Skip to main content

Full text of "Monitoring results from the first Boston Harbor Navigation Improvement Project confined aquatic disposal cell"

See other formats


Monitoring Results from the 
First Boston Harbor Navigation 
Improvement Project Confined 
Aquatic Disposal Cell 


Disposal Area 
Monitoring System 


ra 
en oe 
AH 
x ANY ade 
oa eos 
at ar) 
” PA, 
Pes ‘ 
wn 
a i 4 
a 4 mp \% 
a tr, ' Ci 
oe : - 
ye vo 
we 
re re 
ie oo eet 
\ ang 
. AL i 
\ ee 
\ a 
XN cate 
% a? A> a 
YN wn 
\ 
\ Da 
a 


DA|M O §$ 


DISPOSAL AREA MONITORING SYSTEM 


Contribution 124 
January 1999 


US Army Corps 
of Engineerse 


. 

New England District ee? 
Det 
no- 124 


e @hSL4900 TOEO oO 


WU 


IOHM/181N 


Form roved 
REPORT DOCUMENTATION PAGE 


Public reporting concern for the collection of information is estimated to average | hour per persons inculding the time for reviewing 


instructions, searching existing data sources, gathering and measuring data needed and correcting and reviewing the collection of 
information. Send comments regarding this burden estimate or any other aspect of this collection of information including suggestions 
for reducing this burden to Washington Beadgt arters Services, Directorate for Information Observations and Records, 1216 Jefferson 
Davis Highway, Suite 1204, Arlington VA 22202-4302 and to the Office of Management and Support. 


1. AGENCY USE ONLY (LEAVE BLANK) 2. REPORT DATE 3. REPORT TYPE AND 
January 1999 DATES Final Report 


4. TITLE AND SUBTITLE Monitoring results from the first Boston Harbor Navigation Improvement Project _ 6. FUNDING NUMBERS 
confined aquatic disposal cell 
6. AUTHORS f 
PEGGY MYRE MURRAY 


7. PERFROMING ORGANIZATION NAME(S) AND ADDRESS(ES) 8. PERFORMING 
Science Applications International Corporation ORGANIZATION REPORT 
221 Third Street 
Newport, RI 02840 SAIC No. 443 


9. SRPONSORING/MONITORING AGENCY NAMES(S) AND ADDRESS(ES) 10. SPONSORING/ 
US Army Corps of Engineers-New England District MONITORING AGENCY 


696 Virginia Rd DAMOS Contribution 
Concord, MA 01742-2751 Number 124 


Available from : DAMOS PROGRAM MANAGER Regulatory Division, USACE- 
696 Virginia Rd 


11. SUPPLEMENTARY NOTES 


oncord MA 0 


12a. DISTRIBUTION/A VAIABILTY STATEMENT 12b. DISTRIBUTION CODE 
Approved for public release; distribution unlimited 


13. ABSTRACT 


As part of the overall Boston Harbor Navigation and Improvement Project (BHNIP), shipping berths 11 and 12 
at Conley Terminal in South Boston were deepened to -40 ft and -45 ft MLLW, respectively, in June-July 1997. In 
phasel of the BHNIP, fine-grained maintenance sediment, classified as unsuitable for open-disposal, was dredged and 
placed into an in-channel confined aquatic disposal (CAD) cell in Boston Harbor. The cell was extracted into the 
existing federal channel, below the BHNIP channel depth of -40 ft MLLW. Following placement of maintenance 
material into the cell, sufficient sand to cover the dredged material with a minimum of 3 ft capping layer was placed 
using split-hull scows. 


A monitoring survey was conducted by SAIC in October 1997 to assess the status of capped CAD cell. Survey 
methods included one day of vibracoring, and one day of acoustic surveying including bathymetry, subbottom, and 
side-scan sonar. Results of the survey indicated that most of the CAD cell was covered with a highly variable 
thickness of sand, while the southern end had little to no cap material. This distribution was consistent with the 
positioning of the split-hull scows used to dispose the sand. Sand disposal was permitted during the outgoing 
(southerly) tidal cycle. Prior to the initiation of the project, preliminary modeling of sand transport due to Boston 
Harbor tidal currents predicted that sand would be transported to the south, so no barge was placed directly over the 
southern end of the cell. The results suggested that the sand remained in the convective state during placement, so that 
all the cap material was placed directly below each positioned barge. 


The monitoring results also suggested that postcap operations designed to level the sand served to enhance 
mixing of the cap and underlying dredged material, and resulted in uneven sand coverage. A final videosled survey 
was conducted by C.R. Environmental in December 1997. These data confirmed the presence of a thick layer of sand 
covered with tunicates and other organisms in most of the cell, and the flat, fine-grained uncapped mud surface to the 
south. Overall, the maintenance material was successfully placed in the cell, and capped with sand in all locations 
where capping barges were located. The results of monitoring of Phase I provided guidance for operational and 
monitoring modifications for Phase II of the BHNIP in 1998-99. 


14. SUBECT TERMS 15.NUMBER OF PAGES 
pAWA\ 


Boston Harbor, South Boston, capping, confined aquatic disposal (CAD), videosled survey re = 


17. SECURITY CLASSIFICATION OF REPORT 18. SECURITY CLASSIFICATION }19. SECURITY CLASSIFICATION  20.LIMITATION OF 
UNCLASSIFIED OF THIS PAGE OF ABSTRACT ABSTRACT 


T , = ot i 
i . pesatihs in a ‘ ' i 
! } ihe { Ta Oa i Dd Ure 
par oceans eae crime -: 
} aa NED ews haus Pah eas, We tal y 
te Ws Leake ND pe Kn beidrg tian #9 Becht Bab 
bedi omaw a yuitid Lai She sneha LP ts ea ser 
‘ - seu ak aie - + ae eS: ve ijl ty 5  BhAREE 
Pel Slip snc RZ 


ee ee Lists: edule \eacestaaiedaen eam naenee 
ap at tA Weiss Peay Ad ie ry ee pies Ld ee 
j a ‘ ae en tee ae. 


fergie ht «sles oh ras “se mite seen 


aster Sheet 
aa 


nae tr ti vip te eoHhna pees 


Rigs ON ee At Le of SPE eae CTR 


i 
b ce oe cH OS cc afr os mpacrnanereen ip aroeryrnaminne -_ semitone 


ates ee 
TSR OUT ASE 


0 ape argo cme aeitengre eal 
ras) AY: dl 4 
re) he SA STe) oat 


apini det 


ay oe x 


oT: stares tt 


rad part atta 
doa , i ERE Peper bey tae (Shee incite in A pie Aes Sy Hid co. cainn Aaa $ AEN ot aa 
' , : E a 2 me} ke y ; 
: ; | SPE AR ER oes SLRS 


, j i 
a en noe 2 sik ancy cain. tf Auge Ara tral anihon et a Naat ee nr Siniichaied etka’ renal eaten St BRE Se NONENS RPR NR Rat 8 SS ARMIN 


. erie Tot 40); ‘ivi & Ff 45 5 £ Oy ; bipipeye Cae ey ba fiz inwey 
, " £ : 
} " mt ; VY EVN aT 
ip ti Ox PTR rise itt 
£1) kot} ; } thing fi Esha 
i ia boat hive hernia? 
rae 
a cas Ali ET) Php Leper es vee] 
: 
he at 


} Ve PF 
: fa a ™,, 
iy y v 
| j ay 
vinden ha 
( wy} 
4 y 
rv Sa) pT CMOS eG 
{ e <0 ae 
{ ned Sa t. 
{ TE? a yioepnes 
‘2 ) DLE Baneee AF ee 
t ‘ i Mile i 
1. J e * 5 aalis 9 
| 
b Léa TA, 
te 
» " ‘ m4 ’ 
\ 
foal Ne ; oe 
fae 2: 
. ¥ AR 
t 
, ‘ ik f 
nat 
; 
1 
i 
a 
5 
} \ " i : U 
ee er ae ym ee Se a ke ate ai Cay? sl Re ee he a a De I ee are Latha 
oxi CEA BEEN AE AEE ; ‘ 
4 "J x ay { 
: ey * te ‘ I say) 
Ot) ae ee ee OS ke, ‘4 ad y al s 
tatters c Aad iz 12 hee Dt at rh hice wae Hee) 


ws Ra serio one het re a ad aren AN ete jee SNe ie 
Z 4 > + N “yy “) 
owns ea ry z “ii SPREE TPA OR was the porn 
ie ny yp j 
Seah opeideons Ah in iy reetaane ” : nat ee ah am Londo ding wi me Rpt MY eld obi ete penne Sees 


4 


Monitoring Results from the First Boston Harbor Navigation 
Improvement Project Confined 
Aquatic Disposal Cell 


CONTRIBUTION #124 


January 1999 


Report No. 
SAIC 443 


Submitted to: 
Regulatory Branch 
New England District 
U.S. Army Corps of Engineers 
696 Virginia Road 
Concord, MA 01742-2751 


Prepared by: 
Peggy Myre Murray 


Submitted by: 
Science Applications International Corporation 
Admiral's Gate 
221 Third Street 
Newport, RI 02840 
(401) 847-4210 


US Army Corps 
of Engineerss 


New England District 


? eller anenEenRnCrE TIES 


acer here aE pote oath ay anit 


Jn 


iq  aodisie " 


j fe i 


bait? Pe 


esse rin isk ait ape ike uae ce ROM Aa a Pe rnp San erase ony A edb aseONY 
. y ee he 4 eae 7: 


sates er } 


raed beiwtts Fe a 


TABLE OF CONTENTS 


Page 

IETS OR LA BIEE S22 Wk Piece te ccees coc Eee Aetna eA OL ae Ree aes Se ke MRR RS iV 
NETS TMORGEIGUIRES ccrncencnecucecemecenbeiicse econ se cueus une nu neoee auciant Se eRe RRSER Eien eac era cree Vv 
EE © WINE. SWIMINIAIRN Greene aincsecs cle cnc toes aa cnoanee sas soe ne nen Seb resect tecie as Vi 
EO sUIN RO IDC CIION 6 hice etcetera or tai RENO ceed eter. loulncticte ae ics 1 
1.1 The Boston Harbor Navigation and Improvement Project ...................... 1 

iQ backeround tothe Conley erminalsbrojectan ase teree eee eee eee eee 4 

2 Excavation ofthe;CAD.Gelle ii. uc eRe EOE ona cer 4 
ip2eDeDredgediMaterial)Disposali@perationsies-) eee ee eee eee eee eee eee 4 

1263). Capping Operations. 7y.c secs agai seseeensasdads aces Meee nee Etec ee 7 

130 “CAD Celli Monitoring Surveys aes coer so esec te os tee es sceueeee see reiareasee 7 

PRO @SURVENOME HOD Sic @ seen A: Aen etnitee en ae een ISR IN dances WM eh Me eras banat 9 
Dn ANaVIGatlOM ee. ha.8 ae seasoieaned soadonees aolsetinsrana ts oor eacmes mae mesma se ase ince 9 

DEIN NA DTACOLE; SUIVEW Race se ane ec reeralh Uaya ere ele he hae te tA vera Oe eee cree y) 

DLA Corne Operations: esria an. Sales sat cei ee eteep tear cen ee ne seeeaerers 9 

2) a Nibracore) Collectionsandy Erocessinger ee seeee eee eee eee ee eee eee eee 10 

Desp VGNCOUSHC: SUEVEY* OpPeravlOnseisy sans tia ooy a aacomiseeeicne etre cee eee ane neers WW 

poe eobathymetuc Data Collectionand’Analiysisens--es eee eee eee eee acces 12 

2.3.2 Subbottom Data Collection and Analysis........................200eeee es 13 

Dasy oe SidescanyData CollectionrandyAnalySiseeeeeseeeeee eee eee eee eee eee 14 

DRA S NAGEOSIEUUSUEVEN a acide lice Hes sae eae raee cea cients et acne nen nets eer 14 

