Vol. 6 DEPARTMENT OF THE ARMY CORPS OF ENGINEERS BULLETIN | °c: ‘ COL Li LEC TION OF THE WOODS HOLE BEACH EROSION BOARD OCEANOGRAPHIC InSTITATION JUL 16 195} OFFICE, CHIEF OF ENGINEERS wooDs HOLE, MASS. WASHINGTON, D.C. VOL. 5 JULY 1, 1951 NO.3 TABLE OF CONTENTS By-Passing Littoral Drift at a Harbour Entrance .....0¢. Calculation of Diffracted Wave Height Behind a Semi Infinite Jetty gQ°o00200008 e@ooo00en00o00009009000 007n0.908008090000000 Beach Erosion Studies ..ccovc. O9000000000 900000000000000 Beach Erosion Literature ..... s00000baD00000 FOSOOUaOODS Wahine wey Page al NO. Booster Pumping Station Future Alignment Of Coast Drag Line REPAIR BASE CUSTOMS PORT FREE PORT a Dredge Pipe Swing Span ANCHORAGE FIXED DREDGE OPERATION OF THE FIXED DREDGE AT SALINA CRUZ, MEXICO FIGURE | 400 METERS BY-PASSING LITTORAL DRIFT AT A HARBOUR ENTRANCE FOREWORD The problem of maintaining coastal harbors at locations where the rate of littoral drift is large is encountered often. Employment of fixed dredging plant to by—pass littoral accumulations across the harbor entrance has been considered at several localities in this country. Because of the large cost of initial installation and the lack of assured design eriteria, no major installation of the fixed type has been attempted in the United States. In addition to the obvious benefit to navigation which would be achiaved by intercepting littoral mterial before it can reach and form shoals in navigation channels, by—passing of the material to the dowm- drift shore would prevent costly erosion problems which sometimes result from interference with littoral processes, A relatively small fixed dredge has been employed intermittently with some success at South Lake Worth Inlet, Florida. Application of the by—passing principal by employ- ment of a conventional floating dredge has been successfully accomplished at Santa Barbara, California, where the zone of littoral accumulation is suitable for that method, and is now a routine biennial operation. The following article is abstracted from a pamphlet titled "Draga Fija" (Fixed Dredge) published in November 1950 by "Junta Directiva de Puertos Libres Mexicanos" (Translation by William H. Vesper of the Beach Erosion Board Staff). It is understood that the Salina Cruz installation described therein has not been in operation sufficiently long to es— tablish conclusively its adequacy and economic value. An early difficulty encountered, and the remedial means employed, is described in the following extract from a letter 8 May 1951, received from the Secretaria de Marina Mexico: "The fact that the arms of the dredge are not long enough to open a channel in the beach that would permit the free entrance of the sand to the dredges, the Office of Mexican Free Ports has found it necessary to install a power shovel to open this channel and bring the sand to the dredge. The scoop is hung from a cable supported by two posts lo- cated as shown on the attached plan. This scoop is moved by a motor and capstan. Before the installation of the scoop it was thought necessary to bring the sand to the dredge by some means but it was not thought that the scoop would necessarily be the solution to the problem.! ka *edpeip ayy 07 KTQOeITp TetseqeW Zutaq 04 ueeD0 eyy 4twased [ [TM puno.za -yoerq 64 UT pues JO pUNoW e844 Jo [eACWeY “piemees ZUTYOOT espeud % ° Std nthe installation complete, it will begin operating at full capacity during the present month." : The Port of Salina Cruz.is completely artificial. It consists of a repair and maintenance basin and an anchorage area separated by two large wharves on which are-six doublé warehouses. Originally, it was intended to build only one breakwater which would extend from the lighthouse bluff along the entire length of the wharves so as to protect them from the waves and wind from the south, thus furnishing an anchorage whose entrance would be to the East. While the break- water was under construction, it was observed that after stormy days. with large waves from the south, sand filled the region between the. partly constructed breakwater and the wharves, that is, the area which will be the harbor. The engineers then discovered the enormous importance of the transport of sand which was constantly being brought from the west. The direction of the breakwater was immediately changed and turned more seaward and another had to be constructed to the east so as to form the actual harbor. There was then an accretion of sand from the lighthouse to the end of the breakwater. This large area was Quickly filled with sand, covering depths of 15 fathoms. When this area was filled, sand began to enter the harbor, It has been necessary to maintain a dredge for more than forty years to remove the sand that had been deposited and is still being deposited. This work has cost the government more than 50,000,000 pesos, (at the present rate of exchange, 8.65 Mexican pesos equal one U. S. dollar), and the bay is still in the same danger, the channel shoals constantly and there are large deposits of sand inside the harbor making navigation of the channel from the harbor entrance to the repair basin difficult. In later years, dredging has been very intermittent. This has been a great factor in the loss of prestige of the port of Salina Cruz, large ships have not been able to call, thus paralyzing commerce in this region. The fact that Salina Cruz and Puerto Mexico are at the terminus of Tehuano Railroad make them strategic points and a very important means of increasing the commerce with the United States. The obstruction of the bay by sand carried from the west, remained a great engineering problem. This sand which is brought from the west is not carried by littoral currents but by the dynamic action of the waves which strike the coast at an acute angle for the entire year, in such a manner as to carry the sand up on the shore and toward the east and then back down on the inclined plane of the beach where it is caught by the surf. This continual rtse and fall, always with a force toward the east, causes the eternal voyage of the sand that moves along the whole coast to the region of Chiapas, where the wave attack is Fig. 3 Pumps of the main plant and their connecting hoses to the suction tubes. parallel to the shore and the sand ceases its journey. This continuous wave action would cause the sand to fill the whole western area between the western breakwater and the lighthouse point and on occasions it would fill the anchorage and close it completely. This same wave action which causes the continuous journey of the sand has formed bay-mouth bars in front of Juchitan, isolating thsse lakes from the sea, there remains only a small exit, maintained by the tidal cwrents and also by the rivers which flow into the lakes. In Salina Cruz Bay there is not a strong tidal current but only a weak one that flows into the harbor and this cwrent has not been able to maintain a channel. The sand which arrives from the west would obstruct the harbor and completely block the entrance. This problem was studied by the commissioners of Free Ports and after much thought it was decided to build a firmstructure near the end of the western breakwater on the side where sand ac-— cumulates and to install powerful suction pumps to take up the sand and pump it around the harbor along the wharves, to the other side of the eastern breakwater where it would be deposited on the shore. The sea will continue to force the sand toward the east as it has done up to now. Careful studies were made and capable contractors of the United States were consulted and finally enough money was obtained from the Mexican Government to complete the structure. It consists of three large sections each one being twenty meters long and twelve meters wide. These sections were placed on a line parallel with the break- water near the end of a protective rubble mound. The sections with walls one and a half meters thick and transversal partitions of the same thickness were lowered into position, using their own weight to force the sand out of the interior. This procedure was called "Chinese Pit" and we believe that this is the first time an operation of this nature has been attempted on such a large scale in either Mexico or America. This operation was accomplished, and though laborious, the sections were lowered in perfect alinement. The base of these sections rest 15 meters below low tide. On these sections, a room 60 meters long was built to house the dredge equipment which included the pumps and their motors, generators, electric motors, and pumps for refrigeration, vaccum, etc., but care had to be taken to get duplicate machinery in order to maintain a reliable operation at all times. The pumps pick up the sand from the seaward side through six suction tubes which are moved by special apparatus, up, down and to the sides like a fan. The movement of the six tubes cover the entire area along the front of the structure making a large pit 10 meters deep. Sand arriving from the west continually falls into this pit. “This is a real sand trap." The suction