Skip to main content

Full text of "Shop systems"

See other formats


TJ 

7 


UC-NRLF 


B    3    Dlfl 


CENTS 


SHOP  SYSTEMS 

FOUR  TVPICAI    SHOP  SYSTEMS  USED 

IN  REPRESENTATIVE  MACHINE 

BUILDING  PLANTS 


MACHINERY'S  REFERENCE  BOOK  NO.  139 
PUBLISHED  BY  MACHINERY,  NEW  YORK 


MACHINERY'S  REFERENCE  SERIES 

EACH    NUMBER    IS     ONE     UNIT    IN     A     COMPLETE     LIBRARY     OF 

MACHINE  DESIGN    AND    SHOP    PRACTICE    REVISED   AND 

REPUBLISHED    FROM    MACHINERY 


NUMBER    139 

SHOP  SYSTEMS 

CONTENTS 

; 

General  Shop  System        -      -      -      -      -     :<v. "•  V-  -  3  ^ 

Stock-keeping  System,  by  S.  M.  Hovis  -      -      -  *   -  -  10  2~ 

An  Effective  Follow-up  System,  by  A.  L.  VALENTINE  -  17  y 

Routing  System  in  a  Machine  Tool  Shop    -      -      -  -  33  •* 


Copyright,    1914,   The   Industrial   Press,    Publishers   of   MACHINERY, 
140-148  Lafayette  Street,    New  York  City 


PREFACE 
1 

There  are  practically  as  many  shop  systems  in  use  as  there  are 
shops  or  factories;  because  in  every  shop  there  are  some  conditions 
peculiar  to  that  shop,  which  cannot  be  covered  by  any  system  of  uni- 
versal application.  There  are,  however,  certain  fundamental  princi- 
ples that  must  be  embodied  in  all  shop  systems,  and  these  can  be  best 
explained  by  describing  in  detail  a  number  of  systems  that  have  been 
successfully  applied  in  practice.  The  systems  outlined  in  this  Refer- 
ence Book  have  proved  their  value  in  the  manufacturing  establish- 
ments where  they  are  used.  They  may  not  apply  directly  to  the  con- 
ditions in  other  plants;  certain  details  may  have  to  be  changed  and 
some  of  the  forms  modified;  but  the  general  outlines  can  be  followed, 
and  will  prove  of  value  to  those  who  have  to  devise  new  systems  or 
are  endeavoring  to  improve  old  ones. 


CHAPTER  I 


GENERAL,   SHOP   SYSTEM 

Much  has  been  said  in  technical  books  and  magazines  regarding 
shop  systems,  but  many  of  these  systems  are  cumbersome,  and  show 
a  tendency  towards  "red  tape."  In  the  following  a  system  is  out- 
lined that  is  anything  but  elaborate,  being  compact  and  concise,  in- 
asmuch as  it  puts  all  information  regarding  the  affairs  of  the  works 
under  the  complete  control  of  the  works  superintendent.  It  makes 
him  entirely  independent  of  the  various  heads  of  departments  in  de- 
termining the  progress  of  all  work  through  these  departments,  and 
enables  him  at  a  glance  to  stop  or  push  such  work  as  is  important 


FACTORY  COST. 

IWBINENO.    izt=       STYLE      f       ISM*  to  Kqi'ts  N«.     t-*-a-t-s-i 

>rderNo. 

No.  Fin. 

Material 

Department  Costs 

Total  Cust 

Average  Com 

1 

1) 

I&&7 

Z*f 

IZ31>tt 
H4&4 
t*W 

to*, 
tttt 

f»^ 

7V  -if 

te^ 

zM-vJ 

ii-9Z 

^•A 

>9£i 

SI 

77 

3^. 

»*s* 

*.4 

«4fe 

»a-*» 

5?'7« 

W-'» 

..._.. 

il*3 

74 

IM 

t-z 

i'O-V* 

M-^ 

J^-» 

ri-»» 

«f«J 

lit 

») 

— 

— 

_ 

^_ 

Fig.   1.     Superintendent's  Office  Reference  and  Record  Card  of  Machine  Costs 

or  is  wanted  in  a  hurry.  At  the  same  time  it  gives  him  an  authentic 
record  of  all  facts  pertaining  to  the  cost  of  material  and  labor,  ana 
other  particulars  of  equal  importance.  Not  only  that,  but  in  case  of 
emergency,  it  assures  a  promise  of  any  special  delivery,  rush  order, 
etc.,  with  an  accuracy  that  cannot  be  denied. 

The  fundamental  principle  of  the  system  is  not  building  the  com- 
pleted machine  as  a  unit,  but  building  the  machine  by  the  part.  Con- 
sidering that  in  most  manufacturing  establishments,  the  machines" 
are  standardized  and  fully  detailed  with  complete  drawings  of  alJ 
parts,  this  can  readily  be  accomplished,  and  means  the  grouping  to- 
gether of  the  equipment  in  batteries  best  suited  to  handle  the  work 
along  these  lines  without  any  undue  shifting  around  of  material, 
keeping  it  in  the  correct  rotation  from  department  to  department 
in  succession  until  finally  brought  to  the  assembly.  To  do  this  the 
following  departments  known  by  number  have  been  established  in 


347603 


Xo.    i:'!» • -?M01»  SYSTEMS 


one  machine  building -plant,  where  the  system  described   is  used: 
D     Drafting-room; 
P     Pattern-shop; 

1  Planer,  boring  mills  and  large  radials; 

2  Lathe; 

3  Milling   machine; 

4  Shaper    and    drill    press; 

5  Tool  and  die  making; 

6  Grinding; 

7  Experimental; 

8  Small  part  assembly; 

9,    10,  11,  and  12  Assembly; 
13     Miscellaneous. 

The    assembly    departments,    8    to    12    inclusive,    are    equipped    with 
the  necessary  small  machine  tools. 


PART* 
rorli 

iO.    z_^     N< 

FACT( 

>.  required  each  nuchi 
*    Style      ^ 

)RY  ( 

K      '          ( 

COST. 

Mer  issued  to  Dep'ts 

HI.      2-J-^-«? 

chteeNt.-^ 

Jr.;.-r\., 

No  Flo 

Miit.-nnl 

Ik-|*rtmvnt  Cram, 

Ti.i.-il  c.-i 

Atmgvunj 

1 

1 

1 

1 

I 

" 

! 

1 

1 

10 

11 

II 

u 

1- 

" 

•£L1 

2V 

/V«  Vo 

<v-* 

vfcz 

«*• 

H7 

in 

2 

•ZJ 

>Vi* 

2V 

/4-o-fV 

/*•*> 

"foi 

/V*> 

• 

Zoi 

To 

| 

£l 

>*£* 

/« 

So^V 

•?V.S 

JJM 

^7 

lOt, 

*<> 

« 

88 

• 

Figr.  2.     Superintendent's  Office  Reference  and  Record  Card  of  Parts  Costs 

The  mode  of  procedure  is  as  follows:  The  sales  department  issues 
its  order  to  the  superintendent  in  the  customary  manner  for  a  given 
number  of  machines  of  a  certain  type;  all  machines  are  known  by 
nitmber.  The  superintendent  then  secures  from  the  drafting  depart- 
ment a  complete  set  of  blueprints  showing  all  the  details,  and  from 
which  the  orders  calling  for  these  parts  are  issued  to  the  various 
departments. 

The  following  is  a  list  of  blanks  and  cards  used,  and  which  are 
herewith  illustrated: 

Pig.  1.  Superintendent's  office  reference  and  record  card  of  machine 
costs. 

Fig.  2.  Superintendent's  office  reference  and  record  card  of  parts 
costs. 

Fig.  3.     Requisition  blank. 

Fig.  4.     Superintendent's  office  stock  advice  ticket. 


GENERAL  SHOP  SYSTEM 


Fig.  5.     Identification   tag. 

Fig.  6.     Department  shop  order. 

Fig.  7.     Department  partial    shop   order   ticket. 

Fig.  8.     Daily  time  ticket. 

When  the  superintendent  receives  the  order  for  the  machines,  he 
will  cause  the  order  number  to  be  recorded  on  a  card  like  that  in 
Fig.  1;  eventually  this  card  will  contain  a  full  record  of  all  costs  of 
the  machine;  it  is  known  as  the  "Machine  Factory  Cost,"  and  is 
printed  on  blue  paper  so  that  it  may  be  readily  recognized.  This 
card  is  ruled  into  columns,  and  will  contain,  as  before  stated,  all 
factory  particulars,  including  the  number  finished,  cost  of  material, 
cost  of  every  department  that  has  any  work  in  connection  with  same, 
and  finally  the  total  cost  of  the  order  and  the  individual  cost  of  each 


REQUISITION  FOR  MATE 

To  Store  Keeper,                                                                           Da 
Please  deliver  the  following  supplies, 

RIAL. 

,.      •z/rt/'l- 

T 

Quantity 

Patt.  No. 

Part  No. 

Mach.  No. 

Order  No. 

*> 

7>-1<, 

)L 

^7 

'^7 

i&t 

P-./ 

4 

it 

<r 

v-4 

f^fr~f 

*L 

„ 

„ 

#| 

e-**/ 

•^ 

H 

„ 

A_3    UtXx  t^X-'KVxVO                                  dtna»m» 

Department  No  ^- 

Fig.    3.     Requisition    Blank 

machine.  Each  successive  order  is  recorded  on  this  card,  and  a  ready 
comparison  of  the  fluctuations  in  operating  expenses  for  departments 
are  immediately  noted  for  investigation  with  a  view  to  ascertaining 
the  causes. 

The  parts  of  each  machine  are  numbered  in  rotation,  and  a  separate 
record,  as  in  Fig.  2,  printed  on  yellow  paper  is  kept  of  each  in  con- 
nection with  the  blue  card  above.  This  "Parts"  card  will  eventually 
contain  a  full  record  of  departments  that  handle  the  part,  its  weight, 
cost  of  material,  costs  of  each  department,  and  also  the  total  and  indi- 
vidual or  average  cost  per  part.  Each  successive  order  is  recorded 
the  same  as  on  the  card  above,  and  the  loop-holes  in  manufacturing 
due  to  negligence  on  the  part  of  foreman  or  operator  are  immediately 
shown  by  the  comparison  of  costs  of  labor,  etc.,  in  each  department. 

The  large  and  heavy  castings  that  represent  the  main  parts  of  the 
machine  are  never  kept  in  stock,  and  so  are  provided  for  immediately 


6 


No.  139— SHOP  SYSTEMS 


by  the  superintendent  on  a  requisition  blank  like  that  in  Pig.  3,  sent 
to  the  purchasing  department.  These  blanks  are  made  up  in  book 
form,  four  on  a  page;  they  have  perforated  edges,  and  are  made  in 
duplicate,  the  copy  remaining  in  the  book  as  a  part  of  the  superin- 
tendent's record. 

For  the  smaller  parts  or  castings,  the  superintendent  causes  the  list 
shown  in  Fig.  4  to  be  sent  to  the  store-keeper.  This  list,  which  is 
printed  on  heavy  flexible  paper,  and  put  up  in  pad  form,  gives  all  par- 
ticulars, and  asks  for  the  information  indicated.  The  store-keeper,  on 

receiving  it,  ascertains  the  num- 
ber of  parts  or  castings  he  has 
on  hand  as  requested,  fills  in  the 
date,  signs  his  name  or  initials, 
and  returns  the  list  immediately 
to  the  superintendent's  office. 
Upon  the  advice  thus  received, 
the  balance  of  supplies,  if  any, 
are  immediately  ordered  by  the 
superintendent  through  the  pur- 
chasing department,  using  the 
blank  before  described,  Fig.  3. 
By  adopting  this  plan,  a  check  is 
kept  on  all  castings  and  supplies, 
which  prevents  the  continual  ac- 
cumulation of  such  supplies,  a 
condition  that  would  occur  if 
they  were  ordered  on  each  suc- 
cessive order  without  first  ascer- 
taining whether  or  not  any  stock 
was  available. 

The  parts  being  all  provided 
for  through  the  superintendent's 
office,  department  shop  orders, 
Fig.  6,  are  now  issued  to  the 
various  departments  for  all  the 


STOCK  ADVICE  TICKET. 

„...         Z/lo/l/ 

To  Store  Keeper. 
Please  ad  via 
without   delay,    regarding   the 
Supplies  for  MACHINE  NO 

*  Superintendent's  Office 
following    Castings    and 
.   IZ4  STVI  P     /=» 

Q^.,^ 

From  Ptf.  No. 

On  H«Ki 

S«uMr<  ot   Stof    K";r 

24 

F-  10 

"-'  'i 

*v 

f*-n 

M 

4* 

F>-,4 

=tV 

_ 

//£ 

P-I& 

-  ,-. 

