Skip to main content

Full text of "Case histories of Corps breakwater and jetty structures"

See other formats


(Wa w)) | REPAIR, EVALUATION, MAINTENANCE, AND 
(3) | REHABILITATION RESEARCH PROGRAM 


US Army Corps i] hah eas 81 eats 
of Engineers 1 TECHNICAL REPORT REMR-CO-3 


CASE HISTORIES OF CORPS BREAKWATER 
AND JETTY STRUCTURES 


Report 5 & 
NORTH ATLANTIC DIVISION 
by 


Ernest R. Smith 
Coastal Engineering Research Center a 
DEPARTMENT OF THE ARMY 


Waterways Experiment Station, Corps of Engineers 
PO Box 631, Vicksburg, Mississippi 39181-0631 


November 1988 


Report 5 of a Series 


Approved For Public Release; Distribution Unlimited | 


Prepared for DEPARTMENT OF THE ARMY 
US Army Corps of Engineers 
Washington, DC 20314-1000 


Under Work Unit 32278 and Work Unit 31269 


The following two letters used as part of the number designating technical reports of research published under the Repair, 
Evaluation, Maintenance, and Rehabilitation (REMR) Research Program identify the problem area under which the report 
was prepared: 


Problem Area Problem Area 
cs Concrete and Steel Structures EM Electrical and Mechanical 
GT Geotechnical El Environmental Impacts 
HY Hydraulics OM Operations Management 


co Coastal 


Destroy this report when no longer needed. Do not return 
it to the originator. 


The findings in this report are not to be construed as an Official 
Department of the Army position unless so designated 
by other authorized documents. 


The contents of this report are not to be used for 

advertising, publication, or promotional purposes. 

Citation of trade names does not constitute an 

official endorsement or approval of the use of such 
commercial products. 


COVER PHOTOS: 
TOP — Field Research Facility, Duck, North Carolina. 
BOTTOM — Photograph of Indian River Inlet jetties. 


Unclassified 


SECURITY CLASSIFICATION OF THIS PAGE 
Form Approved 


REPORT DOCUMENTATION PAGE OMB No. 0704-0188 
Exp. Date: Jun 30, 1986 


Ja. REPORT SECURITY CLASSIFICATION 1b. RESTRICTIVE MARKINGS 
Unclassified 
2a. SECURITY CLASSIFICATION AUTHORITY F 3. DISTRIBUTION / AVAILABILITY OF REPORT 


2b. DECLASSIFICATION/ DOWNGRADING SCHEDULE Approved for public release, 
distribution unlimited 


4. PERFORMING ORGANIZATION REPORT NUMBER(S) 5. MONITORING ORGANIZATION REPORT NUMBER(S) 
Technical Report REMR-CO-3 


6a. NAME OF PERFORMING ORGANIZATION 6b. OFFICE SYMBOL || 7a. NAME OF MONITORING ORGANIZATION 
USAEWES, Coastal Engineering (If applicable) 


Research Center 
6c. ADDRESS (City, State, and ZIP Code) 7b. ADDRESS (City, State, and ZIP Code) 


PO Box 631 
Vicksburg, MS 39181-0631 


8a. NAME OF FUNDING/SPONSORING 8b. OFFICE SYMBOL 9. PROCUREMENT INSTRUMENT IDENTIFICATION NUMBER 
ORGANIZATION (if applicable) 


US Army Corps of Engineers 
8c. ADDRESS (City, State, and ZIP Code) 10. SOURCE OF FUNDING NUMBERS 


PROGRAM PROJECT TASK WORK UNIT 
Washington, DC 20314-1000 ELEMENT NO. | NO NO. ACCESSION NO 
See 
reverse. 


11. TITLE (Include Security Classification) 
Case Histories of Corps Breakwater and Jetty Structures; Report 5: North Atlantic Division 


12. PERSONAL AUTHOR(S) 
Ernest R. Smith 


13a. TYPE OF REPORT 13b. TIME COVERED 14. DATE OF REPORT (Year, Month, Day) |15. PAGE COUNT 
Report 5 of a Series | rrom Jun 85 toDec 86 November 1988 vUe 

16. SUPPLEMENTARY NOTATION 

See reverse. 


17. COSATI CODES 18. SUBJECT TERMS (Continue on reverse if necessary and identify by block number) 
Breakwater REMR (Repair, Evaluation, 
aS | a | RN uecoucketcharmongunuts Maintenance, and Rehabilitation) 


Jetty Rubble-mound structures 
19. ABSTRACT (Continue on reverse if necessary and identify by block number) 


This report is fifth in a series of case histories of US Army Corps of Engineers 
(Corps) breakwater and jetty structures at nine Corps divisions. Chronological histories 
are presented for 58 breakwater and jetty structures located within the US Army Engineer 
Division, North Atlantic (NAD), which includes the New York, Philadelphia, Baltimore, and 
Norfolk Districts. Presently, there are approximately 161,500 lin ft of breakwater and 
jetty structures managed by NAD. Structure cross sections of rubble-mound or stone-filled 
timber crib account for most of this total. Thirty-three of the project structures have 
been repaired since construction. Other construction materials that have been used include 
steel, dolosse, concrete cap, concrete block, and timber. 


20. DISTRIBUTION / AVAILABILITY OF ABSTRACT 21. ABSTRACT SECURITY CLASSIFICATION 
[3 UNCLASSIFIED/UNLIMITED =) SAME AS RPT. 1 otic USERS Unclassified i 
22a. NAME OF RESPONSIBLE INDIVIDUAL 22b. TELEPHONE (Include Area Code) | 22c. OFFICE SYMBOL 


DD FORM 1473, 84 MAR 83 APR edition may be used until exhausted. SECURITY CLASSIFICATION OF THIS PAGE 
All other editions are obsolete 


Unclassified 


Unclassified 
SECURITY CLASSIFICATION OF THIS PAGE 


10. SOURCE OF FUNDING NUMBERS (Continued). 


Work Unit 32278 and Work Unit 31269 


16. SUPPLEMENTARY NOTATION (Continued). 


A report of the Coastal Problem Area of the Repair, Evaluation, Maintenance, and Rehabili- 
tation (REMR) Research Program. Available from National Technical Information Service, 


5285 Port Royal Road, Springfield, VA 22161. 


Unclassified 
wo EE EE eee 
SECURITY CLASSIFICATION OF THIS PAGE 


PREFACE 


This report was prepared as part of the Coastal Problem Area of the 
Repair, Evaluation, Maintenance, and Rehabilitation (REMR) Research Program. 
The work was carried out jointly under Work Unit 32278, "Rehabilitation of 
Rubble-Mound Structure Toes," of the REMR program and Work Unit 31269, "Sta- 
bility of Breakwaters," of the Civil Works Coastal Area Program. For the REMR 
Program, Coastal Problem Area Monitor is Mr. John H. Lockhart, Jr., Office, 
Chief of Engineers (OCE), US Army Corps of Engineers (Corps). REMR Program 
Manager is Mr. William F. McCleese of the US Army Engineer Waterways Experi- 
ment Station's (WES's) Structures Laboratory, and Coastal Problem Area Leader 
is Mr. D. D. Davidson of WES's Coastal Engineering Research Center (CERC). 
Messrs. John G. Housley and Lockhart are Technical Monitors of the Civil Works 
Coastal Area Program. 

This report is fifth in a series of case histories of Corps breakwater 
and jetty structures at nine Corps divisions. The case histories were written 
from information obtained from several sources (where available), including 
inspection correspondence, design memorandums, survey reports, and annual re- 
ports to the Chief of Engineers. Unless otherwise noted, any changes in pro- 
totype structures subsequent to 1985 are not included. 

This work was conducted at WES during the period June 1985 to December 
1986 under general direction of Dr. James R. Houston, Chief, CERC, and 
Mr. Charles C. Calhoun, Jr., Assistant Chief, CERC; and under direct supervi- 
sion of Mr. C. Eugene Chatham, Jr., Chief, Wave Dynamics Division (CW), and 
Mr. D. D. Davidson, Chief, Wave Research Branch (CW-R). This report was pre- 
pared by Mr. Ernest R. Smith, Hydraulic Engineer, Wave Processes Branch 
(CW-P). Messrs. John P. Ahrens, Peter J. Grace, John M. Heggins, and 
Cornelius Lewis, CW-R, and Frances E. Sargent, CW-P, visited project sites 
and gathered information. Mr. Marvin G. Mize, CW-P, drafted figures, and 
Ms. Shirley A. J. Hanshaw, Information Products Division, Information Tech- 
nology Laboratory, edited this report. 

Commander and Director of WES during publication of this report was 


COL Dwayne G. Lee, EN. Technical Director was Dr. Robert W. Whalin. 


CONTENTS 


PREBACERrieletsve crctareyclelcteketeteratololencroichorsiensMele) iefolaehenot ele eleleorakel on McheNeL el emoued: 
CONVERSION FACTORS, NON-SI TO (SI) METRIC UNITS OF MEASUREMENT 
PART I: UAH KOU G ooacocqc6G00060000000000000000000000000 


Backgrounders crrctercchedarerKererciehehenst et emeitoiel tekelerelel el teu eNoNotel oven cMevomiey 
AMINO s6ocooodo0oobUbO doo DOOD OC OODDOODD OOOO OOO OOOODDDON 


PART II: SUMMARY OF CORPS BREAKWATER AND JETTY STRUCTURES IN NAD 


ecoceoesce ee eee 


CONVERSION FACTORS, NON-SI TO SI (METRIC) 
UNITS OF MEASUREMENT 


Non-SI customary units of measurement used in this report can be converted to 


SI (metric) units as follows: 


Multiply By 
cubic yards 0.76455549 
feet 0.3048 
inches 2.54 
miles (US statute) 1.609347 
pounds (force) 4.448222 
square feet 0.09290204 
tons (2,000 lb force) 8896 . 443353 


To obtain 
cubic metres 
metres 
centimetres 
kilometres 
newtons 
square metres 


newtons 


CASE HISTORIES OF CORPS BREAKWATER AND JETTY STRUCTURES 


NORTH ATLANTIC DIVISION 


PART I: INTRODUCTION 


Background 


1. The US Army Corps of Engineers (Corps) is responsible for a wide vari- 
ety of coastal structures located on the Atlantic, Pacific, and gulf coasts, 
the Great Lakes, the Hawaiian Islands, other islands, and inland waterways. 
Coastal improvements such as breakwaters or jetties are necessary where safe 
harboring or passage of shipping is required. These structures are contin- 
uously subjected to wave and current forces, and they are usually constructed 
on top of movable-bed materials. Under these conditions structural deteriora- 
tion can occur and, at some point, maintenance is required if the structure 
fails to serve the existing needs of the project. Some of these projects have 
been maintained for 150 years or more. Methods of construction (and repair) 
have varied significantly during this time, due principally to a better under- 
standing of coastal processes, availability of construction materials, existing 


wave climates, regional construction practices, and economic considerations. 


Purpose 


2. The purposes of this report are to lend insight into the scope, magni- 
tude, and history of coastal breakwaters and jetties under Corps jurisdiction; 
determine their maintenance and repair history; determine their methods of 
construction; make this information available to Corps personnel; and address 
objectives of the Repair, Evaluation, Maintenance, and Rehabilitation (REMR) 
research program. To do this, case histories of Corps breakwater and jetty 
structures have been developed to quantify past and present problem areas (if 
any), to take steps to rectify these problems, and to subsequently evaluate the 
remedial measures. General design guidance can be obtained from those solu- 
tions that have been most successful. Information in this report should be of 
particular value to Corps personnel in the US Army Engineer Division, North 
Atlantic (NAD), and its coastal districts and possibly to non-Corps personnel. 


Where adequate solutions are lacking or where specific guidance is needed, 


further research will be conducted to address these problems (e.g. general 
armor stability, toe protection, localized damage, use of dissimilar armor, 


wave runup and overtopping). 


PART II: SUMMARY OF CORPS BREAKWATER AND JETTY STRUCTURES IN NAD 


3. NAD has 58 projects which contain breakwater and/or jetty structures 
that are located in four coastal districts as follows: New York (NAN), 21; 
Philadelphia (NAP), 17; Baltimore (NAB), 16; and Norfolk (NAO), 4. Case 
histories for these structures are included in Tables 1-58 which are ordered 
according to the preceding districts and coastal location. Twelve of the 
projects are located in an ocean environment, and the remainder are situated 
in bays, sounds, or rivers. Overall, there are approximately 161,500 lin ft* 
of breakwaters (22.6 percent) and jetties (77.4 percent). Most of the struc- 
tures' cross sections are rubble mound (73.1 percent) or stone-filled timber 
crib (10.4 percent). Other construction materials that have been used include 
steel (Wilmington Harbor and Indian River Inlet), dolosse (Manasquan Inlet), 
concrete cap (Manasquan Inlet and Ocean City Inlet), concrete block (Cold 
Spring Inlet), and timber (Double Creek, Little Wicomico River, and Urbanna 
Creek). Thirty-three of the project structures have been repaired since 
construction. 

4, Figures 1 through 4 are maps of NAN, NAP, NAB, AND NAO, respectively, 
showing project locations. Pertinent summary information on each project is 


presented in the following listing. 


* & table of factors for converting non-SI units of measurement to SI 
(metric) units is presented on page 3. 


ri 
< 
°) 
a 
in] 
2) 
3 
ar 


| 
| 


ORDONS LANDING 


PLATTSBURGH HARBOR 


NEW YORK DISTRICT 
BOUNDARIES 


i 2 y) 


rf 


MASSACHUSETTS 


———_— 


YOSYVH : 


YOsYVH * 
MONLIL LWW <I 


D 


ee 


— §3183H9 140d 
yOauVH 
AINNOWHOYV 1 


BES NIN] 1S: YL AVAVAIN IA 


NESGLEN COVE 


“HARBOR BS 
pe wa 


413 1NI (S83q) 
AVMV AION LSV3 


Ava VIIVAE 


cv OOH AGNVS 


43349 
J a%vno3as33H9 


AN Di 


10 20 30 


SCALE OF MILES 


(fo) = (e) 


NAN breakwater and jetty project locations 


Figure 1. 


MANTUA CREEK 


RACCON CREEK 


DELAWARE RIVER AN 
CHESAPEAKE BAY CANAL & 
& 


> 


oy 


DELAWARE GOSHEN 
BAY CREEK 


CAPE MAY HARBOR 
TO DELAWARE BAY 


oy 


ROOSEVELT > 
\A\INCET 
BALTIMORE 


DISTRICT 
BOUNDARY 


Ti : 


es g 

\; PHILADELPHIA LE \ 4 
.. DISTRICT : 
)): BOUNDARY 
, 


MANASQUANY.¢3 
INLET 


DOUBLE « 
CREEK—> 


SCALE OF MILES. 


