Skip to main content

Full text of "The Russell process at Yedras, Sinaloa, Mexico. Comparison with the Patera, or old leaching process. Lixiviation of old tailings"

See other formats


BANCROFT 
LIBRARY 

<» 

THE  LIBRARY 

OF 

THE  UNIVERSITY 
OF  CALIFORNIA 


THE  RUSSELL  PROCESS 

AT  THE  YEDRAS  MILL. 

BY  ROBERT  F.   LETTS, 


LATE    SUPERINTENDENT    OF    MILL. 


The  Russell  Process  was  introduced  at  the  Yedras  Mill  (Anglo- 
Mexican  Mining  Company)  in  November,  1887,  and  has  been  in  con- 
tinuous use  since  then,  having  superseded  the  old  leaching  process 
which  had  been  previously  employed  in  the  treatment  of  this  ore. 
The  object  of  this  article  is  to  compare  these  two  processes,  as  well  as 
to  give  such  statistics  on  mill  work,  results  obtained  and  expenses,  as 
will  be  of  general  interest,  without  going  too  much  into  the  technical 
details  of  the  two  processes. 

The  statistics  here  given  have  been  accumulated  during  my  con- 
nection with  the  Anglo-Mexican  Company,  extending  over  a  period 
of  six  years,  both  before  and  after  the  introduction  of  the  Russell 
Process,  and  the  results  here  given  cover  not  only  the  treatment  of 
Yedras  ore  by  that  process,  but  also  the  re-treatment  of  all  the  old 
tailings  which  had  previously  been  produced  by  the  old  leaching  pro- 
cess. 

The  metallurgical  history  of  the  Yedras  mill  is  as  follows  : 

Smelting  being  economically  and  metallurgically  out  of  the 
question,  it  was  originally  intended  to  work  Yedras  ore  by  roasting 
in  Bruckner  furnaces  (four  of  which  were  erected  at  the  mill)  and 
treatment  by  amalgamation. 

But  it  was  soon  discovered  that  neither  these  furnaces  nor  the 
amalgamation  process  would  work  on  this  ore.  Not  only  was  it  im- 
possible to  obtain  sufficiently  good  roasting  results  in  the  Bruckners, 
but  then  the  ore  was  not  in  suitable  condition  for  the  subsequent  treat- 
ment. Long  reverberatory  furnaces  were  therefore  adopted  for  roasting 
and  the  old  leaching  process  for  the  extraction  of  the  silver. 

This  course  was  pursued  for  about  three  years,  during  which 
time  I  suppose  the  extraction  of  silver  did  not  average  over  65  per 
cent,  of  the  value  of  the  roasted  ore. 

In  order  to  increase  the  extraction  the  Russell  Process  was  intro- 
duced. The  result,  the  first  three  months,  as  shown  by  the  report  of 
the  superintendent  of  the  mill,  was  a  saving  at  the  rate  of  $100,560 
U.  S.  coin  per  year,*  the  gain  in  extraction  by  the  use  of  the  Russell 
Process  being  17.47  per  cent,  of  the  value  of  the  ore  more  than  could 
be  obtained  by  the  old  leaching  process.  These  comparative  results 

*  NOTE  — In  this  and  subsequent  statements  the  royalty  for  use  of  process  ''s  omitted. 


were  obtained  by  running  the  two  processes  side  by  side  on  the  same 
ore  for  three  months.  Subsequent  tests  showed  similar  results,  and 
are  given  in  the  superintendent's  reports  at  the  end  of  this  article. 

The  property  of  the  Anglo-Mexican  Mining  Company  is  situated 
on  an  eastern  spur  of  the  Sierra  Madre  mountains  in  the  state  of  Sin- 
aloa,  Mexico,  and  can  be  reached  from  Jimenez,  in  Chihuahua,  by 
stage  to  Parral,  and  then  by  mule  for  eight  to  ten  days  over  a  moun- 
tainous trail  to  Yedras. 

The  mill  plant  consists  of 

2  rock  breakers, 

2  shelf  ore  dryers, 

1  shelf  salt  dryer, 
40  ore  stamps, 

5  salt  stamps, 

8  reverberatory  furnaces, 

14  ore  leaching  vats,  n  ft,  8  in.  diameter,  by  5  ft.  2  in.  highr 

2  wash  water  precipitating  tanks,  21  ft.  diameter,  by  5  ft.  high, 

2  solution  precipitating  tanks,  14^  x  pX, 

3  solution  precipitating  tanks,  io}4  *  9/4, 

1  solution  storage  tank,  n  x  8X, 

2  solution  storage  tanks,  9  x  42/3, 
i  sulphide  sump  tank,  7^  x  4^3, 

1  sodium  sulphide  mixing  tank  (iron)  3x7, 

2  sodium  sulphide  storage  tanks  (iron)  3^  x  5. 

The  variations  in  size  of  the  tanks  and  vats  is  explained  by  the 
fact  that  the  leaching  department  was  made  to  suit  existing  circum- 
stances as  to  grade  and  area,  otherwise  the  ore  vats  would  have  been 
made  larger  and  the  tanks  generally  of  more  uniform  size. 

The  leaching  department  at  Yedras  has  a  capacity  of  about  60 
tons  per  day,  occupying  a  building  60x100  feet. 

The  following  are  two  analyses  of  Yedras  ore,  representing  the 
averages  of  the  ore  treated  at  different  periods  : 

No.  i.          No.  2. 

Carbonate  of  lime 33.78        46.50 

Silica 15.13        25.00 

Iron 17.33          9.80 

Sulphur 13.31        12.50 

Arsenic 9.82          2.50 

Zinc  4.92 

Lead 1.78 

Magnesia 2.58 

Alumina 1.35 

No.  2  is  an  analysis  of  the  average  battery  sample  for  one  month. 
The  composition  of  the  ore  varies  greatly.  A  couple  of  months  after 


the  above  analysis  No.  2  was  made,  the  battery  samples  for  several 
weeks  had  4  per  cent,  zinc,  and  two  months  later  contained  great  quan- 
tities of  antimony. 

Table  I.  gives  general  mill  statistics,  representing  the  average  for 
five  years. 

TABLE  I. 


CRUSHING  AND   ROASTING. 


Year. 

Mesh  of  Screen 
on  Battery. 

Rate  of  Crush- 
ing per  Stamp 
per  Day. 

Per  Cent,  of  Salt 
used  in  Roast- 
ing 

Wood  used 
per  Ton  in 
Roasting. 