*4 

P-lo 

/& 

N 

<4 

r*-*t 

-••/ 

v> 

14 

P-3Z 

o 

I 

y.4 

P-34 

£> 

j 

4$ 

-p-4z 

IZ 

D*.      *_/>//// 

R*t»rn  to  taperinteiMlmtt-*  Offic*.                      '^ 

Fig.  4.     Superintendent's  Office  Stock 
Advice  Ticket 


parts  to  make  up  the  completed 
machines.  These  orders  have 
the  number  of  the  department  printed  in  heavy  black  type  in  the 
upper  left  hand  corner,  and  are  printed  on  flexible  paper  (prefer- 
ably white),  so  that  they  may  be  typed  in  multiple,  to  include  all 
the  departments  handling  or  machining  that  particular  part.  As 
illustrative  of  its  operation,  an  order  is  issued  for  25  crankshafts  for 
a  certain  style  of  press;  orders  are  issued  to  departments  2,  3,  4,  and 
9.  The  lathe  department  No.  2  handles  the  work  at  the  beginning;  the 
milling  department,  No.  3,  handles  it  after  No.  2;  and  so  on.  Similar 
orders  are  issued  to  the  first  three  departments,  the  orders  being  dis- 
tinguishable by  the  number  representing  the  department  printed  in 
the  upper  left-hand  corner  as  above  stated.  A  separate  order,  similar 
to  the  others,  calling  for  the  number  of  the  complete  machines,  is 


GENERAL  SHOP  SYSTEM 


ORDER  NO. 
PART  NO._ 


issued  to  department  No.  9,  the  assembly  department  of  this  type  of 
machine.  Consequently  all  parts  machined  eventually  find  their  way 
to  the  assembly. 

Upon  the  receipt  of  this  order  by  the  head  of  department  No.  2,  or 
the  department  that  first  handles  it,  a  requistion  on  the  store-keeper 
is  issued  on  a  blank  similar  to  that  shown  in  Fig.  3,  for  the  number  of 
f orgings  required  to  fill  the  order,  and  as  these  have  been  provided 
through  the  superintendent's  office,  they  are  sent  as  requested,  having 
a  red  tag,  as  in  Fig.  5,  attached  to  one  of  the  lot  to  identify  them. 
This  tag  contains  all  particulars  as  to  quantity,  part  number,  machine 
and  style,  and  order  number.  As  the  work  is  completed  in  this  de- 
partment, this  same  tag  or  a  duplicate 
is  attached  to  one  of  the  crankshafts 
already  machined,  and  sent  to  the  next 
department  handling  the  same,  which 
in  this  case  is  No.  3.  The  same  pro- 
cedure applies  in  this  department;  the 
work  is  then  sent  to  the  next,  which 
is  No.  4,  with  the  red  tag  still  at- 
tached. This  department,  in  turn, 
sends  the  shafts  when  finished  to  the 
final  department,  No.  9,  which  is  the 
assembly.  Should  one  of  these  crank- 
shafts, by  any  mischance,  be  spoiled 
or  incorrectly  machined  through  an 
error  on  the  part  of  some  mechanic, 
this  system  compels  the  foreman  of 
the  department  to  report  this  fact  im- 
mediately to  the  superintendent,  thus 
causing  an  investigation  to  be  made  as 
to  how  it  happened,  whether  through 
negligence  or  accident,  and  gives  no 
opportunity  for  anyone  to  quietly  scrap 
it  without  the  full  knowledge  of  the 
superintendent.  As  the  work  is  fin- 
ished in  each  department,  the  shafts  Fi&1  5>  Identification  Ta* 
are  sent  on,  the  head  of  department  sending  them  to  the  head  of  the 
next  department,  who  acknowledges  their  receipt  by  signing  his  name 
in  the  space  provided  on  the  department  shop  order,  at  the  same  time 
filling  in  the  date.  This  compels  the  receiving  foreman  to  verify  the 
number  of  pieces  so  that  it  tallies  with  the  number  on  the  red  tag,  Fig. 
5.  After  obtaining  the  signature  of  the  next  department  foreman,  the 
shop  order  is  returned  to  the  superintendent  and  is  filed,  until  all 
departments  having  any  handling  of  this  part  have  turned  in  their 
shop  orders.  All  labor  being  completed  on  the  part,  the  costs  are 
transferred  to  the  factory  cost  ticket,  Fig.  2,  which  is  then  a  complete 
record  of  actual  costs. 

At  various  times,  through  the  excessive  rush  of  work  and  piling  up 
of  orders,  it  may  be  found  to  be  good  policy  in  some  departments  to 


MACHINE  NO. 
and  Style 


Quantity. 


Department  No.. 


8 


No.  139— SHOP  SYSTEMS 


make  up  only  a  part  of  the  order.  To  record  this,  another  blank,  Fig. 
7,  called  the  "Partial  Order  Ticket,"  printed  on  brown  paper  is  used 
by  the  head  of  the  department  in  lieu  of  the  regular  department  shop 
order,  and  after  going  through  the  same  routine  as  the  original  order, 
being  signed  by  the  foremen  of  the  departments,  is  turned  in  to  the 


2       DEPARTMENT  SHOP  ORDER. 

>r<Jfr  iiiur-1  ^  n-p'«-  ~»            2~3--1--q                                                                      n...           zl  '/  ol  II. 

F;  n,.!    Hv 

I3t>1 

24 

26 

p-ltl 

r-3 

1~r~l 

., 

AZ 

4* 

" 

f>-*t 

f*-*t*. 

'• 

24 

10 

" 

P-Z. 

f-ID 

To  be  used  by  Foreman  of  Department  as  a  Memorandum  of  PARTIAL  ORDERS  only. 

/* 

- 

• 

•  ,  '• 

* 

Return  to  Superintendent'*  Office  when  all  work  is  finished. 

Fig.    6.     Department   Shop   Order   Ticket 


2 


PARTIAL  ORDER  TICKET. 


To  be  used  for  ONE  ITEM  ONLY  when  Impossible  to  finish  up  full  number  of  Parts  on  Dep't  Shop  Order. 
Return  to  Superintendent's  Office. 


Fig.    7.     Department    Partial   Shop    Order    Ticket 

superintendent's  office.  As  this  is  done  the  fact  is  recorded  on  the 
original  shop  order  in  the  space  provided  for  this  purpose;  this  acts 
as  a  constant  memorandum  of  parts  still  due  on  the  original  order. 
Each  department,  in  turn,  on  completion  of  the  work  to  be  done  turns 
in  a  similar  ticket  to  the  superintendent;  these  are  in  pad  form  as 
issued  to  the  heads  of  the  departments.  This  partial  order  ticket, 
as  it  is  turned  into  the  superintendent's  office,  forms  part  of  the 
record  and  shows  what  progress  is  being  made  on  this  particular  part 


GENERAL  SHOP  SYSTEM 


through  the  works.  The  adoption  of  this  plan  enables  the  superin- 
tendent to  take  steps  to  push  through  and  direct  what  parts  are  to  be 
rushed,  and  avoids  the  holding  up  and  delaying  of  parts  in  the  various 
departments,  for  he  has  the  information  at  hand  to  locate  the  part  by 
looking  up  the  department  shop  orders  returned  to  his  office. 

A  "Daily  Time  Ticket"  as  shown  in  Fig.  8,  is  an  absolute  necessity. 
It  is  ruled  and  printed,  as  shown,  provision  being  made  for  all  par- 
ticulars of  both  stock  and  time;  it  also  forms  part  of  the  superin- 
tendent's record.  These  are  collected  daily  and  filed  in  respective 
order  number  rotation,  and  upon  completion  of  any  department  shop 
order,  all  information  is  transferred  to  factory  cost  cards  as  before 


DAILY  TIME  CARD. 


Fig.    8.     Daily   Time   Ticket 

described.     This  daily  time  ticket  is  an  important  factor  in  determin- 
ing actual  costs,  etc. 

To  sum  up,  a  system  such  as  this  one  is  automatic  in  operation,  ,and 
has  much  to  commend  it:  Firstj  there  is  a  complete  and  actual  record 
of  labor  costs  by  departments;  second,  a  constant  check  is  kept  of 
costs  by  comparison,  and  a  means  provided  for  locating  any  excessive 
expenditures  due  to  negligence,  incompetent  help  or  other  conditions; 
third,  the  cost  of  each  individual  part  or  piece  of  every  machine  is 
recorded — information  that  can  be  advantageously  used  in  computing 
cost  of  duplicate  parts  when  needed;  fourth,  there  is  a  correct  tally  of 
material  used  for  both  part  or  machine,  and  actual  cost  of  each;  fifth, 
an  additional  feature  is  that  after  a  complete  record  of  all  parts  and 
the  machine  have  been  established  on  the  factory  cost  cards,  Figs.  1 
and  2,  and  the  department  shop  order,  Fig.  6,  the  information  is  all 
there  to  facilitate  the  issuance  of  any  further  orders  for  similar  parts. 


CHAPTER  II 


STOCK-KEEPING   SYSTEM 


In  all  manufacturing  establishments  the  place  in  which  the  most 
money  can  be  lost  or  saved  is  undoubtedly  the  stock  room;  for  here, 
in  one  department,  we  find  all  the  parts  comprised  in  the  product,  the 
smaller  tools  used  in  its  making,  and  in  some  cases,  expensive  printed 
and  advertising  matter.  Yet,  in  nine  cases  out  of  ten,  this  depart- 
ment-is placed  in  some  poorly-lighted,  ill-ventilated,  obscure  part  of 
the  building  and  is  in  charge  of  a  man  who  has  probably  secured  the 
position  in  consequence  of  a  good  memory  or  his  inability  to  become 
a  mechanic,  and  who  is  very  frequently  incompetent,  probably  due  to 
his  being  very  much  underpaid.  As  assistants,,  there  are  usually  with 
him  a  few  boys  or  old  men  who  cannot  be  usefully  employed  in  other 
departments. 

The  system  of  stock-keeping  explained  in  this  chapter  has  been 
tried  in  various  plants  and  proved  to  be  very  successful,  not  only 


v 

>f 

v 

Jjf 

4 

V 

C 

_] 
3 

J 
4 

^"^~        2         ^^~ 

J 

j 

j 

J-- 

J 
1 

J 

J 
3 

_J 

_l 

1 

J 

^£ 

j 

-y 

j 

V 

J 

V 

FLOOR 

Machinery.!*  Y. 

Fig.    1.     Elevation   of   the   Arrangement   for   Keeping   Parts   used   by 
a    Company    Manufacturing    Small    Machines 

from  a  production,  but  also  from  a  pay-roll,  standpoint.  It  must  be 
understood,  however,  that  the  success  of  any  system  depends  largely 
on  the  cooperation  of  the  office  and  accounting  departments  with  the 
stock-keeper,  and  any  error  or  misunderstanding  between  them  should 
be  investigated  and.  settled  at  once;  for  frequently,  even  in  the  best 
managed  plants,  the  office  is  obliged  to  call  on  the  stock-keeper  for 
information,  and  his  prompt  attention  facilitates  matters. 

In  a  properly  systematized  plant  all  the  parts  entering  into  the 
final  product  should  be  kept  in  the  stock  room  and  drawn  out  as 
desired  on  orders  signed  by  the  proper  authority,  usually  the  foreman 
of  the  department  concerned.  This  stock  may  be  divided  into  three 
classes:  finished  stock,  rough  stock  and  supply  stock.  Under  the 


STOCK-KEEPING  SYSTEM 


11 


classification  "finished  stock"  are  included  all  the  parts  which  are 
manufactured  in  the  plant.  The  rough  stock  includes  all  purchased 
materials  such  as  steel,  iron,  rough  castings,  etc.  Supply  stock  con- 
stitutes such  materials  as  paint,  waste  oil,  small  tools,  etc.,  and  at 
times  includes  such  things  as  advertising  matter,  letter-heads,  en- 
velopes and  office  supplies.  The  first-mentioned  of  these  supplies  are 
frequently  included  under  the  "rough-«tock"  head,  but  experience 
shows  that  by  keeping  these  supplies  under  a  separate  heading,  better 
accounting  results  may  be  secured.  These  divisions,  of  course,  may  be 
varied  to  suit  the  requirements  of  the  accounting  department,  but  in 
most  cases  these  three  divisions  will  be  found  to  be  sufficient. 

It  cannot  be  too  forcibly  stated  that  every  article  in  a  stock  room 
should  be  known  by  a  number  in  addition  to  its  name,  and  wherever 


r 

D 

C 

B 

A 

7                    8 
5                   6 

a 

<2 
< 

3                   4 
1     Oco«     ? 