tubes are moved by cranes operated from a booth Fig. 4 Winches which operate the suction tubes. in the main room. The motion of the tubes, up, down, and to the sides is accomplished by three electric winches which are con- trolled by an operator stationed at the central window between the suction tubes. The sand is pumped out through a pipe that runs between the dredge and the breakwater on a straight line to the beginning of the wharves, where a sub-station has been constructed with motors and pumps the same as in the main station. The pipe runs along the wharves across the entrance to the repair area of the harbor and discharges on the shore east of the eastern break- water. A removable pipe section is used in crossing the entrance. The sand is pumped a distance of 2,200 meters. When the traffic of the port increases, it will be necessary to run the pipe on land from the sub-station around and in back of the repair basin thus eliminating necessity of uncoupling the pipe at the entrance to the harbor. The fact that this efficient dredge, which does the same work as one afloat, has its machinery in a fixed edifice induced us to nam it "Draga Fija". (Fixed Dredge). The operation of this dredge is very simple and very cheap, costing little more than 20 centavos a cubic meter to pump the sand to the beach, as against a cost of two or three pesos a cubic meter for boat dredging. A dredge operator and an electrician with their helpers are all that is needed for the operation of the dredge. The dredge will not pump all of the required sand from the bay but when this new equipment is functioning normally there will be time to check its condition. Not less than 2 or 3 million cubic meters of sand will have to be removed in order to put the port in a reasonable condition. Without the fixed dredge, the removal of the sand by floating dredges would be an impossible operation, as has been shown by 40 years experience. The fixed dredge conceived by us is progressing very well. It furnishes a new method of resolving many of the obstacles encountered in the control of littoral drift. If the expected success is obtained, there will be international reprecussions for there are many ports in the same condition, and the cause of Commerce and World production will be benefited. The dredge has cost about 10 million pesos of which 6 million was used to purchase machinery. The machinery was purchased from the Wert Conrad Company who specialize in the construction of dredges, and was paid for in sugar. The civil engineering was done by the *(punousyoeq UT JJnTQ ssnoyqyst, jo 4yooy ye Aq,ef) *uoTQonI4s —u0d suUTINp UeeDO ely WoIs esperp eyy SuTQoeZoId JeTaseq pues ¢ - Sta Fig. 6 Interior of the booster pumping station showing the pumps, motors, and intake and discharge pipes. The top pipe is the by-pass. *uotatsod uedo ut eouei4uUe uUTseq Itedei eyy ssoroe edtd eyg sutéaseo ueds durms Sul *L ° STA Obras Portuarias Company, South America, whose diligent and constant struggle against the sea brought this work to a successful end. THE MACHINERY OF THE DREDGE The machinery of the dredge consists of the following: 1. 2 Superior Diesel engines, 450 h.p. American make which operate the two dredge pumps. 2. 2 Chicago Pneumatic diesel engines with generators, 200 hep. These produce the energy to operate the auxiliary motors and winches. 3. Strong pumps for water pressure, vacuum refrigeration, lubrication, etc. 4e Bilge pumps. 5. Hlectrical distribution panel. On the outside of the engine room there are six pipes which connect to the suction tubes of the dredge. Each pump is coupled to each of these pipes by a flexible hose. Water at high pressure is injected separately into each of the suction tubes by the water pressure pump to agitate the sand and facilitate its removal. The suction tubes are on the seaward side of the dredge. The base of these tubes are fastened to large brackets which are securely attached to the wall of the structure. They can be swung in a manner that will permit the pumping of sand from the area along the front of the dredge and even from in between the tubes themselves. The vertical and lateral motion of the tubes are controlled by cables which run in front of the operators booth and along the roof of the main room. There are three winches for each tube or a total of eighteen winches. The movement of each suction tube is controlled electrically by an operator stationed at a window between each pair of tubes. From two discharge tubes of the dredge, a pipe line runs direct to the sub-station located at the foot of the wharves, It then continues along wharves cross the entrance to the repair basin and terminates on the seaward bank of the eastern breakwater. At the repair basin entrance there is a draw which can be opened for the passage of ships. 11 12 General view of the pipe bridge in operating position. Fig. 8 *pesperp eq 07 [eT Jequ Jo yUNoWe eYy4 eoNpar pue 4JTIp [e1099TT qselie 04 JJNTQ ssnoy_qUstT ey. JO 4OOT 4e UOTZONAYGSUOD JepuN A49QeP 13 SUB-STATION The sub-station (booster pumping plant) was built to aid the dredge pumps in moving the dredge material. At the sub-station there are two pumps each run by a 450 h.p. electric motor similar to those on the dredge. Aliso at the sub-station there are duplicate pumps for refrigeration, fuel, etc. The motors which operate this auxiliary equipment are run by electricity supplied at the rate of 40 h.p. at 400 volts through a transmission line from the dredge. Three #00 copper Wires are used for the transmission line. All of the pipe is 18 inch diameter steel and is run exposed 50 that it may be inspected at any time. In the beginning the practica- bility of laying the pipe along the bay and crossing the repair basin entrance by means of a siphon was considered. This however was discarded in favor of the present method due to the possibility of deteriation of the submerged pipe. At the foot of the lighthouse bluff, west of the fixed dredge, a jetty is being constructed at the least possible cost. With it, it is hoped to impound the littoral drift from the west, forming a bank of sand that will not have to be dredged, thus prolonging the useful life of the Draga Fija. Eventually the sand that collects at the end of the jetty will be in a depth less than five or six meters. When this occurs, the action of the surf will be capable of lifting the sand and starting it on its eastward journey. This is the only sand that the fixed dredge will have to pump. It has been calculated that a jetty five or six hundred meters long will impound sand for two hundred years. However, when a beach is formed near the end of the jetty surf action will cause the sand to be transported to the east. This is the limiting point of the jetty's effectiveness. As yet it is not known whether or not it would be more economical to construct such a jetty or to pump sand that would be trapped by it, nor is it known which method would be the more effective. The answer to these questions can be resolved only through experience. For the present the littoral drift will be allowed to go directly to the dredge. However, it would be well to consider the construction of this jetty for though it might cost a little more to retain the sand than to pump it, the jetty would prolong the life of the dredge. In either case, whether by the joint.function of the jetty and the dredge or by the operation of the dredge alone, sand will be pre- vented from entering the Bay of Salina Cruz. 14 CALCULATION OF DIFFRACTED WAVE HEIGHT BEHIND A SEMI INFINITE JETTY by C. Carry and E. Chapus La Howille Blanche, Jan-Feb 1951 FOREWORD Wave diffraction is the phenomenon in which water waves are propagated into a sheltered region formed by a breakwater, island, or similar barrier which interrupts a portion of an otherwise continuous wave train. The ability to predict wave diffraction obviously has important application in the planning and design of harbor works where wave action is involved. A theory of the diffraction of water waves passing a breakwater has been adapted from theories of physical optics. Putnam and Arthur investigated the theory ex-— perimentally for deep water waves approaching a break- water with angles of incidence of 45°, 90°, and 135°, measured at distances varying from 3.38 to 17.85 wave lengths from the breakwater and compared results both with the somewhat complicated rigorous theory and a Simplified solution employing approximations (Trans— actions, American Geophysical Union, Vol. 29, No. 4, August 1948). The application of diffraction theory to water waves passing through a breakwater gap, for both deep and shallow water waves in uniform depth, has been investigated experimentally by Blue and Johnson. (Transactions, American Geophysical Union, Vol. 30, No. 5, October 1949). Experiments reported in the follow- ing translation supplement the work of Putnam and Arthur, covering diffracted shallow water wave heights along the breakwater itself in the sheltered region, for angles of incidence corresponding to those tested by Putnam and Arthur. This article has a double objective: first, to translate into curves or asymptotic formulae(1) results derived by the method developed by Messrs. Putnam and Arthur for the calculation of the diffracted wave height behind a semi-infinite jetty; second, to report certain experiments which had as their objective the verification of this theory. 