Mesh. 

Tons. 

Per  Cent. 

Cords. 

Nov.  1888,  to  Sept.  1892 

22 

2.8^ 

Ql/2.  to  7 

0.23 

The  rate   of  crushing   per  stamp  given  in  the  above  table  is  for 
twenty-four  hours,  but  the  battery  is  not  usually  run  at  night. 

TABLE  II. 


GENERAL   LIXIVIATION   STATISTICS. 


Year. 

Net  Weight 
of 
Vat  Charges 

Depth  of 
Charges 
before 
Leaching. 

Depth  of 
Charges 
after 
Leaching. 

Filtering 
Rate 
per  Hour. 

Strength 
of  Stock 
Solution  in 
Hypo. 

Strength  of 
Extra 
Solution  in 
Blue  Stone. 

Temper- 
ature of  all 
Solutions. 

Tons. 

Inches. 

Inches. 

Inches. 

Per  Cent. 

Per  Cent. 

0  Fah. 

1888 
1889 
1890 

16  to  18  y2 

16  to  18  K 
16  to  18  y2 

62 
62 
62 

53 
53 
53 

4.38 
3.34 
3.63 

1.89 

1.43 
1.40 

0.69 
0.69 
0.69 

»H    O 

o«o 
-d  o 

SI 

The  mill  solutions  at  Yedras  are  never  used  warm,  cold  solutions 
giving  equally  good  results. 

TABLE  III. 


LIXIVIATION   STATISTICS. 


DEPTHS  AND  VOLUMES  OF  WATER  AND  SOLUTIONS,  AND  TIME  OF  LEACHING. 


Year. 

ist  Wash  Water. 

ist  Ordinary  Solution. 

Extra  Solution  of  the  Russell  Process 

Time. 

Depth 

Volume 
per  Ton 

Time. 

Depth. 

Volume 
per  Ton 

Time. 

Depth. 

Volume 
per  Ton. 

Hrs. 

In. 

Cub.  ft. 

Hrs. 

In. 

Cu.  ft. 

Hrs. 

In. 

Cu.  ft. 

1888 
1889 

1890 

10.72 

12.52 
12.24 

43.24 
41.81 
40.25 

23.2 
22.5 
21.6 

25.63 

32.09 
43.50 

95.37 

93.45 
149.20 

51.3 

50.3 
86.0 

19.02 
20.77 

19.07 

24 

24 
24 

13 
13 
13 

The  twenty  hours  time  given  for  ' 'extra  solution"  includes  twelve 
hours  during  which  the  solution  stands  in  the  ore.  In  the  case  of  the 
wash  waters  and  ordinary  solutions  the  liquid  is  continually  running 
through  the  charge. 


TABLE  III.— CONTINUED. 


LIXIVIATION  STATISTICS. 


DEPTHS   AND   VOLUMES    OF     WASH    WATERS    AND    SOLUTIONS, 
AND    TIME   OF    LEACHING. 


Second  Ordinary  Solution 

2d  Wash  Water,     j  Total  Times  .Depths  &  Volumes. 

• 

c 

jj 

o 

H 

H 

o 

^H 

fin 

1 

o 

6 

S3 

PH 
6 

If 

ll 

^  o 

«d 

rt 

1 

V 

3 

"o 

6 

1 

15 

|j 

ll 

o  J2 

IH 

> 

H 

Q 

H 

Q 

H 

H 

Hw 

H 

Hours. 

Inches. 

Cu.  Ft. 

Hours. 

In.   [CuFt 

Hours. 

Inches. 

Cu.  Ft. 

Cu.Ft 

1888 

54.20 

212.27 

114.1 

7.34 

24 

13 

116.91 

331.6 

178.4 

36.2 

1889 

57.17 

176.41 

94.3 

10.38 

24 

13 

132.91 

293.9 

157.6 

35.5 

1890 

54.27 

193.40 

140.0 

8.72 

24 

13 

137.80 

366.6 

203.0 

34.6 

The  volume  of  water  per  ton,  referred  to  in  the  last  column  of 
the  above  table,  represents  the  total  quantity  used  per  ton  in  leach- 
ing. The  solutions  being  used  over  and  over  again  indefinitely,  no 
water  is  required  for  them  except  at  the  first  starting  of  a  mill,  when 
they  are  made  up  once  for  all.  If  the  rate  of  leaching  at  Yedras 
were  faster,  as  at  the  Aspen  mill  in  Colorado,  where,  I  understand,  the 
leaching  rate  is  about  14  inches  per  hour,  instead  of  three  as  at 
"Yedras,  the  time  occupied  in  treating  a  charge  would  be  much  re- 
duced. Just  so  much  solution  must  pass  through  the  ore  to  accom- 
plish the  work,  but,  with  the  exception  of  the  extra  solution  which  is 
allowed  to  stand  twelve  hours,  all  the  wash  waters  and  solutions  do 
just  as  good  work  running  rapidly  through  the  charge  as  slowly. 
For  a  four  times  as  rapid  rate  of  leaching  the  time  of  treatment 
£>f  a  charge  would  be  reduced  about  two-thirds. 

TABLE  IV. 


CHEMICALS   USED   PER   TON   OF   ORE. 


Year. 

Hyposulphite. 

Blue  Stone.  - 

Caustic  Soda. 

Sulphur. 

Total  Chemicals 
per  Ton. 

Ibs. 

Ibs. 

Ibs 

Ibs. 

Ibs. 

1888 
1889 
1890 
18.^1 
1892 

1.07 
0.82 
0.74 
1.31 

0.85 

7.02 

5.62 
3.85 
6.02 
6.16 

5.12 
3.13 
2.69 
4.23 
3.64 

3.97 
2.69 
1.86 
2.92 
2.50 

17.18 
12.26 
9.14 
14.48 
13.15 

Average          0.96 

5.73 

3.76 

2.79 

13.24 

Owing  to  distance  from  railroad  the  price  of  chemicals  per  pound 
at  Yedras  is,  of  course,  considerably  greater  than  at  any  place  in  the 
United  States  or  at  most  localities  in  Mexico. 

In  the  following  table,  and  throughout  this  article,  United  States 
money  is  used,  as  the  value  of  Mexican  silver  coin  varies  according 
to  the  price  of  silver. 

The  average  cost  of  chemicals  per  pound  at  Yedras  for  the  last 
three  years  is  as  follows  : 

Hyposulphite  of  soda 8.0  cents. 

