Skip to main content

Full text of "Record of decision : Central Prince of Wales final supplement to the final environmental impact statement"

See other formats


Historic,  Archive  Document 

Do  not  assume  content  reflects  current 
scientific  knowledge,  policies,  or  practices. 


United  States 
Department  of 
Agriculture 

Forest  Service 


Alaska  Region 

Tongass 
National  Forest 


R10-MB-311b 
December  1 995 


Central  Prince  of  Wales 

Supplement 

to  the  Final  Environmental 
Impact  Statement 


Central  Prince  of  Wales 
Final  Supplement  to  the 
Final  Environmental  Impact  Statement 

Record  of  Decision 


Ketchikan  Area  - Tongass  National  Forest 
USDA  Forest  Service 
Alaska  Region 


Lead  Agency  USDA  Forest  Service 

Tongass  National  Forest 
Ketchikan  Area 

Responsible  Official  Forest  Supervisor 

Ketchikan  Area 
Tongass  National  Forest 
Federal  Building 
Ketchikan,  Alaska  99901 


For  Further  Information  Contact  David  Arrasmith,  Planning  Staff  Officer 

Ketchikan  Area 
Tongass  National  Forest 
Federal  Building 
Ketchikan,  Alaska  99901 


Contents 


Record  of  Decision 1 

Background 1 

Decision 2 

Reasons  for  Decision 2 

How  Issues  Are  Addressed  4 

Issue  1 : Falldown 4 

Issue  2:  Sustainability  4 

Additional  Issues  Raised  in  Comments  on  the  Draft  Supplement 6 

Public  Involvement  7 

Coordination  with  Other  Agencies  8 

Description  of  Options 8 

Options  Eliminated  from  Detailed  Study  8 

Options  Considered  for  Detailed  Study 8 

Environmentally  Preferred  Option  8 

Planning  Record 8 

Findings  Required  by  Law 9 

Federal  and  State  Permits 9 

Implementation  Process 9 

Process  for  Change  During  Implementation  9 

Right  to  Appeal  10 


Contact  Person 


11 


Record  of  Decision 


Background 

The  Record  of  Decision  (ROD)  for  the  CPOW  FEIS  was  published  on  August  6,  1993. 

The  ROD  documented  the  decision  of  the  Ketchikan  Area  Forest  Supervisor  to  implement 
alternative  F5  (as  modified)  as  the  selected  alternative  which  would  harvest  267  MMBF  on 
approximately  9,836  acres  and  would  meet  the  purpose  and  need  for  the  project. 

The  ROD  was  followed  by  a 45-day  appeal  filing  period  which  ended  on  September  20, 
1993.  Five  appeals  of  the  CPOW  ROD  were  received. 

On  November  23,  1993,  the  Regional  Forester’s  appeal  decisions  on  the  Central  Prince  of 
Wales  project  affirmed  the  Ketchikan  Area  Forest  Supervisor's  decision.  On 
February  2, 1994,  the  Reviewing  Officer  for  the  Chief  of  the  Forest  Service  affirmed  the 
Regional  Forester's  appeal  decisions  on  all  CPOW  appeals  and  appeal  points. 

Five  offerings  or  releases  of  timber  from  the  CPOW  project  were  made  to  Ketchikan 
Pulp  Company  (KPC)  between  February  and  December  1994.  These  releases  totaled 
approximately  78  million  board  feet  (MMBF). 

On  June  1,  1994,  Sierra  Club  Legal  Defense  Fund,  Inc.,  filed  a complaint  for  declaratory 
judgement  and  injunctive  relief  on  behalf  of  its  clients  (SEACC,  et  al.)  in  the  United 
States  District  Court,  District  of  Alaska.  The  complaint  named  the  Ketchikan  Area 
Forest  Supervisor  and  the  Forest  Service  as  defendants  and  challenged  the  CPOW  timber 
project:  The  complaint  alleged  violations  of  the  National  Environmental  Policy  Act 
(NEPA),  the  Administrative  Procedures  Act  (APA),  and  the  Tongass  Timber  Reform  Act 
(TTRA).  The  NEPA  and  APA  allegations  focused  on  the  volume  of  timber  available  in 
the  project  area  and  the  sustainability  of  future  timber  supply.  The  TTRA  allegation 
challenged  the  method  used  for  determining  proportionality  in  the  CPOW  project  under 
Section  301(c)(2)  of  the  TTRA. 