15 It should be recalled that the theory consists in applying the rigorous theory of diffraction of light, or of sound, behind a semi-infinite screen to the diffraction of a water wave in constant depth behind a semi-infinite jetty; if the application is limited to the terms of the first order for this latter problem the equations and the limiting conditions are in effect the same for the two cases. The ratio of the amplitude of the diffracted wave at a polar coordinate point (r, 9) to the amplitude of the incident wave is given by the modulus of the following complex function: — { 8% cos(a-e) F (r,0) = f(u,)e L ay See cos (8,46) ae if (Beko where x ! ode 2, oe ~ip eS @ v eh) = —\ [82 sin G — 6 AL IL 2 Up - —\[& sin +e UE 2 Note that F(r,@) may also be written in the form F(r,0) =0(7r, @)e’ 6M whe re e (r,@) is the modulus of the function F and determines the re- lative height of the wave and ¢(r,0), the argument of the function F, determines the plan of the wave distribution, or in other words, ¢(r,0) = const. is, in (1) Putnam and Arthur: Diffraction of water waves by breakwaters. Trans. Am. Geophy. Union, Aug 48). Note that this method of calcula- tion was proposed previously by Mr. Iarras in the French publication "Travaux" for June 1942. 16 polar coordinates, the location of points of equal phase. Our pur- pose is to calculate the wave heights, that is to calculate Qe . It is convenient to define the geometric shadow as the zone situated behind the jetty corresponding to the geometric shadow of optics. I. GRAPHS Figures 1, 2, and 3 show three series of curves corresponding to the following wave incidences: 1. direction of propagation normal to the jetty, i.e., normal incidence; 2. direction of propagation makes an angle of 45° with the jetty; 3. direction of propagation makes an angle of 135° with the jetty. For each angle of incidence we have drawn curves showing the distribution of wave height on the radius vectors drawn from the end of the jetty and making a certain angle with the direction of the jetty. The curves are draw to r = 51, beyond that one my utilize the asymptotic formulae. It is necessary to distinguish several zones; a.) within the geometric shadow, (i.e., 9<@ ) the height decreases in a uniform fashion as one moves along the radius vector. One my interpolate without difficulty between the different curves, b.) outside the geometric shadow, (i.e., 0< O< 7m), the height presents a series of mxima or minima, as functions of r/L and 9. These mxima and minima may be very sharp and very close for certain values of the angle 0; for other values they are not so evident or are quite separated. As an example of the first case we may cite the curve corresponding to a value of @ = 56° for an incidence of 45°; as an example of the second case we my cite the curve correspond- ing to 0 = 67° for an incidence angle of 45°. For these reasons the drawing of the curve is very laborious and presents great difficulty, and for the same reason it is impossible to interpolate between curves. It may be states however, that in the neighborhood of the origin there exists a minimum which may be very sharp. When r increases indefinite—- ly the ratio of the amplitude to the amplitude in the open sea approaches unity. ce) on the geometric shadow the amplitude decreases regularly to a value 0.5; Ibi “Aq9ef & putyeq eAem & Jo UCTIOeITIJIG °T emsty epniijduy 434044 dae PDNLUGWI7 Amplitude Deep Water Amplitude ce Jetty Origin of angle Direction of propagation Figure 2. Diffraction of a wave behind a jetty. Amplitude7- wo : Sea Oy i Amplitude A) 90 Figure 3. Diffraction of a wave behind a jetty. 19 d.) on the prolongation of the jetty the height ratio is almost unity. Il. ASYMPTOTIC FORMULAE 1. In the geometric shadow one may substitute for f(u) the following equivalent expression when Uy and Uy are smaller than -2 1 —tr(l4g+urzy) Placa = Tue or ment ve at rr (1/q+ ue) a i Sana 3 cade fe Piss ame fF sin 9 + 6. Age 2 In this case ~ 7 47r cos (8, — @) f(%)e d ; A —~¢ £22 cos(a +6) f (42)e have the sams phase; the relative height then becomes: Bon et Pali sale i ps SN 4r ff Sin GarO sin 2=@ ib 2 2 (3) Along the jetty where 9 = O one has BO es ath 1 P 0 FG Zia a Mis (4) 2. On the geometric shadow, where u, = 0, then f(u,) = 1/2, and starting at uo <— 2, the relative height of the wave is furnished by the modulus of the complex expressfon = BE, A =0.5+ 1 e 4 4n Ve sin @, 3e. Outside the geometric shadow: (a) when u, is greater than 2, one may write Be ed ne) is, eae 20 (b) when u,; is greater than 2 and up less than -2 the amplitude has as its asymptotic value the modulus of the following complex expressions cos_2 Sin Se SS BURRS i) HE cos @ — COS, =) ao bs |s In this zone it does not appear that the variation of the second term of A can be greater than + 0.16. (c) when uj is smaller than 2 it is necessary to expect in general a maximum of amplitude on the curve 6 © Oc W963 By and a minimun on the curve . [_——2 Ove 0.924+2yY the axis Ox being the perpendicular of the polar angle 8, and the axis Oy the perpendicular of the polar angle Q@ + eS We must now examine in what measure the preceding theory re— presents the real phenomena. In the article cited above Messrs. Putnam and Arthur give the results of experiments made at the University of California. They were conducted in deep water, i.e. ina depth greater than L/2 and they include angles of incidence of 45°, 90° and 135°; the height of the diffracted wave was measured along parallels to the jetty and compared to the corresponding theoretical curve. These parallels were Situated at distances from the jetty varying from 3.38L to 17.85L, with however, a predominance for the larger distance. The agreement was good between thsory and experinent within the geometric shadow. In a thesis submitted to the Faculty of Science of Grenoble, in July 1949, and prepared in the Laboratoire Dauphinois d!Hydraulique Neyrpic, Mr. Dixon studied the same problem for normal incidence in a zone which had not been studied by Messrs. Putnam and Arthur. The lines on which Dixon measured the height were situated at distances from the jetty varying from 0.41%, to 3.35L. Furthermore, the study was conducted in shallow water, i.e. in a depth smller than one-half wave length (depth of 12 cm. for a wave length of 60 cm). The agreement with theory was good in the interior of the geometric shadow and in the neighborhood of the jetty end. Finally, in the course of studies on diffraction now under way in the Eaboratoire Dauphinois d'Hydraulique Neyrpic we have made measurements along the jetty itself for incidences of 45°, ails Ob 6 8 Z 9 S "Aqqgel ayy suoTe oAcM pepoerTsFtp eyy JO opnqttdwe eatyepsey °7 a|InsT a OPN HOW JHO/ daeq apnys/duiy 02'0 22 90° and 135° with the objective of verifying Equation 4. The test basin, the same which was utilized by Mr. Dixon, was 25 meters (82.5 feet) long by 4 meters (13.2 feet) wide, and 0.5 meter (1.65 feet) deep. Since mritime ports are established always in relatively shallow depths, we limited ourselves to the case of diffraction in shallow water. Although very simple in appearance, this condition necessitates the use of a basin with an absolutely horizontal bottom, which was not easily obtained. It is known, in fact, that in shallow water the wave refracts and reflects in relation to the bottom that it encounters, The modifications in propagation which result may cause, sometimes at large distances from their original topographic cause, notable wave reinforcenent and interference resulting in augmentation or diminution of the instantaneous height. We think however, that we have limited this cause of error because the difference in elevation between any two points of the bottom of the basin was, on the average, of the order of a 0.5 mm. and never exceeded 1.5 mm. The apparatus used in the basin was the same as that used by Mr. Dixon. The wave generator was a three-—section paddle driven by a 2 HP AC motor and gear box. Absorbent beaches of round gravel were used to surpress reflection at the basin end and along the wall of the basin sheltered by the jetty. A straight jetty with vertical walls was milt from one of the jongitudinal walls of the basin at a distance of 9 meters (29.7 feet) from the wave generator, leaving an opening of 1.2 meters (3.96 feet) minimum width. To avoid reflection of the incident wave on the jetty an absorbent beach was built in front of its; a flat guide of sheet mtal 0.5 meters (1.65 feet) long, placed perpendicular to the extremity of the jetty avoided any lateral reduction of the wave penetrating into the opening. Wave heights were measured by means of a resistance gauge; the variations of voltage at the electrodes of the sounding gauge as a function of the depth of immersion of the points of the electrodes were registered photographically through the medium of a cathode oscillograph. The results obtained with a wave 76 cm. long in a depth of water of 13 cm. are represented by points on Figure 4. The curves of this figure correspond to equation 4 for the angles of incidence Q@, = 45°, 90°, and 135°. The portions of the curves that are dotted correspond to the region where hy mann L 2 sin® $e i.e. where the approximation of Equation 2 is no longer valid. The curves give values that are greater than true values in this region. 