SM OMIRIE SUOIERS oss eecte canro ne ete carte aectui teeta law ome ternctene scree eval te ergy Weta ao fas aera 15 
BI ASVGl Sayer ol Soporte XAT [aenneouncehoannens dcoocsucdcemosesaspoodanadaaddhscomaosounete 15 

322.) BathymetricdResullts..2 72s uit ens teed clgeeer orient ist tauinl a arate eee eras 15 

Beso NaIbTACOLE RESUMES Aree aun eo tatare cere mane ae aed cc cenitete epee eictae isin eet rae 19 

35455 SUDDOLMLOMPRES ULES ie eee ict ati eit eaneinar alia isle act De alata ettacteleseeae Aaa 25) 

BHP VV TMCOMRESUMES He, catiatale aca lereisevouie eva wicvetata cia iieteval Leiber ge Sg eve pth tue tte en oe eral ak 29 

AN OERPDIS © UWSSTON eee. yeas teeter ice weal a ce stir peatarae Career reteset Seto reat ere othe a ra 32 
4.1 Topography and Texture of the Sediment Surface of the CAD Cell ......... 32 

AD Thicknessiofithe: Sand (Capiicsnrs vccekse eect Noe acts eer ee ieee ec ae ee oar 32 

4.3 Implications of Cap/Dredged Material Mixing ......................2eeeeee eee 313 

4.4 Consolidation of the Maintenance Material.....................eeeeeeeeeee ee eee 34 

4.5 Implications of Erosion from the Unsupported Cell Walls..................... 34 


TABLE OF CONTENTS (continued) 


Page 

5.0. SUMMARY AND RECOMMENDATIONS ree. secnecceee sees scis-ertaae ict te eee eeere 36 
Cyd eenme Wut roto oer HendrporiHecens daar Grondtondoanan ison osodsausosaacieccaqccuchsooness00. 26° 36 

5.11. Sidescan is .2 3 cschs cual ddedenecee da dctsneds idee ste Meee ee ee oe hee eee 36 

Sale Bath me tyne eee ee eet eeee eee eee acer eeecr ener crc eces eo eee ee eee eee 36 

Syne STi Ole) ot Vase cewennaccob nan seodosonabancesoudndodadscnso ch dobudascadaseoosscacoces 36 

5.1.4 Subbottomre gen. Qs eden ese ees ee, Se) eee Bi 

5 .1-5.. Video.........Inaiets Jamies 2. We bees ae ee ee ee ES eae oF 

5.2 _,..Recommendations.,-.<:o5..4. 149: 9h-0- oie ee Bee ee eaeee sok seis oeeeeeeee 37/ 

6.0, REFERENCES wisisscisicsis cod ntswsondlsiie ed douse sete «OES Ue Goer Mas. cnet ee eee Cee 41 


APPENDIX 


ili 


Table 1-1. 


Table 2-1. 


LIST OF TABLES 


Volumes of Material to be Dredged from Boston Harbor 


Core; DatarSumimanyyeseene ewes ssece rine acccteee a eeeee emer! 


S.0° Sut 


3 een 


{0 REPR 


Ty 


APPEN! 


ne 


Ie 


a 


a 


te 


in tr 


Suretivs my wane 


besa Urs 


Bee “Budlouease: aay 


an 


2 ataryonitcy 
AS .Qigeing..... 
La apo ypesy i 
AS Sidep 
Recaro ieogan Mars 


we ES. 


ee 


ain) 


Ay; 
i Epp ee ued 


Figure 1-1. 


Figure 1-2. 
Figure 1-3. 


Figure 1-4. 


Figure 3-1. 


Figure 3-2. 


Figure 3-3. 


Figure 3-4. 


Figure 3-5. 


Figure 3-6. 


Figure 3-7 
Figure 3-8 


Figure 3-9 


Figure 3-10 


LIST OF FIGURES 


Page 
Boston Harbor Navigation Improvement Project location of main 
Channels; toybeydned Sed ok seth Penn et sees. hs masz tea es igh bays Wires Ae e cee 2 
Proposed location of in-channel confined aquatic disposal cells .................... 3 
Location map of Phase 1 confined aquatic disposal cell........................00000 5) 
Bathymetry of cell area following excavation, prior to disposal 
@NiecksiMfarinesINAIDS Siete lacus Scene n uae alll ie listo oka DUAR err Uae iG reas 6 
SiCle-Cezin Gomeir Mis OH SUMRIES Oi Cal .noadadéascasade ss ccocsedabeccobaodsdooneasdes 16 
Bathymetry of cell area after completion of capping in a) July 
(Weeks Marine); and b) October 1997 (SAIC; NAD83) ......................02... 18 
3D view of postcap cell bathymetry in a) July (Weeks Marine); 
and b) October 1997 (SAIC); view towards the southern end of 
the Celle rast seren acne aetna cite oetich Rice eta nen te a ARAN DUNES ent TN SOUANERR MEER 20 
Postcap bathymetry of cell collected in October 1997 (NAD83) 
showing locations of cores and three cross Sections..............2...0.0eceee eee ees 21 
Bathymetric transects along north-south lanes 6 and 7 
(see Rigure SA yiman vated pie Mami ciiae Wall gS rs eee aah here rerun Mane 2D 
Bhotographs of selectedicores»;scale mycmiepe qe hee eee 24 
Subbottom'profile ofeane)Si(seeskisune3—4 in @ ye eee ee 26 
Subbottomiprohleior Wanew/a(See iounes—4) penance eee eee eee eee 28 
Video image of sand cap showing presence of tunicates and other 
SDI S es see Ge ce es san MN ai era we Meta A en tr aR OU RE a 30 
Videoumarerom Boston’Blue Clay icelliwallpeennss eee eee ee eee Sil 


” 


Le 8 


rien vi potaaul meee aabasach sayntt 


pentesence ten RMD latogeth oheips bacitans tensor ; 

qial fe. as pris 16 sabisignns yah. eoris thay 3, ona 

caveore ROGA. CHG) TOE! wa ee (eat wanes BY. rs 
tgnrrehh sisi Gol (8 ah vattigdiad Greeomine! 10. wey, ae. 

‘8 bart Wienived 212 abarwe weary )(OLAGY ORE edo (2 tie 

play alee «Pla garee enter aa ~ Hi war 
CSG HY VRET textoto nt hitoelien Yon To stoerneititod facet 
aie AION e039 sets bak 2o7G0, to: Aa ooF guirond:- 

a bine @ ome! fiveaatfart qncis ciyeina sbaonmeiad ene 

are Peers maar ct bejdiens tities tana CE Sanaa ae 
te 0 site ioe betesies To aggergoiodt 

Reeed, . hm G SRT oan), ooh ay Sait q tromodda® ou 
: ) (b-Beanigr daa) T one to all nrg rristed 
iho bins 2hraokeLt To sonmanag paive cule tee hake te ograa ooh: al 


 PAAVNTAG TAT) 


aR aly, 


ee ON 


EXECUTIVE SUMMARY 


As part of the overall Boston Harbor Navigation and Improvement Project 
(BHNIP), shipping berths 11 and 12 at Conley Terminal in South Boston were deepened to 
MLLW -40 and -45, respectively, in June-July 1997. In phase 1 of the BHNIP, fine- 
grained maintenance sediment, classified as unsuitable for open ocean-disposal, was 
dredged and placed into an in-channel confined aquatic disposal (CAD) cell in Boston 
Harbor. The cell was excavated into the existing federal channel, below the BHNIP 
channel depth of -40 ft MLLW. Following placement of maintenance material into the 
cell, sufficient sand to cover the dredged material with a minimum of a 3 ft capping layer 
was placed using split-hull scows. 


A monitoring survey was conducted by SAIC in October 1997 to assess the status of 
capped CAD cell. Survey methods included one day of vibracoring, and one day of 
acoustic surveying including bathymetry, subbottom, and side-scan sonar. Results of the 
survey indicated that most of the CAD cell was covered with a highly variable thickness of 
sand, while the southern end had little to no cap material. This distribution was consistent 
with the positioning of the split-hull scows used to dispose the sand. Sand disposal was 
permitted during the outgoing (southerly) tidal cycle. Prior to the initiation of the project, 
preliminary modeling of sand transport due to Boston Harbor tidal currents predicted that 
sand would be transported to the south, so no barge was placed directly over the southern 
end of the cell. The results suggested that the sand remained in the convective state during 
placement, so that all the cap material was placed directly below each positioned barge. 


The monitoring results also suggested that postcap operations designed to level the 
sand served to enhance mixing of the cap and underlying dredged material, and resulted in 
uneven sand coverage. A final videosled survey was conducted by C. R. Environmental in 
December 1997. These data confirmed the presence of a thick layer of sand covered with 
tunicates and other organisms in most of the cell, and the flat, fine-grained uncapped mud 
surface to the south. Overall, the maintenance material was successfully placed in the cell, 
and capped with sand in all locations where capping barges were located. The results of 
monitoring of Phase I provided guidance for operational and monitoring modifications for 
Phase 2 of the BHNIP in 1998-99. 


VI 


a mp 


cpa 


fostord 1p shanna iameaian odeatan es 
“08 boaaqosb =9w aye’ el rt dard eee tt at fine TE 


Toy gic fe Es sto cutsulntin 8 iw tat og ie 


40 milinta oH) 224234 oF 5 FORE pine am othe we 
to yah 10 ae gotugerdiv toy 
ails to ea PRE inege-abie ben pacer 
pe 0 22 joueen siclebay ‘Uityit & aii? hetavea 2 iowites : 
oiaiwios ‘28  diodgudlie=th euty ieteeten tne at aS 
eee abet ) bag? beaks ont sz0neih oF Sea 
Asapore valt Lie i aaa NOP yor ielons inkl ne 
eet) hevoiboi aura lebih roniaH werep dd OF oh 


% 


 nisdiee Sf Vo Wes betes! 
_ Bat, aint avi? shaven sl ab b 
aati baaghise iin walt 


2 bee i 


iti pone 3 Deliv ae 
p ra oyH® be poate 


aif ral ay Dein apiniraqe Ga oeg 


rig 


"ive Desrorisd 
bura oe Ropu | 
‘a Sale ii Shi 
% Anan ts 
(Gk BAe 


1.0 INTRODUCTION 
1.1. The Boston Harbor Navigation and Improvement Project 


The Boston Harbor Navigation and Improvement Project (BHNIP) involves 
deepening of the main ship channel (in the Inner Confluence and the mouth of the 
Reserved Channel), and three tributary channels (Mystic River, Chelsea Creek, and 
Reserved Channel) in Boston Harbor (Figure 1-1). In addition to the channels, several 
terminals and berth areas will also be dredged, for a total of 2.1 million yd* of material 
(Table 1-1). All of the channels will be deepened to -40 ft MLLW, except for Chelsea 
Channel, which will be dredged to -38 ft MLLW. BHNIP is a joint project between the 
US Army Corps of Engineers, New England District (NAE) and the local sponsor, the 
Massachusetts Port Authority (Massport). The first phase of the project, Conley Terminal, 
was conducted in the summer of 1997. 