Blue  stone 10.0  cents. 

Caustic  soda 9.1  cents. 

Sulphur 7.1  cents. 

No  soda  ash  (sodium  carbonate)  is  used  at  Yedras,  as  there  is 
usually  no  lead  in  the  ore. 

The  total  cost  of  all  chemicals  at  Yedras  in  1890  was  3.6  cents 
per  ounce  of  silver  produced.  Of  the  copper  used  in  the  form  of  blue 
stone,  about  50  per  cent,  remains  in  the  ore. 

TABLE  V. 


COST   OF    CHEMICALS   PER   TQN   OF   ORE. 


Year. 

Hyposulphite. 

Blue  Stone. 

Caustic  Soda. 

Sulphur. 

Total  Cost  of 
Chemicals  per 
Ton  of  Ore. 

Cents. 

Cents. 

Cents. 

Cents. 

Dollars. 

1888 
1889 

1890 
1891 
1892 

8.7 

6.6 
6.0 
11.1 
7.6 

70.2 

56.0 
38.5 
63.2 
70.8 

46.5 

28.5 
24.5 
402 
383 

28.2 

19.1 
13.2 
21.9 
21.2 

1.54 
1.10 

0.85 
1.36 
1.38 

Average 

8.0 

59.7 

35.6 

20.7 

1.25 

In  the  following  table  are  given  the  assay  office  results  by  both  the 
old  leaching  process  and  the  Russell  Process,  and  the  mill  results  ob- 
tained by  the  latter  during  the  past  year.  The  assay  office  results  are, 
of  course,  the  standard  up  to  which  each  of  these  processes  is  expected 
to  work  in  the  mill.  As  shown  in  the  tables  the  Russell  Process  in  the 
mill  is  a  little  above  its  standard.  On  each  charge  of  ore  the  old 
process  is  used  first,  extracting  what  it  can,  and  then  the  Russell 
Process  follows  it.  But,  except  when  a  comparative  mill  run  between 
the  two  processes  is  made,  the  results  of  which  are  given  further  on, 
the  tailings  are  not  sampled  after  the  old  process  and  before  the 
Russell  Process,  but  only  when  each  charge  is  entirely  finished. 
Consequently  the  mill  results  by  the  old  leaching  process  are  not 
given  in  this  table. 


TABLE  VI. 


ASSAY   OFFICE   AND   MILL   RESULTS   FOR 


Month. 

Extraction  by 
Old  Process 
in  Assay  Office. 

Extraction  by 
Russell  Process 
in  Assay  Office. 

Extraction  by 
Russell  Process 
in  Mill. 

Russell  Process  in  Mill 
compared  with  same 
Process  inAssay  Office. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent 

January  .... 
February  .  .  . 
March 

71.28 
77.73 
78.26 

84.75 
85.77 
85.96 

80.45 
84.25 
8633 

-4.30 
-1.52 

+  037 

April   

78.72 

87.01 

87.94 

+  0.93 

May  

75.62 

86.98 

88.53 

+  1.55 

Tune    

69.52 

87.30 

8861 

+  1.31 

July.. 

70.29 

85.61 

86.26 

+  0.65 

Au£TUSt 

69.51 

86.88 

89.65 

+  2.77 

September  . 
October  
November  .  . 
December  .  . 

69.43 
61.87 
61.44 
62.42 

87.55 
86.32 
87.24 
84.68 

90.55 
89.88 
87.61 
91.24 

+  3.00 
+  3.56 
+  0.37 
+  6.56 

Average  .  . 

70.50 

86.30 

87.57 

+  1.27 

In  Table  VI  the  —  and  +  signs  indicate  by  how  much  the  Russell 
Process  in  the  mill  fell  below  or  exceeded  its  standard,  i.  e.  the  re- 
sults by  that  process  in  the  assay  office.  So  far,  this  year,  the  results  of 
the  process  in  the  mill  exceed  the  assay  office  results  by  1.27  per 
cent. 

The  mill  extraction  at  Yedras,  as  given  in  Table  VI,  is  not 
as  high  as  at  most  other  mills  using  the  process.  This  is  due 
to  the  fact  that  the  roasting  in  the  reverberatories,  owing  to  the  large 
loss  of  silver,  which  may  then  take  place,  if  it  is  too  long  continued, 
or  at  too  high  a  temperature,  must  be  conducted  with  reference  to 
this  loss  as  well  as  to  the  subsequent  extraction  by  lixiviation.  The 
roasting  might  be  so  conducted  as  to  yield  92  or  93  per  cent,  of  the 
value  of  the  roasted  ore  by  lixiviation,  but  such  a  roasting  would  cause 
a  greater  loss  of  silver  by  volatilization.  Also,  if  more  salt  were  used 
the  per  cent,  of  extraction  from  the  roasted  ore  would  be  higher.  But 
salt  costs  at  Yedras  about  twelve  times  as  much  as  at  Park  City,  Utah. 
With  seven  per  cent,  salt  and  the  roasting  as  at  present  conducted, 
the  loss  by  volatilization  is  6  to  8  per  cent.,  and  the  extraction  from 
the  roasted  ore  87  per  cent.  This  is  better  economically  than  to  use 
a  larger  per  cent,  of  salt  or  roast  longer,  even  with  92  per  cent,  ex- 
traction from  the  roasted  ore  as  a  result. 


NOTE.— The  statistics  for  1892  are  furnished  by  H.  H.  Hughes,  Superintendent  of  the  Anglo- 
Mexican  Mining  Company  at  Yedras. 


TABLE  VII. 


DIFFERENCE   BETWEEN   ASSAY   OFFICE  AND   MILL   RESULTS 
FOR   FIVE   YEARS. 


Year. 

Russell  Process  in  Mill 
over  Old  Process  in 
Assay  Office. 

Russell  Process  in  Mill 
over  Old  Process  in  Mill. 
(See  Table  A.) 

Russell  Process  in  Mill 
over  (  +  )  or  below  (  —  ) 
Russell  Process  in  Assay 
Office. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

1888 
1889 
1890 
1891 
1892 

11.13 

8.47 
9.17 
11.62 
17.07 

O5       £- 

•*  _{.C5 

^'      T*5 

i—  i 

+  0.02 
-0.29 

+  0.54 
-4.75 
+  1.27 

Av6rasf6  

11  49 

16  46 

-0  64 

As  shown  in  above  Table  VII,  the  Russell  Process  during  the  past 
five  years  has  extracted  in  the  mill  16.46  per  cent,  of  the  value  of  the 
ore  more  than  could  be  extracted  by  the  Old  Process  in  the  mill. 
Also,  the  extraction  by  the  Russell  Process  in  the  mill  averaged  only 
64-100  of  one  per  cent,  less  than  the  highest  extraction  obtainable 
by  that  Process  in  the  assay  office. 