23 Note that the preceding theory concerns a semi-infinite screen, infinitely thin, and perfectly reflecting; on our model the problem studied differed slightly from the theoretical problem but was nevertheless very nearly the same in the zone where we have made our measurements. aT sas reac Note: The curves given in this paper were calculated before the appearance of the approximate theory of diffraction developed by Mr. Lacombe in the Hydrographique Annalsx. This fact explains why we have not shown the corresponding curves of which the interest is obviously apparent. Sn * Editors Note: Note sur la diffraction de la houle en incidence normale, Henri Lacombe, Annales Hydrographiques Paper No. 1363, 1949. Translated by Dr. Martin A. Mason, Beach Erosion Board. 24 BEACH EROSION STUDIES The principal types of beach erosion control reports of studies at specific localities are the following: a. Cooperative studies (authorization by the Chief of Engineers in accordance with Section 2, River and Harbor Act approved on 3 July 1930). b. Preliminary examinations and surveys (Congressional authorization by reference to locality by name). co Reports on shore line changes which may result from improvements of the entrances at the mouths of rivers and inlets (Section 5, Public Law No. 409, 74th Gongress). d. Reports on shore protection of Federal property (authorization by the Chief of Enginesrs). Of these types of studies, cooperative beach erosion studies are the type most frequently made when a community desires investi- gation of its particular problem. As these studies have greater general interest, information concerning studies of specific localities contained in these quarterly bulletins will be confined to cooperative studies. Information about other types of studies can be obtained upon inquiry to this office. Cooperative studies of beach erosion are studies made by the Gorps of Engineers in cooperation with appropriate agencies of the various States by authority of Section 2, of the River and Harbor Act approved 3 July 1930. By executive ruling the cost of these studies is divided equally between the United States and the co. operating agency. information concerning the initiation of a co- perative study may be obtained from any District Engineer of the Gorps of Engineers. After a report on a cooperative study has been transmitted to Congress, a summary thereof is included in the next issue of this bulletin. Summaries of reports transmitted to Congress since the last issue of the Bulletin and lists of completed co~ operative studies and those now in progress follows: SUMMARIES OF REPORTS TRANSMITTED TO CONGRESS QUINCY SHORE, MASSACHUSETTS The area studied is located in the City of Quincy, Massachusetts, at the head of Quincy Bay in Boston Harbor, 6 miles southeast of the 25 City of Boston. It comprises the southerly 6700 feet of the publicly owned Quincy Shore Reservation which is under the jurisdiction of the Metropolitan District Gommission. The Reservation comprises a marrow public beach which is generally undér water at high tide, seawalls and riprap shore protection, parking areas, and a boulevard. The shore of the study area is lined with concrete seawalls except at ths southerly end where 400 feet of riprap have been placed. The beach consists of coarse sand and gravel above mean tide level and mud below that elevation. The offshore area is very flat and shoal, ex- cept in the dredged yacht channel, and at low tide large calm flats and other areas are exposed, The land immediately adjacent to the boulevard which traverses the reservation is used for commercial purposes. The adjacent area is a densely populated, urban, middle class residential area which extends back across the City of Quincy. Two yacht clubs, the Wollaston Yacht Club and the Squantum Yacht Club are located on the bay sise of the reservation boulevard. Hach club maintains a pier which projects 350 feet into the bay to the head of a yacht basin and channel which are maintained by the Commonwealth of Massachusetts. Free public parking is provided along the entire length of the beach on a parking strip between the highway and the seawall. Bus service is provided within 800 feet of the beach by a system serving the area south of Boston and connecting with the Metropolitan Transit Authority system of Boston. Ths beach is open to the public free of charge. There are no public bathhouses in the study area, but ex- tensive use is made of the beach by bathers from nearby homes and by those who travel to the beach attired in bathing mits. The daily summer attendance is estimated to average 1000, Sunday and holiday attendance 3000 to 5000. The existing beach in the study area was artificially developed and resulted from the realignment of the shores of Quincy Bay by construction in 1905 of a highway over beaches and marshes. The highway was built on an embankment, the seaward face of which within most of the length of the study area is now protected by a low concrete stepped seawall which was constructed in 1926. The present beach is the result of wave and tidal action on the highway embank- ment. The stepped seawall is too low to provide adequate protection to the highway and adjacent property and is, furthermore, presently in need of extensive repairs. In 1948 a reinforced concrete parapet wall was added to the top of the northerly 1130 feet of the stepped seawall, The parapet wall has since been extended about 1000 feet in a southerly direction. In furtherance of the general purpose of the study, specific problems at Quincy Shore Beach were found to require determination of the most suitable measures to provide adequate protection to the 26 highway and adjacent property from high tides and storm wave action and to provide a more suitable recreational beach. The division engineer considered the desires of the cooperating agency, studied the existing structures, the sources and movement of beach material, the changes in the shore line and offshore bottom, the effects of winds and storms, developed plans for protecting and improving the shore of the study area, and made an economic analysis of proposed new protective and improvement construction for Quincy Shore Beach. He found that prospective benefits warrant construction of these measures and that the public interest therein justifies Federal participation to the extent of one-third of the total cost of the recommended new work, in accordance with the policy established by Public Law 727, 79th Congress. The division engineer recommended, subject to certain conditions, adoption of a project authorizing Federal participation in an amount equal to one-third of the first cost of protecting and improving the shore of the Metropolitan District Commission Quincy Shore Reserva— tion, Massachusetts, by: a. Placing approximately 126,000 cubic yards of sand and gravel, and 221,500 cubic yards of sand on the beach between Hovey Street, and Rufe's Hummock Sea Wall, a distance of 8500 feet, to provide a backshore elevation of 15.0 feet above mean low water; b. Constructing a concrete-encased steel sheet-pile bulkhead with a top elevation of 18 feet above mean low water between the parapet wall, near Hollis Avenue, and the National Sailor's Home Hill Sea Wall, a distance of 4750 feet; ec. Constructing a concrete sea wall, with a top elevation of 19.2 feet above mean low water, in extension of the existing parapet wall to high ground at Billings Street, a distance of 325 feet: d. Constructing two impermeable stone groins each 350 feet long, with tops generally 2 feet above the highest adjacent fill, one 200 feet north of the Squantum Yacht Club, the other 200 feet south of the Wollaston Yacht Club; and e. Constructing a culvert at Sachem Creek, and extending existing drains across the beach to discharge seaward of the recommend— ed fill. The Beach Erosion Board carefully considered the report of the division engineer and concurred generally in his conclusions and recommendations, subject to the following comments. 