromises, NASA gained approval from the
Nixon Administration to develop, on a hxed budget, only
the transport vehicle. Because the Administration did not ap-
prove a low-Earth-orbit station, NASA had to create a mis-
sion for the vehicle. To satisfy the Administration's require-
ment that the system be economically justifiable, the vehicle
had to capture essentially all space launch business, and to
do that, it had to meet wide-ranging requirements. These
sometimes-competing requirements resulted in a compro-
mise vehicle that was less than optimal for manned flights.
NASA designed and developed a remarkably capable and
resilient vehicle, consisting of an Orbiter with three Main
Engines, two Solid Rocket Boosters, and an External Tank,
but one that has never met any of its original requirements
for reliability, cost, ease of turnaround, maintainability, or,
regrettably, safety.
Chapter 2 documents the final flight of Coliinihia. As a
straightforward record of the event, it contains no findings or
recommendations. Designated STS-107, this was the Space
Shuttle Program's 113th flight and Coliiiiihia's. 28th. The
flight was close to trouble-free. Unfortunately, there were no
indications to either the crew onboard Coliinihia or to engi-
neers in Mission Control that the mission was in trouble as
a result of a foam strike during ascent. Mission management
failed to detect weak signals that the Orbiter was in trouble
and take corrective actitin.
Coliinihia was the first space-rated Orbiter It made the Space
Shuttle Program's first four orbital test flights. Because it was
the first of its kind, Coliinihia differed slightly from Orbiters
Clialleiificr. Dixcoven\ Atlantis, and Endeavour. Built to an
earlier engineering standard, Coliinihia was slightly heavier,
and, although it could reach the high-inclination orbit of the
International Space Station, its payload was insufficient to
make Coliinihia cost-effective for Space Station missions.
Therefore. Coliinihia was not equipped with a Space Station
docking system, which freed up space in the payload bay for
longer cargos, such as the science modules Spacelab and
SPACEHAB. Consequently, Coliinihia generally flew sci-
ence missions and serviced the Hubble Space Telescope.
STS-107 was an intense science mission that required the
seven-member crew to form two teams, enabling round-
the-clock shifts. Because the extensive science cargo and
its extra power sources required additional checkout time,
the launch sequence and countdown were about 24 hours
longer than normal. Nevertheless, the countdown proceeded
as planned, and Coliinihia was launched from Launch Com-
plex 39-Aon January 16, 2003, at 10:39 a.m. Eastern Stan-
dard Time (EST).
At 81.7 seconds after launch, when the Shuttle was at about
65,820 feet and traveling at Mach 2.46 ( 1 ,6.50 mph), a large
piece of hand-crafted insulating foam came off an area
where the Orbiter attaches to the External Tank. At 81.9
seconds, it struck the leading edge of Colnnihia's left wing.
This event was not detected by the crew on board or seen
by ground support teams until the next day, during detailed
reviews of all launch camera photography and videos. This
foam strike had no apparent effect on the daily conduct of
the 16-day mission, which met all its objectives.
The de-orbit burn to slow Coliinihia down for re-entry
into Earth's atmosphere was nomial, and the flight profile
throughout re-entry was standard. Time dining re-entry is
Report Volui
IT 2 O O 3
COLUMBIA
ACCIDENT INVESTIGATIDN BDARD
measured in seconds from "Entry Interface," an arbitrarily
determined altitude of 400,000 feet where the Orbiter be-
gins to experience the effects of Earth's atmosphere. Entry
Interface for STS-107 occurred at 8:44:09 a.m. on February
i. Unknown to the crew or ground personnel, because the
data is recorded and stored in the Orbiter instead of being
transmitted to Mission Control at Johnson Space Center, the
first abnormal indication occurred 270 seconds after Entry
Interface. Chapter 2 reconstructs in detail the events lead-
ing to the loss of Coliii7ihia and her crew, and refers to more
details in the appendices.
In Chapter 3, the Board analyzes all the information avail-
able to conclude that the direct, physical action that initiated
the chain of events leading to the loss of Coliinihia and her
crew was the foam strike during ascent. This chapter re-
views five analytical paths - aerodynamic, thermodynamic,
sensor data timeline, debris reconstruction, and imaging
evidence - to show that all five independently arrive at the
same conclusion. The subsequent impact testing conducted
by the Board is also discussed.
That conclusion is that Coliinihia re-entered Earth's atmo-
sphere with a* pre-existing breach in the leading edge of its
left wing in the vicinity of Reinforced Carbon-Carbon (RCC)
panel 8. This breach, caused by the foam strike on ascent,
was of sufficient size to allow superheated air (probably ex-
ceeding 5,000 degrees Fahrenheit) to penetrate the cavity be-
hind the RCC panel. The breach widened, destroying the in-
sulation protecting the wing's leading edge support structure,
and the superheated air eventually melted the thin aluminum
wing spar. Once in the interior, the superheated air began to
destroy the left wing. This destructive process was carefully
reconstructed from the recordings of hundreds of sen.sors in-
side the wing, and from analyses of the reactions of the flight
control systems to the changes in aerodynamic forces.
By the time Coliinihia passed over the coast of California
in the pre-dawn hours of February I, at Entry Interface plus
555 seconds, amateur videos show that pieces of the Orbiter
were shedding. The Orbiter was captured on videotape dur-
ing most of its quick transit over the Western United States.
The Board correlated the events seen in these videos to
sensor readings recorded during re-entry. Analysis indi-
cates that the Orbiter continued to fly its pre-planned flight
profile, although, still unknown to anyone on the ground or
aboard Coliinihia, her control systems were working furi-
ously to maintain that flight profile. Finally, over Texas, just
southwest of Dallas-Fort Worth, the increasing aerodynamic
forces the Orbiter experienced in the denser levels of the at-
mosphere overcame the catastrophically damaged left wing,
causing the Orbiter to fall out of control at speeds in excess
of 10,000 mph.
The chapter details the recovery of about 38 percent of the
Orbiter (some 84,000 pieces) and the reconstruction and
analysis of this debris. It presents findings and recommenda-
tions to make future Space Shuttle operations safer.
Chapter 4 describes the investigation into other possible
physical factors that may have contributed to the accident.
The chapter opens with the methodology of the fault tree
analysis, which is an engineering tool for identifying every
conceivable fault, then detennining whether that fault could
have caused the system in question to fail. In all, more than
3,000 individual elements in the Coliinihia accident fault
tree were examined.
In addition, the Board analyzed the more plausible fault sce-
narios, including the impact of space weather, collisions with
micrometeoroids or "space junk," willful damage, flight crew
performance, and failure of some critical Shuttle hardware.
The Board concludes in Chapter 4 that despite certain fault
tree exceptions left "open" because they cannot be conclu-
sively disproved, none of these factors caused or contributed
to the accident. This chapter also contains findings and rec-
ommendations to make Space Shuttle operations safer.
Part Two: Why the Accident Occurred
Part Two, "Why the Accident Occurred," examines NASA's
organizational, historical, and cultural factors, as well as
how these factors contributed to the accident.
As in Part One, Part Two begins with history. Chapter 5
examines the posl-Challeni^er history of NASA and its
Human Space Flight Program. A summary of the relevant
portit)ns of the Challeiii>er investigation recommendations
is pre.sented. followed by a review of N./KSA budgets to indi-
cate how committed the nation is to supporting human space
flight, and within the NASA budget we look at how the
Space Shuttle Program has fared. Next, organizational and
management history, such as shifting management systems
and locations, are reviewed.
Chapter 6 documents management performance related to
Coliinihia to establish events analyzed in later chapters. The
chapter begins with a review of the history of foam strikes on
theOrbitertodeterminehow Space Shuttle Program managers
rationalized the danger from repeated strikes on the Or-
biter's Thermal Protection System. Next is an explanation
of the intense pressure the program was under to stay on
schedule, driven largely by the self-imposed requirement to
complete the International Space Station. Chapter 6 then re-
lates in detail the effort by some NASA engineers to obtain
additional imagery of Coliinihia to determine if the foam
strike had damaged the Orbiter. and how management dealt
with that effort.
In Chapter 7, the Board presents its view that NASA's or-
ganizational culture had as much to do with this accident
as foam did. By examining safety history, organizational
theory, best business practices, and current safety failures,
the report notes that only significant structural changes to
NASA's organizational culture will enable it to succeed.
This chapter measures the Shuttle Program's practices
against this organizational context and finds them wanting.
The Board concludes that NASA's current organization
does not provide effective checks and balances, does not
have an independant safety program, and has not dem-
onstrated the characteristics of a learning organization.
Chapter 7 provides recommendations tor adjustments in
orsanizational culture.
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Chapter 8, the final chapter in Part Two, draws from the
previous chapters on history, budgets, culture, organization,
and safety practices, and analyzes how all these factors con-
tributed to this accident. The chapter opens with "echoes of
Challeiific'r" that compares the two accidents. This chapter
captures the Board's views of the need to adjust manage-
ment to enhance safety margins in Shuttle operations, and
reaffirms the Board's position that without these changes,
we have no confidence that other "corrective actions" will
improve the safety of Shuttle operations. The changes we
recommend will be difficult to accomplish - and will be
internally resisted.
Part Three: A Look Ahead
Part Three summarizes the Board's conclusions on what
needs to be done to resume our journey into space, lists
significant observations the Board made that are unrelated
to the accident but should be recorded, and provides a sum-
mary of the Board's recommendations.
In Chapter 9, the Board first reviews its short-term recom-
mendations. These return-to-flight recommendations are the
minimum that must be done to essentially li\ the problems
that were identified by this accident. Next, the report dis-
cusses what needs to be done to operate the Shuttle in the
mid-term, 3 to 15 years. Based on NASA's history of ignor-
ing external recommendations, or making improvements
that atrophy with time, the Board has no confidence that the
Space Shuttle can be safely operated for more than a few
years based solely on renewed post-accident vigilance.
Chapter 9 then outlines the management system changes the
Board feels are necessary to safely operate the Shuttle in the
mid-term. These changes separate the management of sched-
uling and budgets from technical specification authority,
build a capability of systems integration, and establish and
provide the resources for an independent safety and mission
assurance organization that has supervisory authority. The
third part of the chapter discusses the poor record this na-
tion has, in the Board's view, of developing either a comple-
ment to or a replacement for the Space Shuttle. The report is
critical of several bodies in the U.S. government that share
responsibility for this situation, and expresses an opinion on
how to proceed from here, but does not suggest what the next
vehicle should look like.
Chapter 10 contains findings, observations, and recom-
mendations that the Board developed over the course of this
extensive investigation that are not directly related to the
accident but should prove helpful to NASA.
Chapter 1 1 is a compilation of all the recommendations in
the previous chapters.
Part Four: Appendices
Part Four of the report by the Columbia Accident Inves-
tigation Board contains material relevant to this volume
organized in appendices. Additional, stand-alone volumes
will contain more reference, background, and analysis ma-
terials.
This Earfh view of the Sinai Peninsula, Red Sea, Egypt, Nile River,
and the Mediterranean was taken from Columbia during STS107.
Report voli
IQUST 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
An Introduction to the Space Shuhle
The Space Shuttle is one of the most complex machines ever
devised. Its main elements - the Orbiter. Space Shuttle Main
Engines, External Tank, and Solid Rocket Boosters - are assembled
from more than 2.5 million parts, 230 miles of wire, 1,060 valves,
and 1,440 circuit breakers. Weighing approximately 4.5 million-
pounds at launch, the Space Shuttle accelerates to an orbital
velocity of 17,500 miles per hour - 25 times faster than the speed
of sound - in just over eight minutes. Once on orbit, the Orbiter
must protect its crew from the vacuum of space while enabling
astronauts to conduct scientific research, deploy and service
satellites, and assemble the Inlernational Space Station. At the end
of its mission, the Shuttle uses the Earth's atmosphere as a brake lo
decelerate from orbital velocity to a safe landing at 220 miles per
hour, dissipating in the process all the energy it gained on its way
into orbit.
The Orbiter
The Orbiter is what is popularly refen-ed to as "the Space Shuttle."
About the size of a small commercial airliner, the Orbiter nonnally
carries a crew of seven, including a Commander, Pilot, and five
Mission or Payload Specialists. The Orbiter can accommodate a
payload the size of a school bus weighing between .38,000 and
56,300 pounds depending on what orbit it is launched into, fhc
Orbiter's upper flight deck is filled with equipment for flying and
maneuvering the vehicle and controlling its remote manipulator
arm. The mid-deck contains stowage lockers for food, equipment,
supplies, and experiments, as well as a toilet, a hatch for entering
and exiting the vehicle on the ground, and - in some instances - an
airlock for doing so in orbit. During liftoff and landing, four crew
members sit on the flight deck and the rest on the mid-deck.
n
^
4? r^.
►s
B^^
IjyKi
^1
^,„p:^*L:^
mnnm
Different pails of the Orbiter are subjected to dramatically different
temperatures during re-entry. The nose and leading edges of the
wings are exposed to superheated air temperatures of 2,800 to 3,000
degrees Fahrenheit, depending upon re-entry profile. Other portions
of the wing and fuselage can reach 2,300 degrees Fahrenheit. Still
other areas on top of the fuselage are sufficiently shielded from
superheated air that ice sometimes survives through landing.
To protect its thin aluminum structure during re-entry, the Orbiter
is covered with various materials collectively referred to as the
Thermal Protection System. The three major components of the
system are various types of heat-resistant tiles, blankets, and the
Reinforced Carbon-Carbon (RCC) panels on the leading edge of
the wing and nose cap. The RCC panels most closely resemble a
hi-tech fiberglass - layers of special graphite cloth that are molded
to the desired shape at ver> high temperatures. The tiles, which
protect most other areas of the Orbiter exposed to medium and
high heating, are 90 percent air and 10 percent silica (similar to
common sand). One-tenth the weight of ablative heat shields,
which are designed to erode during re-entry and therefore can only
be used once, the Shuttle's tiles are reusable. They come in varying
strengths and sizes, depending on which area of the Orbiter they
protect, and are designed to withstand either 1 ,200 or 2.300 degrees
Fahrenheit. In a dramatic demonstration of how little heat the tiles
transfer, one can place a blowtorch on one side of a tile and a bare
hand on the other. The blankets, capable of withstanding either
700 or 1,200 degrees Fahrenheit, cover regions of the Orbiter that
experience only moderate heating.
Space Shuhle Main Engines
Each Orbiter has three main engines mounted at the aft fuselage.
These engines use the most efficient propellants in the world
- oxygen and liydrogen - at a rate of half a ton per second. At 100
percent power, each engine produces 375,000 pounds of thrust,
four times that of the largest engine on commercial jets. The large
bell-shaped nozzle on each engine can swivel 10.5 degrees up and
down and 8.5 degrees left and right to provide steering control
during ascent.
External Tank
The three main engines burn propellant at a rate that would drain
an average-size swimming pool in 20 seconds. The External
Tank accommodates up to 143,351 gallons of liquid oxygen and
385.265 gallons of liquid hydrogen. In order to keep the super-cold
propellants from boiling and to prevent ice from forming on the
outside of the tank while it is sitting on the launch pad. the External
Tank is covered with a one-inch-thick coating of insulating foam.
This insulation is so effective that the surface of the External Tank
feels only slightly cool to the touch, even though the liquid oxygen
is stored at minus 297 degrees Fahrenheit and liquid hydrogen
at minus 423 degrees Fahrenheit, fhis insulating foam also
protects the tank's aluminum structure from aerodynamic heating
during ascent. Although generally considered the least complex
of the Shuttle's main components, in fact the External Tank is a
remarkable engineering achievement. In addition to holding over
1.5 million pounds of cryogenic propellants, the 153.8-foot long
tank must support the weight of the Orbiter while on the launch pad
and absorb the 7.3 million pounds of thrust generated by the Solid
Rocket Boosters and Space Shuttle Main Engines during launch and
ascent. The External Tanks are manufactured in a plant near New
Report Volume I
iT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Orleans and are transported by barge to the Kennedy Space Center
in Florida. Unlike the Solid Rocket Boosters, w hich are reused, the
External Tank is discarded during each mission, burning up in the
Earth's atmosphere alter being jettisoned from the Orbiter.
Solid Rocket Boosters
Despite their power, the Space Shuttle Main Engines alone are not
sufficient to boost the vehicle to orbit - in lact. they provide only 1 5
percent of the necessary thrust. Two Solid Rocket Boosters attached
to the External Tank generate the remaining S.'S percent. Together,
these two 149-foot long motors produce over six million pounds of
thrust. The largest solid propellant rockets ever flown, these motors
use an aluminum powder fuel and ammonium perchlorate oxidizer
in a binder that has the feel and consistency of a pencil eraser.
m
A Solid Rocket Booster (SRB) Demonstration Motor being tested
near Brigham City, Utah.
Eiach of the Solid Rocket Boosters consists of 1 1 separate segments
joined together. The joints between the segments were extensively
redesigned after the Cludlenf>er accident, w hich occurred when hot
ga.ses burned through an O-ring and .seal in the aft joint on the left
Solid Rocket Booster. The motor segments are shipped from their
manufacturer in Utah and assembled at the Kennedy Space Center.
Once assembled, each Solid Rocket Booster is connected to the
External Tank by bolts weighing 65 pounds each. After the Solid
Rocket Boosters burn for just over two minutes, these bolts are
separated by pyrotechnic charges and small rockets then push the
Solid Rocket Biwsters safely away from the rest of the vehicle. As
the boosters fall back to liarlh, parachutes in their nosecones deploy.
After splashing down into the ocean 1 20 miles downrange from the
launch pad. they arc recovered for refurbishment and reuse.
The Shuhle Stack
The lirsl step in assembling a Space Shuttle for launch is stacking
the Solid Rocket Booster segments on the Mobile Launch
Platform. Eight large hold-down bolts at the base of the Solid
Rocket Boosters will bear the weight of the entire Space Shuttle
stack while it awaits launch. The External Tank is attached to
the Solid Rocket Boosters, and the Orbiter is then attached to the
External Tank at three points - two at its bottom and a "bipod"
attachment near the nose. When the vehicle is ready to move out of
the Vehicle Assembly Building, a Crawler-Transporter picks up the
entire Mobile Launch Platform and carries it - at one mile per hour
- to one of the two launch pads.
REPORT VOUUME I
iT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
An Introduction to NASA
■'An Act to provide for research into the problems of flight within
and outside the Etirlh's atmosphere, and for other purposes." With
this simple preamble, the Congress and the President of the United
States created the National Aeronautics and Space Administration
(NASA) on October 1, 1958. Formed in response to the launch of
Sputnik by the Soviet Union, N.ASA inherited the research-oriented
National Advisory' Committee for Aeronautics (NACA) and several
other government organizations, and almost immediately began
working on options for manned space flight. NASA's first high
profile program was Project Merctny. an early effort to learn if hu-
mans could survive in space. Project Gemini followed with a more
complex series of experiments to increase man's time in space and
validate advanced concepts such as rendezvous. The efforts con-
tinued with Project Apollo, culminating in 1969 when Apollo II
landed the first humans on the Moon. The return from orbit on July
24, 1975, of the crew from the Apollo-Soyuz Test Project began
a six-year hiatus of American manned space flight. The launch of
the first Space Shuttle in April 1981 brought Americans back into
space, continuing today w ith the assembly and initial operations of
the international Space Station.
In addition to the human space flight program, NASA also main-
tains an active (if small) aeronautics research program, a space
science progrsfm (including deep space and interplanetary explora-
tion), and an Earth observation program. The agency also conducts
basic research activities in a variety of fields.
NASA, like many federal agencies, is a heavily matrixed organiza-
tion, meaning that the lines of authority are not necessarily straight-
forward. At the simplest level, there are three major types of entities
involved in the Human Space Flight Program: NASA field centers,
NASA programs carried out at those centers, and industrial and
academic contractors. The centers provide the buildings, facilities,
and support services for the various programs. The programs, along
with field centers and Headquarters, hire civil servants and contrac-
tors from the private sector to support aspects of their enterprises.
Canoga Park, CA
BHSF&E - Rochetdyne
Space StnilUe Meln Engines
Brigham City, UT
ATK - Thiokol Propulsion
Reusable SoM Rocket
Huntsvllle, AL
Marshall Space Flight Center
Space Shuttle Projects Office
(RSRM. ET. SSME)
Ames Research Center'
Moffett Field, CA
TPS Devotopmoni
Langley Research Center
Hampton.VA
Wind Tunnei Testing
The Locations
NASA Headc|uarters, located in Washington U.C, is responsit
leadership and management across five strategic enterprises: Aero-
space Technology, Biological and Physical Research. Earth Science,
Space Science, and Human Exploration and Development of Space.
NASA Headquarters also provides strategic management for the
Space Shuttle and International Space Station programs.
The Johnson Space Center in Houston, Texas, was established in
1961 as the Manned Spacecraft Center and has led the development
of every U.S. manned space flight program. Currently, Johnson is
home to both the Space Shuttle and International Space Station Pro-
gram Offices. The facilities at Johnson include the training, simula-
tion, and mission control centers for the Space Shuttle and Space
Station. Johnson also has flight operations at Ellington Field, where
the training aircraft for the astronauts and support aircraft for the
Space Shuttle Program are stationed, and manages the White Sands
Test Facility, New Mexico, where hazardous testing is conducted.
The Kennedy Space Center was created to launch the Apollo mis-
sions to the Moon, and currently provides launch and landing facili-
ties for the Space Shuttle. The Center is located on Merritt Island.
Florida, adjacent to the Cape Canaveral Air Force Station that also
provides support for the Space Shuttle Program (and was the site
of the earlier Mercury and Gemini launches). Personnel at Ken-
nedy support maintenance and overhaul services for the Orbiters,
assemble and check-out the integrated vehicle prior to launch, and
operate the Space Station Processing Facility where components of
the orbiting laboratory are packaged for launch aboard the Space
Shuttle. The majority of contractor personnel assigned to Kennedy
are part of the Space Flight Operations Contract administered by
the Space Shuttle Program Office at Johnson.
riie Marshall Space Flight Center, near Hunslville, Alabama, is
home to most NASA rocket propulsion efforts. The Space Shuttle
Projects Office located at
Marshall —organization-
ally part of the Space
Shuttle Program Office
at Johnson— manages the
manufacturing and support
contracts to Boeing Rock-
etdyne for the Space Shut-
tle Main Engine (SSME),
to Eockheed Martin for the
External Tank (ET). and to
ATK Ihiokol Propulsion
for the Reusable Solid
Rocket Motor (RSRM. the
major piece of the Solid
Rocket Booster). Marshall
is also involved in micro-
gravity research and space
product development pro-
grams that fly as payloads
on the Space Shuttle.
West Palm Beach, PL
Pratt A Whitney
Tuftjopumps
OftiHe' Protluction
White Sands
Test Facility, NM
Hypfligotic Testing
Stennis Space Center
Bey si Louia. MS
SSME Test
The Stennis Space Center
in Bay St. Louis, Missis-
sippi, is the largest rocket
propulsion test complex in
ihe United States. Stennis
provides all of the testing
facilities for the Space
1 6
Report Volume I Auibust 2003
Shuttle Main Engines and External
Tank. (The Solid Rocket Boosters are
tested at the ATK Thiokol Propulsion
facilities in Utah.)
The Ames Research Center at Moffett
Field. California, has evolved from its
aeronautical research roots to become
a Center of Excellence for information
technology. The Center's primary im-
portance to the Space Shuttle Program,
however, lies in wind tunnel and arc -jet
testing, and the development of thermal
protection system concepts.
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Space Shuffle Program
NASA Organization
Human Explorotion & Development of Space
Associate Administrator
n
InternatK
Spac
Deputy /
^a\ Space Station and
Shuttle Programs
ssociole Administrator
Space Shuttle Progr.
Monoge
Manage
Space Shuttle Program (SSP)
Lounch Integration (KSC)
Program Integration
Manage
, SSP Sofety ond Miss
, SSP Development
, SSP Logistics (KSCl
Space Shuttle
Processing (KSC)
The Langley Research Center, at Hamp-
ton, Virginia, is the agency's primary
center for structures and materials and
supports the Space Shuttle Program in
these areas, as v\ell as in basic aerody-
namic and thermodynamic research.
The Programs
The two major human space flight ef-
forts within NASA are the Space Shut-
tle Program and International Space
Station Program, both headquartered at
Johnson although they re|X)rt to a Dep-
uty Associate Administrator at NASA
Headquarters in Washington. D.C.
The Space Shuttle Program Office at
Johnson is responsible for all aspects
of developing, supporting, and flying
the Space Shuttle. To accomplish these
tasks, the program maintains large
workforces at the various NASA Cen-
ters that host the facilities used by the program. The Space Shuttle
Program Office is also responsible for managing the Space Flight
Operations Contract with United Space Alliance that provides most
of the contractor support at Johnson and Kennedy, as well as a small
amoiml at Marshall.
The Contractors
The Space Shuttle Program employs a wide variel) of commercial
companies to provide services and products. Among the.se are some
of the largest aerospace and defense contractors in the counti7, in-
cluding (but not limited to):
United Space Alliance
This is a joint venture between Boeing and Lockheed Martin that
was established in 1996 to perform the Space Flight Operations
Contract that essentially conducts the day-to-day operation of the
Space Shuttle. United Space Alliance is headquartered in Houston.
Texas, and employs more than 10.000 people at Johnson, Kennedv,
and Marshall. Its contract currently runs through 2005.
The Boeing Company, NASA Systems
The Space Shuttle Orbiter was designed and manufactured by
Rockwell International, located primarily in Downey and Palmdale.
California. In 1996. The Boeing Company purchased the aerospace
assets of Rockwell International, and later moved the Downey op-
eration to Huntington Beach. California, as part of a consolidation
of facilities. Boeing is subcontracted lo United Space Alliance to
provide support to Orbiter modifications and operations, with work
performed in California, and at Johnson and Kennedy.
Spoce Shuttle |
ims tntegralion Office |
.^'-W'<fti"«M^r^f
Spoce Shuttle
Customer ond Flight
Integration Office
Spoce Shuttle
ojects Office (MSFC)
The Boeing Company, Rocketdyne Propulsion & Power
The Rocketdjne Division ttf Rockwell International was responsi-
ble lor the development and manufacture of the Space Shuttle Main
Engines, and continues to support the engines as a part of The Boe-
ing Company. The Space Shuttle Projects Office at Marshall man-
ages the main engines contract, with most of the work performed in
California, Stennis, and Kennedy.
ATK Thiokol Propulsion
ATK Thiokol Propulsion (formerly Morton-Thiokol) in Brigham
City, Utah, manufactures the Reusable Solid Rocket Motor seg-
ments that are the propellant sections of the Solid Rocket Boosters.
The Space Shuttle Projects Office at Marshall manages the Reus-
able Solid Rocket Motor contract.
Lockheed Martin Space Systems, Michoud Operations
The External lank was developed and manufactured by Martin
Marietta at the NASA Michoud Assembly Facility near New Or-
leans. Louisiana. Martin Marietta later merged with Lockheed to
create Lockheed Martin. The External Tank is the only disposable
part of the Space Shuttle system, .so new ones are always under
construction. The Space Shuttle Projects Office at Marshall man-
ages the External Tank contract.
Lockheed Martin Missiles and Fire Control
The Reinforced Carbon-Carbon (RCC) panels used on the nose
and wing leading edges of the Orbiter were manufactured by Ling-
Temco-Vought in Grand Prairie. Fcxas. Lockheed Martin acquired
LTV through a series of mergers and acquisitions. The Space Shuttle
Program office at Johnson manages the RCC support contract.
Report vouume I
» e*<*-
The launch of STS-107 on January 16, 2003.
Part One
The Accident
"Building rockets is hard." Part of the problem is that space
travel is in its infancy. Although humans have been launch-
ing orbital vehicles for almost 50 years now - about half the
amount of time we have been flying airplanes - contrast the
numbers. Since Sputnik, humans have launched just over
4,500 rockets towards orbit (not counting suborbital flights
and small sounding rockets). During the first 50 years of
aviation, there were over one million aircraft built. Almost
all of the rockets were used only once; most of the airplanes
were used more often.
There is also the issue of performance. Airplanes slowly
built their performance from the tens of miles per hour the
Wright Brothers initially managed to the 4.520 mph that Ma-
jor William J. Knight flew in the X-15A-2 research airplane
during 1967. Aircraft designers and pilots would slightly
push the envelope, slop and get comfortable with where they
were, then push on. Orbital rockets, by contrast, must have
ail of their performance on the first (and often, only) flight.
Physics dictates this - to reach orbit, without falling back to
Earth, you have to exceed about 17,500 mph. If you cannot
vary performance, then the only thing left to change is the
amount of payload - the rocket designers began with small
payloads and worked their way up.
Rockets, by their very nature, are complex and unforgiving
vehicles. They must be as light as possible, yet attain out-
standing performance to get to orbit. Mankind is, however,
getting better at building them. In the early days as often
as not the vehicle exploded on or near the launch pad; that
seldom happens any longer. It was not that different from
early airplanes, which tended to crash about as often as they
flew. Aircraft seldom crash these days, but rockets still fail
between two-and-five percent of the time. This is true of
just about any launch vehicle -Atlas. Delta, Soyuz, Shuttle
- regardless of what nation builds it or what basic configura-
tion is used; they all fail about the same amount of the time.
Building and launching rockets is still a very dangerous
business, and will continue to be so for the foreseeable fu-
ture while we gain experience at it. It is unlikely that launch-
ing a space vehicle will ever be as routine an undertaking as
commercial air travel - certainly not in the lifetime of any-
body who reads this. The scientists and engineers continu-
ally work on better ways, but if we want to continue going
into outer space, we must continue to accept the risks.
Pail One of the report of the Columbia Accident Investiga-
tion Board is organized into four chapters. In order to set
the background for further discussion. Chapter I relates the
history of the Space Shuttle Program before the Challenger
accident. The events leading to the original approval of the
Space Shuttle Program are recounted, as well as an exami-
nation of some of the promises made in order to gain that
approval. In retrospect, many of these promises could never
have been achieved. Chapter 2 documents the final flight of
Colmnbki. As a straightforward record of the event, it con-
tains no findings or recommendations. Chapter 3 reviews
five analytical paths - aerodynamic, thermodynamic, sensor
data timeline, debris reconstruction, and imaging evidence
- to show that all five independently arrive at the same con-
clusion. Chapter 4 describes the investigation into other pos-
sible physical factors that might have contributed to the ac-
cident, but were subsequently dismissed as possible causes.
REPORT Volume I
AUOUST 2003
The launch of ST S- 107 on January ?6, 2003.
The Evolution of the
Space Shuttle Program
More than two decades after its first flight, the Space Shuttle
remains the only reusable spacecraft in the world capable
of simultaneously putting multiple-person crews and heavy
cargo into orbit, of deploying, servicing, and retrieving
satellites, and of returning the products of on-orbit research
to Earth. These capabilities are an important asset for the
United States and its international partners in space. Current
plans call for the Space Shuttle to play a central role in the
U.S. human space flight program for years to come.
The Space Shuttle Program's remarkable successes, how-
ever, come with high costs and tremendous risks. The Feb-
ruary I disintegration of Columbia during re-entry. 17 years
after Chulleniicr was destroyed on ascent, is the most recent
reminder that sending people into orbit and returning them
safely to Earth remains a difficult and perilous endeavor.
It is the view of the Columbia Accident Investigation Board
that the Columbia accident is not a random event, but rather
a product of the Space Shuttle Program's history and current
management processes. Fully understanding how it hap-
pened requires an exploration of that history and manage-
ment. This chapter charts how the Shuttle emerged from a
series of political compromises that produced unreasonable
expectations - even myths - about its performance, how the
Challenf>er accident shattered those myths several years af-
ter NASA began acting upon them as fact, and how, in retro-
spect, the Shuttle's technically ambitious design resulted in
an inherently vulnerable vehicle, the safe operation of which
exceeded NASA's organizational capabilities as they existed
at the time of the Columbia accident. The Board's investiga-
tion of what caused the Columbia accident thus begins in the
fields of East Texas but reaches more than 30 years into the
past, to a series of economically and politically driven deci-
sions that cast the Shuttle program in a role that its nascent
technology could not support. To understand the cause of the
Columbia accident is to understand how a program promis-
ing reliability and cost efficiency resulted instead in a devel-
opmental vehicle that never achieved the fully operational
status NASA and the nation accorded it.
1.1 Genesis OF THE
Space Transportation System
The origins of the Space Shuttle Program date to discussions
on what should follow Project Apollo, the dramatic U.S.
missions to the moon.' NASA centered its post-Apollo plans
on developing nicrcasingly larger outposts in Earth orbit that
would be launched atop Apollo's immense Saturn V booster.
The space agency hoped to construct a 12-person space sta-
tion by 1975; subsequent stations would support 50. then
100 people. Other stations would be placed in orbit around
the moon and then be constructed on the lunar surface. In
parallel. NASA would develop the capability for the manned
exploration of Mars. The concept of a vehicle - or Space
Shuttle - to take crews and supplies to and from low-Earth
orbit arose as part of this grand vision ( see Figure 1 . 1 - 1 ). To
keep the costs of these trips to a minimum, NASA intended
to develop a fully reusable vehicle. -
Figure 1.1-1. Early concepfs for the Space Shuttle envisioned a
reusable two-stage vehicle with the reliability and versatility of o
commercial airliner.
Report vdlui
iT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BDARD
NASA's vision of a constellation of space stations and jour-
neying to Mars had little connection with political realities
of the time. In his final year in office. President Lyndon
Johnson gave highest priority to his Great Society programs
and to dealing with the costs and domestic turmoil associated
with the Vietnam war. Johnson's successor. President Rich-
ard Nixon, also had no appetite for another large, expensive,
Apollo-like space commitment. Nixon rejected NASA's am-
bitions with little hesitation and directed that the agency 's bud-
get be cut as much as was politically feasible. With NASA's
space station plans deferred and further production of the
Saturn V launch vehicle cancelled, the Space Shuttle was
the only manned space llight program that the space agency
could hope to undertake. But without space stations to ser-
vice, NASA needed a new rationale for the Shuttle. That ra-
tionale emerged from an intense three-year process of tech-
nical studies and political and budgetary negotiations that
attempted to reconcile the conflicting interests of NASA, the
Department of Defense, and the White House.'
1.2 Merging Conflicting Interests
During 1970, NASA's leaders hoped to secure White House
approval for' developing a fully reusable vehicle to provide
routine and low cost manned access to space. However, the
staff of the White House Office of Management and Budget,
charged by Nixon with reducing NASA's budget, was skep-
tical of the value of manned space flight, especially given
its high costs. To overcome these objections, NASA turned
to justifying the Space Shuttle on economic grounds. If the
same vehicle, NASA argued, launched all government and
private sector payloads and if that vehicle were reusable,
then the total costs of launching and maintaining satellites
could be dramatically reduced. Such an economic argument,
however, hinged on the willingness of the Department of
Defense to use the Shuttle to place national security pay-
loads in orbit. When combined, commercial, scientific, and
national security payloads would require 50 Space Shuttle
missions per year. This was enough to justify - at least on
paper - investing in the Shuttle.
Meeting the military's perceived needs while also keeping
the cost of missions low posed tremendous technological
hurdles. The Department of Defense wanted the Shuttle to
carry a 40,000-pound payload in a 60-foot-long payload
bay and, on some missions, launch and return to a West
Coast launch site after a single polar orbit. Since the Earth's
surface - including the runway on which the Shuttle was to
land - would rotate during that orbit, the Shuttle would need
to maneuver 1. 100 miles to the east during re-entry. This
"cross-range" requirement meant the Orbiter required large
delta-shaped wings and a more robust thermal protection
system to shield it from the heat of re-entry.
Developing a vehicle that could conduct a wide variety of
missions, and do .so cost-effectively, demanded a revolution in
space technology. The Space Shuttle would be the first reus-
able spacecraft, the first to have wings, and the first with a reus-
able thermal pri)tection system. Further, the Shuttle would be
the first to fly with reusable, high-pressure hydrogen/oxygen
engines, and the first winged vehicle to transition from orbital
speed to a hypersonic glide during re-entry.
Even as the design grew in technical complexity, the Office of
Management and Budget forced NASA to keep - or at least
promise to keep - the Shuttle's development and operating
costs low. In May 1 97 1 , NASA was told that it could count on
a maximum of $3 billion spread over five years for any new
development program. This budget ceiling forced NASA to
give up its hope of building a fully reusable two-stage vehicle
and kicked off an intense six-month search for an alternate
design, in the course of selling the Space Shuttle Program
within these budget limitations, and therefore guaranteeing
itself a viable post-Apollo future, NASA made bold claims
about the expected savings to be derived from revolutionary
technologies not yet developed. At the start of 1972, NASA
leaders told the White House that for $5. 1 5 billion they could
develop a Space Shuttle that would meet all performance
requirements, have a lifetime of 100 missions per vehicle,
and cost $7.7 million per flight.^ All the while, many people,
particularly those at the White House Office of Management
and Budget, knew NASA's in-house and external economic
studies were overly optimistic.^
Those in favor of the Shuttle program eventually won the
day. On January 5, 1972, President Nixon announced that
the Shuttle would be "designed to help transform the space
frontier of the 1970s into familiar territory, easily accessible
for human endeavor in the 1980s and 90s. This system will
center on a space vehicle that can shuttle repeatedly from
Earth to orbit and back. It will revdhttioiiize transpurtation
into near space, hy roiitiniziiii; it. (emphasis added)"'' Some-
what ironically, the President based his decision on grounds
very different from those vigorously debated by NASA and
the White House budget and science offices. Rather than
focusing on the intricacies of cost/benefit projections, Nixon
was swayed by the political benefits of increasing employ-
ment in key states by initiating a major new aerospace pro-
gram in the 1972 election year, and by a geopolitical calcula-
tion articulated most clearly by NASA Administrator James
Fletcher. One month before the decision, Fletcher wrote a
memo to the White House stating, "For the U.S. not to be
in space, while others do have men in space, is unthinkable,
and a position which America cannot accept."^
The cost projections Nixon had ignored were not forgotten
by his budget aides, or by Congress. A $5.5 billion ceiling
imposed by the Office of Management and Budget led NASA
to make a number of tradeoffs that achieved savings in the
short term but produced a vehicle that had higher operational
costs and greater risks than promised. One example was the
question of whether the "strap-on" boosters would use liquid
or solid propellants. Even though they had higher projected
operational costs, solid-rocket boosters were chosen largely
because they were less expensive to develop, making the
Shuttle the first piloted spacecraft to use solid boosters. And
since NASA believed that the Space Shuttle would be far
safer than any other spacecraft, the agency accepted a design
with no crew escape system {see Chapter 10.)
The commitments NASA made during the policy process
drove a design aimed at satisfying conflicting requirements:
large payloads and cross-range capability, but also low
development costs and the even lower operating costs of a
"routine" .system. Over the past 22 years, the resulting ve-
Report vouui
August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
hide has proved difficult and costly to operate, riskier than
expected, and, on two occasions, deadly.
It is the Board's view that, in retrospect, the increased com-
plexity of a Shuttle designed to be all things to all people
created inherently greater risks than if more realistic tech-
nical goals had been set at the start. Designing a reusable
spacecraft that is also cost-effective is a daunting engineer-
ing challenge; doing so on a tightly constrained budget is
even more difficult. Nevertheless, the remarkable system
we have today is a reflection of the tremendous engineering
expertise and dedication of the workforce that designed and
built the Space Shuttle w ithin the constraints it was given.
In the end, the greatest compromise NASA made was not so
much with any particular element of the technical design,
but rather with the premise of the vehicle itself. NASA
promised it could develop a Shuttle that would be launched
almost on demand and would fly many missions each year.
Throughout the history of the program, a gap has persisted
between the rhetoric NASA has used to market the Space
Shuttle and operational reality, leading to an enduring image
of the Shuttle as capable of safely and routinely carrying out
missions with little risk.
1 .3 Shuhle Development, Testing,
AND Qualification
The Space Shuttle was subjected to a variety of tests before
its first flight. However, NASA conducted these tests some-
what differently than it had for previous spacecraft." The
Space Shuttle Program philosophy was to ground-test key
hardware elements such as the main engines. Solid Rocket
Boosters. External Tank, and Orbiter separately and to use
analytical models, not flight testing, to certify the integrated
Space Shuttle system. During the Approach and Landing
Tests (see Figure 1 .3- 1 ). crews verified that the Orbiter could
successfully fly at low speeds and land safely; however, the
Space Shuttle was not flown on an unmanned orbital test
flight prior to its first mission - a significant change in phi-
losophy compared to that of earlier American spacecraft
Figure ).3-J. The firsf Orbiter was Enterprise, shown here being
released from >he Boeing 747 ShuHle Carrier Aircraft during the
Approach and landing Tests at Edwards Air Force Base.
The significant advances in technology that the Shuttle's
design depended on led its development to run behind
schedule. The dale for the first Space Shuttle launch slipped
from March 1978 to 1979, then to 1980. and finally to the
spring of 198 1 . One historian has attributed one year of this
delay "to budget cuts, a second year to problems with the
main engines, and a third year to problems with the thermal
protection tiles."" Because of these difficulties, in 1979 the
program underwent an exhaustive White House review. The
program was thought to be a billion dollars over budget,
and President Jimmy Carter wanted to make sure that it was
worth continuing. A key factor in the White House's final
assessment was that the Shuttle was needed to launch the
intelligence satellites required for verification of the SALT
II arms control treaty, a top Carter Administration priority.
The review reaffirmed the need for the Space Shuttle, and
with continued White House and Congressional support, the
path was clear for its transition from development to flight.
NASA ultimately completed Shuttle development for only
15 percent more than its projected cost, a comparatively
small cost oveirun for so complex a program.'"
The Orbiter that was destined to be the first to fly into space
was Coliinihia. In early 1979, NASA was beginning to feel
the pressure of being behind schedule. Despite the fact that
only 24,000 of the 30,000 Thermal Protection System tiles
had been installed, NASA decided to fly Coliinihia from the
manufacturing plant in Palmdale, California, to the Kennedy
Space Center in March 1979. The rest of the tiles would be
installed in Florida, thus allowing NASA to maintain the
appearance of Coliiiuhia'a scheduled launch date. Problems
with the main engines and the tiles were to leave Coliinihia
grounded for two more years.
1.4 The SHunLE Becomes "Operational"
On the first Space Shuttle mission, STS-I," Coliinihia car-
ried John W. Young and Robert L. Crippen to orbit on April
12, 1981, and returned them safely two days later to Ed-
wards Air Force Base in California (see Figure 1 .4-1 ). After
three years of policy debate and nine years of development,
the Shuttle returned U.S. astronauts to space for the first time
since the Apollo-Soyuz Test Project flew in July 1975. Post-
flight inspection showed that Coliinihia suffered slight dam-
age from excess Solid Rocket Booster ignition pressure and
lost 16 tiles, with 148 others sustaining some damage. Over
the following 15 months, Columbia was launched three
more times. At the end of its fourth mission, on July 4. 1982,
Coliinihia landed at Edwards where President Ronald Rea-
gan declared to a nation celebrating Independence Day that
"beginning with the next flight, the Coliinihia and her sister
ships will he fully operatitnuil. ready to provide economi-
cal and miiiine access to space for scientific exploration,
commercial ventures, and for tasks related to the national
security" [emphasis added |.'-
There were two reasons for declaring the Space Shuttle "op-
erational" so early in its flight program. One was NASA's
hope for quick Presidential approval of its next manned
space flight program, a space station, which would not
move forward while the Shuttle was still considered devel-
opmental. The second reason was that the nation was sud-
Repdrt Vdli
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Figure 1.4-1. The April 12, 1981, launch of STS-1, just seconds posf
7 a.m., carried osfronoufs John Young and Roberf Crippen info on
Earth orbital mission that lasted 54 hours.
denly facing a foreign challenger in launching commercial
satellites. The European Space Agency decided in 1973 to
develop Ariane, an expendable launch vehicle. Ariane first
flew in December 1979 and by 1982 was actively competing
with the Space Shuttle for commercial launch contracts. At
this point, NASA still hoped that revenue from commercial
launches would offset some or all of the Shuttle's operating
costs. In an effort to attract commercial launch contracts,
NASA heavily subsidized commercial launches by offering
services for $42 million per launch, when actual costs were
more than triple that figure." A 1983 NASA brochure titled
We Deliver touted the Shuttle as "the most reliable, flexible,
and cost-effective launch system in the world. "'^
Figure 1.4-2. The crew of STS-5 successfully deployed two
commercial communications satellites during the first "operational"
mission of the Space Shuttle.
Between 1982 and early 1986, the Shuttle demonstrated its
capabilities for space operations, retrieving two commu-
nications satellites that had suffered upper-stage misfires
after launch, repairing another communications satellite
on-orbit, and flying science missions with the pressur-
ized European-built Spacelab module in its payload bay.
The Shuttle took into space not only U.S. astronauts, but
also citizens of Germany, Mexico, Canada, Saudi Arabia,
France, the Netherlands, two payload specialists from
commercial enterprises, and two U.S. legislators. Senator
Jake Garn and Representative Bill Nelson. In 1985, when
four Orbiters were in operation, the vehicles flew nine mis-
sions, the most launched in a single calendar year. By the
end of 1985, the Shuttle had launched 24 communications
satellites (see Figure 1.4-2) and had a backlog of 44 orders
for future commercial launches.
On the surface, the program seemed to be progressing well.
But those close to it realized that there were numerous prob-
lems. The system was proving difficult to operate, with more
maintenance required between flights than had been expect-
ed. Rather than needing the 10 working days projected in
1975 to process a returned Orbiter for its next flight, by the
end of 1985 an average of 67 days elapsed before the Shuttle
was ready for launch.''*
Though assigned an operational role by NASA, during this
period the Shuttle was in reality .still in its early flight-test
stage. As with any other first-generation technology, opera-
tors were learning more about its strengths and weaknesses
from each flight, and making what changes they could, while
still attempting to ramp up to the ambitious flight schedule
NASA set forth years earlier. Already, the goal of launching
50 flights a year had given way to a goal of 24 flights per year
by 1989. The per-mission cost was more than $140 million, a
figure that when adjusted for inflation was seven times great-
er than what NASA projected over a decade earlier."' More
troubling, the pressure of maintaining the flight schedule cre-
ated a management atmosphere that increasingly accepted
less-than-specification performance of various components
and systems, on the grounds that such deviations had not
interfered with the success of previous flights.'
1.5 The Chauenger Accident
The illusion that the Space Shuttle was an operational
system, safe enough to carry legislators and a high-school
teacher into orbit, was abruptly and tragically shattered on
the morifing of January 28, 1986, when Challeiii^er was de-
stroyed 73 seconds after launch during the 25th mission (see
Figure 1 .5- 1 1. The seven-member crew perished.
To investigate. President Reagan appointed the 13-member
Presidential Commission on the Space Shuttle Challenger
Accident, which soon became known as the Rogers Com-
mission, after its chairman, former Secretary of State Wil-
liam P. Rogers."* Early in its investigation, the Commission
identified the mechanical cause of the accident to be the
failure of the joint of tine of the Solid Rocket Boosters. The
Commission foimd that the design was not well understood
by the engineers that operated it and that it had not been
adequately tested.
Report Volume I
COLUMBIA
ACCIDENT INVESTIGATION BDARO
Figure 1.5-1. the Space Shuttle Challenger v/os lost during ascent
on January 28, J986, when an O-ring and seal in the right Solid
Rocket Booster failed.
When the Rogers Commission discovered that, on the eve of
the launch, NASA and a contractor had vigorously debated
the wisdom of operating the Shuttle in the cold temperatures
predicted for the next day, and that more senior NASA
managers were unaware of this debate, the Commission
shifted the focus of its investigation to "NASA manage-
ment practices. Center-Headquarters relationships, and the
chain of command for launch commit decisions."''' As the
investigation continued, it revealed a NASA culture that
had gradually begun to accept escalating risk, and a NASA
safety program that was largely silent and ineffective.
The Rogers Commission report, issued on June 6, 1986,
recommended a redesign and recertification of the Solid
Rocket Motor joint and seal and urged that an indepen-
dent body oversee its qualification and testing. The report
concluded that the drive to declare the Shuttle operational
had put enormous pressures on the system and stretched its
resources to the limit. Faulting NASA safety practices, the
Commission also called for the creation of an independent
NASA Office of Safety, Reliability, and Quality Assurance,
reporting directly to the NASA Administrator, as well as
structural changes in program management.-" (The Rogers
Commission findings and recommendations are discussed in
more detail in Chapter 5.) It would take NASA 32 months
before the next Space Shuttle mission was launched. Dur-
ing this time, NASA initiated a series of longer-term vehicle
upgrades, began the construction of the Orbiter Endeavour
to replace Cliallenf^er, made significant organizational
changes, and revised the Shuttle manifest to reflect a more
realistic flight rate.
The Challcnfier accident also prompted policy changes. On
August 15, 1986, President Reagan announced that the Shut-
tle would no longer launch commercial satellites. As a result
of the accident, the Department of Defense made a decision
to launch all future military payloads on expendable launch
vehicles, except the few remaining satellites that required
the Shuttle's unique capabilities.
In the seventeen years between the Challenfjer and Co-
lumbia accidents, the Space Shuttle Program achieved
significant successes and also underwent organizational and
managerial changes. The program had successfully launched
several important research satellites and was providing most
of the "heavy lifting" of components necessary to build the
International Space Station (see Figure 1.5-2). But as the
Board subsequently learned, things were not necessarily as
they appeared. (The posl-Challenger history of the Space
Shuttle Program is the topic of Chapter 5.)
Figure 1.5-2. The International Space Station as seen from an
approaching Space Shuttle.
1.6 Concluding Thoughts
The Orbiter that carried the STS-107 crew to orbit 22 years
after its first flight reflects the histoid of the Space Shuttle
Program. When Cohiinhia lifted off from Launch Complex
39-A at Kennedy Space Center on January 16, 2003, it su-
perficially resembled the Orbiter that had first flown in 1981.
and indeed many eleinents of its airframe dated back to its
first flight. More than 44 percent of its tiles, and 41 of the
44 wing leading edge Reinforced Carbon-Carbon (RCC)
panels were original equipment. But there were also many
new systems in Columbia, from a modern "glass" cockpit to
second-generation main engines.
Although an engineering marvel that enables a wide-variety
of on-orbit operations, including the assembly of the Inter-
national Space Station, the Shuttle has few of the mission
capabilities that NASA originally promised. It cannot be
launched on demand, does not recoup its costs, no longer
carries national security payloads, and is not cost-effective
enough, nor allowed by law, to carry commercial satellites.
Despite efforts to improve its safety, the Shuttle remains a
complex and risky system that remains central to U.S. ambi-
tions in space. Columbia's failure to return home is a harsh
reminder that the Space Shuttle is a developmental vehicle
that operates not in routine flight but in the realm of danger-
ous exploration.
Report volui
AUBUST zaQ3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Endnotes For Chapter 1
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
George Mueller, Associate Administrator for Manned Space Flight,
NASA, "Honorary Fellowship Acceptance," address delivered to the
British Interplanetary Society, University College, London, England,
August 10, 1968, contained in John M. Logsdon, Ray A. Williamson,
Roger D. Launius, Russell J. Acker, Stephen J. Garber, and Jonathan L.
Friedman, editors. Exploring the Unknown: Selected Documents in the
History of the U.S. Civil Space Program Volume IV: Accessing Space,
NASA SP-4407 (V^ashington: Government Printing Office, 1999), pp.
202-205.
' For detailed discussions of the origins of the Space Shuttle, see Dennis R.
Jenkins, Space Shuttle: The History of the National Space Transportation
System - The First 100 Missions (Cope Canaveral, FL: Specialty Press,
2001); T. A. Heppenheimer, The Space Shuttle Decision: NASA's Search
for a Reusable Space Vehicle, NASA SP-4221 (Washington: Government
Printing Office, 1999; also published by the Smithsonian Institution Press,
2002); and T. A. Heppenheimer, Development of the Space Shuttle,
1972-1981 (Washington: Smithsonian Institution Press, 2002). Much of
the discussion in this section is based on these studies.
See John M. Logsdon, "The Space Shuttle Program: A Policy Failure?"
Science, May 30, 1986 (Vol. 232), pp. 1099-1105 for on account of this
decision process. Most of the information and quotes in this section are
taken from this article.
See also comments by Robert F. Thompson, Columbia Accident
Investigation Board Public Hearing, April 23, 2003, in Appendix G.
Heppenheimer, The Space Shuttle Decision, pp. 278-289, and Roger
A. Pieike, Jr., "The Space Shuttle Program; 'Performance vs. Promise,'"
Center for Space and Geosciences Policy, University of Colorado, August
31, 1991; Logsdon, "The Space Shuttle Program: A Policy Failure?" pp.
1099-1105.
Quoted in Jenkins, Space Shuttle, p. 171.
Memorandum from J. Fletcher to J. Rose, Special Assistant to the
President, November 22, 1971; Logsdon, John, "The Space Shuttle
Program: A Policy Failure?" Science, May 30, 1986, Volume 232, pp.
1099-1105.
The only actual flight tests conducted of the Orbiter were a series of
Approach and Landing Tests where Enterprise (OV-101) was dropped
from its Boeing 747 Shuttle Carrier Aircraft while flying at 25,000 feet.
These tests - with crews aboard - demonstrated the low-speed handling
capabilities of the Orbiter and allowed an evaluation of the vehicle's
landing characteristics. See Jenkins, Space Shuttle, pp. 205-212 for more
information.
Heppenheimer, Deve/opment of the Space Shuttle, p. 355.
As Howard McCurdy, a historian of NASA, has noted: "With the
now-familiar Shuttle configuration, NASA officials come close to
meeting their cost estimate of $5.15 billion for phase one of the Shuttle
program. NASA actually spent $9.9 billion in real year dollars to
take the Shuttle through design, development and initial testing. This
sum, when converted to fixed year 1971 dollars using the aerospace
price deflator, equals $5.9 billion, or a 15 percent cost overrun on
the original estimate for phase one Compared to other complex
development programs, this was not o large cost overrun." See Howard
McCurdy, "The Cost of Space Flight," Space Policy 10 (4) p. 280. For
a program budget summary, see Jenkins, Space Shuttle, p. 256.
STS stands for Space Transportation System. Although in the years just
before the 1986 Challenger accident NASA adopted on alternate Space
Shuttle mission numbering scheme, this report uses the original STS flight
designations.
President Reagan's quote is contained in President Ronald Reagan,
"Remarks on the Completion of the Fourth Mission of the Space Shuttle
Columbia," July 4, 1982, p. 870, in Public Papers of the Presidents of the
United States: Ronald Reagan (Washington: Government Printing Office,
1982-1991 ). The emphasis noted is the Board's.
"Pricing Options for the Space Shuttle," Congressional Budget Office
Report, 1985.
The quote is from page 2 of the We Deliver brochure, reproduced in
Exploring the Unknown Volume IV, p. 423.
NASA Johnson Space Center, "Technology Influences on the Space
Shuttle Development," June 8, 1986, p. 1-7,
The 1971 cost-per-flight estimate was $7.7 million; $140.5 million dollars
in 1985 when adjusted for inflation becomes $52.9 million in 1971
dollars or nearly seven times the 1971 estimate. "Pricing Options for the
Space Shuttle."
See Diane Vaughon, The Challenger Launch Decision: Risky Technology,
Culture, and Deviance at NASA (Chicago: The University of Chicago
Press, 1996).
See John M. Logsdon, "Return to Flight: Richard H. Truly and the
Recovery from the Challenger Accident," in Pomelo E. Mack, editor.
From Engineering to Big Science; The NACA and NASA Collier Trophy
Research Project Winners, NASA SP-42t9 (Washington; Government
Printing Office, 1998) for on account of the aftermath of the accident.
Much of the account in this section is drown from this source.
Logsdon, "Return to Flight," p. 348.
Pres/dent/ol Commission on the Spoce Shuttle Challenger Accident
(Washington; Government Printing Office, June 6, 1986).
Report Voui
Columbians Final Fliaht
Space Shuttle missions are not necessarily launched in the
same order they are planned (or "manifested." as NASA
calls the process). A variety of scheduling, funding, tech-
nical, and - occasionally - political reasons can cause the
shuffling of missions over the course of the two to three
years it takes to plan and launch a flight. This explains why
the 1 13th mission of the Space Shuttle Program was called
STS-107. It would be the 28th flight ofColiinihici.
While the STS-107 mission will likely be remembered most
for the way it ended, there was a great deal more to the
dedicated science mission than its tragic conclusion. The
planned microgravity research spanned life sciences, physi-
cal sciences, space and earth sciences, and education. More
than 70 scientists were involved in the research that was
conducted by Coliiiiihia's seven-member crew over 1 6 days.
This chapter outlines the history of STS-107 from its mis-
sion objectives and their rationale through the accident and
its initial aftermath. The analysis of the accident's causes
follows in Chapter 3 and subsequent chapters.
2.1 Mission Objectives and Their Rationales
Throughout the 1990s. NASA flew a number of dedicated
science missions, usually aboard Coliimhia because it was
equipped for extended-duration missions and was not being
used for Shuttle-Mir docking missions or the assembly of
the International Space Station. On many of these missions,
Columbia carried pressurized Spacelab or SPACEHAB
modules that extended the habitable experiment space avail-
able and were intended as facilities for life sciences and
microgravity research.
In June 1997, the Flight Assignment Working Group at John-
son Space Center in Houston designated STS- 1 07, tentatively
scheduled for launch in the third quarter of Fiscal Year 2000, a
"research module" flight. In July 1997, several committees of
the National Academy of Science's Space Studies Board sent
a letter to NASA Administrator Daniel Goldin recommend-
ing that NASA dedicate several future Shuttle missions to
microgravity and life sciences. The purpose would be to train
scientists to take full advantage of the International Space
Station's research capabilities once it became operational,
and to reduce the gap between the last planned Shuttle science
mission and the start of science research aboard the Space
Station.' In March 1998. Goldin announced that STS-107.
tentatively scheduled for launch in May 2000. would be a
multi-disciplinary science mission modeled after STS-90. the
Neurolab mi.ssion scheduled later in 1998.^ In October 1998.
the Veterans Affairs and Housing and Urban Development
and Independent Agencies Appropriations Conference Re-
port expressed Congress' concern about the lack of Shuttle-
based science missions in Fiscal Year 1999, and added $\5
million to NASA's budget for STS-107. The following year
the Conference Report reserved $40 million for a second sci-
ence mission. N.-XS A cancelled the second science mission in
October 2002 and used the money for STS-107.
In addition to a variety of U.S. experiments assigned to
STS-107. a joint U.S. /Israeli space experiment - the Medi-
terranean-Israeli Dust Experiment, or MEIDEX - was added
to STS-107 to be accompanied by an Israeli astronaut as
part of an international cooperative effort aboard the Shuttle
similar to those NASA had begun in the early 1980s. Triaiui,
a deployable Earth-observing satellite, was also added to the
mission to save NASA from having to buy a commercial
launch to place the satellite in orbit. Political disagreements
between Congress and the White House delayed Triana, and
the satellite was replaced by the Fast Reaction Experiments
Enabling Science, Technology, Applications, and Research
(FREESTAR) payload. which was mounted behind the
SPACEHAB Research Double Module.'
Figure 2.1-1 . Columbia, at the launch pad on January 15, 2003.
Report VoLur
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Schedule Slippage
STS-107 was finally scheduled for launch on January II,
2001. After 13 delays over two years, due mainly to other
missions taking priority, Colnmhia was launched on January
16, 2003 (see Figure 2. 1-1 ). Delays may take several fomis.
When any delay is mentioned, most people think of a Space
Shuttle sitting on the launch pad waiting for launch. But mo.st
delays actually occur long before the Shuttle is configured for
a mission. This was the case for STS-107 - of the 1 3 delays,
only a few occurred after the Orbiter was configured for
flight; most happened earlier in the planning process. Three
specific events caused delays for STS-107:
• Removal of Trhiiur. This Earth-observing satellite was
replaced with the FREESTAR payload.
• Orbiter Maintenance Down Period: Columhici's depot-
level maintenance took six months longer than original-
ly planned, primarily to correct problems encountered
with Kapton wiring (see Chapter 4). This resulted in the
STS-109 Hubble Space Telescope service mission be-
COLUMBIA
Coliimhki was named after a Boston-based sloop com-
manded by Captain Robert Gray, who noted while sailing to
the Pacific Northwest a flow of muddy water fanning from
the shore, and decided to explore what he deemed the "Great
River of the West." On May 11, 1792. Gray and his crew
maneuvered the Colnmhia past the treacherous sand bar and
named the river after his ship. After a week or so of trading
with the local tribes. Gray left without investigating where
the river led. Instead, Gray led the Colnmhia and its crew on
the first U.S. circumnavigation of the globe, carrying otter
skins to Canton, China, before returning to Boston in 1793.
In addition to Colnmhia (0V-I()2), which first flew in 1981,
Challenger (OV-099) first flew in 1 983. Discovery (OV- 1 03 )
in 1 984, and Atlantis (OV- 1 04) in 1 985. Endeavonr(0\- 1 05),
which replaced Challenf^er. first flew in 1992. At the time
of the launch of ST.S-107. Colnmhia was unique since it
was the last remaining Orbiter to have an internal airlock
on the mid-deck. (All the Orbiters originally had internal
aidocks. but all excepting Colnmhia were modified to pro-
vide an external docking mechanism for flights to Mir and
the International Space Station.) Because the airlock was
not located in the payload bay, Colnmhia could carry longer
payloads such as the Chandra space telescope, which used
the full length of the payload bay. The internal airlock made
the mid-deck more cramped than those of other Orbiters, but
this was less of a problem when one of the laboratory mod-
ules was installed in the payload bay to provide additional
habitable volume.
Colnmhia had been manufactured to an early structtiral
standard that resulted in the airframe being heavier than the
later Orbiters. Coupled with a more-forward center of grav-
ity because of the internal aidock, Colnmhia could not carry
as much payload weight into orbit as the other Orbiters. This
made Colnmhia less desirable for missions to the Interna-
tional Space Station, although planning was nevertheless
underway to modify Colnmhia for an International Space
Station flight sometime after STS-107.
ing launched before STS-107 because it was considered
more urgent.
• Flowliner cracks: About one month before the planned
July 19, 2002 launch date for STS-107, concerns about
cracks in the Space Shuttle Main Engine propellant
system flowliners caused a four-month grounding of
the Orbiter fleet. (The flowliner, which is in the inain
propellant feed lines, mitigates turbulence across the
flexible bellows to smooth the flow of propellant into
the main engine low-pressure turbopump. It also pro-
tects the bellows from flow-induced vibration.) First
discovered on Atlantis, the cracks were eventually
discovered on each Orbiter; they were fixed by weld-
ing and polishing. The grounding delayed the e.xchange
of the Expedition 5 International Space Station crew
with the Expedition 6 crew, which was scheduled for
STS-113. To maintain the International Space Sta-
tion assembly sequence while minimizing the delay
in returning the Expedition 5 crew, both STS-112 and
STS-1 13 were launched before STS-107.
The Crew
The STS-107 crew selection process followed standard pro-
cedures. The Space Shuttle Program provided the Astronaut
Office with mission requirements calling for a crew of seven.
There were no special requirements for a rendezvous, extra-
vehicular activity (spacewalking), or use of the remote ma-
nipulator arm. The Chief of the Astronaut Office announced
the crew in July 2000. To maximize the amount of science re-
search that could be performed, the crew formed two teams,
Red and Blue, to support around-the-clock operations.
Crew Training
The Columbia Accident Investigation Board thoroughly re-
viewed all pre-mission training (see Figure 2.1-2) for the
STS-107 crew, Houston Mission Controllers, and the Ken-
Figure 2.) -2. tian Ramon (left), Laurel Clark, and Michael Ander-
son during a training exercise at the Johnson Space Center.
Report Volume I
IGUST Z003
Left to right: David Brown, Rick Husband, Laurel Clark, Kalpana Chawla, Michael Anderson, William McCool, llan Ramon.
Rick Husband, Commander. Husband. 45. was a Colonel in the
U.S. Air Force, a test pilot, and a veteran of ST.S -96. He received a
B.S. in Mechanical Engineering from Texas Tech University and a
M.S. in Mechanical Engineering from California State University,
Fresno. He was a member of the Red Team, working on experi-
ments including the European Research In Space and Terrestrial
Osteoporosis and the Shuttle Ozone Limb Sounding Experiment.
William C. McCool, Pilot. McCool, 41, was a Commander in the
U.S. Navy and a test pilot. He received a B.S. in Applied Science
from the U.S. Naval Academy, a M.S. in Computer Science from
the University of Maryland, and a M.S. in Aeronautical Engi-
neering from the U.S. Naval Postgraduate School. A member of
the Blue Team, McCool worked on experiments including the
Advanced Respirator)- Monitoring System, Biopack, and Mediter-
ranean Israeli Dust Experiment.
Michael P. Anderson, Payload Commander and Mission Special-
ist. Anderson, 43, was a Lieutenant Colonel in the U.S. Air Force,
a former instructor pilot and tactical officer, and a veteran of
STS-89. He received a B.S. in
Physics/Astronomy from the Uni- THE
versity of Washington, and a M.S. in
Physics from Creighton University. A
member of the Blue Team, Anderson
worked with experiments including
the Advanced Respiratory Monitor-
ing System. Water Mist Fire Suppres-
sion, and Structures of Flame Balls at
Low Lewis-number.
David M. Brown, Mission Specialist.
Brown, 46, was a Captain in the U.S.
Navy, a naval aviator, and a naval
night surgeon. He received a B.S. in
Biology from the College of William
and Mary and a M.D. from Eastern
Virginia Medical School. A member
of the Blue Team, Brown worked on the Laminar Soot Processes,
Structures of Flame Balls at Low Lewis-number, and Water Mist
Fire Suppression experiments.
Kalpana Chawla, Flight Engineer and Mission Specialist. Chawla,
41, was an aerospace engineer, a FAA Certified Flight Instructor,
and a veteran of STS-87. She received a B.S. in Aeronautical En-
gineering from Punjab Engineering College, India, a M.S. in Aero-
space Engineering from the University of Texas, Arlington, and a
Ph.D. in Aerospace Engineering from the University of Colorado,
Boulder. A member of the Red Team, Chawla worked with experi-
ments on Astroculture, Advanced Protein Crystal Facility, Mechan-
ics of Granular Materials, and the Zeolite Crystal Growth Furnace.
Laurel Clark, Mission Specialist. Clark, 41, was a Commander
(Captain-Select) in the U.S. Navy and a naval flight surgeon. She
received both a B.S. in Zoology and a M.D. from the University of
Wisconsin, Madison. A member of the Red Team, Clark worked on
experiments including the Closed Equilibrated Biological Aquatic
System, Sleep-Wake Actigraphy and Light Exposure During
Spaceflight, and the Vapor Compres-
CREW ^'"" Distillation Flight Flxperiment,
llan Rimion, Payload Specialist. Ra-
mon, 48, was a Colonel in the Israeli
Air Force, a fighter pilot, and Israel's
first astronaut. Ramon received a
B.S. in Electronics and Computer
Engineering from the University of
Tel Aviv, Israel. As a member of the
Red Team, Ramon was the primary
crew member responsible for the
Mediterranean Israeli Dust Experi-
ment (MEIDEX). He also worked
on the Water Mist Fire Suppression
and the Microbial Physiology Flight
Experiments Team experiments,
amont; others.
COLUMBIA
ACCIDENT INVESTIGATION BHARD
nedy Space Center Launch Control Team. Mission training
for the STS-107 crew comprised 4,81 1 hours, with an addi-
tional 3,500 hours of payload-specific training. The Ascent/
Entry Flight Control Team began training with the STS-107
crew on October 22, 2002, and participated in 16 integrated
ascent or entry simulations. The Orbiter Flight Control team
began training with the crew on April 23, 2002. participating
in six joint integrated simulations with the crew and payload
customers. Seventy-seven Flight Control Room operators
were assigned to four shifts for the STS-107 mission. All had
prior certifications and had worked missions in the past.
The STS-107 Launch Readiness Review was held on Decem-
ber 18, 2002, at the Kennedy Space Center. Neither NASA
nor United Space Alliance noted any training issues for launch
controllers. The Mission Operations Directorate noted no
crew or flight controller training issues during the January
9. 2003, STS-107 Flight Readi'ness Review. According to
documentation, all personnel were trained and certified, or
would be trained and certified before the flight. Appendix D. I
contains a detailed STS-107 Training Report.
Orbiter Preparation
Board investigators reviewed Coltiiiihia's maintenance, or
"flow" records, including the recovery from STS-109 and
preparation for STS-107, and relevant areas in NASA's
Problem Reporting and Corrective Action database, which
contained 1 6,500 Work Authorization Documents consisting
of 600,000 pages and 3.9 million steps. This database main-
tains critical information on all maintenance and modifica-
tion work done on the Orbiters (as required by the Orbiter
Maintenance Requirements and Specifications Document).
It al.so maintains Corrective Action Reports that document
problems discovered and resolved, the Lost/Found item da-
tabase, and the Launch Readiness Review and Flight Readi-
ness Re^view documentation (see Chapter 7).
The Board placed emphasis on maintenance done in areas
of particular concern to the investigation. Specifically, re-
cords for the left main landing gear and door assembly and
left wing leading edge were analyzed for any potential con-
tributing factors, but nothing relevant to the cause of the
accident was discovered. A review of Thermal Protection
System tile maintenance records revealed some "non-con-
formances" and repairs made after Coliiinbicfs last flight,
but these were eventually dismissed as not relevant to the
investigation. Additionally, the Launch Readiness Review
and Flight Readiness Review records relating to those sys-
tems and the Lost/Found item records were reviewed, and
no relevance was found. During the Launch Readiness Re-
view and Flight Readiness Review processes, NASA teams
analyzed 18 lost items and deemed them inconsequential.
(Although this incident was not considered significant by
the Board, a further discussion of foreign object debris
may be found in Chapter 4.)
Payload Preparation
The payload bay configuration for STS-107 included the
SPACEHAB access tunnel, SPACEHAB Research Double
Module (RDM), the FREESTAR payload, the Orbital Ac-
SRACEHmB
Figure 2.1-3. The SPACEHAB Research Double Module as seen
from the off fJigfif deck windows of Columbia during S7S-107. A
thin slice of Earth's horizon is visible behind the vertical stabilizer.
celeration Research Experiment, and an Extended Duration
Orbiter pallet to accommodate the long flight time needed
to conduct all the experiments. Additional experiments
were stowed in the Orbiter mid-deck and on the SPACE-
HAB roof (see Figures 2.1-3 and 2.1-4). The total liftoff
payload weight for STS-107 was 24,536 pounds. Details on
STS-107 payload preparations and on-orbit operations are
in Appendix D.2.
Payload readiness reviews for STS-107 began in May 2002,
with no significant abnormalities reported throughout the
processing. The final Pa>load Safety Review Panel meet-
ing prior to the mission was held on January 8, 2003, at the
Kennedy Space Center, where the Integrated Safety Assess-
ments conducted for the SPACEHAB and FREESTAR pay-
loads were presented for final approval. All payload physical
stresses on the Orbiter were reported within acceptable lim-
its. The Extended Duration Orbiter pallet was loaded into the
aft section of the payload bay in High Bay 3 of the Orbiter
Processing Facility on April 25. 2002. The SPACEHAB
Report Vai
IGUST 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Figure 2.1-4. The configuration
of Columbia's payload bay for
ST^W7.
and FREESTAR payloads were loaded horizontally on
March 24, with an Integration Verification Test on June 6.
The payload bay doors were closed on October 31 and were
not opened prior to launch. (All late stow activities at the
launch pad were accomplished in the vertical position using
the normal crew entry hatch and SPACEHAB access tunnel.)
Rollover of the Orbiterto the Vehicle Assembly Building for
mating to the Solid Rocket Boosters and External Tank oc-
curred on November 18. Mating took place two days later,
and rollout to Launch Complex 39-A was on December 9.
Unprecedented security precautions were in place at
Kennedy Space Center prior to and during the launch of
STS-107 because of prevailing national security concerns
and the inclusion of an Israeli crew member.
SPACEHAB was powered up at Launch minus 51 (L-51)
hours (January 14) to prepare for the late stowing of time-
critical experiments. The stowing of material in SPACE-
HAB once it was positioned vertically took place at L^6
hours and was completed by L-3 1 hours. Late middeck pay-
load stowage, required for the experiments involving plants
and insects, was performed at the launch pad. Flight crew
equipment loading started at L-22.5 hours, while middeck
experiment loading took place from Launch minus 19 to 16
hours. Fourteen experiments, four of which were powered,
were loaded, all without incident.
2.2 Flight Preparation
NASA senior management conducts a complex series of
reviews and readiness polls to monitor a mission's prog-
ress toward flight readiness and eventual launch. Each step
requires written certification. At the final review, called the
Flight Readiness Review, NASA and its contractors certify
that the necessary analyses, verification activities, and data
products associated with the endorsement have been ac-
complished and "indicate a high probability for mission
success." The review establishes the rationale for accepting
any remaining identifiable risk; by signing the Certificate of
Flight Readiness, NASA senior managers agree that they
have accomplished all preliminary items and that they agree
to accept that risk. The Launch Integration Manager over-
sees the flight preparation process.
STS-107 Flight Preparation Process
The flight preparation process reviews progress toward
flight readiness at various junctures and ensures the organi-
zation is ready for the next operational phase. This process
includes Project Milestone Reviews, three Program Mile-
stone Reviews, and the Flight Readiness Review, where the
Certification of Flight Readiness is endorsed.
The Launch Readiness Review is conducted within one
month of the launch to certify that Certification of Launch
Readiness items from NSTS-08117, Appendices H and Q,
Flight Preparation Process Plan, have been reviewed and
acted upon. The STS-107 Launch Readiness Review was
held at Kennedy Space Center on December 18, 2002.
The Kennedy Space Center Director of Shuttle Processing
chaired the review and approved continued preparations for
a January 16, 2003. launch. Onboard payload and experi-
mental status and late stowage activity were reviewed.
A Flight Readiness Review, which is chaired by the Of-
fice of Space Flight Associate Administrator, usually occurs
about two weeks before launch and provides senior NASA
management with a summary of the certification and veri-
fication of the Space Shuttle vehicle, flight crew, payloads,
and rationales for accepting residual risk. In cases where
the Flight Preparation Process has not been successfully
completed. Certification of Flight Readiness exceptions will
be made, and presented at the Pre-Launch Mission Manage-
ment Team Review for disposition. The final Flight Readi-
ness Review for STS-107 was held on January 9, 2003, a
week prior to launch. Representatives of all organizations
except Flight Crew, Ferry Readiness, and Department of
Defense Space Shuttle Support made presentations. Safety,
Reliability & Quality Assurance summarized the work per-
formed on the Ball Strut Tie Rod Assembly crack, defective
booster connector pin, booster separation motor propellant
paint chip contamination, and STS-113 Main Engine 1
nozzle leak (see Appendix E. 1 for the briefing charts). None
of the work performed on these items affected the launch.
Certificate of Flight Readiness: No actions were assigned
during the Flight Readiness Review. One exception was
included in the Certificate of Flight Readiness pending the
completion of testing on the Ball Strut Tie Rod Assembly.
Report volui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Testing was to be completed on January 15. This exception
was to be closed witii final flight rationale at the STS-107
Pre-iaunch Mission Management Team meeting. All princi-
pal managers and organizations indicated their readiness to
support the mission.
Normally, a Mission Management Team - consisting of
managers from Engineering, System Integration, the Space
Flight Operations Contract Office, the Shuttle Safety Office,
and the Johnson Space Center directors of flight crew opera-
tions, mission operations, and space and life sciences - con-
venes two days before launch and is maintained until the
Orbiter safely lands. The Mission Management Team Chair
reports directly to the Shuttle Program Manager
The Mission Management Team resolves outstanding prob-
lems outside the responsibility or authority of the Launch
and Flight Directors. During pre-launch. the Mission
Management Team is chaired by the Launch Integration
Manager at Kennedy Space Center, and during flight by
the Space Shuttle Program Integration Manager at Johnson
Space Center. The guiding document for Mission Manage-
ment operations is NSTS 07700. Volume VIII.
A Pre-launch Mission Management Team Meeting oc-
curs one or two days before launch to assess any open items
or changes since the Flight Readiness Review, provide a
GO/NO-GO decision on continuing the countdown, and
approve changes to the Launch Commit Criteria. Simul-
taneously, the Mission Management Team is activated to
evaluate the countdown and address any issues remaining
from the Flight Readiness Review. STS-107's Pre-launch
Mission Management Team meeting, chaired by the Acting
Manager of Launch Integration, was held on January 14,
some 48 hours prior to launch, at the Kennedy Space Cen-
ter. In addition to the standard topics, such as weather and
range support, the Pre-Launch Mission Management Team
was updated on the status of the Ball Strut Tie Rod Assem-
bly testing. The exception would remain open pending the
presentation of additional test data at the Delta Pre-Launch
Mission Management Team review the next day.
The Delta Pre-Launch Mission Management Team Meet-
ing was also chaired by the Acting Manager of Launch Inte-
gration and met at 9:00 a.m. EST on January 15 at the Ken-
nedy Space Center The major issues addressed concerned
the Ball Strut Tie Rod Assembly and potential strontium
chromate contamination found during routine inspection of
a (non-STS-107) spacesuit on January 14. The contamina-
tion concern was addressed and a toxicology analysis de-
termined there was no risk to the STS-107 crew. A poll of
the principal managers and organizations indicated all were
ready to support STS-107.
A Pre-Tanking Mission Management Team Meeting
was also chaired by the Acting Manager of Launch Integra-
tion. This meeting was held at 12:10 a.m. on January 16.
A problem with the Solid Rocket Booster External Tank At-
tachment ring was addressed for the first time. Recent mis-
sion life capability testing of the material in the ring plates
revealed static strength properties below minimum require-
ments. There were concerns that, assuming worst-case flight
NASA Times
SliS5^
Like most engineering or technical operations, NASA
generally uses Coordinated Universal Time (UTC,
formerly called Greenwich Mean Time) as the standard
reference for activities. This is, for convenience, often
converted to local time in either Florida or Texas - this
report uses Eastern Standard Time (EST) unless other-
wise noted. In addition to the normal 24-hour clock,
NASA tells time via several other methods, all tied to
specific events. The most recognizable of these is "T
minus (T-)" time that counts down to every launch in
hours, minutes, and seconds. NASA also uses a less
precise "L minus" (L-) time that tags events that hap-
pens days or weeks prior to launch. Later in this report
there are references to "Entiy Interface plus (El-i-)" time
that counts, in seconds, from when an Orbiter begins re-
entry. In all ca.ses, if the time is "minus" then the event
being counted toward has not happened yet; if the time
is "plus" then the event has already occurred.
environments, the ring plate would not meet the safety factor
requirement of 1.4 - that is, able to withstand 1.4 times the
maximum load expected in operation. Based on analysis of
the anticipated flight environment for STS-107, the need to
meet the safety factor requirement of 1.4 was waived (see
Chapter 10). No Launch Commit Criteria violations were
noted, and the STS-107 final countdown began. The loading
of propel lants into the External Tank was delayed by some
70 minutes, until seven hours and 20 minutes before launch,
due to an extended fuel cell calibration, a liquid oxygen
replenish valve problem, and a Launch Processing System
reconfiguration. The countdown continued normally, and at
T-9 minutes tlje Launch Mission Management Team was
polled for a GO/NO-GO launch decision. All members re-
ported GO, and the Acting Manager of Launch Integration
gave the final GO launch decision.
Once the Orbiter clears the launch pad, responsibility passes
from the Launch Director at the Kennedy Space Center to
the Flight Director at Johnson Space Center During flight,
the mission is also evaluated from an engineering perspec-
tive in the Mission Evaluation Room, which is managed
by Vehicle Engineering Office personnel. Any engineering
analysis conducted during a mission is coordinated through
and first presented to the Mission Evaluation Room, and is
then presented by the Mission Evaluation Room manager to
the Mission Management Team.
2.3 Launch Sequence
The STS-107 launch countdown was scheduled to be about
24 hours longer than usual, primarily because of the extra
time required to load cryogens for generating electricity
and water into the Extended Duration Orbiter pallet, and
for final stowage of plants, insects, and other unique science
payloads. SPACEHAB stowage activities were about 90
minutes behind schedule, but the overall launch countdown
was back on schedule when the communication system
check was completed at L-24 hours.
REPORT Van
August 2003
COLUMBIA
ACCIDENT INVESTIGATiCN BOARD
At 7 hours and 20 minutes prior to the scheduled launch on
January 16, 2003. ground crews began filling the External
Tank with over 1.500.000 pounds of cryogenic propellants.
At about 6:15 a.m.. the Final Inspection Team began its vi-
sual and photographic check of the launch pad and vehicle.
Frost had been noted during earlier inspections, but it had
dissipated by 7:15 a.m.. when the Ice Team completed its
inspection.
Heavy rain had fallen on Kennedy Space Center while
the Shuttle stack was on the pad. The launch-day weather
was 65 degrees Fahrenheit with 68 percent relative humid-
ity, dew point 59 degrees, calm winds, scattered clouds at
4.000 feet, and visibility of seven statute miles. The fore-
cast weather for Kennedy Space Center and the Transoce-
anic Abort Landing sites in Spain and Morocco was within
launch criteria limits.
At about 7:.^0 a.m. the crew was driven from their quarters
in the Kennedy Space Center Industrial Area to Launch
Complex 39-A. Commander Rick Husband was the first
crew member to enter Coliiiiihiii. at the 195-foot level of
the launch tower at 7:53 a.m. Mission Specialist Kalpana
Chawla was the last to enter, at 8:45 a.m. The hatch was
closed and locked at 9:17 a.m.
The countdown clock e.xecuted the planned hold at the T-20
minute-mark at 10:10 a.m. The primary ascent computer
software was switched over to the launch-ready configura-
tion, communications checks were completed with all crew
members, and all non-essential personnel were cleared from
the launch area at 10:16 a.m. Fifteen minutes later the count-
down clock came out of the planned hold at the T-9 minutes,
and at 10:35 a.m., the GO was given for Auxiliary Power
Unit start. STS-107 began at 10:39 a.m. with ignition of the
Solid Rocket Boosters (.see Figure 2.3-1 ).
Wind Shear
Before a launch, balloons are released to detemiine the di-
rection and speed of the winds up to 50.000 to 60,000 feet.
Various Doppler sounders are alsi) used to get a wind profile,
which, for STS- 107, was unremarkable and relatively constant
at the lower altitudes.
Columbia encountered a wind shear about 57 seconds
after launch during the period of maximum dynamic pres-
sure (max-q). As the Shuttle passed through 32,000 feet, it
experienced a rapid change in the out-of-plane wind speed
of minus 37.7 feet per second over a 1.200-foot altitude
range. Immediately after the vehicle flew through this alti-
tude range, its sideslip (beta) angle began to increase in the
negative direction, reaching a value of minus 1.75 degrees
at 60 seconds.
A negative beta angle means that the wind vector was on
the left side of the vehicle, pushing the nose to the right
and increasing the aerodynamic force on the External Tank
bipod stiTJt attachment. Several studies have indicated that
the aerodynamic loads on the External Tank forward attach
bipod, and also the interacting aerodynamic loads between
the External Tank and the Orbiter, were larger than normal
but within design limits.
Predicted and Actual l-Loads
On launch day, the General-Purpose Computers on the Or-
biter are updated with information based on the latest obser-
vations of weather and the physical properties of the vehicle.
These "I-loads" are initializing data sets that contain ele-
ments specific to each mission, such as measured winds, at-
mospheric data, and Shuttle configuration. The I-loads output
target angle of attack, angle of sideslip, and dynamic pressure
Report vdli
\T 2 a o 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
as a function of Mach number to ensure that the structural
loads the Shuttle experiences during ascent are acceptable.
After the accident, investigators analyzed Columbia's as-
cent loads using a reconstruction of the ascent trajectory.
The wing loads measurement used a flexible body structural
loads assessment that was validated by data from the Modu-
lar Auxiliary Data System recorder, which was recovered
from the accident debris. The wing loads assessment includ-
ed crosswind effects, angle of attack (alpha) effects, angle of
sideslip (beta) effects, normal acceleration (g), and dynamic
pressure (q) that could produce stresses and strains on the
Orbiter's wings during ascent. This assessment showed that
all Orbiter wing loads were approximately 70 percent of
their design limit or less throughout the ascent, including the
previously mentioned wind shear.
The wind shear at 37 seconds after launch and the Shuttle
stack's reaction to it appears to have initiated a very low
frequency oscillation, caused by liquid oxygen sloshing in-
side the External Tank,"" that peaked in amplitude 75 seconds
after launch and continued through Solid Rocket Booster
separation at 127 seconds after launch. A small oscillation
is not unusual during ascent, but on STS-107 the amplitude
was larger than normal and lasted longer. Less severe wind
shears at 95 and 105 seconds after launch contributed to the
continuing oscillation.
An analysis of the External Tank/Orbiter interface loads,
using simulated wind shear, crosswind, beta effects, and
liquid oxygen slosh effects, showed that the loads on the
External Tank forward attachment were only 70 percent
of the design certification limit. The External Tank slosh
study confirmed that the flight control system provided
adequate stability throughout ascent.
The aerodynamic loads on the External Tank forward attach
bipod were analyzed using a Computational Fluid Dynamics
simulation, that yielded axial, side-force, and radial loads,
and indicated that the external air loads were well below the
design limit during the period of maximum dynamic pres-
sure and also when the bipod foam separated.
Nozzle Deflections
Both Solid Rocket Boosters and each of the Space Shuttle
Main Engines have exhaust nozzles that deflect ("gimbal")
in response to flight control system commands. Review of
the STS-107 ascent data revealed that the Solid Rocket
Booster and Space Shuttle Main Engine nozzle positions
twice exceeded deflections seen on previous flights by a
factor of 1.24 to 1.33 and 1.06, respectively. The center
and right main engine yaw deflections first exceeded those
on previous flights during the period of maximum dynamic
pressure, immediately following the wind shear. The de-
flections were the flight control system's reaction to the
wind shear, and the motion of the nozzles was well within
the design margins of the flight control system.
Approximately 1 15 seconds after launch, as booster thrust
diminished, the Solid Rocket Booster and Space Shuttle
Main Engine exhaust nozzle pitch and yaw deflections ex-
ceeded those seen previously by a factor of 1.4 and 1.06 to
1.6, respectively. These deflections were caused by lower
than expected Reusable Solid Rocket Motor performance,
indicated by a low burn rate; a thrust mismatch between
the left and right boosters caused by lower-than-normal
thrust on the right Solid Rocket Booster; a small built-in
adjustment that favored the left Solid Rocket Booster pitch
actuator; and flight control trim characteristics unique to the
Performance Enhancements flight profile for STS-107.^
The Solid Rocket Booster burn rate is temperature-depen-
dent, and behaved as predicted for the launch day weather
conditions. No two boosters bum exactly the same, and a
minor thrust mismatch has been experienced on almost
every Space Shuttle mission. The booster thrust mismatch
on STS-107 was well within the design margin of the flight
control system.
Debris Strike
Post-launch photographic analysis showed that one large
piece and at lea,st two smaller pieces of insulating foam
separated from the External Tank left bipod (-Y) ramp area
at 81 .7 seconds after launch. Later analysis showed that the
larger piece struck Colitiiihia on the underside of the left
wing, around Reinforced Carbon-Carbon (RCC) panels 5
through 9, at 81.9 seconds after launch (see Figure 2.3-2).
Further photographic analysis conducted the day after
launch revealed that the large foam piece was approximately
21 to 27 inches long and 12 to 18 inches wide, tumbling at
a minimum of 1 8 times per second, and moving at a relative
velocity to the Shuttle Stack of 625 to 840 feet per second
(416 to 573 miles per hour) at the time of impact.
Figure 2.3-2. A sfiower of foam debris offer fhe impact on
Columbia's left wing. The event was nof observed in real time.
Report Volume I
AUQU5T 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Arrival on Orbit
Two minutes and seven seconds after launch, the Solid
Rocket Boosters separated from the External Tank. They
made a normal splashdown in the Atlantic Ocean and were
subsequently recovered and returned to the Kennedy Space
Center for inspection and refurbishment. Approximately
eight and a half minutes after launch, the Space Shuttle Main
Engines shut down normally, followed by the separation of
the Externa! Tank. .At 1 1:20 a.m., a two-minute burn of the
Orbital Maneuvering System engines began to position
Coluiithia in its proper orbit, inclined 39 degrees to the
equator and approximately 175 miles above Earth.
2.4 On-Orbit Events
By 1 1 :39 a.m. EST, one hour after launch, Columbia was in
orbit and crew members entered the "post-insertion time-
line." The crew immediately began to configure onboard
systems for their 1 6-day stay in space.
Flight Day 1, Thursday, January 16
The payload bay doors were opened at 12:36 p.m. and the
radiator was deployed for cooling. Crew members activated
the Extended Duration Orbiter pallet (containing extra pro-
pellants for power and water production) and FREESTAR,
and they began to set up the SPACEHAB module (see Fig-
ure 2.4-1 ). The crew then ran two experiments with the Ad-
vanced Respiratory Monitoring System stationary bicycle in
SPACEHAB.
The crew also set up the Bioreactor Demonstration System,
Space Technology and Research Students Bootes, Osteopo-
rosis Experiment in Orbit, Closed Equilibrated Biological
Aquatic System, Miniature Satellite Threat Reporting Sys-
tem, and Biopack, and performed Low Power Transceiver
communication tests.
Flight Day 2, Friday, January 17
The Ozone Limb Sounding Experiment 2 began measuring
the ozone layer, while the Mediterranean Israeli Dust Ex-
periment (MEIDEX) was set to measure atmospheric aero-
sols over the Mediterranean Sea and the Sahara Desert. The
Critical Viscosity of Xenon 2 experiment began studying the
fluid properties of Xenon.
The crew activated the SPACEHAB Centralized Experiment
Water Loop in preparation for the Combustion Module 2 and
Vapor Compression Distillation Flight Experiment and also
activated the Facility for Absorption and Surface Tension,
Zeolite Crystal Growth, Astroculture, Mechanics of Granu-
lar Materials, Combined Two Phase Loop Experiment,
European Research In Space and Terrestrial Osteoporosis,
Biological Research in Canisters, centrifuge configurations.
Enhanced Orbiter Refrigerator/Freezer Operations, and Mi-
crobial Physiological Flight Experiment.
Not known to Mission Control, the Columbia crew, or anyone
else, between 10:30 and 1 1 :00 a.m. on Flight Day 2, an object
drifted away from the Orbiter This object, which subsequent
analysis suggests may have been related to the debris strike,
had a departure velocity between 0.7 and 3.4 miles per hour,
remained in a degraded orbit for approximately two and a
half days, and re-entered the atmosphere between 8:45 and
1 1:45 p.m. on January 19. This object was discovered after
the accident when Air Force Space Command reviewed its ra-
dar tracking data. (See Chapter 3 for additional discussion.)
Flight Day 3, Saturday, January 18
The crew conducted its first on-orbit press conference. Be-
cause of heavy cloud cover over the Middle East, MEIDEX
objectives could not be accomplished. Crew members began
an experiment to track metabolic changes in their calcium
levels. The crew resolved a discrepancy in the SPACEHAB
Video Switching Unit, provided body fluid samples for the
Physiology and Biochemistry experiment, and activated the
Vapor Compression Distillation Flight Experiment.
Figure 2.4-1. The tunnel linking the SPACEHAB module fo the
Columbia crew compartment provides a view of Kalpana Chawla
worlc/ng in SPACEHAB.
Flight Day 4, Sunday, January 19
Husband. Chawla. Clark, and Ramon completed the first ex-
periments with the Combustion Module 2 in SPACEHAB,
which were the Laminar Soot Processes, Water Mist Fire
suppression, and Structure of Flame Balls at Low Lewis
number. The latter studied combustion at the limits of flam-
mability. producing the weakest flame ever to burn: each
flame produced one watt of thermal power (a birthday-cake
candle, by comparison, produces 50 watts).
Experiments on the human body's response to microgravity
continued, with a focus on protein manufacturing, bone and
calcium production, renal stone formation, and saliva and
urine changes due to viruses. Brown captured the first ever
images of upper-atmosphere "sprites" and "elves." which
are produced by intense cloud-to-ground electromagnetic
impulses radiated by heavy lightning discharges and are as-
sociated with storms near the Earth's surface.
Report Vouur
IQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The crew reported about a cup of water under the SPACE-
HAB module sub-floor and significant amounts clinging
to the Water Separator Assembly and Aft Power Distribu-
tion Unit. The water was mopped up and Mission Control
switched power from Rotary Separator I to 2.
Flight Day 5, Monday, January 20
Mission Control saw indications of an electrical short on
Rotary Separator 2 in SPACEHAB; the separator was pow-
ered down and isolated from the electrical bus. To reduce
condensation with both Rotary Separators off, the crew
had to reduce the flow in one of Columbia's Freon loops to
SPACEHAB in order to keep the water temperature above
the dew point and prevent condensation from forming in the
Condensing Heat Exchanger. However, warmer water could
lead to higher SPACEHAB cabin temperatures; fortunately,
the crew was able to keep SPACEHAB temperatures accept-
able and avoid condensation in the heat exchanger.
Flight Day 6, Tuesday, January 21
The temperature in the SPACEHAB module reached 81 de-
grees Fahranhcil. The crew reset the temperature to accept-
able levels, and Mission Control developed a contingency
plan to re-establish SPACEHAB humidity and temperature
control if further degradation occuired. The Miniature Satel-
lite Threat Reporting System, which detects ground-based
radio frequency sources, experienced minor command and
telemetry problems.
Flight Day 7, Wednesday, January 22
Both teams took a half day off. MEIDEX tracked thunder-
storms over central Africa and captured images of four sprites
and two elves as well as two rare images of meteoroids enter-
ing Earth's atmosphere. Payload experiments continued in
SPACEHAB, with no further temperature complications.
Flight Day 8, Thursday, January 23
Eleven educational events were completed using the low-
power transceiver to transfer data files to and from schools
in Maryland and Massachusetts. The Mechanics of Granular
Materials experiment completed the sixth of nine tests. Bio-
pack shut down, and attempts to recycle the power were un-
successful; ground teams began developing a repair plan.
Mission Control e-mailed Husband and McCool that post-
launch photo analysis showed foam from the External Tank
had struck the Orbiter's left wing during ascent. Mission
Control relayed that there was "no concern for RCC or tile
damage'" and because the phenomenon had been seen be-
fore, there was "absolutely no concern for entry." Mission
Control also e-mailed a short video clip of the debris strike,
which Husband forwarded to the rest of the crew.
Flight Day 9, Friday, January 24
Crew members conducted the mission's longest combustion
test. Spiral moss growth experiments continued, as well as
Astroculture experiments that harvested samples of oils from
roses and rice flowers. Experiments in the combustion cham-
ber continued. Although the temperature in SPACEHAB was
maintained. Mission Control estimated that about a half-gal-
lon of water was unaccounted for, and began planning in-
flight maintenance for the Water Separator Assembly.
Davtd Brown sfabilizes a digital video camera prior fo a press
conference in the SPACEHAB Research Double Module aboard
Columbia during STS-107.
Flight Day 10, Saturday, January 25
Experiments with bone cells, prostate cancer, bacteria
growth, thermal heating, and surface tension continued.
MEIDEX captured images of plumes of dust off the coasts
of Nigeria, Mauritania, and Mali. Images of sprites were
captured over storms in Perth, Australia. Biopack power
could not be restored, so all subsequent Biopack sampling
was performed at ambient temperatures.
Flight Day 11, Sunday, January 26
Vapor Compression Distillation Flight Experiment opera-
tions were complete; SPACEHAB temperature was allowed
to drop to 73 degrees Fahrenheit. Scientists received the first
live Xybion digital downlink images from MEIDEX and
confirmed significant dust in the Middle East. The STARS
experiment hatched a fish in the aquatic habitat and a silk
moth from its cocoon.
Flight Day 12, Monday, January 27
Combustion and granular materials experiments concluded.
The combustion module was configured for the Water Mist
experiment, which developed a leak. The Microbial Physiol-
RepORT Volume i Auoust 2003
COLUMBIA
ACCIOENT INVESTIGATION BDARD
ogy Right Experiment expended its final set of samples in
yeast and bacteria growth. The crew made a joint observa-
tion using MEIDEX and the Ozone Limb Sounding Experi-
ment. MEIDEX captured images of dust over the Atlantic
Ocean for the first time.
Flight Day 13, Tuesday, January 28
The crew took another half day off. The Bioreactor experi-
ment produced a bone and prostate cancer tumor tissue sam-
ple the size of a golf ball, the largest ever grown in space.
The crew, along with ground support personnel, observed
a moment of silence to honor the memory of the men and
women of Apollo J and Challenger. MEIDE.X was prepared
to monitor smoke trails from research aircraft and bonfires
in Brazil. Water Mist nms began after the leak was stopped.
Flight Day 14, Wednesday, January 29
Ramon reported a giant dust storm over the Atlantic Ocean
that provided three days of MEIDEX observations. Ground
teams confirmed predicted weather and climate effects and
found a huge smoke plume in a large cuinulus cloud over
the Amazon jungle. BIOTUBE experiment ground teams
reported growth rates and root curvatures in plant and flax
roots different from anything seen in normal gravit\' on
Earth. The crew received procedures from Mission Con-
trol for vacuum cleanup and taping of the Water Separator
Assembly prior to re-entr>. Temperatures in two Biopack
culture chambers were too high for normal cell growth, so
several Biopack experiments were terminated.
Flight Day 15, Thursday, January 30
Final samples and readings were taken for the Physiology
and Biochemistry team experiments. Husband, McCool, and
Chawla ran landing simulations on the computer training
system. Husband found no excess water in the SPACEHAB
sub-floor, but as a precaution, he covered several holes in the
Water Separator Assembly.
Flight Day 16, Friday, January 31
The Water Mist Experiment concluded and the combustion
module was closed. MEIDEX made final observations of
dust concentrations, sprites, and elves. Husband, McCool.
and Chawla completed their second computer-based landing
simulation. A flight control system checkout was performed
satisfactorily using Auxiliary Power Unit 1. with a run time
of 5 minutes, 27 seconds.
After the flight control system checkout, a Reaction Control
System "hot-fire" was performed during which all thrust-
ers were fired for at least 240 milliseconds. The Ku-band
antenna and the radiator on the left payload bay door were
stowed.
Flight Day 17, Saturday, February 1
Ail onboard experiments were concluded and stowed, and
payload doors and covers were closed. Preparations were
completed for de-orbit, re-entry, and landing at the Kennedy
Rick Husband works with the Biological Research in Canister ex-
periment on Columbia's mid-declc.
Space Center Suit checks confirmed that proper pressure
would be maintained during re-entry and landing. The pay-
load bay doors were closed. Husband and McCool config-
ured the onboard computers with the re-entry software, and
placed Columhki in the proper attitude for the de-orbit burn.
2.5 Debris Strike Analysis
AND Requests for Imagery
As is done after every launch, within two hours of the lift-
off the Intercenter Photo Working Group examined video
from tracking cameras. An initial review did not reveal any
unusual events. The next day. when the Intercenter Photo
Working Group personnel received much higher resolution
film that had been processed overnight, they noticed a debris
strike at 8 1 .9 seconds after launch.
A large object from the left bipod area of the External Tank
struck the Orbiter, apparently impacting the underside of the
left wing near RCC panels 3 through 9. The object's large
size and the apparent momentum transfer concerned Inter-
center Photo Working Group personnel, who were worried
that Coliiinhia had sustained damage not detectable in the
limited number of views their tracking cameras captured.
This concern led the Intercenter Photo Working Group Chair
to request, in anticipation of analysts' needs, that a high-
resolution image of the Orbiter on-orbit be obtained by the
Department of Defense. By the Board's count, this would
be the first of three distinct requests to image Columbia
on-orbit. The exact chain of events and circumstances sur-
rounding the movement of each of these requests through
Shuttle Program Management, as well as the ultimate denial
of these requests, is a topic of Chapter 6.
After discovering the strike, the Intercenter Photo Working
Group prepared a report with a video clip of the impact and
sent it to the Mission Management Team, the Mission Evalu-
ation Room, and engineers at United Space Alliance and
Boeing. In accordance with NASA guidelines, these contrac-
tor and NASA engineers began an assessment of potential
impact damage to Coliiinhia\ left wing, and soon formed a
Debris Assessment Team to conduct a formal review.
Report vouui
August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BDARO
The first formal Debris Assessment Team meeting was held
on January 21, five days into the mission. It ended with the
highest-ranking NASA engineer on the team agreeing to
bring the team's request for imaging of the wing on-orbit,
which would provide better information on which to base
their analysis, to the Johnson Space Center Engineering
Management Directorate, with the expectation the request
would go forward to Space Shuttle Program managers. De-
bris Assessment Team members subsequently learned that
these managers declined to image Columbia.
Without on-orbit pictures of Coliiiiihici, the Debris Assess-
ment Team was restricted to using a mathematical modeling
tool called Crater to assess damage, although it had not been
designed with this type of impact in mind. Team members
concluded over the next six days that some localized heating
damage would most likely occur during re-entry, but they
could not definitively state that structural damage would
result. On January 24, the Debris Assessment Team made a
presentation of these results to the Mission Evaluation Room,
whose manager gave a verbal summary (with no data) of that
presentation to the Mission Management Team the same day.
The Mission Management Team declared the debris strike a
"turnaround'" issue and did not pursue a request for imagery.
Even after the Debris Assessment Team's conclusion had
been reported to the Mission Management Team, engineers
throughout NASA and Mission Control continued to ex-
change e-mails and discuss possible damage. These messag-
es and discussions were generally sent only to people within
the senders' area of expertise and level of seniority.
William McCool folks to Mission Confro/ from fbe off flight deck of
Columbia during STS-107.
2.6 De-Orbit Burn and Re-Entry Events
At 2:30 a.m. EST on Februai-y 1. 2003, the Entry Flight
Control Team began duty in the Mission Control Center.
The Flight Control Team was not working any issues or
problems related to the planned de-orbit and re-entry of
Columbia. In particular, the team indicated no concerns
about the debris impact to the left wing during ascent, and
treated the re-entry like any other.
The team worked through the de-orbit preparation checklist
and re-entry checklist procedures. Weather forecasters, with
the help of pilots in the Shuttle Training Aircraft, evaluated
landing site weather conditions at the Kennedy Space Cen-
ter. At the time of the de-orbit decision, about 20 minutes
before the initiation of the de-orbit burn, all weather obser-
vations and forecasts were within guidelines set by the flight
rules, and all systems were normal.
Shortly after 8:00 a.m., the Mission Control Center Entiy
Flight Director polled the Mission Control room for a GO/
NO-GO decision for the de-orbit burn, and at 8: 10 a.m., the
Capsule Communicator notified the crew they were GO for
de-orbit burn.
As the Orbiter flew upside down and tail-first over the In-
dian Ocean at an altitude of 175 statute miles. Commander
Husband and Pilot McCool executed the de-orbit burn at
8:15:30 a.m. using Columbia'!^ two Orbital Maneuvering
System engines. The de-orbit maneuver was performed on
the 255th orbit, and the 2-minute, 38-second burn slowed
the Orbiter from 17,500 mph to begin its re-entry into the
atmosphere. During the de-orbit burn, the crew felt about
10 percent of the effects of gravity. There were no prob-
lems during the burn, after which Husband maneuvered
Columbia into a right-side-up, forward-facing position, with
the Orbiter's nose pitched up.
Entry Interface, arbitrarily defined as the point at which the
Orbiter enters the discernible atmosphere at 400.000 feet,
occurred at 8:44:09 a.m. (Entry Interface plus 000 seconds,
written EI-i-000) over the Pacific Ocean. As Columbia de-
scended from space into the atmosphere, the heat produced
by air molecules colliding with the Orbiter typically caused
wing leading-edge temperatures to rise steadily, reaching
an estimated 2,500 degrees Fahrenheit during the next six
minutes. As superheated air molecules discharged light,
astronauts on the flight deck saw bright flashes envelop the
Orbiter, a normal phenomenon.
At 8:48:39 a.m. (EI4-270), a sensor on the left wing leading
edge spar showed strains higher than those seen i)n previous
Columbia re-entries. This was recorded only on the Modular
Auxiliary Data System, and was not telemetered to ground
controllers or displayed to the crew (see Figure 2.6-1 ).
At 8:49:32 a.m. (EI-i-323). traveling at approximately Mach
24.5, Columbia executed a roll to the right, beginning a pre-
planned banking turn to manage lift, and therefore limit the
Orbiter's rate of descent and heating.
At 8:50:53 a.m. (El-i-404). traveling at Mach 24.1 and at
approximately 243,000 feet, Columbia entered a 10-minute
period of peak heating, during which the thermal stresses
were at their maximum. By 8:52:00 a.m. (EI-i-471), nearly
eight minutes after entering the atmosphere and some 300
miles west of the California coastline, the wing leading-edge
temperatures usually reached 2,650 degrees Fahrenheit.
Columbia crossed the California coast west of Sacramento
at 8:53:26 a.m. (EI+557). Traveling at Mach 23 and 23 1 .600
feet, the Orbiter's wing leading edge typically reached more
than an estimated 2.800 degrees Fahrenheit.
Report Volui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARD
Now crossing California, the Orbiter appeared to obsei"v-
ers on tiie ground as a brigiit spot of light moving rapidly
across the sky. Signs of debris being shed were sighted at
8:53:46 a.m. (EI+577), when the superheated air surround-
ing the Orbiter suddenly brightened, causing a noticeable
streak in the Orbiter's luminescent trail. Observers witnessed
another four similar events during the following 23 seconds,
and a bright flash just seconds after Columbia crossed from
California into Nevada airspace at 8:54:25 a.m. (EI+614),
when the Orbiter was traveling at Mach 22.5 and 227,400
feet. Witnesses observed another 1 8 similar events in the next
four minutes as Colunihia streaked over Utah, Arizona. New
Mexico, and Texas.
In Mission Control, re-entry appeared normal until 8:54:24
a.m. (EI+613), when the Maintenance, Mechanical, and Crew
Systems (MMACS) officer informed the Flight Director that
four hydraulic sensors in the left wing were indicating "off-
scale low," a reading that falls below the minimum capability
of the sensor As the seconds passed, the Entry Team contin-
ued to discuss the four failed indicators.
At 8:55:00 a.m. ( El+65 1 ), nearly 1 1 minutes after Coliiinhia
had re-entered the atmosphere, wing leading edge tempera-
tures normally reached nearly 3.000 degrees Fahrenheit. At
8:55:32 a.m. (EI-(-683), Columbia crossed from Nevada into
Utah while traveling at Mach 21.8 and 223.400 ft. Twenty
seconds later, the Orbiter crossed from Utah into Arizona.
At 8:56:30 a.m. (EI+741 ). Columbia initiated a roll reversal,
turning from right to left over Arizona. Traveling at Mach
20.9 and 219.000 feet, Columbia crossed the Arizona-New
Mexico state line at 8:56:45 (Ei+756), and passed just north
of Albuquerque at 8:57:24 (El+795).
Around 8:58:00 a.m. (El-i-831). wing leading edge tem-
peratures typically decreased to 2.880 degrees Fahrenheit.
At 8:58:20 a.m. ( E1-k85 1 ), traveling at 209,800 feet and Mach
19.5, Columbia crossed from New Mexico into Texas, and
about this time shed a Thermal Protection System tile, which
was the most westerly piece of debris that has been recovered.
Searchers found the tile in a field in Littlefieid, Texas, just
northwest of Lubbock. At 8:59:15 a.m. (EI-^906), MMACS
informed the Flight Director that pressure readings had been
lost on both left main landing gear tires. The Flight Director
then told the Capsule Communicator (CAPCOM) to let the
crew know that Mission Control saw the messages and was
evaluating the indications, and added that the Flight Control
Team did not understand the crew's last transmission.
At 8:59:32 a.m. (EI-i-923), a broken response from the
mission commander was recorded: "Roger, [cut off in mid-
word) ..." It was the last communication from the crew and
the last telemetry signal received in Mission Control. Videos
made by observers on the ground at 9:00:18 a.m. (EI-i-969)
revealed that the Orbiter was disintegrating.
2.7 Events Immediately Following
THE Accident
A series of events occurred immediately after the accident
that would set the stage for the subsequent investigation.
NASA Emergency Response
Shortly after the scheduled landing time of 9:16 a.m. EST,
NASA declared a "Shuttle Contingency" and executed the
Contingency Action Plan that had been established after
the Cli(illc'ni>er accident. As part of that plan, NASA Ad-
ministrator Sean O'Keefe activated the international Space
Station and Space Shuttle Mishap Interagency Investigation
Board at I0:.30 a.m. and named Admiral Harold W. Gehman
Jr., U.S. Navy, retired, as its chair.
Senior members of the NASA leadership met as part of the
Headquarters Contingency Action Team and quickly notified
astronaut families, the President, and members of Congress.
President Bush telephoned Israeli Prime Minster Ariel Sha-
ron to inform him of the loss oi Columbia crew member llan
Ramon, Israel's first astronaut. Several hours later. President
Bush addressed the nation, saying. "The Columbia is lost.
There are no survivors."
R E P O R ■
IQUST 2003
COLUMBIA
ACCIDENT iNVESTIGATIDN 8DARD
The Orbiter has a large glowing Field surrounding it in this view
taken from Mesquite, Texas, /oolc/ng south.
Taken at the same time as the photo at left, but from Hewitt, Texas,
looking north.
13:46:39 (El*270)
Sensor 1
(Front Wing Spar al
RCC Panel 9)
small increase in strain
13:52:17
LMG Brake Line temp 0 - On
Wtieelwell Inboard Sidewall
(Small Increase in temp -
"Bit Flip Up")
13:53:11
Hydraulic System 1 LH
lnt)oard Eleven Actr Ret LN
temp Otf-Scale Low
13:49:49 (EH340)
Left OMS Pod
Thermocouple
Start of off-nominal
temperature trend
13:51:14(61*4251
Sensor 4
(Wing Spar Panel 9 temp)
Stan of off-nominal trend
13:48:59 (EH2901
Sensor 2
(Wing LE LWR
Attacfi Clevis RCC10)
off-nominal
temperature trend
13:50:19 (EH-370)
Sensor 3
(Left Wing Lower
Surface Thermocouple)
Begins off-nominal
temperature Increase
13:51:00 (EK411)
LATD = 38 8 deg N
LONG = 135.5 degW
ALTD = 242.824 ft
VREL =16.420 2 mph
HRATE = 76 51 blu(sq,ft.-
QBAR = 21.79 psf
13:50:00 (El*351)
Lj6,TD
LONG =
ALTD =
VREL =
HRATE =
08AR =
38.3 deg N
140,5 deg W
246.445 ft
16,631 .2 mph
70.40 btu(sq.ft.-s)
17 42 psf
13:52:06 (EI-M77)
LATD = 39 0 deg N
LONG = 130-1 deg W
ALTD =237.910 ft
VREL =16, 133.3 mph
HFiATE = 80.73 btu(sq.fl -s)
OBAR =26 2 psf
13:53:06 (EK537)
LATD = 38 8 deg N
LOI>IG =125 2 deg W
ALTD = 233.426 ft
VREL =15,823.8 mph
HRATE = 83.98 blu(Sg ft.-s)
QBAR =30.88 psf
13:54:06 (EH-597)
LATD = 38.4 deg N
LONG = 120.5 deg W
ALTD =229.037 ft
VREL =15,470.0 mph
HRATE = 86.34 btu(sq.fl,-s)
QBAR =36 04 psf
Figure 2.6-1 . This simpliFied timeline shows the re-entry path of Columbia on February 1, 2003. The information presented here is a com-
posite of sensor data telemetered to the ground combined with data from the Modular Auxiliary Data System recorder recovered after the
accident. Note that the First off-nominal reading was a small increase in a strain gauge at the front wing spar behind RCC panel 9-left. The
chart is color-coded: blue boxes confoin position, attitude, and velocity information; orange boxes indicate when debris was shed from the
Orbiter; green boxes are signiFicant aerodynamic control events; gray boxes confain sensor information from the Modular Auxiliary Data
System, and yellow boxes contain telemetered sensor information. The red boxes indicate other significant events.
Report Voli
IT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BDARD
This view was taken from Dallas. (Robert McCullough/© 2003 The
Dallas Morning News)
This video was captured by a Danish crew operating an AH-64
Apache helicopter near Fort Hood, Texas.
STS-107 Re-entry Trajectory and Timeline
(First Off-Nominal Event to Loss of Signal)
13:55:07-58:11
D»bris#?-15
13:57:24
Main Landing Gear
LH Outboard Tire
Pressure 2 (Slart of
il trend -
■Bit Flip Up")
13:55:06 (El*657)
LATD = 37 8 deg N
LONG =1l69degW
ALTD = 22S.079 K
VREL = 15,057,9 mpll
HRATE = 86,72 blu(sq,N -s)
QBAR = 40,90 ps(
13:56:06 (EH-717)
lATD = 36 7 deg N
LONG =1117degW
ALTD = 221,649 «
VREL = 14.600,3 mph
HRATE = 85 10 btu(sq tt -s)
QBAR =45 05psf
13:57:06 (El*777)
LATD = 35 7 deg N
LONG = 107 6 deg W
ALTO =218,783 ft
VREL =14,070 9 mph
HRATE = 81 ,00 biu(sq.fl,-
QBAR = 47.93 psf
13:58:02 (EH-833)
LATD = 34,6 derj N
LONG = 104 2 deg W
ALTO = 212,475 ft
VREL =13,499,3 mph
HRATE = 81,59 btu(sq,ft,-s)
QBAR =58 29psf
13:59:06 (El*897)
LATD = 33 4 deg N
LONG = 100,4 deg W
ALTD = 204.320 tt
VREL = 12,726,9 mph
HRATE = 80,44 btu(sq.fl -
QBAR =73 30psf
13:59:31
(El'r922)
LATD
32 9 deg N
LONG
- 99,8 deg W
ALTD
200.861 ft
VREL
- 12,384 8 mph
HRATE
- 79,29 Wu(sq,ft,-S)
QBAR
= 80 19 psf
Report Voi
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Mission Control Center Communications
Al 8:49 a.m. Eastern Standard lime (Hl+289), the Orbiter's flight
control system began steering a precise course, or drag profile,
with the initial roll command occurring about .^0 seconds later. At
8:49:38 a.m., the Mission Control Guidance and Procedures offi-
cer called the Flight Director and indicated that the ""closed-loop"
guidance system had been initiated.
The Maintenance, Mechanical, (nid Crew Systems (MMACS) of-
ficer and the Flif^ht Director f Flight ) had the followlnii exchaiific
beginning at 8:54:24 a.m. (El +6 1 J I.
MMACS: -Flight -MMACS."
Flight: -Go ahead, MMACS."
MMACS: "'FYI. I've just lost four separate temperature
transducers on the left side of the vehicle, hydraulic
return temperatures. Two of them on system one and
one in each of systems tv\o and three."
Flight: "Four hyd |hydraulic| return temps?"
MMACS: "To the left outboard and left inboard elevon."
Flight: "Okay, is there anything common to them? DSC
idiscrete signal conditioner! "^^r MDM | multiplexer-
demultiplexer] or anything? I mean, you're telling
me you lost them all at exactly the same time?"
MMACS: "No. not exactly, fhey were w ithin probably four or
five seconds of each other."
Flight: ""Okay, where are those, where is that instrumenta-
tion located?"
MMACS: ""All four of them are located in the aft jjart of the
left wing, right in front of the elevons. elevon actua-
tors. And there is no commonality."
Flight: ""No commonality."
At H:56:02 a.m. (El+713). the conversation between the Flight
Director and the MMACS officer continnes:
The Flight Director then continues to dLsctiss indications with other
Mission Control Center personnel. Induduig the Guidance, Navi-
gation, and Control officer (GNC).
Flight:
MMACS:
Flisiht:
"MMACS, tell me again which systems they're for."
'That's all three hydraulic systems. It's ... two of
them are to the left outboard elevon and two of them
to the left inboard."
"Okay, I got )ou."
Flight:
GNC:
Flight:
GNC:
Flight:
MMACS:
Flight:
MMACS:
Flight:
MMACS:
Flight:
MMACS:
Flis-hl:
""GNC -Flight."
'"Flight -GNC."
""F>erythitig look good to you, control and rates and
e\erything is nominal, right?"
"Control's been stable through the rolls that we've
done so far, flight. We have good trims. I don't see
anything (Hit of the ordinary."
"Okay. And MMACS, Flight?"
"Flight - MMACS."
""All other indications for your hydraulic system
indications are good."
■"They're all good. We've had good quantities all the
way across."
""And the other temps are normal?"
"'The other lemps are normal, yes sir."
""And v\ hen you say you lost these, are you saying
that they went to zero?" [Time: 8:57:59 a.m., EI-^830i
""Or, off-scale low?"
"All four of them are off-scale low. And they were
all staggered. They were, like I said, within several
seconds of each other."
"Okay."
At (S';.5,S'.-CW a.m. (FI-i-iS.< 1 1. Columbia crossed the New Me.xlco-
Te.ms state line. Within the ininiile. a broken call came on the
air-to-ground voice loop from Columbia !v commander. "And. uh,
Hon ..." This was followed by a call from MMAC S about failed tire
pressure sensors at 8:59:15 a.m. (EI+906).
MMACS: "Flight -MMACS."
Flight: ""Go."
MMACS: ""We just lost tire pressure on the left outboard and left
inboard, both tires."
/continued on ne.xt page]
Report VOLur
1ST z O O 3
COLUMBIA
ACCIDENT INVESTIGATION SDARD
The Flight Director then told the Capsule Coinniiiiiicator (CAP-
COM) to let the crew know that Mission Control saw the messai;es
and that the Flii^ht Control Team was evaliiatini^ the indications
and did not copy their last transmission.
CAPCOM: "And Columbia. Houston, we see your tire pressure
messages and we did not copy your last call."
Flight: "Is it instrumentation, MMACS? Gotta be ...""
MMACS: "Flight - MMACS, those are also oft-scale low."
At 8:59:32 a.m. (EI+92J), Columbia was approachinii Dallas.
Te.xas. at 200.700 feet and Macli 18.1. At the same time, another
broken call, the final call from Columbia',? commander, came on
the air-to-ground voice loop:
Commander; "Roger, |cut off in mid-\\ord| ..."
This call may have been about the backup fHf-ht system tire pres-
sure fault-summary mes.tafies annunciated to the crew onboard.
and .'ieen in the telemetry by Mission Control personiwl. An ex-
tended loss of signal began at 08:59:32.136 a.m. (EI+9231. This
was the last valid data accepted by the Mission Control computer
stream, and no further real-time data updates occurred in Mis-
sion Control. This coincided with the appro.ximate time when the
Flight Control Team would e.xpect a short-duration loss of signal
during antenna switching, as the onboard communicatiim system
automatically reconfigured from the west Tracking atul Data
Relay System satellite to either the east satellite or to the ground
station at Kennedy Space Center The following exchange then
took place on the Flight Director loop with the Instrumentation
and Communication Office {INCO):
INCO: "Flight -INCO."
Flight: "Go."
INCO: "Just taking a few hits here. We're right up on top of
the tail. Not too bad."
The Flight Director then resumes discussion with the MMACS
officer at 9:00:18 a.m. (£1+969).
Flight:
MMACS:
Flight:
MMACS:
Flight:
MMACS:
"MMACS - Flight."
"Flight -MMACS."
"And there's no commonality between all these tire
pressure instrumentations and the hydraulic return
instmmentations."
"No sir, there's not. We"\e also lost the nose gear
down talkback and the right main gear down talk-
back."
"Nose gear and right main gear down talkbacks'.'"
"Yes sir."
At 9:00:18 a.m. (El +969). the postflight video and imagery anal-
yses indicate that a catastrophic event occurred. Bright flashes
suddenly enveloped the Orhiter. followed by a dramatic change in
the trail of superheated air This is considered the most likely lime
of the main breakup <■>/' Columbia. Because the loss of signal had
occurred 46 seconds earlier Mission Control had no insight into
this event. Mission Control continued to work the loss-of- signal
problem to regain conmumication with Columbia.'
INCO: "Flight - INCO. I didn't expect, uh, this bad of a hit
on comm |communications|."
Flight: "GC j Ground Control officer] how far are we from
IIHF'.' Is that two-minute clock good?"
GC: "Afhrmative, Flight."
GNC: "Flight -GNC."
Flight: "Go."
GNC:
Flisjht:
"if we have any rea.son to suspect any sort o
controllability issue, I would keep the control cards
handy on page 4-dash-l.^."
"Copy."
At 9:02:21 a.m. (EI+1092, or 18 minutes-plus), the Mission
Control Center commentator reported, "Fourteen minutes to
touchdown for Columbia at the Kennedy Space Center. Flight
controllers are continuing to stand by to regain communications
with the spacecraft. "
Flight: "INCO, we were rolled left last data we had and you
were expecting a little bit of ratty comm jcommuni-
cations|, but not this long?"
INCO: "That's correct. Flight. 1 expected it to be a little
intermittent. And this is pretty solid right here."
Flight: "No onboard system config [configuration] changes
right before we lost data?"
INCO: "That is correct. Flight. All looked good."
Flight: "Still on string two and everything looked good?"
INCO: "String two looking good."
The Ground Control officer then told the Flight Director that
the Orbiter was within two rniiuites of acquiring the Kennedy
Space Center ground .station for communications, "Two minutes
to MILA. " The Flight Director told the CAPCOM to fry another
communications check with Columbia, including one on the UHF
system (via MILA, the Kennedy Space Center tracking station):
CAPCOM: "Columbia. Houston, comm Icuniniunications]
check."
CAPCOM: "Columbia. Houston, IIHF comm ]communicalions]
check."
At 9:03:45 a.m. (El+1176, or 19 minutes-plus), the Mission Con-
trol Center conunentator reported, "CAPCOM Charlie Hobaugh
calling ColiHiibia on a UHF frequency as it approaches the Mer-
ritt Island (MILA) tracking station in Florida. Twelve-and-a-half
minutes to touchdown, accinxling to clocks in Mission Control."
MMACS:
Flight:
MMACS:
Flight:
"Flight -MMACS."
"MMACS'.'"
"On the tire pressures, we did see them go erratic for
a little bit before they went away, so I do believe it's
instrumentation."
"Okay."
The Flight dmtrol Team still luul no indications of any serious
problems onboard the Orbiter In Mission Control, there was no
way to know the exact cause of the fidled sensor measurements,
and while there was concern for the e.xtended loss of signal, the
recourse was to continue to try to regain communications and in
the meantime determine if the other .systems, based on the last
valid data, continued to appear as expected. The Flight Director
told the CAPCOM to continue to try to raise Columbia via UHF:
CAPCOM: "Columbia. Houston, UHF comm Icomnuinications]
check."
CAPCOM: "Columbia. Houston, UHF comm Icommunications)
check."
GC: "Flight -GC."
Flight: "Go."
GC: "MILA not reporting any RF (radio frequency] at
this time."
[continued on next page/
Report vouur
iT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
INCO:
Hight:
Flishl:
FDO;
GC:
Flight:
CAPCOM
INCO:
Flight:
INCO:
Flight:
INCO:
"Flight - INCO, SPC [stored program command]
just should have taken us to S TDN low." [STDN is
the Space Trackin,!' and Data Network, or i^roiiiid
station comwnnication mode I
"Okay."
"FDO. when are you expecting tracking? " [FDO
is the Flii^ht Dynamics Officer in the Mission
Control Center/
"One minute ago. Flight."
"And Flight - (iC, no C-band yet."
"Copy."
"Colinnhia. Houston, UHFcomm (communica-
lionsl check."
"Flight -INCO."
"Gor
"I could swap strings in the blind."
"Okay, command us over." !^^
"In work. Flight."
At 0Q:08:25 a.m. (EI+ 1456. or 24 miiuites-pltiM ilie Instrumen-
tation and Coininnnications Officer reported. "l-'lii>ht - INCO.