Figure 2. NAP breakwater and jetty project locations 


BOUNDARY —>\ 
PENNSYLVANIA 


DISTRICT 


h 
ye 


OCEAN CITY 
INLET 


AQ AYSAIN JYVJONOHL OIG. 
a NS ONV 3A09 HOLIMI~ ew 


N aawouous usdan 


i : RS = ss == tS 
= SJPIOQHSILNUN es 
y JANIS SHOHSILNYN or 


JAKWAIS 1 
43AIN SOHOILNWN 


Ue 


7 > 7. 
OBYVH 3NNOBIVID-H“7 


BACK CREEK— <p 
D ROCKHOLD CREEK~Ste 


AN 


FISHING CREEK~*-S\ 


DISTRICT BOUNDARY 


SCALE OF MILES 


NAB breakwater and jetty project locations 


Figure 3. 


URBANNA CREEK 


1 Xo 
ee 
=.) 1 
a ee 


a7 Ve 178 el Ld 


<: MILFORD Se x 
= HAVEN——— 


Cas 


Al 
cd 


SCALE OF MILES 
40 ie} 40 


———————— 


Figure 4. 


NAO breakwater and jetty project locations 


10 


Structure Armor Length Date of Improve- 


Location Table Type & No.* Type** ft Origin mentt 

Rouses Point 1 B S 1,835 1892 N 
Gordons Landing 2 B S 675 1891 R 
Plattsburgh Harbor 3 B X,S 1,565 1836 R 
Burlington Harbor 4 B(2) X,S 4,157 1836 R 
Port Chester 5 B S 783 1895 R 
Larchmont Harbor 6 B Ss 1,440 1906 R 
Glen Cove Harbor 7 B S 1,465 1906 N 
Port Jefferson 8 J(2) iS} 2,490 1871 R 
Mattituck Harbor 9 J(2) S 1,705 1906 R 
Greenport Harbor 10 B - oO 1083 N 
Sag Harbor 11 B Ss 3,180 1908 R 
Lake Montauk Harbor 12 J(2) S 1,962 1926 R 
Shinnecock Inlet 13 J(2) S 2,309 1953 R 
Moriches Inlet 14 J(2) iS} 2,302 1953 R 
Browns Creek 15 J(2) S 1,148 1892 R 
Fire Island Inlet 16 3 - 4,950 1941 N 
Jones Inlet 17 J S) 5,200 1959 R 
East Rockaway 

(Debs) Inlet 18 J s 3,750 1934 R 
Jamaica Bay 19 J S 8,400 1933 R 
Sandy Hook Bay 20 B BS) 4,000 1940 N 
Cheesequake Creek 21 J(2) S 1,920 1883 N 
Neshaminy State Park 22 J ) 230 1968 N 
Mantua Creek 23 J(2) S,X 3,033 1907 R 
Raccoon Creek 24 J X 950 1922 N 
Wilmington Harbor 25 J(2) Stax 3,440 1936 R 
Delaware River and 26 J(2) Ss 4,190 1903 R 

Chesapeake Bay Canal 
Smyrna River 27 J(2) X 2,803 1939 N 
Mispillion River 28 J(2) Six 11,442 1859 

(Continued) 


* Indicates type and number of structures (i.e. B-breakwater, J-jetty, B(2)- 
two breakwaters, J(2)-two jetties, etc.) 
** Indicates amor types (i.e. S-stone, X-timber crib, St-steel, C-concrete 
cap, D-dolosse, T-timber, CB-concrete block. 
+ R-repair, N-none. 


Location 
Roosevelt Inlet 


Delaware Bay Harbor 
of Refuge 


Manasquan Inlet 
Barnegat Inlet 
Double Creek 
Absecon Inlet 
Goshen Creek 

Cold Spring Inlet 


Cape May Harbor to 
Delaware Bay Canal 


Indian River Inlet 
Rock Hall Harbor 
Claiborne Harbor 
Back Creek 


Herring Bay and 
Rockhold Creek 


Fishing Creek 
Tilghman Island 


Nanticoke River at 
Bivalve 


Nanticoke River at 
Nanticoke 


Upper Thorofare 


Twitch Cove and 
Big Thorofare River 


Ocean City Inlet 
Colonial Beach 

Nomini Bay and Creek 
Bonum Creek 

Herring Creek 

Little Wicomico River 
Urbanna Creek 

Carters Creek 

Milford Haven 

Tylers Beach 


Table 
29 
30 


31 
32 
33 
34 
35 
36 
Shi 


38 
39 
40 
44 
42 


43 
yy 
45 


46 


47 
48 


49 
50 
51 
52 
23 
54 
Be) 
56 
57 
58 


Structure Armor 
Type & No. Type 


J(2) 
B(2) 


J(2) 
J(2) 
J 

J(2) 
J(2) 
J(2) 
J(2) 


J(2) 
B(2) 
J 


St 
S) 


n 


Length 
ft 


3,400 
12,500 


2,260 
7,495 

550 
4527 
2,480 
8,958 
1,300 


3,452 


1,000 
650 
900 


2,150 
200 
2,100 


1,600 


720 
3,870 


3,480 
1,500 
2,410 
1, 100 
1,450 
3,307 
2,612 

TH2 
1,183 

740 


Date of 
Origin 

1908-1938 
1898-1901 


1931 
1940 
1912 
1948 
1897 
1911 
ISR) 


1939 
1939 
1888 
1938 
1939 


1941 
1981 
1960 


1938 


1934 
1940 


1934 
1982 
1912 
1967 
1960 
USS 
1956 
1902 
1913 
1981 


Improve- 


ment 


tq fs) fe) fo) 


eo) 


te so 


Table 1 


Rouses Point Breakwater, Rouses Point, New York, New York District 


Date(s) 


1892 


1986 


Construction and Rehabilitation Histor 


A 1,835-ft-long breakwater was completed for harbor protection (Fig- 
ure 5). Construction was of rubble mound, faced with large stones. 
Cost of construction was $98,467. 


No further repair or maintenance information has been found. 


BREAKWATER 


Figure 5. Rouses Point, New York 


133 


Table 2 


Gordons Landing Breakwater, Gordons Landing, Vermont 
New York District 


Date(s) Construction and Rehabilitation History 


1891 A 675-ft-long breakwater was constructed to provide dock protection 
(Figure 6). The structure was built of rubble and large stone. Cost 
of construction was $34,750. 


1893 Core rubble and large facing stones were placed on the seaward 135 ft 
of the breakwater. 


1986 No further repair or maintenance information has been found. 


Ff" WiLcox POINT SS 
[=] 


. CUMBERLAND 


runny \. 
oocn 


oncanwaren~ \ Pied® GORDONS LANDING 
[IN 


av a 
nocKweLl e co 


TYPICAL CROSS SECTION 


Figure 6. Gordons Landing, Vermont 


14 


Table 3 


Plattsburgh Harbor Breakwater 
Plattsburgh, New York 


Date(s) Construction and Rehabilitation History 

1836- 1,250 ft of breakwater was constructed of timber cribs filled with 

1875 rubblestone and capped with large stone. Slopes were 1:1, and the 
timber elevation was at low water level. 

1893 The breakwater was extended to 1,565 ft (Figure 7). A total of 
$32,500 was spent on renewal of the old timber superstructure by one 
composed of large facing stones with rubblestone core. 

1949 A survey indicated the breakwater was in good condition except at the 
ends. 

1971 Repairs were made to the north end of the breakwater at a cost of 
$118,000. 

1986 No further repair or maintenance information has been found. 


15 


RANGE LIGHTS 


PLATTSBURGH 


LANDING 


us. 
RESERVATION 


PROVIDENCE 
ISLAND 


STAVE 
ISLAND 


SCALE OF FEET 
° 


Figure 7. Plattsburgh Harbor, New York 


16 


Date(s) 


1890 


1948 


1960 


1962- 
1965 


1986 


Table 4 


Burlington Harbor Breakwater 


Burlington, Vermont 
New York District 


Construction and Rehabilitation History 


A 4,157-ft breakwater was completed after 54 years of construction 
(Figure 8). The breakwater consisted of two segments at lengths of 
364 ft (north) and 3,793 ft (south) which were separated by 250 ft. 
Construction was of rubble mound resting on rock-filled timber cribs 
capped by either concrete (2,457 ft), or rock (1,700 ft). The cribs 
rested on a sand and gravel bed and were fastened with dowels and 
tenons. Crest elevation was +8.0 ft low lake level (111), and crib 
width ranged from 24 to 34 ft. 


The breakwater was repaired. Stone was placed on the lakeside at 
weakened sections. 


A survey indicated the existing structure had settled 1.0 to 3.0 ft 
along the entire length. Deterioration of sections of the timber 
fasteners left unconnected sections and caused timber displacement 
and leaning of the structure lakeward. Deterioration was believed to 
be caused by wave action and ice conditions over long periods of 
time. Approximately 550 lin ft of the stone superstructure was un- 
dermined. Eighty feet of the structure was breached. 


The breakwater was rehabilitated using 16,573 tons of stone at a cost 
of $381,000. 


No further repair or maintenance information has been found. 


APPLETREE 8AY 


ye. 
9 7 Vz 


LIGHT 


BREAKWATER 


BR UPR AERIANEG? ci ON, 


= 
x 
~N 
Q 
= 
x 
x 
iS) 


SCALE OF FEET 
° 


2000 2000 
Se 


Figure 8. Burlington Harbor, Vermont 


18 


Date(s) 


1895 


1963 


1986 


Table 5 


Port Chester Breakwater, Port Chester, New York 


New York District 


Construction and Rehabilitation History 


A 783-ft-long rubble-mound breakwater was completed from Byram Point 
to Sunken Rock (Figure 9). Crest elevation was +15 ft mlw. The 
estimated cost of breakwater construction was $25,000. 


The breakwater was repaired using 990 tons of stone. The cost of the 
repairs was $25,500. 


No further repair or maintenance information has been found. The 
project has been deauthorized. 


— miLL ST 
PORT 
CHESTER 


east 


PORT CHESTER 


yo 
cM 
AW 
te 


CRORNENE EMCO Tah CHUInT 


MO & @ 
SRR: 

Jo 
= Ib 
cnove Ty Sau 

AE 

YQ, 

YOR K Ke “ 
\ 4 9 
wean )) 1 6 v 
“Va C) 
9 
ny 
> 
x v 
eS C) 
s . BYRAM at 
PT. & 
2 * @ 6 
> 

o 
os Q 


ecALE OF PERT 
. t00 


Figure 9. Port Chester Harbor, New York 


19 


Date(s) 


1906 


1967 


1969 


1986 


Table 6 
Larchmont Harbor Breakwater 
Larchmont, New York 


New York District 


Construction and Rehabilitation History 


Construction was completed on a 1,440-ft-long stone breakwater, (Fig- 
ure 10). Crest elevation was +10.0 ft mlw, crown width was 5.0 ft, 
and side slopes were 1:1. Stone sizes 8.0 to 10.0 tons were placed 
in random fashion. Initial construction costs were $71,065. 


A survey of the breakwater indicated the entire length was below 
design elevation and varied from +4.0 to +8.0 ft mlw. A localized 
depression of +2.0 ft mlw was located approximately 1,300 ft from the 
shoreward end. The breakwater was submerged during high tides, which 
created danger areas and was only partially effective as a barrier to 
storm waves. The structure had no breaks and was considered stable. 


_The entire breakwater was rehabilitated by adding 8.0- to 10.0-ton 


stone in pell mell fashion to raise the elevation up to original 
design. Crown width remained 5.0 ft, and side slopes were 1V:1.5H. 
Cost of rehabilitation was $215,500. A 12.5-ft, 4.9-sec design wave 
was used. 


No further repair or maintenance information has been found. 


20 


Vi 


\ \ / ° =e 4 
\ ¥ 


pevancey.:// 
say octancer J 


| °F 
if FZ (SSNS 
hee wo SS ah 


V\ woarn ceose 
v 


= — 


‘. s “ 
F xy eH: 
i. MQ EOGE WATER PT. 
Oy §sourw Levee 


A Oo 
HURON ROCK 
(REMOVED) 
ep mene PT. BREAKWATER 
Ligar 


Soavaress Rock 


& 


eno ear 


Figure 10. Larchmont Harbor, New York 


21 


Table 7 
Glen Cove Breakwater 
Glen Cove, New York 


New York District 


Date(s) Construction and Rehabilitation History 


1906 A 1,465-ft-long stone breakwater was completed to provide shelter to 
anchorage (Figure 11). Crest elevation was +10.4 ft mlw, crown width 
was 5.0 ft, and side slopes were 1:1. Stone sizes of 1,500 lb to 
2.0 ton were placed in pell mell fashion. Cost of initial con- 
struction was $71,830. 


1964 A survey of the breakwater revealed that the offshore portion had 
deteriorated and the outer half had settled 3.0 ft. Crest elevation 
varied from +5.0 to +10.4 ft mlw, and side slopes varied from 1:1 to 
1V:2H. Stones were displaced due to undersized stone. Over 50 per- 
cent of the breakwater was submerged at high tide. The breakwater 
was considered stable with no breach along the entire length. 


1986 No further repair or maintenance information has been found. The 
project has been deauthorized. 


22 


[RED SPRING PT. 


SCALE OF FEET 


Figure 11. Glen Cove Harbor, New York 


23 


Date(s) 


1871 


1872 


1875 


1877 


1878 


1879 
1881 
1882 
1883 


1891 
1908 
1964 
1986 


Table 8 
Port Jefferson Jetties 


Port Jefferson, New York 
New York District 


Construction and Rehabilitation History 


A 600-ft-long riprap jetty was constructed east of the harbor en- 
trance to prevent shoaling in the channel. Crest elevation was 
+6.5 ft mlw. 


The jetty was extended to 1,050 ft, maintaining the same crest 
elevation. 


A 475-ft-long riprap jetty was built west of the harbor using 
3,933 tons of stone (Figure 12). Crest elevation was +11.0 ft mlw. 


The east jetty was extended 50 ft seaward, and the entire jetty was 
raised to +5.0 ft high water (hw). 


The west jetty was extended 450 ft with a crest elevation of +2.0 ft 
mlw, except the seaward end was +11.0 ft mlw. 


The east jetty was extended 70 ft using 1,437 tons of stone. 
Stone was placed on both jetties. 
The east jetty was extended 120 ft using 2,020 tons of stone. 


The west jetty was extended to 940 ft. Crest elevation of the jetty 
was +11.0 ft mlw over the shoreward 550 ft and +2.0 ft mlw seaward. 
The middle of the +2.0 ft mlw section was +11.0 ft mlw, and the sea- 
ard end was +14.0 ft mlw. Crown width was 4.0 ft at the seaward 

250 ft, and side slopes were 1:1. The east jetty was extended to 
1,390 ft at +5.0 ft hw, with a 4.0-ft crown width. The total cost of 
the jetties since 1871 was $79,000. 


The east jetty was repaired over 600 ft with 1,464 tons of stone. 
The east jetty was extended to 1,550 ft (Figure 12). 
A survey indicated the jetties were in poor condition. 


No further repair or maintenance information has been found. 