27 The beach under study, located at the head of Quincy Bay is = partially protected against wave action during the dominant north-~ east storms by islands and by extensive shoal areas in front of the beach. Littoral currents are relatively weak in the study area. The shore consists of a highway embankment located over former beach and’ marsh areas. The seaward face of this embankment along most of the length of the study area is protected by a low stepped concrete wall which is in need of repair. During storms accompanied by extreme high tides, storm waves break over this wall flooding the highway and at adjacent low-lying residential areas, Fronting the seawall is a narrow public beach which is mostly under water at high tide, The lowering of this beach by erosion has exposed the toe of the seawall to incipient undermining at a number of points. The water is now © polluted by raw sewage discharged into Boston Harbor. However, sewage treatment plants now under construction or proposed, will materially reduce and probably ultimtely eliminate the existing pollution. In spite of the present undesirable characteristics of the existing beach, it is now used extensively as a recreational bathing beach. ast The division engineer recommended the construction of a concrete encased steel sheet pile bulkhead immediately seaward of the existing seawall throughout the greater portion of its length and the back-— fill of the space between the two structures to an elevation of +15 feet. No provision was made for tie-backs, presumably because the sand fill seaward of the bulkhead will also have an elevation of +15 feet or 3 feet below the top of that structure. The Board nevertheless believed that tie-backs should be included in the bulkhead design as a measure of reasonable prudence and recommends that they be so included when the detailed design of the structure is undertaken. The artificial sand fill proposed by the division engineer will raise and widen the beach thereby constituting a material improvement of the beach as a recreational facility. The Board was of the opinion that this fill is also an essential part of the plan for the protection of this shore and the installations immediately behind it. Without this protective fill the proposed bulkhead would be in- adequate to withstand the direct attack of storm waves. The alterna-— tive would be the construction of an expensive seawall with a foundation level considerably below sea level and with adequate pro- vision for protection at its toe. Such a seawall would probably hasten the present processes of erosion which would in turn result in the ultimate loss of the existing beach with consequent increased cost of maintenance of the wall itself. The Beach Erosion Board noted that the recommended plan includes two impermeable stone groins adjacent to the yacht club area. The stated purposes of these groins are to maintain a steeper beach slope in the area between them, and preyent the movement of beach mterial 28 into the yacht club area and the dredged yacht basin. The Board was of the opinion that these groins, as designed, will be inadequate to accomplish these purposes in their entirety, and that groins properly designed to accomplish the intended purposes would of necessity be larger and more costly. The Board recommended that the proposed groins be eliminated from the plan as unnecessary and undesirable features. The Board recognized that this elimination will require that the shore line in the immediate vicinity of the yacht clubs be advanced to correspond with the proposed beach al- ignment throughout the remainder of the area. This change will eliminate the cost of the groins but will necessitate an increase in the length of the Sachem Creek conduit and an increase in the Quantity of sand fill. The net effect will be an increase in the total estimated cost of the plan from $849,000 to $897,000. The Board was of the opinion that the recommended plan of pro— tection and improvement as modified by the above comments will pro- vide needed protection to the shore of the publicly owned Metro— politan District Commission, Quincy Shore Reservation and adjacent privately owned property and will promote and encourage une heaith— ful recreation of the people. In accardance with existing statutory requirements, the Board stated its opinion that; a. It is advisable for the United States to adopt a pro— ject authorizing Federal participation in the cost of protecting and improving the publicly owned shore of the Metropolitan District Gommission Quincy Shore Reservation, Massachusetts. b. The public interest involved in the proposed measures for the publicly owned shores is substantial. It is associated with prevention of direct damages to public property, increased tax revenue resulting from increased earning power of adjacent property and recreational benefits to the public; co The share of the expense which should be borne by the United States is one-third of the first cost of the proposed work for publicly owned shores. The estimated amount of this share is $299,000. The Board recommended that a project be adopted by the United States authorizing Federal participation by the contribution of Federal funds in an amount equal to one-third of the first cost of protecting and improving the shore of the Metropolitan District Gommission Quincy Shore Reservation, Massachusetts, bys a. Placing approxi mately 126,000 cubic yards of sand and gravel, and 253,000 cubic yards of sand on the beach between Hovey Street and Rufe's Hummock Sea Wall, a distance of 8500 feet, to provide 29 a back shore elevation of 15 feet above mean low water; b. Gonstructing a concrete-encased steel shest—-pile bulk-— head with a top elevation of 18 feet above mean low water between the parapet wall, near Hollis Avenue, and the National Sailor's Hom Hill Sea Wall, a distance of 4750 feet; ce. Constructing a concrete sea wall with a top elevation of 19.2 feet above mean low water, in extension of the existing parapet wall to high ground at Billings Street, a distance of 325 feet; d. Constructing a culvert at Sachem Creek, and extending existing drains across the beach to discharge seaward of the recommended fill. Federal participation was recommended subject to the conditions that the Commonwealth of Massachusetts will: a. Adopt the project named herein; b. Submit for approval by the Chief of Engineers prior to the commencement of work, the plans and specifications for the project and also the arrangements for prosecuting the work. co Assure maintenance of the protective and improvement measures during their useful life as my be required to serve their intended purposes: d. Provide at its own expense, all necessary lands, ease- ments, and rights—of-way; e. Hold and save the United States free from all claims for damages that may arise either before, during, or after pro- secution of the work3 f. Assure that water pollution that would endanger the health of bathers will be eliminated; g. Assure continued public ownership of the shore and its administration for public use only. The estimated amount of Federal participation in accordance with the foregoing recommendations is $299,000. 30 REVERE BEACH, MASSACHUSETTS Revere Beach is located in the Gity of Revere, 5s miles north- east of the City of Boston. It is a barrier beach which extends a distance of 34 miles northward from Roughan's Point to the mouth of Saugus River, separating the Lynn marshes from Broad Sound. The southern half of Revere Beach has been developed as a large amusement area; the northern half as a residential area. The shore is publicly owned and comprises the Metropolitan District Commission Revere Beach Reservation for a length of 3 miles between Point of Pines at the north end and Roughan's Point at the south end. The reservation con- sists of the beach, a wide boulevard, sidewalks, a series of seawalls, pavilions and retaining walls along the seaward edge of the boulevard. Excellent highways and the Metropolitan Transit Authority transporta— tion system connect the study area with all sections of Metropolitan Boston. Revere Beach is open to the public without charge. A nominal fee is charged for use of the public bathhouse. The daily attendance at Revere Béach during the summer season is estimated at 150,000 to 200,000, Sunday and holiday attendance at 400,000 to 500,000. Point of Pines, north of the Revere Beach Reservation, is a densely populated, permanent residential area bounded by a paved town road paralleling the privately owned shore. The road is partially protected by miscellaneous walls, bulkheads and riprap revetments. Roughan's Point, south of the Reservation, is a summer and year-round residential area protected by a sea wall constructed by the Massachusetts Department of Public Works. The beach fronting the Metropolitan District Commission Reserva- tion consists of firm sand with deposits of stones in the backshore area. The width of beach above the mean high water line varies from 50 feet to 100 feet for most of the length and increases to more than 200 feet at the ends. The position of the beach is stabilized by Roughan's Point, Cherry Island Bar, Oak Island, and the Saugus River. Although the beach is exposed to waves from the open ocean with directions of approach between southeast and east, direct wave attack during the dominant northeast storms is prevented by Nahant, Little Nahant and the tombolos connecting them to the minland. Waves approaching the coast from the northeast reach Revere Beach only after being refracted around the outer end of Nahant. Shore protection works along the coast