Following extensive environmental review, the disposal options for both suitable 
and unsuitable material were described in the Final Environmental Impact 
Statement/Report (FEIS/R; NAE and Massport 1995). The plan included disposing the 
unsuitable material in approximately 50 in-channel confined aquatic disposal (CAD) cells, 
approximately 1.3 million yds’ of clean material will be dredged to create the cells 
averaging 20 feet deep, dredged below the federal navigation channels in the Mystic River, 
Chelsea River, and the Inner Confluence (Figure 1-2; NAE and Massport 1995; Demos 
1997). Because of concerns over the environmental impact of such a large-scale project, 
the state of Massachusetts negotiated for intensive environmental monitoring under the 
auspices of the CWA 401 Water Quality Certificate (WQC; Babb-Brott 1997). The WQC, 
granted by the Massachusetts Department of Environmental Protection, included the 
stipulation that the unsuitable material must be dredged using an environmental (closed) 
clamshell bucket, and capped by at least 3 ft of clean, granular material. One of the goals 
of the WQC was to monitor the short and long-term integrity of the capped CAD cells, and 
included review of all monitoring data by a state-sponsored Independent Observer (IO) for 
the Coastal Zone Management Agency (CZM; ENSR, Acton, MA was selected as IO). 
Survey results presented in this paper are only part of the extensive monitoring data 
collected for the Conley Terminal project (ENSR 1997a,b; Section 1.2). 


Concerns were raised by the BHNIP Technical Advisory Committee (TAC) prior to 
capping that the density difference between the fine-grained maintenance sediment and the 
coarse-grained sand cap would result in displacement of the cap, and that cap coverage 
would be difficult to verify using bathymetric methods alone (ENSR 1997b). Verification 
monitoring of the cell, in addition to the required monitoring by the WQC, was initiated in 
the summer-fall of 1997. The survey data presented in this report were collected in order 
to address these TAC concerns (Section 1.3). 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


"(S661 Modssepy pue 
AVN Woy) pesporp aq 0} sjouuRYyS urew jo UOnRIO] JoAlo1g JUSMIIAOIA WY WONESTARN Jogie}] uo}sog *T-[ oansiy 


8661 eunr 


oalolg jUsWUeAOIdLU] UOYOBWON S BUeioe : we 000r anna 0 
SLSSNYODsSOY\ JOCIOH UOJsog : : ee es : / Gee 
solysiq Pu_|GUA MeN Bi cea 
sigaul6uz Jo sdiog Auuy sn 


MIW_.8€- Oj Usdeaq 


MI Ov- of usdesq [_] 


leuuDYd se 


e6piig Eee = WSShyg / UlgoL 
$$ DeS|eYD, >< _ SIPIVOW 


WASH 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


Table 1-1 
Volumes of material to be dredged from Boston Harbor 


ieee meee) a sera ha ge pee 
(cy) (cy) 
Federal Channels 1,230,000 16,900 612,000 1,858,900 


In-channel Cells* 1,300,000 1,300,000 
Berths 95,000 181,500 276,500 


2,625,000 16,900 793,500 3,435,400 


*Assumes 54 cells as in Figure 1-2. 


Chelsea River 


re East Boston 
- 


Figure 1-2. Proposed location of in-channel confined 
aquatic disposal cells. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


1.2. Background to the Conley Terminal Project 


For the first phase of the BHNIP, an in-channel CAD cell was constructed for 
containment of unsuitable dredged material from shipping berths at Conley Container 
Terminal in South Boston by Weeks Marine (Camden, NJ). The dredged, fine-grained 
sediments were disposed into the CAD cell and then capped with sufficient sand to cover 
the deposit with a 3 ft thick layer of clean, granular material. Dredging and disposal 
operations are summarized in the following sections. 


‘ 


1.2.1 Excavation of the CAD Cell 


The CAD cell, located in the main ship channel south of the Inner Confluence near 
the East Boston shoreline (Figure 1-3), was designated Cell #2 in the FEIR/S for the 
BHNIP project. The cell was excavated below the maximum channel depth anticipated for 
Boston Harbor (40 ft MLLW) to an average total depth of 57.5 ft. First, the unsuitable 
maintenance material from the cell area was removed and stored in a barge. Cell 
excavation continued into Boston Blue Clay (BBC), a homogeneous, high strength greenish 
gray clay with low water content and low permeability (CDM 1991). Bathymetric surveys 
were conducted at all phases of cell construction and fill by the dredging contractor (Weeks 
Marine; ENSR 1997a). Bathymetric data were provided from a survey conducted by 
Weeks Marine following the dredging of the cell on 29 June 1997, and processed for 
graphical purposes by SAIC (Figure 1-4). Results showed an irregular topography, with 
depths of the cell floor that varied from minimum depths along the edges and in the north 
central part (54-56 ft), to maximum depths in the SW corner (62-64 ft). The approximate 
dimensions of the CAD cell were 500 ft long (north-south) by 200 ft wide (east-west). 


1.2.2 Dredged Material Disposal Operations 


Following the completion of the cell, the unsuitable maintenance material from both 
the surface of the cell and from Conley terminal was placed in the cell from 29 June to 
5 July 1997. Six gravity cores were collected throughout the cell by the NAE on 9 July 
1997. The recovered cores ranged from 3.3 - 4.5 ft, and results showed that the majority 
of the cores consisted of dark gray to black silt with a consistent sand component (13- 
32%), and were relatively watery (moisture content 80-160%). The bottom 3-10 in of 
each core consisted of gray clay (approximately 95% silt/clay) with low moisture content 
(approximately 40%), consistent with the basement BBC. 


Four bathymetric surveys were conducted after disposal of the unsuitable material (6, 7, 
8, and 14 July). Results from the first postdisposal bathymetry survey (6 July) showed a 
relatively uniform bottom within the cell with an average depth of 48.5 ft, resulting in an 
average dredged material thickness of 9 ft (NAE 1997). These results indicated that the 
material was relatively fluid and settled evenly over the cell floor. By the third survey (8 July), 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


Tobin Bridge 


500 ft 


Figure 1-3. Location map of Phase 1 confined aquatic disposal cell. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


N 


(MII ‘) U 
v9 


cg 


09 


8S 


9S 


vs 


cs 


9e70 LL 


(ESQ VN) [esodsip [eLa}eur 0} JOU ‘WOMBARSXS BUIMOTIOJ VOIR [99 JO AnomApeg  p-[ amsyy 


OvvO LL 
zl 


da bZ- 


IL 


8rr0' LL I 


(MAW ‘Y) wded 


Gc 0¢ St Ol GS 


}daq 


cele cv = gg 09 GS 0S Sh Ov SE OF 
OOevO'lZ-  O00Fv0'LZ- 


00Sv0 LZ 


L-p8le-Zp 
oe 
-88le Zp 


06Le'zr 


-C6LE CV 
 v6LE CV 


,96LE cH 


-008E cr 


(16 eunr GZ) Aening AjewAujeg euljeseg 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


the material had apparently consolidated approximately 2 ft. One week later (14 July), the 
range of depths in the cell was still relatively narrow (approximately 47.5 - 50 ft), but the 
deposit showed an average depth of approximately 49.5 ft, indicating an overall consolidation 
of approximately 1 ft over a period of one week. 


1.2.3 Capping Operations 


Capping operations were conducted from 14 July to 25 July 1997. Sand was slowly 
placed in the cell using a split-hull scow that was cracked open to slow the rate of material 
deposition. Disposal operations were conducted only during the outgoing tidal cycle. The 
scow was positioned using differential GPS (DGPS) in eight locations over the cell for a 
total volume of 14,800 yd’ (Appendix; ENSR 1997a; NAE 1997). The sand was obtained 
from Ossippee Aggregate. Grain size ranges of the sand were reported as dominated by 
coarse sand (59%), with smaller fractions of gravel (15%), and fine-medium sand (23%; 
grain size classifications from Wentworth 1922). 


A bathymetric survey was conducted after seven loads of material were placed with 
the scow oriented in north-south positions around the cell (Appendix). The bathymetric data 
showed a large mound in the center of the cell. Modeling conducted prior to capping using 
tidal current data predicted that the sand would spread towards the south (down current) 
during sand disposal. The preliminary bathymetric data showing a flat, well defined 
sediment surface was interpreted as indicating that the sand coverage in the southern end was 
well distributed (resulting from settling from the southerly tidal current), but the northern 
end of the cell was insufficiently covered. To rectify this, the contractor first unsuccessfully 
used a sweep bar to even the coverage, and then used a clamshell bucket to redistribute the 
material. Three 80-ft wide cuts were dredged from the central portion of the cell, and the 
material was placed in the northern end of the cell. Following this operation, a final barge 
of sand was placed in the cell; this scow was positioned along an east-west orientation in the 
northern section of the cell for the final cap disposal event. Weeks Marine conducted a final 
postcap bathymetric survey at the end of the project on 25 July 1997. 


1.3. CAD Cell Monitoring Survey 


Following completion of the cell, NAE and Massport were planning on accelerating 
part of the monitoring required by the Water Quality Certificate. Coincidentally, samples 
collected as part of a separate research project suggested that part of the cell contained 
insufficient cap material (Shull and Fitzgerald 1997). Using this information and 
recommendations of the technical advisory committee (TAC), NAE planned and 
implemented an acoustic and coring survey as part of the Water Quality Certificate 
monitoring to assess the success of capping of the first CAD cell, and to provide a resource 
for operational and monitoring modifications for application to the remainder of the 
BHNIP. In addition to the acoustic and coring survey, a follow-up video survey was 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


conducted by C. R. Environmental that confirmed some of the monitoring observations and 
provided visual evidence of the surface of the CAD cell. 


The acoustic and coring survey was planned and implemented to assess the success 
of capping for two objectives of equal importance: 


e to verify coverage of the first CAD cell and locate areas potentially requiring additional 
cap material; 

e to provide a resource for operational and monitoring modifications for application to 
the remainder of the BHNIP. 


The results of the monitoring survey presented here indicated that the majority of the 
CAD cell was capped with a highly variable thickness of sand, but that the southern end had 
little or no cap material. Postcap operations designed to level the sand cap appeared to have 
resulted in highly uneven sand coverage, and potentially served to enhance mixing of the cap 
and underlying dredged material. The acoustic data suggested that unsupported cell walls had 
become less steep, and provided evidence that consolidated blocks of material had fallen from 
the walls and settled on top of the dredged/cap material. Finally, the sediment placed in the 
cell (maintenance material and cap) had continued to consolidate, resulting in a topography 
that grossly mimicked the topography of the cell floor. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


2.0 SURVEY METHODS 
2.1 Navigation 


Vessel positioning and data integration were achieved with SAIC’s Portable 
Integrated Navigation Survey System (PINSS) using a Magnavox 4200 GPS receiver. One 
to 5-m DGPS accuracy was achieved to the GPS signals by applying corrections that were 
acquired from the U.S. Coast Guard differential beacon located at Portsmouth, NH, using 
a frequency of 288 kHz. During field operations, PINSS provided the navigator and vessel 
operator with range and bearing to selected targets (1.e., beginning and end of survey 
lines), signal quality, time of day, and selected data from environmental sensors including 
the fathometer, subbottom towfish, and side-scan sonar. Core station and survey lane 
positioning are discussed under the different survey operation descriptions below. 


2.2  Vibracore Survey 
2.2.1 Coring Operations 


Target locations for the cores were selected in order to meet the goals of the 
monitoring survey. The primary goal was to collect cores in potential areas of concern as 
suggested by results of several surface sediment samples collected in the area of the cell 
(Shull and FitzGerald 1997), including the southern end and the edges of the cell. In 
addition, bathymetric data collected during the various phases of the project were used to 
identify areas of potentially thinner cap. Therefore, the cores were collected beginning 
from the southern end of the cell, and moving to the central and northern end of the cell as 
the day progressed. 


Long cores were collected with the goal of penetrating to the basement of the cell, 
which consisted of Boston Blue Clay (BBC). With penetration into the BBC, a complete 
stratigraphy (cap/dredged material/BBC) could be identified. The complete stratigraphy 
was essential to determine if cap material had displaced dredged material during 
operations. The final goal of core collection was to collect material to be used for 
estimates of speed of sound in the layers of sediment detected by the subbottom data. 