I've commanded string one in the blind. " which indicated that
the officer had executed a coninnnid sei/iience lo Columbia tf>
force the onhc/ard S-inind coninunucaiion\ sxsiciu to the backup
strinfi of avionics to try to retrain conininnication. per the Fli,i;lil
Director 's direction in the previous call.
GC: "And Flight -GC."
Flight: "Go."
GC: "IVllLA's taking one of their antennas off into a
search mode [to try to lind Columbia]."
Flight: "Copy. FDO - Flight?"
FDO: "Go ahead. Flight."
Flight: "Did we get, ha\c \\c gotten any tracking data?"
FDO: "We got a blip nf iiackmg data, il was a ixul data
point. Flight. We do not belies e that was the
Orbiter j referring to an errant blip on the larife
front screen in the Mission Control, where Orhiter
' tracking data is displnycd./ We're entering a
search pattern v\ itli our C bands at this time. We
do not have any valid data at this time."
By this time. 9:(W:29 a.m. (F/+I520). Coliimbia'.f .speed would
have dropped lo Mach 2.5 for a standard approach to the Ken-
nedy .Space Center
Flight:
FDO:
"OK. Any other trackers that we can go to?"
"Let me start talking. Flight, to my navigator."
At 9:12:39 a.tn. (E+ 1710. or 2H minutes-plus I. Col umbia should
have been hanking on the heading aligmnent cone to line up on
Runway 33. At about this time, a nwmher of the Mission Con-
trol team received a call on his cell phone from someone who
had just seen live television coverage «/ Columbia breaking
up during re-entry. The Mission Control team member walked
to the Flight Director's console and told him the Orhiter had
disintegrated.
Flight:
GC:
Flight:
"GC, - Flight. GC
"Flight -GC."
"Lock the doors."
Flight?
Having confirmed the loss f.;/' Columbia, the Entry Flight Di-
rector directed the Flight Control Team to begin contingency
procedures.
In order to preserve all material relating to STS-107 as
evidence for the accident investigation, NASA officials im-
pounded data, software, hardware, and facilities at NASA
and contractor sites in accordance with the pre-existing
mishap response plan.
At the .Johnson Space Center, the door to Mission Control
was locked while personnel at the flight control consoles
archived all original mission data. At the Kennedy Space
Center, mission facilities and related hardware, including
Lainich Complex 39-A, were put under guard or stored in
secure warehouses. Officials took similar actions at other
key Shuttle facilities, including the Marshall Space Flight
Center and the Michoud Assembly Facility.
Within minutes of the accident, the NASA Mishap Inves-
tigation Team was activated to coordinate debris recovery
effoils with local, state, and federal agencies. The team ini-
tially operated out of Barksdale Air Force Base in Louisiana
and .soon after in Lutl<in, Texas, and Carswell Field in Fort
Worth, Texas.
Debris Search and Recovery
On the morning of February I, a crackling boom that sig-
naled the breakup of Coltiiiihkt startled residents of East
Texas. The long, low-pitched rumble heard just before
8:00 a.m. Central Standard Time (CST) was generated by
pieces of debris streaking into the upper atmosphere at
nearly 12,000 miles per hour. Within minutes, that debris
fell to the ground. Cattle stampeded in Eastern Nacogdo-
ches County. A fisherman on Toledo Bend reservoir saw
a piece splash down in the water, while a women driving
near Lufkin almost lost control of her car when debris
smacked her windshield. As 91 1 dispatchers across Texas
were flooded with calls repoiling sonic booms and smoking
debris, emergency personnel soon realized that residents
were encountering the remnants of the Orbiter that NASA
had reported missing minutes before.
The emergency response that began shortly after 8:00 a.m.
CST Saturday moniing grew into a massive effort to decon-
taminate and recover debris strewn over an area that in Texas
alone exceeded 2,000 square miles (see Figure 2.7- 1 ). Local
fire and police departments called in all personnel, who be-
gan responding to debris repoils that by late afternoon were
phoned in at a rate of 18 per minute.
Within hours of the accident. President Bush declared
Ea.st Texas a federal disaster area, enabling the dispatch
of emergency response teams from the Federal Emer-
gency Management Agency and Environmental Protection
Agency. As the day wore on, county constables, volunteers
on horseback, and local citizens headed into pine forests
and bushy thickets in search of debris and crew remains,
while National Guard units mobilized to assist local law-
enforcement guard debris sites. Researchers from Stephen
F. Austin University sent seven teams into the field with
Global Positioning System units to mark the exact location
of debris. The researchers and later searchers then used this
data to update debris distribution on detailed Geographic
Information System maps.
4 4
Report Voli
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
\—7i . ^
'-j-f-^"^'
Figure 2.7-1 . The debris field in East Texas spread over 2,000 square miles, and eventually over 700,000 acres were searched.
Public Safety Concerns
From the start. NASA officials sought to make the public
aware of the hazards posed by certain pieces of debris,
as well as the importance of turning over all debris to the
authorities. Coliiwhia carried highly toxic propellants that
maneuvered the Orbiter in space and during early stages
of re-entry. These propellants and other gases and liquids
were stored in pressurized tanks and cylinders that posed a
danger to people who might approach Orbiter debris. The
propellants, monomethyl hydrazine and nitrogen tetroxide.
as well as concentrated ammonia used in the Orbiter's cool-
ing systems, can severely burn the lungs and exposed skin
when encountered in vapor form. Other materials used in the
Orbiter. such as beryllium, are also toxic. The Orbiter also
contains various pyrotechnic devices that eject or release
items such as the Ku-Band antenna, landing gear doors, and
hatches in an emergency. These pyrotechnic devices and
their triggers, which are designed to withstand high heat
and therefore may have survived re-entry, posed a danger to
people and livestock. They had to be removed by personnel
trained in ordnance disposal.
In light of these and other hazards, NASA officials worked
with local media and law enforcement to ensure that no one
on the ground would be injured. To determine that Orbiter
debris did not threaten air quality or drinking water, the Envi-
ronmental Protection Agency activated Emergency Response
and Removal Service contractors, who surveyed the area.
Land Search
The tremendous efforts mounted by the National Guard,
Texas Department of Public Safety, and emergency per-
sonnel from local towns and communities were soon over-
whelmed by the expanding bounds of the debris field, the
densest region of which ran from just south of Fort Worth.
Texas, to Fort Polk, Louisiana. Faced with a debris field
.several orders of magnitude larger than any previous ac-
cident site, NASA and Federal Emergency Management
Agency officials activated Forest Service wildland firefight-
ers to serve as the primary search teams. As NASA identi-
fied the areas to be searched, personnel and equipment were
furnished by the Forest Service.
Within two weeks, the number of ground searchers ex-
ceeded 3,000. Within a month, more than 4.000 searchers
were flown in from around the country to base camps in
Corsicana. Palestine. Nacogdoches, and Hemphill. Texas.
These searchers, drawn from across the United States and
Puerto Rico, worked 1 2 hours per day on 1 4-, 2 1 -, or 30-day
rotations and were accompanied by Global Positioning Sys-
tem-equipped NASA and Environmental Protection Agency
personnel trained to handle and identify debris.
Report Volume I
AUQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Based on sophisticated mapping of debris trajectories galii-
ered from telemetry, radar, photographs, video, and meteoro-
logical data, as well as reports from the general public, teams
were dispatched to walk precise grids of East Texas pine
brush and thicket (see Figure 2.7-2). In lines 10 feet apart, a
distance calculated to provide a 75 percent probability of de-
tecting a si.x-inch-square object, wildland firefighters scoured
snake-infested swamps, mud-filled creek beds, and brush so
thick that one team advanced only a few hundred feet in an
entire morning. These 20-person ground teams systemati-
cally covered an area two miles to either side of the Orbiter's
ground track. Initial efforts concentrated on the search for
human remains and the debris corridor between Corsicana,
Texas, and Foil Polk. Searchers gave highest priority to a list
of some 20 "hot items" that potentially contained crucial in-
formation, including the Orbiter's General Purpose Comput-
ers, film, cameras, and the Modular Auxiliary Data System
recorder. Once the wildland firefighters entered the field,
recovery rates exceeded 1 ,000 pieces of debris per day.
Figure 2.7-2. Searching for debris was o laborious task thai used
thousands of people walking over hundreds of acres of Texas and
Louisiana.
After searchers spotted a piece of debris and determined it
was not hazardous, its location was recorded with a Global
Positioning System unit and photographed. The debris was
then tagged and taken to one of foin- collection centers at
Corsicana, Palestine, Nacogdoches, and Hemphill, Texas.
There, engineers made a preliminary identification, entered
the find into a database, and then shipped the debris to Ken-
nedy Space Center, where it was further analyzed in a han-
gar dedicated to the debris reconstruction.
Air Search
Air crews used 37 helicopters and seven fixed-wing aircraft
to augment ground searchers by searching for debris farther
out from the Orbiter's ground track, from two miles from the
centerline to five miles on either side. Initially, these crews
used advanced remote sensing technologies, including two
satellite platforms, hyper-spectral and forward-looking in-
frared scanners, forest penetration radars, and imagery from
Lockheed U-2 reconnaissance aircraft. Becau.se of the densi-
Figure 2.7-3. Tragically, a helicopter crash during the debris
search claimed the lives of Jules "Buzz" Mier (in black coat) and
Charles Krenek (yellow coat).
ty of the East Texas vegetation, the small sizes of the debris,
and the inability of sensors to differentiate Orbiter material
from other objects, these devices proved of little value. As
a result, the detection work fell to spotter teams who visu-
ally scanned the terrain. Air search coordinators apportioned
grids to allow a 50 percent probability of detection for a one-
foot-square object. Civil Air Patrol volunteers and others in
powered parachutes, a type of ultralight aircraft, also partici-
pated in the search, but were less successful than helicopter
and fixed-wing aircrews in retrieving debris. During the air
search, a Bell 407 helicopter crashed in Angelina National
Forest in San Augustine County after a mechanical failure.
The accident took the lives of Jules F. "Buzz" Mier Jr., a
contract pilot, and Charles Krenek, a Texas Forest Service
employee, and injured three others (see Figure 2.7-3).
Water Search
The United States Navy Supervisor of Salvage organized
eight dive teams to search Lake Nacogdoches and Toledo
Bend Reservoir, two bodies of water in dense debris fields.
Sonar mapping of more than 3 1 square miles of lake bottom
identified more than 3,100 targets in Toledo Bend and 326
targets in Lake Nacogdoches. Divers explored each target,
but in murky water with visibility of only a few inches,
underwater forests, and other submerged hazards, they re-
covered only one object in Toledo Bend and none in Lake
Nacogdoches. The 60 divers came from the Navy. Coast
Guard. Environmental Protection Agency. Texas Forest
Service. Texas Department of Public Safety. Houston and
Galveston police and fire departments, and Jasper County
Sheriff's Department.
Search Beyond Texas and Louisiana
As thousands of personnel combed the Orbiter's ground track
in Texas and Louisiana, other civic and community groups
searched areas farther west. Environmental organizations
and local law enforcement walked three counties of Cali-
fornia coastline where oceanographic data indicated a high
Report Volume I
IGUST 2Da3
COLUMBIA
ACCIDENT INVESTIGATION BDARO
probability of debris washing ashore. Prison inmates scoured
sections of the Nevada desert. Civil Air Patrol units and other
volunteers searched thousands of acres in New Mexico, by
air and on foot. Though these searchers failed to find any
debris, they provided a valuable service by closing out poten-
tial debris sites, including nine areas in Texas, New Mexico.
Nevada, and Utah identified by the National Transportation
Safety Board as likel> to contain debris. NASA's Mishap in-
vestigation Team addressed each of the 1 ,4?9 debris reports
it received. So eager was the general public to turn in pieces
of potential debris that NASA received reports from 37 U.S.
states that Columbia's re-entiy ground track did not cross, as
well as from Canada, Jamaica, and the Bahamas.
Property Damage
No one was injured and little property damage resulted from
the tens of thousands of pieces of falling debris (see Chap-
ter 10). A reimbursement program administered by NASA
distributed approximately $5(),00() to property owners who
made claims resulting from falling debris or collateral dam-
age from the search efforts. There were, however, a few close
calls that emphasize the importance of selecting the ground
track that re-enlering Orbiters follow. A 600-pound piece of
a main engine dug a six-foot-wide hole in the Fort Polk golf
course, while an 800-pound main engine piece, which hit the
ground at an estimated 1 ,400 miles per hour, dug an even
larger hole nearby. Disaster was narrowly averted outside
Nacogdoches when a piece of debris landed between two
highly explosive natural gas tanks set just feet apart.
Debris Amnesty
The response of the public in reporting and turning in debris
was outstanding. To reinforce the message that Orbiter de-
bris was government property as well as essential evitlence
of the accident's cause, NASA and local media officials
repeatedly urged local residents to report all debris imme-
diately. For those who might have been keeping debris as
souvenirs. NASA offered an amnesty that ran for several
days. In the end, only a handful of people were prosecuted
for theft of debris.
Final Totals
More than 25,000 people from 270 organizations t(x)k part
in debris recovery operations. All told, searchers expended
over 1.5 million hours covering more than 2.3 million acres,
an area approaching the size of Connecticut. Over 700,000
acres were searched by foot, and searchers found over X4,000
individual pieces of Orbiter debris weighing more than
84,900 pounds, representing 38 percent of the Orbiter's dry
weight. Though significant evidence from radar returns and
video recordings indicate debris shedding across California,
Nevada, and New Mexico, the most westerly piece of con-
firmed debris (at the time this report was published) was the
tile found in a field in Littleton, Texas. Heavier objects with
higher ballistic coefficients, a measure of how far objects will
travel in the air, landed toward the end of the debris trail in
western Louisiana. The most easterly debris pieces, includ-
ing the Space Shuttle Main Engine turbopumps, were found
in Fort Polk, Louisiana.
Figure 2.7-4. Recovered debris was returned fo the Kennedy
Space Center where if wos laid out in a large hangar. The tape
on the floor helped workers place each piece near where it had
been on the Orbiter.
The Federal Emergency Management Agency, which di-
rected the overall effort, expended more than $305 million
to fund the search. This cost does not include what NASA
spent on aircraft support or the wages of hundreds of civil
servants employed at the recovery area and in analysis roles
at NASA centers.
The Importance of Debris
The debris collected (see Figure 2.7-4) by searchers aided
the investigation in significant ways. Among the most
important finds was the Modular Auxiliary Data System
recorder that captured data from hundreds of sensors that
was not telemetered to Mission Control. Data from these
800 sensors, recorded on 9,400 feet of magnetic tape, pro-
vided investigators with millions of data points, including
temperature sensor readings from Coliiiiihia's left wing
leading edge. The data al.so helped fill a 30-.second gap in
telemetered data and provided an additional 14 seconds of
data after the telemetry loss of signal.
Recovered debris allowed investigators to build a three-di-
mensional reconstruction of Cohtmhia'?, left wing leading
edge, which was the basis for understanding the order in
which the left wing structure came apart, and led investiga-
tors to determine that heat first entered the wing in the loca-
tion where photo analysis indicated the foam had struck.
Report Voli
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BDARE
Endnotes for Chapter 2
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
The primary source document for this process is NSTS 08117,
Requirements and Procedures for Certification and Flight Readiness.
CAIB document CTF017-03960413.
Statement of Daniel S. Goldin, Administrator, National Aeronautics and
Space Administration, before the Subcommittee on VA-HUD-lndependent
Agencies, Committee on Appropriations, House of Representatives,
March 31, 1998. CAIB document CAB048-04000418
Roberta L. Gross, Inspector General, NASA, to Daniel S. Goldin,
Administrator, NASA, "Assessment of the Triana Mission, G-99013, Final
Report," September 10, 1999. See in particular footnote 3, concerning
Triana and the requirements of the Commercial Space Act, and Appendix
C, "Accounting for Shuttle Costs." CAIB document CAB048-02680269
Although there is more volume of liquid hydrogen in the External Tank,
liquid fiydrogen is very light and its slosh effects are minimal and are
generally ignored. At launch, the External Tank contains approximotely
1 .4 million pounds (140,000 gallons) of liquid oxygen, but only 230,000
pounds (385,000 gallons) of liquid hydrogen.
The Performance Enhancements (PE) flight profile flown by STS107 is
a combination of flight software and trajectory design changes that
were introduced in late 1997 for STS-85. These changes to the ascent
flight profile allow the Shuttle to carry some 1,600 pounds of additional
poylood on International Space Station assembly missions. Although
developed to meet the Space Station poylood lift requirement, a modified
PE profile has been used for all Shuttle missions since it was introduced.
Report Volume I
ICUST 2003
Accident Analysis
One of the central puqjoses of this investigation, like those
for other kinds of accidents, was to identify the chain of
circumstances that caused the Coliiinhia accident, [n this
case the task was particularly challenging, because the
breakup of the Orbiter occurred at hypersonic velocities and
extremely high altitudes, and the debris was scattered over
a wide area. Moreover, the initiating event preceded the ac-
cident by more than two weeks. In pursuit of the sequence t)f
the cause, investigators developed a broad array of infonna-
tion sources. Evidence was derived from film and video of
the launch, radar images of Coliinihia on orbit, and amateur
video of debris shedding during the in-flight breakup. Data
was obtained from sensors onboard the Orbiter - some of
this data was downlinked during the flight, and some came
from an on-board recorder that was recovered during the
debris search. Analysis of the debris was particularly valu-
able to the investigation. Clues were to be found not only in
the condition of the pieces, but also in their location - both
where they had been on the Orbiter and where they were
found on the ground. The investigation also included exten-
sive computer modeling, impact tests, w ind tunnel studies,
and other analytical techniques. Each of these avenues of
inquiry is described in this chapter.
Because it became evident that the key event in the chain
leading to the accident involved both the External Tank and
one of the Orbiter 's wings, the chapter includes a study of
these two structures. The understanding of the accident's
physical cau.se that emerged from this investigation is sum-
marized in the statement at the beginning of the chapter. In-
cluded in the chapter are the findings and recommendations
of the Columbia Accident investigation Board that are based
on this examination of the physical evidence.
3.1 The Physical Cause
The physical cause of the loss of Columbia and its
crew was a breach in the Thermal Protection System
on the leading edge of the left wing. The breacn was
initiated by a piece of insulating foam that separated
from the left bipod ramp of the External Tank and
struck the wing in the vicinity of the lower half of Rein-
forced Carbon-Carbon panel 8 at 81.9 seconds after
launch. During re-entry, this breach in the Thermal
Protection System allowed superheated air to pen-
etrate the leading-edge insulation and progressively
melt the aluminum structure of the left wing, resulting
in a weakening of the structure until increasing aero-
dynamic forces caused loss of control, failure of the
wing, and breakup of the Orbiter.
Figure 3.??. Columbia sitting at Launch Complex 39A. The upper
circle shows the left bipod (-Y) ramp on the forward attach poinf,
while fhe lower circle is around RCC panel 8-left.
Report voui
AUQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
3.2 The External Tank and Foam
The External Tank is the largest element of the Space Shuttle.
Because it is the common element to which the Solid Rocket
Boosters and the Orbiter are connected, it serves as the main
structural component during assembly, launch, and ascent,
it also fultills the role of the low-temperature, or cryogenic,
propellant tank for the Space Shuttle Main Engines, it holds
14.^,351 gallons of liquid oxygen at minus 297 degrees
Fahrenheit in its forward (upper) tank and .^85.265 gallons
of liquid hydrogen at minus 42.3 degrees Fahrenheit in its aft
(lower) tank.'
Figure 3 21 The major components of the External Tank
Lockheed Mailin builds the External Tank under contract to
the NASA Marshall Space Flight Center at the Michoud As-
sembly Facility in eastern New Orleans, Louisiana.
The External Tank is constructed primarily of aluminum al-
loys (mainly 2219 aluminum alloy for standard-weight and
lightweight tanks, and 2195 Aluminum-Lithium alloy for
super-lightweight tanks), with steel and titanium tittings and
attach points, and some composite materials in fairings and
access panels. The External Tank is 153.8 feet long and 27.6
feet in diameter, and comprises three major sections: the liq-
uid oxygen tank, the liquid hydrogen tank, and the intertank
area between them (see Figure 3.2- 1 ). The liquid oxygen and
liquid hydrogen tanks are welded assemblies of machined
and formed panels, barrel sections, ring frarnes, and dome
and ogive sections. The liquid oxygen tank is pressure-tested
with water, and the liquid hydrogen tank with compressed air,
before they are incorporated into the External Tank assembly.
STS-1()7 used Lightweight External Tank-93.
Bipod Romp
(+Y, Right Hand)
^
Liquid
::^: 'j^H
'1^1
Oxygen
Bipod Ramp
l)^l
(-Y, LetfHond) ^
""^"-^ -^Jm
JockPod
" Standoff
Intertank to
'"^*. f ^mhIhI^H
Cioseouts
Uquid
"''^IM^^^^^I
Hydrogen
Fit$<v,„^ ^^nl^^^^^iP
Tank Flange
^'*~-~-^ ?F% *^j
Closeout
.ft 81 ._.^aap(aHMZ
Kipod
■^HH
Struts
Figure 3.2-2. The exterior of the left bipod attachment area show-
ing the foam ramp that came off during the ascent of STS-107.
ternal Tank by two umbilical fittings at the bottom (that also
contain fluid and electrical connections) and by a "bipod" at
the top. The bipod is attached to the External Tank by fittings
at the right and left of the External Tank centerline. The bipod
fittings, which are titaniinii forgings bolted to the External
Tank, are forward (above) of the intetlank-liquid hydrogen
flange joint (see Figures 3.2-2 and 3.2-3). Each forging con-
tains a spindle that attaches to one end of a bipod strut and
rotates to compensate for External Tank shrinkage during the
loading of cryogenic propellants.
Liquid Hydrogen Tonk
lo Intertank Flange
Liquid Hydrogen Tank
Figure 3,2-3. Cutaway drawing of the bipod ramp and its associ-
ated Fittings and hardware.
The propellant tanks are connected by the intertank. a 22.5-
foot-long hollow cylinder made of eight stiffened aluininum
alloy panels bolted together along longitudinal joints. Two of
these panels, the integrally stiffened thrust panels (.so called
because they react to the Solid Rocket Booster thrust loads)
are located on the sides of the External Tank where the Solid
Rocket Boosters are mounted; they consist of single slabs of
aluminum alloy machined into panels with solid longitudinal External Tank Thermal Protection System Materials
ribs. The thrust panels are joined across the inner diameter
by the intertank truss, the major structural element of the
External Tank. During propellant loading, nitrogen is used to
purge the intertank to prevent condensation and also to pre-
vent liquid oxygen and liquid hydrogen from combining.
The External Tank is attached to the Solid Rocket Boosters
by bolts and fittings on the thrust panels and near the aft end
of the liquid hydrogen tank. The Orbiter is attached to the Ex-
The External Tank is coated with two materials that serve
as the Thermal Protection System: dense composite ablators
for dissipating heat, and low density closed-cell foams for
high insulation efficiency.- (Closed-cell materials consist
of small pores filled with air and blowing agents that are
separated by thin membranes of the foam's polymeric com-
ponent.) The External Tank Thermal Protection System is
designed to maintain an interior temperature that keeps the
Report Vdli
COLUMBIA
ACCIDENT INVESTIGATION BDARD
L02 Feedline
• BX-250 S SS-1171 with
PDL-1034closeouts
L02 Ice/Frost Ramps
• PDL 1034
Tank Fittings
• BX-250 with PDL-1034
ctoseouis
Ogive Cover Plate
• BX-250
\
L02 Tank Ogive/Barrel
Thick/thin spray
•NCF 124-124
LH2 Ice/Frost Ramps
• PDL-1034
LH2 PAL Ramps
■ BX-250
^.
LH2 Tank Fwd Dome
■ BX-250
Fwd and Aft InterTank Flange
Closeouts
• BX-250
InterTank Acreage (Machined/Vented)
•NCFI 24-124
InterTank Closeouts
■BX-250 and PDL-1034
Aft Interfaces/Cable
Trays/Covers
BX-250
BX-265 (unique for
ET-93)
LH2 Tank Dome
■ NCFI 24-57
Apex Closeout
• BX-250
Figure 3.2-4. Locations of fhe various foam systems as used on ET-93, the External Tank used for STS-W7.
oxygen and hydrogen in a liquid state, and to maintain the
temperature of external parts high enough to prevent ice and
frost from forming on the surface. Figure 3.2-4 summarizes
the foam systems used on the External Tank for STS-107.
The adhesion between spray ed-on foam insulation and the
External Tank's aluminum substrate is actually quite good,
provided that the substrate has been properly cleaned and
primed. (Poor surface preparation does not appear to have
been a problem in the past.) In addition, large areas of the
aluminum substrate are usually heated during foam appli-
cation to ensure that the foam cures properly and develops
the maximum adhesive strength. The interface between the
foam and the aluminum substrate experiences .stresses due
to differences in how much the aluminum and the foam
contract when subjected to cryogenic temperatures, and due
to the stresses on the External Tank's aluminum structure
while it serves as the backbone of the Shuttle stack. While
these stresses at the foam-aluminum interface are certainly
not trivial, they do not appear to be excessive, since very few
of the observed foam loss events indicated that the foam was
lost down to the primed aluminum substrate.
Throughout the history of the External Tank, factors unre-
lated to the insulation process have caused foam chemistry
changes (Environmental Protection Agency regulations and
material availability, for example). The most recent changes
resulted from modifications to governmental regulations of
chlorofiuorocarbons.
Most of the External Tank is insulated with three types of
spray-on foam. NCFI 24-124, a polyisocyanurate foam ap-
plied with blowing agent HCFC 141b hydrochlorofluorocar-
bon, is used on most areas of the liquid oxygen and liquid
hydrogen tanks. NCFI 24-57, another polyisocyanurate
foam applied with blowing agent HCFC 141b hydrochlo-
rofluorocarbon, is used on the lower liquid hydrogen tank
dome. BX-250, a polyurethane foam applied with CFC-li
chlorofluorocarbon. was used on domes, ramps, and areas
where the foam is applied by hand. The foam types changed
on External Tanks built after External Tank 93, which was
used on STS- 107, but these changes are beyond the scope of
this section.
Metallic sections of the External Tank that will be insulated
with foam are first coated with an epoxy primer. In some
areas, such as on the bipod hand-sculpted regions, foam is
applied directly over ablator materials. Where foam is ap-
plied over cured or dried foam, a bonding enhancer called
Conathane is first applied to aid the adhesion between the
two foam coats.
After foam is applied in the intertank region, the larger areas
of foam coverage are machined down to a thickness of about
an inch. Since controlling weight is a major concern for the
External Tank, this machining serves to reduce foam thick-
ness while still maintaining sufficient insulation.
The insulated region where the bipod struts attach to the
External Tank is structurally, geometrically, and materially
complex. Because of concerns that foam applied over the
fittings would not provide enough protection from the high
heating of exposed surfaces during ascent, the bipod fittings
are coated with ablators. B.X-250 foam is sprayed by hand
over the fittings (and ablator materials), allowed to dry, and
manually shaved into a ramp shape. The foam is visually
Report Voi
IC3UST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
inspected at the Michoud Assembly Facility and also at the
Kennedy Space Center, but no other non-destructive evalu-
ation is performed.
Since the Shuttle's inaugural flight, the shape of the bipod
ramp has changed twice. The bipod foam ramps on External
Tanks I through 13 originally had a 45-degree ramp angle.
On STS-7, foam was lost from the External Tank bipod
ramp; subsequent wind tunnel testing showed that shallower
angles were aerodynamically preferable. The ramp angle
was changed from 45 degrees to between 22 and 30 degrees
on External Tank 14 and later tanks. A slight modification
to the ramp impingement profile, implemented on External
Tank 76 and later, was the last ramp geometry change.
STS-107 Left Bipod Foam Romp Loss
A combination of factors, rather than a single factor, led to the
loss of the left bipod foam ramp during the ascent of STS- 1 07.
NASA personnel believe that testing conducted during the
investigation, including the dissection of as-built hardware
and testing of simulated defects, showed conclusively that
pre-existing defects in the foam were a major factor, and in
briefings tO'the Board, these were cited as a necessary condi-
tion for foam loss. However, analysis indicated that pre-ex-
isting defects alone were not responsible for foam loss.
The basic External Tank was designed more than 30 years
ago. The design process then was substantially different
than it is today, in the 1970s, engineers often developed par-
ticular facets of a design (structural, thermal, and .so on) one
after another and in relative isolation from other engineers
working on different facets. Today, engineers usually work
together on all aspects of a design as an integrated team.
The bipod fitting was designed first from a structural stand-
point, and the application processes for foam (to prevent ice
formation) and Super Lightweight Ablator (to protect from
high heating) were developed separately. Unfortunately, the
structurally optimum fitting design, along with the geomet-
ric complexity of its location (near the flange between the in-
tertank and the liquid hydrogen tank), posed many problems
in the application of foam and Super Lightweight Ablator
that would lead to foam-ramp defects.
Although there is no evidence that substandard methods
were used to qualify the bipod ramp design, tests made near-
ly three decades ago were rudimentary by today's standards
and capabilities. Also, testing did not follow the often-used
engineering and design philosophy of "Fly what you test and
test what you fly." Wind tunnel tests observed the aerody-
namics and strength of two geometries of foam bipod enclo-
sures (flat-faced and a 20-degree ramp), but these tests were
done on essentially solid foam blocks that were not sprayed
onto the complex bipod fitting geometry. Extensive mate-
rial property tests gauged the strength, insulating potential,
and ablative characteristics of foam and Super Lightweight
Ablator specimens.
It was - and still is - impossible to conduct a ground-based,
simultaneous, full-scale simulation of the combination
of loads, airflows, temperatures, pressures, vibration, and
acoustics the External Tank experiences during launch and
ascent. Therefore, the qualification testing did not truly re-
flect the combination of factors the bipod would experience
during flight. Engineers and designers used the best meth-
ods available at the time: test the bipod and foam under as
many severe combinations as could be simulated and then
interpolate the results. Various analyses determined stresses,
thermal gradients, air loads, and other conditions that could
not be obtained through testing.
Significant analytical advancements have been made since
the External Tank was first conceived, particularly in com-
putational fluid dynamics (see Figure 3.2-5). Computational
fluid dynamics comprises a computer-generated model that
represents a system or device and uses fluid-flow physics
and software to create predictions of flow behavior, and
stress or deformation of solid structures. However, analysis
must always be verified by test and/or flight data. The Exter-
nal Tank and the bipod ramp were not tested in the complex
flight environment, nor were fully instrumented External
Tanks ever launched to gather data for verifying analytical
tools. The accuracy of the analytical tools used to simulate
the External Tank and bipod ramp were verified only by us-
ing flight and test data from other Space Shuttle regions.
Figure 3.2-5. Compufational Fluid Dynamics was used fo under-
stand the complex flow Fields and pressure coefficienfs around
bipod sirui. The flight conditions shown here approximate those
present when the left bipod foam ramp was lost from External
Tank 93 at Mach 2.46 at a 2.08-degree angle of attack.
Further complicating this problem, foam does not have the
same properties in all directions, and there is also variability
in the foam it.self. Because it consists of small hollow cells,
it does not have the same composition at every point. This
combination of properties and composition makes foam
extremely difficult to model analytically or to characterize
physically. The great variability in its properties makes for
difficulty in predicting its response in even relatively static
conditions, much less during the launch and ascent of the
Shuttle. And too little effort went into understanding the
origins of this variability and its failure modes.
The way the foam was produced and applied, particularly
in the bipod region, also contributed to its variability. Foam
consists of two chemical components that must be mixed
in an exact ratio and is then sprayed according to strict
specifications. Foam is applied to the bipod fitting by hand
to make the foam ramp, and this process may be the primar>
source of foam variability. Board-directed dissection of
foam ramps has revealed that defects (voids, pockets, and
debris) are likely due to a lack of control of various combi-
nations of parameters in spray-by-hand applications, which
Report Von
August z aa 3
COLUMBIA
ACCIDENT INVESTIGATION BDARO
is exacerbated by the complexity of the underlying hardware
configuration. These defects often occur along "knit lines."
the boundaries between each layer that are formed by the
repeated application of thin layers - a detail of the spray-by-
hand process that contributes to foam variability, suggesting
that while foam is sprayed according to approved proce-
dures, these procedures may be questionable if the people
who devised them did not have a sufficient understanding of
the properties of the foam.
Subsurface defects can be detected only by cutting away the
foam to examine the interior. Non-destructive evaluation
techniques for determining External Tank foam strength
have not been perfected or qualified (although non-destruc-
tive testing has been used successfully on the foam on
Boeing's new Delta IV booster, a design of much simpler
geometry than the External Tank). Therefore, it has been im-
possible to determine the quality of foam bipod ramps on any
External Tank. Furthemiore. multiple defects in some cases
can combine to weaken the foam along a line or plane.
"Cryopumping" has long been theorized as one of the
processes contributing to foam loss from larger areas of
coverage. If there are cracks in the foam, and if these cracks
lead through the foam to voids at or near the surface of the
liquid oxygen and liquid hydrogen tanks, then air, chilled
by the extremely low temperatures of the cryogenic tanks,
can liquefy in the voids. After launch, as propellant levels
fall and aerodynamic heating of the exterior increases, the
temperature of the trapped air can increase, leading to boil-
ing and evaporation of the liquid, with concurrent buildup of
pressure within the foam. It was believed that the resulting
rapid increase in subsurface pressure could cause foam to
break away from the External Tank.
"Cryoingestion" follows essentially the same scenario,
except it involves gaseous nitrogen seeping out of the in-
tertank and liquefying inside a foam void or collecting in
the Super Lightweight Ablator. (The intertank is filled with
nitrogen during tanking operations to prevent condensation
and also to prevent liquid hydrogen and liquid oxygen from
combining.) Liquefying would most likely occur in the
circumferential "Y" joint, where the liquid hydrogen tank
mates with the intertank, just above the liquid hydrogen-in-
tertank flange. The bipod foam ramps straddle this complex
feature. If pooled liquid nitrogen contacts the liquid hydro-
gen tank, it can solidify, because the freezing temperature
of liquid nitrogen (minus 348 degrees Fahrenheit) is higher
than the temperature of liquid hydrogen (minus 423 degrees
Fahrenheit). As with cryopumping. cryoingested liquid or
solid nitrogen could also "flash evaporate" during launch
and ascent, causing the foam to crack off. Several paths al-
low gaseous nitrogen to escape from the intertank. including
beneath the flange, between the intertank panels, through
the rivet holes that connect stringers to intertank panels, and
through vent holes beneath the stringers that prevent over-
pressurization of the stringers.
No evidence suggests that defects or cryo-effects alone
caused the loss of the left bipod foam ramp from the
STS-107 External Tank. Indeed, NASA calculations have
suggested that during ascent, the Super Lightweight Ablator
remains just slightly above the temperature at which nitro-
gen liquefies, and that the outer wall of the hydrogen tank
near the bipod ramp does not reach the temperature at which
nitrogen boils until 130 seconds into the flight,' which is too
late to explain the only two bipod ramp foam losses whose
times during ascent are known. Recent tests at the Marshall
Space Flight Center revealed that flight conditions could
permit ingestion of nitrogen or air into subsurface foam,
but would not permit "flash evaporation" and a sufficient
subsurface pressure increase to crack the foam. When
conditions are modified to force a flash evaporation, the
failure mode in the foam is a crack that provides pressure
relief rather than explosive cracking. Therefore, the flight
environment itself must also have played a role. Aerody-
namic loads, thermal and vacuum effects, vibrations, stress
in the External Tank structure, and myriad other conditions
may have contributed to the growth of subsurface defects,
weakening the foam ramp until it could no longer withstand
flight conditions.
Conditions in ceilain combinations during ascent may also
have contributed to the loss of the foam ramp, even if in-
dividually they were well within design certification limits.
These include a wind shear, associated Solid Rocket Booster
and Space Shuttle Main Engine responses, and liquid oxy-
gen sloshing in the External Tank."" Each of these conditions,
alone, does not appear to have caused the foam loss, but
their contribution to the event in combination is unknown.
Negligence on the part of NASA. Lockheed Martin, or United
Space Alliance workers does not appear to have been a fac-
tor. There is no evidence of sabotage, either during produc-
tion or pre-launch. Although a Problem Report was written
for a small area of crushed foam near the left bipod (a condi-
tion on nearly every flight), this affected only a very small
region and does not appear to have contributed to the loss of
the ramp (see Chapter 4 for a fuller discussion). Nor does the
basic quality of the foam appear to be a concern. Many of the
basic components are continually and meticulously tested for
quality before they are applied. Finally, despite commonly
held perceptions, numerous tests show that moisture absorp-
tion and ice formation in the foam appears negligible.
Foam loss has occurred on more than SO percent of the 79
missions for which imagery is available, and foam was lost
from the left bipod ramp on nearly 10 percent of missions
where the left bipod ramp was visible following External
Tank separation. For about 30 percent of all missions, there
is no way to determine if foam was lost; these were either
night launches, or the External Tank bipod ramp areas were
not in view when the images were taken. The External Tank
was not designed to be instrumented or recovered after
separation, which deprives NASA of physical evidence that
could help pinpoint why foam separates from it.
The precise reasons why the left bipod foam ramp was lost
from the External Tank during STS- 1 07 may never be known.
The specific initiating event may likewise remain a mystery.
However, it is evident that a combination of variable and
pre-existing factors, such as insufficient testing and analysis
in the early design stages, resulted in a highly variable and
complex foam material, defects induced by an imperfect
Report Voll
iT ZOOS
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Foam Fracture Under Hydrostatic Pressure
The Board has concluded that the physical cause of the breakup of
Columbia upon re-entr>' was the result of damage to the Orbiter's
rhermal Protection System, which occurred when a large piece of
BX-250 foam insulation fell from the left (-Y) bipod assembly 81.7
seconds after launch and struck the leading edge of the left wing. As
the Hxlernal Tank is covered with insulating foam, it seemed to me
essential that we understand the mechanisms that could cause foam
to shed.
Many if not most of the systems in the three components of the
Shuttle stack (Orbiter, External Tank, and Solid Rocket Boosters) are
by themselves complex, and often operate near the limits of their per-
formance. Attempts to understand their complex behavior and failure
modes are hampered by their strong interactions with other systems
in the stack, through their shared environment. The foam of the Ther-
mal Protection System is no exception. To understand the behavior
of systems under such circumstances, one must first understand their
behavior in relatively simple limits. Using this understanding as a
guide, one is much more likely to determine the mechanisms of com-
plex behavior, such as the shedding of foam from the -Y bipod ramp,
than simply creating simulations of the complex behavior itself.
I approachcj.! this problem by trying to im;iginc the fracture mecha-
nism by which fluid pressure built up inside the foam could propagate
to the surface, Determining this process is clearly key to understand-
ing foam ejection through the heating of cryogenic fluids trapped in
voids beneath the surface of the foam, either through "cryopumping"
or "cryoingcstion." I started by imagining a fluid under hydrostatic
pressure in contact with the surface of such foam. It seemed clear
that as the pressure increased, it would cause the weakest cell wall
to burst, filling the adjacent cell with the fluid, and exerting the same
hydrostatic pressure on all the walls of that cell. What happened next
was unclear. It was possible that the next cell wall to burst would not
be one of the walls of the newly filled cell, but some other cell that
had been on the surface that was initially subjected to the fluid pres-
sure. This seemed like a rather complex process, and 1 questioned my
ability to include all the physics correctly if 1 tried to model it. In-
stead, l>chose to perform an experiment that seemed straightforward,
but which had a result 1 could not have foreseen.
1 glued a 1.25-inch-thick piece of BX-25() foam to a ().25-inch-thick
brass plate. The .Vby-3-inch plate had a 0.25-inch-diameter hole in
its center, into which a brass tube was soldered. The tube v\as filled
with a liquid dye. and the air pressure above the dye could be slowly
raised, using a battery-operated tire pump to which a pressure regu-
lator was attached until the fluid was forced through the foam to its
outer surface. Not know ing what to expect, the first lime 1 tried this
experiment with my graduate student, ,lim Baumgardner, we did
so out on the loading dock of the Stanford Physics Department. If
this process were to mimic the cryoejcction t)f foam, we expected
a violent explosion when the pressure burst through the surface. To
keep from being showered w ith dye, we put the assembly in a closed
cardboard box, and donned white lab coats.
Instead of a loud explosion, we heard nothing. We found, though, that
the pressure above the liquid began dro])ping <ince the gas pressure
reached about 4.S pounds per square inch. [Releasing the pressure and
opening the box, we found a thin crack, about a half-inch long, at the
upper surface of the foam. Curious about the path the pressure had
taken to reach the surface. 1 cut the foam off the brass plate, and made
two vertical cuts through the foam in line with the crack. When I bent
the foam in line with the crack, it separated into two sections along
the crack. The dye served as a tracer for where the fluid had traveled
in its path through the foam. This path was along a flat plane, and was
the shape of a teardrop that intersected perpendicular to the upper
surface of the foam. Since the pressure could only exert force in the
two directions peq^endicular to this fault plane, it could not possibly
result in the ejection of foam, because that would require a force per-
pendicular to the surface of the foam. I repeated this experiment with
several pieces of foam and always found the same behavior.
I was curious why the path of the pressure fault was planar, and why
it had propagated upward, nearly perpendicular to the outer surface
of the foam. For this sample, and most of the samples that NASA
had given me. the direction of growth of the foam was vertical, as
evidenced by horizontal "knit lines" that result from successive ap-
plications of the sprayed foam. The knit lines are perpendicular to
the growth direction. 1 then guessed that the growth of the pressure
fault was influenced by the foam's direction of growth. To lest this
hypothesis, I found a piece of foam for which the growth direction
was vertical near the top surface of the foam, but was at an approxi-
mately 45-degree angle to the vertical near the bottom. If my hypoth-
esis were correct, the direction of growth of the pressure fault would
follow the direction of growth of the foam, and hence would always
intersect the knit lines at 90 degrees. Indeed, this was the case.
The reason the pressure fault is planar has to do with the fact that
such a geometry can amplify the fluid pressure, creating a much
greater stress on the cell walls near the outer edges of the teardrop,
for a given hydrostatic pressure, than would exist for a spherical
pressure-filled void. A pressure fault follows the direction of foam
growth because more cell walls have their surfaces along this direc-
tion than along any other. The stiffness of the foam is highest when
you apply a force parallel to the cell walls. If you squeeze a cube of
foam in various directions, you find that the foam is stiffest along its
growth direction. By advancing along the stiff direction, the crack is
oriented so that the fluid pressure can more easily force the (nearly)
planar walls of the crack apart.
Because the pressure fault intersects perpendicular to the upper sur-
face, hydrostatic pressure will generally not lead to foam shedding.
There are, however, cases where pressure can lead to foam shedding,
but this will only occur when the fluid pressure exists over an area
whose dimensions are large compared to the thickness of the foam
above it. and roughly parallel to the outer surface. This would require
a large structural defect within the foam, such as the delamination
of the foam from its substrate or the separation of the foam at a knit
line. Such large defects are quite different from the small voids that
occur when gravity causes uncured foam to "roll over" and trap a
small bubble of air.
Experiments like this help us Luidersiand how foam shedding does
(and doesn't) occur, because they elucidate the properties of "per-
fect" foam, free from voids and other defects. Thus, this behavior
represents the true behavior of the foam, free from defects that may
or may not have been present. In addition, these exj'Hjrimcnts are fast
and cheap, since they can be carried out on relatively small pieces of
foam in simple environments. Finally, we can understand why the
observed behavior occurs from our imderstanding of the basic physi-
cal properties of the foam itself. B) contrast, if you wish to mimic
left bipod foam loss, keep in mind that such loss could have been
detected only 7 times in 72 instances. Thus, not observing foam loss
in a particular experiment will not insure that it would ne\er happen
under the same conditions at a later time. NASA is now undertaking
both kinds of experiments, but it is the simple studies that so far have
most contributed to our understanding of foam failure modes.
Douglas Osliero/J. Board Member
Report Voli
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
and variable application, and the results of that imperfect
process, as well as severe load, thermal, pressure, vibration,
acoustic, and structural launch and ascent conditions.
Findings:
F3.2-1 NASA does not fully understand the mechanisms
that cause foam loss on almost all flights from
larger areas of foam coverage and from areas that
are sculpted by hand.
F3.2-2 There are no qualified non-destnictive evaluation
techniques for the as-installed foam to determine
the characteristics of the foam before flight.
F3.2-3 Foam loss from an External Tank is unrelated to
the tank's age and to its total pre-launch expo-
sure to the elements. Therefore, the foam loss on
STS-107 is unrelated to either the age or expo-
sure of External Tank 93 before launch.
F3.2-4 The Board found no indications of negligence
in the application of the External Tank Thermal
Protection System.
F3.2-5 The Board found instances of left bipod ramp
shedding on launch that NASA was not aware of.
bringing the total known left bipod ramp shed-
ding events to 7 out of 72 missions for which im-
agery of the launch or External Tank separation
is available.
F3.2-6 Subsurface defects were found during the dissec-
tion of three bipod foam ramps, suggesting that
similar defects were likely present in the left bi-
pod ramp of External Tank 93 used on STS-107.
F3.2-7 Foam loss occurred on more than 80 percent of
the 79 missions for which imagery was available
to confirm or rule out foam loss.
F3.2-8 Thirty percent of all missions lacked sufficient
imagery to determine if foam had been lost.
F3.2-9 Analysis of numerous separate variables indi-
cated that none could be identified as the sole
initiating factor of bipod foam loss. The Board
therefore concludes that a combination of several
factors resulted in bipod foam loss.
Recommendation:
R3.2-1 Initiate an aggressive program to eliminate all
External Tank Thermal Protection System de-
bris-shedding at the source with particular em-
phasis on the region where the bipod struts attach
to the External Tank.
3.3 Wing Leading Edge
Structural Subsystem
The components of the Orbiter's wing leading edge pro-
vide the aerodynamic load bearing, structural, and thermal
control capability for areas that exceed 2. .^00 degrees
Fahrenheit. Key design requirements included flying 100
missions with minimal refurbishment, maintaining the alu-
minum wing structure at less than ?>50 degrees Fahrenheit,
withstanding a kinetic energy impact of 0.006 foot-pounds,
and the ability to withstand 1 .4 times the load ever expected
in operation.^ The requirements specifically stated that the
Reinforced Carbon-Carbon (RCC)
The basic RCC composite is a laminate of graphite-impreg-
nated rayon fabric, further impregnated with phenolic resin
and layered, one ply at a time, in a unique moid for each part,
then cured, rough-trimmed, drilled, and inspected. The part
is then packed in calcined coke and fired in a furnace to con-
vert it to carbon and is made more dense by three cycles of
fiirfuryl alcohol \acuum impregnation and firing.
To pre\ent oxidation, the outer layers of the carbon substrate
are converted into a 0.02-to-().()4-inch-thick layer of silicon
carbide in a chamber filled with argon at temperatures up
to 3.000 degrees Fahrenheit. As the silicon carbide cools,
"craze cracks" fomi because the thermal expansion rates of
the silicon carbide and the carbon substrate differ The part is
then repeated!) \acuum-impregnalcd with tctraethyl ortho-
silicate to till the pores in the substrate, and the craze cracks
are filled with a sealant.
wing leading edge would not need to withstand iinpact from
debris or ice. since these objects would not pose a threat dur-
ing the launch phase.''
Reinforced Carbon-Carbon
The development of Reinforced Carbon-Carbon (RCC) as
part of the Thermal Protection System was key to meeting
the wing leading edge design requirements. Developed by
Ling-Temco-Vought (now Lockheed Mailin Missiles and
Fire Control), RCC is used for the Orbiter nose cap, chin
panel, forward External Tank attachment point, and wing
leading edge panels and T-seals. RCC is a hard structural
inaterial, with reasonable strength across its operational
teinperature range (ininus 2.50 degrees Fahrenheit to 3,000
degrees). Its low thermal expansion coefficient minimizes
thermal shock and themioelastic stress.
Each wing leading edge consists of 22 RCC panels (see
Figure 3.3-1). nuinbered from 1 to 22 moving outward on
each wing (the nomenclature is "5-left" or ".5-right" to dif-
ferentiate, for example, the two number 5 panels). Because
the shape of the wing changes from inboard to outboard,
each panel is unique.
Figure 3.3-J. There are 22 panels of Reinforced Carbon-Carbon
on eacfi wing, numbered os shown above.
REPORT VOUl
AUGUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Wing Leading Edge Damage
The risk of micrometeoroid or debris damage to the RCC
panels has been evaluated several times. Hypervelocity im-
pact testing, using nylon, glass, and aluminum projectiles,
as well as low-velocity impact testing with ice, aluminum,
steel, and lead projectiles, resulted in the addition of a 0.03- to
0.06-inch-thick layer of Ne\tel-440 fabric between the Inco-
nel foil and Cerachrome insulation. Analysis of the design
change predicts that the Orbiter could survive re-entiT with
a quarter-inch diameter hole in the lower surfaces of RCC
panels 8 through 10 or with a one-inch hole in the rest of the
RCC panels.
RCC components have been struck by objects throughout
their operational life, but none of these components has been
completely penetrated. A sampling of 21 post-flight reports
noted 43 hypervelocity impacts, the largest being 0.2 inch.
The most signiticant low-velocity impact was to Atlantis'
panel lO-right during STS-45 in March and April 1992. The
damaged area was 1.9 inches by 1.6 inches on the exterior
surface and 0.5 inches by 0.1 inches in the interior surface.
The substrate was exposed and oxidized, and the panel was
scrapped. Analysis concluded that the damage was caused
by a strike by a man-made object, possibly during ascent.
Figures 3.3-2 and 3.3-3 show the damage to the outer and
iiiiiei' surfaces. i-especli\cl\
Figure 3.3-2. Damage on the oufer surface of RCC panel lO-righf
from Aflanfis after STS-45.
Figure 3.3-3. Damage on the inner surface of RCC panel 10-right
from Atlantis after STS-45.
Leading Edge Maintenance
Post-flight RCC component inspections for cracks, chips,
scratches, pinholes, and abnormal discoloration are primar-
ily visual, with tactile evaluations (pushing with a finger)
of some regions. Boeing personnel at the Kennedy Space
Center make minor repairs to the silicon carbide coating and
surface defects.
With the goal of a long service life, panels 6 through 1 7 are
refurbished every 18 missions, and panels 18 and 19 every
36 missions. The remaining panels have no specific refur-
bishment requirement.
At the lime of STS-107, most of the RCC panels on
Coliiinhia's left wing were original equipment, but panel
lO-left, T-seal lO-left, panel 1 1 -left, and T-seal 1 1 -left had
been replaced (along with panel 12 on the right wing). Panel
lO-left was tested to destruction after 19 flights. Minor sur-
face repairs had been made to panels 5, 7, 10, II, 12, 13, and
19 and T-seals 3, II, 12. 13, 14, and 19. Panels and T-seals
6 through 9 and 1 1 through 17 of the left wing had been
refurbished.
Reinforced Carbon-Carbon Mission Life
The rate of oxidation is the most important variable in de-
termining the mission life of RCC components. Oxidation
of the carbon substrate results when oxygen penetrates the
microscopic pores or fissures of the silicon carbide protec-
tive coating. The subsequent loss of mass due to oxidation
reduces the load the structure can carry and is the basis for
establishing a mission life limit. The oxidation rate is a func-
tion of temperature, pressure, time, and the type of heating.
Repeated exposure to the Orbiter"s normal flight environ-
ment degrades the protective coating system and accelerates
the loss of mass, which weakens components and reduces
mission life capability.
Currently, mass loss of flown RCC components cannot be
directly measured. Instead, mass loss and mission life reduc-
tion are predicted analytically using a methodology based on
mass loss rates experimentally derived in simulated re-entry
environments. This approach then uses derived re-entry
temperature-time profiles of various portions of RCC com-
ponents to estimate the actual re-entry mass loss.
For the first five missions of Coluiiihia. the RCC compo-
nents were not coated with Type A sealant, and had shorter
mission service lives than the RCC components on the
other Orbiters. {Columbia's panel 9 has the shortest mis-
sion service life of 50 flights as shown in Figure 3.3-4.) The
predicted life tor panel/T-seals 7 through 16 range from 54
to 97 flights."
Localized penetration of the protective coating on RCC
components (pinholes) were first discovered on Columbia in
1992, after STS-50, Columbia'^, 12th flight. Pinholes were
later found in all Orbiters. and their quantity and size have
increased as flights continue. Tests showed that pinholes
were caused by zinc oxide contamination from a primer
used on the launch pad.
Report Volume
August ZQOS
COLUMBIA
ACCIDENT INVESTIGATION BDARD
1
1
1
1
,
Ponel/T-Seol Assembly
Figure 3.3-4. The expected mission life for each of the wing lead-
ing edge RCC panels on Columbia. Note fhat panel 9 has fhe
shortest life expectancy.
In October 1 993, panel 1 2-right was removed from Cohimhia
after its 15th flight for destructive evaluation. Optical and
scanning electron microscope examinations of 15 pinholes
revealed that a majority occurred along craze cracks in the
thick regions of the silicon carbide layer. Pinhole glass
chemistry revealed the presence of zinc, silicon, oxygen,
and aluminum. There is no zinc in the leading edge sup-
port system, but the launch pad corrosion protection system
uses an inorganic zinc primer under a coat of paint, and this
coat of paint is not always refurbished after a launch. Rain
samples from the Rotating Support Structure at Launch
Complex 39- A in July 1994 confirmed that rain washed the
unprotected primer off the service structure and deposited it
on RCC panels while the Orbiter sat on the launch pad. At
the request of the Columbia Accident Investigation Board,
rain samples were again collected in May 2003. The zinc
Left Wing and Wing Leading Edge
The Orbiter wing leading edge structural subsystem consists of
the RCC panels, the upper and lower access panels (also called
carrier panels), and the associated attachment hardware for each
of these components.
On Columbia, t\so upper and lower A-286 stainless steel spar
attachment fittings connected each RCC panel to the aluminum
wing leading edge spar. On later Orbitcrs, each upper and lower
spar attachment fitting is a one-piece assembly.
The space between each RCC panel is covered by a gap seal,
also known as a T-seal. Each T-seal, also manufactured from
RCC. is attached to its associated RCC panel by two Inconel 718
attachment clevises. The upper and lower carrier panels, which
allow access behind each RCC panel, are attached to the spar at-
tachment fittings after the RCC panels and T-seals are installed.
The lower carrier panel prevents superheated air from entering
A Space Shuttle
* Wing Lsading Edge Structural System
ifelT^I ^r^
H|H|^^''
KCWt^fmi
\noarSmMM
Leading Edge CroM-Sadion lamrCjMiitt iVinl
C=1U2200 !=l Inconel 718 ^RCC
^LI900 ■IA-286(»eel 1=1 Aluminum
tlnconel-
Oynoflex
the RCC panel cavity. A small space between the upper carrier
panel and the RCC panel allows air pressure to equalize behind
the RCC panels during ascent and re-entry.
The mid-wing area on the left wing, behind where the breach
occurred, is supported by a series of trusses, as shown in red
in the figure below. The mid-wing area is bounded in the front
and back by the Xol040 and Xol 191 cross spars, respectively.
The numerical designation of each spar comes from its location
along the Orbiter's X-axis; for example, the Xol 040 spar is
1 ,040 inches from the zero point on the X-axis. The cross spars
provide the wing's structural integrity. Three major cross spars
behind the Xol 191 spar provide the primary structural strength
for the aft portion of the w ing. The inboard portion of the mid-
wing is the outer wall of the left wheel-well, and the outboard
portion of the mid-wing is the wing leading edge spar, where the
RCC panels attach.
Xoll91
Xol 040
Tlie Wing Leading Edge Structural System on Columbia.
The major infernal support structures in the mid-wing ire con-
structed from aluminum alloy. Since aluminum melts at 1,200
degrees Fahrenheit, it is likely these truss tubes in the mid-wing
were destroyed and wing structural integrity was lost.
Report volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
fallout rate was generally less than previously recorded
except for one location, which had the highest rate of zinc
fallout of all the samples from both evaluations. Chemical
analysis of the most recent rainwater samples determined
the percentage of zinc to be consistently around nine per-
cent, with that one exception.
Specimens with pinholes were fabricated from RCC panel
12-right and arc -jet-tested, but the arc-jet testing did not
substantially change the pinhole dimensions or substrate
oxidation. (Arc jet testing is done in a wind tunnel with an
electrical arc that provides an airflow of up to 2,800 degrees
Fahrenheit.) As a result of the pinhole investigation, the
sealant refurbishment process was revised to include clean-
ing the part in a vacuum at 2,000 degrees Fahrenheit to bake
out contaminants like zinc oxide and salt, and forcing seal-
ant into pinholes.
Post-flight analysis of RCC components confirms that seal-
ant is ablated during each mission, which increases subsur-
face oxidation and reduces component strength and mission
life. Based on the destructive evaluation of Colitnihia'^i pan-
el 12-right and various arc -jet tests, refurbishment intervals
were established to achieve the desired service life.
In November 2001, white residue was discovered on about
half the RCC panels on Coliimhici, Atlantis, and Emleavoiir.
Investigations revealed that the deposits were sodium car-
bonate that resulted from the exposure of sealant to rain-
water, with three possible outcomes: ( i ) the deposits are
washed off, which decreases sealant effectiveness; (2) the
deposits remain on the part's surface, melt on re-entry, and
combine with the glass, restoring the sealant composition;
or (3) the deposits remain on the part's surface, melt on re-
entry, and flow onto metal parts.
The root cause of the white deposits on the surface of RCC
parts was the breakdown of the sealant. This does not dam-
age RCC material.
Non-Destructive Evaluations of Reinforced Carbon-
Carbon Components
Over the 20 years of Space Shuttle operations, RCC has
performed extremely well in the harsh environment it is
exposed to during a mission. Within the last several years,
a few instances of damage to RCC material have resulted
in a re-examination of the current visual inspection process.
Concerns about potential oxidation between the silicon
carbide layer and the substrate and within the substrate has
resulted in further efforts to develop improved Non-Destruc-
tive Evaluation methods and a better understanding of sub-
surface oxidation.
Since 1997, inspections have revealed five instances of
RCC silicon carbide layer loss with exposed substrate. In
November 1997, Columbia returned from STS-87 with three
damaged RCC parts with carbon substrate exposed. Panel
19-right had a 0.04 inch-diameter by 0.035 inch-deep circu-
lar dimple, panel 17-righl had a 0.1 inch-wide by 0.2 inch-
long by 0.025-inch-deep dimple, and the Orbiter forward
External Tank attachment point had a 0.2-inch by 0.15-inch
by 0.026-inch-deep dimple. In January 2000, after STS- 103,
Discovery'^, panel 8-left was scrapped because of similar
damage (see Figure 3.3-5).
In April 2001 , after STS- 102, Columbian panel 10-Ieft had a
0. 2-inch by 0.3-inch wide by 0.018-inch-deep dimple in the
panel corner next to the T-seal. The dimple was repaired and
the panel flew one more mission, then was scrapped because
of damage found in the repair.
Figure 3.3-5. RCC panel 8-left from Discovery had to be scrapped
after STS-103 because of the damage shown here.
Findings:
F3.3-I The original design specifications required the
RCC components to have essentially no impact
resistance.
F3.3-2 Current inspection techniques are not adequate
to assess structural integrity of the RCC compo-
nents.
F3.3-3 After manufacturer's acceptance non-destructive
evaluation, only periodic visual and touch tests
are conducted.
F3.3-4 RCC components are weakened by mass loss
caused by oxidation within the substrate, which
accumulates with age. The extent of oxidation is
not directly measurable, and the resulting mission
life reduction is developed analytically.
F3.3-5 To date, only two flown RCC panels, having
achieved 15 and 19 missions, have been destruc-
tively tested to detennine actual loss of strength
due to oxidation.
F3.3-6 Contamination from zinc leaching from a primer
under the paint topcoat on the launch pad struc-
ture increases the opportunities for localized oxi-
dation.
Report V □ c u m e I
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Recommendations:
R3.3-
R3.3-2
R3.3-3
R3.3-4
R3.3-5
Develop and implement a comprehensive in-
spection plan to determine the structural integ-
rity of all Reinforced Carbon-Carbon system
components. This inspection plan should take
advantage of advanced non-destructive inspec-
tion technology.
Initiate a program designed to increase the
Orbiter's ability to sustain minor debris damage
by measures such as improved impact-resistant
Reinforced Carbon-Carbon and acreage tiles.
This program should determine the actual impact
resistance of cuirent materials and the effect of
likely debris strikes.
To the extent possible, increase the Orbiter's abil-
ity to successfully re-enter the Earth's atmosphere
with minor leading edge structural sub-system
damage.
In order to understand the true material character-
istics of Reinforced Carbon-Carbon components,
develop a comprehensiv e database of flown Rein-
forced Carbon-Carbon material characteristics by
destructive testing and evaluation.
Improve the maintenance of launch pad struc-
tures to minimize the leaching of zinc primer
onto Reinforced Carbon-Carbon components.
3.4 Image and Transport Analyses
At 81.9 seconds after launch of STS-1()7, a sizable piece of
foam struck the leading edge o\' Coliinihia's left wing. Visual
evidence established the source of the foam as the left bipod
ramp area of the External Tank. The widely accepted im-
plausibility of foam causing significant damage to the wing
leading edge sy.stem led the Board to conduct independent
tests to characterize the impact. While it was impossible to
determine the precise impact parameters because of uncer-
tainties about the foam's density, dimensions, shape, and
initial velocity, intensive work by the Board, NASA, and
contractors provided credible ranges for these elements. The
Figure 3.4-? (color enhanced and "de-blurred" by Lockheed Mar-
tin Gaithersburg) and Figure 3.4-2 (processed by the National
Imagery and Mapping Agency) are samples of the type of visual
data used to establish the time of the impact (87.9 seconds), the
altitude at which it occurred (65,860 feefj, and the object's rela-
tive velocity at impact (about 545 mph relative to the Orbiter).
Board used a combination of tests and analyses to conclude
that the foam strike observed during the flight of STS-107
was the direct, physical cause of the accident.
Image Analysis: Establishing Size, Velocity, Origin,
and Impact Area
The investigation image analysis team included members
from Johnson Space Center Image Analysis. Johnson Space
Center Engineering. Kennedy Space Center Photo Analysis,
Marshall Space Flight Center Photo Analysis, Lockheed
Martin Management and Data Systems, the National Im-
agery and Mapping Agency. Boeing Systems Integration,
and Langley Research Center. Each member of the image
analysis team performed independent analyses using tools
and methods of their own choosing. Representatives of the
Board participated regularly in the meetings and delibera-
tions of the image analysis team.
A 35-mm film camera, E212. which recorded the foam
strike from 17 miles away, and video camera E208. which
recorded it from 26 miles away, provided the best of the
available evidence. Analysis of this visual evidence (see
Figures 3.4-1 and 3.4-2) along with computer-aided design
analysis, refined the potential impact area to less than 20
square feet in RCC panels 6 through 9 (see Figure 3.4-3),
including a portion of the corresponding carrier panels and
adjacent tiles. The investigation image analysis team found
no conclusive visual evidence of post-impact debris flowing
over the top of the wing.
Figure 3.4-3: The best estimate of the site of impact by the center
of the foam.
The image analysis team established impact velocities from
625 to 840 feet per second (about 400 to 600 mph) relative to
the Orbiter. and foam dimensions from 2! to 27 inches long
by 1 2 to 1 8 inches wide." The wide range for these measure-
ments is due primarily to the cameras' relatively slow frame
rate and poor resolution. For example, a 20-inch change in
the position of the foam near the impact point world change
the estimated relative impact speed from 675 feet per second
to 825 feet per second. The visual evidence could not reveal
the foam's shape, but the team was able to describe it as flat
and relatively thin. The mass and hence the volume of the
Report volui
(OUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
foam was determined from the velocity estimates and their
ballistic coefficients.
Image analysis determined that the foam was moving almost
parallel to the Orbiter's fuselage at impact, with about a
five-degree angle upward toward the bottom of the wing and
slight motion in the outboard direction. If the foam had hit
the tiles adjacent to the leading edge, the angle of incidence
would have been about five degrees (the angle of incidence
is the angle between the relative velocity of the projectile and
the plane of the impacted surface). Because the wing leading
edge curves, the angle of incidence increases as the point of
impact approaches the apex of an RCC panel. Image and
transport analyses estimated that for impact on RCC panel
8, the angle of incidence was between 10 and 20 degrees
(see Figure 3.4-4).'' Because the total force delivered by the
impact depends on the angle of incidence, a foam strike near
the apex of an RCC panel could have delivered about twice
the force as an impact close to the base of the panel.
Despite the uncertainties and potential errors in the data, the
Board concurred with conclusions made unanimously by the
post-flight image analysis team and concludes the informa-
tion available about the foam impact during the mission was
adequate to determine its effect on both the thermal tiles and
RCC. Those conclusions made during the mission follow:
• The bipod ramp was the source of the foam.
• Multiple pieces of foam were generated, but there was
no evidence of more than one strike to the Orbiter.
• The center of the foam struck the leading edge structural
subsystem of the left wing between panels 6 to 9. The
potential impact location included the corresponding
carrier panels, T-seals, and adjacent tiles. (Based on fur-
ther image analysis performed by the National Imagei^
and Mapping Agency, the transport analysis that fol-
lows, and forensic evidence, the Board concluded that a
smaller estimated impact area in the immediate vicinity
of panel 8 was credible.)
• Estimates of the impact location and velocities rely on
timing of camera images and foam position measure-
ments.
• The relative velocity of the foam at impact was 625 to
840 feet per second. (The Board agreed on a narrower
speed range based on a transport analysis that follows.)
• The trajectoi7 of the foam at impact was essentially
parallel to the Orbiter's fuselage.
• The foam was making about 18 revolutions per second
as it fell.
• The orientation at impact could not be determined.
• The foam that struck the wing was 24 (plus or minus 3)
inches by 15 (plus or minus 3) inches. The foam shape
could only be described as flat. (A subsequent transport
analysis estimated a thickness.)
• Ice was not present on the external surface of the bipod
ramp during the last Ice Team camera scan prior to
launch (at approximately T-5 minutes).
• There was no visual evidence of the presence of other
materials inside the bipod ramp.
. • The foam impact generated a cloud of pulverized debris
with very little component of velocity away from the
Possible
Foam '
trajectory
Possible
Foam -
trajectory
angle of incidence
Figure 3.4-4. This drawing shows fhe curve of the wing leading
edge and illustrates the difference the angle of incidence has on
the effect of the foam strike.
• In addition, the visual evidence showed two sizable,
traceable post-strike debris pieces with a significant
component of velocity away from the wing.
Although the investigation image analysis team found no
evidence of post-strike debris going over the top of the
wing before or after impact, a colorimetric analysis by
the National Imagery and Mapping Agency indicated the
potential presence of debris material over the top of the left
wing immediately following the foam strike. This analysis
suggests that some of the foam may have struck closer to the
apex of the wing than what occurred during the impact tests
described below.
Imaging Issues
The image analysis was hampered by the lack of high reso-
lution and high speed ground-based cameras. The existing
camera locations are a legacy of earlier NASA programs,
and are not optimum for the high-inclination Space Shuttle
missions to the International Space Station and oftentimes
The Orbiter "Ran Into" the Foam ^ ^
"How could a lightweight piece of foam travel so fast and hit
the wing at 545 miles per hour?""
Just prior to separating from the External Tank, the foam was
traveling with the Shuttle stack at about I.56S mph (2,.^00
feet per second). Visual evidence shows that the foam de-
bris impacted the wing approximately 0.161 seconds after
separating from the External Tank. In that lime, the velocity
of the foam debris slowed from 1,568 mph to about 1,022
mph (1,500 feet per second). Therefore, the Orbiter hit the
foam with a relative velocity of about 545 mph (800 feet per
second). In essence, the foam debris slowed down and the
Orbiter did not, so the Orbiter ran into the foam. The foam
slowed down rapidly because such low-density objects have
low ballistic coefficients, which means their speed rapidly
decreases when they lose their means of propulsion.
( T Volume I
COLUMBIA
ACCIDENT INVESTIGATION BDARD
Minimum
Impact Speed
(mph)
Maximum
Impact
Speed (mph)
Best Estimated
Impact Speed
(mph)
Minimum
Volume
(cubic inches)
Maximum
Volume
(cubic inches)
Best Estimated
Volume
(cubic inches)
During STS-107
375
654
All
400
1,920
1,200
After STS- 107
528
559
528
1,026
1,239
1,200
Figure 3.4-5. The best estimates of velocities and volumes calculated during the mission and after the accident based on visual evidence and
computer analyses. Information available during the miss/on was adequate to determine the foam's effect on both thermal tiles and RCC.
cameras are not operating or. as in the case of STS-107, out
of focus. Launch Commit Criteria should include that suf-
ficient cameras are operating to track the Shuttle from liftoff
to Solid Rocket Booster separation.
Similarly, a developmental vehicle like the Shuttle should be
equipped w ith high resolution cameras that monitor potential
hazard areas. The wing leading edge system, the area around
the landing gear doors, and other critical Themial Protection
System eleinents need to be imaged to check for damage.
Debris sources, such as the External Tank, also need to be
monitored. Such critical images need to be downlinked so
that potential problems are identified as soon as possible.
Transport Analysis: Establishing Foam Path
by Computational Fluid Dynamics
Transport analysis is the process of determining the path of
the foam. To refine the Board's understanding of the foam
strike, a transport analysis team, consisting of members
from Johnson Space Center, Ames Research Center, and
Boeing, augmented the image analysis team's research.
A variety of computer models were used to estimate the vol-
ume of the foam, as well as to refine the estimates of its ve-
locity, its other dimensions, and the impact location. Figure
3.4-5 lists the velocity and foam size estimates produced dur-
ing the mission and at the conclusion of the investigation.
The results listed in Figure .^.4-3 demonstrate that reason-
ably accurate estimates of the foam size and impact velocity
were available during the mission. Despite the lack of high-
quality visual evidence, the input data available to assess the
impact damage during the mission was adequate.
The input data to the transport analysis consisted of the com-
puted airflow around the Shuttle stack when the foam was
shed, the estimated aerodynamic characteristics of the foam,
the image analysis team's trajectory estimates, and the size
and shape of the bipod ramp.
The transport analysis team screened several of the image
analysis team's location estimates, based on the feasible
aerodynamic characteristics of the foam and the laws of
physics. Optical distortions caused by the atmospheric den-
sity gradients associated with the shock waves off the Or-
biter's nose. External Tank, and Solid Rocket Boosters may
have compromised the image analysis team's three position
estimates closest to the bipod ramp. In addition, the image
analysis team's position estimates closest to the wing were
compromised by the lack of two camera views and the shock
region ahead of the wing, making triangulation impossible
and requiring extrapolation. However, the transport analysis
confinned that the image analysis team's estimates for the
central portion of the foam trajectory were well within the
computed flow field and the estimated range of aerodynamic
characteristics of the foam.
The team identified a relatively narrow range of foam im-
pact velocities and ballistic coefficients. The ballistic coef-
ficient of an object expresses the relative influence of weight
and atmospheric drag on it, and is the primary aerodynamic
characteristic of an object that does not produce lift. An
object with a large ballistic coefficient, such as a cannon
ball, has a trajectory that can be computed fairly accurately
without accounting for drag. In contrast, the foam that struck
the wing had a relatively small ballistic coefficient with a
large drag force relative to its weight, which explains why
it slowed down quickly after separating from the External
Tank. Just prior to separation, the speed of the foam was
equal to the speed of the Shuttle, about 1,568 mph (2.300
feet per second). Because of a large drag force, the foam
slowed to about 1 ,022 mph ( 1 ,500 feet per second) in about
0.2 seconds, and the Shuttle struck the foam at a relative
Figure 3.4-6. These are the results of a trajectory analysis that
used a computational fluid dynamics approach in a program
called CART-3D, a comprehensive (six-degree-of-freedom) com-
puter simulation based on the laws of physics. This analysis used
the aerodynamic and mass properties of bipod ramp foam,
coupled with the complex flow Field during ascent, to determine
the likely position and velocity histories of the foam.
Report Volume I
AuousT 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
600
0.5
1 1.5 2 2.5
Ballistic Number (psf)
Figure 3.4-7, The results of numerous possible fro/ecfories based
on various ossumed sizes, sfiopes, and densifies of ffie foam.
Either the foam had a slightly higher ballistic coefficienf and the
Orbifer struck the foam at a lower speed relative to the Orbiter,
or the foam was more compact and the wing struck the foam at a
higher speed. The "best fit" box represents the overlay of the data
from the impge analysis with the transport <inalysis computations.
This data enabled a Final selection of projectile characteristics for
impact testing.
speed of about 545 mph (800 feet per second). (See Ap-
pendix D.8.)
The undetermined and yet certainly inegular shape of the
foam introduced substantial uncertainty about its estimated
aerodynamic characteristics. Appendix D.8 contains an in-
dependent analysis conducted by the Board to confirm that
the estimated range of ballistic coefficients of the foam in
Figure 3.4-6 was credible, given the foam dimension results
from the image analyses and the expected range of the foam
density. Based on the results in Figure 3.4-7, the physical
dimensions of the bipod ramp, and the sizes and shapes
of the available barrels for the compressed-gas gun used
in the impact test program described later in this chapter,
the Board and the NASA Accident Investigation Team de-
cided that a foam projectile 19 inches by 1 1.5 inches by 5.5
inches, weighing 1 .67 pounds, and with a weight density of
2.4 pounds per cubic foot, would best represent the piece of
foam that separated from the External Tank bipod ramp and
was hit by the Orbiter's left wing. See Section 3.8 for a full
discussion of the foam impact testing.
Findings:
F3.4-1 Photographic evidence during ascent indicates
the projectile that stmck the Orbiter was the left
bipod ramp foam.
F3.4-2 The same photographic evidence, confirmed by
independent analysis, indicates the projectile
struck the underside of the leading edge of the
left wing in the vicinity of RCC panels 6 through
9 or the tiles directly behind, with a velocity of
approximately 775 feet per second.
F3.4-3 There is a requirement to obtain and downlink
on-board engineering quality imaging from the
Shuttle during launch and ascent.
F3.4-4 The current long-range camera assets on the Ken-
nedy Space Center and Eastern Range do not pro-
vide best possible engineering data during Space
Shuttle a.scents.
F3.4-5 Evaluation of STS-107 debris impact was ham-
pered by lack of high resolution, high speed cam-
eras (temporal and spatial imagery data).
F3.4-6 Despite the lack of high quality visual evidence,
the information available about the foam impact
during the mission was adequate to determine its
effect on both the thermal tiles and RCC.
Recommendations:
R3.4-1 Upgrade the imaging system to be capable of
providing a minimum of three useful views of the
Space Shuttle from liftoff to at least Solid Rocket
Booster separation, along any expected ascent
azimuth. The operational status of these assets
should be included in the Launch Commit Cri-
teria for future launches. Consider using ships or
aircraft to provide additional views of the Shuttle
during ascent.
R3.4-2 Provide a capability to obtain and downlink high-
resolution images of the External Tank after it
separates.
R3.4-3 Provide a capability to obtain and downlink high-
resolution images of the underside of the Orbiter
wing leading edge and forward section of both
wings" Thermal Protection System.
3.5 On-Orbit Debris Separation -
The "Flight Day 2" Object
Immediately after the accident. Air Force Space Command
began an in-depth review of its Space Surveillance Network
data to determine if there were any detectable anomalies
during the STS-107 mission. A review of the data resulted in
no information regarding damage to the Orbiter. However,
Air Force processing of Space Surveillance Network data
yielded 3,180 separate radar or optical observations of the
Orbiter from radar sites at Eglin, Beale, and Kirtland Air
Force Bases. Cape Cod Air Force Station, the Air Force
Space Command's Maui Space Surveillance System in
Hawaii, and the Navy Space Surveillance System. These
observations, examined after the accident, showed a small
object in orbit with Columbia. In accordance with the In-
ternational Designator system, the object was named 2003-
003B (Columbia was designated 2003-003A). The timeline
of significant events includes:
1. January 17, 2(X)3, 9:42 a.m. Eastern Standard Time:
Orbiter moves from tail-first to right-wing-first orien-
tation
2. January 17, 10:17 a.m.: Orbiter returns to tail-first
orientation
3. Januai7 17, 3:57 p.m.: First confirmed sensor track of
object 2003-003B
4. January 1 7, 4:46 p.m.: Last confirmed sensor track for
this date
Report Volume I
COLUMBIA
ACCIDENT INVESTIGATION BOARD
5. Januan' 18: Object reacquired and tracked by Cape
Cod Air Force Station PAVE PAWS
6. Januarv' 19; Object reacquired and tracked by Space
Surveillance Network
7. January 20. 8:45 - 1 1 :45 p.m.: 2003-0038 orbit de-
cays. Last track by Navy Space Surveillance System
Events around the estimated separation time of the object
were reviewed in great detail. Extensive on-board sensor
data indicates that no unusual crew activities, telemetiy
data, or accelerations in Orbiter or payload can account for
the release of an object. No external mechanical systems
were active, nor were any translational (forward, backward,
or sideways, as opposed to rotational) maneuvers attempted
in this period. However, two attitude maneuvers were made:
a 48-degree yaw maneuver to a left-wing-forward and pay-
load-bay-to-Earth attitude from 9:42 to 9:46 a.m. EST), and
On-Orbit Collision Avoidance
The Space Control Center, operated by the 2 1st Space Wing's
1st Space Control Squadron (a unit of Air Force Space Com-
mand), maintains an orbital data catalog on some 9.0()()
Earth-orbiting objects, from active satellites to space debris,
some of which may be as small as four inches. The Space
Control Center ensures that no known orbiting objects will
transit an Orbiter "safety zone'" measuring 6 miles deep by
25 miles wide and long (Figure A) during a Shuttle mission
by projecting the Orbiter"s flight path for the next 72 hours
(Figure B) and comparing it to the flight paths of all known
orbiting or re-entering objects, which generally travel at
17.500 miles per hour Whenever possible, the Orbiter moves
tail-first while on orbit to minimize the chances of orbital
debris or micrometeoroids impacting the cabin windscreen or
the Orbiter's wing leading edae.
a maneuver back to the bay-to-Earth, tail-forward attitude
from 10:17 to 10:21 a.m. It is possible that this maneuver
imparted the initial departure velocity to the object.
Although various Space Surveillance Network radars
tracked the object, the only reliable physical information
includes the object's ballistic coefficient in kilograms per
square meter and its radar cross-section in decibels per
square meter. An object's radar cross-section relates how
much radar energy the object scatters. Since radar cross-
.section depends on the object's material properties, shape,
and orientation relative to the radar, the Space Surveillance
Network could not independently estimate the object's size
or shape. By radar observation, the object's Ultra-High
Frequency (UHF) radar cross-section varied between 0.0
and minus 18.0 decibels per square meter (plus or minus
1.3 decibels), and its ballistic coefficient was known to be
0.1 kilogram per meter .squared (plus or minus 15 percent).
These two quantities were used to test and ultimately elimi-
nate various objects.
RCC Panel Fragment 2018
(From STS.107 Right Wing
panel #10)
RCC Panel Fragment 37736
(From STS.107 Right Wing
panel #10)
If an object is determined to be
within .'^6-72 hours of collid-
ing with the Orbiter. the Space
Control Center notifies NASA.
and the agency then determines
a maneuver to avoid a collision.
There were no close apprt)ach-
es to Columbia detected during
STS-107.
Figure A Orbifer Safety Zone
Figure 6. Protecting the Orbifer's flight path
Figure 3.5-]. These represenfofive RCC ocreage pieces matched
the radar cross-section of the Flight Day 2 object.
In the Advanced Compact Range at the Air Force Research
Laboratory in Dayton, Ohio, analysts tested 31 materials
from the Orbiter's exterior and payload bay. Additional
supercomputer radar cross-section predictions were made
for Reinforced Carbon-Carbon T-seals. After exhaustive
radar cross-section analysis and testing, coupled with bal-
listic analysis of the object's orbital decay, only a fragment
of RCC panel would match the UHF radar cross-section
and ballistic coefficients observed by the Space Surveil-
lance network. Such an RCC panel fragment must be ap-
proximately 140 square inches or greater in area to meet the
observed radar cross-section characteristics. Figure 3.5-1
shows RCC panel fragments from Coliimhici's right wing
that represent those meeting the observed characteristics of
object 2003-003B.'"
Note that the Southwest Research Institute foam impact test
on panel 8 (see Section 3.8) created RCC fragments that fell
into the wing cavity. These pieces are consistent in size with
the RCC panel fragments that exhibited the required physi-
cal characteristics consistent with the Flight Day 2 object.
Report VOLUt
IBUST Z003
COLUMBIA
ACCIDENT INVESTIGATION flDARD
Findings:
F3.5-1 The object seen on orbit with Colitmhiu on Flight
Day 2 through 4 matches the radar cross-section
and area-to-mass measurements of an RCC panel
fragment.
F3.5-2 Though the Board could not positively identify
the Flight Day 2 object, the U.S. Air Force ex-
clusionary test and analysis processes reduced
the potential Flight Day 2 candidates to an RCC
panel fragment.
Recommendations:
• None
3.6 De-Orbit/Re-Entry
As Columbia re-entered Earth's atmosphere, sensors in the
Orbiter relayed streams of data both to entry controllers on
the ground at .lohn.son Space Center and to the Modular
Auxiliai7 Data System recorder, which survived the breakup
of the Orbiter and was recovered by ground search teams.
This data - temperatures, pressures, and stresses - came
from sensors located throughout the Orbiter. Entry control-
lers were unaware of any problems with re-enti-y until telem-
etry data indicated errant readings. During the investigation
data from these two sources was used to make aerodynamic,
aerothermal, and mechanical reconstructions of re-entry that
showed how these stresses affected the Orbiter.
The re-entry analysis and testing focused on eight areas:
1 . Analysis of the Modular Auxiliaiy Data System re-
corder information and the pattern of wire runs and
sensor failures throughout the Orbiter.
2. Physical and chemical analysis of the recovered de-
,bris to determine where the breach in the RCC panels
likely occurred.
3. Analysis of videos and photography provided by the
general public.
4. Abnormal heating on the outside of the Orbiter body.
Sensors showed lower heating and then higher heating
than is usually seen on the left Orbital Maneuvering
System pod and the left side of the fuselage.
5. Early heating inside the wing leading edge. Initially,
heating occurred inside the left wing RCC panels be-
fore the wing leading edge spar was breached.
6. Later heating inside the left wing structure. This analy-
sis focused on the inside of the left wing after the wing
leading edge spar had been breached.
7. Early changes in aerodynamic performance. The Or-
biter began reacting to increasing left yaw and left roll,
consistent with developing drag and loss of lift on the
left wing.
8. Later changes in aerodynamic performance. Almost
6()0 seconds after Entry Inteiface, the left-rolling ten-
dency of the Orbiter changes to a right roll, indicating
an increase in lift on the left wing. The left yaw also
increased, showing increasing drag on the left wing.
For a complete compilation of all re-entry data, see the
CAIB/NAIT Working Scenario (Appendix D.7), Qualification
and Interpretation of Sensor Data from STS- 107 (Appendix
D. 19) and the Re-entry Timeline (Appendix D.9). The
extensive aerothermal calculations and wind tunnel tests
performed to investigate the observed re-entry phenomenon
are documented in NASA report NSTS-37398.
Re-Entry Environment
In the demanding environment of re-entry, the Orbiter must
withstand the high temperatures generated by its movement
through the increasingly dense atmosphere as it deceler-
ates from orbital speeds to land safely. At these velocities,
shock waves form at the nose and along the leading edges
of the wing, intersecting near RCC panel 9. The interac-
tion between these two shock waves generates extremely
high temperatures, especially around RCC panel 9. which
experiences the highest surface temperatures of all the RCC
panels. The flow behind these shock waves is at such a high
temperature that air molecules are torn apart, or "dissoci-
ated." The air immediately around the leading edge surface
can reach 1 0,000 degrees Fahrenheit; however, the boundary
layer shields the Orbiter so that the actual temperature is only
approximately 3,000 degrees Fahrenheit at the leading edge.
The RCC panels and internal insulation protect the alumi-
num wing leading edge spar. A breach in one of the leading-
edge RCC panels would expose the internal wing structure
to temperatures well above 3,000 degrees Fahrenheit.
In contrast to the aerothermal environment, the aerodynamic
environment during ColiinihUfs re-entry was relatively be-
nign, especially early in re-entry. The re-entry dynamic pres-
sure ranged from zero at Entry Interface to 80 pounds per
square foot when the Orbiter went out of control, compared
with a dynamic pressure during laimch and ascent of nearly
700 pounds per square foot. H(Hvever, the aerodynamic
forces were increasing quickly during the final minutes of
Columbia ?• flight, and played an important role in the loss
of control.
Orbiter Sensors
The Operational Flight Instrumentation monitors physical
sensors and logic signals that report the status of various
Orbiter functions. These sensor readings and signals are
telemetered via a 128 kilobit-per-second data stream to the
Mission Control Center, where engineers ascertain the real-
time health of key Orbiter systems. An extensive review of
this data has been key to understanding what happened to
STS- 107 during ascent, orbit, and re-entry.
The Modular Auxiliary Data System is a supplemental
instrumentation system that gathers Orbiter data for pro-
cessing after the mission is completed. Inputs are almost
exclusively physical sensor readings of temperatures, pres-
sures, mechanical strains, accelerations, and vibrations. The
Modular Auxiliary Data System usually records only the
mission's first and last two hours (see Figure 3.6-1 ).
The Orbiter Experiment instrumentation is an expanded
suite of sensors for the Modular Auxiliary Data System that
was installed on Columbia for engineering development
purposes. Because Columbia was the first Orbiter launched.
Report Volui
AuBusT zona
COLUMBIA
ACCIDENT INVESTIGATIQN BOARD
IF
W.^.s,.-.
^H^^^
1
■T
'
I^Bk^
^P
■ ^
V ... ' 1
Figure 3.6-?. The Modular Auxiliary Data System recorder, found
near Hemphill, Texas. While not designed to withsfand impact
damage, the recorder was in near-perfect condition when recov-
ered on March 19, 2003.
engineering teams needed a means to gather more detailed
flight data to validate their calculations of conditions the
vehicle would experience during critical flight phases. The
instrumentation remained on Cohiinhia as a legacy of the
development process, and was still providing valuable flight
data from ascent, de-orbit, and re-entry for ongoing flight
analysis and vehicle engineering. Nearly all of Columbia's
sensors were specified to have only a 10-year shelf life, and
in some cases an even shorter .service life.
At 22 years old, the majority of the Orbiter Experiment in-
strumentation had been in service twice as long as its speci-
fied service life, and in fact, many sensors were already fail-
ing. Engineers planned to stop collecting and analyzing data
once most of the sensors had failed, so failed sensors and
wiring were not repaired. For instance, of the 181 sensors in
Coh(inhici\ wings, 55 had already failed or were producing
questionable readings before STS-107 was launched.
Re-Entry Timeline
Times in the following section are noted in seconds elapsed
from the time Colimihiu crossed Entry interface (El) over
the Pacific Ocean at 8:44:09 a.m. EST. Cohiinhia ■a destruc-
tion occurred in the period from Entry interface at 400,000
feet (Ei-HOOO) to about 200,000 feet (Ei-i-970) over Texas.
The Modular Auxiliary Data System recorded the first
indications of problems at EI plus 270 seconds (Ei-H270).
Because data from this system is retained onboard, Mission
Control did not notice any troubling indications from telem-
etry data until 8:34:24 a.m. (Ei-i-613), some 10 minutes after
Entry Interface.
Left Wing Leading Edge Spar Breach
(EI+270 through EI+515)
At EI-t-270, the Modular Auxiliary Data System recorded
the first unusual condition while the Orbiter was still over
the Pacific Ocean. Four sensors, which were all either inside
Figure 3.6-2. tocafion of sensors on the back of the left wing lead-
ing edge spar (vertical aluminum structure in picture). Also shown
are the round truss tubes ond ribs that provided the structural
support for the mid-wing in this area.
or outside the wing leading edge spar near Reinforced Car-
bon-Carbon (RCC) panel 9-left, helped tell the story of what
happened on the left wing of the Orbiter early in the re-entry.
These four sensors were: strain gauge VI2G992IA (Sensor
I ), resistance temperature detector V09T99I0A on the RCC
clevis between panel 9 and 10 (Sensor 2), thermocouple
V07T9666A, within a Thermal Protection System tile (Sen-
sor 3), and resistance temperature detector V09T9895A
(Sensor 4), located on the back side of the wing leading edge
spar behind RCC panels 8 and 9 (see Figure 3.6-2).
V12G9921A - Left Wing Leading Edge Spor Strain Gouge
-250
"5 .500
■750
• 1000
0
.14:09
First off nominal indicofion
100 200 300 400 500 600
Time (seconds from El)
700 800 900 1000
59:09
Figure 3.6-3. The strain gauge (Sensor 1) on the back of the left
wing leading edge spar was the First sensor fo show on anomalous
reading. In this chart, and the others that follow, the red line indi-
cates data from STS-T07. Data from other Columbia re-enfries, simi-
lar to the STS-107 re-entry profile, are shown in the other colors.
Report VOLUt
IT 2 Q O 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
V07T9910A - Left Wing Leading Edge Spar Temperature
fyl F^
STS- 107
STS • 073
STS 090
STS 109
T
Rrst off nominal indication
Time (seconds from El)
800 900 1000
5909
Figure 3.6-4. This temperature thermocouple (Sensor 2} was
mounted on the outside of the wing leading edge spar behind the
insulation that protects the spar from radiated heat from the RCC
panels. It clearly showed an off-nominal trend early in the re-entry
sequence and begon to show an increase in temperature much
earlier than the temperature sensor behind the spar.
Sensor I provided the first anomalous reading (see Figure
3.6-3). From El+270 to EI-i-360, the strain is higher than that
on previous Coliinihia flights. At El+450, the strain reverses,
and then peaks again in a negative direction at EI+475. The
strain then drops slightly, and remains constant and negative
until EI+495, when the sensor pattern becomes unreliable,
probably due to a propagating soft short, or "bum-through"
of the insulation between cable conductors caused by heating
or combustion. This strain likely indicates significant damage
to the aluminum honeycomb spar. In particular, strain rever-
sals, which are unusual, likely mean there was significant
high-temperature damage to the spar during this time.
At EI-t-290, 20 seconds after Sensor 1 gave its first anoma-
lous reading. Sensor 2, the only sensor in the front of the
70
Clevis Temperatures
10" Hole with Sneak Flow
60
£ 50
/
1 40
S 30
^
J'\
/
20
10
iri-A-
.^4, f\ — TXn^
1 1
D 50 100
150 200 250 300 350
Time (seconds from El)
400 450 500
Figure 3.6-5. The analysis of the effect of a W-inch hole in RCC
panel 8 on Sensor 2 from El to EI+500 seconds. The jagged line
shows the actual flight data readings and the smooth line the
calculated result for a 10-inch hole with some sneak flow of super-
heated air behind the spar insulation.
left wing leading edge spar, recorded the beginning of a
gradual and abnormal rise in temperature from an expected
30 degrees Fahrenheit to 65 degrees at El+493, when it then
dropped to "off-scale low," a reading that drops off the scale
at the low end of the sensor's range (see Figure 3.6-4). Sen-
sor 2, one of the first to fail, did so abruptly. It had indicated
only a mild warming of the RCC attachment clevis before
the signal was lost.
A series of thermal analyses were performed for different
sized holes in RCC panel 8 to compute the time required to
heat Sensor 2 to the temperature recorded by the Modular
Auxiliary Data System. To heat the clevis, various insula-
tors would have to be bypassed with a small amount of
leakage, or "sneak flow." Figure 3.6-.*^ shows the results of
these calculations for, as an example, a 10-inch hole, and
demonstrates that with sneak flow around the insulation, the
temperature profile of the clevis sensor was closely matched
by the engineering calculations. This is consistent with the
same sneak flow required to match a similar but abnormal
a.scent temperature rise of the same sensor, which further
supports the premise that the breach in the leading edge of
the wing occurred during ascent. While the exact size of the
breach will never be known, and may have been smaller or
larger than 10 inches, these analyses do provide a plausible
explanation for the observed rises in temperature sensor data
during re-entry.
Investigators initially theorized that the foam might have
broken a T-seal and allowed superheated air to enter the
wing between the RCC panels. However, the amount of
T-seal debris from this area and subsequent aerothermal
analysis showing this type of breach did not match the ob-
served damage to the wing, led investigators to eliminate a
missing T-seal as the source of the breach.
Although abnonnal, the re-entry temperature rise was slow
and small compared to what would be expected if Sensor 2
were exposed to a blast of superheated air from an assumed
breach in the RCC panels. The slow temperature rise is at-
V07T9666A - Left Wing Lower Surface Temperature
^00 500 400
Time (seconds from El)
Figure 3.6-6. As early as EI+370, Sensor 3 began reading sig-
nificantly higher than on previous flights. Since this sensor was
located in a thermal tile on ffie lower surface of the left wing, its
temperatures are much higher than those for the other sensors.
Repcjut Volui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
tributed to the presence of a relatively modest breach in the
RCC, the thick insulation that surrounds the sensor, and the
distance from the site of the breach in RCC panel 8 to the
clevis sensor.
The readings of Sensor 3. which was in a thermal tile,
began rising abnormally high and somewhat erratically as
early as EI+370, with several brief spikes to 2,500 degrees
Fahrenheit, significantly higher than the 2.000-degree peak
temperature on a normal re-entry (Figure 3.6-6). At EI-i-496,
this reading became unreliable, indicating a failure of the
wire or the sensor. Because this thermocouple was on the
wing lower surface, directly behind the junction of RCC
panel 9 and 10, the high temperatures it initially recorded
were almost certainly a result of air jetting through the dam-
aged area of RCC panel 8, or of the normal airflow being
disturbed by the damage. Note that Sensor 3 provided an
external temperature measurement, while Sensors 2 and 4
provided internal temperature measurements.
Sensor 4 also recorded a rise in temperature that ended in an
abrupt fall to off-scale low. Figure 3.6-7 shows that an ab-
normal temperature rise began at EI-(-425 and abruptly fell at
EI-(-525. Unlike Sensor 2. this temperature rise was extreme,
from an expected 20 degrees Fahrenheit at EI-i-425 to 40 de-
grees at EI-i-485, and then rising much faster to 120 degrees
at EI-i-515, then to an off-scale high (a reading that climbs
off the scale at the high end of the range) of 450 degrees at
EI+522. The failure pattern of this sensor likely indicates
destruction by extreme heat.
The timing of the failures of these four sensors and the path
of their cable routing enables a determination of both the
timing and location of the breach of the leading edge spar,
and indirectly, the breach of the RCC panels. All the cables
from these sensors, and many others, were routed into wir-
ing harnesses that ran forward along the back side of the
leading edge spar up to a cross spar (see Figure 3.6-8), where
they passed through the service opening in the cross spar
and then ran in front of the left wheel well before reaching
interconnect panel 65R where they entered the fuselage. All
sensors with wiring in this set of harnesses failed between
EI+487 to EI+497, except Sensor 4, which survived until
EI-i-522. The diversity of sensor types (temperature, pres-
sure, and strains) and their locations in the left wing indi-
cates that they failed because their wiring was destroyed
at spar burn-through, as opposed to destmction of each
individual sensor by direct heating.
Examination of wiring installation closeout photographs (pic-
tures that document the state of the area that are normally taken
just before access is closed) and engineering drawings show
five main wiring harness bundles running forward along the
spar, labeled top to bottom as A through E (see Figure 3.6-8).
The top four, A through D. are spaced 3 inches apart, while
the fifth, E. is 6 inches beneath them. The separation between
bundle E and the other four is consistent with the later fail-
ure time of Sensor 4 by 25 to 29 seconds, and indicates that
the breach was in the upper two-thirds of the spar, causing
all but one of the cables in this area to fail between EI4-487
to EI+497. The breach then expanded vertically, toward the
underside of the wing, causing Sensor 4 to fail 25 seconds
V09T9895A - Left Wing Front Spar Panel 9 Temperature
500
400
300
u. 200
a 100
d
STS- 107
STS • 073
STS 090
STS- 109
100 200 300 400 500 600 700 800 900 1000
Time (seconds from El)
Figure 3.6-7. Sensor 4 also began reading s/gnificonf/y higher
than previous flights before it fell off-scale low. The relatively late
reaction of this sensor compared to Sensor 2, clearly indicated
that superheated air started on ffie outside of the wing leading
edge spar and then moved into the mid-wing after the spar was
burned through. Note that immediately before the sensor (or the
wire) fails, the temperature is at 450 degrees Fahrenheit and
climbing rapidly. It was the only temperature sensor that showed
this pattern.
later. Because the distance between bundle A and bundle E
is 9 inches, the failure of all the.se wires indicates that the
breach in the wing leading edge spar was at least 9 inches
from top to bottom by EI-i-522 seconds.
^■v09T9895aJ^^,,,«j^ JH
Figure 3.6-8. The left photo above shows the wiring runs on the
backside of the wing leading edge behind RCC panel 8 - the cir-
cle marks the most likely area where the burn through of the wing
leading edge spar initially occurred at EI+487 seconds. The right
photo shows the wire bundles as they continue forward behind
RCC panels 7 and 6. The major cable bundles in the upper right
of the right photo carried the majority of the sensor data inside
the wing. As these bundles were burned, controllers on the ground
began seeing off-nominal sensor indicofions.
Report voll
AUBUBT 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
Also directly behind RCC pane! 8 were pressure sensors
V07P80I0A (Sensor 5), on the upper interior surface of
the wing, and V07P8058A (Sensor 6). on the lower interior
surface of the wing. Sensor 5 failed abruptly at El+497.
Sensor 6, which was slightly more protected, began falling
at EI+495, and failed completely at EI+505. Closeout pho-
tographs show that the wiring from Sensor 5 travels down
from the top of the wing to join the uppermost harness. A,
which then travels along the leading edge spar. Similarly,
wiring from Sensor 6 travels up from the bottom of the wing,
joins harness A, and continues along the spar. It appears that
Sensor 5's wiring, on the upper wing surface, was damaged
at El+497, right after Sensor 1 failed. Noting the times of the
sensor failures, and the locations of Sensors 5 and 6 forward
of Sensors 1 through 4, spar burn-through must have oc-
curred near where these wires came together.
Two of the 45 left wing strain gauges also recorded an anom-
aly around EI-)-5()0 to EI+580, but their readings were not
erratic or off-scale until late in the re-entry, at EI-t-930. Strain
gauge V12G9048A was far forward on a cross spar in the
frontof the wheel well on the lower spar cap, and strain gauge
V 1 2G9049A was on the upper spar cap. Their responses ap-
pear to ba the actual strain at that location until their failure
at EI-i-935. The exposed wiring for most of the left wing sen-
sors runs along the front of the spar that crosses in front of
the left wheel well. The very late failure times of these two
sensors indicate that the damage did not spread into the wing
cavity forward of the wheel well until at least EI-(-935, which
implies that the breach was aft of the cross spar. Because the
cross spar attaches to the transition spar behind RCC panel
6, the breach must have been aft (outboard) of panel 6. The
superheated air likely burned through the outboard wall of
the wheel well, rather than snaking forward and then back
through the vent at the front of the wheel well. Had the gases
flowed through the access opening in the cross spar and then
through the vent into the wheel well, it is unlikely that the
lower strain gauge wiring would have survived.
Leff OMS Pod Surface Mounted Tile
Temperature on Forward Looking Face
100 200 300 iOO 500 600 700 800 900 1000
Time (seconds from El) 5'<"
Figure 3.6-9. Orbifal Maneuvering System (OMS) pod heating
was initially significantly lower than that seen on previous Colum-
bia missions. As wing leading edge damage later increased, the
OMS pod heating increased dramatically. Debris recovered from
this area of the OMS pod showed substantial pre-breakup heat
damage and imbedded drops of once-molten metal from the wing
leading edge in the OMS pod thermal tiles.
Finally, the rapid rise in Sensor 4 at EI+425, before the other
sensors began to fail, indicates that high temperatures were
responsible. Coinparisons of sensors on the outside of the
wing leading edge spar, those inside of the spar, and those in
the wing and left wheel well indicate that abnormal heating
first began on the outside of the spar behind the RCC panels
and worked through the spar. Since the aluminum spar must
have burned through before any cable harnesses attached to
it failed, the breach through the wing leading edge spar must
have occurred at or before EI-<-487.
Other abnormalities also occurred during re-entry. Early in
re-entry, the heating normally .seen on the left Orbital Ma-
neuvering System pod was much lower than usual for this
point in the flight (.see Figure 3.6-9). Wind tunnel testing
demonstrated that airflow into a breach in an RCC panel
would then escape through the wing leading edge vents
behind the upper pail of the panel and interrupt the weak
aerodynamic flow held on top of the wing. During re-entry,
air normally flows into these vents to equalize air pressure
across the RCC panels. The interruption in the flow field
behind the wing caused a displacement of the vortices that
normally hit the leading edge of the left pod, and resulted
in a slowing of pod heating. Heating of the side fuselage
slowed, which wind tunnel testing also predicted.
To match this scenario, investigators had to postulate dam-
age to the tiles on the upper carrier panel 9, in order to
allow sufficient mass flow through the vent to cause the
observed decrease in sidewall heating. No upper carrier
panels were found from panels 9, 10, and 1 1 . which supports
this hypothesis. Although this can account for the abnormal
temperatures on the body of the Orbiter and at the Orbital
Maneuvering System pod, flight data and wind tunnel tests
confirmed that this venting was not strong enough to alter
the aerodynamic force on the Orbiter, and the aerodynamic
analysis of mission data showed no change in Orbiter flight
control parameters during this time.
During re-entry, a change was noted in the rate of the tem-
perature rise around the RCC chin panel clevis temperature
sensor and two water supply nozzles on the left side of the
fuselage, just aft of the main bulkhead that divides the crew
cabin from the payload bay. Because these sensors were well
forward of the dainage in the left wing leading edge, it is still
unclear how their indications fit into the failure scenario.
Sensor Loss and the Onset of Unusual Aerodynamic
Effects (EI+500 through EI+611)
Fourteen seconds after the loss of the first sensor wire on the
wing leading edge spar at EI-t-487, a sensor wire in a bundle
of some 150 wires that ran along the upper outside comer
of the left wheel well showed a bum-through. In the ne.xt 50
seconds, more than 70 percent of the sensor wires in three
cables in this area also burned through (see Figure 3.6-10).
Investigators plotted the wiring run for every left-wing sen-
sor, looking for a relationship between their location and
time of failure.
Only two sensor wires of 169 remained intact when the
Modular Auxiliary Data System recorder stopped, indicat-
Report volume I
AUQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
100
'ercent Loss of Sensor Signals Versus Time In Left Wing and Wing Leading Edge Wire Bundles
V09T9895A
1 : X;^ ■— r— r-T^ '. , , , , , '. , 1 -r-, , : , ^^
90
80
°-: 70
1 60
o
§) 50
<^
o 40
c
:2. 30
o
•I" 20
c
D
O 10
0
4i
5
S
(18 of 18) 1 ^
::^
1
^
r^
Bui
die
>oF
3
L_
z
-H
r
=!
B
(
•of
el
91
r
i
Buidle
(2;iof
4
25)
kni.
-r.
Wheel W«
II
/
^
r
Bit Flip ^
Left Eleven >
►
/
r-\-
1 J
1
1 St Wheel Well TeiT i
(1700,1702 Bite c
Rise
orb Foi
♦
/r
i]
1 J
iJ
1
1
lOI 1
1
ure
/
1
*s
■hO
Sta
stn
h Fdilure
7
f"'
Ji
1
1
« Reversal of 1 oil moment a id st< irt o
Slo> f Ail< ron Trim
- 1
:hoi ge
1
|<
/
J
1
1
(Ml Oi Sla[ls Failure
1 1 1 1
*
*7 h OI Stoi 5 F« lure
/
r
1
1
f
■
— 1
1
1*-
Flat
Port!
5n f<
r3(
und
BS
50 500 550 600 650 700 750 800
ensors with Cobles Along Looding Edge Jj^^g (seconds frOm El)
art Loss Usee Eorlier Than the 3 Bundles ' '
Figure 3.6-10. This chart shows how rapidly the wire bundles in the left wing were destroyed. Over 70 percent of the sensor wires in ffie
wiring bundles burned through in under a minute. The black diamonds show the times of significant timeline sensor events.
ing that the bum-throughs had to occur in an area that nearly
every wire ran through. To sustain this type of damage, the
wires had to be close enough to the breach for the gas plume
to hit them. Arc jet testing (in a wind tunnel with an electri-
cal arc that provides up to a 2.800-degree Fahrenheit air-
flow) on a simulated wing leading edge spar and simulated
wire bundles showed how the leading edge spar would burn
through in a few seconds. It also showed that wire bundles
would burn through in a timeframe consistent with those
seen in the Modular Auxiliary Data System information and
the telemetered data.
Later computational fluid dynamics analysis of the mid-
wing area behind the spar showed that superheated air
flowing into a breached RCC panel 8 and then interacting
with the internal structure behind the RCC cavity (RCC ribs
and spar insulation) would have continued through the wing
leading edge spar as a jet. and would have easily allowed
superheated air to traverse the 56.5 inches from the spar to
the outside of the wheel well and destroy the cables (Figure
3.6-1 1 ). Controllers on the ground saw these first anomalies
in the telemetry data at EI-i-613. when four hydraulic sensor
cables that ran from the aft part of the left wing through the
wiring bundles outside the wheel well failed.
Aerodynamic roll and yaw forces began to differ from those
on previous flights at about EI-i-500 (see Figure 3.6-12). In-
vestigators used flight data to reconstruct the aerodynamic
forces acting on the Orbiter. This reconstructed data was then
compared to forces seen on other similar flights of Coliiinhici
mph
I
Contours of Velocify Magnitude (fps) Jun 10, 2003
FLUENT 6.1 (2d, coupled imp, ske)
Figure 3.6-11. The computational fluid dynamics analysis of the
speed of the superheated air as it entered the breach in RCC panel
8 and ffien traveled through the wing leading edge spar. The dark-
est red color indicates speeds of over 4,000 miles per hour. Tem-
peratures in this area likely exceeded 5,000 degrees Fahrenheit.
The area of detail is looking down at the top of the left wing.
Report Volui^e I
August 2003
COLUMBIA
ACCIDENT iNVESTIGATIDN BOARD
O
u
c
o
E
o
o
>-
"5
(1)
o
STS 107 Delta Rolling/Yawing Moment Coefficients
Off-Nominal Roll & Yaw
0.0025
0.0020
0.0015
0.0010
0.0005
0.000
-0.0005
Delta Cll (Roll Moment)
Delta CIn (Yaw Momen
— Delta Cll Aero Model
■Mi Delta CIn Aero Model
Wing Frnf Spor Ponet 9 Temp
Winfl IE 55 IWR An. Clevi-,
RCC 10
- Start Off Nomirol Trend
. 13:51;l-i
2 Temp Seniors Begin Off Nomlnol Reipon!
- V09T9895A • Wing Front Spar Pond 9
- V09T98'19A ■ OB Eleven, Lower Surfac.
.13 52,49 .5/51. -I
UBtiperoturo i?ise Roto Change
Hyd iy: I IMG UplK UnIK U Temp
Sys 3 IMG Brake Rel lino Tom
- LMG Bralte Line Temp B, C
13 56:16/22
Loft Upper Wing Skin Temp
■ Begin Oft Niminol Irond
■ 13:56:24
LeH Lower Wing Skin Temp
.OSL- 13 57,28
Le(t Upper Wing Skin Temp
-OSL. 13:57-43
00.0 50:00.0 51:00.0 52:00.0 53:00.0 54:00.0 55:00.0 56:00.0 57:00.0 58:00.0 59:00.0 00:00.0
Time (min:sec)
Figure 3,6-J2, Af approximately E/+500 seconds, the aerodynamic roll and yaw forces began to diverge from those observed on previous
flights. The blue line shows the Orbiter's tendency to yaw while the red line shows its tendency to roll. Nominal values would parallel the
solid b/ocfe line. Above the black line, the direction of the force is to the right, while below the black line, the force is to the left.
and to the forces predicted tor STS- 1 07. In the early phase
of fight, these abnormal aerodynamic forces indicated that
C(>lunihia\ flight control system was reacting to a change
in the external shape of the wing, which was caused by pro-
gressive RCC damage that caused a continuing decrease in
lift and a continuing increase in drag on the left wing.
Between EI-(-530 and EI-)-562, four sensors on the left in-
board elevon failed. These sensor readings were part of the
data telemetered to the ground. Noting the system failures,
the Maintenance, Mechanical, and Crew Systems officer
notified the Flight Director of the failures. (See sidebar in
Chapter 2 for a complete version of the Mission Control
Center conversation about this data.)
At EI-t-555, Colinnbiu crossed the California coast. People
on the ground now saw the damage developing on the Or-
biter in the form of debris being shed, and documented this
with video cameras. In the next 15 seconds, temperatures
on the fuselage sidewall and the left Orbital Maneuvering
System pod began to rise. Hypersonic wind tunnel tests indi-
cated that the increased heating on the Orbital Maneuvering
System pod and the roll and yaw changes were caused by
substantial leading edge damage around RCC panel 9. Data
on Orbiter temperature distribution as well as aerodynamic
forces for various damage scenarios were obtained from
wind tunnel testing.
Figure 3.6-13 shows the comparison of surface temperature
distribution with an undamaged Orbiter and one with an en-
tire panel 9 removed. With panel 9 removed, a strong vortex
flow structure is positioned to increase the temperature on
the leading edge of the Orbital Maneuvering System pod.
The aim is not to demonstrate that all of panel 9 was miss-
ing at this point, but rather to indicate that major damage to
panels near panel 9 can shift the strong vortex flow pattern
and change the Orbiter's temperature distribution to match
the Modular Auxiliary Data System information. Wind tun-
nel tests also demonstrated that increasing damage to lead-
ing edge RCC panels would result in increasing drag and
decreasing lift on the left wing.
Recovered debris showed that Inconel 718, which is only
found in wing leading edge spanner beams and attachment
fittings, was deposited on the left Orbital Maneuvering Sys-
tem pod. verifying that airflow through the breach and out
Report Vouume I
IBUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
of the upper slot carried molten wing leading edge material
back to the pod. Temperatures far exceeded those seen on
previous re-entries and further confirmed that the wing lead-
ing-edge damage was increasing.
By this time, superheated air had been entering the wing
since EI+487. and significant internal damage had probably
occurred. The major internal support structure in the mid-
wing consists of aluminum trusses with a melting point of
1.200 degrees Fahrenheit. Because the ingested air may have
been as hot as 8.000 degrees near the breach, it is likely that
the internal support structure that maintains the shape of the
wing was severely compromised.
As the Orbiter Hew east, people on the ground continued to
record the major shedding of debris. Investigators later scru-
tinized these videos to compare Coliiinhia's re-entry with
recordings of other re-entries and to identify the debris. The
video analysis was also used to determine additional search
areas on the ground and to estimate the size of various pieces
of debris as they fell from the Orbiter.
Temperatures in the wheel well began to rise rapidly at
EI-(-601. which indicated that the superheated air coming
through the wing leading edge spar had breached the wheel
well wall. At the same time, observers on the ground noted
additional significant shedding of debris. Analysis of one of
these "debris events" showed that the photographed object
could have weighed nearly 190 pounds, which would have
significantly altered Columbia's physical condition.
At EI+602. the tendency of the Orbiter to roll to the left in
response to a loss of lift on the left wing transitioned to a
right-rolling tendency, now in response to increased lift on
the left wing. Observers on the ground noted additional sig-
nificant shedding of debris in the next 30 seconds. Left yaw
continued to increase, consistent with increasing drag on the
left wing. Further damage to the RCC panels explains the
increased drag on the left wing, but it does not explain the
sudden increase in lift, which can be explained only by some
other type of wing damage.
Investigators ran multiple analyses and wind tunnel tests
to understand this significant aerodynamic event. Analysis
showed that by EI-t-850, the temperatures inside the wing
Boseline
smooth
TC lie
TC 1724'-
^1^
Run 18
^^^
^^^<
BBe^
— -^ '^^
Effect of Missinq RCC Panel on Orbiter
Mid-Fuselage Thermal Mapping
RELATIVE HEATING RATE
0 0 1 0 2 0.3 0.4 0.5
Figure 3.6-)3. The effects of removing RCC panel 9 ore shown in
this figure. Note the brighter colors on the front of the OMS pod
show increased heofing, o phenomenon supported by both the
OMS pod femperafure sensors and the debris analysis.
The Kirtland Image
As Columbia passed over Albuquerque, New Mexico, during
re-entr\' (around EI+795), scientists at the Air Force Starfire
Optical Range at Kirtland Air Force Base acquired images of
the Orbiter. This imaging had not been officially assigned,
and the photograph was taken using commercial equipment
located at the site, not with the advanced Starfire adaptive-
optics telescope.
The image shows an unusual condition on the iefl wing, a
leading-edge disturbance that might indicate damage. Sev-
eral analysts concluded that the distortion evident in the
image likely came from the modification and interaction of
shock waves due to the damaged leading edge. The overall
appearance of the leading-edge damage at this point on the
trajectory is consistent with the scenario.
were high enough to substantially damage the wing skins,
wing leading edge spar, and the wheel well wall, and melt
the wing's support struts. Once structural support was lost,
the wing likely deformed, effectively changing shape and re-
sulting in increased lift and a corresponding increase in drag
on the left wing. The increased drag on the left wing further
increased the Orbiter 's tendency to yaw left.
Loss of Vehicle Control (EI+612 through EI+970)
A rise in hydraulic line temperatures inside the left wheel
well indicated that superheated air had penetrated the wheel
well wall by EI-i-727. This temperature rise, telemetered to
Mission Control, was noted by the Maintenance, Mechani-
cal, and Crew Systems officer. The Orbiter initiated and
completed its roll reversal by EI-(-766 and was positioned
left-wing-down for this portion of re-entry. The Guidance
and Flight Control Systems performed normally, although
the aero-control surfaces (aileron trim) continued to counter-
act the additional drag and lift from the left wing.
At EI-i-790, two left main gear outboard tire pressure sen-
sors began trending slightly upward, followed very shortly
by going off-scale low, which indicated extreme heating of
both the left inboard and outboard tires. The tires, with their
large mass, would require substantial heating to produce the
sensors' slight temperature rise. Another sharp change in the
rolling tendency of the Orbiter occurred at EI-i-834, along
Peport Volume I
lauBT Z003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Lower Left wing debris
Lower Right wing debris
Figure 3.7-1, Comparison of amount of debris recovered from the left and right vv/ngs of Columbia. Nofe the amount of debris recovered
from areas in front of the wheel well (the red boxes on eocfi wing) were similar, but there were dramatic differences in the amount of debris
recovered aft of each wheel well.
with additional shedding of debris. In an attempt to maintain
attitude control, the Orbiter responded with a sharp change
in aileron trim, which indicated there was another significant
change to the left wing configuration, likely due to wing de-
formation. By El+887, all left main gear inboard and out-
board tire pressure and wheel temperature measurements
were lost, indicating burning wires and a rapid progression
of damage in the wheel well.
At EI+897. the left main landing gear downlock position
indicator reported that the gear was now down and locked.
At the same time, a sensor indicated the landing gear door
was still closed, while another sensor indicated that the
main landing gear was still locked in the up position. Wire
burn-through testing showed that a burn-induced short in the
downlock sensor wiring could produce these same contra-
dictions in gear status indication. Several measurements on
the strut produced valid data until the final loss of telemetry
data. This suggests that the gear-down-and locked indica-
tion was the result of a wire burn-through, not a result of
the landing gear actually deploying. All four corresponding
proximity switch sensors for the right main landing gear re-
mained normal throughout re-entry until telemetry was lost.
Figure 3.7-2. Each RCC panel has a U-shaped slot (see arrow) in
the back of the panel. Once superheated air entered the breach
in RCC panel 8, some of that superheated air went through this
slot and caused substantial damage to the Thermal Protection
System tiles behind this area.
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
Post-accident analysis of flight data that was generated af-
ter telemetry information was lost showed another abrupt
change in the Orbiter's aerodynamics caused by a contin-
ued progression of left wing damage at El-t-917. The data
showed a significant increase in positive roll and negative
yaw, again indicating another increase in drag on and lift
from the damaged left wing. Coliiiiihia's flight control sys-
tem attempted to compensate for this increased left yaw by
firing all four right yaw jets. Even with all thrusters firing,
combined with a maximum rate of change of aileron trim, the
flight control system was unable to control the left yaw, and
control of the Orbiter was lost at El -(-970 seconds. Mission
Control lost all telemetr\' data from the Orbiter at EI-(-923
(8:59:32 a.m.). Civilian and military video cameras on the
ground documented the final breakup. The Modular Auxil-
iary Data System stopped recording at EI-i-970 seconds.
Findings:
F3.6-I The de-orbit burn and re-entry flight path were
normal until just before Loss of Signal.
F3.6-2 Coliiiiihia re-entered the atmosphere with a pre-
existing breach in the left wing.
F3.6-3 Data from the Modular Auxiliar) Data System
recorder indicates the location of the breach was
in the RCC panels on the left wing leading edge.
F3.6-4 Abnormal heating events preceded abnormal
aerodynamic events by several minutes.
F3.6-5 By the time data indicating problems was teleme-
tered to Mission Control Center, the Orbiter had
already suffered damage from which it could not
recoN'er.
Recommendations:
R3.6-I The Modular .Auxiliary Data System instrumen-
tation and sensor suite on each Orbiter should be
maintained and updated to include cuaent sensor
and data acquisition technologies.
R3.6-2 The Modular Auxiliary Data System should be
redesigned to include engineering peiformance
and vehicle health information, and have the
ability to be reconfigured during flight in order to
allow certain data to be recorded, telemetered, or
both, as needs change.
3.7 Debris Analysis
The Board performed a detailed and exhaustive investigation
of the debris that was recovered. While sensor data from the
Orbiter pointed to early problems on the left wing, it could
only isolate the breach to the general area of the left wing
RCC panels. Forensics analysis independently determined
that RCC panel 8 was the most likely site of the breach, and
this was subsequently corroborated by other analyses. (See
Appendix D. 1 1.)
Pre-Breokup and
Post-Breakup Damage Determination
Differentiating between pre-breakup and post-breakup dam-
age pnncd a challcncc. When Cnliiiiihid's main body break-
up occurred, the Orbiter was at an altitude of about 200,000
feet and traveling at Mach 19, well within the peak-heating
region calculated for its re-entry profile. Consequently, as
individual pieces of the Orbiter were exposed to the at-
mosphere at breakup, they experienced temperatures high
enough to damage them. If a part had been damaged by heat
prior to breakup, high post-breakup temperatures could eas-
ily conceal the pre-breakup evidence. In some cases, there
was no clear way to determine what happened when. In
other cases, heat erosion occurred over fracture surfaces, in-
dicating the piece had first broken and had then experienced
high temperatures. Investigators concluded that pre- and
post-breakup damage had to be determined on a part-by-part
basis: it was impossible to make broad generalizations based
on the gross physical evidence.
Amount of Right Wing Debris
versus Left Wing Debris
Detailed analysis of the debris revealed unique features
and convincing evidence that the damage to the left wing
differed significantly from damage to the right, and that sig-
nificant differences existed in pieces from various areas of
the left wing. While a substantial amount of upper and lower
right wing structure was recovered, comparatively little of
the upper and lower left wing structure was recovered (see
Figure 3.7-1).
The difference in recovered debris from the Orbiter's wings
clearly indicates that after the breakup, most of the left wing
succumbed to both high heat and aerodynamic forces, while
the right wing succumbed to aerodynamic forces only. Be-
cause the left wing was already compromised, it was the first
area of the Orbiter to fail structurally. Pieces were exposed
to higher heating for a longer period, resulting in more heat
damage and ablation of left wing structural material. The left
wing was also subjected to superheated air that penetrated
directly into the mid-body of the wing for a substantial
period. This pre-heating likely rendered those components
unable to absorb much, if any, of the post-breakup heating.
Those internal and external structures were likely vaporized
during post-breakup re-entry. Finally, the left wing likely
lost significant amounts of the Thermal Protection System
prior to breakup due to the effect of internal wing heating on
the Thermal Protection System bonding materials, and this
further degraded the left wing's ability to resist the high heat
of re-entry after it broke up.
Tile Slumping and External Patterns of Tile Loss
Tiles recovered from the lower left wing yielded their own
interesting clues. The left wing lower carrier panel 9 tiles
sustained extreme heat damage (slumping) and showed more
signs of erosion than any other tiles. This severe heat erosion
damage was likely caused by an oiiffitw of superheated air
and molten inaterial from behind RCC panel 8 through
a U-shaped design gap in the panel (see Figure 3.7-2)
that allows room for the T-scal attachment. Effluents from
the back side of panel 8 would directly impact this area of
lower carrier panel 9 and its tiles. In addition, flow lines in
these tiles (see Figure 3.7-3) exhibit evidence of superheated
airflow across their surface from the area of the RCC panel
Report Voli
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Figure 3.7-3. Superheated airflow caused erosion in files around
the RCC panel 8 and 9 inferfoce. Tfie tiles shown are from behind
the area where the superheated air exited from the slot in Figure
3.7-2. These tiles showed much greater thermal damage than
other tiles in this area and chemical analysis showed the presence
of metals only found in wing leading edge components.
8 and 9 interface. Chemical analysis shows that these car-
rier panel tiles were covered with molten Inconel, which is
found in wing leading edge attachment fittings, and other
metals coming from inside the RCC cavity. Skimping and
heavy erosion of this magnitude is not noted on tiles from
anywhere else on the Orbiter.
Failure modes of recovered tiles from the left and the right
wing also differ. Most right wing tiles were simply broken
off the wing due to aerodynamic forces, which indicates that
they failed due to physical overload at breakup, not because
of heat. Most of the tiles on the left wing behind RCC panels
8 and<9 show significant evidence of backside healing of
the wing skin and failure of the adhesive that held the tiles
on the wing. This pattern of failure suggests that heat pen-
etrated the left wing cavity and then heated the aluminum
skin front the inside out. As the aluminum skin was heated.
the strength of the tile bond degraded, and tiles separated
from the Orbiter.
Erosion of Left Wing Reinforced Carbon-Carbon
Several pieces of left wing RCC showed unique signs of
heavy erosion from exposure to extreme heat. There was
erosion on two rib panels on the left wing leading edge in
the RCC panel 8 and 9 interface. Both the outboard rib of
panel 8 and the inboard rib of panel 9 showed signs of ex-
treme heating and erosion (see Figure 3.7-4). This erosion
indicates that there was extreme heat behind RCC panels 8
and 9. This type of RCC erosion was not seen on any other
part of the left or right wing.
Locations of Reinforced Carbon-Carbon Debris
The location of debris on the ground also provided evidence
of where the initial breach occurred. The location of every
piece of recovered RCC was plotted on a map and labeled
according to the panel the piece originally came from. Two
distinct patterns were immediately evident. First, it was
clear that pieces from left wing RCC panels 9 through 22
had fallen the farthest west, and that RCC from left wing
panels 1 through 7 had fallen considerably farther east (see
Figure 3.7-5). Second, pieces from left wing panel 8 were
Panel 7
Panel 8
Panel 9
Panel 10
-Panel 11
Figure 3.7-4. The outboard rib of panel 8 and the inboard rib of
panel 9 showed signs of exfreme heating and erosion. RCC ero-
sion of this magnitude was not observed in any other location on
the Orbiter.
Figure 3.7-6. The tiles recovered farthest west all came from the
area immediately behind left wing RCC panels 8 and 9. In the
Figure, each small box represenfs an individual tile on ffie lower
surface of the left wing. The more red an individual tile appears,
the farther west it was found.
Report voi
IGU5T 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Figure 3.7-5. The location of RCC panel debris from the left and right wings, shown where it was recovered from in East Texas. The debris
pattern suggested that the left wing failed before the right wing, most likely near left RCC panels 8 and 9.
found throughout the debris field, which suggested that the
left wing likely failed in the vicinity of RCC panel 8. The
early loss of the left wing from RCC panel 9 and outboard
caused the RCC from that area to be deposited well west
of the RCC from the inboard part of the wing. Since panels
I through 7 were so much farther to the east, investigators
concluded that RCC panels I through 7 had stayed with the
Orbiter longer than had panels 8 through 22.