A 

B 

C 

D 

AISLE 

AISLE 

D 

C 

B 

A 

A 

B 

C 

D 

AISLE 

AISLE 

D 

C 

B 

A 

A 

B 

C 

D 

AISLE 

AISLE 

D 

C 

B 

A 

B 

C 

.D 

Machincro.N 

Fig:.   2.     Plan  of  Arrangement  Shown  in  Fig-.   1,   for  Keeping 
Machine    Farts 

possible  that  number  should  appear  on  the  requisition  for  material. 
In  good  manufacturing  systems  the  use  of  names  for  parts  may  be 
entirely  eliminated,  numbers  being  used  exclusively,  the  result  being 
better  and  quicker  service  in  the  filling  of  orders.  The  use  of  letters 
in  designating  material,  except  where  absolutely  necessary,  is  to  be 
avoided,  although  in  some  cases  a  letter  is  placed  before  or  after  a 
number  to  show  the  kind  or  quality  of  the  material.  As  for  example 
211 A  might  mean  casting;  642B  forging;  and  so  on,  although  a  sys- 
tem of  numbering  may  be  devised  that  is  equally  effective.  For  in- 
stance in  a  case  where  the  product  is  a  machine  consisting  of  a  num- 
ber of  minor  assemblies,  all  numbers  ending  with  0  would  designate  an 
assembled  part;  01  a  screw;  03  casting,  and  so  on.  By  such  an  ar- 
rangement a  parts-list  may  be  made  up  and  mastered  after  a  little 
study. 


12 


No.  139— SHOP  SYSTEMS 


The  center  of  the  building  seems  to  be  the  generally  preferred  posi- 
tion for  the  stock  room,  but  the  ideal  location  is  at  the  end  of  the 
building,  as  near  the  office  as  possible,  for  in  the  former  case  a  con- 
siderable drawback  arises  should  it  ever  become  necessary  to  enlarge 
this  department,  as  other  departments  would  be  more  or  less  incon- 
venienced. Furthermore,  firmer  and  better  structures  for  holding 
material  may  be  built  at  the  end  of  the  building. 

No  drawers  or  shelving  for  parts  that  are  in  constant  use  should 
be  more  than  sever^  feet  above  the  floor,  the  space  above  this  being 
utilized  for  such  parts  as  are  only  occasionally  called  for.  In  so  ar- 


X/  ^t/K.  cU^ 


#25:1 


4/253 


4/257 


Ox 


a, 


r 


a, 


Co 


14- 


Fig.    3.     Portion    of    Parts    List 

ranging  the  parts  that  they  may  be  readily  located,  an  indexing  system 
has  been  devised  which  with  slight  variations  may  be  suited  to  any 
special  business.  Fig.  1  shows  the  front  view  of  an  arrangement  used 
by  a  plant  manufacturing  a  number  of  small  machines.  This  room 
which  is  about  forty  feet  square  is  divided  through  the  center  by  an 
aisle  four  feet  wide  and  is  sub-divided  into  sections,  tiers,  and  com- 
partments. The  term  section  is  applied  to  the  construction  on  either 
side  of  the  aisle,  that  on  the  right  being  designated  by  even  numbers 
and  that  on  the  left  by  odd.  These  sections  are  divided  into  tiers 
which  represent  spaces  between  the  uprights  and  are  alphabetically 
lettered  to  avoid  the  confusion  of  numbers.  The  compartments  are  the 


STOCK-KEEPING  SYSTEM 


13 


drawers  or  shelving  for  holding  parts.  Figs.  1  and  2  give  a  general 
idea  of  the  application  of  this  plan. 

Sheet  iron  or  heavy  tin  is  the  most  practical  and  durable  construc- 
tion material  for  drawers,  especially  for  those  holding  parts  which  are 
oiled.  These,  with  a  small  card-holder  and  handle,  may  be  obtained 
at  low  price,  and  being  easily  washed  and  lighter  than  wood,  facilitate 
handling.  In  addition  they  should  be  made  interchangeable,  the  tiers 
being  fitted  with  strips  to  hold  interchangeable  boards  upon  which  the 
drawers  can  rest.  In  drawers  that  are  the  same  width  as  the  tiers 
(see  Fig.  1,  1A1  and  1A2),  these  strips  may  be  fastened  to  the  sides 
and  will  be  found  to  work  very  satisfactorily. 

The  arrangement  for  taking  care  of  the  stock  having  thus  been 
attended  to,  the  application  may  next  be  noted.  Fig.  3  shows  a  section 


STORES  ORDER                                                  ORDER  „„     ,437 

DELIVER  TO  A/JL     DEPT.      tj_       DATE      ^/2-//0               LOT  NO.             _2/ 

QUAN 

DESCRIPTION 

NO. 

PEH^JNIT 

TC0°TSA\ 

100 

YaA/fa,  ~fa>   GLAAJtsTYlJuriJt, 

^J-50 

FILLED  BV 

6/6 

CHECKED  BY 

7/2. 

O'K1  STOREKEEPEK 

*3*2>wi&L' 

FOREMAN 

C^-^^TTX^M/ 

Fig.    4.     Stock   Requisition   Slip 


Machinery.  N.  y. 


of  a  page  of  a  parts-list  in  common  use.  A  requisition  calls  for  part 
4250  which  is  shown  in  parts-list  as  being  located  in  section  1,  tier  A, 
drawer  1  (1A1.)  The  stock  clerk  knows  that  1  being  odd,  is  located  to 
the  left  of  the  main  aisle;  A  being  the  first  letter  of  the  alphabet,  is 
the  first  tier  of  section  1;  and  drawer  1  will  be  at  the  bottom  of  a 
tier.  One  company,  in  mind  at  present,  has  its  product  divided  into 
sections,  parts  for  which  are  drawn  out,  assembled  and  then  returned 
to  the  stock  room  and  again  drawn  out  combined  with  other  assem- 
blies, completing  the  finished  product.  Fig.  4  shows  the  form  of  stock 
requisition  slip  which  is  given  to  the  stock  clerk,  who  turns  to  the  card 
or  sheet  shown  in  Fig.  5,  looking  up  the  corresponding  number,  which 
readily  locates  the  article  desired.  This  order  after  being  filled  is 
checked  and  forwarded  to  the  office  where,  after  being  priced,  it  is 
filed  against  the  original  order.  It  is  not  within  the  range  of  this 
treatise  to  discuss  systems  of  accounting,  but  it  may  be  stated  that 
the  best  results  will  be  obtained  where  the  least  time  is  lost  between 
filling  the  order  and  sending  it  to  the  accounting  department. 


14 


No.  139— SHOP  SYSTEMS 


In  handling  steel  bars  of  all  shapes,  iron  pipe  may  be  used  in  the 
building  structure,  and  the  divisions  marked  with  tin  tags. 

The  stock  card,  Fig.  6,  gives  a  record  of  the  in-coming  and  out- 
going material;  and  the  stock  clerk  after  making  deductions,  should 
see  that  the  amount  in  stock  is  above  the  low  mark  which  is  indicated 
in  the  upper  right-hand  corner.  As  soon  as  filled  these  tickets  should 
be  forwarded  and  old  cards  filed  numerically  per  part  number;  but, 
this  work  should  be  done  by  the  stock-keeper  and  not  by  his  clerks. 
In  every  case  where  the  ticket  is  to  be  forwarded  or  parts  to  be 
ordered,  the  ticket  should  b€  placed  on  the  stock-keeper's  desk  where 
a  glance  at  it  will  at  once  convey  to  him  a  knowledge  of  the  way 
things  stand  in  regard  to  this  particular  article.  Every  card  should 
be  gone  over  carefully  before  forwarding  on  account  of  arithmetical 
errors  which  are  always  likely  to  occur;  and,  if  the  stock  system  is 


Z  5~0 


V-2.5L 


NAME 


SEC       TIER     COMP 


ft. 


4 


a. 


/9 


Fig.    5.     Stock-keeper's    Location    Card 

used  in  connection  with  the  so-called  perpetual  stocfr  record  system, 
this  is  imperative  as  any  difference  between  card  and  ledger  will  cause 
delay  in  checking  for  the  inventory. 

The  most  important  consideration  in  the  organization  of  a  stock  de- 
partment is  the  selection  of  the  stock-keeper,  who  must  be  a  good  man 
even  if  it  be  necessary  to  pay  him  the  highest  salary  on  the  roll.  This 
man  who  has  charge  of  what  should  be  the  most  valuable  department 
in  the  plant,  should  be  above  the  ordinary  employe  as  regards  both 
ability  and  character,  and  one  who  is  indifferent  or  incapable  should 
not  be  retained.  Furthermore  he  should  have  sufficient  capability  to 
assume  full  control  of  his  department.  By  this  'it  is  not  to  be  under- 
stood that  the  stock-keeper  is  to  be  allowed  to  adopt  his  own  methods 
regardless  of  the  prevailing  policy  of  the  management,  but  that  he 
should  be  strong  enough  to  fill  his  position  without  being  constantly 


STOCK-KEEPING  SYSTEM 


15 


called  upon  to  explain  errors  and  accidents,  for  a  man  of  this  type 
would  never  be  able  to  manage  a  department. 

Check  Systems  for  Tool-rooms 

In  order  to  determine  the  best  system  for  keeping  track  of  the 
tools  lent  to  the  workmen  from  the  tool  store-room,  three  methods, 
as  outlined  in  the  following,  were  tried  in  a  well-known  shop  employ- 
ing about  five  hundred  hands. 

With  the  first  methpd,   each  man  had  a  number  of  checks  in  his 
own  keeping,  and  one  of  these  was  deposited  with  the  store-keeper  for 


"°'  t+150 

LOCATION          /    CO/. 

LOW  MARK              5  0 

Ji^^dLi    6w^(2vs/vvv 

IN 

OUT 

ON  HAND 

O'.TC 

QUAN. 

Wl 

CUAN. 

b/-. 

fO 

3 

0 

t/4/ 

I 

//- 

3 

b 

3 

3 

3 

•=/,„ 

/  0  0 

/ 

3' 

3 

EXAMINED 

AND 
FORD 


/OO 


ORDER  NO. 

/f  37 


FRONT 


BACK 


Machinery,  N.Y. 


Fig.   6.     Card  for  Recording  Stock  in  the  Stock-room 


each  tool  borrowed.  This  check  was  hung  near  the  space  previously 
occupied  by  the  tool  lent,  in  the  usual  manner. 

As  the  foregoing  method  was  somewhat  unsatisfactory,  all  checks 
were  collected  from  the  workmen,  and  kept  on  a  board  in  charge  of 
the  store-keeper,  from  which  they  were  removed  and  hung,  as  in  the 
first  case,  when  tools  were  borrowed. 

The  second  method  also  proved  unsatisfactory  and  was  abandoned. 
Loose  printed  slips  of  paper  were  then  distributed  in  suitable  boxes 
about  the  works,  and  each  man  was  obliged  to  write  on  a  slip  his 
pay  roll  check  number,  what  tool  he  required,  the  date,  and  his  signa- 
ture. This  slip  was  then  handed  to  the  store-keeper  in  receipt  for  the 
tool  borrowed,  and  the  slips  filed  away  in  card  cases,  in  numerical 
order,  back  of  guide  cards  arranged  to  suit  the  various  classes  of 
tools,  such  as  taps,  reamers,  cutters,  etc.  When  the  tool  was  returned, 
the  slip  was  handed  back  to  the  man  to  be  destroyed. 

The  first  two  methods  are  the  ones  commonly  used  where  there  is 
a  tool  store-room,  some  firms  preferring  one,  and  some  the  other.  The 


16  No.  139— SHOP  SYSTEMS 

first  method  was  abandoned  by  the  shop  in  question'  after  a  twelve 
months'  trial,  because  the  men  could  not,  or  would  not,  take  care  of 
their  checks,  and  if  one  of  these  were  lost,  there  was  nothing  to  pre- 
vent its  being  used  by  another  man,  if  he  found  it,  for  it  was  im- 
possible for  the  store-boys  to  know  whether  every  man  handed  in  the 
proper  check  or  not.  Again,  checks  would  occasionally  get  misplaced, 
causing  considerable  trouble.  Various  means  were  taken  to  prevent 
these  troubles,  but  without  success,  and  finally  the  second  method 
was  adopted.  This  was  also  given  a  twelve  months'  trial,  and,  if 
anything,  proved  rather  worse  than  the  first,  as  the  store-boys  mis- 
placed the  checks,  omitted  to  replace  them  on  the  board  when  tools 
were  returned,  or,  if  there  was  more  than  one  check  on  the  hook, 
sometimes  took  off  the  wrong  check.  No  doubt  some  of  the  men  con- 
tributed to  the  trouble  by  losing  or  mislaying  a  tool,  and  then  claim- 
ing that  it  had  been  returned  and  that  the  boy  had  forgotten  to  re- 
place the  check  on  the  board.  The  third  method  has  proved  more  suc- 
cessful than  either  of  the  other  two.  Of  course,  it  takes  longer  to 
write  out  the  slips,  arid  there  is  a  slight  expense  for  paper,  printing, 
etc.,  but  this  expenditure  is  more  than  offset  by  the  satisfactory  way 
in  which  the  system  works. 