The sediment vibracoring survey was conducted on 9 October 1997. Cores were 
collected using a two-vessel operation. PINSS navigation software and the GPS antenna 
was configured on a workboat supplied by Boston Line and Service Co., Boston, MA. 
Cores were obtained using a crane off of a 40 ft barge that was lashed to the workboat, and 
anchored in a 2-point configuration. Actual core locations were calculated as a distance 
and offset between the GPS antenna and the coring wireline. 


An Aqua Surveys Inc. (ASI) electric motor vibracorer was used to acquire sediment 
core samples. The corer was deployed off of the barge using the crane, and lowered to the 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


10 


seafloor for vibracore collection. Two types of liners were used, flexible plastic liners that 
were processed during the survey, and hard lexane liners (internal diameter of 3.5 in) that 
were transported to a shore-based core processing facility (Section 2.2.2). Replicate cores 
(one with a soft liner, one with a hard liner) were collected at each station. A variety of 
core catchers and nose cones were used throughout the coring day to maximize sediment 
recovery. In addition to personnel from SAIC, ASI, and Boston Line and Services, two 
Massachusetts Institute of Technology (MIT) SeaGrant Program students were on-board, as 
well as the independent observer (IO, ENSR) for the Massachusetts CZM. 


2.2.2 Vibracore Collection and Processing 


Sediment cores were acquired at a total of seven stations (Table 2-1). Two 
replicates were collected at each station from CAD-1 through CAD-5. Replicate A from 
each was collected in a flexible liner and processed on-board, and replicate B was collected 
in a hard liner and relocated to a shore-based core processing facility. The final two core 
locations, CAD-6 and CAD-7, were located in areas of thicker sand as suggested by the 
several feet of sand coating the recovered barrel. Recovery of 6A was low and a loss of 
material was indicated, so two soft liner cores were collected at this station (CAD-6A, 6B). 
Two cores became stuck in the sediment, so that no core was recovered at CAD-6C and 
CAD-7A. 


Immediately following retrieval of the vibracore at each station, the flexible core 
liners were placed in a core cradle that was pre-marked with a scale interval (cm), being 
careful to keep the core oriented (top to bottom). The soft liner was split open with a 
utility knife, and the core catcher was placed at the bottom of the core. Cores were 
described and photographs were collected every 20 cm of the core. Samples were 
collected by MIT student observers. 


The replicate cores collected with a hard liner were removed from the core barrel, 
carefully capped to prevent loss of sediment and/or water, marked with core numbers, and 
“top” and “bottom” labels on the core, and stored horizontally for transport back to 
laboratory coring facilities. Several cores were stored vertically for several hours because 
the top of the core consisted of very fluid mud, and it was difficult to determine the 
boundary of the sediment/water interface. After settling, these cores were re-cut at what 
was determined to be the interface. 


Cores were transported to the coring facilities at the Graduate School of 
Oceanography, University of Rhode Island in Narragansett, RI. They were stored 
horizontally in a core refrigerator for 4-7 days prior to processing. Cores liners were split 
longitudinally using the GSO’s core splitter which uses two razors to score the outside of 
the liner. The caps were cut using a utility knife, and then a piano wire was used to split 
the core into two longitudinal halves. One half was described, and eight samples were 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


I] 


Table 2-1 


Core Data Summary 
Core Total Liner Latitude Longitude Top 


Name Length (cm) Type (cm) 
42.37904 -71.04436 


42.37902 -71.04442 


42.37893 -71.04449 


42.37895 -71.04448 


42.37863 -71.04383 
42.37869 -71.04395 
42.37863 -71.04408 


42.37869 -71.04408 
42.37927 -71.04391 


42.37925 -71.04400 


42.37956 -71.04406 


42.37958 -71.04385 


hard 42.37960 -71.04379 Core not recovered. 
long core 42.37958 -71.04407 Core not recovered. 


DM = Black silty clay or clayey silt, industrial smell, assumed to be dredged material. 


Sand = Brown medium to coarse sand, assumed to be sand cap. 
Mixed = Black medium to coarse sand with silt component, assumed to be mix of above. 
BBC = Boston Blue Clay. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


12 


collected for potential future analysis of grain size. The other half was photographed and 
archived in a refrigerated coring facility for potential future evaluation. 


2.3 Acoustic Survey Operations 


Survey operations were conducted aboard the survey vessel Cyprinodon (CR 
Environmental) on 10 October 1997. Those involved in the survey included SAIC, the IO, 
one MIT student, and two pilots from CR Environmental. The PINSS navigation system 
was used for all navigation. Survey lanes were designed using the estimated locations for 
the four corners of the cell (ENSR 1997a). Survey lanes for bathymetry (Section 2.3.1) 
and subbottom (Section 2.3.2) were planned using the PINSS survey planning module to 
cover the area of the cell and one survey lane outside in all four directions. PINSS 
computed towfish position for the subbottom and side-scan sonar fish using a cable layback 
calculation and provided this position to the data collection system. Side-scan sonar 
operations were conducted following the bathymetry and subbottom surveys on the same 
day (Section 2.3.3). 


2.3.1 Bathymetric Data Collection and Analysis 


Depth soundings were collected with an Odom DF3200 Echotrac® survey 
echosounder using a 208 kHz transducer with a 3° beam angle. The Odom simultaneously 
displayed water depth data on a chart recorder and transferred the digital sounding data to 
the PINSS. The echosounder collected 6-8 soundings per second and transmitted an 
average value to the PINSS at a rate of one sounding per second. Depth soundings were 
collected along pre-configured survey lanes with 15 meter spacing in both E-W (14 lanes) 
and N-S (8 lanes) orientations. 


A Seabird Electronics, Inc. Model SBE 19-01 conductivity-temperature-depth 
(CTD) profiler was used to acquire a vertical profile of sound velocity in the water column 
during the day. These data were used to correct the bathymetry data for speed of sound 
during post-processing. 


Using SAIC’s Hydrographic Data Analysis System (HDAS), bathymetric soundings 
were edited for outliers and corrected for sound velocity, transducer draft, and tidal 
variation. Tidal data from the Boston Harbor tide station (station #8443970 located near 
the Northern Avenue bridge) were obtained from the NOAA Ocean and Lakes Levels 
Division (OLLD) web-server (http://www.olld.nos.noaa.gov). Following the application 
of all correctors, the depth soundings were spatially averaged to produce a grid of cells. 
The gridded bathymetric data were used to produce the various topographic maps included 
in this report. 


All graphics have been plotted in NAD83 latitude/longitude coordinates. Depth 
values are relative to Mean Low Water (MLW) in order to compare with data provided by 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


13 


Weeks Marine. Water depths are indicated with specific contour intervals noted on the 
figures. Both contour plots and three-dimensional relief plots were produced using Golden 
Software’s Surfer® program; a vertical exaggeration has been added to the 3D plots shaded 
relief in order to highlight small topographic gradients. 


2.3.2 Subbottom Data Collection and Analysis 


High resolution subbottom profile data were acquired with an Edgetech X-Star™ 
Model 216S Full Spectrum Digital Subbottom Profiler. Subbottom profile data were 
collected simultaneously with bathymetry, and therefore along the same survey lanes 
(Section 2.3.1). Subbottom seismic profiling is a standard technique for determining the 
presence of sediment layers below the sediment/water interface. The X-star system emits a 
swept-frequency pulse; the frequency of the transmitted pulse changes linearly with time, 
and is therefore called a chirp system. The depth of penetration and the degree of 
resolution is dependent on the frequency and pulse width of the seismic signal, and the 
characteristics of the penetrated material. 


The narrow beam (13°) transducers of the X-Star system, mounted in a towfish, 
were lowered using the winch aboard the survey vessel Cyprinodon, and trailed the vessel 
by approximately 15 m. The X-Star system generated a frequency-modulated pulse that 
was swept over an acoustic range of 2 to 10 kHz during the subbottom survey. The pulse 
rate was set to 6 pulses per second for optimum performance of the output devices. At 6 
pulses per second, traveling at an average vessel speed of 4-5 knots, a subbottom 
measurement was acquired every 34-43 cm along the vessel track. The return signals were 
transmitted via a data cable through an analog to digital (A/D) signal converter to an on- 
board Sun Sparc II Workstation for data display and archive. Data were stored on Exabyte 
tapes, and continuous profile data were printed on an Alden thermal printer. 


Penetration of sound in sediment is both a function of system frequency and the 
impedance contrast between the water column and sediment. Acoustic impedance, the 
product of velocity and density of sound in a layer, is also affected by differences in 
surface roughness, porosity, and grain size, among other factors (Hamilton 1970; LeBlanc 
et al. 1992). In general, sound penetrates further into fine-grained sediment because the 
impedance of high-water content silt and clay is closer to that of the water column. The 
ability to detect subbottom layers is similarly dependent on the acoustic impedance contrast 
between sediment layers. Subbottom has been used to accurately map the lateral and 
vertical coverage of a sand cap over dredged material because of the contrast between the 
sand cap and underlying fine-grained dredged material (e.g., Murray et al. 1994a). 


Subbottom layers were not digitized due to the difficulty in identifying continuous 
reflectors below the surface of the dredged material. The thermal paper printouts were 
scanned and several representative sections are included in this report. Although depths 
are shown in the figures, these are not reliable for estimating actual layer thicknesses or 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


14 


water depth. First, the depths are estimated using 1500 m/s as the speed of sound; the 
speed of sound will be higher in sand and the well-consolidated, homogeneous BBC 
(approximately 1700 m/s; Hamilton 1971). In addition, one lane was digitized to compare 
the subbottom depths with bathymetry, and the scale printed on the subbottom cross section 
was found to be inaccurate. 


2.3.3 Sidescan Data Collection and Analysis 


A Marine Sonics PC Scan side-scan sonar system was used for side-scan sonar data 
collection. This system is a single frequency (300 kHz) system that collects digital data 
directly to a PC-compatible computer. Bottom coverage was 100% for each pass. Several 
N-S passes were made with the cell on one channel, and the best image was processed 
using Adobe Photoshop® to enhance the visual resolution and add annotations. The image 
was not geo-registered, so that the aspect ratio of the cell (width vs. length) has been 
compressed in the vertical (N - S) direction because of survey vessel speed. 


2.4 Videosled Survey 


On 3 December 1997, CR Environmental, Inc. (CR) performed a towed video sled 
survey at the CAD in Boston Harbor to demonstrate the effectiveness of using high 
resolution underwater video in detecting the coverage of the sand cap. The CR 
Underwater Video Sled is equipped with a high resolution Sony Hi8 video camera, and two 
250 watt Deep Sea Power lights with variable light output. The system has a 100 meter 
cable, portable monitor and VCR, and isolated power for shock protection. 


The operations were performed from CR Environmental’s 32-foot survey vessel 
Cyprinodon equipped with a hydraulic winch, A-frame and a large enclosed pilot house for 
survey equipment. A Northstar DGPS and the Coastal Oceanographics’ HY PACK 
navigation software package were utilized to provide the boundaries of the confined 
disposal cell and a pre-programmed set of tracklines. The layback of the video sled to the 
navigation antennae was estimated to be approximately 50 ft. By examining the real-time 
video display, the vessel captain adjusted the towing speed and the pay out of the tow cable 
to achieve the best towing angle and bottom coverage. Two north-south transects were 
made through the disposal cell. Operations were performed at slack low tide and water 
visibility was estimated as 5 to 10 ft. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


15 


3.0 RESULTS 


Results from the monitoring surveys are summarized in this section. First, the 
surface topography and texture of the cell was measured using side-scan sonar (Section 
3.1) and bathymetry (Section 3.2). The video data were useful in corroborating the 
surface sediment topography and recolonization, and are incorporated throughout the 
presentation of results. Next, the information gathered that documented layer thicknesses 
within the cell, including core (Section 3.3) and subbottom (Section 3.4) results, is 
presented. 