Tile Locations
An analysis of where tiles were found on the ground also
yielded significant evidence of the breach location. Since
most of the tiles are of similar size, weight, and shape, they
would all have similar ballistic coefficients and would have
behaved similarly after they separated from the Orbiter. By
noting where each tile fell and then plotting its location on
the Orbiter tile map, a distinctive pattern emerged. The tiles
recovered farthest west all came from the area immediately
behind the left wing RCC panel H and 9 (see Figure 3.7-6),
which suggests that these tiles were released earlier than
those from other areas of the left wing. While it is not con-
clusive evidence of a breach in this area, this pattern does
suggest unique damage around RCC panels X and 9 that was
not seen in other areas. Tiles from this area also showed evi-
dence of a brown deposit that was not seen on tiles from any
other part of the Orbiter. Chemical analysis revealed it was
an Inconel-based deposit that had come from inside the RCC
cavity on the left wing (Inconel is found in wing leading
edge attachment fittings). Since the streamlines from tiles
with the brown deposit originate near left RCC panels 8 and
9. this brown deposit likely originated as an outflow of su-
perheated air and molten metal from the panel 8 and 9 area.
Molten Deposits
High heat damage to metal parts caused molten deposits to
form on some Orbiter debris. Early analysis of these depos-
its focused on their density and location. Much of the left
wing leading edge showed some signs of deposits, but the
left wing RCC panels ."S to 10 had the highest levels.
Of all the debris pieces recovered, left wing panels 8 and
9 showed the largest amounts of deposits. Significant but
lesser amounts of deposits were also observed on left wing
RCC panels 5 and 7. Right wing RCC panel 8 was the only
right-wing panel with significant deposits.
Chemical and X-Ray Analysis
Chemical analysis focused on recovered pieces of RCC pan-
els with unusual deposits. Samples were obtained from areas
Report Voli
I s T 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
in the vicinity of left wing RCC panel 8 as well as other left
and right wing RCC panels. Deposits on recovered RCC de-
bris were analyzed by cross-sectional optical and scanning
electron microscopy, microprobe analysis, and x-ray diffrac-
tion to determine the content and layering of slag deposits.
Slag was defined as metallic and non-metallic deposits that
resulted from the melting of the internal wing structures.
X-ray analysis determined the best areas to sample for
chemical testing and to see if an overall flow pattern could
be discerned.
The X-ray analysis of left wing RCC panel 8 (see Figure
3.7-7) showed a bottom-to-top pattern of slag deposits. In
some areas, small spheroids of heavy metal were aligned
vertically on the recovered pieces, which indicated a super-
healed airflow from the bottom of the panel toward the top
in the area of RCC panel 8-left. These deposits were later
detemiined by cheniical analysis to be Inconel 718, prob-
ably from the wing leading edge attachment fittings on the
spanner beams on RCC panels 8 and 9. Computational fluid
dynamics modeling of the flow behind panel 8 indicated that
the molten deposits would be laid down in this manner.
Figure 3.7-7. X-ray analysis of RCC panel 8-leH sfiowec/ a boftom-
fo-fop pattern of slag deposits.
The layered deposits on panel 8 were also markedly different
from those on all other left- and right-wing panels. There was
much more material deposited on RCC panel 8-left. These
deposits had a much rougher overall structure, including
rivulets of Ccrachrome slag deposited directly on the RCC.
This indicated that Cerachrome, the insulation that protects
the wing leading edge spar, was one of the first materials to
succumb to the superheated air entering through the breach in
RCC panel 8-left. Because the melting temperature of Cera-
chrome is greater than 3,200 degrees Fahrenheit, analysis in-
dicated that materials in this area were exposed to extremely
figure 3.7-8. Spheroids of Inconel 718 and Cerachrome were
deposited directly on the surface of RCC panel 8-left. This slag
deposit pattern was not seen on any other RCC panels.
high temperatures for a long period. Spheroids of Inconel
718 were mixed in with the Cerachrome. Because these
spheroids (see Figure 3.7-8) were directly on the surface of
the RCC and also in the first layers of deposits, investigators
concluded that the Inconel 718 spanner beam RCC fittings
were most likely the first internal structures subjected to
intense heating. No aluminum was detected in the earliest
slag layers on RCC panel 8-left. Only one location on an up-
per corner piece, near the spar fitting attachment, contained
A-286 stainless steel. This steel was not present in the bottom
layer of the slag directly on the RCC surface, which indicated
that the A-286 attachment fittings on the wing spar were not
in the direct line of the initial plume impingement.
In wing locations other than left RCC panels 8 and 9, the
deposits were generally thinner and relatively uniform. This
suggests no particular breach location other than in left RCC
panels 8 and 9. These other slag deposits contained primarily
aluminum and aluminum oxides mixed with A-286, Inconel,
and Cerachrome, with no consistent layering. This mixing
of multiple metals in no apparent order suggests concurrent
melting and re-depositing of all leading-edge components,
which is more consistent with post-breakup damage than
the organized melting and depositing of materials that oc-
cun^ed near the original breach at left RCC panels 8 and 9.
RCC panel 9-left also differs from the rest of the locations
analyzed. It was similar to panel 8-left on the inboard side,
but more like the remainder of the samples analyzed on its
outboard side. The deposition of molten deposits strongly
suggests the original breach occurred in RCC panel 8-left.
Spanner Beams, Fittings, and Upper Carrier Panels
Spanner beams, fittings, and upper carrier panels were recov-
ered from areas adjacent to most of the RCC panels on both
wings. However, significant numbers of these items were not
recovered from the vicinity of left RCC panels 6 to 10. None
of the left wing upper carrier panels at positions 9, 10, or 1 1
were recovered. No spanner beam parts were recovered from
Report Voui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
STS-107 Crew Survivability
At the Board's request. NASA formed a Crev\ Survi\abi!it\
Working Group within two weeks of the accident to better un-
derstand the cause of crew death and the breakup of the crew
module. This group made the follow ing observations.
Medical and Life Sciences
The Working Group found no irregularities in its extensive re-
view of all applicable medical records and crew health data. The
Armed Forces Institute of Pathology and the Federal Bureau of
Investigation conducted forensic analyses on the remains of the
crew of Colnnihiii after they were recovered. It was determined
that the acceleration levels the crew module experienced prior
to its catastrophic failure were not lethal. The death of the crew
members was due to blunt trauma and hypo.xia. The exact time
of death - sometime after 9:()0:19 a.m. Eastern Standard Time
- cannot be determined because of the lack of direct physical or
recorded evidence.
Failure of tfie Crew Module
The forensic evaluation of all recovered crew module/forward
fuselage compKinents did not show any evidence of over-pres-
surization or explosion. This conclusion is supported by both
the lack of forensic evidence and a credible source for either
sort of event." The failure of the crew module resulted from the
thermal degradation of structural properties, which resulted in a
rapid catastrophic sequential structural breakdown rather than
an instantaneous "explosive" failure.
Separation of the crew module/forward fuselage assembly from
the rest of the Orbiter likely occurred immediately in front of
the payload bay (between Xo376 and Xo582 bulkheads). Sub-
sequent breakup of the assembly was a result of ballistic healing
and dynamic loading. Evaluations of fractures on both primary
and secondary structure elements suggest that structural failures
occurred at high temperatures and in some cases at high strain
rates. An extensive trajectory reconstruction established the
most likely breakup sequence, shown below.
The load and heat rate calculations are shown for the crew mod-
ule along its reconstructed trajectory. The band superimposed
on the trajectory (starting about 9:00:58 a.m. EST) represents
the window where all the evaluated debris originated. It ap-
pears that the destruction of the crew module took place over a
period of 24 seconds beginning at an altitude of approximately
140,000 feel and ending at 105.000 feet. These figures are
consistent with the results of independent thermal re-entry and
aerodynamic models. The debris footprint proved consistent
w ith the results of these trajectory analyses and models. Ap-
proximately 40 to 50 percent, by weight, of the crew module
was recovered.
The Working Group's results significantly add to the knowledge
gained from the loss of Challenger in 1986. Such knowledge is
critical to efforts to improve crew survivability when designing
new vehicles and identifying feasible imprcnemenis to the exist-
ing Orbiters.
Crew Worn Equipment
Videos of the crew during re-entry that have been made public
demonstrate that prescribed procedures for use of equipment
such as full-pressure suits, gloves, and helmets were not strictly
followed. This is confirmed by the Working Group's conclu-
sions that three crew members were not wearing gloves, and one
was not wearing a helmet. However, under these circumstances,
this did not affect their chances of survival.
Report v/olume 1
I 5 T 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Board Testing
NASA and the Board agreed that tests would be required and
a test plan developed to validate an impact/breach scenario.
Initially, the Board intended to act only in an oversight role in
the development and implementation of a test plan. However,
ongoing and continual 1> unresolved debate on the si/.e and
velocity of the foam projectile, largely due to the Marshall
Space Flight Center's insistence that, despite overwhelm-
ing evidence to the contrary, the foam could have been no
larger than 855 cubic inches, convinced the Board to take a
more active role. Additionally, in its assessment of potential
foam damage NASA continued to rely heavily on the Crater
model, v\hich was used during the mission to determine that
the foam-shedding event was non-threatening. Crater is a
semi-empirical model constructed from Apollo-era data. An-
other factor that contributed to the Board's decision to play an
active role in the test program was the Orbiter Vehicle Engi-
neering Working Group's requirement that the test program
be used to validate the Crater model. NASA failed to focus
on physics-based pre-test predictions, the schedule priorities
for RCC tests that were determined by transport analysis, the
addition of appropriate test instrumentation, and the consid-
eration of additional factors such as launch loads. Ultimately,
in discussions with the Orbiter Vehicle Engineering Working
Group and the NASA Accident Investigation Team, the Board
provided test plan requirements that outlined the template for
all testing. The Board directed that a detailed written test plan,
with Board-signature approval, be provided before each test.
gesting that the breach in the RCC was through panel 8-ieft.
It is notewoithy that it occurred only in this area and not
in any other areas on either the left or the right wing lower
carrier panels. There is also significant and unique evidence
of severe "knife edges" erosion in left RCC panels 8 and 9.
Lastly, the pattern of the debris field also suggests the left
wing likely failed in the area of RCC panel 8-left.
The preponderance of unique debris evidence in and near
RCC panel 8-left strongly suggests that a breach occurred
here. Finally, the unique debris damage in the RCC panel
8-left area is completely consistent with other data, such as
the Modular Au.\iliary Data System recorder, visual imagery
analysis, and the aerodynamic and aerothermal analysis.
Findings:
F3.7-I Multiple indications from the debris analysis es-
tablish the point of heat intrusion as RCC panel
8-left.
F3.7-2 The recovery of debris from the ground and its
reconstruction was critical to understanding the
accident scenario.
Recommendations:
None
3.8 Impact Analysis AND Testing
the left RCC panel 8 to 10 area. No upper or lower RCC fit-
tings were recovered for left panels 8. 9, or 10. Some of this
debris may not have been found in the search, but it is un-
likely that all of it was missed. Much of this structure prob-
ably melted, and was burned away by superheated air inside
the wing. What did not melt was so hot that when it broke
apart, it did not survive the heat of re-entry. This supports the
theory that superheated air penetrated the wing in the general
area of RCC panel 8-left and caused considerable structural
damage to the left wing leading edge spar and hardware.
Debris Analysis Conclusions
A thorough analysis of left wing debris (independent of
the preceding aerodynamic, aerothermal, sensor, and photo
data) supports the conclusion that significant abnormalities
occurred in the vicinity of left RCC panels 8 and 9. The pre-
ponderance of debris evidence alone strongly indicates that
the breach occurred in the bottom of panel 8-left. The unique
composition of the slag found in panels 8 and 9, and espe-
cially on RCC panel 8-left, indicates extreme and prolonged
heating in these areas very early in re-entry.
The early loss of tiles in the region directly behind left RCC
panels 8 and 9 also supports the conclusion that a breach
through the wing leading edge spar occuired here. This al-
lowed superheated air to flow into the wing directly behind
panel 8. The heating of the aluminum wing skin degraded tile
adhesion and contributed to the early loss of tiles.
Severe damage to the lower earner panel 9-left tiles is
indicative of a flow out of panel 8-left. also strongly sug-
The importance of understanding this potential impact dam-
age and the need to prove or disprove the impression that
foam could not break an RCC panel prompted the investi-
gation to develop computer models for foam impacts and
undertake an impact-testing program of shooting pieces of
foam at a mockup of the wing leading edge to re-create, to
the extent practical, the actual STS-107 debris impact event.
Based on imagery analysis conducted during the mission
and early in the investigation, the test plan included impacts
on the lower wing tile, the left main landing gear door, the
wing leading edge, and the carrier panels.
A main landing gear door assembly was the first unit ready
for testing. By the time that testing occurred, however, anal-
ysis was pointing to an impact site in RCC panels 6 through
9. After the main landing gear door tests, the analysis and
testing effort shifted to the wing leading edge RCC panel as-
semblies. The main landing gear door testing provided valu-
able data on test processes, equipment, and instrumentation.
Insignificant tile damage was observed at the low impact
angles of less than 20 degrees (the impact angle if the foam
had struck the main landing gear door would have been
roughly five degrees). The apparent damage threshold was
consistent with previous testing with much smaller projec-
tiles in 1999, and with independent modeling by Southwest
Research Institute. (See Appendix D. 12.)
Impact Test - Wing Leading Edge Panel Assemblies
The test concept was to impact flightworthy wing leading
edge RCC panel assemblies w ith a foam projectile fired by
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARD
a compressed-gas gun. Target panel assemblies with a flight
history similar to Coliinihia's would be mounted on a sup-
port that was structurally equivalent to CohnnbUi?. wing.
The attaching hardware and fittings would be either flight
certified or built to Colwnhia drawings. Several consider-
ations influenced the overall RCC test design:
• RCC panel assemblies were limited, particularly those
with a flight history similar to Colitnihki'f,.
• The basic material properties of new RCC were known
to be highly variable and were not characterized for high
strain rate loadings typical of an impact.
• The influence of aging was uncertain.
• The RCC's brittleness allowed only one test impact on
each panel to avoid the possibility that hidden damage
would influence the results of later impacts.
• The structural system response of RCC components,
their support hardware, and the wing structure was
complex.
• The foam projectile had to be precisely targeted, be-
cause the predicted structural response depended on the
impact point.
Because of these concerns, engineering tests with fiberglass
panel assemblies from the first Orbiter, Enterprise.^- were
used to obtain an understanding of overall system response
to various impact angles, locations, and foam orientations.
The fiberglass panel impact tests were used to confirm in-
strumentation design and placement and the adequacy of the
overall test setup.
Test projectiles were made from the same type of foam as
the bipod ramp on STS-107's External Tank. The projectile's
mass and velocity were determined by the previously de-
scribed "best fit" image and transport analyses. Because the
precise impact point was estimated, the aiming point for any
individual test panel was based on structural analyses to
maximize the loads in the area being assessed without pro-
ducing a spray of foam over the top of the wing. The angle
of impact relative to the test panel was determined from
the transport analysis of the panel being tested. The foam's
rotational velocity was accounted for with a three-degree
increase in the impact angle.
Computer Modeling of Impact Tests
The investigation used sophisticated computer models to
analyze the foam impact and to help develop an impact test
program. Because an exhaustive test matrix to cover all fea-
sible impact scenarios was not practical, these models were
especially important to the investigation.
The investigation impact modeling team included members
from Boeing, Glenn Research Center, .Johnson Space Cen-
ter, Langley Research Center, Marshall Space Flight Center.
Sandia National Laboratory, and Stellingwerf Consulting.
The Board also contracted with Southwest Research Insti-
tute to peiform independent computer analyses because of
the institute's extensive test and analysis experience with
ballistic impacts, including work on the Orbiter's Thermal
Protection System. (Appendix D.12 provides a complete
description of Southwest's impact modeling methods and
results.)
The objectives of the modeling effort included ( 1 ) evalua-
tion of test instrumentation requirements to provide test data
with which to calibrate the computer models, (2) prediction
of stress, damage, and instrumentation response prior to the
Test Readiness Reviews, and (3) determination of the flight
conditions/loads (vibrations, aerodynamic, inertial, acoustic,
and themial) to include in the tests. In addition, the impact
modeling team provided information about foam impact lo-
cations, orientation at impact, and impact angle adjustments
that accounted for the foam's rotational velocity.
Flight Environment
A comprehensive consideration of the Shuttle's flight en-
vironment, including temperature, pressure, and vibration,
was required to establish the experimental protocol.
Figure 3.8? Nitrogen-powered gun at the Southwest Research Institute used for the test series.
Report Volume I August ZD03
COLUMBIA
ACCIDENT INVESTIGATION aOAR[
Based on the results of Glenn Research Center sub-scale im-
pact tests of how various foam temperatures and pressures
influence the impact force, the Board found that full-scale
impact tests with foam at room temperature and pressure
could adequately simulate the conditions during the foam
strike on STS- 107."
The structure of the foam complicated the testing process.
The bipod ramp foam is hand-sprayed in layers, which cre-
ates "knit lines," the boundaries between each layer, and the
foam compression characteristics depend on the knit lines'
orientation. The projectiles used in the full-scale impact tests
had knit lines consistent with those in the bipod ramp foam.
.\ primary concern of investigators was that external loads
present in the flight environment might add substantial extra
force to the left wing. However, analysis demonstrated that
the only significant external loads on the wing leading edge
structural subsystem at about 82 seconds into flight are due
to random vibration and the pressure differences inside and
outside the leading edge. The Board concluded that the flight
environment stresses in the RCC panels and the attachment
fittings could be accounted for in post-impact analyses if
necessary. However, the dramatic damage produced by the
impact tests demonstrated that the foam strike could breach
the wing leading edge structure subsystein independent of
any stresses associated with the flight environment. (Appen-
dix D. 12 contains more detail.)
Test Assembly
The impact tests were conducted at a Southwest Research
Institute facility. Figure 3.8- 1 shows the nitrogen gas gun that
had evaluated bird strikes on aircraft fuselages. The gun was
modified to accept a 33-foot-long rectangular barrel, and the
target site was equipped with sensors and high-speed camer-
as that photographed 2,000 to 7,0(X) frames per second, with
intense light provided by theater spotlights and the sun.
Test Impact Target
The leading edge structural subsystem test target was designed
to accommodate the Board's evolving determination of the
most likely point of impact. Initially, analysis pointed to the
main landing gear door. As the imaging and transport teams
refined their assessments, the likely strike zone narrowed to
RCC panels 6 through 9. Because of the long lead time to de-
velop and produce the large complex test assemblies, inves-
tigators developed an adaptable test assembly (Figure 3.8-2)
that would provide a structurally similar mounting for RCC
panel assemblies 5 to 10 and would accommodate some 200
sensors, including high-speed cameras, strain and deflection
gauges, accelerometers, and load cells. '^
Test Panels
RCC panels 6 and 9, which bracketed the likely impact re-
gion, were the first identified for testing. They would also
permit a comparison of the structural response of panels with
and without the additional thickness at certain locations.
Panel 6 tests demonstrated the complex system response to
impacts. While the initial focus of the investigation had been
on single panel response, early results from the tests with
fiberglass panels hinted at "boundary condition" effects.
Instruments measured high stresses through panels 6, 7, and
8. With this in mind, as well as forensic and sensor evidence
that panel 8 was the likeliest location of the foam strike, the
Board decided that the second RCC test should target panel
8, which was placed in an assembly that included RCC pan-
els 9 and 10 to provide high fidelity boundary conditions.
The decision to impact test RCC panel 8 was complicated
by the lack of spare RCC components.
The specific RCC panel assemblies selected for testing
had flight histories similar to that of STS- 107, which was
Coltiinhia'f, 28th flight. Panel 6 had flown 30 missions on
Di.scovcry. and Panel 8 had flown 26 missions on Atlantis.
Test Projectile
The preparation of BX-250 foam test projectiles used the
same material and preparation processes that produced the
foam bipod ramp. Foam was selected as the projectile mate-
rial because foam was the most likely debris, and materials
other than foam would represent a greater threat.
Figure 3.8-2. Test assembly thai provided a sfrucfural mounfing
for RCC panel assemblies 5 io 10 and would accommodafe some
200 sensors and other test equipment.
Figure 3.8-3 A typical foam projectile, which has marks for de-
termining position and velocity as well as blackened outlines for
indicating the impact footprint.
Report Voli
AUC3UST 2003
COLUMBIA
ACCIDENT INVESTIGATION 8DARD
The testing required a projectile (see Figure 3.8-3) made
from standard stock, so investigators selected a rectangular
cross-section of 11.5 by 5.5 inches, which was within 15
percent of the footprint of the mean debris size initially esti-
mated by image analysis. To account for the foam's density,
the projectile length was cut to weigh 1.67 pounds, a figure
determined by image and transport analysis to best repre-
sent the STS-107 projectile. For foam with a density of 2.4
pounds per cubic foot,'^ the projectile dimensions were 19
inches by 1 1 .5 inches by 5.5 inches.
Impact Angles
The precise impact location of the foam determined the im-
pact angle because the debris was moving almost parallel to
the Orbiter's fuselage at impact. Tile areas would have been
hit at vei7 small angles (approximately five degrees), but
the curvature of the leading edge created angles closer to 20
degrees (see Figure 3.4-4).
The foam that struck Coliiinhiu on January 16, 2003. had
both a translational speed and a rotational speed relative to
the Orbiter. The translational velocity was easily replicated
by adjusting the gas pressure in the gun. The rotational en-
ergy could be calculated, but the impact force depends on
the material composition and properties of the impacting
body and how the rotating body struck the wing. Because
the details of the foam contact were not available from any
visual e\idence. analysis estimated the increase in impact
energy that would be imparted by the rotation. These analy-
ses resulted in a three-degree increase in the angle at which
the foam test projectile would hit the test panel.'"
The "clocking angle" was an additional consideration. As
shown in Figure 3.8-4, the gun barrel could be rotated to
change the impact point of the foam projectile on the leading
edge. Investigators conducted experiments to determine if
the comer of the foam block or the full edge would impart a
greater force. During the fiberglass tests, it was found that a
clocking angle of 30 degrees allowed the 1 1 .5-inch-edge to
fully contact the panel at impact, resulting in a greater local
force than a zero degree angle, which was achieved with the
barrel aligned vertically. A zero-degree angle was used for
the test on RCC panel 6, and a 30-degree angle was used for
RCC panel 8.
Test Results from Fiberglass Panel Tests 1-5
Five engineering tests on fiberglass panels (see Figure 3.8-5)
established the test parameters of the impact tests on RCC
panels. Details of the fiberglass tests are in Appendix D. 12.
If!;
V'^:
s
l^h^iliWn. .
Figure 3 8-4. 7/ie barrel on fhe nitrogen gun could be rotated to
adjust the impact point of the foam projectile.
Figure 3.8-5. A typical foam strike leaves impact streaks, and the
foam projectile breaks into shards and larger pieces tiere the
foam is striking Panel 6 on a fiberglass test article.
Test Results from Reinforced Carbon-Carbon Panel 6
(From Discovery)
RCC panel 6 was tested first to begin to establish RCC
impact response, although by the time of the test, other
data had indicated that RCC panel 8-left was the most
likely site of the breach. RCC panel 6 was impacted us-
ing the same parameters as the test on fiberglass panel 6
and developed a 5.5-inch crack on the outboard end of the
panel that extended through the rib (see Figure 3.8-6). There
was also a crack through the "web" of the T-seal between
panels 6 and 7 (see Figure 3.8-7). As in the fiberglass test,
the foam block deflected, or moved, the face of the RCC
panel, creating a slit between the panel and the adjacent
T-seal, which ripped the projectile and stuffed pieces of foam
into the slit (see Figure 3.8-8). The panel rib failed at lower
stresses than predicted, and the T-seal failed closer to predic-
tions, but overall, the stress pattern was similar to what was
predicted, demonstrating the need to incorporate more com-
plete RCC failure criteria in the computational models.
Without further crack growth, the specific structural dam-
age this test produced would probably not have allowed
enough superheated air to penetrate the wing during re-entry
to cause serious damage. However, the test did demonstrate
that a foam impact representative of the debris strike at 81.9
seconds after launch could damage an RCC panel. Note that
REPORT VOUUf
COLUMBIA
ACCIOENT INVESTIGATION BOARD
Figure 3.8-6. A 5.5-inch crack on the outboard portion of RCC
Panel 6 during testing.
Figure 3.8-7. Two views of the crack in the T-seal between RCC
Panels 6 and 7.
the RCC panel 6-let't test used fiberglass panels and T-seals in
panel 7, 8, 9, and 10 locations. As seen later in the RCC panel
8-ieft test, this test configuration may not have adequately
reproduced the flight configuration. Testing of a .full RCC
panel 6, 7, and 8 configuration might have resulted in more
severe damage.
Test Results from Reinforced Carbon-Carbon Panel 8
(From Atlantis)
The second impact test of RCC material used panel 8 from
Atlantis, which had flown 26 missions. Based on forensic
evidence, sensor data, and aerothermal studies, panel 8 was
considered the most likely point of the foam debris impact
on Cohiiuhia.
Based on the system response of the leading edge in the
fiberglass and RCC panel 6 impact tests, the adjacent RCC
panel assemblies (9 and 10) were also flown hardware. The
reference 1.67-pound foam test projectile impacted panel 8
Figure 3.8-8. Two views of foam lodged into the slit during tests.
Figure 3.8-9. The large impact hole in Panel 8 from the fmal test.
Figure 3.8-10. Numerous cracks were also noted in RCC Panel 8.
Report Volume I auqust zaas
COLUMBIA
ACCIDENT INVESTIGATION BDARD
at 777 feet per second with a clocking angle of 30 degrees
and an angle of incidence of 25. 1 degrees.
The impact created a hole roughly 16 inches by 17 inches,
which was within the range consistent with all the findings
of the investigation (see Figure 3.8-9). Additionally, cracks
in the panel ranged up to 1 1 inches in length (Figure 3.8-10).
The T-seal between panels 8 and 9 also failed at the lower
outboard mounting lug.
Three large pieces of the broken panel face sheet (see Fig-
ure 3.8-11) were retained within the wing. The two largest
pieces had surface areas of 86 and 75 square inches. While
this test cannot exactly duplicate the damage Coliinihia in-
curred, pieces such as these could have remained in the wing
cavity for some time, and could then have floated out of the
damaged wing while the Orbiter was maneuvering in space.
This scenario is consistent with the event observed on Flight
Day 2 (see Section 3.5).
The test clearly demonstrated that a foam impact of the type
Columbia sustained could seriously breach the Wing Lead-
ing Edge Structural Subsystem.
Conclusion
At the beginning of this chapter, the Board stated that the
physical cause of the accident was a breach in the Thermal
Protection System on the leading edge of the left wing. The
breach was initiated by a piece of foam that separated from
the left bipod ramp of the External Tank and struck the wing
in the vicinity of the lower half of the Reinforced Carbon-
Carbon (RCC) panel 8.
The conclusion that foam separated from the External Tank
bipod ramp and struck the wing in the vicinity of panel 8 is
documented by photographic evidence (Section 3.4). Sensor
data and the aerodynamic and thermodynamic analyses (Sec-
tion 3.6) based on that data led to the determination that the
breach was in the vicinity of panel 8 and also accounted for
the subsequent melting of the supporting structure, the spar,
and the wiring behind the spar that occurred behind panel
8. The detailed examination of the debris (Section 3.7) also
pointed to panel 8 as the breach site. The impact tests (Sec-
tion 3.8) established that foam can breach the RCC, and also
counteracted the lingering denial or discounting of the ana-
lytic evidence. Based on this evidence, the Board concluded
that panel 8 was the site of the foam strike to Colionhia
during the liftoff of STS- 107 on January 23, 2003.
Findings:
F3.8-1 The impact test program demonstrated that foam
can cau.se a wide range of impact damage, from
cracks to a 16- by 17-inch hole.
F3.8-2 The wing leading edge Reinforced Carbon-Car-
bon composite material and associated support
hardware are remarkably tough and have impact
capabilities that far exceed the minimal impact
resistance specified in their original design re-
quirements. Nevertheless, these tests demonstrate
that this inherent toughness can be exceeded by
impacts representative of those that occurred dur-
ing Columbia's ascent.
F3.8-3 The response of the wing leading edge to impacts
is complex and can vai^ greatly, depending on the
location of the impact, projectile mass, orienta-
tion, composition, and the material properties of
the panel assembly, making analytic predictions
of damage to RCC assemblies a challenge."
F3.8-4 Testing indicates the RCC panels and T-seals
have much higher impact resistance than the de-
sign specifications call for.
F3.8-5 NASA has an inadequate number of spare Rein-
forced Carbon-Carbon panel assemblies.
F3.8-6 NASA's current tools, including the Crater mod-
el, are inadequate to evaluate Orbiter Thermal
Protection System damage from debris impacts
during pre-launch, on-orbit, and post-launch ac-
tivity.
F3.8-7 The bipod ramp foam debris critically damaged
the leading edge of Columbia's left wing.
Recommendations:
R3.8-I Obtain sufficent spare Reinforced Carbon-Car-
bon panel assemblies and associated support
components to ensure that decisions related to
Reinforced Carbon-Carbon maintenance are
made on the basis of component specifications,
free of external pressures relating to schedules,
costs, or other considerations.
R3.8-2 Develop, validate, and maintain physics-based
computer models to evaluate Thermal Protection
System damage from debris impacts. These tools
should provide realistic and timely estimates of
any impact damage from possible debris from
any .source that may ultimately impact the Or-
biter. Establish impact damage thresholds that
trigger responsive corrective action, such as on-
orbit inspection and lepair. when indicated.
Figure 3.8-11. Three large pieces of debris from the panel face
sheet were lodged withm the hollow area behind the RCC panel.
REPORT VOUUME I
AUQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARD
Endnotes for Chapter 3
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
See Dennis R. Jenkins, Space Shuffle: The History of the Nationo/ Spoce
Transportation System - The First 100 Missions (Cape Canaveral, FL,
Specialty Press, 2001), pp. 421-424 for a complete description of the
External Tank.
Scotty Sparks and Lee Foster, "ET Cryoinsulotion," CAIB Public Hearing,
April 7, 2003. CAIB document CAB017-03140371.
Scotty Sparks and Steve Holmes, Presentation to the CAIB, March 27,
2003, CAIB document CTF036-02000200.
See the CAIB/NAIT Joint Working Scenario in Appendix D.7 of Volume
II of this report.
Boeing Specification MJ070-0001-1E, "Orbiter End Item Specification for
the Space Shuttle Systems, Part 1, Performance and Design Requirements,
November 7, 2002.
Ibid., Paragraph 3.3.1.8.16.
NSTS-08171, "Operations and Maintenance Requirements and
Specifications Document (OMRSD)" File II, Volume 3. CAIB document
CAB03312821997
Dr. Gregory J. Byrne and Dr. Cynthia A. Evans, "STS-107 Image Analysis
Team Final Report in Support of the Columbia Accident Investigation,"
NSTS-37384, June 2003. CAIB document CTF076- 155 11657 See
Appendix E.2 for a copy of the report.
R. J. Gomex et ol, "STS-107 Foam Transport Final Report," NSNS-
60506, August 2003.
This section based on information from the following reports: MIT Lincoln
Laboratory "Report on Flight Day 2 Object Analysis," Dr. Brian M.
Kent, Dr. Kueichien C. Hill, and Captain John Gulick, "An Assessment
of Potential Materiol Candidates for the 'Flight Day 2' Radar Object
Observed During the NASA Mission STS-107 (Columbia)", Air Force
Research Laboratory Final Summary Report AFRL-SNS-2003-001, July
20, 2003 (see Appendix E.2); Multiple briefings to the CAIB from Dr.
Brian M. Kent, AFRL/SN (CAIB document CTF076-19782017); Briefing
to the CAIB from HQ AFSPC/XPY, April 18, 2003 (CAIB document
CAB066-13771388).
The water tanks from below the mid-deck floor, along with both Forward
Reaction Control System propellant tanks were recovered in good
condition.
Enterprise was used for the initial Approach and Landing Tests and
ground tests of the Orbiter, but was never used for orbital tests. The
vehicle is now held by the Notional Air and Space Museum. See Jenkins,
Space Shuffle, pp. 205-223, for more information on Enterprise.
Philip Kopfinger and Wanda Sigur, "Impact Test Results of BX-250 In
Support of the Columbia Accident Investigation," ETTP-MS-03-021, July
17, 2003.
Details of the test instrumentation ore in Appendix D.12.
Evaluations of the adjustments in the angle of incidence to account for
rotation ore in Appendix D.12.
The potential damage estimates had great uncertainty because the
database of bending, tension, crushing, and other measures of failure
were incomplete, particularly for RCC material.
Report Vului
AUC3UST 2003
Chapter 4
Other Factors Considered
During its investigation, the Board evaluated every known
factor that could have caused or contributed to the Coliini-
hia accident, such as the effects of space weather on the
Orbiter during re-entry and the specters of sabotage and
terrorism. In addition to the analysis/scenario investiga-
tions, the Board oversaw a NASA "fault tree" investiga-
tion, which accounts for every chain of events that could
possibly cause a system to fail. Most of these factors were
conclusively eliminated as having nothing to do with the
accident; however, several factors have yet to be ruled out.
Although deemed by the Board as unlikely to have con-
tributed to the accident, these are still open and are being
investigated further by NASA. In a few other cases, there
is insufficient evidence to completely eliminate a factor,
though most evidence indicates that it did not play a role in
the accident. In the course of investigating these factors, the
Board identified several serious problems that were not pail
of the accident's causal chain but nonetheless have major
implications for future missions.
In this chapter, a discussion of these potential causal and
contributing factors is divided into two sections. The first
introduces the primary tool used to assess potential causes
of the breakup: the fault tree. The second addres.ses fault
tree items and particularly notable factors that raised con-
cerns for this investigation and. more broadly, for the future
operation of the Space Shuttle.
4.1 Fault Tree
The NAS.'X Accident Investigation Team investigated the
accident using "fault trees," a common organizational tool
in systems engineering. Fault trees are graphical represei'-
tations of every conceivable sequence of events that could
cause a system to fail. The fault tree's uppermost level
illustrates the events that could have directly caused the loss
of Coliinihici by aerodynamic breakup during re-entry. Subse-
quent levels comprise all individual elements or factors that
could cause the failure described immediately above it. In
this way, all potential chains of causation that lead ultimately
to the loss of Coliinihid can be diagrammed, and the behavior
of every subsystem that was not a precipitating cause can be
eliminated from consideration. Figure 4.1-1 depicts the fault
tree structure for the Cohinihici accident investigation.
^
^
q?^ i i _y .
Figure 4.?-]. Accident investigation fault tree structure.
NASA chartered six teams to develop fault trees, one for each
of the Shuttle's major components: the Orbiter, Space Shuttle
Main Engine, Reusable Solid Rocket Motor, Solid Rocket
Booster, External Tank, and Payload. A seventh "systems
integration" fault tree team analyzed failure scenarios involv-
ing two or more Shuttle components. These interdisciplinary
teams included NASA and contractor personnel, as well as
outside experts.
Some of the fault trees are very large and intricate. For in-
stance, the Orbiter fault tree, which only considers events
on the Orbiter that could have led to the accident, includes
234 elements. In contrast, the Systems Integration fault tree,
which deals with interactions among parts of the Shuttle,
includes 29.5 unique multi-element integration faults, 128
Orbiter multi-element faults, and 22 1 connections to the other
Shuttle components. These faults fall into three categories:
induced and natural environments (such as structural inter-
face loads and electromechanical elfects); integrated vehicle
mass properties; and external impacts (such as debris from the
External Tank). Because the Systems Integration team consid-
ered multi-element faults - that is, .scenarios involving several
Shuttle components - it frequently worked in tandem with the
Component teams.
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
In the case of the Cohiinhia accident, there could be two
plausible explanations for the aerodynamic breakup of the
Orbiter: ( 1 ) the Orbiter sustained structural damage that un-
dermined attitude control during re-entry; or (2) the Orbiter
maneuvered to an attitude in which it was not designed to
fly. The former explanation deals with structural damage
initiated before launch, during ascent, on orbit, or during
re-entry. The latter considers aerodynamic breakup caused
by improper attitude or trajectory control by the Orbiter's
Flight Control System. Telemetry and other data strongly
suggest that improper maneuvering was not a factor. There-
fore, most of the fault tree analysis concentrated on struc-
tural damage that could have impeded the Orbiter's attitude
control, in spite of properly operating guidance, navigation,
and flight control systems.
When investigators ruled out a potential cascade of events,
as represented by a branch on the fault tree, it was deemed
"closed." When evidence proved inconclusive, the item re-
mained "open." Some elements could be dismissed at a high
level in the tree, but most required delving into lower levels.
An intact Shuttle component or system (for example, a piece
of Orbiter debris) often provided the basis for closing an ele-
ment. Telemetry data can be equally persuasive: it frequently
demonstrated that a system operated correctly until the loss
of signal, providing strong evidence that the system in ques-
tion did not contribute to the accident. The same holds true
for data obtained from the Modular Auxiliary Data System
recorder, which was recovered intact after the accident.
The closeout of particular chains of causation was exam-
ined at various stages, culminating in reviews by the NASA
Orbiter Vehicle Engineering Working Group and the NASA
Accident Investigation Team. After these groups agreed
to close an element, their findings were forwarded to the
Board for review. At the time of this report's publication,
the Bpard had closed more than one thousand items. A sum-
mary of fault tree elements is listed in Figure 4. 1 -2.
Branch
lotal
Number
of Elements
Number of Open Elements
Likely
Possible
Unlikely
Orbiter
234
3
8
6
SSME
22
0
0
0
RSRM
35
0
0
0
SRB
88
0
4
4
ET
883
6
0
135
Payload
3
0
0
0
Integration
295
1
0
1
Figure 4.1-2. Summary of fault tree elements reviewed by the
Board.
The open elements are grouped by their potential for con-
tributing either directly or indirectly to the accident. The first
group contains elements that may have in any way contrib-
uted to the accident. Here, "contributed" means that the ele-
ment may have been an initiating event or a likely cause of
the accident. The second group contains elements that could
not be closed and may or may not have contributed to the
accident. These elements are possible causes or factors in
this accident. The third group contains elements that could
not be closed, but are unlikely to have contributed to the ac-
cident. Appendix D.3 lists all the elements that were closed
and thus eliminated from consideration as a cause or factor
of this accident.
Some of the element closure efforts will continue after this
report is published. Some elements will never be closed, be-
cause there is insufficient data and analysis to uncondition-
ally conclude that they did not contribute to the accident. For
instance, heavy rain fell on Kennedy Space Center prior to
the launch of STS-107. Could this abnormally heavy rainfall
have compromised the External Tank bipod foam? Experi-
ments showed that the foam did not tend to absorb rain, but
the rain could not be ruled out entirely as having contributed
to the accident. Fault tree elements that were not closed as of
publication are listed in Appendix D.4.
4.2 Remaining Factors
Several significant factors caught the attention of the Board
during the investigation. Although it appears that they were
not causal in the STS-107 accident, they are presented here
for completeness.
Solid Rocket Booster Bolt Catchers
The fault tree review brought to light a significant problem
with the Solid Rocket Booster bolt catchers. Each Solid
Rocket Booster is connected to the External Tank by four
separation bolts: three at the bottom plus a larger one at the
top that weighs approximately 65 pounds. These larger upper
(or "forward") separation bolts (one on each Solid Rocket
Booster) and their associated boll catchers on the External
Tank provoked a great deal of Board scrutiny.
About two minutes after launch, the firing of pyrotechnic
charges breaks each forward separation bolt into two pieces,
allowing the spent Solid Rocket Boosters to separate from
the External Tank (see Figure 4.2-1 ). Two "bolt catchers" on
the External Tank each trap the upper half of a fired separa-
tion bolt, while the lower half stays attached to the Solid
Rocket Booster. As a result, both halves are kept from flying
free of the assembly and potentially hitting the Orbiter. Bolt
catchers have a domed aluminum cover containing an alu-
minum honeycomb matrix that absorbs the fired bolt's en-
ergy. The two upper bolt halves and their respective catchers
subsequently remain connected to the External Tank, which
burns up on re-entry, while the lower hal\es stay with the
Solid Rocket Boosters that are recovered from the ocean.
If one of the bolt catchers failed during STS-107, the result-
ing debris could have damaged Coliinihia's wing leading
edge. Concerns that the bolt catchers may have failed, caus-
ing metal debris to ricochet toward the Orbiter, arose be-
cause the configuration of the bolt catchers used on Shuttle
missions differs in impoilant ways from the design used in
Report Von
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
Bolt _
Catcher
Externol tank
Forward Separation Bolt
fa!!lf!lzJ!BBi=MB*
Figure 4.2-1. A cutaway drawing of f/ie forward Solid Rockef
Booster bolt catcher and separation bolt assembly.
initial qualification tests.' First, the attachments that cunent-
ly hold bolt catchers in place use bolts threaded into inserts
rather than through-bolts. Second, the test design included
neither the Super Lightweight .Ablative material applied to
the bolt catcher apparatus for thermal protection, nor the
aluminum honeycomb configuration currently used. Also,
during these initial tests, temperature and pressure readings
for the bolt firings were not recorded.
Instead of conducting additional tests to correct for these
discrepancies. NASA engineers qualified the flight design
configuration using a process called "analysis and similar-
ity." The flight configuration was validated using extrapo-
lated test data and redesign specifications rather than direct
testing. This means that N.ASA"s rationale for considering
bolt catchers to be safe for flight is based on limited data
from testing 24 years ago on a model that differs signifi-
cantly from the current design.
Due to these testing deficiencies, the Board recognized
that bolt catchers could have played a role in damaging
Coliinihi(i\ left wing. The aluminum dome could have
failed catastrophically. ablative coating could have come off
in large quantities, or the device could have failed to hold to
its mount point on the External Tank. To determine whether
bolt catchers should be eliminated as a source of debris, in-
vestigators conducted tests to establish a performance base-
line for bolt catchers in their current configuration and also
reviewed radar data to see whether boh catcher failure could
be observed. The results had serious implications: Every
bolt catcher tested failed well below the expected load range
of 6X.000 pounds. In one test, a bolt catcher failed at 44,()()0
pounds, which was two percent below the 46.()()() pounds
generated by a fired separation bolt. This means that the
force at which a separation bolt is predicted to come apart
during flight could exceed the bolt catcher's ability to safely
capture the bolt. If these results are consistent with further
tests, the factor of safety for the bolt catcher system would
be 0.956 - far below the design requirement of 1 .4 (that is,
able to withstand 1 .4 times the maximum load ever expected
in operation).
Every bolt catcher must be inspected (via X-ray) as a final
step in the manufacturing process to ensure specification
compliance. There are specific requirements for film type/
quality to allow sufficient visibility of weld quality (where
the dome is mated to the mounting flange) and reveal any
flaws. There is also a requirement to archive the film for sev-
eral years after the hardware has been used. The manufac-
turer is required to evaluate the film, and a Defense Contract
Management Agency representative certifies that require-
ments have been met. The substandard peiformance of the
Summa bolt catchers tested by NASA at Marshall Space
Flight Center and subsequent investigation revealed that
the contractor's use of film failed to meet quality require-
ments and, because of this questionable quality, there were
"probable" weld defects in most of the archived film. Film
of STS-107's bolt catchers (serial numbers I and 19. both
Summa-manufactured), was also determined to be substan-
dard with "probable" weld defects (cracks, porosity, lack
of penetration) on number 1 (left Solid Rocket Booster to
External Tank attach point). Number 19 appeared adequate,
though the substandard film quality leaves some doubt.
Further investigation revealed that a lack of qualified
non-destructive inspection technicians and differing inter-
pretations of inspection requirements contributed to this
oversight. United Space Alliance, NASA's agent in pro-
curing bolt catchers, exercises limited process oversight
and delegates actual contract compliance verification to
the Defense Contract Management Agency. The Defense
Contract Management Agency interpreted its responsibility
as limited to certifying compliance with the requirement for
X-ray inspections. Since neither the Defense Contract Man-
agement Agency nor United Space Alliance had a resident
non-destructive inspection specialist, they could not read the
X-ray film or certify the weld. Consequently, the required
inspections of weld quality and end-item certification were
not properly performed. Inadequate oversight and confusion
over the requirement on the parts of NASA. United Space
Alliance, and the Defense Contract Management Agency all
contributed to this problem.
In addition, STS-107 radar data from the U.S. Air Force
Eastern Range tracking system identified an object with a
radar cross-section consistent with a bolt catcher departing
the Shuttle stack at the time of Solid Rocket Booster separa-
tion. The resolution of the radar return was not sufficient to
definitively identify the object. However, an object that has
about the same radar signature as a bolt catcher was seen on
at least five other Shuttle missions. Debris shedding during
Solid Rocket Booster separation is not an unusual event.
However, the size of this object indicated that it could be a
potential threat if it came close to the Orbiter after coming
off the stack.
Report Voli
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Although bolt catchers can be neither definitively excluded
nor included as a potential cause of left wing damage to
Coliiinhia. the impact of such a large object would likely
have registered on the Shuttle stack's sensors. The indefinite
data at the time of Solid Rocket Booster separation, in tan-
dem with overwhelming evidence related to the foam debris
strike, leads the Board to conclude that bolt catchers are
unlikely to have been involved in the accident.
Findings:
H-4.2-1
F4.2-
F4.2-3
F4.2-4
The certification of the bolt catchers flown on
STS-107 was accomplished by extrapolating
analysis done on similar but not identical bolt
catchers in original testing. No testing of flight
hardware was performed.
Board-directed testing of a small sample size
demonstrated that the "as-flown" bolt catchers
do not have the required 1.4 margin of safety.
Quality assurance processes for bolt catchers (a
Critical ity I subsystem) were not adequate to as-
sure contract compliance or product adequacy.
An unknown metal object was seen separating
from the stack during Solid Rocket Booster sepa-
ration during six Space Shuttle missions. These
objects were not identified, but were character-
ized as of little to no concern.
Recommendations:
R4.2-
Test and qualify the flight hardware bolt catch-
ers.
Kapton Wiring
Because of previous problems with its use in the Space Shut-
tle and its implication in aviation accidents, Kapton-insulated
wiring was targeted as a possible cause of the Coliiinhia
accident. Kapton is an aromatic polyimide insulation that
the DuPont Corporation developed in the 1960s. Because
Kapton is lightweight, nonflammable, has a wide operating
temperature range, and resists damage, it has been widely
used in aircraft and spacecraft for more than 30 years. Each
Orbiter contains 140 to 157 miles of Kapton-insulated wire,
approximately 1,700 feet of which is inaccessible.
Despite its positive properties, decades of use have revealed
one significant problem that was not apparent during its
development and initial use: Kapton insulation can break
down, leading to a phenomenon known as arc tracking.
When arc tracking occurs, the insulation turns to carbon, or
carbonizes, at teinperatures of 1 , 100 to 1 ,200 degrees Fahr-
enheit. Carbonization is not the same as combustion. Dur-
ing tests unrelated to Columbia. Kapton wiring placed in an
open flame did not continue to bum when the wiring was
removed from the flame. Nevertheless, when carbonized,
Kapton becomes a conductor, leading to a "soft electrical
short" that causes systems to gradually fail or operate in
a degraded fashion. Improper installati()n and inishandling
during inspection and maintenance can also cause Kapton
insulation to split, crack, tiake, or otherwise physically de-
grade.- (Arc tracking is pictured in Figure 4.2-2.)
Figure 4.2-2. Arc tracking damage ir^ Kapton wiring.
Perhaps the greatest concern is the breakdown of the wire's
insulation when exposed to moisture. Over the years, the
Federal Aviation .Administration has undertaken extensive
studies into wiring-related issues, and has issued Advi-
sory Circulars (2.5-16 and 43. 13- IB) on aircraft wiring
that discuss using aromatic polyimide insulation. It was
discovered that as long as the wiring is designed, installed,
and maintained properly, it is safe and reliable, it was also
discovered, however, that the aromatic polyimide insulation
does not function well in high-moisture environments, or
in installations that require large or frequent flexing. The
military had discovered the potentially undesirable aspects
of aromatic polyimide insulation much eariier. and had ef-
fectively banned its use on new aircraft beginning in 19K3.
These rules, however, apply only to pure polyimide insula-
tion; various other insulations that contain polyimide are
still used in appropriate areas.
The first extensive scnitiny of Kapton wiring on any of the
Orbiters occurred during Columbia's third Orbiter Major
Modification period, after a serious system malfunction dur-
ing the STS-93 launch of Coliiiiibia in July 1999. A short cir-
cuit five seconds after liftoff caused two of the six Main En-
gine Controller computers to lose power, which could have
caused one or two of the three Main Engines to shut down.
The ensuing investigation identified damaged Kapton wire
as the cau.se of the malfunction. In order to identify and cor-
rect such wiring problems, all Orbiters were grounded for an
initial (partial) inspection, with more extensive inspections
planned during their next depot-level maintenance. During
Columbia's subsequent Orbiter Major Modification, wiring
was inspected and redundant system wiring in the same bun-
dles was separated to prevent arc tracking damage. Nearly
4,900 wiring nonconformances (conditions that did not
meet specifications) were identified and corrected. Kapton-
related problems accounted for approximately 27 percent of
the nonconformances. This examination revealed a strong
ccurelation between wire damage and the Orbiter areas that
had experienced the most foot traffic during maintenance
and modification.'
Report V i
August 2QQ3
COLUMBIA
ACCIDENT INVESTIGATION BDARD
Other aspects of Shuttle operation may degrade Kapton
wiring. In orbit, atomic oxygen acts as an oxidizing agent,
causing chemical reactions and physical erosion that can
lead to mass loss and surface property changes. Fortunately,
actual exposure has been relatively limited, and inspections
show that degradation is minimal. Laboratory tests on Kap-
ton also confirm that on-orbit ultraviolet radiation can cause
delamination, shrinkase, and wrinklins.
Finding:
F4.2-5
Figure 4.2-3. Typical wiring bundle imide Orbifer wing.
A typical wiring bundle is shown in Figure 4.2-3. Wiring
nonconformances are connected by rerouting, reclamping.
or installing additional insulation such as convoluted tub-
ing, insulating tape, insulating sheets, heat shrink sleeving,
and abrasion pads (see Figure 4.2-4). Testing has shown
that wiring bundles usually stop arc tracking when wires are
physically separated from one another. Funher testing un-
der conditions simulating the Shuttle's wiring environment
demonstrated that arc tracking does not progress beyond six
inches. Based on these results. Boeing recommended that
NASA separate all critical paths from larger wire bundles and
individually protect them for a minimum of six inches be-
yond their separation points.^ This recommendation is being
adopted through modifications performed during scheduled
Orbiter Major Modihcations. For example, analysis of tele-
metered data from 14 of Columbia 'i left wing sensors (hy-
draulic line/wing skin/wheel temperatures, tire pressures, and
landing gear downlock position indication) provided failure
signatures supporting the scenario of left-wing thermal intru-
sion, as oppo.sed to a catastrophic failure (extensive arc track-
ing) of Kapton wiring. Actual NASA testing in the months
following the accident, during which wiring bundles were
subjected to intense heat (ovens, blowtorch, and arc jet), veri-
fied the failure signature analyses. Finally, extensive testing
and analysis in years prior to STS-107 showed that, with the
low currents and low voltages associated with the Orbiter's
instrumentation system (such as those in the left wing), the
probability of arc tracking is commensurately low.
Based on the extensive wiring inspections, main-
tenance, and modifications prior to STS-107,
analysis of sensor/wiring failure signatures, and
the alignment of the signatures with themial
intrusion into the wing, the Board found no
evidence that Kapton wiring problems caused or
contributed to this accident.
Recommendation:
R4.2-2 As pail of the Shuttle Service Life Extension Pro-
gram and potential 40-year service life, develop a
state-of-the-art means to inspect all Orbiter wir-
ing, including that which is inaccessible.
Crushed Foam
Based on the anticipated launch date of STS-107, a set
of Solid Rocket Boosters had been stacked in the Vehicle
Assembly Building and a Lightweight Tank had been at-
tached to them. A reshuffling of the manifest in .luly 2002
resulted in a delay to the STS-107 mission.^ It was decided
to use the already-stacked Solid Rocket Boosters for the
STS-II3 mission to the international Space Station. All
flights to the International Space Station use Super Light-
weight Tanks, meaning that the External Tank already mated
would need to be removed and stored pending the rescheduled
STS-107 mission. Since External Tanks are not stored with
the bipod struts attached, workers at the Kennedy Space
Center removed the bipod strut from the Lightweight Tank
before it was lifted into a storage cell."
Following the de-mating of the bipod strut, an area of
crushed PDL-1034 foam was found in the region beneath
where the left bipod strut attached to the tank's -Y bipod
fitting. The region measured about 1.5 inches by 1.25 inches
by 0.187 inches and was located at roughly the five o'clock
position. Foam thickness in this region was 2.187 inches.
Examples of Harness Protection
Silicon Rubber Extrusion ""
Figure 4.2-4. Typical wiring harness profecfion methods.
Report Volume: I
1ST Z OO 3
COLUMBIA
ACCIDENT INVESTIGATION BDARO
The crushed foam was exposed when the bipod strut was
removed. This constituted an unacceptable condition and
required a Problem Report write-up.^
NASA conducted testing at the Michoud Assembly Facility
and at Kennedy Space Center to determine if crushed foam
could have caused the loss of the left bipod ramp, and to de-
termine if the limits specified in Problem Report procedures
were sufficient for safety."
Kennedy engineers decided not to take action on the crushed
foam because it would be covered after the External Tank
was mated to a new set of bipod struts that would connect
it to Columbia, and the struts would sufficiently contain and
shield the crushed foam." An inspection after the bipod struts
were attached determined that the area of crtished foam was
within limits specified in the drawing for this region.'"
STS-107 was therefore launched with crushed foam behind
the clevis of the left bipod strut. Crushed foam in this region
is a routine occurrence because the foam is poured and shaved
so that the mating of the bipod strut to the bipod fitting results
in a tight fit between the bipod strtit and the foam.
Pre-launch testing showed that the extent of crushed foam
did not exceed limits." In these tests, red dye was wicked
into the crushed (open) foam cells, and the damaged and
dyed foam was then cut out and examined. Despite the ef-
fects of crushing, the foam's thickness around the bipod at-
tach point was not sub.stantially reduced; the foam effective-
ly maintained insulation against ice and frost. The crushed
foam was contained by the bipod struts and was subjected to
little or no airflow.
Finding:
F4.2-6
Crushed foam does not appear to have contrib-
uted to the loss of the bipod foam ramp off the
External Tank during the ascent of STS- 107.
Recommendations:
• None
Hypergolic Fuel Spill
Concerns that hypergolic (ignites spontaneously when
mixed) fuel contamination might have contributed to the
accident led the Board to investigate an August 20, 1999,
hydrazine spill at Kennedy Space Center that occurred while
Columbia was being prepared for shipment to the Boeing
facility in Palmdale, California. The spill occurred when a
maintenance technician disconnected a hydrazine fuel line
without capping it. When the fuel line was placed on a main-
tenance platform. 2.25 ounces of the volatile, corrosive fuel
dripped onto the trailing edge of the Orbiter's left inboard
elevon. After the spill was cleaned up, two tiles were re-
moved for inspection. No damage to the control surface skin
or structure was found, and the tiles were replaced.'^
United Space Alliance briefed all employees working with
these systems on procedures to prevent another spill, and on
November 1, 1999, the Shuttle Operations Advisory Group
was briefed on the corrective action that had been taken.
Finding:
F4.2-7 The hypergolic spill was not a factor in this ac-
cident.
Recommendations:
• None
Space Weather
Space weather refers to the action of highly energetic par-
ticles in the outer layers of Earth's atmosphere. Eruptions of
particles from the sun are the primary source of space weath-
er events, which fluctuate daily or even more frequently. The
most common space weather concern is a potentially harmful
radiation dose to astronauts during a mission. Particles can
also cau.se structural damage to a vehicle, harm electronic
components, and adversely affect communication links.
After the accident, several researchers contacted the Board
and NASA with concerns about unusual space weather
just before Columbia started its re-entry. A coronal mass
ejection, or solar flare, of high-energy particles from the
outer layers of the sun's atmosphere occurred on January 3 1 ,
2003. The shock wave from the solar flare passed Earth at
about the same time that the Orbiter began its de-orbit burn.
To examine the possible effects of this solar flare, the Board
enlisted the expertise of the Space Environmental Center of
the National Oceanic and Atmospheric Administration and
the Space Vehicles Directorate of the Air Force Research
Laboratory at Hanscom Air Force Base in Massachusetts.
Measurements from multiple space- and ground-based sys-
tems indicate that the solar flare occuired near the edge of
the sun (as observed from Earth), reducing the impact of the
subsequent shock wave to a glancing blow. Most of the ef-
fects of the solar flare were not observed on Earth until six
or more hours after Columbia broke up. See Appendix D.5
for more on space weather effects.
Finding:
F4.2-8 Space weather was not a factor in this accident.
Recommendations:
• None
Asymmetric Boundary Layer Transition
Columbia had recently been through a complete refurbish-
ment, including detailed inspection and certification of all
lower wing surface dimensions. Any grossly protruding
gap fillers would have been observed and repaired. Indeed,
though investigators found that Columbia's reputation for a
rough left wing was well deserved prior to STS-75, quantita-
tive measurements show that the measured wing roughness
was below the fleet average by the launch of STS-107."
Report Voli
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Finding:
F4.2-9 A "rough wing" was not a factor in this accident.
Recommendations:
• None
Training and On-Orbit Performance
All mission-specific training requirements for STS-107
launch and flight control operators were completed before
launch with no perfonnance problems. However, seven
flight controllers assigned to the mission did not have
current recertitications at the time of the Flight Readiness
Review, nor were they certified by the mission date. (Most
flight controllers must recertify for their positions every 18
months.) The Board has determined that this oversight had
no bearing on mission performance (see Chapter 6). The
Launch Control Team and crew members held a full "dress
rehearsal" of the launch day during the Terminal Countdown
Demonstration Test. See Appendix D. I for additional details
on training for STS-107.
Because the majority of the mission was completed before
re-entry, an assessment of the training preparation and
flight readiness of the crew, launch controllers, and Hight
controllers was based on the documented peiformance
of mission duties. All STS-107 personnel performed
satisfactorily during the launch countdown, launch,
and mission. Crew and mission controller actions were
consistent with re-entry procedures.
There were a few incorrect switch movements by the
crew during the mission, including the configuration of an
inter-communications switch and an accidental bump of
a rotational hand controller (which affected the Orbiter's
attitude) after the de-orbit burn but prior to Entry Interface.
The inter-communications switch error was identified and
then corrected by the crew; both the crew and Mission
Control noticed the bump and took the necessai^ steps to
place the Orbiter in the correct attitude. Neither of these
events was a factor in the accident, nor are they considered
training or performance issues. Details on STS-107 on-orbit
operations are in Appendix D.2.
Find
mg:
F4.2-10
The Board concludes that training and on-orbit
considerations were not factors in this accident.
Recommendations:
• None
Payloods
To ensure that a payload malfunction did not cause or con-
tribute to the Coliimhiu accident, the Board conducted a
thorough examination of all pay loads and their integration
with the Orbiter's systems. The Board reviewed all down-
linked payload telemetry data during the mission, as well as
all payload hardware technical documentation. Investigators
assessed every payload readiness review, safety review, and
payload integration process used by NASA, and interviewed
individuals involved in the payload process at both Johnson
and Kennedy Space Centers.
The Board's review of the STS-107 Flight Readiness Review,
Payload Readiness Review. Payload Safety Review Panel,
and Integrated Safety Assessments of experiment payloads
on STS-107 found that all pay load-associated hazards were
adequately identified, accounted for, and appropriately miti-
gated. Payload integration engineers encountered no unique
problems during SPACEH AB integration, there were no pay-
load constraints on the launch, and there were no guideline
violations during the payload preparation process.
The Board evaluated 1 1 payload anomalies, one of which
was significant. A SPACEHAB Water Separator Assembly
leak under the aft sub-floor caused an electrical short and
subsequent shutdown of both Water Separator Assemblies.
Ground and flight crew responses sufficiently addressed these
anomalies during the mission. Circuit protection and telem-
etry data further indicate that during re-entry, this leak could
not have produced a similar electrical short in SPACEHAB
that might have affected the main Orbiter power supply.
The Board detemiined that the powered payloads aboard
STS-107 were performing as expected when the Orbiter's
signal was lost. In addition, all potential "fault-tree" payload
failures that could have contributed to the Orbiter breakup
were evaluated using real-time downlinked telemetry, debris
analysis, or design specification analysis. These analyses in-
dicate that no such failures occurred.
Several experiments within SPACEHAB were flammable,
used flames, or involved combustible materials. All down-
linked SPACEHAB telemetry was normal through re-entry,
indicating no unexpected rise in temperature within the
module and no increases in atmospheric or hull pressures.
All fire alarms and indicators within SPACEHAB were op-
erational, and they detected no smoke or fire. Gas percent-
ages within SPACEHAB were also within limits.
Because a major shift in the Orbiter's center of gravity
could potentially cause flight-control or heat management
problems, researchers investigated a possible shifting of
equipment in the payload bay. Telemetrj' during re-entry
indicated that all payload cooling loops, electrical wiring,
and communications links were functioning as expected,
supporting the conclusion that no payload came loose dur-
ing re-entry. In addition, there are no indications from the
Orbiter's telemetry that any flight control adjustments were
made to compensate for a change in the Orbiter's center of
gravity, which indicates that the center of gravity in the pay-
load bay did not shift during re-entry.
The Board explored whether the pressurized SPACEHAB
module may have ruptured during re-entry. A rup Hire could
breach the fuselage of the Orbiter or force open the pay-
load bay doors, allowing hot gases to enter the Orbiter. All
downlinked payload telemetry indicates that there was no
decompression of SPACEHAB prior to loss of signal, and
Report volume
(Abovej The SPACEHAB Research Double Module (left) and Hitchhiker Carrier are lowered foward Columbia's payload bay on May 23,
2002. The Fast Reaction Experiments Enabling Science, Tecfino/ogy, Applications and Research (FREESTAR) is on the Hitchhiker Carrier.
(Below) Columbia's payload bay doors are ready to be closed over the SPACEHAB Research Double Module on June 14, 2002.
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARD
no dramatic increase in internal temperature or change in the
air composition. This analysis suggests that the pressurized
SPACEHAB module did not rupture during re-entry (see
Appendix D.6.).
Finding:
F4.2-II
The payloads Columbia carried were not a factor
in this accident.
Recommendations:
• None
Willful Damage and Security
During the Board's investigation, suggestions of willful
damage, including the possibility of a terrorist act or sabo-
tage by a disgruntled employee, surfaced in the media and
on various Web sites. The Board assessed such theories,
giving particular attention to the unprecedented security
precautions taken during the launch of STS-i07 because of
prevailing national security concerns and the inclusion of an
Israeli crew member.
Speculation that Columbia was shot down by a missile was
easily dismissed. The Orbiter's altitude and speed prior
to breakup was far beyond the reach of any air-to-air or
surface-to-air missile, and telemetry and Orbiter support
system data demonstrate that events leading to the breakup
began at even greater altitudes.
The Board's evaluation of whether sabotage played any
role included several factors: security planning and counter-
measures, personnel and facility security, maintenance and
processing procedures, and debris analysis.
To rule out an act of sabotage by an employee with access
to these facilities, maintenance and processing procedures
were thoroughly reviewed. The Board also interviewed em-
ployees who had access to the Orbiter.
The processes in place to detect anything unusual on the Or-
biter. from a planted explosive to a bolt incorrectly torqued.
make it likely that anything unusual would be caught during
the many checks that employees perform as the Orbiter nears
final closeout (closing and sealing panels that have been left
open for inspection) prior to launch, in addition, the process
of securing various panels before launch and taking close-
out photos of hardware (see Figure 4.2-5) almost always
requires the presence of more than one person, which means
a saboteur would need the complicity of at least one other
employee, if not more.
Debris from Columbia was examined for traces of explo-
sives that would indicate a bomb onboard. Federal Bureau
of Investigation laboratories provided analysis. Laboratory
technicians took multiple samples of debris specimens and
compared them with swabs from Atlantis and Discovery.
Visual examination and gas chromatography with chemi-
luminescence detection found no explosive residues on any
specimens that could not be traced to the Shuttle's pyrotech-
Figure 4.2-5. Ai left, a wing secfion open for inspection; at right,
wing access closed off after inspection.
nic devices. Additionally, telemetry and other data indicate
these pyrotechnic devices operated normally.
In its review of willful damage scenarios mentioned in the
press or submitted to the investigation, the Board could not
find any that were plausible. Most demonstrated a basic lack
of knowledge of Shuttle processing and the physics of explo-
sives, altitude, and thermodynamics, as well as the processes
of maintenance documentation and employee screening.
NAS.A and its contractors have a comprehensive security
system, outlined in documents like NASA Policy Directive
I600.2A. Rules, procedures, and guidelines address topics
ranging from foreign travel to information security, from se-
curity education to investigations, and from the use offeree
to security for public tours.
The Board examined .security at NASA and its related fa-
cilities through a combination of employee interviews, site
visits, briefing reviews, and discussions with security per-
sonnel. The Board focused primarily on reviewing the capa-
bility of unauthorized access to Shuttle system components.
Facilities and programs examined for security and sabotage
potential included ATK Thiokol in Utah and its Reusable
Solid Rocket Motor production, the Michoud Assembly Fa-
cility in Louisiana and its External Tank production, and the
Kennedy Space Center in Florida for its Orbiter and overall
integration responsibilities.
The Board visited the Boeing facility in Palmdale, Califor-
nia; Edwards Air Force Base in California; Stennis Space
Center in Bay St. Louis. Mississippi; Marshall Space Flight
Center near Huntsville, Alabama; and Cape Canaveral Air
Force Station in Florida. These facilities exhibited a variety
of security processes, according to each site's unique de-
mands. At Kennedy, access to secure areas requires a series
of identification card exchanges that electronically record
each entry. The Michoud Assembly Facility employs similar
measures, with additional security limiting access to a com-
pleted External Tank. The use of closed-circuit television
systems complemented by security patrols is universal.
Employee screening and tracking measures appear solid
across NASA and at the contractors examined by the Board.
The agency relies on standard background and law enforce-
ment checks to prevent the hiring of applicants with ques-
tionable records and the dismissal of those who may accrue
such a record.
REPORT VOI-UI
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
It is difficult for anyone to access critical Shuttle hardware
alone or unobserved by a responsible NASA or contractor
employee. With the exception of two processes when foam
is applied to the External Tank at the Michoud Assembly
Facility, there are no known final closeouts of any Shuttle
component that can be completed with fewer than two peo-
ple. Most closeouts involve at least five to eight employees
before the component is sealed and certified for flight. All
payloads also undergo an extensive review to ensure proper
processing and to verify that they pose no danger to the crew
or the Orbiter.
Security reviews also occur at locations such as the Trans-
oceanic Abort Landing facilities. These sites are assessed
prior to launch, and appropriate measures are taken to
guarantee they are secure in case an emergency landing is
required. NASA also has contingency plans in place, includ-
ing dealing with bioterrorism.
Both daily and launch-day security at the Kennedy Space
Center has been tightened in recent years. Each Shuttle
launch has an extensive security countdown, with a variety
of checks to guarantee that signs are posted, beaches are
closed, and patrols are deployed. K-9 patrols and helicopters
guard the launch area against intrusion.
Because the STS-107 manifest included Israel's first astro-
naut, security measures, developed with National Security
Council approval, went beyond the normally stringent pre-
cautions, including the development of a Security Support
Plan.
a review of on-board accelerometer data rules out a major
strike, micrometeoroids or space debris cannot be entirely
ruled out as a potential or contributing factor.
Micrometeoroids, each usually no larger than a grain of
sand, are numerous and particularly dangerous to orbiting
spacecraft. Traveling at velocities that can exceed 20,000
miles per hour, they can easily penetrate the Orbiter's
skin. In contrast to micrometeoroids, orbital debris gener-
ally comes from destroyed satellites, payload remnants,
exhaust from solid rockets, and other man-made objects,
and typically travel at far lower velocities. Pieces of debris
four inches or larger are catalogued and tracked by the U.S.
Air Force Space Command so they can be avoided during
flight.
NASA has developed computer models to predict the risk
of impacts. The Orbital Debris Model 2000 (ORDEM2000)
database is used to predict the probability of a micromete-
oroid or space debris collision with an Orbiter, based on its
flight trajectory, altitude, date, and duration. Development
of the database was based on radar tracking of debris and
satellite experiments, as well as inspections of returned
Orbiters. The computer code BUMPER translates expected
debris hits from ORDEM2000 into an overall risk probabil-
ity for each flight. The worst-case scenario during orbital
debris strikes is known as the Critical Penetration Risk,
which can include the depressurization of the crew module,
venting or explosion of pressurized systems, breaching
of the Thermal Protection System, and damage to control
surfaces.
Military aircraft patrolled a 40-mile Federal Aviation Ad-
ministration-restricted area starting nine hours before the
launch of STS-107. Eight Coast Guard vessels patrolled a
three-nautical-mile security zone around Kennedy Space
Center and Cape Canaveral Air Force Station, and Coast
Guard and NASA boats patrolled the inland waterways. Se-
curity forces were doubled on the day of the launch.
Findings:
F4.2- 1 2 The Board found no evidence that willful damage
was a factor in this accident.
F4.2-13 Two close-out processes at the Michoud Assem-
bly Facility are currently able to be performed by
a single person.
F4.2-14 Photographs of every close out activity are not
routinely taken.
Recommendation:
R4.2-3 Require that at least two employees attend all
final closeouts and intertank area hand-spraying
procedures.
Micrometeoroids and Orbital Debris Risks
Micrometeoroids and space debris (often called "space
junk") are among the most serious risk factors in Shuttle
missions. While there is little evidence that micrometeor-
oids or space debris caused the loss of Coliiiuhia, and in fact
NASA guidelines require the Critical Penetration Risk to
be better than 1 in 200, a number that has been the subject
of several reviews. NASA has made changes to reduce the
probability. For STS-107. the estimated risk was 1 in 370.
though the actual as-flown value turned out to be 1 in 356.
The current risk guideline of 1 in 200 makes space debris or
micrometeoroid strikes by far the greatest risk factor in the
Probabilistic Risk Assessment used for missions. Although
1 -in-200 flights may seem to be long odds, and many flights
have exceeded the guideline, the cumulative risk for such
a strike over the 113-flight history of the Space Shuttle
Program is calculated to be 1 in 3. The Board considers
this probability of a critical penetration to be unacceptably
high. The Space Station's micrometeoroid and space debris
protection system reduces its critical penetration risk to
five percent or less over 10 years, which translates into a
per-mission risk of 1 in 1 ,200 with 6 flights per year, or 60
flights over 10 years.
To improve crew and vehicle safety over the next 10 to 20
years, the Board believes risk guidelines need to be changed
to compel the Shuttle Program to identify and, more to the
point, reduce the micrometeoroid and orbital debris threat
to missions.
Findings:
F4.2-15
There is little evidence that Colimihki encoun-
tered either micrometeoroids or orbital debris on
this flight.
9 4
Report V o u u m e I A u b u s t ZOQ3
COLUMBIA
ACCIDENT INVESTIGATION BOARO
F4.2-16 The Board found markedly different criteria for
margins of micrometeoroid and orbital debris
safety between the hitemational Space Station
and the Shuttle.
Recommendation:
R4.2-4 Require the Space Shuttle to be operated with the
same degree of safety for micrometeoroid and
orbital debris as the degree of safety calculated
for the International Space Station. Change the
micrometeoroid and orbital debris safety criteria
from guidelines to requirements.
Orbiter Major Modification
The Board investigated concerns that mistakes, mishaps, or
human error during Columbia s last Orbiter Major Modi-
fication might have contributed to the accident. Orbiters
are removed from service for inspection, maintenance, and
modification approximately every eight flights or three years.
Columbia began its last Orbiter Major Modification in Sep-
tember 1999, completed it in February 2001, and had flown
once before STS-I07. Several aspects of the Orbiter Major
Modification process trouble the Board, and need to be ad-
dressed for future flights. These concerns are discussed in
Chapter 10.
Findings:
F4.2-17
Based on a thorough investigation of maintenance
records and interviews with maintenance person-
nel, the Board found no errors during Columbia's.
most recent Orbiter Major Modification that con-
tributed to the accident.
Recommendations:
• None
Foreign Object Damage Prevention
Problems with the Kennedy Space Center and United Space
Alliance Foreign Object Damage Prevention Program,
which in the Department of Defense and aviation industry
typically falls under the auspices of Quality Assurance, are
related to changes made in 2001. In that year, Kennedy and
Alliance redefined the single term "Foreign Object Damage"
- an industry-standard blanket term - into two terms: "Pro-
cessing Debris" and "Foreign Object Debris."
Processing Debris then became:
Any material, product, substance, tool or aid generally
used during the processing of flight hardware that re-
mains in the work area when not directly in use, or that
is left unattended in the work area ft )r any length of time
during the processing of tasks, or that is left remaining
or forgotten in the work area after the completion of a
task or at the end of a work shift. Also any item, mate-
rial or substance in the work area that should he found
and removed as part of standard housekeeping. Hazard
Recognition and Inspection Program (HRIP) walk-
downs, or as part of "Clean As You Go" practices."*
Foreign Object Debris then became:
Processing debris becomes FOD when it poses a poten-
tial risk to the Shuttle or any of its components, and only
occurs when the debris is found during or subsequent to
a final/flight Closeout Inspection, or subsequent to OMI
S0007 ET Umd SAF/FAC yndkdown.''
These definitions are inconsistent with those of other NASA
centers. Naval Reactor programs, the Department of De-
fense, commercial aviation, and National Aerospace FOD
Prevention Inc. guidelines."' They are unique to Kennedy
Space Center and United Space Alliance.
Because debris of any kind has critical safety implications,
these definitions are important. The United Space Alliance
Foreign Object Program includes daily debris checks by
management to ensure that workers comply with United
Space Alliance's "clean as you go" policy, but United Space
.Alliance statistics reveal that the success rate of daily debris
checks is between 70 and 86 percent.'"
The perception among many interviewees is that these novel
definitions mitigate the impact of Kennedy Mission As-
surance-found Foreign Object Debris on the United Space
Alliance award fee. This is because "Processing Debris"
statistics do not directly affect the award fee. Simply put,
in splitting "Foreign Object Damage" into two categories,
many of the violations are tolerated. Indeed, with 18 prob-
lem reports generated on "lost items" during the processing
of STS-107 alone, the need for an ongoing, thorough, and
stringent Foreign Object Debris program is indisputable.
However, with two definitions of foreign objects - Process-
ing Debris and Foreign Object Debris - the former is por-
trayed as less significant and dangerous than the latter. The
assumption that all debris will be found before flight fails to
underscore the destructive potential of Foreign Object De-
bris, and creates an incentive to simply accept "Processing
Debris."
Finding:
F4.2-I8
Since 2001, Kennedy Space Center has used a
non-standard approach to define foreign object
debris. The industry standard term "Foreign Ob-
ject Damage" has been divided into two catego-
ries, one of which is much more permissive.
Recommendation:
R4.2-5 Kennedy Space Center Quality Assurance and
United Space Alliance must return to the straight-
forward, industry-standard definition of "Foreign
Object Debris." and eliminate any alternate or
statistically deceptive definitions like "processing
debris."
Report Voli
lOUST ZOOS
CDLUMBiA
ACCIDENT INVESTIGATION BOARD
Endnotes for Chapter 4
The citotions that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CAB001-0010, refer to a
document in the Columbia Accident Investigation Board database mointained
by the Department of Justice and archived at the National Archives.
SRB Forward Separation Bolt Test Plan, Document Number 90ENG-
OOXX, April 2, 2003. CAIB document CTF044-62496260.
" Cynthia Furse and Randy Houpt, "Down to the Wire," in the
online version of the IEEE Spectrum magazine, accessed ot http://
www.spectrum.ieee.org/WEBONLY/publicfeature/feb01/wire.html on 2
August 2002.
' Boeing Inspection Report, OV-102 J3, V30/V31 (Wire) Inspection Report,
September 1999-February 2001. CAIB document CTF070-34793501.
Boeing briefing, "Arc Tracking Separation of Critical Wiring Redundancy
Violations", present to NASA by Joe Daileda and Bill Crawford, April 18,
2001. CAIB document CAB033-43774435.
E-mail message from Jim Feeley, Lockheed Martin, Michoud Assembly
Facility, April 24, 2003. This External Tank (ET-93) was originally mated
to the Solid Rocket Boosters and bipod struts in anticipation of an earlier
lounch date for mission STS-107. Since Space Station missions require
the use of a Super Light Weight Tank, ET-93 (which is a Light Weight
Tank) had to be de-mated from the Solid Rocket Boosters so that they
could be mated to such a Super Light Weight Tank. The mating of the
bipod struts to ET-93 was performed in anticipation of an Orbiter mate.
Once STS-107 was delayed and ET-93 had to be de-mated from the Solid
Rocket Boosters, the bipod struts were also de-mated, since they are not
designed to be attached to the External Tank during subsequent Solid
Rocket Booster de-mate/mate operations.
'' "Production Info - Splinter Meeting," presented at Michoud Assembly
Facility, March 13, 2002. TSPB ET-93-ST-003, "Bipod Strut Removal,"
August 1, 2002.
^ PR ET-93-TS-00073, "There Is An Area Of Crushed Foam From The
Installation Of The -Y Bipod," August 8, 2002.
"Crushed Foam Testing." CAIB document CTF059-10561058.
PR ET-93-TS-00073, "There Is An Area Of Crushed Foam From The
Installation Of The -Y Bipod," August 8, 2002; Meeting with John Blue,
USA Engineer, Kennedy Space Center, March 10, 2003.
Lockheed Martin drawing 80911019109-509, "BIPOD INSTL,ET/
ORB,FWD"
"Crushed Foam Testing." CAIB document CTF059-10561058.
Minutes of Orbiter Structures Telecon meeting, June 19, 2001, held with
NASA, KSC, USA, JSC, BNA-Downey, Huntington Beach and Palmdale.
CAIB document CAB033-38743888.
NASA Report NSTS-37398.
Standard Operating Procedure, Foreign Object Debris (FOD) Reporting,
Revision A, Document Number SOP-O-0801-035, October 1, 2002,
United Space Alliance, Kennedy Space Center, pg. 3.
Ibid, pg. 2.
"An effective FOD prevention program identifies potential problems,
corrects negative factors, provides awareness, effective employee
training, and uses industry "lessons learned" for continued improvement.
There is no mention of Processing Debris, but the guidance does address
potential Foreign Object Damoge and Foreign Object Debris. While
NASA has done a good job of complying with almost every area of
this guideline, the document addresses Foreign Object investigations in
o singular sense: "All incidents of actual or potential FOD should be
reported and investigated. These reports should be directed to the FOD
Focal Point who should perform tracking and trending analysis. The focal
point should also assure all affected personnel ore aware of all potential
(near mishap) and actual FOD reports to facilitate feedback ('lessons
learned')."
Space Flight Operations Contract, Performance Measurement System
Reports for January 2003, February 2003, USA004840, issue 014,
contract NAS9-2000.
9 e
Report Volume I
August 2003
Part Two
The Accident Occurred
Many accident investigations do not go far enougii. Tiiey
identify the technical cause of the accident, and then connect
it to a variant of "operator error" - the line worker who forgot
to insert the bolt, the engineer who miscalculated the stress,
or the manager who made the wrong decision. But this is sel-
dom the entire issue. When the determinations of the causal
chain are limited to the technical flaw and individual failure,
typically the actions taken to prevent a similar event in the fu-
ture are also limited; fix the technical problem and replace or
retrain the individual responsible. Putting these corrections in
place leads to another mistake - the belief that the problem is
solved. The Board did not want to make these errors.
Attempting to manage high-risk technologies while mini-
mizing failures is an extraordinary challenge. By their
nature, these complex technologies are intricate, with many
interrelated parts. Standing alone, the components may be
well understood and have failure modes that can be antici-
pated. Yet when these components are integrated into a larg-
er system, unanticipated interactions can occur that lead to
catastrophic outcomes. The risk of these complex systems is
increased when they are produced and operated by complex
organizations that also break down in unanticipated ways.
In our view, the NASA organizational culture had as much
to do with this accident as the foam. Organizational culture
refers to the basic values, norms, beliefs, and practices that
characterize the functioning of an institution. At the most ba-
sic level, organizational culture defines the assumptions that
employees make as they carr> out their work. It is a powerful
force that can persist through reorganizations and the change
of key personnel. It can be a positive or a negative force.
In a report dealing with nuclear wastes, the National Re-
search Council quoted Alvin Weinberg's classic statement
about the "Faustian bargain" that nuclear scientists made
with society. "The price that we demand of society for this
magical energy source is both a vigilance and a longevity of
our social institutions that we are quite unaccustomed to."
This is also true of the space program. At NASA's urging, the
nation committed to building an amazing, if compromised.
vehicle called the Space Shuttle. When the agency did this,
it accepted the bargain to operate and maintain the vehicle
in the safest possible way. The Board is not convinced that
NASA has completely lived up to the bargain, or that Con-
gress and the Administration has provided the funding and
support necessary for NASA to do so. This situation needs to
be addressed - if the nation intends to keep conducting hu-
man space flight, it needs to live up to its part of the bargain.
Part Two of this report examines NASA's organizational,
historical, and cultural factors, as well as how these factors
contributed to the accident. As in Part One, this part begins
with history. Chapter ."^ examines the post-Cluilleii^er his-
tory of NASA and its Human Space Flight Program. This
includes reviewing the budget as well as organizational and
management history, such as shifting management systems
and locations. Chapter 6 documents management perfor-
mance related to Coliinihia to establish events analyzed in
later chapters. The chapter reviews the foam strikes, intense
schedule pressure driven by an artificial requirement to de-
liver Node 2 to the International Space Station by a certain
date, and NASA management's handling of concerns regard-
ing Columbia during the STS-107 mission.
In Chapter 7, the Board presents its views of how high-risk
activities should be managed, and lists the characteristics
of institutions that emphasize high-reliability results over
economic efficiency or strict adherence to a schedule. This
chapter measures the Space Shuttle Program's organizational
and management practices against these principles and finds
them wanting. Chapter? defines the organizational cause and
offers recommendations. Chapter 8 draws from the previous
chapters on histoiy. budgets, culture, organization, and safety
practices, and analyzes how all these factors contributed to
this accident. This chapter captures the Board's views of the
need to adjust management to enhance safety margins in
Shuttle operations, and reaffirms the Board's position that
without these changes, we have no confidence that other
"corrective actions" will improve the safety of Shuttle opera-
tions. The changes we recommend will be difficult to accom-
plish - and will be internally resisted.
Report vouume i
AUBUST 2003
f=n:ri r-
Chapter 5
From Challenger
to Columbia
The Board is convinced that the factors that led to the
Coluinhia accident go well beyond the physical mechanisms
discussed in Chapter 3. The causal roots of the accident can
also be traced, in part, to the turbulent post-Cold War policy
environment in which NASA functioned during most of the
years between the destruction of Cluilleiiiier and the loss of
Coluinhia. The end of the Cold War in the late 1980s meant
that the most important political underpinning of NASA's
Human Space Flight Program - U.S. -Soviet space competi-
tion - was lost, with no equally strong political objective to
replace it. No longer able to justify its projects with the kind
of urgency that the superpower struggle had provided, the
agency could not obtain budget increases through the 1990s.
Rather than adjust its ambitions to this new state of affairs,
NASA continued to push an ambitious agenda of space
science and exploration, including a costly Space Station
Program.
If NASA wanted to carry out that agenda, its only recourse,
given its budget allocation, was to become more efficient,
accomplishing more at less cost. The search for cost reduc-
tions led top NASA leaders over the past decade to downsize
the Shuttle workforce, outsource various Shuttle Program
responsibilities - including safety oversight - and consider
eventual privatization of the Space Shuttle Program. The
program's budget was reduced by 40 percent in purchasing
power over the past decade and repeatedly raided to make
up for Space Station cost overruns, even as the Program
maintained a launch schedule in which the Shuttle, a de-
velopmental vehicle, was used in an operational mode. In
addition, the uncertainty of top policymakers in the White
House, Congress, and NASA as to how long the Shuttle
would fly before being replaced resulted in the delay of
upgrades needed to make the Shuttle safer and to extend its
service life.
The Space Shuttle Program has been transformed since the
late 1980s implementation of post-ClHillenf>cr management
changes in ways that raise questions, addressed here and in
later chapters of Part Two, about NASA's ability to safely
operate the Space Shuttle. While it would be inaccurate to
say that NASA managed the Space Shuttle Program at the
time of the Coluinhia accident in the same manner it did prior
to Challeuiicr, there are unfortunate similarities between the
agency's performance and safety practices in both periods.
5.1 The Chaiienger Accident
AND ITS Aftermath
The inherently vulnerable design of the Space Shuttle,
described in Chapter 1, was a product of policy and tech-
nological compromises made at the time of its approval in
1972. That approval process also produced unreasonable
expectations, even myths, about the Shuttle's future per-
formance that NASA tried futilely to fulfill as the Shuttle
became "operational" in 1982. At first, NASA was able to
maintain the image of the Shuttle as an operational vehicle.
During its early years of operation, the Shuttle launched sat-
ellites, perfomied on-orbit research, and even took members
of Congress into orbit. At the beginning of 1986, the goal of
"routine access to space" established by President Ronald
Reagan in 1982 was ostensibly being achieved. That appear-
ance soon proved illusory. On the cold morning of January
28, 1986. the Shuttle Challcni>er broke apart 73 seconds into
its climb towards orbit. On board were Francis R. Scobee,
Michael J. Smith. Ellison S. Onizuka. Judith A. Resnick,
Ronald E. McNair, Sharon Christa McAuliffe. and Gregory
B. Jarvis. All perished.
Rogers Commission
On February 3, 1 986, President Reagan created the Presiden-
tial Commission on the Space Shuttle Challenger Accident,
which soon became known as the Rogers Commission after
its chairman, former Secretary of State William Rogers. The
Commission's report, issued on June 6, 1986, concluded that
the loss of Challeniicr was caused by a failure of the joint
and seal between the two lower segments of the right Solid
Rocket Booster. Hot gases blew past a rubber 0-ring in the
joint, leading to a structural failure and the explosive bum-
REPORT VOUl
IGUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
ing of the Shuttle's hydrogen fuel. While the Rogers Com-
mission identified the failure of the Solid Rocket Booster
joint and seal as the physical cause of the accident, it also
noted a number of NASA management failures that contrib-
uted to the catastrophe.
The Rogers Commission concluded "the decision to launch
the Chdlleiiiier was flawed." Communication failures,
incomplete and misleading information, and poor manage-
ment judgments all figured in a decision-making process
that permitted, in the words of the Commission, "internal
flight safety problems to bypass key Shuttle inanagers." As
a result, if those making the launch decision "had known all
the facts, it is highly unlikely that they would have decided
to launch." Far from meticulously guarding against potential
problems, the Commission found that NASA had required
"a contractor to prove that it was not safe to launch, rather
than proving it was safe."'
The Commission also found that NASA had missed warn-
ing signs of the impending accident. When the joint began
behaving in unexpected ways, neither NASA nor the Solid
Rocket Motor manufacturer Morton-Thiokol adequately
tested the joint to determine the source of the deviations
from specifications or developed a solution to them, even
though the problems frequently recun-ed. Nor did they re-
spond to internal warnings about the faulty seal. Instead,
Morton-Thiokol and NASA management came to see the
problems as an acceptable flight risk -a violation of a design
requirement that could be tolerated. -
During this period of increasing uncertainty about the joint's
performance, the Commission found that NASA's safety
system had been "silent." Of the management, organiza-
tional, and communication failures that contributed to the
accident, four related to faults within the safety system,
including "a lack of problem reporting requirements, inad-
equate trend analysis, misrepresentation of criticality, and
lack of involvement in critical discussions."' The checks
and balances the safety system was meant to provide were
not working.
Still another factor influenced the decisions that led to the
accident. The Rogers Commission noted that the Shuttle's
increasing flight rate in the mid-1980s created .schedule
pressure, including the compression of training schedules,
a shoitage of spare parts, and the focusing of resources on
near-term problems. NASA managers "may have forgot-
ten-partly because of past success, partly because of their
own well-nurtured image of the program-that the Shuttle
was still in a research and development phase."'*
The Challenger accident had profound effects on the U.S.
space program. On August 15, 1986, President Reagan an-
nounced that "NASA will no longer be in the business of
launching private satellites." The accident ended Air Force
and intelligence community reliance on the Shuttle to launch
national security payloads, prompted the decision to aban-
don the yet-to-be-opened Shuttle launch site at Vandenberg
Air Force Base, and forced the development of improved
expendable launch vehicles.'' A 1992 White House advisory
committee concluded that the recovery frtim the Ciicilleitfier
Selected Rogers Commission
Recommendations
• "The faulty Solid Rocket Motor joint and seal must"
be changed. This could be a new design eliminating
the joint or a redesign of the current joint and seal. No
design options should be prematurely precluded because
of schedule, cost or reliance on existing hardware. All
Solid Rocket Motor joints should satisfy the following:
• "The joints should be fully understood, tested and
verified."
• "The certitication of the new design should include:
• Tests which duplicate the actual launch configu-
■ radon as closely as possible.
• Tests over the full range of operating conditions,
including temperature."
• "Full consideration should be given to conducting static
firings of the exact flight configuration in a vertical at-
titude."
• "The Shuttle Program Structure should be reviewed.
The project managers for the various elements of the
Shuttle program felt more accountable to their center
management than to the Shuttle program organization."
• "NASA should encourage the transition of qualified
astronauts into agency management positions."
• "NASA should establish an Office of Safety. Reliability
and Quality Assurance to be headed by an Associate Ad-
ministrator, reporting directly to the NASA Administra-
tor It would have direct authority for safety, reliability,
and quality assurance throughout the agency. The office
should be assigned the work force to ensure adequate
oversight of its functions and should be independent of
other NASA functional and program responsibilities."
• "NASA should establish an STS Safety Advisory Panel
reporting to the STS Program Manager. The charter of
this panel should include Shuttle operational issues,
launch commit criteria, flight rules, flight readiness and >
risk management."
• "The Commission found that Marshall Space Flight
Center project managers, because of a tendency at
Marshall to management isolation, failed to provide full
and timely infomiation bearing on the safety of flight
51-L I the Challenger mission] to other vital elements
of Shuttle program management ... NASA should take
energetic steps to eliminate this tendency at Marshall
Space Flight Center, whether by changes of personnel,
organization, indoctrination or all three.""
• "The nation"s reliance on the Shuttle as its principal ._
space launch capability created a relentless pressure on •.
NASA to increase the flight rate ... NASA must estab- ':
lish a flight rate that is consistent v\'ith its resources."^ ^
disaster cost the country $ 1 2 billion, which included the cost
of building the replacement Orbiter Endeavour."
It took NASA 32 months after the Challenger accident to
redesign and requalify the Solid Rocket Booster and to re-
turn the Shuttle to flight. The first post-accident flight was
launched on September 29, 1988. As the Shuttle returned
to flight, NASA Associate Administrator for Space Flight
1 D Q
VOLUME I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Richard Truly commented. "We will always have to treat
it (the Shuttle] like an R&D test program, even many years
into the future. 1 don't think calling it operational fooled
anybody within the program ... It was a signal to the public
that shouldn't have been sent.""
The Shuttle Program After Return to Flight
.After the Rogers Commission report was issued. NASA made
many of the organizational changes the Commission recom-
mended. The space agency mov ed management of the Space
Shuttle Program from the Johnson Space Center to N.'XSA
Headquarters in Washington. D.C. The intent of this change
was to create a management structure "resembling that of the
.-Xpollo program, with the aim of preventing communication
deficiencies that contributed to the Cluillen^er accident.'"'
NASA also established an Office of Safety. Reliability, and
Quality Assurance at its Headquarters, though that office was
not given the "direct authority" over all of NASA's safety
operations as the Rogers Commission had recommended.
Rather. NASA human space flight centers each retained their
own safety organization reporting to the Center Director.
In the almost 15 years between the return to flight and the
loss of Coliimhia. the Shuttle was again being used on a
regular basis to conduct space-based research, and. in line
with NASA's original 1969 vision, to build and service
a space station. The Shuttle tlew 87 missions during this
period, compared to 24 before CliaUeiiiicr. Highlights from
these missions include the 1990 launch, 1993 repair, and
1999 and 2002 servicing of the Hubble Space Telescope:
the launch of several major planetary probes; a number of
Shuttle-Spacelab missions devoted to scientific research:
nine missions to rendezvous with the Russian space station
Mir; the return of former Mercui^ astronaut Senator John
Glenn to orbit in October 1998: and the launch of the first
U.S. elements of the International Space Station.
After the Cluillenfier accident, the Shuttle was no longer
described as "operational" in the same sense as commercial
aircraft. Nevertheless. NASA continued planning as if the
Shuttle could be readied for launch at or near whatever date
was set. Tying the Shuttle closely to International Space
Station needs, such as crew rotation, added to the urgency
of maintaining a predictable launch schedule. The Shuttle
is currently the only means to launch the already-built
European, Japanese, and remaining U.S. modules needed
to complete Station assembly and to carry and return most
experiments and on-orbit supplies.'" Even after three occa-
sions when technical problems grounded the Shuttle fleet
for a month or more, NASA continued to assume that the
Shuttle could regularly and predictably service the Sta-
tion. In recent years, this coupling between the Station and
Shuttle has become the primary driver of the Shuttle launch
schedule. Whenever a Shuttle launch is delayed, it impacts
Station assembly and operations.
In September 2001. testimony on the Shuttle's achieve-
ments during the preceding decade by NASA's then-Deputy
Associate Administrator for Space Flight William Readdy
indicated the assumptions under which NASA was operat-
ing during that period:
The Space Shuttle has made dramatic improvements in
the capahilities. operations and safety of the system.
The payload-to-orhit performance of the Space Shuttle
has been significantly improved - hy over 70 percent to
the Space Station. The safery of the Space Shuttle has
also been dramatically improved hy reducinf> risk hy
more than a factor of five. In addition, the operahility
of the .system has been significantly improved, with five
minute launch windows - which would not have been
attempted a decade ago - now becoming routine. This
record of success is a testament to the cpiality and
dedication of the Space Shuttle management team and
workforce, both civil servants and contractors."
5.2 The NASA Human Space Flight Culture
Though NASA underwent many management reforms in
the wake of the Challenger accident and appointed new
directors at the Johnson. Marshall, and Kennedy centers, the
agency's powerful human space flight culture remained in-
tact, as did many institutional practices, even if in a modified
form. As a close observer of NASA's organizational culture
has observed. "Cultural norms tend to be fairly resilient ...
The norms bounce back into shape after being stretched or
bent. Beliefs held in common throughout the organization
resist alteration."'' This culture, as will become clear across
the chapters of Part Two of this report, acted over time to re-
sist externally imposed change. By the eve of the Columbia
accident, institutional practices that were in effect at the time
of the Challenger accident - such as inadequate concent
over deviations from expected perfonnance, a silent safety
program, and schedule pressure - had returned to NASA.
Organizational Culture
Organizational culture refers to the basic values, norms,
beliefs, and practices that characterize the functioning of a
particular institution. At the most basic level, organizational
culture defines the assumptions that employees make as they
carp, out their work; it defines "the way we do things here."
An organization's culture is a powerful force that persists
through reorganizations and the departure of key personnel.
The human space flight culture within NASA originated in
the Cold War environment. The space agency itself was cre-
ated in 1958 as a response to the Soviet launch of Sputnik,
the first artificial Earth satellite. In 1961, President John F.
Kennedy charged the new space agency with the task of
reaching the moon before the end of the decade, and asked
Congress and the American people to commit the immense
resources for doing so, even though at the time NASA had
only accumulated 15 minutes of human space flight experi-
ence. With its efforts linked to U.S. -Soviet competition for
global leadership, there was a sense in the NASA workforce
that the agency was engaged in a historic struggle central to
the nation's agenda.
The Apollo era created at NASA an exceptional "can-do"
culture marked by tenacity in the face of seemingly impos-
sible challenues. This culture valued the interaction among
Report Voi-ui
August 2003
1 a 1
COLUMBIA
ACCIDENT iNVESTIGATIDN BOARD
research and testing, hands-on engineering experience, and
a dependence on the exceptional quality of the its workforce
and leadership that provided in-house technical capability to
oversee the work of contractors. The culture also accepted
risk and failure as inevitable aspects of operating in space,
even as it held as its highest value attention to detail in order
to lower the chances of failure.
The dramatic Apollo II lunar landing in July 1969 fixed
NASA's achievements in the national consciousness, and
in history. However, the numerous accolades in the wake
of the moon landing also helped reinforce the NASA staff's
faith in their organizational culture. Apollo successes created
the powerful image of the space agency as a "perfect place,"
as "the best organization that human beings could create to
accomplish selected goals."" During Apollo, NASA was in
many respects a highly successful organization capable of
achieving seemingly impossible feats. The continuing image
of NASA as a "perfect place" in the years after Apollo left
NASA employees unable to recognize that NASA never had
been, and .still was not. perfect, nor was it as symbolically
important in the continuing Cold War struggle as it had been
for its first decade of existence. NASA personnel maintained
a vision Qf their agency that was rooted in the glories of an
earlier time, even as the world, and thus the context within
which the space agency operated, changed around them.
As a result, NASA's human space flight culture never fully
adapted to the Space Shuttle Program, with its goal of rou-
tine access to space rather than further exploration beyond
low-Eailh orbit. The Apollo-era organizational culture came
to be in tension with the more bureaucratic space agency of
the 1970s, whose focus turned from designing new space-
craft at any expense to repetitively flying a reusable vehicle
on an ever-tightening budget. This trend toward bureaucracy
and the as.sociated increased reliance on contracting neces-
sitated more effective communications and more extensive
safety' oversight processes than had been in place during the
Apollo era, but the Rogers Commission found that such fea-
tures were lacking.
In the aftermath of the Challenger accident, these contra-
dictory forces prompted a resistance to externally imposed
changes and an attempt to maintain the internal belief that
NASA was still a "perfect place," alone in its ability to
execute a program of human space flight. Within NASA
centers, as Human Space Flight Program managers strove to
maintain their view of the organization, they lost their ability
to accept criticism, leading them to reject the recommenda-
tions of many boards and blue-ribbon panels, the Rogers
Commission among them.
External criticism and doubt, rather than spurring N.ASA to
change for the better, instead reinforced the will to "impose
the party line vision on the environment, not to reconsider
it," according to one authority on organizational behavior
This in turn led to "flawed decision making, self deception,
introversion and a diminished curiosity about the world
outside the perfect place. "'^ The NASA human space flight
culture the Board found during its investigation manifested
many of these characteristics, in particular a self-confidence
about NASA possessing unique knowledge about how to
safely launch people into space. '^ As will be discussed later
in this chapter, as well as in Chapters 6, 7, and 8, the Board
views this cultural resistance as a fundamental impediment
to NASA's effective organizational performance.
5.3 An Agency Trying to Do Too Much
With Too Little
A strong indicator of the priority the national political lead-
ership assigns to a federally funded activity is its budget. By
that criterion, NASA's space activities have not been high
on the list of national priorities over the pa.st three decades
(see Figure 5.3-1 ). After a peak during the Apollo program,
when NASA's budget was almost four percent of the federal
budget, NASA's budget since the early 1970s has hovered at
one percent of federal spending or less.
Figure 5.3-1. NASA boc/gef as a percenfoge of fhe Federal bud-
get. (Source: NASA History Office)
Particularly in recent years, as the national leadership has
confronted the challenging task of allocating scarce public
resources across many competing demands, NASA has
had difficulty obtaining a budget allocation adequate to its
continuing ambitions. In 1990, the White House chartered a
blue-ribbon committee chaired by aerospace executive Nor-
man Augustine to conduct a sweeping review of NASA and
its programs in response to Shuttle problems and the flawed
mirror on the Hubble Space Telescope."' The review found
that NASA's budget was inadequate for all the programs
the agency was executing, saying that "NASA is currently
over committed in terms of program obligations relative to
resources available-in short, it is trying to do too much, and
allowing too little margin for the unexpected."'^ "A reinvigo-
rated space program," the Augustine committee went on to
say, "will require real growth in the NASA budget of approx-
imately 10 percent per year (through the year 2000) reaching
a peak spending level of about $30 billion per year (in con-
stant 1990 dollars) by about the year 2000." Translated into
the actual dollars of Fiscal Year 2000, that recommendation
would have meant a NASA budget of over $40 billion; the
actual NASA budget for that year was $ 1 3.6 billion."'
During the past decade, neither the White House nor Con-
gress has been interested in "a reinvigorated space program."
Instead, the goal has been a program that would continue to
Report Volume I August Z003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
produce valuable scientific and symbolic payoffs for the na-
tion without a need for increased budgets. Recent budget al-
locations reflect this continuing policy reality. Between 1993
and 2002. the government's discretionary spending grew in
purchasing power by more than 25 percent, defense spend-
ing by \5 percent, and non-defense spending by 40 percent
(see Figure 5.3-2). NASA's budget, in comparison, showed
little change, going from .$14.31 billion in Fi.scal Year 1993
to a low of $13.6 billion in Fiscal Year 2000. and increas-
ing to $14.87 billion in Fiscal Year 2002. This represented a
loss of 13 percent in purchasing power over the decade (see
Figure 5.3-3).'"
1993 FY 1994 FY 1995 FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 FY 2002
Figure 5.3-2. Changes in Federal spending from 7993 through
2002. (Source: NASA Office of tegis/ofiVe Affairs)
Fiscal Year
1965
Real Dollars
(in mi//ionsj
Consfanf Do//ars
(m FY 2002 mi7/,onsj
5,250
24,696
1975
3,229
10,079
11,643
1985
7,573
1993
14,310
17,060
1994
14,570
16,965
1995
13,854
15,790
1996
13,884
15,489
1997
1998
13,709
13,648
14,994
14,641
1999
13,653
13,601
14,443
14,202
2000
2001
14,230
14,559
14,868
2002
14,868
2003
15,335
NA
2004
(requested)
15,255
NA
Figure 5.3-3. NASA Budget. (Source: NASA and OfFice of Mon-
ogemenf and Budget)
The lack of top-level interest in the space program led a
2002 review of the U.S. aerospace sector to observe that
"a sense of lethargy has affected the space industry and
community, instead of the excitement and exuberance that
dominated our early ventures into space, we at times seem
almost apologetic about our continued investments in the
space program."-"
What the Experts Have Said
Warnings of a Shuttle Accident
"Shuttle reliability is uncertain, hut has been estimated to
range between 97 and 99 percent. If the Shuttle reliability
is 98 percent, there would he a 50-50 chance oflosin,^ an
Orhiter within 34 flights . . . The probability ofnuiintainina
at least three Orbiters in the Shuttle fleet declines to less
than 50 percent after flight 113."-'
-The Office of Technology Assessment. 1989
"And although it is a subject that meets with reluctance
to open discussion, and has therefore loo often been
relegated to silence, the stalislicat evidoice indicates
that we are likely to lose another Space Shuttle in the
ne.vt several years . . . probably before the planned Space
Station is completely established on orbit. This would seem
to be the weak link of the civil space program - unpleasant
to recognize, involving all the uncertainties of statistics.
and difficult to resolve. "
-The Augustine Committee. 1990
Shuffle as Developmenfal Vehicle
"Shuttle is also a complex system that has yet to
demonstrate an ability to adhere to a fi.xed .schedule "
-The Augustine Committee. 1990
NASA Human Space Flight Culture
"NASA has not been sufficiently responsive to valid
criticism and the need for change. "'-
-The Augustine Committee. 1990
Faced with this budget situation. NASA had the choice of
either eliminating major prograttis or achieving greater effi-
ciencies while maintaining its existing agenda. Agency lead-
ers chose to attempt the latter. They continued to develop
the space station, continued robotic planetary and scientific
missions, and continued Shuttle-based missions for both sci-
entific and symbolic purposes. In 1994 they took on the re-
sponsibility for developing an advanced technology launch
vehicle in partnership with the private sector. They tried to
do this by becoming more efficient. "Faster, better, cheaper"
became the NASA slogan of the 1990s.-'
The flat budget at NASA particularly affected the hu-
man space flight enterprise. During the decade before the
Cohmihia accident. NASA rebalanced the share of its bud-
get allocated to human space flight from 48 percent of agen-
cy funding in Fiscal Year 1991 to 38 percent in Fiscal Year
1 999. with the remainder going mainly to other science and
technology effoits. On NASA's fixed budget, that meant
Report vout
August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BDARO
Earmarks
Pressure on NASA's budget has come not only Ironi the
White House, but also from the Congress. In recent years
there has been an increasing tendency for the Congress
to add "earmarks" - congressional additit)ns to the NASA
budget request that reflect targeted Members' interests. These
earmarks come out of already-appropriated funds, reducing
the amounts available for the original tasks. For example, as
Congress considered NASA's Fiscal Year 2002 appropriation,
the NASA Administrator told the House Appropriations
subcommittee with jurisdiction over the NASA budget
that the agency was "extremely concerned regarding the
magnitude and number of congressional earmarks" in the
House and Senate versions of the NASA appropriations bill.-"*
He noted "the total number of House and Senate earmarks . . .
is approximately 140 separate items, an increase of nearly
50 percent over FY 2001." These earmarks reHecied "an
increasing fraction of items that circumvent the peer review
process, or involve construction or other objectives that have
no relation to NASA mission objectives." The potential
Fiscal Year 2002 earmarks represented "a net total of $540
million in reductions to ongoing NASA programs to fund this
extremely large number of earmarks.'"-''
the Space Shuttle and the International Space Station were
competing for decreasing resources. In addition, at least
$650 million of NASA's human space flight budget was
used to purchase Russian hardware and services related to
U.S. -Russian space cooperation. This initiative was largely
driven by the Clinton Administration's foreign policy and
national security objectives of supporting the administra-
tion of Boris Yeltsin and halting the proliferation of nuclear
weapons and the means to deliver them.
Space Shuttle Program Budget Patterns
For the past 30 years, tiie Space Shuttle Program has been
NASA's single most expensive activity, and of all NASA's
efforts, that program has been hardest hit by the budget con-
straints of the past decade. Given the high priority assigned
after 1993 to completing the costly International Space Sta-
tion, NASA managers have had little choice but to attempt
to reduce the costs of operating the Space Shuttle. This
left little funding for Shuttle improvements. The squeeze
on the Shuttle budget was even more severe after the Of-
fice of Management and Budget in 1994 insisted that any
cost overrinis in the international Space Station budget be
made up from within the budget allocation for human space
flight, rather than from the agency's budget as a whole. The
Shuttle was the only other large program within that budget
category.
Figures 5.3-4 and 5.3-5 show the traJectoi7 of the Shuttle
budget over the past decade. In Fiscal Year 1993, the out-
going Bush administration requested $4,128 billion for the
Space Shuttle Program; five years later, the Clinton Admin-
istration request was for $2,977 billion, a 27 percent reduc-
tion. By Fiscal Year 2003, the budget request had increased
to $3,208 billion, still a 22 percent reduction from a decade
earlier. With inflation taken into account, over the past de-
cade, there has been a reduction of approximately 40 percent
in the purchasing power of the program's budget, compared
to a reduction of 13 percent in the NASA budget overall.
Fiscal Year
President's
Request to
Congress
Congressional
Appropriation
Change
NASA
Operating Plan *
Change
1993
4,128.0
4,078.0
-50.0
4,052.9
-25.1
1994
4,196.1
3,778.7
-417.4**
3,772.3
-6.4
1995
3,324.0
3,155.1
-168.9
3,155.1
0.0
1996
3,231.8
3,178.8
-53.0
3,143.8
-35.0
1997
3,150.9
3,150.9
0.0
2,960.9
-190.0
1998
2,977.8
2,9278
-50.0
2,912.8
-15.0
1999
3,059.0
3,028.0
-31.0
2,998.3
-29.7
2000
2,986.2
3,011.2
+25.0
2,984.4
-26.8
2001
3,165.7
3,125.7
-40.0
3,118.8
-6.9
2002
3,283.8
3,278.8
-5,0
3,270.0
-8.9
2003
3,208.0
3,252.8
+44.8
Figure 5.3-4. Space Shuttle Program Budget (in millions of dollars). (Source: NASA Office of Space Flight)
* NASA's operating plan is the means for adjusting congressional appropriations among various ocfivifies during the Fiscal year as changing
circumstances dictate. These changes must be approved by NASA's appropriation sutcommiftees before they can be put into effect.
**This reduction primarily reflects the congressional cancellation of the Advanced Solid Rocket Motor Program
Report voli
COLUMBIA
ACCIDENT INVESTIGATION 8DARD
6000
5500
I 5000
5 4500
J 4000
° 3000
1 2500
J 2000
1500
j 40% PurcKoslng Power 45% Porchosing Power
^\^''^''^'^^^''^^''^^ ^"^"^^^'^"^^^^^^^^^^^ ^^
Figure 5.3-5. NASA budget as a percentage of the Federal budget
from 1991 to 2008. (Source; NASA Office of Space Flight)
This budget squeeze also came at a time when the Space
Shuttle Program exhibited a trait common to most aging
systems: increased costs due to greater maintenance require-
ments, a declining second- and third-tier contractor support
base, and deteriorating infrastructure. Maintaining the Shut-
tle was becoming more expensive at a time when Shuttle
budgets were decreasing or being held constant. Only in the
last few years have those budgets begun a gradual increase.
As Figure 5.3-5 indicates, most of the steep reductions in
the Shuttle budget date back to the first half of the 1990s.
In the second half of the decade, the White House Office
of Management and Budget and NASA Headquarters held
the Shuttle budget relatively level by deferring substantial
funding for Shuttle upgrades and infrastructure improve-
ments, while keeping pressure on NASA to limit increases
in operating costs.
5.4 Turbulence in NASA Hits the Space
SHuniE Program
In 1992 the White House replaced NASA Administrator
Richard Truly with aerospace executive Daniel S. Goldin.
a self-proclaimed "agent of change" who held office from
April 1, 1992. to November 17, 2001 (in the process be-
coming the longest-serving NASA Administrator). Seeing
"space exploration (manned and unmanned) as NASA's
principal purpose with Mars as a destiny." as one man-
agement scholar observed, and favoring "administrative
transformation" of NASA, Goldin engineered "not one or
two policy changes, but a torrent of changes. This was not
evolutionar>' change, but radical or discontinuous change."-"
His tenure at NASA was one of continuous turmoil, to which
the Space Shuttle Program was not immune.
Of course, turbulence does not necessarily degrade organi-
zational performance. In some cases, it accompanies pro-
ductive change, and that is what Goldin hoped to achieve.
He believed in the management approach advocated by W.
Edwards Deming. who had developed a series of widely
acclaimed management principles based on his work in
Japan during the "economic miracle" of the 1980s. Goldin
attempted to apply some of those principles to NASA,
including the notion that a corporate headquarters should
Congressional Budget Reductions
In most years. Congress appropriates slightly less for the
Space Shuttle Program than the President requested: in some
cases, these reductions have been requested b> NASA during
the final stages of budget deliberations. After its budget was
passed by Congress. NASA furliier reduced the Shuttle
budget in the agency's operating plan-the plan by which
NASA actually allocates its appropriated budget during
the fiscal year to react to changing program needs. These
released funds were allocated to other activities, both within
the human space flight program and in other parts of the
agency. Changes in recent years include:
Fiscal Year 1997
• NASA transferred $190 million to International Space
Station (ISS).
Fiscal Year 1998
• At NASA's request. Congress transfencd $50 million to
ISS.
• NASA transferred $15 million to ISS.
Fiscal Year 1999
• At NASA's request. Congress reduced Shuttle $.^1 mil-
lion so NASA could fund other requirements.
• NASA reduced Shuttle $32 million bv deferring two
flights: funds transferred to ISS.
• NASA added $2..^ million from ISS to previous NASA
request.
Fiscal Year 2000
• Congress added $25 million to Shuttle budget for up-
grades and transferred $25 million from operations to
upgrades.
• NASA reduced Shuttle $11. 5 million per government-
wide rescission requirement and transferred $15..^ mil-
lion to ISS.
Fiscal Year 2001
• At NASA's request, Conjiress reduced Shuttle budget by
$40 million to fund Mars initiative.
• NASA reduced Shuttle $6.9 million per rescission re-
quirement.
Fiscal Year 2002
• Congress reduced Shuttle budget $50 million to reflect
cancellation of electric Auxiliary Power Unit and added
$20 million for Shuttle upgrades and $25 million for
Vehicle Assembly Building repairs.
• NASA transferred $7. ft million to fund Headquarters re-
quirements and cut $1.2 million per rescission require-
ment.
i Source: Marcia Smith. Congressional Research Service,
Presentation at CAIB Public Hearing. June 12. 200.^|
not attempt to exert bureaucratic control over a complex
organization, but rather set strategic directions and provide
operating units with the authority and resources needed to
pursue those directions. Another Deming principle was that
checks and balances in an organization were unnecessary
Volume I
1ST zona
COLUMBIA
ACCIDENT INVESTIGATION BOARD
and sometimes counteiproductive, and those carrying out
tiie work should bear primary responsibility for its quality.
It is arguable whether these business principles can readily
be applied to a government agency operating under civil
service rules and in a politicized environment. Nevertheless.
Goldin sought to implement them throughout his tenure.-"
Goidin made many positive changes in his decade at NASA.
By bringing Russia into the Space Station partnership in
1993, Goldin developed a new post-Cold War rationale
for the agency while managing to save a program that was
politically faltering. The International Space Station became
NASA's premier program, with the Shuttle serving in a sup-
porting role. Goldin was also instrumental in gaining accep-
tance of the "faster, better, cheaper"-** approach to the plan-
ning of robotic missions and downsizing "an agency that was
considered bloated and bureaucratic when he took it over."-''
Goldin described himself as "sharp-edged" and could often
be blunt. He rejected the criticism that he was sacrificing
safety in the name of efficiency. In 1994 he told an audience
at the Jet Propulsion Laboratory, "When I ask for the budget
to be cut, I'm told it's going to impact safety on the Space
Shuttle ..,1 think that's a bunch of crap."*"
One of Goldin's high-priority objectives was to decrease
involvement of the NASA engineering workforce with the
Space Shuttle Program and thereby free up those skills for
finishing the space station and beginning work on his pre-
fened objective-human exploration of Mars. Such a shift
would return NASA to its exploratory mission. He was often
at odds with those who continued to focus on the centrality
of the Shuttle to NASA's future.
Initial Shuttle Workforce Reductions
With NASA leadership choosing to maintain existing pro-
grams within a no-growth budget, Goldin's "faster, better,
cheaper" motto became the agency's slogan of the 1990s.*'
NASA leaders, however, had little maneuvering room in
which to achieve efficiency gains. Attempts by NASA
Headquarters to shift functions or to close one of the three
human space flight centers were met with strong resistance
from the Centers themselves, the aerospace firms they used
as contractors, and the congressional delegations of the
states in which the Centers were located. This alliance re-
.sembles the classic "iron triangle" of bureaucratic politics,
a conservative coalition of bureaucrats, interest groups, and
congressional subcommittees working together to promote
their common interests. '-
With Center infrastructure off-limits, this left the Space
Shuttle budget as an obvious target for cuts. Because the
Shuttle required a large "standing army" of workers to
1993
7994
1995
7996
7997
7998
7999
2000
2007
2002
Total Workforce
30,091
27,538
25,346
23,625
19,476
18,654
18,068
17,851
18,012
17,462
Total Civil Service
Workforce
3,781
3,324
2,959
2,596
2,195
1,954
1,777
1,786
1,759
1,718
JSC
1,330
1,304
1,248
1,076
958
841
800
798
794
738
KSC
1,373
1,104
1,018
932
788
691
613
626
614
615
MSFC
874
791
576
523
401
379
328
336
327
337
Stennis/Dryden
84
64
55
32
29
27
26
16
14
16
Headquarters
120
61
62
32
20
16
10
10
10
12
Total Contractor
Workforce
26,310
24,214
22,387
21,029
17,281
16,700
16,291
16,065
16,253
15,744
JSC
7,487
6,805
5,887
5,442
* 10,556
10,525
10,733
10,854
11,414
11,445
KSC
9,173
8,177
7,691
7,208
539
511
430
436
439
408
MSFC
9,298
8,635
8,210
7,837
5,650
5,312
4,799
4,444
4,197
3,695
Sfennis/Dryden
267
523
529
505
536
453
329
331
203
196
tieadquarters
85
74
70
37
0
0
0
0
0
0
Figure 5.4-7. Space Shuttle Program workforce. [Source: NASA Office of Space Flight]
* Because Johnson Space Center manages the Space Flight Operations Contract, all United Space Alliance employees are counted as
worfe/ng for Johnson.
Report Vdui
COLUMBIA
ACCIQENT INVESTIGATION BOARD
keep it flying, reducing the size of the Shuttle wori<force
became the primary means by which top leaders lowered the
Shuttle's operating costs. These personnel reduction efforts
started early in the decade and continued through most of
the 1990s. They created substantial uncertainty and tension
within the Shuttle workforce, as well as the transitional diffi-
culties inherent in any large-scale workforce reassignment.
In early 1991, even before Goldin assumed office and less
than three years after the Shuttle had returned to flight after
the Challenger accident. NASA announced a goal of saving
three to five percent per year in the Shuttle budget over five
years. This move was in reaction to a perception that the
agency had overreacted to the Rogers Commission recom-
mendations - for example, the notion that the many layers of
safety inspections involved in preparing a Shuttle for flight
had created a bloated and costly safety program.
From 1991 to 1994, NASA was able to cut Shuttle operating
costs by 21 percent. Contractor personnel working on the
Shuttle declined from 28.394 to 22.387 in these three years,
and NASA Shuttle staff decreased from 4.031 to 2,959."
Figure 5.4-1 shows the changes in Space Shuttle workforce
over the past decade. A 1994 National Academy of Public
.Administration review found that these cuts were achieved
primarily through "operational and organizational efficien-
cies and consolidations, with resultant reductions in staffing
levels and other actions which do not significantly impact
basic program content or capabilities."*^
NASA considered additional staff cuts in late 1994 and early
1995 as a way of further reducing the Space Shuttle Program
budget. In early 1995. as the national leadership focused its
attention on balancing the federal budget, the projected
five-year Shuttle budget requirements exceeded by $2.5 bil-
lion the budget that was likely to be approved by the White
House Office of Management and Budget.'^ Despite its al-
ready significant progress in reducing costs, NASA had to
make further workforce cuts.
Anticipating this impending need, a 1994-1995 NASA
"Functional Workforce Review" concluded that removing
an additional 5,900 people from the NASA and contractor
Shuttle workforce -just under 1 3 percent of the total - could
be done without compromising safety."' These personnel
cuts were made in Fiscal Years 1996 and 1997. By the end
of 1997, the NASA Shuttle civilian workforce numbered
2, 1 95, and the contractor workforce 1 7,28 1 .
Shifting Shuttle Management Arrangements
Workforce reductions were not the only modifications to the
Shuttle Program in the middle of the decade. In keeping with
Goldin's philosophy that Headquarters should concern itself
primarily with strategic issues, in February 1996 Johnson
Space Center was designated as "lead center" for the Space
Shuttle Program, a role it held prior to the Challenger ac-
cident. This shift was part of a general move of all program
management responsibilities from NASA Headquarters to
the agency's field centers. Among other things, this change
meant that Johnson Space Center managers would have au-
thority over the funding and management of Shuttle activi-
ties at the Marshall and Kennedy Centers. Johnson and Mar-
shall had been rivals since the days of Apollo, and long-term
Marshall employees and managers did not easily accept the
return of Johnson to this lead role.
The shift of Space Shuttle Program management to Johnson
was worrisome to some. The head of the Space Shuttle Pro-
gram at NASA Headquarters, Bryan O'Connor, argued that
transfer of the management function to the Johnson Space
Center would return the Shuttle Program management to the
flawed structure that was in place before the Challenger ac-
cident. "It is a safety issue." he said, "we ran it that way (with
program management at Headquarters, as recommended by
the Rogers Commission | for 10 years without a mishap and
I didn't see any reason why we should go back to the way
we operated in the pre-Challenger days."'" Goldin gave
O'Connor several opportunities to present his arguments
against a transfer of management responsibility, but ulti-
mately decided to proceed. O'Connor felt he had no choice
but to resign. '** (O'Connor returned to NASA in 2002 as As-
sociate Administrator for Safety and Mission Assurance.)
In January 1996. Goldin appointed as John.son's director his
close advisor. George W.S. Abbey. Abbey, a space program
veteran, was a firm believer in the values of the original hu-
man space flight culture, and as he assumed the directorship,
he set about recreating as many of the positive features of
that culture as possible. For example, he and Goldin initiat-
ed, as a way for young engineers to get hands-on experience,
an in-house X-38 development program as a prototype for
a space station crew rescue vehicle. Abbey was a powerful
leader, who through the rest of the decade exerted substan-
tial control over all aspects of Johnson Space Center opera-
tions, including the Space Shuttle Program.
Space Flight Operations Contract
By the middle of the decade, spurred on by Vice President Al
Gore's "reinventing government" initiative, the goal of bal-
ancing the federal budget, and the views of a Republican-led
House of Representatives, managers throughout the govern-
ment sought new ways of making public sector programs
more efficient and less costly. One method considered was
transferring significant government operations and respon-
sibilities to the private sector, or "privatization." NASA led
the way toward privatization, serving as an example to other
government agencies.
In keeping with his philo.sophy that NASA should focus on
its research-and-development role, Goldin wanted to remove
NASA employees from the repetitive operations of vari-
ous systems, including the Space Shuttle. Giving primary
responsibility for Space Shuttle operations to the private
sector was therefore consistent with White House and
congressional priorities and attractive to Goldin on its own
terms. Beginning in 1994. NASA considered the feasibility
of consolidating many of the numerous Shuttle operations
contracts under a single prime contractor. At that time, the
Space Shuttle Program was managing 86 separate contracts
held by 56 different firms. Top NASA managers thought that
consolidating these contracts could reduce the amount of
redundant overhead, both for N.ASA and for the contractors
VOLUME I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
themselves. They also wanted to explore whether there were
functions being canied out by NASA that C(Hild be more ef-
fectively and inexpensively catried out by the private sector.
An advisory committee headed by early space flight veteran
Christopher Kraft recommended such a step in its March
1995 report, which became known as the "Kraft Report.""'
(The report characterized the Space Shuttle in a way that the
Board judges to be at odds with the realities of the Shuttle
Program).
The report made the following findings and recommenda-
tions:
• "The Shuttle has become a mature and reliable system
... about as safe as today's technology will provide."
• "Given the maturity of the vehicle, a change to a new
mode of management with considerably less NASA
oversight is possible at this time."
• "Many inefficiencies and difficulties in the current
Shuttle Program can be attributed to the diffuse and
fragmented NASA and contractor structure. Numerous
contractors exist supporting various program elements,
resuUing in ambiguous lines of communication and dif-
fused responsibilities."
• NASA should "consolidate operations under a single-
business entity."
• "The program remains in a quasi-development mode
and yearly costs remain higher than required," and
NASA should "freeze the current vehicle configuration,
minimizing future modifications, with such modifica-
tions delivered in block updates. Future block updates
should implement modifications required to make the
vehicle more re-usable and operational."
• NASA should "restrticture and reduce the overall
Safety, Reliability, and Quality A.ssurance elements
- without reducing safety."*
When he released his committee's report, Kraft said that "if
NASA wants to make more substantive gains in terms of ef-
ficiency, cost savings and better service to its customers, we
think it"s imperative they act on these recommendations ...
,^nd we believe that these savings are real, achievable, and
can be accomplished with no impact to the safe and success-
ful operation of the Shuttle system."'"