24 


LONG (SLANOD SOUND i 


MT_MISERY PT. 


Bran, 


wEST JETTY 


x 
oO 
Ww 
2 


omy SELLE TERRE 


yy z= R 
7) . a4 <2) 
<) RY 
: =: > \. 

fo) Lr, 

fo) ro) > Ve 
« r a 
Le 4 
7) ty 


PORT JEFFERSON 


SCALE OF FEET 


Figure 12. Port Jefferson Harbor, New York 


25 


Table 9 
Mattituck Harbor Jetties 
Mattituck, New York 


New York District 


Date(s) Construction and Rehabilitation History 


1906 Two parallel jetties were constructed 400 ft apart at the harbor 
entrance. Lengths were 775 ft (east (Figure 13)), and 680 ft (west). 
The estimated cost of construction was $40,000. 


1910 The landward 680 ft of the east jetty and 485 ft of the west jetty 
were repaired and made sand tight at a cost of $6,158. Seaward por- 
tions of the jetties were in need of repair and sand tightening. 


1938 The west jetty was extended to 930 ft (Figure 13). The jetties were 
considered to be in good condition. 


1975 Both jetties were repaired using $10,670 tons of stone. The cost of 
repairs was $385,000. 


1986 No further repair or maintenance information has been found. 


26 


SCALE OF FEET 


Figure 13. Mattituck Harbor, New York 


ail 


Table 10 


Greenport Harbor Breakwater 


Greenport, New York 
New York District 


Date(s) Construction and Rehabilitation Histor 


1883 A 1,570-ft-long breakwater was constructed to provide harbor protec- 
tion from east and northeast storms (Figure 14). Crest elevation was 
+3.0 ft hw and allowed for 1.0-ft expected settlement. Crown width 
was 5.0 ft, and side slopes were 1:1. The estimated cost of con- 
struction was $22,000. 


1986 No further repair or maintenance information has been found. 


Figure 14. Greenport Harbor, New York 


28 


Date(s) 


1908 


1962 


1963 
1986 


Table 11 


Sag Harbor Breakwater, Sag Harbor, New York 
New York District 


Construction and Rehabilitation History 


A two-section breakwater was constructed of stone to provide harbor 
protection (Figure 15). The total length of the breakwater was 

3,180 ft. The inshore section extended 1,330 ft north-northwest from 
Conklin Point. The offshore and inshore sections overlapped and were 
separated by 100 ft. The offshore section extended 1,850 ft west- 
northwest. Crest elevations were +7.5 ft mlw, crown width was 

5.0 ft, and side slopes were 1:1. The cost of construction was 
$59,800. 


Surveys indicated the breakwater had settled 0.5 to 1.0 ft for con- 
siderable lengths. The breakwater was considered stable. 


Repairs were made using 1,429 tons of stone at a cost of $15,150. 


No further repair or maintenance information has been found. 


SHELTER /SLAND SOUND 


FLOOD 
£88 — 


NORTH HAVEN 
PENINSULA 


SAG HARBOR 
COVE 


Figure 15. Sag Harbor, New York 


2s) 


Date(s) 


1926 


1942 


1967 


1968 


1986 


Table 12 
Lake Montauk Jetties 


Star Island, New York 
New York District 


Construction and Rehabilitation History 


Private interests constructed jetties east and west of the lake en- 
trance. The east jetty was 750 ft long (Figure 16), and the west 
jetty was 981 ft long. Crest elevations were +6.0 ft and +8.0 ft 
mean low water (mlw) west and +8.0 ft mlw east. Crown width varied 
from 5.0 to 6.0 ft, and the side slopes were 1V:1.5H. One- to 
4,0-ton stone was used and placed in random fashion. 


The west jetty was extended 231 ft shoreward at the request of the 
Department of the Navy using $82,738 of Navy funds (Figure 16). 
Crest elevation of the extension was +8.0 ft mlw, crown width was 
6.0 ft, and side slopes were 1V:1.5H. Cover stone used was 4.0 to 
6.0 tons, and core stone was 8.0 to 6,000 lb. 


A survey indicated the jetty was in poor condition. Proposals were 
made to repair and extend the jetties using a design wave of WoO) sae 
and 5.8 sec. 


The jetties were repaired, and the east jetty was extended 350 ft. 
The cost of repairs and the extension was $526,600, and 18,400 tons 
of stone were used. 


No further repair or maintenance information has been found. 


30 


BLOCK 1/SLANDB SOUND 


LAKE MONTAUK 


HARBOR 


SCALE OF FEET 
300 


Figure 16. Lake Montauk Harbor, New York 


31 


Date(s) 


1953 


1954 


1956 


1982 


1985 


Table 13 


Shinnecock Inlet Jetties 


Tiana Beach and Hampton Beach, New York 
New York District 


Construction and Rehabilitation History 


Local interests constructed two jetties for inlet stabilization at 
lengths of 1,363 ft east (Figure 17) and 850 ft west. The cost of 
construction was $846,210 east and $376,000 west. The design geome- 
try of both jetties consisted of +9.0-ft mlw crest elevations, 12.0- 
ft crown widths, and 1V:1.5H side slopes. The jetties were con- 
structed of one layer capstone, 4.0- to 10-ton stone on the landward 
1,163 ft of the east jetty, and 6.0- to 12-ton stone elsewhere. 
Core stone used on the east jetty was 5.0 lb to 1.0 ton on the land- 
ward 1,163 ft and 5.0 lb to 2.0 tons elsewhere. Core stone used on 
the west jetty was 50 lb to 1.0 ton. A 2.0-ft-thick blanket and 
apron stone were placed using 5.0- to 500-1b stone. 


Local interests extended the west jetty 96 ft (Figure 17) at a cost 
of $166,230. The extension was built at the same elevation and width 
as the original jetty. Side slopes were 1V:2H. Capstone was 6.0 to 
12 tons, covering 10-lb to 2.0-ton core stone resting on a 2.0-ft- 
thick blanket and apron, consisting of 50- to 500-1b stone. 


A survey revealed that the east jetty had suffered severe damage. 
Capstones and slope stones had slipped and were disarranged in nu- 
merous spots. Core stones were washed out in several places. Cap- 
stones and core stones were washed out in four locations totaling 

150 ft. The outer 250 ft of the jetty was partly washed out. Beach 
and dunes adjacent to the jetty eroded, and waves rode over the dunes 
and flanked the jetty. The west jetty was in fair condition with 
minor slips and disarrangement in five spots. The inlet was ina 
shoal condition. Most of the damage was due to a hurricane in 1954. 


The west jetty was reconstructed by resetting cap stones to original 
design geometry over 170 ft. A 1,470-ft-long pile crib revetment on 
the north end of the west jetty was replaced by a rubble-mound jetty. 
(Figure 18). 


A survey revealed that the reconstructed portion of the west jetty 
was in good condition. The seaward 200 ft of the west jetty had 
unraveled and capstones were scattered. The west jetty head had not 
maintained design configuration. Stones on the inlet side of the 
east jetty had sloughed in some sections, but stones on the beach 
Side had retained their original position. Two areas on the northern 
end were completely deteriorated. Erosion of sand caused undermining 
of the east jetty with continual loss of sand undermining it further. 


(Continued) 


32 


DAL B16 2 bts 


PROJECT DEPTH 


PROJECT OEPTH 


DATUM PLANES 


(M.L.W) (OCEAN SIDE)°15 FT. BELOW MSL. 
(M.L.w) (BAY SIDE) °O2 FT BELOW MSL. 


SCALE OF FEET 
ie} 


800 800 
—eEE————E 


ES new WORK REMAINING TO BE DONE 


Figure 17. Shinnecock Inlet, New York 


33 


an NEW JETTY CONSTRUCTED 
ORIGINAL CAP STONE 5 TO 9 TONS 
PILE CRIB 
REVET MENT- 


NON- FUNCTIONAL 
REVETMENT SECTION 


DUNE RO 
JETTY RECONSTRUCTED 


P STONES 
ESET 


COMPLETE 
WASHOUTS 


PARTIAL Af 
WASHOUTS Tees GAPS IN STONES 
Be NO INTERLOCKING 


HW LINE 1953 
UNRAVELING 
TO JETTY 
STONES SLOPED STONE SLOUGHING, 
TOP OF JETTY SETTLEMENT 
WEST JETTY nner SAND LOSS BEHIND 


f: EXISTING CONDITIONS 
SHOALING . MEAN HIGH WATER LINE. ... 
ADJACENT ft ney 
TO JETTY = 


STONE SETTLEMENT, 
GAPS EVIDENT 


ATLANTIC 
OCEAN 


| 

Y| 

A S UNRAVELED 
Yj Lo} 


COMPLETELY 


EAST JETTY 


NOT TO SCALE 


Figure 18. 1982 reconstruction of west jetty and 1985 existing 
conditions of east jetty, Shinnecock Inlet 


34 


Date(s) 


1985 
(Cont. ) 


1986 


Table 13 (Concluded) 


Construction and Rehabilitation History 


There were areas of partial washouts of stone, settlement, and non- 
interlocking capstones. The seaward 300 ft was completely unraveled, 
with all stones scattered (Figure 18). It was determined that the 
jetties had served their function of inlet stabilization and they 
were not leaking significant amounts of sand. 


Plans call for rehabilitation of the jetties. The east jetty will 
need new capstones and core stones where there are complete washouts, 
approximately 450 ft. Original stones will be removed and reset 
where settlement and sloughing has occurred, approximately 700 ft. 
The 300-ft east jetty head section will be completely rebuilt with 
new and original stone. A blanket will be placed for scour protec- 
tion. A 5.0-ft-thick blanket using 1,000-lb stone will be laid on 
the existing bottom to prevent additional scouring of the west jetty 
toe. New capstone and core stone are needed to supplement the dis- 
placed stones of the west jetty head. The section will be rebuilt 
using existing stone but will consist of two layers of armor stone. 


35 


Date(s) 


1953 


1954 


1956 


1983 


1986 


Table 14 


Moriches Inlet Jetties 


Great South Beach and Pikes Beach, New York 
New York District 


Construction and Rehabilitation History 


Construction of two jetties by local interests was completed at 
lengths of 750 ft east and 1,420 ft west. Elevations were +9.0 ft 
mlw, crown widths were 12.0 ft, and side slopes were 1V:1.5H. One 
layer of capstone was placed over core stone, which rested on a 
2-ft-thick blanket. Stone sizes used on the east jetty were 4.0- to 
10.0-ton capstone and 5.0-lb to 1.0-ton core stone on the shoreward 
580 ft, and 6.0- to 12-ton capstone and 5.0-lb to 2.0-ton core stone 
on the remainder of the jetty. The west jetty consisted of 2.0- to 
6.0-ton capstone and 10-lb to 1,000-lb core stone on the shoreward 
1,280 ft and 6.0- to 12-ton capstone and 10-lb to 1.0-ton core stone 
elsewhere. Blanket and apron stone was 5.0 to 500 lb and 10 1b to 
500 lb on the east and west jetties, respectively. Cost was $327,630 
for the east jetty and $420,210 for the west jetty, all non-Federal 
funds. 


Local interests extended the jetties to 841 ft east and 1,461 ft west 
(Figure 19) using 6.0- to 12.0-ton capstone at 1V:2H side slopes. 
Core stone used was 15 lb to 5.0 ton, east jetty, and 10 1b to 2.0 
tons west jetty. A 2.0-ft-thick blanket and apron was placed using 
15- to 500-lb stone. Jetty ends were approximately 800 ft apart. 
Cost was $194,290 east and $142,260 west. 


An inspection of the jetties was conducted. Stone on the inlet side 
of both jetties had slipped at numerous locations. Slope stones and 
capstones had unraveled at the outer end of the east jetty. Approxi- 
mately 300 ft of the west jetty had settled 2.0 to 3.0 ft. The 
jetties had undergone severe wave attack since their construction, 
and most of the damage was attributed to the hurricane of August 31, 
1954. 


A survey indicated the jetties were in a good, stable condition. The 
jetties had settled approximately 2.0 ft over 65 ft on the east jetty 
and 130 ft on the west jetty. The jetties did not meet Corps of 
Engineers standards for armor stone layer thickness, weight, or ele- 
vation, and it was determined that it would be more economical to 
maintain the jetties on an annual basis than by rehabilitation. 
Potential damage was anticipated to increase. 


No further repair or maintenance information has been found. 


36 


f INLET 
_ ISLAND 


PROJECT DEPTH 


DATUM PLANES 


Q4.L.w) (OCEAN SIDE)° 1.7 FT BELOW MS.L. 
(M.LW) BAY SOE) °O4 FT. BELOW MSL 


= [new work remains To 8 CONE 


Figure 19. Moriches Inlet, New York 


S/ 


Date(s) 


1892 


1927 


1935 


1962- 
1963 


1986 


Table 15 


Browns Creek Jetties 


Sayville, New York 
New York District 


Construction and Rehabilitation History 


Two riprap jetties were constructed east and west of the creek en- 
trance. The east jetty was 448 ft long, and the west jetty was 492 ft 
long (Figure 20). Crest elevations were +1.0 ft hw, crown width 

was 3.0 ft, and side slopes were 1:1. The minimum stone used was 

500 1b. 


The west jetty was repaired and extended 208 ft (Figure 20). Eleva- 
tion of the extension was +3.0 ft hw. Nine hundred eighty one cubic 
yards of rock was used for repair and extension. 


The outer 213 ft of the west jetty was repaired. Minimum capstone 
and slope stone was 2.0 tons, and core stone was 15 lb to 1.5 tons. 
The crest elevation was raised over the entire jetty to +4.0 ft mlw, 
crown width was 4.0 ft, and side slopes were 1V:1.5H. 


A survey indicated the jetties were deteriorated. Almost all stones 
were displaced on the west jetty, and there were numerous openings in 
the structure. Most of the stones were shifted out of place on the 
east jetty. Almost half of the jetty was breached and was not visi- 
ble at mean low water. The jetties were rehabilitated over the en- 
tire lengths in 1963 using 4,000 tons of stone at a cost of $71,000. 
Crest elevations were +4.0 ft mlw, crown width was 6.0 ft, and side 
slopes were 1V:1.5H (Figure 20). Three-ton cap and slope stone, and 
15-1b to 1.5-ton core stone was used. The design wave was 5.0 sec, 
0) te. 


No further repair or maintenance information has been found. The 
project has been deauthorized. 


38 


prownd River Road 


TOWN DOCK 
(new) 


RivER ROAD 


cI |): 
oo ort timit f 
oF GFT PRovect? H |b 


| 
i 
| 
| 


im 
© 


EAST JETTY 


west 
—}— 700’ 


DEPTH 


= 
SS ace 


(SVS 
~ 
=x 


PROJECT 


SCALE OF FEET 
° 


400 400 
—S—S SSS 


Figure 20. Browns Creek, New York 


39 


Table 16 
Fire Island Jetty 
Democrat Point, New York 


New York District 


Date(s) Construction and Rehabilitation History 


1941 A 4,950-ft jetty was constructed to stabilize the inlet (Figure 21). 
Crest elevation was +8.0 ft mlw, crown width was 12.0 ft, and side 
slopes were 1V:2H. The jetty rested on a 3-ft-thick blanket which 
extended 50 ft seaward of the jetty toe. 