Modifications  of  Check  Systems 

Some  shops  have  endeavored,  with  certain  additions  to  the  metal 
check  systems,  to  make  them  more  successful.  In  one  case,  a  number 
of  checks  stamped  from  one  to  thirty-one  and  of  a  different  shape 
than  the  other  checks,  are  kept  in  separate  boxes  in  a  drawer  and 
used  for  each  date  of  the  month;  they  are  used  for  the  finer  tools 
only,  such  as  standard  plugs,  etc.  When  a  man  gets  a  standard  plug, 
for  instance,  his  check  is  placed  on  the  pin  where  the  tool  is  kept, 
and  a  check  with  the  date  of  the  month  is  also  placed  on  the  same 
pin,  thus  showing  what  day  the  tool  was  taken.  At  the  end  of  the 
month  if  the  tool  is  still  out,  the  man  having  it  is  looked  up  and  if 
he  still  wishes  to  use  the  tool,  he  must  first  return  it  to  the  tool-room; 
another  check  is  then  put  on  the  pin  showing  that  the  tool  was  taken 
again  on  the  first  of  the  month.  By  this  method  the  tool-room  fore- 
man knows  where  the  tools  are  on  any  date  of  the  month,  and  how 
long  they  have  been  out.  No  trouble  has  been  experienced  with  this 
part  of  the  system  thus  far. 

Another  modification  makes  use  of  duplicate  checks  in  the  follow- 
ing manner.  Each  man  has  a  number  of  checks  in  his  own  keeping, 
as  before.  A  check  of  different  shape,  with  the  name  and  size  of  tool 
stamped  on  it,  is  placed  on  a  pin  near  each  tool  on  the  shelf  or  in  the 
drawer.  When  a  man  calls  for  a  tool,  he  gives  his  check,  and,  in  re- 
turn, receives  in  addition  to  the  tool,  the  check  with  the  name  and 
size  of  tool  on  it;  it  is  really  an  exchange  of  checks.  This  system 
would  tend  to  prevent  the  men  or  boys  who  give  out  the  tools,  from 
placing  the  wrong  check  on  the  peg  of  some  missing  tool  and  holding 
the  wrong  man  responsible  for  it,  because  the  man  who  has  the  tool 
also  has  the  check  to  show  for  it;  furthermore  the  men  sometimes 


FOLLOW-UP  SYSTEM  17 

forget  what  tools  they  have  out  on  check,  either  by  lending  or  mis- 
placing them,  and  in  such  a  case  the  check  with  the  name  and  size  of 
tool  on,  would  be  a  reminder.  This  system,  in  which  there  is  an  ex- 
change of  checks,  is  in  use  and  has  proved  satisfactory. 


CHAPTER  III 


AN  EFFECTIVE   FOLLOW-UP  SYSTEM 

The  primary  consideration  in  introducing  new  methods  of  manage- 
ment, is  whether  or  not  an  adequate  return  will  be  derived  from  the 
expenditure  involved.  Such  return  may  be  either  direct  or  indirect, 
but  it  must  be  sufficient  to  offset  both  the  cost  of  introducing  the  new 
method  and  the  operating  and  maintenance  costs,  and  still  leave  the 
required  margin  or  profit.  When  the  project  is  of  a  size  which  in- 
volves a  large  outlay  of  money,  it  is  obvious  that  the  most  careful 
study  must  be  given  to  every  detail  of  the  proposed  plan. 

It  is  the  purpose  to  outline,  in  this  chapter,  a  follow-up  system  for 
keeping  an  account  of  the  materials  used  in  a  factory  engaged  in  small 
interchangeable  manufacture,  and  also  of  the  progress  made  by  dif- 
ferent orders  in  passing  from  department  to  department  in  the  course 
of  manufacture.  This  system  was  introduced  to  remedy  certain  evils 
that  are  likely  to  arise  in  any  manufacturing  establishment,  and  the 
man  responsible  for  it  was  particularly  fortunate  in  that  he  was  not 
hindered  by  considerations  of  expenditure.  This  fact  is  mentioned 
because,  had  considerations  of  expenditure  been-  carefuly  weighed  be- 
fore the  benefits  derived  from  the  change  had  been  demonstrated,  it 
is  probable  that  the  new  system  would  have  been  one  of  the  many  use- 
ful ideas  "adorning  the  shelf,"  owing  to  the  large  initial  and  up-keep 
expenses.  It  may  be  mentioned  that  lack  of  perception  on  the  part  of 
the  management  is  often  responsible  for  discarding  valuable  ideas 
from  failure  to  see  the  advantages  which  they  possess,  and  unwilling- 
ness to  bear  the  burden  of  what  appear  to  be  unreasonable  expenses. 

Before  explaining  the  workings  of  the  follow-up  system  described, 
it  will  be  of  interest  to  outline  briefly  the  conditions  which  were 
responsible  for  bringing  it  about.  As  previously  mentioned,  this  sys- 
tem was  introduced  through  necessity,  and  the  same  may  be  said  of 
the  changes  which  are  made  in  many  industrial  establishments.  When 
a  factory  is  engaged  in  the  manufacture  of  small  tools  or  similar 
products,  turned  out  in  large  quantities,  a  great  many  letters  are  re- 
ceived containing  the  vexing  question,  "When  will  you  ship?"  If 
these  inquiries  are  not  answered  promptly  and  truthfully,  the  people 
v/aiting  for  the  shipment  of  their  orders  will  often  be  put  to  consider- 
able inconvenience,  as  it  is  likely  that  they  have  planned  and  laid  out 
their  work  with  such  promises  of  shipment  in  view.  If  these  promises 


18  No.  139— SHOP  SYSTEMS 

are  not  kept,  the  orders  will  frequently  be  cancelled  or  repeat  orders, 
at  least,  will  not  be  received  by  the  manufacturer.  It  was  due  to  the 
distrust  created  among  prospective  purchasers,  through  giving  evasive 
answers  to  inquiries  about  dates  of  shipment,  and  failure  to  keep 
promises,  which  led  to  the  development  of  this  follow-up  system.  This 
system  is,  with  some  modifications,  in  use  in  one  of  the  largest  fac- 
tories of  its  kind  in  the  United  States,  and  after  more  than  three 
years'  experience,  it  has  demonstrated  its  ability  not  only  to  remedy 
the  evils  which  previously  existed,  but  also  to  improve  manufacturing 
conditions,  so  that  the  work  of  the  sales  department  has  been  made 
far  more  efficient. 

Benefits  of  a  Follow-up  System 

The  benefits  derived  from  this  system  may  be  briefly  outlined  as 
follows: 

1.  It    enables    the    management    to    tell    the    date    on    which    any 
order  will  be  finished  and  ready  for  shipment,  without  having  to  go 
out    into     the    different     manufacturing     departments,     and     with     a 
minimum  expenditure  of  time. 

2.  To     systematically     follow     up     all     work — promised     and     un- 
promised  from  one  department  to  another,  and  thus  receive  warning 
of  any  delays  or  mishaps  which  may  occur. 

3.  To   tell  at  short  notice  in  which  department  any   order   is   at 
any  time. 

4.  To  tell  at  equally  short  notice  how  long  an  order  has  been  in 
any  department  at  a  given  time,  thus  making  it  possible  to  investi- 
gate causes  of  delay  and  take  steps  to  remedy  them. 

5.  To  find  out  how  many  orders  a  department  has  on  hand,  thus 
making  it  possible  to  trace  congestion  and  investigate  the  cause,  i.  e., 
shortage  of  help,  equipment,  etc. 

6.  To    afford    a   means    of   creating   watchfulness   on    the    part    of 
department  heads   in   regard   to  the   time   taken   in  the  execution   of 
orders. 

As  a  result,  it  is  impossible  for  men  who  are  responsible  for  delays 
to  avoid  censure  by  such  time-worn  excuses  as,  "I  did  not  understand 
it  that  way,"  "I  mislaid  the  instructions,"  "I  did  not  know,"  etc.  As 
the  foremen  know  that  the  follow-up  system  affords  a  sure  method  of 
placing  responsibility  for  any  hitch  that  may  arise  in  the  execution  of 
an  order,  they  are  quite  careful  to  make  investigations  on  their  own 
account  before  their  superiors  have  been  advised  in  regard  to  any 
delinquency  that  may  have  occurred  in  their  respective  departments. 

To  those  who  are  intimately  in  touch  with  the  details  of  operating 
a  modern  plant,  it  may  seem  that  any  follow-up  system  is  a  needless 
expense,  especially  if  the  goods  manufactured  are  of  a  standard  kind 
(not  necessarily  size).  In  most  lines  of  manufacture,  however,  even 
standard  articles  consist  of  several  parts,  and  in  order  to  turn  out  the 
finished  product  these  parts  must  be  finished  and  made  ready  for  the 
assembling  department  long  before  the  supply  of  finished  product  has 
been  exhausted.  In  such  cases,  a  follow-up  system  is  necessary  for 


FOLLOW-UP  SYSTEM  19 

tracing  the  parts  of  the  coqa-pleted  product  through  the  different  de- 
partments of  the  factory.  Under  these  conditions,  the  system  can  be 
reduced  to  its  simplest  and  most  inexpensive  form,  its  chief  function 
being  to  follow  up  orders,  consisting  of  a  limited  number  of  either 
parts  or  complete  articles,  finishing  them  before  the  supply  is 
exhausted. 

The  system  has  its  greatest  usefulness,  and  is,  in  fact,  an  absolute 
necessity  in  establishments  manufacturing  small  products  of  many 
sizes  and  many  kinds,  where  a  great  variety  of  stock  must  be  kept  on 
hand  at  all  times.  It  will  also  prove  itself  of  more  than  ordinary 
value  to  an  establishment  where  the  departments  have  been  grouped 
according  to  operations  as  is  now  nearly  universally  the  case.  The 
advantage  of  this  method  is  that  each  department  is  run  by  an  expert 
who  operates  the  type  of  machines  used  in  his  department  according 
to  the  most  economical  method,  thus  making  them  produce  more  and 
better  work  than  would  be  possible  if  the  product  were  made  complete 
in  a  single  department.  The  saving  effected  by  this  method  is  limited 
by  the  loss  of  time  which  is  involved  in  moving  the  work  from  one 
department  to  another,  in  getting  started  in  each  department  and  by 
such  necessary  operations  as  counting,  inspecting,  etc.  Where  a  fac- 
tory is  run  on  this  method,  without  the  use  of  an  efficient  follow-up 
system,  it  will  not  be  long  before  trouble  will  be  encountered  from 
failure  to  keep  promises  in  regard  to  shipment  dates,  through  finding 
the  supply  of  raw  material  suddenly  exhausted,  etc. 

Causes  of  Delay  in  Finishing:  Orders 

The  most  important  features  governing  deliveries  in  any  manu- 
facturing plant  are  the  stock  and  store-rooms  for  either  finished  parts 
or  the  complete  product.  Such  being  the  case,  it  will  be  well  to  in- 
vestigate some  of  the  causes  which  are  responsible  for  failure  to  supply 
these  departments  with  goods  in  the  required  quantity  and  at  the 
specified  time.  The  causes  may  be  outlined  as  follows: 

1.  Non-anticipation  of  large  orders  and  the  receipt  of  a  number  of 
small  orders  at  the  same  time. 

2.  Shortage  of  raw  material  and  failure  to  get  in  a  fresh  supply 
in  time  to  meet  existing  requirements. 

3.  Failure  to  obtain  additional  equipment  in  time  to  meet  existing 
requirements. 

4.  Lack  of  system  in  ordering  stock,  resulting  in  failure  to  issue 
orders  to  the  factory  in  time  to  allow  them  to  be  completed  before  the 
stock  on  hand  has  been  exhausted.     The  department  having  this  work 
in  hand  should  have  intimate  knowledge  of  the  capacity  of  each  de- 
partment, as  well  as  of  the  entire  factory,   so  that  it  is  possible  to 
foretell   exactly   the  amount  of  time  required   to  complete  any  order 
which  is  issued. 