Although the Kraft Report stressed that the dramatic changes
it recommended could be made without compromising safe-
ty, there was considerable dissent about this claim. NASA's
.Aerospace Safety Advisory Panel - independent, but often
not very influential - was particularly critical, in May 199.5.
the Panel noted that "the assumption [in the Kraft Report]
that the Space Shuttle systems are now 'mature' smacks of
a complacency which may lead to serious mishaps. The fact
is that the Space Shuttle may never be mature enough to to-
tally freeze the design." The Panel also noted that "the report
dismisses the concerns of many credible sources by labeling
honest reservations and the people who have made them as
being partners in an unneeded 'safety shield' conspiracy.
Since only one more accident would kill the program and
destroy far more than the spacecraft, it is extremely callous"
to make such an accusation."*-
The notion that NASA would further reduce the number of
civil servants working on the Shuttle Program prompted
senior Kennedy Space Center engineer Jose Garcia to send
to President Bill Clinton on August 25, 1995, a letter that
stated, "The biggest threat to the safety of the crew since
the Challenger disaster is presently underway at NASA."
Garcia's particular concern was NASA's "efforts to delete
the "checks and balances' system of processing Shuttles as a
way of saving money ... Historically NASA has employed
two engineering teams at KSC, one contractor and one gov-
ernment, to cross check each other and prevent catastrophic
errors ... although this technique is expensive, it is effec-
tive, and it is the single most important factor that sets the
Shuttle's success above that of any other launch vehicle ...
Anyone who doesn't have a hidden agenda or fear of losing
his job would admit that you can't delete NASA's checks
and balances system of Shuttle processing without affecting
the safety of the Shuttle and crew.""''
NASA leaders accepted the advice of the Kraft Report and
in August 1995 solicited industry bids for the assignment of
Shuttle prime contractor In response, Lockheed Martin and
Rockwell, the two major Space Shuttle operations contrac-
tors, formed a limited liability corporation, with each firm a
50 percent owner, to compete for what was called the Space
Flight Operations Contract. The new corporation would be
known as United Space Alliance.
In November 1995, NASA awarded the operations contract
to United Space Alliance on a sole source basis. (When
Boeing bought Rockwell's aerospace group in December
1996, it also took over Rockwell's 50 percent ownership of
United Space Alliance.) The company was responsible for
61 percent of the Shuttle operations contracts. Some in Con-
gress were skeptical that safety could be maintained under
the new arrangement, which transferred significant NASA
responsibilities to the private sector. Despite these concerns.
Congress ultimately accepted the reasoning behind the
contract.^ NASA then spent much of 1996 negotiating the
contract's terms and conditions with United Space Alliance.
The Space Flight Operations Contract was designed to reward
United Space Alliance for performance successes and penal-
ize its performance failures. Before being eligible for any
performance fees. United Space Alliance would have to meet
a series of safety "gates," which were intended to ensure that
safety remained the top priority in Shuttle operations. The
contract also rewarded any cost reductions that United Space
Alliance was able to achieve, with N.ASA taking 65 percent
of any savings and United Space Alliance 35 percent.^^
NASA and United Space Alliance formally signed the
Space Flight Operations Contract on October I, 1996. ini-
tially, only the major Lockheed Martin and Rockwell Shuttle
contracts and a smaller Allied Signal L'nisys contract were
transferred to United Space Alliance. The initial contractual
period was six years, from October 1996 to September 2002.
NASA exerci.sed an option for a two-year extension in 2002.
and another two-year option exists. The total value of the
contract through the current extension is estimated at $12.8
billion. United Space Alliance currently has approximately
10,000 employees.
rcuST 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
Space Flight Operations Contract
The Space Flight Operations Contract has two major areas
of innovation:
• It replaced the previous "cost-plus" contracts ( in which a
firm was paid for the costs of its activity plus a negotiat-
ed profit) w ith a complex contract structure that included
performance-based and cost reduction incentives. Per-
formance measures include safety, launch readiness,
on-time launch. Solid Rocket Booster recovery, proper
orbital insertion, and successful landing.
• It ea\e additional responsibilities for Shuttle operation,
including safety and other inspections and integration
of the various elements of the Shuttle system, to United
Space Alliance. Many of those responsibilities were pre-
viously within the purview of NASA employees.
Under the Space Flight Operations Contract. United Space
Alliance had overall responsibility for processing selected
Shuttle hardware, including;
• Inspecting and modifying the Orbiters
• Installing the Space Shuttle Main Engines on the Orbit-
ers
• Assembling the sections that make up the Solid Rocket
Boosters
• Attaching the External Tank to the Solid Rocket Boost-
ers, and then the Orbiter to the External Tank
• Recovering expended Solid Rocket boosters
In addition to processing Shuttle hardware, L'nited Space
Alliance is responsible for mission design and planning,
a.stronaut and flight controller training, design and integration
of flight software, payload integration, flight operations,
launch and recovery operations, vehicle-sustaining
engineering, flight crew equipment processing, and operation
and maintenance of Shuttle-specific facilities such as
the Vehicle Assembly Building, the Orbiter Processing
Facility, and the launch pads. United Space Alliance also
provides spare parts for the Orbiters, maintains Shuttle
flight simulators, and provides tools and supplies, including
consumables such as food, for Shuttle missions.
Under the Space Flight Operations Contract. NASA has the
following responsibilities and roles:
• Maintaining ownership of the Shuttles and all other as-
sets of the Shuttle program
• Providing to United Space Alliance the Space Shuttle
Main Engines, the External Tanks, and the Redesigned
Solid Rocket Motor segments for assembly into the
Solid Rocket Boosters
• Managing the overall process of ensuring Shuttle safety
• Developing requirements for major upgrades to all as-
sets
• Participating in the planning vi Shuttle missions, the
directing of launches, and the execution of flights
• Performing surveillance and audits and obtaining tech-
nical insight into contractor activities
• Deciding if and when to "commit to flight" for each mis-
sion*
The contract provided for additional consolidation and then
privatization, when all remaining Shuttle operations would
be transferred from NASA. Phase 2, scheduled tor 1998-
2000, called for the transfer of Johnson Space Center-man-
aged flight software and flight crew equipment contracts
and the Marshall Space Center-managed contracts for the
External Tank, Space Shuttle Main Engine, Reusable Solid
Rocket Motor, and Solid Rocket Booster.
However, Marshall and its contractors, with the concurrence
of the Space Shuttle Program Office at Johnson Space Cen-
ter, successfully resisted the transfer of its contracts. There-
fore, the Space Elight Operations Contract's initial efficiency
and integrated management goals have not been achieved.
The major annual savings resulting from the Space Flight
Operations Contract, which in 1996 were touted to be some
$500 million to $1 billion per year by the early 2000s,
have not materialized. These projections assumed that by
2002. NASA would have put all Shuttle contracts under
the auspices of United Space Alliance, and would be mov-
ing toward Shuttle privatization. Although the Space Flight
Operations Contract has not been as successful in achiev-
ing cost efficiencies as its proponents hoped, it has reduced
some Shuttle operating costs and other expenses. By one
estimate, in its first six years the contract has saved NASA a
total of more than $1 billion.'*''
Privatizing the Space Shuttle
To its proponents, the Space Flight Operations Contract was
only a beginning. In October 1997. United Space Alliance
submitted to the Space Shuttle Program Office a contrac-
tually required plan for privatizing the Shuttle, which the
program did not accept. But the notion of Shuttle privatiza-
tion lingered at NASA Hcadquaiters and in Congress, where
some members advocated a greater private sector role in the
space program. Congress passed the Commercial Space Act
of 1998. which directed the NASA Administrator to "plan for
the eventual privatization of the Space Shuttle Program. ■■^'*
By August 2001. NASA Headquailers prepared for White
House consideration a "Privatization White Paper" that called
for transferring all Shuttle hardware, pilot and commander
astronauts, and launch and operations teams to a private op-
erator. ■*" In September 2001 . Space Shuttle Program Manager
Ron Dittemore released his report on a "Concept of Priva-
tization of the Space Shuttle Program.'"'" which argued that
for the Space Shuttle "to remain safe and viable, it is neces-
sary to merge the required NASA and contractor skill bases"
into a single private organization that would manage human
space flight. This perspective reflected Dittemore "s belief that
the split of responsibilities between NASA and United Space
Alliance was not optimal, and that it was inilikely that NASA
would ever recapture the Shuttle responsibilities that were
transferred in the Space Flight Operations Contract.
Dittemore's plan recommended transferring 700 to 900
NASA employees to the private organization, including:
• Astronauts, including the flight crew members who op-
erate the Shuttle
Report V t
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
• Program and project management, including Space
Shuttle Main Engine, External lank. Redesigned Solid
Rocket Booster, and Extravehicular Activity
• Mission operations, including flight directors and flight
controllers
• Ground operations and processing, including launch
director, process engineering, and flow management
• Responsibility for safety and mission assurance
After such a shift occurred, according to the Dittemore plan,
"the primary role for NASA in Space Shuttle operations ...
will be to provide an SMA [Safety and Mission Assurance]
independent assessment ... utilizing audit and surveillance
techniques."^'
With a change in NASA Administrators at the end of 2001
and the new Bush Administration's emphasis on "competitive
sourcing" of government operations, the notion of wholesale
privatization of the Space Shuttle was replaced with an ex-
amination of the feasibility of both public- and private-sector
Program management. This competitive sourcing was under
examination at the time of the Coliiiiihia accident.
Workforfce TransformaHon and the End of
Downsizing
Workforce reductions instituted by Administrator Goldin as
he attempted to redefine the agency's mission and its overall
organization also added to the turbulence of his reign. In the
1990s, the overall NASA workforce was reduced by 25 per-
cent through normal attrition, early retirements, and buyouts
- cash bonuses for leaving NASA employment. NASA op-
erated under a hiring freeze for most of the decade, making
it difficult to bring in new or younger people. Figure 5.4-2
shows the downsizing of the overall NASA workforce dur-
ing this period as well as the associated shrinkage in NASA's
technical workforce.
NASA Headquarters was particularly affected by workforce
reductions. More than half its employees left or were trans-
ferred in parallel with the 1996 transfer of program manage-
ment responsibilities back to the NASA centers. The Space
Shuttle Program bore more than its share of Headquarters
personnel cuts. Headquarters civil service staff working on
the Space Shuttle Program went from 120 in 1993 to 12 in
2003.
While the overall workforce at the NASA Centers involved
in human space flight was not as radically reduced, the
combination of the general workforce reduction and the
intrt)duction of the Space Flight Operations Contract sig-
nificantly impacted the Centers' Space Shuttle Program civil
service staff. Johnson Space Center went from 1 ,330 in 1993
to 738 in 2002; Marshall Space Flight Center, from 874 to
337; and Kennedy Space Center from 1.373 to 615. Ken-
nedy Director Roy Bridges argued that personnel cuts were
too deep, and threatened to resign unless the downsizing of
his civil service workforce, particularly those involved with
safety issues, was reversed.''"
By the end of the decade. NASA realized that staff reduc-
tions had gone too far. By early 2000. internal and external
24,000^
\
32.000'
s
V
\
1
c
o
F
20,000
1».000
18.000
17,000
- -
^
\
Total Workforce
1
. 1
o
\
_
E
—
c
o
o
0
F
U.OOO
_j
h=
u_
"*-*^
^
Tei:hnical Workforce
10,000
9.000
;
1993 1994 1995 199« 1997 1998 1999 2000 2001 2002 2003
Figure 5.4-2. Downsizing of the overall NASA workforce and ihe
NASA technical workforce.
Studies convinced NASA leaders that the workforce needed
to be revitalized. These studies noted that "five years of
buyouts and downsizing have led to serious skill imbal-
ances and an overtaxed core workforce. As more employees
have departed, the workload and stress |on those] remain-
ing have increased, with a corresponding increase in the
potential for impacts to operational capacity and safety."^'
NASA announced that NASA workforce downsizing would
stop short of the 1 7.500 target, and that its human space flight
centers would immediately hire several hundred workers.
5.5 When to Replace the Space Shuhle?
In addition to budget pressures, workforce reductions, man-
agement changes, and the transfer of government functions
to the private sector, the Space Shuttle Program was beset
during the past decade by uncertainty about when the Shuttle
might be replaced. National policy has vacillated between
treating the Shuttle as a "going out of business" program
and anticipating two or more decades of Shuttle use. As a
result, limited and inconsistent investments have been made
in Shuttle upgrades and in revitalizing the infrastructure to
support the continued use of the Shuttle.
Even before the 1986 ChalU'iii>er accident, when and how
to replace the Space Shuttle with a second generation reus-
able launch vehicle was a topic of discussion among space
policy leaders. In January 1986, the congressionally char-
tered National Commission on Space expressed the need
for a Shuttle replacement, suggesting that "the Shuttle
fleet will become obsolescent by the turn of the century.'"'"'
Shortly after the Clialk'iii^er accident (but not as a reaction
to it). President Reagan announced his approval of "the new
Orient Express" (see Figure 5.5-1). This reusable launch
vehicle, later known as the National Aerospace Plane,
"could, by the end of the decade, take off from Dulles Air-
port, accelerate up to 25 times the speed of sound attaining
low-Earth orbit, or fly to Tokyo within two hours. '"'^ This
goal proved too ambitious, particularly u ithout substantia!
Report Volui
COLUMBIA
ACCIDENT INVESTIGATION BOARD
funding. In 1992. after a $1.7 billion government invest-
ment, the National Aerospace Plane project was cancelled.
This pattern - optimistic pronouncements about a revolu-
tionary Shuttle replacement followed by insufficient gov-
ernment in\estment. and then program cancellation due to
technical difhculties - was repeated again in the 1990s.
Figure 5.5-1. A 7986 artist's conception of the National Aerospace
Plane on o mission fo the Space Station.
In 1994. NASA listed alternatives for access to space
through 2030.
• Upgrade the Space Shuttle to enable flights through
203^0
• Develop a new expendable launcher
• Replace the Space Shuttle with a "leapfrog"" next-gen-
eration advanced technology system that would achieve
order-of-magnitude improvements in the cost effective-
ness of space transportation.""'
Figure 5.5-2. The VeniureStar was intended to replace the Space
Shuttle based on technology developed for the X-33.
Reflecting its leadership's preference for bold initiatives,
NASA chose the third alternative. With White House sup-.,
port,''" NASA began the X-33 project in 1996 as a joint effort
with Lockheed Martin. NASA also initiated the less ambi-
tious X-34 project with Orbital Sciences Corporation. At the
time, the future of commercial space launches was bright,
and political sentiment in the White House and Congress
encouraged an increasing reliance on private-sector solu-
tions for limiting government expenditures. In this context,
these unprecedented joint projects appeared less risky than
they actually were. The hope was that NASA could replace
the Shuttle through private investments, without significant
government spending.
Both the X-33 and X-34 incorporated new technologies.
The X-33 was to demonstrate the feasibility of an aerospike
engine, new Thermal Protection Systems, and composite
rather than metal propcllant tanks. These radically new tech-
nologies were in turn to become the basis for a new orbital
vehicle called VentureStar"^" that could replace the Space
Shuttle by 2006 (see Figure 5.5-2). The X-33 and X-34 ran
into technical problems and never flew. In 2001 , after spend-
ing SI. 3 billion. NASA abandoned both projects.
In all three projects - National Aerospace Plane, X-33, and
X-34 - national leaders had set ambitious goals in response
to NASA's ambitious proposals. These programs relied on
the invention of revolutionary technology, had run into
major technical problems, and had been denied the funds
needed to overcome these problems - assuming they could
be solved. NASA had spent nearly 15 years and several
billion dollars, and yet had made no meaningful progress
toward a Space Shuttle replacement.
In 2000, as the agency ran into increasing problems with
the X-33, NASA initiated the Space Launch Initiative, a
$4.5 billion multi-year effort to develop new space launch
technologies. By 2002, after spending nearly $800 million,
NASA again changed course. The Space Launch Initiative
failed to find technologies that could revolutionize space
launch, forcing NASA to shift its focus to an Orbital Space
Plane, developed with existing technology, that would com-
plement the Shuttle by carrying crew, but not cargo, to and
from orbit. Under a new Integrated Space Transportation
Plan, the Shuttle might continue to fly until 2020 or beyond.
(See Section 5.6 for a discussion of this plan.)
As a result of the haphazard policy process that created these
still-bom developmental programs, the uncertainty over
Shuttle replacement persisted. Between 1986 and 2002, the
planned replacement date for the Space Shuttle was consis-
tent only in its inconsistency: it changed from 2002 to 2006
to 201 2, and before the Coliimhia accident, to 2020 or later.
Safety Concerns and Upgrading the Space Shuttle
This shifting date for Shuttle replacement has severely com-
plicated decisions on how to invest in Shuttle Program up-
grades. More often than not. investments in upgrades were
delayed or deferred on the assumption they would be a waste
of money if the Shuttle were to be retired in the near future
(see Figure 5.5-3).
Report Volui
AUQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Past Reports Reviewed
During the course of the investigation, more than 50 past reports regarding NASA and the Space Shuttle Program were reviewed. The
principal purpose of these reviews what factors those reports examined, what findings were made, and what response, if any. NASA may
have made to the findings. Board members then used these findings and responses as a benchmark during their investigation to compare
to NASA's current programs. In addition to an extensive 3()()-page examination of every Aerospace Safely Advisory Panel report (see
Appendix D. 18), the reports listed on the accompanying chart were examined for specific factors related to the investigation. A complete
listing of those past reports' findings, is contained in Appendix D. 1 S.
Report Reviewed
Topic Examined
£
2
J
6
3 C
E.2
E*-
o
O
0
c
0
U
c
0)
E
-!< Q)
■ !2 en
Qi D
c
0
:5
Q.
o
c
D
C
■Si
c
'5
:5
(J
0)
CO
0)
^ i
Rogers Commission Report - 1986
•
•
•
•
•
•
STS-29R Preiaunch Assessment -1989
"Augustine Report" - 1990
•
•
•
•
Pate-Cornell Report - 1990
•
"Aldridge Report" - 1992
GAO: NASA Infrastructure - 1996
•
•
GAO: NASA Workforce Reductions - 1996
•
•
Super Light Weight Tank Independent
Assessment - 1997
•
•
Process Readiness Review - 1998
•
•
•
S&MA Ground Operations Report - 1998
•
GAO: NASA Management Challenges
- 1999
•
•
•
Independent Assessment JS-9047 - 1999
•
Independent Assessment JS-9059 - 1999
•
Independent Assessment JS-9078 - 1999
•
•
Independent Assessment JS-9083 - 1999
•
S&MA Ground Operations Report - 1999
•
•
Space Shuttle Independent Assessment Team
- 1999
•
•
•
•
•
Space Shuttle Ground Operations Report
- 1999
•
Space Shuttle Program (SSP) Annual Report
- 1999
•
Report Vqll
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
0)
6
u
3 C
E.o
E "-
0
u
1
"c
0
(1)
E
■ ^ D)
Qi D
C
D
:5
0)
-D S
3 3
o s
<
CO 0
o
c
D
C
"c
'5
:5
c
3
o
0)
u
i~
GAO; Human Capital & Safety - 2000
•
Independent Assessment JS-0032 - 2000
•
Independent Assessment JS-0034 - 2000
•
Independent Assessment JS-0045 - 2000
•
IG Audit Report 00-039 - 2000
•
NASA Independent Assessment Team - 2000
•
•
•
•
•
Space Shuttle Program Annual Report - 2000
•
•
•
•
ASAP Report - 2001
•
•
•
•
•
•
•
GAO: NASA Critical Areas - 2001
•
GAO; Space Shuttle Safety - 2001
•
Independent Assessment JS-101 4 - 2001
•
•
•
•
Independent Assessment JS-1024 - 2001
•
•
•
Independent Assessment KS-0003 - 2001
•
•
•
Independent Assessment KS-lOOl - 2001
9
•
Workforce Survey-KSC - 2001
•
Space Shuttle Program Annual Report - 2001
•
SSP Processina Independent Assessment
- 2001
•
•
•
ASAP Report - 2002
•
•
•
•
•
GAO: Lessons Learned Process - 2002
•
Independent Assessment KS-1002 - 2002
«
Selected NASA Lessons Learned - 1992-2002
•
•
•
•
•
•
NASA/Navy Benchmarking Exchange - 2002
•
•
•
•
•
Space Shuttle Program Annual Report - 2002
•
•
•
•
ASAP Leading Indicators - 2003
•
•
•
NASA Quality Management System - 2003
•
QAS Tiger Team Report - 2003
•
Shuttle Business Environment - 2003
•
Report volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Fiscal Year
Upgrades
1994
$454.5
1995
$247.2
1996
$224.5
1997
$215.9
1998
$206.7
1999
$175.2
2000
$239.1
2001
$289.3
2002
$379.5
2003
$3475
Figure 5.5-3. Shuffle Upgrade Budgets (in millions of dollars).
(Source. NASA)
In 1995, for instance, the Kraft Report embraced the prin-
ciple that NASA .should "freeze the design'" of the Shuttle
and defer upgrades due to the vehicle's "mature" status
and the n^ed for NASA to "concentrate scarce resources on
developing potential replacements for the Shuttle."^*' NASA
subsequently halted a number of planned upgrades, only
to reverse course a year later to "take advantage of tech-
nologies to improve Shuttle safety and the need for a robust
Space Shuttle to assemble the ISS."''^
in a June 1999 letter to the White House, NASA Adminis-
trator Daniel Goldin declared that the nation faced a "Space
Launch Crisis." He reported on a NASA review of Shuttle
safety that indicated the budget for Shuttle upgrades in Fiscal
year 2000 was "inadequate to accommodate upgrades neces-
sary to yield significant safety improvements."'^' After two
"clo.se calls" during STS-93 in July 1999 Goldin also char-
tered a Shuttle Independent Assessment Team (Si AT) chaired
by Harry McDonald, Director of NASA Ames Research Cen-
ter Among the team's findings, reported in March 2000:"'
• "Over the course of the Shuttle Program ... proces.ses,
procedures and training have continuously been im-
proved and implemented to make the system safer. The
SI AT has a major concern ... that this critical feature of
the Shuttle Program is being eroded." The major factor
leading to this concern "is the reduction in allocated
resources and appropriate staff . . . There are important
technical areas that are 'one-deep.' " Also, "the SIAT
feels strongly that workforce augmentation must be
realized principally with NASA personnel rather than
with contractor personnel."
• The SiAT was concerned with "success-engendered
safety optimism ... The SSP must rigorously guard
against the tendency to accept risk solely because of
prior success."
• "The SIAT was very concerned with what it perceived as
Risk Management process erosion created by the desire
to reduce costs ... The SiAT feels strongly that NASA
Safety and Mission Assurance should be restored to its
previous role of an independent oversight body, and not
be simply a 'safety auditor.' "
• "The size and complexity of the Shuttle system and of
NASA/contractor relationships place extreme impor-
tance on understanding, communication, and informa-
tion handling ... Communication of problems and con-
cerns upward to the SSP from the 'floor' also appeared
to leave room for improvement."'''
The Shuttle independent Assessment Team report also stated
that the Shuttle "clearly cannot be thought of as 'operational'
in the usual sense. Extensive maintenance, major amounts
of 'touch labor' and a high degree of skill and expertise will
always be required." However, "the workforce has received
a conflicting message due to the emphasis on achieving cost
and staff reductions, and the pressures placed on increasing
scheduled flights as a result of the Space Station."'"'
Responding to NASA's concern that the Shuttle required
safety-related upgrades, the President's proposed NASA
budget for Fiscal Year 2001 proposed a "safety upgrades
initiative." That initiative had a short life span, in its Fiscal
Year 2002 budget request, NASA proposed to spend $1,836
billion on Shuttle upgrades over five years. A year later, the
Fiscal Year 2003 request contained a plan to spend $1,220
billion - a 34 percent reduction. The reductions were pri-
marily a response to rising Shuttle operating costs and the
need to stay within a fixed Shuttle budget. Cost growth in
Shuttle operations forced NASA to "use funds intended for
Space Shuttle safety upgrades to address operational, sup-
portability, obsolescence, and infrastructure needs."'*'
At its March 2001 meeting, NASA's Space Flight Advisory
Committee advised that "the Space Shuttle Program must
make larger, more substantial safety upgrades than currently
planned ... a budget on the order of three times the budget
cunently allotted for improving the Shuttle systems" was
needed."'^ I^ater that year, five Senators complained that "the
Shuttle program is being penalized, despite its outstanding
pertormance, in order to conform to a budget strategy that
is dangerously inadequate to ensure safety in America's hu-
man space flight program."'* (See Chapter 7 for additional
discussion of Shuttle safety upgrades.)
Deteriorating Shuttle Infrastructure
The same ambiguity about investing in Shuttle upgrades has
also affected the maintenance of Shuttle Program ground
infrastructure, much of which dates to Project Apollo and
1970s Shuttle Program construction. Figure 5.5-4 depicts the
age of the Shuttle's infrastructure as of 2000. Most ground
infrastructure was not built for such a protracted lifespan.
Maintaining infrastructure has been particularly difficult at
Kennedy Space Center, where it is constantly exposed to a
salt water environment.
Board investigators have identified deteriorating infrastruc-
ture associated with the launch pads. Vehicle Assembly
Building, and the crawler transporter. Figures 5.5-5 and 5.5-6
depict some of this deterioration. For example. NASA has
installed nets, and even an entire sub-roof, inside the Vehicle
Assembly Building to prevent concrete from the building's
ceiling from hitting the Orbiter and Shuttle stack, in addi-
tion, the corrosion-control challenge results in zinc primer
Report Voui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
c
.2
1
c
&
20-
15-
10-
0 -
nf2
p"
'.■J.-,J.v,'
r^B
M
000
Age:[
fr ;ooi
FY 2010
■ 0-20
D 21-35
■ 36-70+
Figure 5.5-4. Age of the Space Shuffle infrastrucfure. (Source: Con-
nie Mi/fon fo Space Flighf Advisory Council, 2000.
on certain launch pad areas being exposed to the elements.
When rain fails on these areas, it carries away zinc, runs onto
the leading edge of the Orbiler's wings, and causes pinholes
in the Reinforced Carbon-Carbon panels (see Chapter 3).
In 2000. NASA identitied 100 infrastructure items that
demanded immediate attention. NASA briefed the Space
Flight Advisory Committee on this "Infrastructure Revitai-
ization" initiative in November of that year. The Committee
concluded that "deteriorating infrastructure is a serious,
major problem." and. upon touring several Kennedy Space
Center facilities, declared them "in deplorable condition."''
NASA subsequently submitted a request to the White House
Office of Management and Budget during Fiscal Year 2002
budget deliberations for $600 million to fund the infrastruc-
ture initiative. No funding was approved.
In Fiscal Year 2002, Congress added $25 million to NASA's
budget for Vehicle Assembly Building repairs. NASA has
reallocated limited funds from the Shuttle budget to press-
ing infrastructure repairs, and intends to take an integrated
look at infrastructure as part of its new Shuttle Service
Life Extension Program. Nonetheless, like Space Shuttle
upgrades, infrastructure revitalization has been mired by
the uncertainty surrounding the Shuttle Program's lifetime.
Considering that the Shuttle will likely be flying for many
years to come. NASA, the White House, and Congress alike
now face the specter of having to deal with years of infra-
structure neglect.
5.6 A Change in NASA Leadership
Daniel Goldin left NASA in November 2001 after more
than nine years as Administrator. The White House chose
Sean O'Keefe. the Deputy Director of the White House
Office of Management and Budget, as his replacement.
O'Keefe stated as he took office that he was not a "rocket
scientist." but rather that his expertise was in the manage-
ment of large government programs. His appointment was
an explicit acknowledgement by the new Bush administra-
tion that NASA's primary problems were managerial and
financial.
By the time O'Keefe arrived. NASA managers had come to
recognize that 1990s funding reductions for the Space Shut-
tle Program had resulted in an excessively fragile program,
and also realized that a Space Shuttle replacement was not
on the horizon. In 2002. with these issues in mind, O'Keefe
made a number of changes to the Space Shuttle Program.
He transferred management of both the Space Shuttle Pro-
gram and the International Space Station from Johnson
Space Center to NASA Headquarters. O'Keefe also began
considering whether to expand the Space Flight Opera-
tions Contract to cover additional Space Shuttle elements,
or to pursue "competitive sourcing." a Bush administration
initiative that encouraged government agencies to compete
with the private sector for management responsibilities of
publicly funded activities. To research whether competitive
sourcing would be a viable approach for the Space Shuttle
Program, NASA chartered the Space Shuttle Competitive
Sourcing Task Force through the RAND Corporation, a
federally funded think tank. In its report, the Task Force rec-
ognized the many obstacles to transferring the Space Shuttle
to non-NASA management, primarily NASA's reticence to
relinquish control, but concluded that "NASA must pursue
competitive sourcing in one form or another."'""
NASA began a "Strategic Management of Human Capital"
initiative to ensure the quality of the future NASA work-
force. The goal is to address the various external and internal
challenges that NASA faces as it tries to ensure an appropri-
ate mix and depth of skills for future program requirements.
A number of aspects to its Strategic Human Capital Plan
require legislative approval and are currently before the
Congress.
Figure 5 5-5 and 5 5-6. Examples of fhe seriously deferiorafing infrastructure used to support the Space Shuttle Program. At left is launch
Complex 39A, and at right is the Vehicle Assembly building, both at fhe Kennedy Space Center.
Report volume i a u c3 u s t 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The new NASA leadership also began to compare Space
Shuttle program practices with the practices of similar
high-technology, high-risk enterprises. The Navy nuclear
submarine program was the first enterprise selected for com-
parative analysis. An interim report on this "benchmarking"
effort was presented to NASA in December 2002.''"
In November 2002, NASA made a fundamental change in
strategy, in what was called the Integrated Space Transpor-
tation Plan (see Figure 5.6-1), NASA shifted money from
the Space Launch Initiative to the Space Shuttle and Inter-
national Space Station programs. The plan also introduced
the Orbital Space Plane as a complement to the Shuttle for
the immediate future. Under this strategy, the Shuttle is to
fly through at least 2010, when a decision will be made on
how long to extend Shuttle operations - possibly through
2020 or even beyond.
As a step in implementing the plan, NASA included $281 .4
million in its Fi.scal Year 2004 budget submission to begin
a Shuttle Service Life Extension Program.'" which NASA
describes as a "strategic and proactive program designed to
keep the Space Shuttle Hying safely and efficiently." The
program includes "high priority projects for safety, support-
ability, and infrastructure" in order to "combat obsolescence
of vehicle, oround systems, and facilities." '
Figure 5.6-1. The Integrated Space Transportation Plan.
5. 7 The Return of Schedule Pressure
The International Space Station has been the centerpiece of
NASA's human space flight program in the 1990s. In several
instances, funds for the Shuttle Program have paid for vari-
ous International Space Station items. The Space Station has
also affected the Space Shuttle Program schedule. By the
time the functional cargo block Zarya. the Space Station's
first element, was launched from the Baikonur Cosmodrome
in Kazakhstan in November 1998, the Space Station was
two years behind schedule. The launch of STS-88. the first
of many Shuttle missions assigned to station assembly, fol-
lowed a month later. Another four assembly missions in
1999 and 2000 readied the station for its first permanent
crew. Expedition I, which arrived in late 2000.
When the Bush Administration came to the White House in
January 2001, the International Space Station program was
$4 billion over its projected budget. The Administration's
Fiscal Year 2002 budget, released in February 2001, de-
clared that the International Space Station would be limited
to a "U.S Core Complete" configuration, a reduced design
that could accommodate only three crew members. The
last step in completing the U.S. portion of this configura-
tion would be the addition of the Italian-supplied but U.S.-
owned "Node 2," which would allow Europe and Japan to
connect their laboratory modules to the Station. Launching
Node 2 and thereby finishing "core complete" configuration
became an important political and programmatic milestone
(see Figure 5.7-1 ).
Figure 5.7-1. The "Core Complete" configuration of the Interna-
tional Space Station.
During congressional testimony in May of 2001, Sean
O'Keefe, who was then Deputy Director of the White House
Office of Management and Budget, presented the Adminis-
tration's plan to bring International Space Station costs un-
der control. The plan outlined a reduction in assembly and
logistics flights to reach "core complete" configuration from
36 to 30. It also recommended redirecting about $1 billion in
funding by canceling U.S. elements not yet completed, such
as the habitation module and the X-38 Crew Return Vehicle.
The X-38 would have allowed emergency evacuation and
landing capability for a seven-member station crew. Without
it, the crew was limited to three, the number that could fit
into a Russian Soyuz crew rescue vehicle.
In his remarks, O'Keefe stated:
NASA ',v deiiree of success in i^aiiiiiiii control of cos!
growth on Space Station will not only dictate the ca-
pabilities that the Station wUl provide, but will send a
stron^i signal about the ability of NASA's Human Space
Fliiiht program to effectively manage large development
programs. NASA's credibility with the Administration
and the Congress for delivering on what is promised
and the longer-term implications that such credibility
may have on the future of Human Space Flight hang in
the balance.^-
At the request of the White House Office of Management
and Budget, in July 2001 NASA Administrator Dan Goldin
Report Voui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION 8DARD
formed an International Space Station Management and
Cost Evaluation Task Force. The International Space Station
Management and Cost Evaluation Task Force was to assist
NASA in identifying the reforms needed to restore the Sta-
tion Program's fiscal and management credibility.
While the primary focus of the Task Force was on the Space
Station Program management, its November 2001 report
issued a general condemnation of how NASA, and particu-
larly Johnson Space Center, had managed the Internatiiinal
Space Station, and by implication, NASA's overall human
space flight effort. ' The report noted '"existing deficien-
cies in management structure, institutional culture, cost
estimating, and program control." and that "the institutional
needs of the [human space flight] Centers are dri\ing the
Program, rather than Program requirements being served by
the Centers." The Task Force suggested that as a cost control
measure, the Space Shuttle be limited to four flights per year
and that NASA revise the station crew rotation period to six
months. The cost savings that would result from eliminating
flights could be used to offset cost overruns.
NASA accepted a reduced flight rate. The Space Shuttle Pro-
gram ofhce concluded that, based on a rate of four flights a
year. Node 2 could be launched by February 19, 2004.
In testimony before the House Committee on Science on
November 7. 2001. Task Force Chairman Thomas Young
identified what became known as a "performance gate." He
suggested that over the next two years, NASA should plan
and implement a credible "'core complete" program. In Fall
2003, "an assessment would be made concerning the ISS
program performance and NASA's credibility. If satisfac-
tory, resource needs would be assessed and an (ISS] "end
state" that realized the science potential would become the
baseline. If unsatisfactory, the core complete program would
become the "end state.' "■■*
Testifying the same day. Office of Management and Budget
Deputy Director Sean O'Keefe indicated the Administra-
tion's agreement with the planned performance gate:
The concept presented by the task force of u decision
f^ate in tH'o years that could lead to an end state other
than the U.S. core complete Station is an innovative ap-
proach, and one the Administration will adopt. It calls
for NASA to make the necessary mana^iement reforms to
successfully build the core complete Station and oper-
ate it within the $H.3 billion available throufih FY 2006
plus other human space flight resmirces . . . If NASA fails
to meet the standards, then an end-state beyond core
complete is not an option. The stratef^y places the bur-
den of proof on NASA performance to ensure that NASA
fully implements the needed reforms.^''
Mr O'Keefe added in closing:
A most important next step - one on which the success of
all these reforms hinf>es - is to provide new leadership
for NASA and its Human Space Flight activities. NASA
has been well-served by Dan Goldin. New leadership
is now necessary to continue moviiiii the hall down the
field with the goal line in sight. The Administration rec-
ognizes the importance of getting the right leaders in
place as .soon as possible, and I am personalty engaged
in making sure that this happens.
A week later, Sean O'Keefe was nominated by President
Bush as the new NASA Administrator.
To meet the new flight schedule, in 2002 NASA revised its
Shuttle manifest, calling for a docking adaptor to be installed
in Columbia after the STS- 107 mission so that it could make
an October 2003 flight to the International Space Station.
Columbia was not optimal for Station flights - the Orbiter
could not carry enough payload - but it was assigned to this
flight because Discovery was scheduled for 18 months of
major maintenance. To ensure adequate Shuttle availability
for the February 2004 Node 2 launch date, Columbia would
fly an International Space Station resupply mission.
The White House and Congress had put the International
Space Station Program, the Space Shuttle Program, and
indeed NASA on probation. NASA had to prove it could
meet schedules within cost, or risk halting Space Station
construction at core complete - a configuration far short
of what NASA anticipated. The new NASA management
viewed the achievement of an on-schedule Node 2 launch
as an endorsement of its successful approach to Shuttle and
Station Programs. Any suggestions that it would be difficult
to meet that launch date were brushed aside.
This insistence on a fixed launch schedule was worrisome.
The International Space Station Management and Cost
Evaluation Task Force, in particular, was concerned with
the emphasis on a specific launch date. It noted in its 2002
review of progress toward meeting its recommendations that
"significant progress has been made in nearly all aspects of
the ISS Program," but that there was "significant risk with
the Node 2 (February '04) schedule."'"
By November 2002, NASA had flown 16 Space Shuttle
missions dedicated to Station assembly and crew rotation.
Five crews had lived onboard the Station, the last four
of them delivered via Space Shuttles. As the Station had
grown, so had the complexity of the missions required to
complete it. With the International Space Station assembly
more than half complete, the Station and Shuttle programs
had become irreversibly linked. Any problems with or per-
turbations to the planned schedule of one program rever-
berated through both programs. For the Shuttle program,
this meant that the conduct of all missions, even non-Sta-
tion missions like STS- 107, would have an impact on the
Node 2 launch date.
In 2002, this reality, and the events of the months that would
follow, began to place additional schedule pressures on the
Space Shuttle Program. Those pressures are discussed in
Section 6.2.
5.8 Conclusion
Over the last decade, the Space Shuttle Program has oper-
ated in a challeneins and often turbulent environment. As
Report VOLUf
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
discussed in this chapter, there were at least three major
contributing factors to that environment:
• Throughout the decade, the Shuttle Program has had
to function within an increasingly constrained budget.
Both the Shuttle budget and workforce have been re-
duced by over 40 percent during the past decade. The
White House, Congress, and NASA leadership exerted
constant pressure to reduce or at least freeze operating
costs. As a result, there was little margin in the budget
to deal with unexpected technical problems or make
Shuttle improvements.
• The Shuttle was mischaracterized by the 1995 Kraft
Report as "a mature and reliable system ... about as
safe as today's technology will provide." Based on
this mischaracterization, NASA believed that it could
turn increased responsibilities for Shuttle operations
over to a single prime contractor and reduce its direct
involvement in ensuring safe Shuttle operations, in-
stead monitoring contractor performance from a more
detached position. NASA also believed that it could use
the "mature" Shuttle to carry out operational missions
withput continually focusing engineering attention on
understanding the mission-by-mission anomalies inher-
ent in a developmental vehicle.
• In the 1990s, the planned date for replacing the Shuttle
shifted from 2006 to 2012 and then to 2015 or later.
Given the uncertainty regarding the Shuttle's service
life, there has been policy and budgetary ambivalence
on investing in the vehicle. Only in the past year has
NASA begun to provide the resources needed to sus-
tain extended Shuttle operations. Previously, safety and
support upgrades were delayed or deferred, and Shuttle
infrastructure was allowed to deteriorate.
The Board observes that this is hardly an environment in
which those responsible for safe operation of the Shuttle can
function without being influenced by external pressures, ft
is to the credit of Space Shuttle managers and the Shuttle
workforce that the vehicle was able to achieve its program
objectives for as long as it did.
An examination of the Shuttle Program's history from
Challeiiiier to Coliinihia raises the question: Did the Space
Shuttle Program budgets constrained by the White House
and Congress threaten safe Shuttle operations? There is no
straightforward answer. In 1994, an analysis of the Shuttle
budget concluded that reductions made in the early 1990s
represented a "healthy tightening up" of the program.'"
Certainly those in the Ofrtce of Management and Budget
and in NASA's congressional authorization and appropria-
tions subcommittees thought they were providing enough
resources to operate the Shuttle safely, while also taking into
account the expected Shuttle lifetime and the many other de-
mands on the Federal budget. NASA Headcjuarters agreed,
at least until Administrator Goldin declared a "space launch
crisis" in June 1999 and asked that additional resources for
safety upgrades be added to the NASA budget. By 2001,
however, one experienced observer of the space program
described the Shuttle workforce as "The Few. the Tired."
and suggested that "a decade of downsizing and budget
tightening has left NASA exploring the universe with a less
experienced staff and older equipment.""**
It is the Board's view that this latter statement is an accurate
depiction of the Space Shuttle Program at the time of STS-
107. The Program was operating too close to too many mar-
gins. The Board also finds that recent modest increases in the
Shuttle Program's budget are necessary and overdue steps
toward providing the resources to sustain the program for its
now-extended lifetime. Similarly, NASA has recently recog-
nized that providing an adequately sized and appropriately
trained workforce is critical to the agency's future success.
An examination of the Program's management changes
also leads to the question: Did turmoil in the management
structure contribute to the accident? The Board found no
evidence that the transition from many Space Shuttle con-
tractors to a partial consolidation of contracts under a single
firm has by itself introduced additional technical risk into
the Space Shuttle Program. The transfer of responsibilities
that has accompanied the Space Flight Operations Contract
has, however, complicated an already complex Program
structure and created barriers to effective communica-
tion. Designating the Johnson Space Center as the "lead
center" for the Space Shuttle Program did resurrect some
of the Center rivalries and communication difficulties that
existed before the Challent'er accident. The specific ways
in which this complexity and lack of an integrated approach
to Shuttle management impinged on NASA's performance
during and before the flight of STS-107 are discussed in
Chapters 6 and 7.
As the 21st century began, NASA's deeply ingrained human
space flight culture - one that has evolved over 30 years as
the basis for a more conservative, less technically and orga-
nizationally capable organization than the Apollo-era NASA
- remained strong enough to resist external pressures for ad-
aptation and change. At the time of the launch of STS-107.
NASA retained too many negative (and also many positive)
aspects of its traditional culture: "flawed decision making,
self deception, introversion and a diminished curiosity about
the world outside the perfect place."''' These characteristics
were reflected in NASA's less than stellar performance be-
fore and during the STS-107 mission, which is described in
the following chapters.
Report volume 1
IGU5T 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Endnotes For Chapter 5
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
Report of the Presidential Commission on the Space Shuttle Challenger
Accident, June 6, 1986, (Washington: Government Printing Office,
1986), Vol. I, p. 82, 118.
Report of the Presidential Commission, Vol. I, p. 48.
Report of the Presidential Commission, Vol. I, p. 52.
Report of the President/a/ Commission, Vol. I, pp. 164-165.
Report of the Presidential Commission, Vol. I, pp. 198-201.
Report of The National Commission for the Review of the National
Reconnaissance Office The NRO ot the Crossroads, November 2000, p.
66. Roger Guillemette, "Vondenberg: Space Shuttle Launch and Landing
Site, Part 1," Spaceflight, October 1994, pp. 354-357, ond Roger
Guillemette, "Vondenberg: Space Shuttle Launch and Landing Site, Part
2," SpaceRight, November 1994, pp. 378-381; Dennis R. Jenkins, Space
Shuttle: The History of the Notional Space Transportation System - The
First 100 Missions (Cope Canaveral, FL, Specialty Press, 2001 ), pp. 467-
476.
Vice President's Spoce Policy Advisory Board, A Post Cold War
Assessment of US Space Policy, December 1992, p. 6.
Quoted in John M. Logsdon, "Return to Flight: Richard H. Truly and the
Recovery from the Challenger Accident," in Pamela E. Mack, editor.
From Engineering to Big Science The NACA and NASA Collier Trophy
Research Project Winners, NASA SP-4219 (Washington: Government
Printing Office, 1998), p. 363.
Aviation Week & Space Technology, November 10, 1986, p. 30.
There ore proposals for using other U.S. systems, in development but not
yet ready for flight, to provide an alternate U.S. means of station access.
These "Alternate Access to Space" proposals hove not been evaluated
by the Board.
Testimony of William F. Reoddy to the Subcommittee on Science,
Technology and Space, U.S. Senate, September 6, 2001.
Howord E. McCurdy, Inside NASA. High Technology and Organizational
Change in the US. Space Program (Baltimore: The Johns Hopkins
University Press, 1993), p. 24.
Garry D. Brewer, "Perfect Places: NASA as on Idealized Institution,"
in Radford Byerly, Jr., ed.. Space Policy Reconsidered (Boulder, CO:
Westview Press, 1989), p. 158. Brewer, when he wrote these words,
was a professor of organizational behavior at Yale University with no
prior exposure to NASA. For first-hand discussions of NASA's Apollo-era
organizational culture, see Christopher Kraft, Flight: My Life in Mission
Control (New York: E.P. Dutton, 2001); Gene Kranz, Failure is Not an
Option: Mission Control from Mercury to Apollo ?3 (New York: Simon &
Schuster, 2000); and Thomas J. Kelly, Moon Lander: How We Developed
the Apollo Lunar Module (Washington: Smithsonian Institution Press,
2001).
' Brewer, "Perfect Places," pp. 159-165.
' As NASA human space flight personnel began to become closely
involved with their counterparts in the Russian space program after
1992, there was grudging acceptance that Russian human space flight
personnel were olso skilled in their work, although they carried it out
rather differently than did NASA.
Bush administration space policy is discussed in Dan Quayle, Standing
Firm: A Vice-Presidentiol Memoir (New York: Harper Collins, 1994), pp.
185-190.
Report of the Advisory Committee on the Future of the U.S. Space
Program, December 1990. The quotes are from p. 2 of the report's
executive summary.
Report of the Advisory Committee on the Future of the U.S. Space
Program Measured in terms of total notional spending, the report's
recommendations would hove returned NASA spending to 0.38 percent
of U.S. Gross Domestic Product - a level of investment not seen since
1969.
For Fiscal Years 1965-2002 in Real and Constant Dollars, see NASA,
"Space Activities of the U.S. Government - in Millions of Real Year
Dollars," and "Space Activities of the U.S. Government - Adjusted for
Inflation," in Aeronoutics and Space Report of the President - Fiscal Year
2002 Activity, forthcoming. For Fiscal Years 2003-2004 in Real Dollars,
see Office of Management and Budget, "Outlays By Agency: 1962-
2008," in Historical Budget of the United States Government, Fiscal Year
2004, (Washington: Government Printing Office, 2003), pp. 70-75.
Commission on the Future of the U.S. Aerospace Industry, Final Report,
November 18, 2002, p. 31.
U.S. Congress, Office of Technology Assessment, "Shuttle Fleet Attrition
if Orbiter Recovery Reliability is 98 Percent," August 1989, p. 6. From:
Round Trip to Orbit: Human Space Flight Alternatives: Special Report,
OTS-ISC-419.
Report of the Advisory Committee on the Future of the U.S. Space
Progrom.
Howard E. McCurdy, Faster, Better, Cheaper: Low-Cost Innovation in
the U.S Space Program (Baltimore: The Jotins Hopkins University Press,
2001).
Letter from Daniel Goldin to Representative James T. Walsh, October 4,
2001. CAIB document CAB065-0t630169.
Ibid.
W. Henry Lambright, Tronsforming Government: Don Goldin and the
Remaking of NASA (Washington: Price Waterhouse Coopers Endowment
for the Business of Government, March 2001 ), pp. 12; 27-29.
Deming's management philosophy was not the only new notion that
Goldin attempted to apply to t^ASA. He was also an advocate of the
"Total Quality Management" approach and other modern management
schemes. Trying to adapt to these various management theories was a
source of some stress.
For 0 discussion of Goldin's approach, see Howard McCurdy, Faster,
Better, Cheaper: tow-Cost Innovation in the U.S. Space Program
(Baltimore: The Johns Hopkins University Press, 2001). It is worth noting
that while the "faster, better, cheaper" approach led to many more
NASA robotic missions being launched after 1992, not all of those
missions were successful. In particular, there were two embarrassing
failures of Mors missions in 1999.
Lambright, Transforming Government, provides on early but
comprehensive evaluation of the Goldin record. The quote is from p.
28.
Goldin is quoted in Bill Horwood, "Pace of Cuts Fuels Concerns About
Shuttle," Spoce News, December 19-25, 1994, p. 1.
McCurdy, Faster, Better, Cheaper.
REPORT Volume I
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
For two recent works that apply the "Iron Triangle" concept to other
policy areas, see Randall B. Ripley and Grace A. Fronklin, Congress, the
Bureaucrocy and Public Policy, 5th Edition, (Pacific Grove, CA: Brooks/
Cole Publishing Company, 1991); and Paul C. Light, Forging Legislaiion:
The Politics of Veterans Reform, (New York: W. W. Norton, 1992).
Information obtained from Anna Henderson, NASA Office of Space
Flight, to e-mail to John Logsdon, June 13, 2003.
National Academy of Public Administration, A Review of the Space
Shutile Costs, Reduction Goals, and Procedures, December 1994, pp.
3-5. CAIB document CAB026-0313.
Presentation to NASA Advisory Council by Stephen Oswald, Acting
Director, Space Shuttle Requirements, "Space Flight Operations Contract
(SFOC) Acquisition Status," April 23, 1996. CAIB document CTF064-
1369.
Bryan D. O'Connor, Status Briefing to NASA Administrator, "Space
Shuttle Functional Workforce Review," February 14, 1995. CAIB
document CABOl 5-0400.
Ralph Vortabedian, "Ex-NASA Chief Hits Flight Safety," Houston
Chronicle, March 7, 1996.
Kothy Sawyer, "NASA Space Shuttle Director Resigns," Wosfiingfon
Post, February 3, 1996, p. A3. See also "Take this Job and Shuttle
It: Why NASA's Space Shuttle Chief Quit," Final Frontier, July/August
1996, pp. 16-17; "NASA Alters Its Management, Philosophy," Space
News, February 12-18, 1996, p. 3.
f?eport of the Space Shuttle Management Independent Review Team,
February 1995.
Ibid, pp. 3-18.
NASA News Release 95-27, "Shuttle Management Team Issues Final
Report," March 15, 1995.
Aerospace Safety Advisory Panel, "Review of the Space Shuttle
Management Independent Review Program," May 1995. CAIB document
CAB015-04120413.
Jose Garcia to President William Jefferson Clinton, August 25, 1995.
See, tor instance: "Determinations and Findings for the Space Shuttle
Program," United States House of Representatives, Subcommittee on
Space, of the Committee on Science, 104 Cong., 1 Sess., November 30,
1995.
See remarks by Daniel S. Goldin, Opening Remarks at the September
30, 1996, ceremony commemorating the signing of the Space Flight
Operations Contract, Houston, Texas. (Videotape recording)
' Congressional Budget Office, "NASA's Space Flight Operations Contract
and Other Technologically Complex Government Activities Conducted by
Coijjroctors," July 29, 2003.
Russell Turner, testimony at public hearing before the Columbia Accident
Investigation Board, June 12, 2003.
' See Section 204 of Public Low 105-303, October 28, 1999.
' Joe Rothenberg to Dan Goldin, August 17, 2001, CAIB document
CAB015-1134; "Space Shuttle Privatization," CAIB document CAB015-
1135; "Space Shuttle Privatization: Options and Issues," Rev; 8/14/01,
CAIB document CAB015-1147
' Ron Dittemore, "Concept of Privatization of the Space Shuttle Program,"
September 2001. CAIB document CTF005-0283.
Ibid.
■ Roy Bridges, Testimony before the Columbia Accident Investigation
Board, March 25, 2003.
' The quotes ore token from NASA-submitted material appended to
the statement of NASA Administrator Daniel Goldin to the Senate
Subcommittee on Science, Technology and Space, March 22, 2000, p.
7
' National Commission on Space, Pioneering the Space Frontier: An
Exciting Vision of Our Next Fifty Years in Space, Report of the National
Commission on Space (Bantam Books, 1986).
President Ronald Reagan, "Message to the Congress on America's
Agenda for the Future," February 6, 1986, Public Papers of the
Presidents of the United States Ronald Reagan: Book /-January 7 to
June 27 1986 (Washington, DC: U.S. Government Printing Office, 1982-
1991), p. 159.
' Office of Space Systems Development, NASA Headquarters, "Access to
Space Study-Summary Report," January 1994, reproduced in John M.
Logsdon, ef al. eds., Exploring the Unknown, Volume IV: Accessing Space
NASA SP-4407 (Government Printing Office, 1999), pp. 584-604.
The White House, Office of Science and Technology Policy, "Fact
Sheet-Notional Space Tronsportotion Policy," August 5, 1994, pp. 1-2,
reprinted in Logsdon et al., Exploring the Unknown, Volume IV, pp. 626-
631.
Report of the Space Shutile Management Independent Review Team, pp.
3-18.
"Statement of William F. Readdy, Deputy Associate Administrator, Office
of Space Flight, Notional Aeronautics and Space Administration before
the Subcommittee on Space and Aeronautics Committee on Science,
House of Representatives," October 21, 1999. CAIB document CAB026-
0146.
Letter from Daniel Goldin to Jacob Lew, Director, Office of Monogement
and Budget, July 6, 1999.
NASA, Space Shuttle Independent Assessment Team, "Report to the
Associate Administrator, Office of Space Flight, October-December
1999," March 7, 2000. CAIB document CTF017-0169.
Ibid.
Ibid.
Dr. Richard Beck, Director, Resources Analysis Division, NASA, "Agency
Budget Overview, FY 2003 Budget," February 6, 2002, p. 20, CAIB
document CAB070-0001.
Space Flight Advisory Committee, NASA Office of Space Flight, Meeting
Report, May 1-2, 2001, p. 7 CAIB document CTF017-0034.
Senators Bill Nelson, Bob Graham, Mary Landrieu, John Breaux, and
Orrin Hatch to Senator Barbara Mikulski, September 18, 2001.
Space Flight Advisory Committee, NASA Office of Space Flight, Meeting
Report, May 1-2, 2001, p. 7 CAIB document CTF0170034.
Task Force on Space Shuttle Competitive Sourcing, Alternate Trajectories:
Options for Competitive Sourcing of the Space Shuttle Program,
Executive Summary, The RAND Corporation, 2002. CAIB document
CAB003-1614.
NNBE Benchmarking Team, NASA Office of Safety & Mission Assurance
and NAVSEA 92Q Submarine Safety & Quality Assurance Division,
"NASA/Navy Benchmarking Exchange (NNBE)," Interim Report,
December 20, 2002. CAIB document CAB030-0392. The team's final
report was issued in July 2003.
' NASA FY 2004 Congressional Budget, "Theme: Space Shuttle." [Excerpt
from NASA FY 2004 budget briefing book also known as the "IBRD
Narrative"). CAIB document CAB065-04190440.
NASA, "Theme: Space Shuttle." CAIB document CAB065-04 190440.
Testimony of Sean O'Keefe, Deputy Director, Office of Management and
Budget, to the Subcommittee of the Committee on Appropriations, "Part
1, National Aeronautics and Space Administration," Hearings Before a
Subcommittee of the Committee on Appropriations, United States House
of Representatives, 107th Congress, 1st Sess., May 2001, p. 32.
' "Report by the International Space Station (ISS) Management and
Cost Evaluation (IMCE) Task Force to the NASA Advisory Council,"
November 1, 2001, pp. 1-5. CAIB document CTF044-6016.
' Testimony of Tom Young, Chairman, ISS Management and Cost
Evaluation (IMCE) Task Force, to the Committee on Science, U.S. House of
Representatives, "The Space Station Task Force Report," Hearing Before
the Committee on Science, United States House of Representatives, 107th
Congress, 1st Sess., November, 2001, p. 23.
' Testimony of Sean O'Keefe, Deputy Director, Office of Management and
Budget, to the Committee on Science, U.S. House of Representatives,
"The Space Station Task Force Report," Hearing Before the Committee
on Science, United States House of Representatives, 107th Congress, 1st
Sess., November, 2001, p. 28.
' Thomas Young, IMCE Choir, "International Space Station (ISS)
Management and Cost Evaluation (IMCE) Task Force Status Report to
the NASA Advisory Council," (Viewgraphs) December 11, 2002, p. 11.
CAIB document CAB065-0189.
General Research Corporation, Space Shuttle Budget Allocation Review,
Volume I, July 1994, p. 7 CAIB document CAIB015-0161.
^ Beth Dickey, "The Few, the Tired," Government Executive, April 2001, p.
71.
' Brewer, "Perfect Places," pp. 159.
Report von
August Z003
Chapter 6
Decision Making
at NASA
The dwindling post-Cold War Shuttle budget that launched
NASA leadership on a crusade for efficiency in the decade
before Colnnihia's final flight powerfully shaped the envi-
ronment in which Shuttle managers worked. The increased
organizational complexity, transitioning authority struc-
tures, and ambiguous working relationships that defined
the restructured Space Shuttle Program in the 1990s created
turbulence that repeatedly influenced decisions made before
and during STS-107.
This chapter connects Chapter 5's analysis of NASA's
broader policy environment to a focused scrutiny of Space
Shuttle Program decisions that led to the STS-107 accident.
Section 6.1 illustrates how foam debris losses that violated
design requirements came to be defined by NASA manage-
ment as an acceptable aspect of Shuttle missions, one that
posed merely a maintenance "turnaround" problem rather
than a safety-of-flight concern. Section 6.2 shows how. at a
pivotal juncture just months before the Coliiinbiu accident,
the management goal of completing Node 2 of the interna-
tional Space Station on time encouraged Shuttle managers
to continue flying, even after a significant bipod-foam debris
strike on STS-II2. Section 6.3 notes the decisions made
during STS-107 in response to the bipod foam strike, and
reveals how engineers' concerns about risk and safety were
competing with - and were defeated by - management's be-
lief that foam could not hurt the Orbiter, as well as the need
to keep on schedule, in relating a rescue and repair scenario
that might have enabled the crew's safe return. Section 6.4
grapples with yet another latent assumption held by Shuttle
managers during and after STS-107: that even if the foam
strike had been discovered, nothing could have been done.
6.1 A History OF Foam Anomalies
The shedding of External Tank foam - the physical cause of
the Columbia accident - had a long history. Damage caused
by debris has occurred on every Space Shuttle flight, and
most missions have had insulating foam shed during ascent.
This raises an obvious question: Why did NASA continue
flying the Shuttle with a known problem that violated de-
sign requirements? it would seem that the longer the Shuttle
Program allowed debris to continue striking the Orbiters,
the more opportunity existed to detect the serious threat it
posed. But this is not what happened. Although engineers
have made numerous changes in foam design and applica-
tion in the 25 years that the External Tank has been in pro-
duction, the problem of foam-shedding has not been solved,
nor has the Orbiter's ability to tolerate impacts from foam
or other debris been significantly improved.
The Need for Foam Insulation
The External Tank contains liquid oxygen and hydrogen
propellants stored at minus 297 and minus 423 degrees Fahr-
enheit. Were the super-cold External Tank not sufficiently in-
sulated from the warm air, its liquid propellants would boil,
and atmospheric nitrogen and water vapor would condense
and form thick layers of ice on its surface. Upon launch, the
ice could break off and damage the Orbiter. (See Chapter 3.)
To prevent this from happening, large areas of the Exter-
nal Tank are machine-.sprayed with one or two inches of
foam, while specific fixtures, such as the bipod ramps, are
hand-sculpted with thicker coats. Most of these insulating
materials fall into a general category of "foam," and are
outwardly similar to hardware store-sprayable foam insula-
tion. The problem is that foam does not always stay where
the External Tank manufacturer Lockheed Martin installs it.
During flight, popcorn- to briefcase-size chunks detach from
the External Tank.
Original Design Requirements
Early in the Space Shuttle Program, foam loss was consid-
ered a dangerous problem. Design engineers were extremely
concerned about potential damage to the Orbiter and its
fragile Thermal Protection System, parts of which are so
vulnerable to impacts that lightly pressing a thumbnail into
them leaves a mark. Because of these concerns, the baseline
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
design requirements in the Shuttle's "Flight and Ground
System Specification-Book I, Requirements," precluded
foam-shedding by the External Tank. Specifically:
3.2.1.2.14 Debris Prevention: The Space Shuttle Sys-
tem, inchidiiii; the iiroiiml systems, shall he desifiued to
preclude the sheddiiii; of ice and/or other debris from
the Shuttle elements dnrini^ prelaiuich and fli,i;ht op-
erations that would Jeopardize the frif>ht crew, vehicle,
mission success, or would adversely impact turnaround
operations. '
3.2.1.1.17 External Tank Debris Limits: No debris
shall emanate from the critiad zone of the External
Tank on the launch pad or diirini> ascent except for such
material which may result from normal thermal protec-
tion system recession due to ascent heatinf^r
The assumption that only tiny pieces of debris would strike
the Orbiter was also built into original design requirements,
which specified that the Thermal Protection System (the
tiles and Reinforced Carbon-Carbon, or RCC, panels) would
be built to withstand impacts with a kinetic energy less than
0.006 foot-pounds. Such a small tolerance leaves the Orbiter
vulnerable to strikes from birds, ice, launch pad debris, and
pieces of foam.
Despite the design requirement that the External Tank shed
no debris, and that the Orbiter not be subjected to any sig-
nificant debris hits, Columbia sustained damage from debris
strikes on its inaugural 1981 flight. More than 300 tiles had
to be replaced.' Engineers .stated that had they known in ad-
vance that the External Tank "was going to produce the de-
bris shower that occurred" during launch, "they would have
had a difficult time clearing Columbia for flight."'^
Discission of Foam Strikes
Prior to the Rogers Commission
Foam strikes were a topic of management concern at the
time of the Challen,^er accident. In fact, during the Rog-
ers Commission accident investigation. Shuttle Program
Manager Arnold Aidrich cited a contractor's concerns about
foam shedding to illustrate how well the Shuttle Program
manages risk:
On a series of four or five external tanks, the thermal
insulation around the inner tank ... had large divots
of insulation comini> off and impacting the Orbiter
We found significant amount of damage to one Orbiter
after a flight and . . . on the subsequent flight we had a
camera in the equivalent of the wheel well, which took a
picture of the tank after separation, and we determined
that this was in fact the cause of the ckunage. At that
time, we wanted to be able to proceed with the launch
program if it was acceptable . . . so we undertook discus-
sions of what would be acceptable in terms of potential
field repairs, and during those discussions. Rockwell
was very conservative because, rightly, damage to the
Orbiter TPS [Thermal Protection System j is damage to
the Orbiter system, and it has a very stringent environ-
ment to experience during the re-entrv phase.
Aidrich described the pieces of foam as "... half a foot
square or a foot by half a foot, and some of them much
smaller and localized to a specific area, but fairly high up on
the tank. So they had a good shot at the Orbiter underbelly,
and this is where we had the damage."^
Continuing Foam Loss
Despite the high level of concern after STS-I and through
the Challenger accident, foam continued to separate from
the External Tank. Photographic evidence of foam shedding
exists for 65 of the 79 missions for which imagery is avail-
able. Of the 34 missions for which there are no imagery, 8
missions where foam loss is not seen in the imagery, and 6
missions where imagery is inconclusive, foam loss can be
inferred from the number of divots on the Orbiter's lower
surfaces. Over the life of the Space Shuttle Program. Orbit-
ers have returned with an average of 143 divots in the upper
and lower surfaces of the Thermal Protection System tiles,
with 31 divots averaging over an inch in one dimension.''
(The Orbiters' lower surfaces have an average of 10! hits,
23 of which are larger than an inch in diameter.) Though
the Orbiter is also struck by ice and pieces of launch-pad
hardware during launch, by micromeleoroids and orbital
debris in space, and by runway debris during landing, the
Board concludes that foam is likely responsible for most
debris hits.
With each successful landing, it appears that NASA engi-
neers and managers increasingly regarded the foam-shed-
ding as inevitable, and as either unlikely to jeopardize safety
or simply an acceptable risk. The distinction between foam
loss and debris events also appears to have become bluired.
NASA and contractor personnel came to view foam strikes
not as a safety of flight issue, but rather a simple mainte-
nance, or "turnaround" issue. In Flight Readiness Review
documentation. Mission Management Team minutes, In-
Flight Anomaly disposition reports, and elsewhere, what
was originally considered a serious threat to the Orbiter
Definitions
In Family: A reportable problem that was previously experi-
enced, analyzed, and understood. Out ol limits performance
or discrepancies that have been previously experienced may
be considered as in-family when specifically approved by the
Space Shuttle Program or design project.**
Out of Family: Operation or peifomiance outside the ex-
pected performance range for a given parameter or which has
not previously been experienced.''
Accepted Risk: The threat as.sociated with a specific cir-
cumstance is known and understood, cannot be completely
eliminated, and the circumstance(s) producing that threat is
considered unlikely to reoccur Hence, the circumstance is
fully known and is considered a tolerable threat to the con-
duct of a Shuttle mission.
No Safety-of-Flight-lssuc: The threat associated with a
specific circumstance is known and understood and does not
pose a threat to the crew and/or vehicle.
Report Volume I
AUC3U5T 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
Flight
STS-7
STS-32R
STS-50
STS-52
STS-62
STS-112
STS-107
Er#
06
25
45
55
62
115
93
ET Type
SWT
LWT
LWT
LWT
LWT
SLWT
LWT
Orbiier
Challenger
Columbia
Columbia
Columbia
Columbia
Atlantis
Columbia
Inclination
28.45 deg
28.45 deg
28.45 deg
28.45 deg
39.0 deg
51.6 deg
39.0 deg
Launch Date
06/18/83
01/09/90
06/25/92
10/22/92
03/04/94
10/07/02
01/16/03
Launch Time
(Local)
07:33:00
AMEDT
07:35:00
AM EST
12:12:23
PM EDT
1:09:39
PMEDT
08:53:00
AM EST
3:46:00
PM EDT
10:39:00
AMEDT
Figure 6.1-7. There have been seven known cases where the left External Tank bipod ramp foam has come off in flight.
came to be treated as "in-family."" a reportable problem that
was within the known experience base, was believed to be
understood, and was not regarded as a safety-of-flight issue.
Bipod Ramp Foam Loss Events
Chunks of foam from the E.xternal Tank's forward bipod
attachment, which connects the Orbiter to the External
Tank, are some of the largest pieces of debris that have
struck the Orbiter. To place the foam loss from STS-107
in a broader context, the Board examined every known
instance of foam-shedding from this area. Foam loss from
the left bipod ramp (called the -Y ramp in NASA parlance)
has been confirmed by imagery on 7 of the 113 missions
flown. However, only on 72 ofthe.se missions was available
imagery of sufficient quality to determine left bipod ramp
foam loss. Therefore, foam loss from the left bipod area oc-
curred on approximately 10 percent of flights (seven events
out of 72 imaged flights). On the 66 flights that imagery
was available for the right bipod area, foam loss was never
observed. NASA could not explain why only the left bipod
experienced foam loss. (See Figure 6.1-1.)
The first know n bipod ramp foam loss occurred during STS-7.
Challeni^er's second mission (see Figure 6.1-2). Images
taken after External Tank separation revealed that a 19- by
1 2-inch piece of the left bipod ramp was missing, and that the
External Tank had some 25 shallow divots in the foam just
forward of the bipod struts and another 40 divots in the foam
covering the lower External Tank. After the mission was
completed, the Program Requirements Control Board cited
the foam loss as an In-Flight Anomaly. Citing an event as an
In-Flight Anomaly means that before the next launch, a spe-
cific NASA organization must resolve the problem or prove
that it does not threaten the safety of the vehicle or crew."
At the Flight Readiness Review for the next mission. Orbiter
Project management reported that, based on the completion
of repairs to the Orbiter Thermal Protection System, the
bipod ramp foam loss In-Flight Anomaly was resolved, or
"closed." However, although the closure documents detailed
the repairs made to the Orbiter. neither the Certificate of
Flight Readiness documentation nor the Flight Readiness
Review documentation referenced correcting the cause of
the damaee - the slicddins of foam.
Figure 6.1-2. The first known instance of bipod ramp shedding oc-
curred on STS-7 which was launched on June 18, 1983.
Figure 6.1-3. Only three months before the Final launch of Colum-
bia, the bipod ramp foam had come off during STS112.
Report V o i. u r
August Z003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Umbilical Cameras and the
Statistics of Bipod Ramp Loss
Over llie course of the 1 13 Space Shuttle missions, the left
bipod ramp has shed significant pieces ol foam at least seven
times. (Foam-shedding from the right bipod ramp has never
been confirmed. The right bipod ramp may be less subject to
foam shedding because it is partially shielded from aerody-
namic forces by the Kxlernal Tank's liquid oxygen line.) The
fact that five of these left bipod shedding events occurred
on missions flown by Coliiiribia sparked considerable Board
debate. Although initially this appeared to be a ini|>robable
coincidence that would have caused the Board to fault NASA
for improper trend analysis and lack of engineering curiosity,
on closer in.spection, the Board concluded that this "coinci-
dence" is probably the result of a bias in the sample of known
bipod foam-shedding. Before the Cluilleiii^cr accident, only
Challenger and Colitnihia carried umbilical well cameras
that imaged the External Tank after separation, so there are
more images of Cnhiinhia than of the other Orbiters. '"
The bipod was imaged 26 of 28 of Coliiiiit?ia's missions; in
contrast. Challenger had 7 of 10, Discovery had only 14 of
30, Atlantis only 14 of 26. and Endeavour 12 of 19.
The second bipod ramp foam loss occurred during STS-32R.
Coliiinhia's ninth flight, on January 9. 1990. A post-mission
review of STS-32R photography revealed hve divots in the
intertank foam ranging from 6 to 28 inches in diameter, the
largest of which extended into the left bipod ramp foam. A
post-mission inspection of the lower suil^'ace of the Orbiter
revealed 1 1 1 hits. 13 of which were one inch or greater in
one dimension. An In-Flight Anomaly assigned to the Ex-
ternal Tank Project was closed out at the Flight Readiness
Review for the next mission, STS-36. on the basis that there
may have been local voids in the foam bipod ramp where
it attached to the metal skin of the External Tank. To ad-
dress the foam loss, NASA engineers poked small "vent
holes" through the intertank foam to allow trapped gases to
escape voids in the foam where they otherwise might build
up pressure and cause the foam to pop off. However, NASA
is still studying this hypothesized mechanism of foam loss.
Experiments conducted under the Board's purview indicate
that other mechanisms may be at work. (See "Foam Fracture
Under Hydrostatic Pressure" in Chapter 3.) As discussed in
Chapter 3, the Board notes that the persistent uncertainty
about the causes of foam loss and potential Orbiter damage
results from a lack of thorough hazard analysis and engi-
neering attention.
The third bipod foam loss occurred on June 25, 1992, during
the launch of Coliiiiihici on STS-50, when an approximately
26- by 10-inch piece separated from the left bipod ramp
area. Post-mission inspection revealed a 9-inch by 4.5-inch
by 0.5-inch divot in the tile, the largest area of tile damage in
Shuttle history. The External Tank Project at Marshall Space
Flight Center and the Integration Office at Johnson Space
Center cited separate In-Flight Anomalies. The Integration
Ofhce closed out its In-Flight Anomaly two days before
the next Might, STS-46. by deeming damage to the Thermal
Protection System an "accepted flight risk."'- In integra-
tion Hazard Report 37. the Integration Office noted that the
impact damage was shallow, the tile loss was not a result
of excessive aerodynamic loads, and the External Tank
Thermal Protection System failure was the result of "inad-
equate venting."" The External Tank Project closed out its
In-Flight Anomaly with the rationale that foam loss during
ascent was "not considered a flight or safety issue."'"* Note
the difference in how the each program addressed the foam-
shedding problem: While the Integration Office deemed it
an "accepted risk," the External Tank Project considered it
"not a safcty-of-flight issue." Hazard Report 37 would figure
in the STS-1 13 Flight Readiness Review, where the crucial
decision was made to continue flying with the foam-loss
problem. This inconsistency would reappear 10 years later,
after bipod foam-shedding during STS-1 12.
The fourth and fifth bipod ramp foam loss events went un-
detected until the Board directed NASA to review all avail-
able imagery for other instances of bipod foam-shedding.
This review of imagery from tracking cameras, the umbili-
cal well camera, and video and still images from flight crew
hand held cameras revealed bipod foam loss on STS-52 and
STS-62. both of which were flown by Cottttiihia. STS-52,
launched on October 22. 1992, lost an 8- by 4-inch corner
of the left bipod ramp as well as portions of foam cover-
ing the left jackpad, a piece of External Tank hardware
that facilitates the Orbiter attachment process. The STS-52
post-mission inspection noted a higher-than-average 290
hits on upper and lower Thermal Protection System tiles,
16 of which were greater than one inch in one dimension.
External Tank separation videos of STS-62. launched on
March 4, 1994, revealed that a 1- by 3-inch piece of foam
in the rear face of the left bipod ramp was missing, as were
small pieces of foam around the bipod ramp. Because these
incidents of missing bipod foam were not detected until
after the STS-1 07 accident, no In-Flight Anomalies had
been written. The Board concludes that NASA's failure to
identify these bipod foam losses at the time they occurred
means the agency must examine the adequacy of its film
review, post-flight inspection, and Program Requirements
Control Board processes.
The sixth and final bipod ramp event before STS-1 07 oc-
curred during STS-1 12 on October 7, 2002 (see Figure 6.1-
3). At 33 seconds after launch, when Atlantis was at 12,500
feet and traveling at Mach 0.75. ground cameras observed
an object traveling from the External Tank that subsequently
impacted the Solid Rocket Booster/External Tank Attach-
ment ring (see Figure 6.1-4). After impact, the debris broke
into multiple pieces that fell along the Solid Rocket Booster
exhaust plume. '"^ Post-mission inspection of the Solid Rocket
Booster confirmed damage to foam on the forward face of
the External Tank Attachment ring. The impact was approxi-
mately 4 inches wide and 3 inches deep. Post-External Tank
separation photography by the crew showed that a 4- by 5-
by 12-inch (240 cubic-inch) corner section of the left bipod
ramp was missing, which exposed the super lightweight
ablator coating on the bipod housing. This missing chunk of
foam was believed to be the debris that impacted the External
Tank Attachment ring during ascent. The post-launch review
of photos and video identified these debris events, but the
Mission Evaluation Room logs and Mission Management
Team minutes do not reflect any discussions of them.
Report Vouume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION 8DARD
Figure 6.1-4. On STS-112, the foam impacied fhe Exfernai Tank
Attach ring on the Solid Rocket Booster, causing this tear in the
insulation on the ring.
STS-113 Flight Readiness Review: A Pivotal Decision
Because the bipod ramp shedding on STS-1 12 was signifi-
cant, both in size and in the damage it caused, and because
it occurred only two flights before STS-107, the Board
investigated NASA's rationale to continue flying. This deci-
sion made by the Program Requirements Control Board at
the STS-1 13 Flight Readiness Review is among those most
directly linked to the STS-107 accident. Had the foam loss
during STS-112 been classified as a more serious threat,
managers might have responded differently when they heard
about the foam strike on STS-107. Alternately, in the face
of the increased risk. STS-107 might not have flown at all.
However, at STS-1 13"s Flight Readiness Review, managers
formally accepted a flight rationale that stated it was safe
to fly with foam losses. This decision enabled, and perhaps
even encouraged. Mission Management Team members to
use similar reasoning when evaluating whether the foam
strike on STS-107 posed a safety -of-flight issue.
At the Program Requirements Control Board meeting fol-
lowing the return of STS-1 12, the Intercenter Photo Work-
ing Group recommended that the loss of bipod foam be
classified as an In-Flight Anomaly. In a meeting chaired by
SPACE SHUTTLE PROGRAM
Space Shuttle Projects Office (MSFC)
STS-1 12/ET-1 15 Bipod Ramp Foam Loss
' Issue
• Foam was lost on the STS- 1 1 2yET-1 1 5 -Y
bipod ramp (•4" X 5" X 1 2") exposing the
bipod housing Sl_A closeout
' Background
' More than 100 External Tanks have ttown
with oniy 3 documented instances ot
significant foam loss on a bipod ramp
Shuttle Program Manager Ron Dittemore and attended by
many of the managers who would be actively involved with
STS-107, including Linda Ham, the Program Requirements
Control Board ultimately decided against such classifica-
tion. Instead, after discussions with the Integration Office
and the External Tank Project, the Program Requirements
Control Board Chairman assigned an "action'" to the Ex-
ternal Tank Project to determine the root cause of the foam
loss and to propose corrective action. This was inconsistent
with previous practice, in which all other known bipod
foam-shedding was designated as In-Flight Anomalies. The
Program Requirements Control Board initially set Decem-
ber 5. 2002, as the date to report back on this action, even
though STS-1 13 was scheduled to launch on November 10.
The due date subsequently slipped until after the planned
launch and return of STS-107. The Space Shuttle Program
decided to fly not one but two missions before resolving the
STS-1 12 foam loss.
The Board wondered why NASA would treat the STS-1 12
foam loss differently than all others. What drove managers
to reject the recommendation that the foam loss be deemed
an In-Flight Anomaly? Why did they take the unprecedented
step of scheduling not one but eventually two missions to fly
before the E.Mernal Tank Project was to report back on foam
losses? It seems that Shuttle managers had become condi-
tioned over time to not regard foam loss or debris as a safety-
of-flight concern. As will be discussed in Section 6.2, the
need to adhere to the Node 2 launch schedule also appears
to have influenced their decision. Had the STS-1 13 mission
been delayed beyond early December 2002, the Expedition
5 crew on board the Space Station would have exceeded its
1 80-day on-orbit limit, and the Node 2 launch date, a major
management goal, would not be met.
Even though the results of the External Tank Project en-
gineering analysis were not due until after STS- 113, the
foam-shedding was reported, or "'briefed," at STS-113's
Flight Readiness Review on October 31, 2002, a meeting
that Dittemore and Ham attended. Two slides from this brief
(Figure 6.1-5) explain the disposition of bipod ramp foam
loss on STS-1 12.
f CSS* SPACE SHUTTLE PROGRAM
, ^P'^^J Space Sfiuttle Projects Office (H/ISFC)
^Qf
STS-1 12/ET-1 15 Bipod Ramp Foam Loss
' Rationale for Flight
• Current bipod ramp closeout has not been changed
. The Orbiter has not yet expenenced "Satety
of Flight" damage from loss of foam in
112 flights (including 3 known flights
with bipod ramp foam loss)
- There have been no design I process /
equipment changes over the last 60
ETs (flights)
. All ramp closeout wor1< (including ET-115 and ET-116)
performed by expenenced practitioners (all over 20 years
experience each)
. Ramp foam application involves craflmanship in the use of
validated application processess
• No change in Inspection / Process control / Post application handling, etc
• Probability of loss of ramp TPS is no higher/no lower than previous flights
• TheET is safe to fly with no new concerns (and no added risk)
Figure 6.?-5. These two brieFing slides are from the STS 113 Flight Readiness Review. The First and third bullets on the right-hand slide are
incorrect since the design of the bipod ramp had changed several times since the flights listed on fhe slide.
REPORT VOLUr
(OUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
This rationale is seriously flawed. The first and third state-
ments listed under "Rationale for Flight" are incorrect. Con-
trary to the chart, which was presented by Jerry Smelser, the
Program Manager for the External Tank Project, the bipod
ramp design had changed, as of External Tank-76. This
casts doubt on the implied argument that because the design
had not changed, future bipod foam events were unlikely
to occur. Although the other points may be factually cor-
rect, they provide an exceptionally weak rationale for safe
flight. The fact that ramp closeout work was "performed
by experienced practitioners" or that "application involves
craftsmanship in the use of validated application processes"
in no way decreases the chances of recurrent foam loss. The
statement that the "probability of loss of ramp Thermal Pro-
tection System is no higher/no lower than previous flights"
could be just as accurately stated "the probability of bipod
foam loss on the next flight is just as high as it was on previ-
ous flights." With no engineering analysis. Shuttle managers
used past success as a justification for future flights, and
made no change to the External Tank configurations planned
for STS- 1 1 3. and. subsequently, for STS- 1 07.
Along with this chart, the NASA Headquarters Safety
Office presented a report that estimated a 99 percent prob-
ability of foam not being shed from the same area, even
though no corrective action had been taken following the
STS-112 foam-shedding."' The ostensible justification for
the 99 percent figure was a calculation of the actual rate of
bipod loss over 61 flights. This calculation was a sleight-
of-hand effort to make the probability of bipod foam loss
appear low rather than a serious grappling with the prob-
ability of bipod ramp foam separating. For one thing, the
calculation equates the probability oi left and right bipod
loss, when right bipod loss has never been observed, and the
amount of imagery available for left and right bipod events
differs. The calculation also miscounts the actual number
of bipod ramp losses in two ways. First, by restricting the
sampfe size to flights between STS-1 12 and the last known
bipod ramp loss, it excludes known bipod ramp losses from
STS-7. STS-32R, and STS-50. Second, by failing to project
the statistical rate of bipod loss across the many missions
for which no bipod imagery is available, the calculation
assumes a "what you don't see won't hurt you" mentality
when in fact the reverse is true. When the statistical rate
of bipod foam loss is projected across missions for which
imagery is not available, and the sample size is extended
to include every mission from STS-1 on. the probability of
bipod loss increases dramatically. The Board's review after
STS- 107, which included the discovery of two additional
bipod ramp losses that NASA had not previously noted,
concluded that bipod foam loss occurred on approximately
10 percent of all missions.
During the brief at STS- 1 1 3's Flight Readiness Review, the
Associate Administrator for Safety and Mission Assurance
scrutinized the Integration Hazard Report 37 conclusion
that debris-shedding was an accepted risk, as well as the
External Tank Project's rationale for flight. After confer-
ring, STS-1 13 Flight Readiness Review participants ulti-
mately agreed that foam shedding should be characterized
as an "accepted risk" rather than a "not a safety-of-flight"
issue. Space Shuttle Program management accepted this
rationale, and STS-1 1 3's Certificate of Flight Readiness
was signed.
The decision made at the STS-113 Flight Readiness Review
seemingly acknowledged that the foam posed a threat to the
Orbiter, although the continuing disagreement over whether
foam was "not a safety of flight issue" versus an "accepted
risk" demonstrates how the two terms became blurred over
time, clouding the precise conditions under which an increase
in risk would be pemiitted by Shuttle Program management.
In retrospect, the bipod foam that caused a 4- by 3-inch
gouge in the foam on one of Atlantis' Solid Rocket Boosters
-just months before STS- 107 - was a "strong signal" of po-
tential future damage that Shuttle engineers ignored. Despite
the significant bipod foam loss on STS-1 12, Shuttle Program
engineers made no External Tank configuration changes, no
moves to reduce the risk of bipod ramp shedding or poten-
tial damage to the Orbiter on either of the next two flights,
STS- i 1 3 and STS- 1 07, and did not update Integrated Hazard
Report 37. The Board notes that although there is a process
for conducting hazard analyses when the system is designed
and a process for re-evaluating them when a design is
changed or the component is replaced, no process addresses
the need to update a hazard analysis when anomalies occur. A
stronger Integration Office would likely have insisted that In-
tegrated Hazard Analysis 37 be updated. In the course of that
update, engineers would be forced to consider the cause of
foam-shedding and the effects of shedding on other Shuttle
elements, including the Orbiter Thermal Protection System.
STS-1 13 launched at night, and although it is occasionally
possible to image the Orbiter from light given off by the
Solid Rocket Motor plume, in this instance no imagery was
obtained and it is possible that foam could have been shed.
The acceptance of the rationale to fly cleared the way for
Coliiiuhia's launch and provided a method for Mission man-
agers to classify the STS- 107 foam strike as a maintenance
and turnaround concern rather than a safety-of-flight issue.
It is significant that in retrospect, several NASA managers
identified their acceptance of this flight rationale as a seri-
ous error.
The foam-loss issue was considered so insignificant by some
Shuttle Program engineers and managers that the STS- 107
Flight Readiness Review documents include no discussion
of the still-unresolved STS-1 12 foam loss. According to Pro-
gram rules, this discussion was not a requirement because
the STS-1 12 incident was only identified as an "action," not
an In-Flight Anomaly. However, because the action was still
open, and the date of its resolution had slipped, the Board be-
lieves that Shuttle Program managers should have addressed
it. Had the foam issue been discussed in STS- 107 pre-launch
meetings. Mission managers may have been more sensitive
to the foam-shedding, and may have taken more aggressive
steps to determine the extent of the damage.
The seventh and final known bipod ramp foam loss occurred
on Januai7 16, 2003, during the launch of Columbia on
STS- 107. After the Columbia bipod loss, the Program Re-
quirements Control Board deemed the foam loss an In-Flight
Anomaly to be dealt with by the External Tank Project.
Report volume 1
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Other Foam/Debris Events
To better understand how NASA's treatment of debris strikes
evolved over time, the Board investigated missions where
debris was shed from locations other than the External Tank
bipod ramp. The number of debris strikes to the Orbiters"
lower surface Thermal Protection System that resulted in tile
damage greater than one inch in diameter is shown in Figure
6.1-6.'^ The number of debris strikes may be small, but a
single strike could damage several tiles (see Figure 6. 1-7).
One debris strike in particular foreshadows the STS-107
event. When Atlantis was launched on STS-27R on De-
cember 2, 1988, the largest debris event up to that time
significantly damaged the Orbiter. Post-launch analysis of
tracking camera imagerv by the Intercenter Photo Working
Group identified a large piece of debris that struck the Ther-
mal Protection System tile at approximately 85 seconds into
the flight. On Flight Day Two, Mission Control asked the
flight crew to inspect Atlantis with a camera mounted on the
remote manipulator arm, a robotic device that was not in-
stalled on Coliinihia for STS-107. Mission Commander R.L.
"Hoot" Gibson later stated that Atlantis "looked like it had
been blasted by a shotgun.'""* Concerned that the Orbiter's
Thermal Protection System had been breached, Gibson or-
dered that the video be transferred to Mission Control so that
NASA engineers could evaluate the damage.
When Atlantis landed, engineers were surprised by the ex-
tent of the damage. Post-mission inspections deemed it "the
most severe of any mission yet flown."''' The Orbiter had
707 dings, 298 of which were greater than an inch in one di-
mension. Damage was concentrated outboard of a line right
of the bipod attachment to the liquid oxygen umbilical line.
Even more worrisome, the debris had knocked off a tile, ex-
posing the Orbiter's skin to the heat of re-entry. Post-flight
analysis concluded that structural damage was confined to
the exposed cavity left by the missing tile, which happened
to be at the location of a thick aluminum plate covering an
L-band navigation antenna. Were it not for the thick alumi-
num plate, Gibson stated during a presentation to the Board
that a burn-through may have occurred.-"
The Board notes the distinctly different ways in which the
STS-27R and STS-107 debris strike events were treated.
After the discovery of the debris strike on Flight Day Two
of STS-27R. the crew was immediately directed to inspect
the vehicle. More severe thermal damage - perhaps even a
bum-through - may have occurred were it not for the alu-
minum plate at the site of the tile loss. Fourteen years later,
when a debris strike was discovered on Flight Day Two of
STS-107. Shuttle Program management declined to have the
crew inspect the Orbiter for damage, declined to request on-
orbit imaging, and ultimately discounted the possibility of a
burn-through. In retrospect, the debris strike on STS-27R is
a "strong signal" of the threat debris posed that should have
been considered by Shuttle management when STS-107 suf-
fered a similar debris strike. The Board views the failure to
do so as an illustration of the lack of institutional memory in
the Space Shuttle Program that supports the Board's claim,
discussed in Chapter 7. that NASA is not functioning as a
learning organization.
After the STS-27R damage was evaluated during a post-
flight inspection, the Program Requirements Control Board
assigned In-Flight Anomalies to the Orbiter and Solid Rock-
et Booster Projects. Marshall Sprayable Ablator (MSA- 1)
material found embedded in an insulation blanket on the
right Orbital Maneuvering System pod confirmed that the
ablator on the right Solid Rocket Booster nose cap was the
most likely source of debris.-' Because an improved ablator
material (MSA-2) would now be used on the Solid Rocket
Booster nose cap. the issue was considered "closed" by the
time of the next mission's Flight Readiness Review. The
Orbiter Thermal Protection System review team concurred
with the u.se of the improved ablator without reservation.
.An S rS-27R investigation team notation mirrors a Colum-
bia Accident Investigation Board finding. The STS-27R
investigation noted: "it is observed that program emphasis
Lower surface
damage clings
>1 inch
diameter
i STS-26R
OV-103, Flight?
T Bipod Ramp Foam Loss Event
1L...J1IIII1.II1 I
STS-27R
OV-104, Flights
Cause: SRB Ablative
STS-73
OV-102, Flight 18
STS-87
OV-102, Flight 24
Cause: ET Intertank Foam
I -. lu ^ — / I 1^
llillibi.i.illiJl.liJiiln.l..Iill.LiLlll^i...ii.H.llUuibllllfa.iJilillh^
Space Shuttle Mission Number
Figure 6.) -6. T/i/s chart shows the number of dings greater thar\ one inch in diameter on the lower surface of the Orhiter after each mission
from STS-6 through STS-113. Flights where the bipod ramp foam is known to have come off are marked with a red triangle.
Report Volume
■ BUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
MISSION
DATE
COMMENTS
STS-1
April 12, 1981
Lots of debris damage. 300 tiles replaced.
STS-7
June 18, 1983
First known left bipod ramp foam shedding event.
STS-27R
December 2, 1988
Debris knocks off tile; structural damage and near burn through results.
STS-32R
January 9, 1990
Second knov/n left bipod ramp foam event.
STS-35
December 2, 1990
First time NASA calls foam debris "safety of flight issue," and "re-use or turn-
around issue."
STS-42
January 22, 1992
First mission after which the next mission (STS-45) launched without debris In-
Flight Anomaly closure/resolution.
STS-45
March 24, 1992
Damage to wing RCC Panel 10-right. Unexplained Anomaly, "most likely orbital
debris."
STS-50
June 25, 1992
Third known bipod ramp foam event. Hazard Report 37: an "accepted risk."
STS-52
October 22, 1992
Undetected bipod romp foam loss (Fourth bipod event).
STS-56
April 8, 1993
Acreage tile damage (large area). Called "within experience base" and consid-
ered "in family."
STS-62
October 4, 1994
Undetected bipod ramp foam loss (Fifth bipod event).
STS-87
November 19, 1997
Damage to Orbiter Thermal Protection System spurs NASA to begin 9 flight
tests to resolve foam-shedding. Foam fix ineffective. In-Flight Anomaly eventually
closed after STS-1 01 as "accepted risk."
STS-n2
October 7, 2002
Sixth known left bipod ramp foam loss. First time major debris event not assigned
an In-Flight Anomaly. External Tank Project was assigned an Action. Not closed
out until after STS-1 13 and STS-1 07
STS-1 07
January 16, 2003
Columbia launch. Seventh known left bipod ramp foam loss event.
Figure 6.1-7. The Board idenfifiec/ 14 flights fhai had significant Thermal Protection System damage or major foam loss. Two of the bipod foam
loss events had not been detected by NASA prior to the Columbia Accident Investigation Board requesting a review of all launch images.
and attention to tile daniai^e a.s.se.s.'inient.s varies with severity
and that detailed records could be augmented to ease trend
maintenance" (emphasis added)." In other words. Space
Shuttle Program personnel knew that the monitoring of
tile damage was inadequate and that clear trends could be
more readily identified if monitoring was improved, but no
such improvements were made. The Board also noted that
an STS-27R investigation team recommendation correlated
to the Columbia accident 14 years later: "It is recommended
that the program actively solicit design improvements di-
rected toward eliminating debris sources or minimizing
damage potential."-'
Another instance of non-bipod foam damage occurred on
STS-35. Post-flight inspections o^ Columbia after STS-S.^i in
December 1990. showed a higher-than-average amount of
damage on the Orbiter's lower surface. A review of External
Tank separation film revealed approximately 10 areas of
missing foam on the flange connecting the liquid hydrogen
tank to the inteilank. An In-Flight Anomaly was assigned
to the External Tank Project, which closed it by stating that
there was no increase in Orbiter Thermal Protection System
damage and that it was "not a .safety-of-flight concern. "-"*
The Board notes that it was in a discussion at the STS-36
Flight Readiness Review that NASA first identified this
problem as a turnaround issue." Per established procedures.
NASA was still designating foam-loss events as In-Flight
Anomalies and continued to make various corrective ac-
tions, such as drilling more vent holes and improving the
foam application process.
Discovery was launched on STS-42 on January 22, 1992. A
total of 159 hits on the Orbiter Thermal Protection System
were noted after landing. Two 8- to 12-inch-diameter div-
ots in the External Tank intertank area were noted during
post-External Tank separation photo evaluation, and these
pieces of foam were identified as the most probable sources
of the damage. The External Tank Project was assigned an
Report Volume i
iT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
In-Flight Anomaly, and the incident was later described as
an unexplained or isolated event. However, at later Flight
Readiness Reviews, the Marshall Space Flight Center
briefed this as being "not a safety-of-fiight" concern.-" The
next flight, STS-45, would be the first mission launched be-
fore the foam-loss in-Flight Anomaly was closed.
On March 24. 1992, Atlantis was launched on STS-45.
Post-mission inspection revealed exposed substrate on the
upper surface of right wing leading edge Reinforced Car-
bon-Carbon (RCC) panel 10 caused by two gouges, one 1.9
inches by 1.6 inches and the other 0.4 inches by I inch.-^
Before the next flight, an In-Flight Anomaly assigned to
the Orbiter Project was closed as "unexplained," but "most
likely orbital debris."-** Despite this closure, the Safety and
Mission Assurance Office expressed concern as late as the
pre-launch Mission Management Team meeting two days
before the launch of STS-49. Nevertheless, the mission was
cleared for launch. Later laboratory tests identified pieces
of man-made debris lodged in the RCC, including stainless
steel, aluminum, and titanium, but no conclusion was made
about the source of the debris. (The Board notes that this
indicates there were transport mechanisms available to de-
termine the path the debris took to impact the wing leading
edge. See Section 3.4.)
The Program Requirements Control Board also assigned the
External Tank Project an In-Flight Anomaly after foam loss
on STS-.'56 (Discovery) and STS-58 (Cohtmhia). both of
which were launched in 1993. These missions demonstrate
the increasingly casual ways in which debris impacts were
dispositioned by Shuttle Program managers. After post-
flight analysis determined that on both missions the foam
had come from the intertank and bipod jackpad areas, the
rationale for closing the In-Flight Anomalies included nota-
tions that the External Tank foam debris was "in-family," or
within the experience base.-''
During the launch of STS-87 (Columbia) on November 19,
1997, a debris event focused NASA's attention on debris-
shedding and damage to the Orbiter Post-External Tank
separation photography revealed a significant loss of mate-
rial from both thrust panels, which are fastened to the Solid
Rocket Booster forward attachment points on the intertank
structure. Post-landing inspection of the Orbiter noted 308
hits, with 244 on the lower surface and 109 larger than an
inch. The foam loss from the External Tank thrust panels was
suspected as the most probable cause of the Orbiter Thermal
Protection System damage. Based on data from post-flight
inspection reports, as well as comparisons with statistics
from 71 similarly configured flights, the total number of
damage sites, and the number of damage sites one inch or
larger, were considered "out-of-family."'" An investigation
was conducted to determine the cause of the material loss
and the actions required to prevent a recurrence.
The foam loss problem on STS-87 was described as "pop-
coming" because of the numerous popcorn-size foam par-
ticles that came off the thrust panels. Popcorning has always
occurred, but it began earlier than usual in the launch of
STS-87. The cause of the earlier-than-normal popcorning
(but not the fundamental cause of popcorning) was traced
back to a change in foam-blowing agents that caused pres-
sure buildups and stress concentrations within the foam. In
an effort to reduce its use of chlorofluorocarbons (CFCs),
NASA had switched from a CFC-ll (chlorofluorocarbon)
blowing agent to an HCFC-14lb blowing agent beginning
with External Tank-85, which was assigned to STS-84. (The
change in blowing agent affected only mechanically applied
foam. Foam that is hand sprayed, such as on the bipod ramp,
is still applied using CFC-1 1.)
The Program Requirements Control Board issued a Direc-
tive and the External Tank Project was assigned an In-Flight
Anomaly to address the intertank thrust panel foam loss.
Over the course of nine missions, the External Tank Project
first reduced the thickness of the foam on the thrust panels
to minimize the amount of foam that could be shed; and,
due to a misunderstanding of what caused foam loss at
that time, put vent holes in the thrust panel foam to relieve
trapped gas pressure.
The In-Flight Anomaly remained open during these changes,
and foam shedding occurred on the nine missions that tested
the corrective actions. Following STS-101, the 10th mission
after STS-87, the Program Requirements Control Board
concluded that foam-shedding from the thrust panel had
been reduced to an "acceptable level" by sanding and vent-
ing, and the In-Flight Anomaly was closed." The Orbiter
Project, External Tank Project, and Space Shuttle Program
management all accepted this rationale without question.
The Board notes that these interventions merely reduced
foam-shedding to previously experienced levels, which have
remained relatively constant over the Shuttle's lifetime.
Making the Orbiter More Resistant To Debris Strikes
If foam shedding could not be prevented entirely, what did
NASA do to make the Thermal Protection System more
resistant to debris strikes? A 1990 study by Dr. Elisabeth
Pate-Cornell and Paul Fishback attempted to quantify the
risk of a Thermal Protection System failure using probabilis-
tic analysis.'- The data they used included ( 1 ) the probability
that a tile would become debonded by either debris strikes or
a poor bond, (2) the probability of then losing adjacent tiles,
(3) depending on the final size of the failed area, the prob-
ability of burn-through, and (4) the probability of failure of
a critical sub-system if burn-through occurs. The study con-
cluded that the probability of losing an Orbiter on any given
mission due to a failure of Thermal Protection System tiles
was approximately one in 1,000. Debris-related problems
accounted for approximately 40 percent of the probability,
while 60 percent was attributable to tile debonding caused
by other factors. An estimated 85 percent of the risk could
be attributed to 15 percent of the "acreage," or larger areas
of tile, meaning that the loss of any one of a relatively small
number of tiles pose a relatively large amount of risk to the
Orbiter. In other words, not all tiles are equal - losing certain
tiles is more dangerous. While the actual risk may be differ-
ent than that computed in the 1990 study due to the limited
amount of data and the underiying simplified assumptions,
this type of analysis offers insight that enables management
to concentrate their resources on protecting the Orbiters'
critical areas.
Report Volume I
lOUST 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Two years after the conclusion of that study, NASA wrote
to Pate-Cornel! and Fishback describing the importance
of their work, and stated that it was developing a long-
term effort to use probabilistic risk assessment and related
disciplines to improve programmatic decisions." Though
NASA has taken some measures to invest in probabilistic
risk assessment as a tool, it is the Board's view that NASA
has not fully exploited the insights that Pate-Cornell's and
Fishback "s work offered.'"
Impact Resistant Tile
NASA also evaluated the possibility of increasing Thermal
Protection System tile resistance to debris hits, lowering the
possibility of tile debonding, and reducing tile production
and maintenance costs." Indeed, tiles with a "tough" coat-
ing are currently used on the Orbiters. This coating, known
as Toughened Uni-piece Fibrous Insulation (TUFI), was
patented in 1992 and developed for use on high-temperature
rigid insulation."' TUFI is used on a tile material known as
Alumina Enhanced Thermal Barrier (AETB), and has a de-
bris impact resistance that is greater than the current acreage
tile's resistance by a factor of approximately 6-20." At least
772 of these advanced tiles have been installed on the Orbit-
ers' base heat shields and upper body flaps. '** However, due
to its higher thermal conductivity, TUFI-coated AETB can-
not be used as a replacement for the larger areas of tile cov-
erage. (Boeing, Lockheed Martin and NASA are developing
a lightweight, impact-resistant, low-conductivity tile.'")
Because the impact requirements for these next-generation
tiles do not appear to be based on resistance to specific (and
probable) damage sources, it is the Board's view that certifi-
cation of the new tile will not adequately address the threat
posed by debris.
Conclusion
Despite original design requirements that the External Tank
not shed debris, and the corresponding design requirement
that the Orbiter not receive debris hits exceeding a trivial
amount of force, debris has impacted the Shuttle on each
flight. Over the course of 1 13 missions, foam-shedding and
other debris impacts came to be regarded more as a turn-
around or maintenance issue, and less as a hazard to the
vehicle and crew.
Assessments of foam-shedding and strikes were not thor-
oughly substantiated by engineering analysis, and the pro-
cess for closing In-Flight Anomalies is not well-documented
and appears to vary. Shuttle Program managers appear to
have confused the notion of foam posing an "accepted risk"
with foam not being a "safety-of-flight issue." At times, the
pressure to meet the flight schedule appeared to cut short
engineering efforts to resolve the foam-shedding problem.
NASA's lack of understanding of foam properties and be-
havior must also be questioned. Although tests were con-
ducted to develop and qualify foam for use on the External
Tank, it appears there were large gaps in NASA's knowledge
about this complex and variable material. Recent testing
conducted at Marshall Space Flight Center and under the
auspices of the Board indicate that mechanisms previously
considered a prime source of foam loss, cryopumping and
cryoingestion, are not feasible in the conditions experienced
during tanking, launch, and ascent. Also, dissections of foam
bipod ramps on External Tanks yet to be launched reveal
subsurface flaws and defects that only now are being discov-
ered and identified as contributing to the loss of foam from
the bipod ramps.
While NASA properly designated key debris events as In-
Flight Anomalies in the past, more recent events indicate
that NASA engineers and management did not appreciate
the scope, or lack of scope, of the Hazard Reports involv-
ing foam shedding.*"' Ultimately, NASA's hazard analyses,
which were based on reducing or eliminating foam-shed-
ding, were not succeeding. Shuttle Program management
made no adjustments to the analyses to recognize this fact.
The acceptance of events that are not supposed to happen
has been described by sociologist Diane Vaughan as the
"normalization of deviance."*" The history of foam-problem
decisions shows how NASA first began and then continued
flying with foam losses, so that flying with these deviations
from design specifications was viewed as normal and ac-
ceptable. Dr. Richard Feynman, a member of the Presiden-
tial Commission on the Space Shuttle Challenger Accident,
discusses this phenomena in the context of the Clialleii^er
accident. The parallels are .striking:
The phenomenon of cicreptini> . . . flight seals that had
shown erosion and hlow-hy in previous flights is very
clear. The Challenf>er flight is an excellent example.
There are several references to flights that had gone he-
fore. The acceptance and success (yf these flights is taken
as evidence of safety. But erosions and hlow-hy are not
what the design expected. They are warnings that some-
thing is wrong . . . The 0-rings of the Solid Rocket Boost-
ers were not designed to erode. Erosion was a clue that
something was wrong. Erosion was not something from
which safef}' can he inferred ... If a reasonable launch
schedule is to he maintained, engineering often cannot
be done fast enough to keep up with the expectations of
origmally conservative certification criteria designed
to guarantee a very safe vehicle. In these situations,
subtly, and often with apparently logical arguments, the
criteria are altered so that flights may still be certified in
time. They thereft)re fly in a relatively iin.safe condition,
with a chance of failure of the order of a percent (it is
difficult to he more accurate).'*^
Findings
F6. 1 -1 NASA has not followed its own rules and require-
ments on foam-shedding. Although the agency
continuously worked on the foam-shedding
problem, the debris impact requirements have not
been met on any mission.
F6. 1-2 Foam-shedding, which had initially raised seri-
ous safety concerns, evolved into "in-family" or
"no safety-of-flight" events or were deemed an
"accepted risk."
F6. 1-3 Five of the seven bipod ramp events occurred
on missions flown by Columbia, a seemingly
high number. This observation is likely due to
Report Volume i
AuausT 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Cohiinhia having been equipped with umbilical
cameras earlier than other Orbiters.
F6. 1 -4 There is lack of effective processes for feedback
or integration among project elements in the reso-
lution of in-Flight Anomalies.
F6. 1 -5 Foam bipod debris-shedding incidents on STS-52
and STS-62 were undetected at the time they oc-
curred, and were not discovered until the Board
directed NASA to examine External Tank separa-
tion images more closely.
F6. 1-6 Foam bipod debris-shedding events were clas-
sified as In-Flight Anomalies up until STS-II2,
which was the first known bipod foam-shedding
event not classified as an In-Flight Anomaly.
F6. 1-7 The STS-112 assignment for the External Tank
Project to "identify the cause and corrective ac-
tion of the bipod ramp foam loss event" was not
due until after the planned launch of STS-113.
and then slipped to after the launch of STS- 107.
F6. 1-8 No External Tank configuration changes were
made after the bipod foam loss on STS-1 12.
F6. 1 -9 Although it is sometimes possible to obtain imag-
ery of night launches because of light provided by
the Solid Rcx'ket Motor plume, no imagery was
obtained for STS- 113.
F6. 1-10 NASA failed to adequately perform trend analy-
sis on foam losses. This greatly hampered the
agency's ability to make informed decisions
about foam losses.
F6. 1 - 1 1 Despite the constant shedding of foam, the Shut-
tle Program did little to harden the Orbiter against
foam impacts through upgrades to the Thermal
Protection System. Without impact resistance
and strength requirements that are calibrated to
the energy of debris likely to impact the Orbiter,
certification of new Thermal Protection System
tile will not adequately address the threat posed
by debris.
Reconfimendations:
• None
6.2 Schedule Pressure
Countdown to Space Station "Core Complete:" A
Workforce Under Pressure
During the course of this investigation, the Board received
several unsolicited comments from NASA personnel regard-
ing pressure to meet a schedule. These comments all con-
cerned a date, more than a year after the launch of Coliimhia.
that seemed etched in stone: February 19, 2004, the sched-
uled launch date of STS- 1 20. This flight was a milestone in
the minds of NASA management since it would carry a sec-
tion of the International Space Station called "Node 2." This
would configure the International Space Station to its "U.S.
Core Complete" status.
At first glance, the Core Complete configuration date
seemed noteworthy but unrelated to the Coliimhia accident.
However, as the investigation continued, it became apparent
that the complexity and political mandates surrounding the
International Space Station Program, as well as Shuttle Pro-
gram management's responses to them, resulted in pressure
to meet an increasingly ambitious launch schedule.
In mid-2001. NASA adopted plans to make the over-budget
and behind-schedule International Space Station credible to
the White House and Congress. The Space Station Program
and NASA were on probation, and had to prove they could
meet schedules and budgets. The plan to regain credibility fo-
cused on the Februarv' 19, 2004, date for the launch of Node
2 and the resultant Core Complete status. If this goal was not
met. NASA would risk losing support from the White House
and Congress for subsequent Space Station growth.
By the late summer of 2002, a variety of problems caused
Space Station assembly work and Shuttle flights to slip be-
yond their target dates. With the Node 2 launch endpoint
fixed, these delays caused the schedule to become ever more
compressed.
Meeting U.S. Core Complete by February 19, 2004, would
require preparing and launching 10 flights in less than 16
months. With the focus on retaining support for the Space
Station program, little attention was paid to the effects the
aggressive Node 2 launch date would have on the Shuttle
Program. After years of downsizing and budget cuts (Chapter
5), this mandate and events in the months leading up to STS-
107 intrtKluced elements of risk to the Program. Coliimhia
and the STS- 1 07 crew, who had seen numerous launch slips
due to missions that were deemed higher priorities, were
further affected by the mandatory Core Complete date. The
high-pressure environments created by NASA Headquarters
unquestionably affected Coliimhia, even though it was not
flying to the International Space Station.
February 19, 2004 - "A Line in the Sand"
Schedules are essential tools that help large organizations
effectively manage their resources. Aggressive schedules by
themselves are often a sign of a healthy institution. How-
ever, other institutional goals, such as safety, sometimes
compete with schedules, so the effects of schedule pres-
sure in an organization must be carefully monitored. The
Board posed the question: Was there undue pressure to nail
the Node 2 launch date to the February 19. 2004, signpost?
The management and workforce of the Shuttle and Space
Station programs each answered the question differently.
Various members of NASA upper management gave a defi-
nite "no." In contrast, the workforce within both programs
thought there was considerable management focus on Node
2 and resulting pressure to hold firm to that launch date, and
individuals were becoming concerned that safety might be
compromised. The weight of evidence supports the work-
force view.
Employees attributed the Node 2 launch date to the new
Administrator, Sean O'Keefe, who was appointed to execute
a Space Station management plan he had proposed as Dep-
uty Director of the White House Office of Management and
Budget. They understood the scrutiny that NASA, the new
Administrator, and the Space Station Program were under.
Report Volui
August 2003
1 3 1
COLUMBIA
ACCIDENT INVESTIGATION BOARD
but now it seemed to some that budget and schedule were of
paramount concern. As one employee reflected:
I i;iiess niY frustration was ...I know the importance of
sl]owint> that yon . . . inanai^e your hiulget and that 's an
important impression to make to Congress so you can
contitiue the future of the agency, hut to a lot of people,
Fehruary 19th just seemed like an arbitrary date ...
It doesn 't make sen.se to me why at all costs we were
marching to this date.
The importance of this date was stressed from the very top.
The Space Shuttle and Space Station Program Managers
briefed the new NASA Administrator monthly on the status
of their programs, and a significant part of those briefings
was the days of margin remaining in the schedule to the
launch of Node 2 - still well over a year away. The Node 2
schedule margin typically accounted for more than half of
the briefing slides.
Figure 6.2-1 is one of the charts presented by the Shuttle
Program Manager to the NASA Administrator in December
2002. The chart shows how the days of margin in the exist-
ing schedule were being managed to meet the requirement
of a Node 2 launch on the prescribed date. The triangles
are events that affected the schedule (such as the slip of a
Russian Soyuz flight). The squares indicate action taken
by management to regain the lost time (such as authorizing
work over the 2002 winter holidays).
Figure 6.2-2 shows a slide from the International Space Sta-
tion Program Manager's portion of the briefing. It indicates
that International Space Station Program management was
also taking actions to regain margin. Over the months, the
extent of some testing at Kennedy was reduced, the number
of tasks done in parallel was increased, and a third shift of
workers would be added in 2003 to accomplish the process-
ing. These charts illustrate that both the Space Shuttle and
Space Station Programs were being managed to a particular
launch date - February 19, 2004. Days of margin in that
schedule were one of the principle metrics by which both
programs came to be judged.
NASA Headquarters stressed the importance of this date in
other ways. A screen saver (see Figure 6.2-3) was mailed
to managers in NASA's human spaceflight program that
depicted a clock counting down to February 19, 2004 - U.S.
Core Complete.
flS
SSP Schedule Reserve
c
03
SSP Core Complete 35
Sctiedule hAargin - PdSt 28
A A
t
A
A
s
A
A
A
Late OMM start (Node 2 was on
OV-103)
Moved Node2toOV-105
Accommodate 4S slip 1 week
ISS adding wrist joint on UF2
Moved OV-104 Str Ins, to 9*^ At
Engine Flowliner cracks
Reduced Structural Inspection
Requirements
Accommodate 4S slip
02 flexline leak/ SRMS damage
Defer reqmts; apply reserve
D Management action
A Schedule impact event
SSP Core Complete Schedule Threats
STS-120/Node 2 launch subject to 45 days of schedule risk
• HQ mitigate Range Cutout
• HQ and ISS mitigate Soyuz
• HQ mitigate Range Cutout
• HQ and ISS mitigate Soyuz
• HQ and ISS mitigate Soyuz
Management Options
' USA commit holiday/weekend reserves and
apply additional resources (i.e., S'^shift) to
hold schedule (Note: 3'" shift not yet included)
• HQ mitigate Range Cutout
' HQ and ISS mitigate Soyuz conflict threat
Figure 6.2-1. This chart was presented by the Space Shuttle Program Manager to the NASA Administrator in December 2002. It illustrates
how the schedule was being managed to meet the Node 2 launch date of February J9, 2004.
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARD
While employees found this amusing because they saw it as
a date that could not be met, it also reinforced the message
that NASA Headquarters was focused on and promoting the
achievement of that date. This schedule was on the minds of
the Shuttle managers in the months leading up to STS-i07.
The Background: Schedule Complexity and
Compression
In 2001, the International Space Station Cost and Manage-
ment Evaluation Task Force report recommended, as a
cost-saving measure, a limit of four Shuttle flights to the In-
ternational Space Station per year. To meet this requirement,
managers began adjusting the Shuttle and Station manifests
to "get back in the budget box." They reananged Station
assembly sequences, moving some elements forward and
taking others out. When all was said and done, the launch
of STS-120. which would carry Node 2 to the International
Space Station, fell on February 19. 2004.
The Core Complete date simply emerged from this plan-
ning effort in 2001. By all accounts, it was a realistic and
achievable date when first approved. At the time there was
more concern that four Shuttle flights a year would limit the
coomtccv.'w to
Spjce Station Ptogtam
TS
!
US Coite Complete
>.
. V
February 19 2004
>-^%
'■ *llw
477 iiayi to yo
li
1 1 4 S 9 tKiurs to gvi
J
^^Se 't'
HW*
S 8 7 5 9 3 minutes tc* s,c
t
^ll^af^<l!lvs^^^
-ii'
4 1255585 wconds to ;,.
#7
■l^y
f
477:11:53:105
if
(
t.
tf^
Figure 6.2-3. NASA Headquarters distributed to NASA employees
this computer Screensaver counting down to February 19, 2004.
capability to can^ supplies to and from the Space Station,
to rotate its crew, and to transport remaining Space Station
segments and equipment. Still, managers felt it was a rea-
^^Sj
ISS Schedule Reserve
c
1 0
o
E
c
- —
0.0
c
m
ro
-30
/SS Core Complete Schedule Margin
45 days
67 5 days
Schedule margin decreased 0 75
month due to KSC Systems Test
growth and closeouts growth
1 75 months slip to on dock (0/D)
at KSC Alenia build and
subcontractor problems
Reduced KSC Systems Test
Preps/Site Activation and Systems
Test scope
3 months slip to 0/D at KSC,
Alenia assembly and financial
problems
Reduced scope and testing;
worked KSC tasks in parallel (e g.:
Closeouts & Leak Checks)
1 25 months slip to O/D at KSC
Alenia work planning inefficiencies
Increased the number of KSC
tasks in parallel, and adjusted
powered-on testing to 3
shifts/day/5days/week
6/01
9/01
2/02
■ As of Date Schedule Time
/SS Core Complete Schedule Threat
• 0/D KSC date will likely slip another 2 months
• Alenia financial concerns
• KSC test problems
• Node ships on time but work or paper is not complete 0-1
month impact
• Traveled work "as-built" reconciliation
• Paper closure
/SS Management Options
' Hold ASI to delivery schedule
• Management discussions with ASI and ESA
• Reduce testing scope
' Add Resources/ShiftsA/Veekends@KSC
(Lose contingency on Node)
Figure 6.2-2. At the same December 2002 meefing, the International Space Station Program Manager presented this slide, showing the
actions being taken to regain margin in the schedule. Note that the yellow triangles reflect zero days remaining margin.
Report Voll
IGUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
sonable goal and assumed that if circumstances wairanted a
slip of that date, it would be granted.
Shuttle and Station managers worked diligently to meet the
schedule. Events gradually ate away at the schedule margin.
Unlike the "old days" before the Station, the Station/Shuttle
partnership created problems that had a ripple effect on
both programs" manifests. As one employee described it,
"the serial nature" of having to fly Space Station assembly
missions in a specific order made staying on schedule more
challenging. Before the Space Station, if a Shuttle flight had
to slip, it would; other missions that had originally followed
it would be launched in the meantime. Missions could be
flown in any sequence. Now the manifests were a delicate
balancing act. Missions had to be flown in a certain order
and were constrained by the availability of the launch site,
the Russian Soyuz and Progress schedules, and a myriad of
other processes. As a result, employees stated they were now
experiencing a new kind of pressure. Any necessary change
they made on one mission was now impacting future launch
dates. They had a sense of being "under the gun."
Shuttle and Station prograin personnel ended up with mani-
fests that one employee described as "changing, changing,
changing" all the time. One of the biggest issues they faced
entering 2002 was "up mass," the amount of cargo the Shut-
tle can carry to the Station. Up mass was not a new problem,
but when the Shuttle flight rate was reduced to four per year,
up mass became critical. Working groups were actively
evaluating options in the summer of 2002 and bartering to
get each flight to function as expected.
Sometimes the up mass being traded was actual Space Sta-
tion crew members. A crew rotation planned for STS-118
was moved to a later flight because STS- 1 1 8 was needed for
other cargo. This resulted in an increase of crew duration on
the Space Station, which was creeping past the 1 80-day limit
agreed to by the astronaut office, flight surgeons, and Space
Station international partners. A space station worker de-
scribed how this one change created many other problems,
and added: ". . . we had a train wreck coiiiiiif^ ..." Future on-
orbit crew time was being projected at 205 days or longer to
maintain the assembly sequence and meet the schedule.
By .July 2002, the Shuttle and Space Station Programs were
facing a schedule with very little margin. Two setbacks oc-
curred when technical problems were found during routine
maintenance on Discovery. STS- 1 07 was four weeks away
from launch at the time, but the problems grounded the
entire Shuttle fleet. The longer the fleet was grounded, the
more schedule margin was lost, which further compounded
the complexity of the intertwined Shuttle and Station sched-
ules. As one worker described the situation:
...a one-week hit on a particular launch can .start a
.steam roll effect includinii all [the] constraints and
by the time you f>et out of here, that one-week slip has
turned into a couple of months.
In August 2002, the Shuttle Program realized it would be
unable to meet the Space Station schedule with the avail-
able Shuttles. Columbia had never been outfitted to make
a Space Station flight, so the other three Orbiters flew the
Station missions. But Discovery was in its Orbiter Mainte-
nance Down Period, and would not be available for another
17 months. All Space Station flights until then would have
to be made by Atlantis and Endeavour. As managers looked
ahead to 2003, they saw that after STS- 107, these two Orbit-
ers would have to alternate flying five consecutive missions,
STS-II4 through STS-118. To alleviate this pressure, and
regain .schedule margin, Shuttle Program managers elected
to modify Columbia to enable it to fly Space Station mis-
sions. Those modifications were to take place immediately
after STS- 107 so that Columbia would be ready to fly its first
Space Station mission eight months later. This decision put
Columbia directly in the path of Core Complete.
As the autumn of 2002 began, both the Space Shuttle and
Space Station Programs began to use what some employ-
ees termed "tricks" to regain schedule margin. Employees
expressed concent that their ability to gain schedule margin
using existing measures was waning.
In September 2002, it was clear to Space Shuttle and Space
Station Program managers that they were not going to meet
the schedule as it was laid out. The two Programs proposed a
new set of launch dates, documented in an e-mail (right) that
included moving STS- 1 20, the Node 2 flight, to mid-March
2004. (Note that the first paragraph ends with "... the JOA
[U.S. Core Cortiplete. Node 2])aunch remains 2/19/04.")
The.se launch date changes made it possible to meet the
early part of the schedule, but compressed the late 2003/
early 2004 schedule even further. This did not make sense
to many in the program. One described the system as at "an
uncomfortable point. " noted having to go to great lengths to
reduce vehicle-processing time at Kennedy, and added:
... / don't know what Coni>ress communicated to
O'Keefe. I don't really understand the criticality of
February 1 9th. that if we didn 't make that date, did that
mean the end of NASA'.' I don't know ... / would like to
think that the technical i.ssues and safely resolving the
technical i.ssues can take priority over any budget issue
or .scheduling issue.
When the Shuttle fleet was cleared to return to flight, atten-
tion turned to .STS- 1 12, STS- 1 13. and STS- 107, set for Oc-
tober, November, and January. Workers were uncomfortable
with the rapid sequence of flights.
The thing that was beginning to concern me ... is I
wasn 't convinced that people were being given enough
time to work the problems correctly.
The problems that had grounded the fleet had been handled
well, but the program nevertheless lost the rest of its margin.
As the pressure to keep to the Node 2 schedule continued,
some were concerned that this might influence the future
handling of problems. One worker expressed the concern:
... and I have to think that subconsciously that even
though you don't want it to affect decisi(m-making. it
probably does.
Report Volui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Original Message
From: THOMAS, DAWN A. (JSC-OC) (NASA)
Sent: Friday, September 20, 2002 7:10 PM
To: Tlowers, David'; "Horvath, Greg'; 'O'Fallon, Lee'; Van Scyoc, Neal'; 'Gouti, Tom'; 'Hagen, Ray'; "Kennedy, John';
Thornburg, Richard'; "Garl, Judy'; 'Dodds, Joel'; 'Janes, Lou Ann'; 'Breen, Brian'; 'Deheck-Stokes, Kristina';
'Narita, Kaneaki (NASDA)'; "Patrick, Penny O'; 'Michael Rasmussen (E-mail)'; DL FPWG; 'Hughes, Michael G';
'Bennett, Patty'; "MasazumI, Miyake'; 'Mayumi Matsuura'; NORIEGA, CARLOS I. (JSC-CB) (NASA); BARCLOvY,
DINA E. (JSC-DX) (NASA); MEARS, AARON (JSC-XA) (HS); BROWN, WILLIAM C. (JSC-DT) (NASA); DUMESNIL,
DEANNA T (JSC-OC) (USA); MOORE, NATHAN (JSC-REMOTE); MONTALBANO, JOEL R. (JSC-DA8) (NASA);
MOORE, PATRICIA (PATTI) (JSC-DA8) (NASA); SANCHEZ, HUMBERTO (JSC-DA8) (NASA)
Subject: FPWG status - 9/20/02 OA/MA mgrs mtg results
The ISS and SSP Program Managers have agreed to proceed with the crew rotation change and the
following date changes: 12A launch to 5/23/03, 12A.1 launch to 7/24/03, 13A launch to 10/2/03, and
13A.1 launch to NET 11/13/03. Please note that 10A launch remains 2/19/04.
The ISS SSCN that requests evaluation of these changes will be released Monday morning after the
NASA/Russian bilateral Requirements and Increment Planning videocon. It will contain the following:
• Increments 8 and 9 redefinition - this includes baseline of ULF2 into the tactical timeframe as the
new return flight for Expedition 9
• Crew size changes for 7S, 13A.1, 15A, and 10A
• Shuttle date changes as listed above
• Russian date changes for CY2003 that were removed from SSCN 6872 (IIP launch/1 OP undock
and subsequent)
• CY2004 Russian data if available Monday morning
• Duration changes for 1 2A and 1 5A
• Docking altitude update for 10A, along with "NET" TBR closure.
The evaluation due date is 10/2/02. Board/meeting dates are as follows: MIOCB status - 10/3/02;
comment dispositioning - 10/3/02 FPWG (meeting date/time under review); OA/MA Program Man-
agers status - 10/4/02; SSPCB and JPRCB - 10/8/02; MMIOCB status (under review) and SSCB
-10/10/02.
The 1 3A. 1 date is indicated as "NET" (No Earlier Than) since SSP ability to meet that launch date is
under review due to the processing flow requirements.
There is no longer a backup option to move ULF2 to OV-105: due to vehicle processing requirements,
there is no launch opportunity on OV-105 past May 2004 until after OMM.
The Program Managers have asked for preparation of a backup plan in case of a schedule slip of
ULF2. In order to accomplish this, the projected ISS upmass capability shortfall will be calculated as
if ULF2 launch were 10/7/04, and a recommendation made for addressing the resulting shortfall and
increment durations. Some methods to be assessed: manifest restructuring, fallback moves of rota-
tion flight launch dates, LON (Launch on Need) flight on 4/29/04.
llSS=lntemaHonal Space Station, SSP=Space Shuttle Program, NET=no earlier than, SSCN=Space Station Change No-
tice, CY=Co/endar Year, T6R=To Be Revised for Reviewed), MIOCB=Mission Integration and Operations Control Board,
FPWC=Flight Planning Working Group, OA/MA=Space Station Office Symbol/ShuHle Program Office Symbol, SSPC6=Space
Station Program Control Board, JPRCB=Space Shuttle/Space Station Joint Program Requirements Control Board,
MMIOCB= Multi-Lateral Mission Integration and Operations Control Board, SSCB=Space Station Control Board, ULF2=U.S.