1950 A survey indicated the sand trapping capacity of the jetty was 
reached, and the jetty was in fair condition. 


1986 No further repair or maintenance information has been found. 


STATE < 
804T CHANNEL ——= 


1SLANO 


DEMOCRAT ROBERT MOSES STATE PARK 


DATUM PLANES 


MLW, (AT DEMOCRAT PORT - OCEAN G:DE) = 20 FT. BELOW MSL 
MLW. (AT DEMOCRAT PONTT-ugT GIDE) = 1.2 FT. BELOW MSL 


Figure 21. Fire Island Inlet, New York 


40 


Date(s) 


Table 17 
Jones Inlet Jetty 


Jones Beach State Park, New York 
New York District 


Construction and Rehabilitation History 


1959 


1962 


1985 


1986 


A 5,200-ft-long jetty was constructed to provide inlet stabilization, 
and a sand barrier was constructed to prevent shoaling of the inlet 
(Figure 22). The jetty was constructed in four sections. The land- 
ward section (Section 1) was 1,150 ft in length and had a crown 

width of 6.0 ft and side slopes of 1V:1.5H. Minimum capstone sizes 
were 5.0 tons, and core stone was 10 lb to 3.0 tons. Section 2 was 
3,650 ft long and had a crown width of 8.0 ft and side slopes of 
1V:2H, except the shoreward 1,850 ft on the western side, which was 
1V:1.5H. Minimum capstone used was 5.0 tons, and core stone was 

15 lb to 4.0 tons. Section 3 was 350 ft long and had a crown width 
of 12.0 ft and side slopes of 1V:2H. Capstone used was 8.0 ton mini- 
mum, and core stone was 15 lb to 5.0 ton. Section 4, the most sea- 
ward section, was 50 ft and had a crown width of 15 ft and side 
slopes of 1V:2.5H. Stone sizes were the same as those in Section 3. 
All crest elevations were +9.0 ft mlw. The jetty rested on a 2.0-ft- 
thick blanket that extended 20 ft west from the base of Sections 1 
and 2 and extended 30 ft from both sides of the base of Section 3, 
except for 125 ft on the seaward west side. A 2.0-ft-thick apron 
extended 100 ft from the toe and curved to intersect the blanket in 
Section 3. The useful life of the jetty was expected to be 20 years. 


The Middle Atlantic coastal storm of 6-8 March 1962 damaged the 
jetty. The outer 200 ft was raveled and broken down to the high 
water level. A second layer of capstone was added to the outer 

120 ft to restore the original design. The adjacent 1,080 ft shore- 
ward was repaired by replacing armor stone and by adding stone. 
Armor stone was replaced on the adjacent 900 ft shoreward. 


The jetty had nearly reached impoundment. Sand was bypassing the 
jetty, mostly through large voids at the jetty-shoreline intersec- 
tion. The apron had settled approximately 7.0 ft at the seaward end 
due to sand loss through voids in the apron. 


No further repair or maintenance information has been found. 


44 


MIDDLE BAY 


aN 
NSS ON- FEDERAL Coane 


(Sy 


Eu 
ya 
ADOW 
ME yy 
cDeRaL Peostct 


ISLAND 


4 
Welkeaet ae 
arte et 


=H ee 
ean bead 
uuu 


HROINT LOCKOUT, 
ee 


R 
y 
S 


Figure 22. Jones Inlet, New York 


42 


Date(s) 


1934 


1935 


1941 


1946 


1963 


1986 


Table 18 


East Rockaway (Debs) Inlet Jetty 


Long Beach, New York 
New York District 


Construction and Rehabilitation History 


A 3,750-ft-long jetty was constructed on the east side of the inlet 
for stabilization (Figure 23). The jetty was constructed in three 
sections with lengths of 1,400 ft, 1,400 ft, and 950 ft, landward to 
seaward, respectively. The design geometry for each section was: 


Section 1: Crest elevation of +8.0 ft mlw, 6.0-ft crown width, 1:1 
side slopes, and one layer of cover and capstone. 


Section 2: Crest elevation of +8.0 ft mlw, 8.0-ft crown width, 1:1 
side slopes, and one layer of cover and capstone. 


Section 3: Crest elevation of +10.0 ft mlw, 15.0-ft crown width, 
1V:1.5H side slopes, and one layer cover and capstone. 


The jetty rested on a 1.0-ft-thick blanket and a 1.0-ft-thick apron 
which extended seaward of the toe 500 ft. A jetty was to be built 
west of the inlet if necessary. 


Repairs were made to the jetty beginning 2,500 ft from the landward 
end, and extending seaward 250 ft. The cost of repairs was $14,426, 
and 1,926 tons of stone were used. 


Repairs were made by rearranging 212 tons of stone on the seaward 
610 ft at a cost of $6,000. An additional 375 tons were placed on 
the east side of the seaward end at a cost of $1,670. 


Twenty-four hundred tons of stone were placed on the jetty at a cost 
of $78,000. The jetty was considered to be in good condition. 


Repairs were made using 800 tons of stone at a cost of $18,411, and 
the structure was in good condition with the exception of minor 
repairs. 


No further repair or maintenance information is available on the east 
jetty. The west jetty has not been built. The project has been 
deauthorized. 


43 


f° ATLANTIC BEAGH 


PROJECT 


EAST JETTY 


Ae Tee M AN ETE (aC OF Cue Ane 


SCALE OF FEET 
600 


DaTuUM (M4. Ww) = 210 FT. BELOW M.S. 


Figure 23. East Rockway (Debs) Inlet, New York 


4y 


Table 19 
Jamaica Bay Jetty, Rockaway Point, New York 


New York District 


Date(s) Construction and Rehabilitation History 


1933 A jetty was constructed east of the bay entrance, 8,400 ft long, for 
channel protection (Figure 24). Plans called for construction of a 
west jetty. 

1949 A survey of the jetty stated it was in fair condition. 

1953 Repairs were made to 225 ft of the jetty using 580 tons of stone at a 
cost of $14,088. 

1963 The jetty was rehabilitated to project dimensions. 

1986 No further repair or maintenance information is available on the east 


jetty. The west jetty has not been constructed. 


BERGEN 


BEACH 


OS BO © ff Gb % 


— 
i] - ns at 
o i 


5, 
“C40 y CPt 


‘ay, 
LJ 
went Tan 


ROCKAWAY INLET 


FORT TILOEN 


EAST JETTY 


iD geo ATLANTIC OCEAN 


CHANBEL 


Figure 24. Jamaica Bay, New York 


45 


Table 20 


Sandy Hook Bay Breakwater 
Atlantic Highlands, New Jersey 
New York District 


Date(s) Construction and Rehabilitation History 

1940 A 4,000-ft-long rubble-mound breakwater was completed (Figure 25). 
The breakwater extended east from the New Jersey Central Railroad 
steamboat dock. The cost of construction for the breakwater was 
$239,600, of which $158,334 were federal funds. A total of 
93,548 tons of stone was used. 

1986 No further repair or maintenance information has been found. 


" S\SPERMACETI 
cove 


ATLANTIC HIGHLANDS 


Figure 25. Sandy Hook Bay, New Jersey 


46 


Table 21 


Cheesequake Creek Jetties, Morgan, New Jersey 
New York District 


Date(s) Construction and Rehabilitation History 

1883 Two parallel jetties were constructed 200 ft apart for channel pro- 
tection. Lengths were 925 ft east and 995 ft west (Figure 26). 

1986 No further repair or maintenance information is available. The 


project has been deauthorized. 


ALON 
Ep) FEN 
le \ 
y. PROJECT CEPT 
Be 3st 


0 
[Nonovesto Sé5 
PILE Diae 


FORMER 
WHTEREAD DOC. 


veoregam iw 
PeDERaL prosacT 


SCALE OF FEET 
\ ° 1000 
eon 


Figure 26. Cheesequake Creek, New Jersey 


47 


Table 22 
Neshaminy State Park Jetty 
Neshaminy State Park, Pennsylvania 
Philadelphia District 


Date(s) Construction and Rehabilitation Histor 


1968 


1986 


A 230-ft-long rubble-mound groin was built but has served as a jetty 
for channel control (Figure 27). 


No further repair or maintenance information has been found. 


2 
Dr Ses 
2 = \ 
Yee 
SSS Sea Se \- 
S 32325255 
N 2 
Sa eS, 
BUCKS —— COUNTY 
—_ 
a 
=v. 
a 
op s) 
Ayal 
™m 
z 
NESHAMINY STATE 
PARK HARBOR 
Li eee SUES cauuy 
R 
ave 
DELAWARE 
ie 


SCALE OF FEET 
400 9 800 


Figure 27. Neshaminy State Park Harbor, Pennsylvania 


48 


Date(s) 


1907 


1912- 
1913 


1918 
1962 


1963 


1964 


1986 


Table 23 


Mantua Creek Jetties 


Paulsboro, New Jersey 
Philadelphia District 


Construction and Rehabilitation History 


Two jetties were constructed to provide channel protection. Lengths 
were 754 ft and 580 ft east and west, respectively. The jetties were 
constructed of stone-filled timber cribs, with mat brush placed to 
support the stone (Figure 28). Top width and elevation were 12.0 ft 
and +8.0 ft mlw, respectively, for each jetty. 


The east jetty was extended to 1,577 ft, and the west jetty was 
extended to 1,456 ft (Figure 28). 


Repairs were made by the addition of stone. 


An investigation of the jetties revealed the jetties had settled an 
average of 2.0 ft. Approximately 100 ft of the offshore end of the 
east jetty had deteriorated, with most of the pilings gone, and stone 
had fallen out to below the waterline. Most of the walings had 
deteriorated and were missing. Piles were missing at intermediate 
locations along the jetties, but there was no significant loss of 
stone at those locations. Piles that remained were in good 
condition. 


The jetties were rehabilitated at a cost of $136,895. A new row of 
piles was placed over approximately 100 ft at the offshore ends. 
Piles were placed 7.5 ft on either side of the center line of the 
jetties. Corestone was dumped between the piles to an elevation of 
+8.0 ft mlw (Figure 29). Missing piles were replaced, and new wales 
were provided along the remainder of the jetties. One row of cap- 
stone was placed on the inner sides of both cribs on top of the 
existing stone to +8.0 ft mlw. Core stone was filled between the 
capstones in the center of the jetties to +8.0 ft mlw (Figure 29). 
Crown width was 16.0 ft at the offshore ends and 12.0 ft on the re- 
mainder of the jetty. Design wave height was 4.2 ft. 


Repairs were made to the seaward end of the east jetty at a cost of 
$4,864. The Corps was reimbursed later for this work. 


No further repair or maintenance information has been found. 


49 


Grasset; 
Chemical Co. 


Paulsboro WS 


wiGuwary’ 7X 
BRIDGE 
(ORAM) 


Strathmann 
Sand @ Grove! Co. 


AMIGHWAY 


GLOUCESTER COUNTY BRIOGE 


Porters Lae 


Upstream limit of 
Federal Project 


‘F.R_BRIOGE 
(FIXED) 


pA 
Mount Royal 
(@ 
é palsies grid? (FIXED) 
ul qari Cooks Landing ——Y 
me 


0" 


EL+80 | £ 
wh as 


WALES 8x10" 


10" 


WALES 8 xI2" 


TYPICAL CROSS SECTION 


5000 ie) 5000 


Figure 28. Mantua Creek, New Jersey 


50 


€961 ‘satqqef yooug enqueW Jo uOTIeITTIGQeYysy “62 ouNdTyY 


NOILVA3 13 


NOILD3S 3YOHSIIO 


ay 
> 


MIN 


SY31LN39 0-2 


NO 31d GOOM’, 2! 


51 


08+ 13 
SNO1SdV9 
SNO1S 3409 


Date(s) 


1922 


1986 


Table 24 
Raccoon Creek Jetty 
Bridgeport, New Jersey 
Philadelphia District 


Construction and Rehabilitation History 


A 950-ft-long timber pile, brush, and stone jetty was constructed 
south of the entrance to provide channel protection (Figure 30). The 
cost of construction was $29,159. 


No further repair or maintenance information has been found. 


Bridgeport 


Ae Ia aA yous! 
19 mea to Camden —————=> 
aE 


ry 


GLOUCESTER COUNTY 


Figure 30. Racoon Creek, New Jersey 


52 


Table 25 


Wilmington Harbor Jetties 
Wilmington, Delaware 
Philadelphia District 


Date(s) Construction and Rehabilitation History 


1883 A 1,740-ft-long curved stone-filled pile and timber crib jetty was 
constructed north of the Christina River mouth. 


1884 The north jetty was raised 4.0 ft to a height above high water (no 
information on exact height). 


1900 The north jetty was repaired and extended 313 ft. A terminal crib 
was also constructed. The total length of the north jetty was 
2,150 ft. Jetties were constructed on the south side of the 
Christina River and at the mouth of the Brandywine River. The length 
of the south Christina River jetty was 1,515 ft and was built of pile 
and stone. A cross dike was built to connect the inner end of the 
jetty to the shore at high water. The Brandywine River jetty was 
V-shaped and was built of stone-filled pile and timber crib. The 
total length of this jetty was 690 ft, 430 ft on the Brandywine River 
side and 260 ft on the Christina River side (Figure 31). 


1905 Repairs were made to the Brandywine River jetty and the north 
Christina River jetty. New wales were put on the Brandywine jetty, 
and face timber was replaced on the north Christina jetty. Stone was 
replaced where needed on both jetties. 


1916 Repairs were made to the north Christina River jetty. Broken timber 
and piling was replaced with new material. Fender piles were placed 
along the channel face, and the interior of the crib was filled with 
stone where settling had occurred along the entire length of the 


jetty. 

1925 The south jetty was removed, and a new jetty was to be built south of 
the Christina River. 

1931 Approximately 1,200 ft of the north jetty was removed to improve the 
channel regime. The total length of the north jetty was 950 ft (Fig- 
ure 31). 

1936 A new jetty was completed south of the Christina River mouth. The 


jetty was 2,300 ft long (Figure 31) and consisted of 1,352 lin ft of 
steel sheet-pile wall, buttressed with 100-ft timber piles 12 ft on 
center, a 948-ft outboard section consisting of twelve 25.5-ft- 
diameter steel sheet-pile cells, and one 30.5-ft-diameter terminal 
cell with twelve 51-ft interconnecting fences. Crest elevation was 
+10 ft Corps of Engineers Datum (2.9 ft below mean sea level, 1929). 
The landward end of the jetty was connected to shore by a 120-ft 
steel sheet-pile anchor wall. The cost of construction was $205,000. 


(Continued) 


53 


Table 25 (Concluded) 


Date(s) Construction and Rehabilitation History 


1937- Damages to the Christina south jetty, caused by ships colliding 

1939, with it, were repaired each of these years at a total cost 

1948 of $90,000. 