On  December  20,  1994,  the  Forest  Supervisor  partially  suspended  implementation  of  the 
CPOW  ROD  pending  completion  of  a Supplement  to  the  CPOW  FEIS.  The  Forest 
Supervisor  did  not  suspend  implementation  on  the  78  MMBF  previously  released  in  the 
project,  nor  an  additional  20  MMBF  in  two  offering  areas  being  contemplated  for  release 
to  KPC  prior  to  April  1996.  These  two  offerings  were  made  to  KPC  in  1995  and  totaled 
approximately  18  MMBF 

A Notice  of  Intent  to  prepare  a Supplement  to  the  CPOW  FEIS  was  published  in  the 
Federal  Register  on  April  5,  1995.  The  Draft  Supplement  to  the  CPOW  FEIS  was 
published  in  July  1995. 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


Record  of  Decision-1 


RECORD  OF  DECISION 

Decision 

It  is  my  decision  to  continue  implementing  the  CPOW  project.  My  rationale  for  this 

decision  is  shown  below. 

Reasons  for  Decision 

• Continuing  the  project  as  planned  should  result  in  the  harvest  of  approximately 
214  MMBF  of  the  267  MMBF  cleared  in  the  original  CPOW  ROD,  taking  into 
account  20  percent  project  level  falldown.  Halting  the  project  now  would  result 
in  harvest  of  only  96  MMBF  previously  released.  Continuing  the  project  as 
planned  will  more  closely  approach  meeting  the  stated  purpose  and  need  of  290 
MMBF  for  the  CPOW  project  than  would  halting  the  project  now. 

• Sustainability  is  a standard  required  by  the  National  Forest  Management  Act 
and  regulations  stated  in  36  CFR  219  to  be  applied  at  a National  Forest  level. 
While  not  a legal  requirement  for  a project  area,  current  and  projected  timber 
harvest  levels  help  provide  a measure  by  which  decisions  affecting  community 
stability  can  be  made. 

• In  Chapter  4 of  the  Final  Supplement,  one  estimate  of  suitable  timber  remaining 
for  harvest  in  the  project  area  is  that  represented  by  the  combined  CPOW  MELP 
and  the  updated  LSTA  from  the  Control  Lake  Cumulative  Effect  Analysis.  The 
combination  of  the  MELP  and  LSTA  offsets  some  of  the  weaknesses  identified 
for  each  study  as  documented  in  Chapter  3 of  the  Supplement.  Each  analysis 
identifies  harvestable  timber  in  areas  the  other  study  did  not  consider. 

The  Final  Supplement  indicated  that  a modified  version  of  this  combination 
provided  the  best  assessment  of  harvestable  timber  in  the  project  area.  That 
modification  recognized  moderate  to  high  risk  factors  including  encumbered 
lands,  steep  slopes,  and  high  vulnerability  karst.  Based  on  these  risk  factors,  the 
Final  Supplement  proposed  that  84,345  acres  of  suitable  timber  was  the  best 
assessment  of  remaining  timber  available  in  the  project  area. 

I disagree  with  this  rationale.  The  only  factor  that  should  be  considered  in 
modifying  the  combined  results  of  the  MELP  and  the  updated  LSTA  is 
conveyed  lands.  Of  the  4,539  acres  of  suitable  timber  located  on  encumbered 
lands  in  the  updated  LSTA,  3,218  acres  have  been  conveyed  to  the  State  of 
Alaska  or  Sealaska  Corporation.  Of  the  remaining  1,321  acres,  504  acres  have 
been  selected  by  the  State  of  Alaska  as  low  priority,  798  acres  have  been 
selected  by  Sealaska  Corporation  but  appear  unlikely  to  be  conveyed,  and  19 
acres  were  incorrectly  identified  as  encumbered.  Removing  only  those 
conveyed  acres  from  the  acres  of  suitable  timber  identified  in  the  combined 
CPOW  MELP  and  the  updated  LSTA  would  result  in  a total  of  91,025  acres  of 
potentially  harvestable  timber. 

Other  high  risk  factors  recognized  in  the  updated  LSTA  should  not  be  dropped 
from  harvest  consideration  until  further  field  reconnaissance  (recon)  occurs.  If 
potential  harvest  acres  are  found  to  be  unharvestable,  they  are  accounted  for  as 
part  of  the  anticipated  recon  and  implementation  falldown  of  23  percent 
discussed  in  the  Supplement. 


2-Record  of  Decision 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


RECORD  OF  DECISION 

• Projected  harvest  on  the  CPOW  project  area  over  the  current  ten-year  sale  plan 
through  year  2004,  including  the  remainder  of  the  CPOW  project,  will  average 
17  MMBF  per  year.  If  the  project  were  to  be  halted,  average  annual  harvest  on 
the  project  area  would  drop  to  10  MMBF. 