Logistics Flight 2, OMM=Orbiter Major Modification, OV-105=Endeavour]
This was the environment tor October and November of The Operations Tempo Follov/Ing STS-107
2002. During this time, a bipod foam event occurred on STS-
112. For the first time in the history of the Shuttle Program. After STS-107, the tempo was only going to increase. The
the Program Requirements Control Board chose to classify vehicle processing schedules, training schedules, and mission
that bipod foam loss as an "action" rather than a more seri- control flight staffing assignments were all overburdened.
ous In-Flight Anomaly. At the STS-113 Flight Readiness
Review, managers accepted with little question the rationale The vehicle-processing schedule for flights from February
that it was safe to fly with the known foam pr(^blem. 2003, through February 2004, was optimistic. The schedule
Report Volume I A u t3 u s t 2D03 1 35
COLUMBIA
ACCIDENT iNVESTIGATiaN BOARD
could not be met with only two shifts of workers per day. In
late 2002, NASA Headquarters approved plans to hire a third
shift. There were four Shuttle launches to the Space Station
scheduled in the five months from October 2003. through the
launch of Node 2 in February 2004. To put this in perspec-
tive, the launch rate in 1985, for which NASA was criticized
by the Rogers Commission, was nine flights in 12 months
- and that was accomplished with four Orbiters and a mani-
fest that was not complicated by Space Station assembly.
Endeavour was the Orbiter on the critical path. Figure 6.2-4
shows the schedule margin for STS-ll.'i, STS-117, and
STS-120 (Node 2). To preserve the margin going into 2003,
the vehicle processing team would be required to work the
late 2002-early 2003^ winter holidays. The third shift of
workers at Kennedy would be available in March 2003,
and would buy eight more days of margin for STS-1 17 and
STS-12(). The workforce would likely have to work on the
2003 winter holidays to meet the Node 2 date.
Figure 6.2-5 shows the margin for each vehicle {Discovery,
OV-103, was in extended maintenance). The large boxes
indicate the "margin to critical path" (to Node 2 launch
date). The three smaller boxes underneath indicate (from
left to right) vehicle processing margin, holiday margin, and
Dryden margin. The vehicle processing margin indicates
how many days there are in addition to the days required for
that mission's vehicle processing. Endeavour (OV-105) had
zero days of margin for the processing flows for STS-1 15,
STS-1 17, and STS-120. The holiday margin is the number
of days that could be gained by working holidays. The
Dryden margin is the six days that are always reserved to
accommodate an Orbiter landing at Edwards Air Force Base
in California and having to be ferried to Kennedy, if the
Orbiter landed at Kennedy, those six days would automati-
cally be regained. Note that the Dryden margin had already
been sun-endered in the STS-l 14 and STS-1 15 schedules. If
bad weather at Kennedy forced those two flights to land at
Edwards, the schedule would be directly affected.
The clear message in these charts is that any technical prob-
lem that resulted in a slip to one launch would now directly
affect the Node 2 launch.
The lack of housing for the Orbiters was becoming a fac-
tor as well. Prior to launch, an Orbiter can be placed in an
Orbiter Processing Facility, the Vehicle Assembly Building,
or on one of the two Shuttle launch pads. Maintenance and
SSP Schedule Reserve
Time Now
MarOS-*-
+ 18;
STS-115FI0W
"3"' shift". Adds + 8 day reserve per flow to mitigate "threats" ►
A +25 A +27
„ „ Work 2003 Xmas holidays
+ 17m STS-117 Flow +19i^, STS-120 Flow /,„ hold schedule, if req'd
A
w/ to I
:^A
Work 2003 Xmas
holidays to preserve
18 day margin
Potential 15 day schedule impact for each flow = 45 day total threat (+/- 15 days)
5/23/03
STS-115
12A
10/02/03
STS-117
13A
2/19/04
STS-120
Node 2
Core Complete
10
SSP Core Complete Schedule Threats
STS-120/Node 2 launch subject to 45 days of schedule risk
• Space Shuttle technical problems
• Station on-orbit technical problems/mission requirements impact
• Range launch cutouts
• Weather delays
• Soyuz and Progress conflicts
Management Options
• USA commit holiday/weekend reserves and
apply additional resources to hold schedule
1. Flex 3" shift avail— Mar 03
2. LCC 3" shift avail— Apr 03
• HQ mitigate Range Cutout
• HQ and ISS mitigate Soyuz conflict threat
Figure 6.2-4. By late 2002, the vehicle processing team at the Kennedy Space Center would be required to work through the winter holi-
days, and a third shift was being hired in order to meet the February 19, 2004, schedule for U.S. Core Complete.
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION 8DARD
refurbishment is perfonned in tiie three Orbiter Processing
Facilities at Kennedy. One was occupied by Discovery dur-
ing its scheduled extended maintenance. This left two to
serve the other three Orbiters over the next several months.
The 2003 schedule indicated plans to move Columbia (after
its return from STS- 107) from an Orbiter Processing Facility
to the Vehicle Assembly Building and back several times in
order to make room for Atlantis (OV-104) and Endeavour
(OV-105) and prepare them for missions. Moving an Orbiter
is tedious, time-consuming, carefully orchestrated work.
Each move introduces an opportunity for problems. Those
2003 moves were often slated to occur without a day of mar-
gin between them -another indication of the additional risks
that managers were willing to incur to meet the schedule.
The effect of the compressed schedule was also evident in
the Mission Operations Directorate. The plans for flight con-
troller staffing of Mission Control showed that of the seven
flight controllers who lacked current certifications during
STS- 107 (.see Chapter 4), five were scheduled to work the
next mission, and three were scheduled to work the next
three missions (STS-114, -115. and -116). These control-
lers would have been constantly either supporting missions
or supporting mission training, and were unlikely to have
the time to complete the recertification requirements. With
the pressure of the schedule, the things perceived to be less
important, like recertification (which was not done before
STS- 1 07), would likely continue to be deferred. As a result
of the schedule pressure, managers either were willing to de-
lay recertification or were too busy to notice that deadlines
for recertification had passed.
Columbia: Caught in the Middle
STS-II2 flew in October 2002. At 33 seconds into the
flight, a piece of the bipod foam from the External Tank
struck one of the Solid Rocket Boosters. As described in
Section 6.1, the STS-112 foam strike was discussed at
the Program Requirements Control Board following the
flight. Although the initial recommendation was to treat
the foam loss as an In-Flight Anomaly, the Shuttle Program
instead assigned it as an action, with a due date after the
next launch. (This was the first instance of bipod foam loss
that was not designated an In-Flight Anomaly.) The action
was noted at the STS- 1 13 Flight Readiness Review. Those
Flight Readiness Review charts (see Section 6.1) provided
a flawed flight rationale by concluding that the foam loss
was "not a safety-of-flight" issue.
B^Sj
SSP Schedule Reserve
Processing Hoiic
Dryden DayS ot
Constraints-
1-L
OV-102
OV-104
OV-105
m
M JS-
STS-114
ULF1
Critical path
STS-116
12A.1
0
Hi]
STS-115
12A
0
STS-117
13A
0
|19| 10| 6 I
STS-120
Node 2
SSP Core Complete Schedule Threats
STS-120/Nocle 2 launch subject to 45 days of schedule risk
• Space Shuttle technical problems
• Station on-orbit technical problems/mission requirements impact
• Range launch cutouts
• Weather delays
• Soyuz and Progress conflicts
Management Options
' USA commit holiday/weekend reserves and
apply additional resources (i.e., 3'" shift) to
hold schedule (Note: S'shift not yet included)
• HQ mitigate Range Cutout
• HQ and ISS mitigate Soyuz conflict threat
Figure 6.2-5. This slide sfiows ffie margin for each Orbifer. The large boxes show ihe number of days margin to the Node 2 launch dofe,
while the three smaller boxes indicate vehicle processing margin, holiday margin, and the margin if a Dryden landing was not required.
Report Voli
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Interestingly, during Columbia's mission, the Chair of the
Mission Management Team, Linda Ham, would characterize
that reasoning as "lousy" - though neither she nor Shuttle
Program Manager Ron Dittemore, who were both present at
the meeting, questioned it at the time. The pressing need to
launch STS-II3 to retrieve the International Space Station
Expedition 5 crew before they surpassed the 180-day limit
and to continue the countdown to Node 2 were surely in the
back of managers' minds during these reviews.
By December 2002. every bit of padding in the schedule
had disappeared. Another chart from the Shuttle and Station
Program Managers' briefing to the NASA Administrator
summarizes the schedule dilemma (see Figure 6.2-6).
Even with work scheduled on holidays, a third shift of work-
ers being hired and trained, future crew rotations drifting
beyond 1 80 days, and some tests previously deemed "re-
quirements" being skipped or deferred, Program managers
estimated that Ntide 2 launch would be one to two months
late. They were slowly accepting additional risk in trying to
meet a schedule that probably could not be met.
Interview;* with workers provided insight into how this situ-
ation occurred. They noted that people who work at NASA
have the legendary can-do attitude, which contributes to the
agency's successes. But it can also cause problems. When
workers are asked to find days of margin, they work furious-
ly to do so and are praised for each extra day they find. But
those same people (and this same culture) have difficulty
admitting that something "can't" or "shouldn't" be done,
that the margin has been cut too much, or that resources are
being stretched too thin. No one at NASA wants to be the
one to stand up and say, "We can't make that date."
STS-I()7 was launched on .lanuary 16, 2003. Bipod foam
separated from the External Tank and struck Coliinihia's left
wing 81.9 seconds after liftoff. As the mission proceeded
over the next 16 days, critical decisions about that event
would be made.
The STS-107 Mission Management Team Chair, Linda
Ham, had been present at the Program Requirements Control
Board discussing the STS-112 foam loss and the STS-II3
Flight Readiness Review. So had many of the other Shuttle
Program managers who had roles in STS-107. Ham was also
the Launch Integration Manager for the next mission. STS-
1 14. In that capacity, she would chair many of the meetings
leading up to the launch of that flight, and many of those
individuals would have to confront Cohiinhia's foam strike
and its possible impact on the launch of STS- 1 1 4. Would the
Cnliiiiihia foam strike be classified as an In-Flight Anomaly?
Would the fact that foam had detached from the bipod ramp
on two out of the last three flights have made this problem a
constraint to flight that would need to be solved before the
next launch? Could the Program develop a solid rationale
to fly STS- 1 14. or would additional analysis be required to
clear the flight for launch?
Summary
Critical Path to U.S. Core Complete driven by
Shuttle Launch
>" Program Station assessment: up to 14 days late
>- Program Shuttle assessment: up to 45 days late
Program proactively managing schedule threats
Most probable launch date is March 19-April 19
^ Program Target Remains 2/19/04
Figure 6.2-6. By December 2002, every bit of padding in the schedule had disappeared. Another chart from the Shuttle and Station Pro-
gram Managers' briefing to the NASA Administrator summarizes the schedule dilemma.
Report VOLUwe I August Z003
COLUMBIA
ACCIDENT INVESTIGATION SDARD
Original Message
From: HAM, LINDA J. (JSC-MA2) (NASA)
Sent: Wednesday, January 22, 2003 10:16 AM
To: DITTEMORE, RONALD D. (JSC-MA) (NASA)
Subject: RE: ET Briefing - STS-112 Foam Loss
Yes, I remember.... It was not good. I told Jerry to address it at the ORR next Tuesday (even though
he won't have any more data and it really doesn't impact Orbiter roll to the VAB). I just want him to be
thinking hard about this now, not wait until IFA review to get a formal action.
fORR=Orbi>er Ro//ouf Review, VA6=Vehic/e Assembly Budding, /FA=/n-F//g/if Anomaly]
In fact, most of Linda Ham's inquiries about the foam
strike were not to determine what action to lai<e during
Columbia's mission, but to understand the implications for
STS-1 14. During a Mission Management Team meeting on
January 2 1 , she asked about the rationale put forward at the
STS-1 13 Flight Readiness Review, which she had attended.
Later that morning she reviewed the charts presented at
that Flight Readiness Review. Her assessment, which she
e-mailed to Shuttle Program Manager Ron Dittemore on
January 21, was "Rationale was lousy then and still is ..."
(See Section 6.3 for the e-mail.)
One of Ham's STS- 1 14 duties was to chair a review to deter-
mine if the mission's Orbiter. Atlantis, should be rolled from
the Orbiter Processing Facility to the Vehicle Assembly
Building, per its pre-launch schedule. In the above e-mail to
Ron Dittemore, Ham indicates a desire to have the same in-
dividual responsible for the "lousy" STS-1 13 flight rationale
start working the foam shedding issue - and presumably
present a new flight rationale - very soon.
As STS- 107 prepared for re-entry. Shuttle Program manag-
ers prepared for STS-1 14 flight rationale by arranging to
have post-flight photographs taken of Columbia's left wing
rushed to Johnson Space Center for analysis.
As will become clear in the ne.xt section, most of the Shuttle
Program's concern about Columbia's foam strike were not
about the threat it might pose to the vehicle in orbit, but
about the threat it might pose to the schedule.
Conclusion
The agency's commitment to hold firm to a February 19,
2004, launch date for Node 2 influenced many of decisions
in the months leading up to the launch of STS- 107. and may
well have subtly influenced the way managers handled the
STS-1 12 foam strike and Columbia's as well.
When a program agrees to spend less money or accelerate
a schedule beyond what the engineers and program man-
agers think is reasonable, a small amount of overall risk is
added. These little pieces of risk add up until managers are
no longer aware of the total program risk, and are. in fact,
gambling. Little by little, NASA was accepting more and
more risk in order to stay on schedule.
Findings
F6.2-1
F6.2-2
F6.2-3
F6.2-4
F6.2-5
F6.2-6
F6.2-7
NASA Headquarters" focus was on the Node 2
launch date, February 19. 2004.
The intertwined nature of the Space Shuttle and
Space Station programs significantly increased
the complexity of the schedule and made meeting
the schedule far more challenging.
The capabilities of the system were being
stretched to the limit to support the schedule.
Projections into 2003 showed stress on vehicle
processing at the Kennedy Space Center, on flight
controller training at Johnson Space Center, and
on Space Station crew rotation schedules. Effects
of this stress included neglecting flight control-
ler recertification requirements, extending crew
rotation schedules, and adding incremental risk
by scheduling additional Orbiter movements at
Kennedy.
The four flights scheduled in the five months
from October 2003. to February 2004, would
have required a processing effort comparable to
the effort immediately before the Clialleni^er ac-
cident.
There was no schedule margin to accommodate
unforeseen problems. When flights come in rapid
succession, there is no assurance that anomalies
on one flight will be identified and appropriately
addressed before the next flight.
The environment of the countdown to Node 2 and
the importance of maintaining the schedule may
have begun to influence managers' decisions,
including those made about the STS-112 foam
strike.
During STS- 107, Shuttle Program managers
were concerned with the foam strike's possible
effect on the launch schedule.
Recommendation
R6.2-1
Adopt and maintain a Shuttle flight .schedule that
is consistent with available resources. Although
schedule deadlines are an important management
tool, those deadlines must be regularly evaluated
to ensure that any additional risk incurred to meet
the schedule is recognized, understood, and ac-
ceptable.
Report vouume 1
i T 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
6.3 Decision-Making During the Flight of STS-107
initial Foam Strike Identification
As soon as Coliniihia reached orbit on the morning of January 16, 2003, NASA's Intercenter
Photo Working Group began reviewing iifloff imagery by video and film cameras on the launch
pad and at other sites at and nearby the Kennedy Space Center. The debris strike was not seen
during the first review of video imagery by tracking cameras, but it was noticed at 9:30 a.m.
EST the next day. Flight Day Two, by intercenter Photo Working Group engineers at Marshall
Space Flight Center. Within an hour, Intercenter Photo Working Group personnel at Kennedy
also identified the strike on higher-resolution film images that had just been developed.
The images revealed that a large piece of debris from the left bipod area of the External Tank
had struck the Orbiter's left wing. Because the resulting shower of post-impact fragments could
not be seen passing over the top of the wing, analysts concluded that the debris had apparently
impacted the left wing below the leading edge. Intercenter Photo Working Group members
were concerned about the size of the object and the apparent momentum of the strike. In search-
ing for better views, Intercenter Photo Working Group members realized that none of the other
cameras provided a higher-quality view of the impact and the potential damage to the Orbiter.
Of the dozen ground-based camera sites used to obtain images of the ascent for engineering
analyses, each of which has film and video cameras, five are designed to track the Shuttle from
liftoff until it is out of view. Due to expected angle of view and atmospheric limitations, two
sites did not capture the debris event. Of the remaining three sites positioned to "see" at least a
portion of" the event, none provided a clear view of the actual debris impact to the wing. The first
site lost track of Cohiinhia on ascent, the second site was out of focus - because of an improp-
erly maintained lens - and the third site captured only a view of the upper side of Coltinihia's
left wing. The Board notes that camera problems also hindered the CInilleiiiier investigation.
Over the years, it appears that due to budget and camera-team staff cuts, NASA's ability to track
ascending Shuttles has atrophied - a development that reflects NASA's disregard of the devel-
opmental nature of the Shuttle's technology. (See recommendation R3.4-I.)
Because they had no sufficiently resolved pictures with which to determine potential damage,
and having never seen such a large piece of debris strike the Orbiter so late in ascent, Intercenter
Photo Working Group members decided to ask for ground-based imagery of Coliimhki.
Imagery Request 1
To accomplish this, the Intercenter Photo Working Group's Chair, Bob Page, contacted Wayne
Hale, the Shuttle Program Manager for Launch Integration at Kennedy Space Center, to request
imagery of Coliiwhia's left wing on-orbit. Hale, who agreed to explore the possibility, holds a
Top Secret clearance and was familiar with the process for requesting military imaging from his
experience as a Mission Control Flight Director.
This would be the first of three discrete requests for imagery by a NASA engineer or manager.
In addition to these three requests, there were, by the Board's count, at least eight "missed op-
portunities" where actions may have resulted in the discovery of debris damage.
Shortly after confirming the debris hit, Intercenter Photo Working Group members distributed
a "L+l" (Launch plus one day) report and digitized clips of the strike via e-mail throughout the
NASA and contractor communities. This report provided an initial view of the foam strike and
served as the basis for subsequent decisions and actions.
Mission Management's Response to the Foam Strike
As soon as the Intercenter Working Group report was distributed, engineers and technical
managers from NASA, United Space Alliance, and Boeing began responding. Engineers and
managers from Kennedy Space Center called engineers and Program managers at .lohnson
Space Center. United Space Alliance and Boeing employees exchanged e-mails with details of
the initial film analysis and the work in progress to determine the result of the impact. Details
of the strike, actions taken in response to the impact, and records of telephone conversations
were documented in the Mission Control operational log. The following section recounts in
1 40 — ^— — ^-^— ^^-^^— — ^^^ Report volume I August 2003 —^—^——
COLUMBIA
ACCIDENT INVESTIGATION BDARO
chronological order many of tliese exchanges and provides insight into why, in spite of the
debris strike's severity. NASA managers ultimately declined to request images of Columbia's
left wing on-orbit.
Flight Day Two, Friday, January 17, 2003
In the Mission Evaluation Room, a support function of the Shuttle Program office that supplies
engineering expertise for missions in progress, a set of consoles are staffed by engineers and
technical managers from NASA and contractor organizations. For record keeping, each Mission
Evaluation Room member types mission-related comments into a running log. A log entry by a
Mission Evaluation Room manager at 10:58 a.m. Central Standard Time noted that the vehicle
may have sustained damage from a debris strike.
"John Disler [a photo lab eiif^ineer at Johnson Space Center] called to report a debris hit
on the vehicle. The debris appears to originate from the ET Forward Bipod area... travels
down the left side and hits the left wing leading edge near the fuselage... The launch video
review team at KSC think that the vehicle nuiy have been damaged by the impact. Bill
Reeves and Mike Stoner I USA SAM) were notified. " [EJ=Exfernal Tank, KSC=Kennedy Space
Center, USA SAM=United Space Alliance Sub-system Area tAanager]
At 3: 1 5 p.m.. Bob Page, Chair of the Intercenter Photo Working Group, contacted Wayne Hale,
the Shuttle Program Manager for Launch Integration at Kennedy Space Center, and Lambert
Austin, the head of the Space Shuttle Systems Integration at Johnson Space Center, to inform
them that Boeing was periorming an analysis to determine trajectories, velocities, angles, and
energies for the debris impact. Page also stated that photo-analysis would continue over the
Martin Luther King Jr. holiday weekend as additional film from tracking cameras was devel-
oped. Shortly thereafter, Wayne Hale telephoned Linda Ham, Chair of the Mission Manage-
ment Team, and Ron Dittemore, Space Shuttle Program Manager, to pass along information
about the debris strike and let them know that a formal report would be issued by the end of
the day. John Disler, a member of the Intercenter Photo Working Group, notified the Mission
Evaluation Room manager that a newly formed group of analysts, to be known as the Debris
Assessment Team, needed the entire weekend to conduct a more thorough analysis. Meanwhile,
early opinions about Reinforced Carbon-Carbon (RCC) resiliency were circulated via e-mail
between United Space Alliance technical managers and NASA engineers, which may have
contributed to a mindset that foam hitting the RCC was not a concern.
— Original Message
From: Stoner- 1, Michael D
Sent: Friday, January 17, 2003 4:03 PM
To: Woodworth, Warren H; Reeves, William D
Cc: Wilder, James; White, Doug; Bitner, Barbara K; Blank, Donald E; Cooper, Curt W; Gordon, Michael P.
Subject: RE: STS 107 Debris
Just spoke with Calvin and Mike Gordon (RCC SSM) about the impact.
Basically the RCC is extremely resilient to impact type damage. The piece of debris (most likely
foam/ice) looked like it most likely impacted the WLE RCC and broke apart. It didn't look like a big
enough piece to pose any serious threat to the system and Mike Gordon the RCC SSM concurs. At T
+81 seconds the piece wouldn't have had enough energy to create a large damage to the RCC WLE
system. Plus they have analysis that says they have a single mission safe re-entry in case of impact
that penetrates the system.
As far as the tile go in the wing leading edge area they are thicker than required (taper in the outer
mold line) and can handle a large area of shallow damage which is what this event most likely would
have caused. They have impact data that says the structure would get slightly hotter but still be OK.
Mike Stoner
USATPSSAM
fRCC=Reinforced Corbon-Corbon, SSM=Sub-system Manager, WLE=Wing Leading Edge, TPS=Thermal Protection System,
SAA/t= Sub-system Area Manager]
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Engineering Coordination at NASA
AND United Space Alliance
After United Space Alliance became contractually responsible for most aspects of Shuttle operations.
NASA developed procedures to ensure that its own engineering expertise was coordinated with that
of contractors for any "out-of-f'amily" issue. In the case of the foam strike on STS-1()7, which was
classified as out-of-family. clearly defined written guidance led United Space Alliance technical man-
agers to liaise with their NASA counterparts. Once NASA managers were officially notified of the
foam strike classification, and NASA engineers joined their contractor peers in an early analysis, the
resultant group should, according to standing procedures, become a Mission Evaluation Room I'iger
Team. Tiger Teams have clearly defined roles and responsibilities.'*- Instead, the group of analysts
came to be called a Debris Assessment Team. While they were the right group of engineers work-
ing the problem at the right time, by not being classified as a Tiger learn, they did not fall under the
Shuttle Program procedures described in Tiger Team checklists, and as a result were not "owned" or
led by Shutde Program managers. This left the Debris Assessment Team in a kind of organizational
limbo, with no guidance except the date by which Program managers expected to hear their results:
.lanuary 24th.
Already, by Friday afternoon. Shuttle Program managers and working engineers had different
levels of concern about what the foam strike might have meant. After reviewing available film.
Intercenter Photo Working Group engineers believed the Orbiter may have been damaged by
the strik(^. They wanted on-orbit images of Columbia's left wing to confirm their suspicions
and initiated action to obtain them. Boeing and United Space Alliance engineers decided to
work through the holiday weekend to analyze the strike. At the same time, high-level managers
Ralph Roe. head of the Shuttle Program Office of Vehicle Engineering, and Bill Reeves, from
United Space Alliance, voiced a lower level of concern. It was at this point, before any analysis
had started, that Shuttle Program managers officially shared their belief that the strike posed no
safety issues, and that there was no need for a review to be conducted over the weekend. The
following is a 4;28 p.m. Mission Evaluation Room manager log entry:
"Bill Reeves called, after a meetiii!^ with Ralph Roe. it is confirmed that USA/Boeing will
no! work the debris issue over the weekend, but will wait till Monday when the films are
released. The LCC constraints on ice, the ener^iyLspeed of impact at +8 J .seconds, and the
loui^hness of the RCC are t^vo main fiictors ft)r the low concern. Al.so, analysis supports
sin,i;le mission safe re-entry for an impact that penetrates the system. . . " fUSA=Uni>ec/ Space
Alliance, LCC=Launch Commit Criteria]
The following is a 4:37 p.m. Mission Evaluation Room manager log entry.
"Bob Paiie told MER that KSC/TPS engineers were sent by the USA SAM/Woody Wood-
worth to review the video and films. Indicated that Pa^e had said that Woody had said this
was an action fi-om the MER to work this issue and a possible early landing!, on Tue.ulay.
MER Manai^er told Bob that no official action was given by USA or Boeinf^ and they had
no c(mcern about landinfi early. Woody indicated that the TPS engineers at KSC have been
'turned away' from reviewing the films. It was stated that the film reviews wouldn't be fin-
ished till Monday. " [MER=Mission Evaluation Room, KSC=Kennedy Space Center, TPS=Thermal
Protection System, USA SAM=United Space Alliance SuJb-sysfem Areo Manager]
The Mission Evaluation Room manager also wrote:
"7 also confirmed that there was no rush on this issue and that it was okay to wait till the
film reviews are finished on Monday to do a TPS review. "
in addition to individual log entries by Mission Evaluation Room members, managers prepared
"handover" notes for delivery from one working shift to the next. Handovers from Shift 1 to 2
on .January 17 included the following entry under a "problem" category.
'"Disler Report - Debris impact on port wing edge-appears to have origincued at the ET
fvd bipod -foam?- if so, it shouldn V be a problem - video clip will be available on the web
.soon - will look at high-speed film today. " [ET=External Tank, fwd={orward]
1 42 Report Volume I A u C3 u s t 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Shortly after these entries were made, the deputy manager of Johnson Space Center Shuttle En-
gineering notified Rodney Rocha, NASA's designated chief engineer for the Thermal Protection
System, of the strike and the approximate debris size. It was Rocha's responsibility to coordinate
NASA engineering resources and work with contract engineers at United Space Alliance, who
together would form a Debris Assessment Team that would be Co-Chaired by United Space Al-
liance engineering manager Pam Madera. The United Space Alliance deputy manager of Shuttle
Engineering signaled that the debris strike was initially classified as "out-of-family" and there-
fore of greater concern than previous debris strikes. At about the same time, the Intercenter Photo
Working Group's L+l report, containing both video clips and still images of the debris strike,
was e-mailed to engineers and technical managers both inside and outside of NASA.
Flight Days Three and Four, Saturday and Sunday, January 18 and 19, 2003
Though senior United Space Alliance Manager Bill Reeves had told Mission Evaluation Room
personnel that the debris problem would not be worked over the holiday weekend, engineers
from Boeing did in fact work through the weekend. Boeing analysts conducted a preliminary
damage assessment on Saturday. Using video and photo images, they generated two estimates
of possible debris size - 20 inches by 20 inches by 2 inches, and 20 inches by 16 inches by 6
inches - and determined that the debris was traveling at a approximately 750 feet per second,
or 51 1 miles per hour, when it struck the Orbiter at an estimated impact angle of less than 20
degrees. These estimates later proved remarkably accurate.
To calculate the damage that might result from such a strike, the analysts turned to a Boeing
mathematical modeling tool called Crater that uses a specially developed algorithm to predict
the depth of a Thermal Protection System tile to which debris will penetrate. This algorithm, suit-
able for estimating small (on the order of three cubic inches) debris impacts, had been calibrated
by the results of foam, ice, and metal debris impact testing. A similar Crater-like algorithm was
also developed and validated with test results to assess the damage caused by ice projectiles
impacting the RCC leading edge panels. These tests showed that within certain limits, the Crater
algorithm predicted more severe damage than was observed. This led engineers to classify Crater
as a "conservative" tool - one that predicts more damage than will actually occur.
Until STS-107, Crater was normally used only to predict whether small debris, usually ice on
the External Tank, would pose a threat to the Orbiter during launch. The use of Crater to assess
the damage caused by foam during the launch of STS- 1 07 was the first use of the model while
a mission was on orbit. Al.so of note is that engineers used Crater during STS-107 to analyze a
piece of debris that was at maximum 640 times larger in volume than the pieces of debris used
to calibrate and validate the Crater model (the Board's best estimate is that it actually was 400
times larger). Therefore, the u.se of Crater in this new and very different situation compromised
NASA's ability to accurately predict debris damage in ways that Debris Assessment Team en-
gineers did not fully comprehend (see Figure 6.3-1 ).
Figure 6,3-?. The small cylinder at top illustrates the size of debris Crater was intended to analyze. The
larger cylinder was used for the STS-107 analysis; the block at right is the estimated size of the foam.
Report VoLur
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The Crater Model
0.0195(L/cI)0.45(d)(p^)°^'(V-V*)'/'
p = penetration depth
L = length of foam projectile
d = diameter of foam projectile
f)p = density of foam
V = component of foam velocity at right angle to foam
V* = velocity required to break through the tile coating
Sj - compressive strength of tile
()j = density of tile
0.0195 = empirical consfanf
In I %6, during the Apollo proeram, engineers developed an equation to assess impact damage, or "cra-
tering," by micrometeoroids. The equation was modified between 1 979 and 1 985 to enable the analy-
sis of impacts to "acreage" tiles that cover the lower surface of the Orbiter. " The modified equation,
now known a>, ( "rater, predicts possible damage from sources such as foam, ice, and launch site debris,
and is most often used in the day-of-launch analysis of ice debris falling off the External Tank.
When used within its validated limits, Crater provides conservative predictions (that is. Crater pre-
dictions are larger than actual damage). When used outside its validated limits. Crater's precision is
unknown.
Crater has been correlated to actual impact data using results from several tests. Preliminary ice drop
tests were performed in 1978,^' and additional tests using sprayed-on foam insulation projectiles
were conducted in 1979 and 1999.'*'^ However, the test projectiles were relatively small (maximum
volume of 3 cubic inches), and targeted only single tiles, not groups of tiles as actually installed on
the Orbiter. No tests were perfonned with larger debris objects because it was not believed such
debris could ever impact the Orbiter. This resulted in a very limited set of conditions under which
Crater's results were empirically validated.
During 1984. tests were conducted using ice projectiles against the Reinforced Carbon-Carbon used
on the Orbiler^■ w ing leading edges.'*'^ These tests used an 0.875-inch diameter, .^.75-inch long ice
projectile to validate an algorithm that was similar to Crater. Unlike Crater, which was designed to
predict damage during a flight, the RCC predictions were intended to determine the thickness of RCC
required to withstand ice impacts as an aid to design engineers. Like Crater, however, the limited set
of test data significantly restricts the potential application of the model.
Other damage assessniciii methods available today, such as hydrodynamic structural codes, like
Dyna, are able to anal y/c a larger set of projectile sizes and materials than Crater. Boeing and NASA
did not currently sanction these finite element codes because of the time required to correlate their
results in order to use the models effectively.
Although Crater was designed, and certified, for a very limited set of impact events, the results from
Crater simulations can be generated quickly. During S'fS-107, this led to Crater being used to model
an event that was well outside the parameters against which it had been empirically validated. As the
accompanying table shows, many of the STS-107 debris characteristics were orders of magnitude
outside the validated envelope. For instance, while Crater had been designed and validated for pro-
jectiles up to 3 cubic inches in volume, the initial STS-107 analysis estimated the piece of debris at
1 ,200 cubic inches - 400 times larger.
Crater paramefers used during development of experimental test data versus STS-107
analysis:
Tesf Paramefer
Tesf Value
STS-107 Analysis
Volume
Up to 3 cu.in
10" X 6" X 20" = 1200 cu.in. *
Length
Up to 1 inch
~ 20 inches *
Cylinder Dimensions
<= 3/8" dia x 3"
6" dia X 20"
Projectile Block Dimensions
<= 3"x 1 "x 1 "
6" X 10" X 20" *
Tile Material
LI-900 "acreage" tile
LI-2200 * and LI-900
Projectile Shape
Cylinder
Block
Outside experimental test limits
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Crater equation parameter lim
its:
Crater Equation Parameter
Applicable Range
STS-1 07 Analysis
L/d
1 - 20
3.3
L
n/a
~ 20 inches
Pj
1 - 3 pounds per cu.ft.
2.4 pounds per cu.ft.
d
0.4 - 2.0 inches
6 inches *
V
up to 810 fps
~ 700 fps
* Outside validated limits
Over the weekend, an engineer certified by Boeing to use Crater entered the two estimated
debris dimensions, the estimated debris velocity, and the estimated angle of impact. The en-
gineer had received formal training on Crater from senior Houston-based Boeing engineering
staff, but he had only used the program twice before, and had reservations about using it to
model the piece of foam debris that struck Columbia. The engineer did not consult with more
experienced engineers from Boeing's Huntington Beach. California, facility, who up until the
time of STS- 107 had performed or overseen Crater analysis. (Boeing completed the transfer of
responsibilities for Crater analysis from its Huntington Beach engineers to its Houston office
in January 2003. STS- 1 07 was the first mission that the Huntington Beach engineers were not
directly involved with.)
For the TheiTnal Protection System tile. Crater predicted damage deeper than the actual tile
thickness. This seemingly alarming result suggested that the debris that struck Columbia
would have exposed the Orbiter's underlying aluminum airframe to extreme temperatures,
resulting in a possible burn-through during re-entry. Debris Assessment Team engineers dis-
counted the possibility of burn through for two reasons. First, the results of calibration tests
with small projectiles showed that Crater predicted a deeper penetration than would actually
occur. Second, the Crater equation does not take into account the increased density of a tile's
lower "densified" layer, which is much stronger than tile's fragile outer layer. Therefore, engi-
neers judged that the actual damage from the large piece of foam lost on STS- 107 would not
be as severe as Crater predicted, and assumed that the debris did not penetrate the Orbiter's
skin. This uncertainty, however, meant that determining the precise location of the impact was
paramount for an accurate damage estimate. Some areas on the Orbiter's lower surface, such
as the seals around the landing gear doors, are more vulnerable than others. Only by knowing
precisely where the debris struck could the analysts more accurately determine if the Orbiter
had been damaged.
To determine potential RCC damage, analysts used a Crater-like algorithm that was calibrated
in 1984 by impact data from ice projectiles. At the time the algorithm was empirically tested,
ice was considered the only realistic threat to RCC integrity. (See Appendix E.4, RCC Impact
Analysis.) The Debris Assessment Team analysis indicated that impact angles greater than 15
degrees would result in RCC penetration. A separate "transport" analysis, which attempts to
determine the path the debris took, identified 15 strike regions and angles of impact. Twelve
transport scenarios predicted an impact in regions of Shuttle tile. Only one scenario predicted
an impact on the RCC leading edge, at a 2 1 -degree angle. Because the foam that struck Cohuu-
bia was less dense than ice. Debris Assessment Team analysts used a qualitative extrapolation
of the test data and engineering judgment to conclude that a foam impact angle up to 2 1 degrees
would not penetrate the RCC. Although some engineers were uncomfortable with this extrapo-
lation, no other analyses were performed to assess RCC damage. The Debris Assessment Team
focused on analyzing the impact at locations other than the RCC leading edge. This may have
been due, at least in part, to the transport analysis presentation and the long-standing belief
that foam was not a threat to RCC panels. The assumptions and uncertainty embedded in this
analysis were never fully presented to the Mission Evaluation Room or the Mission Manage-
ment Team.
Missed Opportunity 1
On Sunday, Rodney Rocha e-mailed a Johnson Space Center Engineering Directorate manager
to ask if a Mission Action Request was in progress for Columbia'^ crew to visually inspect the
left wing for damage. Rocha never received an answer.
Report von
August Z003
1 4 5
COLUMBIA
ACCIDENT INVESTIGATION BOARD
This photo from the aft flighf deck window of an Orbiter shows that RCC panels 1-11 are not visible
from inside the Orbiter. Since Columbia did not have a manipulator arm for STS-107, it would have been
necessary for an astronaut to take a spacewalk to visibly inspect the inboard leading edge of the wing.
Flight Day Five, Monday, January 20, 2003
On Monday morning, the Martin Luther King Jr holiday, the Debris Assessment Team held an
informal meeting before its first formal meeting, which was scheduled for Tuesday afternoon.
The team expanded to include NASA and Boeing transport analysts expert in the movement
of debris in airflows, tile and RCC experts from Boeing and NASA, aerothermal and thermal
engineers from NASA, United Space Alliance, and Boeing, and a safety representative from the
NASA contractor Science Applications International Corporation.
Engineers emerged from that informal meeting with a goal of obtaining images from ground-
based assets. Uncertainty as to precisely where the debris had struck Columbia generated con-
cerns about the possibility of a breach in the left main landing gear door seal. They conducted
further analysis using angle and thickness variables and thermal data obtained by personnel at
Boeing's Huntington'^Bea^ch facility for STS-87 and STS-50. the two missions that had incurred
Thermal Protection System damage. (See Section 6.1.)
Debris Assessment Team Co-Chair Pam Madera distributed an e-mail summarizing the day's
events and outlined the agenda for Tuesday's first formal Debris Assessment Team meeting.
Included on the agenda was the desire to obtain on-orbit images of Columbia's left wing.
According to an 1 1 :39 a.m. entry in the Mission Evaluation Room Manager's log:
". . .the debri.s 'blob ' is estimated at 20 " +/-I0 " in .some direction, u.sini^ the Orbiter hatch
as a basis. It appears to be similar size as that .seen in STS-J12. There will be more com-
parison work done, and more info and details in tomorrow's report."
This entry illustrates, in NASA language, an initial attempt by managers to classify this bipod
ramp foam strike as close to being within the experience base and therefore, being almost an
"in-family" event, not necessarily a safety concern. While the size and source of STS-107 de-
bris was somewhat similar to what STS-1 1 2 had experienced, the impact sites (the wing versus
the Solid Rocket Booster) differed - a distinction not examined by mission managers.
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Flight Day Six, Tuesday, January 21, 2003
At 7:00 a.m.. the Debris Assessment Team briefed Don McCormaci<, the chief Mission Evalu-
ation Room manager, that the foam's source and size was similar to what struck STS-112, and
that an analysis of measured versus predicted tile damage from STS-87 was being scrutinized
by Boeing. An hour later. McCormack related this information to the Mission Management
Team at its first post-holiday meeting. Although Space Shuttle Program requirements state that
the Mission Management Team will convene daily during a mission, the STS-107 Mission
Management Team met only on January 1 7. 2 1 , 24, 27, and 3 1 . The transcript below is the first
record of an official discussion of the debris impact at a Mission Management Team meeting.
Before even referring to the debris strike, the Mission Management Team focused on end-of-
mission "downweight" (the Orbiter was 150 pounds over the limit), a leaking water separator,
a jammed Hasselblad camera, payload and experiment status, and a communications downlink
problem. McCormack then stated that engineers planned to determine what could be done if
ColiiiiihUi had sustained damage. STS-107 Mission Management Team Chair Linda Ham sug-
gested the team learn what rationale had been used to fly after External Tank foam losses on
STS-87 and STS-112,
Transcript Excerpts from the January 21, Mission Management Team Meeting
Ham.- "Alrii^lit. I kiion- yon i>iiys are lookiiii; at llie debris. "
McCormack; "Yeah, as e\x'r\hoci\ knows, we look a hit on the, somewhere on the left wing
leading edge and the photo TV guys have completed I think, pretty much their work although
I'm sure they are reviewing their stuff and they've given us an approximate size for the debris
and approximate area for where it came from and approximately where it hit. so we are talking
about doing .some sort of parametric type of analysis and also we 're talking about what you can
do in the event we have some damage there. "
Ham; "That comment. I was thinking that the flight rationale at the FRR from tank and orbiter
from STS-1 12 was.... I'm iu)t sure that the area is exactly the same where the foam came from
hut the carrier properties and density of the foam wouldn 't do any damage. So we ought to pull
that along with the H7 data where we had some damage, pull this data p'om J 12 or whatever
flight it was and make sure that. . .you know I hope that we had good flight rationale then. "
McCormack; "Yeah, and we'll look at that, you mentioned H7. you know we saw some fairly
significant damage in the area between RCC panels H and 9 and the main landing gear door on
the bottom on STS-H7 we did some analysis prior to STS-H9 so uh. . . "
Ham; "And I'm really I don 't think there is much we can do so it's not really a factor during the
flight because there is not much we can do about it. But what I'm really interested in is making
sure our flight rationale to go was good, and maybe this is foam from a different area and I'm
not sure and it may not be co-related, but you can try to see what we have. "
McCormack; "Okay."
After the meeting, the rationale for continuing to fly after the STS-1 12 foam loss was sent to
Ham for review. She then exchanged e-mails with her boss, Space Shuttle Program Manager
Ron Dittemore:
Original Message
From: DITTEMORE, RONALD D. (JSC-MA) (NASA)
Sent: Wednesday, January 22, 2003 9:14 AM
To: HAM, LINDA J. (JSC-MA2) (NASA)
Subject: RE: ET Briefing - STS-112 Foam Loss
You remember the briefing! Jerry did it and had to go out and say that the hazard report had not
changed and that the risk had not changed... But it is worth looking at again.
f continued on next page J
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BDARO
[continiietl from previous pcifie]
Original Message
From: HAM, LINDA J. (JSC-MA2) (NASA)
Sent: Tuesday, January 21, 2003 11:14 AM
To: DITTEMORE, RONALD D. (JSC-MA) (NASA)
Subject: FW: ET Briefing - STS-112 Foam Loss
You probably can't open the attachment. But, the ET rationale for flight for the STS-112 loss of foam
was lousy. Rationale states we haven't changed anything, we haven't experienced any 'safety of flight'
damage in 112 flights, risk of loss of bi-pod ramp TPS is same as previous fights... So ET is safe to fly
with no added risk
Rationale was lousy then and still is....
— Original Message
From: MCCORMACK, DONALD L. (DON) (JSC-MV6) (NASA)
Sent: Tuesday, January 21, 2003 9:45 AM
To: HAM, LINDA J. (JSC-MA2) (NASA)
Subject: FW: ET Briefing - STS-112 Foann Loss
Importance: High
FYI - it kinda says that it will probably be all right
fORR=Operafiona/ Readiness Review, VA6=Vefiic/e Assembly Sui/ding, IFA=ln-Flight Anomaly, TPS=Thermal Protection Sys-
tem, ET=External Tank]
Ham's focus on examining the rationale for continuing to fly after the foam problems with
STS-87 and STS-1 12 indicates that her attention had already shifted from the threat the foam
posed to STS-107 to the downstream implications of the foam strike. Ham was due to serve,
along with Wayne Hale, as the launch integration manager for the next mission, STS-1 14. If the
Shuttle Program's rationale to fiy with foam loss was found to be flawed, .STS-1 14, due to be
launched in about a month, would have to be delayed per NASA rules that require serious prob-
lems to be resolved before the next flight. An STS-1 14 delay could in turn delay completion of
the International Space Station's Node 2, which was a high-priority goal for NASA managers.
(See Section 6.2 for a detailed description of schedule pressures.)
During this same Mission Management Team meeting, the Space Shuttle Integration Office's
Lambert Austin reported that engineers were reviewing long-range tracking film and that the
foam debris that appeared to hit the left wing leading edge may have come from the bipod area
of the External Tank. Austin said that the Engineering Directorate would continue to run analy-
ses and compare this foam loss to that of STS-1 12. Austin al.so said that after STS-i()7 landed,
engineers were anxious to see the crew-filmed footage of External Tank separation that might
show the bipod ramp and therefore could be checked for missing foam.
Missed Opportunity 2
Reviews of flight-deck footage confirm that on Flight Day One, Mission Specialist David Brown
filmed parts of the External Tank separation with a Sony PD-K)() Camcorder, and Payload Com-
mander Mike Anderson photographed it with a Nikon F-5 camera with a 400-millimeter lens.
Brown later downlinked .-^5 seconds of this video to the ground as part of his Flight Day One mis-
sion summary, but the bipod ramp area had rotated out of view, so no evidence of missing foam
was seen when this footage was reviewed during the mission. However, after the Intercenter
Photo Working Group caught the debris strike on January 17, ground personnel failed to ask
Brown if he had additional footage of External Tank separation. Based on how crews are trained
to film External Tank separation, the Board concludes Brown did in fact have more film than the
35 seconds he downlinked. Such footage may have confirmed that foam was missing from the
bipod ramp area or could have identified other areas of missing foam. Austin's mention of the
crew "s filming of External Tank separation should have prompted someone at the meeting to ask
Brown if he had more External Tank separation film, and if so. to downlink it immediately.
1 4S ^^^—^^—^^—^^-^^^—^^^^ Report Volume I August zaa3 — ^^— —
COLUMBIA
ACCIDENT INVESTIGATION BDARD
Flight Director Steve Stich discussed the debris strike with Phil Engelauf, a member of the
Mission Operations Directorate, after Engelauf returned from the Mission Management Team
meeting. As written in a timeline Stich composed after the accident, the conversation included
the following.
"Pliil said the Space Shuttle Program community- is not concerned and that Orhiter Project
is analy:.ini> ascent debris. . .relayed that there had been no direction for MOD to ask DOD
for any photography of possible damaged tiles" [MOD=Mission Operafions Direcforate, or
Aiission Conirol, DOD=Deparfmenf of Defense]
"No direction for DOD photography" seems to refer to either a previous discussion of pho-
tography with Mission managers or an expectation of future activity. Since the interagency
agreement on imaging support stated that the Flight Dynamics Officer is responsible for initiat-
ing such a request, Engelauf 's comments demonstrates that an informal chain of command, in
which the Mission Operations Directorate figures prominently, was at work.
About an hour later, Calvin Schomburg, a Johnson Space Center engineer with close connections
to Shuttle management, sent the following e-mail to other Johnson engineering managers.
— Original Message —
From: SCHOMBURG, CALVIN (JSC-EA) (NASA)
Sent: Tuesday, January 21, 2003 9:26 AM
To: SHACK, PAUL E. (JSC-EA42) (NASA); SERIALE-GRUSH, JOYCE M. (JSC-EA) (NASA); HAMILTON, DAVID A.
(DAVE) (JSC-EA) (NASA)
Subject: FW: STS-107 Post-Launch Film Review - Day 1
FYl-TPS took a hit-should not be a problem-status by end of week.
[Fyi=For Your Information, TPS=Thermal Protection System]
Shuttle Program managers regarded Schomburg as an expert on the Thermal Protection System.
His message downplays the possibility that foam damaged the Thermal Protection System.
However, the Board notes that Schomburg was not an expert on Reinforced Carbon-Carbon
(RCC). which initial debris analysis indicated the foam may have struck. Because neither
Schomburg nor Shuttle management rigorously differentiated between tiles and RCC panels,
the bounds of Schomburg's expertise were never properly qualified or questioned.
Seven minutes later, Paul Shack, Manager of the Shuttle Engineering Office. Johnson Engineer-
ing Directorate, e-mailed to Rocha and other Johnson engineering managers information on
how previous bipod ramp foam losses were handled.
Original Message
From: SHACK, PAUL E. (JSC-EA42) (NASA)
Sent: Tuesday, January 21, 2003 9:33 AM
To: ROCHA, ALAN R. (RODNEY) (JSC-ES2) (NASA); SERIALE-GRUSH, JOYCE M. (JSC-EA) (NASA)
Cc: KRAMER, JULIE A. (JSC-EA4) (NASA); MILLER, GLENN J. (JSC-EA) (NASA); RICKMAN, STEVEN L. (JSC-ES3)
(NASA); MADDEN, CHRISTOPHER B. (CHRIS) (JSC-ES3) (NASA)
Subject: RE: STS-107 Debris Analysis Team Plans
This reminded me that at the STS-113 FRR the ET Project reported on foam loss from the Bipod
Ramp during STS-112. The foam (estimated 4X5X12 inches) impacted the ET Attach Ring and
dented an SRB electronics box cover.
Their charts stated "ET TPS foam loss over the life of the Shuttle program has never been a 'Safety of
Flight' issue". They were severely wire brushed over this and Brian O'Connor (Associate Administra-
f continued on next page/
RePORT VOUUME I AUGUST 2003 1 49
COLUMBIA
ACCIDENT INVESTIGATION BOARD
[continued from previous pci^e]
tor for Safety) asked for a hazard assessment for loss of foam.
The suspected cause for foam loss is trapped air pockets which expand due to altitude and aerother-
mal heating.
{FRR=Flighi Readinesi Review, ET=Exferno/ Tank, SRB=So{id Rocket Booster, TPS=Thermal Protection System]
Shack's message informed Rocha that during the STS-1 13 Flight Readiness Review, foam loss
was not considered to be a safety-of-flight issue. The "wirebrushing" that the External Tank
Project received for stating tiiat foam loss has "never been a "Safety of Flight" issue" refers to
the wording used to justify continuing to fly. Officials at the Flight Readiness Review insisted
on classifying the foam loss as an "accepted risk" rather than "not a safety-of-flight problem"
to indicate that although the Shuttle would continue to fly, the threat posed by foam is not zero
but rather a known and acceptable risk.
It is here that the decision to fly before resolving the foam problem at the STS-1 13 Flight
Readiness Review influences decisions made during STS-i07. Having at hand a previously
accepted rationale - reached just one mission ago - that foam strikes are not a safety-of-flight
issue provides a strong incentive for Mission managers and working engineers to use that
same judgment for STS-1 07. If managers and engineers were to argue that foam strikes are
a safety-of-flight issue, they would contradict an established consensus that was a product of
the Shuttle Program's most rigorous review - a review in which many of them were active
participants.
An entry in a Mission Evaluation Room console log included a 10:30 a.m. report that compared
the STS-1 07 foam loss to previous foam losses and subsequent tile damage, which reinforced
management acceptance about foam strikes by indicating that the foam strike appeared to be
more of an "in-family" event.
'■...STS-107 debris measured at 22" \on^ +/- 10". On STS-1 12 the debris spray pattern
was a lot smaller than that of STS-107. On STS-50 debris that was determined to be the
Bipod ramp which nwasured 26 " x 10 " caused danu(,i;e to the left wint^. . .to J tile and 20%
of the adjacent tile. Same event occurred on STS-7 [no data available). "
Missed Opportunity 3
The foam strike to STS-107 was mentioned by a speaker at an unrelated meeting of NASA
Headquarters and National Imagery and Mapping Agency personnel, who then discussed a
possible NASA request for Department of Defense imagery support. However, no action was
taken.
Imagery Request 2
Responding to concerns from his employees who were participating in the Debris Assessment
Team, United Space Alliance manager Bob White called Lambert Austin on Flight Day Six
to ask what it would take to get imagery of Columbia on orbit. They discus.sed the analytical
debris damage work plan, as well as the belief of some integration team members that such
imaging might be beneficial.
Austin subsequently telephoned the Department of Defense Manned Space Flight Support Of-
fice representative to ask about actions necessary to get imagery of Columbia on orbit. Austin
emphasized that this was merely information gathering, not a request for action. This call indi-
cates that Austin was unfamiliar with NASA/National Imagery and Mapping Agency imagery
request procedures.
An e-mail that Lieutenant Colonel Timothy Lee sent to Don McCormack the following day
shows that the Defense Department had begun to implement Austin's request.
'ORT VOUUME I AUGUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Original Message
From: LEE, TIMOTHY F, LTCOL. (JSC-MT) (USAF)
Sent: Wednesday, January 22, 2003 9:01 AM
To: MCCORMACK, DONALD L. (DON) (JSC-MV6) (NASA)
Subject: NASA request for DOD
Don,
FYI: Lambert Austin called me yesterday requesting DOD photo support for STS-107. Specifically, he
is asking us if we have a ground or satellite asset that can take a high resolution photo of the shuttle
while on-orbit--to see if there is any FOD damage on the wing. We are working his request.
Tim
fDOD=Deparffnenf of Defense, FOD=Foreign Ob;ecf Debris]
At the same time, managers Ralph Roe, Lambert Austin, and Linda Ham referred to conversa-
tions with Cal\ in Schomburg. whom they referred to as a Thermal Protection System "expert."
They indicated that Schomburg had advised that any tile damage should be considered a turn-
around maintenance concern and not a safety-of-flight issue, and that imagery of Coliimhia's
left wing was not necessary. There was no discussion of potential RCC damage.
First Debris Assessment Team Meeting
On Flight Day Six. the Debris Assessment Team held its first formal meeting to finalize Orbiter
damage estimates and their potential consequences. Some participants joined the proceedings
via conference call.
Imagery Request 3
After two hours of discussing the Crater results and the need to learn precisely where the debris
had hit Coliiiiihici. the Debris Assessment Team assigned its NASA Co-Chair, Rodney Rocha,
to pursue a request for imagery of the vehicle on-orbit. Each team member supported the idea
to seek imagery from an outside source. Rather than working the request up the usual mission
chain of command through the Mission Evaluation Room to the Mission Management Team to
the Flight Dynamics Officer, the Debris Assessment Team agreed, largely due to a lack of par-
ticipation by Mission Management Team and Mission Evaluation Room managers, that Rocha
would pursue the request through his division, the Engineering Directorate at Johnson Space
Center. Rocha sent the following e-mail to Paul Shack shortly after the meeting adjourned.
— Original Message K
From: ROCHA, ALAN R. (RODNEY) (JSC-ES2) (NASA) |
Sent: Tuesday, January 21, 2003 4:41 PM
To: SHACK, PAUL E. (JSC-EA42) (NASA); HAMILTON, DAVID A. (DAVE) (JSC-EA) (NASA); MILLER, GLENN J. (JSC-
EA) (NASA)
Cc: SERIALE-GRUSH, JOYCE M. (JSC-EA) (NASA); ROGERS, JOSEPH E. (JOE) (JSC-ES2) (NASA); GALBREATH,
GREGORY R (GREG) (JSC-ES2) (NASA)
Subject: STS-107 Wing Debris Impact, Request for Outside Photo-Imaging Help
Paul and Dave,
The meeting participants (Boeing, USA, NASA ES2 and ESS, KSC) all agreed we will always have
big uncertainties in any transport/trajectory analyses and applicability/extrapolation of the old Arc-Jet
test data until we get definitive, better, clearer photos of the wing and body underside. Without better
images it will be very difficult to even bound the problem and initialize thermal, trajectory, and struc-
tural analyses. Their answers may have a wide spread ranging from acceptable to not-acceptable to
horrible, and no way to reduce uncertainty. Thus, giving MOD options for entry will be very difficult.
f continued on next pa,i^ej
^^^^^— ^^^^^^^,^— — ^^-^^— — Report Voi-ume I August 2003 ____^^^^_— — ^^^— — ^— ^— 15 1
COLUMBIA
ACCIDENT INVESTIGATIDN BDARO
[fontiiuietl from previous pcii>e]
Can we petition (beg) for outside agency assistance? We are asking for Frank Benz with Ralph Roe
or Ron Dittemore to ask for such. Some of the old timers here remember we got such help in the early
1980's when we had missing tile concerns.
Despite some nay-sayers, there are some options for the team to talk about: On-orbit thermal condi-
tioning for the major structure (but is in contradiction with tire pressure temp, cold limits), limiting high
cross-range de-orbit entries, constraining hght or left had turns during the Heading Alignment Circle
(only if there is struc. damage to the RCC panels to the extent it affects flight control.
Rodney Rocha
Structural Engineering Division (ES-SED)
• ES Div. Chief Engineer (Space Shuttle DOE)
• Chair, Space Shuttle Loads & Dynamics Panel
Mail Code ES2
fUSA=Un/fed Space A/liance, NASA ES2, ES3=seporofe divisions of f/ie Johnson Space Cenfer Engineering Direcforafe,
KSC=Kennedy Space Cenfer, MOD=A/)issions Operafions Direcforofe, or Mission Confro/J
Routing the request through the Engineering department led in part to it being viewed by Shuttle
Program managers as a non-critical engineering desire rather than a critical operational need.
Flight Day Seven, Wednesday, January 22, 2003
Conversations and log entries on Flight Day Seven document how three requests for images
(Bob Page to Wayne Hale, Bob White to Lambert Austin, and Rodney Rocha to Paul Shack)
were ultimately dismissed by the Mission Management Team, and how the order to halt those
requests was then interpreted by the Debris Assessment Team as a direct and final denial of their
request for imagery.
Missed Opportunity 4
On the morning of Flight Day Seven, Wayne Hale responded to the earlier Flight Day Two re-
quest from Bob Page and a call from Lambert Austin on Flight Day Five, during which Austin
mentioned that "some analysts" from the Debris Assessment Team were interested in getting
imagery. Hale called a Department of Defense representative at Kennedy Space Center (who
was not the designated Department of Defense official for coordinating imagery requests) and
asked that the military start the planning process for imaging Columbia on orbit.
Within an hour, the Defense Department representative at NASA contacted U.S. Strategic
Command (USSTRATCOM) at Colorado's Cheyenne Mountain Air Force Station and asked
what it would take to get imagery of Columliia on orbit. (This call was similar to Austin's call
to the Department of Defense Manned Space Flight Support Office in that the caller character-
ized it as "information gathering" rather than a request for action.) A representative from the
USSTRATCOM Plans Ofhce initiated actions to identify ground-based and other imaging as-
sets that could execute the request.
Hale's earlier call to the Defense Department representative at Kennedy Space Center was
placed without authorization from Mission Management Team Chair Linda Ham. Also, the call
was made to a Department of Defense Representative who was not the designated liaison for
handling such requests. In order to initiate the imager)' request through official channels. Hale
also called Phil Engelauf at the Mission Operations Directorate, told him he had started Defense
Department action, and asked if Engelauf could have the Flight Dynamics Officer at Johnson
Space Center make an official request to the Cheyenne Mountain Operations Center. Engelauf
started to comply with Hale's request.
RePORT VOLUI
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
After the Department of Defense representatives were called, Lambert Austin telephoned Linda
Ham to inform her about the imagery requests that he and Hale had initiated. Austin also told
Wayne Hale that he had asked Lieutenant Colonel Lee at the Department of Defense Manned
Space Flight Support Office about what actions were necessary to get on-orbit imagei^.
Missed Opportunities 5 and 6
Mike Card, a NASA Headquarters manager from the Safety and Mission Assurance Office,
called Mark Erminger at the Johnson Space Center Safety and Mission Assurance for Shuttle
Safety Program and Bryan O'Connor. Associate Administrator for Safety and Mission Assur-
ance, to discuss a potential Department of Defense imaging request. Erminger said that he was
told this was an "in-family" event. O'Connor stated he would defer to Shuttle management in
handling such a request. Despite two safety officials being contacted, one of whom was NASA's
highest-ranking safety official, safety personnel took no actions to obtain imagery.
The following is an 8:09 a.m. entry in the Mission Evaluation Room Console log.
"We received a visit from Mission Manager/Vanessa Ellerlw and FD Office/ Pliil Engekuif
regarding two items: ( I ) the MMT's action item to the MER to determine the impacts to the
vehicle 's 150 Ihs of additional weight. . .and (2) Mr Engelauf wants to know who is request-
ing the Air Force to look at the vehicle. " [FD=Flight Director, MMT=Mission Management Team,
MER=Mission Evaluation Room]
Cancellation of the Request for Imagery
At 8:30 a.m.. the NASA Department of Defense liaison officer called USSTRATCOM and can-
celled the request for imagery. The reason given for the cancellation was that NASA had identi-
fied its own in-house resources and no longer needed the military's help. The NASA request to
the Department of Defense to prepare to image Columbia on-orbit was both made and rescinded
within 90 minutes.
The Board has determined that the following sequence of events likely occurred within that 90-
minute period. Linda Ham asked Lambert Austin if he knew who was requesting the imagery.
After admitting his participation in helping to make the imagery request outside the official
chain of command and without first gaining Ham's permission, Austin referred to his conver-
sation with United Space Alliance Shuttle Integration manager Bob White on Flight Day Six,
in which White had asked Austin, in response to White's Debris Assessment Team employee
concerns, what it would take to get Orbiter imagery.
Even though Austin had already informed Ham of the request for imagery, Ham later called
Mission Management Team members Ralph Roe, Manager of the Space Shuttle Vehicle En-
gineering Office, Loren Shriver, United Space Alliance Deputy Program Manager for Shuttle,
and David Moyer, the on-duty Mission Evaluation Room manager, to determine the origin of
the request and to confirm that there was a "requirement" for a request. Ham also asked Flight
Director Phil Engelauf if he had a "requirement" for imagery of Columbia's left wing. These
individuals all stated that they had not requested imagery, were not aware of any "official"
requests for imagery, and could not identify a "requirement" for imagery. Linda Ham later told
several individuals that nobody had a requirement for imagery.
What started as a request by the Intercenter Photo Working Group to seek outside help in ob-
taining images on Flight Day Two in anticipation of analysts' needs had become by Flight Day
Six an actual engineering request by members of the Debris Assessment Team, made informally
through Bob White to Lambert Austin, and formally in Rodney Rocha's e-mail to Paul Shack.
These requests had then caused Lambert Austin and Wayne Hale to contact Department of
Defense representatives. When Ham officially terminated the actions that the Department
of Defense had begun, she effectively terminated both the Intercenter Photo Working Group
request and the Debris Assessment Team request. While Ham has publicly stated she did not
know of the Debris Assessment Team members' desire for imagery, she never asked them di-
rectly if the request was theirs, even though they were the team analyzing the foam strike.
Also on Flight Day Seven, Ham raised concerns that the extra time spent maneuvering Columbia
to make the left wing visible for imaging would unduly impact the mission schedule; for ex-
—————— Report Volume I Auoust 2003 -^— ^^^.^^^^— — — — — — 15 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
ample, science experiments would have to stop while the imagery was taken. According to
personal notes obtained by the Board:
"Linda Ham said it was no l<nii>er hcini; pursued since even if we saw something, we
coiildn 't do (diytliini; about it. The Proi^ram dichi 't want to spend the resources. "
Shuttle managers, including Ham, also said they were looking for very small areas on the Or-
biter and that past imagery resolution was not very good. The Board notes that no individuals in
the STS- 107 operational chain of command had the security clearance necessary to know about
National imaging capabilities. Additionally, no evidence has been uncovered that anyone from
NASA, United Space Alliance, or Boeing .sought to determine the expected quality of images
and the difficulty and costs of obtaining Department of Defense assistance. Therefore, members
of the Mission Management Team were making critical decisions about imagery capabilities
based on little or no knowledge.
The following is an entry in the Flight Director Handover Log.
'•NASA Resident Office, Peterson AFB called and SOI at USSPACECOM was officially
turned off. This went all the way up to 4 star General. Post flight we will write a memo to
USSPACECOM telling them whom they .should take SOI requests from.""" lAFB=Air Force
Base, SO/=Spacecroff Object IdentiFicafion, USSPACECOM=U.S. Space Command]
After canceling the Department of Defense imagery request, Linda Ham continued to explore
whether foam strikes posed a safety of flight issue. She sent an e-mail to Lambert Austin and
Ralph Roe.
Original Message—
From: HAM, LINDA J. (JSC-MA2) (NASA)
Sent: Wednesday, January 22, 2003 9:33 AM
To: AUSTIN, LAMBERT D. (JSC-MS) (NASA); ROE,
Subject: ET Foam Loss
RALPH R.
(JSC-MV) (NASA)
Can we
the den
say that for any
sity?
ET foam lost, no 'safety of flight' damage can occur
to the Orbiter because
of
[ET=Extemal Tank]
Responses included the following.
Original Message
From: ROE, RALPH R. (JSC-MV) (NASA)
Sent: Wednesday, January 22, 2003 9:38 AM
To: SCHOMBURG, CALVIN (JSC-EA) (NASA)
Subject: FW: ET Foam Loss
Calvin,
1 wouldn't think we could make such a generic statement but can we bound it some how by size or
acreage?
[Acreoge=larger areas of foam coverage^
Ron Dittermore e-mailed Linda Ham the following.
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Original Message
From: DITTEMORE, RONALD D. (JSC-MA) (NASA)
Sent: Wednesday, January 22, 2003 10:15 AM
To: HAM, LINDA J. (JSC-MA2) (NASA)
Subject: RE: ET Briefing - STS-112 Foam Loss
Another thought, we need to make sure that the density of the ET foam cannot damage the tile to
where it is an impact to the orbiter... Lambert and Ralph need to get some folks working with ET.
The following is an e-mail from Calvin Schombiirg to Ralph Roe.
Original Message
From: SCHOMBURG, CALVIN (JSC-EA) (NASA)
Sent: Wednesday, January 22, 2003 10:53 AM
To: ROE, RALPH R. (JSC-MV) (NASA)
Subject: RE: ET Foam Loss
No-the amount of damage ET foam can cause to the TPS material-tiles is based on the amount of
impact energy-the size of the piece and its velocity( from just after pad clear until about 120 seconds-
after that it will not hit or it will not enough energy to cause any damage)-it is a pure kinetic problem-
there is a size that can cause enough damage to a tile that enough of the material is lost that we
could burn a hole through the skin and have a bad day-(loss of vehicle and crew -about 200-400 tile
locations( out of the 23,000 on the lower surface )-the foam usually fails in small popcorn pieces-that
is why it is vented-to make small hits-the two or three times we have been hit with a piece as large
as the one this flight-we got a gouge about 8-10 inches long about 2 inches wide and 3/4 to an 1 inch
deep across two or three tiles. That is what I expect this time-nothing worst. If that is all we get we
have have no problem-will have to replace a couple of tiles but nothing else.
[ET=External Tank, TPS=Tbermal Profection System]
The following is a response from Lambert Austin to Linda Ham.
Original Message
From: AUSTIN, LAMBERT D. (JSC-MS) (NASA)
Sent: Wednesday, January 22, 2003 3:22 PM
To: HAM, LINDA J. (JSC-MA2) (NASA)
Cc: WALLACE, RODNEY 0. (ROD) (JSC-MS2) (NASA); NOAH, DONALD S. (DON) (JSC-MS) (NASA)
Subject: RE: ET Foam Loss
NO. I will cover some of the pertinent rationale. ...there could be more if I spent more time thinking
about it. Recall this issue has been discussed from time to time since the inception of the basic "no
debris" requirement in Vol. X and at each review the SSP has concluded that it is not possible to
PRECLUDE a potential catastrophic event as a result of debris impact damage to the flight elements.
As regards the Orbiter, both windows and tiles are areas of concern.
You can talk to Cal Schomberg and he will verify the many times we have covered this in SSP
reviews. While there is much tolerance to window and tile damage, ET foam loss can result in im-
pact damage that under subsequent entry environments can lead to loss of structural integrity of the
Orbiter area impacted or a penetration in a critical function area that results in loss of that function.
My recollection of the most critical Orbiter bottom acreage areas are the wing spar, main landing gear
door seal and RCC panels. ..of course Cal can give you a much better rundown.
We can and have generated parametric impact zone characterizations for many areas of the Orbiter
for a few of our more typical ET foam loss areas. Of course, the impact/damage significance is always
a function of debrir size and density, impact velocity, and impact angle-these latter 2 being a function
of the flight time at which the ET foam becomes debris. For STS-107 specifically, we have generated
[continued on next pcii^e]
Report volume i august Z003 — ^^^__^^.^— — — ^^^^ 1 55
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
[continued from previous pa}>e]
this info and provided it to Orbiter. Of course, even this is based on the ASSUMPTION that the loca-
tion and size of the debris is the same as occurred on STS-112 this cannot be verified until we
receive the on-board ET separation photo evidence post Orbiter landing. We are requesting that this
be expedited. I have the STS-107 Orbiter innpact map based on the assumptions noted herein being
sent down to you. Rod is in a review with Orbiter on this info right now.
[SSP-Space Sf)utf/e Program, Er=Exferna/ Tank]
The Board notes that these e-mail exchanges indicate that senior Mission Management Team
managers, including the Shuttle Program Manager. Mission Management Team Chair, head of
Space Shuttle Systems Integration, and a Shuttle tile expert, correctly identified the technical
bounds of the foam strike problem and its potential seriousness. Mission managers understood
that the relevant question was not whether foam posed a safcty-of- flight issue - it did - but
rather whether the observed foam strike contained sufficient kinetic energy to cause damage
that could lead to a burn-through. Here, all the key managers were asking the right question
and admitting the danger. They even identified RCC as a critical impact zone. Yet little follow-
through occurred with either the request for imagery or the Debris Assessment Team analysis.
(See Section 3.4 and 3.6 for details on the kinetics of foam strikes.)
A Mission Evaluation Room log entry at 10:37 a.m. records the decision not to seek imaging
of Coliinihia's left wing.
"USA Prof;rani Mwntiier/Loren Sliriver. NASA Manager, Program Integration/ Linda Ham,
& NASA SSVEO/Ralph Roe have stated that there is no need for the Air Force to take a look
at the vehicle." [USA=United Space Alliance, SSVEO=Space Shuttle Vehicle Engineering Office]
At 1 1 ;22 a.m.. Debris Assessment Team Co-Chair Pam Madera sent an e-mail to team members
setting the agenda for the team's second formal meeting that afternoon that included:
"... Discussion on Need/Rationale for Mandatory Viewing ff damage site (All)..."
Earlier e-mail agenda wording did not include "Need/Rationale for Mandatory" wording as
listecj here, which indicates that Madera knew of management's decision to not seek images of
Columbia 's left wing and anticipated having to articulate a "mandatory" rationale to reverse that
decision. In fact, a United Space Alliance manager had informed Madera that imagery would be
sought only if the request was a "mandatory need." Twenty-three minutes later, an e-mail from
Paul Shack to Rodney Rocha, who the day before had carried forward the Debris Assessment
Team's request for imaging, stated the following.
". . . FYl. According to the MER, Ralph Roe has told program that Orbiter is not requesting
any outside imaging help ..." [MER=Mission Evaluation Room]
Earlier that morning, Ralph Roe's deputy manager, Trish Petite, had separate conversations
with Paul Shack and tile expert Calvin Schomburg. In those conversations. Petite noted that
an analysis of potential damage was in progress, and they should wait to see what the analysis
showed before asking for imagery. Schomburg, though aware of the Debris Assessment Team's
request for imaging, told Shack and Petite that he believed on-orbit imaging of potentially dam-
aged areas was not necessary.
As the moming wore on. Debris Assessment Team engineers. Shuttle Program management,
and other NASA personnel exchanged e-mail. Most messages centered on technical matters
to be discussed at the Debris Assessment Team's afternoon meeting, including debris density,
computer-aided design models, and the highest angle of incidence to use for a particular mate-
rial property. One e-mail from Rocha to his managers and other Johnson engineers at 11:19
a.m., included the following.
". . . there are good scenarios (acceptable and minimal damage) to horrible ones, depend-
ing on the extent of the damage incurred by the wing and location. The most critical loca-
1 5S — — — ^— — — — ^— — Report Volume I August 2003 — — ^—
COLUMBIA
ACCIDENT INVESTIGATION BOARD
rions seem to he the 1191 witi}^ spar region, the main hmding gear door seal, and the RCC
panels. We do not know yet the exact extent or nature of the damage without being provided
better images, and without such all the high powered analyses and as.sessments in work
will retain significant uncertainties ..."
Second Debris Assessment Team Meeting
Some but not all of the engineers attending the Debris Assessment Team's second meeting had
learned that the Shuttle Program was not pursuing imaging of potentially damaged areas. What
team members did not realize was the Shuttle Program's decision not to seek on-orbit imagery
was not necessarily a direct and final response to their request. Rather, the "no" was partly in
response to the Kennedy Space Center action initiated by United Space Alliance engineers and
managers and finally by Wayne Hale.
Not knowing that this was the case. Debris Assessment Team members speculated as to why
their request was rejected and whether their analysis was worth pursuing without new imagery.
Discussion then moved on to whether the Debris Assessment Team had a "mandatory need" for
Department of Defense imaging. Most team members, when asked by the Board what "manda-
tory need" meant, replied with a shrug of their shoulders. They believed the need for imagery
was obvious: without better pictures, engineers would be unable to make reliable predictions of
the depth and area of damage caused by a foam strike that was outside of the experience base.
However, team members concluded that although their need was important, they could not cite
a "mandatory" requirement for the request. Analysts on the Debris Assessment Team were in the
unenviable position of wanting images to more accurately assess damage while simultaneously
needing to prove to Program managers, as a result of their asses.sment. that there was a need
for images in the first place.
After the meeting adjourned. Rocha read the 1 1 :45 a.m. e-mail from Paul Shack, which said that
the Orbiter Project was not requesting any outside imaging help. Rocha called Shack to ask if
Shack's boss. Johnson Space Center engineering director Frank Benz, knew about the request.
Rocha then sent several e-mails consisting of questions about the ongoing analyses and details
on the Shuttle Program's cancellation of the imaging request. An e-mail that he did not send but
instead printed out and shared with a colleague follows.
"In m\ humble technical opinion, this is the wrong (and bordering on irresponsible) an-
swer from the SSP and Orbiter not to request additional imaging help from any outside
source. I must emphasize (again) that severe enough damage (3 or 4 multiple tiles knocked
out down to the densification layer) combined with the heating and re.mlting damage to the
underlying .structure at the most critical location (viz.. MLG door/wheels/tires/hydraulics
or the XI 191 spar cap) could present potentially grave hazards. The engineering team will
admit it might not achieve definitive high confidence answers without additional images,
but, without action to request help to clarify the damage visually, we will guarantee it will
not. Can we talk to Frank Benz before Friday 's MMT? Remember the NASA safety post-
ers everywhere around stating. 'If it's not safe, say so".' Yes, it's that serious." [SSP^Space
Shuttle Program, MLG=Main Landing Gear, MA^T=Mission /Management Team]
When asked why he did not send this e-mail, Rocha replied that he did not want to jump the
chain of command. Having already raised the need to have the Orbiter imaged with Shack, he
would defer to management's judgment on obtaining imagery.
Even after the imagery request had been cancelled by Program management, engineers in the
Debris Assessment Team and Mission Control continued to analyze the foam strike. A structural
engineer in the Mechanical, Maintenance, Arm and Crew Systems sent an e-mail to a flight
dynamics engineer that stated:
"There is lots of speculation as to extent of the damage, and we could get a burn through
into the wheel well upon entry. "
Less than an hour later, at 6:09 p.m.. a Mission Evaluation Room Console log entry stated the
following.
"MMACS is trying to view a Quicktime movie on the debris impact but doesn V have Quick-
RepdRT Volume I August 2003 1 57
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
time software on his console. He needs either cm avi, mpei> file or a vhs tape. He is ciskini^
us for help. " [MMACS=Mechanical, Mainfenance, Arm and Crew Systems]
The controller at the Mechanical, Maintenance, Arm and Crew Systems console would be
among the first in Mission Control to see indications of burn-through during Coliiinhia\ re-en-
try on the morning of February 1. This log entry also indicates that Mission Control personnel
were aware of the strike.
Flight Day Eight, Thursday, January 23, 2003
The morning after Shuttle Program Management decided not to pursue on-orbit imagery. Rod-
ney Rocha received a return call from Mission Operations Directorate representative Barbara
Conte to discuss what kinds of imaging capabilities were available for STS-107.
Missed Opportunity 7
Conte explained to Rocha that the Mission Operations Directorate at Johnson did have U.S.
Air Force standard services for imaging the Shuttle during Solid Rocket Booster separation
and External Tank separation. Conte explained that the Orbiter would probably have to fly over
Hawaii to be imaged. The Board notes that this statement illustrates an unfamiliarity with Na-
tional imaging assets. Hawaii is only one of many sites where relevant assets are based. Conte
asked Rocha if he wanted her to pursue such a request through Missions Operations Directorate
channels. Rocha said no, because he believed Program managers would still have to support
such a request. Since they had already decided that imaging of potentially damaged areas was
not necessary, Rocha thought it unlikely that the Debris Assessment Team could convince them
otherwise without definitive data.
Later that day, Conte and another Mission Operations Directorate representative were attending
an unrelated meeting with Leroy Cain, the STS-107 ascent/entry Flight Director. At that meet-
ing, they conveyed Rocha's concern to Cain and offered to help with obtaining imaging. After
checking with Phil Engelauf, Cain distributed the following e-mail.
Original Message
From: CAIN, LEROY E. (JSC-DA8) (NASA)
Sent: Thursday, January 23, 2003 12:07 PM
To: JONES, RICHARD S. (JSC-DM) (NASA); OLIVER, GREGORY T (GREG) (JSC-DM4) (NASA); CONTE, BARBARA A.
(JSC-DM) (NASA)
Cc: ENGELAUF, PHILIP L. (JSC-DA8) (NASA); AUSTIN, BRYAN P. (JSC-DA8) (NASA); BECK, KELLY B. (JSC-DA8)
(NASA); HANLEY, JEFFREY M. (JEFF) (JSC-DA8) (NASA); STICH, J. S. (STEVE) (JSC-DA8) (NASA)
Subject: Help with debris hit
The SSP was asked directly if they had any interest/desire in requesting resources outside of NASA
to view the Orbiter (ref. the wing leading edge debris concern).
They said, No.
After talking to Phil, I consider it to be a dead issue.
[SSP=Space Shuttle Program]
Also on Flight Day Eight, Debris Assessment Team engineers presented their final debris trajec-
tory estimates to their NASA, United Space Alliance, and Boeing managers. These estimates
formed the basis for predicting the Orbiter's damaged areas as well as the extent of damage,
which in turn determined the ultimate threat to the Orbiter during re-entry.
Mission Control personnel thought they should tell Commander Rick Husband and Pilot Wil-
liam McCool about the debris strike, not because they thought that it was worthy of the crew's
attention but because the crew might be asked about it in an upcoming media interview. Flight
Director Steve Stitch sent the following e-mail to Husband and McCool and copied other Flight
Directors.
15a ^^^_^^-^^^^^^^^^^___ Report Volume I August zaa3 — ^— —
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Original Message
From: STICH, J. S. (STEVE) (JSC-DA8) (NASA)
Sent: Thursday, January 23, 2003 11:13 PM
To: CDR; PLT
Cc: BECK, KELLY B. (JSC-DA8) (NASA); ENGELAUF, PHIUP L. (JSC-DA8) (NASA); CAIN, LEROY E. (JSC-DA8)
(NASA); HANLEY, JEFFREY M. (JEFF) (JSC-DA8) (NASA); AUSTIN, BRYAN P. (JSC-DA8) (NASA)
Subject: INFO: Possible PAO Event Question
Rick and Willie,
You guys are doing a fantastic job staying on the timeline and accomplishing great science. Keep up
the good work and let us know if there is anything that we can do better from an MCC/POCC stand-
point.
There is one item that I would like to make you aware of for the upcoming PAO event on Blue FD
10 and for future PAO events later in the mission. This item is not even worth mentioning other than
wanting to make sure that you are not surprised by it in a question from a reporter.
During ascent at approximately 80 seconds, photo analysis shows that some debris from the area of
the -Y ET Bipod Attach Point came loose and subsequently impacted the orbiter left wing, in the area
of transition from Chine to Main Wing, creating a shower of smaller particles. The impact appears
to be totally on the lower surface and no particles are seen to traverse over the upper surface of the
wing. Experts have reviewed the high speed photography and there is no concern for RCC or tile
damage. We have seen this same phenomenon on several other flights and there is absolutely no
concern for entry.
That is all for now. It's a pleasure working with you every day.
fMCC/POCC=Mission Control Center/Payload Operations Control Center, PAO=Pub/(c Affairs Officer, FD 70=F/(g/)f Day
Ten, -Y=left, ET=External Tank]
This e-mail was followed by another to the crew with an attachment of the video showing the
debris impact. Husband acknowledged receipt of these messages.
Later, a NASA liaison to USSTRATCOM sent an e-mail thanking personnel for the prompt
response to the imagery request. The e-mail asked that they help NASA observe "official chan-
nels" for this type of support in the future. Excerpts from this message follow.
"Let me assure you that, as of yesterday afternoon, the Shuttle was in excellent shape,
mission objectives were heinfi performed, and that there were no major debris system
problems identified. The request that you received was based on a piece of debris, most
likely ice or insulation from the ET, that came off shortly after launch and hit the underside
of the vehicle. Even thoui-h this is not a common occurrence it is something that has hap-
pened before and is not considered to be a major problem. The one problem that this has
identified is the need for some additional coordination within NASA to assure that when a
request is made it is done throuf^h the official channels. The NASA/ USSTRAT (USSPACE)
MO A identifies the need for this type of support and that it will be provided by USSTRAT.
Procedures have been loiiff established that identifies the Flight Dynamics Officer {for the
Shuttle) and the Trajectory Operations Officer (for the International Space Station) as the
POCs to work these issues with the personnel in Cheyenne Mountain. One of the primary
purposes for this chain is to make sure that requests like this one does not slip through the
system and spin the community up about potential problems that have not been fully vet-
ted through the proper channels. Two things that you can help us with is to make sure that
future requests of this sort are confirmed through the proper channels. For the Shuttle it
is via CMOC to the Flight Dyiuimics Officer. For the International Space Station it is via
CMOC to the Trajectory Operations Officer. The second request is that no resources are
spent unless the request has been confirmed. These requests are not meant to diminish the
responsibilities of the DDMS office or to change any previous agreements but to eliminate
the confusion that can be caused by a lack of proper coordiiuition." [ET=External Tank,
— ^-^— — Report Volume I Auqust 2003 __^^^^^_^^^— — ^^^^.^.— ^— ^ 15 9
COLUMBIA
ACCIDENT INVESTIGATION BOARD
MOA=Memorandum of Agreemenf, POC=Poinf of Contact, CMOC=Cheyenne Mountain Opera-
tions Center, DDMS=Department of Defense Manned Space Fligfit Support Office]
Third Debris Assessment Team Meeting
The Debris Assessment Team met for the third time Thursday afternoon to review updated
impact analyses. Engineers noted that there were no alternate re-entry trajectories that the Or-
biter could fly to substantially reduce heating in the general area of the foam strike. Engineers
also presented final debris trajectory data that included three debris size estimates to cover
the continuing uncertainty about the size of the debris. Team members were told that imaging
would not be forthcoming. In the face of this denial, the team discussed whether to include a
presentation slide supporting their desire for images of the potentially damaged area. Many still
felt it was a valid request and wanted their concerns aired at the upcoming Mission Evaluation
Room brief and then at the Mission Management Team level. Eventually, the idea of including
a presentation slide about the imaging request was dropped.
Just prior to attending the third assessment meeting, tile expert Calvin Schomburg and Rod-
ney Rocha met to discuss foam impacts from other missions. Schomburg implied that the
STS-107 foam impact was in the Orbiter's experience base and represented only a maintenance
issue. Rocha disagreed and argued about the potential for burn-through on re-enti^. Calvin
Schomburg stated a belief that if there was severe damage to the tiles, "nothing could he done. "
(See Section 6.4.) Both then joined the meeting already in progress.
According to Boeing analysts who were members of the Debris Assessment Team, Schomburg
called to ask about their rationale for pursuing imagery. The Boeing analysts told him that
something the size of a large cooler had hit the Orbiter at 500 miles per hour. Pressed for ad-
ditional reasons and not fully understanding why their original justification was insufficient,
the analysts said that at least they would know what happened if something were to go terribly
wrong. The Boeing analysts next asked why they were working so hard analyzing potential
damage areas if Shuttle Program management believed the damage was minor and that no
safety-of-flight issues existed. Schomburg replied that the analysts were new and would learn
from this exercise.
Flight Day Nine, Friday, January 24, 2003
At 7:00 a.m., Boeing and United Space Alliance contract personnel presented the Debris As-
sess/nent Team's findings to Don McCormack. the Mission Evaluation Room manager. In yet
another signal that working engineers and mission personnel shared a high level of concern for
Coliimhia'?, condition, so many engineers crowded the briefing room that it was standing room
only, with people lining the hallway.
The presentation included viewgraphs that discussed the teain's analytical methodology and
five scenarios for debris damage, each based on different estimates of debris size and impact
point. A sixth scenario had not yet been completed, but early indications suggested that it would
not differ significantly from the other five. Each case was presented with a general overview
of transport mechanics, results from the Crater modeling, aerothermal considerations, and pre-
dicted thermal and structural effects for Columbia ^ re-entry. The briefing focused primarily on
potential damage to the tiles, not the RCC panels. (An analysis of how the poor construction
of these viewgraphs effectively minimized key assumptions and uncertainties is presented in
Chapter 7.)
While the team members were confident that they had conducted the analysis properly - with-
in the limitations of the information they had - they stressed that many uncertainties remained.
First, there was great uncertainty about where the debris had struck. Second, Crater, the analyt-
ical tool they used to predict the penetration depth of debris impact, was being used on a piece
of debris that was 400 times larger than the standard in Boeing's database. (At the time, the
team believed that the debris was 640 times larger.) Engineers ultimately concluded that their
analysis, limited as it was, did not show that a safety-of-flight issue existed. Engineers who
attended this briefing indicated a belief that management focused on the answer- that analysis
proved there was no safety-of-flight issue - rather than concerns about the large uncertainties
that may have undermined the analysis that provided that answer.
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
At the Mission Management Team's 8:00 a.m. meeting. Mission Evaluation Room manager
Don McCormack verbally summarized the Debris Assessment Team's 7:00 a.m. brief. It was
the third topic discussed. Unlike the earlier briefing, McCormack's presentation did not include
the Debris Assessment Team's presentation charts. The Board notes that no supporting analysis
or e.xamination of minority engineering views was asked for or offered, that neither Mission
Evaluation Room nor Mission Management Team members requested a technical paper of the
Debris Assessment Team analysis, and that no technical questions were asked.
January 24, 2003, Mission Management Team Meeting Transcript
The following is a transcript of McCormack's verbal briefing to the Mission Management
Team, which Linda Ham Chaired. Early in the meeting, Phil Engelauf. Chief of the Flight
Director's office, reported that he had made clear in an e-mail to Colunihia's crew that there
were "no concerns" that the debris strike had caused serious damage. The Board notes that this
conclusion about whether the debris strike posed a safety-of-flight issue was presented to Mis-
sion Management Team members before they discussed the debris strike damage assessment.
Engelauf: '7 will say that crew did send down a note last nii^ht asking if anybody is talking
about extension days or going to go with that and we sent up to the crew about a 15 second
video clip of the strike just so they are armed if they get any questions at the press conferences
or that sort of thing, but we made it ver\- clear to them no, no concerns. "
Linda Ham: ''When is the press conference'.' Is it today/"
Engelauf: "It's later today."
Ham: "They may get asked because the press is aware of it. "
Engelauf: "The press is aware of it I know folks have asked me because the press corps at the
cape have been asking. . .wanted to make sure they were properly. . . "
Ham: "Okay, back on the temperature..."
The meeting went on for another 25 minutes. Other mission-related subjects were discussed
before team members returned to the debris strike.
Ham: "Go ahead, Don. "
Don McCormack: "Okay. And also we've received the data from the systems integration guys
of the potential ranges of sizes and impact angles and where it might have hit. And the guys
have gone off and done an analysis, they use a tool they refer to as Crater which is their official
evaluation tool to determine the potential size of the damage. So they went off and done all that
work and they've done thermal analysis to the areas where there may he damaged tiles. The
analysis is not complete. There is one case yet that they wish to run, hut kind of just Jumping to
the conclusion of all that, they do show that, obviously, a potential for significant tile damage
here, but thermal analysis does not indicate that there is potential for a burn-through. I mean
there could be localized heating damage. There is... obviously there is a lot of uncertainty in
all this in terms of the size of the debris and where it hit and the angle of incidence. "
Ham: "No burn through, means no catastrophic damage and the localiz.ed heating damage
would mean a tile replacement'.' "
McCormack: "Right, it would mean possible impacts to turnaround repairs and that .sort of
thing, but we do not see any kind of safety of flight issue here yet in anything that we 've looked
at."
Ham: "And no safety (f flight, no issue for this missicm, nothing that we're going to do different,
there may be a turnaround. "
McCormack: "Right, it could potentially hit the RCC and we don 'f indicate any other possible
coating damage or .something, we don 't see any issue if it hit the RCC. Although we could have
some significant tile damage if we don 't .see a .safety -of flight issue. "
— — — Report Volume I Auqust 2003 —————— ^——^—^— 16 1
Ham: "What do von mean hv that'.'
COLUMBIA
ACCIDENT INVESTIGATION BOARD
McCormack: ''Well it could he down throui>h the ...we could lose an entire file and then the
ramp into and out of that. I mean it could he a significant area of tile damage down to the SIP
perhaps, so it could he a significant piece missing, hut. . . " [SIP refers to the denser lower loyers of
tile to which the debris may have penetrated.]
Ham.: "It would he a turnaround issue only?"
McCormack: "Right."
(Unintelligible speaker)
At this point, tile expert Calvin Schomburg states his belief that no safety-of-flight issue exists.
However, some participants listening via teleconference to the meeting are unable to hear his
comments.
Ham: "Okay. Same thing you told me about the other day in my office. We 've seen pieces of this
size before haven't we'.''"
Unknown speaker. "Hey Linda, we're missing part of that conversation. "
Ham: "Right. "
Unknown speaker: "Linda, we can 't hear the .speaker. "
Ham: "He was just reiterating with Calvin that he doesn 't believe that there is any burn-through
so no safi'ty of flight kind of issue, it 's more of a turiuiround issue similar to what we 've had on
other flights. That's it? Alright, any questions on that?"
The Board notes that when the official minutes of the January 24 Mission Management Team
were produced and distributed, there was no mention of the debris strike. These minutes were
approved and signed by Frank Moreno, STS-107 Lead Payload Integration Manager, and Linda
Ham. For anyone not present at the January 24 Mission Management Team who was relying on
the minutes to update them on key issues, they would have read nothing about the debris-strike
discussions between Don McCormack and Linda Ham.
A subsequent 8:59 a.m. Mission Evaluation Room console log entiy follows.
"MMT Summary. . .McCormack also summarized the debris assessment. Bottom line is that
there appears to he no safely of flight issue, but good chance of turnaround impact to repair
tile damage. " ltAM7=Mission Management Team]
Flight Day 10 through 16, Saturday through Friday, January 25 through 31, 2003
Although "no safety-of-fiight issue" had officially been noted in the Mission Evaluation Room
log, the Debris Assessment Team was still working on parts of its analysis of potential damage
to the wing and main landing gear door. On Sunday, January 26, Rodney Rocha spoke with a
Boeing thermal analyst and a Boeing stress analyst by telephone to express his concern about
the Debris Assessment Team's overall analysis, as well as the remaining work on the main land-
ing gear door analysis. After the Boeing engineers stated their confidence with their analyses,
Rocha became more comfortable with the damage assessment and sent the following e-mail to
his management.
Report Voi-ume I Auqust 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Original Message
From: ROCHA, ALAN R. (RODNEY) (JSC-ES2) (NASA)
Sent: Sunday, January 26, 2003 7:45 PM
To: SHACK, PAUL E. (JSC-EA42) (NASA); MCCORMACK, DONALD L. (DON) (JSC-MV6) (NASA); OUELLETTE, FRED A.
(JSC-MV6) (NASA)
Cc: ROGERS, JOSEPH E. (JOE) (JSC-ES2) (NASA); GALBREATH, GREGORY F. (GREG) (JSC-ES2) (NASA); JACOBS,
JEREMY B. (JSC-ES4) (NASA); SERIALE-GRUSH, JOYCE M. (JSC-EA) (NASA); KRAMER, JULIE A. (JSC-EA4)
(NASA); CURRY, DONALD M. (JSC-ES3) (NASA); KOWAL, T. J. (JOHN) (JSC-ES3) (NASA); RICKMAN, STEVEN L.
(JSC-ES3) (NASA); SCHOMBURG, CALVIN (JSC-EA) (NASA); CAMPBELL, CARLISLE C, JR (JSC-ES2) (NASA)
Subject: STS-107 Wing Debris Impact on Ascent: Final analysis case completed
As you recall from Friday's briefing to the MER, there remained open work to assess analytically
predicted impact damage to the wing underside in the region of the main landing gear door. This area
was considered a low probability hit area by the image analysis teams, but they admitted a debris
strike here could not be ruled out.
As with the other analyses performed and reported on Friday, this assessment by the Boeing multi-
technical discipline engineering teams also employed the system integration's dispersed trajectories
followed by serial results from the Crater damage prediction tool, thermal analysis, and stress analy-
sis. It was reviewed and accepted by the ES-DCE (R. Rocha) by Sunday morning, Jan. 26. The case
is defined by a large area gouge about 7 inch wide and about 30 inch long with sloped sides like a
crater, and reaching down to the densified layer of the TPS.
SUMMARY: Though this case predicted some higher temperatures at the outer layer of the hon-
eycomb aluminum face sheet and subsequent debonding of the sheet, there is no predicted burn-
through of the door, no breeching of the thermal and gas seals, nor is there door structural deforma-
tion or thermal warpage to open the seal to hot plasma intrusion. Though degradation of the TPS and
door structure is likely (if the impact occurred here), there is no safety of flight (entry, descent, land-
ing) issue.
Note to Don M. and Fred O.: On Friday I believe the MER was thoroughly briefed and it was clear that
open work remained (viz., the case summarized above), the message of open work was not clearly
given, in my opinion, to Linda Ham at the MMT. I believe we left her the impression that engineering
assessments and cases were all finished and we could state with finality no safety of flight issues or
questions remaining. This very serious case could not be ruled out and it was a very good thing we
carried it through to a finish.
Rodney Rocha (ES2)
• Division Shuttle Chief Engineer (DCE), ES-Structural Engineering Division
• Chair, Space Shuttle Loads & Dynamics Panel
[MER-Mission Evaluafion Room, ES-DCE=Siructural Engineering-Division Shuffle Chiei Engineer, TPS=Thermal Protection
System]
In response to this e-mail, Don McCormack told Rocha that he would make sure to correct
Linda Ham's possible misconception that the Debris Assessment Team's analysis was finished
as of the briefing to the Mission Management Team. McCormack informed Ham at the next
Mission Management Team meeting on January 27, that the damage assessment had in fact
been ongoing and that their final conclusion was that no safety-of-flight issue existed. The de-
bris strike, in the official estimation of the Debris Assessment Team, amounted to only a post-
landing turn-around maintenance issue.
On Monday morning. January 27, Doug Drewry. a structural engineering manager from John-
son Space Center, summoned several Johnson engineers and Rocha to his office and asked them
if they all agreed with the completed analyses and with the conclusion that no safety-of-flight
issues existed. Although all participants agreed with that conclusion, they also knew that the
Debris Assessment Team members and most structural engineers at Johnson still wanted im-
ages of C(>hiinhui\ left wing but had given up trying to make that desire fit the "mandatory"
requirement that Shuttle management had set.
Report Volume I August 2003 ____^^— — — — — — ^^^^— — — — — 16 3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Langley Research Center
Although the Debris Analysis Team had completed its analysis and rendered a "no safety-of-
flight" verdict, concern persisted among engineers elsewhere at NASA as they learned about
the debris strike and potential damage. On Monday. January 27, Carlisle Campbell, the design
engineer responsible for landing gear/tires/brakes at Johnson Space Center forwarded Rodney
Rocha's January 26, e-mail to Bob Daugherty, an engineer at Langley Research Center who
specialized in landing gear design. Engineers at Langley and Ames Research Center and John-
son Space Center did not entertain the possibility of Coltiiiihia breaking up during re-entry,
but rather focused on the idea that landing might not be safe, and that the crew might need to
"ditch" the vehicle (crash land in water) or be prepared to land with damaged landing gear.
Campbell initially contacted Daugherty to ask his opinion of the arguments used to declare the
debris strike "not a safety-of-flight issue." Campbell commented that someone had brought up
worst-case scenarios in which a breach in the main landing gear door causes two tires to go flat.
To help Daugherty understand the problem, Campbell forwarded him e-mails, briefing slides,
and film clips from the debris damage analysis.
Both engineers felt that the potential ramifications of landing with two flat tires had not been
sufficiently explored. They discussed using Shuttle simulator facilities at Ames Research Cen-
ter to simulate a landing with two flat tires, but initially ruled it out because there was no formal
request from the Mission Management Team to work the problem. Because astronauts were
training in the Ames simulation facility, the two engineers looked into conducting the simula-
tions after hours. Daugherty contacted his management on Tuesday, January 28, to update them
on the plan for after-hours simulations. He reviewed previous data runs, current simulation
results, and prepared scenarios that could result from main landing gear problems.
The simulated landings with two flat tires that Daugherty eventually conducted indicated that it
was a survivable but very serious malfunction. Of the various scenarios he prepared, Daugherty
shared the most unfavorable only with his management and selected Johnson Space Center
engineers. In contrast, his favorable simulation results were forwarded to a wider Johnson audi-
ence for review, including Rodney Rocha and other Debris Assessment Team members. The
Board is disappointed that Daugherty *s favorable scenarios received a wider distribution than
his discovery of a potentially serious malfunction, and also does not approve of the reticence
that he and his managers displayed in not notifying the Mission Management Team of their
concerns or his assumption that they could not displace astronauts who were training in the
Am^s simulator.
At 4:36 p.m. on Monday, January 27, Daugherty sent the following to Campbell.
Original Message
From: Robert H. Daugherty
Sent: Monday, January 27, 2003 3:35 PM
To: CAMPBELL, CARLISLE C, JR (JSC-ES2) (NASA)
Subject: Video you sent
WOW!!!
I bet there are a few pucker strings pulled tight around there!
Thinking about a belly landing versus bailout (I would say that if there is a question about main
gear well burn thru that its crazy to even hit the deploy gear button. ..the reason being that you might
have failed the wheels since they are aluminum.. they will fail before the tire heating/pressure makes
them fail. .and you will send debris all over the wheel well making it a possibility that the gear would
not even deploy due to ancillary damage. ..300 feet is the wrong altitude to find out you have one gear
down and the other not down. ..you're dead in that case)
Think about the pitch-down moment for a belly landing when hitting not the main gear but the trailing
edge of the wing or body flap when landing gear up. ..even if you come in fast and at slightly less pitch
attitude. ..the nose slapdown with that pitching moment arm seems to me to be pretty scary.. .so much
so that I would bail out before I would let a loved one land like that.
My two cents.
See ya,
Bob
— — ^^^— — — — — ^— ^— Report volume I August 2003 ^^^__^^_^_______
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The following reply from Campbell to Daugherty was sent at 4:49 p.m.
Original Message
From: "CAMPBELL, CARLISLE C, JR (JSC-ES2) (NASA)"
To: "'Bob Daugherty'"
Subject: FW: Video you sent
Date: Mon, 27 Jan 2003 15:59:53 -0600
X-Mailer: RInternet Mail Service (5.5.2653.19)
Thanks. That's why they need to get all the facts in early on--such as look at innpact damage from the
spy telescope. Even then, we may not know the real effect of the damage.
The LaRC ditching model tests 20 some years ago showed that the Orbiter was the best ditching
shape that they had ever tested, of many. But, our structures people have said that if we ditch we
would blow such big holes in the lower panels that the orbiter might break up. Anyway, they refuse to
even consider water ditching any more--! still have the test results[ Bailout seems best.
[LaRC=Langley Research Center]
On the next day, Tuesday, Daugherty sent the following to Campbell.
Original Message
From: Robert H. Daugherty
Sent: Tuesday, January 28, 2003 12:39 PM
To: CAMPBELL, CARLISLE C, JR (JSC-ES2) (NASA)
Subject: Tile Damage
Any more activity today on the tile damage or are people just relegated to
crossing their fingers and hoping for the best?
See ya,
Bob
Campbell's reply:
Original Message
From: "CAMPBELL, CARLISLE C, JR (JSC-ES2) (NASA)"
To: "'Robert H. Daugherty'"
Subject: RE: Tile Damage
Date: Tue, 28 Jan 2003 13:29:58 -0600
X-Mailer: Internet Mail Service (5.5.2653.19)
I have not heard anything new. I'll let you know if I do.
COG
Carlisle Campbell sent the following e-mail to Johnson Space Center engineering managers on
January 31.
"In order to alleviate concerns regardin;^ the worst case scenario which could potentially
he caused by the debris impact under the Orbiter '.v left wing during launch, EG conducted
some landing simulations on the Ames Vertical Motion Simulator which tested the ability
of the crew and vehicle to sur\'ive a condition where two main gear tires are deflated before
landing. The results, although limited, showed that this condition is controllable, including
the nose slap down rates. These results may give MOD a different decision path should
this scenario become a reality. Previous opinions were that bailout was the only answer."
fEG=Aeroscience and F/ig/it Mechanics Divh'ion, tAOD=Mhsion Operations Directorate]
-^^-^^— Report Vquume I Aucsust ZGOS -^^^^^^————^——— 1 S 5
COLUMBIA
ACCIDENT INVESTIGATION BOARD
In the Mission Evaluation Room, a safety representative from Science Applications Interna-
tional Corporation. NASA's contract safety company, made a log entry at the Safety and Quality
Assurance console on January 28, at 12:15 p.m. It was only the second mention of the debris
strike in the safety console log during the mission (the first was also minor).
"[MCC SAJCJ called asking if any SR&QA people were involved in the deeision to say that
the aseent debris hit (left wing) is safe. [SAIC engineer] has indeed been involved in the
analysis and stated that he eoimtrs with the analysis. Details about the debris hit are found
in the Flight Da\ 12 MER Manager and our Daily Report. " fMCC=Mission Control Center,
SA/C=Science Applications International Corporation, SR&QA=Safety, Reliabilify, and Quality As-
surance, MER=Mission Evaluation Room]
Missed Opportunity 8
According to a Memorandum for the Record written by William Readdy, Associate Administra-
tor for Sp'iice Flight. Readdy and Michael Card, from NASA's Safety and Mission Assurance
Office, discussed an offer of Department of Defense imagery support for Columbia. This Janu-
ary 29. conversation ended with Readdy telling Card that NASA would accept the offer but
because the Mission Management Team had concluded that this was not a safety -of-flight issue,
the imagery should be gathered only on a low priority "not-to-interfere" basis. Ultimately, no
imagery was taken.
The Board notes that at the January 31 , Mission Management Team meeting, there was only a
minor mention of the debris strike. Other issues discussed included onboard crew consumables,
the status of the leaking water separator, an intercom anomaly, SPACEHAB water flow rates,
an update of the status of onboard experiments, end-of-mission weight concerns, landing day
weather forecasts, and landing opportunities. The only mention of the debris strike was a brief
comment by Bob Page, representing Kennedy Space Center's Launch Integration Office, who
stated that the crew's hand-held cameras and External Tank films would be expedited to Mar-
shall Space Flight Center via the Shuttle Training Aircraft for post-flight foam/debris imagery
analysis, per Linda Ham's request.
Summary: Mission Management Decision Making
Discovery and Initial Analysis of Debris Strike
In the course of examining film and video images oi Columbia's ascent, the Intercenter Photo
Working Group identified, on the day after launch, a large debris strike to the leading edge
of Columbia?, left wing. Alarmed at seeing so severe a hit so late in ascent, and at not hav-
ing a clear view of damage the strike might have caused, Intercenter Photo Working Group
members alerted senior Program managers by phone and sent a digitized clip of the strike
to hundreds of NASA personnel via e-mail. These actions initiated a contingency plan that
brought together an interdisciplinary group of experts from NASA, Boeing, and the United
Space Alliance to analyze the strike. So concerned were Intercenter Photo Working Group
personnel that on the day they discovered the debris strike, they tapped their Chair, Bob Page,
to see through a request to image the left wing with Department of Defense assets in anticipa-
tion of analysts needing these images to better determine potential damage. By the Board's
count, this would be the first of three requests to secure imagery of Columbia on-orbit during
the 16-day mission.
Imagery Requests
i. Flight Day 2. Bob Page, Chair, Intercenter Photo Working Group to Wayne Hale. .Shuttle Pro-
gram Manager for Launch Integration at Kennedy Space Center (in person).
2. Flight Day 6. Bob White, United Space Alliance manager, to Lambert Austin, head of the Space
Shuttle Systems Integration at Johnson Space Center (by phone).
3. Flight Day 6. Rodney Rocha, Co-Chair of Debris Assessment Team to Paul Shack, Manager,
Shuttle Engineering Office (by e-mail).
.| gg Report Volume I Auoust Z003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Missed Opportunities ■§
1. Flight Day 4. Rodney Rocha inquires if crew has been asked to inspect for damage. No re-
sponse.
2. Flight Day 6. Mission Control fails to ask crew member David Brow n to downlink video he took
of External Tank separation, which may have revealed missing bipod foam.
3. Flight Day 6. NASA and National Imagery and Mapping Agency personnel discuss possible
request for imagery. No action taken.
4. Flight Day 7. Wayne Hale phones Department of Defense representative, who begins identify-
ing imaging assets, only to be stopped per Linda Ham's orders.
5. Flight Day 7. Mike Card, a NASA Headquarters manager from the Safety and Mission Assur-
ance Office, discusses imagery request with Mark Emtinger. Johnson Space Center Safety and
Mission Assurance. No action taken.
6. Flight Day 7. Mike Card discusses imagery request with Br>'an O'Connor. Associate Adminis-
trator for Safety and Mission Assurance. No action taken.
7. Flight Day 8. Barbara Conte. after discussing imagery request with Rodney Rocha. calls LeRoy
Cain, the STS-107 ascent/entry Flight Director Cain checks with Phil Engelauf. and then deliv-
ers a "no" answer.
8. Flight Day 14. Michael Card, from NASA's Safety and Mission Assurance Office, discusses the
imaging request with William Readdy. Associate Administrator for Space Flight. Readdy directs
that imagery should only be gathered on a "not-to-interfere" basis. None wtts forthcoming.
Upon learning of the debris strike on Flight Day Two. the responsible system area manager
from United Space Alliance and her NASA counterpart formed a team to analyze the debris
strike in accordance with mission rules requiring the careful examination of any '"out-of-fam-
ily" event. Using film from the Intercenter Photo Working Group, Boeing systems integration
analysts prepared a preliminary analysis that afternoon. (Initial estimates of debris size and
speed, origin of debris, and point of impact would later prove remarkably accurate.)
As Flight Day Three and Four unfolded over the Martin Luther King Jr. holiday weekend, en-
gineers began their analysis. One Boeing analyst used Crater, a mathematical prediction tool,
to assess possible damage to the Thermal Protection System. Analysis predicted tile damage
deeper than the actual tile depth, and penetration of the RCC coating at impact angles above
15 degrees. This suggested the potential for a burn-through during re-entry. Debris Assessment
Team members judged that the actual damage would not be as severe as predicted because of
the inherent conservatism in the Crater model and because, in the case of tile. Crater does not
take into account the tile's stronger and more impact-resistant "densified" layer, and in the
case of RCC, the lower density of foam would preclude penetration at impact angles under 21
degrees.
On Flight Day Five, impact assessment results for tile and RCC were presented at an informal
meeting of the Debris Assessment Team, which was operating without direct Shuttle Program
or Mission Management leadership. Mission Control's engineering support, the Mission Evalu-
ation Room, provided no direction for team activities other than to request the team's results
by January 24. As the problem was being worked. Shuttle managers did not formally direct
the actions of or consult with Debris Assessment Team leaders about the team's assumptions,
uncertainties, progress, or interim results, an unusual circumstance given that NASA managers
are normally engaged in analyzing what they view as problems. At this meeting, participants
agreed that an image of the area of the wing in question was essential to refine their analysis and
reduce the uncertainties in their damage assessment.
Each member supported the idea to seek imagery from an outside source. Due in part to a lack
of guidance from the Mission Management Team or Mission Evaluation Room managers, the
Debris Assessment Team chose an unconventional route for its request. Rather than working
the request up the normal chain of command - through the Mission Evaluation Room to the
Mission Management Team for action to Mission Control - team members nominated Rodney
Rocha. the team's Co-Chair, to pursue the request through the Engineering Directorate at John-
son Space Center. As a result, even after the accident the Debris Assessment Team's request was
viewed by Shuttle Program managers as a non-critical engineering desire rather than a critical
operational need.
Report voi-ume I August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BDARD
When the team learned that the Mission Management Team was not pursuing on-orbit imag-
ing, members were concerned. What Debris Assessment Team members did not realize was
the negative response from the Program was not necessarily a direct and final response to their
official request. Rather, the "no" was in part a response to requests for imagery initiated by the
Intercenter Photo Working Group at Kennedy on Flight Day 2 in anticipation of analysts' needs
that had become by Flight Day 6 an actual engineering request by the Debris Assessment Team,
made informally through Bob White to Lambert Austin, and formally through Rodney Rocha's
e-mail to Paul Shack. Even after learning that the Shuttle Program was not going to provide the
team with imagery, some members sought information on how to obtain it anyway.
Debris Assessment Team members believed that imaging of potentially damaged areas was
necessary even after the January 24, Mission Management Team meeting, where they had re-
ported their results. Why they did not directly approach Shuttle Program managers and share
their concern and uncertainty, and why Shuttle Program managers claimed to be isolated from
engineers, are points that the Board labored to understand. Several reasons for this communica-
tions failure relate to NASA's interna! culture and the climate established by Shuttle Program
management, which are discussed in more detail in Chapters 7 and 8.
A Flawed Analysis
An inexperienced team, using a mathematical tool that was not designed to assess an impact
of this estimated size, performed the analysis of the potential effect of the debris impact. Cra-
ter was designed for "in-family" impact events and was intended for day-of-launch analysis
of debris) impacts. It was not intended for large projectiles like those observed on STS-107.
Crater initially predicted possible damage, but the Debris Assessment Team assumed, without
theoretical or experimental validation, that because Crater is a conservative tool - that is, it pre-
dicts more damage than will actually occur - the debris would stop at the tile's densified layer,
even though their experience did not involve debris strikes as large as STS-107's. Crater-like
equations were also used as part of the analysis to assess potential impact damage to the wing
leading edge RCC. Again, the tool was used for something other than that for which it was
designed; again, it predicted possible penetration; and again, the Debris Assessment Team used
engineering arguments and their experience to discount the results.
As a result of a transition of responsibility for Crater analysis from the Boeing Huntington
Beach facility to the Houston-based Boeing office, the team that conducted the Crater analyses
had been formed fairly recently, and therefore could be considered less experienced when com-
pared with the more senior Huntington Beach analysts. In fact, STS-107 was the first mission for
whicli they were solely responsible for providing analysis with the Crater tool. Though post-ac-
cident interviews suggested that the training for the Houston Boeing analysts was of high quality
and adequate in substance and duration, communications and theoretical understandings of the
Crater model among the Houston-based team members had not yet developed to the standard of
a more senior team. Due in part to contractual arrangements related to the transition, the Hous-
ton-based team did not take full advantage of the Huntington Beach engineers' experience.
At the January 24, Mission Management Team meeting at which the "no safety -of-flight" con-
clusion was presented, there was little engineering discussion about the assumptions made, and
how the results would differ if other assumptions were used.
Engineering solutions presented to management should have included a quantifiable range of
uncertainty and risk analysis. Those types of tools were readily available, routinely used, and
would have helped management understand the risk involved in the decision. Management, in
turn, should have demanded such information. The very absence of a clear and open discussion
of uncertainties and assumptions in the analysis presented should have caused management to
probe further.
Shuttle Program Management's Low Level of Concern
While the debris strike was well outside the activities covered by normal mission flight rules.
Mission Management Team members and Shuttle Program managers did not treat the debris
strike as an issue that required operational action by Mission Control. Program managers, from
Ron Dittemore to individual Mission Management Team members, had, over the course of the
Space Shuttle Program, gradually become inured to External Tank foam losses and on a funda-
1 6S ^^—————^.^———^ Report Volume I August 2003 —^-^—
COLUMBIA
ACCIDENT INVESTIGATION BOARD
mental level did not believe foam striking the vehicle posed a critical threat to the Orbiter. In
particular. Shuttle managers exhibited a belief that RCC panels are impervious to foam impacts.
Even after seeing the video of Coliinihia's debris impact, learning estimates of the size and
location of the strike, and noting that a foam strike with sufficient kinetic energy could cause
Thermal Protection System damage, management's level of concern did not change.
The opinions of Shuttle Program managers and debris and photo analysts on the potential
severity of the debris strike diverged early in the mission and continued to diverge as the mis-
sion progressed, making it increasingly difficult for the Debris Assessment Team to have their
concerns heard by those in a decision-making capacity. In the face of Mission managers" low
level of concern and desire to get on with the mission. Debris Assessment Team members had
to prove unequivocally that a safety-of-flight issue existed before Shuttle Program management
would move to obtain images of the left wing. The engineers found themselves in the unusual
position of having to prove that the situation was unsafe - a reversal of the usual requirement
to prove that a situation is safe.
Other factors contributed to Mission management's ability to resist the Debris Assessment
Team's concerns. A tile expert told managers during frequent consultations that strike damage
was only a maintenance-level concern and that on-orbit imaging of potential wing damage was
not necessary. Mission management welcomed this opinion and sought no others. This constant
reinforcement of managers' pre-existing beliefs added another block to the wall between deci-
sion makers and concerned engineers.
Another factor that enabled Mission management's detachment from the concerns of their own
engineers is rooted in the culture of N.ASA itself. The Board observed an unofficial hierarchy
among N.ASA programs and directorates that hindered the flow of communications. The effects
of this unofficial hierarchy are seen in the attitude that members of the Debris Assessment Team
held. Part of the reason they chose the institutional route for their imagery request was that
without direction from the Mission Evaluation Room and Mission Management Team, they felt
more comfortable with their own chain of command, which was outside the Shuttle Program.
Further, when asked by investigators why they were not more vocal about their concerns. De-
bris Assessment Team members opined that by raising contrary points of view about Shuttle
mission safety, they would be singled out for possible ridicule by their peers and managers.
A Lack of Clear Communication
Communication did not flow effectively up to or down from Program managers. As it became
clear during the mission that managers were not as concerned as others about the danger of the
foam strike, the ability of engineers to challenge those beliefs greatly diminished. Managers' ten-
dency to accept opinions that agree with their own dams the flow of effective communications.
After the accident. Program managers stated privately and publicly that if engineers had a safe-
ty concern, they were obligated to communicate their concerns to management. Managers did
not seem to understand that as leaders they had a corresponding and perhaps greater obligation
to create viable routes for the engineering community to express their views and receive infor-
mation. This barrier to communications not only blocked the flow of information to managers,
but it also prevented the downstream flow of information from managers to engineers, leaving
Debris Assessment Team members no basis for understanding the reasoning behind Mission
Management Team decisions.
The January 27 to January 3 1 , phone and e-mail exchanges, primarily between NASA engi-
neers at Langley and Johnson, illustrate another symptom of the "cultural fence" that impairs
open communications between mission managers and working engineers. These exchanges and
the reaction to them indicated that during the evaluation of a mission contingency, the Mission
Management Team failed to disseminate information to all system and technology experts who
could be consulted. Issues raised by two Langley and Johnson engineers led to the development
of "what-if landing scenarios of the potential outcome if the main landing gear door sustained
damaged. This led to behind-the-scenes networking by these engineers to use NASA facilities
to make simulation runs of a compromised landing configuration. These engineers - who un-
derstood their systems and related technology - saw the potential for a problem on landing and
ran it down in case the unthinkable occurred. But their concerns never reached the managers on
the Mission Management Team that had operational control over Coliiiiihia.
^-^——— Report Volume I August z a a 3 ^^.^^^^^^________^^^^^___ 16 9
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
A Lack of Effective Leadership
The Shuttle Program, the Mission Management Team, and through it the Mission Evaluation
Room, were not actively directing the efforts of the Debris Assessment Team. These manage-
ment teams were not engaged in scenario selection or discussions of assumptions and did not
actively seek status, inputs, or even preliminary results from the individuals charged with
analyzing the debris strike. They did not investigate the value of imagery, did not intervene to
consult the more experienced Crater analysts at Boeing's Huntington Beach facility, did not
probe the assumptions of the Debris Assessment Team's analysis, and did not consider actions
to mitigate the effects of the damage on re-entry. Managers' claims that they didn't hear the
engineers' concerns were due in part to their not asking or listening.
The Failure of Safety's Role
As will be discussed in Chapter 7, safety personnel were present but passive and did not serve
as a channel for the voicing of concerns or dissenting views. Safety representatives attended
meetings of the Debris Assessment Team, Mission Evaluation Room, and Mission Management
Team, but were merely party to the analysis process and conclusions instead of an independent
source of questions and challenges. Safety contractors in the Mission Evaluation Room were
only marginally aware of the debris strike analysis. One contractor did question the Debris As-
sessment Team safety representative about the analysis and was told that it was adequate. No
additional inquiries were made. The highest-ranking safety representative at NASA headquar-
ters deferred to Program managers when asked for an opinion on imaging of Cohimhia. The
safety manager he spoke to also failed to follow up.
Summary
Management decisions made during Columhias final flight reflect missed opportunities,
blocked or ineffective communications channels, flawed analysis, and ineffective leadership.
Perhaps most striking is the fact that management - including Shuttle Program. Mission Man-
agement Team, Mission Evaluation Room, and Flight Director and Mission Control - displayed
no interest in understanding a problem and its implications. Because managers failed to avail
themselves of the wide range of expertise and opinion necessaiy to achieve the best answer
to the debris strike question - "W/,s this a saf'ety-nf-fiii>ht coiiceni'.'" - some Space Shuttle
Program managers failed to fulfill the implicit contract to do whatever is possible to ensure the
safety of the crew. In fact, their management techniques unknowingly imposed barriers that
keptat bay both engineering concerns and dissenting views, and ultimately helped create "blind
spots" that prevented them from seeing the danger the foam strike posed.
Because this chapter has focused on key personnel who participated in STS-107 bipod foam
debris strike decisions, it is tempting to conclude that replacing them will solve all NASA's
problems. However, solving NASA's problems is not quite so easily achieved. Peoples' actions
are influenced by the organizations in which they work, shaping their choices in directions that
even they may not realize. The Board explores the organizational context of decision making
more fully in Chapters 7 and 8.
Findings
Intercenter Photo Working Group
F6.3-I The foam strike was first seen by the Intercenter Photo Working Group on the morn-
ing of Flight Day Two during the standard review of launch video and high-speed
photography. The strike was larger than any seen in the past, and the group was
concerned about possible damage to the Orbiter. No conclusive images of the strike
existed. One camera that may have provided an additional view was out of focus
because of an improperly maintained lens.
F6.3-2 The Chair of the Intercenter Photo Working Group asked management to begin the
process of getting outside imagery to help in damage assessment. This request, the
first of three, began its journey through the management hierarchy on Flight Day
Two.
F6.3-3 The Intercenter Photo Working Group distributed its first report, including a digitized
video clip and initial assessment of the strike, on Flight Day Two. This information
1 V □ — — — — ^^— ^^^-^^-^— — Report voi-ume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
was widely disseminated to NASA and contractor engineers, Siiuttle Program man-
agers, and Mission Operations Directorate personnel.
F6.3-4 Initial estimates of debris size, speed, and origin were remarkably accurate. Initial in-
formation available to managers stated that the debris originated in the left bipod area
of the External Tank, was quite large, had a high velocity, and stnick the underside of
the left wing near its leading edge. The report stated that the debris could have hit the
RCC or tile!
The Debris Assessment Team
F6.3-5 A Debris Assessment Team began forming on Flight Day two to analyze the impact.
Once the debris strike was categorized as "out of family" by United Space Alliance,
contractual obligations led to the Team being Co-Chaired by the cognizant contrac-
tor sub-system manager and her NASA counteipart. The team was not designated a
Tiger Team by the Mission Evaluation Room or Mission Management Team.
F6.3-6 Though the Team was clearly reporting its plans (and final results) through the Mis-
sion Evaluation Room to the Mission Management Team, no Mission manager ap-
peared to "own" the Team's actions. The Mission Management Team, through the
Mission Evaluation Room, provided no direction for team activities, and Shuttle
managers did not formally consult the Team's leaders about their progress or interim
results.
F6.3-7 During an organizational meeting, the Team discussed the uncertainty of the data
and the value of on-orbit imagery to "bound" their analysis. In its first official meet-
ing the next day, the Team gave its NASA Co-Chair the action to request imagery of
Colunihia on-orbit.
F6.3-8 The Team routed its request for imagery through Johnson Space Center's Engineer-
ing Directorate rather than through the Mission Evaluation Room to the Mission
Management Team to the Flight Dynamics Officer, the channel used during a mis-
sion. This routing diluted the urgency of their request. Managers viewed it as a non-
critical engineering desire rather than a critical operational need.
F6.3-9 Team members never realized that management's decision against seeking imagery
was not intended as a direct or final response to their request.
F6.3-10 The Team's assessment of possible tile damage was performed using an impact
simulation that was well outside Crater's test databa.se. The Boeing analyst was inex-
perienced in the use of Crater and the interpretation of its results. Engineers with ex-
tensive Themial Protection System expertise at Huntington Beach were not actively
involved in determining if the Crater results were properly inteipreted.
F6.3-1 1 Crater initially predicted tile damage deeper than the actual tile depth, but engineers
used their judgment to conclude that damage would not penetrate the densified layer
of tile. Similarly. RCC damage conclusions were based primarily on judgment and
experience rather than analysis.
F6.3-I2 For a variety of reasons, including management failures, communication break-
downs, inadequate imagery, inappropriate use of assessment tools, and flawed engi-
neering judgments, the damage assessments contained substantial uncertainties.
F6.3-I3 The assumptions (and their uncertainties) used in the analysis were never presented
or discussed in full to either the Mission Evaluation Room or the Mission Manage-
ment Team.
F6.3-14 While engineers and managers knew the foam could have struck RCC panels: the
briefings on the analysis to the Mission Evaluation Room and Mission Management
Team did not address RCC damage, and neither Mission Evaluation Room nor Mis-
sion Management Team managers asked about it.
Space Shuttle Program Management
F6.3-I5 There were lapses in leadership and communication that made it difficult for en-
gineers to raise concerns or understand decisions. Management failed to actively
engage in the analysis of potential damage caused by the foam strike.
F6.3-I6 Mission Management Team meetings occurred infrequently (five times during a 16
day mission), not every day, as specified in Shuttle Program management rules.
F6.3-17 Shuttle Program Managers entered the mission with the belief, recently reinforced
by the STS-1 13 Flight Readiness Review, that a foam strike is not a safety-of-flight
issue.
— ^— — Report Volume I august zoo3 ____^_^— — ^-^—— — — 1 V 1
COLUMBIA
ACCIOENT INVESTIGATIDN BOARD
F6.3- 1 8 After Program managers learned about the foam strike, their belief that it would not
be a problem was confirmed (early, and without analysis) by a trusted expert who was
readily accessible and spoke from "experience." No one in management questioned
this conclusion.
F6.3-I9 Managers asked "Who's reqiiestini; the photos'/" instead of assessing the merits of
the request. Management seemed more concerned about the staff following proper
channels (even while they were themselves taking informal advice) than they were
about the analysis.
F6.3-20 No one in the operational chain of command for STS-107 held a security clearance
that would enable them to understand the capabilities and limitations of National
imagei7 resources.
F6.3-2 1 Managers associated with STS-107 began investigating the implications of the foam
strike on the launch schedule, and took steps to expedite post-flight analysis.
F6.3-22 Program managers required engineers to prove that the debris strike created a safety-
of-flight issue: that is, engineers had to produce evidence that the system was unsafe
rather than prove that it was safe.
F6.3-23 In both the Mission Evaluation Room and Mission Management Team meetings over
the Debris Assessment Team's results, the focus was on the bottom line - was there
a safety-of-flight issue, or not? There was little discussion of analysis, assumptions,
issues, or ramifications.
Communication
F6.3-24 / Communication did not flow effectively up to or down from Program managers.
F6.3-25 Three independent requests for imagery were initiated.
F6.3-26 Much of Program managers" information came through informal channels, which
prevented relevant opinion and analysis from reaching decision makers.
F6.3-27 Program Managers did not actively communicate with the Debris Assessment Team.
Partly as a result of this, the Team went through institutional, not mission-related,
channels with its request for imagery, and confusion surrounded the origin of imag-
ery requests and their subsequent denial.
F6.3-28 Communication was stifled by the Shuttle Program attempts to find out who had a
"mandatory requirement" for imagery.