TABLE  VIII. 


VALUES   OF    PRODUCTS   AND   DISTRIBUTION   OF   VALUES   IN   PRODUCTS. 


Year. 

1890 

Per  Cent.  Silver  in  each  Product. 

Distribution  of  Silver  in  the  Products. 

Wash  Water 
and  Weak 
Solution 
Sulphides. 

Sulphides 
from 
"Ordinary 
Solution." 

Sulphides 
from 
"Extra 
Solution." 

Average 
Value  of 
Total 
Product. 

Per  Cent,  of 
Total  Pro- 
duct in  Wash 
Water  and 
Weak  Solu- 
tion Sul- 
phides . 

Per  Cent,  of 
Total  Pro- 
duct in  Sul- 
phides from 
Ordinary 
Solutions. 

Per  Cent,  ot 
Total  Pro- 
duct in  Sul- 
phides from 
Extra 
Solution. 

Per  Cent. 
Silver. 

Per  Cent. 
Silver. 

Per  Cent. 
Silver. 

Per  Cent. 
Silver. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

46.47 

69.10 

24.79 

60.2 

10.0 

75.0 

15.0 

TREATMENT  OF  OLD  TAILINGS 

BY   THE    RUSSELL    PROCESS. 


All  the  tailings  which  had  been  produced  at  the  Yedras  mill  by 
the  old  leaching  process,  before  the  introduction  of  the  Russell  Pro- 
cess in  1887,  have  now  been  re-treated  by  the  latter.  The  manipula- 
tions of  the  solutions  for  tailings  is  practically  the  same  as  in  the  treat- 
ment of  ore. 

The  tailings  are  brought  from  the  old  dumps,  where  they  had 
been  thrown  out  in  former  years,  and  are  charged  directly  to  the 
leaching  vats  without  any  drying,  roasting  or  other  preliminary  treat- 
ment. Like  the  charges  of  ore,  they  are  leached  first  with  water  in 
order  to  remove  the  small  per  cent,  of  soluble  salts  which  is  present, 
this  washing  requiring  about  four  hours.  A  small  amount  of  ordi- 
nary hypo-sulphite  solution  is  then  applied,  not  because  this  solution 
extracts  anything,  as  it  extracts  absolutely  nothing.  But,  as  the  vol- 
ume of  the  "extra  solution"  is  only  enough  to  saturate  the  charge,  and 
it  would  become  diluted  to  some  extent  with  the  wash  water  if  it  fol- 
lowed that,  the  small  volume  of  ordinary  solution  is  interposed  be- 
tween them. 

As  in  treating  ore,  the  "extra  solution"  amounts  to  13  cubic  feet 
per  ton.  It  is  followed  by  more  of  the  ordinary  hyposulphite  solu- 
tion to  extract  any  silver  which  has  been  made  soluble  by  the  "extra 
solution"  but  which  has  not  passed  out  of  the  charge  with  that  solu- 
tion, but  remains  mechanically  held  in  the  pulp. 

The  total  amount  of  tailings  from  the  old  leaching  process  at 
Yedras  which  have  been  re-treated  by  the  Russell  Process  is  about 
30,000  tons. 

Table  IX  gives  the  assay  office  and  mill  results  on  the  tailings 
re-treated  in  1889. 

TABLE  IX. 

TREATMENT   OF   OLD   TAILINGS   BY   RUSSELL   PROCESS— l88o. 


MONTH. 

Value 
Per 
Ton. 

Per  Cent,  by 
Old  Process  in 
Assay  Office. 

Per  Cent,  by 
Russell  Process 
in  Assay  Office. 

Per  Cent, 
by  Old 
Process 
in  Mill. 

Actual  "Clean 
Up"  by  Russell 
Process  in  Mill. 

Ounces. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

January  
February... 
March  
April 

18.49 
18.40 
17.45 
1639 

33.60 
35.49 
28.60 
3063 

62.30 
59.30 
56.39 

5827 

b« 

8J 

aid 

70.46 

63.43 
56.13 
6693 

May  . 

17,92 

36.72 

61.22 

Vs 

7407 

June..  . 

16.14 

31.11 

5663 

1-1* 

5350 

July  

16.00 

33.75 

5675 

o~.S 

55.90 

August  
September.. 

14.68 
18.26 

31.00 
37.03 

56.68 
58.60 

£  2 

H^ 
<u 

64.87 
52.51 

Averages  .  . 

17.23 

32.17 

57.20 

0.0 

60.14 

9 


No  tailings  were  treated  in  October,  November  or  December  of 
1889,  nor  in  June,  July,  August,  September  or  December,  1890. 
Table  X  gives  the  results  on  tailings  for  1890. 

TABLE  X. 

TREATMENT   OF   OLD   TAILINGS   BY   THE   RUSSELL   PROCESS — 1890. 


MONTH. 

Value 
Per 
Ton. 

Per  Cent,  by  Old 
Process  in 
Assay  Office. 

Per  Cent,  by 
Russell  Process 
in  Assay  Office. 

Per  Cent  . 
by  Old 
Process 
in  Mill. 

Actual  "Clean 
Up"  by  Russell 
Process  in  Mill. 

Ounces. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

January.  .  .  • 
February.  .  . 
March    .... 

13.02 
15.24 
1548 

24.35 
36.62 
36.12 

39.56 
50.20 
53.88 

JLti 

2£a 

O.U-- 
?  fcuo   • 

34.09 
47.95 
55.00 

Apri]  

13  03 

32.00 

5380 

2  ~  S3 

45.28 

May  

10.93 

30.38 

45.29 

0$-B  g 

59.73 

October  
November.. 

10.41 
11.50 

26.50 
31.83 

35.50 
43.57 

D   (/>   O 

£%  G 

H  o 

34.28 
43.91 

Averages  .  . 

13.46 

34.48 

49.26 

0.0 

46.84 

In  both  the  foregoing  tables  it  will  be  noticed  that  the  old  leach- 
ing process  in  the  mill  fails  to  extract  anything  from  the  tailings  which, 
had  been  previously  produced  by  it,  although  in  the  assay  office  the 
extraction  from  these  tailings  by  that  process  is  32.0  to  34.0  per 
cent. 