• The  combined  MELP  and  updated  LSTA  (modified  by  the  deduction  of 
conveyed  lands)  suitable  timber  estimate  would  yield  an  average  annual  harvest 
of  3 1 MMBF  beyond  the  year  2004,  after  the  completion  of  the  CPOW  project 
and  additional  planned  timber  projects  in  the  area.  If  the  project  were  halted, 
the  potential  average  annual  harvest  could  be  as  much  as  35  MMBF.  While 
both  figures  are  lower  than  historic  harvest  of  52  MMBF  annually,  both  are 
higher  than  harvest  currently  planned  for  the  period  of  1995  through  2004. 

• Community  stability  is  affected  by  timber  harvest  over  a larger  area  than  that 
defmed  by  the  CPOW  project.  In  this  case,  harvest  on  Prince  of  Wales  Island  as 
a whole  was  also  considered.  Over  the  next  ten  year  period  (through  2004) 
average  annual  harvest  on  Prince  of  Wales  is  projected  to  be  69  MMBF, 
including  the  completion  of  the  CPOW  project.  If  the  project  were  to  be 
deferred  until  after  the  year  2004,  the  average  annual  harvest  would  be 

61  MMBF  on  the  island. 

• TLMP  (1979a)  scheduled  commercial  forest  land  (CFL)  on  the  CPOW  project 
area  is  71,666  acres.  The  suitable  acres  identified  by  the  combined  MELP  and 
LSTA  (excluding  conveyed  lands)  amounts  to  91,025  acres,  or  127  percent  of 
TLMP  scheduled  CFL.  Extrapolating  that  proportion  to  TLMP  (1979a) 
scheduled  CFL  for  Prince  of  Wales  Island  as  a whole  (333,159  acres),  the 
resulting  suitable  timber  estimate  is  423,1 12  acres.  This  would  yield  a potential 
average  annual  harvest  of  167  MMBF  beyond  the  year  2004,  assuming  the 
CPOW  project  is  completed.  If  the  project  is  halted  and  remaining  volume 
rescheduled,  the  potential  average  annual  harvest  on  Prince  of  Wales  would  be 
168  MMBF.  Both  figures  are  greater  than  the  historic  average  annual  harvest  of 
122  MMBF  on  Prince  of  Wales. 

• The  ten-year  sale  schedule(Appendix  G)  reflects  a lower  planned  harvest  than 
can  reasonably  be  expected  in  the  future,  even  considering  a 23  percent 
falldown  factor. 

• If  falldown  approaches  30  percent  (combined  hard  falldown  of  23  percent  and  7 
percent  soft  falldown  at  moderate  to  high  risk  of  not  being  scheduled  for 
harvest),  future  harvest  potential  on  both  the  project  area  and  Prince  of  Wales 
Island  could  exceed  harvest  planned  over  the  next  ten  year  period. 

• The  next  ten-year  period  from  1995  through  2004  is  expected  to  experience 
lower  timber  harvest  volumes  on  the  CPOW  project  area  and  on  Prince  of  Wales 
Island  than  that  experienced  in  the  past.  Potential  future  timber  harvest  levels 
are  projected  to  be  greater  than  those  that  will  occur  over  the  next  ten  years. 

• I believe  that  deferring  the  remainder  of  the  CPOW  project  during  a period  of 
exceptionally  low  timber  harvest  is  not  justified  by  the  long-term  benefits  of  a 
1-3  MMBF  increased  average  annual  harvest  expected  in  the  future.  This 
long-term  benefit  does  not  outweigh  the  immediate  disruption  of  community 
stability  if  the  CPOW  timber  project  is  brought  to  a halt. 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


Record  of  Decision-3 


RECORD  OF  DECISION 

• Reallocation  of  timber  harvest  based  on  speculative  changes  to  the  allowable 

sale  quantity  (ASQ)  is  best  addressed  through  the  Tongass  Land  Management 
Plan  revision  process,  not  in  a project  level  decision  document  such  as  this 
Supplement. 

How  Issues  Are  Addressed 

ISSUG  1 1 The  issue  of  falldown  was  not  fully  addressed  in  either  the  CPOW  DEIS  or  the  CPOW 

Falldown  FEIS.  The  Supplement  reviewed  The  Irland  Group  Report,  the  Forest  Service 

Evaluation  of  The  Irland  Group  Report,  and  data  gathered  during  the  field 
reconnaissance  of  the  CPOW,  Lab  Bay,  Control  Lake,  and  Polk  Inlet  projects.  In 
addition,  data  gathered  during  the  implementation  of  121  CPOW  harvest  units 
(approximately  half  of  the  total  planned  units)  provided  a site-specific  and  accurate 
measure  of  falldown  that  can  be  expected  during  project  implementation. 