3.1 Side-scan Sonar Results 


The side-scan sonar data over the cell area showed distinct acoustic regions of the 
cell (Figure 3-1). The southern end of the cell consisted of a uniform low reflectance area 
interpreted as a flat surface. Strong backscatter from the central and northern portions of 
the cell indicated a harder bottom, and a rough, uneven topography. Throughout the 
central portion of the cell, clamshell bucket markings were noted clearly, with dark 
shadows indicating strong changes in topography that we termed artificial “sand waves” 
for further discussion. Two of the three dredge cuts (NAE 1997), aligned east-west, 
showed individual ridges caused by clamshell bucket passes. The third most northern cut 
was partially obscured because of the sand that was disposed in the northern part of the cell 
after dredging (Section 1.2). Spud marks from the dredge were noted along the northern 
edge. 


Although the eastern edge of the pit was in shadow, there was a bright spot in the 
lower southeast corner indicating a topographic feature, consistent with bathymetric results 
(Section 3.2). This hard acoustic return (dark crescent) suggested that it was present above 
the ambient sediments to rise above the edge shadow, and hard enough for a strong 
acoustic return. Further interpretation of this feature is discussed below. 


The final distinctive feature of the side-scan sonar results was the scalloped edges of 
the cell. The shape of the cell walls still appeared to reflect much of the original clamshell 
markings from the excavation. Although sequential bathymetric surveys indicated some 
changes in the cell wall orientation, the sidescan results indicated that the BBC was firm 
enough to retain much of the original dredged topography. 


3.2 Bathymetric Results 


Weeks Marine provided two bathymetric datasets for evaluation of the survey data, 
including the survey conducted after the excavation of the cell prior to any disposal 
(predisposal survey; 29 June 1997), and the final postcap survey conducted at the end of 
the project (25 July 1997). The surveys were conducted using different survey parameters: 
the predisposal survey was conducted over a large area with east-west lanes, at 50 ft lane 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


pate 


_ Striations — 
~~) Se & < 


SS 


i ‘Sand Cap SS 


ie 2 se 


Figure 3-1. Side-scan sonar image of surface of cell. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


17 


spacing (Figure 1-4). The postcap survey was conducted at higher spatial resolution (25 ft 
lane spacing), but over a smaller area. The October bathymetric survey collected by SAIC 
was conducted using a 15 m lane spacing (approximately 45 ft), and over both east-west 
and north-south lanes. Because of the different survey parameters, calculating differences 
in depth by the normal procedure of subtracting equal grids over replicate areas was not 
reliable, so therefore, qualitative differences between the surveys are discussed below. In 
addition, comparing the depths collected around the cell (that presumably did not change) 
showed variation in depth of +2 ft among all of the surveys. This variability is due to 
different survey parameters, different vessels (with potentially different depths of the 
transducer), and potential error due to sea state. These errors would be much reduced, and 
allow for electronic survey comparison, if the surveys were conducted using exact replicate 
survey parameters and equipment. All three surveys have been corrected to MLW for 
comparison purposes. 


The predisposal baseline bathymetric survey showed ambient water depths ranging 
from 5 to 40 ft in the area around where the cell was excavated (Figure 1-4). Water 
depths in the cell itself prior to disposal ranged from 56-64 ft MLW. The cell walls were 
fairly irregular, showing scalloping along the edges remnant from the clamshell 
excavation. The deepest part of the cell was in the southwestern corner, and there were 
several topographically higher areas along the edges and in the center of the cell. 


The postcap survey conducted after completion of the project (Figure 3-2a) showed 
steep, almost vertical, western and eastern cell walls (lanes were not extended to the 
southern and northern ends of the cell). Depths ranged between 46-50 ft, with the 
shallowest depths in the center of the cell consistent with the areas of dredge-induced sand 
waves shown by the side-scan sonar data. The southern end of the cell was relatively flat 
(49-50 ft). The average thicknesses of dredged and cap material, therefore, was 
approximately 10 ft, with a range of thicknesses over the variable topography of the cell 
floor of approximately 6-14 ft. 


The survey conducted in October by SAIC resulted in somewhat less steep cell 
walls, and a more irregular topography on the floor of the cell (Figure 3-2b). Overall, the 
bottom of the cell appeared to increase in depth by 1-4 ft (i.e., the bottom of the cell was 
deeper) over most of the cell during the period between the July and October postcap 
surveys. Some areas north and south of the sandy peaks from the final postdisposal survey 
appeared to remain relatively constant between the two surveys (49-51 ft, blue areas). 
Considering the approximate 1-2 ft of error between the two surveys, the maximum 
consolidation that could be confidently estimated was at least 2 ft in the far southwestern 
corner of the cell and in the center of the cell below the thick sandy peaks. 

Conservatively, this resulted in an overall consolidation of 10-20% since the final postcap 
survey, concentrated in the dredged material as sand is relatively incompressible. 
Including the consolidation prior to capping, the total consolidation of the dredged material 
ranged from 20-40% during the four months past the initial capping. This value was 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


18 


SIOIOIN 


OOS Oe Sian O 
— UL S| 


(IW ‘¥) uded 
€G 


LS 


6V 


LV 


SV 


‘][99 Oy} JO pus UIOYINOS SY} SpIeMO} MTA 
<“(QIWS) L66L 1990190 (q pue ‘(outreyy Sy) Ayn (e ut Butddes Jo uonsyduros 1sye vare ]j29 Jo AnowAyeg "7-€ DANS 


(J9qG0190 OL) AewAujeg deoj}sod 


OvrO'LL bro LL 
- ! | ZOE ty 


-b8le cy 


-98LE Ch 


| -88Ze Cr 


|-O6LE Cr 


|-C6LE Cr 


|-V6LE cy 


|-96LE cr 


|-86LE Cr 


| -O08E cr 


(Aine gz) AewAuyeg deojsod 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


19 


within a reasonable range, as prior studies of dredged material have shown volume 
reductions of up to 50% for fine-grained materials attributable to consolidation (e.g., 
Poindexter-Rollings 1990). 


Viewing the data from a three dimensional perspective, the bathymetric data 
suggested that the slope of the cell walls had become less steep over the 10 weeks between 
surveys (Figure 3-3). Several areas appeared to show slumping of the wall itself (note far 
northwestern corner). Sequential side-scan sonar datasets collected during the disposal 
phase also suggested the outline of the cell wall changed through time (ENSR 1997a). 
Because the clamshell dredge that was used to create the cell left a sawtooth pattern along 
the cell walls, it is likely that the dredging process weakened parts of the wall and material 
sloughed or calved from the walls into the cell. Because Boston Blue Clay is relatively 
firm (e.g., CDM 1991), this process will likely not continue indefinitely, but until a stable 
slope for BBC material has been reached. The force of ship propellers along the piers may 
have also tended to weaken the unsupported walls, especially along the eastern wall of the 
cell. 


An anomalous topographic peak in the southeastern corner of the cell was noted 
several feet higher than was measured in the previous postcap survey in July (Figure 3-2). 
The location of the peak was consistent with the hard reflector seen in the side-scan sonar 
data, and was also seen in the subbottom results (Section 3.4). As discussed below, this 
deposit may be material that ended up overlying the uncapped dredged material, possibly a 
remnant of material fallen from the cell wall. 


Two N-S transects of raw depth soundings from the October survey (not gridded 
data) were extracted from the data to produce cross sections of bathymetry. Lanes 6 
(central cell) and 7 (eastern cell) were selected (Figure 3-4). The data were plotted to 
show the transition from the rough surface associated with the re-dredged sand cap to the 
smooth surface noted in side-scan sonar data. The results showed that the rough, uneven 
surface slopes down to the smooth surface, and the transition is approximately '4 of the 
distance from the southern end of the cell (Figure 3-5). Note that north and south are 
reversed between Lanes 6 and 7, and are plotted relative to the direction of the boat transit. 
The difference in topographic expression was investigated further with vibracore data. 


3.3. Vibracore Results 


A total of 12 cores at six stations were recovered, with core lengths ranging from 
45-241 cm (Table 2-1; Figure 3-4). In all, a total of 14 cores were attempted; two core 
liners became stuck (Cores CAD-6C, 7A; Figure 3-4). Cores collected from CAD-2A and 
2B appeared to be outside of the cell. The recovery of 72-105 cm of apparent dredged 
material, however, suggested that the cores were actually collected in the cell. One of the 
CAD-2 cores showed evidence of BBC on the top drive motor, indicating the core was 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


Postcap Bathymetry (25 July) 


Figure 3-3. 3D view of postcap cell bathymetry in a) July (Weeks Marine); and 
b) October 1997 (SAIC); view towards the southern end of the cell. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


42.3798| = \ ie 


42.3796— 


42.3794- 


42.3792- 


42.37905 


Depth (ft, MLV) 


42.3788- 


N 


42.3/86— 


42.3784— 


OE C‘( 
0 15 30 45 60 
Meters 


42.3782» i 3 : 
71.0448 -71.0444 ~—-71.0440 


I 
-71.0436 


Figure 3-4. Postcap bathymetry of cell collected in October 1997 (NAD83) showing locations of cores 
and three cross sections. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


bo 
bo 


Depth (ft MLW) 


Depth (ft MLW) 


Lane 6 


Relative Distance Along NS Lane 


South 


Relative Distance Along NS Lane 


Figure 3-5. Bathymetric transects along north-south lanes 6 and 7 (see Figure 3-4). Note that 


south is to the right on lane 6 and to the left on lane 7. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


collected very near the cell wall. Core recovery was greater in the cores collected 
throughout most of the day in the southern area and along the edges where there was little 
to no sand. The outside of the barrels of the last two cores which were not recovered 
because of stuck core barrels (6C and 7A) returned covered with sand, indicating that core 
recovery was hampered by thick sand intervals. 


There were three distinct units recovered in the cores. The most common was a 
black silty clay/clayey silt with a strong hydrocarbon odor. The texture ranged from very 
watery silt to highly consolidated, low water content firm clay. The second end member 
unit was a brown medium to coarse sand. Finally, several cores penetrated into a 
continuous interval of well consolidated BBC. When the core penetrated to refusal into the 
BBC material, we assumed the core had penetrated into the bottom of the cell. Comparing 
total dredged material thicknesses as recovered in the cores with bathymetry suggested that 
core recovery was hampered by loss or compaction of dredged material during the coring 
process. In Table 2-1, a fourth unit was described as “Mixed,” which was commonly 
medium to coarse sand with a component of black watery silt material, apparently from the 
dredged material unit. These units were described in order to estimate the potential 
magnitude of mixing between sand and dredged material. 


The dredged material unit was mottled with BBC in many cores, and in one core 
(CAD-SA), a solid 15 cm interval of BBC was recovered above the dredged material. The 
presence of BBC in the dredged material was consistent with reports from on-site 
inspectors. In addition to BBC, discrete sandier intervals were also noted in the dredged 
material. Data from cores collected prior to capping indicated that the dredged material 
consisted of up to 30% sand. For classification purposes, if the sand was a minor 
component of the dredged material, and disseminated throughout an interval, it was 
classified as dredged material. If the unit was dominated by medium-coarse sand but was 
infused with black watery silt material, it was classified as mixed. 