Tables  XI  and  XII  give  the  chemicals  consumed  in  leaching  for 
the  months  corresponding  to  those  of .  Tables  IX  and  X. 

TABLE  XI. 

TREATMENT   OF   OLD   TAILINGS   BY   THE  RUSSELL  PROCESS. 
CHEMICALS  USED   PER   TON — 1889. 


Month. 

Hyposulphite. 

Blue  Stone. 

Caustic  Soda. 

Sulphur. 

Total 
Chemicals  . 
Per  Ton. 

Ibs. 

Ibs. 

Ibs. 

Ibs. 

Ibs. 

January  
February  

1.07 
1.33 

5.70 
571 

4.82 

4.00 

3.21 
2.66 

14.80 

13.70 

March  

1.50 

582 

*14.21 

*7.10 

*28.63 

April  

246 

600 

431 

2.86 

15.63 

May             

286 

610 

389 

2.59 

15.44 

June            

1.65 

531 

321 

2.14 

12.31 

July 

1.94 

512 

2.68 

1.78 

11.52 

J     j  
August  

1.13 

503 

2.84 

1.89 

10.89 

September 

131 

462 

350 

2.33 

11.76 

Averages  .  . 

1.62 

5.11 

3.13 

2.69 

12.55 

*  Caustic  lime,  as  during  March  "calcium  sulphide"  was  used  as  a  precipitant  for  silver 
sulphide.  As  a  result  the  cost  of  precipitating  was  increased  about  25  per  cent,  instead  of  sodium, 
for  that  month . 


10 
TABLE  XII. 


TREATMENT  OF   OLD   TAILINGS   BY  THE  RUSSELL  PROCESS. 
CHEMICALS   USED   PER   TON — l8gO. 


MONTH  . 

Sulphite. 

Bluestone. 

Caustic 
Soda. 

Sulphur. 

Total 
Chemicals 
Per  Ton. 

Ibs. 

Ibs. 

Ibs. 

Ibs. 

Ibs. 

January    

0.85 

3.80 

2.21 

1.47 

833 

February  .    . 

1.08 

3.84 

2.45 

1.69 

9.06 

March          

2  85 

427 

1.74 

1.20 

1006 

April       

1  89 

426 

2.48 

1.72 

1035 

May  

0.77 

3.69 

2.54 

1.76 

8.76 

October 

002 

417 

2.29 

1.57 

8.05 

November  

004 

4.43 

3.67 

2.53 

10.67 

Averages  

107 

406 

248 

1.71 

9.33 

Tables  XIII  and  XIV  give  a  summary  of  statistics  on  the  treat- 
ment of  the  old  tailings  at  Yedras  for  three  years.  Naturally 
the  richest  of  these  old  tailings  were  treated  first,  which  accounts 
for  their  decreasing  value. 


TABLE  XIII. 


TREATMENT  OF  OLD   TAILINGS    BY   THE    RUSSELL   PROCESS   AT   YEDRAS. 


SUMMARY. 


Year. 

Value 
per  Ton. 

Per  Cent,  by 
Old  Process 
in  Assay 
Office. 

Per  Cent, 
by  Russell 
Process  in 
\ssay  Office 

Per  Cent, 
by  Old 
Process 
in  Mill. 

Apparent 
per  Cent,  by 
Russell 
Process  in 
Mill. 

Apparent  by 
Russell  Pro- 
cess in  Mill 
below  that 
Process  in 
AssayOffice. 

Actual 
Extraction 
by  Russell 
Process 
in   Mill. 

Ozs. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

1888 

1889 
1890 

19.49 
17.23 
13.46 

37.40 
32.17 

38.48 

62.70 

57.20 
49.26 

Old  Process 
extracts 
nothing  in 
Mill. 

60.14 
55.95 

48.37 

-2.55 

—1.25 

—0.89 

62.74 
60.14 
46.84 

Av'ges 

16.73 

36.02 

56.39 

00.00 

54.82 

—1.57 

56.57 

In  the  above  table  ' 'apparent"  extraction  in  mill  is  obtained  by 
-comparing  the  value  per  ton  of  the  final  tailings  with  the  old  tailings  as 


11 


charged  to  the  leaching  vats  (taking  into  account  any  soluble  salts 
also). 

"Actual  extraction"  in  mill  isobtained  by  comparing  the  "clean 
up"  in  silver  with  the  silver  actually  charged  to  leaching  vats. 

The  "actual  "  extraction  averages  ify  Per  cent-  above  the  "ap- 
parent "  for  the  three  years. 


TABLE  XIV. 


TREATMENT   OF    OLD   TAILINGS   BY   THE   RUSSELL  PROCESS   AT   YEDRAS. 


SUMMARY — CONTINUED. 


CHEMICALS   USED   PER   TON,    ETC. 


Year. 

Hypo- 
sulphite. 

Blue  Stone. 

Caustic 
Soda. 

Sulphur. 

Total 
Chemicals 
per  Ton. 

Cost  of 
Chemicals 
per  Ton. 

Ounces 
Silver 
Extracted 
per  Ton. 

Ibs. 

Ibs. 

Ibs. 

Ibs. 

Ibs. 

Dollars. 

Ozs. 

1888 
1889 
1890 

2.08   . 
1.62 
1.07 

6.32 
5.11 
4.06 

4.54 
3.13 
2.48 

3.30 
2.69 
1.71 

16.24 
12.55 
9.33 

1.45 
1.12 
0.84 

12.23 
9.75 
6.30 

Ar'ges 

1.59 

5.10 

3.38 

2.57 

12.64 

1.13 

9.43 

The  value  of  the  product  from  the  treatment  of  old  tailings  at 
Yedras,  by  the  Russell  Process,  averages  about  25  per  cent,  in  silver, 
or  approximately  7,000  ounces  per  ton. 


12 


SUMMARY. 

Tables  IV  and  XIV  give  the  chemicals  on  both  ore  and  tailings 
for  the  years  1888,  1889  and  1890,  as  follows: 


YEAR. 

Total  Chemicals  Per  Ton 
for  Ore. 

Total  Chemicals  Per  Ton 
.             for  Tailings. 

Ibs. 

Ibs. 