The  relative  strengths  and  weaknesses  of  applying  falldown  projections  from  each  of 
these  sources  to  the  CPOW  project  were  discussed.  Based  on  the  information  and 
analysis  displayed  in  the  Supplement  and  the  planning  record,  the  falldown  percentages 
of  8 percent  during  field  reconnaissance  and  15  percent  during  project  implementation 
are  the  best  available  information  regarding  hard  falldown.  Soft  falldown  factors 
encountered  during  field  reconnaissance  (10  percent)  and  project  implementation 
(5  percent)  were  also  identified.  While  some  soft  falldown  is  simply  the  rescheduling  of 
proposed  harvest  until  the  next  project,  some  falldown  is  implemented  for  resource 
protection  measures  until  standards  and  guidelines  are  formulated  and  implemented 
through  revision  or  amendment  of  the  Forest  Plan.  The  potential  for  7 percent  soft 
falldown  (moderate  to  high  risk  of  not  being  harvested)  is  addressed  in  the  Supplement. 
If  this  soft  falldown  factor  of  7 percent  is  applied  to  potential  harvest  volumes,  one  could 
expect  an  average  annual  harvest  of  29  MMBF  from  2005  through  2054  on  the  CPOW 
project  area  if  the  project  continues  as  planned.  If  halted  now,  average  annual  harvest 
from  2005  through  2054  may  be  32  MMBF.  If  the  7 percent  factor  is  applied  to  harvest 
on  Prince  of  Wales  Island,  the  average  annual  harvest  from  2005  through  2054  would  be 
slightly  under  153  MMBF  if  the  CPOW  project  continues  as  planned.  If  the  project  is 
halted,  average  annual  harvest  on  Prince  of  Wales  would  yield  slightly  more  than  153 
MMBF.  Even  with  this  additional  7 percent  soft  falldown,  potential  harvest  on  the 
project  area  and  on  Prince  of  Wales  Island  beyond  year  2005  is  greater  than  planned 
harvest  over  the  next  ten  years,  whether  or  not  the  CPOW  project  continues  as  planned. 

Estimated  falldown  discussed  in  The  Irland  Group  Report  and  the  Forest  Service 
Evaluation  of  The  Irland  Group  Report  are  not  inconsistent  with  the  site-specific  data 
generated  on  the  Prince  of  Wales  projects.  These  reports  were  intended  to  be  forest-wide 
(Tongass  NF)  projections  bearing  on  the  ASQ  proposed  by  the  alternatives  in  the 
Supplement  to  the  Draft  Environmental  Impact  Statement,  Tongass  Land  Management 
Plan  Revision  published  in  1991.  Their  findings  are  not  as  accurate  as  the  data  collected 
on  the  project  area  over  the  past  several  years. 

Issue  2:  The  issue  of  sustainable  timber  harvest  was  addressed  in  both  the  CPOW  DEIS  and  the 

Sustainability  CPOW  FEIS.  The  Supplement  provides  additional  analysis  and  data  on  this  issue. 

The  CPOW  DEIS  used  results  of  the  CPOW  MELP  (identified  as  52,727  acres  in  the 
DEIS)  to  project  potential  future  harvest  levels  on  the  project  area.  The  CPOW  FEIS 
used  TLMP  Draft  Revision  Alternative  P projections  of  suitable  timber  (1 14,016  acres) 
to  predict  potential  future  harvest  levels. 


4-Record  of  Decision 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


RECORD  OF  DECISION 

The  Supplement  uses  site-specific  data  from  the  CPOW  MELP  (50,288  acres  in  the 
CPOW  FEIS)  and  the  updated  logging  system  transportation  analysis  (LSTA)  from  the 
Control  Lake  Cumulative  Effects  Analysis  (75,205  acres)  as  starting  points  for  the 
analysis  of  potential  timber  harvest  levels  from  the  CPOW  project  area.  The  updated 
LSTA  for  the  project  area  is  the  result  of  updating  resource  databases  on  the  Ketchikan 
Area  in  project  areas  identified  in  the  ten-year  sale  plan.  These  estimates  of  suitable 
timber  are  compared  with  TLMP  (1979a)  planned  harvest  represented  by  scheduled  CFL 
for  the  project  area. 

The  combination  of  these  two  studies  offsets  some  of  the  weaknesses  of  each  discussed 
in  Chapter  3 of  the  Supplement.  The  MELP  was  not  an  attempt  to  identify  all 
harvestable  suitable  timber  within  the  project  area,  and  the  updated  LSTA  did  not 
identify  harvestable  timber  beyond  the  suitable  timber  identified  by  using  updated 
resource  data  and  TLMP  Draft  Revision  Alternative  P standards  and  guidelines.  The 
combination  provides  the  most  accurate  estimate  of  timber  harvest  opportunities  in  the 
project  area  from  which  future  projects  will  be  identified.  The  total  suitable  acreage 
identified  by  the  two  studies  is  94,243  acres.  There  is  a 31,250  acre  overlap  between  the 
two. 