The two replicate cores collected at CAD-2, CAD-3, and CAD-4 recovered no 
sand, and all but CAD-4B were cored to refusal in BBC. These results indicated that no 
sand was placed in the southern section of the cell. Cores CAD-1A and 1B (Figure 3-6) 
were collected near the sand/mud boundary, and the results indicated that, near the sand 
cap boundary, limited mixing of sand and mud resulted in interleaved layers of sand and 
mud in these cores. The subbottom data also indicated that a wedge of sand near the edge 
of the sand cap may have been intermixed with the more fluid mud, hampering acoustic 
differentiation between these lithologies (Section 3.4). 


Cap thicknesses among the four cores where sand cap was clearly recovered at the 
top of the core (CAD-5A, 5B, 6A, and 6B) ranged from 20-28 cm. In cores CAD-5A and 
5B, the boundary between the sand cap and the underlying material was sharp and clearly 
delineated due to the presence of consolidated clays below the sand (Figure 3-6). The 
stratigraphy was uncertain at core CAD-6A (45 cm of recovery), because material was lost 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


oll 


"WD Ul O[BOS 


(4 


SaI09 payogas Jo sydeisoj0yg *9-¢ dANSIY 


g-Savd 8109 


Ot (4 i} fy 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


ZS) 


from the bottom of the core during operations. Recovery was better for core CAD-6B, 
where 20 cm of sand overlay 60 cm of mixed sand and dredged material, indicating a 
maximum recovered thickness of mixed material of almost 2 ft. 


The loss of 6C and 7A with evidence of thick sand so close to 6A and 6B indicated 
a high variability of sand thicknesses. Coring data indicated that mixing of sand and mud 
of up to 2 out of 3 ft occurred in areas of highly variable sand thickness. This mixing was 
probably enhanced, and possibly caused, by the force applied to the sand during postcap 
dredging operations. The consolidation state of the dredged material prior to capping, as 
shown in Cores CAD-5A and 5B, however, contributed to the presence of a clear 
sand/dredged material interface. The potential for increasing the consolidation state of the 
material prior to capping is discussed further in Section 4.0. 


3.4 Subbottom Results 


Two north-south lanes (Lanes 5 and 7) were selected to show the results of 
subbottom data (Figure 3-4). Lane 5, through the central portion of the cell, was 
representative of most of the subbottom results (Figure 3-7). The view is a cross section 
through the sediment, showing acoustic reflectors below the sediment/water interface 
where changes in lithology (acoustic impedance) occurred. As discussed in the Methods, 
the depth markings on the subbottom records do not accurately represent actual depths or 
thicknesses of the cell lithologies. 


Outside of the celi area, a series of horizontal reflectors throughout the harbor 
resulted from the natural geology of Boston Harbor. These sediments are a combination of 
BBC and glacial till (material left after a glacier melts) that were deposited in a nearshore 
marine environment that existed in the Boston area during an interglacial period about 
18,000 years ago (CDM 1991 and references therein). 


In the area of the cell, much of the subbottom acoustic information reflective of the 
natural geology of the material was lost, indicating no sound penetration to depths below 
the dredged and cap material. This result is not surprising, as prior acoustic work over 
dredged material has indicated that the acoustic signature of dredged material is distinct 
because of sound loss due to scattering and refraction, indicative of the heterogeneous 
nature of the deposit (Bokuniewicz et al. 1976; Schock et al. 1992; Murray et al. 1995). 
Two distinct acoustic regions were consistent with side-scan sonar data. In the southern 
area of the cell, the top reflector was a strong, smooth reflector indicating a smooth surface 
with little topography to scatter sound. The high amplitude of the reflector indicated either 
a harder surface (not borne out by coring data), or a very flat surface. Below this surface 
reflector, there was a very homogeneous layer as indicated by few internal reflectors, and 
there is a clear reflector from the base of the cell. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


CEs ay tee 


an aeustenen 


: SS : 
Soe cS ee ke Ze ma ast asd me 
4 P:20a5_2.00_10.00kHZ_FH SB-216{ P:20ms_2,00_10.00KB2_FN SB-216; P:20us_2.00_10.00KHZ_FR SB-216;P:20ms_2.00_10.00kHZ_FH S8-216} P:20us_2.00_10.00 

No.21162 Edgelech Wo.21412 EdgeTech No. 21662 Edgetech No.24912 Edgetech Wo.22162 Et 


Time: 14:32:27 Time:14:33:10 Time314:33:52 Tiae344394:35 Tine:14:95:47 
Date:410/10/1997 Ine Date:10/10/1997 Inc Date:10/10/1997 Ine Date:10/10/1997 In Date:10/10/1997 
Lat:42°22.826'H ; Lat:42°22.792'H ; Lat:42°22. 755‘ : Lat:42°22,718"N 4 Lats42°22.682'H 
Lon:71°2.644°9 Lon:71°2.650°H Lon:71°2.645'H Lon:74°2.646'9 Lon:71°2,645°8 


Course:150 = File: 1 Course:176 Fille: 1 Course:i81 File: 1 Course:189 File: 1 Course:165 = Fi 
Speed:2.7 Rec: 14800 © Speed:3.1 Rec: 15050  Speed:3.2 Rec: 15900 Speed:3.2 Rec: 15550  Speed:3.4 Rei 


Figure 3-7. | Subbottom profile of Lane 5 (see Figure 3-4). 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


In the central and northern portions of the cell, there was a marked change where 
the surface became highly irregular as the sound was reflected from the dredge marks 
shown by side-scan sonar data. Although the surface was very rough and uneven, the 
amplitude (strength) of the surface reflector was still strong, indicating a relatively hard 
surface consistent with sand. Below the surface, there was a series of discontinuous 
internal reflectors indicating a more heterogeneous deposit. Throughout this layer there 
were u-shaped reflectors that indicated refraction off of irregular deposits. The bottom of 
the cell was not a continuous reflector, most likely because most or all of the sound was 
lost in the sand-capped area. This is because at each acoustic boundary where sound was 
reflected or scattered within the sand deposit itself, less energy was left to continue 
downward penetration. 


The subbottom data indicated that approximately 25% of the cell was uncapped. 
There was a transition zone between the sand-capped area, and the fine-grained, uncapped 
area in the south along the N-S cross section (Figure 3-7). Comparing results from cores 
CAD-1A and 1B near the boundary and the bathymetric transects, it was apparent that 
there is an interval of transition where sand and mud was interleaved. The reflector along 
the peak of sand at the southern end of the capped section appeared to dip down towards 
the south, and was overlain by the mud in that transition. Because the subbottom cross 
section shown are uncorrected for speed of sound, the transition area between the capped 
and uncapped portion of the cell should not be interpreted as the actual stratigraphy, as the 
speed of sound in the sand (and BBC) is faster than in the fine-grained, heterogeneous 
dredged material. Without digitizing and correcting for speed of sound, the data can still 
be used to make qualitative conclusions about the interval between the capped and 
uncapped areas. Because of the weight of the thick sand layer in the central portion of the 
cell, in combination with the force applied to the central sand cap by the postcap dredging 
operation, the boundary was most likely characterized by deformed layers of sand and 
mud. 


The farthest eastern N-S lane (Figure 3-4), Lane 7, showed two interesting features 
(Figure 3-8). First, the cell bottom was a relatively continuous reflector below the cap and 
dredged material. This indicates that the material was more homogeneous, so that sound 
could penetrate further to the bottom of the cell. In the sand capped area, however, there 
was still no sand/mud reflector. Results from cores CAD-6B showed a thick mixed 
boundary between the sand and mud. These data suggested that the method of delineating 
cap thickness using subbottom will not be effective if there is a mixed zone that is greater 
than the depth resolution (wavelength) of the system. If there is a consistent sand/dredged 
material boundary (as in CAD-5A and 5B, Figure 3-6), subbottom will be more effective 
in determining cap thickness. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


SRS SER Ra et 


S 


he ie 
2484S. Giz FH SE-ZI6 P:2ms_ 2.8015. 6chz_ AE 00.15. 00k 
9.12852 


io 12082 : 
iets CRE tigers RI eter, SC Teeteey Oe 
Datett/afiss?««MatecMUNOSS57 |g, ‘ates/LONSST | ateSNVNUNSCT. 
ene penal ano: = orem ™ 
Lae toatt'2.606°8 (os1t"2.626°¥ Lense. 
Coarsexkt File: £ Course: Flext Tourse:¢ fie: i Ceorsesé Hiei 


Speed:3.¢ Reez SS Speedsi.4 Beer Sebe Speed:3.7 Sec: SSG Seeeds9.5 Res Boh 


Figure 3-8. | Subbottom profile of Lane 7 (see Figure 3-4). 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


Finally, the southern end of Lane 7 showed an apparent mound of material in the 
southeast corner of the cell overlying the uncapped mud with a clear acoustic reflector in 
between. This mound was consistent with the topographic peak that showed up in both the 
bathymetric and side-scan sonar data. This finding has important implications. The 
subbottom data were consistent with the bathymetric data that suggested material had 
settled on top of the dredged material after capping was completed. The fact that the 
material appeared to have settled on top of the uncapped material suggested that the 
bearing strength of the material had increased from July to October, and was potentially in 
an advanced state of consolidation that would increase the success of final capping of the 
material. Further geotechnical testing of the uncapped material by investigators at MIT 
will be continuing to address the issues of consolidation and bearing strength. 


3.5 Video Results 


The videosled survey that was conducted following the monitoring survey 
confirmed the acoustic data in two north-south transects. The video data provided clear 
evidence of sand in the north and central portions of the cell, showing tunicate-covered 
sand waves with dramatic topography (Figure 3-9). Audio data provided additional 
evidence as the sled was dragged and scraped through the sand. The transition from the 
sand cap to the uncapped dredged material was apparent primarily from the additional 
resuspended material associated with the videosled movement through the far southern end 
of the cell, but also from the change in sound. In general, water clarity was good 
throughout the cell, contrasting with the suspended sediment present in the ambient Boston 
Harbor sediments above the edge of the cell. During the second pass of the sled, the 
tracks from the first pass were noted in both the sand and mud areas, indicating a relatively 
consolidated surface of the dredged material. 


In addition to the surface coverage of sand and mud, the video captured images of 
ex situ material deposited on top of the dredged/cap material deposit, including entrapped 
debris and blocks of high-reflectance BBC (Figure 3-9). The blocks of BBC probably 
were remnant from material loosened from the cell walls, similar to the evidence provided 
by the acoustic data. The presence of debris indicated that material had become entrapped 
below the ambient current of Boston Harbor and settled on top of the cap. Inferences of 
the physical environment also could be drawn from the benthic community (tunicates, 
lobsters, etc.) that inhabited the cell at the time of the video survey. Tunicates, especially, 
tend to attach to hard bottoms (associated with ship fouling), and are filter feeders. The 
presence of tunicates on the sand cap indicated that the sand provided sufficiently hard 
substrate, within a fairly quiescent environment. Finally, video data collected along the 
cell walls confirmed that the steep walls were scalloped, primarily from the dredging 
process (Figure 3-10). The BBC walls also had begun to be colonized by a variety of 
burrowing organisms. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


30 


Boston Blue Clay 


Piece of Brick 


Crab Tunicates 


Debris 


Figure 3-9. Video image of sand cap showing presence of 
tunicates and other debris. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


31 


Boston Blue Clay;* 
Base of Cell Wall 


Shrimp Holes 


Hydroids 


Shrimp Holes 


Figure 3-10. Video image of Boston Blue Clay cell wall. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


4.0 DISCUSSION 
4.1. Topography and Texture of the Sediment Surface of the CAD Cell 


The presence of two distinct acoustic regions was consistent among all of the data 
collected within the CAD cell. The acoustic data, in tandem with cores collected 
throughout the cell, indicated that the northern and central portions of the cell were 
covered with a coarse sand. Throughout the central portion of the cell, clamshell bucket 
markings were noted clearly in the sidescan data, resulting in the appearance of sand waves 
that confounded core recovery in the thicker layers of sand. The distribution of sand 
across the surface of the cell also was clearly delineated in subbottom data. In that area of 
the cell, the subbottom reflectors apparent in the ambient Boston Harbor sediments were 
dissipated, indicating no effective sound penetration to depths below the dredged and cap 
material. Below the surface of the central and northern portions of the cell, there was a 
marked change in subbottom penetration, where there was a series of discontinuous 
internal, u-shaped reflectors that indicated refraction from the heterogeneous sand wave 
deposit. Clear evidence of sand on the surface was supported by video data, that showed 
tunicate-covered sand waves with dramatic topography (Figure 3-9), as well as audio 
evidence as the sled was dragged and scraped through the sand. 