1961 The landward 500 ft of the Christina south jetty was removed to ac- 
commodate marine terminal expansion. The total length of the jetty 
was 1,800 ft. 

1962 275 ft of buttressed steel sheet-pile wall failed during an extremely 


low tide and was eventually repaired. 


1985 The Christina south jetty is in good condition. 


NEW CASTLE COUNTY 


oo (gascune) BS 


ot I es 


U.S.Gour 


Wee 


SCALE OF FEET 


Figure 31. Wilmington Harbor, Delaware 


54 


Table 26 


Delaware River and Chesapeake Bay Canal Jetties 
Reedy Point, Delaware 
Philadelphia District 


Date(s) Construction and Rehabilitation History 


1903 Construction of two rubble-mound jetties, north and south of the 
canal, was completed to provide channel protection. The length of 
each jetty was 725 ft, crest elevations were +8.0 ft mlw, crown 
widths were 6.0 ft, and side slopes were 1:1 (Figure 32). 


1938 Each jetty was extended to 2,095 ft (Figure 32). 


1960's The south jetty was removed and replaced by a new jetty to increase 
the entrance size to accommodate larger vessels and to improve 
navigation safety. The new jetty had a crest elevation of +8.0 ft 
mlw and a 14.0-ft crown width (Figure 32). The design wave was 
6.3 ft, 4.8 sec. 


1985 The north jetty has subsided, lost stone, and the toe has scoured. 


aD 


Bulkhead 


BACON 


HEALTH CENTER 


HWY. BR. 
(FIXED) 2 LANES 


South Jett, 


SCALE OF FEET 
600 2 600 3200 


MHW 6.0-4__ r= EL+8.0 


CAPSTONE 14.0 CAPSTONE 
MLW (aeciesl 
CORESTONE, | p= EETBION CORESTONE 


XMATSTONE—’ 
ORIGINAL CROSS SECTION 


NEW SOUTH JETTY CROSS SECTION 


Figure 32. Delaware River and Chesapeake Bay Canal, Delaware 


56 


Table 27 


Smyrna River Jetties, Kent County, Delaware 
Philadelphia District 


Date(s) Construction and Rehabilitation History 

1939 Two parallel stone-filled timber crib jetties were constructed to 
provide channel protection. The north jetty was 803 ft, and original 
plans called for the south jetty to be 2,700 ft; however, project 
maps indicate it was approximately 2,000 ft (Figure 33). 


1986 There is no records of repairs. The project has been deauthorized. 


NEW CASTLE 
COUNTY 


Landing 


KENT COUNTY ) 


Brick Store 
Landing 


Upstream limit of 
Federal Project 


Smyrna Ldg Ris 
Prices Ldg. a 
\\ 


SCALE OF FEET 


5000 2) 3000 
———— 


Figure 33. Smyrna River, Delaware 


57 


Date(s) 


Table 28 


Mispillion River Jetties 
Kent and Sussex Counties, Delaware 


Philadelphia District 


Construction and Rehabilitation History 


1859 


1879 


1896 


1897 
1899 


1901 


1904 


1907 


1908 


1911 


A 560-ft-long jetty was constructed by local interests north of the 
entrance. The jetty was installed by placing a row of close-fitting 
piling and brush. 


The jetty had deteriorated considerably, and the Federal government 
made repairs. 


A 350-ft-long stone-filled timber crib dike was constructed on the 
west side of the new channel. 


The jetty was extended shoreward 200 ft at a cost of $1,600. 


Repairs were made to 141 ft of the 1897 extension at the seaward end 
at a cost of $506. 


The stone-filled timber crib dike had become a channel obstruction 
and was removed. 


The jetty was extended 805 ft shoreward by placing stone over brush- 
filled pile and timber crib. The extension was 12.0 ft wide with 
pile elevations of +11.0 ft mlw and stone elevations of +8.0 ft mlw. 
The gap between the extension and the existing jetty ends was filled 
with 313 cu yd of stone. 


The jetty was extended 85 ft shoreward at a cost of $870, using 1904 
construction geometry. The extension was classified as repairs. 


Repairs were made to 68 ft of the jetty damaged by a storm on Jan- 
uary 11, 1908. A jetty was constructed south of the entrance and 
parallel to the north jetty. The south jetty was 3,300 ft long and 
was constructed by placing stone over brush-filled pile and timber 
erib for 2,200 ft, and over an existing 1,100-ft-long bulkhead. The 
jetty was 6.0 ft wide with pile elevations of +7.0 ft mlw and stone 
elevations of +5.5 ft mlw. The north and south jetties were separ- 
ated by 210 ft. Costs of repairs and new construction were $22,770 
and $350,000, respectively. The locations of the jetties are shown 
in Figure 34. 


The south jetty was extended 1,800 ft at a cost of $18,431 using 1904 
construction geometry. Repairs were made to the south jetty by fill- 
ing settled sections with 96 cu yd of stone. The cost was $18,431 
for extension and $384 for repairs. 


(Continued) 


58 


Date(s) 


Table 28 (Continued) 


Construction and Rehabilitation History 


1912, 
1913, 
1914 


1915 


1920 


1939 
1944 


1948 


1963 


1964 


The north jetty was extended 400 ft seaward in each of these years 
(1,200-ft total) at a cost of $4,940, $4,800, and $5,000, respec- 
tively. Extensions were 6.0 ft wide with +7.0-ft mlw pile elevations 
and +5.5-ft mlw stone elevations. 


Both jetties were repaired by adding or replacing broken and decayed 
timber or piling, and a preservative was applied to tops of piles. 
Stone was placed to fill settled sections. The cost of repairs was 


Somsnier 


The south jetty was extended 700 ft to a total length of 5,800 ft 
using the same type of construction and geometry as the existing 
jetty. Both jetties were repaired in the same manner as the 1915 
repairs. Costs of repairs and the extension were $2,422 and $26,033, 
respectively. 


The north jetty was extended 3,500 ft seaward at a cost of $129,140, 
using 1912-1914 construction geometry. 


Tops of piles were coated with tar on the north jetty near the river 
mouth at a cost of $320. 


The north jetty was repaired beginning 708 ft from the shoreward end 
and extending 942 ft seaward. The original timber crib section was 

rehabilitated to a rubble-mound structure (Figure 34). The cost of 

repairs was $51,493, and 4,870 tons of stone were used. 


A survey of the north jetty indicated there was no visible trace of 
the shoreward 708 ft. The total length of the existing jetty was 
5,642 ft. The shoreward, rubble-mound, end had an average height of 
+6.2 ft mlw. The 1,200-ft-long timber crib structure adjacent to the 
rubble-mound section had deteriorated. Upper crib work was virtually 
nonexistent, and tops of piles were rotted or broken off. Stone had 
settled an average of 2.8 ft from design, was displaced, and had 
spilled out between piles. Piles, tie rods, and wales in the most 
seaward 3,500 ft appeared to be in good condition. Stone had settled 
an average of 1.5 ft in this section. 


Minor rehabilitation was done on the north jetty at a cost of 
$377,848. The 1,200-ft-long deteriorated timber crib section was 
rehabilitated to a rubble-mound structure. The center line of the 
rubble-mound structure was placed north of the center line of the 
timber crib jetty to prevent failure of the jetty on the channel side 
due to lateral forces. The offset was 11.0 ft over a distance of 
650 ft and 9.0 ft over a distance of 400 ft, shoreward and seaward 
ends of the section, respectively. Transition sections were on 
either end of the new structure and between the two offset sections. 
Crest elevation was +7.0 ft mlw, crown width was 10.0 ft, and side 
slopes were 1V:1.5H. Twenty-five ton minimum capstone was placed 
over 1- to 50-lb matstone. A layer of willow matting, compressed in 


(Continued) 


59 


Table 28 (Concluded) 


Date(s) Construction and Rehabilitation History 


1964 place to 1.5 ft thick, was provided as a filter. Core stone, 25 to 

(Cont.) 500 1b, was placed on the channel side of the existing jetty ata 
slope of 1V:1H to 1V:1.5H to ensure stability of the rubble-mound 
structure. The 3,500-ft-long timber crib on the seaward end of the 
jetty was filled with core stone, 150 to 300 lb, to the original de- 
sign elevation of +5.5 ft mlw. Cross sections of the rehabilitation 
are shown in Figure 35. 


1985 The jetties are in good condition and have been effective in pro- 
viding safe navigation and preventing channel shoaling. 


9/ autes to Pritodelphra 


SUSSEX COUNTY 
Mwy. ORIDGE ( FIXED) 


DELAWARE 


SCALE OF FEET 
20000 2 4 6 810000 


STONE TO BE PLACED 
IN INNER END OF 
NORTH JETTY 


EXISTING TIMBER PILES 
ROTTED OFF AT EL*3.0 <4 


SECTION AT STA. I*+50 


Figure 34. Mispillion River, Delaware 


60 


& | @ EXISTING JETTY 
+10F +10 
APPROX. +7.0 FEET MLW 
15 MecrosriNG TIMBER PILING (BADLY DETERIORATED) 
6.0 
HA si 
Or Beil 0ZZ wey Suede o 
CORE STONE 
BRUSH MAT MAT STONE 
EXISTING GROUND 

3 EXISTING TIMBER CRIB JETTY bara wi Lig 

10k 
SHOREWARD SECTION 
£ ISTING JETTY 
+o ROAERERIS +0 
APPROX. *+7.0 FEET MLW 
60 EXISTING TIMBER PILING (BADLY DETERIORATED) 
CHANNEL SIDE 
Oj— 30 Z— MAT STONE -—--— : CORE STONE mic 
| MAT STONE 
_- EXISTING GROUND 
ey aN 
EXISTING TIMBER CRIB JETTY 

“a “10 


SEAWARD SECTION 


SCALE _IN FEET 


10 5 (0) 10 20 
a 


Gaar| 
@ FILL TO EL+5.5 mac 
EL +5.5 CHANNEL SIDE | 
PILI —_-—-—~ 
EXISTING TIMBER PILING neReceONE | 
52 | N 40 
Seiad pop Le CAPA AM Wen & 
EXISTING GROUND 
Ae be | 
| 
EXISTING STONE FILL is 


TYPICAL SECTION 
__TIMBER CRIB 


SCALE _IN FEET 
10 : Q 19 20 
Figure 35. Cross sections of 1964 rehabilitation 
of Mispillion River jetties 


Date(s) 


1908 


1911- 
1914 
1917, 
1920, 
1923 


1937 


1939 
1944 


1985 


Table 29 


Roosevelt Inlet Jetty 
Lewes, Delaware 


Philadelphia District 


Construction and Rehabilitation History 


A 1,263-ft-long stone-filled timber crib jetty was constructed on the 
west side of the inlet. 


Stone replacement repairs were made each of these years. Cause 
of damage was due to inadequate jetty design; waves easily damaged 
the timber cribs. The cribs were also permeable to sand. 


The timber crib jetty was replaced by two steel sheet-pile jetties, 
constructed 500 ft apart, on the east and west sides of the inlet. 
Both jetties were 1,700 ft long (Figure 36). Crest elevations were 
+8.0 ft mlw, except the shoreward ends which were +10.0 ft mlw. 


The jetties had deteriorated due to corrosion. 


The jetties were flanked and rubble was placed along the east bank. 
The additional rubble extended the east jetty shoreward 400 ft. The 
possibility of the west jetty becoming completely flanked was 
determined to be remote; therefore, no rubble was placed on the west 
bank. Seaward ends of both jetties were repaired due to 
deterioration by corrosion. 


The jetties are in poor condition and are ineffective. They are 
considered a navigation hazard and are to be removed. 


62 


4 
WEST JETTY LIGHT © 

D SEAST JETTY LIGHT 
a 


Oc.G. LEWES 


yy ‘ 
LES 
OC 
SOM ‘ 


SS 
Oy 


’ 
% 


SCALE IN FEET 
000 ) 1000 _2000 
La a wn wn] 


Figure 36. Roosevelt Inlet, Delaware 


63 


Date(s) 


1898 


1901 


1985 


Table 30 


Delaware Bay Harbor of Refuge Breakwaters 
Fort Miles 


, Delaware 


Construction and Rehabilitation History 


A 5,000-ft-long detached breakwater was completed to offer harbor 
protection from east-northeast storms. 


The structure was located 
2,800 ft west of Cape Henlopen and extended west-northwest (Fig- 
ure 37). 


The cost of construction was $2,790,000. 


Construction was completed on a second detached breakwater to provide 
harbor protection from northwest storms (Figure 37). 


The structure 
began at a point 6,000 ft north of Cape Henlopen and extended north- 
west 7,500 ft. 


The rubble-mound breakwater was constructed with 
1,475,276 tons of stone at a cost of $2,239,000. 


The breakwaters have no history of repairs and have survived remark- 
ably well. The structures are outdated and would not be repaired if 
damaged. 


They no longer serve their intended purpose because of 
changes in the shipping industry. 


(CE PIERS 


eee” 


ro) 
i 2) 
2 
VS BS N 
CZ =) 
I Vg aN iA 
< Nips: 
ee Bb 
ies 
° ey. & = 
a Sx + 
= 
D 
> a carers te coves’ he BREAKWATER 
=3 i we Cape Henlopen 
par eas Poe hy ¥ e ? 
a Ld sarvies ¥ ff 
TER 4 be 
= Pree S 
— — SSS Yy : Fort Miles ™m 
a Se > 
(@ASCULE) Os =z, Xe P= 
~~ /: 


Figure 37. 


Delaware Bay Harbor of Refuge, Delaware 


64 


Date(s) 


1882 


1883 


1886 


1922 
1924 


1930- 
1931 


1946 


1955 


1959 


1977 


IS = 
1982 


Table 31 


Manasquan Inlet Jetties 
Manasquan, New Jersey 
Philadelphia District 


Construction and Rehabilitation History 


A 1,515-ft-long timber jetty and dike was constructed north of the 
inlet. 


A timber jetty was constructed south of the inlet to a length of 
approximately 500 ft. 


The south jetty was flanked, and use of the inlet was seriously 
impaired. 


New timber jetties were constructed. 
The jetties were in a state of disrepair. 


Two rubble-mound jetties were constructed north and south of the 
inlet to replace the timber jetties and provide channel protection. 
The north jetty was 1,230 ft long, and the south jetty was 1,030 ft 
long. The jetties were spaced 400 ft apart and built to an elevation 
of +14 ft mlw, with a 12.0-ft crown width and side slopes of 1V:1.5H 
on the ocean side, and 1V:1H on the channel side (Figure 38). Cap- 
stone was 2.0 ton, and core stone ranged from 100 to 500 lb. 


Both jetties were rehabilitated using 5,190 tons of capstone, 
2,886 tons of corestone, and 628 cu yd of grout. The cost of 
rehabilitation was $56,778. 


The north jetty was rehabilitated using 5,400 tons of stone at a cost 
of $128,597. 