Analysis  of  the  data  provided  with  the  updated  LSTA  revealed  a potential  risk  to  harvest 
for  9,898  acres.  These  risks  involved  steep  slopes,  high  vulnerability  karst,  excessive 
numbers  of  streams,  V-notches,  and  encumbered  lands.  Of  this  total,  4,539  acres  fall  on 
lands  selected  by  the  State  of  Alaska  or  the  Sealaska  Corporation. 

Of  the  4,539  acres  of  suitable  timber  on  encumbered  lands,  3,218  acres  have  been 
recently  conveyed  to  either  the  State  of  Alaska  or  Sealaska  Corporation.  Of  the 
remaining  1,321  encumbered  acres,  1,302  have  been  selected  but  are  of  lower  priority. 
These  acres  will  probably  remain  in  the  National  Forest  System.  There  are  19  acres  that 
were  mistakenly  identified  as  encumbered  but  are  not. 

Excluding  only  those  conveyed  lands  from  the  total  harvest  potential  provides  a more 
accurate  forecast  of  potential  timber  harvest  levels  on  the  project  area.  The  result  of 
excluding  conveyed  lands  from  the  combined  MELP  and  the  updated  LSTA  total  is 
91,205  acres  of  potentially  harvestable  timber.  This  total  exceeds  TLMP  (1979a) 
scheduled  CFL  (71,666  acres)  for  the  project  area,  though  it  does  not  equal  the  suitable 
timber  identified  by  the  Draft  Revision  Alternative  P (1991)  of  1 14,260  acres. 

The  combination  of  the  MELP  and  the  updated  LSTA  (excluding  conveyed  lands)  would 
allow  an  average  annual  harvest  of  3 1 MMBF  from  2005  through  2054.  This  exceeds 
the  ten-year  sale  plan  average  of  17  MMBF  for  the  project  area. 

Updated  LSTAs  for  the  remainder  of  the  project  areas  identified  in  the  ten-year  sale  plan 
were  not  yet  available  at  the  time  the  Supplement  was  completed.  In  order  to  provide  an 
estimate  of  suitable  timber  available  over  the  remainder  of  Prince  of  Wales  Island,  the 
proportion  of  the  five  suitable  timber  estimates  to  TLMP  (1979a)  scheduled  CFL  for  the 
CPOW  project  area  were  applied  to  the  scheduled  CFL  for  Prince  of  Wales. 

The  proportional  amount  of  suitable  timber  that  may  be  available  on  Prince  of  Wales  as  a 
whole  (based  on  the  combined  LSTA  and  MELP  excluding  conveyed  lands)  would  yield 
an  average  annual  harvest  of  167  MMBF  from  2005  through  2054  given  an  average 
falldown  of  23  percent  and  completion  of  the  CPOW  project  as  planned.  It  should  be 
noted  that  only  the  most  conservative  estimate  (the  overlap  between  the  LSTA  and 
the  MELP)  would  have  resulted  in  a future  average  annual  harvest  less  than  that  expected 
over  the  1995  through  2004  period. 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


Record  of  Decision-5 


RECORD  OF  DECISION 


Additional  Issues  Raised  in  Comments  on 
the  Draft  Supplement 

Some  comments  indicated  that  timber  harvest  under  the  Long-term  Contract  with 
Ketchikan  Pulp  Company  is  unsustainable. 

The  contention  that  logging  under  the  KPC  contract  is  unsustainable  is  a conclusion 
that  cannot  be  reached  based  on  the  analysis  of  timber  supply  on  one  project  area. 
Sustainability  is  a legal  requirement  that  applies  to  a National  Forest  rather  than  a 
project  area.  Whether  or  not  Long-term  Contract  commitments  can  be  met  on  the 
Tongass  National  Forest  and  how  much  suitable  timber  will  remain  for  harvest  on  the 
Tongass  and  the  Ketchikan  Area  beyond  the  end  of  the  contract  in  the  year  2004  is 
beyond  the  scope  of  this  Supplement. 

There  is  no  assurance  of  an  even  flow  of  timber  from  any  given  project  area  for  each 
year  or  each  decade.  Initial  entries  into  areas  have  traditionally  harvested 
proportionally  more  timber  and  more  easily  accessible  timber  than  later  entries.  This  is 
done  to  offset  high  initial  roading  and  logging  camp  costs  (Alaska  Regional  Guide,  p.  2- 
48).  Future  entries  would  have  proportionately  lower  harvest  volumes.  There  are 
project  areas  on  the  Ketchikan  Area,  such  as  the  Cleveland  Peninsula,  that  have 
experienced  little  to  no  harvest  to  this  point.  Substantially  less  than  50  percent  of  the 
suitable  timber  has  been  harvested  in  the  first  50  years  of  the  timber  rotation. 