have cut off all onshore sources of beach building materials. Since 1900, the date of the earliest profile surveys, accretion has occurred along 2000 feet at the southerly end, erosion along the remaining 12000 feet of the Reservation. Since 1932, stones have appeared on the beach in large quantities inter— fering with recreational use of the beach. During severe storms seawalls have been overtopped and the adjacent road flooded, but structures along the beach have not, as yet, suffered great damege. Gontinued erosion will, however, endanger existing protective structures. BL In furtherance of the general purpose of the study, specific problems at Revere Beach were found to require determination of the most suitable measures for protecting and improving the beach in the Metropolitan District Commission Reservation and for preventing flooding in the Point of Pines area. The Division Engineer considered the desires of the cooperating agency, determined the character, source, and movement of beach material, studied the existing structures, the changes in the shore lines and offshore bottom, the effects of winds and storms, developed plans for protecting and improving the shore of the area, and made an economic analysis of proposed new protective and improve- ment construction for the publicly owned shore in the study area, He found that the estimated benefits warrant construction of certain masures for the protection and improvement of the publicly owned shore and that the public interest therein justifies Federal parti- cipation to the extent of one-third of the total cost of recommended new work, in accordance with ene policy established by Public Law Weis 79th Congress. The Divisien Engineer recommended, subject to certain conditions, adoption of a project by the United States authorizing Federal parti- cipation in an amount equal to one-third of the first cost of pro= tecting and improving the beach of the Metropolitan District Commission Revere Beach Reservation for a length of 13,700 feet between Northern Girecle and a point near Shirley Avenue by placing theraen §22 ,00%) cubic yards of sand fi11 te provide a backshore elevation of 13.0 feet above mean low water, except at the northern end of the beach where local conditions require backshore elevations between 16.8 and 17,3 feat above man low water. The Division Ingineer also recommended that the Commonwealth of Massachusetts, if it considers the work justified, (a) construct a concrete-encased steel sheet pile sea wall having a top elevation of 18.0 feet above mean low water in tha Point of Pines area between the General Edwards Bridge and Northern Circle, a distance of 4500 feet; (b) periodically level the top of the stone ridge at the southerly end of Revere Baach Reservation when it reaches an elevation higher than that of the adjacent road; (c) seal openings in the existing Roughan's Point sea wall and extend it to Eliot Gircle. Federal contrition to items (b) and (¢c) would not be in accordance with the policy stated in Public Law 727, 79th Gongress. tudy of item (a), not originally included in the scope of the investigation, was not sufficiently extensive to determine the extent of Federal aid to be recommended in accordance with existing statutes. The Division Engineer was of the opinion that Federal participation in this item that might be recommended as a result of further study would not exceed 9 per cent of the total cost, The Beach Erosion Board carefully considered the report of the Division Engineer. It concurred generally in his conclusions and recommendations. The beach under study is protected from the dominant storm waves by Nahant, Little Nahant and the tombolos connecting them to each other and to the mainland. The publicly owmed portion, the Metropolitan District Commission Reservation, has not yet suffered severe storm damages, although the highway is occasionally washed over. The recent history of the beach of the Reservation indicates a greater amount of erosion than accretion and interference with recreational use of the beach by exposure of increasing numbers of stones on the backshore areas. Continued erosion will endanger many structures, but, since the rate of erosion is relatively low, only a small portion of the exist- ing structures are in imminent danger. The natural rate of supply of beach material is insufficient to permit its entrapment to create a stable beach of satisfactory composition. The Board therefore con— curred in the plan of the Division Engineer to provide protection and improvement of the beach by artificial placement of sand fill. The improved wider beach will provide more effective shore protection. Furthermore, as the backshore beach areas are stony and unsatisfactory for recreational use, the recommended wider and improved beach will provide, in addition to other benefits, very large recreational benefits which provide economic justification for the wrk. The Board concurred in the opinion of the Division Ingineer that pro- spective benefits warrant the proposed expenditure for an improved protective beach. The Board noted that the volume of sand necessary to maintain the artificial fill in its original condition was estimated by the Division Engineer at 5,000 cubic yards per year. The Board believed that this figure will be found to be too small in practice and there- fore that the cost of maintenance will probably be somewhat higher than estimated in the report. However, it is apparent that no reason- able increase of mintenance cost from this cause will appreciably disturb the present economic justification. In accordance with existing statutory requirenmnts, the Board stated its opinion that: a. It is advisable for the United States to adopt a pro— ject authorizing Federal participation in the cost of protecting and improving the publicly-owned shore of the Metropolitan District Commission Revere Beach Reservation, Massachusetts; b. The public interest involved in the proposed measures for the publicly owned shores is substantial. It is associated with prevention of direct damages to public property, increased tax revenue resulting from increased earning power of adjacent property, 33 and recreational benefits to the general public. Private benefits will also result in lesser amount from increased earning power of adjacent lands; c. The share of the expense which should be borne by the United States is one-third of the first cost of the proposed work for publicly owned shores. The estimated amount of this share is $337,300. The Board recommended that a project be adopted by the United States authorizing Federal participation by the contribution of Federal funds in an amount equal to one-third of the first cost of works for the protection and improvement of the shore of the Metropolitan District Commission Revere Beach Reservation, Massachusetts, con-— sisting of the placement of 522,000 cubic yards of sand fill between Northern Circle and Profile 13 near Shirley Avenue, a distance of about 13,700 feet, to provide a backshore elevation of 18.0 feet above mean low water, except at the northern end of the beach wheres local conditions require backshore elevations between 16.8 and 17.3 feet above mean low water. Federal participation was recommended subject to the conditions that responsible local interests will: a. Adopt the project named herein; b. AsSSure maintenance of the improvement during its use- ful life as may be required to serve its intended purpose; c. Provide, at their own expense, all necessary lands, easements, and rights—of-way; d. Hold and save the United States free from all claims for damages that may arise either before, during, or after pro- secution of the works e. Assure that water pollution that would endanger the health of bathers will not be permitted; f. Assure continued public ownership of the shore and its administration for public use only. The estimated amount of Federal participation in accordance with the foregoing recommendations is $337,300. Opes pide rate SRS LYNN — NAHANT BEACH, MASSACHUSETTS The beach referred to herein as Lynn-Nahant Beach comprises portions of the shore in the towns of Swampscott and Nahant and the City of Lynn, a total length of about 2-3/4 miles. The area is located 7-1/2 miles north of the main entrance channel to Boston Harbor and 9 miles northeast of the City of Boston. Th shore is publicly owned between the privately owned headlands, Blaney Rock and Little Nahant, respectively at the north and south ends of the beach. The publicly owned reservations are under the control of the Metropolitan District Commission. Good roadsfollow the shore for the length of the study area. Public parking areas have been provided. All parts of the beach are open to the publie without charge. A nominal fee is charged for use of the public bathhouse. The Swampscott and Lynn portions of the area are extensivély developed for year-round residential use. The northern section of the area studied is the mainland head- land consisting of moderately high bluffs composed of a thin veneer of till over bed rock. Rock outcrops