1888 
1889 
1890 

17.18 
12.26 
9.14 

16.24 
12.55 
9.33 

The  above  Table  illustrates  a  fact,  which,  I  believe,  has  been 
observed  wherever  the  Russell  Process,  has  been  used,  viz.:  .  That  the 
amount  of  chemicals  consumed  per  ton  is  practically  independent  of 
the  richness  of  the  ore.  For,  in  the  above  case,  the  amount  of  silver 
extracted  from  the  ore  per  ton  is  four  to  six  times  the  amount  extract- 
ed from  the  tailings  and  yet  the  weight  of  chemicals  used  per  ton  is 
almost  exactly  the  same. 

The  average  amount  and  cost  of  chemicals  per  ton  used  in  re- 
treating the  old  tailings  at  Yedras  by  the  Russell  Process,  during  the 
above  three  years,  has  been  as  follows: 


Hyposulphite 1.59  Ibs.  at     8.0  cents 12.72  cents. 

Blue  Stone 5.10     "     "    10.0    "     51.00  cents. 

Caustic  Soda 3.38    "     "      9.1    "     30.76  cents, 

Sulphur 2.57    "     "      7.1     " 18.24  cents. 

12.64  $1.1272!100 


In  the  United  States,  for  instance,  at  Park  City,  Aspen  or  Butte, 
the  cost  of  these  chemicals  would  be  about  65  cents,  instead  of  $i.  13, 
per  ton  of  tailings. 

The  average  actual  extraction  in  silver  from  these  old  tailings 
during  these  three  years  has  been  56.57  per  cent.,  or  9.46  ozs.  per  ton. 
The  average  price  of  silver  in  the  United  States  for  this  period  was 
97  cents  per  oz.,  making  the  gross  extraction  of  silver  from  the  tailings 
equal  to  $9.18  per  ton. 

The  following  table  gives  the  average  expenses  and  profits  at 
Yedras  arising  from  the  treatment  of  these  tailings  by  the  Russell 


13 

Process  at  the  rate  of  50  tons  per  day  (the  usual  rate  being  30  to  50 
tons)  : 

Chemicals per  ton $1.13 

Loading per  ton 0.25 

Unloading per  ton 0.13 

Labor  in  leaching per  ton 0.29 

Fuel  and  power  per  ton 0.13 

Product  and  sundry  expense  per  ton 0.50 

Total  expenses  per  ton $2.43 

RECAPITULATION. 

Extraction  per  ton  (9.43  ozs.  at  97  cts.) $9.18 

Expenses  per  ton 2.43 

Net  profit  per  ton $6.75 

The  statistics  which  have  just  been  given  refer  to  the  treatment  ot 
Yedras  tailings  only.  We  now  come  to  a  comparison  of  the  Russell 
Process  and  the  old  leaching  process  in  the  treatment  of  Yedras  ore. 

During  the  past  five  years  the  comparative  efficiency  of  these  two 
processes  at  the  Yedras  mill  has  been  tested  four  times.  The  dura- 
tion of  each  of  these  tests  was  from  one  to  three  months. 

Two  of  these  were  made  by  my  predecessor  in  charge  of  the 
mill,  Mr.  F.  M.  Johnson,  and  two  by  myself. 

Two  methods  were  pursued  in  making  these  comparative  runs. 
One  was  to  divide  the  roasted  ore  equally  between  the  two  processes, 
running  one-half  the  ore  vats  and  precipitating  tanks  on  the  old  pro- 
cess and  the  other  half  by  the  Russell  Process,  the  products  being 
kept  entirely  separate  and  the  tailings  from  each  process  being  thrown 
out.  By  this  method,  however,  there  is  a  loss  of  seven  to  ten  ounces 
per  ton  on  all  the  ore  treated  by  the  old  leaching  process;  as  that 
amount,  which  might  be  extracted  by  the  Russell  Process,  if  it  were 
used  on  those  charges  after  the  old  process,  remains  in  the  tailings 
and  is  lost. 

In  the  other  method  of  making  the  comparison  between  the 
two  processes,  all  the  charges  are  treated  first  by  the  old  process,  that 
is  by  the  simple  hypo-sulphite  solution,  until  no  more  silver  can  be 
extracted  by  that  process,  the  sulphides  being  precipitated  by  them- 
selves and  kept  separate.  Then  these  same  charges  of  ore  are  treated 
by  the  Russell  Process,  that  is  by  a  cuprous  hypo-sulphite,  or  "extra" 
solution.  The  precipitates  from  this  solution  are  likewise  kept  sep- 
arate. In  this  way  a  comparison  between  the  two  processes  is  made 
without  any  loss,  each  charge  of  ore  having  the  benefit  of  being 
treated  by  both  processes  before  it  is  thrown  out. 


In  fact  this  is  the  way  all  the  ore  is  treated  at  Yedras,  whether  a 
comparison  is  being  made  or  not,  all  charges  being  first  treated  by 
the  old  process  and  then  by  the  Russell  Process. 

The  first  of  the  two  comparative  runs  made  by  myself  between 
the  two  processes  was  in  September,  1890,  the  test  being  continued 
during  the  whole  of  the  month. 

I  extract  from  my  report  to  the  Anglo-Mexican  Company,  made 
at  the  time  on  this  test  run : 

"  Our  intention  was  to  give  the  old  process  every  possible  show. 
Great  care  was  taken  to  keep  the  precipitates  separate,  both  at  the  be- 
ginning and  end  of  the  month.  The  tons  of  ore  in  question  were  to- 
tally leached  out.  During  the  month  no  experiments,  or  extra  <  clean 
up,'  was  carrried  out.  In  making  the  test  we  allowed  the  old  process 
to  take  out  all  it  could  take,  /.  e. ,  we  ran  the  vats  (by  the  old  process) 
as  long  as  sodium  sulphide  would  show  the  least  trace  of  silver  in  the 
solution.  When  the  old  process  would  not  take  any  more  silver  out, 
the  'extra  solution'  of  the  Russell  Process  was  applied,  and,  as  in  the 
case  of  the  old  process,  was  run  as  long  as  sodium  sulphide  showed 
any  trace  of  silver  coming  out." 

The  actual  "clean  ups"  from  the  two  processes  were  as  follows: 

Extracted  by  the  old  leaching  process 26,361.42  ozs. 

Additional  extracted  by  the  Russell  Process,  5,088.76  ozs. 
Total, .31,450.18  ozs. 