5.  Delays  resulting  from  resetting  automatic  machinery  to  adapt  it 
for  a  new  class  of  work. 

6.  Delays    caused    by   premium    or   contract   systems   where    depart- 
ment   foremen    evade   changing   machines    from    one   kind    of   work   to 


20  No.  139— SHOP  SYSTEMS 

another,  in  order  to  secure  the  greatest  possible  financial  gains  for 
themselves  and  their  men. 

7.  Failure  of  the  management  to  see  the  advantage  of  investing 
money  in  finished  material,  blanks,  castings,  and  raw  material.  This 
condition  is  most  pronounced  in  times  of  depression,  which  are  best 
suited  for  "stocking  up,"  as  labor  is  cheapest  at  such  times  and  manu- 
facturing can  progress  unhampered  by  special  orders  that  must  be 
completed  by  a  specified  time. 

Nearly  all  of  these  causes  of  delay  were  remedied  in  less  than 
eighteen  months  by  the  follow-up  system  described.  This  was  due  to 
the  fact  that  the  system  automatically  calls  attention  to  conditions 
responsible  for  delays,  and  keeps  everyone  from  the  manager  and 
"superintendent  to  the  foreman  and  his  assistant,  informed  of  the  con- 
ditions that  have  to  be  met  in  order  for  shipments  to  be  made  at  a 
specified  time.  After  a  careful  investigation  of  the  causes  of  delay 
outlined  in  the  preceding  paragraph,  it  may  be  stated  that  the  failure 
to  keep  an  adequate  supply  of  materials  on  hand  is  responsible  for  the 
greatest  amount  of  trouble.  The  other  reasons  outlined  suggest 
methods  of  avoiding  them,  so  that  little  comment  is  necessary.  It 
\vill  prove  worth  while  in  the  long  run  to  keep  a  few  surplus  ma- 
chines and  a  reserve  quantity  of  finished  parts,  blanks  and  raw  ma- 
terial on  hand.  This  will  make  it  possible  to  take  care  of  large  orders 
that  come  in  unexpectedly  or  a  number  of  small  orders  received  simul- 
taneously, without  impairing  the  operation  of  the  factory  in  any  way. 

There  is  no  excuse  for  any  plant  manufacturing  a  product  for 
which  there  is  a  continued  demand,  not  providing  itself  with  a  sur- 
plus supply  of  finished  product.  It  is  a  conceded  fact  that  the  growth 
of  any  industry  is  dependent  upon  its  ability  to  meet  the  demands  of 
its  customers,  both  as  regards  quality  and  prompt  service.  The  cus- 
tomer scarcely  considers  whether  his  order  is  too  large  for  your 
establishment  or  whether  there  are  other  orders  on  hand  which  must 
be  filled  before  his  receives  attention.  The  result  is  that  the  factory 
Avhich  is  able  to  fill  orders  promptly  usually  gets  the  business.  The 
question  of  quality  is  taken  for  granted,  and  the  manufacturer  who 
neglects  this  feature  will  find  himself  unable  to  meet  the  keen  com- 
petition that  exists  in  practically  all  lines. 

Value  of  Surplus  Stock  and  Equipment 

The  preceding  may  be  summarized  by  stating  that  in  order  to  meet 
possible  demands  of  customers  for  immediate  delivery,  one  of  two 
conditions  must  exist  in  the  factory.  The  stock-room  must  either  be 
well  filled  with  finished  product  or  finished  parts  of  which  the  product 
consists,  so  that  it  is  merely  a  matter  of  assembling  them  for  prompt 
shipment,  or  else  the  factory  must  have  an  equipment  large  enough 
to  take  care  immediately  of  large  orders  and  finish  them  without  de- 
lay. The  first  condition  may  be  fulfilled  by  issuing  orders  to  the  fac- 
tory in  sufficient  quantity  and  far  enough  ahead  to  enable  the  parts  to 
be  finished  before  the  supply  of  stock  on  hand  is  exhausted.  (It  is 
suggested,  in  this  connection,  that  when  the  supply  on  hand  has  been 


FOLLOW-UP  SYSTEM 


21 


reduced  to  an  amount  equal  to  /the  number  of  pieces  sold  during  any 
previous  year,  another  order  for  an  equal  quantity  should  be  issued 
immediately.  The  machine  and  tool  equipment  should  also  be  large 
enough  to  produce  such  a  number  of  pieces  in  a  year.)  While  most 
manufacturers  are  willing  to  invest  in  reserve  equipment,  they  are 
unwilling  to  keep  a  surplus  stock  of  product  on  hand.  It  is  reasonable 
to  assume  that  the  capital  invested  in  extra  equipment  provided  to 
meet  emergencies  is  equal  at  least  to  that  necessary  for  keeping  a  suf- 
ficient quantity  of  finished  product  on  hand  to  meet  such  emergencies. 
In  most  cases,  however,  the  capital  invested  in  finished  product  'is 
less  than  that  required  for  a  sufficient  reserve  equipment,  and  this 
advantage  is  further  emphasized  by  the  fact  that  shipments  can  be 
made  immediately  upon  the  receipt  of  orders,  when  the  product  is  on 
hand  in  the  store-room.  In  addition,  the  capital  will  be  turned  over 
more  rapidly,  as  it  is  not  necessary  to  wait  while  the  product  is  being 


CUSTOMERS 
ORDER  NO. 

OUR 
ORDER  NO. 

NO.  PIECES 
WANTED 

KIND  OF  TOOLS 
WANTED 

WILL  FINISH 
DATE 

1 

2 

3 

4 

5 

FILLED  IN 
BY  OFFICE  OR 
(STOCK  DEPT.) 

. 

FILLED  IN 
BY  FOLLOW-UP 
DEPT. 
AND  RETURNED 
TO  OFFICE  WITH 
ORIGINAL  LET. 
OF  INQUIRY. 

Machinery 

F 
BEF( 

LLED  IN   BY  ; 

RE  BEING  SENT  T 

>TOCK  DER-R" 

>  FOLLOW-UP  DEPT. 

Fig.   1.     Form  used  to  follow  up  an  Inquiry  Regarding  Date   of  Shipment 

made  before  it  can  be  shipped  on  a  given  order.  It  seems  scarcely 
possible  that  this  fact  can  escape  the  attention  of  the  management  of 
so  many  manufacturing  establishments,  especially  when  the  product 
so  "stocked"  can  generally  be  produced  at  less  expense  than  when 
made  under  average  conditions.  The  solution  is  seemingly  found  in 
the  fact  that  equipment  does  not  show  up  on  the  books  in  the  same 
way  as  finished  product.  In  considering  this  subject,  it  should  also 
be  borne  in  mind  that  immediate  shipment  is  a  means  of  adding  to 
the  list  of  satisfied  customers,  who  will  send  in  repeat  orders  as  the 
result  of  efficient  service. 

The  Follow-up  System 

Having  thus  outlined  some  of  the  more  important  reasons  for  the 
use  of  a  follow-up  system,  and  the  conditions  over  which  it  has  con- 
trol, the  system  which  has  many  original  features,  and  which  has  been 
proved  to  be  more  efficient  than  other  systems  coming  under  the 
author's  observation  will  be  described.  In  order  to  make  the  explana- 


22 


No.  139— SHOP  SYSTEMS 


tion  readily  understood,  certain  minor  details  such  as  shipping  and 
factory  order  forms  will  be  omitted.  Suffice  it  to  say  that  the  forms 
in  general  use  for  such  purposes  can  be  adapted  to  almost  any  system 
with  satisfactory  results.  In  starting  upon  an  explanation  of  the  work- 
ings of  this  system,  it  will  be  assumed  that  any  inquiry  as  to  the  date 
of  shipment  of  an  order  is  received  by  the  office.  This  inquiry  usually 
carries  the  customer's  order  number,  and  is  generally  given  a  factory 
order  number  by  which  it  is  known  until  the  order  has  been  completed 
and  shipped.  The  inquiry  is  immediately  turned  over  to  the  stock  de- 
partment with  the  tag  shown  in  Fig.  1  attached  to  it.  The  customer's 
order  number  is  generally  filled  in  by  the  office,  but  in  certain  cases 


CUSTOMER __ 
ADDRESS. 


CUSTOMERS 
NO. 


OUR 
NO. 


NUMBER  AND  KIND  OF  TOOLS 
WANTED 


DATE 
SHIPPED 


Machinery 


Fig.    2.     Card  Index   kept  by  Stock   Department 

where  the  customer's  original   order  number  is  on  file  in   the  stock 
department,  the  tag  is  left  to  be  filled  in  when  it  reaches  that  point. 

The  stock  department  keeps  a  card  index,  of  the  form  shown  in  Fig. 
2,  on  which  the  factory  order  number  is  given  opposite  the  customer's 
order  number  in  cases  where  the  goods  are  not  in  stock  and  have  to 
be  made.  If  no  number  appears  on  the  card  opposite  the  customer's 
order  number,  it  signifies  that  the  goods  have  already  been  shipped, 
the  date  of  shipment  being  recorded  in  the  column  marked,  "Date 
Shipped."  If  shipment  has  not  been  made,  which  is  shown  by  the 
fact  that  no  notation  appears  in  column  4,  and  if  no  number  appears 
in  column  2  it  shows  that  shipment  can  be  made  from  surplus  stock 
on  hand.  These  cards  are  indexed  according  to  names,  and  it  will  be 
noticed  that  one  or  more  cards  are  used  for  each  customer  and  that 
each  card  takes  care  of  several  orders. 


FOLLOW-UP  SYSTEM 


23 


£=$ 

100 

DATE  ( 
NAME 

ORDER 
PROMIS 
DESCRI 

ORD 

3F  ISSUE  OF  W 
OF  CUSTOMER 
(» 
NO. 

ER  TRACER 
o  

•  STOCK—  WRITE  "STOCK"  HERE) 

i1 
>ED 

PTION  OF  TOOl 

s 

NAME  OF 
DEPT. 

DEPT. 
NO. 

LEFT 
THIS 
DEPT. 
DATE 

MUST  LEAVE 
THIS  DEPT. 
DATE 

REMARKS: 
REASON  FOR  DELAYS 
ETC. 

CUT-OFF 

1 

CHUCKING 

2 

<o    ^     • 

T        ?       *~ 

TURNING 

3 

dj 

MILLING 

4 

CO      til     ° 

INSPECTING 

5 

2     0    0 

HARDENING 

6 

I     <    0 

H    z    h 

GRINDING 

7 

rp 

INSPECTING 

8 

1  ss 

o   z-S 

9 

0      S    £0 

-ifj 

10 

«  8  i 

s 

ae 

GIVING  EACH  DEPARTMENT  A  NUMBER  SAVES 
WRITING  OUT  THE  NAME  OF  THE  DEPARTMENT 
ON  "DAILY  REPORT",  ETC. 

THIS  IS  FILLED  IN  BY  ROUTE  CLERK  AND  IS  A  COPY 
OF  ROUTE  CARD  GOING  WITH  W.O.  DATES  "MUST 
LEAVE"  ARE  NOT  IN  ROTATION  AS  THE  WORK  DOES 
NOT  ALWAYS  TRAVEL  IN  THE  ORDER  IN  WHICH  NAME 
OF  DEPT.  IS  GIVEN  IN  COL.  1 

FILLED  OUT  FROM  FOREMAN'S  REPORT  TO  SUPER- 
INTENDENT BY  FOREMAN  SENDING  THE  WORK. 

1234                                     5                   Machinery 

Fig.    3.     Order   Tracer   Card   Index   kept   by   Follow-up   Department 


24 


No.  139— SHOP  SYSTEMS 


If  the  order  is  special  (not  in  stock  and  not  finished),  the  inquiry, 
with  the  tag  shown  in  Fig.  1  attached  to  it,  is  immediately  turned  over 
to  the  follow-up  department  for  answer  in  regard  to  the  date  on  which 
delivery  will  be  made.  All  of  the  columns  on  the  tag,  shown  in  Fig. 
1,  except  the  last  one,  have  been  filled  out  by  the  stock  department, 
the  date  being  taken  from  what  is  known  as  the  shipping  order  which 
includes  all  details  in  regard  to  the  items  covered  by  the  order. 

The  follow-up  department  refers  to  the  order  tracer  card  file,  the 
form  of  which  is  shown  in  Fig.  3.  These  cards  are  filed  in  numerical 
order,  one  card  being  provided  for  each  order  number,  and  show  the 
location  of  any  order  in  the  factory  at  any  specified  time.  Conse- 
quently it  is  known  how  far  the  work  has  advanced,  and  also  the  date 


1 

PROMISED 
9  

DATE 

-; 

i 

4 

5 

» 

j 

* 

I 

1 

J 

1 

1 

12 

1 

* 

14 

15 

• 

i 

• 

• 

1 

2 

2 

2 

? 