Potential  harvest  of  timber  in  the  CPOW  project  area  may  be  lower  than  has  occurred 
historically.  This  has  been  documented  and  discussed  in  the  Supplement.  This  is  not 
relevant  to  the  decision  to  be  made.  The  issue  addressed  by  this  Supplement  is  how 
much  suitable  timber  remains  for  harvest  on  the  project  area  and  the  allocation  of 
harvest  over  the  next  decade  compared  with  potential  harvest  in  future  decades.  The 
decision  to  be  made  is  how  much  of  the  CPOW  project  should  be  re-allocated  to  harvest 
in  future  decades  based  on  what  is  planned  for  harvest  in  the  next  ten  years  as  compared 
with  potential  harvest  in  the  decades  beyond. 

Several  comments  received  stated  that  the  Forest  Plan  ASQ  should  be  changed  to  reflect 
the  effects  of  falldown. 

The  Forest  Plan  ASQ  is  established  through  amendment  or  revision  of  the  Forest  Plan. 
This  is  beyond  the  scope  of  the  Supplement.  Analysis  regarding  falldown  was  forwarded 
to  the  TLMP  Revision  Team  for  use  in  the  current  revision  effort.  Updated  resource 
databases  provided  by  the  contractor  performing  the  Control  Lake  Cumulative  Effects 
Analysis  were  also  forwarded  to  the  TLMP  Revision  Team.  Falldown  is  the  subject  of 
one  of  the  sixteen  science  assessments  and  resource  analyses  being  prepared  by  the 
Revision  Team. 

Comments  were  also  received  that  express  concern  that  there  is  less  suitable  timber  on 
the  CPOW  project  area  than  projected  by  Alternative  P of  the  Proposed  Revised  Forest 
Plan  (1991)  raising  the  question  of  an  ASQ  of  418  MMBF  as  opposed  to  TLMP  (1979a) 
ASQ  of  450  MMBF. 

The  results  of  intensive  efforts  to  identify  suitable  timber  on  one  project  area  best  apply 
to  that  project  area.  While  it  would  appear  that  20  percent  less  suitable  timber  may  be 
found  on  the  CPOW  project  area  than  projected  by  Alternative  P (proposed  ASQ  of  418 
MMBF),  that  may  not  hold  true  for  other  project  areas. 


6-Record  of  Decision 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


RECORD  OF  DECISION 


Some  comments  requested  that  the  scope  of  the  Supplement  be  broadened  into 
discussions  of  viable  wildlife  populations  including  Alexander  Archipelago  wolf  and 
Queen  Charlotte  goshawk.  Other  comments  suggested  that  we  delay  the  Final 
Supplement  until  new  habitat  capability  models  can  be  developed. 

The  scope  of  the  Supplement  was  clearly  defined  by  the  memo  directing  the  Supplement 
IDT  to  prepare  a supplement  regarding  f alldown  and  its  effects  on  timber  harvest. 
Wildlife  population  viability,  more  accurate  habitat  capability  models,  and  the  status  of 
the  wolf  and  goshawk  were  addressed  in  the  CPOW  FE1S  including  the  Biological 
Assessment.  These  issues  are  currently  being  dealt  with  in  the  revision  of  the  TLMP,  the 
draft  of  which  is  due  for  publication  by  the  end  of  the  calendar  year.  These  issues  are 
clearly  beyond  the  scope  of  the  decision  to  be  made  for  this  one  project. 

Comments  expressed  concern  that  the  current  Forest  Plan  ASQ  of 450  MMBF  cannot  be 
sustained  from  now  through  the  end  of  the  rotation  without  disastrous  effects  on  the  local 
and  regional  economy  as  well  as  subsistence  lifestyles. 

The  point  must  be  made  that  ASQ  is  a ceiling  on  decadal  amounts  of  timber  harvest  that 
may  be  accommodated  on  a National  Forest  level.  From  1954  through  1990,  average 
annual  harvest  has  averaged  364  MMBF,  well  less  than  the  ASQ  of 450  MMBF.  This 
allows  some  flexibility  and  room  for  decision-making  that  will  accompany  the  Forest 
Plan  Revision.  While  the  concerns  raised  are  not  groundless,  they  are  not  grounds  for 
immediate  cessation  of  timber  projects  pending  the  revision  of  the  Forest  Plan. 