Per  cent,  of  total  product  extracted  by  old  process 83.8 

Per  cent,  of  total  product  extracted  by  Russell  process, 16.2 

That  is,  after  the  old  process  had  done  its  utmost  work,  extract- 
ing 26,361.42  ozs.,  the  Russell  Process  was  used  on  the  same  charges 
of  ore  and  extracted  5,088.76  ounces  more. 

The  total  chemicals  used  per  ton  for  both  processes  was: 

Hyposulphite  of  Soda 0.0    Ibs.  at    8.1  cents 0.00 

Blue  Stone 3.0    Ibs.  at  10.0  cents ....  33.00 

Caustic  Soda 3.58  Ibs.  at     9.1  cents ....  28.60 

Sulphur 2.48  Ibs.  at     9.3  cents ....  17.40 

Total 9.06  $0.79.00 

The  total  additional  cost  of  the  Russell  Process,  or  in  other 
words,  the  extra  expense  of  producing  this  5,088.76  ozs.  over  the 
cost  of  the  old  process  was  as  follows: 

Chemicals $632.50 

Fuel 21.21 

Extra  help,  etc 155.60 


Total $809.31 


15 


At  the  then  price  of  silver  the  5,088.76  ozs.  equalled  $5,852.07-.. 
Deducting  the  above  expenses  there  is  left  $5,042.76  as  the  net  profit 
per  month  due  to  the  use  of  the  Russell  Process. 

The  second  test  made  by  myself  on  the  comparative  efficiency  of 
the  two  processes  was  carried  out  during  the  month  of  November, 
1890. 

In  this  run  the  total  chemicals  used  per  ton  for  both  processes 
were: 

Hypo-sulphite 0.35  Ibs. 

Blue  Stone 6.40  Ibs. 

Caustic  Soda 2.84  Ibs. 

Sulphur 1.70  Ibs. 

Total 11.29  Ibs. 

The  total  cost  of  these  chemicals  per  ton  was  95  cents. 

Of  the  total  ounces  extracted  the  old  process  took  out  80.29  per- 
cent, and  the  Russell  Process  the  remaining  19.71  per  cent.  The  ad- 
ditional ounces  silver  extracted  by  the  Russell  Process  over  the  old 
process  were  7,653.7,  or  (with  silver  at  $1.02.5  per  oz.),  $7,845.04, 
making  a  net  profit  due  to  the  use  of  the  Russell  Process  of  about 
$7^000  per  month. 

Of  the  two  comparative  runs  made  by  my  predecessor  in  charge 
of  the  mill,  Mr.  F.  M.  Johnson,  the  first  was  made  during  the  first 
three  months  of  the  use  of  the  Russell  Process.  The  following  taftle- 
from  June  to  December,  1887,  shows  the  mill  extraction  by  the  old'- 
leaching  process  for  seven  months  and  the  results  by  the  Russell  Pro- 
cess for  two  months. 

TABLE  XV. 


MILL   RESULTS   FOR   SEVEN   MONTHS,    1887. 


Month. 

Extraction  in  Mill  by 
Old  Process. 

Extraction  in  Mill  by 
Russell  Process. 

Per  Cent. 

Per  Cent. 

June  

711 

July 

660 

»    J 
August         

660 

Process  not  in  use 

September  

731 

until  November. 

October  

631 

November  

637 

81  2 

December          

673 

822 

The  following  is  from  the  printed  report  of  Mr.  F.  M.  Johnson 
on  the  above  mentioned  comparative  run  between  the  two  processes. 
The  data  on  the  "old  process"  dates  from  June  i,  1887,  up  to  and. 


16 


including  January   31,    1888.      The   data   on  the  "Russell  Process" 
dates  from  November  i  (when  it  was  introduced),  1887,  up  to  January 

31,  1888. 

TABLE  A. 

OLD   LEACHING   PROCESS. — ASSAY   OFFICE   AND   MILL   RESULTS. 


Number 
of  Months 
Run. 

Value 
per  Ton. 

Extraction 
in  the 
Assay  Office. 

Extraction 
in  Mill. 

Extraction  in 
Mill  below 
Assay  Office. 

Total 
Leaching  Time. 

No. 

O/s. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Hours. 

8 

60.67 

72.09 

67.12 

-4.97 

92 

TABLE  B. 


RUSSELL   PROCESS. — ASSAY   OFFICE   AND   MILL    RESULTS. 


Number  of 
Months  Run. 

Value 
per  Ton. 

Extracted 
by  Old  Pro- 
cess in  Assay 
Office. 

Extracted 
by  Russell 
Process  in 
Assay 
Office. 

Extracted 
by  Russell 
Process  in 
Mill. 

Difference  be- 
tween Old  Pro- 
cess in  Assay 
Office  and  Rus- 
sell Process  in 
Mill. 

Difference 
between  Russell 
Process  in 
Assay  Office 
and  Mill. 

Total 
Leach- 
ing 
Time. 

Ozs. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Per  Cent. 

Hours. 

3 

55.3 

69.94 

83.62 

82.44 

12.5 

-    1.18 

76 

TABLE  C. 

OLD  LEACHING  PROCESS — CHEMICALS  PER  TON. 


Lime. 

Sulphur. 

Total  Chemicals 
Per  Ton. 

Total  Cost 
Per  Ton. 

Ibs. 

Ibs. 

Ibs. 

Dollars 

9.7 

4.7 

14.4 

0.52 

TABLE  D. 


RUSSELL   PROCESS— CHEMICALS   PER   TON. 


Hypo-Sulphite. 

Eluestone. 

Caustic  Soda. 

Sulphur. 

Total  Chemi- 
cals Per  Ton. 

Total  Cost 
Per  Ton. 

Ibs. 

Ibs. 

Ibs. 

Ihs. 

Ibs. 

$ 

1.4 

9,6 

5.5 

3.6 

20.1 

2.20 

NOTE  i. — By  referring  to  the  above  tables  (A  and  B)  it  will  be  seen  that  the  old  process  in 
the  assay  office  extracts  4.97  more  than  the  old  process  in  mill,  and  12.05  per  cent,  less  than  the 
Russell  Process  in  the  mill,  which  shows  a  net  gain  in  extraction  in  favor  of  the  Russell  Process  of 
17.47  per  cent. 

NOTE  -2.. — That  the  time  for  treatment  is  shortened  by  the  Russell  Process. 