The south jetty was rehabilitated using 12.0-ton capstone at a cost 
of $67,048. 


The seaward 100 ft and 60 ft of the north and south jetties, respec- 
tively, were destroyed through continued displacement of armor stone 
and loss of structural integrity. The south jetty was damaged from 
the seaward end to 700 ft shoreward. Sand passed from the south 
jetty fillet through and over the jetty into the inlet. 


Both jetties were rehabilitated using dolosse. Sand and displaced 
stone were excavated and reshaped to design configuration before 
dolosse placement. Sixteen-ton dolosse were placed along the seaward 
400 ft on the north side of the south jetty, around the jetty head, 
and along the seaward 50 ft on the south side. The dolosse extended 
to -10 ft mlw on the channel side, with side slopes of 1V:2H, and 
front slopes of 1V:3H. The seaward 400 ft was concrete capped, 20 ft 
wide, and was built at an elevation of +14 ft mlw. Sixteen-ton 
dolosse were placed along the seaward 250 ft on the north side of the 
north jetty, around the jetty head, and along the seaward 90 ft on 


(Continued ) 


65 


Date(s) 


1979- 
1982 
(Cont. ) 


1985 


Table 31 (Concluded) 


Construction and Rehabilitation History 


the south side. The seaward 240 ft was concrete capped, 35 ft wide 
at the seaward end and 20 ft wide elsewhere. Capstone was placed 
shoreward of the dolosse section, 375 ft on the north side and crest, 
and 90 ft on the south side. Capstone size decreased in the shore- 
ward direction from 12.0 to 3.0 to 5.0 tons. Design wave height was 
25.0 ft. An aerial photograph of the rehabilitation is shown in 
Figure 39. 


The jetties were subjected to several storms after the 1982 rehabili- 
tation, including a design level storm in March 1984. Photogram- 
metric monitoring of the structures under the Monitoring of Completed 
Coastal Projects (MCCP) Program indicated the last rehabilitation of 
the jetties has been fully successful to date. 


66 


4 
N Sx ; 
ON a SS pennies = 
64 a) 
MONMOUTH Vrs rae $ Kk i 
p RR BR \> wy 
COUNTY Sia Sy bas = Ye Z 
§ AA ° 
c ( <Sancnonace o> cnannec 
2 12 FT. OEEP ne 8 
4 intet channel 
Y y /4 Ft deep to 
YY) Zr Yttem ianer end of 
EA el ER North ees 
= 
emt ‘ANCHORAGE Cs [SS 
(| 10 FT. DEEP 19 ACRES, 2, oal— > 
\ SS 
fs 3 >? KR 
i i >>. 2 
4, Caraaerg ‘S 
bo ain x 
Sees — ae 
INT PLEASANT BEACH acc 
re 
Sim & 
os 
n 3 
OCEAN ~ COUNTY 
VEW JERSEY 
/NTRACOASTAL 
WATERWAY 
(SEE (NOEX WAP a 
NO a7) Sy 
Upstream limit of 
Federal Project 
SCALE IN FEET 
1000 2000 


500_0 


POINT PLEASANT CANAL, FORMERLY BAYHEAD-MANASQUAN 
CANAL 


CAPSTONE 
CHANNEL SIDE 


CORESTONE 


Toe T 


ORIGINAL NORTH & SOUTH JETTY SECTION 


5 O 5 10 IS FEET 
ee Ee 


Manasquan River, New Jersey 


Figure 38. 


67 


SASS 


WHA 


SSS 


a aes 


1es 


pb 
b 
oO 
2) 
b 
oO 
4 
s 
Hs 
° 
Sd 
amb 
3 0 
low) 
Qed 
a 4 
S-d 
@ a 
= @ 
a 
GH oO 
oO & 
an 
Q. 00 
wo 
{<4 G> 
80 
ou 
ob ov 
ov 
awa 
ad 
lon) 
~ 
1) 
= 
2 
jolt) 
pian 


Fi 


68 


Date(s) 


1940 


1944 
1950 
1954 


1972- 
1974 


1985 


Table 32 


Barnegat Inlet Jetties 
Barnegat, New Jersey 
Philadelphia District 


Construction and Rehabilitation History 


Two converging stone jetties were constructed north and south of the 
inlet for channel protection. The north jetty was 4,675 ft long, and 
the south jetty was 2,820 ft long (Figure 40). Design crest eleva- 
tion was +2.0 ft mlw. 


The shoreward 100 ft of the south jetty was lowered. 
Repairs were made to the seaward end of the north jetty. 
Repairs were made to the shoreward portion of the south jetty. 


To prevent sand passing through and waves overtopping the north 
jetty, the shoreward 3,700 ft was raised to +8.0 ft mlw and made 
impermeable. The center line of the section repaired was offset 12.0 
ft toward the inlet from the existing section (Figure 40). 


Due to instability and continuous shoaling of the navigation channel, 
proposals are being considered to construct a new south jetty. Por- 
tions of the jetties have crest elevations of +10.0 ft mlw. These 
sections were probably built as part of repair work conducted in 1950 
and 1954. Figure 41 is an aerial photograph of the jetties in 1984. 


69 


07 —\ 
‘Sler ea 


OCEAN COUNTY 


Woretown 4 
— 
S le 
NI 
“, \3 
x 
S$ 
8 
Ni 
ls 
= 
: i 
w 
= a 
\§ > 
w 
— > 
= Ne 
F by 
= 2 
—~, 
= North Jerty S 
(Reised to pont 
+ 1235 ¢t. from oa 
= 
— 
= ~~ 
= v 
Ge ¢ Altered serty 
Existing Jetty ¢ 
| 16'-O"* /niet_sid@__§—_ 
| El 8 
5-0" — 6'-0O" Cap stone, five tons min 


Exist. grade, elevarion varies 
MLW E'00 


10'- 0" 
Excavarion~ 


— Core stone, (OO ro 1000 = 


yy L_ grade or El-/5' 
Mar stone 3 #* 10 50 4% 


TYPICAL SECTION 
RAISED NORTH JETTY 


NOT TO SCALE 


Figure 40. Barnegat Inlet, New Jersey 


70 


Figure 41. Photograph of Barnegat Inlet jetties 


al 


Table 33 


Double Creek Jetty 
Ocean County, New Jersey 
Philadelphia District 


Date(s) Construction and Rehabilitation Histor 


1912 A 550-ft-long timber pile jetty was constructed to provide channel 
control (Figure 42). 


1986 There is no repair history. 


COUNTY 


Shad Point 


—S 77 mii ry 
G 
a ’o Barnegat elie ne 
e 


y 7 We 
aes 


Figure 42. Double Creek, New Jersey 


T2 


Table 34 


Absecon Inlet Jetties 


Atlantic City, New Jersey 
Philadelphia District 


Date(s) Construction and Rehabilitation History 


1948 Construction began on a 3,727-ft-long jetty on the east side of the 
harbor for channel control. Crest elevation was +8.0 ft mlw. An 
800-ft-long groin served as a jetty on the west side of the harbor 
(Figure 43). 


1986 No repair or rehabilitation history is available. Figure 44 is an 
aerial photograph of the jetties in 1971. 


WZ Upstream limit of 
/ (Federo Project 
/ 


ATLANTIC 


| 


SCALE OF FEET 
SEs 4 


= —S—S—S 


Figure 43. Absecon Inlet, New Jersey 


is 


Figure 44. Photograph of Absecon Inlet jetties 


74 


Table 35 
Goshen Creek Jetties 


Cape May County, New Jersey 
Philadelphia District 


Date(s) Construction and Rehabilitation History 


1897 A 600-ft-long sheet-pile jetty was constructed south of the entrance 
to provide channel control. 


1898 The south jetty was extended shoreward to maintain the dredged 
channel. 
1899 The south jetty was repaired with brush and stone and extended to 


680 ft. A jetty was constructed north of the entrance, parallel to 
the south jetty, at a length of 680 ft (Figure 45). 


1986 The south jetty is now 1,800 ft long (Figure 45), but the date of the 
extension is unknown. No history is available on maintenance in this 
century, and the project is specified as inactive. 


é CAPE MAY 
mS 8 
z é 
g = COUNTY 
Ver 
ys J 
NE ; 
q 
g “SN 
Sy 
Q 


ete 


Figure 45. Goshen Creek, New Jersey 


15 


Date(s) 


1911 


1915 


1916 


1917 
1922 
1923 


1927 


1946 
1948 
1949 
1964 
1979 
1986 


Table 36 


Cold Spring Inlet Jetties 
Cape May County, New Jersey 
Philadelphia District 


Construction and Rehabilitation History 


Construction was completed on two parallel jetties 850 ft apart, on 
the east and west sides of the inlet. Lengths were approximately 
4,548 ft and 4,410 ft east and west, respectively (Figure 46). Crest 
elevations were +10 ft mlw, crown widths varied from 6.0 to 15.0 ft, 
and side slopes were generally 1V:1.5H. A total of 326,049 tons of 
stone was used. Shoreward wing lengths were 750 ft and 297 ft east 
and west, respectively. Wings of both jetties and the shoreward 
2,000 ft of the west jetty were constructed of stone-filled pile and 
timber. The remainder of the west jetty and the entire east jetty 
were rubble mound. 


Repairs were made by placing 8,497 tons of stone at a cost of 
$24,810. 


Repairs were made by placing 9,023 tons of stone at a cost of 
$31,816. 


Repairs were made by placing 1,500 tons of stone. 
An unknown quantity of stone was placed at a cost of $5,410. 


The seaward 368 ft of the west jetty was repaired with concrete 
blocks and stone. The shoreward 1,572 ft of the west jetty was 
grout-sealed. 


Repairs were made by placing 10,424 tons of stone at a cost of 
$63,884. 


Repairs were made by placing 519 tons of stone at a cost of $12,072. 
Dolphin and jetty repairs were made at a cost of $6,204. 

Repairs were made by placing 235 tons of stone at a cost of $3,416. 
Jetties were rehabilitated at a cost of $174,879. 

Jetties were rehabilitated at a cost of $197,891. 


No further repair information is available. Figure 47 is an aerial 
photograph of the jetties in 1982. 


76 


yw 


19 


——— oo 
Fix. 


£Qvwr ga > 


| Yp jee 


= 


tes Lg 
aRBOR 
mo 
P CAPE 
Scnelienger oa 
Se se \\ < 

i U.S. COAST & 
\ GUARD BASE 3 

De \ = 


(ale.o} >) = mn a 5000 
— 


Figure 46. Cold Spring Inlet, New Jersey 


Ut 


Figure 47. Photograph of Cold Spring Inlet jetties 


78 


Table 37 


Cape May Harbor to Delaware Bay Canal Jetties 
Cape May, New Jersey, Philadelphia District 


Date(s) Construction and Rehabilitation History 


1943 Two parallel jetties were constructed on either side of the entrance 
for channel protection (Figure 48). 


1986 No jetty repair information was found. Lengths of the jetties are 
approximately 600 ft and 700 ft north and south, respectively. 


Z ? 2 
=. 
a SCALE OF FEET 
EXTEND 8 STONE GROINS i000 0 1 2 3 4 5 6000 
2 or 


SCALE OF FEET 
2 coo 3000 


Figure 48. Cape May Harbor to Delaware Bay Canal, New Jersey 


vg 


Date(s) 


1939 


1956 
IG 


1985 


Table 38 
Indian River Inlet Jetties 


Indian River Inlet, Delaware 


Philadelphia District 


Construction and Rehabilitation History 


Two parallel jetties were completed to provide inlet protection. The 
jetties were 1,566 ft long and 500 ft apart. The shoreward 904 ft 
and 890 ft of the north and south jetties, respectively, were con- 
structed of steel sheet pile, and the seaward portions were con- 
structed of stone. The stone jetties had a crest elevation of 

+6.0 ft mlw, a crown width of 10.0 ft, and side slopes of 1V:1.5H 
(Figure 49). 


Storm damages to the south jetty were repaired. 


The north jetty was repaired because of storm damages and was ex- 
tended shoreward 320 ft because of shoreline recession and 
deterioration of the sheet pile (Figure 49). 


The jetty heads are in poor condition because of slope failure, sub- 
sidence, and toe scour. Repair alternatives have been proposed, and 
the use of dolosse has been suggested. Figure 50 is an aerial photo- 
graph of the jetties taken in 1985. 


80 


CAPSTONE 0 
CORESTONE 


MATSTONE STEEL SHEET 
PILING 


TYPICAL SECTION 
NTS 


CAP STONE 


CORESTONE 


MATSTONE 
PRESENT BOTTOM 


HALF SECTION-OUTER 300' OF JETTY 
NTS 


Figure 49. 


y 


oa 
Uy 


REHOBOTH 
BAY 


b 


ok 
OGEAN 


Bolders 
Pond ~ 


BOTTOM HILLS DRAIN 


§2Z 


: —=— AB 


US COAST GUARD STATION 


Burton 
talond 


INDIAN RIVER 


—— he INLET 
JETTIES 
a 


RIVER BAY 


DELAWARE SEASHORE 
STATE PARK 


ELEV 35° MHWw 


S 
| ~ 
i 
: & = 
x’ 3 e 
S : 
: N 
Tt 


SCALE OF MILES 
| 0 | 


NEW FILTER MATERIAL 
NEW FINISHED GRADE 
ELEVATION VARIES 


EXISTING CONCRETE WALK 

EXISTING HANDRAIL 

NEW INTERLOCKING CAPSTONE 
INLET SIDE 


EXISTING CAPSTONE 


EXISTING FILTER MATERIAL 
EXISTING SHEET PILING 


TYPICAL SECTION OF REHABILITATED BULKHEAD 
NTS 


Indian River Inlet, Delaware 


81 


Figure 50. 


| 
I 


ReMi 


Photograph of 


Indian River Inlet jetties 


82 


Date(s) 


1939 


1964 


1982 


1986 


Table 39 
Rock Hall Harbor Breakwaters 


Rock Hall, Maryland 
Baltimore District 


Construction and Rehabilitation History 


Two breakwaters were constructed with 8,400 tons of stone. Lengths 
of the breakwaters were 850 ft and 700 ft east and west, respectively 
(Figure 51). Elevations of the breakwaters were +4.0 ft mlw, with a 
single capstone, crown width of 4.0 ft, and side slopes of 1V:1.5H. 


Repairs were made on both breakwaters to restore them to original 
design geometry. The east breakwater was in good condition with 
crest subsidence of less than 0.5 ft. The majority of the repairs 
were made on the west breakwater. The landward 80 ft had subsided up 
to 2.0 ft, the seaward 50 ft had subsided to mlw, and the adjacent 
380 ft had subsided 1.0 to 2.5 ft. The landward ends of both break- 
waters were repaired with 250- to 500-lb stone. A 40-ft extension 
was added to the west breakwater (Figure 51), and the outer 220 ft, 
including the extension, were repaired with 1,000 to 2,000-lb cover 
and core stone. The adjacent 260 ft were raised by filling the 
existing section with additional core stone. 