In the southern end of the cell, the acoustic and coring data indicated that no sand 
was present, as all of the cores recovered in the southern end (except CAD-4B) recovered 
dredged material to refusal in BBC. In the southern area of the cell, the sediment/water 
interface was a high amplitude reflector in the subbottom data caused by the flat, 
featureless fine-grained cell surface. Below this surface reflector, there was a very 
homogeneous layer as indicated by few internal reflectors, and the base of the cell was 
noted as a continuous subbottom reflector along the southern portion of the cell. In 
combination, these results indicated that no sand was placed in the southern section of the 
cell. 


The lack of sand in the southernmost area of the CAD cell was attributed to the 
placement of the split hull scows used for capping. Modeling conducted prior to capping 
using tidal current data predicted that the sand would spread towards the south (down 
current). Monitoring data suggested, however, that the majority of the sand, although 
released slowly from the barge, was released convectively so that the areal coverage was 
more limited than predicted. The distribution of barges over the cell indicated that no 
barge was ever placed directly over the southern end, resulting in a lack of sand in this 
area. 


4.2 Thickness of the Sand Cap 


The second major result of the monitoring survey was that the central and northern 
areas of the disposal cell were covered in sand, but the thickness was unevenly distributed. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


33 


Sand thickness appeared to be most variable in the area impacted by postcap dredging 
operation. As noted in the side-scan sonar data, clamshell bucket operations resulted in a 
topography similar to sand waves, so that the resulting cap thicknesses were highly 
variable. Sand cap thicknesses among the four cores where sand cap was clearly recovered 
at the top of the core (CAD-5A, 5B, 6A, and 6B) ranged from 20-80 cm of sand or mixed 
sand and mud (Table 2-1). The inability to collect cores at 6C and 7A with evidence of 
thick sand so close to 6A and 6B indicated a high variability of sand thickness. A mass 
balance approach was used to approximate the variable thicknesses of the deposit. 
Assuming that the total volume of sand was deposited over, conservatively, 75% of the 
cell, the average thickness would be 4 ft. The minimum cap thickness measured was 
approximately 1 ft (26 cm), so the range of cap thicknesses could vary from 1-7 ft. 


4.3 Implications of Cap/Dredged Material Mixing 


One of the lithological units recovered in the cores was described as mixed, which 
had the appearance of the sand cap (medium to coarse sand), but with a component of 
black watery silt material, apparently from the dredged material unit. Coring data 
indicated that mixing of sand and mud of up to 2 ft occurred in areas of highly variable 
sand thickness, indicating that mixing was enhanced, and possibly caused, by the force 
applied to the sand during the postcap dredging operations. 


The consolidation state of the dredged material prior to capping, as shown in cores 
where sand overlay more consolidated clay, contributed to the presence of a clear 
sand/dredged material interface (Figure 3-6). These data suggested that the more 
consolidated the dredged material was prior to capping, the less mixing occurred. 
Maximizing consolidation of the dredged material prior to capping, thereby increasing the 
bearing strength of the dredged material and reducing the interval over which sand and 
mud are mixed, therefore, has several advantages, including: 


e Increasing the protection of benthic organisms by maximizing the “effective 
cap” above the zone of advective flux of potentially contaminated pore waters 
into sand (e.g., Murray et al. 1994b); 

e Reducing the volume of sand that has to be placed to ensure 3 ft of coverage; 

e Maximizing the efficiency of the subbottom profiling technique to detect the 
cap/dredged material boundary, which has provided the widest spatial coverage 
of cap confirmation data to date; 


e Increasing the overall long-term stability of the deposit. 


The bathymetric results suggested that consolidation has continued throughout the 
cell, in both the sand-capped and uncapped areas. The critical parameter of consolidation 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


34 


was identified from the monitoring results; specifically, the time necessary to allow for 
self-weight consolidation of dredged material. 


4.4 Consolidation of the Maintenance Material 


The overall depth of the cell appeared to increase by 1-4 ft during the 10-week 
period between the bathymetric data collected immediately after capping in July 1997, and 
in October 1997. The sequential bathymetric data were used to calculate an overall 
consolidation of at least 2 ft in the far southwestern corner of the cell, and in the central 
cell below the sand wave deposits. Conservatively, this resulted in an overall consolidation 
of the dredged material from initial deposition to 10 weeks after capping of 20-40% . 
Previous data collected on dredged material consolidation indicated that this value is 
probably a minimum, considering volume reductions of up to 50% for fine-grained 
materials have been attributed to consolidation (e.g., Poindexter-Rollings 1990). More 
accurate estimates of the rate of consolidation within the CAD cells will be useful for the 
second phase of the BHNIP (Section 5.0). 


The acoustic data consistently indicated the presence of a large block of material in 
the southeast corner of the cell overlying the uncapped dredged material (Figure 3-8). 
Although no samples were collected from the area of this topographic anomaly, the most 
logical conclusion is that a large block of BBC fell from the cell wall and settled on top of 
the dredged material. Although this is highly conjectural, the inference can be drawn that 
the bearing strength of the uncapped material had increased by the October survey to 
support the overlying block of material. If this is the case, sometime during the 10-week 
period between the completion of the dredging project and the October monitoring survey, 
the material developed sufficient self-weight consolidation to optimize capping. 


4.5 Implications of Erosion from the Unsupported Cell Walls 


The side-scan sonar data from this report and from prior data collection efforts 
(ENSR 1997a), as well as the bathymetric and subbottom data, suggested strongly that the 
slopes of the unsupported cell walls have become less steep, and material has fallen from 
the walls into the pit. The video captured images of the surface of the cell showing blocks 
of BBC on top of the CAD cell cap (Figure 3-9). Because the clamshell dredging process 
that was used to create the cell walls left a sawtooth pattern along the cell walls, it is likely 
that the dredging process weakened parts of the wall resulting in sloughing or calving from 
the weakened walls. Video data collected in the cell confirmed that the steep walls are 
scalloped, potentially increasing the chance for erosion of the cell walls (Figure 3-10). 


Boston Blue Clay has a high strength and is relatively firm (CDM 1991), indicating 
that the erosional process will not continue indefinitely, and may be limited to areas that 
were weakened during the dredging process by the clamshell bucket. In addition, spud 
marks on the side-scan image were close to the edge of cell, potentially contributing to 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


35 


sloughing. Because the walls remained unsupported (unfilled cell) at the time of this 
survey, however, these erosion processes may continue, especially on the eastern side of 
the pit because of the impact of vessel propeller wash. 


For Phase 2 of the BHNIP, the cells will be filled up to ambient seafloor depth 
(channel depth), so that this result does not affect the dredging and monitoring plans. For 
the Phase 1 CAD cell, the interesting implication of the monitoring data is that material 
will continue to settle into the cell, from both weakened cell walls and entrapped sediment 
and debris. During Phase 2 surrounding areas will be deepened by 5 to 7 feet decreasing 
unsupported cell wall height. This suggests a sedimentation rate that is more rapid than the 
surrounding Boston Harbor seafloor, making the estimation of overall sand cap thickness 
more difficult to assess as time progresses. Ultimately, dependent upon the sedimentation 
rate and the rapidity of erosion of the remaining cell wall, the dredged material will be 
covered to ambient depth with sediment. This very thick layer of sediment, be it sand, 
BBC, or ambient fine-grained sediment, will provide ample containment for the dredged 
material placed at the bottom of the cell. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


5.0 


Sell 


5.1.2 


SUMMARY AND RECOMMENDATIONS 
Summary 
Sidescan 


e The southern end of the cell had low reflectance relative to the rest of cell, 
indicating a smooth cell bottom and homogenous grain size; 

e There was an acoustic bright spot in the southeast corner indicating a 
topographic peak lying above the shadow created by the edge of the pit; 

e The central portion of the cell showed a strong topographic signature from 
clamshell dredging, resulting in artificial sand waves throughout the center of 
the cell; 

e Rough texture of the surface of the northern end of the cell indicated sand cover, 
but was less disturbed than central section. 


Bathymetry 


e Consolidation of at least 1-2 ft in some areas, especially in the southwestern 
corner and in the center of the cell below the thickest sand layers, continued 
between the final postcap survey conducted in late July, and the postcap 
bathymetric survey conducted 10 weeks later in early October; 

e Total consolidation of the dredged material since the time of placement was 
estimated to be 20-40%; 

e Evidence for material falling from the unsupported cell walls included the 
irregular cell outline and flatter slope, as well as the anomalous topographic 
peak in the southeast corner; 

e The dredging process, as well as propeller action along the eastern side and 
spudding, likely weakened parts of the cell wall, enhancing the potential for 
material slumping; 


Coring 


e Cores indicated that the southern end of the cell was uncapped; 

e The artificial sand waves in the central portion of the cell resulted in widely 
varying sand thicknesses over short distances; 

e A sharp cap/dredged material boundary was present over consolidated dredged 
material; 

e The estimated range of thickness of the sand in the capped area was estimated to 
range from 1-7 ft; 

e Potential mixing of up to 2 ft of the cap into the dredged material in one core 
was probably enhanced by the postcap dredging operation, but may also be a 
result of underconsolidated dredged material prior to capping; 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


37 


e Loss or compaction of dredged material resulted in underestimated total unit 
thicknesses above BBC. 


5.1.4 Subbottom 


e In the southern area of the cell, a sharp seafloor reflector indicated a smooth 
surface with little topography to scatter sound; 

e In the central and northern portions of the cell, the surface was highly irregular 
and very rough, coincident with the sand cap and sand wave area; 

e Below the surface in the sand-capped area, a series of discontinuous internal 
reflectors indicated a more heterogeneous deposit, and most or all of the sound 
was lost in the upper portion of the deposit; 

e The data suggested that delineating cap thickness using the subbottom method 
will not be effective if there is a mixed zone that is greater than the resolution of 
the acoustic system; 

e New material from the cell wall appeared to have settled on top of the uncapped 
material, suggesting that the strength of the material has increased and is 
potentially in a state of consolidation sufficient to support even large sized cap 
materials with minimal mixing. 


5.1.5 Video 


e Video data confirmed the presence of thick sand waves in the central and 
northern parts of the cells, and the transition from the sand cap to the uncapped 
dredged material was apparent both in audio and video; 

e Further evidence of consolidation of the uncapped material was suggested by the 
presence of sled tracks noted during the second pass of the sled; 

e The video captured images of ex situ material deposited on top of the 
dredged/cap material deposit, including entrapped debris and BBC, indicating 
that material had become entrapped below the ambient current above the cell; 

e The presence of tunicates on the sand cap indicated that the sand provided 
sufficiently hard substrate, within a fairly quiescent environment; 

e The video data collected along the cell walls confirmed that the steep walls were 
scalloped, primarily from the dredging process. 