NOTE  3.— That  the  cost  for  chemicals  in  the  Russell  Process  is  $1.68  more  than  in  the  old 
process.  (C  and  D) 

NOTE  4. — The  net  gain  in  extract-ion  of  17.47  percent.  (A  and  B)  on  60  ounce  ore  would  be  10.48 
ounces,  or  $10.06  per  ton  (with  silver  at  96  cents  per  oz.)  From  this  take  $  i  .68  (the  extra  cost  for 
chemicals  in  the  Russell  Process)  and  there  will  be  left  a  profit  of  $8.38  per  ton.  If  12,000  tons  be 
treated  in  a  year  the  net  gain  in  profits  by  using  the  Russell  Process  would  be  $100,560.00  per  year. 


17 


The  above  is  the  report  of  Mr.  Johnson,  dated  Feb.  7,  1888. 
Being  the  first  three  months  run  the  amount  of  chemicals  is  much 
greater  than  afterward,  and  also  the  cost  per  ton,  as  shown  by  the 
following  table: 

AMOUNT   AND   COST   OF   CHEMICALS    FOR   DIFFERENT   PERIODS 
BY    RUSSELL   PROCESS. 


Weight  of  Chemicals 

Cost  of  Chemicals 

Period 

per  Ton  of  Ore. 

per  Ton  of  Ore. 

Ibs. 

Dollars. 

First  3  months  run  as  per 
above  report. 

20.10 

2.20 

1888 

17.18 

1.54 

1889 

12.26 

1.10 

1890 

9.14 

0.85 

1891 

14.48 

1.36 

1892 

13.15 

1.38 

The  following  is  the  report  of  Mr.  Johnson  on  the  second  com- 
parative run  made  by  him  in  August,  1889,  the  report  being  dated 
September  7,  1889: 

"THE  EFFICIENCY  OF  THE  'EXTRA  SOLUTION'  IN  RUSSELL'S  IMPROVED 
PROCESS  OF  LIXIVIATION  AT  THE  YEDRAS  MILL. — REMARKS. 

"To  determine  the  actual  efficiency  of  the  extra  solution  of  the 
Russell  Process,  on  Yedras  ores,  we  precipitated  the  silver-bearing 
solution  of  simple  hypo-sulphite  of  soda  coming  from  the  ore  in  a 
separate  set  of  vats.,  The  silver  extracted  by  the  extra  solution  of 
the  Russell  Process  was  also  precipitated  in  vats  by  itself.  We  aimed 
to  leach  all  the  silver  out  of  the  ore  that  the  simple  hypo-sulphite 
of  soda  solution  was  capable  of  extracting,  and  then  the  extra  solu- 
tion was  added  to  the  same  ore  to  further  the  extraction. 

TABLE  NO.  1. 


Ozs.   Extracted  as 
Sulphides  Without 
Use  ot  Russell 
Process. 

Ounces  Extracted 
as  Sulphides  by  the 
Russell  Process. 

Amount  extracted  during"  base  metal 
leaching  (z.  e.,  first  wash  water).  .  .  . 
Amount   extracted  by   simple   hypo- 
sulphite solution                                 .  . 

3,576.26 
23  678  66 

Amount  extracted  by  extra  solution 
after  the  simple  hyposulphite  had 
done  its  utmost  work  

10  115  20 

Totals  .  .  '.  

27,254.92 

10,115.20 

Amount  extracted  by  both  methods  in  sulphides 37,370.12  ounces. 

Per  cent,  of  total  extraction  by  simple  hypo-sulphite 

solution  and  wash  water  (old  process) 72.93  per  cent. 

Additional  extraction  by  extra  solution  (Russell  Process)      27.07  per  cent. 


18 

-     TABLE  INO.[2. 

COST  OF   ADDITIONAL   CHEMICALS    USED   IN   RUSSELL   PROCESS. 

Hyposulphite  of  Soda 1687  Ibs.  @  7.7       $  129.90 

Blue  Stone 8650  Ibs.  @  8.5  =      735.25 

Caustic  Soda 2292  Ibs.  @  6.2  =      142.10 

Sulphur 1528  Ibs..  @  5.4  -         82.51 

Total  cost  of  Chemicals  for  Russell  Process $1,089.76 

REMARKS  ON  TABLES  I  AND  2. 

"The  value  of  the  silver  which  was  further  extracted  by  the  Rus- 
sell Process  is  $9,407.14.  Subtracting  the  cost  of  the  chemicals, 
$1,089.76,  from  this  leaves  $8,317.38,  which  is  the  net  profit  due  to 
the  use  of  the  "  extra  solution"  of  the  Russell  Process  over  and  above 
the  simple  hypo-sulphite  solution  (or  old  process)  expressed  in  dollars, 
for  the  month  of  August. 

"The  extraction  by  the  hypo-sulphite  solution  (old  process)  is 
probably  a  little  greater  than  it  would  have  been  if  the  stock  solution 
(of  that  process)  had  not  been  kept  in  thorough  condition  due  to  the 
use  of  the  bluestone  (of  the  Russell  Process)  which  was  used  in  the 
extra  solution." 

The  net  savings  at  Yedras  due  to  the  use  of  the  Russell  Process 
over  the  old  leaching  process  may  be  summed  up  as  follows.  (All  the 
old  tailings  have  already  been  treated. ) 

Net  Saving 
per  Year. 

On  tailings  at  rate  of  1,500  tons  per  month $121,500.00 

On  ore  as  per  1st  comparative  mill  run 100,560.00 

On  ore  as  per  2d  comparative  mill  run 99,808.56 

On  ore  as  per  3d  comparative  mill  run 60,513.12 

On  ore  as  per  4th  comparative  mill  run 84,000.00 

The  amount  of  ore  treated  at  Yedras  varies  from  1000  to  1200 
tons  per  month. 

Omitting  the  profits  arising  from  the  treatment  of  the  old  tail- 
ings, the  net  profits  per  year,  due  to  the  use  of  the  Russell  Process, 
over  the  old  leaching  process  on  ore,  at  Yedras,  have  averaged 
$86,000.00  per  year,  or  $6.00  to  $7.00  per  ton.  The  difference  in 
extraction  of  silver  in  the  mill  for  the  five  years  has  averaged  16.5 
per  cent,  of  the  value  of  the  ore  in  tavor  of  the  Russell  Process  and  in 
the  treatment  of  old  tailings  56.6  per  cent,  of  their  value,  over  the  ex- 
traction by  the  old  leaching  process. 


PUBLISHED   BY 

RUSSELL  PROCESS  Co., 

PARK  CITY,  UTAH, 
U.  S.  A.