Extensive rehabilitation was done to both breakwaters due to wave 
transmission and overtopping causing excessive wave heights (greater 
than 4.0 ft) in the inner harbor. Estimated cost of the rehabi- 
litation was $1,800,000 and required over 27,000 tons of stone. 
Crown elevation was raised to +7.0 ft mlw, crown width was widened 
to 8.0 ft with three capstones, and side slopes remained 1V:1.5H 
requiring 12,400 tons of stone. The west breakwater was extended 
to 1,100 ft requiring 14,800 tons of stone. Cover stone used for 
rehabilitation ranged from 2,300 lb at the trunk to 2,800 lb at the 
head. Cross sections and location of the rehabilitation are shown 
in Figure 52. 


No further repair or maintenance information has been found. 


83 


el 
“EY ROCK HALL 


eo 


COUNT Y 


WINOMILL Aw, 
POINT 
wl y 


SCALE OF FEET 


100 Oo 500 
ee oe ee 


Figure 51. Rock Hall Harbor, Maryland 


84 


JOQUeY TTPH Yooy ‘uoTAJeAYTTTGeyed 2g, JO SuOTJOaS SSOUD pue MATA UeTq “2G aun3Ty 


ee oat ® 
——— 


4284 wt D1V98 


YILVANVaUE LSVA 


aoosv3s GNv 
u3id 8.0uveann 


AVAATIVE JNIUVWY 
TiwH "30u 


02-..1 31v9S 
SNOISN31X3 H3LVMyV3H8 
SNOILD3S WOIdA! 


SNOT 14 08 
€ NOILD3S 


1400 = 


4 ta 


MW 00 A373 


MIW 14 0 14A313 


7 68Vs WIL 
Y3AV7 ONIDO3B & HOD aa 


OL/M UBAVIZ 
3NO18 Y3AVTE3ONN 


$81 0002 - OOE'2-m SYURAVIZ 
ANOLS BHONYY 


SNOT 14 SEI 
2 NOILO3S. 
DIMA A HAL WE 


139tt -———. 


ae 


WH38 ALIMBVIS 8 HO) 
ae an | Nes 


= 


MIW 1490/4 A373 


GAZ e 
= —— —_— OL/M SUIAWI 2 
em 3NOIS HIAVINIONN 


— SR100F 2 M SURAWTZ 
3NOLS HOWHY 


ONO114 Set 
' NON93S 


ig ay —- - 
owas 


u3Av1 ONIGO3a & ey CoN) 
131 — =I — OL/M SURIAWTE 


MW 00 A313 


NOLS B3AVIN30NN 
$61 OOE'2-M BUSAVIZ 


' 
mW HONOR —— <a EG aa 3NO1S HONUY 
13 


MIN 00 A313 


win 1400+ 0909 


02...t 39S 
ONISIVY H3LVMyv3He 
NOILD3S WOI!dAL 
§¥3AV7 ONIGGIS 


O1/M U3AVTE 
3NO1S B3AVIN30NN 


07 006 2M UaAVT I 
3NO1S HOMUY 


85 


Date(s) 


Table 40 


Claiborne Harbor Jetty 


Claiborne, Maryland 
Baltimore District 


Construction and Rehabilitation History A 


1888 


1912 


1928 


1970's 


1978 
1981 
1986 


A 750-ft-long slag jetty was constructed by a railway company at 
Claiborne Harbor. 


The jetty was extended 250 ft seaward as part of the federal project 
and was constructed of timber piles (Figure 53). 


The timber pile extension was in poor condition and was missing a 
seaward section. 


The jetty was repaired, and revetment was placed around the jetty and 
wharf area of the harbor by non-Federal interests. 


A report recommended removal of deteriorated timber piles. 
A survey indicated the jetty was in excellent condition. 


Plans are complete for jetty rehabilitation. No details are 
available. 


86 


A 


y 


Figure 53. 


SCALE OF FEET 
[Ore y es es es 


Claiborne Harbor, Maryland 


87 


< 
w 
eo b \ 
co . 
CRoMaNCcOKE sa 
FERRY PIER XK 


y Ab =8—@. 1 


100 O soo 


Le 
a TAA 


Table 41 
Back Creek Jetty, Anne Arundel County, Maryland 


Baltimore District 
Date(s) Construction and Rehabilitation History 


1938- A 650-ft-long jetty was constructed to a crest elevation of +4.0 ft 


1939 mlw (Figure 54). Crown width was 4.0 ft with a single capstone, and 
Side slopes were 1V:2H. 


1981 A survey indicated the jetty was in very good condition. 
1986 


No further repair or maintenance information has been found. 


HORM POINT 


EASTPORT 
* 


SCALE OF FEET 
jf Sp hdeg 


Figure 54. Back Creek, Maryland 


88 


Table 42 


Herring Bay and Rockhold Creek Breakwater 
Anne Arundel County, Maryland 
Baltimore District 
Date(s) 


Construction and Rehabilitation History 
1939- 


A 900-ft-long stone breakwater was constructed to a crown elevation 
1940 of +4.0 ft mlw (Figure 55). Crown width was 4.0 ft, and side slopes 
were 1V:1.5H. 
1981 A survey indicated that the structure was in good condition with very 
little subsidence. 
1986 


No further repair or maintenance information has been found. 


ANNE 


4 6 
ses Fly 


NUTWELL 


g10HH904 


2 
8 
8 
8 


Figure 55. Herring Bay and Rockhold Creek, Maryland 


89 


Table 43 


Fishing Creek Jetties, Calvert County, Maryland 
Baltimore District 


Date(s) Construction and Rehabilitation History 


1941- Two converging stone jetties were constructed to lengths of 1,050 and 
1942 1,100 ft north and south, respectively (Figure 56). Crown elevation 
was +4.0 ft mlw, crown width was 4.0 ft, and side slopes were 
UWS teBlals 
1981 A survey revealed that both jetties were in good condition with minor 


settlement and some displaced stone. 


1985 Plans call for sand tightening of the jetties with 2,100 to 3,500 1b 
of cover stone, 20 to 100 1b of core stone, and 1.0 to 20 lb of bed- 
ding stone. 


CHESAPEAKE BEACH 
GALVERT COUNTY 


SCALE OF FEET 
° 


Figure 56. Fishing Creek, Maryland 


90 


Table 44 


Tilghman Island Breakwater 
Talbot County, Maryland 


Baltimore District 


Construction and Rehabilitation History 


Date(s) 


1981 


1986 


A 200-ft-long breakwater was constructed at an estimated cost of 
$140,000 with 1,750 tons of stone to reduce wave action in the inner 
harbor area (Figure 57). Crown elevation was +6.0 ft mlw and allowed 
for expected settling to +5.0 ft mlw. Crown width was 6.0 ft, and 
side slopes were 1V:1.5H. The structure consisted of two layers of 
armor stone, 750 to 1,200 1b and 70 to 130 lb, and a 1- to 50-1b core 
and bedding layer. Design wave height and period were 2.3 ft and 

4.0 sec. 


No further repair or maintenance information has been found. 


91 


sl¥uVH 


NEEL (o 


pueT Arey 


& 


Z#NOOVSE 
gay 


(uojoeg seyemysag punow e1qqny 1891041) 


S17 0S-t=M 
ONIdG3d ¥ SHOO/ NOILVONNOJ TivdS XOOU 


MW 00 ‘A313 
4 BNOLS HAAVIWIONN 


$81 00Z1-0SZ=M 'SUAAVT Z 


MIA 09+ * 
YEN) @ 3NOLS HONEY 


‘pueTs] uewystt ys 


av3aHyine 


uojye007 JayeMyHesJIg 


"LG aan3ty 


e 
oo 
INZWANOW 
31L3Y9NO9 


QV3H Ing 


€€ eINOY e)2B)5 


92 


Date(s) 


1960 


1985 


Table 45 


Nanticoke River at Bivalve Jetties 


Wicomico County, Maryland 
Baltimore District 


Construction and Rehabilitation History 


Two jetties were constructed at lengths of 1,050 ft each and spaced 
400 ft apart (Figure 58). Crown elevation was +4.0 ft mlw, crown 
width was 4.0 ft with a single capstone, and side slopes were 1V:2H. 
Minimum coverstone weight was 1.5 tons, and corestone ranged from 15 
to 500 1b with a 1.0-ft-thick bedding layer. Design wave height was 
7.0 ft. 


Both jetties are in excellent condition; however, present shoaling in 
the channel may be due to sand passing through the jetties. 


STONE JETTIES +40'—~ 


SS 
“WIC OMI C O 


seoatc, 


(WN We 


SCALE OF FEET 
TO “a 9 = | 


Figure 58. Nanticoke River at Bivalve, Maryland 


93 


Date(s) 


1938 


1944 
1981 
1986 


Table 46 
Nanticoke River at Nanticoke Jetties 


Nanticoke, Maryland 
Baltimore District 


Construction and Rehabilitation History 


Two converging stone jetties were constructed at lengths of 850 ft 
and 750 ft north and south, respectively (Figure 59). Crown eleva- 
tion was +5.0 ft mlw, crown width was 4.0 ft, with a single capstone, 
and side slopes were 1V:1.5H. A post-construction survey showed lit- 
tle deviation from the design elevation. 


A survey of the jetties indicated little change in crown elevation. 
A survey indicated both jetties were in excellent condition. 


No further repair or maintenance information has been found. 


ves ie 
a 
| of 
6 
‘ \ 
Shaw 
ve 


ROARING POINT 


4 
4 4 
i vi 
4 I \ 
4 Y) 
y 
/ 


Zo mts 


SCALE OF FEE? 
190.9 300 


Figure 59. Nanticoke River at Nanticoke, Maryland 


94 


Date(s) 


Table 47 


Upper Thorofare Breakwaters 


Deal Island, Maryland 
Baltimore District 


Construction and Rehabilitation History 


1934 


1966 


1981 


1986 


Two stone breakwaters were constructed with 3,650 tons of stone at an 
estimated cost of $9,000. The north breakwater was 410 ft long. The 
south breakwater was 310 ft long. The seaward ends were 180 ft apart 
(Figure 60). Crest elevations were +7.0 ft mlw, except the landward 
142 ft of the south breakwater which was from +5.0 to +6.5 mlw. 

Crown width was 4.0 ft, and side slopes were 1:1. 


Sand had accumulated around one-half to two-thirds of the landward 
end of the north breakwater. The south breakwater had an average 
subsidence of 2.0 ft and was repaired to raise the elevation to 
+7.0 ft mlw. Crown width was 4.0 ft, and side slopes were 1V:1.5H. 


A survey indicated the south breakwater was in excellent condition, 
although the midsection appeared to have subsided 1.0 ft. The north 
breakwater was almost completely surrounded by sand, and future 
shoaling of the channel was foreseen. The north breakwater appeared 
to have subsided 1.0 ft from the original design elevation. 


No further repair or maintenance information has been found. 


95 


STONE BREAKWATER 


ot 


DEAL 
PT. 


STONE BREAKWATER 


COUNTY 


& 
Wy 
S 
= 
I 
K 


ISLAND 


SCALE OF FEET 
te} ' 


Figure 60. Upper Thorofare, Maryland 


96 


Date(s) 


1940 


1945 


1952 


1955- 
1956 


1962 


Table 48 


Twitch Cove and Big Thorofare River Jetties 
Somerset County, Maryland 


Baltimore District 


Construction and Rehabilitation History 


Two converging stone jetties were constructed with 23,000 tons of 
stone at a cost of $112,000 (Figure 61). The north jetty was 

2,070 ft long, and the south jetty was 1,800 ft long. The design 
section included a crown elevation of +4.0 ft mlw, a crown width of 
2.0 ft with the exception of the seaward 120 ft of the north jetty 
which was 4.0 ft, and side slopes of 1V:2H, except for the bay side 
of the north jetty which was designed for 1:1 along the landward 
1,950 ft. No stone size details were given; however, a 1981 survey 
indicated the side slope stone was approximately 1.5 tons, and the 
core was of similar stone. The survey also revealed the single cap- 
stone ranged from 2.0 to 3.0 tons. No apron or bedding was placed 
during construction or subsequent repairs. 


A condition survey was performed which indicated the north jetty was 
in a severe state of deterioration. The seaward 1,300 ft of this 
jetty had a typical subsidence of 0.5 ft below the original eleva- 
tion, and the seaward 300 ft of this section had a range of subsid- 
ence of 2.0 to 4.0 ft. The south jetty was flanked, and the seaward 
400 ft of the south jetty had subsided 0.5 to 1.5 ft. The seaward 
end of this section had subsided below mlw. Toe areas had scoured 
from -5.0 to -7.0 ft mlw. 


A condition survey was made on the north jetty. The seaward 570 ft 
had a range of subsidence from 2.0 to 5.0 ft, and 700 ft landward of 
this section had subsided 1.0 to 2.0 ft. Jetty cross sections indi- 
cated most of the subsidence occurred on the bay side. Repairs were 
made to the seaward 1,030 ft of the north jetty using original design 
geometry to raise the crest elevation to +3.0 ft mlw. The cost of 
the repairs and dredging was $33,000. 


A condition survey performed on the south jetty indicated an aver- 
age subsidence of 0.5 ft over the entire length. The seaward 300 ft 
had subsided 2.0 to 4.0 ft, and a length of 80 ft had subsided near 
the landward end. Areas of subsidence were typically 1.0 to 2.0 ft 
below adjacent sections. Repair work began in 1956 to raise the 
crest elevation to +3.5 ft mlw using original design geometry. Ap- 
proximately 1,000 tons of stone were used at a cost of about $35,000 
which included dredging. Toe areas had scoured to -9.0 ft mlw. 


Both jetties were surveyed and repaired with 2,200 tons of stone for 
approximately $64,500. The north jetty had been flanked on the 
landward end, and elevations of the seaward 520 ft ranged from +1.0 
to +3.0 ft mlw. The seaward 180 ft of the south jetty had elevations 
ranging from 0.0 to +4.0 ft mlw. The above sections were repaired to 


(Continued) 


97 


CAH ER Se Al PIETAKKOEs 


4INIOd 
\ TSNNVHS 


s3liLiar 
3NOLS 


: 
s 
x J 


© 000! 
31Vv9s 

9N0I 

HOLIML 


+ 


0002 OOO! 


TANG/ER 


Figure 61. Twitch Cove and Big Thorofare River, Maryland 


98 


Date(s) 


1962 
(Cont. ) 


1981 


1986 


Table 48 (Concluded) 


Construction and Rehabilitation History 


a crown elevation of +4.0 ft mlw, with a 2.0-ft crown width, except 
the seaward 70 ft of the north jetty was 4.0 ft. The side slopes 
were 1V:2H. The landward end of the north jetty was extended 120 ft. 
Voids along the remainder of the jetties were repaired by placing and 
resetting existing stone at existing section elevations. The depth 
at the toes of the jetties ranged from 10.0 to 12.0 ft mlw. 