Safety Representative's Role
F6.3-29 Safety representatives from the appropriate organizations attended meetings of the
Debris Assessment Team, Mission Evaluation Room, and Mission Management
Team, but were passive, and therefore were not a channel through which to voice
concerns or dissenting views.
Recommendation:
R6.3-1 Implement an expanded training program in which the Mission Management Team
faces potential crew and vehicle safety contingences beyond launch and ascent.
These contingences should involve potential loss of Shuttle or crew, contain numer-
ous uncertainties and unknowns, and require the Mission Management Team to as-
semble and interact with support organizations across NASA/Contractor lines and in
various locations.
R6.3-2 Modify the Memorandum of Agreement with the National Imagery and Mapping
Agency (NIMA) to make the imaging of each Shuttle flight while on orbit a standard
requirement.
REPORT VDLUI
COLUMBIA
ACCIDENT INVESTIGATION BOARD
6.4 Possibility of Rescue or Repair
To put the decisions made during the tlight of STS-107 into
perspective, the Board asked NASA to determine if there
were options for the safe return of the STS-107 crew. In this
study. NASA was to assume that the extent of damage to the
leading edge of the left wing was detennined b\ national
imaging assets or by a spacewalk. NASA was then asked to
evaluate the possibility of;
1. Rescuing the STS-107 crew by launching Atlantis.
Atlaiiris would be hurried to the pad. launched, rendez-
vous with Coltinihia. and take on Coliinihia's crew for
a return. It was assumed that NASA would be willing
to expose Atlantis and its crew to the same possibil-
ity of External Tank bipod foam loss that damaged
Colitnihia.
2. Repairing damage to Columbia's wing on orbit. In the
repair scenario, astronauts would use onboard materi-
als to rig a temporar) fix. Some of Cohnnhia's cargo
might be jettisoned and a different re-entry profile
would be flown to lessen heating on the left wing lead-
ing edge. The crew would be prepared to bail out if the
wing structure was predicted to fail on landing.
In its study of these two options, NASA assumed the follow-
ing timeline. Following the debris strike discovery on Flight
Day Two, Mission Managers requested imagery by Flight
Day Three. That imagery was inconclusive, leading to a de-
cision on Flight Day Four to perform a spacewalk on Flight
Day Five. That spacewalk revealed potentially catastrophic
damage. The crew was directed to begin conserving con-
sumables, such as oxygen and water, and Shuttle managers
began around-the-clock processing of Atlantis to prepare it
for launch. Shuttle managers pursued both the rescue and the
repair options from Flight Day Six to Flight Day 26, and on
that day (February 10) decided which one to abandon.
The NASA team deemed this timeline realistic for sev-
eral reasons. First, the team determined that a spacewalk
to inspect the left wing could be easily accomplished. The
team then assessed how the crew could limit its use of con-
sumables to determine how long Coliiiuhia could stay in
orbit. The limiting consumable was the lithium hydroxide
canisters, which scrub from the cabin atmosphere the carbon
dioxide the crew exhales. After consulting with flight sur-
geons, the team concluded that by modifying crew activity
and sleep time carbon dioxide could be kept to acceptable
levels until Flight Day 30 (the morning of February 15). All
other consumables would last longer Oxygen, the next most
critical, would require the crew to return on Flight Day 31.
Repairing Damage On Orbit
The repair option (see Figure 6.4-1). while logistically vi-
able using existing materials onboard Columbia, relied on so
many uncertainties that NASA rated this option "high risk."
To complete a repair, the crew would perform a spacewalk to
fill an assumed 6-inch hole in an RCC panel with heavy met-
al tools, small pieces of titanium, or other metal scavenged
from the crew cabin. These heavy metals, which would help
protect the wing structure, would be held in place during
Figure 6.4-?. The speculative repair option would have sent astro-
nauts hanging over the payload bay door to reach the left wing
RCC panels using o ladder scavenged from the crew module.
re-enti7 by a water-filled bag that had turned into ice in the
cold of space. The ice and metal would help restore wing
leading edge geometry, preventing a turbulent airflow over
the wing and therefore keeping heating and bum-through
levels low enough for the crew to survive re-entry and bail
out before landing. Because the NASA team could not verify
that the repairs would survive even a modified re-entry, the
rescue option had a considerably higher chance of bringing
Columbia's crew back alive.
Rescuing the STS-107 Crew with Atlantis
Accelerating the processing of Atlantis for early launch and
rendezvous with Columbia was by far the most complex
task in the rescue scenario. On Columbia's Flight Day Four,
Atlantis was in the Orbiter Processing Facility at Kennedy
Space Center with its main engines installed and only 41
days from its scheduled March 1 launch. The Solid Rocket
Boosters were already mated with the External Tank in the
Vehicle Assembly Building. By working three around-the-
clock shifts seven days a week, Atlantis could be readied for
launch, with no necessary testing skipped, by February 10.
If launch processing and countdown proceeded smoothly,
this would provide a five-day window, from February 10
to February 15, in which Atlantis could rendezvous with
Columbia before Columbia's consumables ran out. Accord-
ing to records, the weather on these days allowed a launch.
Atlantis would be launched with a crew of four: a command-
Report Vouume I August 2003
Figure 6.4-2. The rescue option had Atlantis flower vehicle) rendezvousing with Columbia and ffie STS-107 crew transferring via ropes. Note
that the payload bay of Atlantis is empty except for the external airlock/docking adapter.
er, pilot, and two astronauts trained for spacewalks. In Janu-
ary, seven commanders, seven pilots, and nine spacewalk-
trained astronauts were available. During the rendezvous on
Atlantis's first day in orbit, the two Orbiters would maneuver
to face each other with their payload bay doors open (see
Figure 6.4-2). Suited Coliiinhici crew members would then
be transferred to Atlantis via spacewalks. AtUmtls would
return with four crew members on the flight deck and seven
in the mid-deck. Mission Control would then configure Co-
liiinhici for a de-orbit burn that would ditch the Orbiter in the
Pacific Ocean, or would have the Columbia crew take it to a
higher orbit for a possible subsequent repair mission if more
thorough repairs could be developed.
This rescue was considered challenging but feasible. To
succeed, it required problem-free processing oi Atlantis and
a flawless launch countdown. If Program managers had un-
derstood the threat that the bipod foam strike posed and were
able to unequivocally determine before Flight Day Seven
that there was potentially catastrophic damage to the left
wing, these repair and rescue plans would most likely have
been developed, and a rescue would have been conceivable.
For a detailed discussion of the rescue and repair options,
see Appendix D.13.
Findings:
F6.4-1
F6.4-2
The repair option, while logistically viable using
existing materials onboard Coliinihia, relied on so
many uncertainties that NASA rated this option
"high risk."
If Program managers were able to unequivocally
determine before Flight Day Seven that there
was potentially catastrophic damage to the left
wing, accelerated processing of Atlantis might
have provided a window in which Atlantis could
rendezvous with Coliiinhia before Columbia's
limited consumables ran out.
Recommendation:
R6.4-1 For missions to the International Space Station,
develop a practicable capability to inspect and
effect emergency repairs to the widest possible
range of damage to the Thennal Protection Sys-
tem, including both tile and Reinforced Carbon-
Carbon, taking advantage of the additional capa-
bilities available when near to or docked at the
International Space Station.
For non-Station missions, develop a comprehen-
sive autonomous (independent of Station) inspec-
tion and repair capability to cover the widest
possible range of damage scenarios.
Accomplish an on-orbit Thermal Protection
System inspection, using appropriate assets and
capabilities, early in all missions.
The ultimate objective should be a fully autono-
mous capability for all missions to address the
possibility that an International Space Station
mission fails to achieve the correct orbit, fails to
dock successfully, or is damaged during or after
undocking.
Report Voli
August 2003
^c^
I nnniin
tf\
wjimuuiuum
(f;;mmifiiiii i
IIIUIIIIII Ml h
mmiii mi '
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Endnotes for Chapter 6
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
"Space Shuttle Program Description and Requirements Baseline," NSTS-
07700, Volume X, Book 1. CAIB document CTF028-32643667
"External Tank End Item (CEI) Specification - Port 1," CPT01M09A,
contract NAS8 -30300, April 9, 1980, WBS 1.6.1.2 and 1.6.2.2.
"STS-1 Orbiter Final Mission Report, ' JSC-17378, August 1981, p. 85.
Discussed in Craig Covault, "Investigators Studying Shuttle Tiles, Aviation
Weefc & Space Technology, May 11, 1981, pg. 40.
Report of the Presidential Commission on the Space Shuffle Challenger
Accident, Volume V, 1986, pp. 1028-9, hearing section pp. 1845-1849.
"Orbiter Vehicle End Item Specification for the Space Shuttle System,
Part 1, Performance and Design Requirements," contract NAS9-20000,
November 7, 2002. CAIB documents CAB006-06440645 and CAB033-
20242971.
"Problem Reporting and Corrective Action System Requirements," NSTS-
08126, Revision H, November 22, 2000, Appendix C, Definitions, In
Family. CAIB document CTF044-28652894.
Ibid.
Ibid. .'
The umbilical wells are compartments on the underside of the Orbiter
where External Tank liquid oxygen and hydrogen lines connect. After the
Orbiters land, the umbilical well camera film is retrieved and developed.
NSTS-08126, Paragraph 3.4, Additional Requirements for In-Flight
Anomaly (IFA) Reporting.
Integrated Hazard Analysis INTG 037, "Degraded Functioning of
Orbiter TPS or Damage to the Windows Caused by SRB/ET Ablatives or
Debonded ET or SRB TPS."
Ibid.
Ibid.
During the flight of SIS- 11 2, the Intercenter Photo Working Group
speculated that a second debris strike occurred at 72 seconds, possibly
to the right wing. Although post-flight analysis showed that this did not
occur, the Board notes that the Intercenter Photo Working Group failed
to f>roperly inform the Mission Management Team of this strike, and
that the Mission Management Team subsequently failed to aggressively
address the event during flight.
"Safety and Mission Assurance Report for the STS-1 13 Mission, Pre-
Launch Mission Management Team Edition," Enterprise Safety and
Mission Assurance Division, November 7, 2002. CAIB Document
CTF024-00430061
Orbiter TPS damage numbers come from the Shuttle Flight Data and In-
Flight Anomaly List (JSC-19413).
CAIB Meeting Minutes, presentation and discussion on IFAs for STS-27
and STS-28, March 28, 2003, Houston, Texas.
"STS-27R Notional Space Transportation System Mission Report," NSTS-
23370, February 1989, p. 2.
CAIB Meeting Minutes, presentation and discussion on IFAs for STS-27
and STS-28, March 28, 2003, Houston, Texas.
Corrective Action Record, 27RF13, Closeout Report (no date). CAIB
document CTFOlO-20822107
"STS-27R OV-104 Orbiter TPS Damage Review Team Summary Report,"
Volume I, February 1989, TM-100355, p. 64. CAIB document CAB035-
02290303.
Ibid.
"In-Flight Anomaly: STS-35/ET-35," External Tank Flight Readiness
Report 3500.2.3/91. CAIB document CAB057-51185119.
STS-36 PRCB, IFA Closure Rationale for STS-35. CAIB document CAB029-
03620433.
Identified by MSEC in PRACA database as "not a safety of flight"
concern. Briefed ot post-STS-42 PRCB and STS-45 Flight Readiness
Review.
"STS-45 Space Shuttle Mission Report," NSTS-08275, Moy 1992, pg. 17
CAIB document CTF00300030006.
"STS-45 Space Shuttle Mission Report," NSTS-08275, May 1992. CAIB
document CTF003-00030006.
Both STS-56 and STS-58 post mission PRCBs discussed the debris events
and IFAs. Closeout rationole was based upon the events being considered
"in family" and "within experience base."
"Problem Reporting and Corrective Action System Requirements," NSTS-
08126, Revision H, November 22, 2000, Appendix C, Definitions, Out of
Family. CAIB document CTF044-28652894.
Post STS-87 PRCBD, S 062127, 18 Dec 1997
M. Elisabeth Pate-Cornell and Paul S. Fischbeck, "Risk Management
for the Tiles of the Space Shuttle," pp. 64-86, Interfaces 24, January-
February 1994. CAIB document CAB005-0141.
Letter to M. Elisabeth Pate-Cornell, Stanford University, from Benjamin
Buchbinder, Risk Management Program Manager, NASA, 10 May 1993.
CAIB document CAB038-36973698.
M. Elisabeth Pate-Cornell, "Follow-up on the Standard 1990 Study of the
Risk of Loss of Vehicle and Crew of the NASA Space Shuttle Due to Tile
Failure," Report to the Columbia Accident Investigation Board, 18 June
2003. CAIB document CAB006-00970104.
M. Litwinsk and G. Wilson, el al., "End-to-End TPS Upgrades Plan
for Space Shuttle Orbiter," February 1997; K. Hinkle and G. Wilson,
"Advancements in TPS," M&P Engineering, 22 October 1998.
Daniel B. Leiser, et ol., "Toughened Uni-piece Fibrous Insulation (TUFI)"
Patent #5,079,082, ^ Januory 1992.
Karrie Hinkle, "High Density Tile for Enhanced Dimensional Stability,"
Briefing to Space Shuttle Program, October 19, 1998. CAIB document
CAB033-32663280.
Doniel B. Leiser, "Present/Future Tile Thermal Protection Systems," A
presentation to the CAIB (Group 1), 16 May 2003.
John Kowal, "Orbiter Thermal Protection System (TPS) Upgrades." Space
Shuttle Upgrades Safety Panel Review, 10 February 2003.
"Problem Reporting and Corrective Action System Requirements,"
NSTS-08126, Revision H, November 22, 2000. CAIB document CTF044-
28652894.
Diane Vaughan, The Challenger Launch Decision: Risky Technology,
Culture, and Deviance at NASA (Chicago: University of Chicago Press,
1996).
Richard Feynman, Minority Report on Challenger, The Pleasure of
Finding Things Out, (New York: Perseus Publishing, 2002).
See Appendix D.17 Tiger Team Checklists.
Allen J. Richardson and A. H. McHugh, "Hypervelocity Impact
Penetration Equation for Metal By Multiple Regression Analysis,"
STR153, North American Aviation, Inc., March 1966.
Allen J. Richordson and J. C. Chou, "Correlation of TPS Tile Penetration
Equation & Impact Test Data," 3 March 1985.
"Review of Crater Program for Evaluating Impact Damage to Orbiter
TPS Tiles," presented at Boeing-Huntington Beach, 29 Apr 2003. CAIB
document CTF070-29492999.
J. L. Rand, "Impact Testing of Orbiter HRSI Tiles," Texas Engineering
Experiment Station Report (Texas A&M), 1979; Tests conducted by
NASA (D. Arabian) co. 1979.
Drew L. Goodlin, "Orbiter Tile Impact Testing, Final Report", SwRI Project
# 18-7503-005, March 5, 1999.
Allen J. Richardson, "Evaluation of Flight Experience & Test Results for
Ice Impaction on Orbiter RCC & ACC Surfaces," Rockwell International,
November 26, 1984.
Though this entry indicates that NASA contacted USSPACECOM, the
correct entity is USSTRATCOM. USSPACECOM ceased to exist in
October 2002.
Report v t
iT 2 00 3
Chapter 7
The Accident's
Organizational Causes
Many accident investigations maice the same mistake in
defining causes. They identify the widget that broke or mal-
functioned, then locate the person most closely connected
with the technical failure: the engineer who miscalculated
an analysis, the operator who missed signals or pulled the
wrong switches, the supervisor who failed to listen, or the
manager who made bad decisions. When causal chains are
limited to technical flaws and individual failures, the ensu-
ing responses aimed at preventing a similar event in the
future are equally limited: they aim to fix the technical prob-
lem and replace or retrain the individual responsible. Such
corrections lead to a misguided and potentially disastrous
belief that the underlying problem has been solved. The
Board did not want to make these errors. A central piece of
our expanded cause model involves NASA as an organiza-
tional whole.
Organizational Cause Statement
The organizational causes of this accident are rooted
in the Space Shuttle Program's history and culture,
including the original compromises that were re-
quired to gain approval for the Shuttle Program,
subsequent years of resource constraints, fluctuafing
priorities, schedule pressures, mischaracterizafions of
the Shuttle as operafional rather than developmental,
and lack of an agreed nafional vision. Cultural traits
and organizafional practices detrimental to safety
and reliability were allowed to develop, including:
reliance on past success as a subsfitute for sound
engineering pracfices (such as testing to understand
why systems were not performing in accordance with
requirements/specifications); organizational barriers
which prevented effecfive communication of crifical
safety informafion and stifled professional differences
of opinion; lack of integrated management across
program elements; and trie evolution of an informal
chain of command and decision-making processes
that operated outside the organization's rules.
Understanding Causes
In the Board's view, NASA's organizational culture and
structure had as much to do with this accident as the Exter-
nal Tank foam. Organizational culture refers to the values,
norms, beliefs, and practices that govern how an institution
functions. .At the most basic level, organizational culture
defines the assumptions that employees make as they can^y
out their work. It is a powerful force that can persist through
reorganizations and the reassignment of key personnel.
Given that today's risks in human space flight are as high
and the safety margins as razor thin as they have ever been,
there is little room for overconfidence. Yet the attitudes
and decision-making of Shuttle Program managers and
engineers during the events leading up to this accident were
clearly overconfident and often bureaucratic in nature. They
deferred to layered and cumbersome regulations rather than
the fundamentals of safety. The Shuttle Program's safety
culture is straining to hold together the vestiges of a once
robust systems safety program.
As the Board investigated the Columbia accident, it expected
to find a vigorous safety organization, process, and culture at
NASA, bearing little resemblance to what the Rogers Com-
mission identified as the ineffective "silent safety" system in
which budget cuts resulted in a lack of resources, personnel,
independence, and authority. NASA's initial briefings to the
Board on its safety programs espoused a risk-averse philoso-
phy that empowered any employee to stop an operation at the
mere glimmer of a problem. Unfortunately. NASA's views
of its safety culture in those briefings did not reflect reality.
Shuttle Program safety personnel failed to adequately assess
anomalies and frequently accepted critical risks without
qualitative or quantitative support, even when the tools to
provide more comprehensive assessments were available.
Similarly, the Board expected to find NASA's Safety and
Mission Assurance organization deeply engaged at every
1ST 2 a o 3
COLUMBIA
ACCIDENT INVESTIGATION 8DARD
level of Shuttle management: the Flight Readiness Review,
the Mission Management Team, the Debris Assessment
Team, the Mission Evaluation Room, and so forth. This
was not the case. In briefing after briefing, interview after
interview, NASA remained in denial: in the agency's eyes,
"there were no safety-of-flight issues," and no safety com-
promises in the long history of debris strikes on the Ther-
mal Protection System. The silence of Program-level safety
processes undermined oversight; when they did not speak
up, safety personnel could not fulfill their stated mission
to provide "checks and balances." A pattern of acceptance
prevailed throughout the organization that tolerated foam
problems without sufficient engineering justification for
doing so.
This chapter presents an organizational context for under-
standing the Columbia accident. Section 7.1 outlines a short
history of safety at NASA, beginning in the pre-Apollo era
when the agency reputedly had the finest system safety-
engineering programs in the world. Section 7.2 discusses
organizational theory and its importance to the Board's in-
vestigation, and Section 7.3 examines the practices of three
organizations that successfully manage high risk. Sections
7.4 and 7.5 look at NASA today and answer the question,
"How could NASA have missed the foam signal?" by high-
lighting the blind spots that rendered the Shuttle Program's
risk perspective myopic. The Board's conclusion and rec-
ommendations are presented in 7.6. (See Chapter 10 for a
discussion of the differences between industrial safety and
mission assurance/quality assurance.)
7.1 Organizational Causes: Insights from
History
NASA's organizational culture is rooted in history and tradi-
tion. From NASA's inception in 1958 to the Cludleiiiier ac-
cident in 1986, the agency's Safety, Reliability, and Quality
Assurance (SRQA) activities, "although distinct disciplines,"
were "typically treated as one function in the design, devel-
opment, and operations of NASA's manned space flight
programs."' Contractors and NASA engineers collaborated
closely to assure the safety of human space flight. Solid en-
gineering practices emphasized defining goals and relating
system performance to them; establishing and using decision
criteria; developing alternatives; modeling systems for analy-
sis; and managing operations.- Although a NASA Office of
Reliability and Quality Assurance existed for a short time
during the early 1960s, it was funded by the human space
flight program. By 1963, the office disappeared from the
agency's organization charts. For the next few years, the only
type of safety program that existed at NASA was a decentral-
ized "loose federation" of risk assessment oversight mn by
each program's contractors and the project offices at each of
the three Human Space Flight Centers.
Fallout from Apollo - 1967
In January 1967, months before the scheduled launch of
Apollo y, three astronauts died when a fire erupted in a
ground-test capsule. In response. Congress, seeking to
establish an independent safety organization to oversee
space flight, created the Aerospace Safety Advisory Panel
(ASAP). The ASAP was intended to be a senior advisory
committee to NASA, reviewing space flight safety studies
and operations plans, and evaluating ".systems procedures
and management policies that contribute to risk." The
panel's main priority was human space flight missions.^
Although four of the panel's nine members can be NASA
employees, in recent years few have served as members.
While the panel's support staff generally consists of full-
time NASA employees, the group technically remains an
independent oversight body.
Congress simultaneously mandated that NASA create sepa-
rate safety and reliability offices at the agency's headquar-
ters and at each of its Human Space Flight Centers and Pro-
grams. Overall safety oversight became the responsibility
of NASA's Chief Engineer. Although these offices were not
totally independent - their funding was linked with the very
programs they were supposed to oversee - their existence
allowed NASA to treat safety as a unique function. Until the
Challenger accident in 1986, NASA safety remained linked
organizationally and financially to the agency's Human
Space Flight Program.
ChaWenger - 1986
In the aftermath of the Challenger accident, the Rogers
Commission issued recommendations intended to remedy
what it considered to be basic deficiencies in NASA's safety
system. These recommendations centered on an underlying
theme; the lack of independent safety oversight at NASA.
Without independence, the Commission believed, the slate
of safety failures that contributed to the Challenger accident
- such as the undue influence of schedule pressures and the
flawed Flight Readiness process - would not be corrected.
"NASA should establish an Office of Safety, Reliability,
and Quality Assurance to be headed by an Associate Ad-
ministrator, reporting directly to the NASA Administrator,"
concluded the Commission. "It would have direct authority
for safety, reliability, and quality assurance throughout the
Agency. The office should be assigned the workforce to
ensure adequate oversight of its functions and should be
independent of other NASA functional and program respon-
sibilities" [emphasis added).
In July 1986, NASA Administrator James Fletcher created a
Headquarters Office of Safety, Reliability, and Quality As-
surance, which was given responsibility for all agency-wide
safety-related policy functions. In the process, the position of
Chief Engineer was abolished."* The new office's Associate
Administrator promptly initiated studies on Shuttle in-flight
anomalies, overtime levels, the lack of spare parts, and land-
ing and crew safety systems, among other issues." Yet NASA's
response to the Rogers Commission recommendation did not
meet the Commission's intent: the Associate .Administrator
did not have direct authority, and safety, reliability, and mis-
sion assurance activities across the agency remained depen-
dent on other programs and Centers for funding.
General Accounting Office Reviev/ - 1990
A 1990 review by the U.S. General Accounting Office
questioned the effectiveness of NASA's new safety organi-
Report VOI-l
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
zations in a report titled "Space Program Safety: Funding
for NASA's Safety Organizations Should Be Centralized."'"
The report concluded "NASA did not have an independent
and effective safety organization" [emphasis added]. Al-
though the safety organizational structure may have "ap-
peared adequate." in the late 1980s the space agency had
concentrated most of its efforts on creating an independent
safety office at NASA Headquarters. In contrast, the safety
offices at NASA's field centers "were not entirely indepen-
dent because they obtained most of their funds from activi-
ties whose safety-related performance they were responsible
for overseeing." The General Accounting Office worried
that "the lack of centralized independent funding may also
restrict the flexibility of center safety managers." It also
suggested "most NASA safety managers believe that cen-
tralized SRM&QA [Safety, Reliability. Maintainability and
Quality Assurance] funding would ensure independence."
NASA did not institute centralized funding in response to
the General Accounting Office report, nor has it since. The
problems outlined in 1990 persist to this day.
Space Flight Operations Contract - 1996
The Space Flight Operations Contract was intended to
streamline and modernize NASA's cumbersome contracting
practices, thereby freeing the agency to focus on research
and development (see Chapter 5). Yet its implementation
complicated issues of safety independence. A single contrac-
tor would, in principle, provide "oversight" on production,
safety, and mission assurance, as well as cost management,
while NASA maintained "insight" into safety and quality
assurance through reviews and metrics. Indeed, the reduc-
tion to a single primary contract simplified some aspects of
the NASA/contractor interface. However, as a result, e.\-
perienced engineers changed jobs. NASA grew dependent
on contractors for technical support, contract monitoring
requirements increased, and positions were subsequently
staffed by less experienced engineers who were placed in
management roles.
Collectively, this eroded NASA's in-house engineering
and technical capabilities and increased the agency's reli-
ance on the United Space Alliance and its subcontractors
to identify, track, and resolve problems. The contract also
involved substantial transfers of safety responsibility from
the government to the private sector; rollbacks of tens of
thousands of Government Mandated Inspection Points;
and vast reductions in NASA's in-house safety-related
technical expertise (see Chapter 10). In the aggregate, these
mid-1990s transformations rendered NASA's already prob-
lematic safety system simultaneously weaker and more
complex.
The effects of transitioning Shuttle operations to the Space
Flight Operations Contract were not immediately apparent
in the years following implementation. In November 1996,
as the contract was being implemented, the Aerospace
Safety Advisory Panel published a comprehensive contract
review, which concluded that the effort "to streamline the
Space Shuttle program has not inadvertently created unac-
ceptable flight or ground risks. "^ The Aerospace Safety Ad-
visory Panel's passing grades proved temporary.
Shuttle Independent Assessment Team - 1999
Just three years later, after a number of close calls, NASA
chartered the Shuttle Independent Assessment Team to
examine Shuttle sub-systems and maintenance practices
(see Chapter 5). The Shuttle Independent Assessment Team
Report sounded a stem warning about the quality of NASA's
Safety and Mission Assurance efforts and noted that the
Space Shuttle Program had undergone a massive change in
structure and was transitioning to "a slimmed down, con-
tractor-run operation."
The team produced several pointed conclusions: the Shuttle
Program was inappropriately iisin}> previous success as
a justification for accepting increased risk; the Shuttle
Program's ahilir\' to manage risk was being eroded "by the
desire to reduce costs;" the size and complexity of the Shut-
tle Program and NASA/contractor relationships demanded
better connnunication practices: NASA's safety and mission
assurance organization was not siifficientlx independent: and
"the workforce has received a conflicting message due to
the emphasis on achieving cost and staff reductions, and the
pressures placed on increasing scheduled fiights as a result
of the Space Station" [emphasis added].** The Shuttle Inde-
pendent Assessment Team found failures of communication
to flow up from the "shop floor" and down from supervisors
to workers, deficiencies in problem and waiver-tracking
systems, potential conflicts of interest between Program and
contractor goals, and a general failure to communicate re-
quirements and changes across organizations. In general, the
Program's organizational culture was deemed "too insular."'
NASA subsequently formed an Integrated Action Team to
develop a plan to address the recommendations from pre-
vious Program-specific assessments, including the Shuttle
Independent Assessment Team, and to formulate improve-
ments.'" In part this effort was also a response to program
missteps in the drive for efficiency seen in the "faster, better,
cheaper" NASA of the 1990s. The NASA Integrated Action
Team observed: "NASA should continue to remove commu-
nication barriers and foster an inclusive environment where
open comnunucation is the norm." The intent was to estab-
lish an initiative where "the importance of communication
and a culture of trust and openness permeate all facets of the
organization." The report indicated that "multiple processes
to get the messages across the organizational structure"
would need to be explored and fostered [emphasis added].
The report recommended that NASA solicit expert advice in
identifying and removing barriers, providing tools, training,
and education, and facilitating communication processes.
The Shuttle Independent Assessment Team and NASA Inte-
grated Action Team findings mirror those presented by the
Rogers Commission. The same communication problems
persisted in the Space Shuttle Program at the time of the
Columbia accident.
Space Shuttle Competitive Source
Task Force - 2002
In 2002, a I4-member Space Shuttle Competitive Task
Force supported by the RAND Corporation examined com-
Repdrt Vaut
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
petitive sourcing options for the Shuttle Program. In its final
report to NASA, the team highlighted several safety-related
concerns, which the Board shares:
• Flight and ground hardware and software are obsolete,
and safety upgrades and aging infrastructure repairs
have been deferred.
• Budget constraints have impacted personnel and re-
sources required for maintenance and upgrades.
• International Space Station schedules exert significant
pressures on the Shuttle Program.
• Certain mechanisms may impede worker anonymity in
reporting safety concerns.
• NASA does not have a truly independent safety function
with the authority to halt the progress of a critical mis-
sion element. "
Based on these findings, the task force suggested that an In-
dependent Safety Assurance function should be created that
would hold one of "three keys" in the Certification of Flight
Readiness process (NASA and the operating contractor
would hold the other two), effectively giving this function
the ability to stop any launch. Although in the Board's view
the "third key" Certification of Flight Readiness process is
not a perfect solution, independent safety and verification
functions are vital to continued Shuttle operations. This
independent function should possess the authority to shut
down the flight preparation processes or intervene post-
launch when an anomaly occurs.
7.2 Organizational Causes: Insights from
Theory
To develop a thorough understanding of accident causes and
risk, and to better interpret the chain of events that led to the
CdliiDihia accident, the Board turned to the contemporai-y
social science literature on accidents and risk and sought
insight from experts in High Reliability, Normal Accident,
and Organizational Theory.'- Additionally, the Board held a
forum, organized by the National Safety Council, to define
the essential characteristics of a sound safety program."
High Reliability Theory argues that organizations operating
high-risk technologies, if properly designed and managed,
can compensate for inevitable human shortcomings, and
therefore avoid mistakes that under other circumstances
would lead to catastrophic failures.'^ Normal Accident
Theory, on the other hand, has a more pessimistic view of
the ability of organizations and their members to manage
high-risk technology. Normal Accident Theory holds that
organizational and technological complexity contributes
to failures. Organizations that aspire to failure-free perfor-
mance are inevitably doomed to fail because of the inherent
risks in the technology they operate.'^ Normal Accident
models also emphasize systems approaches and systems
thinking, while the High Reliability model works from the
bottom up: if each component is highly reliable, then the
system will be highly reliable and safe.
Though neither High Reliability Theory nor Normal Ac-
cident Theory is entirely appropriate for understanding
this accident, insights from each figured prominently in the
Board's deliberation. Fundamental to each theory is the im-
portance of strong organizational culture and commitment to
building successful safely strategies.
The Board selected certain well-known traits from these
models to use as a yardstick to assess the Space Shuttle
Program, and found them particularly useful in shaping its
views on whether NASA's current organization of its Hu-
man Space Flight Program is appropriate for the remaining
years of Shuttle operation and beyond. Additionally, organi-
zational theory, which encompasses organizational culture,
structure, history, and hierarchy, is used to explain the
Coliinihia accident, and, ultimately, combines with Chapters
5 and 6 to produce an expanded explanation of the accident's
causes."' The Board believes the following considerations
are critical to understand what went wrong during STS-I()7.
They will become the central motifs of the Board's analysis
later in this chapter.
• Commitment to a Safety Culture: NASA's safety cul-
ture has become reactive, complacent, and dominated
by unjustified optimism. Over time, slowly and unin-
tentionally, independent checks and balances intended
to increase safety have been eroded in favor of detailed
processes that produce massive amounts of data and
unwarranted consensus, but little effective communica-
tion. Organizations that successfully deal with high-risk
technologies create and sustain a disciplined safety sys-
tem capable of identifying, analyzing, and controlling
hazards throughout a technology's life cycle.
• Ability to Operate in Both a Centralized and Decen-
tralized Manner: The ability to operate in a centralized
manner when appropriate, and to operate in a decentral-
ized manner when appropriate, is the hallmark of a
high-reliability organization. On the operational side,
the Space Shuttle Program has a highly centralized
structure. Launch commit criteria and flight rules gov-
ern every imaginable contingency. The Mission Control
Center and the Mission Management Team have very
capable decentralized processes to solve problems that
are not covered by such rules. The process is so highly
regarded that it is considered one of the best problem-
solving organizations of its type.'' In these situations,
mature processes anchor rules, procedures, and routines
to make the Shuttle Program's matrixed workforce
.seamless, at least on the surface.
Nevertheless, it is evident that the position one occupies
in this structure makes a difference. When supporting
organizations try to "push back" against centralized
Program direction - like the Debris Assessment Team
did during STS-107 - independent analysis gener-
ated by a decentralized decision-making process can
be stifled. The Debris Assessment Team, working in an
essentially decentralized format, was well-led and had
the right expertise to work the problem, but their charter
was "fuzzy," and the team had little direct connection
to the Mission Management Team. This lack of connec-
tion to the Mission Management Team and the Mi.ssion
Evaluation Room is the single most compelling reason
why communications were so poor during the debris
Report Voli
1ST 2 O O 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
assessment. In this case, the Shuttle Program was un-
able to simultaneously manage both the centralized and
decentralized systems.
• Importance of Communication: At every juncture
of STS-107. the Shuttle Program's structure and pro-
cesses, and therefore the managers in charge, resisted
new information. Early in the mission, it became clear
that the Program was not going to authorize imaging of
the Orbiter because, in the Program's opinion, images
were not needed. Overwhelming evidence indicates that
Program leaders decided the foam strike was merely a
maintenance problem long before any analysis had be-
gun. Every manager knew the party line: "we'll wait for
the analysis - no safety-of-flight issue expected." Pro-
gram leaders spent at least as much time making sure
hierarchical rules and processes were followed as they
did trying to establish why anyone would want a picture
of the Orbiter. These attitudes are incompatible with an
organization that deals with high-risk technology.
• Avoiding Oversimplification: The Columbia accident
is an unfortunate illustration of how NASA's strong
cultural bias and its optimistic organizational think-
ing undermined effective decision-making. Over the
course of 22 years, foam strikes were normalized to the
point where they were simply a "maintenance" issue
- a concern that did not threaten a mission's success.
This oversimplification of the threat posed by foam
debris rendered the issue a low-level concern in the
minds of Shuttle managers. Ascent risk, so evident in
Cluilleiii^er. biased leaders to focus on strong signals
from the Shuttle System Main Engine and the Solid
Rocket Boosters. Foam strikes, by comparison, were
a weak and consequently overlooked signal, although
they turned out to be no less dangerous.
• Conditioned by Success: Even after it was clear from
the launch videos that foam had struck the Orbiter in a
manner never beft)re seen. Space Shuttle Program man-
agers were not unduly alarmed. They could not imagine
why anyone would want a photo of something that
could be fixed after landing. Mt)re importantly, learned
attitudes about foam strikes diminished management's
wariness of their danger. The Shuttle Program turned
"the experience of failure into the memory of suc-
cess.""* Managers also failed to develop simple con-
tingency plans for a re-entry emergency. They were
convinced, without study, that nothing could be done
about such an emergency. The intellectual curiosity and
skepticism that a solid safety culture requires was al-
most entirely absent. Shuttle managers did not embrace
safety-conscious attitudes. Instead, their attitudes were
shaped and reinforced by an organization that, in this in-
stance, was incapable of stepping back and gauging its
biases. Bureaucracy and process trumped thoroughness
and reason.
• Significance of Redundancy: The Human Space Flight
Program has compromised the many redundant process-
es, checks, and balances that should identify and correct
small errors. Redundant systems essential to every
high-risk enterprise have fallen victim to bureaucratic
efficiency. Years of workforce reductions and outsourc-
ing have culled from NASA's workforce the layers of
experience and hands-on systems knowledge that once
provided a capacity for safety oversight. Safety and
Mission Assurance personnel have been eliminated, ca-
reers in safety have lost organizational prestige, and the
Program now decides on its own how much safety and
engineering oversight it needs. .Aiming to align its in-
spection regime with the International Organization for
Standardization 9000/9001 protocol, commonly used in
industrial environments - environments vei7 different
than the Shuttle Program - the Human Space Flight
Program shifted from a comprehensive "oversight"
inspection process to a more limited "insight" process,
cutting mandatory inspection points by more than half
and leaving even fewer workers to make "second" or
"third" Shuttle systems checks (see Chapter 10).
Implications for the Shuttle Program Organization
The Board's investigation into the Columbia accident re-
vealed two major causes with which NASA has to contend:
one technical, the other organizational. As mentioned earlier,
the Board studied the two dominant theories on complex or-
ganizations and accidents involving high-risk technologies.
These schools of thought were influential in shaping the
Board's organizational recommendations, primarily because
each takes a different approach to understanding accidents
and risk.
The Board determined that high-reliability theory is ex-
tremely useful in describing the culture that should exist in
the human space flight organization. NASA and the Space
Shuttle Program must be committed to a strong safety
culture, a view that serious accidents can be prevented, a
willingness to learn from mistakes, from technology, and
from others, and a realistic training program that empowers
employees to know when to decentralize or centralize prob-
lem-solving. The Shuttle Program cannot afford the mindset
that accidents are inevitable because it may lead to unneces-
sarily accepting known and preventable risks.
The Board believes normal accident theory has a key role
in human spaceflight as well. Complex organizations need
specific mechanisms to maintain their commitment to safety
and assist their understanding of how complex interactions
can make organizations accident-prone. Organizations can-
not put blind faith into redundant warning systems because
they inherently create more complexity, and this complexity
in turn often produces unintended system interactions that
can lead to failure. The Human Space Flight Program must
realize that additional protective layers are not always the
best choice. The Program must also remain sensitive to the
fact that despite its best intentions, managers, engineers,
safety professionals, and other employees, can. when con-
fronted with extraordinary demands, act in counterproduc-
tive ways.
The challenges to failure-free performance highlighted by
these two theoretical approaches will always be present in
an organization that aims to send humans into space. What
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
can the Program do about these difficulties? The Board con-
sidered three alternatives. First, the Board could recommend
that NASA follow traditional paths to improving safety by
making changes to policy, procedures, and processes. These
initiatives could improve organizational culture. The analy-
sis provided by experts and the literature leads the Board
to conclude that although reforming management practices
has certain merits, it also has critical limitations. Second, the
Board could recommend that the Shuttle is simply too risky
and should be grounded. As will be discussed in Chapter
9, the Board is committed to continuing human space ex-
ploration, and believes the Shuttle Program can and should
continue to operate. Finally, the Board could recommend a
significant change to the organizational structure that con-
trols the Space Shuttle Program's technology. As will be
discussed at length in this chapter's conclusion, the Board
believes this option has the best chance to successfully man-
age the complexities and risks of human space flight.
7.3 Organizational Causes: Evaluating Best
Safety Practices
Many of the principles of solid safety practice identified as
crucial by independent reviews of NASA and in accident
and risk literature are exhibited by organizations that, like
NASA, operate risky technologies with little or no margin
for error. While the Board appreciates that organizations
dealing with high-risk technology cannot sustain accident-
free performance indefinitely, evidence suggests that there
are effective ways to minimize risk and limit the number of
accidents.
in this section, the Board compares NASA to three specific
examples of independent safety programs that have strived
for accident-free performance and have, by and large,
achieved it: the U.S. Navy Submarine Flooding Prevention
and Recovery (SUBSAFE), Naval Nuclear Propulsion (Na-
val Reactors) programs, and the Aerospace Corporation's
Launch Verification Process, which supports U.S. Air Force
space launches.''' The safety cultures and organizational
stmcture of all three make them highly adept in dealing
with inordinately high risk by designing hardware and man-
agement systems that prevent seemingly inconsequential
failures from leading to major accidents. Although size,
complexity, and missions in these organizations and NASA
differ, the following comparisons yield valuable lessons for
the space agency to consider when re-designing its organiza-
tion to increase safety.
Navy Submarine and Reactor Safety Programs
Human space flight and submarine programs share notable
similarities. Spacecraft and submarines both operate in haz-
ardous environments, use complex and dangerous systems,
and perform missions of critical national significance. Both
NASA and Navy operational experience include failures (for
example, USS Thresher, USS Scorpion, Apollo I capsule
fire. Challenger, and Columbia). Prior to the Columbia mis-
hap. Administrator Sean O'Keefe initiated the NASA/Navy
Benchmarking Exchange to compare and contrast the pro-
grams, specifically in safety and mission assurance.-"
The Navy SUBSAFE and Naval Reactor programs exercise
a high degree of engineering discipline, emphasize total
responsibility of individuals and organizations, and provide
redundant and rapid means of communicating problems
to decision-makers. The Navy's nuclear safety program
emerged with its first nuclear-powered warship (USS Nau-
tilus), while non-nuclear SUBSAFE practices evolved from
from past flooding mishaps and philosophies first introduced
by Naval Reactors. The Navy lost two nuclear-powered
submarines in the 1960s - the USS Thresher in 1963 and
the Scorpion 1968 - which resulted in a renewed effort to
prevent accidents.-' The SUBSAFE program was initiated
just two months after the Thresher mishap to identify criti-
cal changes to submarine certification requirements. Until a
ship was independently recertified, its operating depth and
maneuvers were limited. SUBSAFE proved its value as a
means of verifying the readiness and safety of submarines,
and continues to do so today. -^
The Naval Reactor Program is a joint Navy/Department
of Energy organization responsible for all aspects of Navy
nuclear propulsion, including research, design, construction,
testing, training, operation, maintenance, and the disposi-
tion of the nuclear propulsion plants onboard many Naval
ships and submarines, as well as their radioactive materials.
Although the naval fleet is ultimately responsible for day-
to-day operations and maintenance, those operations occur
within parameters established by an entirely independent
division of Naval Reactors.
The U.S. nuclear Navy has more than 5,500 reactor years of
experience without a reactor accident. Put another way, nu-
clear-powered warships have steamed a cumulative total of
over 127 million miles, which is roughly equivalent to over
265 lunar roundtrips. In contrast, the Space Shuttle Program
has spent about three years on-orbit, although its spacecraft
have traveled some 420 million miles.
Naval Reactor success depends on several key elements:
• Concise and timely communication of problems using
redundant paths
• Insistence on airing minority opinions
• Formal written reports based on independent peer-re-
viewed recommendations from prime contractors
• Facing facts objectively and with attention to detail
• Ability to manage change and deal with obsolescence of
classes of warships over their lifetime
These elements can be grouped into several thematic cat-
egories:
• Communication and Action: Formal and informal
practices ensure that relevant personnel at all levels are
informed of technical decisions and actions that affect
their area of responsibility. Contractor technical recom-
mendations and government actions are documented in
peer-reviewed formal written correspondence. Unlike
NASA, PowerPoint briefings and papers for technical
seminars are not substitutes for completed staff work. In
addition, contractors strive to provide recommendations
1 B 2
Report Volume I
2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
based on a technical need, uninfluenced by headquarters
or its representatives. Accordingly, division of respon-
sibilities between the contractor and the Government
remain clear, and a system of checks and balances is
therefore inherent.
• Recurring Training and Learning From Mistakes:
The Naval Reactor Program has yet to experience a
reactor accident. This success is partially a testament
to design, but also due to relentless and innovative
training, grounded on lessons learned both inside and
outside the program. For example, since 1996. Naval
Reactors has educated more than 5,000 Naval Nuclear
Propulsion Program personnel on the lessons learned
from the Challenger accident.-' Senior NASA man-
agers recently attended the 143rd presentation of the
Naval Reactors seminar entitled "The Challenger Ac-
cident Re-examined." The Board credits NASA's inter-
est in the Navy nuclear community, and encourages the
agency to continue to learn from the mistakes of other
organizations as well as from its own.
• Encouraging Minority Opinions: The Naval Reactor
Program encourages minority opinions and "bad news."
Leaders continually emphasize that when no minority
opinions are present, the responsibility for a thorough
and critical examination falls to management. Alternate
perspectives and critical questions are always encour-
aged. In practice, NASA does not appear to embrace
these attitudes. Board interviews revealed that it is diffi-
cult for minority and dissenting opinions to percolate up
through the agency's hierarchy, despite processes like
the anonymous NASA Safety Reporting System that
supposedly encourages the airing of opinions.
• Retaining Knowledge: Naval Reactors uses many
mechanisms to ensure knowledge is retained. The Di-
rector serves a minimum eight-year term, and the pro-
gram documents the history of the rationale for every
technical requirement. Key personnel in Headquarters
routinely rotate into field positions to remain familiar
with every aspect of operations, training, maintenance,
development and the workforce. Current and past is-
sues are discussed in open forum with the Director and
immediate staff at "all-hands" informational meetings
under an in-house professional development program.
NASA lacks such a program.
• Worst-Case Event Failures: Naval Reactors hazard
analyses evaluate potential damage to the reactor plant,
potential impact on people, and potential environmental
impact. The Board identified NASA's failure to ad-
equately prepare for a range of worst-case scenarios as
a weakness in the agency's safety and mission assurance
training programs.
SUBSAFE
The Board observed the following during its study of the
Navy's SUBSAFE Program.
• SUBSAFE requirements are clearly documented and
achievable, with minimal "tailoring" or granting of
waivers. NASA requirements are clearly documented
but are also more easily waived.
• A separate compliance verification organization inde-
pendently assesses program management.-'' NASA's
Flight Preparation Process, which leads to Certification
of Flight Readiness, is supposed to be an independent
check-and-balance process. However, the Shuttle
Program's control of both engineering and safety com-
promises the independence of the Flight Preparation
Process.
• The submarine Navy has a strong safety culture that em-
phasizes understanding and learning from past failures.
NASA emphasizes safety as well, but training programs
are not robust and methods of learning from past fail-
ures are informal.
• The Navy implements extensive safety training based
on the Thresher and Scorpion accidents. NASA has not
focused on any of its past accidents as a means of men-
toring new engineers or those destined for management
positions.
• The SUBSAFE structure is enhanced by the clarity,
uniformity, and consistency of submarine safety re-
quirements and responsibilities. Program managers are
not permitted to "tailor" requirements without approval
from the organization with final authority for technical
requirements and the organization that verifies SUB-
SAFE's compliance with critical design and process
requirements.-"^
• The SUBSAFE Program and implementing organiza-
tion are relatively immune to budget pressures. NASA's
program structure requires the Program Manager posi-
tion to consider such issues, which forces the manager
to juggle cost, schedule, and safety considerations. In-
dependent advice on these issues is therefore inevitably
subject to political and administrative pressure.
• Compliance with critical SUBSAFE design and pro-
cess requirements is independently verified by a highly
capable centralized organization that also "owns" the
processes and monitors the program for compliance.
• Quantitative safety assessments in the Navy submarine
program are deterministic rather than probabilistic.
NASA does not have a quantitative, program-wide risk
and safety database to support future design capabilities
and assist risk assessment teams.
Comparing Navy Programs with NASA
Significant differences exist between NASA and Navy sub-
marine programs.
• Requirements Ownership (Technical Authority):
Both the SUBSAFE and Naval Reactors' organizational
Report Vdli
August 2003
COLUMBIA
ACCIDENT INVESTIGATION SDARO
approach separates the technical and funding authority
from program management in safety matters. The Board
believes this separation of authority of program man-
agers - who, by nature, must be sensitive to costs and
schedules - and "owners" of technical requirements and
waiver capabilities - who, by nature, are more sensitive
to safety and technical rigor - is crucial. In the Naval
Reactors Program, safety matters are the responsibility
of the technical authority. They are not merely relegated
to an independent safety organization with oversight
responsibilities. This creates valuable checks and bal-
ances for safety matters in the Naval Reactors Program
technical "requirements owner" community.
• Emphasis on Lessons Learned: Both Naval Reac-
tors and the SUBSAFE have "institutionalized" their
"lessons learned" approaches to ensure that knowl-
edge gained from both good and bad experience
is maintained in corporate memory. This has been
accomplished by designating a central technical au-
thority responsible for establishing and maintaining
functional technical requirements as well as providing
an organizational and institutional focus for capturing,
documenting, and using operational lessons to improve
future designs. NASA has an impressive history of
scientific discovery, but can learn much from the ap-
plication of lessons learned, especially those that relate
to future vehicle design and training for contingen-
cies. NASA has a broad Lessons Learned Information
System that is strictly voluntary for program/project
managers and management teams. Ideally, the Lessons
Learned Information System should support overall
program management and engineering functions and
provide a historical experience base to aid conceptual
developments and preliminary design.
The Aerospace Corporation
The Aerospace Corporation, created in 1960, operates as a
Federally Funded Research and Development Center that
supports the government in science and technology that is
critical to national security. It is the equivalent of a $500
million enterprise that supports U.S. Air Force planning,
development, and acquisition of space launch systems.
The Aerospace Cor{:)oration employs approximately 3,200
people including 2,200 technical staff (29 percent Doctors
of Philosophy, 41 percent Masters of Science) who conduct
advanced planning, system design and integration, verify
readiness, and provide technical oversight of contractors.'''
The Aerospace Corporation's independent launch verifica-
tion process offers another relevant benchmark for NASA's
safety and mission assurance program. Several aspects of
the Aerospace Corporation launch verification process and
independent mission assurance structure could be tailored to
the Shuttle Program.
Aerospace's primary product is a formal verification letter
to the Air Force Systems Program Office stating a vehicle
has been independently verified as ready for launch. The
verification includes an independent General Systems En-
gineering and Integration review of launch preparations by
Aerospace staff, a review of launch system design and pay-
load integration, and a review of the adequacy of flight and
ground hardware, software, and interfaces. This "concept-
to-orbit" process begins in the design requirements phase,
continues through the formal verification to countdown
and launch, and concludes with a post-flight evaluation of
events with findings for subsequent missions. Aerospace
Corporation personnel cover the depth and breadth of space
disciplines, and the organization has its own integrated en-
gineering analysis, laboratory, and test matrix capability.
This enables the Aerospace Corporation to rapidly transfer
lessons learned and respond to program anomalies. Most
importantly. Aerospace is uniquely independent and is not
subject to any schedule or cost pressures.
The Aerospace Corporation and the Air Force have found
the independent launch verification process extremely
valuable. Aerospace Corporation involvement in Air Force
launch verification has significantly reduced engineering er-
rors, resulting in a 2.9 percent "probability-of-failure" rate
for expendable launch vehicles, compared to 14.6 percent in
the commercial sector."
Conclusion
The practices noted here suggest that responsibility and au-
thority for decisions involving technical requirements and
safety should rest with an independent technical authority.
Organizations that successfully operate high-risk technolo-
gies have a major characteristic in common: they place a
premium on safety and reliability by structuring their pro-
grams so that technical and safety engineering organizations
own the process of determining, maintaining, and waiving
technical requirements with a voice that is equal to yet in-
dependent of Program Managers, who are governed by cost,
schedule and mission-accomplishment goals. The Naval
Reactors Program, SUBSAFE program, and the Aerospace
Corporation are examples of organizations that have in-
vested in redundant technical authorities and processes to
become highly reliable.
7.4 Organizational Causes:
A Broken Safety Culture
Perhaps the most perplexing question the Board faced
during its seven-month investigation into the Coliiinhia
accident was "How could NASA have missed the signals
the foam was sending?" Answering this question was a
challenge. The investigation revealed that in most cases,
the Human Space Flight Program is extremely aggressive in
reducing threats to safety. But we also know - in hindsight
- that detection of the dangers posed by foam was impeded
by "blind spots" in NASA's safety culture.
From the beginning, the Board witnessed a consistent lack
of concern nboul the debris strike on Coliinihia. NASA man-
agers told the Board "there was no safety-of-flight issue"
and "we couldn't have done anything about it anyway." The
investigation uncovered a troubling pattern in which Shuttle
Program management made erroneous assumptions about
the robustness of a system based on prior success rather than
on dependable engineering data and rigorous testing.
Report Voli
IGUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The Shuttle Program's complex structure erected barriers
to effective communication and its safety culture no longer
asks enough hard questions about risk. (Safety culture refers
to an organization's characteristics and attitudes - promoted
by its leaders and internalized by its members - that serve
to make safety the top priority.) In this context, the Board
believes the mistakes that were made on STS-107 are not
isolated failures, but are indicative of systemic flaws that
existed prior to the accident. Had the Shuttle Program ob-
served the principles discussed in the previous two sections,
the threat that foam posed to the Orbiter, particularly after
the STS-112 and STS-107 foam strikes, might have been
more fully appreciated by Shuttle Program management.
In this section, the Board examines the NASA's safety
policy, structure, and process, communication barriers, the
risk assessment systems that govern decision-making and
risk management, and the Shuttle Program's penchant for
substituting analysis for testing.
NASA's Safety: Policy, Structure, and Process
quarters and decentralized execution of safety programs at
the enterprise, program, and project levels. Headquarters
dictates what must be done, not how it should be done. The
operational premise that logically follows is that safety is the
responsibility of program and project managers. Managers
are subsequently given flexibility to organize safety efforts
as they see fit, while NASA Headquarters is charged with
maintaining oversight through independent surveillance and
assessment.-'* NASA policy dictates that .safety programs
should be placed high enough in the organization, and be
vested with enough authority and seniority, to "maintain
independence." Signals of potential danger, anomalies,
and critical infomiation should, in principle, surface in the
hazard identification process and be tracked with risk assess-
ments supported by engineering analyses. In reality, such a
process demands a more independent status than NASA has
ever been willing to give its safety organizations, despite the
recommendations of numerous outside experts over nearly
two decades, including the Rogers Commi.ssion (1986),
General Accounting Office ( 1990), and the Shuttle Indepen-
dent Assessment Team (2000).
Safety Policy
Safety Organization Structure
NASA's current philosophy for safety and mission assur-
ance calls for centralized policy and oversight at Head-
Center safety organizations that support the Shuttle Pro-
gram are tailored to the missions they perfonn. Johnson and
NASA Administrator
Issue:
Same Individual, 4 roles that
cross Center, Program and
Headquarters responsibilles
Result:
Failure of checks and balances
CodeM
Office of Space Flight AA
(Safety Advisorl
CodeQ
Sofety and Mission Assurance AA
Code Q MMT Letter
Deputy AA
ISS/SSP
JSC Center Director
Space Shuttle
SR & QA Manager
ISS Progrc
Manage
Space Shuttle
Progrom
Monager
Verbal Input
JSC SR SQA
Director
I JSC Organization
I Managers
SR & QA Director
'
I I I I I
Shuttle Element Managers
Endorse
Space Shuttle
S & MA Manage
Spoce Shuttle
Organization
Manogers
Space Shuttle
Division Chief
Independent
Assessment
Office
Funding via Integrated Task Agreements
United Space Alliance
Vice President SQ & MA
Responsibility
Policy/Advice
Figure 7.4-1. Independent safety checfcs and balance failure.
REPOBT vouui
IGUBT ZQoa
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Marshall Safety and Mission Assurance organizations are
organized similarly. In contrast, Kennedy has decentralized
its Safety and Mission Assurance components and assigned
them to the Shuttle Processing Directorate. This manage-
ment change renders Kennedy's Safety and Mission Assur-
ance structure even more dependent on the Shuttle Program,
which reduces effective oversight.
At Johnson, safety programs are centralized under a Direc-
tor who oversees five divisions and an Independent Assess-
ment Office. Each division has clearly-defined roles and
responsibilities, with the exception of the Space Shuttle
Division Chief, whose job description does not reflect the
full scope of authority and responsibility ostensibly vested
in the position. Yet the Space Shuttle Division Chief is em-
powered to represent the Center, the Shuttle Program, and
NASA Headquarters Safety and Mission Assurance at criti-
cal junctures in the safety process. The position therefore
represents a critical node in NASA's Safety and Mission As-
surance architecture that seems to the Board to be plagued
by conflict of interest. It is a single point of failure without
any checks or balances.
Johnson, also has a Shuttle Program Safety and Mission
Assurance Manager who oversees United Space Alliance's
safety organization. The Shuttle Program further receives
program safety support from the Center's Safety. Reliability,
and Quality Assurance Space Shuttle Division. Johnson's
Space Shuttle Division Chief has the additional role of
Shuttle Program Safety, Reliability, and Quality Assurance
Manager (see Figure 7.4-1). Over the years, this dual desig-
nation has resulted in a general acceptance of the fact that
the Johnson Space Shuttle Division Chief performs duties
on both the Center's and Program's behalf. The detached
nature of the support provided by the Space Shuttle Division
Chief, and the wide band of the position's responsibilities
throughout multiple layers of NASA's hierarchy, confuses
lines' of authority, responsibility, and accountability in a
manner that almost defies explanation.
A March 2001 NASA Office of Inspector General Audit
Report on Space Shuttle Program Management Safety Ob-
servations made the same point;
The job descriptions and responsibilities of the Space
Shuttle Program Manager and Chief, Johnson Safety
Office Space Shuttle Division, are nearly identical with
each official reporting to a different manager. This over-
lap in responsibilities conflicts with the SFOC [Space
Flight Operations Contract] and NSTS 07700, which
requires the Chief, Johnson Safety Office Space Shuttle
Division, to provide matrixed personnel support to the
Space Shuttle Program Safety Manager in fulfilling re-
quirements applicable to the safety, reliability, and qual-
ity assurance aspects of the Space Shuttle Program.
The fact that Headquarters, Center, and Program functions
are rolled-up into one position is an example of how a care-
fully designed oversight process has been circumvented and
made susceptible to conflicts of interest. This organizational
construct is unnecessarily bureaucratic and defeats NASA's
stated objective of providing an independent safety func-
tion. A similar argument can be made about the placement
of quality assurance in the Shuttle Processing Divisions at
Kennedy, which increases the risk that quality assurance
personnel will become too "familiar" with programs they are
charged to oversee, which hinders oversight and judgment.
The Board believes that although the Space Shuttle Program
has effective safety practices at the "shop floor" level, its
operational and systems safety program is flawed by its
dependence on the Shuttle Program. Hindered by a cumber-
some organizational structure, chronic understaffing, and
poor management principles, the safety apparatus is not
currently capable of fulfilling its mission. An independent
safety structure would provide the Shuttle Program a more
effective operational safety process. Crucial components of
this structure include a comprehensive integration of safety
across all the Shuttle programs and elements, and a more
independent system of checks and balances.
Safety Process
In response to the Rogers Commission Report, NASA es-
tablished what is now known as the Office of Safety and
Mission Assurance at Headquarters to independently moni-
tor safety and ensure communication and accountability
agency-wide. The Office of Safety and Mission Assurance
monitors unusual events like "out of family" anomalies
and establishes agency-wide Safety and Mission Assurance
policy. (An out-of-family event is an operation or perfor-
mance outside the expected performance range for a given
parameter or which has not previously been experienced.)
The Office of Safety and Mission Assurance also screens the
Shuttle Program's Flight Readiness Process and signs the
Certificate of Flight Readiness. The Shuttle Program Man-
ager, in turn, is responsible for overall Shuttle safety and is
supported by a one-person safety staff.
The Shuttle Program has been permitted to organize its
safety program as it sees fit, which has resulted in a lack of
standardized structure throughout NASA's various Centers,
enterprises, programs, and projects. The level of funding a
program is granted impacts how much safety the Program
can "buy" from a Center's safety organization. In turn. Safe-
ty and Mission Assurance organizations struggle to antici-
pate program requirements and guarantee adequate support
for the many programs for which they are responsible.
It is the Board's view, shared by previous assessments,
that the current safety system structure leaves the Office of
Safety and Mission Assurance ill-equipped to hold a strong
and central role in integrating safety functions. NASA Head-
quarters has not effectively integrated safety efforts across
its culturally and technically distinct Centers. In addition,
the practice of "buying" safety services establishes a rela-
tionship in which programs sustain the very livelihoods of
the safety experts hired to oversee them. These idiosyncra-
sies of structure and funding preclude the safety organiza-
tion from effectively providing independent safety analysis.
The commit-to-flight review process, as described in Chap-
ters 2 and 6. consists of program reviews and readiness polls
that are structured to allow NASA's senior leaders to assess
Report Volume 1
August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BDARO
mission readiness. In lii<e fashion, safety organizations affil-
iated with various projects, programs, and Centers at NASA,
conduct a Pre-iaunch Assessment Review of safety prepara-
tions and mission concerns. The Shuttle Program does not
officially sanction the Pre-iaunch Assessment Review, which
updates the Associate Administrator for Safety and Mission
Assurance on safety concerns during the Flight Readiness
Review/Certification of Flight Readiness process.
The Johnson Space Shuttle Safety. Reliability, and Quality
Assurance Division Chief orchestrates this review on behalf
of Headquarters. Note that this division chief also advises
the Shuttle Program Manager of Safety. Because it lacks
independent analytical rigor, the Pre-iaunch Assessment Re-
view is only marginally effective, in this an^angement. the
Johnson Shuttle Safety. Reliability, and Quality Assurance
Division Chief is expected to render an independent assess-
mentofhis own activities. Therefore, the Board is concerned
that the Pre-Launch Assessment Review is not an effective
check and balance in the Flight Readiness Review.
Given that the entire Safety and Mission Assurance orga-
nization depends on the Shuttle Program for resources and
simultaneously lacks the independent ability to conduct
detailed analyses, cost and schedule pressures can easily
and unintentionally influence safety deliberations. Structure
and process places Shuttle safety programs in the unenvi-
able position of having to choose between rubber-stamping
engineering analyses, technical efforts, and Shuttle program
decisions, or tr>'ing to carry the day during a committee
meeting in which the other side almost always has more
information and analytic capability.
NASA Barriers to Communication: Integration,
Information Systems, and Databases
By their very nature, high-risk technologies are exception-
ally difficult to manage. Complex and intricate, they consist
of numerous interrelated parts. Standing alone, components
may function adequately, and failure modes may be an-
ticipated. Yet when components are integrated into a total
system and work in concert, unanticipated interactions can
occur that can lead to catastrophic outcomes.-'' The risks
inherent in these technical systems are heightened when
they are produced and operated by complex organizations
that can also break down in unanticipated ways. The Shuttle
Program is such an organization. All of these factors make
effective communication - between individuals and between
programs - absolutely critical. However, the structure and
complexity of the Shuttle Program hinders communication.
The Shuttle Program consists of government and contract
personnel who cover an array of scientific and technical
disciplines and are affiliated with various dispersed space,
research, and test centers. NASA derives its organizational
complexity from its origins as much as its widely varied
missions. NASA Centers naturally evolved with different
points of focus, a "divergence" that the Rogers Commission
found evident in the propensity of Marshall personnel to
resolve problems without including program managers out-
side their Center - especially managers at Johnson, to whom
they officially reported (see Chapter 5).
Despite periodic attempts to emphasize safety, NASA's fre-
quent reorganizations in the drive to become more efficient
reduced the budget for safety, sending employees conflict-
ing messages and creating conditions more conducive to
the development of a conventional bureaucracy than to the
maintenance of a safety-conscious research-and-develop-
ment organization. Over time, a pattern of ineffective com-
munication has resulted, leaving risks improperly defined,
problems unreported, and concerns unexpressed.'" The
question is, why?
The transition to the Space Flight Operations Contract - and
the effects it initiated - provides part of the answer In the
Space Flight Operations Contract, NASA encountered a
completely new set of structural constraints that hindered ef-
fective communication. New organizational and contractual
requirements demanded an even more complex system of
shared management reviews, reporting relationships, safety
oversight and insight, and program information develop-
ment, dissemination, and tracking.
The Shuttle Independent Assessment Team's report docu-
mented these changes, noting that "the size and complexity
of the Shuttle system and of the NASA/contractor relation-
ships place extreme importance on understanding, commu-
nication, and information handling."" Among other findings,
the Shuttle Independent Assessment Team observed that:
• The current Shuttle program culture is too insular
• There is a potential for conflicts between contractual
and programmatic goals
• There are deficiencies in problem and waiver-tracking
systems
• The exchange of communication across the Shuttle pro-
gram hierarchy is structurally limited, both upward and
downward. '-
The Board believes that deficiencies in communication, in-
cluding those spelled out by the Shuttle Independent Assess-
ment Team, were a foundation for the Columbia accident.
These deficiencies are byproducts of a cumbersome, bureau-
cratic, and highly complex Shuttle Program structure and
the absence of authority in two key program areas that are
responsible for integrating information across all programs
and elements in the Shuttle program.
Integration Structures
NASA did not adequately prepare for the consequences of
adding organizational structure and process complexity in
the transition to the Space Flight Operations Contract. The
agency's lack of a centralized clearinghouse for integration
and safety further hindered safe operations. In the Board's
opinion, the Shuttle Integration and Shuttle Safety. Reli-
ability, and Quality Assurance Offices do not fully integrate
information on behalf of the Shuttle Program. This is due, in
pail, to an irregular division of responsibilities between the
Integration Office and the Orbiter Vehicle Enginecing Office
and the absence of a truly independent safety organization.
Within the Shuttle Program, the Orbiter Office handles many
key integration tasks, even though the Integration Office ap-
REPORT VOLUf
IQUST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
pears to be the more logical office to conduct them; the Or-
biter Office does not actively participate in the Integration
Control Board; and Orbiter Office managers are actually
ranked above their Integration Office counterparts. These
uncoordinated roles result in conflicting and erroneous
information, and support the perception that the Orbiter Of-
fice is isolated from the Integration Office and has its own
priorities.
The Shuttle Program's structure and process for Safety and
Mission Assurance activities further confuse authority and
responsibility by giving the Program's Safety and Mis-
sion Assurance Manager technical oversight of the safety
aspects of the Space Flight Operations Contract, while
simultaneously making the Johnson Space Shuttle Division
Chief responsible for advising the Program on safety per-
formance. As a result, no one office or person in Program
management is responsible for developing an integrated
risk assessment above the sub-system level that would pro-
vide a comprehensive picture of total program risks. The
net effect is that many Shuttle Program safety, quality, and
mission assurance roles are never clearly defined.
Safety Information Systems
Numerous reviews and independent assessments have
noted that NASA's safety system does not effectively man-
age risk. In particular, these reviews have observed that the
processes in which NASA tracks and attempts to mitigate
the risks po.sed by components on its Critical Items List is
flawed. The Post Challenger Evaluation of Space Shuttle
Risk Assessment and Management Report (1988) con-
cluded that:
The committee views NASA critical items list (CIL)
waiver decision-making process as being siihjective,
with little in the way of formal and consistent criteria
for approval or rejection of waivers. Waiver decisions
appear to he driven almost e.\:clusively hy the design
based Failure Mode Effects Analysis (FMEAj/CIL
retention rationale, rather than being based on an in-
tegrated assessment of all inputs to risk management.
The retention rationales appear biased toward proving
that the design is "safe, " sometimes ignoring signifi-
cant evidence to the contrary'.
The report continues, "... the Committee has not found an
independent, detailed analysis or assessment of the CIL
retention rationale which considers all inputs to the risk as-
sessment process."*' Ten years later, the Shuttle Independent
Assessment Team reported "Risk Management process ero-
sion created by the desire to reduce costs ..." '■* The Shuttle
Independent Assessment Team argued strongly that NASA
Safety and Mission Assurance should be restored to its pre-
vious role of an independent oversight body, and Safety and
Mission Assurance not be simply a "safety auditor."
The Board found similar problems with integrated hazard
analyses of debris strikes on the Orbiter. In addition, the
information systems supporting the Shuttle - intended to be
tools for decision-making - are extremely cumbersome and
difficult to use at anv level.
The following addresses the hazard tracking tools and major
databases in the Shuttle Program that promote risk manage-
ment.
• Hazard Analysis: A fundamental element of system
safety is managing and controlling hazards. NASA's
only guidance on hazard analysis is outlined in the
Methodology for Conduct of Space Shuttle Program
Hazard Analysis, which merely lists tcxils available.''
Therefore, it is not suiprising that hazard analysis pro-
cesses are applied inconsistently across systems, sub-
systems, assemblies, and components.
United Space Alliance, which is responsible for both
Orbiter integration and Shuttle Safety Reliability and
Quality Assurance, delegates hazard analysis to Boe-
ing. However, as of 2001, the Shuttle Program no
longer requires Boeing to conduct integrated hazard
analyses. Instead, Boeing now performs hazard analysis
only at the sub-system level. In other words, Boeing
analyzes hazards to components and elements, but is
not required to consider the Shuttle as a whole. Since
the current Failure Mode Effects Analysis/Critical Item
List process is designed for bottom-up analysis at the
component level, it cannot effectively support the kind
of "top-down" hazard analysis that is needed to inform
managers on nsk trends and identify potentially harmful
interactions between systems.
The Critical Item List (CIL) tracks 5.396 individual
Shuttle hazards, of which 4,222 are termed "Critical-
Space Shuhle Safety Upgrade
Program
NASA presented a Space Shuttle Safety Upgrade Initiative
to Congress as part of its Fiscal Year 2001 budget in March
2000. This initiative sought to create a "Pro-active upgrade
program to keep ShuUle flying safely and efficiently to 2012
and beyond to meet agency commitments and goals for hu-
man access to space."
The planned Shuttle safety upgrades included: Electric
Auxiliary Power Unit, Improved Main Landing Gear Tire,
Orbiter Cockpit/ Avionics Upgrades, Space Shuttle Main En-
gine Advanced Health Management System, Block HI Space
Shuttle Main Engine, Solid Rocket Booster Thrust Vector
Control/Auxiliary Power Unit Upgrades Plan, Redesigned
Solid Rocket Motor - Propellant Grain Geometry Modifica-
tion, and External Tank Upgrades - Friction Stir Weld. The
plan called tor the upgrades to be completed by 2008.
However, as discussed in Chapter 5, every proposed safety
upgrade - with a few exceptions - was either not approved
or was defeired.
The irony of the Space Shutde Safety Upgrade Program was
that the strategy placed emphasis on keeping the "Shuttle
flying safely and efficiendy to 2012 and beyond." yet the
Space Flight Leadership Council accepted the upgrades
only as long as they were financially feasible. Funding a
safely upgrade in order to fly safely, and then canceling it
for Inulgetary reasons, makes the concept of mission safety
rather hollow.
Report Volui
AUC3UST 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
ity 1/lR." Of those. 3,233 have waivers. CRIT I/IR
component failures are defined as those that will result
in loss of the Orbiter and crew. Waivers are granted
whenever a Critical Item List component cannot be
redesigned or replaced. More than 36 percent of these
waivers have not been reviewed in 10 years, a sign that
NASA is not aggressively monitoring changes in sys-
tem risk.
It is worth noting that the Shuttle's Thermal Protection
System is on the Critical Item List, and an existing haz-
ard analysis and hazard report deals with debris strikes.
As discussed in Chapter 6, Hazard Report #37 is inef-
fectual as a decision aid, yet the Shuttle Program never
challenged its validity at the pivotal STS-113 Flight
Readiness Review.
Although the Shuttle Program has undoubtedly learned
a great deal about the technological limitations inher-
ent in Shuttle operations, it is equally clear that risk
- as represented by the number of critical items list
and waivers - has grown substantially without a vigor-
ous effort to assess and reduce technical problems that
increase risk. An information system bulging with over
5,000 critical items and 3,200 waivers is exceedingly
difficult to manage.
• Hazard Reports: Hazard reports, written either by the
Space Shuttle Program or a contractor, document con-
ditions that threaten the safe operation of the Shuttle.
Managers use these reports to evaluate risk and justify
flight.''' During mission preparations, contractors and
Centers review all baseline hazard reports to ensure
they are current and technically correct.
Board investigators found that a large number of hazard
reports contained subjective and qualitative judgments,
such as "believed" and "based on experience from
previous flights this hazard is an 'Accepted Risk."" A
critical ingredient of a healthy safety program is the
rigorous implementation of technical standards. These
standards must include more than hazard analysis or
low-level technical activities. Standards must integrate
project engineering and management activities. Finally,
a mechanism for feedback on the effectiveness of sys-
tem safety engineering and management needs to be
built into procedures to learn if safety engineering and
management methods are weakening over time.
Dy.sfunctional Databases
In its investigation, the Board found that the information
systems that support the Shuttle program are extremely
cumbersome and difficult to use in decision-making at any
level. For obvious reasons, these shortcomings imperil the
Shuttle Program's ability to disseminate and share critical
information among its many layers. This section explores
the report databases that are crucial to effective risk man-
agement.
• Problem Reporting and Corrective Action: The
Problem Reporting and Corrective Action database
records any non-conformances (instances in which a
requirement is not met). Formerly, different Centers and
contractors used the Problem Reporting and Corrective
Action database differently, which prevented compari-
sons across the databa.se. NASA recently initiated an
effort to integrate these databases to permit anyone in
the agency to access information from different Centers.
This system. Web Program Compliance Assurance and
Status System (WEBPCASS). is supposed to provide
easier access to consolidated information and facilitates
higher-level searches.
However, NASA safety managers have complained that
the system is too time-consuming and cumbersome.
Only employees trained on the database seem capable
of using WEBPCASS effectively. One particularly
frustrating aspect of which the Board is acutely aware is
the database's waiver section. It is a critical information
source, but only the most expert users can employ it ef-
fectively. The database is also incomplete. For instance,
in the case of foam strikes on the Thermal Protection
System, only strikes that were declared "In-Fight
Anomalies" are added to the Problem Reporting and
Cort'ective Action database, which masks the full extent
of the foam debris trends.
• Lessons Learned Information System: The Lessons
Learned Information System database is a much simpler
system to use, and it can assist with hazard identification
and risk assessment. However, personnel familiar with
the Lessons Learned Information System indicate that
design engineers and mission assurance personnel use it
only on an ad hoc basis, thereby limiting its utility. The
Board is not the first to note such deficiencies. Numer-
ous reports, including most recently a General Account-
ing Office 2001 report, highlighted fundamental weak-
nesses in the collection and sharing of lessons learned
by program and project managers.''
Conclusions
Throughout the course of this investigation, the Board found
that the Shuttle Program's complexity demands highly ef-
fective communication. Yet integrated hazard reports and
risk analyses are rarely communicated effectively, nor are
the many databases used by Shuttle Program engineers and
managers capable of translating operational experiences
into effective risk management practices. Although the
Space Shuttle system has conducted a relatively small num-
ber of missions, there is more than enough data to generate
performance trends. As it is currently structured, the Shuttle
Program does not use data-driven safety methodologies to
their fullest advantage.
7.5 Organizational Causes: Impact of
A Flawed Safety Culture on STS-107
In this section, the Board examines how and why an array
of processes, groups, and individuals in the Shuttle Program
failed to appreciate the severity and implications of the
foam strike on STS-107. The Board believes that the Shuttle
Program should have been able to detect the foam trend and
REPOHT VOLl
August 20Q3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
more fully appreciate the danger it represented. Recall that
"safety culture" refers to the collection of characteristics and
attitudes in an organization - promoted by its leaders and in-
ternalized by its members - that makes safety an ovemding
priority. In the following analysis, the Board outlines short-
comings in the Space Shuttle Program, Debris Assessment
Team, and Mission Management Team that resulted from a
flawed safety culture.
Shuttle Program Shortcomings
The flight readiness process, which involves every organi-
zation affiliated with a Shuttle mission, missed the danger
signals in the history of foam loss.
Generally, the higher information is transmitted in a hierar-
chy, the more it gets "rolled-up," abbreviated, and simpli-
fied. Sometimes information gets lost altogether, as weak
signals drop from memos, problem identification systems,
and formal presentations. The same conclusions, repeated
over time, can result in problems eventually being deemed
non-problems. An extraordinary example of this phenom-
enon is how Shuttle Program managers assumed the foam
strike on STS-1 12 was not a warning sign (see Chapter 6).
During the STS-1 13 Flight Readiness Review, the bipod
foam strike to STS-1 12 was rationalized by simply restat-
ing earlier assessments of foam loss. The question of why
bipod foam would detach and strike a Solid Rocket Booster
spawned no further analysis or heightened curiosity; nor
did anyone challenge the weakness of External Tank Proj-
ect Manager's argument that backed launching the next
mission. After STS-I13's successful flight, once again the
STS- 1 1 2 foam event was not discussed at the STS- 1 07 Flight
Readiness Review. The failure to mention an outstanding
technical anomaly, even if not technically a violation of
NASA's own procedures, desensitized the Shuttle Program
to the dangers of foam striking the Thermal Protection Sys-
tem, and demonstrated just how easily the flight preparation
process can be compromised. In short, the dangers of bipod
foam got "rolled-up," which resulted in a missed opportuni-
ty to make Shuttle managers aware that the Shuttle required,
and did not yet have a fix for the problem.
Once the Coliinihia foam strike was discovered, the Mission
Management Team Chairperson asked for the rationale the
STS-1 13 Flight Readiness Review used to launch in spite
of the STS- 1 12 foam strike. In her e-mail, she admitted that
the analysis used to continue flying was, in a word, "lousy"
(Chapter 6). This admission - that the rationale to fly was
rubber-stamped - is, to say the least, unsettling.
The Flight Readiness process is supposed to be shielded
from outside influence, and is viewed as both rigorous and
systematic. Yet the Shuttle Program is inevitably influenced
by external factors, including, in the case of the STS- 107,
schedule demands. Collectively, such factors shape how
the Program establishes mission schedules and sets budget
priorities, which affects safety oversight, workforce levels,
facility maintenance, and contractor workloads. Ultimately,
external expectations and pressures impact even data collec-
tion, trend analysis, information development, and the re-
porting and disposition of anomalies. These realities contra-
dict NASA's optimistic belief that pre-flight reviews provide
true safeguards against unacceptable hazards. The schedule
pressure to launch International Space Station Node 2 is a
powerful example of this point (Section 6.2).
The premium placed on maintaining an operational sched-
ule, combined with ever-decreasing resources, gradually led
Shuttle managers and engineers to miss signals of potential
danger. Foam strikes on the Orbiter's Thermal Protec-
tion System, no matter what the size of the debris, were
"normalized" and accepted as not being a "safety-of-flight
risk." Clearly, the risk of Thennal Protection damage due to
such a strike needed to be better understood in quantifiable
terms. External Tank foam loss should have been eliminated
or mitigated with redundant layers of protection. If there
was in fact a strong safety culture at NASA, safety experts
would have had the authority to test the actual resilience of
the leading edge Reinforced Carbon-Carbon panels, as the
Board has done.
Debris Assessment Team Shortcomings
Chapter Six details the Debris Assessment Team's efforts to
obtain additional imagery of Columbia. When managers in
the Shuttle Program denied the team's request for imagery,
the Debris Assessment Team was put in the untenable posi-
tion of having to prove that a safety-of-flight issue existed
without the very images that would permit such a determina-
tion. This is precisely the opposite of how an effective safety
culture would act. Organizations that deal with high-risk op-
erations must always have a healthy fear of failure - opera-
tions must be proved safe, rather than the other way around.
NASA inverted this burden of proof.
Another crucial failure involves the Boeing engineers who
conducted the Crater analysis. The Debris Assessment Team
relied on the inputs of these engineers along with many oth-
ers to assess the potential damage caused by the foam strike.
Prior to STS- 107, Crater analysis was the responsibility of
a team at Boeing's Huntington Beach facility in California,
but this responsibility had recently been transferred to
Boeing's Houston office. In October 2002, the Shuttle Pro-
gram completed a risk assessment that predicted the move of
Boeing functions from Huntington Beach to Houston would
increase risk to Shuttle missions through the end of 2003.
because of the small number of experienced engineers who
were willing to relocate. To mitigate this risk, NASA and
United Space Alliance developed a transition plan to run
through .lanuary 2003.
The Board has discovered that the implementation of the
transition plan was incomplete and that training of replace-
ment personnel was not uniform. STS- 107 was the first
mission during which Johnson-based Boeing engineers
conducted analysis without guidance and oversight from
engineers at Huntington Beach.
Even though STS-107's debris strike was 400 times larger
than the objects Crater is designed to model, neither John-
son engineers nor Program managers appealed for assistance
from the more experienced Huntington Beach engineers.
REPORT VOl-Ut
AUBUST 2003
COLUMBIA
ACCIDENT INVESIIGATIDN BDARD
Engineering by Viewgraphs
The Debris Assessment Team presented its analysis in a formal
briefing to the Mission Evaluation Room that relied on Power-
Point slides from Boeing. When engineering analyses and risk
assessments are condensed to fit on a standard form or overhead
slide, information is inevitably lost. In the process, the prior-
ity assigned to information can be easily misrepresented by its
placement on a chart and the language that is used. Dr. Edward
Tufte of Yale University, an e.xpert in information presentation
who also researched communications failures in the Clicillenger
accident, studied how the slides used by the Debris Assessment
Team in their briefing to the Mission Evaluation Room misrep-
resented key information.'**
The slide created six levels of hierarchy, signified by the title
and the symbols to the left of each line. These levels prioritized
information that was already contained in 1 1 simple sentences.
Tufte also notes that the title is confusing. "Review of Test Data
Indicates Conservatism" refers not to the predicted tile damage,
but to the choice of test models used to predict the damage.
Only at the bottom of the slide do engineers state a key piece of
information; that one estimate of the debris that struck Columbia
was 640 times larger than the data used to calibrate the model on
which engineers based their damage assessments. (Later analy-
sis showed that the debris object was actually 400 times larger).
This difference led Tufte to suggest that a more appropriate
headline would be "Review of Test Data Indicates Irrelevance
of Two Models." '''
Tufte also criticized the sloppy language on the slide. "The
vaguely quantitative words 'significant" and 'significantly' are
used 5 times on this slide," he notes, "w ith de facto meanings
ranging from 'detectable in largely irrelevant calibration case
study' to 'an amount of damage so that everyone dies' to 'a dif-
ference of 640-fold.' " * Another example of sloppiness is that
"cubic inches" is written inconsistently: "3cu. In," "1920cu in,"
and "3 cu in." While such inconsistencies might seem minor, in
highly technical fields like aerospace engineering a misplaced
decimal point or mistaken unit of measurement can easily
engender inconsistencies and inaccuracies. In another phrase
"Test results do show that it is possible at sufficient mass and
velocity," the word "it" actually refers to "damage to the protec-
tive tiles."
As information gets passed up an organization hierarchy, from
people who do analysis to mid-level managers to high-level
leadership, key explanations and supporting information is fil-
tered out. In this context, it is easy to understand how a senior
manager might read this PowerPoint slide and not realize that it
addresses a life-threatening situation.
At many points during its investigation, the Board was sur-
prised to receive similar presentation slides from NASA offi-
cials in place of technical reports. The Board views the endemic
use of PowerPoint briefing slides instead of technical papers as
an illustration of the problematic methods of technical com-
munication at NASA.
The vaguely quanlitaiive words "significant" and
"significantly" are used 5 times on this slide, with tie fm-
meanings ranging from "detectable in largely irrelevant
calibration case study" lo "an amount of damage so that
everyone dies" to "a difference of 640-fold." None of
these 5 usages appears lo refer to the technical meaning
of "statistical significance."
i
Review Of Test Data Indicates Conservatism for Tile<
Penetration
The existing SOFI on tile test data used to create Crater
was reviewed along with STS-107 Southwest Research data
- Crater overpredicted penetration of t.le coating
significantly
• Initial penetration to described by normal velocity 4
• Vanes With volume/mass of pro]ectile(e g . 200ft/sec for
3cu In)
• Significant energy is required for the softer SOFlj
to penetrate the relatively hard tile 1
■ Test results do show thaQys-pOsslEie at sufficient mass
and velocity
• Conversely, once tile Is penetrated SOFI can cause
significant damage
. Minor vanations in total energy (above penetration level)
can cause significant tile damage
- Flight condition is significantly outside of test database
• Volume of ramp is 1920cu in vs 3 cu In for test
The low resolution of PowerPoint slides promotes
the use of compressed phrases like "Tile Penetration."
As is the case here, such phrases may well be ambiquous.
(The low resolution and large font generate 3 typographic
orphans, lonely words dangling on a seperale line.)
This vague pronoun reference "it" alludes 10 damafie
to the protective ;//fi. which caused the destruction of the
Columbia. The slide weakens important material with
ambiquous language (sentence fragments, passive voice,
multiple meanings of "significant"). The .1 reports
were created by engineers for high-level NASA officials
who were deciding whether the threat of wing damage
required further investigation before the Columbia
allcmpled return. The officials were satisfied that the
reports indicated that the Columbia was not in danger,
and no allenipts to further examine the threat were
made. The slides were pan of an oral presentation and
also were circulated as e-mail attachments.
In this slide the same unit of measure for volume
(cubic inches) is shown a different way every time
.^cu. in I920CU. in 3 cu. in
rather than in clear and tidy exponential form 1920 in'.
Perhaps the available font cannot show exponents.
Shakiness in units of measurement provokes concern.
Slides that use hierarchical bullet-outlines here do not
handle statistical data and scientific notation gracefully.
If PowerPoint is a corporate-mandated format for all
engineering reports, then some competent scientific
typography (rather than the PP market-pitch style) is
essential. In this slide, the typography is so choppy and
clunky thai il impedes understanding.
The analysis by Dr. Edward Tufte of f/ie slide from fhe Debris Assessmenf Team briefing. fSOFI=Sproy-On Foam /nsu/afionj
Repd«t Volume
AUBUST 2003
1 9 1
COLUMBIA
ACCIDENT INVESTIGATION BOARD
who might have cautioned against using Crater so far out-
side its validated limits. Nor did safety personnel provide
any additional oversight. NASA failed to connect the dots:
the engineers who misinterpreted Crater - a tool already
unsuited to the task at hand - were the very ones the Shuttle
Program identified as engendering the most risk in their
transition from Huntington Beach. The Board views this ex-
ample as characteristic of the greater turbulence the Shuttle
Program experienced in the decade before Cohimhia as a
result of workforce reductions and management reforms.
Mission Management Team Shortcomings
In the Board's view, the decision to fly STS-1 13 without a
compelling explanation for why bipod foam had separated
on ascent during the preceding mission, combined with the
low number of Mission Management Team meetings during
STS-1 07, indicates that the Shuttle Program had become
overconfident. Over time, the organization determined it did
not need daily meetings during a mission, despite regula-
tions that state otherwise.
Status update meetings should provide an opportunity to raise
concerns and hold discussions across structural and technical
boundaries. The leader of such meetings must encourage
participation and guarantee that problems are assessed and
resolved fully. All voices must be heard, which can be dif-
ficult when facing a hierarchy. An employee's location in the
hierarchy can encourage silence. Organizations interested in
safety must take steps to guarantee that all relevant informa-
tion is presented to decision-makers. This did not happen in
the meetings during the Cohimhia mission (.see Chapter 6).
For instance, e-mails from engineers at Johnson and Langley
conveyed the depth of their concern about the foam strike,
the questions they had about its implications, and the actions
they wanted to take as a follow-up. However, these e-mails
did not reach the Mission Management Team.
The failure to convey the urgency of engineering concerns
was caused, at least in part, by organizational structure and
spheres of authority. The Langley e-mails were circulated
among co-workers at Johnson who explored the possible ef-
fects of the foam .strike and its consequences for landing. Yet,
like Debris Assessment Team Co-Chair Rodney Rocha, they
kept their concerns within local channels and did not forward
them to the Mission Management Team. They were separated
from the decision-making process by distance and rank.
Similarly, Mission Management Team participants felt pres-
sured to remain quiet unless discussion turned to their par-
ticular area of technological or system expertise, and, even
then, to be brief. The initial damage assessment briefing
prepared for the Mission Evaluation Room was cut down
considerably in order to make it "fit" the schedule. Even so,
it took 40 minutes. It was cut down further to a three-minute
discussion topic at the Mission Management Team. Tapes of
STS-107 Mission Management Team sessions reveal a no-
ticeable "rush" by the meeting's leader to the preconceived
bottom line that there was "no safety-of- flight" issue (see
Chapter 6). Program managers created huge barriers against
dissenting opinions by stating preconceived conclusions
based on subjective knowledge and experience, rather than
on solid data. Managers demonstrated little concern for mis-
sion safety.
Organizations with strong safety cultures generally acknowl-
edge that a leader's best response to unanimous consent is to
play devil's advocate and encourage an exhaustive debate.
Mission Management Team leaders failed to seek out such
minority opinions. Imagine the difference if any Shuttle
manager had simply asked, "Prove to me that Columbia has
mn been harmed."
Similarly, organizations committed to effective communica-
tion seek avenues through which unidentified concerns and
dissenting insights can be raised, so that weak signals are
not lost in background noise. Common methods of bringing
minority opinions to the fore include hazard reports, sug-
gestion programs, and empowering employees to call "time
out" (Chapter 10). For these methods to be effective, they
must mitigate the fear of retribution, and management and
technical staff must pay attention. Shuttle Program hazard
reporting is seldom used, safety time outs are at times disre-
garded, and informal efforts to gain support are squelched.
The very fact that engineers felt inclined to conduct simulat-
ed blown tire landings at Ames "after hours," indicates their
reluctance to bring the concern up in established channels.
Safety Shortcomings
The Board believes that the safety organization, due to a
lack of capability and resources independent of the Shuttle
Program, was not an effective voice in discussing technical
issues or mission operations pertaining to STS-107. The
safety personnel present in the Debris Assessment Team,
Mission Evaluation Room, and on the Mission Management
Team were largely silent during the events leading up to the
loss of Columbia. That silence was not merely a failure of
safety, but a failure of the entire organization.
7.6 Findings and Recommendations
The evidence that supports the organizational causes also
led the Board to conclude that NASA's current organization,
which combines in the Shuttle Program all authority and
responsibility for schedule, cost, manifest, safety, technical
requirements, and waivers to technical requirements, is not
an effective check and balance to achieve safety and mission
assurance. Further, NASA's Office of Safety and Mission
Assurance does not have the independence and authority
that the Board and many outside reviews believe is neces-
sary. Consequently, the Space Shuttle Program does not
consistently demonstrate the characteristics of organizations
that effectively manage high risk. Therefore, the Board of-
fers the following Findings and Recommendations;
Findings:
F7.I-1
Throughout its history, NASA has consistently
struggled to achieve viable safety programs and
adjust them to the constraints and vagaries of
changing budgets. Yet. according to multiple high
level independent reviews. NASA's safety system
has fallen short of the mark.
Report Volui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION flDARO
F7.4-1
F7.4-2
R.4-3
R.4-4
F7.4-5
F7.4-6
F7.4-7
F7.4-8
F7.4-9
R.4-10
R.4-11
R.4-12
The Associate Administrator for Safety and Mis-
sion Assurance is not responsible for safety and
mission assurance execution, as intended by the F7.4-13
Rogers Commission, but is responsible for Safety
and Mission Assurance policy, advice, coordina-
tion, and budgets. This view is consistent with
NASA's recent philosophy of management at a
strategic level at NASA Headquarters but contrary
to the Rogers' Commission recommendation.
Safety and Mission Assurance organizations sup-
porting the Shuttle Program are largely dependent
upon the Program for funding, which hampers
their status as independent advisors.
Over the last two decades, little to no progress has
been made toward attaining integrated, indepen-
dent, and detailed analyses of risk to the Space R7.5-1
Shuttle system.
System safety engineering and management is
separated from mainstream engineering, is not
vigorous enough to have an impact on system de-
sign, and is hidden in the other safety disciplines
at NASA Headquarters.
Risk information and data from hazard analy.ses
are not communicated effectively to the risk as-
sessment and mission assurance processes. The
Board could not find adequate application of a
process, database, or metric analysis tool that
took an integrated, systemic view of the entire
Space Shuttle system.
The Space Shuttle Systems Integration Office
handles all Shuttle systems except the Orbiter.
Therefore, it is not a true integration office.
When the Integration Office convenes the Inte-
gration Control Board, the Orbiter Office usually
does not send a representative, and its staff makes
verbal inputs only when requested.
The Integration office did not have continuous
responsibility to integrate responses to bipod
foam shedding from various offices. Sometimes
the Orbiter Office had responsibility, sometimes
the External Tank Office at Marshall Space Flight
Center had responsibility, and sometime the bi-
pod shedding did not result in any designation of
an In-Flight Anomaly. Integration did not occur
NASA information databases such as The Prob-
lem Reporting and Corrective Action and the R7.5-2
Web Program Compliance Assurance and Status
System are marginally effective decision tools.
Senior Safety, Reliability & Quality Assurance
and element managers do not use the Lessons R7.5-3
Learned Information System when making de-
cisions. NASA subsequently does not have a
constructive program to use past lessons to edu-
cate engineers, managers, astronauts, or safety
personnel.
The Space Shuttle Program has a wealth of data
tucked away in multiple databases without a
convenient way to integrate and use the data for
management, engineering, or safety decisions.
The dependence of Safety, Reliability & Quality
Assurance personnel on Shuttle Program sup-
port limits their ability to oversee operations and
communicate potential problems throughout the
organization.
There are conflicting roles, responsibilities, and
guidance in the Space Shuttle safety programs.
The Safety & Mission Assurance Pre-Launch As-
.sessment Review process is not recognized by the
Space Shuttle Program as a requirement that must
be followed (NSTS 22778). Failure to consistent-
ly apply the Pre-Launch Assessment Review as a
requirements document creates confusion about
roles and responsibilities in the NASA safety or-
sanization.
Recommendations:
Establish an independent Technical Engineer-
ing Authority that is responsible for technical
requirements and all waivers to them, and will
build a disciplined, systematic approach to
identifying, analyzing, and controlling hazards
throughout the life cycle of the Shuttle System.
The independent technical authority does the fol-
lowing as a minimum:
• Develop and maintain technical standards
for all Space Shuttle Program projects and
elements
• Be the sole waiver-granting authority for
all technical standards
• Conduct trend and risk analysis at the sub-
system, system, and enterprise levels
• Own the failure mode, effects analysis and
hazard reporting systems
• Conduct integrated hazard analysis
• Decide what is and is not an anomalous
event
• Independently verify launch readiness
• Approve the provisions of the recertifica-
tion program called for in Recommenda-
tion R9. 1-1
The Technical Engineering Authority should be
funded directly from NASA Headquarters, and
should have no connection to or responsibility for
schedule or program cost.
NASA Headquarters Office of Safety and Mission
Assurance should have direct line authority over
the entire Space Shuttle Program safety organiza-
tion and should be independently resourced.
Reorganize the Space Shuttle Integration Office
to make it capable of integrating all elements of
the Space Shuttle Program, including the Orbiter.
Report voui
August 2003
1 9 3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Endnotes for Chapter 7
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
Sylvia Kramer, "History of NASA Safety Office from 1958-1980's,"
NASA History Division Record Collection, 1986, p. 1. CAIB document
CAB065-0358.
Ralph M. Miles Jr. "Introduction." In Ralph M. Miles Jr., editor, Sysfem
Concepts: Lectures on Contemporary Approaches to Systems, p. 1-12
(New York: John F. Wiley & Sons, 1973).
"The Aerospace Safety Advisory Panel, " NASA History Office, July 1,
1987, p. 1.
On Rodney's appointment, see NASA Management /nstruction 1103.39,
July 3, 1986, and NASA News July 8, 1986.
NASA Focts, "Brief Overview, Office of Safety, Reliability, Maintainability
and Quality Assurance," circa 1987.
"Space Program Safety: Funding for NASA's Safety Organizations
Should Be Centralized," General Accounting Office Report, NSIAD-90-
187, 1990.
"Aerospace Safety Advisory Panel Annual Report," 1996.
The quotes are from the Executive Summary of Notional Aeronautics
and Space Administration Space Shuttle Independent Assessment Team,
"Report to Associate Administrator, Office of Space Flight," October-
December 1999. CAIB document CTF017-0169.
Harry McDonald, "SIAT Space Shuttle Independent Assessment Team
Report."
NASA Chief Engineer and NASA Integrated Action Team, "Enhancing
Mission Success - A Framework for the Future," December 21, 2000.
The information in this section is derived from a briefing titled, "Draft
Final Report of the Space Shuttle Competitive Source Task Force," July
12, 2002. Mr. Liam Sorsfield briefed this report to NASA Headquarters.
Dr. Karl Weick, University of Michigan; Dr. Karlene Roberts, University of
Colifornia-Berkley; Dr. Howard McCurdy, American University; and Dr.
Diane Vaughan, Boston College.
Dr. David Woods, Ohio State University; Dr. Nancy G. Leveson,
Massachusetts Institute of Technology; Mr. James Wick, Intel
Corporation; Ms. Deboroh L. Grubbe, DuPonI Corporation; Dr. M. Sam
Monnan, Texas A&M University; Douglas A. Wiegmann, University of
Illinois at Urbona-Champoign; and Mr. Alan C. McMillan, President and
Chief Executive Officer, Notional Safety Council.
Todd R. La Porte and Paulo M. Consolini, "Working in Practice but Not in
Theory," Journal of Public Admmistration Research and Theory, 1 (1991)
pp. 19-47.
Scoff Sagan, The Limits of Safety (Princeton: Princeton University Press,
1995).
Dr. Diane Vaughan, Boston College; Dr. David Woods, Ohio State
University; Dr. Howard E. McCurdy, American University; Dr. Karl
E. Weick, University of Michigan; Dr. Karlene H. Roberts; Dr. M.
Elisabeth Pate-Cornell; Dr. Douglas A. Wiegmann, University of Illinois
at Urbano-Champoign; Dr. Nancy G. Leveson, Massachusetts Institute of
Technology; Mr. James Wick, Intel Corporation; Ms. Deborah L. Grubbe,
Dupont Corporation; Dr. M. Sam Mannon, Texas A&M University; and
Mr. Alan C. McMillan, President and Chief Executive Officer, National
Safety Council.
Dr. David Woods of Ohio State University speaking to the Board on Hind-
Sight Bios. April 28, 2003.
Sagan, The Limits of Safety, p. 258.
LoPorte and Consolini, "Working In Practice."
Notes from "NASA/Navy Benchmarking Exchange (NNBE), Interim
Report, Observations & Opportunities Concerning Navy Submarine
Program Safety Assurance," Joint NASA and Naval Sea Systems
Command NNBE Intorim Report, December 20, 2002.
Theodore Rockwell, The Rickover Effect, How One Man Made a
Difference. (Annapolis, Maryland: Naval Institute Press, 1992), p. 318.
Rockwell, fiiclcover, p. 320.
For more information, see Dr. Diane Vaughn, The Challenger Launch
Decision, Risky Technology, Culture, and Deviance at NASA (Chicago:
University of Chicago Press, 1996).
Presentation to the Board by Admiral Walter Contrell, Aerospace
Advisory Panel member, April 7, 2003.
Presentation to the Board by Admiral Walter Contrell, Aerospace
Advisory Panel member, April 7, 2003.
Aerospace's Launch Verification Process and its Contribution to Titan Risk
Management, Briefing given to Board, May 21, 2003, Mr. Ken Holden,
General Manager, Launch Verification Division.
Joe Tomei, "ELV Launch Risk Assessment Briefing," 3rd Government/
Industry Mission Assurance Forum, Aerospace Corporation, September
24, 2002.
NASA Policy Directive 8700.1 A, "NASA Policy for Safety and Mission
Success", Para l.b, 5.b(l), 5.e(l), and 5.f(l).
Charles B. Perrow. Normal Accidents (New York: Basic Books, 1984).
A. Shenhar, "Project management style and the space shuttle program
(part 2): A retrospective look," Project Management Journal, 23 (1 ), pp.
32-37.
Harry McDonald, "SIAT Space Shuttle Independent Assessment Team
Report."
Ibid.
"Post Challenger Evaluation of Space Shuttle Risk Assessment and
Monagement Report, Notional Academy Press 1988," section 5.1, pg.
40.
Harry McDonald, "SIAT Space Shuttle Independent Assessment Team
Report."
NSTS-22254 Rev B.
Ibid.
GAO Report, "Survey of NASA Lessons Learned," GAO-01-1015R,
September 5, 2001.
E. Tufte, Beautiful Evidence (Cheshire, CT: Graphics Press), [in press.]
Ibid., Edward R. Tufte, "The Cognitive Style of PowerPoint," (Cheshire,
CT: Graphics Press, May 2003).
Ibid.
Report Volume
August 2003
Chapter 8
History As Cause:
Columbia and Challenger
The Board began its investigation with two central ques-
tions about NASA decisions. Why did NASA continue to fly
with known foam debris problems in the years preceding the
Coliimhiu launch, and why did NASA managers conclude
that the foam debris strike 81.9 seconds into Columbia^
flight was not a threat to the safety of the mission, despite
the concerns of their engineers?
8.1 Echoes of Challenger
As the investigation progressed. Board member Dr. Sally
Ride, who also served on the Rogers Commission, observed
that there were "echoes" of Challeimer in Cohiiuhia. Ironi-
cally, the Rogers Commission investigation into Clialleniier
started with two remarkably similar central questions: Why
did NASA continue to fly with known O-ring erosion prob-
lems in the years before the Challeniier launch, and why, on
the eve of the Challenj^er launch, did NASA managers decide
that launching the mission in such cold temperatures was an
acceptable risk, despite the concerns of their engineers?
The echoes did not stop there. The foam debris hit was not
the single cause of the Columbia accident, just as the failure
of the joint seal that permitted O-ring erosion was not the
single cause of Clialleiiffer. Both Columbia and Challeniier
were lost also because of the failure of NASA's organiza-
tional system. Part Two of this report cites failures of the
three parts of NASA's organizational system. This chapter
shows how previous political, budgetary, and policy deci-
sions by leaders at the White House. Congress, and NASA
(Chapter 5) impacted the Space Shuttle Program's structure,
culture, and safety system (Chapter 7). and how these in turn
resulted in flawed decision-making (Chapter 6) for both ac-
cidents. The explanation is about system effects: how actions
taken in one layer of NASA's organizational system impact
other layers. History is not just a backdrop or a scene-setter
History is cause. History set the Columbia and Cluilleiii>er
accidents in motion. Although Part Two is separated into
chapters and sections to make clear what happened in the
political environment, the organization, and managers' and
engineers' decision-making, the three worked together. Each
is a critical link in the causal chain.
This chapter shows that both accidents were "failures of
foresight" in which history played a prominent role.' First,
the history of engineering decisions on foam and O-ring
incidents had identical trajectories that "normalized" these
anomalies, so that flying with these flaws became routine
and acceptable. Second. NASA history had an effect. In re-
sponse to White House and Congressional mandates. NASA
leaders took actions that created systemic organizational
flaws at the time of Challeniier that were also present for
Columbia. The final section compares the two critical deci-
sion sequences immediately before the loss of both Orbit-
ers - the pre-launch teleconference for Challeni>er and the
post-launch foam strike discussions for Columbia. It shows
history again at work: how past definitions of risk combined
with systemic problems in the NASA organization caused
both accidents.
Connecting the parts of NASA's organizational system and
drawing the parallels with Challeni>er demonstrate three
things. First, despite all the post-Challeniier changes at
NASA and the agency's notable achievements since, the
causes of the institutional failure responsible for Challeniier
have not been fixed. Second, the Board strongly believes
that if these persistent, systemic flaws are not resolved,
the scene is set for another accident. Therefore, the recom-
mendations for change are not only for fixing the Shuttle's
technical system, but also for fixing each part of the orga-
nizational system that produced Columbia's failure. Third,
the Board's focus on the context in which decision making
occurred does not mean that individuals are not responsible
and accountable. To the contrary, individuals always must
assume responsibility for their actions. What it does mean
is that NASA's problems cannot be solved simply by retire-
ments, resignations, or transferring personnel.-
The constraints under which the agency has operated
throughout the Shuttle Program have contributed to both
Report volume I Ausust Z003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Shuttle accidents. Although NASA leaders have played
an important role, these constraints were not entirely of
NASA's own making. The White House and Congress must
recognize the role of their decisions in this accident and take
responsibility for safety in the future.
8.2 Failures of Foresight: Two Decision
Histories and the Normalization of
Deviance
Foam loss may have occurred on all missions, and left bipod
ramp foam loss occurred on 10 percent of the flights for
which visible evidence exists. The Board had a hard time
understanding how, after the bitter lessons of Clnilleiif;cr.
NASA could have failed to identify a similar trend. Rather
than view the foam decision only in hindsight, the Board
tried to see the foam incidents as NASA engineers and man-
agers saw them as they made their decisions. This section
gives an insider perspective: how NASA defined risk and
how those definitions changed over time for both foam debris
hits and 0-ring erosion. In both cases, engineers and manag-
ers conducting risk assessments continually normalized the
technical deviations they found.' In all official engineering
analyse* and launch recommendations prior to the accidents,
evidence that the design was not performing as expected was
reinteipreted as acceptable and non-deviant, which dimin-
ished perceptions of risk throughout the agency.
The initial Shuttle design predicted neither foam debris
problems nor poor sealing action of the Solid Rocket Boost-
er joints. To experience either on a mission was a violation
of design specifications. These anomalies were signals of
potential danger, not something to be tolerated, but in both
cases after the first incident the engineering analysis con-
cluded that the design could tolerate the damage. These en-
gineers decided to implement a temporary fix and/or accept
the risk, and fly. For both 0-rings and foam, that first deci-
sion was a turning point. It established a precedent for ac-
cepting, rather than eliminating, these technical deviations.
As a result of this new classification, subsequent incidents of
O-ring erosion or foam debris strikes were not defined as
signals of danger, but as evidence that the design was now
acting as predicted. Engineers and managers incorporated
worsening anomalies into the engineering experience base,
which functioned as an elastic waistband, expanding to hold
larger deviations from the original design. Anomalies that
did not lead to catastrophic failure were treated as a .source
of valid engineering data that justified further flights. These
anomalies were translated into a safety margin that was ex-
tremely influential, allowing engineers and managers to add
incrementally to the amount and seriousness of damage that
was acceptable. Both O-ring erosion and foam debris events
were repeatedly "addressed" in NASA's Flight Readiness
Reviews but never fully resolved. In both cases, the engi-
neering analysis was incomplete and inadequate. Engineers
understood what was happening, but they never understood
why. NASA continued to implement a series of small correc-
tive actions, living with the problems until it was too late."*
. NASA documents show how official classifications of risk
were downgraded over time.^ Program managers designated
both the foam problems and O-ring erosion as "acceptable
risks" in Flight Readiness Reviews. NASA managers also
assigned each bipod foam event In-Ftight Anomaly status,
and then removed the designation as corrective actions
were implemented. But when major bipod foam-shedding
occurred on STS-1 12 in October 2002, Program manage-
ment did not assign an In-Flight Anomaly. Instead, it down-
graded the problem to the lower status of an "action" item.
Before Cluilleiiiier. the problematic Solid Rocket Booster
joint had been elevated to a Criticality 1 item on NASA's
Critical Items List, which ranked Shuttle components by
failure consequences and noted why each was an accept-
able risk. The joint was later demoted to a Criticality l-R
(redundant), and then in the month before Cluilleiii'er's
launch was "closed out" of the problem-reporting system.
Prior to both accidents, this demotion from high-risk item
to low-risk item was very similar, but with some important
differences. Damaging the Orbiter's Thermal Protection
System, especially its fragile tiles, was normalized even be-
fore Shuttle launches began: it was expected due to forces
at launch, orbit, and re-entry.'' So normal was replacement
of Thermal Protection System materials that NASA manag-
ers budgeted for tile cost and turnaround maintenance time
from the start.
It was a small and logical next step for the discovery of foam
debris damage to the tiles to be viewed by NASA as part of an
already existing maintenance problem, an assessment based
on experience, not on a thorough hazard analysis. Foam de-
bris anomalies came to be categorized by the reassuring
term "in-family," a formal classification indicating that new
occurrences of an anomaly were within the engineering ex-
perience base. "In-family" was a strange term indeed for a
violation of system requirements. Although "in-family" was
a designation introduced posX-Clnilleiif^er to separate prob-
lems by seriousness so that "out-of-family" problems got
more attention, by definition the problems that were shifted
into the lesser "in-family" category got less attention. The
Board's investigation uncovered no paper trail showing es-
calating concern about the foam problem like the one that
Solid Rocket Booster engineers left prior to Challeui'erP
So ingrained was the agency's belief that foam debris was
not a threat to flight safety that in press briefings after the
Coluinbia accident, the Space Shuttle Program Manager
still discounted the foam as a probable cause, saying that
Shuttle managers were "comfortable" with their previous
risk assessments.
From the beginning, NASA's belief about both these prob-
lems was affected by the fact that engineers were evaluat-
ing them in a work environment where technical problems
were nornial. Although management treated the Shuttle
as operational, it was in reality an experimental vehicle.
Many anomalies were expected on each mission. Against
this backdrop, an anomaly was not in itself a warning sign
of impending catastrophe. Another contributing factor was
that both foam debris strikes and O-ring erosion events were
examined separately, one at a time. Individual incidents
were not read by engineers as strong signals of danger
What NASA engineers and managers saw were pieces of ill-
structured problems.** An incident of O-ring erosion or foam
bipod debris would be followed by several launches where
the machine behaved properly, so that signals of danger
1 9 6
Report Volui
August 2aD3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
were followed by all-clear signals - in other words, NASA
managers and engineers were receiving mixed signals.''
Some signals defined as weak at the time were, in retrospect,
warnings of danger. Foam debris damaged tile was assumed
(erroneously) not to pose a danger to the wing. If a primary
0-ring failed, the secondary was assumed (erroneously)
to provide a backup. Finally, because foam debris strikes
were occurring frequently, like O-ring erosion in the years
before Clutlleimer, foam anomalies became routine signals
- a nomial part of Shuttle operations, not signals of danger.
Other anomalies gave signals that were strong, like sviring
malfunctions or the cracked balls in Ball Strut Tie Rod As-
semblies, which had a clear relationship to a "loss of mis-
sion." On those occasions, NASA stood down from launch,
sometimes for months, while the problems were corrected.
In contrast, foam debris and eroding O-rings were defined
as nagging issues of seemingly little consequence. Their
significance became clear only in retrospect, after lives had
been lost.
History became cause as the repeating pattern of anomalies
was ratified as safe in Flight Readiness Reviews. The official
definitions of risk assigned to each anomaly in Flight Readi-
ness Reviews limited the actions taken and the resources
spent on these problems. Two examples of the road not taken
and the devastating implications for the future occuned close
in time to both accidents. On the October 2002 launch of
STS-II2, a large piece of bipod ramp foam hit and dam-
aged the External Tank Attachment ring on the Solid Rocket
Booster skirt, a strong signal of danger 10 years after the last
known bipod ramp foam event. Prior to CludlcniU'r. there
was a comparable surprise. After a January 1985 launch, for
which the Shuttle sat on the launch pad for three consecutive
nights of unprecedented cold temperatures, engineers discov-
ered upon the Orbiter's return that hot gases had eroded the
primary and reached the secondary O-ring, blackening the
putty in between - an indication that the joint nearly failed.
But accidents are not always preceded by a wake-up call.'"
In 1983, engineers realized they needed data on the rela-
tionship between cold temperatures and O-ring erosion.
However, the task of getting better temperature data stayed
on the back burner because of the definition of risk: the
primary erosion was within the experience base; the sec-
ondary O-ring (thought to be redundant) was not damaged
and, significantly, there was a low probability that such cold
Florida temperatures would recur." The scorched putty, ini-
tially a strong signal, was redefined after analysis as weak.
On the eve of the Cluillen^er launch, when cold temperature
became a concern, engineers had no test data on the effect
of cold temperatures on O-ring erosion. Before Columbia.
engineers concluded that the damage from the STS-112
foam hit in October 2002 was not a threat to flight safety.
The logic was that, yes, the foam piece was large and there
was damage, but no serious consequences followed. Further,
a hit this size, like cold temperature, was a low-probability
event. After analysis, the biggest foam hit to date was re-
defined as a weak signal. Similar self-defeating actions and
inactions followed. Fngineers were again dealing with the
poor quality of tracking camera images of strikes during
ascent. Yet NASA took no steps to improve imagery and
took no immediate action to reduce the risk of bipod ramp
foam shedding and potential damage to the Orbiter before
Coliinihia. Furthermore, NASA performed no tests on what
would happen if a wing leading edge were struck by bipod
foam, even though foam had repeatedly separated from the
External Tank.
During the Challenger investigation, Rogers Commis-
sion member Dr. Richard Feynman famously compared
launching Shuttles with known problems to playing Russian
roulette.'- But that characterization is only possible in hind-
sight. It is not how NASA personnel perceived the risks as
they were being assessed, one launch at a time. Playing Rus-
sian roulette implies that the pLstol-holder realizes that death
might be imminent and still takes the risk. For both foam
debris and O-ring erosion, fixes were in the works at the time
of the accidents, but there was no rush to complete them be-
cause neither problem was defined as a show-stopper. Each
time an incident occuired, the Flight Readiness process
declared it safe to continue flying. Taken one at a time, each
decision seemed correct. The agency allocated attention and
resources to these two problems accordingly. The conse-
quences of living with both of these anomalies were, in its
view, minor. Not all engineers agreed in the months immedi-
ately preceding Cluillein^cr. but the dominant view at NASA
- the managerial view - was, as one manager put it, "we
were just eroding rubber O-rings," which was a low-cost
problem." The financial consequences of foam debris also
were relatively low: replacing tiles extended the turnaround
time between launches. In both cases, NASA was comfort-
able with its analyses. Prior to each accident, the agency saw
no greater consequences on the horizon.
8.3 System Effects: The Impact of History
AND Politics on Risky Work
The series of engineering decisions that normalized technical
deviations shows one way that history became cause in both
accidents. But NASA's own history encouraged this pattern
of flying with known flaws. Seventeen years separated the
two accidents. NASA Administrators, Congresses, and po-
litical administrations changed. However, NASA's political
and budgetary situation remained the same in principle as it
had been since the inception of the Shuttle Program. NASA
remained a politicized and vulnerable agency, dependent on
key political players who accepted NASA's ambitious pro-
posals and then imposed .strict budget limits. Po9.t-Cluillenf;-
er policy decisions made by the White House, Congress, and
NASA leadership resulted in the agency reproducing many
of the failings identified by the Rogers Commission. Policy
constraints affected the Shuttle Program's organization cul-
ture, its structure, and the structure t)f the safety system. The
three combined to keep NASA on its slippery slope toward
Challenger and Coliinihia. NASA culture allowed flying
with flaws when problems were defined as normal and rou-
tine; the structure of NASA's Shuttle Program blocked the
flow of critical information up the hierarchy, so definitions
of risk continued unaltered. Finally, a perennially weakened
safety system, unable to critically analyze and intervene, had
no choice but to ratify the existing risk assessments on these
two problems. The following comparison shows that these
system effects persisted through time, and affected engineer-
ing decisions in the years leading up to both accidents.
Report Volume I
iGueT 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The Board found that dangerous aspects of NASA's 1986
culture, identified by the Rogers Commission, remained
unchanged. The Space Shuttle Program had been built on
compromises hammered out by the White House and NASA
headquarters.'' As a result, NASA was transformed from a
research and development agency to more of a business,
with schedules, production pressures, deadlines, and cost
efficiency goals elevated to the level of technical innovation
and safety goals. '^ The Rogers Commission dedicated an
entire chapter of its report to production pressures."' More-
over, the Rogers Commission, as well as the 1990 Augus-
tine Committee and the 1999 Shuttle Independent Assess-
ment Team, criticized NASA for treating the Shuttle as if it
were an operational vehicle. Launching on a tight schedule,
which the agency had pursued as part of its initial bargain
with the White House, was not the way to operate what
was in fact an experimental vehicle. The Board found that
prior to Coluiiihia, a budget-limited Space Shuttle Program,
forced again and again to refashion itself into an efficiency
model because of repeated government cutbacks, was beset
by these same ills. The harmful effects of schedule pressure
identified in previous reports had returned.
Prior to both accidents, NASA was scrambling to keep up.
Not only were schedule pressures impacting the people
who worked most closely with the technology - techni-
cians, mission operators, flight crews, and vehicle proces-
sors - engineering decisions also were affected.'^ For foam
debris and O-ring erosion, the definition of risk established
during the Flight Readiness process determined actions
taken and not taken, but the schedule and shoestring bud-
get were equally influential. NASA was cutting corners.
Launches proceeded with incomplete engineering work on
these flaws. Cluillenger-Qra engineers were working on a
permanent fix for the booster joints while launches contin-
ued."* After the major foam bipod hit on STS-1 12, manage-
ment made the deadline for con'ective action on the foam
problem after the next launch, STS-1 13, and then slipped it
again until after the flight of STS-1 07. Delays for flowliner
and Ball Strut Tie Rod Assembly problems left no margin in
the schedule between February 2003 and the management-
imposed February 2004 launch date for the International
Space Station Node 2. Available resources - including time
out of the schedule for research and hardware modifications
- went to the problems that were designated as serious -
those most likely to bring down a Shuttle. The NASA
culture encouraged flying with flaws because the schedule
could not be held up for routine problems that were not de-
fined as a threat to mission safety."'
The question the Board had to answer was why, since the
foam debris anomalies went on for so long, had no one rec-
ognized the trend and intervened? The O-ring history prior
to Challenfier had followed the same pattern. This question
pointed the Board's attention toward the NASA organiza-
tion structure and the structure of its safety system. Safety-
oriented organizations often build in checks and balances
to identify and monitor signals of potential danger. If these
checks and balances were in place in the Shuttle Program,
they weren't working. Again, past policy decisions pro-
duced system effects with implications for both Clialleiii^er
and Coliniihia.
Prior to Challenger, Shuttle Program structure had hindered
information flows, leading the Rogers Commission to con-
clude that critical infonnation about technical problems was
not conveyed effectively through the hierarchy.'" The Space
Shuttle Program had altered its structure by outsourcing
to contractors, which added to communication problems.
The Commission recommended many changes to remedy
these problems, and NASA made many of them. However,
the Board found that those posl-Clialleniier changes were
undone over time by management actions.-' NASA ad-
ministrators, reacting to govenmient pressures, transferred
more functions and responsibilities to the private sector.
The change was cost-efficient, but personnel cuts reduced
oversight of contractors at the same time that the agency's
dependence upon contractor engineering judgment in-
creased. When high-risk technology is the product and lives
are at stake, safety, oversight, and communication flows are
critical. The Board found that the Shuttle Program's normal
chain of command and matrix system did not perform a
check-and-balance function on either foam or 0-rings.
The Flight Readiness Review process might have reversed
the disastrous trend of normalizing O-ring erosion and foam
debris hits, but it didn't. In fact, the Rogers Commission
found that the Flight Readiness process only affirmed the
\)ve.-Challenfier engineering risk assessments." Equally
troubling, the Board found that the Flight Readiness pro-
cess, which is built on consensus verified by signatures of
all responsible parties, in effect renders no one accountable.
Although the process was altered after Cluillenger, these
changes did not erase the basic problems that were built into
the structure of the Flight Readiness Review.-' Managers at
the top were dependent on engineers at the bottom for their
engineering analysis and risk assessments. Information was
lost as engineering risk analyses moved through the process.
At succeeding stages, management awareness of anomalies,
and therefore risks, was reduced either because of the need
to be increasingly brief and concise as all the parts of the
system came together, or because of the need to produce
consensus decisions at each level. The Flight Readiness
process was designed to assess hardware and take corrective
actions that would transfonn known problems into accept-
able flight risks, and that is precisely what it did. The 1986
House Committee on Science and Technology concluded
during its investigation into Challenger that Flight Readi-
ness Reviews had performed exactly as they were designed,
but that they could not be expected to replace engineering
analysis, and therefore they "cannot be expected to prevent
a flight because of a design flaw that Project management
had already determined an acceptable risk."" Those words,
true for the history of O-ring erosion, also hold true for the
history of foam debris.
The last line of defense against en'ors is usually a safety
system. But the previous policy decisions by leaders de-
scribed in Chapter ."i also impacted the safety structure
and contributed to both accidents. Neither in the O-ring
erosion nor the foam debris problems did NASA's safety
system attempt to reverse the course of events. In 1986,
the Rogers Commission called it "The Silent Safety Sys-
tem."-' Pre-Challenger budget shortages resulted in safety
personnel cutbacks. Without clout or independence, the
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BDARD
safety personnel who remained were ineffective. In the
case of Coliimhia. the Board found the same problems
were reproduced and for an identical reason: when pressed
for cost reduction. NASA attacked its own safety system.
The faulty assumption that supported this strategy prior to
Columbia was that a reduction in safety staff would not
result in a reduction of safety, because contractors would
assume greater safety responsibility. The effectiveness
of those remaining staff safety engineers was blocked by
their dependence on the very Program they were charged
to supervise. Also, the Board found many safety units with
unclear roles and responsibilities that left crucial gaps.
Post-Challeiiiier NASA still had no systematic procedure
for identifying and monitoring trends. The Board was sur-
prised at how long it took NASA to put together trend data
in response to Board requests for information. Problem
reporting and tracking systems were still overloaded or
underused, which undermined their very purpose. Mul-
tiple job titles disgui.sed the true extent of safety personnel
shortages. The Board found cases in which the same person
was occupying more than one safety position - and in one
instance at least three positions - which compromised any
possibility of safety organization independence because the
jobs were established w ith built-in conflicts of interest.
8.4 Organization, Culture, and
Unintended Consequences
A number of changes to the Space Shuttle Program structure
made in response to policy decisions had the unintended
effect of perpetuating dangerous aspects of prc-Cluilleiii^cr
culture and continued the pattern of normalizing things that
were not supposed to happen. At the same time that NASA
leaders were emphasizing the importance of safety, their
personnel cutbacks sent other signals. Streamlining and
downsizing, which scarcely go unnoticed by employees,
convey a message that efficiency is an important goal.
The Shuttle/Space Station partnership affected both pro-
grams. Working evenings and weekends just to meet the
intemational Space Station Node 2 deadline sent a signal
to employees that schedule is important. When paired with
the "faster, better, cheaper" NASA motto of the 1990s and
cuts that dramatically decreased safety personnel, efficiency
becomes a strong signal and safety a weak one. This kind of
doublespeak by top administrators affects people's decisions
and actions without them even realizing it.-"
Changes in Space Shuttle Program structure contributed to
the accident in a second important way. Despite the con-
straints that the agency was under, prior to both accidents
NASA appeared to be immersed in a culture of invincibility,
in stark contradiction to post-accident reality. The Rogers
Commission found a NASA blinded by its "Can-Do" atti-
tude,-" a cultural artifact of the Apollo era that was inappro-
priate in a Space Shuttle Program so strapped by schedule
pressures and shortages that spare parts had to be cannibal-
ized from one vehicle to launch another.-'* This can-do atti-
tude bolstered administrators" belief in an achievable launch
rate, the belief that they h?d an operational system, and an
unwillingness to listen to outside experts. The Aerospace
Safety and Advisory Panel in a 1985 report told NASA
that the vehicle was not operational and NASA should stop
treating it as if it were.-' The Board found that even after the
loss of Cluilleni>er, NASA was guilty of treating an experi-
mental vehicle as if it were operational and of not listening
to outside experts. In a repeat of the pre-Clialleni;er warn-
ing, the 1999 Shuttle Independent Assessment Team report
reiterated that "the Shuttle was not an 'operational' vehicle
in the usual meaning of the tenn.'"'" Engineers and program
planners were also affected by "Can-Do," which, when
taken too far, can create a reluctance to say that something
cannot be done.
How could the lessons of Cluilleii!^er have been forgotten
so quickly? Again, history was a factor. First, if success
is measured by launches and landings," the machine ap-
peared to be working successfully prior to both accidents.
Challenger was the 25th launch. Seventeen years and 87
missions passed without major incident. Second, previous
policy decisions again had an impact. NASA's Apollo-era
research and development culture and its prized deference
to the technical expertise of its working engineers was
overridden in the Space Shuttle era by "bureaucratic ac-
countability" - an allegiance to hierarchy, procedure, and
following the chain of command.*- Prior to Cluilleuger. the
can-do culture was a result not just of years of apparently
successful launches, but of the cultural belief that the Shut-
tle Program's many structures, rigorous procedures, and
detailed system of rules were responsible for those success-
es." The Board noted that the pK-Challeiiiier layers of pro-
cesses, boards, and panels that had produced a false sense of
confidence in the system and its level of safety returned in
full force prior to Coliinihia. NASA made many changes to
the Space Shuttle Program structure after Challenger. The
fact that many changes had been made supported a belief in
the safety of the system, the invincibility of organizational
and technical systems, and ultimately, a sense that the foam
problem was understood.
8.5 History as Cause: Two Accidents
Risk, uncertainty, and history came together when unprec-
edented circumstances arose prior to both accidents. For
Challeni^er, the weather prediction for launch time the next
day was for cold temperatures that were out of the engineer-
ing experience base. For Colitnihia. a large foam hit - also
outside the experience base - was discovered after launch.