Public  Involvement 

A Notice  of  Intent  to  prepare  a Supplement  to  the  CPOW  FEIS  was  published  in  the 
Federal  Register  on  April  5, 1995.  A letter  explaining  the  supplement  process  and 
describing  the  focus  of  the  analysis  was  mailed  on  April  10,  1995  to  over  700  individuals 
and  organizations  on  the  original  CPOW  mailing  list.  Those  interested  in 
remaining  on  the  Supplement  mailing  list  were  asked  to  complete  and  return  an  attached 
form.  Eight-five  respondents  indicated  their  interest  in  the  project  by  returning 
completed  forms. 

The  CPOW  Supplement  was  also  placed  on  the  NEPA  Schedule  of  Proposed  Actions  for 
the  Ketchikan  Area.  This  schedule  is  updated  quarterly  and  mailed  directly  to  67 
individuals  and  organizations.  The  quarterly  schedule  gives  a brief  description  of  the 
project  and  a contact  person  for  more  information. 

The  Draft  Supplement  to  the  CPOW  FEIS  was  published  in  late  July  and  mailed  to  all 
interested  parties  in  the  first  week  of  August.  A notice  of  Availability  was  published  in 
the  Federal  Register  on  August  1 1 with  a comment  period  ending  September  25,  1995. 

A total  of  seven  comment  letters  were  received. 

A press  release  regarding  the  Draft  Supplement  was  issued  on  August  23,  1995.  The 
press  release  briefly  summarized  the  issues  of  falldown  and  the  implications  for 
sustainable  timber  harvest  and  provided  information  for  those  persons  wishing  to 
comment. 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


Record  of  Decision-7 


RECORD  OF  DECISION 


Options 

Eliminated  from 
Detailed  Study 


Options 
Considered  for 
Detailed  Study 


Environmentally 
Preferred  Option 


8-Record  of  Decision 


Coordination  with  Other  Agencies 

Appendix  C lists  all  individuals  and  organizations  to  whom  copies  of  the  Final 
Supplement  to  the  CPOW  FEIS  were  provided.  The  Alaska  Department  of  Fish  and 
Game  and  the  United  States  Department  of  Interior  provided  comments  on  the  Draft 
Supplement.  Their  comment  letters  and  Forest  Service  responses  are  included  in 
Appendix  F. 

Description  of  Options 

The  original  alternatives  examined  in  detail  in  the  CPOW  FEIS  were  not  considered 
in  detail  in  the  Supplement.  The  estimated  harvest  volumes  ranged  from  261  MMBF 
to  268  MMBF  for  the  action  alternatives  and  no  harvest  for  the  no  action  alternative. 

The  original  alternatives  were  not  examined  in  detail  as  they  do  not  take  into  account  that 
the  selected  alternative  (F5)  has  been  partially  implemented  and  the  no  action  alternative 
would  now  have  to  account  for  the  harvest  of  98  MMBF.  Additional  information  is 
provided  in  the  Preface  of  the  Supplement. 

Two  options  were  considered  for  this  Supplement.  The  first  option  was  to  halt  the 
CPOW  project  after  an  estimated  98  MMBF  had  been  released.  The  second  option  was 
to  continue  the  CPOW  project  as  planned.  The  effects  of  these  two  options  on  future 
harvest  volumes  in  the  project  area  and  over  Prince  of  Wales  Island  as  a whole  were 
displayed. 

A wide  range  of  options  was  not  considered  as  the  purpose  and  need  for  the  project 
remains  valid.  The  option  of  continuing  the  project  as  planned  meets  the  purpose  and 
need  for  the  project.  Halting  the  project  now  would  not  meet  the  purpose  and  need. 

Of  the  two  options  analyzed,  the  option  to  halt  implementation  of  the  CPOW  project  now 
would  result  in  less  timber  harvest  over  the  next  ten  years.  That  deferred  volume  would 
then  be  rescheduled  for  harvest  between  2005  and  2054.  This  option  has  fewer 
short-term  effects  on  the  environment,  but  there  would  be  little  to  no  difference  over  the 
course  of  the  rotation  through  2054.  Based  on  this  analysis,  the  option  to  halt 

implementation  of  the  CPOW  project  would  be  the  environmentally  preferred  option. 
This  option  was  not  selected  as  it  does  not  meet  the  purpose  and  need  for  the  CPOW 
project. 