2 

4 

2 

5 

? 

> 

2 

7 

? 

2 

| 

3 

T 

_3 

•MMMTI 

Fig.   4.     Work  Calendar  showing  Dates   on  which   Orders   must  be  Finished 

on  which  the  work  will  be  finished.  A  record  is  also  kept  on  this  file 
of  any  delay  that  has  occurred,  the  department  in  which  it  occurred 
and  the  reasons  for  the  delay,  reference  being  made  to  the  superin- 
tendent's "Reasons  for  Delayed  Orders"  file  for  this  information. 
Every  foreman  is  required  to  report  to  the  superintendent  at  the  end 
of  each  day's  work  in  regard  to  every  order  which  could  not  be  finished 
and  sent  on  to  the  next  department  as  required  by  the  schedule.  When 
a  department  foreman  receives  an  order,  he  marks  the  number  of 
the  order  on  his  work  calendar  in  the  column  opposite  the  date  on 
which  the  operation  must  be  finished  by  his  department.  One  of  these 
calendars,  shown  in  Fig.  4,  is  generally  hung  up  in  the  office  of  the 
foreman  to  afford  him  a  means  of  looking  ahead  to  make  sure  that  all 
orders  will  be  finished  on  time,  according  to  the  schedule  laid  out  by 
the  route  clerk. 


FOLLOW-UP  SYSTEM 


25 


ESTIMATE  AND  ROUTE  CARD 

(MUST  ALWAYS  TRAVEL  WITH  ORDER  IN  ENVELOPE) 

ORDER  NO. 

DESCRIP1 

CUSTOMS 

'ION 

R 

NAME  OF 
DEPT. 

DEPT. 
NO. 

ROUTE 

MUST 
LEAVE 
THIS 
DEPT. 
DATE 

ACTUAL 
DATE 
OF 
LEAVING 
DEPT. 

REMARKS: 
REASON  FOR  DELAYS 

ETC. 

CUT-OFF 

1 

1 

CHUCKING 

2 

2 

TURNING 

3 

5 

MILLING 

4 

4 

INSPECTING 

5 

6 

HARDENING 

6 

7 

GRINDING 

7 

8 

INSPECTING 

8 

3 

9 

,     ' 

10 

1 

2 

WHEN  OPERATION  IS  DONE  SEND  WORK 
W  TO  DEPT.  NEXT  IN  ROTATION. 

FILLED  OUT  BY  ROUTE  CLERK 
FROM  CAPACITY  CARDS. 

01  FILLED  OUT  BY  DEPT.  FOREMAN. 

0)  FILLED  OUT  BY  DEPT.  FOREMAN. 

1 

Fig:.   5.     Estimate  and  Route   Card  which  follows  an   Order 
through    the    Factory 

The  date  on  which  the  work  or  operation  must  be  completed  by  any 
department  or  foreman  will  be  found  on  the  "Route  and  Estimate" 
card  shown  in  Fig.  5.  These  cards  are  filled  out  by  the  route  clerk 
before  the  orders  for  the  work  are  sent  out  to  the  factory,  and  follow 
the  orders  for  the  work  from  one  department  to  another  until  the  order 


No.  139— SHOP  SYSTEMS 


is  completed.  These  route  cards  not  only  show  when  each  operation 
must  be  finished,  but  also  the  order  in  which  the  work  is  passed  along 
from  department  to  department,  as  shown  in  column  3.  Referring  to 
Fig.  5,  it  will  be  seen  that  after  the  chucking  operation  is  competed 
in  Department  2,  the  work  must  be  sent  to  Department  5  for  inspec- 
tion, then  to  Department  4  for  the  milling  operation,  and  so  on  until 
it  is  completed.  Before  the  work  leaves  any  department,  the  actual 
date  of  leaving  is  filled  out  on  the  route  and  estimate  card  by  the  fore- 
man of  the  department.  This  is  done  at  the  same  time  that  the  daily 


OF  OR! 

NAME  OF  DEPT.  .. 

DAILY  REPORT 

)ERS  HAVING  TO-DAY   LEFT  THIS  DEPT. 
DATE  

NAME  OF 
DEPT. 

DEPT. 
NO. 

DATE  OF 
PROMISE 
OF 
ORDER 

ORDER 
NUMBER 

ORDER 
SENT  TO 
DEPT. 
NO. 

REMARKS 

CUT-OFF 

1 

CHUCKING 

2 

TURNING 

3 

MILLING 

4 

INSPECTING 

5 

HARDENING 

6 

GRINDING 

7 

INSPECTING 

8 

9 

10 

1 

2 

3 

4 

5 

6 

Machinery 

(DEPT.  FOREMAN) 

Fig.    6.     Form   used   by   Foremen   in    making-   Daily   Reports 

report,  shown  in  Fig.  6,  is  filled  out,  and  the  foreman  receiving  the 
work  will  be  certain  to  report  any  errors  in  these  dates  to  the  follow- 
up  department,  if  the  route  cards  are  dated  unfavorably  to  him.  This 
affords  a  method  of  checking  the  accuracy  of  the  daily  reports  when 
they  are  being  recorded  on  the  tracer  card  file  by  the  follow-up  clerk. 

The  plan  of  having  the  foremen  report  any  delinquincies  or  causes 
for  failure  to  complete  an  order  in  accordance  with  the  schedule,  is  one 
of  the  best  guarantees  that  the  work  will  be  finished  on  time.  As  the 
superintendent  is  kept  constantly  in  touch  with  the  progress  of  each 
order  by  this  method,  he  is  able  to  take  the  necessary  steps  to  prevent 


FOLLOW-UP  SYSTEM 


27 


a  constant  recurrence  of  delays  in  any  department,  and  this  is  largely 
responsible  for  the  success  which  has  been  obtained  from  the  use  of 
this  system. 

With  the  data  available  through  the  records  kept  by  this  system,  it 
is  possible  to  answer  inquiries  in  regard  to  the  date  of  shipment  im- 
mediately and  with  a  reasonable  degree  of  accuracy,  without  having 


ROUTE  CARD 

COLLETS  &2  SCREW  MACHINE 

ALL  SIZES  COLLETS  FOR  THIS  MACHINE  TAKE  SAME  ROUTE; 
ALSO  ALL  SIZES  FOR  *3  AND  ^4  SCREW  MACHINE. 

ROUTE 

DEPARTMENT 

No.  OF 
DEPT. 

REMARKS 

1 

CUT-OFF 

1 

2 

CHUCKING 

2 

5 

TURNING 

3 

4 

MILLING 

4 

6 

INSPECTING 

5 

8 

HARDENING 

6 

GRINDING 

7 

INSPECTING 

8 

f 

\THIS  ( 
MADE 

1 

OLUMN   PILLED  IN 
OUT  IN  CASE  OF 

2 

-AND  CAN 
CHANGE  IN 

3 

BE  CHANGED  OR  NEW  CARD 
EQUIPMENT  OR   METHODS. 

4" 
Machinery 

Fig.   7.     Route  Card  for  Collets  for  No.   2  Screw  Machine 

to  go  out  into  the  manufacturing  plant  for  the  purpose.  It  will  be 
seen  that  the  tracer  card  file,  shown  in  Pig.  3,  is  the  key  to  the  whole 
situation.  As  previously  mentioned,  these  tracer  cards  are  made  out 
before  the  orders  go  to  the  factory  and  are  checked  every  day  from 
the  daily  reports  shown  in  Fig.  6.  The  route  outlined  on  the  route 
and  estimate  card,  shown  in  Fig.  5,  is,  of  course,  an  exact  copy  of  the 
route  card  illustrated  in  Fig.  7  for  the  particular  class  of  work  which 


28 


No.  139— SHOP  SYSTEMS 


0 

o 

0 

CAPACITY  SHEET—  PER  HOUR-PER  DAY  OF  10  HOURS 

COLLETS  ^2  SCREW  MACHINE 

DEPART- 
MENTS 

CAPACITY-SIZE 

REMARKS 

Va 

H 

:5i 

% 

CUT-OFF 

CHUCKING 

TURNING 

MILLING 

i 

INSPECTING 

HARDENING 

GRINDING 

INSPECTING 

Machinery 

Fig.   8.     Capacity  Sheet  for  No.   2  Screw  Machine   Collets 


0 

o 
o 

ORDERS  IN   PROCESS  -PROMISED 

COLLETS—  2  SCREW  MACHINE 

SIZE 

QUAN- 
TITY 

ORDER 

NO. 

CUT- 

DAT 

E  PROMIJ 

ED 

% 

H 

H 

% 

% 

% 

% 

% 

% 

% 

% 

% 

Machinery 

Figr.    9.     Sheet   giving  Record   of    Orders   in   Process   of   Manufacture 


FOLLOW-UP  SYSTEM  29 

is  being  made.  In  this  connection,  it  may  be  mentioned  that  the 
routes  followed  through  the  factory  by  many  classes  of  work  are 
practically  the  same. 

Determining-  the  Capacity  of  the  Factory 

The  capacity  sheet,  shown  in  Fig.  8,  although  not  directly  connected 
with  the  follow-up  department,  plays  an  important  part  in  the  oper- 
ation of  the  factory.  These  sheets  show  the  capacity  of  each  depart- 
ment for  all  the  different  operations  which  it  handles.  They  are  kept 
in  a  special  loose-leaf  binder,  so  that  changes  may  easily  be  made  in 
case  of  the  addition  of  new  machinery  or  methods  in  any  department. 
The  left-hand  pages  of  the  sheets  kept  in  this  binder  enable  the  route 
clerk  to  determine  the  capacity  of  any  department  for  a  given  opera- 
tion at  a  glance,  and  the  right-hand  pages,  shown  in  Fig.  9,  give  a 
record  of  all  the  orders  in  the  factory  that  must  be  handled  by  the 
different  classes  of  tools,  the  capacities  of  which  are  given  on  the 
capacity  sheets.  The  dates  on  which  these  operations  must  be  com- 
pleted are  recorded!  so  that  when  a  new  order  is  issued  an  accurate 
estimate  of  its  date  of  completion  may  be  made. 

The  follow-up  clerk  checks  the  number  of  each  order  which  has 
been  passed  on  to  a  new  department  and  the  departments  to  which 
the  work  was  sent  from  the  daily  reports,  when  checking  up  the  tracer 
cards  each  morning.  In  so  doing,  he  finds  any  discrepancy  between 
the  date  on  which  the  work  was  finished  and  the  date  when  it  should 
have  been  finished,  according  to  the  schedule.  He  may  refer  to  the 
superintendent's  file  to  obtain  the  reason  in  case  of  delay. 

Although  this  system  may  be  said  to  fill  all  of  the  requirements  of 
following  up  the  progress  of  orders  through  the  factory,  and  keeping 
them  moving  according  to  schedule,  it  is  lacking  in  certain  respects. 
For  example,  how  can  a  factory  manager  or  superintendent  determine 
the  number  of  orders  that  a  certain  department  has  on  hand  at  any 
time  from  a  qard  index?  How  are  such  officials  going  to  find  out 
(without  the  assistance  of  a  lot  of  clerical  help  and  a  lot  of  red  tape) 
how  long  an  order  has  been  held  in  a  given  department?  How  are 
they  going  to  know  if  promises  are  kept?  For  this  purpose,  the 
"Follow-up  Rack"  was  designed,  of  which  two  sections  are  shown  in 
Fig.  10,  and  which  the  writer  believes  to  be  an  entirely  new  feature  in 
follow-up  systems. 