For the first case, all the discussion was pre-launch; for
the second, it was post-launch. This initial difference de-
termined the shape these two decision sequences took, the
number of people who had information about the problem,
and the locations of the involved parties.
For Challeni>er, engineers at Morton-Thiokol," the Solid
Rocket Motor contractor in Utah, were concerned about
the effect of the unprecedented cold temperatures on the
rubber O-rings." Because launch was scheduled for the
next morning, the new condition required a reassessment of
the engineering analysis presented at the Flight Readiness
Review two weeks prior. A teleconference began at 8:45
p.m. Eastern Standard Time (EST) that included 34 people
in three locations: Morton-Thiokol in Utah. Marshall, and
Kennedy. Thiokol engineers were recommending a launch
delay. A reconsideration of a Flight Readiness Review risk
Volume I
(OUST 2003
COLUMBIA
ACCIDENT iNVESTIGATIDN BOARD
assessment the night before a launch was as unprecedented
as the predicted cold temperatures. With no ground rules or
procedures to guide their discussion, the participants auto-
matically reverted to the centralized, hierarchical, tightly
structured, and procedure-bound model used in Flight Read-
iness Reviews. The entire discussion and decision to launch
began and ended with this group of 34 engineers. The phone
conference linking them together concluded at 11:15 p.m.
EST after a decision to accept the risk and fly.
For Coliiiiihia. information about the foam debris hit was
widely distributed the day after launch. Time allowed for
videos of the strike, initial assessments of the size and speed
of the foam, and the approximate location of the impact to
be dispersed throughout the agency. This was the first de-
bris impact of this magnitude. Engineers at the Marshall,
Johnson, Kennedy, and Langley centers showed initiative
and jumped on the problem without direction from above.
Working groups and e-mail groups formed spontaneously.
The size of Johnson's Debris Assessment Team alone neared
and in some instances exceeded the total number of partici-
pants in the 1986 Challeni>er teleconference. Rather than a
tightly constructed exchange of information completed in a
few hours, time allowed for the development of ideas and
free-wheeling discussion among the engineering ranks. The
early post-launch discussion among engineers and all later
decision-making at management levels were decentralized,
loosely organized, and with little form. While the spontane-
ous and decentralized exchanging of information was evi-
dence that NASA's original technical culture was alive and
well, the diffuse form and lack of structm-e in the rest of the
proceedings would have several negative con.sequences.
In both situations, all new information was weighed and
interpreted against past experience. Formal categories and
cultural beliefs provide a consistent frame of reference in
which people view and interpret information and experi-
ences.* Pre-existing definitions of risk shaped the actions
taken and not taken. Worried engineers in 1986 and again
in 2003 found it impossible to reverse the Flight Readiness
Review risk assessments that foam and O-rings did not pose
safety-of-flight concerns. These engineers could not prove
that foam strikes and cold temperatures were unsafe, even
though the previous analyses that declared them safe had
been incomplete and were based on insufficient data and
testing. Engineers' failed attempts were not just a matter
of psychological frames and interpretations. The obstacles
these engineers faced were political and organizational.
They were rooted in NASA history and the decisions of
leaders that had altered NASA culture, structure, and the
structure of the safety system and affected the social con-
text of decision-making for both accidents. In the following
comparison of these critical decision scenarios for Coliinihia
and Challenger, the systemic problems in the NASA orga-
nization are in italics, with the system effects on decision-
making following.
NASA had confUvtinf' goals of cost, schedule, and safety.
Safety lost out as the mandates of an "operational system"
increased the schedule pressure. Scarce resources went to
problems that were defined as more serious, rather than to
foam strikes or 0-ring erosion.
In both situations, upper-level managers and engineering
teams working the O-ring and foam strike problems held
opposing definitions of risk. This was demonstrated imme-
diately, as engineers reacted with urgency to the immediate
safety implications: Thiokol engineers scrambled to put
together an engineering assessment for the teleconference,
Langley Research Center engineers initiated simulations
of landings that were run after hours at Ames Research
Center, and Boeing analysts worked through the weekend
on the debris impact analysis. But key managers were re-
sponding to additional demands of cost and schedule, which
competed with their safety concerns. NASA's conflicting
goals put engineers at a disadvantage before these new situ-
ations even aro.se. In neither case did they have good data
as a basis for decision-making. Because both problems had
been previously normalized, resources sufficient for testing
or hardware were not dedicated. The Space Shuttle Program
had not produced good data on the correlation betvv'een cold
temperature and O-ring resilience or good data on the poten-
tial effect of bipod ramp foam debris hits.''
Cultural beliefs about the low risk O-rings and foam debris
posed, backed by years of Flight Readiness Review deci-
sions and successful missions, provided a frame of refer-
ence against which the engineering analyses were judged.
When confronted with the engineering risk assessments, top
Shuttle Program managers held to the previous Flight Readi-
ness Review assessments. In the Challenger teleconference,
where engineers were recommending that NASA delay the
launch, the Marshall Solid Rocket Booster Project manager,
Lawrence Mulloy, repeatedly challenged the contractor's
risk assessment and restated Thiokol's engineering ratio-
nale for previous flights."* STS-107 Mission Management
Team Chair Linda Ham made many statements in meetings
reiterating her understanding that foam was a maintenance
problem and a turnaround issue, not a safety-of-flight issue.
The effects of working as a manager in a culture with a cost/
efficiency/safety conflict showed in managerial responses. In
both cases, managers' techniques focused on the information
that tended to support the expected or desired result at that
time. In both cases, believing the safety of the mission was
not at risk, managers drew conclusions that minimized the
risk of delay."' At one point, Marshall's Mulloy, believing
in the previous Flight Readiness Review assessments, un-
convinced by the engineering analysis, and concerned about
the schedule implications of the 53-degree temperature limit
on launch the engineers proposed, said, "My God, Thiokol.
when do you want me to launch, next April?"* Reflecting the
overall goal of keeping to the Node 2 launch schedule. Ham's
priority was to avoid the delay of STS-II4, the next mis-
sion after STS-107. Ham was slated as Manager of Launch
Integration for STS-1 14 - a dual role promoting a conflict of
interest and a single-point failure, a situation that should be
avoided in all organizational as well as technical systems.
NASA's culture of bureaucratic accountability emphasized
chain of commaiul. procedure, following the rules, and go-
ing by the book. While rules and procedures were essential
for coordination, they had an unintended but negative effect.
Allegiance to hierarchy and procedure had replaced defer-
ence to NASA engineers' technical expertise.
2 a Q
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARD
In both cases, engineers initially presented concerns as well
as possible solutions - a request for images, a recommenda-
tion to place temperature constraints on launch. Manage-
ment did not listen to what their engineers were telling them.
Instead, rules and procedures took priority. For Colnnihiu,
program managers turned off the Kennedy engineers' initial
request for Department of Defense imagery, with apologies
to Defense Department representatives for not having fol-
lowed ""proper channels." In addition, NASA administrators
asked for and promised corrective action to prevent such
a violation of protocol from recurring. Debris Assessment
Team analysts at Johnson were asked by managers to dem-
onstrate a ""mandatoiy need" for their imagery request, but
were not told how to do that. Both CliaUen^er and Coluwhia
engineering teams were held to the usual quantitative stan-
dard of proof. But it was a reverse of the usual circumstance:
instead of having to prove it was safe to fly, they were asked
to prove that it was unsafe to fly.
In the Challenger teleconference, a key engineering chart
presented a qualitative argument about the relationship be-
tween cold temperatures and O-ring erosion that engineers
were asked to prove. Thiokol's Roger Boisjoly said, ""I had
no data to quantify it. But I did say I knew it was away from
goodness in the current data base."'" Similarly, the Debris
Assessment Team was asked to prove that the foam hit was
a threat to flight safety, a determination that only the imag-
ei'y they were requesting could help them make. Ignored by
management was the qualitative data that the engineering
teams did have: both instances were outside the experience
base. In stark contrast to the requirement that engineers ad-
here to protocol and hierarchy was management's failure to
apply this criterion to their own activities. The Mission Man-
agement Team did not meet on a regular schedule during the
mission, proceeded in a loose format that allowed infonnal
influence and status differences to shape their decisions, and
allowed unchallenged opinions and assumptions to prevail,
all the while holding the engineers who were making risk
assessments to higher standards. In highly uncertain circum-
stances, when lives were immediately at risk, management
failed to defer to its engineers and failed to recognize that
different data standards - qualitative, subjective, and intui-
tive - and different processes - democratic rather than proto-
col and chain of command - were more appropriate.
The organizational stnutiire and hierarchy blocked effective
communication of technical problems. Signals were over-
looked, people were silenced, and useful information and
dissenting views on technical issues did not surface at higher
levels. What was comnumicated to parts of the organization
was that O-ring erosion and foam debris were not problems.
Structure and hierarchy represent power and status. For both
Challenger and Columbia, employees' positions in the orga-
nization detennined the weight given to their information.
by their own judgment and in the eyes of others. As a result,
many signals of danger were missed. Relevant information
that could have altered the course of events was available
but was not presented.
Early in the Challenger teleconference, some engineers who
had important information did not speak up. They did not
define themselves as qualified because of their position: they
were not in an appropriate specialization, had not recently
worked the O-ring problem, or did not have access to the
""good data" that they assumed others more involved in key
discussions would have."*- Geographic locations also re-
sulted in missing signals. At one point, in light of Marshall's
objections, Thiokol managers in Utah requested an '"off-line
caucus" to discuss their data. No consensus was reached,
so a "management risk decision" was made. Managers
voted and engineers did not. Thiokol managers came back
on line, saying they had reversed their earlier NO-GO rec-
ommendation, decided to accept risk, and would send new
engineering charts to back their reversal. When a Marshall
administrator asked, ""Does anyone have anything to add to
this?," no one spoke. Engineers at Thiokol who still objected
to the decision later testified that they were intimidated by
management authority, were accustomed to turning their
analysis over to managers and letting them decide, and did
not have the quantitative data that would empower them to
object further.^*
In the more decentralized decision process prior to
Columbia's re-entry, structure and hierarchy again were re-
sponsible for an absence of signals. The initial request for
imagery came from the "low status" Kennedy Space Center,
bypassed the Mission Management Team, and went directly
to the Department of Defense separate from the all-power-
ful Shuttle Program. By using the Engineering Directorate
avenue to request imagery, the Debris Assessment Team was
working at the margins of the hierarchy. But some signals
were missing even when engineers traversed the appropriate
channels. The Mission Management Team Chair's position in
the hierarchy governed what information she would or would
not receive. Information was lost as it traveled up the hierar-
chy. A demoralized Debris Assessment Team did not include
a slide about the need for better imagery in their presentation
to the Mission Evaluation Room. Their presentation included
the Crater analysis, which they reported as incomplete and
uncertain. However, the Mission Evaluation Room manager
perceived the Boeing analysis as rigorous and quantitative.
The choice of headings, arrangement of information, and size
of bullets on the key chart served to highlight what manage-
ment already believed. The uncertainties and assumptions
that signaled danger dropped out of the information chain
when the Mission Evaluation Room manager conden.sed the
Debris Assessment Team's fonnal presentation to an infor-
mal verbal brief at the Mission Management Team meeting.
As what the Board calls an "'informal chain of command"
began to shape STS-107's outcome, location in the struc-
ture empowered some to speak and silenced others. For
example, a Thermal Protection System tile expert, who was
a member of the Debris Assessment Team but had an office
in the more prestigious Shuttle Program, used his personal
network to shape the Mission Management Team view and
snuff out dissent. The informal hierarchy among and within
Centers was also influential. Early identifications of prob-
lems by Marshall and Kennedy may have contributed to the
Johnson-based Mission Management Team's indifference to
concerns about the foam strike. The engineers and managers
circulating e-mails at Langley were peripheral to the Shuttle
Program, not stnicturally connected to the proceedings, and
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
therefore of lower status. When asked hi a post-accident
press conference why they didn't voice their concerns to
Shuttle Program management, the Langley engineers said
that people "need to stick to their expertise."'" Status mat-
tered. In its absence, numbers were the great equalizer.
One striking exception: the Debris Assessment Team tile
expert was so influential that his word was taken as gospel,
though he lacked the requisite expeilise, data, or analysis
to evaluate damage to RCC. For those with lesser standing,
the requirement for data was stringent and inhibiting, which
resulted in information that warned of danger not being
passed up the chain. As in the teleconference. Debris As-
sessment Team engineers did not speak up when the Mission
Management Team Chair asked if anyone else had anything
to say. Not only did they not have the numbers, they also
were intimidated by the Mission Management Team Chair's
position in the hierarchy and the conclusions she had already
made. Debris Assessment Team members signed off on the
Crater analysis, even though they had trouble understanding
it. They still wanted images of Coluiiihia's left wing.
In neither impending crisis did management recognize how
structure and hierarchy can silence employees and follow
through by polling participants, soliciting dissenting opin-
ions, or bringing in outsiders who might have a different
perspective or useful information. In perhaps the ultimate
example of engineering concerns not making their way
upstream. Clialleiiiier astronauts were told that the cold tem-
perature was not a problem, and Cohiiuhia astronauts were
told that the foam strike was not a problem.
NASA structure cliciiiged as roles and responsibilities were
transferred to contractors, which increased the dependence
oil the private sector for safety functions and risk assess-
ment while sinuiltaneoitsly reducini> the in-hoiise capability
to spot safety issues.
A critical turning point in both decisions hung on the discus-
sion of contractor risk assessments. Although both Thiokol
and Boeing engineering assessments were replete with
uncertainties. NASA ultimately accepted each. Thiokol's
initial recommendation against the launch of Challeni>er
was at first criticized by Marshall as flawed and unaccept-
able. Thiokol was recommending an unheard-of delay on
the eve of a launch, with schedule ramifications and NASA-
contractor relationship repercussions. In the Thiokol off-line
caucus, a senior vice president who seldom participated in
these engineering discussions championed the Marshall
engineering rationale for flight. When he told the managers
present to "Take off your engineering hat and put on your
inanagement hat." they reversed the position their own
engineers had taken.'*^ Marshall engineers then accepted
this as.sessment. deferring to the expertise of the contractor.
NASA was dependent on Thiokol for the risk assessment,
but the decision process was affected by the contractor's
dependence on NASA. Not willing to be responsible for a
delay, and swayed by the strength of Marshall's argument,
the contractor did not act in the best interests of safety.
Boeing's Crater analysis was performed in the context of
the Debris Assessment Team, which was a collaborative
effort that included Johnson. United Space Alliance, and
Boeing. In this case, the decision process was also affected
by NASA's dependence on the contractor. Unfamiliar with
Crater. NASA engineers and managers had to rely on Boeing
for interpretation and analysis, and did not have the train-
ing necessary to evaluate the results. They accepted Boeing
engineers' use of Crater to model a debris impact 400 times
outside validated limits.
NASA's safety system lacked the resources, independence,
personnel, and authority to successfully apply alternate per-
spectives to developing; problems. Overlapping^ roles and re-
sponsibilities across multiple safety offices also undermined
the possibility of a reliable system of checks and balances.
NASA's "Silent Safety System" did nothing to alter the deci-
sion-making that immediately preceded both accidents. No
safety representatives were present dining the Challenger
teleconference - no one even thought to call them.* In the
case of Columbia, safety representatives were present at
Mission Evaluation Room. Mission Management Team, and
Debris As.sessment Team meetings. However, rather than
critically question or actively participate in the analysis, the
safety representatives simply listened and concurred.
8.6 Changing NASA's Organizational
System
The echoes of Cluilleiii^er in Columbia identified in this
chapter have serious implications. These repeating patterns
mean that flawed practices embedded in NASA's organiza-
tional system continued for 20 years and made substantial
contributions to both accidents. The Columbia Accident
Investigation Board noted the same problems as the Rog-
ers Commission. An organization system failure calls for
corrective measures that address all relevant levels of the
organization, but the Board's investigation shows that for all
its cutting-edge technologies, "diving-catch" rescues, and
imaginative plans for the technology and the future of space
exploration, NASA has shown very little understanding of
the inner workings of its own organization.
NASA managers believed that the agency had a strong
safety culture, but the Board found that the agency had
the same conflicting goals that it did before Challeniier.
when schedule concerns, production pressure, cost-cut-
ting and a drive for ever-greater efficiency - all the signs
of an "operational" enterprise - had eroded NASA's abil-
ity to assure mission safety. The belief in a safety culture
has even less credibility in light of repeated cuts of safety
personnel and budgets - also conditions that existed before
Challeiii^er. NASA managers stated confidently that every-
one was encouraged to speak up about safety issues and that
the agency was responsive to those concerns, but the Board
found evidence to the contrary in the responses to the Debris
Assessment Team's request for imagery, to the initiation of
the imagery request from Kennedy Space Center, and to the
"we were just 'what-iffing'" e-mail concents that did not
reach the Mission Management Team. NASA's bureaucratic
structure kept important information from reaching engi-
neers and managers alike. The same NASA whose engineers
showed initiative and a solid working knowledge of how
to get things done fast had a managerial culture with an al-
legiance to bureaucracy and cost-efficiency that squelched
Report voli
August 20a3
COLUMBIA
ACCIDENT INVESTIGATION SDARO
the engineers' efforts. When it came to managers' own ac-
tions, however, a different set of rules prevailed. The Board
found that Mission Management Team decision-making
operated outside the rules even as it held its engineers to
a stifling protocol. Management was not able to recognize
that in unprecedented conditions, when lives are on the line,
flexibility and democratic process should take priority over
bureaucratic response.'*"
During the Coliiiiihiii investigation, the Board consistently
searched for causal principles that would explain both the
technical and organizational system failures. These prin-
ciples were needed to explain Coliimhia and its echoes of
Clialleiiiicr. They were also necessarj' to provide guidance
for NASA. The Board's analysis of organizational causes in
Chapters 5. 6, and 7 supports the following principles that
should govern the changes in the agency's organizational
system. The Board's specific recommendations, based on
these principles, are presented in Part Three.
Lenders create culture. It is their responsibility to change
it. Top administrators must take responsibility for risk,
failure, and safety by remaining alert to the effects their
decisions have on the system. Leaders are responsible for
establishing the conditions that lead to their subordinates"
successes or failures. The past decisions of national lead-
ers - the White House. Congress, and NASA Headquarters
- set the Cohimbia accident in motion by creating resource
and schedule strains that compromised the principles of a
high-risk technology organization. The measure of NASA's
success became how much costs were reduced and how ef-
ficiently the schedule was met. But the Space Shuttle is not
now. nor has it ever been, an operational vehicle. We cannot
explore space on a fixed-cost basis. Nevertheless, due to
International Space Station needs and scientific experiments
that require particular timing and orbits, the Space Shuttle
Program seems likely to continue to be schedule-driven.
National leadership needs to recognize that NASA must fly
only when it is ready. As the White House, Congress, and
NASA Headquarters plan the future of human space flight,
the goals and the resources required to achieve them safely
must be aligned.
Chaiiiies in ori'anizdtioinil structure should he made only
with careful consideration of their effect on the system and
their possible unintended consequences. Changes that make
the organization more complex may create new ways that it
can fail.^" When changes are put in place, the risk of error
initially increases, as old ways of doing things compete with
new. Institutional memory is lost as personnel and records
are moved and replaced. Changing the structure of organi-
zations is complicated by external political and budgetary
constraints, the inability of leaders to conceive of the full
ramifications of their actions, the vested interests of insiders,
and the failure to learn from the past.^"*
Nonetheless, changes must be made. The Shuttle Program's
structure is a source of problems, not just because of the
way it impedes the flow of information, but because it
has had effects on the culture that contradict safety goals.
NASA's blind spot is it believes it has a strong safety cul-
ture. Program history shows that the loss of a truly indepen-
dent, robust capability to protect the system's fundamental
requirements and specifications inevitably compromised
those requirements, and therefore increased risk. The
Shuttle Program's structure created power distributions that
need new structuring, rules, and management training to
restore deference to technical experts, empower engineers
to get resources they need, and allow safety concerns to be
freely aired.
Strategies must increase the clarity, streni^th. and presence
of signed s that challenge assumptions about risk. Twice in
NASA history, the agency embarked on a slippery slope that
resulted in catastrophe. Each decision, taken by itself, seemed
correct, routine, and indeed, insignificant and unremarkable.
Yet in retrospect, the cumulative effect was stunning. In
both pre-accident periods, events unfolded over a long time
and in small increments rather than in sudden and dramatic
occurrences. NASA's challenge is to design systems that
maximize the clarity of signals, amplify weak signals so they
can be tracked, and accoimt for missing signals. For both ac-
cidents there were moments when management definitions
of risk might have been reversed were it not for the many
missing signals - an absence of trend analysis, imagery data
not obtained, concerns not voiced, information overlooked
or dropped from briefings. A safety team must have equal
and independent representation so that managers are not
again lulled into complacency by shifting definitions of risk.
It is obvious but worth acknowledging that people who are
marginal and powerless in organizations may have useful
infoiTTiation or opinions that they don't express. Even when
these people are encouraged to speak, they find it intimidat-
ing to contradict a leader's strategy or a group consensus.
Extra effort must be made to contribute all relevant informa-
tion to discussions of risk. These strategies are important for
all safety aspects, but especially necessary for ill-structured
problems like O-rings and foam debris. Because ill-structured
problems are less visible and therefore invite the normaliza-
tion of deviance, they may be the most risky of all.
Challenger launches on the ill-fafeci STS-33/51 -L mission on Janu-
ary 28, 1986. The Orbiter would be destroyed 73 seconds later.
Report volu?
1ST 2003
Endnotes for Chapter 8
COLUMBIA
ACCIDENT INVESTIGATION BOARD
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOI-OOIO, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
Turner studied 85 different accidents and disasters, noting o common
pattern: each had a long incubation period in which hazards and
warning signs prior to the accident were either ignored or misinterpreted.
He called these "failures of foresight." Barry Turner, Man-made Disosfers,
(London: Wykeham, 1978); Barry Turner and Nick Pidgeon, Mon-mode
Disosters, 2nd ed. (Oxford: Butterworth Heinneman,1997).
Changing personnel is a typical response after an organization has
some kind of harmful outcome, it has great symbolic value. A change in
personnel points to individuals as the cause and removing them gives the
false impression that the problems have been solved, leaving unresolved
organizational system problems. See Scott Sagan, The Limits of Safety.
Princeton: Princeton University Press, 1993.
Diane Vaughan, The Challenger Launch Decision: Risky Technology,
Culture, and Deviance at NASA (Chicago: University of Chicago Press.
1996).
William H. Storbuck and Frances J. Milliken, "Challenger: Fine-tuning
the Odds until Something Breaks." Journal of Management Studies 23
(1988), pp. 319-40.
Report of the Presidential Commission on the Space Shuttle Challenger
Accident, (Washington: Government Printing Office, 1986), Vol. II,
Appendix H.
Alex Roland, "The Shuttle: Triumph or Turkey?" Discover, November
1985: pp. 29-49.
Report of the Presidential Commission, Vol. I, Ch. 6.
Turner, Man-made Disasters.
Vaughan, The Challenger Launch Deci:
350-52, 356-72.
pp. 243-49, 253-57, 262-64,
Turner, Man-made Disasters.
U.S. Congress, House, /nvestigatjon of the Challenger Accident,
(Washington: Government Printing Office, 1986), pp. 149.
Report of the President/a/ Commission, Vol. I, p. 148; Vol. IV, p. 1446.
Vaughan, The Challenger Launch Decision, p. 235.
Report of the Presidential Commission, Vol. I, pp. 1-3.
Howard E. McCurdy, "The Decay of NASA's Technical Culture," Spoce
Policy (November 1989), pp. 301-10.
Report of the Presidential Commissi
Report of tfie Presidential Commiss,
Report of the Presidential Commiss
•on. Vol. I, pp. 164-177.
, Vol. I, Ch. VII and VIII.
on. Vol. I, pp. 140.
For background on culture in general and engineering culture in
particular, see Peter Whalley and Stephen R. Barley, "Technical Work
in the Division of Labor: Stalking the Wily Anomaly," in Stephen R.
Barley and Julian Orr (eds.) Between Craft and Science, (Ithaca: Cornell
University Press, 1997) pp. 23-53; Gideon Kunda, Engineering Culture;
Control ond Commitment in a High-Tech Corporation, (Philadelphia:
Temple University Press, 1992); Peter Meiksins and James M. Watson,
"Professional Autonomy and Organizational Constraint: The Case of
Engineers," Sociological Quarterly 30 (1989), pp. 561-85; Henry
Petroski, To Engineer is Human: Tfie Role of Failure in Successful Design
(New York: St. Martin's, 1985); Edgar Schein. Orgonization Culture and
Leadership, (San Francisco: Jossey-Boss, 1985); John Van Moanen ond
Stephen R. Barley, "Cultural Organization," in Peter J. Frost, Larry F.
Moore, Meryl Ries Louise, Craig C. Lundberg, and Joanne Martin (eds.)
Organization Culture, (Beverly Hills: Sage, 1985).
Report of tlie Presidential Commission, Vol. I, pp. 82-111.
Horry McDonald, Report of the Shuttle independent Assessment Team.
Report of the Presidential Commission, Vol. I, pp. 145-148.
Vaughan, The Challenger Launch Decision, pp. 257-264.
U. S. Congress, House, Investigation of the Challenger Accident,
(Washington: Government Printing Office, 1986), pp. 70-71.
Report of the Presidential Commission, Vol. I, Ch.VII.
Mary Douglas, How Institutions Think (London: Routledge and Kegan
Paul, 1987); Michael Burowoy, Manufacturing Consent (Chicago:
University of Chicago Press, 1979).
Report of the Presidential Commission, Vol. I, pp. 171-173.
Report of the Presidential Commission, Vol. I, pp. 173-174.
National Aeronautics and Space Administration, Aerospace Safety
Advisory Panel, "Notional Aeronautics and Space Administration Annual
Report: Covering Calendar Year 1984," (Washington: Government
Printing Office, 1985).
Horry McDonald, Report of the Shuttle Independent Assessment Team.
Richard J. Feynmon, "Personal Observations on Reliability of the
Shuttle," Report of the Presidential Commission, Appendix F:l.
Howard E, McCurdy, "The Decoy of NASA's Technical Culture," Space
Policy (November 1989), pp. 301-10; See also Howard E. McCurdy,
Inside NASA (Baltimore: Johns Hopkins University Press, 1993).
Diane Vaughan, "The Trickle-Down Effect: Policy Decisions, Risky Work,
and the Challenger Tragedy," California Management Review, 39, 2,
Winter 1997.
Morton subsequently sold its propulsion division of Alcoa, and the
company Is now known as ATK Thiokol Propulsion.
Report of the Presidential Commission, pp. 82-118.
For discussions of how frames and cultural beliefs shape perceptions, see,
e.g., Lee Clarke, "The Disqualification Heuristic: When Do Organizations
Misperceive Risk?" in Sociol Problems and Public Policy, vol. 5, ed. R. Ted
Youn and William F. Freudenberg, (Greenwich, CT: JAI, 1993); William
Storbuck and Frances Milliken, "Executive Perceptual Filters - What They
Notice and How They Moke Sense," in The Executive Effect, Donald C.
Hambrick, ed. (Greenwich, CT: JAI Press, 1988); Daniel Kohnemon,
Paul Slovic, and Amos Tversky, eds. Judgment Under Uncertainty:
Heuristics and Biases (Cambridge: Cambridge University Press, 1982);
Carol A. Heimer, "Social Structure, Psychology, and the Estimation of
Risk." Annual Review of Sociology 14 (I988J: 491-519, Stephen J. Pfohl,
Predicting Dongeroujness (Lexington, MA: Lexington Books, 1978).
Report of the Presidential Commission, Vol. IV: 791; Vaughan, The
Challenger Launch Decision, p. 178.
Report of the Presidential Commission, Vol. I, pp. 91-92; Vol. IV, p. 612.
Report of the Presidential Commission, Vol. I, pp. 164-177; Chapter 6,
this Report.
Report of the Presidential Commission, Vol. I, p. 90.
Report of the Presidential Commission, Vol. IV, pp. 791. For details of
teleconference and engineering analysis, see Roger M. Boisjoly, "Ethical
Decisions: Morton Thiokol and the Space Shuttle Challenger Disaster,"
American Society of Mechanical Engineers, (Boston: 1987), pp. 1-13.
Vaughan, The Challenger tounch Decision, pp. 358-361.
Report of the Presidential Commission, Vol. I, pp. 88-89, 93.
Edward Wong, "E-Mail Writer Says He was Hypothesizing, Not
Predicting Disaster," New Yorit Times, 11 March 2003, Sec. A-20, Col. 1
(excerpts from press conference. Col. 3).
Report of tfie Presidenh'ol Commission, Vol. I, pp. 92-95.
Report of the Presidential Commission, Vol. I, p. 152.
Weick argues that In a risky situation, people need to learn how to "drop
their tools:" learn to recognize when they are in unprecedented situations
in which following the rules con be disastrous. See Karl E. Weick, "The
Collapse of Sensemoking in Organizations: The Mann Gulch Disaster."
Administrative Science Quarterly 38, 1993, pp. 628-652.
Lee Clarke, Mission Improbable: Using Fantasy Documents to Tame
Disaster, (Chicago: University of Chicago Press, 1999); Charles Perrow,
Normal Accidents, op. cit.; Scott Sagon, The limits of Safety, op. cit.;
Diane Vaughan, "The Dark Side of Organizations," Annual Review of
Sociology, Vol. 25, 1999, pp. 271-305.
Typically, after a public failure, the responsible organization makes
safety the priority. They sink resources into discovering what went wrong
and lessons learned ore on everyone's minds. A boost in resources goes
to safety to build on those lessons in order to prevent another failure.
But concentrating on rebuilding, repair, and safety takes energy and
resources from other goals. As the crisis ebbs and normal functioning
returns. Institutional memory grows short. The tendency Is then to
backslide, as external pressures force a return to operating goals.
William R. Freudenberg, "Nothing Recedes Like Success? Risk Analysis
and the Organizational Amplification of Risks," Risk Issues in Health and
Safety 3, I: 1992, pp. 1-35; Richard H. Hall, Organizations; Structures,
Processes, and Outcomes, (Prentice-Hall. 1998), pp. 184-204; James G.
March, Lee S. Sproull, and Michol Tomuz, "Learning from Samples of
One or Fewer," Orgonizotion Science, 2, 1: February 1991, pp. 1-13.
Report voi-ume i
August zoa 3
Part Three
A Look Ahead
When it 's dark, the stars come out . . . The same is true
with people. When the tragedies of life turn a bright day
into a frightening night. God's stars come out and these
stars are families who say although we grieve deeply
as do the families of Apollo 1 and Challenger before
us, the bold exploration of space must go on. These
stars are the leaders in Government and in NASA who
will not let the visi(m die. These stars are the next gen-
eration of astronauts, who like the prophets of old said,
"Here am I, send me. "
- Brig. Gen. Charles Baldwin. STS-I(I7 Memorial
Ceremony at the National Cathedral. February 6, 2003
As this report ends, the Board wants to recognize the out-
standing people in NASA. We have been impressed with
their diligence, commitment, and professionalism as the
agency has been working tirelessly to help the Board com-
plete this report. While mistakes did lead to the accident, and
we found that organizational and cultural constraints have
worked against safety margins, the NASA family should
nonetheless continue to take great pride in their legacy and
ongoing accomplishments. As we look ahead, the Board sin-
cerely hopes this report will aid NASA in safely getting back
to human space flight.
In Part Three the Board presents its views and recommenda-
tions for the steps needed to achieve that goal, of continuing
our exploration of space, in a manner with improved safety.
Chapter 9 discusses the near-term, mid-term and long-term
implications for the future of human space flight. For the
near term, NASA should submit to the Relurn-to-Flight Task
Force a plan for implementing the return-to-flight recom-
mendations. For the mid-terin, the agency should focus on:
the remaining Part One recommendations, the Part Two rec-
ommendations for organizational and cultural changes, and
the Part Three recommendation for recertifying the Shuttle
for use to 2020 or bcvf)nd. In setting the stasze for a debate
on the long-term future of human space flight, the Board ad-
dresses the need for a national vision to direct the design of
a new Space Transportation System.
Chapter 10 contains additional recommendations and the
significant "look ahead" observations the Board made in the
course of this investigation that were not directly related to
the accident, but could be viewed as "weak signals" of fu-
ture problems. The observations may be indications of seri-
ous future problems and must be addressed by NASA.
Chapter 1 1 contains the recommendations made in Parts
One, Two and Three, all issued with the resolve to continue
human space flight.
Report van
August ZDOa
COLUMBIA
ACCIOENT INVESTIGATIDN BDARE
Columbia in the Vehicle Assembly Building at the Kennedy Space Cenfer being readied for STS-107 in lafe 2002.
Report Volume I August 2003
Chapter 9
Implications for the
Future of Human Space Flight
And while many memorials will he built to honor Co-
lumbia 'v crew, their greatest memorial will he a vibrant
space program with new missions carried out by a new
generation of brave explorers.
Remarks by Vice President Richard B. Ciicncy, Memorial
Ceremony al the National Cathedral. Februarv 6. 2003
The report up to this point has been a look backward: a single
accident with multiple causes, both physical and organiza-
tional. In this chapter, the Board looks to the future. We take
the insights gained in investigating the loss of Columbia and
her crew and seek to apply them to this nation's continu-
ing journey into space. We divide our discussion into three
timeframes: I ) short-term. NASA's return to flight after the
Columbia accident; 2) mid-term, what is needed to continue
flying the Shuttle fleet until a replacement means for human
access to space and for other Shuttle capabilities is available:
and 3) long-term, future directions for the U.S. in space. The
objective in each case is for this country to maintain a human
presence in space, but with enhanced safety of flight.
In this report we have documented numerous indications
that NASA's safety performance has been lacking. But even
correcting all those shortcomings, it should be understood,
will not eliminate risk. All flight entails some measure of
risk, and this has been the case since before the days of the
Wright Brothers. Furthermore, the risk is not distributed
evenly over the course of the flight. It is greater by far at the
beginning and end than during the middle.
This concentration of risk at the endpoints of flight is particu-
larly true for crew-carrying space missions. The Shuttle Pro-
gram has now suffered two accidents, one just over a minute
after takeoff and the other about 16 minutes before landing.
The laws of physics make it extraordinarily difhcult to reach
Earth orbit and return safely. Using existing technology, or-
bital flight is accomplished only by harnessing a chemical
reaction that converts vast amounts of stored energy into
speed. There is great risk in placing human beings atop a
machine that stores and then burns millions of pounds of
dangerous propellants. Fx|ually risky is having humans then
ride the machine back to Earth while it dissipates the orbital
speed by c(Miverting the energy into heat, much like a meteor
entering Earth's atmosphere. No alternatives to this pathway
to space are available or even on the horizon, so we must
set our sights on managing this risky process using the inost
advanced and versatile techniques at our disposal.
Columbia launches as STS107 on January 16, 2003.
Report Voli
August ZOOS
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Because of the dangers of ascent and re-entry, because of
the hostility of the space environment, and because we
are still relative newcomers to this realm, operation of the
Shuttle and indeed all human spaceflight must be viewed
as a developmental activity. It is still far from a routine,
operational undertaking. Throughout the Columbia accident
investigation, the Board has commented on the widespread
but erroneous perception of the Space Shuttle as somehow
comparable to civil or military air transport. They are not
comparable; the inherent risks of spaceflight are vastly high-
er, and our experience level with spaceflight is vastly lower.
if Shuttle operations came to be viewed as routine, it was, at
least in part, thanks to the skill and dedication of those in-
volved in the program. They have made it look easy, though
in fact it never was. The Board urges NASA leadership, the
architects of U.S. space policy, and the American people to
adopt a realistic understanding of the risks and rewards of
venturing into space.
9.1 Near-Term: Return to Flight
The Board supports return to flight for the Space Shuttle at
the earliest date consistent with an overriding consideration:
safety. The recognition of human spaceflight as a develop-
mental activity requires a shift in focus from operations and
meeting schedules to a concern for the risks involved. Nec-
essary measures include:
• Identifying risks by looking relentlessly for the next
eroding O-ring. the next falling foam; obtaining better
data, analyzing and spotting trends.
• Mitigating risks by stopping the failure at its source:
when a failure does occur, improving the ability to tol-
erate it; repairing the damage on a timely basis.
• Decoupling unforeseen events from the loss of crew and
vehicle.
• Exploring all options for survival, such as provisions for
crew escape systems and safe havens.
• Barring unwarranted departures froin design standards,
and adjusting standards only under the most rigorous,
safety-driven process.
The Board has recommended improvements that are needed
before the Shuttle Program returns to flight, as well as other
measures to be adopted over the longer term - what might be
considered "continuing to fly" recommendations. To ensure
implementation of these longer-term recommendations, the
Board makes the following recommendation, which should
be included in the requirements for retum-to-flight:
R9. 1 - 1 Prepare a detailed plan for defining, establishing,
transitioning, and implementing an independent
Technical Engineering Authority, independent
safety program, and a reorganized Space Shuttle
Integration Office as described in R7.5-I, R7.3-
2, and R7.5-3. In addition, NASA should submit
annual reports to Congress, as part of the budget
review process, on its implementation activi-
ties.
The complete list of the Board's recommendations can be
found in Chapter 1 1.
9.2 Mid-Term: Continuing to Fly
It is the view of the Board that the present Shuttle is not
inherently unsafe. However, the observations and recom-
mendations in this report are needed to make the vehicle
safe enough to operate in the coming years. In order to con-
tinue operating the Shuttle for another decade or even more,
which the Human Space Flight Program may find necessary,
these significant measures must be taken:
• Implement all the recommendations listed in Part One
of this report that were not already accomplished as part
of the retum-to-flight reforms.
• Institute all the organizational and cultural changes
called for in Part Two of this report.
• Undertake complete recertification of the Shuttle, as
detailed in the discussion and recommendation below.
The urgency of these recommendations derives, at least in
part, from the likely pattern of what is to come. In the near
term, the recent memory of the Coliimhia accident will mo-
tivate the entire NASA organization to scrupulous attention
to detail and vigorous efforts to resolve elusive technical
problems. That energy will inevitably dissipate over time.
This decline in vigilance is a characteristic of many large
organizations, and it has been demonstrated in NASA's own
history. As reported in Part Two of this report, the Human
Space Flight Program has at times compromised safety be-
cause of its organizational problems and cultural traits. That
is the reason, in order to prevent the return of bad habits over
time, that the Board makes the recommendations in Part
Two calling for changes in the organization and culture of
the Human Space Flight Program. These changes will take
more time and effort than would be reasonable to expect
prior to return to flight.
Through its recoinmendations in Part Two. the Board has
urged that NASA's Human Space Flight Program adopt the
characteristics observed in high-reliability organizations.
One is separating technical authority from the functions of
managing schedules and cost. Another is an independent
Safety and Mission Assurance organization. The third is the
capability for effective systems integration. Perhaps even
more challenging than these organizational changes are the
cultural changes required. Within NASA, the cultural im-
pediments to safe and effective Shuttle operations are real
and substantial, as documented extensively in this report.
The Board's view is that cultural problems are unlikely to
be corrected without top-level leadership. Such leadership
will have to rid the system of practices and patterns that
have been validated simply because they have been around
so long. Examples include: the tendency to keep knowledge
of problems contained within a Center or program; making
technical decisions without in-depth, peer-reviewed techni-
cal analysis; and an unofficial hierarchy or caste system cre-
ated by placing excessive power in one office. Such factors
interfere with open communication, impede the sharing of
lessons learned, cause duplication and unnecessary expen-
diture of resources, prompt resistance to external advice,
and create a burden for managers, among other undesirable
outcomes. Collectively, these undesirable characteristics
threaten safety.
z o s
Report Voli
iT 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION fiDARD
Unlike retum-to-flight recommendations, the Board's man-
agement and cultural recommendations will take longer
to implement, and the responses must be tine-tuned and
adjusted during implementation. The question of how to fol-
low up on NASA's implementation of these more subtle, but
equally important recommendations remains unanswered.
The Board is aware that response to these recommenda-
tions will be difficult to initiate, and they will encounter
some degree of institutional resistance. Nevertheless, in the
Board's view, they are so critical to safer operation of the
Shuttle fleet that they must be carried out completely. Since
NASA is an independent agency answerable only to the
White House and Congress, the ultimate responsibility for
enforcement of the recommended corrective actions must
reside with those governmental authorities.
Recertification
Recertification is a process to ensure flight safety when a
vehicle's actual utilization exceeds its original design life;
such a baseline examination is essential to certify that ve-
hicle for continued use. in the case of the Shuttle to 2020
and possibly beyond. This report addresses recertification as
a mid-term issue.
Measured by their 20 or more missions per Orbiter, the
Shuttle fleet is young, but by chronological age - 10 to 20
years each - it is old. The Board's discovery of mass loss in
RCC panels, the deferral of investigation into signs of metal
corrosion, and the deferral of upgrades all strongly suggest
that a policy is needed requiring a complete recertification
of the Space Shuttle. This recertification must be rigorous
and comprehensive at every level (i.e.. material, compo-
nent, subsystem, and system); the higher the level, the more
critical the integration of lower-level components. A post-
Challeni^er. 10-year review was conducted, but it lacked this
kind of rigor, comprehensiveness and, most importantly, in-
tegration at the subsystem and system levels.
Aviation industry standards offer ample measurable criteria
for gauging specific aging characteristics, such as stress and
corrosion. The Shuttle Program, by contrast, lacks a closed-
loop feedback system and consequently does not take full
advantage of all available data to adjust its certification pro-
cess and maintenance practices. Data sources can include
experience with material and component failures, non-con-
formances (deviations from original specifications) discov-
ered during Orbiter .Vlaintenance Down Periods, Analytical
Condition Inspections, and Aging Aircraft studies. Several
of the recommendations in this report constitute the basis for
a recertification program (such as the call for nondestrtictive
evaluation of RCC components). Chapters .^ and 4 cite in-
stances of waivers and certification of components for flight
based on analysis rather than testing. The recertification
program should correct all those deficiencies.
Finally, recertification is but one aspect of a Service Life Ex-
tension Program that is essential if the Shuttle is to continue
operating for another 10 to 20 years. While NASA has such
a program, it is in its infancy and needs to be pursued with
vigor. The Service Life Extension Program goes beyond the
Shuttle itself and addresses critical associated components
in equipment, infrastructure, and other areas. Aspects of the
program are addressed in Appendix D. 1 5.
The Board makes the following recommendation regarding
recertification:
R9.2-1 Prior to operating the Shuttle beyond 2010,
develop and conduct a vehicle recertification at
the material, ctimponent, subsystem, and system
levels. Recertification requirements should be
included in the Service Life Extension Program.
9.3 Long-Term: Future Directions for the
U.S. in Space
The Board in its investigation has focused on the physical
and organizational causes of the Columbia accident and the
recommended actions required for future safe Shuttle opera-
tion. In the course of that investigation, however, two reali-
ties affecting those recommendations have become evident
to the Board. One is the lack, over the past three decades,
of any national mandate providing NASA a compelling
mission requiring human presence in space. President John
Kennedy's 1961 charge to send Americans to the moon and
return them safely to Earth "before this decade is out" linked
NASA's efforts to core Cold War national interests. Since
the 1970s, NASA has not been charged with carrying out a
similar high priority mission that would justify the expendi-
ture of resources on a scale equivalent to those allocated for
Project Apollo. The result is the agency has found it neces-
sary to gain the support of diverse constituencies. NASA has
had to participate in the give and take of the normal political
process in order to obtain the resources needed to carry out
its programs. NASA has usually failed to receive budgetary
support consistent with its ambitions. The result, as noted
throughout Part Two of the report, is an organization strain-
ing to do too much with too little.
A second reality, following from the lack of a clearly defined
long-term space mission, is the lack of sustained government
commitment over the past decade to improving U.S. access
to space by developing a second-generation space transpor-
tation system. Without a compelling reason to do so, succes-
sive Administrations and Congresses have not been willing
to commit the billions of dollars required to develop such a
vehicle. In addition, the space community has proposed to
the government the development of vehicles such as the Na-
tional Aerospace Plane and X-33, which required "leapfrog"
advances in technology; those advances have proven to be
unachievable. As Apollo 1 1 Astronaut Buzz Aldrin, one of
the members of the recent Commission on the Future of the
United States Aerospace Industry, commented in the Com-
mission's November 2002 report, "Attempts at developing
breakthrough space transportation systems have proved il-
lusory."' The Board believes that the country should plan
for future space transportation capabilities without making
them dependent on technological breakthroughs.
Lack of a National Vision for Space
In 1969 President Richard Ni.xon rejected NASA's sweeping
vision for a post-Apollo effort that involved full develop-
Report Volume i
1ST 2 O D 3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
ment of low-Earth orbit, permanent outposts on the moon,
and initial journeys to Mars. Since that rejection, these objec-
tives have reappeared as central elements in many proposals
setting forth a long-term vision for the U.S. Space program.
In 1986 the National Commission on Space proposed "a
pioneering mission for 21st-century America: To lead the
exploration and development of the space frontier, advanc-
ing science, technology, and enterprise, and building institu-
tions and systems that make accessible vast new resources
and support human settlements beyond Earth orbit, from the
highlands of the Moon to the plains of Mars."- In 1 989, on the
20th anniversary of the first lunar landing. President George
H.W. Bush proposed a Space Exploration Initiative, calling
for "a sustained program of manned exploration of the solar
system."' Space advocates have been consistent in their call
for sending humans beyond low-Earth orbit as the appropri-
ate objective of U.S. space activities. Review committees as
diverse as the 1990 Advisoiy Committee on the Future of
the U.S. Space Program, chaired by Norman Augustine, and
the 2001 International Space Station Management and Cost
Evaluation Task Force have suggested that the primary justi-
fication for a space station is to conduct the research required
to plan missions to Mars and/or other distant destinations.
However, , human travel to destinations beyond Earth orbit
has not been adopted as a national objective.
The report of the Augustine Committee commented, "It
seems that most Americans do support a viable space pro-
gram for the nation - but no two individuals seem able to
agree upon what that space program should be."'' The Board
observes that none of the competing long-term visions for
space have found support from the nation's leadership, or
indeed among the general public. The U.S. civilian space
effort has moved forward for more than 30 years without a
guiding vision, and none seems imminent. In the past, this
absence of a strategic vision in itself has reflected a policy
decision, since there have been many opportunities for na-
tional 'leaders to agree on ambitious goals for space, and
none have done so.
The Board does observe that there is one area of agreement
among almost all parties interested in the future of U.S. ac-
tivities in space: The United States needs improved access for
Inimans to low-Earth orbit as a foundation for whatever di-
rections the nation '.v space proi^rani takes in the future. In the
Board's view, a full national debate on how best to achieve
such improved access should take place in parallel with the
steps the Board has recommended for returning the Space
Shuttle to flight and for keeping it operating safely in coming
years. Recommending the content of this debate goes well
beyond the Board's mandate, but we believe that the White
House, Congress, and NASA should honor the memory of
Cohinihia\ crew by reflecting on the nation's future in space
and the role of new space transportation capabilities in en-
abling whatever space goals the nation chooses to pursue.
All members of the Board agree that America's future space
efforts must include human presence in Earth orbit, and
eventually beyond, as outlined in the current NASA vision.
Recognizing the absence of an agreed national mandate
cited above, the current NASA strategic plan stresses an
approach of investing in "transfonnational technologies"
that will enable the development of capabilities to serve as
"stepping stones" for whatever path the nation may decide it
wants to pursue in space. While the Board has not reviewed
this plan in depth, this approach seems prudent. Absent any
long-term statement of what the country wants to accom-
plish in space, it is difficult to state with any specificity the
requirements that should guide major public investments in
new capabilities. The Board does believe that NASA and
the nation should give more attention to developing a new
"concept of operations" for future activities - defining the
range of activities the country intends to carry out in space
- that could provide more specificity than currently exists.
Such a concept does not necessarily require full agreement
on a future vision, but it should help identify the capabilities
required and prevent the debate from focusing solely on the
design of the next vehicle.
Developing a New Space Transportation System
When the Space Shuttle development was approved in
1972. there was a corresponding decision not to fund tech-
nologies for space transportation other than those related
to the Shuttle. This decision guided policy for more than
20 years, until the National Space Transportation Policy of
1994 assigned NASA the role of developing a next-genera-
tion, advanced-technology, single-stage-to-orbit replace-
ment for the Space Shuttle. That decision was flawed for
several reasons. Because the United States had not funded
a broad portfolio of space transportation technologies for
the preceding three decades, there was a limited technology
base on which to base the choice of this second-generation
system. The technologies chosen for development in 1996,
which were embodied in the X-33 demonstrator, proved
not yet mature enough for use. Attracted by the notion of
a growing private sector market for space transportation,
the Clinton Administration hoped this new system could be
developed with minimal public investment - the hope was
that the private sector would help pay for the development
of a Shuttle replacement.
In recent years there has been increasing investment in
space transportation technologies, particularly through
NASA's Space Launch Initiative effort, begun in 2000. This
investment has not yet created a technology base for a sec-
ond-generation reusable system for carrying people to orbit.
Accordingly, in 2002 NASA decided to reorient the Space
Launch Initiative to longer-term objectives, and to introduce
the concept of an Orbital Space Plane as an interim comple-
ment to the Space Shuttle for space station crew-candying re-
sponsibilities. The Integrated Space Transportation Plan also
called for using the Space Shuttle for an extended period
into the future. The Board has evaluated neither NASA's In-
tegrated Space Transportation Plan nor the detailed require-
ments of an Orbital Space Plane.
Even so, based on its in-depth examination of the Space
Shuttle Program, the Board has reached an inescapable
conclusion: Because of the risks inherent in the orii^inal
design of the Space Shuttle, because that desii^n was based
in many aspects on now-obsolete technologies, and because
the Shuttle is now an «.!,'/';,!,' system but still developnwntal in
character, it is in the nation's interest to replace the Shuttle
Report vai_ui
fGUST ZQQ3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
as soon as possible as the primary means for transportini^
humans To and from Earth orbit. At least in the mid-term,
that replacement will be some form of what NASA now
characterizes as an Orbital Space Plane. The design of the
system should give overriding priority to crew safety, rather
than trade safety against other performance criteria, such as
low cost and reusability, or against advanced space opera-
tion capabilities other than crew transfer.
This conclusion implies that whatever design NASA chooses
should become the primai^ means for taking people to and
from the International Space Station, not just a complement
to the Space Shuttle. And it follows from the same conclusion
that there is urgency in choosing that design, after serious
review of a "concept of operations" for human space flight,
and bringing it into operation as soon as possible. This is
likely to require a significant commitment of resources over
the next several years. The nation must not shy from making
that commitment. The International Space Station is likely
to be the major destination for human space travel for the
next decade or longer. The Space Shuttle would continue to
be used when its unique capabilities are required, both with
respect to space station missions such as experiment deliveiy
and retrieval or other logistical missions, and with respect to
the few planned missions not traveling to the space station.
When cargo can be carried to the space station or other desti-
nations by an expendable launch vehicle, it should be.
However, the Orbital Space Plane is seen by NASA as an
interim system for transporting humans to orbit. NASA plans
to make continuing investments in "next generation launch
technology," with the hope that those investments will en-
able a decision by the end of this decade on what that next
generation launch vehicle should be. This is a worthy goal,
and should be pursued. The Board notes that this approach
can only be successful: if it is sustained over the decade: if by
the time a decision to develop a new vehicle is made there is
a clearer idea of how the new space transportation system fits
into the nation's overall plans for space: and if the U.S. i^ov-
ernment is willini> at the time a development decision is made
to commit the suhsfcmticd resources required to implement it.
One of the major problems with the way the Space Shuttle
Program was carried out was an a priori fixed ceiling on de-
velopment costs. That approach should not be repeated.
It is the view of the Board that the previous attempts to de-
velop a replacement vehicle for the a^inf; Shuttle represent
a failure of national leadership. The cause of the failure
was continuing to expect major technological advances in
that vehicle. With the amount of risk inherent in the Space
Shuttle, the first step should be to reach an agreement that
the overriding mission of the replacement system is to move
humans safely and reliably into and out of Earth orbit. To
demand more would be to fall into the same trap as all previ-
ous, unsuccessful, efforts. That being said, it seems to the
Board that past and future investments in space launch tech-
nologies should certainly provide by 2010 or thereabouts the
basis for developing a system, significantly improved over
one designed 40 years earlier, for carrying humans to orbit
and enabling their work in space. Continued U.S. leadership
in space is an important national objective. That leadership
depends on a willingness to pay the costs of achieving it.
Final Conclusions
The Board's perspective assumes, of course, that the United
States wants to retain a continuing capability to send people
into space, whether to Earth orbit or beyond. The Board's
work over the past seven months has been motivated by
the desire to honor the STS-107 crew by understanding
the cause of the accident in which they died, and to help
the United States and indeed all spacefaring countries to
minimize the risks of future loss of lives in the exploration
of space. The United States should continue with a Human
Space Flight Program consistent with the resolve voiced by
President George W. Bush on February 1, 2003: "Mankind
is led into the darkness beyond our world by the inspiration
of discovery and the loni^iui^ to understand. Our journey into
space will i>o on."
Two proposals - a capsule (above) and a winged vehicle - for the
Orbital Space Plane, courtesy of The Boeing Company.
Report Von
tGUST 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Endnotes for Chapter 9
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the National Archives.
Report on the Commission on the Future of the United States Aerospace
Industry, November 2002, p. 3-3.
National Commission on Space, Pioneering the Space Frontier: An
Exciting Vision of Our Next Fifty Years /n Space, f?eport of the National
Commission on Spoce (Bantam Books, 1986), p. 2.
President George H. W. Bush, "Remarks on the 20th Anniversary of the
Apollo n Moon Landing," Washington, D.C., July 20, 1989.
"Report of the Advisory Committee on the Future of the U.S. Space
Program," December 1990, p. 2.
1 2 —————— ——"^^—^^—"— "^— Report V □ i. u m i
Other
Significant Observations
Although the Board now understands the combination of
technical and organizational factors that contributed to the
ColiimhUi accident, the investigation did not immediately
zero in on the causes identified in previous chapters. Instead,
the Board explored a number of avenues and topics that, in
the end, were not directly related to the cause of this ac-
cident. Nonetheless, these forays revealed technical, safety,
and cultural issues that could impact the Space Shuttle Pro-
gram, and, more broadly, the future of human space flight.
The significant issues listed in this chapter are potentially
serious matters that should be addresed by NASA becau.se
they fall into the category of "'weak signals" that could be
indications of future problems.
10.1 Public Safety
Shortly after the breakup of Coltinihia over Texas, dramatic
images of the Orbiter's debris surfaced: an intact spherical
tank in an empty parking lot, an obliterated office rooftop,
mangled metal along roadsides, charred chunks of material
in fields. These images, combined with the large number of
debris fragments that were recovered, compelled many to
proclaim it was a ""miracle" that no one on the ground had
been hurt.'
The Columbia accident raises some important questions
about public safety. What were the chances that the general
public could have been hurt by a breakup of an Orbiter?
How safe are Shuttle flights compared with those of con-
ventional aircraft? How much public risk from space flight
is acceptable? Who is responsible for public safety during
space flight operations?
Public Risk from Columbia's Breakup
The Board commissioned a study to determine if the lack of
reported injuries on the ground was a predictable outcome or
simply exceptionally good fortune (see Appendix D. 1 6). The
study extrapolated from an array of data, including census
figures for the debris impact area, the Orbiter's last reported
position and velocity, the impact locations (latitude and lon-
gitude), and the total weight t)f all recovered debris, as well
as the composition and dimensions of many debris pieces.-
Based on the best available evidence on C()liinihia\ disinte-
gration and ground impact, the lack of serious injuries on the
ground was the expected outcome for the location and time
at which the breakup occuired.'
NASA and others have developed sophisticated computer
tools to predict the trajectory and survivability of spacecraft
debris during re-entry.^ Such tools have been used to assess
the risk of serious injuries to the public due to spacecraft
re-entry, including debris impacts from launch vehicle
malfunctions.'' However, it is impossible to be certain about
what fraction of Coliinihia survived to impact the ground.
Some 38 percent of Coliiiiihia's, dry (empty) weight was
recovered, but there is no way to determine how much still
lies on the ground. Accounting for the inherent uncertainties
associated with the amount of ground debris and the num-
ber of people outdoors,'' there was about a 9- to 24-percent
chance of at least one person being seriously injured by the
disintegration of the Orbiter."
Debris fell on a relatively sparsely populated area of the
United States, with an average of about 8.5 inhabitants per
square mile. Orbiter re-entry flight paths often pass over
much more populated areas, including major cities that
average more than 1 ,000 inhabitants per square mile. For
example, the STS-107 re-enti^y profile passed over Sac-
ramento, California, and Albuquerque. New Mexico. The
Board-sponsored study concluded that, given the unlikely
event of a similar Orbiter breakup over a densely populated
area such as Houston, the most likely outcome would be one
or two ground casualties.
Space Flight Risk Compared to Aircraft Operations
A recent study of U.S. civil aviation accidents found that
between 1964 and 1999, falling aircraft debris killed an av-
REPORT VOLl
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
erage of eight people per year.** In comparison, the National
Center for Health Statistics reports that between 1992 and
1994, an average of 65 people in the United States were
killed each year by lightning strikes. The aviation accident
study revealed a decreasing trend in the annual number of
"groundling" fatalities, so that an average of about four
fatalities per year are predicted in the near future.'* The prob-
ability of a U.S. resident being killed by aircraft debris is
now less than one in a million over a 70-year lifetime.'"
The history of U.S. space flight has a flawless public safety
record. Since the 1950s, there have been hundreds of U.S.
space launches without a single member of the public being
injured. Comparisons between the risk to the public from
space flight and aviation operations are limited by two fac-
tors; the absence of public injuries resulting from U.S. space
flight operations, and the relatively small number of space
flights (hundreds) compared to aircraft flights (billions)."
Nonetheless, it is unlikely that U.S. space flights will pro-
duce many, if any, public injuries in the coming years based
on ( 1 ) the low numberof space flight operations per year, (2)
the flawless public safety record of past U.S. space launches,
(3) government-adopted space flight safety standards,'- and
(4) the risk assessment result that, even in the unlikely event
of a similar Orbiter breakup over a major city, less than two
ground casualties would be expected. In short, the risk posed
to people on the ground by U.S. space flight operations is
small compared to the risk from civil aircraft operations.
The government has sought to limit public risk from space
flight to levels comparable to the risk produced by aircraft.
U.S. space launch range commanders have agreed that the
public should face no more than a one-in-a-million chance
of fatality from launch vehicle and unmanned aircraft op-
erations." This aligns with Federal Aviation Administration
(FAA) regulations that individuals be exposed to no more
than a one-in-a-million chance of serious injury due to com-
mercial space launch and re-entry operations.'^
NASA has not actively followed public ri.sk acceptability
standards used by other government agencies during past
Orbiter re-entry operations. However, in the aftermath of the
Columbia accident, the agency has attempted to adopt similar
rules to protect the public. It has also developed computer
tools to predict the sui-vivability of spacecraft debris during
re-entry. Such tools have been used to assess the risk of public
casualties attributable to spacecraft re-entry, including debris
impacts from commercial launch vehicle malfunctions.'^
Responsibility for Public Safety
The Director of the Kennedy Space Center is responsible
for the ground and flight safety of Kennedy Space Center
people and property for all launches."' The Air Force pro-
vides the Director with written notification of launch area
risk estimates for Shuttle ascents. The Air Force routinely
computes the risk that Shuttle ascents'^ pose to people on
and off Kennedy grounds from potential debris impacts,
toxic exposures, and explosions."*
However, no equivalent collaboration exists between NASA
and the Air Force for re-entry risk. FAA rules on commercial
space launch activities do not apply "where the Government
is so substantially involved that it is effectively directing or
controlling the launch." Based on the lack of a response, in
tandem with NASA's public statements and informal replies
to Board questions, the Board determined that NASA made
no documented effort to assess public risk from Orbiter re-
entry operations prior to the Coliiinhia accident. The Board
believes that NASA should be legally responsible for public
safety during all phases of Shuttle operations, including re-
entry'.
Findings:
F 1 0. 1 - 1 The Columbia accident demonstrated that Orbiter
breakup during re-entry has the potential to cause
casualties among the general public.
FIO. 1-2 Given the best information available to date,
a formal risk analysis sponsored by the Board
found that the lack of general-public casualties
from Columbia's break-up was the expected out-
come.
FIO. 1-3 The history of U.S. space flight has a flawless
public safety record. Since the 1950s, hundreds
of space flights have occurred without a single
public injury.
FIO. I -4 The FAA and U.S. space launch ranges have safe-
ty standards designed to ensure that the general
public is exposed to less than a one-in-a-million
chance of serious injury from the operation of
space launch vehicles and unmanned aircraft.
FIO. 1-5 NASA did not demonstrably follow public risk
acceptability standards during past Orbiter re-
entries. NASA efforts are underway to define a
national policy for the protection of public safety
during all operations involving space launch ve-
hicles.
Observations:
OIO.I-I NASA should develop and implement a public
risk acceptability policy for launch and re-entry
of space vehicles and unmanned aircraft.
0 10. 1-2 NASA should develop and implement a plan to
mitigate the risk that Shuttle flights pose to the
general public.
Ol 0.1-3 NASA should study the debris recovered from
Columbia to facilitate realistic estimates of the
risk to the public during Orbiter re-entry.
10.2 Crew Escape and Survival
The Board has examined crew escape systems in historical
context with a view to future improvements. It is important
to note at the outset that Columbia broke up during a phase
of flight that, given the current design of the Orbiter. offered
no possibility of crew survival.
The goal of evei7 Shuttle mission is the safe return of the
crew. An escape system— a means for the crew to leave a
vehicle in distress during some or all of its flight phases
and return safely to Earth - has historically been viewed
Report Voui
iT ZOOS
COLUMBIA
ACCIDENT INVESTIGATIDN BDARO
as one "technique" to accomplish that end. Other methods
include various abort modes, rescue, and the creation of a
safe haven (a location where crew members could remain
unharmed if they are unable to return to Earth aboard a dam-
aged Shuttle).
While crew escape systems have been discussed and stud-
ied continuously since the Shuttle's early design phases,
only two systems have been incorporated: one for the de-
velopmental test flights, and the current system installed
after the Cluillc'ni;er accident. Both designs have extremely
limited capabilities, and neither has ever been used during
a mission.
Developmental Test Flights
Early studies assumed that the Space Shuttle would be op-
erational in every sense of the word. As a result, much like
commercial airliners, a Shuttle crew escape system was con-
sidered unnecessary. NASA adopted requirements for rapid
emergency egress of the crew in early Shuttle test flights.
Modified SR-71 ejection seats for the two pilot positions
were installed on the Orbiter test vehicle Enterprise, which
was carried to an altitude of 25.000 feet by a Boeing 747
Shuttle Carrier Aircraft during the Approach and Landing
Tests in 1977.'''
Essentially the same system was installed on Coliiinhici and
used for the four Orbital Test Flights during 1981-82. While
this system was designed for use during first-stage ascent
and in gliding flight below 100.000 feet, considerable doubt
emerged about the survivability of an ejection that would
expose crew members to the .Solid Rocket Booster exhaust
plume. Regardless, NASA declared the developmental test
flight phase complete after STS-4, Coliinihia's fourth flight,
and the ejection seat system was deactivated. Its as.sociated
hardware was removed during modification after STS-9. All
Space Shuttle missions after STS-4 were conducted with
crews of four or more, and no escape system was installed
until after the loss of Cluilleni;er in 1986.
Before the CluiUeni>er accident, the question of crew sur-
vival was not considered independently from the possibility
of catastrophic Shuttle damage. In short, NASA believed if
the Orbiter could be saved, then the crew would be safe. Per-
ceived limits of the use of escape systems, along with their
cost, engineering complexity, and weight/payload trade-
offs, dissuaded NASA from implementing a crew escape
plan. Instead, the agency focused on preventing the loss of a
Shuttle as the sole means for assuring crew survival.
Post-C/ia//enger: the Current System
NASA's rejection of a crew escape system was severely
criticized after the loss of Challeiiiier. The Rogers Commis-
sion addressed the topic in a recommendation that combined
the issues of launch abort and crew escape:-"
Ldiineh Abort anil Crew Escape. The Shuttle Pr(>f>raiii
manafiement considered first-staf;e abort options and
crew escape options .several times diirini> the history
of the prof>ram. hitt because of limited utility, technical
infeasibility, or prof^ram cost and .schedule, no systems
were implemeii'ed. The Commission recommends that
NASA:
• Make all efforts to provide a crew escape .system for
use during controlled gliding flight.
• Make every effort to increase the range of flight
conditions under which an emergency runway land-
ing can be succes.sfully condiuted in the event that
two or three main engines fail early in a.scent.
In response to this recommendation, NASA developed the
current "pole bailout" system for use during controlled, sub-
sonic gliding flight (see Figure 10.2-1 ). The system requires
crew members to "vent" the cabin at 40.000 feet (to equalize
the cabin pressure with the pressure at that altitude), jettison
the hatch at approximately 32,000 feet, and then jump out of
the vehicle (the pole allows crew members to avoid striking
the Orbiter's wings).
Figure 70.2-7. A demonstration of the pole bailout system. The
pole is extending from the side of a C-141 simulating the Orbiter,
with a crew member sliding down the pole so that he would fall
clear of the Orbiter's wing during an actual bailout.
Current Human-Rating Requirements
In June 1998, Johnson Space Center issued new Human-
Rating Requirements applicable to "all future human-rated
spacecraft operated by NASA." In July 2003, shortly before
this report was published, NASA issued further Human-Rat-
ing Requirements and Guidelines for Space Flight Systems,
over the signature of the Associate Administrator for Safety
and Mission Assurance. While these new requirements "...
shall not supersede more stringent requirements imposed by
individual NASA organizations ..." NASA has infonned the
Board that the earlier - and in some cases more prescriptive
- Johnson Space Center requirements have been cancelled.
Report Vauui
AUGUST 2003
COLUMBIA
ACCIOENT INVESTIGATIDN BOARD
NASA's 2003 Human-Rating Requirements and Guidelines
for Space Flight Systems laid out the following principles
regarding crew escape and survival:
2.5.4 Crew .siin'ival
2.5.4.1 As part of the ilesiiiii process. pn>:j^rain
nuiiuii^einent (with approval from the
CHMO [Chief Health and Medical Offi-
cer], AAfor OSF [Associate Administrator
for the Office of Spaceflight |, and AAfor
SMA [Associate Administrator for Safety
and Mission Assurance] shall establish,
assess, and document the program re-
quirements for an acceptable life cycle
cumulative prohabilit}' of safe crew and
passenger return. This probability require-
ment can be satisfied through the use of all
available mechanisms including nomincd
mission completion, abort, safe haven, or
crew escape.
2.5.4.2 The cumulative probability of safe crew
and passenger return shall address all
missions planned for the life of the pro-
gram, not just a single space flight system
for a single mission.
The overall probability of crew and passenger survival must
meet the minimum program requirements (as defined in
section 2.5.4.1 ) for the stated life of a space flight systems
program.-' This approach is required to reflect the different
technical challenges and levels of operational risk exposure
on various types t)f missions. For example, low-Earth-orbit
missions represent fundamentally different risks than does
the first mission to Mars. Single-mission risk on the order
of 0.9^ for a beyond-Earth-orbit mission may be acceptable,
but considerably better performance, on the order of 0.9999,
is expected for a reusable low-Earth-orbit design that will
make 100 or more flights.
2.6 Abort and Crew Escape
2.6.1 The capability for rapid crew and occu-
pant egress shall be provided dufi'tg (ill
pre-laimch activities.
2.6.2 The capability for crew and occupant
siu-vival and recover}' shall be provided on
ascent using a combination of abort and
escape.
2.6.3 The capability for crew and occupant
survival and recovery shall be provided
during all other phases of flight (includ-
ing on-orhit, reentry, and landing) using
a combination of abort and escape, un-
less comprehensive .safety and reliability
analyses indicate that abort and escape
capability is not required to meet crew
survival requirenwnts.
2.6.4 Determinations regarding escape and
abort shall be made based upon compre-
hensive .safety and reliabUity analyses
across all mission profiles.
These new requirements focus on general crew survival
rather than on particular crew escape systems. This provides
a logical context for discussions of tradeoffs that will yield
the best crew-survival outcome. Such tradeoffs include
"mass-trades" - for example, an escape system could
add weight to a vehicle, but in the process cause payload
changes that require additional missions, thereby inherently
increasing the overall exposure to risk.
Note that the new requirements for crew escape appear less
prescriptive than Johnson Space Center Requirement 7,
which deals with "safe crew extraction" from pre-launch to
landing. --
In addition, the extent to which NASA's 2003 requirements
will retroactively apply to the Space Shuttle is an open ques-
tion:
The Governing Program Management Council (GPMC)
will determine the applicability of this document to pro-
grams and projects in existence (e.g., heritage expend-
able and reusable launch vehicles and evolved expend-
able launch vehicles), at or beyond implementation, at
the time of the issuance of this document.
Recommendations of the NASA Aerospace Safety
Advisory Panel
The issue of crew escape has long been a matter of con-
cern to NASA's Aerospace Safety Advisory' Panel. In its
2002 Annual Repoil, the panel noted that NASA Program
Guidelines on Human Rating require escape systems for all
flight vehicles, but the guidelines do not apply to the Space
Shuttle. The Panel considered it appropriate, in view of the
Shuttle's proposed life extension, to consider upgrading the
vehicle to comply with the guidelines.-'
Recommendation 02-9: Complete the ongoing .studies
of crew escape design options. Either document the rea-
sons for twt implementing the NASA Program Guide-
lines on Human Rating or expedite the deployment of
such capabilities.
The Board shares the concern of the NASA Aerospace
Safety Advisory Panel and others over the lack of a crew es-
cape system for the Space Shuttle that could cover the wid-
est possible range of flight regimes and emergencies. At the
same time, a crew escape system is just one element to be
optimized for crew survival. Crucial tradeoffs in risk, com-
plexity, weight, and operational utility must be made when
considering a Shuttle escape system. Designs for future ve-
hicles and possible retrofits should be evaluated in this con-
text. The sole objective must be the highest probability of a
crew's safe return regardless if that is due to successful mis-
sion completions, vehicle-intact aborts, safe haven/rescues,
escape systems, or some combination of these scenarios.
Report Volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Finally, a crew escape system cannot be considered sepa-
rately from the issues of Shuttle retirement/replacement,
separation of cargo from crew in future vehicles, and other
considerations in the development - and the inherent risks
of space flight.
Space flight is an inherently dangerous undertaking, and will
remain so for the foreseeable future. While all efforts must
be taken to minimize its risks, the White House, Congress,
and the American public must acknowledge these dangers
and be prepared to accept their consequences.
Observations:
OI0.2-1 Future crewed-vehicle requirements should in-
coiporate the knowledge gained from the Clicil-
leiii>er and Cnluinbiu accidents in assessing the
feasibility of vehicles that could ensure crew
survival even if the vehicle is destroyed.
10.3 Shuhle Engineering Drawings and
Closeout Photographs
In the years since the Shuttle was designed, NASA has not
updated its engineering drawings or converted to computer-
aided drafting systems. The Board's review of these engi-
neering drawings revealed numerous inaccuracies. In par-
ticular, the drawings do not incorporate many engineering
changes made in the last two decades. Equally troubling was
the difficulty in obtaining these drawings: it took up to four
weeks to receive them, and, though some photographs were
available as a short-term substitute, closeout photos took up
to six weeks to obtain. (Closeout photos are pictures taken
of Shuttle areas before they are sealed off for flight.) The
Aerospace Safety Advisory Panel noted similar difficulties
in its 2001 and 2002 reports.
The Board believes that the Shuttle's current engineer-
ing drawing system is inadequate for another 20 years"
use. Widespread inaccuracies, unincorporated engineering
updates, and significant delays in this system represent a
significant dilemma for NASA in the event of an on-orbit
crisis that requires timely and accurate engineering informa-
tion. The dangers of an inaccurate and inaccessible draw-
ing system are exacerbated by the apparent lack of readily
available closeout photographs as interim replacements (see
Appendix D. 15).
Findings:
FIO.3-1 The engineering drawing system contains out-
dated information and is paper-based rather than
computer-aided.
FIO.3-2 The current drawing system cannot quickly
portray Shuttle sub-systems for on-orbit trouble-
shooting.
FIO.3-3 NASA normally uses closeout photographs but
lacks a clear system to define which critical
sub-systems should have such photographs. The
current system does not allow the immediate re-
trieval of closeout photos.
Recommendations:
R 10.3-1 Develop an interim program of closeout pho-
tographs for all critical sub-systems that differ
froiTi engineering drawings. Digitize the close-
out photograph system so that images are imme-
diately available for on-orbit troubleshooting.
R 10.3-2 Provide adequate resources for a long-term pro-
gram to upgrade the Shuttle engineering drawing
system including:
• Reviewing drawings for accuracy
• Converting all drawings to a computer-
aided drafting system
• Incorporating engineering changes
10.4 Industrial Safety and Quality Assurance
The industrial safety programs in place at NASA and its
contractors are robust and in good health. However, the
scope and depth of NASA's maintenance and quality as-
surance programs are troublesome. Though unrelated to the
Coliiiiihia accident, the major deficiencies in these programs
uncovered by the Board could potentially contribute to a
future accident.
Industrial Safety
Industrial safety programs at NASA and its contractors-
covering safety measures "on the shop floor" and in the
workplace - were examined by interviews, observations, and
reviews. Vibrant industrial safety programs were found in ev-
ery area examined, reflecting a common interview comment:
"If anything, we go overboard on safety." Industrial safety
programs are highly visible: they are nearly always a topic
of work center meetings and are represented by numerous
safety campaigns and posters (see Figure 10.4-1 ).
Figure 10.4-1, Safety posters at NASA and contractor facilities.
Report Vdli
AUQUST 2003
CDLU
ACCIDENT INVEST
MBIA
IGATION BDARO
Initiatives like Michoiid's "This is Stupid" program and
the United Space Alliance's "Time Out" cards empower
employees to halt any operation under way if they believe
industrial safety is being compromised (see Figure 10.4-2).
For example, the Time Out program encourages and even
rewards workers who report suspected safety problems to
management.
ASSERTIVE
STATEMENT
OPENING
Gel persons attention
CONCERN
Slate level ot concern
Uneasy'^Very wofned''
PROBLEM
Slate the problem, realoi
perceived
SOLUTION
State your suggested
solution, if you have one
AGREEMENT
Assertively respectfully
ask for their response For
example What do you
Ihink'^ Don't you agree''
When all else fails, use "THIS IS STUPID'"' to
aien PIC and olfiers to potential for incident.
injufv. Of accident
TIME
m
EVERY EMPLOYEE
HAS THE RIGHT
TO CALL A TIME OUT
Figure 10.4-2. The "This is Stupid" card from fhe Michoud Assem-
bly Facility and the "Time Out" card from United Space Alliance.
NASA similarly maintains the Safety Reporting System,
which creates lines of communication through which anon-
ymous inputs are forwarded directly to headquarters (see
Figure 10.4-3). The NASA Shuttle Logistics Depot focus on
safety has been recognized as an Occupational Safety and
Health Administration Star Site for its participation in the
Voluntary Protection Program. After the Shuttle Logistics
Depot was recertified in 2002, employees worked more than
750 days without a lost-time mishap.
Quality Assurance
Quality Assurance programs - encompassing steps to en-
courage error-free work, as well as inspections and assess-
ments of that work - have evolved considerably in scope
over the past five years, transitioning from intensive, com-
prehensive inspection regimens to much smaller programs
based on past risk analysis.
As described in Part Two, after the Space Flight Operations
Contract was established, NASA's quality assurance role
at Kennedy Space Center was significantly reduced. In the
course of this transition. Kennedy reduced its inspections
- called Government Mandatory Inspection Points - by
more than 80 percent. Marshall Space Flight Center cut its
inspection workload from 49,000 government inspection
points and 82 1 ,000 contractor inspections in 1990 to 1 3.700
and 461,000, respectively, in 2002. Similar cutbacks were
made at most NASA centers.
Inspection requirements are specified in the Quality Planning
Requirements Document (also called the Mandatoi^ inspec-
tions Document). United Space Alliance technicians must
document an estimated 730,000 tasks to complete a single
Shuttle maintenance flow at Kennedy Space Center. Nearly
every task assessed as Critical ity Code 1 , I R (redundant), or
2 is always inspected, as are any systems not verifiable by op-
erational checks or tests prior to final preparations for flight.
Nearly everyone interviewed at Kennedy indicated that the
current inspection process is both inadequate and difficult
to expand, even incrementally. One example was a long-
standing request to add a main engine final review before
transporting the engine to the Orbiter Processing Facility for
installation. This request was first voiced two years before
the launch of STS-107, and has been repeatedly denied due
to inadequate staffing. In its place, NASA Mission Assur-
ance conducts a final "informal" review. Adjusting govern-
ment inspection tasks is constrained by institutional dogma
that the status quo is based on strong engineering logic, and
should need no adju.stment. This mindset inhibits the ability
of Quality Assurance to respond to an aging system, chang-
ing workforce dynamics, and improvement initiatives.
The Quality Planning Requirements Document, which de-
fines inspection requirements, was well formulated but is not
routinely reviewed. Indeed, NASA seems reluctant to add or
subtract government inspections, particularly at Kennedy.
Additions and subtractions are rare, and generally occur
only as a response to obvious problems. For instance, NASA
augmented wiring inspections after .STS-93 in 1999. when a
short circuit shut down two of Coliinihia'^ Main Engine Con-
trollers. Interviews confirmed that the current Requirements
Document lacks numerous critical items, but conversely de-
mands redundant and unnecessai^ inspections.
The NASA/United Space Alliance Quality Assurance pro-
cesses at Kennedy are not fully integrated with each other,
with Safety, Health, and Independent Assessment, or with
Engineering Surveillance Programs. Individually, each
plays a vital role in the control and assessment of the Shuttle
as it comes together in the Orbiter Processing Facility and
Vehicle Assembly Building. Were they to be carefully inte-
grated, these programs could attain a nearly comprehensive
quality control process. Marshall has a similar challenge. It
Sat.
nil
m
^^^
^S^^
— =■
""TL^-t^.^
!«.»«..
- — 1
-=.T=
=:==::=r-
-=5—
^ST'^sS^
^M
■=S=.T=
37K:SSr3Sr-
:^=-"--
r-'srrvri^iir-
t —
srr
1 . — .-
,__ —
1
,~:,—
' —
— — -
'
izr-
1 =_== ^1
Figure 10.4-3. NASA Safety Reporting System Form.
Report Volume I
AUBUST 2003
COLUMBIA
ACCIDENT INVESTIGATIDN SDARD
is responsible for managing several different Shuttle sys-
tems through contractors who maintain mostly proprietary
databases, and therefore, integration is limited. The main
engine program overcomes this challenge by being centrally
organized under a single Mission Assurance Division Chief
who reports to the Marshall Center Director In contrast.
Kennedy has a separate Mission Assurance office working
directly for each program, a separate Safety. Health, and In-
dependent Assessment office under the Center Director, and
separate quality engineers under each program. Observing
the effectiveness of Marshall, and other successful Mission
Assurance programs (such as at Johnson Space Center), a
solution may be the consolidation of the Kennedy Space
Center Quality Assurance program under one Mission As-
surance office, which would report to the Center Director.
While reports by the 1986 Rogers Commission, 2000 Shuttle
Independent Assessment Team, and 2003 internal Kennedy
Tiger Team all affirmed the need for a strong and independent
Quality Assurance Program, Kennedy's Program has taken
the opposite tack. Kennedy's Quality Assurance program
discrepancy-tracking system is inadequate to nonexistent.
Robust as recently as three years ago, Kennedy no longer
has a "closed loop" system in which discrepancies and
their remedies circle back to the person who first noted the
problem. Previous methods included the NAS.A Corrective
Action Report, two-way memos, and other tools that helped
ensure that a discrepancy would be addressed and corrected.
The Kennedy Quality Program Manager cancelled these
programs in favor of a contractor-run database called the
Quality Control Assessment Tool. However, it does not
demand a closed-loop or reply deadline, and suffers from
limitations on effective data entry and retrieval.
Kennedy Quality Assurance management has recently fo-
cused its efforts on implementing the International Organiza-
tion for Standardization (ISO) 9000/9(X)l, a process-driven
program originally intended for manufacturing plants. Board
observations and interviews underscore areas where Kenne-
dy has diverged from its Apollo-era reputation of setting the
standard for quality. With the implementation of Internation-
al Standardization, it could devolve further While ISO 9000/
9001 expresses strong principles, they are more applicable
to manufacturing and repetitive-procedure industries, such as
HEX Stomps Recorded FYOl thru FY03 (October 1, 2000 - April 2, 2003)
HEX stomps categori
Figure 10.4-4 Rejecfion, or "Hex" stamps issued from Ocfober
2000 fhrough Apnl 2003.
running a major airline, than to a research-and-development,
non-operational flight test environment like that of the Space
Shuttle. NASA technicians may perform a specific procedure
only three or four times a year, in contrast with their airline
counterparts, who pert'orm procedures dozens of times each
week. In NASA's own words regarding standardization,
"ISO 9001 is not a management panacea, and is never a
replacement for management taking responsibility for sound
decision making." Indeed, many perceive International Stan-
dardization as emphasizing process over product.
Efforts by Kennedy Quality Assurance management to move
its workforce towards a "hands-off, eyes-off " approach are
unsettling. To use a term coined by the 2000 Shuttle In-
dependent Assessment Team Report, "diving catches," or
last-minute saves, continue to occur in maintenance and
processing and pose serious hazards to Shuttle safety. More
disturbingly, some proverbial balls are not caught until af-
ter flight. For example, documentation revealed instances
where Shuttle components stamped "ground test only" were
detected both before and after they had flown. Addition-
ally, testimony and documentation submitted by witnesses
revealed components that had flown "as is" without proper
disposition by the Material Review Board prior to flight,
which implies a growing acceptance of risk. Such incidents
underscore the need to expand government inspections and
surveillance, and highlight a lack of communication be-
tween NASA employees and contractors.
Another indication of continuing problems lies in an opinion
voiced by many witnesses that is confirmed by Board track-
ing: Kennedy Quality Assurance management discourages
inspectors from rejecting contractor work. Inspectors are
told to cooperate with contractors to fix problems rather
than rejecting the work and forcing contractors to resub-
mit it. With a rejection, discrepancies become a matter of
record; in this new process, discrepancies are not recorded
or tracked. As a result, discrepancies are currently not being
tracked in any easily accessible database.
Of the 141,127 inspections subject to rejection from Oc-
tober 2000 through March 2003, only 20 rejections, or
"hexes," were recorded, resulting in a .statistically improb-
able discrepancy rate of .014 percent (see Figure 10.4-4). In
interviews, technicians and inspectors alike confirmed the
dubiousness of this rate. NASA's published rejection rate
therefore indicates either inadequate documentation or an
underused system. Testimony further revealed incidents of
quality assurance inspectors being played against each other
to accept work that had originally been refused.
Findings:
FlO.4-1 Shuttle System industrial safety programs are in
good health.
F 10.4-2 The Quality Planning Requirements Document,
which defines inspection conditions, was well
formulated. However, there is no requirement
that it be routinely reviewed.
F 10.4-3 Kennedy Space Center's current government
mandatory inspection process is both inadequate
and difficult to expand, which inhibits the ability
Report volume I
August 2003
COLUMBIA
ACCIDENT INVESTIGATION HOARD
of Quality Assurance to process improvement
initiatives.
FIO.4-4 Kennedy's quality assurance system encourages
inspectors to allow incorrect work to be corrected
without being labeled "rejected." These opportu-
nities hide "rejections," making it impossible to
determine how often and on what items frequent
rejections and errors occur
Observations:
0 10.4- 1 Perform an independently led, bottom-up review
of the Kennedy Space Center Quality Planning
Requirements Document to address the entire
quality assurance program and its administra-
tion. This review should include development of
a responsive system to add or delete government
mandatory inspections.
01 0.4-2 Kennedy Space Center's Quality Assurance
programs should be consolidated under one
Mission Assurance office, which reports to the
Center Director.
0 1 0.4-3 Kennedy Space Center quality assurance man-
' agement must work with NASA and perhaps
the Department of Defen.se to develop training
programs for its personnel.
0 10.4-4 Kennedy Space Center should examine which
areas of International Organization for Stan-
dardization 9000/9001 truly apply to a 20-year-
old research and development system like the
Space Shuttle.
10.5 Maintenance Documentation
The Board reviewed Coliiinbia's maintenance records for
any documentation problems, evidence of maintenance
fiaw^, or significant omissions, and simultaneously inves-
tigated the organizations and management responsible for
this documentation. The review revealed both inaccurate
data entries and a widespread inability to find and correct
these inaccuracies.
The Board asked Kennedy Space Center and United Space
Alliance to review documentation for STS-107, STS-109,
and Coliiiiihici's most recent Orbiter Major Modification. A
NASA Process Review Team, consisting of 445 NASA engi-
neers, contractor engineers, and Quality Assurance person-
nel, reviewed some 16,500 Work Authorization Documents,
and provided a list of Findings (potential relationships to
the accident). Technical Observations (technical concerns
or process issues), and Documentation Observations (minor
errors). The list contained one Finding related to the Exter-
nal Tank bipod ramp. None of the Observations contributed
to the accident.
The Process Review Team's sampling plan resulted in excel-
lent ob.servations.-'^ The number of observations is relatively
low compared to the total amount of Work Authorization
Documents reviewed, ostensibly yielding a 99.75 percent
accuracy rate. While this number is high, a closer review of
the data reveals some of the system's weaknes.ses. Techni-
cal Observations are delineated into 17 categories. Five of
these categories are of particular concern for mishap pre-
vention and reinforce the need for process improvements.
The category entitled "System configuration could damage
hardware" is listed 1 1 2 times. Categories that deal with poor
incorporation of technical guidance are of particular interest
due to the Board's concern over the backlog of unincorpo-
rated engineering orders. Finally, a category entitled "paper
has open work steps," indicates that the review system failed
to catch a potentially significant oversight 310 times in this
sample. (The complete results of this review may be found
in Appendix D. 14.)
The ciMTent process includes three or more layers of
tnersight before paperwork is scanned into the database.
However, if review authorities are not aware of the most
common problems to look for, corrections cannot be made.
Routine sampling will help refine this process and cut eiTors
significantly.
Observations:
0 1 0.5-1 Quality and Engineering review of work docu-
ments for STS- 1 14 should be accomplished using
statistical sampling to ensure that a representative
sample is evaluated and adequate feedback is
communicated to resolve documentation prob-
lems.
0 1 0.5-2 NASA should implement United Space Alliance's
suggestions for process improvement, which rec-
ommend including a statistical sampling of all
future paperwork to identify recurring problems
and implement corrective actions.
01 0.5-3 NASA needs an oversight process to statistically
sample the work performed and documented by
Alliance technicians to ensure process control,
compliance, and consistency.
10.6 Orbiter Maintenance Down Period/
Orbiter Major Modification
During the Orbiter Major Modification process, Orbiters
are removed from service for inspections, maintenance,
and modification. The process occm^s every eight flights or
three years.
Orbiter Major Modifications combine with Orbiter flows
(preparation of the vehicle for its next mission) and in-
clude Orbiter Maintenance Down Periods (not every Or-
biter Maintenance Down Period includes an Orbiter Major
Modification). The primary differences between an Orbiter
Major Modification and an Orbiter How are the larger num-
ber of requirements and the greater degree of intrusiveness
of a modification (a recent comparison showed 8,702 Or-
biter Major Modification requirements versus 3,826 flow
requirements).
Ten Orbiter Major Modifications have been performed to
date, with an eleventh in progress. They have varied from 6
to 20 months. Because missions do not occur at the rate the
Shuttle Program anticipated at its inception, it is endlessly
challenged to meet numerous calendar-based requirements.
These must be performed regardless of the lower flight
Report Volui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
rate, which contributes to extensive downtime. The Shuttle
Program has explored the possibility of extending Orbiter
Major Modification cycles to once every 12 flights or six
years. This initiative runs counter to the industry norm of
increasing the frequency of inspections as systems age, and
should be carefully scrutinized, particularly in light of the
high-performance Orbiters" demands.
Orbiter Major Modifications underwent a significant
change when they were relocated from the Boeing facil-
ity in Palmdale. California, (where the Orbiters had been
manufactured) to Kennedy Space Center in September
2002. The major impetus for this change was budget short-
ages in Fiscal Years 2002 and 2003. The move capitalizes
on many advantages at Kennedy, including lower labor and
utility costs and more efficient use of existing overhead,
while eliminating expensive, underused, and redundant
capabilities at Palmdale. However, the move also created
new challenges: for instance, it complicates the integration
of planning and scheduling, and forces the Space Shuttle
Program to maintain a fluid workforce in which employees
must repeatedly change tasks as they shift between Orbiter
Major Modifications, flows, and downtime.
Throughout the history of Orbiter Major Modifications, a
major area of concern has been their wide variability in con-
tent and duration. Columbia's last Orbiter Major Modifica-
tion is just the most recent example of overruns due to tech-
nical surprises and management difficulties. It exceeded the
schedule by 186 days. While many factors contributed to
this delay, the two most prominent were the introduction
of a major wiring inspection one month after Orbiter Major
Modification roll-in, and what an internal NASA assess-
ment cited as "poor performance on the parts of NASA.
USA [United Space Alliance], and Boeing."
While the Shuttle Program has made efforts to correct these
problems, there is still much to be done. The transfer to
Kennedy creates a steep learning curve both for technicians
and managers. Planning and scheduling the integration of
all three Orbiters. as well as ground support systems main-
tenance, is critical to limit competition for resources. More-
over, estimating the "right" amount of work required on
each Orbiter continues to be a challenge. For example. 20
modifications were planned for Discovery's modification;
the number has since grown to 84. Such changes introduce
turmoil and increase the potential for mistakes.
An Air Force "benchmarking" visit in June 2003 high-
lighted the need for better planning and more scheduling
stability. It further recommended improvements to the re-
quirements feedback process and incorporating service life
extension actions into Orbiter Major Modifications.
Observations:
01 0.6-1 The Space Shuttle Program Office must make
every effort to achieve greater stability, con-
sistency, and predictability in Orbiter Major
Modification planning, scheduling, and work
standards (particularly in the number of modi-
fications). Endless changes create unnecessary
turmoil and can adversely impact quality and
safety.
0 10.6-2 NASA and United Space Alliance managers
must understand workforce and infrastructure
requirements, match them against capabilities,
and take actions to avoid exceeding thresholds.
01 0.6-3 NASA should continue to work with the U.S. Air
Force, particularly in areas of program manage-
ment that deal with aging systems, service life
extension, planning and scheduling, workforce
management, training, and quality assurance.
01 0.6-4 The Space Shuttle Program Office must deter-
mine how it will effectively meet the challenges
of inspecting and maintaining an aging Orbiter
fleet before lengthening Orbiter Major Mainte-
nance intervals.
10.7 Orbiter Corrosion
Removing and replacing Thermal Protection System tiles
sometimes results in damage to the anti-corrosion primer
that covers the Orbiters' sheet metal skin. Tile replacement
often occurs without first re-priming the primed aluminum
substrate. The current repair practice allows Room Tem-
perature Vulcanizing adhesive to be applied over a bare
aluminum substrate (with no Koropon corrosion-inhibiting
compound) when bonding tile to the Orbiter.
A video borescope of Coliimhia prior to STS-107 found
corrosion on the lower forward fuselage skin panel and
stringer areas. Corrosion on visible rivets and on the sides
and feet of stringer sections was also uncovered during
borescope inspections, but was not repaired.
Other corrosion concerns focus on the area between the
crew module and outer hull, which is a difficult area to ac-
cess for inspection and repair .At present, corrosion in this
area is only monitored with borescope inspections. There is
also concern that unchecked corrosion could progress from
internal areas to external surfaces through fastener holes,
joints, or directly through the skin. If this occurs beneath
the tile, the tile system bond line could degrade.
Long-Term Corrosion Detection
Limited accessibility renders some corrosion damage dif-
ficult to detect. Approximately 90 percent of the Orbiter
structure (excluding the tile-covered outer mold line) can
be inspected for corrosion.-' Corrosion in the remaining 10
percent may remain undetected for the life of the vehicle.
NASA has recently outlined a $70 million, 19-year pro-
gram to assess and mitigate corrosion. The agency fore-
sees inspection intervals based on trends in the Problem
Resolution and Corrective Action database, exposure to
the environment, and refurbishment programs. Develop-
ment of a correlation between corrosion initiation, growth,
and environmental exposure requires the judicious use of
long-term test data. Moreover, some corrosion problems
are uncovered during non-corrosion inspections. The risk
of undetected corrosion may increase as other inspections
are removed or intervals between inspections are extended.
Report volume i
AUBUBT 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Observations:
10.9 Hold-Down Post Cable Anomaly
O10.7-1 Additional and recurring evaluation of corrosion
damage should include non-destructive analysis
of the potential impacts on structural integrity.
01 0.7-2 Long-term corrosion detection should be a fund-
ing priority.
0 1 0.7-3 Develop non-destructive evaluation inspections
to find hidden corrosion.
01 0.7-4 Inspection requirements for coiTOsion due to
environmental exposure should first establish
conosion rates for Orbiter-specific environments,
materials, and structural configurations. Consider
applying Air Force corrosion prevention pro-
grams to the Orbiter.
10.8 BRimE Fracture of A-286 Bolts
Investigators sought to determine the cause of brittle frac-
tures in the A-286 steel bolts that support the wing's lower
earner panels, which provide direct access to the interior of
the Reinforced Carbon-Carbon (RCC) panels. Any misalign-
ment of the carrier panels affects the continuity of airflow
under the, wing and can cause a "rough wing" (see Chap-
ter 4). in the end, 57 of the 88 A-286 bolts on Columbia's
wings were recovered; 22 had brittle fractures. The frac-
tures occurred equally in two groups of bolts in the same
locations on each wing. Investigators determined that liquid
metal embrittlement caused by aluminum vapor created by
G>/»//;/w/'s breakup could have contributed to these fractures,
but the axial loads placed on the bolts when they separated
from the carrier panel/box beam at temperatures approaching
2,000 degrees Fahrenheit likely caused the failures.
Findings:
FIO.8-1 The present design and fabrication of the lower
carrier panel attachments are inadequate. The
bolts can readily pull through the relatively large
holes in the box beams.
FIO.8-2 The current design of the box beam in the lower
carrier panel assembly exposes the attachment
bolts to a rapid exchange of air along the wing,
which enables the failure of numerous bolts.
F 1 0.8-3 Primers and sealants such as Room Temperature
Vulcanizing 560 and Koropon may accelerate
corrosion, particularly in tight crevices.
FlO.8-4 The negligible compressive stresses that normally
occur in A-286 bolts help protect against failure.
Observations:
OI0.8-I Teflon (material) and Molybdenum Disulfide
(lubricant) should not be used in the cairier panel
bolt assembly.
01 0.8-2 Galvanic coupling between aluminum and steel
alloys must be mitigated.
0 1 0.8-3 The use of Room Temperature Vulcanizing 560
and Koropon should be reviewed.
OI0.8-4 Assuring the continued presence of compressive
stresses in A-286 bolts should be part of their ac-
ceptance and qualification procedures.
Each of the two Solid Rocket Boosters is attached to the
Mobile Launch Platform by four "hold down" bolts. A five-
inch diameter restraint nut that contains two pyrotechnic
initiators secures each of these bolts. The initiators sever
the nuts when the Solid Rocket Boosters ignite, allowing
the Space Shuttle stack to lift off. During launch, STS-1 12
suffered a failure in the Hold-Down Post and External Tank
Vent Arm Systems that control the firing of initiators in each
Solid Rocket Booster restraint nut. NASA had been warned
that a recurrence of this type of failure could cause cata-
strophic failure of the Shuttle stack (see Appendix D. 15).
The signal to fire the initiators begins in the General Pur-
pose Computers and goes to both of the Master Events
Controllers on the Orbiter. Master Events Controller 1
communicates this signal to the A system cable, and Master
Events Controller 2 feeds the B system. The cabling then
goes through the T-0 umbilical (that connects fluid and
electrical connections between the launch pad and the
Orbiter) to the Pyrotechnics Initiator Controllers and then
to the initiators. (There are 16 Pyrotechnics Initiator Con-
trollers for Hold Down Post Systems A and B, and four for
the External Tank Vent Arm Systems A and B.) The Hold
Down Post System A is hard-wired to one of the initiators
on each of the four restraint nuts (eight total) while System
B is hard-wired to the other initiator on each nut. The A and
B systems also send a duplicate signal to the External Tank
Vent Arm System. Either Master Events Controller will op-
erate if the other or the intervening cabling fails.
A post-launch review of STS- 1 12 indicated that the System
A Hold-Down Post and External Tank Vent Arm System
Pyrotechnics Initiator Controllers did not discharge. Initial
troubleshooting revealed no malfunction, leading to the
conclusion that the failure was intermittent. A subsequent
investigation recommended the following:
• All T-0 Ground Cables will be replaced after every
flight.
• The T-f) interface to the Pyrotechnics Initiator Con-
trollers rack cable (Kapton) is in redesign.
• All Orbiter T-0 Connector Savers have been re-
placed.
• Pyrotechnic connectors will be pre-screened with pin-
retention tests, and the connector saver mate process
will be verified using videoscopes.
However, prelaunch testing procedures have not changed
and may not be able to identify intermittent failures.
Findings:
F 1 0.9-1 The Hold-Down Post External Tank Vent Arm
System is a Criticality IR (redundant) system.
Before the anomaly on STS- 1 12, and despite
the high-criticality factor, the original cabling
for this system was used repeatedly until it was
visibly damaged. Replacing these cables after ev-
ery flight and removing the Kapton will prevent
bending and manipulation damage.
Report Volui
1ST 2 o o 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
FlO.9-2 NASA is unclear about the potential for damage
if the system malfunctions, oreven if one nut fails
to split. Several program managers were asked:
What if the A system fails, and a B-system initia-
tor fails simultaneously? The consensus was that
the system would continue to burn on the pad or
that the Solid Rocket Booster would rip free of
the pad, causing potentially catastrophic damage
to the Solid Rocket Booster skirt and nozzle ma-
neuvering mechanism. However, they agree that
the probability of this is extremely low.
FlO.9-3 With the exception of STS-112's anomaly, nu-
merous bolt hang-ups. and occasional Master
Events Controller failures, these systems have a
good record. In the early design stages, risk-miti-
gating options were considered, including strap-
ping with either a wire that crosses over the nut
from the A to B side, or with a toggle circuit that
sends a signal to the opposite side when either
initiator fires. Both options would eliminate the
potential of a catastrophic dual failure. However,
they could also create new failure potentials that
may not reduce overall system risk. Today's test
and troubleshooting technology may have im-
proved the ability to test circuits and potentially
prevent intermittent failures, but it is not clear if
NASA has explored these options.
Observation:
0 1 0.9- 1 NASA should consider a redesign of the system,
such as adding a cross-strapping cable, or con-
duct advanced testing for intermittent failure.
10.10 Solid Rocket Booster External Tank
Ahachment Ring
In Chapter 4, the Board noted how NASA's reliance on
"analysis" to validate Shuttle components led to the use
of flawed bolt catchers. NASA's use of this flawed "analy-
sis" technique is endemic. The Board has found that such
analysis was invoked, with potentially dire consequences,
on the Solid Rocket Booster External Tank Attach Ring.
Tests showed that the tensile strength of several of these
rings was well below minimum safety requirements. This
problem was brought to NASA's attention shortly before
the launch of STS-107. To accommodate the launch sched-
ule, the External Tanking Meeting chair, after a cursory
briefing without a full technical review, reduced the Attach
Rings' minimum required safety factor of 1.4 (that is. able
to withstand 1.4 times the maximum load ever expected in
operations) to 1.25. Though NASA has formulated short-
and long-term corrections, its long-term plan has not yet
been authorized.
Observation:
10.11 Test Equipment Upgrades
Visits to NASA facilities (both government and contractor
operated, as well as contractor facilities) and interviews
with technicians revealed the use of 1970s-era oscilloscopes
and other analog equipment. Cuirently available equipment
is digital, and in other venues has proved to be less costly,
easier to maintain, and more reliable and accurate. With the
Shuttle forecast to fly through 2020, an upgrade to digital
equipment would avoid the high maintenance, lack of parts,
and dubious accuracy of equipment cunently used. New
equipment would require certification for its uses, but the
benefit in accuracy, maintainability, and longevity would
likely outweigh the drawbacks of certification costs.
Observation:
0 1 0. 1 1 - 1 Assess NASA and contractor equipment to deter-
mine if an upgrade will provide the reliability and
accuracy needed to maintain the Shuttle through
2020. Plan an aggressive certification program
for replaced items so that new equipment can be
put into operation as soon as possible.
10.12 Leadership/Managerial Training
Managers at many levels in NAS.A., from GS-14 to Associ-
ate Administrator, have taken their positions without fol-
lowing a recommended standard of training and education
to prepare them for roles of increased responsibility. While
NASA has a number of in-house academic training and
career development opportunities, the timing and strategy
for management and leadership development differs across
organizations. Unlike other sectors of the Federal Govern-
ment and the military, NASA does not have a standard
agency-wide career planning process to prepare its junior
and mid-level managers for advanced roles. These programs
range from academic fellowships to civil service education
programs to billets in militai7-sponsored programs, and will
allow NASA to build a strong corps of potential leaders for
future progression.
Observation:
Ol 0.12-1 NASA should implement an agency-wide strat-
egy for leadership and management training
that provides a more consistent and integrated
approach to career development. This strategy
should identify the management and leadership
skills, abilities, and experiences required for each
level of advancement. NASA should continue to
expand its leadership development partnerships
with the Department of Defense and other exter-
nal organizations.
OlO.lO-l NASA should reinstate a safety factor of 1.4 for
the Attachment Rings— which invalidates the
use of ring serial numbers 16 and 15 in their
present state — and replace all deficient material
in the Attachment Rings.
Report Volume I August 20Q3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Endnotes for Chapter 10
The citations that contain a reference to "CAIB document" with CAB or
CTF followed by seven to eleven digits, such as CABOOl-0010, refer to a
document in the Columbia Accident Investigation Board database maintained
by the Department of Justice and archived at the Notional Archives.
' "And stunningly. In as much os this was tragic and horrific through a
loss of seven very important lives, it is amazing that there were no other
collateral damage happened as a result of it. No one else was injured.
All of the "claims hove been very, very minor iri dealing with these issues."
NASA Administrator Sean O'Keefe, testimony before the United States
Senate Committee on Commerce, Science, and Transportation, May 14,
2003.
An intensive search of over a million acres in Texas and Louisiana
recovered 83,900 pieces of Columbia debris weighing a total of 84,900
pounds. (Over 700,000 acres were searched on foot, and 1.6 million
acres were searched with aircraft.) The latitude and longitude was
recorded for more than 75,000 of these pieces. The majority of the
recovered items were no larger than 0.5 square feet. More than 40,000
items could not be positively identified but were classified as unknown
tile, metal, composite, plastic, fabric, etc. Details about the debris
reconstruction and recovery effort are provided in Appendix E.5, S.
Altemis, J. Cowart, W. Woodworth, "STS-107 Columbia Reconstruction
Report," NSTS-60501, June 30, 2003. CAIB document CTF076-
20302182.
The precise probability is uncertain due to many factors, such as the
amount of debris that burned up during re-entry, and the fraction of the
population that was outdoors when the Coiumtia accident occurred.
"User's Guide for Object Reentry Survival Analysis Tool (ORSAT),
Version 5.0, Volume l-Methodology, Input Description, and Results,"
JSC-28742, July 1999; W. Alior, "V/hot Con V/e Learn From Recovered
Debris," Aerospace Corp, briefing presented to CAIB, on March 13,
2003.
"Reentry Survivability Analysis of Delta IV Launch Vehicle Upper Stage,"
JSC-29775, June 2002.
' Anolysis of the recovered debris indicates that relatively few pieces
posed a threat to people indoors. See Appendix D.16.
Detailed information about individual frogments, including weight in
most cases, was not available for the study. Therefore, some engineering
discretion was needed to develop models of individual weights,
dimensions, aerodynamic characteristics, and conditions of impact. This
lack of information increases uncertainty in the accuracy of the final
results. The study should be revisited after the fragment data has been
fully choracterized.
K.M. Thompson, R.F. Rabouw, and R.M. Cooke, "The Risk of Groundling
Fatalities from Unintentional Airplane Crashes," Risk Analysis, Vol. 21,
No. 6, 2001.
" Ibid.
The civil aviation study indicates that the risk to groundlings is significantly
higher in the vicinity of on airport. The overage annual risk of fatality
within 0.2 miles of a busy (top 100) oirport is about 1 in a million.
Thompson, "The Risk of Groundling Fatalities," Code of Federal
Regulations (CFR) 14 CFR Port 415, 415, and 417, "Licensing and Safety
Requirements for Launch: Proposed Rule," Federal Register Vol. 67, No.
146, July 30, 2002, p. 49495.
Code of Federal Regulations (CFR) 14 CFR Part 415 Launch License,
Federal Register Vol. 64, No. 76, April 21, 1999; Range Commanders
Council Standard 321-02, "Common Risk Criteria for Notional Test
Ranges," published by the Secretariat of the RCC U.S. Army White Sands
Missile Range, NM 88002-5110, June 2002; "Mitigation of Orbital
Debris," Notice of Proposed Rulemaking by the Federal Communications
Commission, FCC 02-80, Federal Register Vol. 67, No. 86, Friday, May
3, 2002.
Air Force launch safety standards define a Hazardous Launch Area, a
controlled surface area and airspace, where individual risk of serious
injury from a launch vehicle malfunction during the early phase of
flight exceeds one in a million. Only personnel essential to the launch
operation are permitted in this area. "Eastern and Western Range
Requirements 127-1," March 1995, pp. 1-12 and Fig. 1-6.
Code of Federal Regulations (CFR) 14 CFR Part 431, Launch and Reentry
of a Reusable Launch Vehicle, Section 35 paragraphs (a) and (b).
Federal Register Vol. 65, No. 182, September 19, 2000, p. 56660.
"Reentry Survivability Analysis of Delta IV Launch Vehicle Upper Stage,"
JSC-29775, June 2002.
M. Tobin, "Range Safety Risk Assessments For Kennedy Space Center,"
October 2002. CAIB document CTF059-22802288; "Space Shuttle
Program Requirements Document," NSTS-07700, Vol. I, change no. 76,
Section 5-1. CAIB document CAB024-04120475.
Here, ascent refers to (1) the Orbiter from liftoff to Main Engine Cut Off
(MECO), (2) the Solid Rocket Boosters from liftoff to splashdown, and (3)
the External Tank from liftoff to splashdown.
Pete Cadden, "Shuttle Launch Area Debris Risk," October 2002. CAIB
document CTF059-22682279.
See Dennis R. Jenkins, Space Shuttle: The History of the National Space
Transportation Syslen) - The First TOO Missions (Cope Canaveral,
FL, Specialty Press, 2001), pp. 205-212 for a complete description
of the Approach and Landing Tests and other testing conducted with
Enterprise.
Report of the Presidential Commission on the Space Shuttle Challenger
Accident (Washington; Government Printing Office, 1986).
The pre-declared time period or number of missions over which the
system is expected to operate without major redesign or redefinition.
"A crew escape system shall be provided on Earth to Orbit vehicles for
safe crew extraction and recovery from in-flight failures across the flight
envelope from pre-launch to landing. The escape system shall hove a
probability of successful crew return of 0.99."
Report of the Aerospace Safety Advisory Panel Annual Report for 2002,
(Washington: Government Printing Office, March 2002). CAIB document
CTF014-25882645.
Charlie Abner, "KSC Processing Review Team Final Summary," June 16,
2003. CAIB document CTF063-11801276.
Julie Kramer, et ol., "Minutes from CAIB / Engineering Meeting to
Discuss CAIB Action / Request for Information B 1-0001 93," April 24,
2003. CAIB document CTF042-00930095.
Report Voli
AUBUST 2Q03
Chapter 11
Recommendations
It is the Board's opinion tiiat good leadership can direct
a culture to adapt to new realities. NASA's culture must
change, and the Board intends the following recommenda-
tions to be steps toward effecting this change.
Recommendations have been put forth in many of the chap-
ters. In this chapter, the recommendations are grouped by
subject area with the Retum-to-Flight (RTF] tasks listed
first within the subject area. Each Recommendation retains
its number so the reader can refer to the related section for
additional details. These recommendations are not listed in
priority order.
Part One - The Accident
Thermal Protection System
R3.2-1 Initiate an aggressive program to eliminate all
External Tank Thermal Protection System debris-
shedding at the source with particular emphasis
on the region where the bipod struts attach to the
External Tank. [RTF]
R3.3-2 Initiate a program designed to increase the
Orbiter's ability to sustain minor debris damage
by measures such as improved impact-resistant
Reinforced Carbon-Carbon and acreage tiles.
This program should determine the actual impact
resistance of current materials and the effect of
likely debris strikes. (RTF]
R3.3- 1 Develop and implement a comprehensive inspec-
tion plan to determine the structural integrity of
all Reinforced Carbon-Carbon system compo-
nents. This inspection plan should take advantage
of advanced non-destructive inspection technol-
ogy. [RTF]
R6.4-1 For missions to the International Space Station,
develop a practicable capability to inspect and
effect emergency repairs to the widest possible
range of damage to the Thermal Protection Sys-
tem, including both tile and Reinforced Carbon-
Carbon, taking advantage of the additional capa-
bilities available when near to or docked at the
International Space Station.
For non-Station missions, develop a comprehen-
sive autonomous (independent of Station) inspec-
tion and repair capability to cover the widest
possible range of damage scenarios.
Accomplish an on-orbit Thermal Protection
System inspection, using appropriate assets and
capabilities, early in all missions.
The ultimate objective should be a fully autono-
mous capability for all missions to address the
possibility that an International Space Station
mission fails to achieve the correct orbit, fails to
dock successfully, or is damaged during or after
undocking. [RTF]
R3.3-3 To the extent possible, increase the Orbiter's abil-
ity to successfully re-enter Earth's atmosphere
with minor leading edge structural sub-system
damage.
R3.3-4 In order to understand the true material character-
istics of Reinforced Carbon-Carbon components,
develop a comprehensive database of flown Rein-
forced Carbon-Carbon material characteristics by
destructive testing and evaluation.
R3.3-5 Improve the maintenance of launch pad struc-
tures to minimize the leaching of zinc primer
onto Reinforced Carbon-Carbon components.
R3.8-1 Obtain sufficient spare Reinforced Carbon-Car-
bon panel assemblies and associated support
components to ensure that decisions on Rein-
forced Carbon-Carbon maintenance are made
on the basis of component specifications, free of
external pressures relating to schedules, costs, or
other considerations.
Report voi
COLUMBIA
ACCIDENT INVESIIGATIDN BOARD
R3.8-2 Develop, validate, and maintain physics-based
computer models to evaluate Thermal Protec-
tion System damage from debris impacts. These
tools should provide realistic and timely esti-
mates of any impact damage from possible de-
bris from any source that may ultimately impact
the Orbiter. Establish impact damage thresholds
that trigger responsive corrective action, such as
on-orbit inspection and repair, when indicated.
Imaging
R3.4-I
Upgrade the imaging system to be capable of
providing a minimum of three useful views of
the Space Shuttle from liftoff to at least Solid
Rocket Booster separation, along any expected
ascent azimuth. The operational status of these
assets should be included in the Launch Com-
mit Criteria for future launches. Consider using
ships or aircraft to provide additional views of
the Shuttle during ascent. [RTF]
R3.4-2 Provide a capability to obtain and downlink
high-resolution images of the External Tank
after it separates. [RTF]
R3.4-3 Provide a capability to obtain and downlink
high-resolution images of the underside of the
Orbiter wing leading edge and forward section
of both wings' Thermal Protection System.
[RTF]
R6.3-2 Modify the Memorandum of Agreement with
the National Imagery and Mapping Agency to
make the imaging of each Shuttle flight while on
orbit a standard requirement. [RTF]
Orbiter Sensor Data
R3.6-I
R3.6-2
Wiring
R4.2-2
The Modular Auxiliary Data System instrumen-
tation and sensor suite on each Orbiter should be
maintained and updated to include current sen-
sor and data acquisition technologies.
The Modular Auxiliary Data System should be
redesigned to include engineering performance
and vehicle health information, and have the
ability to be reconfigured during flight in order
to allow certain data to be recorded, telemetered,
or both as needs change.
As part of the Shuttle Service Life Extension
Program and potential 40-year service life,
develop a state-of-the-art means to inspect all
Orbiter wiring, including that which is inacces-
sible.
Bolt Catchers
R4.2-I Test and qualify the flight hardware bolt catch-
ers. [RTF]
Closeouts
R4.2-3 Require that at least two employees attend all
final closeouts and intertank area hand-spraying
procedures, [RTF]
Micrometeoroid and Orbital Debris
R4.2-4 Require the Space Shuttle to be operated with
the same degree of safety for micrometeoroid
and orbital debris as the degree of safety calcu-
lated for the International Space Station. Change
the micrometeoroid and orbital debris safety cri-
teria from guidelines to requirements.
Foreign Object Debris
R4.2-5 Kennedy Space Center Quality Assurance
and United Space Alliance must return to the
straightforward, industry-standard definition of
"Foreign Object Debris" and eliminate any al-
ternate or statistically deceptive definitions like
"processing debris." [RTF]
Part Two - Why the Accident Occurred
Scheduling
R6.2-
Training
R6.3-I
Adopt and maintain a Shuttle flight schedule
that is consistent with available resources.
Although schedule deadlines are an important
management tool, those deadlines must be
regularly evaluated to ensure that any additional
risk incurred to meet the schedule is recognized,
understood, and acceptable. [RTF]
Implement an expanded training program in
which the Mission Management Team faces
potential crew and vehicle safety contingencies
beyond launch and ascent. These contingencies
should involve potential loss of Shuttle or crew,
contain numerous uncertainties and unknowns,
and require the Mission Management Team to
assemble and interact with support organiza-
tions across NASA/Contractor lines and in vari-
ous locations. [RTF]
Report Voll
AU3UST 2003
COLUMBIA
ACCIDENT INVESTIGATION aCARD
Organization
R7.5-I Establish an independent Technical Engineer-
ing Authority that is responsible for technical
requirements and all waivers to them, and will
build a disciplined, systematic approach to
identifying, analyzing, and controlling hazards
throughout the life cycle of the Shuttle System.
The independent technical authority does the fol-
lowing as a minimum:
• Develop and maintain technical standards
for all Space Shuttle Program projects and
elements
• Be the sole waiver-granting authority for
all technical standards
• Conduct trend and risk analysis at the sub-
system, system, and enterprise levels
• Own the failure mode, effects analysis and
hazard reptiiting systems
• Conduct integrated hazard analysis
• Decide what is and is not an anomalous
event
• Independently verify launch readiness
• Approve the provisions of the recertifica-
tion program called for in Recommenda-
tion R9.1-1.
RecerHfication
R9.2-I Prior to operating the Shuttle beyond 2010,
develop and conduct a vehicle recertification at
the material, component, subsystem, and system
levels. Recertification requirements should be
included in the Service Life E.xtension Program.
Closeout Photos/Drawing System
R 10.3-1 Develop an interim program of closeout pho-
tographs for all critical sub-systems that differ
from engineering drawings. Digitize the close-
out photograph system so that images are imme-
diately available for on-orbit troubleshooting.
IRTFl
R 10.3-2 Provide adequate resources for a long-term pro-
gram to upgrade the Shuttle engineering draw-
ing system including:
• Reviewing drawings for accuracy
• Converting all drawings to a computer-
aided drafting system
• Incorporating engineering changes
R7.5-2
The Technical Engineering Authority should be
funded directly from NASA Headquarters, and
should have no connection to or responsibility
for schedule or program cost.
NASA Headquarters Office of Safety and Mis-
sion Assurance should have direct line authority
over the entire Space Shuttle Program safety
organization and should be independently re-
sourced.
R7.5-3 Reorganize the Space Shuttle Integration Office
to make it capable of integrating all elements of
the Space Shuttle Program, including the Or-
biter.
Part Three - A Look Ahead
Organization
R9. 1 - 1 Prepare a detailed plan for defining, establishing,
transitioning, and implementing an independent
Technical Engineering Authority, independent
safety program, and a reorganized Space Shuttle
Integration Office as described in R7..S-1, R7.5-
2, and R7..'S-3. In addition, NASA should submit
annual reports to Congress, as part of the budget
review process, on its implementation activi-
ties. [RTF]
Report Vdi_i
I ST 2 0 0 3
Part Four
Sunrise from STS107 on Flight Day 3
Report Volume I august 2003
CDLUMBiA
ACCIOENT INVESTIGATION BDARO
)SS^S3IS6^SK
Columbia being fransporfed fo Launch Complex 39-A at fhe Kennedy Space Center, Florida^ in preparation for STS-107.
RePORT VOLUME) August 2003
PPENDIX A
The Investigation
A.l Activation of the
Columbia Accident Investigation Board
At 8:59:32 a.m. Eastern Standard Time on Saturday, February'
I. 2003, communication with the Shuttle Columbia was lost.
Shortly after the planned landing time of 9:16 a.m., NASA
declared a Shuttle Contingency and executed the Agency
Contingency Action Plan for Space Flight Operations that
had been established after the Space Shuttle Challenger ac-
cident in January 1986. As part of that plan, NASA Adminis-
trator Sean G'Keefe deployed NASA's Mishap Investigation
Team, activated the Headquarters Contingency Action Team,
and, at 10:30 a.m., activated the International Space Station
and Space Shuttle Mishap Interagency Investigation Board.
The International Space Station and Space Shuttle Mishap
Interagency Investigation Board is designated in Appendix
D of the Agency Contingency Action Plan as an external
investigating board that works to uncover the "facts, as well
as the actual or probable causes of the Shuttle mishap" and
to '"recommend preventative and other appropriate actions
to preclude the recurrence of a similar mishap."' The Board
is composed of seven members and is chartered with provi-
sions for naming a Chairman and additional members. The
seven members take their position on the Board because
they occupy specific government posts. At the time of the
accident, these individuals included:
• Chief of Safety, U.S. Air Force: Major General Kenneth
W. Hess
• Director, Office of Accident Investigation, Federal
Aviation Administration: Steven B. Wallace
• Representative, U.S. Air Force Space Command: Briga-
dier General Duane W. Deal
• Commander, Naval Safety Center: Rear Admiral Ste-
phen A. Turcotte
• Director, Aviation Safety Division, Volpe National
Transportation Systems Center, Department of Trans-
portation: Dr. James N. Hallock
• Representative, U.S. Air Force Materiel Command:
Major General John L. Barry
• Director, NASA Field Center or NASA Program Asso-
ciate Administrator (not related to mission): Vacant
Upon activating the Board, Administrator O'Keefe named
Admiral Harold W. Gehman Jr., United States Navy (re-
tired), as its Chair, and G. Scott Hubbard, Director of NASA
Ames Research Center, as the NASA Field Center Director
representative. In addition to these eight voting members,
contingency procedures provided for adding two non-vot-
ing NASA representatives, who helped establish the Board
during the first weeks of activity but then returned to their
regular duties. They were Bryan D. O'Connor. NASA A.sso-
ciate Administrator for Safety and Mission Assurance, who
served as an ex-officio Member of the Board, and Theron
M. Bradley Jr.. NASA Chief Engineer, who served as the
Board's Executive Secretary. Upon the Board's activation,
two NASA officials, David Lengyel and Steven Schmidt,
were dispatched to provide for the Board's administra-
tive needs. J. William Sikora, Chief Counsel of the Glenn
Research Center in Cleveland, Ohio, was assigned as the
counsel to the Board.
By noon on February 1 , NASA officials notified most Board
members of the mishap and issued tentative orders for the
Board to convene the next day at Barksdale Air Force Base
in Shreveport, Louisiana, where the NASA Mishap Investi-
gation Team was coordinating the .search for debris. At 5:00
p.m., available Board members participated in a teleconfer-
ence with NASA's Headquarters Contingency Action Team.
During that teleconference, Gehman proposed that the
International Space Station and Space Shuttle Mishap Inter-
agency Investigation Board be renamed the Columbia Acci-
dent Investigation Board. O'Keefe accepted this change and
fomially chartered the Board on Sunday, February 2, 2003.
On Sunday, Board members flew on government and com-
mercial aircraft to Barksdale Air Force Base, where at 6:50
p.m. Central Standard Time the Board held its first official
meeting. The Board initiated its investigation on Monday,
February 3, at 8:00 a.m. Central Standard Time. On Tuesday
morning, February 4, the Board toured the debris field in
and around Nacogdoches, Texas, and observed a moment
of silence. On Thursday, February 6, the Board relocated to
the Johnson Space Center, eventually settling into its own
offices off Center grounds. That evening, the Board formally
relieved the NASA Headquarters Contingency Action Team
Report Vduui
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
of its interim responsibilities for initial accident investiga-
tion activities. The Board assumed operational control of
the debris search and recovery efforts from NASA's Mishap
Investigation Team, which functioned under the Board's di-
rection until the completion of the search in early May.
A. 2 Board Charter and
Organization
During meetings that first week. Chairman Gehman and the
Board proposed that its charter be rewritten. The original
charter, derived from Appendix D of NASA's Contingency
Action Plan, had a number of internal inconsistencies and
provisions that the Board believed would impede the execu-
tion of its duties. Additionally, the Board was not satisfied
that its initial charter adequately ensured independence from
NASA. The Board resolved to:
• Have its own administrative and technical staff so that
it could independently conduct testing and analysis and
establish facts and conclusions
• Secure an adequate and independent budget to be over-
seen by the Board Chairman
• Establish and maintain records independent from NASA
recoi'ds
• Empower the Board Chairman to appoint new Board
Members
• Provide the public with detailed updates on the progress
of its investigation through frequent public hearings,
press briefings, and by immediately releasing all signifi-
cant information, with the exception of details relating
to the death of the crew members and privileged witness
statements taken under the condition of confidentiality
• Simultaneously release its report to Congress, the White
House, NASA, the public, and the astronauts' families
• Allow Board members to voice any disagreements with
Board conclusions in minority reports
With the full cooperation of Administrator O'Keefe, the
Board's charter was rewritten to incorporate these prin-
ciples. The new charter, which underwent three drafts, was
signed and ratified by O'Keefe on Februai7 18, 2003. In
re-chartering the Board, O'Keefe waived the requirements
specified in the Contingency Action Plan that the Board use
standard NASA mishap investigation procedures and instead
authorizeti the Board to pursue "whatever avenue you deem
appropriate" to conduct the investigation.^
Additional Board Members
To manage its burgeoning investigative responsibilities, the
Board added additional members, each of whom brought to
the Board a needed area of expertise. On February 6, the
Board appointed Roger E. Tetrault, retired Chairman and
Chief Executive Officer of McDermott International. On
February 15, the Board appointed Sheila E. Widnall, Ph.D.,
Institute Professor and Professor of Aeronautics and Astro-
nautics at the Massachusetts Institute of Technology and
former Secretary of the Air Force. On March 5, the Board
appointed Douglas D. Osheroff, Ph.D., Nobel Laureate in
Physics and Chair of the Stanford Physics Department; Sally
K. Ride, Ph.D., Professor of Space Science at the University
of California at San Diego and the nation's first woman in
space; and John M. Logsdon, Ph.D., Director of the Space
Policy Institute at George Washington University. This
brought the total number of Board members to 13, coinci-
dental ly the same number as the Presidential Commission
on the Space Shuttle Cluillciiiier Accident.
Board OrganizaHon
In the first week, the Board divided into four groups, each of
which addressed separate areas of the investigation. Group
I, consisting of General Barry, General Deal, and Admiral
Turcotte, examined NASA management and treatment of
materials, including Shuttle maintenance safety and mis-
sion assurance. Group II, consisting of General Hess. Mr.