Planning  Record 

The  planning  record  for  the  Supplement  to  the  CPOW  FEIS  is  available  for  review,  by 
appointment,  at  the  Forest  Supervisor's  Office  in  Ketchikan,  Alaska.  The  planning  record 
also  includes  the  certified  administrative  record  for  the  CPOW  project,  TLMP  (1979a), 
TLMP  Draft  Revision  (1991),  and  the  Regional  Guide. 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


RECORD  OF  DECISION 


Findings  Required  by  Law 

The  original  CPOW  Record  of  Decision  (July  93)  documented  how  the  CPOW  project 
and  the  decision  to  implement  the  project  complied  with  the  following  laws: 

National  Forest  Management  Act 
Tongass  Timber  Reform  Act 
Endangered  Species  Act 
Bald  Eagle  Protection  Act 
Clean  Water  Act 

National  Historic  Preservation  Act 
ANILCA  Section  810 

Executive  Orders  1J988  and  1 1990  (floodplains  and  wetlands) 

Coastal  Zone  Management  Act 

Compliance  with  these  laws  and  executive  orders  has  not  changed  with  the  decision  I 
have  made  as  documented  in  this  Record  of  Decision. 

Federal  and  State  Permits 

This  decision  does  not  obligate  the  Forest  Service  to  obtain  any  permits  in  addition  to 
those  already  described  in  Chapter  1 of  the  CPOW  FEIS. 

Implementation  Process 

Implementation  of  this  decision  may  occur  no  sooner  than  30  days  after  the  date  of 
publication  of  the  notice  of  decision  and  availability  of  the  Final  Supplement  in  the 
Federal  Register,  or  50  days  following  publication  of  the  legal  notice  of  the  decision  in 
the  Ketchikan  Daily  News,  published  in  Ketchikan,  Alaska,  whichever  is  later. 

Process  for  Change  During  Implementation 

Proposed  changes  to  the  authorized  project  actions  will  be  subject  to  the  requirements  of 
the  National  Environmental  Policy  Act  (NEPA),  the  National  Forest  Management  Act  of 
1976  (NFMA),  Section  810  of  the  Alaska  National  Interest  Lands  Conservation  Act 
(ANILCA),  the  Tongass  Timber  Reform  Act  (TTRA),  the  Coastal  Zone  Management  Act 
(CZMA),  and  other  laws  concerning  such  changes. 


In  determining  whether  and  what  kind  of  NEPA  action  is  required,  the  Forest  Supervisor 
will  consider  the  criteria  for  whether  to  supplement  an  existing  EIS  in  40  CFR  1502.9(c) 
and  FSH  1909.15,  sec.  18,  and  in  particular,  whether  the  proposed  change  is  a substantial 
change  to  the  selected  alternative  as  planned  and  already  approved  (CPOW  FEIS  and 
ROD,  July  1993),  and  whether  the  change  is  relevant  to  environmental  concerns. 
Connected  or  interrelated  proposed  changes  regarding  particular  areas  or  specific 
activities  will  be  considered  together  in  making  this  determination.  The  cumulative 
impacts  of  these  changes  will  also  be  considered. 


FINAL  SUPPLEMENT  TO  THE  CPOW  FEIS 


Record  of  Decision-9 


The  United  States  Department  of  Agriculture  (USDA)  prohibits  discrimination  in  its  programs  on  the  basis  of  race,  color,  national  origin,  sex,  religion,  age,  disability, 
political  beliefs,  and  marital  or  familial  status.  (Not  all  prohibited  bases  apply  to  all  programs.)  Persons  with  disabilities  who  require  alternative  means  of  communicatior 
of  program  information  (braille,  large  print,  audiotape,  etc.)  should  contact  the  USDA  Office  of  Communications  at  (202)  720-2791. 

To  file  a complaint,  write  the  Secretary  of  Agriculture,  U.S.  Department  of  Agriculture,  Washington,  DC  20250,  or  call  (202)  720-7327  (voice)  or  (202)  720-1127  (TDD). 
USDA  is  an  equal  employment  opportunity  employer. 


Federal  Recycling  Program 
Printed  on  Recycled  Paper 


o 

'i  *■< 

s3  gc 

< ^ 

SC/5 

$ w 

C/5 


u 

H 

<Z> 

e* 


«8 

W 

o 

C/5 

c 

On 


< 

-T  O 

w o 
§6 
5 z 

^ H 


C/3 

£ 

< 

Q 

C/5 

P 


W 

Cm 


a> 

CZ3 

<+■> 

co 

£ 

O 

fe 

< 

Q 

c/3 

P 


Pm 

Z 

co 

co 

cc 

DC 

C 

e5 

r\ 

CO 

£ 

< 

c 

03 

• p* 

JG 

u 

•w 

0> 


C/5 

C 

#© 

*5 

co 


oo  S 

^ s 

WD<* 

Is 

= c 

03 
U 


CQ 

"3 

S* 

© 

T3 

r» 

fe 


0) 


rr> 

</> 

w 

CO 

CO  ^ 
CO  H 

w t? 

z £ 

3- 
0S 
ft. 

OS 

£ 

J* 

a 

c 
z 
w 

ft. 


CO 

£> 

tt 

fa 

C 


fa 

fa 

O