This  rack  consists  of  twelve  sections,  one  being  provided  for  each 
month  in  the  year,  and  is  used  to  keep  a  record  of  progress  of  the 
work  in  the  factory.  A  small  card,  of  the  form  shown  in  Fig.  11,  is 
made  out  at  the  same  time  that  the  estimate  card  is  made  out  when 
an  order  is  sent  to  the  factory.  Referring  to  Fig.  11,  it  will  be  seen 
that  one  side  of  this  card  has  spaces  for  the  order  number,  the  name 
of  the  customer,  the  date  on  which  delivery  is  promised  and  a  descrip- 
tion of  the  product  called  for  by  the  order.  The  opposite  side  shows 
the  different  operations  that  must  be  performed  on  the  work,  the  dates 
when  the  work  should  leave  the  different  departments  according  to 
the  schedule,  and  the  actual  dates  upon  which  it  did  leave  these  de- 


30 


No.  139— SHOP  SYSTEMS 


jnnnooflQnQQQO 


— 4 


E-SI 


§  -2 


OJ    *O     <D 

en     <D    -M 
O>     >    *2 


£  =  £S 


0      U    '"     rH 


!  SS| 
lie 

^  -^         *H  O 

t^      ra   4_>   4-> 

^     ^3    w    oj    cc 


S     o    o    01    « 
,     S  EH    S  o 


•a  -   tn 

I  =  1 1 ; 

.    £§S2 


i 

o      ^_, 


i  s  i 


E    i   S  5 


0    ^3    "- 


-I1 

o  H    ^  .2 

02  r-T 

7-1      O     ^     5 

bib  W)  fe 

1 5 1 

a  -  g  I 

C     tj     O    -g 

0)    c   43    ;- 

I*1  «  8 


FOLLOW-UP  SYSTEM 


in  Column  2  by.  the  route  clerk/'at  the  same  time  that  he  is  filling  out 
the  estimate  and  tracer  card,  the  clerk  refers  to  the  capacity  sheet, 
Pig.  8,  and  to  the  promised  order  sheet,  Fig.  9,  to  find  if  the  order  can 
be  completed  by  January  28,  which  is  the  date  specified  for  delivery. 
He  then  files  the  card  in  the  28th  column  of  the  January  rack,  opposite 
the  department  in  which  the  first  operation  is  performed.  The  card 
is  then  moved  up  or  down  in  this  column,  keeping  it  opposite  the  de- 
partment to  which  the  work  has  been  transferred  until  the  work  is 
completed.  The  proper  location  for  the  card  is  found  from  the  daily 
report,  which  not  only  indicates  to  which  department  the  work  has 
been  sent,  but  also  the  date  on  which  the  order  was  promised  for 


SPECIAL 

WO     Nn. 

DATE 

PROMISED   COMPLETE 

DESCRIPTION 

CUSTOMER 

FRONT 


h- 
U. 
UJ 

-I 

00 

°% 

' 

;OF 

Y 

OF 

CC 

)LL 

M 

,- 

,   F 

IG. 

5 

<N 

u 

Q. 
O 

LL 
0 
h- 

3 

[CHUCKING 

[TURNING 

o 

z 

s 

[INSPECT. 

|  HARDEN. 

[GRINDING 

[INSPECT. 

- 

BACK 


Machinery 


Fig.    11.     Follow-up   Rack   Card   for   Special   Orders 

delivery.    This  enables  the  position  of  the  card  in  the  rack  to  be  im- 
mediately found,  and  also  the  date  on  which  it  was  promised. 

The  card  remains  in  the  28th  column  until  the  order  is  completed, 
after  which  it  can  either  be  thrown  away  or  filed  for  future  reference. 
This  arrangement  enables  one  to  see  at  a  glance  just  how  many  orders 
are  promised  to  be  completed,  and  if  they  are  not  finished  on  time 
this  is  immediately  indicated  by  the  appearance  of  the  cards  in  the 
rack  for  dates  already  passed.  This  naturally  causes  everyone  con- 
cerned to  push  the  work  along  with  all  possible  speed,  and  constitutes 
a  gage  of  efficiency  for  both  the  department  foremen  and  the  follow-up 
department.  This  rack  also  makes  it  possible  to  look  ahead,  and  if 
there  appears  to  be  any  doubt  in  regard  to  a  given  order  being  unfin- 
ished by  the  specified  date,  there  is  ample  time  to  take  the  necessary 
steps  to  avoid  such  a  contingency. 


32 


No.  139— SHOP  SYSTEMS 


All  twelve  racks  are  arranged  in  a  single  horizontal  row,  and  by 
looking  along  the  row  it  is  possible  to  form  an  accurate  estimate  of 
how  many  orders  a  given  department  has  on  hand  at  any  time,  which 
could  not  otherwise  be  easily  done.  By  looking  at  the  back  of  the 
card,  it  is  possible  to  see  just  when  the  work  should  have  been  com- 
pleted in  a  given  department,  and  when  it  actually  was  finished,  the 
backs  of  the  cards  being  filled  out  by  the  follow-up  clerk  from  the 
daily  reports  sent  in  by  the  foremen.  These  data  are  especially  valu- 
able in  cases  where  delay  has  occurred,  as  the  department  where  the 
delay  occurred  can  be  instantly  located  without  having  to  refer  to 
the  order  tracer  file. 

It  will  readily  be  seen  that  the  capacity  records  involve  a  good 
deal  of  expense,  not  only  in  getting  them  up  but  in  keeping  them 


STOCK 

w.n.  NO.                         P 

DATF 

ROMISFD  COMPLETE: 

npsr.RiPTioN 

FRONT 


t 

CO 

0    0 
jUI 

0* 

( 

OF 

Y 

OF 

Of 

M  I 

M 

M   4 

,    1 

1C. 

> 

CM 

Is 

t 

£ 

K 
3 

0 

[CHUCKING 

[TURNING 

0 

? 

[INSPECT. 

.-• 
I 

i 

[GRINDING 

[INSPECT. 

^- 

BACK 


Machinery 


Fig.    12.     Follow-up  Rack  Card  for  Stock  Orders 

up-to-date.  It  has  been  found  however,  that  these  records  are  an  actual 
necessity,  whether  a  follow-up  system  is  used  or  not,  and  conse- 
quently this  expense  cannot  justly  be  entered  on  the  books  against  the 
follow-up  system.  The  advantages  secured  through  the  follow-up  sys- 
tem and  follow-up  rack  which  have  been  described  are  far-reaching  in 
their  results.  The  heads  of  manufacturing  companies  have  not  gen- 
erally much  time  for  details,  and  the  use  of  this  system  keeps  them 
informed  of  nearly  all  the  conditions  in  the  plant  that  are  of  vital 
importance.  Very  little  time  is  required  to  secure  this  information, 
and,  best  of  all,  they  can  determine  just  what  these  conditions  are 
without  spending  valuable  time  in  going  about  the  factory.  Figures 
and  data  are  often  misleading  and  errors  or  unintentional  deceptions 


ROUTING  SYSTEM  33 

entering  into  the  reports  of  subordinates  are  very  frequently  responsi- 
ble for  serious  complications.  Where  this  system  is  used,  however, 
such  deceptions  are  impossible  and  the  management  is  thus  protected 
from  both  deserved  and  undeserved  criticism  of  customers,  which  leads 
to  the  loss  of  future  orders.  Hence,  this  follow-up  system  may  be 
said  to  constitute  one  of  the  most  productive  non-productive  depart- 
ments in  any  manufacturing  establishment. 


CHAPTER    IV 


ROUTING   SYSTEM   IN  A  MACHINE  TOOL  SHOP 

Of  shop  systems,  like  books,  there  is  no  end,  and  again  like  books, 
there  are  good  and  bad  systems.  Any  shop  system  must  be  judged  by 
what  it  accomplishes  and  the  cost  of  its  administration.  The  simpler 
a  system,  other  things  being  equal,  the  better  it  is  when  judged  from 
the  practical  man's  point  of  view.  The  following  system  of  routing 
work  through  a  machine  shop  is  that  used  in  the  building  of  hori- 
zontal boring  machines  by  the  Lucas  Machine  Tool  Co.,  Cleveland, 
Ohio,  and  is  commended  for  its  simplicity  and  the  complete  control 
and  knowledge  of  the  progress  of  work  through  the  shop. 

The  detail  drawings  are  made  on  sheets  19%  by  26  inches.  The 
sheets  are  divided  into  sections,  the  size  varying  according  to  the  size 
of  the  parts  shown.  The  largest  number  of  divisions  of  the  sheet  is 
sixteen,  these  being  obtained  by  three  horizontal  and  three  vertical 
lines.  This  size  is  used  only  for  the  small  simple  details  that  can  be 
clearly  delineated  in  the  available  space.  In  all,  there  are  five  sizes 
of  divisions  up  to  and  including  one  half  the  sheet.  The  scheme  is 
illustrated  in  part  in  Pig.  1.  At  the  bottom,  space  is  reserved  for 
the  operation  numbers  and  records  of  progress. 

Two  blue-prints  are  made  of  each  group  of  details  in  the  drawing 
room  and  issued  for  each  lot  of  twenty-four  machines.  One  print  is 
made  of  paper  and  is  kept  in  a  binder  in  the  shop  office.  The  other 
print  is  made  on  cloth  and  is  cut  apart,  making  as  many  individual 
prints  as  there  are  separate  details  on  the  sheet.  These  are  punched 
at  the  top  and  provided  with  a  ring  to  which  is  attached  a  routing  tag. 
The  routing  tag  is  filled  out  in  the  shop  office  and  sent  into  the  shop 
with  its  blue-print  to  accompany  the  parts  until  finished  and  de- 
livered to  the  assembling  floor  or  the  store-room. 

For  the  purpose  of  illustration  the  4-pitch  23-tooth  first  driving 
bevel  gear  has  been  chosen.  This  detail,  shown  on  the  sheet  Fig.  1, 
is  shown  detached  in  Fig.  2  with  its  routing  tag  attached.  The  sym- 
bol of  this  part  on  the  drawing  is  32—139,  in  a  circle.  The  first  num- 
ber is  the  machine  number  and  the  second  is  the  pattern  number,  in 
case  the  piece  is  a  casting.  Each  operation  for  each  piece  on  the  sheet 


34 


No.  139— SHOP  SYSTEMS 


1-OfilVING  n/U£ 


i-nRivma  CHAIN  SPROCKET  SLeeve 

v. 
I 


«o   r 

I! 


Fig.    1.     Detail    Drawing    showing    Operation    Numbers    and    Record    of    Progress 


ROUTING  SYSTEM 


35 


is  designated  in  the  operation  sheet  at  the  bottom  of  Fig.  1,  in  the 
spaces  opposite  the  part  symbol.  The  operations  on  the  chosen  piece 
are  12-a,  12-b,  13,  16,  24,  9,  15  and  20,  these  being  "turret  chuck"  (a 
and  b),  "gear  cutter,"  "keyseater,"  "store-room,"  "lathe,"  "milling  ma- 


ROOTANGLE     39*48' 


SEGMENT  NO.      /Z 


TOOTH  ANGLE  3°44' 
THROW     //          S° 


l-c*-% 


YWG  BWEL  GFAR 


v 


P^BT  NUMBER 


•?3-T. 


BLOCK 


3°^'    urn 


#-/?*  — 

T~"C 


1 
< 


r 

I  5 


tiKrenfr  i 

OIOIRED  FO 


HIST86S  m). 

T8MAK  » '-> 

PIECES  IS  ST8SI  M 

\iw  FSS  mwm  it.^-. 


\ 


Fig.    2.     Detached  Detail  Drawing  with  Routing  Tag 

chine,"  and  "fitting"  as  will  be  seen  in  the  accompanying  schedule  of 
operation  numbers. 

It  will  be  noted  that  this  schedule  gives  the  name  of  the  operation 
in  some  cases,  but  in  more  it  gives  the  name  of  the  machine.  The 
reason  for  this  is  that  the  individual  operations  on  the  lathe,  milling 
machine,  etc.,  are  minutely  specified  in  separate  lists  that  accompany 
the  routing  tag  and  blue-print  when  required  to  follow  out  the  order 


36 


No.  139— SHOP  SYSTEMS 


that  has  been  determined  in  the  planning  department.  These  lists 
of  operations  are  typewritten  and  blue-printed,  &nd  are  pasted  on  the 
back  of  the  shop  blue-prints. 


No    o6S 

ORDER  NO. 


PIECE  NO. 


OPERATION  ... 

'NO.  PCS.             ->  ^—-  NO.  PCS. 

ORDERED .^C.O FINISHED 


NO 


.7 


.CARD  ..  ...DATE 


if 


DATE 


MOR^MNQ_      _[     AFTERNOON  'fTIME 

IN         |    OUT   \       IN 


•   1  17  | 
' 


1-18 


OUT 


;  : 


OUT 


Fig.    3.     Top  Portion  of  a  Cost  Card 


1. — Planing 

2. — Boring  Machine 

3. — Drilling  Machine 

4.— Helping 

5. — Cleaning  Castings 

6. — Painting  (includ- 
ing filling  and 
rubbing) 

7. — Cutting  off 

8. — Centering 

9.— Lathe 


Operation  Numbers 

10. — Lo-swing  Lathe 
11.— Turret  Bar 
12.— Turret   Chuck 
13. — Gear  Cutter 
14.— Thread  Milling 

Machine 

15.— Milling   Machine 
16. — Keyseater 
17. — Grinder 
18. — Polishing 
19. — Scraping 


20.— Fitting 

21. — Miscellaneous 
hand   work 

22. — Erecting 

23. — Inspecting 

24. — Store  Room 

25. — Graduating 

26.— Spindle  Boring 
Machine 

27. — Auto.  Turret  Ma- 
chine 


The  first  operation  on  the  bevel  gear  blank  is  chucking  in  the 
Gisholt  turret  lathe  and  performing  operation  "a."  This  operation  is 
boring,  facing  and  turning  the  surfaces  designated  by  the  line  a  in 
the  drawing,  which  starts  in  the  bore  and  terminates  at  the  outer 
angle  of  the  tooth  section.  This  line  is  broken,  the  break  being  one 
short  dash.  One  short  dash  indicates  that  it  is  the  first  operation. 
The  second  operation  "b"  is  indicated  on  the  drawing  by  another 
broken  line  6,  the  break  consisting  of  two  short  dashes.  Of  course, 
the  operator  on  the  turret  lathe  does  not  change  from  one  operation 


ROUTING  SYSTEM 


37 


to  the  other  on  each  piece.  He  does  one  operation  on  each  piece  first 
and  then  changes  his  chuck  and  tools  to  do  the  second  operation,  and 
so  on. 