Wallace, and later Dr. Ride, scrutinized NASA training,
operations, and the in-flight performance of ground crews
and the Shuttle crew. Group III, consisting of Dr. Hallock,
Mr. Hubbard, and later Mr. Tetrault, Dr. Widnall, and Dr.
Osheroff, focused on engineering and technical analysis of
the accident and resulting debris. Group IV, consisting of Dr.
Logsdon, Dr. Ride, and Mr. Hubbard, examined how NASA
history, budget, and institutional culture affected the opera-
tion of the Space Shuttle Program. Each group, with the ap-
proval of the Chairman, hired investigators and supprart staff
and collaborated extensively with one another.
The Board also organized an internal staff of technical ex-
perts called the Independent Assessment Team. Under the
leadership of .lames Mosquera, a senior nuclear engineer
with the U. S. Navy, the Independent Assessment Team ad-
vised the Board when and where NASA analysis should be
independently verified and, when needed, conducted fully
independent tests on the Board's behalf.
A. 3 Investigation Process and Scope
Decision to Pursue a Safety Investigation
During the first week of its investigation, the Board reviewed
the stiTJCture and methodology of the Presidential Commis-
sion on the Space Shuttle Challenger Accident, the Interna-
tional Civil Aviation Organization standards used by the Na-
tional Transportation Safety Board and the Federal Aviation
Administration, and the accident investigation models under
which the U.S. Air Force and Navy Safety Centers operate.
Rather than assign formal blame or determine legal liability
for the cause of the accident, the Board affirmed its charge to
pursue both an accident investigation and a safety investiga-
tion, the primary aim of which would be to identify and cor-
rect threats to the safe operation of the Space Shuttle.
The Use of Privileged Witness Statements
With a principal focus on identifying and correcting threats
to safe operations, safety investigations place a premium on
obtaining full and complete disclosure about every aspect of
an accident, even if that information may prove damaging
or embarrassing to particular individuals or organizations.
However, individuals who have made mistakes, know of
negligence by others, or suspect potential flaws in their or-
ganizations are often afraid of being fired or even prosecuted
r s T 2 a D 3
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
if they speak out. To allay these fears, which can prevent the
emergence of information that could save lives in the future,
many safety investigations, including those by NASA and
by the Air Force and Navy Safety Centers, grant witnesses
complete confidentiality, as do internal affairs investigations
by agency Inspector Generals. This confidentiality, which
courts recognize as "privileged communication," allows
witnesses to volunteer information that they would not
otherwise provide and to speculate more openly about their
organizations' flaws than they would in a public forum.
Given the stakes of the Columbia accident investigation, the
most important being the lives of future astronauts, the Board
decided to extend witnesses confidentiality, even though this
confidentiality would necessitate that investigators redact
some witness information before releasing it to the public.
Consistent with NASA Safety Program policy NPD 862 1 . 1 H
Para I .j, statements made to Board investigators under privi-
lege were not made under legal oath. Investigators recorded
and then transcribed interviews, with those interviewed af-
firming by their signatures the accuracy of the transcripts.
The Board took extraordinary' measures to ensure that
privileged witness statements would remain confidential by
restricting access to these statements to its 13 members and
a small number of authorized support staff. Witness state-
ments and information derived from them are exempt from
disclosure under the Freedom of Information Act.
The existence of a safety investigation in which privileged
statements are taken does not prevent an accounting of per-
sonal responsibility associated with an accident. It merely
means that such an accounting must result from a separate
investigation, in this instance, that responsibility has been
left to the NASA administration and the Congressional com-
mittees that oversee the agency. To facilitate this separate
investigation, the Board pledged to notify NASA and Con-
gress if evidence of criminal activity or willful negligence is
found in privileged statements or elsewhere. Additionally,
the Board opened all its files to Congressional representa-
tives, with the exception of privileged witness statements.
Limited Congressional access to these statements is gov-
erned by a special written agreement between the oversight
committees and the Board that preserves the Board's obliga-
tion to witnesses who have entrusted them with information
on the condition of confidentiality.
Expanded Bounds of Board Investigation
Throughout the investigation, Chairman Gehman consulted
regularly with members of Congress and the Administration
tf) ensure that the Board met its responsibilities to provide
the public with a full and open accounting of the Colitmhia
accident. At the request of Congressional Oversight Com-
mittees, the Board significantly expanded the scope of its
investigation to include a broad review of the Space Shuttle
Program since its inception. In addition to establishing the
accident's probable and contributing cau.ses, the Board's re-
port is intended to serve as the basis for an extended public
policy debate over the future course of the Space Shuttle
Program and the role it will play in the nation's manned
space flight program.
A. 4 Board Policies and Procedures
Authorizing Investigators
To maintain control over the investigation process, the Chair-
man established a system of written authorizations specify-
ing individuals who were sanctioned to interview witnesses
or perform other functions on behalf of the Board.
Consideration of Federal Advisory Committee Act
Statutes
Not long after its activation, and well before adding addi-
tional members, the Board considered the applicability of
the Federal Advisory Committee Act.' This statute requires
advisory committees established by the President or a fed-
eral agency to provide formal public notice of their meet-
ings as well as public access to their deliberations. In con-
trast to most committees governed by the Federal Advisory
Committee Act. which meet a few times per year, the Board
intended from the outset to conduct a full-time, fast-paced
investigation, in which Board members themselves were
active investigators who would shape the investigation's
direction as it developed. The Board concluded that the
formalities required by the Federal Advisory Committee
Act are not compatible with the kind of investigation it was
charged to complete. Nor did the Board find the Federal
Advisoiy Committee Act statutes compatible with exercis-
ing operational responsibility for more than a hundred staff
and thousands of debris searchers.
Though the Federal Advisory Committee Act did not apply
to the Board's activities, the Board resolved to be faithful to
the standards of openness the .Act embodies. The Board held
frequent press briefings and public hearings, released all sig-
nificant findings immediately, and maintained a telephone
hotline and a Web site, where users accessed Web pages
more than 40,000,000 times. The Board also processed
Freedom of Infonnation Act requests according to proce-
dures established in 14 C.F.R. Section 1206.
Board Members as Federal Employees
The possibility of litigation against Board members for
their actions while on the Board, especially becau.se the
Space Flight Operations Contract would be a subject of
investigation, made it necessary to bring Board Members
within the protections that the Federal Tort Claims Act af-
fords to federal employees. This and other considerations
led the Board Chairman to determine that the Board should
consist of full-time federal employees. As the Chairman
named new Board members, the NASA Administrator hon-
ored the Board's determination and deemed them full-time
federal employees.
Oversight of Board Activities
To ensure that the Board acted in an independent and unbi-
a,sed manner in its investigation, the NASA Inspector Gener-
al was admitted on request to any Board proceeding, except
those involving privileged witness statements. The Board
also allowed Congressional access to the Board's databases
Report Vdui
IT 2 o o 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
and offices in Houston and Washington, D.C., with special
restrictions that preserved the integrity and confidentiality of
privileged witness statements.
Financial Independence
To ensure the Board's financial independence, NASA estab-
lished a separate operating budget for the Board's activities.
This fund provided for Board operating expenses, including
extensive testing and analysis and the acquisition of services
by support staff and technical experts. With the exception
of Chairman Gehman, whose salary was paid by the Office
of Personnel Management, and those Board members who
were already federal government or military employees.
Board members were compensated by Congressionally ap-
propriated funds administered by NASA.
Board Staffing and Administrative Support
Through a Government Services Administration-supervised
bidding process, Valador, Inc., a service-disabled-veteran-
ovvned professional services contractor, was selected to
provide the Board's administrative and technical support.
Under a Mission Operation and Business Improvement
Systems contract, Valador arranged for the Board's support
staff, technical experts, and information technology needs,
including the Board Web site, http://viu\c.(<//7>.;/.s. Valador
also supported the Board's public hearings, press confer-
ences, the public-input database, and the publication of the
final report.
The Board was aided by public affairs officers; a budget
manager; representatives from the National Transportation
Safety Board, Federal Emergency Management Agency,
Department of Defense, and the Department of Justice Civil
Division, Office of Litigation Support; and Dr. James B.
Bagian, an astronaut flight surgeon assigned from the De-
partment of Veterans Affairs who worked with the NASA
medical staff. Armed Forces Institute of Pathology, and the
local medical examiner. A complete list of staff and consul-
tants appears in Appendix B.2 and B.3.
Public Inputs
The Board established a system for inputs from the public
that included a 24-hour hotline, mailing address, and online
comment form linked to the Board's Web site. This enabled
the submission of pheitographs, comments, technical papers,
and other materials by the public, some of whom made sub-
missions anonymously. Board staff logged every input into
a database. To establish the relevance of every phone call,
letter, e-mail, or online comment, investigators evaluated
their significance and, if appropriate, followed up with the
submitters. Of the 3,0(X) submissions the Board received,
more than 750 resulted in actions by one of the Board's
four investigative sub-groups, the Independent Assessment
Team, or other Board staff.
Office of Governmental Affairs
As inquiries from Congress grew and the need to keep
the Executive and Legislative branches updated on the
investigation's progress became clear, the Board opened an
Office of Governmental Affairs. Based in Washington, D.C.,
it served as the Board's liaison to the White House, depart-
ments within the Executive Branch, Congressional Oversight
Committees, and members of Congress and their staffs. The
office conducted numerous briefings, responded to Congres-
sional inquiries, and ensured that the investigation met the
needs of the Congressional Oversight Committees that plan
to use the Board's report as the basis for a public policy de-
bate on the future of the Space Shuttle Program.
A. 5 Investigation Interface with NASA
NASA mobilized hundreds of personnel to directly support
the Board's investigation on a full-time basis. Initially, as
part of the Contingency Action Plan activated on February
I, the Mishap Investigation Team went to Barksdale Air
Force Base to coordinate the search for debris. NASA then
deployed a Mishap Response Team to begin an engineering
analysis of the accident. These groups consisted of Space
Shuttle Program personnel and outside experts from NASA
and contractor facilities.
As prescribed by its charter, the Board coordinated its in-
vestigation with NASA through a NASA Task Force Team,
later designated the Columbia Task Force. This group was
the liaison between the Board and the Mishap Response
Team. As the investigation progressed, NASA modified the
organizational structure of the Mishap Response Team to
more clo.sely align with Board structure and investigative
paths, and NASA renamed it the NASA Accident Investiga-
tion Team. This team supported the Board's investigation,
along with thousands of other NASA and contract personnel
who worked in the fault tree teams described in Chapter 4
and on the debris search efforts described in Chapter 2.
Documents and Actions Requested From NASA
The close coordination of the NASA Investigation Team with
the Board's sub-groups required a system for tracking docu-
ments and actions requested by the investigation. The Board
and the Columbia Task Force each appointed representatives
to track documents and manage their configuration.
Board investigators submitted more than 600 requests for
action or information from NASA. Requests were submitted
in writing, on a standardized form,^ and signed by a Board
member. Only Board members were authorized to sign such
requests. Each request was given a priority and tracked in a
database. Once answered by Columbia Task Force person-
nel, the Board member who submitted the request either
noted by signature that the response was satisfactory or re-
submitted the request for further action.
Reassignment of Certain NASA Personnel Involved
in STS-107
On February 25, 2003, Chairman Gehman wrote to NASA
Administrator O'Keefe, asking that he "reassign the top
level Space Shuttle Program management personnel who
were involved in the preparation and operation of the flight
of .STS-107 back to their duties and remove them from di-
2 3 4
Report Volume I August 2003
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
rectly managing or supporting the investigation."^ This letter
expressed the Board's desire to prevent actual or perceived
conflicts of interest between NASA personnel and the inves-
tigation. In response, O'Keefe reassigned several members
of NASA's Columbia Task Force and Mishap Investigation
Team and reorganized it along the same lines as the Board's
groups. Additionally. Bryan O'Connor, an Ex-Officio Mem-
ber to the Board, and Theron Bradley Jr., the Board's Execu-
tive Secretary, returned to their respective duties as Associate
Administrator for Safety and Mission Assurance and Chief
Engineer, and were not replaced. After O'Connor's depar-
ture. Colonel (Selectee) Michael J. Bloomfield, an active
Shuttle Commander and the lead training astronaut, joined
the Board as a representative from the Astronaut Office.
Handling of Debris and Impounded Materials
To ensure that all material associated with Columbia's mis-
sion was preserved as evidence in the investigation. NASA
officials impounded data, software, hardware, and facilities
at NASA and contractor sites. At the Johnson Space Center
in Houston, Texas, the door to the Mission Control Center
was locked while flight control personnel created and ar-
chived backup copies of all original mission data and took
statements from Mission Control personnel. .At the Ken-
nedy Space Center in Florida, mission facilities and related
hardware, including Launch Pad Complex 39-A, were put
under guard or stored in secure warehouses. Similar steps
were taken at other key Shuttle facilities, including the Mar-
shall Space Flight Center in Huntsville, Alabama, and the
Michoud Assembly Facility near New Orleans, Louisiana.
Impounded items and data were released only when the
Board Chairman approved a formal request from the NASA
Columbia Task Force.
Similarly, any testing performed on Shuttle debris was ap-
proved by the Board Chairman only after the Columbia Task
Force provided a written request outlining the potential ben-
efits of the testing and addressing any possible degradation of
the debris that could affect the investigation. When testing of
Shuttle debris or hardware occurred outside the secure debris
hanger at the Kennedy Space Center, investigation personnel
escorted the debris for the duration of the testing process or
otherwise ensured the items' integrity and security.
A. 6 Board Documentation System
The Columbia Accident Investigation Board
Database Server
The sheer volume of documentation and research generated
in the investigation required an electronic repository capable
of storing hundreds of thousands of pages of technical in-
formation, briefing charts, hearing transcripts, government
documents, witness statements, public inputs, and corre-
spondence related to the Coltimhia accident.
For the first few months of its investigation, the Board used
the Process-Based Mission Assurance (PBMA) system
for many of its documentation needs. This Web-based ac-
tion tracking and document management system, which is
hosted on a server at the NASA Glenn Research Center,
was developed and maintained by NASA Ames Research
Center. The PBMA system was established as a repository
for all data provided by NASA in response to the Board's
Action/Request for Information process. It contained all in-
formation produced by the Columbia Task Force, as well as
reports from NASA and other external groups, presentations
to the Board, signed hardware release and test release forms,
images, and schedule information.
However, the PBMA system had several critical limita-
tions that eventually compelled the Board to establish its
own server and databases. First. NASA owned the Mission
Assurance system and was responsible for the documents
it produced. The Board, seeking to maintain independence
from NASA and the Columbia Task Force, found it unac-
ceptable to keep its documentation on what was ultimately a
NASA database. Second, the PBMA system is not full-text
searchable, and did not allow investigators to efficiently
cross-reference documents.
The Board wanted access to all the documents produced by
the Columbia Task Force, while simultaneously maintaining
its own secure and independent databases. To accomplish
this, the Board secured the assistance of the Department of
Justice Civil Division, Office of Litigation Support, which
established the Columbia Accident Investigation Board Da-
tabase Server This server provided access to four document
databases:
• Columbia Task Force Database: all the data in NASA's
Process-Based Mission Assurance system, though inde-
pendent from it.
• Columbia Accident Investigation Board Document Da-
tabase: all documents gathered or generated by Board
members, investigators, and support staff.
• Interview Database: all transcriptions of privileged wit-
ness interviews.
• Investigation Meeting Minutes Database: text of ap-
proved Board meeting minutes.
Although the Board had access to the Process-Based Mis-
sion Assurance system and therefore every document cre-
ated by the Columbia Task Force, the Task Force did not
have access to any of the Board's documents that were
independently produced in the Board's four other databases.
A security system allowed Board members to access these
databases through the Board's Database Server using confi-
dential IDs and passwords. In total, the Columbia Accident
Investigation Board Database Server housed more than
450,000 pages that comprised more than 75,000 documents.
The bulk of these are from NASA's Columbia Task Force
Document Database, which holds over 45,000 documents
totaling 270,000 pages.
To ensure that all documents received and generated by
individual investigators became part of the permanent Co-
lumbia Accident Investigation Board archive. Department
of Justice contractors had coordinators in each investigative
group who gathered electronic or hard copies of all relevant
investigation documents for inclusion in the Columbia
Accident Investigation Board Document Database. Every
page of hard copy received a unique tracking number, was
REPORT Volume i
IBUST 2D03
COLUMBIA
ACCIDENT INVESTIGATION BOARD
imaged, converted to a digital format, and loaded onto the
server. Documents submitted electronically were saved in
Adobe PDF format and endorsed with a tracking number
on each page. Where relevant, these document numbers are
referenced in citations found in this report. The Columbia
Accident Investigation Board Document database contains
more than 30,000 documents comprising 1 80,000 pages.
Other significant holdings on the Columbia Accident In-
vestigation Board Document Database Server include the
interview Database, which holds 287 documents compris-
ing 6. .300 pages, and the Investigative Meeting Minutes
Database, which holds 72 documents totaling 598 pages.
Concordance
Acting on the recommendation of the Department of Justice,
the Board selected Concordance as the software to manage
all the electronic documents on the Columbia Accident
Investigation Board Database Server. Concordance is a
full-text, image-enabled document and transcript database
accessible to authorized Board members on their office com-
puters. Concordance allowed the Board to quickly search the
data provided by the Columbia Task Force, as well as any
documents created and stored in the four other databases.
The Concordance application was on a server in a secure
location in the Board office. Though connected to the John-
son Space Center backbone, it was exclusively managed and
administered by the Department of Justice and contract staff
from Aspen Systems Corporation. Department of Justice
and contract staff trained users to search the database, and
performed searches at the request of Board members and
investigators. The Department of Justice and contract staff
also assisted Congressional representatives in accessing the
Columbia Accident Investigation Board Database Server.
Investigation Database Tools
In addition to these databases, several information manage-
ment tools aided the Board's investigation, deliberation, and
report writing.
Group Systems
Group Systems is a collaborative software tool that orga-
nizes ideas and information by narrowing in on key issues
and possible solutions. It supports academic, government,
and commercial organizations worldwide. The Board used
Group Systems primarily to brainstorm topics for inclusion
in the report outline and to classify information related to
the accident.
Investigation Organizer
Investigation Organizer is a Web-based pre-decisional
management and modeling tool designed by NASA to sup-
port mishap investigation teams. Investigation Organizer
provides a central information repository that can be used
by investigation teams to store digital products. The Board
used Investigation Organizer to connect data from various
sources to the outline that guided its investigation. Inves-
tigation Organizer was developed, maintained, and hosted
by NASA Ames Research Center. Access to Board files on
Investigation Organizer was restricted to Board members
and authorized staff.
Tech Doc
The Board drafted its final report with the assistance of
Tech Doc, a secure Web-based file management program
that allowed the 13 Board members and the editorial staff
to comment on report drafts. TechDoc requires two-factor
authentication and is certified to store sensitive Shuttle engi-
neering data that is governed by the International Traffic in
Amis Reduction Treaty.
Official Photographer
The Board employed an official photographer, who took
more than 5,000 digital images. These photographs, many
of which have been electronically edited, document Board
members and support staff at work in their offices and in the
field in Te.xas, Florida, Alabama, Louisiana, and Washing-
ton, D.C.; at Shuttle debris collection, analysis, and testing;
and at public hearings, press briefings, and Congressional
hearings. Images captured by NASA photographers relevant
to the investigation are available through NASA's Public
Affairs Office.
National Archives and Records Administration
All appropriate Board documentation and products will be
stored for submission to the National Archives and Records
Administration, with the exception of documents originating
in the Process-Based Mission Assurance system, which will
be archived by NASA under standard agency procedures.
Representatives of the Board will review all documentation
prior to its transfer to the National Archives to safeguard
privacy and national security. This preparation will include a
review of all documents to ensure compliance with the Free-
dom of Infomiation Act. the Trade Secrets Act, the Privacy
Act, the International Traffic in Arms Reduction Treaty, and
Export Administration Regulations. To gain access to the
Board's documents, requests can be made to:
National Archives and Records Administration
Customer Services Division (NWCC)
Room 2400
8601 Adelphi Road
College Park, MD 20740-601 1
The National Archives and Records Administration can be
contacted at 301.837.3130. More infomiation is available at
http://www.nara.gov.
Report volui
lOUBT 2003
A. 7 List of Public Hearings
COLUMBIA
ACCIDENT INVESTIGATIQN BOARD
The Board held public hearings to listen to and question expert witnesses. A list of these hearings, and the participating wit-
nesses, follows; transcripts of the hearings are available in Appendix G.
March 6, 2003 Houston, Texas
Review of NASA's Organizational Structure and Recent Space Shuttle History
Lt. Gen. Jefferson D. Howell, Jr. Director. NASA Johnson Space Center
Mr Ronald D. Dittemore, Manager. Space Shuttle Program
Mr Keith \. Chong. Engineer. Boeing Corporation
Dr Harry McDonald, Professor, University of Tennessee
March 17, 2003, Houston, Texas
Columbia Re-entry Telemetry Data, and Debris Dispersion Timeline
Mr Paul S. Hill, Space Shuttle and International Space Station Flight Director, NASA Johnson Space Center
Mr R. Douglas White. Director for Operations Requirements. Orbiter Element Department. United Space Alliance
Prior Orbital Debris Re-entry Data
Dr. William H. Ailor. Director, Center for Orbital and Re-entry Debris Studies, The Aerospace Corporation
March 18, 2003, Houston, Texas
Aero and Thermal Analysis of Columbia Re-entry Data
Mr Jose M. Caram. Aerospace Engineer. Aeroscience and Flight Mechanics Division. NASA Johnson Space Center
Mr Steven G. Labbe. Chief, Applied Aeroscience and Computational Fluid Dynamics Branch, NASA Johnson Space Center
Dr. John J. Bertin, Professor of Aerodynamics, United States Air Force Academy
Mr Christopher B. Madden. Deputy Chief. Thermal Design Branch, NASA Johnson Space Center
March 25, 2003, Cape Canaveral, Florida
Launch Safety Considerations
Mr Roy D. Bridges, Jr, Director. Kennedy Space Center
Role of the Kennedy Space Center in the Shuttle Program
Mr William S. Higgins, Chief of Shuttle Processing Safety and Mission Assurance Division. Kennedy Space Center
Lt. Gen. Aloysius G. Casey. U.S. Air Force (Retired)
March 26, 2003, Cape Canaveral, Florida
Debris Collection, Layout, and Analysis, including Forensic Metallurgy
Mr Michael U. Rudolphi. Deputy Director, Stennis Space Center
Mr Steven J. Altemus, Shuttle Test Director, Kennedy Space Center
Dr Gregory T A. Kovacs, Associate Professor of Electronics, Stanford University
Mr G. Mark. Tanner, Vice President and Senior Consulting Engineer, Mechanical & Materials Engineering
April 7, 2003, Houston, Texas
Post-Flight Analysis, Flight Rules, and the Dynamics of Shedding Foam from the External Tank
Col. James D. Halsell, Jr. U.S. Air Force. NASA Astronaut. NASA Johnson Space Center
Mr. Robert E. Castle. Jr, Chief Engineer. Mission Operations Directorate. NASA Johnson Space Center
Mr J. Scott Sparks, Department Lead, External Tank issues, NASA Marshall Space Flight Center
Mr Lee D. Foster, Technical Staff. Vehicle and Systems Development Department, NASA Marshall Space Flight Center
— ^^^— ^^^— ^^^— — — — — — — — Repout Volume I Auoust 2003 __________^__— — — — 2 3 7
COLUMBIA
ACCIDENT INVESTIGATION BOARD
April 8, 2003, Houston, Texas
Shuttle Safety Concerns, Upgrade Issues, and Debris Strikes on the Orbiter
Mr. Richard D. Blomberg, Former Chairman, NASA Aerospace Safety Advisory Panel
Mr. Daniel R. Bell, Thermal Protection System Sub-System Manager for the Boeing Company at Kennedy Space Center
Mr. Gary W. Grant. Systems Engineer in the Thermal Management Group for the Boeing Company at Kennedy Space Center
April 23, 2003, Houston, Texas
Tradeoffs Made During the Shuttle's Initial Design and Development Period
Dr. Milton A. Silveira. Technical Advisor to the Program Director, Missile Defense Agency, Office of the Secretary of Defense
Mr. George W. Jeffs, Retired President of Aerospace and Energy Operations. Rockwell International Corporation
Prof. Aaron Cohen, Professor Emeritus of Mechanical Engineering, Texas A&M University
Mr. Owen G. Morris, Founder, CEO, and Chairman of Eagle Aerospace, Inc.
Mr. Robert F. Thompson, former Vice President of the Space Station Program for McDonnell Douglas
Managing Aging Aircraft
Dr. Jean R. Gebman. Senior Engineer. RAND Corporation
Mr. Robert P Ernst. Head of the Aging Aircraft Program, Naval Air Systems Command
Risk Assessment and Management in Complex Organizations
Dr. Diane Vaughan. Professor. Department of Sociology at Boston College
May 6, 2003, Houston, Texas
MADS Timeline Update, Ascent Video
Dr. Gregory J. Byrne. Assistant Manager, Human Exploration Science. Astromaterials Research and Exploration Science Of-
fice at the Joiinson Space Center
Mr. Steven Rickman. Chief of the Thermal Design Branch. Johnson Space Center. NASA
Dr. Brian M. Kent. Air Force Research Laboratory Research Fellow
David \V. Whittle, Chairman of the Systems Safety Review Panel and Chairman of the Mishap Investigation Team in the
Shuttle Program Office
June 12, 2003, Washington, DC
NASA Budgetary History and Shuttle Program Management
Mr. Allen Li, Director, Acquisition and Sourcing Management, General Accounting Office
Ms. Marcia S. Smith, Specialist in Aerospace and Telecommunications Policy, Congressional Research Service
Mr. Rus.sell D. Turner, Former President and CEO, United Space Alliance
Mr. A. Thomas Young, Retired Aerospace Executive
Endnotes for Appendix A
' NASA Agency Contingency Action Plan for Space Flight Operations, January 2003, p. D-2.
" Guidelines per NASA Policy Guideline 8621.
'SU.S.C. App§§l efseq. (1972).
^JSC Form 564 (March 24, 2003).
' Harold W. Gehmon to Sean O'Keefe, February 25, 2003.
2 -a B Report volume i Aubust 2003
I^lil
Board Member
Biographies
Admiral Harold W. Gehman Jr. (Retired)
Chairman, Columbia Accident Investigation Board. Formerly Co-Chairman of the Department of
Defense review of the attack on the U.S.S. Cole. Before retiring, Gehman served as the NATO
Supreme Allied Commander, Atlantic. Commander in Chief of the U.S. Joint Forces Command,
and Vice Chief of Naval Operations for the U.S. Navy. Gehman earned a B.S. in industrial Engi-
neering from Penn State University and is a retired four star Admiral.
Major General John L. Barry
Executive Director for the Columbia Accident Investigation. Director, Plans and Programs,
Headquarters Air Force Materiel Command, Wright-Patterson Air Force Base, Ohio. An honors
graduate of the Air Force Academy with an MPA from Oklahoma University, Barry has an exten-
sive background as a fighter pilot and Air Force commander: Squadron, Group and two Wings. A
trained accident investigator, Barry has presided or served on numerous aircraft mishap boards.
He was a White House Fellow at NASA during the Challenger mishap and was the White House
liaison for NASA, served as the Military Assistant to the Secretary of Defense during Desert
Storm and was the director of Strategic Planning for the U.S. Air Force.
Brigadier General Duane W, Deal
Commander, 21st Space Wing, Peterson Air Force Base, Colorado. Currently in his eighth com-
mander position in the U.S. Air Force, Deal has served on or presided over 12 investigations of
space launch and aircraft incidents. Formerly a Research Fellow with the RAND Corporation
and Fellow of the Harvard Center for International Affairs, he has flown seven aircraft types as
an Air Force pilot, including the SR-71 Blackbird, and served as a crew commander in two space
systems. Deal holds a B.S. in Physics and a M.S. in Counseling Psychology from Mississippi
State University, as well as a M.S. in Systems Management from the University of Southern
California.
Report Voli
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BDARO
James N. Hallock, Ph.D.
Manager. Aviation Safety Division. Voipe National Transportation Systems Center. Massachu-
setts. He lias worked in the Apollo Optics Group of the MIT Instrumentation Lab and was a
physicist at the NASA Electronics Research Center, where he developed a spacecraft attitude
determining system. He joined the DOT Transportation Systems Center (now the Volpc Center) in
1970. Hallock received B.S., M.S. and Ph.D. degrees in Physics from the Massachusetts Institute
of Technology (MIT). He is an expert in aircraft wake vortex behavior and has conducted safety
analyses on air traffic control procedures, aircraft certification, and separation standards, as well
as developed aviation-information and decision-support systems.
Major General Kenneth W. Hess
Commander. .\\r Force Safety Center. Kirtland Air Force Base. New Mexico, and Chief of Safety.
United States Air Force. Headquarters U.S. Air Force. Washington. D.C. Hess entered the Air
Force in 1969 and has flown operationally in seven aircraft types. He has commanded three Air
Force wings - the 47th Flying Training Wing. 374th Airlift Wing, and 3 19th Air Refueling Wing
- and commanded the U.S. 3rd Air Force. RAF Mildenhall, England. Hess also has extensive staff
experience at the Joint Staff and U.S. Pacific Command. He holds a B.B.A. from Texas A&M
University and a M.S. in Human Relations and Management from Webster College.
G. Scon Hubbard
Director of the NASA Ames Research Center, California. Hubbard was the first Mars Program
Director at NASA Headquarters, successfully restructuring the program after mission failures.
Other NASA positions include Deputy Director for Research. Director of NASA's Astrobiology
Institute, and Manager of the Lunar Prospector mission. Before joining NASA, he was Vice Presi-
dent of Canberra Semiconductor and Staff Scientist at the Lawrence Berkeley National Labora-
tory. Hubbard holds a B.A. in Physics-Astronomy from Vanderbilt University, and conducted
graduate studies at the University of California, Berkeley. Hubbard is a Fellow of the American
Institute of Aeronautics and Astronautics.
John M. Logsdon , Ph.D.
Director, Space Policy Institute, Elliott School of International Affairs, The George Washington
University, Washington, D.C, where he has been a faculty member since 1970. A former member
of the NASA Advisory Council, and current member of the Commercial Space Transpi)rtation
Advisory Committee and the International Academy of Astronautics, Log.sdon is a FelUw of
the American Institute of Aeronautics and Astronautics and the American Association for the
Advancement of Science, and was the first Chair in Space History at the National Air and Space
Museum. He received a B.S. in Physics from Xavier University and a Ph.D. in Political Science
from New York University.
Douglas D. Osheroff, Ph.D.
J. G. Jack.son and C. J. Wood Professor of Physics and Applied Physics, Stanford University,
California. A 1996 Nobel Laureate in Physics for his joint discovery of superfluidity in helium-3,
Osheroff is also a member of the National .Academy of Sciences and a MacArthur Fellow. Osher-
off has been awarded the Simon Memorial Prize and the Oliver Buckley Prize. He received a B.S.
from the California Institute of Technology and a Ph.D. from Cornell University.
z 4 Q
Report volume I
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Sally T. Ride, Ph.D.
Professor of Physics, University of California. San Diego, and President and CEO of Imaginaiy
Lines. Inc. The first American female astronaut in space. Ride served on the Presidential Com-
mission investigating the Space Shuttle Challenger Accident. A Fellow of the American Physical
Society and Board Member of the California Institute of Technology, she was formerly Director
of NASA's Strategic Planning and served on the Space Studies Board and the President's Com-
mittee of Advisors on Science and Technology. Ride has received the .lefferson Award for Public
Service and twice been awarded the National Spaceflight Medal. She received a B.S. in Physics,
a B.A. in English, and a M.S. and Ph.D. in Physics from Stanford University.
Roger E. Tetrault
Retired Chairman and Chief Executive Officer, McDermott International. Tetrault has also served
as Coiporate Vice President and President of the Electric Boat Division and the Land Systems
Division at General Dynamics, as well as Vice President and Group Executive of the Government
Group at Babcock and Wilcox Company. He is a 1963 graduate of the U.S. Naval Academy and
holds a MBA from Lynchburg College.
Rear Admiral Stephen A. Turcohe
Commander, Naval Safety Center, Virginia. Formerly Commanding Officer of the Jacksonville
Naval Air Station and Deputy Commander of the .foint Task Force Southwest Asia, Turcotte has
also commanded an aviation squadron and served on the Joint Staff (Operations Division). A
decorated aviator, he has flown more than 5.500 hours in 15 different aircraft and has extensive
experience in aircraft maintenance and operations. Turcotte holds a B.S. in Political Science from
Marquette University NROTC and masters degrees in National Security and Strategic Studies
from the Naval WarColleee. and in Management from Salve Regina University.
Steven B. Walu^ce
Director, Office of Accident Investigation. Federal Aviation Administration, Washington, D.C.
Wallace's previous FAA positions include Senior Representative at the U.S. Embassy in Rome,
Italy, Manager of the Transport Airplane Directorate Standards Staff in Seattle, and Attorney/
Advisor in t^he New York and Seattle offices. He holds a B.S. in Psychology from Springfield
College and a J.D. from St. John's University School of Law. Wallace is admitted to legal practice
before New York State and Federal courts, and is a licensed commercial pilot with multiengine,
instrument, and seaplane ratings.
Sheila E. Widnall, Ph.D.
Institute Professor and Professor of Aeronautics and Astronautics and Engineering Systems,
Massachusetts Institute of Technology (MIT). Massachusetts. Widnall has served as Associate
Provost, MIT, and as Secretary of the Air Force. She is currently Co-Chairman of the Lean Aero-
space Initiative. A leading expert in fluid dynamics. Widnall received her B.S., M.S.. and Ph.D. in
Aeronautics and Astronautics from MIT.
Board Member pholofiniphs h\ Rick IV. .S7/7(',v
Report voLUf
AUQUST 2003
The launch of STS-107 on January 16, 2003.
^iiill
PENDIX C
Board Staff
Advisors to the Chair
James F. Bagian. MD.
Giiion S. Bluford Jr.
Dennis R. Jenkins
Medical Consultant and
Chief Right Surgeon
Executive Director for
Investigative Activities
Investigator and Liaison to the Board
Astronaut (ret.).
Department of Veterans Affairs
Astronaut (ret.)
Consulting Engineer. Valador. Inc.
Group I: Management and Treatment of Materials
Charles A. Babish
Col. Timothy D. Bair
Lt. Col. Lawrence M. Butkus. P.E.. Ph.D.
CDR Michael J. Francis
CAPT James R. Fraser. MD.
John F. Lehman
Lt. Col. Christophers. Mardis
Col. David T. Nakayama
Clare A. Paul
Maj. Lisa Sayegh. Ph.D.
CAPTJohnK. Schmidt. Ph.D.
John R. Vallaster
Capt. Steven J. Clark
1st Lt. Michael A. Daniels
1st Lt. David L. Drummond
Joshua W. Lane
Ed Mackey
Jana M. Price. Ph.D.
Dana L. Schuize
Stacy L. Walpole
Investigator
Inxcstigator
Investigator
Investigator
Investigator
Investigator
Investigator
Investigator
Investigator
Investigator
Investigator
Investigator
Researcher
Support Staff
Support Staff
Support Staff
Support Staff
Support Staff
Support Staff
Administrative Support
Air Force Materiel Command
Air Force Materiel Command
Air Force Academy
Naval Safely Center
Naval Safety Center
Defense Contract Management Agency
Air Force Materiel Command
Air Force Materiel Command
Air Force Research laboratory
Air Force Materiel Command
Naval Safety Center
Naval Safety Center
Air Force Materiel Command
Air Force Materiel Command
Air Force Space Command
Analytical Graphics. Inc.
Analytical Graphics, Inc.
National Transportation Safety Board
National Transportation Safety Board
Valador, Inc.
Report Volu»
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Group II: Training, Operations, and In-Flight Performance
Lt. Col, Richard .1. Burgess
Daniel P. Diggins
Gregory J. Phillips
Lisa M. Reed
Ll. Col. Donald J. White
Diane Vaughan. Ph.D.
Maj. Tracy G. Dillinger, Ph.D.
Lt. Matthew E. Granger
Maj. David L. Krai
Helen E. Cunningham
Col. Donald W. Pitts
Investigator
Investigator
Investigator
Investigator
Investigator
Researcher
Support Staff
Support Staff
Support Staff
Administrative Support
Consultant
Air Force Safety Center
Federal Aviation Administration
National Transportation Safety Board
Booz Allen Hamilton
Air Force Safety Center
Boston College
Air Force Safety Center
Air Force Safety Center
Air Force Safety Center
Valador. Inc.
Air Force Safety Center
Group III: Engineering and Technical Analysis
James O. Arnold. Ph.D.
R. Bruce Darling, Ph.D.
Lt. Col. Patrick A. Goodman
G. Mark Tanner, P.E.
Gregory T. Kovacs. Ph.D.
Paul D. Wilde. Ph.D.
Douglas R. Cooke
Capt. David J. Bawcom
Robert E. Carvalho
Lisa Chu-Thielbar
Capt. Anne-Marie Contreras
Jay H. Grinstead
Richard M. Keller
Lt. Col. Robert J. Primhs, Jr.
Ian B. Sturken
Y'Dhanna Daniels
Investigator
Investigator
Investigator
Investigator
Investigator
Investigator
Advisor
Support Staff
Support Staff
Support Staff
Support Staff
Support Staff
Support Staff
Support Staff
Support Staff
Administrative Support
University of California, Santa Cruz
University of Washington
Air Force Space Command
Valador. Inc. Consultant
Stanford University
Federal Aviation Administration
NASA Johnson Space Center
Air Force Space Command
NASA Ames Research Center
NASA Ames Research Center
Air Force Space Command
NASA Ames Research Center
NASA Ames Research Center
Air Force Space Command
NASA Ames Research Center
Honeywell Technology Solutions, Inc.
Group IV: Organization and Policy
Dwayne A. Day, Ph.D
David H. Onkst
Richard H. Buenneke
W. Henry Lambright, Ph.D.
Roger D. Launius, Ph.D.
Howard E. McCurdy, Ph.D.
Jill B. Dyszynski
Jonathan M. Krezel
Chirag B. Vyas
Investigator
Researcher
Consultant
Consultant
Consultant
Consultant
Research Assistant
Research Assistant
Research Assistant
Valador. Inc. Consultant
American University
The Aerospace Corporation
Syracuse University
National Air and Space Museum
American University
George Washington University
George Washington University
George Washington LJniversity
REPaRT VOUL
1ST 2 0 0 3
COLUMBIA
ACCIDENT INVESTIGATION BDARD
Independent Assessment Team
James P. Mosquera
Ronald K. Gress
James W. Smiley, Ph.D.
David B. Pye
CDR (Selectee) Johnny R Wolfe
John Benin, Ph.D.
Tim Foster
Robert M. Hammond
Daniel J. Heimerdinger. Ph.D.
.-Arthur Heuer. Ph.D.
Michael W. Miller
Gary C. Olson
Jacqueline A. Stemen
Lead Investigator
Investigator
Investigator
Investigator
Investigator
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Administrative Support
U.S. Navy
Valador, Inc. Consultant
Valador, Inc. Consultant
Valador. Inc. Consultant
Strategic Systems Program
Valador, Inc. Consultant
Valador, Inc. Consultant
Valador, Inc.
Valador, Inc.
Valador, Inc. Consultant
Valador, Inc. Consultant
Valador, Inc. Consultant
Valador, Inc.
NASA Representatives
Col. (Selectee) Michael J. Bloomtield
Theron M. Bradley, Jr
Robert W. Cobb
Bryan D. O'Connor
David M. Lengyel
Steven G. Schmidt
J. William Sikora, Esq.
Astronaut Representative
Executive Secretary
Observer
Ex-Oliicio Board Member
Executive Secretary for Adininistration
Executive Secretary for Management
Board General Counsel
USAF/NASA Astronaut Office
NASA Headquarters
NASA Office of the Inspector Gener;
NASA Headquarters
NASA Headquarters
NASA Headquarters
NASA Glenn Research Center
Editorial Team and Production Staff
Lester A. Reingold
Christopher M. Kirchhoff
Patricia D. Trenner
Ariel H. Simon
Joshua M. Limbaugh
Joseph A. Rcid
James M. Thoburn
Lead Editor
Editor
Copy Editor
Assistant Editor
Layout Arti.st
Graphic Designer
Website and Public Database Lead
Valador, Inc. Consultant
Valador, Inc. Consultant
Air& Space/Smithsonian Magazine
Valador, Inc. Consultant
Valador, Inc.
Valador, Inc.
Valador. Inc.
Public Affairs
Laura J. Brown
Patricia L. Brach
Paul 1. Schlamm
Terry Williams
Lt. Col. Tyrone M. Woody ard
Rick W. Stiles
Marie T. Jones
Lead Public Affairs Officer
Public Affairs Officer
Public Affairs Officer
Public Affairs Officer
Public Affairs Officer
Photographer
Public Affairs Administrative Support
Federal Aviation Adininistration
Federal Emergency
Management Agency
National Transportation Safety Board
National Transportation Safely Board
Air Force Office of the Chief of Staff
Rick Stiles Photography
Valador. Inc.
Report vdli
August 2003
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Keith Carney
Clirtorcl Feldman
Press Conference/Hearing Support
Press Conference/Hearing Support
Federal Networks , Inc.
Federal Networks, Inc.
Government Affairs
Thomas L. Carter
Matthew J. Martin
Capt. David R. Young
Lt. Col. Wade J. Thompson
Col. Jack F. Anthony
Paul E. Cormier. Esq.
Frances C. Fisher
Frank E. Hutchison
Charles R. McKee
Lead Government Affairs
Government Affairs
Government Affairs
Government Affairs
Department of Defense Liaison
Counsel to the Chairman
ANSER Liaison
Special Assistant
Special Assistant
Government Relations Consultant
Government Relations Consultant
Kansas Air National Guard
Air Combat Command
Air Force Space Command
Government Relations Consultant
ANSER. Inc.
ANSER. Inc.
ANSER, Inc.
Administrative Staff
Lt. Gharles W. Ensinger
YNC(SS) Barry M. Fitzgibbons
Christine F. Cole
Jana T. Schultz
Sharon J. Martin
Anna K. "Kitty" Rogers
Trudy Davis
Lillian M. Hudson
Anita 1. Abrego
Kevin R Bass
Robert J. Navarro
James F. Williams
James McMahon
Michele 0"Connell
Robert L. Binkley
Roberta B. Sherrard
Paula B. Frankel
Mitchell L. Bage, Jr.
Rudy G. Gazarek
Patrick Garrett
Douglas S. Griffen
Adininistrative Support to the Chairman
Administrative Support to the Chairman
Administrative Support
Administrative Support
Budget Manager
Lead Travel Coordinator
Travel Coordinator
Travel Coordinator
Investigation Software Support
Investigation Software Support
Investigation Software Support
Investigation Softv\are Support
Information Technology
Information Technology
Information Technology
Information Technology
Recorder
Scheduler
Software Support
Software Support
Software Support
Naval Safety Center
Naval Safety Center
NASA Johnson Space Center
NASA Johnson Space Center
Al-Razaq Computing Services
Valador. Inc. Consultant
Valador, Inc. Consultant
Valador. Inc. Consultant
NASA Ames Research Center
NASA Ames Research Center
NASA Ames Research Center
NASA Ames Research Center
NASA Marshall Space Flight Center
Science Applications
International Corporation
NASA Dryden Flight Research Center
NASA Dryden Flight Research Center
Westover and Associates. Inc.
Blackhavvk
GroupSystems.com. Inc.
GroupSystems.com, Inc.
GroupSy.stems.com, Inc.
Documentation Support
Clarisse Abramidis
Norman L. Bailey
Michael R. Broschat
Director
Information Technology Lead
Database Administrator
U.S. Department of Justice,
Office of Litigation Supjxirt
Aspen Systems Corporation
Aspen Systems Corporation
Report Volume I
iT 2 00 3
COLUMBIA
ACCIDENT INVESTIGATION BOARD
Jennifer L. Bukvics
Bethany C. Frye
Donna J. Fudge
Elizabeth G. Henderson
Ronald K. Hourihane
Kenneth B. Hulsey
Leo Kaplus
Carl Kikuchi
Douglas P. McManus
Susan M. Plott
Maxwell Prempeh
Donald Smith
Ellen M. Tanner
Vera M. Thorpe
David L. Vetal
Shannon S. Wiggins
Susan Corbin
Carolyn Paquette
Joseph Prevo
Lead Project Manager
Paralegal
Senior Paralegal. Group II Coordinator
Case Manager
Network Administrator
Senior Paralegal, lAT Coordinator
Network Administrator
Contracting Ollicer's
Technical Representative
Branch Chief and IT Manager
Project Supevisor, Group III Coordinator
Database Administrator
Scanner Operator
Project Supervisor
Contract Director
Lead Project Manager
Senior Paralegal. Group 1 Coordinator
TechDoc Support
TechDoc Support
TechDoc Support
Aspen Systems Corporation
Aspen Systems Corporation
Aspen Systems Corporation
U.S. Department of Justice.
Office of IJtigation Support
Aspen Systems Corporation
U.S. Department of Justice/
ASPEN Systems
Aspen Systems Corporation
U.S. Department of Justice.
Office of Litigation Support
U.S. Department of Justice.
Office of Litigation Support
Aspen Systems Corporation
Aspen Systems Corporation
Aspen Systems Corporation
LLS. Department of Justice/
ASPEN Systems
Ll.S. Department of Justice/
ASPEN Systems
Aspen Systems Corporation
Aspen Systems Corporation
NASA Kennedy Space Center
NASA Kennedy Space Center
Prevo Tech
Advisors and Consultants
John C. Clark Advisor
Vernon S. Ellingstad. Ph.D. Advisor
JeffGuzzetti Advisor
Thomas K. Haueter Advisor
Tina L. Panontin Ph.D. P.E. Advisor
Max D. Alexander Consultant
Anthony M. Calomino. Ph.D. Consultant
RADM Walter H. Cantrell. USN ( Ret) Consultant
Elisabeth Pale-Cornell. Ph.D Consultant
Robert L. Crane. Ph.D. Consultant
Peter J. Erbland. Ph.D. Consultant
Jean R. Gebman. Ph.D. Consultant
Leon R. Glicksman. Ph.D. Consultant
Howard E. Goldstein Consultant
Deborah L. Grubbe Consultant
Mark F. Horstemeyer, Ph.D. Consultant
Francis I. Hurwitz. Ph.D. Consultant
Sylvia M. Johnson. Ph.D. Consultant
Ralph L. Keency. Ph.D. Consultant
Brian M. Kent, Ph.D. Consultant
Daniel B. Leiser. Ph.D. Consultant
National Transportation Safety Board
National 1 ransportation Safety Board
Nalit)nal I'ransportation Safety Board
National Transportation Safety Board
NASA Ames Research Center
Air Force Research Laboratory
Glenn Research Center
Aerospace Safety Advisory Panel
Stanford University
Air Force Research Laboratory
Air Force Research Laboratory
RAND Corporation
Massachusetts Institute of 1'echnology
Valador, Inc. Consultant
DuPont Corporation
Mississippi State University
Glenn Research Center
NASA Ames Research Center
Duke University
Air Force Research i aho-;'.:,r-
NASA Ames Researci. • .-iu .i
Report Volume I
IBUST 2003
Nancy G. Leveson, Ph.D.
M. Sam Mannan, Ph.D.
Robert A. Mantz. Ph.D.
Alan C. McMillan
Story Musgrave
Theodore Nicholas. Ph.D.
Larry P. Perkins
Donald J. Rigali, Ph.D.. PE.
Karlene H. Roberts. Ph.D.
John R. Scully. Ph.D.
George A. Slenski
RogerW. Staehle, Ph.D.
Ethiraj Venkatapathy. Ph.D.
Karl E. Wcick, Ph.D.
Douglas A. Weigmann, Ph.D.
James Wick
David D. Woods. Ph.D.
COLUMBIA
ACCIDENT INVESTIGATIDN BOARD
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Consultant
Massachusetts Institute of Technology
Texas A&M University
Air Force Research laboratory
National Safety Council
Astronaut (Ret.)
University of Dayton
Research Institute
Air Force Research Laboratory
Valador, Inc. Consultant
University of California, Berkeley
LIniversity of Virginia
Air Force Research L;iboratory
Roger W. Staehle Consulting
NASA Ames Research Center
University of Michigan
University of Illinois,
Urbana-Champaign
Intel Corporation
Ohio State University
1
Valador, Inc., Board Support Contractor
Kevin T. Mabie
Richard A, Kaplan
Neda Akbarzadeh
Christy D. Blasingame
Kim Hunt
Charles M. Mitchell
Karen Bircher
Vicci Biondo
Jeanette Hutcherson
Caye Liles
Jennifer North
Barbara Rowe
Terry Rogers
Susan Vick
Elizabeth Maiek
Sally McGrath
Bridget D. Penk
Ray Weal
Robert Floodeen
James Helmlinger
Philippe E. Simard
Mario A. Loundermon
President and CEO Valador. Inc.
Senior Vice President of Engineering Valador, Inc.
and CIO
Contract Support Valador, Inc.
Contract Support Valador, Inc.
Contract Support Valador, Inc.
Contract Support Valador, Inc.
Transcriber Valador, Inc.
Transcriber Valador, Inc.
Transcriber Valador, Inc.
Transcriber Valador, Inc.
Transcriber Valador. Inc.
Transcriber Valador, Inc.
Transcriber Valador, Inc.
Transcriber Valador. Inc.
Support Staff Valador, Inc.
Support Staff Valador, Inc.
Public Database Support Valador. Inc.
Public Database Support Valador, Inc.
Website Support Valador. Inc.
Website Support Valador, Inc.
Website Support Valador. Inc.
Graphic Designer Valador. Inc.
Report voli
IQUST 2003
COLUMBIA
SUPPLEMENTAL MATERIAL
NASA Press Conference on the Space Shuttle Columbia
Sean O'Keefe, Administrator
NASA Facts
National Aeronautics and Space Administration
Washington. DC 20546 (202) 358-1600
For Release
Wednesday, August 27. 2003, 1 1 :02 a.m.
MR. MAHONE: Good morning, and thank you for joining
us here in Washington and from the centers across the
country at our various NASA field centers. Before I intro-
duce the NASA Administrator, I want to go over a few
guidelines for this morning's press conference. We'll begin
with questions here in Washington, and then go to the var-
ious NASA centers. Please wait for the microphone before
asking your question, and don't forget to tell us your name
and affiliation. Because of the large number of reporters
who want to participate in today's briefing, please limit
your inquiries to one question and one follow-up, and,
please, please, no multi-part quesUons. Again, thank you
for taking the time to join us today, and allow me to intro-
duce the NASA Administrator, Sean O'Keefe.
MR. O'KEEFE: Thank you. Glenn, and good morning.
Thank you all for spending time with us here this morning.
Yesterday, we received the report of the Columbia Accident
Investigation Board run by Admiral Hal Gehman, and
shortly thereafter I had the opportunity to speak to several
of our colleagues here throughout this agency to describe
those initial findings and recommendations as well as to
offer some views of what the direction will be from this
point forward. And so if you'll permit me. let me draw a lit-
tle bit from some of those comments here in the context of
today's discussion with you, as well, as we start this and, of
course, respond to your questions.
This is, I think, a very seminal moment in our agency's his-
tory. Over the 45 years of this extraordinary agency, it has
been marked and defined in many respects by its extraordi-
nary successes and the tragic failures in both contexts. And
in each of those, in a tracing of the history of that 45 years,
there is always an extended debate and discussion of the
national policy as well as the focus of the charter and
objective of exploration of what this agency was chartered
and founded to do in 1958. And I expect that in this circum-
stance it will be no different. This is one of those moments
in which there will certainly be a very profound debate, dis-
cussion, and I think a very inward look here within the
agency of how we approach this important charter that
we've been asked to follow on behalf of the American peo-
ple to explore and discover on their behalf. In each of these
defining moments as well, our strength and resolve as pro-
fessionals has been tested, and certainly that will be the
case in this circumstance, and it has been for these past
seven months, to be sure. On February 1st. on the mornins
of that horrific tragedy that befell the NASA families and
the families of the crew of Columbia, we pledged to the
Columbia families that we would find the problem, fix it.
and return to the exploration objectives that their loved
ones had dedicated their lives to. The Board's effort and the
report we received yesterday completes the first of those
commitments and does it in an exemplary manner. They
have succeeded in a very, very thorough coverage of all the
factors which caused this accident and that led to this sem-
inal moment, which is marked by a tragic failure. And their
exceptional public service and their incredible diligence in
working through this very difficult task I think will stand us
in good stead for a long time to come as we evaluate those
tlndings and recommendations as carefully as we know
how.
As we begin to fulfill the second commitment that we made
to the families to fix the problems, the very first important
step in that direction is to accept those findings and to com-
ply with the recommendations, and that is our commit-
ment. We intend to do that without reservation. This report
is a very, very valuable blueprint. It's a road map to achiev-
ing that second objective, to fix the problem. They've given
us a head start in the course of their discussions over the
last several months and in the course of their investigation,
in the public testimony, in their press conferences, in all of
their commentary, which has been very, very open in an
extremely inclusive process as they have wrestled with the
challenges of finding the problems that caused this partic-
ular horrible accident. And that candor, that openness, that
release of their findings and recommendations during the
course of the investigation has given us a very strong head
start in the direction of fulfilling that second commitment.
At this point, we have already developed a preliminary
implementation plan, and we will update that, and we're
about that process right now of updating to include all the
findings and recommendations included in the report, in
addition to those that were released and described very
specifically during the course of their investigative proce-
dures. But. again, much as the Chairman, Admiral Hal
Gehman, observed throughout the course of those proceed-
ings, what we will read and what we did read as of yester-
day was precisely the same commentary that we had heard
during the course of their investigative activities and in all
of their public testimony that they've offered, which has
been considerable and, again, very extensive, exhaustive.
So as we implement those particular findings and recom-
mendafions, our challenge at this point will be to choose
wisely as we select the options that are necessary to fully
comply with each of those recommendafions. We'll contin-
ually improve and upgrade that implementation plan in
order to incorporate every aspect of knowing what's in the
report, but also so much of what we ha\ e determined and
COLUMBIA
SUPPLEMENTAL MATERIAL
seen as factors that need improvement and consistent
upgrading throughout our own process within the NASA
family. It's going to be a long road in order to do that, but
it is necessary in order to fulfill that second commitment
we've made to the families.
Now, the report covers hardware failures, to be sure, but it
also covers human failures and how our culture needs to
change to mitigate succumbing to these failings again. We
get it. Clearly got the point. There is just no question that is
one of their primary observations, that what we need to do,
we need to be focused on, is to examine those cultural pro-
cedures, those systems, the way we do business, the princi-
ples and the values that we adhere to as a means to improve
and constantly upgrade to focus on safety objectives as
well as the larger task before us of exploring and discover-
ing on behalf of the American people. But they've been
very clear in their statements throughout the report in sev-
eral instances, repetitively, and in the public commentary
that the Chairman and members of the Board have offered
following their efforts yesterday after the release of the
report, that these must be institutional changes. And that's
what we're committed to doing, and that will assure that
over time those changes will be sustained, as those process,
procedures, and systems are altered in order to reinvigorate
the very strong ethos and culture of safety and exploration,
those dual objectives that we have always pursued. That is
what's going to withstand the test of time if we are success-
ful in this effort, and we fully intend to be. So we will go
forward now and with great resolve to follow this blueprint
and do our best to make this a much stronger organization.
In the process of doing so, it will involve the capacity and
capability of all of us within this agency.
This is not about an individual program. It's not about an
individual aspect or enterprise of what we pursue. It is
about everything we do throughout this agency. There is so
much of what has been observed in this report that really
has tremendous bearing and tremendous purpose in defin-
ing everything we do throughout the agency. And so, there-
fore, we will approach it and have considered this to be an
agency-wide issue that must be confronted in that regard.
Now, this is a very different NASA today than it was on the
1st of February. Our lives are forever changed by this trag-
ic event, but certainly not nearly as much as the lives of the
Columbia families. This is forever for them. And so that
resolve to find the problem which we have successfully
done, thanks to the extraordinary efforts on the part of this
Board, to fix those problems which we are now in pursuit
of as the second commitment, and to return to the explo-
ration objectives that their loved ones dedicated their lives
to is something we take as an absolute solemn promise. We
have to resolve and be as resolute and courageous in our
efforts as they have been in working through this horrible
tragedy. The time that we have spent, I think, over the
course of since the accident, and certainly well before, in
trying to work through those particular questions, again,
are focused on institutional change. Since I arrived a little
less than a year and a half ago, we have almost completely
rebuilt the management team, and so it is a new, fresh per-
spective in looking at a range of challenges that we current-
ly confront, and those changes have been ongoing of a
management team as well as the institutional changes we
have implemented and will continue to do in full compli-
ance with this report.
The new management team began I think by evaluating ini-
tially on the first day that I airived here the contingency
planning effort that was necessary in the event of such a
tragedy. It was the first thing I did on the first morning I
arrived at this agency. And in reviewing that contingency
plan of how we would respond to a disaster, to a tragic
event, which I had hoped and was in the expectation and
fond hope that I would never, ever have to utilize, we
nonetheless improved that contingency planning effort by
doing two things: First of all, reaching back to the Rogers
Commission, the Challenger incident and accident, to
incorporate in that contingency plan all the changes neces-
sary in order to respond definitively. The second step we
went through was to specifically benchmark it against best
practices of any comparable organization, of which there
are very, very few. And the only one that in my personal
experience that I was aware or felt had any direct compara-
bility to the risks and the stakes involved was the Navy
nuclear program. And so from that first day, we upgraded
that particular contingency plan based on the benchmark-
ing procedures that we followed through with them. We
then began a very vigorous effort by late spring, early sum-
mer of last year to begin a comprehensive benchmarking
procedure against the submarine service as well as the
naval reactors community, to, again, pick up best practices
as well as to institutionally change the way we do business.
And that process is ongoing as it had been a year ago as we
continue to make those changes. That was a lesson I
learned very specifically in my tenure as Navy Secretary
better than ten years ago, was to look at those particular
procedures and assure that we have incorporated as much
of that, and that was a work in progress that will continue.
But, again, the observation by Admiral Gehman and the
members of the Board yesterday and replete throughout the
report, it is not about changing boxes or individual faces in
each of those positions. It is about the longer-term institu-
tional changes that must be made. And, again, to that point
we get it. It is about the culture of this agency, and we all
throughout the agency view that as something that's appli-
cable to the entire agency, not any individual element there-
of. With that, I thank you again for the opportunity to get
together this morning and, again, look forward to your
questions and comments.
MR. MAHONE: Yes, sir?
QUESTION: Mr. Administrator, Matt Wald, New York
Times. There are other organizations that have gone
through this kind of change. Most have called for some out-
side help. I'm tempted to ask if you're read Diane Vaughn's
book or called her up or if there are other specialists in
safety culture who you would be bringing in at this time to
help transform yourself, your agency.
MR. O'KEEFE: 1 appreciate that. Yes, indeed, we have
read Dr. Vaughn's book, and there have been several folks
here in headquarters as well as Johnson who have been in
touch with her. Dr. Michael Greenfield spoke to her I think
CDLUMBiA
SUPPLEMENTAL MATERIAL
initially about four months ago, three months ago. shortly
after her testimony before the Columbia Accident
Investigation Board's hearings. The primary source of safe-
ty experts that we have been trying to encourage and have
requested come in to assist with us, again, are from the
naval reactors community. This is a very specific set of pro-
cedures they follow. It's a very exhaustive effort that they
have gone through over a comparable period of time as the
span of this agency, in order to upgrade their procedures as
a consequence of incidents in the early phases of that pro-
gram that gave them great pause. And so there's a report
that I think was released about a month and a half ago
which was the second step in that benchmarking procedure
with the submarine service, which is the operational com-
munity, and the naval reactors community, which is the dis-
ciplinaires, if you will, over the technical requirements
side, that we continue to solicit. Beyond that, there are cer-
tainly a number of folks that we have invited in and will
continue to do so. I spent the better part of four hours last
night with Admiral Gehman and most of the members of
the Board asking them specifically for the folks that they
had brought in as advisers to the Board on this particular
question so we may be in contact with them in order to ask
for their advice and assistance and contributions in this
regard as we implement these recommendations on that
front as well. So. yes, we're about that as well.
MR. MAHONE: Keith?
QUESTION: Keith Cowing. Nasawatch.com. Yesterday
you read Gene Kranz's inspiring words that were issued to
his troops after another accident. And, you know, that was
then and this is now. You've got a workforce that has been
downsized, bought out, they're jaded by innumerable man-
agement fads, and clearly it hasn't worked. I got an e-mail
from somebody yesterday saying, "What's he going to do,
actually make us — write us on the white board?" I mean,
the cynicism is that high. What are you going to do this
time that is demonstrably different than all these attempts
before it, getting the agency motivated and beyond the cyn-
icism and malaise that seems to have beset it?
MR. O'KEEFE: Well, it's going to require leadership at
every level. This is not something that you direct or dictate.
Again, in my experience, in my prior life as the Navy
Secretary confronted with an incident, an event that really
rocked that institution at that time, when I came in, in the
post-Tailhook incident, it's not about just walking around
telling everybody shape up or ship out. It really takes per-
sistent, regular, constant leadership focus, and I think the
folks that we have recruited and are in place now as the
senior management team that, again, have been over the
course of certainly this last seven months, to be sure, but
over the previous year, have been recruited to those capac-
ities specifically for that, are the kinds of people. I think,
who not only get it but also are going to be the first start at
that leadership objective. Throughout the agency we're
going to have to persistently move through that, but I think
it is staying with a very set of clear principles and values
that we will continue to work through, and it's going to take
time, but the time begins right now. And it has been in
process, I think, for some period before this, but we will
continue to redouble our efforts of that. But it's something
that there is no one trick pony at this. It is not something
that happens simply because I send out a memo. I'm not a
Pollyanna on that point at all. It is something that really
requires. I think, constant, unrelenting diligence, and that is
another theme that I think comes out very resolutely in the
Accident Investigation Board report, which is consistency
as well as persistence and vigilance in the leadership direc-
tion in that regard. And that's what we are committed to
doing.
MR. MAHONE: Yes, sir?
QUESTION: Thank you. I'm Larry Wheeler with Gannett
News Service. I want to get back to the leadership question
a little bit. I was wondering if you could share with us your
thinking about how you motivate your leaders to follow
through on this point that you said they get it. Two weeks
ago, one of your senior managers had a press conference at
Kennedy Space Center in which he, if I understand — if I
recollect correctly, he denied that there was a culture in
NASA or that he was aware that there was a culture in
NASA. And this is the same senior manager who ran the
Safety and Mission Assurance Program throughout the
'90s, which has been highly criticized by the CAIB. Can
you give us your thinking? How do you turn around that
kind of thinking?
MR. O'KEEFE: Well, first of all, I think it's a— it's always
a challenge to define with common specificity to which all
accept of what the term "culture" means. And in my expe-
rience, again, as Navy Secretary, there were multiple cul-
tures. There's the culture — there's a Navy culture, to be
sure, and a naval service ethos. But there's also a surface
sailor culture, an aviator's culture, a submariner's culture.
And then, just to really get some extraordinary oomph into
it, let's get the Marine Corps involved. They're part of the
Navy Department as well. And the common distinctions
between those are born of years of history as well as deep
tradition. It is also true here. There is every single aspect of
how this agency has formed over its 45 years and well
before when at the beginning of the last century the NACA
was formed to respond to aeronautics challenges at that
time that were to be advanced. Every one of the centers,
every one of the elements of what you see throughout this
agency, can reach back and trace historical roots to each of
those individual moments. And so in that regard, there are
lots of different ways in which folks respond, but the over-
all, overarching, overriding NASA culture for this agency
overall is a set of principles and discipline in order to pur-
sue safety of program consideration, which has always
been the case, in pursuit of those exploration objectives.
Those are the kinds of things we need to redouble, and,
again, as you define it very specifically in that regard, there
is importance that I think we get great clarity of exactly
what the definition is, and that's the part we get. There is an
overriding culture which must dominate, and certainly we
celebrate the history and traditions of every aspect of this
agency, much as any other storied agenc\ '-i pstiUition
does.
MR. MAHONE: Yes, sir?
COLUMBIA
SUPPLEMENTAL MATERIAL
QUESTION: Earl Lane with Newsday. A lot of what the
report spoke about on culture, though. I think dealt with
attitudes as much as institutions and talked about how
lower-level engineers were reluctant to come forward with
the concerns. And I'm wondering how you deal with that to
get that message out, and is it perhaps time for a stand-
down like the Navy sometimes does?
MR. O'KEEFE: Well, it is — to be sure, that's one of their
findings and views, is that there is — there was evidence that
they saw, even in the course of their investigation, in which
reluctance dominated. And I think part of that is — or the
two things we've really got to focus on in that direction is,
first of all, reinforce that principle, which, again, we artic-
ulate regularly and I think we see evidence of all the time.
There was a stand-down in June through October of last
year in which an individual observed an anomaly on the
fuel line for Atlanfis. There was a crack on the fuel line that
in turn stood down the fleet for that period of four months
as we ran that to parade rest and determined exactly what
the conclusions and solutions needed to be. So we've got
to, again, continually identify that as the kind of behavior
we want to encourage, and to the extent we do not see it
evidenced or there is evidence in the opposite direction, to
assure that we motivate and encourage folks to feel that
sense of responsibility. And that's the second part as well,
is that there is, I guess, a renewal of the view that I heard
expressed best by Leroy Cain, the Flight Director on STS-
107, who observed this is all of our responsibility. And so
for those who are part of this agency, we have to renew that
view, and for those we recruit to that have to have it under-
stand as the first principle that we all must adhere to.
MR. MAHONE: Yes, Tracy?
QUESTION: Tracy Watson with USA Today.
Administrator, did you have any hints before the accident
that you had this kind of serious attitude and value problem
at the agency?
MR. O'KEEFE: Well, to be sure, there's always cases in
which there are folks who feel like there are certain aspects
of what has occurred in the course of our history or in the
course of events that are not as advantageous as others. And
so I've had a very open policy of let's communicate what-
ever those concerns are, let's have an open dialogue
throughout the agency on every matter. I've tried to be as
open about that to include encouraging e-mails, of which I
get lots of from lots of folks. So I've seen, I think, lots of
evidence of folks who are feeling, you know, very empow-
ered to offer their view and their concerns. And at the same
time, I think it's also evidence of the fact that the process
or the systems to permit that discussion isn't happening at
every level. So there's two things you can draw from that
that I have taken away, which is those who feel that it's nec-
essary to respond in that regard really require other means
because the systems may have broken down. So there is
certainly some indicator of that, but certainly this was a
wake-up call in yesterday's report to see how extensive that
communications link that contributed during the course of
this mission and operation needed to be improved to deal
with precisely that set of problems. It wasn't for lack of
people talking. It was for lack of people, I think, coordinat-
ing those observations effectively to serve up appropriate
decision making about the challenges we were confronting
at that time. And I think that's — you know, the upside of
that is that there's ample evidence to suggest that folks are
feeling like there is an opportunity to communicate and
speak. It is also another quesdon, though, of exactly at what
level can they do so, and I think that's the point and the
communications breakdown that is part of the culture and
is part of the observation that was made by the Board, and
the findings and recommendations speak to that very effec-
fively.
MR. MAHONE: Yes. ma'am?
QUESTION: Marsha Dutton, Associated Press. The Board
made — put quite a bit of emphasis on deadline pressure
affecting decision making and even usurping safety, and
that this pressure came from on high. And you're up there
in the highness here, and I'm just wondering-[Laughter.]
QUESTION: — do you feel some accountability also for
this accident since you've frequently made mention of the
February 2004 date?
MR. O'KEEFE: Absolutely. I feel accountable for every-
thing that goes on in this agency. That's a part of the
responsibility and accountability I think you must accept in
these capacities. No question about it. The Board, I think,
was very specific in observing that schedules and milestone
objectives and so forth are important management goals in
order to achieve outcomes, and these are — this is an appro-
priate and necessary way to go about doing business. But
their observation was that in this instance, this may have
influenced managers, may have begun to influence man-
agers to think in terms of different approaches in order to
comply. And in that regard, I think we have-we've got to
take great heart in the point that — and stock in the point
that in order to pursue such appropriate management tech-
niques and approaches in order to establish goals, objec-
tives, and milestones, you must also assure that the checks
and balances are in place to guarantee that paramount,
number one objective, which is safety. In the course of my
tenure here, there was not a single flight of a Shuttle that
occurred when it was scheduled. Not one. And so as a con-
sequence of that, I think the system has demonstrated the
capacity to not only establish what those objectives would
be, but also a capacity and a flexibility to adjust to those
based on the realities and the pressures that may exist at the
time. Now, the fact that that, again, observed by the Board
as may have begun to influence a decision on the part of
managers was a very important observation and one that we
need to assure that, as we make these institutional changes,
that we adhere to the same management principles of set-
ting goals and objectives, but at the same time assuring that
the checks and balances are in place they not override.
MR. MAHONE: Yes, sir?
QUESTION: Steven Young with spaceflightnow.com. You
said a few months ago that you warned NASA employees
COLUMBIA
SUPPLEMENTAL MATERIAL
this report was going to be ugly. I'm wondering: Was it
ugly? And what etfect do you think it's going to have on
agency morale?
MR. O'KEEFE: Well. I think Admiral Gehman's observa-
tion, when asked the same question yesterday, was that, no,
it's clinical and very straightforward. And there is no ques-
tion about that. It is a very direct review. It is — again, the
whole contingency planning effort that we went through on
the prospect that something like this could happen ended
up working exactly — better than we could have ever antic-
ipated in that sense. That Board was activated that day.
They met for the first time at 5:00 p.m. on that afternoon.
So they were immediately about the business of investigat-
ing, and in concert with that, there was-there was nary a
hint or suggestion that there was ever any point throughout
the course of this seven months in which we sought to
influence the outcome of that result. What we wanted was
an unvarnished, straightforward assessment from them, and
we got that. Now, I think the approach that we have talked
about among our colleagues here in the agency is that it
would be that straightforward approach, that that would be
that direct commentary, and then in the process of reading
through this, that we'd be deliberate about following —
accepting those findings and complying with those recom-
mendations in order to strengthen this organization in the
future. I think we've got a very competent, very profession-
al, extremely well considered work that didn't, you know,
spare anything in risking, you know, the sensibilities or the
emotions or sentiments of anybody in this agency. And
that's exactly the way we expected it to be. That's what we
wanted it to be. And that's what we asked for them to do.
And they did it.
MR. MAHONE: we're going to take one more question
here, and then we're going to go to our centers, and then we
will come back here in just a few moments. Kathy?
QUESTION: Kathy Sawyer, the Washington Post. Mr.
O'Keefe, the report pointed out that the schedule leading
up to next February was going to be as challenging and
fast-paced as the one that immediately preceded the
Challenger launch in 1986. Were you aware of that? Did
anybody come to you and say, hey, we're pressing too
hard? And what do you feel about that now in light of
events?
MR. O'KEEFE: Well, again, the scheduling and the mani-
fest, as it were, the milestones and so forth that were set,
was established by the Shuttle Program Office and the
International Space Station program management at the
request to specifically idenUfy the optimum systems engi-
neering approach for deployment of all of the components
of the International Space Station. So they laid out the
schedule. They established what those dates would be and
milestone objectives would be. And, again, in the course of
my tenure, there was not a single launch that occun'ed
when it was actually scheduled. So I think the approach
that we adhered to at the time, as well as continue to, I
think, is to always set what our milestone objectives and
goals, and clearly the establishment of the core configura-
tion of the International Space Station was an objective that
our international partners looked to. Members of Congress,
all kinds of folks examined and viewed as one of the sem-
inal aspects that needed to be achieved in order to permit
then a wider debate of what that broader composition or
configuration of the International Space Station could be.
But you had to reach that point first. And so in dealing with
that, the approach that the International Space Station and
the Shuttle Program office devised was that schedule for
the optimum engineering configuration necessary to do so,
and the operational considerations were factored into it.
And, again, at every single interval, at any point in which
there appeared to be any anomaly, the flight schedule was
adjusted, as it was for every single flight since I've been
here. There has not been one that flew on the day on which
the launch schedule dictated it should. And that's, again,
appropriate, necessary. The stand-down that occurred from
June to October of last year was a direct consequence of
that. So all those factors, I think the paramount objective
that we continue to look to is the safety objective. And,
again, that's what the Board report points to, is that the
checks and balances really needed to be reinforced, and we
need to be mindful in the future that those be in place as we
use that appropriate management tool, as they have identi-
fied it, of establishing goals, objectives, and milestones.
MR. MAHONE: Sir, we're going to go to Stennis first, so,
Stennis Space Flight Center?
QUESTION: Hi, Administrator. This is Keith Darcy with
the Times-Picayune out of New Orleans. Can you say how
the return to flight process will affect the long-term flight
schedule of the Shuttle, and specifically the production
level at the external fuel tank plant in New Orleans.
MR. O'KEEFE: I wouldn't speculate at this moment.
We've really — we've received the report yesterday, and
what we have put together, again, is an implementation
plan in its preliminary form based on everything that the
Board identified in its public statements and commentary
and in the written material they sent to us as preliminary
findings over the course of the last several months. Now we
have the benefit of the entire report. We're going to update
and upgrade that implementation plan. We hope to release
that here in the next ten days to two weeks so we can iden-
tify what those objectives are, informed by the report. We
also have a number of factors and issues that we have iden-
tified within the agency that need to be adjusted prior to
return to flight. And so as that unfolds in the weeks and
months ahead, we'll be able to establish exactly what it will
take in order to achieve that. But, again, the paramount,
overriding factor in this case is going to be that we comply
with those recommendations, and when we are fit to fly,
that's when that milestone will be achieved on return to
flight.
MR. MAHONE: We'll go to Langley. Langley?
QUESTION: This is Dave Schlect with the Daily Press. I
have a question about the Safety Center being developed
here at Langley. One of the Board's recomr-!end."i!ons is to
establish an independent technical engine- ,: ;'i'.ihority
that would be the sole waiver-grantin;/ ■ - for all
COLUMBIA
SUPPLEMENTAL MATERIAL
technical standards. It would decide what is and what is not
an anomalous event and would independently verify launch
readiness. How might the new NASA Engineering and
Safety Center fulfill this recommendation?
MR. O'KEEFE: Well, we're sorting through that right now.
The initial charter of the Safety Center has been formulat-
ed. As a matter of fact, Brian O'Connor is there at Langley
today, working with General Roy Bridges, the Center
Director at Langley, and others in order to begin working
through the findings and recommendations of this report
and how it will affect how we should adjust the charter of
the NASA Engineering and Safety Center. The approach
that is identified — and, again, we spent a lot of dme last
night talking to Admiral Gehman and his colleagues on the
board — of exactly how we may consider various approach-
es here, and they were more in the listening mode of what
that could be, because, again, they have not been disposi-
tive about which options we should select other than to,
again, reiterate that the recommendations are to, again,
establish that independent technical authority for the con-
trol of requirements of the Space Shuttle Program. And
that's a factor of whether or not that's part of the
Engineering and Safety Center, which, frankly, could serve
as more of a research and development, testing, trend
analysis ki,nd of center and an organization that can come
in to regularly examine what our processes and procedures
are with a fresh set of eyes all the time, and to have the
influence during the course of operational activities to
identify cases where they see anomalies that have some his-
torical or trend assessment to it, that's the issue that we've
really got to sort through, is whether or not you have both
of those capacities inherent in the same organization or
whether it should be two separate functions. In the time
ahead, very short time ahead, that's, you know, the set of
options we really need to sort through in order to comply
with those recommendations, which I think are solid.
The science component will be drawn from an effort that
we conducted through last summer and early fall, not quite
a year ago, which was an effort to prioritize what the sci-
ence performance will be aboard the International Space
Station. We had a blue-ribbon panel of external scientists
representing every single scientific discipline who came in
to specifically organize what that priority sequence is. Until
that time, it was a collection of priorities from every disci-
pline, all of which ranked number one. And so when every-
thing is number one, that means nothing is number one. Sc
what the Board — what was referred to the re-map effort die
last summer and fall that organized that prioritization set
actually had a rank order that began with the number one
and moved through by sequence, two, three, four, and five,
and so that is the sequence in which we will organize the
Space Station scientific objectives from this point forward,
because that is the primary source of all the scientific
micro-gravity experimentation that will be carried out in
the future, is aboard the International Space Station. So
we'll adhere to that blueprint very carefully.
MR. MAHONE: Sir, we have a question at the Kennedy
Space Center.
QUESTION: Mr. O'Keefe, this is Jay Barbee with NBC
News. In talking with the workers here and in Houston, I'm
finding they are very encouraged with you at the helm.
They believe at this time in NASA's history that you are the
right man for the job. Now, they're encouraged by your
honesty and your willingness to admit NASA's mistakes.
But their concern is still communications. It has been sti-
fled, and many with safety concerns have been intimidated
into silence, in fear of losing their jobs. Can you today reas-
sure any NASA or contractor employee if they speak up
with safety concerns, even to members of the press, that
they won't be fired, that they won't suffer setbacks in theii
careers?
MR. MAHONE: Next would be the Glenn Research
Center.
QUESTION: Mr. Administrator, Paul Winovsky (ph) from
WOIO Television. I'm working on an assumption here that
there's a backlog of science waiting to fly once safety con-
cerns are handled. How will you go about prioritizing what
flies in the payloads. For example, the combustion experi-
ment developed here was destroyed on the last mission. Is
the pipeline full? And how will you prioritize what goes
into space next?
MR. O'KEEFE: That's a very good question. There are two
approaches we're going to use to this. The first one is that
if you go to the Kennedy Space Center today, the payload
processing facility and all the International Space Station
program elements that have arrived are stacked up in
sequence and are being tested and checked out for deploy-
ment at the — as soon as the resumption of flight occurs. So
there will be not a lot of confusion about exactly what that
sequence will be. It's going to follow the pattern that,
again, fits that optimum systems integration, engineering
strategy that is best for the production — construction of the
International Space Station to reach the core configuration.
MR. O'KEEFE: Absolutely. We get it, and that's what mes-
sage has been transmitted and understood by every single
leader and senior official in this agency, is that we need ta
promote precisely that attitude. So the answer is absolute-
ly, unequivocally yes.
MR. MAHONE: Johnson Space Center?
QUESTION: Gina Treadgold with ABC News. Sir, you've
said you take responsibility. Do you plan to step down as a
result of this? Or do you feel any pressure to resign?
MR. O'KEEFE: Well, certainly I serve at the pleasure of
the President of the United States, and I will adhere to his
judgment always on any matter, including that one. And so,
no, there is nothing that in my mind transcends that
requirement, and I intend to be guided by his judgment in
that regard.
MR. MAHONE: Marshall Space Flight Center?
QUESTION: Shelby Spires with the Huntsville Times.
Given that the Board suggests that the external tank be
blown with no foam loss, and engineers say this isn't pos-
COLUMBIA
SUPPLEMENTAL MATERIAL
sible. is NASA prepared to redesign the tank without foam
and go to Congress to ask for the money to do this?
MR. O'KEEFE: We'll see. I mean, there may be an option
down the road in which will be selecting to do something
along those lines. Don't know. But the approach that I think
very clearly articulated yesterday by the Accident
Investigation Board membership was that there — just
based on the current configuration and the safety consider-
ations, the issue of foam loss per se is not something they
find as being totally disqualifying. What they do find to be
a problem and what was a contributor, to be sure, a causal
effect based on what is the likely condition of what
occurred in that first 81 seconds, was the departure of the
bipod ramp from the — insulation from the external tank
which struck the leading edge of the orbiter. That's the part
that already we have eliminated as a factor that's going to
be heating segments around that area to act as, instead of
the insulation, so you will not fmd an insulated bipod ramp
at that point on the external tank in the future. Exactly how
much further that's going to need to go, that's one of the
things that I think in the report they said very specifically
we ought to aggressively develop a program to eliminate
departure of any debris of insulation coming off the exter-
nal tank. And that's the part that has already been tasked
and that Bill Readdy, as part of the return to flight eftbrt,
has already charged our external tank management team
over to look at. So we'll be looking to the results of that
view, and all the options are on the table. We'll see what
comes.
MR. MAHONE: We'll take two more quesUons from the
centers, and then we'll come back here to headquarters, and
we'll go to Dryden.
QUESTION: Mr. Administrator, this is Jim Steen with the
L.A. Daily News. I was wondering if the folks at NASA are
looking at the possibility of bringing Shuttle landings back
to Edwards Air Force Base as a safety precaution. And I
also wanted to know what role, if any, that Dryden
Palmdale facility will have in your return to space opera-
tions.
MR. O'KEEFE: Well, in terms of the option of landing at
Edwards, to be sure, that is an option we've always exerted
and used anytime the weather conditions don't permit a
return to the Kennedy Space Center in Florida. So we'll
continue to do that, and anytime there is a condition which
would dictate that we land on the west coast, that's exactly
what we'll do. The challenge thereafter, once landing at
Edwards, is to transport the orbiters across country, and
that's something that, again, one of the quality assurance
and risk management challenges of dealing with the Shuttle
orbiters. is the more you touch it and the more you fiddle
with it, the more likely is the prospect that you can damage
it. And every time we do that, it gets more and more diffi-
cult to sort with, because, again, it's always launched from
Cape Canaveral at the Kennedy Space Center. So, yes,
Edwards will always be an option, and it's one that we are
not deterred by that challenge if there are factors that dic-
tate the consideration of landing there. In terms of the
Dryden Center, there is no question that the flight opera-
tions activities that are continuing to go on there that cover
a wide range of different supporting efforts that we go
through for unmanned aerial vehicles for the Defense
Department, for a wide range of different programs, no
question we will continue to see that activity unabated
there. And as circumstances dictate, there may be further
flight test requirements that we would conduct there in sup-
port of return to flight activities for the Shuttle.
MR. MAHONE: We're having some technical difficulties
at JPL. so we'll come back to headquarters. And, Mr.
Administrator, if I could start off with Bill Harwood, we'll
start with Bill.
QUESTION: Thanks, Glenn. Bill Harwood, CBS News.
Well, just looking ahead to 1 14, I think the previous ques-
tioner was probably asking you about overflight to land at
Edwards versus Kennedy, just for the record. My
QUESTION: Looking at 1 14, are you committed to not fly-
ing that flight until you have both a tile repair capability
and an on-orbit RCC repair capability, realizing that it's the
RCC that's obviously the long pole in the tent right now.
MR. O'KEEFE: Well, there's no question. The report very
specifically divides the findings and recommendations into
those areas which must be complied with prior to return to
flight. We intend to take that with absolute conviction, no
doubt about it, and we're committed to doing that. Among
them is the point of an on-orbit repair capacity, and that's
the range of options, because it could cover a wide set of
circumstances. We've got to look at what is a responsible
set of options in order to provide that repair capacity, and
those are the things we're looking at right now as weighing
all those options to figure out what's the most appropriate
course on that. But it's one of the requirements within
the — or what we view as a requirement within the report as
a recommendation that must be complied with prior to
return to flight, and we intend to adhere to that.
MR. MAHONE: Mike?
QUESTION: Mike Cabbage with the Orlando Sentinel.
One of the things the Board made pretty clear in their
report was that they have a concern that after you imple-
ment cultural changes, that NASA will sort of backslide the
way that it did after the Rogers Commission. What can you
do to make sure that cultural changes you put in place now
will sfill be in eft'ect 5, 10, 15 years from now?
MR. O'KEEFE: That's a point that we really have spent a
lot of fime. Again, last night the Board was generous with
their time for several hours in sorting through, and that
dominated the discussion in many ways, and they were
consistent and repetitive in their responses to this, which is
it can't be personality dependent. It's got to be a set of insd-
tutional changes that will withstand any change in leader-
ship and management and so forth, and it's got to be a set
of principles and values that are reiterated regularly that
then become institutionalized. So, I mean, the ^m nre of
that is going to be, I think, over time if we se ge
in the mindset. But, importantly, I'm \ - ' the
COLUMBIA
SUPPLEMENTAL MATERIAL
observations that several have made in the pubhc, which is,
yes, we've heard this before, and, yes, they've pledged to
do these things. No question, that's a very clear criticism.
All I can offer is I wasn't here at that time, and a lot of folks
who were in senior management and leadership positions
were not in those capacities at that time either. So we've got
to move forward with the objective of adhering to what the
Board has said, which is to be sure that it not turn on just
the individual personalities involved, but instead become
an institutional set of values and disciplines that will with-
stand that test of time. And that's going to be the real meas-
ure. It's something that, again, the jury's out. We'll see how
far that goes, and I'm certain, I'm absolutely certain that
you will be the judge of that.
MR. MAHONE: Frank?
QUESTION: Frank Sietzen (ph) with Aerospace America.
Among the Board's report — recommendations yesterday
was that the Space Shuttle be replaced as soon as possible.
Admiral Gehman expressed his concern that there wasn't at
least a design candidate on the drawing boards, he said.
Given that, are you looking afresh at when and under what
circumstances to retire the Shuttle? And what kind of mix
of systems do you propose to do so with?
MR. O'KEEFE: Well, it's exactly one of the charges that is
now slightly over 24 hours old that we do, so maybe I
could — if I could ask you for another hour or two to get
through that analysis, it would be helpful. But we are try-
ing, I think, to sort through exactly what the implications
would be there of a range of alternatives. The Board — what
I read and what I saw in the report was very specific in say-
ing that if there is an extension of the Shuttle operations
beyond the beginning of the next decade, it must be recer-
tified. And so establishing what those recertification
requirements would be is part of what I read also to be one
of theif recommendations and findings, that we establish
exactly how we would go about doing that, so that you
make those judgments today so that later, when those deci-
sions are made by all of our successors, that there not be
just matters of convenience taken at the time to determine
what the recertification requirements would be. So that's an
aspect we've got to think about now in anticipation of
tomorrow. And, finally, the approach we have pursued as a
consequence of the President's amendment to last year's
program submitted in November of last year to, as part of
the integrated space transportation plan, is to begin an
effort for a crew transfer vehicle that is focused on crew
transfer capacity as a supplement to that capability that we
have used for both crew transfer as well as heavy-lift cargo
assets on the Shuttle. And so we're pursuing that. There is
a very aggressive effort right now to be very specific and
very deliberate about a very limited number of require-
ments, and I think we have followed through on what the
Board observation on that point is, which is to make sure
that those requirements are very straightforward and not so
extensive that it requires either an invention, a suspension
of the laws of physics, or the use of what Admiral Gehman
referred to last night as a material referred to as "unobtani-
um" in the effort of trying to put together the alternative. So
make sure it's realistic, is something that is technically
doable now, and that is the set of very limited requirements
that we have put together for a crew transfer vehicle that is
the orbital space plane configuration. So we'll see what the
results from the creative juices and innovation of the indus-
try will be here in the weeks and very short months to fol-
low.
MR. MAHONE: Debra?
QUESTION: I'm Debra Zabarenko. I work for Reuters.
You've got a lot of big challenges contained in this report,
but for safety concerns, you can go to safety experts anc
systems analysts. For organizational problems, you can gc
to the folks who are expert there. But one thing the report
said that NASA needs and does not now have is the kind of
urgent mission that it had during the Cold War years. Are
you going to be looking to the White House, to Congress's
Where are you going to go for guidance on dealing with
what seems to be one of the biggest underlying problems
that the report remarked on?
MR. O'KEEFE: Absolutely. Again, as I mentioned at the
very opening of my comments here this morning, in each
of these events of great success and great tragedy it has
been always attendant thereafter with a very extensive
national policy debate. And sometimes that national policy
debate has resulted in a set of objectives that are identified,
and in other cases it has been unsatisfying. Our anticipation
is this next national debate coming is one that we hope and
we certainly plan for it to be a satisfying result. And how
that sorts its way out between our colleagues within the
administration as well as in Congress, and certainly the
general public, is going to be a question that in the time
ahead — and Congress has — the committees of jurisdiction
have planned a set of very aggressive, very extensive pub-
lic hearings in the weeks ahead that I expect will spark thai
debate. And the answer to your question I think will be
resolved from that set of policy debates that will be shortly
coming.
QUESTION: Do you agree with the report's estimation that
that is something that NASA doesn't have right now, an
urgent sense of mission?
MR. O'KEEFE: Nothing comparable to what drove us as a
nation with the threat of the prospect of thermonuclear war
by a bipolar, you know, opponent on the other side of this
globe that existed in the early 1960s. No, we don't have
anything nearly as earth-shattering in that. Thank God.
MR. MAHONE: Frank?
QUESTION: Frank Moring with Aviation Week. Another
thing that the space program needs is money, and there's
been some bad news lately from the — most recently from
the Congressional Budget Office. What is your assessment
of the budget prospects for the space program as this
national debate gets underway? And, also, what do you see
as the cost of meeting — in rough terms, of meeting the!
Gehman recommendations?
MR. O'KEEFE: Again. I would not even speculate on what
COLUMBIA
SUPPLEMENTAL MATERIAL
the national debate that will occur over the federal budget
proposals would yield. That's going to be in the time ahead
as well. That's happening currently. I think you pointed that
very succinctly. As a member of this administration, we
certainly are going to be valuing and evaluating those par-
ticular consequences in the context of what is necessary to
proceed forward with compliance with these recommenda-
tions and what resource requirements we'll have. And cer-
tainly that debate will continue and will go on inside the
administration as well as within the Congress. And so the
results of that will be known in due time. In terms of what
it's going to cost for us to implement, again, if you give me
another hour on top of the one that I asked from Frank to
figure out what the cost is beyond just evaluating a report
24 hours old, we might be able to get back to you. But at
this juncture, I wouldn't even put an estimate or a price tag
on that at this juncture.
MR. MAHONE: Okay. Brian?
QUESTION: Brian Berger with Space News. One of the
points that the report made is that NASA has exhibited a
tendency to bite off more than it can chew, have more ambi-
tion than budget. Can you fix Shuttle, can you complete
Station, and undertake an ambitious effort like Project
Prometheus on the same schedule that you've laid out so
far?
MR. O'KEEFE: Well, again, this is not a new observation,
is your point. It's one that was very clearly driven home to
me in the course of my confirmation hearings, as a matter
of fact, a year and a half ago by several Members of
Congress, that we have had a history of trying to do too
much with too little or not prioritizing sufficiently. And
there are several different ways to go about looking at tech-
nology management. One is what is commonly referred to
within. I think, the technology sector kind of approach,
which is put a lot out there and let a thousand flowers
bloom. And the ones that do come up and the ones that are
considered to be of greatest value, those are the ones you
pursue. Well, maybe that's the closest comparable manage-
ment approach of technology that was pursued within this
agency in the past. Upon my arrival here, in fairly short
order we established that there were three mission objec-
tives: understanding and protecting the home planet,
exploring the universe and searching for life, and inspiring
that next generation of explorers. And if it doesn't fall in
those three mission categories, it doesn't belong here — not
because it isn't a neat thing to do or would be interesting or
whatever else. So in the course of the past year-plus, we've
been really going through the process of winnowing down
what are the programs that really participate and contribute
to those three mission objectives very succinctly, and those
that are neat ideas and good things to do, well, we try to
find some other home for them somewhere else, but not
here, because we're trying to be very disciplined and very
selective about what we do. We've got to continue that
effort and be more deliberate about it in the future, I think,
in finding those efforts that fall within those categories. In
terms of the very specific example that you cited of Project
Prometheus and developing power generation and propul-
sion capabilities, that is something that comes right into our
wheelhouse of the kinds of things we need to be doing, and
it marks the technology kind of prowess of this agency that
it's been known for four decades, which is to overcome
those technical obstacles in order to achieve the next set of
exploration objectives. And so that is there in the program.
It's fully financed. You know, the money that's required and
the resources necessary in order to do so have been
approved within our administration, have been offered to
Congress for their consideration. And we're underway with
that effort because that's one of the serious long poles in the
tent to pursuing future exploration objectives. And so that
one tits very, very precisely within those three mission cat-
egories, without reservation or equivocation.
MR. MAHONE: Mark?
QUESTION: Thank you. Mark Carreau (ph) from the
Houston Chronicle. I think I have a question and a follow-
up, if that's okay. What do you contemplate —
MR. O'KEEFE: How can you have a follow-up when you
haven't heard the answer yet? [Laughter.]
MR. O'KEEFE: Sorry. Go ahead.
QUESTION: Okay.
MR. O'KEEFE: Pardon me. I didn't mean to be flip.
QUESTION: That's okay, sir. Thank you. What do you
contemplate doing or saying to your managers and work-
force to explicitly uncouple schedule pressure to build the
Space Station from the Shuttle recovery?
MR. O'KEEFE: Well, let me take the first part of that
because I'm not sure — Shuttle recovery, do you mean
return to flight?
QUESTION: Yes, sir.
MR. O'KEEFE: Okay. I'm sorry. Again, the point that I
think was very clearly enunciated in the report that resonat-
ed with me is that this may have begun to influence the pro-
gram manager's view of how you proceed to meet mile-
stone objectives. Again, that's a useful, very valuable man-
agement tool that has to establish goals. It's a leadership
principle. You have to have folks — again, it's part of the
point that was raised in several other questions earlier, too,
that you have to have goals, you have to have objectives,
you have to enunciate what they are and when you intend
to achieve them. That's part of any other aspect of what we
do. The really profound point, I think, that the Board raised
was that there was some mixed signal, miscommunication
of that point, of which was more dominant. And so the
checks and balances must be established, and they were
very clear on that point repetitively in their — in every part
of the report, that what we need to do is establish institu-
tionally an ethos, a set of values, a discipline that really
encourages folks to have an open communications loop, to
express when they believe something to be not safe at that
time to proceed with. Now, that may not rule the day. It
may not be, well, in that case, since you've simply asserted
COLUMBIA
SUPPLEMENTAL MATERIAL
it, it must be so. There really is a case in which we've got
to demonstrate that it is safe, and that's a very ditferent
approach that now the burden of proof, I think, has to be
reiterated in that direction as well. So as we move through
this, establishing what those institutional checks and bal-
ances will be. and part — I think the answer to that one in
this particular instance is assuring that that communication
loop is very open and that there is resolution to each of the
objectives or objections heard so that everybody is heard
and that crisp decisions are made thereafter in terms of how
to serve it up and follow through from there. Once you've
heard it, your follow-up?
QUESTION: Yes, my follow-up is: Do you need the flexi-
bility to deal with the Russians, contract with the Russians,
or whatever, to give you this time so that you have the sup-
plies aboard the Station? And how do you deal with your
international partners' expectations of having their equip-
ment aboard, that there's commitments made even above
your level to try to do that that you have to respond to? And
I'm wondering how you deal with the workforce, but also
deal with that issue.
MR. O'KEEFE: That's a very important question and one
that we've taken extremely seriously. But I'm very, very
impressed, with the response of our international partners
and their capacity to really act like partners in an
International Space Station effort. This is an endeavor pur-
sued by 16 nations, and they have responded very, very
definitively. So in working through all those issues, as
recently as a month ago I met with all the heads of agencies
of the International Space Station partnership, and we
worked through all of the challenges that, as we sort
through the months ahead and anticipate return to flight,
that there be a lot of obligations and commitments. We're
going to continue to look to them and to us to honor as we
work through this. And we have — I've got a very clear
understanding with them, and they have been really just
exemplary in the manner in which they've done that. So I
have — we've all taken a part of the responsibility of this,
and we all view this as a partnership challenge. This is not
something which they say, you know, to the United States,
"What are you going to do to help us out today?" No.
They've been very forthcoming in terms of their approach
and accepting their piece of the partnership responsibility
in doing this. It's been commendable.
MR. MAHONE: We're going to go right here.
QUESTION: Mr. O'Keefe, Peter King, with CBS News
Radio. Yesterday, we read the report, of course, and there
were lines in there that expressed pessimism that NASA
would be able to change, and in an interview after the
report was issued. Admiral Gehman told my colleague. Bill
Harwood, that some are or will be in denial about the
changes needed and the flaws in the system. What message
have you or will you send to those particular people at
NASA?
MR. O'KEEFE: Well, again, and this is reminiscent of
some of the earlier comments that we have shared here, this
is tough stuff, and we shouldn't be a bit surprised when
engineers, and technical folks and all of the rest of us as
colleagues here in NASA act like all other human beings
doing, which is, when you hear something, it really is
tough, and it's hard to accept that it takes a little effort to
work through it. And that's exactly what we've been really
endeavoring to do in the last few months here is just kind
of steeling ourselves for what we asked for, which was an
unvarnished position, a very direct report, take off the
gloves and let us know what's wrong. We didn't ask
Admiral Gehman and his colleagues to tell us what's so
right about this place. I mean, that's something that has,
you know, again, been widely viewed as "over-thought" of.
We got that point. The issue is we really wanted to know,
in a very clear, distinctive way, exactly what they thought
was flawed about the way we do business, what caused this
accident, what were the contributing factors, all of the other
things that may go to it, and they complied with that, and
they did it with great skill, and it could — I can't imagine
what the deliberations among the Board members must
have been over these past several months. Trying to get 13
very, very smart, very thoughtful, very Type A people to
come to closure on a set of views could not have been an
easy task. And you can see that they really worked through
some very differing approaches that ultimately came to a
very crisp set of conclusions. So I think that's something
we've got to work through, and this is part of the process
we've been engaged in for the last few months is kind of
strapping ourselves in for the fact this was going to be an
unvarnished view and a very clinical, direct, straightfor-
ward position, and it has been. We got what we asked for,
and there's no question that we now need to go about the
process of all of the steps that it takes in order to accept
those findings and to comply with those recommendations,
and that's a commitment we're not going to back off of.
QUESTION: Todd Halvorson of Florida Today. Now that
you have had the CRIB report for 25 hours, and given the
fact that you've gotten a good head start on your retum-to-
flight activities, what are your thoughts now about your
ability to make that March through April window for return
to flight next year, and what are your thoughts about when
you can get to core complete?
MR. O'KEEFE: Well, the answer to both is we'll see. From
the technical hardware standpoint, all of the assessments
we've gone through here in the last couple three months are
there are a number of options that would certainly permit
an opportunity after the new year to look at a retum-to-
flight set of objectives, and we've reviewed those with the
Board. They're aware of that activity, and that's underway.
The larger questions I think that are raised in this report,
too, that deal with some of the management systems, the
processes, the procedures, the, again, the culture of how we
do business, we really have to set this bar higher than what
they did, what anybody would do. The standards that we
are expecting of ourselves, we need to be our toughest crit-
ics on that. And so those are going to be a little more diffi-
cult to I think assess in terms of a calendar or a time line,
in terms of when they're done, and instead I think it's going
to be a case where, when we've made the judgment that we
are fit to fly, that's when it's going to occur.
COLUMBIA
SUPPLEMENTAL MATERIAL
Now. we're not going to just do this in isolation or a vacu-
um. We've asked a very impressive group of 27 folks who
are part of the Tom Stafford and Dick Covey's Return-to-
Flight Task Group to help us work through those options
and assure that we're not just, you know, drinking our own
bath water on this or singing ourselves to sleep on the
options we love the most, you know. It's a case where we
really want to lay out the full range of things we're going
to do and have their assessment of whether they think that
passes the sanity check. And that group of folks, I would
suggest to you. if you haven't had the opportunity to do so,
to look at the varied backgrounds that those 27 people
bring, not only the technical and engineering and I think
smart folks on the hard sciences side, but also a lot of man-
agement experts, a lot of folks who have dealt with large
organizations, dealt with culture change. Walter Broadnax,
who was the deputy secretary in the last administration for
the Health and Human Services, is a member of that. He is
now the president of Clark Atlanta University. This is a guy
who has been through several different organizational
shifts working for the State of New York, working for the
last administration at HHS, and so forth, dealing with very
large organizations, understanding management culture
change requirements. Richard Danzig, who was the last
Secretary of the Navy in the last administration, as well,
was a member of this. Ron Fogleman. who was the Chief
of Staff of the Air Force, who really set some standards in
the Khobar Tower incident over what accountability stan-
dards should be adhered to within the Air Force, is a mem-
ber of this group. So if you work through every one of
those, what you find are folks that aren't just — or I should-
n't say "just" — it's not dominated by a group of folks look-
ing strictly at the engineering-hardware kinds of chal-
lenges. It's also looking at these larger systems process
changes, and those are the kind of folks that have been
added to this, including a number of academics who have
written about it, and thought about it, and worked through
it like Dr. Vaughn and others, colleagues of hers, who have
really looked at organization change issues and, in turn, are
going the help us really think through this. And they've
been there, done that, gotten several T-shirts and recog-
nized lots of tendencies on the part of organizations or
institutions to select options that may or may not be more
or less convenient. They're going to be good sanity check-
ers as we work through that, and those are the kinds of peo-
ple I think that their judgment will be invaluable as we
work up to that inevitable retum-to-flight milestone.
MR. MAHONE: And the complete list of those members
are at www.nasa.gov. You can go to that and find their bios
and so forth. A question right here.
QUESTION: Jim Oberg with NBC. I'd like to ask a ques-
tion on culture and the issues of intellectual isolation of the
NASA community from the outside world. The Board and
other people have mentioned words, from the Board exam-
ple, self-deception, introversion, diminished curiosity
about the outside world, NASA's history of ignoring exter-
nal recommendations. These are some pretty serious
charges, and people have seen evidence of it. The Board did
and other people have mentioned it, too. You have a situa-
tion where people who are here now are almost hunkering
down into a siege mentality, where outside critics are cold
and timid souls whose views should be ignored. How can
you get the people to become what the Board wants you to
be, a learning organization like that, when many of the
same people who have been immersed in this culture for all
of their working lives are the ones designing, developing
and judging the success of your recovery process?
MR. O'KEEFE: Again, you have accurately recited what
are the findings of the Board and their overarching view of
what they have deemed or viewed to be the culture within
the agency. The first step in any process is to accept the
findings and to comply with those recommendations, and I
think Admiral Gehman had been very fond of saying to the
Board. "T equals zero," zero meaning anything that hap-
pened after February 1st is not something they're looking
at. They're really focused on examining that. Well, to
NASA today, T equals zero starts today, and we've really
got to work our way through accepting those findings and
complying with those recommendations and that will be
the beginnings I think of sorting our way through these
larger institutional challenges. I think the questions and
comments and observations made by your colleagues here,
as well as in my statements at the opening of this, suggest
we've got to being that process and work with what is a
very professional group of folks throughout this agency,
who I think can step up and accept those responsibilities,
and we all have, in working through this, and recognizing
that this is a institutional set of failures that must be
addressed. I don't see that the reticence on the part of any
individual in this agency is going to be a setback in that
regard. We've just got to work through that very methodi-
cally, very deliberately, very consistently, and employing a
principle of the United States Marine Corps that I always
found to be pretty pointed, which is "repeated rhythmic
insult." If you always say the same thing, and you mean it,
and you keep going at it, and you stick with that set of prin-
ciples and values and discipline, it's going to resonate in
time, and in time means sooner rather than later in order for
us to really reconcile and come to grips with these findings,
and accept them, and comply with those recommendations.
MR. MAHONE: Question, here.
QUESTION: Bill Glanz, Washington Times. I just want to
find out what your gut reaction was while you were read-
ing that part. For instance, were you appalled at some of the
decisions that the program managers made, and also, when
you were reading it, did you have any "holy crap"
moments? [Laughter.]
MR. O'KEEFE: I've had so many of those since February
1st I can't count them all any more. Again, this was not a
surprise. Among the emotions that I felt in reading through
this, surprise was not among them, because again, they
were very faithful in what they said they would do. Admiral
Gehman and every member of that Board were very, very
clear in the course of their proceedings of saying, "What
we're telling you and what we're inquiring about in these
public hearings is what you will read in this report." Very
explicit about that. They never walked away from that
point. Again, talking about repeated rhythmic insult, that
COLUMBIA
SUPPLEMENTAL MATERIAL
was, a repetitive commentary that they followed through on
and did precisely what they said they were going to do. So
in reading through this, and again, our approach from day
one, from the 1st of February on, was again to be as open
as we possibly could conceive of being, release all of the
information for everybody to see what was going on. So
reading lots of the discourse and back and forthing and
communication that went on that are now faithfully repeat-
ed in the report, was not the first time I'd read them,
because we released them a lot here, and they talked about
them a lot in the hearings, and so in the course of this, I
think the terminology they used was very consistent with
what I heard in the course of all those public hearings. And
after 22, 23 hearings that lasted on average three-and-a-half
to four hours each, that was a lot of volume. So really, dis-
tilling all of that and coming up with a report that was as
succinct as this is, that it was only 248 pages by compari-
son to the thousands of pages of transcripts from all those
hearings, was really the part that I found most impressive,
was they were able to distill this into a very pointed set of
findings and recommendations. But surprise was not
among them, and there was nothing that I saw there that
they had not previously talked about. They were very, very
conscientious about following through on that commitment
and they did what they said they were going to do.
QUESTION: [Off microphone] — appalled by some of the
decisions that the program managers made, you know,
being pressured by the long schedule, and all the missed
opportunities that they mentioned in the report?
MR. O'KEEFE: Again, I mean the course of this. There
have been countless hearings that I've been a witness at.
There have been lots of different opportunities where we
have gotten together among your colleagues in the press
corps to discuss several of the events as we've walked
through this in the last seven months. At each one of those
there were plenty of cases in which you said, gosh, how
could this have happened? But there's no question. None of
it was a new revelation in that regard. It has been all by
degrees over time in these last six, seven months, you
know, rolling out and laying out in ways that we have real-
ly seen institutionally as well as with the hardware, as well
as human failures were that led to this. By all means, they
are a guidepost to figuring out exactly how you improve
that communicate net, sharpen the decision-making
process that informs, decision-making that includes all the
information that's necessary to make those kinds of judg-
ments at the time, and I think that's exactly what we saw
come out of this.
QUESTION: Chris Stolnich from Bloomberg News. I was
just wondering if you could describe what you believe the
goals for manned space flight are in the wake of this report,
and how or if they should change?
MR. O'KEEFE: We are, and have always been, dedicated
to exploration objectives which in some instances require a
multitude of different capabilities, to include human inter-
vention. What we've laid out is a strategy, a stepping stone
approach in which we conquer each of the technical and
technology limitations as we pursue greater opportunities.
Calls for a sequence of capabilities, which we see playin;
out right now. In early January we're going to see two
Rovers land on the planet Mars, and it will follow, as it did,
several other missions that preceded this, in order to colled
and gather the information and the knowledge necessary to
inform the opportunity for human exploration at some
point. And as we prepare those capabilities to proceed, we
have a more complete knowledge of precisely what it is
we're going to encounter, and what will be garnered am
gathered from that set of missions and those that will fol
low, which are robotic, will inform that decision makin;
and inform that understanding and judgment about exacti]
how human exploration thereafter could be permissible
The second phase of it though is an important one, becaus
your question I think also speaks to the immediacy o
instances and cases in which human involvement is imper
ative in order to preserve capacity.
Today there's a spirit of debate that's going on, that again
I commend you all for having covered rather broadly, o
exactly what is going to be the service life of the Hubble
telescope. Just launched on Monday the SIRTF infrared tel-
escope that will be a companion to Hubble, if you will, foi
all the infrared lower temperature observations and read-
ings that could be observed by that imagery. But recall thai
the history of Hubble — which I have not seen very exten-
sively discussed in all the coverage of the current debate
about how long Hubble should be operational and whal
servicing missions are necessary — the history of that was
your predecessors 10 years ago roundly viewed the deploy-
ment of that capability as a piece of $1 billion space junk
because it couldn't see. The lens needed correction. Il
required a Lasik-equivalent surgery. And the only way thai
could be done was by human intervention. So in 1993 wher
that mission was launched to correct the Hubble, that was
done successfully, and the only way it could be done was
because a human being, several of them, spent many, manj
months training to be prepared for making those correc-
tions on the spot, and for every contingency that could arise
as you work through it. It was nothing we could do, adjusi
from the ground. The last round trip flight of the Columbia
in March of 2002 was to the Hubble again to service it, to~
install new gyros, to install an infrared camera, to upgrade
a number of different factors to it that improved its capaci-
ty by a factor of 10, according to all the astronomers who
observed this, and they are just elated over the quality of
what has come back from this. And yet it turned out that the
primary human characteristic that was so important on that
mission was embodied by a gent who will be joining us
here in about a month, or a matter of fact, weeks — I'm los-
ing track of days here — Dr. John Grunsfeld, who will be
our Chief Scientist, and relieving Dr. Shannon Lucid, as
she goes back to Johnson Space Center, as our Chief
Scientist. He was on that mission. He"s an astrophysicist,
got all kinds of incredible scientific background. But his
primary human characteristic trait that was most valuable
proved to be that all the instruments for adjustment on the
Hubble telescope are on the left-hand side.
So rather than having, like many of us — righties are stuck
with the problem or reaching around the front of your face
with a catcher's mitt equivalent capacity to adjust things,
COLUMBIA
SUPPLEMENTAL MATERIAL
and a big bubble over year head, trying to see what's going
on — his primary human characteristic that was most valu-
able is he's a lefty. He's now referred to as "the southpaw
savant." But it was a human characteristic that made those
adjustments, that made that capacity work in a way that we
never imagined possible, and that 10 years ago we were
prepared to write off as garbage. And instead today, it's rev-
olutionizing not only the field of astronomy, but also
infonning all of us as human beings of the origins of this
universe, its progression over time. It has changed the way
we look at everything. In the last 18 months it has been a
remarkable set of discoveries that have emerged from that
capability that would never have been possible were it not
for human intervention. So those are the two areas we real-
ly have to focus on, is recognizing how we can advance the
exploration opportunities by being informed as deeply as
we can through a stepping-stone approach of always devel-
oping those capabilities and technologies that then permits
the maximum opportunity for human involvement, and
then in those cases in which nothing else will do than
human intervention and cognitive judgment and determina-
tion, and making selections that only humans can do, where
do you use those judiciously in order to avoid the unneces-
sary risk that's attendant to space flight for only those pur-
poses and causes that are of greatest gain.
MR. MAHONE: Riaht here.
kinds of leaders who very clearly understand, they get it,
that this is about institutional change. Those are the folks
that I fully anticipate are going to be the ones who will be
the folks who will cany this out and accomplish the objec-
tives we talked about here today, and they in turn select
those managers, engineers, technical folks who share that
same ethos. So as we work through this we've got to be
very, very deliberate in relying on the judgment of individ-
uals who have committed to those objectives. And I encour-
age you to just kind of scan through the senior leadership
as well as the senior positions here throughout the agency
that have been conducted, and you'll find a rather signifi-
cant new management team in those capacities, new lead-
ership team, and all of them share the view that I've just
talked about here, which is this is an institutional challenge
which is greater than any one of us individually or even
collectively. It's about the longer-term values, discipline
and principles that this agency should adhere to, and they
share those goals and views.
MR. MAHONE: Last question.
QUESTION: Steven Young with SpaceFlightNow.com.
I'm wondering if you've actually read the report cover to
cover, or whether you intend to do that, and whether you
would make it required reading for NASA employees and
contractors?
QUESTION: David Chandler with New Scientist
Magazine. One thing that the Board explicitly avoided talk-
ing about, not because they didn't think it was important
but because they didn't see it as their role to do, was issues
of personal accountability. I'm wondering what your
thoughts are on whether it is your role, and for example,
people within the agency who failed to follow NASA's own
rules. What kind of a message about the importance of
safety will be sent if there is no personal accountability or
personal consequences for people who didn't follow your
own rules in this mission?
MR. O'KEEFE: Well, first and foremost, I am personally
accountable, myself, for all the activities of this agency. I
take that as a responsibility and I do not equivocate on that
point. I think it is absolutely imperative that we all view our
responsibilities, and that one is mine. The approach I think
that is absolutely imperative to follow through with in this
institutional change that we've talked about here, and had
lots of different comments and observations about, that the
report covers in depth, is that you must select folks in lead-
ership and senior management capacities who understand
exactly what that set of institutional change requirements
are. So rather than saying I'm going to remove so-and-so.
it's more a case of, I need to appoint folks who understand
that. At this juncture of the four space flight centers that
have any specific activity over Shuttle operations.
International Space Station, et cetera, so among the 10 cen-
ters there are four that specifically and uniquely deal with
space fiight operations. The longest-serving tenure center
director was appointed in April of 2002. He is now the
elder statesman among them. The rest have been appointed
since. And those are the folks who are, in my judgment, the
MR. O'KEEFE: I think I don't need to direct that it be
required reading. I haven't run into anybody in this agency,
any colleague in the organization who have not felt that this
is something they want to read in its fullness. So I think no
amount of direction from me is going to make a difference.
People are doing it because they view that as a responsibil-
ity, that we all need to view this is a responsibility that all
of us must carry. I have read through it as of — again, it was
a long day yesterday, but I started when Admiral Gehman
dropped it off at 10 o'clock yesterday morning, so I had
about a one hour head start from his press conference. And
again, what I found in reading through it was that it remark-
ably patterns exactly what they said in all their public state-
ments. So in many respects I was reading the same things
I've been hearing, in listening to those public hearings, lis-
tening to their public comments. I've got to go back this
weekend and read every single word for its content to do
that right, but in reading through it briskly, as of yesterday
morning and then last night after we left them, after a long
session with them, had a chance for several hours to read
through it again. But again, it struck me immediately as
being remarkably close and right on to what it is they've
been saying. So there were no surprises in that regard. But
this weekend, you bet, word for word, from the first page
to the last word on page 248 is what I intend to read. I don't
need to instruct that anybody in the agency do that. I'll bet
everybody is, because I think this is the sense of responsi-
bility we all need to share, and I think that doesn't need to
be directed by anybody.
MR. MAHONE: Mr. Administrator, thank you very much,
and thank all of you for being here today. [Whereupon, at
12:31 p.m., the press briefing was concluded.]
The Mission Reports Series.
Freedom 7 ISBN 1896522807 America's first man in space Alan B Shepard Jr. puts
the US firmly in the race against the Soviets. Includes CD Rom
Friendship 7 ISBN 1896522602 John Glenn pilots the US first manned orbital
flight in 1962 and becomes a national hero. Includes CD Rom
Gemini 6 ISBN 1896522610 Piloted by Mercury astronaut Wally Schirra and Tom
Stafford; the US achieves the first rendezvous in space with Gemini 7. Includes CD Rom
Gemini 7 ISBN 1896522823 Frank Borman and James Lovell not only achieve the
first rendezvous with Gemini 6, but go on to an endurance record of two weeks in
space. Includes CD Rom
Apollo 7 ISBN 1 896522645. Wally Schirra takes the helm again to prove that
America's Apollo moonship can perform flawlessly for a full 8 days. CD Rom
Apollo 8 ISBN 1896522661 Borman, Lovell and Anders pilot the Apollo spacecraft
out of Earth orbit to the moon for the first time in human history. Genesis is read
from Lunar orbit on Christmas eve 1968. CD Rom
Apollo 9 ISBN 1896522513 This mission to test the full Apollo configuration
including the LM had so many firsts it was almost a space program in its own right.
CD Rom
g,
Apollo 10 ISBN 1 896522688 The penultimate full up test of the CSM and LM in
lunar orbit before the landing. The crew was probably the best ever to fly and they
had a, blast doing it. CD Rom
Apollo I I Vol. One ISBN I89652253X Neil, Buzz and Mike take that "One small
step.." and succeed in completing the greatest scientific achievement ever in the his-
tory of mankind. The first manned landing on the moon. CD Rom of the EVA and over
1200 color photos.
Apollo I I Vol. Two ISBN 1896522491 The crew debrief of the mission, that was
declassified specifically for this book.The story of the first moon landing in the crew's
own words, including that pesky UFO sighting. CD Rom with interactive lunar panoramas
and exclusive interview with Buzz Aldrin.
<^
9 .-S
:2l
V' >
Apollo I I Vol. Three ISBN 1896522858 The crew performed many scientific
tests on the moon, here is what they found. The DVD includes the landing video and EVA
in a highly acclaimed format never seen before.
Apollo 12 ISBN 1896522548 "It may have been a small one for Neil, but it was a
big one for me!" Pete Conrad and Al Bean prove that a landing can be bang on target.
CD Rom includes the full EVA and exclusive interview with Dick Gordon.
Apollo 13 ISBN 1896522556 Possibly the US space programs finest hour.
Find out what went wrong and how they saved this dramatic mission that
almost resulted in the deaths of the crew. Exclusive video interview with Copt.
Loveli
Apollo 14 ISBN 1896522564 It was up to America's first astronaut, Alan
Shepard and his crew to get back to the moon and to... play a little golf! CD
Rom.
Apollo I 5 Vol. One ISBN 1 896522572 Dave Scott and Jim Irwin land in the
middle of a mountain range with their little moon buggy to go for a spin; while
AlWorden conducts many experiments in lunar orbit. Includes CD Rom
Apollo 16 Vol. One ISBN 1896522580 Capt. John Young (The astronaut
King) and Charlie Duke spend three days on the highlands at Descartes in typ-
ically flawless Young fashion. CD Rom includes hours of EVA footage.
Apollo 17 Vol. One ISBN 1896522599 The last men on the moon, Gene
Cernan and Jack Schmitt (the first scientist to make the trip) almost make the
whole thing look routine because they have so much fun. CD Rom
Space Shuttle STS I -5 The NASA Mission Reports. ISBN 1896522696
The first amazing five missions of the Space Shuttle Columbia with crew
debriefings and mission reports. CD Rom hours of video and lOO's of photos.
X-15 ISBN 1896522653 Before and whilst the US space program was in full
swing, there was another group of men becoming astronauts in a very promis-
ing precursor to the Shuttle program. Some wonderful film of rocket planes in
full flight. CD Rom
Mars: The NASA Mission Reports. ISBN 1896522629 Every mission to
Mars from Mariner 4 to Global Surveyor See how our knowledge of the red
planet has grown exponentially since the 60's. CD Rom with 1,000's of photos.
The Apogee Space Series
Rocket & Space Corporation Energia ISBN 1896522815 For the first
time in English a pictorial history of the Russian Space program from the I940's
through Sealaunch.
Arrows To The Moon ISBN 1896522831 Did you know that in 1958 the
most advanced fighter aircraft in the world was not US or Russian? It was
Canadian! When their government cancelled that program many of the aero-
space engineers went on to become an integral part of NASA.
The High Frontier ISBN I89652267X Gerard O'Neill writes about human
colonies in space. The book that inspired the founders of the Space Frontier
Foundation, among others. Includes 6 new contemporary chapters by leading
visionaries.
The Unbroken Chain ISBN I89652284X by Guenter Wendt and
Russell Still. The man who tucked all of the astronauts in their couches, shook
their hands and closed the hatch from Alan Shepard through Shuttle. An amaz-
ing story! Hardcover with CD Rom
D
Creating Space ISBN 1896522866 by Mat Irvine.The story of the Space
age told through model kits. Color book with foreword by Sir Arthur C Clarke.
Women Astronauts ISBN 1 896522874 by Laura Woodmansee. Every
woman who has ever flown in space, how they did it and more importantly
WHY they did it. Full color with CD Rom, which includes exclusive interviews with
current astronauts.
On To Mars ISBN 1896522904 Edited by Dr. Robert Zubrin. Many
papers presented at the annual Mars Society Conferences, from the scientific
to the moral and ethical questions posed by colonizing a new world. CD Rom
The Conquest of Space ISBN 1896522920 by David Lasser.The first sci-
entifically accurate book written about space travel in the English language. This
book is the one that inspired people like Sir Arthur C. Clarke to become inter-
ested in space. It still holds up today and is a wonderful reference for the
novice.
Lost Spacecraft ISBN 1 896522882 by Curt Newport. The search and
recovery of Gus Grissom's Liberty Bell 7 space ship by the man who did it.This
was the subject of a major Discovery Channel program. CD Rom
Virtual' Apollo ISBN 1 896522947 by Scott Sullivan. If you ever wanted to
know how to build a moonship here it is in awesome 3D color computer
graphics.
A Vision Of Future Space Transportation ISBN 1 896522939 by Tim
McElyea.The Official publication of SpaceDay 2003 by the man who produces
the computer simulations of future spacecraft for NASA and the USAF. Includes
CD Rom with animations, videos and 3D renderings.
Apollo EECOM ISBN 1 896522963 by Sy Llebergot. The amazing and
heartrending story of one of the key figures in US space history.The first man
in Mission Control to acknowledge that Apollo 13 really did have a problem.
CD Rom
Interstellar Travel & Multi Generational Spacecraft ISBN 1 896522998
by Yojl Kondo and others from Goddard Space Flight Center. If you
really wish to travel to the stars, these guys are the ones who could "make it
SO!
I"
Space Trivia ISBN I89652298X by Bill Pogue.The latest book from the
Skylab astronaut who brought us, "How Do You Go To The Bathroom In Space"
a space bestseller. I OOO's of irreverent facts about how and why we go to space.
Dyna-Soar ISBN 1 896522955. Called "A treasure trove..." by IEEE Spectrum.
The complete story of America's first military space shuttle and how it could
have flown in the early 1 960's. DVD
The Rocket Team ISBN 1 894959-00-0 by Frederick I Ordway III &
Mitchell Sharpe. The historic tale of Germany's amazing rocket engineers
from PeenemiJnde to the Moon. Now with a DVDl
B»l
Q
Check us out on the Web -
http://www.apogeebooks.com
Return this completed
form and become eligi-
ble to win
free books!
One new space book
almost every month!
The worlds number
one space book pub-
lisher!
NO POSTAGE
NECESSARY
IF MAILED
IN THE
UNITED STATES
BUSINESS REPLY MAIL
FIRST CLASS MAIL PERMIT NO. 350 WHEATON IL
POSTAGE WILL BE PAID BY ADDRESSEE
COLLECTOR'S GUIDE
PUBLISHING INC
P.O. BOX 4588
WHEATON, IL 60189-9937
l..l.l.l..l.l..l.l..,.ll.l...ll..l.l
Check us out on the Web -
http://www.apogeebooks.com
Return this completed
form and become eligi-
ble to win
free books!
One new space book
almost every month!
The world's number
one space book pub-
lisher!
NO POSTAGE
NECESSARY
IF MAILED
IN THE
UNITED STATES
BUSINESS REPLY MAIL
FIRST CLASS MAIL PERMIT NO. 350 WHEATON IL
POSTAGE WILL BE PAID BY ADDRESSEE
COLLECTOR'S GUIDE
PUBLISHING INC
P.O. BOX 4588
WHEATON, IL 60189-9937
I, II. .11 Ill..l.l.l..l.l..l.l.,..ll.l...ll..l.l
THE SPACE BOOK COMPf
DATE DUE
y/^/oY
P.O. BOX 4588
WHEATON ILLINOIS 60189-9
HTTP:/AWWW.APOGEEBOOKS_
NAME: (Please PRINT)
Company:
Address:
City:
E Mail:
Where did you buy this book?"
Bookstore Chain LJ lndep(
THE SPACE BOOK COMF.
GAYLORD
PO. 80X4588 -..^ ,_c-«_i rar»xcie.
WHEATON ILLINOIS 60189-9937 - "^l-dteS.
HTTP;//WWW.APOGEEBOOKS.CO'
ipany, with almost
d every month.
Jnt your address below,
ss below) *
■ burse this email address to any other
I purposes.
Other n
PRINTED IN USA.
npany, with almost
"^ cwory month.
{address below.
Report
NAME: (Please PRINT)
Company:
Address:
City:
Astro TL 795. 5 . U53 2003
United States.
Report
E Mail:
Where did you buy this book
Bookstore Chain CH indef
lail address to any other
Other n
WELLESLEY COLLEGE LIBRARY
3 5002 03423 2616
Bonus CDRDM features: The entire contents of the CAIB
CDRDM WITH NEARLY 1 DDMB OF video PLUS OVER 7DD PAGES
OF NASA DOCUMENTS, INCLUDING THE STS-1D7 PRESS KIT
AND NASA'S Implementation Plan for Return to Flight &.
Beyond.
1-894959-06-X
781894"959063
Box 62D34, SURLINGTDN
Dntarid, LVR ^KZ. Canada
HTTP://WWW.APaBEEBDaKS.CDM
us $25.95
CAN $33.95
UK C 1 9.95