5.2 Recommendations 


Results from all of the environmental monitoring surveys were discussed among the 
project proponents and the BHNIP TAC. Recommendations to modify the requirements 
for dredging and disposal operations, and potential alterations to the environmental 
monitoring approach, were considered. The recommendations briefly described below 
were summarized from the October monitoring survey report (Murray 1997), and 
preliminary recommendations from the project proponents as summarized by the CZM 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


38 


Independent Observer (ENSR 1997b). The recommendations were designed around the 
primary concerns raised by the dataset, including lack of spatial coverage of sand, variable 
thicknesses of sand, and potential mixing between sand and dredged material. The 
recommendations are intended as practicable methods of improving the CAD capping 
process for Phase 2 of the BHNIP and other projects. 


e Operational Control During Capping 


The primary source of both uneven spatial coverage and variable cap thicknesses 
was the method of sand placement in the first CAD cell. For Phase 2, operations will be 
designed to improve placement of the material, as well as increase the ability to diffuse the 
sand while capping. In addition, physical disturbance of the sand cap after placement will 
be minimized. 


e Increase Bearing Capacity of Dredged Material Prior to Capping 


Increasing the consolidation time for the fine-grained maintenance sediments will 
increase the bearing capacity of the material, increasing the likelihood for a sharp 
cap/dredged material boundary. The Phase 1 monitoring studies provided no clear 
guidance for the time required for sufficient consolidation, as there was no hard evidence 
that the consolidation time for Phase 1 (9 days) was insufficient. The time allowed for 
consolidation partially will be governed by the potential risk of resuspension of this 
material. Future geotechnical studies will be conducted to address this issue for further 
projects. 


The most cost-effective method to increase bearing capacity is to allow more time 
for self-weight consolidation to take place. The subbottom data provided an estimate of 
the maximum time necessary for the dredged material to be able to support an overlying 
load, because of the apparent ability of the uncapped dredged material to support the mass 
of material at the southeast corner of the cell. The topographic peak appeared sometime 
between the last postcap survey in July and the October survey, providing a maximum 
waiting period of 10 weeks. The actual waiting period may be shorter (perhaps much 
shorter depending on when the block fell or could have been supported), and will also 
depend on the geotechnical character of the actual dredged material as it is placed. This 
waiting period will be established through careful monitoring of the first few cells. 


Another method to increase the bearing capacity of the dredged material is to reduce 
the water content of the material prior to disposal in the cell. Dewatering, however, is 
expensive and time-consuming. Use of the environmental clamshell bucket increased the 
water content of the material, ultimately decreasing the strength of the placed dredged 
material. The final potential method for increasing the bearing strength of the material 
prior to placement is to phase the capping process. By adding additional material to the 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


39 


top of the dredged material (additional dredged material, cap material, BBC), the strength 
of the material will increase and improve the ultimate success of final capping. 


e Confirming Cap Coverage and Thickness 


The basic methods used for this survey can be successful in determining cap spatial 
coverage and thickness in tandem with improved operational methods. Modifications to 
these procedures are summarized for the individual types of monitoring. 


Bathymetry. Bathymetry proved to be a useful tool to monitor overall consolidation of the 
project. The advantage of the Boston Harbor project is that the underlying BBC is 
relatively incompressible, so that any difference in height of the material can be attributed 
to consolidation of the dredged material itself. It is imperative, especially in small areas 
like the CAD cells, to replicate survey parameters so that electronic depth differencing 
between surveys can be conducted. Typically, consolidation will occur rapidly at first, and 
then slow and become more gradual (e.g., Poindexter Rollings 1990). At the point the 
consolidation curve begins to flatten is the optimum time to begin capping from a strength 
perspective. Bathymetry can be used as a tool during dredging, therefore, to allow 
qualitative analysis of the consolidation state of the material. 


Using bathymetry to estimate cap thickness is problematic, however, because of further 
consolidation of the dredged material after cap placement. Use of subbottom (below) will 
allow a more comprehensive and accurate acoustic assessment of cap thickness (Murray et 
al. 1994a). 


Coring. Coring has the advantage of actual, visual evidence of the state of the cap. It is 
limited, however, to measuring in only discrete points so that, with uneven coverage, it 
may provide an inaccurate picture of the overall cap. Coring can be used to evaluate the 
boundary between cap and dredged material, so that the ability of subbottom (below) to 
detect the overall coverage of the cap can be evaluated. Vibracores are required for this 
type of operation. 


Subbottom. As discussed above, if the material is sufficiently consolidated to minimize 
mixing between the sand and cap, subbottom is the most promising method to evaluate 
both the spatial coverage and overall thickness of a sand cap. It becomes less useful if the 
sand is unevenly placed so that sound is lost at the surface, and if the mixed interval 
exceeds the depth resolution of the subbottom frequencies. 


Sidescan. Sidescan data were essential in Phase 1 because of the unique topography of the 
sand waves. If the sand cap is uniformly placed throughout the cell area, sidescan will 
show the uniform deposit but will need groundtruth data (cores or video) to document the 
lithology. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


oe sete oan ec en ee ee ee ee 
int ee ESN IA Se ee a 


Video. The use of the videosled data proved useful to visually document the status of the 


cap. Because the area of the cells is small, video can provide relatively good coverage at a 
reasonable cost. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


4] 


6.0 REFERENCES 


Babb-Brott, D. 1997. “BHNIP: State permitting considerations for CAD disposal.” 
Conference Proceedings of Coastal Zone ’97, Vol. I., pp. 196-198. 


Bokuniewicz, H. G., J. Gebert, and R. B. Gordon. 1976. “Sediment mass balance of a 
large estuary, Long Island Sound.” Est. Coast. Mar. Sci., 4:523-536. 


CDM. 1991. “Environmental consequences of utilizing Boston Blue Clay in landfill 
closures. Central Artery/Tunnel Project, ROWARS Task Assignment #1.” 
Submitted to Massachusetts Dept. of Public Works, Camp Dresser & McKee, Inc., 
Boston, MA. 


Demos, C. J. 1997. “The federal environmental review process.” Conference Proceedings 
of Coastal Zone ’97, Vol. I., pp. 187-189. 


ENSR. 1997a. “Summary report of independent observations Phase 1 - Boston Harbor 
Navigation Improvement Project.” Prepared for Massachusetts Coastal Zone 
Management Agency, Executive Office of Environmental Affairs, Boston, MA. 
ENSR Document Number 4479-001-150, ENSR, Acton, MA. 


ENSR. 1997b. “Summary of capping investigations.” BHNIP Independent Observer 
Report I/O-9703. Prepared for Massachusetts Coastal Zone Management Agency, 
Executive Office of Environmental Affairs, Boston, MA. ENSR Document Number 
4479-001-120, ENSR, Acton, MA. 


Hamilton, E. L. 1970. “Reflection coefficients and bottom losses at normal incidence 
computed from Pacific sediment properties.” Geophysics, 35:995-1004. 


Hamilton, E. L. 1971. Prediction of in-situ acoustic and elastic properties of marine 
sediments. Geophysics, 36(2):266-284. 


LeBlanc, L. R., L. Mayer, M. Rufino, S. Schock, and J. King. 1992. “Marine sediment 
classification using the chirp sonar.” J. Acoust. Soc. Am., 91(1):107-115. 


Murray, P. M., M. B. Wiley, D. Pabst, and B. May. 1994a. “Subbottom profiling of a 
sand capped disposal mound.” Jn: McNair, E.C., Jr. (ed.), Proceedings of the 
Second International Conference on Dredging and Dredged Material Placement, 
Vol. I. Lake Buena Vista, FL, Nov. 13-16, 1994. Amer. Soc. Civ. Eng., New 
York, pp.1285-1294. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


42 


Murray, P. M., D. Carey, and T. J. Fredette. 1994b. “Chemical flux of pore water through 
sediment caps.” Jn: McNair, E.C., Jr. (ed.), Proceedings of the Second International 
Conference on Dredging and Dredged Material Placement, Vol. I. Lake Buena Vista, 
FL, Nov. 13-16, 1994. Amer. Soc. Civ. Eng., New York, pp.1008-1016. 


Murray, P. M., J.T. Morris, A. J. Silva, and T. J. Fredette. 1995. “Swept-frequency 
(chirp) subbottom analysis of a shallow-water dredged material deposit in Long 
Island Sound.” SAIC Report No. 342. Submitted to U.S. Army Corps of 
Engineers, New England Division, Waltham, MA. 


Murray, P. M. 1997. “Postcap monitoring of Boston Harbor Navigation Improvement 
Project (BHNIP) Phase 1: assessment of inner confluence CAD cell.” Submitted to: 
U.S. Army Corps of Engineers, New England District, Waltham, MA. SAIC 
Report No. 413, SAIC, Newport, RI. 


NAE (U.S. Army Corps of Engineers, New England Division [now District]) and 
Massport (Massachusetts Port Authority). 1995. “Boston Harbor, Massachusetts 
Navigation Improvement Project and Berth Dredging Project.” Final Environmental 
Impact Report and Final Environmental Impact Statement. Massachusetts Executive 
Office of Environmental Affairs, File Number 8695. 


NAE (U.S. Army Corps of Engineers, New England District). 1997. “Bathymetric survey 
results at disposal cell, Conley Terminal dredging project.” MPA Contract No. 
3.288D. Prepared for the Massachusetts Port Authority, Boston, MA. 


Pace, S. D., D. L. Dorson, and S. E. McDowell. 1998. “A surveillance system for 
dredged material disposal.” Submitted to Ports 98, Long Beach, CA, March 1998. 


Poindexter-Rollings, M. E. 1990. Methodology for Analysis of Subaqueous Sediment 
Mound. Technical Report D-90-2, U. S. Army Engineer Waterways Experiment 
Station, Vicksburg, MS 110pp. 


Schock, S. G., D. J. Kieth, D. L. Debruin, E. Dettmann, and G. Tracey. 1992. “Utilizing 
a chirp sonar to accurately characterize newly deposited material at the Calcasieu 
Ocean Dredged Material Disposal Site, Louisiana.” Proceedings, Oceans ’92, 
IEEE, 26-29 October 1992, Newport, RI. 


Shull, D. and FitzGerald, S. 1997. “Follow-up survey results of disposal cell 1 
(8/28/97).” Report prepared for Massachusetts Institute of Technology Sea Grant 


College Program. 


Wentworth, 1922. A scale of grade and class terms of clastic sediments. J. Geol., 3:377-390. 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


APPENDIX 


MONITORING RESULTS FROM THE FIRST BHNIP CONFINED AQUATIC DISPOSAL CELL 


ta ins 


Murray, My | 
eras ¢ ana? dats re BE or es edd Pade vd Wl 
Confenrnive on Dredging (aut Dred uct Material Placeamant,: mn 
FL, Nov. 15-16, 894, ‘Anter doe, i, ait de New Biwi 


Morsay, Poo Me 1 ‘Aorta Ail Sie, 
| (cttiepy) subblapitern unalveis of.6 ns ur 
island Sond," SAIC Refit Nigu3 3%, Sibmn aca Ae 
Fi ier, Poituy Eat gland yy iw wikia, Watthani, WHA. i bee 


coin Roson Har 
ATRAB RINT , iver eX "7 Fi oa 
. Aver tounch Diet 


blast he 


00+0 


puiddey bung sjuaju0gD 
DUP SMOIS JO UOHEIO7] 


OO+L 


00+¢e 


MOOS 
ul jeueyeyy de 
JO uoNeo07 “xoiddy 


OO0+Y 


(4G¢#) g dwndqy; | 
(yGZ#) 2 CWNC fae 
(4Sc#) 9 dung 
(49¢#) S dwn jm 
(ZSZ#) 7 CWNG peepee 
(2SZ#) € dwnq jaa 
(ySc#) ¢ dwNd [jay 


(ZSZ#) | GUNG fae 
Buidwing jo 18piC 


00+S 


nage ¢ 
ane 
> & 


’ 


iMjal J! 


wi 


———