When  the  lot  of  castings  and  the  routing  tag  are  delivered  to  the 
turret  lathe,  a  check  mark  is  made  by  the  clerk  on  the  shop  office 
drawing,  opposite  the  symbol.  This  mark  shows  that  work  has  been 
started  on  these  parts.  Further  records  are  made  from  the  cost 
cards,  a  sample  of  which  is  shown  in  Fig.  3.  The  cost  cards  are  of 
the  regular  form  supplied  by  the  International  Time  Recorder  Co. 
and  are  stamped  in  a  time  recording  clock  when  the  job  is  started 


PART  NUMBER 


o 

-^" 


BLUEPRINT  No. 


ORDERED  FOR. 

NUMBER  OF  EXTRAS 

IN  STOCK  0 


/O  6  6 


NUMBER  OF  PIECES 

TO  MAKE <X.O 


PIECES  IN  STOCK  ARE 
READY  FOR  OPERATION  No.. 


WORKMAN  WILL  BE  HELD  RESPONSIBLE  FOR  THE 
CARE  OF  THIS  TAG  AND  KEEPIN.G  ITWITH  THE 
WORK. 
Po.r.m  No.  17 


O 


OPERATION 
NUMBER 

w  ~° 

0     " 

i£  u 

?.£ 

No.Rej't'd 
Acct. 
Material 

No.  Pieces 
Spoiled 

S"S 
<u  5 

Q-  -i 
Q   o> 

•Z.  Q 

Checked 
Inspected 

/2  0.-2 

3.5 

O 

O 

££ 

if 

/3 

2f 

/ 

0 

2  4 

Py 

/6 

24 

0 

0 

24 

^ 

3-? 

24 

Z4 

m 

9 

x± 

24 

w 

IS 

34 

24 

fa 

20 

£4 

24 

4// 

Figs.    4  and   5.     Front   and   Back  of  Routing   Tag 

and  when  completed.  They  are  partly  filled  out  by  the  shop  office 
clerk,  the  order  number,  piece  number,  operation  and  number  of 
pieces  being  the  items  entered.  The  cards  then  go  to  the  foreman 
who  keeps  them  in  a  card  rack  with  index  tab  cards  to  designate 
the  various  operations.  Thus  there  will  be  cards  for  practically  all 
the  operations  enumerated  on  the  schedule  of  operations. 

The  turret  lathe  operator  who  machined  the  bevel  gear  blanks  was 
charged  with  twenty-five  pieces,  an  extra  piece  being  supplied  to  re- 
place any  casting  found  defective  or  spoiled.  When  he  finishes  opera- 
tion 12-a  and  12-b,  the  time  of  completion  is  stamped  in  the  time 
recorder,  and  the  card  is  turned  in  to  the  foreman,  who  then  gives  the 


38  No.  139— SHOP  SYSTEMS 

workman  another  job,  and  the  cost  card  for  the  operation  is  stamped 
in  the  "In"  column.  The  cards  for  completed  operations  are  col- 
lected each  morning,  and  the  completed  operations  are  marked  off 
on  the  shop  office  blueprints  as  indicated  in  Fig.  1  for  operations 
12-a  and  12-b.  The  same  is  being  done  for  all  the  other  parts  on  this 
sheet  and  on  the  other  sheets  for  the  lot  of  machines  going  through. 

When  the  turret  lathe  man  completes  the  lot  of  bevel  gear  blanks 
and  so  reports  to  his  foreman,  the  report  means  to  the  shop  office 
that  the  lot  has  been  delivered  to  the  machine  for  the  next  operation. 
An  order  is  not  considered  complete  until  the  delivery  is  made. 

The  next  operation  in  this  case  is  gear  cutting.  Twenty-five  turned 
and  bored  blanks  are  delivered  to  the  gear  cutting  department  to- 
gether with  the  routing  tag  and  blue-print,  Fig.  2.  The  operator  to 
whom  they  are  turned  over  stamps  the  time  of  beginning  in  the  "In" 


32-106 

JIG     NO.  616  PART  No.       32-109  DRAWING    No     2-520 

RACK  6  .  SHELF         £*L.  .  SECTION      /'"',& 

No.  OFMACH.  *|     NO.     32    H.B.M.  JIG  FIRST) 

NAME  OF  PIECE) -Driving  pulley  Sleeve  &  Chain  USED  ON>  M.32-L2 
Sprocket  Sleeve. 

REMARKS : 

Jig  for  drilling  oil  and  screw  holea. 


Loose  piece  -  13/32  Buah- 


Fig.   6.     Sample  Index  Card  Showing  Location  of  a  Jig  in  the  Tool-room 

column  of  a  cost  card  filled  out  for  operation  13,  and  when  the  lot 
is  completed  the  time  is  stamped  in  the  "Out"  column  as  before.  In 
this  case  one  blank  was  found  defective  when  cut  and  twenty-four  per- 
fect gears  were  turned  over  to  the  keyseater  for  operation  No.  16. 
The  next  morning  the  cost  card  went  into  the  shop  office  and  opera- 
tion 13  was  checked  off  on  the  shop  office  record  blue-print. 

The  orders  for  castings  also  originate  in  the  drawing  office,  and 
the  prints  are  not  issued  to  the  shop  office  until  the  castings  are 
delivered  by  the  foundry.  The  drawings  are  made  to  convey  all  neces- 
sary instructions  to  the  workmen.  Thus  when  parts  are  to  be  drilled 
or  bored  in  jigs,  the  jig  number  is  given  on  the  drawing.  For  ex- 
ample, the  driving  pulley  sleeve  and  driving  chain  sprocket  sleeve, 
symbols  32—108  and  32—109,  are  drilled  in  jig  No.  616.  This  jig 
will  be  found  in  the  tool-room  in  rack  6,  on  shelf  E,  in  section  1 — 2. 
The  description  of  the  jig  and  location  are  given  on  a  card,  Fig.  6, 
kept  in  a  card  index  in  the  tool-room. 


ROUTING'  SYSTEM  '  39 

From  this  outline  it  will  be  understood  that  a  constant  record  is 
available  in  the  shop  office  which  shows  from  day  to  day  the  progress 
of  work  on  any  lot  of  machines  and  the  location  of  all  parts.  It 
also  shows  the  number  of  parts  spoiled  and  indicates  on  what  opera- 
tion they  were  spoiled.  The  costs  can  be  calculated  for  a  machine 
or  lot  of  machines  in  any  stage  of  construction.  The  system  is  much 
more  quickly  comprehended  than  described,  and  its  simplicity  is 
shown  by  the  fact  that  one  clerk  attends  to  all  its  details  after  re- 
ceiving the  blue-prints  from  the  drawing  office. 


Heat-Treatment  of  Steel 

is  one  of  a 
series  of 
high  -  class 
authorita- 
tive, attract- 
ive and  well- 
bound  books 
published  by 
MACHINERY. 

The  strong- 
est claim  that 
can  be  made 
for  these 
books  is  that 
they  have  all 
the  charac- 
teristics of 
MACHINERY 
itself. 

These  books 
cover  com- 
prehensively, 
and  in  a  thoroughly  practical  manner,  the  most 
important  subjects  in  the  metal-working  field. 

Each  book  comprises  about  300  pages,  printed 
on  high-grade  paper,  with  engravings  of  the 
same  superior  type  that  has  made  MACHINERY 
distinctive  in  its  field. 

The  price  of  each  book  is  $2.50.  Special  com- 
bination offers  on  a  monthly  payment  plan  will 
be  sent  upon  request. 

MACHINERY 

140-148  Lafayette  St.  New  York  City 

51  and  52,  Chancery  Lane,  London,  W.  C. 


UNIVERSITY  OF  CALIFORNIA  LIBRARY 
BERKELEY 

THIS  BOOK  IS  DUE  ON  THE  LAST  DATE 
STAMPED  BELOW 

Books  not  returned  on  time  are  subject  to  a  fine  of 
50c  per  volume  after  the  third  day  overdue,  increasing 
to  $1.00  per  volume  after  the  sixth  day.  Books  not  in 
demand  may  be  renewed  if  application  is  made  before 
expiration  of  loan  period. 


il 

NOV  27  1917 

01  12  IMS 


7Api>50GE 


5  Om-  7,'  16 


VC  539 


UNIVERSITY  OF  CALIFORNIA  LIBRARY 


MACHINERY'S 

HANDBOOK 

For   MACHINE    SHOP 
AND  DRAF1INQ-ROOM 


A  REFERENCE  BOOK  ON  MACHINE 
DESIGN  AND  SHOP  PRACTICE  FOR 
THE  MECHANICAL  ENGINEER, 
DRAFTSMAN,  TOOLMAKER  AND 
MACHINIST. 


MACHLN  ,-ises  nearly  MOO  p.  .u-pfully  edi      : 

condensed    data   f-iating   to   the   'heory     H  aehine-1 

industries.     It  is  tl;  'id  only  conip]  ;te  handbook 

the   metal  ,iU   contains    in   compact   ai  *sed    fo         i.e 

information  and   d  .\    during  ...       twi>ntj 

It  is  the  one  •  uook  in  a  library  of  mecli. 

contains  all  that  is  of  importance  in  the  text  books  and  treaties  on  met 
engineering  prat- rice.    Price  $5.00.  (1£). 

GENERAL  CONTENTS 

Mathematical    tables — Principal    m  formulas    in    arithmetic    and    al-< 

Logarithms     and     logarithmic     tables-  volumes — Solution     of     triangles 

trigonometrical    tables — Geometrical    proposition    and    problems — Vjchanics — Strength    of 
materials — Riveting   and   riveted   joints — Strength   and   proper':  [    wire — Stn  ; 

and  properties   cf   wire   rope — Formulas   and   tables   for   spring   ue.v.(?n — Torsional   strength 
— Shaftiu^    -Friction — Plain,    roller   and   ball   bearings — Kcyo    u  V — Clutches   and 

couplings — Friction    brakes — Cams,    cam    design    ari    cam    millin^  — Spur    gearing — Bevel 
gearing — Spiral  gearing-- -Herringbone  gearinpr — Worm  gearing — Epicyclic  Bearing — Belting 
and  rope  drives — Transmiss.  -n  chain  am!    .ham  dtivos — Crane  chain — Dimensions  of  s;j  all 
machine  details — Speeds  and  feeds  of  machine  tools — Shrinkage  and  force  fit  allowan< 
Measuring   tools   and   0;iging   methoils — Change   gears   for   spiral   milling — Milling   machine 
indexing — Jigs    and    fixtures — Grinding   and    grinding    wheels — Screw    thread    systems 
thread    grap  . — Taps    and    threading    dies — Milling    cutters — Reamers,     countfj  bores    and 
twist   drills — Heat-treatm«nt   of   steel — Hardening,    casehardening,    annealing — Testing    the 
hardness    of    metals — Foundry    and    pattern    shop    information — The    welding    of    metals — 
Autogenous    welding — Thermit    welding — Machine    welding — Blacksmith    shb*p    information 
— Bit,    casting — Extrusion    process — Soldering    and    brazing — Etching    and    etching    flu. 
Coloring  metals — Machinery  foundations — Application  of  motors  to  machine  tools — Dynamo 
and    mot        troubles — Weights    and   measures — Metric    system — Conversion    tables — Sp 
gravity — Weights   of   materials — Heat — Pneumatics — Water  pressure   and   flow   of  wa1 
Pipes  and  piping — Luted  and  cements — Patents. 


MACIIINEKY,  the  leading  jourr  .1  in  the  machine-building  field,  the  originator 
of  the  25-cent  Reference  and  Data  Books.  Published  monthly.  Subscription, 
$2.00  yearly.  Foreign  subscription,  $3.0-. 

THE  INDUSTRIAL  PRESS,  Publishers  of  MACHINERY 
140-148  LAFAYETTE  STREET  NEW  YORK  CITY,  L.  S.  A.