occur at Blaney Rock and Red Rock in this section. The southern end of the area is the former island of Little Nahant, which also consists of bluffs of till with rock outcrops. Between these headlands a narrow tombolo has been formed, which separates Lynn Harbor from Nahant Bay, the latter being a broad open arm of the Atlantic Ocean. The tombolo averages about 350 feet in width and its crest is 15 to 20 feet above mean low water. The narrow beaches fronting the headlands on the miinland and Little Nahant are generally of hard-packed sand with some stones and boulders. Nahant Beach on the tombolo is composed generally of sand on the flat foreshore, with con~- siderable stone backed by low dunes on the backshore. The headlands on the mainland and on Little Nahant have been protected by substantial seawalls. Most of the wall on the mainland was constructed 40 or 45 years ago and is now in poor condition. Erosion of the beach at the base of the wall has necessitated the construction of toe walls to prevent undermining.. Although the tombolo between the mainland and Little Nahant has been reasonably stable, a storm in 1945 eroded the dunes where they were not pro- tected by riprap revetment. In furtherance of the general purpose of the study, specific problems at Lynn—Nahant Beach were found to require determination of the most suitable measures for insuring the stability of the existing mainland seawalls, for protecting and improving the tombolo beach in the vicinity of the bathhouse and for protection of the tombolo from erosion and the possibility of breaching. 35 The Division Engineer considered the desires of the cooperating agency, determined the sources and movement of beach material, the changes in the shore line and offshore bottom, the effects of winds, storms and of existing structures, developed plans for protecting and improving the shores of the area, and made an economic analysis of proposed new protective and improvement construction for Lynn-Nahant Beach. He found that prospective benefits warrant construction of these measures and that the public intsrest therein justifies ‘ Federal participation to the extent of one-third of the total cost of recommended new work, in accordance with the policy established by Public Law 727, 79th Gongress, o The Division Engineer recommended, subject to certain conditions, | adoption of a project by the United States authorizing Federal participation in an amount equal to one-third of the first cost of protecting and improving the beach between Woodbury's Point and the dune on Nahant tombolo, a distance of about 2,600 feet, by placing 172,000 cubic yards of sand thereon to perce a ‘sepleehnone elevation of 18 feet above mean low water, and constructing a stone mound having a top elevation of 18 feet above mean low water along the tombolo from the improved beach to Little Nahant, a distance of 6,250 feet.. The Division Engineer also recommended a plan for insuring the .. stability of existing seawalls on ths mainland shore between Blaney — Rock am Wocdbury's Point, consisting of the construction of steel pile cut-off walls at those places where tue walls do not extend below elevation 6 feet above mean low water, and refacing the exist- ing wall. The entire cost of this maintenance work should be borne . by local interests as it is not eligible for Federal assistance under the policy established by Public Law 727, 79th Congress. The Beach Erosion Board carefully considered the report of the Division Engineer. It concurred generally in his conclusions and, recommendations » The beach under study, lying at the head of Nahant Bay, is pro- tected by the headlands at Philips Point and those of Nahant and Little Nahant. As a result, the beach is reasonably stable. Material is moved by wave action back and forth within the area, but the rate of loss of material from the area is low. The headlands have been protected by seawalls, most of which are 40 to 45 years old and now in poor condition, The Beach Erosion Board is of the opinion that the storm damage to these conerete seawalls described by the Division Engineer can be attributed largely to the deteriorated condition of concrete 40 to 45 years old. Mcedern seawalls of concrete properly designed and constructed will certainly withstand similar exposure to wave action with little or no damege. In connection with the recommendation of the Division Engineer for armoring the existing concrete wall between Blaney Rock and 36 Woodbury's Point, the Board believed that although it may not be the most economical, reinforced concrete facing is the most satisfactory, and feasible method. Gareful treatment will be required to avoid infiltration of water, either from wave action or precipitation, into any exposed joint. Largely as a result of protection of the headlands against erosion there is now no apparent natural source of new mterial to replace losses. In view of the lack of natural replacement material, breach- ing of the tombolo is possible, if low places are allowed to develop where storm waves can wash across the tombolo. The Board therefore concurred in the plan of the Division Engineer to build up the crest of the tombolo to elevation 18 feet above mean low water. The Board noted that the recommended method of protection of the shore in the vicinity of the Metropolitan District Commission bath- house results in an improved beach. The Board concurred in the opinion that the improved wider beach will provide more effective shore protection. As the backshore beach area in the vicinity of the bath— house is stony and unsatisfactory for recreational use, the proposed wider and improved beach will provide, in addition to other benefits, recreational benefits which increase the economic justification of the work. The Board also noted that the benefits evaluated for the pro- tection and improvement of Lynn-Nahant Beach apply principally to the shore from Woodbury's Point to and including the recreational beach in the vicinity of the Metropolitan Bistrict Commission bathhouse. However, the Board believed that the unevaluated benefits consisting of prevention of indirect damages that would result to the Little Nahant and Nahant area from breaching of the tombolo amply justify the proposed stone mound construction from south of the bathhouse to - Little Nahant, the annual charges on which are estimated at $4,860. In accordance with existing statutory requirements, the Board stated its opinion that: a. It is advisable for the United States to adopt a project authorizing Federal participation in the cost of protecting and im— proving the publicly owned shores at Lynn and Nahant, Massachusetts; b. The public interest involved in the proposed measures for the publicly owned shores is substantial. It is associated with prevention of direct damages to public property, indirect damges prevented, and recreational benefits to the general public. ¢. The share of the expense which should be borne by the United States is one-third of the first cost of the proposed new construction for publicly owned shores. The estimted amount of this share is $154,670. 37 The Board recommended that a project be adopted by the United States authorizing Federal participation by the contribution of Federal funds in an amount equal to one-third of the first cost of the following measures for the protection and improvement of the shores of Lynn and Nahant, Massachusetts, as follows: a. Artificial placement of approximtely 172,000 cubic yards of sand on the beach for a distance of 2,600 feet south of Woodbury's Point, to provide a backshore elevation of 18 feet above mean low waters: b. Gonstruction of a stone mound with a top elevation of 18 feet above mean low water along the tombolo from the foregoing improved beach to Little Nahant, a distance of about 6,250 feet. Federal participation was recommended subject to the conditions that responsible local interests will: a. Adopt the project named herein; b. Assure maintenance of the improvements during their useful life as may be required to serve their intended purpose: c. Provide, at their oWm expense, all necessary lands, easements, and rights-of-way; d. Hold and save the United States free from all claims for damages that may arise either before, during, or after prosecution of the work; e. Assure that water pollution that would endanger the health of bathers will not be permitted; f. Assure continued public ownership of the shore and its administration for public use only. The estimated amount of Federal participation in accordance with the foregoing recommendation is $154,670. RE SR eat COMPLETED COOPERATIVE BEACH EROSION STUDIES Location Qld Orchard Beach Hampton Beach South Shore of Cape Cod (Pt. Gammon to Chatham) Salisbury Beach Winthrop Beach Lynn=-Nahant Beach Revere Beach Nantasket Beach Quincy Shore South Shore (Town of Narragansett, South Kingstown, Gharlestown & Westerly} Compo Beach, Westport Hawk's Nest Beach, Old Lyme Ash Creek to Saugatuck River Hammonasset River to East River Jacob Riis Park, Long Is. Orchard Beach, Pelham Bay, Bronx Niagara County South