A survey report indicates both jetties are in "poor" condition. The 
seaward end of the north jetty and the landward ends of both jetties 
were flanked, and there were numerous areas of subsidence along their 
lengths. It is believed that scour is the reason for their 
deterioration for the following reasons: 


-- Existence of a homogeneous cross section (no smaller core placed). 


-- No bedding stone or apron stone being placed during original 
construction or during repairs. 


-- Increase in depth from a range of 5.0 to 6.0 ft to a range of 10.0 
to 12.0 ft mlw at the seaward ends. 


-- Landward ends of the jetties being flanked at present. Each has 
been flanked once and repaired since original construction. 


-- General susidence along the entire lengths of the jetties of 0.5 
to 1.0 ft. 


-- Numerous voids or gaps where capstones were missing. 


No further repair or maintenance information has been found. 


99 


Date(s) 


1934 


1935 


USES 


1956 


1963 


1984 


Table 49 


Ocean City Inlet Jetties 


Ocean City, Maryland 
Baltimore District 


Construction and Rehabilitation History 


A 1,100-ft-long jetty was constructed on the north side of a newly 
formed inlet at Ocean City (Figure 62). Crest elevation was +4.0 
mlw, crown width was 12.0 ft, and side slopes were 1V:2H from the 
crest to -4.0 mlw and 1V:1.5H from -4.0 mlw to the bottom. 


Construction was completed on a jetty on the south side of the inlet. 
Crest elevation was +6.0 ft mlw, and crown width was 12.0 ft. The 
landward 750 ft of the jetty was 1,100 ft south of the north jetty. 
The south jetty angled north 1,100 ft to a point 600 ft from the 
north jetty. The final 530 ft of the south jetty was parallel to 
that of the north jetty. The crest elevation decreased from +6.0 ft 
mlw to the apron elevation beginning 170 ft seaward of this final 
section. The apron extended 200 ft farther seaward. The total 
length of the jetty was 2,380 ft, including the apron. A total of 
39,500 tons of stone was used for core; 17,300 tons were used for 
capstone on the south jetty. 


Sand on the north side of the north jetty had reached the top of the 
jetty and was depositing in the inlet. A concrete superstructure was 
built to raise the jetty elevation. The first 100 ft from the 
boardwalk was raised to +12.0 ft mlw, the next 254 ft was raised to 
+9.0 ft, and the next 170 ft was raised to +7.0 ft mlw. 


Repairs were made on the seaward 750 ft of the north jetty because of 
slope failures on the channel side from toe scour. The existing con- 
crete cap was repaired and raised to +9.0 ft. Armor stone was placed 
on the seaward 575 ft. The armor stone section was placed 26 ft 
north of the center line to use existing stone as toe protection and 
to minimize the stone required. The landward end of the south jetty 
was repaired to maintain integrity with the shoreline. 


Approximately 720 ft of the south jetty was rehabilitated due to 
slope failures caused by a scour hole that had an elevation of -37 ft 
mlw. Armor stone was placed 25 ft seaward of the center line for the 
same reasons stated above in positioning the north jetty. The land- 
ward end of the south jetty was again repaired to maintain integrity 
with the shoreline. 


The seaward 1,100 ft of the south jetty was rehabilitated due to 
slope failures. The section repaired in 1963 had deteriorated. The 
scour hole had a maximum depth of -54 ft mlw. Repairs consisted of 
filling the scour hole with dredged material to -20 ft mlw, covering 
the hole with 18 in. of blanket stone, and placing stone berm quarry 
run and armor stone along the toe on the channel side of the 


(Continued) 


100 


Date(s) 


1984 
(Cont. ) 


1986 


Table 49 (Concluded) 


Construction and Rehabilitation History 


existing jetty. The landward end of the south jetty was sand tight- 
ened to prevent material from passing through the jetty and shoaling 
into the channel. Three rubble mound breakwaters were constructed 
landward of the jetty to prevent expected erosion from occurring as a 
result of sand tightening. 


No further repair or maintenance information has been found. 


HOR. CL. 70° 
VERT. CL. 16" 
ORAWARIDGE 


STNEPUXENT | /f* 


MARYLAND 


ORIGINAL CROSS SECTION 
T_T 
OCEAN SIDE 


SCALE OF FEET 
1000 300 ° 


CAP STONE: 6TON 
MIN. ABOVE -9.0; 
| CORE 
15 #TO 2 TON 
‘ ae 
ORIGINAL 
JETTY 


FILTER; RUN OF 
CRUSHER STONE 


1956 NORTH JETTY REPAIR 


OCEAN SIDE 


CAPSTONE, 
9 TON MIN 


“ELEVATIONS IN FEET SS 


CZ Oe 
REFERRED TO MLW Ly tye C, 


1963 SOUTH JETTY REPAIR 
EXISTING 
Y 


150" 
6&0TO 100 TON STONE 
MIN EL FOR TOP OF ARMOR STONE [-3.0) fae 


2670 10—> -ho OCEAN SIDE 
TON STONE 1+ FILTER FABRIC 


1983 SOUTH JETTY REPAIR 


Figure 62. Ocean City Inlet, Maryland 


101 


Date(s) 


Table 50 
Colonial Beach Breakwaters 


Colonial Beach, Virginia 
Baltimore District 


Construction and Rehabilitation History 


1982 


1985 


Seven offshore breakwaters were constructed as part of a beach 
restoration project for approximately $447,000, using over 9,000 tons 
of stone (Figure 63). One 300-ft breakwater and two 200-ft break- 
waters were placed at Castlewood Beach, and four 200-ft breakwaters 
were placed at Central Beach. All were placed parallel to the shore- 
line and approximately 100 ft offshore, and they were separated by 
150-ft gaps. Crest elevations were +3.0 ft mlw but allowed for set- 
tlement to +2.0 ft mlw. Crown widths were 6.0 ft, and side slopes 
were 1V:1.5H. One layer of 2,000-lb cover stone was placed over one 
layer of 500-1lb underlayer resting on a core and 1 ft bedding layer. 
Design wave height was 6.0 ft. 


The breakwaters are in excellent condition and serving their intended 
function. 


102 


SIUTSITA ‘yoRag 


31v9S OL LON 
V3auv HOV3E WYVd GOOMIAILSVD 


NOILIIS TWWOIIdAL 
QUOJSJOW YJDOUEQ |/0S NyIsUI UO Ped0)d I1NqQ04 J24I14 
NEI NIGU 39 GNV_ 3JYOI) JNOLSLYW Ol-----—----** 


(Y3Av7 | —pNoss 8 00s 
3NOLS us waONN ITS. SNOLS 81 0002 67; WW 


S 
(43AV7 1) NOLS YONYY og—e=! MIW 140° 


31VIS OL LON 
v3¥uV HOV38 IWYLN3ZO 
NOILISS = WWOIIdAL 


(Y3AV1 1) NOLS YOWNY 


le 9'9—=] MINIS O72 


TeTUOTO) 


"€9 aun3tTy 


SYSLVMAVING 


HOvae YW ee 


GOOM3TISVD — 7 =; 


SuaLVMV3ua : 
Hdv3a9g \\ 
WYLN3D) —e \ . 


\\:. 


03 


1 


Table 51 


Nomini Bay and Creek Jetty 
Westmoreland County, Virginia 
Baltimore District 


Date(s) Construction and Rehabilitation History 

1912 A 2,410-ft-long stone jetty was completed (Figure 64). 

1981 A survey indicated the jetty was in good condition. 

1986 No further repair or maintenance information has been found. 


Elbow Point 


‘White Oak Point 


Hickory Point 


WESTMORELAND 


COUNTY 


fT HOLLY 
/— Draw Bridge 


Figure 64. Nomini Bay and Creek, Virginia 


104 


Date(s) 


1968 


1981 


1986 


Table 52 
Bonum Creek Jetties 


Westmoreland County, Virginia 
Baltimore District 


Construction and Rehabilitation History 


Construction was completed on two stone jetties at an estimated cost 
of $221,000 using 8,000 tons of stone. The north jetty was 800 ft 
long, and the south jetty was 300 ft long (Figure 65). Crown eleva- 
tion was +4.0 ft mlw, crown width was 4.0 ft with a single capstone, 
and side slopes were 1V:2H. Cover stone used was 2.5 tons, and core 
stone ranged from 25 to 500 lb. Design wave height was 9.0 ft. 


A condition survey revealed that the jetties had undergone some set- 
tlement but were in good condition. 


No further repair or maintenance information has been found. 


25LBS TO 5OOLBS 
CORE MATERIAL 


25 TON MIN. 2 
CAP STONES 'C77 


VARIABLE BOTTOM FILTER BLANKET 


TYPICAL JETTY SECTION ss 


SCALE OF FEET : 7) 
° 5 10 By 
irewere rareere | rn 


WESTMORELAND.) (~ <<" COUNTY 


SCALE OF FEET 
woo + & 3 4 300 


Figure 65. Bonum Creek, Virginia 


105 


Table 53 


Herring Creek Jetties 


St. Marys County, Maryland 
Baltimore District 


Date(s) Construction and Rehabilitation Histor 
1960- Two jetties were constructed to 750- and 700-ft lengths north and 
1961 south, respectively (Figure 66). Crown elevation was +4.5 ft mlw, 


crown width was 4.0 ft, and side slopes were 1V:2.5H. A 1.0-ft-thick 
bedding layer was placed, and a 1.0-ft-thick by 10.0-ft-wide apron 
was placed along both jetty toes. 


1981 A survey indicated the jetties were in good condition with only minor 
settlement. 
1986 No further repair or maintenance information has been found. 


. MARYS 
COUNTY 


Free! 


Figure 66. Herring Creek, Maryland 


106 


Date(s) 


1937 


1970 
1981 


1985 


Table 54 


Little Wicomico River Jetties 


Norththumberland County, Virginia 
Baltimore District 


Construction and Rehabilitation History 


Two stone jetties were constructed to lengths of 1,000 and 1,300 ft 
north and south, respectively (Figure 67). Timber pile jetties were 
also placed at the landward ends of the stone jetties. Lengths of 
the timber piles were 357 ft north and 650 ft south. 


The north timber pile jetty was repaired at a cost of $51,822. 


Survey of the jetties indicated the seaward 300 ft of each jetty had 
crown elevations ranging from -2.0 to +6.0 ft and no semblance of a 
crown width. 


The jetties were to be rehabilitated to minimize shoaling of the fed- 
eral channel. The seaward 290 ft of each jetty was to be made sand 
tight by placing core stone and cover stone on the outer face at a 
1-V:1.5-H slope. Crown elevation was to be +4.0 ft mlw, with a crown 
width up to 15.0 ft along the sections with crown elevations below 
+4.0 ft mlw. Toe protection was to be provided by a 2.0-ft-thick by 
5.0-ft-wide extension of the core stone. A double layer of 1.0-ton 
cover stone was to be used. It is not known if the work was done. 


107 


#. 
Td) 
wars 


TYPICAL SECTION THROUGH JETTIES 
ANDO CHANNEL 
(NOT TO SCALE) 


NORTHUMBERLAND 


COUNTY 


SCALE OF FEET 


Figure 67. Little Wicomico River, Virginia 


108 


Table 55 
Urbanna Creek Jetties 


Urbanna, Virginia 
Norfolk District 


Date(s) Construction and Rehabilitation History 


1956 Two jetties were constructed for channel control. The north jetty, 
1,895 ft long, was rubble mound. The 717-ft-long south jetty was 
built of timber (Figure 68). 


1962 The north jetty was rehabilitated. 


1986 No further repair or maintenance information has been found. 


MIDDLESEX CO>™> 


Rosegill Farm 


SCALE IN FEET 
4 6 8-10 _ 1200 


Figure 68. Urbanna Creek, Virginia 


109 


Table 56 


Carters Creek Jetty, Crab Point, Virginia 
Norfolk District 


Construction and Rehabilitation History 


Date(s) 


1902- 
1906 


1986 


A 742-ft-long rubble-mound jetty was built to provide channel control 
(Figure 69). 


No further repair or maintenance information has been found. 


ae oe Humphreys 
x:, Marine Railway Inc. » 


/o\ RV INGTON 


Gallyhook Pt\:J 
accyene 
Branch 


ead 


Roce Ground Pt 


Bulkh 


| 
Pierhead Xe 
Line b-Butkheoa Line 


— Pierhead Line 


EVAN CHAR SHal Esk co. 


4, Pp 
7) 
P/ Ve, 
a 


SCALE IN FEET 
o 500 1000 1300 


Figure 69. Carters Creek, Virginia 


110 


Table 57 


Milford Haven Jetty 
Narrows Point, Virginia 
Norfolk District 


Date(s) Construction and Rehabilitation History 

1913 A 1,183-ft-long rubble-mound jetty was constructed to provide channel 
control (Figure 70). 

1986 


No further repair or maintenance information has been found. 


GWYNN 
ISLAND 


calls wrart.\ 


VE DRAW SPAN ~ 
\ G cteroene YEE EM 


SCALE IN FEET 
° t 


1000 3000 


Figure 70. Milford Haven, Virginia 


Date(s) 


1981 


1986 


Table 58 


Tylers Beach Jetties 


Isle of Wight County, Virginia 
Norfolk District 


Construction and Rehabilitation History 


Two parallel rubble-mound jetties were constructed to provide channel 
control. Both jetties were 370 ft in length and spaced 120 ft apart 
(Figure 71). Crest elevation was +5.0 ft mlw but allowed for 0.5 to 
1.0 settlement; crown width was 5.0 ft; and side slopes were 1V:2H. 
One layer of armor stone, 300 to 500 1b, was placed over one layer of 
core stone, 3.0 to 40 lb. The jetties rested on a 2.0-ft-thick sand 
blanket. The sand was encased by filter fabric. A 5.0-ft-wide, 
1.5-ft-thick apron and a 5.0-ft-wide, 3.0-ft-thick apron were placed 
on the shore and channel sides, respectively (Figure 71). A 6.0-sec, 
4.1-ft design wave was used. Estimated cost of construction was 
$245,000. 


No further repair or maintenance information has been found. 


112 


COUNTY 


eeu 


/ 


Stone Jetty 


Wim We bb S 


Vie BA 


\ 


NG 
SCALE _IN FEET > 
400 {e) 400 8 1200 
SHORE SIDE CHANNEL SIDE 
——5.0" 
— en 


eu 


ms 
an SAND @LAMKET 


REVETMENT/JETTY 
TYPICAL SECTION 


Tylers Beach, Virginia 


Figure 71. 


113 


ish ba mee EP) 


Re 
HONE ERR | 


we 
Ma 

: 
es 


Re 


fa 
} y" F :, Saas 


eis “ee 


Onsale mes pare ied 


E , 
icai¢ 
ee 
Lf ie ry, 
- Ss 
wer. 
o 
bie 
, e 
_ , ve ace 
‘ ‘ a Sys 
nas Lo ee Dea 
rt yeeeeve ages a Se n\n mre eka enh Ar 
‘ vi 
aS os P 
eS te ,