Shore of Long Is. Completed MAINE 20 Sep 35 NEW HAMPSHIRE 15 Jul 32 MASSACHUSETTS 26 Aug 41 26 Aug 41 12 Sep 47 20 Jan 50 12 Jan 50 12 Jan 50 2 May 50 RHODE ISLAND 4 Dec 48 CONNECTICUT 18 Apr 35 21 Jun 39 29 Apr 49 29 Apr 49 NEW YORK 16 Dec 35 30 Aug 37 27 Jun 42 6 Aug 46 39 Published in House Doc. Congress 764 490 239 454 47h, Boi 450 271 80 81 74 81 81 74 75 78 NEW JERSEY Wanasquan Inlet & Adjacent Beaches 15 May 36 ail om Atlantic City 11 Jul 49 538 81 | VIRGINIA. Willoughby Spit, Norfolk 20 Nov 37 482 75 Golonial Beach, Potomac River 24 Jan 49 333 81 NORTH CAROLINA Fort Fisher 10 Nov 31 204 72 Wrightsville Beach 2 Jan 34 218 UW Kitty Hawk, Nags Head & Oregon Inlet 1 Mar 35 155 74 State of North Carolina 22 May 47 763 80 SOUTH CAROLINA Folly Beach 31 Jan 35 156 74 GEORGIA St. Simon Island 18 Mar 40 820 76 FLORIDA Blind Pass {Boca Giega) 1 Feb 37 187 15 Miami Beach. - 1 Feb 37 169 UD Hollywood Beach 28 Apr 37 253 75 Daytona Beach 15 Mar 38 Syak UE Bakers Haulover Inlet 21 May 4$ Da Ue Anna Maria & Longboat Keys 12 Feb 47 760 80 Jupiter Island 13 Feb 47 765 80 Palm Beach (1) 13 Feb 47 772 80 MISSISSIPPI Hancock County 3 Apr 42 Harrison County—Initial 15 Mar 44 Harrison GCounty—Supplement 16 Feb 48 682 80 LOUISIANA Grand Isle 28 Jul 36 92 75 (1) A cooperative study of experimental steel pile groins was also made, under which-methods of improvement were recommended in an interim report dated 19 Sep 40. Final report on experimental groins was published in 1948 as Technical Memorandum No. 10 of the Beach Erosion Board. 40 Galveston Galveston Bay, Harris Cty. Santa Barbara - Initial Supplement Final Ballona Creek & San Gabriel River (Partial) Orange County Coronado Beach Long Beach Mission Beach PENNSYLVANIA Presque Isle Peninsula, Erie (interim) (Final,) Erie County-Vicinity of Huron Lake Erie Shore-Michigan Line to Marblehead Cities of Cleveland & Lakewood Lake County Chagrin River to Fairport, Vermillion to Sheffield Lake Village, Lorain Cty. State of Illinois Milwaukee County Punta Las Marias, San Juan TEXAS 10 May 34 31 Jul 34 CALIFORNIA 15 Jan 38 18 Feb 42 22 Nay 47 ll May 38 10 Jan 40 4 Apr 41 3 Apr 42 4 Nov 42 3 Apr 42 23 Aug 49 OHIO 26 Aug 41 30 Oct 44 22 Mar 48 22 Nov 49 24 Jul 50 ILLINOIS 8 Jun 50 WISCONSIN 21 May 45 PUERTO RICO 5 Aug 47 4l 400 74 552 761 637 636 220 177 502 596 526 769 (3 74, WD 80 76 Wil 719 ug, 81 81 19 80 COOPERATIVE BEACH BHOSION STUDIES IN PROGRESS NEW HA MPSHIRE HAMPTON BEACH. Cooperative Agency: New Hampshire Shore and Beach Preservation and Development Commission. Problem: To determine the best method of preventing further erosion and of stabilizing and restoring the beaches, also to determine the extent of Federal aid in any proposed plans of protection and improvement. MASSACHUSETTS PEMBERION POINT TO GURNET POINT. Cooperating Agency: Department of Public Works, Commonwealth of Massachusetts. Problem: To determine the best methods of shore protection prevention of further erosion and improvement of beaches, and specifically to develop plans for pro- tection of Crescent Beach, The Glades, North Scituate Beach and Brant Rock. CONNECTICUT STATE OF CONNECTICUL. Cooperating Agency : State of Connecticut (Acting through the Flood Control and Water Policy Commission). Problem: To determine the most suitable mthods of stabilizing and improving the shore line. Sections of the coast will be studied in order of priority as requested by the cooperating agency until the entire coast is in- cluded. JONES BEACH. Cooperating Agency: Long Island State Parks Gommission Problem: To determine behavior of the shore during.a 12-month cycle, including study of littoral drift, wave re- fraction and movement of artificial sand supply between Fire Island and Jones Inlets. NEW JERSEY OCEAN CITY. Cooperating Agency: City of Ocean City. Problem: To determine the causes of erosion or accretion and the effect of previously constructed groins and structures, and to recommend remedial measures to prevent further erosion and to restore the beaches. 42 VIRGINIA VIRGINIA BEACH. Cooperating Agency: Town of Virginia Beach. Problem: To determine the methods for the improvement and protection of the beach and existing concrete sea wall. SOUTH CAROLINA STATE OF SOUTH CAROLINA. Cooperating Agency; State Highway Department o Problem: To determine the best method of preventing erosion, stabilizing and improving the beaches. FLORIDA PINELLAS COUNTY. Cooperating Agency: Board of County Commissioners. Problem: To determine the best methods of preventing further recession of the gulf shore line, stabilizing the gulf shores of certain passes, and widening certain beaches within the study area. LOUISIANA LAKE PONTCJARTRAIN. Cooperating Agency: Board of Levee Commissioners, Orleans Levee District. Problem: To determine the best method of effecting necessary repairs to the existing sea wall and the desirability of building an artificial beach to provide protection to the wall and also to provide additional recreational beach area. TEXAS GALVESTON COUNTY. Cooperating Agency: County Commissioners Court of Galveston County. Problem; To determine the best method of providing a permanent beach and the necessity for further protection or ex- tending the sea wall within the area bounded by the Galveston South Jetty and Eight Mile Road. To determine the most practicable and economical method of preventing or retarding bank recession on the shore of Galveston Bay between April Fool Point and Kemah. 43 CALIFORNIA STATE OF CALIFORNIA. Cooperating Agency. Division of Beaches and Parks, State of California. i Problem: To conduct a study of the problems of beach erosion - and shore protection along the entire coast of California. The initial studies are being made in the Ventura-Port Hueneme area, the Santa Monica Bay area and the Santa Cruz area. WISCONSIN RACINE COUNTY. Cooperating Agency; Racine County. Problem: To prevent erosion by waves and currents, and to determine the most suitable methods for protection, restoration and development of beaches. Kenosha. Cooperating Agency: City of Kenosha. Problem: To determine the best method of shore protection and beach erosion control. OHIO STATE OF OHIO. Cooperating Agency: State of Ohio (Acting through the Superintendent of Public Works). Problem: To determine the best method of preventing further erosion of and stabilizing existing beaches, of re- storing and creating new beaches, and appropriate locations for the development of recreational facilities by the State along the Lake Erie shore line. TERRITORY OF HAWAII WAIKIKI BEACH: WAIMEA & HANAPEPE, KAUAI. Cooperating Agency: Board of Harbor Commissioners, Territory of Hawaii. Problem: To determine the most suitable method of prevent— ing erosion, and of increasing the usable recreational beach area, and to determine the extent of Federal aid in effecting the desired improvement. A4 BEACH EROSION LITERATURE There are listed below some recent acquisitions to the Board's library which are considered to be of general interest. Copies of these publications can be obtained on 30-day loan by interested official agencies. "Observations of Echo Signals Obtained Using Variable Frequency Trans- mission," Edwin M. WeMillan, July 4, 1942. In dealing with the problem of large amplitude fluctuations in underwater echoes, the frequency modulation offers very considerable improvement in the distinguishability of echoes from reverberation; for listening, the signal frequency sweep is preferable because of the ability of the ear to differentiate a tone, or sequence of tones, froma toneless background and for presentation on a cathode ray screen, rapid modulation by a Sine wave or by noise is preferable because it gives more effective smoothing of the reverberation. "Model Study of Sand Transport Along an Infinitely Long, Straight, Beach ,* Thorndike Saville, Jr., Trans. AGU, Vol. 31, No. 4, 1950 This paper describes a small-scale tank study of the rate littoral transport of sand induced by wave action ona straight beach inclined to the direction of wave crest. "Notes on the Studies of Dam Problems Carried Out in the Laboratorio de Engenharia Civil," Lisbon, 1950. The Laboratorio de Engenharia has made numerous studies of problems related to the building of large dams. This paper discusses studies of materials, cements, concretes and soils together with studies of mechanical properties of the founda- tion rock and observations of the dams during and after con— struction. "Report of Sedimentation Surveys, Denison Dam (Lake Texoma) Red River, Texas and Oklahoma," June 1950, Tulsa District. This report presents the results of the first resurvey of sedimentation-in Lake Texoma. Data relative to changes in the river below the dam are also presented. The purpose of the investigation was to determine the effect of the operation of the project upon the channel of the Red River downstream from the dam. 45 1 gee «Oy LPG, Fannie! . be 4 . 1 1 le ee 'y « ce a y “ 6 Bare. f iy t T i : ti i F L e 7 om 4 i f } has j Heat , inh ! fe i opin ng . j yim st) } . fiat is, ver - 4 f i \ 4 hela ( j en al? ‘4 ‘ Na i EDM IY Aue eet ee eat i